Official AYRSHIRE SHARED SERVICE JOINT COMMITTEE 06 June 2025 Report by the Head of Ayrshire Roads Alliance ______________________________________________________________ SUBJECT: ROADWORKS PROGRAMME 2025/26 ______________________________________________________________ Purpose of report 1. The purpose of this report is to advise the Joint Committee on the progress of work through the roads improvement programmes within East Ayrshire and South Ayrshire for financial year 2025 to 2026. Recommendations 2. It is recommended that Joint Committee: (i) Notes, the Ayrshire Roads Alliance programmed works 2025/26 (ii) Otherwise, notes the contents of this Report. Background 3. The budget allocation for East and South Ayrshire Councils Roads Investment Programme for FY 2025/26 can be seen in tables 1 and 2 below respectively. Table 1: East Ayrshire Council Roads Investment Programme 2025/26 Programme Area Budget (£m) Carriageway Resurfacing 2.305 Footway Resurfacing 0.150 Street Lighting 0.215 Traffic & Transportation incl. road safety 0.330 Active Travel 0.050 School Streets 0.050 Bridge and Culvert Strengthening (incl. road slips) 3.500 Car Parks incl. Multi-storey demolition 0.820 Fleet 0.600 Total £8.020 External Funding (Confirmed) SPT – Behaviour Change £0.385 Transport Scotland – Behaviour Change £0.116 ATIF - Tier 1 £0.758 Developer Contributions/Route Action Plans £0.396 SG – EV Infrastructure Fund £2.800 Total £4.455
Page 2
Official External Funding (To be Confirmed) Sustrans – Annick Valley Stage 2 £0.175 (Tbc.) ATIF Tier 2 - Design £2.405 (Tbc.) Road Safety Improvement Fund £0.270 (Tbc) SPT General Bus Infrastructure £0.270 (Tbc) Total £3.120 (Tbc.) Table 2: South Ayrshire Council Roads Investment Programme 2025/26 Programme Area Budget (£m) Carriageway & Footway Resurfacing 1.581 Street Lighting 0.150 Bridges Capital 0.881 Millennium and Craigholm Bridges 0.145 C12 Dunure slope stabilisation 0.130 Vehicle restraint barriers 0.073 Cattle grid renewal 0.033 Girvan Harbour Jetty repairs 0.504 Local Flood Risk Plan 0.153 Ayr Depot 0.250 Climate Changes St Ninians Park 0.255 EV Charging Infrastructure 0.281 Total £4.436 External Funding (Confirmed) SPT – Behaviour Change £0.170 Transport Scotland £0.116 Tier 1 – Active Travel Funding £0.737 ATIF–Tier 2(Dundonald – Barassie) £2.500 Ayrshire Growth Deal £0.857 Levelling Up Fund (Active Travel) £4.000 Total £8.380 External Funding (To be Confirmed) Levelling Up Fund (Burns Statue) £15.000 (Tbc. Sustrans £2.788 (Tbc.) ATIF Tier 2 - Design £1.626 (Tbc.) Road Safety Improvement Fund £0.270 (Tbc.) SPT – Bus Infrastructure Improvements £0.100 (Tbc.) Total £18.870 (Tbc.) Note: Several funding applications have still to be confirmed. The affected areas of potential funding are denoted by the use of “£Tbc.” in Tables 1 and 2 above. Main report/main issues 4. Surfacing programmes for FY 2025/26 are contained within Appendices One and Two.
Page 3
Official Capital Resurfacing 5. In East Ayrshire 1% of the carriageway resurfacing programme has been completed with some delays with the programming of the remaining works due to the need to re-tender the contract for coal tar testing which must be carried out ahead of any works. It is anticipated that this new testing contract will be issued within the next month which will allow works to be programmed and completed before the end of the financial year. 6. In South Ayrshire we have completed 20% of the carriageway programme with an anticipated completion date of October 2025. Footway resurfacing programme commences in September 2025 and with an anticipated completion date of November 2025. There has been several carriageways and footways that have tested positive for coal tar which required additional control measures to be put in place. Some locations identified for 2025/26 have been carried forward and rescheduled to 2026/27 programme. East Ayrshire Council residential road and footway repairs (Additional Revenue Funding) 7. At Cabinet on 13 March 2025, East Ayrshire Members Initiatives approved £800k revenue funding for residential and footway repairs with locations identified detailed within Appendix 2 of this report. South Ayrshire Council Ward Investment Programme 2025/26 8. Officers within our engineering disciplines continue to develop work schemes identified by Ward Members under the South Ayrshire Council Ward Investment Programme for 2025/26 as detailed within Appendix 4 of the report. Note: Sites will be further added as discussions progress with Officers and Ward Members. Timber Transport 9. Two grant funded locations in South Ayrshire for 2024/25 are now complete. 10. 5no. locations in the East and 2no. locations in the South were submitted by Officers for Timber Transport funding. All have been ranked just below the threshold limits and consequently were unsuccessful to secure funding for 2025/26. A meeting will be arranged to review our application process for when the window opens for 2026/27 applications. Street Lighting 11. Street lighting column and cable replacement programme of works which incorporates LED lanterns is detailed in Appendix 1 and 2. 12. Ayrshire Roads Alliance is actively exploring alternative procurement routes due to a further delay of Scotland Excel Street Lighting Material Framework which is hampering the completion of the LED project in the East.
Page 4
Official Electric Vehicle Infrastructure 13. The Electric Vehicle Infrastructure Fund (EVIF) programme with the number of public chargers installed to date is listed within Appendix 3 for South and East Ayrshire respectively. 14. East Ayrshire Council is the lead authority for the PAN Ayrshire Public Electric Vehicle Charging Strategy. The project has secured a grant of £2.8million and work continues on the procurement phase. Following the previously approved business case, further papers have been presented to the cabinet regarding the introduction of an EV charging tariff, which has been implemented across all three Ayrshires as of 1st January 2025. A further increase to tariff will be implemented on 1st July 2025. This tariff aims to establish a sustainable funding model and attract private investment. 15. Work continues on the tender documentation for the Pan Ayrshire concession contract with the appointment of Mott MacDonald as consultants to assist with the collation of the relevant documents required for tender. The Single Procurement Document (SPD) was issued on 3rd March 2025 for the initial stage of tendering, followed which we received numerous bids. The evaluation is currently ongoing, with the Invitation to Tender (ITT) to be published in June 2025 for the shortlisted bidders, followed by contract award in October 2025. 16. All Rapid Chargers are required under the Public Charge point regulations 2023 legislation to be able to accept contactless payment by 24th November 2024. Ayrshire Roads Alliance has secured funding from Transport Scotland Contactless Compliance Grant Funding to replace/activate/retrofit eligible CPS rapid chargers to incorporate contactless payment. Works have been carried out to replace the non-compatible units and to activate contactless terminals on compatible rapid chargers. 17. Replacement of 22kW charger at Troon Swimming Pool is approved by SAC to come from their capital fund. Replacement of 50kW chargers at Burns Statue Square, Ayr and Girvan Harbour are funded by the Contactless Compliance Funding. Structures 18. Land acquisition and/or access agreements alongside environmental license requirements continue to cause delays to a number of projects. ARA are working closely with EAC Legal/Estates and relevant stakeholders to progress these issues. 19. Appendix 2 details East Ayrshire Council Bridges Capital programme for 2025/26. Seven works contracts are near tender ready. 20. A Consultant has been appointed to carry out Principal Inspections on 437 EAC structures. These are ongoing and should be complete by end of May 2025. The internal Principal Inspection program for 2025 is underway.
