North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
Ayrshire Shared Services Committee
A Meeting of the Ayrshire Shared Services Committee of North Ayrshire Council will
be held in the Council Chambers, Ground Floor, Cunninghame House, Irvine,
KA12 8EE on Friday, 05 September 2025 at 10:00 to consider the undernoted
business.
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.  Where possible, the meeting will be live-streamed
and available to view at https://north-ayrshire.public-
i.tv/core/portal/home. 
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda.
2 Revenue Financial Monitoring Report
Submit report by the Chief Financial Officer and Head of Finance and
ICT on the revenue budget monitoring position for the year to 31 March
2025, for the Ayrshire Roads Alliance and the budget for 2025-26 (copy
enclosed).
3 Internal Audit Annual Update
Submit report by the Chief Auditor – East Ayrshire Council on the internal
audit work for the Ayrshire Roads Alliance (copy enclosed).
4 Performance Scorecard
Submit report by the Head of Ayrshire Roads Alliance on the progress
made to date against the Performance Scorecard (copy enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
5 Risk Report & Register
Submit report by the Head of Ayrshire Roads Alliance on the management
of risk associated with the Ayrshire Roads Alliance (copy enclosed).
6 Roadworks Programme 2025/2026
Submit report by the Head of Ayrshire Roads Alliance on the progress of
work through the roads improvement programmes within East Ayrshire and
South Ayrshire for financial year 2025 to 2026 (copy enclosed).
7 Improvement Action Plan
Submit report by the Head of Ayrshire Roads Alliance on the management
of the Improvement Action Plan by the Ayrshire Roads Alliance (copy
enclosed).
8 Winter Service Review Progress
Submit report by the Head of Ayrshire Roads Alliance on the review of the
winter service (copy enclosed).
9 Asset Management Plan Update
Submit report by the Head of Ayrshire Roads Alliance on the updated
Asset Management Plan for the road networks of East and South Ayrshire
(copy enclosed).
10 Urgent Items
Any other items which the Chair considers to be urgent.
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
Webcasting
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at https://north-ayrshire.public-
i.tv/core/portal/home, where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
Generally, the press and public will not be filmed. However, by entering the
Council Chambers and using the press or public seating area, you
acknowledge that you may be filmed and that any information pertaining to
you contained in the video and oral recording of the meeting will be used
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. In
making this use of your information the Council is processing data which is
necessary for the performance of a task carried out in the public interest.
If you have any queries regarding this and, in particular, if you believe
that use and/or storage of any particular information would cause, or be
likely to cause, substantial damage or distress to any individual, please
contact dataprotectionofficer@north-ayrshire.gov.uk
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
Ayrshire Shared Services Committee Sederunt
North Ayrshire Council
Marie Burns
Joe Cullinane
Scott Davidson
Cameron Inglis
East Ayrshire Council
Barry Douglas
Jim McMahon
Douglas Reid
Neill Watts
South Ayrshire Council
Alec Clark
Martin Kilbride
Craig Mackay
Philip Saxton
Chair:
Apologies:
Attending:
4

Page 5

Official
THE AYRSHIRE SHARED SERVICES JOINT COMMITTEE -  
5 SEPTEMBER 2025 
Report by Chief Financial Officer & Head of
Finance & ICT 
AYRSHIRE ROADS ALLIANCE
REVENUE FINANCIAL MONITORING REPORT 
Purpose of report 
1. The purpose of this Report is to update the Joint Committee on the revenue
budget monitoring position for the year to 31 March 2025, for the Ayrshire
Roads Alliance and the budget for 2025-26. 
Recommendations 
2.  It is recommended that the Joint Committee 
(i) Note the financial management position of the Ayrshire Roads
Alliance for 2024-25.
(ii) Notes details of the 2025-26 Ayrshire Roads Alliance revenue budget
(iii) Requests a further financial update at the next meeting of the Joint
Committee.
(iv) Otherwise, notes the content of this report 
Background 
3. The Joint Committee approved a Report on 23 May 2014 describing the budget
monitoring arrangements for the Ayrshire Roads Alliance. 
4. As part of the Detailed Business Case the service budget is split between
strategic service delivery and local service delivery. This separates out the
core/recurring costs of service delivery from the local service costs at a single
Council level. This ensures that decisions on the level of local spend remain
with local Members and ensures that the local Members retain control of their
local roads budgets. Appendix 1 provides a breakdown of this split. 
5. At its meeting of 19th February 2016, Committee agreed a change to how
Strategic Service Delivery would be allocated between the two Councils. A
smaller group of core Strategic Delivery staff have been identified and their
costs continue to be split equally. The remaining Strategic Delivery costs would
be apportioned in line with Local Delivery budget inputs plus actual capital
expenditure in-year.   
Agenda Item 2
5

Page 6

Official 
Budget Monitoring Position 
6. The overall outturn for 2024-25 is £1.209m greater than budget. 
7. Strategic Delivery out-turn is £0.211m less than budget. 
Strategic Service Delivery Combined
(£m)
Initial Budget 3.411
Probable Outturn 3.200
Probable Variance (0.211) 
8. East Ayrshire Local Delivery out-turn is £0.551m greater than budget and South
Ayrshire Local Delivery £0.869m greater than budget. 
9. Summary information is provided in the table below. A full budget monitoring
statement, including reasons for major variances is attached at Appendix 2.   
Service Division
Annual Estimate
2024/25           
£m
Projected
Actual to 31/3/25            
£m
Variance
(Favourable) /
Adverse       
£m
STRATEGIC DELIVERY 3.411 3.200 (0.211)
LOCAL DELIVERY - EAST AYRSHIRE 5.699 6.250 0.551
LOCAL DELIVERY - SOUTH AYRSHIRE 4.221 5.090 0.869
TOTAL 13.331 14.540 1.209 
10. The position for each Council is shown below: 
EAC
(£m)
SAC
(£m)
TOTAL
(£m)
Strategic Delivery (0.222) 0.011 (0.211)
Local Delivery 0.551 0.869 1.420
2024-25 Variance 0.329 0.880 1.209  
11. To address the financial position, interventions have been put in place across
ARA to apply financial restraint.  These interventions will be challenging and
will require an increased level of financial control and monitoring to ensure
that their implementation has the desired impact. It is proposed that going
forward and until further notice: 
• A freeze is placed on the filling of all non-essential vacancies;
• An increased level of authorisation by Head of ARA is put in place for all
orders and expenditure above a specific level;
• Head of ARA is required to undertake detailed monthly monitoring of
6

Page 7

Official
expenditure to ensure robust review of essential spend.
• All contracts currently being tendered or appraised are to be
reconsidered by Head of ARA regarding continued need and availability
of resources. 
Progress will be reported to future meetings of Joint Committee. 
Timber Transport 
12. At the meeting of the Joint Committee on 23rd June 2017, further information
was requested in relation to timber transport funding. The undernoted table
provides an analysis of relevant project and Timber Transport contributions for
2024-25. 
2024-25
Actual to
31/3/23
(£m)
South Ayrshire 
Expenditure on Projects 0.338
Timber Transport
Contribution
0.159 
BUDGET REALIGNMENT 
13. In June 2017 South Ayrshire Council Internal Audit issued a report –
“Ayrshire Roads Alliance: Review of South Ayrshire Council Monitoring
Procedures”. 
14. The report contains a recommendation “Executive Director (Economy,
Neighbourhood and Environment) to request ARA management to present a
budget statement showing any adjustments made between subjective budget
headings to the ASSJC for information”. 
15. This relates to the setting of 2025-26 ARA budgets. The budget is created by
adding inflation and savings targets to a base budget (the base budget being
the 2024-25 budget). The budget is then discussed with ARA management
who have the opportunity to move funds based on the anticipated spend in
the forthcoming year. In order to facilitate this exercise ARA management also
considered 2024-25 outturn figures. No changes were made to Strategic,
Local Delivery – East or Local Delivery – South net expenditure budget
allocations. 
7

Page 8

Official
16. An analysis of budget movement between 2024-25 and 2025-26 budget
allocations along with an explanation of those movements is provided at
Appendix 3. 
Implications
17. 
Implications Yes No Paragraph number
in the report
1. Policy/Strategic Planning Yes  18
2. Governance Yes  19
3. Human Resources Yes  20
4. Equality and Fairer Scotland Duty  No 
5. Financial Yes  21
6. Risk Yes  22
7. Community Wealth Building  No 
8. Net Zero  No 
Policy/strategic planning implications 
18. The work undertaken by the Ayrshire Roads Alliance aligns with the
Community Plan for East Ayrshire Council and the Council Plan for South
Ayrshire Council. 
Governance implications 
19. The work of the Ayrshire Roads Alliance is undertaken in accordance with 
relevant legislation. 
Human resources implications 
20. The establishment of the Ayrshire Roads Alliance is dependent on the
available budget. Available budget and human resource requirements will be
reviewed as part of budget monitoring. 
Financial implications 
21. The available revenue budget for the Ayrshire Roads Alliance for 2024-25 was
£13.331m. The baseline budget for 2025-26 is £12.930m. The budget will
continue to be monitored and reported to the Joint Committee. 
Risk implications 
22. Appropriate financial monitoring arrangements are in place to mitigate risk. 
This is included in the Ayrshire Roads Alliance Risk Register.  Regular
meetings are held between relevant finance staff and the Ayrshire Roads
Alliance. 
8

Page 9

Official
Appendices (if applicable) 
Appendix One - Split between Strategic and Local Service Delivery
Appendix Two - Financial Monitoring Report
Appendix Three – Analysis of Movements in Budgets 2024-25 to 2025-26 
Background papers 
None 
Person to contact 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance
Tel No: 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
Implementation Officer 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance
Tel No: 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
9

Page 10

CLASSIFICATION: PUBLIC 
Appendix 1 – Split Between Strategic and Local Service Delivery
Strategic Service Delivery Local Service Delivery
Transportation, Development Control
and Road Safety
Local Transport Strategy; Transportation
Policy; Road Safety Plan; Travel Planning,
Cycling Strategy; Planning Applications;
Road Construction Consents; Development
Planning; Council/Partner  Liaison; Section
75 Agreements;  Road Safety Schemes;
Road Safety Audits;  School Travel Plans;
School Crossing Patrol; Road Safety
Education. 
Transportation, Development
Control and Road Safety
Maintenance of Bus Shelters; Split
Cycle Offset Optimisation Technique
(SCOOT) systems (an adaptive
control system for controlled road
crossings); Development Control;
Bus Shelter Advertising;
Shopmobility; Construction of Road
Safety Schemes. 
Asset, Traffic and Parking
Asset Management Plan; Roads
Improvement Plan; Infrastructure Surveys;
Inventory Management; Scottish Roadworks
Register; Issue of Permits; Performance
Monitoring; Accident Investigation and
Prevention; Traffic Orders; Traffic Counts;
and Parking Strategy. 
Asset, Traffic and Parking
Maintenance of Traffic Signals,
Traffic Signs; Car Park Maintenance
and Parking Enforcement.
Design and Environment
Flood Risk Management Strategy; Flood
Risk Management Plans; Watercourses;
Flood Mitigation; Coastal Protection;
Inspection  of Piers & Harbours; Bridge
Inspections and Maintenance; Structural
Assessments; Technical Approval; 
Abnormal Load Routing; and Design of
Major and Minor Road Schemes and
Improvements. 
Design and Environment
Maintenance of Watercourses,
Bridges, Retaining Walls, Piers and
Harbours. 
Operations
Carriageway Inspections; Winter Service
Planning; Programming of Proactive,
Reactive and Cyclic Maintenance; Street
Lighting Design and Management; and
Festive Lighting.
Operations
Proactive, Reactive, Cyclic
Maintenance of Roads and
Footways; Winter and Weather
Emergency Service; Proactive and
Reactive Maintenance of Streetlights;
Electricity costs for streetlights. 
Support Services        
HR, Finance, ICT, and Administrative
Support. 
10

Page 11

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY
CLASSIFICATION: OFFICIAL-PROTECT 
SERVICE SUMMARY - OVERVIEW POSITION 
The outturn for Ayrshire Roads Alliance at 31st March 2025 was £1.209m greater than
budget. 
Actual
Expenditure
as at P12           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Service Division Annual
Estimate
2024/25           
£m
Actual to
31/3/25            
£m
Variance
(Favourable) /
Adverse       
£m
3.200 93.8% STRATEGIC DELIVERY 3.411 3.200 (0.211)
6.250 109.7% LOCAL DELIVERY - EAST AYRSHIRE 5.699 6.250 0.551
5.090 120.6% LOCAL DELIVERY - SOUTH AYRSHIRE 4.221 5.090 0.869
14.540 109.1% TOTAL 13.331 14.540 1.209    
EARMARKED FUNDS TO BE CARRIED FORWARD      
14.540 109.1% TOTAL INCLUDING EARMARKED FUNDS 13.331 14.540 1.209 
STRATEGIC DELIVERY 
This variance reflects a number of employee vacancies and turnover within the service
(£0.217m), a budget for unfunded superannuation costs within ARA – South which will not
be required (£0.100m) and employee recharges (£0.103m), along with a saving on
insurance costs (£0.086m). 
This is partly offset by a shortfall in income (£0.259m) 
LOCAL DELIVERY – EAST AYRSHIRE
This variance mainly reflects shortfalls in income particularly in roads maintenance
(£0.564m), capital fees (£0.217m) and parking (£0.152m), along with winter maintenance
costs (£0.249m), overtime (£0.060m) and additional sub-contractor costs (£0.046m). 
This is partly offset by vacancies, particularly within Roads Maintenance (£0.602m) and
employee recharges in respect of cross boundary working (£0.139m). 
LOCAL DELIVERY – SOUTH AYRSHIRE
This variance mainly reflects shortfalls in parking income (£0.440m) and pier dues
(£0.043m) along with street lighting electricity (£0.377m), subcontractors (£0.746m),
additional overtime costs (£0.125m), cross boundary working (£0.134m) 
This is partly offset by vacancies/turnover (£0.339m), and roads maintenance income
(£0.507m). 
11

Page 12

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY
CLASSIFICATION: OFFICIAL-PROTECT 
STRATEGIC DELIVERY 
Actual
Expenditure
as at P12           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Service Division
Annual
Estimate
2024/25           
£m
Actual to
31/3/25            
£m
Variance
(Favourable) /
Adverse       
£m
3.208 88.1% EMPLOYEE COSTS 3.643 3.208 (0.435)
0.045 80.4% PREMISES COSTS 0.056 0.045 (0.011)
0.058 223.1% TRANSPORT COSTS 0.026 0.058 0.032
0.688 91.9% SUPPLIES & SERVICES 0.749 0.688 (0.061)
0.000 0.0% THIRD PARTY PAYMENTS 0.000 0.000 0.000
0.005 0.0% DEBT CHARGES 0.000 0.005 0.005
4.004 89.5% TOTAL EXPENDITURE 4.474 4.004 (0.470)
(0.804) 75.6% INCOME (1.063) (0.804) 0.259
3.200 93.8% NET EXPENDITURE 3.411 3.200 (0.211)    
EARMARKED FUNDS TO BE CARRIED FORWARD      
3.200 93.8% TOTAL INCLUDING EARMARKED FUNDS 3.411 3.200 (0.211) 
12

Page 13

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
Projected
Variance at     
31 March
2025
(£m)
Strategic Delivery            
(0.435) 
(0.011)               
0.032 
(0.061) 
0.259 
0.005
Employee Costs
This variance reflects vacant posts and turnover (£0.217m), a budget for
severance costs within ARA – South which will not be required (£0.100m),
employee recharges, mainly to local-delivery and capital programme
(£0.103m) and a saving on training costs (£0.019m). 
Premises Costs
This variance mainly reflects reduced non-domestic rates charges. 
Transport Costs
This variance mainly reflects additional vehicle and plant hires (£0.012m),
vehicle repairs (£0.008) along with additional expenditure on fuel and EV
charging (£0.009m). 
Supplies & Services
This variance reflects a saving on insurance premiums (£0.086m) mainly
in relation to ARA-South, along with reduced expenditure on EV charging
costs (£0.018m) and a reduction in road safety training materials
(£0.009m). This is partly offset by computer related expenditure
(£0.037m) and subscriptions (£0.012m). 
Income
This variance mainly reflects a shortfall in fee income (£0.157m) reflecting
reduced expenditure on Capital Programme and reduced income from
permits and notices (£0.009m), along with inspection fees, penalty
notices, temporary traffic regulation orders and temporary road closures
(£0.092m), mainly as a result of an increased income target which wasn’t
achieved. 
Other Variances
This represents other non-material variances within Strategic Delivery.
(0.211) Total reported variance 
13

Page 14

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
LOCAL DELIVERY – EAST AYRSHIRE 
Actual
Expenditure
as at P12           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Detail Annual
Estimate
2024/25           
£m
Actual to
31/3/25            
£m
Variance
(Favourable) /
Adverse       
£m
2.636 77.7% EMPLOYEE COSTS 3.392 2.636 (0.756)
0.277 98.2% PREMISES COSTS 0.282 0.277 (0.005)
1.001 100.9% TRANSPORT COSTS 0.992 1.001 0.009
3.860 133.3% SUPPLIES & SERVICES 2.896 3.860 0.964
1.702 102.8% THIRD PARTY PAYMENTS 1.656 1.702 0.046
0.338 105.3% DEBT CHARGES 0.321 0.338 0.017
9.814 102.9% TOTAL EXPENDITURE 9.539 9.814 0.275
(3.564) 92.8% INCOME (3.840) (3.564) 0.276
6.250 109.7% NET EXPENDITURE 5.699 6.250 0.551    
EARMARKED FUNDS TO BE CARRIED FORWARD      
6.250 109.7% TOTAL INCLUDING EARMARKED FUNDS 5.699 6.250 0.551 
14

Page 15

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
Projected
Variance at   
31 March
2025
(£m)
Local Delivery - East Ayrshire 
(0.756) 
0.964                                                                                                              
0.046 
0.017               
0.276 
0.004
Employee Costs
This variance represents vacant posts and turnover (£0.602m),
particularly within Roads Maintenance Unit, modern apprentices
(£0.089m), employee recharges in respect of cross boundary working
(£0.139m). This is partly offset by additional overtime (£0.060m) and
standby (£0.024m). 
Supplies & Services
This variance mainly reflects additional expenditure on EV electricity
(£0.507m) which is rechargeable to users, winter maintenance materials
(£0.249m) and security at Kilmarnock Bus Station (£0.163m) a portion of
which is rechargeable, along with additional computing expenditure
(£0.036m). 
Third Party Payments
This variance reflects additional sub-contractor costs within Roads
Maintenance (£0.022m) and Street Lighting (£0.056m). This is partly
offset by a saving on car park (£0.022m) costs. 
Debt Charges
This variance reflects higher debt charges for LED replacement projects
(£0.053m) offset by lower vehicle debt charges (£0.036m) 
Income
This variance reflects shortfalls in roads maintenance (£0.564m),
reduced income due to slippage in capital programme (£0.217m) and an
under recovery of parking (£0.152m) income. This is partly offset by EV
charging income (£0.410m) and rechargeable income (£0.224m) within
design and traffic. 
Other Variances
This represents other non-material variances within Local Delivery
0.551 Total reported variance
15

Page 16

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
LOCAL DELIVERY – SOUTH AYRSHIRE 
Actual
Expenditure
as at P12           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Service Division Annual
Estimate
2024/25           
£m
Actual to
31/3/25            
£m
Variance
(Favourable)
/ Adverse       
£m
2.480 96.5% EMPLOYEE COSTS 2.570 2.480 (0.090)
0.302 146.6% PREMISES COSTS 0.206 0.302 0.096
1.241 111.1% TRANSPORT COSTS 1.117 1.241 0.124
2.676 127.9% SUPPLIES & SERVICES 2.093 2.676 0.583
1.947 162.1% THIRD PARTY PAYMENTS 1.201 1.947 0.746
0.206 96.7% DEBT CHARGES 0.213 0.206 (0.007)
8.852 42.5% TOTAL EXPENDITURE 7.400 8.852 1.452
(3.762) 118.3% INCOME (3.179) (3.762) (0.583)
5.090 120.6% NET EXPENDITURE 4.221 5.090 0.869    
EARMARKED FUNDS TO BE CARRIED FORWARD      
5.090 120.6% TOTAL INCLUDING EARMARKED FUNDS 4.221 5.090 0.869 
16

Page 17

Official#
Appendix 3
Ayrshire Roads Alliance
Analysis of Movements in Budgets 2024-25 to 2025-26
Strategic Delivery
Detail
Annual
Estimate
2024/25           
£m
Annual
Estimate
2025/26          
£m
Movement
2024-25 to
2025-26 Explanation of Movement
EMPLOYEE COSTS
3.577 3.713 0.136
Movement mainly reflects  payroll inflation, including the impact of additional National
Insurance contributions (£0.183m). This is partly offset by a budget realignment based on
2024-25 outturn and discussion with the service (£0.047m).
PREMISES COSTS
0.042 0.030 (0.012) Movement mainly reflects a budget realignment based on 2024-25 outturn and discussion
with the service, particularly in relation to non-domestic rates
TRANSPORT COSTS
0.026 0.037 0.011
Movement mainly reflects a budget realignment based on 2024-25 outturn and discussion
with the service, particularly in relation to vehicle hires and non-contract repairs.
SUPPLIES & SERVICES
0.749 0.776 0.027 Movement mainly reflects a budget realignment based on 2024-25 outturn and discussion
with the service, particularly in relation to computing costs and subscriptions.
THIRD PARTY PAYMENTS 0.000 0.000 0.000
DEBT CHARGES
0.000 0.004 0.004 Movement mainly reflects a budget realignment based on 2024-25 outturn and discussion
with the service.
TOTAL EXPENDITURE 4.394 4.560 0.166
INCOME (1.058) (0.889) 0.169
Movement mainly reflects a budget realignment based on 2024-25 outturn and discussion
with the service, particularly in relation to permits & notices (£0.183m). This is partly offset by 
the impact fees and charges inflation as part of the 2025-26 budget setting process (£0.014m).
NET EXPENDITURE 3.336 3.671 0.335
17

Page 18

Official#
Appendix 3
Ayrshire Roads Alliance
Analysis of Movements in Budgets 2024-25 to 2025-26
Local Delivery - East
Detail
Annual
Estimate
2024/25           
£m
Annual
Estimate
2025/26          
£m
Movement
2024-25 to
2025-26 Explanation of Movement
EMPLOYEE COSTS 3.361 3.440 0.079
Movement mainly reflects payroll inflation (£0.164m) and additional National
Insurance charges (£0.167m). This is partly offset by a budget realignment
based on 2024-25 outturn and discussion with the service (£0.207m) and the
impact of 2025-26 savings package (£0.045m).
PREMISES COSTS 0.323 0.320 (0.003) Movement mainly reflects a budget realignment based on 2024-25 outturn and
discussion with the service, particularly in relation to water charges.
TRANSPORT COSTS 0.837 0.829 (0.008)
Movement mainly reflects a budget realignment based on 2024-25 outturn and
discussion with the service, particularly in relation to vehicle / plant hire.
SUPPLIES & SERVICES 1.891 2.457 0.566
Movement mainly reflects a budget realignment based on 2024-25 outturn and
discussion with the service, particularly in relation to EV electricity costs
(£0.550m).
THIRD PARTY PAYMENTS 1.228 1.128 (0.100)
Movement mainly reflects the impact of 2025-26 savings package (£0.090m)
along with a budget realignment based on 2024-25 outturn and discussion with
the service (£0.010m).
DEBT CHARGES 0.321 0.365 0.044 Movement mainly reflects a budget realignment based on 2024-25 outturn and
discussion with the service.
TOTAL EXPENDITURE 7.961 8.539 0.578
INCOME (3.860) (4.471) (0.611)
Movement mainly reflects fees and charges inflation (£0.030m) and the impact
of 2025-26 savings package (£0.079m), both as part of 2025-26 budget setting
process, along with a budget realignment based on 2024-25 outturn and
discussion with the service (£0.502m), particularly in relation to EV charging
income.
NET EXPENDITURE 4.101 4.068 (0.033)
18

Page 19

Official#
Appendix 3
Ayrshire Roads Alliance
Analysis of Movements in Budgets 2024-25 to 2025-26
Local Delivery - South
Detail
Annual
Estimate
2024/25           
£m
Annual
Estimate
2025/26          
£m
Movement
2024-25 to
2025-26 Explanation of Movement
EMPLOYEE COSTS 2.570 2.661 0.091 Movement mainly reflects payroll inflation (£0.048m)  and a budget realignment based on 2024-25 outturn
and discussion with the service (£0.042m).
PREMISES COSTS 0.206 0.230 0.024
Movement mainly reflects a budget realignment based on 2024-25 outturn and discussion with the service,
particularly in respect of electricity (£0.013m), waste collection (£0.007m) and property rent charges
(£0.004m).
TRANSPORT COSTS 1.117 1.100 (0.017)
Movement mainly reflects a saving from a move away from HVO fuel (£0.025m) as part of 2025-26 budget
setting exercise. This is partly offset by  a budget realignment based on 2024-25 outturn and discussion with
the service (£0.008m), particulary in relation to vehicle maintenance.
SUPPLIES & SERVICES 2.093 2.325 0.232
Movement reflects additional resources in relation to street lighting electricity (£0.148m), along with a budget
realignment based on 2024-25 outturn and discussion with the service (£0.079m), particularly in relation to
EV elctricity (£0.050m) and computing (£0.011m) costs.
THIRD PARTY PAYMENTS 1.201 1.549 0.348
This movement mainly reflects additional resources in relation to dredging at Girvan Harbour as part of 2025-
26 budget setting exercise (£0.325m) and a budget realignment based on 2024-25 outturn and discussion
with the service (£0.023m), particularly in relation to roads maintenance sub-contractors.
DEBT CHARGES 0.213 0.213 0.000
TOTAL EXPENDITURE 7.400 8.078 0.678
INCOME (3.179) (2.887) 0.292
Movement mainly reflects a reduction in the parking income target (£0.490m) as part of 2025-26 budget
setting exercise. This is partly offset by an increased income targets in respect of pier dues (£0.003m) and
Motorhome Parking Scheme (£0.019m), along with a budget realignment based on 2024-25 outturn and
discussion with the service (£0.176m), particularly in relation to EV charging (£0.148m) and Roads
Maintenance income (£0.025m).
NET EXPENDITURE 4.221 5.191 0.970
19

Page 20

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
Projected
Variance at   
31 March
2025
(£m) 
Local Delivery - South Ayrshire 
(0.090) 
0.096 
0.124 
0.583 
0.746           
(0.007) 
(0.583) 
Employee Costs
This variance mainly reflects staff turnover due to vacancies (£0.339m),
partly offset by additional overtime (£0.125m) and employee recharges in
respect of cross boundary working (£0.134m) 
Premises Costs
This variance mainly reflects non-domestic rates (£0.023m), waste
collection charges (£0.011m) and electricity (£0.053m) charges. 
Transport Costs
This variance mainly reflects additional external hires (£0.160m) within Roads
Maintenance which is offset by additional income. This is partly offset by
reduced fuel charges (£0.048m). 
Supplies & Services
This variance mainly reflects street lighting electricity charges (£0.377m),
EV charging costs which are offset by additional income (£0.050m)
consultancy costs which is partly offset by additional income (£0.258m),
along with additional expenditure on computing (£0.069m) and tools &
equipment (£0.049m). This is partly offset by savings on roads
maintenance and lighting materials (£0.214m). 
Third Party Payments
This variance reflects additional sub-contractors particularly within Roads
Maintenance, this being offset by additional income.
Debt Charges
This variance reflects a reduction in debt charges for new vehicles within
Roads Maintenance
Income
This variance mainly reflects additional roads maintenance income
(£0.507m), particularly in relation to Ayrshire Growth Deal, promenade
works and a cycling event, street lighting (£0.077m), design works
(£0.076m), EV charging income (£0.125m) and traffic income (£0.281m),
particularly in relation to Alloway Tunnel and LDP2. This is partly offset by
a shortfall in parking income (£0.440m) and income at Girvan Harbour
(£0.043m).
0.869 Total reported variance
20

Page 21

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 
2025
2024/25 GENERAL SERVICES REVENUE BUDGET
AS AT 31 MARCH 2025 – PERIOD 12
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
21

Page 22

22

Page 23

1
AYRSHIRE SHARED SERVICES JOINT COMMITTEE 5 SEPTEMBER 2025 
INTERNAL AUDIT ANNUAL UPDATE REPORT: 
AYRSHIRE ROADS ALLIANCE 
Report by Chief Auditor, East Ayrshire Council 
SUBJECT: INTERNAL AUDIT ANNUAL UPDATE REPORT 
PURPOSE OF REPORT 
1. This established annual report is intended to provide, for noting, an update on
internal audit work for the Ayrshire Roads Alliance (ARA). 
RECOMMENDATIONS 
2. It is recommended that Joint Committee: 
i. notes the outcomes of a wide range of Internal Audit work for ARA
carried out by East Ayrshire Council since inception as summarised at
paragraphs 11-12 and detailed at Appendices 1 and 2; 
ii.  notes the Chief Auditor’s ongoing annual opinion for 2024/25 of
reasonable assurance for EAC arrangements as laid out at paragraph
13; 
iii. notes the ARA items included in the 2025/26 EAC Internal Audit plan as
referred to at paragraph 14 and listed in Appendices 1 and 2; and
iv. otherwise notes the contents of this report. 
BACKGROUND 
FRAMEWORK FOR INTERNAL AUDIT WORK
3. As the lead authority EAC provides the internal audit service to ARA. South
Ayrshire Council (SAC) is able to carry out Following the Public Pound (FtPP)
type audits as desired and those reports would be a matter for SAC to
consider. The Chief Auditors of both Councils work closely together including
through the longstanding Pan-Ayrshire Chief Auditors Group. 
4. ARA assignments are included in the annual EAC Internal Audit Plan
approved by EAC’s Governance and Scrutiny Committee in line with current
professional standards which, until 31 March 2025 were those set out in the
Public Sector Internal Audit Standards (PSIAS) and from 1 April 2025 are
those set out in the Global Internal Audit Standards (GIAS) in the UK Public
Sector.
5. Professional standards require the Chief Auditor to establish a follow-up
process to monitor and ensure management actions have been effectively
implemented. We follow-up by testing evidence to gauge implementation of
recommendations (Appendix 2). 
Agenda Item 3
23

Page 24

2
6. Individual internal audit assignment reports and follow-up exercises are
shared with both EAC and SAC as well as External Audit: 
• EAC - the established readership includes senior management and all
Elected Members through the Councillors’ Noticeboard. 
• SAC – all reports are copied to the Director of Housing, Operations and
Development and shared with the SAC Chief Internal Auditor for
onward reporting in line with SAC arrangements. 
7. The Head of Roads continues to accept and welcome Internal Audit
recommendations. 
TRUST IN INTERNAL AUDIT - EXTERNAL AUDIT
8. External Audit report their annual conclusions on internal audit within their
annual audit report to the Council. The most recent report is for 2023/24 with
no significant issues arising providing assurance for those placing confidence
in the work of Internal Audit. Our arrangements have remained stable since
2023/24. 
TRUST IN INTERNAL AUDIT - EXTERNAL QUALITY ASSESSMENT (EQA)
9. The PSIAS required a Quality Assurance and Improvement Programme
(QAIP) to be in place including an independent EQA to be carried out every
five years. EAC’s Governance and Scrutiny Committee considered the very
positive outcomes from the most recent EQA exercise, carried out by the
Chartered Institute of Public Finance & Accountancy (CIPFA), on 20 April 2023
as reported to the ASSJC on 1 September 2023. Our arrangements have
remained stable since that EQA, with an equivalent exercise required in due
course under the GIAS.
MAIN REPORT 
ASSURANCE OUTCOMES FOR INDIVIDUAL ASSIGNMENT REPORTS 
10. Assignment reports, with the exception of some advisory work and fact-
finding, conclude with an overall assessment of the controls under review
using the list below as a guide. We also consider context including risk and
materiality. 
sound assurance / sound assurance in most areas – objectives of
internal control have been met in all/almost all areas within the scope of the
audit; non-compliance has only been identified in low risk or medium risk
areas. 
reasonable assurance - objectives of internal control have been met in the
majority of areas; some weaknesses have been identified in medium risk
areas; this tends to be the most common assurance outcome. 
limited assurance – the control objectives have not been fully achieved;
control weaknesses have been identified in some high risk areas.               
no assurance – the control objectives have not been met; significant non-
compliance and/or control weaknesses have been identified.   
24

Page 25

3
INTERNAL AUDIT WORK – AN OVERVIEW   
11. Appendix 1 lists internal audit work since 2013/14 at which point the EAC
Chief Auditor was a member of the working group to establish ARA.  An
overview of all outcomes is listed in the table below. 
Assurance Outcome  Number of outcomes 
sound assurance / sound
assurance in most areas
5
reasonable assurance 7
limited assurance 4
no assurance  0
advisory  5
Total outcomes  21 
12. Appendix 2 lists 10 completed follow-up exercises since 2016/17 to test
implementation of internal audit recommendations made since the inception of
ARA. Follow-up exercises show improved performance since 2018/19 with all
exercises carried out since that year resulting in scores of 100% which means
that all recommendations tested were either fully or sufficiently implemented
demonstrating ongoing management commitment to continuous improvement. 
ANNUAL INTERNAL AUDIT OPINION: EAC 2024/25
13. ARA operates within the control systems of EAC, therefore the Chief Auditor’s
annual opinion for EAC is of interest to the ASSJC. The most that Internal
Audit can provide in an annual opinion for the Council is reasonable assurance
based on the risk based plan and a rolling programme of work. This is similar
to the scope of external audit work in the context of the Council’s financial
statements which aims to give reasonable assurance on the statements. The
Annual Internal Audit Opinion for East Ayrshire Council in 2024/25 stated that,
“reasonable assurance can continue to be placed upon the adequacy and
effectiveness of the Council’s framework of governance, risk management and
control in the year to 31 March 2025”. The opinion was considered by EAC’s
Governance and Scrutiny Committee on 24 April 2025.
PLANNED AUDIT ASSIGNMENTS FOR ARA – 2025/26 
14. In line with professional standards a full risk based plan was agreed by EAC’s
Governance and Scrutiny Committee on 5 June 2025. SAC were consulted
during the planning process. It should be noted, that in line with good practice
the plan can be changed in year to accommodate emerging priorities. The
planned ARA work for 2025/26 is included in Appendices 1 and 2. 
25

Page 26

4 
15. The EAC Depute Chief Executive (Communities and Economy), the Head of
Roads and the EAC Chief Auditor will agree the scheduling and detailed
content of assignments in line with established arrangements.   
IMPLICATIONS 
16. Eight implications have been considered in the preparation of this report.   
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance  No 
3. Human Resources  No 
4. Equality and Fairer Scotland Duty  No 
5. Financial   No 
6. Risk  Yes  Para 17
7. Community Wealth Building   No 
8. Net Zero   No 
RISK IMPLICATIONS 
17. Each year there is the ongoing risk of significant unplanned work emerging,
planned resources not being available and work not being carried out to an
acceptable standard which would compromise the ability to complete sufficient
work. The likelihood is low to medium risk but the impact would be high risk.
The EAC Audit Manager and Chief Auditor oversee operations with the
objective of mitigating this risk. 
APPENDICES 
18. Two appendices support this report: 
• Appendix 1: Internal Audit Assignments: 2013/14 to 2025/26  
• Appendix 2: Internal Audit Follow-Up Exercises 2016/17 to 2025/26 
BACKGROUND PAPERS  
1. Public Sector Internal Audit Standards (PSIAS) (3rd edition March 2017) 
2. Chartered Institute of Public Finance and Accountancy (CIPFA) Local
Government Application Note for the United Kingdom Public Sector Internal
Audit Standards (2nd edition February 2019) 
3. Chartered Institute of Public Finance and Accountancy (CIPFA), Statement on
the Role of the Head of Internal Audit in Public Service Organisations (2nd
edition April 2019) 
4. Institute of Internal Auditors (IIA) Global Internal Audit Standards (GIAS)
(January 2024) 
26

