AYRSHIRE ECONOMIC PARTNERSHIP BOARD
MEETING – 23 AUGUST 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL 
SUBJECT: AYRSHIRE GROWTH DEAL – PROGRAMME RISK REGISTER
UPDATE – JUNE 2024 
PURPOSE OF REPORT 
1. To advise the Ayrshire Economic Partnership Board (AEPB) members on
the update for the AGD Programme Risk Register. 
RECOMMENDATIONS 
2. Agree the content of the report and recommend approval to the Ayrshire
Economic Joint Committee (AEJC) to: 
(i) Note the proposed adaptation of presentation style to meet Scottish
Government quarterly reporting templates; and
(ii) Approve the updated Programme Risk Register dated June 2024. 
BACKGROUND 
3. The AGD Programme Risk Register is a key tool in which to monitor and
evaluate potential risks associated with the development and delivery of the
programme. The AEJC (dated 26 June 2023) approved the quarterly review
and reporting of the AGD Programme Risk Register as a separate item on
future AEPB and AEJC meetings. 
4. It should be noted that the top scoring programme and project risks are
reported to the Chief Executives Group, Steering Group, AEPB and AEJC
on a regular basis via the sharing of the AGD Programme’s Monthly
Reports. 
MAIN REPORT 
5. The PMO regularly reviews the Programme Risk Register in line with the
recommendations of the AEJC. This has included reviewing the nature of
the risks, their RAG status/scoring, and the mitigation measures used to
manage the potential risks identified. The review covers the majority of Q4
2022/23 from February to March 2024 and Q1 2024/25 (from April to June
2024) and reflects comments received from the AGD S95 Officer, the

Page 2

Steering Group and both Governments. 
6. The updated Programme Risk Register is set out in Appendix 1 attached to
this report. The opportunity has also been taken to renumber the Risks
following the review. There are no changes proposed to 11 of the current 19
risks on the Risk Register. 
7. There have been changes proposed to 7 of the current risks and the
introduction of a new risk as follows: 
Number Risk
AGDRISK03 Introduction of a new Risk:
• AGDRISK03 - Failure to drawdown full yearly
allocated AGD funding as per Grant Offer
Letter 
AGDRISK’s
04; 18 and
19
Amendment in the nature of the risks being monitored so
they now consider: 
• AGDRISK04 - Failure to drawdown full AGD funding
by 2030 as per Tripartite Agreement; 
• AGDRISK18 - Failure to ensure AGD projects
working towards net zero ambitions as set by
SG/UKG; and 
• AGDRISK19 - Potential impact of macro events on
the wider economy and economic prosperity of
Ayrshire.
AGDRISK’s
04, 05, 07,
08, 14, 15
and 18
Increase in risk scoring, whether in likelihood and/or in
impact:
• AGDRISK04 - Failure to drawdown full AGD funding
by 2030 as per Tripartite Agreement;
• AGDRISK05 - Delays in development and approval
of business cases;
• AGDRISK07 - Failure to deliver community benefits
from AGD;
• AGDRISK08 - Failure to deliver individual projects
within the AGD programme;
• AGDRISK14 - Failure to attract commercial interest
in AGD;
• 
AGDRISK’s
01 and 02
Decrease in risk scoring, whether in likelihood and/or
impact:
• AGDRISK01 - Failure to achieve AGD programme
objectives within agreed budget; and
• AGDRISK02 – Failure to provide accurate
projections for programme spend.
From
AGDRISK
04 onwards
Renumber of risks categories to reflect new AGDRISK03

