Page 1

Official
AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
05 September 2025 
Report by the Head of Ayrshire Roads Alliance
______________________________________________________________ 
SUBJECT: ROADWORKS PROGRAMME 2025/26
______________________________________________________________ 
Purpose of report 
1. The purpose of this report is to advise the Joint Committee on the progress of
work through the road improvement programmes within East Ayrshire and South
Ayrshire for financial year 2025 to 2026. 
Recommendations 
2. It is recommended that Joint Committee: 
(i) Notes, the Ayrshire Roads Alliance programmed works 2025/26
(ii) Otherwise, notes the contents of this Report.  
Background 
3. The budget allocation for East and South Ayrshire Councils Roads Investment
Programme for FY 2025/26 can be seen in tables 1 and 2 below respectively. 
Table 1: East Ayrshire Council Roads Investment Programme 2025/26 
Programme Area Budget (£m)
Carriageway Resurfacing 2.081
Footway Resurfacing 0.084
Street Lighting 0.215
Traffic & Transportation incl. road safety 0.330 
Active Travel 0.050
School Streets 0.050
Bridge and Culvert Strengthening 
(incl. road slips)
3.500
Car Parks incl. Multi-storey demolition 0.820
Fleet 0.600
Total  £7.730
External Funding (Confirmed) 
SPT – Behaviour Change £0.385
Transport Scotland – Behaviour Change £0.116
ATIF - Tier 1  £0.758
Developer Contributions/Route Action
Plans
£0.359
Bus Infrastructure Fund – Tier 1 £0.645
SG – EV Infrastructure Fund £2.800

Page 2

Official
Total £ 5.063
External Funding (To be Confirmed) 
Sustrans – Annick Valley Stage 2 £0.165 
(Award letter to be issued)
ATIF Tier 2 - Design £2.405 (Tbc.)
Road Safety Improvement Fund £0.300 (Tbc)
Total £2.870 (Tbc.) 
Table 2: South Ayrshire Council Roads Investment Programme 2025/26 
Programme Area Budget (£m)
Carriageway & Footway Resurfacing 1.581
Street Lighting 0.150
Bridges Capital 0.881
Millennium and Craigholm Bridges 0.145
C12 Dunure slope stabilisation 0.130
Vehicle restraint barriers 0.073
Cattle grid renewal 0.033
Girvan Harbour Jetty repairs 0.504
Local Flood Risk Plan 0.153
Ayr Depot 0.250
Climate Changes St Ninians Park 0.255
EV Charging Infrastructure 0.281
Total £4.436
External Funding (Confirmed) 
SPT – Behaviour Change £0.170
Transport Scotland £0.116
Tier 1 – Active Travel Funding £0.737
ATIF–Tier 2(Dundonald – Barassie) £2.700
Ayrshire Growth Deal £0.857
Levelling Up Fund (Active Travel) £4.000
Levelling Up Fund (Burns Statue) £15.000
Bus Infrastructure Fund – Tier 1 £0.382
Total £23.962
External Funding (To be Confirmed) 
Sustrans £0.753 
(Award letter to be issued)
ATIF Tier 2 - Design £1.626 (Tbc.)
Road Safety Improvement Fund £0.270 (Tbc.)
Total £2.649 (Tbc.) 
Note: Several funding applications have still to be confirmed. The affected areas
of potential funding are denoted by the use of “£Tbc.” in Tables 1 and 2 above. 
Main report/main issues 
4. Surfacing programmes for FY 2025/26 are contained within Appendices 1 and 2.

Page 3

Official
Capital Resurfacing 
5. Due to carcinogenic properties in Coal Tar, additional control measures are in
place which requires coal tar testing to be undertaken before the commencement
of works. 
6. The requirement for a new coring contract has meant that the start date for some
of our resurfacing sites has been delayed until the sites can be tested when the
coring contract is awarded in September. 
7. The Capital budget for both authority areas is committed and it is anticipated
remaining surfacing works will commence late November.  Depending on
weather conditions during the winter months there is a possibility that some
works may require to be carried over into financial year 2026/27. 
8. In South Ayrshire we have completed 40% of the carriageway programme with
an anticipated completion date of March 2026.  The footway resurfacing
programme commences in September 2025 with an anticipated completion date
of November 2025 with some sites identified for surfacing being carried over into
financial year 2026/27 as detailed in appendix 1. 
9. Due to the delay with the Coring Contract, there is a risk resurfacing works may
not be completed as planned during December to March 2026, owing to potential
unsuitable winter weather conditions.   As an alternative in South Ayrshire we are
proposing to carry out overlay works on sites which do not require planing and
associated coal tar disposal prior to winter. These sites could potentially be
surface dressed in the future.  It is therefore proposed that 6 resurfacing sites be
carried forward into 26/27 programme to ensure works are completed under
more favourable conditions. 
10. In East Ayrshire 11% of the carriageway resurfacing programme has been
completed as detailed in appendix 2 
11. During a more detailed inspection undertaken on the A71, Kilmarnock from
Moorfield Roundabout to the North Ayrshire Boundary, it was discovered the
condition of the carriageway surface was worse than initially anticipated and the
engineering decision was made to allocate a further £400k+ towards this project
thus allowing the full length to be completely resurfaced with new road markings
and cats eyes being installed. 
King Street Fire – Kilmarnock Town Centre 
12. At around 21:00 hrs on the evening of Monday 14th July a huge fire took hold of
a property in King Street with the first 48 hours, the scene was under the direct
control of Police Scotland and Scottish Fire and Rescue.  Ayrshire Roads
Alliance under the direction of the police incident commander coordinated road
closures and diversions around the scene and arranged for heras fencing to
secure the site.

Page 4

Official
13. Ayrshire Local Resilience Partnership (ALRP) was activated followed by a
coordinated response to the immediate aftermath and recovery phase
demonstrating the strength of partnership working between our blue light
emergency services, East Ayrshire Council, Ayrshire Roads Alliance and Utility
Companies. 
The President and Vice President of the United States visit to Ayrshire 
14. Adopting a “Gold, Silver & Bronze” Command and Control structure chaired by
Police Scotland, East Ayrshire, South Ayrshire & Ayrshire Roads Alliance in
partnership with all agencies including the US Secret Service supported the
policing operation around the Presidential visit on 25th until 31st July.25 and
shortly thereafter also accommodated the Vice President visit on 13th August until
17th August.25. 
East Ayrshire Council residential road and footway repairs (Additional Revenue
Funding) 
15. At Cabinet on 13 March 2025, East Ayrshire Members Initiatives approved £800k
revenue funding for residential and footway repairs with locations identified
detailed within Appendix 2 of this report with 13% complete to date. 
South Ayrshire Council Ward Investment and Promenade Programme 2025/26 
16. Officers within our engineering disciplines continue to develop work schemes
identified by Ward Members under the South Ayrshire Council Ward Investment
Programme for 2025/26 as detailed within Appendix 4 of the report. Sites will be
further added as discussions progress with Officers and Ward Members. 
Timber Transport 
17. As reported at the last joint committee in June 2025 neither authority area was
successful in their bids for grant funding from the Timber Transport Fund. 
18. Officers are committed to reviewing our application process and an early meeting
will be arranged with the Timber Transport Consortium when the window opens
for 2026/27 applications. 
Street Lighting 
19. The Scotland Excel Street Lighting Material Framework has still not been issued
and this is hampering the completion of the LED project in the East.  This has
been ongoing for 3 years and with assistance from our Procurement colleagues
after exploring alternative options we have recently issued a tender via the YPO
‘Highway Electrical Installations’ procurement framework for the supply of street
lighting materials and sundry electrical items. 
20. The Street lighting column and cable replacement programme of works which
incorporates LED lanterns is detailed in Appendix 1 and 2.

