AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
10 JUNE 2022 
Report by the Head of Ayrshire Roads Alliance
______________________________________________________________ 
SUBJECT: DEVELOPMENT CONTROL UPDATE - ROAD BONDS 
______________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this Report is to update the Joint Committee on the current
position regarding road bonds held by the Ayrshire Roads Alliance on behalf
of East Ayrshire and South Ayrshire Councils. 
RECOMMENDATIONS 
2. It is recommended that the Joint Committee: 
(i) Notes the position regarding road bonds currently held by the
Ayrshire Roads Alliance on behalf of East Ayrshire Council and
South Ayrshire Council;
(ii) Notes the outcome and actions from an internal audit of road
bonds;
(iii) Agrees that progress updates are provided to future meetings of
the Joint Committee on an annual basis;
(iv) Otherwise, notes the content of this report. 
BACKGROUND 
3. The Roads (Scotland) Act 1984 requires that, for any road not constructed by
a roads authority, the appropriate consent from the local roads authority is
obtained to undertake this work.  This is generally referred to as the Road
Construction Consent (RCC).  The Ayrshire Roads Alliance maintains a
register of all RCCs under the remit of the Ayrshire Roads Alliance. 
4. Where new roads are being constructed for housing the developers are
required to provide the roads authority with security to cover the cost of
constructing the roads should the developer default.  The provisions are set
out in the Security for Private Road Works (Scotland) Regulations 1985, as
amended.  This security may take the form of a cash deposit but it is generally
in the form of a road bond.  The security is retained by the Roads Authority
until completion of the consented works, although the value may be reduced
as the works progress. Road bonds are not required for local authority or
housing association developments.

Page 2

5. The Joint Committee, at its meeting on 23 May 2014, remitted the Head of
Roads to undertake a review of road bonds more than three years old and
report to a future meeting of the Joint Committee. An annual report is now
presented to the Joint Committee summarising the road bond position and
providing other updates on the development control process as required. 
CURRENT RESIDENTIAL ROAD BONDS 
6. A list of all RCCs and their associated road bonds for each Council area is
shown in Appendix 1.  As of 24 May 2022, ARA manages 24 road bonds with
a current value of £9,336,951.61 in East Ayrshire, and 30 road bonds with a
current value of £12,207,800 in South Ayrshire. 
7. Appendix 2 provides details of completed road bonds and road adoptions
since the previous report to Joint Committee on 4 June 2021, and Appendix 3
shows new bonds received since the previous report. 
8. The current review has found that the value of the road bonds held in
Appendix 1 is adequate to complete the outstanding road works on each
development site across both East Ayrshire and South Ayrshire for which
RCC has been issued. 
CONSTRUCTION TAKING PLACE WITHOUT RCC AND ROAD BONDS 
9.  There are no developments being constructed within East Ayrshire Council
without an RCC and Road Bond in place. 
OTHER DEVELOPMENT MATTERS  
North East Troon – Stewart Milne Homes 
10. An outstanding issue has been resolved at NE Troon development regarding
the roundabout junction at B746 Kilmarnock Rd/Lang Rd/Commonwealth Rd.
Funding has now been secured to remove the roundabout and install traffic
lights, work programmed to commence week beginning 4 July 2022. 
Corton, Ayr – Allanvale Residential 
11. Allanvale Residential have submitted a total of nine RCC applications, eight
for the Corton development in Ayr and one for Auchincruive. None of the nine
RCCs are listed in Appendix 1 as consent has yet to be issued. Six of the
Allanvale RCC applications have been reviewed by the ARA, with subsequent
requests for road bonds totalling £3.3 million and associated inspection fees
of £120,000 issued in June 2020, inspection fees have been received. In
accordance with ARA procedures, RCC will not be granted until the road
bonds are lodged with the Council. The remaining three RCC applications as
yet to be reviewed by the ARA involve a further £4.5 million in road bonds and
£175,000 in inspection fees, however these have yet to be requested. It
should be noted that no development is currently taking place associated with