Page 5
Official 21. A713 Polnessan Upper Bridge - ARA have erected temporary traffic signals due to subsidence in the carriageway. Traffic lights will remain in place until the slope has been stabilised. There has been some disruption to Windfarms and Sub- stations in the area and ARA working closely with developers to find alternative routes for their abnormal load movements. A consultant has been appointed and discussions are ongoing regarding a permanent solution. 22. B741 Coal Glen Embankments works have been awarded; however, the works have been postponed due to issues with a 132kV SPEN cable in the carriageway. ARA are in ongoing discussions with SPEN, the contractor, legal services and insurance to find a solution, works are now not likely to be completed until 2025/26. 23. B713 near Sorn road slip sheet piling works are ongoing. Works going well, programmed to be complete beginning of July 2025 24. ARA are working with EAC Legal/Estates to acquire land at West Clerkland Bridge through a Compulsory Purchase Order. The bridge has been shut to vehicular traffic since 2012 and shut to both pedestrians and vehicular traffic since 2021. 25. 3no. bridges on the A71 between the Bellfield Interchange and Moorfield Roundabout need replacement expansion joints. A consultant was appointed to explore options in removing the joints and making the structures semi/fully integral. It has been decided that in the meantime 2 joints that are repeatedly failing will be replaced with asphaltic plug joints. 26. B730/10 Littlemill Bridge land acquisition complete after years of negotiation. Tender documents to be reviewed and works put out to tender with a view to start on site in Spring 26. 27. The South Pier Quay at Girvan Harbour has been assessed to have a load carrying capacity of 0.5 tonnes per square metre. Following dive surveys undertaken earlier this year the option chosen to extend the life of the structure is steel plate repairs to the existing sheet piles and grouting of the voids. All technical contract documentation has been completed and the tender process is ongoing. It is anticipated that tenders will be issued in June with works commencing on site in August/September. 28. The detailed design of the Girvan Harbour Timber Jetty works are progressing again now that the South Pier Quay design work has been completed. Submission of the contract documentation for review is expected in July 2025 followed by the tender process in August 2025 led by East Ayrshire Council procurement. 29. The A79/30 Victoria Bridge Concrete Repairs and Painting on site work is currently paused. The Marine Licence 28 day consultation process is ongoing
Page 6
Official and will be concluded on the 21st May 2025. It is expected that determination of the Marine Licence will take place soon afterwards, allowing the work to continue. 30. Girvan Harbour dredging. Funding has been secured from SAC to carry out the first phase of dredging in 2025/26to re-establish full operational status for the RNLI lifeboat. Dredging will be carried out in two areas to ensure the RNLI lifeboat can operate at all tides. Area 1 is in the main channel where a 15m wide x 181m long dredge will take place to 1.5m below chart datum. Area 2 is at the RNLI Pontoon where a 15m wide x 43m long dredge will take place to 1.5m below chart datum. All dredge material will be taken on shore and disposed at landfill. Discussions are ongoing with SEPA and Marine Scotland to establish if any works can be carried out prior to the end of the bathing restrictions in mid September. 31. Ayr South Pier. In May 2022 ARA and South Ayrshire Council agreed a procedure for the inspection of Ayr South Pier as there did not appear to be an inspection regime in place for this significant piece of Ayr Common Good infrastructure. A key element of the procedure is that : “South Ayrshire Council, Asset Management and Community Asset Transfer – Housing, Operations and Development Directorate are the owner of the asset, responsible for liaison with the Ayrshire Roads Alliance and funding / carrying out repairs” 32. A key type of inspection detailed in the procedure is underwater inspection by divers and to this end a 2024/25 Business Case submitted for Capital funding to employ a consultant to carry out an underwater dive survey and structural assessment was submitted. This was not accepted as the asset was Ayr Common Good. A dive survey and assessment requires to be carried out soon and we need to find a way of making this happen. No alternative method of funding has been identified which is a matter of concern. 33. On the 3rd February 2025 a sink hole was reported which had developed at the land end of the South Pier in a verge area. Emergency repairs were required immediately and follow up repairs are needed highlighting the importance of a dive survey and assessment. Funding is being sought for this. Traffic & Transportation 34. Active Travel Infrastructure Tier 1 grant funding has been received from Transport Scotland. Active Travel projects using the Tier 1 funding is currently in development, and will be implemented over the course of the current financial year. 35. There was a reported underspend in EAC of £170k in 24/25 which has been carried forward and the associated delayed projects have been included in this years project list contained in Appendix 2. 36. Confirmation of the Road Safety Improvement Fund grant allocations is pending but it is anticipated that this years allocation for EAC will be in the region of £300k
Page 7
Official and for SAC £219k. Schemes are currently being identified and prioritised and the schemes listed in the appendices may be subject to change pending Transport Scotland approval. 37. The Kilmarnock Bus Station refurbishment programme is now complete and a new cleaning and inspection regime has been implemented. Additional funding has been allocated this year for upgrades to Cumnock Bus Station which include changes to materials and the installation of a public address system. Ayrshire Growth Deal (AGD) Roads Projects 38. The three Ayrshire Councils have worked in partnership with other agencies, communities and businesses to secure the first Regional Growth Deal in Scotland. This will see £251.5 million of investment in key assets and key sectors across Ayrshire. 39. There are currently no transport projects within the Ayrshire Growth Deal proposed for East Ayrshire Council however the Ayrshire Roads Alliance recognise the strategic importance of Bellfield Interchange and will continue to work with colleagues to secure the improvements required. 40. By carrying out extensive modelling of the existing road network around Glasgow Prestwick Airport/Ayrshire Growth Deal cluster and building on the LDP2 no net detriment approach the Ayrshire Roads Alliance was able to stress-test the road network and identify the following improvements which will reduce peak congestion, build capacity into the network to facilitate future growth, improve road safety and journey time reliability. Project Location 1 Sandyford Toll Roundabout capacity improvements 2 Dutch House Roundabout capacity improvements 3 Monktonhead Roundabout capacity improvements 4 A79/Station Road Roundabout capacity improvements 5 Shawfarm Road Roundabout capacity improvements 6 Shaw Road/Shawfarm Road junction re-alignment/improvements 7 Active Travel links from existing network to AGD Commercial Build 8 Public Transport Infrastructure improvements 41. Project 7 & 8 compliment the project currently being progressed under the de- carbonisation of the road network being developed by the Ayrshire Roads Alliance and funded by the successful Levelling Up Fund round 3 award. 42. A Case for Change has been submitted to Scottish & UK Governments seeking approval of the changes noted above and also the Prestwick Proposition, the Ayrshire Roads Alliance will assist in the delivery of all these projects for South Ayrshire Council.
