Democracy Spraffa

6 - 2022 09 13 Strategic Risk Register 2022-23

North Ayrshire Council · 27 September 2022
Back to Audit and Scrutiny Committee — 27 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

NORTH AYRSHIRE COUNCIL
27 September 2022                                                                                                                                                            
Audit and Scrutiny Committee
Title: Strategic Risk Register 2022/23
Purpose: To inform the Committee of the Council’s agreed Strategic Risk
Register for 2022/23.
Recommendation: That Committee notes the Strategic Risk Register.
1. Executive Summary
1.1 The Strategic Risk Register has been reviewed and updated for 2022/23.
1.2 Six of the eight previous risks remain on the Strategic Risk Register at their existing risk
scores and titles – Financial Environment, Inequalities, Cyber Security, Transformation,
Climate Change and Community Capacity Building & Empowerment.
1.3 Financial Sustainability of the Health and Social Care Partnership has reduced in risk
score from 16 to 12 as a result of further positive corrective actions improving the
partnerships financial position.
1.4 A risk relating to the impact of Covid-19 was tabled at Cabinet in March 2020 as the
pandemic emerged. This risk has been renamed ‘Operating Environment’ and updated
to take account of the challenges of recovery and the uncertain operating environment.
1.5 The Strategic Risk Register was agreed by Cabinet on 7 June 2022.
1.6 It is noted that there are emerging risks associated with the creation of a National Care
Service and officers are currently working to incorporate this into the next update to the
Strategic Risk Register.
2. Background
2.1 North Ayrshire Council is committed to ensuring that it is proactive in identifying and
managing the risks impacting on the authority. The Council recognises that a certain
amount of risk is inevitable if the organisation is to achieve its objectives.
2.2 The aim of risk management is to reduce the likelihood and/or impact of risk by
identifying and controlling risks to the Council.  If risk is to be managed appropriately,
and Services are aware of these risks, risk management can contribute positively

Page 2

towards the organisation's decision-making processes, making the Council more
innovative and effective in its approach to service delivery. 
2.3 The most significant risks are identified through the Council's Strategic Risk Register
(SRR), recognising the challenges facing the Council and demonstrating the
arrangements in place to manage these risks. 
2.4 The Strategic Risk Register has been reviewed and updated for 2022/23 and is
attached at Appendix 1 to this report.  For each of the risks detailed within the register
a number of components are identified: 
• Risk proximity factors.
• Risk score.
• Potential effect on the Council's priorities.
• Internal controls currently in place.
• Assessment of controls, and
• Additional actions identified. 
2.5 To assist in the assessment of each risk, the Council’s agreed risk matrix was used to
ensure consistency. This is used to assess the likelihood of occurrence (on a scale from
1 to 5) and the significance of the impact of the risk should it occur (on a scale from 1
to 5). The risk score is the product of likelihood multiplied by impact. Only those risks
rated as high or very high (10 or above) will feature on the SRR to ensure a focus on
managing the most significant risks. 
2.6 Six risks remain on the Strategic Risk Register at their existing risk scores – Financial
Environment, Inequalities, Cyber Security, Transformation, Climate Change and
Community Capacity Building and Empowerment. 
2.7 Financial Sustainability of the Health and Social Care Partnership has reduced risk
score from 16 to 12 which is a continuous line of improvement following a reduction
from 20 to 16 in 2021/22. 
2.8 A risk relating to the impact of Covid-19 was tabled at Cabinet in March 2020 as the
pandemic emerged and wording subsequently formulated. This risk has now been
renamed ‘Operating Environment’ and updated to consider the challenging emerging
risks. This considers a number of proximate and relevant risks such as recovery, living
with covid, Inflation impacts - cost of living and supply chain/construction inflation. 
2.9 Very High Risks  
• Financial Environment - this risk reflects the ongoing financial challenge faced
by the Council. (risk score 20)
• Inequalities - this highlights the socio-economic inequalities faced in North
Ayrshire. (risk score 20)
• Emergent Operating Environment – this risk reflects the challenges the
Council and its partners are facing as we move out of a covid control
environment requiring agile strategy. (risk score 20) 
High Risks