Page 3

8. The following risks have currently been identified as being ‘red’ in RAG
status: 
Number Risk Action
AGDRISK04
(formerly
AGDRISK03)
Failure to drawdown full
AGD funding by 2030 as
per Tripartite Agreement
Conclusions from the
Programme Review will
provide clarity on the
delivery of Projects and
the whole Programme.
AGDRISK05
(formerly
AGDRISK04)
Delays in development and
approval of business cases
Conclusions from the
Programme Review will
provide clarity on the
timelines and milestones
for the development and
approval of business
cases.
AGDRISK19
(formerly
AGDRISK21)
Potential impact of macro
events on the wider
economy and economic
prosperity of Ayrshire
Continued monitoring of
external macro events and
to plan where possible. 
9. The updated mitigation measures associated with each risk are set out in
Appendix 1. 
10. Overall these changes have been undertaken in the context of the
Programme Review and its emerging outcomes, which include the
development of a more robust Programme that takes account of increased
costs and the impact of this upon development and delivery of capital
projects. There is a commitment to continue to review all Risk Registers
including the Programme Risk Register to reflect changes in the
Programme. It is therefore anticipated that further changes will be presented
to future AEPBs. 
11. Moving forward, the risks identified, especially those highlighted as ‘red’, are
anticipated to start to be de-risked once the Programme Review has been
agreed by the Government and key projects gain business case approval,
thus allowing drawdown of funds from the Government and delivery on the
ground. This includes projects for the Prestwick area that form the
Aerospace and Space Programme of the Deal. 
12. Changes in the programme risks and the application of mitigation measures
are working their way into the draft Implementation Plan 2024/25 that
includes an updated Financial Plan. This includes more realistic timelines
being developed which seek to ensure the development of business cases
and delivery by the end of the Programme. 
13. The PMO are also reviewing the presentation of the Programme Risk
Register so that it reflects more closely the Scottish Government’s quarterly
template for reporting. The benefits of this are to ensure the transfer of
information between formats and audiences are more efficient. This includes

Page 4

taking into account the differences between the AGD and Government’s
RAG criteria. Note that the AGD RAG scoring will continue to be retained
and used on a day to day basis. For example as illustrated below 
Source GREEN AMBER/GREEN AMBER/RED RED
Scottish
Government
Guidance 
Successful
delivery appears
highly likely with
regard to time,
cost and quality
and there are no
major
outstanding
issues that at
this stage
appear to
significantly
threaten
progress
Successful
delivery appears
probable
however
attention will be
needed in
certain areas to
ensure risks do
not develop into
major issues that
will threaten
delivery
Successful
delivery appears
possible, but
issues already
exist that require
serious attention.
These appear
resolvable at this
stage, but further
action is required
Successful
delivery is in
serious doubt
with major risks
or issues
apparent in a
number of key
areas. Urgent
action is needed
to ensure these
are addressed
Source GREEN AMBER RED
Ayrshire
Growth Deal
RAG
Guidance
Note
with an AGD risk
register score of
between 0-3
with an AGD risk
register  score of
between 4-9
with an AGD risk
register score of
between 10-14
with an AGD risk
register score of
between 15-25 
14. In conclusion the Programme Risk Register provides an assessment of the
challenges the programme continues to face. As noted the PMO are working
across the partnership to conclude the Programme Review with details of
the outcome (e.g. Executive Summary and Implementation Plan 2024/25)
scheduled to be presented to Board members at the next meeting (23
August 2024). Once agreed subsequently by the AEJC (scheduled for 4
September 2024) the Programme Review will provide a baseline in which to
ensure the delivery of projects, which will help  mitigate the current ‘red’ risks
wherever possible.

Page 5

IMPLICATIONS 
15. The implications arising from this report are: 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 16-17
2.Governance/Legal Yes  Para 19
3. Human Resources Yes  Para 20
4. Equality and Fairer Scotland Duty Yes  Para 21
5. Financial  Yes  Para 20
6. Risk  Yes  Whole paper
7. Community Wealth Building   No 
8. Net Zero   No 
ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
16. Inclusion is a key driver for the AGD business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
17. The Risk Register provides the framework for reviewing the challenges the
AGD needs to address and sets out the mitigation measures to be
undertaken that include meeting the headline Deal objective of delivering
inclusive growth. 
FINANCIAL IMPLICATIONS 
18. It is accepted by the Ayrshire Councils and the Government that risks
should be managed and mitigated where necessary in order to support the
effective delivery of projects and the programme. 
LEGAL IMPLICATIONS 
19. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2022. 
HUMAN RESOURCES IMPLICATIONS 
20. There are no immediate human resource implications arising from this
report. However for the risk associated with lack of resources in PMO to be
addressed there could be human resource implications. 
EQUALITY IMPACT ASSESSMENT 
21. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business

