AYRSHIRE ECONOMIC JOINT COMMITTEE BOARD MEETING
20 MAY 2024 
REPORT BY HEAD OF ECONOMIC GROWTH
EAST AYRSHIRE COUNCIL
SUBJECT: AYRSHIRE MANUFACTURING INVESTMENT CORRIDOR PROJECT
AND AYRSHIRE ENGINEERING PARK
PURPOSE
1. To seek approval from the Ayrshire Economic Joint Committee on the change
management process in relation to the relocation of the Ayrshire Manufacturing
Investment Corridor (AMIC) to the Ayrshire Engineering Park (AEP) project,
following confirmation from both Scottish and UK Governments that the change
request has been agreed in principle along with the renaming of the site as the
Ayrshire Innovation Park.
RECOMMENDATIONS
2. It is recommended that Members:
(i) Approve the change request relating to the preferred relocation of AMIC to
Moorfield, alongside the Ayrshire Engineering Park
(ii) Note that this change has now been approved in principle by both
Governments, subject to a number of clarifications which will be provided as
part of the development of Outline Business Cases;
(iii) Note that the co-located development will be known as the Ayrshire
Innovation Park (AIP);
(iv) Note that revised Outline Business Cases will be prepared for submission
to both Governments by no later than May 2024;
(v) Note that a joint Full Business Case for Infrastructure Works will be prepared
for submission, to allow works to commence by January 2025;
(vi) Note that a further two Full Business Cases for AMIC (Centre of
Excellence/Food Grade Units and Large Advanced Manufacturing Unit) will
be submitted, allowing construction works to take place during 2026/27;
(vii) Note that a further two Full Business Cases for AEP (Small Terraced
Engineering Units and Large Engineering Units) will be submitted, allowing
construction works to take place during 2026/27; and
(viii) Otherwise, note the contents of this report.
BACKGROUND
3. On 19 November 2020, the Ayrshire Growth Deal (AGD) was signed off in a virtual
meeting attended by UK and Scottish Governments and the leaders of the three

Page 2

Ayrshire Councils.  This secured £251.5m of funding to help realise Ayrshire’s
potential as a world-class business region for the food and drink, energy, tourism,
aerospace, manufacturing and engineering industries.  The majority of projects
within the AGD programme focus on infrastructure investment designed to act as
a catalyst for business growth and are complemented by a Skills and Inclusion
Programme and a Community Wealth Building programme to ensure maximum
benefit for Ayrshire communities.   
4. The AMIC project is one of 19 projects which make up the Ayrshire Growth Deal. 
Recognising that product development and innovation are key catalysts for
business growth, AMIC will enable the delivery of the Ayrshire Regional Economic
Strategy for the food and drink sector.  It will also provide a Food and Drink Centre
of Excellence and new advanced manufacturing and industrial units to service the
wider manufacturing industry in Ayrshire and South West Scotland.  This
investment in manufacturing across all sectors will provide industry growth and
attract inward investment to the Ayrshire region.   
5. The Ayrshire Engineering Park is an AGD project which will provide high quality
industrial premises for engineering and manufacturing companies, encompassing
a fully developed site with the required access and utilities infrastructure and digital
connectivity.  It will allow the expansion and development of Moorfield Industrial
Park in Kilmarnock, creating serviced and high quality business space, with a range
of units to support the advanced manufacturing and light engineering sectors in
Ayrshire. 
6. At the outset of the AMIC project and the first iteration of the outline business case,
a site options appraisal was undertaken and a number of sites were considered in
and around the Kilmarnock area. Following the options appraisal, two options
emerged; a site at Moorfield and a site between the A71 & A76 to the west of
Bellfield Interchange. 
7. The site at Bellfield Interchange was selected as the preferred option on the basis
that infrastructure improvements relating to capacity, pedestrian and vehicular
safety would be funded via the Strategic Transport Projects Review (STPR2) and
thereafter the Levelling Up Fund (LUF2).  Unfortunately, the Bellfield Interchange
was not included in STPR2 and the LUF2 funding application was unsuccessful. 
Transport Scotland have made a number of challenges to the selection of Bellfield
and as a result, the site remains constrained.   
8. The constraints surrounding Bellfield Interchange would require to be addressed
to enable economic growth at this location and with two unsuccessful funding bids,
the development of the transport infrastructure will be reliant on private sector
investment aligned to the development of industrial land allocated in LDP2. 
9. Due to the transport infrastructure constraints on the Bellfield site and inflationary
pressures, a proposal to transfer the location to Moorfield (alongside the AEP) was
discussed with UK and Scottish Governments in April and May 2023.  This was the
subject of further discussions at a joint meeting between the three councils and
both Governments on 3 October 2023 and the co-location proposal was verbally
approved in principle subject to the submission of the relevant change