Page 5

Official
Electric Vehicle Infrastructure 
21. The Electric Vehicle Infrastructure Fund (EVIF) programme with the number of
public chargers installed to date is listed within Appendix 3 for South and East
Ayrshire respectively. 
22. East Ayrshire Council is the lead authority for the PAN Ayrshire Public Electric
Vehicle Charging Strategy. The project has secured a grant of £2.8million and
work continues on the procurement phase. Following the previously approved
business case, further papers have been presented to the cabinet regarding the
introduction of an EV charging tariff, which has been implemented across all
three Ayrshires as of 1st January 2025. A further increase to tariff was
implemented on 1st July 2025. This tariff aims to establish a sustainable funding
model and attract private investment. 
23. Work continues on the tender documentation for the Pan Ayrshire concession
contract with the appointment of Mott MacDonald as consultants to assist with
the collation of the relevant documents required for tender. The Single
Procurement Document (SPD) was issued on 3rd March 2025 for the initial stage
of tendering, followed which we received numerous bids. The second part of the
tendering process is currently ongoing, with the Invitation to Tender (ITT) to be
published in September 2025 for the shortlisted bidders, followed by contract
award in January 2026. 
24. Under the Public Charge point regulations 2023 legislation all Rapid Chargers
are required to be able to accept contactless payment by 24th November 2024. 
Ayrshire Roads Alliance has secured funding from Transport Scotland
Contactless Compliance Grant Funding to replace/activate/retrofit eligible CPS
rapid chargers to incorporate contactless payment. Works have been carried out
to replace the non-compatible units and to activate contactless terminals on
compatible rapid chargers. 
25. Replacement of 22kW charger at Troon Swimming Pool will be funded from SAC
Capital budget but is on hold until the concession Contract is awarded in
December 2025. 
26. Replacement of 50kW chargers at Burns Statue Square, Ayr and Girvan Harbour
have been replaced and commissioned. 
Structures 
27. Land acquisition and/or access agreements alongside environmental license
requirements continue to cause delays to a number of projects. ARA are working
closely with EAC Legal/Estates and relevant stakeholders to progress these
issues. 
28. Appendix 2 details East Ayrshire Council Bridges Capital programme for
2025/26.

Page 6

Official
29. A713 Polnessan Upper Bridge - ARA have erected temporary traffic signals due
to subsidence in the carriageway. Traffic lights will remain in place until the slope
has been stabilised. Project is near tender ready. 
30. B741 Coal Glen Embankments works to be retendered following discussion with
SPEN regarding utilities in the vicinity of the works. 
31. A735 Lochridge Culvert - general culvert repair works ongoing. Scope of work
increased on site due to poor ground conditions. 
32. ARA are working with EAC Legal/Estates to acquire land at West Clerkland
Bridge through a Compulsory Purchase Order. The bridge has been shut to
vehicular traffic since 2012 and shut to both pedestrians and vehicular traffic
since 2021. 
33. 3no. bridges on the A71 between the Bellfield Interchange and Moorfield
Roundabout need replacement expansion joints. A consultant was appointed to
explore options in removing the joints and making the structures semi/fully
integral. It has been decided that in the meantime 2 joints that are repeatedly
failing will be replaced with asphaltic plug joints. 
34. B730/10 Littlemill Bridge - land acquisition complete after years of negotiation.
Tender documents to be reviewed and works tendered with a view to start on
site in Spring 26. 
35. Contract awarded for low bridge sign upgrades at 5 structures in Kilmarnock and
Kilmaurs. 
36. South Pier Quay at Girvan Harbour – tenders for steel plate repairs to the existing
sheet piles and grouting is anticipated to be issued in August/September with
works completed by the end of 2025. 
37. The detailed design of the Girvan Harbour Timber Jetty works are progressing
with the Contract documentation substantially complete.  The Tender will be
issued once the South Pier Quay tenders have been returned and costs known. 
38. The A79/30 Victoria Bridge Concrete Repairs and Painting has been completed. 
39. The Contract Documentation for Girvan Harbour dredging and land based
material disposal has been finalised and are with Procurement for Tender issue. 
40. Ayr South Pier - as previously reported at the last Shared Service Joint
Committee in June 2025, funding to employ a consultant to carry out an
underwater dive survey and structural assessment has not been secured. This
is a matter of concern as the importance of a dive survey and assessment was
highlighted following the development of a sink hole in a verge area at the end
of the South Pier.

Page 7

Official
Traffic & Transportation 
41. Active Travel Infrastructure Fund (ATIF) Tier 1 grant funding for both autjority
areas has been received from Transport Scotland.  Active Travel projects using
the Tier 1 funding is currently in development, and will be implemented over the
course of the current financial year. 
42. Grant awards have been confirmed from Transport Scotland for both EAC
(£645,000) and SAC (£382,000) from the Bus Infrastructure Fund – Tier 1. This
unforeseen funding is directly awarded and paid to local authorities as part of the
General Capital Block Grant (GCBG) Allocation. ARA are currently developing
delivery programmes for both EAC and SAC areas and reports will be presented
to both Cabinets with proposed programmes of work for review and approval. 
43. Confirmation of the Road Safety Improvement Fund grant allocations is pending
for both authority areas.  Schemes are currently being identified and prioritised
as listed in the appendices but may be subject to change pending Transport
Scotland approval. 
44. Kilmarnock Bus Station refurbishment programme is now complete with Officers
currently reviewing the cleaning regime. 
45. The Contract for Cumnock Bus Station which include changes to materials and
the installation of a public address system is currently being prepared. 
Ayrshire Growth Deal (AGD) Roads Projects 
46. A Case for Change seeking approval of the changes to the Roads Infrastructure
project and also the Prestwick Proposition has now been approved by Scottish
& UK Governments. Ayrshire Roads Alliance will assist in the delivery of all these
projects for South Ayrshire Council. 
47. A Planning application for the construction of a new car park at Shaw Road,
Prestwick will be submitted in September 2025, this is a significant step forward
in the delivery of the AGD. 
48. Extensive ground investigations and environmental studies are currently being
undertaken on the remaining phases of the AGD in an attempt to accelerate the
design process and move more projects through to construction.
Levelling Up Fund
49. South Ayrshire Council successfully secured £20million of funding from the
Levelling Up Fund (LUF) round 3.£15million of this funding has been transferred
to ARA and will be utilised to redevelop Burns Statue Square. Balfour Beatty
have been appointed as the principle contractor, design is currently underway
and a delivery programme will be produced in the coming weeks. 
50. £1.2million of the LUF funding along with a £2.7million award from ATIF will be
used to construct a new Active Travel Route linking Dundonald to Barassie

