NORTH AYRSHIRE COUNCIL 
23rd September 2025   
Audit and Scrutiny Committee 
Title:    Our Council Plan Year End Progress Reporting including
LGBF Analysis 
Purpose:  To consider and approve Our Council Plan Year End
Reporting including LGBF Analysis 
Recommendation:  The Audit and Scrutiny Committee agrees to: 
(i) Consider progress within the LGBF Report as at June
2025 (Appendix 1). 
(ii) Consider Our Council Plan Six Monthly Progress Report
1 October to 31 March 2025 (Appendix 2).
(iii) Consider Our Council Plan Annual Performance Report
(Appendix 3).
(iv) Note Cabinet approval relates to the content of the
report, not the layout or media used to ensure future
flexibility for production of accessible format reports. 
1 Executive Summary 
1.1 Our Council Plan 2023-28 is the overarching strategy of our council and details
our council’s strategic priorities.  We have a statutory duty to publish information
that enables effective scrutiny of our performance.
1.2 This report presents the progress made in delivering Our Council Plan 2023-
2028 as at Year-End 2024-2025. As a result, this report combines three key
Council Plan and corporate performance reports: 
• The Local Government Benchmarking Framework (LGBF) - Analysis of June
2025 Data Release. (Appendix 1)
• Our six-monthly Council Plan 2023-28 Progress Update, Year End 2024/25
(Appendix 2)
• Our Annual Performance Report 2024/25 (Appendix 3) 
1.3 As a continuation of the approach at Mid-Year and following Best Value Thematic
Audit recommendations, the report includes further details on:

Page 2

• Transformation workstreams.
• Workforce Planning. 
1.4 To adhere to the Statutory Performance Information Direction 2024 Cabinet
agreed to note that approval of the report is considered as approval of the content
of the PDF report.  The report formatting may be changed following Cabinet
approval to enable publication in more accessible formats such as html on our
website and other media.  In addition, summaries may be produced for easy read
and child friendly versions as appropriate.
1.5 Following Cabinet approval, our corporate performance reports are published on
our website www.north-ayrshire.gov.uk/performance.
2 Background 
2.1 Under the Local Government (Scotland) Act 1992 and Local Government in
Scotland Act 2003 we have a duty to demonstrate Best Value.  To ensure we
support our residents, fulfil our statutory duties and invite scrutiny, we actively
manage performance and develop our reporting to make it accessible and
engaging.
2.2 How we demonstrate our performance is defined in the Statutory Performance
Information (SPI) Direction 2021 for up to year ending 31 March 2025.  The
Statutory Performance Information Direction 2024 takes effect on reporting of
activity that takes place from 1st April 2025 for reporting year 2025-26 for
approximately three years.  Though outside the scope of Direction 2024,
elements from it have been considered within this report.
2.3 One key area for consideration is the need to ensure our reports are both
“technically accessible” and “non-technically accessible”.  The Direction
Guidance refers to “technically accessible” as adhering to accessibility
regulations including the use of language, layout of the report, contrast and use
of image alternative text.  “Non-technically accessible” refers to ensuring our
performance is easily understood and engaging, such as the magazine style
used for our six-monthly reports.  To adapt our reporting effectively to adhere to
our statutory obligations and explore the use of html, easy read and child friendly
versions while ensuring effective governance, Cabinet agreed to note that
approval of the report is considered as being for the content of the PDF reports
and that specific wording, layout, format or media used may be adapted to make
it suitable for other audiences, such as our young people under the UNCRC
(Incorporation) (Scotland) Act 2024, while keeping our performance fully
transparent.
2.4 We have embedded key contextual indicators from the Wellbeing Economy
Dashboard - which outlines our council’s Wellbeing Economy journey. We will
continue to work with the Economic Policy Team to further embed this approach
as the new Wellbeing Economy Dashboard becomes established.

Page 3

3 Assessment of Performance 
Performance Indicators
3.1 There are 26 performance indicators within our framework. As at Year End, 18
(75%) of our indicators where the status is known are either on target or just
slightly adrift of target and 6 (25%) are significantly adrift of target.  A comparison
to our position at the same period last year is shown below when 88.9% of
indicators were on or slightly adrift of target.
Status Year End 2023/24 Year End 2024/25
On Target (Green) 14 (77.8%*) 13 (54.2%*)
Slightly Adrift of Target
(Amber) 2 (11.1%*) 5 (20.8%*)
Significantly Adrift of
Target (Red) 2 (11.1%*) 6 (25%*)
Data Only / Status
Unknown 8 2
(* Of PIs where status is known)
3.2 The status of a PI is determined by the following tolerances:
Status Description 
On target 
Slightly adrift of target (typically this represents a variance ≥ 1% and < 5% from the
target). 
Significantly adrift of target (typically this represents a variance ≥ 5% from the target). 
Data only (PIs only) – this is where a target has intentionally not been set, usually due
to the indicator being a new indicator or where we can only partly contribute to the
outcome. 
Data not available / status unknown - (PIs only) the status is not available either due to
data not being available or no target being set.
(Source:  Our Performance Management Strategy 2023/2028)
3.3 Of the eight PIs where the status was either data only (target intentionally not
set) or status unknown at year end in 2023/24, their status was finalised in this
reporting period as three red, one amber and four green.  The three red and one
amber relate to CP37 (average total tariff score of pupils living in SIMD 20% most
deprived areas), CP_06 (average tariff score, all leavers), CP_38 (average total
tariff for care experienced young people) and CP_04 (proportion of children
meeting developmental milestones) respectively.

Page 4

3.4 For these PIs, the status was set to data only (i.e. target intentionally not set) for
2022/23, and stretch targets were set for several for 2023/24 (see paragraph
3.35 below).  The most recent data relates to 2023/24 academic years and has
been released recently.  As a result, these statuses are reported for the first time
within this year end 2024/25 progress report.
3.5 Though this position makes it difficult to determine conclusively whether our
overall performance status based on PIs has improved during the year, the
individual PI progress is detailed below and despite being adrift of target, shows
consistent progress in many areas.
3.6 Context for the PIs adrift of target and not previously reported in our performance
reporting are detailed in Appendix 2 and listed below:
3.7 CP_37 Average total tariff score of pupils living in SIMD 20% most deprived
areas (Red)
3.8 Actual is 664.3 against a target of 714 for 2023/24 (most recent data available). 
The average total tariff score gained from all qualifications by 2024 school
leavers from the 20% most deprived SIMD data zones has marginally decreased
from the previous year.  The endeavour to offer candidates a wider breadth of
learning experiences has included more courses (or units of courses) from a
wider vocational range of courses and awards that sometimes are graded at the
same SCQF level as National Qualifications courses but amass a smaller
number of tariff points in the Insight scale. However, these courses can provide
learners with a more suitable set of skills and knowledge to prepare them for
work, training or further education. 
3.9 Though this PI records the total tariff score for SIMD Quintile 1 of S4-6 pupils
who left school in 2023/24, the LGBF has a similar measure based on the cohort
of young people who would have reached the end of S6 in 2023/24, irrespective
of their leaving year.  For the same period, 2023/24, the equivalent LGBF
measure shows a total tariff score of 685, above both the family group average
of 660 and the Scottish average of 658 and leading to our council being ranked
6th in Scotland. 
3.10 CP_06 Average tariff score: All Leavers (Red)
3.11 Actual is 840.8 against a target of 908 for 2023/24 (most recent data available). 
The average total tariff score gained from all qualifications by school leavers has
marginally decreased from the previous year but is in line with pre-pandemic as
well as recent years’ performance. The 2019/2020 and 2020/2021 results are not
comparable with other academic years, as SQA has employed the Alternative
Certification Model (ACM) instead of exam-based evaluation for awarding
qualifications at SCQF level 5 and above. Advice provided by Scottish
Government colleagues emphasises direct comparison to alternative certification
years should not be made without further evidence and the impact of these
approaches. For all SIMD deciles except SIMD 10 (for which we have a very low
number of learners), we continue to outperform national figures. 
3.12 Though this PI records the total tariff score of S4-6 pupils who left school in
2023/24, the LGBF has a similar measure based on the cohort of young people
who would have reached the end of S6 in 2023/24, irrespective of their leaving

Page 5

year.  For the same period, 2023/24, this measure shows a total tariff score of
845, above the family group average of 829 but below the Scottish average of
917 and ranked 26th in Scotland. 
3.13 Closer examination of the LGBF highlights the strong influence that deprivation
has on this indicator. When disaggregated by SIMD quintile, our council
outperforms both the national figures and the family group for each of SIMD
quintiles 1 to 4 and also outperforms the family group for SIMD quintile 5. Despite
this strong performance, we know it is important to maintain our holistic, cross-
service commitment to our Wellbeing priority in order to reflect this at an absolute
level. 
3.14 CP_38 Average total tariff for care experienced Young People (Red)
3.15 Actual is 355 against a target of 465.  The average total tariff score (ATTS)
achieved by North Ayrshire care experienced leavers was lower in 2023/2024,
at 355 tariff points, than the general trend over the last five years. A slightly higher
proportion than average of care experienced learners left before the end of S6 in
2023/2024, which has contributed in part to the lower average total tariff score. 
3.16 Schools have analysed the data locally and have a clear narrative for individual
circumstances. The service will continue to focus on improving this benchmark
of achievement for care experienced learners.  Attainment of care experienced
learners is specifically referenced within the Education Service Plan. Quality
Improvement visits and attainment discussions with senior school leaders will
include a focus on the attainment and achievement of this group of learners to
ensure consistency of delivery of interventions with a positive impact.
3.17 CP_40 Number of new build housing units reaching completion (all
tenures) (actual not cumulative) (Red)
3.18 Actual 371 against a target of 396.  We achieved our target for 2024/2025 with
regards to new build social housing and have limited influence over the delivery
of new build housing constructed by private housing developers to meet the total
396 homes target. The 25 new homes unable to be delivered during 2024/2025
were across a number of sites throughout North Ayrshire. We exceeded our
target for bringing empty homes back into use and intend to review this
performance indicator and continue to focus on improving performance in the
forthcoming year. (This indicator is linked to action CP_10 detailed below).
3.19 CP_30 Total installed capacity of low carbon heat and electricity generation
across the council's estate (Red)
3.20 Actual is 17,630 against a target of 28,499.  Our council had aimed to have both
solar PV farms energised in December 2024, however this has not been possible
due to extended development time required by the Distribution Network
Operator.  The solar farms have been built and are due to be commissioned in
the summer.  
3.21 CP_31 % of total household waste that is recycled (calendar year as per
SEPA) (LGBF) (Red)
3.22 Actual is 52.8% against a target of 56%.  The provisional household waste
recycling figure for the calendar year 2024 is 52.8%, subject to verification by
SEPA. This has reduced since 2023 as a result of the introduction of the new

Page 6

SEPA guidance regarding the requirement for Waste Upholstered Domestic
Seating (WUDS) to only be sent for incineration, which has negatively affected
the amount of bulky waste that can be recycled (this affects all councils).  In
addition, more wood is being deposited at recycling centres suitable only for
biomass recovery rather than recycling. 
3.23 For context, LGBF benchmarking information for 2023/24 (2023 calendar year)
released in June showed we were ranked third in Scotland.  Though our
provisional data shows a reduction for 2024/25, as the new SEPA guidance
affects all councils we will closely monitor our relative position when comparative
data is released over the coming months.
3.24 CP_04 Proportion of children meeting developmental milestones (LGBF)
(Amber)
3.25 Actual is 77.5% against a target of 79% for 2023/24 (most recent data available). 
At the most recent data release for data for 2023/2024, the proportion of children
meeting developmental milestones is 77.50%, slightly below the target of 79%. 
We are working to ensure there is more robust data gathering and analysis within
Early Years and are moving towards using CfE levels with inbuilt milestones. 
This will help improve accuracy and consistency of data as well as improved
progression pathways to primary.  Roles and remits for Excellence and Equality
Leads (EELs) developed this academic session will support this work.
3.26 The challenges we are experiencing in North Ayrshire are reflected in the LGBF
comparisons with other local authorities.  We are below the family group average
of 79.8% and the Scottish Average of 83.3%. As a result we are currently ranked
31 out of the 32 local authorities for our children meeting developmental
milestones. This is an area that we know will need specific focus within wider
principles of prevention and early intervention, including through the
Collaboration for Health Equity in Scotland. 
3.27 CP_28 Hectares of vacant and derelict land in North Ayrshire (Amber)
3.28 Actual is 942ha against a target of 925ha.  The majority of vacant and derelict
land sites are within private ownership, therefore their condition or development
timescales to inform if they are added or removed from the register is out with
the control of our council. However, we utilise the Repurposing Property Grant
Fund to help support landowners and community groups to bring back vacant
land and properties to use. Furthermore, in 2024/2025, several of the key
external regeneration funds which support the redevelopment of such land,
including the national Vacant and Derelict Land Investment Programme, were
paused which reduced the potential to regenerate sites.  Funding has now been
confirmed and works will commence in 2025/2026.
3.29 CP_43 Number of council assets under community management
(cumulative) (Amber)
3.30 Actual is 55 against a target of 56.  One Community Asset Transfer was delayed
until Q1 2025 due to some minor administrative issues within the community
group which took longer to resolve than expected. We continue to publicise the
range of offers available for management and ownership of assets to our
community groups and are currently engaged with around 30 groups at various
stages of the CAT process.

Page 7

3.31 CP_29 Overall carbon emissions (tonnes) (Non-domestic council estate)
(Amber) 
3.32 Actual is 20,333tCO2e against a target of 19,953tCO2e.  This figure is an
estimate and will be confirmed at the next data release.  Though slightly adrift of
target the overall trend is a steady decrease in emissions.  
3.33 CP_25 % of Council dwellings that meet the Scottish Housing Quality
Standard (LGBF) (Amber)
3.34 Actual is 94% against a target of 97.4%.  The target of 97.4% was set as part of
last year’s ARC completion. This pass rate is based on a combination of many
different compliance criteria for each individual property, including EICR
(Electrical Installation Condition Report). When the 97.4% compliance target was
set, it was based on 100% compliance regarding the EICR element; however
with issues accessing properties, we were unable to achieve this (the EICR
compliance outturn figure for 2024/25 was 97.71)%) which has resulted in the
slightly lower overall SHQS compliance of 94% against the 97.4% target.
3.35 Education Performance Targets
3.36 As mentioned above several of the education targets are linked directly to the
stretch aims previously agreed with the Scottish Government and show figures
that are significantly above the attainment levels achieved during the Covid
period when the Alternative Certification Model was deployed. 
3.37 It is not recommended to draw comparison between these periods. Therefor
while we recognise the merits of being aspirational and are committed to
delivering ongoing improvement over time, we believe it would be sensible to
reconsider the level of these targets to align them more closely to performance
in the post-Covid period. This is something we intend to do through appropriate
engagement and as part of the process of developing the next three-year service
plan due in 2026.  Cabinet approval will be sought through the new Education
Service Plan in 2026 or Council Plan Progress Reporting as appropriate.
Actions
One action is currently adrift of target:
3.38 CP10 Increase the number of homes in the area through a mix of private
and social developments and bringing empty buildings back into use
(Wellbeing Priority). (Amber)
3.39 This action is linked to the indicator “CP_40 Number of new build housing units
reaching completion (all tenures) (actual not cumulative)” which is currently
significantly adrift of target (red) (see above).  We achieved our target for
2024/2025 for new build social housing and we have limited influence over the
delivery of new build housing constructed by private housing developers. The 25
new homes unable to be delivered during 2024/2025 were across a number of
sites throughout North Ayrshire. We exceeded our target for bringing empty
homes back into use and intend to focus on improving performance in the
forthcoming year.

Page 8

Local Government Benchmarking Framework
3.40 LGBF performance is viewed in short, medium or long-term trends in terms of
our actual performance as well as our position relative to other councils.  In
addition, the range of indicators contains those directly reflecting council
performance, those where performance is weighted by our demographics (per
10,000 population for example) or contextual (Gross Value Added and area wide
CO2 emissions) to reflect our operating environment.  This complex landscape
means it is difficult to summarise effectively across all 33 priority indicators within
this covering report.  Some key messages are noted below, however it is
demonstrated more fully in the tables from page 4 of Appendix 1.  
3.41 As at June 2025, 17 of our 33 priority indicators were in the top two quartiles.
Top quartile performance includes areas such as proportion of the highest paid
5% of employees who are women, gender pay gap, percentage of invoices
sampled that were paid within 30 days, proportion of total household waste
arising that is recycled, percentage of operational buildings that are suitable for
their current use and town vacancy rates. 
3.42 In the short term (most recent one year period available), 23 of our 33 priority
indicators have shown improvement in performance, whereas ten have
demonstrated a reduction in performance.  In terms of improvement, data shows
our council’s commitment to investment in the road infrastructure is displaying
positive impacts with an improving Road Condition Index across all
classifications.
3.43 In comparison with other councils, eight indicators have improved their quartile,
19 have maintained quartile (nine remaining in the top two quartiles and six in
the 4th quartile) and six have declined.
3.44 The information contained within the LGBF is being used to inform delivery
across our services.
3.45 Key Highlights
• Recent statistics published by the End Child Poverty Coalition showed that child
poverty within North Ayrshire decreased from 29.2% in 2022/23 to 24.3% in
2023/24. This reduction of 4.9 percentage points was the largest in Scotland over
this time period.
• Following a competitive application process, we have been selected as one of
three places to engage in the Collaboration for Health Equity in Scotland (CHES)
programme. Over the next two years, we will work in partnership with Public
Health Scotland and the Institute for Health Equity to reduce health inequity in
North Ayrshire through improving the conditions people live and work in. The
ultimate goal is to enable people to live longer, healthier lives by addressing the
root causes of health inequalities and preventing illness before it starts.
• During 2024/2025, our Money Matters team received 5,842 referrals and secured
£21.5 million in financial gains through income maximisation for service users.
• Our council was successful in becoming one of Scotland’s Fairer Future
Partnerships (FFP).  This £350,000 investment enabled our new Child Poverty
Strategy Team (CPST) to be established in January. It will work with partners to

Page 9

test ways of mitigating poverty, through addressing the specific needs of our
communities. In preparation, the team has appointed the Centre of Excellence for
Children’s Care and Protection (CELCIS) as a learning partner
• We published our new Participation Strategy which will focus on raising
awareness of participation processes including locality partnerships and enhance
our budget consultation. 
• Locality Plans were approved at Locality Partnership meetings in September. 
• We have expanded our capacity to support Community Asset Transfers (CATs)
through engaging with our Active Schools team. Our Community Asset Transfer
Team has received 17 expressions of interest during 2024/2025, with 56 council
assets under community management to date.
• Our Financial Inclusion Partnership is developing a communications plan to help
promote services to island residents, our gypsy traveller community, those who
are digitally excluded and residents with disabilities.
• Installation of our council’s two new solar photovoltaic (PV) farms is now
complete with the next phase being the connection to the electricity network and
commissioning works. They are expected to generate £400,000 of revenue per
year over 25 years as well as reduce our carbon footprint.
• 15 households on Cumbrae and 25 in Kilwinning have been identified for
improvements via the Energy Efficient Scotland: Area Based Scheme. This will
help address the impact of energy costs and address fuel poverty. 
• A £17.4m award from the Levelling Up Fund Round 3 was secured from the UK
Government.  This will support Levelling Up for Ayrshire, Commercial and Low
Carbon Infrastructure.
• Cabinet approved the proposal to vacate Bridgegate House in Irvine and consider
future uses as part of the Irvine town centre regeneration work and establishment
of the Irvine Town Board.
• Our most recent Best Value Thematic Audit focusing on Workforce Innovation
was positive, showing how our council is responding to current challenges by
building capacity, increasing productivity and innovation.
• Our Transformation Programme continues to progress, with key milestones
reached within the Digital Workstream, Irvine Property Review as well as the
Nethermains and Shewalton Solar PV Farm detailed above.
• The Transformation Board is overseeing service reviews across the Learning
Resource; Housing Service; Financial Inclusion Services; External Residential
Placements; Economic Development, Growth and Regeneration; and Waste
Services.
• The Irvine Locality Review is progressing to align our operational property estate
to complement modern ways of working.   To date we have:
o Relocated Genealogy from Irvine Townhouse to Irvine Library resulting in
increased footfall. 
o Relocated 255 colleagues to Cunninghame House. 
o Relocated the Eglington Trophy to the Heritage Centre. 
o Approved a £300,000 investment in a Community Wealth Building Initiative to
support the exploration of a wellbeing enterprise hub at the current
Greenwood Conference Centre site.

Page 10

3.46 Key Next Steps
We will:
• Through our new Child Poverty Strategy Team – and liaising through the CPP
and CPP Senior Officers Group - continue to bring a more systematic approach
to addressing child poverty in North Ayrshire. This will include the co-design of
mitigations based on the needs of our communities with partners from the third
sector.
• Establish our local priorities and areas for action as part of the Collaboration for
Health Equity in Scotland programme. 
• Consolidate our financial inclusion services and rebrand as “Money Smart”.
• Reach Financial Close on the new state-of-the-art Ardrossan Community
Campus and start the construction process. 
• Review research commissioned by our council into the potential options for
developing Community Wealth Building approaches at a locality level including
consideration of unique island contexts.  
• Explore a debt advice resource for non-council tenants to enable a seamless
internal pathway to debt advice.
• Make progress on the priorities identified through the Community Asset Transfer
Start-up Fund review.
• Complete our comprehensive approach to application, assessment, award and
compliance in relation to community funds and grants.
• Continue to work with the Third Sector Chief Officers Group to codesign solutions
to develop our strategic understanding and the sector’s capacity. These projects
focus on two areas which our council has earmarked funds to support, Child
Poverty and the Cost of Living as well as developing our Community Wealth
Building aims within our communities. 
• Launch our new digital Household Waste Recycling Centre booking system.
• Continue to develop Community Climate Action Plans for our six localities. 
• Continue to develop a Renewable Energy Strategy and identify projects which
may be suitable for investment.
• Deliver the North Ayrshire Network Strategy, aligned with the Scottish
Government’s Biodiversity Strategy.
• Continue to progress recommendations arising from the Audit Scotland Best
Value Thematic Work.
• Continue to progress property rationalisation.
• Commence preparations for our budget engagement for 2026 to 2027.
• Continue to carry out essential works at both Nethermains and Shewalton Solar
PV Farms.

Page 11

4 Proposals 
4.1 Cabinet agrees to: 
The Audit and Scrutiny Committee agrees to: 
i. Consider progress within the LGBF Report as at June 2025 (Appendix 1). 
ii. Consider Our Council Plan Six Monthly Progress Report 1 October to 31
March 2025 (Appendix 2).
iii. Consider Our Council Plan Annual Performance Report (Appendix 3).
iv. Note Cabinet approval relates to the content of the report, not the layout or
media used to ensure future flexibility for production of accessible format
reports. 
5 Implications/Socio-economic Duty
Financial
5.1 There are no financial implications arising from this report.
Human Resources
5.2 There are no human resource implications arising from this report.
Legal
5.3 There are no legal implications arising from this report.
Equality/Socio-economic
5.4 There are no equality/socio-economic implications arising from this report.
Climate Change and Carbon
5.5 There are no climate change and carbon implications arising from this report.
Key Priorities
5.6 The Progress Report enables the effective scrutiny of the delivery of our Council
Plan strategic priorities.
Community Wealth Building
5.7 There are no Community Wealth Building implications arising from this report.
Islands Communities Impact Assessment (ICIA)
5.8 There are no island communities implications arising from this report.
United Nations Rights of the Child (UNCRC)
5.9 The Audit and Scrutiny Committee is asked to note that the Cabinet approval of
the report relates to the content only, this enables us to explore child friendly
reporting in line with the UNCRC (Incorporation) (Scotland) Act 2024 while
ensuring effective governance.

Page 12

Consumer Duty
5.10 There are no consumer duty implications arising from this report.
6 Consultation
6.1 The Executive Leadership Team (ELT) and Cabinet reviewed and scrutinised the
report prior to submission to the Audit and Scrutiny Committee. 
Aileen Craig
Head of Service (Democratic)
For further information please contact Isla Cruickshanks, Senior Manager (Policy,
Performance and Democracy) on 01294 324035 or email IslaCruickshanks@north-
ayrshire.gov.uk.

