NORTH AYRSHIRE COUNCIL 
21st March 2024   
Audit and Scrutiny Committee 
Title:    Council Plan Mid-Year Progress Report 2023-24 
Purpose:  To consider the Council Plan Mid-Year Progress Report
2023-24. 
Recommendation:  The Audit and Scrutiny Committee agrees to note the
Council Plan Mid-Year Progress Report 2023-24 attached
at Appendix 1. 
1 Executive Summary 
1.1 Our Council Plan 2023-28 is the overarching strategy of our Council and details
our Council’s strategic priorities.  We have a statutory duty to publish information
that enables effective scrutiny of our performance.
1.2 This report presents the progress made in delivering our new Council Plan 2023-
28 as at Mid-Year 2023/24 (30th September 2023).  The approach and layout
have been refreshed to reflect our new Council Plan as well as the results of our
Best Value Thematic Audit. Following Cabinet approval, our corporate
performance reports are published on our website www.north-
ayrshire.gov.uk/performance.
2 Background 
2.1 Under the Local Government (Scotland) Act 1992 and Local Government in
Scotland Act 2003 we have a duty to demonstrate Best Value.  To ensure we
support our residents, fulfil our statutory duties and invite scrutiny, we actively
manage performance and develop our reporting to make it accessible and
engaging.  
2.2 Our new Council Plan 2023-28 was approved by Council in June 2023 with the
Performance Management Framework (PMF) approved in August 2023.  Targets
were set for 2023/24, however due to the timing of the PMF development, mid-
year targets were not set for all indicators (it would not have been best practice
to set targets so close to the mid-year point).  This has been mitigated by
including a review of progress within the report, comparing performance to year
end targets.

Page 2

2.3 In parallel to the approval of Our Council Plan, we undertook our Best Value
Thematic Audit focusing on “Leadership of the development of new local
strategic priorities”.  The outcomes of this Audit were extremely positive stating
we have a culture of continuous improvement.  
2.4 In addition, some areas could be improved further such as how we report on
audits, inspections and self-assessment activity.  This has been reflected in our
new report at Appendix 1, with the ‘Best In Class’ section of previous reports
refocused towards existing and completed audits, inspections and accreditations
– linking to the published reports where available.  This approach was discussed
with our External Auditors during the Best Value Thematic Audit, primarily as it
meant that context (such as reasons for and next steps) rather than purely a list
of audits would be available for our residents to scrutinise.
2.5 The use of the Inclusive Growth Dashboard was included in our report to Council
in June and is highlighted in the Best Value Thematic report.  This tool provides
a contextual overview of North Ayrshire, is currently being reviewed and will be
available in 2024/25 for use within our reporting.  However contextual indicators
as outlined in our PMF are included in the report.
3 Assessment of Performance 
3.1 The development of Our Council Plan leaned towards evolution rather than
revolution.  As a result, many areas are continuing to progress well from the
previous Council Plan and are detailed within the body of the report.  
3.2 There are 47 actions within Our Council Plan, with one reported directly through
the HSCP and therefore excluded from this report.  The remaining 46 actions are
all on target at mid-year.
3.3 There are 26 performance indicators within our framework.  At mid-year, the
status of 16 PIs were either unknown or data only, seven were on target and
three were slightly adrift of target (amber).  The status of the three indicators
slightly adrift of target (amber) were included in our previous Council Plan and
scrutinised at year end.
3.4 Though not all mid-year targets were available this period, our annual targets
give confidence that performance is on schedule, with some areas such as the
number of unemployed people progressing into employment already exceeding
their annual target at mid-year (652 against a target of 450).  Our Street
Cleanliness score shows we have performed better than expected at 90.1%
against a target of 87%.  Participatory Budgeting is currently showing 2.06% of
our Council budget to date, ahead of the 1.5% target for Quarter two and year
end.
3.5 Other areas include the number of empty properties brought back into use and
number of new build properties (all tenures) which are progressing at over 50%
of target at mid-year, though these may be subject to seasonal fluctuations later
in the year.

Page 3

3.6 Key Highlights
• Our Council Plan 2023-28 was developed with our communities and approved
in June.
• We established our Financial Inclusion Partnership to increase access to
financial advice and support for our residents.
• Our £198,377 participatory budgeting grants programme was launched for
2023/24.
• 6,529 adults took part in adult learning and capacity building activities.
• Our Regeneration Development Plan’s action programme 2023-25 was
approved by Cabinet and includes £4million of funding.
• Several significant Ayrshire Growth Deal milestones were reached, including
contractor appointments at the Ardrossan Coastal Quarter site of Ardrossan
Campus, breaking ground on i3 in Irvine and further progress on the delivery
of Irvine Harbourside.
• We launched a £350k Community Net Zero Carbon Fund, enabling local
community groups to bid for funding to help with feasibility and/or installation
of renewable energy technologies on land or buildings they own.
• Over 100 tonnes of furniture and mattresses were collected to encourage the
reuse of items through our bulky waste partner.
3.7 Key Next Steps
• We will meet with the Improvement Service to push forward our data sharing
work following the outcome of our Scottish Government Child Poverty Practice
Accelerator Fund and Cash First Fund application.
• We will continue drafting our new Community Wealth Building strategy
following consideration by the Policy Advisory Panel and Cabinet.
• We will present a paper on treating Care Experienced as a protected
characteristic to Council in December.
• We will continue the development of the Participation Strategy and new
Community Planning Partnership website and Community Directory. 
• We will continue to plan for our 2024 Community Planning Conference, which
will focus on Democracy Matters Phase 2. 
• We will publish our new ‘Sustainable North Ayrshire’ and Energy Efficiency
Strategies.
• We will progress to construction stage for our new solar farm projects. 
• We will launch new energy efficiency measures offer as part of our Energy
Smart programme. 
• We will progress the procurement exercise for the new Ayrshire Electric
Vehicle Charging Infrastructure project. 
• We will progress with our fleet decarbonisation route map, including
exploration of a hydrogen production feasibility study. 
• We will continue the construction of the North Crescent Coastal Path Phase 1,
Ardrossan.

Page 4

• We will review and implement any actions following our Best Value report due
to be published in November. 
• We will support our External Auditors in the audit of the next Best Value
Thematic Approach early in 2024, focussing on workforce innovation. 
• We will continue to engage with the Island Plan Delivery and Steering Groups
to shape the annual action plans for the Island Plans. 
4 Proposals 
4.1 The Audit and Scrutiny Committee agrees to note the Council Plan Mid-Year
Progress Report 2023-24 attached at Appendix 1.
5 Implications/Socio-economic Duty
Financial
5.1  There are no financial implications arising from this report.
Human Resources
5.2 There are no human resource implications arising from this report.
Legal
5.3 There are no legal implications arising from this report.
Equality/Socio-economic
5.4 There are no equality/socio-economic implications arising from this report.
Climate Change and Carbon
5.5 There are no climate change and carbon implications arising from this report.
Key Priorities
5.6 The Mid-Year Progress Report enables the effective scrutiny of the delivery of
our Council Plan strategic priorities.
Community Wealth Building
5.7 There are no Community Wealth Building implications arising from this report.
Consultation
5.8 The Executive Leadership Team (ELT) and North Ayrshire Council Cabinet
reviewed and scrutinised the report prior to submission to the Audit and Scrutiny
Committee. 
Aileen Craig
Head of Service (Democratic) 
For further information please contact Isla Hardy, Team Manager (Corporate
Policy and Performance), on 01294 324035 or email IslaHardy@north-
ayrshire.gov.uk.

Page 5

Our Council Plan
Mid-Year Progress
Report 2023-24
Appendix 1

Page 6

Contents
Our Performance at a Glance .................................................................................................................. 1
Wellbeing ................................................................................................................................................ 4
Key Ac�vi�es ....................................................................................................................................... 4
Next Steps ........................................................................................................................................... 9
Case Study ......................................................................................................................................... 10
Communi�es and Local Democracy ...................................................................................................... 11
Key Ac�vi�es ..................................................................................................................................... 11
Next Steps ......................................................................................................................................... 13
Case Study ......................................................................................................................................... 14
Climate Change ..................................................................................................................................... 15
Key Ac�vi�es ..................................................................................................................................... 15
Next Steps ......................................................................................................................................... 18
Case Study ......................................................................................................................................... 19
A Sustainable Council ............................................................................................................................ 20
Key Ac�vi�es ..................................................................................................................................... 20
Next Steps ......................................................................................................................................... 21
Case Study ......................................................................................................................................... 22
Audits, Inspec�ons and Accredita�ons ................................................................................................. 24
Performance Summary ......................................................................................................................... 25
Measures adri� of target .................................................................................................................. 25
Performance Indicators ..................................................................................................................... 26
Ac�on Tracker ................................................................................................................................... 29

Page 7

Our Council Plan Progress Update – Mid Year 2023-24  Page 1 of 33
Our Performance at a Glance
We established our
Financial Inclusion
Partnership to increase
access to financial advice
and support for residents.
Council approved Our
Council Plan 2023-28,
developed with our
communities.  Focus now
moves to delivery of this
contract with our residents.
1,300 residents
participated in ‘Take
Time on the Road’
roadshows focussing on
mental health and
wellbeing.
Our £198,377
participatory
budgeting grants
programme launched for
2023/24.
11,000 young people
accessed holiday
meals provisions during
the summer holidays.
6,529 adults took part
in adult learning and
capacity building
activities between April
and September.
Community Transport
Pathfinder approved
to explore transport needs
in our communities.
Our Regeneration
Development Plan’s
action programme 
2023-25 was approved by
Cabinet and includes £4m
of funding
28 Community Wishes
have been delivered, linking
the needs of communities to
our contracted businesses. 
61 have been granted since
launch in October 2021.
We launched a £350k
Community Net Zero
Carbon Fund, enabling local
community groups to bid
for funding to help with
feasibility and/or
installation of renewable
energy technologies on land
or buildings they own.
Over 100 tonnes of
furniture and
mattresses collected to
encourage the reuse of
items through our bulky
waste partner.
Several significant
Ayrshire Growth Deal
milestones reached
including contractor
appointments, breaking
ground on i3 and a move
towards the delivery of
Irvine Harbourside.

