Audit and Scrutiny Committee 
A Special Meeting of the Audit and Scrutiny Committee of North Ayrshire Council
will be held remotely on Thursday, 30 June 2022 at 10:00 to consider the undernoted
business. 
Remote Meeting Arrangements
This meeting will be held remotely in accordance with the provisions of the
Local Government (Scotland) Act 2003.  Where possible, the meeting will
be live-streamed and available to view at https://north-ayrshire.public-
i.tv/core/portal/home.  In the event that live-streaming is not possible, a
recording of the meeting will instead be available to view at this location. 
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
2 Call In: Revenue Budget 2021/22: Financial Performance to 31 March
2022
Submit report by the Chief Executive on a Call In Request received in
respect of a decision taken by Cabinet on 7 June 2022 on the financial
performance of the Council at 31 March 2022 (copy enclosed) 
3 Call In: Regeneration Delivery Plan Funding Proposals 2022/23
Submit report by the Chief Executive on a Call In Request received in
respect of a decision taken by Cabinet on 7 June 2022 on
the Regeneration Delivery Plan Funding Proposals for 2022/23 (copy
enclosed). 
4 Call In: North Ayrshire Covid Recovery Fund
Submit report by the Chief Executive on a Call In Request received in
respect of a decision taken by Cabinet on 7 June 2022 on the North
Ayrshire Covid Recovery Fund (copy enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
5 Urgent Items
Any other items which the Chair considers to be urgent.  
Webcasting - Virtual Meeting
Please note: this meeting may be recorded/live-streamed to the Council's
internet site, where it will be capable of repeated viewing.  At the start of
the meeting, the Provost/Chair will confirm if all or part of the meeting is
being recorded/live-streamed. 
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
If you are participating in this meeting by invitation, you are consenting to
being filmed and consenting to the use and storage of those images and
sound recordings and any information pertaining to you contained in the
them live-streaming/recording or training purposes and for the purpose of
keeping historical records and making those records available to the
public.  If you do not wish to participate in a recording, you should leave
the 'virtual meeting'.  This will constitute your revocation of consent.
If you have any queries regarding this, please contact
dataprotectionofficer@north-ayrshire.gov.uk.   
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Audit and Scrutiny Committee Sederunt 
John Bell (Chair)
Donald Reid (Vice Chair)
Eleanor Collier
Cameron Inglis
Tom Marshall
Matthew McLean
Davina McTiernan
Ian Murdoch
John Sweeney 
Chair: 
Apologies: 
Attending: 
3

Page 4

NORTH AYRSHIRE COUNCIL 
30 June 2022 
Audit and Scrutiny Committee 
Title:    Call In:   Revenue Budget 2021/22: Financial Performance 
to 31 March 2022 
Purpose:  To allow the Committee to consider a Call In Request in respect
of the decision taken by Cabinet at its meeting on 7 June 2022
to:- 
(a) to note (i) the information and financial performance outlined in
the report and its associated appendices, (ii) the transfer of the
net in-year underspend of £3.073m to supplement the Investment
Fund, (iii) the financial performance of the Health and Social Care
Partnership at paragraph 2.7 of the report and (iv) the IJB
cumulative deficit position of £2.320m at 31 March 2022; and 
(b) to approve the additional earmarking of £11.833m identified at
section 2.5 of the report to meet future year commitments. 
Recommendation:  That the Committee considers the terms of the Call In and
agrees, or otherwise, to make a recommendation to the Cabinet. 
1. Executive Summary 
1.1   In terms of the Scheme of Administration (Section 24), the Audit and Scrutiny Committee
has a remit to consider Call in Requests and invite at least one of the Members who has
requested the reference to Call In to attend the Committee to explain the request. 
1.2 This report sets out the background to the Call In Request in respect of the decision
taken by Cabinet at its meeting on 7 June 2022 in relation to the report on Revenue
Budget 2021/22: Financial Performance to 31 March 2022. 
2. Background 
2.1  The Cabinet, at its meeting on 7 June 2019, considered a report on Revenue Budget
2021/22: Financial Performance to 31 March 2022. 
2.2 A request was received in terms of the Call In procedure set out in the Council's Scheme
of Administration and Standing Orders, that the Audit and Scrutiny Committee examine
the decision taken by the Cabinet. 
Agenda Item 2
4

Page 5

2.3 The Call In Request, which was signed by Councillors Foster, McDonald and
Cullinane is in the following terms:- 
Reason for Call In 
To provide more support to residents struggling with the cost-of-living crisis. 
Desired Outcome 
• Remove Contribution to the Loans Fund
• Remove Provision for additional non-contractual inflationary pressures (with it
to be met by existing unearmarked reserves 
Reallocate to: 
• £500,000 pre-payment meter fund to support low-income families on pre-
payment meters
• £750,000 to reinstate £4 per eligible child per day voucher scheme during the
school holidays for the remainder of 2022/23.
• Additional £1,000,000 the Community Based Energy Support (check name)
for energy-efficiency grants
• £300,000 to provide a £50 winter top-up to the school clothing grant in 2022/23
• Additional £200,000 for Cost of the School Day activity win 2022/23 to address
the rising cost of living
• £641,000 to widen access to the Better Off financial inclusion service 
2.4 A copy of the original report presented to Cabinet on 7 June 2022 is attached as an
appendix to the report.  An updated briefing note has been provided by the Head of
Service (Finance) and is attached at Appendix 2. 
2.5 The Call In Request is valid for consideration by the Committee.  The request was
received within the appropriate timescale, it was signed by three Elected Members and
details were provided on both the reason for the Call In and the desired outcome. 
2.6 The Elected Members who have submitted the Call In will be invited to address the Audit
and Scrutiny Committee to explain the Call In Request.  The appropriate Cabinet
Member, accompanied by senior officers, will then be invited to clarify the reasons for
the decision.  The Committee will have an opportunity to ask questions of both parties
and of those officers in attendance. 
2.7 The Committee will then debate the Call In Request and decide whether or not it agrees
with the decision of the Cabinet. 
2.8 Where the Committee does not agree with the decision of the Cabinet, the matter will
be referred to the next meeting of the Cabinet with recommendations from the Audit and
Scrutiny Committee for alternative action.  The Audit and Scrutiny Committee therefore
has to:- 
i)  decide if it agrees or not with the decision of the Cabinet; and
ii) consider what alternative action the Committee would recommend to the
Cabinet if it does not agree with the decision. 
5

Page 6

2.9 When the matter is considered by the Cabinet, the Chairperson or another member of
the Audit and Scrutiny Committee will have the right to attend the Cabinet and speak in
support of any recommendation. 
2.10 In the event the Cabinet declines to accept the recommendation from the Audit and
Scrutiny Committee, the matter will be referred to the next ordinary meeting of the
Council for determination.  The decision of the Council will be final.  
3. Proposals 
3.1 It is proposed that the Committee considers the Call In Request. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are outlined in the Revenue Budget 2021/22: Financial
Performance to 31 March 2022 report attached at Appendix 1. 
Human Resources 
4.2 The human resource implications are outlined in the Revenue Budget 2021/22:
Financial Performance to 31 March 2022  report attached at Appendix 1. 
Legal 
4.3 The legal implications are outlined in the Revenue Budget 2021/22: Financial
Performance to 31 March 2022 report attached at Appendix 1. 
Equality/Socio-economic 
4.4 The equality/social-economic implications are outlined in the Revenue Budget
2021/22: Financial Performance to 31 March 2022 report attached at Appendix 1. 
Climate Change and Carbon 
4.5 The climate change and carbon implications are outlined in the Revenue Budget
2021/22: Financial Performance to 31 March 2022 report attached at Appendix 1. 
Key Priorities 
4.6 The key priorities are outlined in the Revenue Budget 2021/22: Financial Performance
to 31 March 2022 report attached at Appendix 1. 
Community Wealth Building 
4.7 The community wealth building implications are outlined in the Revenue Budget
2021/22: Financial Performance to 31 March 2022 report attached at Appendix 1. 
5. Consultation 
5.1 No formal consultation has been undertaken at this stage. 
6

Page 7

Craig Hatton
Chief Executive 
For further information please contact Angela Little, Committee Services Officer, on 
01294 324132 
Background Papers 
N/A
7

Page 8

NORTH AYRSHIRE COUNCIL
7 June 2022                                                                                  
Cabinet
Title: Revenue Budget 2021/22 : Financial Performance to 31
March 2022
Purpose: To advise Cabinet of the financial performance for the Council
for 2021/22
Recommendation: That Cabinet agrees to:
(a) note the information and financial performance outlined in
the report;
(b) approve the additional earmarking of £11.833m identified at
2.5 to meet future year commitments;
(c) note the transfer of the net in-year underspend of £3.073m
to supplement the Investment Fund;
(d) note the financial performance of the Health and Social
Care Partnership at 2.7; and
(e) note the IJB cumulative deficit position of £2.320m at 31
March 2022
1. Executive Summary
1.1 General Services Revenue Estimates for 2021/22 were approved by Council on 4
March 2021.  The Housing Revenue Account (HRA) Revenue Budget for 2021/22 was
approved by Council on 16 December 2020.
1.2 As part of the monitoring procedures to inform Cabinet of the financial performance of
the Council, financial performance reports are presented on a regular basis.  This is
the final report for 2021/22 and covers the period to the end of March 2022 (Period
12).  This is the final financial performance information on which the Annual Accounts
for the Council will be prepared. 
1.3  At Period 12 the General Fund is reporting a net in-year underspend of (£3.073m),
0.8%, after transferring resources to other funds.  This is an increase of (£1.865m)
from that reported at Period 8 and is primarily related to lower than anticipated costs
arising from the 2021/22 local government and teacher pay settlements. As approved
by Council on 2 March 2022, these funds will be utilised to supplement the Council’s
Investment Fund for delivery of sustainability projects as part of the Council’s journey
towards net zero.
Appendix 1
8

Page 9

1.4 The transfer of £14.288m to earmarked reserves has been proposed in relation to a
range of pressures which are anticipated to impact in 2022/23 and beyond, including: 
• £4.700m Scottish Government funding received late in the financial year including
support for businesses, low income households and employability;
• £4.457m additional provisions arising from the current cost volatility being
experienced across the construction, food and energy sectors; 
• £2.601m to support the continued expansion of Early Learning and Childcare
services; and
• £2.530m to support the delivery of services which have been deferred to 2022/23
as a result of a number of factors including the impact of Covid-19 restrictions. 
1.5 The Housing Revenue Account has reported a net in-year underspend of (£2.941m),
5.4%. This is a reduction of £0.357m from that reported at Period 8. The movement is
primarily related to an under recovery of Council House rents, which has been partly
offset by additional underspends within Property Costs as a result of lower than
anticipated expenditure on planned and cyclical maintenance. The underspend will be
allocated to HRA Balances to support delivery of services in 2022/23 and beyond. 
1.6 The Health and Social Care Partnership is reporting an underspend of (£13.616m).
This represents an increase of (£12.630m) over that reported at Period 8 with the
main reasons for the movement being additional Scottish Government funding in
relation to Covid mobilisation and other pressures. The Integration Joint Board (IJB)
will carry forward this underspend in earmarked and general reserves for use in future
years, resulting in an in-year net breakeven position for the HSCP. 
1.7 The final outturn includes £1.486m set aside by the Council to support the repayments
of the IJB’s deficit to the Council. This has been applied to reduce the IJB’s
outstanding deficit and Cabinet is asked to note that the IJB’s deficit position to the
Council at 31 March 2022 has been reduced to £2.320m. 
2. Background 
General Fund 
2.1 The Council set a breakeven budget for 2021/22.  In addition to the budget approved
on 4 March 2021, earmarked funds of £28.135m were carried forward from 2020/21
for service expenditure during 2021/22 and are reflected in the reported performance. 
2.2 The reported net in-year underspend is (£3.073m), net of transfers to reserves. This
represents 0.8% of the Council's total budget. 
9

Page 10

2.3 The following table details the final position on a service by service basis: 
App.
No
Annual
Budget
Actual
Outturn to 
31 March
2022
Variance
for year
(Fav)/Adv
Projected
Variance
at P8
(Fav)/Adv
Movement Request
for Carry
Forward
Approved
@ P8
New
Requests
for Carry
Forward
Variance
for Year
After Carry
Forward
(Fav)/Adv
Service Expenditure £000's £000's £000's £000's £000's £000's £000's £000's
Chief Executive's 1    26,350     25,712        (638)       (620)         (18)        145         305          (188)
Communities 2  149,183   146,211     (2,972)    (1,750)    (1,222)     1,400      1,057          (515)
Place 3    69,040     66,565     (2,475)       (781)    (1,694)        910      1,353          (212)
Other Corporate
Services 4    18,452      7,249    (11,203)       (512)   (10,691)            -      9,118       (2,085)
Sub Total  263,025   245,737    (17,288)    (3,663)   (13,625)     2,455     11,833       (3,000)
Health and Social
Care Partnership  107,059   107,059             -             -             -             -             -               -
Balance for Services  370,084   352,796    (17,288)    (3,663)   (13,625)     2,455     11,833       (3,000)
Financing Charges 5    22,185     22,185             -             -             -             -             -               -
Contribution to Loans
Fund Reserve 5     4,094      4,094             -             -             -               -
Total Planned
Expenditure  396,363   379,075    (17,288)    (3,663)   (13,625)     2,455     11,833       (3,000)
Planned Income
Aggregate External
Finance 5 (335,202) (335,244)         (42)            -          (42)            -             -           (42)
Council Tax 5   (59,862)   (59,893)         (31)            -          (31)            -             -           (31)
Contribution to Capital
Fund 5        260         260             -             -             -             -             -               -
Contribution to/from
Earmarked Funds 5    (1,559)    (1,559)            -             -             -             -             -               -
Total Planned Income (396,363) (396,436)         (73)            -          (73)            -             -           (73)
-    (17,361)   (17,361)    (3,663)   (13,698)     2,455     11,833       (3,073)Net Expenditure/ (Income)
10

Page 11

2.4 The reported Aggregate External Finance within Planned Income includes a number
of adjustments to Scottish Government funding from that reported at Period 8, as
detailed in the following table: 
2.5 Detailed explanations of the significant variances in service expenditure compared to
the approved budgets, together with information on funding to be carried forward to
support expenditure during 2022/23, are provided in appendices 1 to 5 to this report.
A full list of the proposed carry forward of earmarked funds is included at Appendix 5.   
A brief explanation of the significant movements for each service since Period 8 is
outlined as follows: 
Non Domestic
Rates
Specific
Grants TOTAL AEF
£000's £000's £000's
Revised Budget 30 November 2021 (274,330)       (28,350)         (22,568)         (325,248)      
Movements:
Business and Low Income Household Support (2,154)           (2,154)          
Care at Home Winter Planning (1,719)           (1,719)          
FWES Employability (1,645)           (1,645)          
Interim Care Winter Planning (1,109)           (1,109)          
Scottish Child Briding and Family Payments (1,003)           (1,003)          
Social Care Workforce Uplift (866)             (866)            
HSCP Living Wage (861)             (861)            
Funding for Pressures (780)             (780)            
Teacher Induction (420)             (420)            
Tenant Grant Fund (314)             (314)            
SNCT Pay Issues (162)             (162)            
Whole Family Wellbeing (106)             (106)            
DHP Accrual (101)             (101)            
MH Recovery and Renewal (68)               (68)              
Low Income Pandemic Payments (53)               (53)              
National Trauma Training (50)               (50)              
Scottish Disability Assistance (28)               (28)              
Telecare Fire Safety (28)               (28)              
Education Psychology Trainees (14)               (14)              
Unaccompanied Asylum Seekers (11)               (11)              
Education Psychology Trainees (10)               (10)              
Free Child Burials (7)                 (7)                
Road Assessments Adjustment 22                22               
Music Tuition Charges Adjustment 32                32               
Curriculum Charges Adjustment 51                51               
FSM Funding Adjustment 209              209             
PEF Carried Forward to 22-23 1,241            1,241           
Final Scottish Government Income (285,525)       (28,350)         (21,327)         (335,202)      
General Revenue
Grant
£000's
11

Page 12

(i) Chief Executive’s – underspend of (£0.638m), an increase in underspend of
(£0.018m) 
The movement is primarily related to:-
• Vacancy management across services , (£0.113m); 
This has been partly offset by increased expenditure in relation to :-
• Additional costs in relation to the procurement of Covid PPE, £0.075m
• Lower than budgeted income from NDR and Council Tax statutory additions,
£0.132m; 
• Additional contribution to the Capital Fund as part of the agreed reimbursement
of ICT infrastructure investment, £0.101m; 
It is requested that a further £0.305m of the underspend is earmarked in respect
of :
• Various committed ICT equipment, resources and software services impacted
by delays in the supply chain, £0.181m;
• AGD Digital Processing Manufacturing Centre project. £0.070m;
• 22/23 Making Waves Festival, £0.044m; and
• Customer Services Kiosk Refurbishment, £0.010m. 
(ii) Communities – underspend of (£2.972m), an increase in underspend of
(£1.222m) 
The movement is primarily related to:-
• Additional vacancy management underspends across services, (£0.662m);  
• Increased underspends on Supplies and Services across the Connected
Communities service linked the Covid-19 restrictions, (£0.445m); and
• Additional PPP rebates, (£0.114m). 
It is requested that a further £1.057m of this underspend is earmarked for use
2022/23 in relation to:
• Support for cost pressures within the Early Learning and Childcare (ELC)
capital programme, £0.300m;
• Additional earmarking in relation to the expansion of ELC, £0.194m;
• Inclusion Group funding to support temporary interventions, £0.173m;
• Eglinton Country Park - Community Gardens and Making Waves funding,
£0.157m;
• Various supplies and services within Libraries, £0.082m.
• Funding to support additional Locality Workers linked to increased workload,
£0.050m;
• Community Planning Partnerships for the Place Cube Project, £0.036m;
• Ardrossan Civic Centre renovation works, £0.027m;
• Procurement of exemplar furniture for Ardrossan Academy, £0.020m; and 
• ICT equipment delays, £0.018m. 
12