Page 3

any of the nine RCC applications, and therefore there is no breach of the
regulations 
BONDS CALLED-IN 
12. No bonds have been required to be called in since the last report to
Committee. 
NON-RESIDENTIAL ROAD BONDS 
13. Roads authorities have a general power under section 96 of the Roads
(Scotland) Act 1984 to recover maintenance costs arising from damage
caused by excessively heavy, or other extraordinary, vehicles or traffic. The
type of development where this applies are Wind Farms or major
infrastructure projects. 
14. The current status of non-residential bonds and financial guarantees is set out
in the table below. In each case the bond value held has been assessed as
being sufficient to cover the cost of potential works arising from extraordinary
damage to roads infrastructure. 
15. Construction works in relation to the Afton Wind Farm have all been
completed with the exception of the replacement of a cattle grid on Afton
Road which ARA propose to undertake in the current financial year. In lieu of
payment of £30,000 to the Council to cover the cost of replacing the cattle grid
the existing Section 96 Bond has been cancelled. 
16. The Greenburn OCC is in its restoration phase and work on the reinstatement
of the U720 road and use of the haul road bridge as part of the realigned
public road is now complete and the road has been reopened to traffic.
Formal adoption of the new section of road and the bridge has still to be
concluded. 
Council
Area
Site Developer Agreement Bond Value
East Ayrshire Greenburn
Open Cast
Coal
Keir Mining Parent
Company
Guarantee
£1.200M
South
Ayrshire
Assel Valley
Wind Farm
Assel Valley
Wind Energy
Ltd
Section 96 of
Roads
Scotland Act
£0.107M 
INTERNAL AUDIT OF ROAD BOND PROCEDURES 
17. Previous reports to Committee advised on the outcome of Internal Audit of
Road Bonds and the actions taken by ARA to review and enhance monitoring
and management of road bond processes. A further internal audit of ARA’s
new processes was undertaken in early 2020 and the audit report received in
August 2020 provided “Sound assurance in most areas - key controls exist

Page 4

and are applied consistently and effectively in most areas. Non-compliance
has only been identified in low risk or medium risk areas”. The audit report
identified some remaining scope for improvement and set out a number of
recommendations. Following the audit a number of actions have been
undertaken to strengthen processes, including the addition of a further
overarching QA procedure setting out the key requirements in respect of
management and reporting of road bonds. The new procedure is included at
Appendix 4. 
POLICY/COMMUNITY PLAN IMPLICATIONS 
18. None. 
LEGAL IMPLICATIONS 
19. The work to manage RCCs and road bonds is carried out in accordance with
the Roads (Scotland) Act 1984 and its associated statutory instruments. 
HUMAN RESOURCES IMPLICATIONS 
20. The management of the development control function and continued review of
road bonds will be undertaken within existing staff resources. 
EQUALITY IMPACT IMPLICATIONS 
21. None 
FINANCIAL IMPLICATIONS 
22. The road bonds currently held by the Alliance on behalf of both East Ayrshire
Council and South Ayrshire Council are considered to be sufficient to
complete the outstanding roadworks on each development site for which RCC
has been issued.   
RISK IMPLICATIONS 
23. Inadequate road bond values expose the roads authority to a potential
financial shortfall if the roadworks have to be completed by them should the
developer default.  An RCC is valid for three years and the developer may ask
the roads authority for an extension if the site is incomplete after this period. 
The value of road bonds that are more than three years old will therefore
continue to be reviewed to determine their adequacy to complete the
outstanding works required to comply with the RCC. Where a shortfall is
identified the developer will be advised to increase the value of the road bond
held when an application is made for an extension to the RCC. 
TRANSFORMATION STRATEGY   
24. None

Page 5

BACKGROUND PAPERS
Development Control Update - Road Bonds - 23 May 2014
Development Control Update - Road Bonds - 21 August 2014
Development Control Update - Road Bonds - 6 November 2015
Development Control Update - Road Bonds - 17 February 2017
Development Control Update - Road Bonds - 16 February 2018
Development Control Update - Road Bonds - 25 April 2019
Non-Residential Road Bonds – 29 August 2019
Development Control Update - Road Bonds – 4 June 2021
LIST OF APPENDICES
Appendix 1 - Register of Road Bonds
Appendix 2 - Completed Road Bonds and Road Adoptions since August 2021
Appendix 3 - New Bonds received since August 2021
Appendix 4 – Procedure relating to the management and reporting of road bonds
and road construction consents.
For further information on this report, please contact Kevin Braidwood, Head of
Ayrshire Roads Alliance on 01563 503064.
Implementation Officer: Kevin Braidwood, Head of Ayrshire Roads Alliance on
01563 503064.