Page 8

Our Council Plan Progress Update – Mid Year 2023-24  Page 2 of 33
Welcome
Welcome to our first Mid-Year Progress Report on Our Council Plan 2023-28.  Our Council Plan was
approved by Council in June 2023.  Our vision remains ‘A North Ayrshire that is fair for all’, and our
mission is ‘Working together to improve the lives of our people in North Ayrshire’.  We worked with
our communi�es to create our plan and iden�fy our four priori�es.  We view Our Council Plan as our
contract with our communi�es, ‘our’ plan.   It is more than a document, it is an ac�ve commitment
to support our residents and deliver on our joint priori�es.
Our four priori�es are Wellbeing, Communi�es and Local Democracy, Climate Change and A
Sustainable Council.  All of these four areas are interlinked and interdependent - they do not sit in
isola�on as the progress of each priority directly impacts the other three areas.  
Challenges for our residents and communi�es persist due to the cost of living crisis and suppor�ng
our residents is a significant role within our new Council Plan.  For example, through our Child
Poverty and Cost of Living Board, we are exploring different ways in which we can use informa�on to
iden�fy and address need in our communi�es.  Our colleagues in the Third and Voluntary sector
con�nue to work alongside us.
As part of our ambi�on to achieve net-zero by 2030 we con�nue to work with our communi�es
across a variety of projects.  This includes providing educa�onal opportuni�es such as the STEM trail
at Eglinton Park and suppor�ng the various volunteer groups who give their �me to help protect the
environment.  
Our communi�es drive the work that we do and as such, lived experience is a crucial element to our
decision-making process.  This can be seen through our work in implemen�ng the Ten-Year Island
Plans for Arran and Cumbrae.  This will prove crucial in forming the annual ac�on plans for the
islands.
Everything we do is achieved in the context of our environment.  Moving forward we will
demonstrate this through our ‘Inclusive Growth Dashboard’ which gives an overview of the status of
North Ayrshire.  This tool is currently being refreshed and will be available in 2024/25.  As an
overview, our key contextual indicators are shown below:
Population of North
Ayrshire:
134,220 (June 2021)
29% of our children live in
poverty after housing costs
(2021/22)
28% of our households live
in fuel poverty (2021/22)
72.1% of working age
population are in
employment (as at June
2023)
11.7% of people earn less
than the living wage
(2021/22)
Area wide CO2 emissions are
5.43kt CO2e 
Together we will create a North Ayrshire that is fair for all.

Page 9

Our Council Plan Progress Update – Mid Year 2023-24  Page 3 of 33
Our Priori�es 
Our Vision – A North Ayrshire that is fair for all. 
Our Mission – Working together to improve the
lives of our people in North Ayrshire.

Page 10

Our Council Plan Progress Update – Mid Year 2023-24  Page 4 of 33
Wellbeing
Key Activities
Cost of Living
We are working alongside our residents to
iden�fy the areas that will make the greatest
impact when suppor�ng them financially.  The
Financial Inclusion Partnership, established in
May, will improve promo�on of and access to
advice services for our residents.  We are
implemen�ng a new case management
system.  This will enable us to see the journey
of each of our residents to provide joined up
support to meet their needs.   
To ensure residents are supported with help
around energy costs and health and wellbeing
services, we have referral pathways
established between North Ayrshire Welfare
Rights and Debt Advice Services and a number
of other services/agencies including CHAP,
Housing and Employability Services, and Citrus
Energy (Lemon Aid).   
Our Child Poverty and Cost of Living Board has
applied for funding from the Sco�sh
Government Child Poverty Prac�ce
Accelerator Fund and Cash First Fund.  If
approved this will fund a small team within
our Transforma�on Team to accelerate
progress on our ‘No Wrong Door’ ini�a�ve
including our Single Shared Assessment
ini�a�ve, which would help iden�fy the
support a resident and their family is en�tled
to more quickly. 
Full details of financial support we have
provided can be found in our six monthly Cost
of Living report.   
Lifelong Learning Opportuni�es
6,529 adults took part in adult learning and
capacity building ac�vi�es between April and
September.  This included 241 New Scots
adults who engaged in learning opportuni�es
suppor�ng their language and resetlement
needs over the summer.  Some of the
ac�vi�es included language cafes,
volunteering opportuni�es and speaking
clubs.  
We are delivering the Discovery Award.  This
helps people 50 or over to adopt an ac�ve and
healthy lifestyle by offering challenges to both
s�mulate and mo�vate.  
The “Mul�ply Project” funded by the UK
Shared Prosperity Fund has now officially
launched in North Ayrshire.  This project aims
to boost people’s ability to use maths in their
daily life, at home and work, targe�ng learners
who are 19+ that have not previously atained
a Level 2 SCQF, Level 5 or Higher Maths
qualifica�on.  
In the Garnock Valley, the North Ayrshire
Digital Network, is working in partnership with
the Sco�sh Council for Voluntary
Organisa�ons (SCVO), to deliver a Place-based
Digital Inclusion Project.  Place-based digital
inclusion builds sustainable solu�ons to digital
exclusion which take into considera�on the
assets, and needs, for a specific place.  Ac�on
is co-ordinated through strong and trusted
partnerships and informed by regular
communica�on with those who live there.   
Mental Health & Wellbeing
During the summer over 1,300 residents took
part in the ‘Take Time on the Road’ roadshow,
focusing on mental health and wellbeing. 
Atendees took part in gaming ac�vi�es,
wellbeing workshops, yoga and a ‘Therapet’
Pe�ng Zone.  Mental health and wellbeing is
a key focus in all of our youth voice, children’s
rights and youth work programmes.  All our
programmes are fully inclusive for all young
people and we specifically support Addi�onal
Support Needs (ASN), Mental
Health & Wellbeing, LGBT
and New Scots, focussing
on tackling inequali�es
and reducing barriers
to par�cipa�on.

Page 11

Our Council Plan Progress Update – Mid Year 2023-24  Page 5 of 33
Our ‘Drama for Wellbeing’ programme took
place during the school holidays.  The
programme saw primary school pupils
working on mini plays while learning about
mindfulness and wellbeing.  Senior secondary
school pupils developed their stage presence
and delivery, presen�ng their own thought-
provoking play focused on the pressures of
modern teenage life.  This ended with a live
performance at the Harbour Arts Centre.
The Ac�ve Schools team has offered a wide
variety of extra-curricular opportuni�es on
offer to all primary, secondary and ASN
establishments.  The work of the Ac�ve
Schools and Communi�es Partnership Officers
has focussed on care experienced young
people and New Scots.  The Ac�ve Schools
Team has further enhanced leadership
opportuni�es to widen achievement by
introducing a new pathway in partnership
with KA Leisure and Ayrshire College.  The sole
focus is the Na�onal Progression Award (NPA)
Fitness Course at Level 6.
Over 11,000 young people accessed holiday
meals provisions over the 2023 summer
holiday period.  
The 2023/24 round of our Par�cipatory
Budge�ng grants programme offers four
separate funds for communi�es to make a
spending decision.  These are ‘Arts & Culture’,
‘Locality’, ‘Youth and UK Shared Prosperity
Communi�es’ and ‘Place’.  A total of £198,377
is available to local organisa�ons.  Full details
of the projects behind the applica�ons can be
found here.
We launched our Science, Technology,
Engineering, and Mathema�cs (STEM) Trail at
Eglinton Country Park to help children
discover and understand STEM concepts using
the outdoor environment as a s�mulus.  
Our North Ayrshire Wellbeing Alliance builds
on extensive exis�ng work to develop the
Wellbeing priority from the Community Plan. 
The work aims to tackle health inequali�es by
co-loca�ng services, delivering preventa�ve
ac�vi�es and strengthening the rela�onship
between health and leisure.  In order to
progress and develop our Wellbeing Alliance,
KA Leisure has been hos�ng a series of
workshops and working group mee�ngs. 
Through this work, a project has been
developed in the Garnock Valley to respond to
an iden�fied need around engaging hard to
reach young people.

