Roadworks Programme
North Ayrshire Council · 5 September 2025
Back to Ayrshire Shared Services Committee — 5 September 2025 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
Official AYRSHIRE SHARED SERVICE JOINT COMMITTEE 05 September 2025 Report by the Head of Ayrshire Roads Alliance ______________________________________________________________ SUBJECT: ROADWORKS PROGRAMME 2025/26 ______________________________________________________________ Purpose of report 1. The purpose of this report is to advise the Joint Committee on the progress of work through the road improvement programmes within East Ayrshire and South Ayrshire for financial year 2025 to 2026. Recommendations 2. It is recommended that Joint Committee: (i) Notes, the Ayrshire Roads Alliance programmed works 2025/26 (ii) Otherwise, notes the contents of this Report. Background 3. The budget allocation for East and South Ayrshire Councils Roads Investment Programme for FY 2025/26 can be seen in tables 1 and 2 below respectively. Table 1: East Ayrshire Council Roads Investment Programme 2025/26 Programme Area Budget (£m) Carriageway Resurfacing 2.081 Footway Resurfacing 0.084 Street Lighting 0.215 Traffic & Transportation incl. road safety 0.330 Active Travel 0.050 School Streets 0.050 Bridge and Culvert Strengthening (incl. road slips) 3.500 Car Parks incl. Multi-storey demolition 0.820 Fleet 0.600 Total £7.730 External Funding (Confirmed) SPT – Behaviour Change £0.385 Transport Scotland – Behaviour Change £0.116 ATIF - Tier 1 £0.758 Developer Contributions/Route Action Plans £0.359 Bus Infrastructure Fund – Tier 1 £0.645 SG – EV Infrastructure Fund £2.800
Page 2
Official Total £ 5.063 External Funding (To be Confirmed) Sustrans – Annick Valley Stage 2 £0.165 (Award letter to be issued) ATIF Tier 2 - Design £2.405 (Tbc.) Road Safety Improvement Fund £0.300 (Tbc) Total £2.870 (Tbc.) Table 2: South Ayrshire Council Roads Investment Programme 2025/26 Programme Area Budget (£m) Carriageway & Footway Resurfacing 1.581 Street Lighting 0.150 Bridges Capital 0.881 Millennium and Craigholm Bridges 0.145 C12 Dunure slope stabilisation 0.130 Vehicle restraint barriers 0.073 Cattle grid renewal 0.033 Girvan Harbour Jetty repairs 0.504 Local Flood Risk Plan 0.153 Ayr Depot 0.250 Climate Changes St Ninians Park 0.255 EV Charging Infrastructure 0.281 Total £4.436 External Funding (Confirmed) SPT – Behaviour Change £0.170 Transport Scotland £0.116 Tier 1 – Active Travel Funding £0.737 ATIF–Tier 2(Dundonald – Barassie) £2.700 Ayrshire Growth Deal £0.857 Levelling Up Fund (Active Travel) £4.000 Levelling Up Fund (Burns Statue) £15.000 Bus Infrastructure Fund – Tier 1 £0.382 Total £23.962 External Funding (To be Confirmed) Sustrans £0.753 (Award letter to be issued) ATIF Tier 2 - Design £1.626 (Tbc.) Road Safety Improvement Fund £0.270 (Tbc.) Total £2.649 (Tbc.) Note: Several funding applications have still to be confirmed. The affected areas of potential funding are denoted by the use of “£Tbc.” in Tables 1 and 2 above. Main report/main issues 4. Surfacing programmes for FY 2025/26 are contained within Appendices 1 and 2.
Page 3
Official Capital Resurfacing 5. Due to carcinogenic properties in Coal Tar, additional control measures are in place which requires coal tar testing to be undertaken before the commencement of works. 6. The requirement for a new coring contract has meant that the start date for some of our resurfacing sites has been delayed until the sites can be tested when the coring contract is awarded in September. 7. The Capital budget for both authority areas is committed and it is anticipated remaining surfacing works will commence late November. Depending on weather conditions during the winter months there is a possibility that some works may require to be carried over into financial year 2026/27. 8. In South Ayrshire we have completed 40% of the carriageway programme with an anticipated completion date of March 2026. The footway resurfacing programme commences in September 2025 with an anticipated completion date of November 2025 with some sites identified for surfacing being carried over into financial year 2026/27 as detailed in appendix 1. 9. Due to the delay with the Coring Contract, there is a risk resurfacing works may not be completed as planned during December to March 2026, owing to potential unsuitable winter weather conditions. As an alternative in South Ayrshire we are proposing to carry out overlay works on sites which do not require planing and associated coal tar disposal prior to winter. These sites could potentially be surface dressed in the future. It is therefore proposed that 6 resurfacing sites be carried forward into 26/27 programme to ensure works are completed under more favourable conditions. 10. In East Ayrshire 11% of the carriageway resurfacing programme has been completed as detailed in appendix 2 11. During a more detailed inspection undertaken on the A71, Kilmarnock from Moorfield Roundabout to the North Ayrshire Boundary, it was discovered the condition of the carriageway surface was worse than initially anticipated and the engineering decision was made to allocate a further £400k+ towards this project thus allowing the full length to be completely resurfaced with new road markings and cats eyes being installed. King Street Fire – Kilmarnock Town Centre 12. At around 21:00 hrs on the evening of Monday 14th July a huge fire took hold of a property in King Street with the first 48 hours, the scene was under the direct control of Police Scotland and Scottish Fire and Rescue. Ayrshire Roads Alliance under the direction of the police incident commander coordinated road closures and diversions around the scene and arranged for heras fencing to secure the site.
Page 4
Official 13. Ayrshire Local Resilience Partnership (ALRP) was activated followed by a coordinated response to the immediate aftermath and recovery phase demonstrating the strength of partnership working between our blue light emergency services, East Ayrshire Council, Ayrshire Roads Alliance and Utility Companies. The President and Vice President of the United States visit to Ayrshire 14. Adopting a “Gold, Silver & Bronze” Command and Control structure chaired by Police Scotland, East Ayrshire, South Ayrshire & Ayrshire Roads Alliance in partnership with all agencies including the US Secret Service supported the policing operation around the Presidential visit on 25th until 31st July.25 and shortly thereafter also accommodated the Vice President visit on 13th August until 17th August.25. East Ayrshire Council residential road and footway repairs (Additional Revenue Funding) 15. At Cabinet on 13 March 2025, East Ayrshire Members Initiatives approved £800k revenue funding for residential and footway repairs with locations identified detailed within Appendix 2 of this report with 13% complete to date. South Ayrshire Council Ward Investment and Promenade Programme 2025/26 16. Officers within our engineering disciplines continue to develop work schemes identified by Ward Members under the South Ayrshire Council Ward Investment Programme for 2025/26 as detailed within Appendix 4 of the report. Sites will be further added as discussions progress with Officers and Ward Members. Timber Transport 17. As reported at the last joint committee in June 2025 neither authority area was successful in their bids for grant funding from the Timber Transport Fund. 18. Officers are committed to reviewing our application process and an early meeting will be arranged with the Timber Transport Consortium when the window opens for 2026/27 applications. Street Lighting 19. The Scotland Excel Street Lighting Material Framework has still not been issued and this is hampering the completion of the LED project in the East. This has been ongoing for 3 years and with assistance from our Procurement colleagues after exploring alternative options we have recently issued a tender via the YPO ‘Highway Electrical Installations’ procurement framework for the supply of street lighting materials and sundry electrical items. 20. The Street lighting column and cable replacement programme of works which incorporates LED lanterns is detailed in Appendix 1 and 2.