Page 6

case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES 
Appendix 1: Updated Risk Register – March 2024
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk

Page 7

Appendix 1:
UPDATED VERSION
AYRSHIRE GROWTH DEAL UPDATED PROGRAMME RISK REGISTER (RISKS AND MITIGATIONS) – JUNE 2024
Note: includes amendments to the Risk Register to reflect review. 
Source
GREEN AMBER/GREEN AMBER/RED RED
Scottish
Government
Guidance 
Successful delivery appears
highly likely with regard to time,
cost and quality and there are
no major outstanding issues
that at this stage appear to
significantly threaten progress
Successful delivery appears
probable however attention will
be needed in certain areas to
ensure risks do not develop into
major issues that will threaten
delivery
Successful delivery appears
possible, but issues already
exist that require serious
attention. These appear
resolvable at this stage, but
further action is required
Successful delivery is in serious
doubt with major risks or issues
apparent in a number of key
areas. Urgent action is needed
to ensure these are addressed
Source GREEN AMBER RED
Ayrshire Growth
Deal RAG
Guidance Note
with an AGD risk register score
of between 0-3
with an AGD risk register  score
of between 4-9
with an AGD risk register score
of between 10-14
with an AGD risk register score
of between 15-25 
RISK (AGD RAG USED) Current
Matrix and
Score
Proposed
Matrix and
Score
Proposed
Scottish
Govt RAG
Score
MITIGATION
AGDRISK01
Failure to achieve AGD
programme objectives
within agreed budget 
Scoring – 12 
CHANGE to reflect
Score 16  Score 12 
AMBER/RED 
• The Regional Economic Joint
Committee, Regional Economic
Partnership, AGD Steering Group in
place to monitor progress and to
address any weaknesses or issues
that could impact on overall delivery. 
• PMO ongoing monitoring and

Page 8

decrease in likelihood.  evaluation of Deal and project
objectives in order to address issues
early. 
• Leading to potential to review of risks
where evidence suggests insufficient
funding to undertake and complete
projects in line with expected
outcomes. Internal governance
include regular reviews undertaken
by PMO with input from SROs, Project
Leads and Chief Executives to ensure
AGD programme objective are met.
Where necessary reporting issues and
potential solutions to the AEPB and
AEJC e.g. Programme Review 23/24.
AGDRISK02
Failure to provide accurate
projections for programme
spend 
Scoring –  - 12 
CHANGE – to reflect
decrease in likelihood 
Score 16  Score 12 
AMBER/RED
• Issues will be escalated to CEOs,
Regional Economic Partnership and
Regional Economic Joint Committee
as appropriate 
• Implementation Plan and Financial
Plan updated annually with input from
Project Leads, SROs and CEOs. 
Business Case process development
supported and monitored on a
monthly basis in order to achieve
approval e.g. OBC and FBC, and then
during delivery. PMO will regularly
review, challenge and agree financial
profiling/phasing with Project Leads,
SROs and Finance Directors and
ensure drawdown projections align
with delivery timescales
• OBCs/FBCs include an optimism bias

Page 9

factor as per Treasury Green Book
and AGD Governance document
• Inflationary factor addressed through
project reviews e.g. re-scoping,
phasing and reviewing costs and
benefits
AGDRISK03 (NEW)
Failure to drawdown full
yearly allocated AGD funding
as per Grant Offer Letter 
Scoring – 9 
NEW
NEW Score 9 
AMBER
/GREEN
• PMO regularly review, challenge and
agree financial profiling/phasing with
Project Leads, SROs and Finance
Directors and ensure drawdown
projections align with delivery
timescales
• Regular monitoring of project
progress and projected drawdown of
AGD allocated funds. Use of bi-annual
returns (Feb return) informing the
expected Grant Offer Letter 
• Monthly reporting to the Steering 
Group, SRO's AEPB/AEJC and the
Government on in year drawdown
profiles
AGDRISK04 (formerly 3)
Failure to drawdown full AGD
funding by 2030 as per
Tripartitie Agreement 
Scoring –   - 20 
CHANGE – to reflect
increase in impact 
Score 16  Score 20 
RED
• PMO will regularly review, challenge
and agree financial profiling/phasing
with Project Leads, SROs and Finance
Directors and ensure drawdown
projections align with delivery
timescales. This includes PMO
working with Project Leads, SRO’s
and S95’s to ensure projects can be
realised and help with change
processes where necessary; and
undertaking effective communication
with Governments to ensure projects
Impact
Likelihood

