AYRSHIRE ECONOMIC PARTNERSHIP
BOARD  MEETING – 19 FEBRUARY 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL 
SUBJECT: AYRSHIRE GROWTH DEAL - PROGRAMME UPDATE 
PURPOSE OF REPORT 
1. To advise the Economic Partnership Board members of the progress of the Ayrshire
Growth Deal and the development of its component projects as at 31 January 2024
(Appendix 1). 
RECOMMENDATIONS 
2. Agree the content of the report and recommend approval to the AEJC to note: 
(i) The updates provided in the attached report;
(ii) The progress across the Ayrshire Growth Deal Programme; and
(iii) Note the outcome of the Annual Conversation and the development of Summary
of the Programme Review.
(iv) Note the progress made and next steps of the Programme Review 23-24. This
includes noting the various work streams which will inform the Review’s outcome. 
BACKGROUND 
3. This report is an update on the progress made on the Ayrshire Growth Deal (AGD). It
has been prepared in line with the agreed governance structure and its commitment to
monitoring and reporting progress across all parts of the Deal’s programme on regular
basis. 
4. A summary of the current status of the programme priorities and the development work
associated with individual projects is contained within the progress report attached to
this covering report. The report covers progress up to 31 January 2024. Please see
Appendix 1). The previous update was reported to the Ayrshire Economic Partnership
Board (AEPB), on 16 November 2023, and included progress up to the 31 October
2023. 
5. Please note that the reporting period has sought to align as much as possible with the
with the financial year’s quarters. This report includes progress made in Q3. Timing of
this report has been delayed partly due to the Annual Conversation which took place
on the 31 January 2024 and the opportunity to update the Board on its outcomes. 
6. The report considers the progress made on the Deal at both a programme and project

Page 2

level. This includes an update on the Red/Amber/Green (RAG) status in regards to
meeting milestone timelines, scope, budget and overall progress. Supporting narrative
is provided where necessary. (Please see Programme and Project Introductions –
Appendix 1). 
MAIN REPORT 
7. The overall status for the programme is still remains as ‘red’. This reflects the continued
challenges project leads are meeting in addressing cost pressures within a fixed
budgets. 
8. Since last reporting to the Board the PMO in consultation with senior management from
the three Ayrshire Councils have undertaken a thorough review of individual projects
and the programme as a whole. 
9. The Annual Conversation is an annual event with the Government and is a requirement
of the Grant Offer Letter. It generally focuses on the Looking Back and Looking Forward
on the progress of the Programme. This time around the focus of discussions were on
the Programme Review. The principal outcome was that the Government
acknowledged that there has been significant challenges with costs pressures, and
that the Programme Review provides an opportunity to reinvigorate the Deal and
provide a sure footing for its delivery moving forward. 
KEY POINTS
Programme level 
10. In December a formal Letter of intent as prepared by the Partnership was submitted to
the Government. It set out the intension of undergoing a midterm review in line the
AGD Governance (e.g. Checkpoint Review - para 3.5 Governance Document v15
December 22). 
11. The Government confirmed receipt in January 2024 and acknowledged the indicative
stages/timetable for the Programme Review 23-24 as set out below: 
Pre-emptive review of projects across all three
Ayrshire Councils 
Summer-Autumn 23
Formalise the Review of the Programme and Capital
Projects 
Nov-Dec 23
Share direction of travel and provisional proposal with
the Government as part of a series of ‘conversations’
e.g. ‘Annual Conversation’ on the 31 January 24.
Jan 24
Prepare change management papers with a
Programme overview supported by summary of project
review papers
Feb 24
Present papers to the Partnership Board and Joint
Committee
Early 2024 (ready for the
new FY 24/25) 
12. Early indications of the Review have identified the need to manage several key
elements in order to develop a finalised Revised Programme that is sufficiently robust

Page 3

and deliverable. Components include review of the:
• Programme and financial management
• Allocation of funds and the potential for reapportionment 
• Governance and change management process
• Benefits delivered and what can now be achieved
• Communications of the Deal in terms of managing the Review outcomes and
reinvigorating awareness and interest in the Deal. 
13. The Review is recognising that there is potential multiple changes across the
Programme to manage. In addition there are a number of projects where clarity on the
changes needed will not be achieved by the original deadline for finalising the
Programme Review (e.g. end of March 24). This is due to a number of dependencies
related to specific projects. A robust body of evidence has now been gathered and the
PMO with the support of the three Councils are pulling together a Summary profile of
the emerging Programme and the changes made. A draft will then be shared with the
Government in order to gain their early feedback and be presented to the Partnership
Board and Joint Committee for their consideration, in accordance with the AGD
Governance. 
Programme Financial Update 
14. The latest financial update (January 2023) included in the monthly report provides a
spend projection for the programme and individual projects. 
15. As previously reported their expected a shortfall between the protected spend and
drawdown from the grant allocation for this financial year (2023/24) against the Grant
Offer Letter 2023/24. This is principally around significant shortfall for the capital
projects such as Spaceport and Commercial Space. Less substantial shortfalls are
expected for i3 Flexi Space and CoRE. 
16. In terms of the revenue projects there is an expected shortfall in spend and drawdown
for Ayrshire Skills Investment Fund due to the lateness in the project gaining FBC
approval, and Community Wealth Building where the project is now expected to run for
an additional year. Working for a Healthy Economy is the only project where the spend
profile matches expectations. Please see details below: 
Capital
Projects
Grant Offer Letter
23/24 (£m)
Projections As at
P9 return (Dec 23)
(£m)
Differences (£m)
Spaceport 2.855 0 -2.855
Commercial
Space
17.689 1.350 -16.339
I3 Flexi Space 2.339 1.440 -0.899
CoRE 0.300 0 -0.300
TOTAL 23.184 2.790 -20.393

Page 4

Revenue
Projects
Grant Offer Letter
23/24
Projections As at
P9 return (Dec 23)
(£m)
Differences
Working for
Healthy
Economy
0.703 0.703 0
Ayrshire Skills
Investment
Fund
0.850 0.159 -0.691
Community
Wealth
Building 
1.073 1.032 -0.041
TOTAL 2.626 1.895 -0.732 
17. As a total the Programme is expected to drawdown £4.685m as opposed to £25.810m,
a potential drop of £21.125m. Further details of the current financial position is set out
in paragraphs 32-35. 
18. In addition and in accordance with the Grant Offer Letter conditions, the PMO is in the
process of preparing the Bi-annual Return which needs to be submitted to the
Government by the end of February 2024. This Return will be used to inform the
forthcoming Grant Offer Letter 24-25 which will set out the expected drawdowns form
the Government funds during the new financial year. Projects which are likely to but
yet to be confirmed, be drawing down on funds include the three revenue projects
(Community Wealth Buildings; Working for Healthy Economy; and Ayrshire Skills
Investment Fund), the two i3 capital projects (Flexi Space and DPMC); and new for the
Programme, phases of the Great Harbour project; the combined AMIC and AEP; and
CoRE. 
Project level 
19. Project leads continue to meeting the challenges of developing and delivering projects.
For example the following activities and milestones have been achieved since reporting
the Board last:
20. Maritime Tourism – a Programme Business Case (PBC) has been submitted to the
Governments for their consideration and approval. If approved, then there is an
expectation that OBCs for the Cumbrae and Arran phases will soon follow (e.g. April
24 and June 24 respectively). In tandem a change request has been submitted to the
PMO that sets out changes to the project which are principally focused on the removal
of Ardrossan as a phase and reduction in Government funding. Details of the changes
are set out in the submitted PBC.
21. AMIC/AEP – via the PMO a paper setting out the changes to the AMIC and AEP project
have been submitted to the Government for their consideration. This includes details
of the colocation of the two projects at Moorfield and this forming the Ayrshire

Page 5

Innovation Park, west of Kilmarnock, and aligning their development and delivery.
Once support had been received an OBC will be submitted to the Government (target
date April 24), followed by three FBCs covering the combined infrastructure, AMIC and
AEP constructions.
22. Digital (Subsea Cable & Infrastructure) - following approval by the AEJC on 20
November 2023 to de-scoping of the Subsea Cable and Infill projects from the AGD
programme and approve Option 5b ‘Building Digital Capital as a new project, a formal
change request has been submitted to the PMO to finalise the change, and to support
the development details of the new project. Target date for finalising the details and
presenting to the Board and gain approval from the AEJC is March 24.This includes
details on the reallocation of the £14m budget and identification of the existing AGD
sites that will contribute to the Building Digital Capital across Ayrshire.  
23. Ayrshire Skills Investment Fund – following approval of the FBC in August 23 the
implementation of the project has progressed. However due to the timing of the FBC
approval the original financial profile has to be amended due to a reduction in expected
drawdown for this financial year 23/24 (e.g. from £850k to £163k). In response the
change proposes an increase in the last year (27/28 from £180k to £739k) to
compensate. The Government has accepted the change.  
24. In addition there are projects that are now ‘red’ in status from the perspective of scope,
budget, and overall position. 
Scope Issues - ‘Red’
status 
Budgetary Issues -
‘Red’ status
Overall - ‘Red’ Status
Digital ASTAC Spaceport 
Spaceport Digital 
Commercial Space 
Digital 
25. Project that still retain an  Overall ‘red’ status as follows:
26. Spaceport – extensive discussions between SAC, SE, SG and UKG have taken place
in light of the significant complex challenges for the delivery of the project. At present
further consideration is being given to how the project can be delivered in response to
cost pressures, limited funding/budget, legal barriers, and clarification on an
appropriate operational model.
27. Digital Programme – As highlighted above following approval by the AEJC to the
development of a new project ‘Building Digital Capital’ details are being developed. It
is expected this outcome of this approach will de-risk the project. 
28. Other highlights include:
• ASTAC – a partnership between SAC, Ayrshire College and GPA has been
established which is working towards developing a deliverable project in
response to budgetary constraints. Target date for an OBC to be submitted is

Page 6

April 24. 
• Commercial Space – Delays on the continued delivery of the project remains
due to the need to confirm funding arrangements. A deadline of the end of
March 24 has been identified where clarification on the future direction of the
project will be made. 
29. Projects in delivery are; Community Wealth Building, Working for Healthy Economy,
Ayrshire Skills Investment Fund, Commercial Space, i3 Flexi Space (Phase 1) and i3
DPMC (Phase 1).
COMMUNICATION UPDATE
30. In line with the AGD Communication Action Plan please find attached (in Appendix 2)
a copy of communication and engagement activity for all projects in the programme.
This includes Q2 Review of past activities and Q3 planned activities. 
IMPLICATIONS 
31. Eight implications have been considered in the preparation of this report. 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance/Legal Yes  Para 32
3. Human Resources  No 
4. Equality and Fairer Scotland Duty Yes  Para 33
5. Financial  Yes  Para 34-37
6. Risk  Yes  Para 38-39
7. Community Wealth Building   No 
8. Net Zero   No 
LEGAL IMPLICAITONS 
32. The legal implications arising from this report are covered through the Agreement
between Ayrshire’s councils and the Governance Document which was revised and
approved at the Joint Committee meeting on 8 December 2022. 
EQUALITY IMPACT ASSESSMENT 
33. There is no equalities impact relating to this report. Inclusion is a key driver for the
AGD. Project Leads will be required to complete an Equality Impact Assessment for
their project and append to the associated business case. Project Leads have received
Equality Impact Assessment training organised by the Scottish Government. Project
Leads are being encouraged by the PMO to link up as soon as possible with their
Equalities Officer within their authority who will be able to assist with this matter.

