Democracy Spraffa

Combined Document Pack (AEJC 040924)

North Ayrshire Council · 4 September 2024
Back to Ayrshire Economic Joint Committee — 4 September 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

County Buildings
Wellington Square
AYR KA7 1DR
Tel No: 01292 612724
28 August 2024
To: Members of the Ayrshire Economic Joint Committee
Dear Member
AYRSHIRE ECONOMIC JOINT COMMITTEE
You are requested to participate in the above Panel to be held on Wednesday, 4 September
2024 at 2p.m. for the purpose of considering the undernoted business.  
This meeting will be held on a hybrid basis in the Prestwick Committee Room, County Buildings,
Ayr and by Microsoft Teams. 
Yours sincerely
CATRIONA CAVES 
Chief Governance Officer
B U S I N E S S
1. Appointment of Chair
The Joint Committee is requested to note the appointment of Councillor Martin Dowey
(South Ayrshire Council) as Chair of the Ayrshire Economic Joint Committee (AEJC) for
the period from September 2024 to 31 August 2025 and to ratify the appointment of
Councillor Martin Dowey as Chair of the Ayrshire Economic Partnership Board (AEPB) for
the period from September 2024 to 31 August 2025.
2. Declarations of Interest
Members are requested to give notice of any declaration of interest in respect of the items
of business on the agenda.
3. Minutes of Previous Meeting held on 20 May 2024 (copy enclosed)
4. AGD Internal Audit Annual Report 2023/24 – Submit report by the Chief Auditor (East
Ayrshire Council) (copy enclosed)
5. AGD Internal Audit Annual Plan 2024/25 – Submit report by the Chief Auditor (East
Ayrshire Council) (copy enclosed)
6. Ayrshire Growth Deal (AGD) – Economic Modelling Update – Submit report by the
Head of Economic Growth (East Ayrshire Council) (copy enclosed)
1

Page 2

7. Ayrshire Growth Deal (AGD) – Programme Risk Register Update – June 2024 –
Submit report by the Head of Economic Growth (East Ayrshire Council) (copy
enclosed)
8. AOCB
9. Exclusion of the Public – Paras 9 & 10
Resolve in terms of Section 50(A)4 of the Local Government (Scotland) Act 1973, to
exclude from the Meeting the press and the public for the following item of business on the
grounds indicated in terms of Paragraphs 9 & 10 of Part 1 of Schedule 7A of the Act.
Non Disclosure of Information In terms of Standing Order 19 (Disclosure of Information),
the information contained within the following report is confidential information within the
meaning of Section 50A of the 1973 Act and shall not be disclosed to any person by any
Member or Officer.
10. Exempt Item Ayrshire Growth Deal – Programme Update
Submit report by the Head of Economic Growth (East Ayrshire Council) on the above (copy
sent under separate cover).
For more information on any of the items on this agenda, please contact
Committee Services at 01292 612724, Wellington Square, Ayr or
e-mail:   arlene.steven@south-ayrshire.gov.uk
www.south-ayrshire.gov.uk
2

Page 3

Ayrshire Economic Joint Committee
20 May 2024
At a Meeting of the Ayrshire Economic Joint Committee at 2.00 p.m. involving
participation by remote electronic means.
Present
Councillors Marie Burns and Anthony Gurney (North Ayrshire Council); Stephen
Canning (Substitute), Iain Linton and Maureen McKay (East Ayrshire Council); and
Martin Dowey, William Grant and Bob Pollock (South Ayrshire Council).
In Attendance
R. McCutcheon and L. Kirk (North Ayrshire Council); J. McLachlan, D. McDowall, G.
Saunders, J. King and A. Muir (East Ayrshire Council); M. Newall and G. Hunter
(South Ayrshire Council); P. Zealey (Skills Development Scotland); C. Stewart and
S. Wilson (North Ayrshire Council).
Apologies
Councillor Douglas Reid, E. Fraser and D. Watt (East Ayrshire Council); C. Hatton
(North Ayrshire Council); L. Reid (South Ayrshire Council); A. Cox (Ayrshire College)
and J. Martin (Scottish Enterprise).
Chair
Councillor Marie Burns in the Chair.
1. Declarations of Interest
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors
2. Minutes
The Minutes of (a) Ordinary meetings of the Joint Committee held on 20 November
2023 and 19 February 2024; and (b) Special meetings of the Joint Committee held
on 18 September 2023 and 15 January 2024 were confirmed and the Minutes signed
in accordance with Paragraph 7 (1) of Schedule 7 of the Local Government
(Scotland) Act 1973.
3. Ayrshire Growth Deal (AGD) – Programme Risk Register Update (March
2024)
Submitted report by the Head of Economic Growth (East Ayrshire Council) providing
an update on the AGD Programme Risk Register. The updated Programme Risk
Register (Risks and Mitigations) was set out at Appendix 1 to the report.
The Joint Committee agreed to (a) note the content of the report; and (b) approve
the updated Programme Risk Register dated March 2024, as set out at Appendix 1
to the report.
Agenda Item 3
3

Page 4

4. Ayrshire Growth Deal – Communications Protocol Update (March 2024)
Submitted report by the Head of Economic Growth (East Ayrshire Council) on the
advising of the updating of the AGD Communications Protocol. The updated
Communications Protocol March 2024 was set out at Appendix 1 to the report.
The Joint Committee agreed to (a) note the content of the report; and (b) approve
the updated Communications Protocol March 2024, as set out at Appendix 1 to the
report.
5. Ayrshire Manufacturing Investment Corridor Project and Ayrshire
Engineering Park
Submitted report by the Head of Economic Growth (East Ayrshire Council) providing
an update on the Ayrshire Manufacturing Investment Corridor (AMIC) and Ayrshire
Engineering Park (AEP) projects, following confirmation from both Scottish and UK
Governments that the change request (proposing the co-location of both projects at
Moorfield and the renaming of the site as the Ayrshire Innovation Park) has been
approved.
Members asked questions and were provided with further information in relation to:-
• the ongoing discussions with Transport Scotland, including anticipated costs,
in relation to potential upgrade and improvement works to the Bellfield
Interchange, Kilmarnock, taking cognisance of concerns discussed at the
meeting in relation to road safety and traffic queuing on the slip road on to it
and the consequential impact on the A77 trunk Road.
The Joint Committee agreed to (a) approve the change request relating to the
preferred relocation of AMIC to Moorfield, alongside the Ayrshire Engineering Park, (b)
note that this change had now been approved in principle by both Governments,
subject to a number of clarifications which would be provided as part of the
development of Outline Business Cases, (c) note that the co-located development
would be known as the Ayrshire Innovation Park (AIP), (d) that revised Outline
Business Cases would be prepared for submission to both Governments by no later
than May 2024, (e) note that a joint Full Business Case for Infrastructure Works
would be prepared for submission, to allow works to commence by January 2025, (f)
note that a further two Full Business Cases for AMIC (Centre of Excellence/Food
Grade Units and Large Advanced Manufacturing Unit) would be submitted, allowing
construction works to take place during 2026/27, (g) note that a further two Full
Business Cases for AEP (Small Terraced Engineering Units and Large Engineering
Units) would be submitted, allowing construction works to take place during 2026/27,
and (h) otherwise, to note the contents of the report.
6. Exclusion of the Public – Para 9
The Joint Committee resolved in terms of Section 50(A)4 of the Local Government
(Scotland) Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraph 9 of Part 1
of Schedule 7A of the Act. 
4

Page 5

7. Exempt Item: Ayrshire Growth Deal Commercial Build A Update
Submitted report by the Chief Executive (South Ayrshire Council) on the above.
Following consideration, the Joint Committee agreed to endorse the
recommendations in the report.
The meeting ended at 2.20 p.m.
5