Page 13

(iii) Place – underspend of (£2.475m), an increase in underspend of (£1.694m) 
The movement is primarily related to:-
• Reduced expenditure on Supplies and Services and Third Party Payments
across services, (£0.717m);
• Vacancy management across services, (£0.464m);
• Lower than anticipated uptake of ELC meals within Facilities Management,
(£0.363m);
• Remaining project expenditure budgets in respect of Community Renewal Fund
and Ayrshire Growth Deal projects, (£0.245m); and
• Reduced provision for bad debts in relation to Temporary Accommodation
income, (£0.122m). 
These have been partly offset by increased Transport Provision costs, £0.252m. 
It is requested that a further £1.353m of the underspend is earmarked for use in
2022/23 in relation to:
• Additional earmarking in relation to the expansion of ELC, £0.372m;
• Community Renewal Fund and Ayrshire Growth Deal project costs, £0.283m;
• Temporary Accommodation furniture, £0.150m; 
• Support for the Sustainability Agenda, £0.118m;
• Rapid Rehousing Transition Plan costs, £0.088m;   
• ESF / Shared Prosperity Fund transition provision, £0.083m;
• Ardrossan Hostel upgrades, £0.072m;  
• Our Future Working Environment reconfiguration costs, £0.049m; 
• Lochshore Visitor and Community Hub initial costs, £0.045m;   
• CCTV Maintenance, £0.036m;
• Community Safety Initiative, £0.026m;
• Window Cleaning Contract, £0.011m; 
• Environmental Health Officer funding, £0.010m; and
• Transport Contractual Commitments, £0.010m. 
(iv) Other Corporate Items – underspend of (£11.203m), an increase in
underspend of (£10.691m) 
The increased underspend is primarily related to :
• Funding announced as part of the Local Government Finance Settlement
2022/23 which will not be utilised during 2021/22, (£4.405m);
• The release of provisions following a review of long term debtor and potential
credit losses, (£3.436m);
• Centrally held funds in relation to the 2021/22 pay settlement, which are no
longer required following the lower than budgeted settlement, (£2.438m);
• Previously approved expenditure pressures which have not been drawn down
during 2021/22, (£0.893m);
• Lower than budgeted severance costs during 2021-22, (£0.501m); and
• Higher than anticipated Housing Benefit Overpayments and Subsidy recovery,
(£0.253m). 
13

Page 14

It is requested that a further £9.118m of the underspend is earmarked for use in
2022/23 in relation to:
• Contribution to the Loans Fund to support the 10 year Capital Investment
Programme and address rising cost pressures, £2.569m;
• Provision for contractual electricity and gas price increases for 2022/23 to
reflect current market inflationary levels, £1.066m;
• Provision for additional non-contractual inflationary pressures (e.g. food costs,
fuel, etc.), £0.822m;
• Business continuity resilience infrastructure, £0.200m;
• Scottish Government Funding received later in the financial year, not fully
utilised in year, in respect of:- 
• Business Support and Low Income Families, £2.154;
• Employability, £0.870m;
• Financial Insecurity, £0.429m;
• Self-isolation Support grants, £0.313m;
• Tenant Grant Fund grants payments, £0.284m;
• 21/22 SNCT Payroll costs £0.162m;
• CO2 Monitors, £0.077m;
• Summer of Play, £0.20m;
• Civil Contingencies, £0.020m;
• Trainee Educational Psychologist, £0.010m; and
• British Sign Language, £0.005m. 
• Previously approved budget allocation to support future service delivery:-
• Customer Service Staffing Commitments, £0.039m;
• Finance Service Software, £0.035m;
• Cost of the School Day, £0.024m; and
• Trainee Health and Safety Officer, £0.019m. 
Health and Social Care Partnership 
2.6 The final HSCP financial performance report for the year will be presented to the
Integration Joint Board on 16 June 2022 and will outline the 2021/22 financial
performance in more detail, including: 
• An underspend of £13.616m for the year, which, after adjustment for earmarked
reserves, leaves an adjusted year-end breakeven position;   
• The earmarking of £13.616m includes £11.762m for specific purposes, including
Covid-19,  ADP, Care at Home. Interim Care Home Placements and Recovery
and Renewal, and £1.854m contribution to the IJB’s General Reserves; and   
• The application of £1.486m, set aside by North Ayrshire Council, to make a partial
repayment of the IJB’s deficit to the Council.  This has reduced the IJB’s
outstanding deficit to £2.320m at 31 March 2022. 
14

Page 15

Housing Revenue Account 
2.7 The Housing Revenue Account budgeted for a breakeven position in 2021/22.  A net
underspend of £2.941 is reported, representing 5.4% of the Council's HRA revenue
budget.  This is summarised in the following table with further details provided in
Appendix 6.  The underspend will be allocated to HRA reserves for utilisation in future
years: 
2.8 Detailed explanations of the significant variances in expenditure compared to the
approved budgets are provided in appendix 6 to this report. 
A brief explanation of the significant movements for each service since Period 8 is
outlined as follows: 
(i) Employee Costs – underspend of (£0.216m), an increase in underspend of
(£0.216m)
The increased underspend reflects vacancy management across the service. 
(ii) Property Costs – underspend of (£2.923m), an increase in underspend of
(£0.803m) 
The movement reflects lower than anticipated expenditure on Planned and
Cyclical Maintenance, (£0.283m), Aids and Adaptations, (£0.352m), and Other
Property Costs, (£0.566m), which have been partly offset by increased
expenditure on Responsive Repairs, £0.121m, and Void Repairs, £0.277m. 
(iii) Supplies and Services – underspend of (£0.027m), a reduction in
underspend of £0.095m
The movement is primarily related to costs related to, £0.111m. 
Annual
Budget
Actual
Outturn to 
31 March
2022
Variance
for year
(Fav)/Adv
Projected
Variance
at P8
(Fav)/Adv
Movement
£000's £000's £000's £000's £000's
Employee Costs      5,175       4,959         (216)             -         (216)
Property Costs     20,924      18,001      (2,923)     (2,120)        (803)
Supplies & Services         331          304           (27)        (122)           95
Transport Costs           33            12           (21)            (3)          (18)
Administration Costs      2,103       1,630         (473)           10         (483)
Third Party Payments      2,435       2,657          222           (39)         261
Transfer Payments         279          118         (161)        (169)             8
Other Expenditure         379          592          213            45          168
Capital Financing Costs     22,324      21,973         (351)        (676)         325
Gross Expenditure     53,983      50,246      (3,737)     (3,074)        (663)
Income    (53,983)    (53,187)         796         (224)      1,020
Net Expenditure             -      (2,941)     (2,941)     (3,298)         357
15

Page 16

(iv) Administration Costs – underspend of (£0.473m), a movement of
(£0.483m) from the previously reported overspend of £0.010m
The movement reflects lower than anticipated recharges from the General
Fund, (£0.210m), and lower than anticipated expenditure on Legal Expenses,
(£0.127m), and a range of business support costs. 
(v) Third Party Payments – overspend of £0.222m, a movement of £0.261m
from the previously reported underspend of (£0.039m)
The movement reflects higher than anticipated payments to other departments
within the Council. 
(vi) Other Expenditure – overspend of £0.213m, an increase in overspend of
£0.168m
The movement reflects increased provision for bad debts. 
(vii) Capital  Financing Costs – underspend of (£0.351m), a reduction in
underspend of £0.325m
The movement reflects the revised borrowing strategy and the actual cash
flows and interest rates to support the HRA capital investment programme. 
(vi) Income – under recovery of £0.796m, a movement of £1.020m from the
previously reported over recovery of (£0.224m)
The movement reflects under recoveries in Council House Rents, £0.820m,
and recharge income. 
3. Proposals 
3.1 It is proposed that Cabinet:
(a) note the information and financial performance outlined in the report; 
(b) approve the additional earmarking of £11.833m identified at 2.5 to meet future year
commitments; 
(c) note the transfer of the net in-year underspend of £3.073m to supplement the
Investment Fund; 
(d) note the financial performance of the Health and Social Care Partnership at 2.7;
and 
(e) note the IJB cumulative deficit position of £2.320m at 31 March 2022. 
4. Implications/Socio-economic Duty 
Financial 
4.1 General Services
The final outturn position for the year is an underspend of (£3.073m) which will be
applied to supplement the Council’s Investment Fund. 
Housing Revenue Account
The final outturn position for the year is an underspend of (£2.941m) which will be
allocated to the HRA Reserves. 
16

Page 17

Human Resources 
4.2 None. 
Legal 
4.3 None.
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2019 to 2024 by maximising resources
and providing value for money to support financially sustainable delivery models. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Executive Directors have been consulted as part of the review of financial performance
and have approved the variances contained in this report. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551 or DavidForbes@north-ayrshire.gov.uk. 
Background Papers
Revenue Budget 2021/22: Financial Performance to 30 November 2021 - Cabinet – 25
January 2022
17

Page 18

Appendix 1
CHIEF EXECUTIVES
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Objective Summary
Annual
Budget
Actual
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Chief Executive's Office
Chief Executive's Office 148              143              (5)                    (3%)
Total for Chief Executive's Office 148              143              (5)                    (3%)
Financial Services
Change Programme 107              107              -                      0%
Audit, Fraud, Safety & Insurance 571              559              (12)                  (2%)
Corporate Procurement 1,021           974              (47)                  (5%) 1         
Financial Services 1,420           1,404           (16)                  (1%)
Revenues 2,218           2,242           24                   1% 2         
Total for Financial Services 5,337           5,286           (51)                  (1%)
People & ICT
Employee Services 1,042           1,070           28                   3%
HR & Organisational Development 1,210           1,169           (41)                  (3%)
ICT 5,440           5,264           (176)                (3%) 3         
Business Support 1,359           1,265           (94)                  (7%) 4         
Customer Services 6,654           6,676           22                   0% 5         
Total for People & ICT 15,705         15,444         (261)                (2%)
Recovery & Renewal
Transformation 846              821              (25)                  (3%)
Total for Recovery & Renewal 846              821              (25)                  (0)           
Democratic Services
Legal & Licensing 777              745              (32)                  (4%) 6         
Policy, Performance & Elections 757              696              (61)                  (8%) 7         
Communications 474              450              (24)                  (5%)
Civil Contingencies 40                37                (3)                    (8%)
Committee Services 353              339              (14)                  (4%)
Member Services 1,251           1,197           (54)                  (4%) 8         
Information Governance 437              370              (67)                  (15%) 9         
Total for Democratic Services 4,089           3,834           (255)                (6%)
Growth & Investment
Tourism 147              103              (44)                  (30%) 10       
Growth & Investment 78                81                3                     4%
Total for Growth & Investment 225              184              (41)                  (0)           
Totals 26,350         25,712         (638)                (2%)
Less Proposed Carry Forwards 450              450                
Net Total 26,350         26,162         (188)                (1%)
18

Page 19

Appendix 1
Subjective Summary
Annual
Budget
Actual
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
£000  £000  £000
Employee Costs 16,907         16,943         36                   0%
Property Costs 73                84                11                   0%
Supplies and Services 3,090           3,112           22                   1%
Transport and Plant Costs 44                39                (5)                    (11%)
Administration Costs 1,440           1,183           (257)                (18%)
Other Agencies & Bodies 8,518           8,523           5                     0%
Transfer Payments 836              836              -                      0%
Other Expenditure 43                43                -                      0%
Capital Financing -                   -                   -                      -
Gross Expenditure 30,951         30,763         (188)                (1%)
Income (4,601)          (5,051)          (450)                10%
Net Expenditure 26,350         25,712         (638)                (2%)
19

Page 20

Appendix 1a
CHIEF EXECUTIVES
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Budget
£000 
Variance
£000
Variance as
% of budget Section
Note 1 Finance - Corporate Procurement
Movement - There has been an adverse movement of £0.070m. Within this movement £0.075m is due to increased
Covid-19 PPE expenses, but is partially offset with a favourable movement of £0.005m due to vacancy management.
953 (194) -20% Employee Costs - An underspend of £0.194m due to vacancy management.
11 154 1400% Supplies and Services - Overspend of £0.154m due to Covid-19 PPE expenses.
(7) Other minor variances
(47)
Finance - Revenues
Movement - There has been an adverse movement of £0.098m from P10 due to an under recovery of statutory
additions income of £0.132m which is slightly offset by an additional underspend in sheriff officer commission of
£0.028m and bank charges of £0.007m.
427 (17) -4% Employee Costs - An underspend of £0.017m due to vacancy management.
235 (96) -41% Administration Costs - Underspends of £0.089m in Sheriff Officer Commission due to new procurement arrangements
and bank charges £0.007m.
(1,285) 132 -10% Income - Under recovery of income due to decreased income from statutory additions of £0.132m.
5 Other minor variances
24
Note 3 People & ICT - ICT
Movement - There has been an adverse movement of £0.101m from P10 mainly due to a contribution to capital fund
as part of the agreed repayment of investment in ICT infrastructure.
3,188 (62) -2% Employee Costs - There is an underspend of 0.032m due to vacancy management and £0.030m due to non uptake of
superann scheme
12 (8) -67% Transport Costs - There is an underspend of £0.008m due to lower than usual staff fares/mileage.
2,205 (102) -5%
Supplies and Services - There is an underspend of £0.103m in WAN due to delays in equipment deliveries resulting
from global chip shortages.  An underspend of £0.042m in ICT Management Software Licences due to delayed
procurement and £0.105m in Software Licence for O365 due to removal of temporary staff costs and reduction in
consultancy costs. £0.009m underspend in Server Support due to reduction in maintenance contract costs and other
minor underspends of £0.009m.  These underspends are partially offset by a £0.167m contribution to capital fund as
part of the agreed repayment of investment in ICT infrastructure.
(4) Other minor variances
It is proposed to earmark funds of £0.070m for Project Resource equipment (WAN /LAN /Telephony /Other
Infrastructure); £0.020m CRM Project Implementation; £0.040m O365 Backup and Recovery; £0.022m ITSM SaaS
shortfall 2022/23; and £0.017m for current backup solution extension; £0.007 for delayed Computer Equipment
(176)
Note 4 People & ICT - Business Support
Movement - There has been a favourable movement of £0.024m since P10.
1,257 (86) -7% Employee Costs -  An underspend of £0.086m due to vacancy management and maternity leave.
(8) Other minor variances
It is proposed to earmark funds of £0.015m - £0.005m for delayed computer equipment, estimated delivery now end of
April and £0.010m for kiosk refurbishment for Customer Services.
(94)
Note 5 People & ICT - Customer Services
Movement - There has been a favourable movement of £0.004m from P10.
63 (21) -33%
Admin Costs - There is an underspend of £0.021m due to Benefits Postages. Excess budget will be utilised to cover
increased software costs in 22/23 (Netcall) Request to earmark £0.010m for kiosk refurbishment through BS
underspend.
(2,097) 41 -2% Income - There is an under recovery of £0.041m in Registration Income due to COVID but also a historic under
recovery.
2 Other minor variances
22                  
Note 2
20

Page 21

Appendix 1a
Budget
£000 
Variance
£000
Variance as
% of budget Section
Note 6 Democratic Services - Legal & Licensing
Movement - There has been an adverse movement of £0.030m.  This is due to an under-recovery of licensing income.
1,184 (57) -5% Employee Costs - An underspend of £0.057m due to vacancy management.
47 (25) -53% Admin Costs - There is an underspend of £0.025m due to a range of minor underspends.
(494) 49 -10% Income - There is an under-recovery of £0.031m within licensing income due to ongoing implications from the COVID
19 pandemic alongside an under-recovery of legal costs £0.016m and other minor variances.
1 Other minor variances
(32)
Note 7 Democratic Services - Policy, Performance & Elections
Movement - There has been a favourable movement of £0.053m  from P10 due to a reduction in employee costs from
vacancy management and overtime costs and reduced admin costs.
667 (40) -6% Employee Costs - An underspend of £0.024m due to vacancy management and £0.016m due to lower overtime costs.
(21) Other minor variances
(61)
Note 8 Democratic Services - Member Services
Movement - There has been a favourable movement of £0.065m  from P10 due to civic events, travel, member
allowances and various minor underspends.
37 (30) -81% Supplies & Services Costs - An underspend of £0.030m mainly due to civic events £0.015m, other departments and
hall lets £0.010m and various other minor underspends
904 (41) -5% Admin Costs - An underspend of £0.040m mainly due to members travel expenses £0.018m, member allowances
£0.009m and various other minor underspends
17 Other minor variances
(54)
Note 9 Democratic Services - Information Governance
Movement - There has been a favourable movement of £0.013m due to reduction in employee costs from vacancy
management.
430 (64) -15% Employee Costs - An underspend of £0.064m due to vacancy management.
(3) Other minor variances
(67)
Note 10 Growth & Investment - Tourism
Movement - There has been a favourable movement of £0.044m from P10 this is in relation to the Events budget.  This
budget requires to be carried forward to 22/23 to contribute towards the planned 22/23 Making Waves Festival.
103 (44) -43%
Other Agencies & Bodies - this underspend consists of £0.044m in relation to the annual events budget.  Events have
been on hold due to risks around Covid.  The Making Waves festival is now planned for 22/23 and these funds require
to be carried forward to meet some of the costs.
It is proposed to earmark £0.044m to contribute towards the planned 22/23 Making Waves Festival.
It is also requested to earmark funds of £0.070m from the Chief Executive overall underspend to support the funding of
phase 1 of the AGD Digital Processing Manufacturing Centre project at i3 in Irvine.
(44)                 
21

Page 22

Appendix 2
COMMUNITIES
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Objective Summary
Annual
Budget Actual Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Early Years Education 21,795         19,730            (2,065)             -9.5% 1         
Primary Education 41,785         41,951            166                 0.4% 2         
Secondary Education 46,467         46,225            (242)                -0.5% 3         
Additional Support Needs 11,870         11,663            (207)                -1.7% 4         
Education - Other 7,433           7,386              (47)                  -0.6% 5         
Pupil Equity Fund 4,626           4,626              -                      0.0% 7         
Connected Communities 15,207         14,630            (577)                -3.8% 8         
Net Total 149,183       146,211          (2,972)             -2.0%
Less Proposed Carry Forwards -                   2,457              2,457             
Net Total 149,183       148,668          (515)                0%
Subjective Summary
Annual
Budget Actual Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs 128,503       126,575          (1,928)             -2%
Property Costs 735              753                 18                   2%
Supplies and Services 12,449         11,662            (787)                (6%)
Transport and Plant Costs 148              105                 (43)                  (29%)
Administration Costs 882              797                 (85)                  (10%)
Other Agencies & Bodies 16,481         15,840            (641)                -4%
Transfer Payments 580              584                 4                     0%
Other Expenditure 8                  8                     -                     
Capital Financing 78                78                   -                      0%
Gross Expenditure 159,864       156,402          (3,462)             -2%
Income (10,681)        (10,191)           490                 -5%
Net Expenditure 149,183       146,211          (2,972)             -2%
22