Page 7

FINANCIAL IMPLICATIONS 
34. The financial implications arising from this report are covered through the Financial
Plan approved at the Joint Committee meeting on 26 June 2023. The overall
cumulative total of Grant claimed for the Deal to date is £13.157m. 
35. The tenth claim since Deal signing (in the financial year 23/24 Qtr3) has been made to
the Scottish Government for c.£1.132m which is made up of expenditure associated
with the Community Wealth Building, Working for a Healthy Economy, Ayrshire Skills
Investment Fund, Commercial Space and i3 Flexible Space. All claims made to date
have been processed by Government and payment received. The financial position
statement for December 2023 within the progress includes the Q3 claim. (Appendix 1). 
36. At the time of preparing this paper the forecast drawdown reported to Scottish
Government for P9 2023/24 amounts to £4.685m, an anticipated decrease of £21.125m
for the year compared to a budget of £25.810 million. Projects are, however,
demonstrating commitment and incurring costs developing projects, with evidence of
£11.103m having been spent by councils to date ahead of project business cases being
approved. Once approval of the relevant business cases has been received from
government and the Joint Committee, the relevant costs will be claimed back from
government. 
37. Please note all capital and revenue project costs are being monitored and discussed
with regional partners, UK and Scottish governments. 
RISK IMPLICATIONS 
38. Strategic and operational risk registers continue to be developed, reviewed and
updated for the AGD Programme. This is being undertaken by the PMO with the
support of EAC audit. The Programme Risk Register has been updated in accordance
with the commitment to be reviewed every quarter as approved by the AEJC on 26
June 2023. Details of the latest update is considered elsewhere on the agenda. 
39. In addition the risk registers for each project which are updated on a monthly basis
and reflected in the attached summary update (Please see Appendix 1). 
APPENDICES 
Appendix 1: Ayrshire Growth Deal Update of Programme and Projects
Appendix 2: Annual Performance Report (Outline) Ayrshire Growth Deal – Q3 Oct-Dec
23) 
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and Ayrshire’s
Councils on 8 March 2019

Page 8

Deal Document, signed by both the UK and Scottish Governments and Ayrshire’s
Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal –Strategic Manager 
graham.saunders@east-ayrshire.gov.uk 
Implementation Officer: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager 
graham.saunders@east-ayrshire.gov.uk

Page 9

Appendix 1 
Ayrshire Growth Deal Update of Programme and Projects

Page 10

AYRSHIRE GROWTH DEAL
Monthly Report - 31 January 2024

Page 11

Programme Updates - Guidance (Milestones) 
RAG Status Programme Milestone Timeline
Status Overall Action Required 
Red
Delay to delivery timeline of key
milestone having a negative impact on
programme 
One or more milestones are RED
Immediate action required by senior
management and relevant Boards as
appropriate to address issues 
Amber
Milestone slipping against planned
date but not expected to impact
delivery of the programme
No milestones are highlighted RED but at
least one is AMBER
Management action is in place by PMO and/or
senior management to address issues 
Green On track to deliver milestone on time
or early  All milestones are GREEN  No management action required 
Complete  Milestone delivered  n /a  No management action required
Status against milestone timeline set out in Implementation Plan
Milestones – current financial year and next financial year
Programme Updates - Guidance (Risks)
This table illustrates the conversion of AGD RAG Status to Scottish Government RAG Status 
Source GREEN AMBER RED N/A
Ayrshire Growth Deal
RAG Guidance Note
with an AGD risk register score of
between 0-3
with an AGD risk register score of between
4-9
with an AGD risk register score of between 10-
14
with an AGD risk register score of
between 15-25 N/A
Source GREEN AMBER/GREEN AMBER/RED RED N/A 
Scottish Government
Guidance
Successful delivery
appears highly likely with
regard to time, cost and
quality and there are no
major outstanding issues
that at this stage appear to
significantly threaten
progress 
Successful delivery appears
probable however attention will
be needed in certain areas to
ensure risks do not develop into
major issues that will threaten
delivery 
Successful delivery appears
possible, but issues already exist
that require serious
attention. These appear resolvable
at this stage, but further action is
required
Successful delivery is in
serious doubt with
major risks or issues
apparent in a number of
key areas. Urgent
action is needed to
ensure these are
addressed 
Not listed
on
previous
Quarter

Page 12

Programme Dashboard – 31 January 2024 Financial Summary 
Programme Milestones Programme Top Risks 
Overall Status
Last Period 
Overall Status
This Period   
Total AGD
Grant £'000 
AGD Grant Drawdown to Date
£'000  %age of total AGD Grant  2023/24 AGD Grant
Allocation £'000 
2023/24 Grant
Drawdown £'000
251,500 13,157 5.23% 25,810 2,573 
Programme & Upcoming Programme Milestones Target Date RAG 
Grant Offer Letter for 2023/24 received and agreed  30-Jun-23  Complete
2023 Annual Review of Deal documentation approved
(Implementation Plan, Financial Plan, Governance Document,
Communications Protocol) 
30-Jun-23  Complete 
Review overarching Monitoring & Evaluation Framework  30-Jul-23  Red
Update Benefits Realisation Plan and progress on performance
(every March)  31-Mar-24  Green 
Review and update Change Management Process - draft and
approve Supplementary Advice Note 1  30-Jul-23  Red
Review and update Business Case process with a focus on Full
business Case requirements - draft and approve
Supplementary Advice Note 2 
31-Aug-23  Red 
Review and update Subsidy Control requirements for the AGD -
draft and approve Supplementary Advice Note 3  31-Aug-23  Red
Review and update AGD web site programme and project
details  30-Sep-23  Red 
Key project interdependencies articulated  31-Mar-24  Green 
Annual Conversation (2022/23)  31-Jan-24  Green
Annual Performance Report approved and published (2022/23) 28-Feb-24 Green 
Submission of statement of compliance with conditions of
grant (2023/24)  30-Apr-24  Green 
Risk Likelihod Impact AGD
Status
SG
Status
Mitigating Action - UPDATE TO ALIGN WITH IMPLEMENTATION PLAN 
Failure to achieve AGD programme objectives within agreed budget  4  4  
The Regional Economic Joint Committee, Regional Economic Partnership, AGD Steering Group in place to monitor progress and to address any weaknesses or issues that could impact on
overall delivery. PMO developing monitoring and evaluation processes to ensure overall objectives are captured and any project failing to achieve and contribute to these is flagged and
issues addressed as quickly as possible. This includes responding to increasing costs of general capital works within the context of the original funding made available by the Government in
2019. Leading to potential to review risks where evidence suggests insufficient funding to undertake and complete projects in line with expected outcomes.PMO are working with Partners in
undertaking a Checklist Review of the Programme in line with the AGD Governance. PMO undertake ongoing environmental analysis to ensure programme objectives are relevant/valid as
well as maximised where relevant and new benefits identified when materialising. Internal governance include regular reviews undertaken by PMO with input from SROs, Project Leads and
Chief Executives to ensure AGD programme objective are met. 
Failure to provide accurate projections for programme spend  4  4  
Issues will be escalated to CEOs, Regional Economic Partnership and Regional Economic Joint Committee as appropriate. PMO working with Partners in undertaking a programme midterm
Checkpoint Review in order to clarify accurate projections for project and programme spend and delivery.The Implementation Plan and Financial Plan have been updated to take account of
the compressed funding. Project Leads have sought to address delays in gaining approved FBCs, by undertaking reviews of projects to fit existing budgets, which are shared with Finance
Directors, the government and wider partners. Revised project mitigation measures seek to demonstrate how inflationary pressures will be managed. Business Case process monitored to
ensure streamlined pathway to approval enabling projects to achieve FBC as quickly as possible to reach project delivery and clarity on expected spend. PMO will regularly review, challenge
and agree financial profiling/phasing with Project Leads, SROs and Finance Directors and ensure drawdown projections align with delivery timescales. OBCs/FBCs include an optimism bias
factor as per Treasury Green Book and AGD Governance document. Inflationary factor addressed through project reviews e.g. re-scoping, phasing and reviewing benefits 
Failure to drawdown full AGD funding  4  4  16  16
PMO will regularly review, challenge and agree financial profiling/phasing with Project Leads, SROs and Finance Directors and ensure drawdown projections align with delivery timescales.
This includes PMO working with Project Leads, SRO’s and S95’s to ensure projects can be realised and help with change processes where necessary; and undertaking effective communication
with Governments to ensure projects can be realised. PMO working with Partners in undertaking a programme midterm Checkpoint Review in order to clarify accurate projections for project
and programme drawdown on AGD funding. Achieve business case approval in line with latest Deal Implementation Plan, and AGD Governance document and, Finance guidance. Annual
review of Financial Plan and Implementation Plan. The Scottish Government’s financial reporting requirements will be implemented. Pivot projects proactively where possible in line with
need and opportunity. Internal procedures, financial controls and processes in place to mitigate this risk 
Delays in development and approval of business cases  4  4  
Undertake focused engagement with SG and UKG in order to help ensure SBC, OBC and/or FBC comply with the Treasury Green Book and gain approval pin line with AGD governance. PMO
working closely with Project Leads and Policy Leads within UK and Scottish Governments to support business case development and approval to an agreed timeline. This includes exploring a
streamlined change process (pre-FBC) particularly where budget constraints are sole driver of change. In addition as part of a programme midterm Checkpoint Review, reschedule business
case timescale for development and delivery. Project Leads have received Green Book business case training. Project Leads’ toolkit in place. Other partners assisting in developing business
cases where capacity is low 
Lack of resources in PMO  3  3  9  9 A permanent PMO structure is in place with all posts about to be filled, once recruitment has been completed. The PMO is being supported by colleagues in each of the Councils in a number
of work streams. PMO is undertaking a review of capacity and skill sets in response to the changing requirements of the Office. 
Potential impact of international events upon cost of living crisis and economic
prosperity of Ayrshire  4  4  
Regular engagement with Project Leads to highlight any risks well in advance, so that the PMO can raise with government, Regional Economic Partnership and Regional Economic Joint
Committee as appropriate. PMO working with Partners in undertaking a programme midterm Checkpoint Review in response to the impact of costs pressures upon the delivery of the
Programme. Regular review vi monthly reports of outputs and timelines for business cases at every stage of development in the light of external events. Continued monitoring of external
environment and government relations. Regional Economic Strategy approved in early 2023 and be supported by an emerging action plan. Regional Economic Partnership will provide voice
for Ayrshire to press the case for government intervention investment. Incentives and other forms of assistance to complement the AGD and stimulate greater economic activity. Current
change management process to be reviewed with both governments and partners. Regional Skills Investment Plan developed, with a focus on its implementation via Ayrshire Skills Group.
Robust data analysis shared amongst key partners and stakeholders to reach common understanding of local economic conditions, leading to early identification of real threats and
opportunities - achieving consensus with partners and stakeholders on strategic objectives for inclusive and sustainable economic growth, with effective action planning and monitoring. PMO
co-ordinated evidence across Deals and submitted collective case via the Implementation Plan update to both governments setting out impact of increased costs or reduced the
scope/outputs and time delivery if costs not met. PMO developing a baseline approach to FBC which will be shared with both governments and partners.