Page 13

Local Government
Benchmarking Framework
Analysis of June 2025
Data Release
Appendix 1

Page 14

LGBF Analysis of June 2025 Data Release Page 1 of 32
Contents
Introduc�on ................................................................................................................................... 2
LGBF Priority Indicators .................................................................................................................. 3
People Services ........................................................................................................................................... 8
CHN11 – Proportion of pupils entering positive destinations .............................................................................. 11
CHN17 – Percentage of children meeting development milestones (27-30 month Review) ............................... 12
CHN24 – Proportion of Children Living in Poverty After Housing Costs ............................................................... 12
ECON1 – Percentage of Unemployed People Assisted into work from Council Programmes ............................. 13
ECON12a – Claimant Count as a percentage of working age population ............................................................. 14
ECON12b - Claimant Count as a percentage of 16-24 population........................................................................ 14
ECON7 – Proportion of people earning less than the living wage ........................................................................ 15
ECON9 – Town Vacancy Rates .............................................................................................................................. 16
ENV3c – Street Cleanliness Score ......................................................................................................................... 16
HSN1b – Gross Rent Arrears (All Tenants) as a Percentage of rent due for the year ........................................... 17
HSN3 – Proportion of Council dwellings meeting Scottish Housing Quality Standards ....................................... 17
HSN5a – Proportion of council dwellings that are energy efficient ..................................................................... 18
CORP7 – Percentage of income due from Council Tax received by the end of the year ...................................... 18
CORP9 – Percentage of Scottish Welfare Fund Crisis Grant decisions within one day ........................................ 19
CORP10 – Percentage of Scottish Welfare Fund Community Care Grant decisions in 15 days ........................... 19
Other Services ........................................................................................................................................... 20
CLIM1 – CO2 emissions area wide per capita ....................................................................................................... 24
CLIM2 – CO2 emissions area wide: emissions within scope of Local Authority per capita .................................. 24
CLIM3 -CO2 emissions from transport per 1000 population ................................................................................ 25
CLIM4 – CO2 emissions from electricity per 1000 population ............................................................................. 25
CLIM5 – CO2 emissions from natural gas per 1000 population ........................................................................... 26
ECON10 – Immediate available employment land as percentage of total land allocated for employment
purposes................................................................................................................................................................ 26
ECON11 – Gross value added (GVA) per capita .................................................................................................... 27
ECON5 – No of business gateway start–ups per 10,000 population .................................................................... 27
ECON4 – Proportion of procurement spent on local enterprises ......................................................................... 28
ENV4b - Percentage of A class roads considered for maintenance treatment .................................................... 30
ENV4c - Percentage of B class roads considered for maintenance treatment ..................................................... 30
ENV4d - Percentage of C class roads considered for maintenance treatment..................................................... 30
ENV4e - Percentage of unclassified roads considered for maintenance treatment ............................................ 30
ENV6 – Percentage of total household waste arising that is recycled ................................................................. 30
CORP3b – Percentage of the highest paid 5% of employees who are women .................................................... 31
CORP3c – Gender Pay Gap .................................................................................................................................... 31
CORP8 – Percentage of invoices sampled that were paid within 30 days ............................................................ 32
CORP-ASSET1 – Percentage of operational buildings that are suitable for their current use .............................. 32

Page 15

LGBF Analysis of June 2025 Data Release Page 2 of 32
Introduction
The Local Government Benchmarking Framework (LGBF) provides an opportunity to benchmark our
performance with other local authorities in Scotland. It is administered by the Improvement Service
in partnership with the Society of Local Authority Chief Executives (SOLACE) and highlighted within
the Accounts Commission’s Statutory Performance Information Direction 2021 which defines how
local authorities should demonstrate they are achieving Best Value for the people they serve. 
We have identified 33 indicators that closely link to the priorities within our Council Plan. Data for
these indicators is released in phases during the year. Areas such as CO2 emissions, Gross Value
Added and claimant count are included as priority indicators as they are monitored by our council to
reflect our operating environment, though we have limited influence on these areas directly. This
section demonstrates our relative performance for these indicators as at the June 2025 data release.
This information alongside the LGBF Dashboard enables us to learn from others to improve services
for our residents.
LGBF performance is viewed in short, medium or long-term trends in terms of our actual
performance as well as our position relative to other councils.  In addition, the range of indicators
contains those directly reflecting council performance, those where performance is weighted by our
demographics (per 10,000 population for example) or contextual (Gross Value Added and area wide
CO2 emissions) to reflect our operating environment.  This complex landscape means it is difficult to
summarise effectively across all 33 priority indicators within this introduction.  Some key messages
are noted below, however it is demonstrated more fully in the following pages.
As at June 2025, 17 of our 33 priority indicators are in the top two quartiles. Top quartile
performance includes areas such as proportion of the highest paid 5% of employees who are women,
percentage of invoices sampled that were paid within 30 days, proportion of total household waste
arising that is recycled, percentage of operational buildings that are suitable for their current use and
town vacancy rates.
In the short term (most recent one year period available), 23 of our 33 priority indicators have shown
improvement in performance, whereas ten have demonstrated a reduction in performance. Some of
the indicators which have improved are proportion of children living in poverty (after housing costs),
proportion of Scottish Welfare Fund (SWF) Community Care Grant decisions within 15 days and
street cleanliness score.  In terms of improvement, data shows our council’s commitment to
investment in the road infrastructure is displaying positive impacts with an improving Road Condition
Index across all classifications.
The following is a breakdown of the priority indicators within the context of family groups. Family
groups enable local authorities to make as close to a like for like comparison as possible with other
councils by grouping those with similar traits depending on the indicator. Grouping is based on levels
of deprivation (people services) or rurality (other services).  We align our LGBF analysis to the family
groups used within the LGBF Dashboard.  These are: 
Peoples Services (Deprivation)
• North Ayrshire Council
• Comhairle nan Eilean Siar
• Dundee City Council
• East Ayrshire Council
• North Lanarkshire Council
• Inverclyde Council
• West Dunbartonshire Council
• Glasgow City Council
Other Services (Rurality)
• North Ayrshire Council
• Perth and Kinross
• S�rling Council
• Moray Council
• South Ayrshire Council
• East Ayrshire Council
• East Lothian Council
• Fife Council

Page 16

LGBF Analysis of June 2025 Data Release Page 3 of 32
LGBF Priority Indicators
The table below displays the short term (or prior year) comparison of the performance, rank and quartile for the 33 priority LGBF indicators. To assess
performance, the terms ‘improved’ or ‘declined’ are used in this report. This terminology is used as for some indicators a value increasing is improved
performance however for other indicators, a value increasing is declining performance. Each indicator listed is an active html link to the chart further in this
document that provides more information on trends, relative performance and comments on performance.
In summary, of the 33 indicators over the short term:
• Performance has improved for 23 (69.7%) and declined for 10 (30.3%)
• Rank has improved for 18 (54.5%), declined for 11 (33.3%), and stayed the same for 4 (12.1%)
• Quar�le has improved for 8 (24.2%), declined for 6 18.2%), and stayed the same for 19 (57.6%)
Key
Performance has improved
Performance has stayed the same
Performance has declined
Performance Rank Quartile
LGBF Priority Indicator
Most
recent
year
available
Previous year’s
data 
Most recent
data
Data
improve
/ decline
Prior year
rank 
Most
recent rank
Rank
improve
/ decline
Previous
year’s
quartile 
Most
recent
quartile
Quartile
improve
/ decline
CHN11 - Proportion of pupils
entering positive destinations
(CP_07)
2023-24 96.50% 95.60% 8 19 1 3
CHN – 17 Proportion of Children
meeting developmental
milestones (CP_04)
2023-24 79.50% 77.50% 26 31 4 4

Page 17

LGBF Analysis of June 2025 Data Release Page 4 of 32
Performance Rank Quartile
LGBF Priority Indicator
Most
recent
year
available
Previous year’s
data 
Most recent
data
Data
improve
/ decline
Prior year
rank 
Most
recent rank
Rank
improve
/ decline
Previous
year’s
quartile 
Most
recent
quartile
Quartile
improve
/ decline
CHN24 - Proportion of children
living in poverty (after housing
costs)
2023-24 29.20% 24.30% 31 24 4 3
CLIM01 - CO2 emissions area
wide per capita 2022-23 4.95 4.64 20 18 3 3
CLIM02 - CO2 emissions area
wide: emissions within scope of
LA per capita
2022-23 5.29 4.97 22 21 3 3
CLIM03 - CO2 emissions from
Transport per capita 2023-24 30.92 29.54 25 22 4 3
CLIM04 - CO2 emissions from
electricity per capita 2023-24 45.16 45.83 23 16 3 2
CLIM05 - CO2 emissions from
natural gas per capita 2023-24 71.75 72.2 24 25 3 4
CORP03b - Proportion of the
highest paid 5% of employees
who are women
2023-24 61.3% 64.7% 10 3 2 1
CORP3c – Gender Pay Gap 2023-24 1.10%% 0.0% 11 7 2 1
CORP07 - Percentage of income
due from Council Tax received
by the end of the year (CP_48)
2023-24 94.7% 93.6% 29 30 4 4
CORP08 - Percentage of invoices
sampled that were paid within
30 days
2023-24 93.3% 95.8% 11 7 2 1

Page 18

LGBF Analysis of June 2025 Data Release Page 5 of 32
Performance Rank Quartile
LGBF Priority Indicator
Most
recent
year
available
Previous year’s
data 
Most recent
data
Data
improve
/ decline
Prior year
rank 
Most
recent rank
Rank
improve
/ decline
Previous
year’s
quartile 
Most
recent
quartile
Quartile
improve
/ decline
CORP09 - Proportion of SWF
Crisis Grant decisions within 1
day
2024-25 99.0% 99.3% 8 8 1 1
CORP10 - Proportion of SWF
Community Care Grant decisions
within 15 days
2024-25 99.0% 99.1% 10 11 2 2
CORP-ASSET01 - % of
operational buildings that are
suitable for their current use
(CP_19)
2023-24 95.1% 95.2% 6 6 1 1
ECON01 - Percentage of
Unemployed People Assisted
into work from Council
Programmes
2023-24 21.4% 19.8% 7 10 1 2
ECON04 - Proportion of
procurement spent on local
enterprises
2023-24 24.1% 23.8% 20 19 3 3
ECON05 - No of business
gateway start-ups per 10,000
population
2024-25 12.4 8.1 20 32 3 4
ECON07 - Proportion of people
earning less than the living wage 2023-24 11.7% 10.7% 5 9 1 2
ECON09 - Town Vacancy Rates 2023-24 7.4% 7.8% 7 6 1 1
ECON10 - Immediate available
employment land as a % of total
land allocated for employment
purposes
2023-24 46.3% 42.7% 7 9 1 2

Page 19

LGBF Analysis of June 2025 Data Release Page 6 of 32
Performance Rank Quartile
LGBF Priority Indicator
Most
recent
year
available
Previous year’s
data 
Most recent
data
Data
improve
/ decline
Prior year
rank 
Most
recent rank
Rank
improve
/ decline
Previous
year’s
quartile 
Most
recent
quartile
Quartile
improve
/ decline
ECON11 - Gross Value Added
(GVA) per capital 2023-24 £20,301 £20,910 26 25 4 4
ECON12a - Claimant Count as a
% of Working Age Population 2024-25 4.4% 4.3% 30 31 4 4
ECON12b - Claimant Count as %
of 16-24 Population 2024-25 5.9% 5.8% 32 32 4 4
ENV03c - Street Cleanliness
Score (CP_27) 2024-25 89.1% 90.3% 24 20 3 3
ENV04b - Percentage of A class
roads considered for
maintenance treatment
2022-24 30.70% 28.9% 27 21 4 3
ENV04c - Percentage of B class
roads considered for
maintenance treatment
2022-24 28.90% 27.4% 19 13 3 2
ENV04d - Percentage of C class
roads considered for
maintenance treatment
2022-24 39.90% 38.50% 27 26 4 4
ENV04e - Percentage of
unclassified roads considered for
maintenance treatment
2020-24 35.40% 32.40% 16 11 2 2
ENV06 - Proportion of total
household waste arising that is
recycled (CP_31)
2023-24 55.3% 56.1% 4 3 1 1
HSN01b - Gross rent arrears (all
tenants) as a percentage of rent
due for the year (CP_47)
2023-24 7.1% 5.9% 6 4 1 1

Page 20

LGBF Analysis of June 2025 Data Release Page 7 of 32
Performance Rank Quartile
LGBF Priority Indicator
Most
recent
year
available
Previous year’s
data 
Most recent
data
Data
improve
/ decline
Prior year
rank 
Most
recent rank
Rank
improve
/ decline
Previous
year’s
quartile 
Most
recent
quartile
Quartile
improve
/ decline
HSN03 - Proportion of council
dwellings meeting Scottish
Housing Quality Standards
(CP_25)
2023-24 63.2% 76.9% 16 16 2 2
HSN05a - Proportion of council
dwellings that are energy
efficient (CP_44)
2021-22 97.6% 97.7% 2 4 1 1

Page 21

LGBF Analysis of June 2025 Data Release Page 8 of 32
People Services
The table below displays the short term, medium term and long term comparisons against our current year for our 15 priority indicators within the People
Services family group. Where a 10 year (long term) trend is not available, the most historical figure has been used for the long term comparison. Each
indicator is linked to a chart in the following pages for more information.
In summary, of the 15 indicators our over the short, medium and long term.
• Short Term Family Group Rank – Improved 3 (20%), declined 5 (33.33%) and stayed the same 7 (46.66%)
• Medium Term Family Group Rank – Improved 7 (46.66%), declined 2 (13.33%) and stayed the same 6 (40%)
• Long Term Family Group Rank – Improved 1 (6.66%), declined 10 (66.66%) and stayed the same 4 (26.66%)
Short Term, Medium Term and Long Term
Comparisons for our People Services Family
Group
Current Year Short Term Comparison Medium Term Comparison Long term Comparison
LGBF Indicators Peoples Services Year Rank Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
CHN11 - Proportion of pupils entering
positive destinations 2023-24 4 2022-23 3 2020-21 5 2013-14 2
CHN17 - Percentage of children meeting
development milestones 2023-24 7 2022-23 4 2020-21 4 2013-14 1
CHN24 - Proportion of Children Living in
Poverty After Housing Costs 2023-24 4 2022-23 7 2020-21 7 2014-15 7

Page 22

LGBF Analysis of June 2025 Data Release  Page 9 of 32
Short Term, Medium Term and Long Term
Comparisons for our People Services Family
Group 
Current Year Short Term Comparison  Medium Term Comparison  Long term Comparison 
LGBF Indicators Peoples Services Year Rank Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
Year  Rank
Rank
improve
/ decline
ECON1 - Percentage of Unemployed People
Assisted into work from Council
Programmes
2023-24 5 2022-23 4  2020-21 6  2013-14 4 
ECON12a - Claimant Count as a percentage
of working age population 2024-25 2 2023-24 2  2021-22 3  2014-15 1 
ECON12b - Claimant Count as a percentage
of 16-24 population 2024-25 1 2023-24 1  2021-22 1  2014-15 1 
ECON7 - Proportion of people earning less
than the living wage 2023-24 3 2021-22 4  2019-20 3  2012-13 5 
ECON9 - Town Vacancy Rates 2023-24 3 2022-23 2  2020-21 4  2014-15 2 
ENV3c - Street Cleanliness Score 2024-25 4 2023-24 4  2021-22 5  2014-15 6

Page 23

LGBF Analysis of June 2025 Data Release  Page 10 of 32
Short Term, Medium Term and Long Term
Comparisons for our People Services Family
Group 
Current Year Short Term Comparison  Medium Term Comparison  Long term Comparison 
LGBF Indicators Peoples Services Year Rank Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
Year  Rank
Rank
improve
/ decline
HSN1b - Gross Rent Arrears (All Tenants) as
a Percentage of rent due for the year 2023-24 1 2022-23 1  2020-21 1  2013-14 1 
HSN3 - Proportion of Council dwellings
meeting Scottish Housing Quality Standards 2023-24 4 2022-23 4  2020-21 2  2013-14 1 
HSN5a - Proportion of council dwellings that
are energy efficient 2021-22 2 2020-21 2  2018-19 1  2015-16 1 
CORP7 - Percentage of income due from
Council Tax received by the end of the year 2023-24 7 2022-23 7  2020-21 8  2013-14 2 
CORP9 - Percentage of Scottish Welfare
Fund Crisis Grant decisions within one day 2024-25 4 2023-24 3  2021-22 4  2018-19 3 
CORP10 - Percentage of Scottish Welfare
Fund Community Care Grant decisions in 15
days
2024-25 2 2023-24 4  2021-22 3  2018-19 2

Page 24

LGBF Analysis of June 2025 Data Release Page 11 of 32
(Please note, axis scales used within the following charts vary to ensure trends are visible.)
CHN11 – Proportion of pupils entering positive destinations
The current proportion of pupils entering positive destinations is 95.6% for 2023 to 2024. Despite a
slight decrease from 2022 to 2023 (which represented our highest figure on record), our
performance on this indicator is consistently strong, with the only local authorities that are currently
higher in terms of pupils entering positive destinations being Glasgow City (95.7%), West
Dunbartonshire (96%) and Eilean Siar Councils (97.8%). 
Data for this indicator is published by the Scottish Government in its ‘School leaver initial destinations
and attainment survey’, which collects information on the destination of school leavers (from publicly
funded mainstream schools) in September. A school leaver is defined as a young person of school
leaving age, who left school during or at the end of the school year. The school year runs from 1
August to 31 July. Data on initial destinations of school leavers is based on approximately three
months after the end of the school term and their post review (previously post appeal) attainment
information. This publication covers school leavers from all stages of secondary school. For most
young people, S4 (15 to 16 year olds) is the last compulsory year of school, but the majority choose
to stay on and complete S5 (16 to 17 year olds) and S6 (17 to 18 year olds). School leavers who
moved away from Scotland are not included in the results.

Page 25

LGBF Analysis of June 2025 Data Release Page 12 of 32
CHN17 – Percentage of children meeting development milestones (27-30 month
Review)
Currently 77.5% (2023 to 2024) of children are meeting developmental milestones which is a decline
from 79.5% (2022/2023) with only one authority, East Ayrshire 77.3% performing less well within our
family group (and nationally). We currently sit lower than both our Family Group Average (79.8%)
and the National Average (83.3%) and remain in the 4th Quartile. We are working to ensure there is
more robust data gathering and analysis within Early Years and are moving towards using CfE levels
with inbuilt milestones.  This will help improve accuracy and consistency of data as well as improved
progression pathways to primary.  Roles and remits for Excellence and Equality Leads (EELs)
developed this academic session will support this work. This is an area that we also know will need
specific focus within wider principles of prevention and early intervention, including through the
Collaboration for Health Equity in Scotland.      
CHN24 – Proportion of Children Living in Poverty After Housing Costs
The most recent data release shows 24.3% of our children in North Ayrshire are living in poverty
(after housing costs) – a decrease of 4.9 percentage points since the previous year - this is below the

Page 26

LGBF Analysis of June 2025 Data Release Page 13 of 32
family group average of 25.3% and is the largest decrease of all Scottish councils. Four councils within
our family group have a higher proportion of children living in poverty (after housing costs): Glasgow
City (36.1%), Dundee City (26.1%), North Lanarkshire (24.9%) and West Dunbartonshire (25.2%)
Councils. At a national level, the introduction of the Scottish Child Payment is thought to have been
significant.  Whilst further analysis is required to determine what has been most impactful in
reducing child poverty at a local level across North Ayrshire, our council is continually working to
address barriers to employment as well as ensuring families are aware of, and can access, the
support they are entitled to.
ECON1 – Percentage of Unemployed People Assisted into work from Council Programmes
Currently 19.8% (2023 to 2024) of unemployed people are assisted into work from council
programmes. Within our family group, Eilean Siar (30.8%), Inverclyde (24.2%), North Lanarkshire
(22.7%) and West Dunbartonshire (29.3%) Councils are all currently reporting a higher percentage of
unemployed people assisted into work, however for context North Ayrshire has the second highest
claimant count as a percentage of working population and the highest for those aged 16 to 24 years
(see charts below). In 2023 to 2024, the family group average was 20.1% and the national average
was 12.1%. Addressing the level of unemployment and the delivery of such support and programmes
remains a priority. This also includes a focus on the maximisation of job opportunities available
within local enterprises and through new inward investment.

Page 27

LGBF Analysis of June 2025 Data Release Page 14 of 32
ECON12a – Claimant Count as a percentage of working age population
North Ayrshire had the second highest claimant count rates as a percentage of working age
population within our family group for 2024 to 2025 at 4.3%. Only Glasgow City Council with 5% has a
higher claimant count. Through the work of the Employability and Skills Team, the Local
Employability Partnership (LEP) and the extensive network of working relationships the focus on
working age employment will continue to improve the outcomes and reduce the claimant count.
ECON12b - Claimant Count as a percentage of 16-24 population
North Ayrshire had the highest claimant count as a percentage of population aged 16 to 24 years
within our family group at 5.8%. North Ayrshire continues to have the highest level across Scotland
but maintains a sharp focus on engaging and supporting young people into employment. The
Employability Team recently launched youth hubs working in partnership with the Department for
Work and Pensions (DWP) and Skills Development Scotland to support our young people. A

Page 28

LGBF Analysis of June 2025 Data Release Page 15 of 32
participant recruitment incentive has supported those we are supporting into employment by
adopting targeting interventions to open opportunities for our young people who are disadvantaged
in the labour market. The team has increased their focus on youth transitions, progression and
tracking and will continue this to improve outcomes for our young people. Through the keyworker
support, they continue to provide in work support to improve employment retention.  Through the
work of the Employability and Skills Team, the LEP and the extensive network of working
relationships this focus on youth employment will continue to improve the outcomes and reduce the
youth claimant count
ECON7 – Proportion of people earning less than the living wage
We currently have 10.7% (2023 to 2024) of people earning less than the living wage. Currently we are
ranked 3rd in our family group (behind Glasgow City and Dundee City Councils). 2023 to 2024 data is
not available for Argyll and Bute, East Renfrewshire, Eilean Siar, Midlothian, Orkney Islands and
Shetland Islands Councils. The national average is currently 10.2% and the Family Group Average is
11.4%. North Ayrshire Council is performing strongly in supporting employers to pay the Real Living
Wage. This has been supported by the work led by Employability Team through Fair Work and Skills
and aligning fair work to the continuing Ayrshire Skills Investment Fund to support more employers
to pay the Real Living Wage (RLW).

Page 29

LGBF Analysis of June 2025 Data Release  Page 16 of 32
ECON9 – Town Vacancy Rates 
Town Vacancy rates have increased from 7.4% in 2022 to 2023 to 7.8% in 2023 to 2024. Town
vacancy rates are a measure of the performance of our town centres and cannot be viewed in
isolation. A suitable mix of various retail and service organisations in our towns is crucial to support
ongoing regeneration. Although we have seen a slight increase, we are still currently below the family
group average of 11.2% and the national average of 12.3%. Town centres remain a priority and focus
for the Regeneration Team and for national funding opportunities including the Place Based
Investment Programme and the Plan for Neighbourhoods, formerly the Long-Term Plan for Towns.
Programmes such as the Repurposing Property Grant Fund aim to contribute to further improving
the vacancy rates alongside our Business Support and Development activities.
ENV3c – Street Cleanliness Score 
Our Street Cleanliness Score for 2024 to 2025 was 90.3% which is improved from 89.1% in 2023
to2024, this has resulted in an improvement in rank and quartile, moving our council from the 4th to
the 3rd quartile. In 2024 to 2025 we performed higher than our family group average (88.9%) but
slightly lower than the national average (91.7%).  East Ayrshire (92.6%), Eilean Siar (92.4%) and
Inverclyde (91.1%) Councils are the only authorities within our family group that have a higher street
cleanliness score.

