NORTH AYRSHIRE COUNCIL 
29 May 2025 
Audit & Scrutiny Committee
Title: Strategic Risk Register 2025/26
Purpose: To inform the Committee of the Council's agreed Strategic
Risk Register for 2025/26.
Recommendation:           That Committee notes the Strategic Risk Register for 2025/26. 
1. Executive Summary 
1.1 The Strategic Risk Register has been reviewed and updated for 2025/26. 
1.2 It is recommended that seven of the eight previous risks remain on the Strategic Risk
Register (SRR) at their existing risk scores. 
1.3 The Financial Sustainability of the Health and Social Care Partnership risk has
increased in risk scoring from 20 to 25. 
2. Background
2.1 North Ayrshire Council is committed to ensuring that it is proactive in identifying and
managing the risks impacting on the authority. The Council recognises that a certain
amount of risk is inevitable if the organisation is to achieve its objectives.
2.2 The aim of risk management is to reduce the likelihood and/or impact of risk by
identifying and controlling risks to the Council. If risk is to be managed appropriately,
and Services are aware of these risks, risk management can contribute positively
towards the organisation's decision-making processes, making the Council more
innovative and effective in its approach to service delivery. 
2.3 The most significant risks are identified through the Council's Strategic Risk Register,
recognising the challenges facing the Council and demonstrating the arrangements in
place to manage these risks. 
2.4 The Strategic Risk Register has been reviewed and updated for 2025/26 and is
attached at Appendix 1 to this report. For each of the risks detailed within the register
a number of components are identified: 
• Risk proximity factors;

Page 2

• Risk score;
• Potential effect on the Council's priorities;
• Internal controls currently in place;
• Assessment of controls; and
• Additional actions identified. 
2.5 To assist in the assessment of each risk, the Council’s agreed risk matrix was used to
ensure consistency. This is used to assess the likelihood of occurrence (on a scale
from 1 to 5) and the significance of the impact of the risk should it occur (on a scale
from 1 to 5). The risk score is the product of likelihood multiplied by impact. Only those
risks rated as high or very high (10 or above) will feature on the Strategic Risk
Register to ensure a focus on managing the most significant risks. 
2.6 Seven risks remain on the Strategic Risk Register at their existing risk scores – all
risks except the Financial Sustainability of the Health and Social Care Partnership
which has increased. 
2.7 The Financial Sustainability of the Health and Social Care Partnership risk has
increased in risk from score 20 to 25 due to continuously increasing budget pressures.
The risk likelihood has gone from a score of 4 to 5. This risk previously increased from
16 to 20 in the previous update at mid-year. 
2.8 This risk is now scored at the maximum level possible both in terms of impact and
likelihood after existing controls have been applied. 
2.9 Very High Risks 
• Financial Sustainability – this risk reflects the ongoing financial challenge
faced by the Council year on year (risk score 20).
• Financial Sustainability of the Health and Social Care Partnership – this
reflects the significant ongoing financial challenges faced by the Partnership and
the risk these present to the Council which are increasing (risk score 25). This
matter is currently being addressed by the Council through current financial
performance reporting governance and through the recent Budget setting
process for 2025/26. However it should be stressed that this position continues
to present significant challenges for the financial sustainability of the Council.
• Inequalities – this highlights the socio-economic inequalities faced in North
Ayrshire (risk score 20).
• Community Capacity Building and Empowerment – this highlights the
challenges associated with the community empowerment act (risk score 20).
• Property Asset Risk – This reflects the impact of long-term restricted budgets
on the Councils ability to maintain these to a good standard (risk score 20). 
High Risks
• Cyber Security – this reflects the ongoing risk from external cyber-attack which
is being faced by all organisations (risk score 16).
• Transformation – this reflects the wider risks associated with delivering the
current Transformation Programme and developing a pipeline of future initiatives
(risk score 12). It is recognised there remains a need for wider reform in order to

Page 3

fully address the financial challenges faced by the Council over the medium and
longer-term.
• Climate Change – this risk has been on the Strategic Risk Register following the
declaration by the Council of a Climate Change Emergency during 2019 (risk
score 16). 
2.10 Council services have identified high level strategic actions within their planning for
2025/26 to help the Council mitigate against its strategic risks. These actions are
detailed in summary format in the Risk Management Action Plans following each Risk
within Appendix 1. These actions will assist with performance monitoring and
reporting on the strategic risks. 
2.11 The Council’s Internal Audit Plan 2025/26 is scheduled to be approved at the Audit
and Scrutiny Committee on 13 March 2025 and is risk-based with clear links in place
between the audit plan and key risks the Council faces. 
Longer-term risks & Horizon Scanning 
2.12 The Strategic Risk Register identifies the most significant risks which the Council
faces at the present time. 
2.13 The Corporate Risk Management Group identifies any new relevant risks though
internal reviews and external horizon scanning utilising a number of sources. 
3. Proposals 
3.1 Committee is requested to note the Strategic Risk Register for 2025/26. 
4. Implications/Socio-economic Duty
Financial
4.1 The Council continues to have a robust long- and medium-term financial planning
framework. Key strands include development of key transformation themes and the
establishment of an Investment Fund that will generate future savings alongside
delivery of a number of key Council priorities.
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 The risk to the Council is that North Ayrshire residents, and in particular certain
groups, will experience increasing levels of poverty and its effects. Current control
measures fall into two categories - measures to address the root causes of socio-

Page 4

economic inequalities - income through employment or benefits – and mitigation
measures to minimise the impacts of poverty. 
Climate Change and Carbon 
4.5 The Council has declared a climate change emergency and has in place an
Environmental Sustainability and Climate Change Strategy. Significant work to help
mitigate the risk of flooding is included within the Capital Plan. The Council is
undertaking an ambitious renewable energy programme. 
Key Priorities 
4.6 A successful risk management framework helps to underpin the delivery of the
Council’s strategic priorities in Our Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The Strategic Risk Register has been reviewed in consultation the Corporate Risk
Management Group and relevant Chief Officers. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Alex Fitzharris, Team Manager (Risk), on 01294-
324515. 
Background Papers
None.