Page 8

Official
Station, work is currently underway on this route and is scheduled to be complete
by 31st March 2026. 
51. The remaining £2.8million along with funding from the AGD & a bid to the ATIF
in January 2026 will be utilised to carry out significant improvements to the NCN7
from Prestwick to Barassie railway stations. Work will commence on-site late
2025 and will be complete by 31st March 2027. 
Active Travel 
52. The Active Travel Infrastructure Fund (ATIF) administered by Transport Scotland
has awarded £2.7million towards the construction of the Dundonald to Barassie
route. 
53. ARA submitted several funding applications to Sustrans in January 2025 to carry
out the next stages of the design process for several active travel routes across
both South and East Ayrshire Council, it has now been confirmed that Sustrans
will not receive funding from Transport Scotland as had originally been advised
and these applications have now been transferred to ATIF. No decision has been
taken on these application at this time. 
Ash Dieback & Other Species 
54. Appendix 5 of the report details the current condition data on all High Risk
roadside trees for both authority areas.  Surveys and programmed works for
removal are ongoing with 28-day notices being issued to owners and any
objections received referred to legal service. 
Implications 
55. 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning x  56 & 57
2. Governance x  58
3. Human Resources x  59
4. Equality and Fairer Scotland Duty  x 60
5. Financial x  3, 61 &
Appendix 1, 2
and 4
6. Risk x  62 & 63
7. Community Wealth Building x  64
8. Net Zero x  65

Page 9

Official
Policy/strategic planning implications 
56. A well-maintained road network will contribute to achieving the 2015-2030
Community Plan objectives and associated 2021-2024 Delivery Plans 
57. The matters referred to in this report contribute to Priority 1 of the South Ayrshire   
Council Plan: Spaces and Places/ Moving around and the environment
(Outcome 1). 
Governance implications 
58. By virtue of the relevant statutory provisions, principally detailed within the Roads
(Scotland) Act 1984, the Council as local roads authority is required to manage
and maintain all publicly adopted roads within its area other than those which are
maintained and managed by the Scottish Ministers. 
Human resources implications 
59. The work programmes have direct impact on human resources and the Alliance  
will ensure all works are suitably resourced to maintain satisfactory progress. 
Equality impact and Fairer Scotland duty implications 
60. Equality Impact and Fairer Scotland Duty screening assessments will be
undertaken annually as required during the planning stage prior to the delivery
of the programme of works. 
Financial implications 
61. The Ayrshire Roads Alliance will deliver the strategic and local services as stated
in the Service Plan. The budget is provided by East Ayrshire Council, South
Ayrshire Council, and other external organisations. Appropriate scrutiny
arrangements are in place to manage these budgets. 
Risk implications 
62. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every 
Joint Committee. 
63. The Works Programmes, Service Plan and the Risk Register do not expose
either Council to an increased risk as they have been developed from existing
budgets and existing service commitment. 
Community Wealth Building implications 
64. The works programme provides economic levers to develop resilient, inclusive
local economies with more local spend and fair employment, as well as ensuring
that wealth is more locally owned and benefits local people.

Page 10

Official
Net zero implications 
65. The Ayrshire Roads Alliance Service Plan and Carbon Strategy supports and
links to East Ayrshire Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment 
Appendices 
Appendix 1 - South Ayrshire Council Programme of Works 2024/26 
Appendix 2 - East Ayrshire Council Programme of Works 2025/26
Appendix 3 – EV Public Chargers
Appendix 4 - South Ayrshire Council Ward Investment and Promenade
Programme 2025/26
Appendix 5 – Ash Dieback Condition reports EAC & SAC 
Background papers 
• East Ayrshire Council – 2025/26 Road Asset Management Plan.  Investment
and Programme
• South Ayrshire Council – Road Improvement Plan 2025 - 2026 
Person to contact. 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail. jane.corrie@ayrshireroadsalliance.org 
Implementation Officer 
Craig Knape, Strategic Manager - Ayrshire Roads Alliance
Tel No. 01563 503164 
E-mail. craig.knape@ayrshireroadsalliance.org

Page 11

Official
Appendix 1 
South Ayrshire Council – Programme of Works 2024/26 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2024 to 2026   
Route
No
Town Road Name Works
Description
Scheme
Score
Estimate
d Cost
Cost to
Date
Variance
+/-
Comments
B734 Old Dailly Barr Old Dailly Old Dailly to Penkill
+ drainage
improvements
N/A £150,813 £163,932  -£13,119 Complete 
B7035 By Girvan Glendoune Houdston
Road (Coalpots)
Braetoll South + S
Power shut down
N/A £200,000 £206,251 -£6,251 Complete 
B743 By Mossblown Ayr / Mossblown? West from
Brocklehill Farm
53 £249,002 £249,239 -£237 Complete
C37 Auchincruive Barrackhall Gibbsyard  48 £123,861 123,873 -£12 Complete
Uncl Tarbolton Springfield Road Garden Street to No
50
46 £54,275 £53,851 +£424 Complete
B742 By Coylton B742 Council Boundary -
A70/Hillhead, Coylton
By Holebogs, S bend 59 £445,000 £440,506 +£4,494 Complete
B742 By Coylton B742 Council Boundary -
A70/Hillhead, Coylton
From A70 at
Hillhead south to
C21 Craigs Road
junction
56
B742 By Coylton B742 A70 Hillhead - B744
Jcn N Of Annbank, Coylton
From Meadowhead
Depot entrance
south-wards
55 Complete
B742 By Coylton B742 A70 Hillhead - B744
Jcn N Of Annbank, Coylton
Bridge of Coyle to
C2
52
B744 Annbank Weston Brae Full Length 53 £152,000 £207,822 -£55,822 Complete
B744 Annbank Browns Crescent 
Weston Avenue
Full Length
Craighall Way to
101 Weston Avenue
53
56
U77 By Coylton Hole Road Full Length 46 £82,867 £83,064 -£197 Complete 
B7023 Maybole Crosshill Road Full Length 56 £74,687 £72,215 +£2,472 Complete
Complete
Complete 
B7023 Maybole St Cuthbert's Road Full Length 53 £30,669 £41,792 -£11,123
B7024 Maybole Alloway Road Redbrae to Bypass 51 £55,922 £96,288 -£40,366
C122 By Maybole  C122 Gardenrose
Path/Maybole - School
Road/Minishant, Maybole
School to new
Bypass 
50  £58,095 £58,097 -£2 Complete

Page 12

Official 
C122 Gardenrose
Path/Maybole - School
Road/Minishant, Maybole  Ladycross to new
Bypass
B7023 Maybole Ballochbroe to Crosshill Dalhowan to C58  £275,435 £362,350 -£86,915 Complete
A719
PH 2
By Maidens 
By Dunure
Pennyglen/B7023 -
Kirkoswald Road/Maidens,
Maidens 
A719 Smithy
Bridge/Dunure - Croy
Brae, Dunure
B7023 Enoch Lodge
-Caravan Park 
Cemetery to
Drumshang
67 £281,669 £326,746 -£45,077 Complete 
Complete A719
PH 1
By Maidens  Pennyglen/B7023 -
Kirkoswald Rd & 
Turnberry Rd /Maidens,
Turnberry 
Morriston Farm to
Jct Blawearie 
Maidens to
Turnberry
56  £441,666 £540,857 -£99,191
Uncl Maybole Ashgrove Avenue Full Length  £88,954 £102,985 -£14,031 Complete 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – New Sites identified for 2024 to 2026 
B749 Troon Monktonhill Road Southwood jct to
Isle of Pin
59 £210,000 £265,328  -£55,328 Complete.
after excavation, additional
material was required to
regulate due to sand & soft
spots localised to lots of
areas in Troon 
B749 Troon Craigend Road Fullarton Drive
railway bridge to
South Beach
48 £167,500 £201,706  -£34,206  Complete
Overspend same as
Monktonhill Rd
B749 Troon South Beach  Lochend Road to
Academy Street jct
54 £200,000 £307,540  -£107,540  Complete.
Overspend same as
Monktonhill and Craigend.

