NORTH AYRSHIRE COUNCIL 
31 October 2024 
Audit and Scrutiny Committee
Title: Strategic Risk Register 2024/25: Mid-year Update
Purpose: To provide the Audit and Scrutiny Committee with an
update on the progress with actions related to the Strategic
Risk Register.
Recommendation: That the Committee notes the mid-year update on the
2024/25 Strategic Risk Register. 
1. Executive Summary 
1.1 The Council’s most significant risks are identified through the Strategic Risk
Register, which is refreshed annually and was last approved by Cabinet in
March 2024. 
1.2 This report, together with Appendix 1, demonstrates progress made by the
Council in mitigating against the potential impact of the strategic risks. 
2. Background 
2.1 The Council’s most significant risks are identified through the Strategic Risk
Register, recognising the challenges facing the Council within the current
financial year and demonstrating the arrangements in place for managing those
risks. 
2.2 The Strategic Risk Register is refreshed annually and was last approved by
Cabinet in March 2024; thereafter it was reported to the Audit and Scrutiny
Committee in May as this Committee has a remit for monitoring key risks. 
2.3 The register is attached at Appendix 1 and provides an update on that approved
by Cabinet in March. The next full refresh of the risk register will take place
early in the new year, to be taken to Cabinet for approval in March 2025 and
thereafter reported to the Audit and Scrutiny Committee. 
2.4 Where relevant, key actions from the Council Plan have been linked to the risks
and progress shown at the end of September. These actions are more strategic
in nature. Some risks are managed as ‘Business as Usual’, through the
appropriate operational plans within Services or through current controls. 
2.5 Of the eight strategic risks presented to Cabinet in March two have increased
in scoring. Inequalities has increased from 16 to 20 due to increasing risk
proximity factors around Community Asset Transfer.  Financial Sustainability of
the Health and Social Care Partnership has also increased from 16 to 20 as a
result of increasing financial pressures on the partnership.

Page 2

Very High Risks 
2.6 There are five strategic risks classed as ‘Very High’ (scoring 17-25):
Financial Environment (risk score 20) – this risk reflects the ongoing financial
challenge faced by the Council. 
Inequalities (risk score 20) – this highlights the socio-economic inequalities
faced in North Ayrshire. 
Financial Sustainability of the Health and Social Care Partnership – this
reflects the ongoing financial challenges faced by the Partnership and the risk
these present to the Council (risk score 20 - up from 16 in March 2024). 
Property Asset Risk – This reflects the impact of long-term restricted budgets
on the Councils ability to maintain these to a good standard (risk score 20). 
Community Capacity Building and Empowerment – this highlights the
challenges associated with community empowerment (risk score 20 – up from 16
in March 2024). 
High Risks
2.7 There are three strategic risks classed as ‘High’ (scoring 10-16):
Cyber Security (risk score 16) – this reflects the ongoing risk from external
cyber-attack which is being faced by all organisations.
Climate Change (risk score 16) – this risk has been on the Strategic Risk
Register following the declaration by the Council of a Climate Change
Emergency during 2019. 
Transformation (risk score 12) – this reflects the wider risks associated with
delivering the current Transformation Programme and developing a pipeline of
future initiatives. 
Longer-term risks and horizon scanning
2.8 The Strategic Risk Register identifies the most significant risks which the
Council faces at the present time. 
2.9 The Corporate Risk Management Group identifies any new relevant risks
though internal reviews and external horizon scanning utilising a number of
sources. 
3. Proposals 
3.1 It is proposed that the Committee notes the mid-year update on the 2024/25
Strategic Risk Register. 
4. Implications/Socio-economic Duty
Financial
4.1 The Council continues to have a robust long and medium-term financial
planning framework. Key strands include development of key transformation

Page 3

themes and the establishment of an Investment Fund that will generate future
savings alongside delivery of a number of key Council priorities.
Human Resources 
4.2 None. 
Legal
4.3 None.
Equality/Socio-economic
4.4 The risk to the Council is that North Ayrshire residents, and in particular certain
groups, will experience increasing levels of poverty and its effects. Current
control measures fall into two categories - measures to address the root causes
of socio-economic inequalities - income through employment or benefits – and
mitigation measures to minimise the impacts of poverty. 
Climate Change and Carbon 
4.5 The Council has declared a climate change emergency and has in place an
Environmental Sustainability and Climate Change Strategy. Significant work to
help mitigate the risk of flooding is included within the Capital Plan. The Council
is undertaking an ambitious renewable energy programme. 
Key Priorities 
4.6 A successful risk management framework helps to underpin the delivery of the
Council’s strategic priorities in the Council Plan 2023-2028.
Community Wealth Building
4.7 The Council has an ongoing commitment to community empowerment and
locality partnerships, together with an enabling approach with community
partners and support with third sector interface to build capacity and identify
opportunities for growth and sustainability. 
5. Consultation 
5.1 The Strategic Risk Register has been reviewed in consultation with the
Executive Leadership Team. 
Mark Boyd
Head of Service (Finance) 
For further information please contact John McCallum, Senior Manager (Audit,
Fraud, Safety, Risk & Insurance), on 01294 324607. 
Background Papers
None

