NORTH AYRSHIRE COUNCIL 
15 November 2022 
Audit and Scrutiny Committee 
Title:    Internal Audit and Corporate Fraud Action Plans: 
Quarter 2 update 
Purpose:  To advise the Audit and Scrutiny Committee on the progress
made by Council Services in implementing the agreed actions
from Internal Audit and Corporate Fraud reports as at 30
September 2022. 
Recommendation:  That the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions;
and (b) challenges those Services that have not implemented
actions within the previously agreed timescales. 
1. Executive Summary 
1.1 The CIPFA document 'Audit Committee Principles in Local Authorities in Scotland'
highlights that Audit Committees should monitor and review the progress made in
implementing audit recommendations. 
1.2 Service managers are responsible for ensuring that agreed actions arising from
Internal Audit and Corporate Fraud reviews are implemented.  This provides
assurance that identified control weaknesses have been addressed and are being
managed effectively. 
1.3 All actions are monitored on the Pentana system and service managers are
responsible for updating Pentana as they progress each action.  This enables Internal
Audit to monitor progress on a 'real-time' basis and address any delays in
implementation. 
1.4 This report details the position at 30 September 2022. 
2. Background 
2.1 The last report to the Audit and Scrutiny Committee on 27 September 2022
highlighted that there were 28 actions outstanding at the end of June 2022: nine that
had not been started or were only partially implemented and 19 where the due date
had not yet passed.

Page 2

2.2 In addition to these 28 carried forward actions, there have been eight new actions
agreed, giving a total of 36 action points for review. 
2.3 Services have completed 23 actions since the last report.  All Council Services are
required to retain evidence of work carried out in completing their actions and Internal
Audit carries out 'spot-checks' on a sample of completed actions on an ongoing basis. 
2.4 Of the remaining 13 actions, one was either not started or only partially complete at 30
September 2022 and the remaining 12 were not due for completion until after that
date. 
2.5 Appendix 1 to this report provides the Committee with full details of the action that was
not complete within the agreed timescales. 
3. Proposals 
3.1 It is proposed that the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions; and (b) challenges
those Services that have not implemented actions within the previously agreed
timescales. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The effective implementation of agreed Internal Audit and Corporate Fraud actions
helps to support the efficient delivery of the strategic priorities within the Council Plan
2019-2024.

Page 3

Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Council Services are consulted during the completion of each Internal Audit and
Corporate Fraud review and have also provided updates on progress made in
implementing action points. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294 324524. 
Background Papers
None.

Page 4

Actions due by 30th September but not started or partially complete 
Code IA2020PA032a Description
Audit Action: Arran should be aligned with the mainland’s processes and
procedures.
Audit Finding: Staff on the mainland and Cumbrae are managing the interment
process electronically, whilst staff on Arran continue to use manual records.
Risk: Business continuity issues due to operating a completely separate system on
Arran; manual records are not backed-up in the same way that electronic records are.  
Priority 2 Latest Note
The Service is working with IT to complete the Data Protection Impact Assessment in
order to progress with the upgrade, we are confident this will be completed and
processed by end of December 2022.
Progress Bar  Original Due Date 31-Mar-2021 Due Date 31-Jul-2022
Parent Code & Title IA2020PA032 Bereavement and Burial Services
Managed By David Hammond
Assigned To Mark McNeil