North Ayrshire Council, Cunninghame House, Irvine KA12 8EE         
Audit and Scrutiny Committee 
A Meeting of the Audit and Scrutiny Committee of North Ayrshire Council will be
held in the Council Chambers, Ground Floor, Cunninghame House, Irvine, KA12
8EE on Thursday, 27 August 2026 at 10:00 to consider the undernoted business. 
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.   Where possible, the meeting will be live-streamed
and available to view at  https://north-ayrshire.public-
i.tv/core/portal/home.   
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
2 Minutes
The accuracy of the Minutes of the Ordinary Meeting of the Audit and
Scrutiny Committee held on4 June 2026 and the Special Meeting held on
15 June 2026 will be confirmed and the Minutes signed in accordance
with Paragraph 7 (1) of Schedule 7 of the Local Government (Scotland)
Act 1973 (copies enclosed). 
3 Audit Scotland - Asset Management Best Value Report
Submit report by the Head of Finance on the findings from the recent Best
Value Audit on Asset Management (copy enclosed). 
4 2025/26 Elected Member Requests
Submit report by the Head of Democratic Services informing of the
Council's performance relating to Elected Member requests handled in the
Financial Year 2025/26 (copy enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
5 2025/26 Complaint Report
Submit report by the Head of Democratic Services on the Council's
complaint performance and volumes and trends of complaints received
in Financial Year 2025/26 (copy enclosed). 
6 Elected Member Development
Submit report by the Head of Democratic Services on the development
sessions provided to Elected Members over the 12 months from
September 2025 to August 2026, and on future planned development
sessions (copy enclosed). 
7 Internal Audit Reports Issued and Update
Submit report by the Head of Finance on the findings of Internal Audit work
completed since June 2026 (copy enclosed). 
8 Internal Audit Plan 2026/27: Progress as at 31 July 2026
Submit report by the Head of Finance on the progress made in delivering
the 2026/27 Internal Audit Plan (copy enclosed). 
9 Accounts Commission’s Briefing: Local Government Budgets
2026/27
Submit report by the Head of Finance on the key messages identified
within the recently published Accounts Commission’s Briefing (copy
enclosed). 
10  National Planning Improvement Framework (NPIF)
Submit report by theExecutive Director (Communities and Housing) on
the outcome of the Planning Service’s National Planning Improvement
Framework (NPIF) (copy enclosed). 
11  Standing Item of Business: Consideration of future business for
scrutiny 
12  Urgent Items
Any other items which the Chair considers to be urgent.
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE  
Webcasting  
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at  https://north-ayrshire.public-
i.tv/core/portal/home,where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.    
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.    
Generally, the press and public will not be filmed. However, by entering the
Council Chambers and using the press or public seating area, you
acknowledge that you may be filmed and that any information pertaining to
you contained in the video and oral recording of the meeting will be used
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. In
making this use of your information the Council is processing data which is
necessary for the performance of a task carried out in the public interest.    
If you have any queries regarding this and, in particular, if you believe
that use and/or storage of any particular information would cause, or be
likely to cause, substantial damage or distress to any individual, please
contact  dataprotectionofficer@north-ayrshire.gov.uk 
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Audit and Scrutiny Committee Sederunt 
John Bell (Chair)
Donald Reid (Vice Chair)
Cameron Inglis
Shaun Macaulay
Tom Marshall
Matthew McLean
Davina McTiernan
Donald L. Reid
John Sweeney 
Chair: 
Apologies: 
Attending: 
4

Page 5

Audit and Scrutiny Committee
4 June 2026 
At a Meeting of the Audit and Scrutiny Committee of North Ayrshire Council at 10.00
a.m. involving participation by remote electronic means and physical attendance
within the Council Chambers, Irvine. 
Present (Physical Participation)
John Bell, Donald Reid and Cameron Inglis. 
Present (Remote Participation)
Tom Marshall, Davina McTiernan, Donald L Reid and John Sweeney. 
In Attendance 
R. McCutcheon, Executive Director; L. Cree, Head of Sustainability, Transport &
Corporate Property); and G. Wilson, Senior Manager (Engineering Services) (Place);
D. Hammond, Executive Director (Communities and Housing); A. McClelland, Head
of Service (Education); A. Johnson, Principal Manager (Business Support) (Health &
Social Care Partnership); M. Boyd, Head of Service; A. Fenton, Team Manager
(Audit); and A. Fitzharris, Team Manager (Risk) (Finance); F. Walker, Head of
Service; and F. Carlyle, Team Manager (HR) (People & ICT); R. Lynch, Senior
Manager (Legal); S. Wilson, Committee Services Officer, and E. Reid, Marketing &
Digital Assistant, (Communications) (Democratic Services) (Corporate Services). 
Chair
Councillor Reid in the Chair. 
1. Declarations of Interest 
In the absence of the Chair, and in terms of Standing Order 6.6, the Members
unanimously appointed Councillor Reid to the Chair. 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors. 
Councillor Bell joined the meeting at this point. 
2. Minutes 
The accuracy of (a) the Minutes of the Meeting of the Audit and Scrutiny Committee
held on 12 March 2026 and (b) the Minutes of the Special Meeting of the Audit and
Scrutiny Committee held on 14 April 2026 were confirmed and the Minutes signed in
accordance with Paragraph 7 (1) of Schedule 7 of the Local Government (Scotland)
Act 1973. 
Agenda Item 2
5

Page 6

3.  Corporate Fraud Team Annual Report 2025/26 
Submitted report by the Head of Finance providing an update on the work of the
Corporate Fraud Team during 2025/26. 
Officers responded to Members’ questions and the Committee agreed to note the
work carried out by the Corporate Fraud Team. 
4. Internal Audit Annual Report 2025/26 
Submitted report by the Head of Finance providing an annual report on the work of
Internal Audit during 2025/26 and providing an opinion on the governance, risk
management and internal control environment of the Council. The Internal Audit
Annual Report 2025/26 was attached at Appendix 1 to the report. 
Officers responded to Members’ questions and the Committee agreed to note the
content of the annual report on the Council’s governance, risk management and
internal control environment. 
5. Internal Audit Reports Issued 
Submitted report by the Head of Finance informing of the findings of Internal Audit
work completed since March 2026. Further information on the Key Findings and
Action Plans in regard to Capital Monitoring, Payroll Transaction Testing and
Building and Estates Maintenance were attached at Appendix 1 to the report. 
Officers responded to Members’ questions and the Committee agreed to consider
the outcomes from the Internal Audit work completed. 
6.  Internal Audit and Corporate Fraud Action Plans: Quarter 4 Update 
Submitted report by the Head of Finance advising on the progress made by Council
Services in implementing the agreed actions from Internal Audit and Corporate
Fraud reports as of 31 March 2026. 
Officers responded to Members’ questions and the Committee agreed to note the
current position with the implementation of Internal Audit and Corporate Fraud
actions. 
7. Annual Governance Statement 2025/26 
Submitted report by the Head of Finance seeking approval of the Council’s Annual
Governance Statement for 2025/26 which will be included within the draft Annual
Accounts. 
The Committee agreed to approve the draft Annual Governance Statement as
outlined at Appendix 1 to the report. 
6

Page 7

8. Strategic Risk Register 2026/27 
Submitted report by the Head of Finance informing of the Council’s agreed Strategic
Risk Register for 2026/27 attached at Appendix 1 to the report. 
Officers responded to Members’ questions and the Committee agreed to note the
Strategic Risk Register for 2026/27 attached at Appendix 1 to the report. 
9. Accounting Policies 2025/26 
Submitted report by the Head of Finance seeking approval of the accounting policies
which will be adopted in the preparation of the Council’s annual accounts for the year
to 31 March 2026. The proposed Accounting Policies 2025/26 was attached at
Appendix 1 to the report. 
Officers responded to Members’ questions and the Committee agreed to approve the
proposed Accounting Policies 2025/26 attached at Appendix 1 to the report. 
10. External Audit Action Plan Update 2024/25 
Submitted report by the Head of Finance providing an update on the actions
identified in the 2024/25 External Audit Action Plan attached at Appendix 1 to the
report. 
Officers responded to Members’ questions and the Committee agreed to note the
actions identified in the 2024/25 External Audit Action Plan attached at Appendix 1 to
the report. 
11. Disclosure Scotland Act 
Submitted report by the Head of People & ICT providing an overview of the recent
legislative and procedural changes to the PVG Scheme and outlining how North
Ayrshire Council has implemented and are managing these changes. 
The Service agreed to provide a copy of the presentation delivered by the Team
Manager (HR), a list of regulated posts which require a PVG check as identified by
Disclosure Scotland and the percentage of North Ayrshire Council employees who
were subject to a PVG check under the Disclosure Scotland Act (2020). The Service
agreed to undertake to arrange an Elected Members development session to provide
all Members with an update on the work carried out as a result of the change of
legislation. 
Officers responded to Members’ questions and the Committee agreed to note the
content of the report. 
7

Page 8

12. Roads Maintenance and Repairs: Policies and Procedures 
Submitted report by the Executive Director informing of the arrangements for
monitoring and control of utility works on the public road network and for planning,
scheduling and undertaking Council operations. 
Officers responded to Members’ questions and the Committee agreed to note the
processes in place for undertaking, co-ordinating and monitoring street works. 
13. Standing Item of Business : Consideration of Future Business for
Scrutiny 
There were no future reports requested by the Committee. 
Councillor Sweeney thanked the Executive Director (Communities and Housing) for
the briefing paper provided to Members on North Ayrshire Council Housing Policy
which was requested at the meeting of the Audit and Scrutiny Committee held 12
March 2026. 
14. Urgent Items 
There were no urgent items. 
15. Investigation Reports Issued 
Submitted report by the Head of Finance informing of investigation reports finalised
since the last meeting. 
The Committee agreed to note the outcomes of the investigations carried out. 
The meeting ended at 12.00 p.m. 
The full meeting proceedings can be viewed at
https://north-ayrshire.public-i.tv/core/portal/home 
8

Page 9

Audit and Scrutiny Committee
15 June 2026 
At a Special Meeting of the Audit and Scrutiny Committee of North Ayrshire Council
at 10.00 a.m. involving participation by remote electronic means and physical
attendance within the Council Chambers, Irvine. 
Present (Physical Participation)
John Bell, Cameron Inglis, Tom Marshall, Matthew McLean, Donald Reid, Donald L
Reid and John Sweeney. 
Present (Remote Participation)
Davina McTiernan and Shaun Macaulay. 
In Attendance 
D. Hammond, Executive Director and K. Bell, Team Manager (Housing Strategy)
(Communities and Housing); S. Anson, Executive Service (Education) M. Boyd,
Head of Service (Finance); L. Cree, Head of Service (Sustainability, Transport &
Corporate Property) (Place); A. Craig, Head of Service, C. Stewart, Committee
Services Officer, and H. Young, Senior Committee Services Office (Democratic
Services) (Corporate Services). 
Also in Attendance
Eleanor Collier, Joe Cullinane, Robert Foster, Christina Larsen, Jim Montgomerie
and Ian Murdoch. 
Chair
Councillor Bell in the Chair. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors. 
2.  Call In: Revenue Budget 2025/26: Financial Performance to 31 March 2026 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026
advising of the financial performance for the Council for 2025/26. The original
Cabinet report and minute from the Cabinet meeting which took place on Tuesday 2
June 2026 was attached at Appendix 1 to the report. Appendix 2 to the report
contained a briefing note provided by the Head of Finance in response to the matters
raised in the call-in request form. 
The Cabinet, on 2 June 2026, considered a report on the financial performance for
Council 2025/26. Cabinet amended the recommendation to the report by determining
to allocate £1.496m of underspend to the 26/27 revenue budget with the funds to be
used to create an Our Places, Our Communities fund designed to benefit all North
Agenda Item 2
9

Page 10

Ayrshire communities with details of the fund being brought to council on the 24th of
June for debate and approval. 
Subsequently, a call-in request was received from Councillors Cullinane, Foster and
Montgomerie in the following terms:-   
Reason for Call-In 
“In passing its budget, the Council set Council Tax bands at a level required to fund
its expenditure requirements, including prioritising investment in areas such as
education and roads. 
The £1.496million underspend should therefore not be spent on another of the
administrations pet projects, particularly when the evidence of the last four years
shows that these pots of money are not used in a timeous manner. 
Instead, the underspend should be returned to council taxpayers.” 
Desired Outcome 
“That the £1.496million allocated to an ‘Our Places, Our Communities fund’ be re-
allocated to provide a Council Tax rebate, reflecting the fact that our expenditure
requirements for 2026/27 have already been funded.  
Although this outcome proposes a Council Tax rebate, we acknowledge officers'
advice that as matters relating to setting Council Tax levels are reserved to Council
and that for this outcome to be implemented it will require a decision of Full Council,
including the suspension of 15.5 and 25.1 of Standing Orders Relating to Meetings
and Proceedings of the Council, as Council Tax was set within the last six months.
The Audit & Scrutiny Committee is asked to accept the call in and recommend that
the matter is referred by Cabinet to Council for further consideration and
determination.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Cullinane addressed the Committee in support of the call-in request and
was heard in response to Members’ questions. 
The Chair then invited Councillor Larsen, as the Cabinet Member for Finance, to
address the meeting. Councillor Larsen explained the reasoning for the Cabinet
decision and referred to a briefing note from the Head of Finance provided at
Appendix 2 to the report. She was also heard in answer to Members’ questions. 
The Head of Finance was then heard in relation to the report presented to Cabinet
and on issues raised by the call-in. 
Councillors Cullinane and Larsen were heard in summing up. 
10

Page 11

Councillor Sweeney, seconded by Councillor D. Reid, moved that the Committee
agree to accept the terms of the call-in request and refer the matter to the Cabinet
for further consideration, with the recommendation that the matter is referred to
Council to determine the use of the underspend and that Council suspends Standing
Orders to consider the proposal regarding a Council Tax rebate. 
As an amendment, Councillor Macaulay, seconded by Councillor McTiernan moved
that the Committee agree not to support the call-in request and that the decision of
Cabinet should stand. 
There followed questions, debate and summing up on the motion and amendment
presented for consideration. 
Thereafter, on a division and a roll call vote, there voted for the amendment,
Councillors Macaulay and McTiernan (2) and for the motion, Councillors Bell, D.
Reid, Inglis, Marshall, McLean, D.L Reid and Sweeney (7). The motion was declared
carried. 
Accordingly, the Committee agreed (a) to support the call-in request; and (b) that the
matter be referred to Cabinet for further consideration, with the recommendation that
the matter is referred to Council to determine the use of the underspend and that
Council suspends Standing Orders to consider the proposal regarding a Council Tax
rebate. 
3.  Call In: North Ayrshire Housing Acquisition Strategy 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026 on
the proposed Housing Acquisition Strategy 2026- 2031. The original Cabinet report
was attached at Appendix 1 to the report. Appendix 2 to the report contained a
briefing note provided by the Executive Director (Communities and Housing) in
response to the matters raised in the call-in request form. 
The Cabinet, on 2 June 2026, considered a report on the proposed Housing
Acquisition Strategy 2026-2031. 
Subsequently, a call-in request was received from Councillors Cullinane, Foster and
Montgomerie in the following terms:-   
Reason for Call-In 
“It is wrong to suggest this policy will have no impact on the Council’s Community
Wealth Building (CWB) strategy. A key component of the strategy is to increase
procurement spend with North Ayrshire, and Ayrshire, businesses creating economic
and socio benefits from investing in the local economy. The fact that Ayrshire based
companies have won our council house building contracts has made a significant
contribution to us achieving the initial procurement targets set out in the first CWB
strategy published in 2020. 
This policy is the opposite of this approach. It will see a significant proportion of our
investment in Council housing, the majority of which comes from the Council with the
11

Page 12

rest from Holyrood, be transferred to private housing developers, many of which are
large national developers. It will see that investment extracted from the Ayrshire
economy. 
We remain as committed to Community Wealth Building as were in 2020. We
therefore reject this policy.” 
Desired Outcome 
“That the Council reaffirms its commitment to Community Wealth Building by
rejecting this policy and redoubling our efforts to ensure that Ayrshire based
companies can bid for, and win, the contracts to build the next generation of Council
houses in North Ayrshire.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Cullinane addressed the Committee in support of the call-in request. 
In the absence of Councillor Hill, as the Cabinet Member for Communities, Housing
and the Islands, the Chair then invited Councillor Collier to address the meeting. She
was also heard in answer to Members’ questions. 
The Executive Director and the Team Manager (Housing Strategy) (Communities
and Housing) were heard in response to Members’ questions. 
Councillors Cullinane and Collier were heard in summing up. 
Councillor Sweeney, seconded by Councillor D. Reid, moved that the Committee
agree to accept the terms of the call-in request and refer the matter to the Cabinet
for further consideration with the recommendation that the policy be rejected. 
As an amendment, Councillor Macaulay seconded by Councillor McTiernan moved
that the Committee agree not to support the call-in request and that the decision of
Cabinet should stand. 
Thereafter, on a division and a roll call vote, there voted for the amendment,
Councillors Inglis, Macaulay, Marshall, McTiernan and D.L Reid (5) and for the
motion, Councillors Bell, D. Reid. McLean and Sweeney (4) and amendment was
declared carried. 
Accordingly, the Committee agreed not to support the call-in request and that the
decision of Cabinet should stand. 
12

Page 13

4. Call In: Ardrossan Campus Project Update 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026 to
note the current progress of the Ardrossan Campus project, including current
projections in relation to costs and programme. The original Cabinet report was
attached at Appendix 1 to the report. 
The Cabinet, on 2 June 2026, considered an update report on the current progress
of the Ardrossan Campus project, including current projections in relation to costs
and programme. 
Subsequently, a call-in request was received from Councillors Stalker, Murdoch and
Stephen in the following terms:-   
Reason for Call-In 
“This decision is being called in because there are some real concerns about how
the Ardrossan Campus project is progressing. The report shows a significant cost
increase of around £10 million, along with delays pushing completion back to May
2028. 
There are also questions about how risks have been handled, especially around
ground contamination and the challenges of building on a contaminated site. It’s not
clear if these issues were fully understood early on, or if more could have been done
to avoid the impact they have had. On top of that, using additional capital funding to
cover the extra costs raises concerns about what this means for and the overall
budget of the campus and what more flexibility funding will be made available in
future budgets. 
Overall, this call-in is about getting reassurance that the project is still under control,
that risks are being properly managed, and that it continues to represent good value
for the Council and local communities.” 
Desired Outcome 
“To provide assurance on and seek greater information on the cost, programme, risk
management, governance and wider capital implications of the Ardrossan Campus
project, ensuring it remains deliverable, financially sustainable and represents value
for money.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Murdoch addressed the Committee in support of the call-in request and
was also heard in response to Members’ questions. 
As a point of clarification it was confirmed that the decision of Cabinet was to note
the update provided in the report presented. 
13

Page 14

The Chair then invited Councillor Collier, as the Cabinet Member for Green
Environment and Economy, to address the meeting. Councillor Collier explained the
reasoning for the Cabinet decision and was also heard in answer to Members’
questions. 
The Executive Director (Education) and the Head of Service (Sustainability,
Transport & Corporate Property) (Place) were heard in answer to Members’
questions. 
Councillors Cullinane and Collier were heard in summing up.  
Councillor Inglis, seconded by Councillor McLean, moved that the Committee agree
to accept the terms of the call-in request with a recommendation that a progress
report is taken to a future meeting of Council in six months for consideration. There
being no amendment the motion was declared carried. 
Accordingly, the Committee agreed (a) to support the call-in request; and (b)
recommended to Cabinet that an update report is taken to a future meeting of
Council in six months. 
The meeting ended at 12.10 p.m. 
The full meeting proceedings can be viewed at
https://north-ayrshire.public-i.tv/core/portal/home 
14

Page 15

NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee 
Title:    Audit Scotland - Asset Management Best Value Report 
Purpose:  To update committee on the findings from the recent Best Value
Audit on Asset Management 
Recommendation:  That committee notes the findings from the recent Best Value
Audit report on Asset Management arrangements within North
Ayrshire Council 
1. Executive Summary 
1.1 The focus of Best Value Audit work this year is on a thematic review of Asset
management arrangements across Councils. Audit Scotland carried out the audit with
support from officers in North Ayrshire Council. 
1.2 The scope of the audit was to assess how well North Ayrshire Council is managing
assets to achieve its corporate objectives and respond to challenges around financial
sustainability and climate change. 
1.3 The report on the audit findings is included within the appendix of the report for
committee to consider. The findings are welcome and reflect robust asset management
arrangements across the Council. It is also noted that the report does not include any
improvement actions. Members of Audit Scotland will attend the meeting to present the
findings. 
2. Background 
2.1 Full details of Audit Scotland’s Best Value thematic audit on asset management
arrangements within North Ayrshire Council are included within the appendix of the
report. 
2.2 The details of the audit include an assessment of asset management planning
arrangements, governance and performance, partnership working and community
engagement 
2.3 The key findings from the audit include: 
Agenda Item 3
15

Page 16

• North Ayrshire Council demonstrates an effective approach to its asset management.
The strategic approach is outlined in its overarching Corporate Asset Strategy and
Plans. This gives consideration to the changing needs of its population, new ways of
working and also sets out how it will support the council to meet its net zero emission
commitments.  
• There is clear strategic alignment between the Corporate Asset Strategy, service level
asset management plans, the Capital Programme and the council’s priorities. 
• The council has sufficiently considered the affordability of its capital programme and
asset management plans whilst navigating substantial financial pressures that are
projected to widen budget gaps in the coming years. 
• The council’s reporting and monitoring arrangements enable good scrutiny and
oversight of progress towards implementing its capital programme and asset
management plans. 
• North Ayrshire Council is progressing well with the delivery of its capital programme
and asset management plans. The council’s performance against the asset
management Local Government Benchmarking Framework indicators has varied over
time. The most recent data shows that the council is currently performing above the
national average and is ranked within the top quartile nationally for these indicators 
• North Ayrshire Council works collaboratively with partners to optimise how assets are
delivered. It has a clear approach to assessing Community Asset Transfer requests
and can demonstrate how it has worked with communities to inform decision making
in relation to specific assets. 
• No improvement actions have been identified or required by the council from the audit 
work. 
3. Proposals 
3.1 It is recommended that committee notes the findings from the recent Best Value Audit
report on Asset Management arrangements within North Ayrshire Council. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The asset management plans inform the annual budget programme and capital
investment plans. 
Human Resources 
4.2 None. 
16

Page 17

Legal 
4.3 None. 
Equality/Socio-economic 
4.4 All required impact assessments are undertaken in the course of managing assets
across the Council. 
Climate Change and Carbon 
4.5 Asset management arrangements support the Council’s key priority in addressing
climate change, demonstrated through investment in renewables, vehicles and energy
efficiency improvements across the property estate. 
Key Priorities 
4.6 The audit notes the linkages between the Council’s asset management planning
arrangements and the Council’s key priorities. 
Community Wealth Building 
4.7 A key focus of asset management arrangements including progress on community
asset transfers, maintenance of community facilities etc. 
5. Consultation 
5.1 Audit Scotland have engaged with a number of Council officers throughout the course
of the audit. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Mark Boyd, Head of Finance, on 01294 324560. 
Background Papers
0
17

Page 18

Best Value thematic work – Asset
management
North Ayrshire
Council 
How well councils are managing assets to achieve
their corporate objectives and respond to challenges
around financial sustainability and climate change 
Prepared by Audit Scotland
June 2026
18

Page 19

Contents | 2 
Contents 
Contents 2
Key messages 3
Introduction 4
1. Asset management planning 6
2. Governance and performance 17
3. Partnership working and community engagement 23 
Accessibility
You can find out more and read this report using assistive technology on
our website www.audit.scot/accessibility.
19

Page 20

Key messages | 3 
Key messages 
1 North Ayrshire Council demonstrates an effective approach to its asset
management. The strategic approach is outlined in its overarching Corporate
Asset Strategy and Plans (December 2025). This gives consideration to the
changing needs of its population, new ways of working and also sets out how
it will support the council to meet its net zero emission commitments.
2 There is clear strategic alignment between the Corporate Asset Strategy,
service level asset management plans, the Capital Programme and the
council’s priorities. 
3 The council has sufficiently considered the affordability of its capital
programme and asset management plans whilst navigating substantial
financial pressures that are projected to widen budget gaps in the coming
years.
4 The council’s reporting and monitoring arrangements enable good scrutiny
and oversight of progress towards implementing its capital programme and
asset management plans. 
5 North Ayrshire Council is progressing well with the delivery of its capital
programme and asset management plans. The council’s performance against
the asset management Local Government Benchmarking Framework
indicators has varied over time. The most recent data shows that the council
is currently performing above the national average and is ranked within the
top quartile nationally for these indicators 
6 North Ayrshire Council works collaboratively with partners to optimise how
assets are delivered. It has a clear approach to assessing Community Asset
Transfer requests and can demonstrate how it has worked with communities
to inform decision making in relation to specific assets. 
7 We have not identified any improvement actions required by the council from
our work.     
20

Page 21

Introduction | 4 
Introduction 
1.  Asset management directly impacts how councils provide services and
achieve their own corporate priorities and longer-term financial
sustainability. Limited capital budgets make it challenging for councils to
maintain their existing assets and estates, invest in new assets and
achieve net zero targets. Exhibit 1 sets out some principles for effective
asset management, informed by CIPFA guidance and the Infrastructure
Investment Plan for Scotland.
Exhibit 1 
Principles for effective asset management
Principle What this looks like in practice
Strategic alignment
Councils’ asset management strategies align with their corporate
objectives, financial plans, new ways of working, population needs
and net zero commitments.
Investment hierarchy
To support sustainability and cost-effectiveness, asset management
strategies prioritise:
1. maintaining and optimising existing assets
2. repurposing or upgrading existing assets to meet the needs of the
community
3. new investment only when necessary
Monitoring condition
and performance
Councils regularly assess the condition, suitability and performance of
their assets, to help inform investment priorities and support
continuous improvement.
Governance and
accountability
Councils have clear roles and responsibilities for asset management,
with regular, transparent reporting and senior oversight.
Community asset
transfers
Councils have transparent and robust processes in place to assess
and support requests for community asset transfers.
Place-based
approaches
Councils collaborate across services and other public and third sector
organisations to manage assets as a collective resource across their
local area. This has the potential to achieve savings, better align
service provision and create opportunities for joint working. 
Source: Audit Scotland
21

Page 22

Introduction | 5 
2.  The Code of Audit Practice sets out the requirements for Best Value
audit work. This report covers the thematic aspect of the Best Value audit
requirements. The Accounts Commission has directed auditors to report
on how well councils are managing their assets. In carrying out the work,
auditors have considered the following questions: 
• Part 1 – To what extent does the council have a clear asset
management strategy and plans that are affordable, align with its
corporate objectives, the changing needs of its population, and net
zero commitments?
• Part 2 –To what extent do the council’s governance and
accountability arrangements support effective asset management?
• Part 3 – To what extent does the council have a robust approach to
working with partners and communities in managing its assets?
3.  The coverage of the work is in line with the expectations for council’s
arrangements for the seven Best Value themes in the Local Government in
Scotland Act 2003, Best Value Statutory Guidance 2020. 
22

Page 23

1. Asset management planning | 6 
1. Asset management planning 
4.  Councils’ capital programmes are a necessary component of
modernising services to improve outcomes for local communities. Doing
this successfully requires good strategic medium- to long-term asset
management and planning. The Accounts Commission’s Local
government budgets 2025/26 briefing reported that capital funding for
2025/26 had increased but remained lower than in 2023/24 and that
investing in new buildings and assets is increasingly expensive. Councils
are relying on borrowing as the main source of funding for capital projects.
In 2025/26, councils intend to borrow £3.13 billion, an increase from
£2.67 billion in 2024/25.
Findings and evidence relating to the council’s asset management strategic
planning arrangements 
Judgements Evidence 
1. The council has an up-
to-date and well-informed
asset management strategy
that clearly sets out its
approach and priorities for
managing and developing
its assets. It covers a
sufficient period enabling
strategic planning and is
clear about how progress
will be monitored and when
priorities will be reviewed. 
1. North Ayrshire Council’s overarching Corporate Asset
Strategy (2025-2030) was updated and approved by
Cabinet in December 2025. It provides a comprehensive
overview of the Council’s key assets and includes
individual asset management plans for six categories of
asset including: property, housing, roads, fleet, open
space and ICT to support the delivery of the Council’s
priorities. It sets out clear aims and objectives including:
• Aligning asset management with the council’s key
strategic priorities
• Making efficient and effective use of the council’s
assets
• Reviewing and rationalising the asset portfolio to ensure
it is fit for purpose
• Ensuring investment in assets is prioritised and
managed through clear governance. 
2. The Corporate Asset Strategy adequately considers how
the organisation and the landscape in which council
services are being delivered is changing. For example, it
notes how the shift to more agile working patterns has
changed how buildings are being used and the
development of school campuses is cited as having
created opportunities for some community services to be
23

Page 24

1. Asset management planning | 7 
Judgements Evidence 
co-located. In addition, financial and climate pressures
have placed a renewed focus on sustainability including
asset decarbonisation, infrastructure requirements for
active travel and opportunities for renewable energy
generation.  
3. The Corporate Asset Strategy is underpinned by six
detailed asset management plans, each clearly linked to
service delivery. For example, the Property Asset
Management Plan explains how schools and education
facilities are assessed for condition, suitability and
utilisation and the Housing Asset Management Plan
clearly links the housing stock and quality to tenant
wellbeing, homelessness prevention,
energy efficiency and climate targets. The Corporate
Asset Strategy is aligned to financial planning through the
10-year Capital Programme which is updated annually. 
4. The Corporate Asset Strategy sets out a clear approach to
asset management, supported by defined governance
arrangements and roles and responsibilities for key
groups. The Capital Programme and Assets Group is
chaired by the Head of Finance and has representation
from senior officers across all services. It meets quarterly
and its remit includes strategic asset management,
investment prioritisation, business case
assessment, capital programme delivery as well as
developing and monitoring of performance across all
assets. Each asset-specific plan includes its own
governance arrangements. 
2. The council’s Corporate
Asset Strategy and Plans
align with its corporate
objectives, new ways of
working, the changing
needs of its population,
and clearly sets out how
net zero commitments will
be met. 
1. There is clear alignment between North Ayrshire
Council’s key priorities and its Corporate Asset Strategy
and Plans.  The overarching Asset Management Strategy
is reported to Cabinet annually to ensure alignment
between high level council-wide priorities and individual
asset management plans. This approach ensures
priorities are interlinked and Chief Officers are allocated
key responsibilities as part of this structure.
2. North Ayrshire’s Council Plan (2023-2028) sets out its four
key priorities: wellbeing; communities and local
democracy; climate change and sustainability. These
priorities underpin the council’s strategic aim of a ‘North
Ayrshire that is fair for all’. 
3. North Ayrshire Council’s four priority themes are clearly
reflected throughout its Corporate Asset Strategy and
individual asset management plans. For example:
24