Page 5
Official Electric Vehicle Infrastructure 21. The Electric Vehicle Infrastructure Fund (EVIF) programme with the number of public chargers installed to date is listed within Appendix 3 for South and East Ayrshire respectively. 22. East Ayrshire Council is the lead authority for the PAN Ayrshire Public Electric Vehicle Charging Strategy. The project has secured a grant of £2.8million and work continues on the procurement phase. Following the previously approved business case, further papers have been presented to the cabinet regarding the introduction of an EV charging tariff, which has been implemented across all three Ayrshires as of 1st January 2025. A further increase to tariff was implemented on 1st July 2025. This tariff aims to establish a sustainable funding model and attract private investment. 23. Work continues on the tender documentation for the Pan Ayrshire concession contract with the appointment of Mott MacDonald as consultants to assist with the collation of the relevant documents required for tender. The Single Procurement Document (SPD) was issued on 3rd March 2025 for the initial stage of tendering, followed which we received numerous bids. The second part of the tendering process is currently ongoing, with the Invitation to Tender (ITT) to be published in September 2025 for the shortlisted bidders, followed by contract award in January 2026. 24. Under the Public Charge point regulations 2023 legislation all Rapid Chargers are required to be able to accept contactless payment by 24th November 2024. Ayrshire Roads Alliance has secured funding from Transport Scotland Contactless Compliance Grant Funding to replace/activate/retrofit eligible CPS rapid chargers to incorporate contactless payment. Works have been carried out to replace the non-compatible units and to activate contactless terminals on compatible rapid chargers. 25. Replacement of 22kW charger at Troon Swimming Pool will be funded from SAC Capital budget but is on hold until the concession Contract is awarded in December 2025. 26. Replacement of 50kW chargers at Burns Statue Square, Ayr and Girvan Harbour have been replaced and commissioned. Structures 27. Land acquisition and/or access agreements alongside environmental license requirements continue to cause delays to a number of projects. ARA are working closely with EAC Legal/Estates and relevant stakeholders to progress these issues. 28. Appendix 2 details East Ayrshire Council Bridges Capital programme for 2025/26.
Page 6
Official 29. A713 Polnessan Upper Bridge - ARA have erected temporary traffic signals due to subsidence in the carriageway. Traffic lights will remain in place until the slope has been stabilised. Project is near tender ready. 30. B741 Coal Glen Embankments works to be retendered following discussion with SPEN regarding utilities in the vicinity of the works. 31. A735 Lochridge Culvert - general culvert repair works ongoing. Scope of work increased on site due to poor ground conditions. 32. ARA are working with EAC Legal/Estates to acquire land at West Clerkland Bridge through a Compulsory Purchase Order. The bridge has been shut to vehicular traffic since 2012 and shut to both pedestrians and vehicular traffic since 2021. 33. 3no. bridges on the A71 between the Bellfield Interchange and Moorfield Roundabout need replacement expansion joints. A consultant was appointed to explore options in removing the joints and making the structures semi/fully integral. It has been decided that in the meantime 2 joints that are repeatedly failing will be replaced with asphaltic plug joints. 34. B730/10 Littlemill Bridge - land acquisition complete after years of negotiation. Tender documents to be reviewed and works tendered with a view to start on site in Spring 26. 35. Contract awarded for low bridge sign upgrades at 5 structures in Kilmarnock and Kilmaurs. 36. South Pier Quay at Girvan Harbour – tenders for steel plate repairs to the existing sheet piles and grouting is anticipated to be issued in August/September with works completed by the end of 2025. 37. The detailed design of the Girvan Harbour Timber Jetty works are progressing with the Contract documentation substantially complete. The Tender will be issued once the South Pier Quay tenders have been returned and costs known. 38. The A79/30 Victoria Bridge Concrete Repairs and Painting has been completed. 39. The Contract Documentation for Girvan Harbour dredging and land based material disposal has been finalised and are with Procurement for Tender issue. 40. Ayr South Pier - as previously reported at the last Shared Service Joint Committee in June 2025, funding to employ a consultant to carry out an underwater dive survey and structural assessment has not been secured. This is a matter of concern as the importance of a dive survey and assessment was highlighted following the development of a sink hole in a verge area at the end of the South Pier.