Page 27

5
5. EAC Governance & Scrutiny Committee, 26 September 2024, Annual External
Audit Report 
6. Global Internal Audit Standards in the UK Public Sector: Application Note
(IASAB, December 2024) 
7. Code of Practice for the Governance of Internal Audit in UK Local Government
(CIPFA, February 2025) 
8. EAC Governance & Scrutiny Committee, 24 April 2025, Internal Audit 2024/25
Annual Report and Annual Internal Audit Opinion 
9. EAC Governance & Scrutiny Committee, 5 June 2025, Internal Audit Plan
2025/26 
Eilidh Mackay 
Chief Auditor, East Ayrshire Council 
25 August 2025 
Person to Contact: 
Eilidh Mackay, Chief Auditor eilidh.mackay@east-ayrshire.gov.uk 
Implementation Officer: 
Paul Davies, Audit Manager paul.davies@east-ayrshire.gov.uk 
27

Page 28

6
Appendix 1
INTERNAL AUDIT ASSIGNMENTS: 2013/14 TO 2025/26
Year  Name Summary Assurance Outcomes 
2013/14  Support to working 
group to establish ARA 
Advisory to support governance, risk management and internal 
control arrangements. 
Advisory   
1 April 2014 – ARA goes live 
2014/15  Plant Hire Contract 
(coverage included ARA 
and other services)
Objectives were to: 
• ensure that hires are awarded to the correct service provider
in accordance with the framework agreement;
•   ensure that processes for managing plant on and off hire are
rigidly controlled and properly recorded; and
• ensure that the correct contractual prices are paid for plant
hires provided in accordance with the framework terms and
conditions.
Reasonable 
2014/15  Inventory 
Inspections 
(unannounced visits) 
Objectives of the assignment were to:
• verify the accuracy of inventory levels recorded within the
store
• report any areas for improvement identified, and
• recommend actions to address areas for improvement.
Reasonable 
2014/15  PROFESS Costing 
System
The objectives of the assignment were to:
• consider the overall costing and financial reporting
arrangements put in place for the Ayrshire Roads Alliance;
• assess the status of implementation and roll-out of the
PROFESS costing system, including the integration of inputs
from the former East and South Ayrshire roads services;
• consider whether the information needs of management and
stakeholders are being met by the current arrangements;
Reasonable 
28

Page 29

7
• report any areas for improvement identified, and recommend
actions to address areas for improvement
2015/16  TRIPS System Advisory Advisory to support governance, risk and internal control 
arrangements regarding the development of the established 
Transparent Roads Infrastructure Procurement Software (TRIPS) 
system used to manage the Roads Minor Works Framework Contract 
to support best value. 
Advisory 
2016/17  Parking Income and 
Penalty Charge Notices 
(PCNs)
The objectives of the assignment were to:
• review the systems for Parking-related income
• report any areas for improvement identified, and 
• recommend actions for improvement.
Reasonable 
2017/18 Performance Bonds  The objectives of this audit assignment were to verify:
• policy and procedures accord with Scottish Government
strategy and national guidance on best practice;
• corporate governance and reporting arrangements are fit for
purpose and effectively applied;
• practical processes and supervisory controls are in place in
ARA for implementing approved policy;
• ARA’ s bond management is supported by effective
partnership arrangements with third parties (for example with
South Ayrshire Council and with EAC’s Planning and
Economic Development, Finance and ICT and Legal);
• bond values reflect application of the above and give
sufficient budget to fund any necessary remedial work.
Limited 
2017/18 Use of Contractors  The objectives of this audit assignment were to:
•  establish the process for awarding roads works contracts
procured through the Transparent Roads Infrastructure
Procurement Software (TRIPS) 
•  ensure roads works are being awarded appropriately in line
with Standing Orders Relating to Contracts and assess
whether Best Value is being achieved.
Reasonable 
29

Page 30

8
•  ensure adequate controls are in place with regards to
processes for awarding works, payment of invoices and
monitoring of contractor performance.
2018/19  Girvan Harbour – office 
administration 
(unannounced visit)
The objectives of this audit assignment were to: 
• understand the operation of Girvan Harbour and ensure that
there are adequate arrangements in place to control income
collected in respect of harbour operations
• to identify areas for potential future audits.  
Limited 
2018/19 Payment Controls  The aims and objectives of this audit assignment were to: 
• review the procedures in place for payment of contractors 
• verify that there are adequate controls in place to verify the
work completed prior to approving invoices for payment.  
Sound 
2018/19 Bridge Inspections  The EAC Depute Chief Executive (Safer Communities) with 
assistance from Internal Audit reviewed ARA-East’s arrangements for 
bridge inspection and reporting.  Following this work, in 2019/20 
Internal Audit undertook a full examination of arrangements for the 
Principal Inspections of road bridges. 
Advisory 
2019/20  Arrangements for the
Principal Inspection (PI)
of road bridges
The objective of this audit assignment was to:
• update the findings of 2018/19 advisory work to reflect the
undertaking and completion of the outsourced Principal
Inspection programme and work done by ARA further to the
Client Response agreed actions set out in the draft audit
report and accompanying advisory note of 2018/19. 
Two outcomes: 
Sound in South and 
Reasonable in East         
2019/20 Road Bonds review of 
new processes 
The objectives of this audit assignment were to:
• verify procedures in relation to roads bonds are adequate,
have been updated to reflect the findings of previous audit
work and have been fully implemented within the service, and
• the audit will also seek to confirm that ARA’s internal review
of the process, and scrutiny by external assessor (SGS Ltd),
have verified control effectiveness; and that if necessary,
procedures have been further revised to improve controls.
Sound in most 
areas 
30

Page 31

9
2020/21 Roads Maintenance:
materials and stores 
The objective of this audit assignment was to:
• obtain assurance that the service has adequate
arrangements in place to ensure proper control over the
receiving, storing and issuing of materials and stores, and
that these processes are operating efficiently and effectively.
Reasonable 
2021/22 Whistleblowing 
allegations – fact-finding 
Final report issued in 2021/22 to both Councils; interim outputs 
issued prior to that to support decision-makers following referral in 
summer 2019. 
Advisory
2022/23 Payment Controls 
(including measurement 
of works) 
The objective of this audit was to verify that payments made to
contractors accurately reflect the quality and quantity of works carried
out.  If controls are absent or ineffective, then works may be
incomplete, sub-standard or over-charged; 
• our audit involved reviewing ARA’s procedures for approving 
contractors’ invoices / certificates for payment, and confirming           
there are effective controls in place and operating to confirm 
the payments made for goods and services are appropriate; 
• we backed this up with a sample check of fifteen transactions,
to confirm that approved procedures are being followed and
controls applied to ensure the accuracy of payments and verify
the evidencing of appropriate checks by the service;
• our audit focussed on three high spend areas - bridge
strengthening, road resurfacing and traffic management.
Three outcomes:
Limited (2) and
sound assurance.   
Our audit confirmed
that ARA has
appropriate procedures
in place incorporating
robust controls, which
when applied in
practice, should ensure
sound control of
expenditure, and
accurate payments to
contractors.   
We noted an
operational impact due
to staff absence.    
ARA has responded
positively to our
findings. 
31

Page 32

10
2023/24 Flood Risk Management  The aims and objectives of this assignment were to support ARA 
self-assessment with regard to:
•  governance arrangements for statutory flood risk
management duties, with a view to ensuring these are fit for
the purpose of supporting strategic oversight, decision-
making and accountability;
•  ARA’s contributions to the Local Flood Management Plans
covering constituent council areas, with a view to ensuring
Plans are consistent with East and South Ayrshire’s exposure
to (and risk appetite for) flood risks;
•  Statutory obligations with regard to a watercourse inspection
and clearance regime.
Advisory. 
Service engaged with
process; self-
assessment checklist
developed with
assurance session
being progressed with
Depute Chief
Executive and Head of
Roads. 
2024/25  Contract Controls  The aims and objectives of this audit were to:
• Verify payments made to major contractors accurately reflect
the quality and quantity of works carried out;
• Confirm service arrangements support achievement of best
value and secure effective internal control.
Report being finalised
with seven
recommendations
which will further
enhance the control
environment.  Scope
expanded following
request from EAC DCE
(Communities &
Economy).
2024/25 Stores  The aims and objectives of this audit assignment were to:
• Review processes for managing inventory within the 
Ayrshire Roads Alliance (ARA) stores.
• Confirm that the security arrangements for ARA inventory 
are adequate.
• Determine the arrangements for replenishing inventory 
when required and confirm adequate controls are in place. 
• Ensure inventory movements are recorded accurately 
Sound in most 
areas
32

Page 33

11      
and reviewed; and confirm inventory on site can be 
matched to records.
2025/26 Digital Transformation
of Workstreams The aims and objectives of this audit assignment are to:
• Verify effective internal controls have been incorporated within
processes subject to digital transformation. 
Work underway. 
33

Page 34

12 
Appendix 2
INTERNAL AUDIT FOLLOW-UP EXERCISES: 2016/17 TO 2025/26
Year  Name Summary Score   
1 April 2014 – ARA goes live 
2016/17  PROFESS Costing 
System – Follow-up
To test implementation of all ten 
recommendations made in 2014/15. 
Score 67%. Six recommendations tested 
with four fully or sufficiently implemented 
and two not implemented.
The four other recommendations were
dependent on the completion of the
definitive build of PROFESS and could
not be tested at the time of the follow-up;
the Head of Service signed a Client
Assurance Statement at that time
agreeing actions required. 
2016/17  Plant Hire – Follow-up To test implementation of all four 
recommendations made in 2014/15.
Score 75%. Three recommendations 
fully implemented and one partially 
implemented. 
2016/17  Inventory 
Inspections – Follow-up
To test implementation of all five 
recommendations made in 2014/15.
Score 60%. Three recommendations  
fully or sufficiently implemented; one
partially and one not implemented.
2017/18 Parking Income and 
PCNs – Follow-up
To test implementation of all 13 
recommendations made in 2016/17.
Score 92%. Twelve recommendations 
fully or sufficiently implemented and one 
partially implemented. 
2018/19 Performance Bonds – 
Follow-up
To test implementation of all two 
recommendations made in 2017/18.
Score 100%. Both recommendations
sufficiently implemented. 
2018/19 Use of Contractors – 
Follow-up
To test implementation of all two 
recommendations made in 2017/18.
Score 100%. Both recommendations fully 
implemented. 
34

Page 35

13
2019/20 ARA Girvan Harbour -
Follow-up 
To test implementation of all five 
recommendations made in 2018/19.
Score 100%. 
All recommendations either fully or 
sufficiently implemented.
2019/20  Arrangements for the 
Principal Inspection (PI) 
of road bridges – 
Follow-up
To test implementation of all five 
recommendations made earlier in 2019/20.
Score 100%. All recommendations either 
fully or sufficiently implemented.
2021/22  Roads 
Maintenance: materials 
and stores - Follow-up 
To test implementation of all five 
recommendations made in 2020/21.
Score 100%. All recommendations fully 
implemented.
2021/22 Road Bonds review of 
new processes – 
Follow-Up 
To test implementation of all six 
recommendations made in 2019/20.
Score 100%. All recommendations either 
fully or sufficiently implemented.
2024/25  Payment Controls 
(including measurement 
of works) – Follow-Up 
Follow up testing of implementation of all three
recommendations made during the 2022/23
assignment.  
Rescheduled into 2025/26 – working with
service to align with new digitised
processes.
2024/25  Flood Risk Management 
– Follow-Up
Advisory support as required for the self-
assessment process previously created with
formal follow-up of the recommendation raised. 
Rescheduled into 2025/26 due to
recruitment of new flooding officer.  Work
anticipated to commence in late summer
2025.
2025/26 Contract Controls –
Follow-Up
To test implementation of the proposed seven
recommendations in the current draft report. 
Work will be scheduled pending
agreement of implementation schedules. 
END 
35

Page 36

36

Page 37

AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
5 September 2025 
Report by the Head of Roads – Ayrshire Roads Alliance 
AYRSHIRE ROADS ALLIANCE
PERFORMANCE SCORECARD 
Purpose of report 
1. The purpose of this Report is to advise the Joint Committee regarding the
progress made to date against the Performance Scorecard.  
Recommendations 
2  It is recommended that the Joint Committee:
i. Notes the performance scorecard presented in this report;
ii. Continues to receive the performance scorecard updates; and
iii.  Otherwise, notes the content of the report. 
Background 
3.    The purpose of the performance management and benchmarking is to work
collaboratively to deliver tangible and sustained improvements within the
Ayrshire Roads Alliance in order to manage the on-going development and
delivery of benchmarking frameworks. 
4. Improved performance management is fundamental to supporting the Ayrshire
Roads Alliance.  This drives change and improvement within the fully integrated
roads service and support improved outcomes, better performance, and more
effective use of resources.   
5.      The Performance Indicators are regularly refreshed when new useful performance
measures are introduced by the Ayrshire Roads Alliance or there is an
agreement to include a specific indicator.  This will be a regular item for the
Ayrshire Shared Service Joint Committee to review 
Main report/main issues 
6.       This scorecard is used to: 
• monitor the progress in meeting the Ayrshire Roads Alliance’s objectives;
• help managers to have performance-related conversations with staff; and 
• identify any problem areas that need addressed.
Agenda Item 4
37

Page 38

7. Some indicators are collated at different frequencies and so these will be
included as appropriate. 
8. The Performance Scorecard is presented in Appendix 1.  Commentary against
the specific red and amber performance measures are included in Appendix 1.
There are a number of green performance measures which should be
highlighted, especially: 
• Finance with respect to the percentage of invoices paid within 30 calendar
days.  This is currently at 98% for this financial year. 
• Priority 1 and Priority 2 Faults – with respect to the percentage of priority 1
and 2 faults completed within timescale.  This is currently above target for
this financial year. 
• Street Lighting Repairs – with respect to the percentage of street lighting
repairs completed within the timescale.  The service has achieved an
average of 99% for this financial year. 
9. The Improvement Action Plan continues to identify improvements to a number of
existing processes for re-design within The Ayrshire Roads Alliance. 
Implications 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning Yes  10 and 11
2. Governance Yes  12
3. Human Resources Yes  13
4. Equality and Fairer Scotland Duty Yes   14
5. Financial Yes  15
6. Risk Yes  16
7. Community Wealth Building Yes  17
8. Net Zero Yes  18 
Policy/strategic planning implications 
10.      A well-maintained road network will contribute to achieving the 2015-2030 
Community Plan objectives and associated 2021-2024 Delivery Plans 
11.      The matters referred to in this report contribute to Priority 1 of the South Ayrshire       
Council Plan: Spaces and Places/ Moving around and the environment       
(Outcome 1). 
Governance Implications 
12. The work of the Ayrshire Roads Alliance is undertaken in accordance with 
relevant legislation. 
38

Page 39

Human resources Implications 
13.     The Performance Scorecard has no direct impact on human resources. 
Equality impact and Fairer Scotland duty implications 
14. The Performance Scorecard complements the Equality Impact Assessment by     
ensuring that any issues arising are adequately prioritised, managed and either
eliminated or mitigated. 
Financial implications 
15.   The Performance Scorecard facilitates the existing scrutiny arrangements to
manage, prioritise, and review the budget provided by East Ayrshire Council and
South Ayrshire Council to the Ayrshire Roads Alliance. 
Risk implications 
16.    The Performance Scorecard assists in the prioritisation of risks that need to be 
mitigated by the Ayrshire Roads Alliance in order to reduce the overall risk to
either Council  and to comply with the Community Plan/Council Plan in both
partner bodies. 
Community Wealth Building implications 
17. The works programme provides economic levers to develop resilient, inclusive
local economies with more local spend and fair employment, as well as ensuring
that wealth is more locally owned and benefits local people 
Net zero implications 
18.   The Ayrshire Roads Alliance Service Plan supports and links to East Ayrshire
Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment 
39

Page 40

Appendices (if applicable) 
1. Performance Scorecard 
Background papers 
None 
Person to contact 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
Implementation Officer 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
40

Page 41

Official#
2019/21
2019/21
Scotland
Average
2020/22
2020/22 
Scotland
Average
2021/23
2021/23
Scotland
Average
2022/24
2022/24
Scotland
Average
2023/25
2023/25
Scotland
Average
2019/21
2019/21
Scotland
Average
2020/22
2020/22 
Scotland
Average
2021/23
2021/23
Scotland
Average
2022/24
2022/24
Scotland
Average
2023/25
2023/25
Scotland
Average
2021 2022 2023 2024 2021 2022 2023 2024 ` 22.10% 29.80% 17.20% 27.60% 15.60% 27.40% 17.60% 28.90% 17.70% 30.60% 34.10% 29.80% 28.90% 27.60% 23.00% 27.40% 21.7% 28.90% 23.4% 30.60%
Number of people killed or seriously injured in road
accidents per 100,000 population 36 42 48 34 37 54 28 54 32.60% 34.00% 26.85% 33.60% 27.00% 31.50% 26.10% 32.50% 25.20% 34.60% 37.30% 34.00% 34.40% 33.60% 32.50% 31.50% 31.0% 32.50% 28.6% 34.60%
Number of slightly injured casualties per 100,000
population 49 58 82 57 41 52 30 58 33.50% 33.60% 29.50% 33.20% 29.60% 32.70% 31.00% 33.40% 30.80% 34.20% 40.80% 33.60% 37.90% 33.20% 38.90% 32.70% 38.1% 33.40% 37.6% 34.20%
42.30% 38.30% 40.90% 36.70% 40.60% 36.40% 39.00% 36.20% 37.00% 36.20% 43.40% 38.30% 42.90% 36.70% 41.00% 36.40% 38.5% 36.20% 36.4% 36.20%
36.80% 35.50% 33.80% 34.20% 33.50% 33.60% 33.00% 34.10% 31.70% 34.70% 40.90% 35.50% 39.00% 34.20% 37.40% 33.60% 35.5% 34.10% 34.0% 34.70%
MONTHLY PERFORMANCE INDICATORS APSE
Average Target Current
Status Apr May Jun Comments APSE
Average Target Current
Status Apr May Jun Comments
No of invoices paid within 30 days 333 357 323 - - 1.43 0.78
No of Invoices Received 341 358 325
% of invoices paid within 30 days 98% 99% 99% - 49,000 per
annum  1,751 3,928 6,316
Average Year to date of Number of Invoices paid
within 30 days 98% 98% 98% -  4,576 4,561 4,559
- 1,800 per
annum             140 562 1,258
Number of ARA Safety Inspections Completed within
Timescale 25 24 20
Number of ARA Safety Inspections Scheduled 25 25 20
% of ARA Safety Inspections Completed within
timescale 100% 96% 100%
Average Number of days to report an incident to the
Health and Safety Section 1.5 2.7 36.3
Target Current
Status Apr May Jun Target Current
Status Apr May Jun Target Current
Status Apr May Jun Target Current
Status Apr May Jun
100% -  
Number of Public Liability claims closed 5 3 3 10 6 6  
Number of Public Liability claims received 6 7 3 7 3 3
Total number of open claims 57 63 63 65 46 40 
Number of Public Liability Claims that were
successful 0 0 0 0 1 0
% of Public Liability Claims that were successful 0% 0% 0% 0% 16% 0% - 0 0 5 34 - 9 11 2
Number of Priority 1 Road Emergency defect repairs
made safe within 2 hours 0 2 1 3 2 2 53 35 34 50 39 30
AYRSHIRE ROADS ALLIANCE PERFORMANCE SCORECARD DETAILED MONITORING REPORT
UPDATE : JOINT COMMITTEE  - 6 SEPTEMBER 2025
40
5
South Ayrshire Council
% of A Class roads that should
be considered for maintenance
% of B Class roads that should
be considered for maintenance
% of C Class roads that should
be considered for maintenance
8%
98%
--
92.02%
SOUTH AYRSHIRE COUNCIL
ANNUAL PERFORMANCE INDICATORS
(CALENDAR YEAR)
East Ayrshire
MONTHLY PERFORMANCE INDICATORS APSE
Average
EAST AYRSHIRE COUNCIL
HEALTH AND SAFETY
100% -
% of U Class roads that should
be considered for maintenance
Overall % of the road network
that should be considered for
maintenance
Monthly visits to the website
from social media
ANNUAL PERFORMANCE
INDICATORS                                                                                              
(FINANCIAL YEAR)
East Ayrshire Council
EAST AYRSHIRE COUNCIL
- 20 50
0
Comments
FACETIME
Managers are aware of the
importance of completing
FACE reviews with their
staff
-
2 0
PUBLIC LIABILITY CLAIMS
100%100%
South Ayrshire
AYRSHIRE ROADS ALLIANCE
WELL ENGAGED
Visits to the ARA Website every
month
ABSENCE MONITORINGAverage days lost per employee
MONTHLY PERFORMANCE
INDICATORS
AYRSHIRE ROADS ALLIANCE
FINANCE
-
AYRSHIRE ROADS ALLIANCE
No of Twitter Followers every
month
0
27
47 12
7 61 7
32
STREET LIGHTING
Number of Street Lighting
repairs completed within 7
working days
0
APSE
Average
SOUTH AYRSHIRE COUNCIL
ROADWORKS PROGRAMME
Physical % of Roadworks
Programme Completed
BRIDGES
Number of General Bridge
Inspections
Number of Special Bridge
Inspections
Number of Principal Bridge
Inspections
40-
-
-
36
27
11%1% 28% 40%20%
Comments
Number of staff who have received annual FACETIME
review 2
- -
PRIORITY 1 FAULTS
41

Page 42

Official#
Target Current
Status Apr May Jun Target Current
Status Apr May Jun Target Current
Status Apr May Jun Target Current
Status Apr May Jun
SOUTH AYRSHIRE COUNCIL
MONTHLY PERFORMANCE INDICATORS APSE
Average
EAST AYRSHIRE COUNCIL EAST AYRSHIRE COUNCIL
Comments MONTHLY PERFORMANCE
INDICATORS
APSE
Average
SOUTH AYRSHIRE COUNCIL
Comments
Number of Priority 1 Repair Lines issued 0 2 1 3 2 2 54 35 35 50 39 30
% of Priority 1 Road Emergency defect repairs made
safe within 2 hours - 100% 100% 100% 100% 100% 98% 100% 97% 100% 100% 100%
Number of Priority 2 Road Emergency defect repairs
made safe within 5 working days 8 17 8 20 5 6 26 27 14 22 11 18
Number of Priority 2 Repair Lines issued 10 18 10 21 5 7 26 27 14 23 13 18
% of Carriageway Priority 2 Defects repaired within 5
working days 80% 95% 80% 95% 100% 86% 100% 100% 100% 96% 85% 100%
Number of Stage 1 Complaints responded to within
allotted timescales 0 1 0 0 4 1 88 85 114 52 39 39
Numer of Stage 1 Complaints received 0 1 0 0 4 1 90 88 118 55 45 44
% of Stage 1 Complaints responded to within allotted
timescales - 100% - - 100% 100% 98% 97% 97% 95% 87% 89%
Number of Stage 2 complaints responded to within
allotted timescales - 0 0 0 1 0 2
Number of Stage 2 complaints received 0 0 0 1 0 2 28 13 15 25 9 23
% of Stage 2 complaints responded to within allotted
timescales - - - 100% - 100% 28 13 16 25 9 24
100% 100% 94% 100% 100% 96%
Number of parking appeals accepted 30 29 33 62 75 52
Number of parking appeals received 99 113 108 182 214 245
% of parking appeals accepted 30% 26% 31% 34% 35% 21%
Number of Street Lighting Repair
Lines Issued
% Street Lighting repairs
completed within 7 working days
% of enquiries responded to
within allotted timescales
83.44% 80%
76.23%
80%
Number of Traffic light repairs
completed within 48 hours
Number of Traffic light repair
lines issued
% of Traffic light repairs
completed within 48 hours
88.23% 95% 95%
ENQUIRIES
Number of enquiries responded
to within allotted timescales
Number of enquiries received
Officers are
reminded of the
importance of
responding to
enquiries within
timescales
88.52% 100%
95%88% 95%
COMPLAINTS
FREEDOM OF INFORMATION
TRAFFIC LIGHTS
Number of FOI & EIR requests
responded to within 20 working
days
100%Number of FOI & EIR requests
received
% of FOI & EIR requests
responded to within 20 working
days
- ----
100% 100%
75%
- 100%
PARKING
50%
75%91.20%
50%
100%
PRIORITY 2 FAULTS
42

Page 43

AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
5 September 2025 
Report by the Head of Roads – Ayrshire Roads Alliance 
AYRSHIRE ROADS ALLIANCE RISK REPORT AND REGISTER 
Purpose of report 
1. The purpose of this Report is to advise the Joint Committee on the management
of risk associated with the Ayrshire Roads Alliance. 
Recommendations 
2 It is recommended that the Joint Committee:
i. Notes the risk register presented in this report;
ii. Continues to receive updates on progress; and
iii.  Otherwise, notes the content of the report. 
Background
3 A report detailing the general approach to the Risk Report and Risk Register was
presented to the Joint Committee on 21 August 2014, where it was agreed that
the Risk Report and Risk Register would be a standing item on the agenda.  This
would ensure that the risks are monitored and scrutinised at a minimum on a
quarterly basis.     
Main report/main issues 
4 The management of risk aims to enable confident decision taking on risk,
innovation, reduce waste and inefficiency, and lead to fewer unanticipated
problems and crises that could undermine the performance and operation of the
Ayrshire Roads Alliance.
5 The risk register is contained in Appendix 1.  
Since the last Joint Committee, there have been no risks added and no risks
removed from the Risk Register.
The revised risk register illustrates the red, amber and green status and also   
illustrates whether the risk severity relates to time, indicated by [T] or cost,
indicated by [C]. 
Agenda Item 5
43

Page 44

Implications 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning Yes  6 and 7
2. Governance Yes  8
3. Human Resources Yes  9
4. Equality and Fairer Scotland Duty Yes  10
5. Financial Yes  11
6. Risk Yes  12
7. Community Wealth Building Yes  13
8. Net Zero Yes  14 
Policy/strategic planning implications 
6.  A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire. 
7. The matters referred to in this report contribute to South Ayrshire Council
strategic objective of ‘Enhanced Environment through Social, Cultural and
Economic Activities’ and within that to the outcome ‘Work with partners to
improve roads and other infrastructure, to encourage house building and
business investment that sustains local communities’. 
Governance Implications 
8. The work of the Ayrshire Roads Alliance is undertaken in accordance with
relevant legislation.             
Humans resources Implications 
9.       The Risk Register has no direct impact on human resources. 
Equality impact and Fairer Scotland duty implications 
10. The Risk Register complements the Equality Impact Assessment by ensuring
that any issues arising are adequately prioritised, managed and either eliminated
or mitigated. 
Financial implications 
11.     The Risk Register facilitates the existing scrutiny arrangements to manage,   
prioritise and review the budget provided by East Ayrshire Council and South
Ayrshire Council to the Ayrshire Roads Alliance. 
44

Page 45

Risk implications 
12.     The Risk Register assists in the prioritisation of risks that need to be mitigated by       
the Ayrshire Roads Alliance in order to reduce the overall risk to either Council       
and to comply with the Community Plan/Council Plan in both partner bodies. 
Community Wealth Building implications 
13. The works programme provides economic levers to develop resilient, inclusive
local economies with more local spend and fair employment, as well as ensuring
that wealth is more locally owned and benefits local people 
Net zero implications 
14.   The Ayrshire Roads Alliance Service Plan supports and links to East Ayrshire
Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment 
45

Page 46

Appendices (if applicable) 
1. Ayrshire Roads Alliance Risk Register 
Background papers 
None 
Person to contact 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
Implementation Officer 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
46

Page 47

Appendix 1: Risk Register Scoring Matrix 
The Risk Matrix for deciding each of the risk factors (Likelihood x Severity) in a 5 by 5
matrix are illustrated in Table 1 below: 
Table 1: Risk Factors in Practical Form 
Rare (1) Unlikely
(2)
Possible
(3)
Likely
(4)
Almost
Certain
(5)
Catastrophic
(5) 5 10 15 20 25
Very Serious
(4) 4 8 12 16 20
Moderate (3) 3 6 9 12 15
Minor (2) 2 4 6 8 10
Insignificant
(1) 1 2 3 4 5
Risk Likelihood
Risk Severity
Following on from Table 1, the following Summary Risk Profile is colour coded to highlight
the risk classification: 
Table 2: Summary Risk Profile 
Assessed
Risk (LxS) Action Required
Low Risk: 
1 to 4 
Acceptable/ can be accepted provided risk is
managed.
Medium Risk: 
5 to 12
Undesirable/ must be avoided if reasonably
practicable.
High Risk: 15
to 25 
Unacceptable risk - must be eliminated or moved to
a lower level. 
47

Page 48

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official 
NOTE:
The Risk rating will be influenced by considering a combination of event effects
Such as associated cost, event duration, and organisational reputation.   
The table below will provide some assistance with risk rating. 
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
1  
a) 
b) 
Personnel Shortage
due to:
• Pandemic
Event 
• Resignation
• Retirement
• Strike Action
• Driver hour
restrictions
Loss of trained and
competent personnel from
all sections within ARA 
Business continuity plans in place
(BUS-12, 13, & 14) to manage all
ARA mission critical activities.       . 
Additional usage of external
contractors to ensure essential
services / works programme targets
are met.   Pandemic safe workplaces
/ sites established to accommodate
reduced number of staff 
Procedures are in place to manage a
short / medium disruption of
Technical / Supervisory / operational
Personnel including re-assignment of
duties and controlled overtime
working as required.  Over long term
there would be recruitment /
procurement of the necessary
experience to fill the gaps. 
3 4  12 [T]
All Service
Managers 
Head of Roads
– Ayrshire
Roads Alliance
The staff numbers are
reviewed whenever there are
significant changes in staffing
level.  The Ayrshire Roads
Alliance has Modern
Apprentices who are
providing a strong foundation
for future staffing levels as an
addition, The Ayrshire Roads
Alliance has appointed a
Training Officer who will
undertake refresher training
to the existing workforce
where skill gaps have been
identified.  Furthermore, the
Training Officer will develop
and enhance the skills and
competency with our MAs
and trainee road workers. 
28/7/25
2  Fuel Shortage Loss or restriction due to
relief events. Any event
that has an effect on the
cost of performing the
Services, or the date of
their completion, including
the occurrence of risks
both foreseen and
unforeseen e.g. industrial
action.
To mitigate the impact of losing
access or having a restricted access
to fuel, a contingency plan has been
established which sets out the
emergency management actions that
will be taken that include designated
fuelling stations and the prioritisation
of fleet, putting non-essential
vehicles off the road. 
3 3  9 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
Continuation of public
support will be dependent on
outcomes, though expect
some mixed reaction 
28/7/25 
To calculate the risk rating, multiply the 
Likelihood x Severity.    Example….   
Possible (3) X Significant (3) = Medium Risk 
Critical (5) 
Severe (4) 
Significant (3) 
Marginal (2) 
Insignificant  (1)      
SEVERITY INDEX 
LIKELIHOOD
INDEX 
Highly probable (5) 25 20 15 10 5
Probable (4) 20 16 12 8 4
Possible (3) 15 12 9 6 3
Unlikely (2) 10 8 6 4 2
Very Unlikely (1) 5 4 3 2 1 
Incident Severity Cost (£) [C] Time [T] Reputation
Min Max Min Max 
Insignificant (1) £0 £10,000 0 1 day Councillors/CEO
Marginal (2) £10,001 £50,000 1 day 2 weeks Local Media Facebook etc.
Significant (3) £50,001 £500,000 2 weeks 1 month Local Newspaper
Severe (4) £500,001 £1,000,000 1 month 3 months National Newspaper
Catastrophic (5) £1,000,001  >£1,000,001 3 months     > 6 months National News (TV)
KEY
High Risk (16 – 25) Risks are not acceptable under any circumstances. Immediate action required
Medium Risk (8 – 15) Additional controls measures may be required.
Low Risk (1 – 6) Continue to monitor as part of review process or where changes occur.
48

Page 49

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
3  Failure to align with
Budget
requirements 
Level of investment
required in road repairs
and resurfacing and
resulting cost of treatment
higher than anticipated. 
Reduced budget could
lead to the deterioration in
the roads network, an
increase in accidents, and
insurance costs.
Loss of parking income as
a result of policy changes.
Appropriate financial and
performance monitoring
arrangements in place to mitigate the
risk.  Regular meetings with and
within partners Councils to advice on
further resource and funding
requirements. 
2 4  8 [C]
Business
Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
Adequate control measures
are in place, specifically,
monthly meetings held with
budget holders to review
revenue budget and take
appropriate corrective
actions to bring budgets
within tolerance limits. 
Monthly meeting with service
managers to review capital
budgets and programmes. 
28/7/25
4
a) 
b) 
C) 
Adverse Weather 
Staffing Issues 
Salt 
Damage to salt
storage (Dome) 
Lack of trained and
competent personnel
including operatives and
drivers to provide full
complement required to
fulfil all gritting routes due
to lack of volunteers for
existing staff, flu
pandemic, mass
resignation, strike action
and breach of Working
Time Directive and Driver
Hours Legislation. 
Reduction and /or loss of
salt stock materials for
Winter Service
operations. 
Reduction and /or loss of
salt stock materials for
Winter Service
operations. 
Procedures in place to manage a
short / medium disruption of Driver /
Operative Personnel including
banking workers and overtime
working as required.  Over the long
term there would be recruitment /
procurement of the necessary
experience to fill the gaps. 
There is adequate salt stock
resilience and conservation control
measures.  Transport Scotland has
strategic salt stock piles. 
Areas identified within depot to stock
pile storage.  Transfer salt to
alternative depots. 
2 4  8 [C]  Strategic
Manager 
Head of Roads
– Ayrshire
Roads Alliance 
Rolling programme
established to ensure
ongoing Health and Safety
training.  Appropriate and
applicable checks are
conducted on all new drivers
to ensure that all reasonable
precautions are taken to
safeguard the ‘O’ licence,
insurance payments and
reputation.  The service has
extended the use of external
companies to provide the
winter service to increase
resilience
The Service has a framework
salt supplier with a 14 day
call down delivery.  There is
a joint agreement with other
Councils to share available
salt stocks.  The existing
weather service provides
long term forecast indicating
extreme and prolonged
weather conditions. 
Cover salt exposed to the
environmental elements. 
28/7/25
5  Loss of Street
Lighting & Traffic
Signals
Extended loss of Public
Electricity supply creating
issues with Street Lighting
and Traffic Signals
Some temporary traffic signals will be
provided at key locations determined
by the Traffic Management Section
should these issues arise. 
Temporary traffic signals deployed by
RMU.  Contingency measures 
3 3  9 [T]  Traffic & Road
Safety Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider that the overall
risk is low due to the
mitigation measures that are 
in place 
28/7/25
49

