North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
Ayrshire Economic Joint Committee
A Meeting of the Ayrshire Economic Joint Committee of North Ayrshire Council will
be held in the Virtual Meeting,  on Monday, 20 November 2023 at 14:00 to consider
the undernoted business.
Meeting Arrangements ­ Fully Remote 
This meeting will be held remotely in accordance with the provisions of 
the Local Government (Scotland) Act 2003.  Where possible, the meeting
will be live­streamed and available to view at https://north­ayrshire.public­
i.tv/core/portal/home.  In the event that live­streaming is not possible, a 
recording of the meeting will instead be available to view at this location.
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda.
2 Appointment of Chair
The Joint Committee is requested to note the appointment of Councillor 
Marie Burns (North Ayrshire Council) as Chair of the Ayrshire Economic 
Joint Committee (AEJC) for the period from September 2023 to 31 
August 2024 and to ratify the appointment of Councillor Marie Burns as 
Chair of the Ayrshire Economic Partnership Board (AEPB) for the period 
from September 2023 to 31 August 2024.
3 Minutes
The accuracy of the Minutes of Special meetings of the Joint Committee 
held on (a) 7 August 2023 and (b) 18 September 2023 will be confirmed 
and the Minutes signed in accordance with Paragraph 7 (1) of Schedule 7
of the Local Government (Scotland) Act 1973 (copy enclosed).
4 AGD Internal Audit Annual Report 2022/23
Submit report by the Chief Auditor (East Ayrshire Council) providing for 
noting an annual report on internal audit activity in line with obligations 
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
laid out in Ayrshire Growth Deal (AGD) Governance Document (copy 
enclosed).
5 AGD Internal Audit Plan 2023/24
Submit report by the Chief Auditor (East Ayrshire Council) providing for 
noting an annual consolidated internal audit plan in line with obligations 
laid out in Ayrshire Growth Deal (AGD) Governance Document (copy 
enclosed).
6 Ayrshire Growth Deal ­ Programme Update
Submit report by the Head of Economic Growth (East Ayrshire Council) 
advising of the progress of the Ayrshire Growth Deal (AGD) and the 
development of its component projects as at 31 October 2023 (Appendix 
1) (copy enclosed).
7 Ayrshire Growth Deal ­ Programme Risk Register Update (October
2023)
Submit report by the Head of Economic Growth (East Ayrshire Council) 
providing an update on the AGD Programme Risk Register as at the end 
of October 2023 (copy enclosed).
8 Schedule of Future Meeting Dates ­ 2024
The Joint Committee is requested to note that Ordinary Meetings of the 
Ayrshire Economic Joint Committee (AEJC) will take place at 2pm on 
Monday, 19 February; Monday, 20 May; Monday, 9 September and 
Monday, 25 November 2024. Calendar invitations have been issued in 
this respect.
9 Urgent Items
Any other items which the Chair considers to be urgent.
10 Exclusion of the Public ­ Paras 9 & 10
Resolve in terms of Section 50(A)4 of the Local Government (Scotland)
Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraphs
9 and 10 of Part 1 of Schedule 7A  of the Act.
Non Disclosure of Information
In terms of Standing Order 21 (Disclosure of Information), the information
contained within the following report is confidential information within the
meaning of Section 50A of the 1973 Act and shall not be disclosed to any
person by any Member or Officer.
11 Exempt Item: Ayrshire Growth Deal Subsea Cable and Infill projects
re­scoping proposal
Submit report by the Project Lead – Digital, Ayrshire Growth Deal (AGD) 
on the above (copy enclosed).
Webcasting
Please note: this meeting may be filmed/recorded/live­streamed to the
Council's internet site and available to view at https://north­ayrshire.public­
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
i.tv/core/portal/home, where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live­streamed.
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
Generally, the press and public seating areas will not be filmed. However,
by entering the Council Chambers, using the press or public seating area
or (by invitation) participating remotely in this meeting, you are consenting
to being filmed and consenting to the use and storage of those images and
sound recordings and any information pertaining to you contained in them
for  webcasting  or  training  purposes  and  for  the  purpose  of  keeping
historical records and making those records available to the public. If you
do not wish to participate in a recording, you should leave the meeting. 
This will constitute your revocation of consent.
If you have any queries regarding this and, in particular, if you believe that
use and/or storage of any particular information would cause, or be likely
to cause, substantial damage or distress to any individual, please contact
dataprotectionofficer@north­ayrshire.gov.uk.
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
Ayrshire Economic Joint Committee Sederunt
North Ayrshire Council
Councillor Marie Burns
Councillor Joe Cullinane
Councillor Anthony Gurney
Craig Hatton
Russell McCutcheon
Neale McIlvanney
Louise Kirk
 
East Ayrshire Council
Councillor Douglas Reid
Councillor Iain Linton
Councillor Maureen McKay
Councillor Stephen Canning (sub)
Councillor Barry Douglas (sub)
Councillor William Lennox (sub)
Eddie Fraser
David McDowall
Graham Saunders
 
South Ayrshire Council
Councillor Martin Dowey
Councillor William Grant
Councillor Bob Pollock
George Hunter
Theo Leijser
Mike Newall
 
Others
Simon Fraser, Spirit Aerosystems
Jane Martin, Scottish Enterprise
Angela Cox, Ayrshire College
Paul Zealey, Skills Development Scotland
 
Chair:
Apologies:
Attending:
4

Page 5

AYRSHIRE ECONOMIC JOINT COMMITTEE
MINUTES OF MEETING HELD ON MONDAY 7 AUGUST 2023 AT 
1049 HRS IN THE COUNCIL CHAMBERS, EAST AYRSHIRE COUNCIL
HEADQUARTERS, LONDON ROAD, KILMARNOCK 
AND BY VIDEO CONFERENCE
PRESENT: Councillors Douglas Reid, Clare Maitland and Maureen McKay, East
Ayrshire Council; Councillor Anthony Gurney, North Ayrshire Council; Councillors
Martin Dowey, William Grant and Bob Pollock, South Ayrshire Council; Angela Cox,
Ayrshire College; and Paul Zealey, Skills Development Scotland.
ATTENDING: Eddie Fraser, Chief Executive; Dougal Watt, Senior Auditor; Graham
Saunders, Interim Strategic Manager and Programme Manager - Ayrshire Growth
Deal; Mags Watson, Strategic Manager Economic Development (Interim). all East
Ayrshire Council; Craig Hatton, Chief Executive; Neale McIlvanney, Interim Head of
Service (Growth, Investment and Employability); Louise Kirk, Head of Service/
Economic Development and Regeneration; Laura Neill, Senior Manager Employability;
and Craig Stewart, Committee Services Officer, all North Ayrshire Council; George
Hunter, Assistant Director - Communities; and Louise Reid, Assistant Director -
Strategic Change;  both South Ayrshire Council; and Christine Baillie, Democratic
Services Team Leader and Sheryl Wilcox, Democratic Services Officer, both East
Ayrshire Council.
APOLOGIES: Councillor Marie Burns, North Ayrshire Council; and Jane Martin,
Scottish Enterprise.
CHAIR: Councillor Douglas Reid, Chair.
PREVIOUS MINUTES
1. There were submitted (circulated) and approved as a correct record, the Minutes of
the meeting held on 26 June 2023, with no matters arising.
AUDIT SCOTLAND: “SCOTLAND’S CITY REGION AND GROWTH DEALS -
PROGRESS OF THE 2020 AUDIT REPORT RECOMMENDATIONS”, JUNE 2023
2. There was submitted and noted a report (circulated) by the Head of Economic Growth,
East Ayrshire Council which informed members of Audit Scotland’s publication of a
follow-up report on Scottish Growth Deals, focussing on issues relevant to the Ayrshire
Growth Deal.
AYRSHIRE REGIONAL REVENUE PROJECT -
AYRSHIRE SKILLS INVESTMENT FUND
3. There was submitted a report (circulated) by the Chief Executive, North Ayrshire
Council which sought approval of the draft Full Business Case for the Ayrshire Growth
Deal Ayrshire Skills Investment Fund (ASIF), subject to final endorsement of the
Scottish Government. The Draft Full Business Case was attached as Appendix 1 to
the report.
It was agreed:
(i) to note the content of the draft Full Business Case (FBC);
Agenda Item 3
5

Page 6

(ii) to delegate authority to the Chief Executive (North Ayrshire Council) to approve
the FBC and agree the implementation of the ASIF subject to modifications to
the business case to secure Scottish Government endorsement; and
(iii) to note agreed governance arrangements had been implemented, which
created the AEJC Sub-Committee, with delegated authority to award the fund. 
CHAIR’S REMARKS 
4. The Chair advised that the Chairing of the Committee and the administrative
arrangements  would rotate to North Ayrshire Council from 1 September 2023 
The meeting terminated at 1053 hrs. 
6

Page 7

Ayrshire Economic Joint Committee
18 September 2023
At a Special Meeting of the Ayrshire Economic Joint Committee at 11.00 a.m.
involving participation by remote electronic means.
Present
Councillors Marie Burns and Anthony Gurney (North Ayrshire Council); Iain Linton
and Maureen McKay (East Ayrshire Council); and Martin Dowey and Bob Pollock
(South Ayrshire Council).
In Attendance
Russell McCutcheon, N. McIlvanney, L. Kirk, E. McMullen and A. Finlayson (North
Ayrshire Council); D. McDowall and D. Watt (East Ayrshire Council); E. Howat and
G. Hunter (South Ayrshire Council); S. Foster (Spirit AeroSystems); D. McCrindle
(Scottish Enterprise); A. Cox (Ayrshire College); P. Zealey (Skills Development
Scotland); C. Stewart and S. Wilson (North Ayrshire Council).
Apologies
Councillors Douglas Reid (East Ayrshire Council) and William Grant (South Ayrshire
Council), Craig Hatton (North Ayrshire Council), Eddie Fraser and Graham Saunders
(East Ayrshire Council) and Jane Martin (Scottish Enterprise).
Chair
Councillor Marie Burns in the Chair.
1. Declarations of Interest
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors
2. Ayrshire Regional Economic Strategy Delivery Plan
Submitted report by the Executive Director, Place (North Ayrshire Council)
requesting approval of the Joint Committee to: (a) agree the draft Year One Delivery
Plan provided at Appendix One to the report; and (b) receive further reports for future
years of the Delivery Plan.
The Joint Committee noted the terms and content of the presentation on the Ayrshire
Regional Economic Strategy Delivery Plan, which was made at the immediately
preceding meeting of the Ayrshire Economic Partnership Board.
The Joint Committee agreed to (a) approve the draft Year One Delivery Plan
provided at Appendix One to the report; and (b) receive further reports for future
years of the Delivery Plan.
The meeting ended at 11.10 a.m.
Agenda Item 3
7

Page 8

8

Page 9

AYRSHIRE ECONOMIC JOINT COMMITEE 
MEETING – 20 NOVEMBER 2023
REPORT BY CHIEF AUDITOR, EAST AYRSHIRE COUNCIL
SUBJECT: AGD INTERNAL AUDIT ANNUAL REPORT 2022/23
PURPOSE OF REPORT
1. The purpose of this report is to provide, for noting, an annual report on internal
audit activity in line with obligations laid out in the Ayrshire Growth Deal (AGD)
Governance Document. Specifically this report provides:
• a summary of AGD internal audit work both prior to and since inception;
and
• an annual internal audit opinion for the AGD for 2022/23.
RECOMMENDATIONS
2. The Joint Committee is asked to:
a) note the current arrangements for Internal Audit as laid out at Appendix 1;
b) note the work carried out prior to and since inception, including during
2022/23, as laid out in Appendix 2;
c) note the AGD Annual Internal Audit Opinion of continuing reasonable
assurance as laid out at paragraphs 10-11;
d) otherwise note the contents of the report.
BACKGROUND
CONSIDERATION BY THE PARTNERSHIP BOARD
3. This report was considered by the Ayrshire Economic Partnership Board on 7
September 2023.
REQUIREMENT TO HAVE AN INTERNAL AUDIT FUNCTION
4. The Local Authority Accounts (Scotland) Regulations 2014 require local
authorities to operate a professional and objective internal auditing service; in
practice this means that the internal audit function is operationally
independent; free from limitations on the scope of its work and that the Chief
Auditor reports independently with no undue influence. The internal audit
service must be provided in accordance with recognised standards and
practices which are currently those set out in the Public Sector Internal Audit
Standards (PSIAS). It is the responsibility of each authority to ensure
compliance with the PSIAS.
Agenda Item 4
9

Page 10

CONTROL ENVIRONMENT WITHIN COUNCILS 
5. It is primarily the responsibility of management to establish an appropriate and
sound system of internal controls, and to monitor the continuing effectiveness
of that system. 
6. Internal Audit reports are presented to senior management and include
recommendations that, when implemented, will further improve the control
environment. 
MAIN REPORT 
INTERNAL AUDIT WORK PRIOR TO AND SINCE INCEPTION 
7. Ten assignments have been carried out across the three Ayrshire Councils for
the AGD. The scope and outcomes of these exercises are summarised at
Appendix 2. Outcomes reported to date range from reasonable assurance to
sound in most areas. EAC advisory exercises are counted as single
assignments in each year but cover multiple areas. 
8. Last year we noted a potential risk from staff turnover and long term sick
absence within the PMO; management at that time moved quickly to put
interim cover arrangements in place and recognised the longer term risk by
progressing a review of the PMO structure. The senior post has now been
filled on a permanent basis with recruitment underway for the second tier post.
The Accountable Body’s Chief Financial Officer is working to further
strengthen resilience in advance of the commencement of the remaining
projects.  
9. Our work has been informed by the Audit Scotland publication Scotland’s City
Region & Growth Deals (January 2020) with a follow up published in June
2023 which was considered by the AEPB and AEJC on 7 August 2023 noting
AGD internal audit good practice. That report also reinforced that the recent
AEJC agreement to review the AGD risk register quarterly is good practice.            
AGD ANNUAL INTERNAL AUDIT OPINION 2022/23
10. Work carried out in 2022/23 and published to date is sufficient to allow the
Chief Auditor to produce an Annual Internal Audit Opinion for the year to 31
March 2023. The most that Internal Audit will provide in the annual opinion is
reasonable assurance based on the risk based plan and a rolling programme
of work. This is similar to the scope of external audit work in the context of a
Council’s financial statements which aims to give reasonable assurance on the
statements. 
11. Our overall opinion, based on the 2022/23 work presented in Appendix 2, is
that reasonable assurance can continue to be placed upon the adequacy and
effectiveness of the AGD’s framework of governance, risk management and
control in the year to 31 March 2023. We note that South Ayrshire Council’s
governance work in 2022/23 is yet to be published but irrespective of that
outcome we are assured that a robust approach is taken by the three Council
internal audit teams supporting the assurance framework within which the
AGD operates. 
10

Page 11

AUTHORITY WIDE ANNUAL INTERNAL AUDIT OPINIONS 2022/23
12. AGD operations are managed mainly through the control environments of the
three Ayrshire Councils. The Chief Auditors in all three Councils have issued
annual authority wide opinions of reasonable assurance. 
IMPLICATIONS 
13. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance  No 
3. Human Resources  No 
4. Equality and Fairer Scotland Duty  No 
5. Financial   No 
6. Risk  Yes  Para 14
7. Community Wealth Building   No 
8. Net Zero   No 
RISK IMPLICATIONS (INTERNAL AUDIT RESOURCES) 
14. Each year there is the ongoing risk of significant unplanned work emerging in
each Council, planned resources for AGD work not being available and work
not being carried out to an acceptable standard which would compromise the
ability to complete sufficient work to produce an Annual Internal Audit Opinion
for the AGD; local mitigations should offset the potential impact of these risks. 
APPENDICES
15. The annual report is supported by two appendices: 
• Appendix 1: AGD Governance Document (Internal Audit Extract) 
• Appendix 2: AGD Internal Audit Assignments Prior to and Since
Inception 
Eilidh Mackay 
Chief Auditor, East Ayrshire Council 
1 November 2023 
BACKGROUND PAPERS 
1. Public Sector Internal Audit Standards (PSIAS) (3rd edition March 2017)
2. Chartered Institute of Public Finance and Accountancy (CIPFA) Local
Government Application Note for the United Kingdom Public Sector Internal
Audit Standards (2nd edition February 2019) 
3. Chartered Institute of Public Finance & Accountancy (CIPFA), CIPFA
Statement on the Role of the Head of Internal Audit in Public Service
Organisations (2nd edition April 2019)
4. AGD Governance Document 
11

Page 12

Deal Documents - All Documents (south-ayrshire.gov.uk) 
Person to Contact:  
Eilidh Mackay, Chief Auditor, East Ayrshire Council             
Email: eilidh.mackay@east-ayrshire.gov.uk 
Implementation Officers: 
Eilidh Mackay, Chief Auditor, East Ayrshire Council              
Laura Miller, Senior Manager (Audit, Fraud, Safety & Insurance), North              
Ayrshire Council 
Email: lauramiller1@north-ayrshire.gov.uk 
Cecilia McGhee, Chief Internal Auditor, South Ayrshire Council 
Email:  Cecilia.McGhee2@south-ayrshire.gov.uk 
12

Page 13

Appendix 1
AGD GOVERNANCE DOCUMENT V15 (INTERNAL AUDIT EXTRACT)
2.16 The Accountable Body’s Chief Auditor will be appointed as Chief Auditor for the
AGD to coordinate Internal Audit activity. 
2.17 Each partner will be responsible for allocating Internal Audit resources as
required for local AGD activities. The Accountable Body’s Internal Audit section
will reserve the right to review programme and project activities as required and
request information from all partners regarding these activities. 
2.18 Each year a consolidated Internal Audit Plan will be presented to the AEJC and
AREP having been prepared following:
• consultation with relevant senior officers of the AGD PMO;
• consideration of the risks affecting the AGD at programme and project
level;
• consideration of both internal and external factors affecting the AGD;
• consideration of previous internal and external audit findings;
• consideration of all of these elements which will inform Public Sector
Internal Audit Standards (PSIAS) based risk assessments carried out
locally by the Accountable Body and Partner Authorities; and
• any relevant items subsequently included in local Internal Audit plans
approved by each partner’s audit committee in line with PSIAS
obligations will be reflected in the consolidated AGD Internal Audit
Plan. 
2.19 All AGD Internal Audit work will be carried out in line with the PSIAS with
individual Internal Audit assignment reports presented to the AEJC and AREP
for noting. 
2.20 The relevant annual Internal Audit Report will be submitted to both UK and
Scottish Governments upon completion. The AEJC and AREP will be advised of
the overall outcomes from Internal Audit work in an annual Internal Audit Report
the timing of which is anticipated to align with the annual accounts timetable
and will be reported to the AEJC and AREP for noting in line with PSIAS
requirements. The Annual Internal Audit Report will include a summary of AGD
internal audit work in year by all partners, an annual opinion for the AGD and for
further assurance will also include the authority–wide Annual Internal Audit
opinions prepared by each partner. 
2.21 Actions arising from Internal Audits will be followed up by the relevant Internal
Audit team in line with established arrangements in that authority and these
follow-up reports will be presented to the AEJC and AREP for noting. 
2.22 Further audit, advisory consultancy or investigative work may be requested by
the AEJC and AREP. 
2.23 The Accountable Body’s Chief Auditor will liaise with partner Chief Auditors
through established arrangements.
13

