North Ayrshire Council, Cunninghame House, Irvine KA12 8EE         
Audit and Scrutiny Committee 
A Meeting of the Audit and Scrutiny Committee of North Ayrshire Council will be
held in the Council Chambers, Ground Floor, Cunninghame House, Irvine, KA12
8EE on Thursday, 30 May 2024 at 10:00 to consider the undernoted business. 
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.  Where possible, the meeting will be live-streamed
and available to view at https://north-ayrshire.public-
i.tv/core/portal/home.   
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
2 Minutes
The accuracy of the Minutes of the Meeting of the Audit and Scrutiny
Committee held on 21 March 2024 will be confirmed and the Minutes
signed in accordance with Paragraph 7 (1) of Schedule 7 of the Local
Government (Scotland) Act 1973 (copy enclosed). 
3 Construction Contract Quality Monitoring
Submit report by the Executive Director (Place) providing an update on
the Council’s approach to Construction Contract delivery (copy enclosed). 
4 2023/24 Elected Member Requests Report
Submit report by the Head of Service (Democratic) informing of the
Council’s performance and the volumes and trends of Elected Member
requests handled in Financial Year 2023/24 (copy enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
5 2023/24 Complaint Report
Submit report by the Head of Service (Democratic) informing of the
Council’s complaint performance and the volumes and trends of
complaints received in Financial Year 2023/24 (copy enclosed). 
6 Code of Corporate Governance Statement 2024/25
Submit report by the Head of Service (Democratic) seeking approval of
the Code of Governance Statement 2024/25 (copy enclosed). 
7 Accounts Commission’s Report: Local Government in Scotland:
Financial Bulletin 2022/23
Submit report by the Head of Service (Finance) informing of the findings of the
recently published report (copy enclosed). 
8 2022/23 External Audit Action Plan Update
Submit report by the Head of Service (Finance) on the updated actions
identified in the 2022/23 External Audit Action Plan (copy enclosed). 
9 Annual Governance Statement 2023/24
Submit report by the Head of Service (Finance) on the Council’s Annual
Governance Statement for 2023/24 which will be included within the draft
Annual Accounts (copy enclosed).   
10  Accounting Policies 2023/24
Submit report by the Head of Service (Finance) seeking approval of the
accounting policies which will be adopted in the preparation of the
Council’s Annual Accounts for the year to 31 March 2024 (copy
enclosed). 
11  Strategic Risk Register 2024/25
Submit report by the Head of Service (Finance) on the Council’s agreed
Strategic Risk Register for 2024/25 (copy enclosed). 
12  Internal Audit Annual Report 2023/24
Submit report by the Head of Service (Finance) on the work of Internal
Audit during 2023/24 and providing an opinion on the governance, risk
management and internal control environment of the Council (copy
enclosed). 
13  Corporate Fraud Team Annual Report 2023/24
Submit report by the Head of Service (Finance) on the work of the
Corporate Fraud Team during 2023/24 (copy enclosed). 
14  Internal Audit and Corporate Fraud Action Plans: Quarter 4 Update
Submit report by Head of Service (Finance) on the progress made by
Council Services in implementing the agreed actions from Internal Audit
and Corporate Fraud reports as at 31 March 2024 (copy enclosed).
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
15  Internal Audit Reports Issued
Submit report by the Head of Service (Finance) on the findings of Internal
Audit work completed between March and April 2024 (copy enclosed). 
16  Standing Item of Business: Consideration of future business for
scrutiny 
17  Urgent Items
Any other items which the Chair considers to be urgent.  
Webcasting
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at https://north-ayrshire.public-
i.tv/core/portal/home, where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
Generally, the press and public seating areas will not be filmed. However,
by entering the Council Chambers, using the press or public seating area
or (by invitation) participating remotely in this meeting, you are consenting
to being filmed and consenting to the use and storage of those images and
sound recordings and any information pertaining to you contained in them
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. If you
do not wish to participate in a recording, you should leave the
meeting.  This will constitute your revocation of consent.
If you have any queries regarding this and, in particular, if you believe that
use and/or storage of any particular information would cause, or be likely
to cause, substantial damage or distress to any individual, please contact
dataprotectionofficer@north-ayrshire.gov.uk. 
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Audit and Scrutiny Committee Sederunt 
John Bell (Chair)
Donald Reid (Vice Chair)
Eleanor Collier
Cameron Inglis
Tom Marshall
Matthew McLean
Davina McTiernan
Donald L. Reid
John Sweeney 
Chair: 
Apologies: 
Attending: 
4

Page 5

Audit and Scrutiny Committee
21 March 2024 
At a Meeting of the Audit and Scrutiny Committee of North Ayrshire Council at 10.00
a.m. involving participation by remote electronic means and physical attendance
within the Council Chambers, Irvine. 
Present (Physical Participation)
John Bell, Donald Reid, Eleanor Collier, Cameron Inglis, Matthew McLean, Donald L.
Reid and John Sweeney. 
Present (Remote Participation)
Tom Marshall and Davina McTiernan. 
In Attendance (Physical Participation)
A. Sutton, Executive Director, R. Leith, Head of Service (Connected Communities)
and A. McClelland, Head of Service (Education); (Communities and Education); P.
Doak, Head of Service (Finance and Transformation) (Health and Social Care
Partnership); T. Reaney, Head of Service (Neighbourhood Services) (Place); M.
Boyd, Head of Service,  L. Miller, Senior Manager (Audit, Fraud, Safety and Risk)
and D. Forbes, Strategic Business Partner (Financial Management and Revenues)
(Finance); A. Elliot, Senior Manager (Housing Operations) (Place); E. Nixon, Senior
Manager (Customer Service) (People and ICT); and A. Craig, Head of Service, I.
Hardy, Team Manager (Policy, Performance and Elections), M. Anderson, Senior
Manager (Committee and Member Services) and H. Clancy, Committee Services
Officer (Democratic Services) (Chief Executive’s Service). 
Also In Attendance (Physical Participation)
D. Jamieson, Audit Scotland. 
Chair
Councillor Bell in the Chair. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors. 
2. Minutes 
The accuracy of the Minutes of the Meeting of the Audit and Scrutiny Committee held
on 25 January 2024 was confirmed and the Minutes signed in accordance with
Paragraph 7 (1) of Schedule 7 of the Local Government (Scotland) Act 1973. 
3. Participatory Budgeting 
Submitted a report by the Executive Director (Communities and Education) on the
ongoing development of small grants Participatory Budgeting (PB).  Appendix 1 to
the report provided the Participatory Budgeting 2023-24 Review report.
Agenda Item 2
5

Page 6

Members asked questions, and received further information on the following: 
• mechanisms to encourage a wider range of groups to apply for funding;
• issues around the submission deadline for the previous round of funding
applications and IT difficulties which were outwith the control of the Council and
which had arisen in relation to voting, as well as recording feedback on such
matters;
• the need to encourage greater competition for funding in future, particularly with
regard to Youth Participatory Budgeting projects;
• the timing of future deadlines for the submission of funding applications, to better
meet the needs of prospective applicants; 
• actions to address technical issues in respect of voting;
• the Council’s approach and policy on the use of animals for entertainment from
Council owned land and premises and how that was reflected in funding decisins
as part of the Participatory Budgeting process; and
• strategies to increase the number of members of the public participating in the
voting process for Participatory Budgeting 
The Head of Service (Democratic), having clarified there was no bye-law in place,
undertook to provide further clarification of any current policy position on the use of
animals for entertainment from Council land and premises. 
Having duly reviewed the adaptations made to the small grants Participatory
Budgeting process and provided feedback, the Committee agreed to note the
progress made in developing the programme within Localities. 
4. Council Plan Mid-Year Progress Report 
Submitted a report by the Head of Service (Democratic) on the Council Plan Mid-
Year Progress Report 2023-24.  The progress report itself was attached as an
appendix to the report. 
Members asked questions, and received further information, on the following: 
• the timing in bringing the mid-year progress report to the committee;
• issues which could arise when a Council supplier/contractor changed its name
and the delays associated with meeting procurement rules around this;
• the extent to which current solar roof projects were generating power; and
• the application of the Council’s policy on community benefit from renewable
energy development. 
The Head of Service (Finance) undertook to look into the particular case raised by a
Member with regard to delays in service delivery following a change of name by a
contractor. 
The Head of Service (Democratic Services) undertook to liaise with the Head of
Service (Sustainability, Transport and Corporate Property) with regard to the
provision of further information on the delivery of community benefits associated with
solar farm projects.
6

Page 7

Noted. 
5. 2023/2024 Half-Yearly Complaint Report 
Submitted a report by the Head of Service (Democratic) on the Council’s complaint
performance and the volumes and trends of complaints received in the first six
months of financial year 2023/24. The progress report itself was attached as an
appendix to the report. 
Members asked questions, and received further information, on the following: 
• whether the “working days” referred to in the report excluded weekends;
• the varying delivery timescales associated with the different colours of
household waste bin due to supply chain issues;
• the perceived impact on litter levels of an identified issue affecting the lids of
purple household waste bins;
• the reputational damage to the Council of service failures in respect of
household waste collections;
• the impact of staff absence and vehicle faults on the waste collection service
and measures to manage these factors;
• the need for better communication with the public around missed/delayed
household waste collections, including whether it was possible to identify
alternative mechanisms to reach those who did not use social media;
• the categorisation of concerns as “service requests”, rather than “complaints”;
• the benefits of conducting a detailed review of the household waste collection
service, with a view to improving resilience, and the timescales for a planned
review;
• the high-profile nature of the household waste collection service and the
reasons for possible variance in performance in different parts of North Ayrshire;
• the potential impact on levels of fly tipping as a result of unscheduled closure of
waste recycling centres due to staff absence;
• the particular circumstances relating to household waste collection in rural
areas; 
• the feasibility of introducing a ‘status dashboard’ which would allow residents to
check on household waste collection issues in real time,
• poor parking on some residential streets, which impeded access by bin lorries,
and measures to address this;
• the circumstances which would lead to the categorisation of an issue as a
service request, stage 1 complaint or stage 2 complaint, and perceived
inconsistencies in categorisation;
• the planned reporting cycle for future Complaints reports; and 
• factors contributing to absence levels within the Waste team and the level of
absence within this Service compared with overall levels of absence across the
Council. 
The Head of Service (Neighbourhood Services) undertook to provide information to
Members on the comparative levels of staff absence within the Waste team and the
Council overall.
Noted.
7

Page 8

6. External Audit Plan 2023/24 
Submitted a report by the Head of Service (Finance) on the External Audit Plan for
2023/24. Audit Scotland’s Annual Audit Plan for the 2023/24 audit was attached as
an appendix to the report. 
Members asked questions, and received further information, on the following: 
• the fee structure of external audit services and the 6% uplift in audit fees;
• the terminology used in the audit report, with regard to “materiality levels”; and
• the Council’s current debt level and financial sustainability. 
Noted. 
7. Internal Audit Plan 2024/25 
Submitted a report by the Head of Service (Finance) on the proposed internal audit
plan for 2024/25. Appendix A to the report provided the internal audit plan for
Quarters 1 and 2 of 2024/25.  A list of potential audit areas was set out at Appendix
B to the report. 
The Chair asked a question, and received further information, on the potential for
slippage of less pressing matters as a result of implementing a dynamic plan
approach. 
The Committee agreed to approve the internal audit plan. 
8. Internal Audit Reports Issued 
Submitted a report by the Head of Service (Finance) on the findings of Internal Audit
work completed between January and February 2024.   The findings from four audit
assignments were detailed at Appendix 1 to the report, together with the respective
executive summaries and action plans. 
Members asked questions, and received further information, on the following: 
• the rectification of an oversight which had resulted in a small number of actions
in respect of IJB Workforce Planning not being assigned to an officer(s); and
• whether IJBs were more certain about their future over the next three years
following changes to proposals around a National Care Service; 
Noted.   
9. Internal Audit and Corporate Fraud Action Plans: Quarter 3 Update 
Submitted a report by the Head of Service (Finance) on the progress made by
Council Services in implementing the agreed actions from Internal Audit and
Corporate Fraud reports as at 31 December 2023. 
Noted.
8

Page 9

10. Standing Item of Business: Consideration of Future Business for
Scrutiny 
The Head of Service (Democratic) referred to the self-evaluation exercise conducted
by the Committee earlier in the year and, arising from this, to the addition of this
standing Agenda item. 
Members were invited to consider potential items of scrutiny business for future
meetings. 
The Executive Director (Communities and Education) undertook to ensure her
Service liaised directly with relevant Members on issues relating to specific
Community Asset Transfer applications, including in respect of Largs Tennis Club. 
The Committee agreed (a) to receive reports to future meetings on (i) the Community
Asset Transfer process and (ii) the Council’s Climate Change target and associated
policies; and (b) that it be remitted to officers to determine the appropriate reporting
timescales for these matters, based on available resources. 
11. Urgent Items 
There were no urgent items. 
12. Exclusion of the Public – Para 1 
The Committee resolved in terms of Section 50(A)4 of the Local Government
(Scotland) Act 1973, to exclude from the Meeting the press and the public for the
following item of business on the grounds indicated in terms of Paragraph 1 of Part 1
of Schedule 7A of the Act. 
13. Investigation Reports Issued (Exempt Item) 
Submitted a report by the Head of Service (Housing and Public Protection) updating
the Committee on the timeline surrounding a matter reported to the last meeting of
the Committee as part of an investigation report. 
Members asked questions, and received further information, on the following: 
• the lessons learned from this case and safeguards now in place; and
• the feasibility of more frequent checking and cross-checking of data. 
Noted. 
The meeting ended at 11.55 a.m.
9

Page 10

10

Page 11

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny
Title: Construction Contract Quality Monitoring
Purpose: To update the Audit and Scrutiny Committee on the Council’s
approach to Construction Contract delivery.
Recommendation: It is proposed that the committee note the contract
administration processes in place and the key risk and
mitigation measures noted in the report
1. Executive Summary
1.1 The Audit and Scrutiny Committee have requested information be provided regarding
the Council’s construction contract management procedures following on-going water
ingress to a sheltered housing unit which had previously undergone a refurbishment
project.
1.2 The cause of the particular issue highlighted has been found to be as a result of the
interface with a section of the building which was not refurbished and a requirement to
clear leaf-debris from the area, rather than a specific flaw in the contract
administration process. 
1.3 A suite of procurement, contract administration and governance measures are in place
to ensure the Council’s construction contracts and associated risk are managed
appropriately; a summary is provided in the report. 
2. Background
2.1 The Audit and Scrutiny Committee have requested information be provided regarding
the Council’s construction contract management procedures, in particular in relation to
construction quality and the sign-off / acceptance of completed works. 
2.2 The question was posed following on-going water ingress to the roof of Connel Court
Sheltered Housing Unit in Kilbirnie. This property underwent a significant
refurbishment between 2018 and 2020 The works were designed, and project
managed by the Council’s Property Management and Investment (PMI) team. The
construction contract was carried out by McLaughlin Construction limited. 
2.3 Investigation of the water ingress highlighted that blocked rain-water outlets in a flat
roof cause the inlets to become overwhelmed and let-in water.
Agenda Item 3
11

Page 12

2.4 The work carried out at the time of the refurbishment included the application of a
liquid applied roofing membrane to the area of flat roof and the installation of brush
gutter-guard system to prevent leaves blocking outlets. The roof-deck and outlets
were not replaced. 
2.5 The extent of the works was governed by the need to maintain a habitable
environment for residents during the course of the project. It was also believed the
liquid applied coating and outlet guards would be sufficient to ensure the roof
remained serviceable moving forward. 
2.6  Following completion of the works, the contract administrator was not made aware of
any water ingress during the one-year Defect Liability Period. It is assumed therefore
that the subsequent water ingress issues have arisen as a result of an excess of leaf
debris blocking the outlets. The underlying roof-deck also appears to have been
compromised by the water ingress. As a result:
• Building Services have agreed to undertake regular clearance of the roof and
outlets.
• A project to undertake a replacement of the roof is being progressed by PMI. 
2.7 A summary of the Council’s construction contract management procedures is set out
below.  
2.8 The majority of the Council’s construction contracts are managed by Property
Management and Investment. This includes Housing and non-housing (General
Services) projects, all non-housing maintenance and all Housing capital lifecycle
investment programmes. 
2.9 This encompasses a huge array of projects and works undertaken which vary greatly
in scope, from small repair works at almost de-minimis values, to educational
community campuses costing tens of millions of pounds. 
2.10 Quality processes associated with construction work therefore also varies accordingly,
relevant to the scale and complexity of the project and works undertaken. 
2.11 All contractors however are subject to procurement processes designed to ensure
people undertaking work have the sufficient knowledge, qualifications, experience and
financial capacity. 
2.12 In order to submit a compliant tender for any construction work, bidders must
demonstrate relevant and recent technical experience for the proposed construction
activities. 
2.13 Tenders are evaluated against the set criteria, which will also vary according to the
nature of the works prescribed in the contract. Often, detailed operational information
must be provided, for example, lists of proposed sub-contractors, traffic management
plans, plant and equipment operating plans etc.  
2.14 When awarded, contracts will be administered by PMI (or appointed external
consultants, depending on the chosen procurement route for the project). 
2.15 Construction works can be extremely complex and carry risk, both operationally and
commercially. Construction contracts are also complex and can give rise to
disagreement and dispute over the reasons for issues such as delays, inappropriate
12

Page 13

material use, incorrect installation methods etc. PMI have an experienced team of in-
house Architects, Surveyors, Project Mangers to manage these risks; also utilising a
range of external consultants and advisors to ensure contracts are delivered using
best practice methodologies. 
2.16 To assist in the process also PMI have a central database of contract administration
documents outlining key processes such as, standard meeting agendas, change
control / variation instructions, risk registers, inspection record pro-formas, hand-over
procedures. These documents are used by both Housing and non-housing teams as
appropriate to the contract in-hand. 
2.17 Prior to commencing works, a pre-start meeting will be held, chaired by PMI. The
purpose of the pre-start meeting is to ensure contractors are aware of requirements
such as the quality expectations of the Council in relation to works undertaken,
contract administration and health and safety requirements. 
2.18 In most capital projects, a Clerk of Works will be assigned to the project. The clerk of
works role is to inspect, record and report on the operational delivery of the works to
the contract administrator. Relevant site observations, issues with performance,
adherence to design / specification, health and safety and other matters arising can
then be addressed by the contract administrator. 
2.19 During the course of a contract, regular progress meetings take place (generally on
monthly basis) chaired by the contract administrator. The purpose of these meetings is
to monitor the progress of work against the contractor’s programme and to ensure that
the work being carried out is in accordance with the design and specification.  
2.20 As work progresses on-site, interim payments for work carried out are made, usually
on a monthly basis. The value to be paid is measured by the project Quantity Surveyor
and reflects the progress of works on-site. A monetary retention (normally 5%) is held
on each of these payments. This sum is partially released when works are complete,
the remainder being released after the end of the defects liability period. 
2.21 As a project approaches completion, it is common for sections of the works to be
offered by the contractor for inspection by the Council’s Clerk of Works and / or
contract administrator. Before offering works for inspection, it is incumbent on the
contractor to ensure all works have been carried out in accordance with the contract
documents. 
2.22 Where works are complex or of a specialist nature, specific design consultants such
as Mechanical and Electrical Engineers and Structural Engineers will be required to
carry-out their own inspections and confirm work have been completed to their
satisfaction. 
2.23 In some circumstances, specialist reports will be commissioned into specific building
elements, particularly where quality issues have been identified during the
construction phase. 
2.24 In the very largest of projects an Independent Tester is also appointed. This is a
relatively new role within the construction project environment. The independent tester
verifies the various testing and commissioning certificates required are received and
they will certify completion of the project in accordance with defined project completion
criteria.
13

Page 14

2.25 Separate Quality Meetings will be held on larger projects, this allows specific areas of
focus to be identified and tracked throughout the construction period and ensure input
by the relevant parties to monitor compliance with specification and desired standards. 
2.26 The majority of projects also require Building Warrant approval to ensure works are
designed and constructed in accordance with the prevailing Building Standards. This
is separate from the contractual process. Upon completion of works, a Building
Standards Completion Certificate will be accepted, following inspection and other such
reasonable enquiry by Building Standards during construction. In larger projects, this
can be carried out on a staged basis, with relevant approvals relating to specific
aspects of the work. 
2.27 When inspected, it is also common for a list of items which are not to the required
standard to be identified by the Council’s Clerk of Works, the Contract Administrator,
or their representative. 
2.28 Significant issues identified prior to hand-over have the potential to preclude the
Council accepting the works as complete. Less critical items (generally referred to as
“snagging” items) will be reasonably assessed on their merits to determine if the
building can be accepted while the contractor continues to address them. 
2.29 There have been several examples where non-compliance with completion criteria
requirements has resulted in a delay to hand-over, often in the face of significant
pressure from contractors to accept the works. This includes a current high-profile
major capital project and previous campus projects.
2.30 When the Contract Administrator is satisfied that works have been completed to an
appropriate standard, this is confirmed by the issue of the Certificate of Practical
Completion (PC). As noted above, achieving Practical Completion also triggers the
release of 50% of the retention. Upon Practical Completion, the Council then take
possession of the works and are fully responsible for all operational elements, such as
utility costs, insurance, statutory compliance checks, health and safety of occupants,
etc. 
2.31 Following Practical Completion, projects enter a Defect Liability Period (DLP), this is
generally for a one-year. During this time, the principal contractor is responsible for
remedying all defects which arise in the contracted works. PMI have dedicated
Contract Quality Officers to oversee this period. Their main responsibility is to manage
defects which arise during the DLP and ensure they are rectified by the contractor. 
2.32 Once the DLP has expired, a final inspection of the works is caried out and, subject to
any outstanding contractual works or defects being resolved, a Certificate of Making
Good Defects (MGD) is issued. This also triggers the release of the remaining
retention. 
2.33 Following the resolution of all known defects and the issue of the MGD certificate,
latent defects which arise, where these are not covered by specific guarantees,
require to be pursued as a claim outwith the construction contract. There is a
maximum 12 year period, dependant on contract type, where defects which arise can
be considered in this way. Any claim for against a latent defect must be raised within 5
years of it becoming apparent. 
14

Page 15

2.34 In addition to the contract administration processes noted above, relevant projects and
capital investment programmes are subject to the Council’s internal governance
procedures. Projects are reported to the relevant Service / Directorate Project Board,
chaired by a Head of Service or Director. Major projects are also subject to a further
level of scrutiny through regular ELT reporting.
2.35 Although the contract procurement, administration and governance process noted
above aim to mitigate against the risks of undertaking construction work, contract
disputes and construction quality issues can occur; leading to issues such as cost and
programme over-run and service impacts. 
2.36 Common risks, issues and mitigations in the construction contract environment are
noted below:
Common issues / examples Mitigations
Health and Safety during
construction 
Construction operations can present
risks to the Health and Safety to site
operatives or others in close proximity
to construction activities. 
Designers, specifiers, contractors, and
clients must carry out their
responsibilities in accordance with the
Construction Design Management
Regulations 2015. 
Risks in relation to the tasks to be
undertaken must be identified and
managed accordingly. 
Works must be carried out in
accordance with appropriate method
statements and safe working practices. 
Ground conditions / site location 
Ground conditions and site location
can impact on the design and cost of
key elements such as building
structure, services infrastructure, traffic
and pedestrian access, etc.   
Undertaking feasibility reports, based on
the high-level project brief as soon as
practical in the development process. 
Undertaking: site investigations to
determine ground conditions, potential
contamination etc; utility investigations
to determine if services can be delivered
to a site; other environmental studies
such as ecology, traffic management
etc. 
Work in existing buildings. 
Undertaking work within existing
buildings can result in previously
unknown defects in structure /
construction requiring to be added to
the scope of works. This can increase
programme and cost. 
Review of information held on record,
for example existing drawings, condition
surveys, asbestos registers etc. 
Surveys of existing building elements
carried out prior to finalisation of
contract documents. 
15

Page 16

The interface of existing building
elements with new installations can
also give rise to technical challenges
and potential disputes over liability. 
Work in occupied buildings. 
Working within an occupied building
can result in operational difficulty for
services, or significant disruption for
residents including utility disruptions,
noise, access restrictions etc.   
Careful project planning to ensure the
interface between the contractor, their
work and building users. 
On-site communication between the
design team, contractor, client and
building occupants. 
Changes to brief and scope of
project. 
Due to the evolving needs of services,
and the time required to properly
scope, design, procure and undertake
a construction project, the project brief
can change between inception and
works being carried out-site. Changes
to a design, particularly during the
construction phase can extend project
timescales and increase costs. 
Robust project briefing and client sign-
off of projects at relevant gateway
review points. 
Use of change control process to ensure
good project governance and
appropriate level sign off of changes. 
Contract monitoring and reporting
throughout the project lifecycle. 
Insufficient budget to deliver
preferred scope 
The ability to deliver all intended
outcomes of any investment will be
limited by the value of the available
budget. 
During the design process, the project
scope and specification will be
developed to ensure the maximum
benefit is achieved and the priorities can
be delivered; cost checks are
undertaken during the project
development phase.   
Contracts cannot be accepted unless
there is sufficient budget to deliver the
project. 
Project reporting and governance
procedures are in place. 
Contractor Performance 
Contractor performance may not meet
our expectations, for example:
inadequate supervision of works on-
site; using inexperienced /
underqualified staff /sub-contractors;
substituting specified materials, etc.   
Robust procurement process to ensure
appropriate contractors are appointed. 
Appropriately qualified design and
contact administration team, including
inspection / sign-off process. 
16

Page 17

The contractual risk and high values
involved can result in a combative
approach by some contractors, seeking
to maximise their financial gain. 
Appropriate contract management
procedures. 
3. Proposals 
3.1  It is proposed that the committee note the contract administration processes in place
and the key risk and mitigation measures noted in the report. 
4. Implications/Socio-economic Duty 
Financial 
4.1 There are no financial implications arising from this report. 
Human Resources 
4.2 There are no human resources implications arising from the report. 
Legal 
4.3 There are no Legal implications arising from this report. 
Equality/Socio-economic 
4.4 There are no equality implications arising from this report. 
Climate Change and Carbon 
4.5 There are no implications in relation to climate change and carbon arising from this
report. 
Key Priorities 
4.6 The processes set out in the report support the Council’s Key Priorities of:   
• Places and public spaces across North Ayrshire are well maintained and accessible.
• Our places encourage strong inclusive communities and respect the local environment
and cultural heritage. 
Community Wealth Building 
4.7 There are no Community Wealth Building implications arising from the report. 
17

Page 18

5. Consultation 
5.1 The Corporate Procurement Unit, Legal Services and Building Standards have been
consulted on the content of this report. 
Russell McCutcheon
Executive Director (Place) 
For further information please contact Laurence Cree,  Senior Manager, Property
Management and Investment , on 01294 324463. 
Background Papers
N/A
18

Page 19

NORTH AYRSHIRE COUNCIL 
30 May 2024 
Audit and Scrutiny Committee 
Title:    2023/24 Elected Member Requests Report 
Purpose:  To inform the Audit and Scrutiny Committee of the Council's
performance relating to Elected Member requests handled in
Financial Year 2023/24. 
Recommendation:  That the Committee notes the report and the information
provided. 
1. Executive Summary 
1.1 This report details Elected Member requests information covering the period 1 April
2023 to 31 March 2024 (referred to in the report as 2023/24). 
2. Background 
2.1 This section contains information and commentary on Elected Member requests
handled by the Council during Financial Year 2023/24. 
2.2 Volume of Elected Member requests actioned during 2023/24 
Volume of requests actioned during year 2,992 
2.2.1 Councillor requests can be handled by Services under two stages: 
Stage One – non-complex requests with a timescale to action of 5 working days
Stage Two – complex requests with a timescale to action of 20 working days 
Agenda Item 4
19

Page 20

2.2.2 The table below details all Councillor requests actioned during the year: 
2023/24
Stage One requests actioned 2,302
Stage One requests actioned on time 1,994
% Stage One requests actioned on time 87%
Stage Two requests actioned 2
Stage Two requests actioned on time 2
% Stage Two requests actioned on time 100%
Total % of requests actioned on time 87% 
2.2.3 Year on Year comparison 
2.2.4 The table below shows a comparison of the volume of Councillor requests received
and actioned over the last three years: 
Councillor Requests 2021/22 2022/23 2023/24 
Stage One requests actioned 1,971 2,903 2,302
Stage One requests actioned on time 1,779 2,588 1,994
% Stage One requests actioned on time 90% 89% 87%
Stage Two requests actioned 0 2 2
Stage Two requests actioned on time 0 1 2
% Stage Two requests actioned on time n/a 50% 100%
Total % of requests actioned on time 90% 89% 87% 
2.3 Volume of requests per Directorate 
2.3.1 Councillor Stage One requests (5 working day timescale to action) 
Directorate Department
No. of
requests
actioned
No.
actioned
on time
%
actioned
on time
Average no. of
days to resolve
Target
(days)
Chief Executive’s
Chief Executive Office 1 1 100% 5 5
Customer Services 21 19 90% 2.4 5
IT 1 1 100% 2 5
Legal Services 15 11 73% 10 5
Communities &
Housing
Building Services 97 86 89% 3.5 5
Community Facilities 2 2 100% 1.5 5
Community Learning & Dev. 11 11 100% 2.4 5
Housing 426 379 89% 3.5 5
Planning 20 19 95% 3.2 5
Protective Services 28 24 86% 4 5
Sports & Activity 6 4 67% 5.8 5
20

Page 21

Education Education 42 30 71% 4.5 5
Facilities Management 9 7 78% 3.4 5
Place
Roads 607 583 96% 2.7 5
Streetscene 389 319 82% 3.5 5
Waste 253 218 86% 3.6 5 
Business Development 3 3 100% 3.3 5
Employability 1 1 100% 5 5
Regeneration 47 31 66% 2.6 5 
Energy/Sustainability 16 8 50% 7.6 5
PMI 130 114 88% 3.7 5
Transport 3 3 100% 2 5
Health & Social
Care Partnership
Children & Families 29 21 72% 3.8 5
Health & Community Care 116 77 66% 5 5
Mental Health 28 21 75% 5.2 5
Support Services 1 1 100% 5 5   
2,302 1,994 87% 3.5 5 
2.3.2 Councillor Stage Two requests (20 working day timescale to action) 
Directorate Department
No. of
requests
actioned
No.
actioned
on time
%
actioned
on time
Average no. of
days to resolve
Stage Ones
Target
(days)
Place PMI 2 2 100% 12 20  
2 2 100% 12 20 
2.4 MP/MSP requests 
2.4.1 MP and MSP requests have a set timescale of 10 working days to action and the table
below details the requests actioned during the period: 
2023/24
Requests actioned 688
Requests actioned on time 509
% of requests actioned on time 74% 
2.4.2 Councillor and MP/MSP requests that did not meet timescale were due to multiple
factors, including: 
• Administrative errors
• Employee/Officer availability for approving responses prior to issue
• Reduced resources, causing delays investigating requests
• Further information required to respond to requests (including from third
parties)
• Operational pressures.
21

Page 22

2.5 Recording Councillor requests 
2.5.1 The table below shows how Councillor requests were logged throughout the year: 
Volume %
Volume of Councillor requests recorded 2,328 
Volume logged by Councillors  1,309 56%
Volume logged by Member Services 555 24%
Volume logged via other channels 464 20% 
2.5.2 Of the 1,309 requests logged by Councillors during the period, 21 Councillors used
their NAC online Member accounts to log requests themselves. 
2.6 Issue identified regarding follow up actions for Councillor requests 
2.6.1 Members noted at a previous Audit and Scrutiny Committee that some requests that
required follow up actions were being closed with no updates provided to the Members
once complete, causing Members difficulties when trying to relay full closure information
to their constituents.  A process to address these concerns was developed and
implemented late 2023 and an update on how the process is functioning will be provided
to a future Committee once sufficient information for analysis has been acquired. 
3. Proposals 
3.1 It is proposed the Committee approves the report and recognises the Council’s
performance in handling Elected Member requests in relation to Section 2 above. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 None.
22

Page 23

Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 None. 
Aileen Craig
Head of Service for Democratic Services 
For further information please contact Aileen Craig, Head of Democratic Services, on
(01294) 324125. 
Background Papers
None
23

Page 24

24

Page 25

NORTH AYRSHIRE COUNCIL 
30 May 2024 
Audit and Scrutiny Committee 
Title:    2023/24 Complaint Report 
Purpose:  To inform the Audit and Scrutiny Committee of the Council's
complaint performance and the volumes and trends of complaints
received in Financial Year 2023/24. 
Recommendation:  That the Committee notes the report and the information
provided. 
1. Executive Summary 
1.1 This report details complaint information relating to North Ayrshire Council during
2023/24, covering the period 1 April 2023 to 31 March 2024. 
1.2 To allow comparisons to be made the report also details some complaint data relating
to 2021 and 2022. 
1.3 Performance is measured through a number of Scottish Public Services Ombudsman
(SPSO) performance indicators, some of which have national targets. 
2. Background 
2.1 This section contains statistical information and commentary on some of the key
complaint performance indicators.  More information relating to the indicators can be
found in the attached report. This report is being presented to Committee earlier than
is usually the case and for that reason the complaints data relating to KA Leisure is
not available. 
2.2  Volume of complaints received 
Year Volume of
complaints
2021 2,827
2022 2,629
2023 1,948 
Agenda Item 5
25