Page 8
Official Levelling Up Fund 43. South Ayrshire Council successfully secured £20million of funding from the Levelling Up Fund (LUF) round 3, £16million of this funding will be utilised to redevelop Burns Statue Square with the remaining £4million allocated to Active Travel. East Ayrshire Council were unsuccessful in securing funding in round 3 to improve the Bellfield Interchange. 44. Burns Statue Square is a key initiative emerging from the Town Centre Framework, it is a priority project to support placemaking and make the town a more successful place to live, work, visit and enjoy. The project’s purpose is to reshape the southern entrance to the town centre as a new attractive and appealing gateway, involving rationalisation/ realignment of road carriageways to create opportunity for more useable, connected, pedestrian friendly, high quality public realm space and arrival point. The Ayrshire Roads Alliance procurement are exploring the potential of usingthe SCAPE Framework to direct appoint Balfour Beattie to deliver the project on a Design & Build basis due to the fixed budget and completion deadline of 31st March 2027. 45. The Ayrshire Roads Alliance will construct a new Active Travel Route linking Dundonald to Barassie Station & improve the existing NCN7 from Prestwick to Barassie railway stations. These improvements, which are being funded by Active Travel Infrastructure Tier 2 funding will compliment further active travel routes which will be delivered as part of the Ayrshire Growth Deal. Active Travel 46. ARA submitted several applications to the Active Travel Infrastructure Fund 2025/26, £5.7m of construction funding in East Ayrshire & £2.878m of construction funding in South Ayrshire was unsuccessful. We await a decision on the remaining applications for design funding. 47. A total of £787,000 has been secured for SPT & TS to deliver a behaviour change programme in both South & East Ayrshire, projects including the re- establishment of the Active Travel Hub in South Ayrshire, phase 1 construction of an active travel innovation centre in East Ayrshire and support to the Cumnock EV Car share project. Ash Dieback 48. Following reports to Cabinets in East Ayrshire and South Ayrshire, surveys and works are ongoing with 28-day notices being issued to owners and any objections received referred to legal service. A detailed update report will be presented to Joint Committee later in the year.
Page 9
Official Implications 49. Implications Yes No Paragraph number in report 1. Policy/Strategic Planning x 50 & 51 2. Governance x 52 3. Human Resources x 53 4. Equality and Fairer Scotland Duty x 54 5. Financial x 3, 55 & Appendix 1, 2 and 4 6. Risk x 56 & 57 7. Community Wealth Building x 58 8. Net Zero x 59 Policy/strategic planning implications 50. A well-maintained road network will contribute to achieving the 2015-2030 Community Plan objectives and associated 2021-2024 Delivery Plans 51. The matters referred to in this report contribute to Priority 1 of the South Ayrshire Council Plan: Spaces and Places/ Moving around and the environment (Outcome 1). Governance implications 52. By virtue of the relevant statutory provisions, principally detailed within the Roads (Scotland) Act 1984, the Council as local roads authority is required to manage and maintain all publicly adopted roads within its area other than those which are maintained and managed by the Scottish Ministers. Human resources implications 53. The work programmes have direct impact on human resources and the Alliance will ensure all works are suitably resourced to maintain satisfactory progress. Equality impact and Fairer Scotland duty implications 54. Equality Impact and Fairer Scotland Duty screening assessments will be undertaken annually as required during the planning stage prior to the delivery of the programme of works. Financial implications 55. The Ayrshire Roads Alliance will deliver the strategic and local services as stated in the Service Plan. The budget is provided by East Ayrshire Council, South
Page 10
Official Ayrshire Council, and other external organisations. Appropriate scrutiny arrangements are in place to manage these budgets. Risk implications 56. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every Joint Committee. 57. The Works Programmes, Service Plan and the Risk Register do not expose either Council to an increased risk as they have been developed from existing budgets and existing service commitment. Community Wealth Building implications 58. The works programme provides economic levers to develop resilient, inclusive local economies with more local spend and fair employment, as well as ensuring that wealth is more locally owned and benefits local people. Net zero implications 59. The Ayrshire Roads Alliance Service Plan and Carbon Strategy supports and links to East Ayrshire Climate Strategy Themes Theme 2: Transport Theme 4: Natural Environment Appendices Appendix 1 - South Ayrshire Council Programme of Works 2024/26 Appendix 2 - East Ayrshire Council Programme of Works 2025/26 Appendix 3 – EV Public Chargers Appendix 4 - South Ayrshire Council Ward Investment Programme 2025/26 Background papers • East Ayrshire Council – 2025/26 Road Asset Management Plan. Investment and Programme • South Ayrshire Council – Road Improvement Plan 2025 - 2026 Person to contact. Jane Corrie, Head of Roads - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail. jane.corrie@ayrshireroadsalliance.org Implementation Officer Craig Knape, Strategic Manager - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail. craig.knape@ayrshireroadsalliance.org
Page 11
Official Appendix 1 South Ayrshire Council – Programme of Works 2024/26 Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2024 to 2026 [Works carried forward from 2023/24] Route No Town Road Name Works Description Sch eme Sco re Estimated Cost Cost to Date Variance +/- Comments B734 Old Dailly Barr Old Dailly Old Dailly to Penkill + drainage improvements N/A £150,813 £163,932 -£13,119 Complete B7035 By Girvan Glendoune Houdston Road (Coalpots) Braetoll South + S Power shut down N/A £200,000 £206,251 -£6,251 Complete B743 By Mossblown Ayr / Mossblown? West from Brocklehill Farm 53 £249,002 £249,239 -£237 Complete C37 Auchincruive Barrackhall Gibbsyard 48 £123,861 123,873 -£12 Complete Uncl Tarbolton Springfield Road Garden Street to No 50 46 £54,275 £53,851 +£424 Complete B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton By Holebogs, S bend 59 £445,000 £440,506 +£4,494 Complete B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton From A70 at Hillhead south to C21 Craigs Road junction 56 B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton From Meadowhead Depot entrance south-wards 55 Complete B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton Bridge of Coyle to C2 52 B744 Annbank Weston Brae Full Length 53 £152,000 £207,822 -£55,822 Complete B744 Annbank Browns Crescent Weston Avenue Full Length Craighall Way to 101 Weston Avenue 53 56 U77 By Coylton Hole Road Full Length 46 £82,867 £83,064 -£197 Complete B7023 Maybole Crosshill Road Full Length 56 £74,687 £72,215 +£2,472 Complete Complete Complete B7023 Maybole St Cuthbert's Road Full Length 53 £30,669 £41,792 -£11,123 B7024 Maybole Alloway Road Redbrae to Bypass 51 £55,922 £96,288 -£40,366