Page 25

1. Asset management planning | 8 
Judgements Evidence 
• The theme of wellbeing is reflected under the council’s
equality and socio-economic duties such as ensuring
the availability of quality public open spaces for physical
activity and health and wellbeing benefits. Wellbeing is
also reflected within the vision for the
Housing Asset Management Plan, whereby the council
envisages that ‘everyone has a safe, affordable, and
warm home that meets their needs and supports their
wellbeing.’  Corresponding wellbeing aims within the
Housing Asset Management Plan include using assets
to support wellbeing in local communities, delivering
homes that meet the needs of residents and ensuring
spaces are well-maintained, inclusive and accessible
for all. 
• Communities and local democracy is a defined priority
within the Housing Asset Management Plan, whereby
corresponding aims include developing strong
relationships with communities and partners based on
trust and shared aspirations using their experiences to
inform service provision, actively supporting the aims of
the Community Planning Partnership and the North
Ayrshire Partnership Plan and strengthening
collaboration with third sector and voluntary
organisations.
• Climate change is a priority within the Roads Asset
Management Plan, with corresponding actions such as 
improvising resilience and reducing carbon by
supporting supply chains where materials and goods
are sources locally, developing and promoting active
travel infrastructure, transitioning to low and zero
carbon travel as well as costal adaptation work and
flood risk management to address the most serious
impacts of climate change.  
• Sustainability is reflected throughout the Property Asset
Management Plan, for instance, there is a dedicated
sustainability assets section detailing the council’s work
to develop two solar farms, receiving an income for the
renewable electricity generated (£0.5 million return on
investment per year).  
4. The Corporate Asset Management Strategy (2025-2030) is
explicitly set over a five-year period from 2025 to 2030,
providing a medium-term framework for asset planning
and investment.  Asset planning is also aligned to the 10-
year Capital Programme which is updated annually and
refreshed every three years, providing a basis for longer
term planning and investment decisions.  
25

Page 26

1. Asset management planning | 9 
Judgements Evidence 
5. The council has clearly considered how its assets can be
optimised to reflect new ways of working, the changing
needs of its population and demands for services. For
example:
• The ICT Asset Management Plan (2025-2028)
discusses how agile working has become a permanent
feature of the council’s work culture since the Covid-19
pandemic and that many staff now operate in a hybrid
or fully remote capacity. This change has been
supported by office rationalisation, the closing of
underutilised buildings and the co-location of teams. In
addition, it notes that IT services have also enhanced
the council’s remote capabilities, including upgrading
office Wi-Fi infrastructure to ensure fast and reliable
connectivity for laptops and mobiles. 
• The Housing Asset Management Plan demonstrates
strong consideration of demographic change
addressing the needs of an ageing population through
sheltered housing refurbishment and adaptations as
well as planning for energy efficiency measures and net
zero standards that affect future housing demands and
requirements. For example, under Energy Efficiency
Standard for Social Housing it states that the Council’s
new build programme is a key area in delivering energy
efficiency measures and that the new homes being
constructed utilise the latest energy efficient
technology including increased levels of thermal
insulation, air tightness, air source heat pumps and
solar panels. 
6. There is evidence of demand forecasting across a range of
individual asset management plans, including property,
fleet, ICT and open space. Forecasting is influenced by a
range of factors including climate change adaptation
requirements, increased community use of buildings and
financial pressures. In addition, the Housing Asset
Management Plan includes a dedicated section on future
demand which states that demand for council housing
continues to be high, however it is recognised there are
areas of ‘unpopular housing stock’ and ongoing work is
focussed on understanding and addressing the factors
that influence demand for specific housing types, ensuring
that options available align with council priorities, including
sustainability, accessibility and community regeneration. 
7. The council clearly sets out how it intends to meet its net
zero commitments. For example, the Corporate Asset
Strategy states ‘The Council’s asset management plans
26

Page 27

1. Asset management planning | 10 
Judgements Evidence 
recognise the opportunities to tackle climate change
through efficient asset management, for example:
investment in energy conservation measures in our
houses and non-domestic buildings; using our assets to
generate renewable energy; continued decarbonisation of
our vehicle fleet; construction of new electric vehicle
charging points; and journey reduction through the use of
technology.’ 
8. Detail about key programmes of work, actions to meet net
zero commitments, as well as performance indicators
detailing how progress will be monitored are set out within
individual asset management plans. For example, the
Fleet Asset Management Plan’s key programmes of work
include fleet rationalisation, the use of
telematics (described as an essential component of
implementing zero emission vehicles), switching to low
carbon alternatives, charging infrastructure in the
workplace to support the expanding electric fleet, as well
as plans for the procurement of zero emissions Heavy
Duty Vehicles.  The Plan incorporates two performance
indicators to measure and monitor progress against its net
zero commitments, including: 
• Fuel use (litres) 3-year trend data from 2022/23,
2023/24 and 2024/25 shows a steady decline each
year, with a target of 1,400,000 litres for 2025/26
continuing this trend.
• CO2 emissions (tonnes) 3-year trend data from
2202/23, 2023/24 and 2024/25 also shows a steady
decline each year, however the 2025/26 target of 3,680
tonnes represents increasing emissions despite lower
fuel use overall.  
9. There is also a Fleet Asset Management action plan
which incorporates actions and outcomes to support net
zero commitments, including the reduction of fleet
produced emissions and demand for vehicles and travel.
3. The council has clear
asset management plans
that align with the
Corporate Asset Strategy
and Capital Programme
1. The council has clear service-level asset management
plans that include sufficient detail
on actions, timescales and costs. We reviewed two asset
management plans and found that these were well-
aligned with the Corporate Asset Strategy and capital
programme.   
Roads Asset Management Plan
2. The Roads Asset Management Plan includes an action
plan that sets out specific actions, a dedicated staff
member assigned to each action and high-level
27

Page 28

1. Asset management planning | 11 
Judgements Evidence 
timescales. There are multiple examples of specific
actions, including preparing a progress report on the
Ayrshire local flood risk management plan. The dedicated
staff member for this specific action is the Team Leader
for flooding, and the timescale is noted as March 2026.
The Roads Asset Management Plan also includes a
dedicated section on finance, which sets out historical and
planned investment, including predictions for future
investment to 2030/31. For example, it notes £3.8 million
of planned capital investment for carriageways annually
until 2030/31. 
3. Planned capital investment for Roads, structure and
lighting is set out within the Council’s Capital Investment
Strategy (2024-2034). It notes planned investment of
£112.8 million until 2033/34. Key objectives for roads
include improvements to roads and the street lighting
network, flood prevention work and bridges infrastructure
improvement. This demonstrates clear alignment in terms
of key priorities within the Roads Asset Management Plan.
There is also alignment with the broader ambitions in the
overarching Corporate Asset Strategy. For example, the
Corporate Asset Strategy aspires to reduce pressure on
budgets and similarly one of the actions in the roads
action plan commits to assessing the cost effectiveness of
footway replacement options.
Property Asset Management Plan
4. The Property Asset Management Plan includes an action
plan with specific actions, desired outcomes, high-
level timescales and a dedicated staff member assigned
to each action.  There are multiple examples of specific
actions, including reviewing governance arrangements to
ensure that strategic asset management reflects best
practice. The desired outcome for this action is described
as the council having a property estate which is being
managed appropriately and in accordance with guidance.
There is a dedicated member of staff for this specific
action, and the timescale is marked as complete. The
Property Asset Management Plan also includes a
dedicated section on finance, setting out high level costs
such as total revenue running costs for the Council’s
operational estate, property running costs for 2024/25 and
a summary of the current Capital Receipts Schedule. 
5. Planned capital investment for property is set out within the
Council’s Capital Investment Strategy (2024-2034). It
notes planned investment of £18.6 million until 2033 to
2034. Key objectives for property include ensuring that
28

Page 29

1. Asset management planning | 12 
Judgements Evidence 
council properties meet all legislative requirements and
are sustainable, energy efficient and maintained to a high
standard, as well as ensuring the physical environment
can support both mobile and flexible work programmes. It
also notes that further rationalisation and remodelling will
progress through the Estates Strategy on a place-by-
place basis. There is clear alignment in terms of high-level
themes with the Property Action Plan, particularly in
relation to efficiency, compliance and sustainability. This
includes implementing new systems to improve workload
efficiency, ensuring compliance with new legislative
requirements, and improving energy efficiency in existing
properties by replacing appliances with more
environmentally friendly heating systems. The action plan
also focuses on rationalisation with plans to undertake
rationalisation reviews to consolidate buildings and create
savings within council property.  There is also clear
alignment with the broader ambitions in the overarching
Corporate Asset Strategy, which aims to create
efficiencies, deliver sustainable change, reduce pressure
on budgets and ensure clear governance and decision-
making is in place for council assets. These themes are
reflected throughout the Property Asset Management
action plan.
4. North Ayrshire Council
demonstrates a
commitment to assessing
affordability whilst
navigating substantial
financial pressures that are
projected to widen budget
gaps in the coming years 
1. North Ayrshire Council, alongside other local authorities, is
navigating substantial fiscal pressures that are projected
to widen budget gaps in the coming years.  The latest
Medium Term Financial Outlook to 2027/28 has identified
a structural funding gap of £46.7 million. Cost risks have
been identified across a number of capital projects and
long-term borrowing has increased in support of the
council’s capital programme. As a result, the council
updated their Strategic Risk Register in March 2024 to
include a new strategic risk associated with the Council's
property estate against a backdrop of financial challenges.
The capital programme is expected to deliver a total
programme of £406.459 million to 2033/34. Total available
funding has been projected at £189.987 million. The
balance of funding required to deliver the capital
programme will be met through prudential borrowing and
is anticipated at £216.472 million. A greater reliance on
borrowing to fund capital programmes increases the
pressures on revenue budgets over the longer term. The
council understands the future revenue implications of
servicing this debt.
29

Page 30

1. Asset management planning | 13 
Judgements Evidence 
2. The council has sufficiently considered the affordability of
its capital programme and asset management plans.
Maintaining capital plans that are ‘affordable, prudent and
sustainable’ is a key consideration of North Ayrshire
Council’s Capital Investment Programme (2026/27 to
2033/34), and the Treasury Management and Investment
Strategy shows that the council is using formal prudential
indicators to monitor affordability over time.
3. There is also evidence that the council is prioritising the
investment hierarchy in its decision-making approach. For
example: 
• The Capital Investment Programme sets out details on
the long-term maintenance investments of assets,
including £79.5 million on roads, structures and
lighting until 2033/34 including roads resurfacing,
upgrading bridges, street lighting and flood protection,
as well as £21.6 million until 2033/34 on fleet
procurement and maintenance to ensure sustainability
and decarbonisation of the vehicle fleet. 
• All new projects undergo an options appraisal whereby
any new investment is considered within the wider
context of outcomes, affordability and balancing the
need to invest to maintain current assets against the
ambitions of acquiring new ones. 
• The Capital Investment Programme also notes that
governance frameworks ensure all capital investment
must demonstrate that it is aligned to the Council’s
strategic priorities, with particular focus and priority
given to capital investment opportunities that meet
multiple strategic priorities.
• In the 2024/25 Annual Audit Report, we reported that
North Ayrshire Council had reviewed the phasing of
expenditure within the approved Capital Investment
Programme (2024/25 - 2033/34) to reflect historic
expenditure patterns and organisational capacity. This
resulted in the rephasing of approximately 19 per cent
of the planned expenditure in both 2024/2025 and
2025/26 for delivery in later years, without impacting on
the overall value of investment within the programme.
4.  The council assesses a range of different funding
sources to support its capital programme. For example,
the Capital Investment Programme (2026/27 - 2033/34)
includes a detailed breakdown of all funding sources. Key
funding sources to support the delivery of £323.9 million
capital investment to 2033/34 include: prudential
30

Page 31

1. Asset management planning | 14 
Judgements Evidence 
borrowing, specific capital grants, general capital grant,
reserve funds, capital receipts and other grants and
contributions. 
5. The council’s consideration of whole life costs of its assets
is evident. There are a range of examples showing
planned lifecycle investment, such as £9.1 million of
planned investment for property lifecycle to ensure
legislative compliance, sustainability and that council
buildings are fit for purpose. 
6. The Capital Investment Programme (2026/27 - 2033/34)
analyses risks related to inflation, cost volatility and
interest rates. For example, it states that the programme
refresh takes account of the ongoing impact of
construction industry inflation, cost volatility and supply
chain issues across the overall capital investment
programme. In addition, it notes that the council has
created a £15 million flexibility budget (over a three-year
period) to manage cost risks associated with inflation and
supply chain issues. 
7. Business case criteria include affordability tests to assess
whether capital and borrowing plans are affordable. Key
indicators include capital expenditure and financing; the
capital financing requirement and total borrowing needed
over time; borrowing limits (operational boundary and
authorised limit) to ensure borrowing stays within safe and
affordable limits, as well as the ratio of financing costs to
net revenue stream. In addition, the Loans Fund Policy
ensures that borrowing is repaid in a way which is
affordable. According to the Capital Investment Strategy
(2024-2034) this involves ensuring that unfinanced capital
expenditure is financed over the expected life of the asset
and that each year's repayment amount is in proportion to
the period and pattern of benefits. There is an emphasis
on ‘prudential borrowing’ to ensure that investment in
assets to deliver on the council’s strategic priorities is
sustainable in the long-term.
8. The Capital Investment Strategy (2024-2034) and Treasury
Management and Investment Strategy (2026/27) show
that the council considers its debt to expenditure ratio and
is keeping borrowing within prudent and sustainable
levels. For example, the council uses formal prudential
indicators – in particular the ratio of financing costs to net
revenue stream - as a key measure of affordability. The
Council’s Capital Financing Requirement is monitored
31

Page 32

1. Asset management planning | 15 
Judgements Evidence 
through the treasury management strategy and is
projected to:
• Increase to £821.544 million by 2030/31
• Reduce annually thereafter to 2033/34.
9. There is clear monitoring of debt in relation to financial
capacity. For example, the council consider if debt is
affordable relative to the revenue budget. The average
ratio of debt servicing costs to net revenue for general
services (over a three-year period) is 4.3 per cent for
General Services (below the Scottish average of 5.4 per
cent). For Housing Revenue Account this is 27.7 per cent,
higher than the Scottish average of 21.4 per cent but the
council explains this is linked to the scale of planned
investment in the Capital Investment Programme. 
5. The council has clear
plans in place to mitigate
significant building safety
risks it has identified
1. There is clear evidence that surveys and assessments are
being undertaken in relation to building safety risks, as
well as remedial actions being taken to mitigate identified
risks. For example:
• An update taken to the Executive Leadership Team and
Cabinet in November 2023 explains that surveys
carried out by Structural Engineers have identified the
presence of RAAC in two Council properties. As a
precaution both properties have since been closed and
contingency arrangements put in place to manage the
impact of the closures. 
• Evidence from the Council’s response to the Grenfell
tower fire in 2017 shows that the Council carried out an
assessment to identify affected buildings and assess
their construction and cladding systems. The review
confirmed that that none of the North Ayrshire Council’s
properties use the aluminium composite cladding
associated with the Grenfell Tower fire. However, the
assessment did identify a risk in relation to high rise
residential buildings, where sprinkler systems were not
installed because there was no statutory requirement at
the time the buildings were constructed.  The Council
has since taken action to address this by progressing
the installation of sprinkler systems, which was
identified as the main mitigation measure.
• North Ayrshire Council’s formal return to the Scottish
Government for the High-Pressure Laminate (HPL)
cladding data collection exercise in January 2020
(introduced following the Grenfell Tower fire) shows that
12 schools in the local area are recorded as having
HPL cladding present. Fire Risk Assessments have
32

Page 33

1. Asset management planning | 16 
Judgements Evidence 
been carried out at all 12 of these locations since the
HPL cladding return.  The Council are currently
preparing to commence a programme of new FRAs
across the estate.
2.  Risk prioritisation, monitoring and reporting arrangements
are clear at a strategic level. The council operates a three-
tier risk management structure to ensure risks have
appropriate oversight. Operational risks are identified and
monitored at individual service level and corporate risks
are considered through the Risk Management Group as
well as being reported to the Executive Leadership Team.
The process also considers risk escalation or deescalation
to or from the Strategic Risk Register which is reported to
the Cabinet and Audit and Scrutiny Committee.
3. The council has provided an example of its risk
management approach in relation to the presence of
RAAC at Mid-Dykes depot. Risks are assessed through a
risk-based review of affected properties, supported by
structural engineer inspections. Reporting arrangements
are clear and involve notifying the Head of Sustainability,
Transport and Corporate Property, regular updates
through Place and Corporate Health and Safety Meetings,
as well as external updates to the Scottish Government
and Audit Scotland. Monitoring arrangements are clearly
defined and require formal annual inspections, with
responsibility assigned to a Team Manager within Assets
and Property Rationalisation. 
33

Page 34

2. Governance and performance | 17 
2. Governance and performance 
5.  It is essential that the council has effective governance arrangements in
place to enable transparency, oversight and scrutiny of progress with
implementing its capital programme and asset management strategy. This
enables better-informed decision making and corrective action where
needed. 
Findings and evidence relating to the council’s governance arrangements and
performance 
Judgements Evidence
6. North Ayrshire Council
has established
appropriate leadership
arrangements, and
reporting and monitoring
arrangements enable good
scrutiny and oversight of
progress towards
implementing the capital
programme and asset
management plans  
1. North Ayrshire Council has established appropriate
leadership arrangements for its capital programme and
asset management plans. The governance framework is
delivered through a range of officer and member
represented groups and committees, each with clearly
defined roles and responsibilities. For example, Cabinet
approves the corporate framework and the council
approves the medium and longer-term investment
programme. The Executive Leadership Team, the
Capital Programme and Assets Group (CPAG) and
Directorate & Service Project Boards ensure officer co-
ordination of corporate asset management and support
the Council and Cabinet at chief officer and senior
management levels. 
2. CPAG is chaired by the Head of Finance and includes
representation from senior officers across all Services. It
meets on a quarterly basis with the remit of: 
• ensuring a strategic and corporate approach overview
of asset management to ensure the Council’s
resources are deployed effectively 
• developing and delivering the corporate asset
management plans 
• developing and delivering the Council’s capital
investment programme, minimising slippage on the
delivery of the programme
• developing clear criteria for investment of Council
resources on asset matters and assessing all
investment business cases 
34

Page 35

2. Governance and performance | 18 
Judgements Evidence
• developing and monitoring performance across all
asset classes 
• developing a capital receipts strategy 
• developing and implementing best practice in all asset
matters. 
3. Chief Officers and Senior Managers are responsible for: 
• working together to ensure a corporate approach to
asset management is in place and delivering the
Council’s asset management plans and associated
investment programme 
• contributing to the development and delivery of asset
strategies and plans; and 
• ensuring consultation on asset management is
undertaken with all relevant stakeholders. 
4. Directorate and Service Project Boards are responsible
for: 
• Ensuring capital and asset plans are being
implemented efficiently and effectively 
• Taking corrective action to ensure delivery
plans remain with agreed parameters of time and
budget 
• Escalating relevant issues to the Executive Leadership
Team and and/or CPAG. 
5. Reporting and monitoring arrangements are sufficiently
regular and provide senior leadership with clear
information about progress towards implementing the
capital programme and asset management plans. For
example, our review of CPAG meeting papers shows
that the group meets on a quarterly basis and meetings
following a standard structure, with papers including
capital financial reports, business cases and draft
minutes and action logs from service project boards.
6. During fieldwork, officers also highlighted that action
plans for individual service level asset management
plans are being monitored regularly through updates to
Heads of Service and Senior Managers, as well as
Council Plan quarterly assessments of performance
which are reported through the Executive Leadership
Team and fed into Cabinet and Audit and Scrutiny
Committee.
7.  Cabinet considers regular capital programme
performance reports. These cover performance relating
35

Page 36

2. Governance and performance | 19 
Judgements Evidence
to the General Services capital programme and Housing
Revenue Account. Reports capture: 
• Movement in the General Services capital budget in-
year 
• In-year changes to funding and alterations to the
phasing of projects 
• Projected capital expenditure to 31 March 2026. 
8.  Reports also include an appendix covering project
expenditure by service area, broken down by the type of
project. This outlines total project budget, total
expenditure to date, total project forecast expenditure
and projected over/underspend. It also covers budget
and expenditure for the current year. Detailed updates
are also given for each project in the General Services
capital programme and HRA. This covers budget and
expenditure along with completion dates and current
project status. A RAG rating is also given for both
financial and ‘physical’ delivery status. Of the three
reports reviewed, two of these also included an
assessment of estimated performance against the
Prudential Indicators set out in the Treasury
Management and Investment Strategy.
7. North Ayrshire Council
is progressing well with the
delivery of its capital
programme and asset
management plans
North Ayrshire Council’s
performance against the
relevant LGBF asset
management indicators has
varied over time. The most
recent data shows that the
council is currently
performing above the
national average and is
ranked within the top
quartile nationally for these
indicators 
1. The latest capital programme performance report shows
that the council is progressing well with the delivery of its
General Services capital programme. For example, in
November 2025, of 164 projects, 59 were complete, 100
were on target (green), 1 was amber and 4 were
classified as ‘holding code’ or ‘on hold’. These
classifications relate to both financial and physical
delivery status of the projects. For Housing Revenue
Account (HRA) delivery, status is not recorded for some
projects, but where delivery status is recorded the
majority of projects were on track. For example, 33 were
on target (green) for financial delivery and 30 were on
target (green) for physical delivery. 1 project was
classified as being slightly off target (Amber) for financial
delivery and 1 amber for physical delivery, with 2
categorised as significantly off target (Red) for financial
delivery and 3 significantly off target (Red) for physical
delivery. 11 were complete for financial delivery and 13
complete for physical delivery.
2. Internal performance indicators for asset management
referenced in the Best Value Thematic Audit 2025/26
and the Council Plan Year End Progress Reporting
(September 2025) show that the council reports
36

Page 37

2. Governance and performance | 20 
Judgements Evidence
performance against 31 internal asset management
indicators. Not all indicators have data or RAG statuses
reported, but of the 21 where RAG statuses are
assigned:
• 13 indicators were reported as green
• 5 indicators were reported as amber
• 3 indicators were reported as red.
3. Examples of indicators with a green status include: the
proportion of operational buildings that are suitable for
their current use; percentage of council dwellings that
are energy efficient (LGBF) and the number of trees
planted under the North Ayrshire 2030 Tree Planting
Strategy. Examples of amber indicators include the
percentage of council dwellings that meet the Scottish
Housing Quality Standard (LGBF); overall carbon
emissions (tonnes) (non-domestic council estate) and
the number of council assets under community
management (cumulative). Examples of red indicators
include: the total installed capacity of low-carbon heat
and electricity generation across the council estate;
percentage of total household waste recycled and the
number of new build housing units reaching completion
(non-cumulative).
4. Specific asset management actions are reported regularly
within the Council’s corporate performance management
system.  Screenshots provided by the council show
examples of actions and performance indicators for the
Fleet, Roads and Open Space Asset Management
Plans. Details such as start date, status, progress and
next update date are being logged and monitored for
actions within the performance management system. We
can also see that targets, expected outcomes, results
and trend of performance indicators are also reported
within the Performance Management System.  
5. North Ayrshire Council has demonstrated mixed trend
performance over time against the relevant Local
Government Benchmarking Framework (LGBF) asset
management indicators.  The most recent data shows
that the council is currently performing above the
national average and is ranked within the top quartile
nationally for these indicators. For example:
• In 2024/25, 95.2 per cent of the council’s operational
buildings were deemed suitable for their current use.
Performance against this indicator has shown a 6.6
percentage point improvement since 2013/14 - which
37

Page 38

2. Governance and performance | 21 
Judgements Evidence
is above the Family Group average of 90.5 per cent
and the national average of 85.74 per cent.
Performance has been consistently high with the
council ranked in the top quartile for the last three
years.  
• The council’s performance in relation to the
percentage of the internal floor area of operational
buildings in a satisfactory condition has shown a
decline of 4 percentage points however it has
consistently been above the Family Group (88.4 per
cent) and national (90.3 per cent) averages since
2013/14. The Council ranked seventh in 2024/25 - an
improvement from the previous year. 
• In 2024/25, 94 per cent of council dwellings met the
Scottish Quality Housing Standards. This represents a
small decline of 2.3 percentage points since 2013/14.
It followed the national trend but experienced a
steeper decline with the onset of the Covid-19
pandemic than other councils and is yet to fully
recover to pre-covid performance levels. The council
has displayed sharp improvement in the previous
three years and is above the Family Group average of
85.9 per cent and the National average of 82.9 per
cent. Performance improvement in the most recent
year was 17.1 per cent, above the national average of
5.1 per cent. The council is currently ranked third
nationally against this indicator. 
• Data for the proportion of council dwellings that are
energy efficient has not been collected since 2021/22.
Energy efficiency targets for social housing are
temporarily on hold pending the development of a new
standard that aligns with Scotland's net zero target.
Reported performance for North Ayrshire Council in
2021/22 was 97.67 per cent, following the national
improvement trend. The Council remains consistently
above the Family Group average of 91.8 per cent and
the national average of 87.6 per cent. It ranked fourth
nationally against this indicator.  
38

Page 39

2. Governance and performance | 22 
Exhibit 2
Trend in performance against Local Government Benchmarking Framework indicators
North Ayrshire Council has demonstrated mixed trend performance over time against the
relevant Local Government Benchmarking Framework (LGBF) asset management indicators.
The most recent data shows that the council is currently performing above the national average
and is ranked within the top quartile nationally for these indicators. 
Source: Audit Scotland using Local Government Benchmarking Framework 
39

Page 40

3. Partnership working and community engagement | 23 
3. Partnership working and
community engagement 
6.  It is essential that councils consider how they can collaborate across
services and with other public and third sector organisations to manage
assets. This has the potential to achieve savings, better align service
provision and create opportunities for joint working. Councils should also
have transparent and robust processes in place for supporting and
assessing community asset transfer requests and engaging with their
communities on asset management plans and priorities.
Findings and evidence relating to the council’s partnership working and
community engagement arrangements 
Judgements Evidence 
8. North Ayrshire Council
works collaboratively with
a range of partners to
optimise how assets are
used to provide services 
1. Partnership working is a key theme throughout North
Ayrshire Council’s Corporate Asset Strategy and Plans
(December 2025). The council has demonstrated that it
works collaboratively with a range of partners to optimise
how assets are used to provide services, as well as
considering new and collaborative ways of using its assets
through place-based approaches. For example: 
• North Ayrshire Council is working in partnership with the
Scottish and UK Governments, and neighbouring
councils to coordinate over £250 million of investment
through the Ayrshire Growth Deal. The deal aims to
strengthen local and national economies creating
around 7,000 new jobs and positioning Ayrshire as a
world class business region for space, energy, marine,
manufacturing and tourism industries. Confirmed
funding includes £103 million from each government, as
well as £45.5 million from the three Ayrshire Councils,
with delivery over a 10-year period and the potential to
attract around £300 million of private investment. 
• As part of the Ayrshire Growth Deal, there are a range
of assets being developed including the i3 Digital
Process Manufacturing Centre and Flexible Business
Space. This investment aims to deliver a Digital
Process Manufacturing Centre alongside approximately
8,830 square meters of flexible, energy efficient
40

Page 41

3. Partnership working and community engagement | 24 
Judgements Evidence 
manufacturing space, building on existing life sciences
activity. The development is intended to support
research and development, start-up activity, the growth
of life sciences businesses and other advanced
manufacturing opportunities. Delivery of the Digital
Process Manufacturing Centre is being taken forward in
partnership with the University of Strathclyde and the
Centre for Process Innovation. The Centre will provide
manufacturing businesses with access to digital and
data driven manufacturing expertise for developing new
technology. It will also act as a pilot for larger,
permanent facilities within the region. 
• Early projects at the Digital Process Manufacturing
Centre have demonstrated benefits such as
improvements in productivity, broad industry
participation, outreach and education for young people
and an anticipated £2 million boost to the local
economy. 
9. North Ayrshire Council
has a clear and transparent
approach to supporting
and assessing Community
Asset Transfer requests
and can demonstrate how it
has worked
with communities to inform
decision making in relation
to specific assets. 
1. North Ayrshire Council supports communities to take
ownership of assets through the Community Asset
Transfer (CAT) process. For example, there is a clear and
transparent process in place to engaging with
communities in asset management planning through its
Community Asset Transfer policy. The CAT policy is
publicly available on the council’s website and was
recently updated in June 2024. The policy also sets out
clear aims of CAT requests including benefits to the local
community, voluntary organisations and community
groups, as well as leverage to attract new funding and
opportunities for partnerships with access to resources out
with the council. There is a clear assessment process in
place whereby applicants must provide a sustainable
business proposal, demonstrate clear demand for
proposed activity, demonstrate capacity to manage the
asset, as well as showing they have good governance and
robust financial systems in place. The proposal must also
contribute to the achievement of the Council’s outcomes
and not duplicate activities already provided within the
local community. The process of making a formal
application for transfer is set out in a clear two stage
decision making process, stage one being the formal
application for transfer, followed by stage two the Cabinet
decision. The council will then support successful
applicants to develop viable proposals during the
implementation and handover stage, whereby a contract
will be drawn up between the council and applicant setting
41

Page 42

3. Partnership working and community engagement | 25 
Judgements Evidence 
out support provided by the council (eg, economic
development, finance etc) to enable the group to meet its
responsibilities.
2. The council has also provided recent examples of
Community Asset Transfer requests to show how the
policy is being applied in practice. These requests
demonstrate transparency against the CAT policy criteria
including community benefit, sustainability and the impact
on council services. The examples also provide clear
evidence that community engagement has influenced
decision making regarding the transfer of specific
assets. For example:
Community Asset Transfer: Brisbine Centre in Largs
• In February 2025, Cabinet approved plans for a
Community Asset Transfer of the Brisbine Centre in
Largs, responding to a community-led initiative and
application from Clyde Coast and Cumbraes Men’s
Shed to acquire the building from the council. The
rationale for the asset transfer is clear, with ownership
enabling the Men’s Shed to enhance the facility,
support the expansion of its membership and increase
opportunities for community engagement, as well as
generating wider local benefits such as maintenance
undertaken by local businesses, contributing to the local
economy and supporting the principles of Community
Wealth Building. 
• Community outcomes such as reduced isolation,
improved wellbeing, increased volunteering and local
economic benefits are explicitly cited as reasons for
approving the transfer and applying a 95 per cent
discount to the property valuation under powers to
dispose of assets below market value where community
benefit is demonstrated. The report states that this
reflects the condition of the facility, the organisation’s
investment to date, savings made against future upkeep
and the potential social return on investment, noting
that the group are in a position to fund the requested
amount of £3,700. These factors are translated into
formal Cabinet recommendations, with the report clearly
setting out how the Men’s Shed proposal supports the
council’s key priorities with alignment to wellbeing,
communities and local democracy, climate change and
Community Wealth Building priorities. 
Community Asset Transfer: Toilet block and land at
Ardrossan South Beach
42

