Democracy Spraffa

Agenda Document Pack - Audit and Scrutiny Committee - 15/11/2022

North Ayrshire Council · 15 November 2022
Back to Audit and Scrutiny Committee — 15 November 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE         
Audit and Scrutiny Committee 
A Meeting of the Audit and Scrutiny Committee of North Ayrshire Council will be
held in the Council Chambers, Ground Floor, Cunninghame House, Irvine, KA12
8EE on Tuesday, 15 November 2022 at 10:00 to consider the undernoted business. 
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.  Where possible, the meeting will be live-streamed
and available to view at https://north-ayrshire.public-
i.tv/core/portal/home.   
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
2 Minutes
The accuracy of the Minutes of the Meeting of the Audit and Scrutiny
Committee held on 27 September 2022 will be confirmed and the Minutes
signed in accordance with Paragraph 7 (1) of Schedule 7 of the Local
Government (Scotland) Act 1973 (copy enclosed). 
3 Petition: Proposed Car Parking Charges: Owenward East and
Almswall Road Car Parks, Kilwinning
Submit report by the Head of Service (Democratic) on the terms of a
petition received in respect of proposed car parking charges at Oxenward
East and Almswall Road Car Parks, Kilwinning (copy enclosed). 
4 Annual Report on the 2021/22 Audit
Submit report by the Head of Finance on the Annual Audit report for
2021/22 and receive verbal report by the external auditor (copy
enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
5 Accounts Commission’s Report: Scotland’s Financial Response to
Covid-19
Submit report by the Head of Service (Finance) on the findings of the
recently published Accounts Commission report (copy enclosed). 
6 Year End Performance Reporting: Council Plan Year End Progress
Report 2021-22, Annual Performance Report 2021-22 and Local
Government Benchmarking Framework Report 2020-21
Submit report by the Head of Service (Democratic) on progress with the
Council Plan priorities (copy enclosed). 
7 2021-2022 Complaints Report
Submit report by the Head of Service (Democratic) providing information
on the Council’s complaint performance and the volumes and trends of
complaints received in Financial Year 2021/22 (copy enclosed). 
8 Workforce Absence 2019-2022
Submit report by the Head of Service (People & ICT) providing a year
end summery of sickness absence for the period 2019/20 to 2021/22
(copy enclosed). 
9 Internal Audit and Corporate Fraud Action Plans: Quarter 2 Update
Submit report by Head of Service (Finance) on the progress made by
Council Services in implementing the agreed actions from Internal Audit
and Corporate Fraud reports as at 30 September 2022 (copy enclosed). 
10  Corporate Fraud Team Update Report
Submit report by the Head of Service (Finance) on the work of the
Corporate Fraud Team between April and September 2022 (copy
enclosed). 
11  Internal Audit Reports Issued
Submit report by the Head of Service (Finance) on the findings of Internal
Audit work completed between September and October 2022 (copy
enclosed). 
12  National Fraud Initiative (NFI) in Scotland 2022
Submit report by the Head of Service (Finance) providing an overview of
the NFI 2020/21 exercise outcomes (copy enclosed). 
13  Urgent Items
Any other items which the Chair considers to be urgent.
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
14  Exclusion of the Public - Para 1
Resolve in terms of Section 50(A)4 of the Local Government (Scotland)
Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraph
1 of Part 1 of Schedule 7A  of the Act.
Non Disclosure of Information
In terms of Standing Order 21 (Disclosure of Information), the information
contained within the following report is confidential information within the
meaning of Section 50A of the 1973 Act and shall not be disclosed to any
person by any Member or Officer. 
15  Investigation Reports Issued
Submit report by the Head of Service (Finance) on investigation reports
finalised since the last meeting (copy enclosed).  
Webcasting
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at https://north-ayrshire.public-
i.tv/core/portal/home, where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
Generally, the press and public seating areas will not be filmed. However,
by entering the Council Chambers, using the press or public seating area
or (by invitation) participating remotely in this meeting, you are consenting
to being filmed and consenting to the use and storage of those images and
sound recordings and any information pertaining to you contained in them
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. If you
do not wish to participate in a recording, you should leave the
meeting.  This will constitute your revocation of consent.
If you have any queries regarding this and, in particular, if you believe that
use and/or storage of any particular information would cause, or be likely
to cause, substantial damage or distress to any individual, please contact
dataprotectionofficer@north-ayrshire.gov.uk. 
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Audit and Scrutiny Committee Sederunt 
John Bell (Chair)
Donald Reid (Vice Chair)
Eleanor Collier
Cameron Inglis
Tom Marshall
Matthew McLean
Davina McTiernan
Ian Murdoch
John Sweeney 
Chair: 
Apologies: 
Attending: 
4

Page 5

Audit and Scrutiny Committee
27 September 2022 
At a Special Meeting of the Audit and Scrutiny Committee of North Ayrshire Council
at 10.00 a.m. involving participation by remote electronic means and physical
attendance within the Council Chambers, Irvine. 
Present (Physical Participation)
John Bell, Donald Reid, Cameron Inglis, Matthew McLean, Davina McTiernan and
John Sweeney. 
Present (Remote Participation)
Tom Marshall. 
In Attendance (Physical Participation)
C. Cameron, Director, A. Sutherland, Head of Service (Children, Families and
Justice) and M. Close, Senior Officer (HSCP); A. McClelland, Head of Service
(Education);  B. Borthwick and W. Turpie, Senior Managers and J. Smith, Senior
Officer (Place); F Ellis, Senior Manager (Place); M. Boyd, Head of Service (Finance),
L. Miller, Senior Manager (Audit, Fraud Safety and Insurance), R. Lynch, Senior
Manager (Legal Services), A. Little and H. Clancy, Committee Services Officers
(Chief Executive’s Service). 
Also in Attendance (Physical Participation)
L. Kirkland, B. Griffin and D. Jarrett (NHS). 
Chair
Councillor Bell in the Chair. 
Apologies
Eleanor Collier. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors. 
2. Minutes 
The Minutes of (i) the Ordinary Meeting of the Audit and Scrutiny Committee held on 31
May 2022; and (ii) the Special Meeting held on 30 June 2022 were confirmed and the
Minutes signed in accordance with Paragraph 7 (1) of Schedule 7 of the Local
Government (Scotland) Act 1973.  
Agenda Item 2
5

Page 6

3. External Quality Assessment of Internal Audit by West Dunbartonshire
Council 
Submitted report by the Head of Service (Finance) on the findings of the recent
external review of Internal Audit carried out by West Dunbartonshire Council.  The
full External Quality Assessment report, including the action plans, was detailed at
Appendix 1 to the report. 
The Committee agreed to (a) note (i) the findings and action plan from the review of
Internal Audit; and (ii) the positive nature of the assessment; and (b) record its
thanks to West Dunbartonshire Council Internal Audit for carrying out the review. 
4. Accounts Commission’s Report: Local Government in Scotland:
Overview 2022  
Submitted a report by the Head of Service (Finance) on the findings of the Local
Government in Scotland Overview 2022 report by the Accounts Commission
highlighting key messages and recommendations. 
A link to the full report was provided within the Executive Summary which reflected
on the evolving and long-term nature of the impact of the Covid-19 pandemic,
considered the second year of the pandemic, building on the previous review of the
initial response of Councils to the challenges, and assessed the ongoing impact of
Covid-19 and Councils’ progress towards recovery and renewal. 
Members asked questions and were provided with further information in relation to
the following:- 
• workforce planning that used a variety of tools and techniques, such as
career development, succession planning, vacancy management,
redeployment and early release schemes to plan the workforce requirements
for the future; and
• a six-monthly review of each Service’s workforce plan that is undertaken, to
ensure service review and redesign of the workforce is on track. 
The Committee agreed to note (i) the findings of the Accounts Commission report;
(ii) the recommendations contained in the report; and (iii) North Ayrshire Council’s
current approach in relation to each recommendation. 
5. Internal Audit Annual Update Report: North Ayrshire Integration Joint
Board (IJB)  
Submitted report by the Head of Service (Finance) on the IJB’s Annual Report for
2021/22 and the approved internal audit plan for 2022/23.  Substantial assurance
was provided over the arrangements in place, and no areas for improvement were
identified during the review.  
6

Page 7

The report also provided details of the Internal Audit Plan 2022/23 and the allocation
of 25 audit days from the Internal Audit service of North Ayrshire Council and 10
days from NHS Ayrshire and Arran. 
Noted. 
6. Strategic Risk Register 2022/23 
Submitted report by the Head of Service (Finance) on the Council’s agreed Strategic
Risk Register for 2022/23.  The Strategic Risk Register Report 2022/23, with detailed
actions, was provided at Appendix 1 to the report. 
Members asked questions and were provided with further information in relation to
the following:- 
• a range of finance pressures that had been identified, including additional
national insurance contributions, energy cost inflation, contractual
commitments as well as significant construction inflation;
• Blackstart workshops that would take place to work through a range of
scenarios, including the loss of all power and mobile networks; and
• six strategic sites in North Ayrshire identified to house generators which
would be used in the event of a national power outage. 
Noted. 
7. Internal Audit and Corporate Fraud Action Plans: Quarter 1 Update  
Submitted report by the Head of Service (Finance) on the progress made by Council
Services in implementing the agreed actions from Internal Audit and Corporate
Fraud reports as at 30 June 2022.  Appendix 1 to the report provided full details of
seven Internal Audit actions which were not completed within the agreed timescale. 
Members asked questions and were provided with further information in relation to
data protection information awareness training arranged for Garnock Academy on
22 November 2022. 
The Committee agreed to note (i) the current position with the implementation of the
Internal Audit and Corporate Fraud actions; and (ii) challenges which were faced by
those services which have not implemented actions within the previously agreed
timescales. 
8. Internal Audit Plan 2022/23: Mid-Year Update  
Submitted report by Head of Service (Finance) on progress made in delivering the
2022/23 Internal Audit Plan, including information on two additional audits for
inclusion in the 2022/23 Plan and five audits to be deferred to the 2023/24 Internal
Audit Plan.  Appendix 1 to the report detailed the full Internal Audit Plan for
2022/23. 
7

Page 8

Members asked questions and were provided with further information in relation to
the following:- 
• four audits undertaken to review controls in the Transport Hub in relation to
transportation, with a particular focus on the use of taxis; and
• deferral of five audits till 2023/24 to allow audit days to be aligned with
available resources. 
The Committee agreed to (a) note the current position; (b) approve the inclusion of
two additional audit reviews in 2022/23; and (c) approve the deferral of five audits
for consideration as part of the 2023/24 Internal Audit Plan. 
9. Internal Audit Reports Issued  
Submitted report by the Head of Service (Finance) on the findings of Internal Audit
work completed between May and August 2022.  The findings from eight audit
assignments were detailed at Appendix 1 to the report, together with the respective
executive summaries and action plans. 
Members asked questions and were provided with further information in relation to
the following:- 
IJB Compliance with the CIPFA Financial Management Code 
• compliance information that had been circulated to staff via email and training
that would be provided to services if required. 
Accounts Payable Transaction Testing Q4 
• 100% of all invoices that had been checked within one accounting period to
test for duplicate invoices for payments to suppliers; and
• the provision of further information to Members on possible duplicate invoices 
Social Media 
• work undertaken to ensure social media accounts aligned with the Council’s
Communication Strategy; 
• the preparation of an Education Digital Strategy; and
• that the Head of Service (Education) would liaise directly with the Chair in
relation to school Twitter accounts; and 
• the provision of further information by the Head of Service (Education) in
relation to school Twitter accounts 
VAT
• thirty transactions that required further investigation to cross-check the
information behind the data.  
8

Page 9

Off-Payroll Working (IR35) 
• the use of agency staff by HSCP, Building Services and Waste Management;
and 
• no issues had been noted during the review of transactions with five local
suppliers whose contract type and company indicated a Personal Service
Company (PSC). 
The Committee agreed (a) that the Head of Finance provide further information to
Members on possible duplicate invoices; (b) that the Head of Service (Education)
liaise directly with the Chair in relation to school Twitter accounts; and (c) to note the
outcomes from the Internal Audit work completed as set out in the report. 
10. Counter Fraud and Corruption Strategy  
Submitted report by the Head of Service (Finance) on the refresh of the Council’s
Counter Fraud and Corruption Strategy.  The refreshed Strategy was detailed at
Appendix 1 to the report and set out how the Council aimed to address fraud risk. 
The Strategy highlighted the areas of the Council's operations that were viewed as
being at greatest risk of fraud and corruption and outlined a number of danger signs
or 'red flags' to which the Council must be alert in order to maximise the opportunity
to identify potential frauds. 
Noted. 
11. Annual Assurance Statement to the Scottish Housing Regulator 2021/22 
Submitted report by the Executive Director (Place) on the Council’s Annual return on
the Charter 2021/21 submission and endorsement of the Annual Assurance
Statement for submission to the Scottish Housing Regulator.  The Annual Assurance
Statement was detailed at Appendix 1 to the report. 
Members asked questions and were provided with further information in relation to
the following:- 
• an update that would be provided to a future meeting on any links between
access not being provided to properties to allow upgrades to be undertaken
and the slight increase in tenancy offers being refused;
• a range of information that is held on the Asset Management System,
including details of properties with compliant and non-compliant smoke
alarms;
• issues with a specific arrangement to upgrade smoke alarms that would be
examined by the Senior Manager (Housing Strategy & Development) and an
update provided to the local Member;
• upgrades to smoke alarm systems that are now completed when gas safety
checks are undertaken;  
9

Page 10

• improved processes that had been put in place to resolve issues that had
been experienced with a contactor’s recording system for gas safety checks;
and
• the provision of a report to the next meeting on staff absences in the previous
3 years. 
The Committee agreed (a) that the Committee Chair sign the Annual Assurance
Statement detailed at Appendix 1 to the report; (b) to note (i) the Annual Return on
the Charter submission 2021-22; (ii) the supporting evidence provided to
demonstrate compliance with the regulatory framework; and (iii) the Council’s Covid
related non-compliance with its legal gas, electrical and fire safety responsibilities,
including that all outstanding gas safety checks for 2021/22, have now been carried
out; (c) that the Director (Place) provide an update to a future meeting on whether
there had been a link between access not being provided to allow upgrades to be
undertaken and the slight increase in tenancy offers being refused; and (d) that the
Head of Service (People and ICT) provide a report to the next meeting on staff
absences in the previous 3 years. 
12. Exclusion of the Public – Para 1 
The Committee resolved in terms of Section 50(A)4 of the Local Government
(Scotland) Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraph 1 of Part 1
of Schedule 7A of the Act. 
13. Investigation Reports Issued 
Submitted report by the Head of Service (Finance) on investigation reports finalised
since the last meeting. 
The Committee agreed (a) that the Director, Health and Social Care Partnership
provide a report to a future meeting on Blue Badges; and (b) to otherwise note the
report. 
14. Internal Audit and Corporate Fraud Action Plans: Quarter 1 Update
(exempted items)  
Submitted report by the Head of Service (Finance) on the progress made by Council
Services in implementing the agreed actions from Internal Audit and Corporate Fraud
reports as at 30 June 2022. 
Noted. 
The meeting ended at 11.20 a.m. 
10

Page 11

NORTH AYRSHIRE COUNCIL 
15 November 2022 
North Ayrshire Council 
Title:    Petition relating to Proposed Car Parking Charges:
Oxenward East and Almswall Road Car Parks, Kilwinning 
Purpose:  To advise the Committee of the terms of a petition objecting to
the proposed parking charges to be introduced at Oxenward
East and Almswall Road Car Parks and requesting that the
Council maintain free parking in Kilwinning. 
Recommendation:  That the Committee considers the terms of the petition and
agrees, or otherwise, to make a recommendation to Cabinet. 
1. Executive Summary 
1.1   In terms of the Scheme of Administration, the Audit and Scrutiny Committee has a remit: 
“To receive all petitions and deputations submitted to the Council except those relating
to the Council’s planning functions, which shall be considered by the Planning
Committee.  The arrangements for receiving petitions are as set out in Appendix B to
the Standing Orders relating to Meetings and Proceedings of the Council and
Committees”. 
1.2 This report sets out the background to a hard copy petition supported by 1700+
signatories and submitted on 3 November 2022, objecting to the proposed parking
charges to be introduced at Oxenward East and Almswall Road Car Parks and
requesting that the Council maintain free parking in Kilwinning.  An online version of the
petition currently has in excess of 1800 signatories. 
2. Background  
2.1 The petition is detailed below: 
“On behalf of Dino and Sons, Graeme Milliken, and many Kilwinning traders,
shopkeepers and residents, we would like to hand deliver this covering letter along
with an Online and Paper Petition in regards to our ardent objections to the proposed
car parking charges to be introduced at Oxenward East car park and Almswall Road
car park. 
Agenda Item 3
11

Page 12

We would like to highlight paragraph 4.2 taken from North Ayrshire’s Town Centre
Parking Strategy dated 2014 – 2020 which is currently available on North Ayrshire
Council's website for public viewing. With this strategy actions for Delivery 4 states the
following, 
https://www.north-
ayrshire.gov.uk/Documents/PropertyServices/InfrastructureDesign/Roads/town-
centre-parking-strategy.pdf 
4.2 Maintain Free Parking 
North Ayrshire is one of a small number of Councils that provides free parking. This is
primarily to support local businesses and maintain visitors within areas identified
within high levels of deprivation and where there are a number of large shopping
centres that offer free parking. Consultation has also identified that free parking is a
key factor in people visiting town centres.   
North Ayrshire Council clearly states, ‘free parking is a key factor in people visiting
town centres.’ Therefore, the introduction of parking charges goes against the findings
within your own strategy, which additionally highlights that Kilwinning and its
surrounding areas of Irvine, the Three Towns and Garnock Valley were identified as
one of the significant areas of deprivation within the Scottish Index of Multiple
Deprivation.   
With the ongoing energy, fuel, and cost of living crisis, business owners feel that the
parking charges are a travesty, and the impact will have a negative effect on keeping
business open, consequently, resulting in more independent shop closures within
Kilwinning main street. Shopkeepers would rather have a guaranteed current footfall,
rather than gambling on an unknown and unguaranteed future footfall.  
Considering the feedback from many customers who were asked if they will pay to
park, the feedback has been extremely negative, customers have stated that they will
shop elsewhere that provides free parking therefore, we must insist that this decision
be reversed to ensure that local businesses remain the backbone of Kilwinning’s
economy, who will continue to support our local community. 
We the shopkeepers fear that the proposed parking charges will significantly reduce
footfall. Therefore, doing so will have a devastating impact on all small independent
businesses who are already striving to compete against the giant supermarkets and
large shopping centres within the surrounding area where all parking is free. 
A substantial number of our customers and visitors, including tourists, many of whom
are elderly, need Kilwinning main street as a community hub. Enabling them to visit
shops, socially integrating with friends and family, helping to have a positive effect on
mental health and wellbeing. Most importantly no one should have to pay to visit
doctors, dentists and nurses within their local surgeries and other such essential
healthcare amenities which many depend on for their wellbeing. Our on-street
residents have a right to remain parking charge free, like every other area in
Kilwinning, relatives and friends should never have to pay to visit their family and
friends, ever! 
Considering the points above, surely now is not the time to introduce parking fees.
May we stress nothing has changed positively since the last survey dated 2014 to
2020, current situations are now, as we are sure you will agree, are worse than when
the above information was first printed. 
PLEASE KEEP PARKING FREE IN KILWINNING.”
12

Page 13

2.2    The Head of Service (Commercial) has provided a briefing note on the background to
this matter, which is detailed at Appendix 1 to the report. 
2.3 In terms of the procedure for petitions and deputations set out in Standing Orders,
representatives of the petitioners have been invited to attend the meeting to address
the Committee.  Spokespersons should be restricted to addressing the specific points
raised in their petition. 
2.4 The spokespersons have, collectively, 10 minutes to address the Committee.  This may
be extended at the discretion of the Chair. 
2.5 Once the Committee has heard from the spokespersons for the petitioners, the Chair
will invite Members of the Committee to ask questions of the spokespersons. 
2.6 While it is for the Chair to decide the stage at which officers should speak to their
briefing, previous Committee practice has been for the Cabinet Member or Officer to
speak to this after the Committee has heard from the petitioners.  The Cabinet
Member or Officer will then respond to any questions that Members of the Committee
may have. 
3. Proposals 
3.1 It is proposed that the Committee considers the terms of the petition and agrees, or
otherwise, to make a recommendation to Cabinet.
4. Implications/Socio-economic Duty 
Financial 
4.1 There is £440k income per year forecast from this initiative across North Ayrshire. If
the initiative does not go ahead it would need to be replaced with an alternative
proposal(s) to plug the budget gap ie. other income opportunities to raise £440k or
£440k of new savings. 
Human Resources 
4.2 None arising from this report. 
Legal 
4.3  None arising from this report. 
Equality/Socio-economic 
4.4 None arising from this report. 
Climate Change and Carbon 
4.5 None arising from this report. 
13

Page 14

Key Priorities 
4.6 None arising from this report. 
Community Wealth Building 
4.7 None arising from this report. 
5. Consultation 
5.1 The Head of Service (Commercial) has been consulted and made aware of the terms
of the petition and has provided a briefing note which is attached as Appendix 1 to the
report. 
Aileen Craig
Head of Service (Democratic) 
For further information please contact Diane McCaw, Committee Services Officer, on
01294 324132 
Background Papers 
N/A
14

Page 15

Briefing Note: DPE and Car Parking Charges
Background
On 11 June 2019 Cabinet recommended that DPE be introduced across North Ayrshire and
that car park charges should apply in Irvine, Kilwinning, Saltcoats, Largs and Brodick. 
Charges were set at:
However, following a call in to Audit and Scrutiny the matter was referred back to Cabinet to
reconsider the previous decision in relation to the introduction of car parking charges in
Brodick and in the inclusion of Arran in DPE.  
On 25 September 2019 full Council backed DPE for the entire Council area but not to
implement car parking charges on Arran.
In 2020, a global pandemic emerged, and the introduction of the proposals was put on hold
due to this. 
On 2 March 2022, at its budget setting meeting full Council approved an increase in charges,
as follows. 
Proposed Tariff
Time (Mins) Short stay
60 £1.50
120 £2.00
240 £3.50
All Day Not permitted
A motion was proposed at the Full Council Meeting on 21 September 2022 that in view of the
pandemic and the cost of living crisis, the introduction of these measures should be paused
and a further review of the impact of these measures on residents and local businesses should
be undertaken. 
However, following a division and a roll call vote, Council agreed that, ‘in light of the deepening
financial crisis, a proposal be brought to Cabinet to reconsider the level of charges proposed
in the 2022/23 budget.’
Key Outcomes of DPE
Traffic Management
A key desired outcome of introducing DPE and parking charges is an improved regulation of
traffic in our town centres, by directing long stay patrons to free parking slightly further out
whilst providing chargeable and short stay parking close to retail and other town centre
services.
Appendix 1
15

Page 16

Sustainable Transport/Climate Change
The introduction of these measures also aligns with National Transport Policy by encouraging
more active and sustainable modes of transport. The Scottish Government has a target to
reduce car usage by 20% by 2030 and car parking charges will help contribute to this target
by shifting people towards using alternative and sustainable modes of transport.
The introduction of DPE and car parking charges aims to support sustainable and active
travel and reduce the impact of transport on our communities. This also aims to reduce the
volume of traffic travelling through our towns and to facilitate public transport to support a
shift towards more sustainable travel behaviour. This aligns with the Council’s agreed
Environmental Sustainability and Climate Change Strategy and furthermore, it aligns with the
Council’s commitment to reduce carbon emissions through our declaration of a Climate
Emergency and will contribute to the ambition to achieve net zero by 2030.
The Town Centre Parking Strategy 2014-20, referred to by the petitioner did state that
parking would be free, at the time of publishing the report in 2014, however the new Local
Transport Strategy will cover this. Since 2014 much change has taken place particularly
around Climate Change and the declaration of a Climate Emergency.
DPE powers and charges
Process to enact DPE
To obtain DPE powers an application has been submitted to Scottish Government to transfer
the enforcement powers from Police Scotland to North Ayrshire Council and the statutory
process is underway with implementation now expected on 1 July 2023.
DPE powers are currently held by 21 Local Authorities including all our neighbouring local
authorities.
Charges
It is important to note that Decriminalised Parking is not sustainable without the income
generated from parking charges.
Transport Scotland recommends that DPE should be financially sustainable as far as possible.
It states, ‘if a strong financial case cannot be made the Local Authority needs to explain how
it would meet any shortfall before Transport Scotland could make a decision on the
application.’
It is recommended that when considering taking on DPE powers a robust Business Case
outlining how DPE will be funded is required. North Ayrshire Council commissioned robust
Feasibility Studies in 2019 which helped inform the Car Parking charges model. 
A Financial Assessment was submitted as part of the application to the Scottish Ministers.
Parking for disabled badge holders/poor parking behaviour
Disabled badge holders will be able to park free of charge in the car parks where charges
apply. 
A significant problem is that disabled parking bays are being abused with able bodied drivers
parking in them preventing disabled badge holders from parking. 
There are also issues with inconsiderate drivers parking on double yellow lines, bus stops,
‘keep clear’ areas near schools etc and DPE powers will help us act on this.
16

Page 17

Pavement Parking Ban
The Scottish Government is introducing a ban on pavement parking in late 2023 and without
car park wardens we will be unable to enforce this legislation.
Car parks where charges will apply
• Irvine – Kirkgate, West Road and East Road
• Kilwinning – Almswell Road and Oxenward
• Saltcoats – Vernon Street, Bradshaw Street, Windmill Street and Kirkgate.
• Largs – Gateside Street.
There is already charging in place at Bellmans Close in Largs.
North Ayrshire Council currently has 55 car parks and 44 will remain free of charge to use, the
exceptions being the 10 named above plus Bellman’s Close, Largs.
There is free parking available nearby the locations where charges will apply.
In Kilwinning, the Woodwynd Car Park will remain free of charge and there is also on street
free parking.
Implementation Plan
Ongoing engagement
Engagement sessions have been arranged with local elected members and will take place
between 5 and 8 December 2022.
These engagement sessions offer the opportunity to discuss concerns and issues around the
proposals.
Car Park usage
Officers have been monitoring parking behaviour in the car parks where charges are to be
introduced. In Kilwinning it is proposed to introduce charges in Almswell Road car park and
Oxenward car park leaving Woodwynd car park and on street parking free of charge.
From our monitoring exercise we have found there are very few spaces available within both
Almswell Road and Oxenward car parks during the day, with these car parks being full of
mainly workers and students by 9:00am each day with very little vehicle movement until the
evening.
There has been a long-standing issue in these car parks with visitors/shoppers being
prevented from getting a space due to the car park being used as a long stay car park. The
introduction of car parking charges should help with vehicle turnover and allow
visitors/shoppers to access the car parks. 
In addition, the disabled bays are also being abused meaning disabled visitors and doctor’s
patients are unable to park. It should be noted that disabled bays will remain free of charge
for blue badge holders, however DPE will mean that the Council can act against the
inappropriate use of disabled bays.
These local issues will be discussed with ward members. 
17

Page 18

Residents parking permits
The Service are considering the introduction of resident parking bays to address resident’s
concerns.
Doctor’s surgeries in Kilwinning
A meeting between Council Officers and representatives from the Doctor’s surgeries took
place on 27 September 2022 and it was agreed to consider the following:   
• Provision of a drop off/pick up point for patients.
• Review the number of GP spaces provided.
• Review the number of disabled bays provided.
A patient’s representative at the meeting acknowledged it was difficult for patients to get a
parking space due to cars being parked in this location all day.
Level of Charges
In accordance with the Council’s decision on 21 September 2022, a report will be submitted
to the Cabinet meeting on 24 January 2023 on charges. 
Financial Implications
Car Parking charges were agreed as part of the Council’s budget setting process and an
income of £440,000 per annum is included in the budget. 
Any proposal to review or abolish car parking charges will require details on how the
£440,000 funding gap will be met through increased charges/income or new savings. 
There is also a cost in providing and maintaining car parks and in the current financial
climate this is difficult to sustain without some sort of charge. 
18

Page 19

NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    Annual Report on the 2021/22 Audit 
Purpose:  To invite Committee to note the annual audit report for 2021/22
and to consider a verbal report by the external auditor. 
Recommendation:  That Committee: 
(a) Notes the findings of the 2021/22 audit of the financial
statements as contained in the External Auditor’s annual
report at Appendix 2; 
(b) Considers the verbal report by the External Auditor; 
(c) Notes the agreed Action Plan as outlined on Page 30 of the
final report; and 
(d) Approves the audited Annual Accounts for signature. 
1. Executive Summary 
1.1 As part of the external audit for 2021/22, Deloitte LLP have produced two reports. 
The initial report, covering Audit Dimensions and Best Value, was considered by the
Audit and Scrutiny Committee on 31 May 2022.  The second report is the Final Report
and includes an opinion on the Council’s financial statements. 
1.2  The unaudited accounts for the year to 31 March 2021 were approved by Council on
22 June 2022 and submitted to the Council’s external auditor, Deloitte LLP, for audit.
The Audit Director for Deloitte LLP has now issued his proposed Independent
Auditor’s Report on the financial statements which is free from qualification and
confirms that the accounts give a true and fair view of the state of affairs of the
Council, its group and the Council’s charitable trusts as at 31 March 2022. 
1.3  As detailed in paragraphs 2.5 to 2.6, a number of adjustments have been identified
during the audit process.  However, these adjustments do not impact on the reported
balance of Unearmarked Reserves which remain unchanged at £11.315m. 
1.4  Deloitte LLP’s final report includes an action plan in relation to one recommendation
for improvement identified during the course of the audit.  This relates to the useful
economic lives of assets classed as Infrastructure Assets.  Full details of this and the
proposed management action are included at Page 30 of the Auditor’s Report. 
Agenda Item 4
19

Page 20

2. Background 
2.1 The 2021/22 audit of the Council’s accounts was conducted by Deloitte LLP, the final
year of a six year cycle as the Council’s appointed external auditors. 
2.2  As well as auditing the financial statements, Deloitte LLP considered the Council’s
arrangements in relation to best value and the four audit dimensions of financial
sustainability, financial management, value for money and governance and
transparency.  An initial report covering the audit dimensions and best value was
considered by the Audit and Scrutiny Committee on 31 May 2022. 
2.3 The Council’s accounts for the year to 31 March 2022 were submitted to Deloitte LLP
for audit by the deadline of 30 June 2022.  Following an extension to the statutory
dates under the Local Authority (Capital Finance and Accounting) (Scotland)
(Coronavirus) Amendment Regulations 2022, the external auditor is required to
complete the audit by 30 November 2022 and to report on certain matters arising to
those charged with governance in sufficient time to enable appropriate action to be
taken before the financial statements are approved and certified. 
2.4  Appendix 1 includes letters of representation to be signed by the Head of Finance as
the responsible officer for North Ayrshire Council. Deloitte LLP’s annual report to
members, which summarises the findings of their audit, is attached at Appendix 2. 
2.5  Accounting adjustments totalling £0.679m have been identified during the audit
process.  These adjustments were related to the treatment of insurance excess
transactions and the valuation provided for “experience losses” in relation to our share
of the liabilities of Strathclyde Pension Fund. 
2.6 In relation to the insurance excess transactions, adjustments have been made to
recognise the correct treatment of these transactions and upgrade internal procedures
to prevent any further recurrence.  This resulted in a net reduction of £0.212m in the
level the Council’s Insurance Fund. 
2.7 In relation to the valuation of pension liabilities, an adjustment to the actuarial
valuation has been made.  This resulted in a net increase of £0.467m in the value of
the Council’s share of Strathclyde Pension Fund’s net long term liability. 
2.8 Further adjustments were identified in relation to transfers between the Council’s
unusable reserves in relation to the impairment of assets and the restatement of the
previous year’s service income and expenditure analysis to reflect changes in North
Ayrshire Council’s internal reporting structure.  An upgrade to the Council’s financial
ledger system linked to revised internal procedures will be undertaken to prevent any
further recurrence.  The overall level of unusable reserves was not affected and the
reported balance of Unearmarked Reserves has remained unchanged at £11.315m. 
2.9  Pages 9 to 18 of the attached Audit Report (Appendix 2) outline the significant risks
and other matters identified in the audit plan for 2021/22 together with the auditor’s
views of the key judgements and controls in place.  These risks relate to: 
• Recognition of Covid-19 Related Income; and
• Management Override of Controls. 
20

Page 21

The report confirms that no material issues were identified in relation to these matters. 
2.10  The report notes that final testing of the charitable trust accounts has been completed
and that no issues have been identified.  It is anticipated that an unmodified opinion
will be issued in relation to this. 
2.11 The report also notes one issue in relation to an internal control arising from the
recognition of the impairment of some assets within our Unusable Reserves, as noted
at 2.8 above.  Actions to upgrade the financial ledger system are being implemented. 
2.12  In addition, in relation to the financial statements, the Audit Report has noted that: 
• The Council’s Management Commentary has been prepared in accordance with
the statutory guidance; 
• The auditable parts of Remuneration Report have been properly prepared in
accordance with the regulations; and 
• The Annual Governance Statement is consistent with the financial statements
and has been prepared in accordance with the Delivering Good Governance in
Local Government Framework. 
2.13 An Action Plan which sets out the main areas identified for action from the annual
audit is detailed on page 30 of the final report.  The only area identified is in relation to
the accounting for Infrastructure Assets which has been subject to an ongoing national
review.  In order to support this, the nature of the assets held under Infrastructure
Assets will be reviewed and engineering advice will be sought to ensure that the
assigned useful economic lives are consistent with the nature of the assets in
question. 
2.14 It should be noted that the auditor has received a statutory objection to the accounts
relating to the Common Good and Trust Funds and has met with the objector to
consider the issues and evidence provided.  The auditor has concluded that the issues
raised are not material to their opinion and no further adjustments to the financial
statements are anticipated. 
2.15 A link to the final audited accounts will be issued to all members for their information. 
2.16 Representatives from Deloitte LLP will be in attendance at Committee and will present
a verbal report highlighting the main findings of the 2021/22 audit. 
3. Proposals 
3.1 It is proposed that Committee: 
(a) Notes the findings of the 2021/22 audit of the financial statements as contained
in the External Auditor’s annual report at Appendix 2; 
(b) Considers the verbal report by the External Auditor; 
(c) Notes the agreed Action Plan as outlined on Page 25 of the final report; and 
(d) Approves the audited Annual Accounts for signature. 
21

Page 22

4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. 
Human Resources 
4.2 None. 
Legal 
4.3 Under the Local Authority (Capital Finance and Accounting) (Scotland) (Coronavirus)
Amendment Regulations 2022, the external auditor is required to complete the audit by
30 November 2022. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 This report and the annual accounts directly support the Council Plan 2019 to 2024 by
maximising resources and providing value for money to support financially sustainable
delivery models. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The Chief Executive, Executive Directors and other appropriate officers have been
consulted as part of the audit process. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551 or DavidForbes@north-ayrshire.gov.uk. 
Background Papers
North Ayrshire Council Unaudited Annual Accounts 2021/22 - Council 22 June 2022; 
North Ayrshire Charitable Trusts: Unaudited Trustees’ Annual Report 2021/22 – Council 22
June 2022; 
External Audit Report on Audit Dimensions and Best Value for the year ended 31 March
2022 – Audit and Scrutiny Committee 31 May 2022.
22

Page 23

23

Page 24

HEAD OF FINANCE:  Mark Boyd
Cunninghame House, Irvine KA12 8EE
Tel: 01294 310000  Fax: 01294 324544
www.north-ayrshire.gov.uk   
Your Ref:  Our Ref:  PK/NAC/2022 
If telephoning please ask for:  Mark Boyd  01294 324560 
15 November 2022 
Dear Pat Kenny, 
NORTH AYRSHIRE COUNCIL AUDIT – YEAR ENDED 31 MARCH 2022 
This representation letter is provided in connection with your audit of the financial
statements of North Ayrshire Council (‘the entity’) for the year ended 31 March 2022 for
the purpose of expressing an opinion as to whether the financial statements give a true
and fair view of the financial position of the entity as of 31 March 2022 and of the results of
its operations, other comprehensive net expenditure and its cash flows for the year then
ended in accordance with the .applicable accounting framework as interpreted by the
Code of Practice on Local Authority Accounting in the United Kingdom. 
In addition to the above, this representation letter is provided in connection with your audit
of the other information in the Annual Accounts, for the purposes set out in the Code of
Audit Practice 2016. 
We are aware that it is an offence to mislead an auditor of a public body. 
On behalf of the entity, I confirm as Responsible Financial Officer, to the best of my
knowledge and belief, the following representations. 
Financial statements
1. We understand and have fulfilled our responsibilities for the preparation of the
financial statements in accordance with the applicable financial reporting framework,
as set out in the Code of Practice on Local Authority Accounting in the United
Kingdom, which give a true and fair view, as set out in the terms of the audit
engagement letter. 
2. Significant assumptions used by us in making accounting estimates, including those
measured at fair value and assessing the impact of COVID-19 on the entity are
reasonable. We have made sufficient and appropriate disclosure of the general
increased estimation uncertainty arising from the impact of COVID-19. 
3. Related party relationships and transactions have been appropriately accounted for
and disclosed in accordance with the requirements of IAS24 “Related party
disclosures”. 
4. All events subsequent to the date of the financial statements and for which the
applicable financial reporting framework requires adjustment of or disclosure have
been adjusted or disclosed. 
Appendix 1
24

Page 25

5. There are no uncorrected misstatements and disclosure deficiencies. 
6. We confirm that the financial statements have been prepared on the going concern
basis and disclose in accordance with IAS 1 all matters of which we are aware that
are relevant to the entity’s ability to continue as a going concern, including principal
conditions or events and our plans. We do not intend to cease operations as we
consider we have realistic alternatives to doing so. We are not aware of any material
uncertainties related to events or conditions that may cast significant doubt upon the
entity’s ability to continue as a going concern. We confirm the completeness of the
information provided regarding events and conditions relating to going concern at the
date of approval of the financial statements, including our plans for future actions. 
7. The entity has satisfactory title to all assets and there are no liens or encumbrances
on the entity’s assets and assets pledged as collateral. 
8. We have recorded or disclosed, as appropriate, all liabilities, both actual and
contingent. 
9. We have reconsidered the remaining useful lives of the property, plant and
equipment and confirm that the present rates of depreciation are appropriate to
amortise the cost less residual value over the remaining useful lives. 
10. We are not aware of events or changes in circumstances occurring during the period
which indicate that the carrying amount of property, plant and equipment may not be
recoverable. 
11. With respect to accounting estimates, we confirm:
•   the measurement processes, including related assumptions and models used to
determine accounting estimates in the context of the applicable financial reporting
framework are appropriate and have been applied consistently; 
•   the assumptions appropriately reflect our intent and ability to carry out specific
courses of action on behalf of the entity where relevant to the accounting
estimates and disclosures; 
•   the disclosures related to accounting estimates under the entity’s applicable
financial reporting framework are complete and appropriate;  and 
•   there have been no subsequent events that require adjustment to the accounting
estimates and disclosures included in the financial statements. 
12. We confirm that we consider the depreciated historic cost is an appropriate proxy for
the fair value of non-property assets, and are not aware of any circumstances that
would indicate that these assets require revaluation. 
13. We confirm that the provisions included within the financial statements are our best
estimate of the liability due by the entity. 
14. We confirm that:
•   all retirement benefits and schemes, including UK, foreign, funded or unfunded,
approved or unapproved, contractual or implicit have been identified and properly
accounted for; 
•   all settlements and curtailments have been identified and properly accounted for;
25

Page 26

•   all events which relate to the determination of pension liabilities have been brought
to the actuary’s attention; 
•   the actuarial assumptions underlying the valuation of the scheme liabilities
(including the discount rate used) accord with our best estimates of the future
events that will affect the cost of retirement benefits and are consistent with our
knowledge of the entity; 
•   the actuary’s calculations have been based on complete and up to date member
data as far as appropriate regarding the adopted methodology; and 
•   the amounts included in the financial statements derived from the work of the
actuary are appropriate. 
15. We have made a reclassification to the prior period financial statements to ensure
transparent comparison for the users of the financial statements. This is in relation to
the income and expenditure charged to “Chief Executive” and “Other Corporate
Items”. 
Information provided 
16. We have provided you with all relevant information and access as agreed in the
terms of the audit engagement letter with Audit Scotland. 
17. All transactions have been recorded and are reflected in the financial statements and
the underlying accounting records. 
18. We acknowledge our responsibilities for the design, implementation and maintenance
of internal control to prevent and detect fraud and error. We are not aware of any
deficiencies in internal control of which you should be aware. 
19. We have disclosed to you the results of our assessment of the risk that the financial
statements may be materially misstated as a result of fraud. 
20. We have disclosed to you all information in relation to fraud or suspected fraud that
we are aware of and that affects the entity or group and involves:
(i) management;
(ii) employees who have significant roles in internal control; or
(iii) others where the fraud could have a material effect on the financial statements. 
21. We have disclosed to you all information in relation to allegations of fraud, or
suspected fraud, affecting the entity’s financial statements communicated by
employees, former employees, analysts, regulators or others. 
22. We are not aware of any instances of non-compliance, or suspected non-compliance,
with laws, regulations, and contractual agreements whose effects should be
considered when preparing financial statements. 
23. We have disclosed to you the identity of the entity’s related parties and all the related
party relationships and transactions of which we are aware. 
26

Page 27

24. All known actual or possible litigation and claims whose effects should be considered
when preparing the financial statements have been disclosed to you and accounted
for and disclosed in accordance with the applicable financial reporting framework. No
other claims in connection with litigation have been or are expected to be received. 
25. We have no plans or intentions that may materially affect the carrying value or
classification of assets and liabilities reflected in the financial statements. 
26. We confirm that:
(i) we consider that the entity has appropriate processes to prevent and identify
any cyber breaches other than those that are clearly inconsequential; and
(ii) we have disclosed to you all cyber breaches of which we are aware that have
resulted in more than inconsequential unauthorised access of data,
applications, services, networks and/or devices. 
27. We have performed an assessment of the impact on the financial statements of
events in Russia and Ukraine including consideration of the impact of sanctions and
have disclosed the results of that assessment to you. 
28. All minutes of Council and Committee meetings during and since the financial year
have been made available to you. 
29. We have drawn to your attention all correspondence and notes of meetings with
regulators. 
30. We confirm that all of the disclosures relating to sections of the Annual Accounts
which are considered ‘other information’ as set out in the Code of Audit Practice 2016
have been prepared in accordance with relevant legislation and guidance. 
We confirm that the above representations are made on the basis of adequate enquiries of
management and staff (and where appropriate, inspection of evidence) sufficient to satisfy
ourselves that we can properly make each of the above representations to you. 
Yours faithfully 
Head of Finance
Signed as Responsible Financial Officer, for and on behalf of North Ayrshire Council
27

Page 28

HEAD OF FINANCE:  Mark Boyd
Cunninghame House, Irvine KA12 8EE
Tel: 01294 310000  Fax: 01294 324544
www.north-ayrshire.gov.uk   
Your Ref:  Our Ref:  PK/NACT/2022
If telephoning please ask for:  Mark Boyd  01294 324560 
15 November 2022 
Deloitte LLP 
Dear Pat Kenny, 
NORTH AYRSHIRE COUNCIL AUDIT – YEAR ENDED 31 MARCH 2022 
This representation letter is provided in connection with your audit of the financial
statements of North Ayrshire Council Trust Funds (‘the entities’) for the year ended 31
March 2022 for the purpose of expressing an opinion as to whether the financial
statements properly present the receipts and payments of the charities as of 31 March
2022 and their statement of balances at that date in accordance with the applicable
accounting framework and the Charities and Trustee Investment (Scotland) Act 2005. 
We are aware that it is an offence to mislead an auditor of a public body. 
On behalf of the entities, I confirm as a Trustee, to the best of my knowledge and belief,
the following representations. 
Financial statements
1. We understand and have fulfilled our responsibilities for the preparation of the
financial statements in accordance with the applicable financial reporting framework
and the Charities and Trustee Investment (Scotland) Act 2005 which present fairly,
as set out in the terms of the audit engagement letter. 
2. Significant assumptions used by us in making accounting estimates, including those
measured at fair value and assessing the impact of Covid-19 on the entities are
reasonable. We have made sufficient and appropriate disclosure of the general
increased estimation uncertainty arising from the impact of Covid-19. 
3. Related party relationships and transactions have been appropriately accounted for
and disclosed in accordance with the requirements of IAS24 “Related party
disclosures”. 
4. All events subsequent to the date of the financial statements and for which the
applicable financial reporting framework requires adjustment of or disclosure have
been adjusted or disclosed. 
5. There are no uncorrected misstatements and disclosure deficiencies. 
28

Page 29

6. We are not aware of events or changes in circumstances occurring during the period
which indicate that the carrying amount of property, plant and equipment may not be
recoverable. 
Information provided
7. We have provided you with all relevant information and access as agreed in the
terms of the audit engagement letter with Audit Scotland. 
8. All transactions have been recorded and are reflected in the financial statements and
the underlying accounting records. 
9. We acknowledge our responsibilities for the design, implementation and maintenance
of internal control to prevent and detect fraud and error. We are not aware of any
deficiencies in internal control of which you should be aware. 
10. We have disclosed to you the results of our assessment of the risk that the financial
statements may be materially misstated as a result of fraud. 
11. We have disclosed to you all information in relation to fraud or suspected fraud that
we are aware of and that affects the entities or group and involves:
(i) management;
(ii) employees who have significant roles in internal control; or 
(iii) others where the fraud could have a material effect on the financial statements. 
12. We have disclosed to you all information in relation to allegations of fraud, or
suspected fraud, affecting the entities’ financial statements communicated by
employees, former employees, analysts, regulators or others. 
13. We are not aware of any instances of non-compliance, or suspected non-compliance,
with laws, regulations, and contractual agreements whose effects should be
considered when preparing financial statements. 
14. We have disclosed to you the identities of the entities’ related parties and all the
related party relationships and transactions of which we are aware. 
15. All known actual or possible litigation and claims whose effects should be considered
when preparing the financial statements have been disclosed to you and accounted
for and disclosed in accordance with the applicable financial reporting framework. No
other claims in connection with litigation have been or are expected to be received. 
16. We have no plans or intentions that may materially affect the carrying value or
classification of assets and liabilities reflected in the financial statements. 
17. We confirm that:
(i) we consider that the entities has appropriate processes to prevent and identify
any cyber breaches other than those that are clearly inconsequential; and
(ii) we have disclosed to you all cyber breaches of which we are aware that have
resulted in more than inconsequential unauthorised access of data,
applications, services, networks and/or devices. 
18. All minutes of Council and Committee meetings during and since the financial year
have been made available to you. 
19. We have drawn to your attention all correspondence and notes of meetings with
regulators.
29

Page 30

We confirm that the above representations are made on the basis of adequate enquiries of
management and staff (and where appropriate, inspection of evidence) sufficient to satisfy
ourselves that we can properly make each of the above representations to you. 
Yours faithfully 
Head of Finance
Signed for and on behalf of the Trustees 
30