Page 10

can be realised
• Annual review of Financial Plan and
Implementation Plan undertaken.
Noted that challenges continue to
impact upon the development and
delivery of the Aerospace and Space
Programme.
• Regular reporting to the Scottish
Government in line with  financial
reporting requirements PMO support
Project Leads achieve business case
milestones in line with the current
Implementation Plan, AGD
Governance document and, Finance
guidance
• Pivot projects proactively where
possible in line with need and
opportunity, and in line with change
management processes as defined by
the AGD Governance
• PMO manage internal procedures,
financial controls and processes in
place to mitigate this risk
AGDRISK05 (formerly 4)
Delays in development and
approval of business cases 
Scoring – 20 
CHANGE – to reflect
increase in impact 
Score 16  Score 20 
RED
• Undertake focused engagement with
SG and UKG in order to help ensure
SBC, OBC and/or FBC comply with the
Treasury Green Book and gain
approval in line with AGD governance
• PMO working closely with Project
Leads and Policy Leads within UK and
Scottish Governments to support
business case development and
approval to an agreed timeline. This

Page 11

includes exploring a streamlined
change process (pre-FBC) particularly
where budget constraints are sole
driver of change. Note challenges
continue to impact upon the
development of business cases
• Project Leads provided with Green
Book business case training
• Project Leads’ toolkit in place
• Seek other partners to assist in
developing business cases where
capacity is low, skills align e.g.
Ayrshire College and SE. 
AGDRISK06 (formerly 5)
Failure to capture accurate
baseline data 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9
AMBER
/GREEN
• Project Leads required to establish
appropriate economic, social and
environmental baseline information in
business cases
• Establish and regularly review
achievable outcomes, output and
targets as part of the development
and delivery of projects and
realization of benefits in line with the
Benefits Realisation Plan 
AGDRISK07 (formerly 6)
Failure to deliver community
benefits from AGD 
Scoring – 9 
CHANGE – to reflect
increase in likelihood 
Score 6  Score 9 
AMBER
/GREEN
• PMO and procurement managers from
the three Ayrshire Councils have
developed a AGD Community Benefit
Tracker, a single mechanism to
monitor delivery of community
benefits so that remedial action can
be taken if required
• Result from the AGD Community
Benefits Tracker system will be

Page 12

analysed and reported to the Regional
Economic Partnership and Regional
Economic Joint 
• PMO working with Project Leads to
develop consistent approach to
embedding inclusive growth,
equalities, clean growth, and
community wealth building within
business cases through the Annual
Performance Report
• Procurement working group has been
established and operates in order to
support delivery of community
benefits which includes development
of a Community Benefits Tracker and
coordination of procurement
approaches so they support the
development and delivery of projects
AGDRISK08 (formerly 7)
Failure to deliver individual
projects within the AGD
programme 
Scoring – 12 
CHANGE – to reflect
increase in likelihood 
Score 8 
PUT UP 1, STILL
AMBER?
Score 12 
AMBER/RED
• Regular dialogue/reporting around
progress undertaken between PMO
and Project Leads. Seek to identify
issues early and raise with Senior
Management and/or the
Governments, AEPB and AEJC.
Regular monitoring and reporting e.g.
quarterly to the AEPB/AEJC, and
monthly to AGD Steering Group and
Project Boards.
• Partners regularly review the AGD
Benefits Realisation Plan every 12
months and report to the AEPB/AEJC.
Current change management process
incorporated in the AGD Governance