Page 6

Appendix 1 - Road Bonds Held at 24 May 2022
East Ayrshire
RCC Ref Developer Site Bond
Provider
Original Bond
Value
Current Bond
Value
Status
EAC/CC/02/007
EXT
KG Building and
Civil Eng Ltd
Manse Gardens,
Brewlands Street,
Galston
NHBC £110,270
(07/03/19)
£110,270 Site currently being developed. Extension to RCC
approved on 29/03/19 and bond value re-calculated and
increased. 
EAC/CC/08/013 McTaggart
Construction Ltd
Dunlop House, Dunlop MD
Insurance
Services Ltd
£353,682
(04/08/16)
£353,682 Site currently abandoned.
Awaiting new application from developer, Bond remains
unchanged at this time.
EAC/CC/14/009 Bellway Homes Fardalehill, Kilmarnock,
Phase 1
NHBC £952,194
(28/07/15)
£95,219
(21/05/21)
Site complete. Maintenance period commenced
21/05/21. Bond reduced to 10%
EAC/CC/15/006 Hemingsley Homes David Dale Avenue,
Stewarton, (Fisher’s
Grove) 
HCC £196,457
(24/03/16)
£40,000
(21/05/19)
Roadworks complete. Developer has to resolve
drainage issue with Scottish Water prior to commencing
maintenance period. £40K road bond retained
EAC/CC/16/003
Phase 1 
Persimmon Homes Dunlop Road, Stewarton,
Phase 1
NHBC £713,585
(19/08/16)
£356,793
(30/10/18)
Site currently being developed.
Bond reduced by 50%. Extension granted on 16/09/19
EAC/CC/16/003
Phase 2 
Persimmon Homes Dunlop Road, Stewarton,
Phase 2
NHBC £951,566
(19/08/16)
£95,156.56
(15/06/21)
Site currently being developed. Bond reduced to 10%
on 15/06/21. On maintenance period from 15/06/21
EAC/CC/16/003
Phase 3 
Persimmon Homes Dunlop Road, Stewarton,
Phase 3
NHBC £713,585
(12/02/18)
£356,792.62
(15/06/21)
Site currently being developed. Bond reduced to 50%
on 15/06/21
EAC/CC/16/003
Phase 4 
Persimmon Homes Dunlop Road, Stewarton,
Phase 4
NHBC £381,205
(07/08/19)
£38120.46
(15/06/21)
Site currently being developed. Bond reduced to 10%
on 15/06/21. On maintenance period from 15/06/21
EAC/CC/16/003
Phase 5
Persimmon Homes Dunlop Road, Stewarton,
Phase 5
NHBC £624,749
(07/08/19)
£312,374.48
(15/06/21)
Site currently being developed. Bond reduced to 50%
on 15/06/21
EAC/CC/16/004 Mooncatcher
Ltd/Campbell
Homes
Rigg Road, Cumnock,
Phase 1
Cash
Deposit
£193,844
(01/05/18)
£168,830
(04/11/19)
Site currently being developed. Remaining cash bond of
£168,830 from EAC/CC/16/004 covers outstanding
value of roadworks for Phases 1 – 4
EAC/CC/16/009 ARH Homes Ltd Riverside Gardens,
Cronberry
Cash
Deposit
£130,929
(14/06/16)
£66,860
(19/10/18)
Site currently abandoned. Bond reduced by 50%.
Developer to lodge new RCC application to replace
existing RCC. Existing cash bond will transfer to new
consent.
New site layout still to be approved through planning,
no change to RCC or bond status at 06/05/22.
EAC/CC/16/010 Ogilvie Homes Helen’s Terrace,
Annandale, Kilmarnock
NHBC £484,574
(23/06/17)
£4,845
(31/07/20)
Internal site roads completed by developer and roads
adopted. Helen’s Terrace footway remains unadopted
until after horsetail weeds have been eradicated. 10%
bond value retained until the work is completed.

