AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 20 NOVEMBER 2023
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL - 
PROGRAMME RISK REGISTER UPDATE (OCTOBER 2023)
PURPOSE OF REPORT
1. To advise the Economic Joint Committee on the update for the AGD
Programme Risk Register as of the end of October 2023. Please note this
is further update to that report to the 7 September 2023 Partnership Board.
RECOMMENDATIONS
2. It is recommended that Members agree the content of the:
(i) The updated Programme Risk Register dated October 2023
BACKGROUND
3. The Ayrshire Economic Joint Committee (AEJC) (dated 26 June 23)
approved the quarterly review and reporting of the AGD Programme Risk
Register as a separate item on future AEPB and AEJC meetings.
4. The attached (Appendix 1) provides the latest update of the Programme
Risk Register. This has been informed by the risk register of all projects
within the programme. The top scoring programme and project risks are
reported to the Chief Executives Group, Steering Group, AEPB and AEJC
on a regular basis via the sharing of the monthly reports.
MAIN REPORT
5. The PMO has undertaken further a review of the Programme Risk Register
in line with the recommendations of the AEJC. This has included reviewing
the nature of the risks, their RAG status/scoring, and in the mitigation
measures used to reduce the potential of risk. This review has been
informed by the P7 October Monthly Report (as considered elsewhere on
the agenda).
6. Further discussions have been held with the Government in order to

Page 2

explore the best way to manage the challenges partners are experiencing
on delivering key capital projects. Initial discussions have identified the
potential for the Programme to undergo a midterm review, in line with the
AGD Governance. This is referenced as a ‘Checkpoint Review’ (para 3.5
Governance Document v15 December 22). This states the following: 
A Checkpoint Review process will be developed and agreed with
partners and governments to examine both the Growth Deal
programme and component projects at key decision points in their
lifecycle. It will look ahead to provide assurance that projects can
progress successfully to their next stage. 
7. The Government has advised that the review should entitled as a
Programme Review 23/24 which will inform the financial year 24/25. The
process of the Review is still early in its execution. Further details of the
steps, scope, approach and timelines are provided elsewhere on the agenda
under the AGD Programme Update item. 
8. Therefore based on the Review at this point in time, no substantial changes
are yet proposed to be made to the Register in terms of the risks identified
and their RAG status. However amendments have been made to some of
the mitigation measures in reflection of the proposed undertaking of a
Programme Review of the programme and its projects. These changes are
highlighted ‘red underscored’ textual changes in the attached (Appendix 1) 
9. In the meantime the six risks identified with a ‘red’ RAG status still remain.
These are: 
(i) AGDRISK01 - Failure to achieve AGD programme objectives within
agreed budget
(ii) AGDRISK02 - Failure to provide accurate projections for programme
spend 
(iii) AGDRISK03 - Failure to drawdown full AGD funding
(iv) AGDRISK04 - Delays in development and approval of business cases
(v) AGDRISK10 - Lack of resources in PMO
(vi) AGDRISK21 - Potential impact of international events upon cost of living
crisis and economic prosperity of Ayrshire 
10. At a project level, individual reviews are still underway. These reviews will
inform the Programme Review where timings permit. Projects that are
expected to undergo reviews in the near future, and are likely to be subject
to change management include the Digital Programme (as reported
previously to the Board) , Spaceport (being considered elsewhere on the
agenda) and other key projects in the Prestwick cluster, AMIC and Moorfield.
Other projects that may be subject to re-scoping include Marine Tourism and
Hunterston. 
11. Collectively once the review of projects have been completed then the level