Page 3

management documentation and supporting information.   The Ayrshire Regional
Economic Partnership considered and approved the proposals at its meeting on
the 25th April 2024. 
REVISED PROPOSALS 
10. In recognition of the above challenges, a change management request was
submitted from the PMO to both Governments on 6 February 2024 to co-locate the
AMIC project alongside the AEP at Moorfield.  The paper set out the nature and
reasons for the change, including an analysis of impacts and options appraisal. 
The approach set out is considered to benefit both projects by releasing economies
of scale in relation to land purchase, infrastructure works and contract
procurement.   
11. On behalf of both Governments, the Scottish Government provided their in-
principle agreement to the change request on 14 March 2024.  A number of
conditions were attached to this including further clarification in relation to
economic analysis, job numbers and the funding profile.  These issues will be
addressed in the development of Outline Business Cases (OBCs) for both projects.   
12. Importantly, East Ayrshire Council purchased the land at Moorfield in March 2023,
which provides more certainty in relation to the construction timeline.  Furthermore,
the change of location removes the transport infrastructure constraints referred to
at the previously preferred site.  There are a number of other benefits to the
proposed co-location, which are highlighted below: 
• Maximisation of resource allocation, with roads and infrastructure costs being
shared across both projects. 
• The proposed site has a Business and Industry allocation in the current
approved Local Development Plan streamlining the planning application
process;
• Limited access constraints identified in the traffic impact study undertaken; 
• Expedited time line for the AMIC delivery due to established existing traffic
impact studies and site investigations/topographical surveys completed;
• Expedited delivery of the AMIC project as the site is already in the ownership
of East Ayrshire Council; as such there is no longer a risk that a site cannot be
secured for the development and purchase costs are known;
• There are already existing large and successful food and drink manufacturers
situated in and around the Moorfield site to utilise the centre’s resources; 
• Easy access from trunk roads across the region; 
• Good existing bus and walking routes to the site with the opportunity to provide
further enhancements and encourage active travel linking up to a number of
improved cycle routes currently planned by Ayrshire Roads Alliance (ARA);
• Adjacent land zoned in the Local Development Plan allocated for Business and
Industry provides future opportunities for growth and the development of more
industrial space for manufacturing, engineering and food & drink sectors; 
• Provides opportunities for shared learning and training across both sectors; and

