AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
06 June 2025 
Report by the Head of Ayrshire Roads Alliance
______________________________________________________________ 
SUBJECT: ROADWORKS PROGRAMME 2025/26
______________________________________________________________ 
Purpose of report 
1. The purpose of this report is to advise the Joint Committee on the progress of
work through the roads improvement programmes within East Ayrshire and
South Ayrshire for financial year 2025 to 2026. 
Recommendations 
2. It is recommended that Joint Committee: 
(i) Notes, the Ayrshire Roads Alliance programmed works 2025/26
(ii) Otherwise, notes the contents of this Report.  
Background 
3. The budget allocation for East and South Ayrshire Councils Roads Investment
Programme for FY 2025/26 can be seen in tables 1 and 2 below respectively. 
Table 1: East Ayrshire Council Roads Investment Programme 2025/26 
Programme Area Budget (£m)
Carriageway Resurfacing 2.305
Footway Resurfacing 0.150
Street Lighting 0.215
Traffic & Transportation incl. road safety 0.330 
Active Travel 0.050
School Streets 0.050
Bridge and Culvert Strengthening 
(incl. road slips)
3.500
Car Parks incl. Multi-storey demolition 0.820
Fleet 0.600
Total  £8.020
External Funding (Confirmed) 
SPT – Behaviour Change £0.385
Transport Scotland – Behaviour Change £0.116
ATIF - Tier 1  £0.758
Developer Contributions/Route Action
Plans
£0.396
SG – EV Infrastructure Fund £2.800
Total £4.455

Page 2

Official
External Funding (To be Confirmed) 
Sustrans – Annick Valley Stage 2 £0.175 (Tbc.)
ATIF Tier 2 - Design £2.405 (Tbc.)
Road Safety Improvement Fund £0.270 (Tbc)
SPT General Bus Infrastructure £0.270 (Tbc)
Total £3.120 (Tbc.) 
Table 2: South Ayrshire Council Roads Investment Programme 2025/26 
Programme Area Budget (£m)
Carriageway & Footway Resurfacing 1.581
Street Lighting 0.150
Bridges Capital 0.881
Millennium and Craigholm Bridges 0.145
C12 Dunure slope stabilisation 0.130
Vehicle restraint barriers 0.073
Cattle grid renewal 0.033
Girvan Harbour Jetty repairs 0.504
Local Flood Risk Plan 0.153
Ayr Depot 0.250
Climate Changes St Ninians Park 0.255
EV Charging Infrastructure 0.281
Total £4.436
External Funding (Confirmed) 
SPT – Behaviour Change £0.170
Transport Scotland £0.116
Tier 1 – Active Travel Funding £0.737
ATIF–Tier 2(Dundonald – Barassie) £2.500
Ayrshire Growth Deal £0.857
Levelling Up Fund (Active Travel) £4.000
Total £8.380
External Funding (To be Confirmed) 
Levelling Up Fund (Burns Statue) £15.000 (Tbc.
Sustrans £2.788 (Tbc.)
ATIF Tier 2 - Design £1.626 (Tbc.)
Road Safety Improvement Fund £0.270 (Tbc.)
SPT – Bus Infrastructure Improvements £0.100 (Tbc.)
Total £18.870 (Tbc.) 
Note: Several funding applications have still to be confirmed. The affected areas
of potential funding are denoted by the use of “£Tbc.” in Tables 1 and 2 above. 
Main report/main issues 
4. Surfacing programmes for FY 2025/26 are contained within Appendices One and
Two.

Page 3

Official
Capital Resurfacing 
5. In East Ayrshire 1% of the carriageway resurfacing programme has been
completed with some delays with the programming of the remaining works due
to the need to re-tender the contract for coal tar testing which must be carried
out ahead of any works. It is anticipated that this new testing contract will be
issued within the next month which will allow works to be programmed and
completed before the end of the financial year.   
6. In South Ayrshire we have completed 20% of the carriageway programme with
an anticipated completion date of October 2025.  Footway resurfacing
programme commences in September 2025 and with an anticipated completion
date of November 2025.  There has been several carriageways and footways
that have tested positive for coal tar which required additional control measures
to be put in place.  Some locations identified for 2025/26 have been carried
forward and rescheduled to 2026/27 programme. 
East Ayrshire Council residential road and footway repairs (Additional Revenue
Funding) 
7. At Cabinet on 13 March 2025, East Ayrshire Members Initiatives approved £800k
revenue funding for residential and footway repairs with locations identified
detailed within Appendix 2 of this report. 
South Ayrshire Council Ward Investment Programme 2025/26 
8. Officers within our engineering disciplines continue to develop work schemes
identified by Ward Members under the South Ayrshire Council Ward Investment
Programme for 2025/26 as detailed within Appendix 4 of the report.  Note:  Sites
will be further added as discussions progress with Officers and Ward Members. 
Timber Transport 
9. Two grant funded locations in South Ayrshire for 2024/25 are now complete. 
10. 5no. locations in the East and 2no. locations in the South were submitted by
Officers for Timber Transport funding.  All have been ranked just below the
threshold limits and consequently were unsuccessful to secure funding for
2025/26.  A meeting will be arranged to review our application process for when
the window opens for 2026/27 applications. 
Street Lighting 
11. Street lighting column and cable replacement programme of works which
incorporates LED lanterns is detailed in Appendix 1 and 2. 
12. Ayrshire Roads Alliance is actively exploring alternative procurement routes due
to a further delay of Scotland Excel Street Lighting Material Framework which is
hampering the completion of the LED project in the East.

Page 4

Official 
Electric Vehicle Infrastructure 
13. The Electric Vehicle Infrastructure Fund (EVIF) programme with the number of
public chargers installed to date is listed within Appendix 3 for South and East
Ayrshire respectively. 
14. East Ayrshire Council is the lead authority for the PAN Ayrshire Public Electric
Vehicle Charging Strategy. The project has secured a grant of £2.8million and
work continues on the procurement phase. Following the previously approved
business case, further papers have been presented to the cabinet regarding the
introduction of an EV charging tariff, which has been implemented across all
three Ayrshires as of 1st January 2025. A further increase to tariff will be
implemented on 1st July 2025. This tariff aims to establish a sustainable funding
model and attract private investment. 
15. Work continues on the tender documentation for the Pan Ayrshire concession
contract with the appointment of Mott MacDonald as consultants to assist with
the collation of the relevant documents required for tender. The Single
Procurement Document (SPD) was issued on 3rd March 2025 for the initial stage
of tendering, followed which we received numerous bids. The evaluation is
currently ongoing, with the Invitation to Tender (ITT) to be published in June 2025
for the shortlisted bidders, followed by contract award in October 2025. 
16. All Rapid Chargers are required under the Public Charge point regulations 2023
legislation to be able to accept contactless payment by 24th November 2024. 
Ayrshire Roads Alliance has secured funding from Transport Scotland
Contactless Compliance Grant Funding to replace/activate/retrofit eligible CPS
rapid chargers to incorporate contactless payment. Works have been carried out
to replace the non-compatible units and to activate contactless terminals on
compatible rapid chargers. 
17. Replacement of 22kW charger at Troon Swimming Pool is approved by SAC to
come from their capital fund. Replacement of 50kW chargers at Burns Statue
Square, Ayr and Girvan Harbour are funded by the Contactless Compliance
Funding. 
Structures 
18. Land acquisition and/or access agreements alongside environmental license
requirements continue to cause delays to a number of projects. ARA are working
closely with EAC Legal/Estates and relevant stakeholders to progress these
issues. 
19. Appendix 2 details East Ayrshire Council Bridges Capital programme for
2025/26. Seven works contracts are near tender ready. 
20. A Consultant has been appointed to carry out Principal Inspections on 437 EAC
structures. These are ongoing and should be complete by end of May 2025. The
internal Principal Inspection program for 2025 is underway.