Page 30

LGBF Analysis of June 2025 Data Release Page 17 of 32
HSN1b – Gross Rent Arrears (All Tenants) as a Percentage of rent due for the year
The gross rent arrears (all tenants) as a percentage of rent due for the year was 5.9%. This is lower
than the family group average of 8.3% as we are the strongest performing local authority in our
family group. Between 2022 and 2024 we have risen in rank from 6th to 4th. We remain in the 1st
quartile. Our most recent local data shows that the estimated percentage for 2024 to 2025 is 8.03%.
HSN3 – Proportion of Council dwellings meeting Scottish Housing Quality Standards
The proportion of Council dwellings meeting Scottish Housing Quality Standard (SHQS) for the
reporting period was 76.9%, in comparison only West Dunbartonshire Council reported a lower
compliance rate which was 51.2%. The SHQS incorporates the Energy Efficiency Standard for Social
Housing (EESSH), along with another 54 tests that must be satisfied prior to a property passing. The
main challenge for North Ayrshire has been gaining access to properties to carry out statutory
compliance works (EICR).  However, this has improved throughout 2024 to 2025 and the updated
local figure for 2024 to 25 is 94%.

Page 31

LGBF Analysis of June 2025 Data Release  Page 18 of 32
HSN5a – Proportion of council dwellings that are energy efficient 
The proportion of council dwellings that are energy efficient remains high, with performance
improving slightly from 97.6% in 2020 to 2021 to 97.7% in 2021 to 2022. This is the second strongest
performance in our family group behind East Ayrshire Council and higher than the Scottish average of
87.6%. To improve the relevance of this measure, the basis on which it is calculated was changed in
2019 to 2020. It is now based on progress towards meeting the Energy Efficiency Standard for Social
Housing (EESSH). Data for this indicator for 2022 to 2023 onwards has not been collected or
published due to the Scottish Government review of EESSH2.  (As reported in our Mid-Year report).
However, we can confirm our locally recorded figures for 2022 to 2023 was 98.2%, for 2023 to 2024
it was 98.01% and for 2024 to 2025 it was 97.66%
CORP7 – Percentage of income due from Council Tax received by the end of the year 
The most recent data release shows that 93.6% of income due from Council Tax was received by the
end of the year compared to the family group average of 94.2%. We remain in the 4th quartile as we
have declined from 29th to 30th in the rankings. We are currently performing less strongly than our
family group with only West Dunbartonshire Council having a lower percentage of income due by the
end of the year (93.2%).

Page 32

LGBF Analysis of June 2025 Data Release Page 19 of 32
CORP9 – Percentage of Scottish Welfare Fund Crisis Grant decisions within one day
The most recent data shows that 99.3% of Scottish Welfare Fund Crisis Grant decisions were made
within one day. Only Eilean Siar and Inverclyde Councils had a higher percentage with both
authorities reaching 100%. 
CORP10 – Percentage of Scottish Welfare Fund Community Care Grant decisions in 15 days
The percentage of Scottish Welfare Fund Community Care Grant decisions in 15 days was 99.1%.
Only Eilean Siar (94.3%) and Inverclyde (99.4%) Councils currently have a higher percentage of
Scottish Welfare Fund Community Care Grant decisions in 15 days

Page 33

LGBF Analysis of June 2025 Data Release Page 20 of 32
Other Services
The table below displays the short term, medium term and long term comparisons against our current year for 18 priority indicators within our Other Services
family group. Where a 10 year (long term) trend is not available, the most historical figure has been used for the long term comparison. Each indicator is
linked to a chart in the following pages for more information.
In summary, of the 18 indicators our over the short, medium and long term.
• Short Term Family Group Rank – Improved 8 (44.44%), declined 4 (22.22%) and stayed the same 6 (33.33%)
• Medium Term Family Group Rank – Improved 9 (50%), declined 4 (22.22%) and stayed the same 5 (27.77%)
• Long Term Family Group Rank – Improved 9 (50%), declined 1 (6.66%) and stayed the same 8 (44.44%)
Short Term, Medium Term and Long Term
Comparisons for our Other Services Family
Group
Current Year Short Term Comparison Medium Term Comparison Long term Comparison
LGBF Indicators Peoples Services Year Rank Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
CLIM1 – CO2 emissions area wide per capita 2022-23 4 2021-22 5 2019-20 5 2012-13 5
CLIM2 – CO2 emissions area wide: emissions
within scope of Local Authority per 2022-23 4 2021-22 4 2019-20 4 2012-13 5
CLIM3 -CO2 emissions from transport per
1000 population 2023-24 6 2022-23 6 2020-21 6 2017-18 6

Page 34

LGBF Analysis of June 2025 Data Release  Page 21 of 32
Short Term, Medium Term and Long Term
Comparisons for our Other Services Family
Group
Current Year Short Term Comparison  Medium Term Comparison  Long term Comparison 
LGBF Indicators Peoples Services Year Rank Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
Year  Rank
Rank
improve
/ decline
CLIM4 – CO2 emissions from electricity per
1000 population 2023-24 3 2022-23 7  2020-21 7  2017-18 6 
CLIM5 – CO2 emissions from natural gas per
1000 population 2023-24 8 2022-23 8  2020-21 7  2017-18 8 
ECON10 – Immediate available employment
land as percentage of total land allocated for
employment purposes
2023-24 2 2022-23 1  2020-21 3  2014-15 7 
ECON11 – Gross value added (GVA) per
capita 2023-24 6 2022-23 6  2020-21 6  2013-14 6 
ECON5 – No of business gateway start – ups
per 10,000 population 2024-25 8 2023-24 6  2021-22 7  2014-15 5 
ECON4 – Proportion of procurement spent
on local enterprises 2023-24 6 2022-23 5  2020-21 7  2013-14 6

Page 35

LGBF Analysis of June 2025 Data Release Page 22 of 32
Short Term, Medium Term and Long Term
Comparisons for our Other Services Family
Group
Current Year Short Term Comparison Medium Term Comparison Long term Comparison
LGBF Indicators Peoples Services Year Rank Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
ENV4b - Percentage of A class roads
considered for maintenance treatment 2022-24 6 2021-23 7 2019-21 7 2012-14 6
ENV4c - Percentage of B class roads
considered for maintenance treatment 2022-24 3 2021-23 3 2019-21 4 2012-14 7
ENV4d - Percentage of C class roads
considered for maintenance treatment 2022-24 8 2021-23 7 2019-21 8 2012-14 8
ENV4e - Percentage of unclassified roads
considered for maintenance treatment 2020-24 3 2019-23 4 2017-21 4 2010-14 5
ENV6 – Percentage of total household waste
arising that is recycled 2023-24 1 2022-23 2 2020-21 4 2013-14 1
CORP3b – Percentage of the highest paid 5%
of employees who are women 2023-24 1 2022-23 3 2020-21 1 2013-14 1

Page 36

LGBF Analysis of June 2025 Data Release  Page 23 of 32
Short Term, Medium Term and Long Term
Comparisons for our Other Services Family
Group
Current Year Short Term Comparison  Medium Term Comparison  Long term Comparison 
LGBF Indicators Peoples Services Year Rank Year Rank
Rank
improve
/ decline
Year Rank
Rank
improve
/ decline
Year  Rank
Rank
improve
/ decline
CORP3c – Gender Pay Gap 2023-24 2 2022-23 3  2020-21 3  2015-16 5 
CORP8 – Percentage of invoices sampled
that were paid within 30 days 2023-24 2 2022-23 3  2021-22 1  2014-15 3 
CORP-ASSET1 – Percentage of operational
buildings that are suitable for their current
use
2023-24 3 2022-23 3  2020-21 2  2013-14 4

Page 37

LGBF Analysis of June 2025 Data Release  Page 24 of 32 
(Please note, axis scales used within the following charts vary to ensure trends are visible.)
CLIM1 – CO2 emissions area wide per capita 
Currently our CO2 Emissions Area wide per Capita is 4.64tCO2e. Perth and Kinross (4.68), Fife (7.81)
and East Lothian (10.02) Councils currently rank higher in our family group. In the production of the
2022 estimates, new data was introduced, together with some improvements to the underlying
methodology. To ensure that the data for 2005 to 2021 is consistent with the data now available for
2022, the estimates for these years have been revised to incorporate both the new data and the
improvements in the underlying methodology. For some local authorities, these revisions have
resulted in noticeable changes to the emissions estimates in historic years, with only slight changes
for North Ayrshire.
CLIM2 – CO2 emissions area wide: emissions within scope of Local Authority per capita 
Currently our CO2 emissions area wide: emissions within scope of local authority per capita is
4.97tCO2e compared to Perth & Kinross (5.90), South Ayrshire (5.11) Stirling (5.74) and Moray (6.94)
Councils. In the production of the 2022 estimates, new data was introduced, together with some
improvements to the underlying methodology. To ensure that the data for 2005 to 2021 is consistent

Page 38

LGBF Analysis of June 2025 Data Release Page 25 of 32
with the data now available for 2022, the estimates for these years have been revised to incorporate
both the new data and the improvements in the underlying methodology. For some local authorities,
these revisions have resulted in noticeable changes to the emissions estimates in historic years, with
only slight changes for North Ayrshire.
CLIM3 -CO2 emissions from transport per 1000 population
Currently our CO2 emissions from transport per capita is 29.54tCO2e for 2023 to 2024. Only Moray
and Fife Councils have higher emissions from transport per capita with 38.64 and 32.67 respectively.
CLIM4 – CO2 emissions from electricity per 1000 population
Currently our CO2 emissions from electricity per capita is 45.83tCO2e for 2023 to 2024. Only Perth
and Moray Councils currently have lower CO2 emissions per capita from electricity with 33.70 and
32.61 respectively.

Page 39

LGBF Analysis of June 2025 Data Release  Page 26 of 32
CLIM5 – CO2 emissions from natural gas per 1000 population 
Currently our CO2 emissions from natural gas per capita is 72.20tCO2e. We have the highest
emissions within our family group by a significant margin.
ECON10 – Immediate available employment land as percentage of total land allocated for
employment purposes 
In North Ayrshire, immediately available employment land as a percentage of total land allocated for
employment purposes is 42.7%. Only East Ayrshire Council has a higher percentage with 42.8%.
Attracting and securing inward investment opportunities remains a priority.

Page 40

LGBF Analysis of June 2025 Data Release Page 27 of 32
ECON11 – Gross value added (GVA) per capita
Gross Value Added (GVA) is something we can help influence as a local authority; however, it relies
on all industry within North Ayrshire and is monitored for context.
ECON5 – No of business gateway start–ups per 10,000 population
At year end 2024 to 2025, we had 8.1 business gateway start-ups per 10,000 population. Data for this
indicator is available on a monthly basis. The yearly values represent an average of the monthly
values. The ongoing review of Economic Development Growth and Regeneration services will provide
greater focus on business start-up activity.

Page 41

LGBF Analysis of June 2025 Data Release  Page 28 of 32
ECON4 – Proportion of procurement spent on local enterprises 
This indicator is a useful comparison for benchmarking purposes; however, it does not capture all
spend as detailed in our 2020 to 2021 Mid-Year Council Plan Progress Report. “The LGBF calculation
excludes certain spend, most notably it excludes all suppliers spend below £1,000 and excludes all
suppliers not categorised as core trade organisations. This is Local Government Benchmarking
Framework is therefore not an accurate reflection of the economic activity within North Ayrshire. As
we have access to the source data used by the LGBF we are able to capture all spend data and refine
the calculation at a local level to better capture our spend with local enterprises and shorten the time
delay in reporting.” Our local figure for 2023 to 2024 was 24.48% which, though not a direct
comparison with the LGBF measure, would put us ranked 4th in our family group and 19th nationally.”
Our most recent local figure is 26.8% for 2024 to 25.

Page 42

LGBF Analysis of June 2025 Data Release Page 29 of 32
Percentage of A Class Roads Considered for Maintenance Treatment   Percentage of B Class Roads Considered for Maintenance Treatment
Percentage of C Class Roads Considered for Maintenance Treatment  Percentage of Unclassified Roads Considered for Maintenance Treatment

Page 43

LGBF Analysis of June 2025 Data Release  Page 30 of 32  
ENV4b - Percentage of A class roads considered for maintenance treatment
Within North Ayrshire the Percentage of A class roads considered for maintenance treatment is
28.9%. This indicates improvement of 1.8% from figures reported in 2023 and is equal to the Scottish
Average for A class roads. (Chart on previous page.)
ENV4c - Percentage of B class roads considered for maintenance treatment
Within North Ayrshire the Percentage of B class roads considered for maintenance treatment is
27.4%. This indicates an improvement of 1.5% and is below the Scottish average of 32.5% (Chart on
previous page.)
ENV4d - Percentage of C class roads considered for maintenance treatment
Within North Ayrshire the Percentage of C class roads considered for maintenance treatment is
38.5%. This indicates an improvement of 1.4%. (Chart on previous page.)
ENV4e - Percentage of unclassified roads considered for maintenance treatment
Within North Ayrshire the Percentage of unclassified roads considered for maintenance treatment is
32.4%. This indicates an improvement of 3% and is below the Scottish average of 36.2% (Chart on
previous page.)
Overall, data shows our council’s commitment to investment in the road infrastructure is displaying
positive impacts with an improving Road Condition index across all classifications.
ENV6 – Percentage of total household waste arising that is recycled 
The most recent percentage of total house waste arising that is recycled was 56.1% and our family
group average was 52.3%. This is the strongest performance within our family group. The estimated
household waste recycling figure for the calendar year 2024 is 52.8%, subject to verification by SEPA.
This has reduced from 2023 as a result of the introduction of the new SEPA guidance regarding the
requirement for Waste Upholstered Domestic Seating (WUDS) to only be sent for incineration, which
has negatively affected the amount of bulky waste that can be recycled (this will affect all Councils),
as well as increased contamination levels within the purple bin for glass, cans and plastics. A
reduction in organic waste arisings in 2024 and increased contamination has also contributed to the
reduction in performance, as well as more wood being deposited at recycling centres that was only
suitable for biomass recovery and not for recycling.

Page 44

LGBF Analysis of June 2025 Data Release  Page 31 of 32  
CORP3b – Percentage of the highest paid 5% of employees who are women 
64.7% of our highest paid 5% of employees are women. This is the highest in our family group. 
CORP3c – Gender Pay Gap 
The most recent figures reported for North Ayrshire Council show that the average hourly rates for
women and men are identical, indicating no gender pay gap for 2023-24. This is below both the
national (2.5%) and family group (2.1%) average.

Page 45

LGBF Analysis of June 2025 Data Release Page 32 of 32
CORP8 – Percentage of invoices sampled that were paid within 30 days
The percentage of invoices sampled that were paid within 30 days was 95.8%, compared to the
89.5% family group average. We are currently second highest in our family group with only Fife
Council (96.4%) having a higher percentage.
CORP-ASSET1 – Percentage of operational buildings that are suitable for their current use
The percentage of operational buildings that are suitable for their current use is currently 95.2%. This
is the third highest with Perth and Kinross (96%) and Moray (97.4%) Councils having stronger
performance.

Page 46

Local Government Benchmarking Framework – June 2025 Analysis Page 33 of 24
We strive to make our reporting as accessible as possible.  If you have any
questions or require further information on our Council’s performance please
contact:
The Corporate Policy and Performance Team
Tel:  01294 310000  Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk
Reports can be viewed at www.north-ayrshire.gov.uk/performance

Page 47

Our Council Plan
Six Monthly
Progress Report
1 October 2024 to
31 March 2025 
Appendix 2

Page 48

Contents
Our Performance at a Glance ................................................................................................. 1
Welcome ................................................................................................................................. 2
Wellbeing ....................................................................................................................... 4
Communi�es and Local Democracy ............................................................................. 14
Climate Change ............................................................................................................ 23
A Sustainable Council ................................................................................................... 30
Our Transforma�on Programme .................................................................................. 32
Audits, Inspec�ons and Accredita�ons ........................................................................ 37
Performance Summary ......................................................................................................... 43
Performance Indicators Adri� of Target ....................................................................... 43
Indicator Amendments and Recommenda�ons .......................................................... 46
Ac�ons Adri� of target ................................................................................................. 46
Performance Indicators ........................................................................................................ 47
Ac�on Tracker ....................................................................................................................... 51

Page 49

Our Council Plan Progress Update – Year End 2024 to 2025 Page 1 of 56
Our Performance at a Glance
£21.5 million income
secured for our
residents through
5,842 Money Matters
referrals
Free school meals
extended to eligible
Primary 6 and Primary
7 Pupils
£171,377 of
Participatory
Budgeting Funding
awarded to 190
groups
423,077sq.ft of
commercial/industrial
floor space within our
council portfolio
Our new Digital
Learning Strategy for
our young people was
launched
Our Strategic Housing
Investment Plan
2025-2030 was
approved
90 climate change
and energy lessons
delivered to 29
primary schools to
date
ECO4 Flex Scheme
Funding of £902,809 has
supported 32 North
Ayrshire households to
improve the energy
efficiency of their homes
Our Local Heat and
Energy Efficiency
Strategy procurement
framework was
launched
56.1% of our
household waste is
recycled
Over 4,400 responses
to our 2025-2026
Budget Consultation
81 Skills for Life
Placements created in
2024-2025

Page 50

Our Council Plan Progress Update – Year End 2024 to 2025 Page 2 of 56
Welcome
Welcome to our Year-End Progress Report on our Council Plan 2023 to 2028. This report
covers the period 1 October 2024 to 31 March 2025. Our Council Plan is our contract with
our residents and details how we are progressing our four priori�es of Wellbeing,
Communi�es and Local Democracy, Climate Change, and A Sustainable Council:
Our Vision: A North Ayrshire that is fair for all
Our Mission: Working together to improve the
lives of our people in North Ayrshire
Delivery of our Council Plan is progressing posi�vely with 69% of our indicators where the
status is known are either on target or just slightly adri� of target, and 98% of our ac�ons
are on target or just slightly adri� of target. We regularly compare our performance to other
local authori�es with similar demographic traits through the Local Government
Benchmarking Framework (LGBF) and include informa�on on this within our Council Plan
repor�ng. There are 33 LGBF indicators that link closely with our Council Plan priori�es and
of these 33 indicators, 17 are in the top two quar�les. 
We commenced our 2025 to 2026 Budget Consulta�on in October 2024 and received over
4,400 responses from our residents and community groups. Learning from previous
consulta�ons, we adapted and tailored our approach in order to reach more of our
communi�es enabling our residents to comment on the areas which matered most to
them. The increased response rate shows that our approach to consulta�on is improving.
Our Money Maters team received 5,842 referrals in 2024 to 2025 and maximised the
income of our residents by £21.5m. This is in addi�on to Welfare Reform Advice who
received 1,899 referrals for welfare rights and debt advice, resul�ng in £5.7m of financial

Page 51

Our Council Plan Progress Update – Year End 2024 to 2025 Page 3 of 56
support being accessed by our tenants. In order to deliver accessible welfare rights and
money advice services for our more vulnerable residents, our Money Maters and Welfare
Reform Advice Team will be rebranded as “Money Smart” and will be accessible via a single
access point. These changes will maximise our resources and capacity to deliver these
services. 
Advancing on the exis�ng provision of Free School Meals for all Primary One to Primary Five
pupils, we are now also offering free school meals to Primary Six and Primary Seven pupils in
receipt of the Sco�sh Child Payment. 
Enabling our residents to par�cipate in local decision making, our 2024 to 2025 Par�cipatory
Budge�ng (PB) round was held both on and offline. This ensured that individuals and groups
who may face barriers to online par�cipa�on could s�ll contribute and have their say. As a
result, 15,882 votes were cast across North Ayrshire.
We have supported 32 households with the installa�on of over 134 energy saving measures
to improve home energy efficiency. This was a part of our ECO4 Flex scheme which looks at
funding for energy efficiency improvements in homes, primarily targe�ng low-income and
vulnerable households. The scheme, part of the wider Energy Company Obliga�on (ECO)
program, offers financial assistance for measures like insula�on, hea�ng upgrades and
renewable energy installa�ons.
To give context to the environment in which we deliver our services, some key measures are
highlighted below:
Together we will ensure a North Ayrshire that is fair for all.
Population of North Ayrshire:
133,570 (2023)
24.3% of our children live in
poverty after housing costs
(2023-24)
28% of our households live in
fuel poverty (2021-22)
65.2% of working age
population is in employment
(June 2024)
10.4% of people earn less than
the living wage (2023)
Area wide CO2 emissions are
682kt CO2 (July 2023)

Page 52

Our Council Plan Progress Update – Year End 2024 to 2025 Page 4 of 56
Wellbeing
To transi�on to a wellbeing
economy, delivering prosperity,
wellbeing and resilience for local
people.
Key Ac�vi�es
Child Poverty
A North Ayrshire that is fair for all requires
every child to have the same
opportuni�es in life. Recent sta�s�cs
published by the End Child Poverty
Coali�on showed that child poverty within
North Ayrshire decreased from 29.2% in
2022-23 to 24.3% in 2023-24. This
reduc�on of 4.9 percentage points was
the largest in Scotland over this �me
period.  Many ac�ons within our Council
Plan help address child poverty including
mi�ga�ng barriers to employment as well
as ensuring families are aware of, and can
access, the support they are en�tled to. At
a na�onal level, the introduc�on of the
Sco�sh Child Payment is thought to have
had a posi�ve impact on our most
vulnerable families. 
However, no child should be living in
poverty, and we s�ll have a lot of work
ahead of us. As part of the Fairer Futures
Partnership (FFP) with the Sco�sh
Government, our new Child Poverty
Strategy Team (CPST) was established in
January 2025. A key part of the CPST
ac�vity will be undertaking a co-designed
place-based test of change. In
prepara�on, the team has appointed the
Centre of Excellence for Children’s Care
and Protec�on (CELCIS) as a learning
partner. Our Third Sector Interface
partners are suppor�ng this work and
£45,000 has been allocated to The
Ayrshire Community Trust. This will enable
third sector organisa�ons to be funded as
co-design partners and support the
involvement of residents with lived
experience.
Health Equity
Across the UK, there are marked regional
differences in life expectancy, par�cularly
among people living in areas of high
depriva�on. Following a compe��ve
applica�on process, we have been

Page 53

Our Council Plan Progress Update – Year End 2024 to 2025 Page 5 of 56
selected as one of three areas to engage
in the Collabora�on for Health Equity in
Scotland (CHES) programme. Over the
next two years, we will work in
partnership with Public Health Scotland
and the Ins�tute for Health Equity – led by
Professor Sir Michael Marmot - to reduce
health inequity in North Ayrshire through
improving the condi�ons people live and
work in. The programme was officially
launched in February 2025 with over 70
delegates from our partners. A local
steering group has been established to
support iden�fica�on of local priori�es,
which will be informed by local data and
community engagement. The ul�mate
goal is to enable people to live longer,
healthier lives by addressing the root
causes of health inequali�es and prevent
illness before it starts. By crea�ng
condi�ons where communi�es can thrive,
the ini�a�ve aims to create las�ng
posi�ve change.
Money Maters
Welfare advice provides a range of
benefits by helping individuals navigate
complex social security systems and
access the financial support they are
en�tled to. During 2024 to 2025, our
Money Maters team received 5,842
referrals and secured £21.5 million in
financial gains through income
maximisa�on for local residents. These
figures are slightly higher than 2023 to
2024 but are provisional following the use
of a new case management system in
September - the actual totals may be
higher.
In addi�on, our Welfare Reform Advice
team received a total of 1,899 referrals for
welfare rights and debt advice for council
tenants, an increase of 28% compared to
2023 to 2024. The total financial gain for
North Ayrshire tenants was £5.7million, up
from £3.8 million in 2023 to 2024. In
addi�on, the Financial Inclusion Officers:
• Undertook 507 ‘pre-tenancy visits’ for
new tenants and tenancies to ensure
tenants understand changes to their
benefits due to taking on a tenancy,
and their responsibili�es to help them
sustain their tenancy - for example:
priority bills, support with accessing
grants and furnishings for their new
home, and support to claim all their
en�tlements.
• Assisted Universal Credit claims for
2,334 tenants who were also taken
through a support plan ‘matrix’ to
iden�fy and ac�on wider needs.
Our advice services con�nue to be
available throughout our communi�es in
nine priority GP surgeries, schools,
foodbanks and larders and local housing
offices. Macmillan Cancer Research also
provides funding to support advisers to
ensure people living with cancer receive
welfare rights advice and support. Our
Money Maters advisers are also
embedded within Health and Social Care
Partnership services including Children
and Families, Addic�ons and Community
Jus�ce services.
The Welfare Rights Officers in Schools
team now cover Early Years Centres and
primary schools.
Community Wealth Building
Community Wealth Building (CWB) is
about working with communi�es and
businesses to build a strong, fair and
sustainable local economy.
Our Economic Policy
team has supported
the forma�on of the
CWB Prac��oners