Page 12

Our Council Plan Progress Update – Mid Year 2023-24  Page 6 of 33
Public Spaces 
Our play facili�es programme of investment
con�nues to progress.  Building on the coastal
park installa�ons last year the focus has now
moved to inland facili�es with 14 facili�es
upgraded since June.  Officers atend the
Sco�sh Government Play Facili�es Working
Group.  Atending this group gives the service
confidence that play facility upgrades within
North Ayrshire are progressing well.  
We are con�nuing to make play accessible for
all children by installing communica�on
boards in parks.  The boards make a big
difference to youngsters with neurodivergent
condi�ons – including au�sm, dyslexia and
aten�on deficit hyperac�vity disorder (ADHD)
- by giving them images, symbols and paterns
to help them express themselves and
communicate.  They have been installed at
seven key parks and further rollout is being
considered.
This investment programme provides great
facili�es for families and visitors and helps
deliver facili�es that are more inclusive and
accessible.  
Our Enforcement Team worked in partnership
with Police Scotland, Network Rail, Coast
Watch, the Mari�me and Coastguard Agency
and Sco�sh Fire and Rescue to implement the
‘Safer Shores’ programme over the summer. 
This partnership allows visitors and residents
to enjoy our coastal loca�ons safely.  
We are working in partnership with
Strathclyde Partnership for Transport (SPT) on
the Strathclyde Regional Bus Strategy.  This
will undertake a study into rural transport
needs and an appraisal of bus opera�on
models.  We are also suppor�ng their regional
funding bid to Transport Scotland’s
Community Bus Fund to further develop the
strategy.  Access to effec�ve transport is key in
enabling our residents to work, access
facili�es and enjoy social opportuni�es.
In May 2023, Cabinet approved the next steps
for a new Community Transport pathfinder. 
This includes plans for detailed engagement
with local communi�es to understand their
transport needs, as well as explora�on of
poten�al delivery models.  We are working
with the Garnock Valley Locality Partnership
to develop a study that will iden�fy what the
travel challenges and barriers are within the
area, providing an evidence base for
interven�on and offering prac�cal and
realis�c recommenda�ons to help address
these challenges in the locality.  A North
Ayrshire survey will be undertaken to establish
the demand for community transport and
how this could be shaped to meet the needs
of the community.  A further update will be
provided to Cabinet in December 2023.
We have iden�fied improvements to bus stop
infrastructure as part of the recent £146,000
capital award under the Community Bus Fund. 
The fund aims to enable local transport
authori�es to improve local public transport,
with a focus on rural deprived areas where
lower popula�on density means bus services
can be less commercially viable.  These will be
delivered alongside the bus corridor
improvements funded under SPT’s Capital
Programme.
Our Streetscene Service has installed 41
wheelchair accessible picnic benches, 115
new benches and 51 large capacity Nexus
bins.  The picnic benches and benches are
galvanised steel and come with a 15-year
guarantee which helps futureproof our street
assets.  The larger capacity bins have been a
key element in allowing Streetscene to review
schedules for street cleaning, and this will
help balance resources between coastal and
residen�al areas to focus on
achieving improved Local
Environmental Audit and
Management System
(LEAMS) outcomes.  
We con�nue to
support the Bri�sh

Page 13

Our Council Plan Progress Update – Mid Year 2023-24  Page 7 of 33
Legion to ensure our war memorials are
presented in the best way possible.  In
par�cular this year, around the Ardrossan War
Memorial and the Dasher Memorial gardens.
Cabinet approved the Regenera�on Delivery
Plan ac�on programme for 2023/24 and
2024/25 alongside the 2023/24 funding
proposals.  This included over £4m funding
under the Place Based Investment
Programme, Cycling Walking and Safer Routes,
Vacant and Derelict Land Fund and SPT’s
Capital Programme.  Addi�onally, a report on
the B714 Upgrade was approved by Cabinet
on 29 August 2023 that approved the
realignment of £5m to support the project.
The Department for Levelling Up Housing and
Communi�es’ (DLUHC), Head of Scotland
Team and Regional Leads visited on 24th
August.  They viewed the projects funded
from the Community Renewal Fund, Shared
Prosperity Fund and Levelling Up Fund.  New
Area Leads are now in place from the
Department of Levelling Up Housing and
Communi�es with an introductory site visit
programme planned for 17th November.  The
third round of Levelling Up Fund (LUF) is s�ll
expected this year, with date to be confirmed.  
Ayrshire Growth Deal
We have reach significant milestones around
the Ayrshire Growth Deal.
A contractor has been appointed to undertake
remedia�on at the Ardrossan Coastal Quarter
site of the future Ardrossan Campus. This is a
key milestone in the wider regenera�on
proposals for the Ardrossan area, and cri�cal
to enabling the development of the Campus.
The i3 Ayrshire Growth Deal Flexible Space
programme has broken ground and
development is underway to provide the first
phase of the commercial advanced
manufacturing space.  This is one of the
leading projects in the Ayrshire Growth Deal
to have reached physical development stage
and will be important to local businesses
providing quality flexible space with low
carbon sustainable design to support high
value jobs in North Ayrshire.  Work has now
also commenced on the design for Phase 2, to
accelerate the programme of delivery.
The Ayrshire Growth Deal programme at
Irvine Harbourside has made significant
progress with the consulta�on on a
masterplan for the area complete and the
appointment of designers to complete a
technical design for the coastal hub playpark
to start on site in 2024.  This represents the
programme moving towards delivery stage,
which will ensure the loca�on maximises its
poten�al as a regional tourism des�na�on,
providing jobs, increased visitors and
improved facili�es.
The Ayrshire Skills Investment Fund has been
approved by the Sco�sh Government and is
now in the implementa�on stage.  An
employer grant scheme has been launched to
support local businesses develop their
workforce with skills for the future in key
sectors.  
A 2023 Visitor Management Plan was
approved, colla�ng the wider range of place-
based services offered throughout our Council
to support and enhance the visitor experience
in North Ayrshire, while minimising the impact
on communi�es.  This provides an overall
investment of over £2m in revenue and capital
investment to support the sector.
A cross-party member/officer working group –
the Tourism Forum – has been formed and
now meets quarterly to oversee strategic
development of programmes and ini�a�ves to
support the tourism sector in North Ayrshire.
Our Council renewed its partnership with the
Crown Estate Scotland to
support con�nued
partnership working to
support coastal
communi�es and
support the

Page 14

Our Council Plan Progress Update – Mid Year 2023-24  Page 8 of 33
advancement of Ayrshire Growth Deal marine
tourism projects.
Atainment
Significant work has been undertaken to
con�nue efforts to close the poverty related
atainment gap through finalising plans to
implement a new model for the Professional
Learning Academy.  This model commenced in
August 2023 and ini�al feedback from school
leadership teams highlighted how this is
providing targeted support to raise atainment
and achievement, with a specific focus on
those most impacted by poverty.  
We have gathered evidence on the impact of
planned interven�ons and ini�a�ves during
the 2022-23 academic year.  This is being used
to inform future approaches.  Full details are
available in the Educa�on Services report.
Employability
We currently have 11 Modern Appren�ces
studying for their SVQ Level 3 in Youth Work,
with on-the-job training being provided by our
Modern Appren�ce Co-ordinator.  Our Youth
Work Modern Appren�ce programme is part
of the regular HM Inspectors of Educa�on
(HMIE) Progress Review Visit of Community
Learning and Development which took place
in September.  Results are due in October.
We have con�nued to expand the use of the
Skills Development Scotland Data Hub, which
is leading to further improvements.  For
example, the recently published Annual
Par�cipa�on Measure for 16-19 year olds is
the highest on record for our Council and the
2nd highest increase across all 32 local
authori�es in Scotland.  This is a result of
increased partnership working with members
of the Local Employability Partnership
including Educa�on, Employability, Self-
Directed Support (SDS), Ayrshire College and
Third Sector partners to ensure posi�ve
des�na�ons for all school leavers.
Employability week was held in May 2023 and
the key highlights were:
• 1,000 people atended events across the
week.
• Almost 140 young people atended the
Modern Appren�ceship recruitment day. 
90 applica�ons for Modern
Appren�ceships were received
immediately a�er the event, with 249
applica�ons to date (an increase from last
year).  CEIS also received 30 applica�ons
on the day for their youth employment
support programme.
• The Department for Work and Pensions
(DWP) job fair atracted almost 500
people and, of these, eight people found
work, 34 interviews were arranged or
conducted and 141 job applica�ons were
filled in within the two hours of the event.  
• At the Parent Hub, more than 100 people
atended and four new parents registered
to get support in finding employment.
Community Wealth Building
We are developing a refreshed Community
Wealth Building (CWB) Strategy that focuses
on achieving a wellbeing economy.  This
reflects the significant change in the local,
regional and na�onal economy since the
original strategy was launched, including the
impacts of the Covid pandemic, war in
Ukraine and the cost of living crisis, alongside
a shi� in the na�onal policy environment
towards a wellbeing economy.  This will be
considered by Cabinet in early 2024.
We have led on the development and
approval of the Ayrshire Regional Economic
Strategy (RES) - Delivery Plan for Year One . 
This focuses on actions that can feasibly be
commenced and/or delivered
in Year One.  It recognises
the substantial level of
activity already
underway which
aligns with the
priorities of the RES

Page 15

Our Council Plan Progress Update – Mid Year 2023-24  Page 9 of 33
including projects delivered by the Ayrshire
Growth Deal and the pioneering work of the
Ayrshire Community Wealth Building
Commission.  It seeks to build on existing
work, add value and align to the RES priority
themes, in addition to identifying new activity
targeted to achieving the strategy’s long-term
ambitious priorities.  This will be led by the
RES Delivery Group to be formed later in the
year.
Care Experienced Children and Young
People
Following a Council mo�on in March that
agreed care experienced should be treated as
a protected characteris�c in North Ayrshire,
work has been ongoing on the defini�on of
care experienced for use within Equality
Impact Assessments (EIA’s) and Children's
Rights Impact Assessments.  An EIA on the
proposed policy will be presented to Council
later this year alongside an update on the
defini�on and work required to include it
within the EIA template for future policy
changes (including budget proposals).
Our Educa�on Service has increased the
capacity of their Care Experienced Tutor by
extending weekly contracted hours funded by
the Sco�sh Government's Care Experienced
Children and Young People Fund.  Ini�al
evidence of impact of this interven�on is
posi�ve.  
The work to review our Educa�on Quality
Improvement Framework and process for
Establishment Reviews for session 2023/24 is
complete.  There is a renewed focus on
iden�fied target groups including care
experienced learners.  The framework
supports effec�ve improvement planning and
evalua�on and is used to support the quality
improvement agenda in all educa�onal
establishments.  
Addi�onally, we have increased opportuni�es
to further develop mentoring rela�onships
and have plans to increase the use of
Mo�va�on, Commitment and Resilience
(MCR) Pathways next session.  We have
developed a planning document to help target
support and review and iden�fy effec�ve
prac�ce for care experienced learners.  
Wellbeing
Next Steps
• We will increase the use of Mo�va�on,
Commitment and Resilience (MCR)
Pathways next session.
• We will await the results of our Child
Poverty and Cost of Living Board
applica�ons for funding from the Sco�sh
Government Child Poverty Prac�ce
Accelerator Fund and Cash First Fund.  
• We will meet with the Improvement
Service to push forward our data sharing
work following the outcome of our
Sco�sh Government Child Poverty
Prac�ce Accelerator Fund and Cash First
Fund applica�on.
• We will con�nue dra�ing our new
Community Wealth Building strategy
following considera�on by the Policy
Advisory Panel and Cabinet 
• We will present a paper on trea�ng Care
Experienced as a protected characteris�c
to Council later this year.
• We will support SPT with their funding bid
to Transport Scotland to further develop
the Strathclyde Regional Bus Strategy.
• We will update Cabinet on progress on the
Community Transport pathfinder in
December 2023.