Page 50

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
detailed in Business Continuity
Plans.
6 Transfer of Shared
Services – Ayrshire
Roads Alliance
Any failure in Service
provision would adversely
affect the resilience of the
Roads services.
Extensive negotiations have taken
place to ensure that the proposed
joint service meets stakeholders
needs 
2 2  4 [T]
Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
The new service is over ten
years old and it is considered
that the initial transfer of the
shared service has been
completed.  Nevertheless
there will always remain
issues on transfer issues
which may still arise. 
28/7/25
7 Council’s Waste
Transfer Licence
Loss off / restrictions on
waste transfer licence for
all depots
Robust management systems and
procedures in place to comply with
Environmental legislation, permit
conditions and health and safety 
2 3  6 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider the overall risk
is low, due to the current
waste management systems
in operation.  Current
contract allows 
28/7/25
8 Council’s Operators
Licence (‘O’
Licence) - 
Loss off / restrictions on
Council’s ‘O’ Licence.
A comprehensive maintenance
regime has been established that
follows all guidance from DVSA and
the Traffic Commissioner to ensure
that the O-Licence is protected.
In addition, compliance activities are
established and in place and a
regular external audit is carried out
by the Freight Transport Association
every 2 years to ensure that all
processes are performing to the
required standard. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Continue to work with fleet
service in East Ayrshire
Council.  28/7/25
9 Failure to meet
statutory duties in
relation to Road
Safety Inspections
Failure to provide a Risk
based approach and 
Inspection System in
accordance with the
approved, Inspection
Manual: Road Safety
Inspections and defect
categorisations.in
accordance with the Well-
Managed Highway
Infrastructure:
A Code of Practice.
There are procedures in place to
manage this process: 
1. Short term by prioritising and
reducing other works activities
and realigning budgets;
2. Medium / long term there would
be a request for additional
budgets;
3. Operatives can be assigned from
other duties and overtime
working approved. 
2 4  8 [T]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Following implementation of
the  Inspection Manual: Road
Safety Inspections and
defect categorisations from
1st April 2019 in accordance
with the Well-Managed
Highway Infrastructure:
A Code of Practice the
Ayrshire Roads Alliance 
a) Inspects the entire road
network within East
Ayrshire and South
Ayrshire, with
performance in relation
to the percentage of
safety inspections carried
out within the timescale
being reported to the
Joint Committee under
the Performance
Scorecard standing item
on the agenda. 
b) Categorise defects in
accordance with a risk
based approach ranking
defects one to four as 
28/7/25
50

Page 51

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
detailed in the Inspection
Manual: Road Safety
Inspections and defect
categorisations 
c) Issue repair lines for
defects on carriageways
and footways with target
response times
determined by the
category of defect, as
identified in the
Inspection Manual: Road
Safety Inspections and
defect categorisations 
d) Complete the vast
majority of Category 1
defects within the target
response time of two
hours.
10 Business Continuity
/ Emergency
Planning
Incident affecting one or
more of the Ayrshire
Roads Alliance service
functions (including ICT
Failure).
Business continuity plans developed
for: Roads Maintenance (including
the Winter Gritting Programme);
Lighting Maintenance Unit; Network;
Design and Traffic and Road Safety
facilities within East Ayrshire and
South Ayrshire.
To prevent fallout from IT system
failure, a business contingency plan
has been developed as well as a
back up process to revert to paper
based recording systems for fleet
management and maintenance. 
2 4  8 [T]
Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
The overall risk is high due to
the unknown nature of such
an incident and because of
the potential reputational
damage and adverse effect
on the service delivery,
including discharge of
statutory responsibilities. 
28/7/25
11 Benefits Realisation Ayrshire Roads Alliance
does not deliver the
expected benefits outlined
in the Detailed Business
Case of June 2013. 
Benefit Realisation Plan to track the
delivery of each benefit and take
corrective action where appropriate it
has been developed. 
A 10 year Service Review is due tol
be completed within the next couple
of years. 
2 3  6 [C] 
Service Managers Head of Roads
– Ayrshire
Roads Alliance
The overall risk is medium
due to the various reviews
outlined in the Benefits
Realisation Strategy and
Plan now progressing
towards fruition.  Internal
management reports to be
prepared reflecting on
progress against Benefits
Realisation Strategy.  As at 1
April 2018 had realised
budget savings of £2.031m
against a target of £1.510m 
28/7/25
12 Performance Performance Metrics are
missed. The Service
monitors the metrics and
also compares
performance against the
APSE average. 
A standardised operational process
and procedures has been developed
to ensure efficient and effective
processes and verification measures
are in place. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Performance metrics are
reviewed and developed with
the Pentana System being
used to review performance. 
Performance is reviewed at
every Management meeting. 
28/7/25
51

Page 52

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
13 Procurement Insufficient due diligence
carried out by the Ayrshire
Roads Alliance in the
procurement of goods and
services. – standardised
processes and
procedures in line with
Council’s contract
procedures.
Standardised processes and
procedures have been developed to
ensure efficient and effective
processes and verification measures
are in place. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
28/7/25
14 Programme
Management
Programme scope,
schedule, objectives, cost
and deliverables are not
clearly defined or
understood. 
Estimating and / or
scheduling errors. 
Unplanned work that must
be accommodated. 
Lack of co-ordination /
communication 
Underestimated support
resources or overly
optimistic delivery
schedule 
Unresolved Programme
conflicts not escalated in
a timely manner. 
Unanticipated escalation
in Programme costs as a
result of uncontrolled
changes or continuous
Clear definition of scope, schedule,
objectives, cost, and deliverables
through Service Improvement Plan,
Benefits Realisation Strategy & Plan,
and Customer Service Strategy. 
A Programme Plan has been
developed which illustrates key
activities, team, timing, milestones,
and delivery of products. 
Incorporate unplanned work within
Programme Plan and minimise
impact on delivery of products
through parallel processes when
feasible 
Programme co-ordination and
communication conducted in
accordance with Programme
governance structure 
Support resources and delivery
schedule developed from robust
Programme Plan and previous
experience of similar Programmes 
Programme conflicts recorded in
Issues Log and progressed in
accordance with reporting
arrangements for project team 
Escalation of Programme costs
addressed through appropriate and
applicable corrective actions and
control measures. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Managed Risk 
28/7/25
52

Page 53

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
inflation of a project’s
scope beyond initial remit 
Unanticipated delays in
Programme timescale as
a result of uncontrolled
changes or continuous
inflation of a project’s
scope beyond initial remit 
Communication Strategy
to engage public
awareness not planned
on a joint Ayrshire basis 
Priorities change on
existing service delivery. 
Affordability of future
service payments. 
Councils withdraw or
cannot provide sufficient
support, or agreed level of
input is not provided
resulting in Programme
delays 
Delay of Programme timescale
addressed through appropriate and
applicable corrective actions and
control measures. 
Ensure that a robust Communication
Strategy and response network is
developed during planning stages of
Programme which incorporates
sufficient key review stages to ensure
effective communication of key
messages regarding deliverables and
progress 
Ensure that changes on existing
service delivery are communicated in
accordance with the existing Service
Level Agreement 
Ensure that East Ayrshire Council
and South Ayrshire Council are fully
aware of the budgetary implications
required to meet the on-going cost of
service provision, as detailed in the
DBC, and have fully committed
sufficient financial resources
following Business Case sign-off. 
Early identification of problems, and
dialogue with Council.  The Ayrshire
Roads Alliance is developing a
module to project manage work
requests received by other Service
providers with East and South
Ayrshire Councils. 
15 Health & Safety /
Risk & Insurance
Insufficient investment,
resources and on-going
maintenance to resolve
issues identified in Health
& Safety surveys of
depots are on-going. This
also includes ensuring
security is adequate. New
harbour facility was
constructed along with
Issues identified in Health and Safety
Surveys are recorded on Issues Log
along with corrective actions to rectify
/ bring up to the required standard.
To ensure that Health and Safety
processes are always followed, this
is a standing agenda item held at
monthly management meetings.  In
addition to a separate H&S group 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
South Ayrshire Council
continues to have ownership
for and maintenance of
depots/harbour within their
area.  Responsibility of
funding the various mitigation
actions identified in the
Issues Log sits solely within
the control of South Ayrshire
Council.  East Ayrshire 
28/7/25
53

Page 54

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
additional fencing, gates
and stillage for timber. 
Dredging is carried out bi-
annually.  Works have
been completed at
lifeboat station and new
sheet piling to be installed
along timber jetty. The
Ayrshire Roads Alliance
operates from and
manage risk of
enforcement action and
penalties should HSE
become involved.
that meets on a quarterly basis with
the H&S Officer.  Risk assessments
and safe systems of work have also
been developed and are in place with
H&S assistance.
Council has ownership and
responsibility for their depots. 
16
Development
Control – Road
Bonds
Inadequate coupon
values of Road Bonds
exposes the Roads
Authority to a potential
shortfall if the roads works
have to be completed by
them in the event that a
developer defaults.
The coupon value of Road Bonds
that are more than three years old
are reviewed to determine their
adequacy.  Where a shortfall is
identified, the developer will be
advised to increase the value of the
Road Bond held when an application
is made for an extension to the Road
Construction Consent (RCC), which
is normally valid for three years. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
If the road authority is
required to complete a
development road then only
the cost up to the value of
the Road Bond can be
recovered from the provider. 
Any shortfall has to be met
by the roads authority.  A
complete review of the
process of delivering road
bonds has been completed 
28/7/25 
17
Bridges and
Structures
Inadequate inspection
and maintenance of
structures, bridges and
culverts due to aging,
increased live loads,
cracking corrosion,
environmental effects
(freeze and thaw cycles)
and fatigue
Rolling programme of repair,
rehabilitation or replacement (for
weak bridges) through Council
Capital Budgets. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
Bridges and culverts are
defined as structures with a
span in excess of 900mm.  28/7/25 
18 
Flooding Receipt of less Grant
Aided Expenditure
funding than anticipated
for flooding mitigation
schemes administered by
SEPA.
Potential lack of sufficient
funding for flooding
mitigation schemes if cost
of schemes exceeds
Grant Aided Expenditure
(GAE) due to Relief
Events or Force Majeure.
Seek capital funding from Council(s)
to bridge funding gap for flooding
mitigation schemes declared in Flood
Risk Management Plan. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
The Councils have a legal
duty under the Flood Risk
Management (Scotland) Act
2009 to implement flooding
mitigation schemes declared
in the Flood Risk
Management Plan. 
Only 80% of principal funding
for flooding mitigation
scheme.  However increased
costs due to relief events or
force majeure is not funded 
28/7/25 
19
Financial Potential swift decline in
value of Pound Sterling
due to Force Majeure or
material adverse change
Mitigation measures would be put in
place to prioritise front line services
as detailed in the specific Business  2  4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk.  The impact
of the United Kingdom exit
from the European Union has
still to be evaluated.  On-
28/7/25
54

Page 55

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
resulting in increased
costs in terms of fuel
prices, interest rates and
insurance premiums.
Continuity Plans for office, depot and
harbour, as applicable
going discussions with
Transport Scotland, COSLA
and Ayrshire Roads Alliance
on the impacts on the
transport network. 
20
Contractual
Agreement
Potential swift decline in
value of Pound Sterling
followed by market
volatility over the short to
medium term resulting in
suppliers and contractors
terminating agreements
due to Force Majeure or
material adverse change.
Mitigation measures would be put in
place to prioritise front line services
as detailed in the specific Business
Continuity Plans for office, deport
and harbour, as applicable. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk.  The impact
of the United Kingdom exit
from the European Union has
still to be evaluated.  On-
going discussions with
Transport Scotland, COSLA
and Ayrshire Roads Alliance
on the impacts on the
transport network. 
28/7/25 
21
GDPR  The existing Data
Protection Act 2018 was
brought about by the
General Data Protection
Regulation (GDPR) which
is an EU Regulation that
sets out the changes that
the UK will implement in a
new Data Protection Act.
Follow Corporate Procedures 
3 3  9 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25 
22
Presence of Coal
Tar within the
carriageway
networkimpac
Coal Tar is a known
material used in the
construction of
carriageways until the
mid-80s and is now
known as a carcinogen
and hazardous waste
material.
Reduce the level of risk by coring all
works prior to design.
Ensure an appropriate solution within
the design is prepared which is either
to retain in-situ and record presence,
or remove and dispose of in
accordance with current guidelines. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk; Ayrshire
Roads Alliance has a duty of
care to all employees in
accordance with the Health
and Safety at Work Act
1974,Construction Design
and Management
Regulations 2015 and the
disposal of hazardous waste. 
28/7/25 
23
Service The impact of the United
Kingdom exit from the
European Union
Mitigation measures are in place to
prioritise front line services as
detailed in the specific Business
Continuity Plans for office, depot and
harbour as applicable. 
4 3  12 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed risk.  Ongoing
discussions with Transport
Scotland, COSLA and
Ayrshire Roads Alliance on
the impacts on the transport
network. 
28/7/25 
24
Transport Increased cost of vehicle
maintenance due to lack
of investment in fleet
replacement
To mitigate the risk of increased
maintenance costs through lack of
fleet investment a comprehensive
maintenance programme is in place
for all vehicles in addition to a vehicle
replacement programme developed
to identify the optimum life cycle for
fleet. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   
28/7/25 
25
Transport Loss of operational base
for any reason
(Crookedholm Depot)
To mitigate the impact of the loss of
the transport depot and garage,
business contingency plans have
been developed that highlight how
and where office based staff will work
in addition to the steps to ensure that 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   
28/7/25
55

Page 56

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
maintenance is undertaken, which
would be to activate external
maintenance frameworks. 
26
Transport Loss of public utilities for
an extended time
including electricity and
water.
Business continuity plans are in
place to allow for the whole service to
continue to function in the case that
utilities are lost for an extended
period of time. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25 
27
Transport Loss of confidential
information and
appropriate handling of
information will lead to
breaches of data
protection and potential
significant financial
penalties being incurred
by the Council
All staff that handle personal details
have undertaken e-learning to advise
of appropriate data protection steps
required and where appropriate
electronic systems are in place for
recording and management of
personal data to avoid paper being
lost or misplaced. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25 
28
Transport Passenger transport –
late / non-attendance /
vehicle breakdown by pick
up vehicle – Failure of
service as Service as user
would miss Transport link
connection / arrives late at
destination activity / part
activity
The delivery of passenger transport
is managed on the Council’s behalf
by SPT.
If there is an issue where there is a
failure in service provision SPT would
be required to organise a
replacement service, working in
conjunction with Officer locally within
EAC. 
2 2  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25 
29
Transport Passenger transport –
escort not in attendance
ASN contracts / Council
owned vehicles service
failure.  Service not able
to be provided until escort
arrives.  Server user
misses activity / part
activity  
Should an escort not be available
H&SC services would arrange to
provide another responsible
individual available to ensure that the
service can be delivered.
In the unlikely case this cannot be
accommodated, the parent would be
notified and alternative arrangements
made for the transport of the child to
the school. 
1 4  4 [T]
Strategic      
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25 
30
Transport No driver available to
deliver service due to
annual leave / sickness
absence. Service not able
to be provided service
user misses activity / part
activity 
Any shortage of driver would result in
arranging for an alternative qualified
individual within transport services to
drive, or to work with Coalfield
Community Transport to deliver the
service. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25 
31
Transport Passenger transport :
Emergency closure of
schools and contractors
unable to provide
Should schools need to close
unexpectedly, all parents will be
contacted to request that children are
collected ASAP.  Teachers will
remain with children until the last one  1  4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25
56

Page 57

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
transport within relevant
timescales - 
has been collected safely by a
parent. 
32
Transport Passenger Transport:
Documentation out of
date risk to service users. 
Potentially inappropriate
individuals, inappropriate
vehicles used being used
to provide service 
Documentation is reviewed and
approved on an annual basis to
ensure that the correct data is held
for pupils, parents, schools and
transport operator information.  1  5  5 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25 
33
Transport Passenger Transport:
Contractor unable to fulfil
obligations due to
bankruptcy etc.  Service
failure not able to be
provided until alternative
arrangements made. 
Server user misses
activity / part activity
SPT manage all transport on behalf
of EAC.  In the case of a contractor
going out of business, an alternative
contractor will be sought.  Where this
cannot be provided, parents will be
contacted and alternative
arrangements may need to be made
for the provision of transporting
school children such as providing a
mileage allowance to parents until an
alternative solution can be
implemented. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   28/7/25
34 EV Charging Tariff Negative feedback to both
authorities
On approval by Cabinets a full
programme of public communication
to be issued
2 3 6[R] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   16/2/24
35 Material Shortages
and Price Increases
Steel products, timber,
electrical equipment and
aggregates have seen a
price increase with
aggregates prices falling
back in the spring.
This is as a result of
market cost increase of
raw material affecting
suppliers, supply chains,
shipping, transportation
and Construction costs. 
Increased admin at UK
ports due to EU Trade
Cooperation has resulted
in increased
transportation costs, raw
materials and surcharges.
Where there are problems we are
working with supplier to optimise
deliveries to get procure best value
under the circumstances.
4 3 12 [C] Strategic
Manager
Head of Service
– Ayrshire
Roads Alliance
This will be under constant
review with contractors. 
28/7/25
36 Storage Related
Risks
Theft / Damage of Stores Risk is very low as there are many
measures that have been put in
place.  For example – CCTV
cameras, secure entry to the depots,
insurance covers all depots for theft /
1 4 4 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   
28/7/25
57

Page 58

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
damage, robust store person / key
holder procedures in place
37 Ash Die Back Potential for death or
injury as a result of ash
dieback related accidents,
both to professionals
working on trees, and to
the general public
Increased safety issues
due to declining ash trees
on roads, owned and
managed land such as in
county parks, housing,
estates, schools, routes to
school, active travel
routes and other well-
used paths
Risks to statutory
functions or service
delivery such as retaining
safe schools, public open
spaces or roads
Risks to staff and
community from trees on
adjacent land falling into
your estate
Ash Trees within the public network
with a fall range will be inspected and
prioritised.
P1 Immediate Felling
P2 Monitor and Fell if moved to P1
P3 Monitor and Fell if moved to P1
Private landowners will be advised of
any trees within their land which
could impact on the public network.
Under Road Scotland Act 1984 ARA
have the authority to pursue
landowners and remove diseased
trees and recharge
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   
28/7/25
38 Ukrainian Crisis /
Middle East Crisis
Increasing cost of bitumen
and the potential of short
supply due to Russian
sanctions and increased
costs.  May also result in
rising fuel and delivery
costs
Pre-programming with suppliers and
contractors as well as monitoring
through revenue period reviews.
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   28/7/25
39 Fuel - Red Diesel  No longer permitted to
use red diesel within
construction vehicles.
This has an impact on
project costs and the
overall programme.
Reviewing alternative forms of fleet,
however, this brings additional cost.
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   28/7/25
40 EV Charging
concession contract
Failure to attract a private
partner
Robust and detailed tender package
to be issued through the procurement
process
2 3 6[T] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   28/7/25
41 Energy Costs
fluctuation
Impact on revenue
budgets
Robust period review of energy costs
for lighting and EV chargers.
3 3 9[C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance 
28/7/25
58

Page 59

APPENDIX 1: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Official
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
42 Land acquisition
and other legal
resource
requirement
Lack of available
resources resulting in
delays to projects
Triage projects at regular update
meetings. Consider outsourcing
Legal work.
4 3 12 [T&R] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance 
19/05/25
43 Procurement Scotland Excel Contract
Framework delays
Review alternative Frameworks to
procure Material and Services  5  3  15 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Alternative Framework
documentation would be
significantly different from
SXL.  Additional staff time
may be require to complete. 
28/7/25
44 United States
Trade Agreement 
This is as a result of
market cost increase of
raw material affecting
suppliers, supply chains,
shipping, transportation
and Construction costs. 
Where there are problems we are
working with supplier to optimise
deliveries to get procure best value
under the circumstances.
4 3 12 [C] Strategic
Manager
Head of Service
– Ayrshire
Roads Alliance
This will be under constant
review with contractors.  28/7/25 
59

Page 60

60

Page 61

Official
AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
05 September 2025 
Report by the Head of Ayrshire Roads Alliance
______________________________________________________________ 
SUBJECT: ROADWORKS PROGRAMME 2025/26
______________________________________________________________ 
Purpose of report 
1. The purpose of this report is to advise the Joint Committee on the progress of
work through the road improvement programmes within East Ayrshire and South
Ayrshire for financial year 2025 to 2026. 
Recommendations 
2. It is recommended that Joint Committee: 
(i) Notes, the Ayrshire Roads Alliance programmed works 2025/26
(ii) Otherwise, notes the contents of this Report.  
Background 
3. The budget allocation for East and South Ayrshire Councils Roads Investment
Programme for FY 2025/26 can be seen in tables 1 and 2 below respectively. 
Table 1: East Ayrshire Council Roads Investment Programme 2025/26 
Programme Area Budget (£m)
Carriageway Resurfacing 2.081
Footway Resurfacing 0.084
Street Lighting 0.215
Traffic & Transportation incl. road safety 0.330 
Active Travel 0.050
School Streets 0.050
Bridge and Culvert Strengthening 
(incl. road slips)
3.500
Car Parks incl. Multi-storey demolition 0.820
Fleet 0.600
Total  £7.730
External Funding (Confirmed) 
SPT – Behaviour Change £0.385
Transport Scotland – Behaviour Change £0.116
ATIF - Tier 1  £0.758
Developer Contributions/Route Action
Plans
£0.359
Bus Infrastructure Fund – Tier 1 £0.645
SG – EV Infrastructure Fund £2.800
Agenda Item 6
61

Page 62

Official
Total £ 5.063
External Funding (To be Confirmed) 
Sustrans – Annick Valley Stage 2 £0.165 
(Award letter to be issued)
ATIF Tier 2 - Design £2.405 (Tbc.)
Road Safety Improvement Fund £0.300 (Tbc)
Total £2.870 (Tbc.) 
Table 2: South Ayrshire Council Roads Investment Programme 2025/26 
Programme Area Budget (£m)
Carriageway & Footway Resurfacing 1.581
Street Lighting 0.150
Bridges Capital 0.881
Millennium and Craigholm Bridges 0.145
C12 Dunure slope stabilisation 0.130
Vehicle restraint barriers 0.073
Cattle grid renewal 0.033
Girvan Harbour Jetty repairs 0.504
Local Flood Risk Plan 0.153
Ayr Depot 0.250
Climate Changes St Ninians Park 0.255
EV Charging Infrastructure 0.281
Total £4.436
External Funding (Confirmed) 
SPT – Behaviour Change £0.170
Transport Scotland £0.116
Tier 1 – Active Travel Funding £0.737
ATIF–Tier 2(Dundonald – Barassie) £2.700
Ayrshire Growth Deal £0.857
Levelling Up Fund (Active Travel) £4.000
Levelling Up Fund (Burns Statue) £15.000
Bus Infrastructure Fund – Tier 1 £0.382
Total £23.962
External Funding (To be Confirmed) 
Sustrans £0.753 
(Award letter to be issued)
ATIF Tier 2 - Design £1.626 (Tbc.)
Road Safety Improvement Fund £0.270 (Tbc.)
Total £2.649 (Tbc.) 
Note: Several funding applications have still to be confirmed. The affected areas
of potential funding are denoted by the use of “£Tbc.” in Tables 1 and 2 above. 
Main report/main issues 
4. Surfacing programmes for FY 2025/26 are contained within Appendices 1 and 2. 
62

Page 63

Official
Capital Resurfacing 
5. Due to carcinogenic properties in Coal Tar, additional control measures are in
place which requires coal tar testing to be undertaken before the commencement
of works. 
6. The requirement for a new coring contract has meant that the start date for some
of our resurfacing sites has been delayed until the sites can be tested when the
coring contract is awarded in September. 
7. The Capital budget for both authority areas is committed and it is anticipated
remaining surfacing works will commence late November.  Depending on
weather conditions during the winter months there is a possibility that some
works may require to be carried over into financial year 2026/27. 
8. In South Ayrshire we have completed 40% of the carriageway programme with
an anticipated completion date of March 2026.  The footway resurfacing
programme commences in September 2025 with an anticipated completion date
of November 2025 with some sites identified for surfacing being carried over into
financial year 2026/27 as detailed in appendix 1. 
9. Due to the delay with the Coring Contract, there is a risk resurfacing works may
not be completed as planned during December to March 2026, owing to potential
unsuitable winter weather conditions.   As an alternative in South Ayrshire we are
proposing to carry out overlay works on sites which do not require planing and
associated coal tar disposal prior to winter. These sites could potentially be
surface dressed in the future.  It is therefore proposed that 6 resurfacing sites be
carried forward into 26/27 programme to ensure works are completed under
more favourable conditions. 
10. In East Ayrshire 11% of the carriageway resurfacing programme has been
completed as detailed in appendix 2 
11. During a more detailed inspection undertaken on the A71, Kilmarnock from
Moorfield Roundabout to the North Ayrshire Boundary, it was discovered the
condition of the carriageway surface was worse than initially anticipated and the
engineering decision was made to allocate a further £400k+ towards this project
thus allowing the full length to be completely resurfaced with new road markings
and cats eyes being installed. 
King Street Fire – Kilmarnock Town Centre 
12. At around 21:00 hrs on the evening of Monday 14th July a huge fire took hold of
a property in King Street with the first 48 hours, the scene was under the direct
control of Police Scotland and Scottish Fire and Rescue.  Ayrshire Roads
Alliance under the direction of the police incident commander coordinated road
closures and diversions around the scene and arranged for heras fencing to
secure the site.   
63

Page 64

Official
13. Ayrshire Local Resilience Partnership (ALRP) was activated followed by a
coordinated response to the immediate aftermath and recovery phase
demonstrating the strength of partnership working between our blue light
emergency services, East Ayrshire Council, Ayrshire Roads Alliance and Utility
Companies. 
The President and Vice President of the United States visit to Ayrshire 
14. Adopting a “Gold, Silver & Bronze” Command and Control structure chaired by
Police Scotland, East Ayrshire, South Ayrshire & Ayrshire Roads Alliance in
partnership with all agencies including the US Secret Service supported the
policing operation around the Presidential visit on 25th until 31st July.25 and
shortly thereafter also accommodated the Vice President visit on 13th August until
17th August.25. 
East Ayrshire Council residential road and footway repairs (Additional Revenue
Funding) 
15. At Cabinet on 13 March 2025, East Ayrshire Members Initiatives approved £800k
revenue funding for residential and footway repairs with locations identified
detailed within Appendix 2 of this report with 13% complete to date. 
South Ayrshire Council Ward Investment and Promenade Programme 2025/26 
16. Officers within our engineering disciplines continue to develop work schemes
identified by Ward Members under the South Ayrshire Council Ward Investment
Programme for 2025/26 as detailed within Appendix 4 of the report. Sites will be
further added as discussions progress with Officers and Ward Members. 
Timber Transport 
17. As reported at the last joint committee in June 2025 neither authority area was
successful in their bids for grant funding from the Timber Transport Fund. 
18. Officers are committed to reviewing our application process and an early meeting
will be arranged with the Timber Transport Consortium when the window opens
for 2026/27 applications. 
Street Lighting 
19. The Scotland Excel Street Lighting Material Framework has still not been issued
and this is hampering the completion of the LED project in the East.  This has
been ongoing for 3 years and with assistance from our Procurement colleagues
after exploring alternative options we have recently issued a tender via the YPO
‘Highway Electrical Installations’ procurement framework for the supply of street
lighting materials and sundry electrical items. 
20. The Street lighting column and cable replacement programme of works which
incorporates LED lanterns is detailed in Appendix 1 and 2. 
64

Page 65

Official
Electric Vehicle Infrastructure 
21. The Electric Vehicle Infrastructure Fund (EVIF) programme with the number of
public chargers installed to date is listed within Appendix 3 for South and East
Ayrshire respectively. 
22. East Ayrshire Council is the lead authority for the PAN Ayrshire Public Electric
Vehicle Charging Strategy. The project has secured a grant of £2.8million and
work continues on the procurement phase. Following the previously approved
business case, further papers have been presented to the cabinet regarding the
introduction of an EV charging tariff, which has been implemented across all
three Ayrshires as of 1st January 2025. A further increase to tariff was
implemented on 1st July 2025. This tariff aims to establish a sustainable funding
model and attract private investment. 
23. Work continues on the tender documentation for the Pan Ayrshire concession
contract with the appointment of Mott MacDonald as consultants to assist with
the collation of the relevant documents required for tender. The Single
Procurement Document (SPD) was issued on 3rd March 2025 for the initial stage
of tendering, followed which we received numerous bids. The second part of the
tendering process is currently ongoing, with the Invitation to Tender (ITT) to be
published in September 2025 for the shortlisted bidders, followed by contract
award in January 2026. 
24. Under the Public Charge point regulations 2023 legislation all Rapid Chargers
are required to be able to accept contactless payment by 24th November 2024. 
Ayrshire Roads Alliance has secured funding from Transport Scotland
Contactless Compliance Grant Funding to replace/activate/retrofit eligible CPS
rapid chargers to incorporate contactless payment. Works have been carried out
to replace the non-compatible units and to activate contactless terminals on
compatible rapid chargers. 
25. Replacement of 22kW charger at Troon Swimming Pool will be funded from SAC
Capital budget but is on hold until the concession Contract is awarded in
December 2025. 
26. Replacement of 50kW chargers at Burns Statue Square, Ayr and Girvan Harbour
have been replaced and commissioned. 
Structures 
27. Land acquisition and/or access agreements alongside environmental license
requirements continue to cause delays to a number of projects. ARA are working
closely with EAC Legal/Estates and relevant stakeholders to progress these
issues. 
28. Appendix 2 details East Ayrshire Council Bridges Capital programme for
2025/26. 
65

Page 66

Official
29. A713 Polnessan Upper Bridge - ARA have erected temporary traffic signals due
to subsidence in the carriageway. Traffic lights will remain in place until the slope
has been stabilised. Project is near tender ready. 
30. B741 Coal Glen Embankments works to be retendered following discussion with
SPEN regarding utilities in the vicinity of the works. 
31. A735 Lochridge Culvert - general culvert repair works ongoing. Scope of work
increased on site due to poor ground conditions. 
32. ARA are working with EAC Legal/Estates to acquire land at West Clerkland
Bridge through a Compulsory Purchase Order. The bridge has been shut to
vehicular traffic since 2012 and shut to both pedestrians and vehicular traffic
since 2021. 
33. 3no. bridges on the A71 between the Bellfield Interchange and Moorfield
Roundabout need replacement expansion joints. A consultant was appointed to
explore options in removing the joints and making the structures semi/fully
integral. It has been decided that in the meantime 2 joints that are repeatedly
failing will be replaced with asphaltic plug joints. 
34. B730/10 Littlemill Bridge - land acquisition complete after years of negotiation.
Tender documents to be reviewed and works tendered with a view to start on
site in Spring 26. 
35. Contract awarded for low bridge sign upgrades at 5 structures in Kilmarnock and
Kilmaurs. 
36. South Pier Quay at Girvan Harbour – tenders for steel plate repairs to the existing
sheet piles and grouting is anticipated to be issued in August/September with
works completed by the end of 2025. 
37. The detailed design of the Girvan Harbour Timber Jetty works are progressing
with the Contract documentation substantially complete.  The Tender will be
issued once the South Pier Quay tenders have been returned and costs known. 
38. The A79/30 Victoria Bridge Concrete Repairs and Painting has been completed. 
39. The Contract Documentation for Girvan Harbour dredging and land based
material disposal has been finalised and are with Procurement for Tender issue. 
40. Ayr South Pier - as previously reported at the last Shared Service Joint
Committee in June 2025, funding to employ a consultant to carry out an
underwater dive survey and structural assessment has not been secured. This
is a matter of concern as the importance of a dive survey and assessment was
highlighted following the development of a sink hole in a verge area at the end
of the South Pier. 
66

Page 67

Official
Traffic & Transportation 
41. Active Travel Infrastructure Fund (ATIF) Tier 1 grant funding for both autjority
areas has been received from Transport Scotland.  Active Travel projects using
the Tier 1 funding is currently in development, and will be implemented over the
course of the current financial year. 
42. Grant awards have been confirmed from Transport Scotland for both EAC
(£645,000) and SAC (£382,000) from the Bus Infrastructure Fund – Tier 1. This
unforeseen funding is directly awarded and paid to local authorities as part of the
General Capital Block Grant (GCBG) Allocation. ARA are currently developing
delivery programmes for both EAC and SAC areas and reports will be presented
to both Cabinets with proposed programmes of work for review and approval. 
43. Confirmation of the Road Safety Improvement Fund grant allocations is pending
for both authority areas.  Schemes are currently being identified and prioritised
as listed in the appendices but may be subject to change pending Transport
Scotland approval. 
44. Kilmarnock Bus Station refurbishment programme is now complete with Officers
currently reviewing the cleaning regime. 
45. The Contract for Cumnock Bus Station which include changes to materials and
the installation of a public address system is currently being prepared. 
Ayrshire Growth Deal (AGD) Roads Projects 
46. A Case for Change seeking approval of the changes to the Roads Infrastructure
project and also the Prestwick Proposition has now been approved by Scottish
& UK Governments. Ayrshire Roads Alliance will assist in the delivery of all these
projects for South Ayrshire Council. 
47. A Planning application for the construction of a new car park at Shaw Road,
Prestwick will be submitted in September 2025, this is a significant step forward
in the delivery of the AGD. 
48. Extensive ground investigations and environmental studies are currently being
undertaken on the remaining phases of the AGD in an attempt to accelerate the
design process and move more projects through to construction.
Levelling Up Fund
49. South Ayrshire Council successfully secured £20million of funding from the
Levelling Up Fund (LUF) round 3.£15million of this funding has been transferred
to ARA and will be utilised to redevelop Burns Statue Square. Balfour Beatty
have been appointed as the principle contractor, design is currently underway
and a delivery programme will be produced in the coming weeks. 
50. £1.2million of the LUF funding along with a £2.7million award from ATIF will be
used to construct a new Active Travel Route linking Dundonald to Barassie
67

Page 68

Official
Station, work is currently underway on this route and is scheduled to be complete
by 31st March 2026. 
51. The remaining £2.8million along with funding from the AGD & a bid to the ATIF
in January 2026 will be utilised to carry out significant improvements to the NCN7
from Prestwick to Barassie railway stations. Work will commence on-site late
2025 and will be complete by 31st March 2027. 
Active Travel 
52. The Active Travel Infrastructure Fund (ATIF) administered by Transport Scotland
has awarded £2.7million towards the construction of the Dundonald to Barassie
route. 
53. ARA submitted several funding applications to Sustrans in January 2025 to carry
out the next stages of the design process for several active travel routes across
both South and East Ayrshire Council, it has now been confirmed that Sustrans
will not receive funding from Transport Scotland as had originally been advised
and these applications have now been transferred to ATIF. No decision has been
taken on these application at this time. 
Ash Dieback & Other Species 
54. Appendix 5 of the report details the current condition data on all High Risk
roadside trees for both authority areas.  Surveys and programmed works for
removal are ongoing with 28-day notices being issued to owners and any
objections received referred to legal service. 
Implications 
55. 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning x  56 & 57
2. Governance x  58
3. Human Resources x  59
4. Equality and Fairer Scotland Duty  x 60
5. Financial x  3, 61 &
Appendix 1, 2
and 4
6. Risk x  62 & 63
7. Community Wealth Building x  64
8. Net Zero x  65 
68

Page 69

Official
Policy/strategic planning implications 
56. A well-maintained road network will contribute to achieving the 2015-2030
Community Plan objectives and associated 2021-2024 Delivery Plans 
57. The matters referred to in this report contribute to Priority 1 of the South Ayrshire   
Council Plan: Spaces and Places/ Moving around and the environment
(Outcome 1). 
Governance implications 
58. By virtue of the relevant statutory provisions, principally detailed within the Roads
(Scotland) Act 1984, the Council as local roads authority is required to manage
and maintain all publicly adopted roads within its area other than those which are
maintained and managed by the Scottish Ministers. 
Human resources implications 
59. The work programmes have direct impact on human resources and the Alliance  
will ensure all works are suitably resourced to maintain satisfactory progress. 
Equality impact and Fairer Scotland duty implications 
60. Equality Impact and Fairer Scotland Duty screening assessments will be
undertaken annually as required during the planning stage prior to the delivery
of the programme of works. 
Financial implications 
61. The Ayrshire Roads Alliance will deliver the strategic and local services as stated
in the Service Plan. The budget is provided by East Ayrshire Council, South
Ayrshire Council, and other external organisations. Appropriate scrutiny
arrangements are in place to manage these budgets. 
Risk implications 
62. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every 
Joint Committee. 
63. The Works Programmes, Service Plan and the Risk Register do not expose
either Council to an increased risk as they have been developed from existing
budgets and existing service commitment. 
Community Wealth Building implications 
64. The works programme provides economic levers to develop resilient, inclusive
local economies with more local spend and fair employment, as well as ensuring
that wealth is more locally owned and benefits local people. 
69

