AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
6 June 2025 
Report by the Head of Roads – Ayrshire Roads Alliance 
AYRSHIRE ROADS ALLIANCE SERVICE PLAN 2025/26 
Purpose of report 
1 The purpose of this Report is to seek the Joint Committee approval for the
Ayrshire Roads Alliance Service Plan for 2025/26 
Recommendations 
2 It is recommended that the Joint Committee:
i.  Approves the Ayrshire Roads Alliance Service Plan for 2025/26 (Appendix
1)
ii. Notes the confirmed finance budgets for 2025/26
iii. Notes the Performance Scorecard for 2024/25 (Appendix 2)
iv. Requests that progress updates are provided to future meetings of the
Joint Committee,
v. Otherwise, notes the content of this Report. 
Background
3 The first Ayrshire Roads Alliance Service Plan for 2014/15 was approved by Joint
Committee on 23 May 2014.  As part of all Service Plans it was agreed that the
draft Service Plan is approved prior to submission to both East Ayrshire Council
and South Ayrshire Council. 
Main report/main issues 
4. The service plan included in Appendix One provides detail on the current
operating position of the Ayrshire Roads Alliance and sets out the vision, aims
and objectives for the 2025/26 financial year. 
The activities to be undertaken in support of these objectives are as follows:- 
• the service ten year review; 
• the Performance Management Framework as approved and updated at
every Joint Committee;   
• the Risk Register and Report which has established a method of effective
management of risk to ensure service improvement through better service
delivery; increased certainty and fewer surprises; more effective and

Page 2

efficient management of resources; reduced waste; and better
management at all levels through improved decision-making; and 
• the Benefits Realisation Strategy and Plan which sets out how benefits will
be tracked and controlled across the fully integrated Roads service and
which was approved by the Joint Committee in on 1 May 2015. 
4. The Service Plan reflects the settled position in terms of South Ayrshire Council
and east Ayrshire Council budgets both approved on 27th February 2025 and
describes the challenges and the targets for the service. 
5. In addition to Revenue Budgets, the Ayrshire Roads Alliance receives budgets
from other sources including capital, and grants from the Scottish Government,
Strathclyde Partnership for Transport; and other organisations including both
external to the Council and internal Council Departments. 
6. The Ayrshire Roads Alliance has been in operation for just over eleven years,
and has achieved a significant amount in that time. The new integrated operating
model provides an excellent platform for service delivery and will continue to
facilitate a number of continuous improvement initiatives. 
7. Significant challenges lie ahead in terms of maintaining good performance,
dealing with financial pressures and their impact on service delivery and
delivering on the Benefits Realisation Strategy and Plan to ensure that all the
revenue saving targets are met. The Benefits Realisation Strategy and Plan was
approved by the Ayrshire Shared Services Joint Committee on 1 May 2015. 
8. The Service Plan contains a change programme, which is complemented by the
Business Realisation Strategy and Plan. This has been designed to enable the
Ayrshire Roads Alliance to achieve the objectives of the detailed business case
set out in June 2013. 
Implications 
Implications  Yes  No
Paragraph
number in
report
1. Policy/Strategic Planning X  9 & 10
2. Governance X  11
3. Human Resources X  12
4. Equality and Fairer Scotland Duty X  13 & 14
5. Financial X  15
6. Risk X  16
7. Community Wealth Building X  17
8. Net Zero X  18

Page 3

Policy/strategic planning implications 
9.  A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire and the wider road
network; improve community safety; improve road safety; improve the
infrastructure and help reduce road accidents. 
10. The matters referred to in this report contribute to Priority 1 of South Ayrshire
Council Plan: Spaces and Places / Moving around and the environment –
“Everyone can access streets, places and spaces that make a positive
contribution to wellbeing, are well connected, well designed and maintained” 
Governance Implications 
11. The work of the Ayrshire Roads Alliance is undertaken in accordance with
relevant legislation.             
Humans resources Implications 
12.    The Service Plan has no direct impact on human resources.  However, as the
Improvement Action Plan work develops, and reviews are completed, it is
expected that some impact on human resources will arise. 
Equality impact and Fairer Scotland duty implications 
13. The proposals in this report allow scrutiny of performance (Ayrshire Roads
Alliance 2024/2025 Performance Report). The report does not involve proposals
for policies, strategies, procedures, processes, financial decisions and activities
(including service delivery), both new and at review, that affect the Council’s
communities and employees, therefore an Integrated Impact Assessment is not
required. 
14. In relation to the Ayrshire Roads Alliance 2025/2026 Service plan, this is a
combination of both operational and strategic priorities and the equality impact
assessment paperwork has been previously carried out as part of Cabinet papers
and will be carried out in the future where appropriate. 
Financial implications 
15.      The Ayrshire Roads Alliance delivers the strategic and local services as stated in
the Service Plan.  The budget is provided by East Ayrshire Council, South
Ayrshire Council, and other external organisations.  Appropriate scrutiny
arrangements are in place to manage these budgets           
Risk implications 
16.     The Risk Register assists in the prioritisation of risks that need to be mitigated by       
the Ayrshire Roads Alliance in order to reduce the overall risk to either Council       
and to comply with the Community Plan/Council Plan in both partner bodies.

Page 4

Community Wealth Building implications 
17. The works programme provides economic levers to develop resilient, inclusive
local economies with more local spend and fair employment, as well as ensuring
that wealth is more locally owned and benefits local people 
Net zero implications 
18.   The Ayrshire Roads Alliance Service Plan supports and links to East Ayrshire
Climate Strategy Themes 
Theme 2: Transport
Theme 4: Natural Environment

Page 5

Appendices (if applicable) 
1 The Ayrshire Roads Alliance Service Plan - 2025/26 
2 Ayrshire Roads Alliance Performance Scorecard 2024/25 
Background papers 
1. Benefits Realisation Strategy and Plan – 1 May 2015 – Joint Committee 
Person to contact 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org 
Implementation Officer 
Jane Corrie, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: jane.corrie@ayrshireroadsalliance.org

Page 6

1 
Official 
Appendix 1 
Service Plan 2025-2026 
April 2025 
A Partnership between East Ayrshire Council and South Ayrshire Council

Page 7

2 
Official
Table of Contents
INTRODUCTION ............................................................................................................................................. 3
STRATEGIC CONTEXT ................................................................................................................................... 14
SERVICE PERFORMANCE FRAMEWORK....................................................................................................... 15
RISK, OPPORTUNITIES and CHALLENGES ..................................................................................................... 18
PROFILE OF SAVINGS AND COSTS OVER THE FIRST 10 YEARS ..................................................................... 22
AYRSHIRE ROADS ALLIANCE IMPROVEMENT ACTION PLAN 2023/24 ......................................................... 24
APPENDIX 1 – ORGANISATIONAL CHART .................................................................................................... 33
APPENDIX 2-STRATEGIC AND LOCAL DELIVERY SPLIT … .............................................................................. 34

Page 8

3 
Official
INTRODUCTION 
The Ayrshire Roads Alliance is a shared integrated roads and transportation service
which provides the roads service for East Ayrshire Council and South Ayrshire Council.
The Service is delivered with the overall objective of improving the road and
transportation service in the East Ayrshire and South Ayrshire areas to move the Ayrshire
Roads Alliance to a position that will deliver at least £8.634 million of savings by 2024.
The Ayrshire Roads Alliance is governed by the Ayrshire Shared Service Joint
Committee. The Joint Committee has responsibility for all shared Council services in
Ayrshire. 
The Shared Services Minute of Agreement describes the functions of the Joint Committee
as follows:
• making decisions within the confines of the service budget,
• developing and implementing a strategic policy framework,
• co-ordinating, monitoring and reviewing service performance,
• monitoring budget spend,
• considering and approving an annual Service Plan.
In addition, the "Joint Committee Arrangements for the Ayrshire Roads Alliance"
document covers those issues that are specific to the Ayrshire Roads Alliance. 
The two Councils involved in the Ayrshire Roads Alliance have each appointed four
Elected Members to the Joint Committee. Meetings take place as often as required to
conduct business, but at least twice per year in line with the terms of the Minute of
Agreement. 
The Alliance is responsible for all the roads and transportation activities listed in Appendix
2, split between strategic and local delivery, that are the responsibility of East Ayrshire
Council and South Ayrshire Council. Both Authorities retain the role of Roads Authority
under the Roads (Scotland) Act 1984 - Section 1.

