AYRSHIRE ECONOMIC JOINT COMMITTEE
– 20 NOVEMBER 2023
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL - PROGRAMME UPDATE
PURPOSE OF REPORT
1. To advise the Economic Joint Committee members of the progress of the Ayrshire
Growth Deal (AGD) and the development of its component projects as at 31 October
2023 (Appendix 1). Please note this report provides a further update on the AGD
Programme and projects as reported to the 7 September 2023 Partnership Board.
RECOMMENDATIONS
2. It is recommended that Members agree:
(i) The updates provided in the attached report (as of 31 October 2023);
(ii) The progress across the Ayrshire Growth Deal Programme; and
(iii) Remit officers to liaise with both Governments to progress the projects having
regard to the updated position in line with the formal change requirements
contained within the Deal protocols;
(iv) Note the proposal for realignment of the reporting requirements, principally the
undertaking of the Annual Performance Report, Financial Plan, Implementation
Plan and Benefit Realisation Plan at the end of March 24, and onwards at the
same time ever year. All subject to agreement from the Government.
BACKGROUND
3. This report is an update on the progress made on the Ayrshire Growth Deal (AGD). It
has been prepared in line with the agreed governance structure and its commitment to
monitoring and reporting progress across all parts of the Deal’s programme on regular
basis.
4. A summary of the current status of the programme priorities and the development work
associated with individual projects is contained within the progress report attached to
this covering report. The report covers progress up to 31 October 2023 Please see
Appendix 1). The previous update was reported to the Ayrshire Economic Partnership
Board (AEPB), on 7 September 2023, and included progress up to the 25 August 2023.
This report and attachments includes further updates.
5. Please note that the reporting period has sought to align as much as possible with the
with the financial year’s quarters. However this report includes progress made in Q2

Page 2

and the start of Q3. Discussions are still underway with the secretariat for the AEPB
and Ayrshire Economic Joint Committee (AEJC) in order to improve alignment of the
quarters with the AGD programme reporting to members. 
6. The report considers the progress made on the Deal at both a programme and project
level. This includes an update on the Red/Amber/Green (RAG) status in regards to
meeting milestone timelines, scope, budget and overall progress. Supporting narrative
is provided where necessary. (Please see Programme and Project Introductions –
Appendix 1). 
MAIN REPORT 
7. The overall status for the programme is still remains as ‘red’. This reflects the continued
challenges project leads are meeting in addressing cost pressures within a fixed
budgets. 
8. In early October senior management from the three Ayrshire Councils held discussions
with the Government in order to consider the challenges the programme and key
projects were and continuing to face. In particular the deliverability of key capital
projects and exploring ways to mitigate the risks and blockages to delivery. Initial
suggestions indicate changes for the programme and key projects. 
KEY POINTS
Programme level 
9. At the programme level the initial outcomes from the October discussions have
identified the potential for the Programme to undergo a Review with a focus upon the
key capital projects which are likely to experience significant change. The AGD
Governance makes reference to the opportunity of undertaking a Checkpoint Review
at any key decision point in the lifecycle of the programme (para 3.5 Governance
Document v15 December 22). To confirm the extract from the Governance states the
following: 
A Checkpoint Review process will be developed and agreed with partners and
governments to examine both the Growth Deal programme and component
projects at key decision points in their lifecycle. It will look ahead to provide
assurance that projects can progress successfully to their next stage. 
10. The Government has advised that the review should entitled as a Programme Review
23/24 which will inform the financial year 24/25. The Review is expected to be
programme wide, with a likely focus on capital projects which are facing substantial
challenges and are estimated to undertake significant change. This means projects
which are currently in delivery, including those with a phased approach, are unlikely to
be affected by the review. For example all revenue projects are now being delivered,
whilst the i3 capital projects are in phased delivery. However where there is a proposal
for a reallocation of funds then a wider range or all projects may be affected. 
11. The approach and timing of the Programme Review is yet to be finalised. Early advice

Page 3

from the Government has expressed the need for a formal Letter of Intent to be
prepared by the Partnership seeking the Governments support in undertaking the
review. It is envisaged support from the Government will be subject to gaining
partnership agreement on the way forward for the Deal; continuous dialogue on any
changes proposed; and compliance with AGD Governance. 
12. The PMO will coordinate the Programme Review in consultation with Partners, in line
with the timetable below: 
Undertake Review of the Programme and
Capital Projects 
Nov-Dec 23
Share direction of travel and provisional
proposal with the Government as part of a
series of ‘conversations’ 
Jan 24
Prepare change management papers with a
Programme overview supported by summary of
project review papers
Feb 24
Present papers to the Partnership Board and
Joint Committee
Early 2024
(ready for the
new FY 24/25) 
Reporting Implications 
13. The proposal to undertake a Programme Review will have implications for the activities
captured in the Programme dashboard (Appendix 1 – page 3). In consultation with the
Government it is proposed to delay the preparation of the next Annual Performance
Report. Originally the reporting period was Oct to Sept each year and recently
amended to Oct 22 to Dec 23. This did not align with other key reporting requirements,
so the PMO are in discussions with the Governments to amend further the reporting
cycle so that it aligns with the financial year. This means the next Annual Performance
Report is expected to cover October 2022 – March 2024 (18 months). This change
would potentially allow the outcome of the Programme Review to be reflected in the
Annual Performance Report, updated Financial Plan 24/25 and updated
Implementation Plan 24/25. In addition we have been advised by Government that the
Benefit Realisation Plan can be reviewed once a year not twice as currently done. So
it is proposed that the BRP is updated at the end of March 24, so aligned with the
above mentioned reporting requirements. We are awaiting Government feedback on
the proposal to change the reporting cycle for the Annual Performance Report. 
Programme Financial Update 
14. The latest financial update (October 2023) included in the monthly report provides a
spend projection for the programme and individual projects. 
15. In comparing the now protected spend and drawdown from the grant allocation for this
financial year (2023/24) against the Grant Offer Letter 2023/24, it is noted that there
will be a significant shortfall in the drawdown of funds allocated for this financial year.
This is principally around capital projects such as Spaceport, Commercial Space and
i3 Flexi Space. Indications are that the approval of FBCs for the Spaceport project is
unlikely to be reached by the end of the financial year (Mar 24). An update on this

Page 4

project is provided elsewhere on the agenda. Commercial Space is unlikely to drawn
down on its allocation due to delays in raising further private section funding. Finally
progress on developing i3 Flexi Space is expected to slower than originally planned,
hence an expected reduction in drawdown. 
16. A shortfall in spend and drawdown is likely for the Community Wealth Building which
reflects the delay in the project being delivered fully across all three Ayrshire Councils.
A further shortfall is expected for the Ayrshire Skills Investment Fund projects due to
the recent approval of its FBC. The scale of the shortfall however are expected to be
minor when compared to the capital projects mentioned. Please see details below: 
Capital
Projects
Grant Offer Letter
23/24 (£m)
As at P6 return
(Sep 24) (£m)
Differences (£m)
Spaceport 2.855 3.355 +501
Commercial
Space
17.689 1.023 -16.666
I3 Flexi Space 2.339 0.951 -1.389
CoRE 0.300 0.300 0
TOTAL 23.184 5.629 -17.555 
Revenue
Projects
Grant Offer Letter
23/24
As at P6 return
(Sep 24) (£m)
Differences
Working for
Healthy
Economy
0.703 0.703 0
Ayrshire Skills
Investment
Fund
0.850 0.850 0
Community
Wealth
Building 
1.073 1.041 -32
TOTAL 2.626 2.594 -32 
17. As a total the Programme is expected to drawdown £8.223m as opposed to £25.810m,
a potential drop of £17.587m. Further details of the current financial position is set out
in paragraphs 32-35. 
18. The PMO continues to work with the SRO’s and project leads in addressing the
changes in expected spend profile and to ensure future projections are accurate. This
is reflected, as already raised, in the proposal to undertake a programme wide
Checkpoint Review in consultation with the Government and in line with the AGD
Governance. Further details on key projects including those under review are detailed
in paragraphs 20-26. 
19. In addition the PMO are continuing to explore ways to enhance the effective
management of projects within the context of the AGD governance. This includes

Page 5

drafting of a series of Supplementary Advice Notes in relation to the change
management process; development and management of Full Business Cases; and the
interpretation of the new Subsidy Control requirements. Delays in preparing these
Notes are due to staff shortages in the PMO (hence RAG status marked Red). Once
drafted the Notes will be shared with the SROs and project leads and in turn be
presented to the AEPB and AEJC. 
Project level 
20. Project leads continue to meeting the challenges of developing and delivering projects.
This is partly reflected in the changes in the spend projections for this financial year
and the meeting of milestones included in the attached summary sheets (e.g. business
case approvals). Below is a summary of the projects that are now ‘red’ in status from
the perspective of budget, scope and overall position. 
Budgetary Issues -
‘Red’ status 
Scope Issues - ‘Red’
status
Overall - ‘Red’ Status
Spaceport Digital Spaceport
Commercial Space  Digital
Digital   
21. Compared to the previous AGD Programme Report to the Board on 7 September 23,
there has been a reduction in the number of projects now rated with a Red RAG status.
Key changes relate to:
 Roads – good progress is being made between SAC/ARA and Transport
Scotland regarding the undertaking of a STAGs report.
 Marine Tourism - further review of the budgetary issues around the project
have been undertaken with clarity provided on the deliverability of the
Cumbrae, Arran and Ardrossan phases.
 ASTAC – progress being made on the development of a partnership
approach with organisations such as Scottish Enterprise (SE) and Ayrshire
College for this project. A further meeting is scheduled with Glasgow
Prestwick Airport in order to confirm siting of the ASTAC proposition. 
22. Project that still retain an  Overall ‘red’ status as follows:
23. Spaceport – extensive discussions between SAC, SG and UKG are ongoing in order
to overcome the complex challenges facing the project. A funding gap still exists and
recent discussions from the Government have highlighted further development of the
business case. An update is provided elsewhere on the agenda.
24. Digital Programme – At the last Board meeting on 7 September 23 an update was
provided on the Digital project and the consideration of options for the future of the
digital programme. The Board supported Option 5b ‘Building Digital Capital’ which
sought the de-scoping of the project and potential reallocation of funds across the Deal.