Page 13

Official
C44 Dailly Dailly to Turnberry Farden 500m
towards Drummock
39 £112,560 £71,137  +£41,422  Complete 
B7027 Barr Knowe Road Lochtonmill
southwards 
£63,000 £53,406.44 +£9,593  Complete 
B734 Colmonell Colmonell to the A77   £106,560 £150,273  -£43,713  Complete 
B7023 Maybole C58 to Cemetary   £297,606 £271,503  +£26,102  Complete 
A70 
C39
Coylton 
Ayr
Joppa 
Doonholm Road
Hole Road jct to
Pharmacy
Alloway to The
Loaning
35 
43
£179,321  £155,377  +£23,944  Complete
C145 Ayr Hillfoot Road Holmston Rd to
Holmston Dr
54 £91,875 £123,733 -£31,858  Complete
Uncl Maybole Queens Terrace/Chesney
Grove/Kincraig Avenue
Full Road 33
33
£166,275  £174,448  -£8,173  Complete
Uncl Maybole Cargill Road Full Road 47 £46,900 £48,224 -£1,324  Complete 
C1
(STTS)
Straiton Newton Stewart Road U8 towards Straiton
to U57
44 £120,400 £119.293  +£1,107  Complete 
B7045
(STTS)
Maybole Cassilis to Kirkmichael Rd Crorieshill Farm
northwards for
360m
44 £46,750  £51,700 -£4,950 Complete
Uncl Ayr Saltpans Road North from Glebe
Road
46 £112,249 £118,940 -£6,691  Complete 
Uncl Prestwick Morris Road Full Road 43 £55,000 £107,345 -£52,345  Complete
(presence of coal tar
increased costs)
Uncl Ayr Green Street Waggon Road to
Crown Street
42 £130,000 £214,584 -£84,584  Complete
(presence of coal tar
increased costs)
Uncl Prestwick Craigie Street Full length 39 £30,000 £36,725 -£6,725  Complete
B744 By Annbank B744 Belston/A70 -
Weston Avenue/Annbank,
Ayr
Auchincruive
Junction to
Glenview
52 £120,000  £139,872  -£19,872  Complete 
B742 By Maybole Dalrymple to Barnford
Farm
Dalrymple Road 46 £130,000  £138,058 -£8,058  Complete

Page 14

Official
Uncl Maybole Hicks Avenue Full cway & fway 30 £104,000 £133,263 -£29,263 Complete
Increased costs due to
combining footway,
kerbing
C59 Colmonell Craigneil Road B734 to Bridge  £67,000 £53,129 +£13,871 Complete 
Uncl Ayr Peggieshill (PH1) Dalmilling Rd to
Nursery Rd
44 £92,000 £99,038 -£7,038  Complete 
Uncl Ayr Kincaidston (PH1) Marigold Sq to
Honeysuckle Park
52 £185,000 £181,768 +£3,232  Complete
Uncl Girvan Louisa Drive Knockcushion St to
Duncan St 
£103,640 £91,410 +£12,230 Complete
Uncl Ayr Peggieshill Rd (PH2) Nursery Rd to
Fenwickland Ave
44 £100,000 £81,228 +18,772 Complete 
C74 By Ayr MacNairston Rd C105 to B742
junction
52 £97,608 £112,326 -£14,718 Complete 
B742 By Maybole Nether Culzean Dalrymple
Rd
Barnford farm to
Nether Culzean
42 £135,000 £130,022 +£4,978  Complete 
Uncl Ayr Ellisland Square (Contains
Coal Tar)
Full Length 42 £125,000  £85,289 +£39,710.80 Complete – final measure
Uncl Ayr Kincaidston Drive (PH2) Honeysuckle Park to
Dalmellington Rd
52 £100,000 £51,730 +£48,270 Complete – final measure
B742 Mossblown Sandyford Road From a point 180
metres east of A719
junction eastwards
for 680m
53 £140,700 £169,432 -£28,732 Complete
Uncl Ayr Dalmilling Road (Contains
Coal Tar)
Harthall to
Mainholm Rd
37 £275,000  £37,032.78 +£212,967.22 Complete – final measure
Uncl Prestwick Bellevue Road (TO BE TESTED) From Main Street to
Adamton Road 
£38,039   c/f to 2026/27 TBC
Uncl Girvan Todd Street (TO BE TESTED) Full length 31 £32,894   c/f to 2026/27 TBC
Uncl Girvan Fauldribbon Road (TO BE
TESTED)
Full length 34 £31,813   c/f to 2026/27 TBC
Uncl Girvan B741 Linfern Road (TO BE
TESTED)
NO.79 to no.3 near
Main Street
29 £100,517   Programmed to Commence
26/01/26
Uncl Maybole Carrick Street (TO BE TESTED) Ladyland Rd  to B77 33 £26,130   c/f to 2026/27 TBC
Uncl Maybole Wellington Street (TO BE
TESTED)
Ladyland Rd to
Carrick St
30 £18,090   c/f to 2026/27 TBC
Uncl Maybole Manse Street (TO BE TESTED) Drumellan St to
Abbott St 
£20,100   c/f to 2026/27 TBC

Page 15

Official
Uncl Girvan Hamilton Street (TO BE
TESTED)
Church Sq to Bridge
St
46 £49,655.55   Programmed to Commence
09/02/26
Uncl Ayr Chapel Park Road Full length 40 £55,984   2026/27
Uncl Prestwick St Cuthbert’s Rd St Andrew’s Ave to
Kirklandholm 
£38,587   2026/27 
Ayrshire Roads Alliance – Overlay surfacing (potential future surface dressing) 
U39 Dailly Hawkhill Road Old Dailly from
number 1 to
number 12
N/A £125,000   TBC 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2024 to 2026 
C17 Tarbolton Westport Footway North side 28 £17,370 £24,984 -£7,644 Complete 
Uncl Prestwick Hunters Avenue South from
Heathfield Road,
west side
23 £7,500 £5,393 +£2,107  Complete
Uncl Troon Morven Drive Cessnock Rd to
Dundonald Rd
(Northside) 
£15,072 £28,820 -£13,748 Complete
C151 Dailly Woodside Both sides from
Back St and
Hadyard Terr
30 £20,400 £17,147 +£3,253 Complete 
Uncl Crosshill Newton Street Church Side of road 30 £15,795 £14,440 +£1,355 Complete
Uncl Dailly Hadyard Terrace Inside footway +
part outer section
28 £54,400 £20,110 +£34,290 Complete 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for 2024 to 2026 
Uncl Mossblown Martin Avenue Mossblown 28 £28,300 £30,829 -£2,529 Complete 
B744 Annbank Weston Brae Full Length 28 £10,700 £5,761 +£4,939 Complete
B730 Dundonald Drybridge Road Bowling Green to
Kilnford Dr
28 £19,223   Works progressing on site
Uncl Ayr Bellevue Crescent Full Length 34 £37,800   TBC - tree inspection,
scope of work to be
determined