Page 14

Appendix 2 
AGD INTERNAL AUDIT ASSIGNMENTS PRIOR TO AND SINCE INCEPTION 
Year Council Type of
Audit Work
Scope Outcome Link to “Audit
Room” on AGD
Portal
(members only)
Up to and
including
2020/21
East Ayrshire
Council 
Advisory  Both prior to the AGD being signed off on
20 November 2020 and since advice has
been provided on governance
arrangements. 
Advisory  Not applicable 
2021/22 East Ayrshire
Council 
Advisory &
Assurance 
The aims and objectives were to inform
the lead client, the Chief Financial Officer
and Head of Finance & ICT, on how well
systems and processes within the
Programme Management Office (PMO)
which are designed to keep the Ayrshire
Growth Deal (AGD) on track, are working
in practice; and to advise on any scope for
improvement in systems and compliance
verification processes which are identified
by our assurance work. This included
advising on the update of the AGD
Governance Document V15. 
Our overall
assessment of
controls
concluded that
there was sound
assurance in
most areas - key
controls exist and
are applied
consistently and
effectively in most
areas. Non-
compliance has
only been
identified in low
risk or medium
risk areas. 
21-22 EAC Internal
Audit Report -
Advisory &
Assurance.pdf 
14

Page 15

2021/22 North Ayrshire
Council 
Governance  The scope of this audit was limited to
North Ayrshire Council’s role in the
projects. It focused on the governance
structures across the Council’s
participation in the deal rather than
individual projects. 
The main objectives of the audit were to
ensure that:
· governance structures and roles and
responsibilities of officers and elected
members within North Ayrshire Council, in
relation to the Ayrshire Growth Deal are
clearly defined and communicated in
order to enable good governance and
strong accountability
· North Ayrshire Council has adequate risk
management arrangements in place in
relation to the Ayrshire Growth Deal
· suitable arrangements are in place to
monitor the progress of the Ayrshire
Growth Deal programmes within North
Ayrshire, including appropriate reporting
and scrutiny arrangements
· there are adequate arrangements in
place to ensure that North Ayrshire
Council is fulfilling the requirements of the
Project Management Office and external
funding providers.
Overall,
reasonable
assurance was
obtained with
regard to the
governance
arrangements for
the Ayrshire
Growth Deal
within North
Ayrshire Council.
Overall good
governance
arrangements are
in place, but
some of the
projects are still
at an early stage
of development
and therefore it
has not been
appropriate to
fully develop
the governance
arrangements
yet.
21-22 NAC Internal
Audit Report - AGD
Governance.pdf 
2021/22 South Ayrshire
Council 
Governance The aim of the assignment was to obtain
assurance that there are adequate
governance arrangements in place for
Reasonable
assurance was
obtained that
21-22 SAC Internal
Audit Report - AGD
Governance.pdf
15

Page 16

South Ayrshire Council Ayrshire Growth
Deal (AGD) portfolio of projects.
there are
adequate internal
governance
arrangements in
place for South
Ayrshire
Council’s portfolio
of AGD projects. 
2022/23  East Ayrshire
Council 
Assurance  Testing of AGD Grant Claims.  
The aim of this assignment was to provide
assurance to the EAC Chief Financial
Officer and Head of Finance & ICT that
the AGD Quarter 4 2021/22 Grant Claim
Forms had been completed accurately
and in line with the requirements of the
UK and Scottish Governments and AGD
procedures, prior to the deadline for their
sign-off on 22 April 2022.  Our work was
carried out in “real-time” and the Chief
Financial Officer was immediately advised
of the assurance which could be placed
on processes prior to the sign-off and
submission of the claim.  The value of the
Grant Claim was £0.335m (Community
Wealth Building - £154,408, Working for a
Healthy Economy - £180,748).Assurance
was also sought for the residual element
of the Quarter 4 2021/22 Grant Claim,
which was claimed for in July 2022 along
Sound
assurance. 
We found that
both elements of
the Quarter 4
Grant Claim had
been completed
accurately, were
fully signed by
appropriate
officers and were
in line with the
requirements of
the UK and
Scottish
Governments and
AGD procedures.
We also identified
areas for
consideration for
continuous
improvement. 
22-23 – EAC AGD
Grant Claims 
16

Page 17

Follow-up 
Advisory 
with the Quarter 1 2022/23 Grant Claim. 
This review was retrospective due to the
low value of the claim (£0.010m). 
Follow-Up of 2021/22 Findings 
Advisory work included: 
• Governance Document revision
• Risk Register 
• Benefits Realisation Plan 
• Support to Audit Scotland follow-
up exercise (see paragraph 8)
• Attendance at AEPB and AEJC
meetings to inform our work 
Score 100% (2/2
recommendations
fully
implemented) 
22-23 – EAC AGD
Advisory &
Assurance – Follow
Up 
2022/23  North Ayrshire
Council 
Assurance Contingency budget in place and the aim 
would be to reserve this for any claims 
audits in year. 
No work required Not applicable
2022/23 South Ayrshire
Council 
Assurance 
Follow-up 
Testing of internal governance 
arrangements. 
Follow-Up of 2021/22 Findings.
To be confirmed. 
All actions
sufficiently
implemented. 
Awaiting publication. 
22-23 - SAC - AGD
Governance
Arrangements -
Follow-Up.pdf
17

Page 18

18

Page 19

AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 20 NOVEMBER 2023
REPORT BY CHIEF AUDITOR, EAST AYRSHIRE COUNCIL
SUBJECT: AGD INTERNAL AUDIT PLAN 2023/24
PURPOSE OF REPORT
1. The purpose of this report is to provide, for noting, an annual consolidated
internal audit plan in line with obligations laid out in the Ayrshire Growth Deal
(AGD) Governance Document.
RECOMMENDATIONS
2. The Joint Committee is asked to:
a) note the current arrangements for Internal Audit as laid out at Appendix 1;
b) note the regulatory responsibility for each Council to approve days spent
on AGD work as laid out at paragraph 7 and the subsequent annual
consolidated internal audit plan for the AGD as presented at Appendix 2;
c) note the previously agreed arrangements to report the outcomes of
individual internal audit assignments laid out at paragraph 8; and
d) otherwise note the contents of the report.
BACKGROUND
CONSIDERATION BY THE PARTNERSHIP BOARD
3. This report was considered by the Ayrshire Economic Partnership Board on 7
September 2023 noting the statutory context in which AGD assignments are
formally approved within individual Council internal audit plans.
REQUIREMENT TO HAVE AN INTERNAL AUDIT FUNCTION
4. The Local Authority Accounts (Scotland) Regulations 2014 require local
authorities to operate a professional and objective internal auditing service; in
practice this means that the internal audit function is operationally
independent; free from limitations on the scope of its work and that the Chief
Auditor reports independently with no undue influence. The internal audit
service must be provided in accordance with recognised standards and
practices which are currently those set out in the Public Sector Internal Audit
Standards (PSIAS). It is the responsibility of each authority to ensure
compliance with the PSIAS.
Agenda Item 5
19

Page 20

CONTROL ENVIRONMENT WITHIN COUNCILS 
5. It is primarily the responsibility of management to establish an appropriate and
sound system of internal controls, and to monitor the continuing effectiveness
of that system. 
6. Internal Audit reports are presented to senior management and include
recommendations that, when implemented, will further improve the control
environment. 
MAIN REPORT 
INTERNAL AUDIT PLANNING RESPONSIBILITIES 
7. From 2021/22 each Council, in line with PSIAS requirements, carries out a risk
assessment and decides how many days are to be allocated to the AGD in
year. In line with the PSIAS, these days are approved as part of each
Council’s Annual Internal Audit Plan by the relevant Council’s audit committee.
The approved days are consolidated by the East Ayrshire Council (EAC) Chief
Auditor and brought to the AEPB and AEJC. The 2023/24 Plan is attached at
Appendix 2 noting a small increase in EAC days since the plan was
considered by the AEPB. 
REPORTING ARRANGEMENTS FOR INDIVIDUAL INTERNAL AUDIT
ASSIGNMENTS
8. On 13 September 2021 the AEJC agreed that outcomes from individual
internal audit assignments will be shared with the established readership in the
Council which carried out the work, the EAC Chief Auditor and members of the
AEJC and other relevant forums in line with any revisions to governance
arrangements agreed by the AEJC. Through the PMO, assignment reports are
placed within an “audit room” on the AGD portal. A summary of this work is
included in the AGD Internal Audit Annual Report for consideration by the
AEPB and AEJC. 
IMPLICATIONS 
9. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance  No 
3. Human Resources  No 
4. Equality and Fairer Scotland Duty  No 
5. Financial   No 
6. Risk  Yes  Para 10
7. Community Wealth Building   No 
8. Net Zero   No 
20

Page 21

RISK IMPLICATIONS (INTERNAL AUDIT RESOURCES) 
10. Each year there is the ongoing risk of significant unplanned work emerging in
each Council, planned resources for AGD work not being available and work
not being carried out to an acceptable standard which would compromise the
ability to complete sufficient work to produce an Annual Internal Audit Opinion
for the AGD; local mitigations should offset the potential impact of these risks.
APPENDICES
11. The report is supported by two appendices: 
• Appendix 1: AGD Governance Document (Internal Audit Extract) 
• Appendix 2: AGD Consolidated Internal Audit Annual Plan 2023/24 
Eilidh Mackay 
Chief Auditor, East Ayrshire Council 
1 November 2023 
BACKGROUND PAPERS 
1. Public Sector Internal Audit Standards (PSIAS) (3rd edition March 2017)
2. Chartered Institute of Public Finance and Accountancy (CIPFA) Local
Government Application Note for the United Kingdom Public Sector Internal
Audit Standards (2nd edition February 2019) 
3. Chartered Institute of Public Finance & Accountancy (CIPFA), CIPFA
Statement on the Role of the Head of Internal Audit in Public Service
Organisations (2nd edition April 2019)
4. AGD Governance Document 
Deal Documents - All Documents (south-ayrshire.gov.uk) 
Person to Contact:  
Eilidh Mackay, Chief Auditor, East Ayrshire Council             
Email: eilidh.mackay@east-ayrshire.gov.uk 
Implementation Officers: 
Eilidh Mackay, Chief Auditor, East Ayrshire Council              
Laura Miller, Senior Manager (Audit, Fraud, Safety & Insurance), North              
Ayrshire Council 
Email: lauramiller1@north-ayrshire.gov.uk 
Cecilia McGhee, Chief Internal Auditor, South Ayrshire Council 
Email:  Cecilia.McGhee2@south-ayrshire.gov.uk 
21

Page 22

Appendix 1
AGD GOVERNANCE DOCUMENT V15 (INTERNAL AUDIT EXTRACT)
2.16 The Accountable Body’s Chief Auditor will be appointed as Chief Auditor for the AGD
to coordinate Internal Audit activity. 
2.17 Each partner will be responsible for allocating Internal Audit resources as required for
local AGD activities. The Accountable Body’s Internal Audit section will reserve the
right to review programme and project activities as required and request information
from all partners regarding these activities. 
2.18 Each year a consolidated Internal Audit Plan will be presented to the AEJC and
AREP having been prepared following:
• consultation with relevant senior officers of the AGD PMO;
• consideration of the risks affecting the AGD at programme and project level;
• consideration of both internal and external factors affecting the AGD;
• consideration of previous internal and external audit findings;
• consideration of all of these elements which will inform Public Sector Internal
Audit Standards (PSIAS) based risk assessments carried out locally by the
Accountable Body and Partner Authorities; and
• any relevant items subsequently included in local Internal Audit plans
approved by each partner’s audit committee in line with PSIAS obligations will
be reflected in the consolidated AGD Internal Audit Plan. 
2.19 All AGD Internal Audit work will be carried out in line with the PSIAS with individual
Internal Audit assignment reports presented to the AEJC and AREP for noting. 
2.20 The relevant annual Internal Audit Report will be submitted to both UK and Scottish
Governments upon completion. The AEJC and AREP will be advised of the overall
outcomes from Internal Audit work in an annual Internal Audit Report the timing of
which is anticipated to align with the annual accounts timetable and will be reported
to the AEJC and AREP for noting in line with PSIAS requirements. The Annual
Internal Audit Report will include a summary of AGD internal audit work in year by all
partners, an annual opinion for the AGD and for further assurance will also include
the authority–wide Annual Internal Audit opinions prepared by each partner. 
2.21 Actions arising from Internal Audits will be followed up by the relevant Internal Audit
team in line with established arrangements in that authority and these follow-up
reports will be presented to the AEJC and AREP for noting. 
2.22 Further audit, advisory consultancy or investigative work may be requested by the
AEJC and AREP. 
2.23 The Accountable Body’s Chief Auditor will liaise with partner Chief Auditors through
established arrangements. 
22

Page 23

Appendix 2 
AGD CONSOLIDATED INTERNAL AUDIT ANNUAL PLAN 2023/24
Council / date
Internal Audit
plan agreed in
line with PSIAS 
Anticipated Assignments Indicative 
Days
East Ayrshire
20 April 2023  
AGD Advisory - incl Chief Auditor support to 
Joint Committee / Audit Manager & Senior 
Auditor support to PMO.  
Original 17
Revised 26        
North Ayrshire
28 March 2023 
Review the arrangements in North Ayrshire
Council in relation to the AGD revenue
projects. 
20 
South Ayrshire 
22 March 2023
Follow-up of actions from 2022/23 
assignment and review (scope to be agreed 
following completion of 2022/23 work) 
25 
Total scheduled days  Original 62
Revised 71 
23

Page 24

24

Page 25

AYRSHIRE ECONOMIC JOINT COMMITTEE
– 20 NOVEMBER 2023
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL - PROGRAMME UPDATE
PURPOSE OF REPORT
1. To advise the Economic Joint Committee members of the progress of the Ayrshire
Growth Deal (AGD) and the development of its component projects as at 31 October
2023 (Appendix 1). Please note this report provides a further update on the AGD
Programme and projects as reported to the 7 September 2023 Partnership Board.
RECOMMENDATIONS
2. It is recommended that Members agree:
(i) The updates provided in the attached report (as of 31 October 2023);
(ii) The progress across the Ayrshire Growth Deal Programme; and
(iii) Remit officers to liaise with both Governments to progress the projects having
regard to the updated position in line with the formal change requirements
contained within the Deal protocols;
(iv) Note the proposal for realignment of the reporting requirements, principally the
undertaking of the Annual Performance Report, Financial Plan, Implementation
Plan and Benefit Realisation Plan at the end of March 24, and onwards at the
same time ever year. All subject to agreement from the Government.
BACKGROUND
3. This report is an update on the progress made on the Ayrshire Growth Deal (AGD). It
has been prepared in line with the agreed governance structure and its commitment to
monitoring and reporting progress across all parts of the Deal’s programme on regular
basis.
4. A summary of the current status of the programme priorities and the development work
associated with individual projects is contained within the progress report attached to
this covering report. The report covers progress up to 31 October 2023 Please see
Appendix 1). The previous update was reported to the Ayrshire Economic Partnership
Board (AEPB), on 7 September 2023, and included progress up to the 25 August 2023.
This report and attachments includes further updates.
5. Please note that the reporting period has sought to align as much as possible with the
with the financial year’s quarters. However this report includes progress made in Q2
Agenda Item 6
25

Page 26

and the start of Q3. Discussions are still underway with the secretariat for the AEPB
and Ayrshire Economic Joint Committee (AEJC) in order to improve alignment of the
quarters with the AGD programme reporting to members. 
6. The report considers the progress made on the Deal at both a programme and project
level. This includes an update on the Red/Amber/Green (RAG) status in regards to
meeting milestone timelines, scope, budget and overall progress. Supporting narrative
is provided where necessary. (Please see Programme and Project Introductions –
Appendix 1). 
MAIN REPORT 
7. The overall status for the programme is still remains as ‘red’. This reflects the continued
challenges project leads are meeting in addressing cost pressures within a fixed
budgets. 
8. In early October senior management from the three Ayrshire Councils held discussions
with the Government in order to consider the challenges the programme and key
projects were and continuing to face. In particular the deliverability of key capital
projects and exploring ways to mitigate the risks and blockages to delivery. Initial
suggestions indicate changes for the programme and key projects. 
KEY POINTS
Programme level 
9. At the programme level the initial outcomes from the October discussions have
identified the potential for the Programme to undergo a Review with a focus upon the
key capital projects which are likely to experience significant change. The AGD
Governance makes reference to the opportunity of undertaking a Checkpoint Review
at any key decision point in the lifecycle of the programme (para 3.5 Governance
Document v15 December 22). To confirm the extract from the Governance states the
following: 
A Checkpoint Review process will be developed and agreed with partners and
governments to examine both the Growth Deal programme and component
projects at key decision points in their lifecycle. It will look ahead to provide
assurance that projects can progress successfully to their next stage. 
10. The Government has advised that the review should entitled as a Programme Review
23/24 which will inform the financial year 24/25. The Review is expected to be
programme wide, with a likely focus on capital projects which are facing substantial
challenges and are estimated to undertake significant change. This means projects
which are currently in delivery, including those with a phased approach, are unlikely to
be affected by the review. For example all revenue projects are now being delivered,
whilst the i3 capital projects are in phased delivery. However where there is a proposal
for a reallocation of funds then a wider range or all projects may be affected. 
11. The approach and timing of the Programme Review is yet to be finalised. Early advice
26