Page 6

The outcome of this meeting is being considered elsewhere on the agenda. 
25. Other highlights include:
 Commercial Space – Delays on the ground works for the Mangata
(Opportunity A) project is still expected. This is due to the need to complete the
Mangata’s series B funding round which is now expected to be by mid-
December 23. Due diligence is continuing to be followed by SE. On site works
is now expected to start in March 2024. 
 Community Wealth Building – The findings of the midterm review of the
project have been completed with a recommendation of extending the project
for another year. Details of this proposal will be shared with the Government
and then presented to the Board and Joint Committee as part of change
management. 
 AEP & AMIC – Change management papers are being prepared in line with
discussions undertaken with the Government. Once received they will be
presented to the Board and Joint Committee as part of the change management
process.
 Ayrshire Skills Investment Fund – Following the approval of the FBC in
August 23, a Delivery Model has been agreed with tenders now out for potential
operators to deliver the fund. 
26. Projects in delivery are; Community Wealth Building, Working for Healthy Economy,
Commercial Space, i3 Flexi Space (Phase 1) and i3 DPMC (Phase 1), with Ayrshire
Skills Investment Fund to be in delivery in the coming weeks.
COMMUNICATION UPDATE
27. In line with the AGD Communication Action Plan please find attached (in Appendix 2)
a copy of communication and engagement activity for all projects in the programme.
This includes Q2 Review of past activities and Q3 planned activities. 
IMPLICATIONS 
28. Eight implications have been considered in the preparation of this report. 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance/Legal Yes  Para 22
3. Human Resources  No 
4. Equality and Fairer Scotland Duty Yes  Para 23
5. Financial  Yes  Para 24-27
6. Risk  Yes  Para 28-29
7. Community Wealth Building   No 
8. Net Zero   No

Page 7

LEGAL IMPLICAITONS 
29. The legal implications arising from this report are covered through the Agreement
between Ayrshire’s councils and the Governance Document which was revised and
approved at the Joint Committee meeting on 8 December 2022. 
EQUALITY IMPACT ASSESSMENT 
30. There is no equalities impact relating to this report. Inclusion is a key driver for the
AGD. Project Leads will be required to complete an Equality Impact Assessment for
their project and append to the associated business case. Project Leads have received
Equality Impact Assessment training organised by the Scottish Government. Project
Leads are being encouraged by the PMO to link up as soon as possible with their
Equalities Officer within their authority who will be able to assist with this matter. 
FINANCIAL IMPLICATIONS 
31. The financial implications arising from this report are covered through the Financial
Plan approved at the Joint Committee meeting on 26 June 2023. The overall
cumulative total of Grant claimed for the Deal to date is £12.025m. 
32. The ninth claim since Deal signing (in the financial year 23/24 Qtr2) has been made to
the Scottish Government for c.£1.145m which is made up of expenditure associated
with the Community Wealth Building, Working for a Healthy Economy, Commercial
Space and i3 flexible Space. All claims made to date have been processed by
Government and payment received. The financial position statement for September
2023 within the progress report does not include the Q2 claim due to date report was
ran. (Appendix 1). 
33. At the time of preparing this paper the forecast drawdown reported to Scottish
Government for P7 2023/24 amounts to £8.223m, an anticipated decrease of £17.587m
for the year compared to a budget of £25.810 million. Projects are, however,
demonstrating commitment and incurring costs developing projects, with evidence of
£10.967m having been spent by councils to date ahead of project business cases being
approved. Once approval of the relevant business cases has been received from
government and the Joint Committee, the relevant costs will be claimed back from
government. 
34. Please note all capital and revenue project costs are being monitored and discussed
with regional partners, UK and Scottish governments. 
RISK IMPLICATIONS 
35. Strategic and operational risk registers continue to be developed, reviewed and
updated for the AGD Programme. This is being undertaken by the PMO with the
support of EAC audit. The Programme Risk Register has been updated in accordance
with the commitment to be reviewed every quarter as approved by the AEJC on 26

Page 8

June 2023. Details of the latest update is considered elsewhere on the agenda. 
36. In addition the risk registers for each project which are updated on a monthly basis
and reflected in the attached summary update (Please see Appendix 1). 
APPENDICES 
Appendix 1: Ayrshire Growth Deal Update of Programme and Projects
Appendix 2: Quarterly Communications Report as October 2023 
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and Ayrshire’s
Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and Ayrshire’s
Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal –Strategic Manager 
graham.saunders@east-ayrshire.gov.uk 
Implementation Officer: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager 
graham.saunders@east-ayrshire.gov.uk

Page 9

Appendix 1 
Ayrshire Growth Deal Update of Programme and Projects

Page 10

AYRSHIRE GROWTH DEAL
Monthly Report - 30 October 2023

Page 11

Programme Updates - Guidance (Milestones) 
RAG Status Programme Milestone Timeline
Status Overall Action Required 
Red
Delay to delivery timeline of key
milestone having a negative impact
on programme 
One or more milestones are RED
Immediate action required by senior
management and relevant Boards as
appropriate to address issues 
Amber
Milestone slipping against planned
date but not expected to impact
delivery of the programme 
No milestones are highlighted RED but at
least one is AMBER 
Management action is in place by PMO and/or
senior management to address issues 
Green On track to deliver milestone on time
or early  All milestones are GREEN  No management action required 
Complete  Milestone delivered  n /a  No management action required
Status against milestone timeline set out in Implementation Plan
Milestones – current financial year and next financial year
Programme Updates - Guidance (Risks)
This table illustrates the conversion of AGD RAG Status to Scottish Government RAG Status 
Source GREEN AMBER RED N/A
Ayrshire Growth Deal
RAG Guidance Note
with an AGD risk register score of
between 0-3
with an AGD risk register score of between
4-9
with an AGD risk register score of between 10-
14
with an AGD risk register score
of between 15-25  N/A
Source GREEN AMBER/GREEN AMBER/RED RED N/A 
Scottish Government
Guidance
Successful delivery
appears highly likely with
regard to time, cost and
quality and there are no
major outstanding issues
that at this stage appear to
significantly threaten
progress 
Successful delivery appears
probable however attention will
be needed in certain areas to
ensure risks do not develop into
major issues that will threaten
delivery 
Successful delivery appears
possible, but issues already exist
that require serious
attention. These appear resolvable
at this stage, but further action is
required
Successful delivery is in
serious doubt with
major risks or issues
apparent in a number of
key areas. Urgent
action is needed to
ensure these are
addressed 
Not listed
on
previous
Quarter

Page 12

Programme Dashboard – 30 October 2023                   Financial Summary 
Programme Milestones                                                       Programme Top Risks 
Overall Status
Last Period 
Overall Status
This Period    Total AGD
Grant £'000 
AGD Grant
Drawdown to Date
£'000 
%age of total AGD
Grant 
2023/24 AGD
Grant Allocation
£'000 
2023/24 Grant
Drawdown 
£'000
251,500 10,880 4.33% 25,810 295
Risk Likelihod Impact AGD Status SG Status Mitigating Action - UPDATE TO ALIGN WITH IMPLEMENTATION PLAN 
Failure to achieve AGD
programme objectives
within agreed budget 
4 4  16  16
The Regional Economic Joint Committee, Regional Economic Partnership, AGD Steering Group in place to monitor progress and to address any weaknesses or
issues that could impact on overall delivery. PMO developing monitoring and evaluation processes to ensure overall objectives are captured and any project
failing to achieve and contribute to these is flagged and issues addressed as quickly as possible. This includes responding to increasing costs of general capital
works within the context of the original funding made available by the Government in 2019. Leading to potential to review risks where evidence suggests
insufficient funding to undertake and complete projects in line with expected outcomes. PMO are working with Partners in undertaking a Programme Review
in line with the AGD Governance. PMO undertake ongoing environmental analysis to ensure programme objectives are relevant/valid as well as maximised
where relevant and new benefits identified when materialising. Internal governance include regular reviews undertaken by PMO with input from SROs, Project
Leads and Chief Executives to ensure AGD programme objective are met. 
Failure to provide
accurate projections
for programme spend 
4 4  16  16
Issues will be escalated to CEOs, Regional Economic Partnership and Regional Economic Joint Committee as appropriate. PMO working with Partners in
undertaking a Programme Review in order to clarify accurate projections for project and programme spend and delivery. The Implementation Plan and
Financial Plan have been updated to take account of the compressed funding. Project Leads have sought to address delays in gaining approved FBCs, by
undertaking reviews of projects to fit existing budgets, which are shared with Finance Directors, the government and wider partners. Revised project
mitigation measures seek to demonstrate how inflationary pressures will be managed. Business Case process monitored to ensure streamlined pathway to
approval enabling projects to achieve FBC as quickly as possible to reach project delivery and clarity on expected spend. PMO will regularly review, challenge
and agree financial profiling/phasing with Project Leads, SROs and Finance Directors and ensure drawdown projections align with delivery timescales.
OBCs/FBCs include an optimism bias factor as per Treasury Green Book and AGD Governance document. Inflationary factor addressed through project reviews
e.g. re-scoping, phasing and reviewing benefits 
Failure to drawdown
full AGD funding 
4 4  16  16
PMO will regularly review, challenge and agree financial profiling/phasing with Project Leads, SROs and Finance Directors and ensure drawdown projections
align with delivery timescales. This includes PMO working with Project Leads, SRO’s and S95’s to ensure projects can be realised and help with change
processes where necessary; and undertaking effective communication with Governments to ensure projects can be realised. PMO working with Partners in
undertaking a Programme Review in order to clarify accurate projections for project and programme drawdown on AGD funding. Achieve business case
approval in line with latest Deal Implementation Plan, and AGD Governance document and, Finance guidance. Annual review of Financial Plan and
Implementation Plan. The Scottish Government’s financial reporting requirements will be implemented. Pivot projects proactively where possible in line with
need and opportunity. Internal procedures, financial controls and processes in place to mitigate this risk 
Delays in development
and approval of
business cases 
4 4  
Undertake focused engagement with SG and UKG in order to help ensure SBC, OBC and/or FBC comply with the Treasury Green Book and gain approval pin line
with AGD governance. PMO working closely with Project Leads and Policy Leads within UK and Scottish Governments to support business case development
and approval to an agreed timeline. This includes exploring a streamlined change process (pre-FBC) particularly where budget constraints are sole driver of
change. In addition as part of a Programme Review, reschedule business case timescale for development and delivery. Project Leads have received Green
Book business case training. Project Leads’ toolkit in place. Other partners assisting in developing business cases where capacity is low 
Lack of resources in
PMO 
4 4  
A permanent PMO structure is in place but not all posts are currently filled, with recruitment now underway to start completing the team. The PMO is being
supported by colleagues in each of the Councils in a number of work streams. PMO undertaking a review of capacity and skill sets in response to the changing
requirements of the Office 
Potential impact of
international events
upon cost of living
crisis and economic
prosperity of Ayrshire 
4 4  
Regular engagement with Project Leads to highlight any risks well in advance, so that the PMO can raise with government, Regional Economic Partnership and
Regional Economic Joint Committee as appropriate. PMO working with Partners in undertaking a programme midterm Checkpoint Review in response to the
impact of costs pressures upon the delivery of the Programme. Regular review via monthly reports of outputs and timelines for business cases at every stage
of development in the light of external events. Continued monitoring of external environment and government relations. Regional Economic Strategy
approved in early 2023 and be supported by an emerging action plan. Regional Economic Partnership will provide voice for Ayrshire to press the case for
government intervention investment. Incentives and other forms of assistance to complement the AGD and stimulate greater economic activity. Current
change management process to be reviewed with both governments and partners. Regional Skills Investment Plan developed, with a focus on its
implementation via Ayrshire Skills Group. Robust data analysis shared amongst key partners and stakeholders to reach common understanding of local
economic conditions, leading to early identification of real threats and opportunities - achieving consensus with partners and stakeholders on strategic
objectives for inclusive and sustainable economic growth, with effective action planning and monitoring. 
PMO co-ordinated evidence across Deals and submitted collective case via the Implementation Plan update to both governments setting out impact of
increased costs or reduced the scope/outputs and time delivery if costs not met. PMO developing a baseline approach to FBC which will be shared with both
governments and partners.
Programme & Upcoming
Programme Milestones
Target Date RAG
Grant Offer Letter for 2023/24
received and agreed
30-Jun-23 Complete
2023 Annual Review of Deal
documentation approved
(Implementation Plan, Financial
Plan, Governance Document,
Communications Protocol) 
30-Jun-23  Complete
Review overarching Monitoring &
Evaluation Framework
30-Jul-23 
Red
Update Benefits Realisation Plan
and progress on performance
(every March) 
31-Mar-24  Green
Review and update Change
Management Process - draft and
approve Supplementary Advice
Note 1 
30-Jul-23  red
Review and update Business Case
process with a focus on Full
business Case requirements - draft
and approve Supplementary
Advice Note 2 
31-Aug-23  red
Review and update Subsidy Control
requirements for the AGD - draft
and approve Supplementary Advice
Note 3 
31-Aug-23  red
Review and update AGD web site
programme and project details  30-Sep-23  Amber
Key project interdependencies
articulated
31-Mar-24 
Green
Annual Conversation (2022/23) 31-Jan-24 Green
Annual Performance Report
approved and published (2022/23)
28-Feb-24 Green
Submission of statement of
compliance with conditions of
grant (2023/24) 
30-Apr-24  Green
Submission of statement of
compliance with conditions of
grant (2023/24) 
30-Apr-24  Green