Page 70

Official
Net zero implications 
65. The Ayrshire Roads Alliance Service Plan and Carbon Strategy supports and
links to East Ayrshire Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment 
Appendices 
Appendix 1 - South Ayrshire Council Programme of Works 2024/26 
Appendix 2 - East Ayrshire Council Programme of Works 2025/26
Appendix 3 – EV Public Chargers
Appendix 4 - South Ayrshire Council Ward Investment and Promenade
Programme 2025/26
Appendix 5 – Ash Dieback Condition reports EAC & SAC 
Background papers 
• East Ayrshire Council – 2025/26 Road Asset Management Plan.  Investment
and Programme
• South Ayrshire Council – Road Improvement Plan 2025 - 2026 
Person to contact. 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail. jane.corrie@ayrshireroadsalliance.org 
Implementation Officer 
Craig Knape, Strategic Manager - Ayrshire Roads Alliance
Tel No. 01563 503164 
E-mail. craig.knape@ayrshireroadsalliance.org
70

Page 71

Official
Appendix 1 
South Ayrshire Council – Programme of Works 2024/26 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2024 to 2026   
Route
No
Town Road Name Works
Description
Scheme
Score
Estimate
d Cost
Cost to
Date
Variance
+/-
Comments
B734 Old Dailly Barr Old Dailly Old Dailly to Penkill
+ drainage
improvements
N/A £150,813 £163,932  -£13,119 Complete 
B7035 By Girvan Glendoune Houdston
Road (Coalpots)
Braetoll South + S
Power shut down
N/A £200,000 £206,251 -£6,251 Complete 
B743 By Mossblown Ayr / Mossblown? West from
Brocklehill Farm
53 £249,002 £249,239 -£237 Complete
C37 Auchincruive Barrackhall Gibbsyard  48 £123,861 123,873 -£12 Complete
Uncl Tarbolton Springfield Road Garden Street to No
50
46 £54,275 £53,851 +£424 Complete
B742 By Coylton B742 Council Boundary -
A70/Hillhead, Coylton
By Holebogs, S bend 59 £445,000 £440,506 +£4,494 Complete
B742 By Coylton B742 Council Boundary -
A70/Hillhead, Coylton
From A70 at
Hillhead south to
C21 Craigs Road
junction
56
B742 By Coylton B742 A70 Hillhead - B744
Jcn N Of Annbank, Coylton
From Meadowhead
Depot entrance
south-wards
55 Complete
B742 By Coylton B742 A70 Hillhead - B744
Jcn N Of Annbank, Coylton
Bridge of Coyle to
C2
52
B744 Annbank Weston Brae Full Length 53 £152,000 £207,822 -£55,822 Complete
B744 Annbank Browns Crescent 
Weston Avenue
Full Length
Craighall Way to
101 Weston Avenue
53
56
U77 By Coylton Hole Road Full Length 46 £82,867 £83,064 -£197 Complete 
B7023 Maybole Crosshill Road Full Length 56 £74,687 £72,215 +£2,472 Complete
Complete
Complete 
B7023 Maybole St Cuthbert's Road Full Length 53 £30,669 £41,792 -£11,123
B7024 Maybole Alloway Road Redbrae to Bypass 51 £55,922 £96,288 -£40,366
C122 By Maybole  C122 Gardenrose
Path/Maybole - School
Road/Minishant, Maybole
School to new
Bypass 
50  £58,095 £58,097 -£2 Complete
71

Page 72

Official 
C122 Gardenrose
Path/Maybole - School
Road/Minishant, Maybole  Ladycross to new
Bypass
B7023 Maybole Ballochbroe to Crosshill Dalhowan to C58  £275,435 £362,350 -£86,915 Complete
A719
PH 2
By Maidens 
By Dunure
Pennyglen/B7023 -
Kirkoswald Road/Maidens,
Maidens 
A719 Smithy
Bridge/Dunure - Croy
Brae, Dunure
B7023 Enoch Lodge
-Caravan Park 
Cemetery to
Drumshang
67 £281,669 £326,746 -£45,077 Complete 
Complete A719
PH 1
By Maidens  Pennyglen/B7023 -
Kirkoswald Rd & 
Turnberry Rd /Maidens,
Turnberry 
Morriston Farm to
Jct Blawearie 
Maidens to
Turnberry
56  £441,666 £540,857 -£99,191
Uncl Maybole Ashgrove Avenue Full Length  £88,954 £102,985 -£14,031 Complete 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – New Sites identified for 2024 to 2026 
B749 Troon Monktonhill Road Southwood jct to
Isle of Pin
59 £210,000 £265,328  -£55,328 Complete.
after excavation, additional
material was required to
regulate due to sand & soft
spots localised to lots of
areas in Troon 
B749 Troon Craigend Road Fullarton Drive
railway bridge to
South Beach
48 £167,500 £201,706  -£34,206  Complete
Overspend same as
Monktonhill Rd
B749 Troon South Beach  Lochend Road to
Academy Street jct
54 £200,000 £307,540  -£107,540  Complete.
Overspend same as
Monktonhill and Craigend. 
72

Page 73

Official
C44 Dailly Dailly to Turnberry Farden 500m
towards Drummock
39 £112,560 £71,137  +£41,422  Complete 
B7027 Barr Knowe Road Lochtonmill
southwards 
£63,000 £53,406.44 +£9,593  Complete 
B734 Colmonell Colmonell to the A77   £106,560 £150,273  -£43,713  Complete 
B7023 Maybole C58 to Cemetary   £297,606 £271,503  +£26,102  Complete 
A70 
C39
Coylton 
Ayr
Joppa 
Doonholm Road
Hole Road jct to
Pharmacy
Alloway to The
Loaning
35 
43
£179,321  £155,377  +£23,944  Complete
C145 Ayr Hillfoot Road Holmston Rd to
Holmston Dr
54 £91,875 £123,733 -£31,858  Complete
Uncl Maybole Queens Terrace/Chesney
Grove/Kincraig Avenue
Full Road 33
33
£166,275  £174,448  -£8,173  Complete
Uncl Maybole Cargill Road Full Road 47 £46,900 £48,224 -£1,324  Complete 
C1
(STTS)
Straiton Newton Stewart Road U8 towards Straiton
to U57
44 £120,400 £119.293  +£1,107  Complete 
B7045
(STTS)
Maybole Cassilis to Kirkmichael Rd Crorieshill Farm
northwards for
360m
44 £46,750  £51,700 -£4,950 Complete
Uncl Ayr Saltpans Road North from Glebe
Road
46 £112,249 £118,940 -£6,691  Complete 
Uncl Prestwick Morris Road Full Road 43 £55,000 £107,345 -£52,345  Complete
(presence of coal tar
increased costs)
Uncl Ayr Green Street Waggon Road to
Crown Street
42 £130,000 £214,584 -£84,584  Complete
(presence of coal tar
increased costs)
Uncl Prestwick Craigie Street Full length 39 £30,000 £36,725 -£6,725  Complete
B744 By Annbank B744 Belston/A70 -
Weston Avenue/Annbank,
Ayr
Auchincruive
Junction to
Glenview
52 £120,000  £139,872  -£19,872  Complete 
B742 By Maybole Dalrymple to Barnford
Farm
Dalrymple Road 46 £130,000  £138,058 -£8,058  Complete
73

Page 74

Official
Uncl Maybole Hicks Avenue Full cway & fway 30 £104,000 £133,263 -£29,263 Complete
Increased costs due to
combining footway,
kerbing
C59 Colmonell Craigneil Road B734 to Bridge  £67,000 £53,129 +£13,871 Complete 
Uncl Ayr Peggieshill (PH1) Dalmilling Rd to
Nursery Rd
44 £92,000 £99,038 -£7,038  Complete 
Uncl Ayr Kincaidston (PH1) Marigold Sq to
Honeysuckle Park
52 £185,000 £181,768 +£3,232  Complete
Uncl Girvan Louisa Drive Knockcushion St to
Duncan St 
£103,640 £91,410 +£12,230 Complete
Uncl Ayr Peggieshill Rd (PH2) Nursery Rd to
Fenwickland Ave
44 £100,000 £81,228 +18,772 Complete 
C74 By Ayr MacNairston Rd C105 to B742
junction
52 £97,608 £112,326 -£14,718 Complete 
B742 By Maybole Nether Culzean Dalrymple
Rd
Barnford farm to
Nether Culzean
42 £135,000 £130,022 +£4,978  Complete 
Uncl Ayr Ellisland Square (Contains
Coal Tar)
Full Length 42 £125,000  £85,289 +£39,710.80 Complete – final measure
Uncl Ayr Kincaidston Drive (PH2) Honeysuckle Park to
Dalmellington Rd
52 £100,000 £51,730 +£48,270 Complete – final measure
B742 Mossblown Sandyford Road From a point 180
metres east of A719
junction eastwards
for 680m
53 £140,700 £169,432 -£28,732 Complete
Uncl Ayr Dalmilling Road (Contains
Coal Tar)
Harthall to
Mainholm Rd
37 £275,000  £37,032.78 +£212,967.22 Complete – final measure
Uncl Prestwick Bellevue Road (TO BE TESTED) From Main Street to
Adamton Road 
£38,039   c/f to 2026/27 TBC
Uncl Girvan Todd Street (TO BE TESTED) Full length 31 £32,894   c/f to 2026/27 TBC
Uncl Girvan Fauldribbon Road (TO BE
TESTED)
Full length 34 £31,813   c/f to 2026/27 TBC
Uncl Girvan B741 Linfern Road (TO BE
TESTED)
NO.79 to no.3 near
Main Street
29 £100,517   Programmed to Commence
26/01/26
Uncl Maybole Carrick Street (TO BE TESTED) Ladyland Rd  to B77 33 £26,130   c/f to 2026/27 TBC
Uncl Maybole Wellington Street (TO BE
TESTED)
Ladyland Rd to
Carrick St
30 £18,090   c/f to 2026/27 TBC
Uncl Maybole Manse Street (TO BE TESTED) Drumellan St to
Abbott St 
£20,100   c/f to 2026/27 TBC
74

Page 75

Official
Uncl Girvan Hamilton Street (TO BE
TESTED)
Church Sq to Bridge
St
46 £49,655.55   Programmed to Commence
09/02/26
Uncl Ayr Chapel Park Road Full length 40 £55,984   2026/27
Uncl Prestwick St Cuthbert’s Rd St Andrew’s Ave to
Kirklandholm 
£38,587   2026/27 
Ayrshire Roads Alliance – Overlay surfacing (potential future surface dressing) 
U39 Dailly Hawkhill Road Old Dailly from
number 1 to
number 12
N/A £125,000   TBC 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2024 to 2026 
C17 Tarbolton Westport Footway North side 28 £17,370 £24,984 -£7,644 Complete 
Uncl Prestwick Hunters Avenue South from
Heathfield Road,
west side
23 £7,500 £5,393 +£2,107  Complete
Uncl Troon Morven Drive Cessnock Rd to
Dundonald Rd
(Northside) 
£15,072 £28,820 -£13,748 Complete
C151 Dailly Woodside Both sides from
Back St and
Hadyard Terr
30 £20,400 £17,147 +£3,253 Complete 
Uncl Crosshill Newton Street Church Side of road 30 £15,795 £14,440 +£1,355 Complete
Uncl Dailly Hadyard Terrace Inside footway +
part outer section
28 £54,400 £20,110 +£34,290 Complete 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for 2024 to 2026 
Uncl Mossblown Martin Avenue Mossblown 28 £28,300 £30,829 -£2,529 Complete 
B744 Annbank Weston Brae Full Length 28 £10,700 £5,761 +£4,939 Complete
B730 Dundonald Drybridge Road Bowling Green to
Kilnford Dr
28 £19,223   Works progressing on site
Uncl Ayr Bellevue Crescent Full Length 34 £37,800   TBC - tree inspection,
scope of work to be
determined
75

Page 76

Official
Uncl Maidens Ardlochan Road Full Length 30 £21,000   Programmed to Commence
24/10/25
Uncl Dailly Church Crecent Odd numbers full
length
30 £16,800   Programmed to Commence
03/11/25
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget allocation 
B743 Mossblown Mauchline Road Fourways to railway
bridge north side
28 £15,300   2026/27
Uncl Ayr Lochpark Slab replacement 23 £20,425   2026/27 
Ayrshire Roads Alliance - Lighting Programme 2025/26 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Ayr Ayr - Old Hillfoot Road, Hillfoot
Crescent & Souter Place
Old steel columns &
unreliable 5th Core 5 £30,000 Complete 
Ayr Cunningham Crescent & Area Unreliable 5th Core
Supplies 16 £40,000 Complete 
Troon Concrete Column
Replacements Ph3
Old deteriorated concrete
columns 43 £55,000 Awarded 
£125,000   
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26
(i) Road Safety Programme 
Town/Route Location Proposed Scheme Progress
Various Various locations   Various schemes (TBC), anticipated to
include:
• Route Action Plan for the
B743 at St Quivox;
• B743 review at Failford
Bridge;
• Speed reduction measures at
Coalpots Road at The
Avenue;
Development of a finalised
programme for the current financial
year will follow confirmation of any
grant award from Transport
Scotland’s Road Safety Improvement
Fund (RSIF).
76

Page 77

Official 
(ii) Safer Neighborhoods 
Town Location Proposed Scheme Progress
Phase 4 20mph schemes Various roads (TBC) 20mph speed limit schemes Discussion with SAC required to
identify appropriate settlements for
inclusion in Phase 4.
Various Various locations Vehicle activated signs upgrade Pending implementation of new
contract, and extents of upgrades will
be subject to budget. 
(iii) Rural Route Action Plans 
Route Location Proposed Scheme Progress
B743  Between the A77(T) and Auchincruive (St
Quivox)
TBC Listed under RSIF schemes above –
subject to confirmation of funding. 
(iv) Active Travel Infrastructure – ATIF & Sustrans 
Town Location Proposed Scheme Progress
Various Various locations • Various smaller schemes
under Tier 1 funding, details
TBC.   
Currently developing a package of
schemes to be progressed during the
current financial year making use of
the Tier 1 grant award.
Loans From Buchan Road to the A759 Loans to Troon Phase 3 Funding application unsuccessful, new
application submitted to ATIF for
2025/26
Loans From Dundonald Road to Buchan Road Loans to Troon Phase 2 £24,500 received to install permanent
monitoring equipment
• Bradan Road, Troon –
enhanced crossing points;
• Road Safety scheme, Links
Road, Prestwick.  
77

Page 78

Official
Dundonald To the northern side of the A759 Dundonald to Barassie Phase 1 Award received to treat Japanese
Knotweed on-site, full construction
funding application submitted to ATIF
for 2025/26.
Various Various Various Funding application unsuccessful, new
application submitted to ATIF for
2025/26
Girvan  Quay to Grangeston Girvan to Grangeston £27,378 received to complete RIBA
Stage 1, 
Ayr Town Centre Accessible Ayr £778,780 received to complete RIBA
Stage 4 of Route 1 Phase 1
Ayr-Girvan Ayr to Girvan Culzean Way £47,755 received to complete RIBA
Stage 1
Coylton Coylton Primary Access for All – Coylton £27,378 received to install permanent
monitoring equipment
Ayr, Prestwick & Troon NCN7 NCN Barrier Removal £113,500 received to remove barriers
from the NCN7 in Ayr Prestwick &
Troon to make the route inclusive.
Prestwick, Troon & Barassie NCN7 from Prestick Station to A759 Barassie Prestwick to Barassie £82,979 received to complete RIBA
Stage 2
Dundonald Junction of A759/B730 Dundonald Cross £80,000 received to install signals at
the junction of the A759/B730 
Ayrshire Roads Alliance - Structures Capital Programme 2025/26 [Includes works carried forward from 2023/24/25] 
Description   Work Type Estimated
Programme Cost 
Comments Variance +/-
A79-30 Victoria Bridge Concrete Repairs and Painting 
£432,776 
Completed  
0
A79-40  John Street, Ayr, Railway Bridge Parapets  £362,000 Design Phase.  
-£294,225
FB.AYR-70 River Doon Cycleway Footbridge (Millenium Br)
Refurbishment
£145,000 Design Phase Tender Documents completed
and Marine Licence applied for. 
£143,951
U740-10 Barbieston Bridge Replacement Design  £86,820.00 Design Phase 50% - 50% EAC / SAC funded
project as this is a boundary bridge. 
£80,025 
Various Locations
Vehicle Restraint Barrier Renewal £50,000  Design Phase Contract awarded works
ongoing  +£50,000
78

Page 79

Official
Various Locations Cattle Grid Renewal Programme £33,600 Design Phase Contract awarded works
ongoing
£-33,600
C12 Dunure Station Road Dunure, Slope Stabilisation 
£130,000
A 70m long gravity retaining wall option has
been selected as the most optimum solution.
Detailed design and contract preparation is
currently underway, however the capital
budget currently available for this project is
insufficient for the proposed solution –
additional funding required. To be discussed
with finance. 
-£124,087
Girvan Harbour Girvan Harbour South Pier Repairs £136,000 The South Pier Quay has been assessed to
have a load carrying capacity of 0.5 tonnes
per square metre. Following dive surveys
undertaken earlier this year the option
chosen to extend the life of the structure is
steel plate repairs to the existing sheet piles
and grouting of the voids.   
Completion and submission of the contract
documentation was delayed in order that the
significant damage caused to the South Pier
Quay by the Q-Varl boat, when it broke its
moorings in a storm, could be assessed and
any repairs required could be included in the
contract documents. Tenders to be issued in
August with works completed by the end of
2025. 
£118,989
Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles 
£504,887
The sediment transfer model has been
completed including options to deal with the
defective sheet piling. The recommended
option is to replace only the piling on the
curved section from the lifeboat station.
Contract documentation substantially
complete and will be issued once tenders for
the South Pier Quay works have been
returned and costs are known. 
-£504,887 
£1,881,083 
79

Page 80

Official
Appendix 2 
East Ayrshire Council 
Ayrshire Roads Alliance – Carriageway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 
ROAD LOCATION Estimated
Cost
Cost to Date variance +/- Comment
A71 Dual Carriageway  From Moorfield Roundabout – Target Worst Sections £300,000.00   Complete – final measure
A736/U20 Junction
Contribution to North
Ayrshire to complete
EAC section
Junction Contribution to North Ayrshire to complete
EAC section
£15,000.00 
To be programmed
A735  From Lochridge House North Entrance to Windmill
factory Farm £182,354.25  
To be programmed
A735 Rigg Street
Stewarton From B778 to Brown Street £60,606.00 
To be programmed
B7046 Skares From Junction Newfield Rd to Recycling Centre
Additional section into Skares £116,000.00 £152,936.00  Complete – final measure
B769 Stewarton  From Stewarton to North Ayrshire Boundary £219,375.00   To be programmed
B743 Mauchline High
Street From A76 to Loans (School) £52,680.60  
Programmed to Commence
11/10/25
B7037 Titchfield
Street Galston From Mini Roundabout to Orchard Street £97,500.00  
Programmed to Commence
06/10/25
B7038 Kilmarnock
Campbell Street From: Fire Station AC / To: Willock Street                   £41,595.40  
Programmed to Commence
24/01/26
C3 Barskimming Road
Mauchline From Loudoun Street to StationRoad £74,074.00  
Programmed to Commence
18/10/25
C108 Stewarton From Greensland to Boundary £114,750.00   To be programmed
C22 Coal Road
Auchinleck From Railway bridge to Barbieston Road £35,612.50  
To be programmed
U55 Galston  From U56 approx 1000m Westwards £78,750.00 £60,954.21  Complete – final measure
Kilmarnock New Mill
Road From Chapmans Terrace to end £45,584.00  
To be programmed
Kilmarnock Whatriggs
Road From Tinto Avenue to Haining Avenue £35,612.50  
To be programmed
Kilmarnock East Shaw
Street From Lidle to and around mini roundabout £37,814.00  
Programmed to Commence
04/10/25
Kilmarnock Bentink
Street On Approach to Mini roundabout £20,797.70  
Programmed to Commence
04/10/25
80

Page 81

Official
Kilmarnock Bellsland
Grove Full Length £19,080.00  
Programmed to Commence
04/10/25
Kimarnock Beech
Avenue From Portland Road to Larch Place £84,501.40  
Programmed to Commence
11/10/25
Kilmarnock Pine Road Full Length £42,022.75  
Programmed to Commence
25/10/25
Kilmarnock Old Irvine
Road From Lindsay Street to Grange Street £37,464.35  
To be programmed
Kilmarnock
Brackenhill Avenue Full Length  £32,323.20  
To be programmed
Kilmarnock Arran
Avenue  Full length  £36,182.30  
To be programmed
Kilmarnock Lainshaw
Avenue One Section £71,225.00  
To be programmed
Kilmarnock Townend Full Length £27,065.50   To be programmed
Stewarton Avenue
Square Access Road into car park £11,396.00  
To be programmed
Kilmaurs East Park
Crescent Full Length £34,045.55  
To be programmed
Galston Western
Road Outside Primary School £29,487.15  
Complete – final measure
Hurlford Mayfield
Avenue Full Length £57,855.42  
To be programmed
Fenwick Skernieland
Road From Old A77 Slip to Rysland Terrace £44,053.31  
To be programmed
Cumnock Hearth
Road Full length £89,909.25  
Programmed to Commence
15/12/25
Drongan Lane
Crescent Full Length £27,195.00  
To be programmed
Bellsbank Corserene
Terrace Full Length £29,526.00  
To be programmed
Dalmellington
Gateside Road Broomknowe to B741 £31,080.00  
To be programmed
Dalrymple Cedar
Terrace  Full Length £15,540.00  
To be programmed
Drongan Mill o Shield
Road From Coyle Avenue and Garrowhill Drive £37,749.25  
To be programmed 
81

Page 82

Official
Ayrshire Roads Alliance – Footway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 
Ayrshire Roads Alliance - £800k Residential Carriageway/Footway Improvement Programme 2025/26 
WARD Location Estimated
Costs
Cost to Date Variance +/- Comment 
1
Carriageway - Stewarton Dornie Close  £9,120.00   To be programmed
1 Carriageway - Stewarton Braemore Road £11,310.00   To be programmed
1 Carriageway - Stewarton Kirkmuir Drive £54,000.00   To be programmed
2 Carriageway - Kilmarnock Tourhill Road £5,580.00   Complete – final measure
2 Carriageway - KilmarnockAuchencar Drive £15,120.00   Complete – final measure
2 Carriageway - KilmarnockWardneuk Drive £6,165.00   Complete – final measure
3 Carriageway - Kilmarnock Woodside Avenue    To be programmed
FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment
Catrine - Newton
Street Outside School £7,290.00  
To be programmed
Auchinleck - Main
Street From Surgery to Council Car Park £21,870.00  
To be programmed
Cumnock -
Glaisnock Road Outside Cemetery £19,044.00  
To be programmed
Kilmarnock -
Dundonald Road Outside School £16,200.00  
To be programmed
Kilmarnock -
Gilmour Street Various Locations £21,060.00  
To be programmed
Stewarton - High
Street From Old Bank to Church £16,200.00  
To be programmed
Stewarton -
Lainshaw Street Standalane to Sainsbury’s Rear Entrance £19,260.00  
To be programmed
Fenwick - Skerniland
Road Both Sides £22,680.00  
To be programmed
Galston - A719
Opposite Loudoun
Academy From Nursing Home to Barriered Section £8,100.00 
To be programmed
82

Page 83

Official
£60,000.00
4
Carriageway - Kilmarnock - Anderson Place/Bannerman
Drive and Drummond Place
£46,200.00   Programmed to Commence
25/10/25
4 Carriageway - Kilmarnock Sparrow Gardens £12,960.00   Programmed to Commence
12/01/26
5 Carriageway - Kilmarnock Simonsburn Road £9,225.00   To be programmed
5 Carriageway - Kilmarnock Elderslie Crescent/Ayr Road £13,500.00   To be programmed
6 Carriageway - Newmilns Sheilds Road £28,050.00   To be programmed
6 Carriageway - Darvel West Donnington Street £16,800.00   Programmed to Commence
06/12/25
6 Carriageway - Darvel Jaimieson Road £17,400.00   Complete – final measure
7 Carriageway - Mauchline Clarinda Crescent £23,100.00   Programmed to Commence
08/09/25
7 Carriageway - Mauchline East Park Avenue £25,560.00   Programmed to Commence
08/09/25
7 Carriageway - Mauchline Southpark Avenue £7,800.00   Programmed to Commence
08/09/25
7 Carriageway - Mauchline Welton Road £19,950.00   Programmed to Commence
23/09/25
7 Carriageway - Mauchline Mansfield Road £43,500.00   Programmed to Commence
23/09/25
8 Carriageway - Cumnock Latta Crescent £20,010.00   Programmed to Commence
12/01/26
8 Carriageway - Cumnock Nans Terrace £16,500.00   Programmed to Commence
24/11/25
8 Carriageway - Cumnock Lorimer Crescent £44,550.00   Programmed to Commence
01/12/25
8 Carriageway - Cumnock Hearth Place £24,000.00   Programmed to Commence
08/12/25
8 Carriageway - Cumnock Bank Avenue £21,420.00   To be programmed
8 Carriageway - Logan Holmhead Crescent £36,600.00   To be programmed
8 Carriageway - Logan Dixton Avenue £21,690.00   To be programmed
9 Carriageway - New Cumnock Castlemains Avenue £42,000.00   To be programmed
9
Carriageway - Dalmellington Church Hill/Melling
Terrace £36,330.00   To be programmed
9 Carriageway - Dalmellington Knowehead £41,820.00   To be programmed
9 Carriageway - Ochiltree Gallowlee Avenue £20,490.00   To be programmed
4 Footway – Hurlford Furnace Court £15,750.00   To be programmed
83

Page 84

Official
6 Footway – Galston Bridge Street £3,750.00   To be programmed
6 Footway – Darvel Glen Crescent £17,500.00   To be programmed 
Ayrshire Roads Alliance - Lighting Capital Programme 2025/26 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Dalmellington Riecawr Ave, Area. Unreliable 5th Core. 22 £65,000 Completed
16 Jun 2025 
Galston Maxwood Road. Unreliable 5th
Core/Concrete columns. 10 £30,000 Completed
14 Jul 2025 
New Cumnock Highpark Ave, Area. Unreliable 5th
Core/Concrete columns. 19 £60,000 Started 
04 Aug 2025 
Stewarton Lothian Rd, Area. Unreliable 5th Core 23 £60,000   
£215,000 
Ayrshire Roads Alliance - LED Lighting Programme Update 2025/26 [Works carried over from 2024/25] 
Town Lantern
Amount Status Delivery /
start install
Install
complete by
Kilmarnock - Central 1400 In progress Mar 2024 Mar 2026
East Ayrshire - Decorative 350 75% complete 
tender to be awarded for next stage  Mar 2026 
Ayrshire Roads Alliance - LED Lighting Programme 2025/26 
Programme completed conversions to date 15,267 Replacement programme 97% complete
Overall LED units completed 20,910 LEDs now 98% of total EAC inventory 
84

Page 85

Official
Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2025/26 
Structure
Reference
Structure Name Proposed Works 2025/26
Estimate
Comments
Bridge Strengthening and Replacement    
A71/280 C80 Mathews Burn Culvert
West Donnington St,
Darvel
Slab Replacement £250,000 Internal design ongoing.
U751/10 Crossflats Bridge Replacement £40,000 Awarded to consultant to design replacement.
Temporary bridge will be required during the works.
U760/00 C93 Glenhead Bridge Replacement £60,000 Internal design ongoing, near tender ready.
U740/10 Barbieston Bridge Replacement £60,000 SAC leading design. Award to consultant.
Road Slips  
B713 South of Sorn  £400,000 Works complete. Final measure being agreed.
B741 Coal Glen Embankment Slip Remediation Works £690,000 Discussions ongoing with SPEN. Works to be retendered
ASAP
U13 Aitket Road Slip Remediation Works £500,000 Site clearance complete. With procurement to be
tendered.
A713/60 C61 Polnessan Upper Bridge Culvert Extension £500,000 Detailed design ongoing. Near tender ready.
Upgrade Works Identified from Inspections  
B705/10 C91 Cowan Place Culvert Part Replacement/Scour
Repairs
£60,000 Near tender ready.
A70/130
W31
Thornwood Wall, Lugar Replacement £500,000 Near tender ready. Discussion regarding requirement for
road closure ongoing.
A736/60 C84 Lochridge Culvert Masonry and Drainage
Repairs
£70,000 Works ongoing. 
A71 Riccarton Viaduct Refurbish - expansion joint
removal/replacement
£100,000 Design ongoing to replace 1 failing expansion joint with
asphaltic plug joints. Works to be carried out ASAP.
85

Page 86

Official
A71 River Irvine Bridge Refurbish - expansion joint
removal/replacement 
Design ongoing to replace 1 failing expansion joint with
asphaltic plug joints. Works to be carried out ASAP.
C85/10 Fenwick Bridge Masonry Refurbishment £40,000 Award to consultant to progress with assessment and
detailed design.
U729/00 C64 Hayholm Bridge Masonry and Scour Repairs £60,000 Internal design ongoing.
C95/10 Furnace Road Bridge Arch Strengthening £100,000 Awaiting PI report from consultant. Internal design
ongoing.
Parapet Upgrades  
A70/110 Causeyhead Bridge Parapet Repairs £60,000 Discussions ongoing regarding options to reduce
disruption at Dumfries House.
A736/50 Bloak Road Bridge Parapet Repairs £30,000 NAC/EAC boundary, EAC progressing design.
Other  
Various Investigative Works Topographical Survey, Paint
Inspection etc
£8,000 Annual cost of surveys/inspections. 
Principal Inspection Consultant Fees £100,000 Consultant fees for 24/25 PI’s
Various Low Bridge Signage  Sign Upgrades £40,000 Upgrades to signage at 6 bridges with low head room.
Contract awarded. 
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26
Funding Source Project
ID
Location Project Description Detail Progress Allocation
EAC Capital Road Safety
Budget: £200,000
(£198,000 Road Safety +
£2,000 Safer Neigh.)
22.23 A71 / Campbell Street
Off Slip, Kilmarnock
Junction
signalisation
Installation of new
traffic signals, stopping
up of Willock Street
and new carriageway
layout to improve
capacity
Final junction
designs from
traffic lights
contractor still
pending.  Works
planned to start
January 2026
£105,000
86

Page 87

Official
22.50 B741 Dalmellington to
New Cumnock
Road safety
review
General route review
to identify safety
measures
Driven survey
along rural
section to be
completed.
Ongoing. 
£2,000
22.38 Glaisnock Street,
Cumnock
Traffic calming Speed
reduction/traffic
calming measures
Design works
started - Late
25/26 for
completion
£15,000
22.15 VAS signs, various
location
Upgrades and
new installations
New contract to be
implemented
In progress £10,000
25.20 A713 - Waterside  Road safety
improvements
40mph repeaters, HFS
gateway features and
road markings upgrade
October 25 £25,000
24.05 Various Traffic calming Speed surveys Ongoing £10,000
25.03
/
25.16
Various Road safety
improvements
HFS Schemes Ongoing £33,000 
24.20 B751 - Kilmaurs to Fenwick  Route Review General route review,
VAS improvements,
Road Markings and
Signage, Studs
Ongoing design
works with
Construction
expected Sept 25
£125,000
25.11 A71 – Priestland Safer system
improvements
Vehicle restraint
barriers
Design work
ongoing with
Construction
expected early 26
£75,000
25.13 A719 – Waterside Road Safety
improvements
VAS improvements ,
HFS and carriageway
studs
Design work
ongoing with
Construction
expected early 26
£50,000
25.17 A70 – Dumfries House Road Safety
improvements
VAS improvements ,
HFS, carriageway studs
and resurfacing
Design work
ongoing with
Construction
expected early 26
£50,000
Rural Route Action Plans
Budget: £359,000
£134,000 (EAC) + £225,000
(Dev. Contributions)
22.08 B778 Stewarton to
Fenwick
Road alignment
improvements at
three key
locations
Agreement to proceed
with site 1
improvements
Process started £359,000
87

Page 88

Official
Tier 1
Budget: £758,000 
22.13 Grougar Road,
Crookedholm
Pedestrian
crossing and road
widening
Installation of new
crossing and layby
Works started
with planned
completion late
August 2025 
£90,000
23.07 Strawberrybank Road,
Kilmarnock
Pedestrian
crossing
Appraisal for new
crossing point
Ped counts low
so project
reduced to
consideration of
ped refuge island 
£10,000
23.10 St Germain Street,
Catrine
Pedestrian safety
improvements
Installation of bollards
and TRO 
Works complete
with TRO to be
finalised 
£10,000
N/A Kilmarnock Green
Infinity Loop
Cycling
Infrastructure
Route 1 & 2, Sturrock
St and MSCP
Route 1 & 2
design placed on
hold due to lack
of funding, MSCP
site
redevelopment
application
submitted to
ATIF 2025/26.
Sturrock St
modelling
completed. 
£100,000
24.18 A759 West of
Gatehead
Pedestrian
improvements
Footway designs and
build out
Design work
ongoing with
Construction
expected early 26 
£30,000
25.15 B751 Kilmaurs to
Knockentiber
Pedestrian
improvements
Footway
improvements
Design work
ongoing with
Construction
expected early 26 
£30,000
24.28 Kilmarnock Pedestrian
improvements
Footway designs and
buildouts
Onsite
consultation to
£30,000
88

Page 89

Official 
be completed
prior to design
work with
Construction
expected early 26 
23.12 A713 Bellsbank Rd,
Dalmellington
Traffic calming 1 x speed table Construction
expected June 25 
£10,000
25.12 A71 Priestland Traffic Calming and
pedestrian crossing
Design work
ongoing with
Construction
expected early 26 
£50,000 
Irvine Road Kilmaurs Pedestrian
improvements
Design work
ongoing with
Construction
expected late 25
£35,000 
Various location Various To be Confirmed  £363,000
EAC Bus Infrastructure
Budget: £645,000
22.51 Onthank Terminus,
Kilmarnock
Upgrades to
existing
infrastructure
Improve crossing and
boarding points
Drawings
complete to be
paired with
Stewarton
Terminus 
£20,000
22.52 Stewarton Terminus,
Stewarton
Upgrades to
existing
infrastructure
Improve turning circle
and boarding points
Design stage in
progress
£20,000
EAC Active Travel
Budget £50,000
24.03 School Streets
Programme
Introduction of
trial sites
Three further schools
to be trialled with
further trials to be
developed
Live trials have
commenced at
Bellsbank and
Dalrymple.
Auchinleck in
development.
Further sites to
be determined
following
completion of
trial sites.
£50,000
89

Page 90

Official
Appendix 3 
Ayrshire Roads Alliance - EV Public Chargers 
EAST AYRSHIRE 
CPS ID Type Make Location
51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
50821 22kw eVolt Foregate Noth Car Park, Kilmarnock, KA1 1LU
51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH
52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW
70279 Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP
60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR
52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU
52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE
90

