NORTH AYRSHIRE COUNCIL 
29 May 2025 
Audit and Scrutiny Committee 
Title:    Audit Scotland: North Ayrshire Council Best Value
Thematic Management Report : Transformation 
Purpose:  To present the findings of the recent Audit Scotland report on
how councils are redesigning and delivering more efficient
services to achieve planned outcomes 
Recommendation:  Note the report findings and the recommended improvement
actions 
1. Executive Summary 
1.1 The Accounts Commission’s “Local government in Scotland Financial bulletin 2023/24”
notes that councils need to intensify transformation activity, progressing at scale and
pace to ensure their financial sustainability. 
1.2 Audit Scotland carried out the Best Value Audit earlier in the year. This report covers
the thematic aspect of the Best Value audit requirements. The Accounts Commission
has directed auditors to report on transformation and how councils are redesigning and
delivering more efficient services to achieve planned outcomes. 
1.3 The full report findings are attached in the appendix of the report. This includes
recommended areas of improvement actions which have been agreed by senior council
officers. Audit Scotland representatives will be in attendance at the committee to present
the findings. 
2. Background 
2.1 The Accounts Commission’s “Transformation in councils” report recognises that, while
work has been ongoing in relation to local government transformation for decades, a
step change is required and the pace and scale of transformation must increase
significantly. Transformation, through greater collaboration with partners, will be key for
councils to deliver more sustainable service models in challenging financial climates. 
2.2 Audit Scotland carried out the Best Value Audit earlier in the year. The audit covers
the thematic aspect of the Best Value audit requirements. The Accounts Commission
has directed auditors to report on transformation and how councils are redesigning
and delivering more efficient services to achieve planned outcomes. In carrying out
the work, auditors have considered the following questions:

Page 2

• To what extent does the council have clear plans for transformation that link to its
priorities and support long-term financial sustainability? 
• To what extent do the council’s programme management arrangements facilitate
effective oversight of its transformation plans? 
• To what extent are partners and communities involved in the development and
delivery of the council’s plans for transformation? 
2.3 The report findings are attached within the appendix of the report, including
recommended areas of improvement actions. Representatives from Audit Scotland will
be in attendance to present the findings. 
3. Proposals 
3.1 Members are asked to note the report findings and the recommended improvement
actions. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None 
Legal 
4.3 None 
Equality/Socio-economic 
4.4 None 
Climate Change and Carbon 
4.5 None 
Key Priorities 
4.6 The Best Value Thematic Audit aligns to the Council’s Key priority of a Sustainable
Council 
Community Wealth Building 
4.7 None

Page 3

5. Consultation 
5.1 Audit Scotland engaged with various council officers throughout the course of the audit. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Mark Boyd, Head of Finance, on 01294 324560. 
Background Papers
0

Page 4

North Ayrshire
Council
Best Value thematic management report 
Transformation: how councils are redesigning and
delivering more efficient services to achieve planned
outcomes 
Prepared by Audit Scotland
May 2025

Page 5

Best Value thematic work:  | 2 
Contents 
Key messages 3
Introduction 5
Transformation planning 8
Programme management 13
Partnership working and community engagement 15
Impact of transformation 19
Appendix 22 
Accessibility
You can find out more and read this report using assistive technology on
our website www.audit.scot/accessibility.

Page 6

Key messages | 3 
Key messages 
1 The Accounts Commission’s Local government in Scotland Financial bulletin
2023/24 notes that councils need to intensify transformation activity,
progressing at scale and pace to ensure their financial sustainability. 
2 In 2024 we reported that North Ayrshire Council’s underlying service cost
base is not sustainable and reserves will be depleted over the longer term
unless future recurring savings are made through the transformation of its
services and other measures. 
3 The council’s current transformation programme, known as its Sustainable
Change Programme, was approved in 2023 and clearly sets out how it
intends to transform its services, in line with its priorities, through five
workstreams and six service reviews. Between 2021/22 and 2024/25 the
council achieved financial efficiencies from its Sustainable Change
Programme of £3.136m. It plans to make further efficiencies of £8.5m over
the next three years.
4 The council’s latest Medium Term Financial Outlook has identified a structural
funding gap of £46.7m in the three-year period to 2027/28 (including HSCP
pressures). Projected savings from transformation fall significantly short of the
savings required. Officers are clear that future recurring savings also need to
be made through workforce changes, cuts in services, and council tax and
fees and charges increases. However, the transformation programme needs
to be sufficiently ambitious to respond to the scale of the financial challenges.
5 The council has robust officer-led governance arrangements in place to
monitor its Sustainable Change Programme through its Transformation
Board. The Executive Leadership Team are all members of the
Transformation Board and so are well-sighted on the council’s transformation
projects. However, there is scope for the council to improve its public
reporting on transformation to provide assurance about how the council plans
to change, to sustain services in the future. 
6 The council has a well-established and well-resourced transformation team. It
has a Change and Service Redesign Fund - an investment fund created by

