AYRSHIRE ECONOMIC PARTNERSHIP BOARD
MEETING – 25 APRIL 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL 
SUBJECT: AYRSHIRE GROWTH DEAL – PROGRAMME RISK REGISTER
UPDATE – MARCH 2024 
PURPOSE OF REPORT 
1. To advise the Economic Partnership Board Members on the update for the
AGD Programme Risk Register. 
RECOMMENDATIONS 
2. Agree the content of the report and recommend approval to the Ayrshire
Economic Joint Committee to note 
(i) Approve the updated Programme Risk Register dated March 2024 
BACKGROUND 
3. The AGD Programme Risk Register is a key tool in which to monitor and
evaluate potential risks associated with the development and delivery of the
programme. The Ayrshire Economic Joint Committee (AEJC) (dated 26
June 23) approved the quarterly review and reporting of the AGD
Programme Risk Register as a separate item on future AEPB and AEJC
meetings. 
4. It should be noted that the top scoring programme and project risks are
reported to the Chief Executives Group, Steering Group, AEPB and AEJC
on a regular basis via the sharing of the monthly reports. 
MAIN REPORT 
5. The PMO reviews regularly the Programme Risk Register in line with the
recommendations of the AEJC. This has included reviewing the nature of
the risks, their RAG status/scoring, and the mitigation measures used to
reduce the potential of risk. The review covers Q4 23/24 up to end of March
2024. 
6. Since reporting last to the Board the PMO is now fully staffed with the

Page 2

following positions forming the team: 
7. As previously reported it should be noted that the PMO has undertaken a
review of capacity and skill sets held in the Office. This is in response to the
changing calls on the staff to support the delivery of the Programme.
Discussions are currently underway with three funding Ayrshire Councils on
the implications of the review. In terms of the Risk Register the scoring for
AGDRISK10 - Lack of resources in PMO, remains the as previously
reported. 
8. The remaining risks identified with a ‘red’ RAG status are proposed not to
be changed. These are: 
(i) AGDRISK01 - Failure to achieve AGD programme objectives within
agreed budget
(ii) AGDRISK02 - Failure to provide accurate projections for programme
spend 
(iii) AGDRISK03 - Failure to drawdown full AGD funding
(iv) AGDRISK04 - Delays in development and approval of business cases
(v) AGDRISK21 - Potential impact of international events upon cost of living
crisis and economic prosperity of Ayrshire 
9. The external context has not changed with significant environmental
challenges such as the legacy of the Covid and Brexit, and the ongoing
Ukraine war. Combined, these challenges have contributed to increased
cost pressures that continue to impact upon the development and delivery
of projects and the programme as a whole (AGDRISK21). 
10. It is expected the rating of the ‘Red’ risks (AGD RISK01-04) is however
expected to change once the outcome of the ongoing Programme Review is
concluded and enacted. The Programme Review is ongoing and outcomes
emerging that will be reported to the AEPB in the coming weeks. These
outcomes will influence the updating of the draft Implementation Plan 24/25
which will incorporate the revised Financial Plan and updated Benefit.
AGD - Strategic
Lead (G16)
AGD - Programme
Manager (G14)
AGD - Compliance
& Performance
Officer (G12)
AGD - Business
Assistant (G5)

Page 3

Together these Plans will have an impact upon the current risk ratings.
11. In conclusion the Programme Risk Register provides a realistic reflection of
the state of the challenges the programme are continuing to face. As noted
the PMO are working across the partnership to conclude the Programme
Review. Once agreed the Programme Review will provide a sound baseline
in which to ensure the delivery of projects, which will help de-risk the current
‘red’ risks. 
IMPLICATIONS 
12. Eight implications have been considered in the preparation of this report. 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 13-14
2.Governance/Legal Yes  Para 16
3. Human Resources Yes  Para 17
4. Equality and Fairer Scotland Duty Yes  Para 18
5. Financial  Yes  Para 15
6. Risk  Yes  Whole paper
7. Community Wealth Building   No 
8. Net Zero   No 
ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
13. Inclusion is a key driver for the AGD. Deal business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
14. The Risk Register provides the framework for reviewing the challenges the
Deal needs to address and enables effective mitigation measures to be
undertaken that include meeting the headline Deal objective of delivering
inclusive growth. 
FINANCIAL IMPLICATIONS 
15. It is accepted by the Ayrshire Councils and the Government that risks
should be managed and mitigated where necessary in order to support the
effective delivery of projects and the programme. 
LEGAL IMPLICATIONS 
16. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the recently revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2022. 
HUMAN RESOURCES IMPLICATIONS

