Roadworks Programme
North Ayrshire Council · 5 December 2025
Back to Ayrshire Shared Services Committee — 5 December 2025 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
Official AYRSHIRE SHARED SERVICE JOINT COMMITTEE 05 December 2025 Report by the Head of Ayrshire Roads Alliance ______________________________________________________________ SUBJECT: ROADWORKS PROGRAMME 2025/26 ______________________________________________________________ Purpose of report 1. The purpose of this report is to advise the Joint Committee on the progress of work through the road improvement programmes within East Ayrshire and South Ayrshire for financial year 2025 to 2026. Recommendations 2. It is recommended that Joint Committee: (i) Notes, the Ayrshire Roads Alliance programmed works 2025/26 (ii) Otherwise, notes the contents of this Report. Background 3. The budget allocation for East and South Ayrshire Councils Roads Investment Programme for FY 2025/26 can be seen in tables 1 and 2 below respectively. Table 1: East Ayrshire Council Roads Investment Programme 2025/26 Programme Area Budget (£m) Carriageway Resurfacing 2.081 Footway Resurfacing 0.084 Street Lighting 0.215 Traffic & Transportation incl. road safety 0.330 Active Travel 0.050 School Streets 0.050 Bridge and Culvert Strengthening (incl. road slips) 3.500 Car Parks incl. Multi-storey demolition 0.820 Fleet 0.600 Total 7.730 External Funding SPT – Behaviour Change 0.385 Transport Scotland – Behaviour Change 0.116 ATIF Tier 1 – General Active Travel Infrastructure Projects 0.758 Developer Contributions/Route Action Plans 0.359 Bus Infrastructure Fund – Tier 1 0.645 SG – EV Infrastructure Fund 2.800 Sustrans – Annick Valley Stage 2 0.144
Page 2
Official Road Safety Improvement Fund 0.359 Total 5.566 External Funding (Provisional Acceptance) ATIF Tier 2 – MSCP Redevelopment - Construction 1.350 ATIF Tier 2 – KGIL Design 0.900 Total 2.250 Table 2: South Ayrshire Council Roads Investment Programme 2025/26 Programme Area Budget (£m) Carriageway & Footway Resurfacing 1.581 Street Lighting 0.150 Bridges Capital 0.881 Millennium and Craigholm Bridges 0.145 C12 Dunure slope stabilisation 0.130 Vehicle restraint barriers 0.073 Cattle grid renewal 0.033 Girvan Harbour Jetty repairs 0.504 Local Flood Risk Plan 0.153 Ayr Depot 0.250 Climate Changes St Ninians Park 0.255 EV Charging Infrastructure 0.281 Total 4.436 External Funding SPT – Behaviour Change 0.170 Transport Scotland 0.116 ATIF Tier 1 – General Active Travel Infrastructure Projects 0.737 ATIF Tier 2 - Dundonald – Barassie 3.050 Ayrshire Growth Deal 0.857 Levelling Up Fund (Active Travel) 4.000 Levelling Up Fund (Burns Statue) 15.000 Bus Infrastructure Fund – Tier 1 0.358 Sustrans – Accessible Ayr 0.799 Sustrans – Girvan to Grangeston 0.041 Road Safety Improvement Fund 0.315 Total 25.443 External Funding (Provisional Acceptance) ATIF Tier 2 – Loans to Troon 0.450 ATIF Tier 2 – Prestwick to Barassie 0.650 Total 1.100 Main report/main issues 4. Surfacing programmes for financial year 2025/26 are contained within Appendix 1 and 2.
Page 3
Official Capital Resurfacing 5. National Testing have now been awarded the new coring contract as of 30 October 2015. A contract start up meeting was held on 05 November 2025. Coring plans will now be sent to National Testing over the coming weeks to commence as soon as possible. 6. The Capital budget for both authority areas is committed and it is anticipated remaining surfacing works will commence January 2026. Depending on weather conditions during the winter months there is a possibility that some works may require to be carried over into financial year 2026/27. 7. In South Ayrshire ARA has completed 80% of the carriageway resurfacing programme with an anticipated completion date of March 2026. The footway resurfacing programme commenced in August 2025 and was completed November 2025. The remaining carriageway and footway sites identified for resurfacing will be carried over into financial year 2026/27 as detailed in Appendix 2. 8. In East Ayrshire 33% of the carriageway resurfacing programme has been completed. Due to ongoing and further programmed Scottish Water Works in Stewarton, three schemes will be carried over into 2026-2027 totalling £462k. Five footway schemes have been programmed within the current financial year with the remainder being carried forward into 2026-2027. Further details contained in Appendix 1. East Ayrshire Council Residential Road and Footway Repairs (Additional Revenue Funding) 9. At Cabinet on 13 March 2025, East Ayrshire Members Initiatives approved £800k revenue funding for residential and footway repairs with locations identified detailed within Appendix 1 of this report with 23% complete to date. South Ayrshire Council Ward Investment and Promenade Programme 2025/26 10. Officers within our engineering disciplines continue to develop work schemes identified by Ward Members under the South Ayrshire Council Ward Investment Programme for 2025/26 as detailed within Appendix 4 of the report. Timber Transport 11. As reported at the last joint committee in June 2025 neither authority area was successful in their bids for grant funding from the Timber Transport Fund although there may be an opportunity for funds being reallocated due to non- delivery by other authorities with ARA expressing an interest to be considered. 12. Officers are committed to reviewing our application process and an early meeting will be arranged with the Timber Transport Consortium when the window opens for 2026/27 applications.