Page 31

Issued on 27 October 2022 for the meeting on 15 November 2022
North Ayrshire Council
Report to the Audit and Scrutiny Committee, Members of the Council and the Controller of Audit  on
the 2021/22 audit
Deloitte Confidential - Approved External Use only31

Page 32

2
Contents
01 Final Report
Introduction 3
Financial Statements Audit
Quality Indicators 7
Our Audit Explained 8
Significant Risks 9
Other Areas of Audit Focus 14
Other Significant Findings 19
Our Audit Report 21
Your Annual Report 22
Audit Dimensions and Best Value
Overview and Conclusions 24
Purpose of our Report and Responsibility
Statement 25
Audit Adjustments 27
Action Plan 30
Our Other Responsibilities Explained 31
Independence and Fees 32
02 Appendices
Deloitte Confidential - Approved External Use only32

Page 33

33
Introduction
The key messages in this report
I have pleasure in presenting our final report to the Audit and Scrutiny Committee (“the Committee”) of the North Ayrshire
Council (“the Council”) for the year ending 31 March 2022 audit. The scope of our audit was set out within our planning report
presentedto theCommittee inMarch2022. Thisreportincludesthecharitabletrusts(“theTrusts”)
Thisreportsummarises ourfindingsandconclusions in relationto:
• The auditof the Annual Accounts;and
• Consideration of the four audit dimensions that frame the wider scope of public sector audit requirements as illustrated in
thefollowingdiagram.Thisincludesourconsiderationof theCouncil’s dutyto secure bestvalue.
Audit quality is our
number one priority.
We plan our audit to
focus on audit quality
and have set the
following audit quality
objectives for this
audit:
• A robust challenge
of the key
judgements taken
in the preparation
of the Annual
Accounts.
• A strong
understanding of
your internal
control
environment.
• A well planned and
delivered audit
that raises findings
early with those
charged with
governance.
Deloitte Confidential - Approved External Use only33

Page 34

4
Introduction (continued)
The key messages in this report (continued)
Conclusions fromour testing
Based on our audit work completed to date we expect to issue an
unmodifiedauditopinion.
The Management Commentary and Annual Governance Statement comply
with the statutory guidance and proper practice and are consistent with
theannualaccounts andourknowledge of the Council.
The auditable parts of the Remuneration Report have been prepared in
accordance with the relevantregulations.
A summary of our work on the significant risks is provided in the
dashboardon page 9.
We have identified four financial statement adjustments above our
reportingthreshold of £250k. These relate to a reclassification of prior year
income and expenditure, a misstatement within the revaluation reserve
andpensions.These are summarised on pages27 – 29.
Statusof thefinancial statementsaudit
Outstandingmattersto conclude the auditinclude:
• Finalisationof theauditof charitabletrusts;
• Finalisationof internalqualitycontrol procedures;
• Receipt of signed managementrepresentationletter;and
• Our reviewof eventssince 31 March2022.
Conclusions on audit dimensions and best value
As set out on page 3, our audit work covered the four audit dimensions.
Our separate detailed report presented to the Committee in May 2022 set
out our findings and conclusions on each dimension. In accordance with
the Code of Audit Practice, we have included our overall conclusions within
thisreporton page 24. Key highlightsinclude:
Financial Management - The Council continues to have robust budget
setting and monitoring arrangements in place. This is supported by an
experienced finance team and a robust internal audit function, as well as
appropriate arrangements for the prevention and detection of fraud and
error.
Financial sustainability - The Council has set a balanced budget for
2022/23 and holds unearmarked reserves at a level consistent with its
Reserves Strategy, therefore is financially sustainable in the short term.
However, it continues to be faced with significant financial challenges over
themedium andlonger-term.
It is positive to see the work progressing with the sustainable Change
Programme, incorporating a comprehensive benefits tracker and a clear
commitment to invest in recovery and renewal. However, progress
continues to be impacted by the pandemic. It is critical that this work is
progressed at pace and scale to ensure that the planned benefits are
realised.
I would like to draw your attention to the key messages of this paper:
Deloitte Confidential - Approved External Use only34

Page 35

5
Introduction (continued)
The key messages in this report (continued)
Conclusions on audit dimensions and best value (continued)
Governance and transparency – The Council continues to have strong
leadership, which has been enhanced in the year with the creation of
additional capacity at Head of Service level to focus on priorities. The
governance arrangements also continue to be robust, with a
comprehensive review of the infrastructure to enable hybrid meetings and
an effective Audit and Scrutiny Committee. The Council continues to be
open and transparent and demonstrates a culture of continuous
improvement,with the planneddevelopmentof a ParticipationStrategy.
Value for money –– The Council continues to have a clear and robust
performance management framework in place which has been enhanced
in the year with the Performance Management Strategy and new
Performance Dashboard. It has continued to report its performance
against the priorities within the Council Plan and also against the Local
Government Benchmarking Framework (LGBF) with clear actions in place
to addressindicatorsthatare adriftof target.
Best value - The Council has robust arrangements in place to secure best
value and has a clear understanding of areas which require further
development.
Next steps
An agreed Action Plan was included in the separate wider scope report
that was presented to Audit and Scrutiny Committee in May 2022. We also
have an Action Plan on page 30 of thisreport.
Added value
Our aim is to add value to the Council by providing insight into, and
offering foresight on, financial sustainability, risk and performance by
identifying areas for improvement and recommending and encouraging
good practice. In so doing, we aim to help the Council promote improved
standards of governance, better management and decision making, and
more effectiveuse of resources.
In addition, we included our “sector developments” in the separate wider
scope report that was presented to Audit and Scrutiny Committee in May
2022 which covers our research, informed perspective and best practice
from our work across the wider public sector that are specifically relevant
to the Council.
Managing transition to 2022/23 audits
2021/22 is the final year of the current audit appointments. We will
minimise disruption to all parties, and maximise the transfer of knowledge
of the Council, by working in partnership with Audit Scotland and the
incomingauditors.
We would like to put on record our thanks to the Board, management and
staff for the good working relationship over the period of our
appointment.
Pat Kenny
Associate Partner
Deloitte Confidential - Approved External Use only35

Page 36

6
Annual Accounts Audit
36

Page 37

77
Area Grading Reason
FY22 FY21 FY20
Timing of key accounting
judgements
Management demonstrated a clear understanding of key accounting judgements and
estimates made in the preparation of the Annual Accounts and provided sufficient
appropriateevidenceof good qualityto supportthese.
Adherence to deliverables
timetable
Management provided all evidence in a timely manner, in advance of agreed timelines.
Any follow-up requests during the audit were quickly actioned.
Access to finance team and
other key personnel
Deloitte and North Ayrshire Council have worked together to facilitate remote
communication during the audit which has been successful. There have been no issues
with access to thefinanceteam or otherkey personnel.
Quality and accuracy of
management accounting
papers
Documentation provided has been of a high standard, which enabled an efficient audit.
This is demonstrated by the fact that we only returned 7% of working papers provided by
officersfor furtherclarification.
Quality of draft financial
statements
A full draft of the Annual Accounts were received for audit on 23 June 2022. We identified
a small numberof requiredchanges primarilyrelatingto formatting.
Response to control
deficiencies identified
We identified one control deficiency during our audit. Further insight can be seen on page
19.
Volume and magnitude of
identified errors
We identified 4 misstatements and 2 disclosure misstatements at the time of writing this
report. Management have corrected for these adjustments. For further detail see pg. 27-
29.
Quality Indicators
Impact on the execution of our audit
Management and those charged with governance are in a position to influence the effectiveness of our audit, through timely formulation of judgements,
provision of accurate information, and responsiveness to issues identified in the course of the audit. This slide summarises some key metrics related to your
control environment which can significantly impact the execution of the audit. We consider these metrics important in assessing the reliability of your
financialreportingandprovidecontext forothermessages in thisreport.
Lagging Developing Mature! !
!
Deloitte Confidential - Approved External Use only
!
37

Page 38

88
Our Audit Explained
We tailor our audit to your business and your strategy
Identify
changes
in your
business and
environment
Determine
materiality Scoping
Significant
risk
assessment
Conclude on
significant
risk areas
Other
findings
Our audit
report
Identify changes in your business
and environment
In our planningreport we identified
the key changes in your business
and articulated how these
impactedour auditapproach.
Scoping
Our planning report set out the
scoping of our audit in line with
the Code of Audit Practice. We
have completed our audit in line
with our auditplan.
Significant risk assessment
In our planning report we
explained our risk
assessment process and
detailed the significant risks
we have identified on this
engagement. We report our
findings and conclusions on
these risks in thisreport.
Determine materiality
When planning our audit we set our materiality
at £10.6m (Council only £10.07m) based on
forecast gross expenditure. We have updated
this to reflect final figures and completed our
audit to group materiality of £10.51m (Council
only £10.50m), group performance materiality
of £7.36m (Council only £7.35m) and report to
you in this paper all misstatements above
£250,000.
Other findings
As well as our conclusions on the significant risks we are
required to report to you our observations on the internal
control environment as well as any other findings from the
audit.
Our audit report
Based on the current
status of our audit work,
we envisage issuing an
unmodifiedauditreport.
Conclude on significant risk
areas
We draw to the Audit and
Scrutiny Committee’s attention
our conclusions on the significant
audit risks. In particular the
Committee must satisfy
themselves that management’s
judgementsare appropriate.
Deloitte Confidential - Approved External Use only38

Page 39

99
Overly optimistic, likely
to lead to future debit.
Overly prudent, likely
to lead to future credit
Significant Risks
Dashboard
Risk Material Fraud
risk
Planned
approach to
controls
testing
Controls
testing
conclusion
Consistency of
judgements with
Deloitte’s
expectations
Comments Page no.
Recognition of COVID-19 related
income D+I Satisfactory Satisfactory 10
Management override of controls D+I Satisfactory Satisfactory 11
D+I: Testing of the design and implementation of key
controls
Deloitte Confidential - Approved External Use only39

Page 40

10
Recognition of COVID-19 related income
Significant Risks (continued)
Risk identified and key judgements Deloitteresponseand challenge
ISA 240 states that when identifying and assessing the risks of material
misstatement due to fraud, the auditor shall, based on a presumption that
there are risks of fraud in revenue recognition, evaluate which types of
revenue,revenuetransactionsor assertions give rise to such risks.
We have assessed the income streams of the Council, the complexity of the
recognition principles and the extent of any estimates used, and concluded
that, with the exception of the funding received in 2021/22 in response to
theCOVID-19 pandemic,thereis no significantrisk of fraud.
During 2021/22, the Council has received additional funding in relation to
COVID-19 mobilisation costs. In addition, there are a number of business
support schemes designed to help eligible businesses during the COVID-19
pandemic that are being administered by Councils on behalf of the Scottish
Government.
We have pinpointed the significant risk to the completeness and occurrence
of the funding for COVID-19 mobilisation costs and the completeness and
accuracy of the agencyarrangementdisclosures.
The key judgementsfor managementare assessing:
• Anyconditionsassociated with themobilisationcost funding;and
• Whether the Council is acting as a principal or agent in administering the
businesssupportschemes.
We have performedthefollowing:
• Assessed the design and implementation of the controls in relation to the
accountingtreatmentof all COVID-19 relatedfunding;
• Tested a sample of funding for COVID-19 mobilisation costs and confirm
these have been recognised in accordance with any conditions applicable;
and
• Tested the agency arrangement disclosures to confirm, where it is
concludedthattheCouncil is actingas an agent,that:
• Transactions have been excluded from the Comprehensive Income
andExpenditureStatement;
• The Balance Sheet reflects the debtor or creditor position at 31
March 2022 in respect of cash collected or expenditure incurred on
behalfof the principal; and
• The net cash position at 31 March 2022 is included in the financing
activitiesin the Cash Flow Statement.
Deloitte view
We have concluded that income has been correctly recognised in
accordance with the requirements of the Code of Practice on Local
Authority Accounting and the “Guidance on Accounting for Coronavirus
(COVID-19)Grants/ Funding Streams” issued byLASSAC.
Deloitte Confidential - Approved External Use only40

Page 41

11
Management override of controls
Significant Risks (continued)
Risk identified
Management is in a unique position to perpetrate fraud because of their
ability to manipulate accounting records and prepare fraudulent financial
statements by overriding controls that otherwise appear to be operating
effectively.
Although management is responsible for safeguarding the assets of the
entity, we planned our audit so that we had a reasonable expectation of
detecting material misstatements to the Annual Accounts and accounting
records.
Deloitteresponseand challenge
In considering the risk of management override, we have performed the
followingauditproceduresthatdirectlyaddressthisrisk:
Journals
We have tested the appropriateness of journal entries recorded in the general
ledgerandother adjustmentsmadeinthe preparation ofthe Annual Accounts.
Indesigningandperformingauditproceduresforsuchtests,wehave:
• Tested the design and implementation of controls over journal entry
processing;
• Made inquiries of individuals involved in the financial reporting process
about inappropriate or unusual activity relating to the processing of journal
entriesandotheradjustments;
• Selected journal entries and other adjustments made at the end of a
reportingperiod;and
• Tested journal entries throughout the year based on fraudulent
characteristics.
Accountingestimatesand judgements
We have reviewed accounting estimates for biases and evaluate whether the
circumstances producing the bias, if any, represent a risk of material
misstatement duetofraud.Inperformingthisreview,wehave:
• Evaluated whether the judgments and decisions made by management in
making the accounting estimates included in the Annual Accounts, even if
they are individually reasonable, indicate a possible bias on the part of the
entity'smanagementthatmayrepresentariskofmaterialmisstatementdue
to fraud. From our testing we did not identify any indications of bias. A
summaryofthe keyestimatesconsideredisprovidedonthefollowingpage;
and
• Performed a retrospective review of management judgements and
assumptions related to significant accounting estimates reflected in the
AnnualAccountsoftheprioryear.
Significant and unusual transactions
We did not identify any significant transactions outside the normal course
of businessor anytransactionswhere thebusinessrationalewas notclear.
Deloitte view
We have not identified any significant bias in the key judgements
made bymanagement.
We have not identified any instances of management override of
controls in relationto the specific transactionstested.
Deloitte Confidential - Approved External Use only41

Page 42

12
Management override of controls (continued)
Significant Risks (continued)
Key judgements The key judgment in the annual accounts relates to our significant risk around the recognition of COVID-19 income (page 10). While not
considered to be significant audit risks, we have considered the assumptions used to calculate the pension liability (page 14), and the
recognition of expenditure (page 17). In the table below, we set out our challenge of the assumptions used in the determination of
propertyvaluations,PFIprojects andprovisions.
Estimate /
judgement
Details of management’s position Deloitte Challenge and conclusions
Property
valuations
The Council is required to hold property assets
within Property, Plant and Equipment at
existing use value provided that an active
market for the asset exists. Where there is no
active market, because of the specialist nature
of the asset, a depreciated replacement cost
approach may be needed which provides the
current cost of replacing an asset with it
modernequivalentasset.
The valuations are, by nature, significant
estimates based on specialist and management
assumptions and which can be subject to
materialchanges in value.
The Council has had an independent valuation
carried out at 31 March 2022 by its internal
valuers to include valuation of 20% of all of the
Council’s land and property in accordance with
its 5-yearrollingprogramme.
The valuation method has not changed from
the prior year and is in line with International
Financial Reporting Standards. The Council’s
revaluation reserve has experienced a surplus
position of £11.509m and the net revaluation
movementin the yearequatedto £11.994m.
We did not identify this as a significant risk in our Audit Plan as our property
specialists, Real Asset Advisory, reviewed the methodology applied by the Council’s
valuer in previous years and concluded it was robust. We have confirmed that the
valuerandthemethodologyappliedhasnot changedin theyear.
We also tested a sample of revaluations in the year by agreeing this to the valuer’s
report and tracing the impact to the Revaluation Reserve and/or CIES. An error was
identified in relation to the Revaluation Reserve. Further insight can be seen on page
27.
We have completed input testing of valuations back to source documentation
includingfloorareas to individualasset site plans.
We have challenged management’s assessment for those assets not subject to
valuation in the year and consulted with our internal property experts. For those
valued on Existing Use Value on a market comparable basis, our property experts
have confirmedthatminimal market valuemovementwould be expected in 2021/22.
For those valued on a Depreciated Replacement Cost basis, which would be impacted
by changes in build costs during the year, we have performed an analysis of changes
in the Build Costs Information Service (BCIS) index and concluded that no material
movement would be expected. We are therefore satisfied that there is no indication
of a material movementin assets not formallyrevaluedduringtheyear.
42

Page 43

13
Management override of controls (continued)
Significant Risks (continued)
Estimate /
judgement
Details of management’s position Deloitte Challenge and conclusions
PrivateFinance
Initiatives
(‘PFI’) and
similar
contracts
The Council currently has 3 PFI and similar projects: Clyde
Valley Waste, North Ayrshire Council Schools and Largs
Campus. Each PFI liability is valued based on the value of the
remaining lease payments under the relevant accounting
standards. The minimum lease rental is split between
interestandprincipalusingthe actuarialmethod.
We obtained and assessed the initial PFI agreements in place and
reconciled to the payment schedules for each model. We identified a
factual disclosure error in Note 18 equating to £8.46m for service
charges and contingent rentals. Management have corrected this error
and we have confirmed that it has not had any impact on the PFI
liability.Furtherdetailscan be viewed on page 29.
We have conducted a retrospective review of the prior year liability to
assess accuracy, and have challenged any changes made to the model.
We have assessed the value of the underlying buildings through our
Valuationswork.
We are satisfied that the PFI liability recognised in the accounts is in
line with themodels andthereis no indicationof managementbias.
Provisions The total provisions held within the Council’s balance sheet is
immaterial, at £1.217m. This comprises of a number of
individuallyimmaterial provisions,including:
• EqualPay / SingleStatus£0.130m
• TerminationBenefits£0.161m
• LandfillSite Restoration£0.363m
• Employee Costs – PaidAbsences £0.148m
• Teachers Maternity£0.198m
• FormerAuthorities£0.217m
We examined the rationale for each provision, including a
retrospective review of amounts provided in 2020/21. We have
consulted with the Council’s legal experts to confirm completeness of
theprovisions.
We concludedthatthe provisionsmade were reasonable.
Deloitte Confidential - Approved External Use only43

Page 44

14
Other Areas of Audit Focus
Defined benefits pension scheme
Background
The Council participates in two defined benefits schemes:
• Scottish Teachers’ Superannuation Scheme, administered by the Scottish
Government;and
• The StrathclydePension Fund,administeredbyGlasgow CityCouncil.
The net pension liability has decreased from £180.577m in 2020/21 to
£56.983m in 2021/22. The decrease is a combination of an increase of £94m
in the fair value of the assets and a reduction of £30m in the liabilities as a
resultof demographicchanges andfinancialassumptions.
Deloitte response
• We assessed the independence and expertise of the actuary supporting
thebasis of relianceupontheirwork;
• We reviewed and challenged the assumptions made by Hymans
Robertson, including benchmarking against nine leading actuarial firms
thatwe consider appropriateas shown thetablebelow;
• We have obtained assurance from the auditor of the pension fund over
thecontrols for providingaccurate datato theactuary;
• We assessed the reasonableness of the Council’s share of the total assets
of the scheme with the PensionFundfinancialstatements;
• We have reviewed and challenged the calculation of the impact of the
McCloudandGoodwin cases on pensionliabilities;and
• We reviewedthedisclosureswithin theaccounts againsttheCode.
Council Comments
Discount rate (% p.a.) 2.7 Within
reasonable
RangeRPI Inflation (% p.a.) 3.65
CPI Inflation (% p.a.) 3.2
Pension increase in payment (% p.a.) 3.2
Salary increase (% p.a.) 3.9 In line with
funding
valuation
Mortality- Life expectancy of a male/
female pensioner from age 65 (currently
aged 65)
19.6/ 22.4 Within
reasonable
range
Mortality- Life expectancy of a male/
female pensioner from age 65 (currently
aged 45)
21/ 24.5
44

Page 45

15
Other Areas of Audit Focus (continued)
• Goodwin – this is a legal challenge made against the Government in
respect of unequitable benefits for male dependants of female members
(based on service after 1988) following the earlier Walker ruling. The 31
March 2020 triennial funding valuation did not allow for the impact of
Goodwin, therefore the Council’s actuary has used the same percentage
allowance that was used last year (0.1% of the liability). Given the lack of
relative data available, we have concluded that the actuary’s calculation
approachis reasonable.
• McCloud – this case is in respect of possible discrimination in the
implementation of transitional protections following the introduction of
the reformed public services pension schemes from 1 April 2014 and 2015.
The actuary has advised that an estimated allowance for McCloud has
been included within the current service cost, consistent with the prior
year. We have concluded that the allowance made and approach taken is
reasonable. There is still uncertainty about the form of compensation that
will be provided to members and therefore the final actual cost of
complyingwith therulingmay be differentto the estimate.
Defined benefits pension scheme (continued)
The Council’s pension liability continues to be impacted by the ongoing legal
cases – known as McCloud and Goodwin, as well as the Guaranteed
Minimum Pensions (GMP) indexation. Our pension specialists have
consideredtheimpact andconcludedas follows:
Deloitte view
Management have agreed to adjust the annual accounts for the above
issue. We have therefore concluded that the pension liability in relation
to the definedbenefitspensionscheme is fairlystated.
• GMP indexation – in order to ensure smooth transition to the single tier
State pension and equalisation of GMP benefits between males and
females, the Government introduced an interim solution in March 2016 in
respect of people who are in public service pension schemes and who
have a State Pension Age (SPA) between 6 April 2016 and 5 December
2018, whereby full inflationary increases will be provided by the LGPS. An
announcement on 23 March 2021 confirmed that all public service
pension schemes, including the LGPS, will need to provide full indexation
to members with a SPA beyond 5 April 2021. This is a permanent
extension of the previous interim solution. We have confirmed that the 31
March 2020 funding valuation for the whole Fund included an allowance
for the additional liability arising as a result of GMP indexation. As this
valuation was used as the starting point for the 31 March 2022 valuation,
this has also been included in the current year liability. We have
concludedthattheapproachtaken is reasonable.
From review of the actuary report, our pension specialists identified the
followingissue:
• The actuary has calculated an “experience loss” of £1.946m. Based on the
data provided during the audit, we have estimated that this should be
circa. £2.413m. In the absence of further information to justify the
quantum of the experience loss, there is a potential misstatement of
£0.467m.
45

Page 46

16
Other Areas of Audit Focus (continued)
Infrastructure Assets
Background
Infrastructure assets are inalienable assets, expenditure on which is only
recovered by continued use of the asset created. They include
carriageways, structures, street lighting, street furniture and traffic
managementsystems, andare measuredat historical cost.
The CIPFA Code requiresthatwhere a componentof an asset is replaced:
• the cost of the new component should be reflected in the carrying
amountof theinfrastructureasset; and
• the gross costs and accumulated depreciation of the old component
shouldbe derecognisedto avoid doublecounting.
Auditors have identified that local authorities in the UK have not been
properly accounting for infrastructure assets since the move to IFRS in
2010/11 due to information deficits. This is particularly the case in relation
to roads, where the engineering records used for maintenance have not
beencreatedto map againstidentifiablecomponents.
CIPFA/ LASAAC attempted to resolve the issues and undertook an urgent
consultation on temporary changes to the accounting code. However, it
was unable to agree an approach that addressed the concerns of all
stakeholders whilst also supporting high quality financial reporting. The
Scottish Government has therefore provided temporary statutory overrides
while a permanentsolutionis developed.
Deloitteview
We have assessed the impact of the adoption of the statutory overrides
and confirmed the updated Annual Accounts correctly reflect the
required disclosure. We are also satisfied that the depreciation charge
for the year, based on UEL’s set out within the Council’s accounting
policy, is not materially misstated. As the Council's Fixed Asset Register
has a degree of detail in terms of different types of infrastructure assets
held, the Council should revisit its UEL policy to consider whether
alternativeUEL's shouldbe set for differenttypesof assets.
The Scottish Government expects that Councils will begin to address
information deficits to ensure adequate accounting records for the
measurement of infrastructure assets and timely adoption of the Code
requirementsonce a more permanentsolution is delivered.
Deloitte response
• We have considered the statutory overrides issued by the Scottish
Government and confirmed that the Council has opted to adopt both, as
summarised above, due to not readily having the information to evidence
thederecognitionof replacedcomponentsof infrastructureassets.
• We have reviewed the updated Annual Accounts and revised disclosures
andconfirmedthatit is compliant with thestatutoryoverrides.
• We have assessed the reasonableness of the Useful Economic Lives (UEL’s)
applied by the Council in its depreciation calculation and concluded that
the UEL’s are reasonable,in line with other similar Council and the risk of a
materialmisstatement on thedepreciationcharge is remote.
Statutory
override 1
For accounting periods commencing from 1 April 2021 until 31 March
2024, a local authority is not required to report the gross cost and
accumulated depreciation for infrastructure assets.
Statutory
override 2
For accounting periods commencing from 1 April 2010 until 31 March
2024, the carrying amount to be derecognised in respect of a replaced
part of an infrastructure asset is to be taken to be and accounted for as a
nil amount No subsequent adjustment shall be made to the carrying
amount of the asset with respect to that part.
46

Page 47

1717
Other Areas of Audit Focus (continued)
Expenditure recognition
Risk identified
In accordance with Practice Note 10 (Audit of financial statements of public sector bodies in the United Kingdom), in addition to the presumed risk of
fraud in revenue recognition set out in ISA (UK) 240, auditors of public sector bodies should also consider the risk of fraud and error on expenditure. This
is on the basis that most public bodies are net spending bodies, therefore the risk of material misstatement due to fraud related to expenditure may be
greaterthantherisk of material misstatementdueto fraudrelatedto revenuerecognition.
We have considered this risk for the Council and concluded that we are satisfied that the control environment is strong and there is no history of errors
or auditadjustments. Thiswas thereforenot beenassessed as a significantrisk area, butcontinuedto be an areaof auditfocus.
Deloitte response
We performed the following procedures to address the above risk:
• A review of the number and median value of invoices processed in the year. As
illustrated in table opposite, based on the medium amount, the Council would
need to omit over 46,620 invoices at year-end to result in a material error. We
noted that in the month following the year-end, a total of 7,557 invoices were
processed. We therefore concluded that a risk of material misstatement was
remote.
• An analytical review to test the completeness and accuracy of year-end creditor
balances was carried out. We are satisfied that the amount recorded is
reasonable.
Deloitte view
We have concluded that expenditure has been correctly recognised in accordance with the requirements of the Code of Practice on Local Authority
Accounting.
Invoice Analysis
Medianinvoice amount £216
Average number of invoices
processed per month
6,311
Number of invoices that would
need to be unrecorded to cause a
material misstatement
46,620
Total invoices processed in April
2022 (one month after year-end)
7,557
Deloitte Confidential - Approved External Use only47

Page 48

1818
Other Areas of Audit Focus (continued)
Charitable trusts
Risk identified
From 2013/14, all Scottish Councils who act as sole trustees for any registered charities have to fully comply with the Charities Accounts Regulations. This
requires Charities SORP compliant accounts to be prepared for each charity, and a separate audit of each. North Ayrshire Council administers eight such
registeredcharities,disclosed in a single set of annualaccounts.This is in accordance with theconnectedcharitiesrules.
As the gross income of each of the Trusts is less than £100,000, the Council has opted to prepare the charitable trust accounts on a receipts and payments
basis in accordance with The Charities Accounts (Scotland) Regulation 2006. Fully compliant Charities SORP accounts are therefore not required and
disclosure is limited to thatspecifiedin theRegulations.
Deloitteresponse
We have assessed that the Statement of Receipts and Payments and the
Statement of Balances to ensure these have been prepared in accordance with
theCharitiesAccounts (Scotland)Regulations2006.
A summary is provided in the table adjacent. From an initial review of draft
annual accounts we note that there has been a large movement in payments
which have increased by £7,553 since 2020/21. This is due to the increase in grant
awardsduringtheyear.
Deloitte view
Our testingof thecharitabletrustsis complete with no issues identifiedWe anticipateissuingan unmodifiedopinion.
Deloitte Confidential - Approved External Use only
0 5,000 10,000 15,000 20,000
Payments
Receipts
Charitable Trust Balances (£)
2020/21 2021/22
48

Page 49

1919
Other Significant Findings
Internal control
The purpose of the audit was for us to express an opinion on the financial statements. The audit included consideration of
internal control relevant to the preparation of the financial statements in order to design audit procedures that are
appropriate in the circumstances, but not for the purpose of expressing an opinion on the effectiveness of internal
control. The matters being reported are limited to those deficiencies that we have identified during the audit and that we
have concludedare of sufficientimportanceto merit beingreportedto you.
During the course of our audit we have identified one internal control finding, which we have included below for information.
Area Observation Priority
Revaluation
Reserve
Postings
During the course of our audit engagement, management informed us of an error in relation to the revaluation
reserve. The error arose as a result of the Integra system inadvertently recognising devaluations in the
revaluation reserve. The result of this brought two assets to a negative value. We have summarised this
misstatementon page 27.
As a result of this, we recommend that management investigate this fault within Integra system with immediate
effect. Management should rectify this and input pre-emptive measures to prevent similar errors occurring in the
future.
We also recommend that management review the revaluation reserve postings prior to preparing the Annual
Accounts. This shouldensurethatsimilar errorsdo not occur in the future.
Low Priority
Medium Priority
High Priority
49

Page 50

2020
Qualitativeaspectsof your accountingpractices:
The Council has prepared its Annual Accounts in line with the Code of
Practice on Local Authority Accounting. We are satisfied that the
Council’saccountingpractices are appropriate.
Other mattersrelevantto financial reporting:
We have not identified other matters arising from the audit that, in the
auditor's professional judgement, are significant to the oversight of the
financialreportingprocess.
We received an objection to the Council’s accounts in accordance with
section 1010 of the Local Government (Scotland) Act 1973 in relation to
the Common Good and Trust funds. We have provided an initial
response and currently considering the detail. Any significant matters
arising will be reported to the Audit and Scrutiny Committee prior to the
approvalof theaccounts.
Significant mattersdiscussed with management:
Significant matters have been discussed with management throughout
the audit engagement. In particular, we discussed the treatment of the
prior year reclassification of income/expenditure adjustment (as
outlined on page 28). We also discussed the treatment of infrastructure
assets (as outlinedon page 16).
Regulatory Change:
IFRS 16, Leases, comes into effect on 1 April 2022, therefore will be
implemented in financial year 2022/23. This will require adjustments to
recognise on balance sheet arrangements currently treated as operating
leases. We have considered the preparatory work carried out by
management and the disclosures made in the 2021/22 Annual Accounts
and are satisfied that the new standard has been appropriately
considered.
Other Significant Findings
Financial reporting findings
We will obtain written representations from the Council on matters material to the Annual Accounts when other sufficient appropriate audit
evidencecannotreasonablybe expectedto exist. A copyof thedraftrepresentationsletterhas beencirculatedseparately.
Below, we set out the findings from our audit surrounding your financial reporting process.
Deloitte Confidential - Approved External Use only50

Page 51

2121
Our opinion on the financial
statements
Based on our audit work completed
to date, we expect to issue an
unmodifiedauditopinion.
Material uncertainty related to
going concern
We have not identified a material
uncertainty related to going concern
and will report by exception
regarding the appropriateness of the
use of the going concern basis of
accounting.
Practice Note 10 provides guidance
on applying ISA (UK) 570 Going
Concern to the audit of public sector
bodies. The anticipated continued
provision of the service is relevant to
the assessment of the continued
existence of a particularbody.
Emphasis of matter and other
matterparagraphs
There are no matters we judge to be
of fundamental importance in the
Annual Accounts that we consider it
necessary to draw attention to in an
emphasisof matterparagraph.
There are no matters relevant to
users’ understanding of the audit
that we consider necessary to
communicate in an other matter
paragraph.
Other reportingresponsibilities
The narrative parts of the Annual
Accounts is reviewed in its entirety
for material consistency with the
annual accounts and the audit work
performed and to ensure that they
are fair,balancedandreasonable.
Our opinion on matters prescribed
by the Controller of Audit is
discussed furtheron page 22.
Our Audit Report
Other matters relating to the form and content of our report
Here we discuss how the results of the audit impact on other significant sections of our audit report.
Deloitte Confidential - Approved External Use only51

Page 52

2222
Requirement Deloitteresponse
Management
Commentary
The management commentary comments
on financial performance, strategy and
performance review and targets. The
commentary included both financial and
non financial KPIs and made good use of
graphs and diagrams. The Council also
focuses on the strategicplanningcontext.
We have assessed whether the management commentary has been prepared in
accordance with the statutoryguidance.
We have also read the management commentary and confirmed that the information
contained within is materially correct and consistent with our knowledge acquired during
thecourse of performingtheaudit,andis nototherwise misleading.
Following amendments for minor improvements in the final version of the Annual
Accounts, we are satisfied that the management commentary has been prepared in
accordance with guidance, is consistent with our knowledge and is not otherwise
misleading.
Remuneration
Report
The remuneration report has been
prepared in accordance with the 2014
Regulations, disclosing the remuneration
and pension benefits of Senior councillors
andSeniorEmployees of the Council.
We have audited the disclosures of remuneration and pension benefits, pay bands, and
exit packages, and we can confirm that they have been properly prepared in accordance
with theregulations.
Annual
Governance
Statement
The Annual Governance Statement reports
that the Council’s governance
arrangements provide assurance, are
adequateandare operatingeffectively.
We have assessed whether the information given in the Annual Governance Statement is
consistent with the financial statements and has been prepared in accordance with the
Delivering Good Governance in Local Government Framework. We conclude that the
Annual Governance Statement is consistent with the financial statements, our knowledge
andtheaccounts regulations.
Your Annual Report
We are required to provide an opinion on the auditable parts of the Remuneration Report, the Annual Governance Statement and whether the
ManagementCommentaryis consistent with thedisclosures in theaccounts.
Deloitte Confidential - Approved External Use only52

Page 53

23
Audit Dimensions and Best Value
53

Page 54

24
Audit Dimensions and Best Value
Overview and conclusions
Financial management
The Council continues to have robust budget setting and monitoring
arrangements in place. This is supported by an experienced finance team
and a robust internal audit function, as well as appropriate arrangements
for thepreventionanddetectionof fraudanderror.
Financial sustainability
The Council has set a balanced budget for 2022/23 and holds unearmarked
reserves at a level consistent with its Reserves Strategy, therefore is
financially sustainable in the short term. However, it continues to be faced
with significantfinancialchallenges overthe mediumandlonger-term.
It is positive to see the work progressing with the sustainable Change
Programme, incorporating a comprehensive benefits tracker and a clear
commitment to invest in recovery and renewal. However, progress
continues to be impacted by the pandemic. It is critical that this work is
progressed at pace and scale to ensure that the planned benefits are
realised.
Governanceand transparency
The Council continues to have strong leadership, which has been enhanced
in the year with the creation of additional capacity at Head of Service level
to focus on priorities. The governance arrangements also continue to be
robust, with a comprehensive review of the infrastructure to enable hybrid
meetings and an effective Audit and Scrutiny Committee. The Council
continues to be open and transparent and demonstrates a culture of
continuous improvement, with the planned development of a Participation
Strategy.
Value formoney
The Council continues to have a clear and robust performance
management framework in place which has been enhanced in the year
with the Performance Management Strategy and new Performance
Dashboard. It has continued to report its performance against the
priorities within the Council Plan and also against the Local Government
Benchmarking Framework (LGBF) with clear actions in place to address
indicatorsthatare adriftof target.
As set out in our audit plan and separate report on the “Audit Dimensions and Best Value” presented to the Committee in, May 2022 public audit in Scotland
is wider inscope thanfinancialaudits. Ours separatereportsets outourfindingsandconclusions on our auditwork coveringtheareasset outbelow.
In accordance with the Code of AuditPractice, ouroverall conclusions on each auditdimensionandbest valueare summarised on thefollowingpage.
Deloitteview – Best Value
The Council has robust arrangements in place to secure best value and
hasa clear understandingof areaswhich requirefurtherdevelopment.
Deloitte Confidential - Approved External Use only54

Page 55

2525
Purpose of our Report and Responsibility Statement
Our report is designed to help you meet your governance duties
What we report
Our report is designed to help the Audit and Scrutiny Committee and the
Council discharge their governance duties. It also represents one way in
which we fulfil our obligations under ISA (UK) 260 to communicate with you
regarding your oversight of the financial reporting process and your
governancerequirements.Our reportincludes:
• Results of our work on key audit judgements and our observations on the
qualityof yourAnnualAccounts;
• Our internalcontrol observations;and
• Otherinsightswe have identifiedfrom ouraudit.
What we don’t report
As you will be aware, our audit was not designed to identify all matters that
may be relevantto the AuditandScrutinyCommittee.
Also, there will be further information you need to discharge your
governance responsibilities, such as matters reported on by management or
byotherspecialist advisers.
Finally, our views on internal controls and business risk assessment should
not be taken as comprehensive or as an opinion on effectiveness since they
have been based solely on the audit procedures performed in the
proceduresperformedin fulfillingourauditplan.
The scopeof our work
Our observations are developed in the context of our audit of the annual
accounts.
We describedthescope of ourwork in our auditplan.
We welcome the opportunity to discuss our report with you and receive
yourfeedback.
Use of this report
This report has been prepared for the Council, as a body, and we therefore
accept responsibility to you alone for its contents. We accept no duty,
responsibility or liability to any other parties, since this report has not been
prepared,andis notintended,foranyotherpurpose.
Pat Kenny, CPFA
For and on behalf of Deloitte LLP
Glasgow | 27 October 2022
Deloitte Confidential - Approved External Use only55

Page 56

26
Appendices
56

Page 57

2727
Audit Adjustments
Unadjusted misstatements
Thereare no uncorrectedmisstatementsupto thedateof thisreport.
Corrected misstatements
The following misstatements have been identified up to the date of this report which have been corrected by management. We nonetheless communicate
them to you to assist you in fulfillingyour governanceresponsibilities,includingreviewingthe effectivenessof thesystem of internalcontrol.
Debit/(Credit)
Comprehensive
Income and
Expenditure
Statement (CIES)
£k
Debit/(Credit)
in Net Assets
£k
Debit/(Credit)
prior year
Reserves
£k
Debit/(Credi
t)
in Income
£k
If applicable,
control
deficiency
identified
Misstatements identified in current year:
Impairment Charge [1] 1,272
Revaluation Reserve [1] (1,272)
Prepayments [2] 212 (212)
Pension experience items [3] 467 (467)
Total 679 (679) - -
[1] The Integra system inadvertently recognised devaluations in the revaluation reserve bringing two assets to a negative value. We have discussed
this with management and reviewed their workings. We have also recalculated the correcting adjustments and, we have comfort that this only
occurred in isolation for two assets. This has been corrected by management and a control deficiency has been summarised on page 19.
[2] An insurance prepayment was made in the year totalling £250,000 and a subsequent reversal should have been made totalling £212,000 as this
was no longer a valid prepayment as at 31/03/2022. The closing prepayment at year-end is £38,000. Management has corrected for this
misstatement.
[3] As discussed on page 15, In the absence of further information to justify the quantum of the experience loss, there is a potential misstatement
of £0.467m.
57

Page 58

2828
Audit Adjustments (continued)
Corrected misstatements (continued)
The following misstatements have been identified up to the date of this report which have been corrected by management. We nonetheless communicate
them to you to assist you in fulfillingyour governanceresponsibilities,includingreviewingthe effectivenessof thesystem of internalcontrol.
Debit/(Credit)
Comprehensive
Income and
Expenditure
Statement (CIES)
£k
Debit/(Credit)
in Net Assets
£k
Debit/(Credit)
prior year
Reserves
£k
Debit/(Credit)
in Income
£k
If applicable,
control
deficiency
identified
Misstatements identified in prior year:
Chief Executive Income [4] 39,394
Other Corporate Items Income [4] (39,394)
Chief Executive Expenditure [4] (41,802)
Other Corporate Items Expenditure [4] 41,802
Total -
[4] Management reclassified housing discretionary income and expenditure in the current year to Other Corporate Items but did not reclassify the
prior year equivalent income and expenditure to this cost centre. This was not in accordance with IAS 1 and the Code which requires entities to
present financial statements in a comparative format. Management have correctly restated these figures from Chief Executive to Other Corporate
Items for the prior year.
58

Page 59

2929
Audit Adjustments (continued)
Disclosures
Disclosure misstatements
The following misstatements have been identified up to the date of this report which have been corrected by management. We nonetheless communicate
them to you to assist you in fulfillingyour governanceresponsibilities,includingreviewingthe effectivenessof thesystem of internalcontrol.
Disclosure Summaryof disclosure requirement Quantitativeor qualitative consideration
Prior Year Reclassification
Disclosures in relation to a prior period reclassification
did not initially comply with the Code, which requires
thefollowing:
a) The natureof thereclassification;
b) The amount of each item or class of items that is
reclassified, and
c) The reason forthereclassification.
Management have since revised the disclosure in
accordance with the Code.
The misstatement is quantitatively and qualitatively
materialfor theusers of the financialstatements.
PrivateFinanceInitiative(“PFI”)
Note 18 of the Annual Accounts details contracts that
the Council have in place with PFI holders. This
includes North Ayrshire Council Schools, Largs Campus
andClyde ValleyWaste.
We discovered a factual disclosure error in Note 18
equating to £8.46m for service charges and contingent
rentals. This did not impact the liability position at the
year-end.
This was due to a fault within management’s working
paperwhich calculates thesplit of Note 18.
The error is above performance materiality is therefore
quantitativelymaterial.
59

Page 60

30
Action Plan
Recommendations for Improvement
No. Area Recommendation Management Response Responsible person Target Date Priority
1 Infrastructure Assets
The Council's Fixed Asset Register has a
degree of detail in terms of different types
of infrastructure assets held, the Council
should revisit its UEL policy to consider
whether alternative UEL's should be set for
differenttypesof assets.
In order to support the
ongoing review of the Code
requirements in relation to
accounting for
Infrastructure Assets, the
nature of assets held under
Infrastructure Assets will be
reviewed and engineering
advice will be sought to
ensure that the assigned
UEL’s are consistent with
the nature of the assets.
Head of Finance March 2023 High
60

Page 61

3131
Responsibilities:
The primary responsibility for the prevention and detection of fraud rests
with management and those charged with governance, including
establishing and maintaining internal controls over the reliability of financial
reporting, effectiveness and efficiency of operations and compliance with
applicablelaws andregulations.
As auditor, we obtain reasonable, but not absolute, assurance that the
financial statements as a whole are free from material misstatement,
whethercaused byfraudor error.
Required representations:
We have asked the Council to confirm in writing that you have disclosed to
us the results of your own assessment of the risk that the financial
statements may be materially misstated as a result of fraud and that you
have disclosed to us all information in relation to fraud or suspected fraud
thatyouare aware of andthataffectstheentityor group.
We have also asked the Council to confirm in writing their responsibility for
the design, implementation and maintenance of internal control to prevent
anddetect fraudanderror.
Audit work performed:
In our planning we identified the risk of fraud in relation to recognition of
COVID-19 related income and management override of controls as key audit
risks for yourorganisation.
During course of our audit, we have had discussions with management, those
chargedwith governanceandtheinternalauditdepartment.
In addition, we have reviewed management’s own documented procedures
regardingfraudanderror in theAnnualAccounts.
Our Other Responsibilities Explained
Fraud responsibilities and representations
Deloitte Confidential - Approved External Use only
Deloitteview – Conclusion:
We have not identified any errors concerning our fraud risks in relation
to the recognition of COVID-19 related income and management
overrideof controls.
We have informed management, the Council and the Committee of their
overallfraudresponsibilities.
In addition, we have reviewed management’s own documented
procedures regarding fraud and error in the Annual Accounts. We have
also explained throughout our audit report, how we considered the
auditcapable of detectingirregularities,includingfraud.
61

Page 62

3232
Independence and Fees
Independence
confirmation
We confirm the audit engagement team, and others in the firm as appropriate, Deloitte LLP and, where applicable, all Deloitte
network firmsare independentof the Councilandandour objectivityis not compromised.
Fees The audit fee for 2021/22, in line with the expected fee range provided by Audit Scotland, is £316,670, as analysed below:
£
Auditor remuneration 194,200
Audit Scotland fixed charges:
Pooled costs 20,240
Contribution to PABV 91,869
Audit support costs 10,370
Total fee 316,670
In addition to the above, the audit fee for the charitable trusts audit is £1,200.
No non-audit services fees have been charged for the period.
Non-audit services In our opinion there are no inconsistencies between the FRC’s Ethical Standard and the Council’s policy for the supply of non-
audit services or any apparent breach of that policy. We continue to review our independence and ensure that appropriate
safeguards are in place including, but not limited to, the rotation of senior partners and professional staff and the involvement
of additionalpartnersandprofessionalstaffto carry outreviewsof thework performedandto otherwise advise as necessary.
Relationships We are required to provide written details of all relationships (including the provision of non-audit services) between us and
the organisation, its board and senior management and its affiliates, including all services provided by us and the DTTL
network to the audited entity, its board and senior management and its affiliates, and other services provided to other known
connectedpartiesthatwe consider may reasonablybe thoughtto bear on ourobjectivityandindependence.
We are notaware of anyrelationshipswhich are requiredto be disclosed.
As partof ourobligationsunderInternationalStandardson Auditing(UK), we are requiredto reportto youon thematterslisted below:
Deloitte Confidential - Approved External Use only62

Page 63

Deloitte LLP does not accept any liability for use of or reliance on the contents of this document by any person save by the intended
recipient(s) to the extent agreed in a Deloitte LLP engagement contract.
If this document contains details of an arrangement that could result in a tax or National Insurance saving, no such conditions of
confidentiality apply to the details of that arrangement (for example, for the purpose of discussion with tax authorities).
Deloitte LLP is a limited liability partnership registered in England and Wales with registered number OC303675 and its registered office at 1
New Street Square, London, EC4A 3HQ, United Kingdom.
Deloitte LLP is the United Kingdom affiliate of Deloitte NSE LLP, a member firm of Deloitte Touche Tohmatsu Limited, a UK private company
limited by guarantee (“DTTL”). DTTL and each of its member firms are legally separate and independent entities. DTTL and Deloitte NSE LLP
do not provide services to clients. Please see www.deloitte.com/about to learn more about our global network of member firms.
© 2022 Deloitte LLP. All rights reserved.
63

Page 64

64

Page 65

NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    Accounts Commission’s Report: Scotland’s financial
response to Covid-19 
Purpose:  To inform the Audit and Scrutiny Committee of the findings of
the recently published report. 
Recommendation:  That the Committee (i) notes the findings of the Accounts
Commission report, (ii) notes the recommendation contained
therein; and (iii) notes North Ayrshire Council’s approach in
relation to these. 
1. Executive Summary 
1.1 The Accounts Commission recently published its national report ‘Local Government in
Scotland: Overview 2022’. This report reflects on the impact of the Covid-19 pandemic
on the Scottish Government, Councils and other public sector bodies including fiscal
context in which these bodies operated and the ongoing development and
implementation of plans for financial recovery. A link to the full report is attached as
follows: 
Scotland’s financial response to Covid-19 
1.2  Throughout the report, the Accounts Commissions has identified a number of key
messages in relation to the financial response to the pandemic and made
recommendations for the Scottish Government, Councils, NHS Boards and integration
authorities. 
1.3 North Ayrshire Council received total Covid related financial support of £126.943m
over 2020-21 to 2021-22. At 31 March 2022, North Ayrshire Council retained
£23.767m across a number of reserves to support services and communities
recovering from the ongoing impacts of the pandemic. 
1.4 The Health and Social Care Partnership (HSCP) received Covid related financial
support of £35.255m over the same period. At 31 March 2022, the HSCP reported a
Covid-19 reserve of £13.321m to support ongoing covid related expenditure. 
Agenda Item 5
65