Page 4

17. There are no immediate human resource implications arising from this
report. However for the risk associated with lack of resources in PMO to be
addressed there could be human resource implications. 
EQUALITY IMPACT ASSESSMENT 
18. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business
case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES 
Appendix 1: Updated Risk Register – March 2024
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk

Page 5

Appendix 1:
AYRSHIRE GROWTH DEAL UPDATED PROGRAMME RISK REGISTER (RISKS AND MITIGATIONS) – MARCH 2024 
RISK Current
Matrix and
Score
Proposed
Matrix and
Score
MITIGATION
AGDRISK01
Failure to achieve AGD
programme objectives
within agreed budget 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16  • The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group in place
to monitor progress and to address any weaknesses
or issues that could impact on overall delivery. 
• PMO ongoing monitoring and evaluation of Deal and
project objectives in order to address issues early.
This includes responding to increasing costs of
general capital works within the context of the
original funding made available by the Government
in 2019. Leading to potential to review risks where
evidence suggests insufficient funding to undertake
and complete projects in line with expected
outcomes.
• PMO undertake ongoing environmental analysis to
ensure programme objectives are relevant/valid as
well as maximised where relevant and new benefits
identified when materialising.
• Internal governance include regular reviews
undertaken by PMO with input from SROs, Project
Leads and Chief Executives to ensure AGD
programme objective are met.
AGDRISK02
Failure to provide accurate
projections for programme
spend 
Score 16  Score 16  • Issues will be escalated to CEOs, Regional Economic
Partnership and Regional Economic Joint Committee
as appropriate 
• The Implementation Plan and Financial Plan being

Page 6

Scoring –  - 16 
NO CHANGE IN SCORING 
updated to take account of Programme Review
outcomes. Project Leads have sought to address
delays in gaining approved FBCs, by undertaking
reviews of projects to fit existing budgets, which are
shared with Finance Directors, the government and
wider partners. Revised project mitigation measures
seek to demonstrate how inflationary pressures will
be managed
• Business Case process monitored to ensure
streamlined pathway to approval enabling projects
to achieve FBC as quickly as possible to reach
project delivery and clarity on expected spend.
• PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs
and Finance Directors and ensure drawdown
projections align with delivery timescales
• OBCs/FBCs include an optimism bias factor as per
Treasury Green Book and AGD Governance
document
• Inflationary factor addressed through project
reviews e.g. re-scoping, phasing and reviewing
benefits
AGDRISK03
Failure to drawdown full AGD
funding 
Scoring –   - 16 
NO CHANGE IN SCORING 
Score 16  Score 16  • PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs
and Finance Directors and ensure drawdown
projections align with delivery timescales. This
includes PMO working with Project Leads, SRO’s and
S95’s to ensure projects can be realised and help
with change processes where necessary; and
undertaking effective communication with
Governments to ensure projects can be realised
• Achieve business case approval in line with latest
Deal Implementation Plan, and AGD Governance

Page 7

document and, Finance guidance
• Annual review of Financial Plan and Implementation
Plan
• The Scottish Government’s financial reporting
requirements will be implemented
• Pivot projects proactively where possible in line with
need and opportunity
• Internal procedures, financial controls and
processes in place to mitigate this risk
AGDRISK04
Delays in development and
approval of business cases 
Scoring – 16
NO CHANGE IN SCORING 
Score 16  Score 16  • Undertake focused engagement with SG and UKG in
order to help ensure SBC, OBC and/or FBC comply
with the Treasury Green Book and gain approval pin
line with AGD governance
• PMO working closely with Project Leads and Policy
Leads within UK and Scottish Governments to
support business case development and approval to
an agreed timeline. This includes exploring a
streamlined change process (pre-FBC) particularly
where budget constraints are sole driver of change.
• Project Leads have received Green Book business
case training
• Project Leads’ toolkit in place
• Other partners assisting in developing business
cases where capacity is low
AGDRISK05
Failure to capture accurate
baseline data 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9 • Project Leads required to establish appropriate
economic, social and environmental baseline
information in business cases
• Establish and regularly review achievable outcomes,
output and targets as part of the development and
delivery of projects and realization of benefits in line
with the Benefits Realisation Plan