Page 43

3. Partnership working and community engagement | 26 
Judgements Evidence 
• A January 2023 Cabinet report seeks approval for a 25-
year lease of the toilet block and adjacent land at
Ardrossan South Beach to Ardrossan Community
Development Trust (ACDT). There is a clear rationale
for the Community Asset Transfer which is to enable
community led regeneration of Ardrossan South Beach,
maximise social value, and support delivery of
accessible facilities, economic activity and community
wellbeing. In particular, the report states that the CAT
will enable ACDT to deliver an agreed programme of
regeneration work, supported by secured funding from
the National Lottery Communities Fund, Scottish
Government Regeneration Capital Grant Fund and
North Ayrshire Council. The Community Asset Transfer
will also provide a sustainable base for local community
activity, including modern beach visitor facilities, an
accessible play area, cafe space, beach huts for
community and social enterprise use as well as
improved public amenities. 
• The report shows that community engagement has
directly influenced decision making, informing the
proposed use of the asset and shaping the design and
delivery choices. Extensive community consultation was
carried out, including a two-day community workshop in
February 2020, community engagement days in August
and September 2021 attended by almost 200 people,
and a community survey of 438 local people in
September 2021. The survey results show strong public
support for the project, anticipated improvements in
wellbeing and accessibility as well as expected
economic and social benefits. A social return on
investment forecast, informed by stakeholder
consultation, concludes that every £1 invested would
create £5.68 of social value. These factors are
translated into Cabinet recommendations to inform their
decision about the transfer. The report also clearly sets
out how the proposals within the CAT support North
Ayrshire Council Plan priorities as well as the key pillars
of Community Wealth Building.  
43

Page 44

Best Value thematic work – Asset management
North Ayrshire Council
How well councils are managing assets to achieve their corporate
objectives and respond to challenges around financial sustainability
and climate change 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot 
AS.5.0
44

Page 45

PUBLIC INFORMATION
PUBLIC INFORMATION 
NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee 
Title:    2025/26 Elected Member Requests Report 
Purpose:  To inform the Audit and Scrutiny Committee of the Council's
performance relating to Elected Member requests handled in
Financial Year 2025/26. 
Recommendation:  That the Committee notes the report and the information
provided. 
1. Executive Summary 
1.1 This report details Elected Member requests information covering the period 1 April
2025 to 31 March 2026 (referred to in the report as 2025/26). 
2. Background 
2.1 This section contains information and commentary on Elected Member requests
handled by the Council during Financial Year 2025/26. 
Volume of Elected Member requests actioned during the year (including
MP/MSP) 
Volume of requests actioned during year 3,107 
Councillor requests can be handled by Services under two stages: 
Stage One – non-complex requests with a timescale to action of 5 working days
Stage Two – complex requests with a timescale to action of 20 working days 
Agenda Item 4
45

Page 46

PUBLIC INFORMATION
PUBLIC INFORMATION
2.2 The table below details all Councillor requests actioned during the year: 
2025/26
Total Actioned 2,101
Stage One requests actioned 2,096
Stage One requests actioned on time 1,764
% Stage One requests actioned on time 84%
Stage Two requests actioned 5
Stage Two requests actioned on time 5
% Stage Two requests actioned on time 100%
Total % of requests actioned on time 84% 
2.3 The table below shows a comparison of the volume of Councillor requests received
and actioned over the last three years: 
Councillor Requests 2023/24  2024/25    2025/26 
Total Actioned  2,307 2,287  2,101
Stage One requests actioned 2,305  2,284  2,096
Stage One requests actioned on time 2,003  2,010  1,764
% Stage One requests actioned on time 87%  88%  84%
Stage Two requests actioned 2  3  5
Stage Two requests actioned on time 2  3  5
% Stage Two requests actioned on time 100%  100%  100%
Total % of requests actioned on time 87% 88%  84% 
46

Page 47

PUBLIC INFORMATION
PUBLIC INFORMATION
2.4 Volume of requests per Directorate 
2.4.1 Councillor Stage One requests (5 working day timescale to action) 
Directorate Department
No. of
requests
actioned
No.
actioned
on time
%
actioned
on time
Average no. of
days to resolve
Stage Ones
Target
(days)
Corporate
Services
Chief Executive Service 1 1 100% 4 5
Committee Services 2 2 100% 2 5
Customer Services 24 17 71% 6.8 5
Finance 4 4 100% 1 5
Legal Services 9 8 89% 3.1 5
Communities &
Housing
Community Facilities 4 4 100% 3.2 5
Community Learning & Dev. 7 5 71% 5.6 5
Sports & Activity 11 8 73% 5.5 5 
Building Services 79 67 85% 3.5 5
Housing 417 376 90% 3.9 5
Planning 24 22 92% 2.1 5
Protective Services 28 24 86% 3.3 5
Education Education 51 50 98% 2.3 5
Facilities Management 10 7 70% 4.3 5
Place
Roads 543 500 92% 2.9 5
Streetscene 323 263 81% 3.5 5
Waste 224 202 90% 2.8 5 
Regeneration 15 10 67% 6 5 
Energy/Sustainability 2 2 100% 3 5
Property Mgmt & Investment 145 119 82% 4.2 5
Transport 2 2 100% 2 5
Health & Social
Care Partnership
Children, Families & Justice 6 3 50% 11.8 5
Finance & Transformation 3 3 100% 4 5
Health & Community Care 135 51 38% 8.8 5
Mental Health 19 9 47% 8.4 5
Other (Money Matters etc) 8 5 63% 4.4 5  
2,096 1,764 84% 3.8 5 
2.4.2 Councillor Stage Two requests (20 working day timescale to action) 
Directorate Department
No. of
requests
actioned
No.
actioned
on time
%
actioned
on time
Average no. of
days to resolve
Stage Ones
Target
(days)
Communities &
Housing
Building Services 2 2 100% 3 20
Planning 1 1 100% 7 20 
Community Facilities 1 1 100% 15 20 
Property Mgmt & Investment 1 1 100% 3 20  
5 5 100% 6.2 20
47

Page 48

PUBLIC INFORMATION
PUBLIC INFORMATION
2.5 MP/MSP requests 
2.5.1 MP and MSP requests have a set timescale of 10 working days to action and the table
below details the requests actioned during the period: 
2025/26
Requests actioned 1,006
Requests actioned on time 798
% of requests actioned on time 79% 
2.6 Elected Member requests analysis 
2.6.1 There was an 8% decrease in Councillor requests compared to the previous year. 
2.6.2 Whilst there was a 5% decrease in MP and MSP requests being closed on time, there
was an uplift of 41% in requests received during the year. 
2.6.3 Elected Member requests that did not meet timescale was due to multiple factors,
including: 
• administrative errors
• employee/officer availability for reviewing/approving responses prior to issue
• reduced resources, causing delays investigating requests
• further information required to respond to requests (including from third parties)
• operational pressures
• in July 2025 the Council replaced EMPro (previously Lagan) with a new CRM
system.  During Implementation there were some preliminary issues that caused some
delays in requests being actioned. 
2.7 Recording Councillor requests 
2.7.1 The table below shows how Councillor requests were logged throughout the year: 
Volume % 
Volume of Councillor requests recorded  2,101 
Volume logged by Councillors  1,116  53%
Volume logged via other channels (Member Services, the
Services directly, the Contact Centre etc.)  985  47% 
2.7.2 Of the 2,101 requests logged by Councillors during the period, 16 Councillors used
their NAC online Member accounts to log requests themselves. 
48

Page 49

PUBLIC INFORMATION
PUBLIC INFORMATION
2.8 Follow up actions for Councillor requests 
2.8.1 At a previous Audit and Scrutiny Committee it was noted that that some Councillor
requests that required follow up actions were being closed with no further updates being
provided, causing difficulties for Councillors relaying closure information to constituents. 
2.8.2 To address this, additional questions were added to the Elected Member request form
(from 1 October 2024) allowing services to record if a request had outstanding/follow up
actions, what these were and when they would be completed by. 
2.8.3 The number of Councillor requests in 2025/26 that had follow up actions was 55. 17 of
these were scheduled to be completed in the 2026/27 financial year and the remaining
38 were all completed in the 2025/26 financial year. 
3. Proposals 
3.1 It is proposed the Committee approves the report and recognises the Council’s
performance in handling Elected Member requests in relation to Section 2 above. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 None. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None.
49

Page 50

PUBLIC INFORMATION
PUBLIC INFORMATION 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 None. 
Aileen Craig
Head of Service for Democratic Services 
For further information please contact Darren Miller, Complaint Manager, on (01294)
322988. 
Background Papers
None
50

Page 51

NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee 
Title:    2025/26 Complaint Report 
Purpose:  To inform the Audit and Scrutiny Committee of the Council's
complaint performance and volumes and trends of complaints
received in Financial Year 2025/26. 
Recommendation:  That the Committee notes the report and the information
provided. 
1. Executive Summary 
1.1 This report details complaint information relating to North Ayrshire Council during
Financial Year 2025/26, covering the period 1 April 2025 to 31 March 2026. 
1.2 To allow comparisons to be made the report also details some complaint data relating
to previous years. 
1.3 Performance is measured through several Scottish Public Services Ombudsman
(SPSO) performance indicators, some of which have national targets. 
2. Background 
2.1 This section contains statistical information and commentary on key complaint
performance indicators.  More information relating to the indicators can be found in the
attached report. 
2.2 Volume of complaints received 
Year Volume of complaints
2022/23 2,576
2023/24 1,948
2024/25 2,039
2025/26 2,066 
2.2.1 A slight increase in complaints received when compared to 2024/25 but a sizeable
20% drop when compared with 2022. 
Agenda Item 5
51

Page 52

2.3  Complaints closed within timescale in 2025/26 
Stage % closed on
time
Target
Stage One  93% 80% and above
Stage Two 92% 85% and above 
2.3.1  The volume closed on time includes extended complaints that met their new due dates. 
2.3.2  Further details of complaints not closed on time are contained in the attached report. 
2.3.3 For comparison purposes, the table below shows the percentage of complaints closed
on time at both stages over the last three years: 
Year Stage One %
closed on time
Stage Two %
closed on time
2023/24  87% 88%
2024/25 92% 93%
2025/26 93% 92% 
2.4  Complaint outcomes for closed complaints in 2025/26 
Stage One
Outcome 
% closed as Resolved* 39%
% closed as Upheld 35%
% closed as Partially Upheld 10%
% closed as Not Upheld 16% 
Stage Two
Outcome 
% closed as Resolved* 9%
% closed as Upheld 11%
% closed as Partially Upheld 36%
% closed as Not Upheld 44%               
2.4.1 *Resolved complaints are where the Council has taken action to address a problem or
issue without deciding whether there were any failings (this would happen where we
agree a solution with the complainant at the outset without needing to investigate the
complaint). 
2.4.2 Complaint outcome analysis can be found in the attached report. 
2.5  Average time in working days for a full response at each Stage 
Stage One Average number of
working days to close
Target
2023/24 3.8 5 workings days or less
2024/25 3.3 5 workings days or less
2025/26 2.9 5 workings days or less 
52

Page 53

Stage Two Average number of
days to close
Target
2023/24 16.8 20 working days or less
2024/25 15.5 20 working days or less
2025/26 16.4 20 working days or less 
2.5.1 The average number of days to close Stage One and Stage Two complaints is better
than the national targets. 
2.6  Changes or Improvements made as a result of complaints 
2.6.1 Services cannot always implement improvements because of complaints due to
several factors, including the feasibility of making changes and resource/budget
considerations. That said, improvements were made in some Services and a selection
are noted in the attached report. 
2.7   Compliments 
2.7.1 The Council received and recorded many compliments during the year. Some praised
specific individuals or teams, some related to more than one Service and some were
raised by employees complimenting other employees. A selection can be found in the
attached report. 
3. Proposals 
3.1 It is proposed the Committee notes the report and recognises the Council’s complaint
handling performance in relation to Section 2 above. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
53

Page 54

Key Priorities 
4.6 The Two Stage Complaint Handling Procedure supports the Council's key priority of
delivering more effective and efficient service provision. It demonstrates commitment
by identifying trends and focussing on service improvements whenever possible for
North Ayrshire residents, customers and visitors. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 If a young person under the age of 18 makes a complaint, or an adult makes a complaint
on behalf of a young person or about an issue that affects them, we will use an
enhanced child-friendly complaints process. This process ensures the young person's
views are heard and considered and follows the SPSO Child Friendly Complaints
Handling Principles and Child Friendly Complaints Handling Process Guidance. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 None. 
Aileen Craig
Head of Service for Democratic Services 
For further information please contact Darren Miller, Complaint Manager, on (01294)
322988. 
Background Papers
North Ayrshire Council 2025/26 Complaint Report 
54

Page 55

1 
PUBLIC INFORMATION
North Ayrshire Council 
Annual Complaint Report 
2025 to 2026 
55

Page 56

2 
PUBLIC INFORMATION
Introduction         3 
1 Volume of complaints closed      4 
2  Volume of complaints closed on time  at both Stages   6 
3 Volume of complaints not closed on time per Directorate     6 
4 Key complaint topics       9 
5 Average time in working days for a full response   10 
6  Extended complaints       11 
7 Complaint Outcomes                                                                    12 
8  Improvements made from complaints                         14 
9 Compliments        15 
10  SPSO complaint referrals       16 
11 Glossary         18
56

Page 57

3 
PUBLIC INFORMATION
Introduction
North Ayrshire Council always seeks to deliver the best services possible to its tenants,
residents and customers but it is recognised that dissatisfaction will sometimes occur. When
it does, we want to know what went wrong, why it went wrong and what we can do to make
things right.
The Council recognises that valuable lessons can be learned from complaints which are
defined as being expressions of dissatisfaction from members of the public about actions, or
lack of actions, or about the standard of service provided by or on behalf of the Council.
The Council’s complaint handling procedure (CHP) has two stages for handling complaints
from the public.
Stage One complaints (also known as Frontline Resolution) are straightforward, non-complex
complaints the Council can resolve at the initial point of contact or as close to the point of
service delivery as possible. The Council has up to 5 working days to resolve these.
Stage Two complaints (also known as Investigations) are complaints the Council is typically
unable to resolve at Stage One and needs more time to carry out further investigation. This
may be because the nature of the complaint is complex, serious or high risk. The Council has
up to 20 working days to resolve these.
This report details the Council’s complaint handling performance covering financial year
2025 to 2026 (1 April 2025 to 31 March 2026). Performance is measured via several Scottish
Public Services Ombudsman indicators (some of which have national targets) and complaint
data relating to previous years has been included in certain sections to allow comparisons to
be made. 
Reporting complaints is a statutory requirement and is monitored by Audit Scotland.
This report will meet accessibility requirements when published.  
57

Page 58

4 
PUBLIC INFORMATION
1 Volume of complaints closed
The Council received 2,066 complaints during the year and closed 2,067. 
The table below provides a breakdown of the closed complaints per Directorate:
Directorate Volume
Communities & Housing 417
Corporate Services 155
Education 216
Health & Social Care 312
Place 959
Multi-Service 8
The following tables highlight complaint volumes per Directorate under each Stage:
Corporate Services
Team Stage One Stage Two
Chief Executive Service 1 0
Customer Services 124 12
Finance 7 1
IT 2 0
Legal Services 6 2
Total 140 15
Communities & Housing
Team Stage One Stage Two
Building Services 190 17
Community Facilities 9 0
Community Learning and Development 3 0
Housing 131 31
Information & Culture 2 0
Planning 4 5
Protective Services 17 5
Sports and Activity 3 0
Total 359 58
Education
Team Stage One Stage Two
Education (HQ) 9 12
Education (Schools) 110 70
Facilities Management 15 0
Total 134 82
58

Page 59

5 
PUBLIC INFORMATION
Health & Social Care
Team Stage One Stage Two
Children, Families & Justice 39 36
Finance & Transformation 17 2
Health & Community Care 138 45
Mental Health 12 13
Support Services 8 2
Total 214 98
Place
Team Stage One Stage Two
Property Management & Investments 95 16
Regeneration 2 0
Roads 87 13
Streetscene 55 2
Sustainability 3 0
Transport 5 0
Waste Services 680 1
Total 927 32
Multi-Service
Team Stage One Stage Two
Complaints involving more than one Service 2 6
Total 2 6
Although there is no target for the volume of complaints handled under each Stage, the
Council seeks to maximise closure at Stage One wherever possible and 86% were handled at
this stage during the period.
Some Services handled all their complaints at Stage One.
Some Services that received high complaint volumes handled few of them at Stage Two,
notably Customer Services, Building Services, Property Management & Investments, Roads,
Streetscene and Waste Services. This will be due to the straightforward nature of the
complaints received.
Regarding Waste Services complaints, the Waste Operations team has an improvement plan
in place and monitors and reviews all complaints received to identify issues and take
appropriate action with them. In the last three years, complaints in respect of Waste
Operations have reduced from 1,371 in 2022/23 to 680 in 2025/26. This equates to a 50%
reduction in complaints over the three-year period. 
Year on Year comparison
The table below shows a comparison of the volume of complaints received over the last four
years:
59

Page 60

6 
PUBLIC INFORMATION
Year Volume of complaints
2022/23 2,576
2023/24 1,948
2024/25 2,039
2025/26 2,066
Whilst there has been a slight increase in complaints received when comparing 2025 with
2024, it is still a 20% drop when comparing 2024 with 2022. The sustained lower volume
could be partly attributable to the complaint page on the Council’s website being enhanced
in 2023, which now includes more information on what the Council does not consider a
complaint and offers appropriate routes to raise such matters.
2 Volume of complaints closed on time at both Stages
Stage Percentage
closed on time
Target
Stage One  93% 80% and above
Stage Two 92% 85% and above
The volume closed on time includes complaints that had their timescales extended and met
the new due dates.
To allow comparisons to be made, the table below shows the percentage of complaints
closed on time at both stages over the last three years:
Year Stage One %
closed on time
Stage Two %
closed on time
2023/24  87% 88%
2024/25 92% 93%
2025/26 93% 92%
3 Volume of complaints not closed on time per Directorate
This section provides details of complaints not closed on time under each Stage and includes
extended complaints that did not meet their new timescales.
Stage One
123 complaints did not meet timescale during the year and the volumes are noted below.
Corporate Services 
Department Volume
Customer Services 6
Finance 1
Legal Services 1
60

Page 61

7 
PUBLIC INFORMATION
Communities & Housing 
Education
Department Volume
Education (HQ) 1
Education (Schools) 9
Facilities Management 3
Health & Social Care
Department Volume
Children & Families 3
Finance & Transformation 2
Health & Community Care 16
Mental Health 1
Support Services 1
Place
Department Volume
Property Management 18
Roads 5
Streetscene 5
Sustainability 1
Transport 2
Waste Services 6
Multiple reasons were noted as to why the above complaints did not meet timescale, including
administrative errors, information awaited to conclude complaints, employee availability, resourcing
issues and operational pressures.
Of the 123 Stage One complaints that did not meet timescale, 18 had their timescales
extended the additional five working days however none met the new due dates so these
complaints could have been escalated and handled as Stage Twos. 
In relation to the 105 complaints that did not have their timescales extended, 73% would
have been closed within the five additional working days had extensions been applied.
Stage Two
22 complaints did not meet timescale during the year and the volumes are noted below.
Department Volume
Building Services 11
Community Facilities 3
Community Learning & Dev 1
Housing 22
Planning 2
Protective Services 3
61

Page 62

8 
PUBLIC INFORMATION
Communities & Housing
Department Volume
Building Services 3
Housing 6
Protective Services 3
Education
Department Volume
Education (Schools) 2
Health & Social Care
Department Volume
Children & Families 2
Health & Community Care 2
Mental Health 3
Place
Department Volume
Roads 1
Reasons noted as to why the above complaints did not meet timescale are similar to those
that did not meet timescale at Stage One. 
62

Page 63

9 
PUBLIC INFORMATION
4 Key complaint topics
Key topics for upheld and partially upheld complaints for Services are listed below. Services
will not be listed where there were low complaint volumes that did not allow meaningful
analysis.
Corporate Services
Service Key complaint topic
Customer Services Incorrect information provided
Customer Services Employee Actions (alleged or perceived)
Communities & Housing
Service Key complaint topic
Building Services Quality issues (work incomplete or poor workmanship)
Building Services Employee Actions (alleged or perceived)
Education
Service Key complaint topic
Education (schools) Sensitive issues relating to teachers and/or pupils
Education (schools) Service delivery
Education (schools)) Employee Actions (alleged or perceived)
Health & Social Care
Service Key complaint topic
All HSCP Services Service delivery
All HSCP Services Employee Actions (alleged or perceived)
Place
Service Key complaint topic
Property Management &
Investment
Gas Central Heating (contractors, maintenance etc.)
Streetscene Tree/grass/verge/hedge cutting issues
Waste Services Missed waste bin/assisted collections (all colours)
Waste Services Employee Actions (alleged or perceived)
Employee Actions (alleged or perceived) appears as a key topic for some Services but the
definition is broad and has been used where complainants allege or believe employee
actions and/or behaviour to be unacceptable. Whilst investigations may determine this is
not always the case, if unacceptable behaviour is identified appropriate action will have
been taken by services to address.
63

Page 64

10 
PUBLIC INFORMATION
5 Average time in working days for a full response
The average time in working days to close complaints under both Stages during the year is
noted below. Values for previous years have been included to allow comparisons to be
made. Any complaints that had their timescales extended have been excluded from the
calculations.
Stage One Average number of
working days to close
Target
2023 3.8 5 workings days or less
2024 3.3 5 workings days or less
2025 2.9 5 workings days or less
Stage Two Average number of days
to close
Target
2023 16.8 20 working days or less
2024 15.5 20 working days or less
2025 16.4 20 working days or less
The average number of days to close Stage One and Stage Two complaints is better than the
national targets. 
The tables below detail Services that did not meet the average time in working days for a
response under either Stage. Services that met the target are not listed and any complaints
that had their timescales extended have been excluded from the calculations.
Communities & Housing
Stage One Average number of
working days to close
Target
Community Learning &
Development
7 5 workings days or less
Protective Services 6.4 5 workings days or less
One CL&D complaint was closed on working day 13 which resulted in the average days target
being breached. No reason was given as to what caused the delay.
One Protective Services complaint was closed on working day 43 because the complaint was
inadvertently overlooked and the complainant was not engaging with the service regarding
the complaint.
Stage Two Average number of
working days to close
Target
Protective Services 29.6 20 workings days or less
Three Protective Services complaints were closed at 30, 33 and 50 working days, resulting in
the average days target being breached. Various reasons were noted as to why the due dates
were not met and at least one of the complaints could have had its due date extended.  
64

Page 65

11 
PUBLIC INFORMATION
Place
Stage One Average number of
working days to close
Target
Sustainability 10.5 5 workings days or less
Transport 7.4 5 workings days or less
One Sustainability complaint was closed on working day 20, resulting in the average days
target being breached. The delay was due to a processing issue and the complaint being sent
to an incorrect service initially.
Two Transport complaints were closed on working days 16 and 17, resulting in the average
target days not being met. Given the circumstances, both complaints could have been
escalated and handled at Stage Two. 
Health & Social Care
Stage Two  Average number of
working days to close
Target
Mental Health 26 20 workings days or less
Three Mental Health complaints were closed at 31, 51 and 59 working days, resulting in the
average days target being breached. Various reasons were noted as to why the due dates
were not met and all of them could have had their due dates extended given the
circumstances. 
6 Extended complaints
159 complaints had their timescales extended during the year (112 at Stage One and 47 at
Stage Two). The complaints related to various Services across all Directorates.
There were various reasons for extending, including complainants, third parties and
employees being unavailable to assist or support with investigations and/or response letter
approvals, obtaining additional information to support investigations and
resourcing/operational issues. Of the 159 complaints that had their timescales extended,
89% were closed within their new target due dates. 
65

Page 66

12 
PUBLIC INFORMATION
7 Complaint Outcomes
The Council has four categories of complaint outcomes. 
• Resolved complaints are complaints where the Council has taken action to address a
problem/issue without needing to decide if there were any failings. 
• Upheld complaints are complaints where something has gone wrong/not happened
and the Council needs to take steps to address.
• Partially Upheld complaints are complaints that have multiple complaint elements,
some of which are upheld, the rest not.
• Not Upheld complaints are complaints that have not been upheld for the following
reasons:
• they related to internal or external policies
• they related to external regulations
• upon investigation they were proven to be unfounded/unsubstantiated
The tables below detail the number of complaints upheld, partially upheld, not upheld or
resolved under both Stages.
Stage One
Outcome Percentage
Closed as Resolved 39%
Closed as Upheld 35%
Closed as Partially Upheld 10%
Closed as Not Upheld 16%
Of the 807 complaints that were upheld and partially upheld at Stage One, the three
services that had the highest volume were Waste Services with 45%, Building Services with
13% and Education (HQ and schools) with 9%.
33% of all Resolved complaints related to Waste Services (mainly missed bin collections),
indicating those complainants simply wanted their bins collected without any need for
investigation. The other complaints closed as Resolved related to various services across all
Directorates.
Complaints that were not upheld related to internal/external policies, regulations and
complaints that were found to be unfounded.
Stage Two 
Outcome Percentage
Closed as Resolved 9%
Closed as Upheld 11%
Closed as Partially Upheld 36%
Closed as Not Upheld 44%
66

Page 67

13 
PUBLIC INFORMATION
Stage Two complaints that were upheld or partially upheld related to various services across
all Directorates.
The reasons for Stage Two complaints being closed as not upheld are the same as those for
Stage One.
The tables below detail the outcomes at each stage covering the last three years:
Stage One complaints
Year Resolved Upheld Partially Upheld Not Upheld
2023/24 39% 32% 12% 17%
2024/25 47% 21% 11% 21%
2025/26 39% 35% 10% 16%
Stage Two complaints
Year Resolved Upheld Partially Upheld Not Upheld
2023/24 4% 13% 39% 44%
2024/25 10% 9% 26% 53%
2025/26 9% 11% 36% 44%  
67

Page 68

14 
PUBLIC INFORMATION
8 Improvements made from complaints
Council Services continually seek to identify improvements in service delivery and complaint
information is analysed regularly to inform service improvements. Some improvements were
implemented as a result of complaints received during the year and a selection is noted
below.
What happened What we did
A complaint was received regarding a
parent’s concerns over the safeguarding of
their child while attending school.
The matter was investigated and a parental
meeting held with the Head Teacher and others
to discuss all concerns raised. The parent was
happy with the actions agreed and the pupil was
taken through all safeguarding procedures. Key
Adults, safe places and various supports
throughout the pupil’s timetable were shared
with a summary card of support actions to be
completed by the pupil. The pupil accepted the
card and agreed it would be helpful.
A complaint was received that a window
cleaner working on behalf of the Council
asked a tenant in a sheltered housing
complex if they could gain access to the
inside of the complex via the tenant’s
property to clean the windows.
It was determined it was a window cleaner from
a contracted company and the contract only
covers the outside of the windows plus
communal areas. The Council now receive a list
of dates in advance from the company, stating
when they will be carrying out cleaning in each
housing complex.  We also now have a system in
place that they can gain access to the front door
(public areas only) of housing complexes without
having to call any flats or houses.
A resident set up a mygov.scot account but
was unable to link two properties to the
Council Tax system.
The issue was investigated and it was discovered
there was a problem within the system that
prohibited more than one property being added. 
This was fixed and the resident was thanked for
bringing this matter to our attention.
A resident complained that rats were
causing damage to their garden and the
nest was on unattended waste ground
between the resident’s property and a
Council property boundary.
The relevant services attended the area to
ensure access could be gained to clear it and the
Council is now reviewing its land ownership
plans to make sure maintenance responsibilities
are established going forward. 
68

Page 69

15 
PUBLIC INFORMATION 
9 Compliments
Over 300 compliments were recorded cross-Council during the year. Whilst they cannot all
be highlighted in this report, a selection is noted below (any employee names that were
provided have been redacted).
• “I would like to thank the plumber that attended my property today. He provided a fantastic
service. My husband is restricted in movement and he even came into the room to speak to
him. Such a lovely young man” 
• “I would like to thank X from the Council Tax department. She was excellent at her job, very
helpful and very kind. She dealt with my query immediately and went above and beyond for
me. You have a great employee there” 
• “Big thank you to X and Y at Largs Library today who made me feel so welcome and went over
and above to provide excellent customer service.  Both show that they care about people that
visit the library and give a great service to the community” 
• Caller wanted to thank the team that dealt with an abandoned car. It was handled very quickly
and a fantastic service was given. Praise was also given to X in the Contact Centre that took
the original call. 
• “My dad has recently been admitted to long term care. Before he was admitted we were really
pleased with the fantastic services we received from Care at Home, Dementia Support,
Stevenson Day Care and Anam Cara respite unit. These services all helped us to look after dad
and keep him at home for as long as possible. Support from the social worker to transition to
long term care was also exceptional. We are very grateful to everyone.” 
• “A huge thank you to North Ayrshire Council for the improvements made outside Beith Primary
School. The pavement is kept very clean and there’s a new bin and a sign to remind people to
pick up after their dog. It had been a problem for a while but is now so much better. Thank
you.” 
• “Would just like to say how amazing it was going to Bartonholm Recycle Centre today via the
booking system. So easy to do, no waiting to enter, straight in to be greeted by 2 lovely
gentleman who directed me to skips. Once I moved round I was met by a young guy who was
also friendly and helpful.” 
• “Can you please pass on my thanks to X in the Roads department for assisting in carrying out
pavement repairs near my home. I am delighted. Thanks.” 
• “This is for the Refugee Housing Team in North Ayrshire Council. They are doing the best job
for all of us who are looking for homes here in Scotland. Really thankful for the help and
support. The best people and the best team ever. Thank you so much” 
• “To Streetscene - really happy with the grass cutting at the High Road in Saltcoats - the place
looks so nice and so tidy. Look superb”
69

Page 70

16 
PUBLIC INFORMATION
10 SPSO complaint referrals
The Scottish Public Services Ombudsman (SPSO) is the final stage for complaints about Local
Authorities in Scotland. The SPSO has published its 2025/26 referral statistics and the table
below details the volume of complaints relating to North Ayrshire Council that were referred to
the SPSO during the year: 
Type of complaint Volume
Building Control 0
Consumer Protection 0
Economic Development 0
Education 6
Environmental Health and Cleansing 1
Finance 6
Fire & Police Boards 0
Housing 17
Land and Property -0
Legal and Admin 3
Local Authority 0
Other 0
Personnel 0
Planning 1
Recreation and Leisure 0
Roads and Transport 6
Social Work 4
Subject unknown or Out of Jurisdiction 5
Valuation Joint Boards 0
Welfare Fund - Community Care Grants 1
Welfare Fund - Crisis Grants 0
Total 50 
• The SPSO received 2,143 complaints about Scottish Local Authorities during 2025/26
and 2.3% related to North Ayrshire Council. This referral rate is consistent with previous
years (typically between 2% to 3%). 
• The highest number of referrals made to the SPSO about the Council related to Housing
but this was not unexpected given 31% of all Local Authority referrals made to the SPSO
during the year related to housing or housing services. 
The outcomes of the North Ayrshire Council complaints referred to the SPSO are noted below. 
Stage Outcome Volume 
Advice/Assessment
Complaint submission - mature 2
Complaint submission - premature 7
Enquiries 12
70