Page 66

2. Background 
2.1 In June 2022, Audit Scotland published a report entitled ‘Scotland’s Financial
Response to Covid-19’. This report reflects on the impact of the Covid-19 pandemic
on the Scottish Government, Councils and other public sector bodies including the
fiscal context in which these bodies operated and the ongoing development and
implementation of plans for financial recovery. 
2.2 The report identifies a number of key messages which have been summarised in the
report as follows: 
• The Scottish Government worked collaboratively and at pace with local and UK
government to direct significant public spending in difficult circumstances. It is
critical that lessons are learned about what worked well, and what did not to
improve the public sector response to any future crises; 
• The Scottish Government streamlined governance arrangements to direct funds
quickly, but it is hard to see how some financial decisions were reached; 
• The Scottish Government directed a large proportion of funding to councils and
other public bodies who had existing systems and local knowledge to enable them
to spend quickly; 
• The Scottish Government has managed its overall budget effectively but some
Covid‑19 funding remains unspent; 
• It is vital for transparency and financial planning that the Scottish Government and
other public bodies are clear about how one-off Covid-19 funding has been spent,
including where spending commitments may last for several years; and 
• More work is needed by the Scottish Government to show how the wide range of
Covid-19 spending measures have worked together to address the harms caused
by the pandemic. 
2.3 The report makes a number of recommendations in relation to the Scottish
Government, Councils, NHS Boards and integration authorities, including:  
• Improve the transparency of public finances to support scrutiny of Covid-19 funding
and spending measures by: 
 collecting, drawing together and analysing Covid-19 funds data to establish how
much money was spent, where, and how quickly it was issued and received; 
 reporting through their accounts and management information how Covid-19
funding held in reserves has been spent, and the extent to which Covid-19
funded spending commitments will exist in future years; 
 reviewing their medium-term and longer-term financial plans to reflect the
ongoing impact and financial consequences of the pandemic. This should
include the longer-term impact on resources and potential costs of continuing to
support citizens and restore lost income; 
66

Page 67

 Continue to monitor and report on fraud and error arising from Covid-19
business support payments to ensure that processes are working in practice,
funds are allocated correctly, and steps are taken to recover funds paid in error; 
• Work together to learn lessons from the financial response to the pandemic by: 
 collecting and sharing findings from their response, including financial
information to demonstrate the impact the spending has had and to allow others
to benefit from good practice; 
 considering what systems should be in place to enable consistent spending
information to be collected while minimising the administrative burden; 
 collectively understanding the ongoing challenges and longer-lasting impacts of
the pandemic which will allow them to work together to recover; 
 developing robust processes which will improve the public sector response to
future crises or other cross-cutting issues, such as climate change and child
poverty; and 
 evaluating whether Covid-19 spending delivered the desired outcomes. 
2.4 In response to the specific recommendations contained within the report, it is noted
that within North Ayrshire: 
• The level of Covid-19 funding and expenditure has been regularly reported to
elected members throughout 2020-21 and 2021-22 as part of the periodic financial
reports of both North Ayrshire Council and the Health and Social Care Partnership; 
• The economic, service delivery and funding impacts of the Covid-19 pandemic
across North Ayrshire were considered as part of the Medium Term Financial
Outlook reported to Council in February 2022; 
• The levels and applications of Covid related reserves have been reported to
elected members throughout the period; 
• Additional control mechanisms to mitigate, detect and prevent fraud in relation to
grant awards to businesses were put in place, including a pan-Ayrshire data
matching exercise; 
• Elected members receive regular updates on the delivery of our Council Plan
objectives through our 6-monthly Council Plan Progress Updates which includes
information on the impact of Covid-19 on service delivery across the Council and
highlights areas of good practice being developed to support recovery and renewal;
and 
• Our Recovery & Renewal Strategy set out a series of key principles and themes to
enable North Ayrshire Council to recover and renew its services in a prioritised
way, ensuring that they met resident needs and addressed key areas including
economic recovery, financial recovery and education recovery. 
67

Page 68

2.5 During 2020-21 and 2021-22, North Ayrshire Council received Covid-19 related
financial support of £126.943m with £103.176m of this utilised in the delivery of
services and the provision of direct support to businesses, families and individuals
during this period.     
2.6 Throughout 2020-21 and 2021-22, North Ayrshire Council has approved the
earmarking of Covid-19 funding balances to support the future delivery of specific
Covid-19 related initiatives and support strategic investment in recovery and renewal
activities across the Council. At 31 March 2022, these included:  
Reserve £m Purpose
Renewal and Recovery
Programme
13.467 Fund to support strategic investment in Recovery and Renewal activities
aligned to the priorities in the Council Plan and Community Wealth
Building strategy. Investment is targeted across the themes of:
Economic Recovery; 
Environmental Initiatives; 
Support for Vulnerable Families, Citizens and Communities; 
Sustainable Investment in physical infrastructure and open space; and 
Mental Health and Wellbeing Initiatives.
Covid Legacy Fund 3.642 Ongoing support for services impacted by Covid restrictions, including
loss of income and adjustments to operating models.
Education Recovery
Programme
3.193 Funds to mitigate against the impact of the Covid pandemic and support
education recovery for children and young people, including engagement
of additional teaching and non-teaching staff and measures to mitigate
the impact of the changes in funding in relation to the Scottish Attainment
Challenge.
CO2 Monitors in
Schools
0.077 Ongoing support for the installation of CO2 monitors across our learning
establishments to reduce the spread of COVID-19.
Tenant Grant Fund 0.284 Support for tenants in the private and social rented sectors who are
struggling with rent arrears and are consequently at risk of homelessness
Financial Insecurity 2.583 Flexible support for businesses and low income households. 
Other Miscellaneous
Covid Reserves
0.521 Residual staffing and administrative support across services. 
23.767 
General Services Funding
Received
In -Year
Expenditure
Carried
Forward
Funding
Received
In -Year
Expenditure
Carried
Forward
£m £m £m £m £m £m £m
Support to individuals, families & communities:
Council Tax Reduction / Scottish Welfare Fund 1.475 0.690 0.785 - - - 0.785
Financial Hardship & Welfare Support 4.290 4.290 - 6.876 3.954 2.922 2.922
Community Food and Free School Meals 2.657 2.512 0.145 -0.145 - -0.145 -
Housing Support 0.418 0.288 0.130 0.314 0.030 0.284 0.414
Community Mental Health 0.370 0.054 0.316 - 0.305 -0.305 0.011
9.210 7.834 1.376 7.045 4.289 2.756 4.132
Support for Education:
Education Recovery and Staffing 6.517 2.137 4.380 2.030 3.217 -1.187 3.193
Digital Inclusion & School Transport 0.583 0.583 - - - - -
CO2 Monitors in Schools - - - 0.077 - 0.077 0.077
7.100 2.720 4.380 2.107 3.217 -1.110 3.270
Support For Businesses:
Business Grants 39.244 39.244 - 13.473 13.473 - -
NDR Grants and Reliefs 14.804 14.804 - 8.401 8.401 - -
Discretionary Grants 2.124 0.284 1.840 - 1.834 -1.834 0.006
56.172 54.332 1.840 21.874 23.708 -1.834 0.006
Other:
General Covid Support 12.597 5.623 6.974 6.731 0.188 6.543 13.517
Employability Funding 1.153 0.994 0.159 - - - 0.159
Loss of Income 2.476 - 2.476 - - - 2.476
Miscellaneous 0.453 0.148 0.305 0.025 0.123 -0.098 0.207
16.679 6.765 9.914 6.756 0.311 6.445 16.359
Total General Services Funding 89.161 71.651 17.510 37.782 31.525 6.257 23.767
2021-22 Total
Carried
Forward
North Ayrshire Council
Utilisation of Covid-19 Funding 2020-21 and 2021-22
2020-2021
68

Page 69

2.7 During 2020-21 and 2021-22, North Ayrshire HSCP received additional financial
support of £35.255m in relation to Covid mobilisation and staff Thank You payments.
£21.934m of this was utilised during this period. 
2.8 At 31 March 2022, North Ayrshire HSCP reported a Covid balance of £13.321m which
was being retained to support ongoing covid-19 related expenditure including
mobilisation costs, provider sustainability payments and care home occupancy
payments. It is currently anticipated that £4.067m of these funds will be required
during 2022-23. However, the Scottish Government has indicated an intention to
recoup any surplus funds during 2022-23 for redistribution elsewhere in the health and
social care system. 
3. Proposals 
3.1 It is proposed that the Committee (i) notes the findings of the Accounts Commission
report, (ii) notes the recommendation contained therein; and (iii) notes North Ayrshire
Council’s approach in relation to these. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Funding
Received
In -Year
Expenditure
Carried
Forward
Funding
Received
In -Year
Expenditure
Carried
Forward
£m £m £m £m £m £m £m
HSCP Mobilisation 14.811 10.087 4.724 18.232 9.635 8.597 13.321
HSCP Staff Thank You Payments - - - 2.212 2.212 - -
Total HSCP Funding 14.811 10.087 4.724 20.444 11.847 13.321
2020-2021 2021-22 Total
Carried
Forward
North Ayrshire HSCP
Utilisation of Covid-19 Funding 2020-21 and 2021-22
69

Page 70

Key Priorities 
4.6 None. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 No consultation has been required in the preparation of this report 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551 or DavidForbes@north-ayrshire.gov.uk. 
Background Papers
None
70

Page 71

NORTH AYRSHIRE COUNCIL 
15th November 2022 
Audit and Scrutiny Committee 
Title:   Year End Performance Reporting:  Council Plan Year
End Progress Report 2021-22, Annual Performance
Report 2021-22 and Local Government Benchmarking
Framework Report 2020-21 
Purpose: To advise the Audit and Scrutiny Committee on progress of
our Council Plan priorities. 
Recommendation:  That the Audit and Scrutiny Committee agrees to: a) Note the
Council Plan year End Progress Report and supporting
performance measures as set out at Appendix One, Two and
Three; b) Note the Council Plan Annual Performance Report
as set out in Appendix Four; and c) Note the status of the
Council’s performance indicators within the 2020-21 LGBF
report at Appendix Five. 
1. Introduction 
1.1. Under the Local Government (Scotland) Act 1992 and Local Government in
Scotland Act 2003 we have a duty to demonstrate Best Value.  To ensure we are
supporting our residents and fulfilling our statutory duties, we actively manage
performance and develop our performance reporting to make it accessible, in order
to invite further scrutiny from our residents and other stakeholders.  Our corporate
performance reports are published on our website www.north-
ayrshire.gov.uk/performance. 
1.2. This report combines three of our key Council Plan and corporate performance
reports: 
• Our six-monthly Council Plan 2019-24 Progress Update (Year End 2021-22)
• Our Annual Performance Report 2021-22
• The Local Government Benchmarking Framework (LGBF) Report 2020-21 
1.3. Due to the timing of these three key performance reports and the recent Local
Government Election, our Executive Leadership Team decided it would be best to
present the reports together at Cabinet and the Audit and Scrutiny Committee to
give Elected Members and our residents an overall view of the performance
management information we manage corporately. 
2. Background 
2.1. Our Council Plan 2019-24 was approved by Council on 26 June 2019 and sets out
our vision and priorities for the next five years.  
Agenda Item 6
71

Page 72

The Council Plan 2019-24 Progress Update (Year End 2021-22) and
accompanying appendices provide detailed information on the progress being
made towards our strategic priority outcomes.  The report includes key activities,
areas of focus, case studies and best in class examples from across our Council
in a magazine style format to ensure this information is easily accessible.  It
provides an overview of performance in the six months up to 31st March 2022. 
2.2. Our Annual Performance Report 2021-22 summarises our performance across
the entire financial year.  For 2021-22, due to the timing of the reports and to
reduce duplication, we have designed an infographic style report with links to our
more detailed six-monthly Council Plan Progress Reports.  It is hoped this ‘at a
glance’ approach will be easier to promote through our North Ayrshire Council
social media channels and therefore improve engagement with our performance
and encourage scrutiny. 
2.3. The Local Government Benchmarking Framework (LGBF) Report 2020-21: 
The LGBF is a national framework which collates performance information from
across all 32 local authorities and is specifically referenced within the Accounts
Commission Strategic Performance Information Direction. The most recent data
available (released in July 2022) relates to 2020/21, which covers the Covid-19
pandemic lockdown periods.  As a result, our performance reflects this
environment and cannot be compared to previous years or other councils directly
(as councils across Scotland redirected resources in bespoke ways to meet the
needs of their residents).  However, it is intended that more in-depth comparisons
and improvement activity will be included in future years. 
3. Performance Summary 
3.1. Key Activities (October to March 2022)
• We delivered a balanced budget for 2022/23 in March including identifying
£4.538m in savings for the year. Although the indicative budget gap for 2023/24
was noted as £10.729m at this time, it is recognised that further significant
inflationary pressures will likely increase this gap further.
• We are working to resettle those displaced due to the war in Ukraine until it is
safe for them to return home.
• Over £7million of our Council budgets was determined through participatory
methods, amounting to 2.32% for 2021/22.
• Money Matters generated over £17.5million in income for our residents in
receipt of welfare benefits this year.
• An additional £2million was approved for our Community Investment Fund in
February, bringing the total approved to £3million this year.  Recent approved
applications include those from Beith Community Development Trust (£15,582)
for a feasibility study into developing a much improved building to meet the
needs of the community and West Kilbride Community Initiative Limited
(£76,605 over three years) for a Technical and Creative Training Programme
and audio visual (AV) service.
• £23.7m was secured for the B714 Upgrade from the UK Government’s
Levelling Up Fund in October 2021 which will aid economic recovery through
improved infrastructure and connectivity.
• We continued our ambitious response to the Climate Emergency including the
development of Council owned renewable energy projects. 
• We published our 10-year Island Plans for Arran and Cumbrae.
• 1,013 of our young people voted in the Scottish Youth Parliamentary Elections
to elect four new Members of the Scottish Youth Parliament.
72

Page 73

• We successfully rolled out universal free school meals to Primary Five children
in January 2022.
• 1,022 Chromebooks have been delivered to schools for Primary Five and S2
pupils in receipt of free school meals or clothing grants.  The remaining 250
Ipads from last year’s order of 600 have been distributed to eligible Primary
Two pupils.
• We have supported 130 local businesses on 249 occasions during the second
half of this year (840 businesses in total during 2021/22).
• 136 young people reported improved mental health and wellbeing outcomes
following engagement in Community Learning and Development activity.  
• We have helped 600 young people progress to employment through our
Kickstart initiative, with our Council’s Gateway creating 300 of these positions.
• We have successfully created 22 Housing First Tenancies during Year Three
bringing the total to 62, exceeding our annual target by 10%.  
• We have completed 681 new Council house units (including a small number of
staff accommodation units in Sheltered Housing complexes).
• We have identified solutions to support hybrid meetings in line with Covid-19
restrictions.   
3.2. Areas of Focus 
3.2.1. As we emerge from the Covid-19 pandemic, we are refocusing our resources from
our response and towards our priority areas and recovering services impacted by
the pandemic such as day services for our residents.  The Council Plan Progress
Report (Year-End 2021-22) contains areas of focus as at 31st March 2022.  Many
of these areas are already progressing.  As at the end of March we stated we
would: 
• Work with NHSAAA and Community Planning partners to develop our Child
Poverty Action Plan for 2022-23, taking account of the Scottish Child Poverty
Delivery Plan 2022-26.
• Scope and progress the “Accessing the Council” initiative to simplify the range
of ways to contact our Council and ensure we provide the best service for our
residents via a ‘no wrong door’ approach.  
• Launch a new community-based energy support model, to help families across
all housing tenures alleviate the impacts of rising energy prices. 
• Recruit permanent employees to our Care at Home workforce to address need
in the community.
• Further develop our participation strategy and locality planning approach.
• Progress our Ayrshire Growth Deal projects, including working towards the
launch of phase one of the Digital Processing Manufacturing Centre (DPMC)
in October.
• Continue our investment in our school kitchens to be prepared for the rollout of
universal free school meals to Primary Six and Seven children.
• Further extend our Community Wealth Building approach to support local
business by implementing a local only Quick Quotes process when procuring
goods and services.
• Progress the procurement of two solar farm installations on the former landfill
sites at Nethermains and Shewalton.
• We will further implement solutions that support hybrid meetings across our
Council.   
73

Page 74

3.3. Council Plan Performance Indicators 
3.3.1. Appendix 2 details Performance Indicators from the Council Plan Performance
Framework, showing (where available) targets and a traffic light (Red, Amber,
Green) symbol to show whether:  the target level of performance has been
achieved (Green); is slightly adrift of target (Amber); or is significantly adrift of
target (Red). 
3.3.2. Analysis of the indicators is outlined in Table 1 below.  Where data is not available
for Year End 2021-22, the most recently available data up to the annual figure for
2020-21 is used.  79.3% of indicators where the status is known are on target or
slightly adrift of target as at 31st March 2022.  This is more than last year, when
78.1% of indicators had this status, however due to surveys on customer
satisfaction and employee engagement not being undertaken due to the
pandemic, there are slightly more PIs where the status is currently unknown this
year.  The two-year period covered below reflects the impact of the lockdown
periods of 2020-21 and the gradual easing of restrictions during 2021-22. 
Table 1
Summary of Performance Indicator Status
Traffic Light Year End 2021-22 Year End 2020-21    
on target 18 (62.1%*) 19 (59.4%**)
slightly adrift 5 (17.2%*) 6 (18.7%**)      
significantly adrift
6 (20.7%*) 7 (21.9%**)
status unknown or
data only
5 (14.7% of all Council
Plan indicators)
2 (5.9% of all Council
Plan indicators) 
* Of the 29 indicators where status is known 
**Of the 32 indicators where status is known
Note: 5 of the 11 indicators slightly or significantly adrift (Amber or Red) were
impacted by the Covid-19 Pandemic. 
3.4. Council Plan Delivery Plan
3.4.1. Appendix 3 details the actions from the Council Plan Delivery Plan.  There are 40
overall actions within the Council Plan supported by 98 sub-actions.  The status of
the sub-actions informs the overall action status.  
3.4.2. At Year End 2021-22 94.9% of actions are either on target or slightly adrift of target
compared to 97.5% at Year End 2020-21. 
74

Page 75

Table 2
Summary of Overall Action Status
Traffic Light Year End 2021-22 Year End 2020-21   
on target 32 (82.1%) 34 (85%)   
slightly adrift 5 (12.8%) 5 (12.5%)   
significantly adrift 2 (5.1%) 1 (2.5%)
(Between Year End 2020-21 and 2021-22, one action was deemed off program
and a second was removed due to duplication, reducing the number of actions
to 39.) 
4. Local Government Benchmarking Framework
4.1. Key Notes include: 
• The range of indicators has increased, with the introduction of four new measures. 
Of the 101 indicators, data is available for 90.  The 11 indicators that have no data
are related to satisfaction.
• Short-term (one year) comparisons are available for 82 indicators:
o 46 (56%) indicators have improved
o 21 (26%) have declined with a further 14 (17%) marginally declining  
o One (1%) remains unchanged
• In terms of quartile, out of 32 local authorities our Council is in the top quartile
(ranked 1st to 8th) for 22 (24%) indicators
• 90 indicators can be compared to the Scottish Average:
o 45 (50%) indicators are performing better than the Scottish
Average
o 44 (49%) are below the Scottish Average
o One (1%) is the same as the Scottish Average
• There is no satisfaction data within the 2020/21 data for any of the 11 indicators,
therefore it has not been possible to provide any analysis for this year. 
• Our Council Plan Performance Framework 2019-24 contains 34 performance
indicators of which eight were sourced from the LGBF during 2020/21.  Of these
eight indicators, four improved and four declined. 
5. Proposals 
5.1. That the Audit and Scrutiny Committee agrees to: a) Note the Council Plan year
End Progress Report and supporting performance measures as set out at
Appendix One, Two and Three; b) Note the Council Plan Annual Performance
Report as set out in Appendix Four; and c) Note the status of the Council’s
performance indicators within the 2020-21 LGBF report at Appendix Five. 
75

Page 76

6. Implications/Socio-economic Duty 
Financial 
6.1. None 
Human Resources 
6.2. None 
Legal 
6.3. This report confirms the arrangements for the Council’s compliance with its
duties under the Local Government (Scotland) Act 1992 and the Local
Government in Scotland Act 2003 and our commitment to improving public
performance reporting. 
Equality/Socio-economic 
6.4. None 
Environmental and Sustainability 
6.5. None 
Climate Change and Carbon 
6.6. None 
Key Priorities 
6.7. This report helps to demonstrate our Council’s delivery of our strategic
priorities. 
Community Wealth Building 
6.8. There are no community wealth building implications. 
7. Consultation 
7.1. Feedback from the Executive Leadership Team (ELT) informed the content
of this report. 
Aileen Craig
Head of Service (Democratic) 
For further information please contact Isla Hardy, Team Manager (Policy and
Performance), email: IslaHardy@North-Ayrshire.gov.uk. 
Background Papers
Council Plan 2019-24
76

Page 77

Council Plan 2019-24 Progress Update
Year End 2021-22
Appendix 1
77

Page 78

Contents
Our Performance at a Glance ................................................................................... 1
Welcome ................................................................................................................. 2
Aspiring Communities .............................................................................................. 3
Inspiring Place ....................................................................................................... 11
A Council for the Future ......................................................................................... 18
Performance Summary .......................................................................................... 21
Best In Class ........................................................................................................... 33
What Our Customers Say ....................................................................................... 34
The Corporate Policy, Performance and Elections Team welcome any feedback you may have.  We strive to make
our Council and reports as accessible as possible and appreciate opportunities to discuss how this can be achieved. 
For further information please contact: 
The Corporate Policy, Performance and Elections Team
Tel: 01294 324648 
Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk 
78

Page 79

Page 1 of 34
Streetscene
Training and
Employment
Academy launched
providing opportunities for
unemployed residents and
supporting community
environmental projects
153 local groups
received funding
through participatory
budgeting
Over £7million of
our Council
budgets allocated
through
participatory
methods
1,013 young
people voted
in the Scottish
Youth
Parliamentary
Elections
600 of our young
people supported into
employment through
Kickstart
Four MSYPs 
elected to the
Scottish Youth
Parliament
136 young people
reported improved
mental health and
wellbeing outcomes
following engagement with
Community Learning and
Development activities
Money Matters
generated over
£17.5m
for our residents in
receipt of Welfare
Benefits in 2021/22
Island Plans
published
for a ten year
period
We have retrofitted
solar PV on a
total of 506
properties with a total
installed capacity of
1.65MW
We obtained a
balanced budget
for 2022/23 
Our Performance at a Glance     
79

Page 80

Page 2 of 34
Welcome
Welcome to the Year End Progress Report on our Council Plan.  This report covers the last six months of
2021/22 and provides an update on our planned activities for 2022/23.
At time of writing, we are due to leave the majority of the Covid-19 pandemic restrictions behind as we transition to
Level Zero in April 2022.  However, the efforts of everyone involved to keep our people of North Ayrshire safe and
protect our most vulnerable during the past two years will never be forgotten.  We are still very much working
alongside the pandemic, knowing that we still have a crucial job to do together with our valued partners in the
community, public, private and third sectors.  We will continue to support our residents and help establish a period
of green recovery and renewal.  We are actively contributing to the ‘Remembering Together’ Scotland’s Covid
Community Memorial Programme.  A commissioning group is in the process of being established with key partners
in the response to the pandemic to ensure a suitable memorial is created.
As the war on Ukraine develops we are proud to be able to welcome displaced Ukrainians and help them settle in
North Ayrshire until the time is right for them to return home safely.  Our Housing Teams are working tirelessly to
ensure safe accommodation is available and many of our other support services are mobilising to ensure assistance.
Our residents are at the heart of everything that we do.  The past six months have seen new initiatives brought
forward such as our ‘Community Benefits Wishlist’ - a list of priorities created by our communities that can be
fulfilled as we award procurement contracts.  We have developed our mental health support within our schools and
are in the process of improving provision in our communities.  We are planning on reintroducing OIder People’s Day
Services, learning from an approach by Alzheimer’s Scotland in Arran.  In addition, we have almost completed the
refurbishment of our early years estate.
These are challenging times, but opportunities are there to create a North Ayrshire that is ‘Fair for All’.
Our Vision
A North Ayrshire that is ‘Fair for All’
Our Mission
Working Together to improve well-being, prosperity
and equality in North Ayrshire
Our Priorities
Aspiring Communities
♦ Active and strong communities
♦ Children and young people
experience the best start in life
♦ Inclusive, growing and
enterprising local economy
♦ Residents and communities
enjoy good life-long health and
well-being
♦ Residents and communities are
safe
Inspiring Place
♦ Well connected with effective
infrastructure
♦ Homes that meet residents’
needs
♦ Vibrant, welcoming and
attractive environment
♦ A sustainable environment
A Council for the Future
♦ An accessible Council that puts
residents and communities at the
heart of what we do
♦ An efficient Council that maximises
resources and provides value for
money
♦ A valued workforce that delivers
high quality services
♦ A powerful and respected voice
80

Page 81

Page 3 of 34
Aspiring Communities
Key Activities 
Active and Strong Communities 
We are working closely with Locality Partnerships and
their working groups to consider and address local
issues focusing on the refreshed priorities.  This
includes applications for the Community Investment
Fund which was increased by a further £2million in
February (an increase of £3million this year).  Recent
approved applications include from Beith Community
Development Trust (£15,582) for a feasibility study
into developing a much-improved building to meet
the needs of the community and West Kilbride
Community Initiative Limited (£76,605 over three
years) for a Technical and Creative Training
Programme and audio visual (AV) service.
A review of Locality Partnerships is ongoing and a
session to brief new Elected Members on both
Community and Locality Planning is due to take place
in May 2022 
Our approach to Locality Charters has evolved to take
account of the learning from the pandemic and the
aspirations of both our communities and our Council. 
A Participatory Democracy Statement of Intent has
been created.  This summarises the main ways in
which our residents can take part in local governance. 
Cabinet has approved the planned community
consultation to co–design a strategy to widen
democratic participation which will explore new ways
of connecting with our people of North Ayrshire.  This
work builds on the Community Empowerment
(Scotland) Act 2015, the joint Review of Local
Governance and learning from the pandemic which
also informed the Social Renewal Advisory Board.  
Four new Members of the Scottish Youth Parliament
(MSYP) have been elected to represent North
Ayrshire.  Five candidates put forward their
manifestoes to prospective voters outlining why they
deserved to take on the important role.  In early
November, young people aged 12 -25 years across
North Ayrshire voted for the candidates they wanted
to represent them at the Scottish Youth Parliament. 
The total number of votes cast was 1,013 including 88
spoiled votes, bringing the total number of valid
votes to 925.  
In total we have allocated over £7million of our
Council budgets through participatory methods.  This
amounts to 2.32% for 2021/22, above our target of
1.1% for the year and above the Scottish Government
target of 1%.
In addition, 153 Local groups and organisations
applied for and secured community grant funding
through participatory budgeting.  We worked with 33
local residents to short list the applications.  In total,
£164,000 was allocated to local groups and
organisations.
Our Arts and Culture Participatory Budgeting recevied
27 applications with 24 successful in receiving an
award.  The Arts Team is continuing to evaluate those
who were successful last year.  
We launched our Community Planning Partnership’s
Local Outcomes Improvement Plan 2022 - 2030.  The
vision is ‘North Ayrshire – Fair for all’ with the three
priorities of ‘Wellbeing’, ‘Work’ and ‘World’.  We used
our ‘Your Voice, Your View’ online consultation
platform in addition to other means to engage with
our residents and will continue to do so to develop
our plan further.
81

Page 82

Page 4 of 34
Our Fairer Food Network has grown from eight Fairer
Food locations to 12.  New larders have opened in
Irvine, Stevenston, Saltcoats and Beith, with further
openings in Kilbirnie and Springside due in 2022.  As
the network has continued to grow, the offer to its
members has evolved.  For example, the Village
Larder at West Kilbride Community Centre has
secured funding to run a ‘Larder Lunches’ programme
from the Communities Mental Health and Wellbeing
Fund.  This will engage members in cooking classes
and social activities based around the larder.
We published the first Irvine Chit Chat magazine and
there are plans for the concept to be spread to other
localities.  Information on community services
(‘Community Books’) is provided on the Community
Planning website.  We have been developing this
approach to ensure a more comprehensive resource
for our residents and partners.  
We are welcoming the opportunity to become
involved in ‘Remembering Together’ Scotland’s Covid
Community Memorial Programme.  A commissioning
group is in the process of being established, including
colleagues from NHS Ayrshire and Arran, arts/creative
practitioners’ groups and community organisations
who were key partners in the response to the
pandemic.  In March we asked local artists, makers
and creative practitioners in all artistic disciplines to
register their interest.  
Our Streetscene Volunteering Strategy (2022 – 2026)
was approved in November, incorporating our
commitment to deliver a service that offers
volunteering opportunities across North Ayrshire
communities and to provide the relevant support for a
growing, successful and sustainable network of
community volunteers.  A series of actions have been
developed to form an action plan and ensure the
strategy is delivered successfully to maximum effect.
Children and young people experience the
best start in life
Our extensive programme to upgrade our Early Years
Estate is in its final stages with projects on Arran and
the major refurbishment of Marress House, Irvine
remaining.  Other main Learning Estate projects
continue including the replacement Moorpark Primary
School, Kilbirnie; a new primary/early years facility for
Montgomerie Park, Irvine; and a significant new
learning and community campus at North Shore
Ardrossan.
We have continued to make good progress in our
efforts to reduce the poverty related attainment gap. 
During this period, we have progressed with planning
for the publication of a revised framework around the
Scottish Attainment Challenge which will support
recovery and accelerate progress.  This has included
work to explore how we will use our reducing funding
allocation to support learners and prioritise the
supports making greatest impact.
We successfully rolled out universal free school meals
to Primary Five children in January 2022.  The further
rollout to Primary Six and Seven children has been
delayed nationally, but we will continue to support
this when a new date is confirmed.  Our Facilities
Management, Property Management and Investment
team (PMI) and Education Service are working closely
to complete work within our kitchens during school
holiday periods where possible to minimise
disruption.  This work will build capacity in our
kitchens to ensure we can provide for the anticipated
increase in pupils accessing school meals when the
free access is fully rolled out.  
We are working on a pilot programme to develop the
Outdoor Strategy.  This work is being supported by
the Scottish Government and Children and Young
People's Improvement Collaborative.  A training
programme has also been developed to support
practitioners’ continued professional development in
this area.  Outdoor environments continue to be
developed in line with the blueprint for Early Learning
Centre (ELC) design and include collaboration with the
Woodland Trust and tree planting programme.  This
work will continue to be evaluated and refined to aid
the completion of the Outdoor Strategy in 2022.  
82

Page 83

Page 5 of 34
1,022 Chromebooks have recently been delivered to
school for Primary Five and S2 pupils in receipt of free
school meals or clothing grants.  The remaining 250
Ipads from last year’s order of 600 have been
distributed to eligible Primary Two pupils.  As this is a
rolling project, more devices will be purchased as
budget becomes available to ensure all our children
and young people have vital access to digital
technology.
A pilot programme was created for a community swap
shop in Garnock Valley to address poverty and
inequality.  Run by our young people it is working in
partnership with our Education Service and parents to
establish an exchange of school items for young
people from the Garnock Valley locality.  Plans are in
place to fund further developments including utilities
to wash clothes.  This will be rolled out to other
localities with our young people taking the lead.  
Three of our Youth Workers have been shortlisted in
the National Youth Work Awards in categories of
‘Digital and Stem’ , ‘Volunteer Youth Worker’ and
‘Lifetime Achievement Award – Fellowship of
YouthLink Scotland’.  
Mental Health and Wellbeing in Schools
We have developed a range of materials and
approaches to support teams, parent, carers and
children to manage anxiety. These have been shared
with a range of stakeholders to help raise awareness
of the resources and approaches. There are also
further awareness raising and employee development
sessions organised, with all resources available on
both our Glow Blog (secure internet space for our
Education teams and pupils) and the Education
Psychology Service website. 
‘Let’s Introduce Anxiety Management’ (LIAM)
continues to be developed with training now offered
to Area Inclusion workers.  We continue to publish
regular news bulletins and have updated our
employee Glow blog to share and signpost the most
up to date resources and approaches.  We are tying
this in with the recently published Whole System
Approach to Mental Health and Wellbeing and
professional learning resource.  
We continue to offer a counselling and wellbeing
service in Primary schools demonstrating positive
outcomes for our children and young people.  
We evaluated the first year of Community Mental
Health and Wellbeing (CMHWB) supports and services
framework and plan to continue with those most
effective for our children and young people.  These
include Play Therapy, Aberlour and our own Family
Centred Wellbeing support service.  We have invested
additional funding for Classroom Assistants to support
wellbeing and have implemented both Nurturing
North Ayrshire Recovery and Building on Positive
Relationships approaches to support our young
people.
North Ayrshire’s Family Centred Wellbeing team now
has five workers in place and are using a range of
approaches such as signposting, Video Interaction
Guidance (VIG), and support with routines and
boundaries in two of our localities.  An Education
Psychologist is working in partnership to support their
understanding of additional support needs.  
Several of our young people have been trained in Peer
Mentoring and will be initiating locality-based drop-in
services over the coming term.
The restrictions which limited the presence of our
Family Learning Team in schools are easing.  This has
increased the number of schools requesting to have
their Family Learning Worker based in school, thus
helping to re-establish relationships with school
teams, children and families.  718 families have
attended a variety of programmes since the beginning
of the academic year, with a large proportion being in-
person delivery.
Inclusive, growing and enterprising economy
Our Protective Services Team continue to support
businesses and our communities to beyond level zero
of the national Covid-19 restriction levels.  
The Ayrshire Regional Skills Investment Plan has been
developed for consideration at the Ayrshire Economic
Joint Committee in June for approval and
implementation.  The plan will ensure that
communities and businesses have the opportunity to
engage with and benefit from investments delivered
through the Ayrshire Growth Deal.
The Integrated Joint Boards of East, South and North
Ayrshire Councils signed the Community Wealth
Building Anchor Charter.  The Anchor Charter mission
is: “To commit to long-term collaboration between
Ayrshire Anchor Institutions, supporting shared
Community Wealth Building (CWB) goals to improve
83

Page 84

Page 6 of 34
collective wellbeing and create a strong, resilient, and
inclusive local and regional economy.”
We continue to offer employability support, with our
Equal employability programme supporting 135
residents with disabilities during the past year.
Procurement and Community Benefits
Procuring goods and services locally is a key pillar of
our Community Wealth Building Strategy, supporting
local businesses and communities.  
As part of Challenge Poverty Week in October we
launched a “Community Benefits Wishlist” for
potential suppliers.  This ensures that when contracts
are awarded, additional benefits within them (which
can range from training through to assistance in
community projects) are identified by and directly
relevant to the needs of our communities.  This was
formally included in our Community Benefits Strategy
launched in December 2021.
At year end, 44 community groups had submitted a
combined total of 94 wishes for the list.  Fourteen
wishes have been fully delivered, with a further seven
in progress and five more in discussion. 
We have been proactively promoting Community
Wealth Building through procurement activities.  This
includes public library sessions with businesses,
coaching, 1-2-1 meetings with businesses and linking
opportunities with businesses. 
We have supported 130 local businesses on 249
occasions during the past six months, 840 businesses
in total during the year.  We provided support on
digital initiatives, energy including transitioning to
more environmental ways of working, as well as
advice on procurement.  Our Business Development
team have worked closely with our Corporate
Procurement team to adapt the process for procuring
lower value goods and services (known as the ‘Quick
Quote’ process) to make it more accessible for local
businesses. Overall, this support will help strengthen
local supply chains.
We have helped 600 young people progress to
employment through our Kickstart initiative, with our
Council’s Gateway creating 300 of these positions.
Community Wealth Building Overview
Our Community Wealth Building Strategy Annual Report 2020/21 was launched in October 2021 during Challenge
Poverty Week.  All thirteen team members are now in post across the three Ayrshire councils.  Key achievements
include:
216 companies received
support
50 enterprises received
financial support
37 enterprises less than a
year old supported
47 local businesses
registered on Public
Contracts Scotland (our
procurement portal)
63 businesses attended
121 procurement support
sessions
12 businesses attended
one to many ‘fair work’
workshops
4 referrals to Fair Work
Ayrshire programme
6 businesses supported
with employee ownership /
cooperative status
Targets for supported
businesses and 1-2-1
procurement support
exceeded in the first year
Though Fair Work Ayrshire Referrals are currently 50% of target, this is expected to increase following the successful
recruitment of the team and the easing of Covid-19 restrictions.  The initial recruitment challenges have resulted in an
underspend in year one of 50% which will be aligned to increased programme activity going forward in order to
deliver better outcomes.
84

Page 85

Page 7 of 34
Residents and communities, enjoy good, life-
long health and wellbeing
Planning for the for remobilisation of Older People's
Day Services continues.  The service has been
engaging with Alzheimer’s Scotland who re-opened its
Day Service in Ardrossan, on a greatly reduced
capacity basis, in late 2021.  The Health and Social
Care Partnership has been working with colleagues
from Alzheimer’s Scotland to build capacity based on
prioritising those on the waiting list for Day Services.
Additional winter investment has been confirmed and
provides an opportunity to continue to grow our in-
house Care at Home workforce to address unmet
need in our communities.  Addressing the full needs of
our residents is dependent on successful recruitment
which continues to be a challenge. 
We are supporting KA Leisure as it builds its
membership and explores a wider role as a
community health and wellbeing organisation. 
Attendances (excluding pools) remain at 16% of pre
Covid-19 levels, however they are increasing steadily,
from 41,083 in Quarter 1 to 104,166 in Quarter 4. 
Recovery and renewal plans are progressing in order
to return to a positive financial position.
Our Arts Team has been successful in gaining funding
for a digital storytelling project. The project will raise
awareness relating to the lives of people with learning
disabilities, highlight their successes and the
contribution they make within the community.  Their
stories will be captured as a short film in their own
way and in their own voice, which will then form the
core of a touring exhibition.     
We have launched a survey to understand the views
of those who may require access to free period
products across a range of sites in North Ayrshire. 
Schools, community centres and halls, libraries,
community hubs, community larders and public
offices have period products available for use by
members of the public, staff, pupils and visitors.  We
want to identify any improvements which can be
made.
Our Ayrshire Shared British Sign Language (BSL) Local
Plan 2018 – 2024 Mid Term Report noted good
progress including:  
♦ Implementation of training, including basic online
awareness, basic introductory face to face courses
and longer–term courses in BSL; as well as
promotion of contact Scotland–BSL Support
Service.
♦ Development of BSL information on public facing
websites and adoption of Video Remote
Interpreting (VRI Technology).  Our Sensory
Impairment Team were provided with
smartphones during the first Covid-19 lockdown,
to allow them to communicate more effectively
with the BSL/Deaf Communities.
♦ Engagement with the BSL Community, including
through the Ayrshire Deaf Club and work within
schools and post–educational settings.
Financial Support
The Better Off Hub currently delivers vital advice
services in a new holistic way, focussed on the whole
person with an objective to resolve underlying issues
and reduce future demand on services.  The proposals
align with Community Wealth Building ambitions and
support our economic recovery.  A total of 183 people
from the Three Towns engaged with Better Off during
2021-22.  Overall, 64 children within supported
families benefitted from the service.  To combat
pressures identified in the first half of the year, new
referral pathways were established and vacancies
were filled in October 2021.  
Our Money Matters Team generated over £17.5m in
financial gains for our residents in receipt of Welfare
Benefits during the year. The service received 4,432
enquires via their Advice Line. This included referrals
from the Health and Social Care Partnership (HSCP),
NHS, Council employees and our website.  We ensure
our most vulnerable residents have support to check
their entitlements and ensure they are receiving their
legal benefit entitlement. 
Whilst the number of benefit appeals continue to
drop throughout the UK, the Money Matters Team
continues to have a high success rate, with 78% of
appeals successful for service users.  The service also
advised/assisted 87 families to claim Scottish Child
Payment, with 75 awards made this year.  This
resulted in financial gains of over £80k to families with
children under six years old (£80,819.58).
Mental Health and Wellbeing Support
Our Community Mental Health Service continues to
provide critical, essential and routine care.  Due to
changes in restrictions, care has been delivered,
where possible, in different ways; with increased use
of telephone consultations and digital opportunities. 
Required face to face consultations continue but with
strict infection control measures in place.  Employee
absence in addition to increased demand for services
has resulted in some delays specifically within brief
interventions and psychological therapies.
85

Page 86

Page 8 of 34
As part of the new ‘Mental Health in Primary Care’
plan, we have submitted a pan Ayrshire first year plan
to the Scottish Government to increase the number of
Mental Health Practitioners (MHP) across Ayrshire.  If
successful, this will mean every GP practice in Ayrshire
will have MHP cover.
136 young people reported improved mental health
and wellbeing outcomes following engagement in
Community Learning and Development activity
including: youth participation work such as youth
forums; mental health and wellbeing courses and
activities; employability one to one sessions as well as
groupwork; and issue-based youth work.
We launched the ‘Ground Force’ Project in Eglinton
Community Gardens.  A tree nursery project for
serving and ex-service personnel of the Armed Forces
and their families.  The project aims to provide
practical, hands-on opportunities involving a variety of
outdoor activities, all of which can contribute to
positive health and wellbeing and a sense of
community.
Organisational change work within the HSCP is
ongoing with the team coordinator for Child and
Adolescent Mental Health Service (CAMHS)
Neurodevelopmental team in a place and a preferred
candidate for the Service Manager for CAMHS
Neurodevelopmental Team identified.  CAMHS
administration management support is now provided
by the North Ayrshire HSCP. 
Residents and communities are safe
In line with the national Equally Safe strategy, the
North Ayrshire Violence Against Women Partnership
developed a robust programme delivered throughout
the 16 Days of Activism which ran from the 25th of
November until the 10th of December.  This year’s
theme was ‘young people and healthy relationships’,
targeting schools in particular.  During the 16 Days of
Activism, a variety of activities took place such as the
launch of ‘Ask for Angela’ safety initiative, extensive
communications programme, Ayrshire Adult Support
and Protection Event and launch of our Domestic
Abuse Policy for Tenants and Residents. 
The North Ayrshire Domestic Abuse Policy sets out
our commitment to support tenants and residents
affected by domestic abuse and recognises it is
unacceptable behaviour which will not be tolerated. 
The policy is aligned to the Chartered Institute of
Housing’s ‘Make a Stand campaign,’ and has been
developed by an inter-agency group comprising of our
own Housing Services, Cunninghame Housing
Association, Riverside Scotland, our own Tenant
Participation Team and North Ayrshire Women’s Aid. 
The policy sets out to provide help to anyone in North
Ayrshire who is at risk of, or is experiencing, domestic
abuse and provides support to those who are worried
about the wellbeing of another individual.  
An agreement to procure quad bikes to enhance
community safety, reduce antisocial behaviour, fly
tipping and graffiti through a joint initiative with
Police Scotland.  The bikes will allow the Police access
to particularly rural areas more quickly to provide an
enhanced community safety response. 
We have embarked on a project with Health
Improvement Scotland aimed at Reducing Harm and
Improving Care for people experiencing homelessness
who require alcohol and drug services within North
Ayrshire.  This is to allow us to identify and
understand where prevention activities could
intervene to reduce the risk of crisis and subsequently
homelessness.  
Our inter-agency Rapid Rehousing Transition Plan
2019-24 details our ambitious targets for allocations
to homeless households over five years.  We
undertook a pilot to allocate 100% lets to homeless
households during the third quarter of 2020/2021. 
We prioritised: households with children, recognising
the impact of homelessness on adverse childhood
trauma; households in employment, given the cost of
temporary accommodation and the impact it can have
on employment and affordability; and women
experiencing domestic violence, to reduce the risk of
further trauma.  The percentage of households
homeless for longer than six months is currently 30%
at year end, compared to 76% prior to the pandemic.
Housing First provides settled housing as a first
response for our residents who are experiencing
homelessness as well as additional challenges.  As well
as providing settled accommodation, we also provide
personalised support.  We have successfully created
22 Housing First tenancies during Year Three bringing
the total to 62 exceeding our annual target by 10%. 
We remain on target to settle 100 people over five
years (by 31st March 2024) with support being
provided through our Housing First model.  In
addition, we are currently supporting a further 11
residents to obtain sustainable accommodation.  
Our specialist HSCP Addiction and Mental Health
posts are now established within the Housing First
Team.  Our Peer Support Service for Housing First
Clients commenced in December 2021.  To date we
have completed 15 referrals to this service.  
86

Page 87

Page 9 of 34
Case Study – The North Ayrshire Fairer Food Network – Taking a moment to learn and improve
The North Ayrshire Fairer Food Network is a community pantry/larder scheme which provides food for its
members.  For a small fee, individuals are allowed to pick produce in a shop environment.  It is a lifeline for many
of our families, especially due to the current cost of living crisis, and grew considerably during 2021.  As at
February, 11 pantry/larder locations were operating in North Ayrshire (12 at year end).
While a few of the larders have support from paid staff (for example The Wee Shoap or Choices), most of them
rely solely on volunteers.  In addition, different membership and pricing structures have evolved, impacting the
need for funding that each location has to consider.  January and February was a good time to review progress,
identify opportunities for collaboration and share good practice.
The Fair for All Development Officer and Community Economic Development Officer developed a meeting
template in advance of visiting each site.  This allowed larder teams consider their priorities and include the
feedback of other people working on the project who weren’t able to attend the meeting (e.g. treasurers and
other volunteers).
Meeting with those running the larders in person on location (where possible) also made a big difference in
terms of getting a sense of scale, the offer, how things work and the experience in each environment.  In
addition to the official meetings, the anecdotal information shared during the walkarounds in the larder was
extremely valuable in identifying the scale of issues and opportunities.
The most common concerns for the larder teams are funding and sustainability, especially rising food costs.  In
the North Ayrshire models, the food is bought rather than donated, so cost is vitally important.  The motivation
to shop locally can be difficult to implement when national supermarket value ranges can drastically undercut
prices even of wholesalers.  This poses a challenge in a Community Wealth Building context.  However, there is a
desire to pursue local spend with independent businesses where it’s feasible to do so as well as recognition of
the high-quality produce offered by our local butchers, greengrocers and other suppliers.
Another concern is applying for funding.  While some locations have employees or volunteers with a lot of
funding experience, this is not the case across the network.
As a result, we have developed a way forward:
♦ To address rising food costs and provide better equity of access to fresh food across the network, the
network will pilot a group buying model for fresh fruit and vegetables.
♦ The support available will be broadened and aligned to a more preventative rather than reactive
approach to food insecurity – building on work such as West Kilbride’s ‘Larder Lunches’ programme,
funded through the Communities Mental Health and Wellbeing Fund.
♦ We will work to build confidence in applying for and reporting on funding.  We will support this on an
ongoing basis both through specific training and by adapting processes for disbursing funds internally,
similar to how we distributed and managed Scottish Government Winter Hardship Funding using a
straightforward online application and follow up discussions.
♦ We will facilitate face-to-face meetings and networking opportunities to build relationships and support
mechanisms.
♦ We will improve communication - feeding back activities that are working in other places is important,
both to share good news and to reduce the chance of others duplicating efforts.
There is a huge level of community assets within the network in terms of experience, networks, ideas and
background; bringing that to the fore to ensure everyone is benefitting from shared knowledge and leadership
will be really important to the longevity of the network as a whole.
87