Page 5

Official 
21. A713 Polnessan Upper Bridge - ARA have erected temporary traffic signals due
to subsidence in the carriageway. Traffic lights will remain in place until the slope
has been stabilised. There has been some disruption to Windfarms and Sub-
stations in the area and ARA working closely with developers to find alternative
routes for their abnormal load movements. A consultant has been appointed and
discussions are ongoing regarding a permanent solution. 
22. B741 Coal Glen Embankments works have been awarded; however, the works
have been postponed due to issues with a 132kV SPEN cable in the carriageway.
ARA are in ongoing discussions with SPEN, the contractor, legal services and
insurance to find a solution, works are now not likely to be completed until
2025/26. 
23. B713 near Sorn road slip sheet piling works are ongoing. Works going well,
programmed to be complete beginning of July 2025 
24. ARA are working with EAC Legal/Estates to acquire land at West Clerkland
Bridge through a Compulsory Purchase Order. The bridge has been shut to
vehicular traffic since 2012 and shut to both pedestrians and vehicular traffic
since 2021. 
25. 3no. bridges on the A71 between the Bellfield Interchange and Moorfield
Roundabout need replacement expansion joints. A consultant was appointed to
explore options in removing the joints and making the structures semi/fully
integral. It has been decided that in the meantime 2 joints that are repeatedly
failing will be replaced with asphaltic plug joints. 
26. B730/10 Littlemill Bridge land acquisition complete after years of negotiation.
Tender documents to be reviewed and works put out to tender with a view to start
on site in Spring 26. 
27. The South Pier Quay at Girvan Harbour has been assessed to have a load
carrying capacity of 0.5 tonnes per square metre. Following dive surveys
undertaken earlier this year the option chosen to extend the life of the structure
is steel plate repairs to the existing sheet piles and grouting of the voids. All
technical contract documentation has been completed and the tender process is
ongoing. It is anticipated that tenders will be issued in June with works
commencing on site in August/September. 
28. The detailed design of the Girvan Harbour Timber Jetty works are progressing
again now that the South Pier Quay design work has been completed. 
Submission of the contract documentation for review is expected in July 2025
followed by the tender process in August 2025 led by East Ayrshire Council
procurement. 
29. The A79/30 Victoria Bridge Concrete Repairs and Painting on site work is
currently paused.  The Marine Licence 28 day consultation process is ongoing

Page 6

Official
and will be concluded on the 21st May 2025. It is expected that determination of
the Marine Licence will take place soon afterwards, allowing the work to continue.   
30. Girvan Harbour dredging. Funding has been secured from SAC to carry out the
first phase of dredging in 2025/26to re-establish full operational status for the
RNLI lifeboat.  Dredging will be carried out in two areas to ensure the RNLI
lifeboat can operate at all tides. Area 1 is in the main channel where a 15m wide
x 181m long dredge will take place to 1.5m below chart datum. Area 2 is at the
RNLI Pontoon where a 15m wide x 43m long dredge will take place to 1.5m below
chart datum. All dredge material will be taken on shore and disposed at landfill.
Discussions are ongoing with SEPA and Marine Scotland to establish if any
works can be carried out prior to the end of the bathing restrictions in mid
September. 
31. Ayr South Pier. In May 2022 ARA and South Ayrshire Council agreed a
procedure for the inspection of Ayr South Pier as there did not appear to be an
inspection regime in place for this significant piece of Ayr Common Good
infrastructure. A key element of the procedure is that : 
“South Ayrshire Council, Asset Management and Community Asset Transfer –
Housing, Operations and Development Directorate are the owner of the asset,
responsible for liaison with the Ayrshire Roads Alliance and funding / carrying
out repairs” 
32. A key type of inspection detailed in the procedure is underwater inspection by
divers and to this end a 2024/25 Business Case submitted for Capital funding to
employ a consultant to carry out an underwater dive survey and structural
assessment was submitted. This was not accepted as the asset was Ayr
Common Good. A dive survey and assessment requires to be carried out soon
and we need to find a way of making this happen. No alternative method of
funding has been identified which is a matter of concern. 
33. On the 3rd February 2025 a sink hole was reported which had developed at the
land end of the South Pier in a verge area. Emergency repairs were required
immediately and follow up repairs are needed highlighting the importance of a
dive survey and assessment. Funding is being sought for this.   
Traffic & Transportation 
34. Active Travel Infrastructure Tier 1 grant funding has been received from
Transport Scotland.  Active Travel projects using the Tier 1 funding is currently
in development, and will be implemented over the course of the current financial
year. 
35. There was a reported underspend in EAC of £170k in 24/25 which has been
carried forward and the associated delayed projects have been included in this
years project list contained in Appendix 2. 
36. Confirmation of the Road Safety Improvement Fund grant allocations is pending
but it is anticipated that this years allocation for EAC will be in the region of £300k

Page 7

Official
and for SAC £219k. Schemes are currently being identified and prioritised and
the schemes listed in the appendices may be subject to change pending
Transport Scotland approval. 
37. The Kilmarnock Bus Station refurbishment programme is now complete and a
new cleaning and inspection regime has been implemented. Additional funding
has been allocated this year for upgrades to Cumnock Bus Station which include
changes to materials and the installation of a public address system. 
Ayrshire Growth Deal (AGD) Roads Projects 
38. The three Ayrshire Councils have worked in partnership with other agencies,
communities and businesses to secure the first Regional Growth Deal in
Scotland. This will see £251.5 million of investment in key assets and key sectors
across Ayrshire. 
39. There are currently no transport projects within the Ayrshire Growth Deal
proposed for East Ayrshire Council however the Ayrshire Roads Alliance
recognise the strategic importance of Bellfield Interchange and will continue to
work with colleagues to secure the improvements required. 
40. By carrying out extensive modelling of the existing road network around Glasgow
Prestwick Airport/Ayrshire Growth Deal cluster and building on the LDP2 no net
detriment approach the Ayrshire Roads Alliance was able to stress-test the road
network and identify the following improvements which will reduce peak
congestion, build capacity into the network to facilitate future growth, improve
road safety and journey time reliability. 
Project Location
1 Sandyford Toll Roundabout capacity improvements
2 Dutch House Roundabout capacity improvements
3 Monktonhead Roundabout capacity improvements 
4 A79/Station Road Roundabout capacity improvements
5 Shawfarm Road Roundabout capacity improvements
6 Shaw Road/Shawfarm Road junction re-alignment/improvements
7 Active Travel links from existing network to AGD Commercial Build
8 Public Transport Infrastructure improvements 
41. Project 7 & 8 compliment the project currently being progressed under the de-
carbonisation of the road network being developed by the Ayrshire Roads
Alliance and funded by the successful Levelling Up Fund round 3 award. 
42. A Case for Change has been submitted to Scottish & UK Governments seeking
approval of the changes noted above and also the Prestwick Proposition, the
Ayrshire Roads Alliance will assist in the delivery of all these projects for South
Ayrshire Council.