Page 16

Council Plan Progress Update – Mid Year 2023-24  Page 10 of 33
Case Study – Townend Skills Hub
Greenwood Academy needed a space outside the school that could be used for learning
ac�vi�es for young people who find being in a school environment difficult.  School staff
approached our local Community Learning and Development team for support.  They
iden�fied Townend Community Centre in Dreghorn as a poten�al venue for a community
café.  This would link community groups, the community associa�on and the school.
In a pilot project before the
summer holidays, our young
people served around 40
customers.  The young people
involved were consulted on what
their expecta�ons would be of the
project and how they would
expect to benefit from it in terms
of preparing them for the world of
work.
At the end of the pilot an
evalua�on was undertaken with
our young people who were
involved.  All of them valued the
project and engaged really well –
more so than if it had been
delivered in the school.  
Some preferred it to the school environment because it was quieter, more approachable and
easier for them to engage with.  Several teachers from Greenwood Academy have visited the
space and there is excellent support from both them and the senior management team in
the school to con�nue the project.
Future plans include expanding the project to include provision for parents to atend adult
learning classes, provide volunteer
opportuni�es for people of all ages
and offer targeted support to 16 – 24
year olds who are not currently in
work.   Our Community, Learning and
Development team
con�nue to work
with the school
and
community
partners to
progress this.

Page 17

Our Council Plan Progress Update – Mid Year 2023-24  Page 11 of 33
Communi�es and
Local Democracy
Key Activities
Partnership Working
Our Officers have been engaging with The
Ayrshire Community Trust (TACT), and their
regional wider Ayrshire counterparts, to
ensure Third Sector representa�on on the
Regional Strategy Delivery Group which will
promote opportuni�es for community
organisa�ons to achieve their goals.
We have been working alongside the Third
and Voluntary Sector through the Child
Poverty and Cost of Living Board and
associated mini enquiries.  A Childcare Mini
Enquiry took place on 25th May 2023. 
Approximately 50 people from a variety of
community groups, Council services and
partner organisa�ons atended the event
which shared ideas and informa�on.  Groups
on the day held around the table discussions
on what is going well, what can be improved
and what gaps exist in provision.  Areas
discussed included:
• A need to improve the registra�on
process for Early Years services.
• A need to increase awareness of
en�tlement to early years provision.  
• A requirement for more breakfast
opportuni�es, ensuring they are
affordable and available across North
Ayrshire.
• A shortage of registered childminders.  
Several links are in place with North Ayrshire’s
Third Sector Interfaces (TSI) across the
Community Planning landscape.  The TSI is
currently Chair of the North Ayrshire
Community Engagement Network.   The Chief
Execu�ve of TACT has taken on the role of
Chair for the Community Planning Partnership
(CPP) Senior Officer’s Group.  
Ac�ve Involvement 
We have recently relaunched our Housing
Services’ Customer Par�cipa�on Strategy for
2023 – 2028.  This will ensure that our
communi�es are involved in decision making
and are empowered to influence how we
deliver our Housing Service.  Three priori�es
have been iden�fied to ensure this happens.  
• ‘Engage and Inform,’ focuses on
communica�ng with, consul�ng and
including our customers. 
Ensuring there is two-
way communica�on
with our tenants
and customers
and providing
opportuni�es for

Page 18

Our Council Plan Progress Update – Mid Year 2023-24  Page 12 of 33
customers to take part in ways that meet
their needs.  
• ‘Empower and Influence,’ focuses on
building community capacity, encouraging
and suppor�ng customers to take part,
and helping them to influence decision
making.  
• ‘Evolve and Innovate’ focuses on the
con�nuous improvement and
development of our service to best meet
the needs of our customers.
We con�nue to work directly with island
communi�es to develop and facilitate the
implementa�on of the Ten Year Island Plans
for Arran and Cumbrae.  This has included
suppor�ng Arran to develop three theme
groups under an 'Island in Balance' approach
of Economy, Community and Environment. 
On Cumbrae, we have worked with the Island
Plan Steering Group to progress the ‘Carbon
Neutral Islands’ project in addi�on to
developing governance arrangements and
crea�ng a fortnightly island presence to
support opportuni�es for direct engagement.
Community Planning Partnership
The second phase of Democracy Maters will
give people across Scotland the opportunity
to come together in their communi�es to
imagine how new and inclusive democra�c
processes can best help their town, village or
neighbourhood.  Discussions on Democracy
Maters Phase 2 have already taken place at
the CPP Senior Officers Group and the North
Ayrshire Joint Youth Forum, with a further
session planned for the Community
Engagement Network.  
The June Community and Locality Planning
training session received posi�ve feedback
from par�cipants including community
members, partner organisa�ons and Elected
Members.  Several partner outreach sessions
have taken place this year, including Police
Scotland and Sco�sh Fire and Rescue
colleagues, KA Leisure and Public Health.  
There con�nues to be significant development
around the structure and content of our
Locality Partnership agendas to ensure
stronger links to partnership, reducing
inequali�es and addressing local priori�es.
The Community Plan (LOIP) for 2022-30 has
been refreshed to ensure it is clearer and
more engaging for our communi�es and
partners.  This has included a redesign and
update of data.  Engagement with young
people around the plan is in progress.  The
results of this will be used to inform our
approach to including young people
throughout the lifespan of the Community
Plan as well as a ‘Plan on a Page’ aimed
specifically at children and young people.  
Locality Planning con�nues to develop across
North Ayrshire with partners becoming even
more embedded in the locality model.  Six
refreshed Locality Plans have been co-
produced with Locality Teams and will be
approved by the Locality Partnerships at their
December 2023 mee�ngs.
Our Community Planning Twiter account
con�nues to grow with over 800 followers and
more than 14,000 impressions since the last
quarter.  
28 Community “wishes” have been delivered
in 2023 so far through the Community
Benefits Wishlist.  This links needs in
communi�es with businesses delivering
contracts and ensures community benefit is
directed in the way which makes the most
impact.  In total, 61 “wishes” have been
delivered since the Wishlist was launched in
October 2021.

Page 19

Our Council Plan Progress Update – Mid Year 2023-24  Page 13 of 33
Communi�es and
Local Democracy
Next Steps
• We will con�nue the development of the
Par�cipa�on Strategy and new
Community Planning Partnership website
and Community Directory.  
• We will con�nue the development of the
new Community Planning website,
including a consulta�on list, events
calendar and online resources and
signpos�ng for staff, partners and
community members.
• We will con�nue to plan for our 2024
Community Planning Conference, which
will focus on Democracy Maters Phase 2.  
• We will hold mee�ngs in October and
November to provide feedback on our six
refreshed Locality Plans and seek approval
for the Plans at the December 2023
Partnership mee�ngs.
• We will con�nue our engagement with
young people around the Community Plan
(LOIP). 
• Will con�nue to develop our Performance
Management and Quality Assurance
Framework for our Advice Services.
• We will con�nue to develop our
consulta�on budget tool for the 2024/25
budget.
• We will con�nue to develop the online
Community Directory tool with a view to
launching in Winter 2023 along with the
new Community Planning website.

Page 20

Our Council Plan Progress Update – Mid Year 2023-24  Page 14 of 33
Case Study – Irvine Tennis Club
Irvine Tennis Club had a vision to revamp tennis courts in Thornhouse Avenue.  Irvine
Locality Partnership worked with the tennis club for the club to take on ownership through
community asset transfer of the courts from our Council to the Club.  We also provided help
and support to access funding.
Our Irvine Locality Officer supported the organisa�on to submit an expression of interest to
their Locality Partnership.  Irvine Tennis Club was invited to progress to the next round to
submit a full applica�on and deliver a presenta�on to the Partnership of the proposals.
Support to access funding was made available to the club and they were successful in
achieving a range of funding:  
• Common Good Funding £25,000
• North Ayrshire Ventures Trust £30,000
• Community Investment Fund £100,000
• Sports Scotland £100,000
This funded the resurfacing and
development of addi�onal tennis
courts, fencing and flood lights to
allow access and con�nued use in
winter months.
Irvine Tennis Club intend to build a
new club house which will host a
social area, toilets and changing
area with showers.
The Club has reinvigorated the
tennis courts in Irvine to enable the
community to come together to
enjoy playing tennis and other
games within the refurbished tennis courts.  They are now of a standard to enable the club
to compete as well as enable their community to use a safe year-round facility.  
Irvine Tennis Club welcomed Judy Murray to open the courts on 11th September – video of
the moment can be viewed online here.  The commitee have all worked hard, coming
together to take ownership of a community asset and turn old red ash pitches into state-of-
the-art tennis facili�es for the whole community.
The Club opened the courts up for community use at the end of
summer and already have over 70 members.  The Club has formed
many partnerships with community groups who have all expressed an
interest in a variety of ac�vi�es on offer at Irvine Tennis Club.