Page 13

AGD PROJECTS - COMPLETE  Total Project Budget
£'000 
Government Grant
Funding £'000 
Government Grant
Claimed to date £'000  
Total Expenditure
17/18 to 20/21 £'000 
FINANCIAL POSITION STATEMENT
FINANCE YEAR 2023/24
QUARTER 3
HALO 9,000 7,000 7,000 10,524 MONTH Dec-23
9,000 7,000 7,000 10,524 
Government Grant 2023/24 £'000 
AGD PROJECTS - EXPECTED FBC/APPROVED FBC IN 2023/24 ~ GRANT OFFER
LETTER 
Total Project Budget
£'000 
Government Grant
Funding £'000
Government Grant
Claimed to 31 Mar 23
£'000  
Total Expenditure
17/18 to 22/23 £'000
Total Expenditure 23/24
YTD
£'000  
Grant Allocation
TBC 
Grant Claimed
Q1 
Grant Claimed
Q2 
Grant Claimed
Q3 
Grant Claimed
Q4 
Total Grant
Claimed YTD 
Remainig Grant Available
to Claim in year
Spaceport Infrastructure 23,000 23,000 0 2,856 351 2,855 0 0 0 0 0 2,855
Commercial Space - Prestwick - Industrial & Hangar 29,000 22,000 825 1,160 1,243 17,690 0 730 500 0 1,230 16,460
i3 Flexible Business Space 15,000 11,000 307 545 0 2,339 65 9 0 0 74 2,265
Community Renewable Energy Project (CoRE) 24,500 17,000 0 976 282 300 0 0 208 0 208 92
Working for a Healthy Economy 5,000 5,000 1,118 1,118 469 703 117 176 176 0 469 234
Ayrshire Skills Investment Fund 3,500 3,500 0 0 15 850 0 0 15 0 15 835
Community Wealth Building Fund 3,000 3,000 1,335 1,335 577 1,073 113 230 233 0 577 496 
103,000 84,500 3,584 7,989 2,936 25,810 295 1,145 1,132 0 2,573 23,238 
AGD PROJECTS - FUTURE  Total Project Budget
£'000 
Government Grant
Funding £'000
Government Grant
Claimed to 31 Mar 23
£'000  
Total Expenditure
17/18 to 22/23 £'000
Total Expenditure 23/24
YTD
£'000 
Aerospace & Space Technology Application Centre (ASTAC) 11,000 5,000 0 728 0
Prestwick Infrastructure - Roads 17,000 12,000 0 472 24
Ayrshire Engineering Park (Moorfield) 16,000 12,000 0 826 46
Ayrshire Manufacturing Investment Corridor (AMIC) 23,500 23,500 0 390 31
i3 Digital Processing Manufacturing Centre 6,000 5,000 0 245 30
Hunterston Strategic Development Area 18,000 18,000 0 192 11
International Marine Science & Environmental Centre (IMSE) 10,500 6,500 0 134 12
The Great Harbour, Irvine Harbourside & Ardeer 14,000 9,000 0 460 170
Marine Tourism 9,500 9,500 0 412 48
Digital Infrastructure & Subsea Cable 14,000 14,000 0 76 30 
139,500 114,500 0 3,934 401
AGD TOTAL 251,500 206,000 10,584  22,447 3,337

Page 14

Project Updates - Guidance 
Project Stages Stage Definition Project Stages Stage Definition 
Define - SBC  Establishing the strategic context for the spending proposal  Implement  Business case has been approved by Joint Committee, and is being implemented 
Define - OBC  Establishing the preferred option  Deliver  Project is in place and monitoring and evaluation is in framework to assess if it is achieving its objectives 
Define - FBC  OBC approved by government, securing delivery plans and finalising detailed costing  Legacy
Project has resulted in mainstreaming or improvements to business as usual (impact) that is generated beyond
the funded period
RAG Status Programme Milestone Timeline Status Project Scope Status Project Budget Status Overall Action Required 
Red  Delay to delivery timeline of key milestone having a
negative impact on project completion date 
Significant change in scope expected, with no change
request in process 
There are projected or actual adverse variances with
recovery plan to be established 
One or more milestone, scope or budget indicators are
RED 
Immediate action required by senior management and
relevant Boards as appropriate to address issues 
Amber
Key milestone missed or projected to miss against
planned date but not expected to negatively impact the
original project completion date
Likely to be minor changes in scope within agreed
business case OR scope is still developing OR significant
change request not yet approved 
There are projected or actual adverse variances,
however a recovery plan is in place 
No milestone, scope or budget indicators are RED but at
least one is AMBER 
Management action is in place by PMO and/or senior
management to address issues 
Green  On track to deliver milestone on time or early  Scope has been set and on plan with agreed business
case AND/OR formal change request approved  There are no actual or projected variances  All milestone, scope and budget indicators are GREEN  No management action required 
Complete  Milestone delivered  Project complete and all items in scope delivered  Financial transactions relating to project have been
settled 
If all the milestone, cost, scope and benefits realisation
indicators are complete  No management action required 
Future  N/A  N/A  Business Case more than one year away from
submission  n /a  No management action required 
Milestones – current financial year and next financial
year PMO = Programme Management Office SBC = Strategic Business Case OBC = Outline Business Case FBC = Full Business Case 
Project Updates - Guidance (Risks)
This table illustrates the conversion of AGD RAG Status to Scottish Government RAG Status 
Source GREEN AMBER RED N/A
Ayrshire Growth
Deal RAG
Guidance Note  with an AGD risk register score of between 0-3  with an AGD risk register score of between 4-9  with an AGD risk register score of between 10-14  with an AGD risk register score of between 15-25  N/A 
GREEN AMBER/GREEN AMBER/RED RED N/A 
Scottish
Government
Guidance
Successful delivery appears highly likely with
regard to time, cost and quality and there are no
major outstanding issues that at this stage appear
to significantly threaten progress
Successful delivery appears probable however
attention will be needed in certain areas to ensure
risks do not develop into major issues that will
threaten delivery
Successful delivery appears possible, but issues
already exist that require serious attention. These
appear resolvable at this stage, but further action is
required
Successful delivery is in serious doubt with major
risks or issues apparent in a number of key areas.
Urgent action is needed to ensure these are
addressed 
Not listed in previous Quarter

Page 15

Programme Summary – 31 January 2024 
Project Name  OBC Date  OBC RAG  FBC Date  FBC RAG
Project Scope
Status
Project Budget
Status
Project Overall
Status
Aerospace and Space Technology Application Centre 01/12/2023 Red 02/08/2024 Amber Amber Red Amber
Spaceport Infrastructure 30/10/2021 Complete 30/09/2023 Red Green Red Red
Prestwick Commercial Build 30/08/2021 Complete 08/09/2022 Complete Amber Red Red
Prestwick Roads 28/02/2024 RED 31/05/2024 RED Amber Amber Amber
Ayrshire Engineering Park (Moorfield) 30/09/2023 Red 10/06/2024 Green Amber Amber Amber
Ayrshire Manufacturing Investment Corridor 30/10/2023 Red 10/06/2024 Green Green Amber Amber
i3 Flexible Business Space 30/05/2021 Complete 30/09/2022 Complete Green Amber Amber
i3 Digital Processing Manufacturing Centre 31/05/2022 Complete 30/06/2022 Complete Green Amber Amber
HALO 31/05/2022 Complete 30/06/2022 Complete Complete Complete Complete
Community Renewable Energy 31/05/2022 Complete 30/04/2024 Amber Amber Amber Amber
Hunterston 30/06/2024 Green 28/02/2026 Green Amber Green Amber
International Marine Science & Environmental Centre 30/06/2024 Green 28/02/2026 Green Amber Amber Amber
Great Harbour 25/06/2021 Complete 31/03/2024 Green Amber Amber Green
Marine Tourism 31/12/2023 Amber 30/03/2026 Amber Amber Amber Amber
Digital Infrastructure & Subsea Cable tbc under rescope tbc under rescope Red Red Red
Ayrshire Skills Investment Fund 30/04/2023 Complete 07/08/2023 Complete Green Green Green
Working for Healthy Economy 19/02/2021 Complete 22/02/2021 Complete Green Green Green
Community Wealth Building 12/02/2021 Complete 22/02/2021 Complete Green Green Green

Page 16

Project Updates – Space and Aerospace Programme 31 January 2024 
Project Name Project Lead Senior Responsible Officer
Aerospace & Space Technology Application Centre George Hunter 
Louise Reid Spaceport Infrastructure Derek Yuille
Commercial Build Derek Yuille
Prestwick Infrastructure Roads (Phase 1) Kevin Braidwood

Page 17

Aerospace and Space Technology Application Centre Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Amber Project Budget Status Red
Monthly update - provide narrative Project Lead: George Hunter
Review of the ASTAC underway with a new concept being developed in partnership with Ayrshire College and GPA to help move the project forward (e.g. integration of partner ambitions of Ayrshire Colleges Aviation Institute with GPA's
Technology Hub). Ayrshire College developing a business case with SAC in order to inform options which were considered by Senior Management in December 23. Preferred option is integration of ASTAC, Tech Hub and SAI. Letter of support being
prepared by GPA to allow for continued collaboration with Ayrshire College and SAC.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 01/12/2023 Red AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC 02/08/2024 Amber AGD/O/2 - Construction jobs created tbc tbc
Phases Target date  AGD/O/9 - Business Space Created tbc tbc
Phases Target date  AGD/O/13 - Visitors tbc tbc
Phases Target date  AGD/O/14 - SME's Supported tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC Submitted to Government 01/12/2023 Red Completion of Phase 2 30/10/2029 Amber
Develop local partnership delivery model 01/12/2023 Red Final financial drawdown 31/03/2030 Amber
Complete final project design and procurement documentation 02/08/2024 Amber   
FBC approved by Joint Committee 02/08/2024 Amber   
Hand-over (Phase 1) to operational organisation 23/10/2026 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
A Viable and Sustainable Operational Funding (OPEX) model not achieved  5  4  20  
• Review existing models (UK- HIE/Perth College)
• Consultation Scottish Funding Council on academic funding support (OPEX)
• Consultation and developing model with Ayrshire College  31/03/2024 
Site for the ASTAC Facility not secured within GPA Estate offering airside
access/scale/offside access on acceptable terms  5  4  20  
• Secure early dialogue with Glasgow Prestwick Airport. Identify ASTAC spatial Needs.
Review options. New option presented to GPA/AC on 20.12.23. Slide Presentation of
conceptual Plan for ASTAC Campus. GPA expressed strong support from
Direcotr/Leadership Team. Positive response GPA albeit concerns until see HoT's 
31/03/2024 
ASTAC capital costs (CAPEX) exceed ASTAC approved budgets and other funding not
available  4  4  16  
• Complete early assessment of CAPEX costs and Prestwick build costs. Ensure
adequate OB provision. Make allowances for fees/legals inflation 
31/03/2024 
Securing agreements and approvals requires additional time and programme delayed  4  4  16  
• Develop Programe with Steering Group. Align SAC and AC resources. Secure early SAC
agreements and internal reporting. Stronger proposition if project links SAC/-AGD with
AC/ GPA. Tripartite agreements required. Board Approvals. Increased dependancies
and partner bespoke risks 
31/03/2024 
GPA lease costs not affordable within AC business case.  5  3  15  
• Review with AC/Develoment of OBC and confirmation of costs/affordability 
31/03/2024