Page 8

Official
Levelling Up Fund
43. South Ayrshire Council successfully secured £20million of funding from the
Levelling Up Fund (LUF) round 3, £16million of this funding will be utilised to
redevelop Burns Statue Square with the remaining £4million allocated to Active
Travel. East Ayrshire Council were unsuccessful in securing funding in round 3
to improve the Bellfield Interchange. 
44. Burns Statue Square is a key initiative emerging from the Town Centre
Framework, it is a priority project to support placemaking and make the town a
more successful place to live, work, visit and enjoy. The project’s purpose is to
reshape the southern entrance to the town centre as a new attractive and
appealing gateway, involving rationalisation/ realignment of road carriageways
to create opportunity for more useable, connected, pedestrian friendly, high
quality public realm space and arrival point. 
The Ayrshire Roads Alliance procurement are exploring the potential of usingthe
SCAPE Framework to direct appoint Balfour Beattie to deliver the project on a
Design & Build basis due to the fixed budget and completion deadline of 31st
March 2027. 
45. The Ayrshire Roads Alliance will construct a new Active Travel Route linking
Dundonald to Barassie Station & improve the existing NCN7 from Prestwick to
Barassie railway stations. These improvements, which are being funded by
Active Travel Infrastructure Tier 2 funding will compliment further active travel
routes which will be delivered as part of the Ayrshire Growth Deal. 
Active Travel 
46. ARA submitted several applications to the Active Travel Infrastructure Fund
2025/26, £5.7m of construction funding in East Ayrshire & £2.878m of
construction funding in South Ayrshire was unsuccessful. We await a decision
on the remaining applications for design funding. 
47. A total of £787,000 has been secured for SPT & TS to deliver a behaviour change
programme in both South & East Ayrshire, projects including the re-
establishment of the Active Travel Hub in South Ayrshire, phase 1 construction
of an active travel innovation centre in East Ayrshire and support to the Cumnock
EV Car share project. 
Ash Dieback 
48. Following reports to Cabinets in East Ayrshire and South Ayrshire, surveys and
works are ongoing with 28-day notices being issued to owners and any
objections received referred to legal service. A detailed update report will be
presented to Joint Committee later in the year.

Page 9

Official
Implications 
49. 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning x  50 & 51
2. Governance x  52
3. Human Resources x  53
4. Equality and Fairer Scotland Duty  x 54
5. Financial x  3, 55 &
Appendix 1, 2
and 4
6. Risk x  56 & 57
7. Community Wealth Building x  58
8. Net Zero x  59 
Policy/strategic planning implications 
50. A well-maintained road network will contribute to achieving the 2015-2030
Community Plan objectives and associated 2021-2024 Delivery Plans 
51. The matters referred to in this report contribute to Priority 1 of the South Ayrshire   
Council Plan: Spaces and Places/ Moving around and the environment
(Outcome 1). 
Governance implications 
52. By virtue of the relevant statutory provisions, principally detailed within the Roads
(Scotland) Act 1984, the Council as local roads authority is required to manage
and maintain all publicly adopted roads within its area other than those which are
maintained and managed by the Scottish Ministers. 
Human resources implications 
53. The work programmes have direct impact on human resources and the Alliance  
will ensure all works are suitably resourced to maintain satisfactory progress. 
Equality impact and Fairer Scotland duty implications 
54. Equality Impact and Fairer Scotland Duty screening assessments will be
undertaken annually as required during the planning stage prior to the delivery of
the programme of works. 
Financial implications 
55. The Ayrshire Roads Alliance will deliver the strategic and local services as stated
in the Service Plan. The budget is provided by East Ayrshire Council, South

Page 10

Official
Ayrshire Council, and other external organisations. Appropriate scrutiny
arrangements are in place to manage these budgets. 
Risk implications 
56. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every 
Joint Committee. 
57. The Works Programmes, Service Plan and the Risk Register do not expose
either Council to an increased risk as they have been developed from existing
budgets and existing service commitment. 
Community Wealth Building implications 
58. The works programme provides economic levers to develop resilient, inclusive
local economies with more local spend and fair employment, as well as ensuring
that wealth is more locally owned and benefits local people. 
Net zero implications 
59. The Ayrshire Roads Alliance Service Plan and Carbon Strategy supports and
links to East Ayrshire Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment 
Appendices 
Appendix 1 - South Ayrshire Council Programme of Works 2024/26 
Appendix 2 - East Ayrshire Council Programme of Works 2025/26
Appendix 3 – EV Public Chargers
Appendix 4 - South Ayrshire Council Ward Investment Programme 2025/26 
Background papers 
• East Ayrshire Council – 2025/26 Road Asset Management Plan.  Investment
and Programme
• South Ayrshire Council – Road Improvement Plan 2025 - 2026 
Person to contact. 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail. jane.corrie@ayrshireroadsalliance.org 
Implementation Officer 
Craig Knape, Strategic Manager - Ayrshire Roads Alliance
Tel No. 01563 503164 
E-mail. craig.knape@ayrshireroadsalliance.org

Page 11

Official
Appendix 1 
South Ayrshire Council – Programme of Works 2024/26 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2024 to 2026  
[Works carried forward from 2023/24] 
Route
No
Town Road Name Works
Description
Sch
eme
Sco
re
Estimated
Cost
Cost to
Date
Variance
+/-
Comments
B734 Old Dailly Barr Old Dailly Old Dailly to Penkill
+ drainage
improvements
N/A £150,813 £163,932  -£13,119 Complete 
B7035 By Girvan Glendoune Houdston
Road (Coalpots)
Braetoll South + S
Power shut down
N/A £200,000 £206,251 -£6,251 Complete 
B743 By Mossblown Ayr / Mossblown? West from
Brocklehill Farm
53 £249,002 £249,239 -£237 Complete
C37 Auchincruive Barrackhall Gibbsyard  48 £123,861 123,873 -£12 Complete
Uncl Tarbolton Springfield Road Garden Street to No
50
46 £54,275 £53,851 +£424 Complete
B742 By Coylton B742 Council Boundary -
A70/Hillhead, Coylton
By Holebogs, S bend 59 £445,000 £440,506 +£4,494 Complete
B742 By Coylton B742 Council Boundary -
A70/Hillhead, Coylton
From A70 at
Hillhead south to
C21 Craigs Road
junction
56
B742 By Coylton B742 A70 Hillhead - B744
Jcn N Of Annbank, Coylton
From Meadowhead
Depot entrance
south-wards
55 Complete
B742 By Coylton B742 A70 Hillhead - B744
Jcn N Of Annbank, Coylton
Bridge of Coyle to
C2
52
B744 Annbank Weston Brae Full Length 53 £152,000 £207,822 -£55,822 Complete
B744 Annbank Browns Crescent 
Weston Avenue
Full Length
Craighall Way to
101 Weston Avenue
53
56
U77 By Coylton Hole Road Full Length 46 £82,867 £83,064 -£197 Complete 
B7023 Maybole Crosshill Road Full Length 56 £74,687 £72,215 +£2,472 Complete
Complete
Complete 
B7023 Maybole St Cuthbert's Road Full Length 53 £30,669 £41,792 -£11,123
B7024 Maybole Alloway Road Redbrae to Bypass 51 £55,922 £96,288 -£40,366