Page 5

Appendix 1 - Strategic Risk Report 2025/26 
Risk Code SRR2526_R01 Risk Title Financial Sustainability Latest Note Date 26-Feb-2025
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The risk is that the level of funding from Scottish Government
to local government falls significantly below the level required
to operate services effectively. This will require the Council to
take increasingly difficult and challenging decisions. The
revised 2025/26 local government settlement represents an
increase in core funding of £7.254m (2.05%). This is against a
backdrop of significant inflationary cost increases and risks,
including and anticipated shortfall in funding for employer
national insurance contributions for direct staff of £2.647m.
The North Ayrshire position is further affected by a reducing
overall population demographic and a growing elderly
population. This will further impact the Council’s share of
funding across the short, medium and long term.
Although there is a commitment through the Verity House
agreement for Councils and Scottish Government to work
together there continues to be challenges around the level of
flexibility the Council has on key areas of Budget, most notable
in areas like HSCP funding and funding for teachers and
support staff, where conditions remain. In 2024/25 in-year cost
pressures across the Council’s General Fund and the Health
and Social Care Partnership present a significant risk to the
sustainability of the Council’s finances. The General fund
currently projects an in-year overspend of £0.3m and the
HSCP has an overall projected outturn of £5.824m for
2024-25, reduced to £4.415m through identified financial
recovery actions. The NAC element of this as a funding partner
is a year-end overspend of £4.285m, reduced to £3.106m
through recovery actions. There is an increasing risk to
achieving financial balance during 2024-25. The Scottish
Government has passed legislation to give Councils powers to
charge additional council tax for second homes. This is an area
the Council will consider within the context of local
circumstances and island communities. 
Scottish Government funding to support the Council’s capital
programme has also not kept pace with rising costs. Set
against high inflationary driven construction costs there is a
risk that the 10-year capital programme will be unaffordable.
This could require projects to be reduced in scale or even
ceased.
Funding not keeping pace with demand
and inflationary cost pressures means that
there will be a reduction in some service
areas potentially resulting in higher risks
for service users. The future delivery of
balanced budgets will become increasingly
challenging. The capital programme could
also be significantly impacted leading to
reduced levels of capital investment.
Robust monitoring of the Council’s revenue and
capital budgets is in place as well as regular
reporting of financial performance of the IJB to
Cabinet and Audit and Scrutiny.
To assist financial planning The Medium and Long-
Term Financial Outlook (LTFO) to 2033/34 was
approved at Council on 13 December 2023 – this is
the cornerstone of the Council's financial planning in
the medium to long term. 
The annual budget process for the General Fund
revenue and Capital Programmes and financial
performance monitoring process will continue to
provide the framework from which control measures
will continue in addressing the financial position. 
Delivery of the Council’s Change Programme is also
vital in addressing the Budget challenges and this is
being progressed by the Council’s Transformation
Board, which is chaired by the Chief Executive. 
Utilising the Council’s available statutory powers is
another important area in addressing the financial
challenges. 
4 5 
Status  Risk Score 
Heat Map 
Change in Score Approach 
No change  Treat
Increasing Risk 20

Page 6

Strategic Risk Action Plan Date Updated 26-Feb-2025
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG 
Regular financial monitoring of Revenue and Capital Budgets. 
11 September 2024:
Ongoing financial monitoring process across capital and revenue, including
identification of measures to address in-year position. 
26 Feb 2025:
Recent finance reports trending towards break-even position for the Council’s
general fund. Major challenges remain however regarding the financial
performance of the IJB. The Council will require to make interim funds
available to the IJB in 2024/25 and this will be on the basis of repayment in
future years. This will be considered by Cabinet. 
31-Mar-2025  Mark Boyd 
Maintain Financial Governance Arrangements for IJB. 
11 September 2024:
New Finance Working Group set up to address in-year and medium-term
pressures. Includes representation from the HSCP, Health and the Council,
Main focus is on development of a finance recovery plan. 
26 Feb 2025:
The Finance Working group continues to progress transformation and
recovery actions, however it is unlikely it will achieve financial balance in
2024/25. Information continues to be reported through to the Council’s
Cabinet 
31-Mar-2025  Mark Boyd 
Progress dialogue via COSLA with Scottish Government on a range of
areas including fair funding, multi-year settlements, reduction in levels of
ring-fenced resources, true costs of SG policy areas, financial flexibilities
and a New Deal partnership with SG and local government. 
11 September 2024:
Discussions ongoing, however, SG have just announced £0.5Billion of cuts
Further dialogue being progressed around teacher number restrictions and
areas of revenue generation. 
26 Feb 2025:
Further progress made in this area as part of the Local Government
settlement through reduced levels of ring-fencing, however, further progress
needs to be made as consitions remain around teacher numbers and HSCP
funding. Financial flexibilities have been progressed by the Council through
approval of 100% premium for second home-owners council tax and through
a review of non-domestic rates empty property relief 
31-Mar-2025  Mark Boyd 
Develop the 2025/26 to 2027/28 revenue budget (medium-term financial
strategy) and capital programme taking account of all pressures and
savings via Directorates and Transformation programme. 
11 September 2024:
The 2025/26 Budget process has commenced earlier, in view of the current
financial challenges. Special Council meeting arranged for 9 October, 2024 to
set out the financial outlook and outline initial proposals as part of a 
26-Feb-2025  Mark Boyd

Page 7

community engagement programme to commence from 10 October, 2024. 
26 Feb 2025:
Medium-Term financial plan approved by Council on 26 February 2025,
included over £4m of savings and a 7% increase in council tax. The budget
also included a £4m risk provision to help manage the risks and pressures
facing the Council. The Budget also included additional funding contribution to
the HSCP of £2.114m plus a further £0.759m funding from the Council to
ensure 100% funding in respect of employers national insurance contribution.
This element of pressure being borne by the council.

Page 8

Risk Code SRR2526_R02 Risk Title Inequalities Latest Note Date 16-Jan-2025
Risk Owner Caroline Cameron; Sam Anson; David Hammond
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
North Ayrshire residents, and
in particular certain excluded
groups, will experience
increasing levels of poverty
and its effects, as a result
both of the economic
situation and further public
sector funding challenges.
Health inequality is closely
linked to poverty,
employment and people's
earliest experiences as
children, and will increase. 
The population of North
Ayrshire is projected to fall
over the next 10 years but
there will also be a larger
proportion of the population
considered dependent (not
economically active).
The impact on specific risk
groups is greatest for our
children, young people and
families, unemployed
people and those in in-
work poverty and people
exposed to the risks of
drug and alcohol addiction.
Demand for HSCP and
Council Services will
increase. 
As reductions in resources
increase, early intervention
and prevention activities
are at risk, thus increasing
the potential for an
increase in costly crisis
interventions. 
The local economy will be
impacted by reduced
spending power by
economically inactive
residents.
The HSCP re-affirmed its commitment to Tackling Inequalities by continuing to consider it a key priority with the
Partnership’s Strategic Plan. 
Through the HSCP strategic plan, the Partnership sets out actions to tackle inequality through its Partnership
Pledge and across its strategic priorities. Tackling inequalities is addressed across HSCP service areas. An
example of actions to help address local inequalities include:
Establishing the Money Matters service in 9 GP practices and 7 local schools in the more deprived areas of
North Ayrshire. This will improve accessibility of the service to those who would benefit most. Building on this
approach through the launch of the Financial Inclusion Partnership bringing a range of key partners and
stakeholders together to improve access and support for the most vulnerable NA residents. 
Increase the number of employability mentors in Justice Services, to support those with experience of the
justice service into meaningful employment or training opportunities and to help divert away from criminal
behaviours.
Working closely with Housing colleagues to support transitions from care and ensuring care experienced young
people can access a positive and stable housing destination. 
In our Drug and Alcohol Services, we are implementing actions to reduce the number of local drug and alcohol
related harms and deaths. This includes implementing the national MAT (Medicated Assisted Treatment)
standards and increasing the number of ABIs (Alcohol Brief Interventions) delivered across North Ayrshire.
Through the Caring for Ayrshire programme, we have set out a phased approach to improve local primary care
premises (GP Practices and Health Centres). This will improve overall professional capacity within GP
practices for Multi-Disciplinary Teams, ensuring the right support is available for local people with health
concerns. 
5 4
Investment in early intervention teams and approaches in Children’s Services to support vulnerable families,
including in Child Protection and Whole Family Support.
The Council considers reducing inequalities to be at the heart of its work.
The Communities & Housing Directorate leads the Community Planning Partnership for the Council, and the
CPP’s Local Outcomes Improvement Plan has a central purpose of reducing inequalities. Locality Planning
priorities and Community Investment Fund funded initiatives are also focused on a range of inequalities,
including poverty, age-related inequalities and digital inequalities. Recent CIF-funded projects have focused on
employability, addictions and community food.
Sam Anson, Executive Director (Education) and David Hammond, Executive Director (Communities & Housing)
led the work of the Child Poverty and Cost of Living Board, chaired by the Council Leader. The five strategic
themes of the Board were:
• No Wrong Door – access to services
• Employability
• Food
• Islands
• Childcare
This work has now been mainstreamed by the Community Planning Partnership (CPP) to ensure greater
partner visibility and impact.