Page 7

RCC Ref Developer Site Bond
Provider
Original Bond
Value
Current Bond
Value
Status
EAC/CC/17/002 Bellway Homes Fardalehill, Kilmarnock
Phase 2
NHBC £1,338,781
(26/04/18)
£133,878
(21/05/21)
Site complete. Maintenance period commenced
21/05/21. Bond reduced to 10%
EAC/CC/17/003
EXT PHASE 1 
Auberne Homes Former Holmhead
hospital site, Cumnock,
Phases 1
Acasta
European
£145,818.50
(08/12/17)
£145,818.50
(07/05/21) 
Site currently being developed. 
Bond total for phase 1 & 2 £291,637.
EAC/CC/17/003
EXT PHASE 2 
Auberne Homes Former Holmhead
hospital site, Cumnock,
Phases 2
Acasta
European
£145,818.50
(08/12/17)
£145,818.50
(07/05/21) 
Site currently being developed.
Bond total for phase 1 & 2 £291,637.
EAC/CC/17/006 Bellway Homes Fardalehill distributor
road, Kilmarnock, 
Phase 2
NHBC £511,934
(07/02/18)
£51,193
(21/05/21)
Maintenance period commenced 21/05/21. Bond
reduced to 10%
EAC/CC/17/007 Taylor Wimpey Altonhill, Kilmarnock, 
Phase 11
NHBC £933,558
(14/05/18)
£93,356
(14/03/22)
Site on maintenance period from 14/03/22, 
road bond reduced by 10%
EAC/CC/17/008 Barratt Homes Northcraigs, Kilmarnock,
Phase 1
NHBC £1,311,088
(29/05/19)
£655,543.94
(08/06/21) 
Site currently being developed
Bond reduced by 50% on 08/06/21
EAC/CC/18/003 Brae Homes Balgreen, Hollybush HCC £202,361
(27/08/19)
£20,236
(18/08/21)
Site completed and on maintenance period from
18/08/21, bond reduced to 10%.
EAC/CC/18/010 Mooncatcher/
Campbell Homes
Rigg Road, Cumnock, 
Phase 2
Cash
Deposit
£58,404
(01/05/18)
See status Site currently being developed. Remaining cash bond of
£168,830 from EAC/CC/16/004 covers outstanding
value of roadworks for Phases 1 – 4
EAC/CC/18/013 Valley Homes
(Scotland) Ltd
John Street, Catrine, 
Phase 1A
Cash
Deposit
£29,641
(26/11/19)
£29,641 Site currently being developed
EAC/CC/18/015
Phase 1
Auberne
Homes/Viga
Homes
Main Street, Auchinleck
(Phase 1)
Acasta
International
£55,498
(12/08/20)
£55,498 Site currently being developed.
Bond total for Phase 1 & 2 £110,996
EAC/CC/18/015
Phase 2
Auberne
Homes/Viga
Homes
Main Street, Auchinleck
(Phase 2)
Acasta
International
£55,498
(12/08/20)
£55,498 Site currently being developed.
Bond total for Phase 1 & 2 £110,996
EAC/CC/19/003 Campbell Homes Rigg Road, Cumnock, 
Phase 3
Cash
Deposit
£81,401
(01/05/18)
See status Site currently being developed. Remaining cash bond of
£168,830 from EAC/CC/16/004 covers outstanding
value of roadworks for Phases 1 – 4
EAC/CC/19/005 Campbell Homes Rigg Road, Cumnock, 
Phase 4
Cash
Deposit
£49,718
(01/05/18)
See status Site currently being developed. Remaining cash bond of
£168,830 from EAC/CC/16/004 covers outstanding
value of roadworks for Phases 1 – 4
EAC/CC/19/008 Barratt Homes West Former Kilmarnock
College, Holehouse Road,
Kilmarnock
NHBC £630,903
(15/11/19)
£ 315415.50
(25/10/21)
Site currently being developed
Bond reduced to 50% on 25/10/21
EAC/CC/19/009 Bellway Homes Ltd Fardalehill, Kilmarnock,
Phase 3
NHBC £1,018,084
(21/08/20)
£ 509041.91
(14/12/21)
Site currently being developed
Bond reduced to 50% on 14/12/21

Page 8

RCC Ref Developer Site Bond
Provider
Original Bond
Value
Current Bond
Value
Status
EAC/CC/19/013 Campbell Homes Rigg Road, Cumnock, 
Phase 5
Cash Deposit £65,114.84
(07/06/21)
See status Site currently being developed. 
LODGED AS CASH BOND 5,6&7 TOTAL £170,807.79
EAC/CC/20/002
Phase 1
Hayhill
Developments
Hillhead Road, Mauchline,
Phase 1
Cash Deposit £218,901.66
(15/07/20)
£218,901.66  Site currently being developed
Bond total for Phase 1,2 & 3 £656,705
EAC/CC/20/002
Phase 2
Hayhill
Developments
Hillhead Road, Mauchline,
Phase 2
Cash Deposit £218,901.66
(15/07/20)
£218,901.66  Site currently being developed
Bond total for Phase 1,2 & 3 £656,705
EAC/CC/20/002
Phase 3
Hayhill
Developments
Hillhead Road, Mauchline,
Phase 3
Cash Deposit £218,901.66
(15/07/20)
£218,901.66  Site currently being developed
Bond total for Phase 1,2 & 3 £656,705
EAC/20/004B Murdoch Properties Glebe Road, Galston.
Phase 2, North, Road 2.
(Adoptable)
Cash Deposit £44,215.84
(03/11/20)
£44,215.84  Site currently being developed 
EAC/CC/20/007  Avant Homes
(Scotland) 
Loudoun Street, Draffen,
Stewarton 
NHBC £2,125,456
(26/03/21)
£2,125,456 Site currently being developed
EAC/CC/20/006 Glencairn Estates One Recreation Road,
Cumnock
Cash
Deposit
£106,370.27
(07/06/21)
£106,370.27 Site currently being developed. 
EAC/CC/21/005 Campbell Homes Rigg Road, Cumnock, 
Phase 6
Cash Deposit £61,114.61
(07/06/21)
See status Site currently being developed. 
LODGED AS CASH BOND 5,6&7 TOTAL £170,807.79
EAC/CC/21/006 Campbell Homes Rigg Road, Cumnock, 
Phase 7
Cash Deposit £44,578.34
(07/06/21)
See status Site currently being developed. 
LODGED AS CASH BOND 5,6&7 TOTAL £170,807.79
EAC/CC/21/009 Campbell Homes Rigg Road, Cumnock, 
Phase 8
Cash Deposit £99,888.44
(09/03/22)
99,888.44 Site currently being developed. 
EAC/CC/21/011 J. Campbell, New
Cumnock
Muirkirk Road, Lugar AVIVA £108,370.21
(28/10/21)
108,370.21 Site currently being developed. 
EAC/CC/21/007 Miller Homes Ltd  Irvine Road, Kilmaurs NHBC £1,743,070.61
(10/08/21)
£1,743,070.61  Site currently being developed. 
South Ayrshire 
RCC Ref Developer Site Bond
Provider
Original Bond
Value
Current Bond
Value
Status
SAC/133/05/12 Stewart Milne NE Troon Phase 1, Troon NHBC £849,603.00 £424,801.00 Site complete – maintenance inspection to be
arranged
SAC/134/06/12  Taylor Wimpey N E Troon Distributor
Road, Phase 2A
NHBC £576,486.63 £576,486.00 Work ongoing