Page 3

• Cyber Security – this reflects the ongoing risk from external cyber-attack which
is being faced by all organisations. (risk score 16)
• Transformation - this reflects the wider risks associated with delivering the
current Transformation Programme and developing a pipeline of future
initiatives. (risk score 16)
• Climate Change – this risk has been on the Strategic Risk Register following the
declaration by the Council of a Climate Change Emergency during 2019 (risk
score 16).
• Financial Sustainability of the Health and Social Care Partnership - this
reflects the ongoing financial challenges faced by the Partnership and the risk
these present to the Council. (risk score 12 – reduced from 16)
• Community Capacity Building and Empowerment - this highlights the
challenges associated with community empowerment (risk score 12). 
2.10 Council Services have identified high level strategic actions within their planning for
2022/23 to help the Council mitigate against its strategic risks. These actions are
detailed in summary format in the Risk Management Action Plans following each Risk
within Appendix 1.  These actions will assist with performance monitoring and reporting
on the strategic risks. 
2.11 The Council’s Internal Audit Plan 2022/23 was approved at the Audit and Scrutiny
Committee on 8 March 2022 and is risk-based with clear links in place between the
audit plan and key risks the Council faces. 
3. Proposals 
3.1 Committee is requested to note the Strategic Risk Register 2022/23. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Council continues to have a robust long- and medium-term financial planning
framework. Key strands include development of key transformation themes and the
establishment of an Investment Fund that will generate future savings alongside
delivery of a number of key Council priorities. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 The risk to the Council is that North Ayrshire residents, and in particular certain
groups, will experience increasing levels of poverty and its effects. Current control
measures fall into two categories - measures to address the root causes of socio-

Page 4

economic inequalities - income through employment or benefits – and mitigation
measures to minimise the impacts of poverty. 
Climate Change and Carbon 
4.5 The Council has declared a climate change emergency and has in place an
Environmental Sustainability and Climate Change Strategy. Significant work to help
mitigate the risk of flooding is included within the Capital Plan. The Council is
undertaking an ambitious renewable energy programme. 
Key Priorities 
4.6 A successful risk management framework helps to underpin the delivery of the Council’s
strategic priorities in the Council Plan 2019-2024. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The Strategic Risk Register has been reviewed and updated in consultation with the
Executive Leadership Team and the Corporate Risk Management Group and approved
by Cabinet. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294-324524. 
Background Papers
None.

Page 5

Appendix 1 - Strategic Risk Report 2022/23
Risk Code SRR2223_R01 Risk Title Financial Environment Latest Note Date 20-Feb-2022 
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The risk is that the level of funding from
Scottish Government to local government
will require the Council to take increasingly
difficult and challenging decisions,
potentially operating with increased levels of
risk to ensure service delivery and
investment in assets align with available
resources. Although the 2022/23 local
government settlement represents an
increase of 0.90% in core grant funding, this
has to continue to be looked at within the
context of financial pressures facing the
council including pay, contractual and
demographic pressures over the short,
medium and long term and more recently
through the significant inflationary pressures
faced by the council. The continuation of
single year settlements makes effective
medium and long term financial planning
challenging. It is recommended that
following the settlement and within the wider
financial pressure context, the risk score
remains unchanged at this time. Any
consideration to change this will only occur
following a sustained period of annual
growth in core revenue funding.
The Council is exposed to financial risk as a
result of underlying cost pressures within the
IJB; more detail on this is set out at risk
SRR03.  
Funding not keeping pace with demand and
cost means that there will be a reduction in
some service areas potentially resulting in
higher risks for service users.  
Robust monitoring of the Council’s revenue and capital
budgets is in place as well as regular reporting of
financial performance of the IJB to Cabinet and Audit
and Scrutiny. 
To assist financial planning The Long Term Financial
Outlook (LTFO) to 2030/31 was approved at Council
on 16 December 2020 - this is the cornerstone of the
Council's financial planning in the medium to long
term. 
The Council approved a balanced budget for 2022/23
on  2 March 2022. Further funding of £3.209m was
announced by SG on 27 January 2022, taking the
settlement to a 0.90% increase from last year. A range
of additional finance pressures have been identified
including additional national insurance contributions,
energy cost inflation, contractual commitments as well
as significant construction inflation coming through the
capital programme. 
Based on the outturn position in 2021/22 for the IJB,
the annual debt repayment to the Council of £1.497m
will again be achieved and it anticipated the debt will
reduce from £3.807m to £2.310m at 31 March 2022.
This position is further supported by the creation of an
unearmarked reserve currently sitting at over £4m.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 20