Page 4
Official Street Lighting 13. The street lighting column and cable replacement programme of works which incorporates LED lanterns is detailed in Appendix 1 and 2. 14. The focus is now on the installation of festive lighting and attending switch-on events in our communities ahead of the Christmas period assisted by our appointed external contractor. 15. The Scotland Excel (SXL) Street Lighting Material Framework has still not been issued and this is hampering the completion of the LED project in the East and material procurement in general. This has been ongoing for 3 years. Following assistance from our Procurement colleagues in exploring alternative frameworks earlier this year, we have been using the YPO ‘Highway Electrical Installations’ procurement framework for the supply of street lighting materials and sundry electrical items. This process though has been found to be more time intensive than with SXL as much of our commonly used material items are not available via ‘direct award’ and subsequently must be procured via Quick Quote tendering. Electric Vehicle Infrastructure 16. The Electric Vehicle Infrastructure Fund (EVIF) programme with the number of public chargers installed to date is listed within Appendix 3 for South and East Ayrshire respectively. 17. East Ayrshire Council is the lead authority for the PAN Ayrshire Public Electric Vehicle Charging Strategy. The project has secured a grant of £2.8million and work continues on the procurement phase. Following the previously approved business case, further papers have been presented to the cabinet regarding the introduction of an EV charging tariff, which has been implemented across all three Ayrshires as of 01 January 2025. A further increase to the tariff was implemented on 01 July 2025. This tariff aims to establish a sustainable funding model and attract private investment. 18. Work is progressing on the tender documentation for the Pan Ayrshire concession contract with the appointment of Mott MacDonald as consultants to assist with the collation of the relevant documents required for tender. The Single Procurement Document (SPD) was issued on 03 March 2025 for the initial stage of tendering, following which we received numerous bids. The second part of the tendering process is currently ongoing, with the Invitation to Tender (ITT) published to the shortlisted bidders on 03 October 2025.The deadline for tender submission is 07 January 2026. Subject to evaluation and approval by the Ayrshire Authorities, the contract award is anticipated in Feb/March 2026. 19. Under the Public Charge point regulations 2023 legislation all rapid chargers were required to be able to accept contactless payment by 24 November 2024. Ayrshire Roads Alliance secured funding from Transport Scotland Contactless Compliance Grant Funding to replace/activate/retrofit eligible CPS rapid chargers to incorporate contactless payment. Works have been carried out to
Page 5
Official replace the non-compatible units and to activate contactless terminals on compatible rapid chargers. 20. Replacement of the 22kW charger at Troon Swimming Pool will be funded from SAC Capital budget but is on hold until the concession contract is awarded in Feb/March 2026. 21. The 50kW chargers at Burns Statue Square, Ayr and Girvan Harbour have been replaced and commissioned. Structures 22. Land acquisition and/or access agreements alongside environmental license requirements continue to cause delays to a number of projects. ARA are working closely with EAC Legal/Estates and relevant stakeholders to progress these issues. 23. Appendix 1 details the East Ayrshire Council bridges capital programme for 2025/26. 24. A713 Polnessan Upper Bridge - ARA have erected temporary traffic signals due to subsidence in the carriageway. Traffic lights will remain in place until the slope has been stabilised. Contract documents are currently being reviewed by Procurement. EAC Legal are finalising land agreements. Works are likely to commence February 2026 subject to land agreements being signed. 25. B741 Coal Glen Embankments - works to be retendered early 2026 following discussion with SPEN regarding utilities in the vicinity of the works. 26. ARA are working with EAC Legal/Estates to acquire land at West Clerkland Bridge through a Compulsory Purchase Order. The bridge has been shut to vehicular traffic since 2012 and shut to both pedestrians and vehicular traffic since 2021. 27. Three bridges on the A71 between the Bellfield Interchange and Moorfield Roundabout need replacement expansion joints. A consultant was appointed to explore options in removing the joints and making the structures semi/fully integral. It has been decided that in the meantime two joints that are repeatedly failing will be replaced with asphaltic plug joints. 28. B730/10 Littlemill Bridge - land acquisition complete after years of negotiation. Tender documents to be reviewed by consultant once SXL consultancy framework is live (anticipated to be April 2026). 29. U13 Aitket Road Slip – contract has been appointed with work due to start on site January 2026. 30. South Pier Quay at Girvan Harbour – A preferred bidder has been identified for these works. The lowest tender is significantly higher than the estimate. Contract award is subject to South Ayrshire Council Cabinet approval of a budget transfer
Page 6
Official from the Girvan Harbour Timber Jetty budget to the South Pier Quay budget. Cabinet sits on the 25th November 2025. 31. The remaining budget for the Girvan Harbour Timber Jetty shall allow for the detailed design works to progress with the contract documentation substantially complete. In order for tenders to be issued for this project additional funding will be required (via Capital Business Case) if the budget transfer request to the South Pier Quay is approved. 32. The A79/30 Victoria Bridge Concrete Repairs and Painting has been completed. The scaffold is currently being removed from this bridge. 33. The Contract Documentation for Girvan Harbour dredging and land based material disposal has been finalised and are with Procurement for Tender issue with a view to works being scheduled for Feb/March 2026. 34. Ayr South Pier - as previously reported at the last Shared Service Joint Committee in June 2025, funding to employ a consultant to carry out an underwater dive survey and structural assessment has not been secured. This is a matter of concern as the importance of a dive survey and assessment was highlighted following the development of a sink hole in a verge area at the end of the South Pier. There has been a recurrence of this sinkhole, therefore, discussions are ongoing regarding the possibility of utilising common good funding. 35. A land slip has occurred on the C13 near Penkill Castle South East of Old Dailly. Temporary barriers have been erected and a monitoring programme established. A Scottish Power 33KV cable has been exposed as a result of the slip as well as a fibre optic communication cable. Discussions are ongoing with Scottish Power about working in the vicinity of this cable as part progressing a solution. Traffic & Transportation 36. Active Travel Infrastructure Fund (ATIF) Tier 1 grant funding for both authority areas has been received from Transport Scotland. Active Travel projects using the Tier 1 funding are currently in development, and will be implemented over the course of the current financial year. 37. Grant awards have been confirmed from Transport Scotland (TS) for both EAC (£645,000) and SAC (£382,000) from the Bus Infrastructure Fund – Tier 1. This unforeseen funding is directly awarded and paid to local authorities as part of the General Capital Block Grant (GCBG) allocation. ARA are currently developing delivery programmes for both EAC and SAC. Completion of the proposed programme will be dependent on resource availability and discussions are underway with TS to determine if the grant can be accrued – particularly if it can be demonstrated that longer term projects e.g. bus park and ride, can be developed and implemented. 38. Grant awards have been confirmed from Transport Scotland for both EAC (£359,000) and SAC (£315,000) from the Road Safety Improvement Fund
Page 7
Official (RSIF). Schemes are currently being identified and prioritised as listed in the appendices but may be subject to change pending Transport Scotland approval. 39. Kilmarnock Bus Station refurbishment programme is now complete with officers currently reviewing the cleaning regime. 40. The contracts for Cumnock Bus Station which include changes to materials and the installation of a public address system are currently being prepared. The new materials to replace damaged glass panels are due to be installed by February 2026 with the public address system to follow in March/April 2026. Ayrshire Growth Deal (AGD) Roads Projects 41. A Case for Change seeking approval of the changes to the roads infrastructure project and also the Prestwick Proposition has now been approved by Scottish & UK Governments. Ayrshire Roads Alliance will assist in the delivery of all these projects for South Ayrshire Council. 42. A Planning application for the construction of a new car park at Shaw Road, Prestwick will be submitted in March 2026. 43. Extensive ground investigations and environmental studies are currently being undertaken on the remaining phases of the AGD in an attempt to accelerate the design process and move more projects through to construction. 44. The ARA will deliver airside improvements to support the commercial build once the sale of GPA has been finalised. 45. An extension to Shawfarm Road will also be delivered to support the commercial build. Levelling Up Fund 46. South Ayrshire Council successfully secured £19M of funding from the Levelling Up Fund (LUF) round three. £15M of this funding has been transferred to ARA and will be utilised to redevelop Burns Statue Square, Ayr. Balfour Beatty are due to be appointed as the principle contractor, design is currently underway and a delivery programme will be produced in December 2025 47. £1.2M of the LUF funding along with a £3.05M award from ATIF will be used to construct a new Active Travel Route linking Dundonald to Barassie Station, work is currently underway on this route and is scheduled to be complete by 31 March 2026. 48. The remaining £2.8M along with funding from the AGD and a bid to the ATIF in December 2025 will be utilised to carry out significant improvements to the NCN7 from Prestwick to Barassie railway stations. Work will commence on-site late April 2026 and will be complete by 31 March 2027.