Page 9

Work to address child poverty and the Cost-of-Living crisis includes a range of employability initiatives to
support parents and people with disabilities, each of whom are Scottish Government priority groups. Progress
has been made with partners to undertake a review of the Child Poverty & Cost of Living approach, with
recommendations being finalised for consideration by the Board. This is supported by the data and Single
Shared Assessment projects being developed by the Transformation team, to provide holistic support for
residents who need it most. 
The Child Poverty Early Intervention Fund is being used to address gaps in current planning and provision.
Previous funding decisions were made as a consequence of the mini-enquiries to support employability and
travel, childcare developments and support for care experienced young people and families. Further
allocations are currently being developed. 
Through the Scottish Government’s Fairer Futures Partnership we have established a Child Poverty Strategy
Team, who came into post in January 2025. This team will have key oversight role in collectively delivering
holistic support, alongside the transition to a wellbeing economy, in reducing child poverty rates in North
Ayrshire. 
We have started work as one of three areas involved in the Collaboration for Health Equity in Scotland (CHES)
programme. The aims of CHES are to answer two fundamental questions: 1) What are the most impactful
areas for intervention in Scotland to make meaningful progress in closing inequities in healthy life expectancy,
and 2) how can national and local organisations work more effectively to close the gap between policy intent
and impact in these areas? 
The Scottish Government has provided a second year of funding to address inequalities on the islands. This
has been used to fund energy support, welfare advice and support, third sector interventions and school
activities. 
The commitment to reducing inequalities is also reflected in the following plans:
• The Educational Service Improvement Plan
• Connected Communities strategic plans and
• Facilities Management plans. 
Examples of actions to reduce inequalities:
• Deployment of Scottish Attainment Challenge funding to reduce the poverty related attainment gap in
schools
• Use of the Pupil Equity Fund to ensure equity of pupil experience in schools, at the discretion of head
teachers
• Cost of the School Day actions to reduce, for example, the cost of school uniforms and clothing, food
and outings
• Support for care experienced young people, both in schools and through youth services
• Additional national and local investment in Active Schools to focus on inequalities and equity
• The Fairer Food Network, with 14 community larders which support the needs of individual communities
• A network of warm spaces and events to mitigate energy use and social isolation
• Work to support “New Scots,” in schools, with families and in community settings through language
support and capacity building, including women’s groups
• LGBT support groups for young people and those over 18
• Mentoring support for young people in secondary schools through a partnership with MCR Pathways

Page 10

Work is in hand with the Third Sector Chief Officers Group to co-design expenditure proposals from the Child
Poverty & Early Intervention Fund on three priorities relating to child poverty, namely childcare, support in
employability and financial inclusion. A sub-group has been established and initial proposals scoped in relation
to the first two priorities, with the group due to meet again prior to the end of March 2025 to finalise proposals
and expenditure commitments. 
In addition to the above, the HSCP re-affirmed its commitment to tackling Inequalities by continuing to consider
it a key priority with the Partnership’s Strategic Plan.
Through the HSCP strategic plan, the Partnership sets out actions to tackle inequality through its Partnership
Pledge and across its strategic priorities. Tackling inequalities is addressed across HSCP service areas. An
example of actions to help address local inequalities include: 
Establishing the Money Matters service in 9 GP practices and 7 local schools in the more deprived areas of
North Ayrshire. This will improve accessibility of the service to those who would benefit most. Building on this
approach through the launch of the Financial Inclusion Partnership bringing a range of key partners and
stakeholders together to improve access and support for the most vulnerable NA residents. 
Increase the number of employability mentors in Justice Services, to support those with experience of the
justice service into meaningful employment or training opportunities and to help divert away from criminal
behaviours. 
Working closely with Housing colleagues to support transitions from care and ensuring care experienced
young people can access a positive and stable housing destination. 
In our Drug and Alcohol Services, we are implementing actions to reduce the number of local drug and alcohol
related harms and deaths. This includes implementing the national MAT (Medicated Assisted Treatment)
standards and increasing the number of ABIs (Alcohol Brief Interventions) delivered across North Ayrshire.
Through the Caring for Ayrshire programme, we have set out a phased approach to improve local primary care
premises (GP Practices and Health Centres). This will improve overall professional capacity within GP
practices for Multi-Disciplinary Teams, ensuring the right support is available for local people with health
concerns. 
Investment in early intervention teams and approaches in Children’s Services to support vulnerable families,
including in Child Protection and Whole Family Support. 
Participation strategies for children and young people and adults to ensure our strategies and investment are
informed by as wide a range of views as possible.   
Status  Risk Score 
Heat Map 
Change in Score Approach 
No Change  Treat
Stable 20

Page 11

Strategic Risk Action Plan Date Updated 20-Feb-2025
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG 
Global and national conditions which affect the cost-of-living and poverty continue
to undermine the effectiveness of local control measures. Substantial work
continues to mitigate inequalities but child poverty data, for example, continues to
show an increase. National data collection methodologies have changed which
explains the change in part, but North Ayrshire continues to have c. 29% of
children living in poverty. 
Although unemployment has reduced, it continues to be a driver of poverty, with
in-work poverty a key factor.
Access to benefits is a key driver of poverty and the range of strategies described
above continues to ensure we are maximising access to entitlements. The Single
Shared Assessment work will improve this.
19 September 2024:
The wide range of strategies and initiatives described above,
being further developed and implemented, is anticipated to make
a significant contribution to a range of inequalities. The review of
the CPCOL Board, Child Poverty & Early Intervention Fund,
Fairer Futures funding, and single shared assessment project are
designed to help ‘shift’ the dial in tackling inequalities. 
Actions are being progressed and remain within the target dates
for completion. 
20 Feb 2025:
The work of the CPCOL board has been mainstreamed as a
workstream of the CPP board following discussion with both
groups and in recognition of the importance of the work as a core
function of the partnership. This improves visibility and
governance. 
Work is being developed around the codesigned use of an
allocation of the Child Poverty and Early Intervention Fund along
with the Third Sector Chief Officers Group. This will improve
capacity for change across third sector initiatives delivering on
child poverty outcomes. 
The recent review of Locality Partnerships has resulted in a series
of recommendations designed to refocus the work of the
partnerships on their prime driver of reducing inequality. 
31-Mar-2025  Caroline Cameron