Page 4

Appendix 1 - Strategic Risk Report 2024/25 
Risk Code SRR2425_R01 Risk Title Financial Sustainability Latest Note Date 11-Sep-2024
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The risk is that the level of funding from Scottish Government
to local government falls significantly below the level required
to operate services effectively. This will require the Council to
take increasingly difficult and challenging decisions. The
revised 2024/25 local government settlement represents a
reduction in core funding of £0.5m (0.15%). This is against a
backdrop of significant inflationary cost increases and risks. 
The North Ayrshire position is further affected by a reducing
overall population demographic and a growing elderly
population. This will further impact the Council’s share of
funding across the short, medium and long term.
Although there is a commitment through the Verity House
agreement for Councils and Scottish Government to work
together there continues to be challenges around the level of
flexibility the Council has on key areas of Budget, most notable
in areas like HSCP funding and funding for teachers and
support staff, where conditions remain. In 2024/25 in-year cost
pressures across the Council’s General Fund and the Health
and Social Care Partnership present a significant risk to the
sustainability of the Council’s finances. The General fund
currently projects an in-year overspend of £2m and the HSCP
projects a £6.5m overspend. The Scottish Government has
passed legislation to give Councils powers to charge additional
council tax for second homes. This is an area the Council will
consider within the context of local circumstances and island
communities.
Scottish Government funding to support the Council’s capital
programme has also been reduced by almost 10% in the
Budget settlement for 2024/25. Set against high inflationary
driven construction costs there is a risk that the 10-year capital
programme will be unaffordable. This could require projects to
be reduced in scale or even ceased.
Funding not keeping pace with demand
and inflationary cost pressures means that
there will be a reduction in some service
areas potentially resulting in higher risks for
service users. The future delivery of
balanced budgets will become increasingly
challenging. The capital programme could
also be significantly impacted leading to
reduced levels of capital investment.
Robust monitoring of the Council’s revenue and
capital budgets is in place as well as regular
reporting of financial performance of the IJB to
Cabinet and Audit and Scrutiny. 
To assist financial planning The Medium and Long-
Term Financial Outlook (LTFO) to 2033/34 was
approved at Council on 13 December 2023 – this is
the cornerstone of the Council's financial planning in
the medium to long term. 
The annual budget process for the General Fund
revenue and Capital Programmes and financial
performance monitoring process will continue to
provide the framework from which control measures
will continue in addressing the financial position.
Delivery of the Council’s Change Programme is also
vital in addressing the Budget challenges and this is
being progressed by the Council’s Transformation
Board, which is chaired by the Chief Executive.
Utilising the Council’s available statutory powers is
another important area in addressing the financial
challenges.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Increasing Risk 20

Page 5

Strategic Risk Action Plan Date Updated 11-Sep-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Regular financial monitoring of Revenue and Capital Budgets.
09 February 2024:
Ongoing monitoring. 
11 September 2024:
Ongoing financial monitoring process across capital and revenue, including
identification of measures to address in-year position
31-Mar-2025 Mark Boyd 
Maintain Financial Governance Arrangements for IJB.
09 February 2024:
Under ongoing review.
11 September 2024:
New Finance Working Group set up to address in-year and medium-term
pressures. Includes representation from the HSCP, Health and the Council,
Main focus is on development of a finance recovery plan.  
31-Mar-2025 Mark Boyd 
Progress dialogue via COSLA with Scottish Government on a range of
areas including fair funding, multi-year settlements, reduction in levels of
ring-fenced resources, true costs of SG policy areas, financial flexibilities
and a New Deal partnership with SG and local government.
09 February 2024:
Ongoing discussions via COSLA around the Verity House Agreement and the
need for maximum financial flexibility for Councils.
11 September 2024:
Discussions ongoing, however, SG have just announced £0.5Billion of cuts
Further dialogue being progressed around teacher number restrictions and
areas of revenue generation. 
31-Mar-2025 Mark Boyd 
Develop the 2025/26 to 2027/28 revenue budget (medium-term financial
strategy) and capital programme taking account of all pressures and
savings via Directorates and Transformation programme.
09 February 2024:
Options to address the £16m Budget gap for 2024/25 have been developed
for elected member consideration at Council Meeting on 28 February 2024.
Following this, require to develop a more detailed programme of options to
address the structural funding challenges over the medium and long-term.
11 September 2024:
The 2025/26 Budget process has commenced earlier, in view of the current
financial challenges. Special Council meeting arranged for 9 October, 2024 to
set out the financial outlook and outline initial proposals as part of a
community engagement programme to commence from 10 October, 2024.
26-Feb-2025 Mark Boyd

Page 6

Risk Code SRR2425_R02 Risk Title Inequalities Latest Note Date 19-Sep-2024
Risk Owner Caroline Cameron; Sam Anson; David Hammond
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
North Ayrshire residents, and in
particular certain excluded
groups, will experience
increasing levels of poverty and
its effects, as a result both of the
economic situation and further
public sector funding
challenges.
Health inequality is closely
linked to poverty, employment
and people's earliest
experiences as children, and will
increase.
The population of North Ayrshire
is projected to fall over the next
10 years but there will also be a
larger proportion of the
population considered
dependent (not economically
active).
The impact on specific risk
groups is greatest for our
children, young people and
families, unemployed people
and those in in-work poverty
and people exposed to the
risks of drug and alcohol
addiction.
Demand for HSCP and
Council Services will
increase.
As reductions in resources
increase, early intervention
and prevention activities are
at risk, thus increasing the
potential for an increase in
costly crisis interventions.
The local economy will be
impacted by reduced
spending power by
economically inactive
residents.
The HSCP re-affirmed its commitment to Tackling Inequalities by continuing to consider it a key priority with the
Partnership’s Strategic Plan.
Through the HSCP strategic plan, the Partnership sets out actions to tackle inequality through its Partnership Pledge and
across its strategic priorities. Tackling inequalities is addressed across HSCP service areas. An example of actions to
help address local inequalities include:
Establishing the Money Matters service in 9 GP practices and 7 local schools in the more deprived areas of North
Ayrshire. This will improve accessibility of the service to those who would benefit most. Building on this approach through
the launch of the Financial Inclusion Partnership bringing a range of key partners and stakeholders together to improve
access and support for the most vulnerable NA residents.
Increase the number of employability mentors in Justice Services, to support those with experience of the justice service
into meaningful employment or training opportunities and to help divert away from criminal behaviours.
Working closely with Housing colleagues to support transitions from care and ensuring care experienced young people
can access a positive and stable housing destination.
In our Drug and Alcohol Services, we are implementing actions to reduce the number of local drug and alcohol related
harms and deaths. This includes implementing the national MAT (Medicated Assisted Treatment) standards and
increasing the number of ABIs (Alcohol Brief Interventions) delivered across North Ayrshire.
Through the Caring for Ayrshire programme, we have set out a phased approach to improve local primary care premises
(GP Practices and Health Centres). This will improve overall professional capacity within GP practices for Multi-
Disciplinary Teams, ensuring the right support is available for local people with health concerns.
Investment in early intervention teams and approaches in Children’s Services to support vulnerable families, including in
Child Protection and Whole Family Support.
The Council considers reducing inequalities to be at the heart of its work.
The Communities & Housing Directorate leads the Community Planning Partnership for the Council and the CPP has
recently developed a new Local Outcomes Improvement Plan, the purpose of which is reducing inequalities. The themes
are Wellbeing, Work and World, the latter addressing climate change and fuel poverty. Locality Planning priorities and
Community Investment Fund funded initiatives are also focused on a range of inequalities, including poverty, age-related
inequalities and digital inequalities. Recent CIF-funded projects have focused on employability, addictions and community
food.
Sam Anson, Executive Director (Education) and David Hammond, Executive Director (Communities & Housing) lead the
work of the Child Poverty and Cost of Living Board, chaired by the Council Leader. The five strategic themes of the Board
to date have been:
• No Wrong Door – access to services
• Employability
• Food
• Islands
• Childcare 
Work to address child poverty and the Cost-of-Living crisis includes a range of employability initiatives to support parents
and people with disabilities, each of whom are Scottish Government priority groups.
Progress has been made with partners to undertake a review of the Child Poverty & Cost of Living approach, with
recommendations being finalised for consideration by the Board.. This is supported by the data and Single Shared
Assessment projects being developed by the Transformation team, to provide holistic support for residents who need it
most. Confirmation was received in September 2024 that the Council will be supported with additional Scottish
Government funding for Fairer Futures project funding which will enable the creation of three additional posts to provide
strategy capacity to support the CPCOL Board.
The Child Poverty Early Intervention Fund is being used to address gaps in current planning and provision. Recent
funding decisions have been made, as a consequence of the mini-enquiries - to support employability and travel,
childcare developments and support for care experienced young people and families. Further allocations are currently
under consideration with the Board. 
The Scottish Government has provided a second year of funding to address inequalities on the islands. This has been
used to fund energy support, welfare advice and support, third sector interventions and school activities.
The commitment to reducing inequalities is also reflected in the following plans:
5 4