Page 7

Key messages | 4 
the council more than eight years ago to help drive transformation. Nearly
£0.8m has been drawn down from the Fund in the last two years although not
all of this has been spent on transformation.
7 The council has shared examples of where it is working well with partners to
deliver transformation with the aim of generating savings and improving
outcomes, but its current transformation programme is primarily internally
focused. There is scope for the council to consider opportunities for more
radical transformational change with partners. 
8 There are discussions ongoing across the senior leadership of North
Ayrshire, East Ayrshire and South Ayrshire Councils to explore further
opportunities for public sector reform and collaboration including the Ayrshire
Economic Strategy. These developments will be subject to scrutiny by elected
members as they progress. Elected members will need to make difficult
decisions on how the use of limited resources is prioritised going forward.
Plans need to be innovative and ambitious.
9 The council has provided good examples of consulting with its communities in
relation to transformation projects and using the results to influence how
services are delivered. The recent extensive budget engagement process
included consultation with residents on many activities overseen by the
Transformation Board. 
10 The council provides regular and detailed information on the financial and
non-financial benefits of individual transformation workstreams and service
reviews to the Transformation Board. The benefits of individual projects are
also reported in individual council reports.  
11 The council has provided evidence of using Equality and Children’s Rights
Impact Assessments in relation to its transformation projects, where
appropriate, and has provided examples of engagement with user groups
leading to changes being made in how services are delivered.

Page 8

Introduction | 5 
Introduction 
1.  Transformation is about radically changing how councils operate and
deliver services to achieve planned outcomes in a financially sustainable
way (Transformation in councils, Accounts Commission, October 2024).
The 2023 Local Government Overview (LGO) notes that councils have
never faced such a challenging situation. Service demands have
increased after the Covid-19 pandemic and funding is forecast to reduce in
real terms. 
2.  The Accounts Commission’s Transformation in councils report
recognises that, while work has been ongoing in relation to local
government transformation for decades, a step change is required and the
pace and scale of transformation must increase significantly.
Transformation, through greater collaboration with partners, will be key for
councils to deliver more sustainable service models in challenging
financial climates.
3.  This report sets out how the council is redesigning and delivering more
efficient services to achieve planned outcomes. It builds on what we have
reported previously in this area in our 2023/24 Annual Audit Report.  
4.  The Accounts Commission’s Strategy (2021-26) sets out its priorities to
focus on inequalities, funding, communities and recovery. The Code of
Audit Practice sets out the Best Value work required to report on these
priorities. 
5.  This report covers the thematic aspect of the Best Value audit
requirements. The Commission has directed auditors to report on
transformation and how councils are redesigning and delivering more
efficient services to achieve planned outcomes. In carrying out the work,
auditors have considered the following questions: 
• To what extent does the council have clear plans for transformation
that link to its priorities and support long-term financial
sustainability?
• To what extent do the council’s programme management
arrangements facilitate effective oversight of its transformation
plans?
• To what extent are partners and communities involved in the
development and delivery of the council’s plans for transformation?

Page 9

Introduction | 6 
• To what extent has the council considered the impact of its
transformation activity, including on vulnerable or protected
groups?  
6.  An improvement action plan is included at Appendix 1 of this report.
This sets out audit recommendations in key areas, and the council’s
planned response including responsible officers and dates for
implementation.
7.  The coverage of the work is in line with the expectations for council’s
arrangements for the seven Best Value themes in the Local Government in
Scotland Act 2003, Best Value Statutory Guidance 2020 and we have
considered the Accounts Commission’s transformation principles set out in
Transformation in councils (Exhibit 1).