Page 6

AYRSHIRE ECONOMIC JOINT COMMITTEE  
MEETING – 4 SEPTEMBER 2024
REPORT BY CHIEF AUDITOR, EAST AYRSHIRE COUNCIL
SUBJECT: AGD INTERNAL AUDIT ANNUAL REPORT 2023/24
PURPOSE OF REPORT
1. The purpose of this report is provide for noting an annual report on internal
audit activity in line with obligations laid out in the Ayrshire Growth Deal (AGD)
Governance Document (Appendix 1). Specifically this report provides:
• a summary of AGD internal audit work both prior to and since inception;
and
• an annual internal audit opinion for the AGD.
RECOMMENDATIONS
2. The Joint Committee is asked to:
(i) Consider and endorse the Internal Audit Annual Report 2023/24; and
(ii) Note that this report will be submitted to both UK and Scottish
Governments upon completion (i.e. after AEJC consideration) in line
with section 2.20 of the Governance Document.
BACKGROUND 
CONSIDERATION BY THE PARTNERSHIP BOARD
3. This report was considered by the Ayrshire Economic Partnership Board on 23
August 2024.
REQUIREMENT TO HAVE AN INTERNAL AUDIT FUNCTION
4. The Local Authority Accounts (Scotland) Regulations 2014 require local
authorities to operate a professional and objective internal auditing service; in
practice this means that the internal audit function is operationally
independent; free from limitations on the scope of its work and that the Chief
Auditor reports independently with no undue influence. The internal audit
service must be provided in accordance with recognised standards and
practices which are currently those set out in the Public Sector Internal Audit
Standards (PSIAS). It is the responsibility of each authority to ensure
compliance with the PSIAS.
Agnda Item 4
6

Page 7

CONTROL ENVIRONMENT WITHIN COUNCILS
5. It is primarily the responsibility of management to establish an appropriate and
sound system of internal controls, and to monitor the continuing effectiveness
of that system.
6. Internal Audit reports are presented to senior management and include
recommendations that, when implemented, will further improve the control
environment.
TRUST IN INTERNAL AUDIT – EXTERNAL AUDIT REVIEW
7. Internal Audit is subject to annual review by the Councils’ external auditors
with the outcome of these reviews included in each Council’s Annual Audit
Report. The most recent reports are for 2022/23 with no significant issues
arising providing assurance for those placing confidence in the work of Internal
Audit. All three Annual Audit Reports are available on the Audit Scotland
website.
MAIN REPORT
INTERNAL AUDIT WORK PRIOR TO AND SINCE INCEPTION
8. Thirteen assignments have been carried out across the three Ayrshire
Councils for the AGD. The scope and outcomes of these exercises are
summarised at Appendix 2. Outcomes reported to date range from one limited
assurance outcome, through to reasonable assurance and up to sound in most
areas. It is noted that the one limited assurance assignment in 2022/23 was
accompanied by immediate management action with the eight
recommendations tested in 2023/24 and found to be sufficiently implemented
which provides assurance to the wider stakeholders.
9. In 2021/22 we noted a potential risk from staff turnover and long term sick
absence within the Programme Management Office (PMO); management at
that time moved quickly to put interim cover arrangements in place and
recognised the longer term risk by progressing a review of the PMO structure.
During 2022/23 the senior post was filled on a permanent basis and the
second tier post filled during 2023/24 in addition to the clerical post. The
Accountable Body’s Chief Financial Officer continues to oversee resilience
aligned with the progress of the projects.
10. Our work continues to be informed by the Audit Scotland publication
Scotland’s City Region & Growth Deals (January 2020) and the follow-up
published in June 2023, recognising AGD internal audit good practice, which
was considered by the AEPB and AEJC on 7 August 2023. That follow-up
report also reinforced that the 2023 AEJC agreement to review the AGD risk
register quarterly is good practice.
AGD ANNUAL INTERNAL AUDIT OPINION 2023/24
11. Work carried out in 2023/24 is sufficient to allow the Chief Auditor to produce
an Annual Internal Audit Opinion for the year to 31 March 2024. The most that
Internal Audit will provide in the annual opinion is reasonable assurance based
on the risk based plan and a rolling programme of work. This is similar to the
7

Page 8

scope of external audit work in the context of a Council’s financial statements
which aims to give reasonable assurance on the statements. 
12. Our overall opinion, based on the work presented in Appendix 2 is that
reasonable assurance can continue to be placed upon the adequacy and
effectiveness of the AGD’s framework of governance, risk management and
control in the year to 31 March 2024. The Chief Auditor continues to be
satisfied that a robust approach is taken by the three internal audit teams with
recommendations being adopted by management supporting the assurance
framework within which the AGD operates. 
AUTHORITY WIDE ANNUAL INTERNAL AUDIT OPINIONS 2023/24
13. AGD operations are managed through the control environments of the three
Ayrshire Councils. The Chief Auditors in all three Councils have issued annual
authority wide opinions of reasonable assurance providing wider assurance to
the AGD stakeholders. 
IMPLICATIONS 
14. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance  No 
3. Human Resources  No 
4. Equality and Fairer Scotland Duty  No 
5. Financial   No 
6. Risk  Yes  Para 15
7. Community Wealth Building   No 
8. Net Zero   No 
RISK IMPLICATIONS (INTERNAL AUDIT RESOURCES) 
15. Each year there is the ongoing risk of significant unplanned work emerging in
each Council, planned resources for AGD work not being available and work
not being carried out to an acceptable standard which would compromise the
ability to complete sufficient work to produce an Annual Internal Audit Opinion
for the AGD; local mitigations should offset the potential impact of these risks. 
APPENDICES
16. The annual report is supported by two appendices: 
• Appendix 1: AGD Governance Document (Internal Audit Extract) 
• Appendix 2: AGD Internal Audit Assignments 
Eilidh Mackay 
Chief Auditor, East Ayrshire Council 
21 August 2024 
8

Page 9

BACKGROUND PAPERS 
1. Public Sector Internal Audit Standards (PSIAS) (3rd edition March 2017)
2. Chartered Institute of Public Finance and Accountancy (CIPFA) Local
Government Application Note for the United Kingdom Public Sector Internal
Audit Standards (2nd edition February 2019) 
3. Chartered Institute of Public Finance & Accountancy (CIPFA), CIPFA
Statement on the Role of the Head of Internal Audit in Public Service
Organisations (2nd edition April 2019)
4. Audit Scotland, Scotland’s City Region & Growth Deals (January 2020)
5. Audit Scotland, Scotland’s City Region & Growth Deals Follow-Up (August
2023)
6. AGD Governance Document V15
Deal Documents - All Documents (south-ayrshire.gov.uk) 
Person to Contact:  
Eilidh Mackay, Chief Auditor, East Ayrshire Council             
Email: eilidh.mackay@east-ayrshire.gov.uk 
Implementation Officers:  
Paul Davies, Audit Manager, East Ayrshire Council 
Email: paul.davies@east-ayrshire.gov.uk 
John McCallum, Senior Manager (Audit, Fraud, Safety & Risk), North              
Ayrshire Council 
Email: johnmccallum@north-ayrshire.gov.uk 
Cecilia McGhee, Chief Internal Auditor, South Ayrshire Council 
Email:  Cecilia.McGhee2@south-ayrshire.gov.uk 
9