Page 54

Our Council Plan Progress Update – Year End 2024 to 2025 Page 6 of 56
Network with support from the
Improvement Service. The Network
provides opportuni�es for knowledge-
sharing and collabora�on on common
challenges across local authori�es. It also
seeks to deliver a comprehensive and up-
to-date overview of CWB implementa�on
across Scotland while strengthening
connec�ons between CWB and other
policy areas. 
We have refreshed the Wellbeing
Economy Dashboard – a suite of socio-
economic indicators which are used to
monitor progress towards the delivery of a
Wellbeing Economy in North Ayrshire and
provide context within our Council Plan
Progress Reports.
Employability and Skills
Skills enable people to par�cipate in the
labour market and lead more fulfilling
lives. We con�nued to deliver our broad
‘Your Next Move, Working North Ayrshire’
programme with partners including our
successful Modern Appren�ceship and
Skills for Life programmes. Available to
residents across our six locali�es, the
programme is delivered in partnership
with the Youth Services team who are a
pivotal part of our council’s Community
Learning and Development team,
delivering in excess of 2,000 youth groups
and ac�vi�es across the locali�es of North
Ayrshire. 
We delivered a range of awareness-raising
and recruitment events with partners to
showcase the opportuni�es available
across North Ayrshire. We are also
planning for our next Employability Week
in May 2025.
We created a Disability Employment Hub
at Lochshore Park to provide a range of
training opportuni�es for grounds
maintenance work, allowing trainees to
gain the skills and experience to complete
their hor�culture qualifica�ons, while
improving the public area too.  A
programme of tree plan�ng and
environmental improvements will be
developed with the stakeholders including
Streetscene, Friends of Lochshore and
Conserva�on Volunteers, providing added
value for all involved.  Work to further
progress the Hub will con�nue in 2025 to
2026.
Atainment
The overriding aim of our Educa�on
Service remains to improve the
educa�onal outcomes for all learners,
par�cularly those most disadvantaged
learners. To support this, we are
strengthening the strategic use of data to
drive con�nuous improvement and raise
atainment across our schools. Innova�ve
approaches include analysing Insight
leavers data to iden�fy strengths and
development areas, which will shape
priori�es in the Service Improvement Plan
2025 to 2026. Senior Leaders par�cipated
in a data clinic to enhance their use of
data for improvement and, together with
our Data Service Improvement Group, we
have launched a pilot exploring new
tracking and monitoring tools for literacy
and numeracy. The group is also
evalua�ng these tools to establish
effec�ve metrics for measuring progress
and achievement.
Our Digital Learning Strategy was
launched in March for young people aged
from two years old to 18. The strategy was
created collabora�vely by
our Educa�on Service,
teachers and early
years employees.  It
aims to develop

Page 55

Our Council Plan Progress Update – Year End 2024 to 2025 Page 7 of 56
learners’ digital skills in prepara�on for an
increasingly complex world.  It will ensure
our young people are confidently able to
use a range of digital technologies to
deliver exci�ng, suppor�ve, relevant and
engaging learning experiences.
All of our educa�onal establishments will
adopt the strategy from 2025 to 2026
onwards as part of the approach to raising
atainment.
Members of our Educa�on Execu�ve Team
met with the Associa�on of Directors of
Educa�on in Scotland (ADES) Quads group
(Dundee, North Ayrshire, Glasgow City
and North Lanarkshire Council) to iden�fy
areas of common improvement for the
next academic session. Senior Managers
will visit Dundee to gather informa�on
around their improvements in
Achievement of Curriculum for Excellence
Levels for Literacy Primary One, Primary
Four, and Primary Seven in May 2025.
Our Cyber Explorers programme focuses
on enhancing the cyber skills of our young
people aged 11 to 14 years old. The
ini�a�ve is designed to engage young
people with cyber security concepts,
digital skills and poten�al career
opportuni�es in the field of technology.
With educa�on increasingly integra�ng
digital tools, Cyber Explorers presents a
unique opportunity for our young people.
Delivery of the programme began in late
2024 in Greenwood Academy with Second
Year pupils. The programme was delivered
during �metabled compu�ng classes and
was carried out as a group to ensure
everyone could proceed at the same pace.
Some of the comments from par�cipants
included: 
“I will take compu�ng a�er doing this, I
love gaming.” 
“I thought this was really fun, and I
learned a few things from it, coding is my
favourite.”  
Free School Meals
There is strong evidence of the posi�ve
impact that a nutri�ous meal can have on
a pupil’s learning and achievement in
school as well as on their health
outcomes. Free school meals (FSM) also
save North Ayrshire families who take up
the offer almost £400 per eligible child per
year. The latest phase of the expansion of
FSM launched on 24th February. This
phase will encourage families of Primary
Six and Primary Seven pupils in receipt of
the Sco�sh Child Payment to register.
Lifelong Learning Opportuni�es
The Mul�ply project focused on
suppor�ng maths skills and qualifica�ons
in adults. To deliver Mul�ply we worked
with partners including CHAP, TACT,
University of Highlands and Islands,
Ayrshire College and 15 community
organisa�ons. Throughout the year
Mul�ply delivered 521 ac�vi�es including
one to one support, group work,
community based programmes and
support drop-in sessions. 2,339 adults
par�cipated with 505 achieving
qualifica�ons. Referrals over the project
were received from a wide range of
services, including Neighbourhood
Networks Ltd, the Church of Scotland,
Social Services, the NHS, Employability,
Financial Inclusion, Customer Services, the
Department for Work and Pensions
(DWP), Turning Point and HSCP services.  
Working with local third sector
and na�onal organisa�ons
we con�nue to provide
access to learning
opportuni�es. The
adult learning

Page 56

Our Council Plan Progress Update – Year End 2024 to 2025 Page 8 of 56
programme supports increased
confidence, progression into further
learning, training or employment, reduced
social isola�on and enhanced community
engagement.
Mental Health & Wellbeing
A key focus for our Community Learning
and Development team has been
suppor�ng schools by delivering our
‘Bounce Back Your Resilience’ youth work
programme. This programme is delivered
by our young people in local primary
schools, is tailored to empower Primary
Six and Seven pupils across North Ayrshire
and helps our Youth Work Modern
Appren�ces to gain experiences in
suppor�ng emo�onal awareness. Upon
comple�on of the six-week programme,
pupils become ‘BeeYou Mental Health
Ambassadors’ for peers in their primary
school. The interac�ve sessions have
raised our children and young people’s
knowledge on:
• What is mental health
• Resilience
• Social Networks
• Friendships and bullying
• Making decisions
• Self-Care
Feedback from pupils has been posi�ve:
“You all helped me realise not to care so
much about what others think.” 
“The youth workers were all amazing
there was nothing I didn’t like.” 
“I have learned to believe in myself and
try to stop doub�ng myself if I fail.” 
Our annual Youth Forum was held at
Ardeer Community Centre on Saturday
22nd February, which brought 50 young
people aged between 12 and 25 years
together to network, share their ideas and
influence local decision making. The day
had a series of workshops including
Money and Mental Health with training
provided by Change Mental Health and
Mental Health UK. Youth groups and
representa�ves in atendance included
North Ayrshire Ac�ve Schools (NAAS)
team, Kilwinning Youth Forum, North
Coast Youth Forum, Garnock Valley Youth
Forum, our council’s Youth Execu�ve (with
pupils from across North Ayrshire
secondary schools), Garnock Valley Youth
Synergy, the Umbrella Club and Members
of Sco�sh Youth Parliament (MSYPs).
Feedback on the day was encouraging
with our young people sharing:
“It was good to develop tools to help us in
the future with managing money and also
overcome the hurdle of speaking about
money openly.”
“I’m excited about my ideas being shared
with people in the council so that I can do
my part to make a difference in other
schools.”
“I feel really good and it felt brilliant to be
actually listened to.” 
Equali�es
Our Ayrshire Shared Bri�sh Sign Language
(BSL) Local Plan 2018 to 2024 Final Report
and Ayrshire Shared BSL Opera�onal Plan
2024 to 2030 was approved by Cabinet in
January 2025. This plan con�nues to align
to the key aims within the Sco�sh
Government strategy and support our BSL
community across East, South and North
Ayrshire.
Care Experienced Young
People
We are commited to
keeping the promise

Page 57

Our Council Plan Progress Update – Year End 2024 to 2025 Page 9 of 56
and ensuring all care-experienced children
grow up loved, safe and respected,
enabling them to reach their full poten�al.
In October, our council took part in our
‘Care Experienced Week Celebra�on’. The
purpose of the event was to celebrate the
work of North Ayrshire-wide Corporate
Parents and the achievements of our Care
Experienced young people over the past
year.  We highlighted the development of
the Champions Board and Promise
Champions Network. This Included a
feature on employability support, an
introduc�on from our Promise Delivery
Partner and an on-stage discussion with
Corporate Parents from Mo�va�on,
Commitment and Resilience (MCR)
Pathways, Ac�ve Schools, Educa�onal
Psychology, Dance Therapy and the
English for Speakers of Other Languages
(ESOL) Hub based in Auchenharvie
Academy. 
The event was atended by 61 adults and
young people with engagement from
Corporate Parents and our young people.
Atendees commented on a good balance
of content between our work, North
Ayrshire-wide ac�vi�es and our young
people’s work. 
This event was very important in terms of
our Youth Work and Community Learning
and Development Strategic Plan Priori�es
to:
• Highlight posi�ve des�na�ons that our
young people can and have accessed.
• Share young people’s experiences in a
non-s�gma�sing way.
• Promote and celebrate our young
people’s health, wellbeing, atainment
and achievement.
• Showcase the ways we are reducing
poverty and inequality for our Care
Experienced young people.
• Provide feedback to our young people
about what has happened over the
past year in response to what they
have said they wanted to see improve
or con�nue.
Ayrshire Area Support Team
Our Ayrshire Area Support Team (AST) is
responsible for helping administer the
opera�ons of Children’s Hearings Scotland
(CHS).  In December they welcomed the
Na�onal Convenor of Children’s Hearings

Page 58

Our Council Plan Progress Update – Year End 2024 to 2025  Page 10 of 56
Scotland to celebrate the first anniversary
of the new ‘Tribunal Support Model’
which was rolled out across Scotland in
December 2023. At the mee�ng, the AST
was praised for its achievements over the
past year.  This included strong leadership,
sharing best prac�ce and innova�on, and
commending the AST for being a high
achieving region where the Clerking team
has a strong reputa�on across the county
for hard work and support of its
volunteers, par�cularly with their
wellbeing. Partnership working with
colleagues across the Health and Social
care Partnership, Educa�on, Champions
Boards and advocacy providers was also
highlighted.
The North Ayrshire Wellbeing Alliance
As part of The North Ayrshire Wellbeing
Alliance‘s focus on ensuring everyone is
given an opportunity to enjoy life and
cope with challenges, a pilot with the
Local Employability Partnership (LEP) in
Blacklands, Kilwinning, has been designed.
This pilot will look at holding a series of
family fun and drop-in events in April to
bring the community together in an
engaging and informal way via:
• Fun ac�vi�es for all ages with
refreshments.
• Free wellbeing checks.
• Opportuni�es to connect with local
services.
• Informa�on on volunteering, health,
lifestyle, training and employment
support.
Leisure Facili�es
In March 2025, Auchenharvie Leisure
Centre hosted the World Wheelchair
Curling Championships. We worked
closely with colleagues from KA Leisure,
Curling Scotland and other na�onal bodies
to deliver this event at short no�ce. It is
the only Olympic or Paralympic Qualifying
Event which will be held in the United
Kingdom during 2025.
The Duke of Edinburgh atended the event
as Patron of the Bri�sh Paralympic
Associa�on. He also visited the Doon the
Beach project in Stevenston, one of the
many examples of community led ac�vity
within North Ayrshire which offers
employability support and leisure
ac�vi�es as well as a café facility. In
recogni�on of the contribu�on they make
the Duke met with some of the volunteers
to learn more about the projects. 
Housing
Our Strategic Housing Investment Plan
2025 to 2030 was approved in December
2024 and submited to the Sco�sh
Government. The Strategic Housing
Investment Plan (SHIP) is reviewed
annually and sets out the priori�es and
loca�ons for affordable housing
investment by our council and registered
social landlords in North Ayrshire for a
five-year period. The focus of our plan is
to deliver the Sco�sh Government’s
Affordable Housing Supply Programme
(AHSP) to ensure affordable housing in
North Ayrshire. The provision of new build
housing has many benefits, including
helping to regenerate the area, providing
sustainable housing solu�ons which help
address fuel poverty and support
educa�onal atainment. It also assists our
ageing popula�on and people with
addi�onal needs to live more
independently. During 2024 to 2025 we
delivered 71 new homes at the following
loca�ons across North
Ayrshire:
• Former St Mary’s
Primary school
site, Largs.

Page 59

Our Council Plan Progress Update – Year End 2024 to 2025 Page 11 of 56
• Former Stanecastle School site, Irvine.
• James McFarlane School site,
Ardrossan.
• Newhouse Drive site, Kilbirnie.
• Laburnum Avenue site, Beith.
• Ayrshire Central Hospital Site, Irvine.
• Garnock Academy site, Kilbirnie.
• Former Kings Arms Hotel, Irvine.
Our Local Housing Strategy 2023 to
2028 annual update was approved at
Cabinet in January 2025. We included a
new ac�on that supports the work
undertaken by the Arran Housing Task
Force established in 2023.  This involves a
wide range of partners to assess the
demand for affordable housing on Arran
and iden�fy issues that may be limi�ng
economic sustainability and growth. A
survey commissioned by the task force is
ongoing to seek opinions on the current
housing provision on the island as well as
future aspira�ons. The survey is open to
homeowners and tenants, landlords,
second homeowners, business owners,
anyone living and working on the island as
well as those considering moving to Arran.
The Sheltered Housing Reprovisioning
Programme con�nues to be implemented.
The next phase planned for refurbishment
includes Laigh Court in Beith and
Vineburgh Court in Irvine.
We con�nue to invest in and maintain our
current housing stock and our estates. We
are proac�vely installing sustainability
measures to ensure they are as thermally
efficient as possible to reduce fuel bills for
tenants. Measures include installing
external wall insula�on and solar
photovoltaic (PV) technology to suitable
proper�es. We are also undertaking a
pathfinder project to explore a 'whole
house' retrofit approach to our exis�ng
homes. This will inform future asset
investment for different property types to
achieve our energy efficiency targets and
reduce fuel costs for our tenants.
Wellbeing Hub
A non-recurring investment of £300,000
was approved by Council in February to
support the explora�on of a new
wellbeing enterprise hub at the former
Greenwood Academy conference centre.
The hub will support the co-loca�on and
development of local third sector
organisa�ons focused on various aspects
of wellness alongside learning
opportuni�es for our young people. A
feasibility study to explore the viability of
a hub and poten�al opera�ng model will
be progressed during 2025.
Great Harbour, Irvine
Our Great Harbour project con�nues with
construc�on on site at Irvine Beach Park.
Our Coastal Hub Play Park is due for
comple�on by the end of September
2025, followed by a new skate park and
pump track and improvements to
connec�ons to the area and around the
Grade B listed Pilot House building. 
When complete, the Coastal Hub area will
provide improved outdoor space and
facili�es for a range of ages and abili�es.
The naming of the play park was discussed
with schools and local groups and an
event has been arranged involving local
schools to announce the chosen name in
June 2025. Design work for Phase 2, the
Mari�me Mile, along Harbour Street, will
commence in June 2025 with stakeholder
engagement taking place as part
of the development work.

Page 60

Our Council Plan Progress Update – Year End 2024 to 2025  Page 12 of 56
Next Steps
• Through our new Child Poverty
Strategy Team – and liaising through
the Community Planning Partnership
(CPP) and CPP Senior Officers’ Group -
we will con�nue to bring a more
systema�c approach to addressing
child poverty in North Ayrshire. This
will include the co-design of place-
based tests of change with partners
from the third sector.
• We will establish our local priori�es
and areas for ac�on as part of the
Collabora�on for Health Equity in
Scotland programme. 
• We will consolidate our financial
inclusion services and rebrand as
“Money Smart”.
• We will explore a debt advice resource
for non-council tenants to enable a
seamless internal pathway to debt
advice. 
• We will roll out the Performing
Engineering Opera�ons (PEO) course
currently available at Ardrossan
Academy to all secondary schools from
August 2025. This course provides
fundamental engineering skills, o�en
for beginners in the field.
• We will review research commissioned
by our council into the poten�al
op�ons for developing CWB
approaches at a locality level including
considera�on of unique island
contexts.
• We will work with anchor ins�tu�ons
to deliver CWB across Ayrshire through
the CWB Commission, Regional
Economic Strategy Delivery Group and
CWB Anchor Charter.
• We will progress the delivery of our
Levelling Up Fund Round 3
Commercial and Low Carbon
Infrastructure project. 
• We will con�nue to provide support
for local enterprise through the
Business Recovery and Sustainability
Fund.
• We will reach Financial Close on the
new Ardrossan Community Campus
and start the construc�on process.
This transforma�onal redevelopment
will bring significant investment to one
of our most deprived communi�es.
• Our Tenant Inspec�on Panel will
scru�nise our Aids and Adapta�ons
provision.
• We will con�nue to deliver new build
housing and regenera�on programmes
to deliver sustainable housing
solu�ons.
• We will progress the review of our
North Ayrshire Housing Register
Alloca�ons Policy.
• We will further develop the Disability
Employment Hub at Lochshore Park.
• We will seek the approval of the Irvine
Neighbourhood Plan by winter 2025.
• We will further consult and engage to
inform the development of the
investment plan in rela�on to the Plan
for Neighbourhoods.
• We will support the delivery of the
Ayrshire Regional Economic Strategy
and Highlands and Islands Economic
Strategy.
• We will work with island stakeholders
to influence the development of the
new Na�onal Islands Plan for Scotland
due for publica�on in late 2025.
• We will review the Arran Task
Force Survey assessing
the demand for
affordable
housing on
Arran.

Page 61

Our Council Plan Progress Update – Year End 2024 to 2025 Page 13 of 56
Case Study - Winter Warmer Breakfast
The Winter Warmer Breakfast returned for a third year offering free breakfasts across all
nine secondary schools and Lockhart Campus.
During Winter 2024 to 2025, the free breakfast was available from the beginning of
November 2024 and ran un�l the end of March 2025. 
A range of hot and cold breakfast items were available for all secondary school pupils
designed as a ‘grab and go’ service.  Each year the catering teams have refined the service to
ensure it con�nues to meet the needs of our young people.  The winter of 2024 to 2025 saw
the highest uptake of this service over the three years it has been running, with an average
of 1,200 items being served every school day and a total of over 100,000 breakfast items
being distributed over five months.
A posi�ve unintended consequence of this provision has been an increase in pupils eligible
for free school meals not using their lunch credit at morning break.  They are instead using
their credit at lunch�me to access a full lunch as intended. 
Hidden hunger is an issue in secondary schools as pupils are free to leave the school grounds
at breaks, therefore there is no way of knowing if pupils are accessing food if they are not
atending the school dining facility.  This service helps to address the issue of hidden hunger
even if just in a small way, by offering dignified free food provision at breakfast.
School breakfast provision is intended to address classroom hunger and strengthen
academic performance by improving children’s energy, concentra�on, behaviour and overall
readiness to learn.

Page 62

Our Council Plan Progress Update – Year End 2024 to 2025 Page 14 of 56
Communi�es and Local
Democracy
We will have ac�ve, inclusive and
resilient communi�es.
Key Ac�vi�es
Community Learning and Development
Youth Work 
In the final six months of 2024 to 2025
youth work programmes and ini�a�ves
reached 5,164 young people aged under
12 years old and 6,582 young people over
12 years old.
Key areas of focus and achievement
include:
• Early Interven�on and Founda�onal
Skills (Under 12s): Programmes
focused on building founda�onal
social skills, promo�ng healthy
lifestyles, fostering crea�vity, and
encouraging early engagement in
community ac�vi�es.
• Empowerment and Future Pathways
(Over 12s): Ini�a�ves concentrated on
developing leadership skills, enhancing
employability, promo�ng mental and
physical well-being, and facilita�ng
ac�ve par�cipa�on in local decision-
making.
• Community Cohesion and Partnership
Working: We con�nued to strengthen
our partnerships with schools, local
community groups, third-sector
organisa�ons, and other council
services.
Youth work is having a posi�ve impact on
our young people such as:
• Improved Mental Health and
Wellbeing: Through targeted
interven�ons and suppor�ve
environments, we contributed to
improved mental, physical, and
emo�onal well-being with 6,971
par�cipants.
• Equality in Community Connec�ons:
Our programmes fostered a sense of
belonging and encouraged ac�ve
par�cipa�on in community life,
including work with 189 New Scots
young people, targeted work with our
care experienced young people and
the crea�on of our equali�es youth
network.
• Cyber Resilience: This year has seen
the roll out of our Cyber Explorers
work, with our young people achieving
their SCQF Level four and five,
equipping them with cyber skills for
life and future employment, with 704
accounts ac�vated, 139 comple�ng
SCQF Level four and 53 achieving SCQF
Level 5.
Members of the Sco�sh Youth Parliament
Our local Members of the Sco�sh Youth
Parliament (MSYPs) atended the na�onal
si�ng of the Sco�sh Youth Parliament in
October. As part of the Youth Parliament,
they were involved in delivering their
mo�ons in the deba�ng chamber at
Holyrood. There were 15 mo�ons raised
covering a range of issues including an�-
social behaviour, broadband for rural
areas, global climate reputa�on,
protec�ng university funding, cost of living
educa�on, xenophobia and racism,
training for transport
workers, vaping adverts,
Gaelic educa�on,
mental health in
curriculum,

Page 63

Our Council Plan Progress Update – Year End 2024 to 2025 Page 15 of 56
femicide, student and appren�ce support,
period products and including Bri�sh Sign
Language in the curriculum. 
Our MSYPs really enjoyed the event. As
well as mee�ng other MSYPs, they had the
opportunity to meet Members of the
Sco�sh Parliament at a parliamentary
recep�on. This meant they could discuss
their roles and the work they are involved
in locally. They felt immensely proud of
their opportunity to sit in the deba�ng
chamber that would normally be filled
with MSP’s and represent not only their
local communi�es but young people from
across Scotland. 
Duke of Edinburgh Awards
Record numbers of our young people
par�cipated in the Duke of Edinburgh
Award scheme in North Ayrshire this year.
The numbers of par�cipants at each level
were: Bronze: 696, Silver: 252, Gold: 58.
An awards ceremony was held at St
Mathews Academy in March to recognise
the achievement of our young people
comple�ng their awards, where 182
received a bronze award, 59 Silver and 11
Gold.
Older People 
Our Community Learning and
Development teams, in partnership with
Locality Workers and residents across
North Ayrshire, hosted an Older People’s
Conference at Saltcoats Town Hall in
February as part of our Older People’s
Voice Par�cipa�on Strategy. The event
welcomed over 60 atendees.
With a focus on ensuring older voices are
heard, respected and acted upon,
especially around issues like local service
delivery and the impact of climate change,
the conference promoted meaningful
dialogue and collabora�on. Atendees
learned about local ini�a�ves addressing
social isola�on and felt more confident
about accessing and par�cipa�ng in these
opportuni�es. New connec�ons were
made across our locali�es. The promo�on
of Discovery Groups, a learning award for
those aged over 50 years, led to increased
registra�ons and a wide range of skills
being shared. One recent newcomer to
the area discovered local ac�vi�es
through the event and has since been
elected secretary for her local community
associa�on. 
New Scots
Our Community Learning and
Development team hosted the first
mee�ng of Afghan women from across
North Ayrshire at the Towerlands
Community Centre. This ini�al mee�ng
was in recogni�on of several new Afghan
families who are geographically diverse
and isolated. All of the women were
invited to an ini�al mee�ng to discuss
whether group ac�vi�es would be helpful
and what they would like to be involved
in. The group has agreed to meet monthly
to con�nue to develop friendships,
networks and reduce isola�on. They also
requested opportuni�es for men and
children to meet and network, so in
partnership with the Health and Social
Care Partnership an Afghan Family fun day
is planned for early April. 
Community Grants and Funding
Par�cipatory Budge�ng (PB) enables
communi�es to have a say in how council
budgets are used. Our 2024 to 2025 small
grants PB saw 15,882 votes cast
across North Ayrshire. To
make sure that as many
residents as possible
were able to have
their say in the

Page 64

Our Council Plan Progress Update – Year End 2024 to 2025 Page 16 of 56
process, we not only used our online
Consul pla�orm for vo�ng but also offered
paper-based vo�ng opportuni�es
alongside Consul. This ensured that
individuals and groups who don’t have
digital access or may find using online
tools difficult could s�ll contribute and
have their say. Our young people also took
part in both Youth and Locality PB
processes, using the Consul online
pla�orm to vote and give their views. 
£171,377 was awarded to 190 groups
across North Ayrshire through the small
grants PB process. This funding enabled a
wide range of community-led projects and
ini�a�ves to address local needs. A diverse
range of projects were funded which
focused on youth services, community
wellbeing, environmental improvements,
and support for vulnerable groups. 
8,620 young people contributed to Youth
PB by ac�vely par�cipa�ng in online
vo�ng, deciding on how local money was
spent to enhance or create new projects
for our young people. Our digital approach
to PB, par�cularly around Youth PB, was
included as an example of good prac�ce at
the interna�onal Consul Conference in
February. 
We reviewed how well small grants PB
worked during 2024. This review collected
feedback and recommenda�ons from our
community PB Champions, and our
employees including Modern Appren�ces
who are involved in its delivery. We used
this feedback to create an in-person
session which will help to develop the
approach for the next round of PB.
Community reviewers will also be invited
to provide their feedback and
recommenda�ons on the last cycle.  
Our Community Investment Fund (CIF)
con�nued to support locality-based
projects which contribute to delivering our
priori�es. Locality Partnerships awarded
funding to a range of groups across North
Ayrshire including:
• £41,000 for Beith Hive to support
transport connec�vity for childcare in
the Garnock Valley.
• £49,500 for Irvine Cricket Club to
improve and expand their facili�es to
allow more par�cipa�on in the sport
from local families.
• £25,000 for Corsehill Community
Associa�on to progress with
redevelopment of the local play park.
• £92,685 for Largs Development Trust
to develop a local community hub and
associated ac�vi�es including
community radio.
• £100,000 for Winton Rovers to renew
their stand roof as part of a major
redevelopment package aimed at
improving the facili�es on offer to the
community.
Our Connected Communi�es teams,
together with colleagues from the Third
Sector Interface, con�nue to provide
support and informa�on to local groups
about the funding opportuni�es available
to them. 
Our Communi�es and Place Fund and
Repurposing Property Grant Fund
con�nued to support local community
organisa�ons to deliver a broad range of
projects and develop proposals to bring
vacant and derelict land and property into
posi�ve use.