Page 8
Official Active Travel 49. The Active Travel Infrastructure Fund (ATIF) administered by Transport Scotland has awarded £3.05M towards the construction of the Dundonald to Barassie route. 50. ARA submitted several funding applications to Sustrans in January 2025 to carry out the next stages of the design process for several active travel routes across both South and East Ayrshire Council. It has now been confirmed that Sustrans will not receive funding from Transport Scotland as had originally been advised and these applications have now been transferred to ATIF. Decisions on these applications initially indicated that the bids had been unsuccessful, however, TS have recently re-engaged ARA on the prospect of late awards pending the feasibility of delivering projects by 31 March 2026. Ash Dieback & Other Species 51. Appendix 5 of the report details the current condition data on all High Risk roadside trees for both authority areas. Surveys and programmed works for removal are ongoing with 28-day notices being issued to owners and any objections received referred to legal service. Implications Implications Yes No Paragraph number in report 1. Policy/Strategic Planning x 52 & 53 2. Governance x 54 3. Human Resources x 55 4. Equality and Fairer Scotland Duty x 66 5. Financial x 57 6. Risk x 58 & 59 7. Community Wealth Building x 60 8. Net Zero x 61 Policy/strategic planning implications 52. A well-maintained road network will contribute to achieving the 2015-2030 Community Plan objectives and associated 2021-2024 Delivery Plans 53. The matters referred to in this report contribute to Priority 1 of the South Ayrshire Council Plan: Spaces and Places / Moving around and the environment (Outcome 1). Governance implications 54. By virtue of the relevant statutory provisions, principally detailed within the Roads (Scotland) Act 1984, the Council as local roads authority is required to manage
Page 9
Official and maintain all publicly adopted roads within its area other than those which are maintained and managed by the Scottish Ministers. Human resources implications 55. The work programmes have direct impact on human resources and the Alliance will ensure all works are suitably resourced to maintain satisfactory progress. Equality impact and Fairer Scotland duty implications 56. Equality Impact and Fairer Scotland Duty screening assessments will be undertaken annually as required during the planning stage prior to the delivery of the programme of works. Financial implications 57. The Ayrshire Roads Alliance will deliver the strategic and local services as stated in the Service Plan. The budget is provided by East Ayrshire Council, South Ayrshire Council, and other external organisations. Appropriate scrutiny arrangements are in place to manage these budgets and programmes are detailed within the appendices. Risk implications 58. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every Joint Committee. 59. The Works Programmes, Service Plan and the Risk Register do not expose either Council to an increased risk as they have been developed from existing budgets and existing service commitment. Community Wealth Building implications 60. The works programme provides economic levers to develop resilient, inclusive local economies with more local spend and fair employment, as well as ensuring that wealth is more locally owned and benefits local people. Net zero implications 61. The Ayrshire Roads Alliance Service Plan and Carbon Strategy supports and links to East Ayrshire Climate Strategy Themes Theme 2: Transport Theme 4: Natural Environment
Page 10
Official Appendices Appendix 1 EAST AYRSHIRE COUNCIL PROGRAMMES 2025/26 Appendix 2 SOUTH AYRSHIRE PROGRAMMES 2024/26 Appendix 3 EV PUBLIC CHARGERS Appendix 4 SAC WARD INVESTMENT & PROMENADE PROGRAMME 25/26 Appendix 5 ASH DIE BACK REPORTS Background papers EAC Road Asset Management Plan 2025-2026 SAC Road Improvement Plan 2025-2026 Person to contact Name: Jane Corrie, Head of Roads - Ayrshire Roads Alliance Tel: 01563 503164 Email: jane.corrie@ayrshireroadsalliance.org Implementation Officers Name: Craig Knape, Strategic Manager - Ayrshire Roads Alliance Tel: 01563 503164 Email: craig.knape@ayrshireroadsalliance.org Name: Barrie McDonnell, Strategic Manager – Ayrshire Roads Alliance Tel: 01563 503190 Email: barrie.mcdonnell@ayrshireroadsalliance.org
Page 11
Official Appendix 1 EAST AYRSHIRE COUNCIL PROGRAMMES EAC Carriageway Structural Maintenance Programme 2025/26 (incl works carried over from 2024/25) ROAD LOCATION Estimated Cost Cost to Date variance +/- Comment A71 Dual Carriageway From Moorfield Roundabout – Target Worst Sections £300,000.00 £525,940.49 -£225,940.49 Complete – final measure A736/U20 Junction Contribution to North Ayrshire to complete EAC section Junction Contribution to North Ayrshire to complete EAC section £15,000.00 To be programmed by North Ayrshire Council A735 From Lochridge House North Entrance to Windmill factory Farm £182,354.25 Due to ongoing/programmed Scottish Water Works these works will be carried over into 2026- 2027 A735 Rigg Street Stewarton From B778 to Brown Street £60,606.00 Due to ongoing/programmed Scottish Water Works these works will be carried over into 2026- 2027 B7046 Skares From Junction Newfield Rd to Recycling Centre Additional section into Skares £116,000.00 £158,459.05 -£42,459.05 Complete – final measure B769 Stewarton ] From Stewarton to North Ayrshire Boundary £219,375.00 Due to ongoing/programmed Scottish Water Works these works will be carried over into 2026- 2027 B743 Mauchline High Street From A76 to Loans (School) £52,680.60 Complete – awaiting final measure B7037 Titchfield Street Galston From Mini Roundabout to Orchard Street £97,500.00 Complete – awaiting final measure
Page 12