Page 10

Introduction | 7 
Exhibit 1
Transformation principles
Transformation is about radically changing how councils operate and deliver services to achieve
planned outcomes in a financially sustainable way.
Principle  
Vision
Have a clear vision that sets out the intended end state of any transformation
activity, focused on: 
• delivering large-scale recurring savings or generating income for the council,
contributing to its longer-term financial sustainability
• improving outcomes for citizens in line with council priorities
• taking a whole-system approach to see and realise opportunities both within
councils and more widely
• meeting the needs of the people who use services and reduce inequalities
• focusing on preventative activity, where applicable, to reduce the demand for
services and to make them sustainable in the longer term.
Planning
• Be clear on the scale of the change required and ensure transformation plans
are sufficiently ambitious to credibly respond to the scale of the challenge.
• Commit staff with appropriate skills, time, and resources to ensure
transformation occurs at the scale and pace required and that there is enough
capacity for the changes to be embedded.
• Be clear about the timescales, costs, outcomes, and anticipated impacts of
transformation projects.
• Show urgency and progress projects at pace without compromising
appropriate governance on projects.
Governance
• Have a clear process for monitoring, evaluating, and reporting progress.
• Put in place effective governance and escalation processes so that the
transformation activities are well managed in their own right, but also able to
be given priority alongside other business-as-usual activities. 
Collaboration 
• Develop better working relationships with communities and/or partners to
achieve a sustainable model of service delivery.
• Actively consider the opportunities offered by regional or national sectoral
collaboration, or by integrating services locally with partners, or by supporting
individuals and communities to achieve desired outcomes in place of an
existing service.
• Learn from good practice across Scotland and beyond.
Innovation 
• Implement new ways of thinking, including innovation, creativity and a desire,
willingness, and action to change and do things in new and different ways that
achieve the outcomes needed.
• Embed the right culture and behaviours to manage change and help maximise
the contribution of all the team.  
Source: Accounts Commission, Transformation in councils, October 2024

Page 11

Transformation planning | 8 
Transformation planning 
8.  The council needs to ensure it can deliver sustainable services now and
in the future, and difficult decisions will need to be made to achieve this.
The Accounts Commission’s Local government budgets 2024/25 briefing
noted that councils’ cumulative funding gap between 2025/26 and 2026/27
is £780 million. This means that, cumulatively, councils need to identify
and deliver recurring measures such as savings or increased income of
five per cent of their overall revenue budget to be financially sustainable in
the short term. 
9.  In January 2025, the Accounts Commission advised in its Local
government in Scotland Financial bulletin 2023/24 that councils need to
intensify transformation activity, progressing at scale and pace to ensure
their financial sustainability and how councils plan to use their reserves,
make savings and transform their services needs to become more
transparent. 
10.  The council’s latest Medium Term Financial Outlook (MTFO) for the
period 2025/26 to 2027/28 was presented to the council in October 2024. 
It identified a number of specific financial challenges in relation to the
availability of Scottish Government funding for local authorities, the impact
that anticipated demographic profile and other demand and cost pressures
will have on the council’s cost base, and the strategies available to
address the resultant funding gap. 
11.  The MTFO identifies a structural funding gap of £46.7m (including
HSCP pressures) which must be addressed as part of the council’s
Medium-Term Financial Plan. 
12.  In February 2025, the council agreed a balanced budget for 2025/26
but only after approving a council tax increase of seven per cent (£5.0m)
and using: 
• a further £4.0m of reserves;
• further savings across Directorates of £4.809m, including new
approved savings of £2.547m, operational budget adjustments of
£2.254m and previously approved savings of £0.008m;
• non-recurring savings of £9.5m relating to the reduction in employer
pension fund contributions;
• a previously approved 100 per cent council tax premium in respect
of second homes (£1.3m); and

Page 12

Transformation planning | 9 
• a revised policy for non-domestic rates empty property relief
(£0.253m).
13.  The council’s latest Medium-Term Financial Plan indicates budget
shortfalls of £3.6m in 2026/27 and £7.4m in 2027/28 (excluding HSCP
pressures) after the planned use of reserves totalling £3.5m in 2026/7 and
£1.8m in 2027/28. This is after assuming the council will fund a maximum
three per cent increase in staff pay and council tax increases of five per
cent for the next two years. The current planning assumption by the
council for years 2026/27 and 2027/28 is that financial pressures facing
the HSCP will be met by savings and recovery actions. However, the IJB’s
total estimated budget gap for 2026/27 and 2027/28 ranges from a best-
case scenario of a £11.6m deficit to a worst-case scenario of a £27.6m
deficit. This position represents a material risk to the financial sustainability
of the council.
14.  Financial efficiencies from the Sustainable Change Programme of up
to £8.5m are planned from 2025/26 to 2027/28. However, these fall
significantly short of the savings required to achieve financial balance and
will only be part of the council’s solution to closing its funding gap. The
underlying service cost base is not sustainable and reserves will be
depleted over the longer term unless further recurring savings are made
through transformation of services, service reduction, service withdrawal
and income generation.