Page 4

• Opportunities for networking among the unit occupiers to build good supply
chain opportunities and enhance community wealth building.  Tenants of the
units and users of the Centre of Excellence will be encouraged to seek out
supply chain and collaboration opportunities with surrounding businesses
which can be facilitated by East Ayrshire Council’s Business Support Team. 
IMPACT OF CO-LOCATION 
13. Whilst the objectives for both projects remain broadly unchanged as a result of the
change request, it should be noted that the proposed development space at AMIC
has been reduced from 7,864 sq m to 5,814 sq m and the proposed development
space at AEP has been reduced from 10,576 sq m to 7,250 sq m.   
14. The co-location will create a new Ayrshire Innovation Park, incorporating transport
links, public realm areas, cycle paths, walkways and an onsite coffee shop. The
creation of these new public realm spaces will deliver social and community
benefits to the wider area and will increase the sustainability of the development. 
15. The reductions in floor space highlighted at paragraph 13 resulted from a detailed
costings process which acknowledged significant inflationary pressures and other
drivers such as the need to build in net zero measures.   Clearly, this will reduce
the numbers of businesses able to utilise the space on a day to day basis and will
also impact upon the total number of jobs created.   
16. An economic modelling exercise is currently underway.  This was carried out by
the PMO to analyse the impact of both developments in terms of jobs created
(construction and non-construction).  The Glasgow City Region Intelligence Hub is
carrying out further analysis and verification of the initial figures generated and an
update will be provided in the OBC.   
17. The co-location at Moorfield also affords an opportunity for both projects to take
advantage of the new 5G connectivity programme which is being funded by the UK
Government.  £3.8 million has been awarded to the Ayrshire region from the 5G
Innovation Regions Fund and the Ayrshire Innovation Park will be established as
one of a number of Regional Strategic Wireless Innovation Hubs across our region.   
18. The 5G project under development at Moorfield will focus on working with existing
manufacturing and other supply chain businesses within all phases of the Moorfield
Industrial Parks to facilitate the adoption of narrowband IoT (Internet of Things),
enabling better data management and IoT integration. £450,000 has been
allocated to this project from the wider fund. 
19. The successful delivery of this project will result in the establishment of an
ecosystem where 5G technology drives economic growth, technological
development and industrial excellence and in doing all of this, will provide essential
digital infrastructure support to businesses locating at the AIP.  Lessons learned
during the delivery of the 5GIR project will inform the development of digital
connectivity and infrastructure delivered as part of the AMIC and AEP projects.

Page 5

PROJECT MANAGEMENT AND TIMELINE 
20. The changes to the projects have necessitated some significant changes to the
timeline and financial projections for both projects.  A summary of these changes
is set out below.   
Ayrshire Manufacturing Investment Corridor 
21. The original funding profile for the AMIC project is set out in the table below.   
Original Funding Profile for AMIC Project, 2019 
Source 23/24
(£m)
24/25
(£m)
25/26
(£m)
26/27
(£m)
27/28
(£m)
28/29
(£m)
29/30
(£m)
30/31
(£m)
Total
UK
Government 0.060 0.625 0.625 1.845 1.846 1.000 0.940 3.059 10.000
Scottish
Government 0.500  0.625 1.125 2.680 2.827 1.647 4.096 13.500
East Ayrshire
Council         
Total 0.560 0.625 1.250 2.970 4.526 3.827 2.587 7.155 23.500 
22. The new funding profile for the AMIC project is set out in the table below.  As the
table demonstrates, East Ayrshire Council expects to reclaim its spend to date
(£1.140m) during 2024/25.  It is also noted that overall spend will be incurred over
a shorter period, concluding by the end of 2026/27.  
23. 
Revised Funding Profile for AMIC Project, 2024 
Source 21/22
(£m)
22/23
(£m)
23/24
(£m)
24/25 (£m) 25/26 (£m) 26/27 (£m) Total
UK
Government    0.400 8.100 1.500 10.000
Scottish
Government    3.920 5.480 4.100 13.500
East Ayrshire
Council 0.067 0.323 0.750 -1.140   
Total 0.067 0.323 0.750 3.180 13.580 5.600 23.500 
24. In terms of project milestones, it is anticipated that the new Outline Business Case
(OBC) will be submitted to both Governments by May 2024.  In order to manage
risk and meet the preferred procurement strategy, it is intended to split the Full
Business Case (FBC) into three new FBCs as follows: 
• FBC Infrastructure (joint FBC with AEP).  Submission by no later than 7
October 2024 and final approval by both Governments by 2 December
2024.  Construction works to commence in January 2025, expected
duration 10-12 months.

Page 6

• FBC Centre of Excellence & Food Grade Units.  Submission by no later
than 12 January 2026 and final approval by both Governments by 20
March 2026.  Construction works to commence in May 2026, duration
12 months.
• FBC Large Advanced Manufacturing Unit.  Submission by no later than
2 December 2024 and final approval by both Governments by 14
February 2025.  Construction works to commence in January 2026,
duration 12 months.   
Ayrshire Engineering Park 
25. The original funding profile for the AEP project is set out in the table below. 
Original Funding Profile for AEP Project, 2019 
Source 21/22  
(£m)
22/23
(£m)
23/24
(£m)
24/25
(£m)
25/26
(£m)
26/27
(£m)
27/28
(£m)
28/29
(£m)
Total
UK
Government         
Scottish
Government  1.789 1.729 2.249 2.541 1.692 1.000 1.000 12.000
East Ayrshire
Council 0.350 1.000 1.000 0.650 0.500 0.500   4.000
Total 0.350 2.789 2.729 2.899 3.041 2.192 1.000 1.000 16.000 
26. The new funding profile for AEP is set out below.  As the table demonstrates, East
Ayrshire Council expects to reclaim its spend to date (£1.454m) during 2024/25.  It
is also noted that overall spend will be incurred over a shorter period, concluding
by the end of 2026/27.   
Revised Funding Profile for AEP Project, 2024 
Source 20/21
(£m)
21/22  
(£m)
22/23
(£m)
23/24
(£m)
24/25
(£m)
25/26
(£m)
26/27
(£m)
Total
UK Government        
Scottish
Government     4.277 2.791 4.932 12.000
East Ayrshire
Council 0.003 0.107 0.744 0.600 -1.454 2.106 1.894 4.000
Total 0.003 0.107 0.744 0.600 2.899 4.897 6.826 16.000 
27. Looking at key milestones, the Outline Business Case for AEP will be submitted by
May 2024 and similar to AMIC, three FBCs will be produced thereafter.  The first,
as referred to in paragraph 18, is the Joint Infrastructure FBC.  The others are as
follows:

Page 7

• FBC Small Terraced Engineering Units.  Submission by no later than 17
March 2025 and final approval by both Governments by 9 May 2025. 
Construction of this phase will start towards the end of the infrastructure
construction phase once access to the development plots are available and
the FBC’s are proposed accordingly to dovetail with construction
programme for both parts of the project.
• FBC Large Engineering Units.  Submission by no later than 2 December
2024 and final approval by both Governments by 14 February 2025. 
Construction works to commence in January 2026, duration 12 months.   
IMPLICATIONS 
28. There are a number of implications arising from the report, summarised in the table
below: 
Implications Yes No
Paragraph
number in
report
1. Policy/Strategic Planning x  29-32
2. Financial x  33-35
3. Governance/Legal x  36-39
4. Human Resources x  40
5. Equality & Fairer Scotland Duty x  41
6. Risk  x  42-45
7. Community Wealth Building x  46-47
8. Net Zero x  48 
POLICY/STRATEGIC PLANNING IMPLICATIONS 
29. The sectoral focus on food and drink and advanced manufacturing, amongst
others, is a key theme of the Regional Economic Strategy.  AMIC and AEP will
predominantly deliver upon two of the 6 key priorities of the Strategy: Support for
Enterprise and Innovation.   
30. The change management request for the AMIC & AEP projects will not affect the
delivery of the strategic objectives and in fact will help ensure efficient delivery.   
31. The AMIC project will support the delivery of the AGD’s strategic objectives.  In
particular, the project will demonstrate to local and international food and drink
manufacturing that Ayrshire has high aspirations for future growth and
development of the food and drink manufacturing sector and that these aspirations
are backed by substantial investment. 
32. The AEP Project will provide businesses with a base and facilities to grow and will
support the existing engineering supply chain. It will also provide opportunities for
businesses to share knowledge and work collaboratively. AEP will demonstrate
commitment to the engineering and light manufacturing sector, encouraging
businesses to relocate to the area and ultimately driving inward investment.

