NORTH AYRSHIRE COUNCIL 
20 November 2025 
Audit and Scrutiny Committee 
Title:    Internal Audit and Corporate Fraud Action Plans:
Quarter 2 Update 
Purpose:  To advise the Audit and Scrutiny Committee on the
progress made by Council Services in implementing the
agreed actions from Internal Audit and Corporate Fraud
reports as at 30 September 2025. 
Recommendation:  That the Committee notes the current position with the
implementation of Internal Audit and Corporate Fraud
actions. 
1. Executive Summary 
1.1 The CIPFA document 'Audit Committee Principles in Local Authorities in
Scotland' highlights that Audit Committees should monitor and review the
progress made in implementing audit recommendations. 
1.2 Service managers are responsible for ensuring that agreed actions arising from
Internal Audit and Corporate Fraud reviews are implemented. This provides
assurance that identified control weaknesses have been addressed and are
being managed effectively. 
1.3 All actions are monitored on the Pentana system and service managers are
responsible for updating Pentana as they progress each action. This enables
Internal Audit to monitor progress on a 'real-time' basis and address any delays
in implementation. 
1.4 This report details the position as at 30 September 2025. 
2. Background 
2.1 The last report to the Audit and Scrutiny Committee on 28 August 2025
highlighted that there were 14 actions outstanding at the end of June 2025 and
all but one actions had not yet passed their due date. 
2.2 In addition to these 14 carried forward actions, there have been 19 new actions
agreed, giving a total of 33 action points for review. 
2.3 Services have completed 26 actions since the last report. All Council Services
are required to retain evidence of work carried out in completing their actions

Page 2

2
and Internal Audit carries out 'spot-checks' on a sample of completed actions
on an ongoing basis. 
2.4 Of the remaining 7 actions, 3 were only partially completed as at 30 September
2025 and the remaining 4 actions were not due for completion until after that
date. 
2.5 Appendix 1 to this report provides the Committee with full details of the 3
actions that were not completed within the agreed timescales. 
3. Proposals 
3.1 It is proposed that the Committee (a) notes the current position with the
implementation of Internal Audit and Corporate Fraud actions; and (b) challenges
those Services that have not implemented actions within the previously agreed
timescales. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The effective implementation of agreed Internal Audit and Corporate Fraud
actions helps to support the efficient delivery of the strategic priorities within the
Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA)

Page 3

3
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Council Services are consulted during the completion of each Internal Audit and
Corporate Fraud review and have also provided updates on progress made in
implementing action points. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Anne-Marie Fenton, Interim Senior Manager
(Internal Audit), on afenton@north-ayrshire.gov.uk. 
Background Papers
None.

Page 4

4
Appendix 1 - Actions due by 30 September 2025 but not started or partially completed
Code IA2025PA005b Description
Action Description:
Management should investigate the feasibility of streamlining the end-to-end process
as part of the transition to Eclipse to minimise the number of instances where data
input is required, where possible.
In the meantime, management should ensure that the access database (DB) is
restricted to a limited number of authorised users only and that the DB is suitably
protected (e.g. by way of strong password) until such time as the new system has
been implemented.  
Finding:
The admin team currently update the budget monitoring spreadsheet, an operational
access database and the CareFirst system at each stage of the process for all
Council tenant jobs.  All serve a different purpose. This is very time consuming for
staff and increases the risk of keying errors being made.  In addition, the access
database is not supported by IT Services.  
Risk:
Inefficient use of staff time and increased risk of keying errors.
Priority 2 Latest Note
Current trial of reporting via Eclipse with a view to eliminating the need for the Access
Database from process.  Target date for removal of Access Database 30th November
2025. 
This action will streamline and remove the requirement for admin duplicate
information across platforms.  The spreadsheet and Eclipse data input will remain.
Progress Bar  Original Due Date 30-Sep-2025 Due Date 30-Sep-2025
Parent Code & Title IA2025PA005 Aids and Adaptations
Managed By
Head of Service (Housing &
Public Protection); AHP
Senior Manager &
Professional Lead 
Assigned To Team Manager (Housing);
Team Manager OT

Page 5

5
Code IA2025PA010a Description
Audit Action: The revised Terms of Reference should be presented to the
Transformation Board for approval. 
Audit Finding: It was noted that the Terms of Reference stated that action notes
from the Board meetings would be shared at each IJB via the Director’s report, but
this has not been done in practice, at the request of the IJB. However, the IJB have
received 6-monthly updates on the progress of the Transformation Plan. The Senior
Manager (Strategic Planning and Transformation) prepared a revised Terms of
Reference to reflect the reporting arrangements to be presented to the
Transformation Board in July 2025. 
Risk: The arrangements for reporting the progress against the Transformation Plan
to the IJB are not compliant with the Terms of Reference of the Transformation
Board.  
Priority 3 Latest Note
The next meeting of the Transformation Board is scheduled to take place on the 5th
December 2025 (3pm). The Terms of Reference will be addressed at this meeting
due to the scheduled meeting for the 22nd of October 2025 being cancelled. 
Progress Bar  Original Due Date 20-Aug-2025 Due Date 20-Aug-2025
Parent Code & Title IA2025PA010 IJB Transformation Managed By Director of Health & Social
Care
Assigned To Chief Social Work Officer

Page 6

6
Code IA2025SI003a Description
Action description: Review the SHR guidance and audit recommendations to
ensure Data Dictionaries are fully completed and issued to appropriate staff prior to
24/25 SHR ARC return being completed. This will ensure consistency in data
collection from year to year. Data Dictionaries should also make reference to what
evidence is required to be kept, which format is used to present it and where this
should be centrally filed. 
Audit finding: No formal internal procedure notes are in place to ensure that
Regulator guidance is followed and updated as required for the period tested -
23/24. Incomplete Data Dictionaries have been provided and are intended for use
for 24/25, however there are currently in draft form. It was also noted that some staff
responsible for collating the data for the ARC were not aware of the Data
Dictionaries. 
Risk: Inaccurate reporting to ARC as required by SHR, due to inconsistent data
collection. Lack of consistency reduces comparability of PIs and therefore
usefulness for management decision-making. Lack of clear instructions for new staff
if those who currently prepare the PIs are unavailable in the future.  
Priority 1 Latest Note
Work has taken place on the ARC indicators to gather the data on a monthly basis. 
The Business Improvement Team are currently working on the new reports which
will form part of the data dictionaries.  This will allow teams to understand where the
data is being pulled from and the inclusions, exclusions set out by the Scottish
Housing Regulator. 
Work will be done to complete a 6 month return, which will enable the data
dictionaries to be completed.  The work will be completed by the 31st October 2025.
Progress Bar  Original Due Date 30-Sep-2025 Due Date 30-Sep-2025
Parent Code & Title IA2025SI003 Housing Indicators
Managed By Head of Service (Housing
& Public Protection);
Assigned To Team Manager
(Performance)