Official B7038 Kilmarnock Campbell Street From: Fire Station AC / To: Willock Street £41,595.40 Programmed to Commence 24/01/26 C3 Barskimming Road Mauchline From Loudoun Street to StationRoad £74,074.00 Complete – awaiting final measure C108 Stewarton From Greensland to Boundary £114,750.00 Programmed to Commence 07/02/26 C22 Coal Road Auchinleck From Railway bridge to Barbieston Road £35,612.50 Programmed to Commence 23/02/26 U55 Galston From U56 approx 1000m Westwards £78,750.00 £63,166.81 +£15,583.19 Complete – final measure Kilmarnock New Mill Road From Chapmans Terrace to end £45,584.00 Programmed to Commence 02/02/26 Kilmarnock Whatriggs Road From Tinto Avenue to Haining Avenue £35,612.50 Programmed to Commence 19/01/26 Kilmarnock East Shaw Street From Lidle to and around mini roundabout £37,814.00 Complete – awaiting final measure Kilmarnock Bentink Street On Approach to Mini roundabout £20,797.70 Complete – awaiting final measure Kilmarnock Bellsland Grove Full Length £19,080.00 Complete – awaiting final measure Kimarnock Beech Avenue From Portland Road to Larch Place £84,501.40 Programmed for the easter School Holidays 2026. Kilmarnock Pine Road Full Length £42,022.75 Complete – awaiting final measure Kilmarnock Old Irvine Road From Lindsay Street to Grange Street £37,464.35 Complete – awaiting final measure Kilmarnock Brackenhill Avenue Full Length £32,323.20 Programmed to Commence 16/02/26 Kilmarnock Arran Avenue Full length £36,182.30 Programmed to Commence 23/02/26 Kilmarnock Lainshaw Avenue One Section £71,225.00 Programmed to Commence 02/02/26 Kilmarnock Townend Full Length £27,065.50 Programmed to Commence 02/03/26 Stewarton Avenue Square Access Road into car park £11,396.00 Programmed to Commence 23/02/26 Kilmaurs East Park Crescent Full Length £34,045.55 Programmed to Commence 09/02/26
Page 13
Official Galston Western Road Outside Primary School £29,487.15 £41,771.61 -£12,284.46 Complete Hurlford Mayfield Avenue Full Length £57,855.42 Programmed to Commence 02/03/26 Fenwick Skernieland Road From Old A77 Slip to Rysland Terrace £44,053.31 Programmed to Commence 16/02/26 Cumnock Hearth Road Full length £89,909.25 Programmed to Commence 15/12/25 Drongan Lane Crescent Full Length £27,195.00 Programmed to Commence 02/03/26 Bellsbank Corserene Terrace Full Length £29,526.00 Programmed to Commence 16/02/26 Dalmellington Gateside Road Broomknowe to B741 £31,080.00 Programmed to Commence 09/02/26 Dalrymple Cedar Terrace Full Length £15,540.00 Programmed to Commence 23/02/26 Drongan Mill o Shield Road From Coyle Avenue and Garrowhill Drive £37,749.25 Programmed to Commence 09/03/26 EAC Footway Structural Maintenance Programme 2025/26 (incl works carried over from 2024/25) FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment Catrine - Newton Street Outside School £7,290.00 Programmed to Commence 04/02/26 Auchinleck - Main Street From Surgery to Council Car Park £21,870.00 Programmed to Commence 07/02/26 Cumnock - Glaisnock Road Outside Cemetery £19,044.00 Programmed to Commence 14/02/26 Kilmarnock - Dundonald Road Outside School £16,200.00 Will be carried over into 2026-2027 Kilmarnock - Gilmour Street Various Locations £21,060.00 Will be carried over into 2026-2027
Page 14
Official EAC £800k Residential Carriageway/Footway Improvement Programme 2025/26 WARD Location Estimated Costs Cost to Date Variance +/- Comment 1 Carriageway - Stewarton Dornie Close £9,120.00 Programmed to Commence 09/02/26 1 Carriageway - Stewarton Braemore Road £11,310.00 Programmed to Commence 09/02/26 1 Carriageway - Stewarton Kirkmuir Drive £54,000.00 Programmed to Commence 09/02/26 2 Carriageway - Kilmarnock Tourhill Road £5,580.00 £19,433.99 -£13,853.99 Complete – final measure 2 Carriageway - KilmarnockAuchencar Drive £15,120.00 £19,463.81 -£4,343.81 Complete – final measure Stewarton - High Street From Old Bank to Church £16,200.00 Due to ongoing/progr ammed Scottish Water Works these works will be carried over into 2026- 2027 Stewarton - Lainshaw Street Standalane to Sainsbury’s Rear Entrance £19,260.00 Due to ongoing/progr ammed Scottish Water Works these works will be carried over into 2026- 2027 Fenwick - Skerniland Road Both Sides £22,680.00 Programmed to Commence 16/02/26 Galston - A719 Opposite Loudoun Academy From Nursing Home to Barriered Section £8,100.00 Programmed to Commence 09/02/26
Page 15
Official 2 Carriageway - KilmarnockWardneuk Drive £6,165.00 £9,932.66 -£3,767.66 Complete – final measure 3 Carriageway - Kilmarnock Woodside Avenue £60,000.00 Programmed to Commence 09/03/26 4 Carriageway - Kilmarnock - Anderson Place/Bannerman Drive and Drummond Place £46,200.00 £8,409.74 Complete – Awaiting Final measure. 4 Carriageway - Kilmarnock Sparrow Gardens £12,960.00 Programmed to Commence 12/01/26 5 Carriageway - Kilmarnock Simonsburn Road £9,225.00 Programmed to Commence 16/03/26 5 Carriageway - Kilmarnock Elderslie Crescent/Ayr Road £13,500.00 Programmed to Commence 12/01/26 6 Carriageway - Newmilns Sheilds Road £28,050.00 Programmed to Commence 15/12/25 6 Carriageway - Darvel West Donnington Street £16,800.00 Programmed to Commence 06/12/25 6 Carriageway - Darvel Jaimieson Road £17,400.00 £22,124.59 Complete – final measure 7 Carriageway - Mauchline Clarinda Crescent Complete – Awaiting Final measure. 7 Carriageway - Mauchline East Park Avenue £56,460.00 £38,854.02 7 Carriageway - Mauchline Southpark Avenue 7 Carriageway - Mauchline Welton Road £63,450.00 £48,497.46 7 Carriageway - Mauchline Mansfield Road Complete – Awaiting Final measure 8 Carriageway - Cumnock Latta Crescent £20,010.00 Programmed to Commence 12/01/26 8 Carriageway - Cumnock Nans Terrace £16,500.00 Programmed to Commence 24/11/25 8 Carriageway - Cumnock Lorimer Crescent £44,550.00 Programmed to Commence 01/12/25 8 Carriageway - Cumnock Hearth Place £24,000.00 Programmed to Commence 08/12/25 8 Carriageway - Cumnock Bank Avenue £21,420.00 Programmed to Commence 12/01/26 8 Carriageway - Logan Holmhead Crescent £36,600.00 Programmed to Commence 19/01/26 8 Carriageway - Logan Dixton Avenue £21,690.00 Programmed to Commence 19/01/26 9 Carriageway - New Cumnock Castlemains Avenue £42,000.00 Programmed to Commence 02/02/26
Page 16
Official 9 Carriageway - Dalmellington Church Hill/Melling Terrace £36,330.00 Programmed to Commence 12/01/26 9 Carriageway - Dalmellington Knowehead £41,820.00 Programmed to Commence 26/01/26 9 Carriageway - Ochiltree Gallowlee Avenue £20,490.00 Programmed to Commence 02/03/26 4 Footway – Hurlford Furnace Court £15,750.00 To be programmed 6 Footway – Galston Bridge Street £3,750.00 To be programmed 6 Footway – Darvel Glen Crescent £17,500.00 To be programmed EAC Lighting Capital Programme 2025/26 Town Location Work Type No of columns Estimated Programme Cost Comments Variance +/- Dalmellington Riecawr Ave, Area. Unreliable 5th Core. 22 £65,000 Completed 16 Jun 2025 3% Galston Maxwood Road. Unreliable 5th Core/Concrete columns. 10 £30,000 Completed 14 Jul 2025 6% New Cumnock Highpark Ave, Area. Unreliable 5th Core/Concrete columns. 19 £60,000 Completed 27 Aug 2025 0% Stewarton Lothian Rd, Area. Unreliable 5th Core 23 £60,000 Cancelled Kilmarnock Irvine Road Area. Column failures 8 £20,000 Completed 09 Oct 2025 Patna Netherhill Crescent. Concrete Columns 8 £25,000 Scheduled Jan 2026 £180,000 EAC LED Lighting Programme Update 2025/26 (works carried over from 2024/25) Town Lantern Amount Status Delivery / start install Install complete by Kilmarnock - Central 1400 In progress Mar 2024 Mar 2026 East Ayrshire - Decorative 350 75% complete Aug 2026