Page 23

Appendix 2a
COMMUNITIES
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Budget
£000
Variance
£000
Variance as
% of budget Section
Note 1 Early Years Education
Movement: There has been a favourable movement of £0.174m since P10, mainly due to an increase in  employee costs
underspend.
16,472 (1,600) -10% Employee costs: An underspend due to the future opening of Marress House and Montgomerie Park establishments,
additional vacancies and cover was not accessed at previously assumed levels.
464 (80) -17% Supplies & Services: underspends across all areas of EY establishments
4,740 (353) -7%
Third Party Payments: A cautious approach was taken when setting the funded provider budget at the outset of the 1140
expansion programme.  This budget will be refined in the future, taking account of uptake of places and the work being
done nationally around the sustainable rates paid to our funded providers.
(32) Other minor movements across various budget lines
It is requested to earmark funds of £1.594m for the EY expansion in view of the future funding model that is to be
confirmed.
It is requested to earmark funds of £0.300m to support cost pressures within the ELC capital investment programme
(2,065)
Note 2 Primary Education
Movement: There has been an adverse movement of £0.062m since P10 mainly due to an increase in employee costs
overspend of £0.072m and an increase in janitor overtime for school lets of £0.032m.
40,173 201 1% Employee Costs : overspends of £0.201m within 8 primary schools. Work is ongoing with the schools to bring their
budgets back in line with resources.
1,456 (50) -3% Supplies and Services : £0.027m underspend in PPP costs due to reduced RPI (Feb 21 rate) and utility costs and
£0.023m collective underspends across all school budgets
110 (45) -41% Third Party Payments: no overtime required due to the schools not operating school lets due to COVID situation
(98) 60 -61% Income: no school let income due to school lets not operating due to COVID situation.
It is requested to earmark funds of £0.018m for IT equipment in schools which had been ordered but not received by 31
March 22
166
Note 3 Secondary Education
Movement: There has been a unfavourable movement of £0.094m since P10, mainly due to increased school cover and
school lets janitor overtime.
39,837 16 0% Employee Costs : £0.016m overspend in school absence cover teaching costs. Work is ongoing with the schools to bring
their budgets back in line with resources.
6,427 (288) -4% Supplies and Services : £0.264m underspend in PPP costs due to reduced RPI (Feb 21 rate) and utility costs
160 (32) -20% Third Party Payments: an underspend of £0.059m as less overtime was required due to the schools not operating school
lets due to COVID
(83) 62 -75% Income: no school let income due to school lets not operating due to COVID situation.
It is requested to earmark funds of £0.020m to cover the costs of the exemplar furniture in Ardrossan Academy that will
be purchased in the new financial year.
(242)
Note 4 ASN
Movement: There has been an unfavourable movement of £0.068m since P10, mainly due to a reduction in employee
costs underspend of £0.099m.
9,160 (260) -3% Employee costs: £0.355m underspend in non teaching costs partially offset by a £0.095m overspend in teaching costs
across ASN school and bases provision.
355 30 8% Other Local Authorities payments - £0.030m overspend due to additional NAC children being placed in other local
authority establishments to meet the expanding demand.
1,010 (266) -26% There is an underspend of £0.266m on external day placements as a result of the screening process currently in place.
This enables the children to remain in mainstream establishments or in-authority ASN establishments.
365 460 126%
There is an overspend of £0.460m on external specialist residential placements due to Covid affecting the ongoing
number of children in residential education.  Currently there are 7 children in accommodation.  Joint working is ongoing
with HSCP to continually assess the care setting for these children in delivering positive outcomes.
(460) (112) 24% Other Local Authorities income - Other Local Authorities that choose to place children in NAC establishments. There is an
an over recovery of £0.112m due to an increase in demand.
(59) Other minor movements across various budget lines
It is requested to earmark funds of £0.173m from Inclusion Group budget underspend to support temporary interventions
in the transition to a new process from August 2022.
(207)
23

Page 24

Appendix 2a
Budget
£000
Variance
£000
Variance as
% of budget Section
Note 5 Education Other
Movement: There has been a favourable movement of £0.713m since P10. This is mainly due to an increase in employee
turnover of £0.575m and increased income from PPP insurance rebate/deductions of £0.114m.
5,738 311 5%
Employee costs: variances are managed within the context of the Covid-19 Education recovery Plan and available
Scottish Government funding. Includes an overspend of £0.055m due to backfilling of Director and HoS post and
£0.062m VER costs for HQ staff.
1,621 (38) -2% Third Party Payments - underspend of £0.046m in grant of additional payment to teachers
(1,944) (318) 16% Income - PPP insurance rebate and deductions was £0.274m in excess of budget.
(2) Other minor movements across various budget lines
(47)
Note 6 Connected Communities
Movement: There has been a favourable movement of £0.527m since P10, mainly due to an increase in employee costs
underspend of £0.168m and further underspends across supplies and services budgets of £0.445m.
7,467 (683) -9%
Employee Costs: Underspends of £0.229m in Libraries, £0.257m in Community Facilities, £0.085m in Arran Outdoor,
£0.010m in Country Parks, £0.010m in Active Schools, £0.069m in Community Development and £0.026m in Arts, all
mainly due to staff costs being reduced due to Covid-19 and staff being redeployed to Facilities Management.
2,156 (344) -16%
Supplies & Services: Underspends in Country Parks £0.112m, Libraries £0.045m, £0.053m in Arran Outdoor, £0.087m in
Community Development, £0.018m in CPP and £0.023m in Arts, mainly due to expenditure being reduced across all
areas to help offset the under recovery of income.
6,738 (29) 0%
Third Party Payments: Includes increased subsidy support for NALL of £1.075m due to the impact of Covid-19 restrictions
and the impact on customer base. Additional support from the Council will be from the use of previously earmarked funds
totalling £1.486m which will be used to support the trading deficit position and the renewal programme within NALL.
Overspends in Libraries of £0.053m and Community facilities of £0.026m for payments to community groups, offset by
underspends of £0.056m in Community Development and £0.053m in Community Development Fund
(1,818) 527 -29% Income: Under recovery of income relates mainly to £0.196m in Community Facilities, £0.114m in Arran Outdoor Centre,
£0.005m in Country Parks,£0.049m in Libraries and £0.043m in Arts, all due to Covid-19.
32 Other minor movements across various budget lines.
It is requested to earmark funds of £0.036m for CPP for the Place Cube Project which is to develop the community books
for each locality
It is requested to earmark funds of £0.050m for salaries of 2 Community Workers to assist increased workload for locaility
planning
It is requested to earmark funds of £0.027m in Community Facilities for Ardrossan Civic Centre renovation works,
following its use in Covid services
It is requested to earmark funds of £0.157m in Eglinton Country Park for Community Gardens and Making Waves
funding, Community Gardens electricity connection, replace fences, contruct a path and pier boardwalk and purchase
storage containers
It is requested to earmark funds of £0.082m in Libraries for Library furniture, Library booking system, I-Phones and the
relocation of Brodick School Library
(497)
24

Page 25

Appendix 3
PLACE
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Objective Summary
Annual
Budget
Actual
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Directorate and Support 9                 -                    (9)                      (100%)
Physical Environment
Building Services (2,490)         (2,710)           (220)                  9% 1         
Property Governance 56               56                 -                        0%
Protective Services 1,386          1,291            (95)                    0% 2         
Facilities Management 17,084        16,135          (949)                  0% 3         
Other Housing 4,376          3,632            (744)                  (17%) 4         
Total for Physical Environment 20,412        18,404          (2,008)               (10%)
Commercial Services
Roads 6,762          6,787            25                     0% 5         
Streetscene 4,988          5,044            56                     1% 6         
Waste Resources 8,728          9,190            462                   5% 7         
Total for Commercial Services 20,478        21,021          543                   3%
Economic Development and Regeneration
Economic Policy 535             361               (174)                  0% 8         
Planning & Protective Services 341             339               (2)                      (1%)
Economic Development 5,481          4,903            (578)                  (11%) 9         
Total for Economic Growth and Regeneration 6,357          5,603            (754)                  (12%)
Sustainability, Transport & Corporate Property
Property Management & Investment 1,946          1,940            (6)                      0% 10       
Housing Assets & Investment (30)              -                    30                     0%
Property Maintenance 197             323               126                   0% 11       
Property Running Costs 5,100          4,739            (361)                  0% 12       
Energy and Sustainability 4,731          4,347            (384)                  (8%) 13       
Internal Transport 9,840          10,188          348                   4% 14       
Total for Economic Growth and Regeneration 21,784        21,537          (247)                  (1%)
Net Total 69,040        66,565          (2,475)               (4%)
Transfer to Earmarked Reserves 2,263            2,263               
Net Total 69,040        68,828          (212)                  0%
25

Page 26

Appendix 3
Subjective Summary
Annual
Budget
Actual
Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs 58,599        58,146          (453)                  (1%)
Property Costs 20,208        19,711          (497)                  (2%)
Supplies and Services 13,350        10,736          (2,614)               (20%)
Transport and Plant Costs 9,739          10,316          577                   6%
Administration Costs 2,241          2,081            (160)                  (7%)
Other Agencies & Bodies 25,134        24,173          (961)                  (4%)
Transfer Payments 526             544               18                     3%
Other Expenditure 486             371               (115)                  (24%)
Capital Financing 95               103               8                      
Gross Expenditure 130,378      126,181        (4,197)               (3%)
Income (61,338)       (59,616)         1,722                (3%)
Net Expenditure 69,040        66,565          (2,475)               (4%)
26

Page 27

Appendix 3a
PLACE
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Budget
£000
Variance
£000
Variance as
% of budget Section
Note 1 Building Services
Movement - There has been a favourable movement of £0.220m since Period 10. This is primarily due to an increased
underspend of £0.334m in supplies and services and £0.360m in third party payments. This is partially offset by a
reduction in the employee costs underspend of £0.177m and an increased shortfall in income of £0.331m.
9,189 (964) (10%) Employee Costs: An underspend of £0.964m due to vacancy management and additional labour no longer required for
the door renewal programme.
4,637 (1,106) (24%)
Supplies & Services: An underspend of £1.106m in supplies and services. This is primarily due to an underspend of
£1.113m in materials due to a change in the composition in the works programme. This underspend is offset against
the reduction in income shown below.
3,002 1 0% Third Party Payments: An overspend of £0.052m in payment to contractors partially offset by an underspend in Agency
costs of £0.051m
(20,673) 1,864 (9%) Income: There is an under recovery of income of £1.864m. This is primarily due to the delay in the door renewal and
kitchen programmes.
(15) Other minor movements
(220)
Note 2 Protective Services
Movement - There has been a favourable movement of £0.017m since P10.  This is mostly due to further vacancy
management.
1,750 (113) (6%) Employee Costs: Underspend of £0.113m due to vacancy management.
(710) 32 (5%) Income: Under-recovery in Building warrants £0.064m offset by additional Income in Pest control £0.010m and
miscellaneous £0.015m.
(14) Other minor movements
It is proposed to earmark £0.010m for Protective service salaries. This is in relation to the grant funded Environmental
Health Officer post.
(95)
Note 3 Facilities Management
Movement - There has been a favourable movement of £0.121m from period 10.  This is due to further underspends of
£0.156m in employee costs through vacancy management, reduction in overtime and casual costs and an underspend
within the pay award budget.  In addition, there has been a favourable movement of £0.126m in income primarily due to
increase in commercial catering income and cleaning non-statutory income.  This has been offset against increased
supplies and services costs of £0.085m primarily due to increased food costs and an increase of £0.073m in property
costs.     
13,657 (536) (4%)
Employee Costs: Underspend of £0.253m is due to reduced commercial catering activity.  There is a further
underspend of £0.191m due to vacancy management and reduced overtime and casual costs.  There is an underspend
of £0.093m due to the pay award not being claimed by past employees.
1,178 81 7% Property Costs:  Overspend is primarily in relation to purchasing cleaning materials in response to Covid-19.
5,222 (1,396) (27%)
Supplies and services: There is a saving of £0.272m in food due to reduced commercial catering.  There are further
food savings of £0.282m due to reduced school meal uptake and a lower average cost per meal from better
procurement and less food wastages. In addition, there is an underspend within Early Years of £0.707m which has
arisen as budgets were based on all establishments being open from April 2021 however some Early Years
establishments did not open until August 2021.  In addition, the absence rate within Early Years is resulting in reduced
meals being served and the cost per meal is lower than initially expected.  There is also a saving of £0.126m within
tools and implements. 
3,169 919 29%
Income: There is an under-recovery in commercial catering income of £1.037m due to the closure of buildings and
Covid-19 restrictions.  There is also an under-recovery of school meal income of £0.097m.  This is offset against
£0.117m of income for providing security at the new Lockhart School, Red Rose House and Flatt Road and £0.050m
over-recovery of cleaning non-statutory income.
As the service emerges from Covid a marketing campaign is currently being rolled out to increase the uptake of school
meals across the school estate.
(17) Other minor movements
FM are requesting to earmark £0.372m within the Early Years expansion as it is linked to specific grant funding
provided by the Scottish Government.  This is in addition to the £0.335m approved at period 8 and makes a revised
total of £0.707m.
(949)
27

Page 28

Appendix 3a
Budget
£000
Variance
£000
Variance as
% of budget Section
Note 4 Other Housing
Movement - There has been favourable movement of £0.250m since period 10. Property costs have decreased by
£0.113m, which is mainly the result of a decrease in furniture purchases and property repairs, partly offset with an
increase in void rent loss and cleaning costs. There has been a decrease of £0.057m in employee costs due to 
vacancy management, a decrease of £0.045m in supplies and services and £0.040m in third party payments.
4,335 (387) (9%) Employee Costs: The underspend is due to vacancy management.
2,986 79 3%
Property Costs: Additional levels of temporary furnished accommodation units as a result of Covid-19 and Hostel
closure, has resulted in increased property rental charges, furnished tenancy grants and void rent loss. These are offset
by the additional rental income generated. Underspend on property repairs to Ardrossan Hostel and furniture purchases
which have been deferred to 2022/23.
255 (42) (16%) Supplies and Services - £0.020m underspend on CCTV WAN costs and small underspends across the service.
2,875 (44) (2%) Third Party Payments - £0.029m underspend on Rapid Rehousing Transition Plan costs.
200 (85) (43%)
Other Expenditure: Underspend of £0.073m for bad debt provision. The bad debt budget was based on the increase
required to the bad debt provision in the previous year, which was due to an increase in arrears as a knock on effect of
Covid-19. It was anticipated that there would be a similar increase this year, however the bad debt provision has only
required an increase of £0.043m.
(6,437) (224) 3% Income: The over recovery of income relates mainly to the increase in temporary accommodation units in use. The
budget was set for 230 units and up to 250 units have been in use at any time.
(41) Other minor movements.
It is requested to earmark £0.357m of this underspend for various items in 2022/23. £0.150m for furniture purchases,
£0.088m for the 5 year Rapid Rehousing Transition Plan, £0.072m for Ardrossan Hostel upgrades, £0.036m for CCTV
maintenance and upgrades and £0.011m for a new window cleaning contract.
(744)
Note 5 Roads
Movement - There has been an adverse movement of £0.025m since P10, mainly due to increased external plant
costs.
4,164 (27) (1%) Employee Costs: Underspend in Winter Maintenance employee costs as the result of a mild winter.
(2,617) 33 (1%) Income: Under recovery of income is mainly for Design income from other departments.
19 Other minor movements.
A budget virement was processed to increase the Network contractors budget by £0.706m, supplies and services
budget by £0.159m, income from other departments budget by £0.805m and decrease the employee costs budget by
£0.060m. The virement is mainly due to an increase in income generating work for other Council Services, which results
in increased expenditure.
25
Note 6 Streetscene
Movement - There has been a favourable movement of £0.117m since period 10. This is primarily due to a £0.089m
decrease in employee costs through vacancy management and a reduction in overtime and casual costs.  In addition,
there was a £0.042m increase in income offset against additional supply and services costs of £0.013m.  
129 121 94%
Transport Costs: Overspend is Covid related, with £0.053m for additional vehicle hire and £0.021m for the associated
fuel costs primarily due to social distancing restrictions. There is also an overspend in skip hire of £0.043m due to
increased waste arising from more visitors. 
(2,757) (108) 4% Income:  This is due to an over-recovery of interment income and site clearance/ flytipping income.
43 Other minor movements
56
Note 7 Waste Services
Movement - There has been a favourable movement of £0.145m since P10 due mostly to movements in materials &
supplies. 
4,762 847 18%
Employee Costs:  Overspend of £0.847m, the majority of which is Covid related, due to the requirement for significant
additional temporary labour and use of overtime to mitigate self-isolation absence, provide Covid support crews and
cover unused annual leave in order to maintain essential services.
358 (70) (20%) Supplies & Services: Underspends in materials £0.050m and trade effluent £0.032m. Offset by overspend in plant &
tools £0.019m.
6,406 (346) (5%)
Third Party Payments:  Underspend in Payment to contractors of £0.379m largely a result of improved quality of our
recyclate streams following sustained ‘right stuff, right bin’ campaigns alongside more competitive recyclate prices
within our disposal contracts.
(3,051) 89 (3%) Income: Under-recovery of income due to a reduction in commercial waste of £0.076m due to Covid-19 and less gas
extracted from the landfill site of £0.095m, offset by an increase of £0.087m from diverted waste. 
145 (26) (18%) Administration Costs: Underspends in general advertising and printing costs £0.024m.
(32) Other minor movements.
462
28

Page 29

Appendix 3a
Budget
£000
Variance
£000
Variance as
% of budget Section
Note 8 Economic Policy
Movement - There has been a favourable movement of £0.152m since P10 mostly due to funds for the Community
Renewal Fund and AGD projects of £0.146m  Delivery periods are extended.
184 (18) (10%) Employee Costs: Underspend of £0.018m due to vacancy management.
341 (157) (46%) Third Party Payments: Underspend of £0.146m in relation to the Community Renewal Fund and AGD projects as well
as £0.011m other payment to contractors.
1 Other minor movements
It is requested to earmark the Community Renewal Funds and AGD projects underspend of £0.146m to meet future
project costs and extended delivery deadlines.
(174)
Note 9 Economic Development
Movement - There has been a favourable movement of £0.112m within Employability and Skills.  This is due to
additional external funding, over recovery of SDS income and young people leaving the MA programme early to take up
jobs or further training opportunities. There has been a favourable movement of £0.099m in Regeneration, mainly due
to the Community Renewal Fund expenditure due to be incurred in 2022/23.
4,367 (38) (1%) Employee Cost:  Underspend of £0.036m within AGD projects which Employability and Skills are requesting to earmark
to help cover future program costs.
6,081 (434) (7%) Third Party Payments:  Employability and Skills underspend of £0.348m is primarily due to receiving external funding in
2021/22. Underspend of £0.101m in Regeneration relating to Community Renewal funding.
(6,111) (101) 2%
Income:  £0.083m of Kickstart administration income has been received. Request that this be earmarked in case of
delays or no approvals in place to allow services and staff to transition from ESF to Shared Prosperity Fund in January
2023.
(5) Other minor movements.
It is requested to earmark the AGD underspend of £0.036m. Due to recruitment challenges this is required to help
cover future project costs.
It is requested to earmark administration income of £0.083m to mitigate risks in case of delays or no approvals in place
to allow services and staff to transition from ESF to Shared Prosperity Fund in January 2023.
It is requested to earmark the Community Renewal Fund underspend of £0.101m to be used in 2022/23.
It is requested to earmark £0.045m of the underspend as a contribution towards the first year costs of the Lochshore
Visitor and Community Hub.
(578)
Note 10 Property Management and Investment
Movement - There has been a favourable movement of £0.064m since P10 mainly due to further underspends in both
employee costs and payments to contractors.
2,470 (75) (3%) Employee Costs: An underspend of £0.075m due to vacancy management.
402 (70) (17%) Third Party Payments: underspend in payment to contractors of £0.035m and recharge from Works Scoping of
£0.035m.
(1,314) 119 (9%) Income: There is an under-recovery of £0.119m in factoring income due to a delay (now scheduled for Sept 2022) in
implementing the new charging policy as a result of Covid-19.
20 Other minor movements
(6)
Note 11 Property Maintenance Costs
Movement - There has been an unfavourable movement of £0.175m since P10 due to an increased spend against the
reactive maintenance budgets.
3,548 153 4% Property Costs - overspends in Reactive Maintenance costs of £0.343m which is offset against collective underspends
across the remaining maintenance budgets of £0.191m
(27) Other minor movements.
It is requested to earmark £0.049m to support a small-scale property reconfiguration approach aligned to Our Future
Working Environment.
126
Note 12 Property Running Costs
Movement - There has been a favourable movement of £0.015m since P10 due to collective underspends across
various property cost budgets.
6,532 (545) (8%)
Property Costs:  The underspend is due to previous refund of 18/19 to 20/21 NDR (Non Domestic Rates)charges on
Shewalton landfill amounting to £0.093m. There is an underspend in NDR charges of £0.442m (of which £0.084m is
due to NDR poundage decrease which is permanent, the remainder is made up of various other reliefs, of which
£0.258m is RHL (retail hospitality and leisure relief). 
(1,609) 188 (12%) Income:  There is an under-recovery of income totalling £0.188m due to a reduction in rental income from commercial
properties (£0.159m), a reduction in service charges (£0.010m) and tenants insurance (£0.014m).
(4) Other minor movements
(361)
29