Page 7
Official Traffic & Transportation 41. Active Travel Infrastructure Fund (ATIF) Tier 1 grant funding for both autjority areas has been received from Transport Scotland. Active Travel projects using the Tier 1 funding is currently in development, and will be implemented over the course of the current financial year. 42. Grant awards have been confirmed from Transport Scotland for both EAC (£645,000) and SAC (£382,000) from the Bus Infrastructure Fund – Tier 1. This unforeseen funding is directly awarded and paid to local authorities as part of the General Capital Block Grant (GCBG) Allocation. ARA are currently developing delivery programmes for both EAC and SAC areas and reports will be presented to both Cabinets with proposed programmes of work for review and approval. 43. Confirmation of the Road Safety Improvement Fund grant allocations is pending for both authority areas. Schemes are currently being identified and prioritised as listed in the appendices but may be subject to change pending Transport Scotland approval. 44. Kilmarnock Bus Station refurbishment programme is now complete with Officers currently reviewing the cleaning regime. 45. The Contract for Cumnock Bus Station which include changes to materials and the installation of a public address system is currently being prepared. Ayrshire Growth Deal (AGD) Roads Projects 46. A Case for Change seeking approval of the changes to the Roads Infrastructure project and also the Prestwick Proposition has now been approved by Scottish & UK Governments. Ayrshire Roads Alliance will assist in the delivery of all these projects for South Ayrshire Council. 47. A Planning application for the construction of a new car park at Shaw Road, Prestwick will be submitted in September 2025, this is a significant step forward in the delivery of the AGD. 48. Extensive ground investigations and environmental studies are currently being undertaken on the remaining phases of the AGD in an attempt to accelerate the design process and move more projects through to construction. Levelling Up Fund 49. South Ayrshire Council successfully secured £20million of funding from the Levelling Up Fund (LUF) round 3.£15million of this funding has been transferred to ARA and will be utilised to redevelop Burns Statue Square. Balfour Beatty have been appointed as the principle contractor, design is currently underway and a delivery programme will be produced in the coming weeks. 50. £1.2million of the LUF funding along with a £2.7million award from ATIF will be used to construct a new Active Travel Route linking Dundonald to Barassie
Page 8
Official Station, work is currently underway on this route and is scheduled to be complete by 31st March 2026. 51. The remaining £2.8million along with funding from the AGD & a bid to the ATIF in January 2026 will be utilised to carry out significant improvements to the NCN7 from Prestwick to Barassie railway stations. Work will commence on-site late 2025 and will be complete by 31st March 2027. Active Travel 52. The Active Travel Infrastructure Fund (ATIF) administered by Transport Scotland has awarded £2.7million towards the construction of the Dundonald to Barassie route. 53. ARA submitted several funding applications to Sustrans in January 2025 to carry out the next stages of the design process for several active travel routes across both South and East Ayrshire Council, it has now been confirmed that Sustrans will not receive funding from Transport Scotland as had originally been advised and these applications have now been transferred to ATIF. No decision has been taken on these application at this time. Ash Dieback & Other Species 54. Appendix 5 of the report details the current condition data on all High Risk roadside trees for both authority areas. Surveys and programmed works for removal are ongoing with 28-day notices being issued to owners and any objections received referred to legal service. Implications 55. Implications Yes No Paragraph number in report 1. Policy/Strategic Planning x 56 & 57 2. Governance x 58 3. Human Resources x 59 4. Equality and Fairer Scotland Duty x 60 5. Financial x 3, 61 & Appendix 1, 2 and 4 6. Risk x 62 & 63 7. Community Wealth Building x 64 8. Net Zero x 65
Page 9
Official Policy/strategic planning implications 56. A well-maintained road network will contribute to achieving the 2015-2030 Community Plan objectives and associated 2021-2024 Delivery Plans 57. The matters referred to in this report contribute to Priority 1 of the South Ayrshire Council Plan: Spaces and Places/ Moving around and the environment (Outcome 1). Governance implications 58. By virtue of the relevant statutory provisions, principally detailed within the Roads (Scotland) Act 1984, the Council as local roads authority is required to manage and maintain all publicly adopted roads within its area other than those which are maintained and managed by the Scottish Ministers. Human resources implications 59. The work programmes have direct impact on human resources and the Alliance will ensure all works are suitably resourced to maintain satisfactory progress. Equality impact and Fairer Scotland duty implications 60. Equality Impact and Fairer Scotland Duty screening assessments will be undertaken annually as required during the planning stage prior to the delivery of the programme of works. Financial implications 61. The Ayrshire Roads Alliance will deliver the strategic and local services as stated in the Service Plan. The budget is provided by East Ayrshire Council, South Ayrshire Council, and other external organisations. Appropriate scrutiny arrangements are in place to manage these budgets. Risk implications 62. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every Joint Committee. 63. The Works Programmes, Service Plan and the Risk Register do not expose either Council to an increased risk as they have been developed from existing budgets and existing service commitment. Community Wealth Building implications 64. The works programme provides economic levers to develop resilient, inclusive local economies with more local spend and fair employment, as well as ensuring that wealth is more locally owned and benefits local people.
Page 10
Official Net zero implications 65. The Ayrshire Roads Alliance Service Plan and Carbon Strategy supports and links to East Ayrshire Climate Strategy Themes Theme 2: Transport Theme 4: Natural Environment Appendices Appendix 1 - South Ayrshire Council Programme of Works 2024/26 Appendix 2 - East Ayrshire Council Programme of Works 2025/26 Appendix 3 – EV Public Chargers Appendix 4 - South Ayrshire Council Ward Investment and Promenade Programme 2025/26 Appendix 5 – Ash Dieback Condition reports EAC & SAC Background papers • East Ayrshire Council – 2025/26 Road Asset Management Plan. Investment and Programme • South Ayrshire Council – Road Improvement Plan 2025 - 2026 Person to contact. Jane Corrie, Head of Roads - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail. jane.corrie@ayrshireroadsalliance.org Implementation Officer Craig Knape, Strategic Manager - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail. craig.knape@ayrshireroadsalliance.org
Page 11
Official Appendix 1 South Ayrshire Council – Programme of Works 2024/26 Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2024 to 2026 Route No Town Road Name Works Description Scheme Score Estimate d Cost Cost to Date Variance +/- Comments B734 Old Dailly Barr Old Dailly Old Dailly to Penkill + drainage improvements N/A £150,813 £163,932 -£13,119 Complete B7035 By Girvan Glendoune Houdston Road (Coalpots) Braetoll South + S Power shut down N/A £200,000 £206,251 -£6,251 Complete B743 By Mossblown Ayr / Mossblown? West from Brocklehill Farm 53 £249,002 £249,239 -£237 Complete C37 Auchincruive Barrackhall Gibbsyard 48 £123,861 123,873 -£12 Complete Uncl Tarbolton Springfield Road Garden Street to No 50 46 £54,275 £53,851 +£424 Complete B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton By Holebogs, S bend 59 £445,000 £440,506 +£4,494 Complete B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton From A70 at Hillhead south to C21 Craigs Road junction 56 B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton From Meadowhead Depot entrance south-wards 55 Complete B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton Bridge of Coyle to C2 52 B744 Annbank Weston Brae Full Length 53 £152,000 £207,822 -£55,822 Complete B744 Annbank Browns Crescent Weston Avenue Full Length Craighall Way to 101 Weston Avenue 53 56 U77 By Coylton Hole Road Full Length 46 £82,867 £83,064 -£197 Complete B7023 Maybole Crosshill Road Full Length 56 £74,687 £72,215 +£2,472 Complete Complete Complete B7023 Maybole St Cuthbert's Road Full Length 53 £30,669 £41,792 -£11,123 B7024 Maybole Alloway Road Redbrae to Bypass 51 £55,922 £96,288 -£40,366 C122 By Maybole C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole School to new Bypass 50 £58,095 £58,097 -£2 Complete
Page 12
Official C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole Ladycross to new Bypass B7023 Maybole Ballochbroe to Crosshill Dalhowan to C58 £275,435 £362,350 -£86,915 Complete A719 PH 2 By Maidens By Dunure Pennyglen/B7023 - Kirkoswald Road/Maidens, Maidens A719 Smithy Bridge/Dunure - Croy Brae, Dunure B7023 Enoch Lodge -Caravan Park Cemetery to Drumshang 67 £281,669 £326,746 -£45,077 Complete Complete A719 PH 1 By Maidens Pennyglen/B7023 - Kirkoswald Rd & Turnberry Rd /Maidens, Turnberry Morriston Farm to Jct Blawearie Maidens to Turnberry 56 £441,666 £540,857 -£99,191 Uncl Maybole Ashgrove Avenue Full Length £88,954 £102,985 -£14,031 Complete Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – New Sites identified for 2024 to 2026 B749 Troon Monktonhill Road Southwood jct to Isle of Pin 59 £210,000 £265,328 -£55,328 Complete. after excavation, additional material was required to regulate due to sand & soft spots localised to lots of areas in Troon B749 Troon Craigend Road Fullarton Drive railway bridge to South Beach 48 £167,500 £201,706 -£34,206 Complete Overspend same as Monktonhill Rd B749 Troon South Beach Lochend Road to Academy Street jct 54 £200,000 £307,540 -£107,540 Complete. Overspend same as Monktonhill and Craigend.