Page 91

Official
52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG
52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS
52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB
52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ
52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB
52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY
53778 Rapid eVolt Main Street Car Park, Muirkirk
53775 22kw eVolt Rose Reilly Sports Centre, Stewarton
53776 7kw eVolt Standalane Car Park, Stewarton
60786 7kW eVolt Academy Street, Hurlford
60792 22kW eVolt Drongan Centre car park, Mill of Shield Road
51210 22kW eVolt Carnshalloch Avenue car park, Patna
60950 22kW eVolt New Cumnock Outdoor Swimming Pool car park
60954 22kW eVolt Gatehead Road car park, Crosshouse
61021 7kW eVolt East Ayrshire Community Hospital, Cumnock
61022 7kW eVolt East Ayrshire Community Hospital, Cumnock
61983 7kW eVolt Morton Place car park, Kilmarnock
61984 7kW eVolt Morton Place car park, Kilmarnock
91

Page 92

Official
61985 7kW eVolt Morton Place car park, Kilmarnock
62184 7kW eVolt Browns Road car park, Newmilns
61886 22kW eVolt Sturrock Street, Kilmarnock
62938 7kW eVolt New London Road car park, Kilmarnock
SOUTH AYRSHIRE
CPS ID Type Make Location
51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW
51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU
70278 Rapid eVolt Burns Statue Square, Ayr, KA7 UT
52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN
52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY
50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ
50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF
52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG
70280 Rapid eVolt Girvan Harbour, Girvan, KA26 9AG
52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR
52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH
52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU
52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL
53774 Rapid eVolt Academy Street, Troon
53773 Rapid eVolt Lodge Road Car Park, Turnberry
53777 22kw eVolt Burnside Road, Monkton
92

Page 93

Official
60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly
60081 22kw eVolt Inches Close car park, Maybole
61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton
61986 22kw eVolt Dundonald Primary School car park, Dundonald
60086 22kw eVolt Mossblown Activity Centre car park, Mossblown
60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald
61979 7kW eVolt Chalmers Arcade car park, Girvan
61980 7kW eVolt Chalmers Arcade car park, Girvan
61981 7kW eVolt Chalmers Arcade car park, Girvan
62000 22kW eVolt Barrhill Community car park, Main Street, Barrhill 
93

Page 94

Official
Appendix 4 South Ayrshire Ward Investment and Promenade Programme for 2025/26 incl. works carried over from 2024/25 
Roads Maintenance Unit
LOCATION Description PO Value  Cost to Date variance +/- Comment
Troon Resurfacing of Troon Esplanade (Ph.3).   
Measuring works on site
Prestwick Repair / renew steps to Boydfield Gardens £85,000.00   Complete – Final measure
Prestwick Install power supply to Boydfield Gardens and Links Road   
Scottish Power quote to
be received.  Followed by
agreed site start date 
Ayr North Provision of Bike Shelter at Lochside Community Centre £15,000.00   Bike shelter currently
being fabricated
Ayr East Glencairn Park – footpath upgrade    Quote issued for approval
Ayr East Car parking provision Peggieshill Road    Quote provided,
consultation required
Ayr West  Promenade raised footway works   
Feasibility study ongoing
with Professional Design
Services 
Kyle Install a History Park at Loans Community Hall and link to
Smugglers trail   
Car park quote issued for
approval.  Garden and
block paving quote being
prepared 
Kyle  Improve accessibility at Mossblown village hall      Quote issued for approval
Kyle Link path from Collins Drive to Collenan Avenue, Loans    Quote provided,
consultation required
Kyle Resurface Bowling Green Car Park, Symington    Quote provided, currently
being assessed
Kyle Construct new footpath at southern edge of Collenan
Reservoir   
On Hold.  Scope of works
changed
Design and Flooding Section
Troon  Shore Defence Structural Stabilisation £10,000.00 £15,432.00 -£5,432.00 Complete 
Citadel Footbridge
Refurbishment
Remove and renew timber deck parapet elements. 
Surface prepare and paint.  Remove or repair lighting £140,000.00 £259,957.00  -£119,957.00  Complete 
94

Page 95

Official 
Appendix 5 Ash dieback East Ayrshire and South Ayrshire 2025/26 
2024 High Risk
Works_EAC Highway
2024 High Risk
Works_SAC Highway 
Girvan Boating Pond
Refurbishment 
Install new stainless steel reinforced concrete base slab to
reduce water leakage. £175,000.00 £170,641.00  £4,359.00  Complete 
Dunure Castle
Footbridge
Replacement 
Replace existing small span concrete footbridge with a
larger footbridge with a view and good aesthetics    £230,000.00  Ongoing.
Lighting Section
Ayr East  Glencairn Park – Install footpath lighting £23,000.00   Design complete.  Tender
issued
Ayr West  Replacement of column lighting on Ayr Promenade £145,000.00  
Column and street
lighting works complete
and operational. 
Additional works to install
public Wi-Fi ongoing
Ayr West New Bridge & Auld Brig.  Design fees for installation of
architectural floodlighting to structures £50,000.00  
Exploring other means to
procure Consultant as
delay with SXL Technical
& Consultancy
Framework 
Ayr West  Wrap round decorative lighting to columns on Ayr
Promenade   
SAC PO to be issued
95

Page 96

96

Page 97

Official
AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
5 September 2025  
Report by the Head of Roads - Ayrshire Roads Alliance     
_________________________________________________________________ 
AYRSHIRE ROADS ALLIANCE
IMPROVEMENT ACTION PLAN
________________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this Report is to advise the Joint Committee on the management
of the Improvement Action Plan by the Ayrshire Roads Alliance. 
RECOMMENDATIONS 
2. It is recommended that the Joint Committee:
i. Notes the Improvement Action Plan presented in this report;
ii. Notes the Improvement Action Plan presented in this report for Fleet
Management East Ayrshire Only. 
iii. Continues to receive updates on progress; and 
iv.  Otherwise, notes the content of the report.
BACKGROUND 
3. The purpose of the report is to provide regular updates on the Improvement
Action Plan.  This ensures that the actions are monitored and scrutinised at a
minimum of a quarterly basis and is contained in Appendices 1-3. 
MAIN REPORT/MAIN ISSUES 
4. This Improvement Action Plan is collated by the Head of Service and used to: 
• monitor the progress in meeting the Ayrshire Roads Alliance’s
objectives;
• help managers to continually review the actions and progress to date;
and 
• identify any risk / problem areas that need addressed regarding the
Improvement Action Plan. 
5.      ARA’s Digital Improvement Programme of work continues with recent
completion of an External Works module to better manage works that ARA
carry out for other Council Services and work is ongoing on Additional Support
Needs (ASN) Transport and Professional Design modules in conjunction with
other Council Services across both South and East Ayrshire. 
Agenda Item 7
97

Page 98

Official
6.      Ayrshire Roads Alliance is assisting with the delivery of the Ayrshire Growth
Deal (AGD) Roads Infrastructure Project and Prestwick Proposition for South
Ayrshire Council (SAC) and meet colleagues from SAC regularly to update
progress. 
7.      In respect of our Public EV Charging, work continues on the tender
documentation for the pan Ayrshire concession contract. The initial stage of
tendering resulted in numerous bids which are currently being evaluated and
Invitation to Tender will be published in September 2025 with contract award
in January 2026. Further updates will be provided to both Cabinets and to
North Ayrshire Council once the procurement process has been finalised. 
8.      An EV charging tariff increase was implemented across all three Ayrshires on
1st July 2025 as approved by both area’s Cabinets. 
9.      Following approval of Ayrshire Roads Alliance Pavement Parking
Enforcement reports by both Cabinets, enforcement commenced with a soft
approach followed by full enforcement in South Ayrshire from 1st May 2025
and in East Ayrshire from 1st June 2025. There has been good compliance
with the new restrictions in both authority areas and officers are currently
reviewing requests for further exemptions in both areas. Once this review is
complete any additional exemption orders considered necessary will be
reported to future Cabinets.   
10. The Active Travel Member Officer Working Group  established in South
Ayrshire continues to meet 6 weekly as do the Community Action Groups.
These meetings are supported by SAC’s Thriving Communities team. In East
Ayrshire an Active Travel Strategy Group led by East Ayrshire Leisure will
meet in September with a view to Community Action Groups being
established thereafter. Work is ongoing in both areas to review and develop
an up to date Active Travel Strategies which will be presented to these
groups. 
11. South Ayrshire Council successfully secured £20m from the Levelling Up
Fund and ARA will deliver £15m worth of improvements to Burns Statue
Square, Ayr. The reminder will be used by ARA along with ATIF funding to
construct a new Active Travel Route linking Dundonald to Barassie and for
improvements to the NCN7 route between Prestwick and Barassie station. 
12. IMPLICATIONS 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning Yes  13&14
2. Governance Yes  15
3. Human Resources  No 16
98

Page 99

Official
4. Equality and Fairer Scotland Duty Yes  17
5. Financial Yes  18
6. Risk Yes  19
7. Community Wealth Building Yes  20
8. Net Zero Yes  21 
POLICY/STRATEGIC PLANNING IMPLICATIONS 
13. A well-maintained road network will contribute to achieving the 2015-2030
Community Plan objectives and associated 2021-2024 Delivery Plans. 
14.    The matters referred to in this report contribute to Priority 1 of the South Ayrshire
Council Plan: Spaces and Places/ Moving around and the environment
(Outcome 1). 
GOVERNANCE IMPLICATIONS 
15. The Improvement Action Plan is a management tool and this will not replace the
existing statutory returns for risk and performance related information. 
HUMAN RESOURCES IMPLICATIONS 
16. The Improvement Action Plan has no direct impact on human resources. 
EQUALITY IMPACT AND FAIRER SCOTLAND DUTY IMPLICATIONS 
17. The Improvement Action Plan complements the Equality Impact Assessment by
ensuring that any issues arising are adequately prioritised, managed and either
eliminated or mitigated. 
FINANCIAL IMPLICATIONS 
18.  The Improvement Action Plan facilitates the existing scrutiny arrangements to
manage, prioritise, and review the budget provided by East Ayrshire Council and
South Ayrshire Council to the Ayrshire Roads Alliance 
RISK IMPLICATIONS 
19.  The Improvement Action Plan assists in the prioritisation of risks that need to be   
mitigated by the Ayrshire Roads Alliance in order to reduce the overall risk to
either Council and to comply with the Community Plan/Council Plan in both
partner bodies. 
99

Page 100

Official
COMMUNITY WEALTH BUILDING IMPLICATIONS 
20. The Improvement Action Plan supports economic levers to develop resilient,
inclusive local economies with more local spend and fair employment, as well as
ensuring that wealth is more locally owned and benefits local people. 
NET ZERO IMPLICATIONS 
21.  The Ayrshire Roads Alliance Improvement Action Plan and Carbon Strategy
supports and links to East Ayrshire Climate Strategy Themes; 
Theme 2: Transport
Theme 4: Natural Environment 
Jane Corrie
Head of Roads – Ayrshire Roads Alliance
21st August 2025 
BACKGROUND PAPERS 
Ayrshire Roads Alliance Service Plan 2025/26 
LIST OF APPENDICES 
1. Ayrshire Roads Alliance Improvement Action Plan
2. East Ayrshire Council Strategic Priorities 2025/26 
3. South Ayrshire Council Strategic Priorities 2025/26 
Person to contact: Jane Corrie, Head of Roads - Ayrshire Roads Alliance
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
Implementation officer: Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
100

Page 101

1 
Official
APPENDIX 1 - AYRSHIRE ROADS ALLIANCE IMPROVEMENT ACTION PLAN 2024/25 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details
1 Continue to use the integrated
Roads Asset Management
Plan across the Ayrshire
Roads Alliance.
There is one Asset Plan for the Service
delivering a risk based approach for full
service delivery
Head of Service Completed Document has been presented to Joint
committee and will be reviewed annually.
2 Continue to prepare details for
developing an integrated Local
Transport Strategy.
A Strategy covering both Council areas,
which will involve consultation with
stakeholders. Information will be
gathered to inform the future Local
Transport Strategy. 
Continue to contribute to the Scottish
National Transport Strategy, Regional
Transport Strategy and Strategic
Transport Projects Review work.
Head of Service  Ongoing The Regional Transport Strategy, through SPT,
on which the Alliance has Board membership,
has now been published. 
The Local Transport Strategy will now be
progressed.
3 Action the Flood Risk
Management Plan
Inform the next national cycle of
potential flood risk management
schemes beyond 2022. 
Complete schemes and undertake
studies.
Head of Service  Complete 
March 2026
Reports submitted to both Cabinets Early 2023 
New Cumnock Flood Defences Complete 
Flood studies for Doon and River Ayr and the
Troon Coastal Flood study are complete. 
Work on the River Irvine and Pow Burn flood
studies is ongoing. 
101

Page 102

2 
Official 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details
4 Improve the condition of the
road network.
Improve annual roads survey results
which are part of the SRMCS work.
Ensure the Alliance undertakes more
proactive maintenance.
Head of Service  Site works will
be undertaken
throughout
2025/26.
Key dependencies are the Road Improvement
Plans approved by the relevant Committees in
East Ayrshire and South Ayrshire in spring
2025. Progress is provided to members, and
relevant Committees.
5 Ensure the road network remains
safe through raising awareness
and improving road safety
through education, engineering
and enforcement.
Reduce road accidents in line with
government targets.
Provide appropriate traffic management
schemes and initiatives.
Strategic Manager  March 2026 Scottish Government and SCOTS guidance is
used. A key dependency is the Road
Improvement Plans which are presented to
Cabinet each year.
6 Improve the condition of the
bridge stock.
Improve bridge condition index. Reduce
the number of weight restricted bridges.
Complete all general, special and
principal bridge inspections.
Strategic Manager  March 2026 Through the Road Asset Management Plan.
Key dependencies are Road Improvement
programmes approved by Committees in East
Ayrshire and South Ayrshire in spring 2025. 
Deliver the capital and revenue programmes.
7 Manage and improve the street
lighting asset and install energy
efficient lighting schemes.
Maintain high standard of fixing dark
street lights. Complete the LED lighting
replacement programme in both East
Ayrshire and South Ayrshire.
Head of Service  March 2026 Through the Road Asset Management Plan,
with additional funding being provided to
commence the LED programme. 
At present performance is 98% of street lights
are now LED in EAC; and 100% in SAC. On
target for completion within timescales.
8 Maximise and deliver externally
funded sources of work
Identify external funding sources and
deliver work on time and on budget.
Improve infrastructure; and contribute to
improving the condition of the
network.
Head of Service  Works will be
undertaken
throughout
2025/26.
External sources, including Timber Transport,
Transport Scotland Active Travel Infrastructure
Tier 1 and Tier 2 Funding, SPT, SUSTRANS
Scottish Government, Ayrshire Growth Deal &
Levelling Up Fund
102

Page 103

3 
Official 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details
9 Implementation of Parking
Strategy
Develop Head of Service Ongoing
through
2025/26
Amendments to TRO’s, lining, signing and 
residential parking permits and implementing 
an improved process using digital technology 
10 Prepare Service Plan Publish Head of Service Annual East Ayrshire Council Community Plan. South
Ayrshire - Local Outcomes Improvement Plan
and Local Place Plans. Regular updates will be
provided to joint committee.
11 Continue to review insurance
costs and insurance issues.
Review current practices to minimise
insurance costs.
Head of Service Complete Ayrshire Roads Alliance Monthly Insurance
Report. 
There is good dialogue with the Risk &
Insurance to ensure our work improves the
number of repudiated claims. The number of
claims has greatly reduced due to the
implementation of the new Code of Practice.
12 Review Depots and
Accommodation
Continue to review in 2024/25 from initial
work was completed in 2017 as a result
of amended working practices.
Head of Service Complete Joint Committee Reports of November 2016. 
Although initial work has been completed we
continue to strive to make depot and
accommodation cost savings. Further work will
continue on this as a result of COVID and the
return to office space during 2022/23. 
13 Review vehicle and plant costs Continue to review in 2021/22 from initial
work that was completed in 2017.
Head of Service  March 2026 The service will continue to review the fleet
requirements through the use of utilization
reports and improvements to the management of
the Vehicle Replacement Plan. 
14 Monitor and exercise Business
Continuity Plans
Improved resilience. Business Support
Manager
Review and
update
following
Existing East Ayrshire and South Ayrshire
Council plans
103

Page 104

4 
Official 
Action  Success Criteria/ Desired Outcome  Responsible  Timescale  Details    
Relevant local
and national
events. 
15 Continue to use the Roads
Costing System to its full
potential.
Improve service performance from both
an on-site and financial perspective.
Business Support
Manager
Ongoing Revised roads costing system was fully
operational from November 2018. 
The system continues to be used to monitor
performance and work is ongoing to implement
digital timesheets linked to the Roads Costing
System.
16 Support and contribute to the
Ayrshire Growth Deal
Project Management of Roads Delivery
Projects.
Head of Service  Ongoing Ayrshire Roads Alliance is assisting with the
planning and delivery of the roads & enabling
infrastructure requirements to allow the Ayrshire
Growth Deal development to progress
17 Regional Transport Strategy Successfully contribute to the
preparation of this work being led by
SPT. The Alliance has Board
representation.
Head of Service Complete SPT documents and existing Regional
Transport Strategy
18 Regional Transport Appraisal Ensure the various projects identified
as part of this work are included in the
Strategic Transport Projects Review.
Head of Service Complete Transport Scotland has published the final
STPR2 with delivery programme to be
published.
19 National Transport Strategy East Ayrshire and South Ayrshire
Councils contribute to this process to
ensure the sustainable transport
hierarchy and sustainable investment
hierarchy are delivered.
Head of Service Complete In recognition of the anticipated increase in
Active Travel work, it is proposed that a
member of staff is dedicated directly to this
work.
20 National Transport Strategy –
review of Governance
East Ayrshire and South Ayrshire
Councils contribute to this process to
ensure that the
outcome/output meets the
Head of Service  Complete National Transport Strategy
104

Page 105

5 
Official
21 Transport (Scotland) Bill –
Pavement Parking ban
East Ayrshire and South Ayrshire
Councils contribute to this process to
ensure a pragmatic approach is taken in
delivering the pavement parking ban in
both Council areas
Head of Service  March 2026 Pavement Parking enforcement commenced in
South Ayrshire with soft approach from 1st April
2025 and full enforcement from 1st May 2025.
Enforcement to commence in East Ayrshire from
1st June 2025. Exemption Orders for both
authorities to be in place by end March 2026. 
22 Digital Transformation  Develop modules to deliver end to end
digital processes 
Business Support
Manager
Ongoing TTRO applications –Implemented 
TRIPS – Implemented 
Traffic Signal permits – Implemented 
Management of external works for EAC & SAC –
Implemented 
ASN School Transport – in Development 
Professional Design Services – in Development 
105

Page 106

6 
Official
Appendix 2 - East Ayrshire Council Strategic Priorities 2025/26 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details
1 Progress and complete the New
Cumnock Flood Protection
Project 
Complete the flood prevention projects
at the Leggate and beside the Afton
Water.
Phases  1 & 2
Head of Service Complete  East Ayrshire Council and Scottish
Government funding.  The full Scheme was
completed April 2023.  Final defects certificate
issued August 2024
2 Develop Projects approved from
the Flood Risk Management
Plan  
Progress relevant studies and inform
the developing list of schemes for
cycle two of the national protection
schemes to be delivered from 2022. 
Head of Service March 2026  The studies for the River Ayr and the Doon are
now fully complete and options being
appraised.
The Irvine Valley Flood Study is currently
being updated to identify options for a potential
scheme that is more likely to attract funding.
3 Active Travel Strategy Develop active strategy for travel
across South Ayrshire Network and
East Ayrshire Network
Head of Service Ongoing Work is ongoing in both areas to review and
develop up to date Active Travel Strategies.
4 EV Strategy  Develop EV strategy across East
Ayrshire Network
Head of Service January
2026 
Work on PAN Ayrshire Concession Contract
ongoing with anticipated contract award in
January 2026. 
5 Ash Die back Strategy Develop a risk based strategy for the
management of Ash Die Back.
Head of Service Strategy –
Complete
Surveys -
Ongoing
through
2025/26
Risk based strategy complete.  
Surveys & works ongoing. 28-day notices to
owners with objections received referred to
legal services. 
106

Page 107

7 
Official
Appendix 3 - South Ayrshire Council Strategic Priorities 2025/26 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
1 Implementation of car parking
strategy for South Ayrshire. 
Complete this work with improved
parking provision and management. 
Head of Service  Ongoing –
through
2025/26
Ayr parking report is being further developed
and expanded to include a review of 2 hours
free parking and off street parking. Report will
be presented late 2025. The Prestwick paper
is also finalised.
Troon to follow thereafter. 
2 Develop Projects approved from
the Flood Risk Management
Plan  
Progress relevant studies and inform
the developing list of schemes for
cycle two of the national protection
schemes to be delivered from 2022. 
Head of Service Ongoing
through
2025/26
A Surface Water Management Plan has been
developed for Ayr, Prestwick and Dundonald.
Identified actions are being progressed on a
priority basis and as resources become
available. 
Troon Coastal Flood Study is complete up to
the Options Appraisal stage. 
Pow Burn Prestwick Flood Study is ongoing.
3 Support and contribute to the
Ayrshire Growth Deal
Stimulate economic growth and
address inclusive growth concerns. 
Contribute to infrastructure projects
which are being developed through the
Regional Transport Appraisal work
being led by Transport Scotland.
Head of Service Ongoing –
through
2025/26
Ayrshire Roads Alliance are assisting with the
planning and delivery of the roads & enabling
infrastructure requirements to allow the
Ayrshire Growth Deal development to progress
4 20mph speed restrictions in
villages
Progress with the 20mph speed
restrictions in all villages.  Maintain
engagement with the local
communities.
Head of Service Ongoing –
through
2025/26
Phase 1 & 2 complete.
Phase 3 complete
Phase 4 programme being developed for
remaining villages
5 Anticipated Budget Reductions
in 2026/27
Continue to provide a high quality
roads service within decreasing
available budgets.
Head of Service March 2026 Reports to various Committees. 
107

Page 108

8 
Official 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
6 Active Travel Strategy Review South Ayrshire Active Travel
Strategy
Head of Service Ongoing –
through
2025/26
The Active Travel Strategy will be reviewed
and discussed with the Active Travel
Community Action Group, any amendments
will be presented to the Active Travel Member
Officer Working Group
7 EV Charging Strategy  Develop further the  EV strategy for
South Ayrshire Network
Head of Service January
2026 
Work on PAN Ayrshire concession contract
ongoing with contract award due in January
2026.
8 Levelling Up Fund Active Travel bid Head of Service  Ongoing –
through
2025/26/27
LUF bid successful for construction of new
Active Travel Route between Dundonald and
Barrassie – works ongoing with completion
expected by 31st March 2026. A 2nd bid for
improvements to the NCN7 route from
Prestwick to Barassie station also successful
with work due to start late 2025 and complete
31st March 2027.
9 Motorhome Trials Develop Campervan sites along the
coastline.
Head of Service Ongoing Permanent schemes now apply at the
Ballantrae, Girvan, Ayr and Troon sites.
Further facilities have been trialled at The
Battery Ayr. 
10 Strategic Economic Impact
Assessment A75/A77
There is a growing desire to
understand the importance /
effectiveness of the improvements
outlined along the A75 and A77.
Head of Service Ongoing SEIA complete, ARA to progress STAG for the
A77 or a combined A75/A77 STAG on behalf
of SAC and D&G Council. Lobbying Group
formed with D&G.
11 Ash Dieback Develop a risk based strategy for the
management of Ash Die Back jointly
with South Ayrshire Council.
Head of Service Complete Risk based strategy complete.  
Surveys ongoing issuing 28-day notices to
owners with objections received referred to
legal services.
12 152nd Open Championship Delivery of Event Traffic and Transport
Management 
Head of Service Complete Successfully delivered.  Debrief September
2024
13 The International Ayrshow -
Festival Of Flight
Delivery of Event Traffic and Transport
Management
Head of Service Ongoing Successfully delivered.  Debrief November
2024. Planning ongoing for 2025 event. 
108

Page 109

AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
05 September 2025 
Report by the Head of Roads - Ayrshire Roads Alliance   
_____________________________________________________________ 
WINTER SERVICE REVIEW PROGRESS REPORT 
______________________________________________________________ 
Purpose of report 
1. The purpose of this Report is to advise the Joint Committee regarding the
Review of the Winter Service 
Recommendations 
2. It is recommended that the Joint Committee: 
(i) Consider improvements introduced for 2025/26 Winter Season 
(ii) Acknowledge ongoing improvements 
(iii) Consider winter and other emergencies funding levels in relation to
current levels of service. 
Background 
3. The Winter season began with the first treatment for below-zero temperatures,
hoar frost and ice on 11 Nov ’24, marking the start of winter operations, The
coldest temperature in November was recorded on 29th, dropping to -7.5. 
December ’24 was generally mild, though it saw a minimum road surface
temperature (RST) of -5.8.  The first snow flurries were forecast on 18 December,
but overall conditions remained manageable.  Rain was more prevalent than
snow and by Christmas day, RSTs had risen to +8.0, reflecting unseasonably
mild conditions. 
Through January to March ’25, snow was forecast on occasion, but no prolonged
or extreme weather events occurred.  The lowest RST for winter was recorded
during this period, dropping to -9.0, prompting precautionary treatments. 
In summary, Winter 24/25 was relatively mild and manageable.  Despite some
sharp overnight frosts and brief snow forecasts, there were no significant extreme
events and conditions allowed for consistent and effective winter maintenance
responses
Agenda Item 8
109

Page 110

The combined figures for winter 2024/25 across both East Ayrshire and South
Ayrshire are noted below: 
Year     Salt Used (t)   Treatment Runs
2024/25   13,972    2,755
2023/24   12,514    2,449  
2022/23   12,356    2,295
2021/22   11,689    2,299
2020/21   17,647    3,016 
Main report/main issues 
4. Gritting 
Gritting routes were originally established in 1996 and have only been fully
reviewed once in South Ayrshire since that time.   
SAC existing Priority 1 (P1) gritting routes treat 507.63km (43.12%) of the
overall public road network of 1177.30km.  However, 442.11km (37.55%) of the
public road network is travelled as part of a priority 1 gritting operation. 
EAC existing Priority 1 (P1) gritting routes treat 563.88 km (46.29%) of the
overall public road network of 1,218.11km.  However, 347.40km (28.52%) of
the public road network is travelled as part of a priority 1 gritting operation.   
5. Route Optimisation 
Following the 2024 Route Optimisation exercise undertaken in collaboration
with consultants, Safecote, across South and East Ayrshire Councils, it has
been concluded that no further efficiencies can be achieved within SAC. 
Current route design and coverage already meet the required standards and no
additional reductions are feasible. 
In EAC, analysis of data identified potential efficiencies by reducing the number
of P1 gritting routes from 10 to 8.  While this reduction retains existing network
treatment coverage, it has introduced challenges in completing all routes within
the previously stated 3-hour target.  Dry runs are currently being carried out
with local knowledge amendments applied where required to address these
issues before these route changes can be confirmed. 
A target date of mid-September 2025 has been set for the completion of all
preparatory activities in advance of the winter season commencing on 20th
October 2025.  This includes, 
• Finalisation of optimised route designs 
• Software licensing and system updates
• Staff training and familiarisation sessions
110

Page 111

• Production of operational support packs for frontline teams. 
These preparatory steps are essential to ensure a smooth transition to the new
routing structure and to support effective service delivery throughout the winter
period. 
6. Storm Eowyn 
In January 2025 Ayrshire was hit by Storm Eowyn. Standby teams were on call
throughout the duration of the storm offering assistance to partners such as
Police Scotland, Scottish Fire and Rescue, and council teams such as Housing. 
In addition to the above, the Director of Housing Operations and Development
was delegated by all three Ayrshire to provide direct liaison with the Scottish
Government and Emergency Services from within Police Scotland Incident
Room at Helen St Glasgow.   
During the severe weather event roads were closed, and fallen tree and other
debris was removed to ensure or communities remained as safe as possible: 
Storm Eowyn reported issues 
Issue reported East Ayrshire  South Ayrshire
Unsafe Building/Structure  7 3
Debris 9 4
Flooding 1 3
Tree down 
Blocked/ Closed Road  118 129
Power line  2 2
Traffic light 2 0 
A dedicated Ayrshire Roads Alliance webpage was created and acted as a
central point of live information updating our communities on road closures,
where our teams were working and how to get in touch. 
During this time the Ayrshire Roads Alliance Facebook and X (formerly Twitter)
channels were fully utilised with staff responding to messages and comments
on each channel ensuring the ever-changing needs of our communities were
met in an efficient and timely manner. 
Updates on Storm Eowyn recorded throughout the event, demonstrated that
social media posts reached 231,313 people a 244% increase on other storm
(Ashley, Bert and Daragh) social media posts. 
Ayrshire Roads Alliance social media 
Metric Reach
Storm Eowyn Reach 231,313
Combined Reach (Storm Ashley, Bert,Darragh) 94,875
111

Page 112

Analytic data on the Ayrshire Roads Alliance website also highlights significant
engagement levels with the Ayrshire Roads Alliance dedicated Storm Eowyn
webpage, which accounted for 46% of the total website visits in January 2025. 
Ayrshire Roads Alliance website
Metric Visits
Storm Eowyn webpage views 6262
Total ARA website visits January  13494   
7. Winter Service Plan, Gritter Tracking System & Community Grit Bins 
Based on valuable feedback from stakeholders, the Ayrshire Roads Alliance
website and Winter Service Plan continually undergo significant improvements.
These enhancements include the provision of more detailed winter information
and improvements to Gritter Tracking, highlighting all streets on Priority 1
gritting routes as well as grit bin locations and the ability to request a grit bin or
the filling of a grit bin online. The Ayrshire Roads Alliance continue to monitor
and review stakeholder feedback ensuring that our services meet the needs of
the community we serve. 
8. The Ayrshire Roads Alliance teamed up with TrueView Visuals to advance the
digital capabilities of its Gritter Tracking system. This system monitors the
position of gritters and grit bins in real time during the winter period for East and
South Ayrshire Councils. Gritting information is securely stored for 10 hours
and is readily available to users who can easily access the system on various
devices from the Ayrshire Roads Alliance website and obtain detailed
information on out-of-hours winter service vehicle operations. 
9. Social Media statistics continue to improve: 
2023/2024 2024/2025 
Post Type  Number of posts  Reach  Number of posts  Reach 
Winter gritting  43 470,099 33 754,170
Weather warning  44 121,502 26 161,107
Flood event  19 53,152 6 15,149
Storm Ashley      6 40,204
Storm Bert      8 18,445
Storm Darragh      5 36,266
Storm Eowyn      20 231,313    
644,753   1,256,654
Figures taken from October to May 
112

Page 113

10. The treatment of footway routes across ARA network involves collaboration and
assistance from various stakeholders, such as:   
• ARA Roads Maintenance Unit, 
• EAC Greener Communities
• Private Contractors 
These parties assist with salt spreading and brine treatments, while the routes
undergo annual reviews to ensure optimal functionality. 
11. Grit Bins remain on site throughout the entire year and are monitored
throughout for acts of vandalism or misuse. 
12. Details of grit bin and community grit bin locations are published on Gritter
Tracker, accessible from the Ayrshire Roads Alliance website.  Members of the
public can report a problem, or request their nearest grit bin is refilled by
entering a postcode.  Grit bins can be requested online with mandatory fields
highlighted to ensure consistent information is received, resulting in timely
decision-making and response to the recipient.   
13. Since the 2023/24 winter season, a single Winter Controller has overseen
treatment decisions across the entire Ayrshire Roads Alliance (ARA) network,
covering six domains.  This centralized approach has worked well and
continued to do so during winter 2024/25, improving communications and
coordination across all Winter operational depots. 
Wherever possible, treatments were reduced during the period 2200hrs and
0400hrs.  However, when forecasts indicated a requirement, treatments were
carried out during these hours. 
Treating roads during periods of minimal traffic offers limited benefit and incurs
high costs.  For treatments to be most effective, vehicle movements are needed
to assist with salt dispersal and to help break up any accumulation of snow and
ice. 
14. We continue to monitor and report on the total number of Treatment Plan
Actions (TPAs), with a particular focus on those occurring between 2200hrs
and 0400hrs.  Comparisons for the 2024/25 winter season are as follows: 
This data provides ongoing insight into operational efficiency and helps support
decisions around timings of treatments, ensuring both effectiveness and cost
control. 
EAC TPAs TPAs 2200-
0400hrs
% 2200-0400hrs
P1 Routes 82 (74 in 23/24) 13 (15 in 23/234) 15%
Patrol only 12 (12 in 23/24) 3 (5 23/24) 25% 
113

Page 114

SAC TPAs TPAs 2200-
0500hrs
% 2200-0400hrs
P1 Routes 78 (48 in 23/24) 7 (7 in 23/24) 8%
Patrol only 4 (2 in 23/24 0 (1 in 23/24) -
Domains
Routes
40 (24 in 23/24) 8 (8 in 23/24) 20% 
15. ARA recognises the potential cost savings of reducing treatments between
2200hrs and 0400hrs, where weather conditions permit.  One key factor
influencing cost is the rolling impact of overnight treatments, particularly the
requirement to provide compensatory rest periods in line with the Working Time
Directive. 
SAC
• 2023/24 rest period costs - £14,997
• 2024/25 rest period costs - £18,135
• Increase - £3,138 
SAC treats 8 routes internally, outsourcing only 2 routes to external
Contractors.  This heavier reliance on in-house operatives increases the
requirement for rest periods following overnight treatments. 
The rise in rest period costs is also linked to an increase in TPAs, including
Priority 1, patrol and domain routes, which necessitated more overnight
working. 
EAC
• 2023/24 rest period costs - £13,413
• 2024/25 rest period costs - £9,437
• Reduction - £3,976 
EAC treats 5 routes internally, outsourcing 5 routes to external Contractors,
which reduces reliance on internal operatives during overnight periods and
results in lower rest period costs. 
However, this approach carries a significantly higher external Contractor cost,
with a difference of approximately £291,000 compared to SAC. 
This highlights the trade off between internal delivery models and outsourcing –
balancing labour-related costs against Contractor expenditure remains a key
consideration in future service planning. 
16. Salt Usage and Post Winter Review 
Salt orders were placed in September, November, January and March with a
total of 14,500tonnes procured throughout the 2024/25 winter season to ensure
continuous and responsive treatment coverage. 
114

Page 115

Following the end of season, review meetings were held with Winter Controllers 
and Winter Supervisors to reflect on operational performance, identify
challenges and discuss potential improvements.  These discussions will inform
planning and preparation for Winter 2025/26, ensuring the service continues to
evolve and adapt based on lessons learned. 
17. The Winter Service Plan is issued and made available to an agreed distribution
list (2.3.1 in the Plan).  This document will be reviewed and updated annually
prior to winter commencing in October to include revisions/changes to the
service delivery. 
Implications 
19. 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning        X     20, 21 & 22
2. Governance        X       23 & 24
3. Human Resources        X 
4. Equality and Fairer Scotland Duty        X 
5. Financial       X           27
6. Risk       X           28
7. Community Wealth Building       X           29
8. Net Zero       X           30 
Policy/Strategic planning implications 
20. Winter Controller (WC) and Winter Supervisor (WS) current Roles and
Responsibilities are detailed within the Winter Service Plan. This is being
reviewed for the coming winter 2024/25 with roles being established and clearly
defined for responsible officers. 
21. Summer Controller (SC) was introduced in 2018/19 and continued throughout
this Summer to improve communication across the Service.  Duties include: 
•  Risk to communities, SC will contact Senior Management immediately, from
this the SC will then escalate to Chief Executive, Elected Members and
Community Councils
•  SC assesses the Met Office forecast on a daily basis and will email Senior
Management when preparations are required for a forecasted event i.e. high
winds, severe cold weather, hot weather, heavy rain etc.
•  SC have familiarised themselves with organised events across Ayrshire
•  SC have familiarised themselves with the protocol for esplanades (SAC) i.e.
in heavy rain/wind events, car parks are closed off to ensure safety of road
users. 
115