Page 18

Spaceport Infrastructure Jan Project Overall Status
2024 Red
Project Update
Project Scope Status Green Project Budget Status Red
Monthly update - provide narrative Project Lead: Derek Yuille
Reported to Partnership Board on 4th December 2023 to highlight the risks and issues and ask partners to consider the feasibility of the spaceport project and whether it offers value for money under the terms of the Ayrshire Growth Deal. The
Board endorsed the issues raised. A report will now be submitted to Joint Committee on 19th February 2024.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/10/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 10 tbc
FBC 30/09/2023 Red AGD/O/2 - Construciton Jobs Created 135 tbc
Phases Target date  AGD/O/9 - Business Space Created 3200 sqm tbc
Phases Target date   Target tbc
Phases Target date   Target tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
RIBA Stage 3 30/04/2023 Red Airspace change agreed 31/03/2024 Red
Heads of Terms agreed to purchase land 20/06/2023 Red LSO/LSP/Range Licence requirements for first launch 30/11/2024 Red
FBC approved by Joint Committee 30/09/2023 Red Spaceport infrastructure complete 30/11/2024 Red
Construction Start 01/11/2023 Red First Commercial Launch 31/01/2025 Red
Safety Case 31/03/2024 Red Full project completed/final drawdown 31/03/2026 Red
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Imp
act
Likelihood Score AGD
Status
SG
Status Mitigation Action 
Risk that project does not comply with new subsidy control rules  5  5  25    The Council and SE will require to obtain legal advice from a subsidy control perspective on any proposed arrangements  29/03/2024 
Requirement from Scottish Government to redraft original OBC due to increases in costs
and delivery model  5  5  25    Discussion with delivery partners to identify ownership of work and who will cover the additional costs  31/12/2024 
Failure to agree operating arrangement for Spaceport  5  5  25  
Avison Young have proposed Spaceport leasing and operating proposals for SAC and the Spaceport Launch Service Operator
Glasgow Prestwick Airport, however an agreement has yet to be reached that complies with AGD capital funding
requirements, local authority operating legislation and that mitigates any financial and legal risks the Council may be exposed to
where the Council has ongoing responsibility for the Spaceport asset.  31/12/2024 
Failure to obtain FBC approval  5  5  25  
A Full Business Case for the Spaceport requires the following to be in place: i) an agreement or Heads of Terms over the land
with confirmed budget source; ii) a costed deliverable infrastructure scheme with budget in place and iii) an agreement or
Heads of Terms on the operating arrangement for the asset between the proposed owner of the asset, and the Launch Service
Operator (LSO) Glasgow Prestwick Operator 
31/12/2024
The model SE use to acquire land for spaceport may require a lease arrangement with
SAC.  5  5  25  
The land acquisition/lease payments are not funded by AGD and the Council are not in
a position to enter any borrowing arrangements to fund this 31/12/2024
Failure to agree ownership of the new Spaceport infrastructure (eg. LVIF, apron, access
road, control point)  5  5  25  
Professional advice being sought by SAC on the legilities of SAC having any ownership
rights to the Spaceport. Advice previously confirmed operating arrangement scenarios.  31/12/2024
Project costs cannot be met by the existing AGD project budget
5 5 25  
Digital re-scoping exercise and proposal that build shortfall is supported by digital
funds. SE will acquire the land. 31/10/2024

Page 19

Prestwick Commercial Build Jan Project Overall Status
2024 Red
Project Update
Project Scope Status Amber Project Budget Status Red
Monthly update - provide narrative Project Lead: Derek Yuille
Mangata continue to work towards Series B completion and have now noted a Lead Investor. This longstop date for this work to conclude has been moved to end March 2024. This has an impact on the programme with main construction delayed and now programmed to start Q1
24/25 and complete Q2 2026. The costs have increased to £110m and SE/Mangata are looking at value engineering to bring down to £90m. The significant deviation in costs and programme from that approved at FBC has triggerred the AGD change control process. Private setor
financial contribution is required to allow the progression of this project.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/08/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 570 tbc
FBC 08/09/2022 Complete AGD/O/2 - Construciton Jobs Created 150 tbc 
AGD/O/9 - Business Space Created 13900 sqm tbc
AGD/O/16 - Leverage (incl. LA, HE/FE, Private Sector and any other levereage) £55,000,000 tbc 
Target tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Planning permission 31/05/2023 Complete   
Handover 31/12/2025 RED   
Final financial drawdown 31/03/2030 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Increase in costs  4  5  20   
SE have confirmed that this eventuality was contracted for in their Deal documents,
and any difference remains the liability of Mangata. SE continue to work with Mangata,
Morgan Sindall, G&T and their sub-contractors on both the potential to reduce costs,
and to mitigate risk by ensuring appropriate financial guarantees are in place. 
30/12/2024 
Failure of Mangata to resource additional funding  4  4  16  
• Closing Series B continues to prove challenging for Mangata, with timing now
forecast for early December (previously end September). However, Mangata have now
signed a letter of intent with a lead investor.
• Mangata are funding the business through Convertible Loan Notes until Series B
close. This requires them to continue to raise cash as current funding forecast lasts
until October and includes the R&D Grant payment. Mangata's forecasts show that
they then anticipate some funding in October 2023, before conclusion of Series B,
expected December. 
30/12/2024
SAC are unable to recoup any costs expended if project does not proceed 
4 4  16  16  16
SAC seeking clarification from SE/PMO and SG on SAC's ability to recoup costs
should project not proceed. 
30/03/2024
Failure of Cabinet/AEPB/AEJC to approve changes to costs, programme 
5 2  10    10
SAC to work with SE to draft report for submission to Cabinet in Jan 24 and
AEPB/AEJC in Feb 24 to endorse/approve changes. 
30/03/2024
Failure to procure and install the specialised manufacturing equipment on time. 
3 3  9    9
Equipment orders are dependent on the successful conclusion of MGTA funding.
Once this has been established, the overall programme to procure and install
can be secured and aligned to the build programme.  31/12/2024

Page 20

Prestwick Roads Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kevin Braidwood
Continue to work closely with the LDP2 project delivery team to obtain TS approval of the traffic modelling baseline data, during these discussions it has become clear the AGD trip generation included in the LDP2 is no longer accurate and needs to reviewed. PMO
currently working to provide as accurate as possible AGD proposals to allow accurate trip generations to be established, inital information received was not detailed or loaction specific enough, further information requested and will be chased up at next monthly
meeting. Additional work is ongoing regarding Surface Water Management on the northern side of Glasgow Prestwick Airport, meeting has been arranged for wc 29/01/2024 to discuss both of these high
risk issues and agree a way forward.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 28/02/2024 RED AGD/O/2 - Construciton Jobs Created 40 tbc
FBC 31/05/2024 RED AGD/O/7 - new roadway created 2 km tbc
Phases Target date  AGD/O/7 - roadway upgraded 1 km tbc
Phases Target date  AGD/O/7 - new roundabouts 1 tbc
Phases Target date  AGD/O/11 - upgraded roundabouts 3 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Roads Enabling STAG Appraisal - Release of funds from Transport Scotland 31/08/2023 Red Procurement of contractor and commencement of works – Monkton 30/06/2024 Red
Planning and regulatory consent achieved – Spaceport (St Quivox) 30/09/2023 Red Completion of works – Spaceport (St Quivox) 31/12/2024 Red
Land assembly, site preparation, contract documentation – Spaceport (St Quivox) 31/12/2023 Red Completion of works – Enabling transport works 01/03/2025 Red
Planning and regulatory consent achieved – Monkton 31/12/2023 Red Planning and regulatory consent achieved - Gannet Link tbc Red
Roads Enabling OBC - TS & Council Approval 28/02/2024 Red Land assembly, site preparation, contract documentation - Gannet Link tbc Red
Land assembly, site preparation, contract documentation – Monkton 31/03/2024 Red Procurement of contractor and commencement of works – Gannet Link tbc Red
Procurement of contractor and commencement of works – Spaceport (St Quivox) 30/04/2024 Red Completion of works - Gannet Link tbc Red
Roads Enabling FBC - TS & Council Approval 01/03/2024 Red Final financial drawdown 31/12/2027 Red
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Delays in release of enabling infrastructure funding from Scottish Government via
Transport Scotland  4  4  16    Commissioning of Enabling Roads STAG and OBC
• Effective scoping and ongoing liaison with Transport Scotland 
STAG Mar 2024
OBC Jul 2024
Roads enabling intervetion - fails to meet demands from current occupiers in
relation to future productivity.
Fails to support the development of available land.
Doesn't support the volumes of future traffic.
Community resistance. 
4 5  20  
STAG process being followed to ensure a suitable solution if established
• Final roads enabling solution(s) will be designed in detail by competant designer
• On-going discussions with the current operators at Prestwick in respect of future
plans
• On-going community consultation 
30/09/2024 
Interdependencies with Spaceport project
Risk that the construction of new access to serve spaceport does not meet
agreements with funders and Heads of Terms requirements 
4 2  8    8
Continual review of interdependencies with other AGD projects, particularly Spaceport
(including site location and exclusion zone requirements).
• Engagement with stakeholders and funders
• Consider in the design of the new road the serving of the spaceport and future
development opportunities. 
30/09/2024 
Requirement for the traffic data within the AGD STAG and LDP2 to align and
provide the same mitigation solution to Transport Scotlan to gain approval on
both 
4 2  8    8 
Continued liaison between the ARA AGD and ARA LDP team
• Agreement on traffic levels and any updates needed to ensure synergy and alignment  31/03/2023 
Planning Approval - Dealys in planning due to capacity constraints, Objections to
proposed route, Planning programme and interrelation between overall Spaceport
development and enabling roads intrastructure 
3 2  6    6 
Programme recognised by Planning Department as a major project and given priority
• Prestwick Campus Masterplan incorporated in development of LDP2 via main issues
report and subsequent consultation with residents and other parties
• On-going community consultation
• Planning Strategy to be developed to ensure planning applications are
interconnected 
31/12/2024 
Land assembly delays - Monkton & Spaceport  3  2  6    6  Early commencement of Land Owner negotiations  31/12/2024

Page 21

Project Updates – Economic Infrastructure Programme 31 January 2024 
Project Name Project Lead Senior Responsible Officer
Ayrshire Engineering Park (Moorfield) Fiona Paterson David McDowall Ayrshire Manufacturing Investment Corridor (AMIC) Gillian Morton
i3 Flexible Business Space Marnie Ritchie Neale McIlvanney i3 Digital Processing Manufacturing Centre (DPMC) Marnie Ritchie
HALO Gary Deans David McDowall

Page 22

Ayrshire Engineering Park (Moorfield) Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Fiona Paterson
1. Change management report was submitted for review to PMO in January 2024 Project team re now finalising amends following feedback from PMO.
2. The project team meeting took place on the 12th January will all external consultats in attendance.
3. The Project Governance structure has now been approved by senior management. Sub group meetings will commence over the coming weeks.
4. Meetings being held with education partners regarding support for schools to deliver more courses in relation to Food, Drink and Agriculture.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/09/2023 Red AGD/O/1 - New Jobs Created (Direct and Indirect) 203 tbc
FBC 10/06/2024 Green AGD/O/2 - Construciton Jobs Created 88 tbc
Phases Target date  AGD/O/9 - Business Space Created 7250 sqm tbc
Phases Target date  AGD/O/10 - Reduced vacant & derelict land 18.3 ha tbc
Phases Target date  AGD/OT/7 - Additional Investment (incl Foreign Direct Investment) tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone status  Milestone Due date Milestone status
OBC Approved by Government 30/09/2023 Amber FBC approved by Joint Committee 10/06/2024 Green
Tender for Building Services & Civil and Structural Engineers Services 02/05/2023 Green Commencement of infrastructure works 24/06/2024 Green
Design period inl community consultation & Environmen Impact Analysis commences 10/07/2023 Green Construction of terraced units and 500sqm unit 21/04/2025 Green
Planning permission secured 30/03/2024 Green Initial business premises operational 19/01/2026 Green
FBC endorsed by Government 20/05/2024 Green First tenants move in 01/02/2026 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Failure to Contribute to AGD programme objectives 
3 3  9    9
• Project will be managed by EAC in line with PRINCE 2 principles – any issues will be
monitored, and remedial action agreed to ensure delivery remains in line with the OBC
projections.
• AGD Steering Group and other governance arrangements are in place to monitor
progress and to address any weaknesses or issues that could impact on overall delivery
and project lead will be required to provide regular project updates 
31/3/2027
Failure to provide accurate projections for project spend 
3 3  9    9
• Ensure sufficient optimism bias built into costing of the project
• Inflationary factor included in cost estimations
• Project will be managed by project team in line with PRINCE 2 principles – any issues
will be monitored, and remedial action agreed to ensure delivery remains in line with
the BC projections
• Issues to be escalated PMO in first instance to agree remedial actions as appropriate
• Challenge panel led by PMO exists to review & scrutinise spend profiles 
31/3/2027
Delays in approval of business case 
3 3  9  9
• Project lead will work closely with PMO and policy leads within UKG and SG to
support business case development and approval to an agreed timeline 
30/12/2025
Failure to deliver community benefits from the project 
3 2  6  6
• Procurement colleagues will support the tender process to ensure that community
benefits are a key aspect of the ITT and are in line with agreed AGD procurement
principles  31/03/2027
Failure to attract commercial interest in this project 
3 2  6    6
• Market campaigns for AEP will target potential investors and tenants.
• Wider Ayrshire Economic Growth Strategy will be put in place to ensure wider growth
ambitions for Ayrshire are agreed and be articulated to stakeholders and investors
• Continue engagement with businesses to ensure unit sizes/specifications are fit for
purpose and meet demand requirements  31/3/2028
Negative Publicity 
3 2  6    6
• A communications protocol has been agreed with both governments and will support
shared communications designed to build stakeholder confidence
• All project specific publicity will be dealt with in a coordinated fashion, sensitivity and
empathy to business climates at the time of publications will be carefully monitored  31/3/2027