Page 88

Page 10 of 34
Aspiring Communities 
Areas of Focus 
Over the next six months we will focus on the
following areas:
Active and Strong Communities
♦ We will work to welcome and resettle Ukrainian
refugees. 
♦ We will further develop our participation strategy
and locality planning approach.
♦ We will continue to develop our community hub
approach to serving communities.
♦ We will further develop the community services
information available on our Community Planning
website to make it as user friendly as possible. 
Children and young people experience the
best start in life
♦ We will work with NHSAAA and other Community
Planning Partners to develop our Child Poverty
Action Plan for 2022-23, taking account of the
Scottish Child Poverty Delivery Plan 2022-26 ‘Best
Start, Bright Futures’  published in March.
♦ We will develop our approach to the refreshed
Scottish Attainment Challenge (SAC) and Pupil
Equity Fund (PEF).
♦ We will continue our investment in our school
kitchens to be prepared for the rollout of
universal free school meals to Primary Six and
Seven children when new dates are confirmed.
♦ We will complete our review of Additional
Support for Learning.
♦ We will fulfil our Outdoor Strategy, supporting our
children and young people to learn in the natural
environment.  This work is being supported by the
Scottish Government and Children and Young
People's Improvement Collaborative. 
Inclusive, growing and enterprising economy
♦ The Ayrshire Regional Skills Investment Plan will
be presented to the Ayrshire Joint Committee in
June for approval and implementation.  The plan
will ensure that communities and businesses have
the opportunity to engage with and benefit from
investments delivered through the Ayrshire
Growth Deal. 
♦ We will continue to develop our Community
Wealth Building approach including implementing
a local only Quick Quotes process when procuring
lower value goods and services as well as works
up to £500k.  Quick Quote is a quicker, less
onerous procurement process than a tender so
should encourage more local businesses to bid. 
Residents and communities, enjoy good, life-
long health and wellbeing
♦ We will review results of our survey on period
poverty and the provision of period products.
♦ We will recruit permanent employees to our Care
at Home workforce to address unmet need in the
community in North Ayrshire.
♦ We will await the outcome of first year plan to
increase the numbers of Mental Health
Practitioners across Ayrshire from the Scottish
Government (due May 2022).  If successful, we
will begin recruitment of practitioners.
♦ We will progress the KA Community Health and
Wellbeing approach.
♦ We will continue our Active Schools focus on
inclusion. 
Residents and communities are safe
♦ We will continue to learn from experience and
build our North Ayrshire Food Network, especially
due to potential increased demand over the
coming months.
♦ We will continue to support businesses to keep
our residents and visitors safe as we transition to
level zero Covid-19 restrictions in April 2022.  
88

Page 89

Page 11 of 34
Inspiring Place
Key Activities 
Well connected with effective infrastructure
Ayrshire Growth Deal Infrastructure
Our Great Harbour project has passed the first project
stage.  Detailed designs are being developed following
the appointment of a masterplan design team in
October.  A public engagement strategy has been
developed and Stakeholder Reference Group has been
set up to guide the consultation process and
methodology.  The first phase of public consultation,
which focussed on the Coastal Hub as a first phase of
developments, was completed at the end of March. 
Procurement has commenced for various
developments, namely the design and build of the
play park as well as the Harbourmaster’s House
restorations - with associated public space to the front
and car park to the rear.  
Ardrossan Harbour – Agreement is in place to develop
a tender package for the project incorporating the
marine and landside works.  To inform the tender
package, consultation on the landside works was
undertaken in February/March. 
Ardrossan Marina – Heads of Terms for a lease and
fundings agreement with the operator Clyde Marine
was signed in March.  Appointment of a design team
to develop the detailed design will take place in April. 
A funding package for works continues to be
developed with recent approval of £800k from North
Ayrshire Ventures Trust (NAVT), the submission of an
Outline Business Case to Scottish Government for the
Ayrshire Growth Deal funding in March and the
submission of an application to the Crown Estate
Scotland Boat Based Tourism Fund for £750k also in
March.
Ardrossan North Shore – We issued the enabling
works tender package in November with tender
responses received March 2022.  These tender
responses are currently being evaluated.  Planning
consent for the advance works package was secured
in March.
Hunterston - Work is ongoing to unlock opportunities
for Hunterston, its assets and investments, to
maximise its impact across energy, circular
(sustainable) economy and blue (marine) economy
sectors.  This has secured leading expertise through
universities to assist in developing a strategic proposal
for Hunterston.  This has been presented to partners
and approved by Cabinet and will position Hunterston
within a wider approach to unlocking blue economy
opportunities.
International Marine Science and Environmental
Centre (IMSE) – Extensive work has been progressed
to underpin the strategic case for both IMSE and
Hunterston, with both aligning with a particular
nationally significant blue (marine) economy and
energy opportunity.  This has included development
of an informal academic partnership, research,
analysis and industry engagement and formation of
partnerships related to project development and
delivery for Hunterston.  We are working towards
formalising academic partnerships to progress both
IMSE and Hunterston projects.  We have signed a
Memorandum of Understanding partnership with the
University of Stirling as lead academic partner.  The
organisations are working to identify a business case
development route.
Marine Tourism - Our development of marine tourism
project looks at marina facilities at Ardrossan, Arran
and Cumbrae.  The Programme Business Case was
submitted in March to enable the flow of Outline
Business cases for each of the three locations.  The
Ardrossan Outline Business Case was also submitted
in March as the first place–based project of this
programme.  Viability studies and scoping is being
undertaken for Arran and Cumbrae marinas. 
Community steering groups have been established on
both islands and are engaged with us as well as
contractors to develop marina projects.
I3 Digital Innovation Campus
We signed a collaboration Agreement for Phase One
of the Digital Processing Manufacturing Centre
(DPMC) on 28 March 2022.  Additional funding has
been agreed between partners and Scottish
Enterprise to cover the expected Phase One shortfall
for refurbishment works.  A grant offer from Scottish
Enterprise was received on 29 March.  
We will advertise our tender for refurbishment works
in May.  Discussions with the Project Management
Office and UK Government will take place around our
approach to completing the Outline / Programme
Business Case stage.  We expect the Phase One facility
to be launched in October 2022.
Likely cost increases for the Phase One Flexible
Business Space unit have been highlighted to the
Scottish Government.  We are seeking support to
proceed with Phase One which is now progressing
towards tender publication and are awaiting a revised
89

Page 90

Page 12 of 34
valuation to enable progress of land purchase.  The
Full Business Case is likely to be reported to the Joint
Committee from September.  We are seeking to
include this work as part of a Levelling Up Two funding
submission in July.
External Funding and Initiatives
Our Active Travel and Transport Team has secured
funding from a range of sources for the continued
implementation of active travel and transport
priorities across North Ayrshire.  This includes: 
♦ Brodick to Corrie Cycle Path - £300k for detailed
design and construction.
♦ Bus Corridor Improvements - £200k for
improvements to bus stop infrastructure.
♦ Bus Route Congestion Reduction Measures -
£100k for the continued implementation of an
Urban Traffic Control system to support bus
priority.
♦ Irvine Cycle Friendly Town - £250k for continued
implementation of the Study recommendations.
♦ Bus Partnership Fund - £200k for extension of the
Bus Routes Congestion project and to investigate
the potential for bus lane extension at Pennyburn
Roundabout.
♦ Travel Smart - £126k for the continued
implementation of Trinity Active Travel Hub
activities and changing the travel behaviour of
residents.
♦ B714 active travel links - £100k for design
development. 
£23.7m was secured for the B714 Upgrade from the
UK Government’s Levelling Up Fund in October 2021. 
The acceptance of the funding and commencement of
the project was approved by Cabinet in January.  A
tender exercise was undertaken to appoint the
designer for the route and to support the ongoing
development of the Business Case.  An initial
development funding award of £1.212m has been
approved to support this stage.  The full funding for
the project will be confirmed when the Final Business
Case is approved by the Department for Transport. 
The Levelling Up Fund requires the approval of a Full
Business Case to allow the project to formally
commence. 
Our funding application to the UK Government's
Community Renewal Fund for the Island Connectivity
Study as part of the Green Islands Programme was
successful, with the overall award being £456,617. 
We are now considering the potential for electric
vehicle infrastructure, active travel hub provision and
the development of a ‘Mobility as a Service’ project to
support sustainable travel on the Islands.  The report
will be complete in June 2022.
Cabinet approved the expenditure of the £0.259m
allocation under the 2021/22 Islands Infrastructure
Fund to: 
♦ Upgrade of the car park at the Mountain Rescue
Centre in Brodick on the Isle of Arran. 
♦ Upgrade of a series of lay-bys at strategic
locations on the Isle of Cumbrae.
♦ Implement a series of recommendations
identified by the Islands Connectivity Study. 
As part of our Electric Vehicle Strategy 2021-25 we
have implemented a new charging tariff to help
improve turnover and availability at our charging
points and help meet the costs of public charging
provision as electric vehicles become more widely
adopted.  The Local Authority Investment Programme
(LAIP) from Transport Scotland, provides capital
grants for the installation of electric vehicle charge
points.  We were awarded £80k for this year, with
almost £70k committed to sites in Skelmorlie and
Arran so far.
In addition, we secured £50k of funding from the
Scottish Futures Trust and Transport Scotland for the
development of a business case for alternative
delivery models of electric vehicle charging
infrastructure.
Phase One of the implementation of the new highway
infrastructure asset management system commenced
on 1 March 2022, this will bring improvements for
Roads inspectors and technical officers particularly
when working remotely.  Phase Two will introduce
mobile working for operational employees which will
ensure a more effective and efficient means of
managing reactive and routine works.
The implementation process for public Wi–Fi rollout is
almost complete with all existing BT Wi–Fi sites
upgraded and two of the seven new sites live, with
the others expected to be complete in April.
Garnock Community and Visitor Hub - Construction
commenced in June 2021 and is on target for
completion in August 2022.  Community and
stakeholder consultation is ongoing and designs for
the Parkland are being finalised through
consultations, taking account of feedback from local
communities.  A final newsletter will be circulated
90

Page 91

Page 13 of 34
across the Garnock Valley in Quarter One 2022/23 to
update on how feedback has shaped the proposals. In
addition, a procurement exercise has been
undertaken for construction of the proposed 5km
leisure route.  It is anticipated that this work will
commence in Spring 2022.
The Green Action Trust is also preparing woodland
planting proposals for the Lochshore parkland.  An
application for £15m was submitted to the UK
Government’s Levelling Up Fund to advance the
delivery of this element project as part of the
Gateway to the West Coast and Clyde Island Project. 
The bid was unsuccessful as the fund was
oversubscribed.  However, Cabinet approval was
secured for its resubmission and a revised bid is being
developed for submission to Round Two of the fund
for the July 2022 deadline.
Homes and Houses That Meet our Residents’
Needs
The Strategic Housing Investment Programme (SHIP)
2022–2027 was approved by Cabinet in November.  A
total of 681 new Council homes (including a small
number of staff accommodation units in Sheltered
Housing complexes units) have been completed since
our development programme commenced.  We have
been monitoring the time and financial impacts of
both Covid-19 and Brexit due to labour and material
shortages and an increase in material costs.
By locality, our development programme is as follows:
Irvine and Kilwinning – We completed the 33 homes
at Dalrymple Gardens, Irvine on 25 October 2021 and
completed the Towerlands, Irvine development on 15
March 2022 with all 50 homes occupied.  Works are
currently on site for 71 homes at Irvine Harbourside
and 79 homes at St Michael’s Wynd in Kilwinning (24
of these had been completed at the end of March
2022). 
Garnock Valley - The former Garnock Academy site
has been increased to 50 homes to provide
replacement homes for the Garnock Valley
regeneration projects at Laburnum Avenue, Beith and
Newhouse Drive, Kilbirnie.  The Laburnum Avenue site
can deliver approximately six new homes whilst the
Newhouse Drive site can accommodate around seven
new homes.
Three Towns and Arran – We completed the 14
homes Springvale development in Saltcoats in
October.  85 new homes are planned for the Three
Towns area at the former James Reid School,
Saltcoats, Afton and Caley Court in Stevenston and the
former James McFarlane school in Ardrossan.  Works
are currently underway on site to develop the 15
homes and employee base at Caley Court, Stevenston.
34 new homes are being developed at Brathwic
Terrace, Arran.  Works are currently on site with 19
homes completed at the end of March.
North Coast and Cumbrae - The 123 units at Flatt
Road were completed on 16 December 2021.  A
further 41 new homes are being developed at St.
91

Page 92

Page 14 of 34
Colm’s Place, Largs and at the site of the former Largs
Police Station.  Works have commenced on site to
develop a new sheltered housing complex at St.
Colm’s Place, Largs.
We committed to buying back four empty homes in
2021/22 to bring them back into the affordable
housing supply.  We purchased three properties
across Irvine, Dreghorn and Dalry.  Though we
identified a fourth property in Kilbirnie, the owner did
not wish to proceed. 
Selective work has commenced on the former King’s
Arms building in Irvine, ahead of the planned
refurbishment into six amenity flats to support our
residents with an accessible housing need.  
----
We have completely reconfigured tenant participation
over the past 20 months due to the impact of Covid-
19. Our employees and tenants are continuing to
support and embrace new methods such as e-
participation and engagement methods.  We were
able to carry out our annual rent consultation
between November and December, this was the
second fully digital consultation we have conducted
and saw a 5% increase in responses.
A new approach for Tenant Led Budgeting has been
presented to the North Ayrshire Network and
approved.  
Vibrant, welcoming and attractive
environment
The installation of new play equipment and street
furniture as part of the £900,000 public realm
investment is underway with the projects currently in
the tendering stage.  In addition, new higher capacity
litter bins have been installed in almost all coastal
areas. 
The first round of the Repurposing Property Grant
Fund of £200k was launched to support landowners
and communities to bring vacant land and properties
back into positive use.  This provides funding of up to
£25k for building and site studies, market advice and
feasibility studies to identify potential options for sites
and assess their viability.  
As part of our Streetscene Volunteering Strategy
(2022 – 2026), we are introducing a North Ayrshire
‘Adopt a Spot’ initiative.  This is a new approach to
provide members of the community, local businesses
and schools with an opportunity and support to
voluntarily litter pick in an area of their choice within
North Ayrshire.
The 10-year Island Plans and Annual Action Plans for
Arran and Cumbrae were approved by Cabinet and
published in February 2022.  These documents have
been developed with local communities, ensuring that
island communities, stakeholders and partners are
fully engaged and involved in the development phase. 
Work is now underway to develop governance models
to oversee the implementation of the plans
Our Planning Service is reviewing the recent Open
Space Audit.  Once finalised, the Open Space audit
report, maps and GIS data will be used to inform the
review and update of the Open Space Strategy 2016 –
2026 and  accompanying Open Space Asset
Management Plan, planned for completion by
Spring/Summer 2022.
Funding was secured from the UK Government
Community Renewal Fund (CRF) to pilot the Place
Framework approach in October 2021.  This has been
aligned with funding from the Place Based Investment
Programme (PBIP) to support the development of the
pilot project.  Initial engagement with Elected
Members and key stakeholders has been undertaken. 
Wider stakeholder and community engagement is
planned for April and May 2022.  The project needs to
be complete by June 2022 in line with the CRF
requirements.
Our first Making Waves Festival is due to take place
during 23 and 24 July 2022 at Irvine Harbourside.  It
will provide top quality outdoor concerts as well as
activities on and off of the water for our residents and
visitors to enjoy.  It is linked to Ayrshire Growth Deal
92

Page 93

Page 15 of 34
tourism projects such as Marine Tourism and the
Great Harbour.
To ensure our residents benefit from tourism, we
published our Visitor Management Plan in February
which will support the positive economic impact of
tourism in North Ayrshire.  Prior to the pandemic, in
the 2019 calendar year there were 3.2m visitor
overnight stays, generating £211.8m for the North
Ayrshire economy.  With domestic tourism expected
to remain popular, this will allow North Ayrshire to
positively benefit from those visiting our outstanding
area.
A sustainable environment
Waste Reduction
Significant work has taken place to reduce the impacts
of waste on our environment as part of our response
to the Climate Emergency. Our Waste Service has
been collaborating on a feasibility study to outline
options and recommendations for the potential scope
of a ‘remakery’ project to support an increase in re-
use and repair, which also aligns to the principles of
Community Wealth Building, the Zero Waste Strategy
and contributes to the development of a circular
economy.  The draft feasibility report is currently
being finalised.  
We have issued tenders to improve signage and waste
separation within our household waste recycling
centres, including improving opportunities for reusing
mattresses and more furniture through our bulky
waste reuse partner.  New mobile technology is being
progressed for our refuse collection vehicles.  Both
projects are being funded through successful bids to
the Recycling Improvement Fund and will be
implemented in Spring 2022, subject to supplier
delivery times.  The total fund value will be confirmed
after this procurement stage.
Work is continuing to progress the Single Use Plastics
Waste Prevention Action Plan.  A communication plan
linking to our Environmental Sustainability and
Climate Change Strategy has been developed to
encourage our employees and residents to be 'Plastic
Smart'.  
Our Waste Service is engaging with Zero Waste
Scotland, the Renewable Energy Association and our
Council’s waste processing contractors to develop
clear guidance for residents to advise which
compostable items are suitable for recycling via our
organic recycling collection service.  
Energy Provision
The district heating installation at Flatt Road, Largs
was completed on 29th November 2021.  The Flatt
Road District heating network also has sufficient spare
capacity to provide heat to properties in the proposed
new development on the site of the former St Mary’s
Primary School.
As at the end of March we have completed solar panel
installations (solar PV) for 216 homes.  The project is
now complete and including the properties in phase
one, we have now retrofitted solar PV on a total of
506 homes with a total installed capacity of 1.65MW.
Community Composting on Arran:  Waste Resources
and Economic Development are supporting the Third
Sector to try and establish a green waste composting
project as part of a pilot Public Social Partnership on
Arran.  We have provided funding to a third sector
partner to conduct a feasibility study on the viability
of the project.  
A pilot recycling system is ongoing within seven
participating schools, which aligns their collection
system in the school with the system that is currently
in place for household collections.  Monitoring is
ongoing regarding the quality of the recyclate, bin
capacity and the collection frequency, to ensure these
are sufficient for each school’s needs.  A report will be
prepared on the pilot findings, with recommendations
relating to any potential scope for the extension of
the system.  
93

Page 94

Page 16 of 34
Case Study –Ukrainian Resettlement
Programme 
We are committed to welcoming people displaced by
the war in Ukraine to North Ayrshire and ensuring
they have safe homes and support networks.  The
scale of the Ukrainian resettlement programme is
much larger than other programmes and we are
determined to support vulnerable families fleeing the
conflict.  
We are working alongside the UK and Scottish
Governments, COSLA and our Community Planning
Partners to identify safe and comfortable homes and
ensure that individuals and families have adequate
support, tailored to their individual needs.  This has
included integrated support from our Refugee Task
Force, which is made up of a number of internal and
external Services, including Housing, Health and Social
Care, Protective Services, Police Scotland, Scottish Fire
and Rescue, DWP, Education, Connected
Communities, Ayrshire College, Employability, NHS,
and the Third Sector.  
An initial 60 social rented properties have been
identified for use under the Scottish Super Sponsor
scheme – 54 Council properties and six from local
Housing Associations.  These consist of mainstream,
sheltered and amenity housing ranging from one
bedroom accommodation to four.
Additionally, we have carried out sponsor disclosure
checks, property checks and safeguarding and support
home visits for private housing under the UK
Government’s Homes for Ukraine scheme.  A £10,500
per person tariff has been introduced by the
Government to cover education, service referrals,
support for finding employment and registering for
benefits, homelessness assistance, community
integration and temporary subsistence.  
Through the Homes for Ukraine scheme, we have
been advised of 25 matched sponsors in North
Ayrshire, with 13 of the 25 households having
already arrived.  Safeguarding and support visits
have been made and an emergency payment of
£200 has been made to each person.  All disclosure,
environmental and property checks have also been
completed.  
As part of the wider Scottish Super Sponsor Scheme,
we have prioritised 67 private householders from an
initial list of 204 who expressed an interest in
providing accommodation in North Ayrshire.  We have
contacted all 67 potential hosts to let them know that
following checks, their details will be passed to COSLA
and the Scottish Government for matching to
Ukrainians in need of accommodation and assistance. 
We have currently prioritised properties based on
those who have offered either self-contained
accommodation or property with exclusive use of a
bathroom.  We have also prioritised mainland
properties due to recognised housing and other
support pressures within our island communities.
Feedback from the Ukrainian individuals and families
who have arrived in North Ayrshire has been generally
very positive.  The homes provided by our Council are
all decorated and furnished to a high standard with
most of the items needed to help people settle
quickly. 
Communities are responding positively, with reports
of small gifts being handed in for distribution.  We
ensure new Ukrainian families are located closely to
one another to provide support to each other. 
Colleagues from the Third Sector have promoted
community interaction, while Community Link
Workers have organised get-togethers to make sure
everyone feels supported and nobody is left isolated.
Feedback from host families has also been positive. 
Our dedicated web page, email address and
telephone number mean that information is available
and officers are able to respond quickly and positively
to requests for assistance.
94

Page 95

Page 17 of 34
Inspiring Place 
Areas of Focus 
Over the next six months we will focus on the
following areas:
Well connected with effective infrastructure
♦ We will appoint a Digital Renewal Manager to
support the development of digital infrastructure
and digital economic transformation in North
Ayrshire.  
♦ The Roads Asset Management Plan (RAMP) will be
updated to include refreshed information on the
condition of assets.  This will inform any future
improvement actions.
♦ We will implement Phase Two of the new highway
infrastructure asset management system which
will introduce mobile working for operational staff
ensuring a more effective and efficient means of
managing reactive and routine works.
♦ We will complete the roll-out of public Wi-Fi
within our scheduled properties.
♦ Ardrossan Marina – We will appoint a design
team to develop detailed design work.
♦ Ardrossan North Shore – We will issue a contract
for the enabling works tender package following
evaluation of tender responses.  
♦ I3 Digital Innovation Campus
o Digital Processing Manufacturing Centre
(DPMC) – We will publish the tender for
refurbishment works in May and develop Full
Business Cases for Phases One and Two by
June.  (With aim of launching Phase One
facility in October.)
o We will include Phase One of the Flexible
Business Space in a Levelling Up Two Funding
submission by July.  We will complete the Full
Business Case for Phase One and submit to
the Joint Committee in the autumn. 
♦ We will progress completion of the estate for our
Early Years and Childcare Expansion Programme
including the final Arran based projects and
provision at Marress House, Irvine.
♦ We will continue investment in our wider learning
estate by progressing our Moorpark Primary
School and Montgomerie Park Primary School
projects. 
♦ Garnock Community and Visitor Hub
o We will complete construction of the hub by
August 2022.
o We will commence work on the proposed 5km
leisure route in Spring 2022.
o We will resubmit an application for £15m of
funding from the UK Government’s Levelling Up
Fund by July 2022.
Homes that meet resident’s needs
♦ We will transform the former Largs police office
into housing.
♦ We will install driveways at Council properties, in
agreement with tenants, in both the Dirrans area
of Kilwinning and Keppenburn Avenue, Fairlie to
alleviate current parking issues.  
Vibrant, welcoming and attractive
environment
♦ We will use data from the recent Open Space
Audit to update our Open Space Strategy 2016 –
2026.  
♦ We will proceed with the next round of the
Repurposing Property Grant Fund, supporting
landowners and communities to bring vacant land
and properties back into positive use.  
♦ We will refresh our Vacant and Derelict Land
Strategy and present to Cabinet for approval.
♦ We will implement our Visitor Management Plan
to manage the impact of tourism on our places
and improve the experience of visitors.
A sustainable environment
♦ We will progress the procurement of two solar
farm installations on the former landfill sites at
Nethermains and Shewalton.
♦ We will launch a new community-based energy
support model, to help families across all housing
tenures alleviate the impacts of rising energy
prices. 
♦ We will progress work on a detailed route map for
decarbonisation of our fleet of vehicles in line
with our net-zero aspirations. 
♦ We will undertake wider stakeholder and
community engagement during April and May
2022 to support the Place Framework.
♦ We will finalise proposals around a ‘remakery’
project led by our Waste Service.
♦ We will improve signage and waste separation
within our household waste recycling centres,
including improving opportunities for reusing
mattresses and more furniture through our bulky
waste reuse partner during Spring 2022.  
♦ We will implement new mobile technology in our
refuse collection vehicles during Spring 2022.
♦ We will review findings of the pilot recycling
system within seven participating schools.
95

Page 96

Page 18 of 34
A Council for the Future
Key Activities 
An accessible Council that puts residents and
communities at the heart of what we do
Our ‘Accessing the Council’ project is continuing to
simplify the range of ways to contact our Council and
ensure we provide the best service for our residents
via a ‘no wrong door’ approach to accessing services.  
We have installed upgraded public Wi-Fi at 30 council
locations.  This includes 15 libraries, the Harbour Arts
Centre, the Heritage Centre in Saltcoats and Eglinton
Country Park.  In addition, implementation of the new
cloud based wireless network solution across our
main Council buildings and schools is over 95%
complete.
The Service Level Agreement with The Ayrshire
Community Trust (TACT) has been refreshed and
updated in the context of Community Wealth Building
and the need for increased third sector input into
Community Asset Transfer.  Funding for this has been
allocated from the Community Asset Transfer Start Up
Fund.  
We have procured web accessibility software which
will ensure our documents published on our website
and intranet are as accessible as possible.  It will also
improve the efficiency of publishing documents.
A new central location on our Council website for
Online Services has been created that enables online
reporting, requesting, applications and payments.  As
a result, the Report-It app has been decommissioned.  
We have strengthened our ICT and Cyber Security
team, which now comprises an ICT and Cyber Security
Architect and two Cyber Security Officers.  This
ensures our Council has the required resources to
continue to deliver a resilient and robust ICT and
cyber security capability.
A Council-wide business continuity exercise was
completed in October based around the scenario of a
major ransomware attack.  This enabled services to
evaluate the effectiveness of their business continuity
plans in coping with a long-term technology outage.  
An efficient Council that maximises resources
and provides value for money
We delivered a balanced budget for 2022/23 in March
including identifying £4.538m in savings for the year. 
The indicative budget gap for 2023/24 is £10.729m
and £8.785m for the following year in 2024/25.  We
are continuing to explore ways to meet the pressures
on our finances.
We are looking at solutions to enable hybrid meetings
in line with Covid-19 restrictions.  The first fully hybrid
Council meeting is expected to take place following
the Local Government Elections in May. 
Following the publication of the Accounts Commission
Statutory Direction 2021 in December, discussions
have been held with the Executive Leadership Team
on how to implement the direction in full, including a
refreshed approach to self-assessment within our
Council services.
Due to the successful roundabout advertising and
floral bedding pilots, further potential for assisting
local businesses to advertise have been considered,
leading to the development of an Advertising and
Sponsorship Framework, which will be taken to
Cabinet shortly.  This will provide guidance to services
looking at utilising assets in this respect.  Current
examples being explored include advertising on refuse
vehicles and digital screen technology for festival
events. 
A valued workforce that delivers high quality
services
Our Professional Learning Academy (PLA) team
continue to deliver interventions and support for
practitioners across North Ayrshire.  Since January,
622 of our employees within primary and secondary
schools took part in ‘twilight’ evening training
sessions.  The Olevi programme (Outstanding Teacher
Programme and Outstanding Classroom Assistant
Programme) was delivered for the first time to eight
classroom assistants from five schools (four primary
and one secondary) and seven teachers from five
primary schools.  The programme supports a
reflective approach, increased confidence and
creative support for learning.  The team continue to
update online resources on the Glow blog
(Education’s secure internet space) for practitioner
use and to support remote learning.
96

Page 97

Page 19 of 34
In November, we launched the opportunity for Senior
Leaders to apply for a supported place on the
Strathclyde University MBA programme.  This
programme will commence in April 2022 and is a
fantastic opportunity to assist individuals with their
own development and well as supporting career
aspirations within the organisation.  
A number of Connected Leadership virtual sessions
have been hosted such as our work on The Promise,
Environmental Sustainability, Prevent awareness (a
duty for authorities to prevent people being drawn
into extremism) and Cyber Security Sessions, and all
have been positively received.  Further events are
planned for 2022 and give an opportunity discuss
major initiatives and share knowledge across our
Council.
Our Journey into Leadership (JIL) employee
development programme continued to be delivered
remotely.  The most recent session commenced in
February 2022. 
A new “Managers Guide to Agile Working” has been
launched as part of the Leadership Academy
Knowledge Nugget series – this is to support
managers as we move into the new phase of hybrid
working.  This nugget contains information on our
four workstyles (Agile, In Building, Mobile and Home),
advantages of agile working, guidance on building and
maintaining trust with your team together with case
studies from an employee and manager perspective. 
We have made improvements to our Wide Area
Network (WAN) separating school and corporate
internet traffic. This means both Education and
Corporate users now have higher internet bandwidth
availability giving faster connection speeds and an
improved user experience. Additionally,
approximately 60 sites have had WAN connection
upgrades completed. 
Employee Wellbeing
Communication of wellbeing resources continues to
be promoted utilising the excellent resources
provided by our Occupational Health provider.  Topics
covered included – Dry January, Building Resilience,
Financial Wellbeing, World Cancer Day and Time to
Talk Day.  There were also resources to support Rest
and Recovery (highlighting the importance of sleep)
and Nutrition and Hydration awareness.
For our Livewell / Workwell programme - there was a
focus on Winter Wellbeing including DrEAM (Drop
Everything and Move), Healthy Eating – Fake Away
(which promoted using the money allocated for a
takeaway to cook a new healthy alternative instead)
and promotion around No Smoking Day in March.  
Carer Positive – We have held Carer Positive Level
Two status (Established) since 2019 and are currently
working towards Level Three status (Exemplary).  In
support of this, the Supporting Carers Policy has
recently been updated to reflect the introduction of
our workstyles and our buying of additional annual
leave scheme. 
Long Covid – We produced guidance to provide
managers with supporting information for colleagues
experiencing Long Covid.  This was launched in
February.
Supporting employees with cancer – Launched in
March, we produced this guide to support managers
and employees with cancer from diagnosis to
treatment and return to work.  It draws on best
practice from MacMillan Cancer Support and CIPD
(Chartered Institute of Personnel and Development). 
We launched a Shared Cost Salary Sacrifice
Additional Voluntary Contribution scheme to support
employees to plan and save for retirement.
A powerful and respected voice
The outcome of the funding applications to Round
One of the Levelling Up Fund was received in October
2021.  This confirmed an allocation of £23.7m to the
B714 Upgrade.  Unfortunately, the Gateway to the
West Coast and Clyde Islands project was unsuccessful
during this first round of funding, however we met
with the UK Government in December to discuss the
applications and this will help inform the resubmission
of the Gateway project to Round Two of the fund.
In November Cabinet approved the submission of an
application to the Levelling Up Fund Round Two with
South Ayrshire Council for the Central Ayrshire
constituency.  This application will focus on the
commercial estate and associated low carbon
infrastructure within the Prestwick to Irvine corridor. 
We received notification of three successful bids to
the Community Renewal Fund which we made on
behalf of local partners totalling just over £1m.  They
include Place Framework, Impact Arts project and
Islands Green Programme.  Grant funding agreements
have been put in place for all three projects and initial
funding has been released.  
97

Page 98

Page 20 of 34
A Council for the Future
Areas of Focus 
Over the next six months we will focus on the
following areas:
An accessible Council that puts residents and
communities at the heart of what we do
♦ We will continue to scope the ‘Accessing the
Council’ initiative and develop the approach.  
♦ We will reopen our front facing offices in line with
Scottish Government guidance.
♦ We will prepare for the Local Government
Elections scheduled for May 2022.  
♦ We will develop an Accessibility Approach that
will help to raise the profile of digital accessibility
including online information and embed good
practice across our Council.
♦ We will implement a new Customer Portal for our
residents that will be fully integrated with the
national MyAccount. 
An efficient Council that maximises resources
and provides value for money
♦ Refresh approach to self-assessment within
Council services.
♦ We will further implement solutions that support
hybrid meetings across our Council.  
♦ We will work towards the renewal of our Public
Services Network compliance certification. 
A valued workforce that delivers high quality
services
♦ We will build on our Carer Positive Level 2 status
(Established) to work towards Carer Positive
Status Level 3 (Exemplary)
♦ We will continue our Connected Leadership
sessions to help share knowledge and discuss
initiatives across our Council.
♦ We will work towards becoming an Ambassador
for Recruit with Conviction, ensuring we are
promoting safe and sustainable employment.
♦ We will continue the wide and local area network
upgrade (WAN and LAN). 
A powerful and respected voice
♦ We will prepare the resubmission of the Gateway
to the West Coast and Clyde Islands project to the
UK Levelling Up Fund (round two of funding).
♦ We will work with South Ayrshire Council to
prepare an application for the Central Ayrshire
constituency.  This will focus on the commercial
estate and associated low carbon infrastructure
within the Prestwick to Irvine corridor.
98

Page 99

Page 21 of 34
Performance Summary
Where performance indicator information is pending, the most recent status up to
2020/21 year-end is used.  Indicators and actions adrift of target and not previously
reported are detailed on the following pages.
Aspiring Communities
♦ Active and strong communities
♦ Children and young people
experience the best start in life
♦ Inclusive, growing and
enterprising local economy
♦ Residents and communities enjoy
good life-long health and well-
being
♦ Residents and communities are
safe
Inspiring Place
♦ Well connected with effective
infrastructure
♦ Homes that meet residents’
needs
♦ Vibrant, welcoming and attractive
environment
♦ A sustainable environment
A Council for the Future
♦ An accessible Council that puts
residents and communities at the
heart of what we do
♦ An efficient Council that maximises
resources and provides value for
money
♦ A valued workforce that delivers
high quality services
♦ A powerful and respected voice
Legend
On Target
Slightly Adrift of Target
Significantly Adrift of Target
Status Unknown / Data Only
15
94%
1
6%
Actions
13
72%
3
17%
2
11%
Actions
10
56%
1
5%
4
22%
3
17%
Performance Indicators
7
54%
4
31%
2
15%
Performance Indicators
1
33%
2
67%
Performance Indicators
4
80%
1
20%
Actions
99

Page 100

Page 22 of 34
Performance Indicators Adrift of Target
This section details the performance indicators adrift of target and the action being taken to address performance. 
Due to expected data lags the most recent data may relate to previous time periods but may only now be available
to report.  To avoid duplication, only data that has not previously been reported to our Cabinet is included in this
section.  
Aspiring Communities 
CP_04 Percentage of children achieving their developmental milestones at the time the child starts primary
school
The most recent data available relates to 2020/21 but is included in this report for the first time.  72% of our children
achieved their developmental milestones by the time the child started primary school, below the target of 80%.  The
Early Years Milestones evaluations were not collected in 2019/2020 due to the Covid-19 lockdown periods.  The
decrease in the percentage of children reaching their pre-school developmental milestones in Health and Wellbeing,
Literacy and Numeracy is largely due to the long periods of Home Learning and lack of social/play interaction with
Early Years practitioners as well as their peers.  This year there can be no direct comparison with the pre-pandemic
period which saw 78% of children meet these milestones in 2018/19. 
CP_07 Percentage of school leavers entering positive destinations (LGBF)
This data is sourced from the Local Government Benchmarking Framework (LGBF) and the most recent data became
available in April 2022 and relates to 2020/21.  The percentage of school leavers entering positive destinations has
increased in 2021, reflecting the first signs of post-pandemic economic recovery.  The percentage of leavers in
employment has increased by almost four percentage points.  The percentage of leavers entering higher education
has also increased compared to 2020. 
CP_09 Percentage of working age population in employment
As at September 2021 (Source: Nomis) 66.4% of working age people living in North Ayrshire are in employment,
below the target of 70% and last year’s value of 69%.  Our economy has been greatly impacted by the pandemic,
however we have developed a ‘No One Left Behind’ Delivery Plan to increase employment levels across North
Ayrshire. 
Inspiring Place 
CP_19 proportion of operational buildings that are suitable for their current use (LGBF)
This data is sourced from the LGBF and the most recent data became available in April 2022 and relates to
2020/21.  Performance has improved from 90.89% to 91.05% in the past year and is expected to improve further due
in part to the rationalisation of the additional support needs school estate including the opening of Lockhart Campus
which took place after this LGBF reporting period. 
CP_21 Proportion of properties receiving superfast broadband (LGBF)
This data is sourced from the LGBF and the most recent data became available in April 2022 and relates to
2020/21.  94.7% of properties are receiving superfast broadband.  We monitor this indicator however, we do not
have direct influence over the rollout of broadband.  The speed of the rollout appears to be slowing, this may be due
to focussing on more rural areas of North Ayrshire which take longer to influence this percentage due to housing
density.  (This slower rollout was apparent between 2018/19 and 2019/20, prior to the pandemic lockdown periods.) 
CP_26 Tourism Visitor Numbers
The figure of 315,620 visits relates to the 2020 calendar year and became available at the end of 2021 due to delays. 
Tourism was of course severely affected by the Covid-19 lockdown periods during this period.  Figures for the 2021
calendar year are expected very shortly.  Various plans are underway for 2022 including the Making Waves festival in
July as well as the longer-term blue economy work being undertaken as part of the Ayrshire Growth Deal. 
100

Page 101

Page 23 of 34 
CP_27 Street Cleanliness Index – Percentage Clean (LGBF)
This data is sourced from the LGBF and the most recent data became available in April 2022 and relates to
2020/21.  Performance reduced from 94.64% to 91.34%, below the 93% target.  The largest impact on our
performance was the essential diversion of Streetscene resources to waste collections during Covid, together with
the impact of Covid restrictions limiting activity.  However, we expect performance to recover as restrictions ease. 
CP_28 Hectares of vacant and derelict land in North Ayrshire
The amount of vacant and derelict land has decreased between 2020/21 and 2021/22 from 1,204 to 1,198 hectares
respectively.  During this time eight sites totalling 9.3ha were removed and eleven sites totalling 3.9ha were added. 
We are reviewing how we can support a reduction in the amount of vacant and derelict land in North Ayrshire
through revising our Vacant and Derelict Land Strategy, with the intention to present to Cabinet later in the financial
year. 
CP_29 Overall carbon emissions (tonnes)
Overall carbon emissions are currently 22,653 against a target of 21,247 tonnes.  This is a provisional figure as not all
data required is available until the end of Quarter One and estimates have been used where data is pending.  Carbon
emissions associated with energy in buildings, transport and travel, street lighting and waste have been used to
calculate this figure. 
Adhering to Covid-19 ventilation guidance, such as the requirement to leave windows open in occupied spaces
including schools for natural ventilation, causes more heating fuel to be used to achieve comfortable temperatures.
This has affected all building groups, particularly sheltered housing, schools and community centres. 
Monthly progress of actions within the Environmental Sustainability and Climate Change Strategy are reported to
Senior Management in order to ensure progress. Recommendations from Energy Performance Certificate surveys
are being developed into an action plan to help reduce emissions from energy use in buildings.
Performance Indicator Amendments
An important element of the Corporate Policy, Performance and Elections Team’s role is to monitor the robustness
of indicators and ensure the framework remains relevant to our Council Plan priorities.  This ensures we are
measuring the correct areas and have the information we need to make decisions.  As a result, the following areas
have been highlighted.
CP_12 Percentage of learning disability service users accessing employment support activities
This measure currently captures the employability opportunities aligned to the Trindlemoss Day service and for
Learning Disability Service users only.  This does not capture the wider work in relation to job coaching and
employability support provided by other agencies including our employability team to a wider cohort of residents
with additional support needs.  As a result, this measure needs to be removed from the Council Plan following 31st
March 2022.  A replacement measure based on wider employability activity is currently being investigated and will
be proposed in the Mid-Year Council Plan Progress Report.  
CP_13 Percentage of children with BMI centile >91 at 27 month review
It is recommended that this indicator is replaced within the Council Plan.  Currently the data gathered measures the
children where a review is undertaken and a clinical intervention is indicated, rather than being a measure which is
reflective of the health of the wider population.  Additional information recently available will potentially provide a
better performance indicator.   We are working with the HSCP and will propose this replacement within the Mid-
Year Council Plan Progress Report.
CP_14 Percentage of households in fuel poverty
It is proposed that the 2023/24 target is increased from 27% to 28% due to the expected increase of the Ofgem
energy price cap.
101

Page 102

Page 24 of 34
CP_16 Percentage of people aged 65 and over with long-term care needs who are receiving personal care at
home (LGBF)
Some historical data relating to this PI has been refreshed following the most recent LGBF data release in April.  No
statuses or trends were changed as a result.
CP_23 Number of new build Council housing units reaching completion (cumulative)
The targets for this indicator are approved by Cabinet as part of the Strategic Housing Investment Plan (SHIP), then
updated in the Council Plan.  As a result, the original indicative target of 1,375 for 2023/24 has been removed and
will be updated once the target is available.
CP_24 Number of empty homes brought back into use (cumulative)
This is a cumulative PI and the target for 2023/24 has been amended from 600 to 1,452 to reflect the overall total,
rather than purely for that year.
CP_25 Percentage of Council dwellings that meet the Scottish Housing Quality Standard (LGBF)
Some historical data relating to this PI has been refreshed following the most recent LGBF data release in April.  No
statuses or trends were changed as a result.  In addition, the method used to calculate this PI is changing so targets
for 2022/23 and 2023/24 have been removed and we will continue to monitor this indicator.
CP_29 Overall carbon emissions (tonnes)
Due to stronger than expected performance in this area, the 2023/24 target has been reduced from 35,000 to
19,500 tonnes.
CP_31 Percentage of total household waste that is recycled (calendar year as per SEPA) (LGBF)
It is proposed the target for 2023/24 is amended from 62% to 57%.  The original target was estimated as part of the
Zero Waste Strategy in 2017.  Though starting to recover, actual recycling performance has been less than
anticipated due to the Covid-19 pandemic negatively impacting recycling performance across Scotland.
CP_33 Percentage of Self-Service Transactions 
It is proposed this target is increased from 50% to 55% due to increasing volumes of online transactions over the
past two years. 
102

Page 103

Page 25 of 34
Actions Adrift of Target
Within our Council Plan Delivery Plan overall actions are supported by sub actions.  Officers provide an update on
activity and an estimate of the current status (red, amber or green).  Where a sub action is adrift of target (amber or
red) this sets the status of the overall target so that any off-target performance can be highlighted, with significantly
adrift (red) statuses taking priority.  This section highlights the reasons for underperformance within each action and
efforts being made to remedy it.    An overview of action performance can be shown in appendix two of this report.
Actions adrift of target will continue to be managed during 2022/23.
CP_05 – We will expand our learning and childcare estate, including ensuring all eligible children are able to access
1140 hours of free childcare each year.
CP-SUB-08 Deliver major educational
new build and refurbishment projects
aligned to Scotland’s Learning Estate
Strategy:  "Connecting People, Places
and Learning”.
(Due 31st March 2022 – See ‘Sub-
Actions Relating to the Education
Service Plan’ section below.)
The extensive programme to upgrade our Early Years Estate is in its final stages
with only those projects on Arran, and the major refurbishment of Marress
House, remaining to be completed. The other main Learning Estate projects - a
replacement Moorpark Primary School, a new primary/early years facility for
Montgomerie Park, Irvine and a significant new learning and community
campus at North Shore Ardrossan, have continued to be developed throughout
Quarter Four.
The concept design for Ardrossan Campus was refined in March to a point
where it meets Royal Institute of British Architects (RIBA) Stage 2 standards,
and this will be considered by the Project Board and SFT before the project can
advance to RIBA Stage 3.
The construction of Moorpark Primary School has commenced, but materials
delays have adversely impacted on progress and this project will be delivered
later than anticipated. Officers are working with the contractor to update the
programme to minimise delay.
Montgomerie Park Primary School is being procured through Hub South West
Scotland (HubSW), and this process has been elongated by Covid, materials and
costs issues.  All large-scale capital projects across our Learning Estate have
been adversely affected by external factors which have hampered progress and
delivery.
CP-SUB-09 Develop an Outdoor Play
Strategy to support Early Years
Practitioners to provide excellent
learning and developmental
opportunities.
(On target – no remedial note required.)
CP_15 We will let people decide how best to manage their own care needs and support people to live in their own
homes for as long as possible
CP-SUB-31 Re-design Older People's
Services - Home First approach. (On target – no remedial note required.)
CP-SUB-32 Grow Care at Home
capacity.
(Due 31st March 2022)
Additional winter investment confirmed in late 2021 has been welcomed and
provides an opportunity for permanent recruitment to the Care at Home
workforce to address unmet need in the community in North Ayrshire, however
this will be dependent on successful recruitment which continues to be a
challenge.
There have been a number of actions taken to grow the Care at Home
workforce throughout 2021 and early 2022, which are detailed below:
♦ Advertising Via MyJobScotland recruitment website, local and social media
as well as leaflet distribution.
103

Page 104

Page 26 of 34
♦ Regular interviews including online/digital when restrictions ceased face to
face interviews
♦ 30+ Care at Home recruitment events held since September 2021
♦ Continued recruitment events weekly in 2022 to date, including extending
venues across wider localities and weekend events
♦ Permanent investment which will see the recruitment of over 80 new
permanent posts into the Care at Home service in North Ayrshire.
♦ CIS Care Academy ongoing and supporting candidates to
interview/appointment (joint initiative with employability team)
♦ Modern Apprentices scheme
♦ Long Term Unemployment/Skills for Life Project (joint initiative with
employability team)
♦ Supporting initiative with Ayrshire College ‘Career in Care’
♦ Promoting permanency of roles available 
CP-SUB-33 Prioritise Day Services
Model and Support for Carers.
(Due 31st March 2022)
The Integration Joint Board (IJB) approved a plan for remobilisation of Older
People's Day Services in August 2021 and the planning continues. The service
has been engaging with Alzheimer’s Scotland who re-opened its Day Service in
Ardrossan in late 2021.  The Partnership’s inhouse Day Services remain
temporarily closed at this time and plans to re-open have unfortunately been
impacted by significant workforce challenges due to the Covid-19 pandemic.
The Partnership continues to provide outreach Day Services support.   The
Carer’s Support Team have been working with colleagues from Addiction
Services to build capacity to support carers and encourage uptake of Adult
Carer Support Plans. 
CP-SUB-34 Prioritise integrated
Island services, including
unscheduled care.
(Due 31st March 2022)
Recruitment continues to be very challenging at the moment, particularly for
services in remote and rural locations including Arran.  There are very small
teams on the Island therefore a small number of vacancies can have a
disproportionate impact on service delivery. The service continues to pro-
actively recruit to remaining roles. 
CP-SUB-35 We will help individuals to
have better choice and control of
their support at an early stage by
reinvigorating the HSCP charging
policy.
(On target – no remedial note required.) 
CP-SUB-35a We will help individuals
to have better choice and control of
their support at an early stage by
reinvigorating Self-Directed Support.
(Due 31st March 2022)
The Scottish Government Pandemic Self-Directed Support Guidance is being
promoted with services as best practice to embed it in our ways of working.  
The HSCP Senior Management Team have endorsed a new Self-Directed
Support Review and Learning Board.  Terms of Reference have been drafted
and experience/ expertise will be drawn from the HSCP, third sector and
independent advisory partners to map, evaluate, plan and remodel the
approach taken to meet our duties under the Social Care (Self-Directed
Support) (Scotland) Act 2013. 
The HSCP and our Council Finance team successfully implemented the national
uplift of wage rates for the Personal Assistant workforce.   
104

