NORTH AYRSHIRE COUNCIL 
31 May 2022 
Audit and Scrutiny Committee 
Title:    Accounts Commission’s Report: Local Government in
Scotland: Financial Overview 2020/21 
Purpose:  To inform the Audit and Scrutiny Committee of the findings of
the recently published report. 
Recommendation:  That the Committee i) notes the findings of the recent Accounts
Commission report, and (ii) notes the current position of North
Ayrshire Council in relation to the findings. 
1. Executive Summary 
1.1 The Accounts Commission published its 2020/21 financial overview of local
government in Scotland in March 2022. The report provides a high-level independent
analysis of the financial performance of local authorities during 2020/21. A link to the
report is attached below;  
Local Government Financial Overview Report 
1.2  The report analyses the annual accounts produced by local authorities, together with
the reports of each body’s external auditors, to identify their relative performance,
highlight the challenges faced and assess their responses to these challenges. The
report has a summary of key findings with more detail provided in four parts; 
• Part 1 - Councils’ income in 2020/21;
• Part 2 - Councils’ financial position in 2020/21; and
• Part 3 - Councils’ financial outlook. 
1.3  Appendix 1 provides Council relevant feedback on each of the key messages
identified. 
2. Background 
General Fund 
2.1 The report provides a high-level independent analysis of the financial performance of
local authorities during 2020/21 and their financial position at the end of that year

Page 2

2.2  A summary of the key messages is provided within the report with further information
provided in 3 main sections: 
• Part 1 - Councils’ income in 2020/21;
• Part 2 - Councils’ financial position in 2020/21; and
• Part 3 - Councils’ financial outlook. 
2.3 The key messages for Councils are summarised below: 
• Councils received an additional £1.5billion in Scottish Government funding to
address the impacts of the Covid-19 pandemic; 
• There has been an underlying real terms reduction in local government funding of
4.2% since 2013/14; 
• More than half of all additional funding received during 2020/21 was ringfenced to
support the delivery of Scottish Government policies, removing local discretion over
how these funds could be used; 
• Council income from customers and clients reduced by £0.5 billion as a result of
Covid-19 restrictions; 
• All Councils increased their usable reserves as a result of late Covid-19 funding
which was unspent at 31 March 2021; 
• Councils administered £1.4 billion of Covid-19 grants on behalf of the Scottish
Government, putting additional pressure on Council staff; 
• Capital expenditure reduced by more than 20% as a result of Covid-19 restrictions;
and 
• Covid-19 pressures contributed to greater and more frequent errors in Councils’
unaudited accounts. 
2.4 In addition, the report identifies a number of issues in relation to the medium and
longer term outlook for local government finances, including: 
• Scottish Government capital funding to Councils is expected to fall in 2021/22; 
• Uncertainty over Covid related funding during 2020/21 led to difficulties in setting
2021/22 budgets; and 
• Covid-19 resulted in revised medium term plans but longer term financial plans will
need to be updated as the uncertainties arising from Covid-19 diminish. 
2.5 An update on the position for North Ayrshire Council is noted below: 
• The impact of Scottish Government funding in relation to both the impact of Covid-
19 and underlying Council funding is summarised in part 1 of appendix 1;

Page 3

• Council reported £66m of General Fund Usable Reserves at 31 March 2021. This
was an increase of £31.5m as detailed in part 2 of appendix 1; 
• During 2020/21 the Council administered £40m of business grants plus a further
£14.8m of Non Domestic Rates Covid related reliefs on behalf of the Scottish
Government; 
• The rephasing of £26.4m of Capital projects as a result of Covid related restrictions
was reported to Council during 2020/21; 
• The annual report of the Council’s external auditors was presented to the Audit and
Scrutiny Committee on 27 September 2021. This report identified no materials
issues or errors in the unaudited accounts;   
• Council approved the Capital Investment Programme 2022/23 to 2030/31 on 2
March 2022 which outlined the Council's investment plans and assumed levels of
capital funding for the next nine years. This included assumed General Capital
Grant funding of £9.8m each year; 
• Council approved the General Services Revenue Estimates 2022/23 to 2024/25 on
2 March 2022 which provided Members with an overview of the Council's
anticipated financial position on the General Fund revenue budget for the next
three financial years and confirmed an additional investment of £1.7m to develop
an energy based community support model to provide sustainable support to
residents; and 
• The Long Term Financial Outlook 2021/22 to 2030/31 was approved by Council on
16 December 2020 and provides the cornerstone of the Council’s strategic financial
framework and establishes a sound basis for the development of the Council’s
medium term financial plans and annual budgets. This is scheduled for a full review
during 2023/24. 
3. Proposals 
3.1 It is proposed that the Committee i) notes the findings of the recent Accounts
Commission report, and (ii) notes the current position of North Ayrshire Council in
relation to the findings. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Accounts Commission report highlights the reliance of local government on
Scottish Government grant funding and the need for the development of robust
medium and longer term financial plans to develop sustainable solutions to support
recovery following the Covid-19 pandemic and bridge the anticipated funding gap.
North Ayrshire Council develops medium term financial plans on a three year rolling
basis and Council has approved a Long Term Financial Outlook covering the next 10
year period. The financial sustainability of the Council, including the impact of the
Covid-19 pandemic, is monitored regularly and reported to Cabinet throughout the
year.

