AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
5 December 2025  
Report by the Head of Roads - Ayrshire Roads Alliance     
_________________________________________________________________ 
AYRSHIRE ROADS ALLIANCE
IMPROVEMENT ACTION PLAN
________________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this Report is to advise the Joint Committee on the management
of the Improvement Action Plan by the Ayrshire Roads Alliance. 
RECOMMENDATIONS 
2. It is recommended that the Joint Committee:
i. Notes the Improvement Action Plan presented in this report; 
iii. Continues to receive updates on progress; and 
iv.  Otherwise, notes the content of the report.
BACKGROUND 
3. The purpose of the report is to provide regular updates on the Improvement
Action Plan.  This ensures that the actions are monitored and scrutinised at a
minimum of a quarterly basis and is contained in Appendices 1-3. 
MAIN REPORT/MAIN ISSUES 
4. This Improvement Action Plan is collated by the Head of Service and used to: 
• monitor the progress in meeting the Ayrshire Roads Alliance’s
objectives;
• help managers to continually review the actions and progress to date;
and 
• identify any risk / problem areas that need addressed regarding the
Improvement Action Plan. 
5.      ARA’s Digital Improvement Programme of work in collaboration with TrueView
Visuals continues with the recent completion and roll out of an External Works
module to better manage works that ARA carry out for other Council Services
and work is nearing completion on Additional Support Needs (ASN) Transport
and Professional Design modules in conjunction with other Council Services
across both South and East Ayrshire. 
6. There has been significant interest recently in these new and other existing
digital modules from other Local Authorities and through the Commercial

Page 2

Official
Agreement established between both Councils and TrueView Visuals a
percentage share of any sales of these jointly developed modules will be
received. 
7.      Ayrshire Roads Alliance continues to assist with the delivery of the Ayrshire
Growth Deal (AGD) Roads Infrastructure Project and Prestwick Proposition for
South Ayrshire Council (SAC) and meet colleagues from SAC regularly to
update progress. 
8.      In respect of our Public EV Charging, tender returns are due early January
2026 and tender award scheduled for February/March 2026. Further updates
will be provided to both Cabinets and to North Ayrshire Council once the
procurement process has been finalised. 
9. Phases 1-3 of the roll out of 20mph speed limits in villages in South Ayrshire
have been completed and work is now ongoing on Phase 4 which will include
the larger settlements of Coylton, Maybole and Girvan. Phase 5 in future
years will then consider the towns of Troon, Prestwick and Ayr. 
10. In October East Ayrshire cabinet gave approval for ARA to progress with trials
of 20mph speed limits in New Cumnock, Mauchline, Kilmaurs and
Crookedholm. 
11.      Following approval of Ayrshire Roads Alliance Pavement Parking
Enforcement reports by both Cabinets, enforcement commenced with a soft
approach followed by full enforcement in South Ayrshire from 1st May 2025
and in East Ayrshire from 1st June 2025. There has been good compliance
with the new restrictions in both authority areas and officers are currently
reviewing requests for further exemptions in both areas. Once this review is
complete any additional exemption orders considered necessary will be
reported to future Cabinets.   
12. The Active Travel Member Officer Working Group  established in South
Ayrshire continues to meet 6 weekly as do the Community Action Groups.
These meetings are supported by SAC’s Thriving Communities team. The
Ayrshire Roads Alliance are currently working in partnership with East
Ayrshire Leisure to finalise the East Ayrshire Active Travel Strategy (EAATS).
Once the EAATS is approved the Active Travel Forum will be re-established
to better co-ordinate projects being delivered by individual services. A
Community Engagement Group will also be formed to provide a structured
mechanism for the public to help shape Active Travel in East Ayrshire.   
13. South Ayrshire Council successfully secured £20m from the Levelling Up
Fund and ARA will deliver £15m worth of improvements to Burns Statue
Square, Ayr. The reminder will be used by ARA along with ATIF funding to
construct a new Active Travel Route linking Dundonald to Barassie and for
improvements to the NCN7 route between Prestwick and Barassie station. 
14. IMPLICATIONS