Page 12

Official
C122 By Maybole  C122 Gardenrose
Path/Maybole - School
Road/Minishant, Maybole 
C122 Gardenrose
Path/Maybole - School
Road/Minishant, Maybole
School to new
Bypass 
Ladycross to new
Bypass
50  £58,095 £58,097 -£2 Complete
B7023 Maybole Ballochbroe to Crosshill Dalhowan to C58  £275,435 £362,350 -£86,915 Complete
A719
PH 2
By Maidens 
By Dunure
Pennyglen/B7023 -
Kirkoswald Road/Maidens,
Maidens 
A719 Smithy
Bridge/Dunure - Croy
Brae, Dunure
B7023 Enoch Lodge
-Caravan Park 
Cemetery to
Drumshang
67 £281,669 £326,746 -£45,077 Complete 
Complete A719
PH 1
By Maidens  Pennyglen/B7023 -
Kirkoswald Rd & 
Turnberry Rd /Maidens,
Turnberry 
Morriston Farm to
Jct Blawearie 
Maidens to
Turnberry
56  £441,666 £540,857 -£99,191
Uncl Maybole Ashgrove Avenue Full Length  £88,954 £102,985 -£14,031 Complete 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – New Sites identified for 2024 to 2026 
B749 Troon Monktonhill Road Southwood jct to
Isle of Pin
59 £210,000 £265,328  -£55,328 Complete.
after excavation, additional
material was required to regulate
due to sand & soft spots localised
to lots of areas in Troon 
B749 Troon Craigend Road Fullarton Drive
railway bridge to
South Beach
48 £167,500 £201,706  -£34,206  Complete
Overspend same as Monktonhill Rd

Page 13

Official
B749 Troon South Beach  Lochend Road to
Academy Street jct
54 £200,000 £307,540  -£107,540  Complete.
Overspend same as Monktonhill
and Craigend. 
C44 Dailly Dailly to Turnberry Farden 500m
towards Drummock
39 £112,560 £71,137  +£41,422  Complete 
B7027 Barr Knowe Road Lochtonmill
southwards 
£63,000 £53,406.44 +£9,593  Complete 
B734 Colmonell Colmonell to the A77   £106,560 £150,273  -£43,713  Complete 
B7023 Maybole C58 to Cemetary   £297,606 £271,503  +£26,102  Complete 
A70 
C39
Coylton 
Ayr
Joppa 
Doonholm Road
Hole Road jct to
Pharmacy
Alloway to The
Loaning
35 
43
£179,321  £155,377  +£23,944  Complete
C145 Ayr Hillfoot Road Holmston Rd to
Holmston Dr
54 £91,875 £123,733 -£31,858  Complete
Uncl Maybole Queens Terrace/Chesney
Grove/Kincraig Avenue
Full Road 33
33
£166,275  £174,448  -£8,173  Complete
Uncl Maybole Cargill Road Full Road 47 £46,900 £48,224 -£1,324  Complete 
C1
(STTS)
Straiton Newton Stewart Road U8 towards Straiton
to U57
44 £120,400 £119.293  +£1,107  Complete 
B7045
(STTS)
Maybole Cassilis to Kirkmichael Rd Crorieshill Farm
northwards for
360m
44 £46,750  £51,700 -£4,950 Complete
Uncl Ayr Saltpans Road North from Glebe
Road
46 £112,249 £118,940 -£6,691  Complete 
Uncl Prestwick Morris Road Full Road 43 £55,000 £107,345 -£52,345  Complete
(positive for coal tar increased
costs)
Uncl Ayr Green Street Waggon Road to
Crown Street
42 £130,000 £214,584 -£84,584  Complete
(positive for coal tar increased
costs)
Uncl Prestwick Craigie Street Full length 39 £30,000 £36,725 -£6,725  Complete

Page 14

Official
B744 By Annbank B744 Belston/A70 -
Weston Avenue/Annbank,
Ayr
Auchincruive
Junction to
Glenview
52 £120,000  £139,872  -£19,872  Complete 
B742 By Maybole Dalrymple to Barnford
Farm
Dalrymple Road 46 £130,000  £138,058 -£8,058  Complete
Uncl Maybole Hicks Avenue Full cway & fway 30 £104,000 £133,263 -£29,263 Complete
Increased estimate due to
combining footway, kerbing,
carriageway resurfacing
C59 Colmonell Craigneil Road B734 to Bridge  £67,000 £53,129 +£13,871 Complete 
Uncl Ayr Peggieshill (PH1) Dalmilling Rd to
Nursery Rd
44 £92,000 £99,038 -£7,038  Complete 
Uncl Ayr Kincaidston (PH1) Marigold Sq to
Honeysuckle Park
52 £185,000 £181,768 +£3,232  Complete
Uncl Girvan Louisa Drive Knockcushion St to
Duncan St 
£103,640 £91,410 +£12,230 Complete
Uncl Ayr Peggieshill Rd (PH2) Nursery Rd to
Fenwickland Ave
44 £100,000 £33,739  Complete
Awaiting final measure
C74 By Ayr MacNairston Rd C105 to B742
junction
52 £97,608 £22,467  Complete
Awaiting final measure
B742 By Maybole Nether Culzean Dalrymple
Rd
Barnford farm to
Nether Culzean
42 £135,000 £20,084  Complete
Awaiting final measure
Uncl Ayr Ellisland Square (Contains
Coal Tar)
Full Length 42 £125,000  2nd-13th June ‘25
Uncl Ayr Kincaidston Drive (PH2) Honeysuckle Park to
Dalmellington Rd
52 £300,000   30th June – 25th July ‘25 
Mossblown Sandyford Road From a point 180
metres east of A719
junction eastwards
for 680m
53 £140,700   19th – 30th May ‘25
Uncl Ayr Dalmilling Road (Contains
Coal Tar)
Harthall to
Mainholm Rd
37 £275,000  28th July – 16th Aug ‘25
Uncl Prestwick Bellevue Road (TO BE TESTED) From Main Street to
Adamton Road 
£38,039   8th Sept – 3rd Oct ‘25
Uncl Girvan Todd Street (TO BE TESTED) Full length 31 £32,894   28th July – 8th Aug ‘25
Uncl Girvan Fauldribbon Road (TO BE
TESTED)
Full length 34 £31,813   11th-22nd Aug ‘25
Uncl Girvan B741 Linfern Road (TO BE
TESTED)
NO.79 to no.3 near
Main Street
29 £100,517   22nd Sept – 6th Oct ‘25
Uncl Maybole Carrick Street (TO BE TESTED) Ladyland Rd  to B77 33 £26,130   25th Aug – 8th Sept ‘25