Page 3

of risk identified on the Programme Register should start to be reduced, in
particular for the ‘red’ risks (AGD RISK01-04) 
12. Finally discussions continue between the three Ayrshire Councils as the
funders to help de-risk issues around PMO resources (AGDRISK10).
Progress is being made on filling the current vacancy for the AGD
Programme Manager and Business Support Assistant. 
13. In conclusion it is considered that the Programme Risk Register continues
to provide a more realistic reflection of the state of the challenges the
programme are facing. ‘Behind the scenes’ senior management, project
leads are working towards reviewing the deliverability of both the programme
and individual projects so that they still meet the objectives and desired
outcomes of the Deal. This activity is being undertaken in consultation with
the Governments, so that we can all reach a satisfactory conclusion. Once
completed partners should start to see amendments in the Risk Register and
the de-risking of the risks identified with a ‘red’ RAG status. 
IMPLICATIONS 
14. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 15
2.Governance/Legal Yes  Para 18
3. Human Resources Yes  Para 19
4. Equality and Fairer Scotland Duty Yes  Para 20
5. Financial  Yes  Para 17
6. Risk  Yes  Whole paper
7. Community Wealth Building   No 
8. Net Zero   No 
ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
15. Inclusion is a key driver for the AGD. Deal business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
16. The Risk Register provides the framework for reviewing the challenges the
Deal needs to address and enables effective mitigation measures to be
undertaken that include meeting the headline Deal objective of delivering
inclusive growth. 
FINANCIAL IMPLICATIONS 
17. It is accepted by the Ayrshire Councils and the Government that risks
should be managed and mitigated where necessary in order to support the

Page 4

effective delivery of projects and the programme. 
LEGAL IMPLICATIONS 
18. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the recently revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2023. 
HUMAN RESOURCES IMPLICATIONS 
19. There are no immediate human resource implications arising from this
report. However for the risk associated with lack of resources in PMO to be
addressed there could be human resource implications. 
EQUALITY IMPACT ASSESSMENT 
20. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business
case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES 
Appendix 1: Updated Risk Register – October 2023
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk

Page 5

Appendix 1:
AYRSHIRE GROWTH DEAL UPDATED PROGRAMME RISK REGISTER (RISKS AND MITIGATIONS) – OCTOBER 2023 
RISK Current
Matrix and
Score
Proposed
Matrix and
Score
MITIGATION
AGDRISK01
Failure to achieve AGD
programme objectives
within agreed budget 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16   The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group in place
to monitor progress and to address any weaknesses
or issues that could impact on overall delivery 
 PMO developing monitoring and evaluation
processes to ensure overall objectives are captured
and any project failing to achieve and contribute to
these is flagged and issues addressed as quickly as
possible. This includes responding to increasing
costs of general capital works within the context of
the original funding made available by the
Government in 2019. Leading to potential to review
risks where evidence suggests insufficient funding
to undertake and complete projects in line with
expected outcomes.
 PMO are working with Partners in undertaking a
Programme Review in line with the AGD
Governance. 
 PMO undertake ongoing environmental analysis to
ensure programme objectives are relevant/valid as
well as maximised where relevant and new benefits
identified when materialising.
 Internal governance include regular reviews
undertaken by PMO with input from SROs, Project
Leads and Chief Executives to ensure AGD

Page 6

programme objective are met.
AGDRISK02
Failure to provide accurate
projections for programme
spend 
Scoring –  - 16 
NO CHANGE IN SCORING 
Score 16  Score 16   Issues will be escalated to CEOs, Regional Economic
Partnership and Regional Economic Joint Committee
as appropriate 
 PMO working with Partners in undertaking a
programme midterm Programme Review in order to
clarify accurate projections for project and
programme spend and delivery. 
 The Implementation Plan and Financial Plan have
been updated to take account of the compressed
funding.  Project Leads have sought to address
delays in gaining approved FBCs, by undertaking
reviews of projects to fit existing budgets, which are
shared with Finance Directors, the government and
wider partners. Revised project mitigation measures
seek to demonstrate how inflationary pressures will
be managed
 Business Case process monitored to ensure
streamlined pathway to approval enabling projects
to achieve FBC as quickly as possible to reach
project delivery and clarity on expected spend.
 PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs
and Finance Directors and ensure drawdown
projections align with delivery timescales
 OBCs/FBCs include an optimism bias factor as per
Treasury Green Book and AGD Governance
document
 Inflationary factor addressed through project
reviews e.g. re-scoping, phasing and reviewing
benefits
AGDRISK03
Failure to drawdown full AGD
Score 16  Score 16   PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs

Page 7

funding 
Scoring –   - 16 
NO CHANGE IN SCORING 
and Finance Directors and ensure drawdown
projections align with delivery timescales. This
includes PMO working with Project Leads, SRO’s and
S95’s to ensure projects can be realised and help
with change processes where necessary; and
undertaking effective communication with
Governments to ensure projects can be realised
 PMO working with Partners in undertaking a
Programme Review in order to clarify accurate
projections for project and programme drawdown
on AGD funding. 
 Achieve business case approval in line with latest
Deal Implementation Plan, and AGD Governance
document and, Finance guidance
 Annual review of Financial Plan and Implementation
Plan
 The Scottish Government’s financial reporting
requirements will be implemented
 Pivot projects proactively where possible in line with
need and opportunity
 Internal procedures, financial controls and
processes in place to mitigate this risk
AGDRISK04
Delays in development and
approval of business cases 
Scoring – 16
NO CHANGE IN SCORING 
Score 16  Score 16   Undertake focused engagement with SG and UKG in
order to help ensure SBC, OBC and/or FBC comply
with the Treasury Green Book and gain approval pin
line with AGD governance
 PMO working closely with Project Leads and Policy
Leads within UK and Scottish Governments to
support business case development and approval to
an agreed timeline. This includes exploring a
streamlined change process (pre-FBC) particularly
where budget constraints are sole driver of change.
In addition as part of a Programme Review,

Page 8

reschedule business case timescale for development
and delivery. 
 Project Leads have received Green Book business
case training
 Project Leads’ toolkit in place
 Other partners assisting in developing business
cases where capacity is low
AGDRISK05
Failure to capture accurate
baseline data 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9  Project Leads required to establish appropriate
economic, social and environmental baseline
information in business cases
 Establish and regularly review achievable outcomes,
output and targets as part of the development and
delivery of projects and realization of benefits in line
with the Benefits Realisation Plan 
AGDRISK06
Failure to deliver community
benefits from AGD 
Scoring – 6 
NO CHANGE IN SCORING
Score 6  Score 6   PMO and procurement managers from the three
Ayrshire Councils have developed a AGD
Community Benefit Tracker, a single mechanism to
monitor delivery of community benefits so that
remedial action can be taken if required
 Result from the AGD Community Benefits Tracker
system will be analysed and reported to the
Regional Economic Partnership and Regional
Economic Joint 
 PMO working with Project Leads to develop
consistent approach to embedding inclusive growth,
equalities, clean growth, and community wealth
building within business cases through the Annual
Performance Report
 Procurement working group has been established
and operates in order to support delivery of
community benefits which includes development of
a Community Benefits Tracker and coordination of

Page 9

procurement approaches so they support the
development and delivery of projects
AGDRISK07
Failure to deliver individual
projects within the AGD
programme 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   Regular dialogue/reporting around progress takes
place between PMO and Project Leads where issues
are raised in advance and if appropriate escalated
to government, Regional Economic Partnership and
Regional Economic Joint Committee, this includes
early discussions with both UK and Scottish
Government
 The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group and
Project Boards in place to monitor project
development, via monthly reports
 Partners are regularly reviewing the AGD Benefits
Realisation Plan every 6 months and reported to the
Regional Economic Partnership and Regional
Economic Joint Committee
 Current change management process incorporated
in the AGD Governance document and regularly
reviewed.
 PMO working with Partners in undertaking a
Programme Review. This will be informed by a
review of individual projects deliverability and
timescales. 
 Risk register in place for each project which is
regularly reviewed via monthly reports, quarterly
reports and when updating the Implementation Plan
 Project risk registers included in business cases
which are formally approved by government and
Regional Economic Joint Committee
 Management Information System in place and used
to track progress of projects against key milestones,
and reported via monthly and quarterly reports