Page 116

22. Winter Resilience – Community Self-Help Gritting Groups 
Since 2018/19, the number of winter resilience groups across the ARA area
has grown significantly – from 44 groups to 129.  These volunteer groups play a
vital role in supporting self-help footway gritting, enhancing community
resilience during winter weather. 
ARA continues to support these groups by providing training, materials,
equipment and PPE.  Engagement with additional communities is ongoing and
we aim to further expand our participation for Winter 2025/26, strengthening
local capacity and ensuring greater coverage across our network. 
Governance Implications
23. The work of the Ayrshire Roads Alliance is undertaken in accordance with
relevant legislation. 
24. By virtue of the relevant statutory provisions, principally detailed within the 
Roads (Scotland) Act 1984, the Council as local roads authority is required to
manage and maintain all publicly adopted roads within its area other than those
which are maintained and managed by the Scottish Ministers. 
Human resources implications 
25. The Winter Service Review has no direct impact on human resources. 
Equality Impact and Fairer Scotland duty implications 
26. The Winter Service Review has no direct impact on Equality. 
Financial Implications 
Winter Service Outturn Summary 2024/25 vs 2023/24 
2023/24 
Labour Materials Hired
Plant
Fleet/
Plant
Contractors TOTAL
OUTTURN
SAC £118,279 £270,654 £150,156 £3,238 £42,424 £584,751
EAC £127,240 £376,751 £113,451 £3,554 £127,270 £748,266 
116

Page 117

2024/25 
Labour Materials Hired
Plant
Fleet/
Plant
Contractors TOTAL
OUTTURN
SAC £222,080 £289,856 £176,742 £4,706 £31,390 £724,773
EAC £182,774 £436,043 £125,858 £4,166 £322,399 £1,067,984
(incl.
income
£3,255) 
SAC
• 2024/25 Total Outturn: £724,773
• 2023/24 Total Outturn: £584,751
• Increase: £140,022 
The main contributor to the increase is labour costs, which rose by £103,801, due
to factors such as increased staff hours and overtime requirements during prolonged
treatment periods, evident in the increased TPAs above. 
There was a decrease in spend on external contractors by £11,934 reflecting a
greater use of internal resources and reduced need for support services. 
EAC
• 2024/25 Total Outturn: £1,067,984
• 2023/24 Total Outturn: £748,266
• Increase: £319,718 
The most significant rise was in external contractors costs, up by £195,129, due
to increased outsourcing to support treatment delivery during peak events.  Material
costs also increased by £59,292 which is attributed to higher salt usage due to
weather conditions and increased TPAs. 
Risk Implications 
27. Funding for winter service delivery remains an area of concern.  The allocated
budgets for 2024/25 were £600,000 (SAC) and £633,190 (EAC). 
Although Winter 24/25 was relatively mild and manageable, with some
overnight frosts but no significant extreme weather events, both areas
experienced outturns well above their allocated budgets.  This highlights the
financial pressures of delivering the service even under moderate conditions. 
Given this context, any future winter requiring above-average treatment
frequencies or response to severe weather would present a significant financial
challenge.  This underscores the importance of ongoing efficiency measures
and robust contingency planning. 
117

Page 118

Community Wealth Building implications 
28. The winter service contributes to the principles of Community Wealth Building 
by supporting resilient and inclusive local economies.  It encourages local
spending, promotes fair employment practices, and helps ensure that economic
benefits are retained within the community, contributing to greater ownership
and improved outcomes for local people. 
Net zero implications 
29. The Ayrshire Roads Alliance Service Plan supports and links to East Ayrshire 
Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment 
Appendices (if applicable)
None 
Background papers
None 
Person to contact 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
Implementation Officer(s) 
Craig Knape – Strategic Manager – Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: craig.knape@ayrshireroadsalliance.org 
Janice Kelly, Team Leader & Winter Lead - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: janice.kelly5@ayrshireroadsalliance.org 
118

Page 119

Official 
AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
05 September 2025 
Report by the Head of Roads – Ayrshire Roads Alliance 
AYRSHIRE ROADS ALLIANCE
ASSET MANAGEMENT PLAN UPDATE 
Purpose of report 
1. The purpose of this Report is to seek approval from the Joint Committee on the
updated Asset Management Plan for the road networks of East and South
Ayrshire. 
Recommendations 
2 It is recommended that the Joint Committee:
i. Approves the updated Asset Management Plan contained within
Appendix 1
ii. Requests that amendments and updates are provided to future
meetings of the Joint Committee.
iii. Otherwise notes the contents of this Report 
Background
3 Road infrastructure is the most valuable community’s assets. In any economic
situation, expenditure in efficient and responsible ways is of great importance.
It is widely recognised that the application of modern, innovative, asset
management practices can enable improved value for money.  In these
challenging times is it essential that Ayrshire Roads Alliance embraces these
methods and strives to ensure that every penny spent is invested as wisely as
possible. 
4 Asset Management provides Ayrshire Roads Alliance with the necessary
tools for efficient and sustainable management of our roads with a short and
long term approach. The Roads Asset Management Plan forms an important part
of the Ayrshire Roads Alliances’ commitment to apply good asset management to
roads. 
5 Our roads ensure mobility in the local communities of East Ayrshire and South
Ayrshire enhancing accessibility, improved health benefits through active travel,
creates employment opportunities & supports economic productivity.
Agenda Item 9
119

Page 120

Official
Main report/main issues 
6 This Roads Asset Management Plan sets out the Ayrshire Roads Alliance’s plans
for the maintenance of road assets for the period 2025 to 2030 on behalf of
East Ayrshire Council, and South Ayrshire Council. 
7 The Roads Asset Management Plan was last submitted to Joint Committee on 24
September 2024. 
Amendments from last year’s RAMP include: -
• Data tables updated throughout.
• Section 02.2 – Asset Inventory Updates to Table 1
• Section 05.1 - Asset Growth tables updated
• Section 05.2 - Traffic Growth figures updated
• Section 05.4 – Utility Company Works – Update on data, including
warranty duration.
• Section 05.5 - Legislative updates
• Section 06.1 – Road Condition Indicators updated
• Section 07.1 – Asset Valuation updated
• Section 07.2 – Historical Expenditure updated
• Section 07.3 – Planned Funding updated
• Section 08.1 - RCI Backlog – Data amended.
• Section 11 – References. Addition of last two documents (“Highways –
Maintaining a Vital Asset. What Should Councillors Know About Asset
Management?” and “Managing a valuable asset: improving local road
condition. All Party Parliamentary Group on Highway Maintenance.”
120

Page 121

Official
Implications 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning Yes  8 / 9
2. Governance Yes  10
3. Human Resources Yes  11
4. Equality and Fairer Scotland Duty Yes  12
5. Financial Yes  13
6. Risk Yes  14
7. Community Wealth Building Yes  15
8. Net Zero Yes  16 
Policy/strategic planning implications 
8. A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain good
access to our communities within East Ayrshire.
9. The matters referred to in this report contribute to Priority 1 of the Council Plan:
Spaces and Places / Moving around and the environment (Outcome 1). 
Governance Implications 
10. The work of the Ayrshire Roads Alliance is undertaken in accordance with relevant
legislation. 
Human resource Implications 
11. There are no implications. 
Equality impact and Fairer Scotland duty implications 
12. The Roads Asset Management Plan complements the Equality Impact Assessment
by ensuring that any issues arising are adequately prioritised, managed and either
eliminated or mitigated. 
Financial implications 
13. The budget for Asset Improvement is set by East Ayrshire Council and South
Ayrshire Council. Appropriate scrutiny arrangements are in place to manage
these budgets.
121

Page 122

Official
Risk implications 
14. The Asset Management Plan assists in the prioritisation of risks that need
to be mitigated by the Ayrshire Roads Alliance in order to reduce the
overall risk to eitherCouncil and to comply with the Community
Plan/Council Plan in both partner bodies. 
Community Wealth Building implications 
15. The works programme provides economic levers to develop resilient,
inclusive local economies with more local spend and fair employment, as
well as ensuring that wealth is more locally owned and benefits local people 
Net zero implications 
16.  The Ayrshire Roads Alliance Service Plan supports and links to East
Ayrshire Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment 
Appendices (if applicable) 
1. Roads Asset Management Plan 
Background papers 
None 
Person to contact 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance
Tel No. 01563 503164
E-mail: jane.corrie@ayrshireroadsalliance.org
Implementation Officer
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164
E-mail: jane.corrie@ayrshireroadsalliance.org 
122

Page 123

Ayrshire Roads Alliance
Roads Asset Management Plan 2025
123

Page 124

i 
Control Page
Document Information
Title Ayrshire Roads Alliance Roads Asset Management Plan
Author David Allen (Road Asset Officer)
Description Roads Asset Management Plan setting out the plans for the management
of the East Ayrshire Council and the South Ayrshire Council road assets.
This document has been produced in accordance with national guidance
& recommended good practices. 
Document Owner Jane Corrie (Head of Roads) 
124

Page 125

ii
Document Changes
Revision SCOTS
Template
Version
Date Author Changes from Previous Version
1 3.0 03/05/2023 David Allen 
ARA Roads
Asset Officer
Not Applicable
2 3.0 21/05/2024 David Allen 
ARA Roads
Asset Officer
Data tables updated; legislative updates;
addition of inventory data improvements
and asset management systems (02.4 &
02.5).
Traffic Growth figures updated
Addition of “Public Space CCTV” in 02.3.
Addition of final paragraph Page 48, 08.1
RCI Backlog.
3 3.0 14/08/2025 David Allen 
ARA Roads
Asset Officer
• Change to Organisation Chart
• Data tables & graphs updated
• Traffic Count data updated
• Updates to data management
systems
• Updates to EV charger numbers 
125

Page 126

iii
Contents
CONTROL PAGE ................................................................................................................. I
Document Information ................................................................................................................................. i
Document Changes ................................................................................................................................... ii
CONTENTS ........................................................................................................................ III
LIST OF TABLES .............................................................................................................. VI
LIST OF FIGURES .......................................................................................................... VIII
FOREWORD ....................................................................................................................... 1
01. INTRODUCTION ........................................................................................................... 1
01.1 Strategic Context .............................................................................................................................. 1
01.2. Overview .......................................................................................................................................... 3
01.3. Purpose of Road Asset Management Plan...................................................................................... 3
02. OUR ROAD ASSETS .................................................................................................... 4
02.1. Road Network .................................................................................................................................. 4
02.2. Assets Inventory .............................................................................................................................. 5
02.3. Assets Not Covered ......................................................................................................................... 8
02.4. Inventory Data Improvement ........................................................................................................... 9
02.4.1. KaarbonTech Gully Smart ................................................................................................................. 9
02.4.2. Vaisala RoadAI .................................................................................................................................. 9
02.4.3. WDM Highways Asset Management System ................................................................................... 9
02.5. Asset Management Systems ........................................................................................................... 9
02.5.1. Ayrshire Roads Alliance HIAMS ........................................................................................................ 9
02.5.2 Vaisala RoadAI ................................................................................................................................. 10
02.5.3 KaarbonTech Gully Smart ................................................................................................................ 10
02.5.4 Asset Management Systems Conclusion ........................................................................................ 11
126

Page 127

iv
03. STAKEHOLDERS ....................................................................................................... 12
03.1. Road Service Key Stakeholders .................................................................................................... 12
Table 3. Stakeholder Groups .................................................................................................................. 12
Stakeholder Group .................................................................................................................................. 12
Examples ................................................................................................................................................ 12
03.2. Stakeholder Communication & Engagement ................................................................................. 13
03.3. Customer Surveys ......................................................................................................................... 13
03.4. Customer Contacts ........................................................................................................................ 14
04. OUR ROAD ASSET MANAGEMENT OBJECTIVES .................................................. 15
05. DEMANDS ................................................................................................................... 17
05.1. Asset Growth ................................................................................................................................. 17
05.2. Traffic Growth & Composition ........................................................................................................ 18
05.2.1. Scotland (2015–2024) ..................................................................................................................... 20
05.2.2. East Ayrshire (2015–2024) ............................................................................................................. 21
05.2.3. South Ayrshire (2015–2024) ........................................................................................................... 22
05.2.4. Key Insights ..................................................................................................................................... 22
05.3. Environmental Conditions .............................................................................................................. 24
05.3.1 Winters ............................................................................................................................................. 25
05.3.2 Flooding ............................................................................................................................................ 26
05.3.3 Ayrshire Shoreline Management Plan.............................................................................................. 28
05.3.4 Climate Change ................................................................................................................................ 29
05.3.5 Twenty Minute Neighbourhood ........................................................................................................ 31
05.3.6. Sustainable Materials in Maintenance of Highways Infrastructure ................................................. 32
05.4. Utility Company Works………………………………………………………………………………………33
05.5. Legislative Changes .......................................................................................................................... 34
06. SERVICE STANDARDS .............................................................................................. 35
06.1 Road Condition Indicators............................................................................................................... 39
127

Page 128

v
07. FINANCIAL SUMMARY .............................................................................................. 41
07.1. How is the Roads Service Funded? .............................................................................................. 41
07.2 Differences between Expenditure and Capital Expenditure ........................................................... 41
07.3. Asset Valuation .............................................................................................................................. 42
07.4. Historical Expenditure .................................................................................................................... 44
07.5. Planned Funding ............................................................................................................................ 46
08. ASSET INVESTMENT STRATEGIES ......................................................................... 49
08.1. Road Condition Indicator Backlog ................................................................................................. 49
09. RISK MANAGEMENT ................................................................................................. 52
09.1. Risk Management Introduction ...................................................................................................... 52
09.2. Safety Inspection Strategy ............................................................................................................. 54
09.3. Risk Strategy .................................................................................................................................. 57
09.3.1. Defect Risk Assessment ................................................................................................................. 57
09.3.2. Priority Response Times ................................................................................................................. 60
10. GLOSSARY ................................................................................................................. 62
10.1. Abbreviations ................................................................................................................................. 62
10.2. Main Definitions ............................................................................................................................. 67
11. REFERENCES ............................................................................................................ 70 
128

Page 129

vi
List of Tables
Table 1. Inventory Data as of 31st March 2025 ................................................................................ 6
Table 2. Snapshot of the percentage of road network surveyed with Vaisala RoadAI (June 2025).
........................................................................................................................................................ 10
Table 3. Stakeholder Groups .......................................................................................................... 12
Table 4. Sum lengths of Carriageway & Footway that have been adopted or disposed of for East
Ayrshire Council .............................................................................................................................. 17
Table 5. Sum lengths of Carriageway & Footway that have been adopted or disposed of for South
Ayrshire Council .............................................................................................................................. 17
Table 5. Service Standards for Carriageways 2024/25 (APSE Data - Carriageways) .................... 35
Table 6. Service Standards for Footways 2024/25 (APSE Data - Footways) ................................. 36
Table 7. Service Standards for Street Lighting 2024/25 (APSE Data) ............................................ 37
Table 8. Service Standards for Structures 2024/25 (APSE Data) .................................................. 38
Table 9. Service Standards for Traffic Signals 2024/25 (APSE Data) ............................................ 38
Table 10. East Ayrshire Council Road Condition Indicators (RCI) .................................................. 40
Table 11. South Ayrshire Council Road Condition Indicators (RCI) ............................................... 40
Table 12. East Ayrshire Council Asset Valuation as of 31st March 2025 ....................................... 42
Table 13 South Ayrshire Council Asset Valuation as of 31st March 2025 ...................................... 43
Table 14. East Ayrshire Council Historical Expenditure .................................................................. 44
Table 15. South Ayrshire Council Historical expenditure ................................................................ 45
Table 16. East Ayrshire Council Planned Capital Funding – 2025/26 to 2030/31 .......................... 46
Table 17. South Ayrshire Council Capital Investment Budgets 2024/25 to 2033/34 ...................... 47
Table 20. Network RCI Data for East Ayrshire Council & for South Ayrshire Council .................... 50
Table 21. Risk Likelihood ................................................................................................................ 57
Table 22. Impact/ Severity Score .................................................................................................... 58
Table 23. Risk Matrix ...................................................................................................................... 59
Table 24. Risk Management Matrix ................................................................................................ 59
129

Page 130

vii
Table 25. Defect Priority and Response Times .............................................................................. 60
Table 26. Abbreviations .................................................................................................................. 62
Table 27.  Definitions ...................................................................................................................... 67 
130

Page 131

viii
List of Figures
Figure 1. Ayrshire Roads Alliance Organisation Chart ..................................................................... 2
Figure 2:  Map Showing EAC and SAC Areas .................................................................................. 4
Figure 3 - Objectives ....................................................................................................................... 16
Figure 4: Annual Traffic by Vehicle Type in East Ayrshire. 1993 To 2024 Inclusive. ...................... 19
Figure 5: Annual Traffic by Vehicle Type in South Ayrshire. 1993 To 2024 Inclusive. ................... 19
Figure 6: Graph Showing Number Utility Company Works for Financial Years 2017/18 to 2024/25 in
East Ayrshire. .................................................................................................................................. 33
Figure 7: Graph Showing Number of Utility Company Works for Financial Years 2017/18 to 2024/25
in South Ayrshire. ............................................................................................................................ 34
Figure 8: Strategy Key Steps .......................................................................................................... 55 
131

Page 132

Foreword
This Roads Asset Management Plan sets out Ayrshire Roads Alliances’ proposals for the
management of East Ayrshire Council and South Ayrshire Council road assets for the next three
years and beyond.  It has been produced in accordance with national guidance and recommended
good practices.
Road infrastructure is the most valuable of a community’s public assets. In any economic situation,
expenditure in efficient and responsible ways is of great importance.  It is widely recognised that the
application of modern, innovative, asset management practices can enable improved value for
money.  In these challenging times is it essential that Ayrshire Roads Alliance embraces these
methods and strives to ensure that every penny spent is invested as wisely as possible. 
Asset Management provides decision makers with the necessary tools for efficient and sustainable
management of roads with a short term and a long term view point. This Roads Asset Management
Plan forms an important part of the Ayrshire Roads Alliances’ commitment to apply good asset
management to roads.
Roads ensure mobility in your local community, and also in the wider Ayrshire area & beyond. Roads
enhance accessibility, health, mobility, facilitate trade & tourism, generates employment
opportunities & boosts economic productivity.
Consideration is given to the levels of investment in the road network to maintain and ultimately
improve on the East Ayrshire Council & South Ayrshire Councils strategic objectives that include: -
 Reducing inequalities
 Delivering inclusive economic growth
 Taking climate action
 Improving health & wellbeing of the community and visitors 
Signature 
Councillor Douglas Reid
Leader
East Ayrshire Council 
Signature 
Councillor Brian Connolly
Leader
South Ayrshire Council
132

Page 133

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 1 of 73 Date 14 AUG 2025 
01. Introduction
01.1 Strategic Context 
The Ayrshire Roads Alliance (ARA) came in to being on the 1st of April, 2014, to deliver shared
Council roads and transportation services to communities across East Ayrshire and South Ayrshire. 
The Alliance is governed by a joint committee of elected members from the two Councils, with East
Ayrshire Council as the lead authority. It delivers roads services including roads maintenance, street
lighting, winter maintenance, design, traffic, transportation and road safety. The Ayrshire Roads
Alliance organisation chart is shown in Figure 1, below.
The shared service ensures a consistent standard of service delivery while improving service
efficiency and resilience, against a backdrop of reducing public sector budgets.
Ayrshire Roads Alliance Road Asset Management Policy confirms our commitment to asset
management and aligns our approach with the SCOTS Road Asset Management (RAM) Framework
of Recommended Practices, including the “Well Managed Highways” Code of Practice.
Ayrshire Roads Alliance Road Asset Management Plan (RAMP), takes the Corporate Outcomes,
Objectives & Visions, for both East Ayrshire Council and South Ayrshire Council, translating them in
to a clear & concise Roads Asset Management objectives. The level of service that the Council is
aiming to achieve provides a means of identifying and prioritising the overall funding required for
road assets.
This RAMP summarises the status of our road assets in terms of size, value and condition and
presents a number of investment options for our major road assets. The scenarios presented and
issues raised are designed to assist with the budget setting process.
Asset groups are Carriageways, Footways, Structures, Street Lighting, and Traffic Signals. 
Condition assessments are carried out for carriageways and for structures.  The information
collected provides an accurate picture of the extent of the area’s roads infrastructure. An accurate
record of condition allows us to anticipate overall funding needs and predict the impact investment
scenarios will have on condition. 
Road infrastructure deterioration is generally slow and often unseen, meaning that the impact of
investment cannot be assessed in the short term.  Over time, the rate of deterioration accelerates
with insufficient maintenance. The investment scenarios presented consider the projected impact
over a 5 year period. This allows decisions to be taken with an understanding of medium and long
term implications. 
133

Page 134

Roads Asset Management Plan 2025  
Document Roads Asset Management Plan REV 3
RAMP Page 2 of 73 Date 14 AUG 2025 
FIGURE 1. Ayrshire Roads Alliance Organisation Chart   
134

Page 135

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 3 of 73 Date 14 AUG 2025 
01.2. Overview
This Roads Asset Management Plan sets out the Ayrshire Roads Alliance’s plans for the
maintenance of road assets for the period 2025 to 2030, on behalf of East Ayrshire Council, and
South Ayrshire Council. 
Roads comprising carriageways, footways, structures, street lighting and traffic management
systems are the largest value assets in our local communities. A communities road network has
impacts that are not only the replacement costs, but also on business, employment, tourism, health,
education, and helping to ensure that East Ayrshire and South Ayrshire are more attractive places
to live.
East Ayrshire Council, and South Ayrshire Council, objectives align with Scottish Government
purposes & values that include: -
 Create a more successful country;
 Give opportunities to all people living in Scotland;
 Increase the wellbeing of people living in Scotland;
 Create sustainable and inclusive growth;
 Reduce inequalities and give equal importance to economic, environmental and social
progress. 
01.3. Purpose of Road Asset Management Plan
The purpose of the Road Asset Management Plan (RAMP) is to:
 Formalise strategies for investment in road asset groups;
 Define service standards;
 Improve how the road asset is managed;
 Support optimised service delivery across both Council areas.
135

Page 136

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 4 of 73 Date 14 AUG 2025 
02. Our Road Assets
02.1. Road Network
FIGURE 2:  Map Showing EAC and SAC Areas
136

Page 137

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 5 of 73 Date 14 AUG 2025 
02.2. Assets Inventory 
The roads networks are the single biggest assets that East Ayrshire Council and South Ayrshire
Council own. The Gross Replacement Cost (GRC), for East Ayrshire Council is £1.84 billion, and
£1.56 billion for South Ayrshire Council as of 31st of March 2024. The roads asset is made up of five
major asset groups:-
 Carriageway;
 Footways and Footpaths;
 Structures;
 Street Lighting;
 Traffic Management Systems.
Data, shown in table 1 below, is based on historical records and new data that is reviewed and
updated at the end of each financial year. Inventory data for non-roads assets is also included. 
137

Page 138

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 6 of 73 Date 14 AUG 2025 
Table 1. Inventory Data as of 31st March 2025
Asset Type Units East Ayrshire
Council
South Ayrshire
Council
Totals
Carriageway km 1,233 1,183 2,416
Footways & Footpaths km 1,050 945 1,995
Street Lighting Columns  No. 21,675 20,590 42,265
Illuminated Signs &
Bollards
No. 1,384 1,053 2,437
Structures  No. 618 371 989
Retaining Walls km 7 3 10
Cattle Grids No. 11 34 45
Traffic Signals No. of Sets 99 94 193
Zebra Crossings No. 27 0 27
Variable Message Signs No. 123 45 168
Vehicle Activated Signs No. 156 60 216
Real Time Passenger
Information
No. 67 50 117
Gullies No. 27,125 25,402 52,527
Grit Bins No. 760 284 1044
Weather Stations No. 3 1 4
Harbours No. 0 1 1
Protected Shoreline km 0 24 24
Public Car Parks No. 47 38 85
EV Dual Charging Points
(Public)
No. 63 36 93
138

Page 139

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 7 of 73 Date 14 AUG 2025 
Table 1. Inventory Data as of 31st March 2025
Asset Type Units East Ayrshire
Council
South Ayrshire
Council
Totals
EV Dual Charging Points
(Fleet)
No. 44 3 47
Depots No. 1 2 3  
139

Page 140

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 8 of 73 Date 14 AUG 2025 
02.3. Assets Not Covered 
The RAMP covers assets maintained by Ayrshire Roads Alliance on behalf of East Ayrshire Council
and South Ayrshire Council, as local roads authorities.
Other Assets have been specifically excluded from this plan, i.e. being privately owned, or not being
directly linked to the public road network.  
These include:
 Private Roads and Footways – those roads that are maintained by persons or bodies
other than the Councils as the local roads authority;
 Trunk Roads – managed and maintained by Transport Scotland, on behalf of the Scottish
Ministers;
 Proposed Public Roads – those roads which will become public roads sometime in the
future;
 Private Bridges (i.e. Network rail structures);
 Council owned bridges, not on or crossing the public road network;
 Decorative, seasonal lighting;
 Public Space CCTV;
 Assets relating to the other five key areas of Council asset ownership (e.g.  Buildings
and Property, Council Housing, Open Space, Vehicle Fleet and Information and
Communications Technology);
 Public Rights of Way – landscape and countryside.  
140

Page 141

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 9 of 73 Date 14 AUG 2025 
02.4. Inventory Data Improvement
02.4.1. KaarbonTech Gully Smart
A gully asset data collection programme commenced on the 4th of March 2024 for East Ayrshire
Council and for South Ayrshire Council. The data collection was completed August 2024. This allows
for improved management of gully cleansing programmes and improved data as to the state of
gullies over time. 
02.4.2. Vaisala RoadAI 
Data, for road traffic signs is to be extracted from Vaisala Roads AI, and imported to the ARA
Highways Infrastructure Asset Management System (HIAMS). A manual review will be required to
remove temporary traffic signs and to remove any duplicate road signs. 
02.4.3. WDM Highways Asset Management System
A module has been developed, within HIAMS, to allow for Vehicle Restraint Systems (VRS) asset
data to be entered. VRS data is being collected in East Ayrshire and South Ayrshire. 
02.5. Asset Management Systems
02.5.1. Ayrshire Roads Alliance HIAMS
The Ayrshire Roads Alliance has, for many years, utilised digital solutions, including WDMs’ Roads
Management System (RMS), WDMs’ Lighting Management System (LMS) and WDMs’ Structures
Management System (SMS). 
Since the WDM Highways Infrastructure Asset Management System (HIAMS) went live, additional
fixed reports have been developed, and are being developed, reducing time to extract information
for analysis and reporting. These reports also allow anyone, who has the necessary permissions, to
run these reports when required.
The ARA Pavement Management System (PMS) was migrated to the new cloud based model, on
HIAMS by the first quarter of 2025, and was utilised to create the carriageway resurfacing works
programme for 2025/26 financial year. 
141

Page 142

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 10 of 73 Date 14 AUG 2025 
02.5.2 Vaisala RoadAI
Vaisala RoadAI utilises a mobile phone camera to record information about visual road condition
data, traffic signs and road markings. The use of Vaisala RoadAI enhances safety, compliance, and
overall asset management data. An exercise to extract road condition data from the Vaisala RoadAI
system was carried out in 2025, and this data is now integrated into the Scheme Builder System
which is part of the WDM HIAMS Pavement Management System (PMS) module.
The Scheme Builder System, which is used to score Carriageway Schemes for the annual
programme of works, was approved by the Ayrshire Shared Services Joint Committee at their
meeting on the 10th November 2017.
Traffic sign data will also be collected from Vaisala RoadAI, and exported to the ARA HIAMS Roads
Management System module. This will provide accurate inventory data within ARA HIAMS.
For the year 2024/25, Vaisala RoadAI data collection has improved over previous years. 
Table 2. Snapshot of the percentage of road network surveyed with Vaisala RoadAI
(June 2025). 
Council Area Filtered Data (KM) & % Unfiltered Data (KM) & %
East Ayrshire Council 805.38 (65.6%) 873.49 (71.1%)
South Ayrshire Council 871.22 (73.6%) 911.94 (77.1%)   
Filtered data is where the road is videoed and where the RoadAI is able to analyse the data. 
Unfiltered data is where the road is videoed and includes lengths where the RoadAI has not been
able to analyse the data – perhaps due to wet weather, snow on the roads, poor lighting, sun in the
camera, or due to the polarising filter not having been set up correctly.
In November 2024, a Vaisala representative provided live demonstrations of the capabilities of
Vaisala RoadAI to the Roads Maintenance Unit, and to other departments within East Ayrshire
Council. 
02.5.3 KaarbonTech Gully Smart
East Ayrshire Council and South Ayrshire Council gully cleaning data has been historically
maintained in Microsoft Excel spreadsheets. The information collected is minimal and does is not
conducive to best practice maintenance, nor data analysis. 
142

Page 143

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 11 of 73 Date 14 AUG 2025 
There is an intention, for future development of a link between the ARA HIAMS and the Gully Smart
systems, to allow gully asset and condition information to be automatically transferred between both
software systems. 
02.5.4 Asset Management Systems Conclusion
The above systems contribute to efficient operations and cost savings. Inspections, and
maintenance activities, generate records that serve as evidence of compliance, maintenance, and
safety. These records are essential for audits, insurance claims, and legal purposes.  
143

Page 144

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 12 of 73 Date 14 AUG 2025 
03. Stakeholders
03.1. Road Service Key Stakeholders
Ayrshire Roads Alliance has a wide variety of stakeholders, which include: 
Table 3. Stakeholder Groups
Stakeholder Group Examples
Customers Pedestrians, cyclists, motorists, commuters, logistics,
tourists, businesses
Transport providers Bus companies, Network Rail, ScotRail, Ferry
Companies, SPT, Prestwick Airport
Statutory Undertakers Water, gas, oil, electricity, telecommunications
Politicians Local Councillors, MSPs, MPs, Scottish Ministers, UK
Government Ministers
Senior Council Executive/Management Finance, Legal, ICT, Department Heads, Procurement
Council Road Infrastructure Officers Section Heads and Team Leaders within the Ayrshire
Roads Alliance
Emergency Services  Police Scotland, Scottish Ambulance Service, Scottish
Fire and Rescue Service, Coastguard
Industry bodies SCOTS, RAC, AA, Cycling Scotland, Sustrans, Scottish
Chambers of Commerce, Regional Timber Transport
group, UKRLG
Other Council Services & Organisations Refuse Collections, Social Services, Regeneration,
Education, Community Councils 
Delivery partners & Supply chain Consultants, Contractors, Suppliers
Neighbouring Roads Authorities North Ayrshire Council, Dumfries & Galloway Council,
South Lanarkshire Council, East Renfrewshire Council,
and Transport Scotland
Environmental SEPA, Scottish Government
144

Page 145

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 13 of 73 Date 14 AUG 2025 
03.2. Stakeholder Communication & Engagement
Involving stakeholders, including communities and their representatives, is core to allowing Ayrshire
Roads Alliance deliver their commitments to the community. Consultation facilitates the creation of
shared values and objectives, allowing for developing and delivering of meaningful services and
setting stakeholder expectations.
East Ayrshire Council strategic framework 2022 to 2027 is available, online, where it is also possible
to provide comments.
South Ayrshire Council, via the “Have Your Say” section of the website have the ability to comment
on current consultations as well as to review historic consultations
Ayrshire Roads Alliance, on behalf of South Ayrshire Council, and East Ayrshire Council carry out
public consultations that may be accessed on line at the East Ayrshire Council and South Ayrshire
Council websites.
Through improvement plans, which are created from the outcomes of consultation, both East
Ayrshire Council, and South Ayrshire Council, show understanding of local needs and aspirations. 
These plans are reviewed and supplemented as necessary. 
Ayrshire Roads Alliance has a procedure in place for the management of complaints, from logging
a complaint (by email, telephone, or online), to a complaint being closed out. 
03.3. Customer Surveys
From 2022/23 financial year Ayrshire Roads Alliance have been using the online APSE Scotland
Road Survey questionnaire for the East Ayrshire Council area and for the South Ayrshire Council
area. The online surveys are available to the public from the Council websites, the Ayrshire Roads
Alliance website and on social media.
Link to the East Ayrshire Council survey is: - https://uk.surveymonkey.com/r/east-ayrshire-2
Link to the South Ayrshire Council Survey is: - https://uk.surveymonkey.com/r/south-ayrshire-
council-2
Due to too few people completing the surveys in 2023 and 2024, a review of how the surveys are
publicised will take place. 
145

Page 146

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 14 of 73 Date 14 AUG 2025 
03.4. Customer Contacts
Roads and street lighting faults reported by customers are recorded on the WDM HIAMS which
incorporates the previous WDM Routine Management System and the WDM Lighting
Management System, respectively.
Faults may be logged online, by email, by letter or by telephone.  The URL, for reporting a roads
or street lighting fault, is online at: - https://www.ayrshireroadsalliance.org/Report/Report-a-
Fault.aspx 
146

Page 147

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 15 of 73 Date 14 AUG 2025 
Official
04. Our Road Asset Management Objectives
The Ayrshire Roads Alliance Asset Management Objectives support the alignment with the East
Ayrshire Council and the South Ayrshire Council corporate management strategies and provide
direction for the implementation of Asset Management Practices across the Roads Service.  
Within East Ayrshire, a well maintained road network will contribute to achieving the Community Plan
objectives  in  relation  to  Economy  &  Skills  and  Safer  Communities  to  maintain good access to
our communities.
The South  Ayrshire  Council has the strategic  objective  of  ‘Enhanced  Environment  through 
Social,  Cultural  and Economic  Activities’  and,  within  that, the outcome  ‘Work  with  partners  to
improve roads  and  other  infrastructure,  to  encourage  house  building  and business investment
that sustains local communities’.
With reference to winter, East Ayrshire and South Ayrshire Council have a statutory obligation under
Section 34 of the Roads (Scotland) Act 1984 to prevent snow and ice endangering the safe passage
of pedestrian and vehicles over public roads in terms of the above legislation a ‘road’ includes
carriageways, footways, and footpaths areas.
Both South Ayrshire Council and East Ayrshire Council aim to provide an effective and efficient
Winter Service in accordance with “Well Maintained Highways”, and within the resources available
to: - 
 Allow the safe passage of vehicles and pedestrians;
 Minimise delays due to winter weather;
 Ensure operations are undertaken safely. 
The Asset Management Objectives support Ayrshire Roads Alliance to:
 Take a strategic approach to asset management;
 Focus on customer needs;
 Measure Performance;
 Communicate decision risks and opportunities;
 Provide a consistent approach to managing the asset.
147

Page 148

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 16 of 73 Date 14 AUG 2025 
Official 
Environmental
Long-term option and planning analysis to minimise the environmental of impacts of
maintenance.   
Safety
Provide a safe network for all road users through the continuous refinement of the
authority’s intelligence-led approach.   
Healthier
Promote the healthier travel options through the provision of maintenance that
priorities pedestrians and cyclists.   
Customer Engagement
Engage with customers to understand their needs, priorities, and expectations to
support the development of service standards and improve customer satisfaction.
FIGURE 3 - Objectives
148