Page 13

document and regularly reviewed 
• Risk register in place for each project
which is regularly reviewed via
monthly reports, quarterly reports
and when updating the
Implementation Plan
• Project risk registers included in
business cases which are formally
approved by government and AEJC
• Management Information System in
place and used to track progress of
projects against key milestones, and
reported via monthly and quarterly
reports
AGDRISK09 (formerly 8)
Inadequate recognition of
interdependencies and/or
knock-on impacts between
parts of the programme
leading to issues with
delivery and/or lost
opportunities. 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9 
AMBER
/GREEN
• Programme meetings take place
regularly between PMO, Project Leads
and partners to ensure 
interdependencies are recognised and
considered; and incorporated in
approved business cases
• PMO working closely with project
leads to ensure interdependencies are
fully articulated within the project
business cases and for the
programme as a whole.
• All forms of interdependencies are
monitored and managed to help
enable the development and delivery
of all Deal projects
AGDRISK010 (formerly 9)
Lack of resource within
partner organisations to
deliver projects in line with
Score 9  Score 9 
AMBER
/GREEN
• Formal approvals of Councils’
resources are now in place for AGD
projects
• Each Council has appointed staff

Page 14

AGD programme 
Scoring – 9 
NO CHANGE IN SCORING 
and/or consultants to support project
development and delivery
• Each project currently has a Project
Lead in place
• Partners including SE are providing
additional resource to relevant
projects
• Resources committed to the delivery
of the programme, with further
discussions underway to explore how
to deliver the recently approved
Regional Economic Strategy 
• Other funding streams is being
explored to support ongoing revenue
costs
• Anticipated revenue streams will be
subject to constant review through
the monitoring procedures in place for
AGD 
AGDRISK11 (formerly 10)
Lack of resources in PMO 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9 
AMBER/
GREEN
• A permanent PMO structure is in place
with recruitment now completed. 
• The PMO is being supported by
colleagues in each of the Councils in a
number of work streams
• PMO undertaking a review of capacity
and skill sets in response to the
changing requirements on staff that
form the Office
AGDRISK12 (formerly 11)
Inadequate governance
arrangements to support
AGD delivery 
Score 6  Score 6 
AMBER/
GREEN
• In accordance with AGD governance,
AEPB and AEJC has been formed and
regular meetings are in place
• Scottish Government’s financial
reporting requirements have been

Page 15

Scoring - 6 
NO CHANGE IN SCORING 
implemented in the AGD Governance
document and Financial guidance
• Partner agreement between EAC, as
Accountable Body for the Deal, and
North and South Ayrshire Councils
has been drawn up and terms agreed 
• Partners working together with both
Governments to keep under review
the AGD Benefits Realisation Plan 
• Current change management process
in place and subject to regular review
with input from the Governments and
Partners AGD is standing item on
CEOs’ meeting agenda
AGDRISK13 (formerly 12) 
Monitoring & Evaluation
Framework is not sufficiently
defined 
Score – 6 
NO CHANGE IN SCORING 
Score 6  Score 6 
AMBER/
GREEN
PMO undertaking ongoing review of
the overarching Monitoring and
Evaluation Framework for the Deal. 
This will ensure acceptable M&E
arrangements.
AGDRISK14 (formerly 13)
Failure to attract commercial
interest in AGD 
Scoring – 12 
CHANGE – to reflect
increase in likelihood 
Score 8  Score 12 
AMBER/RED
• Following conclusion of the
Programme Review commitment to
develop with communications and
economic development teams, a
market campaign, subject to
resources. This will form part of
Communication Plan and will target
potential investors Communications

Page 16

Action Plan continues to be developed
and updated, including a pipeline of
project specific communications
plans. Current private sector
investment is below expected target
for the agreed AGD. 
• Regular briefings with a range of
stakeholders 
• Wider Ayrshire Economic Strategy is
now approved by the AEJC and will
ensure wider growth ambitions for
Ayrshire are achieved. This will help
support attracting greater investment
into Ayrshire. 
AGDRISK15 (formerly 14)
Programme not
communicated effectively to
stakeholders outwith
Governance structure 
Scoring 12 
NO CHANGE IN SCORING 
Score 12  Score 12 
AMBER/RED
• Communications Action Plan
completed and regularly updated, in
conjunction with communication
teams. This includes reporting on past
and future communication activity.
AGD website launched and to be
reviewed in conjunction with
communications teams, in order to
increase traffic and sharing of AGD
information
• AGD social media channels to be
reviewed in conjunction with
communications teams, with greater
linkages made to activity related to
the AGD and its progress
• Regular briefings with a range of
stakeholders via AGD programme
update to the AEPB and AEJC
• Communications Protocol in place and