Page 13
Official C44 Dailly Dailly to Turnberry Farden 500m towards Drummock 39 £112,560 £71,137 +£41,422 Complete B7027 Barr Knowe Road Lochtonmill southwards £63,000 £53,406.44 +£9,593 Complete B734 Colmonell Colmonell to the A77 £106,560 £150,273 -£43,713 Complete B7023 Maybole C58 to Cemetary £297,606 £271,503 +£26,102 Complete A70 C39 Coylton Ayr Joppa Doonholm Road Hole Road jct to Pharmacy Alloway to The Loaning 35 43 £179,321 £155,377 +£23,944 Complete C145 Ayr Hillfoot Road Holmston Rd to Holmston Dr 54 £91,875 £123,733 -£31,858 Complete Uncl Maybole Queens Terrace/Chesney Grove/Kincraig Avenue Full Road 33 33 £166,275 £174,448 -£8,173 Complete Uncl Maybole Cargill Road Full Road 47 £46,900 £48,224 -£1,324 Complete C1 (STTS) Straiton Newton Stewart Road U8 towards Straiton to U57 44 £120,400 £119.293 +£1,107 Complete B7045 (STTS) Maybole Cassilis to Kirkmichael Rd Crorieshill Farm northwards for 360m 44 £46,750 £51,700 -£4,950 Complete Uncl Ayr Saltpans Road North from Glebe Road 46 £112,249 £118,940 -£6,691 Complete Uncl Prestwick Morris Road Full Road 43 £55,000 £107,345 -£52,345 Complete (presence of coal tar increased costs) Uncl Ayr Green Street Waggon Road to Crown Street 42 £130,000 £214,584 -£84,584 Complete (presence of coal tar increased costs) Uncl Prestwick Craigie Street Full length 39 £30,000 £36,725 -£6,725 Complete B744 By Annbank B744 Belston/A70 - Weston Avenue/Annbank, Ayr Auchincruive Junction to Glenview 52 £120,000 £139,872 -£19,872 Complete B742 By Maybole Dalrymple to Barnford Farm Dalrymple Road 46 £130,000 £138,058 -£8,058 Complete
Page 14
Official Uncl Maybole Hicks Avenue Full cway & fway 30 £104,000 £133,263 -£29,263 Complete Increased costs due to combining footway, kerbing C59 Colmonell Craigneil Road B734 to Bridge £67,000 £53,129 +£13,871 Complete Uncl Ayr Peggieshill (PH1) Dalmilling Rd to Nursery Rd 44 £92,000 £99,038 -£7,038 Complete Uncl Ayr Kincaidston (PH1) Marigold Sq to Honeysuckle Park 52 £185,000 £181,768 +£3,232 Complete Uncl Girvan Louisa Drive Knockcushion St to Duncan St £103,640 £91,410 +£12,230 Complete Uncl Ayr Peggieshill Rd (PH2) Nursery Rd to Fenwickland Ave 44 £100,000 £81,228 +18,772 Complete C74 By Ayr MacNairston Rd C105 to B742 junction 52 £97,608 £112,326 -£14,718 Complete B742 By Maybole Nether Culzean Dalrymple Rd Barnford farm to Nether Culzean 42 £135,000 £130,022 +£4,978 Complete Uncl Ayr Ellisland Square (Contains Coal Tar) Full Length 42 £125,000 £85,289 +£39,710.80 Complete – final measure Uncl Ayr Kincaidston Drive (PH2) Honeysuckle Park to Dalmellington Rd 52 £100,000 £51,730 +£48,270 Complete – final measure B742 Mossblown Sandyford Road From a point 180 metres east of A719 junction eastwards for 680m 53 £140,700 £169,432 -£28,732 Complete Uncl Ayr Dalmilling Road (Contains Coal Tar) Harthall to Mainholm Rd 37 £275,000 £37,032.78 +£212,967.22 Complete – final measure Uncl Prestwick Bellevue Road (TO BE TESTED) From Main Street to Adamton Road £38,039 c/f to 2026/27 TBC Uncl Girvan Todd Street (TO BE TESTED) Full length 31 £32,894 c/f to 2026/27 TBC Uncl Girvan Fauldribbon Road (TO BE TESTED) Full length 34 £31,813 c/f to 2026/27 TBC Uncl Girvan B741 Linfern Road (TO BE TESTED) NO.79 to no.3 near Main Street 29 £100,517 Programmed to Commence 26/01/26 Uncl Maybole Carrick Street (TO BE TESTED) Ladyland Rd to B77 33 £26,130 c/f to 2026/27 TBC Uncl Maybole Wellington Street (TO BE TESTED) Ladyland Rd to Carrick St 30 £18,090 c/f to 2026/27 TBC Uncl Maybole Manse Street (TO BE TESTED) Drumellan St to Abbott St £20,100 c/f to 2026/27 TBC
Page 15
Official Uncl Girvan Hamilton Street (TO BE TESTED) Church Sq to Bridge St 46 £49,655.55 Programmed to Commence 09/02/26 Uncl Ayr Chapel Park Road Full length 40 £55,984 2026/27 Uncl Prestwick St Cuthbert’s Rd St Andrew’s Ave to Kirklandholm £38,587 2026/27 Ayrshire Roads Alliance – Overlay surfacing (potential future surface dressing) U39 Dailly Hawkhill Road Old Dailly from number 1 to number 12 N/A £125,000 TBC Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2024 to 2026 C17 Tarbolton Westport Footway North side 28 £17,370 £24,984 -£7,644 Complete Uncl Prestwick Hunters Avenue South from Heathfield Road, west side 23 £7,500 £5,393 +£2,107 Complete Uncl Troon Morven Drive Cessnock Rd to Dundonald Rd (Northside) £15,072 £28,820 -£13,748 Complete C151 Dailly Woodside Both sides from Back St and Hadyard Terr 30 £20,400 £17,147 +£3,253 Complete Uncl Crosshill Newton Street Church Side of road 30 £15,795 £14,440 +£1,355 Complete Uncl Dailly Hadyard Terrace Inside footway + part outer section 28 £54,400 £20,110 +£34,290 Complete Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for 2024 to 2026 Uncl Mossblown Martin Avenue Mossblown 28 £28,300 £30,829 -£2,529 Complete B744 Annbank Weston Brae Full Length 28 £10,700 £5,761 +£4,939 Complete B730 Dundonald Drybridge Road Bowling Green to Kilnford Dr 28 £19,223 Works progressing on site Uncl Ayr Bellevue Crescent Full Length 34 £37,800 TBC - tree inspection, scope of work to be determined
Page 16
Official Uncl Maidens Ardlochan Road Full Length 30 £21,000 Programmed to Commence 24/10/25 Uncl Dailly Church Crecent Odd numbers full length 30 £16,800 Programmed to Commence 03/11/25 Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget allocation B743 Mossblown Mauchline Road Fourways to railway bridge north side 28 £15,300 2026/27 Uncl Ayr Lochpark Slab replacement 23 £20,425 2026/27 Ayrshire Roads Alliance - Lighting Programme 2025/26 Town Location Work Type No of columns Estimated Programme Cost Comments Variance +/- Ayr Ayr - Old Hillfoot Road, Hillfoot Crescent & Souter Place Old steel columns & unreliable 5th Core 5 £30,000 Complete Ayr Cunningham Crescent & Area Unreliable 5th Core Supplies 16 £40,000 Complete Troon Concrete Column Replacements Ph3 Old deteriorated concrete columns 43 £55,000 Awarded £125,000 Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26 (i) Road Safety Programme Town/Route Location Proposed Scheme Progress Various Various locations Various schemes (TBC), anticipated to include: • Route Action Plan for the B743 at St Quivox; • B743 review at Failford Bridge; • Speed reduction measures at Coalpots Road at The Avenue; Development of a finalised programme for the current financial year will follow confirmation of any grant award from Transport Scotland’s Road Safety Improvement Fund (RSIF).