Page 7

• The Educational Service Improvement Plan
• Connected Communities strategic plans and
• Facilities Management plans.
Examples of actions to reduce inequalities:
• Deployment of Scottish Attainment Challenge funding to reduce the poverty related attainment gap in schools
• Use of the Pupil Equity Fund to ensure equity of pupil experience in schools, at the discretion of head teachers
• Cost of the School Day actions to reduce, for example, the cost of school uniforms and clothing, food and outings
• Support for care experienced young people, both in schools and through youth services
• Additional national and local investment in Active Schools to focus on inequalities and equity
• The Fairer Food Network, with 14 community larders which support the needs of individual communities
• A network of warm spaces and events to mitigate energy use and social isolation
• Work to support “New Scots,” in schools, with families and in community settings through language support and
capacity building, including women’s groups
• LGBT support groups for young people and those over 18
• Mentoring support for young people in secondary schools through a partnership with MCR Pathways
Participation strategies for children and young people and adults to ensure our strategies and investment are informed by
as wide a range of views as possible.
Status Risk Score
Heat Map 
Change in Score Approach
No Change Treat
Stable 20

Page 8

Strategic Risk Action Plan Date Updated 19-Sep-2024 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Global and national conditions which affect the cost-of-living and poverty continue
to undermine the effectiveness of local control measures. Substantial work
continues to mitigate inequalities but child poverty data, for example, continues to
show an increase. National data collection methodologies have changed which
explains the change in part, but North Ayrshire continues to have c. 29% of
children living in poverty.
Although unemployment has reduced, it continues to be a driver of poverty, with
in-work poverty a key factor.
Access to benefits is a key driver of poverty and the range of strategies described
above continues to ensure we are maximising access to entitlements. The Single
Shared Assessment work will improve this.
19 September 2024:
The wide range of strategies and initiatives described above,
being further developed and implemented, is anticipated to make
a significant contribution to a range of inequalities. The review of
the CPCOL Board, Child Poverty & Early Intervention Fund, Fairer
Futures funding, and single shared assessment project are
designed to help ‘shift’ the dial in tackling inequalities.  
Actions are being progressed and remain within the target dates
for completion.  
31-Mar-2025  Caroline Cameron

Page 9

Risk Code SRR2425_R03 Risk Title Financial Sustainability of the Health and Social Care Partnership Latest Note Date 18-Sep-2024 
Risk Owner Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Resources have not kept pace with the demand for and
cost of social care services. The budget settlement for
2024-25 is extremely challenging with a gap of over
£10m across the IJB. Financial modelling suggests
significant ongoing challenges across the medium-term.
There is no certainty around future funding against
growing demand, increasing costs and demographic
pressures, with one-year budget settlements remaining
in place.
The ongoing work to review the Integration Scheme and
to develop new risk-sharing arrangements between the
Council and Health Board in relation to the acute set
aside and primary care prescribing present a financial
risk to the Partnership.
The Partnership is projecting an overspend of £6.7m in
2024/25, reduced to £3m following the identification of
cost reduction measures and the utilisation of the
remaining general balance of £0.357m.
Funding levels could result in
savings being made that are not
in alignment with the strategic
plan. This could impact on the
future demand levels e.g.
reduction in early intervention
and prevention means that
future demand is increased. 
An in-year overspend position
impacts on financial reserves
and ultimately poses a financial
risk to the Council and NHS
Board as funding bodies. 
Funding levels increase the
requirement to transform
services at scale and pace.
The IJB actively monitors the financial position with regular detailed
reporting. Directors of Finance of the Council and Health Board have
oversight and regular updates are provided to the Council's Cabinet.
There is an integrated approach to managing the totality of NHS and
Council resources delegated to the IJB. A three-year Medium-term
Financial Outlook is updated on a rolling basis each year.
Previous financial settlements have seen both partners meet the
Scottish Government settlement conditions with any additional
resources passed to the IJB.
The Partnership has developed a new 3-year Transformation Plan
2024-2027 which will be approved by the IJB in March 2024. There is
£2.2m of earmarked reserves set aside to support service change and
re-design.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
Increase from 16 to 20 Treat
Increasing risk 20