Page 16

Official
Uncl Maidens Ardlochan Road Full Length 30 £21,000   Programmed to Commence
24/10/25
Uncl Dailly Church Crecent Odd numbers full
length
30 £16,800   Programmed to Commence
03/11/25
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget allocation 
B743 Mossblown Mauchline Road Fourways to railway
bridge north side
28 £15,300   2026/27
Uncl Ayr Lochpark Slab replacement 23 £20,425   2026/27 
Ayrshire Roads Alliance - Lighting Programme 2025/26 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Ayr Ayr - Old Hillfoot Road, Hillfoot
Crescent & Souter Place
Old steel columns &
unreliable 5th Core 5 £30,000 Complete 
Ayr Cunningham Crescent & Area Unreliable 5th Core
Supplies 16 £40,000 Complete 
Troon Concrete Column
Replacements Ph3
Old deteriorated concrete
columns 43 £55,000 Awarded 
£125,000   
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26
(i) Road Safety Programme 
Town/Route Location Proposed Scheme Progress
Various Various locations   Various schemes (TBC), anticipated to
include:
• Route Action Plan for the
B743 at St Quivox;
• B743 review at Failford
Bridge;
• Speed reduction measures at
Coalpots Road at The
Avenue;
Development of a finalised
programme for the current financial
year will follow confirmation of any
grant award from Transport
Scotland’s Road Safety Improvement
Fund (RSIF).

Page 17

Official 
(ii) Safer Neighborhoods 
Town Location Proposed Scheme Progress
Phase 4 20mph schemes Various roads (TBC) 20mph speed limit schemes Discussion with SAC required to
identify appropriate settlements for
inclusion in Phase 4.
Various Various locations Vehicle activated signs upgrade Pending implementation of new
contract, and extents of upgrades will
be subject to budget. 
(iii) Rural Route Action Plans 
Route Location Proposed Scheme Progress
B743  Between the A77(T) and Auchincruive (St
Quivox)
TBC Listed under RSIF schemes above –
subject to confirmation of funding. 
(iv) Active Travel Infrastructure – ATIF & Sustrans 
Town Location Proposed Scheme Progress
Various Various locations • Various smaller schemes
under Tier 1 funding, details
TBC.   
Currently developing a package of
schemes to be progressed during the
current financial year making use of
the Tier 1 grant award.
Loans From Buchan Road to the A759 Loans to Troon Phase 3 Funding application unsuccessful, new
application submitted to ATIF for
2025/26
Loans From Dundonald Road to Buchan Road Loans to Troon Phase 2 £24,500 received to install permanent
monitoring equipment
• Bradan Road, Troon –
enhanced crossing points;
• Road Safety scheme, Links
Road, Prestwick.

Page 18

Official
Dundonald To the northern side of the A759 Dundonald to Barassie Phase 1 Award received to treat Japanese
Knotweed on-site, full construction
funding application submitted to ATIF
for 2025/26.
Various Various Various Funding application unsuccessful, new
application submitted to ATIF for
2025/26
Girvan  Quay to Grangeston Girvan to Grangeston £27,378 received to complete RIBA
Stage 1, 
Ayr Town Centre Accessible Ayr £778,780 received to complete RIBA
Stage 4 of Route 1 Phase 1
Ayr-Girvan Ayr to Girvan Culzean Way £47,755 received to complete RIBA
Stage 1
Coylton Coylton Primary Access for All – Coylton £27,378 received to install permanent
monitoring equipment
Ayr, Prestwick & Troon NCN7 NCN Barrier Removal £113,500 received to remove barriers
from the NCN7 in Ayr Prestwick &
Troon to make the route inclusive.
Prestwick, Troon & Barassie NCN7 from Prestick Station to A759 Barassie Prestwick to Barassie £82,979 received to complete RIBA
Stage 2
Dundonald Junction of A759/B730 Dundonald Cross £80,000 received to install signals at
the junction of the A759/B730 
Ayrshire Roads Alliance - Structures Capital Programme 2025/26 [Includes works carried forward from 2023/24/25] 
Description   Work Type Estimated
Programme Cost 
Comments Variance +/-
A79-30 Victoria Bridge Concrete Repairs and Painting 
£432,776 
Completed  
0
A79-40  John Street, Ayr, Railway Bridge Parapets  £362,000 Design Phase.  
-£294,225
FB.AYR-70 River Doon Cycleway Footbridge (Millenium Br)
Refurbishment
£145,000 Design Phase Tender Documents completed
and Marine Licence applied for. 
£143,951
U740-10 Barbieston Bridge Replacement Design  £86,820.00 Design Phase 50% - 50% EAC / SAC funded
project as this is a boundary bridge. 
£80,025 
Various Locations
Vehicle Restraint Barrier Renewal £50,000  Design Phase Contract awarded works
ongoing  +£50,000

Page 19

Official
Various Locations Cattle Grid Renewal Programme £33,600 Design Phase Contract awarded works
ongoing
£-33,600
C12 Dunure Station Road Dunure, Slope Stabilisation 
£130,000
A 70m long gravity retaining wall option has
been selected as the most optimum solution.
Detailed design and contract preparation is
currently underway, however the capital
budget currently available for this project is
insufficient for the proposed solution –
additional funding required. To be discussed
with finance. 
-£124,087
Girvan Harbour Girvan Harbour South Pier Repairs £136,000 The South Pier Quay has been assessed to
have a load carrying capacity of 0.5 tonnes
per square metre. Following dive surveys
undertaken earlier this year the option
chosen to extend the life of the structure is
steel plate repairs to the existing sheet piles
and grouting of the voids.   
Completion and submission of the contract
documentation was delayed in order that the
significant damage caused to the South Pier
Quay by the Q-Varl boat, when it broke its
moorings in a storm, could be assessed and
any repairs required could be included in the
contract documents. Tenders to be issued in
August with works completed by the end of
2025. 
£118,989
Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles 
£504,887
The sediment transfer model has been
completed including options to deal with the
defective sheet piling. The recommended
option is to replace only the piling on the
curved section from the lifeboat station.
Contract documentation substantially
complete and will be issued once tenders for
the South Pier Quay works have been
returned and costs are known. 
-£504,887 
£1,881,083