Page 12

Risk Code SRR2526_R03 Risk Title Financial Sustainability of the Health and Social Care Partnership Latest Note Date 16-Jan-2025
Risk Owner Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Resources have not kept pace with the demand for and
cost of social care services. The budget settlement for
2024-25 is extremely challenging with a gap of over
£10m across the IJB. Financial modelling suggests
significant ongoing challenges across the medium-term.
There is no certainty around future funding against
growing demand, increasing costs and demographic
pressures, with one-year budget settlements remaining
in place.
The ongoing work to review the Integration Scheme and
to develop new risk-sharing arrangements between the
Council and Health Board in relation to the acute set
aside and primary care prescribing present a financial
risk to the Partnership and Council. 
The Partnership is projecting an overspend of £5.0m in
2024/25, reduced from the £6.5m forecast in August
2024 due to the implementation of a financial recovery
plan. 
The financial position moving into 2025/26 remains
challenging for the IJB.
Funding levels could result in
savings being made that are not
in alignment with the strategic
plan. This could impact on the
future demand levels e.g.
reduction in early intervention
and prevention means that
future demand is increased.
An in-year overspend position
impacts on financial reserves
and ultimately poses a financial
risk to the Council and NHS
Board as funding bodies. The
IJB have formally written to NAC
and the NHS to advise of the
estimated financial support
required. 
Funding levels increase the
requirement to transform
services at scale and pace.
The IJB actively monitors the financial position with regular detailed
reporting. Directors of Finance of the Council and Health Board have
oversight and regular updates are provided to the Council's Cabinet.
There is an integrated approach to managing the totality of NHS and
Council resources delegated to the IJB. A three-year Medium-term
Financial Outlook is updated on a rolling basis each year.
Previous financial settlements have seen both partners meet the
Scottish Government settlement conditions with any additional
resources passed to the IJB. 
The Partnership has developed a new 3-year Transformation Plan
2024-2027 which will be approved by the IJB in March 2024. There is
£2.2m of earmarked reserves set aside to support service change
and re-design. This is fully committed and any slippage has been
drawn down in-year to support the financial position. 
5 5 
Status  Risk Score 
Heat Map 
Change in Score Approach 
Increase from 20 to 25  Treat
Increasing risk 25

Page 13

Strategic Risk Action Plan Date Updated 16-Jan-2025
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG 
Budget Monitoring - Regular budget monitoring reports to IJB are effective. 
18 September 2024:
Strengthen support from Finance Team to front line services and
increased engagement with Heads of Service and Senior
Management Teams, including line by line reviews of all budget
areas. Review and enhancement of frequency and level of
financial information provided to support oversight and decision
making in line with financial constraints, with an added focus on
areas of underspend to maximise opportunities to delay or stop
spend and contribute to the overall financial challenge. 
16 January 2025:
The capacity of the NHS finance team to provide up to date
monitoring information has been raised and discussions are
ongoing to ensure accurately and timely information is provided to
the IJB. 
31-Mar-2025  Caroline
Cameron 
Corrective Action – Transformation Board is effective 
18 September 2024:
A three-year Transformation Plan covering the period 2024-2027
was approved by the IJB in March 2024. This focusses on
addressing the future financial challenge in a sustainable way, as
well as reviewing service delivery models and implementing local
and national priorities. 
16 January 2025:
The transformation board has a themes-based agenda e.g.
children & families, community care & health etc. This has
allowed a stronger focus on each area. Regular updates have
been presented to the IJB on progress. 
31-Mar-2025  Caroline
Cameron 
Enhanced Financial Controls
18 September 2024:
Establishment of a Budget Working Group to facilitate increased
oversight and scrutiny of the financial position and transformation
programme as well as detailed budget planning for future financial
years. The first meeting took place on 9th September.
Review of expenditure authorisation levels across the Partnership
and escalate specific decisions to senior officers.
Staff communication in relation to discretionary/non-essential
spend. 
Review of temporary posts and robust vacancy
management/approval – only essential frontline posts will be
approved for recruitment.
Strengthen across services the existing approval and prioritisation
approaches for new care requests, which will be approved in line
with resource availability. A new group has been established to
sign off all higher value care packages (Over £40k). 
6th March 2025: 
The Finance Working Group has now met 6 times and covered a 
31-Mar-2025 
Caroline
Cameron

Page 14

range of areas to support increased oversight and scrutiny of the
financial position and transformation programme and to support
detailed budget planning for future years. This has supported
proposals for the 2025/26 budget coming forward before March
2025 for approval and an improved understanding of the scale of
the financial challenge and the difficult decisions required to
manage this.
The Financial Recovery Plan is estimated to deliver £4m of
benefit in-year, with the forecast outturn reported to be £5m, a
reduction from the £6.5m reported in August 2024. Some of the
benefit of the plan has been eroded by unexpected financial
pressures in-year.   
National Influence/Escalation
6th March 2025: 
Through the NA Chief Officer the IJB have raised concerns
nationally with Scottish Government, with Civil Servants and
Politically re the impact of the financial position aligned to
performance, for example the priority of the Delayed Discharge
Mission. Scottish Government plans to publish an NHS Renewal
plan at the end of March 2025 which will describe how the £200m
funding set out as part of the budget will be deployed to improve
performance. As part of this, and through NHS Boards, HSCPs
were requested to submit costed improvement plans. North
Ayrshire HSCP submitted a request for £9.5m of additional
funding of which the majority of funding is for social care, the
HSCP await feedback following submission by all Boards to
Scottish Government. 
Concerns have also been raised nationally by Audit Scotland
through their Finance Bulletin on IJBs published on 6th March and
by Chief Officers as a collective, Chief Officers shared the national
scale of financial challenge with Scottish Government officials and
politicians on 5th March with a request that IJB requests for
funding are prioritised.