Page 27

from the Government has expressed the need for a formal Letter of Intent to be
prepared by the Partnership seeking the Governments support in undertaking the
review. It is envisaged support from the Government will be subject to gaining
partnership agreement on the way forward for the Deal; continuous dialogue on any
changes proposed; and compliance with AGD Governance. 
12. The PMO will coordinate the Programme Review in consultation with Partners, in line
with the timetable below: 
Undertake Review of the Programme and
Capital Projects 
Nov-Dec 23
Share direction of travel and provisional
proposal with the Government as part of a
series of ‘conversations’ 
Jan 24
Prepare change management papers with a
Programme overview supported by summary of
project review papers
Feb 24
Present papers to the Partnership Board and
Joint Committee
Early 2024
(ready for the
new FY 24/25) 
Reporting Implications 
13. The proposal to undertake a Programme Review will have implications for the activities
captured in the Programme dashboard (Appendix 1 – page 3). In consultation with the
Government it is proposed to delay the preparation of the next Annual Performance
Report. Originally the reporting period was Oct to Sept each year and recently
amended to Oct 22 to Dec 23. This did not align with other key reporting requirements,
so the PMO are in discussions with the Governments to amend further the reporting
cycle so that it aligns with the financial year. This means the next Annual Performance
Report is expected to cover October 2022 – March 2024 (18 months). This change
would potentially allow the outcome of the Programme Review to be reflected in the
Annual Performance Report, updated Financial Plan 24/25 and updated
Implementation Plan 24/25. In addition we have been advised by Government that the
Benefit Realisation Plan can be reviewed once a year not twice as currently done. So
it is proposed that the BRP is updated at the end of March 24, so aligned with the
above mentioned reporting requirements. We are awaiting Government feedback on
the proposal to change the reporting cycle for the Annual Performance Report. 
Programme Financial Update 
14. The latest financial update (October 2023) included in the monthly report provides a
spend projection for the programme and individual projects. 
15. In comparing the now protected spend and drawdown from the grant allocation for this
financial year (2023/24) against the Grant Offer Letter 2023/24, it is noted that there
will be a significant shortfall in the drawdown of funds allocated for this financial year.
This is principally around capital projects such as Spaceport, Commercial Space and
i3 Flexi Space. Indications are that the approval of FBCs for the Spaceport project is
unlikely to be reached by the end of the financial year (Mar 24). An update on this
27

Page 28

project is provided elsewhere on the agenda. Commercial Space is unlikely to drawn
down on its allocation due to delays in raising further private section funding. Finally
progress on developing i3 Flexi Space is expected to slower than originally planned,
hence an expected reduction in drawdown. 
16. A shortfall in spend and drawdown is likely for the Community Wealth Building which
reflects the delay in the project being delivered fully across all three Ayrshire Councils.
A further shortfall is expected for the Ayrshire Skills Investment Fund projects due to
the recent approval of its FBC. The scale of the shortfall however are expected to be
minor when compared to the capital projects mentioned. Please see details below: 
Capital
Projects
Grant Offer Letter
23/24 (£m)
As at P6 return
(Sep 24) (£m)
Differences (£m)
Spaceport 2.855 3.355 +501
Commercial
Space
17.689 1.023 -16.666
I3 Flexi Space 2.339 0.951 -1.389
CoRE 0.300 0.300 0
TOTAL 23.184 5.629 -17.555 
Revenue
Projects
Grant Offer Letter
23/24
As at P6 return
(Sep 24) (£m)
Differences
Working for
Healthy
Economy
0.703 0.703 0
Ayrshire Skills
Investment
Fund
0.850 0.850 0
Community
Wealth
Building 
1.073 1.041 -32
TOTAL 2.626 2.594 -32 
17. As a total the Programme is expected to drawdown £8.223m as opposed to £25.810m,
a potential drop of £17.587m. Further details of the current financial position is set out
in paragraphs 32-35. 
18. The PMO continues to work with the SRO’s and project leads in addressing the
changes in expected spend profile and to ensure future projections are accurate. This
is reflected, as already raised, in the proposal to undertake a programme wide
Checkpoint Review in consultation with the Government and in line with the AGD
Governance. Further details on key projects including those under review are detailed
in paragraphs 20-26. 
19. In addition the PMO are continuing to explore ways to enhance the effective
management of projects within the context of the AGD governance. This includes
28

Page 29

drafting of a series of Supplementary Advice Notes in relation to the change
management process; development and management of Full Business Cases; and the
interpretation of the new Subsidy Control requirements. Delays in preparing these
Notes are due to staff shortages in the PMO (hence RAG status marked Red). Once
drafted the Notes will be shared with the SROs and project leads and in turn be
presented to the AEPB and AEJC. 
Project level 
20. Project leads continue to meeting the challenges of developing and delivering projects.
This is partly reflected in the changes in the spend projections for this financial year
and the meeting of milestones included in the attached summary sheets (e.g. business
case approvals). Below is a summary of the projects that are now ‘red’ in status from
the perspective of budget, scope and overall position. 
Budgetary Issues -
‘Red’ status 
Scope Issues - ‘Red’
status
Overall - ‘Red’ Status
Spaceport Digital Spaceport
Commercial Space  Digital
Digital   
21. Compared to the previous AGD Programme Report to the Board on 7 September 23,
there has been a reduction in the number of projects now rated with a Red RAG status.
Key changes relate to:
 Roads – good progress is being made between SAC/ARA and Transport
Scotland regarding the undertaking of a STAGs report.
 Marine Tourism - further review of the budgetary issues around the project
have been undertaken with clarity provided on the deliverability of the
Cumbrae, Arran and Ardrossan phases.
 ASTAC – progress being made on the development of a partnership
approach with organisations such as Scottish Enterprise (SE) and Ayrshire
College for this project. A further meeting is scheduled with Glasgow
Prestwick Airport in order to confirm siting of the ASTAC proposition. 
22. Project that still retain an  Overall ‘red’ status as follows:
23. Spaceport – extensive discussions between SAC, SG and UKG are ongoing in order
to overcome the complex challenges facing the project. A funding gap still exists and
recent discussions from the Government have highlighted further development of the
business case. An update is provided elsewhere on the agenda.
24. Digital Programme – At the last Board meeting on 7 September 23 an update was
provided on the Digital project and the consideration of options for the future of the
digital programme. The Board supported Option 5b ‘Building Digital Capital’ which
sought the de-scoping of the project and potential reallocation of funds across the Deal.
29

Page 30

The outcome of this meeting is being considered elsewhere on the agenda. 
25. Other highlights include:
 Commercial Space – Delays on the ground works for the Mangata
(Opportunity A) project is still expected. This is due to the need to complete the
Mangata’s series B funding round which is now expected to be by mid-
December 23. Due diligence is continuing to be followed by SE. On site works
is now expected to start in March 2024. 
 Community Wealth Building – The findings of the midterm review of the
project have been completed with a recommendation of extending the project
for another year. Details of this proposal will be shared with the Government
and then presented to the Board and Joint Committee as part of change
management. 
 AEP & AMIC – Change management papers are being prepared in line with
discussions undertaken with the Government. Once received they will be
presented to the Board and Joint Committee as part of the change management
process.
 Ayrshire Skills Investment Fund – Following the approval of the FBC in
August 23, a Delivery Model has been agreed with tenders now out for potential
operators to deliver the fund. 
26. Projects in delivery are; Community Wealth Building, Working for Healthy Economy,
Commercial Space, i3 Flexi Space (Phase 1) and i3 DPMC (Phase 1), with Ayrshire
Skills Investment Fund to be in delivery in the coming weeks.
COMMUNICATION UPDATE
27. In line with the AGD Communication Action Plan please find attached (in Appendix 2)
a copy of communication and engagement activity for all projects in the programme.
This includes Q2 Review of past activities and Q3 planned activities. 
IMPLICATIONS 
28. Eight implications have been considered in the preparation of this report. 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance/Legal Yes  Para 22
3. Human Resources  No 
4. Equality and Fairer Scotland Duty Yes  Para 23
5. Financial  Yes  Para 24-27
6. Risk  Yes  Para 28-29
7. Community Wealth Building   No 
8. Net Zero   No 
30

Page 31

LEGAL IMPLICAITONS 
29. The legal implications arising from this report are covered through the Agreement
between Ayrshire’s councils and the Governance Document which was revised and
approved at the Joint Committee meeting on 8 December 2022. 
EQUALITY IMPACT ASSESSMENT 
30. There is no equalities impact relating to this report. Inclusion is a key driver for the
AGD. Project Leads will be required to complete an Equality Impact Assessment for
their project and append to the associated business case. Project Leads have received
Equality Impact Assessment training organised by the Scottish Government. Project
Leads are being encouraged by the PMO to link up as soon as possible with their
Equalities Officer within their authority who will be able to assist with this matter. 
FINANCIAL IMPLICATIONS 
31. The financial implications arising from this report are covered through the Financial
Plan approved at the Joint Committee meeting on 26 June 2023. The overall
cumulative total of Grant claimed for the Deal to date is £12.025m. 
32. The ninth claim since Deal signing (in the financial year 23/24 Qtr2) has been made to
the Scottish Government for c.£1.145m which is made up of expenditure associated
with the Community Wealth Building, Working for a Healthy Economy, Commercial
Space and i3 flexible Space. All claims made to date have been processed by
Government and payment received. The financial position statement for September
2023 within the progress report does not include the Q2 claim due to date report was
ran. (Appendix 1). 
33. At the time of preparing this paper the forecast drawdown reported to Scottish
Government for P7 2023/24 amounts to £8.223m, an anticipated decrease of £17.587m
for the year compared to a budget of £25.810 million. Projects are, however,
demonstrating commitment and incurring costs developing projects, with evidence of
£10.967m having been spent by councils to date ahead of project business cases being
approved. Once approval of the relevant business cases has been received from
government and the Joint Committee, the relevant costs will be claimed back from
government. 
34. Please note all capital and revenue project costs are being monitored and discussed
with regional partners, UK and Scottish governments. 
RISK IMPLICATIONS 
35. Strategic and operational risk registers continue to be developed, reviewed and
updated for the AGD Programme. This is being undertaken by the PMO with the
support of EAC audit. The Programme Risk Register has been updated in accordance
with the commitment to be reviewed every quarter as approved by the AEJC on 26
31

Page 32

June 2023. Details of the latest update is considered elsewhere on the agenda. 
36. In addition the risk registers for each project which are updated on a monthly basis
and reflected in the attached summary update (Please see Appendix 1). 
APPENDICES 
Appendix 1: Ayrshire Growth Deal Update of Programme and Projects
Appendix 2: Quarterly Communications Report as October 2023 
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and Ayrshire’s
Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and Ayrshire’s
Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal –Strategic Manager 
graham.saunders@east-ayrshire.gov.uk 
Implementation Officer: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager 
graham.saunders@east-ayrshire.gov.uk 
32

Page 33

Appendix 1 
Ayrshire Growth Deal Update of Programme and Projects 
33

Page 34

AYRSHIRE GROWTH DEAL
Monthly Report - 30 October 2023
34

Page 35

Programme Updates - Guidance (Milestones) 
RAG Status Programme Milestone Timeline
Status Overall Action Required 
Red
Delay to delivery timeline of key
milestone having a negative impact
on programme 
One or more milestones are RED
Immediate action required by senior
management and relevant Boards as
appropriate to address issues 
Amber
Milestone slipping against planned
date but not expected to impact
delivery of the programme 
No milestones are highlighted RED but at
least one is AMBER 
Management action is in place by PMO and/or
senior management to address issues 
Green On track to deliver milestone on time
or early  All milestones are GREEN  No management action required 
Complete  Milestone delivered  n /a  No management action required
Status against milestone timeline set out in Implementation Plan
Milestones – current financial year and next financial year
Programme Updates - Guidance (Risks)
This table illustrates the conversion of AGD RAG Status to Scottish Government RAG Status 
Source GREEN AMBER RED N/A
Ayrshire Growth Deal
RAG Guidance Note
with an AGD risk register score of
between 0-3
with an AGD risk register score of between
4-9
with an AGD risk register score of between 10-
14
with an AGD risk register score
of between 15-25  N/A
Source GREEN AMBER/GREEN AMBER/RED RED N/A 
Scottish Government
Guidance
Successful delivery
appears highly likely with
regard to time, cost and
quality and there are no
major outstanding issues
that at this stage appear to
significantly threaten
progress 
Successful delivery appears
probable however attention will
be needed in certain areas to
ensure risks do not develop into
major issues that will threaten
delivery 
Successful delivery appears
possible, but issues already exist
that require serious
attention. These appear resolvable
at this stage, but further action is
required
Successful delivery is in
serious doubt with
major risks or issues
apparent in a number of
key areas. Urgent
action is needed to
ensure these are
addressed 
Not listed
on
previous
Quarter
35

Page 36

Programme Dashboard – 30 October 2023                   Financial Summary
Programme Milestones                                                       Programme Top Risks
OverallStatus
Last Period
OverallStatus
This Period TotalAGD
Grant £'000
AGD Grant
Drawdown to Date
£'000
%age of total AGD
Grant
2023/24AGD
Grant Allocation
£'000
2023/24Grant
Drawdown
£'000
251,500 10,880 4.33% 25,810 295
Risk Likelihod Impact AGDStatus SGStatus Mitigating Action - UPDATE TO ALIGN WITH IMPLEMENTATION PLAN
Failure to achieve AGD
programme objectives
within agreed budget
4 4 16 16
The Regional Economic Joint Committee, Regional Economic Partnership, AGD Steering Group in place to monitor progress and to address any weaknesses or
issues that could impact on overall delivery. PMO developing monitoring and evaluation processes to ensure overall objectives are captured and any project
failing to achieve and contribute to these is flagged and issues addressed as quickly as possible. This includes responding to increasing costs of general capital
works within the context of the original funding made available by the Government in 2019. Leading to potential to review risks where evidence suggests
insufficient funding to undertake and complete projects in line with expected outcomes. PMO are working with Partners in undertaking a Programme Review
in line with the AGD Governance. PMO undertake ongoing environmental analysis to ensure programme objectives are relevant/valid as well as maximised
where relevant and new benefits identified when materialising. Internal governance include regular reviews undertaken by PMO with input from SROs, Project
Leads and Chief Executives to ensure AGD programme objective are met.
Failure to provide
accurate projections
for programme spend
4 4 16 16
Issues will be escalated to CEOs, Regional Economic Partnership and Regional Economic Joint Committee as appropriate. PMO working with Partners in
undertaking a Programme Review in order to clarify accurate projections for project and programme spend and delivery. The Implementation Plan and
Financial Plan have been updated to take account of the compressed funding. Project Leads have sought to address delays in gaining approved FBCs, by
undertaking reviews of projects to fit existing budgets, which are shared with Finance Directors, the government and wider partners. Revised project
mitigation measures seek to demonstrate how inflationary pressures will be managed. Business Case process monitored to ensure streamlined pathway to
approval enabling projects to achieve FBC as quickly as possible to reach project delivery and clarity on expected spend. PMO will regularly review, challenge
and agree financial profiling/phasing with Project Leads, SROs and Finance Directors and ensure drawdown projections align with delivery timescales.
OBCs/FBCs include an optimism bias factor as per TreasuryGreen Book and AGD Governance document. Inflationary factor addressed through project reviews
e.g. re-scoping, phasing and reviewing benefits
Failure to drawdown
full AGD funding
4 4 16 16
PMO will regularly review, challenge and agree financial profiling/phasing with Project Leads, SROs and Finance Directors and ensure drawdown projections
align with delivery timescales. This includes PMO working with Project Leads, SRO’s and S95’s to ensure projects can be realised and help with change
processes where necessary; and undertaking effective communication with Governments to ensure projects can be realised. PMO working with Partners in
undertaking a Programme Review in order to clarify accurate projections for project and programme drawdown on AGD funding. Achieve business case
approval in line with latest Deal Implementation Plan, and AGD Governance document and, Finance guidance. Annual review of Financial Plan and
Implementation Plan. The Scottish Government’s financial reporting requirements will be implemented. Pivot projects proactively where possible in line with
need and opportunity. Internal procedures, financial controls and processes in place to mitigate this risk
Delays in development
and approval of
business cases
4 4
Undertake focused engagement with SG and UKG in order to help ensure SBC, OBC and/or FBC comply with the Treasury Green Book and gain approval pin line
with AGD governance. PMO working closely with Project Leads and Policy Leads within UK and Scottish Governments to support business case development
and approval to an agreed timeline. This includes exploring a streamlined change process (pre-FBC) particularly where budget constraints are sole driver of
change. In addition as part of a Programme Review, reschedule business case timescale for development and delivery. Project Leads have received Green
Bookbusiness case training. Project Leads’ toolkit in place. Other partners assisting in developing business cases where capacity is low
Lack of resources in
PMO
4 4
A permanent PMO structure is in place but not all posts are currently filled, with recruitment now underway to start completing the team. The PMO is being
supported by colleagues in each of the Councils in a number of work streams. PMO undertaking a review of capacity and skill sets in response to the changing
requirements of the Office
Potential impact of
international events
upon cost of living
crisis and economic
prosperityofAyrshire
4 4
Regular engagement with Project Leads to highlight any risks well in advance, so that the PMO can raise with government, Regional Economic Partnership and
Regional Economic Joint Committee as appropriate. PMO working with Partners in undertaking a programme midterm Checkpoint Review in response to the
impact of costs pressures upon the delivery of the Programme. Regular review via monthly reports of outputs and timelines for business cases at every stage
of development in the light of external events. Continued monitoring of external environment and government relations. Regional Economic Strategy
approved in early 2023 and be supported by an emerging action plan. Regional Economic Partnership will provide voice for Ayrshire to press the case for
government intervention investment. Incentives and other forms of assistance to complement the AGD and stimulate greater economic activity. Current
change management process to be reviewed with both governments and partners. Regional Skills Investment Plan developed, with a focus on its
implementation via Ayrshire Skills Group. Robust data analysis shared amongst key partners and stakeholders to reach common understanding of local
economic conditions, leading to early identification of real threats and opportunities -achieving consensus with partners and stakeholders on strategic
objectives for inclusive and sustainable economic growth, with effective action planning and monitoring.
PMO co-ordinated evidence across Deals and submitted collective case via the Implementation Plan updateto both governments setting out impact of
increased costs or reduced the scope/outputs and time delivery if costs not met. PMO developing a baseline approach to FBC which will be shared with both
governments and partners.
Programme & Upcoming
Programme Milestones
Target Date RAG
Grant Offer Letter for 2023/24
received and agreed
30-Jun-23 Complete
2023 Annual Review of Deal
documentation approved
(Implementation Plan, Financial
Plan, Governance Document,
CommunicationsProtocol)
30-Jun-23 Complete
Review overarching Monitoring &
Evaluation Framework
30-Jul-23
Red
Update Benefits Realisation Plan
and progress on performance
(everyMarch)
31-Mar-24 Green
Reviewand update Change
Management Process -draft and
approveSupplementary Advice
Note 1
30-Jul-23 red
Reviewand update Business Case
process with a focus on Full
business Case requirements -draft
and approve Supplementary
Advice Note 2
31-Aug-23 red
Reviewand update Subsidy Control
requirements for the AGD - draft
and approve Supplementary Advice
Note 3
31-Aug-23 red
Reviewand update AGD web site
programme and project details 30-Sep-23 Amber
Key project interdependencies
articulated
31-Mar-24
Green
Annual Conversation (2022/23) 31-Jan-24 Green
Annual Performance Report
approved and published (2022/23)
28-Feb-24 Green
Submission ofstatement of
compliance with conditions of
grant(2023/24)
30-Apr-24 Green
Submission ofstatement of
compliance with conditions of
grant(2023/24)
30-Apr-24 Green
36