Page 15

Official
Uncl Maybole Wellington Street (TO BE
TESTED)
Ladyland Rd to
Carrick St
30 £18,090   1st-15th Sept ‘25
Uncl Maybole Manse Street (TO BE TESTED) Drumellan St to
Abbott St 
£20,100   8th-22nd Sept ‘25
Uncl Girvan Hamilton Street (TO BE
TESTED)
Church Sq to Bridge
St
46 £49,655.55   13th-24th Oct ‘25
Uncl Ayr Chapel Park Road Full length 40 £55,984   2026/27
Uncl Prestwick St Cuthbert’s Rd St Andrew’s Ave to
Kirklandholm 
£38,587   2026/27 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2024 to 2026
[Works carried forward from 2023/24] 
C17 Tarbolton Westport Footway North side 28 £17,370 £24,984 -£7,644 Complete 
Uncl Prestwick Hunters Avenue South from
Heathfield Road,
west side
23 £7,500 £5,393 +£2,107  Complete
Uncl Troon Morven Drive Cessnock Rd to
Dundonald Rd
(Northside) 
£15,072 £28,820 -£13,748 Complete
C151 Dailly Woodside Both sides from
Back St and
Hadyard Terr
30 £20,400 £17,147 +£3,253 Complete 
Uncl Crosshill Newton Street Church Side of road 30 £15,795 £14,440 +£1,355 Complete
Uncl Dailly Hadyard Terrace Inside footway +
part outer section
28 £54,400 £20,110 +£34,290 Complete 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for 2024 to 2026 
Uncl Mossblown Martin Avenue Mossblown 28 £28,300 £30,829 -£2,529 Complete 
B744 Annbank Weston Brae Full Length 28 £10,700 £5,761 +£4,939 Complete
B730 Dundonald Drybridge Road Bowling Green to
Kilnford Dr
28 £19,223   18TH Aug – 5th Sept ‘25
Uncl Ayr Bellevue Crescent Full Length 34 £37,800   TBC - tree inspection required
Uncl Maidens Ardlochan Road Full Length 30 £21,000   24th-31st Oct ‘25
Uncl Dailly Church Crecent Odd numbers full
length
30 £16,800   3rd-21st Nov ‘25

Page 16

Official
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget allocation 
B743 Mossblown Mauchline Road Fourways to railway
bridge north side
28 £15,300   2026/27
Uncl Ayr Lochpark Slab replacement 23 £20,425   2026/27 
Ayrshire Roads Alliance - Lighting Programme 2025/26 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Ayr Ayr - Old Hillfoot Road, Hillfoot
Crescent & Souter Place
Old steel columns &
unreliable 5th Core 5 £30,000 Remedial works to
complete 
Ayr Cunningham Crescent & Area Unreliable 5th Core
Supplies 16 £40,000 Final Measure to
complete 
Troon Concrete Column
Replacements Ph3
Old deteriorated concrete
columns 43 £55,000      
£125,000   
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26
(i) Road Safety Programme 
Town/Route Location Proposed Scheme Progress
Various Various locations   Various schemes (TBC), anticipated to
include:
• Route Action Plan for the
B743 at St Quivox;
• B743 review at Failford
Bridge;
• Speed reduction measures at
Coalpots Road at The
Avenue;
• Bradan Road, Troon –
enhanced crossing points;
Development of a finalised
programme for the current financial
year will follow confirmation of any
grant award from Transport
Scotland’s Road Safety Improvement
Fund (RSIF).

Page 17

Official 
(ii) Safer Neighborhoods 
Town Location Proposed Scheme Progress
Phase 4 20mph schemes Various roads (TBC) 20mph speed limit schemes Discussion with SAC required to
identify appropriate settlements for
inclusion in Phase 4.
Various Various locations Vehicle activated signs upgrade Pending implementation of new
contract, and extents of upgrades will
be subject to budget. 
(iii) Rural Route Action Plans 
Route Location Proposed Scheme Progress
B743  Between the A77(T) and Auchincruive (St
Quivox)
TBC Listed under RSIF schemes above –
subject to confirmation of funding. 
(iv) Active Travel Infrastructure – ATIF & Sustrans 
Town Location Proposed Scheme Progress
Various Various locations • Various smaller schemes
under Tier 1 funding, details
TBC.   
The ARA are currently developing a
package of schemes to be progressed
during the current financial year
making use of the Tier 1 grant award.
Loans From Buchan Road to the A759 Loans to Troon Phase 3 Funding application unsuccessful, new
application submitted to ATIF for
2025/26
Loans From Dundonald Road to Buchan Road Loans to Troon Phase 2 £24,500 received to install permanent
monitoring equipment
Dundonald To the northern side of the A759 Dundonald to Barassie Phase 1 Award received to treat Japanese
Knotweed on-site, full construction
• Road Safety scheme, Links
Road, Prestwick.

Page 18

Official
funding application submitted to ATIF
for 2025/26.
Various Various Various Funding application unsuccessful, new
application submitted to ATIF for
2025/26
Girvan  Quay to Grangeston Girvan to Grangeston £27,378 received to complete RIBA
Stage 1, 
Ayr Town Centre Accessible Ayr £778,780 received to complete RIBA
Stage 4 of Route 1 Phase 1
Ayr-Girvan Ayr to Girvan Culzean Way £47,755 received to complete RIBA
Stage 1
Coylton Coylton Primary Access for All – Coylton £27,378 received to install permanent
monitoring equipment
Ayr, Prestwick & Troon NCN7 NCN Barrier Removal £113,500 received to remove barriers
from the NCN7 in Ayr Prestwick &
Troon to make the route inclusive.
Prestwick, Troon & Barassie NCN7 from Prestick Station to A759 Barassie Prestwick to Barassie £82,979 received to complete RIBA
Stage 2
Dundonald Junction of A759/B730 Dundonald Cross £80,000 received to install signals at
the junction of the A759/B730 
Ayrshire Roads Alliance - Structures Capital Programme 2025/26 [Includes works carried forward from 2023/24/25] 
Description   Work Type Estimated
Programme Cost 
Comments Variance +/-
A79-30 Victoria Bridge Concrete Repairs and Painting 
£432,776
Ongoing   
-£432,776
A79-40  John Street, Ayr, Railway Bridge Parapets  £362,000 Design Phase.  
-£294,580
FB.AYR-70 River Doon Cycleway Footbridge (Millenium Br)
Refurbishment
£145,000 Design Phase -£145,000
U740-10 Barbieston Bridge Replacement Design  £86,820.00 Design Phase 50% - 50% EAC / SAC funded
project as this is a boundary bridge.
-£86,820.00 
Various Locations
Vehicle Restraint Barrier Renewal £50,000  Design Phase 
+£50,000
Various Locations Cattle Grid Renewal Programme £33,600 Design Phase £-33,600