Page 13

Transformation planning | 10 
Findings Evidence
The council’s
transformation programme,
known as its Sustainable
Change Programme, clearly
sets out how it intends to
transform its services in
line with its priorities
through five workstreams
and six service reviews. 
The council is clear that the
primary driver behind its
transformation programme
is the need to deliver
financial savings to
address the council’s
financial challenges and
protect frontline services.
There are strong links
between transformation
and the council’s financial
plans and transformation is
included in the council’s
risk register. 
• The council’s current transformation programme, known as
its Sustainable Change Programme, was approved in 2023
and consists of five workstreams and six service reviews. 
• The council is clear that the primary driver behind its
transformation programme is the need to deliver financial
savings to address the council’s financial challenges.
• The current workstreams in the Sustainable Change
Programme are sustainability, non-commercial property,
commercial property, digital, developing data assets and
the tourist visitor levy. Each of these workstreams contain
multiple transformation projects. 
• All five workstreams and six service reviews have clear
links with the council’s priorities. For example, its digital
programme is linked to its Wellbeing, Communities and
local democracy and A Sustainable Council priorities. 
• There is a dedicated section in the council’s annual budget
documents on the Sustainable Change Programme. As
well as setting out the savings generated to date, it notes
that the more progress made through delivery of the
Sustainable Change Programme, the less impact there
could be on delivery of the council’s core services. 
• There are many mentions of transformation in the council’s
December 2023 Long-term Financial Outlook and Medium-
Term Financial Outlook. Reference is made to the fact that
the scale and pace of transformation needs to increase if
the council is to respond effectively to the challenges it
faces.
• The council classifies transformation as a high risk in its
risk register reflecting the risk that transformation and
change activities fail to deliver at the level of scale and
pace required. The council describes risks associated with
delivering the current transformation programme and
developing a pipeline of future initiatives. Risk control
measures put in place by the council include oversight
from the Transformation Board and workforce planning.  
• The council’s risk score in relation to transformation
reduced slightly in 2024 to reflect a more mature
programme with a greater level of governance,
accountability and confidence around delivery.

Page 14

Transformation planning | 11 
Findings Evidence
The council’s Sustainable
Change Programme
consists of five
workstreams and six
service reviews. Regular,
detailed updates are
compiled for each
workstream and service
review. These outline clear
aims, costs and desired
outcomes for users of
services for the majority of
activities. 
• Each of the council’s five transformation workstreams
contain multiple transformation projects. For example, the
sustainability workstream includes two Solar PV Projects,
fleet decarbonisation and expansion of EV structure whilst
the Digital Programme workstream includes website
development and online improvements in accessing the
council. Thirty-three projects and activities are listed in total
across the five workstreams.
• The council has provided the audit team with the detail of
projects under each workstream including status. As at
March 2025, 19 transformation projects were in progress,
two were on hold and two were complete.
• The six service reviews are: early learning and childcare
(now complete), learning resource, waste services,
financial inclusion, housing services and external
residential placements (through the Brighter Pathways
programme). 
• Regular, detailed, internal updates are submitted to the
Transformation Board for each workstream and service
review. These outline clear aims, costs and desired
outcomes for users of services for the majority of activities.
Detailed updates are provided on savings and projected
savings, where these have been identified.

Page 15

Transformation planning | 12 
Findings Evidence
The council’s projected
savings from
transformation fall
significantly short of the
savings required to achieve
financial balance and are
only part of the council’s
solution to closing its
funding gap. 
• The council’s latest Medium Term Financial Outlook
(MTFO) has identified a structural funding gap of £46.7m in
the three-year period to 2027/28 (including HSCP
pressures) Financial efficiencies from the Sustainable
Change Programme amount to £3.136m from 2021/22 to
2023/24, with further efficiencies of up to £8.5m planned
from 2025/26 to 2027/28. 
• The council reported in its Long-term financial outlook that
transformation alone will not offer the full solution to the
financial gap identified in the plan.  
• The council’s structural funding gaps are currently being
met with a combination of recurring and non-recurring
solutions. Officers recognise that future recurring savings
need to be made through transformation of services,
workforce changes, cuts in services, and council tax and
fees and charges increases.  Elected members will need to
make difficult decisions on how the use of limited
resources is prioritised going forward. Plans will need to be
sufficiently ambitious to respond to the scale of its financial
challenges. 
• The council also stated in its long-term financial outlook
that it needed to deliver change and transformation at
scale and pace over the medium and longer term to
address its financial challenges.
• The council is also exploring areas of wider reform to
address its financial challenges. These include national
initiatives through the Improvement Service and Digital
Office that will provide further opportunities for councils to
take a collective approach to areas of service delivery and
opportunities for sharing services on a regional basis. 
Recommendation
The council should ensure its plans are sufficiently ambitious to respond
to its financial challenges. It should clearly set out the extent to which
savings from transformation will help address the budget shortfalls set
out in its Medium-Term Financial Plan.