Page 13

AGD PROJECTS - COMPLETE  Total Project Budget
£'000 
Government Grant
Funding £'000 
Government Grant
Claimed to date £'000  
Total Expenditure
17/18 to 20/21 £'000 
FINANCIAL POSITION STATEMENT
FINANCE YEAR 2023/24
QUARTER 2
HALO 9,000 7,000 7,000 10,524 MONTH Sep-23
9,000 7,000 7,000 10,524 
Government Grant 2023/24 £'000 
AGD PROJECTS - EXPECTED FBC/APPROVED FBC IN 2023/24 ~ GRANT OFFER
LETTER 
Total Project Budget
£'000 
Government Grant
Funding £'000 
Government Grant
Claimed to date £'000  
Total Expenditure
17/18 to 22/23 £'000
Total Expenditure
23/24 YTD
£'000  
Grant Allocation
TBC 
Grant Claimed
Q1 
Grant Claimed
Q2 
Grant Claimed
Q3 
Grant Claimed
Q4 
Total Grant
Claimed YTD 
Remainig Grant Available
to Claim in year
Spaceport Infrastructure 23,000 23,000 0 2,856 329 2,855 0 0 0 0 0 2,855
Commercial Space - Prestwick - Industrial & Hangar 29,000 22,000 825 1,160 730 17,690 0 0 0 0 0 17,690
i3 Flexible Business Space 15,000 11,000 307 545 0 2,339 65 0 0 0 65 2,274
Community Renewable Energy Project (CoRE) 24,500 17,000 0 976 74 300 0 0 0 0 0 300
Working for a Healthy Economy 5,000 5,000 1,118 1,118 293 703 117 0 0 0 117 586
Ayrshire Skills Investment Fund 3,500 3,500 0 0 0 850 0 0 0 0 0 850
Community Wealth Building Fund 3,000 3,000 1,335 1,335 343 1,073 113 0 0 0 113 960 
103,000 84,500 3,584 7,989 1,769 25,810 295 0 0 0 295 25,515 
AGD PROJECTS - FUTURE Total Project Budget
£'000
Government Grant
Funding £'000
Government Grant
Claimed to date £'000 
Total Expenditure
17/18 to 22/23 £'000
Total Expenditure
23/24 YTD
£'000 
Aerospace & Space Technology Application Centre (ASTAC) 11,000 5,000 0 728 0
Prestwick Infrastructure - Roads 17,000 12,000 0 472 20
Ayrshire Engineering Park (Moorfield) 16,000 12,000 0 826 43
Ayrshire Manufacturing Investment Corridor (AMIC) 23,500 23,500 0 390 28
i3 Digital Processing Manufacturing Centre 6,000 5,000 0 245 19
Hunterston Strategic Development Area 18,000 18,000 0 192 6
International Marine Science & Environmental Centre (IMSE) 10,500 6,500 0 134 8
The Great Harbour, Irvine Harbourside & Ardeer 14,000 9,000 0 460 109 
Marine Tourism 9,500 9,500 0 412 30
Digital Projects (name TBC) 14,000 14,000 0 76 0 
139,500 114,500 0 3,934 263
AGD TOTAL 251,500 206,000 10,584  22,447 2,032

Page 14

Project Updates - Guidance 
Project Stages Stage Definition Project Stages Stage Definition 
Define - SBC  Establishing the strategic context for the spending proposal  Implement  Business case has been approved by Joint Committee, and is being implemented 
Define - OBC  Establishing the preferred option  Deliver  Project is in place and monitoring and evaluation is in framework to assess if it is achieving its objectives 
Define - FBC  OBC approved by government, securing delivery plans and finalising detailed costing  Legacy
Project has resulted in mainstreaming or improvements to business as usual (impact) that is generated beyond
the funded period
RAG Status Programme Milestone Timeline Status Project Scope Status Project Budget Status Overall Action Required 
Red  Delay to delivery timeline of key milestone having a
negative impact on project completion date 
Significant change in scope expected, with no change
request in process 
There are projected or actual adverse variances with
recovery plan to be established 
One or more milestone, scope or budget indicators are
RED 
Immediate action required by senior management and
relevant Boards as appropriate to address issues 
Amber
Key milestone missed or projected to miss against
planned date but not expected to negatively impact the
original project completion date
Likely to be minor changes in scope within agreed
business case OR scope is still developing OR significant
change request not yet approved 
There are projected or actual adverse variances,
however a recovery plan is in place 
No milestone, scope or budget indicators are RED but at
least one is AMBER 
Management action is in place by PMO and/or senior
management to address issues 
Green  On track to deliver milestone on time or early  Scope has been set and on plan with agreed business
case AND/OR formal change request approved  There are no actual or projected variances  All milestone, scope and budget indicators are GREEN  No management action required 
Complete  Milestone delivered  Project complete and all items in scope delivered  Financial transactions relating to project have been
settled 
If all the milestone, cost, scope and benefits realisation
indicators are complete  No management action required 
Future  N/A  N/A  Business Case more than one year away from
submission  n /a  No management action required 
Milestones – current financial year and next financial
year PMO = Programme Management Office SBC = Strategic Business Case OBC = Outline Business Case FBC = Full Business Case 
Project Updates - Guidance (Risks)
This table illustrates the conversion of AGD RAG Status to Scottish Government RAG Status 
Source GREEN AMBER RED N/A
Ayrshire Growth
Deal RAG
Guidance Note  with an AGD risk register score of between 0-3  with an AGD risk register score of between 4-9  with an AGD risk register score of between 10-14  with an AGD risk register score of between 15-25  N/A 
GREEN AMBER/GREEN AMBER/RED RED N/A
Scottish
Government
Guidance
Successful delivery appears highly likely with
regard to time, cost and quality and there are no
major outstanding issues that at this stage appear
to significantly threaten progress
Successful delivery appears probable however
attention will be needed in certain areas to ensure
risks do not develop into major issues that will
threaten delivery
Successful delivery appears possible, but issues
already exist that require serious attention. These
appear resolvable at this stage, but further action is
required
Successful delivery is in serious doubt with major
risks or issues apparent in a number of key areas.
Urgent action is needed to ensure these are
addressed 
Not listed in previous Quarter

Page 15

Programme Summary – 30 October 2023 
Project Name  OBC Date  OBC RAG  FBC Date  FBC RAG
Project Scope
Status
Project Budget
Status
Project Overall
Status
Aerospace and Space Technology Application Centre 01/12/2023 Green 02/08/2024 Green Green Amber Amber
Spaceport Infrastructure 30/10/2021 Complete 30/09/2023 Red Green Red Red
Prestwick Commercial Space 30/08/2021 Complete 08/09/2022 Complete Green Red Amber
Prestwick Infrastructure Roads 28/02/2024 Green 31/10/2024 Green Green Amber Amber
Ayrshire Engineering Park (Moorfield) 30/09/2023 Amber 10/06/2024 Green Amber Amber Amber
Ayrshire Manufacturing Investment Corridor 30/10/2023 Amber 10/06/2024 Green Green Amber Amber
i3 Flexible Business Space 30/05/2021 Complete 30/09/2022 Complete Green Amber Amber
i3 Digital Processing Manufacturing Centre 31/05/2022 Complete 30/06/2022 Complete Green Amber Amber
HALO 31/05/2022 Complete 30/06/2022 Complete Complete Complete Complete
Community Renewable Energy 31/05/2022 Complete 20/12/2023 Green Amber Amber Amber
Hunterston 30/06/2024 Green 28/02/2026 Green Amber Green Amber
International Marine Science & Environmental Centre 30/06/2024 Green 28/02/2026 Green Amber Amber Amber
Marine Tourism 31/12/2023 Green 30/03/2026 Green Amber Amber Amber
Great Harbour 25/06/2021 Complete 31/03/2024 Green Amber Amber Green
Digital Infrastructure & Subsea Cable (TBC) tbc under rescope tbc under rescope red Red Red
Ayrshire Skills Investment Fund 30/04/2023 Complete 30/06/2023 Complete Amber Green Amber
Working for Healthy Economy 19/02/2021 Complete 22/02/2021 Complete Green Green Green
Community Wealth Building 12/02/2021 Complete 22/02/2021 Complete Green Green Green

Page 16

Project Updates – Space and Aerospace Programme 30 October 2023 
Project Name Project Lead Senior Responsible Officer
Aerospace & Space Technology Application Centre George Hunter 
Louise Reid Spaceport Infrastructure Derek Yuille
Commercial Space Derek Yuille
Prestwick Infrastructure Roads (Phase 1) Kevin Braidwood

Page 17

Aerospace and Space Technology Application Centre Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: George Hunter
Meeting with Scottish Enterprise head of place and team took place to agree/establish their wider role and responsibilities in supporting the project. Follow-up meeting took place with GPA to review the viable properties within the airport estate and establish the needs of SAC/Ayrshire
college for the facility. SAC presented the case for the area surrounding hanger 457 and reasoning around this. Also discussed were possible alternative sites, each located in close proximity to the terminal building with easy road/rail access links. Next steps include a further meeting
with GPA/AC/SAC with the aim of confirming site of ASTAC proposition and establish needs of all parties concerned regarding land/lease term/legals. Some milestones moved from green to amber.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 01/12/2023 Green AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC 02/08/2024 Green AGD/O/2 - Construction jobs created tbc tbc
Phases Target date  AGD/O/9 - Business Space Created tbc tbc
Phases Target date  AGD/O/13 - Visitors tbc tbc
Phases Target date  AGD/O/14 - SME's Supported tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC Submitted to Government 01/12/2023 Amber Completion of Phase 2 30/10/2029 Amber
Develop local partnership delivery model 01/12/2023 Green Final financial drawdown 31/03/2030 Amber
Complete final project design and procurement documentation 02/08/2024 Amber   
FBC approved by Joint Committee 02/08/2024 Amber   
Hand-over (Phase 1) to operational organisation 23/10/2026 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
A Viable and Sustainable Operational Funding (OPEX) model not achieved  5  4  20  
• Review existing models (UK- HIE/Perth College)
• Consultation Scottish Funding Council on academic funding support (OPEX)
• Consultation and developing model with Ayrshire College  20/12/2023 
Site for the ASTAC Facility not secured within GPA Estate offering airside
access/scale/offside access on acceptable terms  5  4  20  
• Secure early dialogue with Glasgow Prestwick Airport. Sidentify ASTAC spatial needs. Review options.
Develop a conceptual Plan for ASTAC campus 
20/12/2023 
ASTAC capital costs (CAPEX) exceed ASTAC approved budgets and other funding not
available  4  4  16  
• Complete early assessment of CAPEX costs and Prestwick build costs. Ensure adequate OB
provision. Make allowances for fees/legals inflation 
20/12/2023 
Securing aggreements and approvals requires additional time and programme delayed  4  4  16  
• Develop Programme with Steering Group. Align SAC and AC resources. Secure early SAC agreements and
internal reporting 
20/12/2023
Economic and social benefits and a positive BCR not delivered 
4 3  12    12
• OBC to include full EIA to Green Book/PMO template. Develop the Monitoring and Evaluation Framework.
• Complete in the OBC the Benefits Realisation Plan 
20/12/2023