Page 26

2.2.1 A 26% decrease in complaints seen when comparing 2023 with the previous year. 
2.3  Complaints closed at each Stage 
2021/22 2022/23 2023/24
Stage One 2,671 2,510 1,888
Stage Two 156 119 151 
2.3.1 Although there is no national target for the number of complaints to be closed under
each Stage, the Council seeks to maximise closure at Stage One as complainants
receive a quicker resolution compared to Stage Two, reduces the impact on service
resources and reduces the possibility of SPSO referrals. 
2.4  Complaint outcomes 
Stage One
Outcome 
% closed as Resolved 39%
% closed as Upheld 32%
% closed as Partially Upheld 12%
% closed as Not Upheld 17% 
Stage Two
Outcome 
% closed as Resolved 4%
% closed as Upheld 13%
% closed as Partially Upheld 39%
% closed as Not Upheld 44%               
2.4.1 Up to 31 March 2021, a complaint that meets our complaint criteria could be upheld,
partially upheld or not upheld. From 1 April 2021 a fourth outcome became available to
use called ‘Resolved’. Resolved complaints are where the Council has taken action to
address a problem or issue without making a decision on whether there were any failings
(this would happen where we agree a solution with the complainant at the outset without
needing to actually investigate the complaint). 
2.4.2 Complaint outcome analysis can be found in the attached report. 
2.5  Average time in working days for a full response at each Stage 
Stage One Average number of
working days to close
Target
2021 4.2 5 workings days or less
2022 4.2 5 workings days or less
2023 3.8 5 workings days or less 
Stage Two Average number of
days to close
Target
2021 15.4 20 working days or less
2022 14.9 20 working days or less
2023 16.8 20 working days or less
26

Page 27

2.5.1 The average time in working days for a response under both Stages is better than the
SPSO target response timescales for the last three years. 
2.6  Complaints closed within timescale 
Stage % closed on
time
Target
Stage One  87% 80% and above
Stage Two 88% 85% and above 
2.6.1  The volume closed on time includes extended complaints that met their new due dates. 
2.6.2  Further details of complaints not closed on time are contained in the attached report. 
2.7  Changes or Improvements made as a result of complaints 
2.7.1 Not all Services can implement improvements as a result of complaints due to a
number of factors, including the feasibility of making changes and resource/budget
considerations. That said, improvements were implemented in some Services and a
selection are noted in the attached report. 
2.8   Compliments 
2.8.1 The Council received and recorded many compliments during the year.  Some praised
specific individuals or teams, some related to more than one Service and some were
raised by employees complimenting other employees. A selection can be found in the
attached report. 
3. Proposals 
3.1 It is proposed the Committee approves the report and recognises the Council’s
complaint handling performance in relation to Section 2 above. 
4. Implications/Socio-economic Duty 
Financial 
4.1  None. 
Human Resources 
4.2  None. 
Legal 
4.3  None. 
Equality/Socio-economic 
4.4  None.
27

Page 28

Climate Change and Carbon 
4.5  None. 
Key Priorities 
4.6 The Two Stage Complaint Handling Procedure supports the Council's key priority of
delivering more effective and efficient service provision. It demonstrates commitment
through focussing on, and determining, trends for service improvement and delivery
for North Ayrshire residents, customers and visitors. 
Community Wealth Building 
4.7  None. 
5. Consultation 
5.1  None. 
Aileen Craig
Head of Service for Democratic Services 
For further information please contact Darren Miller, Complaint Manager, on (01294)
322988. 
Background Papers
North Ayrshire Council Complaint Report 2023/24
28

Page 29

North Ayrshire Council 
Annual Complaint Report 
2023 to 2024 
Agenda Item 5
29

Page 30

Contents
North Ayrshire Council  Annual Complaint Report  2023 to 2024 ................ 1
Stage One ................................................................................................. 3
Stage Two ................................................................................................. 3
1 Volume of complaints closed ................................................................... 4
Chief Executive’s ....................................................................................... 4
Communities & Housing .......................................................................... 4
Education .................................................................................................. 4
Health & Social Care ................................................................................ 5
Place ......................................................................................................... 5
Multi-Service ............................................................................................ 5
Year on Year comparison ......................................................................... 6
2 Volume of complaints closed on time at both Stages ............................. 6
3 Volume of complaints not closed on time per Directorate ..................... 6
Stage One ................................................................................................. 6
Stage Two ................................................................................................. 8
4 Key complaint topics ................................................................................ 9
5 Average time in working days for a full response ................................. 10
Chief Executive’s ..................................................................................... 10
Communities & Housing ........................................................................ 10
Education ................................................................................................ 11
Health & Social Care .............................................................................. 11
6 Extended complaints .............................................................................. 11
7 Complaint Outcomes ............................................................................. 12
Stage One ............................................................................................... 12
Stage Two ............................................................................................... 12
8 Improvements made as a result of complaints ..................................... 13
9 Compliments .......................................................................................... 14
10 Glossary ................................................................................................ 15
30

Page 31

Introduction
North Ayrshire Council always seeks to deliver the best services possible to its customers and
residents but it is recognised that dissatisfaction will sometimes occur. When it does, we
want to know what went wrong, why it went wrong and what we can do to make things
right.
The Council recognises that valuable lessons can be learnt from complaints which are
defined as being expressions of dissatisfaction from members of the public about actions, or
lack of actions, or about the standard of service provided by or on behalf of the Council.
The Council’s complaint handling procedure (CHP) has two stages for handling complaints
from the public.
Stage One complaints (also known as Frontline Resolution) are straightforward, non-complex
complaints the Council can resolve at the initial point of contact or as close to the point of
service delivery as possible. The Council has up to 5 working days to resolve these.
Stage Two complaints (also known as Investigations) are complaints the Council is typically
unable to resolve at Stage One and needs more time to carry out further investigation. This
may be because the nature of the complaint is complex, serious or high risk. The Council has
up to 20 working days to resolve these.
This report details the Council’s complaint handling performance covering financial year
2023 to 2024 (1 April 2023 to 31 March 2024). Performance is measured via several Scottish
Public Services Ombudsman indicators (some of which have national targets) and complaint
data relating to previous years has been included in certain sections to allow comparisons to
be made. 
Reporting complaints is a statutory requirement and is monitored by Audit Scotland.
This report has been reviewed for accessibility prior to publication.  
31

Page 32

1 Volume of complaints closed
The Council received 1,948 complaints during 2023 and closed 2,039. 
The table below provides a breakdown of the closed complaints per Directorate:
Directorate Volume
Chief Executive’s 100
Communities & Housing 421
Education 182
Health & Social Care 113
Place 1,212
Multi-Service 11
The following tables highlight complaint volumes per Directorate under each Stage:
Chief Executive’s
Team Stage One Stage Two
Chief Executive Service 1 0
Customer Services 79 6
Finance 2 1
IT 4 0
Legal Services 5 2
Total 91 9
Communities & Housing
Team Stage One Stage Two
Building Services 261 11
Community Facilities 2 1
Community Learning & Development 1 0
Housing 100 12
Information & Culture 8 2
Planning 4 3
Protective Services 14 2
Total 390 31
Education
Team Stage One Stage Two
Education (HQ) 18 7
Education (Schools) 102 43
Facilities Management 12 0
Total 132 50
32

Page 33

Health & Social Care
Team Stage One Stage Two
Children, Families & Criminal Justice 27 6
Finance & Transformation 4 0
Health & Community Care 46 12
Mental Health 3 7
Support Services 6 2
Total 86 27
Place
Team Stage One Stage Two
Community Wealth Building 0 1
Property Management 103 9
Regeneration 2 1
Roads 58 2
Streetscene 103 2
Sustainability 1 2
Waste Services 921 7
Total 1,188 24
Multi-Service
Team Stage One Stage Two
Complaints involving more than one Service 1 10
Total 1 10
Although there is no target for the volume of complaints handled under each Stage, the
Council seeks to maximise closure at Stage One wherever possible and 93% were handled at
this Stage during the period.
Some Services handled all their complaints at Stage One.
Some Services that received higher complaint volumes than other Services handled very few
complaints at Stage Two, notably Building Services, Housing, Streetscene and Waste Services
due to the nature of the complaints received.
Whilst 46% of all complaints received during the year related to Waste Services (the majority
being missed bin collections/assisted pullouts), the Service empties over 102,000 household
waste bins each week. As this equates to approximately 4.9 million collections over the year,
only 0.02% of all bins collected resulted in complaints being received. Good progress
continues to be made in the service with a 31% reduction in complaints compared to the
previous year and a 40% reduction when comparing complaints from 2021. Ongoing
challenges remain in the service such as absence levels and these are being handled and
managed appropriately.
33

Page 34

Year on Year comparison
The table below shows a comparison of the volume of complaints received over the last
three years:
Year Volume of complaints
2021 2,827
2022 2,629
2023 1,948
A 26% drop in complaints received when comparing 2023 with the previous year.  The
decrease could be partly attributable to the complaint page in the Council’s website being
enhanced, which now includes more information what the Council does not deem a
complaint and offers appropriate routes to raise such matters.
2 Volume of complaints closed on time at both Stages
Stage Percentage
closed on time
Target
Stage One  87% 80% and above
Stage Two 88% 85% and above
The volume closed on time in the table above includes extended complaints that met their
new due dates.
3 Volume of complaints not closed on time per Directorate
This section provides details of complaints not closed on time under each Stage and includes
extended complaints that did not meet their new timescales.
Stage One
Chief Executive’s 
Department Volume
Customer Services 1
Finance 1
Legal Services 1
These complaints breached timescale because a complaint handler was unable to contact a
complainant to discuss their complaint, a complaint was passed to a complaint handler who
was unavailable due to sickness absence and operational pressures. Extensions could have
been considered for two of these complaints given they were closed within the extra 5
working day extension allowance.
34

Page 35

Communities & Housing
Department Volume
Building Services 17
Housing 9
Protective Services 1
Multiple reasons were noted as to why these complaints did not meet timescale, including
delays in complaints being directed to the correct Services, awaiting information to progress
complaints and employee availability. Extensions could have been considered for the vast
majority of these given they were closed within the extra 5 working day extension allowance. 
Education
Department Volume
Education (HQ) 2
Education (Schools) 8
Various reasons were provided as to why these complaints did not meet timescale, with the
main reason being complainants not being available to assist with investigations.
Health & Social Care
Department Volume
Children & Families 1
Health & Community Care 5
Mental Health 1
Support Services 1
There were various reasons these complaints did not meet timescale, including complaint
handlers, employees and/or complainants not being available to progress investigations. 
Place
Department Volume
Property Management 3
Roads 3
Streetscene 19
Sustainability 1
Waste Services 173
Multiple reasons were given for complaints not closed on time, including complaint handlers
and complainants being unavailable to progress complaints, complainants/third parties
being unavailable to assist with investigations and resourcing issues (including employee
availability).
Of the 199 Place complaints not closed on time, 66% could have been considered for
extension as they were closed within the extra 5 working day extension allowance.
Regarding Waste Services complaints, see additional commentary in next section.
35

Page 36

Stage Two
Chief Executive’s
Department Volume
Legal Services 1
This complaint breached timescale because the complainant requested a change in complaint
handler.   This complaint should have been considered for timescale extension.
Communities & Housing
Department Volume
Building Services 2
Housing 2
Planning 1
Protective Services 1
These complaints breached timescale due to various reasons, with the main reasons being employee
availability and operational pressures. All six complaints could have been considered for timescale
extensions.
Education
Department Volume
Education (HQ) 1
Education (Schools) 9
Several complaints breached timescale due to a change in senior manager and a small
number breached as the complainants were unavailable.  Some of these could have had
their timescales extended.
Health & Social Care
Department Volume
Mental Health 1
This complaint breached timescale as additional checks were required at response approval
stage.  
36

Page 37

4 Key complaint topics
Key topics for upheld and partially upheld complaints for Services are listed below. Services
will not be listed if there were low complaint volumes that did not allow meaningful analysis.
Chief Executive’s
Service Key complaint topic
Customer Services Council tax issues
Customer Services Employee Actions (alleged or perceived)
Education
Service Key complaint topic
Education (HQ & schools) Sensitive issues relating to teachers and/or pupils
Education (HQ & schools) Service delivery/provision
Education (HQ & schools) Employee Actions (alleged or perceived)
Health & Social Care
Service Key complaint topic
All HSCP Services Service delivery/provision
All HSCP Services Employee Actions (alleged or perceived)
Place
Service Key complaint topic
Building Services Follow Up appointments
Building Services Quality of work issues
Housing Estate Management
Property Management & Investment Gas Central Heating (maintenance etc.)
Property Management & Investment Planned Works
Streetscene Tree/grass/verge/hedge cutting issues
Streetscene Employee Actions (alleged or perceived)
Waste Services Employee Actions (alleged or perceived)
Waste Services Issues with new bin deliveries
Waste Services Missed waste bin/assisted collections (all colours)
Waste Services Recycle scheme issues (shortage of food waste
bags etc.)
‘Employee Actions (alleged or perceived)’ appears as a key topic for some Services but the
definition is broad and has been used where complainants either alleged or perceived
employee actions or behaviour to be unacceptable. Whilst investigations may determine this
is not always the case, where unacceptable behaviour was identified by Services appropriate
action will have been taken to address.
37

Page 38

5 Average time in working days for a full response
The average time in working days to close complaints under both Stages during the year is
noted below. Values for previous years have been included to allow comparisons to be
made. Any complaints that had their timescales extended have been excluded from the
calculations.
Stage One Average number of
working days to close
Target
2021 4.2 5 workings days or less
2022 4.2 5 workings days or less
2023 3.8 5 workings days or less
Stage Two Average number of days
to close
Target
2021 15.4 20 working days or less
2022 14.9 20 working days or less
2023 16.8 20 working days or less
The average time to close complaints under both Stages has consistently exceeded target. 
The tables below detail Services that did not meet the average time in working days for a
response under either Stage. Services that met the target are not listed and any complaints
that had their timescales extended have been excluded from the calculations.
Chief Executive’s
Stage One Average number of
working days to close
Target
Finance 13 5 workings days or less
One Finance complaint was closed on working day 21, resulting in the 5 working day average
target not being met for the Service.
Communities & Housing
Stage Two Average number of
working days to close
Target
Planning 23 20 workings days or less
Protective Services 45 20 workings days or less
One Planning complaint was closed on working day 47 due to employee unavailability and
one Protective Services complaint was closed on working day 45 due to the complexity of
the issues raised.  These complaints could have been considered for timescale extension.  
38

Page 39

Education
Stage Two Average number of
working days to close
Target
Education (Schools) 21 20 workings days or less
A small number of complaints were closed out with the 20 working days timescale, resulting
in the target not being met. Some of these complaints could have had their timescales
extended. 
Health & Social Care
Stage One  Average number of
working days to close
Target
Mental Health 9.5 5 workings days or less
A Mental Health Stage One complaint was closed on working day 15, resulting in the target
not being met.   
6 Extended complaints
103 complaints had their timescales extended during the year (81 at Stage One and 22 at
Stage Two). The complaints related to various Services across all Directorates.
There were various reasons for extending, including complainants, third parties and
employees being unavailable to assist or support with investigations and/or letter approvals,
obtaining additional information to support investigations and resourcing/operational
issues. Of the 103 complaints that had their timescales extended, 80% were closed within
their new due dates. 
39

Page 40

7 Complaint Outcomes
Up to 31 March 2021, a complaint that meets our complaint criteria could be upheld,
partially upheld or not upheld. From 1 April 2021, a fourth outcome became available to use
called ‘Resolved’. Resolved complaints are where the Council has taken action to address the
problem/issue without making a decision on whether there were any failings (this would
happen where we agree a solution with the complainant at the outset without needing to
actually investigate the complaint). 
The charts below detail the number of complaints upheld, partially upheld, not upheld or
resolved under both Stages.
Stage One
Outcome Percentage
Closed as Resolved 39%
Closed as Upheld 32%
Closed as Partially Upheld 12%
Closed as Not Upheld 17%
Of all complaints upheld and partially upheld at Stage One, just over half related to Waste
Services and in particular bin collections. 
55% of all Resolved complaints also related to Waste Services (again mainly missed bin
collections), indicating these complainants simply wanted their bins collected without the
need for investigation. 
Complaints that were not upheld related to policies, regulations or were complaints that
were poor quality/unfounded.
Stage Two 
Outcome Percentage
Closed as Resolved 4%
Closed as Upheld 13%
Closed as Partially Upheld 39%
Closed as Not Upheld 44%
All Stage Two complaints that were upheld or partially upheld were split across multiple
Services across all Directorates.
Of the 44% of complaints not upheld, those decisions were reached for various reasons,
including the application of polices and regulations and complaints that were
unsubstantiated.
Note - Partially Upheld complaints are complaints that contain more than one complaint
element and at least one of them is upheld.
40

Page 41

8 Improvements made as a result of complaints
Council Services continually seek to identify improvements in service delivery and complaint
information is analysed regularly to inform service improvements.  Some improvements
were implemented as a result of complaints received during the year and a selection is
noted below.
What happened? What we did
A complaint was received about grass
cutting where litter was not being removed
prior to cutting, which resulted in the litter
being shredded and distributed across the
park.
A refresher with the team responsible was
arranged to ensure they are aware of their
obligations in terms of litter removal and every
effort will be made in the future to ensure litter
is removed prior to any grass cutting activities.
A tenant encountered problems when
radiators were incorrectly fitted and applied
for a disturbance allowance payment for
the inconvenience.  
An apology was offered and the matters
addressed.  Discussions then took place
between the Council and the contractor
regarding the importance of replacing fixtures
like for like as far as is practical and to rectify
errors in a timeous manner. The processing of
disturbance allowance payments is also being
monitored more closely to minimise
inconvenience to tenants.
A trader encountered problems when
completing and returning a paper
application to obtain a licence, including the
incorrect fee being paid as the fees listed on
the Council’s website were out of date.
An apology was offered for the inconvenience
caused, the application processed and licence
granted.  The Council is in the process of placing
the application form online to help speed up
the process and the appropriate webpage has
been updated with the correct fees.
A resident changed their bank details and
experienced problems trying to change
their Council Tax Direct Debit details to the
new account.
An apology was offered to the complainant and
the Direct Debt set up.  The complainant asked
if there could be an online option to amend the
bank details for Council Tax rather than just an
option to set up a new one each time.  The
service is currently considering this feedback.
A visitor to a Recycle Centre encountered
problems in terms of parking at the site due
to excessive public use of the site that day.
An apology was offered to the visitor for the
problems encountered.  The site has been
upgraded to accommodate a larger volume of
people wanting to recycle and a daily update
was placed on the internet regarding footfall at
the site to reduce disruption.
41

Page 42

9 Compliments
Over 230 compliments were recorded cross-Council during the year and whilst they cannot
all be highlighted in this report, a selection is noted below.
• “I just wanted to let you know how impressed I am with the Recovery Development Worker.
Yesterday was the first time I spoke with him and I was really struck by his high level of
motivation, honesty and very obviously genuine desire to help and support people.  He is like
a breath of fresh air.  We don’t give positive feedback often enough so wanted to let you
know”
• “I’ve had an issue regarding arranging a special uplift and made a number of calls to your
Contact Centre. Every time I called your operators were very helpful and considerate. 
They’ve to be commended because every time they answer a call they don’t know what that
call is going to be about and have to rely on their considerable knowledge to try and answer
or resolve it”
• “Thank you to Waste Services for following up on a complaint I made about my waste bins
being missed.  They have not been missed since so thank you!”
• A number of people have complimented the Licensing Team regarding their help and
support regarding a short term let process for a number of hosts
• “I just want to highlight how fantastic the team at Ardrossan Library are. They go out of their
way to show a welcoming, friendly environment. The time and effort they put in with kids
(and adults alike) at the Monday toddler club is just brilliant. The kids look forward to it all
week long”
• “To the staff at Bartonholm Recycling Centre, every time I go there I see them out helping
folk get their discarded stuff away safely. And it’s always done with a smile. It must be a
tough job in all weathers but they’re still so cheery and polite! Good on you, guys.  You could
deliver lessons in customer care!”
• “I recently wrote to you regarding the little garden area outside Largs station.  I was
absolutely delighted to see that the area has been cleared of weeds and litter and bedding
plants have been planted.  It all looks really pretty so thank you to Streetscene who carried
out the planting. What a difference it makes”
• “I recently made a complaint to your Property Management department about some issues
with scaffolding. Just wanted to say it got fixed immediately and you even fixed up the gate.
Thank you to whoever came out to fix it. Absolute brilliant job”
• Exceptional feedback received for the Universal Early Years service which has resulted in an
employee being invited to present at a European Conference on infant feeding.
• “My family and I like everything your Refugee Team does for us Ukrainians. Just want to say
big thank you for everything. Incredible attitude towards us and everything is easy and
simple”  
42

Page 43

10 Glossary
Terms & Explanations
Stage One 
Stage One (also known as Frontline Resolution) aims to resolve straightforward customer
complaints that require little or no investigation. Any employee may deal with complaints at
this stage and they can be resolved via any channel. The main principle is to seek resolution
at the earliest opportunity and as close to the point of service delivery as possible. 
Stage One complaints must be responded to within 5 working days unless an extension (a
maximum of 5 additional working days) is requested and approved by a senior manager or
above. The Council should, however, always aim to resolve these types of complaints within
5 working days.
Stage Two
Not all complaints are suitable for Stage One and not all complaints will be satisfactorily
resolved at that stage. Complaints therefore handled at Stage Two (also known as
Investigations) typically require a detailed examination before the Council can state its
position. These complaints may already have been considered at Stage One, or they may
have been identified from the outset as being complex, serious or high risk and needing
immediate investigation. 
Stage Two complaints must be responded to within 20 working days unless an extension is
approved by senior manager in conjunction with the customer. Stage Two complaints
require a written response, signed by a senior manager.
Complaint criteria 
When an expression of dissatisfaction is received the Council determines if the issue falls
into one (or more) six complaint categories:
• A service the Council should be providing is not being provided or is not available
• A request for a service was provided but not to an appropriate standard 
• A request for service has not been answered or actioned within the agreed timescale
• A Council employee was rude, unhelpful or unprofessional
• A Council employee did not attend an appointment or call-out on a date/time agreed
• The complaint relates to a policy (internal or external)
If the issue being raised relates to one or more of the above, the matter is considered a
complaint and will be recorded and handled as such. If not, the matter will be handled as a
request for a service, observation or enquiry and actioned accordingly.
43

Page 44

44

Page 45

NORTH AYRSHIRE COUNCIL
30th May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Code of Corporate Governance Statement 2024/25
Purpose: To seek approval of Code of Corporate Governance Statement for the
Financial Year 24/25
Recommendation: That the Audit and Scrutiny Committee agrees to: (a) Review
and approve the Code of Corporate Governance Statement
2024/25.
1. Executive Summary
1.1 This report provides details of how we ensure good governance, including clear
accountability for delivering the desired outcomes for service users and communities.
Appendix 1 provides our ‘Code of Corporate Governance Statement 2024/25. 
2. Background
2.1 All local authorities have a statutory requirement to report publicly on the extent to which
they comply with their own Code of Governance on an annual basis, including how they
have monitored and evaluated the effectiveness of their governance arrangements in
the year and considered planned changes in the coming period.
2.2. The ‘Delivering Good Governance in Local Government Framework’ (CIPFA/Solace
2016) applies to annual governance statements.  It helps local government take
responsibility for developing and shaping an informed approach to governance and aims
to achieve the highest standards in a measured and proportionate way.  The Framework
is intended to assist authorities individually in reviewing and accounting for their own
unique approach. 
2.3. The overall aim is to ensure that:
• Resources are directed in accordance with agreed policy and according to
priorities.
• There is sound and inclusive decision making.
• There is clear accountability for the use of those resources in order to achieve
desired outcomes for service users and communities.
Agenda Item 6
45

Page 46

2.4. Appendix 1 contains our Code of Corporate Governance Statement 2024/25 which
aligns to the Framework and demonstrates how we are ensuring good governance and
transparent accountability. 
3. Proposals 
3.1 The Audit and Scrutiny Committee is requested to (a) Review and approve the Code
of Corporate Governance Statement 2024/25.   
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None.   
Environmental and Sustainability 
4.5 None.   
Key Priorities 
4.6 Effective governance is key to delivering our priorities outlined within our Council Plan
2023-28, specifically the Sustainable Council priority. 
Community Wealth Building 
4.7   None. 
5. Consultation 
5.1 The Executive Leadership Team were involved in the creation of the Code of
Corporate Governance.
Aileen Craig
Head of Service (Democratic) 
For further information please contact Isla Hardy, Team Manager (Corporate Policy and
Performance) on 01294 324035. 
Background Papers
46

Page 47

None.
47

Page 48

48

Page 49

Code of Corporate
Governance 
2024/25
Agenda Item 6
49

Page 50

Code of Corporate Governance 2024/25  Page 1 of 13 
Delivering Good Governance in Local Government – 2024/25 
This document details how North Ayrshire Council complies with the Delivering Good Governance in
Local Government: Framework (CIPFA/Solace, 2016). 
The Framework supports local government to take responsibility for developing and shaping an
informed approach to governance, aimed at achieving the highest standards in a measured and
proportionate way. It assists authorities individually in reviewing and accounting for their own
unique approach. The overall aims ensure: 
• Resources are directed in accordance with agreed policy and according to priorities.
• There is sound and inclusive decision making.
• There is clear accountability for the use of those resources in order to achieve desired
outcomes for our service users and communities. 
The Framework applies to annual governance statements prepared for the financial year 2016/17
onwards. 
For further information please contact: 
The Corporate Policy, Performance and Elections Team
North Ayrshire Council
Tel: 01294 310000
Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk 
50

Page 51

Code of Corporate Governance 2024/25  Page 2 of 13 
A. Behaving with integrity, demonstrating strong commitment to
ethical values and respecting the rule of law
Demonstrating strong commitment to ethical values
• New Elected Members are provided with a full Induction Programme which includes all aspects of
conduct. There is an extensive programme of inductions at the outset of the new Council
Administration. Thereafter, sessions are provided on a regular basis. 
• All Elected Members have access to Continuing Professional Development discussions and the
opportunity to participate in self/360 assessments to review and support their ongoing development.
In addition to this, a series of development events are provided to further support Elected Members’
Development. A calendar of events on a variety of topics is arranged and promoted to Elected
Members. Online guides and e-learning are also available.
• All employees including Chief Officers participate in ‘Our Time to Talk’ personal performance
discussions which provide the opportunity to discuss the focus of work, how this will be done
(behaviours linked to our Staff Values) and what development is required to support this. This is an
annual discussion which can be supported throughout the year by 121/supervision discussions and a
mid-year review as required.
• The Council invests in leadership and management development by hosting a Leadership Academy.
This provides aspiring, first, middle and strategic leaders, including Chief Officers and Elected
Members, with a variety of development interventions which enhance, refresh and develop their skills,
knowledge and behaviour.
• There is a Code of Conduct for employees.
• The Code of Conduct for Councillors sets out the minimum standards of conduct that are expected
from Elected Members and provides advice and guidance on registerable interests and on the
declaration of interests. The Code also sets out the sanctions that can be applied by the Standards
Commission where a breach of the Code occurs. Elected Members are provided with quarterly
updates from the Standards Commission.
• The Local Government Act 2000 and the Code of Conduct for Councillors set out the categories of
interests, financial or otherwise, that Councillors of Scottish Local Authorities must register. This
register is available for inspection by members of the public. In compliance with the Act and relevant
Regulations, the 33 Elected Members of North Ayrshire Council have registered interests with the
Proper Officer of the Council. The Register of Interests and notifications of Declarations of Interest are
available for inspection. Reports on Elected Member Training are submitted to the Executive
Leadership Team (ELT) and on an annual basis to the Audit and Scrutiny Committee.
• The Council has approved Guidelines for Member-Officer Relations (incorporating the Protocol on
Member/Officer Relations from the Councillors’ Code of Conduct). This is subject to annual review as
part of the Council’s review of governance documents.
• Declaration of Interest is a set item on all Committee Meeting Agendas. This is to be completed by all
Elected Members, informing of any issues in which they may benefit.
• There is a Whistle Blowing policy in place for employees, this was reviewed in 2020 and again in 2022
in line with accessibility requirements. 
• A Media Protocol is in Place. 
51

Page 52

Code of Corporate Governance 2024/25  Page 3 of 13 
• The People Strategy, “Our People Connect”, was designed by our employees for our employees. This
outlines priorities that will engage and support the transformation of the Council to be a leaner, more
efficient and higher performing organisation where people can develop and thrive. 
• Our Staff Values of Focus, Passion and Inspiration are key to our People Strategy “Our People
Connect”. They are now fully embedded in everything we do each day and visible when logging onto a
laptop or desktop, poster or wall displays, lanyards etc. In addition to this they are embedded in our
recruitment process and throughout our development interventions (such as courses and “Our Time
To Talk” personal development review discussions). 
Respecting the rule of law
• Strategic decision-making is governed by the Council’s key constitutional documents which are subject
to regular review. The governance documents were approved by Council in May 2022 and reviewed in
May 2023 and are scheduled for review in May/June 2024. The key documents are the Scheme of
Administration, The Standing Orders for Meetings and Proceedings of the Council, the Standing Orders
relating to Contracts and Contract Procedure Rules and the Scheme of Delegation to Officers. 
• The Council’s Cabinet is the key strategic decision-making committee, comprising the Leader of the
Council, the Depute Leader and four Members of the Administration.
• The roles and responsibilities of the Council’s Audit and Scrutiny and Appeals Committees are set out
in the approved Scheme of Administration.
• The Head of Service (Finance) is appointed as the Section 95 Officer who is responsible to the authority
for the proper administration of financial affairs as stated within the Local Government (Scotland) Act
1973.
• The Head of Service (Democratic Services) is appointed as the Monitoring Officer.
• The Head of Service (Democratic Services) is appointed as RIPSA Senior Responsible Officer (SRO). The
SRO ensures compliance with the terms of The Regulation of Investigatory Powers (Scotland) Act 2000
(RIPSA) and associated legislation.
• The Chief Social Work Officer is appointed in accordance with Section 3 of the Social Work (Scotland)
Act 1968.
• The Council has appointed a Chief Planning Officer.
• The Head of Service (Education) is appointed as Chief Education Officer in anticipation of the
commencement of Section 25 of the Education (Scotland) Act 2016.
• The Revised Remuneration Policy Guidance is in place.
• The Counter Fraud and Corruption Strategy is in place. 
• A Data Protection Officer (DPO) is appointed. The DPO ensures compliance with the General Data
Protection Regulation (2018) and the Data Protection Act (2018) legislation. 
52

Page 53

Code of Corporate Governance 2024/25  Page 4 of 13 
B. Ensuring openness and comprehensive stakeholder engagement
Openness
• Our Council Plan 2023-28 was approved by Council on 21st June 2023 and sets out our strategic
approach to making North Ayrshire a fairer and more equal society. This sets out our vision, mission
and four priorities up to 2028.
• We have 26 Council Plan Performance Indicators to ensure that progress on the Council Plan is
managed and scrutinised. Targets have been set where appropriate for each of the indicators to
ensure we can monitor progress of our priorities. Progress on the Council Plan is also scrutinised
through the half yearly Council Plan Progress Reports sent to the ELT, Cabinet and the Audit and
Scrutiny Committee. These are published on the performance pages of our website. In addition,
summary reports are scrutinised by the ELT at Quarter 1 and Quarter 3.
• Council Plan actions are high-level five-year actions as listed within the Council Plan 2023-28 and are
supported by relevant strategies.
• The Council’s Annual Performance Report provides a summary of our performance during the year and
is available on our website.
• Financial information including annual accounts is published on our website.
• Our Annual Governance Statement is approved annually by the Audit and Scrutiny Committee and
published on our website.
• Our Performance Management Strategy 2023-28 aligns to our Council Plan and is published on our
website. It outlines current procedures and planned activities to drive continuous improvement for the
people of North Ayrshire.
• Our Children’s Services Planning includes our Children’s Rights Report and our Child Poverty Action
Plan 2023-26. Our Children’s Services Plan outlines our aims and priorities to safeguard, support and
promote the well-being of children and to make North Ayrshire the best place in Scotland to grow up.
Our Children’s Rights Report emphasises our commitment to promote and protect children and young
people’s rights in line with the UN Convention on the Rights of the Child (UNCRC). Our Child Poverty
Action Plan takes account of the actions we are taking with partners to address child poverty in North
Ayrshire. Progress is reported to the Childrens Services Strategic Partnership (CSSP), Integrated Joint
Board and North Ayrshire Council Cabinet.
• Links to My Local Council website are published which provide our residents with Local Government
Benchmarking Framework (LGBF) performance information and comparisons to other local
authorities. Information on our performance within the LGBF is included within our suite of public
performance reporting, in particular within our annual LGBF report published as part of the Council
Plan Year-End Progress Reporting.
• There is a presumption that all committee business is open to the public except where required by law
to be in private. Council/Committee meetings which are open to the public are also live streamed to
the internet and/or available to view as a recording following the meeting. Owing to the pandemic,
Committee meetings resumed on a remote basis from June 2020 and since then both Council and
Committee meetings have been streamed live with recordings available for viewing thereafter. The
Council meeting in September 2022 agreed that “hybrid meetings” should be the default position for
meetings whereby some Members attend the meeting in person and others may join remotely. This
improves accessibility and participation. A hybrid meetings protocol is in place.
53

Page 54

Code of Corporate Governance 2024/25  Page 5 of 13 
• Through our commitment to the Community Empowerment (Scotland) Act 2015, the Council’s
Community Planning website has been developed to share information and research about the work
of the Community Planning Partnership, Locality Planning, our key aims and objectives and align with
the requirements of the Act.
• The Council has separate schemes for reporting complaints, compliments and customer feedback.
• Two complaint reports are submitted to the Audit and Scrutiny Committee each year and trends or
issues fed back to services to identify improvements. Complaint handling performance is also recorded
regularly in Pentana. The Council has a dedicated Complaints Manager who supports Chief Officers,
Senior Managers, Elected Members, complaint handlers and acts as liaison with the Scottish Public
Services Ombudsman.
• All inspection reports are reviewed by Cabinet and the Audit and Scrutiny Committee.
• The Council’s Publication Scheme and guidance on submitting Freedom of Information and
Environmental Information requests are available on the Council’s website.
• Guidance on submitting Subject Access Requests is available on the Council’s website.
• Open Data is published on the Council’s Open Data Portal, allowing members of the public to access
information on various council services ranging from information such as location of libraries to
performance related matters such as contact centre call performance.
• Elected Members have access to data on Pentana on request allowing them to view progress of the
Council Plan indicators. 
Engaging comprehensively with institutional stakeholders
• The Council is committed to engaging in a meaningful way with its communities so that it can
understand and respond effectively to local needs and it is committed to the principles of the National
Standards on Community Engagement.
• The Community Planning Partnership works closely with the Consultation Institute. Accredited training
on best practice in community engagement and consultation has been given to a range of Council and
partner employees.
• The Council is committed to supporting the establishment and work of Community Councils and their
role in Locality Partnerships as well as supporting Locality Planning in its own right as the Council’s
scheme of decentralisation.
• The Community Planning Partnership website contains The Engagement Hub and a consultation
calendar which brings all partner consultations together in a searchable format and gives feedback on
consultations.
• The Community Engagement Network of the Community Planning Partnership has been refocused and
aims to ensure partners meet the revised National Standards for Community Engagement.
• The North Ayrshire Health and Social Care Partnership Integration Joint Board (IJB) is the governing
body of the North Ayrshire Health and Social Care Partnership. It has delegated responsibilities from
North Ayrshire Council and NHS Ayrshire and Arran.
54