Page 16

Programme management | 13 
Programme management 
15.  It is essential that the council has good programme management
arrangements in place to ensure it is making sufficient progress against its
transformation plans. It is important that the council has the structures and
the staffing resource in place to deliver its transformation ambitions. In
addition, the council must ensure that both senior officers and elected
members have appropriate oversight of progress.
Findings and evidence relating to the council’s programme management
arrangements 
Findings Evidence
The Transformation Board
provides effective
oversight of the council’s
transformation programme. 
The council has a well-
established and well-
resourced transformation
team.
• The Chief Executive chairs the council’s bi-monthly
Transformation Board. All Chief Officers are members of
the Board. 
• The Board considers and agrees work to be progressed
under the Sustainable Change programme. It receives
updates on the progress of all projects within the
programme and provides strategic oversight of the
programme. 
• Each of the five workstreams has its own project board in
place which feeds into the Transformation Board. 
• The transformation team is well-resourced with 11
members of staff. Members provides project management
and business analysis support to transformation projects.  
• Internal audit recently carried out work on transformation
and change management. It found there was substantial
assurance regarding the governance and management of
transformation projects within the council. It highlighted
that the programme is reviewed regularly at a senior level
and proportionate governance arrangements for individual
workstreams sit underneath.

Page 17

Programme management | 14 
Findings Evidence
Members of the Executive
Leadership Team are well-
sighted on the council’s
transformation projects.
They are also responsible
for approving applications
to an investment fund to
help drive transformation.
Nearly £0.800m has been
drawn down from the Fund
in the last two years
although not all of this has
been spent on
transformation. 
• The Executive Leadership team are all members of the
Transformation Board so are well-sighted on the projects
within the workstreams and the service reviews. 
• The Change and Service Redesign Fund is an investment
fund created by the council more than eight years ago to
provide upfront investment to help drive transformation
activity. It is also used to help address temporary resource
challenges. £0.460m was drawn down from the Fund in
2023/24 and £0.330m in 2024/25. Although the balance at
the end of 2024/25 was £2.1m the total uncommitted
balance was £0.189m.
• Examples of projects that have been supported by funding
from the Change and Service Redesign Fund over the last
few years include Development Analysts to support the
council’s Digital Workstream, resource to support Fleet
Decarbonisation and APSE specialist resource as part of
the Waste Services Review.
Elected Members receive
updates on transformation
projects through the annual
budget process, the
council’s performance
reporting framework and
reports to individual
committees. 
• Officers engage with elected members from September to
work towards agreeing the budget for the next year.
Member engagement sessions are held if deemed
appropriate. A detailed session on the transformation
programme was held with the Administration in December
2024 and as part of the Elected Member Development
Programme in February 2025.
• As discussed in Part 4, since January 2025 the council’s
six-monthly progress report on its Council Plan has
included a section on its transformation programme.
• In addition elected members will consider standalone
reports on certain transformation projects, for example the
early learning and childcare review, that was reported to
Cabinet.
• In January 2025, the council took a report to its Audit and
Scrutiny Committee assessing itself against the Accounts
Commission’s October 2024 Transformation in councils
report.

Page 18

Partnership working and community engagement | 15 
Partnership working and
community engagement 
16.  The Best Value in Scotland report noted that councils must now
rethink how they work together, and with local partners and communities,
to provide financially sustainable services. Few councils provide services
jointly or share support services across different councils to a great extent.
The scale and nature of the challenge, as set out in the Transformation in
councils report, means that it is only by working more collaboratively that
councils and their local partners, communities and the third sector will be
able to provide sustainable local services.
17.  In January 2025, the Accounts Commission advised in its Local
government in Scotland Financial bulletin 2023/24  that how councils plan
to use their reserves, make savings and transform their services needs to
become more transparent. The need to consult local communities and
clearly communicate the implications for local services of the budget
decisions taken has never been more important.
Findings and evidence relating to the council’s partnership working and
community engagement arrangements 
Findings Evidence
There are discussions
ongoing across the senior
leadership of North
Ayrshire, East Ayrshire and
South Ayrshire Councils to
explore further
opportunities for public
sector reform and
collaboration including the
Ayrshire Economic
Strategy. These
developments will be
subject to scrutiny by
elected members as they
progress.
• The council recognises that as financial and demographic
challenges increase there is a greater need to work with
partners to share services and increase collaboration.
• Initial discussions are underway around potential
opportunities for further shared services on a regional
basis. The council is involved in exploring a Pan-Ayrshire
approach with East Ayrshire Council and South Ayrshire
Council, with a view to potentially sharing services. There
are some barriers to this level of joint working including the
siloed approach to funding, governance, and reporting
arrangements. Also, the three Ayrshire councils have
different political make-ups. The council refers to the vital
role of national government in enabling more
transformational partnership working between different
bodies.