Page 6

Strategic Risk Action Plan Date Updated 20-Feb-2022
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Regular financial monitoring of Revenue and
Capital Budgets  
20 February 2022: 
Bi-monthly monitoring  
31-Mar-2024 Mark Boyd 
Deliver balanced Budget for 2022/23
20 February 2022:
Budget delivered for 2022
02-Mar-2022 Mark Boyd 
Maintain Financial Governance
Arrangements for IJB  
20 February 2022:
Bi-monthly monitoring.  
31-Mar-2024 Mark Boyd 
Progress dialogue via COSLA with Scottish
Government on a range of areas including
fair funding, multi-year settlements,
reduction in levels of ring-fenced resources,
true costs of SG policy areas and financial
flexibilities
20 February 2022:
Regular engagement through Directors of finance group
31-Mar-2024 Mark Boyd

Page 7

Risk Code SRR2223_R02 Risk Title Inequalities Latest Note Date 16-Feb-2022
Risk Owner Audrey Sutton/Caroline Amos
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
North Ayrshire residents, and in particular
certain excluded groups, will experience
increasing levels of poverty and its effects,
as a result both of the economic situation
and Covid-19. 
Health inequality is closely linked to poverty,
employment and people's earliest
experiences as children, and will increase. 
The population of North Ayrshire is
projected to fall over the next 10 years but
there will also be a larger proportion of the
population considered dependent (not
economically active).  
The impact on specific risk groups is
greatest for our children, young people and
families, unemployed people and those in
in-work poverty and people exposed to the
risks of drug and alcohol addiction. 
Demand for HSCP and Council Services
will increase. 
As reductions in resources increase, early
intervention and prevention activities are at
risk, thus increasing the potential for an
increase in costly crisis interventions. 
The local economy will be impacted by
reduced spending power by economically
inactive residents.  
Tackling inequalities is a strategic priority of the Community
Planning Partnership (CPP), the Council and the HSCP. 
Current poverty-related controls fall into two categories:
measures to address the root causes of socio-economic
inequalities – income through employment or benefits – and
mitigation measures to minimise the impacts of poverty. A
range of strategies are in place: Fair for All, Children’s
Services Plan, the Child Poverty Action Plan, Economic
Renewal Strategy, Community Wealth Building, the
Ayrshire Growth Deal. 
The HSCP tackles inequalities in areas of economy, health
and community. Through the HSCP strategic plan, the
Partnership sets out actions to tackle inequality through its
Partnership Pledge and across its strategic priorities. 
The Alcohol and Drug Partnership has a focus on drug and
alcohol misuse, with a focus on reducing the numbers of
drug related deaths. 
The ‘Housing First’ programme provides tenancies for the
most vulnerable homeless people in North Ayrshire, initially
targeting households with addiction and mental health
issues on discharge from prison. 
Through Covid-19 responses a whole system approach is
being developed to support residents through a place
based model of locality hubs and multi-agency locality
working. 
We continue to progress work to fulfil our commitment in
equality of opportunity in employment for all our employees.
The Council’s pioneering Community Wealth Building
Strategy focuses on five pillars to reduce inequalities and
work is well underway on procurement, land and assets
and fair employment.  
5 4
Status Risk Score
Heat Map 
Change in Score Approach
No Change Treat
Increasing 20

Page 8

Strategic Risk Action Plan Date Updated 11-Feb-2022 
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Many of the current controls are in early to
medium stages of implementation: 
Fair for All (ongoing) 
Children’s Services Plan (new plan) 
Child Poverty Action Plan (new annual plan) 
HSCP Strategic Plan (new plan) 
Economic Renewal Strategy (new strategy) 
Community Wealth Building (in delivery) 
Ayrshire Growth Deal (launched and
underway)  
New Ayrshire Regional Economic Strategy
under development underpinned by a CWB
approach to create an inclusive economy
Recovery & Renewal Strategy 
11 February 2022:
Each of these strategies, taken together, and further developed and
implemented, should make a significant contribution to inequalities. 
Actions are being progressed and remain within the Target date for
completion.  
Commissioning commenced in Feb 22.
31-Mar-2024 Audrey Sutton/Caroline
Amos; Caroline Cameron