Page 55

Code of Corporate Governance 2024/25  Page 6 of 13 
Engaging with individual citizens and service users effectively
• The Community Planning Partnership’s People’s Panel is issued to obtain the public’s views on a range
of issues. The People’s Panel is a sample of 1,000 people living in more deprived areas and 1,000
residents is less deprived areas. This survey is carried out every two years to obtain views on the
Community Planning Partnership’s three key priorities, in addition to surveys on particular issues.
Engagement and consultation is at the heart of the Community Planning Partnership and is driven
through the Engagement Centre of Excellence Programme which includes training, digital resources,
and links to key strategies and approaches. For example, the Youth Participation and Citizenship
Strategy, Older People’s Forum and Community Engagement Network are all key examples of this
work. There is now an online ‘Engagement Hub’ on the Community Planning website, comprising of an
online engagement list, events calendar, community and partner resources and information about the
CPP’s Participation Approach.
• The Council routinely engages with our residents on our services. This is also achieved through a range
of groups such as Parent Councils, Tenants Associations, Ayrshire Ethnic Minority Community
Association and the Access Panel. 
• The establishment of Locality Partnerships has made Community Planning more accessible to local
people.
• Increased use of social media through Locality Facebook pages, the Community Planning Partnership
Twitter account and partner use of Community Planning hashtag supports communication with a
wider audience.
• Participatory Budgeting is an approach to deepening engagement with residents which delivers real
influence for individuals and communities and the Council has made significant commitment and
investment in this work. 
• The North Ayrshire Community and Locality Planning Model extends and deepens engagement with
individuals and participation by communities by: co-defining the issues; co-producing the responses;
and co-delivering the solutions.
• We currently use the Consul application to run Shaping North Ayrshire, our online participation forum
allowing residents the opportunity to provide us with feedback on current topics.
• Application of the Place Standard allows individuals and communities to express how it feels to live in
local communities and to shape the development of community and spatial planning in their area.
• Customer satisfaction surveys are carried out by Customer Services on a regular basis to measure
satisfaction levels and receive comments in relation to the service provided. A report is produced and
analysed by our Complaints Manager in conjunction with our Senior Manager (Customer Services) and
is used to form an improvement action plan. 
55

Page 56

Code of Corporate Governance 2024/25  Page 7 of 13 
C. Defining outcomes in terms of sustainable economic, social, and
environmental benefits 
Defining outcomes
• The Council’s vision and mission outlined in Our Council Plan 2023-28 links strongly to the North
Ayrshire Community Planning Partnership’s (CPP’s) shared vision of ‘North Ayrshire – A Better Life’.
• Our Council Plan 2023-28 was approved by Council in June 2023. Our vision and mission in Our Council
Plan are: 
o Vision: ‘A North Ayrshire that is fair for all’
o Mission: ‘Working together to improve the lives of our people in North Ayrshire’
• Our Council Plan has four interlinked and interdependent priorities:
o Wellbeing – to transition to a wellbeing economy, delivering prosperity, wellbeing and
resilience for local people.
o Communities and Local Democracy – We will have active, inclusive and resilient communities.
o Climate Change – To achieve net zero by 2030.
o A Sustainable Council – A community Wealth Building Council that is efficient and accessible,
maximising investment and focusing resources towards our priorities.
• The role of the Audit and Scrutiny Committee and ELT/ Chief Officers Leadership Team is to scrutinise
the findings from the various performance reports. We regularly report on the following to ensure
effective scrutiny:
o Locality Outcome Improvement Plan (LOIP) Progress Reports.
o Locality Partnership progress reports.
o Council Plan Progress Reports - six monthly reports to Cabinet and the Audit & Scrutiny
Committee.
o Council Plan Annual Performance Report.
o Local Government Benchmarking Framework.
• As part of the recent self-evaluation work undertaken by the Audit and Scrutiny Committee, a standing
agenda item to cover areas which the Committee would like to have addressed has been added to the
committee agendas.
• We utilise the Pentana online performance management system to track and manage Council
priorities and measures.
• The Council Plan Performance Management Framework (PIs) is reviewed regularly. The Council Plan
actions are as published within the Council Plan 2023-28 and are high level actions over five years.
They are supported by strategies within the Council.
• Operational Plans are reviewed on an annual basis.
• Strategic risks and control factors are reported to Cabinet.  
56

Page 57

Code of Corporate Governance 2024/25  Page 8 of 13 
Sustainable economic, social and environmental benefits
• The Community Wealth Building Strategy has been refreshed for 2024-27 and is available on our
website. Community Wealth Building is central to our Council Plan 2023-28.
• Our Local Outcomes Improvement Plan’s clear focus has been agreed by Community Planning partners
across themes of Wellbeing, Work and World with an overarching focus on reducing inequalities and
working in partnership.
• The Sustainable North Ayrshire Strategy 2024-27 is established.
• The Local Biodiversity Action Plan 2019-31 is in place.
• The Climate Change Steering Group established, comprising senior management representatives from
each Council Directorate, Community Planning Partners, private sector and other agencies, with
meetings taking place every four months.
• The Annual Climate Change Reporting Duty is submitted to Scottish Government.
• Our Council Plan includes performance indicators in relation to carbon emissions and amount of
energy generated from low carbon sources.
• Our Committee report template includes requirement for evaluation of climate change impacts to
ensure sustainability impacts are embedded within our decision-making processes. 
• The Council is committed to using the Local Government Benchmarking Framework (LGBF)
Performance Indicators to scrutinise performance on our priorities against all local authorities within
Scotland.
• The Housing and Public Protection Service complies with the Scottish Regulators Strategic Code of
Practice. The integrated regulatory functions within the service (Building Standards, Environmental
Health and Trading Standards) can demonstrate an effective contribution towards the Council’s
approach to sustainable economic growth as well as maintaining and promoting a prosperous, fair and
safe society. 
D. Determining the interventions necessary to optimise the
achievement of the intended outcomes 
Determining interventions 
• The information submitted to Committees is discussed in detail at ELT to ensure management
oversight and thereafter at pre-Agenda meetings (except in the case of regulatory committees) that
are held one week prior to the formal meetings. This enables any additional information to be sought
to allow a fully informed decision to be taken at the Committee. 
• Each report should indicate the justification for each action proposed and consultations undertaken in
its development, together with feedback from consultees. Reports also contain separate sections on a
range of implications (financial, socio-economic duty, human resources, legal, equality, children and
young people, sustainability, Community Wealth Building, the Council’s key priorities and Community
Benefit). Guidance for Report Authors provides information on the completion of these elements
within these required fields in a committee report. 
57

Page 58

Code of Corporate Governance 2024/25  Page 9 of 13 
Planning interventions
• Council Plan six monthly progress reports.
• Operational Plan reports to Heads of Service and Executive Directors.
• Use of Pentana online performance management system allows us to ensure we are achieving
acceptable levels of performance, identify opportunities for continuous improvement and ensure we
have plans in place to improve underperforming areas.
• Council and Operational Plan performance reports contain trend information on Performance
Indicators.
• Strategic risks and control factors are reported to Cabinet.
• Risk Management Strategy is in place and available on our website.
• The Community Planning Partnership Risk Register has been reviewed to reflect the refreshed Local
Outcomes Improvement Plan 2022-30.
• The Workforce Strategy, ‘our approach to workforce planning’, sets out how our workforce will
support the delivery of the Council’s ambitions within the available financial resources and builds on
the workforce planning approach carried out at a service level. 
• ‘A Workforce for the Future’ HR guide sets out our Workforce Planning approach and is published on
our intranet to support managers and Heads of Service in shaping their current and future workforce
to ensure delivery of efficient and effective services and is a significant factor in how we transform our
Council to deliver our financial challenges. In order to be successful, it is key for workforce planning to
flow from the Council Plan and link to both people management and operational processes.  
• Long Term Financial Outlook – The Council’s Long-Term Financial Outlook outlines the financial
challenges facing the Council over the next 10 years and is reported to Cabinet. 
• Medium Term Financial Plan – The Council’s Medium-Term Financial Plan provides an overview of the
Council’s anticipated financial position for the next three financial years. This is approved by Council
annually. A copy of the budget book is published on our website each year.
• Capital Investment Programme – The Council’s Capital Investment programme provides an overview
of the capital projects the Council is investing in over the 10-year period and associated funding
sources. The 10-year Capital Investment Programme is reviewed and approved by Council annually. (A
review of the 10-year General Services Capital Investment Programme 2023/24 to 2030/31 was
presented to Council on 1 March 2023.)
• Capital Investment Strategy – The Council’s Capital Investment Strategy provides an overview of how
capital investment plans, financing and treasury management activity contribute to the infrastructure
and provision of services for the benefit of North Ayrshire communities and citizens. (The refreshed
Capital Investment Strategy 2023 – 2031 was approved by Council on 1 March 2023. Our Capital
Investment Programme can be found on our website)
• Asset Management Plans are in place. 
58

Page 59

Code of Corporate Governance 2024/25  Page 10 of 13 
Optimising achievement of intended outcomes
• Regular reporting of financial performance to Cabinet.
• Production of annual accounts and publication on our website.
• Local Financial Returns. 
E. Developing the entity’s capacity, including the capability of its
leadership and the individuals within it 
Developing the entity’s capacity 
• The Leadership Academy provides skills, knowledge and behavioural development for leaders at all
levels. Managers regardless of grade can, if committed to their continuous learning and supported by
their manager, progress through the levels of the Leadership Academy from First to Strategic utilising
development opportunities and accessing tailored interventions for career progression. This provides
an opportunity to build leadership capacity and grow our own talent.
• The Connected Leadership Network is an active Teams channel which provides an opportunity for
senior managers to gain support from others as well as sharing knowledge, ideas and suggestions. This
has been a successful addition to the Leadership Academy and supports the digital agenda. 
• The Chief Executive hosts a Connected Leadership Conference three times per year. This provides an
opportunity for sharing of information and increased engagement and collaboration opportunities
with managers from across the Council. 
Developing the capability of the entity’s leadership and other individuals
• Each employee has a Role Profile which provides information on the expectations of the job. This
supports the development of skills, knowledge and behaviours of our employees.
• All governance documents including the Scheme of Delegation to Officers and the Financial
Regulations documents are reviewed annually and published on our website. 
• All employees throughout the Council participate in “Our Time To Talk” performance review meetings
which provide the opportunity to discuss the focus of work. It ensures managers and employees take
time, at least once per year, to reflect and most importantly ’TALK’ about how the employee is getting
on at work. This is an annual discussion which can be supported throughout the year by
121/supervision discussions and a mid-year review as required.
• New Elected Members are provided with a full Induction programme which includes all aspects of
Council business, such as overview of Council meetings, introduction to the ELT and the role of the
councillor. 
• A series of development events are provided to further support Elected Members Development. A
calendar of events on a variety of topics is arranged and promoted to Elected Members, in addition to
online guides and e-learning.
59

Page 60

Code of Corporate Governance 2024/25  Page 11 of 13 
• Elected Members are invited to participate in an annual development discussion in addition to an
opportunity to participate in self/360 assessment. This allows identification of development activity to
support their role and provides feedback on their individual performance utilising the 360 tool.
• The Community Planning Partnership’s Learning and Development Plan contains leadership
development. 
F. Managing risks and performance through robust internal control
and strong public financial management
Managing risk
• The Strategic Risk Register refreshed annually and approved by Cabinet, and subject to a six-month
progress update. A Corporate Risk Register is refreshed annually and approved by the ELT and also
subject to a six-month progress update. Operational Risk Registers are updated by services six-
monthly. There are escalation and de-escalation processes in place between the registers.
• The Corporate Risk Management Group, with senior representation from all Directorates, meets six-
monthly to review and update risks and their associated risk management action plans. Other related
business will also be considered where this could enhance the organisational risk posture.
• The Community Planning Partnership Risk Register was revised in 2022 to tie in with Local Outcomes
Improvement Plan 2022-30. 
Managing performance
• Council Plan Progress Reports are scrutinised by the ELT, Cabinet and the Audit and Scrutiny
Committee. The reports are produced in a ‘magazine style’ format to make the information as
engaging and accessible as possible. 
• Performance indicators (including targets where appropriate) and actions are included within the
Council Plan Performance Framework and Council Plan. All updates to the framework are detailed
within the six-monthly Progress Reports and reported to ELT, Cabinet and Audit and Scrutiny for full
transparency.
• The six-monthly Council Plan Progress Reports focus on outcomes as well as ongoing activity and
outputs. Case studies are included. Information on audits, inspections and accreditations is included to
show how we performing. Benchmarking activity takes place via the LGBF indicators included in the
Performance Management Framework and the annual LGBF report.  This ensures we learn from others
and continually improve. Links are provided to additional information where appropriate. This holistic
approach provides a well-rounded view of performance within our Council that includes valuable
context.
• The six-monthly Council Plan Progress Reports (Quarters 2 and 4) as well as the Annual Performance
Report and update on Local Government Benchmarking Framework (LGBF) performance are published
on our website. Scrutiny is invited from residents and contact information is contained in the reports.
• Operational Plans within services align directly to the Council Plan and are scrutinised by relevant
Senior Managers and Heads of Service.  
60

Page 61

Code of Corporate Governance 2024/25  Page 12 of 13 
• Benchmarking activity is undertaken based on the Local Government Benchmarking Framework (LGBF)
as well as through specific groups. In addition to quantitative comparisons, outcome-based
benchmarking also takes place.
• Our Performance Management Strategy 2023-28 is published on our website and aligns to Our Council
Plan 2023-28.
Robust internal control
• The Council has a framework of Internal Controls embedded within services, underpinned by Financial
Regulations and Codes of Financial Practice which are approved by the Council.
• Internal Audit establishes an annual risk-based plan of work to review controls across the Council. This
is approved by the Audit and Scrutiny Committee and is subject to a mid-year review process.
• All audit findings are reported to the Council’s Audit and Scrutiny Committee.
• The Council has a Corporate Fraud Team which investigates all allegations of fraud and error against
the Council. Six-monthly update reports are provided to the Audit and Scrutiny Committee. Regular
review of the Counter Fraud and Corruption Strategy is undertaken, with the most recent review
taking place in September 2022.
• An annual report and assurance statement is provided by the Chief Internal Auditor to the Audit and
Scrutiny Committee.
• An annual report on RIPSA is provided to ELT and Cabinet and we provide an annual statistical return
on use of investigatory powers to Investigatory Powers Commissioner’s Office (IPCO).
Managing data
• The Council’s Records Management Plan (RMP) was approved by the Keeper of the Records of
Scotland in 2015 and a successful interim assessment conducted in 2018, with the outcome report
published on the Council website. A further successful interim assessment has been conducted in
2022/23 and the outcome will be uploaded to the Council website once released by the National
Records for Scotland.
• The Council maintains an Information Asset Register (IAR) which is kept under regular review.
• The Council has a process for undertaking Data Protection Impact Assessments (DPIA) with approval
required from DPO and annual reviews embedded to ensure compliance with Article 35 of the UK
GDPR.  
61

Page 62

Code of Corporate Governance 2024/25  Page 13 of 13 
G. Implementing good practices in transparency, reporting and
audit to deliver effective accountability
Implementing good practice in transparency
• We publish our public facing reports on our website.
• Committee Reports and webcasting is on our website.
• There is a presumption that all committee business is open to public except where required by law to
be in private.
• We publish open datasets. 
Implementing good practices in reporting
• Annual Governance Statement.
• Six monthly Council Plan Progress reports and Annual Performance Reports produced, with updates to
accompanying Performance Management Framework reported in detail to the ELT, Cabinet and the
Audit and Scrutiny Committee.
• Community Planning Partnership Annual Performance Report.
• Health and Social Care Partnership Annual Performance Report.
• Annual Accounts demonstrates best practice according to external auditors. 
Assurance and effective accountability
• The Annual Governance Statement is approved by the Audit and Scrutiny Committee prior to inclusion
within the annual accounts.
• Any recommendations by External Audit are reported to the Audit and Scrutiny Committee and
progress with implementation is monitored by Internal Audit and also report to the Committee on a
bi-annual basis.
• Internal Audit work is reported to the Audit and Scrutiny Committee on a quarterly basis.
• The Council’s Internal Audit Team received an independent External Quality Assessment in July 2022
which demonstrates conformance with the Public Sector Internal Audit Standards. This needs to be
carried out at least every five years, with period self-assessments also carried out by the Chief Internal
Auditor.
• The Chief Auditor has rights of access to the Chief Executive and the Chair of the Audit and Scrutiny
Committee in relation to any audit matter.
• The Data Protection Officer has rights of access to the Chief Executive and the highest management in
relation to any personal/sensitive data protection matters. 
62

Page 63

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Accounts Commission’s Report: Local Government in
Scotland: Financial Bulletin 2022/23
Purpose: To inform the Audit and Scrutiny Committee of the findings of
the recently published report.
Recommendation: That the Committee i) notes the findings of the recent Accounts
Commission report, and (ii) notes the current position of North
Ayrshire Council in relation to the findings.
1. Executive Summary
1.1 The Accounts Commission published its 2022/23 local government finance bulletin in
January 2024. The report provides a high-level independent analysis of the financial
performance of local authorities during 2022/23, including funding and expenditure for
2022/23, financial position at the end of 2022/23 and the financial outlook from
2023/24. A link to the report is attached below:
Local Government in Scotland: Finance Bulletin 2022/23
1.2  The report analyses the annual accounts produced by local authorities, together with
the reports of each body’s external auditors, to identify their relative performance,
highlight the challenges faced and assess their responses to these challenges. The
report has a summary of key messages and recommendations, with more detail
provided in two parts:
• Part 1 – Funding and outturn in 2022/23; and
• Part 2 - Councils’ financial position and outlook from 2023/24.
1.3  Appendix 1 provides relevant North Ayrshire Council feedback on each of the key
messages identified.
2. Background
2.1 The report provides a high-level independent analysis of the financial performance of
local authorities during 2022/23, including funding and expenditure for 2022/23,
financial position at the end of 2022/23 and the financial outlook from 2023/24.
Agenda Item 7
63

Page 64

2.2  A summary of the key messages and recommendations is provided within the report
with further information provided in 2 main sections: 
• Part 1 – Funding and outturn in 2022/23; and
• Part 2 - Councils’ financial position and outlook from 2023/24. 
2.3 The key messages within the report are summarised below: 
• Scottish Government revenue funding to councils fell by £619m (2.8%) in real
terms; 
• Councils received more core revenue funding, increasing by £87m (0.7%) in real
terms. However, an increasing proportion is ring‑fenced or provided with the
expectation it will be spent on specific services; 
• Pressure on public-sector capital budgets presents risks to the viability of local
government capital programmes; 
• Councils’ anticipated budget gaps for 2022/23 were over £476m with increased
reliance on savings and reserves to balance budgets; 
• Overall usable reserves grew to £4.45 billion with half of councils reporting
increases in 2022/23; 
• Although no council has been identified as unstable in the short term, Scottish
councils face unprecedented financial and demand pressures; 
• While councils’ medium and long term financial plans recognise the difficult
financial context, some are experiencing significant resistance when seeking
service reductions to balance budgets; and 
• The Verity House Agreement includes a commitment to offer councils longer term
funding and greater local financial flexibility. 
2.4 The key recommendations indicate that councils should: 
• Prioritise the achievement of recurring savings and avoid reliance on non-recurring
savings; 
• Ensure that management commentaries include a clear link between the budget
outturn and the financial performance in the accounts; 
• Provide clear statements on reserves policies and the purposes of committed
reserves; 
• Ensure effective engagement with communities on the options to achieve a
balanced budget; 
• Report on financial resilience, including use of financial resilience indicators within
medium and long term financial plans; and
64

Page 65

• Work with the Scottish Government to develop a fiscal framework to enhance
clarity and certainty of future years’ budgets. 
3. Proposals 
3.1 It is proposed that the Committee i) notes the findings of the recent Accounts
Commission report, and (ii) notes the current position of North Ayrshire Council in
relation to the findings. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Accounts Commission report highlights the reliance of local government on
Scottish Government grant funding and the need for the development of robust
medium and longer term financial plans to develop sustainable solutions to bridge
anticipated future funding gaps. North Ayrshire Council develops medium term
financial plans on a three year rolling basis and Council has approved a Long Term
Financial Outlook covering the next 10 year period. The financial sustainability of the
Council is monitored regularly and reported to Cabinet throughout the year. 
Human Resources 
4.2 As part of a sustainable financial strategy the Council continues to actively manage the
size of its workforce. Regular communication and consultation takes place with the
workforce and Trade Unions. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 Equality impact assessment are carried out for all options identified as part of the
medium and long term financial plans. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 In addressing the financial challenges which it faces, the Council seeks to minimise the
impact on delivering its key priorities. 
Community Wealth Building 
4.7 None. 
65

Page 66

5. Consultation 
5.1 Executive Directors are consulted in the development of the Medium and Long term
Financial plans and the development of investment and recovery and renewal
strategies. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551 or DavidForbes@north-ayrshire.gov.uk. 
Background Papers
None 
66

Page 67

Appendix 1
Local Government in Scotland Financial Bulletin 2022/23 
Part 1 Funding and outturn in 2022/23 
Ref Key Message NAC Feedback
F1 Despite councils receiving more funding and income in cash
terms, due to high inflation in 2022/23 total revenue funding from
all sources fell by £619 million (2.8 per cent) in real terms to
£21.3 billion compared to 2021/22. 
During 2022/23 NAC received a total of £347.192m income from
the Scottish Government, including General Revenue Grant, Non
Domestic Rates and Specific Grants. Although this was an
increase of £13.180m from 2021/22, due to high inflation, this
represented a 2.6% real terms reduction in grant income.  
F2 Councils received more core revenue funding from the Scottish
Government than in 2021/22, rising from £12.1 billion to £12.2
billion (0.7 per cent) in real terms. However, an increasing
proportion is ring‑fenced or provided with the expectation it will
be spent on specific services. This means that the amount of
funding available for councils to spend freely on local priorities is
reducing. There are commitments in the Verity House
Agreement to move to a default position of removing ring‑fencing
or direction of funding wherever possible. 
During 2022/23 £184.084m (53%) of Scottish Government grant
funding was identified as ringfenced or provided with the
expectation that it would be spent on specific services, including:
HSCP £90.803m, Support for Teachers £70.835m, ELC
Expansion £13.093m, PEF £4.211m, Child Payment Bridging
£2.575m and DHP £2.477m.  
F3 There is pressure on all public-sector capital budgets, and this
presents risks to the viability of local government capital
programmes, many of which impact on key services (eg, the
construction and maintenance of schools, libraries, roads).
Capital funding from the Scottish Government rose in 2022/23
but remains lower than before the pandemic and has been
volatile over the past decade. Driven by increased borrowing
councils’ capital expenditure increased in 2022/23 by 16 per cent
in cash terms to £3.6 billion. Borrowing costs have reduced in
recent years as many councils have used permitted financial
flexibilities to reprofile debt payments. While helping with
immediate budget pressures, these decisions defer costs to later
years and do not tackle the underlying challenges to financial
sustainability. Additional borrowing also places further pressure
on revenue budgets over the longer term.
During 2022/23, NAC invested £66.978m in our General Fund and
HRA capital programmes. Major cost risks were reported across
the Capital Investment Programmes as a result of the uncertainty
arising from inflationary pressures and supply chain issues, which
impacted on tender returns, and the cost of materials across a
number of General Fund and HRA projects. 
In addition, upward movements on the interest rates applicable to
public sector borrowing presented further risks to the deliverability
of both the General Fund and HRA capital programmes over the
medium term resulting in an additional revenue cost of £1.132m
per year to support the additional costs of borrowing.
67

Page 68

Appendix 1
F4 At the time of setting their 2022/23 budgets, councils anticipated
budget gaps of over £476 million for the year, higher than the
previous year. Councils are increasingly having to rely on
savings and reserves to balance budgets. Achievement of
savings targets was good in 2022/23 and improved on 2021/22.
Greater transparency is required in the reporting of financial
outturn in council accounts, including savings performance. This
transparency and timely public engagement are essential as
councils make increasingly difficult decisions to reduce or stop
services to help balance budgets.  
As detailed in the Medium Term Financial Plan for 2022/23, the
budget gap for the year was £12.317m. This was met through a
3% Council Tax increase and the identification of net savings
totalling £9.876m. The indicative funding gaps for 2023/24 and
2024/25 were identified as £10.718m and £8.785m respectively. 
Part 2 Councils’ financial position and outlook from 2023/24 
Ref Key Message NAC Feedback
O1 Despite the financial pressures of recent years, half of councils
increased their usable reserves in 2022/23, and overall usable
reserves grew to £4.45 billion. This is driven by growth in
committed reserves. Some of this is remaining Covid-19 funding,
some is attributable to the permitted use of financial flexibilities
for the repayment of longer-term debt but there are also
indications councils are building up reserves to manage the
known financial challenges in future years. However, the lack of
transparency in some councils’ annual accounts makes it difficult
to draw firm conclusions on councils planned use of reserves. 
During 2022/23, NAC’s total usable reserves increased by
£22.439m to £135.680m. This was primarily related to the release
of £24.311m through the review of accounting arrangements for
PFI and similar contracts. These funds have been ringfenced to
help address the impact of construction cost volatility as part of
delivering the Council’s ambitious Capital programme, by helping
to mitigate the significant cost pressures and resultant revenue
budget gaps over the medium-term, support Workforce Planning
and invest in Child Poverty and Cost of Living interventions. 
O2 Local appointed auditors did not identify any councils in Scotland
as being financially unsustainable in the short term. However,
the financial outlook is extremely challenging with Scottish
councils facing unprecedented financial and service demand
pressures which present real risks for the future. Although
Scottish Government core funding increased in cash and real
terms in 2023/24, councils reported a significant increase in the
total budget gap to £725 million.  
NAC’s Medium Term Financial Plan for 2023/24 to 2025/26
highlighted an increase in the budget gap for 2023/24 from
£10.718m to £19.266m. This was addressed through the
application of a 5% Council Tax increase, the use of £3.410m of
reserves and the identification of £12.448m of savings. The
indicative funding gaps for 2024/25 and 2025/26 were identified as
£11.688m and £11.382m respectively. 
68

Page 69

Appendix 1
O3 Councils’ medium- and longer-term financial plans demonstrate
a clear recognition of the difficult financial context and the need
to continue to innovate at pace and make difficult decisions to
become more financially sustainable. But some councils are
already experiencing significant resistance when seeking to
make service reductions to balance budgets. This reinforces the
need for effective consultation and engagement with
communities on planned local service changes.  
NAC carries out a range of community engagement activities to
support the development of our medium term financial plans.
During 2023, NAC developed an on-line Budget Challenge tool
which provided citizens with the opportunity to set their own virtual
Budget. This helped demonstrate the challenges faced by the
Council in allocating financial resources across services against
the backdrop of funding constraints and cost pressures. This was
followed up by an on-line locality engagement session which
included representation from a range of community groups and
associations and additional engagement with young people around
the Budget challenges to determine what is important to them. 
O4 The Verity House Agreement includes a commitment to offer
councils longer term funding and greater local financial flexibility.
These proposed changes will be important, in providing greater
financial certainty to support better long-term planning and more
flexible direction of resources to meet local need. However, the
recent announcement of a proposed council tax freeze
significantly reduces discretion and flexibility at individual council
level. The impact this will have on financial sustainability is not
yet known, but councils have placed an increased reliance on
raising council tax to help deliver a balanced budget over the
past two years.  
NAC continues to engage with the Scottish Government at both a
political and officer level through COSLA and the Directors of
Finance group. There are ongoing discussions and progress
around various areas of financial flexibility including potential
changes to Council Tax through the multiplier and second homes
levy. Discussions continue on the feasibility of a tourist visitor levy
and budget discussions on the Verity House agreement, and what
this means within the context of budget conditions. 
The latest developments in these areas will be addressed as part
of the next iteration of the Medium Term Financial Outlook. 
69

Page 70

70

Page 71

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: 2022/23 External Audit Action Plan Update
Purpose: To invite Committee to note the updated actions identified in the
2022/23 External Audit Action Plan.
Recommendation: That Committee notes the updates to the agreed Action Plans as
outlined in Appendix 1.
1. Executive Summary
1.1 Audit Scotland’s Annual Audit Report and Report on the Best Value Thematic Work for
2022/23 were presented to Audit & Scrutiny Committee on 14 November 2023.
1.2 Audit Scotland’s reports included action plans in relation to the recommendations for
improvement identified during the course of the audit and full details of the proposed
management actions were appended to the reports.
1.3 Appendix 1 provides an update on the management actions taken to date and
provides updated target dates for any outstanding items.
2. Background
2.1 The 2022/23 audit of the Council’s accounts was conducted by Audit Scotland and
their reports on the Annual Audit and Best Value thematic work were presented to
Audit & Scrutiny Committee on 14 November 2023.
2.2 The recommended actions identified in the reports related to a range of issues,
including: 
• Review of Group accounting processes;
• Formal engagement of Heritage Asset valuer;
• Review of capital programme forecasting arrangements;
• Updating of Council Tax system reconciliation format;
• Review of publishing arrangement to comply with the 2021 Statutory Performance
Information Direction; and
• Review and promotion of dormant Charitable Trusts.
Agenda Item 8
71

Page 72

2.3  A review of the proposed management actions has now been undertaken and details
of the completed actions and their completion dates have been detailed in Appendix
1. Where any actions have not yet been completed, the appendix provides an update
on the proposed management action and the target date for completion. 
2.4  In summary, the updates note: 
• 2022/23 Annual Audit Report - All actions completed; 
• Best Value Thematic Report - Actions well advanced with the launch of the
Council’s newly designed website scheduled for September 2024. In addition, the
Performance Dashboard is being refreshed with a target date of 31 August 2024;
and 
• Charitable Trusts - Action is being addressed as part of a long term strategy to
ensure that the coordination of funding support across Council services is clear and
consistent. 
3. Proposals 
3.1 It is proposed that Committee notes the updates to the agreed Action Plans as outlined
in Appendix 1. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by maximising financial
flexibility to support the delivery of our priorities. 
72

Page 73

Community Wealth Building
4.7 None.
5. Consultation
5.1 Responsible Officers identified within the Audit and Best Value reports have been
consulted as part of the review.
Mark Boyd
Head of Service (Finance)
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
External Audit Reports on the 2022/23 Audit and Best Value Thematic Work – Audit &
Scrutiny Committee, 14 November 2023  
73

Page 74

Appendix 1
2022/23 Annual Audit Report
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
1 Group Accounting
We identified a number of issues
in our testing of group
consolidation adjustments.
Risk – If the group accounting
process is not improved, future
accounts could be mis-stated.
The Council should review its
group accounting process to
ensure the completeness
and accuracy of
consolidation adjustments
A full review of group
accounting procedures in line
with Code requirements will
be carried out ahead of the
close of financial year 2023-
24.
David Forbes, Senior
Manager -  Finance and
Revenues
31 March 2024
All accounting guidance in
relation to Group Accounting
has been reviewed, internal
procedures have been updated
accordingly and the group
boundary has been reviewed to
ensure correct treatment of all
group entities
Completed 31 March
2024
2 Heritage Asset Valuation
The Council engaged an external
valuer to value its heritage
assets. No formal letter of
engagement was issued setting
out the scope and objectives of
the valuer’s work.
Risk – The scope and objectives
of the valuation exercise could be
misunderstood, resulting in asset
values being mis-stated.
The Council should obtain a
formal engagement letter
from the Heritage Assets
valuer.
A formal process for the
identification of items to be
valued and scope of work to
be undertaken will be agreed
with the valuation contractors.
Lesley Forsyth, Senior
Manager – Information &
Culture
31 March 2024
With support from the Corporate
Procurement team, a formal
Letter of Engagement has been
issued to the valuation experts,
Lyon and Turnbull. 
The service will continue to
work with them to ensure that
North Ayrshire Museum’s
collection and the Council's
Heritage Assets are properly
assessed and we have
accurate, up to date valuation
data.
Letter of Engagement
issued 15 April 2024
74

Page 75

Appendix 1
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
3 Forecasting of capital
projects
Reprofiling for the General Fund
included £11.0 million for
Ardrossan Campus, £24.1 million
for Ardrossan North Shore and
315.2 million relating to a
corporate phasing adjustment
reflecting the degree of
uncertainty in the total
expenditure projections.
Reprofiling for the HRA mainly
related to New Builds of £42.5
million. 
Risk – the council is unable to
accurately forecast capital
expenditure.
The capital programmes
should be reviewed to reflect
the apparent optimism bias
that existed in 2022/23.
The Head of Finance will
continue to address the
optimism bias issue through
the CPAG group. Specifically,
as part of the Budget setting
process for 2024/25, a further
corporate adjustment will be
made to expenditure
forecasts, and this will be
evidence based from historic
patterns of expenditure and a
recognition of organisational
capacity.
Mark Boyd, Head of Finance
31 March 2024
During the development of the
Capital Investment Programme
2024/25 to 2033/34, the
phasing of expenditure was
reviewed to reflect historic
expenditure patterns and
organisational capacity. This
resulted in the rephasing of
approximately 19% of the
planned expenditure in both
2024/25 and 2025/26 for
delivery in later years, without
impacting on the overall value
of investment within the
programme. The actual levels
of expenditure will be
continually monitored and
reported to Cabinet throughout
the life of the programme.
Capital Investment
Programme 2024/25 to
2033/24 approved by
Council 28 February
2024.
4 Council tax property
reconciliation
The reconciliation between the
council’s records and assessor’s
data does not identify where the
data originates from, what it had
been reconciled to, or who had
performed the reconciliation and
when.
Risk – Reconciliations may be
incorrectly completed leading to
variances between council and
assessor records not being
identified.
The format of the
reconciliation between the
Council’s records and
assessor’s data could be
improved by clearly stating
where the data in the
reconciliation originates from,
what it has been agreed to,
the name of the officer
performing the reconciliation
and the date agreed.
The format of the year end
reconciliation between the
AVJB’s council tax register
and the Council Tax system
will be reviewed and updated.
David Forbes, Senior
Manager -  Finance and
Revenues
31 March 2024
A full review of all reconciliations
has been undertaken to ensure
consistency of content and
format with clear links to all
original source data.
Completed 31 March
2024
75