Page 10

Appendix 1
AGD GOVERNANCE DOCUMENT V15 (INTERNAL AUDIT EXTRACT)
2.16 The Accountable Body’s Chief Auditor will be appointed as Chief Auditor for the
AGD to coordinate Internal Audit activity. 
2.17 Each partner will be responsible for allocating Internal Audit resources as
required for local AGD activities. The Accountable Body’s Internal Audit section
will reserve the right to review programme and project activities as required and
request information from all partners regarding these activities. 
2.18 Each year a consolidated Internal Audit Plan will be presented to the AEJC and
AREP having been prepared following:
• consultation with relevant senior officers of the AGD PMO;
• consideration of the risks affecting the AGD at programme and project
level;
• consideration of both internal and external factors affecting the AGD;
• consideration of previous internal and external audit findings;
• consideration of all of these elements which will inform Public Sector
Internal Audit Standards (PSIAS) based risk assessments carried out
locally by the Accountable Body and Partner Authorities; and
• any relevant items subsequently included in local Internal Audit plans
approved by each partner’s audit committee in line with PSIAS
obligations will be reflected in the consolidated AGD Internal Audit
Plan. 
2.19 All AGD Internal Audit work will be carried out in line with the PSIAS with
individual Internal Audit assignment reports presented to the AEJC and AREP
for noting. 
2.20 The relevant annual Internal Audit Report will be submitted to both UK and
Scottish Governments upon completion. The AEJC and AREP will be advised of
the overall outcomes from Internal Audit work in an annual Internal Audit Report
the timing of which is anticipated to align with the annual accounts timetable
and will be reported to the AEJC and AREP for noting in line with PSIAS
requirements. The Annual Internal Audit Report will include a summary of AGD
internal audit work in year by all partners, an annual opinion for the AGD and for
further assurance will also include the authority–wide Annual Internal Audit
opinions prepared by each partner. 
2.21 Actions arising from Internal Audits will be followed up by the relevant Internal
Audit team in line with established arrangements in that authority and these
follow-up reports will be presented to the AEJC and AREP for noting. 
2.22 Further audit, advisory consultancy or investigative work may be requested by
the AEJC and AREP. 
2.23 The Accountable Body’s Chief Auditor will liaise with partner Chief Auditors
through established arrangements.
10

Page 11

Appendix 2
AGD INTERNAL AUDIT ASSIGNMENTS PRIOR TO AND SINCE INCEPTION
Year Council Type of
Audit Work
Scope Outcome Link to “Audit
Room” on AGD
Portal
(members only)
Up to and
including
2020/21
East Ayrshire
Council 
Advisory Both prior to the AGD being signed off on
20 November 2020 and since advice has
been provided on governance
arrangements. 
Advisory Not applicable
2021/22 East Ayrshire
Council 
Advisory &
Assurance
The aims and objectives were to inform
the lead client, the Chief Financial Officer
and Head of Finance & ICT, on how well
systems and processes within the
Programme Management Office (PMO)
which are designed to keep the Ayrshire
Growth Deal (AGD) on track, are working
in practice; and to advise on any scope for
improvement in systems and compliance
verification processes which are identified
by our assurance work. This included
advising on the update of the AGD
Governance Document V15. 
Our overall
assessment of
controls
concluded that
there was sound
assurance in
most areas - key
controls exist and
are applied
consistently and
effectively in
most areas. Non-
compliance has
only been
identified in low
risk or medium
risk areas. 
21-22 EAC Internal
Audit Report -
Advisory &
Assurance.pdf
11

Page 12

2021/22 North Ayrshire
Council 
Governance  The scope of this audit was limited to
North Ayrshire Council’s role in the
projects. It focused on the governance
structures across the Council’s
participation in the deal rather than
individual projects. 
The main objectives of the audit were to
ensure that:
· governance structures and roles and
responsibilities of officers and elected
members within North Ayrshire Council, in
relation to the Ayrshire Growth Deal are
clearly defined and communicated in
order to enable good governance and
strong accountability
· North Ayrshire Council has adequate risk
management arrangements in place in
relation to the Ayrshire Growth Deal
· suitable arrangements are in place to
monitor the progress of the Ayrshire
Growth Deal programmes within North
Ayrshire, including appropriate reporting
and scrutiny arrangements
· there are adequate arrangements in
place to ensure that North Ayrshire
Council is fulfilling the requirements of the
Project Management Office and external
funding providers.
Overall,
reasonable
assurance was
obtained with
regard to the
governance
arrangements for
the Ayrshire
Growth Deal
within North
Ayrshire Council.
Overall good
governance
arrangements are
in place, but
some of the
projects are still
at an early stage
of development
and therefore it
has not been
appropriate to
fully develop
the governance
arrangements
yet.
21-22 NAC Internal
Audit Report - AGD
Governance.pdf 
2021/22 South Ayrshire
Council 
Governance The aim of the assignment was to obtain
assurance that there are adequate
governance arrangements in place for
Reasonable
assurance was
obtained that
21-22 SAC Internal
Audit Report - AGD
Governance.pdf
12

Page 13

South Ayrshire Council Ayrshire Growth
Deal (AGD) portfolio of projects.
there are
adequate internal
governance
arrangements in
place for South
Ayrshire
Council’s portfolio
of AGD projects. 
2022/23  East Ayrshire
Council 
Assurance  Testing of AGD Grant Claims.  
The aim of this assignment was to provide
assurance to the EAC Chief Financial
Officer and Head of Finance & ICT that
the AGD Quarter 4 2021/22 Grant Claim
Forms had been completed accurately
and in line with the requirements of the
UK and Scottish Governments and AGD
procedures, prior to the deadline for their
sign-off on 22 April 2022.  Our work was
carried out in “real-time” and the Chief
Financial Officer was immediately advised
of the assurance which could be placed
on processes prior to the sign-off and
submission of the claim.  The value of the
Grant Claim was £0.335m (Community
Wealth Building - £154,408, Working for a
Healthy Economy - £180,748).Assurance
was also sought for the residual element
of the Quarter 4 2021/22 Grant Claim,
which was claimed for in July 2022 along
with the Quarter 1 2022/23 Grant Claim. 
This review was retrospective due to the
low value of the claim (£0.010m).
Sound
assurance. 
We found that
both elements of
the Quarter 4
Grant Claim had
been completed
accurately, were
fully signed by
appropriate
officers and were
in line with the
requirements of
the UK and
Scottish
Governments
and AGD
procedures.
We also identified
areas for
consideration for
continuous
improvement. 
22-23 – EAC AGD
Grant Claims 
13

Page 14

Follow-up 
Advisory 
Follow-Up of 2021/22 Findings 
Advisory work included: 
• Governance Document revision
• Risk Register 
• Benefits Realisation Plan 
• Support to Audit Scotland follow-
up exercise (see paragraph 8)
• Attendance at AEPB and AEJC
meetings to inform our work
All actions fully
implemented. 
22-23 – EAC AGD
Advisory &
Assurance – Follow
Up 
2022/23  North Ayrshire
Council 
Assurance Contingency budget in place and the aim 
would be to reserve this for any claims 
audits in year. 
No work required Not applicable
2022/23 South Ayrshire
Council 
Assurance 
Follow-up 
Testing of internal governance 
arrangements. 
Follow-Up of 2021/22 Findings.
Limited
assurance with
immediate action
taken by senior
management.   
All actions
sufficiently
implemented. 
Confidential. 
22-23 - SAC - AGD
Governance
Arrangements -
Follow-Up.pdf
2023/24  East Ayrshire
Council 
Advisory  Work included support to Audit Scotland 
national review, advice on Programme 
Risk Register, Senior Auditor embedded 
in AGD PMO as critical friend. 
Advisory  Not applicable 
14

Page 15

2023/24  North Ayrshire
Council 
Assurance  The audit was structured as 3 mini-
audits covering each of the revenue
projects, reflecting the different stages
each project had reached and the
different natures of the projects. 
The main objectives of the audit were
to: 
• Ensure that controls within the
management of the Community
Wealth Building project are suitable
and operating effectively. 
• Ensure that controls to manage the
contract for the delivery of Working for
a Healthy Economy are suitable and
operating effectively. 
• Provide audit advice regarding the
proposals for the Ayrshire Skills
Investment Fund, including an
employer grants scheme. 
Substantial
assurance
2024-PA-024 AGD
Revenue Projects
(Final -amended).pdf 
2023/24  South Ayrshire
Council 
Follow-up  Follow-Up of 2022/23 Findings. All actions 
sufficiently
implemented
Confidential 
15