Page 4

Human Resources 
4.2 As part of a sustainable financial strategy the Council continues to actively manage the
size of its workforce. Regular communication and consultation takes place with the
workforce and Trade Unions. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 Equality impact assessment are carried out for all options identified as part of the
medium and long term financial plans. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 In addressing the financial challenges which it faces, the Council seeks to minimise the
impact on delivering its key priorities. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Executive Directors are consulted in the development of the Medium and Long term
Financial plans and the development of investment and recovery and renewal
strategies. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551 or DavidForbes@north-ayrshire.gov.uk. 
Background Papers
None

Page 5

Appendix 1
Local Government in Scotland Financial Overview 2020/21 
Part 1 Councils’ Income on 2020/21 
Ref Key Message NAC Feedback
I1 The Covid-19 pandemic persisted throughout 2020/21, with
the Scottish Government increasing funding to councils by
£1.5 billion to support them in dealing with the impacts of
the pandemic. 
In 2020/21 NAC received £29.4m additional General
Revenue funding and £4.5m additional specific revenue
grants in relation to Covid pressures.
I2 The underlying increase in Scottish Government funding to
councils of £358 million in 2020/21 was 1.1 per cent in real
terms. But, over half of this increase is due to specific
grants, which are now £710 million. Ring-fenced funding
helps support delivery of key Scottish Government policies,
such as expanding early learning and childcare services,
but constrains a proportion of the total funding and
resources and removes any local discretion over how these
funds can be used by councils. 
During 2020/21 the level of non Covid related Scottish
Government funding received by NAC increased by £15.9m,
equivalent to a 1.0% reduction in real terms. £5.6m of this
increase was due to additional specific grants, primarily in
relation to the expansion of Early Learning and Childcare.
I3 When Covid-19 funding is excluded, there has been a real
terms underlying reduction in local government funding of
4.2 per cent since 2013/14.
Between 2013/14 and 2020/21 the level of non Covid
related Scottish Government funding received by NAC
increased by £34.3m. This was equivalent to a 4.1%
reduction in real terms

Page 6

Part 2 Councils’ financial position in 2020/21 
Ref Key Message NAC Feedback
P1 Savings plans were mostly delivered across councils, but
with significant variation.
The 2020/21 General Services Revenue Estimates
included savings targets of £4.439m across all services.
Although the majority of savings were delivered in year,
several were impacted by the Covid-19 pandemic. These
were offset by other underspends within the services and
will be further developed once all restrictions are lifted. 
The impacted savings included: Review of Facilities
Management in Schools £0.155m; Property Rationalisation
£0.140m; increased fee income linked to the Capital
Programme £0.093m; increased factoring income
£0.119m; and other minor savings £0.097m.
P2 All councils increased their usable revenue reserves,
mainly due to late Covid-19 funding which was unspent at
31 March 2021. The total increase was £1.2 billion
Total General Fund Reserves increased by £31.5m
between 2019/20 and 2020/21, including £17.9m of Covid
related funding, £8.0m of commitments delayed because
of Covid related restrictions and £2.5m of agreed
investment in recovery and renewal programmes.
P3 Capital expenditure reduced by more than 20 per cent in
2020/21 due to Covid-19
The total value of General Fund capital projects rephased
during 2020/21 as a result of Covid restrictions was
£26.4m, 33% of the original planned expenditure.
P4 Councils administered a further £1.4 billion of Covid-19
grants on behalf of the Scottish Government. The need to
administer payment of these grants quickly to support the
local economy put additional pressure on finance staff
across councils.
NAC administered £40m of business grants during
2020/21, plus a further £14.8m of Non Domestic Rates
Covid related reliefs. 
Several sections across the Council were involved in the
administration of these grants, including Revenues, Legal
and Business Development. Where additional funding for
administration was provided by the Scottish Government,
the timescales involved did not allow for the recruitment or
training of additional staff.