Page 10

Strategic Risk Action Plan Date Updated 18 Sep-2024 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Budget Monitoring - Regular budget monitoring reports to IJB are effective. 
06 February 2024:
Budgets are closely monitoring by the finance team in conjunction
with budget holders to enable corrective action to be taken and
regular in-year budget monitoring reports are presented to the
IJB.
18 September 2024:
Strengthen support from Finance Team to front line services and
increased engagement with Heads of Service and Senior
Management Teams, including line by line reviews of all budget
areas. Review and enhancement of frequency and level of
financial information provided to support oversight and decision
making in line with financial constraints, with an added focus on
areas of underspend to maximise opportunities to delay or stop
spend and contribute to the overall financial challenge.
31-Mar-2025
Caroline
Cameron;
Paul Doak 
Corrective Action – Transformation Board is effective  
06 February 2024:
A three-year Transformation Plan covering the period 2024-2027
will be approved by the IJB in March 2024. This focusses on
addressing the future financial challenge in a sustainable way, as
well as reviewing service delivery models and implementing local
and national priorities.
18 September 2024:
A three-year Transformation Plan covering the period 2024-2027
was approved by the IJB in March 2024. This focusses on
addressing the future financial challenge in a sustainable way, as
well as reviewing service delivery models and implementing local
and national priorities. 
31-Mar-2025
Caroline
Cameron;
Paul Doak 
Enhanced Financial Controls
18 September 2024:
Establishment of a Budget Working Group to facilitate increased
oversight and scrutiny of the financial position and transformation
programme as well as detailed budget planning for future financial
years. The first meeting took place on 9th September.
Review of expenditure authorisation levels across the Partnership
and escalate specific decisions to senior officers.
Staff communication in relation to discretionary/non-essential
spend.
Review of temporary posts and robust vacancy
management/approval – only essential frontline posts will be
approved for recruitment.
Strengthen across services the existing approval and prioritisation
approaches for new care requests, which will be approved in line
with resource availability. A new group has been established to
sign off all higher value care packages (Over £40k)
31-Mar-2025
Caroline
Cameron;
Paul Doak

Page 11

Risk Code SRR2425_R04 Risk Title Cyber Security Latest Note Date 13-Sep-2024 
Risk Owner Fiona Walker
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The potential compromise of business operations or a
data breach orchestrated via either digital channels or
the IT infrastructure. This can include targeting of the
user base. Risk derives from both Council operations
and those of its supply chain. 
The increasing importance of delivering services through
digital channels and maximising efficiency through
effective and secure use of technology. This includes a
growing adoption of cloud-based computing resources
which extend processing capabilities, and associated
risks, beyond the Council’s network. 
Hybrid remote and mobile working is now the normal
working practice for over 3,000 staff. Such a distributed
work force increases the complexity of protecting against
cyber and data protection risks. 
Failure by Services to adopt and comply with
strategies, policies and procedures may result
in a failure to adequately ensure the desired
levels of cyber-security required to maintain
and protect council systems and data. 
There may be a significant impact on the
authority through the release of personal
and/or sensitive information resulting in a loss
of public confidence and significant financial
loss incurred through fines and service
disruption. 
A successful cyber-attack (malicious external
or internal action) on the Council’s IT
environments could also result in significant
service disruption, loss of income streams
and possible data loss/exposure. 
Impacts of a cyber-attack could include
economic (i.e. inability to collect online
payments), societal disruption (i.e. loss of
diaries and client appointments), and
reputational damage (i.e. loss of public
confidence in digital services).
It is recognised that it is not possible for any
organisation to expect to be completely protected
against continually evolving cyber threats. A threat
actor with sufficient motivation, resource and capability
will be able to compromise the most secure system. 
The Council takes a sociotechnical approach to
reducing risk by continually developing protective
measures through technical, organisational and
people-focused controls. 
Technical controls are implemented in areas such as
network defences, secure configuration of systems,
user authentication, malware protection, and
vulnerability management. These are based on best
practice and independently tested on an annual basis
to confirm their effectiveness in accordance with
compliance schemes. 
The Council maintains a comprehensive set of policies,
standards, guidelines, metrics and reporting
mechanisms as part of its information security
governance structure. A comprehensive training and
awareness programme is delivered to nurture a cyber-
aware workforce and culture.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 12

Strategic Risk Action Plan Date Updated 13-Sep-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Incident Detection and Response – Recent cyber-attacks on public
sector organisations highlight the need for robust incident detection and
response procedures and technologies. The current response
procedures been shown to be effective based on incidents experienced
so far, however detection capabilities will need to be reviewed and
improved.
17 January 2024:
A joint procurement of a Managed Security Operation Centre (SOC) service with
other local authorities is being taken forward by the Digital Office.  This has
however been delayed due to resource challenges and to date no procurement
timescales have been set.
Given the delays to the national SOC procurement project, the Council will consider
other SOC alternatives and Manage Detect & Response (MDR) services.
13 September 2024:
Progress on the Digital Office joint procurement exercise has remained extremely
slow, as a result the Council have opted to procure a SOC/MDR service
independently.  The procurement exercise is now progressing. 
31-Mar-2025 Fiona Walker 
Training and Awareness
17 January 2024:
Cyber Security in person training has resumed with multiple sessions being
organised to tackle the backlog incurred due to the pandemic.
The Cyber Security Essentials E-Learning course is a mandatory training
requirement for all staff with access to Council digital resources. Staff are also
encouraged to complete this annually. In addition, the course has been converted
into a briefing to provide as a toolbox talk to reach all of our workforce.
Phishing simulations continued to be hosted to test the effectiveness of training and
raise awareness.
13 September 2024:
Cyber Security training continues to be delivered; however this is now a Teams
delivered course to maximise the attendance numbers.  The Cyber Security
Essentials E-Learning course continues to be available for 2024 and is undergoing
a full re-write for 2025 to ensure this remains current. This training is being
supplemented with a programme of awareness raising initiatives including
educational staff news items and webinars. 
Phishing simulations have continued in order to assess the effectiveness of existing
training and further increase awareness.
Ongoing Fiona Walker