Page 9

RCC Ref Developer Site Bond
Provider
Original Bond
Value
Current Bond
Value
Status
SAC/135/07/12  Stewart Milne NE Troon Housing 1,
Troon
NHBC  £1,110,614.00  £555,307.00  Work complete – maintenance period cannot
commence until SAC/133/05/12 placed on
maintenance.
SAC/138/03/14  Bellway Homes
Ltd 
Kilmarnock Road,
Brassie
NHBC  £508,825.00  £254,412.00  Work complete – maintenance period cannot
commence until SAC/133/05/12 placed on
maintenance.
SAC/142/06/14  Mactaggart &
Mickel 
Greenan, Phase II, Ayr  NHBC £1,970,572.00  £985,286.00  Work ongoing
SAC/146/03/15  Stewart Milne/Mac
and Mic
Townend Brae Phase 1,
Symington
NHBC  £274,302.00  £27,430.00  Work complete – in maintenance period 
SAC/147/04/15  Bellway Homes
Ltd 
Kilmarnock Road, Phase
2, Troon
NHBC  £424,252.00  £212,126.00  Work complete – maintenance period cannot
commence until SAC/133/05/12 placed on
maintenance.
SAC/152/03/16 Stewart Milne
Homes
Townend Brae Phase 2,
Symington
NHBC £664,026.00  £66,402.00 Work complete – in maintenance period
SAC/158/01/17 Tom Bennet Culzean Road, Maybole  Cash
Deposit
£153,879.00  £15,388.00  Final joint inspection to be carried out prior to site
being adopted
SAC/159/02/17 Mactaggart &
Mickel
Townend Brae,
Symington Phase 3
NHBC £610,581.00 £61,058.00 Work complete – in maintenance period 
SAC/161/04/17 Taylor Wimpey N E Troon, Phase 3 NHBC £584,889.22 £584,889.00 Work ongoing
SAC/162/01/18 Stewart Milne N E Troon, Phase 4 NHBC £676,681.87 £338,640.00 Work ongoing
SAC/163/02/18 Mactaggart &
Mickel
Greenan, Ayr Phase 3 NHBC £67,181.00 £67,181.00 Work ongoing
SAC/166/05/18 Taylor Wimpey N E Troon Distributor
Road, Phase 2B
NHBC £576,486,63 £576,486.00 Work ongoing
SAC/167/06/18 Taylor Wimpey N E Troon Distributor
Road, Phase 2C
NHBC £576,486,63 £576,486.00 Work ongoing
SAC/168/07/18 Taylor Wimpey N E Troon, Phase 5 NHBC £346,121.63 £346,121.00 Work ongoing
SAC/170/01/19 Milestone
Developments
West Parish, Maybole Cash
Deposit
£10,933.00 £10,933.00 Work ongoing
SAC171/02/19 Cala Homes Greenan Phase 6 NHBC £963,940.94 £963,940.00 Work ongoing
SAC/175/06/19 Westpoint Homes Seafield Hospital NHBC £577,447.62 £577,447.00 Work ongoing
SAC/176/01/20 Taylor Wimpey N E Troon phase 6 NHBC £329,369.00 £329,369.00 Work ongoing
SAC/177/02/20 Persimmon
Homes
Tarbolton Road, Monkton
Phase 1
NHBC £509,382.85 £509,382.00 Work ongoing
SAC/178/03/20 Persimmon
Homes
Tarbolton Road, Monkton
phase 2
NHBC £707,634.85 £707,634.00 Work ongoing
SAC//187/12/20 Taylor Wimpey N E Troon, Phase 7 NHBC £395,682.75 £395,682.00 Work ongoing
SAC/192/17/20 Taylor Wimpey N E Troon, phase 8 NHBC £797,174.00 £797,174.00 Work ongoing