Page 3

Official 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning Yes  13&14
2. Governance Yes  15
3. Human Resources  No 16
4. Equality and Fairer Scotland Duty Yes  17
5. Financial Yes  18
6. Risk Yes  19
7. Community Wealth Building Yes  20
8. Net Zero Yes  21 
POLICY/STRATEGIC PLANNING IMPLICATIONS 
13. A well-maintained road network will contribute to achieving the 2015-2030
Community Plan objectives and associated 2021-2024 Delivery Plans. 
14.    The matters referred to in this report contribute to Priority 1 of the South Ayrshire
Council Plan: Spaces and Places/ Moving around and the environment
(Outcome 1). 
GOVERNANCE IMPLICATIONS 
15. The Improvement Action Plan is a management tool and this will not replace the
existing statutory returns for risk and performance related information. 
HUMAN RESOURCES IMPLICATIONS 
16. The Improvement Action Plan has no direct impact on human resources. 
EQUALITY IMPACT AND FAIRER SCOTLAND DUTY IMPLICATIONS 
17. The Improvement Action Plan complements the Equality Impact Assessment by
ensuring that any issues arising are adequately prioritised, managed and either
eliminated or mitigated. 
FINANCIAL IMPLICATIONS 
18.  The Improvement Action Plan facilitates the existing scrutiny arrangements to
manage, prioritise, and review the budget provided by East Ayrshire Council and
South Ayrshire Council to the Ayrshire Roads Alliance 
RISK IMPLICATIONS 
19.  The Improvement Action Plan assists in the prioritisation of risks that need to be   
mitigated by the Ayrshire Roads Alliance in order to reduce the overall risk to

Page 4

Official
either Council and to comply with the Community Plan/Council Plan in both
partner bodies. 
COMMUNITY WEALTH BUILDING IMPLICATIONS 
20. The Improvement Action Plan supports economic levers to develop resilient,
inclusive local economies with more local spend and fair employment, as well as
ensuring that wealth is more locally owned and benefits local people. 
NET ZERO IMPLICATIONS 
21.  The Ayrshire Roads Alliance Improvement Action Plan and Carbon Strategy
supports and links to East Ayrshire Climate Strategy Themes; 
Theme 2: Transport
Theme 4: Natural Environment 
Jane Corrie
Head of Roads – Ayrshire Roads Alliance
21st August 2025 
BACKGROUND PAPERS 
Ayrshire Roads Alliance Service Plan 2025/26 
LIST OF APPENDICES 
1. Ayrshire Roads Alliance Improvement Action Plan
2. East Ayrshire Council Strategic Priorities 2025/26 
3. South Ayrshire Council Strategic Priorities 2025/26 
Person to contact: Jane Corrie, Head of Roads - Ayrshire Roads Alliance
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
Implementation officer: Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org

Page 5

1 
Official
APPENDIX 1 - AYRSHIRE ROADS ALLIANCE IMPROVEMENT ACTION PLAN 2025/26 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details
1 Continue to use the integrated
Roads Asset Management
Plan across the Ayrshire
Roads Alliance.
There is one Asset Plan for the Service
delivering a risk based approach for full
service delivery
Head of Service Completed Document has been presented to Joint
committee and will be reviewed annually.
2 Continue to prepare details for
developing an integrated Local
Transport Strategy.
A Strategy covering both Council areas,
which will involve consultation with
stakeholders. Information will be
gathered to inform the future Local
Transport Strategy. 
Continue to contribute to the Scottish
National Transport Strategy, Regional
Transport Strategy and Strategic
Transport Projects Review work.
Head of Service  Ongoing The Regional Transport Strategy, through SPT,
on which the Alliance has Board membership,
has now been published. 
The Local Transport Strategy will now be
progressed during 2026/27.
3 Action the Flood Risk
Management Plan
Inform the next national cycle of
potential flood risk management
schemes beyond 2022. 
Complete schemes and undertake
studies.
Head of Service  Complete 
March 2026
Reports submitted to both Cabinets Early 2023 
New Cumnock Flood Defences Complete 
Flood studies for Doon and River Ayr and the
Troon Coastal Flood study are complete. 
Work on the River Irvine and Pow Burn flood
studies is ongoing.