Page 19

Partnership working and community engagement | 16 
Findings Evidence
The council’s
transformation programme
is primarily internally
focused. However, the
council has shared
examples of where it is
working well with its
partners and listening to its
communities in relation to
transformation. The recent
extensive budget
engagement process
involved consulting with
residents on many
activities overseen by the
Transformation Board.   
• The council notes that although much of its current
transformation programme is internally focused, eg fleet
decarbonisation and maximising rental income across its
estate, it will work with partners and its communities when
opportunities arise. 
• It provided the audit team with examples of transformation
projects involving collaboration with local partners,
communities and the third sector. For example, in 2023, an
engagement programme was undertaken as part of its cost
of living and child poverty initiatives. Its No Wrong Door
mini public enquiry workshops were undertaken with third
sector partners and voluntary organisations. The focus of
these sessions was to identify where the council could
improve, what it was doing well and any gaps. The output
from these sessions helped to influence the development
and delivery of the projects within the council’s Accessing
our Council transformation workstream.
• The Accessing our Council transformation workstream also
used the results of a public engagement survey conducted
in 2022 to gain an understanding of customers’
perceptions on how they were accessing council services
alongside a Peoples Panel survey asking customers about
how they access council services. The results of both
surveys were used to develop the projects within the
Accessing our Council programme such as the introduction
of the council’s new Contact Us process.
• A wider programme of community engagement took place
in winter 2024 on the council’s budget (Exhibit 3). This
included several areas where progress is managed by the
Transformation Board such as: Review of Economic
Development, Growth and Regeneration Services, Review
of waste charges, Realigning the level of teaching resource
and pupil support assistants across schools, charging a
tourist visitor levy and sharing services on a regional basis.
Consulting on specific budget options rather than generic
areas of priority gained a higher level of engagement from
communities.
There is evidence of the
council drawing on the
good practice of other
organisations when
developing transformation
projects.
• There is evidence of the council drawing on other councils’
good practice in transformation projects. For its Solar PV
Farms Project (Exhibit 2), it made positive links with
councils in England embarking on similar projects and
reflected their learning in its plans. Also, a regular item on
the agenda of the Transformation Board is horizon
scanning, supported by evidence of what transformation
projects are being undertaken by other councils.

Page 20

Partnership working and community engagement | 17 
Findings Evidence
There are limited joint
funding arrangements
between the council and its
local partners for
transformation projects. 
• The council is aware of many opportunities in the Pan-
Ayrshire collaboration work that could lead to joint funding. 
• At present there are limited joint funding arrangements
between the council and local partners in relation to its
current transformation projects.  
• The council provided examples of joint funding
arrangements for initiatives funded partly by the Scottish
Government. Two members of its staff were funded by the
Scottish Government’s Child Poverty Accelerator Fund to
work on the Single Shared Assessment Project, part of the
Developing our Data Assets transformation workstream.
Also, the council received a Fairer Futures Partnership
Grant to create a Child Poverty Strategy Team.
• North Ayrshire Council is part of a 5G Innovation Region
project, alongside East Ayrshire and South Ayrshire, that
received funding of £3.8m from the UK Government. This
project aligns to the council’s Digital transformation
workstream.
Exhibit 2 
Solar PV Farms Project – learning from councils in England
North Ayrshire Council formed effective relationships with
experienced councils in England to assist in the design and
development of its Solar PV Farms Project 
• In 2021, the council approved the installation of two solar PV farms at
former landfill sites at Nethermains and Shewalton. This project
contributes to the council’s work on climate change and the farms are key
elements of its Sustainable North Ayrshire Strategy. The solar PV farms,
due to become operational later this year, will provide clean, renewable
energy to supply the local electricity grid and aim to contribute to a
reduction in fuel poverty through the availability of affordable energy. 
• As North Ayrshire was the first council in Scotland to install large-scale
solar PV farms, it decided to meet with various councils in England and
Wales to learn from their experiences. Due to the positive relationships
established, the council still meets regularly with some of the other
councils to discuss the future of their solar PV projects. For example,
representatives from North Ayrshire Council visited a site operated by
Warrington Council in York. In return, Warrington Council visited the
council and did a presentation for key partners and stakeholders on the
benefits of its solar PV farms. The council also worked with Strathclyde
University which provided help and support with the projects.
Source: North Ayrshire Council