Page 16

AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 4 SEPTEMBER 2024
REPORT BY CHIEF AUDITOR, EAST AYRSHIRE COUNCIL
SUBJECT: AGD INTERNAL AUDIT PLAN 2024/25
PURPOSE OF REPORT
1. The purpose of this report is provide for noting an annual consolidated internal
audit plan in line with obligations laid out in the Ayrshire Growth Deal (AGD)
Governance Document (Appendix 1).
RECOMMENDATIONS
2. The Joint Committee is asked to:
(i) Consider and endorse the Internal Audit Annual Plan 2024/25.
BACKGROUND
CONSIDERATION BY THE PARTNERSHIP BOARD
3. This report was considered by the Ayrshire Economic Partnership Board on 23
August 2024.
REQUIREMENT TO HAVE AN INTERNAL AUDIT FUNCTION
4. The Local Authority Accounts (Scotland) Regulations 2014 require local
authorities to operate a professional and objective internal auditing service; in
practice this means that the internal audit function is operationally
independent; free from limitations on the scope of its work and that the Chief
Auditor reports independently with no undue influence. The internal audit
service must be provided in accordance with recognised standards and
practices which are currently those set out in the Public Sector Internal Audit
Standards (PSIAS). It is the responsibility of each authority to ensure
compliance with the PSIAS.
CONTROL ENVIRONMENT WITHIN COUNCILS
5. It is primarily the responsibility of management to establish an appropriate and
sound system of internal controls, and to monitor the continuing effectiveness
of that system.
6. Internal Audit reports are presented to senior management and include
recommendations that, when implemented, will further improve the control
environment.
Agenda Item 5
16

Page 17

MAIN REPORT 
INTERNAL AUDIT PLANNING
7. From 2021/22 each Council, in line with PSIAS requirements, carries out a risk
assessment and decides how many days are to be allocated to the AGD in
year. These days are approved as part of each Council’s Annual Internal Audit
Plan by the relevant audit committee in line with the PSIAS. The approved
days are consolidated and brought to the AEPB and AEJC. The Plans are
informed by the Audit Scotland publications listed in Background Papers. The
2024/25 Plan is attached at Appendix 2. 
REPORTING ARRANGEMENTS FOR INDIVIDUAL INTERNAL AUDIT
ASSIGNMENTS
8. On 13 September 2021 the AEJC agreed that outcomes from individual
internal audit assignments will be shared with the established readership in the
Council which carried out the work, the East Ayrshire Council Chief Auditor
and members of the AEJC and other relevant forums in line with any revisions
to governance arrangements agreed by the AEJC. Through the PMO,
assignment reports are placed within an “audit room” on the AGD portal. A
summary of this work is included in the AGD Internal Audit Annual Report for
consideration by the AEPB and AEJC. 
IMPLICATIONS 
9. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance  No 
3. Human Resources  No 
4. Equality and Fairer Scotland Duty  No 
5. Financial   No 
6. Risk  Yes  Para 10
7. Community Wealth Building   No 
8. Net Zero   No 
RISK IMPLICATIONS (INTERNAL AUDIT RESOURCES) 
10. Each year there is the ongoing risk of significant unplanned work emerging in
each Council, planned resources for AGD work not being available and work
not being carried out to an acceptable standard which would compromise the
ability to complete sufficient work to produce an Annual Internal Audit Opinion
for the AGD; local mitigations should offset the potential impact of these risks.
APPENDICES
11. The report is supported by two appendices: 
• Appendix 1: AGD Governance Document (Internal Audit Extract) 
17

Page 18

• Appendix 2: AGD Consolidated Internal Audit Annual Plan 2024/25 
Eilidh Mackay 
Chief Auditor, East Ayrshire Council 
21 August 2024 
BACKGROUND PAPERS 
1. Public Sector Internal Audit Standards (PSIAS) (3rd edition March 2017)
2. Chartered Institute of Public Finance and Accountancy (CIPFA) Local
Government Application Note for the United Kingdom Public Sector Internal
Audit Standards (2nd edition February 2019) 
3. Chartered Institute of Public Finance & Accountancy (CIPFA), CIPFA
Statement on the Role of the Head of Internal Audit in Public Service
Organisations (2nd edition April 2019)
4. Audit Scotland, Scotland’s City Region & Growth Deals (January 2020)
5. Audit Scotland, Scotland’s City Region & Growth Deals Follow-Up (August
2023)
6. AGD Governance Document V15
Deal Documents - All Documents (south-ayrshire.gov.uk) 
Person to Contact:  
Eilidh Mackay, Chief Auditor, East Ayrshire Council             
Email: eilidh.mackay@east-ayrshire.gov.uk 
Implementation Officers: 
Paul Davies, Audit Manager, East Ayrshire Council             
Email: paul.davies@east-ayrshire.gov.uk 
John McCallum, Senior Manager (Audit, Fraud, Safety & Risk), North              
Ayrshire Council 
Email: johnmccallum@north-ayrshire.gov.uk 
Cecilia McGhee, Chief Internal Auditor, South Ayrshire Council 
Email:  Cecilia.McGhee2@south-ayrshire.gov.uk 
18

Page 19

Appendix 1
AGD GOVERNANCE DOCUMENT V15 (INTERNAL AUDIT EXTRACT)
2.16 The Accountable Body’s Chief Auditor will be appointed as Chief Auditor for the AGD
to coordinate Internal Audit activity. 
2.17 Each partner will be responsible for allocating Internal Audit resources as required for
local AGD activities. The Accountable Body’s Internal Audit section will reserve the
right to review programme and project activities as required and request information
from all partners regarding these activities. 
2.18 Each year a consolidated Internal Audit Plan will be presented to the AEJC and
AREP having been prepared following:
• consultation with relevant senior officers of the AGD PMO;
• consideration of the risks affecting the AGD at programme and project level;
• consideration of both internal and external factors affecting the AGD;
• consideration of previous internal and external audit findings;
• consideration of all of these elements which will inform Public Sector Internal
Audit Standards (PSIAS) based risk assessments carried out locally by the
Accountable Body and Partner Authorities; and
• any relevant items subsequently included in local Internal Audit plans
approved by each partner’s audit committee in line with PSIAS obligations will
be reflected in the consolidated AGD Internal Audit Plan. 
2.19 All AGD Internal Audit work will be carried out in line with the PSIAS with individual
Internal Audit assignment reports presented to the AEJC and AREP for noting. 
2.20 The relevant annual Internal Audit Report will be submitted to both UK and Scottish
Governments upon completion. The AEJC and AREP will be advised of the overall
outcomes from Internal Audit work in an annual Internal Audit Report the timing of
which is anticipated to align with the annual accounts timetable and will be reported
to the AEJC and AREP for noting in line with PSIAS requirements. The Annual
Internal Audit Report will include a summary of AGD internal audit work in year by all
partners, an annual opinion for the AGD and for further assurance will also include
the authority–wide Annual Internal Audit opinions prepared by each partner. 
2.21 Actions arising from Internal Audits will be followed up by the relevant Internal Audit
team in line with established arrangements in that authority and these follow-up
reports will be presented to the AEJC and AREP for noting. 
2.22 Further audit, advisory consultancy or investigative work may be requested by the
AEJC and AREP. 
2.23 The Accountable Body’s Chief Auditor will liaise with partner Chief Auditors through
established arrangements. 
19