Page 9

4 
Official
East Ayrshire Council - Strategic Issues 
The East Ayrshire Community Plan is the sovereign and overarching planning document
for the East Ayrshire area, providing the strategic policy framework for the delivery of
public services by all local Partners. The Plan is the Council’s Corporate Plan and covers
the 15 years from 2015 to 2030. 
The Vision contained within the Community Plan is shared by all Partners and states that:
“East Ayrshire is a place with strong, safe, vibrant communities where
everyone has a good quality of life and access to opportunities, choices
and high quality services which are sustainable, accessible and meet
people’s needs.”
The Community Plan is implemented through three thematic Delivery Plans - Economy
and Skills, Safer Communities and Wellbeing. The Plan is also implemented through
the day to day work carried out by services across the Council. 
East Ayrshire Council Strategic Plan 2022-2027 
This plan sets out our priorities for the communities of East Ayrshire over the next five
years and describes the context in which our services will work collaboratively with
each other, our communities and our partners to drive forward the actions needed to
achieve our aims. This will include prioritising the resources that are entrusted to us and
continuing to find new and innovative ways of working, to ensure the delivery of
services that are affordable, sustainable and which best meet the needs of those we
serve. The Plan recognises the strengths and assets that exist within East Ayrshire and
highlights the ambitions we have for our communities. However, it is written against a
backdrop of what are unprecedented challenges for both our Council and for those we
serve. These challenges include: 
• Rising inflation and increases in the cost of living
• Increased demand for services
• Restrictions in funding
• Pandemic Recovery and Renewal
• Public Sector Reform
• The impact of EU Exit
The Strategic Plan priorities take account of the communities we serve, including local
needs, circumstances and aspirations; the current internal and external context in which
the Council operates; national and local drivers for change, including risks, challenges
and opportunities; governance arrangements; programme management and
performance measurement. Our priorities build on the work of our previous two
Transformation Strategies and our Covid-19 Recovery and Renewal Dynamic Action
Plan. It is important to recognise that there are commonalities and interdependencies
across and between our priorities.

Page 10

5 
Official
• Building a Fairer Economy
• Tackling Poverty and Inequality
• Improving Community Wellbeing
• Supporting Children and Young People
• Delivering a Clean, Green East Ayrshire
• Ensuring Financial Sustainability and Resilience
Service Improvement Plans are an essential element of the Council’s performance
management and improvement framework. They set out the key issues for delivering
services in support of the Community Plan Vision and priorities, provide a focus on
performance improvement aligned to the Single Outcome Agreement and describe the
service specific risks that may impact on the delivery of the Service. 
The diagram below provides a graphic representation of the Council’s Policy Planning
Framework and shows the strategic context within which the Service Improvement Plans
sit. In addition it shows the wider Performance Management and Improvement
Framework which the Council has adopted to ensure the rigorous scrutiny of
performance and drive service improvement across the Council.

Page 11

6 
Official
South Ayrshire Council - Strategic Issues 
The Council Plan 2023-2028 sets out the Council’s vision for the next five years, with a
focus on “Our Pupose”,Our Vision”,”Our Values”. The Plan details the high-level
objectives and outcomes to be achieved by 2028. 
The Council’s priorities and outcomes place an emphasis on the connection between our
places and the wellbeing of our communities and environment. The place-based
approach recognises that every area has a different blend of physical, social, and
economic characteristics that influence each other and aims to address complex
problems that no service alone can solve. The priorities provide a common framework,
aimed at promoting a shared understanding that encourages services and partners to
work collaboratively to achieve improved outcomes and wellbeing for our communities.
• Priority One Spaces and Places
• Priority Two Live, Work, Learn
• Priority Three Civic and Community Pride
The Ayrshire Regional Growth Deal 
The three Ayrshire Councils have worked in partnership with other agencies,
communities and businesses to secure the first Regional Growth Deal in Scotland. This
will see £251.5 million of investment in key assets and key sectors across Ayrshire,
underpinned by an ambition to facilitate economic growth across the region. The projects
within the Growth Deal offer the best opportunity to attract private sector investment into
Ayrshire and to transform the area. It is considered that the various interventions in the
Growth Deal will unlock £300 million of private investment and deliver around 7,000 new
jobs across a wide range of sectors. 
There are currently no transport projects within the Ayrshire Growth Deal proposed for
East Ayrshire Council however the Ayrshire Roads Alliance recognise the strategic
importance of Bellfield Interchange and will continue to work with colleagues to secure
the improvements required. 
South Ayrshire Cabinet approved the ARA recommendation to discard the historic 3
phased roads enabling projects associated with the Ayrshire Growth Deal (AGD) at the
cabinet meeting of 29th August 2023.  A STAG (Scottish Transport Appraisal Guidance)
compliant process has been carried out to assess the roads enabling infrastructure
requirements to allow the Ayrshire Growth Deal development to progress. The outcomes
of the STAG will ensure that the most suitable solution is developed and that the AGD
Roads project can progress to Outline Business Case (OBC) and subsequently Full
Business Case (FBC).   
By carrying out extensive modelling of the existing road network around Glasgow
Prestwick Airport/Ayrshire Growth Deal cluster and building on the LDP2 no net detriment
approach to the road network the Ayrshire Roads Alliance was able to stress-test the
road network and identify the following improvements which will reduce peak congestion,
build capacity into the network to facilitate future growth, improve road safety and journey
time reliability :–

Page 12

7 
Official 
1.1 – Sandyford Toll Roundabout capacity improvements 
1.2 – Dutch House Roundabout capacity improvements 
1.3 – Monktonhead Roundabout capacity improvements 
1.4 – A79/Station Road Roundabout capacity improvements 
1.5 – Shawfarm Road Roundabout capacity improvements 
1.6 – Shaw Road/Shawfarm Road junction re-alignment/improvements 
1.7 – Active Travel links from existing network to AGD Commercial Build 
1.8 – Public Transport Infrastructure improvements 
Points 1.7 & 1.8 compliment the project currently being progressed under the de-
carbonisation of the road network being developed by the Ayrshire Roads Alliance and
funded by the successful Levelling Up Fund round 3 award. 
At this stage no costs have been associated to each of the mitigation measures above
with a high-level costing exercise undertaken as part of the OBC process. It is envisaged
that the available funding from the AGD Roads Enabling project will not be sufficient to
implement all of the above measures, should this be the case the projects will be ranked
by a benefit to cost ratio and a report submitted to Cabinet for further approval. 
A Case for Change has been submitted to Scottish & UK Governments seeking approval
of the changes noted above,ASTAC and  the Prestwick Proposition, the Ayrshire Roads
Alliance will assist in the delivery of all of the Road Schemes and Prestwick Proposition 
projects for South Ayrshire Council. 
STPR2 
Ayrshire’s key transport routes (road, rail, sea and air) are critical for businesses to enable
goods to get to market, our communities to employment and for training opportunities. A
number of key route improvements have been identified. 
The new Strategic Transport Projects Review was published in December 2022 and
included all modes of travel including active travel and public transport. In addition, this
work will develop transport projects outputs at a national, regional and local level. 
Due to Covid-19, Transport Scotland restructured the STPR2 into two phases. Phase 1
focussed on the short-term (up to 5 years) with a view to identifying interventions which
can be accelerated to support a green economic recovery from Covid-19, and also
those which embed, support and extend any increase in travel by sustainable travel
modes, including positive behaviour change seen during the pandemic. Phase 2
completed the review and the report was published in December 2022, giving Scottish
Ministers a programme of potential transport investment opportunities for the period
2022-2042. 
STPR2 makes 45 recommendations that focus investment on sustainable transport
options. Of those recommendations 28 provide benefits for individuals, families,
communities and businesses across most parts of Scotland.

Page 13

8 
Official
Of the 45 recommendations the following have a particular benefit to the Ayrshire and Arran
Region: 
• Supporting Integrated Journeys at Ferry Terminals 
• Ferry Vessel Renewal and Replacement and Progressive Decarbonisation 
• Investment in Port Infrastructure to Support Vessel Renewal and Replacement
and Progressive Decarbonisation 
• Rail Freight Terminals and Facilities 
With recommendation 40 being Specific to the Ayrshire and Arran Region: 
• Access to Stranraer and the Ports at Cairnryan 
Levelling Up Fund
South Ayrshire Council successfully secured £20million of funding from the Leveling Up
Fund (LUF) round 3, £16million of this funding will be utilised for the redevelopment of
Burns Statue Square with the remaining £4million allocated to Active Travel. East
Ayrshire Council were unsuccessful in securing funding in round 3 to improve the Bellfield
Interchange.
Burns Statue Square  is a key initiative emerging from the Town Centre Framework, it is
a priority project to support placemaking and make the town a more successful place to
live, work, visit and enjoy. The project’s purpose is to reshape the southern entrance to
the town centre as a new attractive and appealing gateway, involving rationalisation/
realignment of road carriageways to create opportunity for more useable, connected,
pedestrian friendly, high quality public realm space and arrival point. The project seeks
to connect town centre to a new transport interchange, involving a reconfigured rail station
and potential co-location of the town’s bus station, support retention of the town’s major
cinema and kick-start regeneration south of the town centre to form a vibrant new
southern Gateway to the Town. The Ayrshire Roads Alliance intend to utilise the SCAPE
Framework to direct appoint Balfour Beattie to deliver the project on a Design & Build
basis due to the fixed budget and completion deadline of 31st March 2027.
The Ayrshire Roads Alliance will construct a new Active Travel Route linking Dundonald
to Barassie Station, £1.2million of LUF funding will be used to match-fund £2.8million of
additional funding secured from the Active Travel Infrastructure Fund (ATIF). The
remaining £2.8million of LUF funding will be allocated to improving the existing NCN7
from Prestwick to Barassie railway stations, these improvements will compliment further
active travel routes which will be delivered as part of the Ayrshire Growth Deal. In addition
a further application will be submitted to ATIF to further improve the NCN7 Prestwick to
Barassie.