Page 37

AGD PROJECTS - COMPLETE  Total Project Budget
£'000 
Government Grant
Funding £'000 
Government Grant
Claimed to date £'000  
Total Expenditure
17/18 to 20/21 £'000 
FINANCIAL POSITION STATEMENT
FINANCE YEAR 2023/24
QUARTER 2
HALO 9,000 7,000 7,000 10,524 MONTH Sep-23
9,000 7,000 7,000 10,524 
Government Grant 2023/24 £'000 
AGD PROJECTS - EXPECTED FBC/APPROVED FBC IN 2023/24 ~ GRANT OFFER
LETTER 
Total Project Budget
£'000 
Government Grant
Funding £'000 
Government Grant
Claimed to date £'000  
Total Expenditure
17/18 to 22/23 £'000
Total Expenditure
23/24 YTD
£'000  
Grant Allocation
TBC 
Grant Claimed
Q1 
Grant Claimed
Q2 
Grant Claimed
Q3 
Grant Claimed
Q4 
Total Grant
Claimed YTD 
Remainig Grant Available
to Claim in year
Spaceport Infrastructure 23,000 23,000 0 2,856 329 2,855 0 0 0 0 0 2,855
Commercial Space - Prestwick - Industrial & Hangar 29,000 22,000 825 1,160 730 17,690 0 0 0 0 0 17,690
i3 Flexible Business Space 15,000 11,000 307 545 0 2,339 65 0 0 0 65 2,274
Community Renewable Energy Project (CoRE) 24,500 17,000 0 976 74 300 0 0 0 0 0 300
Working for a Healthy Economy 5,000 5,000 1,118 1,118 293 703 117 0 0 0 117 586
Ayrshire Skills Investment Fund 3,500 3,500 0 0 0 850 0 0 0 0 0 850
Community Wealth Building Fund 3,000 3,000 1,335 1,335 343 1,073 113 0 0 0 113 960 
103,000 84,500 3,584 7,989 1,769 25,810 295 0 0 0 295 25,515 
AGD PROJECTS - FUTURE Total Project Budget
£'000
Government Grant
Funding £'000
Government Grant
Claimed to date £'000 
Total Expenditure
17/18 to 22/23 £'000
Total Expenditure
23/24 YTD
£'000 
Aerospace & Space Technology Application Centre (ASTAC) 11,000 5,000 0 728 0
Prestwick Infrastructure - Roads 17,000 12,000 0 472 20
Ayrshire Engineering Park (Moorfield) 16,000 12,000 0 826 43
Ayrshire Manufacturing Investment Corridor (AMIC) 23,500 23,500 0 390 28
i3 Digital Processing Manufacturing Centre 6,000 5,000 0 245 19
Hunterston Strategic Development Area 18,000 18,000 0 192 6
International Marine Science & Environmental Centre (IMSE) 10,500 6,500 0 134 8
The Great Harbour, Irvine Harbourside & Ardeer 14,000 9,000 0 460 109 
Marine Tourism 9,500 9,500 0 412 30
Digital Projects (name TBC) 14,000 14,000 0 76 0 
139,500 114,500 0 3,934 263
AGD TOTAL 251,500 206,000 10,584  22,447 2,032        
37

Page 38

Project Updates - Guidance 
Project Stages Stage Definition Project Stages Stage Definition 
Define - SBC  Establishing the strategic context for the spending proposal  Implement  Business case has been approved by Joint Committee, and is being implemented 
Define - OBC  Establishing the preferred option  Deliver  Project is in place and monitoring and evaluation is in framework to assess if it is achieving its objectives 
Define - FBC  OBC approved by government, securing delivery plans and finalising detailed costing  Legacy
Project has resulted in mainstreaming or improvements to business as usual (impact) that is generated beyond
the funded period
RAG Status Programme Milestone Timeline Status Project Scope Status Project Budget Status Overall Action Required 
Red  Delay to delivery timeline of key milestone having a
negative impact on project completion date 
Significant change in scope expected, with no change
request in process 
There are projected or actual adverse variances with
recovery plan to be established 
One or more milestone, scope or budget indicators are
RED 
Immediate action required by senior management and
relevant Boards as appropriate to address issues 
Amber
Key milestone missed or projected to miss against
planned date but not expected to negatively impact the
original project completion date
Likely to be minor changes in scope within agreed
business case OR scope is still developing OR significant
change request not yet approved 
There are projected or actual adverse variances,
however a recovery plan is in place 
No milestone, scope or budget indicators are RED but at
least one is AMBER 
Management action is in place by PMO and/or senior
management to address issues 
Green  On track to deliver milestone on time or early  Scope has been set and on plan with agreed business
case AND/OR formal change request approved  There are no actual or projected variances  All milestone, scope and budget indicators are GREEN  No management action required 
Complete  Milestone delivered  Project complete and all items in scope delivered  Financial transactions relating to project have been
settled 
If all the milestone, cost, scope and benefits realisation
indicators are complete  No management action required 
Future  N/A  N/A  Business Case more than one year away from
submission  n /a  No management action required 
Milestones – current financial year and next financial
year PMO = Programme Management Office SBC = Strategic Business Case OBC = Outline Business Case FBC = Full Business Case 
Project Updates - Guidance (Risks)
This table illustrates the conversion of AGD RAG Status to Scottish Government RAG Status 
Source GREEN AMBER RED N/A
Ayrshire Growth
Deal RAG
Guidance Note  with an AGD risk register score of between 0-3  with an AGD risk register score of between 4-9  with an AGD risk register score of between 10-14  with an AGD risk register score of between 15-25  N/A 
GREEN AMBER/GREEN AMBER/RED RED N/A
Scottish
Government
Guidance
Successful delivery appears highly likely with
regard to time, cost and quality and there are no
major outstanding issues that at this stage appear
to significantly threaten progress
Successful delivery appears probable however
attention will be needed in certain areas to ensure
risks do not develop into major issues that will
threaten delivery
Successful delivery appears possible, but issues
already exist that require serious attention. These
appear resolvable at this stage, but further action is
required
Successful delivery is in serious doubt with major
risks or issues apparent in a number of key areas.
Urgent action is needed to ensure these are
addressed 
Not listed in previous Quarter
38

Page 39

Programme Summary – 30 October 2023 
Project Name  OBC Date  OBC RAG  FBC Date  FBC RAG
Project Scope
Status
Project Budget
Status
Project Overall
Status
Aerospace and Space Technology Application Centre 01/12/2023 Green 02/08/2024 Green Green Amber Amber
Spaceport Infrastructure 30/10/2021 Complete 30/09/2023 Red Green Red Red
Prestwick Commercial Space 30/08/2021 Complete 08/09/2022 Complete Green Red Amber
Prestwick Infrastructure Roads 28/02/2024 Green 31/10/2024 Green Green Amber Amber
Ayrshire Engineering Park (Moorfield) 30/09/2023 Amber 10/06/2024 Green Amber Amber Amber
Ayrshire Manufacturing Investment Corridor 30/10/2023 Amber 10/06/2024 Green Green Amber Amber
i3 Flexible Business Space 30/05/2021 Complete 30/09/2022 Complete Green Amber Amber
i3 Digital Processing Manufacturing Centre 31/05/2022 Complete 30/06/2022 Complete Green Amber Amber
HALO 31/05/2022 Complete 30/06/2022 Complete Complete Complete Complete
Community Renewable Energy 31/05/2022 Complete 20/12/2023 Green Amber Amber Amber
Hunterston 30/06/2024 Green 28/02/2026 Green Amber Green Amber
International Marine Science & Environmental Centre 30/06/2024 Green 28/02/2026 Green Amber Amber Amber
Marine Tourism 31/12/2023 Green 30/03/2026 Green Amber Amber Amber
Great Harbour 25/06/2021 Complete 31/03/2024 Green Amber Amber Green
Digital Infrastructure & Subsea Cable (TBC) tbc under rescope tbc under rescope red Red Red
Ayrshire Skills Investment Fund 30/04/2023 Complete 30/06/2023 Complete Amber Green Amber
Working for Healthy Economy 19/02/2021 Complete 22/02/2021 Complete Green Green Green
Community Wealth Building 12/02/2021 Complete 22/02/2021 Complete Green Green Green
39

Page 40

Project Updates – Space and Aerospace Programme 30 October 2023 
Project Name Project Lead Senior Responsible Officer
Aerospace & Space Technology Application Centre George Hunter 
Louise Reid Spaceport Infrastructure Derek Yuille
Commercial Space Derek Yuille
Prestwick Infrastructure Roads (Phase 1) Kevin Braidwood
40

Page 41

Aerospace and Space Technology Application Centre Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: George Hunter
Meeting with Scottish Enterprise head of place and team took place to agree/establish their wider role and responsibilities in supporting the project. Follow-up meeting took place with GPA to review the viable properties within the airport estate and establish the needs of SAC/Ayrshire
college for the facility. SAC presented the case for the area surrounding hanger 457 and reasoning around this. Also discussed were possible alternative sites, each located in close proximity to the terminal building with easy road/rail access links. Next steps include a further meeting
with GPA/AC/SAC with the aim of confirming site of ASTAC proposition and establish needs of all parties concerned regarding land/lease term/legals. Some milestones moved from green to amber.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 01/12/2023 Green AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC 02/08/2024 Green AGD/O/2 - Construction jobs created tbc tbc
Phases Target date  AGD/O/9 - Business Space Created tbc tbc
Phases Target date  AGD/O/13 - Visitors tbc tbc
Phases Target date  AGD/O/14 - SME's Supported tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC Submitted to Government 01/12/2023 Amber Completion of Phase 2 30/10/2029 Amber
Develop local partnership delivery model 01/12/2023 Green Final financial drawdown 31/03/2030 Amber
Complete final project design and procurement documentation 02/08/2024 Amber   
FBC approved by Joint Committee 02/08/2024 Amber   
Hand-over (Phase 1) to operational organisation 23/10/2026 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
A Viable and Sustainable Operational Funding (OPEX) model not achieved  5  4  20  
• Review existing models (UK- HIE/Perth College)
• Consultation Scottish Funding Council on academic funding support (OPEX)
• Consultation and developing model with Ayrshire College  20/12/2023 
Site for the ASTAC Facility not secured within GPA Estate offering airside
access/scale/offside access on acceptable terms  5  4  20  
• Secure early dialogue with Glasgow Prestwick Airport. Sidentify ASTAC spatial needs. Review options.
Develop a conceptual Plan for ASTAC campus 
20/12/2023 
ASTAC capital costs (CAPEX) exceed ASTAC approved budgets and other funding not
available  4  4  16  
• Complete early assessment of CAPEX costs and Prestwick build costs. Ensure adequate OB
provision. Make allowances for fees/legals inflation 
20/12/2023 
Securing aggreements and approvals requires additional time and programme delayed  4  4  16  
• Develop Programme with Steering Group. Align SAC and AC resources. Secure early SAC agreements and
internal reporting 
20/12/2023
Economic and social benefits and a positive BCR not delivered 
4 3  12    12
• OBC to include full EIA to Green Book/PMO template. Develop the Monitoring and Evaluation Framework.
• Complete in the OBC the Benefits Realisation Plan 
20/12/2023
41

Page 42

Spaceport Infrastructure Oct ProjectOverallStatus
2023 Red
Project Update
Project Scope Status Green Project Budget Status Red
Monthly update - provide narrative Project Lead: Derek Yuille
There is a significant funding gap and additional funds are required if the project is to proceed. Discussions are ongoing with SE/SG/UKG to identify where funding can be sourced to meet shortfall, including proposals for SE to acquire land and reapportioning of digital funds. Recent
Government advice has required the approved OBC to be reviewed in light of the likely changes to the project, with a revised OBC and FBC being scheduled for Spring/Summer 2024.
Project Targets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/10/2021 Complete AGD/O/1-New JobsCreated (Direct andIndirect) 10 tbc
FBC 30/09/2023 Red AGD/O/2-ConstrucitonJobsCreated 135 tbc
Phases Target date AGD/O/9-Business SpaceCreated 3200sqm tbc
Phases Target date Target tbc
Phases Target date Target tbc
Progress Update(top priority milestones aspercurrent Implementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
RIBA Stage 3 30/04/2023 Red Airspacechangeagreed 31/03/2024 Red
HeadsofTermsagreedtopurchaseland 20/06/2023 Red LSO/LSP/Range Licence requirements for first launch 30/11/2024 Red
FBCapprovedbyJointCommittee 30/09/2023 Red Spaceport infrastructure complete 30/11/2024 Red
Construction Start 01/11/2023 Red FirstCommercialLaunch 31/01/2025 Red
Safety Case 31/03/2024 Red Full project completed/final drawdown 31/03/2026 Red
ProjectRisks(top5risksandtheirstatuswillbeincludedinthemonthlyreport) TargetClosure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
FailuretoagreeoperatingarrangementforSpaceport 5 5 25
AvisonYounghaveproposedSpaceportleasingandoperatingproposalsforSACandthe Spaceport Launch
Service Operator Glasgow Prestwick Airport, however an agreement has yet to be reached that complies
with AGD capital funding requirements, local authority operating legislation and that mitigates any
financial and legal risks the Council may be exposed to where the Council has ongoing responsibility for
the Spaceportasset.
31/12/2023
FailuretoobtainFBCapproval 5 5 25
A Full Business Case for the Spaceport requires the following to be in place: i) an agreementorHeadsof
Termsoverthelandwithconfirmedbudgetsource;ii)acosted deliverableinfrastructureschemewith
budgetinplaceandiii)anagreementorHeads ofTermsontheoperating arrangementfortheasset
betweentheproposedownerof the asset, and the Launch Service Operator (LSO) Glasgow Prestwick
Operator
31/12/2023
ThemodelSEusetoacquirelandforspaceportmayrequirealeasearrangementwith SAC.
5 5 25
Thelandacquisition/leasepaymentsarenotfundedbyAGDandtheCouncilarenotina position to enter
any borrowing arrangements to fund this 31/12/2023
FailuretoagreeownershipofthenewSpaceportinfrastructure(eg.LVIF,apron,access road,
control point) 5 5 25
Professional advice being sought by SAC on the legilities of SAC having any ownership rightstothe
Spaceport.Advicepreviouslyconfirmedoperatingarrangementscenarios. 31/10/2023
Projectcostscannotbemet by the existing AGDprojectbudget
5 5 25
Digitalre-scopingexerciseandproposalthatbuildshortfallissupportedbydigitalfunds. SE will acquire
the land. 31/10/2023
Landownermay walkaway duetolack ofprogress 4 5 20 SEtotakeforwarddiscussionswithlandowner
04/01/2024
Risktheeconomicimpactofthespaceportscoreslowgiventhatthecostshave significantly
increased but the net jobs has not changed 4 5 20 SEtocommissionfurtherworkonEIA 04/01/2024
SErequiringSACtoenterintolegallybindingagreementthatlinksdeliveryofanew access road
from Sandyford Toll to SE’s purchase of the land 4 5 20
Road deliverability uncertain until STAG complete.
04/01/2024
42

Page 43

Prestwick Commercial Space Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Red
Monthly update - provide narrative Project Lead: Derek Yuille
Site preparatory works/archaeology are now complete on Opp A (Mangata). Construction costs have not changed since last reported. The next significant milestone date is the completion of Mangata’s Series B funding round, where they are targeting c$100m investment. This had
been expected to conclude in July, but the completion date has been pushed out and the anticipated completion date is now December. SE require security for the value of the cost overrun before entering the Main Delivery Agreement (construction contract), and plan to carry
out updated due diligence prior to entering the Main Delivery Agreement. Therefore the delay to the funding and the design finalisations has a knock-on effect on entering the main build contract (expected Q4 23/24), and therefore the construction dates (Q1 24/25). Completion
now Q2 2026.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/08/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 570 tbc
FBC 08/09/2022 Complete AGD/O/2 - Construciton Jobs Created 150 tbc 
AGD/O/9 - Business Space Created 13900 sqm tbc
AGD/O/16 - Leverage (incl. LA, HE/FE, Private Sector and any other levereage) £55,000,000 tbc 
Target tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Planning permission 31/05/2023 Complete   
Handover 31/12/2025 Green   
Final financial drawdown 31/03/2030 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Failure of Mangata to resource additional funding  4  4  16  
• Closing Series B continues to prove challenging for Mangata, with timing now forecast
for early December (previously end September). However, Mangata have now signed a letter of intent
with a lead investor.
• Mangata are funding the business through Convertible Loan Notes until Series B close. This requires
them to continue to raise cash as current funding forecast lasts until October and includes the R&D
Grant payment. Mangata's forecasts show that they then anticipate some funding in October 2023,
before conclusion of Series B, expected
December. 
30/11/2023
Delays in provision of utilities 
2 2  4   4
• Site energy strategy to be put in place and early engagement in place across utilities companies
30/06/2024
Delays to design and build procurement processes
• Challenges to the process
• Availability of contractors  2  2  4  4
• External expert advisers have been procured to support the project team and will adhere to the
procurement policies of South Ayrshire Council
• Timescales have been set to ensure that there is a sufficient pool of suppliers to undertake the
activities and are interested in providing a competitive tender 
31/12/2023
Economic downturn
2 2 4  4
• Early engagement with market indicates that this investment is an important part of recovery and
engagement with market will be maintained 31/12/2024
43