Page 21

Partnership working and community engagement | 18 
Exhibit 3
Engaging with communities on transformation projects as part of the annual budget
engagement process
The council conducted an extended, comprehensive budget
engagement process during Winter 2024 that included asking for
views on several transformation projects
Due to the scale of the financial challenges facing the council, it decided to
carry out a wider than usual programme of community engagement from
October to November 2024 as part of the budget process. Surveys
included a range of options across six main themes, including several
transformation projects such as the learning review, sharing services on a
regional basis and economic development. As the surveys were themed,
people were able to select the areas they were most interested in, rather
than having to complete all themes. 
The refreshed approach resulted in an increased response, from 200 in
2024/25 to 4,461 in 2025-26, in addition to community discussions that
were held. The outcome of the budget engagement process was
communicated to elected members and helped them shape the approach
to future service delivery.
From the transformation proposals included in the budget consultation,
two were agreed as budget savings: the learning review and economic
development service review. 
Source: North Ayrshire Council

Page 22

Impact of transformation | 19 
Impact of transformation 
18.  It is important that the council has success measures in place to
demonstrate the impact of its transformational activity on service quality;
outcomes for people who use services, inequalities and/or savings. 
Findings and evidence relating to the impact of the council’s transformation
activity 
Findings Evidence
The council provides
regular and detailed
information on the financial
and non-financial benefits
of individual transformation
workstreams and service
reviews to the
Transformation Board. The
benefits of individual
projects are also reported
in individual council
reports.   
• The council provides regular and detailed monitoring on the
progress of individual transformation workstreams and
service reviews to the Transformation Board. These updates
include detail on savings and projected savings as well as
intended outcomes. 
• As individual projects complete, the council reports examples
of benefits being realised from individual projects, eg the
Accessing our council transformation workstream (Exhibit 4)
reports on a reduction in public facing email addresses and
phone numbers, a streamlined customer journey that is cost
effective.
• The council has set out the expected benefits of the solar PV
farms project described in Exhibit 2. These include an
approximate £0.4m savings each year from 2026/27 and a
reduction in carbon emissions that will help the council meet
its net-zero targets.

Page 23

Impact of transformation | 20 
Findings Evidence
The council reported
publicly on its progress
with selected
transformation projects in
its Council Plan update in
January 2025. It does not
currently report publicly on
how it is progressing with
delivering transformation
as a whole in terms of
planned and realised
financial and non-financial
benefits. 
• The council provides an overview of its Sustainable Change
Programme in its budget documents. 
• The council produces six-monthly progress reports on its
Council Plan. In January 2025, the progress report included a
dedicated section on transformation providing a summary of
progress on transformation workstreams where key
milestones had been reached during the last six months.
Realised and expected outcomes are referred to. For
example, it notes that the Digital Workstream is expected to
deliver £0.2m of savings by the end of 2027 and realised
benefits from the Accessing our council work is listed. 
• This public-facing report, whilst providing a flavour of its
transformation work, did not provide an overview of the
progress the council is making in delivering transformation as
a whole in terms of planned and realised benefits.   
The council has provided
evidence of using Equality
and Children’s Rights
Impact Assessments in
relation to its
transformation projects,
where appropriate, and has
provided examples of
engagement with user
groups leading to changes
being made in how
services are delivered. 
• We reported in 2023 that the council uses its equality impact
assessment process effectively to ensure children’s rights,
human rights, socio-economic inequalities and the challenges
islands face are considered in new policies, procedures,
strategies and the budget-setting process
• The council uses an Equality and Children’s Rights Impact
Assessment (ECRIA) process. Children’s Rights, Human
Rights, the Fairer Scotland Duty and Island proofing have all
been integrated into this online tool. New or revised policies,
procedures and strategies are assessed to ensure the
council is meeting the needs of the equality duty.
• We asked the council for examples of when it has used the
ECRIA process in relation to transformation projects. The
examples provided were in relation to Contact Us, the
Housing single point of contact project (no full ECRIA was
required) and website redesign. These involved testing of a
new form and process with the Employee Disability Group
and consultation with The Disability Forum, Over 65s’ groups,
Trade Unions, Ayrshire Youth Voice, Drop-in visits to
libraries, NHS Learning and Disability team, Island groups.
• As a result of user testing of the Contact Us form in May
2023, an issue was identified with software used by visually
impaired users which was investigated and re-tested and
successfully resolved the issues raised.
• On the council’s website, ECRIAs carried out for the 2025/26
budget proposals are available. 
• The council is currently working to make all ECRIAs meet
accessibility requirements and so, at present, all other
ECRIAs can only be accessed by emailing the council
directly.