Page 12
Official C122 By Maybole C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole School to new Bypass Ladycross to new Bypass 50 £58,095 £58,097 -£2 Complete B7023 Maybole Ballochbroe to Crosshill Dalhowan to C58 £275,435 £362,350 -£86,915 Complete A719 PH 2 By Maidens By Dunure Pennyglen/B7023 - Kirkoswald Road/Maidens, Maidens A719 Smithy Bridge/Dunure - Croy Brae, Dunure B7023 Enoch Lodge -Caravan Park Cemetery to Drumshang 67 £281,669 £326,746 -£45,077 Complete Complete A719 PH 1 By Maidens Pennyglen/B7023 - Kirkoswald Rd & Turnberry Rd /Maidens, Turnberry Morriston Farm to Jct Blawearie Maidens to Turnberry 56 £441,666 £540,857 -£99,191 Uncl Maybole Ashgrove Avenue Full Length £88,954 £102,985 -£14,031 Complete Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – New Sites identified for 2024 to 2026 B749 Troon Monktonhill Road Southwood jct to Isle of Pin 59 £210,000 £265,328 -£55,328 Complete. after excavation, additional material was required to regulate due to sand & soft spots localised to lots of areas in Troon B749 Troon Craigend Road Fullarton Drive railway bridge to South Beach 48 £167,500 £201,706 -£34,206 Complete Overspend same as Monktonhill Rd
Page 13
Official B749 Troon South Beach Lochend Road to Academy Street jct 54 £200,000 £307,540 -£107,540 Complete. Overspend same as Monktonhill and Craigend. C44 Dailly Dailly to Turnberry Farden 500m towards Drummock 39 £112,560 £71,137 +£41,422 Complete B7027 Barr Knowe Road Lochtonmill southwards £63,000 £53,406.44 +£9,593 Complete B734 Colmonell Colmonell to the A77 £106,560 £150,273 -£43,713 Complete B7023 Maybole C58 to Cemetary £297,606 £271,503 +£26,102 Complete A70 C39 Coylton Ayr Joppa Doonholm Road Hole Road jct to Pharmacy Alloway to The Loaning 35 43 £179,321 £155,377 +£23,944 Complete C145 Ayr Hillfoot Road Holmston Rd to Holmston Dr 54 £91,875 £123,733 -£31,858 Complete Uncl Maybole Queens Terrace/Chesney Grove/Kincraig Avenue Full Road 33 33 £166,275 £174,448 -£8,173 Complete Uncl Maybole Cargill Road Full Road 47 £46,900 £48,224 -£1,324 Complete C1 (STTS) Straiton Newton Stewart Road U8 towards Straiton to U57 44 £120,400 £119.293 +£1,107 Complete B7045 (STTS) Maybole Cassilis to Kirkmichael Rd Crorieshill Farm northwards for 360m 44 £46,750 £51,700 -£4,950 Complete Uncl Ayr Saltpans Road North from Glebe Road 46 £112,249 £118,940 -£6,691 Complete Uncl Prestwick Morris Road Full Road 43 £55,000 £107,345 -£52,345 Complete (positive for coal tar increased costs) Uncl Ayr Green Street Waggon Road to Crown Street 42 £130,000 £214,584 -£84,584 Complete (positive for coal tar increased costs) Uncl Prestwick Craigie Street Full length 39 £30,000 £36,725 -£6,725 Complete
Page 14
Official B744 By Annbank B744 Belston/A70 - Weston Avenue/Annbank, Ayr Auchincruive Junction to Glenview 52 £120,000 £139,872 -£19,872 Complete B742 By Maybole Dalrymple to Barnford Farm Dalrymple Road 46 £130,000 £138,058 -£8,058 Complete Uncl Maybole Hicks Avenue Full cway & fway 30 £104,000 £133,263 -£29,263 Complete Increased estimate due to combining footway, kerbing, carriageway resurfacing C59 Colmonell Craigneil Road B734 to Bridge £67,000 £53,129 +£13,871 Complete Uncl Ayr Peggieshill (PH1) Dalmilling Rd to Nursery Rd 44 £92,000 £99,038 -£7,038 Complete Uncl Ayr Kincaidston (PH1) Marigold Sq to Honeysuckle Park 52 £185,000 £181,768 +£3,232 Complete Uncl Girvan Louisa Drive Knockcushion St to Duncan St £103,640 £91,410 +£12,230 Complete Uncl Ayr Peggieshill Rd (PH2) Nursery Rd to Fenwickland Ave 44 £100,000 £33,739 Complete Awaiting final measure C74 By Ayr MacNairston Rd C105 to B742 junction 52 £97,608 £22,467 Complete Awaiting final measure B742 By Maybole Nether Culzean Dalrymple Rd Barnford farm to Nether Culzean 42 £135,000 £20,084 Complete Awaiting final measure Uncl Ayr Ellisland Square (Contains Coal Tar) Full Length 42 £125,000 2nd-13th June ‘25 Uncl Ayr Kincaidston Drive (PH2) Honeysuckle Park to Dalmellington Rd 52 £300,000 30th June – 25th July ‘25 Mossblown Sandyford Road From a point 180 metres east of A719 junction eastwards for 680m 53 £140,700 19th – 30th May ‘25 Uncl Ayr Dalmilling Road (Contains Coal Tar) Harthall to Mainholm Rd 37 £275,000 28th July – 16th Aug ‘25 Uncl Prestwick Bellevue Road (TO BE TESTED) From Main Street to Adamton Road £38,039 8th Sept – 3rd Oct ‘25 Uncl Girvan Todd Street (TO BE TESTED) Full length 31 £32,894 28th July – 8th Aug ‘25 Uncl Girvan Fauldribbon Road (TO BE TESTED) Full length 34 £31,813 11th-22nd Aug ‘25 Uncl Girvan B741 Linfern Road (TO BE TESTED) NO.79 to no.3 near Main Street 29 £100,517 22nd Sept – 6th Oct ‘25 Uncl Maybole Carrick Street (TO BE TESTED) Ladyland Rd to B77 33 £26,130 25th Aug – 8th Sept ‘25
Page 15
Official Uncl Maybole Wellington Street (TO BE TESTED) Ladyland Rd to Carrick St 30 £18,090 1st-15th Sept ‘25 Uncl Maybole Manse Street (TO BE TESTED) Drumellan St to Abbott St £20,100 8th-22nd Sept ‘25 Uncl Girvan Hamilton Street (TO BE TESTED) Church Sq to Bridge St 46 £49,655.55 13th-24th Oct ‘25 Uncl Ayr Chapel Park Road Full length 40 £55,984 2026/27 Uncl Prestwick St Cuthbert’s Rd St Andrew’s Ave to Kirklandholm £38,587 2026/27 Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2024 to 2026 [Works carried forward from 2023/24] C17 Tarbolton Westport Footway North side 28 £17,370 £24,984 -£7,644 Complete Uncl Prestwick Hunters Avenue South from Heathfield Road, west side 23 £7,500 £5,393 +£2,107 Complete Uncl Troon Morven Drive Cessnock Rd to Dundonald Rd (Northside) £15,072 £28,820 -£13,748 Complete C151 Dailly Woodside Both sides from Back St and Hadyard Terr 30 £20,400 £17,147 +£3,253 Complete Uncl Crosshill Newton Street Church Side of road 30 £15,795 £14,440 +£1,355 Complete Uncl Dailly Hadyard Terrace Inside footway + part outer section 28 £54,400 £20,110 +£34,290 Complete Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for 2024 to 2026 Uncl Mossblown Martin Avenue Mossblown 28 £28,300 £30,829 -£2,529 Complete B744 Annbank Weston Brae Full Length 28 £10,700 £5,761 +£4,939 Complete B730 Dundonald Drybridge Road Bowling Green to Kilnford Dr 28 £19,223 18TH Aug – 5th Sept ‘25 Uncl Ayr Bellevue Crescent Full Length 34 £37,800 TBC - tree inspection required Uncl Maidens Ardlochan Road Full Length 30 £21,000 24th-31st Oct ‘25 Uncl Dailly Church Crecent Odd numbers full length 30 £16,800 3rd-21st Nov ‘25