Page 13

Risk Code SRR2425_R05 Risk Title Transformation Latest Note Date 11-Sep-2024
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
There is a risk that transformation and change
activities, which are core to the future delivery
models and long-term financial sustainability of
both the Council and Health and Social Care
Partnership, fail to deliver at the level of scale
and pace required.
Failure to deliver transformational change
will impact on the Council’s financial
sustainability, effectiveness of service
delivery and delivery of the outcomes set
out in the Council Plan 2023-28 and the
Local Outcome Improvement Plan (LOIP). 
Failure to deliver the HSCP
Transformation programmes across the
Partnership, involving North Ayrshire
Council (NAC) and NHS Ayrshire & Arran
(NHSAA) services may lead to the
identified outcomes not being delivered;
resulting in financial instability, reduced
performance, deteriorating patient
outcomes, and reputational damage
within North Ayrshire Health and Social
Care Partnership (NAHSCP). 
Failure to embed cultural transformation
activities may lead to difficulties in
building future workforce capacity and in
ensuring we have an engaged, skilled
and knowledgeable workforce to meet
service demand.
The transformation programme aligns to the Council Plan and is
monitored via the Transformation Board. The Board is chaired by the
Chief Executive.
Workstreams have been developed across Transport and Travel,
Digital, Land and Property assets, Sustainability, Financial Inclusion
as well as ongoing reviews across Waste Services, ELC, Learning
Resources and Housing. 
HSCP have an established Transformation Board to closely monitor
progress with plans, regular updates on programme to the IJB and
regular meetings with the Chief Executive and S95 Officer to review
progress and mitigation plans. Cultural transformation activities
continue to evolve to support the Council’s transformation and
improve effectiveness and capability. This includes sharing learning
and skills, engagement, design experiments and a whole systems
approach to transformation and change. 
Our workforce planning approach utilises a variety of tools and
techniques, such as career development, succession planning,
vacancy management, redeployment and early release schemes to
ensure our workforce requirements for the future, in terms of skills
and capabilities, are planned. Each Head of Service has a workforce
plan, and these are monitored six-monthly with continued HR
support and guidance to ensure service review and redesign of the
workforce is on track.
3 4
Status Risk Score
Heat Map  
Change in Score Approach
No Change Treat
Stable 12

Page 14

Strategic Risk Action Plan Date Updated 11-Sep-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Existing project level governance and controls remain effective and are
constantly reviewed.
25 January 2024: 
Progress on Transformation projects continues to be governed and
monitored via the Transformation Board which is chaired by the
Chief Executive. Meetings held quarterly Workstreams have been
fully developed and progress and all actions tracked. Financial
efficiencies across commercial property, waste review, learning
resource review, ELC review and the sustainability programme have
been fed into the Council’s Budget programme for 2024/25 to
2026/27.
11 September 2024:
Programme continues to be developed and work being progressed
to feed a pipeline of financial efficiencies into the Budget programme
for 2025/26.
Quarterly
Mark Boyd / Chief
Executive and
Executive Directors 
Review current governance arrangements and project delivery in view of
land and property workstream to seek optimal delivery aligned to the
council’s net zero ambitions.
25 January 2024:
Key progress made around Irvine Based locality property Review.
Next stages to present Cabinet Paper in March 2024 to consider
plans. 
11 September 2024:
Governance arrangements in place and property programme being
progressed. This will feed into the 2025/26 Budget programme.
26-Feb-2025
Mark Boyd / Chief
Executive and
Executive Directors

Page 15

Risk Code SRR2425_R06 Risk Title Climate Change Latest Note Date 20-Sep-2024
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Climate change is expected to continue and
worsen in the future if no action is taken,
with increases to mean global temperatures,
sea level rises and the increasing frequency
and severity of weather events such as
floods, heatwaves, droughts and storms. 
More frequent and intense heavy rainfall
events increase the risk of soil erosion and
flooding. 
Rises in mean sea level increases risks of
coastal erosion, flooding, saltwater intrusion
and soil salinisation (risk to agricultural land
and freshwater habitats). 
Severe weather is already affecting public
services across Scotland, with operational,
reputational, financial and legal
consequences. 
There is also an ongoing impact of severe
winter weather including snowfall and
freezing temperatures which impact service
delivery and the integrity of our roads open
space and buildings infrastructure. This shift
in weather patterns caused by climate
change is also affecting biodiversity across
Scotland.
Increased frequency of severe weather
conditions and flooding events may lead to
more instances of damage to Council
infrastructure and property, interruptions to
service delivery and increased demands on
services, often with little notice. 
Risk to life, transport disruption and
pollution to the local environment, as well
as impact adversely on the local economy
if businesses are unable to operate. 
Council requirement to provide immediate
response and manage the adverse effects
of more frequent and severe weather
emergency situations, including support to
local communities and businesses. 
The Council is required to comply with the
‘Public Bodies Climate Change Duties’
under the Climate Change (Scotland) Act
2009. These duties require the Council to
assess the risks, threats and opportunities
associated with climate change and identify
actions to increase resilience to climate
change.
North Ayrshire Council declared a Climate Emergency in June 2019, committing
to act on climate change and reduce carbon emissions. In January 2020 the
Council approved the target to become net-zero carbon by 2030, for both Council
estate emissions and area-wide emissions.
Following implementation of the Council’s third Environmental Sustainability and
Climate Change Strategy (2021-23), Cabinet approved the new Sustainable North
Ayrshire Strategy (2024-27) in December 2023. This strategy provides a road map
to achieve the net zero carbon emissions by 2030 target. 
There are 5 workstreams within the Sustainable North Ayrshire strategy, namely
Energy, Nature, Transport, Waste and Adaptation. We continue to utilise
Adaptation Scotland’s Capability Framework to ensure North Ayrshire takes a
strong, proactive approach to adapting to climate change.  Officers are
participating in the Sustainable Scotland Network’s ‘Adaptation Scotland
Benchmarking Group’ to learn and share best practice with other local authorities.
Adaptation actions are identified within the Ayrshire Flood Risk Management Plan
(2021), the Ayrshire Local Flood Risk Management Plan (2022), the Ayrshire
Shoreline Management Plan and in the Adaptation Capability Framework.
Flood studies are undertaken to help the Council identify areas that are at risk of
flooding and to appraise options to reduce flood risk to communities and
infrastructure.
In addition, actions to mitigate Climate Change risk are held within strategies such
as the Core Paths Plan, Outdoor Access Strategy, Local Biodiversity Action Plan,
and Weather and Winter Emergencies Plan. Asset management plans are in
place which are regularly reviewed for our Roads, Fleet, Housing, Property and
Open Spaces. 
Furthermore, through the Ayrshire Civil Contingencies Team there are emergency
planning arrangements in place in the event of severe weather and flooding
conditions causing major disruption and damage to the area or to individual
communities within it.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 16