Page 76

Appendix 1
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
5 The Statutory Performance
Indicator (SPI) Direction
Our assessment has concluded
that the Council needs to publish
its response to Best Value
reports and audit and inspection
reports to fully comply with the
requirements of the new SPI
Direction.
Risk – the council may not
comply with the new requirement
to report its own assessment of
audit, scrutiny and inspection
body assessments and how it
has responded to these
assessments.
The Council needs to publish
its response to Best Value
reports and audit and
inspection reports to fully
comply with the requirements
of the 2021 Statutory
Performance Information
(SPI) Direction.
Inspections, audits, awards
and accreditations will be
included in our six monthly
Council Plan Progress
Reports which are published
on the Council’s website.
Isla Hardy, Team Manager -
Corporate Policy and
Performance
31 January 2024
Inspections, audits, awards and
accreditations are now included
in our six monthly Council Plan
Progress Reports with the initial
report for the new Council Plan
(Mid-Year 2023-24) approved by
Cabinet in January.  These
reports are published on our
website.  By including a summary
within the report, rather than a
list, it provides valuable context
around the audit or inspection,
the ability to cross reference with
Council Plan progress and note
key next steps.  It also gives the
Executive Leadership Team,
Cabinet and the Audit and
Scrutiny Committee an
opportunity to view the audits
and inspections holistically.
31 January 2024
76

Page 77

Appendix 1
BV Thematic Report
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
1 Vision
The council has acknowledged
that its website would benefit
from improvement and it is
currently being reviewed with a
view to being replaced by
Autumn 2024.
The Council should prioritise
concluding its website review
with a view to improving it as
soon as possible. This will
bring many benefits,
including raising more
awareness of its vision and
priorities.
The website redesign project
is currently progressing at
pace and the aim is to have a
Beta version live by Summer
2024 and the full version live
by Autumn 2024.  To improve
the visibility of the Council
Plan and Priorities the home
page will be revised to include
reference to our Council Plan
2023-28. 
Fiona Walker, Head of
People and ICT
Summer/Autumn 2024
Aileen Craig, Head of
Democratic Services
December 2023
The website home page has
been updated to include a link to
the Council plan within the
Council and Local Democracy
section.   This will remain as a
featured link on the homepage of
the newly designed website. 
The newly designed
website will have its Beta
launch in July 2024,
going fully live in
September 2024.
77

Page 78

Appendix 1
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
2 Performance
The Council has acknowledged
that the content of its
performance pages needs to be
refreshed and, in particular, its
Performance Dashboard needs
to be update. The Council also
recognises the need to improve
its website as a whole and is
working towards launching a new
website in Autumn 2024. In
addition, it plans to report the
results of, and its response to,
audit and inspection work in its
Council Plan progress report
updates going forward.
The Council should ensure
that all the performance
information published on its
website is up-to-date,
performance reports are as
timely as possible and audit
and inspection information is
easily accessible and
includes how the Council is
responding to
recommendations.
Website will be reviewed to
remove or replace out of date
information.  Audits and
inspections will be included in
six monthly Council Plan
Progress Reports published
on the site.
Isla Hardy, Team Manager -
Corporate Policy and
Performance
31 January 2024
The website has been reviewed
to remove out of date
information.  This mostly related
to historical pages from a
previous Council structure.  The
remaining pages will be able to
be more effectively managed.  A
process is in place to ensure our
reports are accessible under the
website regulations and able to
be uploaded once approved by
Cabinet following the call-in
period.  
Audits and inspections are
included in the six monthly
Council Plan Progress Reports. 
The Performance Dashboard is
currently offline as employees
require further training in Power
BI to support this sustainably. 
The information was previously
updated annually.  All information
is available through the six-
monthly Council Plan Progress
Reports.  We will aim to have the
dashboard refreshed over the
summer once Year End reporting
has been presented to Cabinet.
Completed 30 April
2024
Completed 31 January
2024
Target Date 31 August
2024
78

Page 79

Appendix 1
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
3 Citizen and community
engagement
The Council has published
locality impact reports for five of
its six localities. However, a
number of links to locality
planning information are not yet
available.
The Council should update
all locality planning
information and
corresponding links as soon
as possible.
The CPP website will be
reviewed to ensure all locality
planning information and links
are up to date. The
Community Planning
Partnership website will be
refreshed with new Locality
Partnership pages.
Jacqueline Greenlees,
Senior Manager –
Community Planning
31 December 2023
The CPP website has now been
reviewed and refreshed, with
new Locality pages produced
which include up to date
information. Any out of date
reports or links have been
removed by the site developer.
New annual Locality Action Plans
were co-produced with the
Partnerships in 2023 and are live
on the website. These are due to
be refreshed again early in the
summer.
The new CPP website
went live in Feb 2024
and was launched at the
annual North Ayrshire
Community and Locality
Planning Conference in
Irvine.
4 Tackling climate change
The Council’s website does not
currently have a dedicated
climate change webpage. The
council plans to improve its
website as a whole and is
exploring the inclusion of more
information on carbon emissions
and climate change as part of a
Sustainability Awareness
Communications Plan.
The Council should consider
including more information
on its website about what it is
doing to address climate
change and the progress it is
making.
The Council’s website will be
updated to include more
information on what we are
doing to address Climate
Change and progress we are
making, including publication
of a dedicated public facing
Climate Change webpage.
Options for a social media
page dedicated to climate
change will be investigated.
Jennifer Wraith, Team
Manager - Sustainability
31 January 2024
The Sustainability Team held a
workshop to identify the themes
and contents for the dedicated
Climate Change webpage. The
proposed themes following the
workstreams with the new
Sustainable North Ayrshire
strategy. 
The contents focus on what the
Council is currently doing to tackle
climate change across these
themes, and where to find more
information of how members of
the public can take action. 
Final amendments are being
made prior to submission by mid-
May
Target Date 17 May 2024
79

Page 80

Appendix 1
Charities
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
CH1 Dormant trusts
Six charitable Trusts have been
dormant for 3 years or more.
There is no clear plan on how to
bring the Trusts back into use.
This indicates that the Trusts are
not meeting the requirement of
public benefit.
The Council should ensure
that all Trusts have adequate
governance documentation
enabling grants to be issued.
The Trusts should also be
suitably advertised.
All Trust governance
documents will be reviewed to
ensure that they are adequate
to support the distribution of
grants to support
communities. A strategy for
the promotion of all available
community funding will be
developed to support
communities and individuals
identify and access available
funding options, including
currently dormant charitable
trusts.
Rhonda Leith, Head of
Connect Communities
31 March 2024
Connected Communities have
been working closely with
Finance and Communications
colleagues to promote the
various funding sources, trusts
and bequests available to the
council and ensure that as many
of our staff teams, partners and
communities are aware of the
available financial supports. This
is a long term piece of work and
part of a strategic aim to ensure
coordination of funding support
across council services is clear
and consistent.
In terms of the specific trusts in
question, the service is working
with colleagues within Legal
Services to identify relevant
governance documents and
ensure that proposed
disbursements meet the Trust
requirements.
Target Date 31 March
2025
80

Page 81

NORTH AYRSHIRE COUNCIL 
30 May 2024 
Audit and Scrutiny Committee 
Title:    Annual Governance Statement 2023/24 
Purpose:  To seek approval of the Council’s Annual Governance
Statement for 2023/24 which will be included within the draft
Annual Accounts. 
Recommendation:  That the Committee approves the draft Annual Governance
Statement which is attached at Appendix 1. 
1. Executive Summary 
1.1 The Council’s Annual Governance Statement outlines the governance framework
which is in place and changes which have been made to strengthen the framework
during 2023/24. 
1.2 Approval of the Annual Governance Statement will ensure that the Council complies
with the requirements of the Local Authority Accounts (Scotland) Regulations 2014. 
2. Background 
2.1 North Ayrshire Council is responsible for ensuring that its business is conducted in
accordance with the law and proper standards, and that public money is safeguarded
and properly accounted for and used economically, efficiently, and effectively to
achieve Best Value. 
2.2 The Council is also responsible for putting in place proper arrangements for the
governance of its affairs and facilitating the effective exercise of its functions, which
includes arrangements for the management of risk. 
2.3 The Council has approved and adopted a Code of Corporate Governance, which is
consistent with the principles of the CIPFA/SOLACE framework ‘Delivering Good
Governance in Local Government’. 
2.4 The Local Authority Accounts (Scotland) Regulations 2014 require that local
authorities prepare an Annual Governance Statement, in accordance with proper
practices in relation to internal control, and that the Statement should be approved by
the Audit Committee or equivalent. 
Agenda Item 9
81

Page 82

2.5 Following approval of the Annual Governance Statement, it requires to be signed by
the Leader of the Council and the Chief Executive prior to its inclusion within the
Council’s draft annual accounts. 
2.6 The Annual Governance Statement, which is attached in full at Appendix 1 to this
report, explains how the Council complies with the Code of Corporate Governance. It
identifies the main components of the Corporate Governance Framework which are in
place, including the system of internal control, and details the changes which have
taken place to the framework during 2023/24. 
2.7 The Annual Governance Statement also identifies improvement actions which are
planned to the governance framework during 2024/25. It concludes with an assurance
statement by the Leader of the Council and the Chief Executive. 
2.8 The Financial Management team recently carried out a benchmarking exercise of
annual accounts across other local authorities, and improvements relating to the
Annual Governance Statement have been incorporated. 
3. Proposals 
3.1 It is proposed that the Committee approves the draft Annual Governance Statement
which is attached at Appendix 1. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 Approval of the Annual Governance Statement will ensure that the Council complies
with the requirements of the Local Authority Accounts (Scotland) Regulations 2014. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 Good governance arrangements help to underpin the delivery of the Council’s key
priorities.
82

Page 83

Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 No consultation has been required during the preparation of the Annual Governance
Statement. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Risk), on 01294 324524. 
Background Papers
None.
83

Page 84

Scope of Responsibility
North Ayrshire Council is responsible for ensuring that its business
is conducted in accordance with the law and proper standards,
and that public money is safeguarded and properly accounted for
and used economically, efficiently and effectively to achieve Best
Value.  
The Council is also responsible for putting in place proper
arrangements for the governance of its affairs and facilitating the
effective exercise of its functions, which includes arrangements for
the management of risk.
The Council has approved and adopted a Local Code of Corporate
Governance, which is consistent with the principles of the
CIPFA/SOLACE Framework ‘Delivering Good Governance in Local
Government’ (2016).  A copy of the local code is available here.
This statement explains how North Ayrshire Council complies with the Code
of Corporate Governance and meets the requirements of the ‘Code of Practice for
Local Authority Accounting in the UK: A Statement of Recommended Practice’, in relation to the
Statement on the System of Internal Financial Control. 
The Purpose of the Governance Framework
The governance framework comprises the systems and processes, and culture and values by which
the authority is directed and controlled.  It enables the authority to monitor the achievement of its
strategic objectives and to consider whether those objectives have led to the delivery of appropriate,
cost-effective services and the achievement of key outcomes.
The system of internal control is a significant part of that framework and is designed to manage risk to
a reasonable level.  The system of internal control is based on an ongoing process designed to
identify and prioritise the risks to the achievement of the Council’s objectives, to evaluate the
likelihood of those risks being realised and the impact should they be realised, and to manage them
effectively. 
The Governance Framework
The Council’s Framework is built around the seven core principles and 21 sub-principles that set out
the key building blocks of good governance. 
Annual
Governance
Statement 
84

Page 85

The key features of the governance framework that were in place during 2023/24 are below:
• The Cabinet was the key decision-making Committee, comprising the Leader of the Council, the
Depute Leader and four members of the Administration, each with a specific portfolio of duties. An
Education Cabinet comprised the same members and included church and teaching profession
representatives.
• The Audit and Scrutiny Committee, which is chaired by a Member of an Opposition party, was in
place to consider all matters in relation to Internal and External Audit, Risk Management, Scrutiny
and Performance, as well as receiving reports on the findings of external scrutiny bodies. An
annual self-assessment process is carried out to assess the effectiveness of the Committee
utilising CIPFA’s Self Assessment of Good Practice within the publication ‘Audit Committees:
Practical Guidance for Local Authorities and Police – 2022 Edition’.
• A cross-party Policy Advisory Panel assists in the development of policy proposals for
consideration and approval by Cabinet.
• Strategic decision-making is governed by the Council’s key constitutional documents including
standing orders, scheme of administration, scheme of delegation to officers and financial
regulations and associated codes of financial practice. These were refreshed and approved by
the Council in May 2023.
• The Council has six Locality Partnerships, covering Irvine, Kilwinning, the Three Towns, Arran,
the North Coast and the Garnock Valley. Chaired by a local Elected Member, the Partnerships
provide the opportunity for Elected Members, Community Planning Partners and local community
representatives to consider the priorities for each area.
• The integrated Health and Social Care Partnership (HSCP) has established a governance
framework and an integrated senior management structure to support delivery of its key
objectives. 
• The Council’s mission, vision and key priorities are outlined in the Council Plan 2023-2028 which
is underpinned by a delivery plan and a range of performance indicators. Regular interim reports
are provided to both Cabinet and the Audit and Scrutiny Committee on progress towards meeting
the Council Plan priorities.
• Progress with the Council’s Change and Transformation programme continues to be governed
and monitored through the Transformation Board which is chaired by the Chief Executive.
• A people strategy entitled ‘Our People Connect’ is in place to support the delivery of the Council
Plan and its strategic priorities by focussing on developing the right culture and helping the
Council transform to be a leaner, more efficient and higher performing organisation where people
can develop and thrive.
• The Performance Management Strategy 2023-28 demonstrates how the Council supports a
culture of continuous improvement and how the work of every employee is crucial to the
achievement of the overall vision of a North Ayrshire that is Fair For All. Regular reporting to
Elected Members takes place, and a wide range of performance information is available on the
North Ayrshire Performance Dashboard.
• The Council has adopted a ‘Code of Conduct’ for all its employees. Elected Members adhere to
the national ‘Code of Conduct for Councillors’ and a register of interests is in place.
• The approach to risk management is set out in the Risk Management Policy and Strategy: “Risk
Focus”. The Council’s strategic risk register is refreshed annually and for 2023/24 was approved
by Cabinet in March 2023. Monitoring of progress against action points is reported to the Audit
and Scrutiny Committee at the mid-year point.
• Each Head of Service has a Workforce Plan in place for their portfolio of services which considers
challenges and issues, the transformation agenda and to support career development and
succession planning.
• The Council has in place a development programme for all Elected Members. In November 2023,
feedback was received on the Elected Member Development sessions held from May 2022 to
June 2023, and to seek views on topics for future development. Leadership and Development
programmes are also established for strategic leaders and first line and middle managers across
the Council, through the Leadership Academy approach.
• The ‘Our Time to Talk’ approach is in place to ensure that managers and employees take time to
discuss how each employee is getting on at work; this focusses on the employee’s contribution to
85

Page 86

their team and the Council, their wellbeing, and any development needs that contribute towards
meeting the team’s objectives or the employee’s career aspirations.
• The ICT Asset Management Approach 2021-2024 is linked to the ICT Technology Strategy and
depicts the impact on hardware, software and application assets.  The Council’s approach to
asset management planning is based on CIPFA guidance which covers six core classes of
assets: property, open space, housing, roads, fleet, and ICT.
• A Capital Programme and Assets Group (CPAG), consisting of senior officers from across
Council services and chaired by the Head of Finance, is in place. This group monitors the delivery
of the Council’s capital programme, helping to ensure that projects are delivered on time and
within budget. The work of this group is supported by Service Project Boards.
• The Council has a long-term financial outlook, which covers the period 2024/25 to 2033/34. This
sets out the scale of the potential financial challenge and the approach to pro-actively address it,
ensuring financial sustainability of the Council.
• The Council has Internal Audit and Corporate Fraud teams to carry out independent and objective
reviews of governance and internal control arrangements and investigate allegations of fraud and
error both within and against the authority.
• An Information Governance framework is in place which complies with the General Data
Protection Regulation (GDPR), supported by a central team of staff within Democratic Services.
This is further supported through an Information Governance Procurement Framework. A
corporate training module is in place to support ongoing training, development and awareness
which is completed on an annual basis.
• The Council has a robust Corporate Health, Safety and Wellbeing Policy to help ensure it
complies with health and safety legislation.
• An annual report is prepared for Cabinet by the Council’s statutory Chief Social Work Officer.
• The Council has a two-stage Complaints Procedure, which provides a transparent and
standardised process for customers who wish to complain and enables the Council to manage
complaints more effectively and to identify any service improvements which may be required. 
The governance framework has been in place at North Ayrshire Council throughout the year ended
31st March 2024. 
The System of Internal Financial Control
The system of internal financial control is based on a framework of regular management information,
financial regulations, administrative procedures (including segregation of duties), management
supervision, and a system of delegation and accountability.  Development and maintenance of the
system is undertaken by Chief Officers within the Council.  In particular, the system includes:
• Financial regulations and codes of financial practice.
• Comprehensive budgeting systems.
• Regular reviews of periodic and annual financial reports that indicate financial performance
against the forecasts.
• Setting targets to measure financial and other performance.
• Clearly defined capital expenditure guidelines.
• Formal project management disciplines.
The Council’s financial management arrangements conform to the governance requirements of the
CIPFA statement on ‘The Role of the Chief Financial Officer in Local Government (2016)’.
Regarding the entities incorporated into the Group Accounts, the Council is not aware of any
weaknesses within their internal control systems and has placed reliance on the individual Statements
of Internal Financial Control where appropriate. 
Review of Effectiveness of the Governance Framework
North Ayrshire Council has responsibility for conducting, at least annually, a review of the
effectiveness of its governance framework including the system of internal control. The review of the
86

Page 87

effectiveness of the framework is informed by the work of the Executive Leadership Team who have
responsibility for development and maintenance of the governance environment, the annual report by
the Senior Manager (Audit, Fraud, Safety and Risk) and reports from the Council’s external auditors,
Audit Scotland, and other review agencies.
The Section 95 Officer has overall responsibility for Internal Audit in North Ayrshire Council.  The
Senior Manager (Audit, Fraud, Safety and Risk) is responsible for the management of the section and
reports directly to the Section 95 Officer on all audit matters, with the right of access to the Chief
Executive and Chair of the Audit and Scrutiny Committee. The Internal Audit section is fully resourced
to deliver its planned activity and complies with the Public Sector Internal Audit Standards (PSIAS) in
conducting its audit work. Regular reports were made to the Council’s Audit and Scrutiny Committee
throughout 2023/24.
As detailed in the Internal Audit Charter, most recently approved by the Audit and Scrutiny Committee
in March 2023, the Internal Audit function has independent responsibility for examining, evaluating,
and reporting on the adequacy of internal control.  The Senior Manager (Audit, Fraud, Safety and
Risk) prepares an annual report, including an assurance statement containing a view on the
adequacy and effectiveness of the governance, risk management and internal control frameworks.
This was reported to the Audit and Scrutiny Committee on 30 May 2024.
The Internal Audit Annual Report 2023/24 highlights a number of findings by the Council’s Internal
Audit section. Action plans are put in place to address control weaknesses on conclusion of each
audit and implementation of audit actions is tracked on a quarterly basis by the Council’s Audit and
Scrutiny Committee. None of these are considered material enough to have a significant impact on
the overall control environment and it is the opinion of the Senior Manager (Audit, Fraud, Safety and
Risk) that the Council’s systems of internal control continue to provide reasonable assurance against
loss.
The Council’s internal audit arrangements conform to the governance requirements of the CIPFA
statement on ‘The Role of the Head of Internal Audit (2019)’. 
Significant Governance Developments during 2023/24
The Council Plan is the overarching strategy of the Council and details the Council’s strategic
priorities. A revised Council Plan for 2023-2028 was approved by Council in June 2023.
The Performance Management Strategy 2023-2028 has been developed which proposes a
systematic approach to self-assessment. In August 2023, Cabinet approved the Council Plan 2023-28
Performance Management Framework (PMF) which will be used to demonstrate progress against the
Council Plan priorities. The PMF was further endorsed by the Audit and Scrutiny Committee.
A Long-Term Financial Outlook (covering the period 2024/25 to 2033/34) was approved by Council in
December 2023.  This is underpinned by a Medium-term Financial Outlook (MTFO) which is updated
annually.  The most recent MTFO, covering 2024/25-2026/27, was also approved by the Council in
December 2023. These documents note the scale of the financial challenge which the Council faces
and underpin the development of a balanced budget. The General Services Revenue Estimates
2024/25-2026/27 and Capital Investment Programme 2024/25-2033/34 were approved by Council in
February 2024.
The Digital North Ayrshire Strategy 2023 – 2028 was approved by Cabinet in May 2023. The strategy
recognises the many benefits that digital engagement can bring, and the need to strive for innovation
and continuous improvement in light of increased customer expectations on local services and a
challenging financial environment.
The Council has a variety of assets which are integral to service delivery. The North Ayrshire Asset
Management Strategy and associated Asset Management Plans (including fleet, roads, housing,
property, open space and ICT) covering the period 2023-2028 were approved by Cabinet in October
2023. The strategy ensures that the Council is maximising its opportunities for the use of land and
property assets, and ensures assets contribute to the Council Plan priorities. Asset management also
plays a key role in the development of the Medium Term Financial Strategy.
The Sustainable North Ayrshire Strategy 2024-27 was approved by Cabinet in December 2023. The
Council declared a climate emergency in 2019 and has committed to achieving net zero carbon
emissions by 2030. The Strategy replaces the Council’s previous Environmental Sustainability and
Climate Change Strategies (ESCCS). Linked to supporting the Council’s routemap to net-zero by
2030, a number of proposals have been agreed including the decarbonisation of the Council’s vehicle
fleet by 2030 and the approval of a Tree and Woodland Management Policy.
87

Page 88

Under the Equality Act, public sector organisations are required to publish equality information every
two years and consult on/develop Equality Outcomes every four years. In May 2023, Cabinet
approved the content of the Equality Mainstreaming Report 2020-22 and Outcomes 2021-2025 Mid-
Term Report.
A refreshed Community Wealth Building Strategy for 2024-2027 aims to provide a Community Wealth
Building focussed approach to economic development in North Ayrshire, allowing the Council to
remain at the forefront of this innovative policy area.
The Children’s Services Plan 2023-26 was endorsed by Cabinet in June 2023, and builds on the
progress made since the previous Children’s Services Plan 2020-23. The Children’s Services Plan is
aligned to the Children’s Poverty Strategy 2023-26 and Action Plan 2023-24 and Children’s Rights
Report 2020/23 (also approved in June 2023), together forming the suite of children’s services
planning documents.
A refreshed North Ayrshire Local Housing Strategy 2023 – 2028 is in place, which sets out the
strategic priorities for tackling housing issues in the area over the next five years. The strategy will
allow the Council to monitor progress against national and local priorities and targets. In line with this
same period, a refreshed Housing Services’ Customer Participation Strategy 2023 – 2028 which sets
out Housing Services’ plan for developing customer involvement over the next five years.
The regeneration of vacant and derelict land plays a key role in priorities of the Council Plan,
Community Wealth Building Strategy, and the Regeneration Delivery Plan. A new Vacant and Derelict
Land Strategy 2023-2028 sets out how vacant and derelict land fits within, and supports the wider
context of, national and local priorities and objectives. It also includes a series of actions to promote
the positive re-use of sites to address local priorities, support change within communities and ensure
our places and economy are vibrant and inclusive. 
Planned Actions for 2024/25
The Council has a number of planned actions for 2024/25 which will help to further strengthen the
governance framework:
• Strengthening of the Council’s Executive Leadership Team aligned to the new Council structure;
• Progress a work programme to embed Community Budget engagement within existing
stakeholder networks, as opposed to an annual event; and
• In view of the financial landscape, early development of the Council’s budget programme for
2025/26 to consider public consultation requirements and early political engagement. 
Assurance
Subject to the above, and based on the assurances provided, we consider the governance and
internal control environment operating during 2023/24 to provide reasonable and objective assurance
that any significant risks impacting on the achievement of our actions will be identified and actions
taken to avoid or mitigate their impact. Systems are in place to continually review and improve the
governance and internal control environment and action plans are in place to address identified areas
for improvement. 
Craig Hatton Marie Burns
Chief Executive Leader of the Council
May 2024 May 2024 
88

Page 89

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Accounting Policies 2023/24
Purpose: To seek the Audit and Scrutiny Committee’s approval of the
accounting policies which will be adopted in the preparation of
the Council’s annual accounts for the year to 31 March 2024.
Recommendation: That the Audit and Scrutiny Committee approves the accounting
policies as detailed in Appendix 1.
1. Executive Summary
1.1 The annual accounts for the 2023/24 financial year summarise the Council
transactions during the year and its position at the year end of 31 March 2024. Under
the Local Authority Accounts (Scotland) Regulations 2014, the Council is required to
prepare an annual Statement of Accounts and Section 12 of the Local Government in
Scotland Act 2003 requires that these accounts are prepared in accordance with the
proper accounting practices.
1.2 These practices primarily comprise the Code of Practice on Local Authority
Accounting in the United Kingdom 2023/24 (“the Code”), supported by International
Financial Reporting Standards (IFRS). These are issued jointly by the Chartered
Institute of Public Finance and Accountancy (CIPFA) and the Local Authority
(Scotland) Accounts Advisory Committee (LASAAC) and are designed to give a “true
and fair view” of the financial performance of the Council.
1.3 The accounting policies to be adopted by North Ayrshire Council are reviewed on an
annual basis in line with the CIPFA Code and submitted to the Audit and Scrutiny
Committee for approval in advance of the financial statements being prepared.
1.4 The proposed accounting policies for 2023/24 have been updated to reflect changes
in the guidance received from CIPFA during 2023/24.
1.5 Following further revisions to the guidance in relation to the adoption of IFRS 16 in
relation to the accounting for leases, it has been determined that implementation of
the revised standard will now be with effect from 1 April 2024. As such, the draft
accounting policies continue to reflect the existing accounting treatment.
Agenda Item 10
89

Page 90

2. Background 
2.1 Accounting policies are defined in paragraph 3.3.2.1 of the Code as ‘the specific
principles, bases, conventions, rules and practices applied by an authority in preparing
and presenting financial statements’. 
2.2  Councils are required to select accounting policies and apply changes to accounting
policies in accordance with International Accounting Standard 8 - Accounting Policies. 
2.3  The Council is required to adopt the accounting policies most appropriate to its
particular circumstances for the purpose of giving a true and fair view. The accounting
policies adopted should be reviewed regularly to ensure that they remain appropriate
and consider the required treatment of any new policies relevant to the Council’s
particular circumstances. Sufficient information should be disclosed in the financial
statements to enable users to understand the accounting policies adopted and how
they have been implemented. 
2.4  The draft accounting policies proposed for adoption are detailed in Appendix 1 and
include the following revisions identified during 2023/24: 
i. The previous policies in relation to Soft Loans to Charitable Bodies have been
removed on the basis of materiality as the last such arrangement was brought to
an end during 2022/23. 
ii. The previous policy in relation to Financial Assets Measured at Fair Value through
Profit and Loss (FVPL) has been removed on the basis of materiality as the
Council’s business model is to hold assets to collect contractual cash flows and
our financial assets are, therefore, measured at amortised cost rather than FVPL. 
2.5 Although CIPFA / LASAAC had determined that the mandatory adoption of changes to
the treatment of leases and similar arrangements in line with International Financial
Reporting Standard (IFRS) 16 Leases were to be postponed until 1 April 2024, it was
previously reported that North Ayrshire Council would voluntarily adopt the new
standard from 1 April 2023. However, following delays in the issuing of the final
revised guidance by CIPFA / LASAAC it is now proposed that full adoption of this
standard is deferred until 1 April 2024, in line with mandatory requirements. 
3. Proposals 
3.1 It is proposed that the Audit and Scrutiny Committee approves the accounting policies
as detailed in Appendix 1 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
90

Page 91

Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by maximising financial
flexibility to support the delivery of our priorities and focussing our investment on
priorities. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The council’s appointed external auditors for 2023/24, Audit Scotland, were consulted
on the changes detailed in this report. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
None 
91

Page 92

Appendix 1 
Accounting Policies 2023-24 
General Principles 
The Accounts summarise the Council’s transactions for the 2023-24 financial year and its
position at the year-end of 31 March 2024.  The Council is required to prepare an annual
Statement of Accounts by the Local Authority Accounts (Scotland) Regulations 2014 and
Section 12 of the Local Government in Scotland Act 2003 requires that they are prepared in
accordance with proper accounting practices.   
These practices, under Section 21 of the 2003 Act, primarily comprise the Code of Practice
on Local Authority Accounting in the United Kingdom 2023/24, supported by International
Financial Reporting Standards (IFRS) and statutory guidance under Section 12 of the 2003
Act. 
The accounting convention adopted in the financial statements is principally historical cost,
modified by the revaluation of certain categories of non-current assets and financial
instruments. 
The accounts have been prepared on a going concern basis. 
A Accruals of Income and Expenditure
Activity is accounted for in the year that it takes place, not simply when cash payments are
made or received. In particular: 
• Revenue from contracts with service recipients, whether for services or the provision of
goods, is recognised when (or as) the goods or services are transferred to the service
recipient in accordance with the performance obligations of the contract.
• Supplies are recorded as expenditure when they are consumed. Where there is a gap
between the date supplies are received and their consumption, they are carried as
inventories on the Balance Sheet.
• Expenses in relation to services received (including services provided by employees) are
recorded as expenditure when the services are received rather than when payments are
made.
• Interest payable on borrowings and receivable on investments is accounted for on the
basis of the effective interest rate for the relevant financial instrument rather than the cash
flows fixed or determined by the contract. 
• Suppliers’ invoices paid in the two weeks following the year-end have been included
together with specific accruals in respect of further material items, provided the goods
and services were received prior to 31 March. 
• Where revenue and expenditure have been recognised but cash has not been received
or paid, a debtor or creditor for the relevant amount is recorded in the Balance Sheet. 
The de minimis level for recognition of such transactions has been agreed at £5,000,
therefore all known transactions of £5,000 or above have been included. 
• Where debts may not be settled, the balance of debtors is written down and a charge
made to revenue for the income that might not be collected. 
92

Page 93

B  Allocation of Central Support Costs
A proportion of net central support services is allocated to services outwith the general fund.
The balance of the net central support services is reported on the basis of how the services
are structured and how the Council operates, monitors and manages financial performance. 
C Cash and Cash Equivalents
Cash is represented by cash in hand and deposits with financial institutions repayable
without penalty on notice of not more than 24 hours.  Cash equivalents are investments that
mature in three months or less from the date of acquisition and that are readily convertible to
known amounts of cash with insignificant risk of change in value. 
In the Cash Flow Statement, cash and cash equivalents are shown net of bank overdrafts
that are repayable on demand and form an integral part of the Council’s cash management. 
D Prior Period Adjustments, Changes in Accounting Policies and Estimates and
Errors
Prior period adjustments may arise as a result of a change in accounting policies or to
correct a material error. Changes in accounting estimates are accounted for prospectively,
i.e. in the current and future years affected by the change and do not give rise to a prior
period adjustment. 
Changes in accounting policies are only made when required by proper accounting practices
or the change provides more reliable or relevant information about the effect of transactions,
other events and conditions on the Council’s financial position or performance. When a
change is made, it is applied retrospectively (unless otherwise stated) by adjusting opening
balances and comparative amounts for the prior period as if the new policy had always been
applied. 
Material errors discovered in prior years are corrected retrospectively by amending opening
balances and comparative amounts for the prior period. 
E Charges to Revenue for Non-Current Assets
Services are charged with the following amounts to record the cost of holding non-current
assets during the year: 
• Depreciation attributable to the assets used by the relevant service;
• Revaluation and impairment losses on assets used by the service where there are no
accumulated gains in the Revaluation Reserve against which the losses can be written
off; and 
• Amortisation of intangible fixed assets attributable to the service. 
The Council is not required to raise council tax to cover depreciation, revaluation and
impairment losses or amortisation. However, it is required to make an annual contribution
from revenue towards the reduction in its overall borrowing requirement, equal to an amount
calculated on a prudent basis determined by the Council in accordance with the Statutory
Repayment of Loans Fund Advances. This is known as the Loans Fund Principal
Repayment. Depreciation, revaluation and impairment losses and amortisation are replaced
by the Loans Fund Principal Repayments in the General Fund Balance by way of an
adjusting transaction within the Capital Adjustment Account in the Movement in Reserves
Statement for the difference between the two. 
93