Page 15

Risk Code SRR2526_R04 Risk Title Cyber Security Latest Note Date 15-Jan-2025
Risk Owner Fiona Walker
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The potential compromise of business operations or a
data breach orchestrated via either digital channels or
the IT infrastructure. This can include targeting of the
user base. Risk derives from both Council operations
and those of its supply chain.
The increasing importance of delivering services
through digital channels and maximising efficiency
through effective and secure use of technology. This
includes a growing adoption of cloud-based computing
resources which extend processing capabilities, and
associated risks, beyond the Council’s network. 
Hybrid remote and mobile working is now the normal
working practice for over 3,000 staff. Such a distributed
work force increases the complexity of protecting
against cyber and data protection risks.
Failure by Services to adopt and comply with
strategies, policies and procedures may
result in a failure to adequately ensure the
desired levels of cyber-security required to
maintain and protect council systems and
data.
There may be a significant impact on the
authority through the release of personal
and/or sensitive information resulting in a loss
of public confidence and significant financial
loss incurred through fines and service
disruption. 
A successful cyber-attack (malicious external
or internal action) on the Council’s IT
environments could also result in significant
service disruption, loss of income streams
and possible data loss/exposure.
Impacts of a cyber-attack could include
economic (i.e. inability to collect online
payments), societal disruption (i.e. loss of
diaries and client appointments), and
reputational damage (i.e. loss of public
confidence in digital services).
It is recognised that it is not possible for any
organisation to expect to be completely protected
against continually evolving cyber threats. A threat
actor with sufficient motivation, resource and capability
will be able to compromise the most secure system.
The Council takes a sociotechnical approach to
reducing risk by continually developing protective
measures through technical, organisational and
people-focused controls. 
Technical controls are implemented in areas such as
network defences, secure configuration of systems,
user authentication, malware protection, and
vulnerability management. These are based on best
practice and independently tested on an annual basis
to confirm their effectiveness in accordance with
compliance schemes. 
The Council employ a fully managed Security
Operations Centre (SOC) service which provides
advanced monitoring, detection and response
capabilities on a 24 hours a day, 365 days a year
basis. 
The Council maintains a comprehensive set of policies,
standards, guidelines, metrics and reporting
mechanisms as part of its information security
governance structure. A comprehensive training and
awareness programme is delivered to nurture a cyber-
aware workforce and culture. 
4 4 
Status  Risk Score 
Heat Map 
Change in Score Approach 
No change  Treat
Stable 16

Page 16

Strategic Risk Action Plan Date Updated 15-Jan-2025
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG 
Incident Detection and Response – Recent cyber-attacks on public
sector organisations highlight the need for robust incident detection
and response procedures and technologies. The current response
procedures been shown to be effective based on incidents
experienced so far, however detection capabilities will need to be
reviewed and improved.
.
13 September 2024: 
Progress on the Digital Office joint procurement exercise has remained extremely
slow, as a result the Council have opted to procure a SOC/MDR service
independently. The procurement exercise is now progressing. 
15 January 2025: 
Following a process of market consultation and vendor engagement, the Council have
recently procured a Managed Security Operations Centre (SOC) service for an initial
period of three years. The project is currently in the implementation phase and we
anticipate the service being fully operational by the end of February 2025. 
31-Mar-2025  Fiona Walker 
Training and Awareness 
13 September 2024:
Cyber Security training continues to be delivered; however this is now a Teams
delivered course to maximise the attendance numbers. The Cyber Security
Essentials E-Learning course continues to be available for 2024 and is undergoing
a full re-write for 2025 to ensure this remains current. This training is being
supplemented with a programme of awareness raising initiatives including
educational staff news items and webinars.
Phishing simulations have continued in order to assess the effectiveness of
existing training and further increase awareness.
15 January 2025:
The mandatory Cyber Security Essentials E-Learning course remains our training
initiative with the greatest reach. This course has been fully re-written and is now
live for all employees to complete annually.
The mandatory E-Learning course is being supplemented by a range of further
initiatives to include all-staff webinars, awareness raising news posts and other
communications, this approach aims to ensure messaging is kept current and
reflects the rapidly evolving threat landscape.
Phishing simulations continue to be used to validate effectiveness of training and
awareness initiatives. 
Ongoing  Fiona Walker

Page 17

Risk Code SRR2526_R05 Risk Title Transformation Latest Note Date 25-Feb-2025
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact 
There is a risk that transformation and change
activities, which are core to the future delivery
models and long-term financial sustainability of
both the Council and Health and Social Care
Partnership, fail to deliver at the level of scale
and pace required.
Failure to deliver transformational change
will impact on the Council’s financial
sustainability, effectiveness of service
delivery and delivery of the outcomes set
out in the Council Plan 2023-28 and the
Local Outcome Improvement Plan
(LOIP).
Failure to deliver the HSCP
Transformation programmes across the
Partnership, involving North Ayrshire
Council (NAC) and NHS Ayrshire & Arran
(NHSAA) services may lead to the
identified outcomes not being delivered;
resulting in financial instability, reduced
performance, deteriorating patient
outcomes, and reputational damage
within North Ayrshire Health and Social
Care Partnership (NAHSCP). 
Failure to embed cultural transformation
activities may lead to difficulties in
building future workforce capacity and in
ensuring we have an engaged, skilled
and knowledgeable workforce to meet
service demand.
The transformation programme aligns to the Council Plan and is
monitored via the Transformation Board. The Board is chaired by
the Chief Executive. 
Workstreams have been developed across Transport and Travel,
Digital, Land and Property assets, Sustainability, Financial Inclusion
as well as ongoing reviews across Waste Services, ELC, Learning
Resources and Housing.
HSCP have an established Transformation Board to closely monitor
progress with plans, regular updates on programme to the IJB and
regular meetings with the Chief Executive and S95 Officer to review
progress and mitigation plans. Cultural transformation activities
continue to evolve to support the Council’s transformation and
improve effectiveness and capability. This includes sharing learning
and skills, engagement, design experiments and a whole systems
approach to transformation and change. 
Our workforce planning approach utilises a variety of tools and
techniques, such as career development, succession planning,
vacancy management, redeployment and early release schemes to
ensure our workforce requirements for the future, in terms of skills
and capabilities, are planned. Each Head of Service has a workforce
plan, and these are monitored six-monthly with continued HR
support and guidance to ensure service review and redesign of the
workforce is on track. 
3 4 
Status  Risk Score 
Heat Map 
Change in Score Approach 
No Change  Treat
Stable 12

Page 18

Strategic Risk Action Plan Date Updated 25-Feb-2025
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG 
Existing project level governance and controls remain effective and are
constantly reviewed. 
11 September 2024:
Programme continues to be developed and work being progressed
to feed a pipeline of financial efficiencies into the Budget programme
for 2025/26. 
25 February 2025:
Scoping has commenced to inform the next stages of a further
property transformation workstream, focusing maximising the
benefits that can be derived from the property estate (ie, capital
receipts, community wealth building, net-zero, etc). 
Quarterly 
Mark Boyd / Chief
Executive and
Executive Directors 
Review current governance arrangements and project delivery in view of
land and property workstream to seek optimal delivery aligned to the
council’s net zero ambitions. 
11 September 2024:
Governance arrangements in place and property programme being
progressed. This will feed into the 2025/26 Budget programme. 
25 February 2025:
Regional Land and Assets workstream being further developed with
NAC as lead organisation. 
Work to deliver the Irvine Locality Workstream, approved by Cabinet
in March 2024, is well progressed with the majority of staff now
occupying Cunninghame House. 
26-Feb-2025 
Mark Boyd / Chief
Executive and
Executive Directors