Page 6

2 
Official 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details
4 Improve the condition of the
road network.
Improve annual roads survey results
which are part of the SRMCS work.
Ensure the Alliance undertakes more
proactive maintenance.
Head of Service  Site works will
be undertaken
throughout
2025/26.
Key dependencies are the Road Improvement
Plans approved by the relevant Committees in
East Ayrshire and South Ayrshire in spring
2025. Progress is provided to members, and
relevant Committees.
5 Ensure the road network remains
safe through raising awareness
and improving road safety
through education, engineering
and enforcement.
Reduce road accidents in line with
government targets.
Provide appropriate traffic management
schemes and initiatives.
Strategic Manager  March 2026 Scottish Government and SCOTS guidance is
used. A key dependency is the Road
Improvement Plans which are presented to
Cabinet each year.
6 Improve the condition of the
bridge stock.
Improve bridge condition index. Reduce
the number of weight restricted bridges.
Complete all general, special and
principal bridge inspections.
Strategic Manager  March 2026 Through the Road Asset Management Plan.
Key dependencies are Road Improvement
programmes approved by Committees in East
Ayrshire and South Ayrshire in spring 2025. 
Deliver the capital and revenue programmes.
7 Manage and improve the street
lighting asset and install energy
efficient lighting schemes.
Maintain high standard of fixing dark
street lights. Complete the LED lighting
replacement programme in both East
Ayrshire and South Ayrshire.
Head of Service  March 2026 Through the Road Asset Management Plan,
with additional funding being provided to
commence the LED programme. 
At present performance is 98% of street lights
are now LED in EAC; and 100% in SAC. On
target for completion within timescales.
8 Maximise and deliver externally
funded sources of work
Identify external funding sources and
deliver work on time and on budget.
Improve infrastructure; and contribute to
improving the condition of the
network.
Head of Service  Works will be
undertaken
throughout
2025/26.
External sources, including Timber Transport,
Transport Scotland Active Travel Infrastructure
Tier 1 and Tier 2 Funding, SPT, SUSTRANS
Scottish Government, Ayrshire Growth Deal &
Levelling Up Fund

Page 7

3 
Official 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details
9 Implementation of Parking
Strategy
Develop Head of Service Ongoing
through
2025/26
Amendments to TRO’s, lining, signing and 
residential parking permits and implementing 
an improved process using digital technology 
10 Prepare Service Plan Publish Head of Service Annual East Ayrshire Council Community Plan. South
Ayrshire - Local Outcomes Improvement Plan
and Local Place Plans. Regular updates will be
provided to joint committee.
11 Continue to review insurance
costs and insurance issues.
Review current practices to minimise
insurance costs.
Head of Service Complete Ayrshire Roads Alliance Monthly Insurance
Report. 
There is good dialogue with the Risk &
Insurance to ensure our work improves the
number of repudiated claims. The number of
claims has greatly reduced due to the
implementation of the new Code of Practice.
12 Review Depots and
Accommodation
Continue to review in 2024/25 from initial
work was completed in 2017 as a result
of amended working practices.
Head of Service Complete Joint Committee Reports of November 2016. 
Although initial work has been completed we
continue to strive to make depot and
accommodation cost savings. Further work will
continue on this as a result of COVID and the
return to office space during 2022/23. 
13 Review vehicle and plant costs Continue to review in 2021/22 from initial
work that was completed in 2017.
Head of Service  March 2026 The service will continue to review the fleet
requirements through the use of utilization
reports and improvements to the management of
the Vehicle Replacement Plan. 
14 Monitor and exercise Business
Continuity Plans
Improved resilience. Business Support
Manager
Review and
update
following
Existing East Ayrshire and South Ayrshire
Council plans