Page 17
Official (ii) Safer Neighborhoods Town Location Proposed Scheme Progress Phase 4 20mph schemes Various roads (TBC) 20mph speed limit schemes Discussion with SAC required to identify appropriate settlements for inclusion in Phase 4. Various Various locations Vehicle activated signs upgrade Pending implementation of new contract, and extents of upgrades will be subject to budget. (iii) Rural Route Action Plans Route Location Proposed Scheme Progress B743 Between the A77(T) and Auchincruive (St Quivox) TBC Listed under RSIF schemes above – subject to confirmation of funding. (iv) Active Travel Infrastructure – ATIF & Sustrans Town Location Proposed Scheme Progress Various Various locations • Various smaller schemes under Tier 1 funding, details TBC. Currently developing a package of schemes to be progressed during the current financial year making use of the Tier 1 grant award. Loans From Buchan Road to the A759 Loans to Troon Phase 3 Funding application unsuccessful, new application submitted to ATIF for 2025/26 Loans From Dundonald Road to Buchan Road Loans to Troon Phase 2 £24,500 received to install permanent monitoring equipment • Bradan Road, Troon – enhanced crossing points; • Road Safety scheme, Links Road, Prestwick.
Page 18
Official Dundonald To the northern side of the A759 Dundonald to Barassie Phase 1 Award received to treat Japanese Knotweed on-site, full construction funding application submitted to ATIF for 2025/26. Various Various Various Funding application unsuccessful, new application submitted to ATIF for 2025/26 Girvan Quay to Grangeston Girvan to Grangeston £27,378 received to complete RIBA Stage 1, Ayr Town Centre Accessible Ayr £778,780 received to complete RIBA Stage 4 of Route 1 Phase 1 Ayr-Girvan Ayr to Girvan Culzean Way £47,755 received to complete RIBA Stage 1 Coylton Coylton Primary Access for All – Coylton £27,378 received to install permanent monitoring equipment Ayr, Prestwick & Troon NCN7 NCN Barrier Removal £113,500 received to remove barriers from the NCN7 in Ayr Prestwick & Troon to make the route inclusive. Prestwick, Troon & Barassie NCN7 from Prestick Station to A759 Barassie Prestwick to Barassie £82,979 received to complete RIBA Stage 2 Dundonald Junction of A759/B730 Dundonald Cross £80,000 received to install signals at the junction of the A759/B730 Ayrshire Roads Alliance - Structures Capital Programme 2025/26 [Includes works carried forward from 2023/24/25] Description Work Type Estimated Programme Cost Comments Variance +/- A79-30 Victoria Bridge Concrete Repairs and Painting £432,776 Completed 0 A79-40 John Street, Ayr, Railway Bridge Parapets £362,000 Design Phase. -£294,225 FB.AYR-70 River Doon Cycleway Footbridge (Millenium Br) Refurbishment £145,000 Design Phase Tender Documents completed and Marine Licence applied for. £143,951 U740-10 Barbieston Bridge Replacement Design £86,820.00 Design Phase 50% - 50% EAC / SAC funded project as this is a boundary bridge. £80,025 Various Locations Vehicle Restraint Barrier Renewal £50,000 Design Phase Contract awarded works ongoing +£50,000
Page 19
Official Various Locations Cattle Grid Renewal Programme £33,600 Design Phase Contract awarded works ongoing £-33,600 C12 Dunure Station Road Dunure, Slope Stabilisation £130,000 A 70m long gravity retaining wall option has been selected as the most optimum solution. Detailed design and contract preparation is currently underway, however the capital budget currently available for this project is insufficient for the proposed solution – additional funding required. To be discussed with finance. -£124,087 Girvan Harbour Girvan Harbour South Pier Repairs £136,000 The South Pier Quay has been assessed to have a load carrying capacity of 0.5 tonnes per square metre. Following dive surveys undertaken earlier this year the option chosen to extend the life of the structure is steel plate repairs to the existing sheet piles and grouting of the voids. Completion and submission of the contract documentation was delayed in order that the significant damage caused to the South Pier Quay by the Q-Varl boat, when it broke its moorings in a storm, could be assessed and any repairs required could be included in the contract documents. Tenders to be issued in August with works completed by the end of 2025. £118,989 Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles £504,887 The sediment transfer model has been completed including options to deal with the defective sheet piling. The recommended option is to replace only the piling on the curved section from the lifeboat station. Contract documentation substantially complete and will be issued once tenders for the South Pier Quay works have been returned and costs are known. -£504,887 £1,881,083
Page 20
Official Appendix 2 East Ayrshire Council Ayrshire Roads Alliance – Carriageway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 ROAD LOCATION Estimated Cost Cost to Date variance +/- Comment A71 Dual Carriageway From Moorfield Roundabout – Target Worst Sections £300,000.00 Complete – final measure A736/U20 Junction Contribution to North Ayrshire to complete EAC section Junction Contribution to North Ayrshire to complete EAC section £15,000.00 To be programmed A735 From Lochridge House North Entrance to Windmill factory Farm £182,354.25 To be programmed A735 Rigg Street Stewarton From B778 to Brown Street £60,606.00 To be programmed B7046 Skares From Junction Newfield Rd to Recycling Centre Additional section into Skares £116,000.00 £152,936.00 Complete – final measure B769 Stewarton From Stewarton to North Ayrshire Boundary £219,375.00 To be programmed B743 Mauchline High Street From A76 to Loans (School) £52,680.60 Programmed to Commence 11/10/25 B7037 Titchfield Street Galston From Mini Roundabout to Orchard Street £97,500.00 Programmed to Commence 06/10/25 B7038 Kilmarnock Campbell Street From: Fire Station AC / To: Willock Street £41,595.40 Programmed to Commence 24/01/26 C3 Barskimming Road Mauchline From Loudoun Street to StationRoad £74,074.00 Programmed to Commence 18/10/25 C108 Stewarton From Greensland to Boundary £114,750.00 To be programmed C22 Coal Road Auchinleck From Railway bridge to Barbieston Road £35,612.50 To be programmed U55 Galston From U56 approx 1000m Westwards £78,750.00 £60,954.21 Complete – final measure Kilmarnock New Mill Road From Chapmans Terrace to end £45,584.00 To be programmed Kilmarnock Whatriggs Road From Tinto Avenue to Haining Avenue £35,612.50 To be programmed Kilmarnock East Shaw Street From Lidle to and around mini roundabout £37,814.00 Programmed to Commence 04/10/25 Kilmarnock Bentink Street On Approach to Mini roundabout £20,797.70 Programmed to Commence 04/10/25