Page 17

reviewed and updated annually, with
activity regularly identified and
delivered with the support of
communication teams.
• Resource within AGD to market and
promote project activities and overall
programme
AGDRISK16 (formerly 15)
Supply phasing within
overall programme 
Scoring – 12 
NO CHANGE IN SCORING 
Score 12  Score 12 
AMBER/RED
• PMO help facilitate and update
Procurement teams of the AGD
programme and relevant projects in
terms of timescale for development
and delivery. This includes how to
manage expected peaks in
programme activity and need for
contracts to be advertised and
managed. 
• PMO working with procurement in
supporting the sharing of market
intelligence and the phasing of
development activity, this includes
ensuring procurement leads sign off
when updating Implementation Plans.
AGDRISK17 (formerly 19)
Loss of IT systems 
Scoring – 8 
NO CHANGE IN SCORING 
Score 8  Score 8 
AMBER
/GREEN
• PMO hosted by EAC and as such 
supported by IT recovery protocols
and security systems of EAC to limit
risk and mitigation measures
• Corporate IT recovery protocol and
security systems limit the risk and
mitigation measures
• Contingency Plan in place via EAC for
the PMO, by SAC for the portal, and
for the AGD teams across the three
councils, by their respective employer

Page 18

(e.g. EAC, SAC, NAC)
AGDRISK18 (formerly 20)
Failure to ensure AGD
projects working towards net
zero ambitions as set by
SG/UKG 
Scoring – 8 
NO CHANGE IN SCORING 
Score 8  Score 8 
AMBER
/GREEN
• PMO and Project Leads working with
Scottish Government to ensure the
Deal is aligned with Scotland’s
transition to net zero carbon
emissions by 2045
• UK and Scottish Governments
developed carbon management
guidance for the AGD, as well as other
City Region and Growth Deals in
Scotland, which will allow the carbon
emissions impact of the programme
and projects to be assessed then
minimised.
• Consideration to be given to the
recent Scottish Government
announcement on annual and interim
targets for cutting greenhouse gases
and impact upon projects contributing
to net zero (April 24).  
• A carbon management process
appropriate for each project has been
put in place to ensure any carbon
emissions impact is minimised via
business case process
• PMO working with both Governments
to identify funding opportunities to
support decarbonisation
• PMO is working with both
Governments to agree an overarching
Monitoring and Evaluation Framework
for the Deal

Page 19

AGDRISK19 (formerly 21)
Potential impact of macro
events on the wider
economy and econmic
propserity of Ayrshire 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16 
RED
• Regular engagement with Project
Leads to highlight any risks well in
advance, so that the PMO can raise
with Government, AEPB and AEJC as
appropriate
• Regular review via monthly reports of
outputs and timelines for business
cases at every stage of development
in the light of external events 
• Continued monitoring of external
environment and government
relations
• Regional Economic Strategy approved
in early 2023 and be supported by an
emerging action plan
• AEJC  provide voice for Ayrshire to
press the case for government
intervention investment
• Seek to align incentives and other
forms of assistance to complement
the AGD and stimulate greater
economic activity
• Current change management process
in place but under review
• Regional Skills Investment Plan
developed, with a focus on its
implementation via Ayrshire Skills
Group
• Robust data analysis shared amongst
key partners and stakeholders to
reach common understanding of local
economic conditions, leading to early
identification of real threats and

Page 20

opportunities - Supported by
proposed appointment of Glasgow
Intelligence Unit to revise AGD
economic model. 
• PMO co-ordinate evidence across
Deals and submitted collective case
via the Implementation Plan update
to both governments setting out
impact of increased costs or reduced
the scope/outputs and time delivery if
costs not met