Page 65

Our Council Plan Progress Update – Year End 2024 to 2025 Page 17 of 56
Community Planning Partnership
Developing our work remains a key
feature in how our Community Planning
Partnership (CPP) func�ons. We have now
embedded our Child Poverty and Cost of
Living programme of work as part of our
main CPP ac�vi�es, in recogni�on of the
need for a partnership approach and the
centrality of the work to our priori�es.
Our focus is on understanding where we
can work together as partners, including
our residents, to use our resources most
effec�vely and improve the lives of our
children, families and communi�es. 
Our ongoing development work with the
Third Sector Chief Officers Group, which
brings together key stakeholders from the
third sector within North Ayrshire, has
been codesigning projects to develop our
strategic understanding and the sector’s
capacity. These projects focus on two
areas which our council has earmarked
funds to support, firstly Child Poverty and
the Cost of Living and secondly,
developing our Community Wealth
Building aims within our communi�es. 
During the year we undertook a review of
our Locality Planning arrangements.
Locality Planning is a way of bringing
together communi�es, council
services and partners to address local
priori�es and reduce inequali�es.
With support from our community
members and partners, we iden�fied
improvements including a more
interac�ve approach to Locality
Partnership mee�ngs, a renewed focus
on our Locality Plans and stronger
leadership to support the Partnerships
in their work.  The recommenda�ons
have been approved by Cabinet and a
programme of work to implement
them is now underway.
Community and Voluntary Sector
The Third Sector Chief Officers Group
con�nues to go from strength to
strength. We are transforming our
partnership with the community and
voluntary sector, recognising the vital
role they play in delivering lifeline
services and support to many
vulnerable people. The
group has co-designed
a programme of
work, including
considera�on of
how we

Page 66

Our Council Plan Progress Update – Year End 2024 to 2025 Page 18 of 56
strengthen community wealth building at
a locality level. The group has also
collaborated to develop a number of
innova�ve proposals to be supported
through our council’s Child Poverty and
Early Interven�on Fund.
Community Asset Transfer
Community Asset Transfer (CAT) involves
the transfer of responsibility for an asset
from our council to any suitably qualified
community, voluntary or social enterprise
group. For context, assets may include
public halls and community centres, public
conveniences, parks, sports facili�es and
play areas. In the previous 12 months, our
CAT team has received 17 expressions of
interest - ini�al enquiries that allow us to
ascertain if the asset is available and if the
group is a compliant applicant.  
Earlier this year, our Cabinet agreed to
approve the asset transfer of the Brisbane
Centre to Clyde Coast and Cumbraes
Men’s Shed at the recommended terms of
transfer of 5% of the property valua�on of
£74,000 (totalling £3,700). The Clyde
Coast and Cumbraes Men’s Shed moved
into the Brisbane Centre in October 2022.
Since then, they have been delivering a
valuable service and successfully
opera�ng the facility in the heart of the
local community. Further developments
include: 
• Enhancing the facility to meet the
specific needs of the Men’s Shed -
allowing the club and its members to
expand and grow.
• Increasing membership, thus widening
involvement with the local community
and deepening the impact of their
work.
• Providing stability and a strong base
from which to operate and deliver
events to support the wider
community. 
Plan for Neighbourhoods
Irvine is one of fi�y-five towns benefi�ng
from up to £20 million of investment
through endowment style funding over a
10-year period. The Irvine Neighbourhood
Board is collabora�ng with our council to
develop the objec�ves and projects for
the ini�al four-year neighbourhood plan.
The Plan for Neighbourhoods, previously
known as Long-Term Plan for Towns, seeks
to place communi�es at the heart of the
decision-making process and to provide
the funding to support delivery.
The programme requires a partnership
approach between our council, the
Neighbourhood Board and the
community. A ten-year vision for the town
and more detailed four-year investment
plan must be approved by UK Government
prior to implementa�on by winter 2025.
Further consulta�on and engagement are
planned in 2025 to 2026 to inform the
development of the investment plan.
Tenant Sa�sfac�on 
Overall service sa�sfac�on among North
Ayrshire Council tenants has risen to 92%,
marking an improvement on the previous
result for 2021 of 88.74%. Our three
yearly tenant sa�sfac�on survey ran from
November 2024 to January 2025, with
1,490 responses represen�ng 40% of all
our sampled tenants.  
As part of our ongoing commitment to
consulta�on and improvement, the survey
covered several important
issues rela�ng to our
tenant’s homes, the
service we provide
and their local
neighbourhood.  An

Page 67

Our Council Plan Progress Update – Year End 2024 to 2025 Page 19 of 56
ac�on plan is currently being developed to
further improve our service. 
Islands 
North Ayrshire Islands Programme was a
finalist in COSLA’s Excellence Awards in
the category of ‘Strengthening
Communi�es and Local Democracy’, in
recogni�on of the unique partnership
approach taken. We con�nue to work
closely, posi�vely and progressively with
partners to ensure the Island Plan
priori�es are front and centre of local
decision making where possible. 
We have been ac�ve in the development
of the new Highlands and Islands Regional
Economic Strategy, led by Highlands and
Islands Enterprise (HIE) with collabora�on
and input from across the Regional
Economic Partnership membership. 
It outlines the strategic approach to
economic development for the Highlands
and Islands region, including the islands of
Arran and Cumbrae and sets out the
collabora�ve opportuni�es and ac�ons for
the Highlands and Islands Regional
Economic Partnership. This includes a
range of policy areas such as Housing,
Popula�on Atrac�on and Reten�on, Skills,
Childcare, Local Visitor Levy, Community
Wealth Building and Community Benefit.

Page 68

Our Council Plan Progress Update – Year End 2024 to 2025 Page 20 of 56
Next Steps
• We will implement the recommenda�ons
of our review of Locality Planning with our
communi�es and partners.
• We will further embed our locality-based
approaches to service delivery and
decision making within our council.
• We will hold dedicated network mee�ngs
and informa�on days for older people as
well as pop up informa�on sessions.
• We will deliver our essen�al skills adult
learning programme with support from UK
Shared Prosperity Funding.
• We will develop a coordinated partnership
approach to recrui�ng, suppor�ng and
recognising our volunteers in North
Ayrshire.
• We will work with the University of the
West of Scotland to promote qualifica�ons
and support upskilling our employees and
volunteers in Community Educa�on.
• We will make progress on the priori�es
iden�fied through the Community Asset
Transfer Start-up Fund review.
• Well will complete our comprehensive
approach to applica�on, assessment
award and compliance in rela�on to
community funds and grants.
• We will con�nue to work with the Third
Sector Chief Officers Group to codesign
solu�ons.
• We will con�nue to develop our new
virtual Community Directory for
community members in crisis.
• We will prepare our CPP Project Plan for
2026 to 2027.
• We will carry out Community and Locality
Planning training sessions for partners and
community representa�ves.
• We will test our streamlined Council Tax
process with our Lived Experience Group
in November.
• We will refresh our Local Island Plans
following the review of Locality
Partnerships and the launch of the new
Na�onal Islands Plan for Scotland.
• We will work in partnership with our
island communi�es to maximise the
opportuni�es from the Sco�sh
Government Islands Programme, Cost of
Living Crisis Emergency Fund (COLCEF) and
Carbon Neutral Islands Capital Fund.
• We will contribute to an inaugural Islands
Economy Showcase at the Sco�sh
Parliament in April.

Page 69

Our Council Plan Progress Update – Year End 2024 to 2025 Page 21 of 56
Case Study – Towerlands Graffi� Mural
In response to a recent surge in vandalism at Towerlands Local Community Hub, Irvine, a
unique restora�ve project was created in partnership with the Irvine Locality Partnership
and Locality Team, our Council, Police Scotland and commitee members from Towerlands
Community Centre. 
Five young people were involved in a mural project established as part of the Locality Ac�on
Plan for a targeted group of Greenwood Academy pupils who had played their part in recent
an�-social behaviour. With the help of local graffi� ar�st, Tragic O’Hara, the pupils
par�cipated in six restora�ve youth work sessions at Towerlands Community Centre. 
The aim of the Cyber Explorers mural project is for our young people to create a historic
graffi�-inspired design where they can come together to celebrate the value of their local
community centre and give something back. The group collaborated to map out a design
with key elements celebra�ng community groups such as the kni�ng club, Irvine Pipe Band
and the Dachshund Group who all operate out of the hub.
Engaging with commitee members from Bourtreehill and Broomlands Community
Associa�on (BABCA), the next phase will see the crea�on of a mural to promote the centre
to passers-by. This will depict the history of the community centre, celebrate what the
vibrant community hub offers and how the hub sets its sights on the digital age. 
This work symbolises regenera�on and resilience and offers the young par�cipants an
opportunity to be responsible, crea�ve, collaborate and demonstrate how shared ar�s�c
engagement can help strengthen and rebuild community rela�onships.
Police Constable, Irvine Locality Policing Team:
“Working with our partners and youngsters in the local area, we’ve been
able to emphasise the importance of facili�es like this and try to prevent
criminal ac�vity. We’ve developed an understanding with these teens,
which is helping to improve rela�ons between groups of youths and police
in the area and will benefit the whole community going forward. This
project has also allowed youngsters to channel their energy and learn skills
which they can use for their future”

Page 70

Our Council Plan Progress Update – Year End 2024 to 2025 Page 22 of 56
Case Study – Storm Eowyn
When Storm Eowyn swept across Scotland in March, bringing gale force winds of up to
100mph and widespread flooding, North Ayrshire experienced some of the storm’s most
intense effects, triggering an immediate and determined response to protect residents and
keep cri�cal services running.
As weather warnings intensified, Roads crews were mobilised allowing fallen trees and
debris to be cleared quickly and efficiently ensuring emergency access and restoring key
transport links.
To protect residents and staff, we made the early decision to close council buildings for the
dura�on of the storm. Our council priori�sed support for vulnerable individuals, carrying out
welfare checks through our care networks, as well as delivery of food parcels. Temporary
drop in hubs were made available across several of our community facili�es where
prolonged outages were iden�fied. Addi�onally, our Building Services Repairs Team
responded to emergency repairs.
People were kept informed through regular updates on our social media channels and our
customer services helpline was available to provide advice, support and emergency referrals,
handling almost 3,000 calls within the first 72 hours.
There were 917,371 social media impressions (number of �mes people had the opportunity
to view our posts on their social feeds). These included posts shared from other accounts
and pages such as Sco�sh Fire and Rescue, Transport Scotland, Police Scotland and the Met
Office. Addi�onally, we kept our employees informed through our own internal
communica�ons. In the wake of the storm, we launched a review into storm resilience,
focusing on infrastructure investment, flood mi�ga�on and strengthening community
preparedness.
Storm Eowyn tested our resilience but the response from council services, mul�-agency
partners and volunteers demonstrated what is possible when communi�es come together.

Page 71

Our Council Plan Progress Update – Year End 2024 to 2025 Page 23 of 56
Climate Change
To achieve net-zero by 2030.
Key Ac�vi�es
Energy
The ECO4 Flex scheme provides funding
for energy efficiency improvements in
homes, primarily targe�ng low–income
and vulnerable households. The scheme,
part of the wider Energy Company
Obliga�on (ECO) program, offers financial
assistance for measures like insula�on,
hea�ng upgrades and renewable energy
installa�ons. Our funding of £902,809 has
supported 32 households with the
installa�on of over 134 energy saving
measures to improve home energy
efficiency.
Our Local Heat and Energy Efficiency
Strategy (LHEES) is a long-term plan,
developed in line with Sco�sh
Government guidance, to address heat
demand, decarbonise hea�ng and
improve energy efficiency in both
domes�c and non-domes�c buildings.
Since it was launched, we have
established our LHEES Working Group and
engaged with other local authori�es and
distribu�on network operators. In March,
we launched our LHEES procurement
framework to undertake feasibility work
to inves�gate heat network zones and
explore our role in localised heat networks
to support low carbon affordable warmth.
Biodiversity
In response to the Global Climate and the
Nature Emergency, the Sco�sh
Government launched its Sco�sh
Biodiversity Strategy to 2045 which states
local authori�es will be responsible for
delivering a Nature Network in their own
area. In response, our Cabinet approved
our North Ayrshire Nature Network
(NANN) strategy in March 2025. The
delivery of this strategy will involve
considerable community buy in,
partnership working and
interdepartmental coopera�on. The
inten�on is to establish:
• An explana�on of what Nature
Networks are and what they will
deliver.
• The na�onal and local policy context.
• A methodology for developing a
Nature Network for North Ayrshire,
following the NatureScot Nature
Network delivery guidance.
• An ac�on plan for the implementa�on
and delivery of the NANN.
49,026 trees have been planted in line
with our 2030 Woodland: A Tree Plan�ng
Strategy through various projects and by
community partners. This remains a key
focus, with support being provided to
local community groups and the
assessment of suitable plan�ng sites and
species for our council's tree plan�ng
con�nuing.  A proposal to plant a further
5,500 trees in the Annick Valley Park has
been well received with plan�ng
scheduled for Autumn 2025. 
Plan�ng of an addi�onal 2,420 mixed
species of trees at Milgarholm in Irvine
has now been completed. A new grounds
maintenance management plan for
Lochshore Park in Kilbirnie is being
implemented. This will include a habitat
management plan which is being created
jointly between our council and the
Friends of Lochshore volunteer group. We
have also assisted in facilita�ng plan�ng of
120 fruit trees by the Friends of
Stevenston Conserva�on
Group, in
Auchenharvie,
Stevenston.

Page 72

Our Council Plan Progress Update – Year End 2024 to 2025 Page 24 of 56
Net Zero Accelerator
The Net Zero Accelerator (NZA)
programme which helps businesses
increase sustainability, reduce their
carbon footprint and work towards
elimina�ng greenhouse gas emissions, has
progressed with a number of projects
being developed to reflect our business
base. As part of phase one, cohorts have
been developed with Net Zero Na�on and
partners. We have also further developed
phase two with an aim to embed and
develop enhanced green adop�on and
skills development for those businesses
seeking to enhance their sustainability
opportuni�es.
Other NZA workstreams developed and
supported include:
• Locally Owned Energy Projects:
Collabora�ve buying consor�um.
• Carbon Assistants Training
Programme:  Upskilling employees to
develop skills in Carbon Accoun�ng.
• Solar Funding Challenges to support
energy cost saving.
• Circular Economy – Suppor�ng waste
reduc�on and new product
development.
The first of its kind islands NZA has been
developed, specifically aimed at the
unique needs and challenges of island
based businesses. 16 small and medium
sized enterprises (SME) enrolled from the
Isles of Arran and Cumbrae. Part funded
by Zero Waste Scotland, collabora�ve
projects are emerging. 
Waste and Recycling
During the 2024 to 2025 financial year, our
bulky waste reuse partner, Cunninghame
Furniture Recycling Company, collected
902 matresses (24 tonnes) and 212
tonnes of household furniture as part of
an ini�a�ve to promote opportuni�es for
their reuse, assis�ng 1,787 households to
furnish their homes whilst also employing
17 staff within North Ayrshire.
As part of a new Circular Economy and
Waste Route Map for Scotland, our
officers are working closely with COSLA,
SOLACE and the Sco�sh Government
through a co-design process, to develop a
revised statutory Code of Prac�ce for
Household Waste Recycling and key policy
ac�ons. The Route Map and the revised
Code of Prac�ce (expected late 2026) will
be key in informing the development of
our council's Zero Waste Strategy to
explore further opportuni�es for
improving reuse and recycling
performance.
In partnership with deep cleaning
specialists and the volunteering network,
a gum removal ini�a�ve was carried out
addressing chewing gum removal and
preven�on. This involved deep cleaning of
our pavements and use of signage to
encourage proper disposal.
The 'Sea Starts Here' campaign with the
Irvine Clean Up Crew to raise awareness of
the impact of marine liter is ongoing. A
key method of raising awareness has been
the use of semi-permanent stencilling on
our pavements, displaying messages such
as, “Please Don’t Liter” and “The Sea
Starts Here”. 
The pilot of our 'LiterLoto' liter
campaign has now concluded and has
proved to be extremely successful since its
introduc�on in April 2024. Data is showing
an increase in those disposing of liter
appropriately. In January 2025, 583 items
of liter were binned responsibly by app
users in North Ayrshire and in February
2025 this number increased to
24,089, increasing
further to 24,742 in
March.

Page 73

Our Council Plan Progress Update – Year End 2024 to 2025 Page 25 of 56
The booking system for our four
Household Waste Recycling Centres
(HWRC’s) was approved by Cabinet in
October. The new system will make visits
smoother and quicker, enabling residents
to book slots at recycling sites at a �me
convenient to them.
In addi�on, the change will enable staff to
assist customers to dispose of their
household waste safely and correctly,
minimising contamina�on and improving
recycling. 
Renewable Energy
Our Council con�nues to support wider
ac�on on climate change out with our
own estate. The Community Renewable
Energy Genera�on Fund (a scheme which
offers funding to community organisa�ons
for renewable energy projects) is
promoted during the Community Climate
Ac�on Plan visits with local communi�es.
Four community renewable projects have
been awarded funding through this fund,
totalling approximately £130,000. 
Addi�onal awareness raising ac�vity is
underway to increase the uptake of the
available funding with support from
Connected Communi�es. The
appointment of a new Energy Awareness
Officer will help to promote and engage
with communi�es further in 2025 to 2026.
Our work con�nues at the Solar PV farm
developments at our former landfill sites
of Nethermains and Shewalton. The
installa�on of these is now complete and
the next phase will see the connec�on to
the electricity network and commissioning
works undertaken.
Decarbonisa�on of the Fleet
A Decarbonisa�on of the Fleet Board has
been established to help progress the
wider roll-out of electric vehicles and the
possibility of other fossil fuel alterna�ves.
We have switched 36 refuse collec�on
vehicles from diesel fuel to Hydrotreated
Vegetable Oil (HVO).  HVO, otherwise
known as ‘renewable diesel’, is produced
from waste cooking oil, animal fat and
forestry materials that are saturated with
hydrogen at a high temperature and
pressure in a process known as
hydrotreatment. 
It can be used in vehicles or equipment
designed for standard diesel, without any
changes to the engine or infrastructure,
and can reduce CO2 emissions by up to
90%. Over a 12-month period, there is
poten�al for our council to save around
2,529 tonnes of carbon emissions. 
Work on the next phase of our Electric
Vehicle Workplace charging network has
progressed to procurement stage. This will
support wider electrifica�on of our
council’s fleet. 
Sustainability
Our Sustainability Team has delivered 90
climate change and energy lessons to 29
primary schools to date. The lessons
support awareness of ac�on on climate
change and encourages ac�on within
schools through their climate ac�on plans.
In partnership with Keep Scotland
Beau�ful, we con�nue to support free
energy resources for Secondary Schools.
Development is also underway on a
community carbon literacy training pack
for small community groups in
conjunc�on with APSE Energy for 2025 to
2026.
As part of our Sustainable North Ayrshire
Strategy, a key priority is the crea�on of
Community Climate Ac�on Plans for each
locality. Building on the
momentum of the
Climate Ac�on Town
Stevenston ini�a�ve,
we have engaged
with local groups by

Page 74

Our Council Plan Progress Update – Year End 2024 to 2025 Page 26 of 56
atending community events to explore
poten�al climate ini�a�ves and
understand the barriers they face. The
next phase will see the delivery of three
interac�ve workshops in each locality, co-
designed with community members. 
These sessions will be supported by the
Ayrshire Climate Hub.
In partnership with the Ayrshire Nectar
Network, a project led by the Sco�sh
Wildlife Trust (in partnership with East and
South Ayrshire Councils), we have
supported the establishment of new
wildflower meadows. The ambi�on of this
project is to create pollen rich habitats in
response to the decline of pollinators. We
have provided support to the Friends of
Stevenston Shore and the Friends of
Lochshore.
In partnership with Nature Scotland, we
con�nue our work to implement areas of
naturalised open space to create habitats
for wildlife and encourage bees and
insects through diverse seeding in our wild
meadows. This includes allowing tree
debris to be le� on site (where safe to do
so), to help promote natural habits. We
con�nue to be a key and ac�ve member in
the North Ayrshire Biodiversity
Partnership. A funding applica�on has
been submited for reconstruc�on works
on the banking of Shewalton pond to both
improve access while protec�ng valuable
habitats for flora and fauna.
In November 2024, the third and final
stage of the Fairlie Coastal Path was
completed with the opening of a new,
improved and safer access to the coastline
for residents and visitors to the area (see
case study below). This phase has
completed the link between Bay Street
and the Fairlie Viewpoint path, crea�ng
800m of a con�nuous, traffic free walking,
wheeling and cycling path for people of all
abili�es. 
Travel Smart
Our council’s Travel Smart Behaviour
Change programme con�nues to provide
informa�on and ac�vi�es to the public
and workplaces promo�ng ac�ve travel
and suppor�ng behaviour change.
Through a broad programme of ac�vi�es
aimed to raise awareness and build
confidence, people are encouraged to
walk and cycle more for short journeys.
Short group walks take place across North
Ayrshire enabling par�cipants to increase
their stamina and confidence and develop
a beter knowledge of routes. New and
less confident cyclists receive training to
improve both their on and off-road cycling
skills. Further training is provided for
those wishing to develop their bike
maintenance skills. 
We con�nue to work with Paths for All,
providing walk leader training for people
wan�ng to support exis�ng groups or
develop new walking opportuni�es. We
provide informa�on stalls at libraries,
workplaces and other venues. Since
October 2024 we have delivered over 213
ac�vi�es with over 2,100 people taking
part.
Next Steps
• We will launch our new digital HWRC
booking system.
• We will con�nue to develop
Community Climate Ac�on Plans for
our six locali�es.
• We will con�nue to develop a
Renewable Energy Strategy and
iden�fy projects which may be
suitable for investment.
• We will deliver the North Ayrshire
Network Strategy, aligned
with the Sco�sh
Government’s
Biodiversity
Strategy.