Page 20

Appendix 2 
AGD CONSOLIDATED INTERNAL AUDIT ANNUAL PLAN 2024/25
Council Internal
Audit plans
agreed in line
with PSIAS 
Anticipated Assignments Indicative 
Days
East Ayrshire
18 April 2024 
AGD Advisory as required based on risk 
assessment. Anticipated to include: 
• Chief Auditor support to Joint
Committee
• Audit Manager & Senior Auditor
“critical friend” support to PMO
• Support to scheduled review of
Governance Document V15
15*        
North Ayrshire
21 March 2024 
As required based on operational risk.  20 
South Ayrshire 
20 March 2024
Ayrshire Growth Deal - Follow Up of actions
from 2023/24 Assignment (if required). Review
of contract management within the AGD
programme. 
20 
Total days            55 
*estimated potential allocation within a wider Small Advisory contingency of 40 days
agreed by committee. 
20

Page 21

Agenda Item 6
AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 4 SEPTEMBER 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL – AGD ECONOMIC MODELLING
UPDATE
PURPOSE OF REPORT
1. To advise the Economic Joint Committee Members on an update on the
AGD Economic Modelling used by the PMO and the accessing an
enhanced service from the Glasgow Intelligence Unit.
RECOMMENDATIONS
2. It is recommended that members agree the content of the report :
(i) Note the development of a Service Level Agreement with the Glasgow
City Region Intelligence Hub (GCRIH) for an enhanced economic model
to support the development and monitoring of projects for the AGD; and
(ii) Approve  ‘in principle’ support to the PMO to complete negotiation for a
SLA, subject to legal and procurement advice being met.
BACKGROUND
3. The PMO as a core function as set out by the AGD Governance are
required to host an economic model. Since 2019 the PMO have operated
an AGD economic modelling tool that has helped inform a number of
projects in the development of their business cases e.g. economic case.
This is a simple model that is more effective where projects seek to
develop new builds where the proposed land use will relate to one of the
categories captured by the Use Class Orders.
4. Overtime the robustness of the model has been questioned and in
response the PMO sought external body to review the model. This has
been supported by the feedback received from the Governments when
commenting upon the economic cases of business cases. In early 2024
the Glasgow City Region Intelligence Hub (GCRIH) were contacted to
review the AGD economic model. They were approached on the grounds
that they provide economic modelling advice to the Glasgow City Region
Deal and beyond, and have supported the development of business
cases and funding bids which have been accepted by the Governments.
21

Page 22

5. Their findings recommended that a number of significant changes would
be needed to be undertaken in order for the model to be sufficiently robust
and meaningful. In addition they highlighted the limitations of the model.
Ultimately it was recognised that the best way forward would be to work
with the Glasgow Intelligence Hub in aligning the AGD economic model
with that used by the Glasgow City Region. In addition, ensure the
updating of the AGD model, although hosted by the PMO, is shared and
accessible to Partners in Ayrshire.   
MAIN REPORT 
THE OFFER – DRAFT SERVICE LEVEL AGREEMENT 
6. The PMO has negotiated a Service Level Agreement (SLA) with the GCRIH
that will overhaul the AGD economic model and align it with that used for the
Glasgow City Region and other initiatives undertaken by the City Region. 
7. The draft SLA has been developed with the support of EAC legal team and
will be shared with the procurement team to ensure compliance with relevant
requirements. Both teams will continue to be engaged in the completion of
the SLA and its delivery. 
8. In addition the SLA will also include the following conditions:
• Maintenance undertaken by the Hub so ensuring all relevant
underlying data is updated. This predominately includes national
data from Government sources. 
• Programme of updates to be undertaken of all AGD projects
information used to inform business cases. This will not replace
existing modelling tools used for business cases already approved
or are at an extensive stage of development, but provide a
consistent tool in which to capture potential economic outputs and
outcomes at a Programme level. 
• Training for the PMO and key AGD teams across Ayrshire so that
the operation, maintenance and outputs of the model are
understood and be effectively applied to AGD projects and other
initiatives where the model can be used. 
• Initially a 3 year agreement with an opportunity to terminate or
continue on a rolling year contract. 
9. The cost of the SLA has been agreed at £25k for the updating the model
and development of a revised version aligned with that used by the Hub for
the Glasgow City Region. In addition there will be a £3k commitment per
year for the lifetime of the contract to cover continued maintenance of the
model.  For over three years the total costs would be £34k which split
between the three Ayrshire Councils would equate to £11.3k, with the first
year of the agreement requiring a contribution of £9.3k from each authority.
Subsequent years would be £1k per Authority per year. 
22

Page 23

BENEFITS 
10. The benefits of using the Hubs model has already been demonstrated
through the development of the business cases for the AGD AMIC and
Moorfield projects, where EAC officers worked closely with the Hub’s team.
The details generated have resulted in a robust economic case that is
currently being considered by the Governments. 
11. Other benefits the new model will provide include:
• A Programme level economic model that could be applied to all AGD
projects, and hence provide an updated and robust evidence base
on the potential economic benefits from the Programme.
• The potential to consider unique environmental and social impacts,
due to the ongoing development of the Hub’s model, which is
seeking to investigate effective ways of capturing the economic
consequences upon environmental and social issues. An approach
which the AGD, if aligned, could learn from and incorporate moving
forward. 
• A tool that can be applied beyond AGD projects but also for other
initiatives where a business case aligned to the HM Treasury Green
Book is required e.g. LUF, and potential new regional/local
economic development Government sponsored initiatives. 
• Provide a tool that can support for the implementation of relevant
actions of the Ayrshire Regional Economic Strategy, by providing
economic evidence at a local and regional level.
• An opportunity to build resilience in the PMO and AGD teams on
knowledge, experience and skills in economic modelling. In time this
will lead to the AGD model being supported solely by Ayrshire staff,
which could result in the reduction of costs and dependencies on
external consultants. 
IMPLICATIONS 
12. Eight implications have been considered in the preparation of this report.  
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 13-14
2.Governance/Legal Yes  Para 16
3. Human Resources Yes  Para 18
4. Equality and Fairer Scotland Duty Yes  Para 19
5. Financial  Yes  Para 15
6. Risk  Yes  Para 19
7. Community Wealth Building   No 
8. Net Zero   No 
23

Page 24

ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
13. Inclusion is a key driver for the AGD. Deal business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
14. Ensuring a robust economic modeling tool is available for the AGD is a key
requirement of the PMO’s function in supporting the delivery of sustainable
development and inclusive economic growth across Ayrshire and in line
with the Deal objectives. 
FINANCIAL IMPLICATIONS 
15. The principal financial implications relate to costs associated with
appointing the GCRIH to deliver the SLA. It is recognised that there will be
initial costs but as set out in the above report the benefits derived from the
investment outweigh these costs. 
LEGAL IMPLICATIONS 
16. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the recently revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2023. 
RISK IMPLICATIONS 
17. The management of Risks will be undertaken through the managing and
monitoring of the SLA and will be led by the PMO, with updates on
progression provided to Senior Responsibility Officers for each Ayrshire
Council. 
HUMAN RESOURCES IMPLICATIONS 
18. There are no immediate human resource implications arising from this
report. All named key AGD projects are resourced to develop and deliver
the AGD programme. 
EQUALITY IMPACT ASSESSMENT 
19. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business
case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES 
24

Page 25

None 
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk
25

Page 26

26

Page 27

Agenda Item 7
AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 4 SEPTEMBER 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL – PROGRAMME RISK REGISTER
UPDATE – JUNE 2024
PURPOSE OF REPORT
1. To advise the Ayrshire Economic Joint Committee (AEJC) members on the
update for the AGD Programme Risk Register.
RECOMMENDATIONS
2. It is recommended that members agree the content of the report:
(i) Note the proposed adaptation of presentation style to meet Scottish
Government quarterly reporting templates; and
(ii) Approve the updated Programme Risk Register dated June 2024.
BACKGROUND
3. The AGD Programme Risk Register is a key tool in which to monitor and
evaluate potential risks associated with the development and delivery of the
programme. The AEJC (dated 26 June 2023) approved the quarterly review
and reporting of the AGD Programme Risk Register as a separate item on
future AEPB and AEJC meetings.
4. It should be noted that the top scoring programme and project risks are
reported to the Chief Executives Group, Steering Group, AEPB and AEJC
on a regular basis via the sharing of the AGD Programme’s Monthly
Reports.
MAIN REPORT
5. The PMO regularly reviews the Programme Risk Register in line with the
recommendations of the AEJC. This has included reviewing the nature of
the risks, their RAG status/scoring, and the mitigation measures used to
manage the potential risks identified. The review covers the majority of Q4
2022/23 from February to March 2024 and Q1 2024/25 (from April to June
2024) and reflects comments received from the AGD S95 Officer, the
Steering Group and both Governments.
27

Page 28

6. The updated Programme Risk Register is set out in Appendix 1 attached to
this report. The opportunity has also been taken to renumber the Risks
following the review. There are no changes proposed to 11 of the current 19
risks on the Risk Register. 
7. There have been changes proposed to 7 of the current risks and the
introduction of a new risk as follows: 
Number Risk
AGDRISK03 Introduction of a new Risk:
• AGDRISK03 - Failure to drawdown full yearly
allocated AGD funding as per Grant Offer
Letter 
AGDRISK’s
04; 18 and
19
Amendment in the nature of the risks being monitored so
they now consider: 
• AGDRISK04 - Failure to drawdown full AGD funding
by 2030 as per Tripartite Agreement; 
• AGDRISK18 - Failure to ensure AGD projects
working towards net zero ambitions as set by
SG/UKG; and 
• AGDRISK19 - Potential impact of macro events on
the wider economy and economic prosperity of
Ayrshire.
AGDRISK’s
04, 05, 07,
08, 14, 15
and 18
Increase in risk scoring, whether in likelihood and/or in
impact:
• AGDRISK04 - Failure to drawdown full AGD funding
by 2030 as per Tripartite Agreement;
• AGDRISK05 - Delays in development and approval
of business cases;
• AGDRISK07 - Failure to deliver community benefits
from AGD;
• AGDRISK08 - Failure to deliver individual projects
within the AGD programme;
• AGDRISK14 - Failure to attract commercial interest
in AGD;
• 
AGDRISK’s
01 and 02
Decrease in risk scoring, whether in likelihood and/or
impact:
• AGDRISK01 - Failure to achieve AGD programme
objectives within agreed budget; and
• AGDRISK02 – Failure to provide accurate
projections for programme spend.
From
AGDRISK
04 onwards
Renumber of risks categories to reflect new AGDRISK03 
8. The following risks have currently been identified as being ‘red’ in RAG
28

Page 29

status: 
Number Risk Action
AGDRISK04
(formerly
AGDRISK03)
Failure to drawdown full
AGD funding by 2030 as
per Tripartite Agreement
Conclusions from the
Programme Review will
provide clarity on the
delivery of Projects and
the whole Programme.
AGDRISK05
(formerly
AGDRISK04)
Delays in development and
approval of business cases
Conclusions from the
Programme Review will
provide clarity on the
timelines and milestones
for the development and
approval of business
cases.
AGDRISK19
(formerly
AGDRISK21)
Potential impact of macro
events on the wider
economy and economic
prosperity of Ayrshire
Continued monitoring of
external macro events and
to plan where possible. 
9. The updated mitigation measures associated with each risk are set out in
Appendix 1. 
10. Overall these changes have been undertaken in the context of the
Programme Review and its emerging outcomes, which include the
development of a more robust Programme that takes account of increased
costs and the impact of this upon development and delivery of capital
projects. There is a commitment to continue to review all Risk Registers
including the Programme Risk Register to reflect changes in the
Programme. It is therefore anticipated that further changes will be presented
to future AEPBs. 
11. Moving forward, the risks identified, especially those highlighted as ‘red’, are
anticipated to start to be de-risked once the Programme Review has been
agreed by the Government and key projects gain business case approval,
thus allowing drawdown of funds from the Government and delivery on the
ground. This includes projects for the Prestwick area that form the
Aerospace and Space Programme of the Deal. 
12. Changes in the programme risks and the application of mitigation measures
are working their way into the draft Implementation Plan 2024/25 that
includes an updated Financial Plan. This includes more realistic timelines
being developed which seek to ensure the development of business cases
and delivery by the end of the Programme. 
13. The PMO are also reviewing the presentation of the Programme Risk
Register so that it reflects more closely the Scottish Government’s quarterly
template for reporting. The benefits of this are to ensure the transfer of
information between formats and audiences are more efficient. This includes
taking into account the differences between the AGD and Government’s
29

Page 30

RAG criteria. Note that the AGD RAG scoring will continue to be retained
and used on a day to day basis. For example as illustrated below 
Source GREEN AMBER/GREEN AMBER/RED RED
Scottish
Government
Guidance 
Successful
delivery appears
highly likely with
regard to time,
cost and quality
and there are no
major
outstanding
issues that at
this stage
appear to
significantly
threaten
progress
Successful
delivery appears
probable
however
attention will be
needed in
certain areas to
ensure risks do
not develop into
major issues that
will threaten
delivery
Successful
delivery appears
possible, but
issues already
exist that require
serious attention.
These appear
resolvable at this
stage, but further
action is required
Successful
delivery is in
serious doubt
with major risks
or issues
apparent in a
number of key
areas. Urgent
action is needed
to ensure these
are addressed
Source GREEN AMBER RED
Ayrshire
Growth Deal
RAG
Guidance
Note
with an AGD risk
register score of
between 0-3
with an AGD risk
register  score of
between 4-9
with an AGD risk
register score of
between 10-14
with an AGD risk
register score of
between 15-25 
14. In conclusion the Programme Risk Register provides an assessment of the
challenges the programme continues to face. As noted the PMO are working
across the partnership to conclude the Programme Review with details of
the outcome (e.g. Executive Summary and Implementation Plan 2024/25)
scheduled to be presented to Board members at the next meeting (23
August 2024). Once agreed subsequently by the AEJC (scheduled for 4
September 2024) the Programme Review will provide a baseline in which to
ensure the delivery of projects, which will help  mitigate the current ‘red’ risks
wherever possible. 
30

Page 31

IMPLICATIONS 
15. The implications arising from this report are: 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 16-17
2.Governance/Legal Yes  Para 19
3. Human Resources Yes  Para 20
4. Equality and Fairer Scotland Duty Yes  Para 21
5. Financial  Yes  Para 20
6. Risk  Yes  Whole paper
7. Community Wealth Building   No 
8. Net Zero   No 
ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
16. Inclusion is a key driver for the AGD business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
17. The Risk Register provides the framework for reviewing the challenges the
AGD needs to address and sets out the mitigation measures to be
undertaken that include meeting the headline Deal objective of delivering
inclusive growth. 
FINANCIAL IMPLICATIONS 
18. It is accepted by the Ayrshire Councils and the Government that risks
should be managed and mitigated where necessary in order to support the
effective delivery of projects and the programme. 
LEGAL IMPLICATIONS 
19. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2022. 
HUMAN RESOURCES IMPLICATIONS 
20. There are no immediate human resource implications arising from this
report. However for the risk associated with lack of resources in PMO to be
addressed there could be human resource implications. 
EQUALITY IMPACT ASSESSMENT 
21. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business
31

Page 32

case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES 
Appendix 1: Updated Risk Register – March 2024
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk  
32

Page 33

Appendix 1:
UPDATED VERSION
AYRSHIRE GROWTH DEAL UPDATED PROGRAMME RISK REGISTER (RISKS AND MITIGATIONS) – JUNE 2024
Note: includes amendments to the Risk Register to reflect review. 
Source
GREEN AMBER/GREEN AMBER/RED RED
Scottish
Government
Guidance 
Successful delivery appears
highly likely with regard to time,
cost and quality and there are
no major outstanding issues
that at this stage appear to
significantly threaten progress
Successful delivery appears
probable however attention will
be needed in certain areas to
ensure risks do not develop into
major issues that will threaten
delivery
Successful delivery appears
possible, but issues already
exist that require serious
attention. These appear
resolvable at this stage, but
further action is required
Successful delivery is in serious
doubt with major risks or issues
apparent in a number of key
areas. Urgent action is needed
to ensure these are addressed
Source GREEN AMBER RED
Ayrshire Growth
Deal RAG
Guidance Note
with an AGD risk register score
of between 0-3
with an AGD risk register  score
of between 4-9
with an AGD risk register score
of between 10-14
with an AGD risk register score
of between 15-25 
RISK (AGD RAG USED) Current
Matrix and
Score
Proposed
Matrix and
Score
Proposed
Scottish
Govt RAG
Score
MITIGATION
AGDRISK01
Failure to achieve AGD
programme objectives
within agreed budget 
Scoring – 12 
CHANGE to reflect
Score 16  Score 12 
AMBER/RED 
• The Regional Economic Joint
Committee, Regional Economic
Partnership, AGD Steering Group in
place to monitor progress and to
address any weaknesses or issues
that could impact on overall delivery. 
• PMO ongoing monitoring and
33

Page 34

decrease in likelihood.  evaluation of Deal and project
objectives in order to address issues
early. 
• Leading to potential to review of risks
where evidence suggests insufficient
funding to undertake and complete
projects in line with expected
outcomes. Internal governance
include regular reviews undertaken
by PMO with input from SROs, Project
Leads and Chief Executives to ensure
AGD programme objective are met.
Where necessary reporting issues and
potential solutions to the AEPB and
AEJC e.g. Programme Review 23/24.
AGDRISK02
Failure to provide accurate
projections for programme
spend 
Scoring –  - 12 
CHANGE – to reflect
decrease in likelihood 
Score 16  Score 12 
AMBER/RED
• Issues will be escalated to CEOs,
Regional Economic Partnership and
Regional Economic Joint Committee
as appropriate 
• Implementation Plan and Financial
Plan updated annually with input from
Project Leads, SROs and CEOs. 
Business Case process development
supported and monitored on a
monthly basis in order to achieve
approval e.g. OBC and FBC, and then
during delivery. PMO will regularly
review, challenge and agree financial
profiling/phasing with Project Leads,
SROs and Finance Directors and
ensure drawdown projections align
with delivery timescales
• OBCs/FBCs include an optimism bias
34

Page 35

factor as per Treasury Green Book
and AGD Governance document
• Inflationary factor addressed through
project reviews e.g. re-scoping,
phasing and reviewing costs and
benefits
AGDRISK03 (NEW)
Failure to drawdown full
yearly allocated AGD funding
as per Grant Offer Letter
Scoring – 9
NEW
NEW Score 9
AMBER
/GREEN
• PMO regularly review, challenge and
agree financial profiling/phasing with
Project Leads, SROs and Finance
Directors and ensure drawdown
projections align with delivery
timescales
• Regular monitoring of project
progress and projected drawdown of
AGD allocated funds. Use of bi-annual
returns (Feb return) informing the
expected Grant Offer Letter
• Monthly reporting to the Steering
Group, SRO's AEPB/AEJC and the
Government on in year drawdown
profiles
AGDRISK04 (formerly 3)
Failure to drawdown full AGD
funding by 2030 as per
Tripartitie Agreement
Scoring –   - 20
CHANGE – to reflect
increase in impact
Score 16 Score 20
RED
• PMO will regularly review, challenge
and agree financial profiling/phasing
with Project Leads, SROs and Finance
Directors and ensure drawdown
projections align with delivery
timescales. This includes PMO
working with Project Leads, SRO’s
and S95’s to ensure projects can be
realised and help with change
processes where necessary; and
undertaking effective communication
with Governments to ensure projects
Impact
Likelihood
35

Page 36

can be realised
• Annual review of Financial Plan and
Implementation Plan undertaken.
Noted that challenges continue to
impact upon the development and
delivery of the Aerospace and Space
Programme.
• Regular reporting to the Scottish
Government in line with  financial
reporting requirements PMO support
Project Leads achieve business case
milestones in line with the current
Implementation Plan, AGD
Governance document and, Finance
guidance
• Pivot projects proactively where
possible in line with need and
opportunity, and in line with change
management processes as defined by
the AGD Governance
• PMO manage internal procedures,
financial controls and processes in
place to mitigate this risk
AGDRISK05 (formerly 4)
Delays in development and
approval of business cases
Scoring – 20
CHANGE – to reflect
increase in impact
Score 16 Score 20
RED
• Undertake focused engagement with
SG and UKG in order to help ensure
SBC, OBC and/or FBC comply with the
Treasury Green Book and gain
approval in line with AGD governance
• PMO working closely with Project
Leads and Policy Leads within UK and
Scottish Governments to support
business case development and
approval to an agreed timeline. This
36

Page 37

includes exploring a streamlined
change process (pre-FBC) particularly
where budget constraints are sole
driver of change. Note challenges
continue to impact upon the
development of business cases
• Project Leads provided with Green
Book business case training
• Project Leads’ toolkit in place
• Seek other partners to assist in
developing business cases where
capacity is low, skills align e.g.
Ayrshire College and SE. 
AGDRISK06 (formerly 5)
Failure to capture accurate
baseline data 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9
AMBER
/GREEN
• Project Leads required to establish
appropriate economic, social and
environmental baseline information in
business cases
• Establish and regularly review
achievable outcomes, output and
targets as part of the development
and delivery of projects and
realization of benefits in line with the
Benefits Realisation Plan 
AGDRISK07 (formerly 6)
Failure to deliver community
benefits from AGD 
Scoring – 9 
CHANGE – to reflect
increase in likelihood 
Score 6  Score 9 
AMBER
/GREEN
• PMO and procurement managers from
the three Ayrshire Councils have
developed a AGD Community Benefit
Tracker, a single mechanism to
monitor delivery of community
benefits so that remedial action can
be taken if required
• Result from the AGD Community
Benefits Tracker system will be
37

Page 38

analysed and reported to the Regional
Economic Partnership and Regional
Economic Joint 
• PMO working with Project Leads to
develop consistent approach to
embedding inclusive growth,
equalities, clean growth, and
community wealth building within
business cases through the Annual
Performance Report
• Procurement working group has been
established and operates in order to
support delivery of community
benefits which includes development
of a Community Benefits Tracker and
coordination of procurement
approaches so they support the
development and delivery of projects
AGDRISK08 (formerly 7)
Failure to deliver individual
projects within the AGD
programme 
Scoring – 12 
CHANGE – to reflect
increase in likelihood 
Score 8 
PUT UP 1, STILL
AMBER?
Score 12 
AMBER/RED
• Regular dialogue/reporting around
progress undertaken between PMO
and Project Leads. Seek to identify
issues early and raise with Senior
Management and/or the
Governments, AEPB and AEJC.
Regular monitoring and reporting e.g.
quarterly to the AEPB/AEJC, and
monthly to AGD Steering Group and
Project Boards.
• Partners regularly review the AGD
Benefits Realisation Plan every 12
months and report to the AEPB/AEJC.
Current change management process
incorporated in the AGD Governance
38

