Democracy Spraffa

9 - Internal Audit Plan 2026-27

North Ayrshire Council · 12 March 2026
Back to Audit and Scrutiny Committee — 12 March 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

OFFICIAL INFORMATION
OFFICIAL INFORMATION 
NORTH AYRSHIRE COUNCIL 
12 March 2026 
Audit and Scrutiny Committee 
Title:    Internal Audit Plan 2026/27 
Purpose:  To inform the Committee of the proposed internal audit plan for
2026/27. 
Recommendation:  That the Committee approves the internal audit plan for
2026/27. 
1. Executive Summary 
1.1 Internal Audit provides an independent and objective opinion on the Council’s risk
management, governance and control environment by evaluating its effectiveness.
This report presents the proposed internal audit plan for 2026/27. 
1.2 Prior to the start of each financial year internal audit, in conjunction with senior
management, put together a proposed plan of audit work.  The objective of our
planning process and subsequent plan is to put us in a position to provide a well-
informed and comprehensive annual audit opinion, based on sufficient and
appropriate coverage of key business objectives and risk management processes. 
1.3  The proposed internal plan is risk-based and provides sufficient coverage to support
an annual audit opinion while retaining the flexibility to respond to emerging risks. 
2. Background 
Internal Audit Plan 2026/27 
2.1 The 2026/27 plan has been developed using the rolling approach first used in 2024/25
and continued in 2025/26.  This method ensures the plan remains flexible and
responsive to changing risks across the Council.  The plan is essentially two phased: 
• Phase 1, this paper, will cover quarters 1 and 2 in terms of the planned audits 
for the first 6 months of the financial year.
• Phase 2, or the mid-year review, will identify the audits to be carried out in 
quarters 3 and 4.
• Quarter 3 and 4’s audits are selected from the rolling list of potential audit 
assignments.

Page 2

OFFICIAL INFORMATION
OFFICIAL INFORMATION
2.2 The benefit of this approach is that it allows the internal audit team to remain 
flexible, agile and capable of responding to emerging risks.  This approach is also in 
line with the new Global Internal Audit Standards (GIAS) which came into effect on 1 
April 2025 and require the audit plan to be risk-based. 
2.3 Several factors are considered when putting together the risk based internal audit plan
for 2026/27, including: 
• Consultation with senior management across all services;
• Review of the Council’s key objectives and Council Plan 2023-2028;
• Review of the audit universe, in conjunction with senior management;
• Review of the Council’s fundamental business processes and key services;
• Review of the Council's current risk management framework, processes and 
risk management maturity;
• Review of the key risks featuring in the Council's risk registers;
• Internal Audit’s own risk assessment based on knowledge of the business and 
incorporating findings from previous internal audit work; and
• Internal Audit’s awareness of emerging regional and national risk factors. 
2.4 The risk universe is a documented risk assessment maintained by internal audit and
used to document the consultation which takes place between internal audit and
senior management.  It outlines risk factors such as: 
• Links to the strategic priorities within the Council Plan for 2023-2028;
• Links to strategic, corporate and operational risk registers;
• Whether the auditable area is a source of significant risk;
• Whether there is significant value to the Council in the audit being carried out;
• Known risk factors arising from local and national issues; and
• Risk factors arising from previous internal audit work and knowledge of the 
Council. 
2.5 An overall conclusion is reached from an assessment of each risk area, which
categorises audits into the following priorities: 
• Priority A – a ‘must do’ audit based on risk (very high risk);
• Priority B – a ‘should do’ audit, time permitting (high risk);
• Priority C – a ‘may do’ audit, time permitting (moderate risk); and
• Priority D – an audit where the result would not be of sufficient value to the 
Council (low risk). 
2.6 Examples of the key risk factors which have influenced the early part of the 2026/27
internal audit plan are as follows: 
• Cyber resilience continues to be a high priority across organisations and is 
identified as a strategic risk for the Council.  The Internal Audit team has, over 
a number of years, utilised the Scottish Government’s Cyber Resilience 
Framework as the basis for ICT audit work, and this risk-based approach will 
continue to inform the 2026/27 audit plan.
• The enacting of legislation such as Awaab’s Law will see the implementation 
of legally enforced deadlines for investigations and repairs.  Internal Audit will