Page 75

Our Council Plan Progress Update – Year End 2024 to 2025 Page 27 of 56
• We will con�nue to work with our
partners at South and East Ayrshire
Councils to procure a concession
contract for the delivery of 307 EV
charge points across the area.
• We will install a new permanent self-
led sustainability trail at Eglinton Park.
• We will con�nue to develop projects
for future Ac�ve Travel and
Infrastructure funding opportuni�es.
• We will con�nue to deliver our Travel
Smart behaviour change programme.

Page 76

Our Council Plan Progress Update – Year End 2024 to 2025 Page 28 of 56
Case Study – Fairlie Coastal Path
In November 2024, the village of Fairlie
celebrated the official opening of the
Fairlie Coastal Path, an accessible
walkway designed to enhance local
connec�vity, encourage outdoor ac�vity
and boost tourism, represen�ng a
significant step forward in sustainable
local development and community
wellbeing.
Forming part of the wider Ayrshire
Coastal Path, the Fairlie Coastal Path is a
1 km route linking key parts of the village
with the nearby shoreline and natural
reserves ensuring a con�nuous traffic-
free walking, wheeling and cycling path
along the waterfront for people of all
abili�es. Developed in close collabora�on with local residents and marine engineers, the
£633,084 project was funded by the Sco�sh Government and designed and delivered
through a partnership between our council and Sustrans.  The path priori�ses accessibility
and includes viewing points, rest areas and safe access to coastal features.
Community consulta�on was central to this project with local residents contribu�ng ideas
for the path’s layout and features through surveys and planning sessions. The strong sense
of community ownership has been key to the project’s success. 
Since its opening, the path has become a popular des�na�on for walkers, cyclists, families
and nature enthusiasts. It has strengthened connec�ons between people and place, offering
a safe welcoming space for recrea�on, learning and social interac�on. Early feedback
indicates increased local foo�all and interest from visitors, providing poten�al extra foo�all
for nearby businesses.
The Fairlie Coastal Path demonstrates how small-scale infrastructure can have a big impact
when rooted in community collabora�on and respect for the natural environment. It not
only improves access and wellbeing but also preserves the unique character of Fairlie’s
coastal landscape for future genera�ons.
Head of Na�onal Cycle Network at Sustrans Scotland:
“We are delighted to see work finish on this phase of the Fairlie Coastal Path project.  When
we make it easier and safer for people to walk, wheel and cycle, we save lives.
This new route has created a vital traffic-free space, enabling residents and
visitors to travel ac�vely along the waterfront away from busy roads,
while accessing key services and the local coastline.”

Page 77

Our Council Plan Progress Update – Year End 2024 to 2025 Page 29 of 56
Case Study – Community Renewable Energy Genera�on Fund
Our council launched the Community Renewable Energy Genera�on Fund (CREGF) in 2023
to support community-led renewable energy projects. CREGF is a compe��ve council fund,
where approved applica�ons are agreed on merit. Funding available for projects is £350k
from our council’s Investment Fund as part of a par�cipatory budge�ng approach to enable
crowdfunding for environmental works. The fund supports our council’s Climate Change
priority, achieving net-zero carbon emissions by 2030. 
The aim of CREGF is to provide one-off funding for projects to increase the level of
community owned renewable energy genera�on opportuni�es and accelerate community
benefits from local renewable energy. To be eligible, applica�ons had to be from cons�tuted
North Ayrshire community groups. Applica�ons from na�onal organisa�ons were also
accepted if their project demonstrated direct benefits to the communi�es of North Ayrshire.
Projects were required, where possible, to include match funding from other non-council
funding sources.
Renewable energy genera�on projects could include solar photovoltaic (PV), wind turbines,
hydropower, heat pumps or green hydrogen. The funding was available for different stages
of projects including feasibility, business case, planning, development or installa�on. It is
expected that any surplus, profit or reduced energy costs delivered by the scheme will be
used en�rely for the benefit of the community group and/or wider community.
So far funding of £128,939 has been awarded to projects within the Garnock Valley, Three
Towns and Arran locali�es. Awards have been granted for the development of a solar PV
farm, wind turbine, air source heat pump and batery storage. Beith Community
Development Trust installed Solar PV on their roof, combined with a batery storage facility
in December 2024. This enabled them to reduce energy use and costs while genera�ng
green renewable electricity. 
CREGF con�nues to be promoted amongst community groups as part of the ongoing work to
develop Community Climate Ac�on Plans (CCAPs). The overall aim of the CCAPs is to lower
the area-wide carbon emissions of North Ayrshire. The CCAPs will contain the climate views
of our communi�es and help to iden�fy climate ac�ons which also support the local
priori�es of each of the six locali�es. These ac�ons can be taken by community groups and
supported by our council. An applica�on to the CREGF can then be made to support the
climate ini�a�ves. 
Our council will con�nue to provide financial assistance by promo�ng the CREGF to support
community-based ac�on. This is a key outcome within the Council Plan Climate Change
priority, where the fund aims to unlock the poten�al of community owned energy
genera�on to bring new income streams into communi�es and help them take direct ac�on
to combat climate change. The Sustainable North Ayrshire Strategy 2024-27
supports the vision of a sustainable, climate ready North Ayrshire where we
all play our part, whether as a local authority, business, school,
community group or individual.

Page 78

Our Council Plan Progress Update – Year End 2024 to 2025 Page 30 of 56
A Sustainable Council
To transi�on to a wellbeing economy,
delivering prosperity, wellbeing and
resilience for local people.
Key Ac�vi�es
Modern Appren�ce Employability
Programme
Five of our modern appren�ces completed
their 18-month Youth Work Modern
Appren�ceship accredita�on. They gained
a SCQF7 Youth Work qualifica�on, the
equivalent to an Advanced Higher, a
Higher Na�onal Cer�ficate or the first year
of a degree programme. In addi�on, they
gained accredita�on for First Aid, Mental
Health Resilience, An�-Sectarianism and
Mental Health Awareness. One Modern
Appren�ce stated:
“Since star�ng in 2023, I have gained a
tremendous amount of confidence and
social skills. I am much beter at talking to
new people and engaging in
conversa�ons. Also, I have improved my
�me management, reading, wri�ng, and
decision-making skills. I am so happy I
decided to apply. It has truly been the best
decision I’ve made.”
Skills for Life Programme
In 2024 to 2025, 81 Skills for Life
placements were created in partnership
with the following services and
organisa�ons: Streetscene; Facili�es;
Clerical (various departments); Pupil
Support Assistants; Third Sector; Step Into
Sustainable Business; as well as Care At
Home and Stores through the Health and
Social Care Partnership. 51 of the
placements were across other council
services. 
Accessibility
Our Customer Services, IT and
Transforma�on teams have been ensuring
our public services, both digitally and
locally, are accessible. This includes raising
awareness of our “No Wrong Door”
approach, which aims to ensure residents
are directed to support no mater which
service they ini�ally contact. This has
included employee Drop-In Sessions
across locali�es which were well received.
These are being followed by employee
awareness sessions targeted at front line
colleagues.
The Web Team has been working steadily
to improve the accessibility of our online
content and services, ensuring our
website meets recognised accessibility
standards.
We con�nue to explore how we can, with
our residents’ consent, use the
informa�on we hold to proac�vely offer
them the support they are en�tled to. This
is part of our Single Shared Assessment
model.  Progress is being made within our
Benefits team. Workshops are underway
to review the current customer facing
processes, how we can streamline
applica�ons for benefits and then iden�fy
how these can link to a wider Single
Shared Assessment model. 
Using Data to Inform Decisions
Our tackling poverty dashboard has been
tested, and the data is available for use by
relevant services. U�lising this provides an
understanding of child poverty priority
groups and helps to iden�fy ways to target
unmet need, supported by
the Child Poverty
Strategy and Customer
Service teams.

Page 79

Our Council Plan Progress Update – Year End 2024 to 2025 Page 31 of 56
Agile Workstyle Wellbeing Survey
In December 2024 we hosted an Agile
Workstyle Wellbeing Survey and invited all
1,987 employees who were deemed as
agile workstyle to take part. Key insights
were gathered from the 947 responses
received on how the agile workstyle
impacted on recruitment and reten�on,
work-life balance, benefits to employees,
engagement and collabora�on and the
uptake of wellbeing ini�a�ves. A summary
of the results is below:
Recruitment and Reten�on:  27% of
respondents had joined the Council within
the past four years, with feedback
indica�ng that the agile workstyle
posi�vely influences recruitment and
reten�on.
Engagement and Collabora�on:  89.4% felt
that the amount of �me spent with their
manager (for work/task related issues)
was suitable.  86% felt that the amount of
�me with their manager (to discuss
wellbeing, career growth) was suitable.
80.9% felt that the amount of �me to
collaborate with colleagues in other teams
was suitable.  85.2% felt that the amount
of �me spent on online team mee�ngs
was suitable and 80.3% felt that the
amount of �me spent on in person team
mee�ngs was suitable.
Benefits of agile working:  80% of
respondents felt that agile working
increased the quality of their work and/or
produc�vity. 62% said that agile working
increased their job sa�sfac�on.
79% said that agile working improved
their work life balance with 72% stated
reduced travel �me supported their health
and wellbeing.  66% said agile working
reduced their travel costs.
48% stated that agile working helped
improve their health and wellbeing
rela�ng to caring responsibili�es.
Overall, the survey responses showed that
employees view agile working posi�vely
and would like this to con�nue. They felt
agile working benefits them as individuals,
and teams, improves produc�vity and the
quality of their output.  There is evidence
that agile working has had a posi�ve
impact on recruitment, widening the pool
of candidates who are able to apply for
posts. Most respondents feel agile
working is a factor in retaining them
within our council. This shows workstyle
has a posi�ve impact on atrac�ng and
retaining talent.  An ac�on plan has been
created to support improvements.
Digital Skills Development 
To support the development of a digitally
confident and capable workforce, our
council conducted a Digital Skills Survey in
November 2024. The survey, open to all
employees, received 717 responses and
aimed to provide an evidence-based
understanding of current digital skills and
areas for development.
The findings indicate a high level of
proficiency in core digital tasks, including
device use, communica�on, and
informa�on handling. In response, a
targeted Digital Skills Ac�on Plan has been
developed. This plan will priori�se
improving access to training, increasing
awareness of available resources, and
promo�ng peer support opportuni�es.
The overall aim is to ensure our workforce
can work efficiently, securely,
and confidently in an
increasingly digital
environment.

Page 80

Our Council Plan Progress Update – Year End 2024 to 2025 Page 32 of 56
Our Transforma�on Programme
Our current Transforma�on Programme was approved in 2023 and developed alongside our
Council Plan 2023-28. The programme being delivered by our Council has been progressed
around the key priori�es within our Council Plan, driving change and transforma�on, using
technology and innova�on where possible to deliver efficient services to help address the
financial challenges facing our council. Through embedding a culture of con�nuous
improvement, crucially the delivery of our Transforma�on programme can protect the
services we provide to our residents. 
As part of our council’s annual audit arrangements, the focus of the Accounts Commission
this year has been on how councils are responding to the financial challenges through
transforma�on and redesign of services. Audit Scotland recently completed this Best Value
Thema�c Audit for our council. The findings of the audit will be presented to our Audit and
Scru�ny Commitee in May 2025. 
Our Transforma�on programme con�nues to be progressed at scale and pace. This sec�on
provides a summary of progress across our main Transforma�on themes and areas of service
review.
Digital Workstream
Our Transforma�on Board agreed in August 2024 to create a new Digital workstream,
incorpora�ng the principles and aims of the Accessing Our Council programme, to progress
our council’s digital journey. In such a fast-paced landscape the new workstream will capture
progress on digital ini�a�ves across our council, ensuring they are aligned to our Digital
Strategy, as well as tes�ng new areas of innova�on, including Ar�ficial Intelligence (AI), and
ensuring North Ayrshire supports na�onal ini�a�ves through the Sco�sh Government,
Digital Office, Improvement Service (IS) and SOLACE. To date the following progress has been
made:
• A na�onal planner of digital ac�vi�es and projects has been shared with the Digital
Working Group to ensure appropriate updates and representa�on.
• Mee�ngs have been held with the Improvement Service and Digital Office to explore
opportuni�es to be involved in the IS and SOLACE Transforma�on Programme and Digital
Office Na�onal Digital Strategy Refresh.
• At the March 2025 Transforma�on Board, a pipeline of projects was agreed, these include
AI Policy and inves�ga�on of products (Magic Notes, M365 CoPilot proof of concept),
na�onal opportuni�es such as Parents Portal, which is being taken forward by Educa�on
and Digital Economy and how best to u�lise the investment in Digital Infrastructure and
Connec�vity being led by Economic Development, Growth and Regenera�on.
• A Purchase to Pay service review is underway which will review the end-to-
end procurement process across our council, consider the op�mal
process for delivery and further progress supplier e-invoicing.

Page 81

Our Council Plan Progress Update – Year End 2024 to 2025 Page 33 of 56
Following the launch of our new council website, more customers are shi�ing towards digital
as their channel of choice to access our services. We recognise that our digital services are
key to suppor�ng this change in behaviour and embedding digital opportuni�es across our
organisa�on, whilst also recognising residents will con�nue to be supported through more
tradi�onal access routes. The newly established Digital Workstream repor�ng into the
Transforma�on Board and Digital Working Group will drive our digital journey.
Irvine Locality Property Review
The Irvine Locality Property Review con�nues to be progressed as part of the Land and
Property workstream. The main purpose of the review is to align our opera�onal property
estate to complement modern ways of working, leading to a carefully managed
ra�onalisa�on of our property estate and to support Community Wealth Building ambi�ons
through greater community use of council owned property. This programme aligns closely to
our strategic priori�es. The focus of the first phase of the property review has been Irvine
which has our most significant concentra�on of property assets, taking a whole locality
approach.
Extensive feasibility work, alongside several service engagement sessions with key
stakeholders, was completed to develop the property ra�onalisa�on concept, generate
op�ons and assess costs, benefits and risks. The informa�on gathered from this work led to
the iden�fica�on of a set of recommenda�ons for our property estate within Irvine for
implementa�on on a phased basis and was approved by Cabinet in March 2024:
• Vacate and subsequently market property assets including Quarry Road, Trinity Church
and Galt House to consolidate opera�ons within, and op�mise u�lisa�on of,
Cunninghame House.
• Vacate Bridgegate House and consider future uses as part of the Irvine town centre
regenera�on work and establishment of the Irvine Town Board, aligned to the Irvine
Town Board Plan for Neighbourhoods.
Work completed to date includes:
• Reloca�on of Genealogy from Irvine Townhouse to Irvine Library resul�ng in increased
foo�all.
• A contract awarded for the Training Suite and Customer Services Centre at
Cunninghame House, Irvine with a start date of June 2025.
• A procurement exercise is underway for construc�on changes at Quarry Road.
• 255 employees relocated to Cunninghame House.
• Reloca�on of the Eglington Trophy to the Heritage Centre.
• Approval of a £300,000 investment in a Community Wealth Building Ini�a�ve to support
the explora�on of a wellbeing enterprise hub at the current Greenwood
Conference Centre site.

Page 82

Our Council Plan Progress Update – Year End 2024 to 2025 Page 34 of 56
The employee moves from buildings noted above are expected to be complete by May 2026
with ra�onalisa�on providing the following benefits:
• Op�misa�on of under-u�lised property assets.
• Reduc�on of carbon emissions by an es�mated 286tCO2e.
• Reduc�on of property running costs and property maintenance costs, with combined
es�mated poten�al revenue savings of up to £0.357m per annum.
• Genera�on of poten�al capital receipts or revenue income through leasing
arrangements following marke�ng of the surplus buildings.
Nethermains and Shewalton Solar PV Farm
Construc�on work is complete on the two new solar PV farms at the former Nethermains
landfill site in Kilwinning and the former Shewalton landfill site in Irvine. The new solar farms
will make a major contribu�on to renewable energy genera�on and carbon reduc�on, as
well as bringing sterile land back into produc�ve use, whilst also providing funding for
community ini�a�ves through the renewable energy community benefits scheme. 
The projects are scheduled for energisa�on by mid-2025. The programme of works carried
out in the final 6 months of 2024 to 2025 included:
• Comple�on of moun�ng structure at both sites.
• Comple�on of substa�on works at both sites.
• Comple�on of the grid connec�on works by SP Energy Networks (SPEN).
• Compound area and road installa�on at the Nethermains site.
Commercial Property
The Commercial Property workstream’s vision is of a more efficient property por�olio across
three themes.  Progress across each workstream includes: 
1. Maximise occupancy from the current estate por�olio
Income of £886,199 was generated for 2024 to 2025, which was below expecta�ons due to a
number of factors, including the financial resilience of tenants leading to rent arrears and
even business closures. It is also recognised that the progress being made in the Irvine
Locality Review has had a consequen�al impact on the availability of commercial proper�es.
A detailed review including commercial property performance and associated marked
condi�ons is being prepared for the Transforma�on Board and will inform next steps for
2025 to 2026.
The Irvine Property Board agreed works to maintain the marketable value of Galt House for
disposal funded under the Sco�sh Government’s Place Based Investment Programme
(PBIP). Works include external improvements and roof repairs.  The wider poten�al
for the property will be considered in partnership with the Irvine
Neighbourhood Board in developing the Plan for Neighbourhoods
Investment Plan.

Page 83

Our Council Plan Progress Update – Year End 2024 to 2025 Page 35 of 56
2. Maximise opportuni�es from Economic Development, Growth and Regenera�on
(EDG&R) and Ayrshire Growth Deal (AGD) investment (exis�ng projects)
The following ac�vi�es have been progressed during this period to maximise the
opportuni�es from investment: 
• Annickbank Pavilion Phase 3 – Following comple�on of the project in March 2024, a
closing date was set for July 2024, with a preferred tenant iden�fied for the ground
floor. A subsequent closing date was set for February 2025 to enable bidders to consider
the service charge implica�ons of par�al occupancy. Discussions are currently ongoing
with the preferred bidder.
• Montgomerie Park Retail Phase 1 – The property was successfully marketed for sale,
with a preferred bidder iden�fied. The sale is subject to condi�ons, with a planning
applica�on submited by the bidder in July 2024.
• Montgomerie Park Sites E to G – Following a successful marke�ng strategy, a preferred
bidder has been iden�fied for all three sites. Heads of Terms are currently being dra�ed,
with the sale subject to condi�ons and considera�on by Cabinet for approval in June
2025.
• i3 Flexible Space, Irvine: The Ayrshire Growth Deal programme has provided modern
commercial industrial property with the comple�on of one 18,180 sq. � (1,689m2) unit
as part of the i3 Flexible Space project in Irvine. The unit is currently being marketed for
occupa�on.
• Portland Rd. Land Sale - Marke�ng of the vacant industrial land, formerly occupied by
NACCO, at Portland Road, Irvine recommenced December 2024, with a closing date set
in April 2025. A review of offers will then be carried out.
3. Develop proposals for new investment and securing Return On Investment (future
projects)
• An award for the Levelling Up for Ayrshire – Commercial and Low Carbon Infrastructure
under the Levelling Up Fund (LUF) Round 3 of £17.4m was secured from the UK
Government.
• Informed by market feedback, the North Ayrshire proposal aims to address market
failure in the delivery of new energy efficient commercial property alongside the
provision of associated low carbon infrastructure at key employment areas in Irvine. The
Irvine investment concentrates on Kyle Road, Annickbank and i3 sites, the following
progress has been made to date:
− Kyle Rd Phase 2, Irvine: Delivery of 1200m² of new Class 4/5/6 business space
capable of sub-division located at Irvine Industrial Estate, building upon the success
of Kyle Road Phase 1. The proposed design is complimentary to the Phase 1
development. The proposal provides a Gross Internal Area (GIA) of
1137m2 that is subdivided into nine units, eight with an area
between 70m2 and 120m2, and one larger unit on the internal
corner with an area of 265m2.

Page 84

Our Council Plan Progress Update – Year End 2024 to 2025 Page 36 of 56
− Annickbank Innova�on Campus, Irvine: Delivery of three 500m² new Class 4/5/6
business spaces located at Annickbank Innova�on Campus, Irvine, to complement
the exis�ng provision.
− i3 Flexible Space Phase 2: Design work is currently being finalised to support a
tender issue in Autumn 2025 for the construc�on of a new industrial building
c.1,700m2.
− Ac�ve travel routes are being designed to improve east/west connec�ons between
the commercial development areas including investment at Heatherhouse Road,
Long Drive, Riverside Way and along the River Irvine at i3 Enterprise Area. The
project will progress to implementa�on in 2025/26, subject to the necessary
permissions and approvals.
Service Reviews
As part of the budget se�ng process, it was agreed that there would be a comprehensive
review of the Waste Service during 2023 to 2025. 
The key elements of the Waste Service
are mainly statutory, however there is an
opportunity within the statutory
provision element to review service
demand, collec�on frequencies and
technology that may help to track and
capture data or provide solu�ons to
current issues.
The Waste Service Review has focused
on several projects across the service. 
During 2024 to 2025 the work detailed
below has been successfully delivered:
• Implementa�on of a Household
Waste Recycling Centre booking system.
• A comprehensive review of opera�onal arrangements and supervisory/management
arrangements, leading to service produc�vity improvements.
• Streamlining of the current Assisted Collec�ons process with recommenda�ons for
improvements.
• Implementa�on of a streamlined three weekly collec�on frequency for Absorbent
Hygiene Products.
• Review and streamlining of the payment process for Commercial Waste customers,
introducing a digital payment process.
Extensive benchmarking and feasibility work with mul�ple other local
authori�es was undertaken as part of this delivery, supported by regular
service engagement and consulta�on mee�ngs with several poten�al
system suppliers.