Page 149

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 17 of 73 Date 14 AUG 2025 
05. Demands
05.1. Asset Growth 
The asset grows each year due to the adoption of new Roads and construction of new Road links.
New assets create the need for maintenance, management, and associated funding in future years
as these additional assets age.  Generally, increases in assets are due to new developments.  Over
the last 5 years the following assets lengths have been adopted, or disposed of, by the Councils: 
Table 4. Sum lengths of Carriageway & Footway that have been adopted or disposed
of for East Ayrshire Council 
(Data from Asset Valuation Annual Reports – Carriageway input, Additions and Disposals) 
2020/21 2021/22 2022/23 2023/24 2024/25
Carriageway + 5.4 km + 4.4 km +0.6 km +4.9 km +5.0km
Footways and
Footpaths
+ 5.1 km + 7.8 km +0.6 km +4.3 km +7.7km 
Table 5. Sum lengths of Carriageway & Footway that have been adopted or disposed
of for South Ayrshire Council 
(Data from Asset Valuation Annual Reports – Carriageway input, Additions and Disposals) 
2020/21 2021/22 2022/23 2023/24 2024/25
Carriageway +1.6 km -2.7 km 5.0 km 0.0 km 0.0 km
Footways and
Footpaths
+ 0.6 km 0.0 km 3.2 km 0.0 km 0.0 km
149

Page 150

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 18 of 73 Date 14 AUG 2025 
05.2. Traffic Growth & Composition
Cars, and taxis, remain the dominant mode of transport in Scotland. In 2021, 43 billion vehicle
kilometres of traffic were travelled across the 59.2 thousand kilometres of roads in Scotland. Long
term trends for traffic growth have shown year on year increases. The exception to this have been
the years of 2020 and 2021, where there was a marked drop in traffic levels due to COVID-19. The
increase in traffic places increasing pressure on the Ayrshire Roads Alliance network due to the
significant increase in the general volume of traffic and in particular, large commercial vehicles. 
Increased car ownership and individual mobility since the Second World War was instrumental in
the closure of some of Ayrshire's railways in 1960s’, and created the demand for a road building and
road improvement programme of the principle routes that connect Ayrshire internally (including ferry
ports and Prestwick Airport), and with major conurbations out with of Ayrshire. The main demands,
for development, include for houses, agricultural buildings, tourist accommodation and the
expansion of urban areas.
In 2017 65% of all journeys were made either as drivers or passengers in a car or a van, up 4%
since 2012. Of these journeys the proportion of single occupancy car trips also showed an underlying
increasing trend, up 4% since 2012.
The number of people permitted to drive on our roads is ever increasing and if current trends
continue car trips nationwide are predicted to increase over the next 20 years by 20%.
During the first six months of the COVID-19 pandemic (March 2020 to September 2020) car traffic
throughout Scotland, dropped to 25% of 2019 levels. Total road traffic in Scotland increased by 2%
in 2023 - 2024, reaching 99% of pre-pandemic levels.  Car traffic saw a 3% increase, though it
remained 4% below pre-pandemic levels in 2024.
The tables below, are provided by the Department for Transport. The data show annual traffic by
vehicle type for East Ayrshire and for South Ayrshire from 1993 to 2024. 
150

Page 151

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 19 of 73 Date 14 AUG 2025 
Figure 4: Annual Traffic by Vehicle Type in East Ayrshire. 1993 To 2024 Inclusive. 
Figure 5: Annual Traffic by Vehicle Type in South Ayrshire. 1993 To 2024 Inclusive. 
151

Page 152

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 20 of 73 Date 14 AUG 2025 
05.2.1. Scotland (2015–2024)
The following data, in Sections 05.2.1 to 05.2.3, inclusive, shows how traffic volumes in Scotland,
East Ayrshire and South Ayrshire have recovered (post SARS-CoV-2), and evolved, since 2015.
Metrics used in this section are:
 Monitored network length (km);
 Annual cars & taxis vehicle-km (million);
 Annual all-motor-vehicles vehicle-km (million);
 Car share (% of all traffic);
 Traffic density (vehicle-km per km of road).
Scottish Transport Statistics 2024 reports long‐run growth from 2010 to 2019, a sharp SARS-CoV-2
dip in 2020–21, then rapid rebound by 2023-24. 
Table 5.  Road Traffic Statistics for Scotland (Data from DfT).
Year Network
(km) Cars & taxis (m km) All vehicles (m km) Car share Density (all km⁻¹)
2015 57,327 33,600 45,600 73.7 % 796,000
2016 57,327 34,200 46,200 74.0 % 806,000
2017 57,327 35,000 47,000 74.5 % 820,000
2018 57,327 35,500 47,800 74.3 % 834,000
2019 57,327 36,678 48,400 75.8 % 844,000
2020 57,327 28,800 36,500 78.9 % 637,000
2021 57,327 27,400 35,000 78.3 % 611,000
2022 57,327 32,800 42,000 78.1 % 733,000
2023 57,327 34,375 44,300 77.6 % 773,000
2024 57,327 35,372 48,384 73.1 % 844,000
152

Page 153

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 21 of 73 Date 14 AUG 2025 
Key points:
 2015 to 2019: traffic rose approximately 10 % over four years;
 2020 to 2021: 25 % SARS-CoV-2 drop;
 2022 onwards: strong rebound, reaching 99 % of 2019 total in 2023/24;
 In 2024, 30.4 billion vehicle miles of traffic were travelled across the 37.1 thousand miles of
roads in Scotland, including Trunk Roads. 
05.2.2. East Ayrshire (2015–2024)
Table 6.  Road Traffic Statistics for East Ayrshire (Data from DfT).
Year Network (km) Cars & Taxis (m km) All Vehicles (m km) Car Share Density (all km⁻¹)
2015 1,330.6 503.4 673.0 74.8 % 506,000
2016 1,332.9 500.6 680.9 73.5 % 511,000
2017 1,334.5 514.9 704.2 73.1 % 528,000
2018 1,334.0 521.9 711.0 73.4 % 533,000
2019 1,332.5 522.6 708.9 73.7 % 532,000
2020 1,331.8 390.3 553.7 70.5 % 416,000
2021 1,332.5 453.0 645.6 70.2 % 485,000
2022 1,336.8 499.0 698.4 71.5 % 522,000
2023 1,338.6 515.0 713.1 72.2 % 532,000
2024 1,342.4 524.0 725.4 72.2 % 541,000
East Ayrshire’s recovery:
 SARS-CoV-2 trough in 2020 at -30 % vs 2019;
 Full rebound by 2023/24: cars +0.3 % vs 2019, all vehicles +2.3 %.
153

Page 154

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 22 of 73 Date 14 AUG 2025 
05.2.3. South Ayrshire (2015–2024)
Table 7. Road Traffic Statistics for South Ayrshire (Data from DFT).
Year Network (km) Cars & Taxis (m km) All Vehicles (m km) Car Share Density (all km⁻¹)
2015 1 327.1 473.7 614.6 77.1 % 463 000
2016 1 325.0 486.3 635.0 76.6 % 479 000
2017 1 325.5 489.2 648.2 75.5 % 489 000
2018 1 321.6 492.5 649.4 75.8 % 492 000
2019 1 322.9 493.2 649.7 75.9 % 491 000
2020 1 315.8 362.5 499.0 72.6 % 379 000
2021 1 315.9 422.3 585.1 72.2 % 445 000
2022 1 324.0 471.8 646.0 73.0 % 488 000
2023 1 326.0 481.0 654.6 73.5 % 494 000
2024 1 329.5 485.9 661.5 73.4 % 498 000
South Ayrshire’s recovery:
 2020 bottomed at -22 % vs 2019.
 By 2024 traffic is 2 % above 2019 for total motor vehicles and cars. 
05.2.4. Key Insights
 Scotland, as a whole, as well as East Ayrshire and South Ayrshire saw a 30 %+ drop in 2020,
then a steady rebound by 2023/24;
 Scotland’s car share (approximately 73 %) closely matches South Ayrshire (approximately
73.5 %) and East Ayrshire (approximately 72.2 %);
 South Ayrshire has a marginally higher car share and traffic density than East Ayrshire,
reflecting stronger through-traffic on major routes;
 Post-SARS-CoV-2 recovery was essentially complete in East Ayrshire and South Ayrshire
by 2023.
154

Page 155

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 23 of 73 Date 14 AUG 2025 
The National Transport Strategy outlines the Government’s vision for a Scottish transport system
which creates great places through the provision of a sustainable, inclusive and accessible transport
system which promotes prosperity, health and fairness for all our citizens. It aims to promote equality
by providing fair access to services which are easy to use and affordable for all.  
Many of the roads in East Ayrshire Council and South Ayrshire Council were not designed to
accommodate this level of traffic which creates a growing need for investment in maintenance. The
lack of maintenance can cause delays through disruption, and increase in carbon emissions. Not
intervening on time, can increase treatment costs, and also cause an increase in journey times as
the treatments will be more frequent and will require more time. 
155

Page 156

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 24 of 73 Date 14 AUG 2025 
05.3. Environmental Conditions
The Ayrshire Roads Alliance is responsible for maintenance works across the East Ayrshire Council
and South Ayrshire Council network of roads, bridges, structures and other assets. The protection
and enhancement of the natural environment is an important aspect of transport network
maintenance. 
The Scottish Government is committed to a
net-zero greenhouse emissions by 2045. This
requires fundamental transformations in how
the transport network is utilised, maintained
and developed. The Just Transition
Commission was established in 2018, with a
remit of providing Scottish Government
Ministers with practical advice. The advice is
developed from the gathering of knowledge,
expertise and lived experience from a wide
range of people and groups across Scotland.
As set out in the Scottish Government
Climate Change update, by 2030 Scottish
Governments intends to reduce car miles
travelled by 20%.
The transport system currently prioritises
cars. This will need to change in the future,
with the focus being on other modes of transport. Electric vehicles will play a necessary role in
reducing transport related CO2 emissions. Continued dependence upon private vehicle usage does
not constitute behaviour change towards more active and inclusive forms of travel, and will continue
to be a significant source of harmful particulate matter. Electrification will bring immediate benefits
to some roadside emissions. This does not negate the requirements for a transport system that is
accessible to all and which maximises the physical and mental health benefits of active and
decarbonised transport which will require a range of policy changes.
East Ayrshire Councils’ Climate Change Strategy, “Clean Green east Ayrshire” proposes cutting
emissions both within the Council and in the wider area which will help build a stronger post-carbon,
post-COVID economy, with community wealth building, equality of opportunity and improved quality
of life for all at its heart. The East Ayrshire Council strategy is available online at: - https://www.east-
ayrshire.gov.uk/Clean-Green-East-Ayrshire/Climate-change-strategy/Climate-change-
strategy.aspx 
156

Page 157

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 25 of 73 Date 14 AUG 2025 
As per the survey, South Ayrshire Council’s Climate Change Strategy aims to ensure a just transition
for people and nature, supporting ecological recovery and wellbeing, reducing inequalities and
creating sustainable, liveable places where people are connected to nature, climate literate and
understand the natural systems we rely on, are supported to develop green skills and can work in a
fast-evolving local green jobs market, travel less overall and make active and sustainable travel
choices first.
South Ayrshire Councils current “Sustainable Development and Climate Change Strategy” document
may be found online at: - Sustainable development and climate change strategy 2019-2024 (south-
ayrshire.gov.uk).
Pressures on the transport network assets come from a number of environmental sources that
include: -
 Winters (e.g. 2018, Beast from the East);
 Flooding;
 Climate change;
 Changes in pollution levels. Pollution levels dropping in some instances – more
knowledge required around plastics pollution. 
05.3.1 Winters
The Ayrshire region has a temperate maritime climate where summers tend not to be hot, and
winters not too cold. Generally the hottest month is July, and the coldest January. The weather is
fairly unpredictable, as with the rest of Scotland. 
The climate of the Ayrshire region has a maritime influence, as the prevailing winds blow from the
sea. The warm Gulf Stream also has a strong influence on Western Scotland with winds mainly
blowing from the sea. The annual mean temperatures are in the range 9.5 to 9.9 °C in coastal areas.
The sea reaches its lowest temperature in February or early March so that on average February is
the coldest month in some coastal parts of Ayrshire with minimum daily temperatures being about
2C.  For snow to lie for any length of time then the temperature normally has to be lower than this.
Over most of the area, snowfall is normally confined to the months from November to April. On
average, the number of days with snow falling is about 20 near the Ayrshire coastline. The number
of days where snow lies is less than 5 days.
Occasionally transport disruption can occur. One example being during the winter of 2018/19. There
were 10 days starting on Thursday the 22nd February 2019 where traffic was majorly impacted. A
stratospheric warming (warm air traveling across the Atlantic from Mexico to the UK) disturbed the
jet stream. This allowed for cold winds from Russia to reach the UK. Temperatures dropped, with a
frost each night. Then, the Met Office issued a rare red snow warning across central Scotland. By
157

Page 158

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 26 of 73 Date 14 AUG 2025 
the time the air reached Scotland, it was just below 0C. In addition the air mass had collected water
from the North Sea which resulted in heavy snowfall upon reaching Scotland. Glasgow Airport was
closed and there was widespread travel disruption. Power cuts hits thousands of homes and military
assistance was deployed. This storm was known as The Beast from the East. In Scotland, the
demand for gas required to heat homes rose by 50%. 
05.3.2 Flooding
The Scottish Environmental Protection Agency (SEPA) is Scotland’s national flood forecasting, flood
warning authority and strategic flood risk management organisation.  SEPA liaise closely with other
organisations that are responsible for managing flood risk, to ensure that a nationally consistent
approach to flood risk management is adopted. Councils are responsible for producing Local Flood
Risk Management Plans (LFRMP) and for engaging with SEPA, Scottish Water and other
responsible authorities to develop these.
A LFRMP is a document, or series of documents, that describe how organisations will collaborate
and coordinate in order to mitigate adverse impacts of flooding on communities. Flooding is
something that has the ability to effect people, the environment, property, infrastructure and
economic activity. Due to flooding impacting cross boundaries, it is common for Councils to create
a collaborative Flood Risk Management Plan. For flood risk management purposes, Scotland has
been divided into 14 Local Plan Districts. The two districts that are pertinent to East Ayrshire Council
and South Ayrshire Council are Ayrshire and Solway. 
The first Ayrshire LFRMP, was created in 2009 and is reviewed, and revised, as necessary. The
Ayrshire Flood Risk Management Plan is published by North Ayrshire Council on behalf of North
Ayrshire Council, East Ayrshire Council and South Ayrshire Council, Scottish Water, SEPA and
NatureScot (previously known as Scottish Natural Heritage). North Ayrshire is the lead local authority
for the Ayrshire Local Plan District. 
The Flood Risk Management Strategy is a tool utilised for implementing the Flood Risk Strategy,
and addresses the risk of flooding from rivers, the coast and surface water. The risk of flooding from
rivers is usually due to rainfall causing a river to rise above bank level spreading out and inundating
adjacent areas. Coastal flooding is where the risk is from the sea. Sea levels can change in response
to tidal cycles or atmospheric conditions. Over the longer term sea levels and coastal flood risk may
change due to climate change. Surface water flooding happens when rainwater does not drain away
through the normal drainage systems or soak into the ground, but lies on or flows over the ground
instead.
In summary, there are 18 areas and one candidate area that have been identified as being potentially
vulnerable to flood risk across the Ayrshire Local Plan district. These include 7,800 residential and
2,700 non-residential properties. The estimated annual average damage from the identified flood
risks is £16.4 million. The Flood Risk Management plan presents actions to avoid and reduce the
risk of flooding, and prepare and protect ourselves and communities within these potentially
158

Page 159

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 27 of 73 Date 14 AUG 2025 
vulnerable areas and across the local plan district. These actions include 3 prioritised flood protection
schemes or works; 15 flood protection studies; flood warning schemes, surface water management
plans, and natural flood management studies and works. The delivery of many of these actions may
be dependent on the availability of funding.
For full details the following documents, that are available on the Ayrshire Roads Alliance website,
should be referenced: - 
 Ayrshire Local Flood Risk Management Plan, Cycle 2 – LPD 12;  
 Solway Local Flood Risk Management Plan, Cycle 2 - LPD14.   
The Ayrshire Local Flood Risk Management Plan, Cycle 2 – LPD 12 may be found on the Ayrshire
Roads Alliance website at: - 
https://www.ayrshireroadsalliance.org/Resources/pdf/Flooding/2022/ayrshire-local-flood-risk-
management-plan.pdf
The Solway Local Flood Risk Management Plan, Cycle 2 - LPD14 may be found at: - 
https://www.ayrshireroadsalliance.org/Resources/pdf/Flooding/2022/solway-local-flood-risk-
management-plan.pdf  
159

Page 160

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 28 of 73 Date 14 AUG 2025 
05.3.3 Ayrshire Shoreline Management Plan
A shoreline management plan (SMP) includes a large-scale assessment of the risks associated with
coastal processes, including flooding and erosion over short (0 to 20 years), medium (20 to 50 years)
and long term (50 to 100 years) timescales.  A Shoreline Management Plan informs as to the
management of risks, to an identified stretch of coastline, to people and the developed, historic and
natural environment. One of the main aims of an SMP is to promote sustainable policies into the
next century and provide a timescale for managing risks along the coastline in the future.
The Ayrshire Shoreline Management Plan extends from Skelmorlie to the Galloway Burn, at the
Dumfries and Galloway Council boundary. The islands of Arran and Great Cumbrae are also
included in the plan. Implications of relevant suggested management measures have been
considered for the adjacent council areas of Inverclyde and Dumfries & Galloway, however policy
for these areas is not set by the Ayrshire Shoreline Management Plan. 
The Ayrshire SMP should be reviewed at regular intervals in order to assess if the policies and
actions proposed are still appropriate, particularly as the understanding of the rate of sea level rise
resulting from global climate change becomes better understood. Rising sea levels, increased
coastal erosion and erosion-enhanced flooding will progressively impact soft coastlines.
The Shoreline Management Plan, along with associated documents, is published on the Ayrshire
Roads Alliance website and the South Ayrshire Council website. 
The link to the Shoreline Management Plan, on the Ayrshire Roads Alliance website is at: -
https://www.ayrshireroadsalliance.org/Information-On/Ayrshire-Shoreline-Management-Plan-
Information.aspx 
160

Page 161

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 29 of 73 Date 14 AUG 2025 
05.3.4 Climate Change
The landscape of the Ayrshire region predominantly comprises of a landscape that is at low level.
The localised highest points are Kirrieoch Hill, South of Straiton, at 786 metres ASL and Blackcraig
Hill, near New Cumnock, at 700 metres ASL.
The environment, health of people and the economy within Ayrshire are intrinsically linked. In
Scotland we are already seeing changes in climate that are impacting society. Climate change, the
long term shift in climate patterns, is mainly driven by greenhouse gasses (that include carbon
dioxide, nitrous oxide, methane, water vapour and ozone), aerosol emissions and land use change.
These can impact climate systems in many ways, including: -
➢ Changes to the hydrological cycle (the movement of water on, above and below the surface
of the Earth. E.g. Ground water, rivers, clouds, rain, transpiration from plants, evaporation);
➢ Warming Oceans, land and air;
➢ Melting ice (poles and glaciers);
➢ Rising sea levels;
➢ Ocean acidification;
➢ Changes in ocean currents (i.e. The North Atlantic Drift);
➢ More extreme weather. 
The impacts to Scotland include: -
➢ Damage to infrastructure, including roads, structures and drainage systems;
➢ Flooding of coastal regions;
➢ Localised flooding due to increased amounts of rainfall in shorter periods of time;
➢ Risks to water supplies;
➢ Food instability;
➢ Death of forests;
➢ Change in seasons;
➢ Damage to marine eco systems;
161

Page 162

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 30 of 73 Date 14 AUG 2025 
➢ Conflict and climate migrants.
For the benefit of our communities, our children, the environment and prosperity, Scotland is
transitioning to a net zero emissions society. By 2045 there shall be no greenhouse gas emissions.
To help meet Scotland’s targets, a transformation of all sectors of life is required.
Net Zero Scotland informs us that transport accounts for about 36% of Scotland's greenhouse gas
emissions. 40% of Scotland’s transport emissions comes from cars. Over half of all journeys made
in Scotland are under 5km. Some steps have been taken to reduce this, including the Active Travel
initiative, but the overwhelming majority of vehicles on the road are still greenhouse gas-emitting
petrol or diesel engines.
The Scottish government has said it wants to have "phased out" the need for new petrol and diesel
cars by 2030 - and hopes to reduce the use of cars generally, with the number of kilometres driven
to be reduced by 20%.
The number of new electric and hybrid cars registered in the UK is soaring and the availability of
publicly available charge points in Scotland, as of November 2024, is 6,000 and increasing.
Both East Ayrshire Council, and South Ayrshire Council have completed a review of publicly
accessible Electric Vehicle charging points. East Ayrshire Council and South Ayrshire Council,
through the Ayrshire Roads Alliance, are working in conjunction with North Ayrshire Council to further
develop ways to improve access to charging points for electric vehicles. East Ayrshire currently have
63 publicly accessible Electric Vehicle charging points and South Ayrshire Council have 36. 
A business case was created in 2022 between North, East and South Ayrshire Councils which set
out how all three local authorities could work together to expand the EV charging infrastructure
network to meet projected EV demand over the next three to four years. A list of desired outcomes
for the EV network were produced in consultation with key stakeholders, which stated that the public
EV network should give people access to a technologically advanced, well maintained, reliable
network; that it should be available in rural, remote and more deprived areas; that it must be
commercially viable and attract private sector investment, and that it should promote the use of
public transport and active travel as people’s first choice in line with the National Transport Strategy.
Based on this business case, the Ayrshire Authorities are working in partnership on the Pan Ayrshire
EV infrastructure project, which aims to improve the EV charging Infrastructure across Ayrshire and
increase the EV charging infrastructure by installing additional 307 chargers to the existing 151 public
chargers. The project is currently progressing in tendering phase. The first phase concluded in June
2025, resulting in a shortlist of potential bidders. The second part of the tendering process is set to
go out shortly for the short-listed bidders, with a final contract award anticipated in January 2026.
Potential locations for the proposed EV network were investigated and it was agreed that the aim
would be for 99% of Ayrshire properties without off-street parking to be within a 10-minute drive of a
charge point. The chargers are planned to be installed in three phases within the first 3 years after
162

Page 163

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 31 of 73 Date 14 AUG 2025 
contract award, and a public consultation was conducted recently to gather feedback on the
proposed locations for the new 307 chargers. The locations will include a mix of destination and
residential chargers, covering both urban and rural areas across the three Ayrshire Councils. 
05.3.5 Twenty Minute Neighbourhood
In 2016 transport became the largest greenhouse gas emitting sector. This follows a decrease in
emissions from coal power, as the UK transitioned towards gas for energy. Emissions, from
transport, in Scotland have decreased but transport is still the largest contributor to emissions.  
Transport accounted for 35.6% of Scotland’s total greenhouse gas emissions in 2018; 40% of these
emissions came from car journeys - the highest emitting mode of transport.  In 2020, transport
accounted for 23.8% of Scotland’s total greenhouse gas emissions; cars being 40% of that total.
Between 2019 and 2020, there was a 19% reduction transport within Scotland. This has given the
largest fall in greenhouse gas emissions on record. This reduction coincides with COVID-19 related
restrictions. It is likely that there will have been reduced emissions for 2021 as well.  
Scottish Government, in conjunction with Councils, has made a commitment to deliver a net zero
society by 2045, which means zero greenhouse gas emissions. Councils, throughout Scotland, have
their part to play in meeting the targets. 
Lockdown in 2020, due to COVID-19, showed that people’s lives could be improved through walking,
cycling, taking exercise, access to local or online services, working from or closer to home, and
access to shared green spaces. Lockdown dramatically limited individual movement. These
restrictions have spurred on adoption of twenty minute neighbourhoods, an urban planning strategy
that has existed for decades. The strategy focuses on the decentralisation of towns & cities by
bringing amenities into neighbourhoods.
20 minute neighbourhoods' are places that are designed so that residents may have access to
services they need, including schools, shops, doctors surgeries, dentists, leisure facilities and places
of work, within a 20 minute walk of their home. This is through access to safe walking and cycling
routes, or by public transport.  The goal is to make active travel the easiest option for everyone.  
Benefits of a twenty minute neighbourhood are not just in reductions of traffic and greenhouse gas
emissions. Adults should aim for around 20 - 30 minutes moderate physical activity, such as brisk
walking, as a daily minimum.  20 minute neighbourhoods help to ensure that much of this activity
can be accommodated within our normal daily patterns of behaviour. When then a place is attractive
and easy to move around, individuals are encouraged to choose walking, wheeling or cycling, with
benefits for physical and mental health. Fewer vehicles on our roads, travelling at lower speeds can
help to increase walking, wheeling and cycling and improve air quality.   
163

Page 164

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 32 of 73 Date 14 AUG 2025 
There is no ‘one-size-fits-all’ approach to developing 20 minute neighbourhoods. Every community
is different, as are the needs of its residents. It is also possible that some of those communities
where the ability to engage is lowest, may be where the opportunities to make significant and
measurable changes are the greatest.
The concept needs resourcing and delivery at a scale and intensity proportionate to the degree of
need. All communities will need some support, but the most in need should have the most support
to close the gap.
The South Ayrshire Council Active Travel Strategy has been published on the website below. 
Link to South Ayrshire Council Active Travel Strategy: -
https://www.ayrshireroadsalliance.org/Information-On/Traffic-and-Road-Safety/Active-Travel-
Strategy.aspx 
05.3.6. Sustainable Materials in Maintenance of Highways Infrastructure
Sustainable maintenance practices, of highways infrastructure, is a multi-discipline concept that
integrates ecological, social and economic aspects along with the close involvement of organisations
from manufacturers, government, highways maintenance organisations and industry bodies. 
Ayrshire Roads Alliance has embraced, and is implementing principles of sustainability through
managing works by limiting their impact, on the environment. The intention is to maximize benefits
throughout the life time of an asset whilst minimizing emissions, and minimising waste, through
recycling of materials used.
As an example, on the Loans to Troon Active Travel Corridor, Ayrshire Roads Alliance explored
various alternative materials to reduce carbon emissions. This focussed on kerbing and paved areas
as two of the identified carbon hotspots. After a trial, a porous rubber crumb surface was taken
forward as a replacement for asphalt. This alternative material had several benefits from reducing
the requirement for concrete edge kerbing to being porous and thus providing a sustainable drainage
solution. Lessons learnt from this scheme have been invaluable for ensuring best practice and
considering future low carbon materials.
Other examples include the use of in situ recycling of asphalt, and the use of hydraulically bound
materials (HBM) utilising recycled materials.
The use of sustainable materials can lead to reductions in carbon emissions, but as important is
ensuring that carbon is considered early in the design process, to make efficiency in design and
minimise the volume of materials required. 
164

Page 165

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 33 of 73 Date 14 AUG 2025 
05.4. Utility Company Works
Utility activity can have a major effect on the maintenance and management of the road assets.
There are currently no recorded figures to quantify the effect that utility openings have on the road
structure but it is widely believed that these lead to an increase in defects and earlier deterioration
of the road surface than would otherwise be expected. All Utility companies are responsible for
carrying out their own reinstatements. For any works where the permanent reinstatement was
completed prior to the 1st October 2023, works have a 2-year, or 3-year, guarantee depending upon
the depth of the apparatus. 
The duration of guarantee periods, for permanent reinstatements, has been reviewed.  For any
permanent reinstatements completed from the 1ST October 2023 the guarantee period increased to
six years.
The graphs, below, show the number of works carried out by Utility Companies since the start of the
financial year 2017/18.  There are two graphs, below, one displaying information for East Ayrshire
Council and one graph for South Ayrshire Council. 
Figure 6: Graph Showing Number Utility Company Works for Financial Years 2017/18 to 2024/25 in East Ayrshire. 
165

Page 166

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 34 of 73 Date 14 AUG 2025 
Figure 7: Graph Showing Number of Utility Company Works for Financial Years 2017/18 to 2024/25 in South Ayrshire. 
05.5. Legislative Changes 
There is secondary legislation (Scottish Statutory Instrument) due to be enacted, in the near future
requiring Roads Authorities to hold asset data, such as street lighting underground cables and roads
drainage and upload it, on a regular basis, to the Scottish Road Works Register VAULT.  
This will require substantial investment in staff time to capture the asset data, along with
development of a suitable graphical based information system to store and to manage the data. 
166

Page 167

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 35 of 73 Date 14 AUG 2025 
06. Service Standards
This plan is based upon delivering the service standards indicated below.  They are the standards
that service users can expect from East Ayrshire Council’s and South Ayrshire Council’s road
assets during the plan period. Details of how the specific measures, shown below, are calculated
are included in the Road maintenance manual. Data below, for carriageways, is taken from the
Ayrshire Roads Alliance annual Scottish Roads Maintenance Condition Survey (SRMCS) survey
results for East Ayrshire Council and for South Ayrshire Council for 2024/25. 
Table 5. Service Standards for Carriageways 2024/25 (APSE Data - Carriageways)
Service Measured By EAC
Achieved
SAC
Achieved
Safety Percentage of Priority 1 defects made safe
within response times.
93% 100%
Percentage of safety inspections completed
on time.
80% 93%
Condition Overall Percentage of carriageway length to
be considered for maintenance treatment
(RCI).
31.7% 34.0%
Percentage of “A” Class roads to be
considered for maintenance treatment.
17.7% 23.4%
Percentage of “B” Class roads to be
considered for maintenance treatment.
25.2% 28.6%
Percentage of “C” Class roads to be
considered for maintenance treatment.
30.8% 37.6%
Percentage of unclassified, non-principal
roads network where maintenance should be
considered.
36.4% 37.0% 
167

Page 168

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 36 of 73 Date 14 AUG 2025 
Table 6. Service Standards for Footways 2024/25 (APSE Data - Footways)
Service Measured By EAC Achieved SAC Achieved
Safety Percentage of Priority 1 defects
made safe within response times (2
hours).
75% 100%
Condition Percentage of footway to be
considered for maintenance
treatment.
17.5%  15.0%
Percentage of footway treated. 0.23% 0.07% 
168

Page 169

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 37 of 73 Date 14 AUG 2025 
Table 7. Service Standards for Street Lighting 2024/25 (APSE Data)
Service Measured By EAC Achieved SAC Achieved
Safety Percentage of repairs within 7 days.  93.54% 90.51%
Average time to repair a fault (days).  3.37 3.48 
Environment Average annual electricity consumption
(kilowatt hours per annum) street
lighting only.
185.55
kWh/Annum
157.19 
kWh/Annum
Total annual energy consumption in
kilowatt hours per annum for the street
lighting asset (non-Central
Management System & Central
Management System) EXCLUDING
traffic signals if applicable
3,752,407kWh 3,039,166kWh  
169

Page 170

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 38 of 73 Date 14 AUG 2025 
Table 8. Service Standards for Structures 2024/25 (APSE Data)
Service Measured By EAC Achieved  SAC Achieved 
Condition Number of principal inspections
carried out on time.
91 31
Number of General inspections carried
out on time.
167 276 
Table 9. Service Standards for Traffic Signals 2024/25 (APSE Data)
Service Measured By EAC Achieved SAC Achieved 
Safety Time to repair a 2 hours Urgent fault and
48 Hours Non Urgent fault.
93.5% 96.2% 
170

Page 171

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 39 of 73 Date 14 AUG 2025 
06.1 Road Condition Indicators
The road network represents the Councils’ single largest asset and therefore regular and adequate
maintenance is vital to ensure it does not deteriorate or become dangerous, and that considerable
past investment is not lost. Ayrshire Roads Alliance monitor the deterioration in our road network
via the Scottish Road Condition Maintenance Survey (SRMCS).
The Scottish Road Maintenance Condition Survey, which is organised by the Society of Chief
Officers of Transportation in Scotland (SCOTS) on behalf of Local Authorities, is carried out by a
specialist contractor, WDM Ltd, using vehicles accredited annually by the TRL. The vehicles are
equipped with lasers and high resolution cameras, to collect data for processing by computer and
currently record:-
 Location;
 The road geometry (gradient and shape);
 Variations in the longitudinal profile (evenness of ride along the road);
 Transverse profile variance (deformation across the road);
 Wheel track rutting / deformation in the wheel path;
 The presence of cracking within the carriageway;
 Texture (roughness of the surface of the road);
 The extent of edge deterioration (due to over-riding or lack of lateral support).
The survey covers 100% of A Class roads in one direction each year, 50% of B Class & C Class
roads in one direction each year, and 10% of U Class roads in one direction each year. In order
to minimise the effect of sampling errors on the result, the Road Condition Indicator (RCI) for
unclassified roads is calculated from four years data.
The tables below summarise the data for East Ayrshire Council, and for South Ayrshire Council
when compared to the thirty two Scottish Councils.  
171

Page 172

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 40 of 73 Date 14 AUG 2025 
Table 10. East Ayrshire Council Road Condition Indicators (RCI) 
2019/21 2020/22 2021/23 2022/24 2023/25
Network RCI 36.8% 33.8% 33.5% 33.0% 31.7%
Scotland
Average RCI 35.5% 34.2% 33.6% 34.1% 34.7%
Above / Below
Scotland
Average
+1.3 -0.4 -0.1 -1.1% -3.0%
Quartile 3 3 3 3 2
Ranking (out of
32 Councils) 22nd  18th = 20th 18th 12th 
Table 11. South Ayrshire Council Road Condition Indicators (RCI) 
2019/21 2020/22 2021/23 2022/24 2023/25
Network RCI 40.9% 39.0% 37.4% 35.0% 34.0%
Scotland
Average RCI 35.5% 34.2% 33.6% 34.1% 34.7%
Above / Below
Scotland
Average
+5.4 +4.8 +3.8 -0.9% -0.7%
Quartile 4 4 4 3 3
Ranking (out of
32 Councils) 27th  27th  26th 24th 20th
172

Page 173

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 41 of 73 Date 14 AUG 2025 
07. Financial Summary
07.1. How is the Roads Service Funded?
There are 32 Local Authority councils in Scotland. Each council is responsible for a range of
services, including roads, schools, housing, education, social work, street lighting, refuse
collection, elections, and planning. Each council is responsible for allocating budgets to the various
service areas. 
Councils get their budgets, primarily from four sources that include: -
 Service Income. This is income that councils receive;
 Scottish Government capital expenditure and revenue expenditure grants;
 Council tax;
 Non domestic rates. 
07.2 Differences between Expenditure and Capital Expenditure
Councils meet the costs of their statutory and discretionary services through a combination of
revenue and capital expenditure: - 
 Revenue expenditure covers day to day costs required to manage a service. These
costs include items such as salaries, pensions, rent, and electricity bills. Revenue
expenditure, specifically for a Roads department, also covers items such as winter
maintenance, grass cutting, gully cleansing and pothole repairs. 
 Capital expenditure relates to investments in assets such as buildings and roads
infrastructure. Capital expenditure varies between individual councils. This is due to the
particular services each authority provides and the distinctive nature of their local
economies. Capital expenditure, for a Roads department includes costs for projects
that include roads and footway resurfacing schemes, street lighting replacement
schemes, replacing structures, or replacing/ installing vehicle restraint systems (VRS). 
173

Page 174

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 42 of 73 Date 14 AUG 2025 
07.3. Asset Valuation
As of 31st March 2024, the Roads assets are valued as follows: -
Table 12. East Ayrshire Council Asset Valuation as of 31st March 2025 
(Data from Asset Valuation Summary Output, Table 1.2)
Asset Type
Gross
Replacement Cost
£'000
Depreciated
Replacement Cost
£'000 
Annualised
Depreciation
Charge £'000
Carriageway £1,323,840 £1,124,717 £22,698
Footway £119,501 £70,615 £2,384
Structures £205,519 £165,934 £2,012
Street Lighting £48,999 £23,458 £1,168
Street Furniture £12,388 £6,168 £584
Traffic Management
Systems £10,004 £6,268 £464
Land £139,678    
Total £1,859,929 £1,397,160 £29,309 
174