Page 30

Appendix 3a
Budget
£000
Variance
£000
Variance as
% of budget Section
Note 13 Energy and Sustainability
Movement - There has been a favourable movement since P10 of £0.025m due to additional underspend in Water &
Sewerage. 
4,776 (380) (8%)
Property Costs:  There are underspends of £0.209m in Electricity, £0.101m in Gas and £0.021m in Water & Sewerage
due to reduced volume of usage in relation to lower occupancy in the council buildings and £0.058m underspend in
Biomass costs.  This is offset by higher spend in Oil £0.008m.
(4) Other minor movements
It is requested to earmark £0.118m to continue the sustainability agenda.
(384)
Note 14 Internal Transport
Movement - There has been an unfavourable movement of £0.246m from P10 due to an increase in repairs &
maintenance costs of £0.144m; an adverse movement of £0.209m in transport provision costs; and additional external
hire costs of £0.019m.  These were partially offset by £0.076m fuel underspend and £0.052m over recovery of income.
1,671 22 1% Employee Costs:  There is an overspend of £0.022m due to reduced staff turnover.
4,277 102 2% Transport Provision Costs: Overspend of £0.102m due to increase in contract costs as a result of tender process.
1,657 (76) (5%) Fuel Costs: despite the increase in fuel prices there is an underspend of £0.076m due to fuel consumption not being at
the same level as pre Covid-19 usage.
545 160 29% External Hires: Overspend of £0.160m primarily due to additional hire vehicles as a result of accommodating social
distancing measures in vehicles.
1,630 204 13%
Repairs & Maintenance: Overspend of £0.204m in repairs and maintenance due to maximising the life of assets due to
the increased lead time for replacement vehicles and the shortage of available rental alternatives, outsourcing of some
statutory work due to Covid restrictions, and from the removal of the HGV MOT exemption resulting in additional costs
this year to ensure vehicles met the required standard.
(43) (52) 121% Income: There is an £0.053m over recovery of bus transport income.
(12) Other minor movements
It is requested to earmark £0.010m to support the costs of a 12 month temporary contract that started in June 2021.
Transport are requesting to earmark £0.026m for costs associated with implementing a Community Safety Initiative.
348
30

Page 31

Appendix 4
OTHER CORPORATE ITEMS
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Objective Summary
Annual
Budget
Actual
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Strathclyde Passenger Transport 2,308 2,226 (82)               -4%
SPT Concessionary Fares 294 287 (7)                 -2%
Ayrshire Joint Valuation Board 958 933 (25)               -3%
3,560 3,446 (114)             -3% 1            
Other Corporate Costs
Pension Costs 2,625 2,625 -                   0%
Central Telephones 154 158 4                  3%
Other Corporate Items (incl Transformation
Costs, Bad Debt Provision, External Audit fees
and other centrally held funding.)
9,219 (1,620)          (10,839)        (118%) 2            
Insurance Account 94 94 -                   0%
Housing Benefit 2,800 2,546 (254)             -9% 3            
18,452 7,249 (11,203)        (61%)
Less Proposed Carry Forwards 9,118 9,118
Net Total 18,452 16,367 (2,085) (11%)
31

Page 32

Appendix 4a
OTHER CORPORATE ITEMS
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Budget
£000
Variance
£000
Variance as
% of budget Section
Note 1 Joint Boards
There is no material movement from Period 10
3,560 (114)               -3% Annual requisitions confirmed at less than current budget.
(114)              
Note 2 Other Corporate Items
There is favourable movement of £7.135m from Period 10 is primarily related to:
Previously approved, centrally held payroll and utility pressure budgets which have not been drawn down during 21/22,
£1.508m; the release of £2.370m of provisions following a review of long term debtors and potential credit losses; and
additional Scottish Government funding in relation to Employability, financial Insecurity and Support for Businesses and
Families which was received at year end, £3.076m
9,219 (10,839)         
Projected underspend is primarily related to:
Previously approved, centrally held payroll and utility pressure budgets which have not been drawn down during 21/22,
£3.832m; the release of £2.370m of provisions following a review of long term debtors and potential credit losses; and
additional Scottish Government funding in relation to Employability, Financial Insecurity and Support for Businesses
and Families received late in the year, £4.405m.
It is proposed to earmark funds of £9.118m as follows:
Contribution to the Loans Fund to support the 10 year Capital Investment Programme, £2.569m;
Provision for contractual electricity and gas price increases for 2022/23 to reflect current market inflationary levels,
£1.066m;
Provision for additional non-contractual inflationary pressures, £0.822m;
Business continuity resilience infrastructure, £0.200m;
Funding received, not fully utilised in year, for:-  
Business Support and Low Income Families, £2.154;
Employability, £0.870m;
Financial Insecurity, £0.429m;
Self isolation Support grants, £0.313m;
Tenant Grant Fund grants payments, £0.284m;
21/22 SNCT Payroll costs £0.162m;
CO2 Monitors, £0.077m;
Summer of Play, £0.20m;
Civil Contingencies, £0.020m;
Trainee Educational Psychologist, £0.010m;
British Sign Language, £0.005m
Previously approved budget allocation to support future service delivery:-
Customer Service Staffing Commitments, £0.039m;
Finance Service Software, £0.035m;
Cost of the School Day, £0.024m; and
Trainee Health and Safety Officer, £0.019m.
(10,839)         
Note 3 Housing Benefits
There is movement of (£0.164m) from Period 10 mainly related to Housing Benefit overpayment recovery and subsidy.
This is informed by the year end final claim
2,800 (253)               (47%) Increased net income related to the recovery of Housing Benefit overpayments
(253)              
32

Page 33

Appendix 5
MISCELLANEOUS ITEMS
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Objective Summary
Annual
Budget
Actual
Outturn
Annual
Variance
Adverse or
(Favourable) % variance Note No
£000 £000 £000
Financing Charges 22,192 22,192 - -
Contribution to Loans Fund Reserve 4,087 4,087 - -
Scottish Government Funding (335,202) (335,244) (42) 0%
Council Tax (59,862) (59,893) (31) 0%
Use of / Contribution to Earmarked Funds (1,299) (1,299) - -
Net Total (370,084) (370,157) (73) 0%
Carried Forward Funds to 2022-23 £000 £000
Previously Approved Other Commitments
Early Learning and Childcare Expansion 1,735 Contractual Energy Cost Pressures 1,066     
Universal Free School Meals 475 Non Energy Inflationary Pressures 822        
Ash Die-back Survey 100 ELC Expansion - Additional FM 566        
Employee Services Staffing 100 Inclusion Group 173        
Legal Services Case Management System 45 Eglinton Park - Various Works 157        
2,455 Temporary Accommodation Furniture 150        
Sustainability Agenda 118        
Grants / External Funding 5 year Rapid Rehousing Transition Plan 88          
Business Support Low Income Families 2,154 Libraries - Various Works 82          
FWES Employability Funding 870 Ardrossan Hostel Upgrades 72          
Financial Insecurity Funding 429 ICT Project Resource Equipment 70          
Self Isolation Support Grant 313 Digital Process Manufacturing Centre 70          
Tenant Grant Fund 284 Locality Planning Staffing 50          
SNCT Payroll Funding 162 OFWE - Property Reconfigurations 49          
Community Renewal Fund 247 Lochshore Operating Costs 45          
Kickstart/Shared Prosperity Fund 83 22-23 Making Waves Festival 44          
CO2 Monitors Funding 77 O365 Backup and Recovery 40          
AGD Community Wealth Building 36 Customer Services Staffing 39          
Summer of Play Funding 20 Place Cube Project 36          
Environmental Health Officer Funding 10 CCTV maintenance 36          
Trainee Education Psychologist Funding 10 Finance Software 35          
BSL Funding 5 Ardrossan Civic Centre Renovation 27          
4,700 Community Safety Initiative 26          
Cost of School Day 24          
Investments ITSM SaaS 22          
Loans Fund Investment 2,569 CRM Project Implementation 20          
Early Learning and Childcare - CFCR 300 Ardrossan Academy - Exemplar Furniture 20          
Resilience Infrastructure 200 Civil Contingencies 20          
3,069 Trainee H&S Officer 19          
Schools ICT - Delayed Delivery 18          
ICT Backup Solution Extension 17          
ICT Equipment - Delayed Delivery 12          
New Window Cleaning Contract 11          
Customer Services Kiosk Refurbishments 10          
Transport Contract 10          
4,064     
14,288   
33

Page 34

Appendix 6
HOUSING REVENUE ACCOUNT
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Annual
Budget
Actual
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
Note
No
£  £  £
Employee Costs 5,175 4,959 (216) (4%) 1
Property Costs
Responsive Repairs 5,245 5,789 544 10%
Void Repairs 3,126 3,591 465 15%
Planned and Cyclical Maintenance 4,492 3,928 (564) (13%)
Aids and Adaptions 1,603 1,251 (352) (22%)
Other property costs 6,458 3,442 (3,016) (47%)
Total for Property Costs 20,924 18,001 (2,923) 2
Supplies & Services 331 304 (27) (8%) 3
Transport Costs 33 12 (21) (64%)
Administration Costs 2,103 1,630 (473) (22%) 4
Third Party Payments 2,434 2,657 223 9% 5
Transfer Payments 279 118 (161) (58%) 6
Other Expenditure 379 592 213 56% 7
Capital Financing Costs 22,325 21,973 (352) (2%) 8
Gross Expenditure 53,983 50,246 (3,737) (7%)
Income
Council House Rents (51,526) (50,706) 820 (2%)
Other Rents (317) (405) (88) 28%
Recharges (2,016) (1,873) 143 (7%)
Other Income (124) (203) (79) 64%
Total Income (53,983) (53,187) 796 (1%) 9
Net Expenditure - (2,941) (2,941)
34

Page 35

Appendix 6a
HRA
BUDGETARY CONTROL 2021/22
REPORT FOR THE YEAR TO 31 MARCH 2022
Budget
£000
Variance
£000
Variance
as % of
budget
Note 1
5,175 (216) -4%
(216)
Note 2
20,924 (2,923) -14%
(2,923)
Note 3
331 (27) -8%
(27)
Note 4
2,103 (473) -22%
(473)
Note 5
2,434 223 9%
223
Note 6
279 (161) -58%
(161)
Note 7
379 213 56%
213
Note 8
22,325 (352) -2%
(352)
Note 9
(53,983) 796 -1%
796
Income
Capital Financing Costs
An underspend in capital financing costs of £0.352m due to reduced loan charges. This is due to the reduced
levels of expenditure currently being experienced in the HRA Capital budget
Movement - there has been an adverse movement of £0.363m since Period 10.
Administration Costs
Movement - there has been an adverse movement of £0.128m since Period 10. This is primarliy due to an adverse
movement of £0.111m in relation to fly tipping costs.
An overspend in third party payments of £0.223m which is mainly due to an overspend in payments to other
departments of £0.229m.
Section
Employee Costs
An underspend in employee costs of £0.216m due to vacancy management.
Movement - there has been a favourable movement of £0.109m since Period 10. This is due to vacancy
management.
An underspend in supplies and services of £0.027m which is mainly due to an underspend of £0.116m in software
licences and computer equipment. This underspend is due to a delay in the required update to the Northgate
system prior to the planned new modules being purchased. This is partially offset by an overspend of £0.093m in
fly tipping costs.
Supplies & Services
Property Costs
An underspend in property costs of £2.926m. This is mainly due to a review of the profiling of a £2.500m
contribution towards the £5m sustainability and regeneration programme. There is also an underspend of £0.565m
in Planned and Cyclical Maintenance and £0.354m in Aids & Adaptations. This is partially offset by an overspend of
£0.545m in Responsive Repairs and £0.465m in Void Repairs.
Movement - there has been a favourable movement of £0.671m since Period 10. This is due to a reduction of
£0.110m in Planned and Cyclical Maintenance, £0.238m in Aids & Adaptations and £0.659m in other property
costs offset by an increase of £0.207m in Responsive Repairs and £0.129m in Void Repiars.
Transfer Payments
Movement - There has been an adverse movement of £0.008m since Period 10.
Third Party Payments
An underspend in transfer payments of £0.161m. This underspend is in relation to disturbance allowance payments
as a result of a reduction in planned maintenance works.
Other Expenditure
Movement - There has been a favourable movement of £0.143m since Period 10. This is due to a reduction in the
overspend in the increased bad debt provision.
An overspend of £0.213m in other expenditure which relates to increased bad debt provision due to an update in
the calculation of bad debt.
Movement - there has been an adverse movement of £1.089m since Period 10. This is primarily due to an adverse
movement of £0.820m in Council House Rents and £0.262m in recharges.
An under recovery of £0.820m in Council House Rents and recharges of £0.143m  partially offset by an over
recovery in other rents of £0.088m and other income of £0.079m
Movement - There has been a favourable movement of £0.219m since Period 10. This is primarily due to an
favourable movement of £0.340m in central supports costs partially offset by £0.130m in relation to Corporate and
Democratic core charges.
Movement - There has been an adverse movement of £0.272m since Period 10. £0.229m of which relates to
payments to other departments.
An underspend in transfer payments of £0.473m which is mainly due to an underspend of £0.126m in Legal
expenses, £0.259m in Central Support costs, £0.032m in postage costs and £0.020m in external printing.
35

Page 36

Appendix 6a
B/fwd from
2019/20
Transfer to /
from Reserves
Use of
Earmarked sums
Earmarking of in
year surplus
Funding of
Capital Projects
Balance at
31/03/20
£m £m £m £m £m £m
5.580 1.000 - 0.246 (1.546) 5.280
1.500 - - - - 1.500
3.174 0.318 - 1.508 - 5.000
- 0.272 - 1.286 - 1.558
- - - 0.123 - 0.123
- - - 0.270 - 0.270
0.305 - - 0.111 - 0.416
0.052 - - - - 0.052
0.520 - - 0.116 - 0.636
1.500 - - (0.719) - 0.781
1.000 (1.000) - - - -
0.055 (0.055) - - - -
0.385 (0.385) - - - -
0.150 (0.150) - - - -
14.221 - - 2.941 (1.546) 15.616
Voids - non programmed works
Software Licences
Responsive Repairs
Electrical Testing
Infrastructure Improvements
Major Refurbishment Works
Transfer to / from Reserves - Unused balances for Cyclical Planned Maintenance of £0.055m, Disturbance Allowance of £0.385m and Responsive
Repairs of £0.150m have been reallocated with £0.318m being transferred to the Sustainability Fund and £0.272m to Voids - non programmed works. The
additional CFCR balance of £1.000m is now no longer required and has been reallocated to the Council House Building Fund to provide for future
contingencies. £0.719m from unearmarked reserves is also required to offset the movement in surplus.
Earmarking of in year surplus - The underspend of £2.941m has been allocated as follows: £0.246m to Council House Building Fund, £1.508m to the
Sustainability Fund, £1.286m to Voids non programmed works, £0.123m to software licences, £0.111m to Infrastructure Improvements, £0.116m to
Tenant led balances and £0.270m to Electrical testing. A drawdown of £0.719m from unearmarked reserves is also required.
Sustainability Fund
Council House Building Fund
Welfare Reform
Unearmarked
Tenant led budget
Additional CFCR
Cyclical Planned Maintenance
Disturbance Allowances
HRA reserves and balances
36

Page 37

Appendix 2 
Revenue Budget 2021/22 : Call In Briefing - Earmarking of Balances 
Background 
As part of the Revenue Budget Monitoring Reports provided to Cabinet throughout the
financial year, any underspends against the approved budgets are identified. The reasons
behind these underspends are investigated and, where a future expenditure commitment or
pressure is identified which would have otherwise been funded from this budget,
recommendations are made on appropriate levels of earmarking within the Council’s
reserves to offset the future pressure / commitment and ensure that any adverse impact on
future years’ budgets is minimised. 
Proposal 
Within the Revenue Budget 2021/22 Financial Performance to 31 March 2022 report
considered by Cabinet on 7 June 2022, total underspends of £17.361m were identified and
recommendations were made to earmark £11.833m of this underspend to support a range of
identified pressures in relation to: 
• £4.700m Scottish Government funding received late in the financial year including
support for businesses, low income households and employability;
• £4.457m additional provisions arising from the current cost volatility being
experienced across the construction, food and energy sectors; 
• £0.866m to support the continued expansion of Early Learning and Childcare services;
and
• £1.810m to support the delivery of services which have been deferred to 2022/23 as a
result of a number of factors including the impact of Covid-19 restrictions. 
The recommendation in relation to the £4.457m cost volatility earmarked request included: 
• £2.569m Contribution to the Loans Fund to support the 10 year Capital Investment
Programme and address rising cost pressures;
• £1.066m Provision for contractual electricity and gas price increases for 2022/23 to reflect
current market inflationary levels; and
• £0.822m Provision for additional non-contractual inflationary pressures (e.g. food
costs, fuel, etc.). 
Contribution to the Loans Fund 
Under the Council’s Capital Investment Strategy, developed in accordance with the Local
Government Scotland Act 2003 and the Prudential Code, the Council is required to ensure
that its capital plans are affordable, prudent and sustainable. 
Throughout 2021/22 Cabinet has received reports on the delivery of the General Fund
Capital Investment Programme which have highlighted significant cost risks across the
Capital Investment Programme which will result in increased contractor and material costs
impacting across a number of projects from 2022/23. 
Any increase in costs within the Programme will result in an additional borrowing
requirement to ensure the delivery of the projects to the agreed specifications which will, in
turn, require the identification of additional revenue resources to meet the increased principal
and interest repayments. 
37