Page 10

RCC Ref Developer Site Bond
Provider
Original Bond
Value
Current Bond
Value
Status
SAC/193/01/21 Mactaggart &
Mickel
Greenan, Phase 4 NHBC £661,142.00 £661,142.00 Work ongoing
SAC/194/02/21 Milestone
Developments
Tunnoch Farm, Phase 1B Evo Surety £540,000.00 £540,000.00 Work ongoing
SAC/199/07/21 Cala Homes Greenan, Phase 8 NHBC £372,104.00 £372,104.00 Work ongoing
SAC/201/09/21 Persimmon
Homes
Monkton, Phase 6 NHBC £432,257.00 £432,257.00 Work ongoing
SAC/203/11/21 Persimmon
Homes
Monkton, Phase 7 NHBC £242,207.00 £242,207.00 Work ongoing       
Appendix 2 - Completed Road Bonds and Road Adoptions since August 2020 
East Ayrshire 
RCC Ref Developer Site Bond Release
Date
Adoption
Date
Comments
EAC/CC/05/011 EXT King Homes Holmhead, Cumnock,
Phase 8
22/11/21 24/11/21  All development completed and adopted
EAC/CC/04/005 George Wimpey Altonhill Distributor Road,
Kilmarnock, Phase 2
11/03/22 11/03/22 All development completed and adopted
EAC/CC/08/003 Bellway Homes Margaret Parker Avenue,
Western Road, Kilmarnock 
08/06/21 08/06/21 All development completed and adopted
EAC/CC/11/003 Stewart Milne
Homes
Kilwinning Road, Dalry
Road, Stewarton,
Phase 1
18/01/21 18/01/21 All development completed and adopted
EAC/CC/11/004 Stewart Milne
Homes
Kilwinning Road, Dalry
Road, Stewarton,
Phase 2
18/01/21 18/01/21 All development completed and adopted
EAC/CC/11/005 Stewart Milne
Homes
Kilwinning Road, Dalry
Road, Stewarton,
Phase 3
18/01/21 18/01/21 All development completed and adopted

Page 11

RCC Ref Developer Site Bond Release
Date
Adoption
Date
Comments
EAC/CC/11/010 Taylor Wimpey Kilwinning Road, Dalry
Road, Stewarton, 
Phase 4
18/01/21 18/01/21 All development completed and adopted
EAC/CC/12/003 Taylor Wimpey Altonhill, Kilmarnock,
Phase 8
11/03/22 11/03/22 All development completed and adopted
EAC/CC/14/004 Keepmoat Homes Former Stoddard’s carpet
factory site, Barbadoes
Road, Kilmarnock,
Phases 1, 2 & 3
24/03/22 24/03/22 All development completed and adopted
EAC/CC/14/005 Barratt Homes Glasgow Road, Kilmarnock,
(Craighall Farm) 
21/08/20 21/08/20 All development completed and adopted
EAC/CC/15/001 Taylor Wimpey Altonhill, Kilmarnock,
Phase 9
11/03/22 11/03/22 All development completed and adopted
EAC/CC/15/002 Taylor Wimpey Altonhill, Kilmarnock,
Phase 10
11/03/22 11/03/22 All development completed and adopted
EAC/CC/15/008 Barony
Developments
Cairn Road, Cumnock 21/10/20 21/10/20 All development completed and adopted
EAC/CC/16/001 Persimmon Homes Dunlop Road, Stewarton
(Roundabout Works)
15/04/21 15/04/21 House building on Phases 1-5 ongoing
EAC/CC/16/011 Milestone
Developments
Robert Burns Avenue,
Drongan, Phase 3, 
(Shanter Crescent) 
19/10/20 19/10/20  All development completed and adopted
EAC/CC/17/011 Hayhill
Developments
Hayhill House 10/03/22 22/03/22 All development completed and adopted 
South Ayrshire 
RCC Ref Developer Site Bond Release
Date
Adoption
Date
Comments