Page 18

Spaceport Infrastructure Oct Project Overall Status
2023 Red
Project Update
Project Scope Status Green Project Budget Status Red
Monthly update - provide narrative Project Lead: Derek Yuille
There is a significant funding gap and additional funds are required if the project is to proceed. Discussions are ongoing with SE/SG/UKG to identify where funding can be sourced to meet shortfall, including proposals for SE to acquire land and reapportioning of digital funds. Recent
Government advice has required the approved OBC to be reviewed in light of the likely changes to the project, with a revised OBC and FBC being scheduled for Spring/Summer 2024.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/10/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 10 tbc
FBC 30/09/2023 Red AGD/O/2 - Construciton Jobs Created 135 tbc
Phases Target date  AGD/O/9 - Business Space Created 3200 sqm tbc
Phases Target date   Target tbc
Phases Target date   Target tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
RIBA Stage 3 30/04/2023 Red Airspace change agreed 31/03/2024 Red
Heads of Terms agreed to purchase land 20/06/2023 Red LSO/LSP/Range Licence requirements for first launch 30/11/2024 Red
FBC approved by Joint Committee 30/09/2023 Red Spaceport infrastructure complete 30/11/2024 Red
Construction Start 01/11/2023 Red First Commercial Launch 31/01/2025 Red
Safety Case 31/03/2024 Red Full project completed/final drawdown 31/03/2026 Red
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Failure to agree operating arrangement for Spaceport  5  5  25  
Avison Young have proposed Spaceport leasing and operating proposals for SAC and the Spaceport Launch
Service Operator Glasgow Prestwick Airport, however an agreement has yet to be reached that complies
with AGD capital funding requirements, local authority operating legislation and that mitigates any
financial and legal risks the Council may be exposed to where the Council has ongoing responsibility for
the Spaceport asset. 
31/12/2023 
Failure to obtain FBC approval  5  5  25  
A Full Business Case for the Spaceport requires the following to be in place: i) an agreement or Heads of
Terms over the land with confirmed budget source; ii) a costed deliverable infrastructure scheme with
budget in place and iii) an agreement or Heads of Terms on the operating arrangement for the asset
between the proposed owner of the asset, and the Launch Service Operator (LSO) Glasgow Prestwick
Operator 
31/12/2023
The model SE use to acquire land for spaceport may require a lease arrangement with SAC.
5 5 25  
The land acquisition/lease payments are not funded by AGD and the Council are not in a position to enter
any borrowing arrangements to fund this 31/12/2023
Failure to agree ownership of the new Spaceport infrastructure (eg. LVIF, apron, access road,
control point)  5  5  25  
Professional advice being sought by SAC on the legilities of SAC having any ownership rights to the
Spaceport. Advice previously confirmed operating arrangement scenarios.  31/10/2023
Project costs cannot be met by the existing AGD project budget
5 5 25  
Digital re-scoping exercise and proposal that build shortfall is supported by digital funds. SE will acquire
the land. 31/10/2023
Land owner may walk away due to lack of progress 4 5 20   SE to take forward discussions with landowner
04/01/2024
Risk the economic impact of the spaceport scores low given that the costs have significantly
increased but the net jobs has not changed 4 5 20   SE to commission further work on EIA 04/01/2024
SE requiring SAC to enter into legally binding agreement that links delivery of a new access road
from Sandyford Toll to SE’s purchase of the land 4 5 20  
Road deliverability uncertain until STAG complete.
04/01/2024

Page 19

Prestwick Commercial Space Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Red
Monthly update - provide narrative Project Lead: Derek Yuille
Site preparatory works/archaeology are now complete on Opp A (Mangata). Construction costs have not changed since last reported. The next significant milestone date is the completion of Mangata’s Series B funding round, where they are targeting c$100m investment. This had
been expected to conclude in July, but the completion date has been pushed out and the anticipated completion date is now December. SE require security for the value of the cost overrun before entering the Main Delivery Agreement (construction contract), and plan to carry
out updated due diligence prior to entering the Main Delivery Agreement. Therefore the delay to the funding and the design finalisations has a knock-on effect on entering the main build contract (expected Q4 23/24), and therefore the construction dates (Q1 24/25). Completion
now Q2 2026.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/08/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 570 tbc
FBC 08/09/2022 Complete AGD/O/2 - Construciton Jobs Created 150 tbc 
AGD/O/9 - Business Space Created 13900 sqm tbc
AGD/O/16 - Leverage (incl. LA, HE/FE, Private Sector and any other levereage) £55,000,000 tbc 
Target tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Planning permission 31/05/2023 Complete   
Handover 31/12/2025 Green   
Final financial drawdown 31/03/2030 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Failure of Mangata to resource additional funding  4  4  16  
• Closing Series B continues to prove challenging for Mangata, with timing now forecast
for early December (previously end September). However, Mangata have now signed a letter of intent
with a lead investor.
• Mangata are funding the business through Convertible Loan Notes until Series B close. This requires
them to continue to raise cash as current funding forecast lasts until October and includes the R&D
Grant payment. Mangata's forecasts show that they then anticipate some funding in October 2023,
before conclusion of Series B, expected
December. 
30/11/2023
Delays in provision of utilities 
2 2  4   4
• Site energy strategy to be put in place and early engagement in place across utilities companies
30/06/2024
Delays to design and build procurement processes
• Challenges to the process
• Availability of contractors  2  2  4  4
• External expert advisers have been procured to support the project team and will adhere to the
procurement policies of South Ayrshire Council
• Timescales have been set to ensure that there is a sufficient pool of suppliers to undertake the
activities and are interested in providing a competitive tender 
31/12/2023
Economic downturn
2 2 4  4
• Early engagement with market indicates that this investment is an important part of recovery and
engagement with market will be maintained 31/12/2024

Page 20

Prestwick Infrastructure Roads Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kevin Braidwood
Progress with the STAG is ongoing for the Ayrshire Growth Deal Roads Enabling project. Following approval to discard the history phased roads enabling projects a further report has been prepared and lodged for presentation to Cabinet detailing the work undertaken to
date with the next steps required to minimise delay in the programme and maintain momentum on the project.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 28/02/2024 Green AGD/O/2 - Construction Jobs Created 40 tbc
FBC 31/10/2024 Green AGD/O/7 - new roadway created 2 km tbc
Phases Target date  AGD/O/7 - roadway upgraded 1 km tbc
Phases Target date  AGD/O/7 - new roundabouts 1 tbc
Phases Target date  AGD/O/11 - upgraded roundabouts 3 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone status
Roads Enabling STAG Appraisal - Release of funds from Transport Scotland 01/03/2024 Green Procurement of contractor and commencement of works – Monkton 01/08/2025 Green
Planning and regulatory consent achieved – Spaceport (St Quivox) 30/09/2023 Red Completion of works – Spaceport (St Quivox) 31/12/2024 Red
Land assembly, site preparation, contract documentation – Spaceport (St Quivox) 31/12/2023 Red Completion of works – Enabling transport works 01/03/2026 Green
Planning and regulatory consent achieved – Monkton 31/12/2023 Red Planning and regulatory consent achieved - Gannet Link tbc Red
Roads Enabling OBC - TS & Council Approval 01/08/2024 Green Land assembly, site preparation, contract documentation - Gannet Link tbc Red
Land assembly, site preparation, contract documentation – Monkton 31/03/2024 Red Procurement of contractor and commencement of works – Gannet Link tbc Red
Procurement of contractor and commencement of works – Spaceport (St Quivox) 30/04/2024 Red Completion of works - Gannet Link tbc Red
Roads Enabling FBC - TS & Council Approval 01/03/2025 Green Final financial drawdown tbc Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Delays in release of enabling infrastructure funding from Scottish Government via Transport
Scotland  4  4  16    Commissioning of Enabling Roads STAG and OBC
• Effective scoping and ongoing liaison with Transport Scotland 
STAG Mar 2024
OBC Nov 2024 
Additional risk that any spaceport access road, delivered outside the STAG process is not only
not eligible for funding via the enabling infrastructure funds but also starilises available land for
the Growth Deal if access cannot be gained due to the Spaceport project working in isolation  4  4  16   
Continues liaison with Spaceport and requirement for this project to meet requirements of STAG process or
withdraw from the AGD enabling works fund. Requirement added for Spaceport project to ensure ongoing access to
the southern AGD lands for future development  30/09/2024 
Cost overruns  4  2  8    8
Project delivery will be led by a qualified project manager following established process for road construction
Costs will be monitored against progress and reported to the programme board Any additional costs will be
absorbed where possible by project redesign and/or re- prioritisation  31/12/2027 
Planning Approval - Dealys in planning due to capacity constraints, Objections to proposed
route, Planning programme and interrelation between overall Spaceport development and
enabling roads intrastructure 
3 2  6    6 
Programme recognised by Planning Department as a major project and given priority
• Prestwick Campus Masterplan incorporated in development of LDP2 via main issues report and subsequent
consultation with residents and other parties
• On-going community consultation
• Planning Strategy to be developed to ensure planning applications are interconnected 
31/12/2024 
Land assembly delays - Monkton & Spaceport  3  2  6   6  Early commencement of Land Owner negotiations 
31/12/2024

Page 21

Project Updates – Economic Infrastructure Programme 30 September 23 
Project Name Project Lead Senior Responsible Officer
Ayrshire Engineering Park (Moorfield) Fiona Paterson David McDowall Ayrshire Manufacturing Investment Corridor (AMIC) Gillian Morton
i3 Flexible Business Space Marnie Ritchie Neale McIlvanney i3 Digital Processing Manufacturing Centre (DPMC) Marnie Ritchie
HALO Gary Deans David McDowall

Page 22

Ayrshire Engineering Park (Moorfield) Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Fiona Paterson
1. Three public consultations for the Ayrshire Innovation Park pre planning application have now taken place. Feedback has been very positive in relation to both the Ayrshire Manufacturing Investment Corridor Project and the Ayrshire Engineering Park. Feedback from the
public consultations held will be included in the next iteration of the OBC.
2. The project team are currently preparing change request documentation in line with discussions held with Government over the past few weeks. A revised target date for the OBC submission for AEP & AMI is under consideration and will be provided ASAP.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/09/2023 Amber AGD/O/1 - New Jobs Created (Direct and Indirect) 203 tbc
FBC 10/06/2024 Green AGD/O/2 - Construciton Jobs Created 88 tbc
Phases Target date  AGD/O/9 - Business Space Created 7250 sqm tbc
Phases Target date  AGD/O/10 - Reduced vacant & derelict land 18.3 ha tbc
Phases Target date  AGD/OT/7 - Additional Investment (incl Foreign Direct Investment) tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC Approved by Government 30/09/2023 Amber FBC approved by Joint Committee 10/06/2024 Green
Tender for Building Services & Civil and Structural Engineers Services 02/05/2023 Green Commencement of infrastructure works 24/06/2024 Green
Design period inl community consultation & Environmen Impact Analysis commences 10/07/2023 Green Construction of terraced units and 500sqm unit 21/04/2025 Green
Planning permission secured 30/03/2024 Green Initial business premises operational 19/01/2026 Green
FBC endorsed by Government 20/05/2024 Green First tenants move in 01/02/2026 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Failure to Contribute to AGD programme objectives 
3 3  9    9
• Project will be managed by EAC in line with PRINCE 2 principles – any issues will be monitored, and
remedial action agreed to ensure delivery remains in line with the OBC projections.
• AGD Steering Group and other governance arrangements are in place to monitor progress and to
address any weaknesses or issues that could impact on overall delivery and project lead will be required to
provide regular project updates 
31/3/2027
Failure to provide accurate projections for project spend 
3 3  9    9
• Ensure sufficient optimism bias built into costing of the project
• Inflationary factor included in cost estimations
• Project will be managed by project team in line with PRINCE 2 principles – any issues will be monitored,
and remedial action agreed to ensure delivery remains in line with the BC projections
• Issues to be escalated PMO in first instance to agree remedial actions as appropriate
• Challenge panel led by PMO exists to review & scrutinise spend profiles 
31/3/2027
Delays in approval of business case 
3 3  9   9
• Project lead will work closely with PMO and policy leads within UKG and SG to support business
case development and approval to an agreed timeline  30/12/2025
Failure to deliver community benefits from the project 
3 2  6   6
• Procurement colleagues will support the tender process to ensure that community benefits are a key
aspect of the ITT and are in line with agreed AGD procurement principles  31/03/2027
Negative Publicity 
3 2  6    6
• A communications protocol has been agreed with both governments and will support shared
communications designed to build stakeholder confidence
• All project specific publicity will be dealt with in a coordinated fashion, sensitivity and empathy to
business climates at the time of publications will be carefully monitored 
31/3/2027