Strategic Risk Action Plan Date Updated 20-Sep-2024
Analysis of Effectiveness of Controls Further Action Required
Target Date
for
Completion
Officers
Responsible
Current
Status: RAG
Reducing Carbon Emissions:
North Ayrshire Council declared a Climate Emergency in June
2019, committing to act on climate change and reduce carbon
emissions. In January 2020 the Council approved the target to
become net-zero carbon by 2030, for both Council estate
emissions and area-wide emissions.
The Council has taken action against climate change since our
first Carbon Management Plan in 2006/07, by working to reduce
emissions associated with Council services, and using the
baseline year of 2005/06 from which to measure progress.
Since the baseline year of 2005/06, Council estate emissions
have reduced by 67%, from 63,334 tonnes of carbon dioxide
equivalent (tCO2e) to 20,745 tCO2e. Area-wide emissions are
published by BEIS. Current records show total emissions have
reduced across North Ayrshire by 42.6%, from 1,454 kilo-tonnes
of carbon dioxide (ktCO2) in 2005 to 835 ktCO2 in 2019.
To ensure North Ayrshire Council can develop a leading, cross-
sector and community led approach we established a Climate
Change Steering Group (CCSG) in 2021. The CCSG is chaired
by the Cabinet Member for Green Environment and Economy,
and brings together young people, local businesses and
community organisations from across North Ayrshire.
Existing controls remain effective and are under review as our
response to climate change develops and we progress towards
achieving net zero by the 2030 target. 
8th February 2024:
Implementation of the Sustainable North Ayrshire strategy, which includes 9 strategic
principles and 46 actions under the 5 workstreams of Energy, Nature, Transport, Waste and
Adaptation. The 9 strategic principles which are being implemented are:
1.We will take a whole system approach (including behaviour change) to tackling climate
change as far as possible, including identification of optimal approaches to achieve social
and economic benefits alongside environmental ones.
2.We will continue to clarify and report transparently on our emissions so that the North
Ayrshire emissions baseline is clearly understood.
3.We will complete a Local Heat and Energy Efficiency Strategy to help understand where
efforts to reducing emissions and reducing fuel poverty are best focused.
4.We will prioritise actions in relation to two of the biggest emissions sources where have
the most influence, commonly referred to as ‘heat and fleet’, including through project
pathfinder approaches for decarbonisation of domestic and non-domestic buildings and
vehicles to bring scale and pace to emissions reduction.
5.We will work with stakeholders, including the Scottish Government, to articulate the
potential costs and skills requirements to meet our net-zero aspirations.
6.We will expand on the need for adaptation measures, recognising mitigation alone will not
combat the impacts of climate changes on communities.
7.We will identify opportunities for expansion of carbon sinks and other carbon capture
technologies, which are expected to be an essential element of our net-zero strategy to
mitigate residual emissions by 2030.
8.We will seek to expand the remit and membership of the CCSG to enable us to work more
closely with communities, taking account of outcomes from recent projects such as Climate
Action Towns and Carbon Neutral Islands.
9.We will explore the potential for carbon accounting, including carbon budgets for Council
services, to support our journey to net-zero.
Updates on progress are provided through the Council’s performance reporting system,
Pentana, on a quarterly basis, and governed through the Sustainability Board. Actions are
designed to be directly and indirectly responsible for carbon reduction and deliver other
socio-economic benefits.
20 September 2024:
Actions detailed within the Sustainable North Ayrshire Strategy continue to be implemented,
with progress monitored through the Council’s corporate performance management system
for example: 
• Participation in the Scottish Climate Intelligence Service to expand action on and
monitor area-wide emissions.
• Publication of North Ayrshire’s first Local Heat and Energy Efficiency Strategy
(LHEES) and progression of initial actions from Delivery Plan. 
• Development of two solar PV farms on former landfill sites. 
• Completion of feasibility study for the decarbonisation of built assets. 
• Progression of green hydrogen generation study. 
• Development of North Ayrshire Nature Network strategy to address statutory
requirements to tackle the nature crisis.
• Partnership working with Ayrshire Roads Alliance to undertake Electric Vehicle
Infrastructure project
31-Mar-2027 Russell
McCutcheon