Page 105

Page 27 of 34 
CP_16 We will work with individuals and communities to support positive lifestyle choices which improve health and
wellbeing. 
CP-SUB-36 We will provide
opportunities for people to be more
active more often, through the Active
Communities Strategy
(On target – no remedial note required.) 
CP-SUB-37 We will work with Scottish
Government as a trailblazer site for
the whole systems approach to diet
and healthy weight (public health
priority)
(Due 31st March 2022)
As employees in Public Heath continue to be seconded elsewhere, the work of
the Trailblazer has been paused. The Lead Officers have attended the regular
catch-up events and skills sharing events to keep abreast of developments
across the sector. 
CP-SUB-38 Prioritisation of children
and young people receiving support
from Child and Adolescent Mental
Health Services.
(Due 31st March 2022)
The organisational change work is ongoing.  The team coordinator for CAMHS
Neurodevelopmental team is in place and a preferred candidate has been
identified for the Service Manager for CAMHS Neurodevelopmental Team.
Recruitment is ongoing for the CAMHS Unscheduled and Intensive Support
Team with interviews commencing from  April. 
CP-SUB-39 Prioritise community
mental health services supporting
people within their communities.
(Due 31st March 2022)
Ongoing high levels of demand against a background of reduced staffing due to
Covid-19 related absences and lack of additional investment in specific fields
such as community psychiatric nursing, remain challenging.
From a social work perspective, we outlined the need for staff in the Mental
Health Officer Service and the care management aspect of the social work
team, in order to provide a service capable of meeting current need in both
areas across North Ayrshire. The funding of several posts within the service has
now been agreed and the team are progressing this. 
From a strategic view, on a Pan Ayrshire basis we have constructed a 1st year
plan for ‘Mental Health in Primary Care’.  This has been submitted to the
Scottish Government with results expected around the end of May 2022.  If
approved this will be a significant piece of work until 2025. 
CP-SUB-40 We will place Mental
Health Practitioners into GP practices
to offer triage calls, urgent and
routine face to face assessments as
well as directing patients to the most
appropriate support without
unnecessary referrals to mental
health services.
(Due 31st March 2022)
There has been ongoing engagement with primary care regarding the
deployment of Mental Health Practitioners.  Following absences, we are now in
the process of returning employees to work which will improve this area.  As
part of the new ‘Mental Health in Primary Care’ plan, we have submitted a
pan-Ayrshire 1st year plan to increase the Mental Health Practitioner numbers
across Ayrshire to original business case submission.  If successful, this would
mean that every practice will have Mental Health Practitioner cover, and
employee absence could be factored into NHS Ayrshire and Arran workforce
practice standards.  This has been submitted to the Scottish Government with
results expected around the end of May 2022.   
CP-SUB-41 We will improve
emotional and mental health and
wellbeing through physical and social
participation in community activities,
including for young people
(On target – no remedial note required.)   
105

Page 106

Page 28 of 34
CP_17 We will work with partners to support our vulnerable residents and communities.
CP-SUB-42 Work closely with
colleagues in Acute Services and
Police Scotland to address the levels
of unscheduled care in mental health.
(Due 31st March 2022)
Following confirmation of additional monies, the Unscheduled Care Mental
Health Service has recruited posts dedicated to the development of an
emergency services mental health pathway.  Final touches are being made to
this pathway, with education and training being vital for referring partners
prior to planned launch in May 2022.
The Unscheduled Care Mental Health Service is also in the process of identifying
accommodation that would allow the development of a mental health
assessment hub.  This hub would alleviate the need to utilise emergency
departments as a place of safety, allowing direct assessment to specialist
mental health staff - bypassing the need to attend emergency departments.  It
would also allow a safe place for assessment in addition to individuals’ homes
and local health centres, meeting the vision of Caring for Ayrshire, providing
the right care, at the right time, by the right clinician.
CP-SUB-44 We will implement the
Safer North Ayrshire Strategy 2020-
2025 along with our Community
Planning Partners
(On target – no remedial note required.)
CP-SUB-46 Introduce a Better Off Hub
to provide holistic short and long
term financial stability for our
residents and reduce impact on
services.
(On target – no remedial note required.)
CP-SUB-47 We will ensure all our
residents are able to access food with
dignity
(On target – no remedial note required.)
CP_18 We will extend the ‘Housing First’ pilot to address homelessness
CP-SUB-48 We will implement a
‘Housing First’ approach in our
provision of homelessness services,
providing mainstream, settled
accommodation for our tenants as
quickly as possible
(Due 31st March 2022 but see ‘Action
Amendments’ section below.)
(On target – no remedial note required.)
CP-SUB-49 We will further improve
support to young people to enable
them to sustain their tenancies
(Due 31st March 2022 but see ‘Action
Amendments’ section below.)
This project is on hold due to the impact of Covid-19.  This will resume once the
restriction levels are at zero.
CP_19 We will provide well-maintained, integrated travel and transport networks, supporting alternative and
sustainable transport.
CP-SUB-50 We will support the
development of the Ayrshire Regional
Transport Appraisal.
(Due 31st March 2022 but see ‘Action
Amendments’ section below.)
Transport Scotland (TS) previously confirmed that the Regional Transport
Appraisal (RTA) would be part of the Strategic Transport Projects Review Two
(STPR2) process. At this stage, there remains little clarity on the approach to
regionally significant projects. A number of these are currently deemed as out
of scope for STPR2 due to being viewed as local projects.
106

Page 107

Page 29 of 34
Phase Two was expected to report in late 2021 on investment over the longer
term. This was published in January 2022.  Our response has been prepared for
submission to Transport Scotland in April 2022.  This reinforces the points
raised in the Phase One consultation response and in particular, our Council’s
disappointment in the lack of any North Ayrshire specific interventions and the
need for more clarity on the RTA approach.
CP-SUB-51 We will implement active
travel and transport projects
including the promotion of strategic
active travel projects with partners
including Sustrans and Strathclyde
Partnership for Transport.
(On target – no remedial note required.)
CP-SUB-52 We will implement an
Electric Vehicle Strategy, and work in
partnership with government
agencies to deliver further electric
charging infrastructure throughout
North Ayrshire
(On target – no remedial note required.)
CP_38 We will use technology to improve access to and delivery of our services
CP-SUB-90 Implement Cloud solutions
where appropriate giving
consideration to business need,
solution availability, viability of
business cases, cyber security and
information governance.
(On target – no remedial note required.)
CP-SUB-91 Support Service re-design
through the use of digital and
technology solutions.
(On target – no remedial note required.)
CP-SUB-92 Deliver Cyber Resilience
Digital Services to support
technological innovation and provide
confidence in the security of our
infrastructure, data management
and technology.
(On target – no remedial note required.)
CP-SUB-93 We will review, refresh
and re-launch the Digital Strategy
taking account of learning from the
Covid-19 pandemic.
(Due 31st March 2022)
Draft high-level strategy produced, however this requires to be revisited to
consider the work of Digital Office.
CP-SUB-94 We will work
collaboratively with our communities
to streamline the benefits process –
helping residents maximise income
opportunities and build relationships
to support them.
(Due 31st March 2022 but see ‘Action
Amendments’ section below.)
(On target – no remedial note required.)
107

Page 108

Page 30 of 34
Action Amendments
To ensure transparency, where the Corporate Policy, Performance and Elections Team in partnership with services
feel an alteration to an action may result in more effective performance management, these recommendations are
listed below:
CP_05 We will expand our early learning and childcare provision to make sure all eligible children are able to
access 1140 hours of free care each year
It is proposed this action is amended slightly to read “We will expand our learning and childcare estate, including
ensuring all eligible children are able to access 1140 hours of free childcare each year”.  Currently building works on
our educational estate are included as a sub action to this action, as well as other activities supporting 1140 hours
provision.  However, the original wording doesn’t take account of the construction work so the status could
potentially be misleading. 
Sub-Actions Relating to the Education Service Plan
To ensure full alignment with the Education Service Plan 2020-22 and therefore academic year, it is proposed that all
Council Plan sub-actions sourced from the Education Service Plan are extended from 31st March 2022 to the end of
June 2022 (Quarter One and Term 4).  This will ensure continuity of updates from Education while the new Education
Service Plan is developed for August 2022.  New actions from this plan for inclusion in our Council Plan will be
proposed in the Mid-Year Council Plan Progress report.
CP-SUB-45 We will roll-out the Child and Adolescent Mental Health Service (CAMHS) wellbeing model piloted
in Kilwinning locality to all localities
This action was originally introduced in 2019, based on the assumption that it would be appropriate to roll out the
same model across all areas.  Progress has not been reported on at Year End 2021/22, however work in the
important area of supporting the mental health and wellbeing of our children and young people is already included
in the related sub-action CP-SUB-17 “We will develop a comprehensive approach to supporting mental health and
wellbeing (of our children and young people) in partnership with other agencies, cognisant of the impact of Covid-
19” so it is proposed this action is removed.  This reflects the tailored approach to supporting the wellbeing of young
people being adapted across the localities, with targeted interventions being established in school settings where
appropriate. 
CP-SUB-48 – We will implement a ‘Housing First’ approach in our provision of homelessness services,
providing mainstream, settled accommodation for our tenants as quickly as possible. 
This action is currently on target, with a due date of March 2022.  However, the actual end date of this programme is
31st March 2024 so the end date has been amended.  The aim of Housing First is to settle 100 people over five years. 
CP-SUB-49 We will further improve support to young people to enable them to sustain their tenancies
This action was impacted by lockdown restrictions with planned resumption once Covid-19 restriction levels are at
zero.  This is expected to be from April 2022 onwards.  In addition, this action is a longer-term action than originally
anticipated.  As a result, it is recommended that this action is extended from 31st March 2022 to March 2024 to
enable effective management of performance through the lifetime of our Council Plan.
CP-SUB-50 We will support the development of the Ayrshire Regional Transport Appraisal.
This action is currently slightly adrift of target as it was due to complete on 31st March, however this action has
become more complex.  More clarity is required to determine the approach to regionally significant projects as they
are currently being viewed by Transport Scotland as local projects and therefore out of scope.  A response to Phase
Two has been prepared for submission to Transport Scotland in April 2022.  To ensure we can capture the outcomes
of these discussions and progress, it is recommended that this action is extended by one year to March 2023.
108

Page 109

Page 31 of 34
CP-SUB-68 We will help private sector residents to improve the condition of their homes by implementing the
actions within the North Ayrshire Scheme of Assistance
This is an ongoing action and it is proposed it is extended to March 2023.
CP-SUB-80 We will implement actions within the Zero Waste Strategy which will incorporate the
implementation of enhanced waste and recycling services and move towards becoming a ‘Plastic Free
Council’ by reducing use of single use plastic.
This sub-action was due to expire on 31st March 2022, however it is recommended to extend the action to 31st
December 2022 to cover the implementation of the national ban on most single use plastics in June.  This will also
provide time for a new strategy to be developed which will be heavily reliant on the Scottish Government’s Route
Map consultation published on 30th May 2022.
CP-SUB-88 We will develop a Whole Systems Approach with our communities to make it easier for citizens to
contact us for advice, support and information 
It is proposed the end date for this action is extended from 31st March 2022 to 31st March 2024 so we can continue
to report on progress.
CP-SUB-94 We will work collaboratively with our communities to streamline the benefits process – helping
residents maximise income opportunities and build relationships to support them.
It is proposed the end date for this action is extended from 31st March 2022 to 31st March 2024 so we can continue
to report on progress. 
109

Page 110

Page 32 of 34
Trend Charts   
Key:  Trendline  
0
10
20
30
40
50
60
2018/19 2019/20 2020/21 2021/22
CP_22
Number of electric vehicle
charging points publicly available
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
2018/19 2019/20 2020/21 2021/22
CP_02
% of Council budget directed via
participatory methods
75.00%
80.00%
85.00%
90.00%
95.00%
2018/19 2019/20 2020/21 2021/22
CP_18
% of new tenancies to applicants who
were assessed as homeless sustained for
more than a year
30.00%
32.00%
34.00%
36.00%
38.00%
40.00%
2018/19 2019/20 2020/21 2021/22
CP_20
Overall percentage of road network that
should be considered for maintenance
treatment
0
200
400
600
800
2018/19 2019/20 2020/21 2021/22
CP_23
Number of new build Council housing
units reaching completion (cumulative)
0
5000
10000
15000
2018/19 2019/20 2020/21 2021/22
CP_30
Total installed capacity of low carbon
heat and electricity generation across
the Council's estate
110

Page 111

Page 33 of 34
Best In Class
This section outlines how we are working with others
to learn and continually improve our services.
Sharing Learning
Our Coding Clubs from 2017 have inspired a national
initiative by Digital Scotland called Code The Future.  It
is looking at reversing the decline in uptake of
computer science at both Higher and National level.  
Our Library and Information Manager and Lifelong
Learning Coordinator presented at the Scottish Library
and Information Council (SLIC) Showcase in
November.  They described the successful ‘Grow
North Ayrshire’ project which encourages
communities to come together and grow food. 
Feedback was very positive “Trailblazer is the word I
would use to describe this project!... The presentation
really brought things to life and shows the art of what
is possible.” – SLIC representative.
We are continuing to attend the Scottish Local
Authority Customer Services Group and have recently
shared experiences and ideas for delivery of face-to-
face services post Covid.  
The GIS and Analytics team are regularly being cited
externally as an exemplar for both data analytics and
GIS.  They are often approached by councils and other
bodies for advice or to give presentations on various
projects they have delivered using Power BI and the
ArcGIS Enterprise suite.  
To promote best practice, we launched our
Community Benefits Newsletter in December.  The
newsletter is intended to highlight best practice
among Council contractors and to share good news
stories from across the community benefit spectrum. 
The second newsletter was issued in March. 
111

Page 112

What Our Customers Say
This section captures a range of feedback from our residents and business representatives who have contacted us
recently.
“Hi – just to let you know that I was most
impressed by the speed with which you dealt
with the lighting problem at Parkend Road! 
Thanks so much.”
(North Ayrshire Resident)
“I just wanted to say thanks to the Roads
Department for fixing the potholes on Anthony
Road, Largs so quickly and doing such a good
job.”
(North Ayrshire Resident)
“Unfortunately we have had two occasions in the
past few months to contact Bereavement Services.
We have already taken steps to pass on our
compliment to the contribution of two of the
cemetery staff (Willie and Lee) who most recently
facilitated the scattering of my sister's ashes at the
family lair, however we feel it is also important to
thank Fiona most sincerely as she made everything
run smoothly and her advice was invaluable.  Her
sensitive approach to matters and her friendly
disposition made the whole process seamless. 
Fiona has been outstanding in the provision of
factual information, advice and options available to
our family. She truly is an asset to your
organisation.”
(North Ayrshire Resident)
“I would like to thank the caretaker/usher
who was assisting at the civic centre in
Ardrossan in late November where I was
attending for my booster.  The queues were
huge even with appointments.  I can only say
thank you to this man who, recognising my
hidden disability, got me a wheelchair.  I still
wonder how I would have managed if he
hadn’t come to my aid.  Thank you - hope
you see this.”
(North Ayrshire Resident)
“Thank you for getting in touch.  Following our
chat I can see that you are using the wrong
version of our bin collection calendar.  Here are
the correct dates and we have also emptied
your bins just now too.”
(North Ayrshire Council Representative)
“Hi, my bins have been missed on multiple
occasions and for the various colours too.  I’m
not sure why this is happening??!”
(North Ayrshire Resident)
112

Page 113

For further information please contact:
The Corporate Policy, Performance and Elections Team
Tel: 01294 324648 
Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk 
113

Page 114

Council Plan Performance Indicators  Year End 2021-22 Page 1 of 8
Appendix 2 – Council Plan Performance Indicators
Priority - Aspiring Communities
PI Code & Description
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Value Target Status Value Target Status Value Target Status Value Target Status Target Target
CP_01 Percentage of population who
are involved in local decision making
(see description)
51% 45.53% 6.67% 55.78%
CP_02 Percentage of Council budget
directed via participatory methods 0.62% 1.11% 0.89% 1.13% 1.2% 2.32% 1.1% 1.5% 1.5%
CP_03 Percentage of residents who
agree they have access to
opportunities to participate in their
local community
47% 47% 47% 47% 47% Data
pending 47% 47% 50%
CP_04 Percentage of children
achieving their developmental
milestones at the time the child
starts primary school
78%
Data not
collected
due to
Covid-19
79% 72% 80%
Data
available
in June
2022
78% TBC 85%
PI Status
Significantly Adrift of Target
Slightly Adrift of Target
On Target
Data Only
Data Not Available
114

Page 115

Council Plan Performance Indicators  Year End 2021-22 Page 2 of 8
PI Code & Description
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Value Target Status Value Target Status Value Target Status Value Target Status Target Target
CP_05 Average total tariff score of
pupils living in SIMD 30% most
deprived areas
638.1 715  685.8 718  744.7 724 
Data
available in
Feb 2023
710  TBC 745
CP_06 Average tariff score: All
Leavers 780.7 885  857.4 895  912 900 
Data
available in
Feb 2023
880  TBC 890
CP_07 Percentage of school leavers
entering positive destinations (LGBF) 94% 95.7%  92.5% 96%  95.2% 96.2% 
Data
expected
May 2023
from LGBF
93.5%  TBC TBC
CP_08 Percentage of Children living
in Poverty (after housing costs) 27.1% -  27.9% 26.5%  Data
pending 26.5%  Data not
available 26.5%  26.5% 25%
CP_09 Percentage of working age
population in employment 69.7% 64.7%  70.2% 70%  69% 64.7%  66.3% 70%  68% 73%
CP_10a Percentage of procurement
spent on local enterprises 20.31%  19.98% 23%  21.39% 23.5%  Data
pending 24%  25% 26%
CP_11 Percentage of people earning
less than the living wage (LGBF) 24.3%  16% 24%  16.2% 23% 
Data
expected
May 2023
from LGBF
22%  21% 20%
CP_12 Percentage of learning
disability service users accessing
employment support activities
23.88% 30%  23.84% 30%  0% 25%  25.69% 25% 
This indicator will be
replaced at Q2
2022/23
115

Page 116

Council Plan Performance Indicators  Year End 2021-22 Page 3 of 8
PI Code & Description
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Value Target Status Value Target Status Value Target Status Value Target Status Target Target
CP_13 Percentage of children with
BMI centile >91 at 27 month review 9.98% 10.5%  13.19% 10.5%  11.59% 10.5% 
Data
available in
July 2022. 
Q3 states
13.79%
(Red).
10.5% 
This indicator will be
replaced at Q2
2022/23
CP_14 Percentage of households in
fuel poverty 26% 26%  28% 25.5%  28% 28% 
Data
available
Feb 2023.
28%  28% 28%
CP_15 Number of attendances at
indoor sports & leisure facilities
(excluding pools)
1,886,930 -  1,859,843 1,964,100  71,913 736,915  298,806   
CP_16 Percentage of people aged 65
and over with long-term care needs
who are receiving personal care at
home (LGBF)
66.68% 65.6%  67.63% 66%  69.51% 66% 
Data
expected
May 2023
from LGBF
66%  66% 65%
CP_17 Emergency Admissions
(Number) 20,933 20,257  19,150 20,257  16,283 20,257  15,171 20,257  20,000 20,000
CP_18 Percentage of new tenancies
to applicants who were assessed as
homeless sustained for more than a
year
81.48% 82%  84.07% 82%  92.48% 85%  86.92% 85%  86% 88%
116

Page 117

Council Plan Performance Indicators  Year End 2021-22 Page 4 of 8
Priority - Inspiring Place
PI Code & Description
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Value Target Status Value Target Status Value Target Status Value Target Status Target Target
CP_19 Proportion of
operational buildings that are
suitable for their current use
(LGBF)
91.01% 92% 90.89% 93% 91.05% 93%
Data
expected
May
2023
from
LGBF
93% 93% 93%
CP_20 Overall percentage of
road network that should be
considered for maintenance
treatment
38.1% 39.3% 37.3% 38.1% 37.1% 38.1% 33.9% 37.5% 33.8% 33.8%
CP_21 Proportion of properties
receiving superfast broadband
(LGBF)
93.7% 94.1% 97% 94.7% 97%
Data
expected
May
2023
from
LGBF
97% 100% 100%
CP_22 Number of electric
vehicle charging points publicly
available
25 25 36 30 45 42 49 43 60 81
117

Page 118

Council Plan Performance Indicators  Year End 2021-22 Page 5 of 7
PI Code & Description
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Value Target Status Value Target Status Value Target Status Value Target Status Target Target
CP_23 Number of new build
Council housing units reaching
completion (cumulative)
296 296 381 351 437 755 681 630 866 TBC
CP_24 Number of empty homes
brought back into use
(cumulative)
295 60 594 500 594 600 1,052 600 1,252 1,452
CP_25 Percentage of Council
dwellings that meet the Scottish
Housing Quality Standard
(LGBF)
99.19% 99.4% 99.36% 99.4% 99.09% 99.5%
Data
expected
May
2023
from
LGBF
99.5% TBC TBC
CP_26 Tourism Visitor Numbers 1,519,260 1,599,400 1,534,968 315,620 1,534,968 Data
pending 1,534,968 1,600,000 1,650,000
CP_27 Street Cleanliness Index -
Percentage Clean (LGBF) 94.5% 94% 94.6% 94% 91.34% 94%
Data
expected
May
2023
from
LGBF
94% 92% 94%
CP_28 Hectares of vacant &
derelict land in North Ayrshire 1,279 1,269 1,180 1,244 1,204 1,194 1,198 1,144 1,094 1,094
118

Page 119

Council Plan Performance Indicators  Year End 2021-22 Page 6 of 7
PI Code & Description
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Value Target Status Value Target Status Value Target Status Value Target Status Target Target
CP_29 Overall carbon emissions
(tonnes) 40,666 45,137 37,508 39,320 22,846 35,127 22,653 21,247 21,000 19,500
CP_30 Total installed capacity of
low carbon heat and electricity
generation across the Council's
estate
9,682 9,600 9,700 9,700 10,720 9,800 11,680 11,000 11,800 12,000
CP_31 Percentage of total
household waste that is
recycled (calendar year as per
SEPA) (LGBF)
54.6% 54.5% 56.3% 59% 52.1% 52.1% 56.4% 53.1% 56.8% 57%
119

Page 120

Council Plan Performance Indicators   Year End 2021-22  Page 7 of 7
Priority - A Council for the Future 
PI Code & Description
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Value Target Status Value Target Status Value Target Status Value Target Status Target Target
CP_32 Percentage of Customers
delighted with the overall Customer
Service
81% 77%  81% 77%  Surveys suspended due to Covid-19 and due to
resume in 2022/23. 77% 77%
CP_33 Percentage of Self Service
Transactions 40.09% 35%  41.26% 40%  58% 45%  58.33% 50%  50% 55%
CP_34 Employee Engagement Level -
Council Wide No survey planned 70.67% 70%  No survey planned 72%
120

Page 121

Council Plan Action Tracker  Year End 2021-22 Page 1 of 6
Appendix 3 - Council Plan Action Tracker
*2021 status based on information available rather than specific sub-
actions.
**Council Plan Delivery Plan was in development during Q1.
2019-20 2020-21* 2021-22 2022-23 2023-24
Priority
Outcome
Ref # Existing Overall Action Q1 Q2 Q3 Q4 Year End
Estimate Q1** Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Aspiring Communities 
What we’
ll do to make active and strong
communities
CP_01 We will build stronger relationships between the
council, communities and partners.
CP_02
We will co-produce a local charter with our communities
which sets out the things we jointly commit to do for
each other, to help each other create a better North
Ayrshire.
CP_03
We will extend our participatory approach, offering
communities more opportunities to lead in local
decision-making.
CP_04 We will support communities to achieve what’s
important to them through strong local networks.
What we’
ll do to ensure our
children and young people
experience the best start in life
CP_05
We will expand our learning and childcare estate,
including ensuring all eligible children are able to access
1140 hours of free childcare each year.
CP_06
We will support our children and young people to
become successful learners, confident individuals,
effective contributors and responsible citizens.
CP_07
We will offer opportunities to our young people and
their families to play a more active role in school life and
encourage more participation in learning opportunities.
121

Page 122

Council Plan Action Tracker  Year End 2021-22 Page 2 of 6
*2021 status based on information available rather than specific sub-
actions.
**Council Plan Delivery Plan was in development during Q1.
2019-20 2020-21* 2021-22 2022-23 2023-24
Priority
Outcome
Ref # Existing Overall Action Q1 Q2 Q3 Q4 Year End
Estimate Q1** Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP_08
We will work with all young people to build their
resilience, supporting their mental health and physical
well-being.
What we’
ll do to have an inclusive, growing and
enterprising local economy
CP_09
We will work with schools, colleges, universities,
businesses and partners to deliver education, skills and
training, helping people into work and sustaining
employment.
CP_10 We will make sure that everyone has the ability and
knowledge to participate in the digital world.
CP_11 We will support our local businesses to become more
innovative and competitive.
CP_12 We will promote fair employment practices.
CP_13 We will develop and implement a Community Wealth
Building (CWB) strategy.
What we’
ll do to make sure
North Ayrshire residents and
communities enjoy good life-
CP_14
We will continue our work with partners, including the
Scottish Government, to explore the feasibility of a
Scottish Basic Income Pilot.
Complete
CP_15
We will let people decide how best to manage their own
care needs and support people to live in their own
homes for as long as possible.
CP_16
We will work with individuals and communities to
support positive lifestyle choices which improve health
and wellbeing.
122

Page 123

Council Plan Action Tracker   Year End 2021-22 Page 3 of 6 
*2021 status based on information available rather than specific sub-
actions.
**Council Plan Delivery Plan was in development during Q1.
2019-20 2020-21* 2021-22 2022-23 2023-24
Priority
Outcome
Ref # Existing Overall Action Q1 Q2 Q3 Q4 Year End 
Estimate Q1** Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
What we will do to
ensure North
Ayrshire residents 
CP_17 We will work with partners to support our vulnerable
residents and communities.                
CP_18 We will extend the ‘Housing First’ pilot to address
homelessness.                
Inspiring Place
What we’
ll do to make North Ayrshire well-connected with effective
infrastructure
CP_19
We will provide well-maintained, integrated travel and
transport networks, supporting alternative and
sustainable transport.                
CP_20
We will work with partners to make sure there is
sustained investment in our roads, ports and harbour
infrastructure to ensure that travel is resilient and 
CP_21 We will work with partners to extend public wi-fi and
improve our digital connectivity.                 
CP_22
We will provide an appropriately sized, fit for purpose,
energy-efficient and digital- enabled property portfolio,
including our schools.                
CP_23
We will attract investment, through the Ayrshire Growth
Deal and other means, to support regeneration and job
creation at our key development sites of i3 Irvine,
Hunterston, Lochshore, Ardrossan Marine Quarter, and
the Irvine Great Harbour.                
CP_24
We will support our communities to maximise the use of
community assets (such as schools) and encourage
Community Asset Transfers.                
CP_25
With our social landlord partners, we will build new,
modern, energy-efficient lifelong homes for life, tailored
to the needs of tenants.                
123

Page 124

Council Plan Action Tracker   Year End 2021-22 Page 4 of 6 
*2021 status based on information available rather than specific sub-
actions.
**Council Plan Delivery Plan was in development during Q1.
2019-20 2020-21* 2021-22 2022-23 2023-24
Priority
Outcome
Ref # Existing Overall Action Q1 Q2 Q3 Q4 Year End 
Estimate Q1** Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
What we’
ll do to
provide our
residents with     CP_26 We will actively promote a mix of homes by facilitating
private housing development.                
CP_27
We will work with property owners and landlords to
make sure our private housing is suitable for the needs
of our residents.                
What we’
ll do to make North Ayrshire a vibrant,
welcoming and attractive environment CP_29
We will provide well-kept public places and town
centres which will benefit our residents, visitors and
businesses.                
CP_30 We will, where possible, bring empty properties back
into use.                
CP_31
We will work with communities to improve the quality
of the local environment through a participatory
approach.                
CP_32 We will develop North Ayrshire as a coastal and island
destination, attracting tourism investment and visitors.               
What we'll do to make sure
we all live in a sustainable
environment CP_33 We will support a circular economy by re-using, recycling
and generating energy from the waste we manage.                
CP_34 We will develop additional low carbon renewable
energy schemes and networks.                
124

Page 125

Council Plan Action Tracker  Year End 2021-22 Page 5 of 6
*2021 status based on information available rather than specific sub-
actions.
**Council Plan Delivery Plan was in development during Q1.
2019-20 2020-21* 2021-22 2022-23 2023-24
Priority
Outcome
Ref # Existing Overall Action Q1 Q2 Q3 Q4 Year End
Estimate Q1** Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP_35
We will protect our communities by delivering the Local
Flood Risk Management Plan, the Shoreline
Management Plan and the Millport and Upper Garnock
Valley Flood Protection Schemes.
A Council for the Future
An accessible Council that puts
residents and communities at the
heart of what we do CP_36
We will work with communities and key stakeholders to
radically review what we do and how we do it, to deliver
cost effective services.
CP_37 We will provide joined up services across the Council
and with partner agencies and communities.
CP_38 We will use technology to improve access to and
delivery of our services.
A powerful and
respected voice
CP_39
We will make our case nationally, regionally and locally
levels to secure investment to support delivery of our
priorities.
125

Page 126

Council Plan Action Tracker  Year End 2021-22 Page 6 of 6
*2021 status based on information available rather than specific sub-
actions.
**Council Plan Delivery Plan was in development during Q1.
2019-20 2020-21* 2021-22 2022-23 2023-24
Priority
Outcome
Ref # Existing Overall Action Q1 Q2 Q3 Q4 Year End
Estimate Q1** Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
An efficient Council that
maximises resources and
provides value for money
CP_40 We will review what we do and how we do it to ensure
we deliver the best possible services.
This action was removed as approved by Cabinet in August
2021 as it duplicates CP_36 and CP_37.
A valued workforce
that delivers high
quality services
CP_41 We will empower and invest in our workforce to
develop new and innovative ways of working.
126

Page 127

Annual Performance Report
2021-22
Appendix 4
127

Page 128

Annual Performance Report 2021-22 | North Ayrshire Council
Elected members
■ SNP: 12
■ Scottish Conservative
and Unionist: 10
■ Labour: 9
(3 use description Labour and
Co-operative Party)
■ Independent: 2
Population
■ 134,300
■ Life expectancy:
Female – 80.1 years
Male – 75.3 years
Key assets include:
■ Early Years Centres:
41 Council owned
16 in Partnership
■ 48 Primary schools
■ 8 Secondary schools
■ 1 Additional Support
Needs school
■ 13,130 Council houses
■ 1,044km of roads
Economy
■ 64.9% of adults in employment
■ 135 residents with disabilities
supported by our Equal
employability programme
■ Streetscene Training and
Employment Academy
launched
■ 24.7% of our children and
young people in child poverty
■ 27% of our datazones in the
15% most deprived in Scotland
■ 3,260 business operating in
North Ayrshire
■ 840 businesses supported
Employees
■ 6,225.38 Full Time Equivalent
employees
■ 75.7% Female
■ 24.3% Male
32
Welcome About us
Welcome to our Annual Performance Report 2021-22.
This report provides an at a glance summary of how we’ve
supported our residents of North Ayrshire over the past year.
You can find full details in our magazine style Council Plan
Progress Reports published on our website 
(www.north-ayrshire.gov.uk/performance).
Thankfully 2021-22 has seen a transition from Covid-19 pandemic lockdowns to a more normal
way of living and delivering our services in a covid-safe way. We have been delighted to re-open
many of our services and once again have the opportunity to support you in person. Our focus is
now on recovery, building on our strong relationships and what we have learned during the past
two years to improve the lives of all our residents. 
It certainly continues to be a challenging time, but we are confident that by working together,
really listening to each other and supporting each other, we can rise to these challenges and
make a positive difference for all our communities.
We are proud to serve our people of North Ayrshire and would like to say thank you to everyone
who has supported the delivery of our services including our communities, Third Sector, public
and private partnerships and of course our employees. Together we will continue to make a
difference and ensure North Ayrshire is Fair For All.
Councillor Marie Burns
Leader of the Council
Craig Hatton
Chief Executive
CCoouunncciill  PPllaann  22001199--2244  PPrrooggrreessss  UUppddaatteeMid Year 2021-22
128

Page 129

North Ayrshire Council | Annual Performance Report 2021-22
54
Our Council planFinancial overview
Aspiring Communities
Funding  (£000s) Allocation  (£000s)
Our Council Plan is our commitment to our communities. It underpins
everything we do for our people in North Ayrshire. 
The Council Plan has three
priorities: ‘Aspiring Communities’,
‘Inspiring Place’ and ‘A Council for
the Future’. During 2021/22:
79.3% of our Council Plan performance
indicators and 94.9% of actions are on
or only slightly adrift of target.
Over £7million
of our Council budget
(2.32%) directed by our
communities
On average every £1 of
Community Investment
Funding has leveraged
£2.80 of additional
funding for our
communities
Money Matters
generated over
£17.5million
for residents in
receipt of 
welfare 
benefits
Our £31.3million
Additional Supports 
Needs school Lockhart
Campus opened 
in August
£3million
approved for our 
Community 
Investment Fund
153 local groups
received funding through
participatory budgeting
Lockhart Campus
Scottish Government General Grant
£285.526 (72%)
Council Tax
£59.887 (15%)
Non Domestic Rates
£28.392 (7%)
Scottish Government Specific Grant
£21.326 (6%)
Communties
£151.467 (38%)
Chief Executive’s
£26.28 (7%)
Financing Costs
£28.842 (7%)
Other Corporate Items
£9.613 (3%)
Health and Social Care Partnership
£107.059 (27%)
Place & Education
£71.87 (18%)
£395.131£395.131
129

Page 130

Annual Performance Report 2021-22 | North Ayrshire Council
6 7
The percentage of
households homeless for
more than six months has
reduced
from 76% 
prior to the
pandemic 
to 22%.
Inspiring Place
1,013
of our young people voted
in the Scottish Youth
Parliamentary Elections 
to elect four new 
Members of the 
Scottish Youth 
Parliament
1,022
Chromebooks
distributed to Primary 
Five and S2 pupils in receipt
of free school meals or 
clothing grants
86.9% of
tenancies
for former homeless
residents have 
been sustained 
for over a year
136
Young people reported
improved mental health
and wellbeing outcomes
through Community learning
and Development activities
Our first Cost 
of the School Day
conference attracted over
100 online
participants
600 young people
helped into employment
through Kickstart – our
Council’s Gateway created 
300 of these jobs
We are resettling
those displaced by the
war in 
Ukraine
10-year Island
Plans published
for Arran and
Cumbrae to 
support our 
island 
communities
49 electric vehicle
charging points
available
56.4%
of household
waste recycled
244 new
Council houses
completed
in total (including a small
number of employee
accommodation units
in sheltered housing
complexes)
506 Council
homes have solar 
panels fitted,
with a total capacity
of 1.65MW
£23.7million
was secured for the
B714 upgrade via 
the UK Government 
Levelling Up Fund
We have further
developed
Council owned renewable
energy projects
Universal school 
meals rolled out to
all Primary Four
and Five children
69.5%
of our
residents 
aged over 65
and with long term care
needs are supported at home
Streetscene
Training and Employment
Academy launched,
providing training and
employment for our
unemployed residents 
and support for 
community 
environmental 
projects
Council housing
130

Page 131

North Ayrshire Council | Annual Performance Report 2021-22
The Corporate Policy, Performance and Elections Team 
Tel: 01294 324 648
NorthAyrshirePerforms@north-ayrshire.gov.uk
The Corporate Policy, Performance and Elections Team welcome any 
feedback you may have. We strive to make our Council and reports as accessible
as possible and appreciate opportunities to discuss how this can be achieved.
For further information please contact:
A Council for the future
You can see how our performance compares to other 
Scottish local authorities through the national 
Local Government Benchmarking Framework online tool.
www.scotland.mylocalcouncil.info
Balanced budget
achieved 
for 2022/23 
including 
£4.538million
in savings
Our workstyles
were reviewed 
based on learning from the
pandemic, with each post
allocated a
workstyle of
‘Inbuilding’,
‘Mobile’, ‘Agile’
or ‘Home’
58.3% of
transactions 
with our Council are
self-service (online)
Through technology we can
now share the condition
of our Council estate
immediately – enabling
real time
decisions
to be made
Council-wide
business
continuity
exercise
completed to ensure we 
are prepared as possible
for any cyber-attacks
Public Wi-Fi
upgraded
at 30 Council locations
including libraries
622 employees
in schools took part in our
Professional Learning
Academy evening training
We delivered a
Covid-safe
Scottish Parliament
Election and Dalry and
West Kilbride By-Election
Face to face
services 
re-opened
131

Page 132

Local Government
Benchmarking Framework
2020-21 Data Analysis
(Data Released July 2022)
Appendix 5
132

Page 133

Contents
Introduction ............................................................................................................................................ 1
About the Data ........................................................................................................................................ 2
Data Trends ......................................................................................................................................... 3
Impact of Covid-19 Coronavirus ......................................................................................................... 3
Areas Expected to be Most Impacted by Covid-19 ......................................................................... 4
Summary of Performance ....................................................................................................................... 5
Rank .................................................................................................................................................... 8
Quartile ............................................................................................................................................... 9
Scottish Average ............................................................................................................................... 10
Council Plan Indicators ...................................................................................................................... 11
Family Groups ................................................................................................................................... 14
Directorates and Services ..................................................................................................................... 16
Chief Executive Services .................................................................................................................... 16
Financial ........................................................................................................................................ 16
Performance ................................................................................................................................. 19
Connected Communities Service ...................................................................................................... 22
Financial ........................................................................................................................................ 22
Education Service .............................................................................................................................. 24
Performance ................................................................................................................................. 26
Place Directorate............................................................................................................................... 31
Financial ........................................................................................................................................ 31
Performance ................................................................................................................................. 34
Health and Social Care Partnership .................................................................................................. 40
Financial ........................................................................................................................................ 40
Performance ................................................................................................................................. 43 
133

Page 134

Page 1 of 45
Introduction
The Local Government Benchmarking
Framework (LGBF) provides an opportunity to
benchmark our performance with other local
authorities in Scotland. It is administered by
the Improvement Service in partnership with
the Society of Local Authority Chief Executives
(SOLACE) and highlighted within the Accounts
Commission’s Statutory Performance
Information Direction 2021 which defines how
local authorities can demonstrate that they are
achieving Best Value for the people they serve. 
As a result, many of the indicators are used
within our Council Plan.  Further information
on Best Value, the Direction, LGBF and
benchmarking can be found in Our
Performance Strategy. 
This report analyses our performance relative
to other local authorities, details LGBF
indicators used within our Council Plan and
segments the full range of indicators by
service.  The most recent data (released in July
2022) relates to 2020/21 and covers the Covid-
19 (Coronavirus) pandemic lockdown periods. 
As a result, though this report details our
performance as at 2020/21, it does not contain
comments on planned improvement activity as
comparisons over time and with other local authorities represent limited value on this occasion.  
The LGBF brings together a range of performance indicators covering nine key themes detailed in the
table to the right.  The 2020/21 dataset sees the introduction of four new indicators.
• % of children living in poverty (After Housing Costs).
• Gross Value Added (GVA) per capita.
• Claimant Count as % of Working Age Population.
• Claimant Count as % of 16-24 Population.
By recording the same indicators as other local authorities across a wide range of themes, in more
normal years we can identify opportunities to learn from each other.  In addition, local authorities
with similar traits such as geography and deprivation are categorised into “family groups” to enable
as close as a like for like comparison as possible (see Family Groups section). 
LGBF Themes
Adult Social Care 
Children’s Services 
Corporate Services 
Culture and Leisure 
Economic Development  
Environmental Services 
Financial Sustainability 
Housing 
Tackling Climate Change 
134

Page 135

Page 2 of 45
About the Data
The most recent LGBF data was released by the Improvement Service in July 2022 and relates to
2020/21.  This is later than usual due to the Covid-19 (Coronavirus) pandemic.  There are 101
indicators across the nine themes.  The number of indicators has increased from 97 to 101 (8%)
between 2019/20 and 2020/21.  They are themed as follows:  
Breakdown of indicators by theme and data collection
Theme No. of
Indicators
2020/21 Data
Available
Adult Social Care 11 7 64%
Children’s Services 32 31 97%
Corporate Services 10 10 100%
Culture & Leisure 8 4 50%
Economic Development 13 13 100%
Environmental Services 15 13 87%
Financial Sustainability 5 5 100%
Housing 5 5 100%
Tackling Climate Change 2 2 100%
Total 101 90 89% 
There are 11 indicators with no data which are satisfaction indicators.  During the lockdown period,
resources tended to be shifted to frontline activities.  Due to this as well as the practicalities of
conducting surveys during this time, satisfaction surveys were put on hold.
For the purposes of this report, 101 indicators have been segmented into overall genres (see below). 
• Financial – All financial related performance
• Performance – All non-financial and non-satisfaction related performance
• Satisfaction – All satisfaction performance.  Seven of the 11 satisfaction indicators are based
on a rolling three-year average.  There is no satisfaction data for 2020-21. 
Breakdown of indicators by areas and data
collection
Theme No. of
Indicators
Data Returns
Financial 28 28 100%
Performance 62 62 100%
Satisfaction 11 0 0%
Total 101 88 87% 
We use three time periods used to compare data.  They are: 
Comparative Years
Description Start End
Short Term (One Year) 2019/20 2020/21
Medium Term (Three Years) 2017/18 2020/21
Long Term (10 Years) 2011/12 2020/21 
135

Page 136

Page 3 of 45
Data Trends
Within the current dataset, only 90 of
the 101 indicators have data available
for 2020/21 as satisfaction data is not
available.  In addition, trend data may
not be available for certain time
periods for some indicators depending
on when they were introduced into the
LGBF.  A breakdown of comparable
data is shown to the right. 
To assess performance the terms “improved” or “declined” are used in this report, rather than
referring to data as “increased” or “decreased”.  This terminology is used as for some indicators a
value increasing is improved performance (such as satisfaction), however, for some indicators a value
increasing is declining performance, (such as some financial indicators). 
Impact of Covid-19 Coronavirus
Prior to the release of the LGBF data, an Improvement Service LGBF learning event highlighted several
areas that appear to be most affected by the impact of the Covid-19 coronavirus pandemic.  This
section explores how we compare with members of our Family Groups in these areas. 
Due to essential closures during the lockdown periods, the cost per attendance at sports facilities has
risen sharply from £1.91 to £50.35, a rise of 2536%.  This scale of increase has been seen throughout
Scotland. 
Our cost per library visit has risen due to the essential closures of our libraries during lockdown, many
of which were utilised as Community Hubs during this period.  However, it is not as affected as other
cost per visit measures as the LGBF includes digital as well as physical visits for this indicator. 
Our cost per dwelling of collecting council tax has decreased considerably in contrast to other
members in our Family Group.  The cost has reduced from £5.02 to £1.58.  This is the biggest reduction
not only within the Family Group but also with all 31 Local Authorities and has resulted in an improved
rank from fifth to first in Scotland. 
The percentage of total household waste that is recycled reduced by four percentage points between
2019/20 and 2020/21 but has since recovered to pre-pandemic levels.  The reduction between 2019
and 2021 was in line with other members of our family group who all saw a reduction in the household
waste that is recycled.  Only six local authorities out of the 32 managed to improve performance. 
Full details on our response with partners to the Covid-19 pandemic can be found in our 2020/21
‘Supporting North Ayrshire Together’ six monthly reports available on our website www.north-
ayrshire.gov.uk/performance. 
Comparison Year No. of Indicators %
Short Term 82 81%
Medium Term 82 81%
Long Term 57 56%
136

Page 137

Page 4 of 45
Areas Expected to be Most Impacted by Covid-19 
Indicator 18/19 Data 19/20 Data 20/21 Data Family
Group 
19/20
Family
Group
20/21
Short Term
Variance
2019/20 to
2020/21*
Cost per attendance
at sports facilities £1.90 £1.91 £50.35 3 5 -2536%
Cost per library visit £2.62 £2.35 £4.29 6 5 -83%
Cost per visit to
Museums & Galleries £0.43 £0.42 £0.49 1 1 -16.67%
Cost of parks & open
spaces per 1,000
population
£19,798.12 £24,098.33 £15,836.13 5 4 34%
Overall Average Total
Tariff 792.94 807.55 868.56 7 7 7%
Average Total Tariff
SIMD quintile 1 627.00 599.00 672.00 6 6 11%
Average total tariff
SIMD quintile 2 781.00 815.00 836.00 4 7 3%
Average total tariff
SIMD quintile 3 850.00 974.00 1041.00 4 2 6%
Average total tariff
SIMD quintile 4 1011.00 1055.00 1073.00 5 5 2%
Average total tariff
SIMD quintile 5 1157.00 1180.00 1184.00 4 6 0%
The cost per dwelling
of collecting council
tax
7.78 5.02 1.58 3 1 69%
Claimant Count as a %
of Working Age
Population
5.70 5.50 8.30 8 8 -51%
Claimant Count as a %
of 16-24 Population 6.63 6.47 10.59 8 8 -64%
No of business
gateway start-ups per
10,000 population
21.66 21.75 8.42 2 6 -61%
Proportion of people
earning less than the
real living wage
24.30 16.00 16.20 2 4 -1%
% of total household
waste arising that is
recycled
54.60 56.34 52.10 3 4 -8%
*Improved performance is shown as positive percentages.  Declined performance is shown as
negative percentages.  
137

Page 138

Page 5 of 45
Summary of Performance
Where a short-term comparison is available, 56% of all indicators have improved, 1% have not
changed and 43% have declined (though 17% have declined only marginally).   Medium-term, 57% of
indicators have improved and long-term, 72% have improved.  The table below examines this in more
detail.   
*Marginal decline - where the variance is less than 5%. 
Our LGBF Indicators Overview 
Short-Term Medium-Term Long-Term  
Number Percent Number Percent Number Percent 
Improving Performance 46 56% 47 57% 41 72% 
No Change 1 1% 0 0% 0 0% 
Marginal Decline* 14 17% 10 12% 5 9% 
Declining Performance 21 26% 25 30% 11 19%
138