Page 19

Official
C12 Dunure Station Road Dunure, Slope Stabilisation 
£130,000
Design Ongoing, Construction Planned
2023/24.  A 70m long gravity retaining wall
option has been selected as the most
optimum solution. Detailed design and
contract preparation is currently underway,
however the capital budget currently
available for this project is insufficient for the
proposed solution. An additional funding
solution has been identified but has not been
presented to or approved by SAC Panel. 
-£130,000
Girvan Harbour Girvan Harbour South Pier Repairs £136,000 The South Pier Quay has been assessed to
have a load carrying capacity of 0.5 tonnes
per square metre. Following dive surveys
undertaken earlier this year the option
chosen to extend the life of the structure is
steel plate repairs to the existing sheet piles
and grouting of the voids.   
Completion and submission of the contract
documentation was delayed in order that the
significant damage caused to the South Pier
Quay by the Q-Varl boat, when it broke its
moorings in a storm, could be assessed and
any repairs required could be included in the
contract documents. The contract
documentation has been completed and it is
anticipated that tenders will be issued in
June with works commencing on site in
August/September 2025. 
-£120,759
Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles 
£504,887
The sediment transfer model has been
completed including options to deal with the
defective sheet piling. The recommended
option is to remove all existing sheet piling
then replace only that on the curved section
from the lifeboat station. The design and
contract preparation is progressing on this
basis and is programmed to be completed by
July with the tender process commencing in
August 2025. 
-£504,887  
£1,881,083

Page 20

Official 
Appendix 2 
East Ayrshire Council 
Ayrshire Roads Alliance – Carriageway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 
ROAD LOCATION Estimated
Cost
Cost to Date variance +/- Comment
A71 Dual Carriageway  From Moorfield Roundabout – Target Worst Sections
£300,000.00  
Programmed to
commence on
02/08/25
A736/U20 Junction
Contribution to North
Ayrshire to complete
EAC section
Junction Contribution to North Ayrshire to complete
EAC section
£15,000.00 
To be programmed
A735  From Lochridge House North Entrance to Windmill
factory Farm £182,354.25  
To be programmed
A735 Rigg Street
Stewarton From B778 to Brown Street £60,606.00 
To be programmed
B7046 Skares From Junction Newfield Rd to Recycling Centre
Additional section into Skares £116,000.00 
Programmed to
commence on
16/06/25
B769 Stewarton  From Stewarton to North Ayrshire Boundary £219,375.00   To be programmed
B743 Mauchline High
Street From A76 to Loans (School) £52,680.60  
To be programmed
B7037 Titchfield
Street Galston From Mini Roundabout to Orchard Street £97,500.00  
To be programmed
B7038 Kilmarnock
Campbell Street From: Fire Station AC / To: Willock Street                   £41,595.40  
To be programmed
C3 Barskimming Road
Mauchline From Loudoun Street to StationRoad £74,074.00  
To be programmed
C108 Stewarton From Greensland to Boundary £114,750.00   To be programmed
C22 Coal Road
Auchinleck From Railway bridge to Barbieston Road £35,612.50  
To be programmed
U55 Galston  From U56 approx 1000m Westwards £78,750.00  
Complete - final
measure
Kilmarnock New Mill
Road From Chapmans Terrace to end £45,584.00  
To be programmed

Page 21

Official
Kilmarnock Whatriggs
Road From Tinto Avenue to Haining Avenue £35,612.50  
To be programmed
Kilmarnock East Shaw
Street From Lidle to and around mini roundabout £37,814.00  
To be programmed
Kilmarnock Bentink
Street On Approach to Mini roundabout £20,797.70  
To be programmed
Kilmarnock Bellsland
Grove Full Length £19,080.00  
To be programmed
Kimarnock Beech
Avenue From Portland Road to Larch Place £84,501.40  
To be programmed
Kilmarnock Pine Road Full Length £42,022.75   To be programmed
Kilmarnock Old Irvine
Road From Lindsay Street to Grange Street £37,464.35  
To be programmed
Kilmarnock
Brackenhill Avenue Full Length  £32,323.20  
To be programmed
Kilmarnock Arran
Avenue  Full length  £36,182.30  
To be programmed
Kilmarnock Lainshaw
Avenue One Section £71,225.00  
To be programmed
Kilmarnock Townend Full Length £27,065.50   To be programmed
Stewarton Avenue
Square Access Road into car park £11,396.00  
To be programmed
Kilmaurs East Park
Crescent Full Length £34,045.55  
To be programmed
Galston Western
Road Outside Primary School £29,487.15  
To be programmed
Hurlford Mayfield
Avenue Full Length £57,855.42  
To be programmed
Fenwick Skernieland
Road From Old A77 Slip to Rysland Terrace £44,053.31  
To be programmed
Cumnock Hearth
Road Full length £89,909.25  
To be programmed
Drongan Lane
Crescent Full Length £27,195.00  
To be programmed
Bellsbank Corserene
Terrace Full Length £29,526.00  
To be programmed
Dalmellington
Gateside Road Broomknowe to B741 £31,080.00  
To be programmed

Page 22

Official
Dalrymple Cedar
Terrace  Full Length £15,540.00  
To be programmed
Drongan Mill o Shield
Road From Coyle Avenue and Garrowhill Drive £37,749.25  
To be programmed 
Ayrshire Roads Alliance – Footway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 
Ayrshire Roads Alliance - £800k Residential Carriageway/Footway Improvement Programme 2025/26 
WARD Location Estimated
Costs
Cost to Date Variance +/- Comment 
1
Carriageway - Stewarton Dornie Close  £9,120.00   To be programmed
1 Carriageway - Stewarton Braemore Road £11,310.00   To be programmed
1 Carriageway - Stewarton Kirkmuir Drive £54,000.00   To be programmed
FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment
Catrine - Newton
Street Outside School £7,290.00  
To be programmed
Auchinleck - Main
Street From Surgery to Council Car Park £21,870.00  
To be programmed
Cumnock -
Glaisnock Road Outside Cemetery £19,044.00  
To be programmed
Kilmarnock -
Dundonald Road Outside School £16,200.00  
To be programmed
Kilmarnock -
Gilmour Street Various Locations £21,060.00  
To be programmed
Stewarton - High
Street From Old Bank to Church £16,200.00  
To be programmed
Stewarton -
Lainshaw Street Standalane to Sainsbury’s Rear Entrance £19,260.00  
To be programmed
Fenwick - Skerniland
Road Both Sides £22,680.00  
To be programmed
Galston - A719
Opposite Loudoun
Academy From Nursing Home to Barriered Section £8,100.00 
To be programmed

Page 23

Official
2 Carriageway - Kilmarnock Tourhill Road £5,580.00   Complete – final measure
2 Carriageway - KilmarnockAuchencar Drive £15,120.00   Complete – final measure
2 Carriageway - KilmarnockWardneuk Drive £6,165.00   Complete – final measure
3 Carriageway - Kilmarnock Woodside Avenue  £60,000.00  
To be programmed
4
Carriageway - Kilmarnock - Anderson Place/Bannerman
Drive and Drummond Place
£46,200.00   To be programmed
4 Carriageway - Kilmarnock Sparrow Gardens £12,960.00   To be programmed
5 Carriageway - Kilmarnock Simonsburn Road £9,225.00   To be programmed
5 Carriageway - Kilmarnock Elderslie Crescent/Ayr Road £13,500.00   To be programmed
6 Carriageway - Newmilns Sheilds Road £28,050.00   To be programmed
6 Carriageway - Darvel West Donnington Street £16,800.00   To be programmed
6 Carriageway - Darvel Jaimieson Road £17,400.00   To be programmed
7 Carriageway - Mauchline Clarinda Crescent £23,100.00   To be programmed
7 Carriageway - Mauchline East Park Avenue £25,560.00   To be programmed
7 Carriageway - Mauchline Southpark Avenue £7,800.00   To be programmed
7 Carriageway - Mauchline Welton Road £19,950.00   To be programmed
7 Carriageway - Mauchline Mansfield Road £43,500.00   To be programmed
8 Carriageway - Cumnock Latta Crescent £20,010.00   To be programmed
8 Carriageway - Cumnock Nans Terrace £16,500.00   To be programmed
8 Carriageway - Cumnock Lorimer Crescent £44,550.00   To be programmed
8 Carriageway - Cumnock Hearth Place £24,000.00   To be programmed
8 Carriageway - Cumnock Bank Avenue £21,420.00   To be programmed
8 Carriageway - Logan Holmhead Crescent £36,600.00   To be programmed
8 Carriageway - Logan Dixton Avenue £21,690.00   To be programmed
9 Carriageway - New Cumnock Castlemains Avenue £42,000.00   To be programmed
9
Carriageway - Dalmellington Church Hill/Melling
Terrace £36,330.00   To be programmed
9 Carriageway - Dalmellington Knowehead £41,820.00   To be programmed
9 Carriageway - Ochiltree Gallowlee Avenue £20,490.00   To be programmed
4 Footway – Hurlford Furnace Court £15,750.00   To be programmed
6 Footway – Galston Bridge Street £3,750.00   To be programmed
6 Footway – Darvel Glen Crescent £17,500.00   To be programmed