Page 38

Through monitoring the capital programme in 2021/22 a number of projects have been
identified as having additional cost risk. They currently include Montgomerie Park Primary
school, Moorpark Primary school and Largs sea wall works. Further major projects being
progressed in the coming months which also present an increased cost risk include
Ardrossan North Shore (Advance works and Campus) and Millport Coastal Flood Prevention
scheme. Although further downstream, this cost risk also applies to all Ayrshire Growth Deal
projects. In order to help manage this risk an additional £10m flexible funding was approved
in the capital budget back in March 22. Since this time the level and impact of inflation and
volatility in the construction sector has grown. Although we do not currently know what the
full extent of the cost pressures facing the Council will be in delivering the capital
programme, when we consider all the major capital projects currently being progressed, the
indications are that it will be in excess of the resources currently set aside to help mitigate
this risk. Therefore, for reasons of prudent financial management, affordability and
sustainability, this transfer of £2.569m to the Council’s Loans Fund Reserve was 
recommended. 
Provision for additional non-contractual inflationary pressures 
The General Services Revenue Estimates 2022/23 to 2024/25 were approved by Council on
2 March 2022. The Revenue Estimates do not normally include provisions for inflationary
pressures, outwith contractual commitments and payroll inflation. The main exception to this
is where provisions are included for price inflationary across key commodities, such as food,
fuel and energy, where services have little or no control over the cost or quantity required to
deliver the key responsibilities of the Council. 
The provisions in relation to these key commodities was based on the Bank of England’s
inflationary projections as at February 2022 and included: 
• £0.056m SPT School Transport Provision, based on 3% inflation;
• £0.073m Food Price Inflation, based on 3% inflation;
• £0.007m Non Contractual Energy Costs (primarily solid fuel), based on 6% inflation; and
• £0.090m Vehicle Fuel Inflation, based on 8% inflation. 
In the period since the approval of the 2022/23 Revenue Estimates, the Bank of England
has reported that global inflationary pressures has intensified sharply following Russia’s
invasion of Ukraine, leading to a material deterioration in the outlook for world and UK
growth. The situation in Ukraine has resulted in further inflationary pressure on energy and
other commodities, including food prices and fuel costs. In addition, further supply chain
disruption has resulted from both the Russian invasion of Ukraine and recent Covid-19
restrictions in China. 
The Bank of England is now reporting that Consumer Price Inflation is expected to reach a
peak of 10% in late 2022 with the Office for National Statistics reporting vehicle fuel inflation
of over 36% in the period to April 2022. At the same time services operating biomass heating
systems are reporting fuel price increases of over 60%. 
To help offset the additional unbudgeted pressures arising from the increased inflation
identified since March 2022 and protect the delivery of essential services including school
meals, school transport and the heating of school and other operational buildings using
biomass heating systems, it was recommended that £0.822m of underspend arising from the
review of bad debt provision and anticipated credit losses is earmarked to support non
contractual inflationary pressures. 
38

Page 39

Uncommitted General Fund Balances 
Local Authorities are required to have a clear reserves policy that takes account of known
commitments, potential liabilities and the risk profile of the Council and provides flexibility to
deal with unforeseen circumstances, with Audit Scotland identifying the management of
reserves being key to maintaining financial sustainability. 
The Council’s approach is in line with CIPFA’s recommended practice as set out in the
document “Local Authority Reserves and Balances” and the General Services Uncommitted
Balance is maintained within the recommended range of between 2% and 4% of the
budgeted General Services expenditure. 
However, Councils are required to assess potential risks and volatility from external factors
and provide for additional levels of uncommitted balances as required. 
During 2020/21, Council agreed to increase the level of General Fund Unearmarked
Balances to £11.315m, or 2.9% of budgeted expenditure, with the additional reserves
required to help mitigate the ongoing impact of the Covid-19 pandemic and support recovery
and renewal activities. 
As part of the 2022/23 to 2024/25 General Services Revenue Estimates it was recognised
that the Council will continue to face a number of financial challenges through 2022/23 and
beyond, including the legacy impact of pressures from the pandemic across Council services
and budgets, significant inflationary pressures across revenue budgets and the capital
programme and the risk of additional costs through delivery of new policy commitments.
Considering this Council agreed to maintain the Uncommitted General Fund Balances at
£11.315m. This level of unearmarked reserve still sits at the lower end of best practice. 
Conclusion and Call In Request 
The recommendations made to Cabinet in relation to the earmarking of reserves to manage
the increased inflationary pressures and cost volatility in the commodities and construction
sectors has been made to help address these risks during this uncertain time. 
Similarly, the current level of Uncommitted General Fund Balances (£11.315m – 2.9%) is
considered prudent at this time when set within the context of the financial pressures and
risks facing the Council at this time. 
The request from the Call in to re-direct resources to benefit citizens in addressing the cost
of living crisis is outlined below along with some supporting commentary / context which is
set out in red;- 
Proposal is to reallocate the £3,391,000 to: 
• £500,000 pre-payment meter fund to support low-income families on pre-
payment meters. Council approved £1.726m in March 2022 to support an
energy based community support model. Proposals are currently being
progressed around this. The support model will include working with a
specialist energy partner to provide sustainable support to citizens through
advice, guidance and the delivery of a range of energy efficiency measures
e.g. enhanced insulation and boiler controls to improve the affordability of
heat in homes across North Ayrshire. The model will also include grant
assistance to help the transition to lower carbon alternatives. To progress
the proposal set out around pre-paid meters will require this data to be firstly
gathered and for the appropriate eligibility support criteria to be developed.    
39

Page 40

• £750,000 to reinstate £4 per eligible child per day voucher scheme during
the school holidays for the remainder of 2022/23. A new programme of
support has been developed across the Communities and Place
Directorates and is due to commence shortly from the upcoming summer
school holiday and will be in place across all school holidays during
2022/23. The Scottish Government provided £0.712m funding to North
Ayrshire Council to enable the provision of alternative free school meal
provision to all children and young people eligible for free school meals
based on low income, in primary and secondary age groups, during the
school holidays. This funding is designed for the 2022 summer holidays; the
Christmas and Easter holidays during the 2022-23 school year; and the mid-
term holidays in October and February. 
Planned Programme: Free School Meals Holiday Provision 2022-23 
Summer Activity Programme: 
The summer holiday activity and food programme will be expanded from 18
to 22 venues with a variety of activities/partners/ volunteers covering 6
weeks. This is the key mechanism in North Ayrshire for ensuring that
children have: 
• Access to food during holiday periods;
• Opportunities to be supported by staff and volunteers;
• Opportunities to meet their peers; and 
• Sessions of physical and other activities. 
Vouchers (£10/£20) 
£10 weekly top-up vouchers will also be provided for all pupils entitled to
Free School Meals.  The purpose of the vouchers is to ensure provision is
made for those days when children cannot access our activities
programmes, such as weekends. 
In those areas where local activity programmes with partners are more
difficult to facilitate (e.g. Arran, Cumbrae, Skelmorlie and Fairlie), it is
planned that weekly vouchers of £20 are provided. 
• Additional £1,000,000 the Community Based Energy Support (check name)
for energy-efficiency grants. From the comments noted above the Council
approved £1.726m in March 2022 to support an energy based community
support model. Proposals are currently being progressed around this. The
support model will include working with a specialist energy partner to
provide sustainable support to citizens through advice, guidance and the
delivery of a range of energy efficiency measures e.g. enhanced insulation
and boiler controls to improve the affordability of heat in homes across North
Ayrshire. The model will also include grant assistance to help the transition
to lower carbon alternatives. It is recognised that an additional £1m would
further support this programme, however, it is still currently being developed.
The scheme will be reviewed on an on-going basis and additional funding
could be requested and considered, within the financial context of the
Council at that time once the success of the existing commitment is known.  
40

Page 41

• £300,000 to provide a £50 winter top-up to the school clothing grant in
2022/23. In June 2021 the Scottish Government increased the minimum
level of clothing grants to £120 for primary pupils and £150 for secondary
pupils to take effect from the start of the 2022/23 academic year. North
Ayrshire Council currently pays grants at this level. 
• Additional £200,000 for Cost of the School Day activity in 2022/23 to
address the rising cost of living. Council approved recurring annual funding
of £500,000 per annum in March 2021 to address cost of the school day.
The funding is used to support a range of measures across schools
including clothing, uniforms, sports kits, equipment, digital support (through
devices and connectivity) and to extend the community food network across
all schools , supporting children and families. This is one of the areas of
focus of the new Child Poverty Board. The feedback from young people
from the recent Cost of the School Day conference is being analysed to
inform the future spend and direction of travel in this area. Proposals would
then be brought to Cabinet. 
• £641,000 to widen access to the Better Off financial inclusion service. We
would require to undertake an assessment of how this funding would be
best utilised as it is not clear as to the intention from the request e.g.
additional temporary staffing etc. It should be noted that a review is currently
ongoing as part of the “Accessing our Council” Transformation workstream.
This is to identify best practice, gaps and duplication in our financial
inclusion services. The outcome of that review will provide evidence for best
value resource allocation. 
Further, the recently approved Cabinet report on 7 June 2022 and titled “North Ayrshire
Economic COVID Recovery Fund” included a range of supports to businesses and citizens
totalling £2.154m. One of the supports included a £100 summer top up payment for families
of children eligible for a free school meal and extended to families of children of pre-school
age on the basis of low income. It is anticipated this will benefit a total of 5,700 children
(3,300 families). 
Throughout 2022/23 these risks and cost pressures will continue to be monitored and
regular reports to Cabinet will identify any changes to the risk assessments or further
underspends which Council can redirect to enhance the levels of support to communities
and families across North Ayrshire Council. 
Mark Boyd
Head of Finance 
21 June 2022 
41

Page 42

NORTH AYRSHIRE COUNCIL 
30 June 2022 
Audit and Scrutiny Committee 
Title:    Call In:   Regeneration Delivery Plan Funding Proposals 
2022/23 
Purpose:  To allow the Committee to consider a Call In Request in respect
of the decision taken by Cabinet at its meeting on 7 June 2022
to:- 
(a) to approve the Regeneration Delivery Plan funding proposals
for 2022/23 provided at Appendix 1 to the report; 
(b) that delegated authority be granted to the Executive Director
(Place) to agree changes to the funding allocations in consultation
with the Portfolio Lead, as required; and 
(c) to note the update on the previously agreed Levelling Up Fund
(LUF) bid for the ‘Gateway to the West Coast and Clyde Islands
strategic regeneration package’ and that this LUF bid would now
be solely based on the development of Lochshore. 
Recommendation:  That the Committee considers the terms of the Call In and
agrees, or otherwise, to make a recommendation to the
Cabinet. 
1. Executive Summary 
1.1    In terms of the Scheme of Administration (Section 24), the Audit and Scrutiny
Committee has a remit to consider Call in Requests and invite at least one of the
Members who has requested the reference to Call In to attend the Committee to
explain the request. 
1.2 This report sets out the background to the Call In Request in respect of the decision
taken by Cabinet at its meeting on 7 June 2022 in relation to the report on
Regeneration Delivery Plan Funding Proposals 2022/23. 
2. Background 
2.1 The Cabinet, at its meeting on 7 June 2019, considered a report on Regeneration
Delivery Plan Funding Proposals 2022/23. 
Agenda Item 3
42

Page 43

2.2 A request was received in terms of the Call In procedure set out in the Council's
Scheme of Administration and Standing Orders, that the Audit and Scrutiny
Committee examine the decision taken by the Cabinet. 
2.3 The Call In Request, which was signed by Councillors Foster, McDonald and
Cullinane is in the following terms:- 
Reason for Call In 
To tackle privately owned vacant and derelict sites in North Ayrshire with a fund
to bring the sites into council or community ownership. 
Desired Outcome 
Remove the following from the Placed based projects: 
Saltcoats Place Framework £70,000 
Largs Place Framework £70,000 
Kilwinning Place Framework £70,000
Future Years Project Development £40,000 
Reduce the following in the VDLF: 
Development work to £160,000 
Replace with: 
£410,000 (£250,000 Placed Based and £160,000 VDLF) to create a new High Street
Buyout Fund to deliver a Community Wealth Building approach to town centre
regeneration, aimed at bringing privately owned derelict sites into Council or
community ownership to be repurposed for the benefit of the community. This fund
would act as a delivery arm of the Place Frameworks and build on the projects
supported through the Repurposing Property Grant with further funding in future
years. 
2.4 A copy of the original report presented to Cabinet on 7 June 2022 is attached as an
appendix to the report.  An updated briefing note has been provided by the Executive
Director (Place) and is attached at Appendix 2. 
2.5 The Call In Request is valid for consideration by the Committee.  The request was
received within the appropriate timescale, it was signed by three Elected Members
and details were provided on both the reason for the Call In and the desired outcome. 
2.6 The Elected Members who have submitted the Call In will be invited to address the
Audit and Scrutiny Committee to explain the Call In Request.  The appropriate Cabinet
Member, accompanied by senior officers, will then be invited to clarify the reasons for
the decision.  The Committee will have an opportunity to ask questions of both parties
and of those officers in attendance. 
2.7 The Committee will then debate the Call In Request and decide whether or not it
agrees with the decision of the Cabinet. 
43

Page 44

2.8 Where the Committee does not agree with the decision of the Cabinet, the matter will
be referred to the next meeting of the Cabinet with recommendations from the Audit
and Scrutiny Committee for alternative action.  The Audit and Scrutiny Committee
therefore has to:- 
i)  decide if it agrees or not with the decision of the Cabinet; and
ii) consider what alternative action the Committee would recommend to the
Cabinet if it does not agree with the decision. 
2.9 When the matter is considered by the Cabinet, the Chairperson or another member of
the Audit and Scrutiny Committee will have the right to attend the Cabinet and speak
in support of any recommendation. 
2.10 In the event the Cabinet declines to accept the recommendation from the Audit and
Scrutiny Committee, the matter will be referred to the next ordinary meeting of the
Council for determination.  The decision of the Council will be final.  
3. Proposals 
3.1 It is proposed that the Committee considers the Call In Request. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are outlined in the report attached at Appendix 1. 
Human Resources 
4.2 The human resource implications are outlined in the report attached at Appendix 1. 
Legal 
4.3 The legal implications are outlined in the report attached at Appendix 1. 
Equality/Socio-economic 
4.4 The equality/social-economic implications are outlined in the report attached at
Appendix 1. 
Climate Change and Carbon 
4.5 The climate change and carbon implications are outlined in the report attached at
Appendix 1. 
Key Priorities 
4.6 The key priorities are outlined in the report attached at Appendix 1.  
44

Page 45

Community Wealth Building 
4.7 The community wealth building implications are outlined in the report attached at
Appendix 1. 
5. Consultation 
5.1 No formal consultation has been undertaken at this stage.   
Craig Hatton
Chief Executive 
For further information please contact Angela Little, Committee Services Officer, on 
01294 324132 
Background Papers 
N/A
45

Page 46

NORTH AYRSHIRE COUNCIL
7 June 2022
Cabinet
Title: Regeneration Delivery Plan Funding Proposals 2022/23
Purpose: To seek approval for the 2022/23 Regeneration Delivery Plan
funding proposals 
Recommendation: That Cabinet:
(a) Approves the Regeneration Delivery Plan funding proposals
for 2022/23 provided at Appendix One; and
(b) Provides delegated authority to the Executive Director
(Place) to agree changes to the funding allocations in
consultation with the Portfolio Lead as required.
(c) Notes the update on the previously agreed LUF bid for the
‘Gateway to the West Coast and Clyde Islands strategic
regeneration package’ and agrees that this LUF bid will now
be solely based on the development of Lochshore
1. Executive Summary
1.1 The Regeneration Delivery Plan was adopted by Cabinet in March 2021.  This sets
out our priorities for delivering on the regeneration ambitions of the Council Plan and
Community Wealth Building strategy, working in partnership with communities.  
1.2 The Plan focuses on the delivery of physical regeneration across North Ayrshire
through an ambitious project based rolling action programme.  It informs our priorities
for securing and delivering against external funding sources including Scottish and UK
Government funds.  This report provides an update on the funding secured to date
and seeks approval for the 2022/23 funding proposals.
2. Background
2.1 The Council has placed the regeneration of communities at the heart of its agenda.
This focus is reflected within the priorities of the Council Plan and Community Wealth
Building Strategy.  The Regeneration Delivery Plan sets out our priorities for delivering
on these ambitions and was approved by Cabinet on 23 March 2021.  
2.2 The Plan focuses on the delivery of physical regeneration in the period 2021 to 2026.
Informed by stakeholder consultation, reviewing existing community priorities and the
outcomes of previous consultations, it aims to address local priorities, support
changes within communities and to contribute to a vibrant and inclusive economy.
Appendix 1
46

Page 47

2.3 The Plan is delivered through an ambitious rolling action focused programme.  This
approach seeks to ensure that the list of projects never exceeds a realistic
assessment of capacity, with projects being prioritised annually.  The action
programme is reviewed annually and will be the subject of ongoing annual reporting to
Cabinet.  This will align priorities with resource informed by an assessment of
progress to date, local priorities, project deliverability and funding. 
2.4 The Regeneration Delivery Plan informs our priorities for securing and delivering
against a range of external funding sources.  Action in 2021/22 substantially focussed
on maximising the impact and leverage of investment including securing sources of
external funding to support and accelerate delivery.  Significant levels of funding have
been secured to date to support delivery in 2022/23.  The details of the funds and the
proposed approach to their expenditure are provided at Appendix One.  These include
the: 
- Scottish Government’s Place Based Investment Programme: £1.093m
- Scottish Government’s Vacant and Derelict Land Fund: £1.32m
- Scottish Government’s Vacant and Derelict Land Investment Programme: £0.4m
- Scottish Government’s Cycling Walking and Safer Routes: £0.86m
- Strathclyde Partnership for Transport Capital Programme: £1.385m 
2.5 Funding applications are proposed to a range of competitive funding sources to
support the delivery of the Plan.  The details of the funds and the proposed
submissions are provided at Appendix One.  These include the: 
- Scottish Government’s Regeneration Capital Grant Fund
- Scottish Government’s Islands Programme
- Scottish Government’s Vacant and Derelict Land Investment Programme
- Historic Environment Scotland’s Heritage and Place Programme
- Heritage Fund’s Grants for Heritage 
2.6 The submission of two applications to the second round of the UK Government’s
Levelling Up Fund was agreed by Cabinet on 2 November 2021.  These require to be
submitted in July 2022.  This agreement was for a partnership bid with South Ayrshire
Council centred on Commercial Estate Development and associated Low Carbon
Infrastructure and the resubmission of the Gateway to the West Coast and Clyde
Islands strategic regeneration package bid.  It is now proposed that the Gateway
package bid be changed to the submission of a single application for the Lochshore
Masterplan.  The rationale for this approach is outlined at Appendix One. 
2.7 Further consultation and engagement will be undertaken with local communities,
stakeholders and Elected Members through the detailed development of any
successful projects. 
3. Proposals 
3.1 That Cabinet: 
(a) Approves the Regeneration Delivery Plan funding proposals for 2022/23 provided
at Appendix One; and
47