Page 94

F Employee Benefits 
Benefits Payable during Employment
Short-term employee benefits are those due to be settled wholly within 12 months of the
year end. They include such benefits as salaries, wages, overtime and paid annual leave for
current employees and are recognised as an expense in the year in which employees render
service to the Council.  All salaries and wages earned up to 31 March are included in the
financial statements irrespective of when the payment was made. An accrual is made for the
cost of holiday entitlements earned by employees but not taken before the year-end and
which employees can carry forward into the next financial year.  The accrual is made at the
wage and salary rates applicable in the following year, being the period in which the benefits
will be taken. Such accruals are required, under statute, to be reversed out of the General
Fund Balance by a credit to the Accumulating Compensated Absences Adjustment Account
in the Movement in Reserves Statement. 
Termination Benefits
Termination benefits are amounts payable as a result of a decision by the Council to
terminate an officer’s employment before the normal retirement date or an officer’s decision
to accept voluntary redundancy. They are charged on an accruals basis to the relevant
services line in the CIES at the point when the offer of termination can no longer be
withdrawn by the Council. Where termination benefits include the enhancement of pensions,
the General Fund balance is charged with the amount payable by the Council to the pension
fund or pensioner in the year. 
Post-Employment Benefits
The Council participates in two separate pension schemes: 
• The Scottish Teachers’ Pension Scheme administered by the Scottish Government; and
• The Local Government (Scotland) Pension Scheme administered by the Strathclyde
Pension Fund.  
Both schemes provide defined benefits to members (retirement lump sums and pensions),
earned while employees work for the Council.  However, the arrangements for the teachers’
scheme mean that liabilities for these benefits cannot be identified specifically to the Council. 
The scheme is therefore accounted for as if it were a defined contributions scheme.  No
liability for future payments of benefits is recognised in the Balance Sheet and the
Communities line in the CIES is charged with the employer’s contributions payable to the
Teachers’ Pension Scheme in the year. 
The Local Government Pension Scheme
The Local Government Pension Scheme (LGPS) is accounted for as a defined benefits
scheme. 
The assets/liabilities of Strathclyde Pension Fund attributable to the Council are included in
the Balance Sheet on an actuarial basis using the ‘projected credit unit method’, i.e. an
assessment of the future payments that will be made in relation to retirement benefits earned
to date by employees, based on assumptions about mortality rates, employee turnover rates,
etc., and projected earnings for current employees. 
Assets/liabilities are discounted to their value at current prices, as advised by the actuaries,
Hymans Robertson, using an appropriate discount rate.
94

Page 95

The assets/liabilities of Strathclyde Pension Fund attributable to North Ayrshire Council are
included in the Balance Sheet at their fair value: 
• Quoted securities – current bid price;
• Unquoted securities – professional estimate;
• Unitised securities – current bid price; and 
• Property – market value. 
The change in the net pension asset/liability is analysed into the following components: 
Service Costs:
• Current service cost – the increase in liabilities as a result of service earned by
employees this year. This is allocated in the CIES to the services for which the
employees worked.
• Past service cost (including curtailments) – the increase in liabilities as a result changes
to the scheme, including amendments or curtailments, where the changes impact on the
service earned by employees in previous years. These costs are charged to the Surplus
or Deficit on the Provision of Services in the CIES. 
• Net interest on the net defined benefit liability (asset), i.e. net interest expense for the
Council – the change during the period in the net defined benefit liability or asset that
arises from the passage of time. This is charged to the Financing and Investment Income
and Expenditure line in the CIES, calculated by applying the discount rate used to
measure the defined benefit obligation at the beginning of the period – taking into account
any changes in the net defined benefit liability or asset during the period as a result of
contribution and benefit payments. 
Remeasurements:
• Return on plan assets – excludes amounts included in net interest on the net defined
liability (asset). This is charged to the Pensions Reserve as Other Comprehensive
Income and Expenditure.
• Actuarial gains and losses – changes in the net pensions liability that arise because
events have not coincided with assumptions made at the last actuarial valuation or
because the actuaries have updated their assumptions. This is charged to the Pensions
Reserve as Other Comprehensive Income and Expenditure.
• Contributions paid to the Strathclyde Pension Fund – cash paid as employer’s
contributions to the pension fund in settlement of liabilities. This is not accounted for as
an expense. 
Statutory provisions require the General Fund balance to be charged with the amount
payable by the Council to the pension fund or directly to pensioners in the year, not the
amount calculated according to the relevant accounting standards.  In the Movement in
Reserves Statement, this means that there are transfers to and from the Pensions Reserve
to remove the notional debits and credits for retirement or pension enhancement termination
benefits and replace them with charges for the cash paid to the pension fund and pensioners
and any such amounts payable but unpaid at the year-end.  The balance that arises on the
Pensions Reserve thereby measures the impact on the General Fund of being required to
account for retirement benefits on the basis of cash flows rather than as benefits earned by
employees. 
95

Page 96

Discretionary Benefits
The Council also has restricted powers to make discretionary awards to retirement benefits
in the event of early retirements. Any liabilities estimated to arise as a result of an award to
any member of staff, including teachers, are accrued in the year of the decision to make the
award and accounted for using the same policies as are applied to the Local Government
Pension Scheme. 
G Events After the Reporting Period 
These are events, both favourable and unfavourable, that occur between the end of the
reporting period (31 March) and the date when the financial statements are authorised for
issue.   
The Statement of Accounts are adjusted to reflect events where they provide evidence of
conditions that existed at the end of the reporting period. 
Where events indicate conditions, which arose after the reporting period, which would have
had a material effect, the Statement of Accounts are not adjusted but a disclosure is made in
the notes of the nature of the event and the estimated financial effect. 
Events taking place after the date of authorisation for issue are not reflected in the
Statement of Accounts. 
H Financial Instruments 
Financial Liabilities
Financial liabilities are recognised on the balance sheet when the Council becomes party to
the contractual provisions of a financial liability. Liabilities are initially measured at fair value
and then carried at amortised cost.  Annual charges to the Financing and Investment Income
and Expenditure line in the CIES for interest payable are based on the carrying amount of
the liability, multiplied by the effective interest rate of the instrument. The effective interest
rate is the rate that exactly discounts estimated future cash payments over the life of the
instrument to the amount at which it was originally recognised. 
For most of the borrowings that the Council has, this means that the amount presented in
the balance sheet is the outstanding principal repayable (plus accrued interest) and interest
charged to the CIES is the amount payable for the year according to the loan agreement. 
Costs associated with debt restructuring (premiums and discounts) are charged to the
Financing and Investment Income and Expenditure line in the CIES in the year of repayment
of the original debt in accordance with accounting regulations. 
Where premiums and discounts have been charged to the CIES, regulations permit the
costs of restructuring to be released to revenue over the period of the replacement loan. 
The reconciliation of amounts charged to the CIES to the net charge required against the
General Fund balance is managed by a transfer to or from the Financial Instruments
Adjustment Account in the Movement in Reserves Statement. 
Financial Assets
Financial assets are classified and measured based on the reasons, or business model, for
holding the financial assets and the characteristics of the anticipated cash flows. There are
three main classes of financial assets measured at:
96

Page 97

• Amortised cost;
• Fair value through profit or loss (FVPL); and
• Fair value through other comprehensive income (FVOCI). 
The Council’s business model is to hold assets to collect contractual cash flows and our
financial assets are therefore classified as amortised cost. 
Financial Assets Measured at Amortised Cost
Financial assets measured at amortised costs are recognised on the Balance Sheet when
the Council becomes party to the contractual provisions of a financial asset and are initially
measured at fair value and then carried at amortised cost. Annual credits to the Financing
and Investment Income and Expenditure line in the CIES for interest receivable are based
on the carrying amount of the asset multiplied by the effective rate of interest for the
instrument. For the financial assets held by the Council, this means that the amount
presented in the Balance Sheet is the outstanding principal receivable (plus accrued
interest) and interest credited to the CIES is the amount receivable for the year in the loan
agreement. 
Any gains or losses which arise on the derecognition of an asset are credited or debited to
the Financing and Investment Income and Expenditure line in the CIES. 
Expected Credit Loss Model
Potential impairment losses on Financial Assets Measured at Amortised Cost are
determined using the Expected Credit Loss Model. The Council recognises expected credit
losses on all of its financial assets held at amortised cost, either on a 12-month or lifetime
basis. Only lifetime losses are recognised for trade receivables (debtors). 
Impairment losses are calculated to reflect the expectation that the future cash flows may not
take place because the borrower may default on their obligations. Credit risk plays a crucial
part in assessing the potential losses. Where risk has increased significantly since an asset
was recognised, losses are assessed on a lifetime basis. Where risk has not increased
significantly or remains low, losses are assessed on the basis of 12-month expected losses. 
For any identified impairment losses, a charge is made to the Financing and Investment
Income and Expenditure line in the CIES.   
I Government Grants and Contributions
Whether paid on account, by instalments or in arrears, government grants and third party
contributions and donations are recognised as due to the Council when there is reasonable
assurance that: 
• The Council will comply with the conditions attached to the payments, and
• The grants or contributions will be received. 
Amounts recognised as due to the Council are not credited to the CIES until conditions
attached to the grant have been satisfied. 
97

Page 98

Monies advanced as grants and contributions for which conditions have not been satisfied
are carried in the Balance Sheet as creditors.  When conditions are satisfied, the grant or
contribution is credited to the relevant service line (for revenue grants) or Taxation and Non-
Specific Grant Income (for non-ring-fenced revenue grants and all capital grants). 
Capital grants are then reversed out of the General Fund Balance in the Movement in
Reserves Statement. Where the grant has yet to be used to finance capital expenditure, it is
posted to the Capital Grants Unapplied Account within the Capital Fund.   
Capital grants which are used and amounts previously posted to the Capital Grants
Unapplied Account which have now been applied, are transferred to the Capital Adjustment
Account. 
J  Heritage Assets 
A heritage asset is defined as a tangible asset with historical, artistic, scientific,
technological, geophysical or environmental qualities that is held and maintained principally
for its contribution to knowledge and culture. 
The Council holds heritage assets consisting of civic regalia and silverware, historical
artefacts, fine art and public artworks. The assets are held at valuation and no depreciation
is charged on the assets. Expenditure to maintain the assets is written off to the
Comprehensive Income and Expenditure Statement (CIES) in the year of expenditure.
Donated heritage assets are reflected in the balance sheet at valuation with a gain
equivalent to the value of the asset reported in the CIES in the year of donation. 
Measurement
The Council’s heritage assets are recognised on the Balance Sheet at values determined by
specialist external valuers and by experienced officers within the Connected Communities
service.  Valuations have been largely undertaken on an insurance basis at retail level.  Only
items deemed to have a value of £10,000 and above have been disclosed in the Balance
Sheet.   
Disclosure
Not all of the Council’s identified heritage assets will be disclosed in the Balance Sheet.  It is
not deemed practicable to obtain external valuations for all items defined as heritage assets. 
These include: Museum and Gallery items with a value of less than £10,000; Castles;
Monuments and War Memorials. 
K Intangible Assets 
Expenditure on non-monetary assets that do not have physical substance but are controlled
by the Council as a result of past events (e.g. software licences) is capitalised when it is
expected that it will bring benefits to the Council for more than twelve months. Intangible
assets are measured initially at cost.  Amounts are not revalued, as the fair value of the
assets held by the Council cannot be determined by reference to an active market.  The
depreciable amount of an intangible asset is amortised over its useful life (generally between
5 and 10 years) to the relevant service line(s) in the CIES.   
98

Page 99

L  Interest in Companies and Other Entities
The Council has interests in companies and other entities which have the nature of
subsidiaries, associates and joint ventures and require it to prepare group accounts. In the
Council’s single entity accounts, these interests are recorded as financial assets at cost, less
any provision for losses. 
M  Internal Transactions
Internal transactions between operational segments of the Council are included within the
management accounts for budgetary control purposes only. All internal transactions between
services have been excluded from the service expenditure analysis within the
Comprehensive Income and Expenditure Statement resulting in reductions in both the gross
expenditure and gross income reported, with no overall net impact. 
N Inventories 
Inventories include consumable stock and work-in-progress and are recognised in the
Balance Sheet at the lower of cost and net realisable value. The valuation of work-in-
progress has been made at cost plus an appropriate proportion of overheads, together with
attributable profits and allowances for foreseeable losses. 
O Investment Properties 
Investment properties are those that are used solely to earn rentals and/or for capital
appreciation. Investment properties are measured initially at cost and subsequently at fair
value, being the price that would be received to sell such an asset in an orderly transaction
between market participants at the measurement date. As a non-financial asset, investment
properties are measured at highest and best use. Properties are not depreciated but
reviewed annually and revalued regularly to ensure their carrying value reflects market
conditions at the year-end.   
P Leases 
Leases are classified as finance leases where the terms of the lease transfer substantially all
the risks and rewards incidental to ownership of the property from the lessor to the lessee. 
All other leases are classified as operating leases. Where a lease covers both land and
buildings, the land and buildings elements are considered separately for classification. 
The Council as Lessee
North Ayrshire Council currently has no finance leases where the Council is the lessee. 
Rentals paid under operating leases for vehicles, plant and equipment are charged to the
appropriate service account in the CIES as an expense of the services benefiting for use of
the leased assets. 
The Council as Lessor
North Ayrshire Council has no finance leases where the Council is the lessor.   
The Council rents out property on cancellable operating leases only.  Where the Council
grants an operating lease over a property or an item of plant or equipment, the asset is
retained in the Balance Sheet.   
99

Page 100

Q Property, Plant and Equipment 
Assets that have physical substance and are held for use in the supply of services, for rental
to others, or for administrative purposes and that are expected to be used during more than
one financial year are classified as Property, Plant and Equipment. 
All valuations of land and buildings are carried out by Royal Institution of Chartered
Surveyors (RICS) qualified valuers, with the exception of valuations of council dwellings
which are based on beacon values calculated by the District Valuer. Both valuations are in
accordance with the methodologies and bases of estimation as set out in the professional
standards of RICS. 
Recognition
Expenditure on the acquisition, creation or enhancement of Property, Plant and Equipment is
capitalised on an accruals basis. Expenditure that merely maintains the condition of an asset
(i.e. repairs and maintenance) is charged as an expense when it is incurred.   
The Council has a de minimis level of £10,000 for expenditure to be classed as capital. 
Land and Buildings with a valuation below £10,000 are not recognised on the Council
Balance Sheet. 
Measurement
Assets are initially measured at cost, comprising: 
• The purchase price; and 
• Any costs attributable to bringing the asset to the location and condition necessary for it
to be capable of operating in the manner intended. 
The Council does not capitalise borrowing costs incurred whilst assets are under
construction. 
The cost of any asset acquired other than by purchase is deemed to be its fair value. 
Assets are carried on the Balance Sheet using the following measurement bases: 
• Council Dwellings - Fair value, determined using the basis of existing use value for social
housing (EUV-SH);
• Other Land and Buildings - Fair value, determined by the amount that would be paid for
the asset in its existing use (existing use value - EUV).  
• Vehicles, Plant and Equipment - depreciated historical cost
• Infrastructure Assets - depreciated historical cost
• Community Assets - depreciated historical cost
• Surplus Assets - fair value based on market value in highest and best use
• Assets Under Construction - historical cost
• Investment Properties (Common Good and Trusts only) - fair value based on market
value in highest and best use 
Where there is no market-based evidence of fair value because of the specialist nature of an
asset, depreciated replacement cost is used as an estimate of fair value. 
100

Page 101

Assets included in the Balance Sheet at fair value are revalued on a rolling basis over a
period not exceeding 5 years, with the exception of Surplus Assets and Investment
Properties which are revalued annually. 
Where a sample of assets in each category has been valued in the current financial year, the
change in values for the sample assets shall be assessed and extrapolated to determine if a
potential material movement in the value of all assets within that category is indicated. The
materiality threshold has been determined as 1.5% of the previous formal valuation, for
2023/24 this is equivalent to £15.6m. Where a material movement is indicated, this will be
disclosed within the annual accounts and additional valuation work will be undertaken in
conjunction with colleagues from the Royal Institute of Chartered Surveyors to assess the
valuations of all other assets within that category. 
Increases in valuations are matched by credits to the Revaluation Reserve to recognise
unrealised gains. Where decreases in value are identified, the revaluation loss is accounted
for as follows: 
• Where there is a balance of revaluation gains for the asset in the Revaluation Reserve,
the carrying amount of the asset is written down against that balance (up to the amount of
the accumulated gains);
• Where there is no balance in the Revaluation Reserve or insufficient balance, the carrying
amount of the asset is written down against the relevant service line(s) in the CIES. 
The Revaluation Reserve contains revaluation gains recognised since 1 April 2007 only, the
date of its formal implementation.  Gains arising before that date have been consolidated
into the Capital Adjustment Account. 
Impairment
Assets are assessed at each year-end to establish whether there is any indication that an
asset may be impaired.  Where indications exist, and any possible differences are estimated
to be material, the recoverable amount of the asset is estimated and, where this is less than
the carrying amount of the asset, an impairment loss is recognised for the shortfall. 
Where impairment losses are identified, they are accounted for as follows: 
• Where there is a balance of revaluation gains for the asset in the Revaluation Reserve,
the carrying amount of the asset is written down against that balance (up to the amount of
the accumulated gains);
• Where there is no balance in the Revaluation Reserve or insufficient balance, the carrying
amount of the asset is written down against the relevant service line(s) in the CIES. 
Where an impairment loss is subsequently reversed, the reversal is credited to the relevant
service line(s) in the CIES, up to the amount of the original loss, adjusted for depreciation
that would have been charged if the loss had not been recognised. 
101

Page 102

Depreciation
Depreciation is provided for on all Property, Plant and Equipment assets. An exception is
made for assets without a determinable finite useful life (i.e. freehold land and certain
Community Assets) and assets that are not yet available for use (i.e. assets under
construction).  Investment Properties and Assets Held for Sale are not subject to
depreciation. 
Depreciation is charged on a straight-line basis over the useful life of the assets (as advised
by a suitably qualified officer).  Depreciation is charged in the year of acquisition but not in
the year of sale. 
Where a Property, Plant and Equipment asset has major components whose cost is
significant in relation to the total cost of the item, the components are depreciated
separately. For the purposes of component accounting the Council considers significant
components being those with a cost that is at least 20% of the overall cost of the asset. 
Individual assets shall be disregarded for component accounting where their carrying value
is below £2m. 
Revaluation gains are also depreciated, with an amount equal to the difference between
current value depreciation charged on assets and the depreciation that would have been
chargeable based on their historical cost being transferred each year from the Revaluation
Reserve to the General Fund. 
Disposals
When it becomes probable that the carrying amount of an asset will be recovered principally
through a sale transaction rather than through its continuing use, it is reclassified as an
Asset Held for Sale.  The asset is revalued immediately before reclassification and then
carried at the lower of this amount and fair value less costs to sell.  Where there is a
subsequent decrease to fair value less costs to sell, the loss is posted to the Other
Operating Expenditure line in the CIES.  Gains in fair value are recognised only up to the
amount of any previously recognised losses.  Depreciation is not charged on Assets Held for
Sale. 
Property, land and buildings are classified as ‘held for sale’ when the following criteria are
met: 
• The property is available for sale in its present condition;
• The sale is highly probable;
• The asset is being actively marketed for sale at a price that is reasonable in relation to its
current fair value;
• The sale is expected to qualify for recognition as a completed sale within one year. 
When an asset is disposed of or decommissioned, the carrying amount of the asset in the
Balance Sheet is written off to the Other Operating Expenditure line in the CIES as part of
the gain or loss on disposal.  Receipts from disposals are credited to the same line in the
CIES as part of the gain or loss on disposal.  Any revaluation gains accumulated for the
asset in the Revaluation Reserve are transferred to the Capital Adjustment Account. 
To comply with statutory guidance, this gain or loss is excluded when determining the
General Fund balance within the Movement in Reserves Statement.
102

Page 103

The Council has determined, in accordance with Local Government Circular 09/2022
Statutory Override Accounting for Infrastructure Assets for Scottish Local Authorities, that
the carrying amount to be derecognised in respect of a replaced part of an infrastructure
asset is to be taken to be, and accounted for, as a nil amount. In accordance with the
circular the Council is not required to make subsequent adjustments to the carrying amount
of the asset with respect to that part. 
R Public Private Partnership (PPP) / NPD and similar contracts 
PPP / NPD and similar contracts are agreements to receive services, where the
responsibility for making available the property, plant and equipment needed to provide the
services passes to the PPP / NPD contractor.  As the Council is deemed to control the
services that are provided under its PPP / NPD schemes and as ownership of the property,
plant and equipment will pass to the Council at the end of the contracts for no additional
charge, the Council carries the assets used under the contracts on its Balance Sheet as part
of Property, Plant and Equipment. 
The original recognition of these assets at fair value (based on the cost to purchase the
property, plant and equipment) was balanced by the recognition of a liability for amounts due
to the scheme operator to pay for the capital investment.  For North Ayrshire Council
Schools PPP contract, the liability was written down by an initial capital contribution of
£1.743 million. 
The amounts payable to the PPP/ NPD operators each year are analysed into four elements: 
• Service charges and lifecycle replacement costs – value of services including cleaning
and janitorial services, repairs and maintenance, energy, non domestic rates and
insurances debited to the relevant service in the CIES;
• Interest payments – the interest charge on the outstanding Balance Sheet liability,
debited to the Financing and Investment Income and Expenditure line in the CIES;
• Contingent rent – increases in the amount to be paid for the property arising during the
contract, debited to the Financing and Investment Income and Expenditure line in the
CIES;
• Liability repayment– repayment of the principal owed to the PPP operator, applied to write
down the Balance Sheet liability. 
In accordance with Scottish Local Government Finance Circular 10/2022, the Council has
applied a statutory accounting flexibility to the PPP and NPD contracts to realign the value of
the Liability Repayment element of the unitary charge to reflect a prudent charge for the
repayment of the Liability across the useful economic life of the assets. 
S Provisions, Contingent Liabilities and Contingent Assets 
Provisions
Provisions are made where an event has taken place that gives the Council a legal or
constructive obligation that probably requires settlement by a transfer of economic benefits
or service potential, and a reliable estimate can be made of the amount of the obligation. 
For instance, the Council may be involved in a court case that could eventually result in the
making of a settlement or the payment of compensation. 
103

Page 104

Provisions are charged as an expense to the appropriate service line in the CIES in the year
that the Council becomes aware of the obligation, and measured at the best estimate, at the
balance sheet date, of the expenditure required to settle the obligation, taking into account
relevant risks and uncertainties. 
When payments are eventually made, they are charged to the provision carried in the
balance sheet.  Estimated settlements are reviewed at the end of each financial year; where
it becomes less than probable that a transfer of economic benefits will be required (or a
lower settlement than anticipated is made); the provision is reversed and credited back to
the relevant service. 
Where some or all of the payment required to settle a provision is expected to be recovered
from another party (e.g. from an insurance claim), this is only recognised as income for the
relevant service if it is virtually certain that reimbursement will be received if the Council
settles the obligation. 
Contingent Liabilities
A contingent liability arises where an event has taken place that gives the Council a possible
obligation, whose existence will only be confirmed by the occurrence or otherwise of
uncertain future events not wholly within the control of the Council.  Contingent liabilities also
arise in circumstances where a provision would otherwise be made but either it is not definite
that an outflow of resources will be required, or the amount of the obligation cannot be
measured reliably. 
Contingent liabilities are not recognised in the balance sheet but disclosed in a note to the
accounts. 
Contingent Assets
A contingent asset arises where an event has taken place that gives the Council a possible
asset whose existence will only be confirmed by the occurrence or otherwise of uncertain
future events not wholly within the control of the Council. 
Contingent assets are not recognised in the balance sheet but disclosed in a note to the
accounts where it is probable that there will be an inflow of economic benefits or service
potential. 
T Reserves 
Reserves are created by appropriating amounts out of the General Fund Balance in the
Movement in Reserves Statement.  When expenditure to be financed from a reserve is
incurred, it is charged to the appropriate service in that year to score against the
Surplus/Deficit on the Provision of Services in the CIES.  The reserve is then appropriated
back into the General Fund Balance in the Movement in Reserves Statement so that there is
no net charge against council tax for the expenditure. 
Certain reserves are kept to manage the accounting processes for non-current assets,
financial instruments and retirement benefits and do not represent usable resources for the
Council; these reserves are explained in the relevant notes. 
104

Page 105

U Revenue Expenditure Funded from Capital Under Statute 
Expenditure incurred during the year that may be capitalised under statutory provisions but
does not result in the creation of a non-current asset is charged as expenditure to the
relevant service in the CIES in the year.  Where the Council has determined to meet the cost
of this expenditure from existing capital resources or by borrowing, a transfer in the
Movement in Reserves Statement from the General Fund Balance to the Capital Adjustment
Account then reverses out the amounts charged so that there is no impact on the level of
council tax. 
V VAT 
All income and expenditure excludes amounts relating to VAT, as all VAT collected is
payable to HM Revenue and Customs and net VAT paid is fully recoverable by the Council. 
W Fair Value Measurement 
The Council values some of its non-financial assets, such as Surplus Assets and Investment
Properties (Common Good Funds and Trusts only), and some of its financial instruments at
Fair Value.  Fair Value is the price that would be received either on the sale of an asset or to
transfer a liability in an orderly transaction between market participants at the measurement
date.  The Fair Value measurement assumes that the transaction to sell the asset or transfer
the liability takes place either: 
• In the principal market for the asset; or
• In the absence of a principal market, in the most advantageous market for the asset. 
The Council measures the Fair Value of an asset or liability using the assumptions that
market participants would use when pricing the asset or liability, assuming that market
participants act in their economic best interest. 
When measuring the Fair Value of a non-financial asset, the Council takes into account a
market participant’s ability to generate economic benefits by using the asset in its highest
and best use or by selling it to another market participant that would use the asset in its
highest and best use. The Council uses valuation techniques that are appropriate in the
circumstances and for which sufficient data is available, maximising the use of relevant
observable inputs and minimising the use of unobservable inputs. 
Inputs to the valuation techniques in respect of assets and liabilities for which Fair Value is
measured or disclosed in the Council’s financial statements are categorised within the fair
value hierarchy, as follows: 
• Level 1 – quoted prices (unadjusted) in active markets for identical assets or liabilities that
the Council can access at the measurement date;
• Level 2 – inputs other than quoted prices included within Level 1 that are observable for
the asset or liability, either directly or indirectly
• Level 3 – unobservable inputs for the asset or liability. 
105

Page 106

106

Page 107

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Strategic Risk Register 2024/25
Purpose: To inform the Committee of the Council’s agreed Strategic Risk
Register for 2024/25.
Recommendation: That Committee notes the Strategic Risk Register.
1. Executive Summary
1.1 The Strategic Risk Register has been reviewed and updated for 2024/25.
1.2 Three of the eight previous risks remain on the Strategic Risk Register at their existing
risk scores and titles – Inequalities, Cyber Security and Climate Change.
1.3 The risk previously titled Financial Environment is changed to Financial Sustainability
to more closely reflect the fundamental funding issues the Council is facing in this year
and future years budgets. The risk scoring remains the same. The Financial
Sustainability of the Health and Social Care Partnership risk and the Community
Capacity Building & Empowerment risk have increased in risk scoring whereas the
Transformation risk has reduced in scoring.
1.4 A new risk has been added which reflects the impact of a deteriorating property asset
portfolio with insufficient funding, and a previous risk relating to the National Care
Service Risk has been removed.
1.5 The Strategic Risk Register was approved by Cabinet on 19 March 2024.
2. Background
2.1 North Ayrshire Council is committed to ensuring that it is proactive in identifying and
managing the risks impacting on the authority. The Council recognises that a certain
amount of risk is inevitable if the organisation is to achieve its objectives.
2.2 The aim of risk management is to reduce the likelihood and/or impact of risk by
identifying and controlling risks to the Council.  If risk is to be managed appropriately,
and Services are aware of these risks, risk management can contribute positively
towards the organisation's decision-making processes, making the Council more
innovative and effective in its approach to service delivery.
Agenda Item 11
107

Page 108

2.3 The most significant risks are identified through the Council's Strategic Risk Register,
recognising the challenges facing the Council and demonstrating the arrangements in
place to manage these risks. 
2.4 The Strategic Risk Register has been reviewed and updated for 2024/25 and is
attached at Appendix 1 to this report.  For each of the risks detailed within the register
a number of components are identified: 
• Risk proximity factors.
• Risk score.
• Potential effect on the Council's priorities.
• Internal controls currently in place.
• Assessment of controls, and
• Additional actions identified. 
2.5 To assist in the assessment of each risk, the Council’s agreed risk matrix was used to
ensure consistency. This is used to assess the likelihood of occurrence (on a scale
from 1 to 5) and the significance of the impact of the risk should it occur (on a scale
from 1 to 5). The risk score is the product of likelihood multiplied by impact. Only those
risks rated as high or very high (10 or above) will feature on the SRR to ensure a
focus on managing the most significant risks. 
2.6 Four risks remain on the Strategic Risk Register at their existing risk scores –
Financial Sustainability (previously Financial Environment), Inequalities, Cyber
Security and Climate Change. 
2.7 The Financial Sustainability of the Health and Social Care Partnership risk has
increased in risk from score 12 to 16 due to increasing budget pressures. 
2.8 Community Capacity Building and Empowerment risk has increased from score 12 to
16 due to increasing financial and resource demands. 
2.9 Transformation risk has reduced from score 16 to 12 as a result of positive
workstream developments and programme delivery against the requirements of The
Council Plan. 
2.10 An additional risk is proposed around the condition of property and how this is set
within the context of the current financial challenges. 
2.11 The previously identified risk regarding the implementation of the National Care
Service is removed from the Strategic Risk Register as there have been a number of
changes to the proposals. These are as follows: 
• A tripartite agreement between national and local government and the NHS in
Summer 2023 included agreement that statutory delivery functions would remain
with local authorities and health boards, along with assets, employment of staff and
relevant funding.
• Scottish Ministers will exercise strategic framework accountability for NCS services
which will include a role in setting policy, having oversight and providing direction;
this will be done through the establishment of a National Care Service Board, but
otherwise local integration authorities will remain in place but may be subject to
some reform.
108

Page 109

• Timescales have also slipped by 3 years, with the new arrangements not now
expected to be in place until 2029. 
2.12 Very High Risks  
• Financial Sustainability – this risk reflects the ongoing financial challenge
faced by the Council year on year (risk score 20).
• Inequalities – this highlights the socio-economic inequalities faced in North
Ayrshire (risk score 20).
• Property Asset Risk – This reflects the impact of long-term restricted budgets
on the Councils ability to maintain these to a good standard (risk score 20).   
High Risks 
• Cyber Security – this reflects the ongoing risk from external cyber-attack which
is being faced by all organisations (risk score 16).
• Transformation – this reflects the wider risks associated with delivering the
current Transformation Programme and developing a pipeline of future initiatives
(risk score 12).
• Climate Change – this risk has been on the Strategic Risk Register following the
declaration by the Council of a Climate Change Emergency during 2019 (risk
score 16).
• Financial Sustainability of the Health and Social Care Partnership – this
reflects the ongoing financial challenges faced by the Partnership and the risk
these present to the Council (risk score 16).
• Community Capacity Building and Empowerment – this highlights the
challenges associated with the community empowerment act (risk score 16). 
2.13 Council services have identified high level strategic actions within their planning for
2024/25 to help the Council mitigate against its strategic risks. These actions are
detailed in summary format in the Risk Management Action Plans following each Risk
within Appendix 1.  These actions will assist with performance monitoring and
reporting on the strategic risks. 
2.14 The Council’s Internal Audit Plan 2024/25 was approved at the Audit and Scrutiny
Committee on 21 March 2024 and is risk-based with clear links in place between the
audit plan and key risks the Council faces. 
Longer-term risks & Horizon Scanning 
2.15 The Strategic Risk Register identifies the most significant risks which the Council
faces at the present time. 
2.16 The Corporate Risk Management Group identifies any new relevant risks though
internal reviews and external horizon scanning utilising a number of sources. 
3. Proposals 
3.1 Committee is requested to note the Strategic Risk Register 2024/25. 
109

Page 110

4. Implications/Socio-economic Duty 
Financial 
4.1 The Council continues to have a robust long- and medium-term financial planning
framework. Key strands include development of key transformation themes and the
establishment of an Investment Fund that will generate future savings alongside
delivery of a number of key Council priorities. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 The risk to the Council is that North Ayrshire residents, and in particular certain
groups, will experience increasing levels of poverty and its effects. Current control
measures fall into two categories - measures to address the root causes of socio-
economic inequalities - income through employment or benefits – and mitigation
measures to minimise the impacts of poverty. 
Climate Change and Carbon 
4.5 The Council has declared a climate change emergency and has in place an
Environmental Sustainability and Climate Change Strategy. Significant work to help
mitigate the risk of flooding is included within the Capital Plan. The Council is
undertaking an ambitious renewable energy programme. 
Key Priorities 
4.6 A successful risk management framework helps to underpin the delivery of the
Council’s strategic priorities in Our Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The Strategic Risk Register has been reviewed and updated in consultation with the
Executive Leadership Team and the Corporate Risk Management Group and
approved by Cabinet. 
Mark Boyd
Head of Service (Finance) 
110

Page 111

For further information please contact Alex Fitzharris, Team Manager (Risk and
Insurance), on 01294-324515. 
Background Papers
None.
111

Page 112

Appendix 1 - Strategic Risk Report 2024/25 
Risk Code SRR2425_R01 Risk Title Financial Sustainability Latest Note Date 09-Feb-2024
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The risk is that the level of funding from Scottish Government
to local government falls significantly below the level required
to operate services effectively. This will require the Council to
take increasingly difficult and challenging decisions. The
2024/25 local government settlement represents a reduction in
core funding of £2.191m (0.64%). This is against a backdrop of
significant cost increases, resulting in a Budget gap of
£16.000m for 2024/25. The North Ayrshire position is further
affected by a reducing overall population demographic and a
growing elderly population. This will further impact the
Council’s share of funding across the short, medium and long
term.
Although there is a commitment through the Verity House
agreement for Councils and Scottish Government to work
together there continues to be challenges around the level of
flexibility the Council has on key areas of Budget, most notable
in areas like HSCP funding and funding for teachers and
support staff, where conditions remain. The Scottish
Government has passed legislation to give Councils powers to
charge additional council tax for second homes. This is an area
the Council will consider within the context of local
circumstances and island communities.
Scottish Government funding to support the Council’s capital
programme has also been reduced by almost 10% in the
Budget settlement for 2024/25. Set against high inflationary
driven construction costs there is a risk that the 10-year capital
programme will be unaffordable. This could require projects to
be reduced in scale or even ceased.
Funding not keeping pace with demand
and inflationary cost pressures means that
there will be a reduction in some service
areas potentially resulting in higher risks
for service users. The future delivery of
balanced budgets will become increasingly
challenging. The capital programme could
also be significantly impacted leading to
reduced levels of capital investment.
Robust monitoring of the Council’s revenue and
capital budgets is in place as well as regular
reporting of financial performance of the IJB to
Cabinet and Audit and Scrutiny. 
To assist financial planning The Medium and Long-
Term Financial Outlook (LTFO) to 2033/34 was
approved at Council on 13 December 2023 – this is
the cornerstone of the Council's financial planning in
the medium to long term. 
The annual budget process for the General Fund
revenue and Capital Programmes and financial
performance monitoring process will continue to
provide the framework from which control measures
will continue in addressing the financial position.
Delivery of the Council’s Change Programme is also
vital in addressing the Budget challenges and this is
being progressed by the Council’s Transformation
Board, which is chaired by the Chief Executive.
Utilising the Council’s available statutory powers is
another important area in addressing the financial
challenges.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 20 
112