Page 21

Our Council Plan Progress Update – Mid Year 2023-24  Page 15 of 33
Climate Change
Key Activities
Energy
Work con�nues on the installa�on of two new
solar farms at former landfill sites in Irvine and
Kilwinning.  The projects both reached the
final detailed design stages and are scheduled
to commence construc�on in early 2024.  The
new solar farms will make a major
contribu�on to renewable energy genera�on
and carbon reduc�on, as well as bringing
sterile land back into produc�ve use.  
A detailed feasibility study for further
renewable energy at the i3 site in Irvine was
also completed, and officers are working on
developing a detailed business case for
considera�on, aligned to wider investment
proposals at the site.  
A new £350k Community Net Zero Carbon
Fund was launched, enabling local community
groups to bid for funding to help with
feasibility and/or installa�on of renewable
energy technologies on land or buildings they
own.  Officers are assessing the ini�al tranche
of applica�ons.
As part of our annual investment programme,
residents from a total of 900 Council owned
homes are expected to benefit from the
adop�on of various energy efficiency
measures, including external wall insula�on
and solar panels, as we invest to meet the
new Energy Efficiency Standard for Social
Housing 2 (EESSH2).  
A study to understand the investment
requirements for decarbonisa�on of Council
buildings has been commissioned, and will
help set out the measures, funding and
�melines required to meet our own net zero
targets and wider, na�onal 2038 public sector
building decarbonisa�on commitment.  The
high-level results of the study are expected in
January 2024.
Finally, work to develop our Local Heat and
Energy Efficiency Strategy and Delivery Plan
(LHEES) is nearing finalisa�on, with the new
LHEES due for publica�on in January 2024. 
The LHEES is designed to be at the heart of a
place based, locally led and tailored approach
to the heat transi�on.  These local strategies
will cover all of Scotland and underpin an
area-based approach to heat and energy
efficiency planning and delivery. Since April,
Home Energy Scotland have supported 2,611
households with energy efficiency advice. 
Transport 
Officers con�nue to work in partnership with
the Ayrshire Roads Alliance to develop the
new Ayrshire Electric Vehicle Pathfinder which
is set to bring £5m public electric vehicle
charging investment into Ayrshire to deliver
300 new chargers, subject to external funding. 
This is an exci�ng next step in helping
residents and businesses transi�on to electric
vehicles, by providing a well-distributed,
affordable and reliable public charging
network.  
A new route map for the decarbonisa�on of
our Council vehicles has priori�sed how we
will reduce emissions across our fleet.  This
includes a commitment that we will not
purchase any new fossil fuel powered
passenger or Light Commercial Vehicles
(LGVs), two years ahead of the 2025 target set
out in the Programme for Government.  
We are commited to improving knowledge
and a�tudes about sustainable transport
choices through the Trinity Ac�ve Travel Hub
and our Travel Smart programme.  This
includes working with organisa�ons and
volunteers to provide ac�ve travel ac�vi�es
across the area and our workplace
engagement programme
working with local
employers.  Ac�vi�es
delivered, included
personalised travel
planning, bike
maintenance classes

Page 22

Our Council Plan Progress Update – Mid Year 2023-24  Page 16 of 33
and challenges such as ‘Cycle to Work
September’.  We con�nue to update and
promote our Ac�ve Travel Hub social media
pages to raise awareness.  
Regenera�on projects that have commenced
this year include: 
• Construc�on of the North Crescent
Coastal Path Phase 1, Ardrossan.  
• An op�ons appraisal study for the
Valefield Bridge, Kilbirnie to help re-
establish this important ac�ve travel link.  
• Fairlie Coastal Path Phase 3 with
construc�on expected to start in Q4.
• Detailed design stage for Largs Promenade
Ac�ve Travel Study.
• Feasibility study for Cumbrae Ac�ve Travel
Link.
• Design of Old Caledonian Railway Path
Phase 2.
The following projects have been completed:
• Upgrade of the Harbour Path, Ardrossan
linking between the town centre and ferry
terminal.
• Design of the North Crescent Coastal Path
Phase 2, Ardrossan with funding for
construc�on secured from Sustrans. 
• Improvements to five separate path links
in Ardrossan, Saltcoats and Stevenston.  
• Upgrade of Old Caledonian Railway
Cu�ng, Saltcoats (Phase 1).  
• Upgrades to bus stop shelters to promote
walking to public transport.
Environment
Our Streetscene Service con�nues to support
volunteering groups.  Following nomina�ons
from volunteer groups, Elected Members and
the general public, a recogni�on event was
held at Saltcoats Town Hall to recognise the
contribu�on of our volunteers, par�cularly
young environmental ambassadors.  There
were 64 atendees with five awards presented
to the young environmental ambassadors for
various ac�vi�es, such as liter picking and
making hor�cultural enhancements in their
local areas.  Through working with volunteers,
issues and solu�ons are iden�fied, such as
litering of disposable vapes.  We worked with
the Irvine Clean Up Crew to provide an
appropriate disposal solu�on.
Our Environmental Enforcement Team are
working on a ‘Sea Starts Here’ campaign to
educate our residents and raise awareness of
liter being placed into drains and waterways,
which ul�mately leads to pollu�on of our
waterways and coastal loca�ons.  
Our ‘Intermediate Labour Market’ (ILM)
ini�a�ve has provided extra capacity and
enabled a focus on the ensuring paths are
edged and encroachment is cut back on our
cycle network to enable our residents to
access zero carbon travel.  
Successful bids for ‘Food for Thought’ grants
were evaluated effec�vely by a number of
North Ayrshire schools.  They are individually
inves�ga�ng the adop�on of low carbon
behaviour change in their communi�es.  
Our Climate Ac�on Town Stevenston Project
launched a�er successful funding from the
Chartered Ins�tute of Library and Informa�on
Professionals in Scotland (CILIPS).  This will
offer a series of climate and environmental
themed ac�vi�es for schools, families and the
local community in the library and
surrounding area, including climate cinema
screenings, climate classroom, eco-learning
ac�vi�es and outdoor learning.  Our
Streetscene Service has been working with
the friends of Kirkton Hall Glen to further
enhance the biodiversity of the area and
involved the local primary school in seeding of
the wildflower meadow in prepara�on for the
2024 growing season.  This project
has helped to bring
biodiversity into the school
curriculum, suppor�ng
learning outcomes and
the biodiversity of the
local area.

Page 23

Our Council Plan Progress Update – Mid Year 2023-24  Page 17 of 33
Our North Ayrshire 2030 Woodland Project is
progressing well with 35,627 new trees
planted.  The target is to plant 108,000 new
trees by 2030.
Reuse and Recycling
Waste Services worked alongside our
Economic Development team to outline
op�ons and recommenda�ons for a poten�al
‘remakery’ project to increase re-use and
repair across North Ayrshire.  The study
recommended op�ons to be progressed in
line with the new Shared Prosperity Fund
programme.  
Our Council's bulky waste reuse partner,
Cunninghame Furniture Recycling Company
(CFRC), collected 107 reusable matresses (1.3
tonnes) from April to September 2023, as part
of the ini�a�ve to promote opportuni�es for
their reuse along with 97.6 tonnes of
household furniture that would otherwise
have been disposed of.  
An Elected Members development session
took place on 20th April 2023 to discuss some
of the key drivers for increasing reuse and
recycling performance.  The Sco�sh
Government has published a dra� Circular
Economy (CE) Bill, which is expected to
become law by May 2024, with a further
consulta�on expected on their Waste Route
Map in the coming months.  The dra� CE Bill
and the Route Map consulta�on will be used
to inform the development of a new Zero
Waste Strategy.  We will schedule further
consulta�on sessions as part of the
development process.
Adapta�on
Our Council is undertaking Adapta�on
Scotland’s Capability Framework in order to
improve North Ayrshire’s resilience to climate
change.  The framework iden�fies four
capabili�es needed for an organisa�on’s
adapta�on journey.  The first internal self-
assessment was undertaken in a workshop
environment, with representa�ves from
services cross our Council and support from
Adapta�on Scotland.  The group iden�fied
evidence for the benchmarking tool, crea�ng
a baseline assessment of the current status.  A
proposed list of ac�ons was also iden�fied
which have been progressed over this period. 
The ac�ons are:
• Create and maintain a Council wide library
of climate change and adapta�on case
studies.
• Inves�gate poten�al of introducing a
climate change (adapta�on) risk
assessment template for strategic
organisa�onal risks.
• Raise awareness via a staff eLearning
module on climate change and
adapta�on.