Page 17

Strategic Risk Action Plan Date Updated 20-Sep-2024
Analysis of Effectiveness of Controls Further Action Required
Target Date
for
Completion
Officers
Responsible
Current
Status: RAG
• Successful realisation of £725,998 external funding for domestic energy efficiency
measures through ECO4 Flex partnership. 
Flood Risk Management Plan:
Cycle 2 of the Ayrshire Local Flood Risk Management Plan has
been developed and was published on 31st December 2022.
Studies and modelling will be undertaken to identify and prioritise
vulnerable areas where financial damage and risk to life are most
likely.
There is an ongoing programme of monthly inspections of debris
screens which have been installed to prevent vulnerable culverts
from blocking and causing flooding. CCTV inspections of culverts
are also undertaken to identify blockages and deterioration of
assets that might cause flooding. This has been effective in
reducing flooding, although there are capacity issues h that this
process cannot address.
The Upper Garnock Valley FPS has been completed and is
currently providing flood protection.
Ayrshire Shoreline Management Plan:
The Ayrshire Shoreline Management Plan will be replaced with a
Coastal Change Adaptation Plan. The adaptation plan will enable
the Council and other stakeholders to effectively plan our future
22 February 2024:
1. We will undertake the actions outlined in cycle 2 of the Ayrshire Local Flood Risk
Management Plan. 
2. We will continue to look for opportunities to implement Natural Flood Management and we
will develop a range of further flood protection measures, which can be put forward as
schemes for inclusion in cycle 3 of the Ayrshire Flood Risk Management Plan and the
Ayrshire Local Flood Risk Management Plan.
3. We will complete the Millport Coastal FPS and the Mill Burn FPS.
4. We will continue to Inspect culverts, screens and watercourses for clearance and repair
work in accordance with the published schedule and prioritise maintenance works that would
substantially reduce flood risk. Efforts will be made to continue to identify unknown culverts
and add these assets to the ongoing inspection and maintenance process.
5. We will develop the Ayrshire Coastal Change Adaptation Plan in partnership with South
Ayrshire Council and other stakeholders.
20 September 2024:
1. The Millport Coastal Flood Protection Scheme is 99% complete and we will commence a
further flood protection scheme at the Mill Burn, also in Millport.
2. The Three Towns flood study is underway. This study will confirm flood risk from the
Stevenston Burn & the Stanley Burn. The impacts of climate change will be evaluated.
30-Jun-2028 Thomas Reaney

Page 18

Strategic Risk Action Plan Date Updated 20-Sep-2024
Analysis of Effectiveness of Controls Further Action Required
Target Date
for
Completion
Officers
Responsible
Current
Status: RAG
actions whilst allowing for flexibility in response to future changes.
It will incorporate recent international and UK advances in
adaptation and shoreline management planning to allow for local
interpretation and involvement.
Where flood risk is confirmed, scoping of the next steps will be completed and this will
inform the second stage of the study.
3. The North Ayrshire Water Body Clearance & Repair Schedule has been updated to
include details of the planned assessment of various water bodies. Where these
assessments find that the condition of the water bodies would or could contribute to
significant flood risk, then the necessary clearance and repair work will be scheduled and
completed.
4. Storm Gerrit brought widespread flooding to North Ayrshire on the 27 December 2023.
Emergency repairs to culverts in Millport and Kilbirnie have now been completed.
5. In April 2024, a blockage in the Minister’s Cast culvert increased flood risk to roads and
properties in Irvine including The Circuit leisure facility and Woodlands Primary School. The
clearance and repair framework was used to commission emergency works that restored the
performance of the culvert. 
6. A draft coastal management study at Irvine & Stevenson is complete and was subject to
public consultation in September 2024. When finalised, the study will help to inform a local
Coastal Change Adaptation Plan. This plan will set out triggers for when the coastal erosion
and flood risk adaptations identified in the management study should be implemented.

Page 19

Risk Code SRR2425_R07 Risk Title Community Capacity Building and Empowerment Latest Note Date  19 Sept 24
Risk Owner Rhonda Leith
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Unrealistic timescales for progressing of aspects of
legislation of the Community Empowerment Act
(Scotland) 2015, such as Community Asset
Transfer. 
Pressure to support community capacity building
and the variation of needs within a reducing
workforce. 
Duplication of effort across HSCP and Locality
Partnerships to foster community participation and
deliver engagement activities.
Complying with the complex and resource
intensive consultation legislation in service
redesign.
Rising energy and utility costs relating to property
management.
Budget savings and pressure on property
maintenance budgets.
Where the risk is not managed effectively the
potential benefits of community capacity building
and empowerment may be lost. 
Widening inequality gap between those
communities where levels of capacity and
engagement with the empowerment agenda are
high and those with less social capital where
interest remains low, which constrains the ability
to influence the planning and delivery service. 
Any disconnect between the Council’s
aspirations, community appetite for increasing
ownership of assets and what communities
themselves feel able and prepared to commit to
can result in community assets reverting back to
Council. 
Accelerating asset transfer risks losing services
and facilities and risks the ability to plan, connect
and deliver strategic services. 
Over-engagement carries disengagement and
engagement fatigue.
Increased property costs can be a deterrent for
organisations engaging and completing the CAT
process.
Lack of budget to undertake proactive
maintenance is resulting in NAC buildings falling
into disrepair detracting organisations from
progressing to lease and or ownership of NAC
assets.
Ongoing commitment to community empowerment and
locality partnerships from CPP. 
Six locality partnerships and alignment with HSCP
locality arrangements. 
Leadership of the CPP Senior Officers’ Group. 
Enabling approach with community partners and support
with third sector interface to build capacity and identify
opportunities for growth and sustainability. 
Reviewed guidance and processes relating to
community empowerment functions. 
Participatory budgeting approach local grants,
commitment to PB with partners and leading practice in
mainstreaming participatory approaches 
External funding bid help for groups through regular
meetings with third sector, funders and funding officer. 
Membership of The Consultation Institute.
Investment from Community Asset Transfer Start Up
Fund, prioritising additional staffing capacity to support
CAT in TACT.
A collaboration and shared resource approach across
Connected Communities Teams will be taken to ensure
the Service deliver on this priority.
5 4
Status Risk Score
Heat Map 
Change in Score Approach
Increase from 16 to 20 Treat 
Increasing  20