Page 19

Risk Code SRR2526_R06 Risk Title Climate Change Latest Note Date 24-Feb-2025
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Climate change is expected to continue and
worsen in the future if no action is taken,
with increases to mean global temperatures,
sea level rises and the increasing frequency
and severity of weather events such as
floods, heatwaves, droughts and storms.
More frequent and intense heavy rainfall
events increase the risk of soil erosion and
flooding.
Rises in mean sea level increases risks of
coastal erosion, flooding, saltwater intrusion
and soil salinisation (risk to agricultural land
and freshwater habitats). 
Severe weather is already affecting public
services across Scotland, with operational,
reputational, financial and legal
consequences.
There is also an ongoing impact of severe
winter weather including snowfall and
freezing temperatures which impact service
delivery and the integrity of our roads open
space and buildings infrastructure. This shift
in weather patterns caused by climate
change is also affecting biodiversity across
Scotland.
Increased frequency of severe weather
conditions and flooding events may lead to
more instances of damage to Council
infrastructure and property, interruptions to
service delivery and increased demands
on services, often with little notice.
Risk to life, transport disruption and
pollution to the local environment, as well
as impact adversely on the local economy
if businesses are unable to operate. 
Council requirement to provide immediate
response and manage the adverse effects
of more frequent and severe weather
emergency situations, including support to
local communities and businesses. 
The Council is required to comply with the
‘Public Bodies Climate Change Duties’
under the Climate Change (Scotland) Act
2009. These duties require the Council to
assess the risks, threats and opportunities
associated with climate change and
identify actions to increase resilience to
climate change.
North Ayrshire Council declared a Climate Emergency in June 2019, committing
to act on climate change and reduce carbon emissions. In January 2020 the
Council approved the target to become net-zero carbon by 2030, for both Council
estate emissions and area-wide emissions.
Following implementation of the Council’s third Environmental Sustainability and
Climate Change Strategy (2021-23), Cabinet approved the new Sustainable North
Ayrshire Strategy (2024-27) in December 2023. This strategy provides a road
map to achieve the net zero carbon emissions by 2030 target. 
There are 5 workstreams within the Sustainable North Ayrshire strategy, namely
Energy, Nature, Transport, Waste and Adaptation. We continue to utilise
Adaptation Scotland’s Capability Framework to ensure North Ayrshire takes a
strong, proactive approach to adapting to climate change. Officers are
participating in the Sustainable Scotland Network’s ‘Adaptation Scotland
Benchmarking Group’ to learn and share best practice with other local authorities. 
Adaptation actions are identified within the Ayrshire Flood Risk Management Plan
(2021), the Ayrshire Local Flood Risk Management Plan (2022), the Ayrshire
Shoreline Management Plan and in the Adaptation Capability Framework.
Flood studies are undertaken to help the Council identify areas that are at risk of
flooding and to appraise options to reduce flood risk to communities and
infrastructure.
In addition, actions to mitigate Climate Change risk are held within strategies such
as the Local Transport and Active Travel Strategy, Local Biodiversity Action Plan,
Vacant and Derelict Land Strategy and Weather and Winter Emergencies Plan.
Asset management plans are in place which are regularly reviewed for our
Roads, Fleet, Housing, Property and Open Spaces.
Furthermore, through the Ayrshire Civil Contingencies Team there are emergency
planning arrangements in place in the event of severe weather and flooding
conditions causing major disruption and damage to the area or to individual
communities within it. 
4 4 
Status  Risk Score 
Heat Map 
Change in Score Approach 
No change  Treat
Stable 16

Page 20

Strategic Risk Action Plan Date Updated 24-Feb-2025 
Analysis of Effectiveness of Controls  Further Action Required
Target Date
for
Completion
Officers
Responsible
Current
Status: RAG 
Reducing Carbon Emissions:
North Ayrshire Council declared a Climate Emergency in June
2019, committing to act on climate change and reduce carbon
emissions. In January 2020 the Council approved the target to
become net-zero carbon by 2030, for both Council estate
emissions and area-wide emissions. 
The Council has taken action against climate change since our
first Carbon Management Plan in 2006/07, by working to reduce
emissions associated with Council services, and using the
baseline year of 2005/06 from which to measure progress. 
Since the baseline year of 2005/06, Council estate emissions
have reduced by 67%, from 63,334 tonnes of carbon dioxide
equivalent (tCO2e) to 20,745 tCO2e. Area-wide emissions are
published by BEIS. Current records show total emissions have
reduced across North Ayrshire by 42.6%, from 1,454 kilo-tonnes
of carbon dioxide (ktCO2) in 2005 to 835 ktCO2 in 2019. 
To ensure North Ayrshire Council can develop a leading, cross-
sector and community led approach we established a Climate
Change Steering Group (CCSG) in 2021. The CCSG is chaired
by the Cabinet Member for Green Environment and Economy,
and brings together young people, local businesses and
community organisations from across North Ayrshire. 
Existing controls remain effective and are under review as our
response to climate change develops and we progress towards
achieving net zero by the 2030 target. 
20 September 2024:
Actions detailed within the Sustainable North Ayrshire Strategy continue to be implemented,
with progress monitored through the Council’s corporate performance management system
for example:
• Participation in the Scottish Climate Intelligence Service to expand action on and
monitor area-wide emissions.
• Publication of North Ayrshire’s first Local Heat and Energy Efficiency Strategy
(LHEES) and progression of initial actions from Delivery Plan.
• Development of two solar PV farms on former landfill sites.
• Completion of feasibility study for the decarbonisation of built assets.
• Progression of green hydrogen generation study.
• Development of North Ayrshire Nature Network strategy to address statutory.
requirements to tackle the nature crisis.
• Partnership working with Ayrshire Roads Alliance to undertake Electric Vehicle
Infrastructure project.
• Successful realisation of £725,998 external funding for domestic energy efficiency
measures through ECO4 Flex partnership. 
20 September 2024:
Progress continues on delivery of the Sustainable North Ayrshire Strategy, including:
• The two solar farm projects are nearing completion and are due to be energised in
the spring of 2025
• The North Ayrshire Network Strategy has been reviewed by the Policy Advisory Panel
and will be presented to Cabinet in March 2025
• A transformation workstream to address the decarbonisation of the fleet
• Corporate engagement on behaviour change, including undertaking a Leadership
Conference, Chief Officer Leadership Team workshop and Member Workshop.
Undertaking physical energy efficiency measures within the corporate estate (predominantly
lighting upgrades) and developing a forward programme of further interventions 
24 February 2025
Business and Sustainability Fund agreed through 2024/25 budget in delivery including
appointment of Programme Manager and development of Islands Net Zero Accelerator
(NZA) and Phase Two Mainland NZA programmes. Islands NZA Programme supported by
£25k funding from Zero Waste Scotland. 
Wider Place strategy updates continue to be provided through Pentana and governed
through the Place Project Board. 
31-Mar-2027  Russell
McCutcheon