Page 21
Official Kilmarnock Bellsland Grove Full Length £19,080.00 Programmed to Commence 04/10/25 Kimarnock Beech Avenue From Portland Road to Larch Place £84,501.40 Programmed to Commence 11/10/25 Kilmarnock Pine Road Full Length £42,022.75 Programmed to Commence 25/10/25 Kilmarnock Old Irvine Road From Lindsay Street to Grange Street £37,464.35 To be programmed Kilmarnock Brackenhill Avenue Full Length £32,323.20 To be programmed Kilmarnock Arran Avenue Full length £36,182.30 To be programmed Kilmarnock Lainshaw Avenue One Section £71,225.00 To be programmed Kilmarnock Townend Full Length £27,065.50 To be programmed Stewarton Avenue Square Access Road into car park £11,396.00 To be programmed Kilmaurs East Park Crescent Full Length £34,045.55 To be programmed Galston Western Road Outside Primary School £29,487.15 Complete – final measure Hurlford Mayfield Avenue Full Length £57,855.42 To be programmed Fenwick Skernieland Road From Old A77 Slip to Rysland Terrace £44,053.31 To be programmed Cumnock Hearth Road Full length £89,909.25 Programmed to Commence 15/12/25 Drongan Lane Crescent Full Length £27,195.00 To be programmed Bellsbank Corserene Terrace Full Length £29,526.00 To be programmed Dalmellington Gateside Road Broomknowe to B741 £31,080.00 To be programmed Dalrymple Cedar Terrace Full Length £15,540.00 To be programmed Drongan Mill o Shield Road From Coyle Avenue and Garrowhill Drive £37,749.25 To be programmed
Page 22
Official Ayrshire Roads Alliance – Footway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 Ayrshire Roads Alliance - £800k Residential Carriageway/Footway Improvement Programme 2025/26 WARD Location Estimated Costs Cost to Date Variance +/- Comment 1 Carriageway - Stewarton Dornie Close £9,120.00 To be programmed 1 Carriageway - Stewarton Braemore Road £11,310.00 To be programmed 1 Carriageway - Stewarton Kirkmuir Drive £54,000.00 To be programmed 2 Carriageway - Kilmarnock Tourhill Road £5,580.00 Complete – final measure 2 Carriageway - KilmarnockAuchencar Drive £15,120.00 Complete – final measure 2 Carriageway - KilmarnockWardneuk Drive £6,165.00 Complete – final measure 3 Carriageway - Kilmarnock Woodside Avenue To be programmed FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment Catrine - Newton Street Outside School £7,290.00 To be programmed Auchinleck - Main Street From Surgery to Council Car Park £21,870.00 To be programmed Cumnock - Glaisnock Road Outside Cemetery £19,044.00 To be programmed Kilmarnock - Dundonald Road Outside School £16,200.00 To be programmed Kilmarnock - Gilmour Street Various Locations £21,060.00 To be programmed Stewarton - High Street From Old Bank to Church £16,200.00 To be programmed Stewarton - Lainshaw Street Standalane to Sainsbury’s Rear Entrance £19,260.00 To be programmed Fenwick - Skerniland Road Both Sides £22,680.00 To be programmed Galston - A719 Opposite Loudoun Academy From Nursing Home to Barriered Section £8,100.00 To be programmed
Page 23
Official £60,000.00 4 Carriageway - Kilmarnock - Anderson Place/Bannerman Drive and Drummond Place £46,200.00 Programmed to Commence 25/10/25 4 Carriageway - Kilmarnock Sparrow Gardens £12,960.00 Programmed to Commence 12/01/26 5 Carriageway - Kilmarnock Simonsburn Road £9,225.00 To be programmed 5 Carriageway - Kilmarnock Elderslie Crescent/Ayr Road £13,500.00 To be programmed 6 Carriageway - Newmilns Sheilds Road £28,050.00 To be programmed 6 Carriageway - Darvel West Donnington Street £16,800.00 Programmed to Commence 06/12/25 6 Carriageway - Darvel Jaimieson Road £17,400.00 Complete – final measure 7 Carriageway - Mauchline Clarinda Crescent £23,100.00 Programmed to Commence 08/09/25 7 Carriageway - Mauchline East Park Avenue £25,560.00 Programmed to Commence 08/09/25 7 Carriageway - Mauchline Southpark Avenue £7,800.00 Programmed to Commence 08/09/25 7 Carriageway - Mauchline Welton Road £19,950.00 Programmed to Commence 23/09/25 7 Carriageway - Mauchline Mansfield Road £43,500.00 Programmed to Commence 23/09/25 8 Carriageway - Cumnock Latta Crescent £20,010.00 Programmed to Commence 12/01/26 8 Carriageway - Cumnock Nans Terrace £16,500.00 Programmed to Commence 24/11/25 8 Carriageway - Cumnock Lorimer Crescent £44,550.00 Programmed to Commence 01/12/25 8 Carriageway - Cumnock Hearth Place £24,000.00 Programmed to Commence 08/12/25 8 Carriageway - Cumnock Bank Avenue £21,420.00 To be programmed 8 Carriageway - Logan Holmhead Crescent £36,600.00 To be programmed 8 Carriageway - Logan Dixton Avenue £21,690.00 To be programmed 9 Carriageway - New Cumnock Castlemains Avenue £42,000.00 To be programmed 9 Carriageway - Dalmellington Church Hill/Melling Terrace £36,330.00 To be programmed 9 Carriageway - Dalmellington Knowehead £41,820.00 To be programmed 9 Carriageway - Ochiltree Gallowlee Avenue £20,490.00 To be programmed 4 Footway – Hurlford Furnace Court £15,750.00 To be programmed
Page 24
Official 6 Footway – Galston Bridge Street £3,750.00 To be programmed 6 Footway – Darvel Glen Crescent £17,500.00 To be programmed Ayrshire Roads Alliance - Lighting Capital Programme 2025/26 Town Location Work Type No of columns Estimated Programme Cost Comments Variance +/- Dalmellington Riecawr Ave, Area. Unreliable 5th Core. 22 £65,000 Completed 16 Jun 2025 Galston Maxwood Road. Unreliable 5th Core/Concrete columns. 10 £30,000 Completed 14 Jul 2025 New Cumnock Highpark Ave, Area. Unreliable 5th Core/Concrete columns. 19 £60,000 Started 04 Aug 2025 Stewarton Lothian Rd, Area. Unreliable 5th Core 23 £60,000 £215,000 Ayrshire Roads Alliance - LED Lighting Programme Update 2025/26 [Works carried over from 2024/25] Town Lantern Amount Status Delivery / start install Install complete by Kilmarnock - Central 1400 In progress Mar 2024 Mar 2026 East Ayrshire - Decorative 350 75% complete tender to be awarded for next stage Mar 2026 Ayrshire Roads Alliance - LED Lighting Programme 2025/26 Programme completed conversions to date 15,267 Replacement programme 97% complete Overall LED units completed 20,910 LEDs now 98% of total EAC inventory
Page 25