Page 44

Prestwick InfrastructureRoads Oct Project OverallStatus
2023 Amber
ProjectUpdate
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kevin Braidwood
Progress withtheSTAGis ongoing fortheAyrshireGrowthDeal RoadsEnabling project. Following approval todiscard thehistory phasedroads enablingprojectsa furtherreport has beenprepared andlodgedforpresentationto Cabinet detailingthe work undertaken to
date withthe next steps required to minimise delay inthe programme and maintain momentum onthe project.
ProjectTargets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 28/02/2024 Green AGD/O/2- ConstructionJobs Created 40 tbc
FBC 31/10/2024 Green AGD/O/7- newroadwaycreated 2 km tbc
Phases Target date AGD/O/7-roadwayupgraded 1 km tbc
Phases Target date AGD/O/7- newroundabouts 1 tbc
Phases Target date AGD/O/11-upgradedroundabouts 3 tbc
ProgressUpdate(top priority milestonesaspercurrentImplementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone status
RoadsEnabling STAGAppraisal-Release offundsfromTransport Scotland 01/03/2024 Green Procurement ofcontractor andcommencementof works – Monkton 01/08/2025 Green
Planningandregulatoryconsentachieved– Spaceport(StQuivox) 30/09/2023 Red Completionof works – Spaceport(StQuivox) 31/12/2024 Red
Land assembly, site preparation, contract documentation – Spaceport (St Quivox) 31/12/2023 Red Completion of works – Enabling transport works 01/03/2026 Green
Planningandregulatoryconsentachieved – Monkton 31/12/2023 Red Planningandregulatoryconsentachieved-Gannet Link tbc Red
RoadsEnablingOBC- TS & Council Approval 01/08/2024 Green Land assembly, site preparation, contract documentation - Gannet Link tbc Red
Land assembly, site preparation, contract documentation – Monkton 31/03/2024 Red Procurement ofcontractor andcommencementof works –Gannet Link tbc Red
Procurement ofcontractor andcommencement ofworks – Spaceport(StQuivox) 30/04/2024 Red Completionof works- GannetLink tbc Red
RoadsEnabling FBC- TS & Council Approval 01/03/2025 Green Final financial drawdown tbc Green
ProjectRisks(top 5risksand their statuswillbe included in the monthly report) TargetClosure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Delays inreleaseof enabling infrastructurefunding fromScottishGovernment via Transport
Scotland 4 4 16 Commissioning of Enabling Roads STAG and OBC
• Effective scoping and ongoing liaison with Transport Scotland
STAG Mar2024
OBC Nov2024
Additional risk that any spaceport access road, delivered outside the STAG process is not only
not eligibleforfunding viathe enabling infrastructurefunds but alsostarilises available land for
the Growth Deal if access cannot be gained due to the Spaceport project working in isolation 4 4 16
Continues liaison with Spaceport and requirement for this project to meet requirements of STAG process or
withdraw from the AGD enabling works fund. Requirement addedforSpaceport project to ensureongoing accessto
thesouthern AGD lands for future development 30/09/2024
Cost overruns 4 2 8 8
Project deliverywillbeledbyaqualifiedproject managerfollowing established process for road construction
Costs will be monitored against progress and reported to the programme board Anyadditionalcosts willbe
absorbedwherepossibleby projectredesignand/or re- prioritisation 31/12/2027
Planning Approval - Dealys in planning due to capacity constraints, Objections to proposed
route,Planning programmeandinterrelation betweenoverallSpaceport development and
enabling roads intrastructure
3 2 6 6
Programmerecognised byPlanning Departmentasa majorproject andgivenpriority
• PrestwickCampus Masterplanincorporatedindevelopment ofLDP2 viamainissues report and subsequent
consultation with residents and other parties
• On-going community consultation
• Planning Strategytobedevelopedtoensureplanning applicationsare interconnected
31/12/2024
Land assemblydelays -Monkton& Spaceport 3 2 6 6 Earlycommencement ofLandOwnernegotiations
31/12/2024
44

Page 45

Project Updates – Economic Infrastructure Programme 30 September 23 
Project Name Project Lead Senior Responsible Officer
Ayrshire Engineering Park (Moorfield) Fiona Paterson David McDowall Ayrshire Manufacturing Investment Corridor (AMIC) Gillian Morton
i3 Flexible Business Space Marnie Ritchie Neale McIlvanney i3 Digital Processing Manufacturing Centre (DPMC) Marnie Ritchie
HALO Gary Deans David McDowall
45

Page 46

AyrshireEngineering Park(Moorfield) Oct Project OverallStatus
2023 Amber
ProjectUpdate
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Fiona Paterson
1. Three public consultations forthe Ayrshire Innovation Park pre planning application have now taken place. Feedback has been very positive inrelation to both the Ayrshire Manufacturing Investment Corridor Project andtheAyrshire Engineering Park. Feedbackfrom the
public consultations held will be included in the next iteration of the OBC.
2. Theproject team are currently preparing changerequest documentation inlinewithdiscussions heldwithGovernment overthe past few weeks. A revised target date fortheOBCsubmission forAEP &AMI is under consideration andwillbe providedASAP.
ProjectTargets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/09/2023 Amber AGD/O/1- New Jobs Created(Direct andIndirect) 203 tbc
FBC 10/06/2024 Green AGD/O/2- ConstrucitonJobs Created 88 tbc
Phases Target date AGD/O/9-Business SpaceCreated 7250sqm tbc
Phases Target date AGD/O/10-Reducedvacant &derelictland 18.3ha tbc
Phases Target date AGD/OT/7- Additional Investment(incl Foreign DirectInvestment) tbc tbc
ProgressUpdate(top priority milestonesaspercurrentImplementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
OBC Approved byGovernment 30/09/2023 Amber FBC approved byJointCommittee 10/06/2024 Green
TenderforBuilding Services &Civil and Structural Engineers Services 02/05/2023 Green Commencement of infrastructure works 24/06/2024 Green
Design period inl community consultation & Environmen Impact Analysis commences 10/07/2023 Green Construction of terraced units and 500sqm unit 21/04/2025 Green
Planning permission secured 30/03/2024 Green Initial business premises operational 19/01/2026 Green
FBC endorsed byGovernment 20/05/2024 Green First tenants movein 01/02/2026 Green
ProjectRisks(top 5risksand their statuswillbe included in the monthly report) TargetClosure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
FailuretoContributetoAGD programme objectives
3 3 9 9
• Project will be managed by EAC in line with PRINCE 2 principles – any issues will be monitored, and
remedial actionagreed toensure delivery remains inline withtheOBC projections.
• AGD Steering Group and other governance arrangements are in place to monitor progress andto
address any weaknesses or issues that couldimpact on overalldelivery and project lead will be required to
provide regular project updates
31/3/2027
Failure to provide accurate projections for project spend
3 3 9 9
• Ensuresufficient optimism bias built intocosting oftheproject
• Inflationary factor included in cost estimations
• Project willbe managed byproject team inline with PRINCE2 principles –anyissues will be monitored,
and remedial action agreedto ensure delivery remains inline with the BC projections
• Issues tobeescalated PMO infirst instancetoagree remedial actions as appropriate
• Challenge panelled byPMO exists toreview&scrutinisespendprofiles
31/3/2027
Delays inapproval of business case
3 3 9 9
• Project leadwill work closely withPMO and policy leads withinUKG andSG to support business
case development and approval to an agreed timeline 30/12/2025
Failuretodelivercommunity benefits from theproject
3 2 6 6
• Procurement colleagues willsupport thetender process toensurethat community benefits are a key
aspect of the ITT and are in line with agreed AGD procurement principles 31/03/2027
NegativePublicity
3 2 6 6
• A communications protocolhas beenagreed with bothgovernments andwillsupport shared
communications designed to build stakeholder confidence
• All project specificpublicity willbe dealt within a coordinated fashion,sensitivity and empathy to
business climates at the time of publications will be carefully monitored
31/3/2027
46

Page 47

Ayrshire Manufacturing Investment Corridor Oct Project OverallStatus
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Gillian Morton
1. ThreepublicconsultationsfortheAyrshireInnovationParkpreplanningapplicationhavenowtakenplace.FeedbackhasbeenverypositiveinrelationtoboththeAyrshireManufacturingInvestment CorridorProjectandtheAyrshireEngineeringPark.Feedbackfromthe public
consultations held will be included in the next iteration of the OBC.
2. Theproject team arecurrentlypreparing change reuquests documentation in line with thediscussions held with Governments overthe past fewweeks. A revised target date forOBCsubmission forAEP &AMIC is under consideration and willbeprovidedASAP.
ProjectTargets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/10/2023 Amber AGD/O/1- New JobsCreated(Direct andIndirect) 189 tbc
FBC 10/06/2024 Green AGD/O/2- Construciton Jobs Created 130 tbc
Phases Target date AGD/O/9- Business Space Created 5814sqm tbc
Phases Target date tbc tbc
Phases Target date tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
OBCApprovedbyGovernment 30/10/2023 Amber Phase1- workscommence(Food & Drink Centre) 07/04/2025 Green
Planning application secured 28/02/2024 Green Phase2 - works commence (speculative units) 02/02/2026 Green
FBCendorsedbyGovernment 20/05/2024 Green Phase1 - Initialpremises operational 01/02/2026 Green
FBCapprovedbyJointCommittee 10/06/2024 Green Phase2 - Initialpremises operational 09/11/2026 Green
Award & Commence Infrastructure - Procurement Contract 24/06/2024 Green First tenant secured 01/02/2026 Green
Project Risks (top 5 risks and their status will be included in the monthly report) TargetClosure Date
(dd/mm/yyyy)
Risk Impac
t
Likelihood Score AGD
Status
SG
Status Mitigation Action
Construction costs in particular costs of materials significantly
increase
4 4 16
•Theproject team will work closely with colleagues in F+PM and thedesign consultantstodevelopacosteffectivebutefficient
buildingdesign.Anaffordability caphasbeenset aspartoftheappointmentofthedesignteamtoensurewework within the
parameters of the budget. 24/06/2024
Delay or failure delivering project due to concerns around transport
implications
3 3 9 9
•UndertakeallTransport Assessments and reports as required by LDP
•Continueto liaise with Transport Scotland
•ContinuetoprogressallsiteoptionsproposedinBCtoensurebestsitepossibleis chosen and the project can be delivered 30/05/2024
Delays in approval of business case
3 3 9 9
•ProjectleadwillworkcloselywithPMOandpolicyleadswithinUKGandSGto support business case development and
approval to an agreed timeline
30/03/2025
Failureto ContributetoAGD programme objectives
3 3 9 9
•Project willbemanaged byEACin linewith PRINCE 2 principles –anyissues willbe monitored,andremedialactionagreedto
ensuredeliveryremainsinlinewiththeOBC projections.
•AGD Steering Group and other governance arrangements are in place to monitor progressandtoaddressanyweaknessesorissues
thatcouldimpactonoveralldelivery and project lead will be required to provide regular project updates 31/03/2027
Failure to provide accurate projections for project spend
3 3 9 9
•Ensuresufficient optimism bias built into costing of the project
•Inflationary factor included in cost estimations
•ProjectwillbemanagedbyprojectteaminlinewithPRINCE2principles–anyissues willbemonitored,andremedialactionagreed
toensuredeliveryremainsinlinewith theBC projections
•Issues tobeescalated PMO in first instanceto agreeremedialactions as appropriate
•Challengepanelled byPMO exists to review& scrutinisespend profiles 31/03/2027
Health Pandemic/UK threat to business activity
3 3 9 9
•AMICbuilding willbea strategiccentreforbusinessesintimesofcrisis.Thecentre willprovidesupportanddirectionforfoodand
drinksbusinessesaswellasproviding additionalmanufacturingspacetoallowsupplytomeetdemandespeciallywithinthe Dairy
Sector.
31/03/2027
47

Page 48

i3 Flexible Business Space Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Marnie Ritchie
Phase 1 - Contractor Muir Group now due to commence works on site on 30 October. Photo call to mark start of works will take place on 9 November. Contractor advising estimated completion date as 29 July 2024. Phase 2 & 3 - Developing
specifications for Phase 2 with internal team of architects and surveyors.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/05/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 133 tbc
FBC 30/09/2022 Complete AGD/O/2 - Construction jobs created 83 tbc
Phase 2 FBC 25/02/2025 Green AGD/O/9 - Business Space Created 6000 sqm tbc
Phase 3 FBC 28/02/2027 Green AGD/O/10 - Reduced vacant and derelict land 20 ha tbc 
AGD/O/14 - Start-ups 5 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover 31/10/2024 Green Completion of Phase 2 30/10/2029 Green
Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/10/2025 Green Final financial drawdown 31/03/2030 Green
Phase 2 FBC approved by Joint Committee 25/02/2025 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2025 Green   
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover tbc Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Cost overruns  4  5  20  
• Develop and validate Project Brief and Specification
• Benchmark costs
• Ensure early infrastructure cost tested/ informed SI
• Provide Green Book compliant optimism bias allowances
• Provide for contingency
• Undertake value engineering
• Pursue additional funding sources 
Project delays and economic impact of Covid-19 and recovery  4  4  16  
• Early analysis has identified that the need for this project is unlikely to be diminished and in
fact may be even greater
• Project team will continue to focus on economic analysis and the development of
recovery plans will incorporate this as a key project for implementation as part of that wider
plan
• Work with contractors to devise solutions designed to minimise impact of social
distancing – such as different work patterns 
Failure to deliver anticipated outputs and outcomes 3 5 15  
• Ensure BC addresses sensitivity of outcomes
• Clear Evaluation & Monitoring Framework 
Demand – no interest from occupiers  3  5  15  
• Flexible design to maximise potential interest from occupiers
• Marketing and promotion of floorspace
• Continue to establish strategic relationship with national sector (including links with NMIS) 
Utilities cause delays e.g. surface water drainage connections, sub-station
requirements. 
3 4  12    12
• Utility companies to be approached and applications to be submitted at an early stage.
Despite this mitigation, issues have arisen on utilities for Phase 1, hence change to status to
reflect this. Contractor working with Scottish Water and current issue resolved. However
changed to amber /red status for ongoing project and future phases.   
48

Page 49

i3 Digital Processing Manufacturing Centre Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Marnie Ritchie 
Phase 1 - University of Strathclyde are procuring the equipment, fit out, recruiting for resources and securing membership of companies which is taking longer than anticipated. Official launch planned for February 2024. Phase 2 - Centre: Analysis with
partners to be completed on Phase 1 to provide scoping parameters for phase 2.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 95 tbc
FBC 30/06/2022 Complete AGD/O/2 - Construction Jobs Created 84 tbc
Phase 2 OBC 31/12/2024 Green AGD/O/9 - Business Space Created 1749 sqm tbc
Phase 2 FBC 31/12/2025 Green AGD/O/10 - Reduced vacant & derelict land 20 Ha tbc 
AGD/O/16 - Leverage: (incl. LA, HE/FE, Private Sector and any other leverage) £19,810,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/07/2027 Green Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 30/04/2028 Green
OBC Phase 2 approved by Government 31/12/2024 Green   
FBC Phase 2 approved by Joint Committee 31/12/2025 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/01/2026 Green   
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover 31/07/2027 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Capital costs are in excess of the budget.  4  4  16  
• Value engineering of works specifications
• Proactive review of funding opportunities to make the shortfall 
Failure to deliver anticipated outputs and outcomes  4  3  12    12
• Ensure BC addresses sensitivity of outcomes
• Clear Evaluation & Monitoring Framework
• Phase 0 and Phase 1 will establish the concept, build operational capacity and industry
interest.
• Conditions of grant will include expected outputs to measure the project’s success.
• Regular monitoring of centre’s performance through Supervisory Board 
Delays to procurement processes  3  4  12  12
• Seek early agreement on appropriate procurement routes
• Include anticipated tender packages within the Council’s Procurement Wave Plan
• Notify potential bidders of procurement opportunities at an early stage 
Ongoing Partnership commitment  4  3  12  12
• Memorandum of Understanding signed August 2021
• Collaboration Agreement signed March 2022
• Development and co-ordination of appropriate governance procedures
• Commitment to lease for Phase 1 location 
Failure to deliver community benefits  4  3  12   12 • Incorporate appropriate community benefits into contract terms and resource
appropriately. 
49

Page 50

HALO June Project Overall Status
2023 Complete
Project Update
Project Scope Status Complete Project Budget Status Complete
Monthly update - provide narrative      Project Lead: Gary Deans   
Since last reporting HALO have continued to hold a variety of events and support a growing number of diverse business at its #RockMe trading floor. A key event was the successful Space and Trade Conference with speakers from Kate Rubins Astronaut NASA; / Jack Hillmeyer US Consul
General; and Dr David Alexander OBE Rice Space Institute Houston. Topics included the role of young people, the realtionship between HALO and USA, and future thoughts in education.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 232 182
FBC 30/06/2022 Complete AGD/O/2 - Construciton Jobs Created 256 265
Phases Target date  AGD/O/3 - safeguarded jobs 300 375
Phases Target date  AGD/O/15 - Private sector investment £15,199,000 tbc
Phases Target date  AGD/OT/7 - Public and private sector investment - Phase 2 £46,000,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due
date
Milestone
status                              
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Failure in financial management and reporting 
2 2  4    4
• The Board of HALO Kilmarnock Ltd receives monthly reports on all
financial aspects of the project and address any significant variances from
the approved full business case Robust financial systems and controls are
in place and the Board of HALO Kilmarnock Ltd retains oversight of these.
Copy of monthly report forwarded to PMO for BRP purposes. 
Reputational 
2 2  4    4
• Specialist advisers have been appointed to deal with media enquiries
and to communicate on any issue which is deemed to potentially impact
on the reputation of the project and the Board of HALO Kilmarnock Ltd 
50

Page 51

Project Updates – Energy, Circular Economy & Environment Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Community Renewable Energy (CoRE) Diarmid Turnbull David McDowall
Hunterston Strategic Development Area 
Neale McIlvanney  Neale McIlvanney International Marine Science & Environment Centre
(IMSE)
51