Page 23

Ayrshire Manufacturing Investment Corridor Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Gillian Morton
1. Change management report was submitted for review to PMO in January 2024 Project team re now finalising amends following feedback from PMO.
2. The project team meeting took place on the 12th January will all external consultats in attendance.
3. The Project Governance structure has now been approved by senior management. Sub group meetings will commence over the coming weeks.
4. Meetings being held with education partners regarding support for schools to deliver more courses in relation to Food, Drink and Agriculture.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/10/2023 Red AGD/O/1 - New Jobs Created (Direct and Indirect) 189 tbc
FBC 10/06/2024 Green AGD/O/2 - Construciton Jobs Created 130 tbc
Phases Target date  AGD/O/9 - Business Space Created 5814 sqm tbc
Phases Target date   tbc tbc
Phases Target date   tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone status  Milestone Due date Milestone status
OBC Approved by Government 30/10/2023 Amber Phase 1 - works commence (Food & Drink Centre) 07/04/2025 Green
Planning application secured 28/02/2024 Green Phase 2 - works commence (speculative units) 02/02/2026 Green
FBC endorsed by Government 20/05/2024 Green Phase 1 - Initial premises operational 01/02/2026 Green
FBC approved by Joint Committee 10/06/2024 Green Phase 2 - Initial premises operational 09/11/2026 Green
Award & Commence Infrastructure - Procurement Contract 24/06/2024 Green First tenant secured 01/02/2026 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Construction costs in particular costs of materials significantly increase 
4 4  16  
• The project team will work closely with colleagues in F+PM and the design
consultants to develop a cost effective but efficient building design. An affordability cap
has been set as part of the appointment of the design team to ensure we work within
the parameters of the budget. 
24/06/2024
Failure to Contribute to AGD programme objectives 
3 3  9    9
• Project will be managed by EAC in line with PRINCE 2 principles – any issues will be
monitored, and remedial action agreed to ensure delivery remains in line with the OBC
projections.
• AGD Steering Group and other governance arrangements are in place to monitor
progress and to address any weaknesses or issues that could impact on overall delivery
and project lead will be required to provide regular project updates 
31/03/2027
Failure to provide accurate projections for project spend 
3 3  9    9
• Ensure sufficient optimism bias built into costing of the project
• Inflationary factor included in cost estimations
• Project will be managed by project team in line with PRINCE 2 principles – any issues
will be monitored, and remedial action agreed to ensure delivery remains in line with
the BC projections
• Issues to be escalated PMO in first instance to agree remedial actions as appropriate
• Challenge panel led by PMO exists to review & scrutinise spend profiles 
31/03/2027
Delays in approval of business case 
3 3  9    9
• Project lead will work closely with PMO and policy leads within UKG and SG to
support business case development and approval to an agreed timeline 
30/03/2025
Economic instability as a result of Covid-19 
3 3  9    9
• The Ayrshire Economic Recovery Plan will focus on a greener and a fairer economy
and this project is key to these two issues
• The project team and wider partnership are focused on ensuring that the value of this
project to those issues is maximised
• The project team will also monitor any potential delays to the project in terms of
construction timelines and will seek to address these as quickly as possible and with
contractors 
31/03/2028
Health Pandemic/UK threat to business activity 
3 3  9    9
• AMIC building will be a strategic centre for businesses in times of crisis. The centre
will provide support and direction for food and drinks businesses as well as providing
additional manufacturing space to allow supply to meet demand especially within the
Dairy Sector. 
31/03/2027

Page 24

i3 Flexible Business Space Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Marnie Ritchie 
Phase 1 - Contractor Muir Group now on site since 30 October. Photo call to mark start of works took place on 9 November. Contractor has made contact with NAC Community Benefits Officer to action this element. Contractor advising estimated completion date as 12 August
2024.
Phase 2 & 3 - Developing specifications for Phase 2 with internal team of architects and surveyors. Potential additional funding for commercial space at i3 may be available through Levelling Up Funding. Details being confirmed.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/05/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 133 tbc
FBC 30/09/2022 Complete AGD/O/2 - Construction jobs created 83 tbc
Phase 2 FBC 25/02/2025 Green AGD/O/9 - Business Space Created 6000 sqm tbc
Phase 3 FBC 28/02/2027 Green AGD/O/10 - Reduced vacant and derelict land 20 ha tbc 
AGD/O/14 - Start-ups 5 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover 31/10/2024 Green Completion of Phase 2 30/10/2029 Green
Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/10/2025 Green Final financial drawdown 31/03/2030 Green
Phase 2 FBC approved by Joint Committee 25/02/2025 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2025 Green   
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover tbc Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Cost overruns  4  5  20  
• Develop and validate Project Brief and Specification
• Benchmark costs
• Ensure early infrastructure cost tested/ informed SI
• Provide Green Book compliant optimism bias allowances
• Provide for contingency
• Undertake value engineering
• Pursue additional funding sources 
Project delays and economic impact of Covid-19 and recovery  4  4  16  
• Early analysis has identified that the need for this project is unlikely to be diminished and in fact
may be even greater
• Project team will continue to focus on economic analysis and the development of recovery plans will
incorporate this as a key project for implementation as part of that wider plan
• Work with contractors to devise solutions designed to minimise impact of social distancing – such as
different work patterns 
Failure to deliver anticipated outputs and outcomes 3 5 15  
• Ensure BC addresses sensitivity of outcomes
• Clear Evaluation & Monitoring Framework 
Demand – no interest from occupiers  3  5  15  
• Flexible design to maximise potential interest from occupiers
• Marketing and promotion of floorspace
• Continue to establish strategic relationship with national sector (including links with NMIS) 
Utilities cause delays e.g. surface water drainage connections, sub-station
requirements.  3  4  12    12
• Utility companies to be approached and applications to be submitted at an early stage. Despite this
mitigation, issues have arisen on utilities for Phase 1, hence change to status to reflect this. Contractor
working with Scottish Water and current issue resolved. However changed to amber /red status for ongoing
project and future phases.

Page 25

i3 Digital Processing Manufacturing Centre Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Marnie Ritchie 
Phase 1 - University of Strathclyde are procuring the equipment, fit out, recruiting for resources and securing membership of companies which is taking longer than anticipated. Official launch planned for February 2024.
Phase 2 - Centre: Analysis with partners to be completed on Phase 1 to provide scoping parameters for phase 2.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 95 tbc
FBC 30/06/2022 Complete AGD/O/2 - Construction Jobs Created 84 tbc
Phase 2 OBC 31/12/2024 Green AGD/O/9 - Business Space Created 1749 sqm tbc
Phase 2 FBC 31/12/2025 Green AGD/O/10 - Reduced vacant & derelict land 20 Ha tbc 
AGD/O/16 - Leverage: (incl. LA, HE/FE, Private Sector and any other leverage) £19,810,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/07/2027 Green Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 30/04/2028 Green
OBC Phase 2 approved by Government 31/12/2024 Green   
FBC Phase 2 approved by Joint Committee 31/12/2025 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/01/2026 Green   
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover 31/07/2027 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Capital costs are in excess of the budget.  4  4  16  
• Value engineering of works specifications
• Proactive review of funding opportunities to make the shortfall 
Failure to deliver anticipated outputs and outcomes  4  3  12    12
• Ensure BC addresses sensitivity of outcomes
• Clear Evaluation & Monitoring Framework
• Phase 0 and Phase 1 will establish the concept, build operational capacity and
industry interest.
• Conditions of grant will include expected outputs to measure the project’s success.
• Regular monitoring of centre’s performance through Supervisory Board 
Delays to procurement processes  3  4  12    12
• Seek early agreement on appropriate procurement routes
• Include anticipated tender packages within the Council’s Procurement Wave Plan
• Notify potential bidders of procurement opportunities at an early stage 
Ongoing Partnership commitment  4  3  12  12
• Memorandum of Understanding signed August 2021
• Collaboration Agreement signed March 2022
• Development and co-ordination of appropriate governance procedures
• Commitment to lease for Phase 1 location 
Failure to deliver community benefits  4  3  12   12 • Incorporate appropriate community benefits into contract terms and resource
appropriately.

Page 26

HALO June Project Overall Status
2023 Complete
Project Update
Project Scope Status Complete Project Budget Status Complete
Monthly update - provide narrative      Project Lead: Gary Deans   
Since last reporting HALO have continued to hold a variety of events and support a growing number of diverse business at its #RockMe trading floor. A key event was the successful Space and Trade Conference with speakers from Kate Rubins Astronaut
NASA; / Jack Hillmeyer US Consul General; and Dr David Alexander OBE Rice Space Institute Houston. Topics included the role of young people, the realtionship between HALO and USA, and future thoughts in education.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 232 182
FBC 30/06/2022 Complete AGD/O/2 - Construciton Jobs Created 256 265
Phases Target date  AGD/O/3 - safeguarded jobs 300 375
Phases Target date  AGD/O/15 - Private sector investment £15,199,000 tbc
Phases Target date  AGD/OT/7 - Public and private sector investment - Phase 2 £46,000,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status                              
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Failure in financial management and reporting 
2 2  4    4
• The Board of HALO Kilmarnock Ltd receives monthly reports on all financial aspects
of the project and address any significant variances from the approved full business
case Robust financial systems and controls are in place and the Board of HALO
Kilmarnock Ltd retains oversight of these.
Copy of monthly report forwarded to PMO for BRP purposes. 
Reputational 
2 2  4    4
• Specialist advisers have been appointed to deal with media enquiries and to
communicate on any issue which is deemed to potentially impact on the reputation of
the project and the Board of HALO Kilmarnock Ltd

Page 27

Project Updates – Energy, Circular Economy & Environment Programme 31 January 2024 
Project Name Project Lead Senior Responsible Officer
Community Renewable Energy (CoRE) Diarmid Turnbull David McDowall
Hunterston Strategic Development Area Neale McIlvanney
Neale McIlvanney International Marine Science & Environment Centre
(IMSE) Neale McIlvanney