Page 14

9 
Official 
Our Current Service Resources
Table 1 – The Ayrshire Roads Alliance Assets (as at 31 March 2025) 
Asset Inventory Data as of 31st March 2025
Asset Type Units East Ayrshire
Council
South Ayrshire
Council
Totals
Carriageway km 1,228 1,183 2,411
Footways & Footpaths km 1,028 945 1,973
Street Lighting Columns No. 21,457 20,488 41,945
Illuminated Signs &
Bollards
No. 1,425 1,296 2,721
Structures No. 618 371 989
Retaining Walls km 7 3 10
Length of Sea Defences km 0 24 24
Piers and Harbours No 0 1 1
Cattle Grids No. 11 34 45
Traffic Signals
Zebra Crossings
No. of Sets
No. of Sets
99
27
92
0
191
27
Variable Message Signs No. 123 45 168
Vehicle Activated Signs No. 156 60 216
Real Time Passenger
Information
No. 67 50 117
Gullies No. 27,455 26,633 54,088
Grit Bins No. 760 296 1056
Weather Stations No. 3 1 4
EV Dual Chargers No 63 36 99

Page 15

10 
Official
Depots No 1 2 3 
Staff, Property and Fleet 
The Ayrshire Roads Alliance has depots located at Gauchalland in Galston; Meadowhead
in Coylton and Grangestone in Girvan. Offices are located in Kilmarnock, Ayr and at
Girvan Harbour. We also have extensive vehicles, plant and equipment to allow our
service to be delivered. 
There will be an ongoing need for property and accommodation across the area for the
Ayrshire Roads Alliance; for vehicle and equipment storage; and maintenance and staff
facilities. It is important that property and accommodation is safe, secure, fit for purpose,
and strategically placed to minimise the time spent travelling from depot toworkplace
to maintain the road asset, minimise the associated vehicle wear and tear, and emissions. 
From April 2014, the following actions have been taken in relation to property and
accommodation:
• Gauchalland Depot - Street lighting operations have moved from Munro Place in
Kilmarnock to Galston.
• The street lighting technical team was located at the Johnnie Walker Bond in
Kilmarnock which provided a more centralised service. Following a further review
this team is now located at Galston depot
• The closure of the Underwood Depot in Cumnock saw staff re-located to the
Gauchalland Depot in Galston.
• All salt for the Ayrshire Roads Alliance previously stored in the Underwood Depot
is now distributed from the Meadowhead Depot in Coylton.
• A rationalisation of fleet across the Ayrshire Roads Alliance has taken place
resulting in a reduction in cost.
Further office developments include staff transferring from the Johnnie Walker Bond to
the Opera House in Kilmarnock and from Burns House to Wellington Square and Town
Hall in Ayr which was restricted due to COVID guidance. 
Staff have now returned to the Opera House Kilmarnock on a rota based model with posts
designated as fixed, flexible and mobile. 
Staff returned to County Buildings and Ayr Town Hall in June 2022 on a rota hybrid model
and in 2024 there was a move of all ARA staff except for Parking Attendants from Ayr Town
Hall to County Buildings. 
Depots at Galston, Ayr and Girvan are fully operational with improvements planned for
the Ayr and Girvan Depots this financial year. 
Our key messages from this work include:
The Ayrshire Roads Alliance completed an organisational review which delivers the
current management structure which has generated £326,000 of revenue savings per
year. This will contribute £2.242 million towards the Business Case savings target of

Page 16

11 
Official
£8.634 million. The Joint Committee agreed to this review on 1 April 2016, and the work
was completed during 2017/18. In accordance with good management practice the
Alliance continued to review staff provision, and completed the service re-design during
2021/22 with management actions realising a saving of £190,000, parking £86,000
and £293,000 in South Ayrshire. 
The Ayrshire Roads Alliance completed a depot review which has resulted in £404,362
of revenue savings by 2024. This included the closure of the Underwood Depot with staff
transferring to Gauchalland Depot; and the Munro Place Street Lighting Depot with all
street lighting staff now being based in Gauchalland. In accordance with good
management practice the Alliance will continue to review depot and accommodation
provision. 
The Ayrshire Roads Alliance has completed the fleet review which has resulted in
£1,350,699 of revenue savings by 2024. In accordance with good management practice
the Alliance will continue to review fleet and plant provision. 
An Organisational Chart is shown in Appendix 2. 
Budgets
The Ayrshire Roads Alliance delivers the strategic and local services as stated in this
Service Plan and listed in Appendix 2. 
The budget to deliver these services is provided from East Ayrshire Council, South
Ayrshire Council, and other external organisations.
Budgets for 2025/26 are confirmed and this is reflected in Tables 1 and 2. 
Table 1 - Budgets 2025/26 
Council Revenue Non - Revenue Total (£m)
East
Ayrshire
Council  £6.712m £11.963m
(Confirmed)
£17.003m
(Potential)
£18.675m
(Confirmed)
£23.715m
(Potential)
South
Ayrshire
Council
£7.011m £25.212m
(Confirmed)
£37.534m
(Potential)
£32.223m
(Confirmed)
£44.545m
(Potential)
Total £13.723m £37.175m
(Confirmed)
£54.537m
(Potential)
£50.898m
(Confirmed)
£68.260m
(Potential)

Page 17

12 
Official 
Table 2 provides the current non-revenue budgets for 2025/26
Table 2- Non-Revenue Budgets
Funding Source Type/Level of Funding Annual Budget 2025/26
East Ayrshire Council
Carriageway
Footway
Street Lighting.
Traffic, Transportation & Road
Safety.
Bridges & Culvert (inc Road Slips)
Car Parks inc Multi-Storey
demolition
School Streets
Fleet
£2.305m
£0.150m
£0.215m  
£0.330m
£3.500m 
£0.820m
£0.050m
£0.600m
Current approved budget
£7.970m at Cabinet
meeting of 12 March
2025.
Scottish Government Active Travel Tier 1
Road Safety Improvement
Fund. 
Active Travel – Tier 2
People & Place Behavioural
Change
Electric Vehicle
Infrastructure Fund (EAC
Lead Authority) 
£0.758   
£0.270 (TBC)   
£4.500m (TBC)   
£0.039m   
£2.800m 
Strathclyde Partnership for
Transport
General bus infrastructure  £0.270m TBC
Scottish Timber Transport Group Projects No funding awarded for
25/26
Developer Contributions Rural route action plans £0.396m 
Funding Source Type/Level of Funding Annual Budget
2025/26
South Ayrshire Council
Roads Improvement Plan 
Street Lighting
Bridge Works
Victoria Bridge
Millennium&Craigholm
Bridges   
C12 Dunure Slope
Stabilisation   
Vehicle Restraint
barriers
Cattle Grid Renewal
Girvan Harbour Jetty
Repairs 
£1.581m
£0.150m
£0.600m
£0.281m 
£0.145m 
£0.130m  
£0.073m 
£0.033m   
£0.504m 
£4.436m
(Confirmed at
Cabinet meeting on
29 April 2025)

Page 18

13 
Official
Local Flood Risk Plan
Ayr Depot     
Climate Change
EV Charging
infrastructure
£0.153m
£0.250m
£0.255m 
£0.281m
Scottish Government Levelling Up Fund Round 3:
• Dundonald to Barassie
• Prestwick to Barassie
• Burns Statue Square 
Active Travel Tier 1
Road Safety Improvement Plan
Active Travel Tier 2
People & Place - Behavioural
Change
Electric Vehicle Infrastructure
Fund 
(Pan Ayrshire funding) 
£ 1.200m 
£ 2.800m   
£16.000m 
£ 0.737 
£0.270 (TBC)   
£8.505m (TBC)   
£0.039m 
Budget indicated in  
EAC above.
Strathclyde Partnership for
Transport
General bus infrastructure £0.100m (TBC)
Sustrans Projects £3.447m (TBC)
Scottish Timber
Transport Group
Projects No funding awarded for
2025/26

Page 19

14 
Official
STRATEGIC CONTEXT 
EAST AYRSHIRE COUNCIL 
The Community Plan 2015 - 2030 includes a Safer Communities Delivery Plan, which
sets out the key actions to be undertaken and also measures progress. The Delivery
Plan contains three distinct strategic priorities, all of which will be influenced by the
activities undertaken by the Ayrshire Roads Alliance. These are:
• Make East Ayrshire a safe, secure and attractive place to live, work and visit.
• Improve community safety in neighbourhoods and homes and protect and
support our most vulnerable individuals and families.
• Promote our vibrant communities by encouraging active and responsible
citizenship.
Single Outcome Agreement (SOA)
The SOA was reviewed and developed as a key element of the comprehensive review
of the Community Plan to ensure alignment with strategic priorities and high level
local outcomes. There are a number of National Outcomes which are supported by the
activities undertaken by the Ayrshire Roads Alliance. The Community Planning
Partnership receives an annual report in September each year at which they are advised
of progress against the local outcomes previously agreed. 
SOUTH AYRSHIRE COUNCIL – 
The Local Outcomes Improvement Plan and Local Place Plans were introduced in 2017.
The plan focuses on two strategic themes which emerged from the development process. 
• Closing the poverty-related outcomes gap for children and young people in
South Ayrshire
• Supporting older people to live in good health
The Plan is supported by a partnership wide focus on four priority areas
• Improving outcomes for looked after children and care leavers
• Providing support for young people who are carers
• Reducing social isolation and loneliness
• Support for people living with dementia and their carers
There will be an effort to improve outcomes for children and older people particularly in
the Ayr North and Girvan Glendoune areas, and to identify transferable good practice to
be used to support outcomes improvement in other parts of South Ayrshire. The work
on progressing this work is taking place within the auspices of the Integrated Children’s
Services Strategic Delivery Partnerships and the Health and Social Care Partnership and
this is supported by appropriate partnership work.