Page 17
Official tender to be awarded for next stage EAC LED Lighting Programme 2025/26 Programme completed conversions to date 15,267 Replacement programme 97% complete Overall LED units completed 20,910 LEDs now 98% of total EAC inventory EAC Bridge and Culvert Strengthening Programme 2025/26 Structure Reference Structure Name Proposed Works 2025/26 Estimate Comments Bridge Strengthening and Replacement A71/280 C80 Mathews Burn Culvert West Donnington St, Darvel Slab Replacement £250,000 Internal design ongoing. U751/10 Crossflats Bridge Replacement £40,000 Awarded to consultant to design replacement. Temporary bridge will be required during the works. U760/00 C93 Glenhead Bridge Replacement £60,000 Internal design ongoing, near tender ready. U740/10 Barbieston Bridge Replacement £60,000 SAC leading design. Award to consultant. Road Slips B713 South of Sorn £400,000 Works complete. B741 Coal Glen Embankment Slip Remediation Works £690,000 Discussions ongoing with SPEN. Works to be retendered ASAP U13 Aitket Road Slip Remediation Works £500,000 Contractor appointed works due to start January 2026. A713/60 C61 Polnessan Upper Bridge Culvert Extension £500,000 Contract docs with Procurement for review. Upgrade Works Identified from Inspections
Page 18
Official B705/10 C91 Cowan Place Culvert Part Replacement/Scour Repairs £60,000 Near tender ready. A70/130 W31 Thornwood Wall, Lugar Replacement £500,000 Near tender ready. Discussion regarding requirement for road closure ongoing. Works to be postponed to 26/27. A736/60 C84 Lochridge Culvert Masonry and Drainage Repairs £70,000 Works Complete. A71 Riccarton Viaduct Refurbish - expansion joint removal/replacement £100,000 Design ongoing to replace 1 failing expansion joint with asphaltic plug joints. Works to be carried out ASAP. A71 River Irvine Bridge Refurbish - expansion joint removal/replacement Design ongoing to replace 1 failing expansion joint with asphaltic plug joints. Works to be carried out ASAP. C85/10 Fenwick Bridge Masonry Refurbishment £40,000 Award to consultant to progress with assessment and detailed design. U729/00 C64 Hayholm Bridge Masonry and Scour Repairs £60,000 Internal design ongoing. C95/10 Furnace Road Bridge Arch Strengthening £100,000 Internal design ongoing. Parapet Upgrades A70/110 Causeyhead Bridge Parapet Repairs £60,000 Discussions ongoing regarding options to reduce disruption at Dumfries House. A736/50 Bloak Road Bridge Parapet Repairs £30,000 NAC/EAC boundary, EAC progressing design. Contract awarded. Other Various Investigative Works Topographical Survey, Paint Inspection etc £8,000 Annual cost of surveys/inspections. Principal Inspection Consultant Fees £100,000 Consultant fees for 24/25 PI’s Various Low Bridge Signage Sign Upgrades £40,000 Works near complete.
Page 19
Official EAC Traffic, Transportation and Road Safety Programmes 2025/26 Funding Source Project ID Location Project Description Detail Progress Allocation EAC Capital Road Safety Budget: £200,000 (£198,000 Road Safety + £2,000 Safer Neigh.) 22.23 A71 / Campbell Street Off Slip, Kilmarnock Junction signalisation Installation of new traffic signals, stopping up of Willock Street and new carriageway layout to improve capacity Works planned to start January 2026 £105,000 22.50 B741 Dalmellington to New Cumnock Road safety review General route review to identify safety measures Survey complete with video footage to be reviewed £2,000 22.38 Glaisnock Street, Cumnock Traffic calming Speed reduction/traffic calming measures Planned start January 2026 £15,000 22.15 VAS signs, various location Upgrades and new installations New contract to be implemented In progress £10,000 25.20 A713 - Waterside Road safety improvements 40mph repeaters, HFS gateway features and road markings upgrade Planned start January 2026 £25,000 24.05 Various Traffic calming Speed surveys Ongoing £10,000 25.03 / 25.16 Various Road safety improvements HFS Schemes Ongoing £33,000 24.20 B751 - Kilmaurs to Fenwick Route Review General route review, VAS improvements, Road Markings and Signage, Studs 75% complete with antiskid to be installed £125,000 25.11 A71 – Priestland Safer system improvements Vehicle restraint barriers Complete £75,000 25.13 A719 – Waterside Road Safety improvements VAS improvements , HFS and carriageway studs Planned start January 2026 £50,000 25.17 A70 – Dumfries House Road Safety improvements VAS improvements , HFS, carriageway studs and resurfacing Construction expected early 26 £60,000
Page 20
Official Rural Route Action Plans Budget: £359,000 £134,000 (EAC) + £225,000 (Dev. Contributions) 22.08 B778 Stewarton to Fenwick Road alignment improvements at three key locations Agreement to proceed with site 1 improvements Process started £359,000 Tier 1 Budget: £758,000 22.13 Grougar Road, Crookedholm Pedestrian crossing and road widening Installation of new crossing and layby Complete £99,000 23.07 Strawberrybank Road, Kilmarnock Pedestrian crossing Appraisal for new crossing point Ped counts low so project reduced to consideration of ped refuge island £10,000 23.10 St Germain Street, Catrine Pedestrian safety improvements Installation of bollards and TRO Works complete with TRO to be finalised £10,000 N/A Kilmarnock Green Infinity Loop Cycling Infrastructure Route 1 & 2, Sturrock St and MSCP Route 1 & 2 design placed on hold due to lack of funding, MSCP site redevelopment application submitted to ATIF 2025/26. Sturrock St modelling completed. £100,000 24.18 A759 West of Gatehead Pedestrian improvements Footway designs and build out Design work ongoing with Construction expected early 26 £30,000 25.15 B751 Kilmaurs to Knockentiber Pedestrian improvements Footway improvements Design work ongoing with Construction expected early 26 £30,000
Page 21