Page 24

Impact of transformation | 21 
Exhibit 4 
North Ayrshire Council’s Accessing our Council project
The council has used an array of success measures to capture the
impact of its project on improving access to council services 
• North Ayrshire Council’s Accessing our Council project was approved in
March 2022. It focuses on improving customer access to council services
through transforming services as well as achieving savings. 
• The project aimed to streamline how customers access council services
digitally and ensure that customers have the information they need at the
first point of contact. The project team developed a new contact us form
for customers to use which presents a drop-down list of the main council
services, which is then linked to relevant pages on the website to provide
more information related to the request. The council captured the impact
of its new approach using a benefits tracker, which included establishing
baseline figures for a number of indicators. 
• The new form went live in June 2023 and the following impact has been
reported: 
• the introduction of the new Contact Us process has led to the number of contacts 
coming into services from the website to reduce by 78 per cent since June 2023. 
This has resulted in a reduction of one FTE no longer being required to manage and 
direct service requests. 
• online interactions have increased from 24 per cent in 2021 to 38 per cent in 2023. 
• the introduction of a web assistant / chat bot in late 2023 has led to over 200 requests 
every week being answered by the chat bot.
• Reduction in phone numbers on the council website of 39 per cent (from 322 to 199)
• Reduction in email addresses on council website of 34 per cent (293 to 200) 
• Shift to online transactions with the council and less reliance on phone calls or visiting
customer centres, increased from 63 per cent to 65 per cent.
Source: North Ayrshire Council 
Recommendation
To provide assurance to elected members and the public about how the
council plans to change to sustain services in the future the council
should report publicly on how it is progressing with delivering
transformation as a whole in terms of planned and realised financial and
non-financial benefits.

Page 25

Appendix | 22 
Appendix
Improvement action plan
Issue/risk Recommendation
Agreed management
action/timing
1. Transformation savings fall
significantly short of the
savings required
The council’s latest MTFO
identifies a structural funding gap
of £46.7m (including HSCP
pressures) which must be
addressed as part of the council’s
Medium-Term Financial Plan.
Whilst we recognise that
transformation alone will not offer
the full solution to the financial
gap identified in the MTFO, the
level of financial efficiencies from
the Sustainable Change
Programme should be
commensurate with the scale of
the financial challenges.
The council should ensure its
plans are sufficiently
ambitious to respond to its
financial challenges. It should
clearly set out the extent to
which savings from
transformation will help
address the budget shortfalls
set out in its Medium-Term
Financial Plan.
Accepted
Management response
It is recognised that the
level of financial
efficiencies should be
commensurate with the
scale of the financial
challenges. Further work
will be progressed as
part of the council’s
medium-term financial
planning to set out clearly
how the council plans to
address budget gaps
through further
transformation and
reform activity and
through a broader
package of measures,
including areas of service
review and possible
reduction, opportunities
for further revenue
generation and an
ongoing planned use of
council reserves. 
Responsible officer
Head of Service
(Financial Services)
Actioned by
31 March 2029

Page 26

Appendix | 23 
Issue/risk Recommendation
Agreed management
action/timing
2. Public reporting on progress
with transformation
The council does not currently
report publicly on how it is
progressing with delivering
transformation as a whole in
terms of planned and realised
financial and non-financial
benefits. 
To provide assurance to
elected members and the
public about how the council
plans to change to sustain
services in the future the
council should report publicly
on how it is progressing with
delivering transformation, as
a whole, in terms of planned
and realised financial and
non-financial benefits.
Accepted
Management response
The development of
more public facing
material will be produced
to demonstrate the
council’s progress on the
Sustainable Change
Programme. This will
include use of the
council’s new website to
further promote activity
and the progress being
made to address the
financial challenges. 
Responsible officer
Head of Service
(Financial Services)
Actioned by
30 September 2025

Page 27

North Ayrshire Council 
Best Value thematic management report 
Transformation: how councils are redesigning and
delivering more efficient services to achieve planned
outcomes 