Page 9

Risk Code SRR2223_R03 Risk Title Financial Sustainability of the Health and Social Care Partnership Latest Note Date 08-Feb-2022 
Risk Owner Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Uncertainty of future funding against
growing demand and demographic
pressures.
Resources have not kept pace with the
demand for and cost of social care services. 
There remains uncertainty around Covid-
related costs and how these ongoing costs
will be funded in the longer-term.
In earlier years, the HSCP did not manage
to contain spend within the delegated
budget, but surpluses were achieved in 20-
21 and 21-22. Outstanding debt to the
Council is currently £2.321m following
repayments 20/21 and 21/22. A further
repayment of £1.486m will be made at the
end of 22/23.
Current Scottish Government proposals to
introduce a National Care Service (NCS) by
2026 will significantly impact on the IJB. A
consultation on the NCS closed in
November 2021 and legislation will be
developed by Summer 2022.
Significant inflationary pressures across
employee pay and contractual costs will
increase the financial challenges for the
Partnership.
Funding levels could result in savings being
made that are not in alignment with the
strategic plan. This could impact on the
future demand levels e.g. reduction in early
intervention and prevention means that
future demand is increased. 
Funding levels increase the requirement to
transform services at scale and pace.
In 2020-21 and 2021-22, the Partnership
was in an underspend position.
The impact of the National Care Service will
become clearer as legislation is progressed.
The IJB actively monitors the financial position with
regular detailed reporting. Directors of Finance of the
Council and Health Board have oversight and regular
updates are provided to the Council's Cabinet.
There is an integrated approach to managing the
totality of NHS and Council resources delegated to the
IJB. The Medium-Term Financial Plan for 2022-25 has
been presented to the March 2022 IJB. Previous
financial settlements have seen both partners meet
the Scottish Government settlement conditions with
any additional resources passed to the IJB.
The IJB had uncommitted reserves of £4.151m (at
01/04/21) and this position is expected to improve at
the end of 21/22. It is anticipated that uncommitted
reserves will be towards the lower end of the good
practice target of 2%-4%.
Significant funding has been provided to IJBs for the
Covid-19 response, supported by regular financial
returns to the Scottish Government. Costs were fully
funded in 20/21 and 21/22 and funding was received
late in 21/22 which has been carried forward into
22/23 to support ongoing Covid-related costs.
The Scottish Government recently announced
additional funding for the areas below which support
the sustainability of the HSCP:
: Enhanced Care at Home capacity
: Interim Care
: Multi-Disciplinary Teams; and
: Mental Health Recovery and Renewal 
The Partnership has a Transformation Board
overseeing the programme of service re-design.
3 4
Status Risk Score
Heat Map 
Change in Score Approach
Reduced from 16 to 12 Tolerate
Reducing 12

Page 10

Strategic Risk Action Plan Date Updated 08-Feb-2022 
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Budget Monitoring - Regular budget
monitoring reports to IJB are effective.  
8 February 2022:
No additional actions planned at this time but will keep under review
31-Mar-2024
Caroline Cameron;
Paul Doak 
Corrective Action – Transformation Board is
effective  
8 February 2022:
No additional actions planned at this time but will keep under review.
31-Mar-2024
Caroline Cameron;
Paul Doak