Page 52

Community Renewable Energy Oct Project Overall Status
2023 Amber
Project Update
ProjectScope Status Amber ProjectBudgetStatus Amber
Monthly update - provide narrative ProjectLead:Diarmid Turnbull
1.TheCoRECabinetpaperwaspresentedtoCabinet on4thOctober.Membersapprovedthe paper'srecommendations,includinga12monthsecondmentofProfessorLawrencefrom UWSandmatch fundedSeniorLecturertoassistwiththedevelopmentanddelivery of CoRE.
2.ThefirstParnershipBoardmeeting washeldon5thOctober.Membersdiscussedandreviewedtrainingandeducationopportunitiestoaddresstheregionalskillsgap,demonstratorproject themes,initialpathfinderproposalsandscopeforredesignoftheCentreof
Excellence.
3. TheBoardalsoagreedthe keythemes forspecialist working groups,whichwill beestablishedtodevelopanddeliverdemonstratorprojects across themes such as energygenerationandsustainabletransport. TheProject Team will nowformaliseeachoftheworking
groups and arrange initial meetings.
Project Targets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1-New JobsCreated(Directand Indirect) 108 tbc
FBCDemonstratorProjects 20/12/2023 Green AGD/O/2-ConstrucitonJobsCreated 88 tbc
FBCCentreofofExcellence 30/05/2024 Green AGD/O/9-DevelopmentSpaceUnlocked 3008sqm tbc
Phases Targetdate tbc tbc
Phases Targetdate tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
FormationofManagementBoard 30/05/2023 Green FBCforCoREInnovationCentre 30/05/2024 Green
EngagementwithEducationandSkillsPartners 30/08/2023 Green CommencementofProgrammeofDemonstratorProjects 01/02/2024 Green
ProgrammeBusinessCase 15/07/2023 Green tbc
ReviewofCoREInnovationBuilding 20/12/2023 Green tbc
FBCforDemonstratorprojects 20/12/2023 Green tbc
Project Risks (top 5 risks and their status will be included in the monthly report) Target
Closure
Date
(dd/mm/yyy
y)
Risk Impact Likelihood Score AGD
Status
SG
Status MitigationAction
Constructioncosts,inparticularcostofmaterials,significantlyincreasesduetothe
pandemic. 4 5 20
•Theprojectteamwillworkcloselywithcolleagues inF+PMandthedesign
consultantstodevelopacosteffectivebut efficientbuildingdesign.
•AnaffordabilitycaphasbeensetaspartoftheappointmentoftheDesignTeamto ensure we work within the parameters of the budget. 31/03/2030
HealthPandemic/UKthreattobusiness security-theriskthataglobalhealth
pandemic
couldshutdownthecountrycausingsignificantdangertolifeandtheeconomic
stability of the country.
3 5 15
•TheCentreofExcellencewillbeanationalcentreforbusinesseswithintheenergy
andtechnologyindustryintimes ofcrisis.
•The Centre will provide support and direction for these businesses as well as providing labspacetoallowforanytechnologytesting(such
ascreatinganewtypeof ventilator) to meet any demand.
31/03/2030
FailuretoattractinvestorsandnewbusinessestolocatewithintheCentreof
Excellence
3 5 15
•EACwillworkcollaborativelywithspecialistpartners,includingScottishEnterprise
andEnergyTechnologyPartnership,fromanearlystagetoidentifyandworkwith potentialinvestors
•Theresearchcarriedoutwithinthefacilitywillbetailoredtowards particular technologies for which there is market interest in.
•WiderAyrshireEconomicGrowthStrategywillbeputinplacetoensurewidergrowth ambitions for Ayrshire are agreed and be articulated
to stakeholders and investors.
•Atalocallevel,theCouncil willworkwithexistingbusinessesandstart-upstoexplore howtheycanbenefit fromtheproject,apotentialarm
ofwhichcouldbetolocateinto the research facility/incubator space
31/03/2028
Delaysinapprovalofbusinesscase(duetoCOVID-19,feedbackfrombothGovernments
may be delayed as their efforts will be focussed on criticalservices). Potential delays
to project delivery may impact on milestone achievements resulting in potential
reduction in realisation of benefits of AGD.
3 5 15
•ProjectLeadwillworkcloselywithPMOandpolicyleadswithinUKGandSGto
supportbusinesscasedevelopmentandapprovaltoanagreedtimeline.
•Ensurebusinesscasestatistics,feedbackandinformationisup-to-datewhilewaiting for further feedback. 31/03/2027
DesignStagesoftheCentreofExcellenceandthesitetakelongerthanexpectedwith
thelandowner(alsoduetoCOVID-19,therecouldbefurtherdelayasstaffworking
arrangementschange). 3 4 12 12
•Cleardeadlinesandtargetshavebeenclearlysetoutwiththelandowneranddesign
team
•EnsurethereiscontinuouscollaborativeworkingbetweentheCouncil,designteam andlandowner.
•EnsurethereisconsistentcommunicationbetweenProjectTeamandlandowner. 31/03/2025
DelayinstartingconstructionoftheCentre(thiscouldbedowntodelayinprocuring
the contract/consultant delays due to COVID-19 or delays from design stage) 3 4 12 12
•Ensurethattheprojectteamworkcloselywithprocurementtoensuretenderprocess
isefficientandsuccessfulcontractorcanbeappointed.
•Holdinitialmeetings/calls withconsultantandprovidesome elementofflexibilityin timescales for the construction of the Centre.
•Establishanotherriskregister solelyfortheconstructionofthebuilding.
•Hold2weekly/monthlymeetings/callswithconsultantthereaftertoensureprogress ismade.
31/03/2025
52

Page 53

Hunterston Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Green
Monthly update - provide narrative Project Lead: Neale McIlvanney
Recent demand analysis commissioned by Peel Ports Group and Scottish Enterprise has highlighted the importance of providing advanced manufacturing space for SME/incubator and supply chain users at Hunterston, in comparison to an innovation centre or large scale
speculative commercial space. SE are currently leading on how this can be delivered with discussions at a recent Parc Board meeting in August 2023 and workshop with NAC in September 2023 to explore business case options. Options will be analysed with SE during
October and November. However, the case for AGD investment at Hunterston is now likely to be more focused on enabling the delivery of commercial space.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/06/2024 Green AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC 28/02/2026 Green AGD/O/2 - construction jobs 1204 tbc
Phases Target date  AGD/O/3 - safeguarded jobs tbc tbc
Phases Target date  AGD/O/7 - New or upgraded roads/junctions/cycle pathways tbc tbc
Phases Target date  AGD/O/16 - Leverage Funding (incl LA, HE/FE, Private Sector and any other
leverage £200,000,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 30/06/2024 Amber Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 30/06/2029 Green
Completion of detailed design - RIBA Stage 3 31/03/2025 Green Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 31/03/2030 Green
Completion of technical design - RIBA Stage 4 31/12/2025 Green   
FBC approved by EJC 28/02/2026 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2026 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target
Closure
Date
(dd/mm/yy
yy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Unforeseen project complexities that require additional funding  4  4  16  
• Provide Green Book compliant optimism bias allowances
• Provide for contingency
• Project monitoring will track potential impacts and create ability to respond 
Ground conditions and historical legacy of site infrastructure create major burdens for
development  4  4  16   • Project team is working with Peel Port Group to understand the development
issues/infrastructure/utilities impacting onsite re-development 
Concept not supported by Partners and evidence of investment/market support not forthcoming  4  4  16  
• Project team/Peel Port Group/SE developing and promoting an investment model to secure major
inward investment plus academic partners and industry
• Dialogue being progressed around role, responsibilities and funding commitments
• MOU signed between NAC/SE/Peel and wider strategic proposition around blue economy and
Hunterston supported by partners 
Concept and Operational Management revised /amended 3 4 12  12 • Project team/Peel Port Group developing a partnership/investment model to secure inward
investment/academic partners and industry 
Other Development/Investment/ Proposals impact on capacity/deliverability  4  3  12    12 
• Project team/Peel Port Group seeking to collaborate with major partners to develop a clear investment
strategy/masterplan and investment led project proposition for AGD
• Peel Ports have gained planning approval of a site Framework to allow planning applications to
be considered 
Project fails to secure necessary consents 4 3 12  12 • Project team is in early dialogue with key regulatory partners and stakeholders 
53

Page 54

International Marine Science & Environmental Centre Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Neale McIlvanney
The initial MoU between NAC and University of Stirling (UoS) to develop a proposition for IMSE, is now advancing to Collaboration Agreement stage. Recent interest from the Field Studies Council (FSC) to invest in FSC Millport as part of IMSE, offers the potential of a
tripartite Collaboration Agreement between NAC, UoS and FSC with the benefit of an existing operational partner and available land assets. A workshop has been arranged for October 2023 to develop the detail of the Collaboration Agreement, with the aim of partner
approval by end of 2023, to enable progress of an OBC during 2024. In addition, partners will continue to explore supporting Ardrossan regeneration as part of the IMSE programme.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/06/2024 Green AGD/O/1 - New Jobs Created (Direct and Indirect) 75 tbc
FBC 28/02/2026 Green AGD/O/2 - Construciton Jobs Created 58 tbc
Phases Target date  AGD/O/9 - Development Space Unlocked 1400 sqm tbc
Phases Target date  AGD/O/10 - Reduced and vacant derelict land 0.6 Ha tbc
Phases Target date  AGD/O/14 - Start-Ups 4 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 30/06/2024 Amber Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 30/06/2029 Green
Completion of detailed design - RIBA Stage 3 31/03/2025 Green Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 31/03/1930 Green
Completion of technical design - RIBA Stage 4 31/12/2025 Green   
FBC approved by EJC 28/02/2026 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2026 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target
Closure
Date
(dd/mm/yy
yy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Unforeseen project complexities that require additional funding  4  4  16  
• Provide for contingency
• Provide Green Book compliant optimism bias allowances
• Project monitoring will track potential impacts and create ability to respond 
Programme delay created within wider strategic delivery plan for Ardrossan  4  4  16   • Project team undertaking masterplanning process to identify all project requirements and spatial
needs 
Concept not supported by Partners  4  4  16  
• Project team developing a partnership model with leading academic partners and industry
• Dialogue being progressed around role, responsibilities and funding commitments
• An MOU has been signed to develop the project definition with University of Stirling 
Strategic need and consolidation in sector advises Co-Location with wider projects 4 3 12  12 • Project team developing a partnership model with leading academic partners and industry 
Concept and Operational Management revised /amended  3  4  12   12 • Project team developing a partnership model with leading academic partners and industry 
Project cannot secure necessary consents  4  3  12   12 • Project team in early dialogue with key regulatory partners and stakeholders to address any
concerns 
54

Page 55

Project Updates – Tourism Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Marine Tourism Kathleen Dow Neale McIlvanney Great Harbour Kasia Smith
55

Page 56

Marine Tourism Oct ProjectOverallStatus
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kathleen Dow
Marine Tourism Programme Business Case scope of change in progress to respond to ScotGov feedback and covering increased scale of the Cumbrae project, viability analysis of the Ardrossan Project and reduced scale of the Arran Project. Timeframes for submission and review
of the updated PBC and Cumbrae OBC (target Dec 2023 to be discussed with PMO). Cumbrae Project -OBC complete to be submitted with updated PBC. Cumbrae Marina operator development and procurement plan and permissions and consents plan prepared and awaiting
mobilisation upon approval of OBC. Millport Flood Prevention Scheme off-shore breakwaters under construction and to be completed by spring 2024, enabling the marina works to proceed. Investigations to remove the timber section of Millport Pier progressing with
Harbours/Floods Teams, to align marina and pier interdependencies to minimise risks ie costs and time delays. Exploring opportunities related to the removal of Millport pierhead buildings and requirements of the marina onshore spatial needs and facilities. Arran Project -a re-
scopeof options with stakeholders has identified a technically and financially viable solution at Lamlash. This is under further development as part of the re-design of the Programme Business Case.
Project Targets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/12/2023 Green AGD/O/1-New JobsCreated (Direct andIndirect) 30 tbc
FBC 30/03/2026 Green AGD/O/2-ConstrucitonJobsCreated 81 tbc
Cumbrae 30/03/2026 Green AGD/O/9-Development SpaceUnlocked 6Ha tbc
Arran 28/02/2026 Amber AGD/O/10-Reducedandvacantderelict land 0.1Ha tbc
Ardrossan 28/02/2027 Red AGD/O/13-increaseinvisitors(dayandnight) 100000 tbc
Progress Update(top priority milestones aspercurrent Implementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
OBCapprovedbyGovernment 31/12/2023 Green Construction/ProjectcompletedandHandover(RIBAStage5-6:Construction&
Handover) 31/01/2027 Green
Completionofdetaileddesign-RIBAStage3 31/12/2024 Green Operatingproject(RIBAStage7)andreporting 30/07/2027 Green
Completionoftechnicaldesign-RIBAStage4andissueoftender 30/08/2025 Green
FBCapprovedbyJointCommittee 30/03/2026 Green
Construction/ProjectStart(RIBAStage5:Manufacturing&Construction) 31/07/2026 Green
ProjectRisks(top5risksandtheirstatuswillbeincludedinthemonthlyreport) TargetClosure
Date
(dd/mm/yyyy)Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Changestocapitalcostsorinappropriatelyquantifiedcostprovisionsorincreasingcosts
that reduce scope of marina projects 5 5 25
•Detailedtechnicalstudiesinplacetoinformdesign
•Designteamincludesacostconsultancy anddetailedassessmentofcontingencyand
optimism bias is in place
•Regularlyreviewviabilityofeachproject.Considerwhatispossiblewithinbudget.
31/3/26 -
DependentUpon PBC
approval concluded
atOBC- finalisedin
detailed atFBC
Developmentagreementandmarket economyinvestorprincipleforArdrossanfailsto
securesupport 5 4 20
•Projectteamtaking legaladviceintermsofsubsidycontrolandagreementswillbe based on
commercial lease terms required for projects.
31/3/26 -
DependentUpon
OBCapproval
concludedatFBC
Site/groundconditionsareinadequatetoprovidecostcertainty 5 3 15 •FullSI/GIandbathysurveyswillbeundertakenatanearlystageinproject
development
Dependent Upon
OBCapproval
concludedatFBC
Agreementontechnicalapproachtoquays/pontoonsandlandconnectionscannotbe
agreed with stakeholders 5 2 10 10
•Developmentofdesign/layouts/connectionsadvancedwithstakeholders/ partners. Dependent Upon
OBCapproval
concludedatFBC
AgreementsincludingDevelopmentandOperatingAgreementsbetweencommercial
partners and community interest company cannot be secured 5 2 10 10
•NorthAyrshireCouncilseeking toadvanceformalDevelopment andOperating
Agreementbetweenpartners/operatorsandagreeajointapproach.Stakeholder
engagement maintained throughout programme.
31/3/26 -
DependentUpon
OBCapproval
concludedatFBC
56

Page 57

Great Harbour Oct Project Overall Status
2023 Green
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kasia Smith
The Great Harbour Masterplan and related Consultation Report are completed and approval will be sought from Cabinet in Dec'23 and from Planning Committee in early 2024, following an elected members briefing in Nov'23. Consultants are working on RIBA Stage 3 design
for Phase 1 Coastal Hub (Beach Park area) for completion and Gateway approval in early December. The Beach Pavilion building is the subject of a Market Feasibility Study to establish the viability of a re- development model with a community hub / restaurant. A
procurement appraisal has been carried out regarding the appointment of consultants for the Phase 2 -Maritime Mile and for the contractor for the Phase 1 - Coastal Hub. The existence of title burdens related to the Harbour Master's Office (HMO) is impacting on progress of
plans for the building. Notes of interest have been received from private food and drink operators and from a social enterprise for the HMO and these are being considered. A Memorandum of Understanding between the Scottish Maritime Museum and the Council is being
prepared to formalise the partnership in order to progress Phase 3 of the Great Harbour - the Maritime Heritage Hub.
Project Targets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 25/06/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 145 tbc
FBC 31/03/2024 Green AGD/O/2 - Construciton Jobs Created 99 tbc
Phase 1 FBC 31/03/2024 Green AGD/O/9 - Development Space Unlocked 9800sqm tbc
Phase 2 FBC 31/10/2024 Green AGD/O/10 - Reduced and vacant derelict land 6Ha tbc
Phase 3FBC 31/03/2025 Green AGD/O/16 - Leverage Funding (incl LA, HE/FE, Private Sector and any other
leverage £4,000,000.00 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
FBC approvedbyJointCommittee 31/03/2024 Green Statutory Consents 30/06/2024 Green
Completion of detailed design - RIBA Stage 3 31/12/2024 Green Completion of technical design - RIBA Stage 4 30/05/2024 Green
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 15/05/2024 Green Completion of Construction Tender 31/08/2024 Green
Construction/Project completed and Handover (RIBA Stage 5-6: Construction & Handover) 31/10/2025 Green Internal sigh-off of FBC (NAC Cabinet) 30/09/2024 Green
Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/10/2026 Green FBC update to Joint Committee Phase 2 31/10/2024 Green
Project Risks (top 5 risks and their status will be included in the monthly report) TargetClosure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Increaseincapitalcostsassociated withchangingscopeorinappropriately
quantified cost provisions 5 3 15
•Cost estimates based on current market
•Detailed technical studies to inform design and a fully detailed/itemised cost plan
•Project management established to monitor costs
•Optimism bias built into costings
•Future design team to include cost consultancy
•Additional internal and external funding bias
Economic downturn as a result of Covid-19 3 3 9 9
•Robust project management inplacetoanalyseimpact onthis project andwider sector and focus will be
placed on this project as an important element of the recovery agenda in Ayrshire
•Project team will work with contractors to understand the impact of social distancing onthelabourforcebut
expected tobeminimalgiventhis is land based
•Continueeconomicanalysis anddevelopment ofrecovery plans willbe implemented
•Robust project scoping should continue to ensure the facility meets needs
Project outcomes,includinginclusivegrowthandreducing
inequalities, failtobe delivered 4 2 8 8
•AGD PMO is currently working with project leads to develop a consistent approach to ensure inclusivegrowth,
equalities and community wealth building outcomes are embedded ineachAGD businesscase. Thisapproach will
ensureexplicit commitment to how the project will achieve inclusive growth and reduce inequality
Technicalapproachtoquays/pontoons andlandconnections cannot be
agreed with keystakeholders 4 2 8 8
 Development of Partnership/Operator Plan and detailed GANTT Programme  ensuring programme allows time for
engagement and approvals
•PPiP routeminimises risks andensuresfull engagement withstatutory bodies and community
•NACindiscussion with HarbourAuthority
•Development Briefs drafted for Great Harbour
57

Page 58

Project Updates – Digital Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Digital Infrastructure & Sub Sea Cable (TBC) Simon Yeardley Louise Reid
58

Page 59

Digital Infrastructure & Subsea Cable (TBC) Oct Project Overall Status
2023 Red
Project Update
Project Scope Status red Project Budget Status red
Monthly update - provide narrative Project Lead: Simon Yeardley
Following on from the Partnership board meeting held on the 7th of September where endorsement of scope option 5b was given by the board a change request will now be made to the (AEJC) in November 2023. Where option 5b has been
identified as the preferred option, two funding scenarios will be presented:
I) Scenario 1: Available funding is split amongst lead authorities based on their AGD contribution and settlement, with Lead Authorities prioritising how spend is then apportioned across AGD capital projects, or:
ii) Scenario 2: Regional partners allocate funds and prioritise projects based on regional economic benefits realised. It is proposed that funding from the de-scoped
Subsea Cable and Infill projects will be apportioned to in train AGD projects identified by the key SRO's as having key connectivity and infrastructure requirements and where there is a risk of stalling or failure to deliver due to lack of sufficient funding.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC tbc under rescope AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC tbc under rescope AGD/O/2 - Construciton Jobs Created tbc tbc
Phases Target date  AGD/OT/1 - Job levels (new and maintained) tbc tbc
Phases Target date  AGD/OT/3 - Digital Usage patterns tbc tbc
Phases Target date  AGD/OT/7 - Additional investment (incl Foreign Direct Investment) tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Report on Re-scope exercise to Partnership Board 27/04/2023 Complete   
Joint Committee approve re-scope of project 22/05/2023 Complete   
AEJC approve re-scope of project (Mtg date tbc) 30/10/2023 Amber   
change management process applied 30/11/2023 Amber   
Project Completion 30/09/2026 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Cost overruns 
2 2  4    4
• Rescoping exercise has concluded and identified a valid option that can be delivered by
reprioritisation of current budget to in train AGD projects
• Robust contract management in place
• Appropriate procurement procedures followed and optimism bias built into business case  30/10/2023
Failure to reach consensus on project re-scope option 
2 2  4  4
• Stakeholder engagement
• Re-scope proposal scope 5b approvals and approved by Partnership Board via
established AGD governance  30/10/2023
Resource availability 
3 2  6   6
• Effective deployment of resource to support delivery of the project 
30/09/2026
59