Page 113

Strategic Risk Action Plan Date Updated 09-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Regular financial monitoring of Revenue and Capital Budgets.
09 February 2024:
Ongoing monitoring. 
31-Mar-2025 Mark Boyd 
Maintain Financial Governance Arrangements for IJB.
09 February 2024:
Under ongoing review.
31-Mar-2025 Mark Boyd 
Progress dialogue via COSLA with Scottish Government on a range of
areas including fair funding, multi-year settlements, reduction in levels of
ring-fenced resources, true costs of SG policy areas, financial flexibilities
and a New Deal partnership with SG and local government.
09 February 2024:
Ongoing discussions via COSLA around the Verity House Agreement and the
need for maximum financial flexibility for Councils.
31-Mar-2025 Mark Boyd 
Develop the 2024/25 to 2026/27 revenue budget (medium-term financial
strategy) and capital programme taking account of all pressures and
savings via Directorates and Transformation programme.
09 February 2024:
Options to address the £16m Budget gap for 2024/25 have been developed
for elected member consideration at Council Meeting on 28 February 2024.
Following this, require to develop a more detailed programme of options to
address the structural funding challenges over the medium and long-term.
31-Mar-2025 Mark Boyd 
113

Page 114

Risk Code SRR2425_R02 Risk Title Inequalities Latest Note Date 25-Jan-2024
Risk Owner Audrey Sutton/Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
North Ayrshire residents, and in
particular certain excluded
groups, will experience
increasing levels of poverty and
its effects, as a result both of the
economic situation and Covid-
19.
Health inequality is closely
linked to poverty, employment
and people's earliest
experiences as children, and will
increase.
The population of North Ayrshire
is projected to fall over the next
10 years but there will also be a
larger proportion of the
population considered
dependent (not economically
active).
The impact on specific risk
groups is greatest for our
children, young people and
families, unemployed people
and those in in-work poverty
and people exposed to the
risks of drug and alcohol
addiction.
Demand for HSCP and
Council Services will
increase.
As reductions in resources
increase, early intervention
and prevention activities are
at risk, thus increasing the
potential for an increase in
costly crisis interventions.
The local economy will be
impacted by reduced
spending power by
economically inactive
residents.
The HSCP re-affirmed its commitment to Tackling Inequalities by continuing to consider it a key priority with the
Partnership’s Strategic Plan.
Through the HSCP strategic plan, the Partnership sets out actions to tackle inequality through its Partnership Pledge and
across its strategic priorities. Tackling inequalities is addressed across HSCP service areas. An example of actions to
help address local inequalities include:
Establishing the Money Matters service in 9 GP practices and 7 local schools in the more deprived areas of North
Ayrshire. This will improve accessibility of the service to those who would benefit most. Building on this approach through
the launch of the Financial Inclusion Partnership bringing a range of key partners and stakeholders together to improve
access and support for the most vulnerable NA residents.
Increase the number of employability mentors in Justice Services, to support those with experience of the justice service
into meaningful employment or training opportunities and to help divert away from criminal behaviours.
Working closely with Housing colleagues to support transitions from care and ensuring care experienced young people
can access a positive and stable housing destination.
In our Drug and Alcohol Services, we are implementing actions to reduce the number of local drug and alcohol related
harms and deaths. This includes implementing the national MAT (Medicated Assisted Treatment) standards and
increasing the number of ABIs (Alcohol Brief Interventions) delivered across North Ayrshire.
Through the Caring for Ayrshire programme, we have set out a phased approach to improve local primary care premises
(GP Practices and Health Centres). This will improve overall professional capacity within GP practices for Multi-
Disciplinary Teams, ensuring the right support is available for local people with health concerns.
Investment in early intervention teams and approaches in Children’s Services to support vulnerable families, including in
Child Protection and Whole Family Support.
The Council considers reducing inequalities to be at the heart of its work.
The Communities and Education Directorate leads the Community Planning Partnership for the Council and the CPP has
recently developed a new Local Outcomes Improvement Plan, the purpose of which is reducing inequalities. The themes
are Wellbeing, Work and World, the latter addressing climate change and fuel poverty. Locality Planning priorities and
Community Investment Fund funded initiatives are also focused on a range of inequalities, including poverty, age-related
inequalities and digital inequalities. Recent CIF-funded projects have focused on employability, addictions and community
food.
The Directorate also leads the work of the Child Poverty and Cost of Living Board, chaired by the Council Leader. The
five strategic themes of the Board to date have been:
• No Wrong Door – access to services
• Employability
• Food
• Islands
• Childcare
5 4
114

Page 115

Work to address child poverty and the Cost-of-Living crisis includes a range of employability initiatives to support parents
and people with disabilities, each of whom are Scottish Government priority groups.
Progress has been made with partners through a series on mini-enquiries, ensuring that lived experience influences
developments and actions. This is supported by the data and Single Shared Assessment projects being developed by the
Transformation team, to provide holistic support for residents who need it most.
The Child Poverty Early Intervention Fund is being used to address gaps in current planning and provision. Recent
funding decisions have been made, as a consequence of the mini-enquiries - to support employability and travel,
childcare developments and support for care experienced young people and families.
The Scottish Government has provided a second year of funding to address inequalities on the islands.8 This has been
used to fund energy support, welfare advice and support, third sector interventions and school activities.
The commitment to reducing inequalities is also reflected in the Communities and Education Directorate plans:
• The Educational Service Improvement Plan
• Connected Communities strategic plans and
• Facilities Management plans.
Examples of actions to reduce inequalities:
• Deployment of Scottish Attainment Challenge funding to reduce the poverty related attainment gap in schools
• Use of the Pupil Equity Fund to ensure equity of pupil experience in schools, at the discretion of head teachers
• Cost of the School Day actions to reduce, for example, the cost of school uniforms and clothing, food and outings
• Support for care experienced young people, both in schools and through youth services
• Additional national and local investment in Active Schools to focus on inequalities and equity
• The Fairer Food Network, with 14 community larders which support the needs of individual communities
• A network of warm spaces and events to mitigate energy use and social isolation
• Work to support “New Scots,” in schools, with families and in community settings through language support and
capacity building, including women’s groups
• LGBT support groups for young people and those over 18
• Mentoring support for young people in secondary schools through a partnership with MCR Pathways
Participation strategies for children and young people and adults to ensure our strategies and investment are informed by
as wide a range of views as possible.
Status Risk Score
Heat Map 
Change in Score Approach
No Change Treat
Stable 20 
115

Page 116

Strategic Risk Action Plan Date Updated 25-Jan-2024 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Global and national conditions which affect the cost-of-living and poverty continue
to undermine the effectiveness of local control measures. Substantial work
continues to mitigate inequalities but child poverty data, for example, continues to
show an increase. National data collection methodologies have changed which
explains the change in part, but North Ayrshire continues to have c. 29% of
children living in poverty.
Although unemployment has reduced, it continues to be a driver of poverty, with
in-work poverty a key factor.
Access to benefits is a key driver of poverty and the range of strategies described
above continues to ensure we are maximising access to entitlements. The Single
Shared Assessment work will improve this.
25 January 2024:
The wide range of strategies and initiatives described above, and
further developed and implemented, will continue to make a
significant contribution to a range of inequalities. 
Actions are being progressed and remain within the target dates
for completion.
31-Mar-2025 Audrey Sutton;
Caroline Cameron 
116

Page 117

Risk Code SRR2425_R03 Risk Title Financial Sustainability of the Health and Social Care Partnership Latest Note Date 06-Feb-2024 
Risk Owner Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Resources have not kept pace with the demand for and
cost of social care services. The budget settlement for
2024-25 is extremely challenging with a gap of over
£10m across the IJB. Financial modelling suggests
significant ongoing challenges across the medium-term.
There is no certainty around future funding against
growing demand, increasing costs and demographic
pressures, with one-year budget settlements remaining
in place.
The ongoing work to review the Integration Scheme and
to develop new risk-sharing arrangements between the
Council and Health Board in relation to the acute set
aside and primary care prescribing present a financial
risk to the Partnership.
An overspend in the region of £3.7m is projected for
2023-24 which will reduce the reserves held by the
Partnership to less than the recommended minimum
level of 2%. Low-volume high-cost care packages and
care placements and an increasing reliance on agency
staff continue to present a particular financial challenge
to the Partnership.
Funding levels could result in
savings being made that are not
in alignment with the strategic
plan. This could impact on the
future demand levels e.g.
reduction in early intervention
and prevention means that
future demand is increased. 
An in-year overspend position
impacts on financial reserves
and ultimately poses a financial
risk to the Council and NHS
Board as funding bodies. 
Funding levels increase the
requirement to transform
services at scale and pace.
The IJB actively monitors the financial position with regular detailed
reporting. Directors of Finance of the Council and Health Board have
oversight and regular updates are provided to the Council's Cabinet.
There is an integrated approach to managing the totality of NHS and
Council resources delegated to the IJB. A three-year Medium-term
Financial Outlook is updated on a rolling basis each year.
Previous financial settlements have seen both partners meet the
Scottish Government settlement conditions with any additional
resources passed to the IJB.
The IJB had uncommitted financial reserves of £5.821m at the
beginning of April 2023, which remains towards the lower end of the
good practice target of 2%-4%. In addition, £2m of additional reserves
were set aside at the start of 23-24 to offset the likelihood of an
overspend in-year, this reduces the impact on unearmarked reserves
of the current projected overspend to £1.7m.
The Partnership has developed a new 3-year Transformation Plan
2024-2027 which will be approved by the IJB in March 2024. There is
£2.2m of earmarked reserves set aside to support service change
and re-design.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
Increase from 12 to 16 Tolerate
Increasing risk 16 
117

Page 118

Strategic Risk Action Plan Date Updated Feb-2024 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Budget Monitoring - Regular budget monitoring reports to IJB are effective. 
06 February 2024:
Budgets are closely monitoring by the finance team in conjunction
with budget holders to enable corrective action to be taken and
regular in-year budget monitoring reports are presented to the
IJB.
31-Mar-2025
Caroline
Cameron;
Paul Doak 
Corrective Action – Transformation Board is effective  
06 February 2024:
A three-year Transformation Plan covering the period 2024-2027
will be approved by the IJB in March 2024. This focusses on
addressing the future financial challenge in a sustainable way, as
well as reviewing service delivery models and implementing local
and national priorities. 
31-Mar-2025
Caroline
Cameron;
Paul Doak 
118

Page 119

Risk Code SRR2425_R04 Risk Title Cyber Security Latest Note Date 17-Jan-2024 
Risk Owner Fiona Walker
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The potential compromise of business operations or a
data breach orchestrated via either digital channels or
the IT infrastructure. This can include targeting of the
user base. Risk derives from both Council operations
and those of its supply chain. 
The increasing importance of delivering services
through digital channels and maximising efficiency
through effective and secure use of technology. This
includes a growing adoption of cloud-based computing
resources which extend processing capabilities, and
associated risks, beyond the Council’s network. 
Hybrid remote and mobile working is now the normal
working practice for over 3,000 staff. Such a distributed
work force increases the complexity of protecting
against cyber and data protection risks. 
Failure by Services to adopt and comply with
strategies, policies and procedures may
result in a failure to adequately ensure the
desired levels of cyber-security required to
maintain and protect council systems and
data. 
There may be a significant impact on the
authority through the release of personal
and/or sensitive information resulting in a loss
of public confidence and significant financial
loss incurred through fines and service
disruption. 
A successful cyber-attack (malicious external
or internal action) on the Council’s IT
environments could also result in significant
service disruption, loss of income streams
and possible data loss/exposure. 
Impacts of a cyber-attack could include
economic (i.e. inability to collect online
payments), societal disruption (i.e. loss of
diaries and client appointments), and
reputational damage (i.e. loss of public
confidence in digital services).
It is recognised that it is not possible for any
organisation to expect to be completely protected
against continually evolving cyber threats. A threat
actor with sufficient motivation, resource and capability
will be able to compromise the most secure system. 
The Council takes a sociotechnical approach to
reducing risk by continually developing protective
measures through technical, organisational and
people-focused controls. 
Technical controls are implemented in areas such as
network defences, secure configuration of systems,
user authentication, malware protection, and
vulnerability management. These are based on best
practice and independently tested on an annual basis
to confirm their effectiveness in accordance with
compliance schemes. 
The Council maintains a comprehensive set of policies,
standards, guidelines, metrics and reporting
mechanisms as part of its information security
governance structure. A comprehensive training and
awareness programme is delivered to nurture a cyber-
aware workforce and culture.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16 
119

Page 120

Strategic Risk Action Plan Date Updated 17-Jan-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Incident Detection and Response – Recent cyber-attacks on public
sector organisations highlight the need for robust incident detection
and response procedures and technologies. The current response
procedures been shown to be effective based on incidents
experienced so far, however detection capabilities will need to be
reviewed and improved.
17 January 2024:
A joint procurement of a Managed Security Operation Centre (SOC) service with
other local authorities is being taken forward by the Digital Office.  This has
however been delayed due to resource challenges and to date no procurement
timescales have been set.
Given the delays to the national SOC procurement project, the Council will
consider other SOC alternatives and Manage Detect & Response (MDR) services.
31-Mar-2025 Fiona Walker 
Training and Awareness
17 January 2024:
Cyber Security in person training has resumed with multiple sessions being
organised to tackle the backlog incurred due to the pandemic.
The Cyber Security Essentials E-Learning course is a mandatory training
requirement for all staff with access to Council digital resources. Staff are also
encouraged to complete this annually. In addition, the course has been converted
into a briefing to provide as a toolbox talk to reach all of our workforce.
Phishing simulations continued to be hosted to test the effectiveness of training
and raise awareness.
Ongoing Fiona Walker 
120

Page 121

Risk Code SRR2425_R05 Risk Title Transformation Latest Note Date 09-Feb-2024
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
There is a risk that transformation and change
activities, which are core to the future delivery
models and long-term financial sustainability of
both the Council and Health and Social Care
Partnership, fail to deliver at the level of scale
and pace required.
Failure to deliver transformational change
will impact on the Council’s financial
sustainability, effectiveness of service
delivery and delivery of the outcomes set
out in the Council Plan 2023-28 and the
Local Outcome Improvement Plan
(LOIP). 
Failure to deliver the HSCP
Transformation programmes across the
Partnership, involving North Ayrshire
Council (NAC) and NHS Ayrshire & Arran
(NHSAA) services may lead to the
identified outcomes not being delivered;
resulting in financial instability, reduced
performance, deteriorating patient
outcomes, and reputational damage
within North Ayrshire Health and Social
Care Partnership (NAHSCP). 
Failure to embed cultural transformation
activities may lead to difficulties in
building future workforce capacity and in
ensuring we have an engaged, skilled
and knowledgeable workforce to meet
service demand.
The transformation programme aligns to the Council Plan and is
monitored via the Transformation Board. The Board is chaired by
the Chief Executive.
Workstreams have been developed across Transport and Travel,
Accessing our Council, Land and Property assets, Sustainability,
Financial Inclusion as well as ongoing reviews across Waste
Services, ELC, Learning Resources and Housing. 
HSCP have an established Transformation Board to closely monitor
progress with plans, regular updates on programme to the IJB and
regular meetings with the Chief Executive and S95 Officer to review
progress and mitigation plans. Cultural transformation activities
continue to evolve to support the Council’s transformation and
improve effectiveness and capability. This includes sharing learning
and skills, engagement, design experiments and a whole systems
approach to transformation and change. 
Our workforce planning approach utilises a variety of tools and
techniques, such as career development, succession planning,
vacancy management, redeployment and early release schemes to
ensure our workforce requirements for the future, in terms of skills
and capabilities, are planned. Each Head of Service has a workforce
plan, and these are monitored six-monthly with continued HR
support and guidance to ensure service review and redesign of the
workforce is on track.
3 4
Status Risk Score
Heat Map  
Change in Score Approach
Reduce from 16 to 12 Treat
Stable 12 
121

Page 122

Strategic Risk Action Plan Date Updated 25-Jan-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Existing project level governance and controls remain effective and are
constantly reviewed.
25 January 2024: 
Progress on Transformation projects continues to be governed and
monitored via the Transformation Board which is chaired by the
Chief Executive. Meetings held quarterly Workstreams have been
fully developed and progress and all actions tracked. Financial
efficiencies across commercial property, waste review, learning
resource review, ELC review and the sustainability programme have
been fed into the Council’s Budget programme for 2024/25 to
2026/27.
Quarterly
Mark Boyd / Chief
Executive and
Executive Directors 
Review current governance arrangements and project delivery in view of
land and property workstream to seek optimal delivery aligned to the
council’s net zero ambitions.
25 January 2024:
Key progress made around Irvine Based locality property Review.
Next stages to present Cabinet Paper in March 2024 to consider
plans.
March 2024
Mark Boyd / Chief
Executive and
Executive Directors 
122

Page 123

Risk Code SRR2425_R06 Risk Title Climate Change Latest Note Date 08-Feb-2024
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Climate change is expected to continue and
worsen in the future if no action is taken,
with increases to mean global temperatures,
sea level rises and the increasing frequency
and severity of weather events such as
floods, heatwaves, droughts and storms. 
More frequent and intense heavy rainfall
events increase the risk of soil erosion and
flooding. 
Rises in mean sea level increases risks of
coastal erosion, flooding, saltwater intrusion
and soil salinisation (risk to agricultural land
and freshwater habitats). 
Severe weather is already affecting public
services across Scotland, with operational,
reputational, financial and legal
consequences. 
There is also an ongoing impact of severe
winter weather including snowfall and
freezing temperatures which impact service
delivery and the integrity of our roads open
space and buildings infrastructure. This shift
in weather patterns caused by climate
change is also affecting biodiversity across
Scotland.
Increased frequency of severe weather
conditions and flooding events may lead to
more instances of damage to Council
infrastructure and property, interruptions to
service delivery and increased demands
on services, often with little notice. 
Risk to life, transport disruption and
pollution to the local environment, as well
as impact adversely on the local economy
if businesses are unable to operate. 
Council requirement to provide immediate
response and manage the adverse effects
of more frequent and severe weather
emergency situations, including support to
local communities and businesses. 
The Council is required to comply with the
‘Public Bodies Climate Change Duties’
under the Climate Change (Scotland) Act
2009. These duties require the Council to
assess the risks, threats and opportunities
associated with climate change and
identify actions to increase resilience to
climate change.
North Ayrshire Council declared a Climate Emergency in June 2019, committing
to act on climate change and reduce carbon emissions. In January 2020 the
Council approved the target to become net-zero carbon by 2030, for both Council
estate emissions and area-wide emissions.
Following implementation of the Council’s third Environmental Sustainability and
Climate Change Strategy (2021-23), Cabinet approved the new Sustainable North
Ayrshire Strategy (2024-27) in December 2023. This strategy provides a road
map to achieve the net zero carbon emissions by 2030 target. 
There are 5 workstreams within the Sustainable North Ayrshire strategy, namely
Energy, Nature, Transport, Waste and Adaptation. We continue to utilise
Adaptation Scotland’s Capability Framework to ensure North Ayrshire takes a
strong, proactive approach to adapting to climate change.  Officers are
participating in the Sustainable Scotland Network’s ‘Adaptation Scotland
Benchmarking Group’ to learn and share best practice with other local authorities.
Adaptation actions are identified within the Ayrshire Flood Risk Management Plan
(2021), the Ayrshire Local Flood Risk Management Plan (2022), the Ayrshire
Shoreline Management Plan and in the Adaptation Capability Framework.
Flood studies are undertaken to help the Council identify areas that are at risk of
flooding and to appraise options to reduce flood risk to communities and
infrastructure.
In addition, actions to mitigate Climate Change risk are held within strategies such
as the Core Paths Plan, Outdoor Access Strategy, Local Biodiversity Action Plan,
and Weather and Winter Emergencies Plan. Asset management plans are in
place which are regularly reviewed for our Roads, Fleet, Housing, Property and
Open Spaces. 
Furthermore, through the Ayrshire Civil Contingencies Team there are emergency
planning arrangements in place in the event of severe weather and flooding
conditions causing major disruption and damage to the area or to individual
communities within it.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16 
123

Page 124

Strategic Risk Action Plan Date Updated 08-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Reducing Carbon Emissions:
North Ayrshire Council declared a Climate Emergency in June
2019, committing to act on climate change and reduce carbon
emissions. In January 2020 the Council approved the target to
become net-zero carbon by 2030, for both Council estate
emissions and area-wide emissions.
The Council has taken action against climate change since our
first Carbon Management Plan in 2006/07, by working to reduce
emissions associated with Council services, and using the
baseline year of 2005/06 from which to measure progress.
Since the baseline year of 2005/06, Council estate emissions
have reduced by 68.9%, from 67,719 tonnes of carbon dioxide
equivalent (tCO2e) to 20,940 tCO2e (a reduction of 854 tCO2e
from the previous year). Area-wide emissions are published by
BEIS. Current records show total emissions have reduced across
North Ayrshire by 42.6%, from 1,437 kilo-tonnes of carbon
dioxide (ktCO2) in 2005 to 835 ktCO2 in 2019.
To ensure North Ayrshire Council can develop a leading, cross-
sector and community led approach we established a Climate
Change Steering Group (CCSG) in 2021. The CCSG is chaired
by the Cabinet Member for Green Environment and Economy,
and brings together young people, local businesses and
community organisations from across North Ayrshire.
Existing controls remain effective and are under review as our
response to climate change develops and we progress towards
achieving net zero by the 2030 target.
8th February 2024:
Implementation of the Sustainable North Ayrshire strategy, which includes 9 strategic
principles and 46 actions under the 5 workstreams of Energy, Nature, Transport, Waste
and Adaptation. The 9 strategic principles which are being implemented are:
1.We will take a whole system approach (including behaviour change) to tackling climate
change as far as possible, including identification of optimal approaches to achieve
social and economic benefits alongside environmental ones.
2.We will continue to clarify and report transparently on our emissions so that the North
Ayrshire emissions baseline is clearly understood.
3.We will complete a Local Heat and Energy Efficiency Strategy to help understand
where efforts to reducing emissions and reducing fuel poverty are best focused.
4.We will prioritise actions in relation to two of the biggest emissions sources where
have the most influence, commonly referred to as ‘heat and fleet’, including through
project pathfinder approaches for decarbonisation of domestic and non-domestic
buildings and vehicles to bring scale and pace to emissions reduction.
5.We will work with stakeholders, including the Scottish Government, to articulate the
potential costs and skills requirements to meet our net-zero aspirations.
6.We will expand on the need for adaptation measures, recognising mitigation alone will
not combat the impacts of climate changes on communities.
7.We will identify opportunities for expansion of carbon sinks and other carbon capture
technologies, which are expected to be an essential element of our net-zero strategy to
mitigate residual emissions by 2030.
8.We will seek to expand the remit and membership of the CCSG to enable us to work
more closely with communities, taking account of outcomes from recent projects such as
Climate Action Towns and Carbon Neutral Islands.
9.We will explore the potential for carbon accounting, including carbon budgets for
Council services, to support our journey to net-zero.
Updates on progress are provided through the Council’s performance reporting system,
Pentana, on a quarterly basis, and governed through the Sustainability Board. Actions
are designed to be directly and indirectly responsible for carbon reduction and deliver
other socio-economic benefits.
31-Mar-2027 Russell
McCutcheon 
124

Page 125

Strategic Risk Action Plan Date Updated 08-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Flood Risk Management Plan:
Cycle 2 of the Ayrshire Local Flood Risk Management Plan has
been developed and was published on 31st December 2022.
Studies and modelling will be undertaken to identify and prioritise
vulnerable areas where financial damage and risk to life are most
likely.
There is an ongoing programme of monthly inspections of debris
screens which have been installed to prevent vulnerable culverts
from blocking and causing flooding. CCTV inspections of culverts
are also undertaken to identify blockages and deterioration of
assets that might cause flooding. This has been effective in
reducing flooding, although there are capacity issues h that this
process cannot address.
The Upper Garnock Valley FPS has been completed and is
currently providing flood protection.
Ayrshire Shoreline Management Plan:
The Ayrshire Shoreline Management Plan will be replaced with a
Coastal Change Adaptation Plan. The adaptation plan will enable
the Council and other stakeholders to effectively plan our future
actions whilst allowing for flexibility in response to future changes.
It will incorporate recent international and UK advances in
adaptation and shoreline management planning to allow for local
interpretation and involvement.
22 February 2024:
1. We will undertake the actions outlined in cycle 2 of the Ayrshire Local Flood Risk
Management Plan. 
2. We will continue to look for opportunities to implement Natural Flood Management
and we will develop a range of further flood protection measures, which can be put
forward as schemes for inclusion in cycle 3 of the Ayrshire Flood Risk Management Plan
and the Ayrshire Local Flood Risk Management Plan.
3. We will complete the Millport Coastal FPS and the Mill Burn FPS.
4. We will continue to Inspect culverts, screens and watercourses for clearance and
repair work in accordance with the published schedule and prioritise maintenance works
that would substantially reduce flood risk. Efforts will be made to continue to identify
unknown culverts and add these assets to the ongoing inspection and maintenance
process.
5. We will develop the Ayrshire Coastal Change Adaptation Plan in partnership with
South Ayrshire Council and other stakeholders.
30-06-2028 Thomas Reaney 
125

Page 126

Risk Code SRR2425_R07 Risk Title Community Capacity Building and Empowerment Latest Note Date  05 February 2024
Risk Owner Rhonda Leith
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Unrealistic timescales for implementation of
aspects of legislation of the Community
Empowerment Act (Scotland) 2015, such as
Community Asset Transfer. 
Pressure to support community capacity building
and the variation of needs within a reducing
workforce. 
Duplication of effort across HSCP and Locality
Partnerships to foster community participation and
deliver engagement activities.
Complying with the complex and resource
intensive consultation legislation in service
redesign.
Rising energy and utility costs relating to property
management.
Budget savings and pressure on property
maintenance budgets.
Where the risk is not managed effectively the
potential benefits of community capacity building
and empowerment may be lost. 
Widening inequality gap between those
communities where levels of capacity and
engagement with the empowerment agenda are
high and those with less social capital where
interest remains low, which constrains the ability
to influence the planning and delivery service. 
Any disconnect between the Council’s
aspirations, community appetite for increasing
ownership of assets and what communities
themselves feel able and prepared to commit to
can result in community assets reverting back to
Council. 
Accelerating asset transfer risks losing services
and facilities and risks the ability to plan, connect
and deliver strategic services. 
Over-engagement carries disengagement and
engagement fatigue.
Increased property costs can be a deterrent for
organisations engaging and completing the CAT
process.
Lack of budget to undertake proactive
maintenance may result in NAC buildings falling
into disrepair detracting organisations from
progressing to lease and or ownership of NAC
assets.
Ongoing commitment to community empowerment and
locality partnerships from CPP. 
Six locality partnerships and alignment with HSCP
locality arrangements. 
Leadership of the CPP Senior Officers’ Group. 
Enabling approach with community partners and support
with third sector interface to build capacity and identify
opportunities for growth and sustainability. 
Reviewed guidance and processes relating to
community empowerment functions. 
Participatory budgeting approach local grants,
commitment to PB with partners and leading practice in
mainstreaming participatory approaches 
External funding bid help for groups through regular
meetings with third sector, funders and funding officers. 
Membership of The Consultation Institute.
Investment from Community Asset Transfer Start Up
Fund, prioritising additional staffing capacity to support
CAT in Connected Communities and TACT.
A collaboration and shared resource approach across
Connected Communities Teams will be taken to ensure
the Service deliver on this priority.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
Increase from 12 to 16 Tolerate
Stable 16 
126

Page 127

Strategic Risk Action Plan Date Updated 05 Feb 2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Implementation of Community Empowerment Act: 
Existing controls remain effective and are kept under review.  
05 February 2024: 
Strategic CLD Plan 2021-2024 identifies priorities for capacity building and the programme
of community support is addressing needs. No further update at this time.  31-Mar-2025 Rhonda Leith 
05 February 2024: 
Post implementation the plan will be monitored and reported as per statutory timescales.
31-Jul-2024 Rhonda Leith 
Staff capacity: 
Existing controls remain effective however forthcoming VER
structure changes will result in a reduction of CLD professional
staff and risks further pressures on staff to deliver effectively to
key outcomes.
05 February 2024: 
CLD service redesign will be implemented from 1st of April with a 6-month review date. The
redesign in light of VER impacts has resulted in the loss of the Capacity and Empowerment
Team, all key priorities of the team will be embedded in the newly formed localities Contact
agreement established with key 3rd Sector organisations This will mitigate the impact on
developments of the key outcomes as detailed in the CLD plan. The CLD plan review will
commence in April, following guidance due to be issued by the Scottish Government which
will be informed by the National Review Of CLD.
31-Jul-2024 Rhonda Leith 
Duplication of effort:
Clearly defined roles and lean processes are reviewed and
maintained to avoid duplication of effort and minimise time and
resource wastage. The team foster open communication
channels with both staff and key stakeholders.
05 February 2024:
Existing controls are effective but remain under proactive review.
31-Jul-2024 Rhonda Leith 
Consultation:
Existing controls remain effective. Existing controls remain
effective and hybrid engagement models have been
implemented post covid to encourage and provide greater
access to participation.
05  February 2024:  Proactive review 6 months post VER restructure to assess the
effectiveness of CLD support for community engagement and consultation.
No further update at this time.
31-Jul-2024 Rhonda Leith 
Increased property costs and lack of investment in community
assets.
05 February 2024
A collaborative approach involving PMI and CC is being used to survey and evaluate
community buildings that require investment. CAT funds have been identified for corrective
actions, which will involve incorporating green investments to support future CAT and
Service development initiatives.
31-Jul-2024 Rhonda Leith 
127

Page 128

Risk Code SRR2425_R08 Risk Title Property Asset Risk Latest Note Date  08-Feb-2024
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The long-term impact of restricted budget
availability for investment in the Council’s property
assets means these assets means they are in
declining condition and have greater long term
investment needs. 
Systemic building safety issues have been
evidenced by issues such as national high profile
safety issues, and the presence of RAAC through
the public sector property portfolio. These have
highlighted the substantial increasing burden of
property asset management.
There have been a number of near misses or
critical failures of aging heating plant and
equipment which the council cannot afford to
replace on a programmed basis.
Inflationary pressures, and on-going volatility in the
construction & related activities sphere, place
further difficulties in the ability of restricted budgets
to address all priorities. 
Maintenance issues and failure of building
components are increasingly likely to result in
disruption to service delivery. There is also an
increasing risk of health and safety and statutory
compliance obligations not being achieved. 
Property events requiring significant interventions
leading to service disruption, closure of facilities,
decant etc. are in increasing in frequency and
often over-lapping (often coinciding with weather
events).
Property condition information is gathered and recorded
within the Council’s electronic asset management
system, providing a baseline to measure building
element lifecycle replacement requirements across the
corporate estate.
Limited investment is therefore targeted on priorities. 
Reactive maintenance, and statutory compliance are
also undertaken corporately by PMI by appropriately
trained / experienced staff. 
There is an on-going Transformation programme
workstream focusing on property rationalisation as a
means of reducing the financial burden of the estate
through reducing overall area occupied (aligned to
carbon reductions). 
Post Incident reviews and lessons learned exercises
with actions undertaken where feasible to do so.
Risk based property reviews are underway to examine,
on a property by property basis, where property risks
have the potential to impact service delivery. The
information gathered influences both investment plans
and business continuity plans. This work is on-going in
respect of the school estate and is being rolled-out to
other services’ assets.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
New Risk Tolerate
Increasing 20 
128

Page 129

Strategic Risk Action Plan Date Updated 08-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
CC&M team within PMI managing reactive maintenance and
statutory compliance.
Team resources stretched; however, restricted budgets are principal risk. Ongoing Russell
McCutcheon 
Asset management team within PMI collecting asset condition
information and leading prioritisation of lifecycle investment.
Improved asset management system is being investigated; however, restricted budgets
are principal risk. Ongoing Russell
McCutcheon 
Property rationalisation programme Locality based property review work currently underway to increase scale and pace of
implementation. Ongoing Russell
McCutcheon 
Risk based property review process Requires up to date property information, including client information and cross service
buy-in to be effective. Ongoing Russell
McCutcheon 
129

Page 130

130

Page 131

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Internal Audit Annual Report 2023/24
Purpose: To provide the Committee with an annual report on the work of
Internal Audit during 2023/24 and provide an opinion on the
governance, risk management and internal control environment
of the Council.
Recommendation: The Committee is asked to note the content of the annual report
and the opinion of the Senior Manager on the Council’s
governance, risk management and internal control environment.
1. Executive Summary
1.1 The purpose of this report is to present the annual report on the internal audit activity
during 2023/24, and to provide an independent opinion on the adequacy and
effectiveness of the Council’s governance, risk management and internal control
systems for the year ended 31 March 2024.
2. Background
2.1 The Public Sector Internal Audit Standards (PSIAS) require that the Chief Internal
Auditor prepares an annual report on the activities of Internal Audit and that the report
should contain a view on the adequacy of the Council’s governance, risk management
and internal control frameworks. The annual report for 2023/24 is attached at
Appendix 1 and outlines the role of Internal Audit, the performance of the section
during the year and the key audit findings. It also contains the annual internal audit
opinion.
2.2 The required annual report for financial year 2023/24, together with the statement on
internal controls, is included in Appendix 1.
2.3 The revised internal audit plan for 2023/24 (approved by the Audit and Scrutiny
Committee in November 2023) has been substantially completed. Audit fieldwork
remains in progress on eight assignments. One audit assignment is at draft report
stage, meaning the assurance opinion can be included in the overall annual audit
opinion.
2.4 All audit findings during the year support and inform the objective opinion of the Senior
Manager (Audit, Fraud, Safety and Risk) on the adequacy of the Council’s
Agenda Item 12
131