Page 24

Official 
Ayrshire Roads Alliance - Lighting Capital Programme 2025/26 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Dalmellington Riecawr Ave, Area. Unreliable 5th Core. 22 £65,000 Scheduled
12 May 2025 
Galston Maxwood Road.
Unreliable 5th
Core/Concrete
columns.
10 £30,000 Scheduled
23 Jun 2025 
New Cumnock Highpark Ave, Area.
Unreliable 5th
Core/Concrete
columns.
19 £60,000  
Stewarton Lothian Rd, Area. Unreliable 5th Core 23 £60,000    
£215,000 
Ayrshire Roads Alliance - LED Lighting Programme Update 2025/26 [Works carried over from 2024/25] 
Town Lantern
Amount Status
Delivery /
start
install
Install
complete
by
Kilmarnock - Central 1400 In progress Mar 2024 Mar 2026
East Ayrshire - Decorative 350 75% complete 
tender to be awarded for next stage  Mar 2026 
Ayrshire Roads Alliance - LED Lighting Programme 2025/26 
Programme completed conversions to date 15,267 Replacement programme 97% complete
Overall LED units completed 20,910 LEDs now 98% of total EAC inventory

Page 25

Official
Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2025/26 
Structure
Reference
Structure Name Proposed Works 2025/26
Estimate
Comments
Bridge Strengthening and Replacement    
A71/280 C80 Mathews Burn Culvert
West Donnington St,
Darvel
Slab Replacement £250,000 Internal design ongoing.
U751/10 Crossflats Bridge Replacement £40,000 Awarded to consultant to design replacement.
Temporary bridge will be required during the works.
U760/00 C93 Glenhead Bridge Replacement £60,000 Internal design ongoing, near tender ready.
U740/10 Barbieston Bridge Replacement £60,000 SAC leading design. Award to consultant.
Road Slips  
B713 South of Sorn  £400,000 Works ongoing. Programmed completion 4th July 25.
B741 Coal Glen Embankment Slip Remediation Works £690,000 Discussions ongoing with contractor and SPEN.
U13 Aitket Road Slip Remediation Works £500,000 Near tender ready. Site clearance complete.
A713/60 C61 Polnessan Upper Bridge Culvert Extension £500,000 Detailed design ongoing.
Upgrade Works Identified from Inspections  
B705/10 C91 Cowan Place Culvert Part Replacement/Scour
Repairs
£60,000 Near tender ready.
A70/130
W31
Thornwood Wall, Lugar Replacement £500,000 Near tender ready. Discussion regarding requirement for
road closure ongoing.
A736/60 C84 Lochridge Culvert Masonry and Drainage
Repairs
£70,000 Near tender ready.
A71 Riccarton Viaduct Refurbish - expansion joint
removal/replacement
£100,000 Design ongoing to replace 1 failing expansion joint with
asphaltic plug joints. Works to be carried out ASAP.

Page 26

Official
A71 River Irvine Bridge Refurbish - expansion joint
removal/replacement 
Design ongoing to replace 1 failing expansion joint with
asphaltic plug joints. Works to be carried out ASAP.
C85/10 Fenwick Bridge Masonry Refurbishment £40,000 Award to consultant to progress with assessment and
detailed design.
U729/00 C64 Hayholm Bridge Masonry and Scour Repairs £60,000 Internal design ongoing.
C95/10 Furnace Road Bridge Arch Stregthening £100,000 Awaiting PI report from consultant. Internal design
ongoing.
Parapet Upgrades  
A70/110 Causeyhead Bridge Parapet Repairs £60,000 Discussions ongoing regarding options to reduce
disruption at Dumfries House.
A736/50 Bloak Road Bridge Parapet Repairs £30,000 NAC/EAC boundary, EAC progressing design.
Other  
Various Investigative Works Topographical Survey, Paint
Inspection etc
£8,000 Annual cost of surveys/inspections. 
Principal Inspection Consultant Fees £100,000 Consultant fees for 24/25 PI’s
Various Low Bridge Signage  Sign Upgrades £40,000 Upgrades to signage at 6 bridges with low head room. 
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26
Funding Source Project
ID
Location Project Description Detail Progress Allocation
EAC Capital Road Safety
Budget: £200,000
(£198,000 Road Safety +
£2,000 Safer Neigh.)
22.23 A71 / Campbell Street
Off Slip, Kilmarnock
Junction
signalisation
Installation of new
traffic signals, stopping
up of Willock Street
and new carriageway
layout to improve
capacity
Final junction
designs from
traffic lights
contractor still
pending.
Implementation
pushed back to
Jul/Aug 25.
£105,000

Page 27

Official
22.50 B741 Dalmellington to
New Cumnock
Road safety
review
General route review
to identify safety
measures
Driven survey
along rural
section to be
completed.
Ongoing. 
£2,000
22.38 Glaisnock Street,
Cumnock
Traffic calming Speed
reduction/traffic
calming measures
Design works
started - Late
25/26 for
completion
£15,000
22.15 VAS signs, various
location
Upgrades and
new installations
New contract to be
implemented
In progress £10,000
23.09 B769 Kingsford Speed limit and
traffic calming
Appraisal Late 25 for
construction
works
£25,000
24.05 Various Traffic calming Speed surveys Ongoing £10,000
25.03
/
25.16
Various Road safety
improvements
HFS Schemes Ongoing £33,000
Road Safety
Improvement Fund
Budget: £300,000 (TBC)      
24.20 B751 - Kilmaurs to
Fenwick 
Route Review General route review,
VAS improvements,
Road Markings and
Signage, Studs
Ongoing design
works with
Construction
expected Sept 25
£125,000
25.11 A71 – Priestland Safer system
improvements
Vehicle restraint
barriers
Design work
ongoing with
Construction
expected early 26
£75,000
25.13 Waterside Road Safety
improvements
VAS improvements ,
HFS and carriageway
studs
Design work
ongoing with
Construction
expected early 26
£50,000
25.17 A70 – Dumfries House Road Safety
improvements
VAS improvements ,
HFS and carriageway
studs
Design work
ongoing with
Construction
expected early 26
£50,000
Rural Route Action Plans
Budget: £359,000
£134,000 (EAC) + £225,000
(Dev. Contributions)
22.08 B778 Stewarton to
Fenwick
Road alignment
improvements at
three key
locations
Agreement to proceed
with site 1
improvements
Process started £359,000