Page 12

Appendix 3 - New Bonds received since August 2020 
East Ayrshire 
RCC Ref Developer Site Bond
Provider
Bond Value Status
EAC/CC/19/009 Bellway Homes
Ltd
Fardalehill, Kilmarnock,
Phase 3
NHBC £1,018,084
(21/08/20)
Site currently being developed
Bond reduced to 50% (£509041.91) on 14/12/21
EAC/CC/19/0013 Campbell Homes Rigg Road, Cumnock, 
Phase 5
Cash
Deposit
£65,114.84
(07/06/21)
Site currently being developed. 
LODGED AS CASH BOND 5,6 &7 TOTAL £170,807.79
EAC/20/004B Murdoch
Properties
Glebe Road, Galston.
Phase 2, North, Road 2.
(Adoptable)
Cash
Deposit
£44,215.84
(03/11/20)
Site currently being developed 
EAC/CC/20/006 Glencairn Estates One Recreation Road,
Cumnock
Cash
Deposit
£106,370.27
(07/06/21)
Site currently being developed. 
EAC/CC/20/007  Avant Homes
(Scotland) 
Loudoun Street, Draffen,
Stewarton 
NHBC £2,125,456
(26/03/21)
Site currently being developed. 
EAC/CC/21/005 Campbell Homes Rigg Road, Cumnock, 
Phase 6
Cash
Deposit
£61,114.61
(07/06/21)
Site currently being developed. 
LODGED AS CASH BOND 5,6 &7 TOTAL £170,807.79
EAC/CC/21/006 Campbell Homes Rigg Road, Cumnock, 
Phase 7
Cash
Deposit
£44,578.34
(07/06/21)
Site currently being developed. 
LODGED AS CASH BOND 5,6 &7 TOTAL £170,807.79
EAC/CC/21/009 Campbell Homes Rigg Road, Cumnock, 
Phase 8
Cash
Deposit
£99,888.44
(09/03/22)
Site currently being developed. 
EAC/CC/21/011 J. Campbell, New
Cumnock
Muirkirk Road, Lugar AVIVA £108,370.21
(28/10/21)
Site currently being developed. 
EAC/CC/21/007 Miller Homes Ltd  Irvine Road, Kilmaurs NHBC £1,743,070.61
(10/08/21)
Site currently being developed.

Page 13

South Ayrshire 
RCC Ref Developer Site Bond Provider Bond Value Comments
SAC/197/12/20 Taylor Wimpey N E Troon, Phase 7 NHBC £395,682.00 Site currently being
developed
SAC/193/01/21 Mactaggart & Mickel Greenan, Phase 4 NHBC £661,142/00 Site currently being
developed
SAC/194/02/21 Milestone
Developments
Tunnoch Farm, Phase 1B Evo Surety £540,000.00 Site currently being
developed
SAC/199/07/21 Cala Homes Greenan, Phase 8 NHBC £372,104.00 Site currently being
developed
SAC/201/09/21 Persimmon Homes Monkton, Phase 6 NHBC £432,257.00 Site currently being
developed 
SAC/203/11/21 Persimmon Homes Monkton, Phase 8 NHBC £242,207.00 Site currently being
developed

Page 14

Appendix 4 – Procedure relating to the management and reporting of
road bonds and road construction consents. 
PROCEDURE RELATING TO THE MANAGEMENT AND REPORTING OF 
ROAD BONDS AND ROAD CONSTRUCTION CONSENTS 
1 PURPOSE 
1.1 The purpose of this procedure is to set out the requirements for the management of road
bonds and Road Construction Consents as well as the requirements for internal and
external reporting of road bonds held by the Ayrshire Roads Alliance. 
2 SCOPE 
2.1 This procedure covers the management and reporting of road bonds and Road
Construction Consents across East and South Ayrshire Councils. 
3 BACKGROUND 
3.1 The Roads (Scotland) Act 1984 requires that, for any road not constructed by a roads
authority, the appropriate consent from the local roads authority is obtained to undertake
this work.  This is known as Road Construction Consent (RCC). The Ayrshire Roads
Alliance undertakes the day to day management of Road RCCs on behalf of East and
South Ayrshire Councils.   
3.2 Where new roads are being constructed for housing, developers are required to provide
the roads authority with security to cover the cost of constructing the roads should the
developer default.  The provisions are set out in the Security for Private Road Works
(Scotland) Regulations 1985, as amended.  This security may take the form of a cash
deposit but it is generally in the form of a road bond.  The security is retained by the
Roads Authority until completion of the consented works, although the value may be
reduced as the works progress. 
3.3 Similarly, Section 96 of the Roads (Scotland) Act 1984 allows that the Roads Authority
can seek a Bond or other financial guarantee where extraordinary damage may be
caused to the roads infrastructure by a private body – typically where heavy or excess
loads are being transported in respect of commercial developments. 
3.4 The requirements for the management and reporting of road bonds is set out in
Accounting Policy Bulletin (APB) 8A: Financial Guarantees. 
3.5 It is the responsibility of the Head of ARA to ensure that a register is maintained of all road
bonds, financial guarantee or deposits that have been requested from a developer and
that this is subject to appropriate monitoring and review. 
3.6 ARA QA Procedure DEVC-01 “Procedure relating to Road Construction Consent and
Road Adoptions’ sets out the detailed procedure and process mapping for the day to day
management of RCCs and Road Bonds from initial application to final adoption.