Page 16
Official Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget allocation B743 Mossblown Mauchline Road Fourways to railway bridge north side 28 £15,300 2026/27 Uncl Ayr Lochpark Slab replacement 23 £20,425 2026/27 Ayrshire Roads Alliance - Lighting Programme 2025/26 Town Location Work Type No of columns Estimated Programme Cost Comments Variance +/- Ayr Ayr - Old Hillfoot Road, Hillfoot Crescent & Souter Place Old steel columns & unreliable 5th Core 5 £30,000 Remedial works to complete Ayr Cunningham Crescent & Area Unreliable 5th Core Supplies 16 £40,000 Final Measure to complete Troon Concrete Column Replacements Ph3 Old deteriorated concrete columns 43 £55,000 £125,000 Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26 (i) Road Safety Programme Town/Route Location Proposed Scheme Progress Various Various locations Various schemes (TBC), anticipated to include: • Route Action Plan for the B743 at St Quivox; • B743 review at Failford Bridge; • Speed reduction measures at Coalpots Road at The Avenue; • Bradan Road, Troon – enhanced crossing points; Development of a finalised programme for the current financial year will follow confirmation of any grant award from Transport Scotland’s Road Safety Improvement Fund (RSIF).
Page 17
Official (ii) Safer Neighborhoods Town Location Proposed Scheme Progress Phase 4 20mph schemes Various roads (TBC) 20mph speed limit schemes Discussion with SAC required to identify appropriate settlements for inclusion in Phase 4. Various Various locations Vehicle activated signs upgrade Pending implementation of new contract, and extents of upgrades will be subject to budget. (iii) Rural Route Action Plans Route Location Proposed Scheme Progress B743 Between the A77(T) and Auchincruive (St Quivox) TBC Listed under RSIF schemes above – subject to confirmation of funding. (iv) Active Travel Infrastructure – ATIF & Sustrans Town Location Proposed Scheme Progress Various Various locations • Various smaller schemes under Tier 1 funding, details TBC. The ARA are currently developing a package of schemes to be progressed during the current financial year making use of the Tier 1 grant award. Loans From Buchan Road to the A759 Loans to Troon Phase 3 Funding application unsuccessful, new application submitted to ATIF for 2025/26 Loans From Dundonald Road to Buchan Road Loans to Troon Phase 2 £24,500 received to install permanent monitoring equipment Dundonald To the northern side of the A759 Dundonald to Barassie Phase 1 Award received to treat Japanese Knotweed on-site, full construction • Road Safety scheme, Links Road, Prestwick.
Page 18
Official funding application submitted to ATIF for 2025/26. Various Various Various Funding application unsuccessful, new application submitted to ATIF for 2025/26 Girvan Quay to Grangeston Girvan to Grangeston £27,378 received to complete RIBA Stage 1, Ayr Town Centre Accessible Ayr £778,780 received to complete RIBA Stage 4 of Route 1 Phase 1 Ayr-Girvan Ayr to Girvan Culzean Way £47,755 received to complete RIBA Stage 1 Coylton Coylton Primary Access for All – Coylton £27,378 received to install permanent monitoring equipment Ayr, Prestwick & Troon NCN7 NCN Barrier Removal £113,500 received to remove barriers from the NCN7 in Ayr Prestwick & Troon to make the route inclusive. Prestwick, Troon & Barassie NCN7 from Prestick Station to A759 Barassie Prestwick to Barassie £82,979 received to complete RIBA Stage 2 Dundonald Junction of A759/B730 Dundonald Cross £80,000 received to install signals at the junction of the A759/B730 Ayrshire Roads Alliance - Structures Capital Programme 2025/26 [Includes works carried forward from 2023/24/25] Description Work Type Estimated Programme Cost Comments Variance +/- A79-30 Victoria Bridge Concrete Repairs and Painting £432,776 Ongoing -£432,776 A79-40 John Street, Ayr, Railway Bridge Parapets £362,000 Design Phase. -£294,580 FB.AYR-70 River Doon Cycleway Footbridge (Millenium Br) Refurbishment £145,000 Design Phase -£145,000 U740-10 Barbieston Bridge Replacement Design £86,820.00 Design Phase 50% - 50% EAC / SAC funded project as this is a boundary bridge. -£86,820.00 Various Locations Vehicle Restraint Barrier Renewal £50,000 Design Phase +£50,000 Various Locations Cattle Grid Renewal Programme £33,600 Design Phase £-33,600
Page 19
Official C12 Dunure Station Road Dunure, Slope Stabilisation £130,000 Design Ongoing, Construction Planned 2023/24. A 70m long gravity retaining wall option has been selected as the most optimum solution. Detailed design and contract preparation is currently underway, however the capital budget currently available for this project is insufficient for the proposed solution. An additional funding solution has been identified but has not been presented to or approved by SAC Panel. -£130,000 Girvan Harbour Girvan Harbour South Pier Repairs £136,000 The South Pier Quay has been assessed to have a load carrying capacity of 0.5 tonnes per square metre. Following dive surveys undertaken earlier this year the option chosen to extend the life of the structure is steel plate repairs to the existing sheet piles and grouting of the voids. Completion and submission of the contract documentation was delayed in order that the significant damage caused to the South Pier Quay by the Q-Varl boat, when it broke its moorings in a storm, could be assessed and any repairs required could be included in the contract documents. The contract documentation has been completed and it is anticipated that tenders will be issued in June with works commencing on site in August/September 2025. -£120,759 Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles £504,887 The sediment transfer model has been completed including options to deal with the defective sheet piling. The recommended option is to remove all existing sheet piling then replace only that on the curved section from the lifeboat station. The design and contract preparation is progressing on this basis and is programmed to be completed by July with the tender process commencing in August 2025. -£504,887 £1,881,083