Page 23

Ayrshire Manufacturing Investment Corridor Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Gillian Morton
1. Three public consultations for the Ayrshire Innovation Park pre planning application have now taken place. Feedback has been very positive in relation to both the Ayrshire Manufacturing Investment Corridor Project and the Ayrshire Engineering Park. Feedback from the public
consultations held will be included in the next iteration of the OBC.
2. The project team are currently preparing change reuquests documentation in line with the discussions held with Governments over the past few weeks. A revised target date for OBC submission for AEP & AMIC is under consideration and will be provided ASAP.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/10/2023 Amber AGD/O/1 - New Jobs Created (Direct and Indirect) 189 tbc
FBC 10/06/2024 Green AGD/O/2 - Construciton Jobs Created 130 tbc
Phases Target date  AGD/O/9 - Business Space Created 5814 sqm tbc
Phases Target date   tbc tbc
Phases Target date   tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC Approved by Government 30/10/2023 Amber Phase 1 - works commence (Food & Drink Centre) 07/04/2025 Green
Planning application secured 28/02/2024 Green Phase 2 - works commence (speculative units) 02/02/2026 Green
FBC endorsed by Government 20/05/2024 Green Phase 1 - Initial premises operational 01/02/2026 Green
FBC approved by Joint Committee 10/06/2024 Green Phase 2 - Initial premises operational 09/11/2026 Green
Award & Commence Infrastructure - Procurement Contract 24/06/2024 Green First tenant secured 01/02/2026 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impac
t
Likelihood Score AGD
Status
SG
Status Mitigation Action
Construction costs in particular costs of materials significantly
increase 
4 4  16  
• The project team will work closely with colleagues in F+PM and the design consultants to develop a cost effective but efficient
building design. An affordability cap has been set as part of the appointment of the design team to ensure we work within the
parameters of the budget.  24/06/2024
Delay or failure delivering project due to concerns around transport
implications 
3 3  9    9
• Undertake all Transport Assessments and reports as required by LDP
• Continue to liaise with Transport Scotland
• Continue to progress all site options proposed in BC to ensure best site possible is chosen and the project can be delivered  30/05/2024
Delays in approval of business case 
3 3  9    9
• Project lead will work closely with PMO and policy leads within UKG and SG to support business case development and
approval to an agreed timeline 
30/03/2025
Failure to Contribute to AGD programme objectives 
3 3  9    9
• Project will be managed by EAC in line with PRINCE 2 principles – any issues will be monitored, and remedial action agreed to
ensure delivery remains in line with the OBC projections.
• AGD Steering Group and other governance arrangements are in place to monitor progress and to address any weaknesses or issues
that could impact on overall delivery and project lead will be required to provide regular project updates  31/03/2027
Failure to provide accurate projections for project spend 
3 3  9    9
• Ensure sufficient optimism bias built into costing of the project
• Inflationary factor included in cost estimations
• Project will be managed by project team in line with PRINCE 2 principles – any issues will be monitored, and remedial action agreed
to ensure delivery remains in line with the BC projections
• Issues to be escalated PMO in first instance to agree remedial actions as appropriate
• Challenge panel led by PMO exists to review & scrutinise spend profiles  31/03/2027
Health Pandemic/UK threat to business activity 
3 3  9    9
• AMIC building will be a strategic centre for businesses in times of crisis. The centre will provide support and direction for food and
drinks businesses as well as providing additional manufacturing space to allow supply to meet demand especially within the Dairy
Sector. 
31/03/2027

Page 24

i3 Flexible Business Space Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Marnie Ritchie
Phase 1 - Contractor Muir Group now due to commence works on site on 30 October. Photo call to mark start of works will take place on 9 November. Contractor advising estimated completion date as 29 July 2024. Phase 2 & 3 - Developing
specifications for Phase 2 with internal team of architects and surveyors.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/05/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 133 tbc
FBC 30/09/2022 Complete AGD/O/2 - Construction jobs created 83 tbc
Phase 2 FBC 25/02/2025 Green AGD/O/9 - Business Space Created 6000 sqm tbc
Phase 3 FBC 28/02/2027 Green AGD/O/10 - Reduced vacant and derelict land 20 ha tbc 
AGD/O/14 - Start-ups 5 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover 31/10/2024 Green Completion of Phase 2 30/10/2029 Green
Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/10/2025 Green Final financial drawdown 31/03/2030 Green
Phase 2 FBC approved by Joint Committee 25/02/2025 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2025 Green   
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover tbc Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Cost overruns  4  5  20  
• Develop and validate Project Brief and Specification
• Benchmark costs
• Ensure early infrastructure cost tested/ informed SI
• Provide Green Book compliant optimism bias allowances
• Provide for contingency
• Undertake value engineering
• Pursue additional funding sources 
Project delays and economic impact of Covid-19 and recovery  4  4  16  
• Early analysis has identified that the need for this project is unlikely to be diminished and in
fact may be even greater
• Project team will continue to focus on economic analysis and the development of
recovery plans will incorporate this as a key project for implementation as part of that wider
plan
• Work with contractors to devise solutions designed to minimise impact of social
distancing – such as different work patterns 
Failure to deliver anticipated outputs and outcomes 3 5 15  
• Ensure BC addresses sensitivity of outcomes
• Clear Evaluation & Monitoring Framework 
Demand – no interest from occupiers  3  5  15  
• Flexible design to maximise potential interest from occupiers
• Marketing and promotion of floorspace
• Continue to establish strategic relationship with national sector (including links with NMIS) 
Utilities cause delays e.g. surface water drainage connections, sub-station
requirements. 
3 4  12    12
• Utility companies to be approached and applications to be submitted at an early stage.
Despite this mitigation, issues have arisen on utilities for Phase 1, hence change to status to
reflect this. Contractor working with Scottish Water and current issue resolved. However
changed to amber /red status for ongoing project and future phases.

Page 25

i3 Digital Processing Manufacturing Centre Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Green Project Budget Status Amber
Monthly update - provide narrative Project Lead: Marnie Ritchie 
Phase 1 - University of Strathclyde are procuring the equipment, fit out, recruiting for resources and securing membership of companies which is taking longer than anticipated. Official launch planned for February 2024. Phase 2 - Centre: Analysis with
partners to be completed on Phase 1 to provide scoping parameters for phase 2.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 95 tbc
FBC 30/06/2022 Complete AGD/O/2 - Construction Jobs Created 84 tbc
Phase 2 OBC 31/12/2024 Green AGD/O/9 - Business Space Created 1749 sqm tbc
Phase 2 FBC 31/12/2025 Green AGD/O/10 - Reduced vacant & derelict land 20 Ha tbc 
AGD/O/16 - Leverage: (incl. LA, HE/FE, Private Sector and any other leverage) £19,810,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/07/2027 Green Reporting; outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 30/04/2028 Green
OBC Phase 2 approved by Government 31/12/2024 Green   
FBC Phase 2 approved by Joint Committee 31/12/2025 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/01/2026 Green   
Construction/Project completed and Handover (RIBA Stage 5-6; Construction & Handover 31/07/2027 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Capital costs are in excess of the budget.  4  4  16  
• Value engineering of works specifications
• Proactive review of funding opportunities to make the shortfall 
Failure to deliver anticipated outputs and outcomes  4  3  12    12
• Ensure BC addresses sensitivity of outcomes
• Clear Evaluation & Monitoring Framework
• Phase 0 and Phase 1 will establish the concept, build operational capacity and industry
interest.
• Conditions of grant will include expected outputs to measure the project’s success.
• Regular monitoring of centre’s performance through Supervisory Board 
Delays to procurement processes  3  4  12  12
• Seek early agreement on appropriate procurement routes
• Include anticipated tender packages within the Council’s Procurement Wave Plan
• Notify potential bidders of procurement opportunities at an early stage 
Ongoing Partnership commitment  4  3  12  12
• Memorandum of Understanding signed August 2021
• Collaboration Agreement signed March 2022
• Development and co-ordination of appropriate governance procedures
• Commitment to lease for Phase 1 location 
Failure to deliver community benefits  4  3  12   12 • Incorporate appropriate community benefits into contract terms and resource
appropriately.

Page 26

HALO June Project Overall Status
2023 Complete
Project Update
Project Scope Status Complete Project Budget Status Complete
Monthly update - provide narrative      Project Lead: Gary Deans   
Since last reporting HALO have continued to hold a variety of events and support a growing number of diverse business at its #RockMe trading floor. A key event was the successful Space and Trade Conference with speakers from Kate Rubins Astronaut NASA; / Jack Hillmeyer US Consul
General; and Dr David Alexander OBE Rice Space Institute Houston. Topics included the role of young people, the realtionship between HALO and USA, and future thoughts in education.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 232 182
FBC 30/06/2022 Complete AGD/O/2 - Construciton Jobs Created 256 265
Phases Target date  AGD/O/3 - safeguarded jobs 300 375
Phases Target date  AGD/O/15 - Private sector investment £15,199,000 tbc
Phases Target date  AGD/OT/7 - Public and private sector investment - Phase 2 £46,000,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due
date
Milestone
status                              
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Failure in financial management and reporting 
2 2  4    4
• The Board of HALO Kilmarnock Ltd receives monthly reports on all
financial aspects of the project and address any significant variances from
the approved full business case Robust financial systems and controls are
in place and the Board of HALO Kilmarnock Ltd retains oversight of these.
Copy of monthly report forwarded to PMO for BRP purposes. 
Reputational 
2 2  4    4
• Specialist advisers have been appointed to deal with media enquiries
and to communicate on any issue which is deemed to potentially impact
on the reputation of the project and the Board of HALO Kilmarnock Ltd

Page 27

Project Updates – Energy, Circular Economy & Environment Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Community Renewable Energy (CoRE) Diarmid Turnbull David McDowall
Hunterston Strategic Development Area 
Neale McIlvanney  Neale McIlvanney International Marine Science & Environment Centre
(IMSE)