Page 20

15 
Official
SERVICE PERFORMANCE FRAMEWORK 
PERFORMANCE AND BENCHMARKING 
The Councils’ performance management frameworks operate on a number of
levels providing detail on strategic priorities, operational priorities and day to day
management information. Within the Ayrshire Roads Alliance, the approach is fully
integrated and aligned with the corporate frameworks. 
• Strategic (Community Plan and Single Outcome Agreement; and Local
Outcomes Improvement Plan)
• Operational Priorities (Council performance indicators)
• Management information (operational statistics, corporate measures of
performance)
Strategic Issues
East Ayrshire Community Plan 2015-30. The Community Plan includes three Delivery
Plans, which set out the key actions to be undertaken and measures to progress against
them. The Delivery Plans contains distinct strategic priorities, which will be
influenced by the activities undertaken by the Ayrshire Roads Alliance Service.
Single Outcome Agreement. The single outcome agreement has been reviewed and
developed as a key element of the comprehensive review of the Community Plan in
2014/15 to ensure alignment with strategic priorities and high level local outcomes.
Operational Issues
Council Performance Indicators.
The Ayrshire Roads Alliance reports on a number of performance indicators through an
electronic Performance Management System. A management framework has been
developed, which has been approved by the Joint Committee. The data includes both
contextual and performance information thereby allowing statutory returns to be made
facilitate benchmarking provide each Council and the Joint Committee with the
information they require to monitor performance. 
A performance scorecard is produced as an integral part of the Ayrshire Roads Alliance
which is reviewed at the monthly Ayrshire Roads Alliance Management Team meetings
and reported to every Joint Committee.
This scorecard is used to:
• monitor the progress in meeting the Ayrshire Roads Alliance’s objectives;
• help managers to have performance-related conversations with staff;
• identify any problem areas that need addressed.

Page 21

16 
Official
Performance Management System
Relevant information contained within the Performance Management System is provided
for each four week period in a scorecard which is used by the Depute Chief
Executive (Safer Communities) and the Head of Service to monitor performance
activity and improvement within their respective management team meetings. 
SCOTS/APSE Benchmarking Framework 
The Society of Chief Officers of Transportation in Scotland (SCOTS) and the Association
for Public Sector Excellence (APSE) have developed a series of indicators to utilise
SCOTS definitions using a single template. 
The Alliance participates in the SCOTS/APSE benchmarking framework through the
APSE Annual Return; the SCOTS/Institution of Civil Engineers “state of the network”
annual return; and the Scottish Road Maintenance Condition Survey. 
Local Government Benchmarking Framework
The Local Government Benchmarking Framework (LGBF) collates information from
the APSE Annual Return that is published by the Improvement Service with specific
actions to improve performance.
Monitoring and Review 
Monitoring of the service plan is the responsibility of the Joint Committee. An annual
review will be completed and reported to the Joint Committee and both Councils. The
Joint Committee will receive a six monthly update on the Service Plan progress. In
addition, separate monthly meetings are held with the Depute Chief Executive
responsible for the provision of the roads service within East Ayrshire Council; and the
Executive Director responsible for the provision of the roads service within South Ayrshire
Council. 
Scrutiny in respect of the Joint Committee is undertaken by both Councils in accordance
with their own processes as set out within their respective Corporate Governance
arrangements. Matters in relation to service performance will be closely monitored by
both Councils through the Joint Committee. 
QUALITY MANAGEMENT AND ASSESSMENT
European Foundation for Quality Management (EFQM) Excellence Model
The European Foundation for Quality Management (EFQM) Excellence Model is a
practical self-assessment tool designed to promote continuous improvement within
organisations by assessing their performance against concepts of tested and recognised
good management practice. The EFQM Model is the cornerstone of Best Value. The
service also has an externally accredited Quality Management System.

Page 22

17 
Official
ENGAGEMENT WITH SERVICE USERS 
The Ayrshire Roads Alliance will continue to undertake engagement with relevant service
users. This engagement will take a number of forms through informing, consulting,
involving, collaborating or empowering our service users. 
Through 2025/26 we will continue engagement with our customers to ensure we
maximise the involvement of our service users. 
The Association for Public Service Excellence (APSE) who work with over 300 Councils
through the UK to promote excellence in the delivery of frontline services to our local
communities have developed the Scotland Roads Survey in conjunction with the Society
of Chief Officers of Transportation in Scotland (SCOTS). 
The Survey will be used to gauge customer service and user experience/satisfaction of
winter gritting, road works, road safety and other road maintenance related matters within
East Ayrshire Council and South Ayrshire Council. 
The information gathered from the survey will help shape future service delivery and
inform on performance. 
The link on the Ayrshire Roads Alliance website to the East Ayrshire Council and the
South Ayrshire Council survey forms is below
https://www.ayrshireroadsalliance.org/Information-On/Consultations/Current-consultations/the-
association-for-public-service-excellence-apse-road-condition-survey.aspx
CONSULTATION WITH EMPLOYEES 
Employee Engagement 
The Employee Attitude Survey identified a number of issues to be addressed. Employee
engagement will continue through 2025/26 and this will take many forms including
management meetings; team meetings and staff forums. The staff forums will take place
when important Council or service information requires to be provided to staff. 
Trade Union Meetings 
The Alliance will continue to engage with the Trade Unions through the established JCC
process which involves meetings at a Corporate; Service and work specific level.

Page 23

18 
Official
RISK, OPPORTUNITIES and CHALLENGES 
Risk 
The Ayrshire Roads Alliance records risk using a “five by five” scoring matrix, for the risks
identified which quantifies the assessment of the likelihood and severity of a particular
risk occurring. This information is hosted on the Performance Management System and
it is used to understand the impact of proposed controls and mitigations on the overall
risk profile. This is a widely used tool in risk management. 
The service risk register, and the Corporate Risk Registers, are aligned to the approach
of identifying and recording risk, which ensures a consistent approach to service level
risk recording. This allows service objectives and priorities, performance measures and
service risks to be captured in a single document. These areas are closely aligned, and
this approach offers benefits in business planning, service delivery, and performance and
risk management. 
The risk register for the Ayrshire Roads Alliance is presented to every meeting of the Joint
Committee.
There continues to be a number of opportunities and challenges which the Ayrshire
Roads Alliance faces over the next twelve months. 
Opportunities
The opportunities include the following
• Although the Organisational Review was approved by Joint Committee on 1 April
2016 and implemented during 2017/18, we continued to review staff provision
during 2020/21 as part of service re-design reported and approved by Cabinet 23
February 2022 the transformation and redesign was implemented from 1 April
2022.
• The Plant & Fleet review from June 2016 was implemented immediately. However,
with new technology and the need to increase the number of electric vehicles then
all plant and fleet will continue to be reviewed during 2025/26.
• The property and accommodation review from November 2016 and all the actions
have been implemented. Nevertheless, with more agile and remote working, the
Alliance will continue to review these issues during 2025/26, as part of the service
re-design.
• The opportunity to continue to make significant revenue budget savings through
the replacement of existing street lighting units with LED units cannot be
understated. Work commenced in 2018/19 with work programmed to be
completed in 2021/22, however completion has been delayed due to COVID and
the impact of material shortages. Currently 96% of street lanterns in East Ayrshire
and 100% of street lanterns in South Ayrshire are LED.

Page 24

19 
Official
• It was expected that street lighting revenue delivery cost would reduce by more
than 50%, however, the current challenge against this, is the current rising energy
costs as a result of wider economic issues.
• Use of Digital software to improve our gully, culvert, and harbour infrastructure
management and mobile working.
• Moving all our permits over to a digital platform and our TTRO process was
recognised in March 2023 and March 2024 at APSE Innovation awards.
• Further development of digital systems for Traffic Signal permits, Management of
External Works, Critical Incidents and Driver Assessments which won a bronze
award from APSE in 2025.
• Continued support offered to other services across both East and South Ayrshire
to help facilitate improvements to their digital systems and in partnership with our
colleagues in Education the development of a digital system to manage ASN
Transport applications and the associated contracts.
• Ten year review of the business plan to be undertaken during 2025/26.
Challenges
There are a number of challenges the Ayrshire Roads Alliance will face in 2025/26
which include the following
External
• There is the potential to increase the utilisation of electric cars and vans to comply
with emission standards and the Scottish Government decision to ensure that all
new cars and vans are not powered through fossil fuel means by 2040. This will
result in the reduction in harmful emissions, and an improvement to air quality. 
• The Transport (Scotland) Bill places increased emphasis on low emission zones;
smarter ticketing arrangements; the increased role and powers for the Roadworks
Commissioner; the ban on pavement and double parking; the workplace parking
levy and the ability for Councils to run public bus services. 
• The National Transport Strategy will focus on sustainable, inclusive and accessible
transport systems to promote prosperity, health and fairness. The Sustainable
Transport Hierarchy will be used to inform budgetary decisions with walking first;
then cycling; public transport; taxis and shared transport and then the private car.
There is a need on many levels for more active travel and public transport use
across Scotland. The Sustainable Investment Hierarchy will be used to inform
budgetary decisions – reduce the need to travel; maintain existing assets; make
better use of existing capacity; and finally targeted infrastructure improvements. 
• The National Transport Strategy has identified the need to focus on increased
collaboration, and this was considered through the Roles and Responsibilities
Working Group which made recommendations to the Scottish Ministers including