Page 15

3.7 This procedure, DECV-02, sets out the overall management responsibilities and reporting
requirements to ensure that there is appropriate management and scrutiny of RCCs and
Road Bonds. The obligations set out in this document aim to meet the requirements of
APB8A and Internal Audit recommendations. 
4. PROCEDURE 
4.1 The levels of management responsibilities and reporting requirements for the key decision
points in the management of RCCs and road bonds are set out in Table 1. 
Table 1: Minimum level of responsibility for approvals 
Engineer/
Technician
Section Manager/
Team Leader
Strategic
Manager
Head of
Service
Day to day control of RCCs
and Road Bonds including
continuous updating of RCC
Register 

Granting of RCC - Signing of
CC4 and DEVC-L08 
  
Road Bond Reduction -
Signing of DEVC-L10 &
DEVC-L11  

Approval of QA letters and
Forms 
  
Approval of QA Procedures
DEVC-01 and DEVC-02  
 
Approval of Quarterly Report    
Approval of Annual Report to
ASSJC   

Referral to Legal Service      
Day to day control of RCCs and Road Bonds 
4.2 The Engineers and Technicians within the Traffic Section are responsible for the day to
operation of the development control process. They will be responsible for ensuring that
the process set out in DEVC-01 ‘Procedure relating to Road Construction Consent and
Road Adoptions’ is adhered to and that the RCC register is continuously updated. 
Management Approval of Key RCC Process Stages 
4.3 DEVC-01 ‘Procedure Relating to Road Construction Consent and Road Adoptions’ sets
out the detailed process relating to RCCs and Road Bonds including the key decision-
making stages within the process. To ensure proper scrutiny line management has a
responsibility to check and approve the key decision making stages following review of
supporting information presented by RCC case officer staff.  The key decision-making
stages are in relation to granting of RCC and for Road Bond Reductions. The following
documents must only be signed by supervisory or management staff: 
• Granting of RCC - Signing of CC4 and DEVC-L08
• Road Bond Reduction - Signing of DEVC-L10 & DEVC-L11 
4.4 The Head of Service must be made aware of any RCCs or Road Bonds where there is a
concern or divergence from the approved procedures and must be advised where it is
considered necessary to escalate matters to Legal Services.

Page 16

Management Approval of written procedures and process maps 
4.5 It is important that senior ARA management are aware of and take responsibility for the
Development Control written procedures. It is a requirement that the ARA Service
Manager will approve the DEVC-01 and DEVC-02 documents. All letters and forms
referred to in the Procedures must be approved by the Team Leader or Section Manager. 
Quarterly Report 
4.6 The Engineers and Technicians will provide a quarterly update listing of all RCCs and
road bonds setting out their current status. This will be reviewed by the Section
Manager/Team Leader before being sent to the Service Manager and Head of Service for
review and comment. The Quarterly Report will also highlight any development sites
where there are or could be potential issues or concerns which may need further
management action, including possible recourse to Legal Services. The Quarterly Report
will contain information on the following: 
• RCCs submitted but not yet approved
• Approved RCC sites under development
• RCC sites on maintenance period
• RCC sites awaiting adoption
• RCC sites with less than 6 months to complete
• RCCs lapsed
• RCC Road Bonds Called-In
• Non-residential bonds 
Annual Report 
4.7 A report will be submitted on an annual basis to the Ayrshire Shared Services Joint
Committee (ASSJC) setting out the current position regarding road bonds held by the
Ayrshire Roads Alliance on behalf of East and South Ayrshire Councils. This sets out for
public record the currents status of road bonds held by ARA. The report will set out the
following: 
• List all current residential road bonds held (including RCC Ref, developer, site
location, bond provider, bond value, and current status)
• List all completed road bonds and adoptions since the previous report to the ASSJC
• List all new road bonds received since the previous report to the ASSJC
• List all non-residential road bonds held
• Provide a written narrative on any significant matters and/or areas of concern
• Advise the Committee on any other relevant development control policy and guidance
matters. 
End.