Page 11

Risk Code SRR2223_R04 Risk Title Cyber Security Latest Note Date 03-Feb-2022 
Risk Owner Fiona Walker
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The potential compromise of business
operations or a data breach orchestrated via
either digital channels or the IT
infrastructure. This can include targeting of
the user base. Risk derives from both
Council operations and those of its supply
chain. 
The increasing importance of delivering
services through digital channels and
maximising efficiency through effective and
secure use of technology. This includes a
growing adoption of cloud-based computing
resources which extend processing
capabilities, and associated risks, beyond
the Council’s network. 
The ongoing response to the Covid-19
pandemic has resulted in the remote and
mobile working by staff as effectively being
the normal working practice. This is likely to
continue as a hybrid approach becomes the
new normal.  Such a distributed work force
increases the complexity of protecting
against cyber and data protection risks.  
Failure by Services to adopt and comply
with strategies, policies and procedures
may result in a failure to adequately ensure
the desired levels of cyber-security required
to maintain and protect council systems and
data. 
There may be a significant impact on the
authority through the release of personal
and/or sensitive information resulting in a
loss of public confidence and significant
financial loss incurred through fines and
service disruption. 
A successful cyber-attack (malicious
external or internal action) on the Council’s
IT environments could also result in
significant service disruption, loss of income
streams and possible data loss/exposure. 
Impacts of a cyber-attack could include
economic (i.e. inability to collect online
payments), societal disruption (i.e. loss of
diaries and client appointments), and
reputational damage (i.e. loss of public
confidence in digital services).  
It is recognised that it is not possible for any
organisation to expect to be completely protected
against continually evolving cyber threats. A threat
actor with sufficient motivation, resource and capability
will be able to compromise the most secure system. 
The Council takes a sociotechnical approach to
reducing risk by continually developing protective
measures through technical, organisational and
people-focused controls. 
Technical controls are implemented in areas such as
network defences, secure configuration of systems,
user authentication, malware protection, and
vulnerability management. These are based on best
practice and independently tested on an annual basis
to confirm their effectiveness in accordance with
compliance schemes. 
The Council maintains a comprehensive set of
policies, standards, guidelines, metrics and reporting
mechanisms as part of its information security
governance structure. A comprehensive training and
awareness programme is delivered to nurture a cyber-
aware workforce and culture.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 12

Strategic Risk Action Plan Date Updated 03-Feb-2022
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Incident Detection and Response – Recent
cyber-attacks on public sector organisations
highlight the need for robust incident
detection and response procedures and
technologies. The current response
procedures been shown to be effective
based on incidents experienced so far,
however detection capabilities will need to
be reviewed and improved.  
3 February 2022:
In progress – Documenting and embedding of specific response
procedures has still to be completed. Revised target date of 31st
December 2022 taking cognisance of ongoing recruitment process for
a replacement cyber security lead.
31-Dec-2022 Fiona Walker 
3 February 2022:
In progress – A joint procurement of a Managed Security Operations
Centre (SOC) service with other local authorities is being taken
forward by the Digital Office.  The intention is to have this agreed by
April 2022 and implemented by the end of 2022. 
31-Dec-2022 Fiona Walker 
3 February 2022:
In progress – The investigation of potential options and quotes is still
underway with Aon.  The risk assessment is complete and will now be
used in discussions to establish whether it is possible to broker for
quotes.  Revised target date of 31st December 2022 taking
cognisance of ongoing recruitment process for a replacement cyber
security lead.
31-Dec-2022 Fiona Walker 
Training and Awareness – The pandemic
has impacted on the cyber training
programme with the long-term cancellation
of all classroom-based training. However, a
new online course was launched to
compensate for this.  
3 February 2022:
In progress – Review of effectiveness still to be undertaken. Revised
target date of 31st December 2022 taking cognisance of ongoing
recruitment process for a replacement cyber security lead.
31-Dec-2022 Fiona Walker

Page 13

Risk Code SRR2223_R05 Risk Title Transformation Latest Note Date 20-Feb-2022
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
There is an overarching risk that
transformation and change management
activities, which are core to the future
delivery models and long-term financial
sustainability of both the Council and Health
and Social Care Partnership, fail to deliver.  
Failure to deliver transformational change
will impact on the Council’s financial
sustainability, effectiveness of service
delivery and delivery of the outcomes set
out in the Council Plan 2019-24 and the
Local Outcome Improvement Plan (LOIP). 
Failure to deliver the HSCP Transformation
programmes across the Partnership,
involving North Ayrshire Council (NAC) and
NHS Ayrshire & Arran (NHSAA) services
may lead to the identified outcomes not
being delivered; resulting in financial
instability, reduced performance,
deteriorating patient outcomes, and
reputational damage within North Ayrshire
Health and Social Care Partnership
(NAHSCP). 
Failure to embed cultural transformation
activities may lead to difficulties in building
future workforce capacity and in ensuring
we have an engaged, skilled and
knowledgeable workforce to meet service
demand.  
The transformation programme aligns to the Council Plan and is
monitored via the Executive Leadership Team (ELT) and the
Transformation Board.
Workstreams have been developed across Transport and Travel,
Accessing our Council, Land and Property, Our Future Working
Environment and Sustainable energy. 
A Benefits Tracking monitoring tool is being developed to ensure
financial and wider outcomes, aligned to our Transformation plan, are
captured. 
HSCP have an established Transformation Board to closely monitor
progress with plans, regular updates on programme to the IJB and
regular meetings with the Chief Executive and S95 Officer to review
progress and mitigation plans. IJB will approve budget and Strategic
Plan for 2022-23 which will align financial plans with transformational
strategic change ambitions. 
Cultural transformation activities continue to evolve to support the
Council’s transformation and improve effectiveness and capability.
This includes sharing learning and skills, engagement, design
experiments and a whole systems approach to transformation and
change. 
Our workforce planning approach utilises a variety of tools and
techniques, such as career development, succession planning,
vacancy management, redeployment and early release schemes to
ensure our workforce requirements for the future, in terms of skills and
capabilities, are planned. Each Head of Service has a workforce plan,
and these are monitored six-monthly with continued HR support and
guidance to ensure service review and redesign of the workforce is on
track. 
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 14