Page 48

(b) Provides delegated authority to the Executive Director (Place) to agree changes to
the funding allocations in consultation with the Portfolio Lead as required.
(c) Notes the update on the previously agreed LUF bid for the ‘Gateway to the West
Coast and Clyde Islands strategic regeneration package’ and agrees that this LUF
bid will now be solely based on the development of Lochshore. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Regeneration Delivery Plan aims to build on and maximise the impact of the
investment being made through a variety of sources including the Ayrshire Growth
Deal, Council’s Capital Programme and the Strategic Housing Investment Programme
(SHIP). It also seeks to lever private funding and investment into North Ayrshire. 
It informs our priorities for securing and delivering against external funding sources. 
This includes the range of funds outlined at Appendix One.  The Regeneration team
has extensive experience of and success in securing external funding for project
development and delivery.  The implementation of projects aligned to competitive
funding sources will be dependent on the success of the funding application. 
Human Resources 
4.2 The Regeneration Delivery Plan projects will be delivered through the existing
Regeneration Team resource. Opportunities to secure funding for additional staff
resource to support delivery will be investigated on a project by project basis as
required. 
Legal 
4.3 The legal implications of all Regeneration Delivery Plan projects will be considered
through their development. Legal agreements will be developed on a project by
project basis as required with support from Legal Services. Negotiation will be
required in relation to land and building acquisitions with support from the Council’s
Legal Services and Property Management and Investment Service. Mechanisms such
as Compulsory Purchase Orders will be considered on a case by case basis, where
considered appropriate. 
Equality/Socio-economic 
4.4 The Regeneration Delivery Plan assists in meeting our socio-economic duty as set out
in the Fairer Scotland Duty. It seeks to reverse economic, social and physical decline
and reduce socio-economic disadvantage. It will tackle long-term vacant and derelict
land and buildings thereby reducing their levels and impact on communities. It aims to
build community wealth and tackle local deprivation through the regeneration of our
communities by maximising the potential of our land and assets and those of anchor
institutions. 
The Plan also contributes to the delivery of the Isle of Cumbrae and Isle of Arran
Local Island Plans, their key themes and priorities. The funding proposals will directly
contribute to several of the actions identified within the annual action plans. The
48

Page 49

proposals for the Scottish Government’s Islands Programme have been informed by
the Islands Plans and identified from the Action Programmes. 
An initial screening will be undertaken to establish if an Equality and Children’s Rights
Impact Assessment is required for projects on a case by case basis. 
Climate Change and Carbon 
4.5 The Regeneration Delivery Plan aligns with the Environmental Sustainability and
Climate Change Strategy workstreams of: Green Economy; Transport and Travel;
Natural Environment; Sustainable Operations; and Carbon Absorption. Furthermore, it
aligns with the commitment to reduce carbon emissions through declaration of a
Climate Emergency and will contribute to the ambition to achieve net zero by 2030. 
The climate change and carbon impacts of individual process will be assessed on a
case by case basis to minimise the potential impacts in line with best practice. 
Key Priorities 
4.6 The Regeneration Delivery Plan has been informed by the priorities identified within
the Local Outcomes Improvements Plan and Locality Partnership priorities. The
implementation of the Plan will contribute to achieving the Council Plan priority
outcomes and will contribute to the ambitions for: an inclusive, growing and
enterprising economy; North Ayrshire to be well-connected with effective
infrastructure; and for a sustainable, vibrant, welcoming and attractive environment. 
Community Wealth Building 
4.7 The Regeneration Delivery Plan sets out our priorities for delivering on the ambitions
on the Community Wealth Building Strategy Land and Assets pillar. Its delivery will
have a significant positive impact on the Council’s ambitions across the pillars of: 
- Land and Assets: by supporting equitable land development and the
development of underutilised assets for community use.
- Procurement: by contributing to the development of the procurement wave
plan; through the inclusion of appropriate community benefit of local supplier
clauses within projects; and by considering phasing and programming of
projects to create local supply chain opportunities and support delivery by
smaller scale and local contractors where appropriate.
- Fair Employment: by supporting the creation of employment opportunities
particularly within the construction sector. Where North Ayrshire is the
contractor for services, through our enhanced Community Benefits approach
we will seek to ensure the creation of local training and work experience
opportunities.
- Financial Power: by investing in localities and leveraging external national
investment into North Ayrshire. 
5. Consultation 
5.1 The Regeneration Delivery Plan was the subject of extensive consultation including
workshops with Council Officers; workshops with Elected Members; reports to and
feedback from North Ayrshire Ventures Trust and the Community Wealth Building
49

Page 50

Expert Panel; and public engagement via Consul. It was also informed by the Locality
Partnerships’ priorities and previous public consultation exercises including Charettes. 
5.2 The funding proposals outlined at Appendix One have been informed by this
consultation.  Further consultation and engagement will be undertaken with local
communities, stakeholders and Elected Members through the detailed development of
any successful projects. 
Russell McCutcheon
Executive Director (Place) 
For further information please contact Louise Kirk, Senior Manager Regeneration, on
01294 324766. 
Background Papers
Cabinet Report – Regeneration Delivery Plan, 23 March 2021
Cabinet Report – Levelling Up Fund, 15 June 2021
Cabinet Report – Levelling Up Fund – Round 2, 2 November 2021
Cabinet Report – Regeneration Delivery Plan Update, 22 February 2022 
50

Page 51

Appendix One: Regeneration Funding Proposals 
The following provides a summary of each of the funds and the proposed approach for
2022/23. The proposals have been identified from the Regeneration Delivery Plan and an
assessment of the: 
- Projects’ stage of development;
- Fit with the fund objectives and priorities;
- Potential benefits;
- Budget available;
- Ability to secure match funding; and
- Deliverability of the project(s) within funders’ timescales. 
This approach aims to implement a range of projects that deliver impactful improvements in
line with the Regeneration Delivery Plan and the various funding streams’ ambitions. 
Where there is an underspend within one of the allocations in 2022/23, it is proposed that
the Executive Director (Place) will reallocate any underspend across the other identified
actions following engagement with the Portfolio Lead. 
Place Based Investment Programme 
The Scottish Government established the five year £325m Place Based Investment
Programme (PBIP) in 2021/22. Underpinned by the Place Principle, this aims to support
community-led regeneration, town centres and the 20-minute neighbourhood ambitions.
The main objectives of the Programme are to: 
- Link and align place based initiatives and establish a coherent local framework to
implement the Place Principle;
- Support place policy ambitions such as town centre revitalisation, community led
regeneration, 20 minute neighbourhoods and Community Wealth Building;
- Ensure that all place based investments are shaped by the needs and aspirations 
- of local communities; and
- Accelerate the ambitions for tackling inequality and disadvantage, wellbeing and
inclusive economic development, net zero, community involvement and ownership 
Local Government is a key partner in delivering the Programme and will receive a share of 
the funding over the five years to support and advance local priorities. A £1.093m allocation
has been received for the current financial year. This requires to be fully expended or at a
minimum financially committed by 31 March 2023. Any unused grant will require to be
repaid to the Scottish Government unless otherwise agreed by Scottish Ministers. 
The table below outlines the proposal for the expenditure of the allocation. This includes a
further allocation to the Town Centre Living Pilot Project for 2022/23. This is required as the
2021/22 allocation could not be fully financially committed by 31 March 2022. £680,000 of
the original £830,000 allocation was reallocated to the Communities Project Fund, Kilbride
Shopfront Scheme and Future Years Project Development. 
The proposals aim to support the delivery of the Place Frameworks currently being
prepared through the previous allocations and the UK Government’s Community Renewal
Fund. Furthermore, they aim to continue the development of Place Frameworks across
North Ayrshire.
51

Page 52

Project Allocation
Town Centre Living Pilot Project
This will further investigate the potential, develop detailed proposals and
designs and support the implementation where appropriate for town centre
living pilot projects at 36 Bank Street, Irvine and Howgate, Kilwinning.
£680,000
Saltcoats Place Framework
This will support the delivery of the Place Framework including physical
improvements and CWB opportunities.
£70,000
Largs Place Framework
This will support the delivery of the Place Framework including physical
improvements and CWB opportunities.
£70,000
Kilwinning Place Framework
This will support the delivery of the Place Framework including physical
improvements and CWB opportunities.
£70,000
Garnock Valley Place Frameworks
This will support the roll out of Place Framework development to Dalry,
Kilbirnie and Beith
£80,000
Future Years Project Development
This will enable the preparation of proposals for implementation in future
years and support funding applications.
£40,000
Lochshore Park Hub Play
This will support the development of play facilities at the Garnock Visitor
and Community Hub and the bid to Round 2 of the Levelling Up Fund.
£50,000
PBIP Regeneration Officer
This will meet the costs associated with the dedicated Regeneration Officer
to support the delivery of the Programme.
£33,000 
Total £1,093,000 
Vacant and Derelict Land Fund 
The Scottish Government's Vacant and Derelict Land Fund (VDLF) aims to tackle the
presence of long-term vacant, for 15 years or longer, and derelict land in Scotland. In doing
so, it aims so stimulate economic growth, job creation, an improved environment and
quality of life. From its inception in 2007, access to the Fund was restricted to 5 local
authorities to focus the available financial resource and prioritise authorities most impacted
by both the extent of vacant and derelict land and levels of deprivation. 
A review in 2015, resulted in North Ayrshire Council benefitting from access to the Fund 
from the financial year 2016/17. The other four authorities which currently benefit are South
Lanarkshire, North Lanarkshire, Fife and Glasgow City Councils. Funding is limited to sites
that have been vacant for at least 15 years and are between 0.1ha and 99ha in size, with a
preference of Council ownership or a landowner agreement in place. It cannot be used on
housing or infrastructure projects such as transport or flooding. 
A Local Delivery Plan requires to be submitted to the Scottish Government to allow
Ministerial approval of the expenditure of the funding in 2022/23. In developing the
proposals for this, several factors have been considered, including the: 
52

Page 53

- Scottish Government funding criteria;
- Economic development focus of the funding;
- The priority sites identified of Irvine Enterprise Area, Ardrossan North Shore, Lochshore
and Irvine Harbourside and their stage of development;
- Alignment with the North Ayrshire Regeneration Delivery Plan (2021) and Vacant and
Derelict Land Strategy (2014);
- Deliverability of projects within the funding timescales;
- Need to balance feasibility and site preparation work, with interventions that see
physical space and employment created;
- Need to secure a spread of interventions in terms of type and geography; and
- Scottish Government’s aspiration for circa 25% to be spent on greening projects. 
The following projects are proposed for inclusion in the local delivery plan.  This has been
submitted to the Scottish Government, subject to Cabinet approval: 
Project Allocation
Ardrossan North Shore
This will support site remediation and infrastructure works and include
additional surveys and design work as required.
£350,000
i3 Investment Area
This will contribute to the development and delivery of the i3 Flexible
Business Space in the strategic investment campus.
£280,000
Lochshore
This will support the delivery of the Lochshore Masterplan including
surveys, consultancy support, site remediation works and environmental
improvements. This will support the submission to Round 2 of the Levelling
Up Fund.
£250,000
Harbour Master’s Office
This will support the restoration of the building including feasibility, design
work and further surveys.
£50,000
Kyle Road Phase 2
This will support the feasibility and design of a new commercial space
following the success of Phase 1. This will support the Commercial Estate
submission to Round 2 of the Levelling Up Fund.
£70,000
Development Work
This will support a range of surveys and investigations to inform proposals
for implementation in future years. This will include feasibility and
investigation work to support landowners and community groups to bring
back vacant land and properties to positive use.
£320,000 
Cycling, Walking and Safer Routes 
The Scottish Government’s Cycling Walking and Safer Routes programme provides direct
allocations to Local Authorities.  This can only be used for cycling, walking, safer routes and
active travel related projects.   
It is proposed that the £0.86m award received for 2022/23 be allocated as follows.  This
approach aims to support a range of eligible projects across North Ayrshire and secure
additional funding to maximise and accelerate delivery. 
53

Page 54

Project Allocation
Commercial Estate Low Carbon Infrastructure
This will provide a match funding contribution towards the low carbon
infrastructure element of the Commercial Estate application to Round 2 of
the Levelling Up Fund. 
£150,000
Lochshore Path Network
This will provide a match funding contribution towards the path network
creation within the Gateway to the West Coast and Clyde Islands application
to Round 2 of the Levelling Up Fund
£150,000
Ardrossan Low Carbon Hub
This will provide an additional match funding contribution towards the path
creation element of the ERDF Low Carbon Travel and Transport Challenge
Fund project.
£150,000
Active Travel Route construction
This will provide match funding to support funding applications to Sustrans
Places for Everyone and other active travel funding programmes.
£150,000
Future Year Feasibility Studies and Design Development
This will support the development of feasibility studies and designs for
implementation in future years and to support funding applications.
£90,000
Route Monitoring 
This will support the network of pedestrian and cycle counters across North
Ayrshire including the installation of new infrastructure.
£40,000
Strategy Development
This will support the continued development of the Local Transport and
Active Travel Strategy.
£30,000
Staff costs and resourcing
This will support the existing externally funded posts within the Active Travel
and Transport Team and provide match funding toward the Travel Smart
project funded by Smarter Choices Smarter Places.
£100,000 
Vacant and Derelict Land Investment Programme 
The Scottish Government announced a 5 year £50M competitive Vacant and Derelict Land
Investment Programme (VDLIP) in 2021/22. This aims to tackle persistent vacant and
derelict land and support place based approaches to delivering regeneration and
sustainable inclusive growth, as part of a ‘just transition’ to net-zero by 2045. The fund
complements the Place Based Investment Programme and is open for all local authorities
to apply.   
Potential projects were identified for the 2022/23 round based on the funding criteria, level
of project development and delivery timescales with Council Services.  Two applications
were submitted in November 2021 for the next phase of commercial development of
Annickbank, Irvine and to support the delivery of town centre living at the King’s Arms in
Irvine.  Both projects progressed to Stage 2 of the Programme in February 2022.   
An award for £0.4m was received for the Annickbank project in May 2022.  This will form
part of the match funding package for the Commercial Estate submission to Round 2 of the
Levelling Up Fund. 
54

Page 55

Strathclyde Partnership for Transport Capital Programme 
Strathclyde Partnership for Transport’s (SPT) Capital Plan sets out the funding programme
for projects to be delivered by SPT and partners on an annual basis.  Applications are
invited from Local Authorities in the Autumn of the preceding year.  Priorities for funding are
informed by the National, Regional and Local Transport Strategies.   
The following projects have been allocated funding through the overall £1.385m award from
2022/23 Capital Programme: 
Project  Award 
Ardrossan Harbour Interchange
This will support the public consultation, detailed design and tender
processes for the public transport interchange at the Harbour.
£50,000
B714 Active Travel Links
This will enable the development of detailed designs for active travel links to
the B714 from Dalry and Saltcoats.
£100,000
Brodick to Corrie Cycle Path
This will deliver the next phase of the off-road National Cycle Network (NCN)
Route 73 at Brodick Castle and Country Park.
£300,000
Bus Corridor Improvements
This will deliver a programme of bus stop infrastructure improvements
across North Ayrshire.
£200,000
Bus Routes Congestion Reduction Measures
This will deliver the final phase of the bus routes congestion measures
project between Kilwinning and Irvine.
£100,000
Cumbrae Ferry Bus Stop and Queuing Facilities
This will deliver the first phase of recommendations of the feasibility study
developed in 2021/22 including detailed designs and construction.
£385,000
Irvine Cycle Friendly Town 
This will deliver the next phase of the Irvine Cycle Friendly Town Study
recommendations including new path construction and signage.
£250,000 
UK Government’s Levelling Up Fund 
The Levelling Up Fund (LUF) is a £4.8 billion capital investment fund that will support town
centre and high street regeneration, local transport projects, and cultural and heritage
assets. North Ayrshire has been allocated as a ‘priority one’ category authority given our
socio-economic and connectivity challenges. 
This is a competitive bidding process against other local areas and the Council requires to
put forward high-quality, detailed and compelling business cases which meet the LUF
criteria. There are 4 assessment criteria for the fund: place (priority area categories),
strategic fit, value for money and deliverability. 
The Gateway to the West Coast and Clyde Islands bid is comprised of two impactful and
strategic regeneration projects at Lochshore in Glengarnock and North Shore in Ardrossan.
These projects will regenerate two former industrial sites which are long term vacant and
derelict land and identified as priorities for investment within the Council Plan and Local
Development Plan. 
55

Page 56

Whilst the individual strengths of the two applications are recognised, a detailed
assessment of the two projects against the assessment criteria has established that the
submission of the Lochshore Masterplan as a standalone project would present a more
compelling and coherent business case.  This would also achieve attractive value for
money assessments and cost benefit ratios further strengthening its competitive position.  It
is now proposed that the Gateway package bid be changed to the submission of a single
application for the Lochshore Masterplan on this basis.  Alternative sources of funding will
continue to be investigated for the North Shore project.   
Scottish Government’s Regeneration Capital Grant Fund 
The Scottish Government’s Regeneration Capital Grant Fund (RCGF) is delivered annually
in partnership with COSLA and local government. It supports locally developed place-based
regeneration projects that involve local communities, help to tackle inequalities and deliver
inclusive growth in deprived, disadvantaged and fragile remote communities across
Scotland. 
The Fund is subject to a two-stage assessment process. Applicants are required submit a
summary of their project on the form provided at Stage 1 by 17 June 2022. Successful
projects at this stage will be invited by the panel to then complete a full Stage 2 application
in October 2022. An independent investment panel will agree the recommendations to
Scottish Ministers and COSLA on projects to be offered grant support. 
The Fund is primarily aimed at providing new and/or improved infrastructure to improve the
economic, social, and physical environment of communities. Projects are expected to detail
how they are considering and contributing towards the target of net zero carbon emissions
by 2045. Projects should also: 
- Primarily focus on areas that suffer from high levels of deprivation and disadvantage; 
- Demonstrate clear community involvement;
- Deliver large scale transformational change with strong regeneration outcomes; and 
- Encourage additional investment and address market failure.
Officers from Connected Communities and Economic Development and Regeneration 
have supported with local groups and organisations to identify potential projects for 
submission to the Fund. This process has been informed by the funding criteria, key 
considerations and the level of community involvement based on the experience from 
previous successful applications. On this basis is it recommended that applications be 
submitted for the following two projects, listed in order of priority: 
i) Geilsland Courtyard Hall, Beith (Project Value £TBC) – £TBC grant sought towards
the upgrade and renovation of Geilsland Courtyard Hall, owned by the Beith
Community Development Trust (BCDT). The final phase of refurbishment would
allow the facility to support a diverse range of services and activity and generate
income for the BCDT. It would host festivals and events, commercial and residential
lets, large capacity venue hire, amenity for business, active lifestyles and creativity,
soft play and visitor accommodation.
ii) Kilwinning Sports Club (Project Value £TBC) – £TBC grant sought towards the
creation of an indoor sports facility and upgrade of infrastructure.  This will create an
inclusive and accessible facility to support a broad range of activities at the facility.
This would generate income for the Club and be capable of hosting a range of
sports, training and events. 
56