Page 24

Our Council Plan Progress Update – Mid Year 2023-24  Page 18 of 33
• Build external capacity to share
understanding on climate change and
adapta�on.  
• Improve repor�ng by recording evidence
and measure outcomes in rela�on to
climate change and adapta�on.  
• Undertake annually the Adapta�on
Capability Framework and Benchmarking
Tool assessment to review Council wide
progress.
Suppor�ng Local Businesses
The Corporate Procurement Unit (CPU) work
closely with the Business Support and
Development Team, to iden�fy local suppliers
to invite them to quick quote.  We can now
confirm local spend for 2022/23 was £57.7
million (26% of total spend) and £2.7 million
worth of Quick Quotes were awarded locally.  
Our Business Development Team has
supported 83 businesses with a range of
ac�vi�es to reduce their environmental
impact including awareness raising,
consultancy support, green event hos�ng,
grant support and referrals to partner
organisa�ons.  We have also directly funded
17 businesses to par�cipate on the Net Zero
Accelerator programme.  This will seek to
provide the individual businesses with advice,
support and informa�on rela�ng to reducing
(and measuring) their environmental impact. 
It runs over a 12-month period and evalua�on
of the impacts will be undertaken during and
at the conclusion of the programme.  
The Communi�es and Place Fund was
approved by Cabinet on 30th May.  The Fund
was developed with input across services, the
Ayrshire Community Trust and Arran Council
for Voluntary Services and reviewed by the
Policy Advisory Panel.  It is comprised of a
compe��ve grant fund and Par�cipatory
Budge�ng (PB) fund.  The compe��ve grant
fund opened to applica�ons on 21st June. 
Nine awards were made to projects across
North Ayrshire, with a total value of £160,330. 
Unsuccessful applicants have been given
support and advice to beter posi�on their
applica�ons to reapply next year or pursue
alterna�ve funding sources.  The PB fund is
underway with awards being made later this
year.
Climate Change
Next Steps
• We will publish our new ‘Sustainable
North Ayrshire’ Strategy.
• We will publish our new Local Heat and
Energy Efficiency Strategy.
• We will progress to construc�on stage for
our new solar farm projects.
• We will launch new energy efficiency
measures offer as part of our Energy
Smart programme.
• We will con�nue the development of a
new Zero Waste Strategy.
• We will progress the procurement
exercise for the new Ayrshire Electric
Vehicle Charging Infrastructure project.  
• We will progress with our fleet
decarbonisa�on route map, including
explora�on of a hydrogen produc�on
feasibility study.  
• We will con�nue the construc�on of the
North Crescent Coastal Path Phase 1,
Ardrossan.  
• We will present our Local Transport and
Ac�ve Travel Strategy to Cabinet in
October.  It will provide a framework for
investment and decision-making in
transport for the benefit of our residents,
visitors and businesses up to 2028.  
• We will complete and submit our
statutory Biodiversity Duty report to the
Sco�sh Government in January.

Page 25

Council Plan Progress Update – Mid Year 2023-24  Page 19 of 33
Case Study – Ac�ve Travel
Several Ac�ve Travel projects took place during the summer months to encourage
sustainable travel.  Our Ac�ve Travel and Communica�ons Teams worked closely together to
promote the ac�vi�es, genera�ng significant interest from across our area.
Public Engagement on Ac�ve Travel Op�ons on
B777 between Beith and Kilbirnie 
In May this consulta�on on proposed
improvements to the B777 to provide walking,
cycling and wheeling opportuni�es, gained a
great deal of interest.   104 people took part in
the survey and there were 57,400 views of the
informa�on and 2,556 interac�ons on social
media.
Family Cycle Event at the Circuit
400 people atended this event at our newest
spor�ng and leisure facility in June following
significant promo�on through social media, press
releases, community radio, poster and leaflet
distribu�on as well as internally to our own
employees.  Held as part of the na�onwide
‘power of the bike’ campaign to promote the UCI
Cycling World Championships in Glasgow, the event enabled residents to try-a-bike, access
free safety checks and bike loans.  As a result, 400 people atended the event and there
were 22,000 views of the informa�on on our social media channels.
Cycle Maintenance Drop-In Sessions
38 people atended the sessions during August and September to help our communi�es get
their bikes ready for autumn.  Held across North Ayrshire, the sessions empowered residents
by teaching them how to care for and make minor repairs ‘on the go’ to their bicycles.  In
addi�on, accessible cycle routes and cycling sessions to build confidence were promoted. 
We received over 16,900 views of the informa�on and 283 interac�ons on social media.
Ayrshire Walking Fes�val
This pan-Ayrshire event was organised and promoted by our Ac�ve Travel Team.  186 people
atended events during the fes�val - an increase on the previous year despite a more
compact schedule. 
Through these ac�vi�es we can see that there is a
significant level of engagement with learning more about
ac�ve travel in North Ayrshire.  This is very posi�ve in
terms of working with our communi�es to deliver our
Climate Change priority.

Page 26

Our Council Plan Progress Update – Mid Year 2023-24  Page 20 of 33
A Sustainable
Council
Key Activities
Our Council Plan 2023-28
Our Council Plan 2023-28 was approved by
Council in June 2023.  Developed alongside
our communi�es, our Council Plan vision
remains ‘A North Ayrshire that is fair for all’. 
Our mission is ‘Working together to improve
the lives of our people in North Ayrshire’.  This
shows how we view our plan as a contract
with our communi�es, hence “our” plan.  It
aims to con�nue a culture of con�nuous
improvement by ensuring everyone working
in and alongside our Council is focussed on
improving the lives of the people we serve.
The first annual Best Value Thema�c Approach
Audit is in progress.  This approach replaces
the previous five-yearly audits.  The Best Value
theme for this year is “Leadership of the
development of new local strategic priori�es”,
focussing on the development of our new
Council Plan 2023-28.  The Best Value report
will be appended to the Annual Audit Report
and will be presented to our Audit and
Scru�ny Commitee in November.  
Tackling Digital Exclusion 
Our Council secured an award of £242,000
from the UK Government's Department for
Science, Innova�on and Technology (DSIT). 
This funding comes as part of the
commitment to advancing wireless
infrastructure and 5G technology.  We were
one of six successful local authori�es and the
only one in Scotland.  
A regional bid was submited to DSIT’s £40
million 5G Innova�on Regions (5GIR)
programme in September with South and East
Ayrshire Councils, with a decision from the UK
Government due at the end of October.  
The Digital Economy Skills Group: a sub-group
of the Ayrshire Skills Group con�nues to work
with partners and have agreed three priority
areas for 2024.  These are to: 
1) Develop a Digital Skills Collabora�on Pilot
with key stakeholders to help streamline
support and collec�vely understand and
address the challenges facing our digital
economy and align with the new Skills
Development Scotland Digital Economy
Skills Ac�on Plan (DESAP).
2) Undertake Digital Economy
Industry/School engagement.
3) Undertake Digital Skills Mapping.  
Effec�ve Financial Management
The budget process for 2024/25 has
commenced and includes a focus on the
alignment of strategic investment
opportuni�es linked to our Council’s key
priori�es outlined in our new Council Plan
2023-28.  For example, the Nethermains /
Shewalton solar investment linked to our
Council's focus on achieving Net Zero as well
as significant capital investment across flood
management and decarbonisa�on of our
Council fleet.  
There is ongoing discussions and progress
around various areas of financial flexibility
with the Sco�sh Government, including
poten�al changes to Council Tax through the
mul�plier and second homes levy. 
Discussions con�nue on the feasibility of a
tourist visitor levy and budget discussions on
the Verity House agreement, and what this
means within the context of budget
condi�ons.  
Further progress has been made with lease
income genera�on from commercial
proper�es and the non-
commercial property
por�olio will now focus
ini�ally on an Irvine
locality office
accommoda�on

Page 27

Our Council Plan Progress Update – Mid Year 2023-24  Page 21 of 33
review which is being managed through the
Transforma�on Board.  
In May 2023, Cabinet approved the
submission of two applica�ons to the Vacant
and Derelict Land Investment Programme.
Both applica�ons, Kyle Road and 36 Bank
Street were invited to submit Stage 2
applica�ons, due 17th November 2023.
Further feedback has been requested to
strengthen the Stage 2 submission.
Our Workforce
The Modern Appren�ceship recruitment
exercise has been undertaken and various
departments have welcomed these new
recruits to their teams.  In September a cohort
of Graduate Appren�ces from various
directorates across our Council started their
courses at the University of the West of
Scotland as part of our Council's workforce
development commitment.  
Cra� Appren�ceships con�nue to be
successful within our Council, with a new
annual intake commencing earlier in the year.
Six-monthly Workforce planning mee�ngs at a
Service level have been completed and plans
updated.  Methodology and tools to aid
analysis and review of data are embedded in
this process to inform decisions.  A PESTLE
analysis approach is u�lised to provide insight
into factors that will impact on workforce
planning.  
We launched a programme to reshape our
workforce in line with financial planning needs
in early May.  This will be concluded by March
2024.   
A Sustainable
Council
Next Steps
• We will review and implement any ac�ons
following our Best Value report due to be
published in November.
• We will support our External Auditors in
the audit of the next Best Value Thema�c
Approach early in 2024, focussing on
workforce innova�on.
• We will con�nue to engage with the Island
Plan Delivery and Steering Groups to
shape the annual ac�on plans for the
Island Plans.
• We will seek further feedback that has
been requested to strengthen the Stage 2
submissions for Kyle Road and 36 Bank
Street.
• We will await the third round of the
Levelling Up Fund.
• We will await the decision from the UK
Government on the regional bid
submited to DSIT’s 5G Innova�on Regions
(5GIR) programme with South and East
Ayrshire Councils.
• We will await the comple�on of The
Digital Connec�vity Maturity Assessment.