Official Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2025/26 Structure Reference Structure Name Proposed Works 2025/26 Estimate Comments Bridge Strengthening and Replacement A71/280 C80 Mathews Burn Culvert West Donnington St, Darvel Slab Replacement £250,000 Internal design ongoing. U751/10 Crossflats Bridge Replacement £40,000 Awarded to consultant to design replacement. Temporary bridge will be required during the works. U760/00 C93 Glenhead Bridge Replacement £60,000 Internal design ongoing, near tender ready. U740/10 Barbieston Bridge Replacement £60,000 SAC leading design. Award to consultant. Road Slips B713 South of Sorn £400,000 Works complete. Final measure being agreed. B741 Coal Glen Embankment Slip Remediation Works £690,000 Discussions ongoing with SPEN. Works to be retendered ASAP U13 Aitket Road Slip Remediation Works £500,000 Site clearance complete. With procurement to be tendered. A713/60 C61 Polnessan Upper Bridge Culvert Extension £500,000 Detailed design ongoing. Near tender ready. Upgrade Works Identified from Inspections B705/10 C91 Cowan Place Culvert Part Replacement/Scour Repairs £60,000 Near tender ready. A70/130 W31 Thornwood Wall, Lugar Replacement £500,000 Near tender ready. Discussion regarding requirement for road closure ongoing. A736/60 C84 Lochridge Culvert Masonry and Drainage Repairs £70,000 Works ongoing. A71 Riccarton Viaduct Refurbish - expansion joint removal/replacement £100,000 Design ongoing to replace 1 failing expansion joint with asphaltic plug joints. Works to be carried out ASAP.
Page 26
Official A71 River Irvine Bridge Refurbish - expansion joint removal/replacement Design ongoing to replace 1 failing expansion joint with asphaltic plug joints. Works to be carried out ASAP. C85/10 Fenwick Bridge Masonry Refurbishment £40,000 Award to consultant to progress with assessment and detailed design. U729/00 C64 Hayholm Bridge Masonry and Scour Repairs £60,000 Internal design ongoing. C95/10 Furnace Road Bridge Arch Strengthening £100,000 Awaiting PI report from consultant. Internal design ongoing. Parapet Upgrades A70/110 Causeyhead Bridge Parapet Repairs £60,000 Discussions ongoing regarding options to reduce disruption at Dumfries House. A736/50 Bloak Road Bridge Parapet Repairs £30,000 NAC/EAC boundary, EAC progressing design. Other Various Investigative Works Topographical Survey, Paint Inspection etc £8,000 Annual cost of surveys/inspections. Principal Inspection Consultant Fees £100,000 Consultant fees for 24/25 PI’s Various Low Bridge Signage Sign Upgrades £40,000 Upgrades to signage at 6 bridges with low head room. Contract awarded. Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26 Funding Source Project ID Location Project Description Detail Progress Allocation EAC Capital Road Safety Budget: £200,000 (£198,000 Road Safety + £2,000 Safer Neigh.) 22.23 A71 / Campbell Street Off Slip, Kilmarnock Junction signalisation Installation of new traffic signals, stopping up of Willock Street and new carriageway layout to improve capacity Final junction designs from traffic lights contractor still pending. Works planned to start January 2026 £105,000
Page 27
Official 22.50 B741 Dalmellington to New Cumnock Road safety review General route review to identify safety measures Driven survey along rural section to be completed. Ongoing. £2,000 22.38 Glaisnock Street, Cumnock Traffic calming Speed reduction/traffic calming measures Design works started - Late 25/26 for completion £15,000 22.15 VAS signs, various location Upgrades and new installations New contract to be implemented In progress £10,000 25.20 A713 - Waterside Road safety improvements 40mph repeaters, HFS gateway features and road markings upgrade October 25 £25,000 24.05 Various Traffic calming Speed surveys Ongoing £10,000 25.03 / 25.16 Various Road safety improvements HFS Schemes Ongoing £33,000 24.20 B751 - Kilmaurs to Fenwick Route Review General route review, VAS improvements, Road Markings and Signage, Studs Ongoing design works with Construction expected Sept 25 £125,000 25.11 A71 – Priestland Safer system improvements Vehicle restraint barriers Design work ongoing with Construction expected early 26 £75,000 25.13 A719 – Waterside Road Safety improvements VAS improvements , HFS and carriageway studs Design work ongoing with Construction expected early 26 £50,000 25.17 A70 – Dumfries House Road Safety improvements VAS improvements , HFS, carriageway studs and resurfacing Design work ongoing with Construction expected early 26 £50,000 Rural Route Action Plans Budget: £359,000 £134,000 (EAC) + £225,000 (Dev. Contributions) 22.08 B778 Stewarton to Fenwick Road alignment improvements at three key locations Agreement to proceed with site 1 improvements Process started £359,000
Page 28
Official Tier 1 Budget: £758,000 22.13 Grougar Road, Crookedholm Pedestrian crossing and road widening Installation of new crossing and layby Works started with planned completion late August 2025 £90,000 23.07 Strawberrybank Road, Kilmarnock Pedestrian crossing Appraisal for new crossing point Ped counts low so project reduced to consideration of ped refuge island £10,000 23.10 St Germain Street, Catrine Pedestrian safety improvements Installation of bollards and TRO Works complete with TRO to be finalised £10,000 N/A Kilmarnock Green Infinity Loop Cycling Infrastructure Route 1 & 2, Sturrock St and MSCP Route 1 & 2 design placed on hold due to lack of funding, MSCP site redevelopment application submitted to ATIF 2025/26. Sturrock St modelling completed. £100,000 24.18 A759 West of Gatehead Pedestrian improvements Footway designs and build out Design work ongoing with Construction expected early 26 £30,000 25.15 B751 Kilmaurs to Knockentiber Pedestrian improvements Footway improvements Design work ongoing with Construction expected early 26 £30,000 24.28 Kilmarnock Pedestrian improvements Footway designs and buildouts Onsite consultation to £30,000
Page 29
Official be completed prior to design work with Construction expected early 26 23.12 A713 Bellsbank Rd, Dalmellington Traffic calming 1 x speed table Construction expected June 25 £10,000 25.12 A71 Priestland Traffic Calming and pedestrian crossing Design work ongoing with Construction expected early 26 £50,000 Irvine Road Kilmaurs Pedestrian improvements Design work ongoing with Construction expected late 25 £35,000 Various location Various To be Confirmed £363,000 EAC Bus Infrastructure Budget: £645,000 22.51 Onthank Terminus, Kilmarnock Upgrades to existing infrastructure Improve crossing and boarding points Drawings complete to be paired with Stewarton Terminus £20,000 22.52 Stewarton Terminus, Stewarton Upgrades to existing infrastructure Improve turning circle and boarding points Design stage in progress £20,000 EAC Active Travel Budget £50,000 24.03 School Streets Programme Introduction of trial sites Three further schools to be trialled with further trials to be developed Live trials have commenced at Bellsbank and Dalrymple. Auchinleck in development. Further sites to be determined following completion of trial sites. £50,000