Page 139

Page 6 of 45
As shown below, when viewed per genre over the short-term (one year) period, 57% of financial
indicators and 56% of performance indicators have improved.    Over the long-term (next page) 56%
of financial indicators and 80% of performance indicators have improved.  Overall, this shows the
majority of measures have improved over the past ten years in terms of financial and performance
indicators.   
As previously mentioned, there are no values for any of the 11 indicators relating to satisfaction for
2020/21.   
Our LGBF Indicators by Genre - Short-Term   
Financial Performance  
Number Percent Number Percent 
Improving Performance 16 57.1% 30 55.6% 
No Change 0 0% 1 1.9% 
Marginal Decline 4 14.3% 10 18.5% 
Declining Performance 8 28.6% 13 24.1% 
139

Page 140

Page 7 of 45
Our LGBF Indicators by Genre - Medium-Term   
Financial Performance  
Number Percent Number Percent 
Improving Performance 18 64.3% 29 53.7% 
No Change 0 0% 0 0% 
Marginal Decline 1 3.6% 9 16.7% 
Declining Performance 9 32.1% 16 29.6% 
Our LGBF Indicators by Genre - Long-Term   
Financial Performance  
Number Percent Number Percent 
Improving
Performance 10 55.6% 31 79.5% 
No Change 0 0% 0 0% 
Marginal Decline 2 11.1% 3 7.7% 
Declining Performance 6 33.3% 5 12.8%
140

Page 141

Page 8 of 45
Rank
Ranking is a useful tool in comparing performance between all 32 local authorities in Scotland,
however an increase in ranking does not necessarily correspond to better outcomes for our residents. 
The purpose of ranking is to easily identify local authorities we can approach to learn from.  An
accurate comparison is highly dependent on each council’s strategic approaches.  For example, a low
cost per visit indicator may result in an increased ranking, however cost per visit can be affected by a
decrease in the number of venues in the same way as an increase in the number of visitors.  Similarly,
the percentage of unemployed people assisted into work can be greatly affected by whether a local
authority is assisting highly skilled unemployed residents, or those who need substantial support. 
Ranking is therefore a useful tool but must be used cautiously.
Our Council has been ranked in the top three for 11% of our indicators for the past two years:  
Top Three Ranking
Comparison Year No. of Indicators %
2020/21 11 12%
2019/20 10 11%
2017/18 9 10%
2011/12 3 5% 
We have seen an improvement in rank for 45% of indicators, a decline in rank for 39% of indicators
with the remaining 16% the same as the previous year.  The medium term shows 44% of indicators
improved their rank.  Over the long term, 49% of indicators have improved ranks, though fewer
comparisons are available.  The table below looks at this in more detail. 
Our Overall LGBF Performance - Rank 
Short-Term Medium-Term Long-Term  
Number Percent Number Percent Number Percent 
Improving
Performance 37 45% 36 44% 28 49% 
No Change 13 16% 10 12% 5 9% 
Declining
Performance 32 39% 36 44% 24 42%
141

Page 142

Page 9 of 45
Quartile
Quartiles group the rankings into four sections, with the 1st Quartile showing ranking positions 1-8 for
each local authority and the 4th Quartile showing ranks 25-32.  It is less prone to fluctuations year on
year, particularly where results for all councils for an indicator are very similar.  In the short term, 83%
of indicators have either improved or not changed their quartile.  In the long-term, 32% of indicators
have improved their quartile, with 23% declining.
‘No-change’ can be the result of our Council already being in the top quartiles, so is not necessarily an
indication of poor performance.  For 2020/21 and 2019/20, there were 22 indicators in the first
quartile.  17 indicators have remained in the top quartile since 2019/20.  The chart below shows our
quartile performance in the short, medium and long term. 
Our Overall LGBF Performance - Quartiles 
Short-Term Medium-Term Long-Term  
Number Percent Number Percent Number Percent 
Improving Performance 15 18% 18 22% 18 32% 
No Change 53 65% 44 54% 26 46% 
Declining Performance 14 17% 20 24% 13 23% 
142

Page 143

Page 10 of 45
Scottish Average
This section looks at our performance compared to the Scottish Average.  Our performance is above
the Scottish Average for 50% of the indicators during 2020/21.  This is similar to 2017/18 when we
performed better in 53% of the indicators.  In 2011/12 and 2019/20, we only performed better than
the Scottish Average in 39% and 47% of the indicators. The table below looks at this in further detail. 
Scottish Average 
2011/12 2017/18 2019/20 2020/21  
Percent Percent Percent Percent 
Above Scottish
Average 39% 53% 47% 50% 
Same as Scottish
Average 0% 2% 0% 1% 
Below Scottish
Average 61% 45% 53% 49 % 
143

Page 144

Page 11 of 45
Council Plan Indicators
Our Council Plan sets out our priorities for the period 2019-24.  Our Council Plan is supported by the
Council Plan Performance Framework which includes 34 performance indicators (including eight LGBF
indicators).  For context, within our Council Plan as at 2020/21, performance had improved in 19
(59.4%) and declined in 13 (40.6%).  There was no comparative data is available for two indicators.  In
terms of the eight LGBF indicators within our Council Plan, performance increased in four. 
Council Plan LGBF Indicators 
Number of Indicators    
Total
Aspiring Communities 2 1 0 3
Inspiring Place 2 3 0 5
A Council For The Future 0 0 0 0
Overall (Number) 4 4 0 8
Overall (Percent) 50% 50% 0% 100% 
144

Page 145

Page 12 of 45 
Council Plan LGBF Indicators - Performance Rank and Quartile  
Performance Rank Quartile  
19/20 20/21 Data
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
Proportion of Pupils Entering Positive Destinations 92.45% 95.2%  23 23  3 3 
Proportion of people earning less than the living wage 16% 16.2%  9 12  2 2 
% of people aged 65 and over with long-term care
needs receiving personal care at home 67.6% 69.5%  5 4  1 1 
% of operational buildings that are suitable for their
current use 90.89% 91.1%  10 9  2 2 
Proportion of properties receiving superfast broadband 94.1% 94.7%  17 17  3 3 
% of council dwellings meeting Scottish Housing
Standards 99.36% 99.1%  2 1  1 1 
Street Cleanliness Score 94.64 91.3  11 18  2 3 
% of total household waste arising that is recycled 56.34% 52.1%  6 7  1 1 
145

Page 146

Page 13 of 45
Council Plan LGBF Indicators – Scottish Rank (SR) and Family Group (FG) 
2011/12 2017/18 2019/20 2020/21 Movement
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend
CHN11 Proportion of Pupils Entering Positive Destinations 18 5 10 1 23 5 23 5      
ECON7 Proportion of people earning less than the living wage - - 17 3 9 2 12 4     - -
SW3a % of people aged 65 and over with long-term care needs
receiving personal care at home 21 6 11 5 5 3 4 2      
CORP-ASSET1 % of operational buildings that are suitable for their current
use 3 1 11 4 10 3 9 2      
ECON8 Proportion of properties receiving superfast broadband - - 18 4 17 3 17 3     - -
HSN3 % of council dwellings meeting Scottish Housing Standards 6 5 4 1 2 1 1 1      
ENV3c Street Cleanliness Score 9 2 20 6 11 2 18 5      
ENV6 % of total household waste arising that is recycled 7 4 7 2 6 3 7 4      
146

Page 147

Page 14 of 45
Family Groups
Family groups enable local authorities to make as close to a like for like comparison as possible with
other councils by grouping those within similar traits such as levels of rurality or deprivation.   
North Ayrshire Council’s LGBF Family Groups
People Services (Family Group 4) Other Services (Family Group 2) 
For indicators relating to Children, Social Work
and Housing, North Ayrshire Council is grouped
with the following Councils: 
• Comhairle nan Eilean Siar
• Dundee City Council
• East Ayrshire Council
• North Lanarkshire Council
• Inverclyde Council
• West Dunbartonshire Council
• Glasgow City Council     
For indicators relating to Corporate Services,
Culture & Leisure, Economic Development,
Environmental Services, Financial Sustainability
and Tackling Climate Change, North Ayrshire
Council is grouped with the following Councils: 
• Perth and Kinross Council
• Stirling Council
• Moray Council
• South Ayrshire Council
• East Ayrshire Council 
• East Lothian Council
• Fife Council 
Direct comparisons with all Scottish local authorities are available through the Improvement Service
“My Local Council” online tool.
The charts below segment our performance in terms of percentage of indicators in each rank within
each family group.  Not all local authorities provided data for all indicators in the most recent LGBF
data release.  The following charts are based on available data. 
147

Page 148

Page 15 of 45
During 2020/21, within the People Services Family Group 14% of our indicators were ranked at
number one and 58% were ranked between one and four.  Only 2% of People Services Family Group
indicators were ranked lowest at rank eight. 
People Services Family Group Comparison 
Within the Other Services Family Group 15% of all indicators were ranked at number one and 57% of
our indicators were ranked one to four.  In comparison, 11% of our indicators in the Other Services
Family Group were ranked lowest in rank eight. 
Other Services Family Group Comparison 
148

Page 149

Page 16 of 45
Directorates and Services
This section explores the LGBF performance of our directorates and services. 
Chief Executive Services
Our Chief Executive Services have a total of 13 LGBF indicators.  These are split by the following:
Financial 6
Performance 7
Satisfaction 0 
Financial 
Of the financial indicators that fall under the Chief Executive services, in the short-term and medium-
term, 67% of the indicators have seen an improvement in performance.
Chief Executive – Financial Indicators Breakdown Short Term 
149

Page 150

Page 17 of 45
Chief Executive Services – Financial Indicators - Performance Rank and Quartile  
Performance Rank Quartile  
19/20 20/21 Performance
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
The cost per dwelling of collecting council tax £5.02 £1.58  5 1  1 1 
Cost per attendance at sports facilities £1.91 £50.35  8 22  1 3 
Total useable reserves as a % of council annual
budgeted revenue 11.4 19.3  26 23  4 3 
Uncommitted General Fund Balance as a % of council
annual budgeted net revenue 2.8 3.2  11 10  2 2 
Ratio of Financing Costs to Net Revenue Stream -
General Fund 4.5 3  6 3  1 1 
Ratio of Financing Costs to Net Revenue Stream -
Housing Revenue Account 17.1 17.7  10 9  2 2 
150

Page 151

Page 18 of 45 
Chief Executive Services – Financial Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
CORP 4 The cost per dwelling of collecting council tax 15 5 16 6 5 3 1 1       
C&L1 Cost per attendance at sports facilities 24 5 10 4 8 3 22 5       
FINSUS1 Total useable reserves as a % of council annual budgeted
revenue - - 22 5 26 6 23 6     - - 
FINSUS2 Uncommitted General Fund Balance as a % of council
annual budgeted net revenue - - 24 8 11 4 10 4     - - 
FINSUS3 Ratio of Financing Costs to Net Revenue Stream - General
Fund - - 4 1 6 1 3 1     - - 
FINSUS4 Ratio of Financing Costs to Net Revenue Stream - Housing
Revenue Account - - 5 2 10 3 9 2     - -
151

Page 152

Page 19 of 45
Performance 
Of the performance indicators that fall under the Chief Executive services, in the short-term, 71% of
the indicators have improved.  This is in comparison for the medium-term which saw improvement
in 57% of the indicators.   
152

Page 153

Page 20 of 45
Chief Executive Services – Performance Indicators – Performance, Rank and Quartile  
Performance Rank Quartile  
19/20 20/21 Performance
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
Support services as a % of total gross expenditure 2.71 2.67  2 2  1 1 
% of the highest paid 5% employees who are women 60.79 61.92  5 5  1 1 
The gender pay gap (%) 1.78 1.31  12 9  2 2 
Sickness absence days per employee (non-teacher) 8.94 9.24  1 15  1 2 
% of income due from council tax received by the end of
the year 93.35 92.09  32 31  4 4 
% of invoices sampled that were paid within 30 days 93.27 93.96  16 16  2 2 
% of procurement spend spent on local enterprises 16.65 17.89  27 26  4 4 
153

Page 154

Page 21 of 45
Chief Executive Services – Performance Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
CORP 1 Support services as a % of total gross expenditure 2 1 2 1 2 1 2 1       
CORP 3b % of the highest paid 5% employees who are women 8 1 10 3 5 2 5 2       
CORP 3c The gender pay gap (%) - - 7 2 12 5 9 3     - - 
CORP 6b Sickness absence days per employee (non-teacher) 10 2 13 5 1 1 15 6       
CORP 7 % of income due from council tax received by the end of the
year 30 8 29 7 32 8 31 8       
CORP 8 % of invoices sampled that were paid within 30 days 29 7 21 5 16 4 16 4      
 ECON4 % of procurement spend spent on local enterprises 28 7 23 5 27 6 26 7      
154

Page 155

Page 22 of 45
Connected Communities Service
Our Connected Communities Service has six LGBF indicators.  These are split by the following:
Financial 2
Performance 0
Satisfaction 4
There is no satisfaction data for 2020/21 
Financial 
There are only two financial indicators that fall under the Connected Communities Service, in the
short-term, none of the indicators showed improved performance.  This is in comparison to the
medium-term which saw improved performance in one indicator. 
Connected Communities – Financial Indicators Breakdown 
155

Page 156

Page 23 of 49
Connected Communities Service – Financial Indicators – Performance, Rank and Quartile  
Performance Rank Quartile  
19/20 20/21 Performance
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
Cost per library visit £2.35 £4.29  19 14  3 2 
Cost of museums per visit £0.42 £0.49  2 4  1 1 
Connected Communities Service – Financial Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend  
Cost per library visit 7 2 14 5 19 6 14 5        
Cost of museums per visit 4 1 3 1 2 1 4 1      
156

Page 157

Page 24 of 49
Education Service
Our Education Service has a total of 27 LGBF indicators.  These are split by the following:
Financial 3
Performance 23
Satisfaction 1
There is no satisfaction data for 2020/21 
Financial 
These indicators relate to cost per pre-school, primary and secondary pupil.  Of the Education Service’s
financial indicators, 33% have improved in the short term and medium term.  Due to the particular
challenges North Ayrshire faces in terms of deprivation, a higher investment in our young people
relative to other local authorities (shown as declining performance in terms of rank) should not
necessarily be viewed as negative performance. 
Education – Financial Indicators Breakdown 
157

Page 158

Page 25 of 49
Education Service – Financial Indicators – Performance, Rank and Quartile 
Performance Rank Quartile  
19/20 20/21 Performance
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
Cost Per Primary School Pupil £6,670 £6,710  27 28  4 4 
Cost per Secondary School Pupil £8,252 £7,945  21 25  3 4 
Cost per Pre-School Education Registration £8,638 £9,749  27 19  4 3 
Education Service – Financial Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
CHN1 Cost Per Primary School Pupil 27 7 16 4 27 6 28 7       
CHN2 Cost per Secondary School Pupil 19 4 28 7 21 4 25 6       
CHN3 Cost per Pre-School Education Registration 24 3 23 5 27 6 19 3       
158

Page 159

Page 26 of 49
Performance 
Of the non-financial / satisfaction indicators assigned to our Education Service, 87% have seen an
improvement in performance in the short-term.  This is in comparison to the medium-term where
73% of the indicators saw improved performance.   
Education – Performance Indicators Breakdown 
159

Page 160

Page 27 of 49
Education Service – Performance Indicators – Performance, Rank and Quartile  
Performance Rank Quartile  
19/20 20/21
Performance
-/+  19/20 20/21
Rank
-/+ 19/20 20/21
Quartile
-/+
% of Pupils Gaining 5+ Awards at Level 5 61 65  20 20  3 3 
% of Pupils Gaining 5+ Awards at Level 6 33 35  22 23  3 3 
% of Pupils from Deprived Areas Gaining 5+ Awards at
Level 5 (SIMD) 46 54  10 8  2 1 
% of Pupils from Deprived Areas Gaining 5+ Awards at
Level 6 (SIMD) 19 23  13 12  2 2 
Proportion of Pupils Entering Positive Destinations 92.45 95.2  23 23  3 3 
Overall Average Total Tariff 808 869  27 29  4 4 
Average Total Tariff SIMD quintile 1 599 672  17 14  3 2 
Average Total Tariff SIMD quintile 2 815 836  9 15  2 2 
Average Total Tariff SIMD quintile 3 974 1041  11 8  2 1 
Average Total Tariff SIMD quintile 4 1055 1073  13 17  2 3 
Average Total Tariff SIMD quintile 5 1180 1184  15 21  2 3 
% of P1, P4 and P7 pupils combined achieving expected
CFE Level in Literacy - 58.60 - - 30 - - 4 -
% of P1, P4 and P7 pupils combined achieving expected
CFE Level in Numeracy - 67.36 - - 30 - - 4 -
Literacy Attainment Gap (P1,4,7 Combined) -
percentage point gap between the least deprived and
most deprived pupils
- 21.47 - - 9 - - 2 -
160

Page 161

Page 28 of 49
Education Service – Performance Indicators – Performance, Rank and Quartile  
Performance Rank Quartile  
19/20 20/21
Performance
-/+  19/20 20/21
Rank
-/+ 19/20 20/21
Quartile
-/+
Numeracy Attainment Gap (P1,4,7 Combined) -
percentage point gap between the least deprived and
most deprived pupils
- 23.61 - - 18 - - 3 -
% of children meeting developmental milestones 83.27% 82.24%  23 25  3 4 
% of funded early years provision which is graded
good/better 96.5% 98.15%  8 2  1 1 
School attendance rate - 91.4% - - 26 - - 4 -
School attendance rate (Looked After Children) - 88.78% - - 10 - - 2 -
School exclusion rates (per 1,000 pupils) - 9.57 - - 9 - - 2 -
School exclusion rates (per 1,000 'looked after children') - 32 - - 1 - - 1 -
Participation rate for 16-19 year olds (per 100) 90.56 90.12  26 29  4 4 
Sickness absence days per teacher 5.53 4.78  11 25  2 4 
161

Page 162

Page 29 of 49
Education Service - Performance Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
CHN4 % of Pupils Gaining 5+ Awards at Level 5 29 6 21 4 20 4 20 3       
CHN5 % of Pupils Gaining 5+ Awards at Level 6 28 6 23 4 22 4 23 4       
CHN6 % of Pupils from Deprived Areas Gaining 5+ Awards at Level
5 (SIMD) 10 4 10 4 10 4 8 2       
CHN7 % of Pupils from Deprived Areas Gaining 5+ Awards at Level
6 (SIMD) 7 3 12 4 13 4 12 4      
 CHN11 Proportion of Pupils Entering Positive Destinations 18 5 10 1 23 5 23 5       
CHN12a Overall Average Total Tariff 30 7 20 4 27 7 29 7       
CHN12b Average Total Tariff SIMD quintile 1 8 3 9 2 17 6 14 6       
CHN12c Average Total Tariff SIMD quintile 2 26 8 6 2 9 4 15 7       
CHN12d Average Total Tariff SIMD quintile 3 17 6 4 2 11 4 8 2       
CHN12e Average Total Tariff SIMD quintile 4 14 5 14 6 13 5 17 5       
CHN12f Average Total Tariff SIMD quintile 5 18 4 14 4 15 4 21 6       
CHN13a % of P1, P4 and P7 pupils combined achieving expected CFE
Level in Literacy - - - - - - 30 7 - - - - - -
162

Page 163

Page 30 of 49
Education Service - Performance Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
CHN13b % of P1, P4 and P7 pupils combined achieving expected CFE
Level in Numeracy - - - - - - 30 7 - - - - - - 
CHN14a Literacy Attainment Gap (P1,4,7 Combined) - percentage
point gap between the least deprived and most deprived
pupils
- - - - - - 9 3 - - - - - - 
CHN14b Numeracy Attainment Gap (P1,4,7 Combined) - percentage
point gap between the least deprived and most deprived
pupils
- - - - - - 18 5 - - - - - - 
CHN17 % of children meeting developmental milestones - - 26 4 23 1 25 4       
CHN18 % of funded early years provision which is graded
good/better 15 4 9 3 8 2 2 1       
CHN19a School attendance rate - - - - - - 26 3 - - - - - - 
CHN19b School attendance rate (Looked After Children) - - - - - - 10 1 - - - - - - 
CHN20a School exclusion rates (per 1,000 pupils) - - - - - - 9 2 - - - - - - 
CHN20b School exclusion rates (per 1,000 'looked after children') - - - - - - 1 1 - - - - - - 
CHN21 Participation rate for 16-19 year olds (per 100) - - 24 3 26 4 29 7     - - 
CORP 6a Sickness absence days per teacher all 11 5 15 4 11 4 25 7      
163

Page 164

Page 31 of 49
Place Directorate
The Place Directorate has a total of 37 LGBF indicators.  These are split as follows:
Financial 11
Performance 24
Satisfaction 2
There is no satisfaction data for 2020/21
Financial 
Of the financial indicators that fall under the Place Directorate, in the short-term, 64% of the indicators
show improved performance.  The medium-term shows an improvement across 73% of the indicators.   
Place – Financial Indicators Breakdown 
164

Page 165

Page 32 of 49
Place Directorate – Financial Indicators – Performance, Rank and Quartile 
Performance Rank Quartile  
19/20 20/21 Performance
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
Cost of parks & open spaces per 1,000 population £24,098 £15,836  21 14  3 2 
Net cost of waste collection per premise £58.39 £63.62  13 12  2 2 
Net cost of waste disposal per premise £103.52 £93.56  15 9  2 2 
Net cost of street cleaning per 1,000 population £16,958 £17,929  24 26  3 4 
Cost of roads per kilometre £10,632 £10,806  16 19  2 3 
Cost of Trading Standards and environmental health per
1,000 population £12,445 £10,734  1 1  1 1 
Cost of Trading Standards per 1000 £2,771 £2,078  1 2  1 1 
Cost of environmental health per 1,000 population £9,674 £8,655  5 5  1 1 
Cost of planning and building standards Per Planning
Application £4,494 £4,224  17 8  3 1 
Investment in of Economic Development & Tourism per
1,000 Population £115,560 £90,026  23 23  3 3 
Gross Value Added (GVA) per capita £16,973 £16,372  28 26  4 4 
165

Page 166

Page 33 of 49
Place Directorate – Financial Indicators – Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
C&L4 Cost of parks & open spaces per 1,000 population 27 7 22 6 21 5 14 4       
ENV1a Net cost of waste collection per premise - - 7 3 13 3 12 3     - - 
ENV2a Net cost of waste disposal per premise - - 12 6 15 7 9 5     - - 
ENV3a Net cost of street cleaning per 1,000 population 27 8 21 6 24 6 26 6       
ENV4a Cost of roads per kilometre 14 4 16 5 16 5 19 7       
ENV5  Cost of Trading Standards and environmental health
per 1,000 population 23 5 3 2 1 1 1 1       
ENV5a Cost of Trading Standards per 1000 - - 7 3 1 1 2 1     - - 
ENV5b Cost of environmental health per 1,000 population - - 6 3 5 1 5 2     - - 
ECON2 Cost of planning and building standards Per Planning
Application 23 7 13 5 17 4 8 2       
ECON6 Investment in of Economic Development & Tourism
per 1,000 Population 18 7 26 8 23 8 23 7       
ECON11 Gross Value Added (GVA) per capita 28 7 30 8 28 7 26 6       
166

Page 167

Page 34 of 49
Performance 
Of the performance indicators within the Place Directorate, 33% of the indicators have improved
performance in the short-term and 38% improved in the medium-term.   
Place Directorate – Performance Indicators Breakdown 
167

Page 168

Page 35 of 45
Place Directorate – Performance Indicators – Performance, Rank and Quartile  
Performance Rank Quartile  
19/20 20/21
Performance
-/+  19/20 20/21
Rank
-/+ 19/20 20/21
Quartile
-/+
Street Cleanliness Score 94.64 91.34  11 18  2 3 
% of A Class roads that should be considered for
maintenance treatment 38.78 36.3  30 29  4 4 
% of B Class roads that should be considered for
maintenance treatment 36.83 32.6  25 18  4 3 
% of C Class roads that should be considered for
maintenance treatment 46.93 44.9  30 31  4 4 
% of U Class roads that should be considered for
maintenance treatment 33.65 35.6  11 16  2 2 
% of total household waste arising that is recycled 56.34 52.1  6 7  1 1 
Gross rent arrears (all tenants) as at 31 March each year
as a percentage of rent due for the reporting year 3.65 5.46  3 5  1 1 
% of rent due in the year that was lost due to voids 0.61 0.47  4 2  1 1 
% of council dwellings meeting Scottish Housing
Standards 99.36 99.09  2 1  1 1 
Average number of days taken to complete non-
emergency repairs 6.3 9.75  9 16  2 2 
% of council dwellings that are energy efficient 98.38 97.58  2 2  1 1 
% of operational buildings that are suitable for their
current use 90.89 91.05  10 9  2 2 
% of internal floor area of operational buildings in
satisfactory condition 94 94  12 11  2 2 
% of unemployed people assisted into work from
council operated / funded employability programmes 20.13 9.06  6 8  1 1 
168

Page 169

Page 36 of 45
Place Directorate – Performance Indicators – Performance, Rank and Quartile  
Performance Rank Quartile  
19/20 20/21
Performance
-/+  19/20 20/21
Rank
-/+ 19/20 20/21
Quartile
-/+
Average time per business and industry planning
application (weeks) 5.1 5.41  1 1  1 1 
No of business gateway start-ups per 10,000 population 21.75 8.42  5 24  1 3 
Proportion of people earning less than the living wage 16% 16.2  9 12  2 2 
Proportion of properties receiving superfast broadband 94.1% 94.7  17 17  3 3 
Town Vacancy Rates 12.55% 13.26  12 11  2 2 
Immediately available employment land as a % of total
land allocated for employment purposes in the local
development plan
60.82% 45.77  10 14  2 2 
Claimant Count as a % of Working Age population 5.5 8.3  32 32  4 4 
Claimant Count as a % of 16-24 Population 6.47 10.59  30 32  4 4 
CO2 emissions area wide per capita 6.07 5.43  25 24  4 3 
CO2 emissions are wide: emissions within scope of LA
per capita 5.68 5.07  24 23  3 3 
169

Page 170

Page 37 of 45 
Place Directorate- Performance Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend
 ENV3c Street Cleanliness Score 9 2 20 6 11 2 18 5       
ENV4b % of A Class roads that should be considered for
maintenance treatment 30 8 28 6 30 7 29 7       
ENV4c % of B Class roads that should be considered for
maintenance treatment 28 6 25 4 25 5 18 3       
ENV4d % of C Class roads that should be considered for
maintenance treatment 30 8 31 8 30 8 31 8       
ENV4e % of U Class roads that should be considered for
maintenance treatment 19 5 15 5 11 3 16 4      
 ENV6 % of total household waste arising that is recycled 7 4 7 2 6 3 7 4       
HSN1b Gross rent arrears (all tenants) as at 31 March each year as
a percentage of rent due for the reporting year - - 3 1 3 1 5 1     - - 
HSN2 % of rent due in the year that was lost due to voids 1 1 1 1 4 1 2 1      
 HSN3 % of council dwellings meeting Scottish Housing Standards 6 1 4 1 2 1 1 1       
HSN4b Average number of days taken to complete non-emergency
repairs - - 6 3 9 3 16 5     - -
170

Page 171

Page 38 of 45
Place Directorate- Performance Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
HSN5a % of council dwellings that are energy efficient - - 2 2 2 2 2 2      
 CORP-
ASSET1
% of operational buildings that are suitable for their current
use 3 1 11 4 10 3 9 2       
CORP-
ASSET2
% of internal floor area of operational buildings in
satisfactory condition 20 5 1 1 12 3 11 3       
ECON1 % of unemployed people assisted into work from council
operated / funded employability programmes - - 6 3 6 2 8 2     - - 
ECON3 Average time per business and industry planning application
(weeks) - - 1 1 1 1 1 1     - - 
ECON5 No of business gateway start-ups per 10,000 population - - 7 2 5 2 24 6     - -
 ECON7 Proportion of people earning less than the living wage - - 17 3 9 2 12 4     - -
 ECON8 Proportion of properties receiving superfast broadband - - 18 4 17 3 17 3     - - 
ECON9 Town Vacancy Rates - - 14 5 12 6 11 6     - - 
ECON10
Immediately available employment land as a % of total land
allocated for employment purposes in the local
development plan
- - 6 1 10 2 14 3     - - 
ECON12a Claimant Count as a % of Working Age population 31 8 31 8 32 8 32 8      
171

Page 172

Page 39 of 45
Place Directorate- Performance Indicators - Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
ECON12b Claimant Count as a % of 16-24 Population 31 8 30 8 30 8 32 8       
CLIM1 CO2 emissions area wide per capita 23 4 25 3 25 3 24 4       
CLIM2 CO2 emissions are wide: emissions within scope of LA per
capita 23 4 22 4 24 4 23 4      
172

Page 173

Page 40 of 45
Health and Social Care Partnership
The Health and Social Care Partnership has a total of 18 LGBF indicators assigned to them.  These are
as follows:
Financial 6
Performance 8
Satisfaction 4
There is no satisfaction data for 2020/21 
Financial 
Of the financial indicators that fall under the HSCP, in the short-term, 67% of the indicators have
seen an improvement in performance, this was also the case in the medium-term.   
HSCP – Financial Indicators Breakdown 
173

Page 174

Page 41 of 45 
HSCP – Financial Performance – Performance, Rank and Quartile  
Performance Rank Quartile  
19/20 20/21 Performance
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
The Gross Cost of "Children Looked After" in Residential
Based Services per Child per Week £3,839 £3,209  15 6  2 1 
The Gross Cost of "Children Looked After" in a
Community Setting per Child per Week £330 £376  15 19  2 3 
% of children living in poverty (after housing costs) 27.92 24.73  31 31  4 4 
Home care costs per hour for people aged 65 or over £31.67 £29.82  25 21  4 3 
Residential costs per week per resident for people aged
65 or over £399 £369  13 11  2 2 
Actual outturn as a percentage of budgeted expenditure £99.32 £89.59  15 31  2 4 
174

Page 175

Page 42 of 45
HSCP – Financial Performance – Performance, Rank and Quartile 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
4F6amily Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
CHN8a The Gross Cost of "Children Looked After" in Residential
Based Services per Child per Week 17 3 13 4 15 4 6 3       
CNH8b The Gross Cost of "Children Looked After" in a Community
Setting per Child per Week 14 5 17 6 15 5 19 7       
CHN24 % of children living in poverty (after housing costs) - - 31 7 31 7 31 2     - - 
SW1 Home care costs per hour for people aged 65 or over 14 5 26 7 25 5 21 5       
SW5 Residential costs per week per resident for people aged 65
or over 6 1 14 3 13 3 11 3       
FINSUS5 Actual outturn as a percentage of budgeted expenditure - - 31 8 15 5 31 8     - - 
175

Page 176

Page 43 of 45
Performance 
Of the performance indicators assigned to the HSCP, 50% of the indicators have seen an
improvement in performance in the short term and 63% have seen an improvement in the medium
term.
HSCP – Performance Indicators Breakdown 
176

Page 177

Page 44 of 45  
Performance Rank Quartile  
19/20 20/21 Performance
-/+  19/20 20/21 Rank
-/+ 19/20 20/21 Quartile
-/+
% of children being looked after in the community 90.26% 89.27%  15 16  2 2 
% of child protection re-registrations within 18 months 15.04% 8.4%  29 21  4 3 
% LAC with more than 1 placement in the last year (Aug-
July) 18.26% 21.65%  14 26  2 4 
Self Directed Support (Direct Payments + Managed
Personalised Budgets) spend on adults 18+ as a % of
total social work spend on adults 18+
3.56% 3.96%  26 23  4 3 
% of people aged 65 and over with long-term care
needs receiving personal care at home 67.63% 69.51%  5 4  1 1 
Rate of readmission to hospital within 28 days per 1,000
discharges 112.25 121.4  20 19  3 3 
Proportion of care services graded 'good' (4) or better in
Care Inspectorate inspections 87.6% 87.2%  9 11  2 2 
Number of days people spend in hospital when they are
ready to be discharged, per 1,000 population (75+) 1328.71 381.64  30 18  4 3 
177

Page 178

Page 45 of 45
HSCP – Performance Indicators – Detail 
2011/12 2017/18 2019/20 2020/21 Movement
Council Plan PI (P) 
Reference
Description
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
Scottish Rank
Family Group Rank
SR Short-term
Trend
FG Short-term
Trend
SR Medium-term
Trend
FG Medium-term
Trend
SR Long-term
Trend
FG Long-term
Trend 
CHN9 % of children being looked after in the community 17 6 17 5 15 5 16 4       
CHN22 % of child protection re-registrations within 18 months - - 17 4 29 7 21 4     - - 
CHN23 % LAC with more than 1 placement in the last year (Aug-
July) 9 5 12 4 14 6 26 8       
SW2 Self Directed Support (Direct Payments + Managed
Personalised Budgets) spend on adults 18+ as a % of total
social work spend on adults 18+
23 4 29 6 26 5 23 5      
 SW3a % of people aged 65 and over with long-term care needs
receiving personal care at home 21 6 11 5 5 3 4 2       
SW6 Rate of readmission to hospital within 28 days per 1,000
discharges 22 5 22 6 20 6 19 5       
SW7 Proportion of care services graded 'good' (4) or better in
Care Inspectorate inspections 32 8 16 5 9 3 11 3       
SW8 Number of days people spend in hospital when they are
ready to be discharged, per 1,000 population (75+) - - 26 7 30 7 18 4     - - 
178

Page 179

Page 46 of 45 
The Corporate Policy, Performance and Elections Team welcome any feedback you may have.  We strive to make
our Council and reports as accessible as possible and appreciate opportunities to discuss how this can be achieved. 
For further information please contact: 
The Corporate Policy, Performance and Elections Team 
Tel: 01294 324648 
Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk 
179

Page 180

180

Page 181

2,443
2,541
2,827
2019 2020 2021
NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    2021/22 Complaint Report 
Purpose:  To inform the Audit and Scrutiny Committee of the Council's
complaint performance and the volumes and trends of complaints
received in Financial Year 2021/22. 
Recommendation:  That the Committee notes the report and the information
provided. 
1. Executive Summary 
1.1 This report details complaint information relating to North Ayrshire Council during
2021/22, covering the period 1 April 2021 to 31 March 2022. 
1.2 To allow comparisons to be made the report also details some complaint data relating
to 2019 and 2020. 
1.3 Performance is measured through a number of Scottish Public Services Ombudsman
(SPSO) performance indicators, some of which have national targets. Reporting on
complaints is a statutory requirement and is monitored by Audit & Scrutiny.   
1.4    When considering the report it should be noted that the coronavirus pandemic continued
to cause disruption to the Council, however, services continued to operate and critical
and key services were maintained.   
2. Background 
2.1 This section contains statistical information and commentary on some of the key
complaint performance indicators.  More information relating to the indicators can be
found in the attached report. 
2.2 Volume of complaints received and closed 
Agenda Item 7
181

Page 182

2.2.1 Whilst Council services continued to be impacted by the pandemic during 2021, there
was a modest increase in complaints when compared with the previous year. 
2.3 Complaints closed at each Stage 
2019/20 2020/21 2021/22
Stage One 2,302 2,417 2,671
Stage Two 141 124 156 
2.3.1 Whilst there is no national target for the number of complaints to be closed under each
Stage, the Council always seeks to maximise closure at Stage One as complainants
receive a quicker resolution, it reduces the impact on complaint handler time and
reduces the possibility of SPSO referrals. 
2.4 Complaint outcomes 
Stage One         Stage Two                                                                   
2.4.1 Up to 31 March 2021, a complaint that meets our complaint criteria could be upheld,
partially upheld or not upheld. From 1 April 2021 a fourth outcome became available to
use called ‘Resolved’. Resolved complaints are where the Council has taken action to
address a problem or issue without making a decision on whether there were any failings
(this would happen where we agree a solution with the complainant at the outset without
needing to actually investigate the complaint). 
2.4.2 Analysis shows the majority of Resolved complaints related to missed bin collections,
where complainants simply wanted the bins collected.   
2.4.3 Half of all upheld and partially upheld complaints also related to Waste Services, however
it should be noted over 102,000 household waste bins are collected each week.  As this
equates to approximately 5 million collections a year, from a complaint perspective this
results in a small percentage complaint rate of 0.03%. 
2.4.4 Many complaints not upheld related to policies, regulations or complaints that turned out
to be unfounded after investigation. 
30%
8%
15%
47%
Upheld Partially Upheld Not Upheld Resolved
10%
33%55%
Upheld Partially Upheld Not Upheld Resolved (2%)
182

Page 183

2.5 Average time in working days for a full response at each Stage 
Stage One 
Stage Two 
2.5.1 The average time in working days for a response under both Stages has exceeded the
SPSO target response timescales for the last three years. 
2.6 Complaints closed within timescale 
Stage One                                                  Stage Two             
2.6.1 The national target for complaints closed on time under Stage One is 80% or above and
the target was exceeded.  The national target for complaints closed on time under Stage
Two is 85% or above and again this target was exceeded. 
2.6.2 Further details of complaints not closed on time are contained in the attached report. 
3.3
4.3 4.2
0
5
2019/20 2020/21 2021/22
average days to resolve National Target (5 days or less)
14.5 14.3 14.5
0
20
2019/20 2020/21 2021/22
average days to resolve National  Target (20 days or less)
84%
16%
Closed on time
Not closed on time
95%
5%
Closed on time
Not closed on time
183

Page 184

2.7 Complaint timescale extensions 
2.7.1 Stage One complaints should be responded to within 5 working days but can be extended
an additional 5 working days under certain circumstances.  Stage Two complaints should
be responded to within 20 working days but again Services can extend the timescale if
certain circumstances are met. 
2.7.2 A total of 106 complaints had their timescales extended during the year and over two thirds
were Stage Ones.  Reasons for extension included complainants and individuals being
unavailable to assist with investigations, additional information having to be sought to
support investigations and issues arising from the ongoing Covid-19 outbreak. 
2.8 Trends identified from upheld/partially upheld complaints 
Key complaint topics for upheld or partially upheld complaints are detailed on page 9
and 10 of the attached report. 
2.9 Changes or Improvements made as a result of complaints 
Not all Services can implement improvements as a result of complaints due to a number
of factors, including the feasibility of making changes and resource/budget
considerations. That said, improvements were made in some Services as a result of
complaints received during the year and a selection are noted in page 15 of the attached
report. 
2.10 Compliments 
The Council recorded over 240 compliments received during the year.  Some praised
specific individuals or teams, some related to more than one Service and some were
raised by employees complimenting other employees. A selection can be found in
page 16 of the attached report. 
3. Proposals 
3.1 It is proposed the Committee approves the report and now the Council’s complaint
handling performance. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
184

Page 185

Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The Two Stage Complaint Handling Procedure supports the Council's key priority of
delivering more effective and efficient service provision. It demonstrates commitment
through focussing on and determining trends to service improvement and delivery for
North Ayrshire residents, customers and visitors. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 None. 
Aileen Craig
Head of Democratic Services 
For further information please contact Darren Millar, Manager Information Governance,
on (01294) 322988. 
Background Papers
0
185

Page 186

Page | 1 
Corporate Complaints 
2021/22
186

Page 187

Page | 2 
Contents 
Page 
Introduction         3 
1 Volume of complaints closed      4 
2  Volume of complaints closed on time  at both Stages   7 
3 Volume of complaints not closed on time per Directorate     7 
4 Key complaint topics       9 
5 Average time in working days for a full response   11 
6  Extended complaints       13 
7 Complaint Outcomes                                                                    14 
8  Improvements made as a result of complaints                        15 
9 Compliments        16 
10 ALEO complaints        17 
11  SPSO complaint referrals      20 
12 Glossary         21  
187

Page 188

Page | 3 
Introduction 
North Ayrshire Council always seeks to deliver the best services possible to its
customers and residents but it is recognised that dissatisfaction will sometimes occur. 
When it does we want to know what went wrong, why it went wrong and what we can
do to make things right. 
The Council recognises valuable lessons can be learnt from complaints which are
defined as expressions of dissatisfaction from members of the public about actions, or
lack of actions, or about the standard of service provided by or on behalf of the Council.  
The Council’s complaint handling procedure (CHP) has two stages for handling
complaints from the public:- 
Stage One complaints (also known as Frontline Resolution complaints)
are straightforward, non-complex complaints the Council can resolve at
the initial point of contact or as close to the point of service delivery as
possible.  The Council has up to 5 working days to resolve these. 
Stage Two complaints (also known as Investigation complaints) are
complaints the Council is typically unable to resolve at Stage One and
requires more time to carry out further investigation.  This may be
because the nature of the complaint is complex, serious or high risk. 
The Council has up to 20 working days to resolve these. 
This report details the Council’s complaint handling performance covering financial
year 2021 (1 April 2021 to 31 March 2022).  Performance is measured via several
Scottish Public Services Ombudsman indicators (some of which have national targets)
and complaint data relating to previous years has been included in certain sections to
allow comparisons to be made.   
Reporting on complaints is a statutory requirement and is monitored by Audit Scotland. 
1
2
188

Page 189

Page | 4 
2,259
159
133 254 Place
Multi-Service (22)
Health & Social Care Partnership
Communities
Chief Executive's
1   Volume of complaints closed 
The Council received 2,859 complaints during 2021/22 and closed 2,827.  The chart below
provides a breakdown of the closed complaints per Directorate: 
The following tables highlight complaints closed per Directorate under each Stage: 
Place Stage One Stage Two
Building Services 208 4
Business Development - 1
Facilities Management 27 -
Housing  166 25
Planning 5 2
Property Management & Investment 74 4
Protective Services 9 1
Regeneration 2 -
Roads 88 6
Streetscene 129 1
Sustainability 2 -
Transport 2 -
Waste Services 1,498 5
Total 2,210 49 
Multi-Service Stage One Stage Two
Complaints involving more than one service 11 11
Total 11 11 
Health & Social Care Partnership Stage One Stage Two
Children, Families & Criminal Justice 31 23
Health & Community Care 65 24
Mental Health 3 4
Support Services 6 3
Total 105 54
189

Page 190

Page | 5 
Communities Stage One Stage Two
Community Facilities 2 -
Education (HQ) 31 24
Education (Schools) 60 9
Information & Culture 6 -
Sports & Activity 1 -
Total 100 33 
Chief Executive’s Stage One Stage Two
Committee & Member Services - 1
Customer Services 204 7
Financial Services 14 -
Fraud & Internal Audit 1 -
HR 1 -
Information Technology 20 -
Legal Services 5 1
Total 245 9 
• Although there is no target for the volume of complaints handled under each Stage,
the Council seeks to maximise closure at Stage One wherever possible and 94% were
handled at this Stage during the period.   
• Some Services handled all their complaints at Stage One. 
• Whilst 53% of all complaints received related to Waste Services (the majority being
missed bins and assisted pullouts), the Service empties over 102,000 household
waste bins each week.  As this equates to approximately 4.9 million collections over
the year, 0.03% of these collections resulted in complaints being raised. This is worth
highlighting given Waste Services experienced significant operational challenges due
to the Covid pandemic during the year and was still able to maintain a bin collection
service. 
• Multi-Service complaints have a table of their own as they are not attributable to a
specific Service. 
190

Page 191

Page | 6 
Year on Year comparison 
The graph below shows a comparison of the volume of complaints received each year over
the last three years: 
The table below shows the volume breakdown for each Directorate over the last three years
(based on the Council’s new 2020 structure): 
Directorate 2019  2020 2021 Variance
(2020 – 2021)
Chief Executive’s 188 176 254 +44%
Communities 136 90 133 +48%
HSCP (Social Work complaints) 125 127 159 +25%
Place 1,978 2,128 2,259 +6%
Total 2,427* 2,521* 2,805* +11%
*Multi-service complaints have been excluded to allow for true Directorate comparisons 
• Whilst the Council maintained various measures, policies, processes and practices to
combat the ongoing pandemic during 2021/22, there has only been an 11% increase in
complaints when comparing 2021 with the previous year. 
• The 44% uplift in Chief Executive complaints can be attributed to increases in Customer
Services, IT and Finance complaints. Key complaint topics are detailed in section 4 of this
report. 
• The 48% increase in Communities complaints is the result of a considerable uplift in
school-related complaints received. Key complaint topics are detailed in section 4 of this
report. 
2,443
2,541
2,827
2019 2020 2021
191

Page 192

Page | 7 
• The national target for closing Stage Two
complaints on time is 85% and above. 
• The volume closed on time includes
extended complaints that met their new
due dates.
• The national target for closing Stage One
complaints on time is 80% and above. 
• The volume closed on time includes
extended complaints that met their new
due dates.
84%
16%
Closed on time
Not closed on time
95%
5%
Closed on time
Not closed on time
6
27
Information Technology
Customer Services
1
14
4
2
Sports & Activity
Education (schools)
Education (HQ)
Community Facilities
2   Volume of complaints closed on time at both Stages 
Stage One 
Stage Two       
3   Volume of complaints not closed on time per Directorate 
This section provides details of complaints not closed on time under each Stage and includes
extended complaints that did not meet their new timescales. 
Stage One                    
Notes
Chief Executive’s 
Communities 
Customer Services complaints breached mainly due to
resourcing issues (including self-isolations) and delays in
obtaining information from complainants/3rd parties to
progress complaints.  Extensions could have been
considered for around 70% of these given they were closed
within the extra 5 working day extension allowance. IT
complaints breached due to the complexity of the system(s)
issues, awaiting further information from complainants and
complaints being incorrectly routed.  Extensions could have
been considered for 50% of these for the same reason given
above.
Some complaints breached due to complaint handlers being
unable to contact complainants in order to discuss or agree
the issues.  Some Education complaints also breached as
they were received when the schools were closed. 
Extensions could have been agreed for 60% of all
Communities complaints not closed on time given they were
closed within the extra 5 working day extension allowance. 
192

Page 193

Page | 8 
8
8
Health & Comm Care
Children & Families
288
1
1
26
6
5
3
2
16
Waste Services
Transport
Sustainability
Streetscene
Roads
PMI
Housing
Facilities Management
Building Services
HSCP (Social Work complaints) 
Place 
Waste Services (operations) complaints in 2021/22 
Waste Operations continued to operate under Covid-related restrictions for the full period of
2021/22 and additional labour was carried throughout the year to ensure vehicles could be
resourced.  Additional vehicle hires were also extended throughout 2021/22 as availability of
vehicles became a pinch point causing operational disruption and service disruption.   
The impact of Covid was seasonal with waves of absences following the general trends seen
in the wider community.  There was a particular peak as the omicron variant became prevalent
from the festive period into the second half of the winter. At one point a suspension of the
brown bin service was necessary in January as the omicron surge peaked. 
The service had to make operational decisions to prioritise resourcing beats unfortunately at
the expense of bin deliveries.  A focus has been undertaken to ensure priority is given to any
complaints relating to assisted collections.   
When reviewing the complaint data for Waste Service, particularly Waste Operations, it is
evident that despite significant operational challenges, the majority of bin collections took
place without issue. 
Reasons for complaints not closed on time included
complaint handlers being unavailable to progress
complaints for various reasons, complainants/3rd
parties being unavailable to assist with investigations,
resourcing issues related to Covid-19 and the
complexity of the complaints.   
Of the 348 Place complaints not closed on time, 64%
could have been considered for the extra 5 working day
extension given they were closed within 10 working
days. 
Regarding the volume of Waste complaints that did not
meet timescale, see additional commentary below. 
These complaints breached due to multiple reasons
and no specific trends were identified, however,
extensions could have been considered for some of
these given they were closed within the extra 5 working
day extension allowance.
193