Page 20

Official
Appendix 2 
East Ayrshire Council 
Ayrshire Roads Alliance – Carriageway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 
ROAD LOCATION Estimated
Cost
Cost to Date variance +/- Comment
A71 Dual Carriageway  From Moorfield Roundabout – Target Worst Sections £300,000.00   Complete – final measure
A736/U20 Junction
Contribution to North
Ayrshire to complete
EAC section
Junction Contribution to North Ayrshire to complete
EAC section
£15,000.00 
To be programmed
A735  From Lochridge House North Entrance to Windmill
factory Farm £182,354.25  
To be programmed
A735 Rigg Street
Stewarton From B778 to Brown Street £60,606.00 
To be programmed
B7046 Skares From Junction Newfield Rd to Recycling Centre
Additional section into Skares £116,000.00 £152,936.00  Complete – final measure
B769 Stewarton  From Stewarton to North Ayrshire Boundary £219,375.00   To be programmed
B743 Mauchline High
Street From A76 to Loans (School) £52,680.60  
Programmed to Commence
11/10/25
B7037 Titchfield
Street Galston From Mini Roundabout to Orchard Street £97,500.00  
Programmed to Commence
06/10/25
B7038 Kilmarnock
Campbell Street From: Fire Station AC / To: Willock Street                   £41,595.40  
Programmed to Commence
24/01/26
C3 Barskimming Road
Mauchline From Loudoun Street to StationRoad £74,074.00  
Programmed to Commence
18/10/25
C108 Stewarton From Greensland to Boundary £114,750.00   To be programmed
C22 Coal Road
Auchinleck From Railway bridge to Barbieston Road £35,612.50  
To be programmed
U55 Galston  From U56 approx 1000m Westwards £78,750.00 £60,954.21  Complete – final measure
Kilmarnock New Mill
Road From Chapmans Terrace to end £45,584.00  
To be programmed
Kilmarnock Whatriggs
Road From Tinto Avenue to Haining Avenue £35,612.50  
To be programmed
Kilmarnock East Shaw
Street From Lidle to and around mini roundabout £37,814.00  
Programmed to Commence
04/10/25
Kilmarnock Bentink
Street On Approach to Mini roundabout £20,797.70  
Programmed to Commence
04/10/25

Page 21

Official
Kilmarnock Bellsland
Grove Full Length £19,080.00  
Programmed to Commence
04/10/25
Kimarnock Beech
Avenue From Portland Road to Larch Place £84,501.40  
Programmed to Commence
11/10/25
Kilmarnock Pine Road Full Length £42,022.75  
Programmed to Commence
25/10/25
Kilmarnock Old Irvine
Road From Lindsay Street to Grange Street £37,464.35  
To be programmed
Kilmarnock
Brackenhill Avenue Full Length  £32,323.20  
To be programmed
Kilmarnock Arran
Avenue  Full length  £36,182.30  
To be programmed
Kilmarnock Lainshaw
Avenue One Section £71,225.00  
To be programmed
Kilmarnock Townend Full Length £27,065.50   To be programmed
Stewarton Avenue
Square Access Road into car park £11,396.00  
To be programmed
Kilmaurs East Park
Crescent Full Length £34,045.55  
To be programmed
Galston Western
Road Outside Primary School £29,487.15  
Complete – final measure
Hurlford Mayfield
Avenue Full Length £57,855.42  
To be programmed
Fenwick Skernieland
Road From Old A77 Slip to Rysland Terrace £44,053.31  
To be programmed
Cumnock Hearth
Road Full length £89,909.25  
Programmed to Commence
15/12/25
Drongan Lane
Crescent Full Length £27,195.00  
To be programmed
Bellsbank Corserene
Terrace Full Length £29,526.00  
To be programmed
Dalmellington
Gateside Road Broomknowe to B741 £31,080.00  
To be programmed
Dalrymple Cedar
Terrace  Full Length £15,540.00  
To be programmed
Drongan Mill o Shield
Road From Coyle Avenue and Garrowhill Drive £37,749.25  
To be programmed

Page 22

Official
Ayrshire Roads Alliance – Footway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 
Ayrshire Roads Alliance - £800k Residential Carriageway/Footway Improvement Programme 2025/26 
WARD Location Estimated
Costs
Cost to Date Variance +/- Comment 
1
Carriageway - Stewarton Dornie Close  £9,120.00   To be programmed
1 Carriageway - Stewarton Braemore Road £11,310.00   To be programmed
1 Carriageway - Stewarton Kirkmuir Drive £54,000.00   To be programmed
2 Carriageway - Kilmarnock Tourhill Road £5,580.00   Complete – final measure
2 Carriageway - KilmarnockAuchencar Drive £15,120.00   Complete – final measure
2 Carriageway - KilmarnockWardneuk Drive £6,165.00   Complete – final measure
3 Carriageway - Kilmarnock Woodside Avenue    To be programmed
FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment
Catrine - Newton
Street Outside School £7,290.00  
To be programmed
Auchinleck - Main
Street From Surgery to Council Car Park £21,870.00  
To be programmed
Cumnock -
Glaisnock Road Outside Cemetery £19,044.00  
To be programmed
Kilmarnock -
Dundonald Road Outside School £16,200.00  
To be programmed
Kilmarnock -
Gilmour Street Various Locations £21,060.00  
To be programmed
Stewarton - High
Street From Old Bank to Church £16,200.00  
To be programmed
Stewarton -
Lainshaw Street Standalane to Sainsbury’s Rear Entrance £19,260.00  
To be programmed
Fenwick - Skerniland
Road Both Sides £22,680.00  
To be programmed
Galston - A719
Opposite Loudoun
Academy From Nursing Home to Barriered Section £8,100.00 
To be programmed

Page 23

Official
£60,000.00
4
Carriageway - Kilmarnock - Anderson Place/Bannerman
Drive and Drummond Place
£46,200.00   Programmed to Commence
25/10/25
4 Carriageway - Kilmarnock Sparrow Gardens £12,960.00   Programmed to Commence
12/01/26
5 Carriageway - Kilmarnock Simonsburn Road £9,225.00   To be programmed
5 Carriageway - Kilmarnock Elderslie Crescent/Ayr Road £13,500.00   To be programmed
6 Carriageway - Newmilns Sheilds Road £28,050.00   To be programmed
6 Carriageway - Darvel West Donnington Street £16,800.00   Programmed to Commence
06/12/25
6 Carriageway - Darvel Jaimieson Road £17,400.00   Complete – final measure
7 Carriageway - Mauchline Clarinda Crescent £23,100.00   Programmed to Commence
08/09/25
7 Carriageway - Mauchline East Park Avenue £25,560.00   Programmed to Commence
08/09/25
7 Carriageway - Mauchline Southpark Avenue £7,800.00   Programmed to Commence
08/09/25
7 Carriageway - Mauchline Welton Road £19,950.00   Programmed to Commence
23/09/25
7 Carriageway - Mauchline Mansfield Road £43,500.00   Programmed to Commence
23/09/25
8 Carriageway - Cumnock Latta Crescent £20,010.00   Programmed to Commence
12/01/26
8 Carriageway - Cumnock Nans Terrace £16,500.00   Programmed to Commence
24/11/25
8 Carriageway - Cumnock Lorimer Crescent £44,550.00   Programmed to Commence
01/12/25
8 Carriageway - Cumnock Hearth Place £24,000.00   Programmed to Commence
08/12/25
8 Carriageway - Cumnock Bank Avenue £21,420.00   To be programmed
8 Carriageway - Logan Holmhead Crescent £36,600.00   To be programmed
8 Carriageway - Logan Dixton Avenue £21,690.00   To be programmed
9 Carriageway - New Cumnock Castlemains Avenue £42,000.00   To be programmed
9
Carriageway - Dalmellington Church Hill/Melling
Terrace £36,330.00   To be programmed
9 Carriageway - Dalmellington Knowehead £41,820.00   To be programmed
9 Carriageway - Ochiltree Gallowlee Avenue £20,490.00   To be programmed
4 Footway – Hurlford Furnace Court £15,750.00   To be programmed