Page 60

Project Updates – Regional Skills & Inclusion Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Ayrshire Skills Investment Fund Laura Neill Neale McIlvanney Working for Healthy Economy 
60

Page 61

AyrshireSkillsInvestmentFund Oct ProjectOverallStatus
2023 Amber
ProjectUpdate
Project Scope Status Amber Project Budget Status Green
Monthly update - provide narrative Project Lead: Laura Neill
The FBC has been endorsed by SG and was approved by the Ayrshire Economic Joint Committee in August 2023. Plans for delivery are emerging through ASIF sub-committee with agreement on the Delivery Model with intention to consider proposals from Ayrshire College, University
of the West of Scotland and Employer Grant applications in November 2023. The Employer Grants Programme was launched in October inviting employers to identify training requests to support priority groups within priority sectors.
ProjectTargets
Business Cases Target date Status Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/04/2023 Complete No of peoplebenefiting from in work skillsdevelopment 500 tbc
FBC 30/06/2023 Complete No of people benefiting from pre-employment upskills 500 tbc
People benefiting from accredited training 300 tbc
No of businesses benefiting from employees with improved skills levels 300 tbc
No of participants progressing to living wageopportunities 200 tbc
Progress Update (top priority milestones asper current Implementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
OBC approved by Government 25/07/2023 Complete 1st annual review 30/06/2024 Green
FBC endorsed by Government 25/08/2023 Complete complete mid-programme evaluation 31/03/2025 Green
FBC approved by Joint Committee 07/08/2023 Complete End of programme/final drawdown 31/03/2027 Green
Development of guidance for fund applicants 30/06/2023 Complete quarterly application deadlines Green
1st call for proposals 01/07/2023 Complete
Project Risks(top 5 risks and their status will be includedin the monthly report) TargetClosure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Project delays due to Covid-19 5 5 25
• Early analysis identifies that the need for this project may be greater as a result of
Covid-19
• Continued economic analysis and development of recovery plans should be implemented and
robust project scoping should continue to ensure the proposal meetsneeds
Programme does not secure sufficient partner buy in to ensure an effective set of
interventions are designed and funded 1 1 1
• Early establishment of Regional Skills Board with strategic oversight
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit
and satisfactory progress
Failure to deliver anticipated impacts across the region in terms of Inclusive
Growth
1 1 1
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit
and satisfactory progress
• The partnership will conduct a mid-programme evaluation to check the direction of travel is still correct
Disadvantaged residents do not see tangible benefits from projects 1 1 1
• Applicants to the fund will be required to detail how delivery against inclusion targets will be
assured
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit
and satisfactory progress
Inadequate project management results in failure to delivery agreed outcomes 1 1 1
• The Regional Skills Board will provide expert advice on what should be supported
through the fund
• Adopt programme and project management best practice
• These arrangements will be reviewed on an annual basis to ensure they remain fit forpurpose
• The Steering Group will conduct a mid-programme evaluation and adjust project activity as
appropriate
61

Page 62

Working for Healthy Economy Oct Project Overall Status
2023 Green
ProjectUpdate
ProjectScope Status Green Project Budget Status Green
Monthlyupdate-providenarrative ProjectLead:LauraNeill
WecontinuetomonitorprogresstoensureeffectivedeliveryacrossAyrshire.Working foraHealthyEconomycontinuestobedeliveredacrossAyrshiretohelpindividualsmanageandimprovetheirhealthtoprogresstoorsustainemployment.In
September2023thefollowingindividualsweresupported:
• 45individualsweresupportedin September2023 •Oftheindividualscompleting theservicestodatetherehasbeena26.9%improvementinoverallhealthandwellbeing
• Onmeasuring anxiety,a36.4%improvement inanxietylevelshasbeenachieved •Depressionlevelsexperiencedhaveimproved by45.3%
WecontinuetomonitorprogresstoensureeffectivedeliveryacrossAyrshire. Arangeofeventsandongoing promotionalactivitieshasbeenundertakentoachievethefiguresreportedabove.
ProjectTargets
BusinessCases Targetdate Status BenefitsRealisation(top5deliverables) Target Actual
OBC 19/02/2021 Complete Noofpeopleaccessingassessment& report 960 tbc
FBC 22/02/2021 Complete No of peopleaccessing full management support via telephone 1600 936
Noof peopleaccessingfull casemanagementsupportdeliveredfacetoface 3838 282
No ofpeoplereturning towork 1157 77
Unemployedresidents supported 4629 tbc
ProgressUpdate(top prioritymilestonesaspercurrentImplementationPlan)
Milestone Duedate Milestone
status Milestone Duedate Milestone
status
Evaluation commences 30/06/2022 Green End of programme/final drawdown 31/03/2027 Green
Year3targetsachieved 31/03/2024 Green
Year4targetsachieved 31/03/2025 Green
Year5targetsachieved 31/03/2026 Green
Year6targetsachieved 31/03/2027 Green
ProjectRisks(top5 risksand theirstatuswillbeincludedinthe monthlyreport) TargetClosure Date
(dd/mm/yyyy)
Risk Impac
t
Likelihood Score AGD
Status
SG
Status MitigationAction
Implementation: Overdemandorlackof demand 5 5 25
•Proposedtargetsarebasedondeliveryexperienceacross Scotlandandthe experience of delivering a
case management service in North Ayrshire recently
•Theproposalasitstandsisdesignedtoremovebarrierstoaccessingthisservice.In the event of over
demand, referral criteria can be set to reduce demand
•Project Board has discussed geographical disparity between geographies and agreed mitigation action. Agreed
to review again in October.
Project delayandmacro-economic impact of Covid-19 and recovery 5 5 25
•Earlyanalysis identifies that theneedfor theproject is unlikelytobediminished –in
factmaybegreater
•Continued economic analysis and development of recoveryplans should be implemented and robust
project scoping should continue to ensure proposal meets needs
Unforeseen complexities that requireadditional funding 1 1 1
•Providefor contingency
•ProvideGreenBookcompliant optimism bias allowances
•Similarproject has beendeliveredpreviously
•Project monitoring willtrackpotentialimpacts and createabilityto respond
National programmes areintroduced which result in duplication 1 1 1
•Closelymonitornationaldevelopments andbuild inflexibilitytocontracting arrangementstoallowusto
changecourseatshortnoticeifnationalprovisionis introduced that duplicates provision.
Failuretodeliveranticipatedoutputsandoutcomes.Failingtoachievemore
inclusive growthand/orreducepovertybyincreasingtheincomeofpeoplein
deprivedareasor protected characteristic groups.
1 1 1
•Closelymonitor nationaldevelopments and havebuiltin flexibilitytocontracting
arrangementstoallowustochangecourseatshortnoticetorespondtoprogramme impact
•Covid-19impactsonspecificgroupswillbeassessed.Earlyindicationsarethatyoung people, females, those
withhealthissues ordisabilities willbedisproportionately impacted by recession, therefore more targeted
Implementation: End ofproject ‘cliff edge’ 1 1 1 •Wouldhopetoinfluencethenationalpolicyaroundoccupationalhealthservices,asa legacy of the programme
Appointed contractor could beimpacted negativelybyCovid-19 1 1 1 •Aspartofprocurementprocess,robustcheckshavebeenmadeonfinancialstanding of delivery organisations
62

Page 63

Project Updates – Community Wealth Building Programme 30 September
2023 
Project Name Project Lead Senior Responsible Officer
Community Wealth Building Emma McMullen Neale McIlvanney
63

Page 64

Community Wealth Building Oct Project Overall Status
2023 Green
ProjectUpdate
ProjectScope Status Green Project Budget Status Green
Monthlyupdate -provide narrative Project Lead: Emma McMullen
The programme is progressing well having nowsurpassed the headline target ofsupporting over over 900 unique enterprises with CWB in theAyrshire region. Inaddition to daily delivery ofkey programme outputs, the programme alsosupported a Meet theBuyer |
Ayrshire event hosted in East Ayrshire during theAyrshire Chamber business week to help progress the procurement pillar outcomes of the programme. Most recently, Fair Work Ayrshire coordinated and hosted a job fair at Ayrshire College which was attended by 385
jobseekers. 27 businesses collaborated onthe day, including anchorinstitutions such as the NHS, Police, SF&RS, Ayrshire College, DWP, NAC and EAC, and wider business stakeholders suchas Woodward, Spirit, Emergency One, TPS Weldtech and Green Home Systems.
Looking forward, the programme is exploring options beyondMarch2024 toideally enable continued delivery of outputs anda streamlined approach to CWB through enterprise support in Ayrshire.
ProjectTargets
BusinessCases Targetdate Status Benefits Realisation(top 5deliverables) Target Actual
OBC 12/02/2021 Complete CWB Officers & Action Plans in place - creation of CWB Locality Baselines 15 allofficers in post
FBC 22/02/2021 Complete Total enterprises engaged 920 956
Employers undertaking Fair Work Action Plans 90 124
Enterprises receiving financial assistance 265 245
New enterprises supported 96 136
Progress Update (top priority milestones as per currentImplementation Plan)
Milestone Due date Milestone
status Milestone Due date Milestone
status
Fairworkinspirationweek(inlRLW & Disability Awareness) 30/11/2023 Green Ayrshire CWB Enterprise Awards & Programme Achievements celebration 30/04/2024 Green
Fair workjobfair 28/02/2023 Green Monthly Programme Steering Group Meetings 31/03/2024 Green
500 Ayrshire enterprises supported by the CWB programme 31/03/2023 Green Reporting to PMO, Ayrshire REP & EJC members 31/03/2024 Green
Programme case study showcase - SG visits 31/05/2023 Green Annualreport 31/03/2024 Green
1000 Ayrshire enterprises supported by the CWB & FWA programme 31/03/2024 Green Project end date/final review/final report/final drawdown 31/03/2024 Green
ProjectRisks (top 5 risks and their status willbe included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Imp
act
Likelihood Score AGD
Status
SG
Status MitigationAction
Project delays due to Covid-19 4 4 16
• Earlyanalysis identifies that theneedforthis project maybegreateras a result of Covid-19
• Continued economic analysis and development of recovery plans should be implemented androbust project
scopingshould continueto ensurethe proposal meets needs
Programme does notsecuresufficient partnerbuyintoensureaneffective
set of interventions are designed and funded 1 1 1
• Early establishment of Regional Skills Board with strategic oversight
• Quarterly progress reports and annual review will inform decision making processes
• TheSkills Fundwillissuecalls forproposals meaning priorities canbeadapted to ensure strategic fit and
satisfactory progress
Failure to deliver anticipated impacts across the region in terms of Inclusive
Growth
1 1 1
• Quarterly progress reports and annual review will inform decision making processes
• TheSkills Fundwillissuecalls forproposals meaning priorities canbeadapted to ensure strategic fit and
satisfactory progress
• Thepartnership willconduct a mid-programme evaluation tocheckthedirection of travel is still correct
Disadvantaged residents do not see tangible benefits from projects 1 1 1
• Applicantstothefundwillberequired todetailhowdeliveryagainst inclusiontargets will be assured
• Quarterly progress reports and annual review will inform decision making processes
• TheSkills Fundwillissuecalls forproposals meaning priorities canbeadapted to ensure strategic fit and
satisfactory progress
Inadequate project management results in failure to delivery agreed
outcomes
1 1 1
• TheRegional Skills Boardwillprovideexpert advice onwhat shouldbesupported
through the fund
• Adopt programme and project management best practice
• Thesearrangements willbe reviewed on anannualbasisto ensurethey remainfit for purpose
• TheSteering Groupwillconduct a mid-programme evaluation andadjust project activity as appropriate
64

Page 65

Appendix 2 - Quarterly Communications Report as at October
23 
Project Quarter 2 Review Quarter 3 Plans 
Spaceport
Initiative
RIBA Stage 3 design complete.  Discussion ongoing with
regards to land acquisition and operating model.
No media proposed until further clarity reached on project.
Aerospace and
Space Innovation
Centre ( ASIC)
Appointed Ironside Farrar as consultant to create OBC
for ASTAC. Appointed Project lead from within SAC
Economy & Regeneration team. Agree timeline for OBC
submission.  Cabinet paper sign off. Key roles/partners
identified.
Establish steering group with SAC/Consultant/AC. Define a
viable ASTAC proposition and and agree the
Definition/Scope/Objectives. Agree Roles/ Responsibilities.
Work supporting College business plan & Land deal with GPA
underway.
Commercial
Space Prestwick
Site clearance now complete and detail design
development ongoing.  
No media proposed until further clarity reached on project.
Prestwick
Infrastructure 
Progress is being made towards completion of the
STAG. Following approval to discard the history phased
roads enabling projects a further report is now
prepared and lodged for presentation to cabinet
detailing the work undertaken to date.  
November: Community council meeting with Monkton
residents where reports will be delivered on traffic calming
exercise outcomes. 
HALO Kilmarnock  Captured in the Monthly Report  Captured in the Monthly Report
Ayrshire
Engineering Park
(Moorfield)
Two consultation events took place in October to share
proposals to merge these 2 projects on the Moorfield
site as Ayrshire Innovation Park (AIP). Branding options
have been created for AIP. Communications activities
included press, social media and email bulletins to
encourage participation. A short survey was hosted on
the AGD website for the duration of the consultation.
https://lnks.gd/2/2TzMJJq
Findings from the consultations will help to inform the
planning application.
Ayrshire
Manufacturing
Investment
Corridor ( AMIC)
65

Page 66

i3 Flexible Space 
(Expected Completion
Summer 24)
Press opportunity to mark the construction start of the
project has been pushed back to mid October 23.
October: Photo call is being arranged in November to mark
the start of construction at a ground breaking event where
key stakeholders will be invited to attend this development
milestone.
i3 Digital
Processing
Manufacturing
Centre (DPMC)
Phase 1Comms Led
by NMIS: Media
activity set out
below
4 August Visit by Parliamentary Under Secretary
(Scotland Office) John Lamont MP visited DPMC  and
met with Booth Welsh.
October: Press Release to be issued highlighting Community
Wealth building in action. Local Kilwinning business Ailsa
Reliability Solutions will be the supplier of technical support
for the DPMC demonstrators.  
Filming being undertaken to develop an "explainer"
video.  This will tell the story about the new Digital
Process Manufacturing Centre in.  The video will be
hosted on NMIS and partner websites and used within
social media posts and presentations and at events. 
February: Date of the official opening of the centre has been
agreed 21st Feb 2024 - event planning taking place to organise
arrangements  
DMPC represented at PharmaTech Integrates 2023 as
part of the NMIS / CPI presence 
Community
Renewable Energy
Project ( CoRE)
Scope of project has been reviewed and refreshed, and
recommendations were accepted by EAC Cabinet in
September. Press release prepared and issued to
promote the update.  https://newsroom.east-
ayrshire.gov.uk/news/renewed-focus-for-community-
renewal-project  
Hunterston
Strategic
Development Area
Work being carried out to finalise scope of offering.
Communications activities will be aligned to this work,
when required
Work being carried out to finalise scope of offering.
Communications activities will be aligned to this work, when
required
66

Page 67

International
Marine Science and
Environmental
Centre (IMSE)
Work progressing to complete OBC by 2023 including
extension to MoU to a Collaboration Agreement. This
will be based on the concept of Clyde monitoring array. 
Potential media opportunities include: the signing of a
tripartite Collaboration agreement with University of Stirling
and Field Studies Council expected Autumn. Refreshed
partnership agreement report to be presented to cabinet in
autumn. 
The Great
Harbour, at Irvine
Harbourside and
Ardeer
The team are in the final stages of developing a detailed
masterplan for the project, following extensive
consultation with the public. Planning permission for
the project will be being sought by the end of 2023. The
next quarter will see technical and operational progress
on this project - with minimal public communications
required at this stage. 
Potential media opportunity include: the publication of the
consultation results following the conclusion of the
harbourside masterplan consultation, planning committee
decision on plans expected November 24.
Marine Tourism The next quarter will see the development of the
Marine Tourism Programme Business Case and outline
business case for the Cumbrae Marina - minimal public
communications will be required. Any communications
required about the wider Marine Tourism programme
will be developed in consultation with colleagues.
Potential media Opportunities: Marine Tourism Programme
Business Case and Outline Business Case for the Cumbrae
Marina development expected to be submitted to
Government by December 23. Supporting communications
will be provided in the works associated with the Millport
Flood Protection Scheme breakwater development and
coastal flood protection works. 
Digital Subsea
Cable and Digital
Infrastructure 
None to report  None to report
67

Page 68

Working for a
Healthy Economy  
Further promotion will be run on social media including a
video series created by Salus. 
We will explore how we can reach more employers as there is
potential to increase referrals here, looking at further work
with Business Teams to promote to their clients and other
contacts.
Ayrshire Skills
Investment Fund
We will continue to work with the Project Lead to
confirm the next steps for this project. A
communications plan will be developed to meet project
outcomes. Press release issued on £3 million training
fund to help develop skills and employment
opportunities to drive forward the Ayrshire economy.
In September a press release was issued to announce the £3m
Ayrshire Skills Investment Fund. 
Following approval (expected around 9 Oct) we will launch
and promote the employer skills grant to local businesses
across Ayrshire. 
Presentation to be given to Ayrshire Economic Partnership
Joint Committee Sub-group on Communications Plan to
promote fund to key audience groups.
Community
Wealth Building
Fund
We will support the Programme Manager as required to
promote the South Ayrshire event.  We will also look at
the wider social media, PR around community wealth
building and identify some key highlights and case study
features to promote during Q2.
South Ayrshire event was held on 27 Sept with over 160
attendees from business and organisations across Ayrshire. 
The video series has now been completed with the addition of
a South Ayrshire film which was premiered at the event. 
During Q3 we will organise social media promotion and PR
(where appropriate) to promote the support available to
businesses and showcase the work of the AGD programme to
date.  
We are also investigating the possibility of recording podcasts
with businesses from across Ayrshire who have benefitted
from CWB support.  This work will start in Q3 and continue
into Q4. 
68