Page 28

Community Renewable Energy Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Diarmid Turnbull
1. Working Group meetings have been hosted for the following project work streams: sustainable transport; active travel; skills, training & education and renewable energy. The groups have helped to inform development of demonstrator projects and identified priority areas for CoRE to address moving forward, through identifying key barriers and opportunities within each sector to transitioning to net-zero. 2. A CPD learning session
was delivered to the low-carbon housing working group, two presentations were delivered on: lessons learned from delivery of a deep retrofit project in Glasgow and the benefits of domestic internal air quality monitors. Both presentations have supported development of CoRE's first housing demonstrator project and provided wider learning benefits to group members.
3. The change management document is being prepared and will subsequently be submitted for approval.
4. The second CoRE Partnership Board meeting is scheduled to be held on 23/01/24.
Project Targets
Business Cases Target date Status  Benefits
Realisation (top
5 deliverables)
Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs
Created (Direct and
Indirect)
108 tbc
FBC Demonstrator Projects 30/04/2024 Amber AGD/O/2 -
Construciton Jobs
Created
88 tbc
FBC Centreof of Excellence 30/05/2024 Green AGD/O/9 -
Development Space
Unlocked
3008 sqm tbc
Phases Target date   tbc tbc
Phases Target date   tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone status  Milestone Due date Milestone status
Formation of Management Board 30/05/2023 Green Commencement of
Programme of
Demonstrator
Projects
31/05/2024 AMBER
Engagement with Education and Skills Partners 30/08/2023 Green   
Review of CoRE Innovation Building 20/12/2023 Green   
FBC for Demonstrator projects 20/12/2023 Amber   
FBC for CoRE Innovation Centre 30/05/2024 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Construction costs, in particular cost of materials, significantly increases due to the pandemic.  4  5  20  
• The project team will work closely with colleagues in F+PM and the design consultants to develop a cost effective but efficient building design.
• An affordability cap has been set as part of the appointment of the Design Team to ensure we work within the parameters of the budget. 
31/03/2030 
Health Pandemic/UK threat to business security- the risk that a global health pandemic could shut down
the country causing significant danger to life and the economic stability of the country.  3  5  15  
• The Centre of Excellence will be a national centre for businesses within the energy and technology industry in times of crisis.
• The Centre will provide support and direction for these businesses as well as providing lab space to allow for any technology testing (such as creating a new type of
ventilator) to meet any demand.  31/03/2030 
Failure to attract investors and new businesses to locate within the Centre of Excellence  3  5  15  
• EAC will work collaboratively with specialist partners, including Scottish Enterprise and Energy Technology Partnership, from an early stage to identify and work with
potential investors
• The research carried out within the facility will be tailored towards particular technologies for which there is market interest in.
• Wider Ayrshire Economic Growth Strategy will be put in place to ensure wider growth ambitions for Ayrshire are agreed and be articulated to stakeholders and
investors.
• At a local level, the Council will work with existing businesses and start-ups to explore how they can benefit from the project, a potential arm of which could be to
locate into the research facility/incubator space  31/03/2028 
Delays in approval of business case (due to COVID-19, feedback from both Governments may be delayed
as their efforts will be focussed on critical services). Potential delays to project delivery may impact on
milestone achievements resulting in potential reduction in realisation of benefits of AGD.  3  5  15  
• Project Lead will work closely with PMO and policy leads within UKG and SG to support business case development and approval to an agreed timeline.
• Ensure business case statistics, feedback and information is up-to-date while waiting for further feedback. 
31/03/2027 
Design Stages of the Centre of Excellence and the site take longer than expected with the landowner
(also due to COVID-19, there could be further delay as staff working arrangements change).  3  4  12    12 
• Clear deadlines and targets have been clearly set out with the landowner and design team
• Ensure there is continuous collaborative working between the Council, design team and landowner.
• Ensure there is consistent communication between Project Team and landowner.  31/03/2025

Page 29

Hunterston Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Amber Project Budget Status Green
Monthly update - provide narrative Project Lead: Neale McIlvanney 
Recent demand analysis commissioned by Peel Ports Group and Scottish Enterprise has highlighted the importance of providing advanced manufacturing space for SME/incubator and supply chain users at Hunterston, in comparison to an innovation centre or large scale
speculative commercial space. 
Parters PPG & SE progressing with site analysis to develop phased options for the site.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/06/2024 Green AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC 28/02/2026 Green AGD/O/2 - construction jobs 1204 tbc
Phases Target date  AGD/O/3 - safeguarded jobs tbc tbc
Phases Target date  AGD/O/7 - New or upgraded roads/junctions/cycle pathways tbc tbc
Phases Target date  AGD/O/16 - Leverage Funding (incl LA, HE/FE, Private Sector and any other
leverage £200,000,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 30/06/2024 Amber Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 30/06/2029 Green
Completion of detailed design - RIBA Stage 3 31/03/2025 Green Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use)  31/03/2030 Green
Completion of technical design - RIBA Stage 4 31/12/2025 Green   
FBC approved by EJC 28/02/2026 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2026 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Unforeseen project complexities that require additional funding  4  4  16  
• Provide Green Book compliant optimism bias allowances
• Provide for contingency
• Project monitoring will track potential impacts and create ability to respond 
Ground conditions and historical legacy of site infrastructure create major burdens for
development  4  4  16   • Project team is working with Peel Port Group to understand the development
issues/infrastructure/utilities impacting onsite re-development 
Concept not supported by Partners and evidence of investment/market support not
forthcoming  4  4  16   
• Project team/Peel Port Group/SE developing and promoting an investment model to secure major
inward investment plus academic partners and industry
• Dialogue being progressed around role, responsibilities and funding commitments
• MOU signed between NAC/SE/Peel and wider strategic proposition around blue economy and
Hunterston supported by partners 
Concept and Operational Management revised /amended  3  4  12   12 • Project team/Peel Port Group developing a partnership/investment model to secure inward
investment/academic partners and industry 
Other Development/Investment/ Proposals impact on capacity/deliverability  4  3  12    12
• Project team/Peel Port Group seeking to collaborate with major partners to develop a clear investment
strategy/masterplan and investment led project proposition for AGD
• Peel Ports have gained planning approval of a site Framework to allow planning applications to be
considered

Page 30

International Marine Science & Environmental Centre Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Neale McIlvanney 
The initial MoU between NAC and University of Stirling (UoS) to develop a proposition for IMSE, is now advancing to Collaboration Agreement stage. Recent interest from the Field Studies Council (FSC) to invest in FSC Millport as part of IMSE, offers the potential
of a tripartite Collaboration Agreement between NAC, UoS and FSC with the benefit of an existing operational partner and available land assets. Collaboration Agreementis to enable progress of an OBC during 2024. In addition, partners will continue to explore
supporting Ardrossan regeneration as part of the IMSE programme.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/06/2024 Green AGD/O/1 - New Jobs Created (Direct and Indirect) 75 tbc
FBC 28/02/2026 Green AGD/O/2 - Construciton Jobs Created 58 tbc
Phases Target date  AGD/O/9 - Development Space Unlocked 1400 sqm tbc
Phases Target date  AGD/O/10 - Reduced and vacant derelict land 0.6 Ha tbc
Phases Target date  AGD/O/14 - Start-Ups 4 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 30/06/2024 Amber Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 30/06/2029 Green
Completion of detailed design - RIBA Stage 3 31/03/2025 Green Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 31/03/1930 Green
Completion of technical design - RIBA Stage 4 31/12/2025 Green   
FBC approved by EJC 28/02/2026 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2026 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Unforeseen project complexities that require additional funding  4  4  16  
• Provide for contingency
• Provide Green Book compliant optimism bias allowances
• Project monitoring will track potential impacts and create ability to respond 
Programme delay created within wider strategic delivery plan for Ardrossan  4  4  16   • Project team undertaking masterplanning process to identify all project requirements and spatial needs 
Concept not supported by Partners  4  4  16   
• Project team developing a partnership model with leading academic partners and industry
• Dialogue being progressed around role, responsibilities and funding commitments
• An MOU has been signed to develop the project definition with University of Stirling 
Strategic need and consolidation in sector advises Co-Location with wider projects 4 3 12  12 • Project team developing a partnership model with leading academic partners and industry 
Concept and Operational Management revised /amended  3  4  12   12 • Project team developing a partnership model with leading academic partners and industry 
Project cannot secure necessary consents  4  3  12   12 • Project team in early dialogue with key regulatory partners and stakeholders to address any
concerns

Page 31

Project Updates – Tourism Programme 31 January 2024 
Project Name Project Lead Senior Responsible Officer
Marine Tourism Kathleen Dow Neale McIlvanney Great Harbour Kasia Smith

Page 32

Great Harbour Jan Project Overall Status
2024 Green
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kasia Smith
The Great Harbour Masterplan was endorsed by NAC Cabinet in Dec 23 and will be submitted to the Planning Committee in early 2024. Detailed design (RIBA 3 gateway) for the Phase 1 - Coastal Hub has been completed and approved by the
internal Project Board. The Beach Pavilion building is the subject of a Market Feasibility Study to establish the viability of a re-development model with a community hub / restaurant. The procurement of consultants for the Phase 2 -Maritime Mile and for contractors for the
Phase 1 - Coastal Hub and for repairs to the Harbour Masters Office is now being progressed through the Council's Procurement Team. A Full Business Case relating to the phase 1 - Coastal Hub is in development. A Memorandum of Understanding between the Scottish Maritime
Museum, Crown Estate Scotland and the Council is being prepared to formalise the partnership in order to progress Phase 3 of the Great Harbour - the Maritime Heritage Hub.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 25/06/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 145 tbc
FBC 31/03/2024 Green AGD/O/2 - Construciton Jobs Created 99 tbc
Phase 1 FBC 31/03/2024 Green AGD/O/9 - Development Space Unlocked 9800 sqm tbc
Phase 2 FBC 31/10/2024 Green AGD/O/10 - Reduced and vacant derelict land 6Ha tbc
Phase 3FBC 31/03/2025 Green AGD/O/16 - Leverage Funding (incl LA, HE/FE, Private Sector and any other
leverage £4,000,000.00 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
FBC approved by Joint Committee 31/03/2024 Green Statutory Consents 30/06/2024 Green
Completion of detailed design - RIBA Stage 3 31/12/2024 Green Completion of technical design - RIBA Stage 4 30/05/2024 Green
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 15/05/2024 Green Completion of Construction Tender 31/08/2024 Green
Construction/Project completed and Handover (RIBA Stage 5-6: Construction & Handover) 31/10/2025 Green Internal sigh-off of FBC (NAC Cabinet) 30/09/2024 Green
Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/10/2026 Green FBC update to Joint Committee Phase 2 31/10/2024 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Increase in capital costs associated with changing scope or inappropriately quantified
cost provisions  5  3  15  
• Cost estimates based on current market
• Detailed technical studies to inform design and a fully detailed/itemised cost plan
• Project management established to monitor costs
• Optimism bias built into costings
• Future design team to include cost consultancy
• Additional internal and external funding bias 
Economic downturn as a result of Covid-19  3  3  9    9
• Robust project management in place to analyse impact on this project and wider sector and focus will be placed
on this project as an important element of the recovery agenda in Ayrshire
• Project team will work with contractors to understand the impact of social distancing on the labour force but
expected to be minimal given this is land based
• Continue economic analysis and development of recovery plans will be implemented
• Robust project scoping should continue to ensure the facility meets needs 
Project outcomes, including inclusive growth and reducing inequalities, fail to be
delivered  4  2  8    8
• AGD PMO is currently working with project leads to develop a consistent approach to ensure inclusive growth,
equalities and community wealth building outcomes are embedded in each AGD business case. This approach will
ensure explicit commitment to how the project will achieve inclusive growth and reduce inequality 
Technical approach to quays/pontoons and land connections cannot be agreed with key
stakeholders  4  2  8    8
• Development of Partnership/Operator Plan and detailed GANTT Programme
ensuring programme allows time for engagement and approvals
• PPiP route minimises risks and ensures full engagement with statutory bodies and community
• NAC in discussion with Harbour Authority
• Development Briefs drafted for Great Harbour

