NORTH AYRSHIRE COUNCIL 
4 June 2026 
Audit & Scrutiny Committee 
Title:    2024/25 External Audit Action Plan Update 
Purpose:  To invite Committee to note the updated actions identified in the
2024/25 External Audit Action Plan. 
Recommendation:  That Committee notes the updates to the agreed Action Plans as
outlined in Appendix 1. 
1. Executive Summary 
1.1 Audit Scotland’s Annual Audit Report for 2024/25 was presented to Audit & Scrutiny
Committee on 23 September 2025. 
1.2  Audit Scotland’s reports included action plans in relation to the recommendations for
improvement identified during the course of the audit and full details of the proposed
management actions were appended to the reports. 
1.3 Appendix 1 provides an update on the management actions taken to date and
provides updated target dates for any outstanding items. 
2. Background 
2.1 The 2024/25 audit of the Council’s accounts was conducted by Audit Scotland and
their report on the Annual Audit was presented to Audit & Scrutiny Committee on 23
September 2025. 
2.2  The recommended actions identified in the reports related to a range of issues,
including: 
• Non-current assets;
• Council Plan actions;
• Transformation savings and
• Public reporting on Transformation.

Page 2

2.3  A review of the proposed management actions has now been undertaken and details
of the completed actions and their completion dates have been detailed in Appendix
1. Where any actions have not yet been completed, the appendix provides an update
on the proposed management action and the target date for completion. 
2.4  In summary, the updates note: 
• 2024/25 Annual Audit Report - All actions completed; and 
• Best Value Thematic Report – One action complete, other action in relation to
transformation savings remains ongoing with a March 2029 target date. 
3. Proposals 
3.1 It is proposed that Committee notes the updates to the agreed Action Plans as outlined
in Appendix 1. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by maximising financial
flexibility to support the delivery of our priorities. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None.

Page 3

United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Audit Scotland and Responsible Officers identified within the Audit and Best Value
reports have been consulted as part of the review. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Natalie Graham, Senior Manager (Corporate
Finance), Financial Management, on 01294 324533. 
Background Papers
0

Page 4

Appendix 1
2024/25 Annual Audit Report 
Issue / Risk Recommendation Agreed management action Actions Completed Completion Date
1. A number of significant
amendments have been required
to the Annual Accounts to ensure
in particular that non-current asset
figures are fairly stated. 
A large number of audit adjustments
were required to the financial
statements to correct misstatements
identified from the audit. In particular,
we identified misstatements of
£82.374 million in the unaudited
Annual Accounts which arose as a
result of errors in the classification
and valuation of Property, Plant and
Equipment. This is outwith the norm
following an audit and has added
additional pressure for the audit team
and council staff in concluding the
audit. 
Risk: The deadline of 30 September
for concluding the audit is not
achieved. 
The council should review
its arrangements for
preparing the Annual
Accounts. This should
include a review of capital
accounting processes and
procedures. 
A full review of capital
accounting year end procedures
will be carried out during 2025-
26. This will include the
procedures for reviewing
information provided by the
Council’s valuation team and the
use of external valuers. 
Natalie Graham, Senior
Manager - Corporate Finance 
31 March 2026
Internal procedures between
Financial Management and
Estates have been
strengthened to include
additional checks when an
asset is replaced, the provision
of dates for ‘approved for sale’
and ‘anticipated completion’
and verifications completed
when external works have
been included in valuations.  
31 March 2026 
2. Impairment of non-current
assets 
Accounting standards require the
council to assess at the end of each
financial year whether there are any
indications an asset is impaired. Most
assets are valued at least every five
years and generally when valued,
each asset is subject to a physical
inspection. There are however some
assets that are never revalued. The
council’s impairment review is largely
An impairment review
should be conducted
whenever there is an
indication that an asset
might be impaired such as
physical damage,
obsolescence or
restructuring. The existence
of an impairment indicator
may also suggest that the
remaining useful life needs
to be adjusted even if no
Under current procedures, an
impairment review is carried out
for all assets valued within the
financial year. In addition, the
valuation team undertakes an
annual impairment review to
determine if any assets not
revalued in year are subject to
material change. 
The Accounting Policies in
relation to asset impairment will
be reviewed and enhanced to
The approach taken by estates
is detailed fully in their
valuations cover report at
section 1.8.1.  
Accounting policies have been
updated to include details of the
impairment review process.  
14 April 2026

Page 5

Appendix 1
limited to assets revalued and should
be made more robust and
comprehensive. 
Risk: There is a risk that asset
values are overstated.  
impairment loss is
recognised.
provide clear reference to the
impairment review process. 
Natalie Graham, Senior
Manager - Corporate Finance 
Emma Mulholland, Team
Manager - Estates
31 March 2026
3. Progress on Council Plan
Actions 
The council does not set out in
advance what criteria have to be met
for an ‘on target’ judgement to be
made for each quarter, relying
instead on updates from individual
teams leading on the strategies and
other supporting evidence (including
‘Next Steps’ from the previous
report). If the ‘Next Steps’ actions
were SMART it might be possible to
analyse whether all the relevant ones
within the time period had been met
and that could feed into whether an
action was on target. 
Risk: There is a lack of transparency
in how progress is assessed for
Council Plan actions.
The council needs to set
out in advance what criteria
have to be met for an ‘on
target’ judgement to be
made for each action in the
Council Plan.
The Performance Management
Strategy is being revised and
will be presented to the Audit
and Scrutiny Committee on 20th
November 2025. This public
facing strategy will contain
details of how to determine the
status of Council Plan actions
based on existing strategies and
next steps. This approach will be
supported by additional training
for teams providing updates
during 2026. 
The Council Plan Progress
Reports will include SMART
next steps. These next steps will
be recorded within our
performance management
system to track their status
transparently and inform the
status of Council Plan actions. 
Isla Cruickshanks, Senior
Manager – Policy,
Performance & Democracy 
20 November 2025
The Performance Management
Strategy was approved by
cabinet on the 2nd December
and considered by Audit &
Scrutiny on the 29th January
2026.  This public facing
strategy is available on our our
website.  It details how to
determine whether the status of
a Council Plan action is on
target, slightly adrift of target or
significantly adrift of
target.  This information
logically details specific criteria
that if met would indicate a
status.  This strategy was
designed as a performance
management manual for our
council and is the basis of
performance management
training, so will in turn support
Best Value.  The Council Plan
Progress Reports now include
SMART next steps with
progress monitored through
future reporting. 
29 January 2026

Page 6

Appendix 1 
BV Thematic Report 
Issue / Risk Recommendation Agreed management
action
Actions Completed  Completion Date
1. Transformation savings fall
significantly short of the savings
required
The council’s latest MTFO identifies a
structural funding gap of £46.7m
(including HSCP pressures) which
must be addressed as part of the
council’s Medium-Term Financial
Plan. Whilst we recognise that
transformation alone will not offer the
full solution to the financial gap
identified in the MTFO, the level of
financial efficiencies from the
Sustainable Change Programme
should be commensurate with the
scale of the financial challenges. 
The council should
ensure its plans are
sufficiently ambitious to
respond to its financial
challenges. It should
clearly set out the extent
to which savings from
transformation will help
address the budget
shortfalls set out in its
Medium-Term Financial
Plan.
It is recognised that the
level of financial
efficiencies should be
commensurate with the
scale of the financial
challenges. Further work
will be progressed as part
of the council’s medium-
term financial planning to
set out clearly how the
council plans to address
budget gaps through
further transformation and
reform activity and
through a broader
package of measures,
including areas of service
review and possible
reduction, opportunities
for further revenue
generation and an
ongoing planned use of
council reserves..
Mark Boyd, Head of
Finance
31 March 2029
On the 25th February 2026 the Council
delivered a balanced budget that included
£6.612m of savings for 2026/27, £3.500m
reserves and an increase in Council tax of
8.5%. From the total savings £2.270m is
attributed to the programme of
Transformation and service reviews across
the Council. The Council's Medium-Term
financial plan for 2027/28 will continue to
be progressed through 2026 and this will
include the further development of a range
of measures to address the pressures
faced by the Council. 
Ongoing

Page 7

Appendix 1 
2 Public reporting on progress with
transformation
The council does not currently report
publicly on how it is progressing with
delivering transformation as a whole
in terms of planned and realised
financial and non-financial benefits. 
To provide assurance to
elected members and the
public about how the
council plans to change
to sustain services in the
future the council should
report publicly on how it
is progressing with
delivering transformation,
as a whole, in terms of
planned and realised
financial and non-
financial benefits. 
The development of more
public facing material will
be produced to
demonstrate the council’s
progress on the
Sustainable Change
Programme. This will
include use of the
council’s new website to
further promote activity
and the progress being
made to address the
financial challenges. 
Mark Boyd, Head of
Finance
30 September 2025 
We published our Council Plan Mid Year
Progress Report on 26th January on a
dedicated web page.  Our Council Plan Six
Monthly Progress Report 1 April 2025 to
30 September 2025  Our six monthly
progress report on our council plan
performance, looking at each of our
council priorities, our performance
summary and indicators and incorporating
updates on the Transformation
Programme. 
26 January 2026