Page 7

P5 Covid-19 pressures contributed to greater and more
frequent errors in councils’ unaudited accounts. Auditors
also reported wider issues relating to Covid-19, including
the slowing of progress in some councils’ transformation
plans, the impact of reduced income on arm’s-length
external organisations (ALEOs) and what that means for
their financial sustainability, identified weaknesses in
internal control systems, and adverse impacts on long-
term planning and capacity.
No material errors were reported in the NAC annual
accounts for 2020/21 which were completed and audited
within statutory timescales. However, a number of
adjustments were required to the accounts during the audit
phase as a result of late or incomplete guidance from the
Scottish Government and Audit Scotland in relation to the
treatment of Covid related issues including mobilisation
funds provided to the IJB and PPE provided to the Council
by the NHS. 
KA Leisure reported significant reductions in income for
the year resulting a trading deficit of £1.9m. A detailed
financial recovery plan, including the provision of additional
cash flow support from NAC, was approved by Cabinet in
February 2021. 
P6 In line with the recovery in global stock markets, pension
fund investments performed well. In addition, the triennial
funding position improved
Although the value of returns on pension scheme assets
increased during 2020/21, this was offset by an increase in
the value of pension liabilities linked to inflation
assumptions. This resulted in a net increase in NAC’s
share of the Scheme’s liabilities of £58.5m for the year. 
Part 3 Councils’ Financial Outlook 
Ref Key Message NAC Feedback
O1 Uncertainty over the amount of funding available for Covid-
19 recovery at the end of 2020/21 led to difficulties in
setting budgets, and many councils established updated
Covid-19 budgets in autumn 2021.
.
£16.9m of additional Covid related funding was confirmed
on 18 March 2021, after Council had approved the
2021/22 budget. These funds were not recurring and
would not have been available to offset savings
requirements. However, the majority of funds could not be
expended before the end of the financial year and were

Page 8

earmarked to support ongoing Covid Recovery and
Renewal and Investment activities in 2021/22 and beyond. 
O2 Initial Scottish Government revenue funding in 2021/22
has increased by 1.1 per cent in real terms
Following confirmation of funding in relation to the Council
Tax freeze in 2021/22, the level of Scottish Government
funding for NAC increased by £7.2m, 2.4%. However, the
increase in core funding, excluding specific grants and
Scottish Government policy commitments was only £2.5m,
0.9%. 
O3 Covid-19 resulted in revised medium-term financial plans,
but longer-term planning will need to be updated as Covid-
19 uncertainty diminishes
NAC’s Long Term Financial Outlook was presented to
Council in December 2020. This is the cornerstone of the
Council’s strategic financial framework and identified an
estimated funding shortfall of £120m over the next ten
years based on best estimates with sensitivity analysis
highlighting the implications of changes to the underlying
assumptions. 
The Long Term Financial Outlook is scheduled for a full
review during 2023/24. 
O4 Scottish Government capital funding in 2021/22 is
expected to fall again. This may have a significant adverse
impact on councils’ investment plans
Excluding ringfenced funding in relation to Flooding
projects, NAC’s General Capital Grant was reduced by
£0.140m, 1%, in 2021/22 and a further £0.022m in
2022/23. 
However, this has been offset by additional ringfenced
capital funding linked to Scottish Government manifesto
commitments including Play Park Renewal and Local
Bridge Maintenance.

Page 9

O5 The long-term funding position for councils remains
uncertain, 
with significant challenges ahead as councils continue to
manage and respond to the impact of Covid-19 on their
services, finances and communities.
NAC approved the 2022/23 to 2024/25 Medium Term
Financial Plan on 2 March 2022. This identified indicative
budget gaps for 2023/24 and 2024/25 of £10.7m and
£8.8m respectively. 
The Long Term Financial Outlook 2021 -2031 has
identified an estimated shortfall of £69m over the period
2025/26 to 2030-31. This is scheduled for a full review
during 2023/24. 
Additional funding received as a result of Covid-19 has
been retained for investment across Education, KA
Leisure, the HSCP and the general Recovery and Renewal
programme to address the long term impact of Covid-19
on the Council and our communities. 
O6 In the longer term, uncertainty creates challenges for
councils as they seek to address cost and demand
pressures that existed before the impact of Covid-19, as
well as develop long-term plans with their partners to
address complex issues such as child poverty and
inequalities, to improve economic growth and to deliver
Scotland’s net zero ambitions
Work continues across NAC to develop the Council’s long
term plans. This is supported by earmarked reserves and
investment funds approved by Council in relation to
financial insecurity, recovery and renewal and
sustainability, including a £1.7m non-recurring investment
approved by Council to develop an energy based
community support model to provide sustainable support
to residents.