Official 24.28 Kilmarnock - Dundonald Road and Gargieston area Pedestrian improvements Footway designs and buildouts Onsite consultation to be completed prior to design work with Construction expected early 26 £30,000 23.12 A713 Bellsbank Rd, Dalmellington Traffic calming 1 x speed table Planned start January 2026 £10,000 25.12 A71 Priestland Traffic Calming and pedestrian crossing Planned start January 2026 £50,000 Irvine Road Kilmaurs Pedestrian improvements Design work ongoing with Construction expected Jan/Feb 2026 £35,000 Various location Various minor works projects To be Confirmed £100,000 25.09 Altonhill Avenue Kilmarnock Traffic Calming and road widening Jan 2026 £80,000 Various Locations Pedestrian improvements Installation of new crossing points and improve existing walking routes Mar 2026 £160,00 24.25 Main Street Stewarton Pedestrian crossing upgrade Jan 2026 £25,000 EAC Bus Infrastructure Budget: £645,000 22.51 Onthank Terminus, Kilmarnock Upgrades to existing infrastructure Improve crossing and boarding points Complete £20,000 22.52 Stewarton Terminus, Stewarton Upgrades to existing infrastructure Improve turning circle and boarding points Design stage in progress £20,000 Newmilns Road , Galston Upgrade to existing infrastructure Installation of new bus layby including shelter To be complete Mar 2026 £32,000
Page 22
Official Various locations Upgrade to existing infrastructure Bus shelter upgrades to various locations To be complete Mar 2026 £85,000 Newmilns Road , Newmilns Upgrade to existing infrastructure Installation of new bus layby including shelter To be complete Mar 2026 £32,000 Various Locations Upgrades to existing infrastructure Installation of bus priority traffic signals To be complete Mar 2026 £155,000 Irvine Road, Kilmarnock Upgrade to existing infrastructure Installation of new bus layby including shelter To be complete Mar 2026 £42,000 Glasgow Road, Kilmarnock Upgrade to existing infrastructure Relocation of bus stop to improve use including crossings To be complete Mar 2026 £57,000 Grassyard Road, Kilmarnock Upgrade to existing infrastructure Installation of raised kerbs to improve access/egress onto bus To be complete Mar 2026 £22,000 TBC Land purchase Land purchase for proposed park and ride site To be complete Mar 2026 £200,000 EAC Active Travel Budget £50,000 24.03 School Streets Programme Introduction of trial sites Three further schools to be trialled with further trials to be developed Live trials have commenced at Bellsbank and Dalrymple. Auchinleck in development. Further sites to be determined following completion of trial sites. £50,000
Page 23
Official Appendix 2 SOUTH AYRSHIRE COUNCIL PROGRAMMES SAC Carriageway Structural Maintenance Programme over two years 2024 to 2026 Route No Town Road Name Works Description Scheme Score Estimate d Cost Cost to Date Variance +/- Comments B734 Old Dailly Barr Old Dailly Old Dailly to Penkill + drainage improvements N/A £150,813 £163,932 -£13,119 Complete B7035 By Girvan Glendoune Houdston Road (Coalpots) Braetoll South + S Power shut down N/A £200,000 £206,251 -£6,251 Complete B743 By Mossblown Ayr / Mossblown? West from Brocklehill Farm 53 £249,002 £249,239 -£237 Complete C37 Auchincruive Barrackhall Gibbsyard 48 £123,861 123,873 -£12 Complete Uncl Tarbolton Springfield Road Garden Street to No 50 46 £54,275 £53,851 +£424 Complete B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton By Holebogs, S bend 59 £445,000 £440,506 +£4,494 Complete B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton From A70 at Hillhead south to C21 Craigs Road junction 56 B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton From Meadowhead Depot entrance south-wards 55 Complete B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton Bridge of Coyle to C2 52 B744 Annbank Weston Brae Full Length 53 £152,000 £207,822 -£55,822 Complete B744 Annbank Browns Crescent Weston Avenue Full Length Craighall Way to 101 Weston Avenue 53 56 U77 By Coylton Hole Road Full Length 46 £82,867 £83,064 -£197 Complete B7023 Maybole Crosshill Road Full Length 56 £74,687 £72,215 +£2,472 Complete Complete Complete B7023 Maybole St Cuthbert's Road Full Length 53 £30,669 £41,792 -£11,123 B7024 Maybole Alloway Road Redbrae to Bypass 51 £55,922 £96,288 -£40,366
Page 24
Official C122 By Maybole C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole School to new Bypass Ladycross to new Bypass 50 £58,095 £58,097 -£2 Complete B7023 Maybole Ballochbroe to Crosshill Dalhowan to C58 £275,435 £362,350 -£86,915 Complete A719 PH 2 By Maidens By Dunure Pennyglen/B7023 - Kirkoswald Road/Maidens, Maidens A719 Smithy Bridge/Dunure - Croy Brae, Dunure B7023 Enoch Lodge -Caravan Park Cemetery to Drumshang 67 £281,669 £326,746 -£45,077 Complete Complete A719 PH 1 By Maidens Pennyglen/B7023 - Kirkoswald Rd & Turnberry Rd /Maidens, Turnberry Morriston Farm to Jct Blawearie Maidens to Turnberry 56 £441,666 £540,857 -£99,191 Uncl Maybole Ashgrove Avenue Full Length £88,954 £102,985 -£14,031 Complete SAC - Carriageway Structural Maintenance Programme – New Sites identified for 2024 to 2026 B749 Troon Monktonhill Road Southwood jct to Isle of Pin 59 £210,000 £265,328 -£55,328 Complete. after excavation, additional material was required to regulate due to sand & soft spots localised
Page 25
Official to lots of areas in Troon B749 Troon Craigend Road Fullarton Drive railway bridge to South Beach 48 £167,500 £201,706 -£34,206 Complete Overspend same as Monktonhill Rd B749 Troon South Beach Lochend Road to Academy Street jct 54 £200,000 £307,540 -£107,540 Complete. Overspend same as Monktonhill and Craigend. C44 Dailly Dailly to Turnberry Farden 500m towards Drummock 39 £112,560 £71,137 +£41,422 Complete B7027 Barr Knowe Road Lochtonmill southwards £63,000 £53,406.44 +£9,593 Complete B734 Colmonell Colmonell to the A77 £106,560 £150,273 -£43,713 Complete B7023 Maybole C58 to Cemetary £297,606 £271,503 +£26,102 Complete A70 C39 Coylton Ayr Joppa Doonholm Road Hole Road jct to Pharmacy Alloway to The Loaning 35 43 £179,321 £155,377 +£23,944 Complete C145 Ayr Hillfoot Road Holmston Rd to Holmston Dr 54 £91,875 £123,733 -£31,858 Complete Uncl Maybole Queens Terrace/Chesney Grove/Kincraig Avenue Full Road 33 33 £166,275 £174,448 -£8,173 Complete Uncl Maybole Cargill Road Full Road 47 £46,900 £48,224 -£1,324 Complete C1 (STTS) Straiton Newton Stewart Road U8 towards Straiton to U57 44 £120,400 £119.293 +£1,107 Complete B7045 (STTS) Maybole Cassilis to Kirkmichael Rd Crorieshill Farm northwards for 360m 44 £46,750 £51,700 -£4,950 Complete Uncl Ayr Saltpans Road North from Glebe Road 46 £112,249 £118,940 -£6,691 Complete Uncl Prestwick Morris Road Full Road 43 £55,000 £107,345 -£52,345 Complete
Page 26