Page 71

17 
PUBLIC INFORMATION 
Early Resolution
Discretion – Good complaint handling 6
Discretion – Insufficient benefit would be achieved by
investigation 
1
Preliminary
Investigation
Discretion – Good complaint handling 10
Discretion – Insufficient benefit would be achieved by
investigation
6
Discretion – Referred back 1
Subject matter not in jurisdiction 4
Time limit 1 
Investigation
Fully upheld 0
Not duly made or withdrawn 0
Not upheld 0
Partially upheld 0 
• All referrals made by North Ayrshire complainants were resolved by the SPSO at their
advice, early resolution or preliminary investigation stages. No complaints were taken
to investigation. 
• Most complaint referrals handled at early resolution and preliminary investigation
were discretionary and it is pleasing to note many were considered ‘good complaint
handling’ complaints, meaning the SPSO was satisfied with the way the Council
handled them. 
More details regarding complaint referrals for North Ayrshire Council can be found on the SPSO
website at Our findings | SPSO.  
71

Page 72

18 
PUBLIC INFORMATION
11 Glossary
Terms & Explanations
Stage One 
Stage One (also known as Frontline Resolution) complaints are complaints that are
straightforward to address and require little or no investigation. Any employee may deal
with complaints at this stage and they can be concluded via any channel. The main principle
is to seek resolution at the earliest opportunity and as close to the point of service delivery
as possible. 
Stage One complaints must be responded to within five working days unless an extension (a
maximum of five additional working days) is requested and approved by a senior manager or
above. The Council should, however, always aim to conclude these types of complaints
within five working days.
Stage Two
Not all complaints are suitable for Stage One and not all complaints will be satisfactorily
concluded at that stage. Complaints therefore handled at Stage Two (also known as
Investigations) typically require a detailed examination before the Council can state its
position. These complaints may already have been considered at Stage One, or they may
have been identified from the outset as being complex, serious or high risk and needing
immediate investigation. 
Stage Two complaints must be responded to within 20 working days unless an extension is
approved by senior manager in conjunction with the customer. Stage Two complaints
require a written response, signed by a senior manager or above.
Complaint criteria 
When an expression of dissatisfaction is received the Council determines if the issue falls
into one (or more) six complaint categories:
• A service the Council should be providing is not being provided or is not available
• A request for a service was provided but not to an appropriate standard 
• A request for service has not been answered or actioned within the agreed timescale
• A Council employee was rude, unhelpful or unprofessional
• A Council employee did not attend an appointment or call-out on a date/time agreed
• The complaint relates to an internal or external policy (but only where the complaint
relates specifically to the way the matter was administered)
If the issue being raised relates to one or more of the above, the matter is considered a
complaint and will be recorded and handled as such. If not, it is deemed to be something
else and will be actioned under the relevant process.
72

Page 73

NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee 
Title:    Elected Member Development 
Purpose:  To provide information and seek views on the development
sessions provided to Elected Members over the 12 months from
September 2025 to August 2026, and on future planned
development sessions. 
Recommendation:  That the Committee notes the report and provides feedback (a)
on the Elected Member Development sessions held in the
period September 2025 to August 2026 (b) on means to support
Elected Member attendance (c) on how future programmes
might be improved (d) the future development sessions
scheduled to date and (e) to suggest additional topics for the
next year. 
1. Executive Summary 
1.1 This report provides information on development support provided to Elected Members
during the period September 2025 - August 2026, on attendance rates, feedback from
current activities and on future planned development. 
2. Background 
2.1 An annual report is provided to Audit & Scrutiny which details the Council's learning
events programme for Elected Members and individual Elected Member attendance
figures.  This report provides information for the period September 2025 until August
2026 inclusive. 
2.2 The Audit Commission report on “Roles and Working Relationships - Are you still
getting it right?” emphasised that Councillors need the skills and tools to carry out their
role. This includes training in relation to both Council and ALEO responsibilities, as
well as scrutiny, audit and financial decision making. Finally, it noted that training and
development should be an ongoing process, not a one-off induction. 
2.3 North Ayrshire Council has continued to offer a full training programme for Members in
addition to e-learning and the opportunity to attend Improvement Service events and
webinars. The number of internal development sessions from September 25 – August
26 was 14 sessions. 
Agenda Item 6
73

Page 74

2.4 Appendix 1 contains details of the internal development that has taken place between
Sep 25 and Aug 26. Individual Member attendance from Sep 2025 to Aug 2026 varied
between attendance at 13 sessions to attendance at none. 
2.5   Elected members also have access to e-learning modules on the iLearn system. Take
up of this learning is low although one Councillor has completed four courses from
Sep 2025 to Aug 2026. 
2.6 Overall there were 137 separate Member attendances at development sessions
between Sep 25 and Aug 26. These figures include those aimed at specific committee
members (i.e. Appeals).   
2.7   The Council offers Members an annual 1-2-1 Personal Development Plan (PDP)
discussion to discuss their development needs.  Whilst take up for this is historically
low, any requests from Members have been actioned. For example, the Planning
Awareness session was previously limited to Planning Committee Members only. This
has now been opened up to all Members after a Member request. 
2.8 Council previously agreed that all Members who sit on the Appeals Committee should
receive training before they sit on the Committee. An externally facilitated session was
held in May 2026 for three new panel Members, but open to any of the existing panel.
Two Members were in attendance. 
2.9 Members can provide feedback by electronic means on sessions attended. For the
period Sep 25 – Aug 26 the feedback response rate was 20%. The sessions are rated
1-5 by respondents on content, presentation, friendliness of tutor, relevance and
overall service provided.  The feedback is primarily positive with only four ratings of 3
or less and everything else a 4 or 5. Generally training is well received with Members
confirming that for the majority of sessions their skills/knowledge has increased by
attending the training. A breakdown of the 28 evaluations received for all sessions for
this 12 month period is included in Appendix 2. 
2.10 In addition to provision offered by the Council, there is learning available from the
Improvement Service (IS) in the form of Briefing notes, masterclasses, newsletters
and more recently webinars.  Our own intranet Connects site also hosts information,
such as the slides from learning events.   
2.11 We are currently at the early stages of planning for the 2027 Elected Member
Induction Programme. In June 2026, a survey was issued to Elected Members to
gather feedback on the effectiveness of the 2022 Induction Programme in preparing
them for their role, and to seek views and suggestions on the development of the
2027 programme. Five responses were received. The feedback provided will be taken
into account in the design and delivery of the 2027 Induction Programme. 
2.12 Members and Officers are consulted on future training topics and any views from the
Committee are also welcome. The Elected Member Learning and Development Event
Schedule for the latter half of 2026 is still in development and will be published in due
course.  A draft copy of the sessions already planned is included in Appendix 3. 
2.13 In conclusion, the Council continues to offer an extensive development programme for
Members. While attendance levels vary from one session to another and between
individual councillors, on average Members attend a significant volume of
74

Page 75

development, particularly when on-line and external events are included.
Nevertheless, it is important that the Committee has the opportunity to review the
current development arrangements and suggest improvements. 
3. Proposals 
3.1 The Committee is recommended to note the report and to provide feedback a) on the
Member Development sessions held in the period September 2025 to August 2026, b)
on means to support Member attendance c) on how future programmes might be
improved d) the future development sessions scheduled to date and e) to suggest
additional topics for the next year. 
4. Implications/Socio-economic Duty 
Financial 
4.1 Investment in development produces more informed decisions and better outcomes. As
this supports good governance and better decision making, Elected Member
development continues to be an area of focus in terms of Best Value activity. 
Human Resources 
4.2 Effective development is key to keeping North Ayrshire Council as a high performing
Council. 
Legal 
4.3 Effective development is a key component of good governance, leading to better
decisions. 
Equality/Socio-economic 
4.4 Effective equalities training is essential for Members. Training in equalities assists
Members to develop policy and inform decision making processes whilst ensuring that
appropriate equalities impacts are taken into account. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 Sharing of information and knowledge through briefings and development sessions with
Elected Members supports the delivery of all priorities outlined in the Council Plan. 
Community Wealth Building 
4.7 There are no direct community wealth building impacts although trained and skilled
Members will be better placed to support their communities. A session on the
Community Wealth Building refresh is planned for next year.
75

Page 76

Islands Communities Impact Assessment (ICIA) 
4.8 There are no direct island communities impacts although trained and skilled Members
will be better placed to support their island communities. A session on the Islands
Programme & National Islands Plan is planned for September. 
United Nations Rights of the Child (UNCRC) 
4.9 There are no direct impacts on UNCRC although there is an e-learning module on
iLearn available to Elected Members. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 The Learning and Organisational development team have been involved in the
preparation of this report. All sessions have been evaluated 
Aileen Craig
Head of Democratic Services 
For further information please contact Paul Houston, Learning and Organisational
Development Adviser, by email on phouston@north-ayrshire.gov.uk. 
Background Papers
None  
76

Page 77

Appendix 1 - Learning & Development Attendance Sep 25 - Aug 26  
  
Community Justice
Parental Employment 
Connected for Change
Supporting Children with Additional
Needs
Community and Locality Planning
Code of Conduct
Cyber Security Update
Planning
Considering Statutory Impact Duties
Councillor Duties on Outside Bodies
Using MyNAC
Appeals Panel
Cyber Security Update
Disclosure Scotland and PVG
  
Alan Hill  Y       Y  Y   Y Y 5
Amanda Kerr                0
Angela Stephen                0
Anthea Dickson    Y Y  Y Y Y Y Y Y  Y Y 10
Anthony Gurney  Y       Y Y Y  Y  Y 6
Cameron Inglis  Y Y   Y Y  Y Y Y   Y  8
Charles Currie     Y Y Y Y      Y 5
Chloe Robertson   Y    Y         2
Christina Larsen   Y  Y Y Y  Y Y  Y Y Y  9
Davina McTiernan  Y Y Y Y  Y Y  Y  Y  Y Y 10
Donald L Reid  Y Y Y Y Y Y Y Y Y Y Y  Y Y 13
Donald Reid  Y Y Y  Y Y Y Y Y Y Y  Y  11
Eleanor Collier    Y   Y Y Y Y Y   Y  7
Ian Murdoch      Y  Y Y  Y    Y 5
Jean McClung      Y          1
Jim Montgomerie                0
Joe Cullinane                0
John Bell  Y  Y Y Y  Y Y Y Y     8
John Sweeney  Y Y Y Y    Y Y Y Y  Y Y 10
Louise McLaughlan                0
Margaret Johnson  Y Y Y Y Y Y Y   Y Y  Y Y 11
Marie Burns    Y Y     Y      3
Mary Hume  Y Y Y Y Y Y Y Y Y    Y 10
Matthew McLean                0
Nairn -
AngusMcDonald                0
Robert Foster                0
Ronnie Stalker                0
Scott Davidson         Y       1
Scott Gallacher                0
Shaun Macaulay                0
Stewart Ferguson      Y Y         2
Todd Ferguson                0
Tom Marshall                0
Totals  9 9 10 9 11 12 10 14 12 12 7 2 10 10 137 
77

Page 78

Appendix 2 – Evaluation Feedback from Sep 2025 – Aug 2026 
Development Session Content
Presentation
Tutor
Relevance
Overall
Has the
session
increased
your
knowledge
and/or
skills?
6 Oct 2025 - Community Justice - Working Together 4 4 4 4 4 Yes
6 Oct 2025 - Community Justice - Working Together 5 5 5 5 5 Yes
22 Oct 2025 - Parental Employment Support 4 4 5 4 4 No
22 Oct 2025 - Parental Employment Support 5 4 5 5 5 Yes
22 Oct 2025 - Parental Employment Support 5 5 5 5 5 Yes
30 Oct 2025 - Connected For Change 4 4 5 4 4 Yes
30 Oct 2025 - Connected For Change 5 5 5 5  Yes
6 Nov 2025 - Supporting Children With Additional Needs 5 5 5 5 5 Yes
6 Nov 2025 - Supporting Children With Additional Needs 5 5 5 5  Yes
10 Nov 2025 - Community and Locality Planning 5 5 5 2 3 No
10 Nov 2025 - Community and Locality Planning 5 5 5  5 Yes
12 Nov 2025 - Code of Conduct 5 5 5 5  Yes
19 Nov 2025 - Cyber Security Update 4 4 4 4 4 Yes
19 Nov 2025 - Cyber Security Update 5 5 5 5 5 Yes
19 Nov 2025 - Cyber Security Update 5 5 5 5 5 Yes
8 Dec 2025 - Planning Awareness Update 5 5 5 5 5 Yes
8 Dec 2025 - Planning Awareness Update 5 5 5 5 5 Yes
8 Dec 2025 - Planning Awareness Update 4 4 4 4 4 Yes
10 Dec 2025 - Considering Statutory Impact Duties 4 4 4 4 4 Yes
10 Dec 2025 - Considering Statutory Impact Duties 5 5 5 5 5 Yes
26 Jan 2026 - Councillor Duties on Outside Bodies 5 5 5 3 4 No
26 Jan 2026 - Councillor Duties on Outside Bodies 5 5 5 5 5 Yes
27 Apr 2026 - Using MyNAC to Log Constituent Requests 3 4 4 2 3 No
27 Apr 2026 - Using MyNAC to Log Constituent Requests 5 5 5 5 5 Yes
27 Apr 2026 - Using MyNAC to Log Constituent Requests 4 4 4 5 4 Yes
27 May 2026 - Cyber Security Update 5 5 5 5 5 Yes
27 May 2026 - Cyber Security Update 4 4 4 4 4 Yes
22 Jun 2026 - Disclosure Scotland and the PVG Scheme 5 5 5 5 5 Yes 
Note
The scale runs from 1 (Dissatisfied) to 5 (Satisfied) on all of these ratings, with the
exception being Overall which is presented as 1 (Dissatisfied) to 5 (Delighted).
78

Page 79

Appendix 3 – Elected Member Development Schedule Sep – Dec 2026 (DRAFT) 
Date Topic Delivered by  Lead Comments     
TBC Roads Update Graeme Robin
(Asset and Strategy
Manager, Roads),
Stewart Walker
(Network and
Operations
Manager, Roads)
Thomas
Reaney (Head
of Service,
Neighbourhood
Services)
TBC
9 Sep 2026
3pm – 4pm
Islands Programme & National
Islands Plan – Progress and Next
Steps
Sarah Baird (Senior
Officer, Islands)
Louise Kirk
(Director,
Regional
Economy)
This session will update Elected Members on the North
Ayrshire Islands Programme and the new National Islands Plan,
including progress to date, key developments and the proposed
next steps to progress delivery and maximise impact for our
island communities.
15 Sep 2026
10am - 11am
Supporting Needs: The Placement
Process
Lindsay Morris
(Executive
Manager),
Xanthe Wylie
(Principal
Psychologist),
Angela Merrylees-
Stalker (Quality
Improvement
Officer)
Andrew
McLelland
(Head of
Service,
Education)
Many children have their needs well supported by their local
mainstream school. In some cases, an alternative placement is
considered. This session will take members through our process
for ensuring appropriate placement in specialist provision, from
identifying needs, to making a referral to the Inclusion Group
and beyond. We will cover the range of universal supports
available in our establishments as well as targeted and
specialist provision. We will also outline the appeals process.
79

Page 80

Date Topic Delivered by  Lead Comments
5 Oct 2026
(2pm – 3pm) 
Community Grants and Funding Jacqueline
Greenlees (Senior
Manager, Policy,
Performance &
Community
Planning)
Rhonda Leith
(Head of
Service,
Connected
Communities)
TBC
2 Nov 2026
3pm – 4pm
Cyber Security Update Gavin Alston (Team
Manager, ICT and
Cyber Security),
Fraser Cunningham
(Cyber Security
Officer) and
Stephen Quigley
(Cyber Security
Officer)
Fiona Walker
(Head of
Service, People
and ICT)
In this session the Cyber Security Team will give an overview of
the cyber security threats facing the Council and the action
being taken to meet these challenges. Elected Members are at
an increased risk of targeted cyber attack, the team will give
practical advice on how to keep yourself safe online. Finally,
there will be time for discussion and any questions.
9 Nov 2026
10am – 11am
Code of Conduct Update  Aileen Craig (Head
of Service,
Democratic
Services) 
This session will provide an update on the Councillor Code of
Conduct and recent cases.
18 Nov 2026
(10am – 11am) 
Youth Employment Laura Neill (Senior
Manager) 
Sam Anson
(Executive
Director,
Education)
TBC
7 Dec 2026
(2pm – 3pm)
Planning Awareness Update Allan Finlayson
(Senior Manager
Aileen Craig
(Head of
Mandatory training for elected members was included in the
Planning (Scotland) Act 2019 and North Ayrshire’s Planning and
Legal service have provided this training to Planning Committee
80

Page 81

Date Topic Delivered by  Lead Comments
(Planning) /
Raymond Lynch
(Senior Manager
(Legal)
Service,
Democratic
Services)
members. The latest opportunity to do so again has now
arrived and the invitation to participate in training is being
widened to all elected members. This is to raise awareness of
the Council’s National Planning Improvement Framework which
will be subject to consultation and engagement with all
Community Councils. 
The training session will provide elected members with an
overview of the following aspects of the Planning system in
Scotland and how this affects communities.
• An introduction to the Planning service
• What is Planning?
• Introduction to the Council’s Planning team
• Development Planning – the Local Development Plan
and National Planning Framework (NPF4)
• Development Management – the assessment of
planning applications by officers and the Planning
Committee
• Enforcement
• Other Planning roles
TBC  Child Poverty Laura Kayes (Policy
Officer) Child
Poverty) 
Sam Anson
(Executive
Director,
Education)
TBC 
81

Page 82

82

Page 83

NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee 
Title:    Internal Audit Reports Issued and Update 
Purpose:  To inform the Committee of the findings of Internal Audit work
completed since June 2026 and the progress made by Council
Services in implementing the agreed actions from Internal Audit
as at 30th June 2026 
Recommendation:  That the Committee considers the outcomes from the Internal
Audit work completed and the current position with the
implementation of Internal Audit actions. 
1. Executive Summary 
1.1 The Council's local Code of Corporate Governance requires effective arrangements to be
put in place for the objective review of risk management and internal control. Internal Audit
is an important element in this framework as it reviews internal controls and offers Elected
Members and officers an objective and independent appraisal of how effectively resources
are being managed. 
1.2   The remit of the Audit and Scrutiny Committee includes the monitoring of Internal Audit
activity. The submission of regular reports assists the Committee in fulfilling this remit. 
1.3 Since the previous Committee meeting, one audit has been finalised and issued with a
Substantial Assurance opinion. No high priority recommendations were raised. Two
medium priority improvement actions were agreed with management. In addition, as at 30
June 2026, there were no overdue Internal Audit recommendations requiring separate
reporting to Committee. 
2. Background 
2.1 This report provides information on Internal Audit work completed since June 2026. Internal
control reviews have been completed in respect of the areas detailed in Appendix A to this
report. The aim of these reviews is to provide assurance that the internal control framework
within the areas examined is appropriate and operating effectively. 
2.2   The findings from each audit assignment have been notified in writing to the Chief
Executive, the Section 95 Officer and the relevant Executive Director and Head of Service
on the completion of each assignment. Where appropriate, this has included an action plan
with recommendations for improving internal control. Appendix A includes the report and
action plan from each audit. 
2.3 Whilst only one final audit report is presented within this report, a number of additional
reviews have reached the draft reporting stage and are currently progressing through
Agenda Item 7
83

Page 84

management clearance processes. These audits are expected to be reported to a future
meeting of the Committee and include Social Work Establishments, ICT Asset
Management, Information Security, IJB Financial Sustainability and Neighbourhood
Services – Overtime. 
2.4 The findings from the audit assignment completed are detailed at Appendix A to this report
and the levels of assurance for each are noted in the table below: 
Audit Title Assurance Level
ELC Payments to Partner Providers Substantial 
2.5 The audit identified a generally effective control framework within the area reviewed. The
recommendations raised relate to opportunities to strengthen ongoing contract monitoring
arrangements and do not materially affect the overall assurance opinion. 
2.6   There are no overdue Internal Audit recommendations requiring reporting to Committee. 
3. Proposals 
3.1 It is proposed that the Committee notes the outcomes from the Internal Audit work
completed since June 2026 and the current position with respect to the implementation of
Internal Audit Actions. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of Internal Audit helps to support the efficient delivery of the strategic priorities
within Our Council Plan 2023-2028. 
Community Wealth Building 
4.7 None. 
84

Page 85

Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 The relevant Services are consulted on Internal Audit findings during each audit
assignment. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Paul Brown, Senior Manager (Audit, Fraud, Health,
Risk & Insurance), on paulbrown1@north-ayrshire.gov.uk. 
Background Papers
None.  
85

Page 86

Appendix A 
ELC Payments to Partner Providers 
1 Background  
1.1    The Scottish Government provided local authorities with additional funding of £9.7
million in 2025-26 to enable childcare workers delivering funded Early Learning and
Childcare (ELC) in private and third sector services to be paid at least the new Real
Living Wage rate of £12.60 per hour from April 2025. Local authorities are required to
pass this additional funding to funded providers through a minimum 3.75% uplift to all
2024-25 sustainable rates. The uplift reflects the estimated increase in the average
staff cost element of the sustainable rate, approximately 75%, required to meet the
real Living Wage uplift from April 2025. North Ayrshire Council opted to apply an uplift
of 4% to the sustainable rate in light of this, along with the variations in cost
circumstances across its partner funded providers. This resulted in rates of £6.77 per
hour for 3–5-year-olds and £7.08 for eligible 2-year-olds from April 2025-March 2026.  
1.2  North Ayrshire Council currently contracts with 16 funded provider nurseries and 51
childminders to deliver up to 1140 hours of funded early learning and childcare to
families. The current contracts commenced in August 2025 for 5 years. Funded
providers enter a contract with North Ayrshire Council requiring them to meet the
National Standard for Early Learning and Childcare Providers. In return, North
Ayrshire Council pay an hourly (sustainable) rate for up to a maximum of 1140 hours
per annum per child.  
2 Objectives and Scope 
2.1 The main objectives for this audit were:
• To ensure that there are suitable policies and procedures in place regarding the
provision of early years childcare.
• To ensure that conditions of Scottish Government Funding are being adhered to.
• To ensure that payments to providers are made correctly and promptly and reflect
the agreements made with providers.  
2.2 The scope of this audit is focussed on partner providers of early years learning and
childcare. This includes childminders and partner nurseries. It excludes nurseries run
by North Ayrshire Council directly.  
3 Findings   
Policies and Procedures  
3.1 The auditors reviewed relevant policies and procedures relating to the provision of
early years childcare, including Early Learning and Childcare Model Terms and
conditions, to ensure that they are suitable and fit for purpose.  
3.2 It was noted that the Terms and Conditions document, which forms part of the latest
5-year contracts with partner early years providers, included links to Scottish
Government guidance which has been superseded. Education confirmed that Terms
and Conditions documents, incorporating the up-to-date Scottish Government
guidance, were prepared in September 2025, but had not yet been issued to providers.
A contract amendment was issued near the end of the audit process to require
providers to adhere to the latest Scottish Government guidance.  
86

Page 87

Appendix A 
Scottish Government Funding  
3.3 Cabinet reports presented on 30 April 2024 and 3 June 2025 set out how the Council
were using the funding from the Scottish Government to increase the rates paid to
external providers and financial documentation provided showed the applicable
budget calculation. In June 2025, providers were asked to agree to pay childcare
workers a minimum of £12.60 an hour in return for the increase in the hourly rate paid
to the provider by NAC. All providers agreed to this rate increase.  
3.4 From August 2025, the contracts with providers require them to pay all individuals
delivering the funded hours at least the Real Living Wage. The questionnaire for the
annual review of contract compliance asks providers to confirm that this is the case.
The service agreed that the Link Officer will also spot-check compliance with this
requirement during quality improvement visits. (Action a)   
Payment of Providers  
3.5 A procedure note for processing claims from providers, including processes to check
the payment and authorisation, was provided but found to be designed for someone
with a high level of understanding of the existing process. Another procedure note for
approval of payments was provided and found to be suitable for the part of the process
it covers. There were no other procedure notes for other processes. However, the
service were already in the process of implementing new procedures and preparing
accompanying notes. The new procedures were provided near the end of the audit
period and were found to be clearly presented and comprehensive.  
3.6 The auditors tested a sample of 30 payments to partner providers to ensure that:
• payments reflected the agreement with the provider, including the uplift for the
payment of the Real Living Wage.
• payments reflected the arrangements agreed for the individual children.
• all uplift agreements for the sample had been completed and signed.
• all payments were arithmetically correct.
• all payments had been checked and authorised properly. 
3.7 There were some discrepancies regarding the agreements with the individual children
in the registration forms provided by the partner providers. However, none had a
material or financial impact. These have been highlighted and either corrected or will
be addressed in the new process.  
3.8 The majority of payments were checked and authorised in line with the correct
procedure at the time of payment. In one instance, a payment was not authorised in
line with the current procedure as the authoriser had not been copied into the email to
Accounts Payable and the payment went ahead regardless. However, Accounts
Payable have since amended their process so that authorisations must be submitted
directly from the authoriser, with copied in approvals no longer accepted. As a result,
this type of error should not recur.  
3.9 Contract monitoring arrangements, including compliance and provider sustainability,
were discussed with the service. The service have regular contact with all the
providers, including monthly meetings, Council-led training sessions (including for
child protection) and quality improvement visits. Teacher Team visits are undertaken
across all providers, reviews of the nursery providers take place and childminders
receive Link Officer visits. These visits and reviews are delivered as part of a rolling
programme. 
87

Page 88

Appendix A 
3.10 The service also monitor reports issued by the Care Inspectorate, as one of the Terms
and Conditions requires that providers must not fall below a level 4 in any category of
the Care Inspectorate ratings. Where a provider falls below this standard, the Council
issues notice of a Service Improvement Period (SIP) requiring them to make
improvements in order to regain the required grade from the Care Inspectorate.
Evidence was shared with the auditors of such an instance. The service had supported
the provider to create and implement an improvement plan which had allowed them
to achieve the required standard when the Care Inspectorate re-visited them.
Therefore, the Council had formally notified them of the conclusion of the SIP.  
3.11 The contracts are still in their first year, but plans are in place to commence an annual
review of contract compliance via a questionnaire asking providers to confirm
compliance with various aspects of the Terms and Conditions and to provide up-to-
date copies of documentary evidence. The auditors noted when looking at the
questionnaire that the section entitled "Insolvency, Conflicts of Interests or
Professional Misconduct” didn’t include a question on Conflicts of Interest. This was
corrected during the audit. 
3.12 Financial sustainability of the providers is checked as part of the procurement process
but there is currently no pro-active checking of sustainability during the contract
period. Therefore, the service added a reference to the Council getting access to
annual business accounts into the annual self-assessment questionnaires. The Senior
Manager also agreed that the Link Officer would discuss sustainability with the
providers as part of the quality improvement visits. The service have prepared a
procedure for the event of a provider ceasing trading, which they would follow to place
any children who lost their placement in such an event. (Action b)  
4 Internal Audit Opinion  
4.1 Overall, substantial assurance was obtained with regard to the management of
payments to partner ELC providers. Generally, processes for managing ELC partner
providers are operating effectively but a few points for improvement were identified.
Errors identified during sample testing were not material and improvements being
made to the processes should reduce the risk of recurrence. The service have started
to implement the suggestions for improvement discussed during the audit. 
Definitions of Assurance Levels: 
Substantial
A sound system of governance, risk management and control exist, with
internal controls operating effectively and being consistently applied to
support the achievement of objectives in the area audited.
Reasonable
There is a generally sound system of governance, risk management and
control in place. Some issues, non-compliance or scope for improvement
were identified which may put at risk the achievement of objectives in the
area audited.
Limited
Significant gaps, weaknesses or non-compliance were identified.
Improvement is required to the system of governance, risk management
and control to effectively manage risks to the achievement of objectives in
the area audited.
88

Page 89

Appendix A 
None
Immediate action is required to address fundamental gaps, weaknesses or
non-compliance identified. The system of governance, risk management
and control is inadequate to effectively manage risks to the achievement of
objectives in the area audited. 
NB The level of assurance given is at the discretion of Internal Audit. 
89

Page 90

Appendix A 
KEY FINDINGS AND ACTION PLAN
ELC PAYMENTS TO PARTNER PROVIDERS 
Action a
Finding Checking of the compliance with the requirement to pay the Real
Living Wage to employees delivering funded hours is currently
based on self-declaration during the annual compliance
questionnaire.
Action Description The Link Officer should spot-check that employees delivering
funded hours are paid the Real Living Wage during quality
improvement visits.
Risk The Real Living Wage is not being paid to employees delivering
funded hours. This would be a breach of the provider’s contract
with North Ayrshire Council and the Scottish Government
guidance.
Priority (1, 2, 3) 2
Paragraph Reference  3.4
Managed by Head of Service (Education)
Assigned to Senior Manager (Education)
Due Date 31 October 2026
Management Comment The link officer has added this to her QIF agendas and will be
completed through her planned QIF visits throughout the year. 
Action b
Finding Financial sustainability of the providers is checked as part of the
procurement process but there is currently no pro-active checking
of sustainability during the contract period. 
Action Description The Link Officer should include discussion of provider
sustainability as part of the quality improvement visits.
Risk The Council has no warning of providers that face sustainability
issues and potentially cease trading, leading to a requirement to
find new placements for children at short notice with associated
costs.
Priority (1, 2, 3) 2
Paragraph Reference  3.12
Managed by Head of Service (Education)
Assigned to Senior Manager (Education)
Due Date 31 October 2026
Management Comment The link officer has added this to her QIF agendas and will be
completed through her planned QIF visits throughout the year. 
Priority Key used in Action Plan
1 (High) Control weakness where there is a material impact on the achievement of the
control objectives, generally requiring prompt attention.
2 (Medium) Control weakness which needs to be rectified, but where there is no material
impact on the achievement of the control objectives.
3 (Low) Minor weakness or points for improvement. 
90