Page 194

Page | 9 
1Health & Comm Care
1
2
Education (Schools)
Education (HQ)
2
1
PMI
Housing
Stage Two
Communities 
HSCP (Social Work complaints) 
Multi-Service 
Place 
4   Key complaint topics 
Key topics for upheld and partially upheld complaints for Services are listed below.  Services
will not be listed if there were low complaint volumes that did not allow meaningful analysis. 
Chief Executive’s
Service Key complaint topic(s)
Customer Services • Issues with Council Tax
• Communication
• System issues
• Waiting times
Information Technology • Systems issues 
1Multi-Service
These complaints were sensitive in nature and
required detailed  investigation.  Extensions could
have been considered for these.
This complaint breached by one day as approval was
required from a Chief Officer before the response
could be issued.
This complaint breached due to service pressures
caused by resourcing issues as a result of the
pandemic.
These complaints breached due to delays in the
Stage Two response letters being approved prior to
issue.
194

Page 195

Page | 10 
Communities
Service Key complaint topic(s)
Education (HQ) • Sensitive issues relating to teachers
and/or pupils
• Service provision/delivery 
HSCP (Social Work complaints) 
Service Key complaint topic(s)
Children & Families • Service provision/delivery
• Alleged employee behaviour
Health & Community Care • Service provision/delivery
• Alleged employee behaviour 
Place
Service Key complaint topic(s)
Building Services • Follow Up appointments
• Quality issues
Housing • Anti-social behaviour
PMI • Gas Central Heating (incl. maintenance)
Roads • Road conditions
Streetscene • Quality/lack of grass cutting
Waste Services • Missed collections (all colours)
• Missed pull out collections (all colours)
• Waste Bins not delivered (all colours)
• Failed special uplifts
• Alleged employee behaviour 
• ‘Alleged employee behaviour’ appears as a key topic for some Services but the definition
is broad and has been used where complainants perceived employee actions or
behaviour to be unacceptable.  Where unacceptable behaviour was identified by Services
appropriate action will have been taken to address.  
195

Page 196

Page | 11 
5   Average time in working days for a full response 
The average time in working days to close complaints under both Stages during the period is
noted below.  Values for previous years have been included to allow comparisons to be made
and any complaints that had their timescales extended have been excluded from the
calculations. 
Stage One 
Stage Two 
• The average time to close complaints under both Stages has consistently  exceeded
target. 
The bar charts on the following two pages detail Services that did not meet the average time
in working days for a response under either Stage.  Services that met the target are not listed
and any complaints that had their timescales extended have been excluded from the
calculations.  
3.3
4.3 4.2
0
5
2019/20 2020/21 2021/22
average days to resolve National Target (5 days or less)
14.5 14.3 14.5
0
20
2019/20 2020/21 2021/22
average days to resolve National  Target (20 days or less)
196

Page 197

Page | 12 
Chief Executive’s 
Stage One 
Two IT complaints that were received were resolved beyond 20 working days,
resulting in the average days to resolve target not being achieved.  One complaint
was hindered due to the delay caused by the complainant not providing further
information.  The other complaint involved a number of services and delays were
encountered in receiving their responses in order to address and fix the issue. 
Communities 
Stage One 
Two complaints were received for Community Facilities and one was closed
significantly beyond the 5 working day target due to resourcing issues in the service
and delays encountered when engaging the relevant community group to assist in
investigating the complaint. 
A small number of school complaints were closed significantly beyond the 5 working
day target as they had been received when the schools were closed for the summer
holidays and so could not be progressed. 
One Sports & Activity complaint was received and closed on day 8, breaching the
target.  This complaint could have been considered for the 5 working day extension.
6.3
IT
Average days to resolve
National Target (5 days)
20
6.7
8
Community
Facilities
Education
(Schools)
Sports & Activity
Average days to resolve National Target (5 days)
197

Page 198

Page | 13 
Place 
Stage One                                                                                     Stage Two           
A small number of Streetscene complaints were closed significantly beyond the 5
working day timescale, impacting on the average days to close.  Reasons for this
included difficulties in contacting complainants to progress complaints and the
complexities of the complaints.  Some of these complaints could have been
considered at Stage Two. 
Energy & Sustainability received two complaints during the year, one of which was
closed on working day 64.  The delay was due to multiple issues, including
bereavement leave, issues with the complaint being directed to the appropriate team
to investigate and a breakdown in communication between services involved. 
PMI closed a small number of Stage Two complaints during the year, two of which
were closed a few days beyond the 20 working day timescale.  The delay in closing
the complaints was due to the response requiring approval before being issued. 
6   Extended complaints 
• 106 complaints had their timescales extended during the year - 77 at Stage One and
29 at Stage Two.  The complaints related mainly to two Directorates - HSCP (30%) and
Place (40%). 
• There were numerous reasons for extending, including complainants, 3rd parties and
employees being unavailable to assist or support with investigations, additional
information having to be sought to support investigations and issues arising from the
ongoing pandemic (particular lack of resource through self-isolations). 
• Of the 106 complaints that had their timescales extended, 81% were closed within
their new due dates. 
5.3
34
Streetscene Sustainability
Average days to resolve National Target (5 days)
22
PMI
Average days to resolve
National Target (20 days)
198

Page 199

Page | 14 
30%
8%
15%
47%
Upheld Partially Upheld Not Upheld Resolved
7   Complaint Outcomes 
Up to 31 March 2021, a complaint that meets our complaint criteria could be upheld, partially
upheld or not upheld. From 1 April 2021, a fourth outcome became available to use called
‘Resolved’. Resolved complaints are where the Council has taken action to address the
problem/issue without making a decision on whether there were any failings (this would
happen where we agree a solution with the complainant at the outset without needing to
actually investigate the complaint). 
The charts below detail the number of complaints upheld, partially upheld, not upheld or
resolved under both Stages. 
Stage One 
Stage Two 
*Partially Upheld complaints are complaints that contain more than one complaint element and at least one of them is upheld
10%
33%55%
Upheld Partially Upheld Not Upheld Resolved (2%)
• All the Stage Two complaints that were upheld or
partially upheld* were split across all Directorates and
multiple services. 
• A very small number of complaints were marked as
‘Resolved’ at Stage Two.  As complaints can only typically
be ‘Resolved’ at Stage One, an investigation is underway
to determine if the outcomes for these complaints are
correct and if not, remedial action will be taken to
address. 
• Of the 55% of complaints not upheld, these related to
various reasons, including polices, regulations and
complaints that were unsubstantiated.
• Of the 38% of complaints upheld and partially upheld*
at Stage One, over half related to Waste Services and in
particular bin collections.  This was anticipated given
issues the service continued to experience as a result of
the pandemic. 
• Over two thirds of all Resolved complaints also related
to Waste Services (mainly missed bin collections) which
indicates many residents simply wanted their bins
collected. 
• The 15% of complaints not upheld related to policies,
regulations or complaints that were poor
quality/unfounded.
199

Page 200

Page | 15 
8   Improvements made as a result of complaints 
Council officers continually seek to make improvements in service delivery and complaint
information is analysed regularly to inform service improvements. The largest proportion of
complaints raised were experienced within Waste Services and work is ongoing to reflect
learning into service delivery arrangements and complaint processing practices to achieve a
reduction in complaints received. 
Many improvements were made as a result of complaints received during the year and a
selection is noted below. 
What happened? What we did
A customer advised they were in the process
of booking a special waste uplift when the
payment system went down.  This resulted
in the payment being taken but no uplift.
An apology was offered to the complainant, the
special uplift payment refunded and
consideration given to adding a statement to the
website advising customers what to do when
payment receipts are not generated.
This complaint was a sensitive matter
regarding a child and an additional support
needs Early Years (EY) placement.
An apology was offered to the complainant and
it was determined the criteria for the allocation
of places to be more clearly communicated with
families.  It was also agreed EY Management
would clarify the process with EY managers
regarding who makes contact with a new
provider when a child moves locality; EY
Management would clarify the start time for an
Early Years placement (on birthday or term after
birthday); to reconcile the Team Around the
Child process regarding the allocation of any
placement and to improve communication and
sharing of information in a timely fashion; full
assessment of needs to be shared with each
prospective setting to inform and help decisions
to be taken in a timely fashion.
A resident contacted the Council in order to
have their address updated as a new build
property but was unable to speak to
someone using the Street Naming &
Numbering (SNN) telephone number in
order to get issue resolved. 
An apology was offered to the complainant as it
was identified the telephone number was not
fully operational.  Use of a new communications
application has allowed the SNN telephone
phone number to become usable again and the
SNN page on the Council’s website will be
reviewed to ensure the most appropriate
contact details and information.
A customer complained as they called the
Council’s Contact Centre about a matter and
were placed in a queue, however the call
was then prematurely  terminated, resulting
in the customer having to call in a second
time and queue again to speak to someone.
A call-back queue has been introduced in the
Contact Centre which allows customers to
request a call back instead of holding on in a
queue. An apology was offered to the
complainant for the problems encountered.  
200

Page 201

Page | 16 
Compliment letter received from a bowling club
commending an employee from Licensing and an
employee from Environmental Health for their help
and support when adhering to Covid-19 restrictions
9   Compliments 
Over 240 compliments were recorded cross-Council during the year.  Although they cannot all
be highlighted in this report, a selection are noted below. 
“I’d like to commend the Streetscene fly-tipping
team.  Any reports I have made have been dealt
with quickly whether in the town or out in the
country.  Well done to all for which has so far been
an excellent service.”
Multiple compliments received for Waste
Services regarding returning to collect missed
bins, delivering new bins and the attitude of the
employees working at the Recycle Centres
“Quick response and excellent service from Pest
Control Officer from Environmental Health today.
He was very knowledgeable about wasps and bees
that I felt reassured following his inspection. Great
work NAC”
“I’d like to compliment the Money Matters
Team - great support and help with my
child's DLA appeal.  Caring and brilliant at
what they do.”
“I would like to thank Housing and the
Welfare Team for their help and support as
I felt very low and the people I spoke to
were very kind, understanding and helpful.
I am grateful for their kindness and support
during a very difficult time for me”
“I had a plumber from Building Services visit my
property today to carry out some work.  His
workmanship was outstanding and he was also very
polite and courteous. He is a credit to NAC and I would
like his bosses to recognise what an asset he is.”
Several compliments received from residents of
Montgomerie Park regarding ground works
undertaken by Regeneration back in June
“I would like to pass on my thanks to the
Assistant Registrar in Customer Services who
conducted my wedding in June. The ceremony
itself was lovely and she and her colleague let
us delay the start as a guest was running late.
We were kept updated regularly which was
lovely and reassuring.  Thank you.” 
“We have had a new wet room put in
by Building Services. I have nothing
but praise for the three men who fitted
it - what a pleasant experience it was.
Friendly, professional and Covid
aware. Thank you so much” “I would like to express my thanks to two members
of your Streetscene Team who came to my aid
yesterday afternoon when my car broke down in
Largs. They were a very calm presence in an
otherwise very stressful situation. I do not know
what I would have done without them”.
201

Page 202

Page | 17 
10   ALEO complaints 
An Arms-Length External Organisation (ALEO) is an organisation formally separate from a local
authority but still subject to its control and influence.  North Ayrshire Leisure Limited (NALL)
is an ALEO for North Ayrshire Council and this section highlights complaints handled by NALL
in 2021/22 using the same Two Stage procedure the Council operates.   
Complaints received per Business Area and Complaint Category
Business Area Complaint Category Volume to
date
LEISURE
Irvine Activities & Programming 40
Facilities General 26
Facilities Cleanliness 7
Customer Service 30
Marketing/Promo 1
Policy/General 25
Three Towns Activities & Programming 10
Facilities General 9
Facilities Cleanliness 2
Customer Service 12
Marketing/Promo 0
Policy/General 3
Garnock & Kilwinning Activities & Programming 6
Facilities General 10
Facilities Cleanliness 1
Customer Service 5
Policy/General 2
North Coast & Arran Activities & Programming 8
Facilities General 26
Facilities Cleanliness 0
Customer Service 6
Policy General 6
Marketing/Promo 1
PHYSICAL ACTIVITY
Active Lifestyles Activities & Programming 3
Customer Service 0
Policy/General 3
Community Sport Activities & Programming 1
Customer Service 0 
Support Team Customer Service 2
Policy General 8
Marketing/Promo 0 
• 253 complaints were received by NALL during the year. 
202

Page 203

Page | 18 
Complaints per 1,000 visits for each department
Department Complaint
Volume
Attendances Complaint
Rate
Leisure 221 697,243 0.32
Physical Activity 12 72,205 0.17
Support Team 20 n/a n/a 
• Whilst the above table only highlights complaint volumes for the first three quarters
of 2020/21, the volume of complaints received over the period is small compared to
the number of people visiting NALL facilities/venues during the period. 
Complaint categories by volume
Category Volume
Facilities General 71
Facilities Cleanliness 10
Customer Service 55
Activities and Programming 68
Policy/General 47
Marketing and Promotion 2
Total 253 
Three-year Complaint Category comparison
Category 2019/20 2020/21 2021/22
Facilities General 23 25 71
Facilities Cleanliness 7 12 10
Customer Service 22 56 55
Activities & Programming 27 41 68
Policy/General 17 16 47
Marketing/Promotion 4 0 2
Total 100 150 253 
Complaints handled at each Stage by category
Category Stage One Stage Two
Facilities General 36 25
Facilities Cleanliness 5 3
Customer Service 33 11
Activities and Programming 40 22
Policy/General 28 14
Marketing and Promotion 2 0
Total 144 75 
203

Page 204

Page | 19 
Examples of complaints received
Category Nature of complaints NALL Response/Action
Facilities General Customer complained
regarding the low
temperature of the main
pool at Vikingar first thing
in the morning. 
Apology offered and customer
advised that the thermostat
had now been set to heat the
pool an hour earlier than
normal to benefit early
morning swimmers.
Facilities Cleanliness Customer complained about
the cleanliness of the sports
halls and toilets at
Greenwood Academy.
Apology offered to customer
and comment passed to the
school facility management
team who are responsible for
school cleaning. KA Leisure
staff have also been instructed
to monitor cleanliness in these
areas.
Customer Service Customer complained that
their direct debit payments
were higher than expected.
Apology offered to customer,
direct debit amount corrected
and refund issued for excess
fees collected.
Activities & Programming Customer complained that
live streaming classes were
not starting on schedule or
sometimes not at all.
Apology offered.  Customer
was advised that all instructors
have been told to ensure
classes start at the time
advertised. Customer also
advised that there are
alternative online classes
available via the KA App.
Policy/General Customer complained about
having to pay a joining fee
which was a deciding factor
in joining up.
Apology given but customer
advised that KA Leisure was
running a join now, pay nothing
until January promotion and
provided the customer the
Promo Code to take advantage
of the offer.
Marketing/Promo Customer complained that
they were unable to get in
contact with Arran
Community Sport Hub or
find details on the web site.
Apology offered to customer
and a contact number and full
list of activities on offer
provided.  
204

Page 205

Page | 20 
11   SPSO complaint referrals 
The Scottish Public Services Ombudsman (SPSO) is the final stage for complaints about Local
Authorities in Scotland.  The table below details the volume of complaints relating to the
Council that were referred to the SPSO during 2021/22: 
Type of Complaint Volume
Economic Development 1
Education 1
Environmental Health & Cleansing 3
Finance 2
Housing 11
Legal & Admin 2
Planning 3
Social Work 1
Welfare Fund - Crisis Grants 1 
• The SPSO received 1,189 complaints about Scottish Local Authorities during 2021/22
which equates to 2% relating to the Council.  This referral rate is consistent with
previous years (typically between 2% and 3%). 
• The highest number of referrals made to the SPSO related to Housing but this was
expected given the majority of Local Authority referrals made to the SPSO during the
year related to Housing or housing services. 
The outcomes of the 24 North Ayrshire Council complaints that were referred to the SPSO and
determined are noted below. 
Stage Outcome Volume
Advice Premature 3
Unable to proceed 4
Early
Resolution
Discretion –  Insufficient benefit achieved by investigation  3
Discretion - Good complaint handling 9
Subject matter not in jurisdiction  1
Time limit (s 10) 1
Unable to proceed 3
Investigation None received n/a 
• All referrals made by North Ayrshire complainants were resolved by the SPSO at the
Advice or Early Resolution stages. None were taken to Investigation stage. 
• Some referrals at Advice stage were premature i.e. complainants approached the
SPSO before exhausting the Council’s Two Stage process.   
205

Page 206

Page | 21 
• The majority of complaint referrals handled at Early Resolution were discretionary in
nature, meaning the Council had discretion in terms of how to action them.  It is
pleasing to note many were considered ‘good complaint handling’ complaints,
meaning the SPSO was satisfied with the way the Council handled them. 
More details regarding complaint referrals for North Ayrshire Council can be found on the
SPSO website at https://www.spso.org.uk/decision-reports. 
206

Page 207

Page | 22 
12   Glossary 
Term   Explanation 
Stage One Stage One (aka Frontline Resolution) aims to resolve straightforward
customer complaints that require little or no investigation.  Any
employee may deal with complaints at this stage and they can be
resolved via any channel.  The main principle is to seek resolution at the
earliest opportunity and as close to the point of service delivery as
possible.  Stage One complaints must be responded to within 5 working
days unless an extension (a maximum of 5 additional working days or 10
if the complaint relates to Social Work) is requested and approved by a
senior manager.  The Council should, however, always aim to resolve
these types of complaints within 5 working days. 
Stage Two Not all complaints are suitable for Frontline Resolution and not all
complaints will be satisfactorily resolved at that stage.  Complaints
therefore handled at Stage Two (aka Investigation) typically require a
detailed examination before the Council can state its position.  These
complaints may already have been considered at Stage One, or they
may have been identified from the outset as being complex, serious or
high risk and needing immediate investigation.  The investigation under
a Stage Two should establish all the facts relevant to the points made in
the complaint and give the customer a full, objective and proportionate
response that represents our final position.  Stage Two complaints must
be responded to within 20 working days unless an extension is approved
by senior manager in conjunction with the customer.  Stage Two
complaints require a written response, signed by a senior manager. 
Complaint criteria 
When an expression of dissatisfaction is received the Council determines if the issue falls into one
of six complaint categories: 
• A service the Council should be providing is not being provided (or is not available)
• A request for a service was provided but not to an appropriate standard 
• A request for service has not been answered or actioned within the agreed timescale
• A Council employee was rude, unhelpful or unprofessional
• A Council employee did not attend an appointment or call-out on a date/time agreed
• The complaint relates to a policy (internal or external) 
If the issue being raised relates to one or more of the above, the matter is considered a complaint
and will be recorded and handled as such.  If not, the matter will be handled as something else i.e.
a request for a service, observation or enquiry and processed accordingly. 
END OF REPORT
207

Page 208

208

Page 209

NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit & Scrutiny
Title: Workforce Absence 2019-2022
Purpose: This report provides a year end summary of sickness absence
for the period 2019/20 to 2021/22.
Recommendation: That the committee notes the absence levels over the last three-
years and the support provided to the workforce.   
1. Executive Summary 
1.1 This report provides a summary of the sickness absence levels and productivity
associated with this for the 3-year period from 2019-2020 to 2021-2022. The report
highlights the policies, procedures, and proactive interventions to support the Council’s
workforce. 
2. Background 
2.1 It is imperative that the Council effectively manages absence levels to ensure a healthy
and productive workforce. To do so each Section, Service and Directorate sets an annual
absence target. Absence targets are based on analysis of the absence levels in previous
years, FTE and external factors which may influence health and wellbeing. All targets are
approved by the Chief Executive. 
2.2 Absence levels are monitored throughout the year, with a 6 monthly report being provided
to the Executive Leadership Team. Where required actions plans have been developed
and updates on progress are provided to the Chief Executive. 
2.3 The Wellbeing@Work (Supporting Attendance) Policy was implemented in 2021. The
policy aims to ensure our employees are supported to maintain high levels of attendance,
thereby minimising the detrimental effects of sickness absence on service provision, our
service users, and colleagues. The policy will ensure a fair, consistent, and
compassionate approach to supporting employee attendance, considering individual
circumstances, whilst ensuring compliance with all associated legislation.   
3. Overview 
3.1  The table below provides the number of days lost per FTE for the whole Council against
the respective annual attendance target for the last 3 years. Employee numbers
increased in 2019/2020 to enable the Council to respond to the COVID19 pandemic,
meeting increased demand on services, whilst also delivering additional services to
support the most vulnerable within the community.     
Agenda Item 8
209

Page 210

3.2  Mental Health and Musculo Skeletal have been the primary reasons for absence over
the last three years. There are multiple initiatives in place to support the workforce
specifically targeting these areas, these are summarised at the support section of this
report. 
3.3  The Council is required to provide statistics for employee absence levels as part of the
National Statutory Performance indicators. The stats are based on the average days lost
per employee and are categorised separately for Teachers and Non-Teaching
employees. The tables below provide a 3-year summary for each category.  Scottish
Local Authority (SLA) ranking indicates the ranking of North Ayrshire Council’s absence
levels in relation to the other Councils in Scotland with 1 being the best performing and
32 the worst.   
The benchmarking table for absence rates in 2021/22 will not be published until early
2023 at which point the ranking for that year will become available. Policies for managing
absence with Councils are determined locally. This may result in different approaches
and length of time given to manage an absence. As a result, the SLA ranking gives an
indication of performance against other Councils however it is not based on a like for like
comparison. 
Year FTE Actual Target Variance
Change from
Previous
Year
2019/2020 6574 10.15 7.91 2.24 0.53
2020/2021 6038 6.79 8.70 -1.91 -3.36
2021/2022 6225 9.87 8.70 1.17 3.08
Days Lost per FTE NAC
Year FTE Actual Target Variance
No of Days
Lost
Change from
Previous Year SLA Ranking
2019/2020 1416 5.53 6.00 -0.47 7,834 1.83 11
2020/2021 1444 4.78 5.72 -0.94 6,907 -0.75 25
2021/2022 1494 7.20 5.72 1.48 10,764 2.42 -
Year FTE Actual Target Variance
No of Days
Lost
Change from
Previous Year SLA Ranking
2019/2020 5158 8.94 7.91 1.03 46,104 -0.28 1
2020/2021 4594 9.24 9.62 -0.38 42,468 0.30 15
2021/2022 4731 12.90 9.62 3.28 60,828 3.66 -
Average Days Lost per FTE per Teachers
Average Days Lost per FTE per Employee Non-Teaching
210

Page 211

Directorate 
3.4  The table below provides details at a directorate level of average days lost and
attendance levels. The attendance level percentage is a measure of the number of
employees who had no absence. In April 2020 the Finance and Corporate Support
Directorate was consolidated within the Chief Executive’s Directorate. 
3.5  2020/21 and 2021/22 absence rates were impacted by COVID19, as absences due to
COVID19 were treated as special leave and not sickness absence. The pandemic has
also resulted in longer than usual waiting times for treatment. During this time the Council
has continued to support employees on long term absence through individual case
management.  2019/20 was the last ‘normal’ year in relation to measuring sickness
absence and it is hoped that absence in 2022/23 will also return to a ‘normal’ year that
will allow a more relevant comparison. 
Productivity 
3.6  The table below outlines the loss of productivity in the last 3 years.  The loss equates to
3% of the paybill in 2019/2020 and 2021/22 and 2% in 2020/21. This reflects pay due to
employees for the days they were absent and does not include replacement cover for
critical posts such as teachers and care workers. It should be noted that the significant
increase within the Chief Executives Directorate can be attributed to the consolidation of
the Finance and Corporate Support directorate in April 2020. 
Directorate 2019/2020 2020/2021 2021/2022
Chief Executives £47,810 £240,491 £379,679
Communities & Education £2,879,874 £1,903,832 £3,592,952
Finance & Corporate Support £279,334 N/A N/A
HSCP  £2,374,393 £2,137,681 £3,263,909
Place  £1,919,167 £1,290,981 £2,022,175
NAC £7,500,578 £5,572,985 £9,258,715 
COVID-19 
3.7 During the height of the COVID19 pandemic the Council was required to stand down
some services resulting in an element of the workforce being inactive, where appropriate,
some employees were redeployed to alternative roles primarily supporting the
community. 
3.8   In addition, employees with significant health conditions were instructed by the Scottish
Government to shield from March 2020 until August 2020. The table below outlines the
impact shielding had on the Council. 
Days Lost Target Variance Attendance Days Lost Target Variance Attendance Days Lost Target Variance Attendance
Chief Executives 3.95 5 1.05 55% 3.92 5.69 1.77 77% 6.29 5.62 0.67 70%
Communities & Education 7.54 6 1.54 57% 4.53 6.51 1.98 72% 7.52 6.5 1.02 55%
Finance & Corporate Support 6.06 6 0.06 53%
HSCP 14.43 11 3.43 45% 11.47 12.42 0.95 57% 15.29 12.5 2.79 49%
Place 11.75 7.91 3.84 54% 6.95 9.8 2.85 75% 9.54 9.84 0.3 61%
N/A
Directorate
2019/2020 2020/21 2021/2022
211

Page 212

3.9   During this time a further 107 of the employees who were advised to shield due to health
conditions continued to work either undertaking alternate duties or by working from
home. Had these options not been available the loss in productivity to the Council
resulting from inactivity due to shielding would have been £1.9m. 
3.10  Employees who had COVID19 symptoms, tested positive or were required to self-isolate
were granted special leave paid for up to 12 weeks and were exempt from the Council’s
Wellbeing@Work absence triggers. This arrangement was reduced to 10 days in April
2022 and then ceased in June 2022. The number of employees who were absent in this
instance, working days lost and loss in productivity to the Council is detailed in the table
below. The loss in productivity does not include replacement cover. In addition to
inactivity the table below also includes the details where employees were able to
continue to work whilst impacted by COVID19 either by working from home or by
undertaking alternate duties. 
Support 
3.11 Wellbeing@Work continues to be high on the Council’s agenda with several policies,
procedures, and initiatives in place to support employees back to work and while at work. 
3.12 HR provide support through individual case management, policies, and guides such as
Work Life Balance, Menopause, working with Cancer, Carers leave and Agile Working
(Workstyles). 
3.13 A suite of Occupational Health interventions are available such as Counselling, CBT
(Cognitive Behavioural Therapy), Physiotherapy, and online resources. The table below
details Occupational health usage during the last 3 years and between April 2022 to
September 2022. 
Year Referrals 
2019/2020 7,004
2020/2021 3,473
2021/2022 3,624
April 2022 – Sept 2022 2,608 
Occurrences
Working Days
Lost
Impact on
Productivity
Chief Executive
Communities & Education 72 6,483 £503,204
HSCP 60 5,180 £357,231
Place 60 5,145 £330,153
Grand Total 192 16,808 £1,190,589
Inactive - Shielding
Directorate
Occurrences
Working
Days
Lost
Loss in
Productivity Occurrences
Working
Days Occurrences
Working
Days
Chief Executive 13 152 £17,000 31 374
Communities & Education 398 4,000 £387,001 745 7,984 41 3,987
HSCP 230 2,782 £205,807 82 2,560 6 1,496
Place 319 2,473 £174,792 50 380 4 92
Total 960 9,407 £784,600 908 11,298 51 5,575
Directorate
Inactive - Loss in Productivity Alternate DutiesWorking From Home
212

Page 213

During 2020/21 the provision was initially paused and then a reduced service was
provided by telephone and virtual methods. 2021/22 continued to be a limited offering in
line with COVID workplace guidance with the provision returning to a pre-pandemic
provision in the last quarter of 2021/22.     
3.14 Livewell is an employee led healthy working lives programme that hosts a variety of
initiatives such as Yoga, Walking clubs, Mindfulness and Paddleboarding.  The calendar
of activities focusses on physical activity, healthy eating, weight management, general
health, mental health, and financial wellbeing. Wellbeing Warriors were introduced in
2020 to support, listen and signpost individuals to internal and external support.  These
30 employees undertook a qualification in mental health first aid to provide them with the
skills and knowledge to provide compassionate support. 
3.15  A variety of development supports are in place throughout the council to ensure the
workforce is supported in the skills and knowledge required in relation to their role.  These
opportunities range from policy and leadership courses such as managing stress which
equips managers in the skills required to define and support employees to practical
health & safety interventions, such as manual handling to reduce the risk of Musculo
skeletal injuries and risk assessment 
3.16 In addition to the variety of support outlined above, Directorates also provide
complimentary wellbeing interventions and a flavour of this is provided below.   
3.17 Within Communities & Education, a whole school/community approach is being taken to
wellbeing. This is built on an ethos and culture that supports inclusion, welcomes
employees and their views, builds relationships, and encourages listening. Regular staff
briefings were introduced during COVID to promote and support employee wellbeing,
due to the success these continue to be a key tool. There is a specific team that support
mental health and wellbeing of young people which is now being extended to support the
workforce. Information is available online and is supplemented with information provided
through professional learning. Collaboration within the Head Teacher network and
localised initiatives allow for best practice to be shared and identify next steps to support
wellbeing. 
3.18 The Health and Social Care Partnership have taken a targeted approach to wellbeing,
focusing themes such as on Physical Activity, Mental Health Support, Leisure and
Recreation Activities, Staff Wellbeing hubs and management support. These themes
harness and enhance the support interventions already available within the Council
through the Livewell Programme and Occupational Health. 
3.19 The Place Directorate, takes an inclusive approach to wellbeing, engaging employees,
trade unions and managers to discuss absence and recognise attendance. There is.
also, a focus on increasing employee satisfaction levels and morale through training and
further education opportunities.  In addition to utilising Occupational Health and corporate
initiatives, the Directorate has worked in partnership with Ayrshire College to develop
and deliver a bespoke “Customer Service & Resilience” training course, this has
supported employees to build resilience and better equip them to deal with challenging
situations. 
4. Proposals 
4.1  The Committee note the content of the report and the interventions in place to support
213

Page 214

the workforce. 
5. Implications/Socio-economic Duty
Financial
5.1. The loss of productivity associated with absence are outlined within this report. 
Human Resources 
5.2   Council’s approach supports the health and wellbeing of its workforce. 
Legal 
5.3 None 
Equality/Socio-economic 
5.4 None 
Climate Change and Carbon 
5.5 None 
Key Priorities 
5.6 None 
Community Wealth Building 
5.7 None 
6. Consultation 
6.1 The Chief Executive and Executive Directors have been consulted in the creation of
this report. 
Fiona Walker
Head of Service (People & ICT) 
For further information please contact Jackie Hamilton, Senior Manager Employee
Services on 01294 324694. 
Background Papers
0
214

Page 215

NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    Internal Audit and Corporate Fraud Action Plans: 
Quarter 2 update 
Purpose:  To advise the Audit and Scrutiny Committee on the progress
made by Council Services in implementing the agreed actions
from Internal Audit and Corporate Fraud reports as at 30
September 2022. 
Recommendation:  That the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions;
and (b) challenges those Services that have not implemented
actions within the previously agreed timescales. 
1. Executive Summary 
1.1 The CIPFA document 'Audit Committee Principles in Local Authorities in Scotland'
highlights that Audit Committees should monitor and review the progress made in
implementing audit recommendations. 
1.2 Service managers are responsible for ensuring that agreed actions arising from
Internal Audit and Corporate Fraud reviews are implemented.  This provides
assurance that identified control weaknesses have been addressed and are being
managed effectively. 
1.3 All actions are monitored on the Pentana system and service managers are
responsible for updating Pentana as they progress each action.  This enables Internal
Audit to monitor progress on a 'real-time' basis and address any delays in
implementation. 
1.4 This report details the position at 30 September 2022. 
2. Background 
2.1 The last report to the Audit and Scrutiny Committee on 27 September 2022
highlighted that there were 28 actions outstanding at the end of June 2022: nine that
had not been started or were only partially implemented and 19 where the due date
had not yet passed. 
Agenda Item 9
215

Page 216

2.2 In addition to these 28 carried forward actions, there have been eight new actions
agreed, giving a total of 36 action points for review. 
2.3 Services have completed 23 actions since the last report.  All Council Services are
required to retain evidence of work carried out in completing their actions and Internal
Audit carries out 'spot-checks' on a sample of completed actions on an ongoing basis. 
2.4 Of the remaining 13 actions, one was either not started or only partially complete at 30
September 2022 and the remaining 12 were not due for completion until after that
date. 
2.5 Appendix 1 to this report provides the Committee with full details of the action that was
not complete within the agreed timescales. 
3. Proposals 
3.1 It is proposed that the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions; and (b) challenges
those Services that have not implemented actions within the previously agreed
timescales. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The effective implementation of agreed Internal Audit and Corporate Fraud actions
helps to support the efficient delivery of the strategic priorities within the Council Plan
2019-2024. 
216

Page 217

Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Council Services are consulted during the completion of each Internal Audit and
Corporate Fraud review and have also provided updates on progress made in
implementing action points. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294 324524. 
Background Papers
None.
217

Page 218

Actions due by 30th September but not started or partially complete 
Code IA2020PA032a Description
Audit Action: Arran should be aligned with the mainland’s processes and
procedures.
Audit Finding: Staff on the mainland and Cumbrae are managing the interment
process electronically, whilst staff on Arran continue to use manual records.
Risk: Business continuity issues due to operating a completely separate system on
Arran; manual records are not backed-up in the same way that electronic records are.  
Priority 2 Latest Note
The Service is working with IT to complete the Data Protection Impact Assessment in
order to progress with the upgrade, we are confident this will be completed and
processed by end of December 2022.
Progress Bar  Original Due Date 31-Mar-2021 Due Date 31-Jul-2022
Parent Code & Title IA2020PA032 Bereavement and Burial Services
Managed By David Hammond
Assigned To Mark McNeil 
218

Page 219

NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    Corporate Fraud Team update report 
Purpose:  To provide the Audit and Scrutiny Committee with an update
report on the work of the Corporate Fraud Team between April
and September 2022. 
Recommendation:  That the Committee notes the work carried out by the Corporate
Fraud Team. 
1. Executive Summary 
1.1 The Corporate Fraud Team provides the Council with the capacity to investigate fraud
both within and against the organisation. 
1.2 Committee receives bi-annual updates on the work of the team. This report provides
an overview of the activity of the team between April and September 2022. 
2. Background 
Referrals 
2.1 Referrals for investigation have been made to the team from a number of different
sources, including Revenues and Benefits and Housing, members of the public and
other agencies and local authorities. The publicity used by the team, including posters
and leaflets, advertising on Council vans and contact information on the Council
website, continues to be successful in generating a stream of referrals. 
2.2 Investigations have been carried out across a range of areas including employee-
related matters as well as Council Tax, Discretionary Housing Payments, Scottish
Welfare Fund, Blue Badges and Housing tenancy issues. Although responsibility for
investigating Housing Benefit fraud now lies with the DWP Single Fraud Investigation
Service (SFIS), issues may be identified by the Corporate Fraud Team which can
result in changes being made to benefits in payment. Joint working with the DWP
paused during the COVID-19 pandemic, but has since recommenced.  This formal
joint working arrangement is in place for cases where there are suspected frauds
relating to both DWP benefits and Council Tax Reduction. 
Agenda Item 10
219

Page 220

2.3 The team investigates all tenancy abandonments which are referred by Housing.
While Housing focus on recovering the tenancy, the Corporate Fraud Team can add
value by locating the missing tenant, which can often lead to changes to benefits or
discounts in payment elsewhere, as well as enabling Housing to recover costs
associated with house clearances and cleaning. 
2.4 Employee-related investigations are the subject of a separate report to the appropriate
Service and the findings are also reported to the Audit and Scrutiny Committee as
each investigation is finalised. 
Financial outcomes for April to September 2022 
2.5 The team received 176 referrals for investigation during the first half of 2022/23
(2021/22: 169 referrals). The team investigates 100% of referrals made. During the
period, 161 cases were closed (2021/22: 144 cases). These can be categorised as
follows: 
Category Number of Cases
Closed with no issues identified 75
Referred to another agency (including SFIS) or Council
Service for investigation
42
Closed with results achieved (fraud, error or other
recovery/action)
44
TOTAL 161 
2.6 Fraud and error totalling £0.079m were identified and are categorised in the table
below: 
Category Value (£000)
Housing Benefit 13
Council Tax (including CTR, Single Person Discount
and other recoveries)
33
Housing 8
Other (including employee investigations) 25
TOTAL 79 
Non-financial outcomes for April to September 2022 
2.7 In addition to the financial outcomes noted above, other outcomes/benefits were noted
as follows: 
• Twenty-six tenancies were recovered by Housing with some assistance from the
Corporate Fraud Team;
• One warning letter was issued for blue badge misuse, with a further badge being
recovered for misuse.
• One application for a new tenancy has been refused as a result of pro-active
checks on tenancy successions, joint tenancies, and tenancy exchanges.
• Two employee investigations have been taken forward to disciplinary action by
services.
• One case was referred to the Crown Office and Procurator Fiscal Service (COPFS)
for them to consider prosecution. 
220

Page 221

Pro-Active work  
2.8 Two data matching exercises commenced in 2021/22 using data from the council tax
and payroll systems, the aim of which was to identify any anomalies in the council tax
accounts of council employees.  £0.030m of recoveries were reported in the year end
report for 2021/22 presented to Audit and Scrutiny Committee in May 2022. A further
18 cases were closed in 2022/23 with single person’s discount anomalies amounting
to £0.025m. 
2.9 This brings recoveries from the full exercise to £0.055m (2021/22: £0.030m; 2022/23:
£0.025m). 
National Fraud Initiative (NFI) 
2.10 The NFI is a long-established exercise which takes place across the UK every two
years and involves the matching of relevant datasets across public bodies to identify
possible fraud or error for further investigation. The team co-ordinates the Council’s
participation in the NFI. 
2.11 Potential data matches from the 2020/21 exercise were received from the Cabinet
Office between February and September 2021 and passed to the appropriate teams
for investigation.  Following conclusion of investigation work, the outcomes for North
Ayrshire Council were as follows: 
Category Value (£000)
Blue badges (89 errors) 51
Council Tax Single Person Discount (30 frauds and 1 error) 26
Business rates (1 error) 8
Council Tax reduction (1 error and 3 frauds) 3
Housing Benefit (1 error) 2
Creditor Payments (1 error) 1
TOTAL 91 
2.12 The NFI exercise for 2022/23 is underway, commencing with the completion of
compliance declarations.  The Council’s data sets are due to be submitted to the
Cabinet Office imminently with data matches expected to be available in early 2023. 
The outcomes from that exercise will be reported to a future meeting of the Audit and
Scrutiny Committee. 
International Fraud Awareness Week 
2.13 International Fraud Awareness Week takes place from 13 – 19 November 2022. With
the removal of COVID-19 restrictions, plans are in place to once again hold events at
properties across North Ayrshire.  The purpose of these visits is to raise knowledge
and awareness of the Corporate Fraud Team. 
3. Proposals 
3.1 It is proposed that the Committee notes the work carried out by the Corporate Fraud
Team. 
221

Page 222

4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of the Corporate Fraud Team helps to support the efficient delivery of the
strategic priorities within the Council Plan 2019-2024. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 No consultation has been required in the preparation of this report. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294 324524. 
Background Papers
None
222

Page 223

NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    Internal Audit Reports issued 
Purpose:  To inform the Committee of the findings of Internal Audit work
completed between September and October 2022. 
Recommendation:  That the Committee considers the outcomes from the Internal
Audit work completed. 
1. Executive Summary 
1.1 The Council's local Code of Corporate Governance requires effective arrangements to
be put in place for the objective review of risk management and internal control. 
Internal Audit is an important element in this framework as it reviews internal controls
and offers Elected Members and officers an objective and independent appraisal of
how effectively resources are being managed. 
1.2 The remit of the Audit and Scrutiny Committee includes the monitoring of Internal
Audit activity.  The submission and consideration of regular reports assists the
Committee in fulfilling this remit. 
2. Background 
2.1 This report provides information on Internal Audit work completed between September
and October 2022.  Internal control reviews have been completed in respect of the
areas detailed in Appendix 1 to this report. The aim of these reviews is to provide
assurance that the internal control framework within the areas examined is appropriate
and operating effectively. 
2.2 The findings from each audit assignment have been notified in writing to the Chief
Executive, the Section 95 Officer and the relevant Executive Director and Head of
Service on the completion of each assignment.  Where appropriate, this has included
an action plan with recommendations for improving internal control.  Appendix 1
includes the report and action plan from each audit. 
2.3 The findings from three separate audit assignments are detailed at Appendix 1 to this
report and the levels of assurance for each are noted in the table below: 
Agenda Item 11
223

Page 224

Audit Title Assurance Level
Building Services Procurement Substantial
Roads – Stores Controls Substantial
Care Home Admissions Substantial 
3. Proposals 
3.1 It is proposed that the Committee considers the outcomes from the Internal Audit work
completed between September and October 2022. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of Internal Audit helps to support the efficient delivery of the strategic
priorities within the Council Plan 2019-2024. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The relevant Services are consulted on Internal Audit findings during each audit
assignment. 
224

Page 225

Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294 324524. 
Background Papers
None.
225

Page 226

BUILDING SERVICES PROCUREMENT 
1 Background  
1.1 Building Services procurement was last audited in 2017/18. 
2 Objectives and Scope  
2.1 The objective of this audit was to:-
• Ensure the Council’s Standing Orders relating to Contracts are being applied
when procuring goods and services
• Confirm that invoices authorised for payment in ROCC URM are subject to
the same level of scrutiny and authorisation as those being processed
directly through Integra. 
3 Findings   
Standing Orders relating to Contracts  
3.1 The Council’s Standing Orders relating to Contracts sets out the process for
awarding a contract, depending on the anticipated level of spend.  
3.2 Audit selected a sample of 20 suppliers with varying levels of actual spend and
reviewed the contract in place to ensure if complied with Standing Orders.  The
following issues were highlighted during testing:-  
3.3 Audit noted 2 suppliers where levels of spend were sufficient to require a quick
quote or contract to be put in place.  Discussions with Building Services confirmed
that both of these suppliers are used at the request of other services, which makes
it difficult to estimate an annual spend for tendering.  Building Services highlighted
that 3 written quotes are obtained for such jobs, thereby ensuring best value is
being obtained.  Audit confirmed this via sample testing.  
3.4 One supplier was found to have a contract in place, but the Council had spent in
excess of the contracted value. Discussions with Corporate Procurement and
Building Services highlighted that they had already identified this issue and had
taken steps to address it.  The Services explained that a business case had been
produced that confirmed staying with the supplier was the best option for the
Council and a new contract was negotiated, with a start date of April 2022.  
3.5 Building Services have confirmed that they have a process in place for monitoring
supplier spend against contracts.  Audit did not test this system in detail during the
audit.   
ROCC URM transactions  
3.6 The majority of Building Services’ purchases are managed via a job costing system
called ROCC URM.  This system allows Officers to raise purchase orders, receipt
goods and approve invoices as fit for payment.  A feeder is then used to transfer
approved invoices into Integra for payment.  
226

Page 227

3.7 Audit confirmed that officer’s authorisation levels in ROCC correspond with those
in Integra.  
3.8 Audit selected a sample of 10 invoices originating in ROCC and ensured:-
• purchase orders have been approved by an authorised officer 
• any variations to the original order have been approved by an authorised officer
• goods received information is available (if applicable – some orders are for sub-
contractors rather than goods)
• invoice is marked as ‘reconciled’.  
3.8 No issues were noted during detailed testing.   
4 Internal Audit Opinion  
4.1 Overall, substantial assurance was obtained with regard the elements of Building
Services procurement processes covered by this audit. 
Definitions of Assurance Levels: 
Substantial
A sound system of governance, risk management and control exist, with
internal controls operating effectively and being consistently applied to
support the achievement of objectives in the area audited.
Reasonable
There is a generally sound system of governance, risk management and
control in place. Some issues, non-compliance or scope for
improvement were identified which may put at risk the achievement of
objectives in the area audited.
Limited
Significant gaps, weaknesses or non-compliance were identified.
Improvement is required to the system of governance, risk management
and control to effectively manage risks to the achievement of objectives
in the area audited.
None
Immediate action is required to address fundamental gaps, weaknesses
or non-compliance identified. The system of governance, risk
management and control is inadequate to effectively manage risks to the
achievement of objectives in the area audited. 
NB The level of assurance given is at the discretion of Internal Audit.  
227

Page 228

ROADS – STORES CONTROLS 
1 Background  
1.1 Goldcraigs depot is responsible for controlling the issuing, replenishment, and
security of Roads stock. 
2 Objectives and Scope  
2.1 The objective of this audit was to ensure that:-
• The Council’s Standing Orders relating to Contracts are being adhered to
• Robust procedures are in place regarding stock purchases
• Robust procedures are in place for recording the issuing of stock
• Physical controls are in place to protect stock from loss or theft 
3 Findings   
Standing Orders relating to Contracts  
3.1 Audit identified the top 5 stock suppliers in 2021/22 and in 2022/23 (up to the end
of August 22) and reviewed the contractual arrangements in place. 
3.2 All contracts were found to be in line with the requirements of the Council’s
Standing Orders.   
Stock Purchase Procedures  
3.3 Roads use a dedicated stock management system called RCM.    
3.4 A combination of RCM and manual processes are used to order stock, record stock
movements and approve invoices.  
3.5 Once approved, invoices are keyed into Integra for payment.  
3.6 Audit selected a sample of 10 stock invoices paid in 2022/23 and for each ensured:
• the order was approved by an authorised signatory
• RCM stock records had been updated to reflect the receipt of goods
• Invoiced quantities had been compared to goods received 
• Invoices had been approved by an authorised signatory  
3.7 Audit testing highlighted that 9 out of the 10 orders reviewed had not been approved
by authorised signatories (although the subsequent invoice had been approved by
an authorised signatory).  
3.8 This issue was immediately raised with Roads Management who agreed that the
officers who had been ‘approving’ orders should have the authority to do so, and
therefore took steps to have them approved as authorised signatories.   
Issuing of stock  
3.9 Audit testing on the process of issuing stock was limited to on-site discussions with
officers at Goldcraigs.
228

Page 229

3.10 Officers were able to demonstrate the daily paper trail involved in the issuing of
stock and confirmed that all paperwork is reconciled daily before any stock
adjustments are noted in RCM.  
3.11 The recording of issued stock was considered as part of the testing of stock controls
below.   
Stock controls  
3.12 Weekly stock checks of the 45 most commonly used items confirms the ongoing
accuracy of RCM.  
3.13 A full count of all stock is undertaken annually - in line with the Council’s year-end
financial procedures. 
3.14 Any differences identified during these counts must be reported to a Team Leader,
who will seek explanations and adjust the stock records on RCM as necessary.  No
staff at the depot have the ability to amend stock records.  
3.15 Audit testing involved:-
• Requesting evidence of 6 of the weekly counts
• Attending the depot and performing a stock count of 10 stock items
• Performing a high level review of site security.  
3.16 No issues were noted during testing. 
4 Internal Audit Opinion  
4.1 Overall, substantial assurance was obtained with regard to Roads stock controls.  
4.2 Roads took immediate action to correct the issue regarding authorised signatories
highlighted in 3.7 above and are now aware of the need to ensure that authorisation
levels are applicable to purchase orders as well as invoice approvals. 
229