Page 28

Official
Tier 1
Budget: £758,000 
22.13 Grougar Road,
Crookedholm
Pedestrian
crossing and road
widening
Installation of new
crossing and layby
Start date
pushed back to
Spring 25
£90,000
23.07 Strawberrybank Road,
Kilmarnock
Pedestrian
crossing
Appraisal for new
crossing point
Ped counts low
so project
reduced to
consideration of
ped refuge island
£10,000
23.10 St Germain Street,
Catrine
Pedestrian safety
improvements
Installation of bollards
and TRO
In progress £10,000
N/A Kilmarnock Green
Infinity Loop
Cycling
Infrastructure
Route 1 & 2, Sturrock
St and MSCP
Route 1 & 2
design placed on
hold due to lack
of funding, MSCP
site
redevelopment
application
submitted to
ATIF 2025/26.
Sturrock St
modelling
completed.
£100,000
24.18 A759 West of
Gatehead
Pedestrian
improvements
Footway designs and
build out
Design work
ongoing with
Construction
expected early 26
£30,000
25.15 B751 Pedestrian
improvements
Footway
improvements
Design work
ongoing with
Construction
expected early 26
£30,000
24.28 Kilmarnock Pedestrian
improvements
Footway designs and
buildouts
Onsite
consultation to
be completed
prior to design
work with
Construction
expected early 26
£30,000
23.12 A713 Traffic calming 1 x speed table Construction
expected June 25
£10,000

Page 29

Official 
Appendix 3 
Ayrshire Roads Alliance - EV Public Chargers 
EAST AYRSHIRE 
CPS ID Type Make Location
51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
50821 22kw eVolt Foregate Noth Car Park, Kilmarnock, KA1 1LU
51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH
52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
25.12 A71 Priestland Traffic Calming and
pedestrian crossing
Design work
ongoing with
Construction
expected early 26
£50,000 
Irvine Road Kilmaurs Pedestrian
improvements
Design work
ongoing with
Construction
expected late 25
£35,000 
Various location Various Unallocated  £363,000
EAC Bus Infrastructure
Budget: £40,000
22.51 Onthank Terminus,
Kilmarnock
Upgrades to
existing
infrastructure
Improve crossing and
boarding points
Drawings
complete to be
paired with
Stewarton
Terminus 
£20,000
22.52 Stewarton Terminus,
Stewarton
Upgrades to
existing
infrastructure
Improve turning circle
and boarding points
Design stage in
progress
£20,000
EAC Active Travel
Budget £50,000
24.03 School Streets
Programme
Introduction of
trial sites
Three further schools
to be trialled with
further trials to be
developed
Trials have
commenced at
Bellsbank and
Dalrymple.
Further sites to
progress.
£50,000

Page 30

Official
52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW
TBC Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP
60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR
52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU
52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE
52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG
52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS
52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB
52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ
52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB
52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ

Page 31

Official
52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY
53778 Rapid eVolt Main Street Car Park, Muirkirk
53775 22kw eVolt Rose Reilly Sports Centre, Stewarton
53776 7kw eVolt Standalane Car Park, Stewarton
60786 7kW eVolt Academy Street, Hurlford
60792 22kW eVolt Drongan Centre car park, Mill of Shield Road
51210 22kW eVolt Carnshalloch Avenue car park, Patna
60950 22kW eVolt New Cumnock Outdoor Swimming Pool car park
60954 22kW eVolt Gatehead Road car park, Crosshouse
61021 7kW eVolt East Ayrshire Community Hospital, Cumnock
61022 7kW eVolt East Ayrshire Community Hospital, Cumnock
61983 7kW eVolt Morton Place car park, Kilmarnock
61984 7kW eVolt Morton Place car park, Kilmarnock
61985 7kW eVolt Morton Place car park, Kilmarnock
62184 7kW eVolt Browns Road car park, Newmilns
61886 22kW eVolt Sturrock Street, Kilmarnock
62938 7kW eVolt New London Road car park, Kilmarnock
SOUTH AYRSHIRE
CPS ID Type Make Location
51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW
51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU
TBC Rapid eVolt Burns Statue Square, Ayr, KA7 UT
52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN
52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT

Page 32

Official
52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY
50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ
50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF
52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG
TBC Rapid eVolt Girvan Harbour, Girvan, KA26 9AG
52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR
52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH
52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU
52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL
53774 Rapid eVolt Academy Street, Troon
53773 Rapid eVolt Lodge Road Car Park, Turnberry
53777 22kw eVolt Burnside Road, Monkton
60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly
60081 22kw eVolt Inches Close car park, Maybole
61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton
61986 22kw eVolt Dundonald Primary School car park, Dundonald
60086 22kw eVolt Mossblown Activity Centre car park, Mossblown
60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald
61979 7kW eVolt Chalmers Arcade car park, Girvan
61980 7kW eVolt Chalmers Arcade car park, Girvan
61981 7kW eVolt Chalmers Arcade car park, Girvan
62000 22kW eVolt Barrhill Community car park, Main Street, Barrhill

Page 33

Official
Appendix 4 South Ayrshire Ward Investment Programme 2025/26 
Roads Maintenance Unit
LOCATION Description PO Value  Cost to Date variance +/- Comment
Troon Emergency repairs to Troon Esplanade. £40,000.00  
Complete – Final measure
Troon Resurfacing of Troon Esplanade (Ph.2). £220,000.00   
Complete – Final measure
Prestwick Repair / renew steps to Boydfield Gardens    Measuring works up on
site
Ayr North Provision of Bike Shelter at Lochside Community Centre    With Procurement
Ayr East Glencairn Park – footpath upgrade    Feasibility study ongoing
Ayr East Car parking provision Peggieshill Road    Feasibility study ongoing
Ayr West  Promenade raised footway works   
Feasibility study ongoing
with Professional Design
Services
Kyle Annbank Park – upgrade footpath    Feasibility study ongoing
Kyle  Construction of new footpath on Southern edge of
Collenan reservoir, 
£22,000.00  Feasibility study ongoing
Design and Flooding Section
Troon  Shore Defence Structural Stabilisation £10,000.00   On site
Citadel Footbridge
Refurbishment
Remove and renew timber deck parapet elements. 
Surface prepare and paint.  Remove or repair lighting £140,000.00   Complete – Final measure
Girvan Boating Pond
Refurbishment 
Install new stainless steel reinforced concrete base slab to
reduce water leakage. £175,000.00 
Complete – Final measure
Dunure Castle
Footbridge
Replacement 
Replace existing small span concrete footbridge with a
larger footbridge with a view and good aesthetics    £230,000.00  Ongoing.
Lighting Section
Ayr East  Glencairn Park – Install footpath lighting    Measuring works up on
site
Ayr West New Bridge & Auld Brig.  Design fees for installation of
architectural floodlighting to structures £50,000.00   Design Fee

Page 34