Page 91

PUBLIC INFORMATION   
NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee 
Title:    Internal Audit Plan 2026/27: Progress as at 31 July 2026 
Purpose:  To provide an update on progress made in delivering the
2026/27 Internal Audit Plan. 
Recommendation:  That the Committee notes progress against the first six-month
Internal Audit Plan as at 31 July 2026. 
1. Executive Summary 
1.1 The first six-month plan within the 2026/27 Internal Audit Plan was approved by the
Audit and Scrutiny Committee in March 2026. The Plan sets out the areas of work which
Internal Audit intends to cover during the first half of the financial year. A further six-
month plan will be presented to the Committee in November 2026 as part of the
Council’s rolling internal audit planning arrangements.   
1.2   The Global Internal Audit Standards (GIAS) recognise that the internal audit plan should
be dynamic and updated in response to changes in the organisation’s business, risks
and control environment. Accordingly, the Chief Audit Executive (Senior Manager) is
required to review and revise the internal audit plan as necessary and to report such
changes to the Committee. 
1.3   Progress against the approved 2026/27 Internal Audit Plan is summarised in Appendix
A. As of 31 July 2026, seven of the ten assignments included in the six-month plan had
commenced. One assignment has been completed, one draft report has been issued,
three assignments were at the fieldwork stage, two at planning stage and three had yet
to commence. The position will be reviewed as part of the Mid-Year Update Report,
including any adjustments required to maintain delivery of the Audit Plan and support
the Annual Internal Audit Opinion. 
1.4   The Mid-Year Update will report the final position against the first six-month plan and
present the proposed plan for the remainder for 2026/27. It will identify any changes
required to maintain sufficient coverage of key risks and support the Annual Internal
Audit Opinion. 
1.5  At this stage, the current delivery position is not expected to have a material impact on
the Senior Manager’s ability to provide the Annual Internal Audit Opinion. This will be
reassessed as part of the Mid-Year Update. 
Agenda Item 8
91

Page 92

PUBLIC INFORMATION
2. Background 
2.1 In line with GIAS, the audit plan should be reviewed and revised as necessary. 
2.2 The Audit and Scrutiny Committee has responsibility for overseeing the effectiveness
of Internal Audit, including monitoring delivery of the approved Internal Audit Plan.
Periodic progress reporting enables the Committee to obtain assurance on the extent
to which planned audit work is being delivered and to understand any material changes
to the plan. 
2.3 Appendix A to this report summarises progress against the approved 2026/27 Internal
Audit Plan and provides an overview of the current status of each audit assignment. 
3. Proposals 
3.1 It is proposed that the Committee notes progress against the first six-month Internal
Audit Plan as at 31 July 2026, as specified in Appendix A.   
4. Implications/Socio-economic Duty 
Financial 
4.1 None. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The work of Internal Audit helps to support the efficient delivery of the strategic
priorities within the Council Plan 2023-2028 
Community Wealth Building 
4.7 None. 
92

Page 93

PUBLIC INFORMATION
5. Consultation 
5.1 Relevant services continue to be consulted throughout the planning, fieldwork and
reporting stages of individual audit assignments. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Paul Brown, Senior Manager (Audit, Fraud,
Safety, Risk and Insurance, on  paulbrown1@north-ayrshire.gov.uk 
Background Papers
None. 
93

Page 94

Appendix A 
PUBLIC INFORMATION
Position as of 31 July 2026 
Audit Assignment Title Planned Quarter Current Progress
Grants Compliance Q1 To Start
General Ledger Q2 To Start
Accounts Payable Transactions Q2 Fieldwork Ongoing
ICT – Incident Detection Q1 Fieldwork Ongoing
School Inventory Management Q1 Planning Stage
Neighbourhood Services – Overtime Q1 Draft Report Issued
Absence Management Q2 Planning Stage
Headstone Inspections Q1 Fieldwork Ongoing
Business Continuity Planning Q2 To Start
Tenants and Residents Association Q1 Complete 
94

Page 95

NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee 
Title:    Accounts Commission’s Briefing: Local Government
Budgets 2026/27 
Purpose:  To inform the Audit and Scrutiny Committee of the key
messages identified within the recently published briefing. 
Recommendation:  That the Committee notes the key messages within the recent
Accounts Commission briefing. 
1. Executive Summary 
1.1 In June 2026 the Accounts Commission published a briefing on Local Government
Budgets 2026/27. This briefing provides a high-level analysis of the 2026/27 budgets
agreed by all 32 Councils highlighting the challenges faced in achieving a balanced
budget and long-term financial sustainability. A link to the report is attached below: 
Local government budgets 2026/27 | Audit Scotland
1.2  The report provides an analysis of the level of Scottish Government funding provided
to Councils, the remaining budget gaps, the steps taken by Councils to bridge these
and the ways in which Councils consulted with their communities. 
2. Background 
2.1 The briefing provides an analysis from Audit Scotland of the budgets set by local
authorities for 2026/27. The report is included in appendix 1 and is in three parts: 
• Part 1 outlines the Scottish Government’s 2026/27 funding allocation to councils and
highlights trends in revenue and capital settlements compared with previous years. 
• Part 2 assesses how councils have balanced their 2026/27 budgets, including the use
of reserves and other measures. This is based on data returns submitted to Audit
Scotland by all councils in March and April 2026, shortly after agreeing their 2026/27
budgets. 
Agenda Item 9
95

Page 96

• Part 3 reviews how councils engaged with stakeholders and considered equality
impacts when making budget decisions.
2.2 The key messages within the briefing are summarised below:
• Despite a small real terms increase in Scottish Government funding for 2026/27,
councils still face major risks to their financial sustainability as funding fails to keep
pace with rising demand and increasing costs. Councils identified a combined budget
gap of around £529 million for 2026/27, representing a gap of around three per cent
of total General Fund revenue budgets across Scotland.  
• A 15 per cent decrease in capital funding is limiting councils’ capacity to sustain and
develop infrastructure, resulting in greater dependence on borrowing and heightened
long-term financial risk. 
• To achieve a balanced budget in 2026/27, councils are implementing a range of local
measures, including planned savings of one per cent of the combined net revenue
budget across services and the use of reserves. All councils increased council tax for
a second consecutive year by an average of 7.7 per cent and collectively expect to
raise more than £1.2 billion through fees and charges for local services. North
Ayrshire Council raised Council tax by 8.5%. 
• Projected reductions in Scottish Government funding over the medium term are
expected to intensify financial pressures and increase the risk of councils becoming
financially unsustainable, unless they stop, reduce or significantly redesign services.
Funding for social care, mainly through Integration Joint Boards (IJBs), represents a
high proportion of council spend, with increasing demand for these services, putting
pressure on council budgets. Councils continue to forecast short-term budget gaps to
2028/29 and are considering a wide range of measures to achieve balanced budgets
in future years. As savings options increasingly focus on changes that impact on
services offered to people, effective and consistent consultation with communities will
be essential. North Ayrshire continues to incorporate a community engagement
programme annually as part of the Budget process. 
3. Proposals 
3.1 It is proposed that the Committee notes the key messages within the recent Accounts
Commission briefing. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Accounts Commission briefing highlights the reliance of local government on
Scottish Government grant funding and the need for further action to bridge
anticipated future funding gaps and achieve financial sustainability. North Ayrshire
Council develops medium term financial plans on a three year rolling basis and
agrees annual Revenue, Capital and HRA budgets. The financial sustainability of the
Council is monitored regularly and reported to Cabinet throughout the year.
96

Page 97

Human Resources 
4.2 As part of a sustainable financial strategy the Council continues to actively manage the
size of its workforce. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 Equality impact assessments are carried out for all options identified as part of the
annual budget proposals. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 In addressing the financial challenges which it faces, the Council seeks to minimise
the impact on delivering its key priorities. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Executive Directors are consulted in the development of the Medium and Long term
Financial plans. Extensive community engagement was undertaken as part of the
development of the 2026/27 budget proposals. 
Mark Boyd
Head of Service (Finance) 
97

Page 98

For further information please contact Mark Boyd, Head of Service (Finance), on 01294
324551 or markboyd@north-ayrshire.gov.uk. 
Background Papers
None 
98

Page 99

Prepared by Audit Scotland
June 2026
Bulletin
Local government
budgets 2026/27
99

Page 100

2Local government budgets 2026/27
Contents
Key facts 3
Key messages 5
Commission expectations 7
Introduction 8
1. Scottish Government funding to councils 10
2. Council budgets 15
3. Consulting with communities 31
Appendix 1 35
Appendix 2 36
Accessibility
You can find out more and read this report using assistive
technology on our website www.audit.scot/accessibility.
100

Page 101

3Key facts
Key facts
Local government budgets 2026/27:
£15.7 billion total funding from the Scottish Government
1 per cent real terms increase in funding (revenue and capital)
to councils in 2026/27 compared to 2025/26
2 per cent real terms increase in revenue funding to councils in
2026/27 compared to 2025/26
15 per cent real terms reduction in capital funding to councils in
2026/27 compared to 2025/26
£18.9 billion councils’ approved net revenue budgets 
£5 billion councils’ approved capital budgets (General Fund
£3.5 billion; Housing Revenue Account £1.5 billion)
7.7 per cent average council tax increase (varies between four
and ten per cent across councils) 
£529 million
revenue budget gap identified by councils at time
of setting 2026/27 budgets (around three per cent of
councils’ General Fund revenue budgets)
£4.3 billion
councils’ revenue contributions to Integration 
Joint Boards (IJBs), (around 24 per cent of councils’
General Fund revenue budgets) a real terms
increase of £220 million compared to 2025/26 
101

Page 102

Key facts 4
Budget actions:
£221 million increase to council tax
£17 million increase to income (including fees and charges)
£168 million agreed savings (recurring)
£12 million agreed savings (non-recurring)
£122 million use of reserves
30 the number of councils that carried out a budget
consultation to inform 2026/27 budget-setting
31 the number of councils that carried out equality
impact assessments as part of budget-setting
102

Page 103

5
Key messages
Key messages
1 Despite a small real terms increase in Scottish Government
funding for 2026/27, councils still face major risks to their
financial sustainability as funding fails to keep pace with rising
demand and increasing costs. Much of the recently baselined
General Revenue Grant funding is still effectively directed
towards specific existing commitments, restricting flexibility.
Councils identified a combined budget gap of around £529
million for 2026/27, representing a gap of around three per cent
of total General Fund revenue budgets across Scotland.
2 A 15 per cent decrease in capital funding is limiting councils’
capacity to sustain and develop infrastructure, resulting in greater
dependence on borrowing and heightened long-term financial
risk. Nevertheless, overall, councils are expanding their capital
budgets for housing, with all councils committing to investment
in new housing for 2026/27.
3 To achieve a balanced budget in 2026/27, councils are
implementing a range of local measures, including planned
savings of one per cent of the combined net revenue budget
across services and the use of reserves. All councils increased
council tax for a second consecutive year by an average of 
7.7 per cent and collectively expect to raise more than 
£1.2 billion through fees and charges for local services.
103

Page 104

Key messages 6
4 Projected reductions in Scottish Government funding over the
medium term are expected to intensify financial pressures and
increase the risk of councils becoming financially unsustainable,
unless they stop, reduce or significantly redesign services.
Funding for social care, mainly through Integration Joint Boards
(IJBs), represents a high proportion of council spend, with
increasing demand for these services, putting pressure on
council budgets. Councils continue to forecast short-term budget
gaps to 2028/29 and are considering a wide range of measures
to achieve balanced budgets in future years. As savings options
increasingly focus on changes that impact on services offered to
people, effective and consistent consultation with communities
will be essential.
104

Page 105

7Commission expectations
Commission expectations
This is our third bulletin on council budgets. Within our
previous bulletins we acknowledged variation in how budgets
are presented and set out a range of expectations relating to
the transparency of council budget papers.
There has been good progress against most of the
expectations set out in Local government budgets
2025/26 (Appendix 2). However, further improvements
could be made in the transparency of budget papers and the
financial monitoring provided to elected members, and how
communities are consulted about budget decisions.
With financial pressures forecast to remain, and the continued
need to identify savings through stopping, reducing and
redesigning services to address these, it is more important
than ever for budget-setting to be clear and well managed.
The decisions taken by councils when setting their budgets
impact us all. Without clear and transparent reporting,
however, it is difficult for elected members and communities
to fully engage and participate in making these decisions.
We have therefore set out the commission’s expectations 
for councils’ annual budget-setting as a checklist (Supplement)
for elected members in order to assist them when making
decisions on setting budgets.
105

Page 106

8Introduction
Introduction
1. Audit Scotland has prepared this budget bulletin on behalf of the
Accounts Commission to summarise key issues arising from our analysis
of the 2026/27 budgets recently agreed by Scotland’s 32 councils.
2. Councils are legally required to set a balanced budget for each
upcoming financial year. This means that a council’s funding and income
must cover their anticipated expenditure. Councils might identify a
budget gap as they are preparing their budgets. This is the difference
between their anticipated expenditure for the year and the funding and
income they expect to receive. Councils will identify and agree actions,
including savings measures or using reserves, to allow them to set a
balanced budget.
3. The wide range of approaches councils take to budget-setting and
the level of information, and the way that it is publicly reported, make it
challenging to report a definitive national position. Some of the variation
between councils is due to differing approaches to budgeting. We have
added caveats to the exhibits and text where caution is required.
4. This report is in three parts:
• Part 1 outlines the Scottish Government’s 2026/27 funding
allocation to councils and highlights trends in revenue and capital
settlements compared with previous years.
• Part 2 assesses how councils have balanced their 2026/27
budgets, including the use of reserves and other measures. This
is based on data returns submitted to us by all councils in March
and April 2026, shortly after agreeing their 2026/27 budgets. We
welcomed the positive engagement from councils and auditors in
completing and returning their data return.
• Part 3 reviews how councils engaged with stakeholders and
considered equality impacts when making budget decisions.
5. As part of the data return, we asked councils to identify the
assumptions they made when calculating projected revenue budget 
gaps over the short term. As expected, these assumptions varied across
the country and across a range of factors although there are no 
identified outliers.
106

Page 107

Introduction 9
6. This year’s budget bulletin provides increased emphasis on:
• the impact that challenging capital settlements have on councils’
ability to invest in local infrastructure
• the level of savings required by Integration Joint Boards (IJBs) in
setting their 2026/27 budgets, including the proportion that relates
specifically to social care services and the impact this has on
council budgets
• the share of council’s capital budgets that sits within the Housing
Revenue Account (if applicable), where that money comes from,
and planned expenditure.
7. When looking at trends, we convert some financial data into real
terms, adjusting it for inflation to make trend information comparable. We
have used the March 2026 deflators published by HM Treasury to adjust
financial information from past or future years into 2026/27 prices.
8. The report is part of a series of overview outputs produced for
the Accounts Commission. These reports provide an independent
overview of the financial and operational performance of Scotland’s local
government sector. The next reports will be our annual financial bulletins
on councils, and IJBs, assessing their financial performance in the most
recently audited financial year.
107

Page 108

10
1.
1. Scottish Government funding to councils
1. Scottish Government
funding to councils
Overall Scottish Government funding to councils is
increasing slightly, in real terms, in 2026/27 compared to
last year. However, rising demand and a significantly lower
capital allocation in 2026/27 will continue to challenge
councils’ financial sustainability if they continue to operate
under the current model of service delivery.
Total Scottish Government funding to councils is
increasing slightly in 2026/27
9. The Scottish Government will provide a total of £15.7 billion of funding
(revenue and capital) to local government in 2026/27 (Exhibit 1), a one
per cent real terms increase compared to 2025/26.
10. The funding going to councils will likely change throughout the year 
as the Scottish Government reprioritises resources from other portfolios
to local government or additional funding becomes available. For
example, councils received £177 million of additional funding during
2025/26, confirmed through the autumn and spring budget revisions. 
It is therefore likely that the 2026/27 budget to local government will 
also change.
Exhibit 1. 
Scottish Budget initial local government settlement 2024/25 to 2026/27
Overall Scottish Government funding to local government is increasing in 2026/27
despite a reduction in the capital settlement.
Cash terms (£ million) Real terms (£ million)
2024/25 2025/26 2026/27 2024/25 2025/26 2026/27
Total local government
funding 13,913 15,165 15,687 14,652 15,469 15,687
Total revenue funding 13,257 14,397 15,018 13,961 14,686 15,018
Total capital funding 656 767 669 691 783 669
Note: Real terms funding has been adjusted into 2026/27 prices using March 2026 GDP deflators.
Source: Analysis of Scottish Government Finance Circulars
The Scottish
Government adjusts its
budget during the year.
This generally takes
place during the annual
autumn and spring
budget revisions
which are approved by
the Scottish Parliament
and may include
allocating additional
funding for specific
purposes, as well as in-
year transfers between
spending portfolios.
108

Page 109

1. Scottish Government funding to councils 11
Revenue funding to all councils is increasing 
in 2026/27
11. The finance circular outlines the revenue and capital funding
that councils will receive from the Scottish Government in
2026/27. Revenue funding contributes to the day-to-day costs
incurred by councils, such as employing staff. The Scottish
Government is allocating £15 billion of revenue funding to local
government in 2026/27, a real terms increase of £331 million
(two per cent) from last year (Exhibit 2, page 12). All councils will
receive a real and cash terms increase in revenue funding from
the Scottish Government in 2026/27.
12. The settlement differs from the figures presented in the
draft Scottish Budget due to changes made prior to it receiving
parliamentary approval. For example, the Scottish Government
provided councils with £20 million of additional funding to
support the Real Living Wage across adult and children’s social
care and early learning and childcare.
While baselining additional funding into the
GRG is intended to enhance councils’ financial
flexibility and align with national commitments
to reduce ring-fencing, much of this funding
remains directed towards specific policies 
and priorities
13. In recent years, there has been a significant increase in the 
General Revenue Grant (GRG) provided to councils, reflecting
the Scottish Government’s decision to baseline several,
previously ring-fenced, grants. Our Supplement to the Financial
bulletin 2024/25 sets out the funds baselined into the GRG.
Between 2024/25 and 2026/27, the GRG has increased in real
terms by £869 million (eight per cent). There has been a modest
increase in GRG funding to councils over the last year, with a
real terms increase of £89 million (0.8 per cent). Over the same
period, specific revenue grants, which are ring-fenced by the
Scottish Government, have reduced by over 20 per cent 
(£56 million).
14. The Scottish Government states that increasing GRG
funding supports the goals of the Verity House Agreement to
lessen ring-fenced funds. However, much of the new funding
is required to meet existing commitments, such as £244 million
of the total £770 million in 2026/27 allocated for teacher pay
increases. Councils must continue using GRG funding for these
obligations, limiting flexibility in spending plans.
The General Revenue Grant
(GRG) is funding provided by the
Scottish Government to help
councils finance their general
services. Unlike specific revenue
grants, GRG is typically not ring-
fenced for specific purposes,
providing councils with a degree
of flexibility over how to allocate
this funding. However, the
Scottish Government directs
councils to spend some GRG
funding on national policy
initiatives, and those expectations
are generally agreed with the
Convention of Scottish Local
Authorities (COSLA). Though
not formally ring-fenced, the
Scottish Government provides
this funding with an expectation
that councils will spend it on
specific services.
The GRG allocation to councils
is based on factors such as
deprivation, levels of rurality
and population size. It is also
based on individual funding
formulas assigned to a particular
local service area. The formula
used to determine the funding
allocation depends on the
specific circumstances for
that service area. This allows
the Scottish Government to
calculate each council’s share
of the GRG. The Scottish
Government jointly agrees the
methodology of distributing
funding to councils with COSLA
which requires regular review.
Scottish Government adjusts
the allocation to each council
as part of the agreed funding
methodology to recognise that
the indicators used, for example,
population size, may lead to
significant annual reductions or
increases for some. The floor
restricts the scale of any grant
increase or reduction within a
set parameter to reduce the
impact in any one financial year.
109

Page 110

1. Scottish Government funding to councils 12
Note: Prior years have been adjusted into 2026/27 prices using the March 2026 GDP deflators.
Source: Analysis of Scottish Government Finance Circulars
Exhibit 2. 
Scottish Government revenue allocation to local government in real 
terms 2024/25 to 2026/27
All councils are receiving an increase in their revenue allocation in 2026/27.
Recent property revaluations are driving a
significant increase in councils’ non-domestic
rates income
15. An increase in non-domestic rates (NDR) income is driving the
overall increase in revenue funding in 2026/27. Funding to councils 
arising from non-domestic rates income is increasing in real terms
by £298 million (nine per cent) between 2025/26 and 2026/27.
This partly reflects the impact of the new non-domestic property
revaluation taking effect from 1 April 2026, which is expected
to result in a higher aggregate NDR yield in the first year of the
revaluation cycle.
16. The Scottish Government takes account of the estimated
income that councils expect to receive in council tax and NDR
income when determining the final GRG allocation to councils.
A significantly reduced capital settlement from
the Scottish Government is making it harder for
councils to invest in local infrastructure
17. Councils use capital funding to buy, maintain or improve assets
such as buildings, general infrastructure and equipment. The
Scottish Government is allocating £669 million of capital funding to
local government in 2026/27, a 15 per cent (£114 million) real terms
reduction compared to last year (Exhibit 3, page 13).
Non-domestic rates
(NDR) are a tax on
businesses and other non-
domestic properties which
helps to fund local services.
The Scottish Government
sets the rate of tax, councils
collect the money, and
the Scottish Government
redistributes it as part of
its funding allocations to
councils. 
The independent Scottish
Assessors calculate the
rateable value of every
non-domestic property
every three years. The
2026 revaluation increased
the rateable value on a
significant number of
non-domestic properties,
including council-owned
buildings. The Scottish
Government has announced
a package of support to help
those affected by increases
in NDR.
£3.2bn £3.2bn £3.5bn
£0.3bn £0.3bn £0.2bn
£10.5bn £11.2bn £11.3bn
General Revenue Grant
Non-Domestic Rates
Specific Revenue Grants
2024/25 2025/26 2026/27
110

Page 111

1. Scottish Government funding to councils 13
18. Twenty-eight councils are receiving a lower capital allocation in
2026/27 compared to the previous year. This impacts on their ability to
invest in local infrastructure, including increasing the pressures on future
revenue budgets (paragraph 57).
19. The Scottish Government and COSLA also use a needs-based
formula to distribute the capital allocation to councils, which is more
variable year-to-year than revenue funding. The General Capital Grant is
distributed based largely on population size and road-length with councils
choosing which projects to fund. Specific Capital Grants are intended to
fund specific national policy priorities.
20. A reduction in the core capital allocation increases the financial
sustainability pressures facing councils and the need for greater and 
more focused capital planning, including:
• Councils increasing their borrowing to fund capital projects.
Borrowing costs, like interest payments, must be met from
councils’ revenue budgets, increasing the pressures further.
• Councils delaying vital investment in local assets. This means 
local assets deteriorate further or councils are forced to close 
them completely.
Exhibit 3. 
Scottish Budget local government capital settlement in real terms
2024/25 to 2026/27
Councils are receiving a lower capital allocation from the Scottish Government in
2026/27 compared to the last two years.
Note: Prior years have been adjusted into 2026/27 prices using the March 2026 GDP deflators.
Source: Analysis of Scottish Government Finance Circulars
£563m £569m£656m
£128m £100m
£126m
2024/25 2025/26 2026/27
General Capital Grant
Specific Capital Grants
111

Page 112

1. Scottish Government funding to councils 14
• A lack of investment in key local infrastructure impacting on wider
outcomes, such as community health and wellbeing.
• A requirement to review existing capital plans to ensure their
affordability under existing pressures.
Further reductions in Scottish Government funding
over the medium term will heighten the risk of
councils becoming financially unsustainable
21. Alongside the draft 2026/27 budget, the Scottish Government
published the Scottish Spending Review, which sets out indicative
multi-year spending plans from 2026/27 to 2028/29 (and to 2029/30 for
capital). This is a projected level of spend rather than a final settlement
and does not provide a council-level breakdown of funding. As such,
there is a lack of information which could provide councils with sufficient
information to assist in effective medium-term financial planning.
22. The Scottish Spending Review projects that revenue funding for
councils will decline in real terms by £528 million (four per cent) between
2026/27 and 2028/29. Councils will therefore continue to face significant
challenges including where to stop, reduce or significantly redesign
services in order to remain financially sustainable, as demand rises and
costs increase while projected funding falls, as set out in our Local
government in Scotland: Financial bulletin 2024/25.
23. The Scottish Spending Review also shows that the capital pressures
facing councils are set to continue. Capital funding from the Scottish
Government to councils is expected to decrease in real terms by 
£28 million (four per cent) from 2026/27 to 2029/30. This reduction 
will impact on councils’ ability to invest in infrastructure projects, such 
as building new schools. Councils will need to assess how the projected
reduction in their capital settlement, together with cost increases, will
affect their longer-term infrastructure strategies.
112

Page 113

152. Council budgets
2. Council budgets
Rising demand and increasing costs mean that councils 
are continuing to face growing financial challenges.
Councils are using reserves, savings, borrowing and
increases in council tax to manage shortfalls.
Councils’ General Fund revenue budget for 2026/27 has
increased since 2025/26
24. Each year, councils set a revenue budget to cover the costs of providing
services and other expenses for the upcoming year. They are required to
ensure that this revenue budget is balanced annually. For 2026/27, councils
reported a General Fund revenue budget of around £18.9 billion, increasing
from around £18.3 billion in 2025/26 (in real terms). While this is an increase
in available budget for councils in the coming year, this sits alongside the
challenging context of Scotland’s public finances. There is a rising demand
for services provided by councils, increased costs and inflation putting
pressure on budgets despite the increase in funding.
25. Most General Fund revenue funding comes from the Scottish Government,
with 60 per cent from the GRG. The remaining revenue funding for councils
comes from a number of sources including NDR, council tax, use of reserves
and other grants and funding from the Scottish and UK governments (Exhibit 4).
Exhibit 4. 
Sources of funding for councils’ 2026/27 General Fund revenue budgets
Source: Council data returns
0 2 4 6 8 10 12
General Revenue Grant
Non-domestic rates
Council tax
Reserves
Other grants, funding
and income 0.9%
0.9%
20.1%
18.4%
59.7%
£ billion
113

Page 114

2. Council budgets 16
IJB funding is a major pressure on councils’ revenue
budgets
26. IJBs receive annual funding from their council and NHS board
partners to deliver local health and social care services. Councils 
are allocating £4.3 billion of revenue funding to IJBs in 2026/27. 
This represents around 24 per cent of the combined 2026/27 revenue
budgets for all councils (excluding Highland who currently operates a
lead agency model) and a £220 million real terms increase since last
year. Three councils are allocating 30 per cent or more of their revenue
budgets to IJBs in 2026/27.
27. The Accounts Commission’s Integration Joint Boards: Financial
bulletin 2024/25 highlights the critical financial pressures facing IJBs.
Twenty councils were able to provide information on savings required
by IJBs in 2026/27, showing that the financial pressures are continuing.
Overall, those IJBs are expected to deliver £179 million of savings in
2026/27, £103 million within social care services (57 per cent of all
savings required by IJBs).
28. The Integration Joint Boards: Financial bulletin 2024/25 also
highlights that reserve levels continue to fall across IJBs, with the total
level of reserves held by IJBs now lower than the budget gap forecast
for the year ahead. While several councils have sought to address health
and social care pressures through additional uplifts to the IJB, they are
acknowledging this only provides short-term stability. Councils are largely
recognising that if IJBs cannot contain financial pressures, then additional
funding may be sought from partners during the financial year, which
could lead to councils making further saving measures.
29. Individual IJBs are acting in response to the significant financial
pressures accumulating from rising demand and constrained funding
settlements, for example:
• Perth and Kinross IJB approved a Financial Recovery Plan for
2025/26 to manage in-year pressures, mainly through the use of
council reserves. While some measures continue, the 2026/27 plan
focuses on sustainable service redesign. This comes alongside
significant savings already delivered and ongoing financial pressures,
with recognition that further measures may risk reduced access 
to care.
• North Ayrshire Council has moved to a ‘critical only’ threshold for
funded adult social care support, meaning only those at critical risk
will receive support. The change follows severe financial pressures,
with rising demand and increasing care delivery costs not matched
by available funding.
114

Page 115

2. Council budgets 17
At the time of setting their 2026/27 budget, almost
all councils reported a budget gap
30. Where councils are reporting that their spending across the year
will be greater than their available income, we refer to this as a budget
gap. The budget gap is the difference between anticipated income
(not including income drawn from council reserves) and anticipated
expenditure (taking into account any savings approved before the
2026/27 budget process began).
31. At the time of setting their budgets, councils identified a combined
budget gap of £528.6 million, representing a gap of around three per
cent of councils’ total combined General Fund revenue budgets for
2026/27. This proportion has remained broadly consistent over the last
seven years. Exhibit 5, (page 18) sets out the budget gaps for individual
councils as a percentage of their individual revenue budgets.
115

Page 116

2. Council budgets 18
Exhibit 5. 
2026/27 budget gap in each council, as a percentage of their General Fund
revenue budget (gap in £ millions shown in brackets)
Note: Shetland and Orkney hold significant reserves related to oil and gas harbour activity. They are
excluded from this chart as they are outliers due to their planned use of reserves to balance the budget.
At the time of setting its budget, South Lanarkshire reported a surplus position. There are differences
in the way councils approach and present their budget and identify budget gaps, including when saving
measures and other actions are agreed. This means that comparisons should be made with caution.
Source: Council data returns
-1% 0% 1% 2% 3% 4% 5% 6% 7%
South Lanarkshire (-£1.5m)
Fife (£3.6m)
Renfrewshire (£5.0m)
East Lothian (£3.5m)
Dundee City (£5.0m)
Inverclyde (£4.0m)
Aberdeen City (£11.0m)
North Lanarkshire (£19.3m)
City of Edinburgh (£27.9m)
East Ayrshire (£9.5m)
Aberdeenshire (£19.2m)
East Renfrewshire (£8.7m)
Dumfries and Galloway (£12.5m)
Highland (£23.4m)
Falkirk (£14.5m)
West Lothian (£20.2m)
Moray (£10.6m)
Stirling (£11.4m)
Eilean Siar (£5.0m)
Angus (£13.9m)
North Ayrshire (£17.8m)
Clackmannanshire (£7.0m)
Glasgow City (£86.7m)
Perth and Kinross (£20.7m)
Scottish Borders (£16.3m)
Midlothian (£13.3m)
Argyll and Bute (£14.9m)
West Dunbartonshire (£15.9m)
South Ayrshire (£20.7m)
East Dunbartonshire (£23.7m)
Councils
116