Page 132

governance, risk management and internal control environment. The assurance
category given to each individual audit informs the overall level of assurance. 
2.5 The annual internal audit opinion also contributes to the Annual Governance
Statement which is published as part of the Council’s annual accounts and is included
under separate cover to this Audit and Scrutiny Committee meeting for approval. 
2.6 Based on the audit work carried out, the opinion of the Senior Manager (Audit, Fraud,
Safety and Risk) is that reasonable assurance can be placed on the adequacy and
effectiveness of the Council’s systems of governance, risk management and internal
control. 
3. Proposals 
3.1 It is proposed that the Committee notes the content of the annual report and the
opinion of the Senior Manager on the Council’s governance, risk management and
internal control environment. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of Internal Audit helps to support the efficient delivery of the strategic
priorities within Our Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
5. Consultation
132

Page 133

5.1 Council Services are consulted on the findings of Internal Audit throughout the year.
No specific consultations have taken place in relation to this annual report. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Risk), on 01294 324524. 
Background Papers
None.
133

Page 134

Appendix 1
INTERNAL AUDIT ANNUAL REPORT 2023/24 
1. Introduction 
1.1. The purpose of this report is to summarise the Internal Audit activity for 2023/24 and
provide an opinion on the overall adequacy and effectiveness of the Council’s
governance, risk management and internal control frameworks. 
1.2. The Council’s Section 95 Officer has overall responsibility for Internal Audit in North
Ayrshire Council. The Senior Manager (Audit, Fraud, Safety and Risk) reports to the
Section 95 Officer, with the right of access to the Chief Executive and the Chair of the
Audit and Scrutiny Committee on any audit matter. These rights of access help ensure
the organisational independence of Internal Audit. 
1.3. The presence of an effective internal audit function contributes towards, but is not a
substitute for, effective control. It is the responsibility of management to have
adequate controls in place and to ensure these controls are operating effectively. A
sound control system will help safeguard assets, ensure records are reliable, promote
operational efficiency and ensure adherence to Council policy and procedure. Such
systems of internal control can provide only reasonable and not absolute assurance
against loss. 
2. Reporting requirements of the Public Sector Internal Audit Standards (PSIAS) 
2.1. Internal Audit operates in accordance with the PSIAS requirements and is an
independent, objective assurance and consulting activity designed to add value and
improve an organisation’s operations. It helps an organisation accomplish its
objectives by bringing a systematic, disciplined approach to evaluate and improve the
effectiveness of risk management, control and governance processes. 
2.2. Internal Audit operates within the Internal Audit Charter, most recently approved by
the Audit and Scrutiny Committee in March 2023. 
2.3. The PSIAS places a number of reporting obligations on the Chief Internal Auditor in
respect of the annual report. These obligations are summarised below: 
PSIAS Ref Requirement Evidence
1110 The chief audit executive must
confirm to the board, at least
annually, the organisational
independence of the internal
audit activity.
The Senior Manager reports
directly to the Audit and Scrutiny
Committee, and unfettered access
is available to the Chief Executive
as required.
1320 The results of the quality and
assurance programme and
progress against any
improvement plans must be
reported in the annual report.
The results of the external quality
assessment, carried out in 2022,
were reported to the Audit and
Scrutiny Committee in September
2022. All actions are complete.
134

Page 135

PSIAS Ref Requirement Evidence
2450 The chief audit executive must
deliver an annual internal audit
opinion and report that can be
used by the organisation to
inform its governance
statement.
This report to Audit and Scrutiny
Committee provides the annual
report and statement of assurance
on internal controls.
2450 The annual internal audit
opinion must conclude on the
overall adequacy and
effectiveness of the
organisation’s framework of
governance, risk management
and control.
This report to Audit and Scrutiny
Committee provides the annual
statement of assurance at Annex
B.
2450 The annual report must also
include a statement on
conformance with the Public
Sector Internal Audit Standards
and the results of the quality
assurance and improvement
programme.
This report to Audit and Scrutiny
Committee provides a statement
on the conformance with the
PSIAS at Section 5 below. 
3. Planned and Actual Activity during 2023/24 
3.1. The internal audit plan was approved by the Audit and Scrutiny Committee in March
2023 with a mid-year change to the plan approved in November 2023. Productive time
is allocated in the plan to the delivery of audit assignments with a balance of time
retained within the service for non-productive activities which includes management
and strategy, attendance at meetings, administration and staff training and
development. 
3.2. The mid-year revised plan included 26 assignments where an audit output was
anticipated. Eleven of these have been completed, one is at draft report stage, eight
are at various stages of work in progress, one is not started, and five are deferred. 
The results of the draft reports and work in progress assignments will be reported to a
future meeting of the Audit and Scrutiny Committee. 
3.3. In line with the Council’s defalcation procedures, all instances of suspected fraud and
irregularity should be reported to Internal Audit. These are investigated by the
specialist Corporate Fraud Team and are not included within this annual report. 
3.4. All audit reports finalised during 2023/24 were reported to meetings of the Audit and
Scrutiny Committee.  A summary of outputs achieved are included in Annex A. 
3.5. The outcomes from the audit work during the year have primarily been positive, with
mostly substantial and reasonable assurance opinions. Two audit reports have been
finalised during the year where elements of the scope have resulted in a limited
assurance opinion. These are as follows: 
• An HR/Payroll system review was carried out covering the CHRIS21 HR and
Payroll system used by the Council. From that review, reasonable assurance was
obtained with regard to administration of payroll processes. However there was
135

Page 136

limited assurance obtained on the timely administration by services to provide
accurate and timeous information to ensure the effectiveness and accuracy of
payroll runs. The HR/Payroll Team are continuing to liaise with services to ensure
these matters are promptly rectified. This includes reminders to services, but also
the development of reporting around absence and overpayments which will allow
all Heads of Service to reiterate the importance of these matters with their
managers.
• A substantial cross-service review of Cyber Resilience Business Continuity was
carried out, as Internal Audit continues to work through the categories and
domains contained within the Scottish Government’s Cyber Resilience
Framework. Again this review concluded with a split opinion. Reasonable
assurance was obtained for most areas within the scope of the review, however
there was limited assurance obtained with regards to the Data Protection Impact
Assessment (DPIA) section of the audit due to all systems sample tested as part
of the audit either having no DPIA in place or no DPIA signed off by the Data
Protection Officer. The services are working with the Information Governance
Team to ensure the prompt sign off of all outstanding DPIAs. The DPIA tracker
held by Information Governance has also been further developed to reflect the
various stages of the outstanding DPIAs. 
3.6. It is important to also highlight some of the most positive outcomes arising from the
audit work concluded during the year. This includes reviews of Financial Resilience
and Viability, and Workforce Planning, both of which are significant priorities for the
Council and both concluded with substantial audit opinions. This provides evidence
that these most significant risks for the Council are being effectively managed in line
with best practice. 
3.7. These findings, together with those from other audits carried out and the individual
assurance levels, contribute to the annual internal audit opinion in Annex B of this
report. 
4. Audit Resources 
4.1. The Internal Audit section is directly managed by the Team Manager (Internal Audit),
who reports to the Senior Manager (Audit, Fraud, Safety and Risk). The Senior
Manager is responsible for Internal Audit, as well as Corporate Fraud, Risk and
Insurance and Corporate Health and Safety. 
4.2. As well as the Team Manager, the Internal Audit team consisted of two part-time
Internal Auditors as well as a part-time Computer Auditor. 
4.3. All staff within the section hold a relevant qualification, either through an institute
which is part of the Consultative Committee of Accountancy Bodies (CCAB) or the
Institute of Internal Auditors (IIA). 
4.4. The Internal Audit Charter requires the Senior Manager to report to the Section 95
Officer and the Audit and Scrutiny Committee if resources available fall below an
acceptable level for the audit work required. No instances of resource limitation have
occurred during 2023/24. 
5. Performance 
136

Page 137

5.1. During 2023/24, Internal Audit provided regular updates to the Audit and Scrutiny
Committee on the activities of the service. Elected Members had the opportunity to
discuss all Internal Audit reports and question either the Senior Manager or relevant
officers from Council services.  The Senior Manager carried out Elected Member
training to the Committee in May 2022, individual training for new members joining the
Committee during the year, and further training is planned for 2024. 
5.2. The Council’s performance management system, Pentana, is used to follow-up on
audit action points. Officers with responsibility for implementing audit actions are
required to update the system and updates are provided to the Audit and Scrutiny
Committee on a quarterly basis. Where actions are overdue, officers are required to
attend the Committee to update Elected Members on plans to ensure that actions are
implemented. 
5.3. The Senior Manager is required to confirm annually internal audit’s compliance with
the Public Sector Internal Audit Standards (PSIAS). A significant achievement during
2022/23 was the successful completion of the External Quality Assessment. Under
the terms of the PSIAS, each organisation’s Internal Audit team is required to
undertake an External Quality Assessment (EQA) at least once in each five-year
period. This helps to ensure compliance with the standards. 
5.4. A peer to peer review network of the Scottish Local Authorities Chief Internal Auditors
Group (SLACIAG) is in place. The review of the Council's Internal Audit team was
completed by West Dunbartonshire Council and was reported to the Audit and
Scrutiny Committee in September 2022. The review assessed the compliance of the
Council's Internal Audit team with the 14 sections of the PSIAS and noted that the
team fully conforms with 13 of the standards and generally conforms with the
remaining one. Overall the assessor was able to provide substantial assurance that
the Council's Internal Audit team complies with the requirements of the PSIAS. There
were four minor routine recommendations for improvement to further improve
compliance, and these have all been completed. In summary, the Internal Audit
service continues to conform with the PSIAS. 
5.5. Internal Audit has a strong working relationship with all Council services and is
frequently asked for audit advice on an ad-hoc basis. The volume of these requests is
outwith the control of Internal Audit however it is important that Internal Audit
responds to these requests when asked, as it ensures advice is provided at the right
time to ensure organisational value is maximised. In 2023/24, there were 36 requests
for service advice. Added to this, Internal Audit is included on the project board of a
number of Corporate working groups, and these are listed in Annex A. 
6. Other Responsibilities 
6.1. The Senior Manager is also the Chief Internal Auditor for the North Ayrshire
Integration Joint Board (NAIJB). In the interests of information sharing, the results of
the NAIJB audit work are shared with the Audit and Scrutiny Committee. 
7. Opinion 
7.1. There is a formal requirement for the Chief Internal Auditor to prepare an assurance
statement on the adequacy of internal control systems within the Council. The internal
audit annual statement on the adequacy of internal controls is included in Annex B.
137

Page 138

8. Conclusion 
8.1. The 2023/24 internal audit plan has been substantially completed. There are no
limitations of scope to the issued audit opinion.
138

Page 139

Summary of Internal Audit Work 2023/24 Annex A 
Type Audit Opinion Reported to A&S
Committee
Actions Arising
Priority
1
Priority
2
Priority
3 Total
COMPLETED WORK
Assurance Glow Reasonable 05/09/2023 0 4 0 4
Investigation Transport Substantial 05/09/2023 0 0 0 0
Assurance Payroll Transaction Testing* Reasonable 05/09/2023 1 3 0 4
Assurance ASN Provision* Reasonable 05/09/2023 2 1 0 3
Assurance Income Collection* Reasonable 05/09/2023 1 1 0 2
Assurance Accounts Payable Transaction
Testing Q2 Reasonable 14/11/2023 2 1 0 3
Assurance Carers (Scotland) Act 2016 Substantial 14/11/2023 0 1 0 1
Assurance Early Years Provision* Substantial 14/11/2023 0 0 1 1
Assurance Financial Resilience and Viability Substantial 14/11/2023 0 0 0 0
Assurance Employee Services HR/Payroll
System and Processes* Reasonable/Limited 25/01/2024 3 1 0 4
Assurance ICT Supplier Management* Reasonable 25/01/2024 0 3 0 3
Assurance Workforce Planning Substantial 21/03/2024 0 0 0 0
Assurance Standalone Early Years Centres Reasonable 21/03/2024 0 1 0 1
Assurance Community Resources
Keyholding Substantial 21/03/2024 0 0 0 0
Assurance Procurement Cards Substantial 30/05/2024 0 0 0 0
Assurance Ayrshire Growth Deal – Revenue
Projects Substantial 30/05/2024 0 1 0 1
Assurance Cyber Resilience Business
Continuity Reasonable/Limited 30/05/2024 5 8 0 13
Annual
Accounts Community Councils n/a n/a n/a n/a n/a n/a
Annual
Accounts
Tenants and Residents
Associations n/a n/a n/a n/a n/a n/a
REPORTING PHASE**
Assurance Supply Teachers Substantial 0 0 0 0 0
WORK IN PROGRESS
139

Page 140

Summary of Internal Audit Work 2023/24 Annex A 
Type Audit Opinion Reported to A&S
Committee
Actions Arising
Priority
1
Priority
2
Priority
3 Total
Assurance Movers/Leavers Education tbc tbc tbc tbc tbc tbc
Assurance Property Asset Management tbc tbc tbc tbc tbc tbc
Assurance Payroll Transaction Testing tbc tbc tbc tbc tbc tbc
Assurance Community Based Support –
Adults tbc tbc tbc tbc tbc tbc
Assurance iPayImpact tbc tbc tbc tbc tbc tbc
Assurance Housing Rental Income and
Arrears tbc tbc tbc tbc tbc tbc
Assurance Regeneration Delivery Plan and
Funding tbc tbc tbc tbc tbc tbc
Assurance Code of Corporate Governance tbc tbc tbc tbc tbc tbc
NOT STARTED
Assurance Community Funding tbc tbc tbc tbc tbc tbc
OTHER/ONGOING
Consultancy O365/Information and
Collaboration Project Board n/a n/a n/a n/a n/a n/a
Consultancy Sustainability and Climate
Change n/a n/a n/a n/a n/a n/a
Consultancy Municipalisation Project Board n/a n/a n/a n/a n/a n/a
Consultancy Education Maintenance
Allowance (EMA) n/a n/a n/a n/a n/a n/a
Consultancy Waste review n/a n/a n/a n/a n/a n/a
Consultancy Education processes for
employees n/a n/a n/a n/a n/a n/a
Small
Advisory 36 various requests n/a n/a n/a n/a n/a n/a
* 2022/23 audit but not sufficiently concluded at the time of the 2022/23 annual report, therefore opinion included 2023/24.
** Audits not yet finalised but sufficiently in draft to conclude on the level of assurance.
140

Page 141

Annex B 
Internal Audit Annual Statement on the Adequacy of Internal Controls 
To the Members and Chief Executive of North Ayrshire Council 
As Chief Internal Auditor for North Ayrshire Council, I am pleased to present my annual
statement on the overall adequacy and effectiveness of the framework of governance, risk
management and control of the Council for the year ended 31 March 2024. 
Respective responsibilities of management and internal auditors in relation to
governance, risk management and control 
It is the responsibility of the Council’s senior management to determine, establish and
maintain sound systems of governance, risk management and control to ensure that the
organisation’s resources are properly applied in a manner and on the activities intended
and that these arrangements are sufficient to address the risks facing their services. This
includes responsibility for the prevention and detection of fraud. Management is also
charged with monitoring the continuing effectiveness of these arrangements and taking
action as appropriate. It is the responsibility of the Chief Internal Auditor to provide an
annual assessment of the overall adequacy and effectiveness of the Council’s framework of
governance, risk management and control. 
Sound internal controls 
The main objectives of the Council’s internal control systems are to: 
• ensure adherence to management policies and directives in order to achieve the
organisation’s objectives;
• safeguard assets;
• ensure the relevance, reliability and integrity of information, so ensuring as far as
possible the completeness and accuracy of records; and
• ensure compliance with statutory requirements. 
Any system of control can only ever provide reasonable and not absolute assurance that
control weaknesses or irregularities do not exist or that there is no risk of material errors,
losses, fraud, or breaches of laws or regulations. Accordingly, the Council is continually
seeking to improve the effectiveness of its systems of internal control. 
The work of internal audit 
Internal audit is an independent, objective assurance and consulting activity designed to
add value and improve an organisation’s operations. It helps an organisation accomplish its
objectives by bringing a systematic, disciplined approach to evaluate and improve the
effectiveness of risk management, control and governance processes. The Internal Audit
section operates in accordance with United Kingdom Public Sector Internal Audit Standards
(PSIAS) which came into force with effect from 1 April 2013 (updated in March 2017). The
requirements under PSIAS represent best practice and are mandatory. 
141

Page 142

Annex B 
The Chief Internal Auditor prepares an annual internal audit plan which outlines the
programme of work to be undertaken. The plan is developed utilising a risk-based
methodology and takes into account the requirement placed upon the Chief Internal Auditor
to deliver an annual internal audit opinion. The plan needs to be flexible to reflect the
changing risks and priorities of the organisation. The plan, and any material changes to the
plan during the year, are approved by the Audit and Scrutiny Committee. 
All internal audit reports are brought to the attention of management, including system
weaknesses and/or non-compliance with expected controls, together with agreed action
plans. It is management’s responsibility to ensure that due consideration is given to internal
audit reports and that appropriate action is taken on audit recommendations. This includes
management taking remedial action where appropriate or accepting that there may be a
level of risk exposure if the weaknesses identified are not addressed for operational
reasons. Internal Audit is required to ensure that appropriate arrangements are made to
determine whether action has been taken on internal audit recommendations or that
management has understood and assumed the risk of not taking action. Matters arising
from internal audit work are also reported to the Chief Executive, Head of Finance (as
Section 95 Officer), Members of the Audit and Scrutiny Committee, and external audit. 
Summary of Internal Audit Activity 2023/24 
A total of 17 internal audit reports have been issued during 2023/24. Eight audit opinions
give substantial assurance and seven reasonable assurance. Two reports with a wider
scope have combined audit opinions of Limited/Reasonable. A further audit report is in draft
and anticipated to have a Substantial assurance opinion. A diverse range of audit areas
have been covered during the year. As well as planned assignments, Internal Audit also
offers advice and guidance on the Council’s control environment as and when required and
will carry out non-fraud investigations which are brought to our attention. 
A range of recommendations have been raised in the areas covered by the 2023/24
internal audit plan. Many expected key controls have been in place and operating
effectively, however Internal Audit has also identified scope for improvement in some
systems. All 40 action points raised in the year have been accepted by management and
will result in continued improvement of the Council’s governance, risk management and
control environment. 
Basis of Opinion 
The evaluation of the control environment is informed by a number of sources: 
• the audit work undertaken by Internal Audit during the year to 31 March 2024;
• the audit work undertaken by Internal Audit in previous years and knowledge of any
significant audit findings after the year end;
• the assessment of risk completed during the preparation of the annual audit plan;
• reports issued by the Council’s external auditors and other review and inspection
agencies;
• knowledge of the Council’s governance, risk management and performance monitoring
arrangements; and
142

Page 143

Annex B 
• any other items brought to the attention of internal audit by whatever means which may
warrant further investigation. 
Opinion 
On the above basis, Internal Audit can provide reasonable assurance over the framework
of governance, risk management and control and that adequate controls were in place and
were operating throughout the Council in 2023/24. 
Laura Miller FCCA
Senior Manager (Audit, Fraud, Safety & Risk)
30 May 2024
143

Page 144

144

Page 145

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Corporate Fraud Team Annual Report 2023/24
Purpose: To provide the Audit and Scrutiny Committee with an update
report on the work of the Corporate Fraud Team during
2023/24.
Recommendation: That the Committee notes the work carried out by the Corporate
Fraud Team.
1. Executive Summary
1.1 The Corporate Fraud Team provides the Council with the capacity to investigate fraud
both within and against the organisation.
1.2 Committee receives bi-annual updates on the work of the team. A mid-year update for
2023/24 was provided in November 2023 and this report provides an overview of the
key activities and outcomes for the full year.
2. Background
Investigation Work
2.1 Referrals for investigation have been made to the team from a number of different
sources, including Revenues and Benefits and Housing, members of the public and
other agencies and local authorities. The publicity used by the team, including posters
and leaflets, advertising on Council vans and contact information on the Council
website, continues to be successful in generating a stream of referrals.
2.2 Investigations have been carried out across a range of areas including employee-
related matters as well as Council Tax, Discretionary Housing Payments, Scottish
Welfare Fund, Blue Badges and Housing tenancy issues. Although responsibility for
investigating Housing Benefit fraud now lies with the DWP Single Fraud Investigation
Service (SFIS), issues may be identified by the Corporate Fraud Team which can
result in changes being made to benefits in payment. Formal joint working
arrangements are in place with the DWP for cases where there are suspected frauds
relating to both DWP benefits and Council Tax Reduction.
2.3 The team investigates all tenancy abandonments which are referred by Housing.
While Housing focus on recovering the tenancy, the Corporate Fraud Team can add
Agenda Item 13
145

Page 146

value by locating the missing tenant, which can often lead to changes to benefits or
discounts in payment elsewhere, as well as enabling Housing to recover costs
associated with house clearances and cleaning. 
2.4 Employee-related investigations are the subject of a separate report to the appropriate
Service and the findings are also reported to the Audit and Scrutiny Committee as
each investigation is finalised. 
Outcomes 2023/24 
2.5 The team received 398 referrals for investigation during 2023/24 (2022/23: 357
referrals). All referrals made to the team are investigated although many can
subsequently prove unfounded. 
2.6 385 cases were closed during 2023/24 (2022/23: 346 cases). These can be
categorised as follows: 
Outcome Number of Cases
Closed with no issues identified 184
Referred to another agency (including SFIS) or Council
Service for investigation
81
Closed with results achieved (fraud, error or other
recovery/action)
120
TOTAL 385 
2.7 Fraud and error totalling £0.139m were identified and are categorised in the table
below: 
Category Value (£000)
Housing Benefit 27
Council Tax (including CTR, Single Person Discount
and other recoveries)
84
Discretionary Housing Payments 2
Care Fees 18
Other 8
TOTAL 139 
2.8 In addition to the financial outcomes noted above, other outcomes/benefits were noted
as follows: 
• 69 tenancies were recovered by Housing with some assistance from the Corporate
Fraud Team.
• 65 referrals were made to the Single Fraud Investigation Service.
• 22 referrals were made to other services, local authorities or agencies.
• In respect of blue badge cases investigated, two cases concluded with a warning
letter to the badge holder, two warning letters were issued to third parties, and one
badge was recovered.
• 22 investigations resulted in updates and corrections to records.
• Five internal investigation reports have been taken forward with recommended
actions for control improvements. 
146

Page 147

International Fraud Awareness Week 
2.9 International Fraud Awareness Week took place from 12 – 18 November 2023.  IFAW
was promoted throughout North Ayrshire Council by social media campaign. 
National Fraud Initiative (NFI) 
2.10 The National Fraud Initiative (NFI) is a long-established exercise which takes place
across the UK every two years and involves the matching of relevant datasets across
public bodies to identify possible fraud or error for further investigation. 
2.11 The latest data sets were submitted to the Cabinet Office in October and November
2022, with most matches released in early 2023. However, a number of matches have
been released more recently in late 2023 and early 2024. This information has been
disseminated to the appropriate teams across the council for investigation. 
2.12 The National Exercise and the ReCheck exercise for 2022/23 is now complete. Audit
Scotland will publish their national report in summer 2024, and thereafter the Audit
and Scrutiny Committee will receive details of the full results as they relate to North
Ayrshire. 
Compliance with the Code of Practice 
2.13 CIPFA published their Code of Practice on Managing the Risk of Fraud and Corruption
in 2014. The Code covers five key principles which are to: 
• Acknowledge the responsibility of the governing body for countering fraud and
corruption;
• Identify the fraud and corruption risks;
• Develop an appropriate counter fraud and corruption strategy;
• Provide resources to implement the strategy; and
• Take action in response to fraud and corruption. 
2.14 Each principles has specific steps which are required to be met in order to comply with
the Code. A self assessment against the Code, its principles, and its specific steps
has been carried out. Having considered these principles, it is concluded that North
Ayrshire Council has adopted a response that is appropriate for its fraud and
corruption risks and commits to maintain its vigilance to tackle fraud. 
3. Proposals 
3.1 It is proposed that the Committee notes the work carried out by the Corporate Fraud
Team. 
147

Page 148

4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of the Corporate Fraud Team helps to support the efficient delivery of the
strategic priorities within Our Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 No consultation has been required in the preparation of this report. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Risk), on 01294 324524. 
Background Papers
None
148

Page 149

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Internal Audit and Corporate Fraud Action Plans:
Quarter 4 update
Purpose: To advise the Audit and Scrutiny Committee on the progress
made by Council Services in implementing the agreed actions
from Internal Audit and Corporate Fraud reports as at 31 March
2024.
Recommendation: That the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions;
and (b) challenges those Services that have not implemented
actions within the previously agreed timescales.
1. Executive Summary
1.1 The CIPFA document 'Audit Committee Principles in Local Authorities in Scotland'
highlights that Audit Committees should monitor and review the progress made in
implementing audit recommendations.
1.2 Service managers are responsible for ensuring that agreed actions arising from
Internal Audit and Corporate Fraud reviews are implemented.  This provides
assurance that identified control weaknesses have been addressed and are being
managed effectively.
1.3 All actions are monitored on the Pentana system and service managers are
responsible for updating Pentana as they progress each action.  This enables Internal
Audit to monitor progress on a 'real-time' basis and address any delays in
implementation.
1.4 This report details the position as at 31 March 2024.
2. Background
2.1 The last report to the Audit and Scrutiny Committee on 21 March 2024 highlighted that
there were nine actions outstanding at 31 December 2023, none of which were
overdue as they were all due for completion after 31 December 2023.
2.2 In addition to these nine carried forward actions, there has been one new action
agreed, giving a total of 10 action points for review.
Agenda Item 14
149

Page 150

2.3 Services have completed four actions since the last report.  All Council Services are
required to retain evidence of work carried out in completing their actions and Internal
Audit carries out 'spot-checks' on a sample of completed actions on an ongoing basis. 
2.4 Of the remaining six actions, one was partially complete at 31 March 2024 and the
remaining five actions were not due for completion until after that date. 
2.5 Appendix 1 to this report provides the Committee with full details of the one action that
has not yet been fully completed within the agreed timescales. 
3. Proposals 
3.1 It is proposed that the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions; and (b) challenges
those Services that have not implemented actions within the previously agreed
timescales. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The effective implementation of agreed Internal Audit and Corporate Fraud actions
helps to support the efficient delivery of the strategic priorities within Our Council Plan
2023-2028. 
Community Wealth Building 
4.7 None.
150

Page 151

5. Consultation
5.1 Council Services are consulted during the completion of each Internal Audit and
Corporate Fraud review and have also provided updates on progress made in
implementing action points.
Mark Boyd
Head of Service (Finance)
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Risk), on 01294 324524. 
Background Papers
None.
151

Page 152

4
Actions due by 31st March 2024 but not started or partially complete
Code IA2022PA019b Description
Audit Action: A minimum technical standard for CCTV systems should be set for the Council. A
Council-wide audit of CCTV inventory should be carried out to assess compliance of CCTV assets
against the standards, which will give an indication of the level of capital investment required to bring
the Council’s CCTV systems up to an appropriate standard and form the basis of a bid for capital.
An approval process should be introduced to ensure new CCTV purchases meet the requirements
of the standards.
Audit Finding: Audit were advised that there are various capital budgets in place covering vehicles
and property lifecycle investment. However, there is no formal replacement programme for CCTV
equipment.
Risk: Substandard systems that aren’t fit for the intended purpose. CCTV footage is not available or
not usable when required. 
Priority 2 Latest Note
Update provided by Scott McKenzie/Aileen Craig: Work in relation to assessment of CCTV
assets continues to be undertaken by Protective Services. This has taken much of available
capacity, however a scheme of delegation for the CCTV and OOH team will be finalised shortly to
address this issue, which is the main reason for the drift in the anticipated completion date of this
action.  To assist with capacity and expertise, an external contractor is to be appointed to capture
the physical data from the systems installed across council properties. The necessary procurement
paperwork is being finalised and a contractor will be appointed shortly to commence the work to
capture the physical data. Protective Services also continue to advise on the operational
requirements for new or replacement systems, thereby ensuring ongoing compliance for current
projects. DPIAs for CCTV systems across the Council continue to be assessed as and when
required. To date 246 members of staff have completed the I-Learn CCTV awareness course.
Revised due date – 31st December 2024.
Progress Bar Original Due Date 30-Jun-2022 Due Date 31-Mar-2024
Parent Code & Title IA2022PA019 CCTV in Council Buildings and Vehicles
Managed By Aileen Craig
Assigned To Mark Boyd; David Hammond
152

Page 153

NORTH AYRSHIRE COUNCIL
30 May 2024                                                                                                                                                            
Audit and Scrutiny Committee
Title: Internal Audit Reports issued
Purpose: To inform the Committee of the findings of Internal Audit work
completed between March and April 2024.
Recommendation: That the Committee considers the outcomes from the Internal
Audit work completed.
1. Executive Summary
1.1 The Council's local Code of Corporate Governance requires effective arrangements to
be put in place for the objective review of risk management and internal control. 
Internal Audit is an important element in this framework as it reviews internal controls
and offers Elected Members and officers an objective and independent appraisal of
how effectively resources are being managed.
1.2 The remit of the Audit and Scrutiny Committee includes the monitoring of Internal
Audit activity.  The submission and consideration of regular reports assists the
Committee in fulfilling this remit.
2. Background
2.1 This report provides information on Internal Audit work completed between March and
April 2024.  Internal control reviews have been completed in respect of the areas
detailed in Appendix 1 to this report. The aim of these reviews is to provide assurance
that the internal control framework within the areas examined is appropriate and
operating effectively.
2.2 The findings from each audit assignment have been notified in writing to the Chief
Executive, the Section 95 Officer and the relevant Executive Director and Head of
Service on the completion of each assignment.  Where appropriate, this has included
an action plan with recommendations for improving internal control.  Appendix 1
includes the report and action plan from each audit.
2.3 The findings from three separate audit assignments are detailed at Appendix 1 to this
report and the levels of assurance for each are noted in the table below:
Agenda Item 15
153

Page 154

Audit Title Assurance Level
Procurement Cards Substantial
Cyber Resilience Business Continuity Reasonable/Limited
Ayrshire Growth Deal – Revenue Projects Substantial 
3. Proposals 
3.1 It is proposed that the Committee considers the outcomes from the Internal Audit work
completed between March and April 2024. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of Internal Audit helps to support the efficient delivery of the strategic
priorities within Our Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The relevant Services are consulted on Internal Audit findings during each audit
assignment. 
154

Page 155

Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Risk), on 01294 324524. 
Background Papers
None.
155

Page 156

PROCUREMENT CARDS 
1 Background  
1.1 When procurement cards are used in line with Council guidance they provide a
number of benefits to both Services and the Council as a whole.  These include:-
• significant time savings from processing less purchase orders and invoices
• one payment per month per card, from the council to the bank eliminating
multiple payments
• reduction in petty cash purchases and cash holdings
• opportunity to purchase items at lower cost through internet
• clear audit trails. 
2 Objectives and Scope  
2.1 The objective of this audit was to ensure:-
• The number of cards in issue is being controlled and reviewed
• Access to imprest (cash) is controlled, and not automatically granted to all
cardholders
• Transactions are being reviewed and approved timeously. 
3 Findings  
3.1 In 2023 all Services were instructed to review and, if necessary, rationalise the
number of procurement cards allocated to their officers.  
3.2 eProcurement also carried out a review of the data within SDOL in 2023.   
Cardholders  
3.3 All applications for a procurement card must be made via an eform.  Within the
eform:-
• Applicants must confirm they have completed online procurement card
training 
• Applicants must confirm if the imprest function requires to be activated on
the card
• Applicants must detail the type of purchases they intend to make with the
card and (if applicable) imprest
• Applications must be approved by an officer of Grade 14 or above, with
the exception of HSCP officers who have their applications approved by
the Head of Service (HSCP Finance & Transformation).  
3.4 The above controls ensure that only those with a genuine business need are
approved for a procurement card.  
3.5 A comparison of the number of cardholders between February 2024 and March
2023 confirmed an overall reduction in the number of procurement cards from
360 to 295.  All Services have either maintained or reduced the number of cards
allocated to their officers.  The following table summarises the comparison
results:-  
156

Page 157

Imprest  
3.6 Activating the imprest function allows a cardholder to withdraw cash using their
procurement card.  
3.7 Cardholders are not automatically granted access to this function – it must be
requested, justified and approved.  For new cardholders this is done as part of
the application process (as detailed in 3.3 above).  For existing cardholders, the
request is made via email.  
3.8 Audit reviewed the number of cards with the imprest function activated in
February 2024 as compared to March 2023.  
3.9 The number of cards with the imprest function activated has increased over the
review period from 91 in March 2023 to 119 in February 2024.  
3.10 Audit discussed this increase with eProcurement. eProcurement explained that
the number of imprest users reported as at March 2023 is artificially low.  Whilst
preparing user reports for Services to review, an issue with the recording of
cardholder function access was identified.  Reports were not flagging a number of
imprest users as having the function when they did, in fact, have it.  
3.11 eProcurement immediately reviewed all cardholders records and updated as
necessary. This update resulted in a revised figure of 130 imprest users.  Reports
were not circulated to Services until this exercise was complete.  
3.12 Audit selected a sample of 10 users who have been given imprest status in
SDOL between March 2023 and February 2024 for detailed review.  
3.13 5 of the 10 were genuine new imprest users.  Audit reviewed the application
process for each of these users.  All stages of the process as set out in 3.7 have
been completed and documented.  
3.14 The remaining 5 were not genuine new users but were picked up as such by
Audit testing due to the error noted in 3.11.  For each of these users, Audit
ensured the report provided to Services for review was reflecting the true access
status of the user.   No issues were noted during testing.  
157