Page 3

OFFICIAL INFORMATION
OFFICIAL INFORMATION 
provide assurance to the Council through planned work relating to dampness 
and mould.
• The Council has recently implemented, or is the process of implementing, 
significant system changes, including upgrades to the general ledger and the 
introduction of a new social work system within the HSCP.  Effective 
implementation and control of these systems is critical, given their role in 
producing reliable management and financial information. 
2.7 The overall objective of the work of internal audit is to enable the Senior Manager to
form an evidence based independent opinion at the end of the year on the adequacy
of the Council’s internal control, risk and governance arrangements. This opinion,
which will be outlined in the annual audit report, also forms part of the Annual
Governance Statement for the year which is included within the Council’s financial
statements. 
2.8 Whilst the audit plan is risk based and the current work has identified audits planned
for the first 6 months of the year, it is also agile.  The implications of this are that
previously agreed work could be deferred should a new risk profile arise.  Any such
changes will be presented back to the committee through the regular reporting to Audit
& Scrutiny. 
2.9 Internal audit coverage can never be absolute, and responsibility for risk management,
governance and internal control arrangements will always remain fully with
management.  As such, internal audit cannot provide complete assurance over any
area, and equally cannot provide any guarantee against material errors, loss or fraud. 
2.10 Appendix A contains the internal audit plan for quarters one and two of 2026/27. The
plan will be added to throughout the year, with a list of potential audit areas provided
at Appendix B.  Audit titles and high-level scopes are indicative at this stage for
planning our resources.  At the start of each audit, detailed planning will be carried out
to agree the objectives and the scope of the work.  The plan will therefore be subject
to change throughout the year, depending on several factors such as available
resources, time required to complete reviews, and unplanned work arising throughout
the year. 
2.11 The Senior Manager is required to ensure that internal audit resources are
appropriate, sufficient and effectively deployed to achieve the approved plan. The
Internal Audit Team currently comprises a Senior Manager, an Internal Audit Manager,
two Internal Auditors and a Computer Auditor.  All members of the team hold
professional accountancy or audit qualifications and are suitably experienced. 
2.12 In addition to the programme of audit work to be carried out, time is also required to be
set aside throughout 2026/27 to support the following areas: 
• Consultancy – both ad hoc advice and project work
• Follow up of prior year internal audit action points
• Staff training
• Audit planning and monitoring
• Committee attendance and reporting
• Development of the internal audit service
• Self-assessment on the new Global Internal Audit Standards
• Review of governance documents such as the Annual Governance Statement.

Page 4

OFFICIAL INFORMATION
OFFICIAL INFORMATION 
Conformance with the Global Internal Audit Standards (GIAS) 
2.13 The Global Internal Audit Standards came into effect in April 2025, replacing the
Public Sector Internal Audit Standards (PSIAS).  The Senior Manager will complete a
self-assessment against the new standards, the results of which will be included within
the annual audit report.   
2.14 The outcome of this self-assessment may identify areas where changes to internal
audit processes or procedures are required.  Any such changes will be captured within
a formal action plan with clearly defined timescales for implementation. 
2.15 Completion of this self-assessment will also form a key element of preparation for the
External Quality Assessment (EQA) of the internal audit function, which is scheduled
to be undertaken in 2027.  The most recent EQA was carried out in 2022 under the
now superseded PSIAS and concluded that the internal audit service was fully or
generally conformant with all 14 standards.  This provides a strong foundation from
which the service can move towards full conformance with the Global Internal Audit
Standards. 
2.16 Similar to PSIAS, the GIAS require the Senior Manager to develop and maintain a
quality assurance and improvement programme (QAIP).  The planned self-
assessment due will provide a key foundation for this programme, alongside the EQA
planned for in 2027. 
Internal Audit Performance 
2.17 As part of the progress reporting regime, we will report on internal audit performance.
The following targets will be used to measure the performance of the internal audit
activity 
Performance Measure Performance Target
Delivery of internal audit plan – percentage completed
at year end
>85%
Quality of audit work – overall client satisfaction >90%
Outcomes from audit work – value to the organisation >90% 
2.18 The Internal Audit Charter is a formal document which defines the internal audit
activity’s purpose, authority and position.  The Senior Manager reviews the Internal
Audit Charter on an annual basis and presents any changes to the Audit and Scrutiny
Committee for approval. In March 2025, the Audit & Scrutiny Committee approved the
changes to the Internal Charter to ensure alignment with the requirements of the
GIAS. 
3. Proposals 
3.1 It is proposed that the Committee approves the Internal Audit plan for 2026/27.

Page 5

OFFICIAL INFORMATION
OFFICIAL INFORMATION
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of Internal Audit helps to support the efficient delivery of the strategic
priorities within the Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Consultation has taken place on an individual basis with the Executive Leadership
Team during the preparation of the Internal Audit plan. 
Mark Boyd
Head of Service (Finance)

Page 6

OFFICIAL INFORMATION
OFFICIAL INFORMATION
For further information please contact Paul Brown, Senior Manager (Audit, Fraud,
Safety, Risk and Insurance), on paulbrown1@north-ayrshire.gov.uk. 
Background Papers
None.

Page 7

OFFICIAL INFORMATION
OFFICIAL INFORMATION
Internal Audit Plan 2026/27 Quarters 1 & 2     Appendix A      
Audit Area to Deliver in Plan Directorate/Service Planned
Quarter Priority Link to Council Plan Link to Risk Registers
Grants Compliance Communities & Housing Q1 B Communities and Local Democracy – we will
have active, inclusive and resilient communities Operational Risk
General Ledger Finance Q2 B n/a n/a
Accounts Payable Transactions People & ICT Q2 A
A Sustainable Council – a Community Wealth
Building Council that is efficient and accessible,
maximising investment and focusing resources
towards our priorities
n/a
ICT – Incident Detection People & ICT Q1 B
A Sustainable Council – a Community Wealth
Building Council that is efficient and accessible,
maximising investment and focusing resources
towards our priorities
Strategic Risk
School Inventory Management Education Q1 B
A Sustainable Council – a Community Wealth
Building Council that is efficient and accessible,
maximising investment and focusing resources
towards our priorities
n/a
Neighbourhood Services – Overtime Place Q1 B
Wellbeing – to transition to a wellbeing
economy, delivering prosperity, wellbeing and
resilience for local people
Operational Risk
Absence Management (specifically
EDU/HSCP) People & ICT Q2 A
Wellbeing – to transition to a wellbeing
economy, delivering prosperity, wellbeing and
resilience for local people
n/a
Headstone Inspections Place Q1 B
Wellbeing – to transition to a wellbeing
economy, delivering prosperity, wellbeing and
resilience for local people
n/a
Business Continuity Planning HSCP Q2 B
Wellbeing – to transition to a wellbeing
economy, delivering prosperity, wellbeing and
resilience for local people
Corporate/Operational
Risk
Tenants and Residents Associations Communities & Housing Ongoing D Communities and Local Democracy – we will
have active, inclusive and resilient communities n/a

Page 8

OFFICIAL INFORMATION
OFFICIAL INFORMATION 
Rolling Internal Audit Plan    Appendix B     
These reviews will form part of the rolling plan for 2026/27. The plan will continue to be adjusted as the year progresses to reflect current organisational risks and issues.
Ongoing risk assessments will be undertaken to determine the priority areas to include in the plan.
Potential Future Audit Areas Directorate/Service Priority Link to Council Plan Link to Risk
Registers
Corporate - Performance All B All N/A
Corporate - Business Continuity
Planning
All C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
Corporate Risk
and Operational
Risk
Stores Controls Communities &
Housing
C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
Community Associations Communities &
Housing
B Communities and Local Democracy – we will have active, inclusive
and resilient communities
Operational Risk
ALEO Arrangements Communities &
Housing
C Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Void Management (27/28 onwards) Communities &
Housing
C Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
Operational Risk
Trading Standards Communities &
Housing
D Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Dampness & Mould Communities &
Housing
A Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Housing Repairs (27/28 onwards) Communities &
Housing / Place
C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
Tenant Safety (fire/gas) Communities &
Housing / Place
B Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Freedom of Information/Subject Access
Requests (27/28 onwards)
Democratic A A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
Corporate and
Operational Risk
Residential Placements Education B Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
Operational Risk
Education - Handling of Medication Education B Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A

Page 9

OFFICIAL INFORMATION
OFFICIAL INFORMATION
Management of Allergens in Schools Education B Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
Operational Risk
School Roll Forecasting Education C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
Facilities Management Timesheet
Processes
Education C N/A N/A
Placement Requests  Education C Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
Operational Risk
Community Based Support - Young
People
HSCP B Communities and Local Democracy – we will have active, inclusive
and resilient communities
Operational Risk
Financial Assessments - non-
residential
HSCP C Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Commissioning – including supplier
failure
HSCP B A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
Strategic Risk
Review of HSCP Charging Policy HSCP C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
Operational Risk 
Implementation of new Social Work
System
HSCP B Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Transitioning Arrangements (27/28
onwards)
HSCP C Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Coming Home Agenda (27/28 onwards) HSCP C Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Integration Joint Board Audit Days IJB A N/A N/A
Payroll Transaction Testing People & ICT A A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
Agency Staff & Workers (IR35) People & ICT B A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
ICT – Network Security People & ICT B A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
Strategic Risk
Council Tax – Second Homes Finance/People &ICT C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A

Page 10

OFFICIAL INFORMATION
OFFICIAL INFORMATION
Contract Management/Monitoring Finance C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
Artificial Intelligence & Governance   All C A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
Fuel Controls Place B A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
N/A
Sustainability Climate Change (27/28
onwards)
Place B Climate Change – achieving net-zero by 2030 Strategic Risk and
Operational Risk
Waste Management – Special Uplifts Place C Climate Change – achieving net-zero by 2030 Operational Risk
Playpark/Tree Management/Street
Furniture Inspection Arrangements
Place B Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
N/A
Deposit Return Scheme (27/28
onwards)
Place C Climate Change – achieving net-zero by 2030 Operational Risk
Assets – Property Lifecycle Investment
(27/28 onwards)
Place B A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
Strategic &
Operational Risk
Ayrshire Growth Deal Place A A Sustainable Council – a Community Wealth Building Council that
is efficient and accessible, maximising investment and focusing
resources towards our priorities
Operational Risk
Fire Safety Risk Management Place A Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
Operational Risk
Local Growth Fund (27/28 onwards) Place C Wellbeing – to transition to a wellbeing economy, delivering
prosperity, wellbeing and resilience for local people
Operational Risk