AYRSHIRE ECONOMIC PARTNERSHIP BOARD
MEETING – 23 AUGUST 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL 
SUBJECT: AYRSHIRE GROWTH DEAL – AGD ECONOMIC MODELLING
UPDATE 
PURPOSE OF REPORT 
1. To advise the Economic Partnership Board Members on an update on the
AGD Economic Modelling used by the PMO and the accessing an
enhanced service from the Glasgow Intelligence Unit. 
RECOMMENDATIONS 
2. Agree the content of the report and recommend approval to the Ayrshire
Economic Joint Committee to note 
(i) the development of a Service Level Agreement with the Glasgow City
Region Intelligence Hub (GCRIH) for an enhanced economic model to
support the development and monitoring of projects for the AGD; and
(ii) provide ‘in principle’ support to the PMO to complete negotiation for a
SLA, subject to legal and procurement advice being met. 
BACKGROUND 
3. The PMO as a core function as set out by the AGD Governance are
required to host an economic model. Since 2019 the PMO have operated
an AGD economic modelling tool that has helped inform a number of
projects in the development of their business cases e.g. economic case.
This is a simple model that is more effective where projects seek to
develop new builds where the proposed land use will relate to one of the
categories captured by the Use Class Orders.   
4. Overtime the robustness of the model has been questioned and in
response the PMO sought external body to review the model. This has
been supported by the feedback received from the Governments when
commenting upon the economic cases of business cases. In early 2024
the Glasgow City Region Intelligence Hub (GCRIH) were contacted to
review the AGD economic model. They were approached on the grounds
that they provide economic modelling advice to the Glasgow City Region
Deal and beyond, and have supported the development of business
cases and funding bids which have been accepted by the Governments.

Page 2

5. Their findings recommended that a number of significant changes would
be needed to be undertaken in order for the model to be sufficiently robust
and meaningful. In addition they highlighted the limitations of the model.
Ultimately it was recognised that the best way forward would be to work
with the Glasgow Intelligence Hub in aligning the AGD economic model
with that used by the Glasgow City Region. In addition, ensure the
updating of the AGD model, although hosted by the PMO, is shared and
accessible to Partners in Ayrshire.   
MAIN REPORT 
THE OFFER – DRAFT SERVICE LEVEL AGREEMENT 
6. The PMO has negotiated a Service Level Agreement (SLA) with the GCRIH
that will overhaul the AGD economic model and align it with that used for the
Glasgow City Region and other initiatives undertaken by the City Region. 
7. The draft SLA has been developed with the support of EAC legal team and
will be shared with the procurement team to ensure compliance with relevant
requirements. Both teams will continue to be engaged in the completion of
the SLA and its delivery. 
8. In addition the SLA will also include the following conditions:
• Maintenance undertaken by the Hub so ensuring all relevant
underlying data is updated. This predominately includes national
data from Government sources. 
• Programme of updates to be undertaken of all AGD projects
information used to inform business cases. This will not replace
existing modelling tools used for business cases already approved
or are at an extensive stage of development, but provide a
consistent tool in which to capture potential economic outputs and
outcomes at a Programme level. 
• Training for the PMO and key AGD teams across Ayrshire so that
the operation, maintenance and outputs of the model are
understood and be effectively applied to AGD projects and other
initiatives where the model can be used. 
• Initially a 3 year agreement with an opportunity to terminate or
continue on a rolling year contract. 
9. The cost of the SLA has been agreed at £25-30k for the updating the model
and development of a revised version aligned with that used by the Hub for
the Glasgow City Region. In addition there will be a £3k commitment per
year for the lifetime of the contract to cover continued maintenance of the
model.  For over three years the total costs would be £39k (maximum) which
split between the three Ayrshire Councils would equate to £13k, with the first
year of the agreement requiring a contribution of £11k from each authority.
Subsequent years would be £1k per year.

Page 3

BENEFITS 
10. The benefits of using the Hubs model has already been demonstrated
through the development of the business cases for the AGD AMIC and
Moorfield projects, where EAC officers worked closely with the Hub’s team.
The details generated have resulted in a robust economic case that is
currently being considered by the Governments. 
11. Other benefits the new model will provide include:
• A Programme level economic model that could be applied to all AGD
projects, and hence provide an updated and robust evidence base
on the potential economic benefits from the Programme.
• The potential to consider unique environmental and social impacts,
due to the ongoing development of the Hub’s model, which is
seeking to investigate effective ways of capturing the economic
consequences upon environmental and social issues. An approach
which the AGD, if aligned, could learn from and incorporate moving
forward. 
• A tool that can be applied beyond AGD projects but also for other
initiatives where a business case aligned to the HM Treasury Green
Book is required e.g. LUF, and potential new regional/local
economic development Government sponsored initiatives. 
• Provide a tool that can support for the implementation of relevant
actions of the Ayrshire Regional Economic Strategy, by providing
economic evidence at a local and regional level.
• An opportunity to build resilience in the PMO and AGD teams on
knowledge, experience and skills in economic modelling. In time this
will lead to the AGD model being supported solely by Ayrshire staff,
which could result in the reduction of costs and dependencies on
external consultants. 
IMPLICATIONS 
12. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 13-14
2.Governance/Legal Yes  Para 16
3. Human Resources Yes  Para 18
4. Equality and Fairer Scotland Duty Yes  Para 19
5. Financial  Yes  Para 15
6. Risk  Yes  Para 19
7. Community Wealth Building   No 
8. Net Zero   No

Page 4

ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
13. Inclusion is a key driver for the AGD. Deal business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
14. Ensuring a robust economic modeling tool is available for the AGD is a key
requirement of the PMO’s function in supporting the delivery of sustainable
development and inclusive economic growth across Ayrshire and in line
with the Deal objectives. 
FINANCIAL IMPLICATIONS 
15. The principal financial implications relate to costs associated with
appointing the GCRIH to deliver the SLA. It is recognised that there will be
initial costs but as set out in the above report the benefits derived from the
investment outweigh these costs. 
LEGAL IMPLICATIONS 
16. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the recently revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2023. 
RISK IMPLICATIONS 
17. The management of Risks will be undertaken through the managing and
monitoring of the SLA and will be led by the PMO, with updates on
progression provided to Senior Responsibility Officers for each Ayrshire
Council. 
HUMAN RESOURCES IMPLICATIONS 
18. There are no immediate human resource implications arising from this
report. All named key AGD projects are resourced to develop and deliver
the AGD programme. 
EQUALITY IMPACT ASSESSMENT 
19. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business
case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES

Page 5

None 
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk