Agenda Document Pack - Ayrshire Economic Joint Committee - 20/05/2024

North Ayrshire Council · 20 May 2024
Back to Ayrshire Economic Joint Committee — 20 May 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE         
Ayrshire Economic Joint Committee 
A meeting of the Ayrshire Economic Joint Committee of North Ayrshire Council will
be held remotely on Monday, 20 May 2024 at 14:00 to consider the undernoted
business. 
Meeting Arrangements - Fully Remote
This meeting will be held remotely in accordance with the provisions of
the Local Government (Scotland) Act 2003.  Where possible, the meeting
will be live-streamed and available to view at https://north-ayrshire.public-
i.tv/core/portal/home.  In the event that live-streaming is not possible, a
recording of the meeting will instead be available to view at this location. 
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
2 Minutes
The accuracy of the Minutes of (a) Ordinary meetings of the Joint
Committee held on 20 November 2023 and 19 February 2024; and (b)
Special meetings of the Joint Committee held on 18 September 2023 and
15 January 2024 will be confirmed and the Minutes signed in accordance
with Paragraph 7 (1) of Schedule 7 of the Local Government (Scotland)
Act 1973 (copy enclosed). 
3 Ayrshire Growth Deal (AGD) – Programme Risk Register Update
(March 2024)
Submit report by the Head of Economic Growth (East Ayrshire Council)
providing an update on the AGD Programme Risk Register (copy
enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
4 Ayrshire Growth Deal - Communications Protocol Update (March
2024)
Submit report by the Head of Economic Growth (East Ayrshire Council)
advising of the updating of the AGD Communications Protocol (copy
enclosed). 
5 Ayrshire Manufacturing Investment Corridor Project and Ayrshire
Engineering Park
Submit report by the Head of Economic Growth (East Ayrshire Council)
providing an update on the Ayrshire Manufacturing Investment Corridor
(AMIC) and Ayrshire Engineering Park (AEP) projects, following
confirmation from both Scottish and UK Governments that the change
request (proposing the co-location of both projects at Moorfield and the
renaming of the site as the Ayrshire Innovation Park) has been approved
(copy enclosed). 
6 Urgent Items
Any other items which the Chair considers to be urgent. 
7 Exclusion of the Public - Para 9
Resolve in terms of Section 50(A)4 of the Local Government (Scotland)
Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraph
9 of Part 1 of Schedule 7A  of the Act.
Non Disclosure of Information
In terms of Standing Order 21 (Disclosure of Information), the information
contained within the following report is confidential information within the
meaning of Section 50A of the 1973 Act and shall not be disclosed to any
person by any Member or Officer. 
8 Exempt Item Ayrshire Growth Deal - Commercial Build Project A
Submit report by the Chief Executive (South Ayrshire Council) on the
above (copy sent under separate cover). 
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE  
Webcasting
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at https://north-ayrshire.public-
i.tv/core/portal/home, where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
Generally, the press and public seating areas will not be filmed. However,
by entering the Council Chambers, using the press or public seating area
or (by invitation) participating remotely in this meeting, you are consenting
to being filmed and consenting to the use and storage of those images and
sound recordings and any information pertaining to you contained in them
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. If you
do not wish to participate in a recording, you should leave the
meeting.  This will constitute your revocation of consent.
If you have any queries regarding this and, in particular, if you believe that
use and/or storage of any particular information would cause, or be likely
to cause, substantial damage or distress to any individual, please contact
dataprotectionofficer@north-ayrshire.gov.uk. 
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Ayrshire Economic Joint Committee Sederunt 
North Ayrshire Council
Councillor Marie Burns
Councillor Joe Cullinane
Councillor Anthony Gurney
Craig Hatton
Russell McCutcheon
Louise Kirk    
East Ayrshire Council
Councillor Douglas Reid
Councillor Iain Linton
Councillor Maureen McKay
Councillor Stephen Canning (sub)
Councillor Barry Douglas (sub)
Councillor William Lennox (sub)
Eddie Fraser
David McDowall
Graham Saunders  
South Ayrshire Council
Councillor Martin Dowey
Councillor William Grant
Councillor Bob Pollock
Mike Newall
George Hunter
Louise Reid  
Others
Simon Foster, Spirit Aerosystems
Jane Martin, Scottish Enterprise
Angela Cox, Ayrshire College
Paul Zealey, Skills Development Scotland   
Chair: 
Apologies: 
Attending: 
4

Page 5

Ayrshire Economic Joint Committee
20 November 2023 
At a Meeting of the Ayrshire Economic Joint Committee at 2.00 p.m. involving
participation by remote electronic means. 
Present
Councillors Marie Burns and Anthony Gurney (North Ayrshire Council); Maureen
McKay (East Ayrshire Council); and Martin Dowey, William Grant and Bob Pollock
(South Ayrshire Council). 
In Attendance
R. McCutcheon, N. McIlvanney and A. Finlayson (North Ayrshire Council); R.
Grieveson, D. McDowall, G. Saunders and P. Davies (East Ayrshire Council); M.
Newall, L. Reid and S. Yeardley (South Ayrshire Council); J. Martin (Scottish
Enterprise); C. Stewart and H. Clancy (North Ayrshire Council). 
Apologies
Councillors Iain Linton, Douglas Reid (East Ayrshire Council) and William Grant
(South Ayrshire Council); C. Hatton and L. Kirk (North Ayrshire Council); E. Fraser,
J. McLachlan, E. Mackay and D. Watt (East Ayrshire Council); A. Cox (Ayrshire
College) and P. Zealey (Skills Development Scotland). 
Chair
Councillor Marie Burns in the Chair. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors 
2. Appointment of Chair 
The Joint Committee agreed (a) to note the appointment of Councillor Marie Burns
(North Ayrshire Council) as Chair of the Ayrshire Economic Joint Committee (AEJC)
for the period from September 2023 to 31 August 2024; and (b) to ratify the
appointment of Councillor Marie Burns as Chair of the Ayrshire Economic
Partnership Board (AEPB) for the period from September 2023 to 31 August 2024. 
3. Minutes 
The Minutes of Special meetings of the Joint Committee held on 7 August 2023 and
18 September 2023 were confirmed and the Minutes signed in accordance with
Paragraph 7 (1) of Schedule 7 of the Local Government (Scotland) Act 1973. 
4. Ayrshire Growth Deal (AGD) Internal Audit Annual Report 2022/23 
Submitted report by the Chief Auditor (East Ayrshire Council) providing an annual
report on internal audit activity in line with obligations laid out in Ayrshire Growth Deal
(AGD) Governance Document. 
Agenda Item 2
5

Page 6

A Member asked a question and was provided with further information in relation to
the difference in terminology, regarding the words used in the Audit report, i.e.,
‘general risk and control’ as compared to ‘general risk and compliance’. 
The Joint Committee agreed to note (i) the current arrangements for Internal Audit as
laid out at Appendix 1 to the report, (ii) note the work carried out prior to and since
inception, including during 2022/23 as laid out at Appendix 2 to the report and (iii) the
AGD Annual Internal Audit Opinion of continuing reasonable assurance as laid out in
sections 10-11 of the report. 
5. Ayrshire Growth Deal (AGD) Internal Audit Plan 2023/24 
Submitted report by the Chief Auditor (East Ayrshire Council) providing an annual
consolidated internal audit plan in line with obligations laid out in Ayrshire Growth
Deal (AGD) Governance document. 
The Joint Committee agreed to note (i) the current arrangements for Internal Audit as
laid out in Appendix 1 to the report, (ii) the regulatory responsibility for each Council
to approve days spent on AGD work as laid out at paragraph 7 and the subsequent
annual consolidated internal audit plan for the AGD as presented at Appendix 2 to
the report and (iii) (c) note the previously agreed arrangements to report the
outcomes of individual internal audit assignments laid out at section 8 to the report. 
6. Ayrshire Growth Deal (AGD) - Programme Update 
Submitted report by the Head of Economic Growth (East Ayrshire Council) advising
of the progress of the Ayrshire Growth Deal (AGD) and the development of its
component projects as at 30 October 2023. The Ayrshire Growth Deal Update of
Programme and Projects and the Quarterly Communications Report, as at October
2023, were attached at Appendices 1 and 2, respectively, to the report. 
The Joint Committee agreed (a) that officers be authorised to liaise with both
Governments to progress the projects having regard to the updated position in line
with the formal change requirements contained within the Deal protocols; and (b) to
note (i) the updates provided in the report (as of 30 October 2023), (ii) the progress
across the Ayrshire Growth Deal Programme, and (iii) the proposal for realignment of
the reporting requirements, principally the undertaking of the Annual Performance
Report, Financial Plan, Implementation Plan and Benefit Realisation Plan at the end
of March 24, and onwards at the same time ever year, all subject to agreement from
the Government. 
7. Ayrshire Growth Deal (AGD) – Programme Risk Register Update (October
2023) 
Submitted report by the Head of Economic Growth (East Ayrshire Council) providing
an update on the AGD Programme Risk Register as at the end of October 2023.  The
updated risk register was set out at Appendix 1 to the report. 
The Joint Committee agreed to approve the content of the updated Programme Risk
Register dated October 2023, as referred to within the report and set out at Appendix 1
to the report.  
6

Page 7

8. Schedule of Future Meeting Dates - 2024 
The Joint Committee was invited to note that Ordinary Meetings of the Ayrshire
Economic Joint Committee (AEJC) would take place at 2.00 p.m. on: 
Monday 19 February 2024
Monday 20 May 2024
Monday 9 September 2024
Monday 25 November 2024 
Noted. 
9. Exclusion of the Public – Paras 9 & 10 
The Joint Committee resolved in terms of Section 50(A)4 of the Local Government
(Scotland) Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraphs 9 & 10 of
Part 1 of Schedule 7A of the Act. 
10. Ayrshire Growth Deal Subsea Cable and Infill projects re-scoping
proposal 
Submitted report by the Project Lead – Digital, Ayrshire Growth Deal (AGD) on the
above. 
The Joint Committee agreed to endorse the recommendations in the report. 
The meeting ended at 2.25 p.m. 
7

Page 8

8

Page 9

Ayrshire Economic Joint Committee
19 February 2024 
At a Meeting of the Ayrshire Economic Joint Committee at 2.00 p.m. involving
participation by remote electronic means. 
Present
Councillors Marie Burns and Anthony Gurney (North Ayrshire Council); Douglas
Reid, Iain Linton and Maureen McKay (East Ayrshire Council); and William Grant
and Bob Pollock (South Ayrshire Council). 
In Attendance
C. Hatton, N. McIlvanney, L. Kirk and J. King (North Ayrshire Council); R. Grieveson,
D. McDowall and G. Saunders (East Ayrshire Council); L. Reid, G. Hunter, D. Yuille
and C. Caves (South Ayrshire Council); J. Martin and D. McCrindle (Scottish
Enterprise); S. Foster (Spirit Aerosystems); A. Cox (Ayrshire College); C. Stewart
(North Ayrshire Council). 
Apologies
Councillors Joe Cullinane (North Ayrshire Council) and Martin Dowey (South
Ayrshire Council); R. McCutcheon (North Ayrshire Council); E. Fraser and J.
McLachlan (East Ayrshire Council); M. Newall (South Ayrshire Council) and P.
Zealey (Skills Development Scotland). 
Chair
Councillor Marie Burns in the Chair. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors 
2. Exclusion of the Public – Para 9 
The Partnership Board resolved in terms of Section 50(A)4 of the Local Government
(Scotland) Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraph 9 of Part 1
of Schedule 7A of the Act. 
3. Ayrshire Growth Deal Spaceport Project 
Submitted report by the Chief Executive (South Ayrshire Council) on the Ayrshire
Growth Deal (AGD) Spaceport Project and seeking approval for next steps. 
Following questions and discussion, the Joint Committee agreed to endorse the
recommendations in the report. 
4. Urgent Items 
Agenda Item 2
9

Page 10

The Chair exercised discretion to allow consideration of the undernoted updates as a
matter of urgency, to permit the Joint Committee to be updated and to allow
appropriate action to be taken without delay. 
4.1 Information Sharing on AGD Projects with Scottish and UK
Governments 
The Strategic Manager (Ayrshire Growth Deal) (East Ayrshire Council) updated the
Joint Committee on information sharing arrangements with the Scottish and UK
Governments and sought permission to share draft reports at pre-agenda stage, in
order to provide full and comprehensive information on the projects under
consideration for the Ayrshire Growth Deal (AGD). 
The Joint Committee agreed to authorise officers to share draft reports with the
Scottish and UK Governments, going forward, as a means of improving and
enhancing communication with both Governments on the progress of AGD projects
underway. 
4.2 Review of AGD Steering Group by Programme Management Office
(PMO) 
The Strategic Manager (Ayrshire Growth Deal) (East Ayrshire Council) provided an
update to the Board on a review, by the Programme Management Office (PMO) of
the steering group under the Ayrshire Growth Deal, and informed that a survey
would shortly be sent to members of the steering group on its effectiveness and how
it could be improved in terms of bringing greater value in terms of developing the
AGD programme. 
Noted. 
4.3 Scotland Office of the UK Government – Local Economic Growth Review
Questionnaire 
The Strategic Manager (Ayrshire Growth Deal) (East Ayrshire Council) informed the
Partnership Board that the Scotland Office of the UK Government had issued a
questionnaire on the Local Economic Growth Review and had requested that the
PMO coordinate a response on the questionnaire. 
The Board agreed (a) that the PMO be instructed to (i) prepare a draft questionnaire
response, (ii) circulate the draft to members of the Board by email, for comment and
(iii) submit the final questionnaire response to the Scotland Office by the deadline
date of 8 March 2024; and (b) to note that the agreed action would not prevent any
authority from making their own individual response, notwithstanding the importance
of avoiding any contradiction with regard to responses. 
The meeting ended at 2.25 p.m.
10

Page 11

Ayrshire Economic Joint Committee
18 September 2023 
At a Special Meeting of the Ayrshire Economic Joint Committee at 11.00 a.m.
involving participation by remote electronic means. 
Present
Councillors Marie Burns and Anthony Gurney (North Ayrshire Council); Iain Linton
and Maureen McKay (East Ayrshire Council); and Martin Dowey and Bob Pollock
(South Ayrshire Council). 
In Attendance
Russell McCutcheon, N. McIlvanney, L. Kirk, E. McMullen and A. Finlayson (North
Ayrshire Council); D. McDowall and D. Watt (East Ayrshire Council); E. Howat and
G. Hunter (South Ayrshire Council); S. Foster (Spirit AeroSystems); D. McCrindle
(Scottish Enterprise); A. Cox (Ayrshire College); P. Zealey (Skills Development
Scotland); C. Stewart and S. Wilson (North Ayrshire Council). 
Apologies
Councillors Douglas Reid (East Ayrshire Council) and William Grant (South Ayrshire
Council), Craig Hatton (North Ayrshire Council), Eddie Fraser and Graham Saunders
(East Ayrshire Council) and Jane Martin (Scottish Enterprise). 
Chair
Councillor Marie Burns in the Chair. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors 
2. Ayrshire Regional Economic Strategy Delivery Plan 
Submitted report by the Executive Director, Place (North Ayrshire Council)
requesting approval of the Joint Committee to: (a) agree the draft Year One Delivery
Plan provided at Appendix One to the report; and (b) receive further reports for future
years of the Delivery Plan. 
The Joint Committee noted the terms and content of the presentation on the Ayrshire
Regional Economic Strategy Delivery Plan, which was made at the immediately
preceding meeting of the Ayrshire Economic Partnership Board. 
The Joint Committee agreed to (a) approve the draft Year One Delivery Plan
provided at Appendix One to the report; and (b) receive further reports for future
years of the Delivery Plan. 
The meeting ended at 11.10 a.m.
Agenda Item 2
11

Page 12

12

Page 13

Ayrshire Economic Joint Committee
15 January 2024 
At a Special Meeting of the Ayrshire Economic Joint Committee at 2.30 p.m.
involving participation by remote electronic means. 
Present
Councillors Marie Burns, Joe Cullinane and Anthony Gurney (North Ayrshire
Council); Douglas Reid and Iain Linton (East Ayrshire Council); and Martin Dowey,
William Grant and Bob Pollock (South Ayrshire Council). 
In Attendance
R. McCutcheon, N. McIlvanney, L. Kirk, E. McMullen, L. Neill and J. King (North
Ayrshire Council); E. Fraser, R. Grieveson, D. McDowall and G. Saunders (East
Ayrshire Council); M. Newall and L. Reid (South Ayrshire Council); J. Martin
(Scottish Enterprise); P. Zealey (Skills Development Scotland); C. Stewart and S.
Wilson (North Ayrshire Council). 
Apologies
Councillor Maureen Mackay (East Ayrshire Council), C. Hatton (North Ayrshire
Council) and A. Cox (Ayrshire College). 
Chair
Councillor Marie Burns in the Chair. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors 
2. Ayrshire Growth Deal (AGD) Community Wealth Building Change
Request 
Submitted report by the Executive Director, Place (North Ayrshire Council) on the
summary mid-term review of the Ayrshire Growth Deal (AGD) Community Wealth
Building (CWB) Programme and seeking approval to extend the programme by one
year.  The AGD CWB Programme Review Report was set out at Appendix 1 to the
report. 
The Joint Committee agreed to approve the project change request proposal to
extend the programme by one year, noting that the proposal had been supported by
the Scottish Government and endorsed by the Ayrshire Economic Partnership
Board. 
3. Ayrshire Skills Investment Fund (ASIF) Governance 
Submitted report by the Chief Executive (North Ayrshire Council) seeking approval of
the detailed governance arrangements for the Ayrshire Skills and Investment (ASIF)
sub-committee of the Ayrshire Economic Joint Committee (AEJC) including the
Terms of Reference and Standing Orders. 
Agenda Item 2
13

Page 14

The Joint Committee agreed (a) to approve the Terms of Reference for the Ayrshire
Economic Joint Committee Ayrshire Skills Investment Fund Sub-Committee; (b) to
note that the agreed governance arrangements had been implemented, creating the
AEJC, Ayrshire Skills and Investment Fund Sub-Committee, with delegated authority
to award the fund; (c) to ratify the appointment of Councillor Marie Burns (North
Ayrshire Council) as Chair and appoint Councillor Bob Pollock (South Ayrshire
Council) as Vice-Chair of the Ayrshire Skills and Investment Fund Sub-Committee
(ASIF sub-committee); (d) to note the grant funding approved at the meeting of the
ASIF sub-committee in November 2023 as detailed in Appendix 3 of the report, in
accordance with the general delegation granted by the AEJC on 20 June 2022 and
ratify the delegation for approval of grant funding awarded; and (e) that an update be
provided to the Joint Committee every 6 months on funding awards and
achievements. 
The meeting ended at 2.40 p.m.
14

Page 15

AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 20 MAY 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL – PROGRAMME RISK REGISTER
UPDATE – MARCH 2024
PURPOSE OF REPORT
1. To advise the Economic Partnership Joint Committee on the update for the
AGD Programme Risk Register.
RECOMMENDATIONS
2. Note the  content of the report and to :
(i) Approve the updated Programme Risk Register dated March 2024
BACKGROUND
3. The AGD Programme Risk Register is a key tool in which to monitor and
evaluate potential risks associated with the development and delivery of the
programme. The Ayrshire Economic Joint Committee (AEJC) (dated 26
June 23) approved the quarterly review and reporting of the AGD
Programme Risk Register as a separate item on future AEPB and AEJC
meetings.
4. It should be noted that the top scoring programme and project risks are
reported to the Chief Executives Group, Steering Group, AEPB and AEJC
on a regular basis via the sharing of the monthly reports.
MAIN REPORT
5. The PMO reviews regularly the Programme Risk Register in line with the
recommendations of the AEJC. This has included reviewing the nature of
the risks, their RAG status/scoring, and the mitigation measures used to
reduce the potential of risk. The review covers Q4 23/24 up to end of March
2024.
6. Since reporting last to the Committee the PMO is now fully staffed with the
following positions forming the team:
Agenda Item 3
15

Page 16

7. As previously reported it should be noted that the PMO has undertaken a
review of capacity and skill sets held in the Office. This is in response to the
changing calls on the staff to support the delivery of the Programme.
Discussions are currently underway with three funding Ayrshire Councils on
the implications of the review. In terms of the Risk Register the scoring for
AGDRISK10 - Lack of resources in PMO, remains the as previously
reported. 
8. The remaining risks identified with a ‘red’ RAG status are proposed not to
be changed. These are: 
(i) AGDRISK01 - Failure to achieve AGD programme objectives within
agreed budget
(ii) AGDRISK02 - Failure to provide accurate projections for programme
spend 
(iii) AGDRISK03 - Failure to drawdown full AGD funding
(iv) AGDRISK04 - Delays in development and approval of business cases
(v) AGDRISK21 - Potential impact of international events upon cost of living
crisis and economic prosperity of Ayrshire 
9. The external context has not changed with significant environmental
challenges such as the legacy of the Covid and Brexit, and the ongoing
Ukraine war. Combined, these challenges have contributed to increased
cost pressures that continue to impact upon the development and delivery
of projects and the programme as a whole (AGDRISK21). 
10. It is expected the rating of the ‘Red’ risks (AGD RISK01-04) is however
expected to change once the outcome of the ongoing Programme Review is
concluded and enacted. The Programme Review is ongoing and outcomes
emerging that will be reported to the AEPB in the coming weeks. These
outcomes will influence the updating of the draft Implementation Plan 24/25
which will incorporate the revised Financial Plan and updated Benefit.
Together these Plans will have an impact upon the current risk ratings.
AGD - Strategic
Lead (G16)
AGD - Programme
Manager (G14)
AGD - Compliance
& Performance
Officer (G12)
AGD - Business
Assistant (G5)
16

Page 17

11. In conclusion the Programme Risk Register provides a realistic reflection of
the state of the challenges the programme are continuing to face. As noted
the PMO are working across the partnership to conclude the Programme
Review. Once agreed the Programme Review will provide a sound baseline
in which to ensure the delivery of projects, which will help de-risk the current
‘red’ risks. 
IMPLICATIONS 
12. Eight implications have been considered in the preparation of this report. 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning Yes  Para 13-14
2.Governance/Legal Yes  Para 16
3. Human Resources Yes  Para 17
4. Equality and Fairer Scotland Duty Yes  Para 18
5. Financial  Yes  Para 15
6. Risk  Yes  Whole paper
7. Community Wealth Building   No 
8. Net Zero   No 
ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
13. Inclusion is a key driver for the AGD. Deal business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
14. The Risk Register provides the framework for reviewing the challenges the
Deal needs to address and enables effective mitigation measures to be
undertaken that include meeting the headline Deal objective of delivering
inclusive growth. 
FINANCIAL IMPLICATIONS 
15. It is accepted by the Ayrshire Councils and the Government that risks
should be managed and mitigated where necessary in order to support the
effective delivery of projects and the programme. 
LEGAL IMPLICATIONS 
16. The legal implications arising from this report are covered through the
Agreement between the three Ayrshire’s Councils and the recently revised
Governance Document which was approved at the Joint Committee
meeting on 8 December 2022. 
HUMAN RESOURCES IMPLICATIONS 
17. There are no immediate human resource implications arising from this
17

Page 18

report. However for the risk associated with lack of resources in PMO to be
addressed there could be human resource implications. 
EQUALITY IMPACT ASSESSMENT 
18. There is no direct equalities impact relating to this report. Inclusion is a key
driver for the AGD. Project leads will be required to complete an Equality
Impact Assessment for their project and append to the associated business
case. Project leads have received Equality Impact Assessment training
organised by the Scottish Government. Project Leads are being
encouraged by the PMO to link up as soon as possible with their Equalities
Officer within their authority who will be able to assist with this matter. 
APPENDICES 
Appendix 1: Updated Risk Register – March 2024
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and
Ayrshire’s Councils on 19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Strategic Manager
Graham.saunders@east-ayrshire.gov.uk  
18

Page 19

Appendix 1:
AYRSHIRE GROWTH DEAL UPDATED PROGRAMME RISK REGISTER (RISKS AND MITIGATIONS) – MARCH 2024 
RISK Current
Matrix and
Score
Proposed
Matrix and
Score
MITIGATION
AGDRISK01
Failure to achieve AGD
programme objectives
within agreed budget 
Scoring – 16 
NO CHANGE IN SCORING 
Score 16  Score 16  • The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group in place
to monitor progress and to address any weaknesses
or issues that could impact on overall delivery. 
• PMO ongoing monitoring and evaluation of Deal and
project objectives in order to address issues early.
This includes responding to increasing costs of
general capital works within the context of the
original funding made available by the Government
in 2019. Leading to potential to review risks where
evidence suggests insufficient funding to undertake
and complete projects in line with expected
outcomes.
• PMO undertake ongoing environmental analysis to
ensure programme objectives are relevant/valid as
well as maximised where relevant and new benefits
identified when materialising.
• Internal governance include regular reviews
undertaken by PMO with input from SROs, Project
Leads and Chief Executives to ensure AGD
programme objective are met.
AGDRISK02
Failure to provide accurate
projections for programme
spend 
Score 16  Score 16  • Issues will be escalated to CEOs, Regional Economic
Partnership and Regional Economic Joint Committee
as appropriate 
• The Implementation Plan and Financial Plan being
19

Page 20

Scoring –  - 16 
NO CHANGE IN SCORING 
updated to take account of Programme Review
outcomes. Project Leads have sought to address
delays in gaining approved FBCs, by undertaking
reviews of projects to fit existing budgets, which are
shared with Finance Directors, the government and
wider partners. Revised project mitigation measures
seek to demonstrate how inflationary pressures will
be managed
• Business Case process monitored to ensure
streamlined pathway to approval enabling projects
to achieve FBC as quickly as possible to reach
project delivery and clarity on expected spend.
• PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs
and Finance Directors and ensure drawdown
projections align with delivery timescales
• OBCs/FBCs include an optimism bias factor as per
Treasury Green Book and AGD Governance
document
• Inflationary factor addressed through project
reviews e.g. re-scoping, phasing and reviewing
benefits
AGDRISK03
Failure to drawdown full AGD
funding 
Scoring –   - 16 
NO CHANGE IN SCORING 
Score 16  Score 16  • PMO will regularly review, challenge and agree
financial profiling/phasing with Project Leads, SROs
and Finance Directors and ensure drawdown
projections align with delivery timescales. This
includes PMO working with Project Leads, SRO’s and
S95’s to ensure projects can be realised and help
with change processes where necessary; and
undertaking effective communication with
Governments to ensure projects can be realised
• Achieve business case approval in line with latest
Deal Implementation Plan, and AGD Governance
20

Page 21

document and, Finance guidance
• Annual review of Financial Plan and Implementation
Plan
• The Scottish Government’s financial reporting
requirements will be implemented
• Pivot projects proactively where possible in line with
need and opportunity
• Internal procedures, financial controls and
processes in place to mitigate this risk
AGDRISK04
Delays in development and
approval of business cases 
Scoring – 16
NO CHANGE IN SCORING 
Score 16  Score 16  • Undertake focused engagement with SG and UKG in
order to help ensure SBC, OBC and/or FBC comply
with the Treasury Green Book and gain approval pin
line with AGD governance
• PMO working closely with Project Leads and Policy
Leads within UK and Scottish Governments to
support business case development and approval to
an agreed timeline. This includes exploring a
streamlined change process (pre-FBC) particularly
where budget constraints are sole driver of change.
• Project Leads have received Green Book business
case training
• Project Leads’ toolkit in place
• Other partners assisting in developing business
cases where capacity is low
AGDRISK05
Failure to capture accurate
baseline data 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9 • Project Leads required to establish appropriate
economic, social and environmental baseline
information in business cases
• Establish and regularly review achievable outcomes,
output and targets as part of the development and
delivery of projects and realization of benefits in line
with the Benefits Realisation Plan 
21

Page 22

AGDRISK06
Failure to deliver community
benefits from AGD 
Scoring – 6 
NO CHANGE IN SCORING
Score 6  Score 6  • PMO and procurement managers from the three
Ayrshire Councils have developed a AGD
Community Benefit Tracker, a single mechanism to
monitor delivery of community benefits so that
remedial action can be taken if required
• Result from the AGD Community Benefits Tracker
system will be analysed and reported to the
Regional Economic Partnership and Regional
Economic Joint 
• PMO working with Project Leads to develop
consistent approach to embedding inclusive growth,
equalities, clean growth, and community wealth
building within business cases through the Annual
Performance Report
• Procurement working group has been established
and operates in order to support delivery of
community benefits which includes development of
a Community Benefits Tracker and coordination of
procurement approaches so they support the
development and delivery of projects
AGDRISK07
Failure to deliver individual
projects within the AGD
programme 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8  • Regular dialogue/reporting around progress takes
place between PMO and Project Leads where issues
are raised in advance and if appropriate escalated
to government, Regional Economic Partnership and
Regional Economic Joint Committee, this includes
early discussions with both UK and Scottish
Government
• The Regional Economic Joint Committee, Regional
Economic Partnership, AGD Steering Group and
Project Boards in place to monitor project
development, via monthly reports
• Partners are regularly reviewing the AGD Benefits
Realisation Plan every 12 months and reported to
22

Page 23

the Regional Economic Partnership and Regional
Economic Joint Committee
• Current change management process incorporated
in the AGD Governance document and regularly
reviewed 
• Risk register in place for each project which is
regularly reviewed via monthly reports, quarterly
reports and when updating the Implementation Plan
• Project risk registers included in business cases
which are formally approved by government and
Regional Economic Joint Committee
• Management Information System in place and used
to track progress of projects against key milestones,
and reported via monthly and quarterly reports
AGDRISK08
Inadequate recognition of
interdependencies and/or
knock-on impacts between
parts of the programme
leading to issues with
delivery and/or lost
opportunities 
Scoring – 9 
NO CHANGE IN SCORING
Score 9  Score 9  • Programme meetings take place regularly between
PMO, Project Leads and partners to ensure 
interdependencies are recognised and considered;
and incorporated in approved business cases
• PMO working closely with project leads to ensure
interdependencies are fully articulated within the
project business cases and for the programme as a
whole.
• All forms of interdependencies are monitored and
managed to help enable the development and
delivery of all Deal projects
AGDRISK09
Lack of resource within
partner organisations to
deliver projects in line with
AGD programme 
Scoring – 9
Score 9  Score 9  • Formal approvals of Councils’ resources are now in
place for AGD projects
• Each Council has appointed staff and/or consultants
to support project development and delivery
• Each project currently has a Project Lead in place
• Partners including SE are providing additional
resource to relevant projects
23

Page 24

NO CHANGE IN SCORING   
• Resources committed to the delivery of the
programme, with further discussions underway to
explore how to deliver the recently approved
Regional Economic Strategy 
• Other funding streams is being explored to support
ongoing revenue costs
• Anticipated revenue streams will be subject to
constant review through the monitoring procedures
in place for AGD 
AGDRISK10
Lack of resources in PMO 
Scoring – 9 
NO CHANGE IN SCORING 
Score 9  Score 9  • A permanent PMO structure is in place with
recruitment now completed. 
• The PMO is being supported by colleagues in each
of the Councils in a number of work streams
• PMO undertaking a review of capacity and skill sets
in response to the changing requirements on staff
that form the Office
AGDRISK11
Inadequate governance
arrangements to support
AGD delivery 
Scoring - 6 
NO CHANGE IN SCORING
Score 6  Score 6  • In accordance with AGD governance, Ayrshire
Economic Joint Committee and Ayrshire Regional
Economic Partnership has been formed and regular
meetings are in place
• Scottish Government’s financial reporting
requirements have been implemented in the AGD
Governance document and Financial guidance
• Partner agreement between EAC, as Accountable
Body for the Deal, and North and South Ayrshire
Councils has been drawn up and terms agreed 
• PMO working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
• Partners working together with both governments to
keep under review the AGD Benefits Realisation Plan 
24

Page 25

• Current change management process to be
reviewed with the governments and partners
• AGD is standing item on CEOs’ meeting agenda
AGDRISK12 - Monitoring &
Evaluation Framework is not
sufficiently defined 
Score – 6 
NO CHANGE IN SCORING
Score 6  Score 6  • PMO undertaking ongoing review of the
overarching Monitoring and Evaluation Framework
for the Deal which will be developed and published
on the AGD web site. This will ensure acceptable
M&E arrangements. 
AGDRISK13
Failure to attract commercial
interest in AGD 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8  • Following conclusion of the Programme Review
undertake with communications and economic
development teams, a market campaign will be
developed, as part of Communication Plan and
target potential investors
• Communications Action Plan continues to be
developed and updated, including a pipeline of
project specific communications plans
• Regular briefings with a range of stakeholders 
• Wider Ayrshire Economic Strategy is now approved
by the Regional Economic Joint Committee and will
ensure wider growth ambitions for Ayrshire are
achieved
AGDRISK14
Programme not
communicated effectively to
stakeholders outwith
Governance structure 
Scoring 12 
Score 12  Score 12  • Communications Action Plan completed and
regularly updated, in conjunction with
communication teams. This includes reporting on
past and future communication activity AGD website
launched and to be reviewed in conjunction with
communications teams, in order to increase traffic
and sharing of AGD information
• AGD social media channels to be reviewed in
25

Page 26

NO CHANGE IN SCORING  conjunction with communications teams, with
greater linkages made to activity related to the AGD
and its progress
• Regular briefings with a range of stakeholders via
AGD programme update to the Regional Economic
Partnership and Regional Economic Joint Committee
• Communications Protocol in place and reviewed and
updated annually, with activity regularly identified
and delivered with the support of communication
teams.
• Resource within AGD to market and promote project
activities and overall programme
AGDRISK15
Supply phasing within
overall programme 
Scoring – 12 
NO CHANGE IN SCORING 
Score 12  Score 12  • Engagement undertaken in 2022 with the
construction sector in order promote and explain the
potential of the AGD programme to local businesses,
so increase Invitation to Tender for future contracts.
Review opportunity to repeat the exercise.
• PMO help facilitate and update Procurement teams
of the AGD programme and relevant projects in
terms of timescale for development and delivery.
This includes how to manage expected peaks in
programme activity and need for contracts to be
advertised and managed. Market engagement
through the Meet the Buyer events with the next
being held in the Autumn 2023
• PMO working with procurement in supporting  the
sharing of market intelligence and the phasing of
development activity
AGDRISK19
Loss of IT systems 
Scoring – 8 
Score 8  Score 8  • PMO hosted by EAC and as such  supported by IT
recovery protocols and security systems of EAC to
limit risk and mitigation measures
• Corporate IT recovery protocol and security systems
limit the risk and mitigation measures
26

Page 27

NO CHANGE IN SCORING    • Contingency Plan in place via EAC for the PMO, by
SAC for the portal, and for the AGD teams across
the three councils, by their respective employer
(e.g. EAC, SAC, NAC)
AGDRISK20
Failure to ensure AGD
projects align with a net zero
transition 
Scoring – 8 
NO CHANGE IN SCORING
Score 8  Score 8  • PMO and Project Leads working with Scottish
Government to ensure the Deal is aligned with
Scotland’s transition to net zero carbon emissions
by 2045
• UK and Scottish Governments developed carbon
management guidance for the AGD, as well as other
City Region and Growth Deals in Scotland, which will
allow the carbon emissions impact of the
programme and projects to be assessed then
minimised
• A carbon management process appropriate for each
project has been put in place to ensure any carbon
emissions impact is minimised via business case
process
• PMO working with both governments to identify
funding opportunities to support decarbonisation
• PMO is working with both governments to agree an
overarching Monitoring and Evaluation Framework
for the Deal 
AGDRISK21
Potential impact of
international events upon
cost of living crisis and
economic prosperity of
Ayrshire 
Score 16  Score 16  • Regular engagement with Project Leads to highlight
any risks well in advance, so that the PMO can raise
with government, Regional Economic Partnership
and Regional Economic Joint Committee as
appropriate
• Regular review via monthly reports of outputs and
timelines for business cases at every stage of
27

Page 28

Scoring – 16 
NO CHANGE IN SCORING 
development in the light of external events 
• Continued monitoring of external environment and
government relations
• Regional Economic Strategy approved in early 2023
and be supported by an emerging action plan
• Regional Economic Partnership will provide voice for
Ayrshire to press the case for government
intervention investment
• Incentives and other forms of assistance to
complement the AGD and stimulate greater
economic activity
• Current change management process to be
reviewed with both governments and partners
• Regional Skills Investment Plan developed, with a
focus on its implementation via Ayrshire Skills
Group
• Robust data analysis shared amongst key partners
and stakeholders to reach common understanding
of local economic conditions, leading to early
identification of real threats and opportunities -
achieving consensus with partners and stakeholders
on strategic objectives for inclusive and sustainable
economic growth, with effective action planning and
monitoring
• PMO co-ordinate evidence across Deals and
submitted collective case via the Implementation
Plan update to both governments setting out impact
of increased costs or reduced the scope/outputs and
time delivery if costs not met 
28

Page 29

1 
AYRSHIRE ECONOMIC JOINT COMMITTEE
MEETING – 20 MAY 2024
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE GROWTH DEAL –COMMS PROTOCOL UPDATE – MARCH 2024
PURPOSE OF REPORT
1. To advise the Economic Joint Committee Members on the updating of the AGD
Communications Protocol.
RECOMMENDATIONS
2. Note the content of the report to:
(i) Approve the updated Communication Protocol March 24.
BACKGROUND
3. In line with good practice and governance requirements the Comms Protocol is
regularly reviewed to ensure it is fit for purpose and meets the needs of the AGD
and its Partners. The last update of the Protocol was in June 2023, when a
series of minor changes were made principally around changes in contact
names. Formal approval is not required by the Joint Committee but the PMO
seeks to highlight the amendments being proposed.
MAIN REPORT
Updated Comms Protocol
4. The Comms Protocol has been reviewed and updated in light of the following
pressures:
• Overall shift in the Programme from a period of development to delivery.
• The outcomes of the Programme Review are becoming clear with an
expectation that a reinvigoration of the Deal is desired in order to raise its
profile and the benefits it will deliver
• Recent project progression has sought the need to clarify how and when
to invite senior politicians from the Scottish and UK Governments to key
stages in the development of projects e.g. ground breaking events,
opening new facilities -including required periods of notice.
• Changes in named contacts from the Governments.
Agenda Item 4
29

Page 30

2 
5. The minor changes made provide greater clarity and are focused on the
following: 
• Updated text on the management of Scottish and UK Governments in
relation to the Ayrshire Growth Deal, principally on how and when to
invite/engage with Ministers from the Scottish and UK Government where
a media opportunity exists (section 4).
• Updating of named lead contacts principally from the Scottish and UK
Governments (section 10). 
6. All changes proposed have been shared with the Governments and project
leads. 
IMPLICATIONS 
7. Eight implications have been considered in the preparation of this report. 
Implications Yes No Paragraph
number in report
1. Policy/Strategic Planning  No 
2.Governance/Legal Yes  Para 11
3. Human Resources Yes  Para 12
4. Equality and Fairer Scotland Duty Yes  Para 8-9
5. Financial  Yes  Para 10
6. Risk  Yes  Para 13
7. Community Wealth Building   No 
8. Net Zero   No 
ALIGNMENT WITH SUSTAINABLE, INCLUSIVE GROWTH AMBITIONS 
8. Inclusion is a key driver for the AGD. Deal business cases for projects
demonstrate how they will reduce inequalities and tackle the inclusion
challenges specific to Ayrshire. 
9. The Comms Protocol provides a framework for communicating the delivery of
inclusive growth ambitions for each project and the programme as a whole. 
FINANCIAL IMPLICATIONS 
10. The Comms Protocol will have some financial impact albeit these costs will be
incorporated as part of the development and delivery of projects. 
LEGAL IMPLICATIONS
30

Page 31

3 
11. The legal implications arising from this report are covered through the Agreement
between Ayrshire’s Councils and the recently revised Governance Document
which was approved at the Joint Committee meeting on 8 December 2022. 
HUMAN RESOURCES IMPLICATIONS 
12. The implementation of the Comms Protocol is undertaken as part of operational
activities for the AGD by the PMO, and Project Leads in consultation with
communication teams across the Ayrshire Councils. 
RISK IMPLICATIONS 
13. Strategic and operational risk registers continue to be developed, reviewed and
updated for the AGD Programme. This is being undertaken by the PMO with the
support of EAC audit. The Programme Risk Register which includes the
consideration of effective communication has been updated in accordance with the
commitment to be reviewed every quarter as approved by the AEJC on 26 June
2023. Details of the latest update is considered elsewhere on the agenda. 
EQUALITY IMPACT ASSESSMENT 
14. There is no equalities impact relating to this report. Inclusion is a key driver for
the AGD. Project leads will be required to complete an Equality Impact
Assessment for their project and append to the associated business case. Project
leads have received Equality Impact Assessment training organised by the
Scottish Government. Project Leads are being encouraged by the PMO to link up
as soon as possible with their Equalities Officer within their authority who will be
able to assist with this matter. 
APPENDICES 
Appendix 1: Updated Comms Protocol March 24
Background Papers: 
Heads of Terms, signed by both the UK and Scottish Governments and Ayrshire’s Councils on
8 March 2019 
Deal Document, signed by both the UK and Scottish Governments and Ayrshire’s Councils on
19 November 2020 
Members requiring further information should contact: 
Graham Saunders, Ayrshire Growth Deal – Interim
Strategic manager and Programme Manager
Graham.saundetrs@east-ayrshire.gov.uk 
Implementation Officer:
Graham Saunders, Ayrshire Growth Deal – Interim
Strategic Manager and Programme Manager
Graham.saundetrs@east-ayrshire.gov.uk 
31

Page 32

4 
Appendix 1: Updated Comms Protocol March 24 (TEXT FORM)
Note a formal version will be prepared for publication in line with previous Comms Protocols 
• Partner commitment
This document sets out an agreed framework for communication protocols around the
Ayrshire Growth Deal. It is designed to ensure:
• Areas of responsibility and working practices across the partners are clearly defined;
• Effectiveness, clarity and timeliness of action when matters concerning one or more partners
are deemed likely to be of public/media interest; and
• Good partner working relationships. 
• Scope
This protocol covers proactive and reactive communications activities in relation to the
Ayrshire Growth Deal by the PMO, member authorities (North Ayrshire, East Ayrshire
and South Ayrshire Councils), Scottish and UK Governments, and other partners, with
communications defined as:
• Press releases and written statements issued to the print, online and broadcast media;
• Interviews and opinion pieces provided to the print, online and broadcast media;
• Briefings, interviews, verbal statements and press conferences;
• Publicity material, including posters, brochures, leaflets, newsletters and reports;
• Media information, blogs and commentary released across each organisation’s social
media;
• Broadcast interviews, documentaries and public interest programmes;
• Information published on each organisation’s website;
• Social media posts;
• Responses to FOIs, political and customer enquiries. 
• Lead organisation
North Ayrshire Council Press Office will lead on and sign off Ayrshire Growth Deal
programme communications in relation to output from all committees and governance
groups. 
• Scottish and UK Governments in relation to the Ayrshire Growth Deal
The UK and Scottish Governments will be engaged as early as possible in every
Ayrshire Growth Deal project milestone, to allow opportunities for attendance at events
and inclusion of media quotes. 
The PMO will act as a liaison between individual projects and the Deal partners and will
be the primary point of contact for the UK and Scottish Governments. As such, the PMO
should be sighted on all potential project and programme level communications
32

Page 33

5 
activities to ensure the UK and Scottish Governments receive sufficient notice of, and
opportunity to contribute to, any media opportunities, visits, or events. 
Government partners will aim to advise the PMO in advance about proposed or
planned media or visits by politicians or senior officers connected to the Ayrshire Growth
Deal. They will also advise the PMO of any unplanned comments made about the Deal
such as at parliamentary committees, or in the chamber. 
If a member authority or partner intends to invite either the UK or Scottish Government
to an event or media opportunity connected to the Ayrshire Growth Deal, or to offer
space for a quote in a news release, the same offer must be made to both
governments. 
As a matter of courtesy, the PMO will share all AGD press releases with UK and Scottish
Governments regardless of whether a quote is required. 
Ayrshire Growth Deal Project Leads should work with the PMO to:
• Provide advance notice of any upcoming events, such as groundbreaking and project
openings.
• Provide an outline of what Ministers would be expected to do at such an event.
• Identify a suitable date and time for ministerial involvement.
• Ensure appropriate supporting communications. 
Please copy the UK and Scottish Government Deal Policy Leads for your area to any
communication. 
• Spokespersons
The agreed spokespersons are as follows:
• For the Ayrshire Growth Deal programme: The Ayrshire Economic Joint Committee Chair, and
where appropriate, with UK and Scottish Governments;
• For individual Ayrshire Growth Deal projects: Lead member authority or partner will appoint, as
appropriate. Where a project is carried out by two or more partners, it is acceptable to
include quotes from the relevant spokesperson for each organisation;
• Where the subject crosses themes or more generally relates to the partnership, the
Joint Committee Chair will be quoted;
• If the Joint Committee Chair is unavailable, such as in pre-election circumstances,
the PMO shall liaise with the Chief Executives in relation to the spokesperson
substitute. 
• Process
The Ayrshire Growth Deal Communications Group shall meet monthly to: 
• Populate and agree a communications planner and upcoming activity;
• Update the communications documents set out below; and
33

Page 34

6 
• Discuss the handling of any forthcoming communications opportunities that have arisen
since the previous meeting.
o Media activity and press releases
 All media releases and briefing notes relating to the Ayrshire Growth
Deal will be shared in advance with the PMO and all communications
leads.
 Media releases relating to the Deal will be posted promptly on the AGD website.
 In instances of sensitive, or conflicting positions, communication leads
representing each organisation will keep each other informed on a ‘no
surprises’ basis. Any confidentiality or embargo relating to this
information will naturally be upheld.
 All media releases must acknowledge funding from the UK and/or
Scottish Government, as well as any other funding partners. This must
be included in the body of the release, not as background information
or editor’s notes, and must be placed early in the release to ensure it is
picked up in coverage.
 Where appropriate, final releases will be shared with partners for wider ongoing
circulation.
 The flow chart attached summarises the approvals and sign-off
procedure for joint press releases and statements.
 Contact details for the partner communications leads are provided on page 7.
o Boilerplate
The following statement must be adapted for use in all AGD project press releases: 
Project x is being funded with £x million from the UK Government, £x million from the Scottish
Government, and £x million from x Ayrshire Council as part of the £251 million Ayrshire Growth Deal, a ten
year investment programme jointly funded by the UK and Scottish governments and local authorities. 
o Media enquiries and FOI requests
The PMO and North Ayrshire Council Press Office will together lead on responding to
media enquiries relating to the Programme. Member authorities and partners should direct
relevant media enquiries to the PMO and North Ayrshire Council Press Office. The PMO
will lead on FOI enquiries relating to the programme.
FOI and media enquiries will be discussed as a standing agenda item at Ayrshire
Growth Deal Communication Group meetings. 
o Project-specific communications arrangements
When preparing and issuing media releases for specific AGD projects,
Communications Teams should ensure the following guiding principles are included:
• Media enquiries relating to individual projects should be dealt with by the relevant lead
organisation;
• All partners should advise the PMO of any forthcoming media activity to ensure
complementarity with other projects;
34

Page 35

7 
• All funding partners should be included and quoted;
• Final release should be shared with all communications partners, including
relevant FOI enquiries, for their information prior to issue to media.
o Social media
For generic AGD programme content, the PMO will lead in posting content from the
Ayrshire Growth Deal twitter account @ayrshiredeal.
The AGD main funders will be tagged in these posts -
@EastAyrshire @North_Ayrshire @southayrshire @scotgov @UKGovScotland. 
For project specific social media posts, the lead authority will post to their own accounts
and will tag @ayrshiredeal and relevant funders as required. If the project only receives
funding from one partner,
e.g. the UK Government, only @UKGovScotland should be tagged in that post. 
Local authority partners will retweet AGD social media posts on their own
networks. Similarly, the PMO will share relevant local authority posts on
@ayrshiredeal. 
It may be appropriate to tag specific Ministers in social media posts if they have their
own profile and they are quoted in the official press release to which the social media
post relates, e.g. @MathesonMichael.
o Communications Action Plan
The Communications Action Plan provides a forward plan of proposed communications
activities by all partners and will be updated by the partner Communications Leads and
PMO ahead of each quarterly meeting of the Ayrshire Economic Partnership Board and
Ayrshire Economic Joint Committee as part of the AGD Programme Update, as well as
each Ayrshire Growth Deal Communication Group meeting. 
Public information about the Ayrshire Growth Deal, such as where meeting papers will
be made publically available ahead of meetings, will be posted on @ayrshiredeal. 
Communications leads should inform other partners and the PMO in advance and at
the earliest opportunity of potential or actual media communication activities that are
not recorded on the Plan. 
o Photo opportunities
Photo opportunities will be organised by the relevant lead organisation on the project.
All partner Communications Leads must be informed in advance and will bear
responsibility for inviting relevant representatives from their organisation to take part. 
15. Communications information
Partners agree to use the following in order to achieve consistency in messaging: 
(i) The AGD website provides a short description of the Ayrshire Growth Deal, how it
came about, what it will do, what it hopes to achieve, and relevant details of
timeframes and investment. Additional frequently asked questions and agreed
responses are also captured on the website.
35

Page 36

8 
(ii) The Communications Action Plan, which sets out the planned and completed AGD
communications activities. It is the responsibility of the Communications Leads to
populate the Plan and keep it up to date, so that it can be reviewed and discussed
at Ayrshire Growth Deal communications group meetings. 
16. Escalation
If a concern arises within the partnership, the partners will work together to agree a
communications strategy, messaging and spokespersons prior to releasing any
statement or comment on the matter. 
17. Branding
Any physical manifestation of a project funded by the Ayrshire Growth Deal should be
appropriately branded with UK Government and Scottish Government logos where
applicable (i.e. where they have provided funding) including signage, and construction
hoarding. Where both government logos appear together they should sit alongside
each other and be of equal size. This branding must also apply to all public facing
documents or communications materials with relation to the Ayrshire Growth Deal
and its supported projects, e.g. press releases, websites, newsletters etc. 
Working together for a successful, fair and inclusive Ayrshire economy 
18. Review
This protocol will be reviewed annually by the Ayrshire Growth Deal
communications group, for discussion/approval by the Ayrshire Growth Deal
Management Group.
36

Page 37

9 
Ayrshire Growth Deal Communication Leads
Core communications group
Organisation Main Contact Contact details
Deal PMO   
UK Government
Paul Malley
(primary)    
Email:
Paul.Malley@ukgovscotland.gov.uk
Tel: 07795 262837 
Graham Bissell 
(secondary)
Kirsten McSporran
(secondary)
Tom Peterkin
(Special Political
Advisor)
Email:
Graham.Bissell@ukgovscotland.gov.uk
Tel: 07771 972607    
Email:
kirsten.mcsporran@ukgovscotland.gov.u
k  
Email:
thomas.peterkin@cabinetoffice.gov.uk
Tel: 07749 713914 
Scottish Government
Michael McHugh
(primary)
Email:
Michael.McHugh@gov.sco
t Tel: 07580 750033
Rebecca Macdonald
(secondary)
Email:
Rebecca.macdonald@gov.
scot Tel: 07468 764849 
North Ayrshire Council
Michele McColm
(primary)
Email: MicheleMccolm@north-
ayrshire.gov.uk Tel: 07766 725118
Mark Sugden
(secondary)
Email: MarkSugden@north-
ayrshire.gov.uk Tel: 07738
001718 
East Ayrshire Council
Lynne Buchanan
(primary)
Email: Lynne.Buchanan@east-
ayrshire.gov.uk Tel: 07827
841176
Catriona Cochrane
(secondary)
Email: Catriona.Cochrane@east-
ayrshire.gov.uk Tel: 07554 332374 
South Ayrshire Council
Sara Burdon
(primary)
Email: Sara.Burdon@south-
ayrshire.gov.uk Tel: 01292
616622
Jenna Robertson
(secondary)
Email: Jenna.Robertson@south-
ayrshire.gov.uk Tel: 01292 612343
37

Page 38

10 
Ayrshire Growth Deal Overview
The Ayrshire Growth Deal (AGD) is a £251.5 million, ten-year programme aimed at matching business growth
opportunities to employment progression, developing the future workforce and community development. Our
programme is based on the achievement of economic growth and inclusive growth, with a clear focus on
increasing innovation and productivity, while reducing inequality across the region.
Community Wealth Building (CWB) is a people centred approach to local economic
development, which redirects wealth back into the local economy. This will be the
cornerstone of the AGD to ensure lasting benefits for our businesses and
communities.
The AGD is based around five themes: 
Ayrshire Growth Deal Project
Funding Breakdown (£m) Lead Delivery Partner
Scot Gov UK Gov Council 
Aerospace &
Space
Spaceport Infrastructure 5.0 18.0  South Ayrshire
Council
Aerospace and Space Technology
Application Centre (ASTAC)
1.0 4.0 6.0
(SAC)
South Ayrshire
Council
Commercial Space Prestwick –
industrial and hangar
12.0 10.0 7.0
(SAC)
South Ayrshire
Council
Prestwick Infrastructure - roads 12.0  5.0
(SAC)
South Ayrshire
Council 
Economic
Infrastructure
HALO Kilmarnock 3.5 3.5 2.0
(EAC)
Halo Kilmarnock
Ltd
Ayrshire Engineering Park (Moorfield) 12.0  4.0
(EAC)
East Ayrshire
Council
Ayrshire Manufacturing Investment
Corridor (AMIC)
13.5 10.0  East Ayrshire
Council
2 projects
£23.5m  
Energy, Circular
Economy and
Environment
3 projects
5 projects
£69.5m
4 projects
£80m
Economic  Aerospace 
£25.5m  
38

Page 39

11 
i3 Flexible Space 11.0  4.0 (NAC) North Ayrshire
Council
i3 Digital Processing Manufacturing
Centre (DPMC) 
5.0 1.0 (NAC) North Ayrshire
Council 
Energy, Circular
Economy &
Environment
Community Renewable Energy Project
(CoRE) 
17.0 7.5
(EAC)
East Ayrshire
Council
Hunterston Strategic Development Area  18.0  North Ayrshire
Council
International Marine Science and
Environmental Centre (IMSE)   6.5  4.0 (NAC)  North Ayrshire
Council
Tourism The Great Harbour, at Irvine
Harbourside and Ardeer
9.0  5.0
(NAC)
North Ayrshire
Council
Marine Tourism 9.5   North Ayrshire
Council 
Communities
Digital Subsea Cable and Digital
Infrastructure
3.0 11.0  South Ayrshire
Council
Working for a Healthy Economy 3.0   North Ayrshire
Council
Ayrshire Skills Investment Fund 8.5   North Ayrshire
Council
Community Wealth Building Fund 3.0   North Ayrshire
Council 
TOTAL 103.0 103.0 45.5 
Grand Total £251.5 million
39

Page 40

12
Procedure for approving joint press releases and statements. 
40

Page 41

41

Page 42

42

Page 43

AYRSHIRE ECONOMIC JOINT COMMITTEE BOARD MEETING
20 MAY 2024 
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE MANUFACTURING INVESTMENT CORRIDOR PROJECT
AND AYRSHIRE ENGINEERING PARK
PURPOSE
1. To seek approval from the Ayrshire Economic Joint Committee on the change
management process in relation to the relocation of the Ayrshire Manufacturing
Investment Corridor (AMIC) to the Ayrshire Engineering Park (AEP) project,
following confirmation from both Scottish and UK Governments that the change
request has been agreed in principle along with the renaming of the site as the
Ayrshire Innovation Park.
RECOMMENDATIONS
2. It is recommended that Members:
(i) Approve the change request relating to the preferred relocation of AMIC to
Moorfield, alongside the Ayrshire Engineering Park
(ii) Note that this change has now been approved in principle by both
Governments, subject to a number of clarifications which will be provided as
part of the development of Outline Business Cases;
(iii) Note that the co-located development will be known as the Ayrshire
Innovation Park (AIP);
(iv) Note that revised Outline Business Cases will be prepared for submission
to both Governments by no later than May 2024;
(v) Note that a joint Full Business Case for Infrastructure Works will be prepared
for submission, to allow works to commence by January 2025;
(vi) Note that a further two Full Business Cases for AMIC (Centre of
Excellence/Food Grade Units and Large Advanced Manufacturing Unit) will
be submitted, allowing construction works to take place during 2026/27;
(vii) Note that a further two Full Business Cases for AEP (Small Terraced
Engineering Units and Large Engineering Units) will be submitted, allowing
construction works to take place during 2026/27; and
(viii) Otherwise, note the contents of this report.
BACKGROUND
3. On 19 November 2020, the Ayrshire Growth Deal (AGD) was signed off in a virtual
meeting attended by UK and Scottish Governments and the leaders of the three
Agenda Item 5
43

Page 44

Ayrshire Councils.  This secured £251.5m of funding to help realise Ayrshire’s
potential as a world-class business region for the food and drink, energy, tourism,
aerospace, manufacturing and engineering industries.  The majority of projects
within the AGD programme focus on infrastructure investment designed to act as
a catalyst for business growth and are complemented by a Skills and Inclusion
Programme and a Community Wealth Building programme to ensure maximum
benefit for Ayrshire communities.   
4. The AMIC project is one of 19 projects which make up the Ayrshire Growth Deal. 
Recognising that product development and innovation are key catalysts for
business growth, AMIC will enable the delivery of the Ayrshire Regional Economic
Strategy for the food and drink sector.  It will also provide a Food and Drink Centre
of Excellence and new advanced manufacturing and industrial units to service the
wider manufacturing industry in Ayrshire and South West Scotland.  This
investment in manufacturing across all sectors will provide industry growth and
attract inward investment to the Ayrshire region.   
5. The Ayrshire Engineering Park is an AGD project which will provide high quality
industrial premises for engineering and manufacturing companies, encompassing
a fully developed site with the required access and utilities infrastructure and digital
connectivity.  It will allow the expansion and development of Moorfield Industrial
Park in Kilmarnock, creating serviced and high quality business space, with a range
of units to support the advanced manufacturing and light engineering sectors in
Ayrshire. 
6. At the outset of the AMIC project and the first iteration of the outline business case,
a site options appraisal was undertaken and a number of sites were considered in
and around the Kilmarnock area. Following the options appraisal, two options
emerged; a site at Moorfield and a site between the A71 & A76 to the west of
Bellfield Interchange. 
7. The site at Bellfield Interchange was selected as the preferred option on the basis
that infrastructure improvements relating to capacity, pedestrian and vehicular
safety would be funded via the Strategic Transport Projects Review (STPR2) and
thereafter the Levelling Up Fund (LUF2).  Unfortunately, the Bellfield Interchange
was not included in STPR2 and the LUF2 funding application was unsuccessful. 
Transport Scotland have made a number of challenges to the selection of Bellfield
and as a result, the site remains constrained.   
8. The constraints surrounding Bellfield Interchange would require to be addressed
to enable economic growth at this location and with two unsuccessful funding bids,
the development of the transport infrastructure will be reliant on private sector
investment aligned to the development of industrial land allocated in LDP2. 
9. Due to the transport infrastructure constraints on the Bellfield site and inflationary
pressures, a proposal to transfer the location to Moorfield (alongside the AEP) was
discussed with UK and Scottish Governments in April and May 2023.  This was the
subject of further discussions at a joint meeting between the three councils and
both Governments on 3 October 2023 and the co-location proposal was verbally
approved in principle subject to the submission of the relevant change
44

Page 45

management documentation and supporting information.   The Ayrshire Regional
Economic Partnership considered and approved the proposals at its meeting on
the 25th April 2024. 
REVISED PROPOSALS 
10. In recognition of the above challenges, a change management request was
submitted from the PMO to both Governments on 6 February 2024 to co-locate the
AMIC project alongside the AEP at Moorfield.  The paper set out the nature and
reasons for the change, including an analysis of impacts and options appraisal. 
The approach set out is considered to benefit both projects by releasing economies
of scale in relation to land purchase, infrastructure works and contract
procurement.   
11. On behalf of both Governments, the Scottish Government provided their in-
principle agreement to the change request on 14 March 2024.  A number of
conditions were attached to this including further clarification in relation to
economic analysis, job numbers and the funding profile.  These issues will be
addressed in the development of Outline Business Cases (OBCs) for both projects.   
12. Importantly, East Ayrshire Council purchased the land at Moorfield in March 2023,
which provides more certainty in relation to the construction timeline.  Furthermore,
the change of location removes the transport infrastructure constraints referred to
at the previously preferred site.  There are a number of other benefits to the
proposed co-location, which are highlighted below: 
• Maximisation of resource allocation, with roads and infrastructure costs being
shared across both projects. 
• The proposed site has a Business and Industry allocation in the current
approved Local Development Plan streamlining the planning application
process;
• Limited access constraints identified in the traffic impact study undertaken; 
• Expedited time line for the AMIC delivery due to established existing traffic
impact studies and site investigations/topographical surveys completed;
• Expedited delivery of the AMIC project as the site is already in the ownership
of East Ayrshire Council; as such there is no longer a risk that a site cannot be
secured for the development and purchase costs are known;
• There are already existing large and successful food and drink manufacturers
situated in and around the Moorfield site to utilise the centre’s resources; 
• Easy access from trunk roads across the region; 
• Good existing bus and walking routes to the site with the opportunity to provide
further enhancements and encourage active travel linking up to a number of
improved cycle routes currently planned by Ayrshire Roads Alliance (ARA);
• Adjacent land zoned in the Local Development Plan allocated for Business and
Industry provides future opportunities for growth and the development of more
industrial space for manufacturing, engineering and food & drink sectors; 
• Provides opportunities for shared learning and training across both sectors; and 
45

Page 46

• Opportunities for networking among the unit occupiers to build good supply
chain opportunities and enhance community wealth building.  Tenants of the
units and users of the Centre of Excellence will be encouraged to seek out
supply chain and collaboration opportunities with surrounding businesses
which can be facilitated by East Ayrshire Council’s Business Support Team. 
IMPACT OF CO-LOCATION 
13. Whilst the objectives for both projects remain broadly unchanged as a result of the
change request, it should be noted that the proposed development space at AMIC
has been reduced from 7,864 sq m to 5,814 sq m and the proposed development
space at AEP has been reduced from 10,576 sq m to 7,250 sq m.   
14. The co-location will create a new Ayrshire Innovation Park, incorporating transport
links, public realm areas, cycle paths, walkways and an onsite coffee shop. The
creation of these new public realm spaces will deliver social and community
benefits to the wider area and will increase the sustainability of the development. 
15. The reductions in floor space highlighted at paragraph 13 resulted from a detailed
costings process which acknowledged significant inflationary pressures and other
drivers such as the need to build in net zero measures.   Clearly, this will reduce
the numbers of businesses able to utilise the space on a day to day basis and will
also impact upon the total number of jobs created.   
16. An economic modelling exercise is currently underway.  This was carried out by
the PMO to analyse the impact of both developments in terms of jobs created
(construction and non-construction).  The Glasgow City Region Intelligence Hub is
carrying out further analysis and verification of the initial figures generated and an
update will be provided in the OBC.   
17. The co-location at Moorfield also affords an opportunity for both projects to take
advantage of the new 5G connectivity programme which is being funded by the UK
Government.  £3.8 million has been awarded to the Ayrshire region from the 5G
Innovation Regions Fund and the Ayrshire Innovation Park will be established as
one of a number of Regional Strategic Wireless Innovation Hubs across our region.   
18. The 5G project under development at Moorfield will focus on working with existing
manufacturing and other supply chain businesses within all phases of the Moorfield
Industrial Parks to facilitate the adoption of narrowband IoT (Internet of Things),
enabling better data management and IoT integration. £450,000 has been
allocated to this project from the wider fund. 
19. The successful delivery of this project will result in the establishment of an
ecosystem where 5G technology drives economic growth, technological
development and industrial excellence and in doing all of this, will provide essential
digital infrastructure support to businesses locating at the AIP.  Lessons learned
during the delivery of the 5GIR project will inform the development of digital
connectivity and infrastructure delivered as part of the AMIC and AEP projects.   
46

Page 47

PROJECT MANAGEMENT AND TIMELINE 
20. The changes to the projects have necessitated some significant changes to the
timeline and financial projections for both projects.  A summary of these changes
is set out below.   
Ayrshire Manufacturing Investment Corridor 
21. The original funding profile for the AMIC project is set out in the table below.   
Original Funding Profile for AMIC Project, 2019 
Source 23/24
(£m)
24/25
(£m)
25/26
(£m)
26/27
(£m)
27/28
(£m)
28/29
(£m)
29/30
(£m)
30/31
(£m)
Total
UK
Government 0.060 0.625 0.625 1.845 1.846 1.000 0.940 3.059 10.000
Scottish
Government 0.500  0.625 1.125 2.680 2.827 1.647 4.096 13.500
East Ayrshire
Council         
Total 0.560 0.625 1.250 2.970 4.526 3.827 2.587 7.155 23.500 
22. The new funding profile for the AMIC project is set out in the table below.  As the
table demonstrates, East Ayrshire Council expects to reclaim its spend to date
(£1.140m) during 2024/25.  It is also noted that overall spend will be incurred over
a shorter period, concluding by the end of 2026/27.  
23. 
Revised Funding Profile for AMIC Project, 2024 
Source 21/22
(£m)
22/23
(£m)
23/24
(£m)
24/25 (£m) 25/26 (£m) 26/27 (£m) Total
UK
Government    0.400 8.100 1.500 10.000
Scottish
Government    3.920 5.480 4.100 13.500
East Ayrshire
Council 0.067 0.323 0.750 -1.140   
Total 0.067 0.323 0.750 3.180 13.580 5.600 23.500 
24. In terms of project milestones, it is anticipated that the new Outline Business Case
(OBC) will be submitted to both Governments by May 2024.  In order to manage
risk and meet the preferred procurement strategy, it is intended to split the Full
Business Case (FBC) into three new FBCs as follows: 
• FBC Infrastructure (joint FBC with AEP).  Submission by no later than 7
October 2024 and final approval by both Governments by 2 December
2024.  Construction works to commence in January 2025, expected
duration 10-12 months.  
47

Page 48

• FBC Centre of Excellence & Food Grade Units.  Submission by no later
than 12 January 2026 and final approval by both Governments by 20
March 2026.  Construction works to commence in May 2026, duration
12 months.
• FBC Large Advanced Manufacturing Unit.  Submission by no later than
2 December 2024 and final approval by both Governments by 14
February 2025.  Construction works to commence in January 2026,
duration 12 months.   
Ayrshire Engineering Park 
25. The original funding profile for the AEP project is set out in the table below. 
Original Funding Profile for AEP Project, 2019 
Source 21/22  
(£m)
22/23
(£m)
23/24
(£m)
24/25
(£m)
25/26
(£m)
26/27
(£m)
27/28
(£m)
28/29
(£m)
Total
UK
Government         
Scottish
Government  1.789 1.729 2.249 2.541 1.692 1.000 1.000 12.000
East Ayrshire
Council 0.350 1.000 1.000 0.650 0.500 0.500   4.000
Total 0.350 2.789 2.729 2.899 3.041 2.192 1.000 1.000 16.000 
26. The new funding profile for AEP is set out below.  As the table demonstrates, East
Ayrshire Council expects to reclaim its spend to date (£1.454m) during 2024/25.  It
is also noted that overall spend will be incurred over a shorter period, concluding
by the end of 2026/27.   
Revised Funding Profile for AEP Project, 2024 
Source 20/21
(£m)
21/22  
(£m)
22/23
(£m)
23/24
(£m)
24/25
(£m)
25/26
(£m)
26/27
(£m)
Total
UK Government        
Scottish
Government     4.277 2.791 4.932 12.000
East Ayrshire
Council 0.003 0.107 0.744 0.600 -1.454 2.106 1.894 4.000
Total 0.003 0.107 0.744 0.600 2.899 4.897 6.826 16.000 
27. Looking at key milestones, the Outline Business Case for AEP will be submitted by
May 2024 and similar to AMIC, three FBCs will be produced thereafter.  The first,
as referred to in paragraph 18, is the Joint Infrastructure FBC.  The others are as
follows: 
48

Page 49

• FBC Small Terraced Engineering Units.  Submission by no later than 17
March 2025 and final approval by both Governments by 9 May 2025. 
Construction of this phase will start towards the end of the infrastructure
construction phase once access to the development plots are available and
the FBC’s are proposed accordingly to dovetail with construction
programme for both parts of the project.
• FBC Large Engineering Units.  Submission by no later than 2 December
2024 and final approval by both Governments by 14 February 2025. 
Construction works to commence in January 2026, duration 12 months.   
IMPLICATIONS 
28. There are a number of implications arising from the report, summarised in the table
below: 
Implications Yes No
Paragraph
number in
report
1. Policy/Strategic Planning x  29-32
2. Financial x  33-35
3. Governance/Legal x  36-39
4. Human Resources x  40
5. Equality & Fairer Scotland Duty x  41
6. Risk  x  42-45
7. Community Wealth Building x  46-47
8. Net Zero x  48 
POLICY/STRATEGIC PLANNING IMPLICATIONS 
29. The sectoral focus on food and drink and advanced manufacturing, amongst
others, is a key theme of the Regional Economic Strategy.  AMIC and AEP will
predominantly deliver upon two of the 6 key priorities of the Strategy: Support for
Enterprise and Innovation.   
30. The change management request for the AMIC & AEP projects will not affect the
delivery of the strategic objectives and in fact will help ensure efficient delivery.   
31. The AMIC project will support the delivery of the AGD’s strategic objectives.  In
particular, the project will demonstrate to local and international food and drink
manufacturing that Ayrshire has high aspirations for future growth and
development of the food and drink manufacturing sector and that these aspirations
are backed by substantial investment. 
32. The AEP Project will provide businesses with a base and facilities to grow and will
support the existing engineering supply chain. It will also provide opportunities for
businesses to share knowledge and work collaboratively. AEP will demonstrate
commitment to the engineering and light manufacturing sector, encouraging
businesses to relocate to the area and ultimately driving inward investment.
49

Page 50

FINANCIAL IMPLICATIONS 
33. As noted at paragraph 22, the AMIC project has incurred spend of £1.140m to date,
which East Ayrshire Council expects will be drawn down from the UK and Scottish
Governments during 2024/25.  As noted at paragraph 25, the AEP project has
incurred spend of £1.454m to date, which the Council anticipates will be drawn
down from the Scottish Government during 2024/25.   
34. Revised funding profiles have been approved following the change request.  Whilst
the overall project budgets remain unchanged, the profiling of spend has been
substantially altered and both projects are expected to incur all project costs over
the next three years (to the end of 2026/27) in line with the revised timelines.   
35. The project team are working with Finance colleagues to agree a consistent and
transparent apportionment of any shared costs such as land purchase and
infrastructure costs over the two projects. 
GOVERNANCE/LEGAL IMPLICATIONS 
36. The Project Teams have developed governance structures in accordance with
AGD PMO governance requirements to oversee both projects and sub-group
meetings have commenced.  The AGD Steering Group is responsible for
monitoring progress across all projects and project leads are required to provide
regular updates to this group.   
37. An Ayrshire Innovation Park Steering Group has been established and is chaired
by the Head of East Ayrshire Council’s Economic Growth Service, with
representation from key partners and stakeholders.  This Group acts as the
strategic and operational decision-making body for both AMIC and AEP.   
38. A number of sub-groups have also been formed which focus on specific areas
including marketing and customer focus, operations, industry focus and
architectural design.   
39. Projects are being managed by East Ayrshire Council in accordance with
recognised project management (PRINCE 2) principles.  Where issues are
identified, remedial action is taken to ensure delivery remains in line with Outline
Business Case projections.   
HUMAN RESOURCE IMPLICATIONS 
40. Project Teams have been recruited from within existing resources, and there are
no additional staffing requirements at this time.   
EQUALITY AND FAIRER SCOTLAND DUTY IMPLICATIONS 
41. An Equality Impact Assessment will be carried out and finalised prior to the
submission of the Full Business Case.  Project Teams are working with East
Ayrshire Council’s Equalities Lead and the AGD PMO on this process.  
50

Page 51

RISK IMPLICATIONS 
42. Strategic and operational risk registers continue to be developed, reviewed and
updated for the AGD programme.  The Programme Risk Register has been
updated in accordance with the commitment to be reviewed every quarter. 
43. The co-location of both projects is considered to mitigate the risk associated with
construction costs as the new approach releases economies of scale in relation to
land purchase, infrastructure works and contract procurement.   
44. The risk associated with transport implications has been removed due to the co-
location, as the Moorfield site is not considered to have the same restrictions in
terms of traffic as Bellfield Interchange.   
45. The risk of not attracting commercial interest in the project has been reduced as
the co-location strengthens the area as a key location for the Food, Drink,
Engineering and Light Manufacturing sectors. 
COMMUNITY WEALTH BUILDING IMPLICATIONS 
46. Procurement contracts for the construction of the projects will be aligned with the
principles set out in the Ayrshire Community Wealth Building Charter and these will
include community benefits. Within the leases for the incubation units and
speculative industrial space for both projects, provision will be made for both
community wealth building and fair work practices to ensure that businesses
utilising and benefiting from the facilities are following best practice. 
47. Both projects will work closely with educational establishments and communities
to raise aspiration and ambition, provide employment and skills support, and
improve access to jobs through innovative community empowerment and
employability programmes. 
NET ZERO IMPLICATIONS 
48. The development will include significant investment in new, sustainable transport
infrastructure which will improve accessibility for local communities.  An active
travel cycle network is also under development via a separate project.  The route
will included the boundary of the AIP, linking the site with other towns and villages
in the region. 
49. The development will include a range of innovative measures aimed at maximising
Net Zero potential.  East Ayrshire Council are investigating the feasibility of working
with an Energy Partner to deliver renewable energy to the AGD projects and
surrounding industrial estates. 
CONCLUSION 
50. The approval of the change request will result in the co-location of both the AMIC
and AEP projects on a site to be known as the Ayrshire Innovation Park.  This
51

Page 52

approach is considered to benefit both projects by releasing economies of scale in
relation to land purchase, infrastructure works and contract procurement.  It also
removes the traffic and transport barriers which had acted as a constraint on
development of the previously identified site. 
51. With the change agreed and the site already in the ownership of East Ayrshire
Council, the focus will now move to the finalisation of Outline Business Cases for
both projects.  Beyond that, it is anticipated that the preparation of Full Business
Cases will be completed in 2025, and subject to approval, construction works will
commence during 2025/26.   
Implementation Officer: David McDowall, Head of Economic Growth, East Ayrshire
Council 
Email: david.mcdowall@east-ayrshire.gov.uk 
Persons to contact: Fiona Paterson, Project Development Manager (Ayrshire
Growth Deal), East Ayrshire Council
Email: fiona.paterson2@east-ayrshire.gov.uk   
Background papers:  AMIC & AEP Change Management Submission, February
2024         