Page 57

Scottish Government’s Islands Programme 
The Islands Programme represents a £30million capital investment over five years to
support the delivery of the National Islands Plan. It aims to support projects which
encourage population growth and stem population decline and deliver on net zero
ambitions in a way that no-one is left behind. This will support a green economic recovery
from the ongoing impacts of the COVID-19 pandemic.   
The Programme is being delivered on a competitive bid basis across all six local authorities
with islands with a budget of £4m in 2022/23. It is open to applications from the six island
Local Authorities including North Ayrshire Council. The Councils are required to act as the
lead applicant. Project proposals are however expected to have been developed with the
involvement and support of relevant communities, as well as third sector and private sector
partners as appropriate. 
For 2022/23 there will only be a one stage application process.  The review of 2022/23 will
inform the approach in future years.  Project proposals should use clear Place based,
Community Wealth Building principles to support inclusive island growth while working to
achieve Scottish Government’s net zero ambitions and to support recovery from the
impacts of the pandemic. 
- Meet the overall objectives of the Islands Programme.
- Link directly to at least one of the National Islands Plan Strategic Objectives.
- Ensure transformational impact against place-based priorities to accelerate local growth
and resilience.
- Align with local critical infrastructure priorities and have the potential to collaborate with
other place-based investment opportunities to maximise benefits.
- Demonstrate project readiness, collaborative and partnership models, project viability
and long-term sustainability.
- Demonstrate clear Community Wealth Building principles and community involvement
and engagement
- Support Scottish Government Net Zero Ambitions and a Just Transition. 
Officers from Connected Communities and Economic Development and Regeneration 
have consulted with local groups and organisations to identify potential projects for 
submission to the Fund. This process has been informed by the funding criteria, key 
considerations and the level of community involvement. On this basis is it recommended
that applications be submitted for the following two projects: 
i) Millport Town Hall Phase Two (Project Value £0.5m): £0.465m grant sought towards
the next phase of the redevelopment of the Town Hall. This will include an office
space, basement Heritage/Conservation Centre plus green room, permanent Men’s
shed, storage areas and small community garden.
ii) Island Pit Stops (Project Value £0.6m): £0.54m grant sought towards the redevelop
island toilet buildings owned by North Ayrshire Council into “Pit Stops.” These will be
refurbished into eco-designed buildings with landscaped outdoor spaces that offer
communities and visitors access to sustainable and efficient amenities including:
improved toilet facilities, local information and interpretation, cycle parking and
maintenance stations. 
57

Page 58

Scottish Government’s Vacant and Derelict Land Investment Programme 
Applications are currently being invited to the 2023/24 round of the Vacant and Derelict
Land Investment Programme.  The following projects are proposed for submission: 
- King’s Arms Redevelopment (Total Project Value £1.754m): £0.6m grant sought
towards the redevelopment of the former King’s Arms.  This will deliver six new Council
town centre amenity homes for affordable rent comprising one and two bedrooms.
- Town Centre Living Pilot at 36 Bank Street, Irvine (Total Project Value £1.1m): £0.4m
grant sought towards the redevelopment of the property as three townhouses.  This
would enable the project to be delivered to an enhanced energy standard. 
Historic Environment Scotland’s Heritage and Place Programme 
The Heritage and Place Programme is an area-based funding programme and the
successor to the Conservation Area Regeneration Scheme (CARS).  It aims to contribute to
the development of vibrant and sustainable places in Scotland, through community-led
regeneration of the historic environment. It supports the development and delivery of
heritage focused schemes within Conservation Areas, or alternatively distinctive heritage
areas with Local Authority recognition. 
The programme is open to expressions of interest by 31 July 2022 from Local Authorities,
National Park Authorities and suitably experienced not-for-profit organisations. If an EOI is
approved, the applicant will be invited to submit a Development Phase application by 15
December 20022. All Development Phase applications will be assessed as a batch through
a competitive process.  Successful applicants will have up to 12 months to undertake a
Development Phase and submit their Delivery Phase application. 
It is proposed that priorities for expressions of interest be identified through the Place
Framework process for Largs, Saltcoats, Kilwinning and the Garnock Valley.  The approach
will be informed by engagement with the funder, Connected Communities and local
heritage organisations. 
National Lottery Heritage Fund’s Grants for Heritage 
The Grants for Heritage programme provides grants of between £0.25m and £5m for
projects that connect people and communities to national, regional and local heritage.  All
projects must be inclusive and environmentally sustainable and deliver on the priority
outcomes to: 
- Create better places to live, work and visit;
- Boost the local economy;
- encourage skills development and job creation;
- Support wellbeing; and
- Improve the resilience of organisations working in heritage. 
Expressions of interest are currently being invited for projects over £0.25m.  It is proposed
that priorities for expressions of interest be identified through the Place Framework process
for Largs, Saltcoats, Kilwinning and the Garnock Valley.  The approach will be informed by
engagement with the funder, Connected Communities and local heritage organisations. 
58

Page 59

Appendix 2 
Regeneration Delivery Plan Funding Proposals
Place Based Investment Programme and Vacant and Derelict Land Fund Proposals 
Overview 
The Regeneration Delivery Plan sets out the Council’s priorities for delivering on the
regeneration ambitions of the Council Plan and Community Wealth Building strategy,
working in partnership with communities. The Plan focuses on the delivery of physical
regeneration across North Ayrshire through an ambitious project based rolling action
programme. It informs priorities for securing and delivering against external funding
sources including Scottish and UK Government funds. 
Cabinet considered the funding proposals under the Regeneration Delivery Plan for
2022/23 on 7 June 2022.  The proposals included the expenditure of the £1.32m Vacant
and Derelict Land Fund (VDLF) allocation and the £1.093m allocation under the Scottish
Government’s Place Based Investment Programme (PBIP).  Underpinned by the Place
Principle, the PBIP aims to support community-led regeneration, and support town centres
and the 20-minute neighbourhood ambitions. The VDLF aims to tackle the presence of
long-term vacant (for 15 years or longer) and derelict land in Scotland. 
Proposal 
The funding proposals under the £1.32m VDLF award included the allocation of £320,000
to Development Work. This aims to support a range of surveys and investigations to inform
proposals for implementation in future years. This will include feasibility and investigation
work to support landowners and community groups to bring back vacant land and
properties to positive use. 
The funding proposals under the £1.093m PBIP award included the allocation of £250,000
to the following projects: 
- £70,000 to Saltcoats Place Framework
- £70,000 to Largs Place Framework
- £70,000 to Kilwinning Place Framework
- £40,000 to Future Years Project Development.   
The Place Framework allocations would support the delivery of the community identified
actions in each of the towns including physical improvements and CWB opportunities. The
Future Years Project Development would enable the preparation of proposals for
implementation in future years and support funding applications. 
Further information 
The Scottish Government's Vacant and Derelict Land Fund (VDLF) aims to tackle the
presence of long-term vacant, for 15 years or longer, and derelict land in Scotland. In
doing so, it aims so stimulate economic growth, job creation, an improved environment
and quality of life. For the purposes of the 2022/23 allocation long term is defined as land
out of use since at least 2006. 
59

Page 60

The annual Scottish Vacant and Derelict Land Survey (VDLS) is used to monitor the direct
impact of the fund on reducing levels of vacant and derelict land. The survey only records
changes to sites greater than 0.1 hectare (1000m2) in size that have previously been
developed but are now considered unused or damaged.  The allocation of the VDLF is
restricted on this basis to sites over 0.1ha, registered as part of the annual VDLS, and
vacant or derelict for over 15 years.  Due to the size limitations, the majority of town centre
or High Street properties would not provide eligible expenditure for this Fund on this basis. 
The 2020 Programme for Government established a Place Based Investment Programme
(PBIP). A budget of £325m was committed to the Programme over 5 years from 2021/22.
The main objectives of the Programme are to: 
- Link and align place based initiatives and establish a coherent local framework to
implement the Place Principle;
- Support place policy ambitions such as town centre revitalisation, community led
regeneration, 20 minute neighbourhoods and Community Wealth Building;
- Ensure that all place based investments are shaped by the needs and aspirations of
local communities; and
- Accelerate the ambitions for tackling inequality and disadvantage, wellbeing and
inclusive economic development, net zero, community involvement and ownership. 
Place Frameworks are a key action of the Regeneration Delivery Plan and aim to ensure
that our regeneration ambitions are delivered in partnership with communities.  These
build on previous community engagement including Charette processes and updated town
centre audits to develop a Place Framework for each town.  Feedback throughout the
development of the Regeneration Delivery Plan and Place Frameworks has reiterated the
need to progress from priority identification to delivery in the towns. 
Funding was secured from the UK Government’s Community Renewal Fund to pilot the
approach in Saltcoats and Largs.  A further allocation was made under the PBIP in
2021/22 to develop a Place Framework for Kilwinning.  Each Place Framework will identify
physical improvements and CWB opportunities to support recovery and development
within the town centre.  They are informed by extensive community and stakeholder
consultation and engagement to ensure that they reflect local priorities and ambitions.   
The Place Framework allocations from the 2022/23 PBIP aim to implement the
recommendations of the Place Frameworks on the ground and progress to the delivery
phase. This could therefore already involve the purchase properties where: 
- The purchase is identified as a priority through the Place Framework process; and 
- A deliverable solution is available for the repurposing of the property. 
By allocating funding to the delivery of Place Frameworks we will ensure that expenditure
is informed by community priorities.  The funding allocations would also be used to secure
external match funding where appropriate to maximise the reach of the funding.  This is in
accordance with the objectives of the PBIP. 
The Future Years Project Development allocation aims to support the preparation of
proposals and detailed designs for PBIP implementation in future years.  It also aims to
support the submission of external funding applications to the Regeneration Capital Grant
Fund, Islands Programme and other funding sources.  This aims to maximise the level of
funding which can be secured and the impact of investment in regeneration across North
Ayrshire.
60

Page 61

The Repurposing Property Grant Fund (RPGF) was developed in 2021 to help support
landowners and community groups to bring back vacant land and properties to use.  The
funding package is comprised of allocations from the 2021/22 PBIP, VDLF and North
Ayrshire Ventures Trust (NAVT).  Funding is allocated to projects from the overall funding
package informed by the constituent funds’ constraints. This provides funding to
landowners and community groups to undertake feasibility studies to identify potential
options for the sites and their viability.     
The second round of the Repurposing Property Grant Fund is open until late July 2022. 
The Regeneration team are actively engaging with landowners and communities to
support applications to the Fund.  It is envisaged that further stages of the Fund will be
developed to support project delivery following the feasibility stage.  The approach to this
will be informed by the outcome of Stage 1 and further funding applications in support of
the Fund.   
This approach aims to complement existing sources of funding such as the Scottish Land
Fund and not replace these.  This aims to maximise the impact of the fund. It is important
to note that costs associated with repurposing town centre properties are not
unsubstantial. A recent feasibility study for a 335m2 town centre property in the Three
Towns has identified cost estimates of circa £0.826m subject to substantial caveats.  This
illustrates the potential levels of resource required to repurpose properties of this nature. 
A Communities Project Fund was also set up in 2021.  This is a small grant scheme to
support community led place-based project development and implementation across North
Ayrshire. This will support the annual RDP action review and PBIP implementation
proposals in future years.  The original fund of £0.07m was further supplemented in
2021/22 by an additional allocation from the PBIP to £0.315m.  This is supporting a range
of projects across North Ayrshire. 
The Council’s £15.723m Investment Fund aims to deliver climate change, sustainable
infrastructure investment and Community Wealth Building (CWB). This includes an
allocation for CWB Commercial Estate, Infrastructure and Town Centre Investment of
£1.155m and an allocation for CWB Communities and Town Centre investment of £1.2m. 
These allocations will support and deliver investment around town centres for example by
providing match funding for external funding applications. 
Conclusion 
The Regeneration Delivery Plan funding proposals aim to align the funding to projects
which deliver on the individual funds’ priorities and objectives.  Place Frameworks are key
to identifying physical improvements and CWB opportunities to support recovery and
development within town centres.  Importantly, they are informed by extensive community
and stakeholder consultation and engagement to ensure that they reflect local priorities
and ambitions.   
The Place Framework allocations would be used to implement the short and medium term
priority actions identified within each town’s Place Framework. This could therefore be
utilised to purchase properties where: 
- The purchase is identified as a priority through the Place Framework process; and 
- A deliverable solution is available for the repurposing of the property. 
61

Page 62

Alongside the Investment Fund allocations, RPGF and Communities Project Fund, these
proposals aim to bring vacant and derelict land into positive use in partnership with
landowners and communities. The proposals are also reflective of the funding constraints
and potential budgetary and funding implications outlined in this Report. 
Louise Kirk
Senior Manager Regeneration
North Ayrshire Council 
23 June 2022
62

Page 63

NORTH AYRSHIRE COUNCIL 
30 June 2022 
Audit and Scrutiny Committee 
Title:    Call In:  North Ayrshire Covid Recovery Fund   
Purpose:  To allow the Committee to consider a Call In Request in respect
of the decision taken by Cabinet at its meeting on 7 June 2022
to:- 
(a) note the Scottish Government’s recently announced Economic
Covid Recovery Fund, which would see an allocation of £2.154m
for North Ayrshire; and (b) approve the proposed North Ayrshire
Economic COVID Recovery Fund Investment Plan. 
Recommendation:  That the Committee considers the terms of the Call In and
agrees, or otherwise, to make a recommendation to the Cabinet. 
1. Executive Summary 
1.1    In terms of the Scheme of Administration (Section 24), the Audit and Scrutiny
Committee has a remit to consider Call in Requests and invite at least one of the
Members who has requested the reference to Call In to attend the Committee to
explain the request. 
1.2 This report sets out the background to the Call In Request in respect of the decision
taken by Cabinet at its meeting on 7 June 2022 in relation to the report on North
Ayrshire Covid Recovery Fund. 
2. Background 
2.1 The Cabinet, at its meeting on 7 June 2019, considered a report on North Ayrshire
Covid Recovery Fund. 
2.2 A request was received in terms of the Call In procedure set out in the Council's
Scheme of Administration and Standing Orders, that the Audit and Scrutiny
Committee examine the decision taken by the Cabinet. 
Agenda Item 4
63

Page 64

2.3 The Call In Request, which was signed by Councillors Foster, McDonald and
Cullinane is in the following terms:- 
Reason for Call In 
Given their dominance of the local bus market, the “Public Transport Travel
Scheme” is effectively a public subsidy for Stagecoach at a time when they are
cutting local services 
Desired Outcome 
That we send a very strong public message to Stagecoach that the Council will
not accept their cuts to local bus services and therefore the £20,000 for the
“Public Transport Travel Scheme” be reallocated to support the North Ayrshire
Fairer Food Network. 
2.4 A copy of the original report presented to Cabinet on 7 June 2022 is attached as an
appendix to the report.  An updated briefing note has been provided by the Executive
Director (Place) and is attached at Appendix 2. 
2.5 The Call In Request is valid for consideration by the Committee.  The request was
received within the appropriate timescale, it was signed by three Elected Members
and details were provided on both the reason for the Call In and the desired outcome. 
2.6 The Elected Members who have submitted the Call In will be invited to address the
Audit and Scrutiny Committee to explain the Call In Request.  The appropriate Cabinet
Member, accompanied by senior officers, will then be invited to clarify the reasons for
the decision.  The Committee will have an opportunity to ask questions of both parties
and of those officers in attendance. 
2.7 The Committee will then debate the Call In Request and decide whether or not it
agrees with the decision of the Cabinet. 
2.8 Where the Committee does not agree with the decision of the Cabinet, the matter will
be referred to the next meeting of the Cabinet with recommendations from the Audit
and Scrutiny Committee for alternative action.  The Audit and Scrutiny Committee
therefore has to:- 
i)  decide if it agrees or not with the decision of the Cabinet; and
ii) consider what alternative action the Committee would recommend to the
Cabinet if it does not agree with the decision. 
2.9 When the matter is considered by the Cabinet, the Chairperson or another member of
the Audit and Scrutiny Committee will have the right to attend the Cabinet and speak
in support of any recommendation. 
2.10 In the event the Cabinet declines to accept the recommendation from the Audit and
Scrutiny Committee, the matter will be referred to the next ordinary meeting of the
Council for determination.  The decision of the Council will be final.  
64

Page 65

3. Proposals 
3.1 It is proposed that the Committee considers the Call In Request. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are outlined in the report attached at Appendix 1. 
Human Resources 
4.2 The human resource implications are outlined in the report attached at Appendix 1. 
Legal 
4.3 The legal implications are outlined in the report attached at Appendix 1. 
Equality/Socio-economic 
4.4 The equality/social-economic implications are outlined in the report attached at
Appendix 1. 
Climate Change and Carbon 
4.5 The climate change and carbon implications are outlined in the report attached at
Appendix 1. 
Key Priorities 
4.6 The key priorities are outlined in the report attached at Appendix 1. 
Community Wealth Building 
4.7 The community wealth building implications are outlined in the report attached at
Appendix 1. 
5. Consultation 
5.1 No formal consultation has been undertaken at this stage. 
Craig Hatton
Chief Executive 
For further information please contact Angela Little, Committee Services Officer, on 
01294 324132 
Background Papers 
N/A
65

Page 66

NORTH AYRSHIRE COUNCIL
7 June 2022                                                                                  
Cabinet
Title: North Ayrshire Economic COVID Recovery Fund
Purpose: The purpose of this report is to provide a briefing on the
Economic COVID Recovery Fund and seek agreement for the
proposed North Ayrshire Economic COVID Recovery Fund
Investment Plan
Recommendation: It is recommended that Cabinet:
i. Notes the Scottish Government’s recently announced
Economic Covid Recovery Fund, which will see an
allocation of £2.154m for North Ayrshire; and
ii. Approves the proposed North Ayrshire Economic COVID
Recovery Fund Investment Plan
1. Executive Summary
1.1 The Economic COVID recovery funding, announced by the First Minister on 21st
February 2022, allocates £80million of additional investment for businesses and
communities to accelerate economic recovery.  This funding will support local flexibility
and must be fully utilised by 31st March 2023.  North Ayrshire Council has been
allocated £2.154m funding to support a new Economic COVID Recovery Investment
Plan. 
1.2 The proposed North Ayrshire Economic COVID Recovery Investment Plan has been
aligned with both the Scottish Government’s recently launched National Strategy for
Economic Transformation (NSET) and the Tackling Child Poverty Delivery Plan 2022-
26 and is focussed on the creation of a well-being economy, supporting a green and
just transition and maximising the opportunities for ensuring reduced family poverty in
North Ayrshire.  
2. Background
2.1 The Economic COVID Recovery Fund provides an additional £80million for Scotland to
support business and communities to accelerate economic recovery within local areas.
2.2 The policy intent of this funding is to support local economic recovery and the cost-of-
living impacts on low-income households. It is acknowledged that Local Authorities are
best placed to understand the needs of local businesses and communities and can
design and deliver interventions to best meet local needs. 
Appendix 1
66