Page 20
Official Appendix 2 East Ayrshire Council Ayrshire Roads Alliance – Carriageway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 ROAD LOCATION Estimated Cost Cost to Date variance +/- Comment A71 Dual Carriageway From Moorfield Roundabout – Target Worst Sections £300,000.00 Programmed to commence on 02/08/25 A736/U20 Junction Contribution to North Ayrshire to complete EAC section Junction Contribution to North Ayrshire to complete EAC section £15,000.00 To be programmed A735 From Lochridge House North Entrance to Windmill factory Farm £182,354.25 To be programmed A735 Rigg Street Stewarton From B778 to Brown Street £60,606.00 To be programmed B7046 Skares From Junction Newfield Rd to Recycling Centre Additional section into Skares £116,000.00 Programmed to commence on 16/06/25 B769 Stewarton From Stewarton to North Ayrshire Boundary £219,375.00 To be programmed B743 Mauchline High Street From A76 to Loans (School) £52,680.60 To be programmed B7037 Titchfield Street Galston From Mini Roundabout to Orchard Street £97,500.00 To be programmed B7038 Kilmarnock Campbell Street From: Fire Station AC / To: Willock Street £41,595.40 To be programmed C3 Barskimming Road Mauchline From Loudoun Street to StationRoad £74,074.00 To be programmed C108 Stewarton From Greensland to Boundary £114,750.00 To be programmed C22 Coal Road Auchinleck From Railway bridge to Barbieston Road £35,612.50 To be programmed U55 Galston From U56 approx 1000m Westwards £78,750.00 Complete - final measure Kilmarnock New Mill Road From Chapmans Terrace to end £45,584.00 To be programmed
Page 21
Official Kilmarnock Whatriggs Road From Tinto Avenue to Haining Avenue £35,612.50 To be programmed Kilmarnock East Shaw Street From Lidle to and around mini roundabout £37,814.00 To be programmed Kilmarnock Bentink Street On Approach to Mini roundabout £20,797.70 To be programmed Kilmarnock Bellsland Grove Full Length £19,080.00 To be programmed Kimarnock Beech Avenue From Portland Road to Larch Place £84,501.40 To be programmed Kilmarnock Pine Road Full Length £42,022.75 To be programmed Kilmarnock Old Irvine Road From Lindsay Street to Grange Street £37,464.35 To be programmed Kilmarnock Brackenhill Avenue Full Length £32,323.20 To be programmed Kilmarnock Arran Avenue Full length £36,182.30 To be programmed Kilmarnock Lainshaw Avenue One Section £71,225.00 To be programmed Kilmarnock Townend Full Length £27,065.50 To be programmed Stewarton Avenue Square Access Road into car park £11,396.00 To be programmed Kilmaurs East Park Crescent Full Length £34,045.55 To be programmed Galston Western Road Outside Primary School £29,487.15 To be programmed Hurlford Mayfield Avenue Full Length £57,855.42 To be programmed Fenwick Skernieland Road From Old A77 Slip to Rysland Terrace £44,053.31 To be programmed Cumnock Hearth Road Full length £89,909.25 To be programmed Drongan Lane Crescent Full Length £27,195.00 To be programmed Bellsbank Corserene Terrace Full Length £29,526.00 To be programmed Dalmellington Gateside Road Broomknowe to B741 £31,080.00 To be programmed
Page 22
Official Dalrymple Cedar Terrace Full Length £15,540.00 To be programmed Drongan Mill o Shield Road From Coyle Avenue and Garrowhill Drive £37,749.25 To be programmed Ayrshire Roads Alliance – Footway Structural Maintenance Programme 2025/26 incl works carried over from 2024/25 Ayrshire Roads Alliance - £800k Residential Carriageway/Footway Improvement Programme 2025/26 WARD Location Estimated Costs Cost to Date Variance +/- Comment 1 Carriageway - Stewarton Dornie Close £9,120.00 To be programmed 1 Carriageway - Stewarton Braemore Road £11,310.00 To be programmed 1 Carriageway - Stewarton Kirkmuir Drive £54,000.00 To be programmed FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment Catrine - Newton Street Outside School £7,290.00 To be programmed Auchinleck - Main Street From Surgery to Council Car Park £21,870.00 To be programmed Cumnock - Glaisnock Road Outside Cemetery £19,044.00 To be programmed Kilmarnock - Dundonald Road Outside School £16,200.00 To be programmed Kilmarnock - Gilmour Street Various Locations £21,060.00 To be programmed Stewarton - High Street From Old Bank to Church £16,200.00 To be programmed Stewarton - Lainshaw Street Standalane to Sainsbury’s Rear Entrance £19,260.00 To be programmed Fenwick - Skerniland Road Both Sides £22,680.00 To be programmed Galston - A719 Opposite Loudoun Academy From Nursing Home to Barriered Section £8,100.00 To be programmed
Page 23
Official 2 Carriageway - Kilmarnock Tourhill Road £5,580.00 Complete – final measure 2 Carriageway - KilmarnockAuchencar Drive £15,120.00 Complete – final measure 2 Carriageway - KilmarnockWardneuk Drive £6,165.00 Complete – final measure 3 Carriageway - Kilmarnock Woodside Avenue £60,000.00 To be programmed 4 Carriageway - Kilmarnock - Anderson Place/Bannerman Drive and Drummond Place £46,200.00 To be programmed 4 Carriageway - Kilmarnock Sparrow Gardens £12,960.00 To be programmed 5 Carriageway - Kilmarnock Simonsburn Road £9,225.00 To be programmed 5 Carriageway - Kilmarnock Elderslie Crescent/Ayr Road £13,500.00 To be programmed 6 Carriageway - Newmilns Sheilds Road £28,050.00 To be programmed 6 Carriageway - Darvel West Donnington Street £16,800.00 To be programmed 6 Carriageway - Darvel Jaimieson Road £17,400.00 To be programmed 7 Carriageway - Mauchline Clarinda Crescent £23,100.00 To be programmed 7 Carriageway - Mauchline East Park Avenue £25,560.00 To be programmed 7 Carriageway - Mauchline Southpark Avenue £7,800.00 To be programmed 7 Carriageway - Mauchline Welton Road £19,950.00 To be programmed 7 Carriageway - Mauchline Mansfield Road £43,500.00 To be programmed 8 Carriageway - Cumnock Latta Crescent £20,010.00 To be programmed 8 Carriageway - Cumnock Nans Terrace £16,500.00 To be programmed 8 Carriageway - Cumnock Lorimer Crescent £44,550.00 To be programmed 8 Carriageway - Cumnock Hearth Place £24,000.00 To be programmed 8 Carriageway - Cumnock Bank Avenue £21,420.00 To be programmed 8 Carriageway - Logan Holmhead Crescent £36,600.00 To be programmed 8 Carriageway - Logan Dixton Avenue £21,690.00 To be programmed 9 Carriageway - New Cumnock Castlemains Avenue £42,000.00 To be programmed 9 Carriageway - Dalmellington Church Hill/Melling Terrace £36,330.00 To be programmed 9 Carriageway - Dalmellington Knowehead £41,820.00 To be programmed 9 Carriageway - Ochiltree Gallowlee Avenue £20,490.00 To be programmed 4 Footway – Hurlford Furnace Court £15,750.00 To be programmed 6 Footway – Galston Bridge Street £3,750.00 To be programmed 6 Footway – Darvel Glen Crescent £17,500.00 To be programmed