Page 28

Our Council Plan Progress Update – Mid Year 2023-24  Page 22 of 33
Case Study – Our Council Plan 2023-28 
We developed Our Council Plan 2023-28 together, it is
our living contract with our communi�es, it is ‘our’
joint plan, ‘Our Council Plan’. 
Many of the challenges North Ayrshire experiences are
complex and longer-term solu�ons are required to
address them sustainably.  As a result, each Council
Plan is designed to build on the progress of the
previous plan, always with a focus on improving the
lives of our residents. 
Our aim remains to achieve ‘A North
Ayrshire that is fair for all’ and our
mission is ‘working together to
improve the lives of our people in North Ayrshire’. 
Consulta�on was at the heart of our developing our new Council Plan.  
In January 2023 the Leader of the Council, the Chief Execu�ve and Chief Officers held in-
depth discussions with community group representa�ves across all six locali�es to ensure
our Council Plan reflected the priori�es of local residents.  We also invited views through a
joint Council Plan and Budget 2023/24 survey, atrac�ng 1,400 responses.   We worked with
Communica�ons, the Customer Contact Centre, the Community Learning and Development
Team, the Educa�on Service, Library Service and specialist Engagement Officers within the
Council to ensure as many of our residents as possible had the opportunity to have their say.
We offered Bri�sh Sign Language interpreters on request at events, induc�on hearing loops
and informa�on in alterna�ve languages.
Real lived experience is the best way to
inform what we do.  Since October 2022 we
have held a series of mini enquiries directed
by our Child Poverty and Cost of
Living Board to discuss and
inform our approach to
addressing Child
Poverty.  These
events have included
public, private and

Page 29

Our Council Plan Progress Update – Mid Year 2023-24  Page 23 of 33
third sector partners, alongside representa�ves from our communi�es, enabling honest
conversa�ons about challenges and how they could be addressed.  These directly informed
both our recent Child Poverty Ac�on Plan and the Council Plan, par�cularly within the
‘Wellbeing’ and ‘Communi�es and Local Democracy’ priori�es. 
Internal consulta�on included Chief Officer Development Workshops as well as discussion at
the employee Leadership Conference and the Execu�ve Leadership Team mee�ngs.
All of this engagement was added to earlier consulta�ons that took place for the Community
Plan (Local Outcomes Improvement Plan), Health and Social Care Partnership Strategic Plan,
Locality Partnership Plans and Island Plans.  It was considered alongside the Strategic Needs
Assessment undertaken for the Health and Social Care Partnership Strategic Plan and the
People’s Panel Survey 2022.  This ensured we gathered as wide a range of views as possible
while minimising duplica�on.  
The views from the consulta�on exercises were used to shape our four priori�es (see image
below) which were therea�er shared with our Modern Appren�ces (aged 16 to 24 years) in
April 2023 for their comments.  They confirmed that the dra� priori�es are “the most
important and crucial” to them and were sa�sfied that
the language and layout of the plan is clear,
straigh�orward and easy to read.  They provided
very helpful guidance on providing effec�ve
and relevant feedback on progress and we
will con�nue to work with them. 
Our Council Plan has also been informed
by use of data including that rela�ng to
popula�on decrease and demographic
change, child poverty, the Sco�sh Index
of Mul�ple Depriva�on as well as data
on climate change. The financial
sustainability of the Council is essen�al to
the future delivery of services and due
regard is therefore paid to that as a priority
so we can con�nue to work in partnership to
meet the needs of our communi�es.   
Now Our Council Plan 2023-28 is approved, we are focussing
on delivering on our priori�es.  If you have any ques�ons or
comments, please contact the Corporate Policy,
Performance and Elec�ons Team on 01294 310000 or
email NorthAyrshirePerforms@north-ayrshire.gov.uk.

Page 30

Our Council Plan Progress Update – Mid Year 2023-24 Page 24 of 33
Audits, Inspec�ons and Accredita�ons 
Our Council's External Audit of the accounts and wider scope Audit is due to be presented at the
Audit and Scru�ny Commitee in November.  This includes the first in the new Best Value Thema�c
Approach audits, replacing previous five yearly audits.  Best Value is a statutory duty that ensures we
are always striving to improve, have effec�ve governance, strong leadership and work closely with
partners (in par�cular our communi�es) to inform decision making.  
In this new annual approach, each year the Accounts Commission will decide on a par�cular theme
to form the basis of the Best Value Thema�c Audit in all 32 Sco�sh local authori�es that year.  This
will enable effec�ve benchmarking and scru�ny of our performance by comparing our audit report to
other councils.  Previously audits were staggered, rather than synchronised, across local authori�es.
The Best Value theme for this year is “Leadership of the development of new local strategic
priori�es”, focussing primarily on the development of our new Council Plan 2023-28 and the
involvement of our communi�es in developing our priori�es.  Once published, we will consider any
recommenda�ons and develop an ac�on plan.
The Corporate Procurement Team is currently undertaking a Procurement and Commercial
Improvement Programme (PCIP) assessment with the outcome being determined later in the year.
Our Community Learning and Development services are currently undertaking their regular HM
Inspectors of Educa�on (HMIE) Progress Review Visit of Community Learning and Development. 
Results of the inspec�on are due to be published in October.
Schools are subject to periodic external evalua�on by the na�onal inspec�on agency, Educa�on
Scotland.  Early Learning and Childcare se�ngs are inspected by both Educa�on Scotland and the
Care Inspectorate.  Recently eight educa�onal establishments were inspected by Educa�on Scotland
and the Care Inspectorate, who found the very posi�ve performance within our schools and Early
Years centres.  Ac�on has been taken to celebrate strengths and address areas for improvement
iden�fied in the inspec�on reports.  Reports have been published on the Educa�on Scotland and
Care Inspectorate websites. 
Our Council is undertaking Adapta�on Scotland’s Capability Framework in order to improve North
Ayrshire’s resilience to climate change.  The framework iden�fies four capabili�es needed for an
organisa�on’s adapta�on journey.  The first internal self-assessment was undertaken in a workshop
environment, with representa�ves from services cross our Council and support from Adapta�on
Scotland.  Full details are included in our Climate Change sec�on above.

Page 31

Our Council Plan Progress Update – Mid Year 2023-24 Page 25 of 33
Performance Summary 
There is a high number of performance indicators (16 PIs) where the current status is unknown.  This
is due to the �ming of the performance management framework in August following approval of the
Council Plan meaning se�ng targets, par�cularly for newer PIs, with only a month le� in the quarter
would not have been best prac�ce.  However, targets where appropriate were set for year-end (see
Performance Indicators sec�on below).  
Progress against the annual targets gives confidence that performance is on schedule, with some
areas such as the number of unemployed people progressing into employment already exceeding
their annual target at mid-year (652 against a target of 450).  Our Street Cleanliness score shows we
have performed better than expected at 90.1% against a target of 87%.  Participatory Budgeting is
currently sitting at 2.06% to date, ahead of the 1.5% target for Quarter two and year end.
Other areas include the number of empty properties brought back into use and number of new build
properties (all tenures) which are progressing at over 50% of target at mid-year, though these may
be subject to seasonal fluctuations later in the year. 
Measures adrift of target
This sec�on details the performance indicators adri� of target and the ac�on being taken to address
performance.  Due to expected data lags the most recent data may relate to previous �me periods
but may only now be available to report.  To avoid duplica�on, only data that has not previously been
reported to our Cabinet is included in this sec�on.
At mid-year, the statuses of all PIs within our new Council Plan are either on target (7) or have
previously been reported under our previous Council Plan at Year-End 2022-23.
On Target, 7,
27%
Slightly Adrift of
Target, 3, 11%
Data Only /
Status Unknown,
16, 62%
Performance Indicators
On Target Slightly Adrift of Target
Significantly Adrift of Target Data Only / Status Unknown
On Target,
46, 100%
Actions
On Target Slightly Adrift of Target Significantly Adrift of Target

Page 32

Our Council Plan Progress Update – Mid Year 2023-24  Page 26 of 33
Performance Indicators
The Council Plan Performance Management Framework was approved by Cabinet on 29th August 2023.  As a result, it wasn’t feasible to set meaningful targets for Quarter 2
(end of September) for some indicators.  The Annual 2023/24 target is included to help support scru�ny of performance.
PI Code and Description 2020/21
Value
2020/21
Target
2020/21
Status
2021/22
Value
2021/22
Target
2021/22
Status
2022/23
Value
2022/23
Target
2022/23
Status
Q2
2023/24
Value
Q2
2023/24
Target
Q2
2023/24
Status
2023/24
Target
CP_36 Number of residents participating in
community learning and development
activity including youth work*   
17,269   17,804   16,503   18,700
CP_04 Proportion of children meeting
developmental milestones (LGBF)** 82.2%   78.7%  
Data
Available
February
2024  
Measured
Annually   79%
CP_37 Average total tariff score of pupils
living in SIMD 20% most deprived areas 724   711  
Data
Available
March 2024  
Measured
Annually   714
CP_06 Average tariff score: All Leavers 912 900  905.6 880 
Data
Available
March 2024  
Measured
Annually   908
CP_38 Average total tariff for Care
Experienced Young People 448   457  
Data
Available
June 2024  
Measured
Annually   465
CP_07 Percentage of school leavers
entering positive destinations (LGBF) 95.2% 96.2%  96% 93.5% 
Data
Available
February
2024  
Measured
Annually   96.4%
CP_39 Number of unemployed people
progressing into employment 285 200  524 450  437   652   450
CP_10a Percentage of procurement spent
on local enterprises 21.39% 23.5%  22.93% 24%  26.04% 25%  Measured
Annually   26%