Page 117

2. Council budgets 19
Councils are taking various actions to close their
2026/27 budget gaps
32. Each council is required to set a balanced budget, so any identified budget
gap must be addressed via a series of measures when the council agrees its
budget. Councils can use a range of tools to help balance their budgets, either
by generating additional income or by reducing expenditure. Actions include
increasing council tax rates, increasing fees and charges, identifying new
saving opportunities and drawing on council reserves (Exhibit 6).
33. Budgets may also include measures to fund additional investment or to
increase reserves. At the time of setting their budgets, councils approved
measures of around £626.4 million to meet the £528.6 million budget gap
and to fund £97.8 million of revenue investment.
34. Councils should prioritise recurring measures that deliver long-term
savings, such as redesigning services or increasing annual income through
changes to council tax. Non-recurring measures, such as delaying expenditure
or leaving posts temporarily vacant, are short term and cannot sustainably
close a budget gap. Any gap covered by these one-off actions will reappear in
future years, and therefore should be addressed through recurring measures.
Exhibit 6. 
Councils’ bridging actions in their 2026/27 budgets
Councils are taking various actions to close their 2026/27 budget gap and fund
additional investment.
0 50 100 150 200 250
Other recurring actions
Other non-recurring actions
Non-recurring savings
Increase to income
Use of reserves
Recurring savings
Increase to council tax
rates/base
£ million
1.8%
2.7%
5.4%
8.5%
19.4%
26.8%
35.2%
Note: Other non-recurring actions mainly relate to measures being taken by Glasgow City Council 
to address homelessness pressures. Percentages do not sum to 100 per cent due to rounding.
Source: Council data returns
117

Page 118

2. Council budgets 20
Councils continue to rely on identified savings across
different service areas to address financial challenges
35. All councils have identified the service areas where they expect 
to make savings when setting their 2026/27 budgets, where previously
some councils had savings that were unidentified. Although this
represents appropriate financial planning at the time of setting the budget,
councils may still need to identify further saving measures if unforeseen
in-year pressures arise.
36. Councils are planning £179.6 million worth of saving measures through
2026/27 budgets, representing one per cent of the General Fund revenue
budget for all councils. Around £168.1 million are recurring savings with
£11.5 million of non-recurring savings identified. Increasing the share of
recurring savings is important for ongoing financial management as it
provides a more reliable financial base going forward.
37. At the time of budget-setting, South Ayrshire Council planned the
largest level of savings as a proportion of its 2026/27 total General
Fund revenue budget. The council plans to deliver recurring savings of
£9.4 million in 2026/27, representing around 2.4 per cent of its 2026/27
General Fund revenue budget. Most of these savings are within corporate
functions and environmental services, particularly through changes to
waste management services.
38. Statutory services, like education and social work services, limits
councils’ ability to reduce spending in these areas, with savings more
common within non-statutory services. Corporate services have the
most individual saving measures across all councils, amounting to around
£66.7 million, representing over a third of the total value of all 2026/27
saving measures. Around 74 individual saving measures are within culture
and leisure, economic development and environmental services. This
represents around £46.6 million of saving measures.
39. Our recently published report Delivering for the future –
Transformation: How councils are redesigning and delivering more
efficient services set out the need for sustainable change through
transformation of services, presenting a mixed picture of how well
councils are doing this.
All councils increased their council tax rates in
2026/27
40. Councils had full flexibility in 2026/27 to determine their council tax
levels. All councils increased their council tax rates in 2026/27, with
increases ranging from four per cent in City of Edinburgh Council to ten
per cent in Aberdeenshire and Moray councils (Exhibit 7, page 21).
118

Page 119

2. Council budgets 21
Source: Council data returns and Scottish Government Council Tax documents
Exhibit 7. 
Band D Council Tax rates in each council, 2024/25 – 2026/27
Council Tax rates increased between four and ten per cent in 2026/27.
0 200 400 600 800 1,000 1,200 1,400 1,600 1,800
Shetland Islands
Eilean Siar
South Lanarkshire
Angus
North Lanarkshire
Dumfries and Galloway
Scottish Borders
Falkirk
Orkney Islands
Fife
West Lothian
Aberdeenshire
West Dunbartonshire
Perth and Kinross
Clackmannanshire
East Renfrewshire
East Dunbartonshire
Highland
Inverclyde
Moray
East Lothian
Renfrewshire
City of Edinburgh
North Ayrshire
South Ayrshire
Argyll and Bute
Stirling
Dundee City
East Ayrshire
Aberdeen City
Glasgow City
Midlothian
£
Councils
2024/25 Council Tax (Band D) 2025/26 increase 2026/27 increase
119

Page 120

2. Council budgets 22
41. In total, councils expect to receive £248 million from increases to
council tax in 2026/27. The income individual councils expect to raise
from council tax depends on several local factors, such as the scale of the
increase, the size of the council area, and the nature of the local housing
stock, as well as local demand and priorities.
42. Councils have different council tax baselines, calculated using the
number of homes in the area, converted to the equivalent number of
homes in band D. For 2026/27, Aberdeen City Council agreed a 6.8 per
cent increase, bringing its band D council tax charge to £1,747, while
Aberdeenshire Council approved a ten per cent increase, resulting in a
band D charge of £1,686. Councils such as Aberdeen City, with a higher
value baseline, will therefore raise more income for each one per cent
increase. Overall, there is a 23.7 per cent difference between the lowest
(£1,468) and highest (£1,816) band D rates in Scotland.
43. The Council Tax Reduction (CTR) scheme provides support to a range
of claimants, recognising that council tax increases disproportionately
impact lower income households. Among the council areas with the
highest levels of deprivation, Glasgow City Council applied one of the
lowest council tax increases in 2026/27, at 5.9 per cent. Increases in
Dundee City, West Dunbartonshire and Inverclyde councils were close to
the national average increase of 7.7 per cent. North Ayrshire exceeded the
average, with an increase of 8.5 per cent.
44. Our 2025/26 budget bulletin reported significant increases in local
council tax rates. Overall, percentage increases were lower in 2026/27
than in 2025/26, but cumulative two-year increases across Scotland range
from 12.3 per cent in City of Edinburgh Council to 25.8 per cent in Falkirk
Council. The average cumulative council tax increase over the last two
years is 18 per cent. There is no clear link between council size and the
level of council tax increase. For example, Glasgow City Council, with the
largest population, has approved a cumulative increase of 13.8 per cent,
while Shetland Islands Council, which has one of the smallest populations
and the second lowest Band D rate (Exhibit 7, page 21), has approved an
18 per cent increase, reflecting the national average.
45. Councils also now have the power to set the amount of an additional
premium on the council tax rate for empty properties and second homes.
Several councils plan to make use of the new power in 2026/27.
Councils anticipate raising over £1 billion in 2026/27
from charging to access certain local services
46. Councils also generate income from the fees and charges they set
for using certain services. For example, councils will charge for accessing
local leisure facilities, like swimming pools, or collecting certain 
household waste.
Council tax makes
up a relatively small
proportion of a
council’s total revenue
budget, representing
around 20 per cent 
of overall council 
income in 2026/27. 
A percentage increase
in council tax does
not result in an
equivalent percentage
increase in a council’s
total budget. For
example, if council
tax represents 20 per
cent of a council’s
income, a ten per cent
increase in council tax
results in only a two
per cent increase in
the council’s overall
funding. This is often
referred to as the
council tax gearing
effect.
120

Page 121

2. Council budgets 23
47. Thirty-one councils provided information about the income they expect
to receive from fees and charges in 2026/27. Councils expect to receive
£1.2 billion from fees and charges in 2026/27, representing around 6.7 per
cent of the combined revenue budgets. Income from fees and charges in
2026/27 is largely equivalent to the estimated income received by councils
from fees and charges in 2025/26.
48. All councils will increase fees and charges in 2026/27, with the largest
percentage rises concentrated in environmental services. The Accounts
Commission’s spotlight report on culture and leisure services highlights
councils’ increasing reliance on charging individuals to access services.
It also highlights inconsistencies in how these charges impact different
groups.
49. Seventeen councils are introducing new fees and charges in
2026/27. These are mostly within environmental services and economic
development and planning. Three councils are removing certain fees and
charges in 2026/27.
50. During the 2026/27 budget cycle, six councils approved tighter
eligibility criteria for certain services, including introducing different
charging policies for certain users of services. For example, in one council
non-residents will face higher charges for accessing bereavement services
compared to those living in the area.
51. Across a sample of budget consultations, there is evidence that
some councils are clearly communicating that fees and charges may
be increased or amended as part of addressing identified budget gaps.
Consultations typically outline the need for savings, income generation
and service changes, and invite residents to comment on proposed
options before decisions are made.
Councils are continuing to use reserves to balance
their budgets
52. As previously set out by the Accounts Commission (Local
government budgets 2025/26), councils’ continued use of reserves
to balance budget pressures is not sustainable. At the end of 2025/26,
councils estimated a total of £2.6 billion in their General Fund, a usable
reserve, with £2 billion committed. Of this total amount held in the
General Fund, £0.17 billion (seven per cent) was specifically earmarked 
for contingency.
121

Page 122

2. Council budgets 24
53. When setting 2026/27 budgets, councils approved the use of 
£0.19 billion of General Fund reserves. Councils are generally using
reserves to manage short-term financial pressures rather than to support
ongoing expenditure. For example, reserves are being used to fund
specific non-recurring pressures, one-off investment, as well as planned
use of service concession flexibility. Some councils have included the use
of reserves as a short-term measure within their budget strategies to 
enable efficiency measures or transformational change.
54. While some councils are using reserves on a one-off basis to manage
short-term financial pressures, all acknowledge that using reserves to fund
budget gaps is not sustainable in the long term, and that reserves must
be managed carefully to ensure minimum uncommitted reserve levels 
are maintained.
Reductions in Scottish Government capital
funding are increasing council borrowing and risk
exacerbating financial sustainability pressures
55. Councils use their capital budgets to fund local infrastructure projects,
like building new schools. The significant capital pressures facing councils
are making it difficult to invest in local infrastructure. The impact from
reduced capital funding from the Scottish Government is exacerbated by
the inflationary pressures making infrastructure projects more expensive.
These pressures are set to continue as capital funding from the Scottish
Government is expected to reduce further with high inflation continuing 
to impact on the cost of projects (paragraph 23).
56. The funding of capital budgets comes from a variety of sources
(Exhibit 8, page 26). The total General Fund capital budget for all 
councils in 2026/27 is £3.5 billion, representing a real terms increase 
of £0.30 billion (9.3 per cent) over the last year. However, 14 councils 
are reducing their General Fund capital budgets in 2026/27.
57. Borrowing is the main way that councils fund capital projects,
representing around 71 per cent of all General Fund capital funding in
2026/27. Councils intend to borrow £2.48 billion in 2026/27 to fund local
infrastructure projects, a real terms increase of £0.41 billion from the
previous year. The Accounts Commission’s 2024/25 Financial bulletin 
on councils explains how councils are relying more on borrowing to
finance projects with debt repayment costs putting pressure on future
revenue budgets.
122

Page 123

2. Council budgets 25
58. Four councils say they are planning an innovative approach to fund
local infrastructure projects in 2026/27, including:
• Angus Council set aside £0.75 million as part of its 2026/27 council
tax increase to cover loan repayments and interest. This increases
the council’s ability to borrow money for capital investment with an
additional £16 million of spending planned through an Angus Public
Infrastructure Fund.
• South Lanarkshire Council is investing £2 million to cover the
upfront costs of creating commercial spaces for local organisations.
This funding allows the council to access more than £11 million of
total investment in commercial properties, which will be paid for
over time through rental income. 
All councils that own housing are investing in new
builds
59. Twenty-six councils own and maintain council housing. Councils
are required to have a Housing Revenue Account (HRA) to record all
income and expenditure for the direct provision of housing services.
Councils are committing a combined £1.5 billion from their capital budgets
to the HRA in 2026/27, a £20.8 million (1.4 per cent) real terms increase
compared to the previous year. Despite this, nine councils are reducing
capital funding to their HRA in 2026/27.
60. Borrowing is the major source of finance for councils’ HRA capital
budgets, accounting for around 74 per cent in 2026/27. This is a slightly
higher proportion than in 2025/26. Higher borrowing increases the
pressures on future HRA revenue budgets because councils must set
aside funding to cover debt repayment costs.
61. HRA funding allows councils to progress their local housing priorities.
• All councils with an HRA are planning expenditure on new builds
in 2026/27. Councils expect to spend £0.66 billion on new housing
this year, a real terms increase of £74.5 million (12.8 per cent)
compared to 2025/26.
• Councils are planning to increase spending in real terms on
refurbishment and repair and maintenance costs by £23.1 million
(3.1 per cent) between 2025/26 and 2026/27.
• Councils are also planning around £113 million in other areas of
expenditure, such as buying back former council housing.
62. The Auditor General and Accounts Commission are undertaking
a report on housing services across Scotland. This report is due for
publication in early 2027.
The Housing
Revenue Account
(HRA) is a ring-fenced
account relating
to local authority
housing. The HRA
is intended to record
expenditure and
income on running a
council’s own housing
stock and closely
related services or
facilities, which are
provided primarily
for the benefit of the
council’s own tenants.
123

Page 124

2. Council budgets 26
Exhibit 8. 
Sources of capital budgets for 2025/26 and 2026/27
Borrowing is the main way that councils fund capital projects.
0.0 0.5 1.0 1.5 2.0 2.5
Other
Developer contributions
Capital receipts
Internal revenue funding
Specific Capital Grants
General Capital Grants
Borrowing
£ billion
2025/26 2026/27
1.9%
5.3%
3.3%
2.4%
2.6%
2.5%
2.4%
2.0%
7.0%
6.9%
64.4%
70.6%
16.4%
General Fund
12.3%
0.0 0.25 0.50 0.75 1.0 1.25
Other
Developer contributions
Capital receipts
Internal revenue funding
Specific Capital Grants
General Capital Grants
Borrowing
£ billion
2025/26 2026/27
0.1%
4.4%
2.1%
0.1%
2.8%
2.2%
71.8%
1.4%
2.2%
HRA
73.9%
10.2%
10.8%
9.3%
8.8%
Note: Figures for 2025/26 have been adjusted into 2026/27 prices using the March 2026 GDP deflators.
Capital receipts are income councils generate from selling existing assets.
Source: Council data returns
124

Page 125

2. Council budgets 27
Councils are considering a range of issues to set
balanced budgets in the future
63. Councils are anticipating that funding pressures will continue in the
medium term, reflecting projected spending levels set out in the Scottish
Spending Review (paragraph 22). In projecting future revenue budget
gaps, councils have considered and made assumptions about a range of
funding and cost pressures (Exhibit 9, page 28).
125

Page 126

2. Council budgets 28
Exhibit 9. 
Factors considered by councils when projecting future revenue 
budget gaps
Source: Council data returns
Considerations
Pay
settlements
All councils considered current and future pay settlements, with assumed
increases ranging from two to 3.5 per cent. Around one third of councils
assumed a pay increase of three per cent.
Pension
contributions
Fewer than half of councils considered potential changes to employer pension
contributions. Where these were considered, most councils assumed no
imminent change. The most recent Scottish Local Government Pension Scheme
triennial valuation was undertaken in March 2026 and will set contribution rates
from 1 April 2027 onwards.
Inflation Most councils took account of general and service specific inflationary pressures,
particularly in relation to contracts and energy or wider utility costs.
Demand More than two-thirds of councils factored in service demand, with some
assuming increased demand in future years. While the scale varied across
councils, many highlighted growing pressures in social care, homelessness 
and Additional Support Needs.
Council Tax More than two-thirds of councils considered future changes to council tax rates.
Of these, around half assumed increases ranging from two to ten per cent in
2027/28, and from one to seven per cent in 2028/29. Some anticipated higher
council tax income due to an increase in the number of taxable properties.
Non-Domestic
Rates
Approximately one-third of councils considered potential changes to Non Domestic
Rates (NDR). Some councils that did not factor in changes noted that NDR decisions
are determined by the Scottish Government and are therefore outside local control.
Fees & charges More than two-thirds of councils considered changes to fees and charges. Some
councils applied inflationary uplifts, typically between two and six per cent, while
others assumed no increases.
Borrowing /
debt
Most councils considered the cost of borrowing and debt servicing, based
on expected loan repayments, interest rate assumptions and agreed capital
investment plans. These costs are generally incorporated within longer-term
financial plans, with additional borrowing costs reflected in annual budgets.
Reserves More than two-thirds of councils considered their level and use of reserves. Some
assumed little or no use of general fund reserves to balance budgets. Where reserves
are used, councils typically draw on specific earmarked funds and apply controls,
such as spreading the impact over time or restricting use to short-term pressures.
Savings More than half of councils considered the risk of savings plans not being fully
delivered. While councils acknowledged that failure to achieve planned savings
could affect services, most assumed that approved savings would be delivered
in full, or that alternative measures would be identified where necessary.
126

Page 127

2. Council budgets 29
64. We reported in the Local Government: Financial bulletin 2024/25
that a number of earlier Private Finance Initiative (PFI) contracts are
now nearing expiry, with councils actively preparing for, or managing,
complex contract exit arrangements. While councils have not generally
made assumptions about PFI handback implications, a sample review
indicates that councils are considering these risks during budget setting.
This includes keeping money aside to cover unitary charges, and in
some cases, setting aside funds to cover potential property repair and
maintenance costs.
Councils are continuing to forecast budget gaps over
the short term
65. Given the ongoing public sector financial pressures (paragraph 22),
councils are projecting they will continue to have gaps in their revenue
budgets; £486.9 million in 2027/28 and £476.6 million in 2028/29. 
Exhibit 10, (page 30) sets out projected gaps across all councils. There
are differences in the way councils’ approach and present their budget
and identify budget gaps including when saving measures are agreed 
so figures may not be directly comparable.
66. Although some pressures in these forecasts are expected to be
resolved or reduce over time, councils still face a combined revenue gap
of £964 million across the next two years. To bridge this shortfall, they will
need to raise additional income, identify further savings, or rethink how –
and what – services they deliver.
127

Page 128

2. Council budgets 30
Councils
Budget gap
2027/28
£ million
Budget gap
2028/29
£ million
Cumulative gap
to 2028/29
£ million
Cumulative gap
as % of 2026/27
General Fund
revenue budget
Highland 4.8 0.8 5.7 0.7%
West Lothian 11.5 - 11.5 1.8%
South Lanarkshire 9.7 19.5 29.2 2.7%
City of Edinburgh 11.8 31.4 43.2 2.8%
Dundee City 7.8 7.1 15.0 2.9%
Fife 8.5 26.6 35.1 2.9%
Perth and Kinross 5.2 10.6 15.9 3.0%
Falkirk 9.4 5.9 15.3 3.0%
Renfrewshire 4.6 16.2 20.7 3.3%
Moray 2.9 7.4 10.3 3.3%
Angus 5.2 8.6 13.7 3.5%
East Renfrewshire 8.0 5.2 13.2 3.6%
North Ayrshire 9.0 9.2 18.3 3.8%
East Ayrshire 6.0 12.0 18.0 3.9%
South Ayrshire 9.9 6.4 16.3 4.1%
Inverclyde 5.2 6.2 11.5 4.2%
North Lanarkshire 26.0 25.4 51.3 4.3%
Argyll and Bute 10.2 5.6 15.8 4.4%
East Lothian 10.5 8.4 18.9 5.0%
Scottish Borders 11.9 9.8 21.7 5.2%
Dumfries and Galloway 13.9 14.1 28.0 5.4%
Stirling 8.1 10.2 18.3 5.7%
Midlothian 13.5 9.3 22.8 6.7%
Eilean Siar 3.6 6.0 9.6 6.8%
Aberdeen City 30.2 18.5 48.7 7.0%
Glasgow City 95.3 72.0 167.3 7.5%
Clackmannanshire 10.1 3.5 13.6 7.5%
West Dunbartonshire 10.9 14.3 25.2 7.7%
Aberdeenshire 42.4 28.3 70.6 8.2%
East Dunbartonshire 23.1 22.2 45.2 11.8%
Orkney Islands 21.0 23.1 44.1 28.7%
Shetland Islands 36.9 32.8 69.7 37.4%
Scotland 486.9 476.6 963.5 5.1%
Exhibit 10.
Councils’ projected budget gaps to 2027/28 and 2028/29
The cumulative projected budget gap to 2028/29 is almost £1 billion.
Note: A detailed 2028/29 budget gap is not currently available for West Lothian Council. Shetland and
Orkney hold significant reserves related to oil and gas harbour activity and are outliers due to their use
of these reserves.
Source: Council data returns
128

Page 129

313. Consulting with communities
3. Consulting with
communities
As councils continue to make challenging budget decisions,
they must ensure the communities affected are fairly and
consistently consulted.
While the majority of councils consulted on their
2026/27 budgets, there is variation in how effectively
they are consulting with communities
67. Councils must effectively consult with residents in helping to identify
ways to address their funding pressures. As demand for services grows
and resources become constrained, it is important that councils explain
the difficult decisions they must make, including how public funds are
used to maintain and improve services, and how they are protecting
essential services.
68. Twenty-seven councils consulted with residents on their 2026/27
budget. Most councils consulted clearly with residents on the funding
pressures they are facing and on possible actions to close their budget
gap. Councils commonly sought views on priority areas and presented
savings options and potential income-generation measures to address
financial pressures.
69. There was some variation in how councils consulted on their 2026/27
budgets, but most did so through online public consultations and
surveys. Some councils also used community engagement methods
such as community meetings, roadshows or workshops. Some councils
provided evidence of new ways they undertook engagement as part of
their 2026/27 budget-setting process, examples include:
• South Lanarkshire Council consulted separately with children and
young people on budget proposals. Recognising that the views
of young people are often missed in normal budget consultation
processes.
• Angus Council changed their approach to allow more open
comments on specific services and budget areas, gathering more
in-depth qualitative feedback than before. In addition, QR codes
were added to posters to make it easier for people to access online
surveys directly.
129

Page 130

3. Consulting with communities 32
• Officers and elected members from Scottish Borders Council ran
targeted consultation exercises with community groups and the
public, including within schools, supermarkets and colleges. This
allowed for more face-to-face engagement with people who may
not normally complete online consultations. Facilitated sessions
were also held with groups who are less frequently represented
in formal consultation exercises to ensure their views were also
included. These are often missed in standard consultations.
70. Councils should use a range of methods to engage and consult
with stakeholders, as this helps ensure wider participation in ways
that are accessible and meaningful, including people whose voices are
under-represented, and reduces the risk that any groups or individuals
are excluded. High levels of engagement and participation lead to
better informed decision-making by ensuring a wide range of views
and experiences are considered. Councils also need to ensure they are
transparent, as part of their engagement, about why they have made
decisions, especially when these decisions directly affect communities.
71. Councils should also consult with a wide range of stakeholders on
their budget decisions, allowing them to better understand the impact
decisions have on different groups. There was variation in how councils
consulted with established groups on their 2026/27 budget proposals.
Twenty-nine (of 31) councils engaged with their local IJBs as part of
their budget setting process, and more than half (17) engaged with
Community Planning Partnerships. Other stakeholder groups councils
engaged with include:
• Staff, unions and communities – engagement most commonly
focused on internal stakeholders and local communities, with 26
councils engaging with staff and trade unions, 23 involving tenants
and residents’ associations, and 22 engaging with community
groups.
• Children, young people and families – most councils sought views
from families and young people, with 19 councils engaging with
children and young people (including school pupils) and 16 engaging
with parent councils.
• Business and other stakeholders – 15 councils engaged with the
business community and seven councils engaged with other users
of services or stakeholders, including third-sector partners and
charities such as Women’s Aid.
72. A review of a sample of council budget consultation documents
shows residents expressing strong support towards protecting frontline
services. Residents highlight the importance of protecting education,
social care, children and family services, and libraries, leisure, and wider
community facilities.
130

Page 131

3. Consulting with communities 33
73. Across budget consultations, councils explain that limited and often
ring-fenced funding, especially for statutory services like education and
social care, means that protecting these areas may lead to reductions,
service changes, closures to non-statutory or discretionary services, 
or higher charges elsewhere.
74. Councils included budget proposals that would reduce access to key
local facilities, such as leisure centres or libraries, or lowering educational
or social care support. These proposals were developed during budget
consultations and prior to final funding settlements, reflecting the range
of savings options councils were considering at the time. As funding
settlements were finalised and public consultations considered, there 
are examples of councils scaling back on proposals or abandoning 
them altogether:
• Stirling Council – rejected savings proposals that would have a
greater impact on families and vulnerable groups.
• Inverclyde Council – withdrew plans for savings to libraries,
swimming pools, and community safety teams after feedback 
from residents.
• Argyll and Bute Council – councillors rejected savings proposals that
would have reduced library and leisure services.
• Fife Council – prioritised protecting vital services, supporting
vulnerable residents, and investing in education and anti-poverty
initiatives.
Councils are using Equality Impact Assessments to
understand the effect budget decisions may have on
their communities
75. Public bodies use Equality Impact Assessments (EIAs) to understand
the potential impact from new policies or budget decisions on
individuals with protected characteristics. EIAs help identify ways to
advance equality and highlight potential discrimination. Public bodies
must complete an EIA whenever introducing a new policy or making a
strategic decision that impacts on different groups. Public bodies must
do this early in the process to allow the findings to shape the decision-
making process.
76. Councils must complete an EIA to understand how their budget
decisions may affect groups and communities, particularly those with
protected characteristics under the Equality Act 2010. This becomes
even more important as councils continue to face significant financial
pressures, including reducing services. Thirty-one (of 32) councils carried
out EIAs. The Accounts Commission’s Spotlight on culture and leisure
services found the quality of EIAs varies when councils are making
changes to services that impact on communities.
131

Page 132

3. Consulting with communities 34
77. The Accounts Commission explained within last year’s budget
bulletin its expectations around councils fully and transparently explaining
the impact budget decisions may have on those with a protected
characteristic. This information, including the actions to mitigate potential
discrimination, should be clearly accessible for everyone.
132

Page 133

Appendix 1 35
Appendix 1
Councils’ 2026/27 revenue budgets, budget gaps, approved
savings and other budget measures  
Councils
General Fund
revenue budget
2026/27 
£ million
Budget 
gap 
2026/27
£ million
Approved
savings 
2026/27 
£ million
Other 
measures
2026/27
£ million
Aberdeen City 697.2 11.0 3.5 11.1
Aberdeenshire 866.2 19.2 9.3 10.3
Angus 388.1 13.9 5.3 8.6
Argyll and Bute 362.0 14.9 6.1 8.8
City of Edinburgh 1,534.5 27.9 20.0 31.3
Clackmannanshire 181.2 7.0 3.6 3.4
Dumfries and Galloway 515.8 12.5 4.2 8.3
Dundee City 521.3 5.0 0.8 6.6
East Ayrshire 460.2 9.5 3.5 6.1
East Dunbartonshire 381.8 23.7 4.1 19.6
East Lothian 379.9 3.5 1.4 2.1
East Renfrewshire 363.1 8.7 3.2 5.5
Eilean Siar 140.8 5.0 0.4 4.6
Falkirk 508.4 14.5 10.2 7.1
Fife 1,205.3 3.6 0.1 14.1
Glasgow City 2,233.8 86.7 31.9 71.7
Highland 868.0 23.4 5.4 18.1
Inverclyde 276.6 4.0 0.6 3.5
Midlothian 340.7 13.3 0.6 12.7
Moray 311.7 10.6 4.2 6.3
North Ayrshire 486.1 17.8 0.2 17.5
North Lanarkshire 1,182.6 19.3 9.2 22.0
Orkney Islands 153.3 21.3 0.2 21.1
Perth and Kinross 533.8 20.7 8.8 12.4
Renfrewshire 630.9 5.0 2.4 10.7
Scottish Borders 418.0 16.3 7.6 8.7
Shetland Islands 186.5 43.7 0.0 43.7
South Ayrshire 398.1 20.7 9.4 11.3
South Lanarkshire 1,086.7 -1.5 4.2 11.5
Stirling 323.0 11.4 5.5 6.0
West Dunbartonshire 325.7 15.9 5.4 10.5
West Lothian 634.6 20.2 8.5 11.7
Scotland 18,895.8 528.6 179.6 446.8
Note: The approach councils take to budget setting, defining budget gaps and the measures taken to
address these gaps varies across councils therefore caution should be taken when comparing councils.
In each council, the sum of approved savings and other measures may be greater than the budget
gap; budgets may also include measures to fund additional investment or increase reserves. Approved
savings include both recurring and non-recurring savings. Other measures include increases to council
tax, increases to income, use of reserves and other actions, as set out in Exhibit 6.
133

Page 134

Appendix 2 36
Appendix 2
Progress against the expectations in the Local Government
Budgets 2025/26
Councils should: Progress/ status
In future, we expect to see councils encourage more active participation in the budget-setting
process by ensuring that:
Budget papers and financial monitoring reports
provided to elected members include clear
and understandable headline figures that state
the impact of specific budget decisions on the
overall financial position of the council
Mixed progress
There is mixed progress in how effectively
councils are presenting key financial information in
budgetary reports that are also publicly available.
Budgets should link back to the council’s
corporate plan to allow elected members to
make spending choices better informed by, 
and based upon, the council’s priorities
Progress
Thirty-one councils linked their 2026/27 budget
back to its corporate plan. Linking key financial plans
back to corporate plans ensures that resources
are targeted towards key strategic priorities.
Fundamental information, such as the forecast
budget gap, is clearly presented as part of the
consultation process with residents
Progress
A sample review of budget consultations
indicates most councils clearly identify their
budget gaps, with some also providing detail
over multiple financial years.
Estimated costings of how specific proposals
will contribute to managing the budget gap
are made available to residents, including the
potential contribution of any proposed increase
to council tax and the anticipated impact on
levels of service delivery
Progress
A sample review indicates that most councils
make estimated costings available for proposed
measures, including indicative savings or income
from council tax increases, with high-level
information on the anticipated impact on service
delivery, though the level of detail can vary.
General public consultations are supplemented
by targeted consultations with groups most
impacted by changes to specific services and
that consideration is given to how to encourage
participation
Mixed progress
Thirty councils consulted to some extent on their
2026/27 budget. Most councils consulted with
local IJBs and residents on budget proposals,
but there is a mixed approach in how councils
engaged with targeted groups.
The ongoing impact of budget decisions are
fully assessed, including through Equality Impact
Assessments, to enable elected members to
make informed decisions.
Progress
Thirty-one councils confirmed they carried out
an EQIA on their 2026/27 budgets. EQIAs are
a statutory requirement to ensure decision-
makers are aware of the impact on groups with
a protected characteristic.
134

Page 135

Audit Scotland 4th Floor 102 West Port Edinburgh EH3 9DN
Phone: 0131 625 1500
www.audit.scot
ISBN 978 1 918486 10 0 
Bulletin
Local government
budgets 2026/27
135

Page 136

136

Page 137

NORTH AYRSHIRE COUNCIL 
27 August 2026 
Audit and Scrutiny Committee
Title: National Planning Improvement Framework (NPIF)
Purpose: To advise the Committee of the completion and outcome of the
Planning Service’s National Planning Improvement Framework
(NPIF)
Recommendation: That the Committee notes the completion and outcome of the
National Planning Improvement Framework (NPIF). 
1. Executive Summary
1.1 The National Planning Improvement Framework (NPIF) replaces the former
annually prepared Planning Performance Framework. The NPIF is a four-stage
process and is designed to shift the focus of measuring planning authorities away
from rigid metrics, moving instead toward a collaborative approach that embeds
continuous improvement. 
1.2 The full assessment is provided at Appendix 1, alongside a summary Action Plan at
Appendix 2. The Audit and Scrutiny Committee is invited to note the outcome of the
performance assessment and agree that the NPIF will be used in consultation with
North Ayrshire communities to support accountable and effective service delivery. 
2. Background 
2.1 The Planning (Scotland) Act 2019 introduced a new approach to measuring the
performance of planning authorities. It made it mandatory for planning authorities to
prepare a report on their performance and identify future improvement actions from
2025 onwards. This report is referred to as the National Planning Improvement Plan
(NPIF) and replaces the former Planning Performance Framework (PPF). The NPIF is
prepared annually and requires to be published and submitted to Scottish Ministers. 
2.2 A new role of National Planning Improvement Champion (NPIC) was introduced in the
Act to monitor the performance of planning authorities and provide advice to them, as
considered appropriate, on the steps that might be taken to improve performance by
Agenda Item 10
137