Page 158

Monitoring  
3.15 Card transactions are not posted to Integra until they have been both reviewed
(by the cardholder) and approved (by the approver) in SDOL. Delays in this
approval process can impact on budget monitoring.  
3.16 Every month emails are sent to all reviewers and approvers reminding them of
the need to review or approve any outstanding transactions.  
3.17 In addition, eProcurement produce a quarterly report of outstanding transactions
for circulation to senior managers. Managers are responsible for reviewing this
report and taking action to address any issues highlighted.  
3.18 Audit obtained details of all outstanding transactions as at 4 January 2024 and
calculated the age of the transaction per Directorate. The following table
summarises these results:-   
3.19 Based on the above, most transactions are being both reviewed and approved
within the first 50 days. 
3.20 The number of transactions outstanding for more than 50 days has reduced over
the review period – in January 2024 there were 449 outstanding as compared to
767 in March 2023. 
3.21 Imprest withdrawals remain outstanding on SDOL until the cash has been spent
in full.  This will account for some of the transactions outstanding for more than
50 days, and is not necessarily reflective of poor transaction management. 
4 Internal Audit Opinion  
4.1 Overall, substantial assurance was obtained with regard the controls surrounding
the issuing and ongoing monitoring of procurement cards. 
158

Page 159

Definitions of Assurance Levels: 
Substantial
A sound system of governance, risk management and control exist, with
internal controls operating effectively and being consistently applied to
support the achievement of objectives in the area audited.
Reasonable
There is a generally sound system of governance, risk management and
control in place. Some issues, non-compliance or scope for
improvement were identified which may put at risk the achievement of
objectives in the area audited.
Limited
Significant gaps, weaknesses or non-compliance were identified.
Improvement is required to the system of governance, risk management
and control to effectively manage risks to the achievement of objectives
in the area audited.
None
Immediate action is required to address fundamental gaps, weaknesses
or non-compliance identified. The system of governance, risk
management and control is inadequate to effectively manage risks to the
achievement of objectives in the area audited. 
NB The level of assurance given is at the discretion of Internal Audit.  
159

Page 160

CYBER RESILIENCE BUSINESS CONTINUITY 
1 Background  
1.1 Business continuity was last audited in 2018/19.  
1.2 The audit program is based on Section 14 of the Public Sector Cyber Resilience
Framework which is called Business Continuity. The overall objective is to ensure
information security continuity shall be embedded in the organisation’s business
continuity management systems. 
Section 14 covers the following 6 areas, all of which will be included in the audit:
• data recovery capability, 
• backup policies and procedures, 
• disaster recovery policies and procedures, 
• business continuity & disaster recovery testing policies and procedures, 
• Data Protection Impact Assessments and 
• business continuity contingency plans.    
1.3 IT Services are responsible for the backup process within the Council’s data
centres.  Audit testing has been restricted to the IT backup process.  
1.4 A sample of business continuity plans that reference key IT systems were
selected for audit testing.  The same key IT systems were used to test Data
Protection Impact Assessment.   
2 Objectives and Scope  
2.1 The objectives of the audit were to ensure that:
• Recovery controls are in place to protect against information/data being lost or
compromised.
• Backup copies of information, software and system images shall be taken and
tested regularly.
• The Council has well defined and tested processes in place to ensure the
continuity of key operational services in the event of failure or compromise.
• Scenario-based exercises and processes to test recovery response plans are
planned and performed.
• DPIAs are undertaken to determine the impact of the intended processing on
the protection of personal data where the processing is likely to result in a high
risk to the rights and freedoms of individuals.  The DPIA should consider the
technical and organisational measures necessary to mitigate that risk.
• Contingency mechanisms are in place to continue to deliver services in the
event of any failure or compromise of any system or service.    
3 Findings   
Data Recovery Capability  
3.1 Site Recovery Manager (SRM) is the disaster recovery product used for Windows
servers and IT provided a list of what is managed via this process. This allows a
160

Page 161

quicker recovery of all servers on the list instead of restoring each server
individually.  There is a separate disaster recovery process in place for Unix
servers which also allows for a quicker recovery of such servers instead of
restoring each server individually.  The Council’s key IT systems have data
recovery capability.  There are a number of locally stored IT systems not covered
by the SRM or Unix disaster recovery process and there is no priority list to
decide which order these IT systems are recovered in the event of a major cyber
security event. (action a)  
3.2 The auditor reviewed the Site Recovery Manager list of servers and compared
this to the Commvault backup schedule report.  This test identified a server on
Site Recovery Manager that cannot be matched to a backup plan on the
Commvault backup schedules report.  IT has provided evidence this has now
been allocated to a backup plan.   
Backup Policies and Procedures  
3.3 Commvault Hyperscale is the backup product for on-premise infrastructure and IT
systems.  Data stored in the primary data centre is backed up to a secondary
data centre which is at a different physical location and a third copy is stored
offsite using a cloud product.  The secondary data centre also provides a second
site for data recovery capability in the event of a disaster but there is limited
capability at the second site.    
3.4 The auditor reviewed the Commvault schedules report which lists all servers, their
associated backup plan and evidence of when the last backup was taken.  The
auditor checked the backup process at a point in time and confirmed the backups
were successful.  However, it should be noted there were a number of servers
that were not allocated to a backup plan.  IT Services advised there is some
housekeeping required to clean up the Commvault schedule, most of which are
due to old servers that no longer need to be allocated to a backup plan but can
still be used to restore historical backups.  IT reviewed and cleaned the
Commvault schedule during the course of the audit and also advised that going
forward, ITSM requests should be made to decommission servers and this
includes a task to remove it from the backup plan.  
3.5 Commvault Metallic is the product which is used to provide additional offsite
backup for the M365 application data. This includes the back up of data for
Exchange, SharePoint, OneDrive and Teams.  This backup is taken every 8
hours and there is a Metallic Commvault console which is used to monitor and
control this backup process.  The auditor checked the status of this backup
process at a point in time and there were no findings to report. 
Disaster Recovery Policies and Procedures  
3.6 IT Services provided a copy of the Disaster Recovery (DR) plans overview
spreadsheet which lists 91 DR plans across the different areas within IT and it
also lists 650 historical DR plans.  Initially, there was information missing but IT
have since updated this to ensure the last review date for completed plans and
expected completion dates for incomplete plans are now recorded. There are 51
plans with the status ‘complete’ or ‘awaiting review’, 38 plans have the status
‘under development’ or ‘not started’ and 2 plans have no status recorded.  The
161

Page 162

Team Manager (Operations) advised the historical data will be deleted, this
spreadsheet will be moved to a SharePoint list and have a flow that will
automatically email plan owners at 12 months to review or remove if the solution
has been decommissioned.  In addition, monthly DR meetings are now scheduled
to progress the completion of outstanding DR plans. (action b)  
3.7 The DR plans reviewed by the auditor do not document the recovery time
objective (RTO) for the operational service.  The Team Manager (Operations)
advised this is difficult to calculate given the different scenarios that could impact
it but agreed an average RTO should be added to the DR plans.  (action c)   
BC/DR Testing Policies and Procedures  
3.8 IT Services have identified the need to test the backup and disaster recovery
processes on a quarterly basis.  Testing is planned to start in quarter 1 of 2024/25
for Windows Server test restore, Site Recovery Manager test recovery, Database
test restore, Unix server test restore and network device test restore.  Testing for
M365 test restore began in Q3 2023/24.  In addition, the planned Business
Continuity and Disaster Recovery Test Plan exercises have been rescheduled to
start again in 2024/25.  They have been delayed due to a vacant Team Manager
(ICT and Cyber Security) post that has now been filled.  (action d)   
Data Protection Impact Assessments (DPIA)  
3.9 There is a Data Protection Impact Assessment SharePoint page on Connects
which provides information on this process and provides a link to the Data
Protection Impact Assessment Information and Guidance document; however,
this document was last reviewed and updated on 20th December 2018.
Information Governance advised this has been identified as needing to be
reviewed and updated.  (action e)  
3.10 Information Governance have recently introduced a DPIA tracker to allow all
DPIA’s to be recorded and monitored. This documents what stage they are at so
the team can be more proactive at chasing up outstanding actions and ensuring
annual reviews are carried out.  A review of the DPIA tracker identified a
significant backlog of completed DPIA’s awaiting sign off by the Data Protection
Officer. There were 56 completed DPIA’s waiting on being signed off at the time
of the audit.  There have been resourcing issues in the team which have since
been resolved.  (action f)  
3.11 A DPIA has not been completed for the CM2000 system.  This should be
completed retrospectively and passed to the Data Protection Officer to sign it off. 
(action g)  
3.12 A DPIA had not been completed for the CareFirst system.  Given that the
implementation of the replacement system (Eclipse) is not imminent, Information
Governance confirmed a DPIA for the CareFirst system should still be completed.  
A DPIA was completed during the course of the audit.  An older template has
been used and it has not yet been passed to the Data Protection Officer to sign it
off.  (action h)  
162

Page 163

3.13 A DPIA has not been completed for the Civica system used by Housing Services
(this system was previously called Abritas). This should be completed
retrospectively and passed to the Data Protection officer to sign off.   (action i)  
3.14 A DPIA was completed for the Flexiroute system; however, this was completed in
an old format and was not signed off by the Data Protection Officer.  Information
Governance advised the DPIA should be reviewed, transferred to the new
template and passed to the Data Protection Officer to sign it off.  (action j)   
BC Contingency Plan  
3.15 The Council has a Business Continuity Management (BCM) Strategy in place,
however, this strategy was last updated in October 2015.  The Team Manager
(Risk) is aware of this and the document is currently being updated.  (action k)  
3.16 The Business Continuity Plan Template includes the threat scenario for the loss
of ICT. The template does not advise requesting a copy of the cloud provider’s
BC plan where the lead officer/plan owner has identified a cloud hosted system is
being used.
(action l)  
3.17 Internal Audit reviewed the Care at Home Business Continuity Plan to ensure the
CM2000 system is properly documented within this plan.  The plan was last
updated on 18/12/23 but this version should be saved in the Business Continuity
Management Hub. The Senior Manager (Locality Services) advised the provider
has been contacted more than once to request a copy of their business Continuity
plan as this is a cloud based system.  Once received, the Senior Manager
(Locality Services) has been advised to reference this document in the Care at
Home Business Continuity Plan.    
3.18 Internal Audit reviewed the Corporate Transport Hub Business Continuity Plan to
ensure the Flexiroute system is properly documented within this plan.  The plan
has not been updated since 15/11/21 and one of the response team members left
in August 2023. The Flexiroute system is not listed as one of the ICT
systems/applications under the Loss of IT section which means the details of
arrangements the service has in place if this system is not available has not been
recorded and the back-up storage information for this system has not been
recorded.  This is a cloud hosted system, but a copy of the cloud providers BC
plan has not been obtained and referenced in this BC plan.  (action m) 
4 Internal Audit Opinion  
4.1 Limited assurance was obtained with regards to the DPIA section of the audit due
to all 4 IT systems selected in the audit sample either having no DPIA in place or
no completed DPIA signed off by the DPO.  In addition, there is a significant
backlog of DPIA’s awaiting sign off by the Data Protection Officer to ensure the
DPIA’s have been reviewed and any necessary DPO advice provided.  
4.2 Reasonable assurance was obtained with regards to the other 5 sections of the
audit.  The recommendations made will assist the Council to strengthen the
response to a cyber security event, particularly in relation to a priority recovery list
for IT systems not covered by the SRM or Unix recovery process, outstanding DR
163

Page 164

plans being completed so they can be followed when needed, and rigorous
testing of the BC/DR process and the restore and recovery process.   
Definitions of Assurance Levels: 
Substantial
A sound system of governance, risk management and control exist, with
internal controls operating effectively and being consistently applied to
support the achievement of objectives in the area audited.
Reasonable
There is a generally sound system of governance, risk management and
control in place. Some issues, non-compliance or scope for
improvement were identified which may put at risk the achievement of
objectives in the area audited.
Limited
Significant gaps, weaknesses or non-compliance were identified.
Improvement is required to the system of governance, risk management
and control to effectively manage risks to the achievement of objectives
in the area audited.
None
Immediate action is required to address fundamental gaps, weaknesses
or non-compliance identified. The system of governance, risk
management and control is inadequate to effectively manage risks to the
achievement of objectives in the area audited. 
NB The level of assurance given is at the discretion of Internal Audit. 
164

Page 165

KEY FINDINGS AND ACTION PLAN
CYBER RESILIENCE BUSINESS CONTINUITY 
Action a
Finding The Council’s key IT systems have data recovery capability. 
There are a number of locally stored IT systems not covered
by the SRM or Unix disaster recovery process and there is no
priority list to decide which order these IT systems are
recovered in the event of a major cyber security event.
Action Description IT Services in consultation with the Risk Manager should
compile an IT Corporate Systems list and facilitate a
discussion with ELT to enable a Corporate priority list for the
recovery of locally stored IT systems not covered by the SRM
or Unix disaster recovery process.
Risk No clear prioritised order for recovery could result in a delay
in the recovery of such systems.    
Priority (1, 2, 3) 2
Paragraph Reference  3.1
Managed by Fiona Walker, Head of Service (People & ICT)
Assigned to James McNeil, Senior Manager (ICT)
Due Date 31st October 2024
Management Comment All council systems are backed up by our Backup and
Recover solution, CommVault. However, Site Recovery
Manager can be used to quickly recover systems in the event
of a disaster scenario to our DR site. This is limited to 40
systems. IT will consult with the Risk Manager to compile a
list of systems that could be sorted into a prioritised list for
recovery. Once agreed, IT would then put the highest priority
systems on SRM and have a priority list for servers out with
SRM, “local”, to be restored in order that is beneficial to the
business. UNIX based applications are automatically covered
by the UNIX DR process. 
Action b
Finding There are 51 DR plans with the status ‘complete’ or ‘awaiting
review’, 38 plans have the status ‘under development’ or ‘not
started’ and 2 plans have no status recorded.  The Team
Manager (Operations) advised the historical data will be
deleted, this spreadsheet will be moved to a SharePoint list
and have a flow that will automatically email plan owners at
12 months to review or remove if the solution has been
decommissioned.  In addition, monthly DR meetings are now
scheduled to progress the completion of outstanding DR
plans.
Action Description IT Services should continue to progress the completion of
outstanding DR plans, ensure all DR plans have been
reviewed at least annually and delete historical DR data no
longer required.
Risk Having no DR plan or an out of date or inaccurate data in the
DR plan could result in a delay in the recovery process.
Priority (1, 2, 3) 2
Paragraph Reference  3.6
165

Page 166

Managed by Fiona Walker, Head of Service (People & ICT)
Assigned to James McNeil, Senior Manager (ICT)
Due Date Complete 
Management Comment SharePoint Document Library has now been created for
current and future DR plans. Document Library is set to
trigger an email to the plan owner when the last review date
hits 12 months to ensure the plans are reviewed again.
Legacy plans have been removed. IT continually work to
review and develop DR plans for systems. 
Action c
Finding The DR plans reviewed by the auditor do not document the
recovery time objective (RTO) for the operational service. 
The Team Manager (Operations) advised this is difficult to
calculate given the different scenarios that could impact it but
agreed an average RTO should be added to the DR plans.   
Action Description Realistic RTOs should be agreed and recorded in the DR
plans.
Risk If RTO’s are not known, services are not sure how long it will
take to recover the system or service and cannot plan
accordingly.
Priority (1, 2, 3) 2
Paragraph Reference  3.7
Managed by Fiona Walker, Head of Service (People & ICT)
Assigned to James McNeil, Senior Manager (ICT)
Due Date Complete
Management Comment Recovery Time objectives have now been added to current
DR plans and will be incorporated in all future plans that are
created. 
RTO (Single Server failure): Two Working Days
RTO (Full Failure | SRM/UNIX Replication): Five Working
Days
RTO (Full Failure | Backup Only): 8 to 12 Weeks 
Action d
Finding IT Services have identified the need to test the backup and
disaster recovery processes on a quarterly basis.  Testing is
planned to start in quarter 1 of 2024/25 for Windows Server
test restore, Site Recovery Manager test recovery, Database
test restore, Unix server test restore and network device test
restore.  Testing for M365 test restore began in Q3 2023/24. 
In addition, the planned Business Continuity and Disaster
Recovery Test Plan exercises have been rescheduled to start
again in 2024/25.  They have been delayed due to a vacant
Team Manager (ICT and Cyber Security) post that has now
been filled.  
Action Description IT Services should start completing the planned backup and
disaster recovery testing and ensure this testing is completed
at least quarterly.  The planned Business Continuity and
Disaster Recovery exercises should be recommenced as
soon as possible.
166

Page 167

Risk Issues identified at testing are not identified prior to a live
scenario; the necessary data is not available for recovery; the
backup cannot be relied upon to restore as expected. 
Priority (1, 2, 3) 2
Paragraph Reference  3.8
Managed by Fiona Walker, Head of Service (People & ICT)
Assigned to Gavin Alston, Team Manager (ICT & Cyber Security)
Due Date 30th June 2024
Management Comment IT have a Backup & Recovery testing schedule and tests
have been scheduled on a quarterly basis from April 2024.   
Action e
Finding There is a Data Protection Impact Assessment SharePoint
page on Connects which provides information on this process
and provides a link to the Data Protection Impact Assessment
Information and Guidance document; however, this document
was last reviewed and updated on 20th December 2018.
Information Governance advised this has been identified as
needing to be reviewed and updated.  
Action Description The Data Protection Impact Assessment Information and
Guidance document should be reviewed, updated and
reissued to ensure staff are aware of the need to complete
DPIA’s.
Risk It is not in line with industry best practice; out of date or
inaccurate information.
Priority (1, 2, 3) 2
Paragraph Reference  3.9
Managed by Aileen Craig, Head of Service (Democratic)
Assigned to Lauren Lewis, Data Protection Officer
Due Date Completed
Management Comment This action was in hand at the time of the audit. The action
has been completed and the 2024 version has been uploaded
to Connects. 
Mandatory Information Management training which is to be
undertaken by all staff on an annual basis highlighting
requirements, including criteria on when DPIAs are required is
in place. 
Action f
Finding A review of the DPIA tracker identified a significant backlog of
completed DPIA’s awaiting sign off by the Data Protection
Officer.  There were 56 completed DPIA’s waiting on being
signed off at the time of the audit.  
Action Description The Information Governance team should prioritise clearing
the backlog to ensure completed DPIA’s are signed off as
soon as possible.
Risk Potential non-compliance with Data Protection Legislation;
Council reputational damage; Council could be subject to
enforcement action by the Information Commissioner’s Office;
167

Page 168

Delays to improvement projects while awaiting sign off of the
DPIA.
Priority (1, 2, 3) 1
Paragraph Reference  3.10
Managed by Aileen Craig, Head of Service (Democratic)
Assigned to Lauren Lewis, Data Protection Officer
Due Date Completed
Management Comment The number of DPIAs received by the Information
Governance Team varies as business is put to the Team for
consideration and review. A number of these involve
consideration of complex and emerging issues which require
detailed investigation. The Information Governance team has
now been augmented to ensure that there are more staff
members in post to deal with DPIAs. The tracker has been
reviewed and updated to reflect the various stages of DPIAs
with the current levels of outstanding DPIAs for Information
Governance Team review being 18 (17 for DPO sign off and 1
for review). At the time of completion, 39 DPIAs have been
returned to Services for further feedback and updating with
relevant information. An online form is now live to log DPIA
requests via EMPro. This further facilitates both reporting
functionality and annual review processes for the Information
Governance Team; coupled with additional resource this will
enhance service performance and compliance in this area. 
Action g
Finding There is no DPIA for the CM2000 system.  
Action Description A DPIA should be completed retrospectively for the CM2000
system and this should be passed to the Data Protection
Officer to sign off.
Risk Non-compliance with Data Protection Legislation; Personal
data is at risk of misuse; Council reputation damage; Council
could be subject to enforcement action by the Information
Commissioner’s Office.
Priority (1, 2, 3) 1
Paragraph Reference  3.11
Managed by Kerry Logan, Head of Service (Health & Community Care)
Assigned to Lorraine Dyet (Senior Manager)
Due Date 30 April 2024
Management Comment The CM2000 Monitoring Officer within the HSCP is currently
progressing the completion of a DPIA, and is engaging with
the Data Protection Officer with the aim of completing this by
the end of April 2024. 
Action h
Finding A DPIA had not been completed for the CareFirst system.  A
DPIA was completed during the course of the audit.  An older
template has been used and it has not yet been passed to the
Data Protection Officer to sign it off.  
Action Description The DPIA should be transferred to the new template and
passed to the Data Protection Officer to sign off.
168

Page 169

Risk Non-compliance with Data Protection Legislation; Personal
data is at risk of misuse; Council reputation damage; Council
could be subject to enforcement action by the Information
Commissioner’s Office.
Priority (1, 2, 3) 1
Paragraph Reference  3.12
Managed by Paul Doak, Head of Service (HSCP Finance &
Transformation)
Assigned to Neil McLaughlin, Team Manager (Information Systems)
Due Date Complete
Management Comment The CareFirst system was introduced in North Ayrshire in
2001. The DPIA which was prepared during the course of the
audit has now been updated onto the new template and
signed off by the Data Protection Officer. 
Action i
Finding There is no DPIA for the Civica system used by Housing
Services. 
Action Description A DPIA should be completed retrospectively for the Civica
system used by Housing Services and this should be passed
to the Data Protection Officer to sign off.
Risk Non-compliance with Data Protection Legislation; Personal
data is at risk of misuse; Council reputation damage; Council
could be subject to enforcement action by the Information
Commissioner’s Office.
Priority (1, 2, 3) 1
Paragraph Reference  3.13
Managed by Yvonne Baulk, Head of Service (Housing & Public Protection)
Assigned to Fiona Ellis, Senior Manager (Housing Strategy &
Development)
Due Date 31/05/24
Management Comment The Digital team are actively working to pull together the DPIA
for the Civica system to coincide with a major system upgrade
and Trust Housing coming on board with the North Ayrshire
Housing Register (NAHR). 
The team are liaising with the Information Governance team
in preparing the draft DPIA which requires to be approved by
them in the first instance.  Input from the Registered and
Social Landlords that utilise the NAHR is also required and is
ongoing at present. 
Action j
Finding A DPIA was completed for the Flexiroute system; however,
this was completed in an old format and was not signed off by
the Data Protection Officer.  
Action Description The DPIA for the Flexiroute system should be reviewed,
transferred to the new template and passed to the Data
Protection Officer to sign it off.
Risk Non-compliance with Data Protection Legislation; Personal
data is at risk of misuse; Council reputation damage; Council
169

Page 170

could be subject to enforcement action by the Information
Commissioner’s Office.
Priority (1, 2, 3) 1
Paragraph Reference  3.14
Managed by Gordon Mitchell, Senior Manager (Transport)
Assigned to Susan Adamson, Team Manager (Journeys & Hires
/Transport)
Due Date 31/05/2024
Management Comment The original DPIA was transferred onto the appropriate new
format and passed to the Data Protection Officer to review
and signoff. However, this has since been returned with
comments and further recommendations. Due to the nature
and sensitivity of the Personal Information held, shared, and
processed, it was a recommendation of the DPO that the
completion of the DPIA should be supported with a
collaborative approach of Senior Managers from both the
Health & Social Care Partnership and Education and Youth
Employment as the key information providers. A meeting has
been arranged with representation from both services and the
Information Governance team with a view of a satisfactory
sign off by the end of May 2024. 
Action k
Finding The Council has a Business Continuity Management (BCM)
Strategy in place, however, this strategy was last updated in
October 2015.  The Team Manager (Risk) is aware of this,
and the document is currently being updated.  
Action Description Once the updated Business Continuity Management Strategy
has been agreed it should be reissued to ensure relevant staff
are aware the strategy has been reviewed and updated.
Risk It is not in line with industry best practice; out of date or
inaccurate information.
Priority (1, 2, 3) 2
Paragraph Reference  3.15
Managed by Mark Boyd, Head of Service (Finance)
Assigned to Alex Fitzharris, Team Manager (Risk & Insurance)
Due Date 29 November 2024
Management Comment The BCM strategy has been revised and reviewed and is
currently subject to further review and amendments ahead of
formal approval process. 
Action l
Finding The Business Continuity Plan Template includes the threat
scenario for the loss of ICT. The template does not advise
requesting a copy of the cloud provider’s BC plan where the
lead officer/plan owner has identified a cloud hosted system is
being used.
Action Description The Business Continuity Plan Template should be amended
to advise that where a cloud hosted system has been
identified, a copy of the cloud provider’s BC plan should be
obtained and referenced in the BC plan.  
170

Page 171

Risk Cloud providers resiliency is not known; delay in recovering
from an incident.
Priority (1, 2, 3) 2
Paragraph Reference  3.16
Managed by Mark Boyd, Head of Service (Finance)
Assigned to Alex Fitzharris, Team Manager (Risk & Insurance)
Due Date 29 November 2024
Management Comment A working group will be set up with officers from across the
Council to revise the BC Plan Template approach considering
the release of the Business Continuity Institutes Good
Practice Guidelines 7.0 (2023).  The BC plan template
changes will be incorporated into the wider BCM Strategy
review work. 
Action m
Finding The Corporate Transport Hub Business Continuity has not
been updated since 15/11/21 and one of the response team
members left in August 2023.  The Flexiroute system is not
listed as one of the ICT systems/applications under the Loss
of IT section which means the details of arrangements the
service has in place if this system is not available has not
been recorded and the back-up storage information for this
system has not been recorded.  This is a cloud hosted
system, but a copy of the cloud providers BC plan has not
been obtained and referenced in the BC plan. 
Action Description The BC plan should be reviewed and updated to ensure the
response team members are current staff members.  The
Flexiroute system should be listed at the Loss of IT section to
ensure the details of arrangements the service has in place if
this system is not available is recorded.  The cloud provider
should be contacted to obtain a copy of their BC plan and this
should be referenced in this BC plan.
Risk Non-compliance with the BC strategy; new critical processes
have not been identified and documented; inaccurate or out of
date information could delay the response during an incident.
Priority (1, 2, 3) 2
Paragraph Reference  3.18
Managed by Gordon Mitchell, Senior Manager (Transport)
Assigned to Susan Adamson, Team Manager (Journeys & Hires
/Transport)
Due Date Completed
Management Comment The Business Continuity Plan has been reviewed and
updated which has been communicated and is reflective of
our current staffing structure. The Flexiroute system is now
listed under the Loss of IT section of the Business Continuity
Plan to ensure the details of arrangements are in place if the
team were to experience a Flexiroute system failure. The
system and cloud supplier (RLDatix) has provided a copy of
their BC plan and this is referenced in the teams Business
Continuity Plan. 
171

Page 172

Priority Key used in Action Plan 
1 (High) Control weakness where there is a material impact on the achievement of
the control objectives, generally requiring prompt attention.
2 (Medium) Control weakness which needs to be rectified, but where there is no
material impact on the achievement of the control objectives.
3 (Low) Minor weakness or points for improvement. 
172

Page 173

AGD – REVENUE PROJECTS 
1 Background  
1.1 The Ayrshire Growth Deal consists of a programme of 19 high-profile major
development projects across Ayrshire involving public, private and 3rd sector
partners and attracting funding from both Scottish and UK governments.  East
Ayrshire Council acts as the lead partner for the deal overall and hosts the Project
Management Office (PMO).  North Ayrshire Council is the lead partner for 9/19 of
the projects (6 capital, 3 revenue).  
1.2 The 3 Revenue Projects are Ayrshire-Wide but NAC is the lead partner for all of
them.  They are Community Wealth Building (CWB), Working for a Healthy
Economy (WfHE) and Ayrshire Skills Investment Fund (ASIF).  
1.3 The 3 projects are at very different stages.  ASIF has only relatively recently
received Final Business Case approval. Proposals include an employer grants
programme.   WfHE is largely undertaken by a contractor, NHS Salus, so the role
of NAC is mostly of contract management.  CWB was due to complete in March
2024, but an extension to March 2025 has recently been approved by the
Ayrshire Economic Joint Committee.     
2 Objectives and Scope  
2.1 The audit was structured as 3 mini-audits covering each of the revenue projects,
reflecting the different stages each audit had reached and the different natures of
the projects.  
2.2 The main objectives of the audit were to:
• Ensure that controls within the management of the Community Wealth
Building project are suitable and operating effectively.
• Ensure that controls to manage the contract for the delivery of Working for
a Healthy Economy are suitable and operating effectively.
• Provide audit advice regarding the proposals for the Ayrshire Skills
Investment Fund, including an employer grants scheme.  
2.3 Activities undertaken by East and South Ayrshire Councils as part of these
projects were not audited directly, although the audit reviewed assurances
obtained by NAC in relation to activities at East and South.   
3 Findings   
Community Wealth Building  
3.1 Overarching governance is provided by an AGD CWB Programme Steering
Group comprising representatives of the 3 Ayrshire local authorities. 
Performance and financial monitoring reports are regularly updated and
submitted to the PMO.  East and South Ayrshire Councils invoice North Ayrshire
quarterly to cover their share of the staff costs and business grants that they have
173

Page 174

distributed.  A risk register is kept in the Ideagen (formerly Pentana) system and
was updated during the audit period.    
3.2 A sample of 10 grants to businesses was checked and overall the applications
were all in order.  They were paid by payment request and the required proof of
bank details was not provided in 1 case or was inadequate in 4 further cases. 
The Business Support team, who process these claims, and the eProcurement
team were advised to ensure that suitable proof of bank details is included in the
payment requests. No other issues were identified.  
3.3 The 5 “top deliverable” performance indicators were checked to ensure that
suitable backup was available.  All were found to be suitable.  One of these
indicators is called “CWB Officers and Action Plans in Place” and is calculated by
adding together the number of officers in place and the number of action plans.  It
seems somewhat incongruous that these 2 figures are added together to form a
performance indicator.  North Ayrshire have contacted the PMO to query this
methodology.   
Working for a Health Economy  
3.4 This project is provided by a contractor appointed in a procurement exercise. 
There is a service level agreement and the agreed costs are invoiced monthly by
the contractor.    
3.5 There is a steering group where the partner organisations and the contractor
meet to discuss the progress on the project and any issues encountered. 
However, the steering group has not met regularly or, in some cases, meetings
have taken place but minutes have not been produced. (Action a)  
3.6 Performance data on people accessing support from this project are provided by
the contractor and reported to the PMO.  There is a risk register which has been
updated as the project progressed.   
Ayrshire Skills Investment Fund  
3.7 The ASIF project was at an early stage at the time of the audit.  The first round of
grants to businesses was awarded in November 2023 and a second round was
awarded near the end of the audit in February 2024.    
3.8 The Grant Offer Letter remitted to grant recipients outlines requirements for grant
recipients, including record keeping and accounting requirements.  The
businesses are required to sign and return a copy of the Grant Offer Letter. 
3.9 Since the UK left the EU the State Aid requirements have been replaced with
Minimum Financial Assistance requirements.  Processes have been introduced to
ensure that the grant recipients comply with these requirements.  
3.10 A small sample of grants awarded in November 2023 was checked and all was
found to be in order.  
3.11 The service requested some advice regarding evidence requirements for the
business grants.  They had been asking for invoices for external training and for
174

Page 175

training plans and hourly rates for in-house training.  Furthermore, they make
contact with all training recipients for monitoring and evaluation purposes, during
and after the training.  It was suggested that if the trainees do not engage
adequately to demonstrate that the training has taken place, then further
evidence should be requested from the businesses. 
4 Internal Audit Opinion  
4.1 Overall, substantial assurance was obtained with regard to the AGD Revenue
Projects.  The WfHE Steering Group meetings need to take place regularly and
minutes be produced promptly after each meeting.     
Definitions of Assurance Levels: 
Substantial
A sound system of governance, risk management and control exist, with
internal controls operating effectively and being consistently applied to
support the achievement of objectives in the area audited.
Reasonable
There is a generally sound system of governance, risk management and
control in place. Some issues, non-compliance or scope for
improvement were identified which may put at risk the achievement of
objectives in the area audited.
Limited
Significant gaps, weaknesses or non-compliance were identified.
Improvement is required to the system of governance, risk management
and control to effectively manage risks to the achievement of objectives
in the area audited.
None
Immediate action is required to address fundamental gaps, weaknesses
or non-compliance identified. The system of governance, risk
management and control is inadequate to effectively manage risks to the
achievement of objectives in the area audited. 
NB The level of assurance given is at the discretion of Internal Audit. 
175

Page 176

KEY FINDINGS AND ACTION PLAN
AGD – REVENUE PROJECTS 
Action a
Finding The WfHE Steering Group has not met regularly or in some
cases meetings have taken place but minutes have not been
produced.
Action Description The Employability team should ensure that WfHE Steering
Group meets regularly and minutes of the meetings are
produced in a timely manner
Risk Issues with the project are not identified promptly.  Agreed
actions from the meetings are not implemented promptly. 
Different parties taking part in the meeting have a different
understanding of what was agreed.
Priority (1, 2, 3) 2
Paragraph Reference  3.5
Managed by Louise Kirk, Head of Service (Economic Development Growth
and Regeneration)
Assigned to Laura Neill, Senior Manager (Employability and Skills)
Due Date 6 June 2024
Management Comment The issue has partly been addressed through a schedule of
meeting dates which have been agreed with partners every 6
weeks. The next meeting is 30 May 2024. 
The next stage will be to ensure that an agenda is prepared at
least one week in advance and the meeting minutes issued
one week after the meeting date. This will be reviewed on 6
June 2024 to ensure compliance with the identified timescales
and the action can be closed thereafter. 
Priority Key used in Action Plan 
1 (High) Control weakness where there is a material impact on the achievement of
the control objectives, generally requiring prompt attention.
2 (Medium) Control weakness which needs to be rectified, but where there is no
material impact on the achievement of the control objectives.
3 (Low) Minor weakness or points for improvement. 
176