Official (presence of coal tar increased costs) Uncl Ayr Green Street Waggon Road to Crown Street 42 £130,000 £214,584 -£84,584 Complete (presence of coal tar increased costs) Uncl Prestwick Craigie Street Full length 39 £30,000 £36,725 -£6,725 Complete B744 By Annbank B744 Belston/A70 - Weston Avenue/Annbank, Ayr Auchincruive Junction to Glenview 52 £120,000 £139,872 -£19,872 Complete B742 By Maybole Dalrymple to Barnford Farm Dalrymple Road 46 £130,000 £138,058 -£8,058 Complete Uncl Maybole Hicks Avenue Full cway & fway 30 £104,000 £133,263 -£29,263 Complete Increased costs due to combining footway, kerbing C59 Colmonell Craigneil Road B734 to Bridge £67,000 £53,129 +£13,871 Complete Uncl Ayr Peggieshill (PH1) Dalmilling Rd to Nursery Rd 44 £92,000 £99,038 -£7,038 Complete Uncl Ayr Kincaidston (PH1) Marigold Sq to Honeysuckle Park 52 £185,000 £181,768 +£3,232 Complete Uncl Girvan Louisa Drive Knockcushion St to Duncan St £103,640 £91,410 +£12,230 Complete Uncl Ayr Peggieshill Rd (PH2) Nursery Rd to Fenwickland Ave 44 £100,000 £81,228 +18,772 Complete C74 By Ayr MacNairston Rd C105 to B742 junction 52 £102,000 £101,917.11 +£82.89 Complete B742 By Maybole Nether Culzean Dalrymple Rd Barnford farm to Nether Culzean 42 £145,000 £144,902 +£97.79 Complete Uncl Ayr Ellisland Square (Contains Coal Tar) Full Length 42 £145,000 145,996.28 -£996.28 Complete (presence of coal tar increased costs)
Page 27
Official Uncl Ayr Kincaidston Drive (PH2) Honeysuckle Park to Dalmellington Rd 52 £135,000 £137,176.04 -£2,176.04 Complete B742 Mossblown Sandyford Road From a point 180 metres east of A719 junction eastwards for 680m 53 £183,751 189,826.06 -£6,074.06 Complete Uncl Ayr Dalmilling Road Harthall to Mainholm Rd 37 £275,000 £255,046.82 +£19,953.18 Complete – final measure (presence of coal tar increased costs) Uncl Prestwick Bellevue Road (TO BE TESTED) From Main Street to Adamton Road £105,687 2026/27 Uncl Girvan Todd Street (TO BE TESTED) Full length 31 £32,894 2026/27 Uncl Girvan Fauldribbon Road (TO BE TESTED) Full length 34 £31,813 2026/27 Uncl Girvan B741 Linfern Road (TO BE TESTED) NO.79 to no.3 near Main Street 29 £100,517 Commence 26/01/26 Uncl Maybole Carrick Street (TO BE TESTED) Ladyland Rd to B77 33 £26,130 2026/27 Uncl Maybole Wellington Street (TO BE TESTED) Ladyland Rd to Carrick St 30 £18,090 2026/27 Uncl Maybole Manse Street (TO BE TESTED) Drumellan St to Abbott St £20,100 2026/27 Uncl Girvan Hamilton Street (TO BE TESTED) Church Sq to Bridge St 46 £49,655.55 Commence 09/02/26 Uncl Ayr Chapel Park Road Full length 40 £55,984 2026/27 Uncl Prestwick St Cuthbert’s Rd St Andrew’s Ave to Kirklandholm £38,587 2026/27 SAC – Overlay surfacing (potential future surface dressing) U39 Dailly Hawkhill Road Old Dailly from number 1 to number 12 N/A £125,000 £21,491.43 SAC - Footway Structural Maintenance Programme over two years 2024 to 2026 C17 Tarbolton Westport Footway North side 28 £17,370 £24,984 -£7,644 Complete
Page 28
Official Uncl Prestwick Hunters Avenue South from Heathfield Road, west side 23 £7,500 £5,393 +£2,107 Complete Uncl Troon Morven Drive Cessnock Rd to Dundonald Rd (Northside) £15,072 £28,820 -£13,748 Complete C151 Dailly Woodside Both sides from Back St and Hadyard Terr 30 £20,400 £17,147 +£3,253 Complete Uncl Crosshill Newton Street Church Side of road 30 £15,795 £14,440 +£1,355 Complete Uncl Dailly Hadyard Terrace Inside footway + part outer section 28 £54,400 £20,110 +£34,290 Complete SAC - Footway Structural Maintenance Programme – sites identified for 2024 to 2026 Uncl Mossblown Martin Avenue Mossblown 28 £28,300 £30,829 -£2,529 Complete B744 Annbank Weston Brae Full Length 28 £10,700 £5,761 +£4,939 Complete B730 Dundonald Drybridge Road Bowling Green to Kilnford Dr 28 £18,963 £15,890 +£3,073 Complete Uncl Ayr Bellevue Crescent Full Length 34 £30,000 £24,299 +£5,701 Further to tree inspection, scope of work amended to patching - Complete Uncl Maidens Ardlochan Road Full Length 30 £21,000 To be re- assessed following Utility works. Likely to carry forward to 2026/27 Uncl Dailly Church Crecent Odd numbers full length 30 £20,000 Complete – final measure Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget allocation B743 Mossblown Mauchline Road Fourways to railway bridge north side 28 £15,300 2026/27
Page 29
Official Uncl Ayr Lochpark Slab replacement 23 £20,425 2026/27 SAC - Lighting Programme 2025/26 Town Location Work Type No of columns Estimated Programme Cost Comments Variance +/- Ayr Ayr - Old Hillfoot Road, Hillfoot Crescent & Souter Place Old steel columns & unreliable 5th Core 5 £30,000 Complete Ayr Cunningham Crescent & Area Unreliable 5th Core Supplies 16 £40,000 Complete Troon Concrete Column Replacements Ph3 Old deteriorated concrete columns 43 £55,000 Complete £125,000 SAC - Traffic, Transportation and Road Safety Programmes 2025/26 (i) Road Safety Programme (ii) Safer Neighborhoods Town/Route Location Proposed Scheme Progress Various Various locations Various schemes (TBC), included in the FY25/26 programme, as follows: • Route Action Plan for the B743 at St Quivox; • B743 review at Failford Bridge; • Speed reduction measures at Coalpots Road at The Avenue; • Loans 20mph – further measures to improve compliance; • Road Safety scheme, Links Road, Prestwick The ARA are now progressing the schemes as identified within the current financial year.
Page 30
Official Town Location Proposed Scheme Progress Phase 4 20mph schemes Various roads (TBC) 20mph speed limit schemes Phase 4 schemes are planned to include Coylton, Maybole and Girvan (to align with Transport Scotland’s Trunk Road speed reduction proposals) Various Various locations Vehicle activated signs upgrade Pending implementation of new contract, and extents of upgrades will be subject to budget. (iii) Rural Route Action Plans Route Location Proposed Scheme Progress B743 Between the A77(T) and Auchincruive (St Quivox) TBC Listed under RSIF schemes above – subject to confirmation of funding. (iv) Active Travel Infrastructure – ATIF & Sustrans Town Location Proposed Scheme Progress Various Various locations Various smaller schemes under Tier 1 funding, anticipated t include: • New pedestrian crossing facilities – A79 Prestwick; • Improved crossing points, Bradan Road, Troon; • New pedestrian crossing, Deveron Road, Troon; • Pedestrian Crossing Enhancements, Troon – increased ferry traffic response Currently finalising a package of schemes to be progressed during the current financial year making use of the Tier 1 grant award.