Page 69

AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 20 NOVEMBER 2023
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL - 
PROGRAMME RISK REGISTER UPDATE (OCTOBER 2023)
PURPOSE OF REPORT
1. To advise the Economic Joint Committee on the update for the AGD
Programme Risk Register as of the end of October 2023. Please note this
is further update to that report to the 7 September 2023 Partnership Board.
RECOMMENDATIONS
2. It is recommended that Members agree the content of the:
(i) The updated Programme Risk Register dated October 2023
BACKGROUND
3. The Ayrshire Economic Joint Committee (AEJC) (dated 26 June 23)
approved the quarterly review and reporting of the AGD Programme Risk
Register as a separate item on future AEPB and AEJC meetings.
4. The attached (Appendix 1) provides the latest update of the Programme
Risk Register. This has been informed by the risk register of all projects
within the programme. The top scoring programme and project risks are
reported to the Chief Executives Group, Steering Group, AEPB and AEJC
on a regular basis via the sharing of the monthly reports.
MAIN REPORT
5. The PMO has undertaken further a review of the Programme Risk Register
in line with the recommendations of the AEJC. This has included reviewing
the nature of the risks, their RAG status/scoring, and in the mitigation
measures used to reduce the potential of risk. This review has been
informed by the P7 October Monthly Report (as considered elsewhere on
the agenda).
6. Further discussions have been held with the Government in order to
Agenda Item 7
69

Page 70

explore the best way to manage the challenges partners are experiencing
on delivering key capital projects. Initial discussions have identified the
potential for the Programme to undergo a midterm review, in line with the
AGD Governance. This is referenced as a ‘Checkpoint Review’ (para 3.5
Governance Document v15 December 22). This states the following: 
A Checkpoint Review process will be developed and agreed with
partners and governments to examine both the Growth Deal
programme and component projects at key decision points in their
lifecycle. It will look ahead to provide assurance that projects can
progress successfully to their next stage. 
7. The Government has advised that the review should entitled as a
Programme Review 23/24 which will inform the financial year 24/25. The
process of the Review is still early in its execution. Further details of the
steps, scope, approach and timelines are provided elsewhere on the agenda
under the AGD Programme Update item. 
8. Therefore based on the Review at this point in time, no substantial changes
are yet proposed to be made to the Register in terms of the risks identified
and their RAG status. However amendments have been made to some of
the mitigation measures in reflection of the proposed undertaking of a
Programme Review of the programme and its projects. These changes are
highlighted ‘red underscored’ textual changes in the attached (Appendix 1) 
9. In the meantime the six risks identified with a ‘red’ RAG status still remain.
These are: 
(i) AGDRISK01 - Failure to achieve AGD programme objectives within
agreed budget
(ii) AGDRISK02 - Failure to provide accurate projections for programme
spend 
(iii) AGDRISK03 - Failure to drawdown full AGD funding
(iv) AGDRISK04 - Delays in development and approval of business cases
(v) AGDRISK10 - Lack of resources in PMO
(vi) AGDRISK21 - Potential impact of international events upon cost of living
crisis and economic prosperity of Ayrshire 
10. At a project level, individual reviews are still underway. These reviews will
inform the Programme Review where timings permit. Projects that are
expected to undergo reviews in the near future, and are likely to be subject
to change management include the Digital Programme (as reported
previously to the Board) , Spaceport (being considered elsewhere on the
agenda) and other key projects in the Prestwick cluster, AMIC and Moorfield.
Other projects that may be subject to re-scoping include Marine Tourism and
Hunterston. 
11. Collectively once the review of projects have been completed then the level
70

Page 71

of risk identified on the Programme Register should start to be reduced, in
particular for the ‘red’ risks (AGD RISK01-04) 
12. Finally discussions continue between the three Ayrshire Councils as the
funders to help de-risk issues around PMO resources (AGDRISK10).
Progress is being made on filling the current vacancy for the AGD
Programme Manager and Business Support Assistant. 
13. In conclusion it is considered that the Programme Risk Register continues
to provide a more realistic reflection of the state of the challenges the
programme are facing. ‘Behind the scenes’ senior management, project
leads are working towards reviewing the deliverability of both the programme
and individual projects so that they still meet the objectives and desired
outcomes of the Deal. This activity is being undertaken in consultation with
the Governments, so that we can all reach a satisfactory conclusion. Once
completed partners should start to see amendments in the Risk Register and
the de-risking of the risks identified with a ‘red’ RAG status. 
IMPLICATIONS 
14. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 15
2.Governance/Legal Yes  Para 18
3. Human Resources Yes  Para 19
4. Equality and Fairer Scotland Duty Yes  Para 20
5. Financial  Yes  Para 17
6. Risk  Yes  Whole paper
7. Community Wealth Building   No 
8. Net Zero   No 
ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
15. Inclusion is a key driver for the AGD. Deal business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
16. The Risk Register provides the framework for reviewing the challenges the
Deal needs to address and enables effective mitigation measures to be
undertaken that include meeting the headline Deal objective of delivering
inclusive growth. 
FINANCIAL IMPLICATIONS 
17. It is accepted by the Ayrshire Councils and the Government that risks
should be managed and mitigated where necessary in order to support the
71

Page 72

effective delivery of projects and the programme. 
LEGAL IMPLICATIONS 
18. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the recently revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2023. 
HUMAN RESOURCES IMPLICATIONS 
19. There are no immediate human resource implications arising from this
report. However for the risk associated with lack of resources in PMO to be
addressed there could be human resource implications. 
EQUALITY IMPACT ASSESSMENT 
20. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business
case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES 
Appendix 1: Updated Risk Register – October 2023
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk  
72

Page 73

Appendix 1:
AYRSHIRE GROWTH DEAL UPDATED PROGRAMME RISK REGISTER (RISKS AND MITIGATIONS) – OCTOBER 2023 
RISK Current
Matrix and
Score
Proposed
Matrix and
Score
MITIGATION
AGDRISK01
Failure to achieve AGD
programme objectives
within agreed budget 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16   The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group in place
to monitor progress and to address any weaknesses
or issues that could impact on overall delivery 
 PMO developing monitoring and evaluation
processes to ensure overall objectives are captured
and any project failing to achieve and contribute to
these is flagged and issues addressed as quickly as
possible. This includes responding to increasing
costs of general capital works within the context of
the original funding made available by the
Government in 2019. Leading to potential to review
risks where evidence suggests insufficient funding
to undertake and complete projects in line with
expected outcomes.
 PMO are working with Partners in undertaking a
Programme Review in line with the AGD
Governance. 
 PMO undertake ongoing environmental analysis to
ensure programme objectives are relevant/valid as
well as maximised where relevant and new benefits
identified when materialising.
 Internal governance include regular reviews
undertaken by PMO with input from SROs, Project
Leads and Chief Executives to ensure AGD
73

Page 74

programme objective are met.
AGDRISK02
Failure to provide accurate
projections for programme
spend 
Scoring –  - 16 
NO CHANGE IN SCORING 
Score 16  Score 16   Issues will be escalated to CEOs, Regional Economic
Partnership and Regional Economic Joint Committee
as appropriate 
 PMO working with Partners in undertaking a
programme midterm Programme Review in order to
clarify accurate projections for project and
programme spend and delivery. 
 The Implementation Plan and Financial Plan have
been updated to take account of the compressed
funding.  Project Leads have sought to address
delays in gaining approved FBCs, by undertaking
reviews of projects to fit existing budgets, which are
shared with Finance Directors, the government and
wider partners. Revised project mitigation measures
seek to demonstrate how inflationary pressures will
be managed
 Business Case process monitored to ensure
streamlined pathway to approval enabling projects
to achieve FBC as quickly as possible to reach
project delivery and clarity on expected spend.
 PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs
and Finance Directors and ensure drawdown
projections align with delivery timescales
 OBCs/FBCs include an optimism bias factor as per
Treasury Green Book and AGD Governance
document
 Inflationary factor addressed through project
reviews e.g. re-scoping, phasing and reviewing
benefits
AGDRISK03
Failure to drawdown full AGD
Score 16  Score 16   PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs
74

Page 75

funding 
Scoring –   - 16 
NO CHANGE IN SCORING 
and Finance Directors and ensure drawdown
projections align with delivery timescales. This
includes PMO working with Project Leads, SRO’s and
S95’s to ensure projects can be realised and help
with change processes where necessary; and
undertaking effective communication with
Governments to ensure projects can be realised
 PMO working with Partners in undertaking a
Programme Review in order to clarify accurate
projections for project and programme drawdown
on AGD funding. 
 Achieve business case approval in line with latest
Deal Implementation Plan, and AGD Governance
document and, Finance guidance
 Annual review of Financial Plan and Implementation
Plan
 The Scottish Government’s financial reporting
requirements will be implemented
 Pivot projects proactively where possible in line with
need and opportunity
 Internal procedures, financial controls and
processes in place to mitigate this risk
AGDRISK04
Delays in development and
approval of business cases 
Scoring – 16
NO CHANGE IN SCORING 
Score 16  Score 16   Undertake focused engagement with SG and UKG in
order to help ensure SBC, OBC and/or FBC comply
with the Treasury Green Book and gain approval pin
line with AGD governance
 PMO working closely with Project Leads and Policy
Leads within UK and Scottish Governments to
support business case development and approval to
an agreed timeline. This includes exploring a
streamlined change process (pre-FBC) particularly
where budget constraints are sole driver of change.
In addition as part of a Programme Review,
75

Page 76

reschedule business case timescale for development
and delivery. 
 Project Leads have received Green Book business
case training
 Project Leads’ toolkit in place
 Other partners assisting in developing business
cases where capacity is low
AGDRISK05
Failure to capture accurate
baseline data 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9  Project Leads required to establish appropriate
economic, social and environmental baseline
information in business cases
 Establish and regularly review achievable outcomes,
output and targets as part of the development and
delivery of projects and realization of benefits in line
with the Benefits Realisation Plan 
AGDRISK06
Failure to deliver community
benefits from AGD 
Scoring – 6 
NO CHANGE IN SCORING
Score 6  Score 6   PMO and procurement managers from the three
Ayrshire Councils have developed a AGD
Community Benefit Tracker, a single mechanism to
monitor delivery of community benefits so that
remedial action can be taken if required
 Result from the AGD Community Benefits Tracker
system will be analysed and reported to the
Regional Economic Partnership and Regional
Economic Joint 
 PMO working with Project Leads to develop
consistent approach to embedding inclusive growth,
equalities, clean growth, and community wealth
building within business cases through the Annual
Performance Report
 Procurement working group has been established
and operates in order to support delivery of
community benefits which includes development of
a Community Benefits Tracker and coordination of
76

Page 77

procurement approaches so they support the
development and delivery of projects
AGDRISK07
Failure to deliver individual
projects within the AGD
programme 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   Regular dialogue/reporting around progress takes
place between PMO and Project Leads where issues
are raised in advance and if appropriate escalated
to government, Regional Economic Partnership and
Regional Economic Joint Committee, this includes
early discussions with both UK and Scottish
Government
 The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group and
Project Boards in place to monitor project
development, via monthly reports
 Partners are regularly reviewing the AGD Benefits
Realisation Plan every 6 months and reported to the
Regional Economic Partnership and Regional
Economic Joint Committee
 Current change management process incorporated
in the AGD Governance document and regularly
reviewed.
 PMO working with Partners in undertaking a
Programme Review. This will be informed by a
review of individual projects deliverability and
timescales. 
 Risk register in place for each project which is
regularly reviewed via monthly reports, quarterly
reports and when updating the Implementation Plan
 Project risk registers included in business cases
which are formally approved by government and
Regional Economic Joint Committee
 Management Information System in place and used
to track progress of projects against key milestones,
and reported via monthly and quarterly reports
77

Page 78

AGDRISK08
Inadequate recognition of
interdependencies and/or
knock-on impacts between
parts of the programme
leading to issues with
delivery and/or lost
opportunities 
Scoring – 9 
NO CHANGE IN SCORING
Score 9  Score 9   Programme meetings take place regularly between
PMO, Project Leads and partners to ensure 
interdependencies are recognised and considered;
and incorporated in approved business cases
 PMO working closely with project leads to ensure
interdependencies are fully articulated within the
project business cases and for the programme as a
whole.
 All forms of interdependencies are monitored and
managed to help enable the development and
delivery of all Deal projects
AGDRISK09
Lack of resource within
partner organisations to
deliver projects in line with
AGD programme 
Scoring – 9 
NO CHANGE IN SCORING
Score 9  Score 9   Formal approvals of Councils’ resources are now in
place for AGD projects
 Each Council has appointed staff and/or consultants
to support project development and delivery
 Each project currently has a Project Lead in place
 Partners including SE are providing additional
resource to relevant projects
 Resources committed to the delivery of the
programme, with further discussions underway to
explore how to deliver the recently approved
Regional Economic Strategy 
 Other funding streams is being explored to support
ongoing revenue costs
 Anticipated revenue streams will be subject to
constant review through the monitoring procedures
in place for AGD 
AGDRISK10
Lack of resources in PMO 
Scoring –  - 16 
Score 16  Score 16   A permanent PMO structure is in place but not all
posts are currently filled, with recruitment now
underway to start completing the team
 The PMO is being supported by colleagues in each
of the Councils in a number of work streams
78

Page 79

NO CHANGE IN SCORING   PMO undertaking a review of capacity and skill sets
in response to the changing requirements of the
Office to service the deliver the Programme.
AGDRISK11
Inadequate governance
arrangements to support
AGD delivery 
Scoring - 6 
NO CHANGE IN SCORING
Score 6  Score 6   In accordance with AGD governance, Ayrshire
Economic Joint Committee and Ayrshire Regional
Economic Partnership has been formed and regular
meetings are in place
 Scottish Government’s financial reporting
requirements have been implemented in the AGD
Governance document and Financial guidance
 Partner agreement between EAC, as Accountable
Body for the Deal, and North and South Ayrshire
Councils has been drawn up and terms agreed 
 PMO working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
 Partners working together with both governments to
keep under review the AGD Benefits Realisation Plan 
 Current change management process to be
reviewed with the governments and partners
 AGD is standing item on CEOs’ meeting agenda
AGDRISK12 - Monitoring &
Evaluation Framework is not
sufficiently defined 
Score – 6 
NO CHANGE IN SCORING
Score 6  Score 6   PMO is working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal which will be published in Spring 2024
and placed on the AGD web site. This will clarify
existing acceptable M&E arrangements. 
79

Page 80

AGDRISK13
Failure to attract commercial
interest in AGD 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   Undertake with communications and economic
development teams, a market campaign will be
developed, as part of Communication Plan and
target potential investors
 Communications Action Plan continues to be
developed and updated, including a pipeline of
project specific communications plans
 Regular briefings with a range of stakeholders 
 Wider Ayrshire Economic Strategy is now approved
by the Regional Economic Joint Committee and will
ensure wider growth ambitions for Ayrshire are
achieved
AGDRISK14
Programme not
communicated effectively to
stakeholders outwith
Governance structure 
Scoring 12 
NO CHANGE IN SCORING 
Score 12  Score 12   Communications Action Plan completed and
regularly updated, in conjunction with
communication teams. This includes reporting on
past and future communication activity AGD website
launched and to be reviewed in conjunction with
communications teams, in order to increase traffic
and sharing of AGD information
 AGD social media channels to be reviewed in
conjunction with communications teams, with
greater linkages made to activity related to the AGD
and its progress
 Regular briefings with a range of stakeholders via
AGD programme update to the Regional Economic
Partnership and Regional Economic Joint Committee
 Communications Protocol in place and reviewed and
updated annually, with activity regularly identified
and delivered with the support of communication
teams.
 Resource within AGD to market and promote project
activities and overall programme
80

Page 81

AGDRISK15
Supply phasing within
overall programme 
Scoring – 12 
NO CHANGE IN SCORING 
Score 12  Score 12   Engagement undertaken in 2022 with the
construction sector in order promote and explain the
potential of the AGD programme to local businesses,
so increase Invitation to Tender for future contracts.
 PMO regularly help facilitate and update
Procurement teams of the AGD programme and
relevant projects in terms of timescale for
development and delivery. This includes how to
manage expected peaks in programme activity and
need for contracts to be advertised and managed.
Market engagement through the Meet the Buyer
events with the next being held in the Autumn 2023
 PMO working with procurement in supporting  the
sharing of market intelligence and the phasing of
development activity
AGDRISK19
Loss of IT systems 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   PMO hosted by EAC and as such  supported by IT
recovery protocols and security systems of EAC to
limit risk and mitigation measures
 Corporate IT recovery protocol and security systems
limit the risk and mitigation measures
 Contingency Plan in place via EAC for the PMO, by
SAC for the portal, and for the AGD teams across
the three councils, by their respective employer
(e.g. EAC, SAC, NAC)
AGDRISK20
Failure to ensure AGD
projects align with a net zero
transition 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   PMO and Project Leads working with Scottish
Government to ensure the Deal is aligned with
Scotland’s transition to net zero carbon emissions
by 2045
 UK and Scottish Governments developed carbon
management guidance for the AGD, as well as other
City Region and Growth Deals in Scotland, which will
allow the carbon emissions impact of the
81

Page 82

programme and projects to be assessed then
minimised
 A carbon management process appropriate for each
project has been put in place to ensure any carbon
emissions impact is minimised via business case
process
 PMO working with both governments to identify
funding opportunities to support decarbonisation
 PMO is working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
NEW - AGDRISK21
Potential impact of
international events upon
cost of living crisis and
economic prosperity of
Ayrshire 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16   Regular engagement with Project Leads to highlight
any risks well in advance, so that the PMO can raise
with government, Regional Economic Partnership
and Regional Economic Joint Committee as
appropriate
 PMO working with Partners in undertaking a
Programme Review in response to the impact of
costs pressures upon the delivery of the
programme. 
 Regular review via monthly reports of outputs and
timelines for business cases at every stage of
development in the light of external events 
 Continued monitoring of external environment and
government relations
 Regional Economic Strategy approved in early 2023
and be supported by an emerging action plan
 Regional Economic Partnership will provide voice for
Ayrshire to press the case for government
intervention investment
 Incentives and other forms of assistance to
complement the AGD and stimulate greater
economic activity
82

Page 83

 Current change management process to be
reviewed with both governments and partners
 Regional Skills Investment Plan developed, with a
focus on its implementation via Ayrshire Skills
Group
 Robust data analysis shared amongst key partners
and stakeholders to reach common understanding
of local economic conditions, leading to early
identification of real threats and opportunities -
achieving consensus with partners and stakeholders
on strategic objectives for inclusive and sustainable
economic growth, with effective action planning and
monitoring
 PMO co-ordinated evidence across Deals and
submitted collective case via the Implementation
Plan update to both governments setting out impact
of increased costs or  reduced the scope/outputs
and time delivery if costs not met
 PMO developing a baseline approach to FBC which
will be shared with both governments and partners 
83