Page 67

2.3 The overarching principles of this fund are to support: 
• Interventions enabling local economic recovery and contributing to businesses
being able progress towards recovery, growth, adaptation and building
resilience 
• Projects that can rebuild consumer confidence, stimulate demand, and enable
economic activity 
• Support low-income households, which are disproportionately impacted by the
pandemic and the current cost of living crisis, to become more economically
active
2.4 The funding cannot be used to increase the overall budget available for Scottish Welfare
Fund and/or fund Discretionary Housing Payments.   
2.5 COSLA’s Settlement and Distribution Group recommended this funding is included in
the Local Government Finance Order and paid as a Redetermination at the end of
March 2022.  The settlement for North Ayrshire totals £2.154m. 
2.6 In March 2022, Scottish Government published the second ‘tackling child poverty
delivery plan’ under the Child Poverty (Scotland) Act 2017. Outlining actions for the
period 2022 to 2026, Best Start, Bright Futures sets out how key stakeholders will
work together to deliver on Scotland's national mission to tackle child poverty. It is
not solely a plan for the Scottish Government, it is a plan for all of Scotland,
recognising the contribution all parts of society must make to deliver the change
needed for children and families. 
2.7 North Ayrshire faces significant challenges with over 6000 young people identified as
living in poverty (approximately 27.9% of all children living in the area).  The Scottish
Government’s recent Spending Review identified reducing child poverty as one of its
three key priorities and has set ambitious targets for 2022-26. Although progress is
being made in addressing child poverty in North Ayrshire, the pressure of the cost-
of-living crisis following so quickly after the Covid-19 pandemic demands immediate
systemic and far-reaching responses. 
2.8 The Scottish Government has recently launched the National Strategy for Economic
Transformation (NSET) with an overarching ambition to work towards the creation of a
well-being economy, supporting a green and just transition.  North Ayrshire Council’s
economic activities are aligned to this ambition and informed by the Council’s
Economic Recovery and Renewal Approach – which proposes to ‘Build Back Better,
Fairer and Greener’; NA’s Community Wealth Building Strategy; NA Regeneration
Delivery Plan; and the recently launched Island Plans.  All these plans are action
focused and this additional investment will support the delivery of them plan to support
recovery more quickly. 
2.9 Details of each proposal and how it aligns with the overarching principles of the
COVID Recovery Fund, and the Child Poverty Fund is set out in the Appendix 1. 
These proposals require to be completed by 31st March 2023.  In summary the North
Ayrshire Economic Recovery Fund Investment Plan (Appendix 1) includes the
following interventions: 
• Public Transport Travel Scheme to support travel to work
• Digital Growth Fund for Businesses 
• Support the delivery of the Council’s Modern Apprentice Programme
67

Page 68

• Create new Skills for Life work placements 
• EQUAL Horticulture Intermediate Labour Market (ILM)
• Employer Recruitment Incentives (ERIs)
• £100 top up to the Summer Child Bridging Payments 
• Review and improve support for childminders and OOSC providers
• Targeted employability opportunities for key families during Summer 2022
• Third sector support for programmes to support low-income families and
individuals by building on current programmes
• North Ayrshire Fairer Food Network  
• Support for the development of a North Ayrshire Child Poverty Strategy
and Action Plan. 
2.10 Throughout the recovery, local authorities, including North Ayrshire, have been
taking part in national community engagement sessions, listening to business and
reviewing the feedback and data in relation to the effectiveness of previous funding
support.  North Ayrshire Council works closely with its communities, who have been
sharing their priorities through virtual community engagement sessions, as well as
in-person through the resumption of targeted community activities such as
community breakfast clubs. 
2.11 The proposals in this report have been shaped by the voices of ‘lived-experience’
through the Fair for All Commission, young people, partners and the experience of
the interventions supported by previous funding.   It has also been shaped and
informed by information and knowledge of demand for support and identification of
capacity to realise an opportunity to scale up services quickly. 
2.12 As a result, a number of investments are therefore proposed in relation to the
following Covid principle: “Support low-income households, that are
disproportionately impacted by the pandemic and the current cost of living crisis, to
become more economically active.”   
The proposals contribute to the child poverty delivery plan themes, focusing on:
• Relieving immediate financial pressure for key groups of families through direct
payments and access to cost effective to food, travel and other supports. 
• Removing barriers to employment by supporting the Out of School Care sector in
North Ayrshire and preparing for the forthcoming wrap-around care requirements
outlined in the Scottish Government child poverty delivery plan; and
• Delivering employability and work placement opportunities for targeted, more
vulnerable families. 
• Supporting businesses to recover and grow by enhancing digital capacity and
providing support to recruit. 
• Creating new and additional job opportunities 
3. Proposals 
3.1 It is proposed that Cabinet: 
i. Notes the Scottish Government’s recently announced Economic
Covid Recovery Fund, which will see an allocation of £2.154m for
North Ayrshire; 
ii. Approves the proposed North Ayrshire Economic COVID Recovery
Fund Investment Plan
68

Page 69

4. Implications/Socio-economic Duty 
Financial 
4.1 These proposals are supported by external funds distributed to Local Authorities.  The
estimated financial profile is included as Appendix 1 of this report. 
Human Resources 
4.2 The proposals outlined will be supported utilising existing staff. In addition, the
Connected Communities proposals include the creation of 5 temporary posts within
the relevant areas of work to increase capacity for specific transition activity and
deliverables:
• 1 temporary G12 Business Support Officer (12 months) post to identify and
develop the support required for the Out of School Care sector;
• 1 temporary G11 Business Support Officer (12 months) post to further extend
and develop the North Ayrshire Fairer Food Network; 
• 2 temporary G9 Locality Workers (12 months) posts to coordinate ‘Out and About
Group’ food growing and mental health and wellbeing activities and extend
capacity at Eglinton Community Garden;
• 1 temporary G12 Business Support Officer (12 months) post to support the
transition to and coordinate the new Child Poverty strategy. 
Legal 
4.3 There will be grant conditions associated with any external funding awards. These will
require to be reviewed with input from Legal Services prior to acceptance to inform
delivery and to be managed appropriately. 
Equality/Socio-economic 
4.4 These proposals aim to support those most disadvantaged and will aim to address
barriers and improve access and equality.  An Equality Impact Assessment will be
completed to ensure equality is considered as part of design and implementation of
these proposed interventions. 
Climate Change and Carbon 
4.5 The Digital Business Support activity supports local business adapt business processes
to maximise digital capabilities and opportunities as part of a green transition.  The
Active Travel proposal supports the use of public and sustainable travel to work options. 
The Fairer Food Network promotes local food growing. 
Key Priorities 
4.6 The approach will contribute to achieving a wide range of the Council Plan outcomes
and ambitions: of an inclusive, growing and enterprising economy; for children and
young people to have the best start in life; residents and communities enjoy good life-
long health and well-being; and for a sustainable, vibrant, welcoming and attractive
environment.”
69

Page 70

Community Wealth Building 
4.7 These proposals directly contribute to the Community Wealth Building mission of
enhancing local wealth and the creation of fair jobs and maximising the potential of all
our places through working in partnership with our communities and businesses. 
5. Consultation 
5.1 North Ayrshire Council works closely with its communities, who have been sharing their
priorities through virtual community engagement sessions, as well as in-person through
the resumption of targeted community activities such as community breakfast clubs. 
The proposals in this report have been shaped by the voices of ‘lived-experience’
through the Fair for All Commission, young people, partners and the experience of the
interventions supported by previous funding. 
This has been informed by the Council Plan priorities, Community Wealth Building
Strategy, Recovery and Renewal Strategy and Regeneration Delivery Plan (RDP) as
well as the Scottish Government’s Child Poverty Delivery Plan. 
.  
RUSSELL McCUTCHEON
Executive Director (Place) 
AUDREY SUTTON
Executive Director (Communities and Education) 
MARK BOYD
Head of Finance 
For further information please contact Laura Neill, Senior Manager Employability &
Skills, on 01294 324802. 
Background Papers
0
70

Page 71

Appendix 1: North Ayrshire Economic COVID Recovery Fund Investment Plan 
COVID
Economic
Recovery
Fund
Intervention
Proposal COVID
Recovery
Fund Cost
COVID
Recovery
Fund
Principles
Child
Poverty
Delivery
Plan
Focus
Public
Transport
Travel
Scheme
To support low-income households
and individuals returning to work
with free access to public transport
for a fixed period e.g., three
months of free access to bus or rail
travel.  Beneficiaries would be
supported with a free personalised
travel plan to identify the best travel
option.  This would support low-
income households, access to
employment, address transport
poverty, build confidence in public
transport post covid.  Due to the
nature of the travel cards this
would benefit them for both work
and their personal life as they could
be used at evenings/weekends.  
£20,000  1, 5 A, B, C
Digital
Growth Fund
for
Businesses
To help support digital growth
within our small and new start
businesses. 
£100,000 3  NA
Modern
Apprentices 
Support the delivery of the
Council’s Modern Apprenticeship
Scheme. 
£476,000  1, 5 A, C
Skills for Life Create additional paid work
placements for low-income families
to gain skills, experience and
qualification to progress to
sustainable employment in the
future
£120,000 1, 5 A, C
EQUAL
Horticulture
Intermediate
Labour
Market (ILM)
Create additional paid work
experience opportunities for people
with disabilities to work in the Equal
community garden and gain
qualifications in horticulture, skills
and experience to progress to
employment.  
£120,000 1, 5 A, C
Employer
Recruitment
Incentives
(ERIs)
Support employers to create a new
and additional job for a benefit from
a COVID Recovery Fund Priority
Group 
£240,000 1, 5 A, C
71

Page 72

Additional
Summer
Child
Bridging
Payment
The Scottish Government already
provide Child Bridging Payment
funding to local authorities for each
child in receipt of Free School
Meals on the basis of low income.
These payments are provided for
all eligible children and young
people of school age. The
payments total £520 per annum
and they are currently paid in
spring, summer, autumn and winter
at £130 for each eligible child. To
help address the current cost of
living pressures and to also
recognise the needs of families of
children of pre-school age it is
proposed that the scheduled
summer Child Bridging Payment of
£130 be increased to £230
(additional £100 payment) and that
eligibility for the £100 payment is
extended to low income families of
children of pre-school age. It is
estimated that the £100 payment
will benefit around 5,700 children
(over 3,300 families) with payments
made from late June 2022. 
£570,000 1, 2, 4, 5 B
Review and
improve
support for
child
minders and
OOSC
providers
Aimed at sustaining local childcare
provision, to support employability
and offer positive placements for
vulnerable children and those in
kinship care. By the end of this
parliament Scottish Government
has committed to ensure provision
of wrap around childcare for
families who need it. Use of
childcare has changed significantly
because of Covid. OOSC providers
face a particularly unstable
business environment. Reduced
use of OOSC services during
lockdown and changed working
patterns provide an opportunity to
assess future demand and support
the sector to ensure the local
availability of services in line with
Scottish Government’s
expectations. 
£126,000 1, 2, 3 A, B, C
Targeted
employability
opportunities
for key
families
during
Summer 2022
With childcare available in OOSC
services over the summer, parents
and carers with school age children
will be encouraged to undertake a
variety of short courses that upskill
or lead to a route into employment.
Ten programmes will be delivered
near OOSC provision or in the
£50,000 1, 2, 3 A, B, C
72

Page 73

same building. This will build
relationships between the
Employability Team and
participants, whilst building up
confidence in the use of childcare
services. It will effectively provide a
wider awareness of and confidence
in the support available and will
help to sustain the providers by
addressing the current pressure
created by current low uptake -
£50k.
Third sector
support for
programmes
to support
low-income
families and
individuals
by building
on current
programmes
Work with the third sector support
for programmes to support low-
income families and individuals by
building on current programmes
such as Out and About, working
with families and key groups to
improve access to food and
environmental opportunities locally,
including through the Fairer Food
network and Eglinton Garden
Project, to develop skills to grow
and cook food and, through family
sessions and activities, build
ongoing individual and community
capacity. These sessions will
encourage people to engage with
the local environment to support
mental health and wellbeing and to
develop parenting skills, family
bonding, relationships, volunteering
and employability in a supportive
environment. This will be a ‘test
and learn’ trial in one locality over a
year, which will establish impact
and provide data and evidence for
future service design and external
funding bids. The initiative will link
to the Love Local voucher scheme
which will support local businesses. 
£114,000  
North
Ayrshire
Fairer Food
Network  
The North Ayrshire Fairer Food
Network is our local alternative to
foodbanks and is aimed at
addressing food insecurity in a
dignified way. Further development
of the larders and shops will
support low-income residents by
developing and improving the
sustainability of the existing
network. New initiatives and
business models include
community fridges, community
cafes, social enterprises based on
growing produce and better links
across providers. It will also focus
on support for the islands
£142,000 3 A, B, C
73

Page 74

communities so that approaches
are developed which fit their
specific needs
Support for
the North
Ayrshire
Child Poverty
Strategy and
Action Plan.
The Council and NHS Ayrshire and
Arran propose to publish a one-
year action plan and a three-year
strategy, to effect a step-change in
our approach to working more
effectively across the system. This
involves a range of services,
partners and actions, the
coordination and planning of which
require additional short-term
resources to ensure maximum
impact. The coordination of the
proposed Child Poverty Board,
North Ayrshire plan and strategy
will identify the strategic
interventions necessary to escalate
the response and impact on child
poverty locally.
£76,000    
TOTAL Request  £2,154,000   
74

Page 75

COVID Recovery Fund Principles:
1. All interventions made under this fund should be based on a clear economic recovery and/or
low-income household support rationale. 
2. A collaborative approach towards sharing of best practice and learnings from different
interventions should be adopted to maximise benefits and positive effects while minimising risk
and unintended consequences   
3. These funds can be used by Local Authorities on interventions that support local economic
recovery and enable businesses to move from surviving the period of trading restrictions
towards recovery, growth, adaptation and building 
4. These funds can be used by Local Authorities on projects that can rebuild consumer confidence
and stimulate demand and economic activity in their specific context
5. These funds can be used by Local Authorities to support the low-income households, which are
disproportionately impacted by the pandemic and the current cost of living crisis, become more
economically active 
Child Poverty Delivery Plan Focus: 
A. Providing the opportunities and support needed to enter, sustain and progress in work –
including a new employability offer to parents and improvements to the support structures
needed including through childcare and transport.
B. Maximising the support available for families to lead dignified lives and meet their basic
needs – actions include a transformational approach to people and places, social security
and income maximisation and delivery of warm and affordable homes.
C. Supporting the next generation to thrive –delivered through a range of interventions
underpinned by GIRFEC, the Promise, tackling the poverty related attainment gap, and
through investment in the Young Person’s Guarantee. 
75

Page 76

Appendix 2 
North Ayrshire Economic Covid Recovery Fund
Public Transport Scheme 
Overview 
The Scottish Government’s Economic COVID recovery funding announced in February
2022, allocated £80m of additional investment for businesses and communities to
accelerate economic recovery. This funding is being directly allocated to Local Authorities,
and aims to support local flexibility and must be fully utilised by 31 March 2023. 
North Ayrshire Council was allocated £2.154m of this funding to support a new Economic
COVID Recovery Investment Plan. The proposed Plan was considered by Cabinet on 7
June 2022.  This was aligned with the Scottish Government’s ‘Strategy for Economic
Transformation’ and the ‘Tackling Child Poverty Delivery Plan 2022-26’. It focussed on the
creation of a well-being economy, supporting a green and just transition and maximising
the opportunities for ensuring reduced family poverty in North Ayrshire. 
Proposal 
The Economic COVID Recovery Investment Plan sought approval for a number of
interventions, including the creation of a Public Transport Scheme using £0.02m of the
overall £2.154m allocation.  This proposal aims to support low-income households and
individuals returning to work with free access to public transport for a fixed period.  The
scheme would provide three months of free access to bus or rail travel.  Beneficiaries
would also be supported with a free personalised travel plan to identify the best travel
option for them.  This would support low-income households, access to employment,
address transport poverty and build confidence in public transport post covid.  Due to the
nature of the travel cards this would benefit beneficiaries for both work and their personal
life as they could also be used at evenings/weekends. 
Further information 
The Council piloted the use of the Inclusive Growth Diagnostic in 2017.  This was
extended to cover the whole of Ayrshire during 2018. This identified the main constraints
to inclusive growth which included transport.  Through this transport was identified as a
limiting factor to and preventing people from accessing employment and training
opportunities.  The cost of transport was identified as a contributing factor.  The Public
Transport Scheme aims to tackle this by providing free travel for a fixed period to support
low income households and the return to employment or training. 
The Public Transport Scheme would be delivered by the Active Travel and Transport
Team within Economic Development and Regeneration.  The beneficiaries of the Public
Transport Scheme would be identified through the Council’s Employability team.  This will
be an important addition to the existing services and support provided through the
Employability programmes. 
Each beneficiary would be provided with a free personalised travel plan through the Trinity
Active Travel Hub to identify the best travel solution for their work journey.  All sustainable
and active travel modes would be considered through this assessment including bus and
rail options depending on the most appropriate travel mode for each individual.  There are
76

Page 77

a number of bus operators across North Ayrshire. The travel card provided will enable the
user to access the most appropriate bus operator’s services or rail options in their area. 
The appropriate travel cards would then be purchased for the beneficiaries for their use
during the 3 month period.  Further advice and support would be provided as required to
beneficiaries through the Trinity Active Travel Hub as required. 
As the travel cards are not limited to use for work journeys, they could be used by
beneficiaries for personal travel for example at evenings and weekends.  This would
support transport for a range of purposes including to access services or undertake social,
health and leisure activities. The travel cards would be able to be used alongside existing
concessionary travel schemes including the: 
- Young Person’s Free Bus Travel Scheme which allows children and young people
under 22 free bus travel;
- Kids for a Quid rail scheme allows children to travel for £1 alongside an adult traveller,
for up to four children; and   
- Concessionary travel scheme for disabled people and those over 60 years of age. 
The proposal contributes to the principles of the Recovery Fund and Child Poverty Action
Plan as follows: 
- Recovery Fund Principle 1 as it is based on a clear economic recovery and providing
support to low-income households.
- Recovery Fund Principle 5 as it provides support to low-income households, that are
disproportionately impacted by the pandemic and the current cost of living crisis, to
become more economically active.
- Child Poverty Action Part A as it provides opportunities and support to enter, sustain
and progress in work by providing free travel as a support structure.
- Child Poverty Action Part B as it maximises the support available for families to lead
dignified lives and meet their basic needs. 
- Child Poverty Action Part C as it provides support to enable the next generation to
thrive by linking in with other travel schemes. 
Pre and post intervention surveys would be undertaken with beneficiaries to assess the
impact of the scheme. 
Conclusion 
The proposed Public Transport Scheme would directly benefit low-income households by
reducing the impact of travel costs on household budgets and helping to address transport
poverty.  This will improve access to employment opportunities and sustain employment. 
It will also build confidence in the public transport network post-pandemic and support
sustainable travel for everyday journeys. 
The mode of transport would be tailored to individual beneficiaries’ needs and both bus
and rail travel solutions would be facilitated across North Ayrshire.   
Louise Kirk
Senior Manager Regeneration
North Ayrshire Council 
20 June 2022
77