Page 10

AGDRISK08
Inadequate recognition of
interdependencies and/or
knock-on impacts between
parts of the programme
leading to issues with
delivery and/or lost
opportunities 
Scoring – 9 
NO CHANGE IN SCORING
Score 9  Score 9   Programme meetings take place regularly between
PMO, Project Leads and partners to ensure 
interdependencies are recognised and considered;
and incorporated in approved business cases
 PMO working closely with project leads to ensure
interdependencies are fully articulated within the
project business cases and for the programme as a
whole.
 All forms of interdependencies are monitored and
managed to help enable the development and
delivery of all Deal projects
AGDRISK09
Lack of resource within
partner organisations to
deliver projects in line with
AGD programme 
Scoring – 9 
NO CHANGE IN SCORING
Score 9  Score 9   Formal approvals of Councils’ resources are now in
place for AGD projects
 Each Council has appointed staff and/or consultants
to support project development and delivery
 Each project currently has a Project Lead in place
 Partners including SE are providing additional
resource to relevant projects
 Resources committed to the delivery of the
programme, with further discussions underway to
explore how to deliver the recently approved
Regional Economic Strategy 
 Other funding streams is being explored to support
ongoing revenue costs
 Anticipated revenue streams will be subject to
constant review through the monitoring procedures
in place for AGD 
AGDRISK10
Lack of resources in PMO 
Scoring –  - 16 
Score 16  Score 16   A permanent PMO structure is in place but not all
posts are currently filled, with recruitment now
underway to start completing the team
 The PMO is being supported by colleagues in each
of the Councils in a number of work streams

Page 11

NO CHANGE IN SCORING   PMO undertaking a review of capacity and skill sets
in response to the changing requirements of the
Office to service the deliver the Programme.
AGDRISK11
Inadequate governance
arrangements to support
AGD delivery 
Scoring - 6 
NO CHANGE IN SCORING
Score 6  Score 6   In accordance with AGD governance, Ayrshire
Economic Joint Committee and Ayrshire Regional
Economic Partnership has been formed and regular
meetings are in place
 Scottish Government’s financial reporting
requirements have been implemented in the AGD
Governance document and Financial guidance
 Partner agreement between EAC, as Accountable
Body for the Deal, and North and South Ayrshire
Councils has been drawn up and terms agreed 
 PMO working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
 Partners working together with both governments to
keep under review the AGD Benefits Realisation Plan 
 Current change management process to be
reviewed with the governments and partners
 AGD is standing item on CEOs’ meeting agenda
AGDRISK12 - Monitoring &
Evaluation Framework is not
sufficiently defined 
Score – 6 
NO CHANGE IN SCORING
Score 6  Score 6   PMO is working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal which will be published in Spring 2024
and placed on the AGD web site. This will clarify
existing acceptable M&E arrangements.

Page 12

AGDRISK13
Failure to attract commercial
interest in AGD 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   Undertake with communications and economic
development teams, a market campaign will be
developed, as part of Communication Plan and
target potential investors
 Communications Action Plan continues to be
developed and updated, including a pipeline of
project specific communications plans
 Regular briefings with a range of stakeholders 
 Wider Ayrshire Economic Strategy is now approved
by the Regional Economic Joint Committee and will
ensure wider growth ambitions for Ayrshire are
achieved
AGDRISK14
Programme not
communicated effectively to
stakeholders outwith
Governance structure 
Scoring 12 
NO CHANGE IN SCORING 
Score 12  Score 12   Communications Action Plan completed and
regularly updated, in conjunction with
communication teams. This includes reporting on
past and future communication activity AGD website
launched and to be reviewed in conjunction with
communications teams, in order to increase traffic
and sharing of AGD information
 AGD social media channels to be reviewed in
conjunction with communications teams, with
greater linkages made to activity related to the AGD
and its progress
 Regular briefings with a range of stakeholders via
AGD programme update to the Regional Economic
Partnership and Regional Economic Joint Committee
 Communications Protocol in place and reviewed and
updated annually, with activity regularly identified
and delivered with the support of communication
teams.
 Resource within AGD to market and promote project
activities and overall programme