Page 25

20 
Official
that future transport governance arrangements should be on the basis of some
form of regional model allowing for variations in approach between different
geographic regions; and there is the potential for continuous increases in the unit
costs of electricity due to on-going energy costs. The Department of Energy and
Climate Change has predicted that electricity prices are likely to double within the
next ten years. SCOTS reported a 20% increase in energy costs with further
increases possible in the future.
• However, as the programme for LED lights is nearing completion then the impact
of this specific challenge may be reduced.
• Ensure the current Regional Transport Appraisal work aligns with the needs of
East Ayrshire and South Ayrshire Council.
• Issues with the renewal of Scotland Excel framework contracts resulting in delays
to procurement processes and therefore works programmes and resulted in added
pressures on our procurement team
• Material and sub contractor cost increases and budgetary pressures restricting
work programmes
Internal
• There are increased austerity measures resulting in need to drive further efficiency
savings over and above the £8.634m identified in the Benefits Realisation Strategy
& Plan which was presented to Joint Committee on 1 May 2015.
• The need to increase the level of mobile working across the Ayrshire Roads
Alliance workforce as a direct result of implementing the Roads Asset
Management Plan and the impact of COVID. This has resulted in an increase in
mobile technology, full use of the WDM Roads Maintenance and Management
System, Artificial Intelligence and the decrease in the demand for desk and office
space. As a result of COVID many of the aforementioned have been accelerated
by the service in particular reduced desk space, mobile technology and the
implementation of Artificial Intelligence, training has been delivered on this
particular element for operational use from April 2022.
• The rise in demand for electricity charging points as a direct result of the greater
number of electric vehicles and the Scottish Government initiative to ban the sale
of new fossil fuel powered cars and vans from 2040. Work is ongoing on a Pan
Ayrshire EV Infrastructure Project. This initiative aims to enhance access to
convenient and affordable public charging facilities, supporting the transition to EV
ownership in both urban and rural areas.
• The impact of an ageing workforce and the need to ensure an appropriate
knowledge transfer and succession planning; and service re-design. Work around
this was carried out over 21/22 with a greater emphasis on the service being more
resilient with an amended structure to be more community focused along with
Modern Apprenticeships and trainee opportunities.

Page 26

21 
Official
In February 2024 approval was given by East Ayrshire for the introduction of a
training programme for road workers so that Ayrshire Roads Alliance could grow
its own, providing full training to school leavers, foundation apprentices, seasonal
workers etc and thereafter, on completion provide a road worker position. In South
Ayrshire one roadworker trainee has progressed to a roadworker position whilst
three Modern Apprentices have progressed onto the roadworker trainee
programme. In the East we have one trainee roadworker at present and in both
areas we have recently appointed another two Modern Apprentices. We have
twelve Community Maintenance Assistants who work between services and over
the last year four former Community Maintenance Assistant have secured
permanent roadworker positions. 
Resilience
• Continue to engage with community councils and community groups to improve
local winter and flooding resilience. This allows these groups to take ownership
of gritting the footpaths and minor roads; and attend minor flooding events and
report them directly to the Alliance for action. The uptake to date has been
encouraging and we currently have 135 groups. This resilience work was
recognised by the National Highways Industry in October 2021 and APSE in March
2022.
• Decreasing requirements for desk and office space due to the increase in
mobilisation of workforce from the developing Roads Asset Management Plan
using the WDM system and working patterns amended due to COVID will see an
increase in ‘hot desking’ and access to welfare facilities at key strategic locations
throughout the geographical area of the Ayrshire Roads Alliance, through service
re-design.
• Improved adverse weather resilience during periods of high winds, heavy rain, and
severe snow conditions.
• Ensuring improved resilience as a measure of our ability to successfully absorb
future changes; to reshape ourselves; and a strategic capability to thrive.

Page 27

22 
Official
PROFILE OF SAVINGS AND COSTS OVER THE FIRST 10 YEARS
The Ayrshire Roads Alliance has achieved savings in excess of the £8.634 million
projected by 2024.
This represents a saving on the costs to deliver the service when comparing the first year
with later years. Table 3 has been extracted from the Detailed Business Case, and this
shows the various costs/savings to be delivered. The reason for the variations in year
one to year four is due to set up costs. In practice, these set up costs may be spread
over a longer period to mitigate any operational risks. This may impact on when
consequential savings are realised. 
Continual updates on progress and targets will be contained within the service plan, and
reported to the Joint Committee when required. 
This savings will enable Councils to take individual decisions, either to bank their share
of the savings, or to invest some or all in additional roads maintenance. 
Strategic Delivery Savings for each Council are now calculated by considering a smaller
group of core strategic delivery staff and that their costs are apportioned on a budget
spend profile basis, in line with local delivery budget spend plus the actual capital
expenditure in that specific year. 
Local Delivery Savings are pro rata to the existing budgets. 
Table 3 – Ayrshire Roads Alliance Total Revenue Savings 
Year
1
Year
2
Year
3
Year
4
Year
5
Year
6
Year
7
Year 8 Year 9 Year 10 Total 
14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 
Proposed
Savings
Benefits
realisation(£
m)  0.696  -0.426  -0.730  -1.049  -1.187  -1.188  -1.187  -1.188  -1.187  -1.188  -8.634 
Budget  14.683  14.813  14.006  13.823  13.551  12.695  12.294  11.992  12.278  12.005  132.14
Savings to
date (£m) 0.696 -0.441 -0.971 -1.315 -1.768 -2.515 -3.067 -3.636 -3.828 0.795 -16.05
Cumulative
Budget
14.683 29.496 43.502 57.325 70.876 83.571 95.865 107.857 120.135 132.14 755.45 
Cumulative
Savings to
date (£m) 
0.696  0.255  -0.715  -2.031  -3.799  -6.314  -9.381  -13.017  -16.845  -16.05  -67.201

Page 28

23 
Official
The Benefits and Realisation Strategy provided a framework for achieving cumulative
savings of £8.634m between 2014/15 and 2023/24. However, during this time additional
savings have been achieved due to prevailing economic conditions and their impact on
public sector funding. This has resulted in cumulative expenditure reductions of
£67.201m over the life of ARA. This is significantly in excess of the £8.634m originally
envisaged.
The Benefits Realisation Strategy and Plan
• Ensures benefits are identified and also defined at the outset, and appropriately
linked to the East Ayrshire and South Ayrshire Council’s strategic objectives.
• Ensures relevant business areas are prepared to realising their defined benefits.
• Reduces the risk of unrealistic optimism in the Detailed Business Case and
subsequent benefits realisation dilution or delay during or after potential
implementation.
• Drives the process of realising benefits, including benefits measurement, tracking
and recording benefits as they are realised.
• Uses the defined, expected benefits as a roadmap for the programme, providing
a focus for delivering change.

Page 29

24 
Official
AYRSHIRE ROADS ALLIANCE IMPROVEMENT ACTION PLAN 2025/26 
Action Success Criteria/
Desired Outcome  Responsible  Timescale  Details
1 Continue to use the integrated
Roads Asset Management
Plan across the Ayrshire
Roads Alliance.
There is one Asset Plan for the
Service delivering a risk based
approach for full service
delivery
Head of Service Completed Document has been presented to Joint
committee and will be reviewed annually.
2 Continue to prepare details for
developing an integrated Local
Transport Strategy.
A Strategy covering both
Council areas, which will
involve consultation with
stakeholders. Information will
be gathered to inform the
future Local Transport
Strategy.
Continue to contribute to the
Scottish National Transport
Strategy, Regional Transport
Strategy and Strategic
Transport Projects Review
work.
Head of Service Ongoing The Regional Transport Strategy, through
SPT, on which the Alliance has Board
membership, has now been published. 
The Local Strategy will be created as an
appendix to the Draft RTS. 
3 Action the Flood Risk
Management Plan
Inform the next national cycle
of potential flood risk
management schemes beyond
2022. 
Complete schemes and
undertake studies.
Head of Service Complete 
March 2026
Reports submitted to both Cabinets Early
2023 
New Cumnock Flood Defences Complete 
Continue Design Work on the Irvine Valley
Continue with flood study works for the river
Ayr, Doon and Girvan