Page 21

Strategic Risk Action Plan Date Updated 24-Feb-2025 
Analysis of Effectiveness of Controls  Further Action Required
Target Date
for
Completion
Officers
Responsible
Current
Status: RAG 
Flood Risk Management Plan:
Cycle 2 of the Ayrshire Local Flood Risk Management Plan has
been developed and was published on 31st December 2022.
Studies and modelling will be undertaken to identify and prioritise
vulnerable areas where financial damage and risk to life are most
likely. 
There is an ongoing programme of monthly inspections of debris
screens which have been installed to prevent vulnerable culverts
from blocking and causing flooding. CCTV inspections of culverts
are also undertaken to identify blockages and deterioration of
assets that might cause flooding. This has been effective in
reducing flooding, although there are capacity issues h that this
process cannot address. 
The Upper Garnock Valley FPS has been completed and is
currently providing flood protection. 
Ayrshire Shoreline Management Plan:
The Ayrshire Shoreline Management Plan will be replaced with a
Coastal Change Adaptation Plan. The adaptation plan will enable
the Council and other stakeholders to effectively plan our future
actions whilst allowing for flexibility in response to future changes.
It will incorporate recent international and UK advances in
adaptation and shoreline management planning to allow for local
interpretation and involvement. 
20 September 2024:
1. The Millport Coastal Flood Protection Scheme is 99% complete and we will commence a
further flood protection scheme at the Mill Burn, also in Millport.
2. The Three Towns flood study is underway. This study will confirm flood risk from the
Stevenston Burn & the Stanley Burn. The impacts of climate change will be evaluated.
Where flood risk is confirmed, scoping of the next steps will be completed and this will
inform the second stage of the study.
3. The North Ayrshire Water Body Clearance & Repair Schedule has been updated to
include details of the planned assessment of various water bodies. Where these
assessments find that the condition of the water bodies would or could contribute to
significant flood risk, then the necessary clearance and repair work will be scheduled and
completed.
4. Storm Gerrit brought widespread flooding to North Ayrshire on the 27 December 2023.
Emergency repairs to culverts in Millport and Kilbirnie have now been completed.
5. In April 2024, a blockage in the Minister’s Cast culvert increased flood risk to roads and
properties in Irvine including The Circuit leisure facility and Woodlands Primary School. The
clearance and repair framework was used to commission emergency works that restored the
performance of the culvert.
6. A draft coastal management study at Irvine & Stevenson is complete and was subject to
public consultation in September 2024. When finalised, the study will help to inform a local
Coastal Change Adaptation Plan. This plan will set out triggers for when the coastal erosion
and flood risk adaptations identified in the management study should be implemented. 
24 February 2025:
1. The construction of the Millport Coastal Flood Protection Scheme is complete. The
scheme performed well during Storm Éowyn and no significant reports of coastal flooding
in Millport were received. A pre-tender notification for the Millport Mill Burn Flood
Protection Scheme was issued in January 2025. It is anticipated that the contract will be
awarded in Autumn 2025, that construction will commence in late 2025, and that
completion will be in 2026.
2. The first stage of the Three Towns Flood Study was completed in February 2025 and the
scope has been agreed for the second stage. 
3. The scheduled clearance and repair work continues to be implemented to help reduce
flood impacts to people and property. 
4. Following completion of the coastal management studies for Stevenston & Irvine,
progress is being made to develop local Coastal Change adaptation plans for the study
areas. A site investigation is planned to confirm the presence of contaminated spoil and
how exposed this material could be to future coastal erosion. 
5. Following completion of the Upper Garnock Flood Protection Scheme and an update of 
30-Jun-2028  Thomas Reaney

Page 22

Strategic Risk Action Plan Date Updated 24-Feb-2025 
Analysis of Effectiveness of Controls  Further Action Required
Target Date
for
Completion
Officers
Responsible
Current
Status: RAG 
the Lower River Irvine hydraulic model, a consultant has been appointed to update the
relevant parts of the Council’s flood resilience plan, including measures at Cunninghame
House and Marress House.

Page 23

Risk Code SRR2526_R07 Risk Title Community Capacity Building and Empowerment Latest Note Date 3-Feb-2025
Risk Owner Rhonda Leith
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Unrealistic timescales for progressing of aspects of
legislation of the Community Empowerment Act
(Scotland) 2015, such as Community Asset
Transfer.
Pressure to support community capacity building
and the variation of needs within a reducing
workforce. 
Duplication of effort across HSCP and Locality
Partnerships to foster community participation and
deliver engagement activities. 
Complying with the complex and resource
intensive consultation legislation in service
redesign. 
Rising energy and utility costs relating to property
management.
Budget savings and pressure on property
maintenance budgets.
Where the risk is not managed effectively the
potential benefits of community capacity building
and empowerment may be lost. 
Widening inequality gap between those
communities where levels of capacity and
engagement with the empowerment agenda are
high and those with less social capital where
interest remains low, which constrains the ability
to influence the planning and delivery service.
Any disconnect between the Council’s
aspirations, community appetite for increasing
ownership of assets and what communities
themselves feel able and prepared to commit to
can result in community assets reverting back to
Council. 
Accelerating asset transfer risks losing services
and facilities and risks the ability to plan, connect
and deliver strategic services.
Over-engagement carries disengagement and
engagement fatigue.
Increased property costs can be a deterrent for
organisations engaging and completing the CAT
process. 
Lack of budget to undertake proactive
maintenance is resulting in NAC buildings falling
into disrepair detracting organisations from
progressing to lease and or ownership of NAC
assets.
Ongoing commitment to community empowerment and
locality partnerships from CPP. 
Six locality partnerships and alignment with HSCP
locality arrangements.
Leadership of the CPP Senior Officers’ Group. 
Enabling approach with community partners and support
with third sector interface to build capacity and identify
opportunities for growth and sustainability. 
Reviewed guidance and processes relating to
community empowerment functions.
Participatory budgeting approach local grants,
commitment to PB with partners and leading practice in
mainstreaming participatory approaches. 
External funding bid help for groups through regular
meetings with third sector, funders and funding officer.
Membership of The Consultation Institute.
Investment from Community Asset Transfer Start Up
Fund, prioritising additional staffing capacity to support
CAT in TACT. 
A collaboration and shared resource approach across
Connected Communities Teams will be taken to ensure
the Service deliver on this priority. 
Careful monitoring of staffing capacity to ensure
legislation is met. Standing item at Senior Manager
Meetings to assess impact
Progress discussions with key stakeholders re
dependencies on the progress and impact of delays. 
5 4 
Status  Risk Score 
Heat Map 
Change in Score Approach 
No change  Treat
Increasing 20

