NORTH AYRSHIRE COUNCIL 
31 May 2022 
Audit and Scrutiny Committee 
Title:    Internal Audit and Corporate Fraud Action Plans: 
Quarter 4 update 
Purpose:  To advise the Audit and Scrutiny Committee on the progress
made by Council Services in implementing the agreed actions
from Internal Audit and Corporate Fraud reports as at 31 March
2022. 
Recommendation:  That the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions;
and (b) challenges those Services that have not implemented
actions within the previously agreed timescales. 
1. Executive Summary 
1.1 The CIPFA document 'Audit Committee Principles in Local Authorities in Scotland'
highlights that Audit Committees should monitor and review the progress made in
implementing audit recommendations. 
1.2 Service managers are responsible for ensuring that agreed actions arising from
Internal Audit and Corporate Fraud reviews are implemented.  This provides
assurance that identified control weaknesses have been addressed and are being
managed effectively. 
1.3 All actions are monitored on the Pentana system and service managers are
responsible for updating Pentana as they progress each action.  This enables Internal
Audit to monitor progress on a 'real-time' basis and address any delays in
implementation. 
1.4 This report details the position at 31 March 2022. 
2. Background 
2.1 The last report to the Audit and Scrutiny Committee on 8 March 2022 highlighted that
there were 23 actions outstanding at the end of December 2021: four that had not
been started or were only partially implemented and 19 where the due date had not
yet passed.

Page 2

2.2 In addition to these 23 carried forward actions, there have been 12 new actions
agreed, giving a total of 35 action points for review. 
2.3 Services have completed 17 actions since the last report.  All Council Services are
required to retain evidence of work carried out in completing their actions and Internal
Audit carries out 'spot-checks' on a sample of completed actions on an ongoing basis. 
2.4 Of the remaining 18 actions, five were either not started or only partially complete at
31 March and the remaining 13 were not due for completion until after that date. 
2.5 Appendix 1 to this report provides the Committee with full details of the five actions
that were not complete within the agreed timescales. 
3. Proposals 
3.1 It is proposed that the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions; and (b) challenges
those Services that have not implemented actions within the previously agreed
timescales. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The effective implementation of agreed Internal Audit and Corporate Fraud actions
helps to support the efficient delivery of the strategic priorities within the Council Plan
2019-2024. 
Community Wealth Building

Page 3

4.7 None. 
5. Consultation 
5.1 Council Services are consulted during the completion of each Internal Audit and
Corporate Fraud review and have also provided updates on progress made in
implementing action points. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294 324524. 
Background Papers
None.

Page 4

Actions due by 31st March but not started or partially complete 
Code IA2019IJB001c Description HSCP Management should work with officers from East and South Ayrshire
HSCPs to progress the risk sharing arrangements at the earliest opportunity  
Priority 1 Latest Note
The pan Ayrshire work on Directions, including lead partnership arrangements is
still paused as a result of service pressures from COVID.   The plan is to now
have these embedded in by December 2022.
Progress Bar  Original Due Date 30-Sep-2019 Due Date 31-Mar-2022
Parent Code & Title IA2019IJB001 IJB Lead Partnership Arrangements
Managed By Caroline Cameron
Assigned To Caroline Cameron  
Code IA2019IJB001d Description
HSCP Management should work with officers from East and South Ayrshire
HSCP’s to progress the fair share methodology at the earliest opportunity,
including developing detailed Directions with commissioning plans  
Priority 1 Latest Note
The Pan Ayrshire work on Directions, including fair shares and set aside,
remains paused due to service pressures arising from the pandemic.   This and
other elements of the Directions work will be completed by December 2022.
Progress Bar  Original Due Date 31-Mar-2019 Due Date 31-Mar-2022
Parent Code & Title IA2019IJB001 IJB Lead Partnership Arrangements
Managed By Caroline Cameron
Assigned To Caroline Cameron

Page 5

Code IA2020PA032a Description
Audit Action: Arran should be aligned with the mainland’s processes and
procedures.
Audit Finding: Staff on the mainland and Cumbrae are managing the interment
process electronically, whilst staff on Arran continue to use manual records.
Risk: Business continuity issues due to operating a completely separate system
on Arran; manual records are not backed-up in the same way that electronic
records are.  
Priority 2 Latest Note
We have a quote now from the software provider to upgrade the software to the
remote option.  We have passed the quote to IT to check it suits requirements
and what paperwork is required from them regarding data protection etc.  Arran
will be included in this. Fiona Porter has requested an update from IT regarding
the suitability and requirements of the quote from the software provider.  Target
date for completion is 31st July 2022.
Progress Bar  Original Due Date 31-Mar-2021 Due Date 31-Mar-2022
Parent Code & Title IA2020PA032 Bereavement and Burial Services
Managed By Thomas Reaney
Assigned To Mark McNeil

Page 6

Code IA2021PA009b Description
Audit Action: The team should liaise with the Transformation team to streamline
this part of the process and reduce the number of times the same information
must be keyed.
Audit Finding: The admin team are required to update the budget monitoring
spreadsheet, an operational access database and the CareFirst system at each
stage of this process for all council tenant jobs. In addition, the access database
is not supported by IT Services.
Risk: Inefficient use of staff time and increased risk of keying errors.  
Priority 2 Latest Note A draft standard operational spreadsheet has been created and is now being
tested.  It is planned to complete the action by 6th June 2022.
Progress Bar  Original Due Date 31-Dec-2021 Due Date 31-Mar-2022
Parent Code & Title IA2021PA009 Aids and Adaptations
Managed By David Thomson
Assigned To Lynn Kirkland

Page 7

Code IA2021PA013a Description
Audit Action: The current user manuals/training documents for the key areas
should be reviewed and adapted to include the Council’s internal process to
provide a compete user manual. 
Audit Finding: User manuals have not been updated since 2014/15 or no date
is noted. Also, although these documents provide a basic step by step flow of
system processes, they have not been adapted to include the Council’s internal
processes. 
Risk: Manual is out of date and incomplete.  
Priority 2 Latest Note
Significant work has been carried out in the quarter of 2021/22 to ensure a
timeline is in place to complete the action by Sept 30th 2022.
Internal Audit have been made aware of the slippage and agreed an extension.
This action will be completed by 30th Sept 2022 or before. 
Progress Bar  Original Due Date 31-Mar-2022 Due Date 31-Mar-2022
Parent Code & Title IA2021PA013 Building Services Systems
Managed By Yvonne Baulk
Assigned To Leigh-Ann Mitchell; Jim
Smith