Page 30

25 
Official 
Action Success Criteria/
Desired Outcome  Responsible  Timescale  Details
4 Improve the condition of the
road network.
Improve annual roads survey
results which are part of the
SRMCS work. Ensure the
Alliance undertakes more
proactive maintenance.
Head of Service Site works will be
undertaken
throughout
2025/26.
Key dependencies are the Road Improvement
Plans approved by the relevant Committees in
East Ayrshire and South Ayrshire in spring
2025. Progress is provided to members, and
relevant Committees.
5 Ensure the road network
remains safe through raising
awareness and improving road
safety through education,
engineering and enforcement.
Reduce road accidents in line
with government targets.
Provide appropriate traffic
management schemes and
initiatives.
Strategic Manager  March 2026 Scottish Government and SCOTS guidance is
used. A key dependency is the Road
Improvement Plans which are presented to
Cabinet each year.
6 Improve the condition of the
bridge stock.
Improve bridge condition index.
Reduce the number of weight
restricted bridges. Complete
all general, special and
principal bridge inspections.
Strategic Manager March 2026 Through the Road Asset Management Plan.
Key dependencies are Road Improvement
programmes approved by Committees in East
Ayrshire and South Ayrshire in spring 2025.
Deliver the capital and revenue programmes.
7 Manage and improve the
street lighting asset and install
energy efficient lighting
schemes.
Maintain high standard of fixing
dark street lights. Complete
the LED lighting replacement
programme in both East
Ayrshire and South Ayrshire.
Head of Service March 2026 Through the Road Asset Management Plan,
with additional funding being provided to
commence the LED programme.
96% of streets lights are now LED in EAC;
and 100% in SAC. 
8 Maximise and deliver
externally funded sources of
work
Identify external funding
sources and deliver work on
time and on budget. Improve
infrastructure; and contribute to
improving the condition of the
network.
Head of Service Works will be
undertaken
throughout
2025/26.
External sources, including Timber Transport,
Transport Scotland Active Travel
Infrastructure Tier 1 and Tier 2 Funding, SPT,
SUSTRANS Scottish Government, Ayrshire
Growth Deal & Levelling Up Fund

Page 31

26 
Official 
Action Success Criteria/
Desired Outcome  Responsible  Timescale  Details      
9 Implementation of Parking
Strategy
Develop Head of Service Works will be
undertaken
through 2025/26
Amendments to TRO’s, lining, signing and
residential parking permits and implementing
an improved process using digital technology. 
10 Prepare Service Plan Publish Head of Service Annual East Ayrshire Council Community Plan. South
Ayrshire - Local Outcomes Improvement Plan
and Local Place Plans. Regular updates will
be provided to joint committee.
11 Continue to review insurance
costs and insurance issues.
Review current practices to
minimise insurance costs.
Head of Service Complete Ayrshire Roads Alliance Monthly Insurance
Report.
There is good dialogue with the Risk &
Insurance to ensure our work improves the
number of repudiated claims. The number of
claims has greatly reduced due to the
implementation of the new Code of Practice. 
12 Review Depots and
Accommodation
Continue to review in 2024/25
from initial work was completed
in 2017 as a result of amended
working practices.
Head of Service Complete Joint Committee Reports of November 2016.
Although initial work has been completed we
continue to strive to make depot and
accommodation cost savings. Further work
will continue on this as a result of COVID and
the return to office space during 2022/23.
13 Review vehicle and plant costs Continue to review in 2021/22
from initial work that was
completed in 2017.
Head of Service March 2026 Joint Committee Reports of June 2016
The service continues to review fleet
requirements with the most recent
improvement being on the management of
vehicle utilisation, electric vehicles and
Telematics.
14 Monitor and exercise Business
Continuity Plans
Improved resilience. Business Support
Manager
Review and
update following
Existing East Ayrshire and South Ayrshire
Council plans

Page 32

27 
Official 
Action Success Criteria/
Desired Outcome  Responsible  Timescale  Details    
relevant local and
national events. 
15 Continue to use the Roads
Costing System to its full
potential.
Improve service performance
from both an on-site and
financial perspective.
Business Support
Manager
Ongoing Revised roads costing system was fully
operational from November 2018 and
continues to be used to monitor performance
and work is ongoing to implement digital
timesheets linked to the Roads Costing
System.
16 Support and contribute to the
Ayrshire Growth Deal
Project Management of Roads
Delivery Projects.
Head of Service Ongoing Ayrshire Roads Alliance will assist with the
planning and delivery of the roads enabling
infrastructure requirements to allow the
Ayrshire Growth Deal development to progress.
17 Regional Transport Strategy Successfully contribute to the
preparation of this work being
led by SPT. The Alliance has
Board representation.
Head of Service Complete SPT documents and existing Regional
Transport Strategy
18 Regional Transport Appraisal Ensure the various projects
identified as part of this work
are included in the Strategic
Transport Projects Review.
Head of Service Complete Transport Scotland has published the final
STPR2 with delivery programme to be
published.
19 National Transport Strategy East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure the
sustainable transport hierarchy
and sustainable investment
hierarchy are delivered.
Head of Service Complete In recognition of the anticipated increase in
Active Travel work, it is proposed that a
member of staff is dedicated directly to this
work.
20 National Transport Strategy –
review of Governance
East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure that the
outcome/output meets the
Head of Service Complete National Transport Strategy

Page 33

28 
Official 
Action Success Criteria/
Desired Outcome  Responsible  Timescale  Details  
needs of the road
users/communities in both
Council areas.   
21 Transport (Scotland) Bill –
Pavement Parking Ban
East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure a
pragmatic approach is taken in
delivering the pavement
parking ban in both Council
areas.
Head of Service Complete Transport (Scotland) Bill and Transport
Scotland Parking Standards working group -
guidance from Transport Scotland. 
Pavement Parking enforcement commenced
in South Ayrshire with soft approach from 1st
April 2025 and full enforcement from 1st May
2025. Enforcement to commence in East
Ayrshire from 1st June 2025. Exemption
Orders for both authorities to be in place by
end March 2026.
22 Levelling Up Fund East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure that the
outcome/output meets the
needs of the road
users/communities
Head of Service Complete Further updates awaited on future Levelling
Up funding
23   Digital Transformation  Develop modules to deliver end
to end digital processes 
Business
Support
Manager
Ongoing TTRO applications –Implemented
TRIPS – ImplementedTraffic 
Signal permits –   Implemented
Management of external works for EAC &
SAC – Development stage
ASN School Transport – Development stage

Page 34

29 
Official
East Ayrshire Council Strategic Priorities 2024/25 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details
1 Progress and complete the
New Cumnock Flood
Protection Project
Complete the flood prevention
projects at the Leggate and
beside the Afton Water.
Head of Service Complete East Ayrshire Council and Scottish Government
funding. The Leggat stage of the works was
completed in August 2018 with the Afton Water
phase commenced May 2021 with an 18 month
contract duration.Contract delayed due to
material shortages.
2 Develop Projects approved
from the Flood Risk
Management Plan
Progress relevant studies and
inform the developing list of
schemes for cycle two of the
national protection schemes to
be delivered from 2022.
Head of Service March 2026 The studies for the River Ayr and the Doon are
now fully complete and options being appraised.
The Irvine Valley Flood Study will be updated to
identify options for a potential scheme that is
more likely to attract funding
3 Active Travel Strategy Develop active strategy for
travel across South Ayrshire
Network and East Ayrshire
Network
Head of Service Complete A full review of active travel provision in East
Ayrshire has been undertaken and this will be
presented to the relevant East Ayrshire Council
Committees.
6 EV Strategy Develop EV strategy across
East Ayrshire Network
Head of Service Complete  Work on concession contract ongoing with
contract award due in September 2025.
7 Levelling Up Fund Completion and Submission of
Bid for improvements to Bellfield
Interchange
Head of Service Complete Design and modelling work to improve Bellfield
to increase capacity and open up [development
opportunities. LUF Bid unsuccessful
8 Ash Die back Strategy Develop a risk based strategy
for the management of Ash Die
Back.
Head of Service Complete Develop a risk based approach to the
management of Ash Die Back.

Page 35

30 
Official
South Ayrshire Council Strategic Priorities 2024/25 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
1 Implementation of car parking
strategy for South Ayrshire.
Complete this work with
improved parking provision and
management.
Head of Service March 2026 A full review of car parking provision in South
Ayrshire is being undertaken at present and this
will be presented to the relevant South Ayrshire
Council Committees.
2 Develop Projects approved
from the Flood Risk
Management Plan
Progress relevant studies and
inform the developing list of
schemes for cycle two of the
national protection schemes to
be delivered from 2022.
Head of Service Ongoing A Surface Water Management Plan has been
developed for Ayr, Prestwick and Dundonald.
Troon Coastal Flood Study is ongoing.
Pow Burn Prestwick Flood Study has been
scoped and Consultant appointment is ongoing.
3 Support and contribute to the
Ayrshire Growth Deal
Stimulate economic growth and
address inclusive growth
concerns. Contribute to
infrastructure projects which are
being developed through the
Regional Transport Appraisal
work being led by Transport
Scotland.
Head of Service Ongoing Ayrshire Roads Alliance will assist with the
planning and delivery of the roads enabling
infrastructure requirements to allow the Ayrshire
Growth Deal development to progress. 
4 20mph speed restrictions in
villages
Progress with the 20mph speed
restrictions in all villages.
Maintain engagement with the
local communities.
Head of Service Phase 1&2
Complete March
2022
Phase 3 – June 2025
Phase 1 and 2 - complete
Phase 3 - TRO consultation process complete
and approved by Regulatory Panel,
implementation ongoing 
5 Anticipated Budget Reductions
in 2025/26
Continue to provide a high
quality roads service within
decreasing available budgets.
Head of Service March 2026 Reports to various Committees.