Page 33

Marine Tourism Jan Project Overall Status
2024 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kathleen Dow
The Marine Tourism Programme Business Case (PBC) was submitted to the PMO in December 2023 and feedback/comments were recieved in early January 2024. The PBC is now updated to refect feedback and submitted to PMO for forwarding onto
Govt. Responses from ScotGov will be refelcted, if required, in the Cumbrae Project OBC which is currently awaiting submission. Preparatory works for Cumbrae are well advanced and awaiting mobilisation. However, futher works can only progress upon
the Project's OBC approval. Timeframes are now critical to minimise the impact of delays, costs and risks to the marina project. There are complexities in developing marine infrastructure projects on the islands and a significant time period of 12-14
months is required to undertake the Environmental Impact Assessement and Marine Scotland etc permissions and consents in order to prepare the FBC for approval to construct in an autumn/winter window for a spring opening/project start. Delays
could impact the project for an additional year to c18 months, increasing costs and potentailly reducing outcomes and benefits. An outline programme of works for removal of the timber section of Millport Pier is agreed with the Harbours/Floods
Teams. This is aligned to the Cumbrae Marina development / programme and also awaits AGD OBC approval to be mobilised. The Arran Project Long list options appraisal has identified a reduced scale option that requires further development.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/12/2023 Amber AGD/O/1 - New Jobs Created (Direct and Indirect) 30 tbc
FBC 30/03/2026 Amber AGD/O/2 - Construciton Jobs Created 81 tbc
Cumbrae 30/03/2026 Amber AGD/O/9 - Development Space Unlocked 6 Ha tbc
Arran 28/02/2026 Amber AGD/O/10 - Reduced and vacant derelict land 0.1 Ha tbc
Ardrossan 28/02/2027 Red AGD/O/13 - increase in visitors(day and night) 100000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 31/12/2023 Amber Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 31/01/2027 Amber
Completion of detailed design - RIBA Stage 3 31/12/2024 Amber Operating project (RIBA Stage 7) and reporting 30/07/2027 Amber
Completion of technical design - RIBA Stage 4 and issue of tender 30/08/2025 Amber   
FBC approved by Joint Committee 30/03/2026 Amber   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/07/2026 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Changes to capital costs or inappropriately quantified cost provisions or increasing costs
that reduce scope of marina projects  5  5  25  
• Detailed technical studies in place to inform design
• Design team includes a cost consultancy and detailed assessment of contingency and
optimism bias is in place
• Regularly review viability of each project. Consider what is possible within budget.
31/3/26 -
Dependent Upon PBC
approval concluded at
OBC - finalised in detailed
at FBC
Development agreement and market economy investor principle for Ardrossan fails to
secure support  5  4  20  
• Project team taking legal advice in terms of subsidy control and agreements will be
based on commercial lease terms required for projects.
31/3/26 -
Dependent Upon OBC
approval concluded at
FBC 
Site/ground conditions are inadequate to provide cost certainty  5  3  15   • Full SI/GI and bathy surveys will be undertaken at an early stage in project
development
Dependent Upon
OBC approval
concluded at FBC
Agreement on technical approach to quays/pontoons and land connections cannot be
agreed with stakeholders  5  2  10   10
• Development of design / layouts / connections advanced with stakeholders /
partners.
Dependent Upon OBC
approval
concluded at FBC
Agreements including Development and Operating Agreements between commercial
partners and community interest company cannot be secured  5  2  10    10
• North Ayrshire Council seeking to advance formal Development and Operating
Agreement between partners/operators and agree a joint approach. Stakeholder
engagement maintained throughout programme.
31/3/26 -
Dependent Upon OBC
approval concluded at
FBC

Page 34

Project Updates – 31 January 2024 
Project Name Project Lead Senior Responsible Officer
Digital Infrastructure & Sub Sea Cable Simon Yeardley Louise Reid

Page 35

Digital Infrastructure & Subsea Cable Jan Project Overall Status
2024 Red
Project Update
Project Scope Status Red Project Budget Status Red
Monthly update - provide narrative Project Lead: Simon Yeardley
A change application has been submitted by the lead authority to the PMO following the approval from the AEJC for the rescope of the original subsea cable and infill project to comments. As part of this approval the three AGD Lead Authority
Senior Responsible Owners (SRO's) and Section 95 Officers will work with the regional PMO, in accordance with the AGD change management process, Deal Heads of Terms and Grant offer, to develop a new financial profile for 'Building Digital
Capital', for consideration and approval by the Joint Committee by the end of Financial Year 2023/24. SAC would propose recipient projects manage the funding as part of an increased financial envelope and complete financial re-profiling. SAC are
not proposing allocating any resource to managing the re-apportioned funds as there is no additional allocation to SAC capital funds.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC tbc under rescope AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC tbc under rescope AGD/O/2 - Construciton Jobs Created tbc tbc
Phases Target date  AGD/OT/1 - Job levels (new and maintained) tbc tbc
Phases Target date  AGD/OT/3 - Digital Usage patterns tbc tbc
Phases Target date  AGD/OT/7 - Additional investment (incl Foreign Direct Investment) tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Report on Re-scope exercise to Partnership Board 27/04/2023 Complete   
Joint Committee approve re-scope of project 22/05/2023 Complete   
AEJC approve re-scope of project 30/10/2023 Complete   
change management process applied 30/11/2023 RED   
Project Completion ( Descoped) 30/09/2026 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Cost overruns 
2 2  4    4
• Rescoping exercise has concluded and identified a valid option that can be delivered
by reprioritisation of current budget to in train AGD projects
• Robust contract management in place
• Appropriate procurement procedures followed and optimism bias built into business
case 
30/10/2023
Failure to reach consensus on project re-scope option 
2 2  4   4
• Stakeholder engagement
• Re-scope proposal scope 5b approvals and approved by Partnership Board via
established AGD governance 
30/10/2023
Resource availability 3 2 6  6 • Effective deployment of resource to support delivery of the project 30/09/2026

Page 36

Project Updates – Regional Skills & Inclusion Programme 31 January 2024 
Project Name Project Lead Senior Responsible Officer
Ayrshire Skills Investment Fund Laura Neill Neale McIlvanney Working for Healthy Economy

Page 37

Ayrshire Skills Investment Fund Jan Project Overall Status
2024 Green
Project Update
Project Scope Status Green Project Budget Status Green
Monthly update - provide narrative Project Lead: Laura Neill
The ASIF sub-committee considered and approved in principle a proposal from Ayrshire College to deliver training interventions within Engineering, Digital, Visitor Economy and Clean Growth sectors across the next 3 years. The Employer Grants Programme was
launched in October inviting employers to identify training requests to support priority groups within priority sectors and the Sub Committee approved the applications recommended. Proposals from the University of the West of Scotland and NMIS Manufacturing
Skills Academy will be considered in the future. Commissioned research on current and future skills requirements for Ayrshire has commenced to ensure ASIF can prioritise skills development interventions to deliver the impact needed to increase productivity and
deliver inclusive economic growth for the region.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/04/2023 Complete No of people benefiting from in work skills development 500 tbc
FBC 30/06/2023 Complete No of people benefiting from pre-employment upskills 500 tbc 
People benefiting from accredited training 300 tbc
No of businesses benefiting from employees with improved skills levels 300 tbc
No of participants progressing to living wage opportunities 200 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 25/07/2023 Complete 1st annual review 30/06/2024 Green
FBC endorsed by Government 25/08/2023 Complete complete mid-programme evaluation 31/03/2025 Green
FBC approved by Joint Committee 07/08/2023 Complete End of programme/final drawdown 31/03/2027 Green
Development of guidance for fund applicants 30/06/2023 Complete quarterly application deadlines  Green
1st call for proposals 01/07/2023 Complete   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Project delays due to Covid-19  5  1  5    5
• Early analysis identifies that the need for this project may be greater as a result of Covid-19
• Continued economic analysis and development of recovery plans should be implemented
and robust project scoping should continue to ensure the proposal meets needs

Page 38

Working for Healthy Economy Jan Project Overall Status
2024 Green
Project Update
Project Scope Status Green Project Budget Status Green
Monthly update - provide narrative Project Lead: Laura Neill
We continue to monitor progress to ensure effective delivery across Ayrshire. Working for a Healthy Economy continues to be delivered across Ayrshire to help individuals manage and improve their health to progress to or sustain employment. In
November 2023 the following individuals were supported:
• 63 individuals were supported in November 2023 • Of the individuals completing the services to date there has been a 26.8% improvement in overall health and wellbeing
• On measuring anxiety, a 35.7% improvement in anxiety levels has been achieved • Depression levels experienced have improved by 44.2%
We continue to monitor progress to ensure effective delivery across Ayrshire. A range of events and ongoing promotional activities has been undertaken to achieve the figures reported above.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 19/02/2021 Complete No of people accessing assessment & report 960 tbc
FBC 22/02/2021 Complete No of people accessing full management support via telephone 1600 936 
No of people accessing full case management support delivered face to face 3838 282
No of people returning to work 1157 77
Unemployed residents supported 4629 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Evaluation commences 30/06/2022 Green End of programme/final drawdown 31/03/2027 Green
Year 3 targets achieved 31/03/2024 Green   
Year 4 targets achieved 31/03/2025 Green   
Year 5 targets achieved 31/03/2026 Green   
Year 6 targets achieved 31/03/2027 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Implementation: Over demand or lack of demand  5  5  25  
• Proposed targets are based on delivery experience across Scotland and the
experience of delivering a case management service in North Ayrshire recently
• The proposal as it stands is designed to remove barriers to accessing this service. In
the event of over demand, referral criteria can be set to reduce demand
• Project Board has discussed geographical disparity between geographies and agreed
mitigation action. Agreed to review again in October. 
Project delay and macro-economic impact of Covid-19 and recovery  5  5  25  
• Early analysis identifies that the need for the project is unlikely to be diminished – in
fact may be greater
• Continued economic analysis and development of recovery plans should be
implemented and robust project scoping should continue to ensure proposal meets
needs

Page 39

Project Updates – Community Wealth Building Programme 31 January 2024 
Project Name Project Lead Senior Responsible Officer
Community Wealth Building Emma McMullen Neale McIlvanney

Page 40

Community Wealth Building Jan Project Overall Status
2024 Green
Project Update
Project Scope Status Green Project Budget Status Green
Monthly update - provide narrative Project Lead: Emma McMullen
Over 1,000 local enterprises across Ayrshire have received support from the programme. This achievement has exceeded the original FBC target by 150 enterprises and is a credit to the hard work of programme delivery officers working with
enterprises to enhance their businesses through a Community Wealth Building approach. Further programme activity has increased, achieving the following key outputs:
• [1050  Unique Enterprises receiving support from the CWB programme •[264 Enterprises receiving financial assistance: Grant/ Consultancy support •[154 New enterprises supported (<12 months old)
• [261 Businesses registered on PCS •[300 Businesses attending 12many procurement workshops •[276 Businesses accessing 121 Procurement support/ Consultancy  •[167 Businesses attending 12many 'fair work' related workshops
• [223 Referrals for FW Ayrshire Programme •[26 Support in the creation or transition of 6 businesses to employee ownership or Co-Operative
• [136 Businesses attending 12many plural ownership workshops •[41 Businesses accessing 121 plural ownership specialist support / Consultancy. On January 15th, the programme received final approval through AEPB & JC for a one year
extension to enable continued momentum and support for enterprises across Ayrshire, and to further explore ways of mainstreaming the programme. The additional year will be resourced by fully utilising the programme’s underspend, with
additional funding brought in by individual Local Authorities such as the Shared Prosperity Fund.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 12/02/2021 Complete CWB Officers & Action Plans in place - creation of CWB Locality Baselines 15 all officers in post
FBC 22/02/2021 Complete Total enterprises engaged 920 1050 
Employers undertaking Fair Work Action Plans 90 222
Enterprises receiving financial assistance 265 264
New enterprises supported 96 154
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Fair work inspiration week (inl RLW & Disability Awareness) 30/11/2023 Green Ayrshire CWB Enterprise Awards & Programme Achievements celebration 30/04/2024 Green
Fair work job fair 28/02/2023 Green Monthly Programme Steering Group Meetings 31/03/2024 Green
500 Ayrshire enterprises supported by the CWB programme 31/03/2023 Green Reporting to PMO, Ayrshire REP & EJC members 31/03/2024 Green
Programme case study showcase - SG visits 31/05/2023 Green Annual report 31/03/2024 Green
1000 Ayrshire enterprises supported by the CWB & FWA programme 31/03/2024 Green Project end date/final review/final report/final drawdown 31/03/2024 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Project delays due to Covid-19  4  4  16  
• Early analysis identifies that the need for this project may be greater as a result of
Covid-19
• Continued economic analysis and development of recovery plans should be
implemented and robust project scoping should continue to ensure the proposal
meets needs