Page 28

Community Renewable Energy Oct  Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Diarmid Turnbull
1. The CoRE Cabinet paper was presented to Cabinet on 4th October. Members approved the paper's recommendations, including a 12 month secondment of Professor Lawrence from UWS and match funded Senior Lecturer to assist with the development and delivery of CoRE.
2. The first Parnership Board meeting was held on 5th October. Members discussed and reviewed training and education opportunities to address the regional skills gap, demonstrator project themes, initial pathfinder proposals and scope for redesign of the Centre of
Excellence.
3. The Board also agreed the key themes for specialist working groups, which will be established to develop and deliver demonstrator projects across themes such as energy generation and sustainable transport. The Project Team will now formalise each of the working
groups and arrange initial meetings.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/05/2022 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 108 tbc
FBC Demonstrator Projects 20/12/2023 Green AGD/O/2 - Construciton Jobs Created 88 tbc
FBC Centreof of Excellence 30/05/2024 Green AGD/O/9 - Development Space Unlocked 3008 sqm tbc
Phases Target date   tbc tbc
Phases Target date   tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Formation of Management Board 30/05/2023 Green FBC for CoRE Innovation Centre 30/05/2024 Green
Engagement with Education and Skills Partners 30/08/2023 Green Commencement of Programme of Demonstrator Projects 01/02/2024 Green
Programme Business Case 15/07/2023 Green  tbc 
Review of CoRE Innovation Building 20/12/2023 Green  tbc 
FBC for Demonstrator projects 20/12/2023 Green  tbc 
Project Risks (top 5 risks and their status will be included in the monthly report) Target
Closure
Date
(dd/mm/yyy
y)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Construction costs, in particular cost of materials, significantly increases due to the
pandemic.  4  5  20  
• The project team will work closely with colleagues in F+PM and the design
consultants to develop a cost effective but efficient building design.
• An affordability cap has been set as part of the appointment of the Design Team to ensure we work within the parameters of the budget.  31/03/2030
Health Pandemic/UK threat to business security- the risk that a global health
pandemic
could shut down the country causing significant danger to life and the economic
stability of the country. 
3 5  15  
• The Centre of Excellence will be a national centre for businesses within the energy
and technology industry in times of crisis.
• The Centre will provide support and direction for these businesses as well as providing lab space to allow for any technology testing (such
as creating a new type of ventilator) to meet any demand. 
31/03/2030
Failure to attract investors and new businesses to locate within the Centre of
Excellence 
3 5  15  
• EAC will work collaboratively with specialist partners, including Scottish Enterprise
and Energy Technology Partnership, from an early stage to identify and work with potential investors
• The research carried out within the facility will be tailored towards particular technologies for which there is market interest in.
• Wider Ayrshire Economic Growth Strategy will be put in place to ensure wider growth ambitions for Ayrshire are agreed and be articulated
to stakeholders and investors.
• At a local level, the Council will work with existing businesses and start-ups to explore how they can benefit from the project, a potential arm
of which could be to locate into the research facility/incubator space 
31/03/2028
Delays in approval of business case (due to COVID-19, feedback from both Governments
may be delayed as their efforts will be focussed on critical services). Potential delays
to project delivery may impact on milestone achievements resulting in potential
reduction in realisation of benefits of AGD. 
3 5  15  
• Project Lead will work closely with PMO and policy leads within UKG and SG to
support business case development and approval to an agreed timeline.
• Ensure business case statistics, feedback and information is up-to-date while waiting for further feedback.  31/03/2027
Design Stages of the Centre of Excellence and the site take longer than expected with
the landowner (also due to COVID-19, there could be further delay as staff working
arrangements change).  3  4  12    12
• Clear deadlines and targets have been clearly set out with the landowner and design
team
• Ensure there is continuous collaborative working between the Council, design team and landowner.
• Ensure there is consistent communication between Project Team and landowner.  31/03/2025 
Delay in starting construction of the Centre (this could be down to delay in procuring
the contract/consultant delays due to COVID-19 or delays from design stage)  3  4  12    12
• Ensure that the project team work closely with procurement to ensure tender process
is efficient and successful contractor can be appointed.
• Hold initial meetings/calls with consultant and provide some element of flexibility in timescales for the construction of the Centre.
• Establish another risk register solely for the construction of the building.
• Hold 2 weekly/monthly meetings/calls with consultant thereafter to ensure progress is made. 
31/03/2025

Page 29

Hunterston Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Green
Monthly update - provide narrative Project Lead: Neale McIlvanney
Recent demand analysis commissioned by Peel Ports Group and Scottish Enterprise has highlighted the importance of providing advanced manufacturing space for SME/incubator and supply chain users at Hunterston, in comparison to an innovation centre or large scale
speculative commercial space. SE are currently leading on how this can be delivered with discussions at a recent Parc Board meeting in August 2023 and workshop with NAC in September 2023 to explore business case options. Options will be analysed with SE during
October and November. However, the case for AGD investment at Hunterston is now likely to be more focused on enabling the delivery of commercial space.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/06/2024 Green AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC 28/02/2026 Green AGD/O/2 - construction jobs 1204 tbc
Phases Target date  AGD/O/3 - safeguarded jobs tbc tbc
Phases Target date  AGD/O/7 - New or upgraded roads/junctions/cycle pathways tbc tbc
Phases Target date  AGD/O/16 - Leverage Funding (incl LA, HE/FE, Private Sector and any other
leverage £200,000,000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 30/06/2024 Amber Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 30/06/2029 Green
Completion of detailed design - RIBA Stage 3 31/03/2025 Green Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 31/03/2030 Green
Completion of technical design - RIBA Stage 4 31/12/2025 Green   
FBC approved by EJC 28/02/2026 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2026 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target
Closure
Date
(dd/mm/yy
yy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Unforeseen project complexities that require additional funding  4  4  16  
• Provide Green Book compliant optimism bias allowances
• Provide for contingency
• Project monitoring will track potential impacts and create ability to respond 
Ground conditions and historical legacy of site infrastructure create major burdens for
development  4  4  16   • Project team is working with Peel Port Group to understand the development
issues/infrastructure/utilities impacting onsite re-development 
Concept not supported by Partners and evidence of investment/market support not forthcoming  4  4  16  
• Project team/Peel Port Group/SE developing and promoting an investment model to secure major
inward investment plus academic partners and industry
• Dialogue being progressed around role, responsibilities and funding commitments
• MOU signed between NAC/SE/Peel and wider strategic proposition around blue economy and
Hunterston supported by partners 
Concept and Operational Management revised /amended 3 4 12  12 • Project team/Peel Port Group developing a partnership/investment model to secure inward
investment/academic partners and industry 
Other Development/Investment/ Proposals impact on capacity/deliverability  4  3  12    12 
• Project team/Peel Port Group seeking to collaborate with major partners to develop a clear investment
strategy/masterplan and investment led project proposition for AGD
• Peel Ports have gained planning approval of a site Framework to allow planning applications to
be considered 
Project fails to secure necessary consents 4 3 12  12 • Project team is in early dialogue with key regulatory partners and stakeholders

Page 30

International Marine Science & Environmental Centre Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Neale McIlvanney
The initial MoU between NAC and University of Stirling (UoS) to develop a proposition for IMSE, is now advancing to Collaboration Agreement stage. Recent interest from the Field Studies Council (FSC) to invest in FSC Millport as part of IMSE, offers the potential of a
tripartite Collaboration Agreement between NAC, UoS and FSC with the benefit of an existing operational partner and available land assets. A workshop has been arranged for October 2023 to develop the detail of the Collaboration Agreement, with the aim of partner
approval by end of 2023, to enable progress of an OBC during 2024. In addition, partners will continue to explore supporting Ardrossan regeneration as part of the IMSE programme.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/06/2024 Green AGD/O/1 - New Jobs Created (Direct and Indirect) 75 tbc
FBC 28/02/2026 Green AGD/O/2 - Construciton Jobs Created 58 tbc
Phases Target date  AGD/O/9 - Development Space Unlocked 1400 sqm tbc
Phases Target date  AGD/O/10 - Reduced and vacant derelict land 0.6 Ha tbc
Phases Target date  AGD/O/14 - Start-Ups 4 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 30/06/2024 Amber Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 30/06/2029 Green
Completion of detailed design - RIBA Stage 3 31/03/2025 Green Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage
7: Use) 31/03/1930 Green
Completion of technical design - RIBA Stage 4 31/12/2025 Green   
FBC approved by EJC 28/02/2026 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/03/2026 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target
Closure
Date
(dd/mm/yy
yy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Unforeseen project complexities that require additional funding  4  4  16  
• Provide for contingency
• Provide Green Book compliant optimism bias allowances
• Project monitoring will track potential impacts and create ability to respond 
Programme delay created within wider strategic delivery plan for Ardrossan  4  4  16   • Project team undertaking masterplanning process to identify all project requirements and spatial
needs 
Concept not supported by Partners  4  4  16  
• Project team developing a partnership model with leading academic partners and industry
• Dialogue being progressed around role, responsibilities and funding commitments
• An MOU has been signed to develop the project definition with University of Stirling 
Strategic need and consolidation in sector advises Co-Location with wider projects 4 3 12  12 • Project team developing a partnership model with leading academic partners and industry 
Concept and Operational Management revised /amended  3  4  12   12 • Project team developing a partnership model with leading academic partners and industry 
Project cannot secure necessary consents  4  3  12   12 • Project team in early dialogue with key regulatory partners and stakeholders to address any
concerns

Page 31

Project Updates – Tourism Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Marine Tourism Kathleen Dow Neale McIlvanney Great Harbour Kasia Smith

Page 32

Marine Tourism Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kathleen Dow
Marine Tourism Programme Business Case scope of change in progress to respond to ScotGov feedback and covering increased scale of the Cumbrae project, viability analysis of the Ardrossan Project and reduced scale of the Arran Project. Timeframes for submission and review
of the updated PBC and Cumbrae OBC (target Dec 2023 to be discussed with PMO). Cumbrae Project - OBC complete to be submitted with updated PBC. Cumbrae Marina operator development and procurement plan and permissions and consents plan prepared and awaiting
mobilisation upon approval of OBC. Millport Flood Prevention Scheme off-shore breakwaters under construction and to be completed by spring 2024, enabling the marina works to proceed. Investigations to remove the timber section of Millport Pier progressing with
Harbours/Floods Teams, to align marina and pier interdependencies to minimise risks ie costs and time delays. Exploring opportunities related to the removal of Millport pierhead buildings and requirements of the marina onshore spatial needs and facilities. Arran Project - a re-
scope of options with stakeholders has identified a technically and financially viable solution at Lamlash. This is under further development as part of the re-design of the Programme Business Case.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 31/12/2023 Green AGD/O/1 - New Jobs Created (Direct and Indirect) 30 tbc
FBC 30/03/2026 Green AGD/O/2 - Construciton Jobs Created 81 tbc
Cumbrae 30/03/2026 Green AGD/O/9 - Development Space Unlocked 6 Ha tbc
Arran 28/02/2026 Amber AGD/O/10 - Reduced and vacant derelict land 0.1 Ha tbc
Ardrossan 28/02/2027 Red AGD/O/13 - increase in visitors(day and night) 100000 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 31/12/2023 Green Construction/Project completed and Handover (RIBA Stage 5-6: Construction &
Handover) 31/01/2027 Green
Completion of detailed design - RIBA Stage 3 31/12/2024 Green Operating project (RIBA Stage 7) and reporting 30/07/2027 Green
Completion of technical design - RIBA Stage 4 and issue of tender 30/08/2025 Green   
FBC approved by Joint Committee 30/03/2026 Green   
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 31/07/2026 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure
Date
(dd/mm/yyyy) Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Changes to capital costs or inappropriately quantified cost provisions or increasing costs
that reduce scope of marina projects  5  5  25  
• Detailed technical studies in place to inform design
• Design team includes a cost consultancy and detailed assessment of contingency and
optimism bias is in place
• Regularly review viability of each project. Consider what is possible within budget.
31/3/26 -
Dependent Upon PBC
approval concluded
at OBC - finalised in
detailed at FBC
Development agreement and market economy investor principle for Ardrossan fails to
secure support  5  4  20  
• Project team taking legal advice in terms of subsidy control and agreements will be based on
commercial lease terms required for projects.
31/3/26 -
Dependent Upon
OBC approval
concluded at FBC
Site/ground conditions are inadequate to provide cost certainty  5  3  15   • Full SI/GI and bathy surveys will be undertaken at an early stage in project
development
Dependent Upon
OBC approval
concluded at FBC
Agreement on technical approach to quays/pontoons and land connections cannot be
agreed with stakeholders  5  2  10   10
• Development of design / layouts / connections advanced with stakeholders / partners. Dependent Upon
OBC approval
concluded at FBC
Agreements including Development and Operating Agreements between commercial
partners and community interest company cannot be secured  5  2  10   10
• North Ayrshire Council seeking to advance formal Development and Operating
Agreement between partners/operators and agree a joint approach. Stakeholder
engagement maintained throughout programme.
31/3/26 -
Dependent Upon
OBC approval
concluded at FBC