Page 13

AGDRISK15
Supply phasing within
overall programme 
Scoring – 12 
NO CHANGE IN SCORING 
Score 12  Score 12   Engagement undertaken in 2022 with the
construction sector in order promote and explain the
potential of the AGD programme to local businesses,
so increase Invitation to Tender for future contracts.
 PMO regularly help facilitate and update
Procurement teams of the AGD programme and
relevant projects in terms of timescale for
development and delivery. This includes how to
manage expected peaks in programme activity and
need for contracts to be advertised and managed.
Market engagement through the Meet the Buyer
events with the next being held in the Autumn 2023
 PMO working with procurement in supporting  the
sharing of market intelligence and the phasing of
development activity
AGDRISK19
Loss of IT systems 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   PMO hosted by EAC and as such  supported by IT
recovery protocols and security systems of EAC to
limit risk and mitigation measures
 Corporate IT recovery protocol and security systems
limit the risk and mitigation measures
 Contingency Plan in place via EAC for the PMO, by
SAC for the portal, and for the AGD teams across
the three councils, by their respective employer
(e.g. EAC, SAC, NAC)
AGDRISK20
Failure to ensure AGD
projects align with a net zero
transition 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8   PMO and Project Leads working with Scottish
Government to ensure the Deal is aligned with
Scotland’s transition to net zero carbon emissions
by 2045
 UK and Scottish Governments developed carbon
management guidance for the AGD, as well as other
City Region and Growth Deals in Scotland, which will
allow the carbon emissions impact of the

Page 14

programme and projects to be assessed then
minimised
 A carbon management process appropriate for each
project has been put in place to ensure any carbon
emissions impact is minimised via business case
process
 PMO working with both governments to identify
funding opportunities to support decarbonisation
 PMO is working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
NEW - AGDRISK21
Potential impact of
international events upon
cost of living crisis and
economic prosperity of
Ayrshire 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16   Regular engagement with Project Leads to highlight
any risks well in advance, so that the PMO can raise
with government, Regional Economic Partnership
and Regional Economic Joint Committee as
appropriate
 PMO working with Partners in undertaking a
Programme Review in response to the impact of
costs pressures upon the delivery of the
programme. 
 Regular review via monthly reports of outputs and
timelines for business cases at every stage of
development in the light of external events 
 Continued monitoring of external environment and
government relations
 Regional Economic Strategy approved in early 2023
and be supported by an emerging action plan
 Regional Economic Partnership will provide voice for
Ayrshire to press the case for government
intervention investment
 Incentives and other forms of assistance to
complement the AGD and stimulate greater
economic activity

Page 15

 Current change management process to be
reviewed with both governments and partners
 Regional Skills Investment Plan developed, with a
focus on its implementation via Ayrshire Skills
Group
 Robust data analysis shared amongst key partners
and stakeholders to reach common understanding
of local economic conditions, leading to early
identification of real threats and opportunities -
achieving consensus with partners and stakeholders
on strategic objectives for inclusive and sustainable
economic growth, with effective action planning and
monitoring
 PMO co-ordinated evidence across Deals and
submitted collective case via the Implementation
Plan update to both governments setting out impact
of increased costs or  reduced the scope/outputs
and time delivery if costs not met
 PMO developing a baseline approach to FBC which
will be shared with both governments and partners