Page 39

document and regularly reviewed 
• Risk register in place for each project
which is regularly reviewed via
monthly reports, quarterly reports
and when updating the
Implementation Plan
• Project risk registers included in
business cases which are formally
approved by government and AEJC
• Management Information System in
place and used to track progress of
projects against key milestones, and
reported via monthly and quarterly
reports
AGDRISK09 (formerly 8)
Inadequate recognition of
interdependencies and/or
knock-on impacts between
parts of the programme
leading to issues with
delivery and/or lost
opportunities. 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9 
AMBER
/GREEN
• Programme meetings take place
regularly between PMO, Project Leads
and partners to ensure 
interdependencies are recognised and
considered; and incorporated in
approved business cases
• PMO working closely with project
leads to ensure interdependencies are
fully articulated within the project
business cases and for the
programme as a whole.
• All forms of interdependencies are
monitored and managed to help
enable the development and delivery
of all Deal projects
AGDRISK010 (formerly 9)
Lack of resource within
partner organisations to
deliver projects in line with
Score 9  Score 9 
AMBER
/GREEN
• Formal approvals of Councils’
resources are now in place for AGD
projects
• Each Council has appointed staff
39

Page 40

AGD programme 
Scoring – 9 
NO CHANGE IN SCORING 
and/or consultants to support project
development and delivery
• Each project currently has a Project
Lead in place
• Partners including SE are providing
additional resource to relevant
projects
• Resources committed to the delivery
of the programme, with further
discussions underway to explore how
to deliver the recently approved
Regional Economic Strategy 
• Other funding streams is being
explored to support ongoing revenue
costs
• Anticipated revenue streams will be
subject to constant review through
the monitoring procedures in place for
AGD 
AGDRISK11 (formerly 10)
Lack of resources in PMO 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9 
AMBER/
GREEN
• A permanent PMO structure is in place
with recruitment now completed. 
• The PMO is being supported by
colleagues in each of the Councils in a
number of work streams
• PMO undertaking a review of capacity
and skill sets in response to the
changing requirements on staff that
form the Office
AGDRISK12 (formerly 11)
Inadequate governance
arrangements to support
AGD delivery 
Score 6  Score 6 
AMBER/
GREEN
• In accordance with AGD governance,
AEPB and AEJC has been formed and
regular meetings are in place
• Scottish Government’s financial
reporting requirements have been
40

Page 41

Scoring - 6 
NO CHANGE IN SCORING 
implemented in the AGD Governance
document and Financial guidance
• Partner agreement between EAC, as
Accountable Body for the Deal, and
North and South Ayrshire Councils
has been drawn up and terms agreed 
• Partners working together with both
Governments to keep under review
the AGD Benefits Realisation Plan 
• Current change management process
in place and subject to regular review
with input from the Governments and
Partners AGD is standing item on
CEOs’ meeting agenda
AGDRISK13 (formerly 12) 
Monitoring & Evaluation
Framework is not sufficiently
defined 
Score – 6 
NO CHANGE IN SCORING 
Score 6  Score 6 
AMBER/
GREEN
PMO undertaking ongoing review of
the overarching Monitoring and
Evaluation Framework for the Deal. 
This will ensure acceptable M&E
arrangements.
AGDRISK14 (formerly 13)
Failure to attract commercial
interest in AGD 
Scoring – 12 
CHANGE – to reflect
increase in likelihood 
Score 8  Score 12 
AMBER/RED
• Following conclusion of the
Programme Review commitment to
develop with communications and
economic development teams, a
market campaign, subject to
resources. This will form part of
Communication Plan and will target
potential investors Communications
41

Page 42

Action Plan continues to be developed
and updated, including a pipeline of
project specific communications
plans. Current private sector
investment is below expected target
for the agreed AGD. 
• Regular briefings with a range of
stakeholders 
• Wider Ayrshire Economic Strategy is
now approved by the AEJC and will
ensure wider growth ambitions for
Ayrshire are achieved. This will help
support attracting greater investment
into Ayrshire. 
AGDRISK15 (formerly 14)
Programme not
communicated effectively to
stakeholders outwith
Governance structure 
Scoring 12 
NO CHANGE IN SCORING 
Score 12  Score 12 
AMBER/RED
• Communications Action Plan
completed and regularly updated, in
conjunction with communication
teams. This includes reporting on past
and future communication activity.
AGD website launched and to be
reviewed in conjunction with
communications teams, in order to
increase traffic and sharing of AGD
information
• AGD social media channels to be
reviewed in conjunction with
communications teams, with greater
linkages made to activity related to
the AGD and its progress
• Regular briefings with a range of
stakeholders via AGD programme
update to the AEPB and AEJC
• Communications Protocol in place and
42

Page 43

reviewed and updated annually, with
activity regularly identified and
delivered with the support of
communication teams.
• Resource within AGD to market and
promote project activities and overall
programme
AGDRISK16 (formerly 15)
Supply phasing within
overall programme 
Scoring – 12 
NO CHANGE IN SCORING 
Score 12  Score 12 
AMBER/RED
• PMO help facilitate and update
Procurement teams of the AGD
programme and relevant projects in
terms of timescale for development
and delivery. This includes how to
manage expected peaks in
programme activity and need for
contracts to be advertised and
managed. 
• PMO working with procurement in
supporting the sharing of market
intelligence and the phasing of
development activity, this includes
ensuring procurement leads sign off
when updating Implementation Plans.
AGDRISK17 (formerly 19)
Loss of IT systems 
Scoring – 8 
NO CHANGE IN SCORING 
Score 8  Score 8 
AMBER
/GREEN
• PMO hosted by EAC and as such 
supported by IT recovery protocols
and security systems of EAC to limit
risk and mitigation measures
• Corporate IT recovery protocol and
security systems limit the risk and
mitigation measures
• Contingency Plan in place via EAC for
the PMO, by SAC for the portal, and
for the AGD teams across the three
councils, by their respective employer
43

Page 44

(e.g. EAC, SAC, NAC)
AGDRISK18 (formerly 20)
Failure to ensure AGD
projects working towards net
zero ambitions as set by
SG/UKG 
Scoring – 8 
NO CHANGE IN SCORING 
Score 8  Score 8 
AMBER
/GREEN
• PMO and Project Leads working with
Scottish Government to ensure the
Deal is aligned with Scotland’s
transition to net zero carbon
emissions by 2045
• UK and Scottish Governments
developed carbon management
guidance for the AGD, as well as other
City Region and Growth Deals in
Scotland, which will allow the carbon
emissions impact of the programme
and projects to be assessed then
minimised.
• Consideration to be given to the
recent Scottish Government
announcement on annual and interim
targets for cutting greenhouse gases
and impact upon projects contributing
to net zero (April 24).  
• A carbon management process
appropriate for each project has been
put in place to ensure any carbon
emissions impact is minimised via
business case process
• PMO working with both Governments
to identify funding opportunities to
support decarbonisation
• PMO is working with both
Governments to agree an overarching
Monitoring and Evaluation Framework
for the Deal 
44

Page 45

AGDRISK19 (formerly 21)
Potential impact of macro
events on the wider
economy and econmic
propserity of Ayrshire 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16 
RED
• Regular engagement with Project
Leads to highlight any risks well in
advance, so that the PMO can raise
with Government, AEPB and AEJC as
appropriate
• Regular review via monthly reports of
outputs and timelines for business
cases at every stage of development
in the light of external events 
• Continued monitoring of external
environment and government
relations
• Regional Economic Strategy approved
in early 2023 and be supported by an
emerging action plan
• AEJC  provide voice for Ayrshire to
press the case for government
intervention investment
• Seek to align incentives and other
forms of assistance to complement
the AGD and stimulate greater
economic activity
• Current change management process
in place but under review
• Regional Skills Investment Plan
developed, with a focus on its
implementation via Ayrshire Skills
Group
• Robust data analysis shared amongst
key partners and stakeholders to
reach common understanding of local
economic conditions, leading to early
identification of real threats and
45

Page 46

opportunities - Supported by
proposed appointment of Glasgow
Intelligence Unit to revise AGD
economic model. 
• PMO co-ordinate evidence across
Deals and submitted collective case
via the Implementation Plan update
to both governments setting out
impact of increased costs or reduced
the scope/outputs and time delivery if
costs not met
46