Page 24

Official
6 Footway – Galston Bridge Street £3,750.00   To be programmed
6 Footway – Darvel Glen Crescent £17,500.00   To be programmed 
Ayrshire Roads Alliance - Lighting Capital Programme 2025/26 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Dalmellington Riecawr Ave, Area. Unreliable 5th Core. 22 £65,000 Completed
16 Jun 2025 
Galston Maxwood Road. Unreliable 5th
Core/Concrete columns. 10 £30,000 Completed
14 Jul 2025 
New Cumnock Highpark Ave, Area. Unreliable 5th
Core/Concrete columns. 19 £60,000 Started 
04 Aug 2025 
Stewarton Lothian Rd, Area. Unreliable 5th Core 23 £60,000   
£215,000 
Ayrshire Roads Alliance - LED Lighting Programme Update 2025/26 [Works carried over from 2024/25] 
Town Lantern
Amount Status Delivery /
start install
Install
complete by
Kilmarnock - Central 1400 In progress Mar 2024 Mar 2026
East Ayrshire - Decorative 350 75% complete 
tender to be awarded for next stage  Mar 2026 
Ayrshire Roads Alliance - LED Lighting Programme 2025/26 
Programme completed conversions to date 15,267 Replacement programme 97% complete
Overall LED units completed 20,910 LEDs now 98% of total EAC inventory

Page 25

Official
Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2025/26 
Structure
Reference
Structure Name Proposed Works 2025/26
Estimate
Comments
Bridge Strengthening and Replacement    
A71/280 C80 Mathews Burn Culvert
West Donnington St,
Darvel
Slab Replacement £250,000 Internal design ongoing.
U751/10 Crossflats Bridge Replacement £40,000 Awarded to consultant to design replacement.
Temporary bridge will be required during the works.
U760/00 C93 Glenhead Bridge Replacement £60,000 Internal design ongoing, near tender ready.
U740/10 Barbieston Bridge Replacement £60,000 SAC leading design. Award to consultant.
Road Slips  
B713 South of Sorn  £400,000 Works complete. Final measure being agreed.
B741 Coal Glen Embankment Slip Remediation Works £690,000 Discussions ongoing with SPEN. Works to be retendered
ASAP
U13 Aitket Road Slip Remediation Works £500,000 Site clearance complete. With procurement to be
tendered.
A713/60 C61 Polnessan Upper Bridge Culvert Extension £500,000 Detailed design ongoing. Near tender ready.
Upgrade Works Identified from Inspections  
B705/10 C91 Cowan Place Culvert Part Replacement/Scour
Repairs
£60,000 Near tender ready.
A70/130
W31
Thornwood Wall, Lugar Replacement £500,000 Near tender ready. Discussion regarding requirement for
road closure ongoing.
A736/60 C84 Lochridge Culvert Masonry and Drainage
Repairs
£70,000 Works ongoing. 
A71 Riccarton Viaduct Refurbish - expansion joint
removal/replacement
£100,000 Design ongoing to replace 1 failing expansion joint with
asphaltic plug joints. Works to be carried out ASAP.

Page 26

Official
A71 River Irvine Bridge Refurbish - expansion joint
removal/replacement 
Design ongoing to replace 1 failing expansion joint with
asphaltic plug joints. Works to be carried out ASAP.
C85/10 Fenwick Bridge Masonry Refurbishment £40,000 Award to consultant to progress with assessment and
detailed design.
U729/00 C64 Hayholm Bridge Masonry and Scour Repairs £60,000 Internal design ongoing.
C95/10 Furnace Road Bridge Arch Strengthening £100,000 Awaiting PI report from consultant. Internal design
ongoing.
Parapet Upgrades  
A70/110 Causeyhead Bridge Parapet Repairs £60,000 Discussions ongoing regarding options to reduce
disruption at Dumfries House.
A736/50 Bloak Road Bridge Parapet Repairs £30,000 NAC/EAC boundary, EAC progressing design.
Other  
Various Investigative Works Topographical Survey, Paint
Inspection etc
£8,000 Annual cost of surveys/inspections. 
Principal Inspection Consultant Fees £100,000 Consultant fees for 24/25 PI’s
Various Low Bridge Signage  Sign Upgrades £40,000 Upgrades to signage at 6 bridges with low head room.
Contract awarded. 
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26
Funding Source Project
ID
Location Project Description Detail Progress Allocation
EAC Capital Road Safety
Budget: £200,000
(£198,000 Road Safety +
£2,000 Safer Neigh.)
22.23 A71 / Campbell Street
Off Slip, Kilmarnock
Junction
signalisation
Installation of new
traffic signals, stopping
up of Willock Street
and new carriageway
layout to improve
capacity
Final junction
designs from
traffic lights
contractor still
pending.  Works
planned to start
January 2026
£105,000

Page 27

Official
22.50 B741 Dalmellington to
New Cumnock
Road safety
review
General route review
to identify safety
measures
Driven survey
along rural
section to be
completed.
Ongoing. 
£2,000
22.38 Glaisnock Street,
Cumnock
Traffic calming Speed
reduction/traffic
calming measures
Design works
started - Late
25/26 for
completion
£15,000
22.15 VAS signs, various
location
Upgrades and
new installations
New contract to be
implemented
In progress £10,000
25.20 A713 - Waterside  Road safety
improvements
40mph repeaters, HFS
gateway features and
road markings upgrade
October 25 £25,000
24.05 Various Traffic calming Speed surveys Ongoing £10,000
25.03
/
25.16
Various Road safety
improvements
HFS Schemes Ongoing £33,000 
24.20 B751 - Kilmaurs to Fenwick  Route Review General route review,
VAS improvements,
Road Markings and
Signage, Studs
Ongoing design
works with
Construction
expected Sept 25
£125,000
25.11 A71 – Priestland Safer system
improvements
Vehicle restraint
barriers
Design work
ongoing with
Construction
expected early 26
£75,000
25.13 A719 – Waterside Road Safety
improvements
VAS improvements ,
HFS and carriageway
studs
Design work
ongoing with
Construction
expected early 26
£50,000
25.17 A70 – Dumfries House Road Safety
improvements
VAS improvements ,
HFS, carriageway studs
and resurfacing
Design work
ongoing with
Construction
expected early 26
£50,000
Rural Route Action Plans
Budget: £359,000
£134,000 (EAC) + £225,000
(Dev. Contributions)
22.08 B778 Stewarton to
Fenwick
Road alignment
improvements at
three key
locations
Agreement to proceed
with site 1
improvements
Process started £359,000

Page 28

Official
Tier 1
Budget: £758,000 
22.13 Grougar Road,
Crookedholm
Pedestrian
crossing and road
widening
Installation of new
crossing and layby
Works started
with planned
completion late
August 2025 
£90,000
23.07 Strawberrybank Road,
Kilmarnock
Pedestrian
crossing
Appraisal for new
crossing point
Ped counts low
so project
reduced to
consideration of
ped refuge island 
£10,000
23.10 St Germain Street,
Catrine
Pedestrian safety
improvements
Installation of bollards
and TRO 
Works complete
with TRO to be
finalised 
£10,000
N/A Kilmarnock Green
Infinity Loop
Cycling
Infrastructure
Route 1 & 2, Sturrock
St and MSCP
Route 1 & 2
design placed on
hold due to lack
of funding, MSCP
site
redevelopment
application
submitted to
ATIF 2025/26.
Sturrock St
modelling
completed. 
£100,000
24.18 A759 West of
Gatehead
Pedestrian
improvements
Footway designs and
build out
Design work
ongoing with
Construction
expected early 26 
£30,000
25.15 B751 Kilmaurs to
Knockentiber
Pedestrian
improvements
Footway
improvements
Design work
ongoing with
Construction
expected early 26 
£30,000
24.28 Kilmarnock Pedestrian
improvements
Footway designs and
buildouts
Onsite
consultation to
£30,000