Page 138

planning authorities. The NPIC post is based within the Improvement Service and is
accountable to Scottish Ministers. 
2.3 The NPIF has been developed by the NPIC, and the framework process comprises
the following four stages: 
• Stage 1 - where the planning authority undertakes a self-assessment exercise and
identifies improvement areas
• Stage 2 - an improvement action plan and performance assessment arising from
stage 1 undergoes peer collaborative review
• Stage 3 - the agreed improvement action plan and performance assessment are
provided to Scottish Ministers and the Council’s Chief Executive
• Stage 4 - the NPIF and improvement action plan is published, actioned and
monitored.
2.4 The Council’s Planning Service has recently completed stages 1-3 and will now enter
stage 4. 
2.5 The self-assessment of the Planning Service is attached as Appendix 1 to this report,
providing a full overview of performance and the Improvement Action Plan detailing
the actions to be implemented in the next two years. A copy of the Action Plan is
provided at Appendix 2.
2.6 The NPIF Performance Assessment and Improvement Action Plan has now been
reviewed by the National Planning Improvement Champion, who has confirmed it to
Scottish Ministers and the Council’s Chief Executive. The review of the Planning
Service has been confirmed as “making excellent progress”. This maintains a long
history of service delivery excellence and North Ayrshire’s Planning Service continues
to be one of the top performing services in Scotland. Notwithstanding this, the focus of
the NPIF performance assessment has been on identifying actions to ensure
continuous improvement.
2.7 The key improvement actions identified include: 
• The undertaking of a service review to prepare a workforce planning strategy and
evaluation of resources
• Further identification and evaluation of local, regional and national challenges to
planning to ensure effective service delivery
• A review and update of the Council’s Planning Enforcement Charter
2.8 The NPIF was recently published on the Council’s website and shared with all North
Ayrshire community councils, with their feedback incorporated as noted. The
Improvement Action Plan is therefore in the public domain and open to scrutiny by all
North Ayrshire communities. There will be regular checks by the Planning Service and
the National Planning Improvement Champion on progress. It is also anticipated that
there will be an annual review to evaluate progress against agreed improvement
actions. 
3. Proposals
138

Page 139

3.1 That the Committee notes the completion and outcome of the National Planning
Improvement Framework (NPIF). 
4. Implications/Socio-economic Duty
Financial
4.1 None
Human Resources 
4.2 None 
Legal 
4.3 The legislative requirements for the preparation, submission and registration of NPIFs
are set out in the Town and Country Planning (Scotland) Act 1997 as amended by the
Planning (Scotland) Act 2019. 
Equality/Socio-economic 
4.4 The Council is required to take account of the NPIF in the preparation of North
Ayrshire’s third Local Development Plan (LDP3) which will be the subject of an
equalities impact assessment and assessment on the impact of the plan on children. 
Climate Change and Carbon 
4.5 The Council is required to take account of the NPIF in the preparation of North
Ayrshire’s third Local Development Plan (LDP3) which will be subject of a Strategic
Environmental Assessment. 
Key Priorities 
4.6 Communities and Local Democracy are one of four interlinked and interdependent
priorities set out in the Council Plan (2023-28). The preparation of the NPIF and
consultation on it are a means of enabling local communities to be active in the
preparation of North Ayrshire’s next Local Development Plan and placemaking
approaches. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None.
139

Page 140

Consumer Duty 
4.10 None. 
5. Consultation 
5.1 The NPIF was shared with community councils across North Ayrshire for their review
and feedback, which was then incorporated into the final assessment. 
David W. Hammond
Executive Director (Communities and Housing) 
For further information please contact Allan Finlayson, Chief Planning Officer, on 01294
324319. 
Background Papers
0
140

Page 141

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
National Planning Improvement Framework
(NPIF)
North Ayrshire Council
Performance Assessment 2025/26  March 2026
Cohort 3 
141

Page 142

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
142

Page 143

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Planning Authority: North Ayrshire Council
Lead officer: Allan Finlayson
Email: allaninlayson@north-ayrshire.gov.uk
Phone number: 07500 226257 
North Ayrshire Planning Service
The Planning Service in North Ayrshire, from January 2024, sits within the Housing and
Public Protection Service within the Communities and Housing Directorate. The Chief
Planning Officer heads a team of ten professional planners and four support staff split
between two teams: Development Management and Strategic Planning. 
Our Development Management team continue to deliver sector-leading determination
timescales for planning applications while handling a high number of cases per officer.
The Strategic Planning Team is at a progressed stage and on track in the preparation of
North Ayrshire’s third Local Development Plan, undertaking early engagement with
communities and stakeholders.   
Introduction
The Planning (Scotland) Act 2019 introduced a new approach to measuring the
performance of planning authorities and made it mandatory for authorities to prepare a
report on their performance after the end of each financial year. 
The National Planning Improvement Framework (NPIF) has been developed by the
National Planning Improvement Champion and aims to support a planning authority to
assess their performance, identify areas of improvement and ascertain how best to
action these to maximise their effectiveness and efficiency. 
The National Planning Improvement Framework aims to support the purpose of
planning to manage the development and use of land in the long-term public interest
through ensuring that: 
▪ The planning system enables the delivery of sustainable, liveable, and productive
places. 
▪ Planning services are equipped to work effectively and efficiently, embedding
continuous improvement. 
▪ Users are able to engage constructively with the planning system and planning
service. A self-assessment tool has been development and focuses on the attributes of
a high performing planning authority. The attributes are grouped into five themes as
detailed below. 
143

Page 144

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
144

Page 145

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
NPIF Scoring Matrix 
Engagement on the National Planning Improvement Framework (NPIF) 
On completion of a draft NPIF the Planning service fulfilled a required peer review
meeting with the National Planning Improvement Champion, the Improvement Service,
Elected Members and internal and external stakeholders. An intention to include the
attendance of external peer review partner (Angus Council) was not possible as a result
of matters out with North Ayrshire’s control. 
The peer review meeting examined the NPIF, discussed its content and the Planning
service in North Ayrshire with all attending parties. 
A decision was made not to invite a community council to the peer review meeting for
the reason that this would not be fully representative of all communities of North
Ayrshire. To fulfil the importance of engaging with all North Ayrshire’s communities it
was determined to update the NPIF with feedback received from the peer review
meeting attendees, the National Improvement Champion and the Improvement Service
and, thereafter, to consult on a revised NPIF with all community councils in North
Ayrshire. 
The revised draft NPIF was subsequently issued to all community councils in North
Ayrshire seeking comments. In addition, the Chief Planning Officer offered to present a
summary of the draft NPIF to all community councils at one of their meetings to inform
on the NPIF and assist in the submission of community views. 
Presentation of the NPIF was subsequently made to all responding community councils
and all feedback has been incorporated into the finalised NPIF. In summary, comments
145

Page 146

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
on the NPIF were positive as was feedback on community engagement with the
Planning service and North Ayrshire Council more widely. Attendance at community
council meetings also provided opportunity to discuss contentious planning
applications, future engagement opportunities in relation to the emerging Local
Development Plan and North Ayrshire Council more widely in respect of many matters
such as community wealth building, community wellbeing and community
infrastructure delivery.  Notwithstanding good experience of past engagement being
noted, discussion on lesson learning took place on how community engagement and
planning decision making could be improved in the future. The approach taken in
respect of community consultation on the NPIF was welcomed by all community
councils and acknowledged as good practice to be built on in the future. 
The only concerns raised by community councils in relation to the NPIF were made in
respect of identified staff resourcing which was seen as a potential impediment to the
success of future engagement with communities and the addressing of identified
community needs. The best examples of this related to impact on investigation and
enforcement of unauthorised development and the ability of the Planning service to
fully develop community engagement in respect of aspirations and concerns contained
in registered Local Place Plans (LPPs). 
146

Page 147

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
A high performing planning authority needs to have
the right number of people to do the work expected of
it with the rights skills set. It also needs to have a
strategy to ensure that it retains and recruits the right
staff in the future. It supports staff to upskill and to be
prepared for changes in policy, legislation, and new
circumstances. 
Please consider the following when thinking about this attribute and how you have
performed over the last year:  
• Does the planning authority have the sufficient level of staff to carry out all activities
within the required timeframes?
YES – although staff resource issues exist
• Does the planning authority have the ability to carry out all activities within the
required timeframes with its current budget?
YES
• Does the planning authority have the ability to carry out all activities within the
required timeframes with its current income?
YES
• Does the planning authority received responses from consultees within the
prescribed timescale when assessing planning applications?
YES 
• Does the planning authority have the ability to access the appropriate advice,
expertise, evidence, and data it requires?
YES
Narrative
The Development Management Team is one of the smallest pro-rata of all Scottish
Planning Authorities at only 5.75 FTE posts comprising of 1.75 FTE Senior Planning
Officers, 2 Planning Officers and 2 Assistant Planning Officers.  The team has 2 FTE
support staff with no enforcement or specialist officers.
The team has experienced significant resource issues in the last year with business
case justification required for the recruitment of a Planning Officer vacancy and
difficulties thereafter in recruiting an Assistant Planning Officer position following
internal promotion. The Planning Officer position was vacant, for 4 months and the
Assistant planning officer post was vacant for one year but has recently been filled.
ATTRIBUTE 1: THIS PLANNING AUTHORITY HAS SUFFICIENT
RESOURCES AND SKILLS TO MAXIMISE PRODUCTIVITY
147

Page 148

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Informal peer review of comparable Planning service resourcing has confirmed that the
team is as little as one third of the size of comparable authorities and with as much as
twice the caseload per officer.     
Consultees play a significant role in the processing of planning applications. Internal
consultation responses are generally received within the requested timescale.
However, there are regulatory pressures on our internal consultees and therefore
limited resources available to direct planning application consultations. External
consultation responses have been noticeably delayed as a result of pressure by
additional demands arising from the implementation of National Planning Framework
(NPF4), enhanced Local Development Plan (LDP) requirements and resourcing
pressures generally. Delay in the consultation process impacts on planning application
determination timescales and is outwith the control of the Planning service. 
The Strategic Planning Team is comprised of a Strategic Planning Manager, 2 Planning
Officers, 1 Assistant Planning Officer and a Technician. The team is currently operating
at a reduce resource following the loss of the Assistant Planning Officer to a promoted
post in a neighbouring authority As with the Development Management team the
Strategic Planning team is small when compared to comparable Planning Authorities
and has no specialist officer resource in areas such as historic buildings or landscape. 
The team is responsible primarily for all aspects of the preparation of the Council's
Local Development Plan and providing support to community bodies in the preparation
of Local Place Plans. The team consists of a manager, two planning officers, an
assistant planning officer and technician.   
The Strategic Planning Team has recently finalised an Evidence Report and submitted
this to Scottish Government as part of the “Gatecheck” process. The breadth of topics
to be covered and the data collection, analysis and engagement that is necessary to
pass the Gate Check stage provided a significant workload challenge for the team.
Identified risks related to the capacity for engagement with Key Agencies and the
impact of an Evidence Report being returned following Gate Check would have on the
planning authority being able to meet the Scottish Government expectation of having a
new style LDP in place within around 5 years of the Regulations coming into force i.e. by
May 2028. To date these risks have been managed and the LDP is on track for adoption
by May 2028. 
Budget provision has been made to support the preparation of the LDP, including the
procurement of specialists to provide appropriate advice, expertise, evidence and data,
specifically in relation to Transport Appraisal; Play Sufficiency Assessment and
landscape assessment.  
Informal review of the Planning service over the past year has identified the following
issues.
148

Page 149

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
• Difficulties in recruitment
• Career progression only possible where a vacancy becomes available
• Ageing workforce in senior positions
• Succession planning limitations
• Increasing legislative complexity without additional resource 
• Pressure of maintaining service excellence in the face of additional pressures
A formal review of the Planning service to examine these issues in more detail is
planned in the coming year. 
Action
Formal reviews of the Planning service will examine existing resource suitability for 
current and future workload, identify potential gaps in service provision, provide
risk  management and a pathway to ensure appropriate future service provision.
149

Page 150

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Professional and Financial Resources
The establishment resource of the Planning service is; 
Head Count:
Chief Planning Officer  1
Development Management  5.75
Development Planning   4  (currently 3 as a result of vacancy)
Technical Support    4
Total     14.75 (currently 13.75 as a result of vacancy 
RTPI Chartered Staff:  6 
Age Profile:
Under 30    2
30-39     5
40-49     5
50 and over    3 
The Chief Planning Officer monitors the service budget on a monthly basis with the
respective service Accountant.
Planning fee income for 25/26 was similar to that of previous years at approximately
£750,000. With outgoings of considerably less than this, the Planning service has
historically “over recovered” in respect of income against expenditure without a
resulting increase in resources. 
150

Page 151

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
151

Page 152

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Please consider the following when thinking about this attribute and how you have
performed over the last year: 
• Does the planning authority have a workforce planning strategy in place?
NO – this is an action
• Does the planning authority have the ability to support staff development and
upskilling and send staff on relevant courses?
YES – training budget exists
• Does the planning authority have a deliverable commitment to support staff health
and wellbeing?
YES – both corporately and within service
Narrative
North Ayrshire Council’s Performance Management Strategy and fair-work-first-
statement aim to aims to create a flexible, skilled, and motivated workforce that
supports the council's vision of a "Fair for All" North Ayrshire. The Council also has a
Wellbeing at Work policy Corporate Health, Safety & Wellbeing and is committed to
excellence in health, safety and wellbeing by preventing or minimising any adverse
impact of our activities and services, and by ensuring that its employees and
communities are safe and protected.
Beyond the identified Council policies there is no Planning workforce strategy however,
as previously noted, a review of the Planning service is programmed for the next year
which will establish service capacities, needs, and strategy for delivery. This work will
build on the informal review previously noted and inform in areas such as workforce
direction, recruitment strategy and financial opportunities/constraints. Action 
The recruitment of Town Planners and associated staff is a national challenge as
recognised in work such as the Royal Town Planning Institute /Heads of Planning
Scotland and Scottish Government Future Planners Project. A historic reduction in the
number of undergraduate Town Planning courses has been addressed with potential
geographic significance to North Ayrshire with the initiation of an accredited course at
the University of West of Scotland bolstering the only other undergraduate course at
Dundee University and the postgraduate course at Glasgow University. The North
Ayrshire Planning service does not currently have budget for intern or graduate
placements however this will be considered in the programmed Planning service
review. 
A more pressing concern, however, is the limited staff resource that can be dedicated
to the investigation into and enforcement of planning breaches. This is an ongoing
difficulty in meeting the expectations of customers concerned with enforcement
matters. The Planning service has no dedicated enforcement officer, and this obligation
ATTRIBUTE 2: THE PLANNING AUTHORITY HAS A VALUED AND
SUPPORTED WORKFORCE 
152

Page 153

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
is shared between Development Management Officers who already have a higher than
nationally averaged workload in respect of application caseload. Therefore, the
investigation of additional staff resource for the service is an action. 
An additional resource concern is the absence of a managerial position in the
Development Management team to reflect the existence of such in the Strategic
Planning team. This is a staffing resourcing issue that will also be investigated as an
action. 
Opportunities to support Planning staff by means of training and upskilling are
constantly reviewed and a limited training budget exists for this. The Planning service is
also committed to enhancing the skills, talents, and confidence of staff through
attendance at relevant and suitable training and development courses which include
those hosted by the RTPI, relevant chapter events, HOPS and the Improvement Service
and other providers. 
153

Page 154

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Improvement Action Plan (People theme) 
Attribute Score 
(1=Making excellent progress, 5= No progress) 
1. The planning authority has sufficient resources and skills to maximise
productivity 
4
2. The planning authority has a value and supported workforce  2 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/
Medium/ Low) and by when (short/ medium/ long term). 
Improvement Action
What action will you take?
What will the outcome be?
Owner Importance
High 
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources
Service review Allan Finlayson High Short Internal
Workforce Planning strategy Allan Finlayson High Short  Internal/peer review
Enforcement resourcing
improvement
Allan Finlayson High Short 
Development Manager
resourcing improvement
Allan Finlayson Medium Medium 
154

Page 155

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
A high performing planning authority has a positive
culture through ensuring it has sound governance,
effective leadership and a commitment to continuous
improvement. The authority has an identified chief
planner, who is supported by a strong leadership group
to advise on decision-making, policy and operational
management. 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Has the planning authority undertaken an annual assessment of its performance and
acted upon areas previously identified as in need of improvement?
YES – annual informal assessment undertaken with committed action to formalise
• Has the planning authority achieved recognition at relevant awards or through
performance accreditation frameworks?
YES – previous award recognition however current resourcing issues preclude seeking
this at this time
• Has the planning authority engaged in peer review, good practice exchange or
improvement activities?
YES – informal peer review and lesson learning regularly undertaken 
• Has the planning authority addressed any complaints upheld by the Scottish Public
Services Ombudsman and have evidence of this and that it has learned from valid cases?
YES – previously however no SPSO cases within the reporting period
Narrative
Continuous improvement of the Planning service is always the subject of ongoing review
and focusses on Development Management and Local Development Planning
obligations.
Development Management performance has decreased slightly as a result of resourcing
difficulties but remains nationally leading and significantly higher than national averages.
The Local Development Plan (LDP) is currently on track for adoption before the 2028
Scottish Government target however programme slippage has been noted recently, again
as a result of resourcing issues and the delay experienced in Scottish Government’s
ATTRIBUTE 3: THIS PLANNING AUTHORITY HAS EMBEDDED
CONTINOUS IMPROVEMENT.
155

Page 156

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
consideration of the LDP Evidence Report at Gate Check stage. The LDP Development Plan
scheme is as up to date as possible in these circumstances.
National award recognition of the high standards of performance and achievements of the
Planning service has been achieved previously. Most notably awards have been given in
the Scottish Awards for Planning (2019) and Royal Town Planning Institute’s Awards for
Planning Excellence (2016 and 2017). Regrettably, given resourcing pressures, the focus of
the Planning service is now on maintaining performance and has not recently been in a
position to seek award recognition to promote the service excellence being maintained. 
Development Management Performance
Our decision-making demonstrates continuous evidence of nationally leading timescales
in the determination of all type of planning applications to assist the development and
meet customer expectations.
Development management performance has decreased slightly in the last year as a result
of long-term vacancies and recruitment difficulties however the performance of the
Planning service remains the highest in Scotland in most measurable indices and in the top
three of all.
The offer of processing agreements or other agreed project plan is made to prospective
applicants in advance of all major applications and availability publicised on planning
authority website.
Early collaboration with applicants and consultees on planning applications providing
clear and proportionate development advice is usually available in the promotion of free of
charge pre-application discussions for all prospective applications. This service is
currently suspended for less significant proposed developments on the basis of vacancy
and recruitment impacts but will be re-introduced as soon as possible following
successful recruitment.
Legal agreements are avoided where possible or invariably concluded within 6 months of
‘resolving to grant’ planning permission.
The Planning service Enforcement charter was last updated in March 2023 and is
therefore due for further updating. This is action for progression in the short term. Action 
Development Plan Progress
North Ayrshire’s Local development plan is currently on track for adoption in late 2027 in
advance of the Scottish Government 2028 target for all Planning Authorities.
The Development plan scheme was last adopted in November 2024 Development Plan
Scheme as required annually. Updating is currently postponed until confirmation of a
decision by Scottish Government at Gate Check. 
Engagement with stakeholders including Elected Members, industry, agencies, the public
and Scottish Government are engaged appropriately through all key stages of development
plan preparation. 
156

Page 157

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Continuous improvement: progress relevant service improvement commitments
identified through NPIF report. 
Delivery of 2025/26 Service Improvement Actions
Repositioning the Planning Service to promote Placemaking: 
• Ayrshire Growth Deal: Contribute to the implementation of the Ayrshire Growth Deal
in North Ayrshire and the wider growth and investment opportunities. 
In addition to supporting the delivery of major investment planned for Hunterston, the
Planning Service has supported the preparation of masterplans for Ayrshire Growth
Deal projects at i3 and the Great Harbour, both in Irvine. 
• Support economic recovery and renewal by contributing to a cross service/Council
approach to economic development, centred on placemaking and Community Wealth
Building. Exploring the alignment of planning and community wealth building, including
in context of NPF4.
The Planning Service continues to collaborate with Economic Development and
Community Wealth Building to input into the preparation of a Regional Economic
Strategy for Ayrshire and the Council’s Community Wealth Building initiatives to
support sustainable economic development within the Ayrshire region and North
Ayrshire communities. 
Driving Improved Performance:
• Development Management: Continue to provide an efficient and effective
Development Management Service. 
The Planning service continues to maintain sector-leading performance in comparison
with nationwide peers despite recent resourcing difficulties. 
• Service Delivery: review service delivery to identify potential opportunities to improve. 
The Planning service was operating under an extended period of resource constraint
since 2024 as a result of the filling of three vacancies out of a team of fifteen therefore
there has been limited opportunity to review potential service improvements.
Notwithstanding the above position, the Local Development team has continued to
develop community engagement. The team has significantly supported the preparation
of Local Plan Plans (LPPs) by local communities to engage, inform and support the
157

Page 158

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
preparation of the emerging Local Development Plan (LDP3). Collaboration with
Community Wellbeing colleagues in community engagement has been further
developed to deliver “one-stop” community consultation involving the Planning service
and the preparation of interdependent information resources such as Place Profiles 
North Ayrshire Place Profiles that collate information from cross Council services.
Modifications to the Development Management processes continue to be made to
ensure planning applications can be determined as efficiently as possible. Limited staff
resource requires that case officers have responsibility for enforcement, the validation
process, sending acknowledgement letters, consultations, posting site notices and
ensuring the Uniform database is maintained to support service standards being
upheld. 
Recent changes have been made to remove some information publicly displayed on
the Council’s Online Planning Information System (OPIS) such as objection comments
and consultation responses. The reason for this is that resource does not exist to
redact information and also that OPIS appears to be being used by some of the public
as an extension to social media platforms e.g. referring to and cross-referencing
comments to seek to direct application assessment. 
Promoting the plan-led system:
• Development Planning:  Following the timetable set out in the Development Plan
Scheme, develop Evidence Base to inform LDP3. 
The Development Plan Scheme was last adopted in November 2024, and we are on track
and nearing the end of the Evidence Reporting stage of LDP3 preparation. 
A strong emphasis is placed within the Strategic Planning Team service on sharing good
practice, skills, and knowledge, including via HOPS sub-forums, the Knowledge Hub
resource, and informal groups, including the Fife LDP Peer Review Group and regular
meetings with South and East Ayrshire.  
In 2025, the Chief Planning Officer “reached out” to peers in East and South Ayrshire to
further develop regional understanding of Planning and related matters and inform
collaborative working, for example, in respect of regional economic and spatial strategy,
and housing, climate and nature crises. This has progressed significantly in the
subsequent period to develop regional spatial and economic understanding and initiatives. 
2025/26 Service Improvement Actions
As a result of the Planning service operating under an extended period of resource
constraint no new improvement actions for the Planning Service have been set at this time. 
The Service is continuing to focus on the early stages of preparing Local Development Plan
3 and is on track for adoption in accordance with Scottish Government targets. 
158

Page 159

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Delivering an efficient and effective Development Management service is being maintained
with the highest level of performance being demonstrated in national comparison.
Notwithstanding the above, the Chief Planning Officer intends to continue to develop
regional collaboration in further discussion with neighbouring authorities in Inverclyde and
Renfrewshire Councils. Action 
159

Page 160

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Does the planning authority have an effective scheme of delegation in place?
YES – reviewed annually and up to date
• Have all councillors who exercise a planning function undergone statutory training and
is there is evidence of ongoing training for members?
YES – historically undertaken in advance of and beyond legislative requirement
• Have more than x % of officer recommendations have been overturned by councillors at
committee or Local Review Body.
NO – historically low numbers of overturned recommendations
Narrative
The Planning service is incorporated within North Ayrshire Council’s Communities,
Housing and Public Protection directorate. This directorate was newly formed in 2024 to
respond to the Council’s commitments in these service areas. 
The decision-making ability of the Planning service is established in the Council’s adopted
Scheme of Delegation, and this details the circumstances whereby planning applications
are required to be considered and determined by the Planning Committee. The scheme of
delegation provides decision making powers to the Chief Planning Officer on an extended
basis in the interests of efficiency in dealing with local planning applications however
major and sensitive applications are commonly determined by the Council’s Planning
Committee. The Scheme of Delegation was most recently adopted in October 2025 and is
regularly reviewed. 
The Local Review Body is the method of appealing decisions made by the Chief Planning
Officer under the Scheme of Delegation. The Local Review Body conducts reviews in
respect of the refusal of planning permission, failure to determine applications and the
imposition of conditions. 
In the last year, the Local Review Body (LRB) determined only four applications for
review. This is considered to demonstrate both general satisfaction with the decision
making of the Chief Planning Officer under the Scheme of Delegation and the
appropriateness of decisions made. The Local Review Body overturned only one officer
decision in this period.
ATTRIBUTE 4: THE PLANNING AUTHORITY HAS SOUND
GOVERNANCE 
160

Page 161

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
The Council’s Planning Committee is the decision-making board which determines
planning applications where delegation authority is not provided to officers. The Planning
Committee meets monthly to consider recommendations on planning applications and
Local Development matters as appropriate. In the past 12 months, 96% of applications
considered by the Planning Committee were decided in accordance with officer
recommendation. This equates to only one officer recommendation being overturned in
that period. 
The Planning (Scotland) Act 2019 requires that mandatory training is implemented for all
elected members who are involved in any decisions involving planning matters. It should
be noted that, as a commitment to effective decision making, North Ayrshire Council has
historically undertaken elected member training significantly in advance of this legislative
requirement. Training is undertaken on a six-monthly basis most recently in December
2024, June 2025 and December 2025. Interim and individual training can be provided at
any time e.g. for new Committee members as and when required. 
In the last year only two appeals to Scottish Ministers for planning decisions have been
made and both remain under consideration. One further planning appeal was submitted
but was rejected as being out with the remit of the DPEA. As noted above in respect of
delegated decisions, the low level of appeals to Scottish Ministers is considered to
demonstrate general satisfaction with and the appropriateness of decisions made.
Guidance to applicants on how to appeal either to Scottish Ministers or the Local Review
Body is available on the Council’s website Planning reviews and appeals.  
161

Page 162

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Does the planning authority have an identified Chief Planning Officer in place?
YES – since 2021, well in advance of regulatory requirement
• Does the Chief Planning Officer advise on corporate decision making and policy within
the broader organisation?  
YES
• Is the planning authority's Chief Planning Officer a member of the Royal Town Planning
Institute?
YES
• Does the Chief Planning Officer advise and support external bodies through engagement
in organisations’ committees, advisory groups or working groups?  
YES
• Does the planning authority have a strong leadership team that supports a culture of
continuous improvement?
YES - both corporately and within service 
Narrative
A Chief Planning Officer was appointed in 2021, in advance of the statutory requirement
being put in place by the Scottish Government in 2024. The officer in question is a
Chartered Member of the Royal Town Planning Institute (RTPI) and is the head of the
profession within the Council. The Chief Planning Officer provides advice throughout the
Council to other departments and services, other Senior Managers, Elected Members, and
members of the public in relation to planning matters. 
Guidance on the role of the Chief Planning Officer advises that the position should
strengthen leadership on planning and corporate recognition of the importance and
positive influence of planning within a Council. The duties and responsibilities of the Chief
Planning Officer are positioned around 5 main attributes: 
• Professional Advisor 
• Delivering National Planning Priorities 
ATTRIBUTE 5: THE PLANNING AUTHORITY HAS EFFECTIVE
LEADERSHIP  
162

Page 163

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
• Champion of place 
• Head of Profession 
• Performance Improvement
The role of the Chief Planning Officer as a Professional Advisor is to direct on the vision
and implementation of the National Planning framework (NPF4) and Local Development
plan for North Ayrshire spatial and associated development priorities.
The Chief Planning Officer is a member of the Council’s Senior Management Team (SLT)
and advises the Council’s Executive Leadership Team (ELT) and elected members in the
development and delivery of corporate objectives to promote and achieve the Strategic
Plan priorities in a spatial and place-based approach. 
The role of the Chief Planning Officer includes Delivering National Planning Priorities in
the alignment and delivery of national planning objectives within North Ayrshire. 
As a Champion of Place, the Chief Planning Officer directs and delivers place making
ambitions within the Council, is the Council’s placemaking champion and ensures a
collaborative approach to place making with other Council officers, elected members and
developers. 
The Chief Planning Officer is the Head of the Planning Profession in North Ayrshire and
the most senior responsible qualified officer for the Council’s Planning Service. The Chief
Planning Officer is the main contact for key stakeholders on planning and place and
represents the Council internally and externally on several groups requiring or benefitting
from input from the planning function. 
The Chief Planning Officer is ultimately responsible for the Performance and
Improvement of the planning service in North Ayrshire and the embedding of an ethos of
continuous improvement. 
The Chief Planning Officer in North Ayrshire participates and advises a number of internal
and external bodies to provide spatial and development planning advice. These include. 
• Ayrshire Economic Partnership Board 
• Ayrshire Economic Joint Committee
• Arran Housing Taskforce
• B714 Project Delivery Board
• Clyde Marine Planning Partnership
• North Ayrshire Inward Investment Group
• Irvine Town Board (Long Term Plan for Towns)
• Islands Group Board 
163

Page 164

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
• Ayrshire Planning Regional discussion group 
Reporting to the Chief Planning Officer are two Senior Planning Officers responsible for the
Council’s Development Management regulatory service and the Strategic Planning
Manager responsible for the Council’s Development Planning regulatory service. 
The Planning service benefits from a direct relationship to and strong support from the
Council’s Chief Executive, Executive Director of Communities and Housing and Head of
Housing and Public Protection. 
A culture of continuous improvement is expected, supported, and delivered in North
Ayrshire Council generally and specifically within the Planning service. 
The Chief Planning Officer, Strategic Planning Manager and Senior Planning Officers all
engage nationally to keep involved and informed in national Planning practice. This takes
the form of national engagement with Heads of Planning Scotland with participation in
both the Development Plan and Development Management groups. Involvement with the
Improvement Service is undertaken by Planning management and all staff in participation
with the Planning Skills programme. The Chief Planning Officer also presented to an
Improvement Service seminar on Customer Service, this being informed by North Ayrshire
Council and the Planning service commitment to community engagement and removing
barriers to customer service. All  of this has informed preparation of the NPIF. 
164