Page 8

4 
Official 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details    
Relevant local
and national
events. 
15 Continue to use the Roads
Costing System to its full
potential.
Improve service performance from both
an on-site and financial perspective.
Business Support
Manager
Ongoing Revised roads costing system was fully
operational from November 2018. 
The system continues to be used to monitor
performance and work is ongoing to implement
digital timesheets linked to the Roads Costing
System.
16 Support and contribute to the
Ayrshire Growth Deal
Project Management of Roads Delivery
Projects.
Head of Service  Ongoing Ayrshire Roads Alliance is leading with the
planning and delivery of the Ayrshire Growth
Deal road improvement proposals and assisting
with the enabling infrastructure requirements of
the Commercial Build proposition.
17 Regional Transport Strategy Successfully contribute to the
preparation of this work being led by
SPT. The Alliance has Board
representation.
Head of Service Complete SPT documents and existing Regional
Transport Strategy
18 Regional Transport Appraisal Ensure the various projects identified
as part of this work are included in the
Strategic Transport Projects Review.
Head of Service Complete Transport Scotland has published the final
STPR2 with delivery programme to be
published.
19 National Transport Strategy East Ayrshire and South Ayrshire
Councils contribute to this process to
ensure the sustainable transport
hierarchy and sustainable investment
hierarchy are delivered.
Head of Service Complete In recognition of the anticipated increase in
Active Travel work, it is proposed that a
member of staff is dedicated directly to this
work.

Page 9

5 
Official
20 National Transport Strategy –
review of Governance
East Ayrshire and South Ayrshire
Councils contribute to this process to
ensure that the
outcome/output meets the
Head of Service  Complete National Transport Strategy
21 Transport (Scotland) Bill –
Pavement Parking ban
East Ayrshire and South Ayrshire
Councils contribute to this process to
ensure a pragmatic approach is taken in
delivering the pavement parking ban in
both Council areas
Head of Service  March 2026 Pavement Parking enforcement has commenced.
A large number of Exemption Order requests in
both authority areas are currently being
reviewed. Committee Papers will be submitted
Jan/Feb 2026 with implementation anticipated
late 2026. 
22 Digital Transformation  Develop modules to deliver end to end
digital processes 
Business Support
Manager
Ongoing TTRO applications –Implemented 
TRIPS – Implemented 
Traffic Signal permits – Implemented 
Management of external works for EAC & SAC –
Implemented 
ASN School Transport – in Development 
Professional Design Services – in Development

Page 10

6 
Official
Appendix 2 - East Ayrshire Council Strategic Priorities 2025/26 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details
1 Progress and complete the New
Cumnock Flood Protection
Project 
Complete the flood prevention projects
at the Leggate and beside the Afton
Water.
Phases  1 & 2
Head of Service Complete  East Ayrshire Council and Scottish
Government funding.  The full Scheme was
completed April 2023.  Final defects certificate
issued August 2024
2 Develop Projects approved from
the Flood Risk Management
Plan  
Progress relevant studies and inform
the developing list of schemes for
cycle two of the national protection
schemes to be delivered from 2022. 
Head of Service March 2026  The studies for the River Ayr and the Doon are
now fully complete and options being
appraised.
The Irvine Valley Flood Study is currently
being updated to identify options for a potential
scheme that is more likely to attract funding.
3 Active Travel Strategy Develop active strategy for travel
across South Ayrshire Network and
East Ayrshire Network
Head of Service Ongoing Work is ongoing to finalise the East Ayrshire
Active Travel Strategy and this will be
submitted to Council for approval prior to
Summer recess 2026.
4 EV Strategy  Develop EV strategy across East
Ayrshire Network
Head of Service February
2026 
Work on PAN Ayrshire Concession Contract
ongoing with anticipated contract award in
February/March 2026. 
5 Ash Die back Strategy Develop a risk based strategy for the
management of Ash Die Back.
Head of Service Strategy –
Complete
Surveys -
Ongoing
through
2025/26
Risk based strategy complete.  
Surveys & works ongoing. 28-day notices to
owners with objections received referred to
legal services.