Page 31
Official Loans From Buchan Road to the A759 Loans to Troon Phase 3 Funding application unsuccessful, new application submitted to ATIF for 2025/26 Loans From Dundonald Road to Buchan Road Loans to Troon Phase 2 £24,500 received to install permanent monitoring equipment Dundonald To the northern side of the A759 Dundonald to Barassie Phase 1 Award received to treat Japanese Knotweed on-site, full construction funding application submitted to ATIF for 2025/26. Various Various Various Funding application unsuccessful, new application submitted to ATIF for 2025/26 Girvan Quay to Grangeston Girvan to Grangeston £27,378 received to complete RIBA Stage 1, Ayr Town Centre Accessible Ayr £778,780 received to complete RIBA Stage 4 of Route 1 Phase 1 Ayr-Girvan Ayr to Girvan Culzean Way £47,755 received to complete RIBA Stage 1 Coylton Coylton Primary Access for All – Coylton £27,378 received to install permanent monitoring equipment Ayr, Prestwick & Troon NCN7 NCN Barrier Removal £113,500 received to remove barriers from the NCN7 in Ayr Prestwick & Troon to make the route inclusive. Prestwick, Troon & Barassie NCN7 from Prestick Station to A759 Barassie Prestwick to Barassie £82,979 received to complete RIBA Stage 2 Dundonald Junction of A759/B730 Dundonald Cross £80,000 received to install signals at the junction of the A759/B730 SAC Structures Capital Programme 2025/26 (Includes works carried forward from 2023/24/25) Description Work Type Estimated Programme Cost Comments Variance +/- A79-30 Victoria Bridge Concrete Repairs and Painting £432,776 Completed 0 A79-40 John Street, Ayr, Railway Bridge Parapets £362,000 Design Phase. -£293,674
Page 32
Official FB.AYR-70 River Doon Cycleway Footbridge (Millenium Br) Refurbishment £145,000 Design Phase Tender Documents completed and Marine Licence applied for. -£139,903 U740-10 Barbieston Bridge Replacement Design £86,820.00 Design Phase 50% - 50% EAC / SAC funded project as this is a boundary bridge. -£74,619 Various Locations Vehicle Restraint Barrier Renewal £50,000 Design Phase Contract awarded works ongoing +£50,000 Various Locations Cattle Grid Renewal Programme £33,600 Design Phase Contract awarded works ongoing £-33,600 C12 Dunure Station Road Dunure, Slope Stabilisation £130,000 A 70m long gravity retaining wall option has been selected as the most optimum solution. Contract awarded pre-start process ongoing. -£110,282 Girvan Harbour Girvan Harbour South Pier Repairs £136,000 The South Pier Quay has been assessed to have a load carrying capacity of 0.5 tonnes per square metre. Following dive surveys undertaken earlier this year the option chosen to extend the life of the structure is steel plate repairs to the existing sheet piles and grouting of the voids. Completion and submission of the contract documentation was delayed in order that the significant damage caused to the South Pier Quay by the Q- Varl boat, when it broke its moorings in a storm, could be assessed and any repairs required could be included in the contract documents. Tenders to be issued in August with works completed by the end of 2025. -£124,197
Page 33
Official Contract award delayed until budget transfer from Timber Jetty Sheet Piles to South Pier Quay budget is approved a Cabinet 25th November. Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles £504,887 The sediment transfer model has been completed including options to deal with the defective sheet piling. The recommended option is to replace only the piling on the curved section from the lifeboat station. Contract documentation substantially complete and will be issued once tenders for the South Pier Quay works have been returned and costs are known. The South Pier Quay works are considered a priority which is why the request to transfer budget has been made to SAC Cabinet. - £494,684 £1,881,083
Page 34
Official Appendix 3 EV PUBLIC CHARGERS EAST AYRSHIRE CPS ID Type Make Location 51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU 50821 22kw eVolt Foregate Noth Car Park, Kilmarnock, KA1 1LU 51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH 52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW 70279 Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP 60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR 52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU
Page 35
Official 52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE 52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG 52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS 52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB 52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ 52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB 52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ 52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ 52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY 53778 Rapid eVolt Main Street Car Park, Muirkirk 53775 22kw eVolt Rose Reilly Sports Centre, Stewarton 53776 7kw eVolt Standalane Car Park, Stewarton 60786 7kW eVolt Academy Street, Hurlford 60792 22kW eVolt Drongan Centre car park, Mill of Shield Road 51210 22kW eVolt Carnshalloch Avenue car park, Patna 60950 22kW eVolt New Cumnock Outdoor Swimming Pool car park 60954 22kW eVolt Gatehead Road car park, Crosshouse 61021 7kW eVolt East Ayrshire Community Hospital, Cumnock 61022 7kW eVolt East Ayrshire Community Hospital, Cumnock 61983 7kW eVolt Morton Place car park, Kilmarnock
Page 36
Official 61984 7kW eVolt Morton Place car park, Kilmarnock 61985 7kW eVolt Morton Place car park, Kilmarnock 62184 7kW eVolt Browns Road car park, Newmilns 61886 22kW eVolt Sturrock Street, Kilmarnock 62938 7kW eVolt New London Road car park, Kilmarnock SOUTH AYRSHIRE CPS ID Type Make Location 51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW 51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU 70278 Rapid eVolt Burns Statue Square, Ayr, KA7 UT 52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN 52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY 50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ 50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF 52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG 70280 Rapid eVolt Girvan Harbour, Girvan, KA26 9AG 52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR 52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH 52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU 52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL 53774 Rapid eVolt Academy Street, Troon 53773 Rapid eVolt Lodge Road Car Park, Turnberry
Page 37
Official 53777 22kw eVolt Burnside Road, Monkton 60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly 60081 22kw eVolt Inches Close car park, Maybole 61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton 61986 22kw eVolt Dundonald Primary School car park, Dundonald 60086 22kw eVolt Mossblown Activity Centre car park, Mossblown 60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald 61979 7kW eVolt Chalmers Arcade car park, Girvan 61980 7kW eVolt Chalmers Arcade car park, Girvan 61981 7kW eVolt Chalmers Arcade car park, Girvan 62000 22kW eVolt Barrhill Community car park, Main Street, Barrhill
Page 38
Official Appendix 4 SAC WARD INVESTMENT & PROMENADE PROGRAMME 2025/26 incl. works carried over from 2024/25 Roads Maintenance Unit LOCATION Description PO Value Cost to Date variance +/- Comment Troon Resurfacing of Troon Esplanade (Ph.3). Measuring works on site Prestwick Repair / renew steps to Boydfield Gardens £85,000.00 Complete – Final measure Prestwick Install power supply to Boydfield Gardens and Links Road Scottish Power quote to be received. Followed by agreed site start date Ayr North Provision of Bike Shelter at Lochside Community Centre £15,000.00 Bike shelter currently being fabricated Ayr East Glencairn Park – footpath upgrade Quote issued for approval Ayr East Car parking provision Peggieshill Road Quote provided, consultation required Ayr West Promenade raised footway works Feasibility study ongoing with Professional Design Services Kyle Install a History Park at Loans Community Hall and link to Smugglers trail Car park quote issued for approval. Garden and block paving quote being prepared Kyle Improve accessibility at Mossblown village hall Quote issued for approval Kyle Link path from Collins Drive to Collenan Avenue, Loans Quote provided, consultation required Kyle Resurface Bowling Green Car Park, Symington Quote provided, currently being assessed
Page 39
Official Kyle Construct new footpath at southern edge of Collenan Reservoir On Hold. Scope of works changed Design and Flooding Section Troon Shore Defence Structural Stabilisation £10,000.00 £15,432.00 -£5,432.00 Complete Citadel Footbridge Refurbishment Remove and renew timber deck parapet elements. Surface prepare and paint. Remove or repair lighting £140,000.00 £259,957.00 -£119,957.00 Complete Girvan Boating Pond Refurbishment Install new stainless steel reinforced concrete base slab to reduce water leakage. £175,000.00 £170,641.00 £4,359.00 Complete Dunure Castle Footbridge Replacement Replace existing small span concrete footbridge with a larger footbridge with a view and good aesthetics £230,000.00 Ongoing. Lighting Section Ayr East Glencairn Park – Install footpath lighting £23,000.00 Design complete. Tender issued Ayr West Replacement of column lighting on Ayr Promenade £145,000.00 Column and street lighting works complete and operational. Additional works to install public Wi-Fi ongoing Ayr West New Bridge & Auld Brig. Design fees for installation of architectural floodlighting to structures £50,000.00 Exploring other means to procure Consultant as delay with SXL Technical & Consultancy Framework Ayr West Wrap round decorative lighting to columns on Ayr Promenade SAC PO to be issued
Page 40
Official Appendix 5 ASH DIE BACK 2025/26 East Ayrshire 2024 High Risk Works_EAC Highway South Ayrshire 2024 High Risk Works_SAC Highway