Strategic Risk Action Plan Date Updated 20-Feb-2022
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Existing project level governance and
controls remain effective and are constantly
reviewed. 
20 February 2022:
Transformation has recently moved to the Finance Service and
continues to progress existing plans as well as integrating into the
service and associated workstreams.   
Mark Boyd

Page 15

Risk Code SRR2122_R06 Risk Title Climate Change Latest Note Date 22-Feb-2022
Risk Owner David Hammond
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Climate change is expected to continue and
worsen in the future if no action is taken,
with increases to mean global temperatures,
sea level rise and the increasing frequency
and severity of weather events such as
floods, heatwaves, droughts and storms. 
More frequent and intense heavy rainfall
events increase the risk of soil erosion and
flooding. 
Rises in mean sea level increases risks of
coastal erosion, flooding, saltwater intrusion
and soil salinisation (risk to agricultural land
and freshwater habitats). 
Severe weather is already affecting public
services across Scotland, with operational,
reputational, financial and legal
consequences. 
There is also an ongoing impact of severe
winter weather including snowfall and
freezing temperatures which impact service
delivery and the integrity of our roads open
space and buildings infrastructure. This shift
in weather patterns caused by climate
change is also affecting biodiversity across
Scotland.  
Increased frequency of severe weather
conditions and flooding events may lead to
more instances of damage to Council
infrastructure and property, interruptions to
service delivery and increased demands on
services, often with little notice. 
Risk to life, transport disruption and
pollution to the local environment, as well as
impact adversely on the local economy if
businesses are unable to operate. 
Council requirement to provide immediate
response and manage the adverse effects
of more frequent and severe weather
emergency situations, including support to
local communities and businesses. 
The Council is required to comply with the
‘Public Bodies Climate Change Duties’
under the Climate Change (Scotland) Act
2009. These duties require the Council to
assess the risks, threats and opportunities
associated with climate change and identify
actions to increase resilience to climate
change.  
North Ayrshire Council declared a Climate Emergency
in June 2019, committing to act on climate change and
reduce carbon emissions. In January 2020 the Council
approved the target to become net-zero carbon by
2030. 
The third iteration of the Environmental Sustainability
& Climate Change Strategy was approved by Cabinet
in May 2021, providing a road map to achieve the net
zero carbon emissions by 2030 target.  Climate
Change Adaptation has been included as a
workstream within the new strategy, utilising
Adaptation Scotland’s Capability Framework to ensure
North Ayrshire takes a strong, proactive approach to
adapting to climate change.  Officers are participating
in the Sustainable Scotland Network’s ‘Adaptation
Scotland Benchmarking Group’ to learn and share
best practice with other local authorities.
The Flood Risk Management Strategy has been
developed into a 6-year plan which began in 2016. A
second plan, which will follow on, is in development. 
In addition, actions to mitigate Climate Change risk are
held within strategies such as the Core Paths Plan,
Outdoor Access Strategy, Local Biodiversity Action
Plan, and Weather and Winter Emergencies Plan.
Asset management plans are in place which are
regularly reviewed for our Roads, Fleet, Housing,
Property and Open Spaces. 
Furthermore, through the Ayrshire Civil Contingencies
Team there are emergency planning arrangements in
place in the event of severe weather and flooding
conditions causing major disruption and damage to the
area or to individual communities within it. 
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 16