Page 33

Our Council Plan Progress Update – Mid Year 2023-24  Page 27 of 33
PI Code and Description 2020/21
Value
2020/21
Target
2020/21
Status
2021/22
Value
2021/22
Target
2021/22
Status
2022/23
Value
2022/23
Target
2022/23
Status
Q2
2023/24
Value
Q2
2023/24
Target
Q2
2023/24
Status
2023/24
Target
CP_40 Number of new build housing units
reaching completion (all tenures) (Actual
not cumulative)*      
562   223   295
CP_41 Number of empty homes brought
back into use (Actual)*** 122   335   120    180   200
CP_28 Hectares of vacant & derelict land in
North Ayrshire 1,204 1,194  1,198 1,144  Data
pending 1,094  Measured
Annually   1,094
CP_27 Street Cleanliness Index –
Percentage Clean (LGBF) 91.34 94  86.7 94  84.6 90  90.1%   87%
CP_20 Overall percentage of road network
that should be considered for maintenance
treatment
37.1% 38.1%  33.9% 37.5%  34.8% 33.8%  Measured
Annually   34.8%
CP_42 Provided floor space of
commercial/industrial space within our
Council portfolio (sq ft)*      
400,991   Measured
Annually   404,755
CP_02 Percentage of Council budget
directed via participatory methods 1.13% 1.2%  2.32% 1.1%  2.74% 1%  2.06% 1.5%  1.5%
CP_43 Number of Council assets under
community management (cumulative)*       49   51   54
CP_30 Total installed capacity of low carbon
heat and electricity generation across the
Council's estate
10,720 9,800  11,680 11,000  12,104 11,800  Measured
Annually   12,000
CP_29 Overall carbon emissions (tonnes)
(Non-domestic Council estate) 22,846 35,127  21,791 21,247  20,896 21,000  4,060   19,500
CP_44 Percentage of council dwellings that
are energy efficient 97.6%   97.7%  
Data
Available
February
2024  
Measured
Annually   98.1%

Page 34

Our Council Plan Progress Update – Mid Year 2023-24  Page 28 of 33
PI Code and Description 2020/21
Value
2020/21
Target
2020/21
Status
2021/22
Value
2021/22
Target
2021/22
Status
2022/23
Value
2022/23
Target
2022/23
Status
Q2
2023/24
Value
Q2
2023/24
Target
Q2
2023/24
Status
2023/24
Target
CP_45 Length of new or improved active
travel routes per annum (Metres)*       1,090   Measured
Annually   2,000
CP_46 Number of trees planted under the
North Ayrshire 2030 Tree Planting Strategy*       35,627   Measured
Annually   40,000
CP_19 Proportion of operational buildings
that are suitable for their current use (LGBF) 91.05% 93%  91.1% 93%  91.5% 93%  Measured
Annually   92.1%
CP_31 Percentage of total household waste
that is recycled (calendar year as per SEPA)
(LGBF)
52.1% 52.1%  56.3% 53.1%  55.3% 56.9%  61.3% 51%  57%
CP_25 Percentage of Council dwellings that
meet the Scottish Housing Quality Standard
(LGBF)
98.83% 99.5%  49.3% 99.5%  63.2%   Measured
Annually   72.5%
CP_47 Gross rent arrears (all tenants) as at
31 March each year as a percentage of rent
due for the reporting year (LGBF)
5.5%   6.6%   7.1%   Measured
Annually   6.5%
CP_48 Percentage of income due from
Council Tax received by the end of the year
(LGBF)
92.1%   93.3%   94.7%   Measured
Annually   94%
*These indicators have been newly introduced for the Council Plan 2023-28, historical data isn’t currently available for the greyed-out time periods.
**CP_04 Proportion of children meeting developmental milestones (LGBF) – This indicator has been renamed from ‘Percentage of children achieving their developmental
milestones at the time the child starts primary (LGBF)’ to fully align wording with the LGBF.  The measure is unchanged.
** CP_41 Number of empty homes brought back into use (Actual) – Due to a system issue the historical data for this PI has changed slightly.  2020/21 has been amended
from 121 to 122.  2021/22 has been amended from 334 to 335 and 2022/23 has been amended from 123 to 120.  This has been rectified for future reporting.

Page 35

Our Council Plan Progress Update – Mid Year 2023-24  Page 29 of 33
Action Tracker
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024/25
2024/25
2024/25
2024/25
2025/26
2025/26
2025/26
2025/26
2026/27
2026/27
2026/27
2026/27
2027/28
2027/28
2027/28
2027/28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 
CP01 Ensuring that wellbeing is at the heart of local life and
opportunities, with a focus on tackling inequalities. 
CP02 Developing a Community Wealth Building approach to a
wellbeing economy. 
CP03 Improving educational attainment and achievement and closing
the attainment gap. 
CP04 Improving outcomes for care experienced young people
including implementation of The Promise. 
CP05 Developing the Young Workforce and ensuring positive
destinations for school leavers. 
CP06 Providing lifelong learning opportunities for individuals and
organisations, including digital literacy. 
CP07 Maximising access to and uptake of benefits, entitlements and
financial advice. 
CP08
Ensuring that supports are available in communities to alleviate
cost-of-living pressures through community hubs and networks. 
CP09
Through our housebuilding programme and wider Housing
Investment provide homes for life that meet the needs of our
residents.

Page 36

Our Council Plan Progress Update – Mid Year 2023-24  Page 30 of 33
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024/25
2024/25
2024/25
2024/25
2025/26
2025/26
2025/26
2025/26
2026/27
2026/27
2026/27
2026/27
2027/28
2027/28
2027/28
2027/28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 
CP10
Increase the number of homes in the area through a mix of
private and social developments and bringing empty buildings
back in to use. 
CP11 Exploration of models and the development of pilot schemes to
increase access to and use of public/community transport. 
CP12 Ensure our places and spaces where we live, work and visit are
well maintained and accessible. 
CP13 Developing infrastructure to support business growth. 
CP14 Support KA Leisure’s leadership of North Ayrshire’s Health and
Wellbeing Alliance. 
CP15
Through the Health and Social Care Partnership Strategic Plan
we will protect and provide care and support for those in
need.***                   
CP16
Developing strong relationships with communities and partners
based on trust and shared aspirations using their experiences to
inform service provision. 
CP17
Providing support for community organisations in achieving
their goals, including as Community Wealth Building anchor
organisations. 
CP18
Creating a participation and engagement framework which
ensures opportunities and support for all residents to take part
in influencing local democracy and Council and partner
strategies.

Page 37

Our Council Plan Progress Update – Mid Year 2023-24  Page 31 of 33
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024/25
2024/25
2024/25
2024/25
2025/26
2025/26
2025/26
2025/26
2026/27
2026/27
2026/27
2026/27
2027/28
2027/28
2027/28
2027/28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 
CP19 Supporting participatory budgeting.                   
CP20 Supporting community asset transfer and community owned
and operated/managed assets. 
CP21 Supporting the Community Planning Partnership and the
Community Plan (LOIP). 
CP22 Developing partnerships with the third and voluntary sector. 
CP23
Placemaking, including creation of locality action plans based
on the Community Plan (LOIP) priorities and support the
delivery of Islands Plans. 
CP24 Ensuring an inclusive, fair, rights-based and asset-based
approach in our work. 
CP25 Accessible public services, both digitally and locally, ensuring a
‘No Wrong Door’ approach. 
CP26 Embedding our net-zero ambition in all democratic decision-
making. 
CP27
Reducing the carbon footprint of our estate through
rationalisation utilising a locality-based approach, and taking a
fabric first and low carbon energy generation approach to
homes and buildings. 
CP28
Improving resilience and reducing carbon by developing and
supporting supply chains where materials and goods are
sourced locally.

Page 38

Our Council Plan Progress Update – Mid Year 2023-24  Page 32 of 33
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024/25
2024/25
2024/25
2024/25
2025/26
2025/26
2025/26
2025/26
2026/27
2026/27
2026/27
2026/27
2027/28
2027/28
2027/28
2027/28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 
CP29 Promoting new woodland creation and protecting our green
spaces to provide a natural resource for carbon sequestration. 
CP30 Supporting local businesses as they meet their climate change
obligations. 
CP31
Promoting a circular economy in North Ayrshire to reduce
consumption of raw materials and promote reuse, repair and
recycling, and generating energy from residual waste. 
CP32 Developing local Low Carbon energy generation schemes and
networks. 
CP33
Unlocking the potential of community owned energy
generation to bring new income streams into communities and
help them take direct action to combat climate change. 
CP34
Learning for Sustainability, and work with communities to
adopt low carbon behaviour change and encourage climate-
based volunteering activities. 
CP35 Improving communities’ preparedness to deal with the impacts
of climate change already locked-in. 
CP36 Working with communities to adopt low carbon behaviour
change and encourage climate-based volunteering activities. 
CP37 Taking a nature-based approach to protect our habitats and
species. 
CP38 Developing and promoting active travel infrastructure.

Page 39

Our Council Plan Progress Update – Mid Year 2023-24  Page 33 of 33
***Delivery of this ac�on is managed through the Health and Social Care Partnership Strategic Plan.
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024/25
2024/25
2024/25
2024/25
2025/26
2025/26
2025/26
2025/26
2026/27
2026/27
2026/27
2026/27
2027/28
2027/28
2027/28
2027/28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 
CP39 Transitioning to low and zero carbon travel. 
CP40
Ensuring robust governance arrangements are in place to fulfil
the Council’s statutory duties, manage risk and support delivery
of key priorities.                   
CP41 Using dynamic data and lived experiences to inform decision-
making.                   
CP42 Working with partners nationally, regionally and locally to
secure investment and target resources towards our priorities.                   
CP43
Driving change and transformation, using technology where
appropriate, to deliver efficient and effective services and
support delivery of priorities.                   
CP44 Maximising financial flexibilities to help support delivery of
priorities.                   
CP45 Maximising value from the use of our assets.                   
CP46 Focusing our investment on priorities.                   
CP47 Effective workforce planning ensuring that we have the right
skills/resources to deliver priorities.

Page 40

Our Council Plan Progress Update – Mid Year 2023-24 
Page 34 of 33 
We strive to make our repor�ng as accessible as possible.  If you have
any ques�ons or require further informa�on on our Council’s
performance please contact:
The Corporate Policy, Performance and Elec�ons Team
Tel:  01294 310000  Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk
Reports can be viewed at www.north-ayrshire.gov.uk/performance