Page 36

31 
Official
Action Success Criteria/
Desired Outcome
Responsible Timescale Details
6 Active Travel Strategy Develop active strategy for
travel across South Ayrshire
Network
Head of Service Ongoing The Active Travel Strategy will be reviewed and
discussed with the Active Travel Community
Action Group, any amendments will be presented
to the Active Travel Member Officer Working
Group
7 EV Charging Strategy Develop further the EV strategy
for South Ayrshire Network
Head of Service Complete Work on concession contract ongoing with
contract award due in September 2025.
8 Levelling Up Fund Submission of Active Travel bid Head of Service Complete Joint bid with NAC for active travel route Ayr to
Irvine successful.
9 Motorhome Trials Develop Campervan sites along
the coastline.
Head of Service Ongoing Formalisation of two temporary sites at Girvan
and Ayr and additional trials at Ballantrae,
Maidens, Prestwick and Troon.
10 Strategic Economic Impact
Assessment A75/A77
There is a growing desire to
understand the importance /
effectiveness of the
improvements outlined along the
A75 and A77.
Head of Service Complete SEIA complete, ARA to progress STAG for the
A77 or a combined A75/A77 STAG on behalf of
SAC and D&G Council. Lobbying Group formed
with D&G with Task Force the next stage.
11 Ash Die back Strategy Develop a risk based strategy
for the management of Ash Die
Back.
Head of Service Complete Develop a risk based approach to the
management of Ash Die Back.
12 152nd Open Championship Delivery of Event Traffic and
Transport Management
Head of Service Complete Successfully delivered.  Debrief September
2024
13 The International Ayrshow -
Festival Of Flight
Delivery of Event Traffic and
Transport Management
Head of Service Ongoing Successfully delivered in 2024. Debrief
November 2024. Planning in progress for 2025
event.

Page 37

32 
Official
APPENDIX 1 – ORGANISATIONAL CHART
Chair 
Joint Committee 
Chief Executive of
South Ayrshire Council
Chief Executive of
East Ayrshire Council
Director of    
Housing,
Operations &
Development
Depute Chief Executive
Strategic Lead: Safer
Communities 
Head of Roads 
2 x Strategic Managers    Strategic Manager 
• Traffic, Parking & Road Safety
• Structures & Flooding
• Piers & Harbours 
• Street Lighting
• Roads Network Mtc
• Winter Mtc & Emergencies 
• Finance & Admin Support
• Business Continuity
• Asset Management & Roadworks

Page 38

33 
Official
APPENDIX 2 – STRATEGIC AND LOCAL DELIVERY SPLIT
TABLE 1 - PROPOSED SPLIT BETWEEN STRATEGIC AND LOCAL DELIVERY 
Strategic Service Delivery Local Service Delivery
Asset and Performance
Local Transport Strategy; Transportation Policy;
Road Safety Plan; Cycling Strategy
Council/Partner Liaison;
Transportation, Development Control and
Road Safety
Maintenance of Bus Shelters; Split Cycle
Offset Optimisation Technique (SCOOT)
systems (an adaptive control system for
controlled road crossings); Development
Control; Bus Shelter Advertising;
Shopmobility; Travel Planning; Planning
Applications; Development Planning; Section
75 Agreements; Road Safety Audits; School
Travel Plans; School Crossing Patrol; Road
Safety Education.
Maintenance of Traffic signals, traffic signs,
Traffic Orders; Traffic Counts, Accident
Investigation and Prevention;
Asset and Performance
Asset Management Plan; Performance
Monitoring; Parking Strategy.
Scottish Roadworks Register
Asset, Traffic and Parking Car Park
Maintenance and Parking Enforcement.
Roads Improvement Plan; Infrastructure
Surveys; Inventory Management; Issue of
Permits; Accident Investigation and
Prevention;
Asset and Performance
Flood Risk Management Strategy; Flood Risk
Management Plans;
Design and Environment
Maintenance of Watercourses, Bridges,
Retaining Walls, Piers and Harbours.
Watercourses; Flood Mitigation; Coastal
Protection; Inspection of Piers & Harbours;
Bridge Inspections and Maintenance;
Structural Assessments; Technical Approval;
Abnormal Load Routing; and Design of Major
Road Schemes and Improvements. Road
Construction Consents
Construction and Roads Maintenance
Winter Service Planning; Street Lighting
Management;
Operations
Proactive, Reactive, Cyclic Maintenance of
Roads and Footways; Winter and Weather
Emergency Service; Proactive and Reactive
Maintenance of Streetlights; Electricity costs
for streetlights. Carriageway Inspections;
Programming of Proactive, Reactive and
Cyclic Maintenance; Street Lighting Design;
Festive  Lighting,  Construction  of  Road
Safety Schemes; Design of Minor Road
Schemes.EV Charging.

Page 39

Official 
Strategic Service Delivery Local Service Delivery  
Business Operations 
Scottish Roadworkers National Training
Programme
New Business opportunities 
Support Services
HR, Finance, ICT, and Administrative Support. 
TABLE 2 - CURRENT SPLIT BETWEEN STRATEGIC AND LOCAL DELIVERY 
Strategic Service Delivery Local Service Delivery
Transportation, Development Control and
Road Safety
Local Transport Strategy; Transportation Policy;
Road Safety Plan; Travel Planning, Cycling
Strategy; Planning Applications; Road
Construction Consents; Development Planning,
Council/Partner Liaison, Section 75 Agreements;
Road Safety Schemes; Road Safety Audits;
School Travel Plans; School Crossing Patrol; Road
Safety Education.
Transportation, Development Control and
Road Safety
Maintenance of Bus Shelters; Split Cycle
Offset Optimisation Technique (SCOOT)
systems (an adaptive control system for
controlled road crossings); Development
Control; Bus Shelter Advertising;
Shopmobility; Construction of Road Safety
Schemes.
Asset, Traffic and Parking
Asset Management Plan; Roads Improvement
Plan; Infrastructure Surveys; Inventory
Management; Scottish Roadworks Register; Issue
of Permits; Performance Monitoring; Accident
Investigation and Prevention; Traffic Orders;
Traffic Counts; and Parking Strategy.
Asset, Traffic and Parking
Maintenance of Traffic signals, traffic signs,
Car Park Maintenance and Parking
Enforcement.
Design and Environment
Flood Risk Management Strategy; Flood Risk
Management Plans; Watercourses; Flood
Mitigation; Coastal Protection; Inspection of Piers
& Harbours; Bridge Inspections and Maintenance;
Structural Assessments; Technical Approval;
Abnormal Load Routing; and Design of Major and
Minor Road Schemes and Improvements.
Design and Environment
Maintenance of Watercourses, Bridges,
Retaining Walls, Piers and Harbours.
Operations
Carriageway Inspections; Winter Service
Planning; Programming of Proactive, Reactive and
Cyclic Maintenance; Street Lighting Design and
Management; and Festive Lighting.
Operations
Proactive, Reactive, Cyclic Maintenance of
Roads and Footways; Winter and Weather
Emergency Service; Proactive and Reactive
Maintenance of Streetlights; Electricity costs
for streetlights.

Page 40

2021 2022 2023 2024 2021 2022 2023 2024
Number of people killed or seriously injured in
road accidents per 100,000 population 36 42 48 34 37 54 28 54
Number of slightly injured casualties per
100,000 population 49 58 82 57 41 52 30 58
2019/21
2019/21
Scotland
Average
2020/22
2020/22 
Scotland
Average
2021/23
2021/23
Scotland
Average
2022/24
2022/24
Scotland
Average
2023/25
2023/25
Scotland
Average
2019/21
2019/21
Scotland
Average
2020/22
2020/22 
Scotland
Average
2021/23
2021/23
Scotland
Average
2022/24
2022/24
Scotland
Average
2023/25
2023/25
Scotland
Average
% of A Class roads that should be considered
for maintenance 22.10% 29.80% 17.20% 27.60% 15.60% 27.40% 17.60% 28.90% 17.70% 30.60% 34.10% 29.80% 28.90% 27.60% 23.00% 27.40% 21.7% 28.90% 23.4% 30.60%
% of B Class roads that should be considered
for maintenance 32.60% 34.00% 26.85% 33.60% 27.00% 31.50% 26.10% 32.50% 25.20% 34.60% 37.30% 34.00% 34.40% 33.60% 32.50% 31.50% 31.0% 32.50% 28.6% 34.60%
% of C Class roads that should be considered
for maintenance 33.50% 33.60% 29.50% 33.20% 29.60% 32.70% 31.00% 33.40% 30.80% 34.20% 40.80% 33.60% 37.90% 33.20% 38.90% 32.70% 38.1% 33.40% 37.6% 34.20%
% of U Class roads that should be considered
for maintenance 42.30% 38.30% 40.90% 36.70% 40.60% 36.40% 39.00% 36.20% 37.00% 36.20% 43.40% 38.30% 42.90% 36.70% 41.00% 36.40% 38.5% 36.20% 36.4% 36.20%
Overall % of the road network that should be
considered for maintenance 36.80% 35.50% 33.80% 34.20% 33.50% 33.60% 33.00% 34.10% 31.70% 34.70% 40.90% 35.50% 39.00% 34.20% 37.40% 33.60% 35.5% 34.10% 34.0% 34.70%
MONTHLY PERFORMANCE INDICATORS
APSE
Average
2024/25
Target Current
Status P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12
No of invoices paid within 30 days 904 886 781 491 521             979 320 1052 1,141 387          1,002            1,237       
No of Invoices Received 907 889 785 494 534             1000 321 1,112 1,178 391          1,029            1,328       
Average Year to date of Number of Invoices
paid within 30 days 100% 100% 99% 99% 98% 98% 100% 95% 97% 99% 97% 93%
Number of ARA Safety Inspections Completed
within Timescale 25 27 21 22 23 20 17 20 6 14 21 16
Number of ARA Safety Inspections Scheduled 25 28 23 23 23 20 17 21 7 16 21 18
% of ARA Safety Inspections Completed within
timescale 100% 96% 93% 96% 100% 100% 100% 95% 85% 88% 100% 89%
Number of Health and Safety Incidents
Reported to the Health and Safety Section 3 4 2 5 3 8 7 7 4 7 2 4
Average Number of days to report an incident to
the Health and Safety Section 1 1 1.5 1.8 2.3 1.6 9.6 2.9 1.8 3.1 3 10.3
Average days lost per employee - - 0.82 0.94 1..06 1.07 0.85 1.19 0.65 1,19 1.19 1.18 1.12 1.43
Visits to the ARA Website every month - 49,000 per
annum  11,906 10,379 9,806 11,231 12,843 11,313 12,657 11,379 7,719 13,494 11,891 6,394
No of Twitter Followers every month - - - 4,676 4,590 4,600 4,605 4,603 4,619 4,620 4,590 4,574 4,528 4,543            4,576
Monthly visits to the website from social media - 1,800 per
annum          1,066 827 792        1,377 1560 1261              1,001 1031 843        6,725 6891 4545
-
92.02%
Comments
AYRSHIRE ROADS ALLIANCE PERFORMANCE SCORECARD DETAILED MONITORING REPORT
ANNUAL REPORT 2024 / 25
ANNUAL PERFORMANCE INDICATORS                                                                                              
(FINANCIAL YEAR)
ANNUAL PERFORMANCE INDICATORS
(CALENDAR YEAR)
HEALTH AND SAFETY
98% -
WELL ENGAGED
90%
5
South AyrshireEast Ayrshire
AYRSHIRE ROADS ALLIANCE
East Ayrshire Council South Ayrshire Council
AYRSHIRE ROADS ALLIANCE
FINANCE
ABSENCE MONITORING