Page 33

Great Harbour Oct Project Overall Status
2023 Green
Project Update
Project Scope Status Amber Project Budget Status Amber
Monthly update - provide narrative Project Lead: Kasia Smith
The Great Harbour Masterplan and related Consultation Report are completed and approval will be sought from Cabinet in Dec'23 and from Planning Committee in early 2024, following an elected members briefing in Nov'23. Consultants are working on RIBA Stage 3 design
for Phase 1 Coastal Hub (Beach Park area) for completion and Gateway approval in early December. The Beach Pavilion building is the subject of a Market Feasibility Study to establish the viability of a re- development model with a community hub / restaurant. A
procurement appraisal has been carried out regarding the appointment of consultants for the Phase 2 -Maritime Mile and for the contractor for the Phase 1 - Coastal Hub. The existence of title burdens related to the Harbour Master's Office (HMO) is impacting on progress of
plans for the building. Notes of interest have been received from private food and drink operators and from a social enterprise for the HMO and these are being considered. A Memorandum of Understanding between the Scottish Maritime Museum and the Council is being
prepared to formalise the partnership in order to progress Phase 3 of the Great Harbour - the Maritime Heritage Hub.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 25/06/2021 Complete AGD/O/1 - New Jobs Created (Direct and Indirect) 145 tbc
FBC 31/03/2024 Green AGD/O/2 - Construciton Jobs Created 99 tbc
Phase 1 FBC 31/03/2024 Green AGD/O/9 - Development Space Unlocked 9800 sqm tbc
Phase 2 FBC 31/10/2024 Green AGD/O/10 - Reduced and vacant derelict land 6Ha tbc
Phase 3FBC 31/03/2025 Green AGD/O/16 - Leverage Funding (incl LA, HE/FE, Private Sector and any other
leverage £4,000,000.00 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
FBC approved by Joint Committee 31/03/2024 Green Statutory Consents 30/06/2024 Green
Completion of detailed design - RIBA Stage 3 31/12/2024 Green Completion of technical design - RIBA Stage 4 30/05/2024 Green
Construction/Project Start (RIBA Stage 5: Manufacturing & Construction) 15/05/2024 Green Completion of Construction Tender 31/08/2024 Green
Construction/Project completed and Handover (RIBA Stage 5-6: Construction & Handover) 31/10/2025 Green Internal sigh-off of FBC (NAC Cabinet) 30/09/2024 Green
Reporting: outputs/outcomes/CWB incl AGD Evaluation/Monitoring (RIBA Stage 7: Use) 31/10/2026 Green FBC update to Joint Committee Phase 2 31/10/2024 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Increase in capital costs associated with changing scope or inappropriately
quantified cost provisions  5  3  15  
• Cost estimates based on current market
• Detailed technical studies to inform design and a fully detailed/itemised cost plan
• Project management established to monitor costs
• Optimism bias built into costings
• Future design team to include cost consultancy
• Additional internal and external funding bias 
Economic downturn as a result of Covid-19  3  3  9    9
• Robust project management in place to analyse impact on this project and wider sector and focus will be
placed on this project as an important element of the recovery agenda in Ayrshire
• Project team will work with contractors to understand the impact of social distancing on the labour force but
expected to be minimal given this is land based
• Continue economic analysis and development of recovery plans will be implemented
• Robust project scoping should continue to ensure the facility meets needs 
Project outcomes, including inclusive growth and reducing
inequalities, fail to be delivered  4  2  8    8
• AGD PMO is currently working with project leads to develop a consistent approach to ensure inclusive growth,
equalities and community wealth building outcomes are embedded in each AGD business case. This approach will
ensure explicit commitment to how the project will achieve inclusive growth and reduce inequality 
Technical approach to quays/pontoons and land connections cannot be
agreed with key stakeholders  4  2  8    8
 Development of Partnership/Operator Plan and detailed GANTT Programme  ensuring programme allows time for
engagement and approvals
• PPiP route minimises risks and ensures full engagement with statutory bodies and community
• NAC in discussion with Harbour Authority
• Development Briefs drafted for Great Harbour

Page 34

Project Updates – Digital Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Digital Infrastructure & Sub Sea Cable (TBC) Simon Yeardley Louise Reid

Page 35

Digital Infrastructure & Subsea Cable (TBC) Oct Project Overall Status
2023 Red
Project Update
Project Scope Status red Project Budget Status red
Monthly update - provide narrative Project Lead: Simon Yeardley
Following on from the Partnership board meeting held on the 7th of September where endorsement of scope option 5b was given by the board a change request will now be made to the (AEJC) in November 2023. Where option 5b has been
identified as the preferred option, two funding scenarios will be presented:
I) Scenario 1: Available funding is split amongst lead authorities based on their AGD contribution and settlement, with Lead Authorities prioritising how spend is then apportioned across AGD capital projects, or:
ii) Scenario 2: Regional partners allocate funds and prioritise projects based on regional economic benefits realised. It is proposed that funding from the de-scoped
Subsea Cable and Infill projects will be apportioned to in train AGD projects identified by the key SRO's as having key connectivity and infrastructure requirements and where there is a risk of stalling or failure to deliver due to lack of sufficient funding.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC tbc under rescope AGD/O/1 - New Jobs Created (Direct and Indirect) tbc tbc
FBC tbc under rescope AGD/O/2 - Construciton Jobs Created tbc tbc
Phases Target date  AGD/OT/1 - Job levels (new and maintained) tbc tbc
Phases Target date  AGD/OT/3 - Digital Usage patterns tbc tbc
Phases Target date  AGD/OT/7 - Additional investment (incl Foreign Direct Investment) tbc tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Report on Re-scope exercise to Partnership Board 27/04/2023 Complete   
Joint Committee approve re-scope of project 22/05/2023 Complete   
AEJC approve re-scope of project (Mtg date tbc) 30/10/2023 Amber   
change management process applied 30/11/2023 Amber   
Project Completion 30/09/2026 Amber   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action
Cost overruns 
2 2  4    4
• Rescoping exercise has concluded and identified a valid option that can be delivered by
reprioritisation of current budget to in train AGD projects
• Robust contract management in place
• Appropriate procurement procedures followed and optimism bias built into business case  30/10/2023
Failure to reach consensus on project re-scope option 
2 2  4  4
• Stakeholder engagement
• Re-scope proposal scope 5b approvals and approved by Partnership Board via
established AGD governance  30/10/2023
Resource availability 
3 2  6   6
• Effective deployment of resource to support delivery of the project 
30/09/2026

Page 36

Project Updates – Regional Skills & Inclusion Programme 30 September 2023 
Project Name Project Lead Senior Responsible Officer
Ayrshire Skills Investment Fund Laura Neill Neale McIlvanney Working for Healthy Economy

Page 37

Ayrshire Skills Investment Fund Oct Project Overall Status
2023 Amber
Project Update
Project Scope Status Amber Project Budget Status Green
Monthly update - provide narrative Project Lead: Laura Neill
The FBC has been endorsed by SG and was approved by the Ayrshire Economic Joint Committee in August 2023. Plans for delivery are emerging through ASIF sub-committee with agreement on the Delivery Model with intention to consider proposals from Ayrshire College, University
of the West of Scotland and Employer Grant applications in November 2023. The Employer Grants Programme was launched in October inviting employers to identify training requests to support priority groups within priority sectors.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 30/04/2023 Complete No of people benefiting from in work skills development 500 tbc
FBC 30/06/2023 Complete No of people benefiting from pre-employment upskills 500 tbc 
People benefiting from accredited training 300 tbc
No of businesses benefiting from employees with improved skills levels 300 tbc
No of participants progressing to living wage opportunities 200 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
OBC approved by Government 25/07/2023 Complete 1st annual review 30/06/2024 Green
FBC endorsed by Government 25/08/2023 Complete complete mid-programme evaluation 31/03/2025 Green
FBC approved by Joint Committee 07/08/2023 Complete End of programme/final drawdown 31/03/2027 Green
Development of guidance for fund applicants 30/06/2023 Complete quarterly application deadlines  Green
1st call for proposals 01/07/2023 Complete   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impact Likelihood Score AGD
Status
SG
Status Mitigation Action 
Project delays due to Covid-19  5  5  25  
• Early analysis identifies that the need for this project may be greater as a result of
Covid-19
• Continued economic analysis and development of recovery plans should be implemented and
robust project scoping should continue to ensure the proposal meets needs 
Programme does not secure sufficient partner buy in to ensure an effective set of
interventions are designed and funded  1  1  1  
• Early establishment of Regional Skills Board with strategic oversight
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit
and satisfactory progress 
Failure to deliver anticipated impacts across the region in terms of Inclusive
Growth 
1 1  1  
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit
and satisfactory progress
• The partnership will conduct a mid-programme evaluation to check the direction of travel is still correct 
Disadvantaged residents do not see tangible benefits from projects  1  1  1  
• Applicants to the fund will be required to detail how delivery against inclusion targets will be
assured
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit
and satisfactory progress 
Inadequate project management results in failure to delivery agreed outcomes  1  1  1  
• The Regional Skills Board will provide expert advice on what should be supported
through the fund
• Adopt programme and project management best practice
• These arrangements will be reviewed on an annual basis to ensure they remain fit for purpose
• The Steering Group will conduct a mid-programme evaluation and adjust project activity as
appropriate

Page 38

Working for Healthy Economy Oct Project Overall Status
2023 Green
Project Update
Project Scope Status Green Project Budget Status Green
Monthly update - provide narrative Project Lead: Laura Neill
We continue to monitor progress to ensure effective delivery across Ayrshire. Working for a Healthy Economy continues to be delivered across Ayrshire to help individuals manage and improve their health to progress to or sustain employment. In
September 2023 the following individuals were supported:
• 45 individuals were supported in September 2023 • Of the individuals completing the services to date there has been a 26.9% improvement in overall health and wellbeing
• On measuring anxiety, a 36.4% improvement in anxiety levels has been achieved • Depression levels experienced have improved by 45.3%
We continue to monitor progress to ensure effective delivery across Ayrshire. A range of events and ongoing promotional activities has been undertaken to achieve the figures reported above.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 19/02/2021 Complete No of people accessing assessment & report 960 tbc
FBC 22/02/2021 Complete No of people accessing full management support via telephone 1600 936 
No of people accessing full case management support delivered face to face 3838 282
No of people returning to work 1157 77
Unemployed residents supported 4629 tbc
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Evaluation commences 30/06/2022 Green End of programme/final drawdown 31/03/2027 Green
Year 3 targets achieved 31/03/2024 Green   
Year 4 targets achieved 31/03/2025 Green   
Year 5 targets achieved 31/03/2026 Green   
Year 6 targets achieved 31/03/2027 Green   
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Impac
t
Likelihood Score AGD
Status
SG
Status Mitigation Action 
Implementation: Over demand or lack of demand  5  5  25  
• Proposed targets are based on delivery experience across Scotland and the experience of delivering a
case management service in North Ayrshire recently
• The proposal as it stands is designed to remove barriers to accessing this service. In the event of over
demand, referral criteria can be set to reduce demand
• Project Board has discussed geographical disparity between geographies and agreed mitigation action. Agreed
to review again in October. 
Project delay and macro-economic impact of Covid-19 and recovery  5  5  25  
• Early analysis identifies that the need for the project is unlikely to be diminished – in
fact may be greater
• Continued economic analysis and development of recovery plans should be implemented and robust
project scoping should continue to ensure proposal meets needs 
Unforeseen complexities that require additional funding  1  1  1  
• Provide for contingency
• Provide Green Book compliant optimism bias allowances
• Similar project has been delivered previously
• Project monitoring will track potential impacts and create ability to respond 
National programmes are introduced which result in duplication  1  1  1  
• Closely monitor national developments and build in flexibility to contracting arrangements to allow us to
change course at short notice if national provision is introduced that duplicates provision. 
Failure to deliver anticipated outputs and outcomes. Failing to achieve more
inclusive growth and/or reduce poverty by increasing the income of people in
deprived areas or protected characteristic groups. 
1 1  1  
• Closely monitor national developments and have built in flexibility to contracting
arrangements to allow us to change course at short notice to respond to programme impact
• Covid-19 impacts on specific groups will be assessed. Early indications are that young people, females, those
with health issues or disabilities will be disproportionately impacted by recession, therefore more targeted 
Implementation: End of project ‘cliff edge’ 1 1 1   • Would hope to influence the national policy around occupational health services, as a legacy of the programme 
Appointed contractor could be impacted negatively by Covid-19 1 1 1   • As part of procurement process, robust checks have been made on financial standing of delivery organisations