Page 85

Our Council Plan Progress Update – Year End 2024 to 2025 Page 37 of 56
Audits, Inspec�ons and Accredita�ons 
Best Value Thema�c Approach – Workforce Innova�on
The Best Value Thema�c Audit on Workforce Innova�on was presented to the Audit and
Scru�ny Commitee in August 2024 demonstra�ng how our council is responding to current
workforce challenges through building capacity, increasing produc�vity and innova�on.
The recommended ac�ons arising from the audit including progress updates are below: 
Recommendation Agreed Management
Action
Action
The council should
establish corporate
workforce planning
priorities and develop a
SMART action plan to
allow progress in
delivering these priorities
to be measured.
The Workforce Strategy
will be updated to
include corporate
workforce planning
priorities and an action
plan to allow progress
to be measured.
The Workforce Strategy has been fully updated
to align with internal and external factors,
workforce challenges, Council Plan priorities
and other key strategies and plans. An Action
Plan and Corporate Performance Indicators
have also been included to allow progress to be
measured.  This refreshed Strategy was agreed
at Cabinet on 18th March 2025. 
The council’s workforce
strategy should be
updated to align with all
four Council Plan 2023 to
2028 priorities and with
other key strategies and
plans. It should include an
analysis of council-wide
workforce data and set
out what the required
skills, learning and
development needs of its
staff are.
The Workforce Strategy
will be updated to
ensure alignment to all
Council Plan priorities,
other key strategies and
plans and include an
extract of council-wide
workforce data.
The Workforce Strategy has been fully updated
to align with internal and external factors,
workforce challenges, Council Plan priorities
and other key strategies and plans. The Strategy
has also been updated to include an extract of
council wide workforce data. This refreshed
Strategy was agreed at Cabinet on 18th March
2025. 
The council should build
on the work it has done to
date to demonstrate and
quantify what workforce
benefits and productivity
gains have been made
through its use of digital
technology.
Further work will be
undertaken to capture
and quantify efficiencies
from digital
improvements and for
this work to be
incorporated within our
council’s Medium Term
Financial Planning.
Complementing the Accessing Our Council
workstream the Transformation Board
recently approved the creation of a new
Digital Programme workstream. The intention
is that this will allow digital activities to be
monitored against the Council’s Digital
Strategy. 
To provide some initial evidence of progress,
the Council’s Budget on the 26th February

Page 86

Our Council Plan Progress Update – Year End 2024 to 2025 Page 38 of 56
Recommendation Agreed Management
Action
Action
2025 included savings associated with the
Channel shift to digital solutions of £100,000
per year for 2025 to 2026 and 2026 to 2027.
Two posts were identified in 2025 to 2026
(through non-filling of vacant posts), and
further posts will be identified for 2026 to
2027 as part of the Council’s Purchase to Pay
project which aims to centralise the accounts
payable process and further advance e-
invoicing.
Reporting progress through the new digital
workstream provides the framework to capture
and monitor the workforce benefits.
The council should
consider conducting
another digital skills
survey to inform the
support it provides for
improving the digital skills
and knowledge of its
workforce.
A digital skills survey will
be conducted to inform
future development
interventions.
The Digital Skills survey was conducted during
November and December 2024 and was open
to all North Ayrshire Council employees. 
The survey focused on key themes designed to
assess digital confidence and competence
across a range of everyday and work-related
tasks. 
Completion of this survey has captured a
comprehensive picture of digital skills that are
relevant both in the workplace and in personal
life to inform future development intervention. 
An Action Plan has been created to monitor the
progress of interventions. 
The council should
consider gathering further
feedback from staff on
the impact of agile
working on wellbeing and
productivity.
Further feedback will be
gathered from those
employees who are
deemed an agile
workstyle to gauge
continued benefits on
wellbeing and
productivity.
The Agile Working wellbeing survey was
conducted during December 2024 and was
open to all council employees deemed as an
agile workstyle. 
The survey focused on key themes designed to
assess how people viewed agile working, their
productivity, work-life balance and wellbeing. 
An Action Plan has been developed in line with
key themes arising from the results. Chief
Officers have also received specific results in
relation to their directorate and service to allow
any local action to be considered and
progressed.

Page 87

Our Council Plan Progress Update – Year End 2024 to 2025 Page 39 of 56
Recommendation Agreed Management
Action
Action
The council should
explore further where it
can work together with
partners to share services
and increase
collaboration.
The Medium-Term
Financial Planning
process for 2025 to
2026 and 2027 to 2028
will include the
exploration of further
opportunities for
sharing services and
collaboration across
partner organisations.
Collaborative opportunities continue to be
explored with South and East Ayrshire Councils
on options around sharing services on a regional
basis. The work to date has been led by the
three Ayrshire Chief Executives. 
A recent £500,000 bid was submitted to the
Scottish Government Public Sector Reform Fund
to further develop opportunities on a spend to
save basis. 
It is anticipated that, should the bid be
successful, this work will form part of the
SOLACE transformation programme.
In addition to providing
general workforce
planning updates, the
council should regularly
report its progress against
its workforce planning
priorities to Elected
Members through its
Council Plan updates or
other means.
Workforce planning
updates and progress
against priorities will be
regularly reported
through Council Plan
Progress Reports and
other means.
The Action Plan aligned to the Workforce
Strategy has been agreed and set up on
Pentana. Lead officers will provide regular
updates which will be included in the regular
reporting of the Council Plan (these reports).  In
addition, an update will be provided on a
regular basis to the 1st Tier JCC. 
The council should
develop a performance
dashboard to provide a
user-friendly overview of
the impact of its
workforce planning. This
could help to inform
future workforce
planning.
A performance
dashboard will be
developed to monitor
and inform future
workforce planning.
A performance dashboard has been scoped in
line with the Performance Indicators agreed as
part of the Workforce Strategy. This dashboard
is currently in design stage and on track for
completion by the end of September 2025.
Next Steps
• We will con�nue to progress recommenda�ons arising from the Audit Scotland Best
Value Thema�c Work.
• We will con�nue to progress property ra�onalisa�on.
• We will commence prepara�ons for our budget engagement for 2026 to 2027.
• We will carry out full site tes�ng and energisa�on of both of our Solar PV Farms and
progress with an Agreement of Purchase Power Agreement (PPA) for the
sale of energy produced at Nethermains and Shewalton.

Page 88

Our Council Plan Progress Update – Year End 2024 to 2025 Page 40 of 56
Case Study – Budget Consulta�on 2025 to 2026
To inform our budget se�ng process, we launched a comprehensive public consulta�on in
October to help shape the 2025 to 2026 budget. Due to the scale of the projected £15.7
million funding gap, our aim was to ensure transparency and collabora�on with our
communi�es and gain insight from their views.
Using collabora�ve methods, a wide-ranging budget engagement exercise was undertaken.
The aim of our approach was to ensure we gained a high number of informa�ve responses
from across our diverse communi�es in North Ayrshire. This was achieved through online,
paper and supported survey comple�on via telephone (through our Customer Contact
Centre) as well as in person engagement. We used a cross-service joined up approach to
improve on previous consulta�ons, develop the surveys and engage our communi�es.
The consulta�on was publicised through our website, press releases and on social media. Of
the 68 posts on social media, we received 81,891 impressions, 211 reac�ons, 178 comments
and 256 shares. 
The surveys were divided into six themes to improve the quality and range of responses.
• Addi�onal Council Tax Levy on Second Homes (507 responses)
• Community Facili�es and Car Parking (1,850 responses)
• Schools and Related Services for Children and Young People (714 responses)
• Service Delivery (254 responses)
• Taxes and Levies (398 responses)
• Waste Services (738 responses)
Specifically, this was to:
• Minimise survey fa�gue as respondents could select the areas they wanted to respond
to quickly.
• Improve accessibility, as it was easier to support paper and telephone responses through
our frontline services and Customer Contact Centre.
• Ensure a more balanced range of responses across each survey and a higher comple�on
rate. (A single survey may have led to the ini�al ques�ons being answered fully with less
detailed or par�al responses for later ques�ons.)
We consulted with a range of community groups across North Ayrshire, some on mul�ple
occasions and at various loca�ons across our area. We reached as broad a range of
community groups as possible. Most of the community engagement was in person, however
there were opportuni�es for video calling to ensure as many people as possible could
contribute their views.
This resulted in an increased response. Whereas in 2024 we received 200
responses through our Budget Challenge tool for the 2024 to 2025 budget
engagement in addi�on to substan�al engagement with our community
groups, this year we received 4,461 responses in addi�on to
community discussions.

Page 89

Our Council Plan Progress Update – Year End 2024 to 2025 Page 41 of 56
(It is important to note that the 4,461 responses do not equate to the same number of
respondents, as more than one survey is likely to have been completed by several
individuals.)
In addi�on, several pe��ons have been considered by the Audit and Scru�ny Commitee and
were referred to Cabinet rela�ng to some of the proposals including:
• Saltcoats and Ardrossan Libraries
• Parking charge enforcement in Kilwinning
• Dreghorn Library
• Beith Library
• Eglinton Park
This informa�on was examined by Officers in order to develop proposals for considera�on
by Elected Members in se�ng the budget. In parallel, as we asked for demographic
informa�on within the surveys, it was used to inform the Equality and Children’s Rights
Impact Assessments (ECRIAs) at each stage to ensure we fully considered the impact of
proposals on our residents and communi�es. The outcome of the engagement was
presented to Elected Members at Council on 12th February ahead of the final budget
decision. On 26th February 2025, Council approved a £459 million budget for 2025 to 2026
which includes measures to support residents and maintain frontline services.
We will con�nue to learn and improve our approaches and would like to thank everyone
who contributed to the budget consulta�on process.

Page 90

Our Council Plan Progress Update – Year End 2024 to 2025 Page 42 of 56
Case Study – Skills for Life
Jane* was eager to return to employment.   A single mother, she had been out of work since
2020 and faced significant barriers such as childcare costs and availability as well as a lack of
confidence a�er years away from a working environment.  A conversa�on with her health
visitor led her to the We Work for Families project.
Upon joining the project, Jane completed a detailed Needs Assessment and Ac�on Plan. Her
goals were clear - regain confidence, upskill and find sustainable employment. Our
Employability team enrolled her in confidence-building and job-readiness courses,
supported her with childcare costs and provided “beter off in work” calcula�ons to help her
plan financially.
Through the Skills for Life Clerical Programme with our council she secured a 26-week paid
placement in their Parental Employment Team. With on-the-job experience and a suppor�ve
team, she quickly setled into the role, gaining valuable skills and confidence.
Jane received tailored In-Work Support, including CV building, interview prepara�on and job
applica�on guidance. She applied for mul�ple roles, fine-tuned her interview skills and
con�nued to receive help naviga�ng childcare solu�ons.
Her efforts paid off as she went on to secure a permanent part-�me clerical posi�on with
our council with flexible hours that suit her family’s needs.
"Skills for Life gave me the confidence to get back into the workplace. The In-Work Support
helped me build my CV and perfect my interview responses. I finally feel like I’m building a
stable future for me and my son."
(*Name has been changed)

Page 91

Our Council Plan Progress Update – Year End 2024 to 2025 Page 43 of 56
Performance Summary
Performance Indicators Adri� of Target
This sec�on details the performance indicators adri� of target and the ac�on being taken to address
performance. Due to expected data lags, the most recent data may relate to previous �me periods
but may only now be available to report. To avoid duplica�on, only data that has not previously been
reported to our Cabinet through Council Plan progress repor�ng is included in this sec�on. Further
details can be found in the Performance Indicators sec�on within this report.
CP_37 Average total tariff score of pupils living in SIMD 20% most deprived areas (Red)
Actual is 664.3 against a target of 714 for 2023 to 2024 (most recent data available).  The average
total tariff score gained from all qualifica�ons by 2024 school leavers from the 20% most deprived
SIMD data zones has marginally decreased from the previous year.  The endeavour to offer candidates
a wider breadth of learning experiences has included more courses (or units of courses) from a wider
voca�onal range of courses and awards that some�mes are graded at the same SCQF level as
Na�onal Qualifica�ons courses but amass a smaller number of tariff points in the Insight scale.
However, these courses can provide learners with a more suitable set of skills and knowledge to
prepare them for work, training or further educa�on. 
Though this PI records the total tariff score for SIMD Quin�le 1 of S4-6 pupils who le� school in 2023
to 2024, the LGBF has a similar measure based on the cohort of young people who would have
reached the end of S6 in 2023 to 2024, irrespec�ve of their leaving year.  For the same period, 2023
to 2024, the equivalent LGBF measure shows a total tariff score of 685, above both the family group
average of 660 and the Sco�sh average of 658 and leading to our council being ranked 6th in
Scotland. 
CP_06 Average tariff score: All Leavers (Red)
Actual is 840.8 against a target of 908 for 2023 to 2024 (most recent data available).  The average
total tariff score gained from all qualifica�ons by school leavers has marginally decreased from the
previous year but is in line with pre-pandemic as well as recent years’ performance. The 2019 to 2020
On Target,
45, 98%
Slightly Adrift
of Target, 1,
2%
Actions
On Target,
13, 50%
Slightly Adrift of
Target, 5, 19%
Significantly Adrift
of Target, 6, 23%
Data Only, 2,
8%
Performance Indicators

Page 92

Our Council Plan Progress Update – Year End 2024 to 2025 Page 44 of 56
and 2020 to 2021 results are not comparable with other academic years, as SQA has employed the
Alterna�ve Cer�fica�on Model (ACM) instead of exam-based evalua�on for awarding qualifica�ons at
SCQF level 5 and above. Advice provided by Sco�sh Government colleagues emphasises direct
comparison to alterna�ve cer�fica�on years should not be made without further evidence and the
impact of these approaches. For all SIMD deciles except SIMD 10 (for which we have a very low
number of learners), we con�nue to outperform na�onal figures. 
Though this PI records the total tariff score of S4-6 pupils who le� school in 2023 to 2024, the LGBF
has a similar measure based on the cohort of young people who would have reached the end of S6 in
2023 to 2024, irrespec�ve of their leaving year.  For the same period, 2023 to 2024, this measure
shows a total tariff score of 845, above the family group average of 829 but below the Sco�sh
average of 917 and ranked 26th in Scotland. 
Closer examina�on of the LGBF highlights the strong influence that depriva�on has on this indicator.
When disaggregated by SIMD quin�le, our council outperforms both the na�onal figures and the
family group for each of SIMD quin�les 1 to 4 and also outperforms the family group for SIMD quin�le
5. Despite this strong performance, we know it is important to maintain our holis�c, cross-service
commitment to our Wellbeing priority in order to reflect this at an absolute level.
CP_38 Average total tariff for care experienced Young People (Red)
Actual is 355 against a target of 465.  The average total tariff score (ATTS) achieved by North Ayrshire
care experienced leavers was lower in 2023 to 2024, at 355 tariff points, than the general trend over
the last five years. A slightly higher propor�on than average of care experienced learners le� before
the end of S6 in 2023 to 2024, which has contributed in part to the lower average total tariff score. 
Schools have analysed the data locally and have a clear narra�ve for individual circumstances. The
service will con�nue to focus on improving this benchmark of achievement for care experienced
learners.  Atainment of care experienced learners is specifically referenced within the Educa�on
Service Plan. Quality Improvement visits and atainment discussions with senior school leaders will
include a focus on the atainment and achievement of this group of learners to ensure consistency of
delivery of interven�ons with a posi�ve impact.
CP_40 Number of new build housing units reaching comple�on (all tenures) (actual not cumula�ve)
(Red)
Actual 371 against a target of 396.  We achieved our target for 2024 to 2025 with regards to new
build social housing and have limited influence over the delivery of new build housing constructed by
private housing developers to meet the total 396 homes target. The 25 new homes unable to be
delivered during 2024 to 2025 were across a number of sites throughout North Ayrshire. We
exceeded our target for bringing empty homes back into use and intend to review this performance
indicator and con�nue to focus on improving performance in the forthcoming year. (This indicator is
linked to ac�on CP_10 detailed below).
CP_30 Total installed capacity of low carbon heat and electricity genera�on across the council's estate
(Red)
Actual is 17,630 against a target of 28,499.  Our council had aimed to have both solar PV farms
energised in December of 2024, however this has not been possible due to extended development
�me required by the Distribu�on Network Operator.  The solar farms have been built and are due to
be commissioned in the summer.

Page 93

Our Council Plan Progress Update – Year End 2024 to 2025 Page 45 of 56
CP_31 % of total household waste that is recycled (calendar year as per SEPA) (LGBF) (Red)
Actual is 52.8% against a target of 56%.  The provisional household waste recycling figure for the
calendar year 2024 is 52.8%, subject to verifica�on by SEPA. This has reduced since 2023 as a result of
the introduc�on of the new SEPA guidance regarding the requirement for Waste Upholstered
Domes�c Sea�ng (WUDS) to only be sent for incinera�on, which has nega�vely affected the amount
of bulky waste that can be recycled (this affects all councils).  In addi�on, more wood is being
deposited at recycling centres suitable only for biomass recovery rather than recycling. 
For context, LGBF benchmarking informa�on for 2023 to 2024 (2023 calendar year) released in June
showed we were ranked third in Scotland.  Though our provisional data shows a reduc�on for 2024 to
2025, as the new SEPA guidance affects all councils we will closely monitor our rela�ve posi�on when
compara�ve data is released over the coming months. 
CP_04 Propor�on of children mee�ng developmental milestones (LGBF) (Amber)
Actual is 77.5% against a target of 79% for 2023/24 (most recent data available).  At the most recent
data release for data for 2023 to 2024, the propor�on of children mee�ng developmental milestones
is 77.50%, slightly below the target of 79%.  We are working to ensure there is more robust data
gathering and analysis within Early Years and are moving towards using CfE levels with inbuilt
milestones.  This will help improve accuracy and consistency of data as well as improved progression
pathways to primary.  Roles and remits for Excellence and Equality Leads (EELs) developed this
academic session will support this work.
The challenges we are experiencing in North Ayrshire are reflected in the LGBF comparisons with
other local authori�es.  We are below the family group average of 79.8% and the Sco�sh Average of
83.3%. As a result we are currently ranked 31 out of the 32 local authori�es for our children mee�ng
developmental milestones. This is an area that we know will need specific focus within wider
principles of preven�on and early interven�on, including through the Collabora�on for Health Equity
in Scotland.
CP_28 Hectares of vacant and derelict land in North Ayrshire (Amber)
Actual is 942ha against a target of 925ha.  The majority of vacant and derelict land sites are within
private ownership, therefore their condi�on or development �mescales to inform if they are added or
removed from the register is out with the control of our council. However, we u�lise the Repurposing
Property Grant Fund to help support landowners and community groups to bring back vacant land
and proper�es to use. Furthermore, in 2024 to 2025, several of the key regenera�on funds which
support the redevelopment of such land, including the Vacant and Derelict Land Investment
Programme, were paused which reduced the poten�al to regenerate sites.  Funding has now been
confirmed and works will commence in 2025 to 2026.
CP_43 Number of council assets under community management (cumula�ve) (Amber)
Actual is 55 against a target of 56.  One Community Asset Transfer was delayed un�l Q1 2025 due to
some minor administra�ve issues within the community group which took longer than expected. We
con�nue to publicise the range of offers available for management and ownership of assets to our
community groups and are currently engaged with around 30 groups at various stages of the CAT
process.

Page 94

Our Council Plan Progress Update – Year End 2024 to 2025 Page 46 of 56
CP_29 Overall carbon emissions (tonnes) (Non-domes�c council estate) (Amber) 
Actual is 20,333tCO2e against a target of 19,953tCO2e.  This figure is an es�mate and will be
confirmed at the next data release.  Though slightly adri� of target the overall trend is a steady
decrease in emissions.  
CP_25 % of Council dwellings that meet the Sco�sh Housing Quality Standard (LGBF) (Amber)
Actual is 94% against a target of 97.4%.  The target of 97.4% was a set as part of last year’s ARC
comple�on. This pass rate is based on a combina�on of many different compliance criteria for each
individual property, including EICR (Electrical Installa�on Condi�on Report). When the 97.4%
compliance target was set, it was based on 100% compliance regarding the EICR element; however
with issues accessing proper�es, we were unable to achieve this (the EICR compliance outurn figure
for 2024 to 2025 was 97.71)%) which has resulted in the slightly lower overall SHQS compliance of
94% against the 97.4% target.
Indicator Amendments and Recommendations
CP_44a % of council dwellings that are energy efficient (Formerly known as SHSN05a) 
Originally sourced from the LGBF, due to the Energy Efficiency in Social Housing (EESH) regula�ons
being updated from EESH1 (recorded in LGBF) to poten�ally more stringent EESH2 requirements, the
Improvement Service (who administer the LGBF) has paused data recording of this indicator.  EESH2 is
being established na�onally and to ensure we remain transparent in our performance in this area, it
is recommended we con�nue to monitor EESH1 within a new PI (CP_44a).  This will contain all the
historical informa�on from the original LGBF but present local data, consistent with historical data,
from 2022 to 2023 to avoid gaps in our performance informa�on.  This approach will be reviewed
once the LGBF recommences recording of this area.
Educa�on Performance Targets
The educa�on targets in the above indicators are linked directly to the stretch aims previously agreed
with the Sco�sh Government and show figures that are significantly above the atainment levels
achieved during the Covid period when the Alterna�ve Cer�fica�on Model was deployed. 
It is not recommended to draw comparison between these periods. Therefor while we recognise the
merits of being aspira�onal and are commited to delivering ongoing improvement over �me, we
believe it would be sensible to reconsider the level of these targets to align them more closely to
performance in the post-Covid period. This is something we intend to do through appropriate
engagement and as part of the process of developing the next three-year service plan due in 2026.  
Ac�ons Adri� of target
This sec�on details ac�ons adri� of target and the measures being taken to address performance.
Further details can be found in the Ac�on Tracker sec�on within this document.
CP10 Increase the number of homes in the area through a mix of private and social developments
and bringing empty buildings back into use (Wellbeing Priority). (Amber) 
This ac�on is linked to the indicator “CP_40 Number of new build housing units reaching comple�on
(all tenures) (actual not cumula�ve)” which is currently significantly adri� of target (red) (see above). 
We achieved our target for 2024 to 2025 for new build social housing and we have limited influence
over the delivery of new build housing constructed by private housing developers. The 25 new homes
unable to be delivered during 2024 to 2025 were across a number of sites throughout North Ayrshire.
We exceeded our target for bringing empty homes back into use and intend to focus on improving
performance in the forthcoming year.

Page 95

Our Council Plan Progress Update – Year End 2024 to 2025 Page 47 of 56
Performance Indicators
PI Code and Descrip�on
2021-
22
Value
2021-
22
Target
2021-
22
Status
2022-
23
Value
2022-
23
Target
2022-
23
Status
2023-
24
Value
2023-
24
Target
2023-24
Status
2024-25
Value
2024-
25
Target
2024-
25
Status
2025-
26
Target
CP_36 Number of residents par�cipa�ng in
community learning and development
ac�vity including youth work
No
data
No
data
No
data 17,804 23,503 18,700 28,102 19,500 23,500
CP_04 Propor�on of children mee�ng
developmental milestones (LGBF) 78.7% 79.5% 77.50% 79%
Data
Available
May 2026
79% 79%
CP_37 Average total tariff score of pupils
living in SIMD 20% most deprived areas 704.8 670.2 664.3 714
Data
Available
March 2026
720 720
CP_06 Average tariff score: All Leavers 905.6 880 847.2 840.8 908
Data
Available
February
2026
910 910
CP_38 Average total tariff for care
experienced Young People 450.3 411.5 355 465
Data
Available
March 2026
470 470
CP_07 % of school leavers entering posi�ve
des�na�ons (LGBF) 96% 93.5% 96.5% 95.6% 96.4%
Data
Available
February
2026
96.8% 96.8%
PI Status
Significantly Adrift of Target
Slightly Adrift of Target
On Target
Data Not Available
Data Only

Page 96

Our Council Plan Progress Update – Year End 2024 to 2025 Page 48 of 56
PI Code and Descrip�on
2021-
22
Value
2021-
22
Target
2021-
22
Status
2022-
23
Value
2022-
23
Target
2022-
23
Status
2023-
24
Value
2023-
24
Target
2023-24
Status
2024-25
Value
2024-
25
Target
2024-
25
Status
2025-
26
Target
CP_39b Number of unemployed people that
have progressed to employment as a result
of par�cipa�on in council funded or
operated employability ac�vi�es
555 427 475
Data
Available
November
2025
475 450
CP_10a % of procurement spend on local
enterprises 22.93% 24% 26.04% 25% 24.48% 26% 26.8% 27% 27%
CP_40 Number of new build housing units
reaching comple�on (all tenures) (actual not
cumula�ve)
No
data
No
data
No
data 562 384 295 371 396 436
CP_41 Number of empty homes brought
back into use (actual) 335 120 378 200 375 300 350
CP_28 Hectares of vacant and derelict land
in North Ayrshire 1,198 1,144 1,130 1,094 951 1,094 942 925 925
CP_27 Street Cleanliness Index - % Clean
(LGBF)1 86.7 94 84.6 90 89.1 87 90.3% 87 89
CP_20 Overall percentage of road network
that should be considered for maintenance
treatment
33.9% 37.5% 34.8% 33.8% 32.5% 34.8%
Data
Available
September
2025
32.5% 32%
CP_42 Provided floor space of
commercial/industrial space within our
council por�olio (sq. �)
No
data
No
data
No
data 400,991 404,897 404,755 423,077 423,077 423,077
1 *Sourced from the Local Environmental Audit and Management System (LEAMS) audit conducted by Keep Scotland Beau�ful.