Page 29

Official 
be completed
prior to design
work with
Construction
expected early 26 
23.12 A713 Bellsbank Rd,
Dalmellington
Traffic calming 1 x speed table Construction
expected June 25 
£10,000
25.12 A71 Priestland Traffic Calming and
pedestrian crossing
Design work
ongoing with
Construction
expected early 26 
£50,000 
Irvine Road Kilmaurs Pedestrian
improvements
Design work
ongoing with
Construction
expected late 25
£35,000 
Various location Various To be Confirmed  £363,000
EAC Bus Infrastructure
Budget: £645,000
22.51 Onthank Terminus,
Kilmarnock
Upgrades to
existing
infrastructure
Improve crossing and
boarding points
Drawings
complete to be
paired with
Stewarton
Terminus 
£20,000
22.52 Stewarton Terminus,
Stewarton
Upgrades to
existing
infrastructure
Improve turning circle
and boarding points
Design stage in
progress
£20,000
EAC Active Travel
Budget £50,000
24.03 School Streets
Programme
Introduction of
trial sites
Three further schools
to be trialled with
further trials to be
developed
Live trials have
commenced at
Bellsbank and
Dalrymple.
Auchinleck in
development.
Further sites to
be determined
following
completion of
trial sites.
£50,000

Page 30

Official
Appendix 3 
Ayrshire Roads Alliance - EV Public Chargers 
EAST AYRSHIRE 
CPS ID Type Make Location
51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
50821 22kw eVolt Foregate Noth Car Park, Kilmarnock, KA1 1LU
51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH
52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW
70279 Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP
60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR
52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU
52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE

Page 31

Official
52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG
52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS
52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB
52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ
52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB
52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY
53778 Rapid eVolt Main Street Car Park, Muirkirk
53775 22kw eVolt Rose Reilly Sports Centre, Stewarton
53776 7kw eVolt Standalane Car Park, Stewarton
60786 7kW eVolt Academy Street, Hurlford
60792 22kW eVolt Drongan Centre car park, Mill of Shield Road
51210 22kW eVolt Carnshalloch Avenue car park, Patna
60950 22kW eVolt New Cumnock Outdoor Swimming Pool car park
60954 22kW eVolt Gatehead Road car park, Crosshouse
61021 7kW eVolt East Ayrshire Community Hospital, Cumnock
61022 7kW eVolt East Ayrshire Community Hospital, Cumnock
61983 7kW eVolt Morton Place car park, Kilmarnock
61984 7kW eVolt Morton Place car park, Kilmarnock

Page 32

Official
61985 7kW eVolt Morton Place car park, Kilmarnock
62184 7kW eVolt Browns Road car park, Newmilns
61886 22kW eVolt Sturrock Street, Kilmarnock
62938 7kW eVolt New London Road car park, Kilmarnock
SOUTH AYRSHIRE
CPS ID Type Make Location
51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW
51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU
70278 Rapid eVolt Burns Statue Square, Ayr, KA7 UT
52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN
52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY
50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ
50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF
52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG
70280 Rapid eVolt Girvan Harbour, Girvan, KA26 9AG
52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR
52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH
52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU
52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL
53774 Rapid eVolt Academy Street, Troon
53773 Rapid eVolt Lodge Road Car Park, Turnberry
53777 22kw eVolt Burnside Road, Monkton

Page 33

Official
60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly
60081 22kw eVolt Inches Close car park, Maybole
61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton
61986 22kw eVolt Dundonald Primary School car park, Dundonald
60086 22kw eVolt Mossblown Activity Centre car park, Mossblown
60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald
61979 7kW eVolt Chalmers Arcade car park, Girvan
61980 7kW eVolt Chalmers Arcade car park, Girvan
61981 7kW eVolt Chalmers Arcade car park, Girvan
62000 22kW eVolt Barrhill Community car park, Main Street, Barrhill

Page 34

Official
Appendix 4 South Ayrshire Ward Investment and Promenade Programme for 2025/26 incl. works carried over from 2024/25 
Roads Maintenance Unit
LOCATION Description PO Value  Cost to Date variance +/- Comment
Troon Resurfacing of Troon Esplanade (Ph.3).   
Measuring works on site
Prestwick Repair / renew steps to Boydfield Gardens £85,000.00   Complete – Final measure
Prestwick Install power supply to Boydfield Gardens and Links Road   
Scottish Power quote to
be received.  Followed by
agreed site start date 
Ayr North Provision of Bike Shelter at Lochside Community Centre £15,000.00   Bike shelter currently
being fabricated
Ayr East Glencairn Park – footpath upgrade    Quote issued for approval
Ayr East Car parking provision Peggieshill Road    Quote provided,
consultation required
Ayr West  Promenade raised footway works   
Feasibility study ongoing
with Professional Design
Services 
Kyle Install a History Park at Loans Community Hall and link to
Smugglers trail   
Car park quote issued for
approval.  Garden and
block paving quote being
prepared 
Kyle  Improve accessibility at Mossblown village hall      Quote issued for approval
Kyle Link path from Collins Drive to Collenan Avenue, Loans    Quote provided,
consultation required
Kyle Resurface Bowling Green Car Park, Symington    Quote provided, currently
being assessed
Kyle Construct new footpath at southern edge of Collenan
Reservoir   
On Hold.  Scope of works
changed
Design and Flooding Section
Troon  Shore Defence Structural Stabilisation £10,000.00 £15,432.00 -£5,432.00 Complete 
Citadel Footbridge
Refurbishment
Remove and renew timber deck parapet elements. 
Surface prepare and paint.  Remove or repair lighting £140,000.00 £259,957.00  -£119,957.00  Complete

Page 35

Official 
Appendix 5 Ash dieback East Ayrshire and South Ayrshire 2025/26 
2024 High Risk
Works_EAC Highway
2024 High Risk
Works_SAC Highway 
Girvan Boating Pond
Refurbishment 
Install new stainless steel reinforced concrete base slab to
reduce water leakage. £175,000.00 £170,641.00  £4,359.00  Complete 
Dunure Castle
Footbridge
Replacement 
Replace existing small span concrete footbridge with a
larger footbridge with a view and good aesthetics    £230,000.00  Ongoing.
Lighting Section
Ayr East  Glencairn Park – Install footpath lighting £23,000.00   Design complete.  Tender
issued
Ayr West  Replacement of column lighting on Ayr Promenade £145,000.00  
Column and street
lighting works complete
and operational. 
Additional works to install
public Wi-Fi ongoing
Ayr West New Bridge & Auld Brig.  Design fees for installation of
architectural floodlighting to structures £50,000.00  
Exploring other means to
procure Consultant as
delay with SXL Technical
& Consultancy
Framework 
Ayr West  Wrap round decorative lighting to columns on Ayr
Promenade   
SAC PO to be issued