Strategic Risk Action Plan Date Updated 22-Feb-2022
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Reducing Carbon Emissions:
North Ayrshire Council declared a Climate
Emergency in June 2019, committing to act
on climate change and reduce carbon
emissions. In January 2020 the Council
approved the target to become net-zero
carbon by 2030. 
We have seen a reduction in overall carbon
emissions in the first half of 2021/2022 from
9,918tCO2 to 9,706 tCO2.
Existing controls remain effective and are
under review as our response to climate
change develops and we progress towards
achieving net zero by the 2030 target.  
22 February 2022:
Continuing the Implementation of the 3rd Environmental
Sustainability & Climate Change Strategy, which Includes a
Roadmap with actions towards achieving the target. The ESCCS 3
contains workstreams: 
• Affordable Warmth 
• Green Economy 
• Transport and Travel 
• Natural Environment 
• Sustainable Operations 
• Carbon Absorption 
• Climate Change Adaptation, which follows Adaptation Scotland’s
Capability Framework, to build a climate resilient North Ayrshire. 
Significant progress has been made in 2021/22 and this will be built
on in 2022/23.  Actions are being progressed and remain within the
Target date for completion.   
31-Mar-2023 David Hammond 
The Flood Risk Management Strategy: 
This has been developed into a multi-year
plan which began in 2016. The strategy
involves taking a proactive approach to flood
protection, using modelling to identify
vulnerable assets. Assets will then be
protected on a prioritised basis taking
financial damages and other impacts such
as danger to life and disruption into account. 
Existing controls remain effective and are
under review as our response to climate
change develops and we progress towards
achieving net zero by 2030 target.  
22 February 2022:
We will continue the implementation of the flood risk management
strategy and develop the next flood risk plans. Adaptation to the
impacts of climate change can be seen in the Flood Protection
Schemes being developed and delivered in the Upper Garnock
Valley and Millport. This is a continuous risk based and cyclical
process. 
31-02-2024 David Hammond

Page 17

Risk Code SRR2122_R07 Risk Title Community Capacity Building and Empowerment Latest Note Date 20-Feb-2022
Risk Owner Rhona Arthur
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Unrealistic timescales for implementation of
aspects of legislation of the Community
Empowerment Act (Scotland) 2015, such as
Community Asset Transfer. 
Pressure to support community capacity
building and the variation of needs within a
reducing workforce. 
Duplication of effort across HSCP and
Locality Partnerships to foster community
participation and deliver engagement
activities.
Complying with the complex consultation
legislation in service redesign.  
Where the risk is not managed effectively
the potential benefits of community capacity
building and empowerment may be lost. 
Widening inequality gap between those
communities where levels of capacity and
engagement with the empowerment agenda
are high and those with less social capital
where interest remains low, which
constrains the ability to influence the
planning and delivery service. 
Any disconnect between the Council’s
aspirations, community appetite for
increasing ownership of assets and what
communities themselves feel able and
prepared to commit to can result in
community assets reverting back to Council. 
Accelerating asset transfer risks losing
services and facilities. 
Over-engagement carries disengagement
and engagement fatigue.  
Ongoing commitment to community empowerment
and locality partnerships from CPP. 
Six locality partnerships and alignment with HSCP
locality arrangements. 
Leadership of the CPP Senior Officers’ Group. 
Enabling approach with community partners and
support with third sector interface to build capacity and
identify opportunities for growth and sustainability. 
Reviewed guidance and processes relating to asset
transfer, allotment and Community Councils. 
Participatory budgeting approach local grants,
commitment to PB with partners and leading practice
in mainstreaming participatory approaches 
External funding bid help for groups through regular
meetings with third sector, funders and funding
officers. 
Membership of The Consultation Institute.  
Additional investment of £1m for a Community Asset
Transfer Start Up Fund, prioritising additional staffing
capacity to support CAT in Connected Communities
and TACT.  
3 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Tolerate
Stable 12