Page 41

Appendix 2 -  Annual Performance Report (Outline) Ayrshire Growth Deal – Q3 Oct-Dec 23) 
Key Performance Indicators: 
1. Increase the value of online coverage secured for Ayrshire Growth Deal partners and projects.
2. Increase the percentage of positive and very positive coverage secured for Ayrshire Growth Deal partners and projects. 
Increase the value of online media coverage secured: The value of each individual piece of coverage is calculated based on its reach (i.e., whether
it was used by a local/sectoral/regional/national media outlet), its prominence within that particular media outlet and the overall tone of the piece.
 Q3, 2023, From 1 October – 31 December, we secured 37 individual pieces of coverage with an overall media value of 430
 Q2, 2023, From 1July – 30 September, we secured 30 individual pieces of coverage with an overall media value of 547
 Q1, 2023, From 1 April – 30 June, we secured 35 individual pieces of coverage with overall media value of 602 
Previous quarter comparison: We have secured 37 individual pieces of coverage with overall media value of 430 in Q3, compared to 30
individual pieces of coverage with an overall media value of 547 last quarter. The overall media value is a 24% decrease in comparison
to last quarter. 
The graph below illustrates the breakdown of Media Value across the last 9 months:
Corporate Communications 
Annual Performance Report (Online)
Ayrshire Growth Deal 
Q3 1 October – 31 December 2023
(with comparison to Q2 1 July – 30 September) 
AGD
Comm

Page 42

The decrease in media value this quarter is due to fewer proactive press releases and breaking news stories compared to Q2 and Q3. 
However, although the media value has decreased, the number of positive or very positive news items has increased due to various third party
mentions of Ayrshire Growth Deal related projects (Prestwick Spaceport, and HALO) and proactive media coverage across a number of projects in
November/early December. 
We had three negative entries in Q3. These were related to local press coverage related to the affordability of East Ayrshire’s CoRE project, following
their recently published AGD performance report. 
Other than these, the media value was positively impacted as the weeks progressed thanks to the following highlights: 
- Several positive and very positive mentions of the launch of the £3m Ayrshire Skills Investment Fund – now open for applications
(October/November)
- Local and national coverage on plans to revive derelict land (with Third Party Mentions of AGD projects) (November)
- Ayrshire named as a ‘5G Innovation Region’ after securing £3.8 million of UK Government funding (November)
- Groundbreaking ceremony at i3 for the Advanced Manufacturing Flexible Space (November)
- Local, national and sectoral coverage secured as North Ayrshire’s Cabinet gives green light to masterplan for Irvine’s ambitious
Great Harbour redevelopment (December)
- Across local, regional, sectoral and national press, we reported 12 positive/very positive Third Party Mentions – the majority of these
were about Prestwick Spaceport and coincided with the news of Saxaford Spaceport in Shetland securing a significant funding boost
(these articles made reference to the Space industry across Scotland and rest of UK)
18
264
360
12
211
324
58
278
94
0
100
200
300
400
Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23
Overall Value of AGD Media Coverage Secured
Value of Media Coverage Secured

Page 43

Tone of online media coverage secured Q3: 
37 individual online pieces of coverage were received between 1 October and 31 December and 90% of the coverage has been either
Positive or Very Positive.
Tone Very Positive Positive Neutral Negative Very Negative
Q3: 1 October – 31 December 22 11 1 3 0 entries recorded
Overall percentage 60% 30% 2% 8% 
Q2 1 July – 30 September 20 8 0 2 0 entries recorded
Overall percentage 67% 27% 0 6% 
Q1: 1 April – 30 June  21 6 8 0 0 entries recorded
Overall percentage 60% 17% 23% 0 
The next section of the report includes a breakdown from Q3 and then the individual hyperlinks to review any of the individual articles of interest
featured this quarter.
Below are the individual pieces of Q3 coverage secured and overview of how we rate and measure tone of media items:
Very Positive (+3) – positive headline, positive mention of Ayrshire Growth Deal services, staff campaigns. No negative comment/component. Third
party endorsement. Any article which does not contain any negative element at all will qualify as very positive – even if it is just factual. 
60% (Very Positive)
30% (Positive)
8% (Negative) 2% (Neutral)
Very Positive Positive Negative Neutral

Page 44

Date Media Outlet Source Hyperlinks
24-Oct Irvine Times Press release Ayrshire Skills Investment Fund is open for applications | Irvine Times 
24-Oct Ayr Advertiser Press release Ayrshire Skills Investment Fund is open for applications - Ayr Advertiser 
25-Oct Largs and Millport Weekly
News Press release Ayrshire Skills Investment Fund is open for applications | Largs and Millport Weekly News 
26-Oct Irvine Times TPM CWB and DPMC North Ayrshire: Bid to revive and regenerate unused land | Irvine Times 
28-Oct Daily Record TPM CWB and DPMC Plans to help revive derelict land across 'struggling' North Ayrshire towns - Daily Record 
15-Nov Irvine Times Press release Irvine harbourside to get 5G upgrade after funding boost 
17-Nov Ayr Advertiser Press release 5G Innovation Region: Ayrshire £3.8 million government funds | Ayr Advertiser 
17-Nov Daily Record Press release Huge 5G tech boost for Ayrshire after four areas set to benefit from £3.8m - Daily Record 
17-Nov Cumnock Chronicle Press release 5G Innovation Region: Ayrshire £3.8 million government funds | Cumnock Chronicle 
18-Nov Irvine Times Press release 5G Innovation Region: Ayrshire £3.8 million government funds | Irvine Times 
18-Nov Irvine Times Press release Ground-breaking ceremony for £15 million Irvine project 
22-Nov Irvine Times Press release North Ayrshire councillor hails £37m Levelling Up funding - Irvine Times 
23-Nov Irvine Times TPM AGD Projects for £17m North Ayrshire Levelling Up funds revealed - Irvine Times 
23-Nov Largs and Millport Weekly
News TPM AGD Projects for £17m North Ayrshire Levelling Up funds revealed | Largs and Millport Weekly News 
23-Nov Ardrossan & Saltcoats
Herald Press release Projects for £17m North Ayrshire Levelling Up funds revealed | Ardrossan and Saltcoats Herald 
26-Nov Cumnock Chronicle TPM HALO Multi-million-pound housing investment agreed by East Ayrshire Council 
05-Dec Irvine Times Press release Council chiefs approve plan to transform Irvine harbourside 
07-Dec STV News Press release Harbour 'regeneration' project given green light as part of growth investment - STV News 
07-Dec Irvine Times Press release Council chiefs approve plan to transform Irvine harbourside 
08-Dec Daily Record Press release Exciting new £14 million Irvine Harbour development set for the go ahead - Daily Record 
06-Dec Scottish Construction Now Press release Irvine Great Harbour masterplan given green light | Scottish Construction Now 
15-Dec Irvine Times Press release Irvine i3 flexible office space set for completion in August - Irvine Times 
Positive (+2) – positive headline, positive mention of services, staff campaigns. It may include minor negative comment/component about North
Ayrshire Council as long as it’s overshadowed by positive aspect/comment. This can include press releases issued by another party as long as it does
more than mention Ayrshire Growth Deal or three-Ayrshire’s in passing, i.e. includes comment from Council. 
Date Media Outlet Source Hyperlinks

Page 45

04-Oct Irvine Times Press release Ayrshire Innovation Park: Consultation events over plans | Irvine Times 
04-Oct Cumnock Chronicle Performance report CoRE Ayrshire Innovation Park: Consultation events over plans | Cumnock Chronicle 
10-Nov Dunfermline Press TPM HALO Fife: Dunfermline MP calls for city's own HALO project 
14-Nov OPP Today Press release The Future of Connectivity: North Ayrshire Secures Funding for Advanced Wireless Infrastructure 
15-Nov BBC TPM Prestwick Spaceport Rocket launch from Shetland spaceport announced for next year - BBC News 
15-Nov The Scotsman TPM Prestwick Spaceport Could overseas talent help take the Scottish space industry to new heights? - Kelly Hardman 
18-Nov OPP Today Press release Ayrshire's Successful Bid for 5G Innovations Promises Transformation - OPP.Today
22-Nov The Herald TPM Prestwick Spaceport Scottish Government-owned Prestwick Airport posts profit - The Herald 
26-Nov Scottish Housing News TPM HALO Multi-million-pound housing investment agreed by East Ayrshire Council 
18-Dec BBC TPM Prestwick Spaceport Shetland is first UK spaceport for vertical rocket launches - BBC News 
25-Dec Cumnock Chronicle TPM AGD East Ayrshire Council leader shares festive message - Cumnock Chronicle 
Neutral (+1) – any incidental mention of Ayrshire Growth Deal or three-Ayrshire’s with no positive or negative comment/component. These will be
articles that only mention North Ayrshire Council in passing e.g. a press release issued by another party which mentions working in partnership with
the Council, national stories which feature performance of Council against other – those which do not focus on or include a comment from North
Ayrshire Council. 
Date Media Outlet Source Hyperlinks
07-Dec Flight Global  CoRE performance report Expression of interest in Glasgow Prestwick airport under examination: chief | Flight Global 
Negative (-2) – negative headline, criticism of Ayrshire Growth Deal, services, campaigns. Includes comment/component from three-Ayrshires… Even
where an article is very damaging, if we have been given a right of reply and there is a quote from us it only qualifies as negative. 
Date Media Outlet Source Hyperlinks
01-Oct Cumnock Chronicle CoRE performance report East Ayrshire Council: Cumnock CORE project unaffordable 
01-Oct Daily Record CoRE performance report East Ayrshire Council's £24.5m renewable energy project in 'unaffordable' - Daily Record 
09-Oct Cumnock Chronicle CoRE performance report Cumnock: Core project delayed due to being unaffordable

Page 46

Very negative (-3) – negative headline, criticism of Ayrshire Growth Deal staff, services, campaigns. Does not include comment/component from
North Ayrshire Council. This should be very rare as it is the lack of response from North Ayrshire Council which qualifies it as very negative. 
Date Media Outlet Source Hyperlinks
N/A N/A N/A  N/A 
Final thoughts
In the coming months, we anticipate securing more positive and very positive news coverage as the following developments will be in the pipeline:
 The official opening of the Digital Process Manufacturing Centre in February
 Progress on the i3 Advanced Manufacturing Flexible Space
 Announcement of successful Ayrshire Skills Investment Fund applications
 Submission of a planning application for phase one of the coastal hub play park, skate park and pilot house development.
Future reporting: For next edition(s) of reporting, we will continue to utilise Google Alerts to ensure we are capturing local, national, sectoral for ALL
AGD projects