Page 20

Strategic Risk Action Plan  19-Sept-24
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Implementation of Community Empowerment Act: 
Existing controls remain effective and are kept under review.  
05 February 2024: 
Strategic CLD Plan 2021-2024 identifies priorities for capacity building and the programme
of community support is addressing needs. No further update at this time.
19 September 2024:
New Strategic CLD Plan 2024 – 2027 in final stages of development and continues to
identify priorities and support available.
31-Mar-2025 Rhonda Leith 
05 February 2024: 
Post implementation the plan will be monitored and reported as per statutory timescales.
19 September 2024:
Linking with National partners i.e. Scottish Government to ensure timely communication to
any changes relating to national legislation and allow preparations to be in place.
31-Dec-2024 Rhonda Leith 
Staff capacity: 
Existing controls remain effective however forthcoming VER
structure changes will result in a reduction of CLD professional
staff and risks further pressures on staff to deliver effectively to
key outcomes.
05 February 2024: 
CLD service redesign will be implemented from 1st of April with a 6-month review date. The
redesign in light of VER impacts has resulted in the loss of the Capacity and Empowerment
Team, all key priorities of the team will be embedded in the newly formed localities Contact
agreement established with key 3rd Sector organisations This will mitigate the impact on
developments of the key outcomes as detailed in the CLD plan. The CLD plan review will
commence in April, following guidance due to be issued by the Scottish Government which
will be informed by the National Review Of CLD.
19 September 2024:
Function review within the CLD team underway to assess capacities and impact following
the service redesign. Focus will be on assigning resource to key priorities.
31-Dec-2024 Rhonda Leith 
Duplication of effort:
Clearly defined roles and lean processes are reviewed and
maintained to avoid duplication of effort and minimise time and
resource wastage. The team foster open communication
channels with both staff and key stakeholders.
05 February 2024:
Existing controls are effective but remain under proactive review.
19 September 2024:
The aim is to capture and address issues through the review of functions underway within
the CLD team.
31-Dec-2024 Rhonda Leith 
Consultation:
Existing controls remain effective. Existing controls remain
effective and hybrid engagement models have been
implemented post covid to encourage and provide greater
access to participation.
05 February 2024:  Proactive review 6 months post VER restructure to assess the
effectiveness of CLD support for community engagement and consultation.
No further update at this time.
19 September 2024:
Cross Service support for consultation and engagement is being further developed with the
promotion of existing tools and supports across all Council services to encourage
ownership over service engagement.
31-Mar-2025 Rhonda Leith 
Increased property costs and lack of investment in community
assets.
05 February 2024
A collaborative approach involving PMI and CC is being used to survey and evaluate
community buildings that require investment. CAT funds have been identified for corrective
actions, which will involve incorporating green investments to support future CAT and
Service development initiatives.
19 September 2024:
Matter escalated through a range of mechanisms including Health & Safety, PMI/Risk
meetings and reporting systems as well as more frequent management on-site building
visits to assess building condition and escalate accordingly.
A strategic plan is in the early stages of development to address identified condition issues
in buildings earmarked for potential Community Asset Transfer (CAT). Specific investment
funds have been allocated to support this initiative.
31-Mar 2025 Rhonda Leith

Page 21

Risk Code SRR2425_R08 Risk Title Property Asset Risk Latest Note Date  13-Sep-2024
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The long-term impact of restricted budget
availability for investment in the Council’s property
assets means these assets are in declining
condition and have greater long term investment
needs. 
Systemic building safety issues have been
evidenced by issues such as national high profile
safety issues, and the presence of RAAC through
the public sector property portfolio. These have
highlighted the substantial increasing burden of
property asset management.
There have been a number of near misses or
critical failures of aging heating plant and
equipment which the council cannot afford to
replace on a programmed basis.
Inflationary pressures, and on-going volatility in the
construction & related activities sphere, place
further difficulties in the ability of restricted budgets
to address all priorities. 
Maintenance issues and failure of building
components are increasingly likely to result in
disruption to service delivery. There is also an
increasing risk of health and safety and statutory
compliance obligations not being achieved. 
Property events requiring significant interventions
leading to service disruption, closure of facilities,
decant etc. are in increasing in frequency and
often over-lapping (often coinciding with weather
events).
Property condition information is gathered and recorded
within the Council’s electronic asset management
system, providing a baseline to measure building
element lifecycle replacement requirements across the
corporate estate.
The limited investment available is therefore targeted on
priorities. 
Reactive maintenance, and statutory compliance are
also undertaken corporately by PMI, by appropriately
trained / experienced staff. 
There is an on-going Transformation programme
workstream focusing on property rationalisation as a
means of reducing the financial burden of the estate
through reducing overall area occupied (aligned to
carbon reductions). 
Post Incident reviews and lessons learned exercises
with actions undertaken where feasible to do so.
Risk based property reviews are underway to examine,
on a property by property basis, where property risks
have the potential to impact service delivery. The
information gathered influences both investment plans
and business continuity plans. This work is on-going in
respect of the school estate and is being rolled-out to
other services’ assets.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
No Change Treat
Stable 20

Page 22

Strategic Risk Action Plan Date Updated 13-Sep-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
CC&M team within PMI managing reactive maintenance and
statutory compliance.
Team resources stretched; however, restricted budgets are principal risk. 
13 September 2024:
Team resources remain stretched, presently exacerbated by recent staff departure,
recruitment exercise currently on-going.  
Ongoing Russell
McCutcheon 
Asset management team within PMI collecting asset condition
information and leading prioritisation of lifecycle investment.
Improved asset management system is being investigated; however, restricted budgets are
principal risk. 
13 September 2024:
Work continues in relation to the new asset management system, including bench-marking
and information sharing with other authorities.  
Ongoing Russell
McCutcheon 
Property rationalisation programme
Locality based property review work currently underway to increase scale and pace of
implementation. 
13 September 2024:
The Irvine Property Accommodation programme received Cabinet approval in March 24
and is progressing to programme. 
Ongoing Russell
McCutcheon 
Risk based property review process
Requires up to date property information, including client information and cross service
buy-in to be effective. 
13 September 2024:
The Education Estate has been reviewed in its entirety and quarterly meetings have been
established to continue this work on a priority-basis. 
The approach has also been utilised in respect of the communities estate. 
Ongoing Russell
McCutcheon