Page 8

AGDRISK06
Failure to deliver community
benefits from AGD 
Scoring – 6 
NO CHANGE IN SCORING
Score 6  Score 6  • PMO and procurement managers from the three
Ayrshire Councils have developed a AGD
Community Benefit Tracker, a single mechanism to
monitor delivery of community benefits so that
remedial action can be taken if required
• Result from the AGD Community Benefits Tracker
system will be analysed and reported to the
Regional Economic Partnership and Regional
Economic Joint 
• PMO working with Project Leads to develop
consistent approach to embedding inclusive growth,
equalities, clean growth, and community wealth
building within business cases through the Annual
Performance Report
• Procurement working group has been established
and operates in order to support delivery of
community benefits which includes development of
a Community Benefits Tracker and coordination of
procurement approaches so they support the
development and delivery of projects
AGDRISK07
Failure to deliver individual
projects within the AGD
programme 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8  • Regular dialogue/reporting around progress takes
place between PMO and Project Leads where issues
are raised in advance and if appropriate escalated
to government, Regional Economic Partnership and
Regional Economic Joint Committee, this includes
early discussions with both UK and Scottish
Government
• The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group and
Project Boards in place to monitor project
development, via monthly reports
• Partners are regularly reviewing the AGD Benefits
Realisation Plan every 12 months and reported to

Page 9

the Regional Economic Partnership and Regional
Economic Joint Committee
• Current change management process incorporated
in the AGD Governance document and regularly
reviewed 
• Risk register in place for each project which is
regularly reviewed via monthly reports, quarterly
reports and when updating the Implementation Plan
• Project risk registers included in business cases
which are formally approved by government and
Regional Economic Joint Committee
• Management Information System in place and used
to track progress of projects against key milestones,
and reported via monthly and quarterly reports
AGDRISK08
Inadequate recognition of
interdependencies and/or
knock-on impacts between
parts of the programme
leading to issues with
delivery and/or lost
opportunities 
Scoring – 9 
NO CHANGE IN SCORING
Score 9  Score 9  • Programme meetings take place regularly between
PMO, Project Leads and partners to ensure 
interdependencies are recognised and considered;
and incorporated in approved business cases
• PMO working closely with project leads to ensure
interdependencies are fully articulated within the
project business cases and for the programme as a
whole.
• All forms of interdependencies are monitored and
managed to help enable the development and
delivery of all Deal projects
AGDRISK09
Lack of resource within
partner organisations to
deliver projects in line with
AGD programme 
Scoring – 9
Score 9  Score 9  • Formal approvals of Councils’ resources are now in
place for AGD projects
• Each Council has appointed staff and/or consultants
to support project development and delivery
• Each project currently has a Project Lead in place
• Partners including SE are providing additional
resource to relevant projects

Page 10

NO CHANGE IN SCORING   
• Resources committed to the delivery of the
programme, with further discussions underway to
explore how to deliver the recently approved
Regional Economic Strategy 
• Other funding streams is being explored to support
ongoing revenue costs
• Anticipated revenue streams will be subject to
constant review through the monitoring procedures
in place for AGD 
AGDRISK10
Lack of resources in PMO 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9  • A permanent PMO structure is in place with
recruitment now completed. 
• The PMO is being supported by colleagues in each
of the Councils in a number of work streams
• PMO undertaking a review of capacity and skill sets
in response to the changing requirements on staff
that form the Office
AGDRISK11
Inadequate governance
arrangements to support
AGD delivery 
Scoring - 6 
NO CHANGE IN SCORING
Score 6  Score 6  • In accordance with AGD governance, Ayrshire
Economic Joint Committee and Ayrshire Regional
Economic Partnership has been formed and regular
meetings are in place
• Scottish Government’s financial reporting
requirements have been implemented in the AGD
Governance document and Financial guidance
• Partner agreement between EAC, as Accountable
Body for the Deal, and North and South Ayrshire
Councils has been drawn up and terms agreed 
• PMO working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
• Partners working together with both governments to
keep under review the AGD Benefits Realisation Plan