Page 24
Official Ayrshire Roads Alliance - Lighting Capital Programme 2025/26 Town Location Work Type No of columns Estimated Programme Cost Comments Variance +/- Dalmellington Riecawr Ave, Area. Unreliable 5th Core. 22 £65,000 Scheduled 12 May 2025 Galston Maxwood Road. Unreliable 5th Core/Concrete columns. 10 £30,000 Scheduled 23 Jun 2025 New Cumnock Highpark Ave, Area. Unreliable 5th Core/Concrete columns. 19 £60,000 Stewarton Lothian Rd, Area. Unreliable 5th Core 23 £60,000 £215,000 Ayrshire Roads Alliance - LED Lighting Programme Update 2025/26 [Works carried over from 2024/25] Town Lantern Amount Status Delivery / start install Install complete by Kilmarnock - Central 1400 In progress Mar 2024 Mar 2026 East Ayrshire - Decorative 350 75% complete tender to be awarded for next stage Mar 2026 Ayrshire Roads Alliance - LED Lighting Programme 2025/26 Programme completed conversions to date 15,267 Replacement programme 97% complete Overall LED units completed 20,910 LEDs now 98% of total EAC inventory
Page 25
Official Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2025/26 Structure Reference Structure Name Proposed Works 2025/26 Estimate Comments Bridge Strengthening and Replacement A71/280 C80 Mathews Burn Culvert West Donnington St, Darvel Slab Replacement £250,000 Internal design ongoing. U751/10 Crossflats Bridge Replacement £40,000 Awarded to consultant to design replacement. Temporary bridge will be required during the works. U760/00 C93 Glenhead Bridge Replacement £60,000 Internal design ongoing, near tender ready. U740/10 Barbieston Bridge Replacement £60,000 SAC leading design. Award to consultant. Road Slips B713 South of Sorn £400,000 Works ongoing. Programmed completion 4th July 25. B741 Coal Glen Embankment Slip Remediation Works £690,000 Discussions ongoing with contractor and SPEN. U13 Aitket Road Slip Remediation Works £500,000 Near tender ready. Site clearance complete. A713/60 C61 Polnessan Upper Bridge Culvert Extension £500,000 Detailed design ongoing. Upgrade Works Identified from Inspections B705/10 C91 Cowan Place Culvert Part Replacement/Scour Repairs £60,000 Near tender ready. A70/130 W31 Thornwood Wall, Lugar Replacement £500,000 Near tender ready. Discussion regarding requirement for road closure ongoing. A736/60 C84 Lochridge Culvert Masonry and Drainage Repairs £70,000 Near tender ready. A71 Riccarton Viaduct Refurbish - expansion joint removal/replacement £100,000 Design ongoing to replace 1 failing expansion joint with asphaltic plug joints. Works to be carried out ASAP.
Page 26
Official A71 River Irvine Bridge Refurbish - expansion joint removal/replacement Design ongoing to replace 1 failing expansion joint with asphaltic plug joints. Works to be carried out ASAP. C85/10 Fenwick Bridge Masonry Refurbishment £40,000 Award to consultant to progress with assessment and detailed design. U729/00 C64 Hayholm Bridge Masonry and Scour Repairs £60,000 Internal design ongoing. C95/10 Furnace Road Bridge Arch Stregthening £100,000 Awaiting PI report from consultant. Internal design ongoing. Parapet Upgrades A70/110 Causeyhead Bridge Parapet Repairs £60,000 Discussions ongoing regarding options to reduce disruption at Dumfries House. A736/50 Bloak Road Bridge Parapet Repairs £30,000 NAC/EAC boundary, EAC progressing design. Other Various Investigative Works Topographical Survey, Paint Inspection etc £8,000 Annual cost of surveys/inspections. Principal Inspection Consultant Fees £100,000 Consultant fees for 24/25 PI’s Various Low Bridge Signage Sign Upgrades £40,000 Upgrades to signage at 6 bridges with low head room. Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2025/26 Funding Source Project ID Location Project Description Detail Progress Allocation EAC Capital Road Safety Budget: £200,000 (£198,000 Road Safety + £2,000 Safer Neigh.) 22.23 A71 / Campbell Street Off Slip, Kilmarnock Junction signalisation Installation of new traffic signals, stopping up of Willock Street and new carriageway layout to improve capacity Final junction designs from traffic lights contractor still pending. Implementation pushed back to Jul/Aug 25. £105,000
Page 27
Official 22.50 B741 Dalmellington to New Cumnock Road safety review General route review to identify safety measures Driven survey along rural section to be completed. Ongoing. £2,000 22.38 Glaisnock Street, Cumnock Traffic calming Speed reduction/traffic calming measures Design works started - Late 25/26 for completion £15,000 22.15 VAS signs, various location Upgrades and new installations New contract to be implemented In progress £10,000 23.09 B769 Kingsford Speed limit and traffic calming Appraisal Late 25 for construction works £25,000 24.05 Various Traffic calming Speed surveys Ongoing £10,000 25.03 / 25.16 Various Road safety improvements HFS Schemes Ongoing £33,000 Road Safety Improvement Fund Budget: £300,000 (TBC) 24.20 B751 - Kilmaurs to Fenwick Route Review General route review, VAS improvements, Road Markings and Signage, Studs Ongoing design works with Construction expected Sept 25 £125,000 25.11 A71 – Priestland Safer system improvements Vehicle restraint barriers Design work ongoing with Construction expected early 26 £75,000 25.13 Waterside Road Safety improvements VAS improvements , HFS and carriageway studs Design work ongoing with Construction expected early 26 £50,000 25.17 A70 – Dumfries House Road Safety improvements VAS improvements , HFS and carriageway studs Design work ongoing with Construction expected early 26 £50,000 Rural Route Action Plans Budget: £359,000 £134,000 (EAC) + £225,000 (Dev. Contributions) 22.08 B778 Stewarton to Fenwick Road alignment improvements at three key locations Agreement to proceed with site 1 improvements Process started £359,000
Page 28
Official Tier 1 Budget: £758,000 22.13 Grougar Road, Crookedholm Pedestrian crossing and road widening Installation of new crossing and layby Start date pushed back to Spring 25 £90,000 23.07 Strawberrybank Road, Kilmarnock Pedestrian crossing Appraisal for new crossing point Ped counts low so project reduced to consideration of ped refuge island £10,000 23.10 St Germain Street, Catrine Pedestrian safety improvements Installation of bollards and TRO In progress £10,000 N/A Kilmarnock Green Infinity Loop Cycling Infrastructure Route 1 & 2, Sturrock St and MSCP Route 1 & 2 design placed on hold due to lack of funding, MSCP site redevelopment application submitted to ATIF 2025/26. Sturrock St modelling completed. £100,000 24.18 A759 West of Gatehead Pedestrian improvements Footway designs and build out Design work ongoing with Construction expected early 26 £30,000 25.15 B751 Pedestrian improvements Footway improvements Design work ongoing with Construction expected early 26 £30,000 24.28 Kilmarnock Pedestrian improvements Footway designs and buildouts Onsite consultation to be completed prior to design work with Construction expected early 26 £30,000 23.12 A713 Traffic calming 1 x speed table Construction expected June 25 £10,000
Page 29
Official Appendix 3 Ayrshire Roads Alliance - EV Public Chargers EAST AYRSHIRE CPS ID Type Make Location 51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU 50821 22kw eVolt Foregate Noth Car Park, Kilmarnock, KA1 1LU 51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH 52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 25.12 A71 Priestland Traffic Calming and pedestrian crossing Design work ongoing with Construction expected early 26 £50,000 Irvine Road Kilmaurs Pedestrian improvements Design work ongoing with Construction expected late 25 £35,000 Various location Various Unallocated £363,000 EAC Bus Infrastructure Budget: £40,000 22.51 Onthank Terminus, Kilmarnock Upgrades to existing infrastructure Improve crossing and boarding points Drawings complete to be paired with Stewarton Terminus £20,000 22.52 Stewarton Terminus, Stewarton Upgrades to existing infrastructure Improve turning circle and boarding points Design stage in progress £20,000 EAC Active Travel Budget £50,000 24.03 School Streets Programme Introduction of trial sites Three further schools to be trialled with further trials to be developed Trials have commenced at Bellsbank and Dalrymple. Further sites to progress. £50,000
Page 30
Official 52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW TBC Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP 60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR 52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU 52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE 52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG 52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS 52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB 52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ 52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB 52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
Page 31
Official 52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ 52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY 53778 Rapid eVolt Main Street Car Park, Muirkirk 53775 22kw eVolt Rose Reilly Sports Centre, Stewarton 53776 7kw eVolt Standalane Car Park, Stewarton 60786 7kW eVolt Academy Street, Hurlford 60792 22kW eVolt Drongan Centre car park, Mill of Shield Road 51210 22kW eVolt Carnshalloch Avenue car park, Patna 60950 22kW eVolt New Cumnock Outdoor Swimming Pool car park 60954 22kW eVolt Gatehead Road car park, Crosshouse 61021 7kW eVolt East Ayrshire Community Hospital, Cumnock 61022 7kW eVolt East Ayrshire Community Hospital, Cumnock 61983 7kW eVolt Morton Place car park, Kilmarnock 61984 7kW eVolt Morton Place car park, Kilmarnock 61985 7kW eVolt Morton Place car park, Kilmarnock 62184 7kW eVolt Browns Road car park, Newmilns 61886 22kW eVolt Sturrock Street, Kilmarnock 62938 7kW eVolt New London Road car park, Kilmarnock SOUTH AYRSHIRE CPS ID Type Make Location 51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW 51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU TBC Rapid eVolt Burns Statue Square, Ayr, KA7 UT 52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN 52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
Page 32
Official 52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY 50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ 50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF 52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG TBC Rapid eVolt Girvan Harbour, Girvan, KA26 9AG 52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR 52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH 52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU 52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL 53774 Rapid eVolt Academy Street, Troon 53773 Rapid eVolt Lodge Road Car Park, Turnberry 53777 22kw eVolt Burnside Road, Monkton 60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly 60081 22kw eVolt Inches Close car park, Maybole 61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton 61986 22kw eVolt Dundonald Primary School car park, Dundonald 60086 22kw eVolt Mossblown Activity Centre car park, Mossblown 60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald 61979 7kW eVolt Chalmers Arcade car park, Girvan 61980 7kW eVolt Chalmers Arcade car park, Girvan 61981 7kW eVolt Chalmers Arcade car park, Girvan 62000 22kW eVolt Barrhill Community car park, Main Street, Barrhill
Page 33
Official Appendix 4 South Ayrshire Ward Investment Programme 2025/26 Roads Maintenance Unit LOCATION Description PO Value Cost to Date variance +/- Comment Troon Emergency repairs to Troon Esplanade. £40,000.00 Complete – Final measure Troon Resurfacing of Troon Esplanade (Ph.2). £220,000.00 Complete – Final measure Prestwick Repair / renew steps to Boydfield Gardens Measuring works up on site Ayr North Provision of Bike Shelter at Lochside Community Centre With Procurement Ayr East Glencairn Park – footpath upgrade Feasibility study ongoing Ayr East Car parking provision Peggieshill Road Feasibility study ongoing Ayr West Promenade raised footway works Feasibility study ongoing with Professional Design Services Kyle Annbank Park – upgrade footpath Feasibility study ongoing Kyle Construction of new footpath on Southern edge of Collenan reservoir, £22,000.00 Feasibility study ongoing Design and Flooding Section Troon Shore Defence Structural Stabilisation £10,000.00 On site Citadel Footbridge Refurbishment Remove and renew timber deck parapet elements. Surface prepare and paint. Remove or repair lighting £140,000.00 Complete – Final measure Girvan Boating Pond Refurbishment Install new stainless steel reinforced concrete base slab to reduce water leakage. £175,000.00 Complete – Final measure Dunure Castle Footbridge Replacement Replace existing small span concrete footbridge with a larger footbridge with a view and good aesthetics £230,000.00 Ongoing. Lighting Section Ayr East Glencairn Park – Install footpath lighting Measuring works up on site Ayr West New Bridge & Auld Brig. Design fees for installation of architectural floodlighting to structures £50,000.00 Design Fee
Page 34
Official