Page 39

Project Updates – Community Wealth Building Programme 30 September
2023 
Project Name Project Lead Senior Responsible Officer
Community Wealth Building Emma McMullen Neale McIlvanney

Page 40

Community Wealth Building Oct Project Overall Status
2023 Green
Project Update
Project Scope Status Green Project Budget Status Green
Monthly update - provide narrative Project Lead: Emma McMullen
The programme is progressing well having now surpassed the headline target of supporting over over 900 unique enterprises with CWB in the Ayrshire region. In addition to daily delivery of key programme outputs, the programme also supported a Meet the Buyer |
Ayrshire event hosted in East Ayrshire during the Ayrshire Chamber business week to help progress the procurement pillar outcomes of the programme. Most recently, Fair Work Ayrshire coordinated and hosted a job fair at Ayrshire College which was attended by 385
jobseekers. 27 businesses collaborated on the day, including anchor institutions such as the NHS, Police, SF&RS, Ayrshire College, DWP, NAC and EAC, and wider business stakeholders such as Woodward, Spirit, Emergency One, TPS Weldtech and Green Home Systems.
Looking forward, the programme is exploring options beyond March 2024 to ideally enable continued delivery of outputs and a streamlined approach to CWB through enterprise support in Ayrshire.
Project Targets
Business Cases Target date Status  Benefits Realisation (top 5 deliverables) Target Actual
OBC 12/02/2021 Complete CWB Officers & Action Plans in place - creation of CWB Locality Baselines 15 all officers in post
FBC 22/02/2021 Complete Total enterprises engaged 920 956 
Employers undertaking Fair Work Action Plans 90 124
Enterprises receiving financial assistance 265 245
New enterprises supported 96 136
Progress Update (top priority milestones as per current Implementation Plan)
Milestone Due date Milestone
status  Milestone Due date Milestone
status
Fair work inspiration week (inl RLW & Disability Awareness) 30/11/2023 Green Ayrshire CWB Enterprise Awards & Programme Achievements celebration 30/04/2024 Green
Fair work job fair 28/02/2023 Green Monthly Programme Steering Group Meetings 31/03/2024 Green
500 Ayrshire enterprises supported by the CWB programme 31/03/2023 Green Reporting to PMO, Ayrshire REP & EJC members 31/03/2024 Green
Programme case study showcase - SG visits 31/05/2023 Green Annual report 31/03/2024 Green
1000 Ayrshire enterprises supported by the CWB & FWA programme 31/03/2024 Green Project end date/final review/final report/final drawdown 31/03/2024 Green
Project Risks (top 5 risks and their status will be included in the monthly report) Target Closure Date
(dd/mm/yyyy)
Risk Imp
act
Likelihood Score AGD
Status
SG
Status Mitigation Action 
Project delays due to Covid-19  4  4  16  
• Early analysis identifies that the need for this project may be greater as a result of Covid-19
• Continued economic analysis and development of recovery plans should be implemented and robust project
scoping should continue to ensure the proposal meets needs 
Programme does not secure sufficient partner buy in to ensure an effective
set of interventions are designed and funded  1  1  1  
• Early establishment of Regional Skills Board with strategic oversight
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit and
satisfactory progress 
Failure to deliver anticipated impacts across the region in terms of Inclusive
Growth 
1 1  1  
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit and
satisfactory progress
• The partnership will conduct a mid-programme evaluation to check the direction of travel is still correct 
Disadvantaged residents do not see tangible benefits from projects  1  1  1  
• Applicants to the fund will be required to detail how delivery against inclusion targets will be assured
• Quarterly progress reports and annual review will inform decision making processes
• The Skills Fund will issue calls for proposals meaning priorities can be adapted to ensure strategic fit and
satisfactory progress 
Inadequate project management results in failure to delivery agreed
outcomes 
1 1  1  
• The Regional Skills Board will provide expert advice on what should be supported
through the fund
• Adopt programme and project management best practice
• These arrangements will be reviewed on an annual basis to ensure they remain fit for purpose
• The Steering Group will conduct a mid-programme evaluation and adjust project activity as appropriate

Page 41

Appendix 2 - Quarterly Communications Report as at October
23 
Project Quarter 2 Review Quarter 3 Plans 
Spaceport
Initiative
RIBA Stage 3 design complete.  Discussion ongoing with
regards to land acquisition and operating model.
No media proposed until further clarity reached on project.
Aerospace and
Space Innovation
Centre ( ASIC)
Appointed Ironside Farrar as consultant to create OBC
for ASTAC. Appointed Project lead from within SAC
Economy & Regeneration team. Agree timeline for OBC
submission.  Cabinet paper sign off. Key roles/partners
identified.
Establish steering group with SAC/Consultant/AC. Define a
viable ASTAC proposition and and agree the
Definition/Scope/Objectives. Agree Roles/ Responsibilities.
Work supporting College business plan & Land deal with GPA
underway.
Commercial
Space Prestwick
Site clearance now complete and detail design
development ongoing.  
No media proposed until further clarity reached on project.
Prestwick
Infrastructure 
Progress is being made towards completion of the
STAG. Following approval to discard the history phased
roads enabling projects a further report is now
prepared and lodged for presentation to cabinet
detailing the work undertaken to date.  
November: Community council meeting with Monkton
residents where reports will be delivered on traffic calming
exercise outcomes. 
HALO Kilmarnock  Captured in the Monthly Report  Captured in the Monthly Report
Ayrshire
Engineering Park
(Moorfield)
Two consultation events took place in October to share
proposals to merge these 2 projects on the Moorfield
site as Ayrshire Innovation Park (AIP). Branding options
have been created for AIP. Communications activities
included press, social media and email bulletins to
encourage participation. A short survey was hosted on
the AGD website for the duration of the consultation.
https://lnks.gd/2/2TzMJJq
Findings from the consultations will help to inform the
planning application.
Ayrshire
Manufacturing
Investment
Corridor ( AMIC)

Page 42

i3 Flexible Space 
(Expected Completion
Summer 24)
Press opportunity to mark the construction start of the
project has been pushed back to mid October 23.
October: Photo call is being arranged in November to mark
the start of construction at a ground breaking event where
key stakeholders will be invited to attend this development
milestone.
i3 Digital
Processing
Manufacturing
Centre (DPMC)
Phase 1Comms Led
by NMIS: Media
activity set out
below
4 August Visit by Parliamentary Under Secretary
(Scotland Office) John Lamont MP visited DPMC  and
met with Booth Welsh.
October: Press Release to be issued highlighting Community
Wealth building in action. Local Kilwinning business Ailsa
Reliability Solutions will be the supplier of technical support
for the DPMC demonstrators.  
Filming being undertaken to develop an "explainer"
video.  This will tell the story about the new Digital
Process Manufacturing Centre in.  The video will be
hosted on NMIS and partner websites and used within
social media posts and presentations and at events. 
February: Date of the official opening of the centre has been
agreed 21st Feb 2024 - event planning taking place to organise
arrangements  
DMPC represented at PharmaTech Integrates 2023 as
part of the NMIS / CPI presence 
Community
Renewable Energy
Project ( CoRE)
Scope of project has been reviewed and refreshed, and
recommendations were accepted by EAC Cabinet in
September. Press release prepared and issued to
promote the update.  https://newsroom.east-
ayrshire.gov.uk/news/renewed-focus-for-community-
renewal-project  
Hunterston
Strategic
Development Area
Work being carried out to finalise scope of offering.
Communications activities will be aligned to this work,
when required
Work being carried out to finalise scope of offering.
Communications activities will be aligned to this work, when
required

Page 43

International
Marine Science and
Environmental
Centre (IMSE)
Work progressing to complete OBC by 2023 including
extension to MoU to a Collaboration Agreement. This
will be based on the concept of Clyde monitoring array. 
Potential media opportunities include: the signing of a
tripartite Collaboration agreement with University of Stirling
and Field Studies Council expected Autumn. Refreshed
partnership agreement report to be presented to cabinet in
autumn. 
The Great
Harbour, at Irvine
Harbourside and
Ardeer
The team are in the final stages of developing a detailed
masterplan for the project, following extensive
consultation with the public. Planning permission for
the project will be being sought by the end of 2023. The
next quarter will see technical and operational progress
on this project - with minimal public communications
required at this stage. 
Potential media opportunity include: the publication of the
consultation results following the conclusion of the
harbourside masterplan consultation, planning committee
decision on plans expected November 24.
Marine Tourism The next quarter will see the development of the
Marine Tourism Programme Business Case and outline
business case for the Cumbrae Marina - minimal public
communications will be required. Any communications
required about the wider Marine Tourism programme
will be developed in consultation with colleagues.
Potential media Opportunities: Marine Tourism Programme
Business Case and Outline Business Case for the Cumbrae
Marina development expected to be submitted to
Government by December 23. Supporting communications
will be provided in the works associated with the Millport
Flood Protection Scheme breakwater development and
coastal flood protection works. 
Digital Subsea
Cable and Digital
Infrastructure 
None to report  None to report

Page 44

Working for a
Healthy Economy  
Further promotion will be run on social media including a
video series created by Salus. 
We will explore how we can reach more employers as there is
potential to increase referrals here, looking at further work
with Business Teams to promote to their clients and other
contacts.
Ayrshire Skills
Investment Fund
We will continue to work with the Project Lead to
confirm the next steps for this project. A
communications plan will be developed to meet project
outcomes. Press release issued on £3 million training
fund to help develop skills and employment
opportunities to drive forward the Ayrshire economy.
In September a press release was issued to announce the £3m
Ayrshire Skills Investment Fund. 
Following approval (expected around 9 Oct) we will launch
and promote the employer skills grant to local businesses
across Ayrshire. 
Presentation to be given to Ayrshire Economic Partnership
Joint Committee Sub-group on Communications Plan to
promote fund to key audience groups.
Community
Wealth Building
Fund
We will support the Programme Manager as required to
promote the South Ayrshire event.  We will also look at
the wider social media, PR around community wealth
building and identify some key highlights and case study
features to promote during Q2.
South Ayrshire event was held on 27 Sept with over 160
attendees from business and organisations across Ayrshire. 
The video series has now been completed with the addition of
a South Ayrshire film which was premiered at the event. 
During Q3 we will organise social media promotion and PR
(where appropriate) to promote the support available to
businesses and showcase the work of the AGD programme to
date.  
We are also investigating the possibility of recording podcasts
with businesses from across Ayrshire who have benefitted
from CWB support.  This work will start in Q3 and continue
into Q4.