Page 11

• Current change management process to be
reviewed with the governments and partners
• AGD is standing item on CEOs’ meeting agenda
AGDRISK12 - Monitoring &
Evaluation Framework is not
sufficiently defined 
Score – 6 
NO CHANGE IN SCORING
Score 6  Score 6  • PMO undertaking ongoing review of the
overarching Monitoring and Evaluation Framework
for the Deal which will be developed and published
on the AGD web site. This will ensure acceptable
M&E arrangements. 
AGDRISK13
Failure to attract commercial
interest in AGD 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8  • Following conclusion of the Programme Review
undertake with communications and economic
development teams, a market campaign will be
developed, as part of Communication Plan and
target potential investors
• Communications Action Plan continues to be
developed and updated, including a pipeline of
project specific communications plans
• Regular briefings with a range of stakeholders 
• Wider Ayrshire Economic Strategy is now approved
by the Regional Economic Joint Committee and will
ensure wider growth ambitions for Ayrshire are
achieved
AGDRISK14
Programme not
communicated effectively to
stakeholders outwith
Governance structure 
Scoring 12 
Score 12  Score 12  • Communications Action Plan completed and
regularly updated, in conjunction with
communication teams. This includes reporting on
past and future communication activity AGD website
launched and to be reviewed in conjunction with
communications teams, in order to increase traffic
and sharing of AGD information
• AGD social media channels to be reviewed in

Page 12

NO CHANGE IN SCORING  conjunction with communications teams, with
greater linkages made to activity related to the AGD
and its progress
• Regular briefings with a range of stakeholders via
AGD programme update to the Regional Economic
Partnership and Regional Economic Joint Committee
• Communications Protocol in place and reviewed and
updated annually, with activity regularly identified
and delivered with the support of communication
teams.
• Resource within AGD to market and promote project
activities and overall programme
AGDRISK15
Supply phasing within
overall programme 
Scoring – 12 
NO CHANGE IN SCORING 
Score 12  Score 12  • Engagement undertaken in 2022 with the
construction sector in order promote and explain the
potential of the AGD programme to local businesses,
so increase Invitation to Tender for future contracts.
Review opportunity to repeat the exercise.
• PMO help facilitate and update Procurement teams
of the AGD programme and relevant projects in
terms of timescale for development and delivery.
This includes how to manage expected peaks in
programme activity and need for contracts to be
advertised and managed. Market engagement
through the Meet the Buyer events with the next
being held in the Autumn 2023
• PMO working with procurement in supporting  the
sharing of market intelligence and the phasing of
development activity
AGDRISK19
Loss of IT systems 
Scoring – 8 
Score 8  Score 8  • PMO hosted by EAC and as such  supported by IT
recovery protocols and security systems of EAC to
limit risk and mitigation measures
• Corporate IT recovery protocol and security systems
limit the risk and mitigation measures

Page 13

NO CHANGE IN SCORING    • Contingency Plan in place via EAC for the PMO, by
SAC for the portal, and for the AGD teams across
the three councils, by their respective employer
(e.g. EAC, SAC, NAC)
AGDRISK20
Failure to ensure AGD
projects align with a net zero
transition 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8  • PMO and Project Leads working with Scottish
Government to ensure the Deal is aligned with
Scotland’s transition to net zero carbon emissions
by 2045
• UK and Scottish Governments developed carbon
management guidance for the AGD, as well as other
City Region and Growth Deals in Scotland, which will
allow the carbon emissions impact of the
programme and projects to be assessed then
minimised
• A carbon management process appropriate for each
project has been put in place to ensure any carbon
emissions impact is minimised via business case
process
• PMO working with both governments to identify
funding opportunities to support decarbonisation
• PMO is working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
AGDRISK21
Potential impact of
international events upon
cost of living crisis and
economic prosperity of
Ayrshire 
Score 16  Score 16  • Regular engagement with Project Leads to highlight
any risks well in advance, so that the PMO can raise
with government, Regional Economic Partnership
and Regional Economic Joint Committee as
appropriate
• Regular review via monthly reports of outputs and
timelines for business cases at every stage of

Page 14

Scoring – 16 
NO CHANGE IN SCORING 
development in the light of external events 
• Continued monitoring of external environment and
government relations
• Regional Economic Strategy approved in early 2023
and be supported by an emerging action plan
• Regional Economic Partnership will provide voice for
Ayrshire to press the case for government
intervention investment
• Incentives and other forms of assistance to
complement the AGD and stimulate greater
economic activity
• Current change management process to be
reviewed with both governments and partners
• Regional Skills Investment Plan developed, with a
focus on its implementation via Ayrshire Skills
Group
• Robust data analysis shared amongst key partners
and stakeholders to reach common understanding
of local economic conditions, leading to early
identification of real threats and opportunities -
achieving consensus with partners and stakeholders
on strategic objectives for inclusive and sustainable
economic growth, with effective action planning and
monitoring
• PMO co-ordinate evidence across Deals and
submitted collective case via the Implementation
Plan update to both governments setting out impact
of increased costs or reduced the scope/outputs and
time delivery if costs not met