Page 30
Official Appendix 3 Ayrshire Roads Alliance - EV Public Chargers EAST AYRSHIRE CPS ID Type Make Location 51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU 50821 22kw eVolt Foregate Noth Car Park, Kilmarnock, KA1 1LU 51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH 52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW 70279 Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP 60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR 52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU 52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE
Page 31
Official 52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG 52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS 52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB 52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ 52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB 52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ 52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ 52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY 53778 Rapid eVolt Main Street Car Park, Muirkirk 53775 22kw eVolt Rose Reilly Sports Centre, Stewarton 53776 7kw eVolt Standalane Car Park, Stewarton 60786 7kW eVolt Academy Street, Hurlford 60792 22kW eVolt Drongan Centre car park, Mill of Shield Road 51210 22kW eVolt Carnshalloch Avenue car park, Patna 60950 22kW eVolt New Cumnock Outdoor Swimming Pool car park 60954 22kW eVolt Gatehead Road car park, Crosshouse 61021 7kW eVolt East Ayrshire Community Hospital, Cumnock 61022 7kW eVolt East Ayrshire Community Hospital, Cumnock 61983 7kW eVolt Morton Place car park, Kilmarnock 61984 7kW eVolt Morton Place car park, Kilmarnock
Page 32
Official 61985 7kW eVolt Morton Place car park, Kilmarnock 62184 7kW eVolt Browns Road car park, Newmilns 61886 22kW eVolt Sturrock Street, Kilmarnock 62938 7kW eVolt New London Road car park, Kilmarnock SOUTH AYRSHIRE CPS ID Type Make Location 51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW 51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU 70278 Rapid eVolt Burns Statue Square, Ayr, KA7 UT 52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN 52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY 50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ 50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF 52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG 70280 Rapid eVolt Girvan Harbour, Girvan, KA26 9AG 52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR 52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH 52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU 52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL 53774 Rapid eVolt Academy Street, Troon 53773 Rapid eVolt Lodge Road Car Park, Turnberry 53777 22kw eVolt Burnside Road, Monkton
Page 33
Official 60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly 60081 22kw eVolt Inches Close car park, Maybole 61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton 61986 22kw eVolt Dundonald Primary School car park, Dundonald 60086 22kw eVolt Mossblown Activity Centre car park, Mossblown 60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald 61979 7kW eVolt Chalmers Arcade car park, Girvan 61980 7kW eVolt Chalmers Arcade car park, Girvan 61981 7kW eVolt Chalmers Arcade car park, Girvan 62000 22kW eVolt Barrhill Community car park, Main Street, Barrhill
Page 34
Official Appendix 4 South Ayrshire Ward Investment and Promenade Programme for 2025/26 incl. works carried over from 2024/25 Roads Maintenance Unit LOCATION Description PO Value Cost to Date variance +/- Comment Troon Resurfacing of Troon Esplanade (Ph.3). Measuring works on site Prestwick Repair / renew steps to Boydfield Gardens £85,000.00 Complete – Final measure Prestwick Install power supply to Boydfield Gardens and Links Road Scottish Power quote to be received. Followed by agreed site start date Ayr North Provision of Bike Shelter at Lochside Community Centre £15,000.00 Bike shelter currently being fabricated Ayr East Glencairn Park – footpath upgrade Quote issued for approval Ayr East Car parking provision Peggieshill Road Quote provided, consultation required Ayr West Promenade raised footway works Feasibility study ongoing with Professional Design Services Kyle Install a History Park at Loans Community Hall and link to Smugglers trail Car park quote issued for approval. Garden and block paving quote being prepared Kyle Improve accessibility at Mossblown village hall Quote issued for approval Kyle Link path from Collins Drive to Collenan Avenue, Loans Quote provided, consultation required Kyle Resurface Bowling Green Car Park, Symington Quote provided, currently being assessed Kyle Construct new footpath at southern edge of Collenan Reservoir On Hold. Scope of works changed Design and Flooding Section Troon Shore Defence Structural Stabilisation £10,000.00 £15,432.00 -£5,432.00 Complete Citadel Footbridge Refurbishment Remove and renew timber deck parapet elements. Surface prepare and paint. Remove or repair lighting £140,000.00 £259,957.00 -£119,957.00 Complete
Page 35
Official Appendix 5 Ash dieback East Ayrshire and South Ayrshire 2025/26 2024 High Risk Works_EAC Highway 2024 High Risk Works_SAC Highway Girvan Boating Pond Refurbishment Install new stainless steel reinforced concrete base slab to reduce water leakage. £175,000.00 £170,641.00 £4,359.00 Complete Dunure Castle Footbridge Replacement Replace existing small span concrete footbridge with a larger footbridge with a view and good aesthetics £230,000.00 Ongoing. Lighting Section Ayr East Glencairn Park – Install footpath lighting £23,000.00 Design complete. Tender issued Ayr West Replacement of column lighting on Ayr Promenade £145,000.00 Column and street lighting works complete and operational. Additional works to install public Wi-Fi ongoing Ayr West New Bridge & Auld Brig. Design fees for installation of architectural floodlighting to structures £50,000.00 Exploring other means to procure Consultant as delay with SXL Technical & Consultancy Framework Ayr West Wrap round decorative lighting to columns on Ayr Promenade SAC PO to be issued