Page 230

Definitions of Assurance Levels: 
Substantial
A sound system of governance, risk management and control exist, with
internal controls operating effectively and being consistently applied to
support the achievement of objectives in the area audited.
Reasonable
There is a generally sound system of governance, risk management and
control in place. Some issues, non-compliance or scope for
improvement were identified which may put at risk the achievement of
objectives in the area audited.
Limited
Significant gaps, weaknesses or non-compliance were identified.
Improvement is required to the system of governance, risk management
and control to effectively manage risks to the achievement of objectives
in the area audited.
None
Immediate action is required to address fundamental gaps, weaknesses
or non-compliance identified. The system of governance, risk
management and control is inadequate to effectively manage risks to the
achievement of objectives in the area audited. 
NB The level of assurance given is at the discretion of Internal Audit. 
230

Page 231

CARE HOME ADMISSIONS 
1 Background  
1.1 Since September 2020 there has been a change to the care homes admissions
process and new managers have taken on the process. This audit was to assess
whether previous issues with admissions have been addressed.  
1.2 Care homes have continued to admit new residents throughout the Covid-19
pandemic with the inclusion of additional Infection Prevention and Control
measures being in place to ensure this was managed as safely as possible.  In
addition the HSCP were asked by Scottish Government to ensure appropriate
oversight arrangements were in place for care homes during the pandemic, the
North Ayrshire Care Home Oversight Group has been in place since April 2020
initially meeting daily and continuing to meet at least fortnightly to take an MDT
approach to oversight and assurance over care homes in North Ayrshire.   
2 Objectives and Scope  
2.1 The main objectives of the audit were to ensure that: 
• sufficient information was available to make an informed choice
• the process is robust and fair
• there is a financial trail
• the admission process is more efficient. 
3 Findings 
Informed Choices  
3.1 There are 24 care homes in the North Ayrshire Council catchment area, 12 of
which offer nursing care level of support. The council runs three of these homes,
four are managed by voluntary organisations and the rest are privately owned.
Information on their location, client reviews and performance are available on the
Care Home North Ayrshire website. 
3.2 The Care Inspectorate is responsible for the inspections and maintenance of
standards. Inspection reports are published online and available to read online on
the Care Commission’s website. 
3.3 Since 2019 there have been 32 inspections by the Care Inspectorate with the
following themes:
• How good is our leadership?
• How good is our setting?
• How well do we support people’s wellbeing?
• How good is our staff team?
• How well is care and support planned? 
3.4 During the Covid 19 period the Care Commission visited seven care homes two
of which received poor ratings subsequently upgraded after a second visit. Four
visits were not assessed.  The oversight for care home inspection gradings,
231

Page 232

feedback and actions required is undertaken by the Care Home Oversight Group. 
The Integration Joint Board receive an annual update in the Annual Performance
Report of the inspection gradings of all registered social care services during the
year. 
Admissions  
3.5 During the COVID period the admissions process from the community remained
in place. Whilst pre-pandemic funding restrictions limited the number of care home
placements and led to waiting lists, these restrictions were lifted over the Covid-
19 response period.  Over the same time hospital admissions were prioritised, and
a discharge to assess methodology was used with assessments retrospectively
completed. 
3.6 Each potential care home resident is appointed a social worker who discusses
options with the person and their families. These options reflect the needs and
preference of the resident and their family. There are three preferred care home
options which the family can rate in preference. Where a preferred option is not
available then an interim plan or placement can be considered. Following this
process, a financial assessment is completed and presented to the Care
Assessment Review Group (CARG) along with supporting documentation which
includes bank statements, POA documentation. 
3.7 Currently there is no community waiting list for long term care home placements.
There is an active a waiting list for hospital discharge to care homes, the majority
of which relate to patients who lack capacity and under the AWI legislation there
are no legal powers in place to facilitate a move to permanent care.   
Decisions 
3.8 The CARG, which is the group that approve placements, meet weekly on a
Thursday, prior to September 2020 this was monthly. The exception to this was
during the Festive period holiday when the Council offices were closed.  
3.9 A selection of 9 CARG meetings covered 190 individual cases.  The maximum
cases reviewed in one meeting was 33 and the minimum was 9. 
3.10  To test client satisfaction with the CARG decision process a review of the internal
complaints recorded on the Council’s LAGAN stage one, two complaints and
enquiries was undertaken. Analysis was difficult due to the methodology of
recording events on LAGAN however for 202 stage one and two complaints there
were 12 were related to the CARG. One was with the process itself; one was in
relation to the client’s home and the others with regards the financial process itself.
13 enquiries were received in relation to care homes.  
3.11 External complaints are investigated and recorded by the Scottish Public Services 
Ombudsman (SPSO). There were 29 Decision notices between August 2011 and
November 2020, none related to care homes. There were no investigations after
this period.  
Compliance 
232

Page 233

3.12 A random sample of 9 clients was selected from the CARG decision cases, these
included a mixture of both residential and nursing care placements.  Preferred
Care homes were listed for 7 of the cases and information provided to the CARG
was complete for each decision, one case was awaiting Power of Attorney to be
appointed by the court. 
3.13 Information for all financial assessments were compliant with guidance, complete
and accurate. 
3.14  Budgetary performance is tracked on a complex Microsoft excel sheet. This
workbook was created in July 2013. Although nine years old, the data when tested
was robust.   
4 Internal Audit Opinion  
4.1 Overall, substantial assurance was obtained with regard to admission process. 
4.2 The care home environment and market faces considerable challenges in terms of
sustainability in the future.  It is imperative that the HSCP continue to have an
efficient admissions process and oversight arrangements in place in relation to care
homes in North Ayrshire. 
Definitions of Assurance Levels: 
Substantial The framework of governance, risk management and control is adequate
and effective.
Reasonable
Some improvements are required to enhance the adequacy and
effectiveness of the framework of governance, risk management and
control.
Limited
There are significant weaknesses in the framework of governance, risk
management and control such that it could be or could become
inadequate and ineffective.
None
There are fundamental weaknesses in the framework of governance, risk
management and control such that it is inadequate and ineffective or is
likely to fail. 
NB The level of assurance given is at the discretion of Internal Audit.
233

Page 234

234

Page 235

NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    National Fraud Initiative (NFI) in Scotland 2022 
Purpose:  To provide the Committee with an overview of the NFI 2020/21
exercise outcomes. 
Recommendation:  That the Committee notes the outcomes of the exercise. 
1. Executive Summary 
1.1 Audit Scotland has published its most recent biennial National Fraud Initiative (NFI)
report. The report is provided in full at Appendix 1. 
1.2 North Ayrshire Council’s participation in the NFI exercise is coordinated by the
Corporate Fraud Team, with matches investigated by appropriate teams across the
Council. 
1.3 Investigation of the 2020/21 data matches was concluded earlier in 2022. 
2. Background 
2.1 The NFI is a major counter fraud exercise carried out across the UK every two years.
Participating bodies provide sets of data and, following matching of data provided by
various public sector bodies, anomalies in the data are provided for investigation. 
2.2 The exercise is coordinated across the UK by the Cabinet Office, and in Scotland is
delegated to Audit Scotland through the powers in the Criminal Justice and Licensing
(Scotland) Act 2010. 
2.3 The NFI exercise is Scotland is well established and remains the most comprehensive
detective and preventative scheme in which vast amounts of data across numerous
public bodies can be compared and matched using dedicated software. A data match
does not necessarily mean there is fraud or error present, but highlights that further
investigation is required in order to make a determination. Outcomes are recorded on
the system and collated for each public body in order to arrive at a total value of
recoveries across the whole of Scotland. 
2.4 132 public bodies across Scotland participated in the 2020/21 NFI exercise, with
507,354 matches recommended for investigation across the country. Matches are
Agenda Item 12
235

Page 236

categorised into risk priority to enable resources to be focussed on the matches with
the most likely outcomes and recoveries. 
2.6 The value of fraud and error identified across Scotland in 2020/21 was £14.9m,
resulting in cumulative outcomes of £158.5m since the NFI first launched in 2006/07.
In the UK, the 2020/21 result was £442.6m, and £2.4bn cumulatively since 2006/07. 
2.7 The majority of the NFI results arise from the following key match areas: 
• Council tax discounts
• Blue badges
• Pensions
• Housing benefit
• Housing tenancy
• Council tax reduction
• Housing waiting lists
• Creditors 
2.8 For North Ayrshire Council, financial recoveries from the 2020/21 exercise amounted
to £0.091m. 
2.9 External audit also carried out an assessment of the Council’s planning and progress
with the NFI and makes recommendations for improvement where appropriate. North
Ayrshire Council was assessed as Satisfactory. 
2.9 Audit Scotland continues to work with the Cabinet Office in developing new ways to
prevent and detect fraud. This includes piloting new data matching opportunities, and
where pilots achieve matches that demonstrate a significant level of success these are
extended nationally and included in the main NFI exercise going forward. 
3. Proposals 
3.1 It is proposed that the Committee notes the content of the Audit Scotland report on the
National Fraud Initiative in Scotland 2022. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic
236

Page 237

4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of the Corporate Fraud Team, including participation in the NFI, helps to
support the efficient delivery of the strategic priorities within the Council Plan 2019-
2024. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 No consultation has been required in the preparation of this report. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294 324524. 
Background Papers
None
237

Page 238

The National 
Fraud Initiative
in Scotland 
2022
Prepared by Audit Scotland
August 2022
238

Page 239

Key messages
The National Fraud Initiative (NFI) is a counter-fraud exercise which aims to prevent and detect fraud. 
The exercise operates across the UK public sector and includes 132 public bodies in Scotland. The NFI
shares and matches data held by public bodies and helps confirm that services and payments are provided
to the correct people. See Appendix 1 for more information about the NFI exercise.
1 The 2020/21 NFI exercise has identified outcomes valued at £14.9 million (see page 4).
2 The cumulative outcomes from the NFI in Scotland since 2006/07 are now £158.5 million.
Across the UK, the cumulative total of NFI outcomes are now £2.4 billion (see page 4).
3 The overall level of fraud identified by the NFI has fallen since our last report. Outcomes from
the Scottish NFI exercise fell by £0.4 million in 2020/21, from £15.3 million in 2018/19. The
reduction in outcomes could be due to less fraud and error in the system, strong internal
controls or due to some key data sets from previous exercises not being included in the
latest exercise (see page 4).
4 Data sharing enables matches to be made between bodies and across national borders. Data submitted by Scottish bodies 
for the 2020/21 NFI exercise helped other organisations in Scotland and across the UK to identify outcomes of £1.2 million 
(see page 17).
5 Most bodies that participate in the NFI continue to demonstrate a strong commitment to counter fraud and the NFI 
(see page 18–19). However, a lower percentage of participating public bodies managed their roles in the 2020/21 NFI exercise
satisfactorily compared to the 2018/19 NFI exercise.
6 Pilot work to look at potential data matches for future NFI exercises identified £2.2 million in incorrect non-domestic rates relief.
The pilot work also identified one £25,000 fraudulent Covid-19 grant payment and 1,737 national entitlement travel cards which
should have been cancelled (see pages 20–23).
An NFI outcome 
describes the overall 
amounts for fraud,
overpayments and error
that are detected by the
NFI exercise as well as an
estimate of future losses that
it prevents (see Appendix 3).
The National Fraud Initiative in Scotland 2022 | 2 |239

Page 240

Recommendations
1. Maximise the benefits
All participating bodies in the NFI exercise should ensure that they maximise the benefits of their participation.
This includes reviewing matches timeously and prioritising high-risk matches.
NFI users should review the guidance within the NFI secure web application, to help ensure the most effective
use of limited resources when reviewing and investigating NFI matches.
2. Self-appraisal
The NFI self-appraisal checklist should be reviewed by the audit committee, or equivalent, and staff leading
the NFI process. This is to ensure that their organisation’s planning, approach, and progress during the next NFI
exercise is appropriate.
3. Take improvement action
Where local auditors have identified specific areas for improvement, participating bodies should act on these as
soon as possible.
The National Fraud Initiative in Scotland 2022 | 3 |240

Page 241

Outcomes from 2020/21 National Fraud Initiative
Trends in overall outcomes between 2018/19 and 2020/21 NFI exercises
4 cases
referred for prosecution
in Scotland 
NFI outcomes
UK NFI outcomes
£14.9 million
NFI outcomes in Scotland from
the 2020/21 exercise
£158.5 million
NFI outcomes cumulatively in
Scotland since 2006/07
£442.6 million
from the 2020/21 exercise
£2.4 billion
cumulatively since 2006/07
20/21 06/07
Since
20/21 06/07
Since
NFI participants include all councils, NHS bodies, colleges and all larger central government bodies,
for example, the Scottish Government, Revenue Scotland and Transport Scotland. In addition, 
14 councils include data from Arm’s-Length External Organisations (ALEOs), joint boards or
subsidiaries within their NFI submissions. A list of all participating bodies is available on our website.
Reduced levels of outcomes could be due to less fraud and error in the system, strong internal controls
or some key datasets from previous years not being included in the latest exercise. Residential care
home data, direct payments and social care customers’ data were not matched in the 2020/21 exercise
due to a legal question being raised around the definition of patient data. Immigration data was also not
included in the 2018/19 and 2020/21 exercises due to restrictions placed on it by the Home Office.
NFI participants have identified pressures on staffing and services particularly because of the 
Covid-19 pandemic, and the strengthening of controls where previous fraud or error has been
identified, as contributing to reduced outcomes in the 2020/21 exercise.
The number of public bodies
participating in the NFI
exercise has increased by
eight since the last exercise,
to 132 bodies.
The number of matches
generated has fallen by
over 73,000 since the last
exercise, to 507,354.
Outcomes in Scotland have
fallen by £0.4 million since
the last exercise, from 
£15.3 million to £14.9 million.
The National Fraud Initiative in Scotland 2022 | 4 |241

Page 242

Having fewer outcomes provides some assurance there does not appear to be significant
problems in the areas covered by the exercise. However, participants still benefit from the
deterrent effect the NFI creates.
The fall in the number of matches is mainly due to the matches between housing benefit and
payroll or pensions not being included in the matches returned to councils during the 2020/21
NFI exercise. Instead, this data was matched in Department for Work and Pensions (DWP)
systems (see page 11). In addition, the removal of immigration, residential care home, direct
payments and social care customers’ data has also reduced the number of matches.
Four cases were referred to the Crown Office and Procurator Fiscal Service for prosecution. 
One resulted in Police Scotland issuing a caution and the offender is now repaying the money.
The outcomes from the other three cases are not yet known.
Although the main purpose of the NFI is to ensure funds and services are provided to the
correct people, the review of NFI matches may also identify that a customer is entitled to
additional services or payments.
A breakdown of the recorded outcomes for Scottish participants is on our Counter-fraud hub.
The National Fraud Initiative in Scotland 2022 | 5 |242

Page 243

Results
Overall outcomes
How the latest outcomes compare to the last exercise
The areas with significant changes are:
NFI outcomes in Scotland have fallen
by £0.4 million, to £14.9 million in the
2020/21 exercise
Housing benef it Pensions
£ m
illion
Council tax Creditors Blue badges Housing Council tax
reduction scheme
Waiting lists
2018/19
2020/21
0
1
2
3
4
5
Housing
benefit
£1.6m
Pensions
£1.7m
Council tax
£0.3m
Creditors
£0.1m
Blue
badges
£0.9m
Housing
£0.8m
Council tax
reduction
scheme
£0.4m
Waiting
lists
£0.1m
The National Fraud Initiative in Scotland 2022 | 6 |243

Page 244

NFI participants have cited the following reasons as to
why outcomes are less in the 2020/21 exercise:
• staff have had less time available to commit to NFI because of the
added pressures on services caused by the Covid-19 pandemic
• external agents were used instead of the NFI to carry out certain data
matching such as the council tax single occupant discounts
• new controls were introduced because of previous errors identified
through the NFI
• a new system was introduced for reporting the death of customers.
More information about the outcomes for each category is provided on
pages 8 to 15.
A full breakdown of outcomes for each participating body is available on
our Counter-fraud hub.
Once overpayments have been identified, public bodies can take
appropriate action to recover the money.
How NFI matches help to identify areas for improvement
The NFI exercise has helped participants to identify system weaknesses
and to make improvements. These include the introduction of:
• a more robust control environment in the creditors system. This
includes monthly purchase ledger reviews, improved checks on
new suppliers, and controls to identify duplicate payments and
duplicate suppliers
• revised procedures when setting up new suppliers
• a review and cleansing of data held in systems
• strengthened controls in the blue badge system
• improved controls around the change of bank details
• a review of policies aimed at supporting good governance such as
declaring interests, registering of conflicts of interest and checks for
identifying potential related parties.
(95%) of cash overpayments
were being recovered
At 31 March 2022
£4.3 million31
March
The National Fraud Initiative in Scotland 2022 | 7 |244

Page 245

Council tax discounts
People living on their own, or with no countable adults in the household,
are eligible for a 25 per cent single person discount (SPD) on their annual
council tax bill.
Council tax data is matched to:
Electoral register
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
£5.6m
£4.4m
£4.9m
£4.6m
4,846 4,802 4,588
3,720
Outcomes
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
£5.6m
£4.4m
£4.9m
£4.6m
4,846 4,802 4,588
3,720
Cases
£4.6 million £1,248 3,720
Total outcomes 
in 2020/21 exercise
Average outcome Cases
The 2020/21 NFI exercise found that the total
council tax discount incorrectly awarded across
Scottish councils totalled £4.6 million.
Four councils reported that they did not use the
NFI and instead used alternative data matching
or verification arrangements to review SPD
cases during 2020/21. The graphs below include
outcomes from the other 28 councils.
Note. Due to an error with the data deletion
schedule in the Cabinet Office, some
supporting evidence for 11 councils was
inadvertently deleted. Therefore, full supporting
documentation is not available for these
councils. The Cabinet Office has taken steps 
to prevent this error from re-occurring.
The National Fraud Initiative in Scotland 2022 | 8 |245

Page 246

Blue badges
The blue badge parking scheme allows people with mobility problems
to park for free at on-street parking meters, in ‘pay and display’ bays, in
designated blue badge spaces, and on single or double yellow lines in
certain circumstances.
Blue badge data is matched to:
Deceased
persons
Amberhill
data1
1. Amberhill is a system used by the
Metropolitan Police to authenticate
documents presented for identity
£2.7 million 4,616 1,401
Total outcomes 
in 2020/21 exercise
Total number of blue
badge outcomes in
2018/19 exercise
Increase from NFI
2018/19 exercise
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
3,073
4,505
3,215
4,616
£1.8m
£2.6m
£1.8m
£2.7m
Outcomes
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
3,073
4,505
3,215
4,616
£1.8m
£2.6m
£1.8m
£2.7m
Badges
The 2020/21 NFI exercise identified 4,616 blue 
badge outcomes, an increase of 1,401 (44 per cent)
since the last exercise. The estimated value of 
these outcomes is £2.7 million.
Blue badges are sometimes used or renewed
improperly by people after the badge holder has
died. It is an offence for an unauthorised person 
to use a blue badge.
The National Fraud Initiative in Scotland 2022 | 9 |246

Page 247

Pensions
The NFI provides both councils that administer pensions and the Scottish
Public Pensions Agency (SPPA) with an efficient and effective way of
checking that they are only paying people who are alive.
Pension data is matched to:
Deceased
persons Payroll Housing
benefit
Injury
benefits
Amberhill
data
In total, pension outcomes for the 2020/21 
NFI exercise are £1.5 million, down £1.7 million
(53 per cent) from the 2018/19 NFI exercise.
This includes two outcomes identified through
the pre-application screening (AppCheck)2 part 
of the NFI system.
Pension outcomes may have fallen due to the
‘tell us once’3 reporting process and to controls
working effectively within pension bodies.
Case study
An NFI match identified one
fraud with a gross annual pension
amount of £10,560 which was
stopped and resulted in an overpayment
of £6,601. The fraudster had notified
Fife Pension Fund of a change of bank
details for receipt of the pension after the
pensioner had died. The council reported
the fraud to Police Scotland which identified
the person who submitted the fraudulent
bank mandate. Following a police caution,
the full amount was repaid. This case was
reported as part of a 2020/21 NFI Progress
Update to both the council’s Standards and
Audit Committee and the Superannuation
Fund & Pensions Committee in December
2021 for their consideration.
2. AppCheck is an NFI data matching service
used at point of applications for a service
or benefit.
3. ‘Tell us once’ is a service that lets you report
a death to most government organisations
when registering the death.
£1.5 million £1.7 million
Total outcomes in 2020/21 exercise Reduction on the 2018/19 NFI exercise
2014/15 2016/17 2018/19 2020/21
£1.5m
£3.2m
£5.4m
£4.6m
Outcomes
The National Fraud Initiative in Scotland 2022 | 10 |247

Page 248

Housing benefit
Housing benefit helps people on low incomes pay their rent. The NFI
provides councils and the DWP with the opportunity to identify a wide
range of benefit frauds and errors.
Housing benefit data is matched to:
Student loans Housing
benefit
Housing
tenants
Right to buy
(in England) Licences
Deceased
persons
Amberhill
data
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
£3.0m
£2.1m
£2.8m
£1.2m
868
710
1,238
177
Outcomes
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
£3.0m
£2.1m
£2.8m
£1.2m
868
710
1,238
177
Cases
The value and number of housing benefit cases
recorded with overpayments has significantly
reduced, from £2.8 million from 1,238 cases in the
2018/19 NFI, to £1.2 million from 177 cases in the
2020/21 NFI. Over the same period, the average
individual value of overpayments has risen from
£2,292 in 2018/19 to £6,663 in 2020/21.
The fall in outcomes is mainly due to the
matches between housing benefit and payroll or
pensions not being included in the 2020/21 NFI
exercise. These matches historically identified
significant outcomes.
These matches were not included in the
2020/21 NFI exercise as similar data matching
is undertaken by the DWP’s Verify Earnings and
Pensions (VEP) Alerts service which identifies
discrepancies between payroll and pension
details held by HM Revenues & Customs and
council benefits services. Alerts from VEP are
sent to councils to investigate discrepancies.
£1.2 million £6,663 177
Total outcomes 
in 2020/21 exercise
Average individual
value of overpayments
Cases
The National Fraud Initiative in Scotland 2022 | 11 |248

Page 249

Housing tenancy
The NFI uses housing tenants’ data to identify possible cases of tenancy
fraud. This may happen when a tenant has sublet their property. It also
helps identify cases where the tenant has died, and the property is either
empty or has other individuals living in it.
Housing tenancy data is matched to:
Waiting list Housing benefit Housing tenants Right to buy 
(in England)
Deceased 
persons Amberhill data Council tax
reduction
NFI matches resulted in councils recovering ten
properties as part of the 2020/21 NFI exercise,
compared to one property in 2018/19.
The estimated value of these cases is 
£0.93 million, based on a calculation of the
average four-year fraudulent tenancy.
£0.9 million 10
Total outcomes in 2020/21 exercise Cases
Outcomes
Cases
2016/17 2018/19 2020/212016/17 2018/19 2020/21
2
1
10
£0.2m
£0.1m
£0.9m
Case study
An NFI match identified a
Midlothian Council tenant who
had failed to disclose that they
had purchased a property within another
council area at the same time they had
been allocated a council house. Enquiries
established the tenant moved into the
owned property ten years ago and sublet
their council house to a family member.
The council has recovered the property.
Outcomes Cases
The National Fraud Initiative in Scotland 2022 | 12 |249

Page 250

Council tax reduction
Council tax reduction helps people on low incomes to pay their council tax
bills. The NFI provides councils with the opportunity to identify a range of
council tax reduction frauds and errors.
Council tax reduction data is matched to:
Council tax
reduction Payroll Pensions
payroll
Housing
benefit
Housing
tenants
Right to buy
(in England) Licences Deceased
persons Amberhill data
This is a relatively new match which has been
included in the NFI since 2016/17.
Outcomes of £0.7 million were identified in the
2020/21 NFI, an increase of £0.4 million from
the £0.3 million reported in 2018/19.
Councils have identified 772 cases in 2020/21,
more than 2.5 times the number of cases in
2018/19 (280).
One council advised that the increase in
outcomes was directly caused by the Covid-19
pandemic. For example, an increase in mortality
rates for those with underlying health conditions
disproportionately impacted on people in receipt
of disability benefits, council tax reduction and
blue parking badges. In addition, there was an
increase in the number of un-notified increases
in the hours worked by those in lower paid
service jobs who are more likely to be in receipt
of council tax reduction.
2016/17 2018/19 2020/21 2016/17 2018/19 2020/21
115
280
772
£0.5m
£0.3m
£0.7m
Outcomes
Cases
£0.7 million 772
Total outcomes in 2020/21 exercise Cases
Case study
An NFI match identified that a
council tax reduction claimant in
Renfrewshire Council had failed to
declare their company pension and pension
lump sum. This resulted in the claimant
fraudulently receiving £14,450 council tax
reduction. This amount is being recovered by
the council.
The National Fraud Initiative in Scotland 2022 | 13 |250

Page 251

Housing waiting lists
The NFI uses housing waiting list data to identify possible cases of waiting
list fraud. This may happen when a person has registered on a council’s
waiting list but there are possible undisclosed changes in circumstances
or false information has been provided. Social housing provides affordable
accommodation, allocated according to need. It usually provides a more
secure, long-term tenancy when compared to private renting.
Housing waiting list data is matched to:
Waiting list Housing benefit Housing tenants Right to buy
(in England)
Deceased
persons Amberhill data
Councils identified 187 cases in 2020/21 
where applicants were removed from waiting
lists (230 in 2018/19).
The estimated value of these cases is 
£0.6 million. This is based on a calculation of
the annual estimated cost of housing a family
in temporary accommodation and the likelihood
a waiting list applicant would be provided a
property (see Appendix 3).
£0.6 million 187
Total outcomes in 2020/21 exercise Cases
2016/17 2018/19 2020/21 2016/17 2018/19 2020/21
90
230
187
£0.3m
£0.7m
£0.6m
Outcomes
2016/17 2018/19 2020/21 2016/17 2018/19 2020/21
90
230
187
£0.3m
£0.7m
£0.6m
Cases
The National Fraud Initiative in Scotland 2022 | 14 |251

Page 252

Creditors
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
£0.7m
£1.1m
£0.6m
£0.5m
139
168
147 144
2014/15 2016/17 2018/19 2020/21 2014/15 2016/17 2018/19 2020/21
£0.7m
£1.1m
£0.6m
£0.5m
139
168
147 144
The NFI provides an efficient way to check for duplicate payments and that
payments are only made to appropriate creditors. A creditor is a person or
an organisation that a public body pays money to for a good or service.
Creditor data is matched to:
Creditor data Payroll
The 2020/21 NFI exercise identified 144 creditor
outcomes of £0.5 million, a fall of three outcomes
and £0.1 million from 2018/19. Recovery action is
taking place for these overpayments.
£0.5 million 100% 144
Total outcomes 
in 2020/21 exercise
Recovery action 
is taking place
Cases
Outcomes
Cases
The National Fraud Initiative in Scotland 2022 | 15 |252

Page 253

Other data matches
Payroll
The NFI also matches all participating bodies’ employee payroll
data as well as those of MSPs and councillors to identify cases of
potential payroll fraud. The 2020/21 NFI exercise identified three
outcomes valued at £27,000 compared to eight outcomes valued 
at £20,000 in the 2018/19 exercise.
Past NFI exercises have identified larger outcomes for payroll. 
This fall in outcomes is partly due to immigration data not being
included in the 2020/21 exercise due to restrictions placed on it by
the Home Office.
2018/19
£20,000 £27,000
2020/21
three outcomes valued ateight outcomes valued at
Case study
An NFI match identified an employee who left Fife Council
in September 2019 and who continued to be paid their
salary until February 2021. The council overpaid a total of £20,288 to
the ex-employee. Recovery of the overpayment is in progress and
internal audit services have investigated the circumstance surrounding
the overpayment. Recommendations for improvements have been
discussed with management and an audit on the council’s leavers
process is part of the 2022/23 Internal Audit Plan. This case was
reported as part of a 2020/21 NFI Progress Update to the council’s
Standards and Audit Committee in December 2021 for consideration.
Case study
New NFI matching of non-domestic rates small business
bonus scheme (SBBS) in East Dunbartonshire Council
identified a case where a ratepayer had failed to declare other business
premises in another council area. This resulted in almost £11,000 in
SBBS relief being claimed from April 2018. The case is being referred
to the Crown Office and Procurator Fiscal Service for prosecution.
We understand this is the first business rates case to be reported for
prosecution in Scotland.
The National Fraud Initiative in Scotland 2022 | 16 |253

Page 254

Councils Central 
government NHS Colleges Total
£601,591 £483,943 £100,456 £0 £1,185,990
2018/19 2018/19 2018/19 2018/19 2018/19
£854,760 £759,879 £120,408 £12,672 £1,747,719
Matches benefiting other public bodies
A key benefit of a UK-wide data matching exercise is that it enables matches to be made between bodies and across
national borders. For those public bodies taking part in the NFI which may not always identify significant outcomes from
their own matches, it is important to appreciate that other bodies and sectors may do so.
Most of these outcomes relate to housing benefits, housing waiting list
and council tax reductions where, for example, payroll data from an NHS
board may allow a council to identify a council tax reduction fraud or error.
Data provided by Scottish participants for the 2020/21 NFI exercise
helped other public bodies, both within and outwith Scotland, to identify
outcomes worth £1.2 million (a reduction of £0.5 million from 2018/19).
The National Fraud Initiative in Scotland 2022 | 17 |254

Page 255

How bodies worked with the NFI in 2020/21
How bodies work with the NFI
Auditors reviewed each participating body’s planning and progress with the
NFI and provided recommendations for improvement where appropriate.
Overall rating of NFI arrangements by year
Local
government
2016/17
Local
government
2018/19
Local
government
2020/21
Central
government
2016/17
Central
government
2018/19
Central
government
2020/21
NHS
2016/17
NHS
2018/19
NHS
2020/21
Colleges
2016/17
Colleges
2018/19
Colleges
2020/21
Percentage
0
20
40
60
80
100
Satisfactory Mostly adequate Unsatisfactory
The National Fraud Initiative in Scotland 2022 | 18 |255

Page 256

Most participating bodies continue to demonstrate a strong commitment
to counter fraud and the NFI. However, across all sectors, a smaller
percentage of participating bodies managed their roles in the 2020/21
NFI exercise satisfactorily compared to the 2018/19 NFI exercise.
Auditors identified that some bodies could be more pro-active in their
approach to the NFI. One central government body was unable to review
matches due to a cyber-attack, one council did not review matches
citing resource issues as the reason, and a central government body was
unable to action matches due to the impact of reallocating resources to
the provision of Covid-19 grant funding to organisations.
Six key contacts felt they did not have sufficient time and/or resources 
to allow them to oversee the NFI exercise. In four bodies, the key contact
considered that they lacked sufficient authority to seek action across the 
relevant departments.
The Covid-19 pandemic created additional pressures for public bodies
and impacted upon the resources available to support the NFI exercise.
Auditors reported that 15 bodies reduced their participation in the NFI
exercise due to resourcing issues including staff vacancies, sickness
absences or changing priorities as a result of Covid-19.
We recommend that all bodies use our checklist to self-appraise their
involvement in the NFI before and during the 2022/23 NFI exercise. 
For the 2020/21 NFI exercise, 64 per cent of bodies completed the
checklist, although not all presented it to their audit committee; 
ten per cent reviewed it but did not complete it; and just over a quarter
did not review it. This was reported as being because either the key 
NFI contact had changed and was unaware of the checklist, staff had
prior experience of the NFI process, and Covid-19 pressures.
A key contact is appointed by the NFI
participating body. They are responsible
for coordinating and monitoring the
overall NFI exercise, ensuring outcomes
from investigations are accurately recorded and
nominating appropriate users of the NFI system.
64%
26%
10%
completed the checklist
did not review it
reviewed it but did not complete it
Public bodies usage of our NFI checklist
20/21
The National Fraud Initiative in Scotland 2022 | 19 |256

Page 257

Pilots help identify the value 
of extending the NFI exercise
Audit Scotland undertakes new areas of data matching on a
pilot basis to test their effectiveness in identifying fraud.
Only pilots which achieve matches that demonstrate a significant level
of success are extended nationally and included in the main NFI exercise
going forward. A small number of serious incidents of fraud or a larger
number of less serious ones may both be considered successful.
The NFI pilots undertaken or under way over the last two years are
shown on the following pages.
Exemptions for NHS dental
and ophthalmic charges
Data matching was undertaken to help identify NHS patients who have
claimed to be exempt from NHS dental and ophthalmic charges, when they
are not entitled. Patient exemption claims were matched to payroll data
to ensure that dental and ophthalmic exemptions, eg for glasses or dental
treatment, are only awarded to those patients qualifying for exemptions. 
NHS Scotland Counter Fraud Services (CFS) received the matches in the
second half of 2019. It worked to identify the highest-risk matches and
then started verifying payroll details before undertaking investigations. 
As part of this investigative work, CFS asked dentists and opticians to
supply the original exemption claim signed by the patient. However, CFS
was unable to progress this part of the investigation due to dentists,
opticians and the CFS being required to close down due to Covid-19
lockdown restrictions. CFS then decided not to use the matches as
originally intended but instead use them as intelligence, for example, as
an alert if the same people claim again. CFS considered it not worthwhile
re-doing the pilot in 2021 as there were very few exemptions claimed
between April to December 2020. This was due to opticians and dentists
initially being closed and then only able to do emergency treatment
which was free of charge. CFS intends to re-run the exercise after new
payroll data goes into NFI in autumn 2022.
The National Fraud Initiative in Scotland 2022 | 20 |257

Page 258

Covid-19 grants
for businesses
Following a Covid-19 grants data matching pilot exercise in
England in the summer of 2020, it was decided to expand
the English pilot to cover Covid-19 business grants paid to 
Scottish businesses.
These grants were paid under the Small Business Grant Fund (SBGF)
and the Retail, Hospitality and Leisure Grant Fund (RHLGF). Scottish
councils submitted data from early in 2021. Initial matches were released
in April 2021, however, match numbers were low. The Scottish schemes
were more complex than similar schemes in other parts of the UK, eg 
in respect to second and subsequent properties held by each ratepayer.
As a result, the algorithms were rechecked and additional matching 
was undertaken.
Additional matches were released in September 2021. Despite the data
having been rematched, only one fraudulent grant payment of £25,000
was identified. Due to Covid-19 grant payments having stopped, it is not
expected that this matching will be required again. However, the systems
are in place should the matching be required for any similar grants or
payments in the future.
Additional counter-fraud
measures introduced by NFI
participants in respect of
Covid-19 grant funding
Auditors identified that around 43 per cent of NFI participating bodies
awarded Covid-19 funding during the pandemic.
Almost three-quarters of these bodies introduced additional counter-
fraud measures such as new internal controls. This included actively
working through national networks, such as the Scottish Local Authority
Investigators Group, the Institute of Revenues Rating and Valuation,
the National Anti-Fraud Network, and with Police Scotland as well as
strengthening internal controls. This resulted in, for example, Dundee
City Council preventing 143 attempted fraudulent applications valued at
£381,500 from being paid in 2020/21. It also resulted in Aberdeenshire
Council identifying eight fraudulent grants totalling £107,000 plus 
14 attempted frauds totalling £151,000. The bodies that did not take
additional counter-fraud measures reported these were not necessary as
for some, payments were made to existing customers using the existing
controls whereas others relied on existing controls around the setting up
of new suppliers and associated payments.
Only one fraudulent grant
payment of £25,000 was identified Aberdeenshire Council identified eight
fraudulent grants totalling £107,000
The National Fraud Initiative in Scotland 2022 | 21 |258

Page 259

Non-domestic rates – Small
Business Bonus Scheme
In 2019/20, a pilot was undertaken with the Scottish
Government and seven Scottish councils to help identify businesses
inappropriately claiming Small Business Bonus Scheme (SBBS) relief. 
The SBBS provides rates relief to owners of non-domestic properties
with rateable values under certain thresholds.
The seven participating councils provided 81,827 ratepayer records to
the NFI system, which were then matched across the councils and with
data from Companies House in order to identify SBBS fraud. The pilot
identified £412,974 in incorrect awards.
Due to the success of this pilot, a national roll-out of this data matching
exercise was carried out in 2021/22.
The 2021/22 pilot identified 17,676 matches which resulted in £2.2 million
in incorrect SBBS relief being identified in 208 SBBS awards. Councils
will now try to recover SBBS which was incorrectly awarded. Recovery
is already in progress for 119 cases with a value of almost £745,000 in
incorrectly awarded relief.
Given the success of the 2021/22 pilot, consideration is now being given
as to how this data match can be repeated on a regular basis as part of
the main NFI exercise. The pilot report is available on our website.
National entitlement
cards for travel
The National Entitlement Card (NEC) is Scotland’s National
Smartcard. Supported by the Scottish Government to deliver national and
local services, the NEC makes it convenient for people to access various
public services and facilities with only one card. The NEC can be used for
services such as a travel pass, a library card, a leisure membership card
and a Young Scot card as well as providing access to other local services.
In 2021/22, a pilot was undertaken with Fife Council, to match travel
passes for elderly and disabled customers with deceased customer
records. Fife Council provided a total of 112,044 NEC records for matching
against deceased person records. This resulted in 1,737 matches being
identified for review by Fife Council (a return rate of 1.6 per cent).
Following Fife Council’s review, all 1,737 cards (100 per cent) were
cancelled on the NEC system as it was established that the customers
had died. This means no further cards can be requested for these
customers, and the card will be blocked should someone attempt to use
it. No matches were identified where the customer was still alive.
Thirteen matches showed cause for concern as the NECs appeared to
have been used after the death of the cardholder. Two of these cards
were used for journeys to the value of almost £2,300 for one, and £240
for the other. The value of the journeys for the other 11 cards varied from
£3.10 to £69.00.
Given the success of this pilot, consideration will be given as to how this
data match can be expanded to other councils in Scotland and included
in the main NFI exercise in the future. The pilot report is available on 
our website.
The pilot identified £412,974
in incorrect awards
The National Fraud Initiative in Scotland 2022 | 22 |259

Page 260

Social security benefits
A pilot is under way with Social Security Scotland to
identify any instances where claimants received support
but were not residing in Scotland, or where claimants
appear to have claimed benefits more than once, eg from more than
one Scottish address. Claimant data was matched to data already in the
NFI system from across the UK. Data was submitted in March 2022,
with matches released to Social Security Scotland in May 2022. Social
Security Scotland is currently reviewing the matches.
Police Scotland’s use
of AppCheck
Police Scotland’s Serious and Organised Crime Interventions
Team deals with vetting applications, eg for landlord registration and pre-
contract procurement check requests from public bodies such as councils
and the NHS. These checks aim to prevent and detect fraud within public
procurement and other public services such as landlord registration and
taxi licencing. Police Scotland is undertaking a pilot to identify if data in
the NFI data base can be used to help its vetting processes to prevent
and detect fraud. Data has yet to be shared.
A match was highlighted,
demonstrating the benefit AppCheck
can bring in preventing fraud
Applications for student
awards 
A pilot was undertaken with Student Awards Agency
Scotland (SAAS) to help confirm residency and address details for
students applying for awards for tuition fees, grants and bursaries. SAAS
funds students from Scotland and as such it is interested in verifying the
address of student applicants and flagging where students are potentially
fraudulently misrepresenting their address to benefit from the more
attractive financial support offered to Scottish students.
Student applications were matched against data held in the NFI system.
An initial batch of 50 applications was processed which SAAS found
very helpful in verifying and querying address details. One known fraud
was put through the NFI pre-application screening service (AppCheck)
to test the system. A match was highlighted, demonstrating the benefit
AppCheck can bring in preventing fraud.
SAAS is now looking to expand the pilot to allow the upload of a large
batch of applications to the NFI system quickly, securely and easily.
Case study
A new NFI pilot matching National Entitlement cards in 
Fife Council against deceased person records identified
one card that had been fraudulently used for bus travel valued at almost
£2,300 after the cardholder had died. Investigations are continuing into
the individual(s) who used this card.
The National Fraud Initiative in Scotland 2022 | 23 |260

Page 261

Future developments
The 2022/23 NFI exercise is due to start in late summer 2022. Datasets have been reviewed and updated as necessary.
Audit Scotland continues to work with the Cabinet Office
in developing new ways to prevent and detect fraud. This
includes piloting new data matching opportunities.
The Scottish Parliament approved The Digital Government (Scottish
Bodies) Regulations 2022 in March 2022. These Regulations name
Audit Scotland under Regulation 3 - ‘Scottish bodies for the disclosure
of information in relation to fraud against the public sector’. This allows
Audit Scotland to access HM Revenue & Customs income and savings
data for Scottish residents for future NFI exercises. This will help identify
outcomes where customers have received benefits and services above
what they are entitled to.
Audit Scotland continues to work with the Scottish Government in
promoting and enhancing participation in the NFI across Scotland.
The Scottish Parliament’s Public Audit Committee (PAC) is considering
the expansion of legislative powers around the NFI. This may include
expanding the NFI to bodies in receipt of significant amounts of public
funding that do not fall under the audit remit of the Auditor General for
Scotland or the Accounts Commission.
The Cabinet Office recently consulted on extending its legal powers
around the purposes for which data matching can be used. It is looking
to potentially extend its legal powers in the following areas:
• to assist in the prevention and detection of crime other than fraud
• to assist in the apprehension and prosecution of offenders
• to assist in prevention and detection of errors and inaccuracies. The
NFI data could be used to help public-sector bodies to ensure citizens
get access to their full benefit entitlements. For example, a number
of passported benefits across the welfare system entitle recipients
to help with housing costs, free school meals, etc. A match could
identify citizens entitled to additional help they are not claiming
• to assist in the recovery of debt owing to public bodies. Public bodies
may need to trace individuals with outstanding overdue debt and with
no arrangement to pay in place. In some instances, these individuals
may be difficult to trace. The NFI data could be used to help identify
where a debtor was living or working, for example.
The Cabinet Office is considering the responses and will publish a formal
consultation response in due course.
Section 97 of the Criminal Justice and Licensing Act 2010 already
permits Audit Scotland to use data matching for the first two purposes.
We will monitor developments.
The National Fraud Initiative in Scotland 2022 | 24 |261

Page 262

Appendix 1. Background to the NFI
The NFI is a counter-fraud exercise across the UK public sector which aims to prevent and detect fraud. The Cabinet Office
oversees it, and Audit Scotland leads the exercise in Scotland, working with a range of Scottish public bodies and external auditors.
The NFI uses data sharing and matching to help
confirm that services are provided to the correct people.
The NFI takes place every second year. 132 public-
sector bodies in Scotland participated in the 2020/21
exercise including councils, NHS bodies, colleges and
larger central government bodies such as the Scottish
Government, Revenue Scotland and Transport Scotland.
A full list of participants is available here.
The NFI enables public bodies to use computer 
data matching techniques to detect fraud and error.
We carry out the NFI under powers in The Criminal
Justice and Licensing (Scotland) Act 2010. It is
important for all parties involved that this exercise is
properly controlled, and data is handled in accordance
with the law. The Audit Scotland Code of Data
Matching Practice includes a summary of the
key legislation and controls governing the NFI data
matching exercise.
Although the main purpose of the NFI is to ensure
funds and services are provided to the correct
people, the review of NFI matches may also identify
that a customer is entitled to additional services or
payments, eg housing benefit matches may identify
customers entitled to council tax discount or reduction.  
Data matching exercise every
two years in partnership with
the Cabinet Office
Participating bodies submit
data to a secure website
NFI outcomes are reported by
participating bodies, auditors
and Audit Scotland 
The NFI system matches data
within and between bodies to
identify anomalies 
Auditors monitor participating
bodies' processes and progress
Potential anomalies called
‘matches’ are reported to
participating bodies to review,
investigate and record outcomes  
The National Fraud Initiative in Scotland 2022 | 25 |262

Page 263

Appendix 2. Costs and benefits
of participating in the NFI
The Scottish Parliament provides funding to Audit Scotland to cover public-sector participants’ NFI fees for the biennial data
matching exercise.
Participating bodies incur costs following up
matches and investigating. Participating bodies
also incur costs for pilot work and additional
services such as the AppCheck pre-application
screening and the ReCheck4 flexible data
matching service.
Many bodies do not keep separate records
for NFI costs as it is just one of many counter-
fraud activities they are doing. Those that
do have records were able to estimate that
their costs ranged from £500 to £71,000.
This compares favourably with the average
outcome for each public body in Scotland of
£113,000 for the 2020/21 NFI exercise.
Overall, the £14.9 million of outcomes from the
2020/21 NFI outweigh the costs.
£8,416 £204,500
Average reported cost of NFI
(total of 25 bodies)
Audit Scotland costs
4. ReCheck is a flexible data matching
service that complements the NFI biennial
national exercise. It allows NFI participants
re-perform the existing NFI data matching
at a time that suits them.
No. of bodies reported Cost range
Councils 0 £0
Other local 
government
bodies
2 £1,397 – £5,000
NHS bodies 7 £1,277 – £71,000
Central 
government
bodies
11 £590 – £20,000
Colleges 5 £500 – £6,000
The National Fraud Initiative in Scotland 2022 | 26 |263

Page 264

Appendix 3. Estimation bases
The figures used in this report for fraud, overpayments and errors include outcomes already delivered (actual amounts
participants have recorded) and estimates. Estimates are included where it is reasonable to assume that incidents of fraud,
overpayments and errors would have continued undetected without NFI data matching.
Details of estimate calculations used in the report are shown below.
Data match Basis of calculation of estimated outcomes 
Council tax single 
person discount  Annual value of the discount cancelled multiplied by two years. 
Housing £93,000 per property recovered, based on average four-year fraudulent tenancy. Includes: temporary accommodation for genuine
applicants; legal costs to recover property; re-let cost; and rent foregone during the void period between tenancies.
Housing benefit  Weekly benefit reduction multiplied by 21 weeks. 
Pensions  Annual pension multiplied by the number of years until the pensioner would have reached the age of 85. 
Payroll   £5,000 for each employee dismissed or resigns as a result of NFI matching, or £10,000 for each resignation or dismissal for
employees who have no right to work in the UK. 
Council tax 
reduction scheme Weekly change in council tax discount multiplied by 21 weeks.
Housing waiting lists £3,240 for each case based on the annual estimated cost of housing a family in temporary accommodation, the duration a fraud
may continue undetected and the likelihood a waiting list applicant would be provided a property.
Blue badges  Number of badge holders confirmed as having died multiplied by £575 to reflect lost parking and congestion charge revenue.
The National Fraud Initiative in Scotland 2022 | 27 |264

Page 265

The National Fraud
Initiative in Scotland
2022
Audit Scotland’s published material is
available for download on the website in a
number of formats. For information on our
accessibility principles, please visit:
www.audit-scotland.gov.uk/accessibility
For the latest news follow us on social media
or subscribe to our email alerts.
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit-scotland.gov.uk
www.audit-scotland.gov.uk
ISBN 978 1 913287 91 7
265

Page 266

266