Page 41

Target Current
Status P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 Target Current
Status P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12
Number of parking appeals accepted 39 40 32 55 47 47 56 45 33 37 32 38 96 101 93 70 51 61 101 106 62 39 23 22
Number of parking appeals received 102 111 127 135 123 133 128 110 70 121 115 129 199 206 223 173 134 223 233 268 191 210 166 206
% of parking appeals accepted 38% 36% 25% 41% 38% 35% 44% 41% 47% 31% 28% 29% 48% 49% 42% 40% 38% 27% 43% 40% 32% 19% 14% 11%
Physical % of Roadworks Programme
Completed - 100% 17% 32% 46% 54% 71% 83% 97% 97% 97% 97% 98% 100% 100% 13% 38% 43% 65% 81% 89% 96% 97% 98% 98% 99% 100%
Number of General Bridge Inspections - 408 0 0 0 61 0 0 16 41 20 28 15 47 257 21 47 37 26 26 17 0 44 10 10 33 45
Number of Special Bridge Inspections - 408 7 7 7 7 7 61 7 61 7 61 7 91 150 30 5 30 0 5 30 28 5 28 5 28 5
Number of Principal Bridge Inspections - 88 0 0 0 0 0 0 0 0 0 0 0 61 56 13 0 0 0 0 0 0 0 0 10 13 14
Number of Category 1 Road Emergency defect
repairs made safe within 2 hours 1 2 2 0 1 0 1 1 3 5 0 1 2 2 1 1 2 0 3 1 1 0 2 1
Number of Category 1 Repair Lines issued 1 2 2 0 1 0 1 1 3 5 0 1 2 2 1 1 2 0 3 1 1 0 2 1
% of Category 1 Road Emergency defect repairs
made safe within 2 hours 100% 100% 100% - 100% - 100% 100% 100% 100% - 100% 100% 100% 100% 100% 100% - 100% 100% 100% - 100% 100%
Number of Category 2 Road Emergency defect
repairs made safe within 5 working days 16 14 15 18 14 9 5 8 10 21 15 11 16 13 12 13 25 11 11 10 12 9 29 11
Number of Category 2 Repair Lines issued 22 16 15 18 15 10 8 8 11 24 16 13 17 13 12 14 26 12 11 10 12 14 35 16
% of Carriageway Category 2 Defects repaired
within 5 working days 73% 88% 100% 100% 93% 90% 63% 100% 91% 88% 94% 85% 94% 100% 100% 93% 96% 92% 100% 100% 100% 64% 83% 69%
Number of Street Lighting repairs completed
within 7 working days 72 49 33 69 92 79 123 94 97 126 98 75 39 33 31 35 49 51 76 97 57 93 75 64
Number of Street Lighting Repair Lines Issued 72 49 33 69 95 81 123 99 100 128 99 78 40 38 33 35 49 54 76 105 60 94 76 64
% Street Lighting repairs completed within 7
working days 100% 100% 100% 100% 97% 98% 100% 95% 97% 98% 99% 96% 98% 87% 94% 100% 100% 94% 100% 92% 95% 99% 99% 100%
Number of Traffic light repairs completed within
48 hours 28 26 22 30 24 17 28 39 28 40 29 24 39 31 24 16 14 18 18 21 31 11 12 19
Number of Traffic light repair lines issued 29 26 23 30 25 17 28 40 28 40 29 24 40 31 24 16 15 18 18 21 32 13 12 20
% of Traffic light repairs completed within 48
hours 97% 100% 96% 100% 96% 100% 100% 98% 100% 100% 100% 100% 98% 100% 100% 100% 94% 100% 100% 100% 97% 85% 100% 95%
Number of Stage 1 Complaints responded to
within allotted timescales 2 2 1 0 5 0 - 1 0 0 1 2 2 0 0 2 1 1 1 4 1 1 0 1
Numer of Stage 1 Complaints received 2 2 1 0 5 0 0 1 0 0 1 2 2 0 0 2 1 1 1 4 1 1 0 3
% of Stage 1 Complaints responded to within
allotted timescales 100% 100% 100% - 100% - - 100% - - 100% 100% 100% - - 100% 100% 100% 100% 100% 100% 100% - 66%
Number of Stage 2 complaints responded to
within allotted timescales 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 1 0 0 1 0 0 0 1 1
Number of Stage 2 complaints received 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 1 0 0 1 0 0 0 1 1
% of Stage 2 complaints responded to within
allotted timescales - - - - - - - - - - - 100% - - - 100% - - 100% - - - 100% 100%
APSE
Average
2024/25
75%
PRIORITY 2 DEFECTS
EAST AYRSHIRE COUNCIL SOUTH AYRSHIRE COUNCIL
76.23%
95%
TRAFFIC
ROADWORKS PROGRAMME
STREET LIGHTING
100%
-
100%
COMPLAINTS
95%
Comments
-
91.20%
Due to sickness and a
vacancy within the EAC
team, the target was not
achieved for General
Inspections.  The post has
now been filled and the team
will endeavour to complete
the remaining general
inspections over the next few
months
75%
88.07%
95%88.23%
- 100%
PRIORITY 1 DEFECTS
100%
50% 50%
95%
BRIDGES
-
PARKING
MONTHLY PERFORMANCE INDICATORS
- -
-

Page 42

Target Current
Status P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12 Target Current
Status P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12
APSE
Average
2024/25
EAST AYRSHIRE COUNCIL SOUTH AYRSHIRE COUNCIL
Comments
MONTHLY PERFORMANCE INDICATORS
Number of enquiries responded to within
allotted timescales 77 85 73 53 43 42 60 58 49 41 62 48 39 41 39 34 31 39 53 48 31 29 26 31
Number of enquiries received 78 91 79 54 45 46 62 64 53 50 66 51 47 45 41 35 34 42 54 51 33 33 30 35
% of enquiries responded to within allotted
timescales 99% 93% 92% 98% 96% 91% 97% 91% 92% 82% 94% 94% 83% 91% 95% 97% 91% 93% 98% 94% 94% 88% 87% 89%
Number of FOI & EIR requests responded to
within 20 working days 17 17 5 13 20 4 12 18 17 11 22 20 24 14 11 13 22 15 26 22 16 18 21 27
Number of FOI & EIR requests received 17 17 5 13 21 4 12 18 17 11 22 20 24 14 11 13 22 15 26 22 16 18 21 30
% of FOI & EIR requests responded to within 20
working days 100% 100% 100% 3% 95% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 90%
Number of Public Liability claims closed 11 12 5 10 3 3 7 2 5 4 4 4 12 6 2 10 3 2 5 2 2 2 3 7
Number of Public Liability claims received 13 13 6 3 1 2 2 1 3 11 3 15 14 8 4 2 0 2 4 2 3 8 2 17
Total number of open claims 70 53 48 46 35 37 46 38 40 50 42 72 46 20 21 26 30 32 37 34 37 44 39 52
Number of Public Liability Claims that were
successful 0 0 0 1 0 0 0 0 0 0 0 1 0 0 1 1 0 0 0 0 0 0 0 0
- - - - -
83.44% 80%
PUBLIC LIABILITY CLAIMS
FREEDOM OF INFORMATION
ENQUIRIES
80%
100%88.52% 100%