Page 18

Strategic Risk Action Plan Date Updated 20-Feb-2022
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Implementation of CEA: 
Existing controls remain effective and are
keep under review to monitor the impact of
Covid-19.  
22 February 2022:
Strategic CLD Plan 2021-2024 identifies priorities for capacity
building and the programme of community support is addressing
needs. New larders and Community Cafes are being supported by
the NA Food System. All other actions are being progressed and
remain within the Target date for completions.
31-Mar-2024 Rhona Arthur 
Implementation of CEA:
Existing controls remain effective and are
keep under review to monitor the impact of
Covid-19.  
20 February 2022:
Action ongoing to test current community priorities with recent
consultation on the Local Outcome Improvements Plan.
30-Mar-2022 Rhona Arthur 
Staff capacity: 
Existing controls remain effective and are
keep under review to monitor the impact of
Covid-19. 
20 February 2022:
Staffing capacity increased with CAT Start Up Fund June 2021.
31-Mar-2024 Rhona Arthur 
Alignment of engagement:
Existing controls remain effective and are
adapting to respond to the impact of Covid-
19.  
20 February 2022:
Actions are being progressed and remain within the Target date for
completion.
31-Mar-2024 Rhona Arthur 
Consultation: 
Existing controls remain effective and are
adapting to respond to the impact of Covid-
19.  
20 February 2022:
Actions are being progressed and remain within the Target date for
completion.
31-Mar-2024 Rhona Arthur

Page 19

Risk Code SRR2223_R08 Risk Title Operating Environment Latest Note Date 24-Feb-2022 
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Residual societal impacts from ongoing
‘background’ waves of the pandemic and
new strains emerging. As the population
mixes again dormant infections such as
norovirus outbreaks will rise. 
There are ongoing and interrelated strategic
risks caused or exacerbated by the
pandemic ranging from increased
technology/cyber risk, financial (multiple
impacts), supply chain – particularly ICT and
specialist equipment, inequalities to how this
affects our transformation ambitions. 
The war in Ukraine is having indirect costs
and affecting market confidence. It is also
causing supply chain issues.  
A significant risk is inflation which is
affecting the cost of living and construction
projects.  Partly accelerated by factors
including Brexit and Covid, as well as
general inflationary pressures, there is a
significant risk of construction cost inflation
impacting on capital investment plans,
including the Ayrshire Growth Deal.
Other factors may increase constriction cost,
such as low carbon development solutions.
Concurrent’ resilience risks such as Cyber
Security and ‘Blackstart’ power resilience
risks add a layer of complexity. 
Delays to key plans, objectives and
projects. 
Consequences from this period including
financial loss, backlogs, socioeconomic,
health and mental health impacts on our
staff and communities. 
The disruption to proactive work in the
community has been detrimental to
inequalities, poverty, socio-economic and
health workstreams.  
The impact of construction cost inflation is
starting to materialise and project
development is requiring to adapt and often
descope to this.
Largely the issue will be a future issue that
will impact on construction projects that do
not have a completed build tender process
in place to restrict movement of material
price.
Strategic, tactical and operational response groups formed. 
Effective internal and external digital communication strategy in
place. 
Established but developing hub model North Ayrshire and
Anchor Community Partners. 
The ’North Ayrshire Food System’ has been developed to
ensure enhanced resilience. 
Ongoing interpretation of guidance, involvement with national
and local resilience partners and horizon scanning. 
Increased work on concurrent resilience risk planning. 
Refreshing the approach to Business Continuity Management. 
Redesigning project scope to reduce what can be delivered to
meet inflated costs
Identification of additional budget to support Business Continuity
measures
Negotiation with funders to seek either of the above, where
applicable.
Robust financial planning through the Medium term financial
Plan and 10 Year Capital programme to recognise impact of
inflation on budgets.
5 4
Status Risk Score
Heat Map 
Change in Score Approach
Revised risk Treat
Uncertain 20

Page 20

Strategic Risk Action Plan Date Updated 24-Feb-2022 
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
There is ongoing work to develop business
continuity processes and ensure constant
horizon scanning for emerging risks. 
The Capital Programme Asset Group and
Ayrshire Growth Deal Governance board will
continue to assess this emerging
environment. 
24 February 22:
This risk will be monitored as the Council emerges from covid related
controls through the period of increasing inflation and update on
relevant actions at mid-year update.
- -