Page 8

FINANCIAL IMPLICATIONS 
33. As noted at paragraph 22, the AMIC project has incurred spend of £1.140m to date,
which East Ayrshire Council expects will be drawn down from the UK and Scottish
Governments during 2024/25.  As noted at paragraph 25, the AEP project has
incurred spend of £1.454m to date, which the Council anticipates will be drawn
down from the Scottish Government during 2024/25.   
34. Revised funding profiles have been approved following the change request.  Whilst
the overall project budgets remain unchanged, the profiling of spend has been
substantially altered and both projects are expected to incur all project costs over
the next three years (to the end of 2026/27) in line with the revised timelines.   
35. The project team are working with Finance colleagues to agree a consistent and
transparent apportionment of any shared costs such as land purchase and
infrastructure costs over the two projects. 
GOVERNANCE/LEGAL IMPLICATIONS 
36. The Project Teams have developed governance structures in accordance with
AGD PMO governance requirements to oversee both projects and sub-group
meetings have commenced.  The AGD Steering Group is responsible for
monitoring progress across all projects and project leads are required to provide
regular updates to this group.   
37. An Ayrshire Innovation Park Steering Group has been established and is chaired
by the Head of East Ayrshire Council’s Economic Growth Service, with
representation from key partners and stakeholders.  This Group acts as the
strategic and operational decision-making body for both AMIC and AEP.   
38. A number of sub-groups have also been formed which focus on specific areas
including marketing and customer focus, operations, industry focus and
architectural design.   
39. Projects are being managed by East Ayrshire Council in accordance with
recognised project management (PRINCE 2) principles.  Where issues are
identified, remedial action is taken to ensure delivery remains in line with Outline
Business Case projections.   
HUMAN RESOURCE IMPLICATIONS 
40. Project Teams have been recruited from within existing resources, and there are
no additional staffing requirements at this time.   
EQUALITY AND FAIRER SCOTLAND DUTY IMPLICATIONS 
41. An Equality Impact Assessment will be carried out and finalised prior to the
submission of the Full Business Case.  Project Teams are working with East
Ayrshire Council’s Equalities Lead and the AGD PMO on this process.

Page 9

RISK IMPLICATIONS 
42. Strategic and operational risk registers continue to be developed, reviewed and
updated for the AGD programme.  The Programme Risk Register has been
updated in accordance with the commitment to be reviewed every quarter. 
43. The co-location of both projects is considered to mitigate the risk associated with
construction costs as the new approach releases economies of scale in relation to
land purchase, infrastructure works and contract procurement.   
44. The risk associated with transport implications has been removed due to the co-
location, as the Moorfield site is not considered to have the same restrictions in
terms of traffic as Bellfield Interchange.   
45. The risk of not attracting commercial interest in the project has been reduced as
the co-location strengthens the area as a key location for the Food, Drink,
Engineering and Light Manufacturing sectors. 
COMMUNITY WEALTH BUILDING IMPLICATIONS 
46. Procurement contracts for the construction of the projects will be aligned with the
principles set out in the Ayrshire Community Wealth Building Charter and these will
include community benefits. Within the leases for the incubation units and
speculative industrial space for both projects, provision will be made for both
community wealth building and fair work practices to ensure that businesses
utilising and benefiting from the facilities are following best practice. 
47. Both projects will work closely with educational establishments and communities
to raise aspiration and ambition, provide employment and skills support, and
improve access to jobs through innovative community empowerment and
employability programmes. 
NET ZERO IMPLICATIONS 
48. The development will include significant investment in new, sustainable transport
infrastructure which will improve accessibility for local communities.  An active
travel cycle network is also under development via a separate project.  The route
will included the boundary of the AIP, linking the site with other towns and villages
in the region. 
49. The development will include a range of innovative measures aimed at maximising
Net Zero potential.  East Ayrshire Council are investigating the feasibility of working
with an Energy Partner to deliver renewable energy to the AGD projects and
surrounding industrial estates. 
CONCLUSION 
50. The approval of the change request will result in the co-location of both the AMIC
and AEP projects on a site to be known as the Ayrshire Innovation Park.  This

Page 10

approach is considered to benefit both projects by releasing economies of scale in
relation to land purchase, infrastructure works and contract procurement.  It also
removes the traffic and transport barriers which had acted as a constraint on
development of the previously identified site. 
51. With the change agreed and the site already in the ownership of East Ayrshire
Council, the focus will now move to the finalisation of Outline Business Cases for
both projects.  Beyond that, it is anticipated that the preparation of Full Business
Cases will be completed in 2025, and subject to approval, construction works will
commence during 2025/26.   
Implementation Officer: David McDowall, Head of Economic Growth, East Ayrshire
Council 
Email: david.mcdowall@east-ayrshire.gov.uk 
Persons to contact: Fiona Paterson, Project Development Manager (Ayrshire
Growth Deal), East Ayrshire Council
Email: fiona.paterson2@east-ayrshire.gov.uk   
Background papers:  AMIC & AEP Change Management Submission, February
2024