Page 165

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Improvement Action Plan (Culture theme) 
Attribute Score 
(1=Making excellent progress, 5= No progress) 
3. This Planning Authority has embedded continuous improvement  1
4. This Planning Authority has sound governance 1
5. This Planning Authority has effective leadership 1 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/
Medium/ Low) and by when (short/ medium/ long term). 
Improvement Action
What action will you take?
What will the outcome be? 
Owner Importance
High 
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources
Renfrewshire/Inverclyde
regional discussions. Further
develop and undertake
meetings with neighbouring
Councils to understand and
develop competing/co-
operative regional
challenges/opportunities.
Allan Finlayson Medium Short  Chief Planning Officer and
Strategic Planning manager
Enforcement Charter review Allan Finlayson/Iain
Davies
High Short 
165

Page 166

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
A high performing planning authority needs to have an
effective local development plan and other strategies in
place to provide a vision for the future of the area. It
needs to be able to set and deliver on policy ambitions
and priorities by clearly informing decision making and
providing certainty and predictability for communities,
developers and investment. The authority’s
development management systems need to be
effective in making the right decisions about
development and be efficient as possible in doing this.
The planning authority makes best use of digital
technology and how it manages and uses data. 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Does the planning authority have an up to date Local Development Plan in place and/ or
is on track to adoption?
YES – the extant LDP2 is up to date and the emerging LDP3 on track to adoption
• Does the planning authority have an up-to-date Regional Spatial Strategy in place/ or on
track to adoption? 
YES –  a RSS is not yet a legislative requirement however North Ayrshire is progressing
towards preparation of a combined RSS and Regional Economic Strategy in
partnership with South and East Ayrshire Councils
• Has the planning authority’s Local Development Plan Evidence Report been approved by
the Department of Planning and Environmental Appeals and/ or on track for approval?
NO – however the Evidence Report has been submitted to DPEA in advance of many
authorities and is currently receiving attention at Gate Check
• Has the application of the Local Development Plan’s policies been found to be deficient
at appeal or judicial review?
NO – policies of the extant LDP2 (2019) are widely considered to be almost entirely
aligned with the subsequent adoption of the National Planning Framework (NPF4) in
2023.  
ATTRIBUTE 6: THE PLANNING AUTHORITY HAS A ROBUST POLICY
AND EVIDENCE BASE 
166

Page 167

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Narrative
North Ayrshire Council’s development plan consists of Local Development Plan (LDP2),
which was adopted in November 2019  Adopted Local Development Plan and the Fourth
National Planning Framework (NPF4), adopted in February 2023 National Planning
Framework 4 - gov.scot. Together these provide an up-to-date development plan covering
North Ayrshire. The local development plan is supplemented by non-statutory planning
guidance documents Non-statutory planning guidance. 
Preparation of a new local development plan (LDP3) is well underway and on track for
adoption in 2027 in advance of Scottish Governments May 2028 deadline. The emerging
LDP’s Evidence Report was submitted to the Directorate of Planning and Environmental
Appeals (DPEA) for Gate Check assessment in January 2026 and a decision is expected in
April. 
Following approval by the appropriate committees of North, South and East Ayrshire
Councils, an indicative Regional Spatial Strategy for Ayrshire was submitted to the
Scottish Government in 2020. Guidance from the Scottish Government remains to be
progressed significantly. Notwithstanding this position, the Chief Planning Officers of all
Ayrshire Councils and Regeneration peers in all Councils  are progressing a combined
Regional Spatial Strategy and Regional Economic Strategy for Ayrshire Ayrshire regional
economic strategy. 
The above work will further develop regional understanding of Planning, Regeneration and
related matters and inform collaborative working, for example, in respect of regional
economic and spatial strategy, housing, climate and nature crises and infrastructure
delivery. Further developing regional discussion with neighbouring authorities in Inverclyde
and Renfrewshire Councils will be progressed in late 2026 to further develop this work and
is a committed action. 
167

Page 168

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Has the planning authority encouraged and promoted planning applications to be
submitted through the e-development portal?
YES – North Ayrshire receives almost entirely all planning applications through the e-
development portal. Notwithstanding this, the receipt of paper applications is
accommodated to assist with customer needs although this rarely occurs.
• Does the planning authority have a data governance strategy in place for the
management of planning data?
YES – both corporately and in service.
• Does the planning authority have the ability to use interactive web-mapping, GIS, and
spatial data?
YES – the service use of interactive and digital data is provided at a level significantly
beyond reasonable expectations of the small Planning team. This is considered a
testament to the professionalism of officers and their commitment to customer and
community engagement
• Does the planning authority have the ability to use digital approaches to engagement,
including website, social media, and other platforms?
YES – and, again, the use of these approaches is provided at a level significantly
beyond reasonable expectations of the small Planning team. 
Narrative
The North Ayrshire Council website has a number of pages dedicated to various aspects of
planning. The Council website has recently been updated to a new, clearer, and more
interactive platform, and officers of the Planning service have contributed to this process
to take the opportunity to update information and links as appropriate. In addition,
updating of the Planning pages is undertaken “in house” as and when required. Planning
and Building Standards 
In respect of Development Management, during 2025-26 96% of planning applications
received were submitted through the Planning Portal, accounting for almost all of the 600
applications received. Use of the Portal is actively encouraged and clear advice with links
is provided on the Planning pages of the Council’s website Make a planning application 
ATTRIBUTE 7: THE PLANNING AUTHORITY MAKES BEST USE OF
DATA AND DIGITAL TECHNOLOGY 
168

Page 169

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
This approach minimises our handling of documents and ensures greater efficiency in
application receipt, validation, and assessment. Our processes are now fully electronic,
with any hard copy information quickly digitised and we have operated in this manner for
many years. 
The Planning service has developed an interactive Local Development Plan interactive
version of the LDP for the benefit of customer service to aid customer engagement in the
LDP process and also to provide direct digital access to detailed policies and additional
related information that provides more detail about how we will consider proposals for
specific uses or developments. A storymap presentation of the LDP is also available
online. 
The Strategic Planning Team also utilises interactive web-mapping and GIS – specifically
ArcGIS’s StoryMaps – to present a wide range of spatial data. This includes housing and
employment land audits. StoryMaps have been used to create Profiles for North Ayrshire’s
six localities. These have been produced to inform the preparation of our third Local
Development Plan LDP3 and support other placemaking activity. The profiles summarise
key social, cultural, environmental, and economic features of the areas.  
The Service has invested in a three-year Commonplace licence to support engagement on
the Local Development Plan through the creation of an online hub: Have Your Say Today -
North Ayrshire’s Third Local Development Plan - Commonplace.    
ArcSurvey GIS has been deployed for the current ‘Call for Ideas’ exercise, allowing
submitted information in support of promoted sites, including mapped boundaries, to be
digitised more easily: Call for Ideas   
The Planning Services makes spatial data available via the Corporate Open Data Portal
under the Open Government Licence for public sector information and in accordance with
North Ayrshire’s  Open Data Strategy and Publication Plan.   
169

Page 170

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Does the planning authority planning have the ability to make decisions on planning
applications within the required timeframes?
YES – planning application decisions in North Ayrshire are in the top three nationally
which is considered a significant achievement for a small Planning team which is
proportionally one of the smallest in Scotland
• Are less than x% of planning decisions overturned at appeal or judicial review?
YES 
• Does the planning authority have an up-to-date Enforcement Charter in place?
YES – however the Enforcement Charter is due for updating and this is committed as
an improvement action 
• Does the planning authority have the ability to resolve enforcement cases?
YES – however the investigation of enforcement  cases as quickly as would be
preferred remains challenging as there is no dedicated enforcement officer and cases
are investigated by Planning Officers
Narrative
North Ayrshire Council’s Development Management performance has historically
demonstrated nationally leading excellence in decision making timescales
notwithstanding a small team size and limited resources. Over the past 10 years, the
service has regularly been the highest performing Planning Authority across all planning
application determination categories (householder, local, major and national) measured
by Scottish Government Supporting documents - Planning Application Statistics 2024/25
(April 2024 to September 2024) - gov.scot 
Development management performance reduced slightly in the last year as a result of staff
resourcing issues. However, performance remains in the top three Planning Authorities in
all measured categories and the top performing in more categories than any other
Authority. 
Development Management performance in North Ayrshire is significantly above national
average performance levels monitored by Scottish Government Planning statistics -
gov.scot. 
ATTRIBUTE 8: THE PLANNING AUTHORITY HAS EFFECTIVE AND
EFFICIENT DECSION MAKING PROCESSES 
170

Page 171

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
The exceptional performance of the Planning service in North Ayrshire is a cornerstone in
serving the individual, community, and business needs of all our customers.
Commendably, this is achieved whilst providing a free of charge pre-application enquiry
service with no discretionary charging beyond statutory requirements. 
In the last year, the Local Review Body (LRB) determined only four applications for review.
This is considered to demonstrate both general satisfaction with the decision making of
the Chief Planning Officer under the Scheme of Delegation and the appropriateness of
decisions made. The Local Review Body overturned only one officer decision in this period. 
In the last year only two appeals to Scottish Ministers for planning decisions have been
made. One further planning appeal was submitted but was rejected as being out with the
remit of the DPEA. As noted previously, the low level of appeals to Scottish Ministers is
considered to demonstrate general satisfaction with and the appropriateness of decisions
made. 
Further evidence demonstrating general satisfaction with decision making is the very low
number of complaints received by the Planning service. Only three complaints have been
received in the last year and none have been upheld. Furthermore, no complaints
investigated were referred to SPSO. No applications for Judicial Review have been
received. The Planning service has also received a level of communication expressing
thanks for good service received significantly above the number of complaints received.
The extremely low level of complaints received, absence of escalation and decision
making challenge are considered to be a testament to decision making within the Planning
service in North Ayrshire. 
The Planning service Enforcement charter was last updated in March 2024 and is
therefore due for further updating. This is action for progression in the short term. Action
A more pressing concern, however, is the limited staff resource that can be dedicated to
the investigation into and enforcement of planning breaches. This is an ongoing difficulty in
meeting the expectations of customers concerned with enforcement matters. The
Planning service has no dedicated enforcement officer, and this obligation is shared
between Development Management Officers who already have a higher than any national
workload in respect of application caseload. Therefore, the investigation of additional staff
resource for the service is also an action. 
An additional resource concern is the absence of a managerial position in the
Development Management team to reflect the existence of such in the Strategic Planning
team. This is a staffing resourcing issue that will also be investigated as an action.
171

Page 172

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Improvement Action Plan (Tools theme) 
Attribute Score 
(1=Making excellent progress, 5= No progress) 
6. The planning authority has a robust policy and evidence base 1
7. The planning authority makes best use of data and digital technology  1
8. The planning authority has effective and efficient decision making
processes 
2
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/
Medium/ Low) and by when (short/ medium/ long term). 
Improvement Action
What action will you take?
What will the outcome be? 
Owner Importance
High 
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources
Enforcement charter review Allan Finlayson/ Iain
Davies
High  Short 
Enforcement resourcing
improvement
Allan Finlayson High Short 
Development Manager
resourcing improvement
Allan Finlayson Medium Medium 
172

Page 173

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
A high performing planning authority should ensure a
wide range of people are involved in shaping their
future places. Engagement should be fair and inclusive,
early, collaborative, meaningful and proportionate and
should include difficult to reach groups. The authority
should engage with a wide range of partners at a
national, regional and local level to ensure a joined-up
approach and that links are made across policies and
programmes. The planning authority should
demonstrate good customer care, transparency and
effective communication. 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Does the planning authority have the ability to offer pre-application advice where it is
requested?
YES – North Ayrshire Council is one of a decreasing number of Planning Authorities to
offer free pre-application guidance. There are no plans to introduce charges as this
service is considered important in providing development guidance to customers,
communities and developers to the benefit of all.
• Has the planning authority held regular engagement events with developers and
communities?
YES – the Planning service regularly attends community events and meetings and
engages with the development industry nationally and locally
• Do the results from the customer and stakeholder survey show that customers are
satisfied with the service offer by the planning authority?
YES – consultation on this survey was widely circulated and the limited number of
responses and comments received should be taken as confirmation of satisfaction
with the Planning service in North Ayrshire. This position is corroborated by the
exceptionally low number of complaints received and the outweighing of these by
positive comments submitted by customers 
ATTRIBUTE 9: THE PLANNING AUTHORITY HAS GOOD CUSTOMER
CARE 
173

Page 174

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Narrative
The ethos of the Planning service is to be directly contactable with customers, wherever
possible, by all forms of communication. The service maintains a direct telephone service
and excellent links with the Council’s general Contact Centre telephone service.
Telephone calls are invariably either answered directly or returned the same day. Officers
at all levels can be contacted directly by telephone or email. Email responses are
invariably returned within 1-2 working days. 
This customer service ethos was noted by the Improvement Service and the Chief Planning
Officer was invited to present to a recent customer service workshop and training session. 
In respect of Development Management, the Planning service welcomes early
engagement with all applicants and developers prior to the submission of any application.
The service is strongly of the view that submission of informed, detailed, and
comprehensive applications results in quicker decision making and better quality of
developments. 
The Council offers a free of charge pre-application advice service intended to guide and
inform the formulation of all development proposals. Maintaining a free of charge service
for pre-application advice is becoming less common in Planning Authorities nationally
however North Ayrshire is committed to the continuation of this given the customer care
and development quality benefits that result. 
The Planning service also offers Processing Agreements for all National or Major
applications and for complex local developments. Details of the Processing Agreements
process is available on the Planning Website Make a planning application. A Processing
Agreement is used to set out the key processes in determining the application, identifying
what information is required and from whom and sets the timescales for the delivery of
various stages of the process. It is recognised that there are several benefits of Processing
Agreements including greater transparency in decision making, increased predictability
and certainty over the timing of key stages. 
The Strategic Planning Team has developed a positive working relationship with Homes
for Scotland, going back to the preparation of the adopted Local Development Plan, the
annual Housing Land Audit, and the early stages of preparing LDP3. 
The Service has engaged proactively with the majority of active Community Councils in
North Ayrshire over the past two-years, providing advice on how they can best engage with
the Planning system. 
174

Page 175

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Does the planning authority have a community engagement strategy and infrastructure
in place to ensure engagement is early, collaborative, meaningful and proportionate?
YES -  the Planning service in North Ayrshire is small, agile and with a demonstrable
track record of community engagement in fulfilment of a wider Council commitment.
There is not considered a need to formalise this in a community engagement strategy
which could be at the expense of the agility and directness of existing community
contact and engagement 
• Has the planning authority undertaken community engagement, for example consistent
and effective use of the Place Standard Tool, to inform decision-making processes? Has
the planning authority encouraged and promoted planning applications to be submitted
through the e-development portal?
YES – the Place Standard Tool is regularly utilized and the e-development portal is
promoted for the submission of all planning applications however applicants who
demonstrate that they cannot use the portal can be accommodated by alternative
submission eg. email or paper receipt. 
• Has the planning authority engaged with a good representation of the community
including young people, gypsies and travellers, people with protected characteristics,
including disability, race, age, sex and sexual orientation, and including people from a
range of socio-economic backgrounds?
YES – the Planning service engages with all customers and communities in North
Ayrshire
• Has the planning authority supported the production of Local Place Plans when
requested?
YES 
• Do the results from the customer and stakeholder survey show that stakeholders are
satisfied with their collaboration with the planning authority?
YES 
Narrative
The Planning service is strongly committed to collaboration with local communities,
public bodies, and other stakeholders at all relevant stages of the planning process.
ATTRIBUTE 10: THE PLANNING AUTHORITY HAS EFFECTIVE
ENGAGEMENT AND COLLABORATION WITH STAKEHOLDERS
AND COMMUNITIES
175

Page 176

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
In respect of Development Management, engagement is undertaken daily in often
challenging circumstances of polarized opinions. Notwithstanding this, the service is
committed to a “listen first” approach to development assessment and to the clear
demonstration of appropriate assessment in reports of handling and decision-making
accountability. 
The Strategic Planning Team has ensured that the current Development Plan Scheme
includes a Participation Statement setting out when consultation is likely to take place,
with whom and its likely form, including the steps to be taken to involve the public in the
preparation of  the local development plan.   
Early engagement to inform the Evidence Report/LDP3 was focused around the use of the
Place Standard Tool, to gather information on what local people think about the places
they live, work and visit in North Ayrshire: Have Your Say Today - Your Place Survey - North
Ayrshire’s Third Local Development Plan. This builds upon previous use of the Tool to
identify Community Planning locality priorities and evidences the strong links between
community planning and spatial planning in North Ayrshire.    
Specific engagement has been undertaken with children, young people and
gypsy/travellers. A commitment has been made via the Council’s emerging equality
outcomes to ensure new places, spaces and buildings will be inclusive and designed to
take account of the needs of people with disabilities and other protected characteristics,
including through their engagement in the preparation of LDP3.   
The Planning service has recently engaged with North Ayrshire schools STEAM week which
enables children to apply their science, technology, engineering, and mathematics
knowledge in contexts that make connections between the classroom and the world
around them. This work involves facilitating and participating in workshops in partnership
with the Council’s Education service. 
The Strategic Planning Team has supported six community bodies to prepare a Local Place
Plan (LPP) with all  plans now registered and a further plan expected soon. We have
prepared a ‘Handbook’ to guide community bodies preparing Local Place Plans and
engaged positively to support the preparation of these plans, providing advice and
technical support where required. This has been welcomed by a number of the community
bodies we have supported.  Local Place Plans are now registered for approximately 70% of
the communities of North Ayrshire. This is understood to be unmatched nationally and a
testament to the commitment to the Planning system by communities in North Ayrshire
and the support that they have received from the Planning service working with wider
Council services and specifically community development staff.
176

Page 177

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Improvement Action Plan (Engage theme) 
Attribute Score 
(1=Making excellent progress, 5= No progress) 
9. This planning authority has good customer care 1
10. The planning authority has effective engagement and collaboration with
stakeholders and communities.
1
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/
Medium/ Low) and by when (short/ medium/ long term). 
Improvement Action
What action will you take?
What will the outcome be? 
Owner Importance
High 
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources     
177

Page 178

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
A high performing planning authority should
demonstrate place leadership by taking a collaborative
place-based approach in line with the Place Principle. It
should use the Place and Wellbeing Outcomes in
decision-making processes, to achieve the three spatial
principles outlined in NPF4: Sustainable places, where
we reduce emissions, restore and better connect
biodiversity; Liveable places, where we can all live
better, healthier lives; and Productive places, where we
have a greener, fairer and more inclusive wellbeing
economy. The planning authority should seek to ensure
that there are no impediments to delivering agreed
development. 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Is the planning authority aware of the Place and Wellbeing Outcomes, the evidence
that sits behind them and is it using them in decision-making processes?
YES
• Has the planning authority identified tools and approaches to delivering sustainable,
liveable, and productive places and is implementing them?
YES 
Narrative
In 2024 North Ayrshire Council established a new Communities, Housing and Public
Protection Directorate to provide greater focus on community delivery outcomes. This
has ensured a wider understanding of Place and Wellbeing Outcomes in the Directorate
composition. 
ATTRIBUTE 11: THE PLANNING AUTHORITY SUPPORTS THE
DELIVERY OF SUSTAINABLE, LIVEABLE AND PRODUCTIVE
PLACES
178

Page 179

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Within the Planning service there is a high awareness of Place and Wellbeing Outcomes
by officers and how these should be used in decision-making processes. 
A cornerstone policy in the extant LDP2 is SP1 (Placemaking) and this is an important
foundation on which all decisions are made and the criteria of policy SP1 are consistent
with both NPF4 and Place and Wellbeing Outcomes. 
LDP, NPF4 (combined being the Council’s statutory Development Plan) policies and non-
statutory Supplementary Guidance Place and Wellbeing Outcomes are all used to deliver
sustainable, liveable, and productive places in North Ayrshire. 
The Strategic Planning Team represents North Ayrshire Council as one of three
authorities working in partnership with Public Health Scotland (PHS), the Institute of
Health Equity (IHE) and local NHS health board to form the ‘Collaboration for Health Equity
in Scotland’ (CHES). This partnership aims to help local areas and community planning
partners to strengthen local plans – including LDPs – to reduce health inequalities and
improve wellbeing in their communities. It intends to support local partners to bridge the
gap between national policies and local implementation and understand the actions which
will have the greatest impact on health inequalities locally and help to overcome the
barriers to implementing these. The ultimate goal is to enable people to live longer,
healthier lives by addressing the root causes of health inequalities and preventing illness
before it starts.  
Working alongside colleagues in South Lanarkshire and Aberdeen City, supported by the
Place & Wellbeing Partnership Lead at the Improvement Service & Public Health Scotland,
we are exploring how the associated ‘Marmot 8’ principles along with the Place and
Wellbeing Outcomes can be embedded into both the evidence report and then LDP3.   
179

Page 180

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Please consider the following when thinking about this attribute and how you have performed
over the last year: 
• Has the planning authority provided clear and proportionate expectations of Section 75
agreements and set these out in the LDP and pre-application discussions and they are
concluded within 6 months of resolution to grant?
YES 
• Does the planning authority take a proportionate approach to imposing conditions?
YES - In North Ayrshire, conditions are proportionally applied for every decision
made and no discretionary charging for condition discharge is levied or
proposed as it is considered it would be to the detriment of customer service,
post decision development implementation and therefore community and
economic development.
• Does the planning authority have an ambitious local housing land requirement that
exceeds the Minimum All Tenure Housing land requirements in NPF4 and is it on track
to support delivery? 
YES
• Are the number of processing agreements the planning authority has agreed with
applicants increasing?
NO
• Does the planning authority have an effective delivery programme in place that
supports the delivery of development on the ground?
YES 
Narrative
To support development and regeneration in North Ayrshire the Planning service does not
routinely require developer contributions. The Local Development Plan expects the
majority of new development to be directed towards sites that have infrastructure or
services in place. Where further provision is required, the Supporting Development
Objective: Infrastructure and Services policy within the Adopted Local Development Plan
(p.16) sets out clear and proportionate expectations and the need for relevant
assessments is highlighted alongside each development site where potential
infrastructure deficiencies are known. 
ATTRIBUTE 12: THE PLANNING AUTHORITY SUPPORTS THE
DELIVERY OF CONSENTED DEVELOPMENT
180

Page 181

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
The Planning service has completed its Evidence Report and this is with DPEA at Gate
Check for consideration with a decision expected in April. In preparing the Evidence
Report, a draft Housing Evidence Paper was shared with Homes for Scotland; Registered
Social Landlords operating in North Ayrshire; developers and agents included on the LDP
mailing list; and parties who have approached the Strategic Planning team with an interest
in having housing sites allocated in LDP3. The Housing Evidence Paper was reissued
(without substantive changes) more widely for comment via the LDP Online Hub and
emails to community councils and the remainder of the LDP mailing list.   
The Paper proposes an indicative Local Housing Land Requirement figure of 4,500 homes,
which exceeds the MATHLR by 52.5%. A ‘Call for Ideas’ has been launched which will
assist in the allocation of deliverable land by LDP3 to meet the 10-year Local Housing Land
Requirement. 
A Draft Delivery Programme was submitted to Scottish Government on 8 April 2025, which
takes account of the views of the key agencies and other stakeholders. At this point, we do
not intend to publish the Delivery Programme rather we will seek approval alongside the
Evidence Report later in the year, following the finalisation of the 2024/25 Housing Land
Audit.   
In respect of Development Management, the free pre-application service supports the
submission of planning applications with necessary information provided to aid decision
making outcomes. 
A general presumption against the use of legal agreements minimises decision making
complication and delay 
The number of processing agreements being used is not increasing but continue to be
promoted on the Council’s website and offered where appropriate during the assessment
of planning applications. Limited uptake from applicants is considered to be another
indication of general satisfaction with decision making and the timescales for this as
evidence by demonstrated excellence in decision making performance. 
Processing agreements are automatically entered into for all major applications and some
complex local applications. The number is small annually (generally less than 10) and
dependent on the number of applications received but consistently applied. In addition,
processing agreements will always reasonably be entered into at an applicant’s request for
any application. 
181

Page 182

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
182

Page 183

__________________________________________________________________________________ 
National Planning Improvement | Improvement Service 
Improvement Action Plan (People theme) 
Attribute Score 
(1=Making excellent progress, 5= No progress) 
11. The planning authority supports the delivery of sustainable, liveable and
productive places
1
12. This planning authority supports the delivery of appropriate development 1 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/
Medium/ Low) and by when (short/ medium/ long term). 
Improvement Action
What action will you take?
What will the outcome be? 
Owner Importance
High 
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources     
183

Page 184

NATIONAL PLANNING IMPROVEMENT FRAMEWORK
Improvement Action Plan 2026
North Ayrshire Council 
184

Page 185

A high performing planning authority needs to have the right number of people to do the work expected
of it with the rights skills set. It also needs to have a strategy to ensure that it retains and recruits the right
staff in the future. It supports staff to upskill and to be prepared for changes in policy, legislation, and new
circumstances. 
Attribute Score
(1=Making excellent progress, 5= No progress)
1. The planning authority has sufficient resources and skills to maximise productivity   4
2. The planning authority has a valued and supported workforce   2 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/ Medium/ Low)
and by when (short/ medium/ long term).   
Improvement Action 
What action will you take?
What will the outcome be?
Owner Importance 
High
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources
Service Review Allan Finlayson High Short Internal
Workforce Planning Strategy Allan Finlayson High Short Internal/Peer Review
Enforcement Resourcing Improvement Allan Finlayson High Short 
Development Manager Resourcing Improvement Allan Finlayson Medium Medium 
185

Page 186

A high performing planning authority has a positive culture through ensuring it has sound
governance, effective leadership and a commitment to continuous improvement. The authority has
an identified chief planner, who is supported by a strong leadership group to advise on decision-
making, policy and operational management. 
Attribute Score
(1=Making excellent progress, 5= No progress)
3. This Planning Authority has embedded continuous improvement   1
4. This Planning Authority has sound governance  1
5. This Planning Authority has effective leadership  1 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/ Medium/ Low)
and by when (short/ medium/ long term).   
Improvement Action 
What action will you take?
What will the outcome be?
Owner Importance 
High
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources
Renfrewshire and Inverclyde regional
discussions. Further develop and undertake
meetings with neighbouring Councils to
understand and develop competing or co-
operative regional challenges and opportunities.
Allan Finlayson Medium Short
Chief Planning
Officer and Strategic
Planning Manager
Enforcement Charter Review Allan Finlayson and
Iain Davies High Short 
186

Page 187

A high performing planning authority needs to have an effective local development plan and other
strategies in place to provide a vision for the future of the area. It needs to be able to set and deliver on
policy ambitions and priorities by clearly informing decision making and providing certainty and
predictability for communities, developers and investment. The authority’s development management
systems need to be effective in making the right decisions about development and be as efficient as
possible in doing this. The planning authority makes best use of digital technology and how it manages
and uses data. 
Attribute Score
(1=Making excellent progress, 5= No progress)
6. The planning authority has a robust policy and evidence base  1
7. The planning authority makes best use of data and digital technology   1
8. The planning authority has effective and efficient decision-making processes   2 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/ Medium/ Low)
and by when (short/ medium/ long term).   
Improvement Action 
What action will you take?
What will the outcome be?
Owner Importance 
High
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources
Enforcement Charter Review Allan Finlayson and
Iain Davies High Short 
Enforcement Resourcing Improvement Allan Finlayson High Short 
Development Manager Resourcing Improvement Allan Finlayson Medium Medium 
187

Page 188

A high performing planning authority should ensure a wide range of people are involved in shaping their
future places. Engagement should be fair and inclusive, early, collaborative, meaningful and
proportionate and should include difficult to reach groups. The authority should engage with a wide
range of partners at a national, regional and local level to ensure a joined-up approach and that links are
made across policies and programmes. The planning authority should demonstrate good customer care,
transparency and effective communication. 
Attribute Score
(1=Making excellent progress, 5= No progress)
9. This planning authority has good customer care  1
10. The planning authority has effective engagement and collaboration with stakeholders and
communities.  1 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/ Medium/
Low) and by when (short/ medium/ long term).   
Improvement Action 
What action will you take?
What will the outcome be?
Owner Importance 
High
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources     
188

Page 189

A high performing planning authority should demonstrate place leadership by taking a collaborative
place-based approach in line with the Place Principle. It should use the Place and Wellbeing Outcomes in
decision-making processes, to achieve the three spatial principles outlined in NPF4: sustainable places,
where we reduce emissions, restore and better connect biodiversity; liveable places, where we can all
live better, healthier lives; and productive places, where we have a greener, fairer, and more inclusive
wellbeing economy. The planning authority should seek to ensure that there are no impediments to
delivering agreed development. 
Attribute Score
(1=Making excellent progress, 5= No progress)
11. The planning authority supports the delivery of sustainable, liveable and productive places  1
12. This planning authority supports the delivery of appropriate development  1 
Based on the grading above, outline any areas of improvement that are required and by whom and their level of importance (High/ Medium/
Low) and by when (short/ medium/ long term).   
Improvement Action 
What action will you take?
What will the outcome be?
Owner Importance 
High
Medium
Low
Timescale 
Short term – 1 year
Medium term – 3 years
Long term – 3+ years
Resources     
189

Page 190

_____________________________________________________________________________
Improvement Service | West Lothian Civic Centre, Howden South Road, Livingston, EH54 6FF | 
07742 694468 | craig.mclaren@improvementservice.org.uk | 
Craig Hatton
Chief Executive 
North Ayrshire Council
Cunninghame House
Friars Croft
Irvine KA12 8EE   
Email to craighatton@north-ayrshire.gov.uk 
20 March 2026 
Dear Mr Hatton 
NATIONAL PLANNING IMPROVEMENT FRAMEWORK: IMPROVEMENT ACTION PLAN 
As you may know we have been piloting new arrangements for assessing planning authority
performance and identifying improvement actions through a pilot of a new National Planning
Improvement Framework in 3 cohorts. North Ayrshire Council has now completed this pilot
which has consisted of a self-assessment against 12 attributes of a high performing planning
authority that has in turn allowed for the development of an Improvement Action Plan.   
Please see attached the planning service’s finalised Improvement Action Plan. This will also
be shared with the Minister for Public Finance, who has responsibility for planning within
Scottish Government, and it will be published on the Improvement Service website. I also
attach the Performance Assessment undertaken by the planning service that provided
context to identify improvement actions. I would be very happy to meet with you to discuss
these. 
I hope this is useful but please feel free to contact me if there is anything you would like to
discuss at craig.mclaren@improvementservice.org.uk or on 07742 694468. 
Yours sincerely 
Craig McLaren FRTPI 
National Planning Improvement Champion 
Copied to Allan Finlayson, Chief Planning Officer 
190