Page 175

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 43 of 73 Date 14 AUG 2025 
Table 13 South Ayrshire Council Asset Valuation as of 31st March 2025 
(Data from Asset Valuation Summary Output, Table 1.2)
Asset Type
Gross
Replacement Cost
£'000
Depreciated
Replacement Cost
£'000 
Annualised
Depreciation
Charge £'000
Carriageway £1,067,408 £898,867 £15,075
Footway £115,952 £70,676 £2,423
Structures £97,948 £89,668 £652
Street Lighting £42,460 £21,722 £977
Street Furniture £3,475 £1,747 £172
Traffic Management
Systems £8,948 £5,774 £364
Land £231,510    
Total £1,567,700 £1,087,796 £21,789 
175

Page 176

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 44 of 73 Date 14 AUG 2025 
07.4. Historical Expenditure
Historical expenditure on the Road Asset over the last five financial years is shown for East
Ayrshire Council, and for South Ayrshire Council in tables below. 
* The historical expenditure data, from APSE, for 2024/25 will not be available until September 2025.   
Table 14. East Ayrshire Council Historical Expenditure 
Asset Works
Historical Expenditure (£’000)
2019/20 2020/21 2021/22 2022/23 2023/24
Carriageways Capital £5,380 £4,659 £4,907 £2,994 £3,194
Revenue £1,261 £1,031 £1,157 £1,557 £2,058
Footways Capital £243 £81 £155 £188 £161
Revenue £86 £75 £135 £187 £217
Structures Routine &
Reactive £104 £111 £172 £1,241 £1,170
Planned £711 £882 £976 £434 £153
Street
Lighting
Energy Costs £1,020 £978 £1,004 £926 £1,312
Routine &
Reactive £246 £239 £293 £283 £306
Planned £273 £340 £715 £828 £1,125
Traffic
Signals
Routine,
Planned &
Reactive
£49 £220 £448 £102 £78 
Total £9,373 £8,616 £9,962 £8,740 £9,774
176

Page 177

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 45 of 73 Date 14 AUG 2025 
Table 15. South Ayrshire Council Historical expenditure
Asset Works
Historical Expenditure (£’000)
2019/20 2020/21 2021/22 2022/23 2023/24
Carriageways Capital £2,091 £2,971 £2,548 £2,864 £4,494
Revenue £1,980 £1,590 £2,242 £1,247 £1,579
Footways Capital £36 £0 £262 £130 £200
Revenue £230 £153 £234 £255 £282
Structures Routine &
Reactive £35 £48 £26 £120 £108
Planned £112 £167 £177 £404 £45
Street Lighting Energy
Costs £773 £634 £545 £546 £1,063
Routine &
Reactive £201 £152 £266 £357 £326
Planned £1,797 £294 £410 £317 £212
Traffic Signals
Routine,
Planned &
Reactive £194 £227 £261 £320 £47
Total £7,449 £6,236 £6,971 £6,560 £8,356 
* The historical expenditure data, from APSE. for 2024/25 will not be available until September 2025.
177

Page 178

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 46 of 73 Date 14 AUG 2025 
07.5. Planned Funding
Table 16. East Ayrshire Council Planned Capital Funding – 2025/26 to 2030/31 
2024/25
(£M)
2025/26
(£M)
2026/27
(£M)
2027/28
(£M)
2028/29
(£M)
2029/30
(£M)
2030/31
(£M)
TOTAL
(£m)
Roads &
Transportation
Programme
3.878 3.050 3.050 3.050 3.050 3.050 2.872 22.000
Bridge Improvement
Programme
2.400 3.500 1.500 1.500 1.500 1.500 1.500 13.400
Total 6.278 6.550 4.550 4.550 4.550 4.550 4.372 35.400 
178

Page 179

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 47 of 73 Date 14 AUG 2025 
Table 17. South Ayrshire Council Capital Investment Budgets 2024/25 to 2033/34 
2025/26
(£m)
2026/27
(£m)
2027/28
(£m)
2028/29
(£m)
2029/30
(£m)
2030/31
(£m)
2031/32
(£m)
2032/33
(£m)
2033/34
(£m)
2034/35
(£m)
Roads
Reconstruction
1.581 2.500 2.500 2.500 2.500 1.500 1.500 1.500 1.500 2.500
Street lighting 0.150 0.150 - - - - - - - -
LED Replacement - - 0.025 0.025 0.025 0.025 - - - -
Bridges Capital 0.600 - - - - - - - - -
Victoria Bridge 0.281 - - - - - - - - -
Millennium and
Craigholm Bridges
0.145 0.145 - - - - - - - -
C12 Dunure Slope
Stabilisation
0.130 - - - - - - - - -
179

Page 180

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 48 of 73 Date 14 AUG 2025 
Table 17. South Ayrshire Council Capital Investment Budgets 2024/25 to 2033/34 
2025/26
(£m)
2026/27
(£m)
2027/28
(£m)
2028/29
(£m)
2029/30
(£m)
2030/31
(£m)
2031/32
(£m)
2032/33
(£m)
2033/34
(£m)
2034/35
(£m)
Vehicle Restraint
Barriers
0.073 0.050 0.050 0.050 - - - - - -
Cattle Grid
Renewal
0.033 0.033 0.033 - - - - - - -
Total 2.993 2.878 2.608 2.575 2.525 1.525 1.500 1.500 1.500 2.500 
180

Page 181

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 49 of 73 Date 14 AUG 2025 
08. Asset Investment Strategies
Managing Assets in a controlled manner optimises cost and risk, allowing timely and fact based
decisions and delivers value in meeting our objectives. 
08.1. Road Condition Indicator Backlog
W.D.M. Limited for Society of Chief Officers of Transportation in Scotland, on behalf of all 32
Councils in Scotland, carry out condition surveys of all roads. This is known as the Scottish Roads
Maintenance Condition Survey (SRMCS) contract. The contract, awarded in 2018, for four years
(with possible three year extension) involves surveying all classes of road at differing frequencies
with a specialist vehicle.
A Road Condition Index (RCI) is calculated for every 10 metre subsection of the road that has been
surveyed. There are five parameters that data is gathered for. These are: -
 Rut depth;
 Texture Depth;
 3m Longitudinal Profile Variance;
 10m Longitudinal Profile Variance;
 Whole Carriageway Cracking Intensity. 
Each 10 metre subsection of road network surveyed is given an overall Road Condition Indicator
(RCI) score dependent on the survey readings of these five parameters. Only the highest of the 3
metre or 10 metre Profile Variance scores contribute to the overall RCI score. The SRMCS
Performance Indicator is made up from the total proportion of a network that is above or equal to an
RCI of 40. 
181

Page 182

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 50 of 73 Date 14 AUG 2025 
Traffic light colours, Green, Amber and Red have been assigned to different RCI bands as shown
below:
➢ Green - A Road Condition Indicator score < 40 - Carriageway is generally in a good state
of repair;
➢ Amber – A Road Condition Indicator score ≥ 40 and <100 - Some deterioration is apparent
which should be investigated to determine the optimum time for planned maintenance
treatment;
➢ Red – A Road Condition Indicator score ≥ 100 - Carriageway is in poor overall condition
which is likely to require planned maintenance soon (i.e. within a year or so).
The SRMCS Performance Indicator score is made up of all the 10 metre subsections that are in an
amber or red condition. The table below shows the backlog (defined as the carriageway maintenance
funding required to treat all 10 metre subsections in the amber or red annual performance indicator
category). 
Table 20. Network RCI Data for East Ayrshire Council & for South Ayrshire Council
Authority RCI 
2018 - 20
RCI 
2019 - 21
RCI 
2020 - 22
RCI
2021 - 23
RCI
2022 - 24
RCI
2023 - 25
RCI
2022/24
to
2023/25
EAC 37.8% 36.8% 33.3% 33.5% 33.0% 31.7% -1.3%
SAC 40.6% 40.9% 39.0% 37.4% 35.5% 34.0% -1.5% 
The headline backlog budget, from the 2023 SCOTS Backlog & Steady State Model Report (SCOTS
Report), is defined as the carriageway maintenance funding required to treat all 10 metre
subsections in an amber or red condition within one year.  This can be thought of as achieving a
network free from carriageway defects exceeding the lower threshold levels. It is not a network free
from any defects because it will allow, for example, rut depths up to 10mm, and texture depths down
to 0.7mm. 
182

Page 183

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 51 of 73 Date 14 AUG 2025 
To treat all the amber and red in one year would not be a practical maintenance option due to the
disruption it would cause, but the figure does allow a comparative budgetary valuation to be
calculated which can be monitored on an on-going basis.
From the SCOTS Report, the headline backlog for 2023 was £53,051,000 for East Ayrshire Council
and is £50,601,000 for South Ayrshire Council.
The average annual budget calculated in the models for each authority, to maintain the SCOTS
Report Steady State RCI scores, excludes any allowance for inflation or discount levels over the
next ten-year period. 
To maintain the RCI’s, from the 2023 SCOTS Report, of 33.5, for East Ayrshire Council, and 37.4,
for South Ayrshire Council, the following steady state carriageway surfacing budgets would require
to be allocated: -
➢ East Ayrshire Council - £8,477,000;
➢ South Ayrshire Council - £6,786,000.
If the Councils do not maintain the above steady state expenditure over the next ten years, for
carriageway surfacing, then the carriageway asset will deteriorate, resulting in an increase in the
overall network Road Condition Indicator (RCI). 
183

Page 184

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 52 of 73 Date 14 AUG 2025 
09. Risk Management
09.1. Risk Management Introduction
The Roads (Scotland) Act 1984 Section 1, states that “…a local roads authority shall manage and
maintain all such roads in their area as are for the time being entered in a list (in this Act referred to
as their “list of public roads”) prepared and kept by them under this section.”
Road Authorities have a Duty of Care under Common Law. The criteria commonly used by the
Courts to determine if a defendant is liable are:
1. The harm which occurred must be a reasonable foreseeable result of the defendant's
conduct;
 Was the authority aware of the defect?
 Was the route inspected within assigned timescales?
 Experience of similar defects and the deterioration/degradation rates?  Will the defect
deterioration/degradation cause the likelihood and/or impact of the defect to increase
before the next inspection?
 Has there been similar incidents on the authorities’ network or is the authority aware
of similar incidents occurring?
2. It is fair, just and reasonable to impose liability.
 Did the authority assess, prioritise and maintain the defect in accordance with their
Maintenance Strategy/Manual or equivalent documents?
 What was the defect risk and priority?
 If necessary, what action(s) had been taken to repair the defect? Timescale for the
repair?
 Was the defect repaired within specified timescales? 
Road Authorities must ensure that their Inspectors are competent. Ayrshire Roads Alliance safety
inspectors are therefore required to undertake the SCOTS Risk-based Approach to Safety Defect
Inspections methodology training and achieve a pass grade on the course assessment. 
184

Page 185

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 53 of 73 Date 14 AUG 2025 
The Safety Inspection regime forms a key aspect of the road authority’s strategy for managing liability
and risk. The objectives of safety inspection activity are to:
 Minimise the risk of injury and disruption to road users as far as is reasonably
practicable;
 Provide a regular, structured inspection of the public road network, within available
resources;
 Deliver a consistent, reliable response to identified defects, within available
resources;
 Maintain accurate and comprehensive records of inspections and response and;
 Provide a clear, accurate and comprehensive response to claims.
The Ayrshire Roads Alliance, since the 1st April 2019, has adopted the SCOTS Risk Based Approach
that promotes a consistency in the management of the road network by focusing on delivering a
programme of permanent repairs to improve its condition and safety.  
The methodology, for this risk based approach, is covered by the “Road Asset Inspections: A Risk
Based Approach – Safety Inspection Strategy Manual”, which has been approved by the Ayrshire
Shared Services Joint Committee.
A Risk Based Approach is also recommended by the Institute of Highway Engineers in their guidance
on managing risk and liability, ‘Well Managed Highway Liability Risk’. 
185

Page 186

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 54 of 73 Date 14 AUG 2025 
09.2. Safety Inspection Strategy
The Road Safety Inspection Strategy was developed, and is maintained, utilising best practices as
specified within the Well Managed Highways Code of Practice along with the SCOTS Roads Asset
Management Planning Project.
Councils continue to face year on year budget reductions with inevitable impact on roads
maintenance budget allocations. Budgets, for roads maintenance must be targeted in the most
efficient manner possible in order to manage our road network efficiently, effectively and to minimise
deteriorating condition.
Taking a risk based approach, as per the above code of practice, means that there are NO
prescriptive investigation or intervention levels to apply. The rationale for removing these is that the
same defect will represent a different level of risk in a different context. Previously, this has led to
inappropriate and often unnecessary, costly, temporary repairs. Instead, by using a risk based
approach, councils can reduce such reactive interventions and target more of their scarce resources
towards programmed work that in the longer term will lead to an overall improvement of road
condition.
The primary aim of the Roads Asset Inspection Strategy is providing operational guidance to those
officers involved in managing and undertaking road asset safety inspections. This is in order to
ensure a consistent approach by utilising a formalised system that prescribes the frequency of
inspections as well as the method of assessing, recording and responding to defects in the road
asset.
The safety inspection strategy requires several key steps, explained in detail within this document.
They are:
186

Page 187

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 55 of 73 Date 14 AUG 2025 
Road hierarchy forms the foundation of a
risk based maintenance strategy; crucial for
establishing service levels and network
management. 
Define the physical routes of inspection, the
standard frequencies and modes of
inspection (driven/walked etc.). 
A methodology inspectors can follow to
assess defects to determine the level of risk
and priority of response. 
Assign an appropriate safety level of
response (time and type) to each prioritised
category of risk. 
Establish procedures for documenting
safety Inspections and other key
information such as inspector training and
competency records. 
Regularly monitor and review the Safety
Inspection strategy and its operation. 
FIGURE 8: Strategy Key Steps
187

Page 188

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 56 of 73 Date 14 AUG 2025 
The Safety Inspection Strategy Manual has a number of sections that include: - 
➢ Safety Inspection Procedures;
o Planned Cyclic Safety Inspections;
o Reactive Safety Inspections (Ad hoc);
o Road Condition inspections;
o Inspections of Utility Works and Third Party Works;
o Service Inspections.
➢ Items for Inspection
o Carriageways;
o Footways, Footpaths & Cycleways;
o Street Furniture;
o Street Lighting;
o Others.
➢ Methodology
o Hierarchy;
o Inspection Frequencies;
o Inspection Tolerances;
o Defect Risk Assessment;
o Utility Company Defects;
o Priority Response Times.
➢ Meeting Response Times 
188

Page 189

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 57 of 73 Date 14 AUG 2025 
09.3. Risk Strategy
09.3.1. Defect Risk Assessment
The Ayrshire Roads Alliance Road Asset Management Safety Inspection Strategy document assists
in specifying what is inspected, the prioritisation of risks, and inspection frequencies, in order to
reduce overall risks to acceptable levels. The procedure for risk assessment is as follows:
➢ Risk Identification 
An inspection item for which the inspector identifies a hazard is to be identified as a risk. The
types of asset to be inspected and the potential associated hazards from defects are detailed
in the Inspectors Operations Manual.
➢ Risk Evaluation 
All risks identified through this process must be evaluated in terms of their significance which
means assessing the likelihood of the risk happening and the likely impact should the risk
occur.
➢ Risk Likelihood
The probability of a risk occurring will be quantified on a scale of Remote to Almost Certain
assessed as follows: 
Table 21. Risk Likelihood
Likelihood /
Probability Likelihood Description
Almost Certain Will undoubtedly happen Daily
Likely Will probably happen, but not a persistent
issue  Monthly
Possible May happen occasionally  Annually
Unlikely Not expected to happen, but it is possible 10 years
Remote Improbable  20 years 
189

Page 190

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 58 of 73 Date 14 AUG 2025 
The probability of a risk occurring will also be quantified by assessing how many users are likely to
pass by or over the defect and consequently the network hierarchy and defect location are important
considerations in the assessment.
The Risk Matrix for deciding each of the risk factors (Likelihood x Severity) in a 5 by 5 matrix are
illustrated in the table below:- 
Table 22. Impact/ Severity Score 
Description
Consequence
(Impact /
Severity)
Impact on
Service
Objectives
Financial Impact Impact on
people
Impact on
Reputation
Catastrophic
Unable to
function, inability
to fulfil obligations
Severe 
financial loss  Death
Highly damaging,
severe loss of
public confidence
Major
Significant impact
on services
provision
Major 
financial loss
Extensive injury,
major permanent
harm
Major adverse
publicity, major
loss of confidence
Moderate
Service
objectives
partially
achievable
Significant 
financial loss
Medical treatment
required, semi-
permanent harm 
up to 1 year
Some adverse
publicity, legal
implications
Minor Minor impact on
service objectives
Moderate
financial loss
First aid
treatment, non-
permanent harm
up to 1 month
Some public
embarrassment,
no damage to
reputation
Negligible
Minimal impact,
no service
disruption
Minimal
financial loss
No obvious
harm/injury
No interest to the
press, internal
only 
190

Page 191

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 59 of 73 Date 14 AUG 2025 
The risk factor for a particular risk is the product of the risk impact and risk. It is this factor that
identifies the overall seriousness of the risk and consequently therefore the appropriateness of the
speed of response to remedy the defect. Accordingly, the priority response time for dealing with a
defect can be determined by correlation with the risk factor as shown in the risk matrix, below. 
Table 23. Risk Matrix
CONSEQUENCE 
LIKLIEHOOD
1
(NEGLIGIBLE)
2
(MINOR)
3
(MODERATE)
4
(MAJOR)
5
(CATASTROPHIC)
1 (REMOTE) No Response No Response No Response No Response P3
2 (UNLIKELY) No Response No Response P4 P4 P3
3 (POSSIBLE No Response P4 P4 P3 P2
4 (LIKELY) No Response P4 P3 P2 P1
5 (ALMOST
CERTAIN) No Response P3 P2 P1 P1 
Having identified a particular risk, assessed its likely impact and probability, and calculated the risk
factor, the risk management procedure can be shown in the form of a risk management (response)
matrix.
Table 24. Risk Management Matrix
RISK CATEGORY PRIORITY RESPONSE
Critical Risk Priority 1 Response (P1)
High Risk Priority 2 Response (P2)
Medium Risk Priority 3 Response (P3)
Low Risk Priority 4 Response (P4)
Negligible Risk No Response (NR)
191

Page 192

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 60 of 73 Date 14 AUG 2025 
For defects located where carriageway and/or footway hierarchies intersect, for example at pelican
or zebra crossings, or other defined crossing points at junctions, the hierarchy of the route with the
most frequent inspection category will always take precedence in determining defect definition and
responses. This principle will also apply to intersections between carriageways and cycle routes and
between cycleways and footways and footpaths. 
09.3.2. Priority Response Times
The Priority Response times, for each Defect Category, are shown in the table below. 
Table 25. Defect Priority and Response Times
Defect
Priority P1 P2 P3 P4 NR
Response
Time 2 Hours 5 Working Days 45 Working Days Programmed
Work
No Action
Required 
Priority 1:  Make safe within 2 hours
Represent a critical risk to road users and should be corrected or made safe at the time of inspection,
if reasonably practicable. In this context, making safe may constitute displaying warning signs and /
or coning off to protect the public from the defect. Where reasonably practicable, safety defects of
this Priority should not be left unattended until made safe or, a temporary or permanent repair has
been carried out.
When a Priority 1 defect is identified within a larger group / area of defects, only that particular
element will be treated as a Priority 1 defect. The remaining defects will be categorised accordingly. 
Priority 2: Repair within 5 Working Days.
This allows a more proactive approach to be adopted for those defects that represent a high risk to
road users or because there is a risk of short-term structural deterioration. Such defects may have
safety implications, although of a lesser significance than Priority 1 defects, but are more likely to
have serviceability or sustainability implications. 
192

Page 193

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 61 of 73 Date 14 AUG 2025 
Priority 3: Action within 45 Working Days.
Defects that require attention although they represent a medium risk to road users. This allows
defects of this nature to be included in medium term programmes of work. 
Priority 4: Consider for Planned Works Programme
The defect is considered to be of low risk; no immediate response is required. Defects in Priority 4
are not classed as safety defects and are collected to assist the development and prioritisation of
Planned Maintenance Works Programmes. 
NR:   No Action Required
The defect is considered to be of negligible risk, no intervention is required and monitoring will
continue as per the inspection regime.  
193

Page 194

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 62 of 73 Date 14 AUG 2025 
10. Glossary
10.1. Abbreviations
Table 26. Abbreviations
Abbreviation Definition
AADF Annual Average Daily Flow: The average over a full year of the number of
vehicles passing a point in the road network each day
ACoP Approved Code of Practice. 
ADC Annualised Depreciation Cost. 
AMP Asset Management Plan. 
APSE The Association for Public Service Excellence (APSE): (APSE Provides
performance data collation and reporting services for SCOTS). 
ARA Ayrshire Roads Alliance. 
BCI Bridge Condition Indicator. 
BSClav Average Bridge Stock Condition Indicator. 
BSClcrit Critical Bridge Stock Condition Indicator. 
CBM Cement Bound Macadam (now more commonly known as Cement Bound
Granular Material – CBGM). 
CBGM Cement Bound Granular Material. Previously known as CBM. 
CIPFA Chartered Institute of Public Finance Accountants. 
CSS County Surveyors Society. 
CVI Coarse Visual Inspection. 
194

Page 195

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 63 of 73 Date 14 AUG 2025 
Table 26. Abbreviations
Abbreviation Definition
DRC Depreciated Replacement Cost. Depreciated replacement cost of an asset
is the current cost to replace the asset less accumulated depreciation. 
DVI Detailed Visual Inspection. 
EAC East Ayrshire Council. Link to website: - https://www.east-
ayrshire.gov.uk/Home.aspx 
FRMP Flood Risk Management Plan. FRMPs are plans to manage the risk of
flooding for people, the economy and the environment, including cultural
heritage. 
GIS Geographic Information System. 
GRC Gross Replacement Cost. The financial cost to build the assets from new. 
HBM Hydraulically Bound Material. Mixtures that set and harden by hydraulic
reaction. They include Cement Bound Materials and slow setting and
hardening mixtures from industrial by products such as fly ash and ground
granulated blast furnace slag. 
HIAMS Highways Infrastructure Asset Management System.
HGV Heavy Goods Vehicle. 
HVO Hydrogenated Vegetable Oil. 
IA Improvement Action. 
KPI Key Performance Indicator. 
LCP Lifecycle Plan. 
LFRMP Local Flood Risk Management Plan. A LFRMP presents actions to avoid
and reduce the risk of flooding, and prepare and protect us, and our
communities, within these potentially vulnerable areas and across the
Local Plan District. 
195

Page 196

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 64 of 73 Date 14 AUG 2025 
Table 26. Abbreviations
Abbreviation Definition
LTP Local Transport Plan. 
LTS Local Transport Strategy. 
NRMCS National Roads Maintenance Condition Survey. 
NRSWA New Roads and Street Works Act 1991. 
PMS Pavement Management System. 
RAMP Road Asset Management Plan.
RAUC(S) Roads Authorities and Utilities Committee (Scotland).
RCI Road Condition Indicator.
RMS Roads Management System.
RQP Reinstatement Quality Plan. Reinstatement Quality Plans provide a way for
organisations to demonstrate their competence to execute road works and
an ongoing commitment to improving quality through having effective
quality control processes in place to ensure standards are met. 
Reinstatement Quality Plans (RQPs) must cover all works that involve
excavation and reinstatement of the road. The plan should cover all aspects
of the works, not just the reinstatement. Undertakers cannot legally start
works without a plan in place. 
RQPs must detail the processes, performance management, evidence
gathering and retention policies specific to your works. Evidence must
demonstrate that plans are being adhered to. 
SAC South Ayrshire Council. Link to website: - https://www.south-
ayrshire.gov.uk/
196

Page 197

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 65 of 73 Date 14 AUG 2025 
Table 26. Abbreviations
Abbreviation Definition
SCANNER Surface Condition Assessment of the National Network of Roads. Objective
method to assess the surface and structural condition of carriageways. 
SCOTS Society of Chief Officers of Transportation in Scotland. A strategic body that
represents Scotland’s 32 Roads Authorities and 7 Regional Transport
Partnerships. 
SCRIM Sideways Coefficient Routine Investigation Machine. The wet skidding
resistance of a road surface is measured that allows an organisation to
know if a road surface has reached levels requiring intervention. Measuring
SCRIM allows for reduced accident rates.
SEPA Scottish Environmental Protection Agency. A non-departmental public
body of the Scottish Government whose role is to ensure that the
environment and human health are protected, to ensure that Scotland’s
natural resources and services are used as sustainably as possible and to
contribute to sustainable economic growth. Link to the SEPA website: - 
https://www.sepa.org.uk/. 
SMP Shoreline Management Plan. A large-scale assessment of the risks
associated with coastal processes and helps to reduce these risks to
people and the developed, historic and natural environment. The plans
intent is to facilitate the management of risks through use of a range of
methods that reflect both national and local priorities. 
SRMCS Scottish Road Maintenance Condition Survey. The Scottish Road
Maintenance Condition Survey is an annual survey which assesses the
condition of the Scottish public road network. This includes both Council
and Trunk Roads. It is used to calculate a Road Condition Indicator (RCI)
that is used by Audit Scotland as a Statutory Performance Indicator (SPI)
for reporting road condition. 
SRWR Scottish Road Works Register. A web based system used for the
management, and coordination of road works, events and road
occupations throughout Scotland. 
SPI Statutory Performance Indicator. Each council reports a range of
measurable performance indicators, to demonstrate that it is securing best
value, by comparing indicators with similar Councils. 
197

Page 198

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 66 of 73 Date 14 AUG 2025 
Table 26. Abbreviations
Abbreviation Definition
TRL TRL is a wholly owned subsidiary of the Transport Research Foundation
(TRF), a non-profit distributing company limited by guarantee, and
established for the impartial furtherance of transport and related research,
consultancy, and expert advice. 
TRO Traffic Regulation Order. A legal tool that allows a Roads Authority to
restrict, regulate or prevent the use of a road. A road may include a
carriageway, footway, footpath & verge. 
A TRO may be permanent, temporary, experimental, or may be imposed
to allow for the holding of a special event. 
UKPMS United Kingdom Pavement Management System. The UKPMS is the
standard system for the assessment of the condition of the UK road
network and for planning investment and maintenance on paved
carriageways, (also footways and cycle-tracks) within the UK. 
Vehicle
mile/kilometre
Used when carrying out traffic counts on roads. One vehicle times one
mile/km travelled (vehicle miles/km are calculated by multiplying the AADF
by the corresponding length of road). For example, 1 vehicle travelling 1
mile a day for a year would be 365 vehicle miles. This is sometimes known
as the volume of traffic. 
WDM  W.D.M. Ltd. - Highways asset management software systems provider.
WGA Whole of Government Accounts (WGA) combines the audited accounts of
over 10,000 organisations across the UK public sector in order to produce
a comprehensive, accounts-based picture of the financial position of the
UK public sector. 
WLC Whole Life Costing. A tool which assesses the total cost of an asset over
its whole life. It takes account of the initial capital cost, as well as
operational, maintenance, repair, upgrade and eventual disposal costs. 
198

Page 199

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 67 of 73 Date 14 AUG 2025 
10.2. Main Definitions
Table 27.  Definitions
Term Definition
Adopted Road Under the Roads (Scotland) Act 1984 Section 151, Public roads,
(sometimes called adopted roads), are those that sit on a roads authority
(local authority) list of roads that are maintainable at public expense. 
Annualised
Depreciation
The cost of annual deterioration of the road network if no maintenance
works are carried out.
Asset Management Asset management involves the balancing of costs, opportunities and risks
against the desired performance of assets to achieve an organisation's
objectives. 
Asset management also enables an organisation to examine the need
for and performance of assets and asset systems at different levels.
Additionally, it enables the application of analytical approaches towards
managing an asset over the different stages of its life cycle (which can start
with the conception of the need for the asset, through to its disposal, and
includes the managing of any potential post disposal liabilities).
Asset management is the art and science of making the right decisions and
optimising the delivery of value. A common objective is to minimise the
whole life cost of assets but there may be other critical factors such as risk
or business continuity to be considered objectively in this decision making.
Asset Valuation The calculation of the current monetary value of an authority’s assets.
Depreciation The systematic allocation of the depreciable amount of an asset over its
useful life arising from use, ageing, deterioration or obsolescence.
Depreciated
Replacement Cost
Method of valuation which provides the current cost of replacing as asset
with its modern equivalent asset less deductions for all physical
deterioration and all relevant forms of obsolescence and optimisation.
199

Page 200

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 68 of 73 Date 14 AUG 2025 
Table 27.  Definitions
Term Definition
Gross Replacement
Cost
The monetary cost of replacing the existing asset with a modern equivalent
asset.
Levels of Service Parameters, or combination of parameters, which reflect social, political,
environmental and economic outcomes that the organisation delivers. 
The level of service statements define how the stakeholders wish that
service to be delivered. The level of service statements become the
justification for funding necessary to deliver the service.
In other words, it’s a way for an organisation to define, capture, and gain
value from its assets.
Levels of Service can be grouped into three categories:
Operational: For example, is the asset clean and well looked after? Is the
paintwork in good condition? Is the asset accessible to the people who
need it?
Service Provision: Is the asset portfolio large enough to serve the
stakeholder requirements? Are there enough of these assets available for
stakeholder needs? Is it fit for purpose?
Implementation: When building a new asset will its capacity be suitable for
the foreseeable future? Or will it have excess capacity that’s not needed –
or will it be far too small? 
Lifecycle Plan Document defining the standards applied to an asset and detailing the
management processes used to deliver those standards.
Public Realm Publicly owned streets, pathways, right of ways, parks, publicly available
open spaces; all areas to which the public has open access.
Public Road A “Public Road” means a road which a roads authority have a duty to
maintain. 
200

Page 201

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 69 of 73 Date 14 AUG 2025 
Table 27.  Definitions
Term Definition
Private Road A “Private Road” means any road other than a public road.  There is still a
public right of passage although the maintenance responsibility lies with the
owner, frontager or others.
Roads Authority Under the Roads (Scotland) Act 1984 Section 151 a Roads Authority may
be a Council, or a Trunk Roads Operating company (who maintain roads
on behalf of Transport Scotland).
Road Infrastructure
Assets
An authority’s portfolio of road assets including adopted roads (excluding
private roads), segregated footpaths and cycle routes, structures, lighting,
traffic management systems, etc. Together they function as a system or
network which as a whole is intended to be maintained at a specified Level
of Service (assessed through performance measures) by the continuing
replacement and refurbishment of its assets and elements.
Section 7 Agreement The Sewerage (Scotland) Act 1968, Section 7 allows roads authorities
(including Transport Scotland) and Scottish Water to enter into
agreements as to the provision, management, maintenance or use
of their sewers or drains for the conveyance of water from the surface
of a road or surface water from premises.
Statutory
Undertakers
Various companies and agencies with legal rights to carry out works on the
road.
201

Page 202

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 70 of 73 Date 14 AUG 2025 
11. References
 Well Managed Highway Infrastructure - A Code of Practice
 Roads Asset Management Framework - Recommended Practices
 EAC Policy documents
 SAC Policy documents
 Maintenance Documents
 WDM Roads Routine Maintenance System
 Roads Asset Management Policy
 Ayrshire Roads Alliance - Road Asset Safety Inspection Strategy Document April
2019
 Ayrshire Roads Alliance - Road Safety Inspector Operations Manual April 2019
 Ayrshire Roads Alliance Service Plan 2022/ 2023 
 Design Manual for Roads & Bridges. GM701 Asset Delivery Asset Maintenance
Requirements
 Performance Report – APSE/SCOTS Results
 Roads Asset Valuation Report - provides information on data used in the valuation,
methods of calculation and interpretation of results
 Annual Status & Options Report (ASOR) - provides a summary of the status of each
asset group in meeting service standards and a prediction of condition based on
varying investment levels
 Just Transition Commission. A National Mission for a Fairer, Greener Scotland (
Just Transition Commission Executive Summary (www.gov.scot) )
 Sustainable Health Equity: Achieving a Net Zero UK (UCL) - Sustainable Health
Equity: Achieving a Net Zero UK (UCL) - Climate Change Committee
(theccc.org.uk)
 United Nations COP27 website - COP27: Delivering for people and the planet |
United Nations
 United Nations COP28 website - COP28 UAE - United Nations Climate Change
Conference
 United Nations Conference of the parties (COP) website -
https://unfccc.int/process/bodies/supreme-bodies/conference-of-the-parties-cop
202

Page 203

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 71 of 73 Date 14 AUG 2025 
 Cycle 1 Solway Local Flood Risk Management Plan LPD14 -
https://www.ayrshireroadsalliance.org/Information-On/Information-on-
Flooding.aspx
 Cycle 2 Solway Local Flood Risk Management Plan LPD 14 -
https://www.ayrshireroadsalliance.org/Information-On/Information-on-
Flooding.aspx
 Cycle 1 Ayrshire Local Flood Risk Management Plan LPD 12 -
https://www.ayrshireroadsalliance.org/Information-On/Information-on-
Flooding.aspx
 Cycle 2 Ayrshire Local Flood Risk Management Plan LPD 12 -
https://www.ayrshireroadsalliance.org/Information-On/Information-on-Flooding.aspx
 Scotland’s Wellbeing: The Impact of COVID-19 - Scotland's Wellbeing: The Impact
of COVID-19 | National Performance Framework
 Ayrshire Roads Alliance Winter Service Plan 2022/23 -
https://www.ayrshireroadsalliance.org/Resources/pdf/Winter-and-gritting/WINTER-
SERVICE-PLAN-2022-23.pdf
 Road Asset Inspections: A Risk Based Approach – Safety Inspection Strategy
Manual
 Scottish Greenhouse Gas Statistics 2020 (Scottish Greenhouse Gas Statistics 2020
(www.gov.scot) )
 Twenty Minute Neighbourhoods in a Scottish Context ( 20 minute neighbourhoods in
a Scottish context (climatexchange.org.uk) )
 Scotland, Let’s Do Net Zero (https://www.netzeronation.scot/ )
 Local Government Information Unit ( https://lgiu.org/perspectives-on-the-20-minute-
neighbourhood-progress-around-the-world/ )
 Marine Scotland. Coastal erosion and flood risk management.
https://marine.gov.scot/sma/assessment/coastal-erosion-and-flood-risk-
management
 Dynamic Coast. https://www.dynamiccoast.com/
 Highways – Maintaining a Vital Asset. What Should Councillors Know About Asset
Management? https://www.ciht.org.uk/media/11809/highways-maintaining-a-vital-
asset-what-should-councillors-know-about-asset-management-pdf-4pages-
148kb.pdf
 Managing a valuable asset: improving local road condition. All Party Parliamentary
Group on Highway Maintenance. https://www.appg-betterroads.org/wp-
content/uploads/2017/07/APPG_Report_-_Managing_a_valuable_asset.pdf
 https://www.transport.gov.scot/media/fgyfwlpi/chapter-summary-scottish-transport-
statistics-2024.pdf
203

Page 204

Roads Asset Management Plan 2025 
Document Roads Asset Management Plan REV 3
RAMP Page 72 of 73 Date 14 AUG 2025 
 https://roadtraffic.dft.gov.uk/regions/3
 https://www.transport.gov.scot/media/2fsn3zku/key-reported-road-casualties-
scotland-2024.pdf
 https://documents1.worldbank.org/curated/en/981831493278252684/pdf/114641-
WP-ClimateAdaptationandAMSSFinal-PUBLIC.pdf
 Institute of Asset Management. – “Asset Management – An Anatomy” -
https://theiam.org/knowledge-library/asset-management-an-anatomy/
 Global Forum on Maintenance & Asset Management – “The Asset Management
Landscape, Third Edition” - https://theiam.org/knowledge-library/the-asset-
management-landscape/
 Institute of Asset Management – “An Introduction to Asset Management” -
https://theiam.org/knowledge-library/an-introduction-to-asset-management/ 