Page 11

7 
Official
Appendix 3 - South Ayrshire Council Strategic Priorities 2025/26 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
1 Implementation of car parking
strategy for South Ayrshire. 
Complete this work with improved
parking provision and management. 
Head of Service  Ongoing –
through
2025/26
Ayr parking report is being further developed
and expanded to include a review of 2 hours
free parking and off street parking. Report will
be presented late 2025. The Prestwick paper
is also finalised.
Troon to follow thereafter. 
2 Develop Projects approved from
the Flood Risk Management
Plan  
Progress relevant studies and inform
the developing list of schemes for
cycle two of the national protection
schemes to be delivered from 2022. 
Head of Service Ongoing
through
2025/26
A Surface Water Management Plan has been
developed for Ayr, Prestwick and Dundonald.
Identified actions are being progressed on a
priority basis and as resources become
available. 
Troon Coastal Flood Study is complete up to
the Options Appraisal stage. 
Pow Burn Prestwick Flood Study is ongoing.
3 Support and contribute to the
Ayrshire Growth Deal
Stimulate economic growth and
address inclusive growth concerns. 
Contribute to infrastructure projects
which are being developed through the
Regional Transport Appraisal work
being led by Transport Scotland.
Head of Service Ongoing until
2030
Ayrshire Roads Alliance is leading with the
planning and delivery of the AGD Road
Improvement proposals & assisting with the
enabling infrastructure requirements of the
Commercial Build proposition.
4 20mph speed restrictions in
villages
Progress with the 20mph speed
restrictions in all villages.  Maintain
engagement with the local
communities.
Head of Service Ongoing –
through
2025/26 and
future years
Phase 1 & 2 complete.
Phase 3 complete
Phase 4 – Coylton, Maybole & Girvan -
ongoing
Phase 5 – Troon, Prestwick & Ayr to be
progressed in future years.

Page 12

8 
Official 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
5 Anticipated Budget Reductions
in 2026/27
Continue to provide a high quality
roads service within decreasing
available budgets.
Head of Service March 2026 Reports to various Committees. 
6 Active Travel Strategy Review South Ayrshire Active Travel
Strategy
Head of Service Ongoing
annually
The Active Travel Strategy will be reviewed
and discussed with the Active Travel
Community Action Group, any amendments
will be presented to the Active Travel Member
Officer Working Group
7 EV Charging Strategy  Develop further the  EV strategy for
South Ayrshire Network
Head of Service February
2026 
Work on PAN Ayrshire concession contract
ongoing with contract award due in
February/March 2026.
8 Levelling Up Fund Active Travel bid Head of Service  Ongoing –
through
2025/26/27
LUF bid successful for construction of new
Active Travel Route between Dundonald and
Barrassie – works ongoing with completion
expected by 31st March 2026. A 2nd bid for
improvements to the NCN7 route from
Prestwick to Barassie station also successful
with work due to start late 2025 and complete
31st March 2027.
9 Motorhome Trials Develop Campervan sites along the
coastline.
Head of Service Complete Permanent schemes now apply at the
Ballantrae, Girvan, Ayr (Esplanade & Battery)
and Troon sites. 
10 Strategic Economic Impact
Assessment A75/A77
There is a growing desire to
understand the importance /
effectiveness of the improvements
outlined along the A75 and A77.
Head of Service Ongoing SEIA complete, ARA tasked to progress STAG
for the A77 or a combined A75/A77 STAG on
behalf of SAC and D&G Council. No funding
forthcoming from D&G, clarification required
from SAC if A77 should be progressed
independently.
11 Ash Dieback Develop a risk based strategy for the
management of Ash Die Back jointly
with South Ayrshire Council.
Head of Service Complete Risk based strategy complete.  
Surveys ongoing issuing 28-day notices to
owners with objections received referred to
legal services.

Page 13

9 
Official 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
12 152nd Open Championship Delivery of Event Traffic and Transport
Management 
Head of Service Complete Successfully delivered.  Debrief September
2024
13 The International Ayrshow -
Festival Of Flight
Delivery of Event Traffic and Transport
Management
Head of Service Ongoing Successfully delivered.  Debrief November
2025. Planning ongoing for 2026 event.