Page 24

Strategic Risk Action Plan  20-Feb-2025
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG 
Implementation of Community Empowerment Act:
Existing controls remain effective and are kept under review. 
19 September 2024:
New Strategic CLD Plan 2024 – 2027 in final stages of development and continues to
identify priorities and support available. 
31-Mar-2025  Rhonda Leith 
19 September 2024:
Linking with National partners i.e. Scottish Government to ensure timely communication to
any changes relating to national legislation and allow preparations to be in place. 
31-Dec-2024  Rhonda Leith 
Staff capacity:
Existing controls remain effective however forthcoming VER
structure changes will result in a reduction of CLD professional
staff and risks further pressures on staff to deliver effectively to
key outcomes. 
19 September 2024:
Function review within the CLD team underway to assess capacities and impact following
the service redesign. Focus will be on assigning resource to key priorities. 
20 February 2025:
Ongoing discussions being held with key stakeholders re capacity across Council services
and impact on timescales. 
31-Dec-2024  Rhonda Leith 
Duplication of effort:
Clearly defined roles and lean processes are reviewed and
maintained to avoid duplication of effort and minimise time and
resource wastage. The team foster open communication
channels with both staff and key stakeholders. 
19 September 2024:
The aim is to capture and address issues through the review of functions underway within
the CLD team. 
31-Dec-2024  Rhonda Leith 
Consultation:
Existing controls remain effective. Existing controls remain
effective and hybrid engagement models have been
implemented post covid to encourage and provide greater
access to participation. 
19 September 2024:
Cross Service support for consultation and engagement is being further developed with the
promotion of existing tools and supports across all Council services to encourage
ownership over service engagement. 
20 February 2025:
An extensive programme of budget engagement took place between 10 October and 25
November 2024 including surveys across six main themes as well as in person and online
focus groups. The approach was designed to support our residents to contribute their
views, make the surveys more accessible and avoid digital exclusion. This has resulted in
4,461 responses and almost 40 community conversations across the six budget themes,
more detailed feedback on proposals and considerable engagement with community
groups across North Ayrshire. The engagement has also enabled our residents to bring
petitions on specific options to the Audit and Scrutiny Committee and Cabinet,
demonstrating a high level of engagement with democracy within our communities 
31-Mar-2025  Rhonda Leith

Page 25

Increased property costs and lack of investment in community
assets. 
19 September 2024:
Matter escalated through a range of mechanisms including Health & Safety, PMI/Risk
meetings and reporting systems as well as more frequent management on-site building
visits to assess building condition and escalate accordingly. 
A strategic plan is in the early stages of development to address identified condition issues
in buildings earmarked for potential Community Asset Transfer (CAT). Specific investment
funds have been allocated to support this initiative. 
20 February 2025:
Strategic plan for use of CAT investment funds in place. ELT oversight continues of plan
and spend. Horizon scanning for other potential investment opportunities carried out on an
ongoing basis. 
31-Mar 2025  Rhonda Leith

Page 26

Risk Code SRR2526_R08 Risk Title Property Asset Risk Latest Note Date 25-Feb-2025
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact 
The long-term impact of restricted budget
availability for investment in the Council’s property
assets means these assets are in declining
condition and have greater long term investment
needs.
Systemic building safety issues have been
evidenced by issues such as national high profile
safety issues, and the presence of RAAC through
the public sector property portfolio. These have
highlighted the substantial increasing burden of
property asset management. 
There have been a number of near misses or
critical failures of aging heating plant and
equipment which the council cannot afford to
replace on a programmed basis. 
Inflationary pressures, and on-going volatility in the
construction & related activities sphere, place
further difficulties in the ability of restricted budgets
to address all priorities. 
Maintenance issues and failure of building
components are increasingly likely to result in
disruption to service delivery. There is also an
increasing risk of health and safety and statutory
compliance obligations not being achieved. 
Property events requiring significant interventions
leading to service disruption, closure of facilities,
decant etc. are in increasing in frequency and
often over-lapping (often coinciding with weather
events).
Property condition information is gathered and recorded
within the Council’s electronic asset management
system, providing a baseline to measure building
element lifecycle replacement requirements across the
corporate estate.
The limited investment available is therefore targeted on
priorities. 
Reactive maintenance, and statutory compliance are
also undertaken corporately by PMI, by appropriately
trained / experienced staff. 
There is an on-going Transformation programme
workstream focusing on property rationalisation as a
means of reducing the financial burden of the estate
through reducing overall area occupied (aligned to
carbon reductions). 
Post Incident reviews and lessons learned exercises
with actions undertaken where feasible to do so. 
Risk based property reviews are underway to examine,
on a property by property basis, where property risks
have the potential to impact service delivery. The
information gathered influences both investment plans
and business continuity plans. This work is on-going in
respect of the school estate and is being rolled-out to
other services’ assets. 
An additional £0.5m has been allocated in the 25/26
budget to the Property Lifecycle Budget to address
condition issues within the corporate estate. 
In addition, £0.5m has been allocated to undertake
energy efficiency measures in the property estate and a
joint Sustainability / PMI working group has been
established to identify and progress relevant investment.
This will be coordinated to ensure optimal benefit for
both energy efficiency and property condition. 
Business Continuity Planning, taking cognisance of the
risks posed by potential building unavailability is also
being strengthened. 
4 5 
Status  Risk Score 
Heat Map 
Change in Score Approach 
No Change  Treat
Stable 20

Page 27

Strategic Risk Action Plan Date Updated 25-Feb-2025
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG 
CC&M team within PMI managing reactive maintenance and
statutory compliance.
Team resources stretched; however, restricted budgets are principal risk.
13 September 2024:
Team resources remain stretched, presently exacerbated by recent staff departure,
recruitment exercise currently on-going. 
21 February 2025:
Although previous vacancies were successfully filled, further staff departure now requires
recruitment process – continuing to stretch resources. 
Ongoing  Russell
McCutcheon 
Asset management team within PMI collecting asset condition
information and leading prioritisation of lifecycle investment.
Improved asset management system is being investigated; however, restricted budgets
are principal risk. 
13 September 2024:
Work continues in relation to the new asset management system, including bench-marking
and information sharing with other authorities. 
Ongoing  Russell
McCutcheon 
Property rationalisation programme
Locality based property review work currently underway to increase scale and pace of
implementation.
13 September 2024:
The Irvine Property Accommodation programme received Cabinet approval in March 24
and is progressing to programme. 
21 February 2025:
The programme of accommodation moves flowing from the Irvine Property Review is well
advanced and scoping has commenced for further review of the Council’s estate across all
localities. 
Ongoing  Russell
McCutcheon 
Risk based property review process
Requires up to date property information, including client information and cross service
buy-in to be effective. 
13 September 2024:
The Education Estate has been reviewed in its entirety and quarterly meetings have been
established to continue this work on a priority-basis.
The approach has also been utilised in respect of the communities estate.
21 February 2025
In addition to the estate review meetings noted above, Business Continuity Planning,
taking cognisance of the risks posed by potential building unavailability is also being
strengthened. 
Ongoing  Russell
McCutcheon