Page 97

Our Council Plan Progress Update – Year End 2024 to 2025 Page 49 of 56
PI Code and Descrip�on
2021-
22
Value
2021-
22
Target
2021-
22
Status
2022-
23
Value
2022-
23
Target
2022-
23
Status
2023-
24
Value
2023-
24
Target
2023-24
Status
2024-25
Value
2024-
25
Target
2024-
25
Status
2025-
26
Target
CP_02 % of council budget directed via
par�cipatory methods 2.32% 1.1% 2.74% 1% 2.05% 1.5% 1.97%. 1.5% 1.5%
CP_43 Number of council assets under
community management (cumula�ve)
No
data
No
data
No
data 49 53 54 55 56 57
CP_30 Total installed capacity of low carbon
heat and electricity genera�on across the
council's estate
11,680 11,000 12,104 11,800 15,992 12,000 17,630 28,499 30,137
CP_29 Overall carbon emissions (tonnes)
(Non-domes�c council estate)2 21,791 21,247 20,896 21,000 20,745 19,500 20,333 19,953 19,824
CP_44a % of council dwellings that are
energy efficient (Formerly known as
SHSN05a) (LGBF)3
97.7 98.2 98.01% 98.1 97.66% 98.5 98.7%
CP_45 Length of new or improved ac�ve
travel routes per annum (Metres)
No
data
No
data
No
data 1,090 3,900 2,000 2,500 2,000 2,000
CP_46 Number of trees planted under the
North Ayrshire 2030 Tree Plan�ng Strategy
No
data
No
data
No
data No data No
data
No
data 36,531 40,000 49,026 47,000 60,000
CP_19 Propor�on of opera�onal buildings
that are suitable for their current use (LGBF) 91.1% 93% 95.1% 93% 95.2% 92.1% 95.4% 93% 93%
2 This 2024-25 value is a provisional figure and will be confirmed in the next data release.
3 LGBF repor�ng has paused on this indicator whilst EESSH2 is established therefore the values from 2022-23 onwards are provisional and sourced locally. 
(See Indicator Amendments and Recommenda�ons above.)

Page 98

Our Council Plan Progress Update – Year End 2024 to 2025 Page 50 of 56
PI Code and Descrip�on
2021-
22
Value
2021-
22
Target
2021-
22
Status
2022-
23
Value
2022-
23
Target
2022-
23
Status
2023-
24
Value
2023-
24
Target
2023-24
Status
2024-25
Value
2024-
25
Target
2024-
25
Status
2025-
26
Target
CP_31 % of total household waste that is
recycled (calendar year as per SEPA) (LGBF)4 56.3% 53.1% 55.3% 56.9% 56.1% 57% 52.8% 56% 53%
CP_25 % of council dwellings that meet the
Sco�sh Housing Quality Standard (LGBF)5 49.3% 99.5% 63.2% 76.9% 72.5% 94% 97.4% 97.57%
CP_47 Gross rent arrears (all tenants) as at
31 March each year as a percentage of rent
due for the repor�ng year (LGBF)6
6.6% 7.1% 5.9% 6.5% 8.03% 7.0%
CP_48 % of income due from council tax
received by the end of the year (LGBF) 93.34% 94.7% 93.6% 94%
Data
Available
September
2025
98% 94%
4 The 2024-25 value is a provisional figure and will be updated in the LGBF data release in October 2025.
5 The 2024-25 value is a provisional figure and will be updated in the LGBF data release in September 2025.
6 The 2024-25 value is a provisional figure and will be updated in the LGBF data release in September 2025.

Page 99

Our Council Plan Progress Update – Year End 2024 to 2025 Page 51 of 56
Ac�on Tracker
Action Status
Significantly Adrift of Target
Slightly Adrift of Target
On Target
Ref # Existing Overall Action and Priority
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP01
Ensuring that wellbeing is at the heart of local life and
opportunities, with a focus on tackling inequalities
(Wellbeing Priority).
- - - - - - - - - - - -
CP02 Developing a Community Wealth Building approach to a
wellbeing economy (Wellbeing Priority). - - - - - - - - - - - -
CP03 Improving educational attainment and achievement and
closing the attainment gap (Wellbeing Priority). - - - - - - - - - - - -
CP04
Improving outcomes for care experienced young people
including implementation of The Promise (Wellbeing
Priority).
- - - - - - - - - - - -
CP05 Developing the Young Workforce and ensuring positive
destinations for school leavers (Wellbeing Priority). - - - - - - - - - - - -
CP06
Providing lifelong learning opportunities for individuals
and organisations, including digital literacy (Wellbeing
Priority).
- - - - - - - - - - - -
CP07 Maximising access to and uptake of benefits,
entitlements and financial advice (Wellbeing Priority). - - - - - - - - - - - -
CP08
Ensuring that supports are available in communities to
alleviate cost-of-living pressures through community
hubs and networks (Wellbeing Priority).
- - - - - - - - - - - -
CP09
Through our housebuilding programme and wider
Housing Investment provide homes for life that meet the
needs of our residents (Wellbeing Priority).
- - - - - - - - - - - -

Page 100

Our Council Plan Progress Update – Year End 2024 to 2025 Page 52 of 56
7 Delivery of this ac�on is managed through the Health and Social Care Partnership Strategic Plan
Ref # Existing Overall Action and Priority
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP10
Increase the number of homes in the area through a mix
of private and social developments and bringing empty
buildings back in to use (Wellbeing Priority).
- - - - - - - - - - - -
CP11
Exploration of models and the development of pilot
schemes to increase access to and use of
public/community transport (Wellbeing Priority).
- - - - - - - - - - - -
CP12
Ensure our places and spaces where we live, work and
visit are well maintained and accessible (Wellbeing
Priority).
- - - - - - - - - - - -
CP13 Developing infrastructure to support business growth
(Wellbeing Priority). - - - - - - - - - - - -
CP14 Support KA Leisure’s leadership of North Ayrshire’s
Health and Wellbeing Alliance (Wellbeing Priority). - - - - - - - - - - - -
CP15
Through the Health and Social Care Partnership Strategic
Plan we will protect and provide care and support for
those in need (Wellbeing Priority).7
- - - - - - - - - - - - - - - - - - -
CP16
Developing strong relationships with communities and
partners based on trust and shared aspirations using
their experiences to inform service provision
(Communities and Local Democracy Priority).
- - - - - - - - - - - -
CP17
Providing support for community organisations in
achieving their goals, including as Community Wealth
Building anchor organisations (Communities and Local
Democracy Priority).
- - - - - - - - - - - -

Page 101

Our Council Plan Progress Update – Year End 2024 to 2025       Page 53 of 56  
Ref # Existing Overall Action and Priority
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28  
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP18
Creating a participation and engagement framework
which ensures opportunities and support for all residents
to take part in influencing local democracy and council
and partner strategies (Communities and Local
Democracy Priority).       
- - - - - - - - - - - -
CP19 Supporting participatory budgeting (Communities and
Local Democracy Priority).        - - - - - - - - - - - -
CP20
Supporting community asset transfer and community
owned and operated/managed assets (Communities and
Local Democracy Priority).       
- - - - - - - - - - - -
CP21
Supporting the Community Planning Partnership and the
Community Plan (LOIP) (Communities and Local
Democracy Priority).       
- - - - - - - - - - - -
CP22 Developing partnerships with the third and voluntary
sector (Communities and Local Democracy Priority).        - - - - - - - - - - - -
CP23
Placemaking, including creation of locality action plans
based on the Community Plan (LOIP) priorities and
support the delivery of Islands Plans (Communities and
Local Democracy Priority).       
- - - - - - - - - - - -
CP24
Ensuring an inclusive, fair, rights-based and asset-based
approach in our work (Communities and Local Democracy
Priority).       
- - - - - - - - - - - -
CP25
Accessible public services, both digitally and locally,
ensuring a ‘No Wrong Door’ approach (Communities and
Local Democracy Priority).       
- - - - - - - - - - - -
CP26 Embedding our net-zero ambition in all democratic
decision-making (Climate Change Priority).        - - - - - - - - - - - -

Page 102

Our Council Plan Progress Update – Year End 2024 to 2025 Page 54 of 56
Ref # Existing Overall Action and Priority
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP27
Reducing the carbon footprint of our estate through
rationalisation utilising a locality-based approach and
taking a fabric first and low carbon energy generation
approach to homes and buildings (Climate Change
Priority).
- - - - - - - - - - - -
CP28
Improving resilience and reducing carbon by developing
and supporting supply chains where materials and goods
are sourced locally (Climate Change Priority).
- - - - - - - - - - - -
CP29
Promoting new woodland creation and protecting our
green spaces to provide a natural resource for carbon
sequestration (Climate Change Priority).
- - - - - - - - - - - -
CP30 Supporting local businesses as they meet their climate
change obligations (Climate Change Priority). - - - - - - - - - - - -
CP31
Promoting a circular economy in North Ayrshire to
reduce consumption of raw materials and promote
reuse, repair and recycling, and generating energy from
residual waste (Climate Change Priority).
- - - - - - - - - - - -
CP32 Developing local low carbon energy generation schemes
and networks (Climate Change Priority). - - - - - - - - - - - -
CP33
Unlocking the potential of community owned energy
generation to bring new income streams into
communities and help them take direct action to combat
climate change (Climate Change Priority).
- - - - - - - - - - - -
CP34
Learning for sustainability, and work with communities to
adopt low carbon behaviour change and encourage
climate-based volunteering activities (Climate Change
Priority).
- - - - - - - - - - - -

Page 103

Our Council Plan Progress Update – Year End 2024 to 2025       Page 55 of 56  
Ref # Existing Overall Action and Priority
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28  
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP35
Improving communities’ preparedness to deal with the
impacts of climate change already locked-in (Climate
Change Priority).       
- - - - - - - - - - - -
CP36
Working with communities to adopt low carbon
behaviour change and encourage climate-based
volunteering activities (Climate Change Priority).       
- - - - - - - - - - - -
CP37 Taking a nature-based approach to protect our habitats
and species (Climate Change Priority).        - - - - - - - - - - - -
CP38 Developing and promoting active travel infrastructure
(Climate Change Priority).        - - - - - - - - - - - -
CP39 Transitioning to low and zero carbon travel (Climate
Change Priority).        - - - - - - - - - - - -
CP40
Ensuring robust governance arrangements are in place to
fulfil the council’s statutory duties, manage risk and
support delivery of key priorities (A Sustainable Council
Priority).       
- - - - - - - - - - - -
CP41 Using dynamic data and lived experiences to inform
decision-making (A Sustainable Council Priority).        - - - - - - - - - - - -
CP42
Working with partners nationally, regionally and locally
to secure investment and target resources towards our
priorities (A Sustainable Council Priority).       
- - - - - - - - - - - -
CP43
Driving change and transformation, using technology
where appropriate, to deliver efficient and effective
services and support delivery of priorities (A Sustainable
Council Priority).       
- - - - - - - - - - - -

Page 104

Our Council Plan Progress Update – Year End 2024 to 2025 Page 56 of 56
Ref # Existing Overall Action and Priority
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP44 Maximising financial flexibilities to help support delivery
of priorities (A Sustainable Council Priority). - - - - - - - - - - - -
CP45 Maximising value from the use of our assets (A
Sustainable Council Priority). - - - - - - - - - - - -
CP46 Focusing our investment on priorities (A Sustainable
Council Priority). - - - - - - - - - - - -
CP47
Effective workforce planning ensuring that we have the
right skills/resources to deliver priorities (A Sustainable
Council Priority).
- - - - - - - - - - - -

Page 105

Our Council Plan Progress Update – Year End 2024 to 2025
Page 57 of 56
For further informa�on on this report please contact:
Corporate Policy and Performance
North Ayrshire Council
Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk
Tel:  01294 310000

Page 106

North Ayrshire Council
Annual Performance
Report 2024 to 2025
Appendix 3

Page 107

Welcome to our Annual Performance
Report 2024 to 2025
This Annual Performance Report is the second annual report relating to Our Council Plan.  Our
Council Plan 2023-28 was approved by Council in June 2023 following consultation with our
residents.  It is our joint plan, our contract with our communities, Our Council Plan.  
This report provides an at a glance summary of how we’ve supported our residents of North
Ayrshire during 2024 to 2025. You can find full details in our magazine style Council Plan Progress
Reports published on our website (Council performance (north-ayrshire.gov.uk)).
We are proud to serve our people of North Ayrshire and would like to say thank you to everyone
who has supported the delivery of our services including our communities, third sector, public and
private partnerships and of course our employees.
Our Vision – A North Ayrshire that is fair for all.
Our Mission – Working together to improve the lives of our people in
North Ayrshire.
Our four Council Plan priorities are interlinked and interdependent.

Page 108

2024 to 2025 About us
Elected Members
• 12 Scottish National Party (SNP)
• 11 Labour Group Members (8 Scottish Labour Party and 3 Labour and Co-operative Party)
• 6 Scottish Conservative and Unionist
• 2 Reform UK
• 2 Independent
Employees
• 6,406.64 Full Time Equivalent employees
• 7,578 employees
• 76% female
• 24% male
Key facts
• Population:  133,570
• 64,633 households
• Life Expectancy:
o Female:  79.3 years
o Male:  74.9 years
• 19,208 children and young people
attend our schools and early years centres
(including partner early years centres)
• 24.3% of children in North Ayrshire live in poverty
(after housing costs)
• 70.3% of residents are in employment
• 40.9% of our residents live in the most deprived Scottish Index
of Multiple Deprivation areas
Key assets include:
• North Ayrshire is 886 sq.km (mainland is 441 sq.km and our islands are
445sq.km)
• 225km coastline with 16 beaches (including three Sites of Special Scientific Interest (SSSI)
• 44 Local Authority Early Years Provisions
• 15 Partner Early Years Provisions
• 49 Primary Schools
• 8 Secondary Schools
• 1 Additional Support Needs School
• 1 Through School (Early Learning Centre, Primary and Secondary School combined)
• 13,315 council homes
• 1,118 km carriageway
• 3,900mm footpaths
• Approximately 23,750 streetlights
• Over 275 Hectares of woodland
• 15,992kW installed capacity of low carbon heat and
electricity generation across our council’s estate

Page 109

Financial Overview
Chief Executive's ,
£20.782, 5%
Education,
£170.791 , 39%
Communities &
Housing, £11.865 ,
2%
Place, £57.815, 13% Health and Social
Care Partnership,
£135.243, 31%
Other Corporate
Items, £9.573, 2%
Financing Costs,
£34.445, 8%
Allocation (£000's)
Scottish
Government
General Grant,
£326.331, 74%
Scottish
Government
Specific Grant,
£6.664, 2%
Non Domestic
Rates, £41.38,
9%
Council Tax,
£66.139, 15%
Funding (£000's)

Page 110

Our Performance
This section highlights key areas we have delivered under each of the four priorities: ‘Wellbeing’,
‘Communities and Local Democracy’, ‘Climate Change’ and ‘A Sustainable Council’.  Full details can
be found in our six monthly Council Plan Progress Reports on our website Council performance
(north-ayrshire.gov.uk)
Wellbeing
• Recent statistics published by the End Child Poverty Coalition showed
that child poverty within North Ayrshire decreased from 29.2% in
2022-23 to 24.3% in 2023-24. This reduction of 4.9 percentage
points was the largest in Scotland over this time period.
• We have been selected as one of three places to engage in the
Collaboration for Health Equity in Scotland (CHES) programme.
Over the next two years, we will work in partnership with Public
Health Scotland and the Institute for Health Equity to reduce
health inequity in North Ayrshire through improving the
conditions people live and work in. The ultimate aim is to enable
people to live longer, healthier lives by addressing the root causes of
health inequalities and preventing illness before it starts.
• During 2024 to 2025, our Money Matters team received 5,842 referrals
and secured £21.5 million in financial gains through income maximisation for
service users.
• Our council was successful in becoming one of Scotland’s Fairer Future Partnerships (FFP).  This
£350,000 investment enabled our new Child Poverty Strategy Team to be established in
January. It will enhance a systematic approach to addressing child poverty in North Ayrshire.
• We have implemented our Strategic Housing Investment Plan 2024 to 2029, including starting
on-site at Ayrshire Central Hospital in Irvine and at the former Garnock Academy site in
Kilbirnie and completion of sheltered housing refurbishment projects at Cheviot Court, Irvine
and Barnett Court, Saltcoats.
• Montgomerie Park Primary School, Moorpark Primary School and Marress Early Years Centre
all opened in the second half of 2024. Montgomerie Park Primary is the first Passivhaus school
in the region, which means the school has been built to a standard which provides a high level
of comfort for pupils and employees while using very little energy for heating and cooling.
• Almost £2.1 million in external funding has been secured to advance the Local Transport and
Active Travel Strategy.
• We commissioned a study into opportunities for Community Transport, specifically examining
the existing public transport provision on Arran and in the Garnock Valley.
• A key focus for our Community Learning and Development Team has been supporting schools
by delivering our ‘Bounce Back Your Resilience’ youth work programme. This programme is
delivered by young people in local primary schools and is tailored to empower Primary Six and
Seven pupils across North Ayrshire.  Our young people said:
“You all helped me realise not to care so much about what others think.”
“The youth workers were all amazing there was nothing I didn’t like.”
“I have learned to believe in myself and try to stop doubting myself if I fail.”
• During 2024 to 2025 we delivered 71 new homes across North Ayrshire.

Page 111

Communities and Local Democracy
• We completed a review of our locality planning framework, agreeing a number of
recommendations informed by feedback from participants, which will further strengthen local
democracy
• We published our new Participation Strategy which will focus on raising awareness of
participation processes including locality partnerships and enhance our budget consultation.
• Our Community Investment Fund continued to support our priorities through community
groups.  This included £41,000 for Beith Hive to support transport connectivity for childcare in
the Garnock Valley.
• Our Community Asset Transfer Team has received 17 expressions of interest during 2024 to
2025, with 56 council assets under community management to date. We have expanded our
capacity to support Community Asset Transfers (CATs) through engaging with our Active
Schools team.
• A number of activities were delivered for our care experienced young people through our
Corporate Parenting Summer Programme, as well as Active Schools and Community
Partnership Officers working closely with our Health and Social Care Partnership. 638 of our
young people took part, with 71% supported into longer term extra-curricular activity. Over
65% of attendees felt safer, that they were achieving more and/or felt more respected.
• Our council services delivered a coordinated approach to protect our residents and keep
critical services running during Storm Eowyn.
• Our Financial Inclusion Partnership is developing a communications plan to help promote
services to island residents, our gypsy traveller community, those who are digitally excluded
and residents with disabilities
• The Multiply project focused on supporting maths skills and qualifications in adults. To deliver
Multiply we worked with partners including CHAP, TACT, University of Highlands and Islands,
Ayrshire College and 15 community organisations. Throughout the year Multiply delivered 521
activities, 2,339 adults participated with 505 achieving qualifications.
• Our 2024 to 2025 small grants participatory budgeting saw 15,882 votes cast across North
Ayrshire, with £171,377 awarded to 190 groups across North Ayrshire
• 8,620 young people contributed to youth participatory budgeting through online voting and
deciding how local money could be sent of projects to benefit our young people.  Our digital
approach was included as an example of good practice at the international Consul Conference
in February.
• Overall service satisfaction among North Ayrshire Council tenants
has risen to 92%, marking an improvement on the previous result
for 2021 of 88.74%. Our three yearly tenant satisfaction survey
ran from November 2024 to January 2025, with 1,490
responses representing 40% of all our sampled tenants.
• Our North Ayrshire Islands Programme was a finalist in
COSLA’s Excellence Awards in the category of
‘Strengthening Communities and Local Democracy’, in
recognition of the unique partnership approach taken.
We continue to work closely, positively and
progressively with partners to ensure the Island Plan
priorities are front and centre of local decision making
where possible.

Page 112

Climate Change
• Installation of our council’s two new solar photovoltaic (PV) farms is now complete with the
next phase being the connection to the electricity network and commissioning works. They are
expected to generate £400,000 of revenue per year over 25 years as well as reduce our carbon
footprint whilst also providing funding for community initiatives through the renewable energy
community benefits scheme.
• A £17.4m award from the Levelling Up Fund Round 3 was secured from the UK Government.
This will support Levelling Up for Ayrshire, Commercial and Low Carbon Infrastructure.
• 15 households on Cumbrae and 25 in Kilwinning have been identified for improvements via the
Energy Efficient Scotland: Area Based Scheme. This will help address the impact of energy costs
and address fuel poverty.
• Four community renewable projects have been awarded £130,000 in funding through the
Community Renewable Energy Generation Fund.
• The ECO4 Flex scheme provides funding for energy efficiency improvements in homes,
primarily targeting low income and vulnerable households.  Our funding of £902,809 has
supported 32 households with the installation of over 134 energy saving measures to improve
home energy efficiency.
• 16 small and medium sized enterprises (SMEs) have enrolled for a first of its kind islands Net
Zero Accelerator programme.  This helps businesses increase sustainability, reduce their
carbon footprint and work towards eliminating greenhouse gas emissions.  Part
funded by Zero Waste Scotland, collaborative projects are emerging.
• Over the year our bulky waste reuse partner, Cunninghame Furniture
Recycling Company, collected 902 mattresses (24 tonnes) and 212
tonnes of household furniture as part of an initiative to promote
opportunities for their reuse, assisting 1,787 households to furnish
their homes whilst also employing 17 people within North
Ayrshire.
• We have switched 36 refuse collection vehicles from diesel fuel
to Hydrotreated Vegetable Oil (HVO).
• In November 2024, the third and final stage of the Fairlie
Coastal Path was completed with the opening of a new,
improved and safer access to the coastline for residents and
visitors to the area.

Page 113

A Sustainable Council
• Our most recent Best Value Thematic Audit focusing on Workforce Innovation was positive,
showing how our council is responding to current challenges by building capacity, increasing
productivity and innovation.
• Our Transformation Programme continues to progress, with key milestones reached within the
Digital Workstream, Irvine Property Review as well as the Nethermains and Shewalton Solar PV
Farm detailed above.
• The Transformation Board is overseeing service reviews across the Learning Resource; Housing
Service; Financial Inclusion Services; External Residential Placements; Economic Development,
Growth and Regeneration; and Waste Services.
• The Irvine Locality Review is progressing to align our operational property estate to the
changing workstyles of our workforce.  To date we have:
o Relocated Genealogy from Irvine Townhouse to
Irvine Library resulting in increased footfall.
o Relocated 255 colleagues to
Cunninghame House.
o Relocated the Eglington Trophy to
the Heritage Centre.
o Approved a £300,000
investment in a Community
Wealth Building Initiative to
support the exploration of a
wellbeing enterprise hub at
the current Greenwood
Conference Centre site.
• We have generated £886,199 in
income from our commercial property
estate.
• £17.4m was secured from the UK
Government via the Levelling Up Fund.
• In 2024 to 2025, 81 Skills for Life placements
were created in partnership with the following
services and organisations: Streetscene; Facilities;
Clerical in various departments; Pupil Support Assistants;
Third Sector; Step Into Sustainable Business; Care At Home and the Stores through the Health
and Social Care Partnership.  51 of the placements were across other council services.
• We delivered a comprehensive public engagement exercise to inform our budget setting
process for 2025 to 2026.  The revised approach generated increased engagement from our
communities, with 4,461 responses received in addition to community group feedback.

Page 114

Next Steps
Next steps for the next six months are included in our six-monthly 
Council Plan Progress Reports on our website www.north-ayrshire.gov.uk.
How do we compare?
You can discover how our
performance compares to
other Scottish local authorities
through the national Local
Government Benchmarking
Framework online tool or
through our LGBF Report
published within our Year End
reporting on our website
www.north-ayrshire.gov.uk.

Page 115

We strive to make our reporting as accessible as possible.  If you
have any questions or require further information on our
council’s performance please contact:
The Corporate Policy and Performance Team
Tel:  01294 310000  Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk