Notice of Meeting and Agenda 
Planning Committee 
Venue:  Council Chambers/Hybrid, 
Midlothian House, Dalkeith, EH22 1DN 
Date:  Monday, 09 December 2024 
Time:  13:30 
Executive Director : Place 
Contact:
Clerk Name: Democratic Services
Clerk Telephone: 
Clerk Email: democratic.services@midlothian.gov.uk 
Further Information: 
This is a meeting which is open to members of the public.  
Privacy notice: Please note that this meeting may be recorded. The
recording may be publicly available following the meeting. If you would
like to know how Midlothian Council collects, uses and shares your
personal information, please visit our website: www.midlothian.gov.uk 
Page 1 of 112

Page 2

1          Welcome, Introductions and Apologies   
2          Order of Business 
Including notice of new business submitted as urgent for consideration at the
end of the meeting. 
3          Declaration of Interest 
Members should declare any financial and non-financial interests they have in
the items of business for consideration, identifying the relevant agenda item
and the nature of their interest. 
4          Minute of Previous Meeting
4.1 Minute of Planning meeting of 29 Oct 2024 submitted for approval 3 - 14 
5          Public Reports
5.1 24.00591.PAC - Land at Dalkeith Country Park Report and Plans 15 - 20
5.2 21.00958.PPP - Land At Junction of The A701 and Pentland
Road, Loanhead Appeal Decision and Decision
21 - 36
5.3 24.00537.S36 - Salters Park, Dalkeith BESS Report and Plans 37 - 54
5.4 18.00082.S42 - Upper Dalhousie, Bonnyrigg Areas A & B Report
and Plan
55 - 80
5.5 18.00081.DPP - Upper Dalhousie, Bonnyrigg Areas C Report and
Plans
81 - 112 
6          Private Reports 
No items for discussion 
7          Date of Next Meeting 
The next meeting will be held on Tuesday 21 January 2025. 
Page 2 of 112

Page 3

Minute of Meeting 
Planning Committee
Monday 9 December 2025
Item No: 4.1                                                   
Planning Committee 
Date Time Venue
Tuesday 29 October 2024 13:00 Council Chambers,
Midlothian House/Hybrid   
Present: 
Councillor Alexander (virtual) Councillor Bowen 
Councillor Cassidy  Councillor Curran
Councillor Imrie (Chair) Councillor McEwan
Councillor McKenzie Councillor Pottinger (Virtual
Councillor Smaill Councillor Virgo 
Councillor Winchester 
In Attendance: 
Peter Arnsdorf, Planning, Sustainable Growth and Investment Manager
Derek Oliver Chief Officer Place
Maria Perez Democratic Services Officer
Nicola Thorburn Democratic Services Officer 
Page 3 of 112

Page 4

1. Welcome, Introduction and Apologies 
The Chair welcomed everyone to the meeting of the Planning Committee. 
Apologies were received from Councillor McCall and Councillor McManus. 
2. Order of Business 
Order of Business as per the agenda. 
3. Declarations of interest 
None submitted. 
4. Minutes of Previous Meetings 
4.1 The Minute of the Planning Committee Meeting 10 September 2024 was
submitted and approved as correct record. 
5. Reports 
Agenda No Report Title Submitted by:
5.1 Midlothian Local Development Plan 2017
Delivery Programme
Planning,
Sustainable
Growth and
Investment
Manager
Outline of Report and Summary of Discussion
The Planning, Sustainable Growth and Investment Manager presented the report.
The purpose of the report is to present the Planning Committee with a copy of the
draft Delivery Programme for the current adopted Midlothian Local Development
Plan 2017 (MLDP) prior to it being reported to Council at its meeting of 12 November
2024 with a recommendation to secure authority to engage in a consultation
exercise.
The purpose of the Delivery Programme is to set up how the Local Development
Plan’s Spatial Strategy and development allocations will and have been delivered.
The relevant Acts and associated guidance require the plan to be subject to public
consultation and subject to be approved by Council. The Scottish Government
expectation is that the planning authorities have an adopted development program
by March 2025. The Committee is asked to note and approve the contents of the
report. 
Page 4 of 112

Page 5

The Chair thanked the Planning, Sustainable Growth and Investment Manager for
the report and opened it up for questions. 
Members questioned the value of approving the Development Plan and putting it up
for consultation without having seen the Capital Plan and noted that the two are
intrinsically linked. Decisions on items of the report like Shawfair Primary and
Secondary School provision, which have an estimated completion date 2027/28
pertain to decisions which are part the Capital Plan. Members asked if some aspects
of the Capital Plan would be introduced during the discussion or whether the
Committee is asked to approve the Delivery Programme without the link to the
entirety of the Capital Plan. 
The Planning, Sustainable Growth and Investment Manager acknowledged the
concerns but advised that the Capital Plan is progressed through a different Council
body, and it would not be possible to present the plan at this Committee. Members
advised that while they realise this, they are being asked to make decisions with an
estimated completion date without the full Capital Plan. The Planning, Sustainable
Growth and Investment Manager noted that the Scottish Government has a March
2025 deadline and prior to this it would be subject to a 6-week consultation period. If
Members had reservations regarding the Delivery Programme it will still be possible
to make changes. 
Members reiterated that presenting the Delivery Programme for a decision without
seeing figures on the Capital Plan may result in making decisions that are not
possible to deliver. Furthermore, decisions on schools are not possible to make
without clarity on what the developer contributions are likely to be. 
The Planning, Sustainable Growth and Investment Manager advised that housing
numbers are part of a building program that set the total number of units to be
delivered within a time period.  The report is presenting a picture of the project’s
current status and progress made since 2017 rather than making assumptions of
where it is going in the future or trying to force the Members into decisions. The report
also identifies how developer contributions will be implemented and delivered. 
The Chair acknowledged Members’ reservations but reminded of the Elected
Members’ duty to report to the public on the delivery of the 2017 Midlothian
Development Plan. The Chair also reminded Members that the current discussion
should focus on the delivery of the 2017 Development Plan, not any future plans, 
Members also highlighted matters relating to future infrastructure developments
which were the following. 
• Green belts and coalescence - This is a sensitive matter that needs to be
prioritised. Members referred to a section of the report concerning the success
of the Newbattle Strategic Greenspace Safeguard and asked for information
on it which could be considered by Members as it is relevant to other items on
the agenda and other parts of the county. 
Page 5 of 112

Page 6

• Pupil number projections - Members noted that these are complex which has
resulted in insufficient school provision when Hopefield was built, while other
developments overestimated the number of children per household. Current
data from England and Wales shows that the number of children per
household is dropping drastically, and if this process is replicated in
Midlothian, it may have implications on future school projections and on school
projects. The Chair added that previous housing developments were
dominated by 5-bedroom homes, but the demand has moved towards
bungalows which are more attractive to retired people. Members agreed that
local authorities should be stronger in their ability to demand infrastructures. 
• Members raised the importance of accessible housing in new private
developments as the current offer is almost universally two-story homes. It is
the Council’s responsibility to deliver housing suitable to other needs such as
one-bedroom flats and accessible homes. The availability of accessible
housing should be prioritised in future Development Plans. 
• Transport links within Midlothian – Members noted that while the plan to
extend Edinburgh tram lines to Dalkeith will ensure it is well connected,
Members were concerned of the possible result of bus companies cutting
some bus lines to the detriment of residents.  Members hoped that the Borders
rail may eventually be extended to Penicuik. Members stressed the need to
contact bus companies to ensure there are services linking new developments
as it is more popular now for residents to choose homes which allow them not
to be dependent on car travel. Unfortunately, new build estates have had
issues with buses due to roads adoption. The Chief Officer Place assured
Members that there are ongoing discussions with bus providers regarding
access to new build estates. The Chief Officer Place explained that the
proposed trams extension to Dalkeith, would be an intermodal passenger
transport solution rather than being in competition to existing local bus routes. 
• Proposed future development of Sheriffhall Roundabout - It was confirmed
that the Council Leader has sent a letter to the Transport Secretary to see if
the matter can be resolved, and Members discussed the possible need for an
alternative plan if the project does not go ahead. The funding ringfenced for
this is Midlothian’s fund for its own infrastructure and it is important to ensure
this does not get used by other Councils, as the Scottish Government funds
are allocated specifically to improve Sheriffhall Roundabout.  It will also be
necessary to safeguard the Loanhead corridor as this will facilitate joined up
transportation. 
• Proposed future infrastructure provision of South Mayfield Distributor Road -
Members asked whether there were other easier delivery solutions as it is not
possible to use this protected route. The Planning, Sustainable Growth and
Investment Manager confirmed this road relates to a residential scheme, a
safeguarded route was identified through the site, and permission was granted
in principle without locking in the safeguarded route. 
Page 6 of 112

Page 7

The applicant had demonstrated that alternative arrangements could mitigate
the impact on traffic. Members noted that Councillors from those wards had
stressed the importance of resolving this matter and asked for the report to be
updated to provide more information on this project. 
Members were content with the details provided and agreed to approve the report
with amendments. The amended report will be presented to the December Council
and reviewed by Elected Members before going to public consultation.
Decision
The Planning Committee approved the recommendations with the suggested
amendments before submitting the report to the December Council meeting.
Action
Planning, Sustainable Development and Investment Manager. 
Agenda No Report Title Submitted by:
5.2 Midlothian Local Development Plan 2 Gate
Check Outcome
Planning,
Sustainable
Growth and
Investment
Manager
Outline of Report and Summary of Discussion
The Planning, Sustainable Growth and Investment Manager presented the report.
The purpose of the report is to provide Members with the following updates.
• The outcome of the Scottish Government ‘Gate Check’ process of the Midlothian
Local Development Plan 2  
• The ‘Call for Ideas’ exercise for the Midlothian Local Development Plan 2
• The next steps in the production of the Midlothian Local Development Plan 2 
The evidence report was approved at Council on 25 June 2024 and submitted to the
Scottish Government Planning and Environmental Appeals Division for gate check
and has cleared this process. This decision also validates the Council’s local housing
land requirement for 8851 residential units for the 10 year period. During the summer,
Council also carried out a Call for Ideas exercise to capture the views of local
residents and other interested parties. The report also sets up the following steps of
the Midlothian Local Development Plan 2. 
Members are recommended to note the contents of the report. The Planning,
Sustainable Growth and Investment Manager is happy to discuss the points raised
regarding the green belt, coalescence and accessible housing during the meeting or
after.  The Planning, Sustainable Growth and Investment Manager also highlighted
Page 7 of 112

Page 8

that the previous ceiling of 25% affordable housing has been lifted, there is also
scope for the Elected Members to draft a policy to request that a certain percentage
of new housing is reserved for bungalows. 
The Chair thanked the Planning, Sustainable Growth and Investment Manager for
the report and opened it up for questions. 
Members noted the critical tone of the Reporter’s feedback and asked whether the
action should be taken to address points made by the Reporter and respond with a
timescale. The Planning, Sustainable Growth and Investment Manager noted that
this is a new process, and Midlothian is the second Council to complete it. The
Planning, Sustainable Growth and Investment Manager explained that the critical
tone may be explained by the need for further work on the areas raised by the
Reporter. 
Members asked whether there would be a penalty if the house building quotas are
not met, and expressed surprise at finding out there had not been engagement with
Sport Scotland as leisure facilities are a basic need for communities. The Planning,
Sustainable Growth and Investment Manager responded that there is no financial
penalty but that it is necessary to deliver targets as otherwise there is a risk of losing
control of development and planning permission being ranted on appeal.  The matter
of engagement with Sport Scotland has also been addressed since the feedback
from the Reporter was received. 
Members also asked whether there is a statutory duty to provide public
conveniences. It was clarified that legislation requires the provision to be considered
as part of the local plan preparation. 
Members highlighted the comments in the report regarding school projection rolls
and asked if the projected figure of children per household is correct considering the
volume of 5-bedroom houses.  The Planning, Sustainable Growth and Investment
Manager agreed with the need to carefully manage data and trends to ensure that
school roll projections are correct and up to date. 
Members also asked for clarification on the role of Homes for Scotland within the
process. The Planning, Sustainable Development and Investment Manager
explained this is an umbrella group which represents the national house builders and
their interests.  Members asked for reassurance that Homes for Scotland is not
lobbying for a relaxing of housing regulations. The Planning, Sustainable Growth and
Investment Manager confirmed that they are a lobby group, and the Scottish
Government also uses them to engage with the building industry. 
Members noted that there are no issues reported in connection with joined up
infrastructure and public transport among the unresolved matters commented by the
Reporter. The Planning, Sustainable Growth and Investment Manager explained that
the report only covers those items identified by the Reporter and that the plan is at a
very early stage. 
Page 8 of 112

Page 9

Members noted the recommendations set on the Midlothian Local Development Plan
2.
Decision
The Planning Committee noted the recommendations as set out in the report.
Action
Planning, Sustainable Growth and Investment Manager 
Agenda No Report Title Submitted by:
5.3 Housing Land Audit 2024 Planning,
Sustainable
Growth and
Investment
Manager
Outline of Report and Summary of Discussion
The Planning, Sustainable Growth and Investment Manager presented the report
which presents the 2024 Housing Land Audit and updates the Committee on the
state of the housing land supply position in Midlothian for the period between 1 April
2023 and 31 March 2024. An annual land audit is how a Local Authority can
determine land supply, and it is used to form infrastructure providers like NHS and
Scottish Water in sites and assist in planning facilities like schools and ensures good
management while avoiding planning by appeal.  The Housing Land Audit indicates
how many houses are built per year and how much stock remains to be built from
site allocations and planning permissions granted. The number of units built is agreed
with Homes for Scotland and the report has identified 10,863 units as of 31 March
2024. The requirement for the next Midlothian Local Development Plan is for 8,851
houses over 10 years and the Housing Land Audit states this requirement should be
met. It is recommended that the report is noted, and the Committee agrees to its
publication. 
The Chair thanked the Planning, Sustainable Growth and Investment Manager for
the report and opened it up for questions. 
Members noted mentions of NHS and Scottish Water in the report and highlighted
previous issues engaging with the various bodies within NHS at an early stage of the
gate check process. Members asked if there is anything that could be done to
guarantee access to infrastructures in newly developed areas and ensure the
services like NHS have a plan for delivery. The Planning, Sustainable Growth and
Investment Manager advised that since going through the Gate Check process there
has been a constructive working relationship developed with NHS providers on what
information they require, and progress has been made in the right direction. 
Members noted that Scottish Power is another actor to consider as some sites can
only be served by Scottish Power. Members asked whether all infrastructure
Page 9 of 112

Page 10

providers can be approached with the expectation that they will deliver services to
approved development sites and that this responsibility does not lie with the Council. 
Members also noted discrepancy in some figures on page 127 and asked for the
report authors to review and confirm that this will not affect the delivery of social
housing. Members also noted that the biggest concentration of social housing is in
the Bilston and Roslin areas, asked whether these are well marketed and accessible
to Midlothian people. The price of homes in Midlothian is seen as attractive compared
to other areas but there were concerns if the new homes in Midlothian are affordable
to the people who already live in the area. The Planning, Sustainable Growth and
Investment Manager noted that the overall completion rates show that the number of
houses coming up has reduced, but despite fluctuation the trend is up. Compared to
other years, the proportion of affordable housing is the highest, but it is not clear
whether this trend will be repeated in future years as it depends on the progression
of the developers’ projects. The Planning, Sustainable Growth and Investment
Manager also clarified that the location of the houses and their price is market driven
and outwith the control of the Council. Members expressed concern that most of new
builds are not affordable to first time buyers. 
Members noted that many sites are nearing full planning consent and completion
dates, and that it is imperative to draw partners like NHS in when considering
planning applications for sites and ask them to comment on proposed developments.
The Planning, Sustainable Growth and Investment Manager acknowledged this is
always a difficulty, as it is possible to consult bodies but not possible to control when
they will respond. This puts the local authority in a difficult position as waiting for
responses to make the best decisions will delay the next phase of the plan. 
Members reiterated the need for more diversified housing like bungalows and
assisted living facilities and asked whether there is sufficient land to address this.
The Planning, Sustainable Growth and Investment Manager stated the next draft of
the policy will be amended to ensure it contains the right provision that meets the
residents’ needs, i.e. affordable housing or accessible housing. The current report
suggests there is a significant amount of housing supply in the district to meet the
shortfall. 
Members noted a discrepancy in table 7 of the report and asked if tables are
automatically updated. The Planning, Sustainable Growth and Investment Manager
confirmed that tables are updated once a year and that there is a separate data for
the employment sites which are not covered in the Housing Land Audit. 
The Committee noted the report and agreed on its publication on the Midlothian
Council’s Website.
Decision
The Planning Committee noted the report and agreed on its publication on the
Midlothian Council’s Website. 
Action
The Planning, Sustainable Growth and Investment Manager
Page 10 of 112

Page 11

Agenda No Report Title Submitted by:
5.4 Unit 9 Ramsay Colliery, Loanhead Appeal
Decision (2200878DPP)
Planning,
Sustainable
Growth and
Investment
Manager
Outline of Report and Summary of Discussion
The Planning, Sustainable Growth and Investment Manager presented the report.
The purpose of the report is to advise the Committee of a planning permission appeal
decision regarding a part retrospective change of use from scrap yard to waste
transfer site and contractors’ yard and associated groundworks and construction land
at Unit 9, Ramsay Colliery, Engine Road, Loanhead.
Planning application 22/00878/DPP was considered by the Committee at its meeting
of 12 March 2024 and refused. The applicant submitted an appeal on 28 June 2024
and a Scottish Government Reporter was appointed to consider the appeal. After a
site visit the appeal was upheld by the Reporter and planning permission granted on
20 September 2024. 
The Chair thanked the Planning, Sustainable Growth and Investment Manager and
noted the contents of the report.
Decision
The Planning Committee noted that appeal concerning retrospective change of use
of the site at Unit 9 Ramsay Colliery, Loanhead (Application 2200878DPP) was
upheld and planning permission was granted on 20 September 2024. The contents
of the report were noted. 
Action
The Planning, Sustainable Growth and Investment Manager 
Agenda No Report Title Submitted by:
5.5 Land north of Crichton Village, Pathead
(24/00411/DPP)
Planning,
Sustainable
Growth and
Investment
Manager
Outline of Report and Summary of Discussion
The Planning, Sustainable Growth and Investment Manager presented the report.
The purpose of the report is to discuss a planning application for the erection of a
dwellinghouse at land north of Crichton Village, Pathhead. The site is located within
the Borthwick and Crichton Conservation Area and Special Landscape Area.  A site
visit was carried out by Elected Members on 28 October 2024. 
Page 11 of 112

Page 12

The proposed house is a 2-story dwelling, with a second floor in the roof space, a
dormer window and roof lights letting light into the second floor. The building
comprises of a pitched roof main structure with a porch main entrance. The building
is of contemporary design covered in timber cladding and corrugated metal roof
material. The proposed development also includes provision of additional shed and
heat pump, landscaping and parking area. 
The application treads a fine line between restricting development in the countryside,
especially in sites with limited access to public transport and supporting small side
incremental housing development by allowing development of small villages hamlets
and clusters of dwellings classed as being in the countryside. Crichton can support
3 additional residential units during the Local Development Plan period, but no new
houses have been built under this principle yet. The project appears acceptable
based on proximity to existing dwellings and relationship to landscape. A prior
permission was granted for this site in 2018 but not implemented, and this shows the
Council’s predisposition for a dwelling on this site. While the dwelling is of a
contemporary style it references traditional styles and will add to the interest of
Crichton Conservation Area. National policies allow the use of modern architectural
styles to support the evolution of conservation areas. There have been six
representations, five supporting, one objecting and two consultation responses. The
recommendation is to grant planning permission subject to the conditions specified
in the report.
The Chair thanked the Planning, Sustainable Growth and Investment Manager for
the report and opened it up for discussion.
Some Members noted that the house is in a conservation area where there has not
been a new build in 140 years, and that there was a prior planning application
submitted for a far more impressive home which was described as wrong for the
location when it was originally presented. This application has since been replaced
by the current application for a more modest dwelling in a smaller site.   Members
highlighted that per the planning regulations, a new built dwelling must be close to
local transport. The policies also note that the site should be contained unless it is
on agricultural land, but the application is for a fenced house on agricultural land.
Members were urged to act in a responsible way as it sets a worrying precedent
particularly considering that in 2009 there was a total ban on any new buildings on
Crichton.
Members also highlighted the archaeological and heritage conservation aspects to
be considered as the build is close to known archaeological sites, and Crichton
Village is the location of one of the two works of the Victorian architect Sir Robert
Rowand Anderson which remain in Midlothian.
Members pointed out that in the materials for the proposed application it states that
the home will have a corrugated metal roof which may stick out as the other buildings
Page 12 of 112

Page 13

in Chrichton have a slate roof. Councillor Smaill proposed to make it a condition that
the site should have a slate roof as there is precedent for corrugated metal roofs not
being deemed appropriate for conservation areas. Some Elected Members
expressed their support for the proposal that the application is amended to make it a
condition that the roof is slated.
Some members stated that while Crichton Village may be a conservation area
Midlothian is not a museum, and that Crichton’s beauty will not be affected by this
build particularly since the house is out of view. Besides there are other merits to this
application such as bringing affordable housing to the area. 
The Chair asked whether it would be possible to make the application subject to the
condition that the project is given a slated roof. The Planning, Sustainable Growth
and Investment Manager stated that while there are some traditional elements, the
house in fact has a very contemporary look and it may not be appropriate to put a
slated roof on a modern design building.
The Commitee was called to a vote on whether to grant planning permission on the
application subject to the conditions specified in the original report as moved by
Councillor McKenzie and seconded by Councillor Cassidy, or with the proposed
amendment to change the roof material from corrugated metal to slate, as suggested
by Councillor Smaill and seconded by Councillor Bowen.
The Commitee voted by a 2:1 majority to grant planning permission subject to the
conditions specified in the original report. 
Decision
The Planning committee agreed to grant planning permission to application
(24/00411/DPP) subject to the conditions specified in the report.
Action
The Planning, Sustainable Growth and Investment Manager 
6. Private Reports 
No items for discussion 
7. Date of Next Meeting 
The next meeting will be held on Tuesday 3 December 2024 at 1:00 pm. 
The meeting terminated at 14.33 pm. 
Page 13 of 112

Page 14

Page 14 of 112

Page 15

Planning Committee 
Monday 9 December 2024
Item No 5.1
PRE - APPLICATION REPORT REGARDING HOLIDAY
ACCOMMODATION DEVELOPMENT INCLUDING COMMUNAL
FACILITIES, FORMATION OF ACCESS, LANDSCAPINNG AND
ASSOCIATED WORKS AT LAND AT DALKEITH COUNTRY PARK,
DALKEITH (24/00591/PAC)
Report by Chief Officer Place
1 PURPOSE OF REPORT
1.1 The purpose of this report is to advise the Committee of the
submission of a Proposal of Application Notice (PAN) and
corresponding pre application consultation for holiday accommodation
development including communal facilities, formation of access,
landscaping and associated works at Land at Dalkeith Country Park
Dalkeith.
1.2 The pre-application consultation is reported to Committee to enable
Councillors to express a provisional view on the proposed major
development. The report outlines the proposal, identifies the key
development plan policies and material considerations and states a
provisional, without prejudice, planning view regarding the principle of
development.
2 BACKGROUND
2.1 Guidance on the role of Councillors in the pre-application process,
published by the Commissioner for Ethical Standards in Public Life in
Scotland, was reported to the Committee at its meeting of 30 August
2022. The guidance clarifies the position regarding Councillors
stating a provisional view on proposals at pre-application stage.
2.2 A pre-application consultation for holiday accommodation
development including communal facilities, formation of access,
landscaping and associated works at Land at Dalkeith Country Park,
Dalkeith was submitted on 18 September 2024. The applicant is
MDS Estates Ltd.
2.3 As part of the pre-application consultation process, two public
events have been held at The Loft, Dalkeith Country Park, Dalkeith. 
The first was held on Thursday 3 October 2024 and the second was
on Wednesday 6 November 2024; these events were advertised via
the Midlothian Advertiser (at least 7 days prior to each event).  The
applicant has also created a dedicated website which provides
Page 15 of 112

Page 16

further information on the proposed development, a copy of the
consultation boards used at the public events, a contact email
address and phone number for members of the public who want to
get in contact for further information or enquiries.  Upon the
conclusion of the public events/engagement the applicant could
submit a planning application for the proposal.
2.4 An applicant must wait 12 weeks from the date of submission of a PAN
before submitting a planning application. The earliest date that the
planning application for this proposal could be submitted is 11
December 2024. The subsequent planning application must be
accompanied by a Pre-Application Consultation Report detailing the
consultation undertaken, a summary of written responses and views
expressed at the public events, an explanation of how the applicant
took account of the views expressed and an explanation of how
members of the public were given feedback on the applicant’s
consideration of their views.
2.5 Copies of the pre application notices have been sent by the
prospective applicant to the local elected members in Ward 3 -
Dalkeith, the Dalkeith Community Council, the local MP and the
local MSP(s).
2.6 It is reasonable for an Elected Member to attend one of the events
without a Council planning officer present, but the Member should (in
accordance with the Commissioner’s guidance reported to the
Committee at its meeting in August 2022) not offer views, as the forum
for doing so will be at meetings of the Planning Committee.
2.7 It is noted that two representations (one objection and one neutral)
were received via the planning portal for this proposal of application
notice. These representations will be forwarded onto the applicant to
be taken into consideration and included in their Pre-Application
Consultation Report. 
3 PLANNING CONSIDERATIONS
3.1 In assessing any subsequent planning application, the main planning
issue to be considered in determining the application is whether the
proposed development complies with development plan policies unless
material planning considerations indicate otherwise.
3.2 The development plan is comprised of National Planning Framework 4
(2023) and the Midlothian Local Development Plan (2017).
3.3 The application site is situated within Dalkeith Country Park, an 800-
hectare estate situated at the northern edge of Dalkeith.  The Country
Park comprises a designed landscape, woodlands and farmlands
associated with Dalkeith Palace.  The application site is approximately
550m east and north-east of Dalkeith Palace and to the east and north
of the Restoration Yard (a shop, cafe, restaurant and wellness clinic
situated within the converted and extended category A listed former
stables), Fort Douglas (a children’s adventure playground situated
Page 16 of 112

Page 17

within an area of woodland) and Go Ape (a high ropes adventure
course in woodland to the north of Fort Douglas).
3.4 The application site measures approximately 41.7 hectares and
comprises of grassed fields to the immediate west of Salters Road and
a sloping grass field situated on raised ground at a meander in the
River South Esk.  The site is bounded to the north, west and south by
steeply sloping wooded banks of the river.  There is an additional area
of woodland to the north-east of the site.  There is a tarmacadam
access road from the restoration yard to the south that runs through
the site. The eastern boundary of the site is defined by a high natural
stone wall and Salters Road.  The rest of the boundaries of the site are
defined by a combination of stock fencing and hedgerows.
3.5 The relevant policies of the Midlothian Local Development Plan 2017
(MLDP) are RD4 - Country Parks; VIS2 - Tourist Accommodation;
DEV5 - Sustainability in New Development; DEV6 – Layout and
Design of New Development; DEV7 – Landscaping in New
Development; DEV9 Open Space Standards; TRAN5 – Electric
Vehicle Charging; IT1 – Digital Infrastructure; ENV1 - Protection of the
Green Belt; ENV4 - Prime Agricultural Land; ENV7 – Landscape
Character; ENV8: Protection of River Valleys; ENV9 – Flooding,
ENV10 – Water Environment; ENV14 - Regionally and Locally
Important Nature Conservation Sites; ENV15 – Species and Habitat
Protection and Enhancement; ENV20 - Nationally Important Gardens
and Designed Landscapes and ENV22 – Listed Buildings.
3.6 The relevant policies of the National Planning Framework 4 (NPF4) are
Policy 1 - Tackling the climate and nature crises; Policy 2 - Climate
mitigation and adaptation; Policy 3 – Biodiversity; Policy 6 - Forestry,
woodland and trees, Policy 7 – Historic Assets and Places, Policy 8 -
Green belts, Policy 14 - Design, quality and place; Policy 22 - Flood
risk and water management; Policy 29 - Rural development; and Policy
30 – Tourism.
3.7 The views of consultees and representors will be material
considerations in the assessment of an application for the proposed
development.  The site is within a protected landscape, the Dalkeith
Country Park and the green belt, however the Park is host to a
number of visitor facilities and as such there is scope for tourist
accommodation and associated development to be supported as
long as it is related to an existing development, is for the
furtherance of a viable long-term business and is of a character and
scale that is in-keeping with its rural setting.
3.8 Detailed consideration will have to be given to design matters, in
particular the developments relationship to the garden and designed
landscape, the setting of listed buildings, the site layout, the siting,
design and appearance of the holiday accommodation and other
structures, the materials used, landscaping, impact on trees, parking
provision and road safety, flood risk mitigation, biodiversity and
sustainability in order to ensure compliance with sustainable place-
making policies within the MLDP and NPF4.  It will also be necessary
Page 17 of 112

Page 18

to consider the impact of the proposed development on the amenity
of neighbouring residents and other land uses, the local
road/transport infrastructure and active travel arrangements.
4 PROCEDURES
4.1 The Scottish Government’s Guidance on the Role of Councillors in
Pre-Application Procedures provides for Councillors to express a
‘without prejudice’ view and to identify material considerations
regarding a major application.
4.2 The Committee is invited to express a ‘without prejudice’ view and to
raise any material considerations which they wish the applicant and/or
officers to consider. Views and comments expressed by the
Committee will be entered into the minutes of the meeting and relayed
to the applicant for consideration.
4.3 The Scottish Government’s Guidance on the Role of Councillors in
Pre-Application Procedures advises that Councillors are expected to
approach their decision-making with an open mind in that they must
have regard to all material considerations and be prepared to change
their views which they are minded towards if persuaded that they
should.
5 RECOMMENDATION
5.1 It is recommended that the Committee notes:
a) the provisional planning position set out in this report;
b) that any comments made by Members will form part of the minute
of the Committee meeting; and
c) that the expression of a provisional view does not fetter the
Committee in its consideration of any subsequent formal planning
application.
Peter Arnsdorf
Planning, Sustainable Growth and Investment Manager
Date: 22 November 2024
Application No: 24/00591/PAC
Applicant:  The MDS Estates Limited
Agent: Andrew Munnis
Validation Date: 19 September 2024
Contact Person: Whitney Lindsay
Email:  Whitney.Lindsay@midlothian.gov.uk
Attached Plans: Location Plan and Indicative Layout Plan
Page 18 of 112

Page 19

N
Midlothian Council
Fairfield House
8 Lothian Road
Dalkeith, EH22 3AA
Reproduced from the Ordnance Survey map with the
permission of the controller of Her Majesty's Stationary Office.
Crown copyright reserved. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil
proceedings.
Planning Service
Place Directorate
Midlothian Council Licence No. AC0000811376 (2024)
Proposal of application notice for holiday
accommodation development including communal
facilities, formation of access, landscaping and
associated works.
Land at Dalkeith Country Park, Dalkeith
File No. 24/00591/PAC
Scale 1:7000Page 19 of 112

Page 20

gate
welcome building
51 Lodges
49 Lodges
14
Lodges
5
Lodges
5 Lodges
7 Lodges
14 Lodges
13
Lodges
15
Lodges
15
Lodges
5 Lodges
6 Lodges
Main
Entrance
AREA IN ABEYANCE
2000
3700
5500 - Proposed Two Way Road
- Fire Tender Access
- Proposed Footpath
Key
- Proposed Bin Store
- Proposed SuDs feature
- Parking Space (331 No.)
- Proposed Swale Network
(surface tbc by Lanarca)
(surface tbc by Lanarca)
(surface tbc by Lanarca) (surface tbc by Lanarca)
- Existing Road - Existing Planting/Trees
- Proposed Planting/Trees
- Existing Structures Removed
- Electrical Sub Station
(tbc by Wallace Whittle)
SUB
STATION
- Proposed Fire Extinguisher Point
(tbc by Wallace Whittle)
FP
- Proposed Low Level Light Bollards
(tbc by Wallace Whittle)
- Proposed Lodge Path
(surface tbc by Lanarca)1200
- River South Esk
- Proposed 1.2m Retention Wall
- Twin Pitch Lodges
Lodge Types
6100
12200
4300
13000
- Center Loaded Lodges
Project Code - Originator - Functional Breakdown - Spatial Breakdown - Form - Discipline - Number
Status
Title
Project
T +44 (0) 20 7287 0735
www.holdermathias.com
London   Cardiff   Munich
Please consider the  environment before printing this document
Refer to dimensions where provided - do not scale from this drawing
ISO 14001 : 2015   ISO 9001 : 2015   RIBA Chartered Practice
Job No RevisionScale at
Rev. Status Date          Check Description      
A0 Classification
S0As indicated4681
DKCP-HMA-ZZ-ZZ-D-A-00111
Site Plan
Dalkeith Country Park
Dalkeith
Buccleuch Estates Ltd
P09PM-xx-xx-xx
P01 S0 26.07.24 JH First Issue
P02 S0 30.07.24 JH Drawing Number Amended
P03 S0 01.08.24 JH Layout Development Based on Consultants
Input and Tree Survey
P04 S0 28.08.24 JH Layout Updated
P05 S0 09.09.24 JH Layout Updated
P06 S0 18.09.24 JH Connection to roundabout added
P07 S0 08.11.24 JH Layout Development Based on Consultants
Input
P08 S0 11.11.24 JH General Amendments
P09 S0 14.11.24 SR Draft Issue for Planning
1 : 1000
Site Plan1
Maintenance &
Housekeeping
Buildings
Welcome Building
with 12 guest
parking spaces
Low point
SUDS
SUDS Low point
Waste Collection Area
0
SCALE 1:
504030201010
m1000
N
DRAFT
Lodge Numbers
Type Count
Center Loaded 120
Twin Pitch 80
Grand total 200
Parking Schedule
Use Count
Entrance Parking 12
Lodge Parking 316
Grand total 328
Page 20 of 112

Page 21

Planning Committee
Monday 9 December 2024
Item No 5.2
PLANNING PERMISSION APPEAL DECISION WITH REGARD TO
APPLICATION 21/00958/PPP FOR A MIXED-USE DEVELOPMENT
COMPRISING CLASS 2 (PROFESSIONAL SERVICES), CLASS 8
(RESIDENTIAL INSTITUTIONS), CLASS 9 (RESIDENTIAL), CLASS 10
(NON-RESIDENTIAL INSTITUTIONS), SUI GENERIS (MIXED USE OF
RETIREMENT FLATS AND ASSISTED LIVING/EXTRA CARE FLATS),
AFFORDABLE HOUSING AND ASSOCIATED WORKS AT LAND AT THE
JUNCTION OF THE A701 AND PENTLAND ROAD, OLD PENTLAND,
LOANHEAD. 
Report by Chief Officer Place
1 PURPOSE OF REPORT
1.1 The purpose of this report is to advise the Committee of a planning
permission in principle appeal decision with regard to an application for
planning permission in principle for a mixed-use development
comprising Class 2 (professional services), Class 8 (residential
institutions), Class 9 (residential), Class 10 (non-residential
institutions), Sui Generis (mixed use of retirement flats and assisted
living/extra care flats), affordable housing and associated works at land
at the junction of the A701 and Pentland Road, Old Pentland,
Loanhead.
2 BACKGROUND
2.1 Planning application 21/00958/DPP was considered by the Committee
at its meeting of 30 August 2022.  The application was refused for the
following reasons:
1. The majority of the application site is designated as countryside in
the Midlothian Local Development Plan 2017. The proposed
development is not for the furtherance of an established rural use
and will not be of a rural scale and character. The proposal is
contrary to policy RD1 of the Midlothian Local Development Plan
2017.
2. The indicative allocation of uses and floorspace for the land within
the built-up area of Loanhead will create a scale and density of
development that will have a significant detrimental impact on the
character and amenity of the surrounding area and the residential
amenity of the residential park homes in Pentland Park. The
Page 21 of 112

Page 22

proposal is contrary to policies DEV2 and DEV4 of the Midlothian
Local Development Plan 2017.
3. Development of an unallocated site that is adjacent to the
undeveloped allocated site (Ec3 - West Straiton) will delay the early
implementation of the allocated development site. The proposal is
contrary to policy STRAT5 of the Midlothian Local Development
Plan 2017.
4. The development does not accord with policies DEV3, IMP1 and
IMP2 of the Midlothian Local Development Plan 2017 as it does not
commit to deliver the required provision of affordable housing and
developer contribution requirements towards infrastructure for new
development.
2.2 The decision notice was issued on 1 September 2022 and the
applicant submitted an appeal on 28 November 2022. A Scottish
Government Reporter was appointed to determine the appeal and
following a site visit and procedural delays (see paragraph 2.3 below)
the appeal was refused on 16 October 2024.  A copy of the appeal
decision is attached to this report as Appendix A.
2.3 Following the adoption, by Scottish Ministers, of National Planning
Framework 4 (NPF4) in February 2023 the Reporter requested further
submissions from the applicant, the Council and other interested
parties.  After the NPF4 submissions the appeal was twice put on hold
to allow for the Scottish Ministers and then the Court of Session to
assess an application in West Lothian, which had implications for the
interpretation of windfall housing policies in NPF4.
3 THE DECISION
3.1 In considering the appeal the Reporter concluded that the proposal
was contrary to the following NPF4 and Midlothian Local Development
Plan 2017 (MLDP) policies:
NPF4 Policy 5 Soils
NPF4 Policy 14 Design, quality and place
NPF4 Policy 15 Local living and 20 minute neighbourhoods
NPF4 Policy 16 Quality homes
NPF4 Policy 17 Rural homes
MLDP Policy DEV2 Protecting Amenity within the Built-Up Area
MLDP Policy RD1 Development in the Countryside
MLDP ENV4 Prime Agricultural Land
3.2 In considering the principle of development the Reporter reached the
following conclusions:
“The proposed uses are a veterinary practice (class 2 at the time of the
application, but now class 1A), community use building (class 10),
Page 22 of 112

Page 23

affordable housing (class 9), public green space, SuDS and
landscaping.  I do not find that any of these elements, particularly the
built aspects, would be for the furtherance of an established
countryside activity.  The proposed public green space is intended to
replace existing open spaces for users of Pentland Park and hence I
do not consider its purpose is for countryside recreation.”
“The area of land is relatively small (0.4 ha) and may not have been
actively farmed for some time. Nevertheless, it currently contributes to
the agricultural land bank and its potential use for agriculture would be
lost as a result of the proposals. I therefore conclude that it fails to
satisfy the provisions of policy ENV4 of MLDP or policy 5 of NPF4.”
“The affordable housing, which lies outwith the built-up area also
requires to be considered in relation to policy 17 – Rural homes of
NPF4. The proposal is not on a site allocated for housing within the
LDP, does not represent reuse of a brownfield site or redundant
building, is not necessary to support management of a viable rural
business, nor is it for a single home or for the subdivision of an existing
residential dwelling or reinstatement of a former dwelling house.  I have
also concluded above that the proposals would not be particularly well
placed to contribute towards local living.  I therefore conclude that it
would fail to satisfy the requirements of policy 17 of NPF4.”
3.3 In considering whether the proposal is supported by policies relating to
windfall housing the Reporter reached the following conclusions:
“Given that much of the proposed housing is specifically targeted at
older populations or those requiring assisted living, I find that the
proposals are not well-located to accord with the intent of this policy.
Thus, the proposals do not satisfy the requirements of policy 15 or
meet the exceptions set out in part f) (ii) of policy 16.”
“I consider that these would not meet the definition of a smaller scale
opportunity.  Parts of the proposal fall outwith the settlement boundary,
and these are not consistent with the policy on rural homes.  Whilst I
recognise that the proposal is for the delivery of less than 50 affordable
homes, these are not part of a local authority supported affordable
housing plan.  I therefore conclude that the proposals fail to meet the
exceptions set out in part f) (iii).  Overall, they fail to meet any of the
locational requirements set out in policy 16.”
“I conclude that the proposals gain support from part c) and to a lesser
extent, part e) of policy 16, but fail to satisfy parts a) or f).  Policy 16
does not explicitly identify parts c) and e) as additional circumstances
to those set out in part f) where new homes on unallocated land may
be acceptable.  Nevertheless, they indicate the importance placed on
provision of these types of housing. I do not, however, accept the
appellant’s view that the nature of the proposed housing means that I
can disregard the locational criteria set out in parts a) and f).  The
Page 23 of 112

Page 24

intent of policy 16 is “to encourage, promote and facilitate the delivery
of more high quality, affordable and sustainable homes, in the right
locations, providing choice across tenures that meet the diverse
housing needs of people and communities across Scotland”.  Thus,
whilst the policy seeks high quality and affordable homes, these must
be “in the right locations”, maintaining a locational element to the
assessment.  It may be that there would be occasions where the
weight given to the types of housing under parts c) and/or e) was
considered sufficient to overcome any conflict with part f) and allow a
conclusion of overall compliance with policy 16.  However, I am not
persuaded that such a conclusion would be valid in this case.  The site
is not particularly well positioned to promote local living and 20 minute
neighbourhoods.  There is also no evidence as to why the proposals
could not be accommodated in other locations, including land adjacent
to the proposal site, which is allocated within the MLDP for mixed-use
development.”
“In reaching a conclusion on this matter, I have considered the terms of
The Chief Planner’s letter (26 June 2024), which was published to
provide clarification on the application of NPF4.  This indicates that the
different parts of policy 16 “should be weighed up as relevant to the
proposal; there is no hierarchy and no one part of policy should always
outweigh others.  A balanced planning judgement should be reached in
each case.” I have considered both the locational aspects of the
proposal (parts a) and f)) and the relevant criteria relating to the types
of housing (parts c) and e)).  I conclude, that whilst the proposals gain
some support from parts c) and e) of policy 16, this support is
tempered when considered within the context of policy 16 as a whole
and is not sufficient for me to conclude that the proposal accords
overall with policy 16.”
3.4 In considering the effect of the proposals on the character and amenity
(including residential amenity) of the surrounding area the Reporter
reached the following conclusions:
“I conclude that the cumulative scale and density of development at the
southern end of the site would be detrimental to the character of the
area and residential amenity of Pentland Park and hence would be
inconsistent with policy DEV2 of the MLDP. For similar reasons, I find it
would also fail to be consistent with policy 14 of NPF4.”
3.5 In considering whether the proposal would satisfy requirements for
contributions to affordable housing and infrastructure the Reporter
reached the following conclusions:
“Had I been minded to allow the appeal I am satisfied that there would
have been a strong likelihood of reaching an agreement on these
matters.”
Page 24 of 112

Page 25

3.6 In considering whether development on an unallocated site would
delay early implementation of an adjacent allocated site the Reporter
reached the following conclusions:
“Development at Ec3 is dependent on the construction of the A701
Relief Road. The council has confirmed its continuing commitment to
the proposals, and I note the recent initiatives to progress the wider
scheme. I accept that delivery of proposals for this site may therefore
be delayed until the road is implemented.  Nevertheless, I do not see
this as justification for development on an adjoining, unallocated site.”
3.7 In assessing other considerations, the Reporter reached the following
conclusions:
“The appellant has referred to information relating to housing land
supply contained in the Evidence Report for the review of the MLDP,
suggesting that supply may need to be increased and that there is a
heightened need and demand within the affordable and specialist
housing sectors.  I note that these figures have been collected to
inform an updated version of the MLDP, including allocation of suitable
sites, rather than to guide development management decisions.
Nevertheless, the council has indicated that through its Evidence
Report, it has agreed a Local Housing Land Requirement of 8,851
homes.  This exceeds the MATHLR, albeit by a single unit.  I therefore
conclude that the current supply of housing land exceeds the
MATHLR.”
“I have also considered the Scottish Government’s declaration of a
housing emergency, as an important material consideration.  The
declaration makes specific reference to affordable housing.  As the
proposals include 10 affordable homes, the proposals gain some
support from this.  However, it does not appear to me that a shortage
of housing land has been identified as an important contributory factor
to the emergency. In any case, based on the figures above, it appears
that adequate housing land has been allocated within Midlothian and
there are policies within the MLDP, which provide for affordable homes
as part of development proposals.  Furthermore, I am not aware of any
ministerial statement or instruction requiring departure from
development plans in the light of the housing emergency.  Therefore, I
find that the declaration of the housing emergency does not justify a
departure from the development plan in this instance.”
“In summary, the proposals would make a small, but valuable
contribution to the supply of affordable housing in Midlothian, for which
there is a recognised demand.  However, there are existing
mechanisms to provide for affordable housing on the already allocated
sites, there appear to be sufficient allocated sites, and there is no
indication that such windfall sites are necessary to meet the demand –
even when considered within the context of a declared national
housing emergency and need for affordable housing.  As such, I
Page 25 of 112

Page 26

conclude that any benefits in terms of the types of homes provided by
the proposals would not be sufficient to overcome the policy tensions
identified above.”
“I have considered the economic benefits of the scheme.  However, I
am not persuaded that these benefits are sufficient reason to consent
commercial development on an unallocated site, particularly given the
proximity of an already allocated and undeveloped site on the opposite
side of Pentland Road.”
3.8 In reaching her decision the Reporter reached the following
conclusions:
“I conclude that the proposed development does not accord overall
with the relevant provisions of the development plan and that there are
no material considerations which would still justify granting planning
permission.  I have considered all the other matters raised, but there
are none which would lead me to alter my conclusions.”
4 RECOMMENDATION
4.1 It is recommended that the Committee notes the planning permission in
principle appeal decision with regard to an application for planning
permission in principle for a mixed-use development comprising Class
2 (professional services), Class 8 (residential institutions), Class 9
(residential), Class 10 (non-residential institutions), Sui Generis (mixed
use of retirement flats and assisted living/extra care flats), affordable
housing and associated works at land at the junction of the A701 and
Pentland Road, Old Pentland, Loanhead. 
Peter Arnsdorf
Planning, Sustainable Growth and Investment Manager
Date:    22 November 2024
Contact Person: Graeme King 
graeme.king@midlothian.gov.uk
Page 26 of 112

Page 27

Planning and Environmental Appeals Division
Hadrian House, Callendar Business Park, Falkirk, FK1 1XR
E: dpea@gov.scot                                     T: 0300 244 6668
Appeal Decision Notice

Decision
I dismiss the appeal and refuse planning permission in principle.
Preliminary matters
By letter dated 22 April 2021 the council issued an Environmental Impact Assessment (EIA)
screening opinion for the proposal. It noted that the proposed development falls within an
‘urban development project’ under terms of 10(b) of Schedule 2 (Column 1) of the Town
and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017. It
exceeded the threshold of 0.5 hectares and hence was considered to be ‘Schedule 2’
development. Having considered the interaction between the characteristics of the
development and its location and potential impact, the council concluded that the proposal
was not anticipated to have the potential to result in significant adverse environmental
impacts and that an EIA was not required. Having reviewed the information provided,
including supporting environmental information, I concur with that opinion.
On 31 March 2023 The Town and Country Planning (General Permitted Development and
Use Classes) (Scotland) Miscellaneous Amendment Order 2023 came into effect. As a
result, class 1 (shops) and class 2 (financial, professional and other services) were
combined to form class 1A (shops and financial, professional and other services).
Prior to determination, Scottish Ministers adopted National Planning Framework 4 (NPF4)
on 13 February 2023. This appeal was subsequently put on hold to allow Scottish Ministers
to determine another housing case, which raised questions about the way in which policy
within NPF4 should be interpreted and applied (the ‘Mossend decision, DPEA reference
PPA-400-2147). This appeal remained on hold until the conclusion of the subsequent
appeal against that decision.
Decision by Sue Bell, a Reporter appointed by the Scottish Ministers
• Planning appeal reference: PPA-290-2067
• Site address: land at Junction of Pentland Road and the A701, New Pentland,
Midlothian, EH20 9NY
• Appeal by Pentland Park Marine Ltd against the decision by Midlothian Council
• Application for planning permission in principle 21/00958/PPP
dated 25 November 2021 refused by notice dated 1 September 2022
• The development proposed: proposed mixed-use development comprising Class 2
(professional services), Class 8 (residential institutions), Class 9 (residential), Class 10
(non-residential institutions), Sui Generis (mixed use of retirement flats and assisted
living/extra care flats), affordable housing and associated works at land at junction of the
A701 and Pentland Road, Old Pentland, Edinburgh
• Date of site visit by Reporter: 23 March 2023
Date of appeal decision: 16 October 2024
Appendix A
Page 27 of 112

Page 28

PPA-290-2067
The appellant, council and community councils have been given an opportunity to comment
on the implications of the Mossend decision, the court’s opinion on that decision
(dated 2 May 2024) and a letter from the Chief Planner relating to planning for housing
(dated 26 June 2024). Given the time that has elapsed since the application was first
considered, parties were also invited to provide details of any material changes that had
occurred whilst the appeal was on hold. The appellant provided drone footage of recent
development in the area. I am content that this provided me with an adequate
understanding of changes to the area, without the need for a second site inspection.
Reasoning
1. I am required to determine this appeal in accordance with the development plan,
unless material considerations indicate otherwise. This comprises the National Planning
Framework 4 (NPF4) (2023) and the Midlothian Local Development Plan 2017 (MLDP).
2. Having regard to the provisions of the development plan and the reasons for refusal,
I find the main issues in this appeal are:
• the principle of development;
• the effect of the proposals on the character and amenity (including residential
amenity) of the surrounding area;
• whether the proposals would satisfy requirements for contributions to affordable
housing and infrastructure;
• the effect of the proposals on delivery of other allocated sites; and
• whether there are material reasons, notably a change in context of the site, that
would justify approval of the proposal.
The principle of development
3. The proposal site sits to the south of Pentland Road and extends to the northern
edge of the built-up area of Loanhead. Various spatial policies within the MLDP apply to
different parts of the site.
4. The bulk of the northern section of the site is identified as countryside within the
MLDP, subject to policy RD1 – Development in the Countryside. This policy protects
countryside areas from development unless it meets certain criteria. In broad terms,
development will only be permitted if it is required for the furtherance of a rural economic
activity including countryside recreation; or it accords with policies in respect of low-density
rural housing (policy RD2), surface mineral extraction (policy MIN1), renewable and low
carbon energy projects (policy NRG1), or wind energy (policy NRG2); or it accords with the
council’s supplementary guidance on “Development in the Countryside and Green Belt.”
5. The proposed uses are a veterinary practice (class 2 at the time of the application,
but now class 1A), community use building (class 10), affordable housing (class 9), public
green space, SuDS and landscaping. I do not find that any of these elements, particularly
the built aspects, would be for the furtherance of an established countryside activity. The
proposed public green space is intended to replace existing open spaces for users of
Pentland Park and hence I do not consider its purpose is for countryside recreation.
6. The north-western part of the proposal site is classified as prime agricultural land.
Policy ENV4 of MLDP and part b) of policy 5 of NPF4 establish criteria for when
development of this is acceptable. Policy ENV4 states that development which leads to the
permanent loss of prime agricultural land will not be permitted unless the site is allocated as
Page 28 of 112

Page 29

PPA-290-2067
part of the development strategy; it is necessary to meet an established need (such as
essential infrastructure), where there is no alternative site available and where the need for
that development outweighs the environmental or economic interests in retaining the
farmland for productive use; or it is a small-scale development directly linked to an existing
rural business. Notwithstanding the appellant’s view that the types of housing proposed are
to address a known need (which I consider further below), I do not find that the proposals
would satisfy these criteria. 
7. Similar criteria are identified within part b) of policy 5 of NPF4, which also identifies
additional exceptions to the presumption against development on prime agricultural land.
These are that it is for the development of production and processing facilities associated
with land produce where no other local site is suitable or for the generation of energy from
renewable sources or the extraction of minerals. None of these circumstances are satisfied
by the current proposals.
8. The area of land is relatively small (0.4 ha) and may not have been actively farmed
for some time. Nevertheless, it currently contributes to the agricultural land bank and its
potential use for agriculture would be lost as a result of the proposals. I therefore conclude
that it fails to satisfy the provisions of policy ENV4 of MLDP or policy 5 of NPF4.
9. The southern-most part of the proposal site lies within the built-up area of Loanhead,
where policy DEV2 - Protecting Amenity within the Built-Up Area and policy
STRAT2 – Windfall Housing Sites apply. It is also subject to the provisions of policy
DEV4 – Residential Park Homes.
10. Policy DEV2 provides support for development within the built-up area, unless it is
likely to detract materially from the existing character or amenity of the area. Policy
STRAT2 is supportive of windfall housing on non-allocated sites within the built-up area,
subject to it not leading to the loss or damage of valuable public or private open space; it
does not conflict with the established land use of the area; it has regard to the character of
the area in terms of scale, form, design and materials; it meets traffic and parking
requirements; and it accords with other relevant policies and proposals including those
relating to infrastructure, design and contributions towards affordable housing.
11. Policy DEV4 - Residential Park Homes safeguards the continued use of Pentland
Park for the siting and management of residential park homes. The proposals would occupy
an area that lies adjacent to the existing dwellings, but would not alter the use of the site
itself. The area currently used for recreation by park users would be lost. The proposals
include for alternative landscaped public space to the north of the site. However, I saw that
this area already received informal use.
12. As the proposals include elements of housing, policy 16 Quality Homes of NPF4 also
requires consideration. The policy includes eight parts, some of which deal with the location
of housing and others to the types of homes proposed. I consider these below.
13. Part d) of policy 16 relates to development proposals for Gypsy/Travellers and
showpeople, whilst Parts g) and h) relate to householder proposals. These do not have any
relevance for the current proposal.
14. Part a) of policy 16 provides support for new homes on land allocated for housing in
local development plans (LDPs). The proposed site is not allocated for housing within the
MLDP.
Page 29 of 112

Page 30

PPA-290-2067
15. Part b) places a requirement that all proposals for 50 or more homes should be
accompanied by a Statement of Community Benefit. The current proposal exceeds this
threshold, but no Statement has been provided. However, I note that the application was
submitted prior to the adoption of NPF4, which introduced this requirement.
16. The key elements of policy 16 of NPF4 are parts c) and e), which relate to the types
of home and part f), which relates to the spatial location of housing. Dealing first with part f),
in respect of location, as already noted, part a) supports housing developments on
allocated sites. For all other locations, part f) is engaged, regardless of the type(s) of
housing being proposed.
17. Part f) sets out the circumstances when development proposals for new homes on
unallocated land may be acceptable. These include at point (ii) that the proposal is
otherwise consistent with the plan spatial strategy and other relevant policies including local
living and 20 minute neighbourhoods. The proposed affordable housing lies within the
countryside and hence is not consistent with the spatial strategy.
18. Local living and 20 minute neighbourhoods is also addressed through policy 15 of
NPF4. The policy seeks to encourage and promote neighbourhoods where people can
meet the majority of their daily needs within a reasonable distance of their home, preferably
by walking, wheeling or cycling or using sustainable transport options. The proposal site
would be close to a number of the facilities required to fulfil daily needs, such as food
shops. The appellant has provided a plan (Appendix 1 to response to further information
request dated 16 February 2023) to illustrate accessibility to facilities (e.g. health and social
care facilities, sports facilities and schools). Whilst many of these facilities are shown as
being within approximately a 20-minute walk from the proposal site, I note that this has
been assessed in terms of time in a single direction and has been calculated ‘as the crow
flies’ rather than being related to the footpath network. The plan includes bus routes, but no
indication of the frequency of service. Furthermore, the facilities do not appear particularly
well-related to the proposal site, with the medical facilities appearing to be located towards
the eastern extent of the walk time. Given that much of the proposed housing is specifically
targeted at older populations or those requiring assisted living, I find that the proposals are
not well-located to accord with the intent of this policy. Thus, the proposals do not satisfy
the requirements of policy 15 or meet the exceptions set out in part f) (ii) of policy 16.
19. Turning to part f) (iii) of policy 16, notwithstanding that deliverable housing land
pipelines have yet to be produced, there is no suggestion that housing sites are being
delivered more rapidly than envisaged, creating a shortage of sites. The elements of the
proposal which fall within the settlement boundary comprise 42 extra care/ assisted living
flats and an 80 room care home. I consider that these would not meet the definition of a
smaller scale opportunity. Parts of the proposal fall outwith the settlement boundary, and
these are not consistent with the policy on rural homes. Whilst I recognise that the proposal
is for the delivery of less than 50 affordable homes, these are not part of a local authority
supported affordable housing plan. I therefore conclude that the proposals fail to meet the
exceptions set out in part f) (iii). Overall, they fail to meet any of the locational requirements
set out in policy 16.
20. I have also considered the types of housing proposed against the criteria set out in
parts c) and e) of policy 16 of NPF4. Part c) provides support for development proposals for
new homes that improve affordability and choice by being adaptable to changing and
diverse needs, and which address identified gaps in provision. Examples of the type of
housing included within this description include: ii – accessible, adaptable and wheelchair
accessible homes; iv – affordable homes; and vi – homes for older people, including
Page 30 of 112

Page 31

PPA-290-2067
supported accommodation, care homes and sheltered housing. Subject to demonstration
that there are identified gaps in provision, I accept that the different elements of proposed
accommodation would each meet one of these descriptions. Hence the proposals would
gain support from this part of policy 16.
21. Part e) provides support for new homes where they make provision for affordable
homes to meet an identified need. It sets an expectation that at least 25% of the total
number of homes should be affordable, although a higher contribution may be justified by
evidence of need. Lower contributions may also be justified, for example to incentivise
particular types of homes needed to diversify supply. The current proposals include for
10 affordable homes and 42 flats. Thus, the numbers of affordable homes fall just short of
the 25% level.
22. I conclude that the proposals gain support from part c) and to a lesser extent, part e)
of policy 16, but fail to satisfy parts a) or f). Policy 16 does not explicitly identify
parts c) and e) as additional circumstances to those set out in part f) where new homes on
unallocated land may be acceptable. Nevertheless, they indicate the importance placed on
provision of these types of housing. I do not, however, accept the appellant’s view that the
nature of the proposed housing means that I can disregard the locational criteria set out in
parts a) and f). The intent of policy 16 is “to encourage, promote and facilitate the delivery
of more high quality, affordable and sustainable homes, in the right locations, providing
choice across tenures that meet the diverse housing needs of people and communities
across Scotland”. Thus, whilst the policy seeks high quality and affordable homes, these
must be “in the right locations”, maintaining a locational element to the assessment. It may
be that there would be occasions where the weight given to the types of housing under
parts c) and/or e) was considered sufficient to overcome any conflict with part f) and allow a
conclusion of overall compliance with policy 16. However, I am not persuaded that such a
conclusion would be valid in this case. The site is not particularly well positioned to promote
local living and 20 minute neighbourhoods. There is also no evidence as to why the
proposals could not be accommodated in other locations, including land adjacent to the
proposal site, which is allocated within the MLDP for mixed-use development.
23. In reaching a conclusion on this matter, I have considered the terms of The Chief
Planner’s letter (26 June 2024), which was published to provide clarification on the
application of NPF4. This indicates that the different parts of policy 16 “should be weighed
up as relevant to the proposal; there is no hierarchy and no one part of policy should always
outweigh others. A balanced planning judgement should be reached in each case.” I have
considered both the locational aspects of the proposal (parts a) and f)) and the relevant
criteria relating to the types of housing (parts c) and e)). I conclude, that whilst the
proposals gain some support from parts c) and e) of policy 16, this support is tempered
when considered within the context of policy 16 as a whole and is not sufficient for me to
conclude that the proposal accords overall with policy 16.
24. The affordable housing, which lies outwith the built-up area also requires to be
considered in relation to policy 17 – Rural homes of NPF4. The proposal is not on a site
allocated for housing within the LDP, does not represent reuse of a brownfield site or
redundant building, is not necessary to support management of a viable rural business, nor
is it for a single home or for the subdivision of an existing residential dwelling or
reinstatement of a former dwelling house. I have also concluded above that the proposals
would not be particularly well placed to contribute towards local living. I therefore conclude
that it would fail to satisfy the requirements of policy 17 of NPF4.
Page 31 of 112

Page 32

PPA-290-2067
25. In conclusion, for the reasons set out above, and subject to my comments in relation
to the effects of the proposals on character and amenity below, I conclude that the principle
of the proposed development does not accord overall with the development plan.
Effect of the proposals on the character and amenity (including residential amenity) of the
surrounding area 
26. Policy DEV2 of MLDP seeks to protect amenity within the built-up area, whilst
policy 14 – design, quality and place of NPF4 seeks to encourage, promote and facilitate
well designed development. I saw that the proposal site currently comprises areas of open
green space, partially sub-divided by fences and a hedge. The residential properties of
Pentland Park are situated adjacent to much of the western and southern boundaries of the
appeal site. The north of the site is bordered by Pentland Road. The A701 lies to the east of
the site, but lies beyond much of the eastern boundary of the site, which is provided by four
residential properties. The appellant reports that three of these operate as commercial
businesses, but there was no obvious noise or disturbance associated with these uses at
the time of my visit.
27. The character of the wider area is mixed. When driving along the A701, I saw a clear
distinction between the retail outlets that lie on the eastern side of the road and the areas of
undeveloped land and smaller residential properties on the western side of the road. These
large-scale retail developments are clearly separate from the appeal site and are sufficiently
distant so as not to dominate the dwellings within Pentland Park.
28. The development of the food store with its associated parking, spine road and the
proposed new access off Pentland Road adjacent to the north-east of the site has extended
commercial development across the A701, bringing it closer to the residential properties
within Pentland Park. Nevertheless, the appeal site continues to provide a buffer of green
open space between Pentland Park and the commercial uses. It also continues to provide a
green corridor to open land to the west and north of the site.
29. The indicative plan shows most of the proposed built development, including all the
housing and residential units, would be located within the south of the appeal site, between
the existing residential areas of Pentland Park and the dwellings adjacent to the A701. In
broad terms, I find that the proposed mix of accommodation may be compatible with the
existing residential use. However, I am aware that the nature and level of servicing
associated with extra care/ assisted living and a care home may be of a different nature and
pattern to that of private residential dwellings, leading to greater noise and disturbance. It
would also lead to a loss of the existing adjoining green space for those properties to the
south and west of the proposals.
30. The appellant has interpreted character and amenity in terms of “landscape and
urban design character with general and visual amenity considerations.” It suggests that
there would be potential benefits to amenity arising from better access to quality
green/open spaces, an increase in the area of open space available to residents of
Pentland Park, walking routes and children’s play facilities and better access through the
site. I am not convinced that any benefits to open space provision would be as substantial
as the appellant suggests. Overall, there would be a loss of some of the existing open
space, including the area that is in closest proximity (and hence most accessible) to the
park dwellings. The appellant states that there is no public access to much of this existing
open space, but that did not accord with my observations. I saw that whilst there is a formal
area for public access at the south of the site, there are no obvious physical barriers
preventing access to the wider site. Indeed, I saw several individuals walking throughout
Page 32 of 112

Page 33

PPA-290-2067
this area. Even in the absence of physical access to this land, I saw that it provides some
visual separation between the eastern boundary of Pentland Park and the more commercial
developments along the A701.
31. I conclude that the cumulative scale and density of development at the southern end
of the site would be detrimental to the character of the area and residential amenity of
Pentland Park and hence would be inconsistent with policy DEV2 of the MLDP. For similar
reasons, I find it would also fail to be consistent with policy 14 of NPF4.
Whether the proposal would satisfy requirements for contributions to affordable housing
and infrastructure
32. Without prejudice to the outcome of the application, the council sent draft Heads of
Terms for a legal agreement to the appellant. These related to contributions towards the
A901 Relief Road and the A702 Link Road; for primary and secondary education provision;
affordable housing; and maintenance of open space including children’s play areas/ open
space and SuDS. No agreement on some of these matters (e.g. affordable housing) had
been reached by the time that the application was determined. Had I been minded to allow
the appeal I am satisfied that there would have been a strong likelihood of reaching an
agreement on these matters.
Whether development on an unallocated site would delay early implementation of an
adjacent allocated site
33. Land to the north of Pentland Road is allocated for mixed-use development (Ec3
West Straiton) including retail, hotel, office, commercial leisure and housing. The southern
part of Ec3 is also identified as part of an allocation for a film studio (MX1). However, the
council has indicated that this is now unlikely to proceed. Whilst I accept that some of the
proposed uses for the appeal site are not specifically identified for Ec3, given its allocation
for mixed-use development, I can see no barrier to the uses proposed as part of this
application being located there.
34. Development at Ec3 is dependent on the construction of the A701 Relief Road. The
council has confirmed its continuing commitment to the proposals, and I note the recent
initiatives to progress the wider scheme. I accept that delivery of proposals for this site may
therefore be delayed until the road is implemented. Nevertheless, I do not see this as
justification for development on an adjoining, unallocated site.
Other considerations
35. The appellant considers that great weight should be placed on the proposals
delivering housing for which there is an identified need. The appellant has identified this
need through discussions with Midlothian Council’s Housing Department; from the council’s
Local Housing Strategy and the Strategic Housing Investment Plan (SHIP) 21/22-24/25
and 2022/23 – 2026/27 which identified the Loanhead area as having a high demand for
social housing. In addition, the appellant refers to their own experiences of a demand for
age-appropriate housing in this area, the declaration of a national housing emergency in
Scotland and primary research for Homes for Scotland relating to the extent of housing
need across Scotland.
36. Accepting that there is a demand for the proposed forms of housing, there appears
to be no suggestion that this demand within Midlothian is related to any shortfall in the
allocation of housing land or could not be accommodated on allocated sites.
Page 33 of 112

Page 34

PPA-290-2067
37. NPF4 sets out a Minimum All Tenure Housing Land Requirement (MATHLR) for
each local authority area. This is the minimum amount of land, (defined in terms of number
of housing units), to be provided for a 10-year period. The MATHLR for Midlothian
is 8,850, which equates to a requirement of 4,425 homes over a 5-year period. This falls
within the stated supply included within the MLDP of 4,500 homes. The council has
provided housing land supply figures included within the approved 2023 Housing Land
Audit, which covers the period 1 April 2022 to 31 March 2023. These identify a housing land
supply of 11,799 homes, of which 11,052 were effective. These figures exceed the
MATHLR figure.
38. The appellant has referred to information relating to housing land supply contained in
the Evidence Report for the review of the MLDP, suggesting that supply may need to be
increased and that there is a heightened need and demand within the affordable and
specialist housing sectors. I note that these figures have been collected to inform an
updated version of the MLDP, including allocation of suitable sites, rather than to guide
development management decisions. Nevertheless, the council has indicated that through
its Evidence Report, it has agreed a Local Housing Land Requirement of 8,851 homes. This
exceeds the MATHLR, albeit by a single unit. I therefore conclude that the current supply of
housing land exceeds the MATHLR.
39. I have also considered the Scottish Government’s declaration of a housing
emergency, as an important material consideration. The declaration makes specific
reference to affordable housing. As the proposals include 10 affordable homes, the
proposals gain some support from this. However, it does not appear to me that a shortage
of housing land has been identified as an important contributory factor to the emergency. In
any case, based on the figures above, it appears that adequate housing land has been
allocated within Midlothian and there are policies within the MLDP, which provide for
affordable homes as part of development proposals. Furthermore, I am not aware of any
ministerial statement or instruction requiring departure from development plans in the light
of the housing emergency. Therefore, I find that the declaration of the housing emergency
does not justify a departure from the development plan in this instance.
40. The appellant has also directed me to research undertaken by The Diffley
Partnership and Rettie & Co. on behalf of Homes for Scotland and suggested that this
should be a factor in my decision-making process. This research has explored existing
housing need in Scotland and concluded that the Scottish Government’s Housing Need and
Demand Assessment tool underestimates housing demand. I find the report to contain
findings, which could help to influence discussions as to how best to measure housing need
and demand both locally and nationally. However, the approach has not been verified and
at this point has no particular status. The report appears to have been commissioned to
assist with the preparation of evidence reports to support local development plans and does
not appear to be intended to guide individual development management decisions. As
noted above, there are up-to-date figures for housing land requirements available through
the Evidence report submitted as part of the review of the MLDP. Therefore, I am not
persuaded that the Diffley & Rettie report provides sufficient justification to permit
development on an unallocated site.
41. In summary, the proposals would make a small, but valuable contribution to the
supply of affordable housing in Midlothian, for which there is a recognised demand.
However, there are existing mechanisms to provide for affordable housing on the already
allocated sites, there appear to be sufficient allocated sites, and there is no indication that
such windfall sites are necessary to meet the demand – even when considered within the
Page 34 of 112

Page 35

PPA-290-2067
context of a declared national housing emergency and need for affordable housing. As
such, I conclude that any benefits in terms of the types of homes provided by the proposals
would not be sufficient to overcome the policy tensions identified above. 
42. The appellant maintains that the context of the site has changed since the
application was considered and that the grant of permission for the food store and
associated spine road and access, is a material consideration of significant weight. The
appellant has suggested that in granting permission for the food store, the council has
determined that the land does not require protection as countryside through policy RD1.
Reference is also made to land to the west of the appeal site, which is safeguarded within
the MLDP for a proposed film studio development (Allocation MX1), as further justification
that land to the west of the food store will, inevitably, be developed. I am not persuaded by
this view. Each proposal must be considered on its own merits. The food store was
consented prior to the adoption of NPF4, and I am not aware of the full range of any
material considerations taken into account by the council in reaching its decision to grant
consent. Whilst the actual visual effects of the food store can now be seen from the
photographs and drone footage submitted by the appellant, the predicted effects of this
development were included as part of the council’s assessment of the appealed scheme.
43. In terms of the film studio, I note that whilst Scottish Ministers were minded to grant
approval for the scheme (subject to a legal agreement), there has been a subsequent
Scottish Land Court decision, which means there is little realistic prospect of the film studio
gaining title to the land, and the applicant has subsequently identified an alternative site.
The MLDP states that the designations of Green Belt/ Countryside/ Prime Agricultural Land
would remain until that part of the site is fully developed (for the film studio). Thus, there is
no certainty that the land to the west of the appeal site would be developed. It may be that
the council would conclude that boundaries of site allocations may require to change.
However, any such changes are best addressed as part of the review of the MLDP.
44. The appellant has referred to a masterplan for the New Pentland Development. This
includes the previously consented (and now under construction) food store. Whilst the
appellant may have aspirations for the land as a whole, I do not believe that the
‘masterplan’ has any formal planning status. The supermarket does not form part of this
application, and the council has indicated that the application for the food store was
submitted (and considered) as a standalone application. There is no indication that the
current application is reliant on the food store for its viability (although I note that it would
use the vehicle access consented as part of that scheme). Thus, I have not given this
masterplan any particular importance in reaching my decision.
45. I note the objections to the proposals based around effects on transport and traffic. I
accept that the site is served by public transport. A transport assessment has been
produced, the findings of which been assessed by Transport Scotland and the council’s
Policy and Road Safety Manager, neither of whom have objected. I am therefore satisfied
that these matters have been adequately assessed and that the road network could
accommodate the estimated volumes of traffic generated by the proposal.
46. I have considered the representations in respect of biodiversity. A preliminary
ecological appraisal has been submitted and been assessed as acceptable by the council.
Whilst the information on which that assessment is based is now older than generally
considered appropriate, updated assessments could be required to support detailed
proposals.
Page 35 of 112

Page 36

PPA-290-2067
47. The council has suggested that two further policies within NPF4, policy 27 - city,
town, local and commercial centres and policy 28 - retail are relevant. Policy 27 deals with
the town centre first principle. The council considers that the proposed class 2, class 8 and
class 10 are all footfall generating uses that could potentially be located within or at the
edge of existing town centres. Despite this, I note that in reaching its decision, the council
did not refer to similar policies within the MLDP. Nor were concerns about proposed footfall
identified as being determinative or a reason for refusal of the application.
48. The council suggests that policy 28 has become engaged following a change in the
Land Use Classes that took place on 31 March 2023. As a result of this change,
class 1 (shops) and class 2 (financial, professional and other services) of the Town and
Country Planning (Use Classes) (Scotland) Order 1997 (as amended) have been combined
into a single use class 1A (shops and financial, professional and other services). Retail
proposals are also to be consistent with the town centre first principle. I do not accept the
appellant’s view that the grant of permission for the adjacent food store negates the need
for a Town Centre First Assessment. Nevertheless, these changes have not been a
determining factor in my decision-making.
49. I acknowledge the various points raised in objections from the Damhead and District
Community Council and the Loanhead and District Community Council. I have already
addressed concerns in relation to compliance with allocations within the MLDP, alternative
locations, effects on the amenity of residents of Pentland Park, transport and biodiversity. In
terms of the consultation process I am satisfied that this met statutory guidance set out by
Midlothian Council and that adequate information has been provided to enable a sufficient
understanding of the nature of the proposals.
50. I have considered the economic benefits of the scheme. However, I am not
persuaded that these benefits are sufficient reason to consent commercial development on
an unallocated site, particularly given the proximity of an already allocated and
undeveloped site on the opposite side of Pentland Road.
Conclusions
51. For the reasons set out above, I conclude that the proposed development does not
accord overall with the relevant provisions of the development plan and that there are no
material considerations which would still justify granting planning permission. I have
considered all the other matters raised, but there are none which would lead me to alter my
conclusions.
Sue Bell
Reporter
Page 36 of 112

Page 37

Planning Committee 
Monday 9 December 2024
Item No 5.3
SECTION 36 CONSULTATION FOR FORMATION OF BATTERY ENERGY
STORAGE SYSTEM (BESS) (200MW) FACILITY, COMPRISING THE
ERECTION OF BATTERY STORAGE UNITS, AREAS OF
HARDSTANDING, SECURITY FENCING AND ANCILLARY BUILDINGS;
FORMATION OF ACCESS, INCLUDING ALTERATIONS TO EXISTING
ACCESS; DRAINAGE WORKS INCLUDING THE FORMATION OF SUDS
POND; LANDSCAPING WORKS INCLUDING BUNDING, HABITAT
CREATION AND TREE PLANTING; AND ASSOCIATED WORKS AT
SALTER'S PARK EXTENSION (SITE EC2), SALTER'S ROAD, DALKEITH
Report by Chief Officer Place
1 PURPOSE OF REPORT
1.1 The purpose of this report is to advise the Committee of a consultation
request from the Scottish Government’s Energy Consents Unit (ECU).
The consultation relates to an application under Section 36 of the
Electricity Act 1989 for consent to construct and operate an electricity
generating station, specifically a Battery Energy Storage System
(BESS) with a capacity of 200MW. 
2 LOCATION AND SITE DESCRIPTION
2.1 The application site comprises an 11.95 hectare agricultural field and a
380 metre long access track.  The site is situated to the north of
Dalkeith with the A68 adjacent to the northeastern boundary and the
Dalkeith to Whitecraig cycleway adjacent to the western boundary.
Vehicular access to the site is via an access track that starts at an
existing field access junction on Salter’s Road (A6094), traverses a
field of scrub vegetation and finishes at the cycleway.  A high-pressure
gas pipeline passes through the site from southeast to northwest.
2.2 The field slopes downhill from east to west with a fall across the site of
between 6.5 metres and 8 metres.  The ground cover is scrub
grassland and the field is not in active agricultural use.  The site
comprises made ground and fill material associated with open cast coal
extraction that formed part of the groundworks for the construction of
the A68.  The land immediately to the south and east is in use as an
arable field.
2.3 The closest residential properties are the properties at Smeatonhead
Farm Cottages which are situated 155m to the west of the field and
Page 37 of 112

Page 38

105 metres to the south of the access track.  The Dalkeith Schools
Campus is situated 70 metres south of the southern edge of the field.
Dalkeith Country Park is situated 330 metres west of the field. 
2.4 The majority of the field is identified in the Midlothian Local
Development Plan 2017 as forming part of a strategic employment land
allocation (Ec2 Salter’s Park Extension) which is identified for Business
(Class 4) and General Industry (Class 5) purposes – the site however
also extends into the green belt beyond the allocated employment site. 
The access track forms part of a previous, but still undeveloped,
employment land allocation (e14 Salter’s Park) which is identified for
Business (Class 4), General Industry (Class 5) and Storage or
Distribution (Class 6) purposes. 
3 PROPOSAL 
3.1  It is proposed to construct and operate a battery energy storage
system (BESS) with a capacity of circa 200 megawatts.  The scheme
will comprise 168 storage containers spread across 4 compounds.  The
containers will be used to house Lithium-ion batteries.  The compounds
will be hard surfaced and enclosed with 3 metres high palisade fencing.
In addition to the containers each compound will include 10 power
conversion units which convert low voltage direct current from the
battery units to high voltage alternating current for grid transmission,
the conversion units can also be used to switch the current when the
batteries are charging from the grid.  The final component in each
compound will be a fire water tank. 
3.2 In addition to the BESS compounds the site will also include modular
buildings for the site operator and grid operator, grid transformer sets
and a grid operator switchyard. It is anticipated that grid connection will
be via buried high voltage cables linking to existing Scottish Power
infrastructure to the north of the A68. 
3.3 The existing access track will be upgraded to accommodate vehicle
movements during site construction.  Surface water drainage will be
collected in an attenuation pond at the southwestern corner of the field.
The pond will provide back-up fire fighting capacity.  Landscape
planting and biodiversity enhancement will be carried out round the
perimeters of the site.  The proposed layout shows development sited
to maintain stand-off distances to the gas pipeline. 
3.4 The application is supported by the following reports: 
• Biodiversity Enhancement Plan
• Ecological Impact Assessment
• Flood Risk Assessment & Conceptual Drainage Strategy
• Land Capability for Agricultural Assessment
• Landscape & Ecological Management Plan
• Landscape & Visual Impact Assessment
Page 38 of 112

Page 39

• Noise Impact Assessment
• Outline Construction Environmental Management Plan
• Phase 1 Preliminary Risk Assessment & Coal Mining Risk
Assessment
• Planning Support Statement
• Statement of Community Engagement
• Transport Statement 
3.5 The application, supporting information and consultation responses are
available for public view on both the ECU public access system and the
Council’s planning portal. 
4 BACKGROUND 
4.1 Proposals to build, operate or modify onshore electricity generating
stations with a capacity exceeding 50 megawatts require consent
under Section 36 of the Electricity Act 1989.  In Scotland the Scottish
Ministers are responsible for assessing Section 36 applications and
this function is carried out by the Scottish Government’s Energy
Consents Unit (ECU).  If the ECU grants consent under Section 36, this
engages Section 57 of the Town and Country Planning (Scotland) Act
1997 (as amended).  Subsection 2 provides that Scottish ministers may
give a direction for planning permission to be deemed to be granted,
subject to such conditions (if any) as may be specified in the direction. 
4.2 The Scottish Government’s Chief Planner confirmed, in a letter
published on 27 August 2020, that the Scottish Government
considered battery installation storage schemes should be treated as a
generating station. Consequently, such schemes require Section 36
consent. 
4.3 In advance of the submission of the Section 36 application the
applicant sought an Environmental Impact Assessment (EIA)
Screening Opinion from the ECU.  The Screening Opinion was adopted
on 23 May 2024 when the ECU confirmed that the proposal does not
constitute EIA development and therefore no EIA Report was required. 
4.4 The current application was submitted to the ECU on 21 August 2024.
The planning authority is a statutory consultee on the application and
has until 21 December 2024 to provide comments to the ECU.  If the
planning authority objects to a Section 36 application a public inquiry
must be held and responsibility for the application will pass from the
ECU to the Scottish Government Planning and Environmental Appeals
Division (DPEA). 
4.5 The land to the west of the cycleway was used as a works compound
during the construction of the A68 Dalkeith bypass in the late 2000s.
The land to the east was used in association with open cast coal
extraction that formed part of the groundworks for the construction of
Page 39 of 112

Page 40

the A68.  After the opening of the A68 the application site has been the
subject of three different development proposals. 
4.6 The earliest proposal was for planning permission in principle for
residential development (up to 400 units) and employment uses;
formation of access roads and associated works.  In advance of the
application a proposal of application notice (reference 14/00833/PAC),
two EIA screening opinion requests (references 15/00026/SCR and
15/00543/SCR) and an EIA scoping opinion request (reference
16/00724/SCO) were submitted.  Planning application 16/00893/PPP
was registered on 20 December 2016 and refused by the Committee at
its meeting of 27 June 2018. 
4.7 A proposal of application notice for a mixed-use development
comprising film and TV studios including workshops/offices;
reception/commissary; gatehouse; backlot; trailer park; film academy
and associated student accommodation; and associated access,
parking and infrastructure was submitted on 9 January 2019.  The
proposal did not proceed to a formal planning application. 
4.8 A mixed-use development comprising Class 4 (light industrial/office),
Class 5 (general industry) and Class 6 (storage or distribution) was the
subject of a withdrawn proposal of application notice (reference
21/00338/PAC), a consented notice (reference 21/00512/PAC) and an
EIA scoping opinion request (reference 21/00584/SCO). The proposal
did not proceed any further. 
5 CONSULTATIONS 
5.1 The planning authority is one of various consultees that have been
consulted by the ECU. The planning authority has sent consultations to
internal Council consultees but, to avoid duplication, consultations have
not been sent to external agencies. The following consultees were
consulted by the planning authority. 
5.2 The Council’s Archaeological Advisor does not object to the
application subject to conditions being used to secure a programme of
archaeological work, to include initially a desk-based assessment of
the proposed development area (and immediate environs), followed by
a trial trench evaluation, and possibly monitoring along the access
route/across the railway.  Further stages of archaeology work may be
required depending on results. 
5.3 The Council’s Biodiversity Advisor (The Wildlife Information Centre)
confirmed that Section 36 consultations are outwith the scope of their
service agreement with the planning authority. 
5.4 The Council’s Education Executive Business Manager (including
school staff) does not object to the application, however raise the
following concerns:
Page 40 of 112

Page 41

• There should have been better public notification of the
application and the sharing of information and knowledge
promoted.  Parents/carers, in particular the parent councils,
should have been consultation.
• Future infrastructure projects and connections to the network
could potentially be affected.
• Potential fire risk - with schools being within close proximity of
the site, if a fire were to occur the worry is the site might have to
be evacuated because of potential toxic fumes.  There is the
need for a point of contact in case of fire/hazard.
• The volume of the batteries which will be stored in each
container.
• The site’s close proximity to the schools.
• Increased traffic impacting on pedestrian safety. 
5.5 The Midlothian Health and Social Care Partnership offered no
comment on the proposal. 
5.6 The Council’s Rights of Way consultee does not object to the
application and provided the following comment: 
The development is directly adjacent to an important multi-user path
which is also part of National Cycle Route 1. Therefore there must be
no impacts that would affect the use of this path or its verges without
permission from Midlothian Council's Land and Countryside Service.
Any unauthorised blocking, obstruction or deterrent from using the
route would be illegal under the Land Reform (Scotland) Act 2003. 
5.7 The Council’s Senior Manager Neighbourhood Services (Flood
Risk and Transportation) does not object to the application and
provided the following comments: 
The proposed access road for the development intersects National
Cycle Network Route 1 (NCN 1). Cognisance of this active travel
facility should be taken when developing the Construction Environment
Management Plan (CEMP), detailing any risks or safety measures
taken to reduce vehicle – pedestrian conflict at this location. 
The finalised design should ensure clear sightlines for pedestrians and
cyclists on the NCN 1, as well as for drivers of maintenance vehicles
on the access road. 
5.8 The Council’s Senior Manager Protective Services (Contingency
Planning and Environmental Health) does not object to the
application subject to any consent including conditions to address
concerns relating to fixed plant noise, contaminated land site
investigations and light emissions.  It is also noted that this type of
development has been discussed at nationwide resilience networking
groups - copies of a House of Commons briefing paper and guidance
Page 41 of 112

Page 42

from the National Fire Chiefs Council was provided (the ECU will have
access to these documents).
5.9 In addition to the consultations carried out by the planning authority the
ECU has consulted and received responses form the following
consultees:
• Historic Environment Scotland
• Scottish Environmental Protection Agency (SEPA)
• Naturescot
• BT (telecoms provider)
• Defence Infrastructure Organisation
• Edinburgh Airport Limited
• Health and Safety Executive
• NATS (air traffic control operator)
• Office for Nuclear Regulation
• Scottish Gas Networks (gas distribution company)
• Scottish Water
• Coal Authority
5.10 The ECU has also consulted the following bodies from which no
response has been received to date (at the time of drafting this report):
• Transport Scotland
• Joint Radio Company
• RSPB Scotland
• Scottish Fire and Rescue Service
• SP Energy Networks
• Scotways
• Scottish Wildlife Trust
• Visit Scotland
• Whitecraig Community Council
6 REPRESENTATIONS
6.1 The planning authority has received two objections to the proposal.
The objections have been made public on the planning portal and the
representors have been advised that the planning authority is not the
consenting authority for the application.  Representors have been
advised of the contact details for the ECU.  The reasons for objection
are as follows:
• Concerns about the proximity of the facility to schools, houses
and gas mains.
• Lack of information on what the potential blast radius would be if
the battery storage containers were to fail and explode.
• There needs to be a proper risk assessment done to show what
would happen in the unlikely event that there is a fire that
causes an explosion.
Page 42 of 112

Page 43

• The proposal would be better situated on the north side of the
A68 on the former travellers’ site where access from the A68 slip
road onto Salters Road already exists, appears to be of
adequate size, and is in close proximity to the Smeaton
Substation to allow for the necessary electrical connections.
• It would be good to have the opinion of the electric network
operator of where they consider a BESS should be fitted. 
• The cycleway is well-used, and closure would be a significant
loss to the community. A public right of way on the cycleway
should be retained throughout the construction process.
• It needs to be demonstrated that the BESS site can be operated
safely over its projected lifetime.
• Any SUDS scheme should consider future possible industrial
development, and an assessment should be made of the water
discharged into the stream feeding into the River Esk.
• Midlothian Council should seek reductions in their energy bills
for their schools at the Dalkeith Campus in return for supporting
the BESS. 
7 PLANNING POLICY 
7.1 The development is comprised of National Planning Framework 4
(2023) and the Midlothian Local Development Plan 2017. The following
policies are relevant to the proposal: 
National Planning Framework 4 (NPF4) 
7.2 NPF4 is a National Spatial Strategy for Scotland 2045 and it sets out to
plan provide a plan for future places using six overarching spatial
principles: 
• Just transition.
• Conserving and recycling assets.
• Local living.
• Compact urban growth.
• Rebalanced development.
• Rural revitalisation. 
7.3 Policy 1 Tackling the climate and nature crisis; sets out to
encourage, promote and facilitate development that addresses the
global climate emergency and nature crisis. 
7.4 Policy 2 Climate mitigation and adaptation; sets out to encourage,
promote and facilitate development that minimises emissions and
adapts to the current and future impacts of climate change. 
7.5 Policy 3 Biodiversity; sets out to protect biodiversity, reverse
biodiversity loss, deliver positive effects from development and
strengthen nature networks.
Page 43 of 112

Page 44

7.6 Policy 4 Natural Places; sets out to protect, restore and enhance
natural assets making best use of nature-based solutions. 
7.7 Policy 5 Soils; sets out to protect carbon-rich soils, restore peatlands
and minimise disturbance to soils from development. The policy also
sets out acceptable scenarios for development on prime agricultural
land. 
7.8 Policy 7 Historic assets and places; sets out to protect and enhance
historic environment assets and places, and to enable positive change
as a catalyst for the regeneration of places. 
7.9 Policy 11 Energy; sets out to encourage, promote and facilitate all
forms of renewable energy development onshore and offshore. This
includes energy generation, storage, new and replacement
transmission and distribution infrastructure and emerging low-carbon
and zero emissions technologies including hydrogen and carbon
capture utilisation and storage (CCUS). 
7.10 Policy 20 Blue and green infrastructure; sets out to protect and
enhance blue and green infrastructure and their networks. 
7.11 Policy 22 Flood risk and water management; sets out to strengthen
resilience to flood risk by promoting avoidance as a first principle and
reducing the vulnerability of existing and future development to
flooding. 
7.12 Policy 23 Health and Safety; sets out to protect people and places
from environmental harm, mitigate risks arising from safety hazards
and encourage, promote and facilitate development that improves
health and wellbeing. 
7.13 Policy 26 Business and industry; sets out to encourage, promote and
facilitate business and industry uses and to enable alternative ways of
working such as home working, live-work units and micro-businesses. 
Midlothian Local Development Plan 2017 (MLDP) 
7.14 Policy STRAT1: Committed Development seeks the early
implementation of all committed development sites and related
infrastructure, including sites in the established economic land supply.
Committed development includes those sites allocated in previous
development plans which are continued in the MLDP. 
7.15 Policy STRAT5: Strategic Employment Land Allocations supports
development for employment uses on sites identified as strategic
employment land allocations. 
Page 44 of 112

Page 45

7.16 Policy DEV2: Protecting Amenity within the Built-Up Area states
that development will not be permitted within existing and future built-
up areas where it is likely to detract materially from the existing
character or amenity of the area.
7.17 Policy ECON1: Existing Employment Locations seeks to safeguard
those sites allocated for economic land uses against loss to non-
business or industrial uses.  Alternative uses for such sites will only be
permitted if there is no net detriment to the overall supply of economic
land.
7.18 Policy ENV1: Protection of the Green Belt advises that development
will not be permitted in the Green Belt except for proposals that:
A. are necessary to agriculture, horticulture or forestry; or
B. provide opportunities for access to the open countryside,
outdoor sport or outdoor recreation which reduce the need to
travel further afield; or
C. are related to other uses appropriate to the rural character of the
area; or
D. provide for essential infrastructure; or
E. form development that meets a national requirement or
established need of no other site is available.
Any development proposal will be required to show that it does not
conflict with the overall objectives of the Green Belt which is to maintain
the identity and landscape setting of Edinburgh and Midlothian towns
by clearly identifying their physical boundaries and preventing
coalescence.
7.19 Policy ENV4: Prime Agricultural Land does not permit development
that would lead to the permanent loss of prime agricultural land unless
there is appropriate justification to do so.
7.20 Policy ENV9: Flooding presumes against development which would
be at unacceptable risk of flooding or would increase the risk of
flooding elsewhere.  It states that Flood Risk Assessments will be
required for most forms of development in areas of medium to high risk,
but may also be required at other locations depending on the
circumstances of the proposed development.  Furthermore it states that
sustainable urban drainage systems will be required for most forms of
development, so that surface water run-off rates are not greater than in
the site’s pre-developed condition, and to avoid any deterioration of
water quality.
7.21 Policy ENV10: Water Environment requires that new development
pass surface water through a sustainable urban drainage system
(SUDS) to mitigate against local flooding and to enhance biodiversity
and the environment.
Page 45 of 112

Page 46

7.22 Policy ENV11: Woodland, Trees and Hedges states that development
will not be permitted where it could lead directly or indirectly to the loss
of, or damage to, woodland, groups of trees (including trees covered by
a Tree Preservation Order, areas defined as ancient or semi-natural
woodland, veteran trees or areas forming part of any designated
landscape) and hedges which have a particular amenity, nature
conservation, biodiversity, recreation, landscape, shelter, cultural, or
historical value or are of other importance.
7.23 Policy ENV15: Species and Habitat Protection and Enhancement
presumes against development that would affect a species protected
by European or UK law.
7.24 Policy ENV25: Site Assessment, Evaluation and Recording requires
that where development could affect an identified site of archaeological
importance, the applicant will be required to provide an assessment of
the archaeological value of the site and of the likely impact of the
proposal on the archaeological resource.
7.25 Policy NRG1: Renewable and Low Carbon Energy Projects
supports renewable and low carbon energy projects, including energy
storage, subject to the following conditions being met:
A. The proposal will not cause an unacceptable significant adverse
effect upon the historic environment;
B. The proposal will not cause an unacceptable significant adverse
effect upon natural heritage;
C. The proposal will not cause an unacceptable significant adverse
effect upon Green Belt, the Pentland Hills Regional Park or its
setting, or the Special Landscape Areas;
D. The proposal will not cause an unacceptable significant adverse
effect upon peat/carbon rich soils or prime agricultural farmland;
E. The proposal will not have an unacceptable effect on the amenity of
nearby communities or residential properties;
F. The proposal will not cause or increase pollution or flood risk, or
have an unacceptable effect on the water environment or water
catchment areas;
G. The proposal will not require infrastructure for access and/or power
transmission which itself has a significantly unacceptable
environmental impact;
H. The proposal will not cause an unacceptable significant adverse
effect upon landscape or visual impact;
I. The proposal will not result in unacceptable cumulative impacts;
J. The proposal will not lead to the loss of public access routes and, if
routes require diversion, alternative acceptable to the Council must
be provided;
K. The proposal will not compromise telecommunications and
broadcasting installations, and transmission links;
L. The proposal will not lead to unacceptable impacts on the road
network including traffic generation and road safety; and/or
Page 46 of 112

Page 47

M. The proposal will not demonstrably damage the local economy in
terms of tourism or recreation. 
8 PLANNING ISSUES 
8.1 The main planning issue to be considered in determining this
application is whether the proposal complies with development plan
policies unless material planning considerations indicate otherwise.
The representations and consultation responses received are material
considerations and should be considered by the ECU. 
Principle of development 
8.2 The majority of the proposed site forms part of an allocated economic
land supply site (MLDP reference e14).  The land to the west of the
cycleway, which includes the route of the access to the BESS site, was
allocated for Class 4 (Business) and Class 5 (General Industry) uses in
the Midlothian Local Plan 2003.  The adoption of the MLDP in 2017
expanded the range of uses to include Class 6 (Storage or Distribution)
uses.  The MLDP also created a new allocation (MLDP reference Ec2),
to the east of the previous allocation, with the identified uses being
Class 4 and Class 5.  The principle of development, of an appropriate
scale and character, on the allocated portions of the site has been
established by virtue of the history of allocation. 
8.3 The proposal site extends to the east of allocated site Ec2 and includes
an area of ground identified as being prime agricultural land within the
green belt.  The data on Land Capability for Agriculture is based on
maps published between 1984 and 1986.  The land within the proposal
site that is identified as being prime agricultural land was subject to
groundworks associated with the construction of the A68, and it is now
comprised of poor quality made ground.  The land to the east and
south of the made ground is in active agricultural use for arable crops,
however the identified prime agricultural land within the proposal site
has not been used for agricultural purposes since construction work
started on the A68.  Given the poor quality of the land, its proximity to
the allocated land and the remaining usable agricultural land to the east
the loss of the green belt would not undermine the aims of the green
belt. 
8.4 The proposed use does not comply with the allocated use classes,
however, use as a BESS does not sit within any of the 11 use classes
set out in the Town and Country Planning (Use Classes) (Scotland)
Order 1997 and there are no allocated sites for use as a BESS. NPF4
is strongly supportive of development that will aid just transition and
help tackle the climate crisis. Battery energy storage systems will help
Scotland meet such targets by adding flexibility and resilience to the
electricity supply network. Focussing such development on sites
already allocated for development is a sustainable solution that is line
with the overarching spatial principles of NPF4.
Page 47 of 112

Page 48

Safety
8.5 Whilst BESS developments can be dangerous if they go on fire, the
same can be said of lots of forms of development and they present no
greater risk of fire than other forms of development.  BESS schemes
are designed to isolate fires and facilitate firefighting, thereby reducing
the risk of fire spreading from one unit to another.  Allocated Class 5
uses such as factories or waste transfer stations could also present fire
risks. 
8.6 Vehicles accessing the main part of the proposal site will need to cross
the existing cycleway, however, once the construction phase is
completed trip generation is forecast to be in the region of two to three
trips per week.  The allocated Class 4 or 5 uses would generate
significantly greater daily vehicle movements across the cycleway.
8.7 The existing substation at Smeaton is only 170m from the site
boundary and any risk associated with pupils gaining access to the
proposal site is no greater than the risk at the substation. The BESS
site will be enclosed with stock fencing and the BESS units will be sited
within a compound enclosed by 3m high palisade fencing. The
compounds will be monitored via CCTV. 
Loss of economic land
8.8 The original allocated economic land site, e14, has excellent access to
the strategic road network, however, despite consistent marketing and
three unsuccessful development proposals the site has remained
undeveloped for over 20 years.  The proposed development will result
in improvements to the access track that passes through e14 and will
create drainage infrastructure that could be expanded upon to facilitate
development of e14.  Furthermore, the BESS development has the
potential to raise the profile of the site which could encourage further
developments.  Development of allocated economic land with a
proposal that benefits the wider economy and aids just transition is a
more sustainable approach to development than the alternative of an
allocated site sitting vacant whilst an unallocated site is developed.
Amenity
8.9 Disruption to the amenity of local residents and to the schools campus
will be similar to the disruption that would be expected were the site to
be developed for its allocated uses.  It is common practice for
developments of this scale to utilise a Construction Environment
Management Plan (CEMP) to control and mitigate impacts on amenity
during the construction process. The application is accompanied by a
draft CEMP and it is the standard practice of the ECU to condition the
use of CEMPs. 
8.10 Disruption to amenity during regular operations will be less than would
be expected with the allocated Class 5 use.  The proposed layout of
Page 48 of 112

Page 49

the development will provide greater separation distance from the
schools campus than a Class 4 or Class 5 use making full use of the
allocated area.
Visual appearance
8.11 The development will be of a utilitarian design with limited architectural
merit; however, the scale of the containers will ensure that the
development will be of a lower level than would be expected with Class
4 or Class 5 development.  Groundworks associated with the
development will create a 1.5m tall bund along the eastern side of the
development plot and landscaping buffers will be formed along the
northern, western and southern boundaries of the site. Once the
landscape planting has established the visual impact of the
development will be no greater than would be expected with the
allocated uses.
9 RECOMMENDATION
9.1 The recommendation is that the planning authority confirm to the
Scottish Government’s Energy Consents Unit that it does not object to
the proposal subject to conditions on any grant of planning permission
to address and regulate the following matters:
1. Implementation in accordance with approved layout and
requirements of the section 36 consent.
2. Commencement of development – duration of permission.
3. Financial guarantee to secure site restoration if required.
4. Construction Environment Management Plan (CEMP).
5. Site decommissioning, restoration and aftercare details.
6. The requirement to remove any redundant equipment.
7. Proposed levels details.
8. Details of design.
9. The appointment of a monitoring officer/the setting of monitoring
arrangements.
10. Landscape works.
11. Soil management plan.
12. Biodiversity enhancement plan.
13. Compliance with the mitigation measures detailed in the Ecological
Impact Assessment Report.
14. Site access details.
15. Construction traffic controls.
16. Measures to ensure safe operation of National Cycle Network
Route 1.
17. Surface water drainage.
18. Noise and vibration.
19. Lighting.
20. Archaeological investigation.
21. Measures to maintain the safety of the high-pressure gas pipeline
Page 49 of 112

Page 50

22. Site investigation and, if required, remediation measures to identify
and address any risks associated with historic coal mining.
23. Site investigation and, if required, remediation measures to identify
and address any contaminated land on the site.
24. Invasive and non-native species survey and, if required,
remediation plan.
Peter Arnsdorf
Planning, Sustainable Growth and Investment Manager
Date: 22 November 2024
Application No:    24/00537/S36
Applicant:  Salters Battery Storage Limited
Agent:       RPS
Validation Date:  21 August 2024 
Contact Person:  Graeme King, Planning Officer 
Email:   graeme.king@midlothian.gov.uk 
Background Papers: 14/00833/PAC, 15/00026/SCR, 15/00543/SCR,
16/00724/SCO, 16/00893/PPP, 19/00012/PAC,
21/00238/PAC, 21/00512/PAC, 21/00584/SCO
Attached Plans: Location Plan, Site/Landscape Plan, Elevations
Page 50 of 112

Page 51

N
Midlothian Council
Fairfield House
8 Lothian Road
Dalkeith, EH22 3AA
Reproduced from the Ordnance Survey map with the
permission of the controller of Her Majesty's Stationary Office.
Crown copyright reserved. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil
proceedings.
Planning Service
Place Directorate
Application Site (24/00537/S36)
e14 - Salter's Park
Ec2 - Salter's Park Extension
Greenbelt
Midlothian Council Licence No. AC0000811376 (2024)
Section 36 consultation for formation of Battery
Energy Storage System facility with ancillary buildings
and associated works.
Salter's Park Extension (Site Ec2), Salter's Road
Dalkeith.
File No. 24/00537/S36
Scale 1:6000Page 51 of 112

Page 52

AUX
BACK
UP
SUPPLY
SPT BUILDING
APPLICANTS
BUILDING
CONTAINER
CONTAINER
HARMONIC
FILTER
HARMONIC
FILTER
TX
TX
TX
TX
FIRE
W
ATER
TANK
FIRE
W
ATER
TANK
FIRE
W
ATER
TANK
FIRE
W
ATER
TANK
CAR
PARKING
Legend
Existing vegetation outside of site
boundary.
Existing hedgerows to be retained
Existing vegetation to be retained (within
Site Boundary) and protected in
accordance with BS5837
Proposed habitat area - scrub and
scattered tree planting comprised of
locally appropriate native species,
including evergreen species.
Proposed attenuation pond with a mix of
marginal, submerged and floating aquatic
plants
Indicative location of underground Gas
Pipeline (5m
buffer indicated )
Soft Landscape Elements - habitat retention, enhancement and creation
Proposed mounding (1.5m
height)
Proposed habitat area - 
wildflower
grassland seeding areas.
Proposed habitat area - grassland
seeding areas, maintained as short
sward grassland
NOTES
check
amendments
rev
date
1.
Verifying Dimensions.
The contractor shall verify dimensions against such other drawings or
site conditions as pertain to this part of the work.
2.
Existing Services.
Any information concerning the location of existing services indicated
on this drawing is intended for general guidance only.  It shall be the
responsibility of the contractor to determine and verify the exact
horizontal and vertical alignment of all cables, pipes, etc. (both
underground and overhead) before work commences.
T
+44 (0) 28 90 667914
F 
+44 (0) 28 90 668286
W
www.rpsgroup.com/ireland
E
ireland@
rpsgroup.com
Elmwood House
74 Boucher Road
Belfast
BT12 6RZ
Drawing Number
Project Number
Sheet Size
Client
Revision
Drawing Scale
Project
Title
Status
Approved By
Drawn By
Checked By
Date
Salters Battery Storage Limited
Salters BESS
(Container Layout)
Landscape Mitigation Plan
NI2828
A1
1:1250
2828.5.02
SA
Planning
E
-
-
20/01/2024
SA
Updated Layout
A
Mar.'24
SA
Updated Layout
B
April'24
SA
Updated Layout
C
April'24
SA
Updated Layout
D
May '24
SA
Updated Red Line
E
July '24
Page 52 of 112

Page 53

Page 53 of 112

Page 54

Page 54 of 112

Page 55

Planning Committee
Monday 9 December 2024
Item No 5.4
SECTION 42 APPLICATION (18/00082/S42) TO AMEND CONDITIONS 2
AND 3, TO EXTEND THE TIME TO COMPLETE THE RESTORATION OF
QUARRY, IMPOSED ON A GRANT OF PLANNING PERMISSION
(06/00689/FUL) FOR THE EXTRACTION AND PROCESSING OF SAND AT
UPPER DALHOUSIE SAND QUARRY, BONNYRIGG.  THE APPLICATION
IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT
REPORT SUBMITTED UNDER THE TOWN AND COUNTRY PLANNING
(ENVIRONMENTAL IMPACT ASSESSMENT) (SCOTLAND)
REGULATIONS 2011
Report by Chief Officer Place
1 SUMMARY OF APPLICATION AND RECOMMENDED DECISION
1.1 In August 2009 planning permission 06/00689/FUL was granted for
the extraction and processing of sand and the siting of associated
plant and office at Upper Dalhousie, Bonnyrigg.  This application
seeks planning permission to amend conditions 2 and 3 of
planning permission 06/00689/FUL to extend the restoration
periods of the two extraction areas.  The application is
accompanied by an Environmental Impact Assessment Report
which has been submitted in terms of the EIA (Scotland)
(Regulations) 2011. 
1.2 There have been no representations received.  Consultation
responses have been received from The Coal Authority, Historic
Environment Scotland, the Scottish Environment Protection
Agency (SEPA), Scottish Water, NatureScot (previously Scottish
Natural Heritage), Bonnyrigg and Lasswade Community Council,
The Council’s Archaeology Advisor, The Council’s Ecological
Advisor (TWIC), The Council’s Senior Manager Protective
Services, the Council’s Senior Manager Neighbourhood Services
(Flood Risk and Transportation) and the Council’s Legal Services
Manager.
1.3 The relevant development plan policies are policies 1, 2, 3, 4, 5, 6,
7, 20, 22, 23 and 33 of National Planning Framework 4 and policies
MIN1, MIN2, RD1, ENV2, ENV4, ENV7, ENV9, ENV10, ENV11,
ENV15, ENV17, ENV18, ENV22, ENV23, ENV24, ENV25, IMP1 and
IMP3 of the Midlothian Local Development Plan 2017.
Page 55 of 112

Page 56

1.4 At its meeting of 28 August 2018 the Committee approved the
application subject to conditions and the developer
demonstrating, to the written satisfaction of the Council, that they
have sufficient bond provision/insurance in place to ensure that,
in the event that the operator is not able to restore the site,
financial provision is made to enable the site to be restored in
accordance with an approved restoration plan. 
1.5 This report provides an update on the bond provision and
considers the impact of the adoption of National Planning
Framework 4 (NPF4) on the assessment of the proposal. 
1.6 The recommendation is to grant planning permission subject to
conditions. 
2 LOCATION AND SITE DESCRIPTION 
2.1 The Upper Dalhousie Sand Quarry is located to the southeast of
Bonnyrigg and comprises two extraction areas separated by an area of
woodland.  Area A is situated to the southeast of the woodland and
Area B is to the northwest.  The existing processing area, site office
and welfare facilities are located in the northern portion of Area A,
close to the site access. The site is accessed from the B6392
distributor road to the south of the Hopefield residential development. 
The site measures approximately 18 hectares in area. 
2.2 Extraction from Area A has been completed.  Extraction from Area B
commenced in 2016 and is ongoing.  Area A has been partially
restored, with the un-restored area being used for settlement ponds
and to accommodate the processing plant and welfare facilities. 
2.3 The site is bounded by agricultural land and areas of woodland with
Whitehill House (and associated residential development) and
Rosewell beyond to the west/southwest and Bonnyrigg beyond to the
north.  The closest dwellinghouses are Parkneuk, at approximately
200m to the west and the residential development at Whitehill House,
at approximately 400m to the southwest. 
2.4 Land to the northwest of Area B was previously quarried for sand and
gravel in the 1950s.  This area was subsequently utilised by the local
authority for the disposal of domestic waste, principally ash, during the
1960s.  The area between Area B and the private property at Parkneuk
was also utilised by the local authority for the disposal of domestic
wastes during the 1960s. 
3 PROPOSAL 
3.1  The application, made under Section 42 of the Town and Country
Planning (Scotland) Act 1997 as amended by the Planning etc.
Page 56 of 112

Page 57

(Scotland) Act 2006 (hereafter referred to as the Act), is to extend the
restoration periods for the Dalhousie Sand Quarry. 
3.2 A Section 42 application is in itself a planning application - a particular
kind of planning application for development without complying with a
condition/s previously imposed on an earlier grant of planning
permission. A grant of planning permission under Section 42 results in
an entirely new planning permission which will supersede the original
permission if implemented. Therefore, if planning permission is granted
for this application, it will supersede planning consent 06/00689/DPP. 
3.3 Although a Section 42 application is a new planning application in law
the Act states “on such an application the planning authority shall
consider only the question of the conditions subject to which planning
permission should be granted”.  The principle, layout and form of
development are not subject to assessment. 
3.4 Condition 2 of planning application 06/00689/DPP, which relates to
extraction Area A, states: 
“Permission for the extraction of sand from area A as indicated on the
approved drawing ED20614/FIG3.2 'AREA A EXCAVATION' is granted
for a period of 7 years from the date of commencement of operations
on the site, such date to be notified to the Planning Authority by the
applicants within one week of commencement; and shall be followed
by the completion of the restoration of Area A to a condition suitable for
agriculture, woodland, as per the details of the Environmental
Statement chapter 3.6 to 3.8 as represented in ED20614/FIG4.1
'REVISED RESTORATION MASTERPLAN' and in accordance with the
requirements of conditions 51 to 56 below.” 
3.5 Condition 3 of planning application 06/00689/DPP, which relates to
extraction Area B, states: 
“Permission for the extraction of sand from area B as indicated on the
approved drawing ED20614/FIG3.3 'AREA B EXCAVATION' is granted
for a period of 7 years starting from the date of the completion of the
restoration of site A as required by conditions 51 to 56; and shall be
followed by the completion of the restoration of Area B to a condition
suitable for agriculture, woodland, as per the details of the
Environmental Statement chapter 3.6 to 3.8 as represented in
ED20614/FIG4.1 'REVISED RESTORATION MASTERPLAN' and in
accordance with the requirements of conditions 51 to 56 below.” 
3.6 The application seeks permission to: 
• extend the permitted period of time for the completion of the
restoration of Area A by three years (condition 2 of planning
permission 06/00689/FUL);
Page 57 of 112

Page 58

• extend the permitted period of time for the completion of the
working/extraction of sand and the restoration of Area B by six
years (condition 3 of planning permission 06/00689/FUL);
• work below the water table in Area B to extract additional sand
reserves (details covered by the plans approved by condition 3
of planning permission 06/00689/FUL); and,
• update the restoration plans for Area A and Area B (conditions 2
and 3 of planning permission 06/00689/FUL). 
In brief this will see the site works and restoration being completed by
31 December 2030. 
3.7 The original application was accompanied by an Environmental
Statement complying with The Town and Country Planning
(Environmental Impact Assessment) (Scotland) Regulations 2011 (the
2011 Regulations).  Whilst the application was submitted after The
Town and Country Planning (Environmental Impact Assessment)
Regulations 2017 (the 2017 Regulations) had come into force, a
transitional provision within the 2017 Regulations allows for
applications to be assessed under the 2011 Regulations where the
Scoping Opinion was issued under the 2011 Regulations. The
Environmental Statement includes the following reports as appendices: 
• Pre-Application Consultation Report;
• Preliminary Ecological Appraisal; and 
• Bat Activity Assessment; 
3.8 The application was updated in 2024 with the submission of the
following reports and plans: 
• NPF4 Policy Update;
• Updated Preliminary Ecological Appraisal;
• Bat Activity Report; and 
• Updated restoration details. 
4 BACKGROUND 
4.1 Planning application 06/00689/FUL for the extraction and processing of
sand and the erection of the associated plant and office provision at
Upper Dalhousie was granted permission in August 2009.  This
consent has been implemented and work continues on the site. 
4.2 Planning application 13/00064/DPP for the installation of sand
processing plant and a conveyor at the quarry was granted permission
in March 2013. 
4.3 An environmental impact assessment (EIA) scoping request
(17/00380/SCO) for the extension of operations was submitted in May
2017.  The applicant was advised what matters need to be covered by
Page 58 of 112

Page 59

an EIA which need to be submitted under schedule 2 of the EIA
Regulations. 
4.4 A related planning application (18/00081/DPP) for the extension of the
quarry is subject to assessment and is also presented on the
Committee agenda.  The application is related to this proposal in that
the extension area (Area C) will provide additional material for the
restoration of Area B. 
4.5 The current application and application 18/00081/DPP were both
reported to the Committee at its meeting of 28 August 2018.  The
Committee approved both applications subject to conditions and to the
developer demonstrating, to the written satisfaction of the Council, that
they have sufficient bond provision/insurance in place to ensure that, in
the event that the operator is not able to restore the site, financial
provision is made to enable the site is restored in accordance with an
approved restoration plan. 
5 CONSULTATIONS 
5.1 The Coal Authority confirms that the application site falls within a
defined Development High Risk Area.  However, the conditions subject
to review are not material to coal mining issues and therefore, The
Coal Authority has no comments. 
5.2 Historic Environment Scotland (HES) do not have any comments to
make on the proposals – however, the application should still be
determined in accordance with national and local policies and guidance
with regard the historic environment. 
5.3 The Scottish Environment Protection Agency (SEPA) does not
object to the application as it is an amendment of conditions which do
not materially change the operation of the quarry. 
5.4 Scottish Water does not object to the application. 
5.5 Scottish Natural Heritage (SNH) (now known as NatureScot) does
not object to the application subject to conditions securing the
conclusions set out in the Environmental Statement regarding
ecological receptors (ancient woodland and protected species). The
new Restoration Masterplan for the site appears to be dependent on
securing consent for extraction in Area C (subject of a separate
planning application). 
5.6 The Bonnyrigg and Lasswade Community Council (the community
council merged with Poltonhall and Hopefield Community Council in
2022 to create Bonnyrigg and District Community Council) advise
that they engaged their local community regarding the existing and
potential future impacts of the quarrying activity, in particularly the
traffic implications, the result of which was that no concerns were
Page 59 of 112

Page 60

raised and as such the Community Council does not object to the
application.  However, the Community Council expect Midlothian
Council to secure a bond to ensure the site’s restoration. 
5.7 The Council’s Archaeology Advisor had no comments to make on
the application. 
5.8 The Council’s Ecological Advisor – The Wildlife Information
Centre (TWIC) has confirmed that both the updated Preliminary
Ecological Appraisal and the updated Bat Activity Report are thorough
and professional.  Further protected species surveys will be required
prior to restoration works commencing. 
5.9 The Council’s Senior Manager Protective Services (Contingency
Planning and Environmental Health) advises that the site is currently
well managed and operates without giving rise to noise or dust
nuisance complaints, officers are of the opinion that no additional
mitigation measures are required subject to conditions to control noise
and dust emissions arising from the operation of the site. 
5.10 The Council’s Senior Manager Neighbourhood Services (Flood
Risk and Transportation) does not object to the application. 
5.11 The Council’s Legal Services have advised that as the landowner is
Crown Estates Scotland the risk to the Council of the landowner and
applicant not restoring the land is low, so if the Council are satisfied
with the terms of the bond, we do not need to be a party to it, it shall be
between the applicant and landowner. 
6 REPRESENTATIONS 
6.1 No representations have been received. 
7 PLANNING POLICY 
7.1 The development is comprised of National Planning Framework 4
(2023) and the Midlothian Local Development Plan 2017. The following
policies are relevant to the proposal: 
National Planning Framework 4 (NPF4) 
7.2 NPF4 is a National Spatial Strategy for Scotland until 2045 and sets out
a vision for future places using six overarching spatial principles: 
• Just transition.
• Conserving and recycling assets.
• Local living.
• Compact urban growth.
• Rebalanced development.
• Rural revitalisation.
Page 60 of 112

Page 61

7.3 Policy 1 Tackling the climate and nature crisis; sets out to
encourage, promote and facilitate development that addresses the
global climate emergency and nature crisis. 
7.4 Policy 2 Climate mitigation and adaptation; sets out to encourage,
promote and facilitate development that minimises emissions and
adapts to the current and future impacts of climate change. 
7.5 Policy 3 Biodiversity; sets out to protect biodiversity, reverse
biodiversity loss, deliver positive effects from development and
strengthen nature networks. 
7.6 Policy 4 Natural Places; sets out to protect, restore and enhance
natural assets making best use of nature-based solutions. 
7.7 Policy 5 Soils; sets out to protect carbon-rich soils, restore peatlands
and minimise disturbance to soils from development. The policy also
sets out acceptable scenarios for development on prime agricultural
land. 
7.8 Policy 6 Forestry, woodland and trees; sets out to protect and
expand forests, woodland and trees. 
7.9 Policy 7 Historic assets and places; sets out to protect and enhance
historic environment assets and places, and to enable positive change
as a catalyst for the regeneration of places. 
7.10 Policy 20 Blue and green infrastructure; sets out to protect and
enhance blue and green infrastructure and their networks. 
7.11 Policy 22 Flood risk and water management; sets out to strengthen
resilience to flood risk by promoting avoidance as a first principle and
reducing the vulnerability of existing and future development to
flooding. 
7.12 Policy 23 Health and Safety; sets out to protect people and places
from environmental harm, mitigate risks arising from safety hazards
and encourage, promote and facilitate development that improves
health and wellbeing. 
7.13 Policy 33 Minerals; sets out to support the sustainable management of
resources and minimise the impacts of extraction of minerals on
communities and the environment. 
Part d - development proposals for the sustainable extraction of
minerals will only be supported where they: 
i. Will not result in significant adverse impacts on biodiversity,
geodiversity and the natural environment, sensitive habitats and
Page 61 of 112

Page 62

the historic environment, as well as landscape and visual
impacts;
ii. provide an adequate buffer zone between sites and settlements
taking account of the specific circumstances of individual
proposals, including size, duration, location, method of working,
topography, and the characteristics of the various environmental
effects likely to arise;
iii. can demonstrate that there are no significant adverse impacts
(including cumulative impact) on any nearby homes, local
communities and known sensitive receptors and designations;
iv. demonstrate acceptable levels (including cumulative impact) of
noise, dust, vibration and potential pollution of land, air and
water;
v. minimise transport impacts through the number and length of
lorry trips and by using rail or water transport wherever practical;
vi. have appropriate mitigation plans in place for any adverse
impacts;
vii. include schemes for a high standard of restoration and aftercare
and commitment that such work is undertaken at the earliest
opportunity. As a further safeguard a range of financial
guarantee options are available, and the most effective solution
should be considered and agreed on a site-by-site basis.
Solutions should provide assurance and clarity over the amount
and period of the guarantee and in particular, where it is a bond,
the risks covered (including operator failure) and the triggers for
calling in a bond, including payment terms. 
7.14  NPF4 states that Local Development Plans should support a landbank
of construction aggregates of at least 10-years at all times in the
relevant market areas, whilst promoting sustainable resource
management, safeguarding important workable mineral resources,
which are of economic or conservation value, and take steps to ensure
these are not sterilised by other types of development. 
Midlothian Local Development Plan 2017 
7.15 Policy MIN1: Areas of Search for Surface Extraction identifies Upper
Dalhousie as being an area for the extraction of sand and gravel where
surface mineral extraction may be acceptable in principle. The policy
states that the identification of an area of search does not indicate the
Council’s acceptance of any particular proposal for the winning and
working of a surface mineral resource within any or all of that area of
search. Outwith the areas of search there is a presumption against
surface mineral extraction. In addition the policy safeguards mineral
resources from sterilisation, in specific circumstances. 
7.16 Policy MIN2: Surface Mineral Extraction requires proposals for
mineral extraction to meet the criteria set out in the Supplementary
Guidance on Resource Extraction. They will not be permitted where
they would have a significant adverse effect on communities, sensitive
Page 62 of 112

Page 63

uses or the environment and will only be supported if the Council is
satisfied that they are acceptable in relation to the following matters: 
• effect on the health and amenity of settlements, communities
and housing groups or other sensitive uses;
• effect on the landscape, in particular that of the Green Belt,
Pentland Hills Regional Park, and Special Landscape Area;
• effect on soils, in particular prime agricultural land, and peatland;
• effect on the water environment;
• effect on nature conservation and biodiversity, in particular sites
of international, national or local nature conservation value;
• effect on the historic environment, in particular: Conservation
areas, scheduled monuments, listed buildings, historic gardens
and designed landscapes, historic battlefields, significant
archaeological sites (and, where relevant, the settings of the
aforementioned designated areas or buildings);
• effect on the road network, particularly local roads;
• cumulative effects of the proposal when combined with other
consented or operational mineral extraction or landfill activities;
• effect on the local economy in terms of tourism, leisure or
recreation; and,
• robustness and suitability of proposals for restoration and
aftercare. 
7.17 The extraction of a secondary material (for example, fireclay from a
coal extraction site) is supported provided that its removal does not
detract from high quality restoration or have unacceptable
environmental effects (including from cumulative vehicle movements).
In order that the supply and demand for aggregates can be monitored,
operators of new aggregates sites will be required to supply annual
statements of production and remaining reserves. 
7.18 Policy RD1: Development in the Countryside sets out where
appropriate development would be acceptable in the countryside
subject to defined criteria.  One acceptable use is resource extraction
in compliance with Policy MIN1.  All such development requires being
of a scale or character appropriate to the rural area and landscape,
capable of being appropriately accessed and serviced, have
acceptable drainage provision and water supply and be accessible by
public transport and services, where appropriate. 
7.19 Policy ENV2 Midlothian Green Networks supports development
proposals brought forward in line with the provisions of the Plan that
help to deliver the green network opportunities identified in the
Supplementary Guidance on the Midlothian Green Network. 
7.20 Policy ENV4: Prime Agricultural Land does not permit development
that would lead to the permanent loss of prime agricultural land unless
there is appropriate justification to do so.
Page 63 of 112

Page 64

7.21 Policy ENV7: Landscape Character states that development will not
be permitted where it significantly and adversely affects local
landscape character.  Where development is acceptable, it should
respect such character and be compatible in terms of scale, siting and
design.  New development will normally be required to incorporate
proposals to maintain the diversity and distinctiveness of the local
landscapes and to enhance landscape characteristics where they have
been weakened. 
7.22 Policy ENV9: Flooding presumes against development which would
be at unacceptable risk of flooding or would increase the risk of
flooding elsewhere.  It states that Flood Risk Assessments will be
required for most forms of development in areas of medium to high risk,
but may also be required at other locations depending on the
circumstances of the proposed development.  Furthermore it states that
sustainable urban drainage systems will be required for most forms of
development, so that surface water run-off rates are not greater than in
the site’s pre-developed condition, and to avoid any deterioration of
water quality. 
7.23 Policy ENV10: Water Environment requires that new development
pass surface water through a sustainable urban drainage system
(SUDS) to mitigate against local flooding and to enhance biodiversity
and the environment. 
7.24 Policy ENV11: Woodland, Trees and Hedges states that development
will not be permitted where it could lead directly or indirectly to the loss
of, or damage to, woodland, groups of trees (including trees covered by
a Tree Preservation Order, areas defined as ancient or semi-natural
woodland, veteran trees or areas forming part of any designated
landscape) and hedges which have a particular amenity, nature
conservation, biodiversity, recreation, landscape, shelter, cultural, or
historical value or are of other importance. 
7.25 Policy ENV15: Species and Habitat Protection and Enhancement
presumes against development that would affect a species protected
by European or UK law. 
7.26 Policy ENV 17 Air Quality states that the Council may require further
assessments to identify air quality impacts where considered requisite.  
It will refuse planning permission, or seek effective mitigation, where
development proposals cause unacceptable air quality or dust impacts. 
7.27 Policy ENV18: Noise requires that where new noise sensitive uses are
proposed in the locality of existing noisy uses, the Council will seek to
ensure that the function of established operations is not adversely
affected. 
Page 64 of 112

Page 65

7.28 Policy ENV22: Listed buildings does not permit development which
would adversely affect the character or appearance of a listed building,
its setting or any feature of special architectural or historic interest. 
7.29 Policy ENV23: Scheduled Monuments states that development which
could have an adverse effect on a scheduled monument, or the
integrity of its setting, will not be permitted. 
7.30 Policy ENV24: Other Important Archaeological or Historic Sites
seeks to prevent development that would adversely affect regionally or
locally important archaeological or historic sites, or their setting 
7.31 Policy ENV25: Site Assessment, Evaluation and Recording requires
that where development could affect an identified site of archaeological
importance, the applicant will be required to provide an assessment of
the archaeological value of the site and of the likely impact of the
proposal on the archaeological resource. 
7.32 Policy IMP1: New Development gives the planning authority the policy
basis to impose appropriate planning conditions and controls to
mitigate the impact of the development. 
7.33 Policy IMP3: Water and Drainage require sustainable urban drainage
systems (SUDS) to be incorporated into new development. 
8 PLANNING ISSUES 
8.1 The main planning issue to be considered in determining this
application is whether the proposal complies with development plan
policies unless material planning considerations indicate otherwise.
The consultation responses received are material considerations. 
Principle of development 
8.2 Planning permission for the extraction and processing of sand and
associated works was granted in 2009.  The site was then given
continued support in the MLDP and identified as an area of search for
mineral extraction.  This application, to extend the period of extraction
and restoration, does not change this presumption in favour of
development. 
8.3 NPF4 was adopted in February 2023. Policy 33 supports the
sustainable extraction of minerals.  The application relates to existing
areas of extraction and processing which are operating in compliance
with points i to vii of Policy 33 d).  The adoption of NPF4 has not
changed the presumption in favour of ongoing development. 
Page 65 of 112

Page 66

Amendments to Conditions 2 and 3 
8.4 The application seeks to extend the restoration period of Area A by
three years and to extend the extraction and restoration period of Area
B by six years.  This is to allow the continued extraction of the
resource; including the extraction of sand from below the water table in
Area B.  This proposal is seen as part of a wider strategy to maximise
the onsite resource which includes extending the extraction area into
Area C (subject to planning application 18/00081/DPP).  It is not
uncommon to adjust the operational time periods of resource extraction
sites in response to fluctuating demands for materials which influences
the rates of extraction, the ability to extract more material than originally
expected and to ensure the best possible restoration programme. 
8.5 Extraction from Area A is completed. Restoration of this part of the site
is underway; but behind schedule, in part due to significant level
changes which need to be addressed (up to a 10m variance in places)
and the siting of water settling ponds on this part of the site.  Additional
ground works and tree/woodland planting is still required in accordance
with the restoration masterplan and as such it is considered necessary
to extend the operation period of the site for an additional three years. 
The small area occupied by the site office and welfare building will be
restored once site operations across the whole site are complete. 
8.6 Extraction and restoration of Area B is to take place over an additional
six-year period.  The restoration of Area B is proposed to be completed
by 31 December 2030.  The restoration masterplan shows the levels
dropping around the southwestern, northwestern and southeastern
boundaries of the site. The maximum drop in levels amounts to 16m.
These areas will be planted with woodland planting, this will integrate
the level change into the landscape.  The central, fairly level, area of
the site is to be restored to agricultural grassland.  Considering the
potential to extract further material and undertake the required
restoration it is considered reasonable and necessary to extend the
operation period of the site to 31 December 2030. 
8.7 Area C is the subject of a separate planning application
(18/00081/DPP); however it is worth noting that the proposed
restoration profiles of Areas A and B will tie into this extended
extraction area and that some of the material from the proposed
extension will be used to restore Area B. The proposed restoration
masterplan includes additional informal footpaths, a sand face for
nesting sand martins and a pond. The potential biodiversity and wildlife
benefits of the restoration proposals are a positive benefit of the
development. 
8.8 The consequence of the extending extraction in Area B and the
delayed restoration of Areas A and B is that the environmental impacts
of the development will be extended over a longer period.  However,
Page 66 of 112

Page 67

the existing quarry has not generated any significant complaints and
appears to be effectively managed. 
Restoration bond 
8.9 The applicant’s agent has confirmed that there is an agreement in
place between the applicant and the landowner, Crown Estate
Scotland. Funds for restoration are secured via a bank guarantee. The
restoration costs have been prepared by suitably qualified
professionals utilising a comprehensive database of comparable costs
and the landowner is satisfied that the costings are sufficient. 
Environmental Statement 
8.10 The Environmental Statement submitted with the application sets out
the findings of an Environmental Impact Assessment process carried
out by the applicant under The Town and Country Planning
(Environmental Impact Assessment) (Scotland) Regulations 2011.  The
process identifies the likely significant environmental effects of the
development and suggests ways in which any significant negative
environmental effects can be mitigated.  The statement considers the
following issues: 
• Landscape and visual impact;
• Ecology;
• Water resources; and
• Noise 
8.11 The environmental statement identifies that there are no long-term
detrimental consequences of the proposed development. The proposal
does present an opportunity for potential longer term environmental
benefits subject to the restoration programme, which, if undertaken in a
sensitive manner, could enhance the environment for the benefit of
wildlife, the local landscape, drainage, pollution prevention and future
recreational and agricultural uses. 
8.12 The EIA process requires that alternative options to the proposed
scheme are considered, and a justification is given for the preferred
option chosen. The options considered were: 1) do nothing with the
site; 2) reduce the extraction area; 3) extract from an alternative site;
and 4) work above the water table only.  The preferred development
option (continued working of the current site) is considered the best
option for a number of reasons.  Firstly, the area is identified as an area
of search in the MLDP for the extraction of construction aggregate to
supply the local area.  Secondly, not continuing with the ongoing
extraction would have a detrimental impact on the provision of
construction sand to meet demand in the region.  Thirdly, reducing the
extraction area (by not fully exploiting the resource in Area B) would
risk sterilising existing available reserves.  Fourthly, the current site has
minimal detrimental impact on local communities.  Finally, identifying
Page 67 of 112

Page 68

an alternative site would present a significant challenge in terms of the
development plan process and the time taken to reach a point where
material could be extracted. 
9 RECOMMENDATION 
9.1 It is recommended that planning permission be granted for the
following reason: 
The proposed development site is identified as a mineral extraction site
within the Midlothian Local Development Plan 2017; as such there is a
presumption in favour of the proposed development.  This presumption
in favour of development is not outweighed by any other material
considerations.  The proposed amendments to conditions 2 and 3 are
considered not to undermine this policy position or have long term
detrimental environmental impact. The proposal complies with the
relevant policies of National Planning Framework 4 and the Midlothian
Local Development Plan 2017. 
9.2 Subject to the following conditions: 
Duration of the Permission 
1. The development to which this permission relates has commenced and
this permission extends the duration of the consent for extraction and
restoration. Permission for the extraction of sand from areas A and B
(as indicated on the approved drawings Figures 3.1 to 3.7 Proposed
Extraction in the approved Environmental Statement showing the 7
proposed phases of extraction) is granted until the end of 31 December
2026. With the exception of the soil stockpile area, conveyor route,
processing plant, site office and welfare facilities (as indicated on
Drawing No. ED11578 - Figure 1.3 Proposed Site Plan Showing
Proposed Levels) restoration of Areas A and B (as per the details of
the Environmental Statement chapter 3 (paragraphs 3.4.1 to 3.4.3) as
indicatively represented in the Restoration Masterplan (drawing no ED
13814-001) and in accordance with the requirements of the conditions
on this permission) shall be completed by the end of 31 December
2030. Should extraction of Area C (as indicated on Drawing No.
ED11578 - Figure 1.3 Proposed Site Plan Showing Proposed Levels)
not commence within 3 years of the date of this consent the said soil
stockpile area, conveyor route, processing plant, site office and welfare
facilities shall be restored (as per the above restoration details) by the
end of 31 December 2030. 
2. Within six months of the date of this permission a phasing plan
detailing the timeline for the restoration of Area A, and the extraction
and restoration of Area B shall be submitted to and approved in writing
by the Planning Authority. An updated timeline shall be submitted to
the Planning Authority on an annual basis (on the anniversary of this
permission). Development shall comply with the approved phasing
Page 68 of 112

Page 69

plan, or such alternatives as may be agreed in writing by the Planning
Authority. 
Reason: To enable the Planning Authority to retain effective control
over the progress of operations and the restoration of the site. 
3. Within six months from the date of this permission detailed proposals
for the restoration of the whole site (Areas A and B), in order to achieve
the indicative restoration identified in the Restoration Masterplan
(drawing no ED 13814-001), shall be submitted for the approval of the
Planning Authority.  These proposals shall include: 
(a) A detailed landscape restoration plan giving full details including
a planting schedule showing species, planting densities, sizes,
protection measures, and specification notes for all ground
preparation, soil, planting, any hard landscape. The plan shall
identify the areas of advanced planting. Local provenance stock
shall be used where possible and any seed and woodland
planting mixes shall be designed with ecological input to ensure
they provide maximum foraging and habitat benefit for species
as identified in the Preliminary Ecological Appraisal issued
August 2024 (Job number: ED13814, Report Number: 0001,
Version: V0.1, Status: Final); 
(b) A soil plan setting out the depths of soil in all planted parts of the
site ensuring the soil depth is adequate for the restoration
planting proposed; 
(c) A Site Biodiversity Action Plan demonstrating how restoration
will protect and enhance biodiversity, and strengthen nature
networks; 
(d) the detailed specification, together with the necessary drawings,
for the re-instatement of the agricultural pastures within the site,
including details profiles and gradients, and all planting to be
undertaken alongside the boundaries with a detailed schedule of
species to be planted; 
(e) the detailed specification for the preparation and planting of all
woodland areas, including the numbers, sizes, species and
planting densities of all trees and hedgerows to be planted; 
(f) the location and details of all new fences and walls to be erected
or repaired, within or around the boundaries of the site; 
(g) a series of cross sections (length and width) bisecting the two
extraction areas and the adjoining ancient woodland and
adjacent trees to illustrate the relation between the existing
planting and the proposed site restoration levels and planting; 
Page 69 of 112

Page 70

(h) details of footpath construction; and 
(i) a restoration phase landscape and ecological management plan
to cover a period of five years from the completion of the
restoration landscape works 
Restoration shall comply with the details approved via the discharge of
this condition, or such alternatives as may be approved in writing by
the Planning Authority. 
Reason: To ensure that the restoration of the site is carried out to a
high standard in order to reinstate and, wherever possible, enhance
biological habitats and diversity within the site. 
Protection of water resources 
4. The existing surface water and groundwater monitoring strategy in use
at the site shall continue to be implemented for the duration of the
operations hereby approved. Sampling of surface water and
groundwater within and downstream from the site shall be carried out
in accordance with the agreed strategy, and the results shall be
supplied to SEPA and the Planning Authority.  Thereafter, at periodic
intervals throughout the duration of the operations, as agreed with the
Planning Authority in consultation with SEPA, further sampling shall be
carried out, and the results shall be submitted to SEPA, with copies to
the Planning Authority. 
Reason: In order to monitor the impact of the operations on the quality
and flow of surface water and groundwater, so that any remedial action
can be taken if problems are identified.  
5. The method statement detailing the procedure for the identification,
isolation and treatment of any iron-rich substrate, and a contingency
plan for the treatment of any ferruginous discharges that may appear
after restoration of the site, which has been approved for the existing
site, shall in the event of the appearance of any ferruginous discharges
following the restoration of the site, the applicants, or their successors,
carry out all necessary measures, as identified in the approved
contingency plan. 
Reason: To protect against any ferruginous contamination of water
resources that may result from the rebound of groundwater within the
site, following its restoration. 
6. Before any soil stripping is carried out on any new phase of the Area B,
a perimeter drainage system shall be constructed around the whole of
that phase, any existing drainage ditches shall be diverted, and the
appropriate water treatment area shall be constructed and brought into
use, all in accordance with the approved plans and the requirements of
SEPA. The prohibition on the prior stripping of soils does not apply to
Page 70 of 112

Page 71

those soils which are required to be removed in the formation of new
ditches and water treatment areas. 
Reason: To ensure that facilities for the diversion of surface water
entering the site, and for the reception and treatment of contaminated
water are available from the earliest stages of the development. 
7. All contaminated water shall be treated in appropriate water treatment
areas prior to discharge into any watercourse. The water treatment
facilities shall be of an adequate capacity to cater for the likely
maximum volume of contaminated water, and to control the discharge
flow into any watercourse in accordance with the requirements of
SEPA.  They must be capable of being cleaned without interruption of
the treatment process, and shall be maintained in good working order
throughout the duration of the operations.  The direct discharge of oil,
chemicals or other pollutants into the water treatment facilities, or into
any watercourse within or adjoining the site, shall not be permitted. 
8. Except where stored in double skinned tanks any oil, fuel, lubricant,
paint or solvent stored within the site shall be provided with a suitable
bund or other means of containment for 110% of the storage capacity,
and with no passive means of drainage. 
Reason for conditions 7 & 8: To prevent the contamination of surface
or ground water resources, or of soil resources. 
Protection of Soil Resources 
9. Apart from the work required in accordance with condition 6 above, no
work shall be carried out on any undisturbed part of the site until all
topsoil has been stripped to an average depth of 300mm from the initial
excavation area, all associated working areas, the site service and
sand processing area, haul roads, subsoil and overburden storage
areas; following which, subsoil shall be stripped to an average depth of
600mm from the same areas, with the exception of the subsoil storage
areas. 
10. No work shall be commenced on any subsequent phases of Area B
until the topsoil and subsoil have been removed from these areas; such
soils shall be either used directly for the progressive restoration of
earlier phases of the operations at Upper Dalhousie, or stored in
accordance with the requirements of condition 13 below.  
11. Throughout the period of the extraction and restoration operations, all
parts of the site from which topsoil has not been stripped, or on which
topsoil has been respread, shall be protected from all working areas
and access routes. Work routines for stripping operations, shall be
designed to minimise vehicle traffic on unstripped land, and at all times
the mechanical handling and compaction of topsoil shall be minimised.
Page 71 of 112

Page 72

No vehicle, other than those involved in soil stripping or spreading or
agricultural operations, shall be permitted on any unstripped land. 
12. The stripping of topsoil and subsoil shall only be carried out when
ground conditions are such that no undue damage is done to topsoil
and subsoil (normally in Spring and Summer months, although this
may be extended into dry Autumn periods). Such operations shall be
suspended during adverse weather conditions. 
13. Topsoil and subsoil shall be carefully stored in separate mounds wholly
within the site boundary, and shall be prevented from mixing.  Topsoil
mounds shall not exceed 5 metres in height, and subsoil mounds shall
not exceed 6 metres in height. 
14. All soil storage mounds shall be evenly graded, shaped and drained to
prevent water ponding on or around them; thereafter, they shall be
seeded with an appropriate grass seeds mixture as soon as practically
possible to ensure a reasonable prospect of successful sowing. 
15. No turf, topsoil or subsoil shall at any time be removed from the site. 
Reason for conditions 9 -15: To protect the existing soil resources of
the site, in order to ensure its successful restoration to agricultural or
other appropriate uses, following the completion of sand extraction. 
Overburden Storage 
16. Any overburden not used immediately for the back-filling of previous
cuts, shall be stored in a location to be agreed in writing with the
Planning Authority, wholly within the application boundary, and the
mound shall not exceed 15m in height; the sides and top of the
overburden mound shall be evenly graded and shaped, and they shall
be seeded with a suitable low-maintenance grass seeds mix. 
Reason: To ensure that the storage of overburden is stable and not
unduly obtrusive. 
Protection of Agricultural Interests 
17. Except where otherwise agreed in writing by the Planning Authority, the
applicants shall make the site stock-proof and maintain as such until
restoration of the site is complete. All the existing perimeter hedges,
fences and walls, shall be maintained to protect the site from damage. 
Where the site boundary does not coincide with an existing hedge,
fence or wall, then the applicants shall, unless otherwise agreed in
writing by the Planning Authority, provide and maintain stock-proof
fencing, with gates or cattle grids at every opening, until the restoration
is completed.  Undisturbed hedgerows not affording screening for the
proposed development, within or bounding the site, shall be carefully
maintained, in accordance with good agricultural practice, and be cut
Page 72 of 112

Page 73

and trimmed at the proper season throughout the period of working and
restoration of the site. 
18. All invasive weeds on the site, including particularly those on the
topsoil and subsoil storage mounds, shall be treated as often as
necessary and as determined by the Planning Authority throughout the
life of the site, at an early stage of growth, in order to prevent spreading
within the site or onto adjoining agricultural land. 
19. All types of vermin shall be controlled in a manner approved by the
Planning Authority to prevent them spreading to adjoining agricultural
land. 
Reason for conditions 17-19: To protect the continued efficient
operation of adjoining farmland. 
Adjacent Site Drainage 
20. The works on site shall be designed and implemented to ensure that
they do not negatively impact on the drainage of either the site as
restored or the surrounding agricultural land.  During the aftercare
period the applicant shall ensure both the site and the surrounding
agricultural land has field drainage that is functioning appropriately to
allow productive agricultural activities to continue. This will include: 
(a) ensuring field drainage for the finally restored land is functioning
appropriately; 
(b) protecting and maintaining any ditch, stream, watercourse or
culvert passing though the site which provides drainage for
adjoining land; 
(c) make provision for the installation of the field drainage system
on the site to commence after one full growing season has
elapsed from the time of the final stage of topsoil restoration;
and, 
(d) make provision for the field drainage system to be completed
within two years of topsoil restoration. 
Should there be any complaints received by the Planning Authority
regarding the drainage at the site, which the Planning Authority
consider merit investigation, the applicant shall take all reasonable
steps to address any drainage issues with the site or the surrounding
land, which can reasonably be considered to have resulted from the
works on the site. 
Reason: To ensure the continued adequate drainage of the site, and
adjoining land, in the interests of its continued productive agricultural
use.
Page 73 of 112

Page 74

21. No refuse, soil or waste material from outside the site shall be
deposited within the site for any purpose without the prior written
permission of the Planning Authority. 
Reason: To ensure that site restoration is achieved using existing on-
site materials only. 
22. Any public utilities crossing or adjacent to the site shall be protected or
diverted, as necessary, in accordance with the requirements of the
relevant authorities. 
Reason: To safeguard existing public utilities in the area. 
23. At all times that the site is in operation, a wheel washing facility for
vehicles exiting the site shall be in use and shall be regularly cleaned
and recharged with clean water, and the sections of public road
between the site access and the A7 shall be kept clear of mud or dirt. 
Reason: To prevent mud and dirt from the site being spread onto the
public road, where it may constitute a hazard or nuisance to road
users. 
Biodiversity 
24. Prior to the commencement of any new restoration works an Ecological
Impact Assessment (complying with CIEEM guidance) shall be
submitted to and approved in writing by the Planning Authority.
Restoration thereafter shall comply with any mitigation measures
identified in the Ecological Impact Assessment.  
Reason:  To ensure that the impact of restoration works on the
biodiversity of the site is assessed and minimised. 
25. Prior to the commencement of any new restoration works a biodiversity
metric should be used to calculate in full the capacity of the proposed
layout and proposed habitats to deliver biodiversity enhancement. The
results of the metric shall be submitted to and approved in writing by
the Planning Authority, prior to the commencement of any new
restoration works. 
Reason:  To ensure that the development protects biodiversity,
reverses biodiversity loss, delivers positive biodiversity effects and
strengthens nature networks. 
26. The mitigation measures identified in Chapter 4 of the Preliminary
Ecological Appraisal issued August 2024 (Job number: ED13814,
Report Number: 0001, Version: V0.1, Status: Final) shall be
implemented throughout the duration of the extraction operations on
Page 74 of 112

Page 75

the site, unless alternative mitigation measures are approved via
condition 24. 
Reason:  To minimise the adverse impact of the development on
wildlife within and adjoining the site. 
Hours of Working 
27. No operations shall take place outwith the hours of 07:00 to 18:00 on
Mondays to Fridays inclusive and 07:00 to 13:00 on Saturdays.
Operations shall include excavation, extraction and restoration, initial
preparation of the site including the formation and removal of perimeter
soil bunds, and the movement of lorries entering or leaving the site.  No
work shall be carried out on Sundays or on public holidays except for
emergency or routine maintenance work. 
Reason:  To minimise the effect the impact of the development on the
amenity of residents living in the vicinity of the site and as a
consequence of the Environmental assessment considering slightly
shorter hours than the existing planning consent.   
Noise Control 
28. Noise levels, as measured at 3.5 metres from any façade of any noise-
sensitive dwelling, from all site operations other than soil stripping but
including bund formation and restoration, shall not exceed a one hour
LAeq of 45db. 
29. Noise levels, as measured in accordance with condition 27, from soil
stripping shall not exceed 60 dB(A) LAeq1h during the approved
operating hours. 
30. The surface of all haul roads and the track between the Hopefield
Distributor Road and the sites shall be maintained in an evenly-graded
condition, without bumps or pot-holes, at all times throughout the
duration of operations at the site. The speed limit of 15mph shall be
enforced along this section of road/track. 
31. The routes of vehicles within the site shall be designed to minimise the
need for lorries to reverse, thereby activating any reversing alarms with
which they may be installed. 
32. All vehicles exiting the site shall turn right and continue to the A7 via
the B6392. 
33. Throughout the duration of the operations at this site, the applicants, or
their successors, shall implement in full the noise mitigation measures,
identified in Section 9 of the Environmental Statement, including those
relating to site operation and general environmental management. In
particular, a programme of regular noise monitoring shall be
Page 75 of 112

Page 76

undertaken, at locations to be agreed beforehand with the Planning
Authority, and the results shall be made available to the Authority on
request. 
Reason for conditions 28-33: To ensure that noise generated by the
operations on the site is minimised, in order to protect the amenity of
those residents living in the vicinity of the site and as recommended in
PAN 50 Annex A: The control of noise at surface mineral workings. 
Dust Control 
34. Whenever necessary, all roads and other un-vegetated surfaces within
the site, including sand stockpiles, shall be damped down to prevent
the spread of windblown dust from the site; particular care shall be
taken in the vicinity of residential properties, and moisture screens shall
be installed within the site, if necessary. 
35. Throughout the duration of operations, the surface of the site access
roads shall be kept in good repair, and shall be regularly graded to
remove loose material. 
36. All mobile plant used within the site shall be fitted with upward facing
exhausts.  
37. All laden vehicles leaving the site shall be effectively sheeted or
enclosed. 
38. All vehicles moving within the site, and along the access road to the
Hopefield Distributor Road shall be subject to a speed limit, not
exceeding 15mph. 
39. Throughout the duration of the operations at this site, the applicants, or
their successors, shall implement in full the dust control measures,
identified in Section 12 of the Environmental Statement attached to the
previous planning permission, reference number 06/00689/FUL,
including those relating to site operation and general environmental
management. In particular, a programme of dust monitoring shall be
undertaken, in accordance with details submitted to and approved by
the Planning Authority prior to operations commencing on the site, and
the results of the monitoring shall be submitted to the Authority at the
agreed intervals. The dust monitoring programme shall include details
of the air quality standards to be achieved at agreed locations on the
perimeter of the site, and the remedial measures to be adopted in the
event of those standards not being achieved, including, in extreme
adverse conditions, the temporary cessation of all operations on the
site. 
Reason for conditions 34-39: To minimise the impact of the
development on the environment of the surrounding area, through the
generation of dust from the operations.
Page 76 of 112

Page 77

Landscaping Restoration and Aftercare 
40. The site shall be completely restored, in compliance with conditions 3
and 40 to 47, within one year of the expiry of the time limit placed on
the operation of the site. 
41. The site shall be restored progressively in accordance with the details
provided in terms of condition 3 of this permission. 
42. The site shall be restored to the contours approved in accordance with
the details approved in terms of condition 3, or such other revised
contours as may be agreed in writing with the Planning Authority, and
the surface levels shall be so graded as to ensure the final surface
merges smoothly with the adjoining land. 
43. Within six months of the completion of sand extraction operations, all
buildings and fixed or moveable plant shall be removed from the site
and all site access roads shall be removed or reverted back to farm
access tracks, unless required for the restoration of the site, or
otherwise agreed by the Planning Authority; and all such areas shall be
subject to the full restoration treatment, as detailed below. Any access
roads required for the restoration work shall be retained until the end of
the restoration period and then removed or reverted back to farm
access tracks. 
44. All operations to remove topsoil and subsoil from the storage mounds
and to re-spread them shall be carried out when the ground and
storage mounds are in a suitable dry condition, as agreed with the
Planning Authority. Earth-moving machinery shall travel to and from the
soil mounds along clearly defined routes, and these routes shall be
ripped before being covered with the next layer of subsoil or topsoil.
When the vehicle is emptied after spreading subsoil or topsoil, it must
immediately turn off on to overburden or subsoil areas respectively. 
On sloping land, the direction of travel of machines should, as far as is
possible, be parallel to the contours, in order to minimise erosion. All
operations following the replacement of topsoil shall be carried out by
suitable agricultural machinery. 
45. On all areas that are to be restored to agricultural use, after
replacement of topsoil, chemical analyses of the soils shall be carried
out by an approved agency to assess the fertiliser, lime and other
major and minor nutrients required to promote the establishment and
growth of appropriate plants for the agreed land use. The land shall
then be cultivated using normal agricultural machinery to prepare a
seed bed suitable for the sowing of grass seeds, during which process
any stones larger than would pass through a wire screen mesh with a
size of 100mm shall be removed, together with other obstructions to
future cultivation. Lime, fertilisers and other plant nutrients shall be
applied in accordance with the recommendations of the approved
Page 77 of 112

Page 78

agency carrying out the soil chemical analyses so that the soil is
sufficiently fertile to permit the chosen programme of restoration.  The
land shall then be sown with a short term grass seed mixture, based on
perennial rye grass and white clove, or such other species as may be
approved. 
46. The site shall be restored only in accordance with the restoration plans
and specifications approved under the terms of condition 3, and
restoration works shall not be considered to be completed until all
watercourses, ditches, fences, walls, hedges, field accesses trees and
other planting have been installed or carried out in accordance with
those plans and specifications agreed with the Planning Authority. 
Reason for conditions 40-46: To ensure that all parts of the site are
properly restored to agriculture or other approved after-use. 
47. Any trees or shrubs planted as part of the restoration proposals that
die, are removed, become seriously diseased or are severely damaged
within five years of planting shall be replaced during the next available
planting season with others of similar size and species. 
Reason: To ensure that all new planting has an adequate opportunity
to become successfully established. 
48. At least three months before the completion of the restoration of Area A
and at least three months before the completion of the restoration of
Area B, aftercare schemes for each Area, in accordance with Schedule
3 to the Town & Country Planning (Scotland) Act 1997 shall be
submitted for the approval of the Planning Authority. The scheme shall
be carried out, as approved or modified by the Authority, for a period of
five years from the date when the restoration of the site has been
completed in accordance with the terms of condition 49. 
49. The aftercare measures to be taken shall be such as to bring the land
to the required standard for use for agriculture, to enable the
establishment of the woodland planting and for amenity purposed
specifically new habitat creation with appropriate footpath access. 
Reason for conditions 48 & 49: To ensure that all the restored land is
properly managed for a sufficient period to ensure its effective
establishment to the approved after-use. 
Monitoring 
50. Throughout the duration of this development, the applicants or their
successors shall, if and when required to do so by the Planning
Authority, submit such information as may be necessary, including any
relevant plans, to enable the Authority to determine the progress of the
operations. 
Page 78 of 112

Page 79

Reason: To ensure effective monitoring of the development.  
51. The proposed development of the site shall progress in accordance
with the Phasing Plan – Extraction and Restoration, submitted as part
of the planning consent. 
Reason: To ensure the phasing of the extraction and restoration of
Areas A, B, and C allow for the appropriate phases development of the
site and to ensure the restoration proposals for the three areas are
achieved. 
52.  The developer shall ensure that the approved bond or other financial
provision is maintained through the duration of the permission and that
the bond provides sufficient funds to cover restoration of the site to the
restoration plans approved in terms of condition 3 of this permission.  
Reason: To ensure that there are sufficient funds available throughout
the life of the development to carry out the full restoration of the site. 
Peter Arnsdorf
Planning, Sustainable Growth and Investment Manager 
Date:     22 November 2024 
Application No:    18/00082/S42
Applicant:   Tillicoutry Quarries
Agent:              Wardell Armstrong LLP
Validation Date:  5 February 2018 
Contact Person:  Graeme King, Planning Officer 
Email:     graeme.king@midlothian.gov.uk 
Background Papers: 06/00689/FUL, 13/00064/DPP, 16/00816/SCO, 
17/00380/SCO, 17/00565/PAC, 18/00081/DPP
Attached Plan:  Location Plan
Page 79 of 112

Page 80

N
Midlothian Council
Fairfield House
8 Lothian Road
Dalkeith, EH22 3AA
Reproduced from the Ordnance Survey map with the
permission of the controller of Her Majesty's Stationary Office.
Crown copyright reserved. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil
proceedings.
Planning Service
Place Directorate
Area A
Midlothian Council Licence No. AC0000811376 (2024)
Section 42 application to amend condition 2 and 3 of
06/00689/FUL to extend the time for completion of
restoration of area A by a further 3 years and area B
by a further 6 years.
Upper Dalhousie Sand Quarry, Bonnyrigg.
Area B
File No. 18/00082/S42
Scale 1:9000Page 80 of 112

Page 81

Planning Committee
Monday 9 December 2024
Item No 5.5
APPLICATION FOR PLANNING PERMISSION 18/00081/DPP FOR THE
EXTRACTION AND PROCESSING OF SAND ON LAND TO THE
SOUTH/SOUTHWEST OF THE UPPER DALHOUSIE SAND QUARRY,
BONNYRIGG.  THE APPLICATION IS ACCOMPANIED BY AN
ENVIRONMENTAL IMPACT ASSESSMENT REPORT SUBMITTED UNDER
THE TOWN AND COUNTRY PLANNING (ENVIRONMENTAL IMPACT
ASSESSMENT) (SCOTLAND) REGULATIONS 2011
Report by Chief Officer Place
1 SUMMARY OF APPLICATION AND RECOMMENDED DECISION
1.1 In August 2009 planning permission 06/00689/FUL was granted for
the extraction and processing of sand and the siting of associated
plant and office at Upper Dalhousie, Bonnyrigg.  This application
seeks planning permission to extend the area of extraction and
processing onto land to the south/southwest of the existing
operational area.  The application is accompanied by an
Environmental Impact Assessment Report which has been
submitted in terms of the EIA (Scotland) (Regulations) 2011. 
1.2 There have been no representations received.  Consultation
responses have been received from The Coal Authority, Historic
Environment Scotland, the Scottish Environment Protection
Agency (SEPA), Scottish Water, NatureScot (previously Scottish
Natural Heritage), Bonnyrigg and Lasswade Community Council,
The Council’s Archaeology Advisor, The Council’s Ecological
Advisor (TWIC), The Council’s Senior Manager Protective
Services, the Council’s Senior Manager Neighbourhood Services
(Flood Risk and Transportation) and the Council’s Legal Services
Manager.
1.3 The relevant development plan policies are policies 1, 2, 3, 4, 5, 6,
7, 20, 22, 23 and 33 of National Planning Framework 4 and policies
MIN1, MIN2, RD1, ENV2, ENV4, ENV6, ENV7, ENV9, ENV10, ENV11,
ENV14, ENV15, ENV17, ENV18, ENV22, ENV23, ENV24, ENV25,
IMP1, and IMP3 of the Midlothian Local Development Plan 2017.
1.4 The application was reported to Planning Committee on 28
August 2018 and the Committee approved the application subject
to conditions and to the developer demonstrating, to the written
satisfaction of the Council, that they have sufficient bond
Page 81 of 112

Page 82

provision/insurance in place to ensure that, in the event that the
operator is not able to restore the site, financial provision is made
to enable the site to be restored in accordance with an approved
restoration plan. 
1.5 This report provides an update on the bond provision and
considers the impact of the adoption of National Planning
Framework 4 (NPF4) on the assessment of the proposal. 
1.6 The recommendation is to grant planning permission subject to
conditions. 
2 LOCATION AND SITE DESCRIPTION 
2.1 The Upper Dalhousie Sand Quarry is located to the southeast of
Bonnyrigg and comprises two extraction areas separated by an area of
woodland.  Area A is situated to the southeast of the woodland and
Area B is to the northwest.  The existing processing area, site office
and welfare facilities are located in the northern portion of Area A,
close to the site access.  The site is accessed from the B6392
distributor road to the south of the Hopefield residential development. 
The site measures approximately 18 hectares in area. 
2.2 The extension site (Area C) extends to some 15.8 hectares and is
irregular in shape and includes part of Area A of the existing quarry, as
the intention is to use the existing onsite processing plant, welfare
facilities and site office.  The additional sand extraction area is
approximately 11.4 hectares.  Conveyor belts move the extracted sand
from the extraction operations to the processing area.  Extraction from
Area A has been completed and this area has been partially restored.
Extraction from Area B commenced in 2016 and is ongoing. 
2.3 As is noted above, the application site includes part of the existing
quarry (the overlap with Area A). The remaining land within the
application site is either woodland or is in agricultural use, the latter
being the main use of the site.  The site is bounded by agricultural land,
areas of woodland and sand extraction Area A, with Whitehill House
(and associated residential development) and Rosewell beyond to the
west/southwest and Bonnyrigg beyond to the north.  The closest
dwellinghouses are Parkneuk, at approximately 300m to the northwest
and the residential development at Whitehill House, at approximately
200m to the southwest. 
2.4 The southern end of the site adjoins the Shiel Burn Wood Local
Biodiversity Site (situated to the southwest of the application site) and
the South Esk and Carrington Farmland Special Landscape Area
(situated to the south of the application site). 
2.5 There is a public footpath link (Core Path 3-6) immediately to the west
of extraction Area C.  Other footpaths are located to the south and east
Page 82 of 112

Page 83

of the site.  The applicant proposes to link into the footpath network as
part of the restoration scheme for the site. 
3 PROPOSAL 
3.1  It is proposed to extract approximately 1.6 million tonnes of sand over a
ten-year period.  This is based on the current extraction rate of around
150,000 tonnes a year, of which 120,000 tonnes is removed from the
site.  Extraction rates may differ year on year depending on market
demand.  Area C would be worked both above and below the water
table.  The proposed phasing of the proposal is that extraction is to
commence in 2026 and continue until 2035.  The rolling restoration
programme will start in 2029 and be completed in 2036. 
3.2 Excavations will take place in three phases; the first phase being the
central area adjacent to Area A and the northwest of the site, the
second phase will be the main central part of the site, and the third
phase will be the southwestern part of the site. 
3.3 It is proposed to continue the existing working hours of the quarry
which are 7.00am to 6.00pm Mondays to Fridays and 7.00am to
1.00pm on Saturdays.  No work is carried out on Sundays or public
holidays except for emergency work or routine maintenance. 
3.4 The operator, Tillicoultry Quarries, is a family-owned Scottish firm that
was established in 1931. The firm currently operates hard rock
quarries, sand and gravel quarries, roadstone coating plants and
concrete plants at 31 sites in Scotland and England. The firm operates
eight sand and gravel quarries, and five hard rock quarries in Scotland.
Three grades of sand are extracted from the site, sand for asphalt,
building sand and ducting sands. Asphalt sand accounts for 60% of the
extractions and is used at the applicant’s production plant at
Newtongrange. 
3.5 The maximum depth of extraction will be 23 metres with extraction
taking place on a series of benches measuring 5 metres in height and
width. Where dry working methods are used the sand will be extracted
using a front-loading excavator. Wet working methods will be used for
extraction below the water table and in such areas a tracked hydraulic
excavator will be used.  The sand will be transported by conveyer belt
to the processing plant which is in Area A. 
3.6 The typical daily HGV movements (a single movement = one inward
journey and one outward journey) are estimated to be 36 movements.
This is comparable to the average daily HGV movements form the
existing extraction operations of 35 per day. 
3.7 The site is to be progressively restored with restoration commencing in
2029 and completion in 2036, one year after the completion of the
extraction process.  Restoration would be achieved using silt material
Page 83 of 112

Page 84

arising during the processing operations along with topsoil stored in
bunds at the site. It is anticipated that silt material from Area C will be
used in the restoration of Area B as well as the application site, Area C. 
3.8 The restoration of Area C has been designed so that the majority of the
site can return to agricultural use integrating with the surrounding
topography, including merging with the restoration profile of Area A to
create a natural appearing landform.  Area C will take the form of a
valley which will slope down to the south-east, towards the Dalhousie
Burn.  The restored site will include a natural water feature within the
northeastern corner of the site.  This wetland habitat will provide an
opportunity to enhance local biodiversity and ecology.  A wet woodland
will be planted at the southern end of the site, this woodland will
provide compensatory planting to replace an area of plantation
woodland at the north end of the site which is to be felled to facilitate
extraction. 
3.9 The restored areas will be seeded and planted and then be subject to a
programme of aftercare to facilitate the return to productive agricultural
use and woodland planting.  All plant and welfare facilities will be
removed from the site and the land in these areas will be returned to an
agricultural use. 
3.10 A path network will be introduced/reinstated as part of the proposed
site restoration.  The paths will include a link from the Core Path,
around the proposed water feature, and then northwards into area A.
Restoration works associated with Areas A and B will create path
networks round those sites and linking to existing paths in the
surrounding area. 
3.11 The original application was accompanied by an Environmental
Statement complying with The Town and Country Planning
(Environmental Impact Assessment) (Scotland) Regulations 2011 (the
2011 Regulations).  Whilst the application was submitted after The
Town and Country Planning (Environmental Impact Assessment)
Regulations 2017 (the 2017 Regulations) had come into force, a
transitional provision within the 2017 Regulations allows for
applications to be assessed under the 2011 Regulations where the
Scoping Opinion was issued under the 2011 Regulations.  The
Environmental Statement includes the following reports as appendices: 
• Coal Mining Risk Assessment;
• Preliminary Ecological Appraisal;
• Bat Activity Assessment;
• Floor Risk Assessment;
• Archaeological Desk Based Assessment; and 
• Dust Management Plan. 
3.12 In addition to the Environmental Statement and its appendices the
application was also accompanied by the following reports:
Page 84 of 112

Page 85

• Pre-Application Consultation Report;
• Transport Statement; and
• Tree Survey and Arboricultural Constraints Report. 
3.13 The application has been updated in 2024 with the submission of the
following reports and plans: 
• NPF4 Policy Update;
• Updated Preliminary Ecological Appraisal;
• Bat Activity Report; and 
• Updated restoration details. 
4 BACKGROUND 
4.1 Planning application 06/00689/FUL for the extraction and processing of
sand and the erection of the associated plant and office provision at
Upper Dalhousie was granted permission in August 2009.  This
consent has been implemented and work continues on the site. 
4.2 Planning application 13/00064/DPP for the installation of sand
processing plant and a conveyor at the quarry was granted permission
in March 2013. 
4.3 An environmental impact assessment (EIA) scoping request
(16/00816/SCO) for the extension of operations was submitted in
November 2016. The applicant was advised what matters need to be
covered by an EIA which need to be submitted under schedule 2 of the
EIA Regulations. 
4.4 Pre-Application Consultation 17/00565/PAC regarding the extension of
the quarry on land to the southwest of the existing Dalhousie Sand
Quarry, Bonnyrigg was reported to the Planning Committee at its
meeting in August 2017. 
4.5 A related planning application (18/00082/S42) for an extension of time
to conclude the extraction and restoration of the existing quarry is
subject to assessment and is elsewhere on the Committee agenda 
4.6 The current application and application 18/00082/S42 were both
reported to the Planning Committee on 28 August 2018. The
Committee approved both applications subject to conditions and to the
developer demonstrating, to the written satisfaction of the Council, that
they have sufficient bond provision/insurance in place to ensure that, in
the event that the operator is not able to restore the site, financial
provision is made to enable the site is restored in accordance with an
approved restoration plan. 
Page 85 of 112

Page 86

5 CONSULTATIONS 
5.1 The Coal Authority consider that the content and conclusions of the
Coal Mining Risk Assessment submitted with the application
demonstrate that the site is safe and stable to enable the proposed
development to be undertaken. The Coal Authority does not object to
the application. 
5.2 Historic Environment Scotland (HES) does not object to the
application.  HES were consulted at the scoping stage of the EIA
process in 2016, which identified a potential impact on the setting of
Whitehill House, a category A listed building. However, they are
satisfied that the impact is a temporary one which can be mitigated by
planting along the boundary of the site. 
5.3 The Scottish Environment Protection Agency (SEPA) does not
object to the application. The site is at a medium to high risk of flooding
(0.5% annual probability or a 1 in 200-year event) from the Shiel
Burn/Dalhousie Burn.  It is however acknowledged that the proposed
use of the land is a temporary one and as such there is no long-term
risk. The applicant’s Flood Risk Assessment (FRA) sets out an onsite
drainage strategy and confirms that operation works will not result in
discharge into local watercourses (the Shiel Burn and Dalhousie Burn). 
In relation to air quality SEPA state that the environmental statement
(non-technical) reports that a negligible impact on air quality is
predicted. 
5.4 Scottish Water does not object to the application. 
5.5 Scottish Natural Heritage (SNH) (now known as NatureScot) does
not object to the application subject to securing a bond to ensure
effective site restoration, effective landscaping, the reinstatement of
active travel routes and securing the conclusions set out in the
Environmental Statement regarding ecological receptors (ancient
woodland and protected species). 
5.6 The Bonnyrigg and Lasswade Community Council (the community
council merged with Poltonhall and Hopefield Community Council in
2022 to create Bonnyrigg and District Community Council) advise
that they engaged their local community regarding the existing and
potential future impacts of the quarrying activity, in particularly the
traffic implications, the result of which was that no concerns were
raised and as such the Community Council does not object to the
application.  However, the Community Council expect Midlothian
Council to secure a bond to ensure the site’s restoration. 
5.7 The Council’s Archaeology Advisor is satisfied that the
Environmental Impact Assessment considers the possible historic
environment implications of the proposed development and that a
programme of archaeological works comprising a monitored soil strip
Page 86 of 112

Page 87

(equivalent to a watching brief) is necessary. This can be secured by a
planning condition. 
5.8 The Council’s Ecological Advisor – The Wildlife Information
Centre (TWIC) has confirmed that both the updated Preliminary
Ecological Appraisal and the updated Bat Activity Report are thorough
and professional. Further protected species surveys will be required
prior to restoration works commencing. 
5.9 The Council’s Senior Manager Protective Services (Contingency
Planning and Environmental Health) advises that the existing site is
currently well managed and operates without giving rise to noise or
dust nuisance complaints.  Officers are of the opinion that extending
the site can also be operated in way in which environmental impacts
are mitigated subject to conditions to control noise and dust emissions
arising from the operation of the site.  The processing plant will remain
in its existing location which will not give rise to an increase in noise
levels. The noise impact assessment accompanying the application
demonstrates that the predicted noise levels at the three noise
sensitive receptors studied would be below the 45 db 1 hour LAeq
guideline value.  Dust mitigation measures which are the conveyor
system, sprinkler system and wheel wash and management plan
appear adequate to prevent nuisance arising.  The operating hours will
be as existing 7.00am to 6.00pm Monday to Friday and 7.00am to
1.00pm Saturday.  The following matters should be addressed by
conditions: 
• roads and un-vegetated surfaces shall be dampened down to
prevent windblown dust;
• site access roads shall be kept in good repair and regularly graded;
• all laden vehicles must be sheeted prior to leaving the quarry;
• a speed limit of 15mph shall be enforced along the site access
road; 
• the dust management plan dated January 2018 shall be enforced,
and a programme of dust monitoring results will be periodically sent
to the local authority; and
• noise levels from soil stripping, bund formation, removal and
restoration operations at nearby noise sensitive dwellings must not
exceed a one hour LAeq of 45db as recommended in PAN 50
Annex A: The control of noise at surface mineral workings. 
5.10 The Council’s Senior Manager Neighbourhood Services (Flood
Risk and Transportation) does not object to the application. 
5.11 The Council’s Legal Services have advised that as the landowner is
Crown Estate Scotland the risk to the Council of the landowner and
applicant not restoring the land is low, so if the Council are satisfied
with the terms of the bond, we do not need to be a party to it, it shall be
between the applicant and landowner. 
Page 87 of 112

Page 88

6 REPRESENTATIONS 
6.1 No representations have been received. 
7 PLANNING POLICY 
7.1 The development is comprised of National Planning Framework 4
(2023) and the Midlothian Local Development Plan 2017. The following
policies are relevant to the proposal: 
National Planning Framework 4 (NPF4) 
7.2 NPF4 is a National Spatial Strategy for Scotland until 2045 and sets out
a vision for future places using six overarching spatial principles: 
• Just transition.
• Conserving and recycling assets.
• Local living.
• Compact urban growth.
• Rebalanced development.
• Rural revitalisation. 
7.3 Policy 1 Tackling the climate and nature crisis; sets out to
encourage, promote and facilitate development that addresses the
global climate emergency and nature crisis. 
7.4 Policy 2 Climate mitigation and adaptation; sets out to encourage,
promote and facilitate development that minimises emissions and
adapts to the current and future impacts of climate change. 
7.5 Policy 3 Biodiversity; sets out to protect biodiversity, reverse
biodiversity loss, deliver positive effects from development and
strengthen nature networks. 
7.6 Policy 4 Natural Places; sets out to protect, restore and enhance
natural assets making best use of nature-based solutions. 
7.7 Policy 5 Soils; sets out to protect carbon-rich soils, restore peatlands
and minimise disturbance to soils from development. The policy also
sets out acceptable scenarios for development on prime agricultural
land. 
7.8 Policy 6 Forestry, woodland and trees; sets out to protect and
expand forests, woodland and trees. 
7.9 Policy 7 Historic assets and places; sets out to protect and enhance
historic environment assets and places, and to enable positive change
as a catalyst for the regeneration of places. 
Page 88 of 112

Page 89

7.10 Policy 20 Blue and green infrastructure; sets out to protect and
enhance blue and green infrastructure and their networks. 
7.11 Policy 22 Flood risk and water management; sets out to strengthen
resilience to flood risk by promoting avoidance as a first principle and
reducing the vulnerability of existing and future development to
flooding. 
7.12 Policy 23 Health and Safety; sets out to protect people and places
from environmental harm, mitigate risks arising from safety hazards
and encourage, promote and facilitate development that improves
health and wellbeing. 
7.13 Policy 33 Minerals; sets out to support the sustainable management of
resources and minimise the impacts of extraction of minerals on
communities and the environment. 
Part d - development proposals for the sustainable extraction of
minerals will only be supported where they: 
i. Will not result in significant adverse impacts on biodiversity,
geodiversity and the natural environment, sensitive habitats and
the historic environment, as well as landscape and visual
impacts;
ii. provide an adequate buffer zone between sites and settlements
taking account of the specific circumstances of individual
proposals, including size, duration, location, method of working,
topography, and the characteristics of the various environmental
effects likely to arise;
iii. can demonstrate that there are no significant adverse impacts
(including cumulative impact) on any nearby homes, local
communities and known sensitive receptors and designations;
iv. demonstrate acceptable levels (including cumulative impact) of
noise, dust, vibration and potential pollution of land, air and
water;
v. minimise transport impacts through the number and length of
lorry trips and by using rail or water transport wherever practical;
vi. have appropriate mitigation plans in place for any adverse
impacts;
vii. include schemes for a high standard of restoration and aftercare
and commitment that such work is undertaken at the earliest
opportunity. As a further safeguard a range of financial
guarantee options are available, and the most effective solution
should be considered and agreed on a site-by-site basis.
Solutions should provide assurance and clarity over the amount
and period of the guarantee and in particular, where it is a bond,
the risks covered (including operator failure) and the triggers for
calling in a bond, including payment terms. 
Page 89 of 112

Page 90

7.14 NPF4 states that Local Development Plans should support a landbank
of construction aggregates of at least 10-years at all times in the
relevant market areas, whilst promoting sustainable resource
management, safeguarding important workable mineral resources,
which are of economic or conservation value, and take steps to ensure
these are not sterilised by other types of development. 
Midlothian Local Development Plan 2017 
7.15 Policy MIN1: Areas of Search for Surface Extraction identifies Upper
Dalhousie as being an area for the extraction of sand and gravel where
surface mineral extraction may be acceptable in principle. The policy
states that the identification of an area of search does not indicate the
Council’s acceptance of any particular proposal for the winning and
working of a surface mineral resource within any or all of that area of
search. Outwith the areas of search there is a presumption against
surface mineral extraction. In addition the policy safeguards mineral
resources from sterilisation, in specific circumstances. 
7.16 Policy MIN2: Surface Mineral Extraction requires proposals for
mineral extraction to meet the criteria set out in the Supplementary
Guidance on Resource Extraction. They will not be permitted where
they would have a significant adverse effect on communities, sensitive
uses or the environment and will only be supported if the Council is
satisfied that they are acceptable in relation to the following matters: 
• effect on the health and amenity of settlements, communities
and housing groups or other sensitive uses;
• effect on the landscape, in particular that of the Green Belt,
Pentland Hills Regional Park, and Special Landscape Area;
• effect on soils, in particular prime agricultural land, and peatland;
• effect on the water environment;
• effect on nature conservation and biodiversity, in particular sites
of international, national or local nature conservation value;
• effect on the historic environment, in particular: Conservation
areas, scheduled monuments, listed buildings, historic gardens
and designed landscapes, historic battlefields, significant
archaeological sites (and, where relevant, the settings of the
aforementioned designated areas or buildings);
• effect on the road network, particularly local roads;
• cumulative effects of the proposal when combined with other
consented or operational mineral extraction or landfill activities;
• effect on the local economy in terms of tourism, leisure or
recreation; and,
• robustness and suitability of proposals for restoration and
aftercare. 
7.17 The extraction of a secondary material (for example, fireclay from a
coal extraction site) is supported provided that its removal does not
Page 90 of 112

Page 91

detract from high quality restoration or have unacceptable
environmental effects (including from cumulative vehicle movements).
In order that the supply and demand for aggregates can be monitored,
operators of new aggregates sites will be required to supply annual
statements of production and remaining reserves. 
7.18 Policy RD1: Development in the Countryside sets out where
appropriate development would be acceptable in the countryside
subject to defined criteria.  One acceptable use is resource extraction
in compliance with Policy MIN1.  All such development requires being
of a scale or character appropriate to the rural area and landscape,
capable of being appropriately accessed and serviced, have
acceptable drainage provision and water supply and be accessible by
public transport and services, where appropriate. 
7.19 Policy ENV2 Midlothian Green Networks supports development
proposals brought forward in line with the provisions of the Plan that
help to deliver the green network opportunities identified in the
Supplementary Guidance on the Midlothian Green Network. 
7.20 Policy ENV4: Prime Agricultural Land does not permit development
that would lead to the permanent loss of prime agricultural land unless
there is appropriate justification to do so. 
7.21 Policy ENV6: Special Landscape Areas states that development
proposals will only be permitted where they incorporate high standards
of siting and design and where they will not have significant adverse
effect on the special landscape qualities of the area. 
7.22 Policy ENV7: Landscape Character states that development will not
be permitted where it significantly and adversely affects local
landscape character.  Where development is acceptable, it should
respect such character and be compatible in terms of scale, siting and
design.  New development will normally be required to incorporate
proposals to maintain the diversity and distinctiveness of the local
landscapes and to enhance landscape characteristics where they have
been weakened. 
7.23 Policy ENV9: Flooding presumes against development which would
be at unacceptable risk of flooding or would increase the risk of
flooding elsewhere.  It states that Flood Risk Assessments will be
required for most forms of development in areas of medium to high risk
but may also be required at other locations depending on the
circumstances of the proposed development.  Furthermore, it states
that sustainable urban drainage systems will be required for most forms
of development, so that surface water run-off rates are not greater than
in the site’s pre-developed condition, and to avoid any deterioration of
water quality. 
Page 91 of 112

Page 92

7.24 Policy ENV10: Water Environment requires that new development
pass surface water through a sustainable urban drainage system
(SUDS) to mitigate against local flooding and to enhance biodiversity
and the environment. 
7.25 Policy ENV11: Woodland, Trees and Hedges states that development
will not be permitted where it could lead directly or indirectly to the loss
of, or damage to, woodland, groups of trees (including trees covered by
a Tree Preservation Order, areas defined as ancient or semi-natural
woodland, veteran trees or areas forming part of any designated
landscape) and hedges which have a particular amenity, nature
conservation, biodiversity, recreation, landscape, shelter, cultural, or
historical value or are of other importance. 
7.26 Policy ENV14: Regionally and Locally Important Nature
Conservation Sites states that development will not be permitted
where it could adversely affect the nature conservation interest of such
sites, unless it can be demonstrated that appropriate mitigation
measures are in place. 
7.27 Policy ENV15: Species and Habitat Protection and Enhancement
presumes against development that would affect a species protected
by European or UK law. 
7.28 Policy ENV 17 Air Quality states that the Council may require further
assessments to identify air quality impacts where considered requisite.  
It will refuse planning permission, or seek effective mitigation, where
development proposals cause unacceptable air quality or dust impacts. 
7.29 Policy ENV18: Noise requires that where new noise sensitive uses are
proposed in the locality of existing noisy uses, the Council will seek to
ensure that the function of established operations is not adversely
affected. 
7.30 Policy ENV22: Listed buildings does not permit development which
would adversely affect the character or appearance of a listed building,
its setting or any feature of special architectural or historic interest. 
7.31 Policy ENV23: Scheduled Monuments states that development which
could have an adverse effect on a scheduled monument, or the
integrity of its setting, will not be permitted. 
7.32 Policy ENV24: Other Important Archaeological or Historic Sites
seeks to prevent development that would adversely affect regionally or
locally important archaeological or historic sites, or their setting 
7.33 Policy ENV25: Site Assessment, Evaluation and Recording requires
that where development could affect an identified site of archaeological
importance, the applicant will be required to provide an assessment of
Page 92 of 112

Page 93

the archaeological value of the site and of the likely impact of the
proposal on the archaeological resource. 
7.34 Policy IMP1: New Development gives the planning authority the policy
basis to impose appropriate planning conditions and controls to
mitigate the impact of the development. 
7.35 Policy IMP3: Water and Drainage require sustainable urban drainage
systems (SUDS) to be incorporated into new development. 
8 PLANNING ISSUES 
8.1 The main planning issue to be considered in determining this
application is whether the proposal complies with development plan
policies unless material planning considerations indicate otherwise.
The consultation responses received are material considerations. 
Principle of development 
8.2 Planning permission for the extraction and processing of sand and
associated works at Areas A and B was granted in 2009.  The principle
of sand and gravel extraction at Upper Dalhousie was then given
further support in the MLDP which identified Upper Dalhousie as an
area of search for mineral extraction.  The area of search includes the
existing sites at Areas A and B as well as the current application site
Area C.  The principle of sand and gravel extraction at the application
site accords with the MLDP and there are no material considerations
which outweigh this presumption in favour of development. 
8.3 NPF4 was adopted in February 2023. Policy 33 supports the
sustainable extraction of minerals. The application relates to existing
areas of extraction and processing which are operating in compliance
with points i to vii of Policy 33 d). The adoption of NPF4 has not
changed the presumption in favour of new development. 
Landscape and visual impact 
8.4 The proposed operations will have a detrimental impact on the
landscape during the extraction process as the topsoil is stripped back
and sand is removed from the ground.  However, the detrimental
impact caused by this ‘opening up’ of the site is mitigated by the fact
that the operation is temporary (from 2026 to 2036) and the phased
extraction and rolling programme of restoration will mean that not all of
the site will be operational at any one time. The separation distance
from any settlements and the established woodland areas adjoining the
site provide further mitigation against the visual impact of the proposal.
To provide further mitigation a landscape buffer will be planted along
the site’s south/southwestern boundary in advance of operations
commencing. The landscape buffer will comprise enhancing the
existing hedge, which runs along the Core Path adjoining the site, with
Page 93 of 112

Page 94

an additional 5 metres of planting along the adjoining length of the Core
Path. This will reduce the visual impact on the landscape and soften
distance views for residents of the Whitehill House residential
development some 200 metres further to the southwest. 
8.5 Additional landscaping, including a new area of wet woodland, is also
proposed along the southeastern boundary of the site which abuts the
South Esk and Carrington Farmlands Special Landscape Area.  In this
sensitive area it will be important to agree a landscaping scheme which
complements the existing planting.  The details of any additional areas
of planting can be secured by conditions on a grant of planning
permission. 
8.6 A restoration masterplan has been submitted as part of the planning
application.  The plan identifies; key proposed landscape features, new
restoration ground levels, the formation of a ‘natural’ water feature to
enhance biodiversity and the end land uses as agriculture and
woodland. This is acceptable in principle subject to the final details
being agreed by condition. 
8.7 There is currently a variation in the levels across the site of
approximately 20 metres dropping from the northwest to southeast. 
After the extraction and restoration processes have been completed
the proposed height variation across the site will be approximately 23
metres.  The main areas of change will be along the south/southwest
boundary and in the north/northwest of the site.  The level changes in
these areas will be softened into the landscape by woodland planting.
By incorporating a steeper level change on the edge of the site it is
possible to create a level area centrally within the site which can be
used for agriculture. The proposed restoration masterplan includes
additional informal footpaths, a sand bank for nesting sand martins and
a pond. The potential biodiversity and wildlife benefits of the restoration
proposals are a positive benefit of the development. The final
restoration details will be secured by condition and protected by the
provision of a financial bond. 
Loss of woodland 
8.8 The application site includes an area of Sitka Spruce plantation,
measuring approximately 1.05 hectares in area, on a north facing slope
at the northern edge of the site. The plantation will be removed via
commercial forestry operations. The restoration plans submitted in
2018 did not include compensatory planting. Following the adoption of
NPF4 the applicant has agreed to plant a 1.58 hectares woodland on a
south facing slope at the southern end of the site. The woodland will be
a native mixed broadleaved woodland with alder, rowan, cherry, birch,
hazel, carb apple and some Scots pine. The planting will take place in
advance of extraction starting. Finalised details will be secured via
condition. 
Page 94 of 112

Page 95

Biodiversity 
8.9 The adoption of NPF4 means that application proposals must now
contribute to the enhancement of biodiversity.  The majority of land
cover within the extraction area of the application site is temporary
grass and clover leys. There are further areas of modified grassland
and neutral grassland.  As is noted above there is an area of Sitka
Spruce plantation.  There are also areas of hedgerow.  The majority of
the habitats within the proposed extraction area are of limited
biodiversity value.  The broadleaved woodland will provide increased
biodiversity and the restored agricultural land will be of similar
biodiversity value to the existing land.  To ensure that the restoration
provides an adequate level of enhancement it would be reasonable to
condition that an assessment of biodiversity net gain is provided as part
of the restoration plans. 
Noise 
8.10 The nature of the operation means that there will be some noise from
the extraction and processing procedures and from the topsoil stripping
process.  These noise levels will be comparable to existing levels within
Areas A and B.  The existing operations have not been the subject of
complaints and comply with the guidance enforced by the Council’s
Environmental Health Service.  The existing noise conditions have
successfully protected amenity in the surrounding area, consequently it
would be reasonable and prudent to attach similar conditions to any
new consent.  Noise levels during the temporary soil stripping process,
which will take a period of up to 8 weeks, will represent a higher risk of
noise disturbance; however, as the impact will be temporary it will not
have a significant effect. 
Transportation matters 
8.11 The transportation statement submitted in support of the application
considers the traffic and transportation effects of the proposal.  It
concludes that the traffic generation will be comparable to that from the
existing operations.  The existing site access arrangements are not
subject to change.  As with the current operations, a number of
mitigation measures will be put in place including:  
• instructions to drivers and suppliers to follow the agreed route to
and from the site; and
• the implementation of good site management practice including
wheel washing, vehicle sheeting and road cleaning. 
8.12 An average of 36 trucks/heavy goods vehicles per day will enter and
leave the site via the existing access road, this is comparable to the
existing volume of vehicular movements (35).  A further 18 non heavy
goods vehicles will enter and leave the site – this will be the 6 staff
arriving for and leaving work, deliveries and visitors.  The non-HGV
Page 95 of 112

Page 96

vehicle movements will be similar to the current operations.  Extraction
and processing have taken place at Upper Dalhousie since 2009
without significant detrimental impact on the surrounding road network,
given the similarity in the scale of operations between the existing and
proposed activities there is no reason to conclude that this situation will
change. 
Restoration bond 
8.13 The applicant’s agent has confirmed that there is an existing
agreement in place between the applicant and the landowner, Crown
Estate Scotland, to secure restoration funds for Areas A and B.  Funds
for restoration are secured via a bank guarantee.  A similar agreement
will be used to secure the restoration funds for Area C.  The restoration
costs have been prepared by suitably qualified professionals utilising a
comprehensive database of comparable costs and the landowner is
satisfied that the costings are sufficient. 
Environmental Statement 
8.14 The Environmental Statement submitted with the application sets out
the findings of an Environmental Impact Assessment process carried
out by the applicant under The Town and Country Planning
(Environmental Impact Assessment) (Scotland) Regulations 2011.  The
process identifies the likely significant environmental effects of the
development and suggests ways in which any significant negative
environmental effects can be mitigated.  The statement considers the
following issues: 
• geology;
• landscape and visual impact;
• ecology;
• soils and agriculture;
• water resources, including hydrology and hydrogeology;
• cultural heritage including archaeology and historic environment;
• noise;
• air quality; and
• access and recreation. 
8.15 The environmental statement identifies that there are no long-term
detrimental consequences of the proposed development. The proposal
does present an opportunity for potential longer term environmental
benefits subject to the restoration programme, which, if undertaken in a
sensitive manner, could enhance the environment for the benefit of
wildlife, the local landscape, drainage, pollution prevention and future
recreational and agricultural uses. 
8.16 The EIA process requires that alternative options to the proposed
scheme are considered, and a justification is given for the preferred
option chosen. The options considered were: 1) do nothing with the
Page 96 of 112

Page 97

site; 2) reduce the extraction area; 3) extract from an alternative site;
and 4) work above the water table only. The preferred development
option (continued working of the current site) is considered the best
option for a number of reasons.  Firstly, the area is identified as an area
of search in the MLDP for the extraction of construction aggregate to
supply the local area.  Secondly, not continuing with the ongoing
extraction would have a detrimental impact on the provision of
construction sand to meet demand in the region. Thirdly, reducing the
extraction area (by not fully exploiting the resource in Area B) would
risk sterilising existing available reserves. Fourthly, the current site has
minimal detrimental impact on local communities. Finally, identifying an
alternative site would present a significant challenge in terms of the
development plan process and the time taken to reach a point where
material could be extracted. 
9 RECOMMENDATION 
9.1 It is recommended that planning permission be granted for the
following reason: 
The proposed development site is identified as a mineral extraction site
within the Midlothian Local Development Plan 2017; as such there is a
presumption in favour of the proposed development.  This presumption
in favour of development is not outweighed by any other material
considerations. The proposal complies with the relevant policies of
National Planning Framework 4 and the Midlothian Local Development
Plan 2017. 
Subject to the following conditions: 
Duration of the Permission 
1. The development to which this permission relates shall commence not
later than the expiration of three years beginning with the date of this
permission. Permission for the extraction of sand from area C (as
indicated on the approved drawings ES Fig 3.3 Area C Phase 1
Proposed Excavation,  ES Fig 3.4 Area C Phase 2 Proposed
Excavation and ES Fig 3.5 Area C Phase 3 Proposed Excavation) and
the storage of soil, conveyor route, processing plant, site office and
welfare facilities (as indicated on ES Fig 1.3 Proposed Site Plan
Showing Proposed Levels) is granted until the end of 31 December
2035. Restoration, as per the details of the Environmental Statement
chapter 3 (paragraphs 3.6.1 to 3.6.6) as represented in the Restoration
Masterplan (drawing no ED 13814-001) and in accordance with the
requirements of the conditions on this permission, shall be completed
by the end of 31 December 2036. 
2. Within six months of the date of this permission a phasing plan
detailing the timeline for the advanced planting, the restoration of Area
A, and the extraction and restoration of Area C shall be submitted to
Page 97 of 112

Page 98

and approved in writing by the Planning Authority. An updated timeline
shall be submitted to the Planning Authority on an annual basis (on the
anniversary of this permission). Development shall comply with the
approved phasing plan, or such alternatives as may be agreed in
writing by the Planning Authority. 
Reason for Conditions 1 & 2: To enable the Planning Authority to
retain effective control over the progress of operations and the
restoration of the site. 
3. Within six months from the date of this permission detailed proposals
for the restoration of the whole site, in order to achieve the indicative
restoration identified in the Restoration Masterplan (drawing no ED
13814-001), shall be submitted for the approval of the Planning
Authority.  These proposals shall include: 
(a) A detailed landscape restoration plan giving full details including
a planting schedule showing species, planting densities, sizes,
protection measures, and specification notes for all ground
preparation, soil, planting, any hard landscape. The plan shall
identify the areas of advanced planting. Local provenance stock
shall be used where possible and any seed and woodland
planting mixes shall be designed with ecological input to ensure
they provide maximum foraging and habitat benefit for species
as identified in the Preliminary Ecological Appraisal issued
August 2024 (Job number: ED13814, Report Number: 0002,
Version: V0.1, Status: Final); 
(b) A soil plan setting out the depths of soil in all planted parts of the
site ensuring the soil depth is adequate for the restoration
planting proposed; 
(c) A Site Biodiversity Action Plan demonstrating how restoration
will protect and enhance biodiversity, and strengthen nature
networks; 
(d) The detailed specification, together with the necessary
drawings, for the re-instatement of the agricultural pastures
within the site, including details profiles and gradients, and all
planting to be undertaken alongside the boundaries with a
detailed schedule of species to be planted. For the avoidance of
doubt the advanced hedgerow planting identified on Restoration
Masterplan (drawing no ED 13814-001) shall be planted in
advance of any soil stripping or extraction taking place and shall
include hedgerow and a 5 metres wide strip of planting; 
(e) The detailed specification for the preparation and planting of all
woodland areas, including the numbers, sizes, species and
planting densities of all trees and hedgerows to be planted. For
the avoidance of doubt the wet woodland identified on
Page 98 of 112

Page 99

Restoration Masterplan (drawing no ED 13814-001) and
outlined in the Tree Planting Plan shall be planted in advance of
any soil stripping or extraction taking place; 
(f) the location and details of all new fences and walls to be erected
or repaired, within or around the boundaries of the site; 
(g) a series of cross sections (length and width) bisecting the
extraction area, the adjoining ancient woodland, the adjacent
trees and the restored areas of Area A to illustrate the relation
between the existing planting and the proposed site restoration
levels and planting; 
(h) cross sections showing proposed levels for water feature; 
(i) details of footpath construction; and 
(j) a restoration phase landscape and ecological management plan
to cover a period of five years from the completion of the
restoration landscape works  
Restoration shall comply with the details approved via the discharge of
this condition, or such alternatives as may be approved in writing by
the Planning Authority. 
Reason: To ensure that the restoration of the site is carried out to a
high standard in order to reinstate and, wherever possible, enhance
biological habitats and diversity within the site. 
Protection of water resources 
4. Prior to any operations which are the subject of this permission
commencing on the site, a surface water and groundwater monitoring
strategy shall be submitted to and agreed with the Planning Authority in
consultation with the Scottish Environment Protection Agency (SEPA).
Sampling of surface water and groundwater within and downstream
from the site shall be carried out in accordance with the agreed
strategy, and the results shall be supplied to SEPA and the Planning
Authority.  Thereafter, at periodic intervals throughout the duration of
the operations, to be agreed with the Planning Authority in consultation
with SEPA, further sampling shall be carried out, and the results shall
be submitted to SEPA, with copies to the Planning Authority. 
Reason: In order to monitor the impact of the operations on the quality
and flow of surface water and groundwater, so that any remedial action
can be taken if problems are identified.  
5. Prior to the replacement of any overburden, a method statement
detailing the procedure for the identification, isolation and treatment of
any iron-rich substrate, and a contingency plan for the treatment of any
Page 99 of 112

Page 100

ferruginous discharges that may appear after restoration of the site,
shall be submitted to and approved by the Planning Authority, in
consultation with SEPA. In the event of the appearance of any
ferruginous discharges following the restoration of the site, the
applicants, or their successors, shall carry out all necessary measures,
as identified in the approved contingency plan. 
Reason: To protect against any ferruginous contamination of water
resources that may result from the rebound of groundwater within the
site, following its restoration. 
6. Before any soil stripping is carried out on any phase of the site, a
perimeter drainage system shall be constructed around the whole of
that phase, any existing drainage ditches shall be diverted, and the
appropriate water treatment area shall be constructed and brought into
use, all in accordance with the approved plans and the requirements of
SEPA. The prohibition on the prior stripping of soils does not apply to
those soils which are required to be removed in the formation of new
ditches and water treatment areas. 
Reason: To ensure that facilities for the diversion of surface water
entering the site, and for the reception and treatment of contaminated
water are available from the earliest stages of the development. 
7. All contaminated water shall be treated in appropriate water treatment
areas prior to discharge into any watercourse. The water treatment
facilities shall be of an adequate capacity to cater for the likely
maximum volume of contaminated water, and to control the discharge
flow into any watercourse in accordance with the requirements of
SEPA.  They must be capable of being cleaned without interruption of
the treatment process and shall be maintained in good working order
throughout the duration of the operations.  The direct discharge of oil,
chemicals or other pollutants into the water treatment facilities, or into
any watercourse within or adjoining the site, shall not be permitted. 
8. Except where stored in double skinned tanks any oil, fuel, lubricant,
paint or solvent stored within the site shall be provided with a suitable
bund or other means of containment for 110% of the storage capacity,
and with no passive means of drainage. 
Reason for conditions 7 & 8: To prevent the contamination of surface
or ground water resources, or of soil resources. 
Protection of Soil Resources 
9. Apart from the work required in accordance with condition 6 above, no
work shall be carried out on any undisturbed part of the site until all
topsoil has been stripped to an average depth of 300mm from the initial
excavation area. 
Page 100 of 112

Page 101

10. After the initial excavations have taken place, no work shall be
commenced on any subsequent phases until the topsoil and subsoil
have been removed from these areas; such soils shall be either used
directly for the progressive restoration of earlier phases of the
operations at Upper Dalhousie or stored in accordance with the
requirements of condition 13 below.  
11. Throughout the period of the extraction and restoration operations, all
parts of the site from which topsoil has not been stripped, or on which
topsoil has been respread, shall be protected from all working areas
and access routes. Work routines for stripping operations, shall be
designed to minimise vehicle traffic on unstripped land, and at all times
the mechanical handling and compaction of topsoil shall be minimised.
No vehicle, other than those involved in soil stripping or spreading or
agricultural operations, shall be permitted on any unstripped land. 
12. The stripping of topsoil and subsoil shall only be carried out when
ground conditions are such that no undue damage is done to topsoil
and subsoil (normally in Spring and Summer months, although this
may be extended into dry Autumn periods). Such operations shall be
suspended during adverse weather conditions. 
13. Topsoil and subsoil shall be carefully stored in separate mounds wholly
within the site boundary and shall be prevented from mixing.  Topsoil
mounds shall not exceed 5 metres in height, and subsoil mounds shall
not exceed 6 metres in height. 
14. All soil storage mounds shall be evenly graded, shaped and drained to
prevent water ponding on or around them; thereafter, they shall be
seeded with an appropriate grass seeds mixture as soon as practically
possible to ensure a reasonable prospect of successful sowing. 
15. No turf, topsoil or subsoil shall at any time be removed from the site. 
Reason for conditions 9 -15: To protect the existing soil resources of
the site, in order to ensure its successful restoration to agricultural or
other appropriate uses, following the completion of sand extraction. 
Overburden Storage 
16. Any overburden not used immediately for the backfilling of previous
cuts, shall be stored in a location to be agreed in writing with the
Planning Authority, wholly within the application boundary, and the
mound shall not exceed 15m in height; the sides and top of the
overburden mound shall be evenly graded and shaped, and they shall
be seeded with a suitable low-maintenance grass seeds mix. 
Reason: To ensure that the storage of overburden is stable and not
unduly obtrusive. 
Page 101 of 112

Page 102

Protection of Agricultural Interests 
17. Except where otherwise agreed in writing by the Planning Authority, the
applicants shall make the site stock-proof and maintained as such until
restoration of the site is complete. All the existing perimeter hedges,
fences and walls, shall be maintained to protect the site from damage. 
Where the site boundary does not coincide with an existing hedge,
fence or wall, then the applicants shall, unless otherwise agreed in
writing by the Planning Authority, provide and maintain stock-proof
fencing, with gates or cattle grids at every opening, until the restoration
is completed.  Undisturbed hedgerows not affording screening for the
proposed development, within or bounding the site, shall be carefully
maintained, in accordance with good agricultural practice, and be cut
and trimmed at the proper season throughout the period of working and
restoration of the site. 
18. All invasive weeds on the site, including particularly those on the
topsoil and subsoil storage mounds, shall be treated as often as
necessary and as determined by the Planning Authority throughout the
life of the site, at an early stage of growth, in order to prevent spreading
within the site or onto adjoining agricultural land. 
19. All types of vermin shall be controlled in a manner approved by the
Planning Authority to prevent them spreading to adjoining agricultural
land. 
Reason for conditions 17-19: To protect the continued efficient
operation of adjoining farmland. 
Adjacent Site Drainage 
20. The works on site shall be designed and implemented to ensure that
they do not negatively impact on the drainage of either the site as
restored or the surrounding agricultural land.  During the aftercare
period the applicant shall ensure both the site, and the surrounding
agricultural land has field drainage that is functioning appropriately to
allow productive agricultural activities to continue. This will include: 
(a) ensuring field drainage for the finally restored land is functioning
appropriately; 
(b) protecting and maintaining any ditch, stream, watercourse or
culvert passing though the site which provides drainage for
adjoining land; 
(c) make provision for the installation of the field drainage system
on the site to commence after one full growing season has
elapsed from the time of the final stage of topsoil restoration;
and, 
Page 102 of 112

Page 103

(d) make provision for the field drainage system to be completed
within two years of topsoil restoration. 
Should there be any complaints received by the Planning Authority
regarding the drainage at the site, which the Planning Authority
consider merit investigation, the applicant shall take all reasonable
steps to address any drainage issues with the site or the surrounding
land, which can reasonably be considered to have resulted from the
works on the site. 
Reason: To ensure the continued adequate drainage of the site, and
adjoining land, in the interests of its continued productive agricultural
use.  
21. No refuse, soil or waste material from outside the site shall be
deposited within the site for any purpose without the prior written
permission of the Planning Authority. 
Reason: To ensure that site restoration is achieved using existing on-
site materials only. 
22. Any public utilities crossing or adjacent to the site shall be protected or
diverted, as necessary, in accordance with the requirements of the
relevant authorities. 
Reason: To safeguard existing public utilities in the area. 
23. At all times that the site is in operation, a wheel washing facility for
vehicles exiting the site shall be in use and shall be regularly cleaned
and recharged with clean water, and the sections of public road
between the site access and the A7 shall be kept clear of mud or dirt. 
Reason: To prevent mud and dirt from the site being spread onto the
public road, where it may constitute a hazard or nuisance to road
users. 
Archaeology 
24. Development shall not begin until the applicant has undertaken and
reported upon a programme of archaeological (Monitored Soil Strip)
work in accordance with a written scheme of investigation which has
been submitted by the applicant (or their agent) and approved by the
planning authority. 
Biodiversity 
25. Prior to the commencement of development an Ecological Impact
Assessment (complying with CIEEM guidance) shall be submitted to
and approved in writing by the Planning Authority. Development and
Page 103 of 112

Page 104

restoration thereafter shall comply with any mitigation measures
identified in the Ecological Impact Assessment.  
Reason:  To ensure that the impact of restoration works on the
biodiversity of the site is assessed and minimised. 
26. Prior to the commencement of development, a biodiversity metric
should be used to calculate in full the capacity of the proposed layout
and proposed habitats to deliver biodiversity enhancement. The results
of the metric shall be submitted to and approved in writing by the
Planning Authority, prior to the commencement of any new restoration
works. 
Reason:  To ensure that the development protects biodiversity,
reverses biodiversity loss, delivers positive biodiversity effects and
strengthens nature networks. 
27. The mitigation measures identified in Chapter 4 of the Preliminary
Ecological Appraisal issued August 2024 (Job number: ED13814,
Report Number: 0001, Version: V0.1, Status: Final) shall be
implemented throughout the duration of the extraction operations on
the site, unless alternative mitigation measures are approved via
condition 24. 
Reason:  To minimise the adverse impact of the development on
wildlife within and adjoining the site. 
28. No soil stripping or extraction works shall take place within 15 metres
of the ancient woodland at Galladean Plantation, Young Bog Wood or
Dalhousie Burn Plantation. 
Reason: To safeguard the biodiversity value of the areas of ancient
woodland. 
Hours of Working 
29. No operations shall take place outwith the hours of 07.00 to 19.00 on
Mondays to Fridays inclusive and 07.00 to 13.00 on Saturdays.
Operations shall include excavation, extraction and restoration, initial
preparation of the site including the formation and removal of perimeter
soil bunds, and the movement of lorries entering or leaving the site.  No
work shall be carried out on Sundays or on public holidays except for
emergency or routine maintenance work. 
Reason:  To minimise the effect the impact of the development on the
amenity of residents living in the vicinity of the site and as a
consequence of the Environmental assessment considering slightly
shorter hours than the existing planning consent.   
Page 104 of 112

Page 105

Noise Control 
30. Noise levels, as measured at 3.5 metres from any façade of any noise-
sensitive dwelling, from all site operations other than soil stripping but
including bund formation and restoration, shall not exceed a one-hour
LAeq of 45db. 
31. Noise levels, as measured in accordance with condition 31, from soil
stripping shall not exceed 60 dB(A) LAeq1h during the approved
operating hours. 
32. The surface of all haul roads and the track between the Hopefield
Distributor Road and the sites shall be maintained in an evenly graded
condition, without bumps or potholes, at all times throughout the
duration of operations at the site. The speed limit of 15mph shall be
enforced along this section of road/track. 
33. The routes of vehicles within the site shall be designed to minimise the
need for lorries to reverse, thereby activating any reversing alarms with
which they may be installed. 
34. All vehicles exiting the site shall turn right and continue to the A7 via
the B6392. 
35. Throughout the duration of the operations at this site, the applicants, or
their successors, shall implement in full the noise mitigation measures,
identified in Section 9 of the Environmental Statement, including those
relating to site operation and general environmental management. In
particular, a programme of regular noise monitoring shall be
undertaken, at locations to be agreed beforehand with the Planning
Authority, and the results shall be made available to the Authority on
request. 
Reason for conditions 30-35: To ensure that noise generated by the
operations on the site is minimised, in order to protect the amenity of
those residents living in the vicinity of the site and as recommended in
PAN 50 Annex A: The control of noise at surface mineral workings. 
Dust Control 
36. Whenever necessary, all roads and other un-vegetated surfaces within
the site, including sand stockpiles, shall be damped down to prevent
the spread of windblown dust from the site; particular care shall be
taken in the vicinity of residential properties, and moisture screens shall
be installed within the site, if necessary. 
37. Throughout the duration of operations, the surface of the site access
roads shall be kept in good repair and shall be regularly graded to
remove loose material. 
Page 105 of 112

Page 106

38. All mobile plant used within the site shall be fitted with upward facing
exhausts.  
39. All laden vehicles leaving the site shall be effectively sheeted or
enclosed. 
40. All vehicles moving within the site, and along the access road to the
Hopefield Distributor Road shall be subject to a speed limit, not
exceeding 15mph. 
41. Throughout the duration of the operations at this site, the applicants, or
their successors, shall implement in full the dust control measures,
identified in the Dust Management Plan issued January 2018 (Job
number: ED11578, Report Number: 0001, Version 1), including those
relating to site operation and general environmental management. In
particular, a programme of dust monitoring shall be undertaken, in
accordance with details submitted to and approved by the Planning
Authority prior to operations commencing on the site, and the results of
the monitoring shall be submitted to the Authority at the agreed
intervals. The dust monitoring programme shall include details of the
air quality standards to be achieved at agreed locations on the
perimeter of the site, and the remedial measures to be adopted in the
event of those standards not being achieved, including, in extreme
adverse conditions, the temporary cessation of all operations on the
site. 
Reason for conditions 36-41: To minimise the impact of the
development on the environment of the surrounding area, through the
generation of dust from the operations. 
Landscaping Restoration and Aftercare 
42. The site shall be completely restored, in compliance with conditions 3
and 43 to 50, within one year of the expiry of the time limit placed on
the operation of the site. 
43. The site shall be restored progressively in accordance with the details
provided in terms of condition 3 of this permission. 
44. The site shall be restored to the contours approved in accordance with
the details approved in terms of condition 3, or such other revised
contours as may be agreed in writing with the Planning Authority, and
the surface levels shall be so graded as to ensure the final surface
merges smoothly with the adjoining land. 
45. Within six months of the completion of sand extraction operations, all
buildings and fixed or moveable plant shall be removed from the site
and all site access roads shall be removed or reverted back to farm
access tracks, unless required for the restoration of the site, or
otherwise agreed by the Planning Authority; and all such areas shall be
Page 106 of 112

Page 107

subject to the full restoration treatment, as detailed below. Any access
roads required for the restoration work shall be retained until the end of
the restoration period and then removed or reverted back to farm
access tracks. 
46. All operations to remove topsoil and subsoil from the storage mounds
and to re-spread them shall be carried out when the ground and
storage mounds are in a suitable dry condition, as agreed with the
Planning Authority. Earth-moving machinery shall travel to and from the
soil mounds along clearly defined routes, and these routes shall be
ripped before being covered with the next layer of subsoil or topsoil.
When the vehicle is emptied after spreading subsoil or topsoil, it must
immediately turn off on to overburden or subsoil areas respectively. 
On sloping land, the direction of travel of machines should, as far as is
possible, be parallel to the contours, in order to minimise erosion. All
operations following the replacement of topsoil shall be carried out by
suitable agricultural machinery. 
47. On all areas that are to be restored to agricultural use, after
replacement of topsoil, chemical analyses of the soils shall be carried
out by an approved agency to assess the fertiliser, lime and other
major and minor nutrients required to promote the establishment and
growth of appropriate plants for the agreed land use. The land shall
then be cultivated using normal agricultural machinery to prepare a
seed bed suitable for the sowing of grass seeds, during which process
any stones larger than would pass through a wire screen mesh with a
size of 100mm shall be removed, together with other obstructions to
future cultivation. Lime, fertilisers and other plant nutrients shall be
applied in accordance with the recommendations of the approved
agency carrying out the soil chemical analyses so that the soil is
sufficiently fertile to permit the chosen programme of restoration.  The
land shall then be sown with a short-term grass seed mixture, based on
perennial rye grass and white clove, or such other species as may be
approved. 
48. The site shall be restored only in accordance with the restoration plans
and specifications approved under the terms of condition 3, and
restoration works shall not be considered to be completed until all
watercourses, ditches, fences, walls, hedges, field accesses trees and
other planting have been installed or carried out in accordance with
those plans and specifications agreed with the Planning Authority. 
Reason for conditions 42-48: To ensure that all parts of the site are
properly restored to agriculture or other approved after-use. 
49. Any trees or shrubs planted as part of the restoration proposals that
die, are removed, become seriously diseased or are severely damaged
within five years of planting shall be replaced during the next available
planting season with others of similar size and species. 
Page 107 of 112

Page 108

Reason: To ensure that all new planting has an adequate opportunity
to become successfully established. 
50. At least three months before the completion of the restoration of the
application site an aftercare scheme, in accordance with Schedule 3 to
the Town & Country Planning (Scotland) Act 1997, shall be submitted
for the approval of the Planning Authority. The scheme shall be carried
out, as approved or modified by the Authority, for a period of five years
from the date when the restoration of the site has been completed in
accordance with the terms of condition 49. 
51. The aftercare measures to be taken shall be such as to bring the land
to the required standard for use for agriculture, to enable the
establishment of the woodland planting and for amenity purposed
specifically new habitat creation with appropriate footpath access. 
Reason for conditions 50 & 51: To ensure that all the restored land is
properly managed for a sufficient period to ensure its effective
establishment to the approved after-use. 
Monitoring 
52. Throughout the duration of this development, the applicants or their
successors shall, if and when required to do so by the Planning
Authority, submit such information as may be necessary, including any
relevant plans, to enable the Authority to determine the progress of the
operations. 
Reason: To ensure effective monitoring of the development.  
53. The proposed development of the site shall progress in accordance
with the Phasing Plan – Extraction and Restoration, submitted as part
of the planning consent. 
Reason: To ensure the phasing of the extraction and restoration of
Areas A, B, and C allow for the appropriate phases development of the
site and to ensure the restoration proposals for the three areas are
achieved. 
54.  The developer shall ensure that an approved bond or other financial
provision is maintained through the duration of the permission and that
the bond provides sufficient funds to cover restoration of the site to the
restoration plans approved in terms of condition 3 of this permission.  
Reason: To ensure that there are sufficient funds available throughout
the life of the development to carry out the full restoration of the site. 
53. All of the mitigation measures identified in Tables 15.1 to 15.9 of the
approved Environmental Statement shall be implemented in full. 
Page 108 of 112

Page 109

Reason: To ensure the mitigation measures identified in the
Environmental Statement are implemented, to minimise possible
environmental impacts and to ensure the development is carried out in
the manner described in the Statement. 
Peter Arnsdorf
Planning, Sustainable Growth and Investment Manager 
Date:     22 November 2024 
Application No:    18/00082/S42
Applicant:   Tillicoutry Quarries
Agent:              Wardell Armstrong LLP
Validation Date:  5 February 2018 
Contact Person:  Graeme King, Planning Officer 
Email:     graeme.king@midlothian.gov.uk 
Background Papers: 06/00689/FUL, 13/00064/DPP, 16/00816/SCO, 
17/00380/SCO, 17/00565/PAC, 18/00082/S42
Attached Plans: Location Plan and Restoration Plan
Page 109 of 112

Page 110

N
Midlothian Council
Fairfield House
8 Lothian Road
Dalkeith, EH22 3AA
Reproduced from the Ordnance Survey map with the
permission of the controller of Her Majesty's Stationary Office.
Crown copyright reserved. Unauthorised reproduction infringes
Crown copyright and may lead to prosecution or civil
proceedings.
Planning Service
Place Directorate
Area A
Application Site (18/0081/DPP)
Existing Site (18/00082/S42)
Midlothian Council Licence No. AC0000811376 (2024)
Extension to existing sand quarry
Land south west of Upper Dalhousie Sand Quarry,
Rosewell
Area B
Area C
File No. 18/00081/DPP
Scale 1:7000Page 110 of 112

Page 111

Iss
Drain
Drain
Issues
Drain
Drain
Sinks
Drain
DrainDrain
Burn
Shiel
Drain
Drain
Issues
Sinks
Issues
Sinks
Issues
140 140 135
140
110
115
120
120
120
120
120
120
145
135
135
135130
130
130
130
130
130
125
125
125
125
125
125
135
125
125
125
125
115
Upper Dalhousie
Parkneuk
Existing wall
retained
Advanced hedgerow
planting with trees to screen
operations in Area C
Advanced gapping-up of
existing hedgerow
to
screen operations in Area C
Advanced hedgerow
planting with trees to screen
operations in Area C
Ecological enhancements
to create wet woodland
Ecological enhancements
to water feature, including
retention of a sand face
for nesting sand martins
Existing wall
retained
Area B
Area A
Area C
Galladean Plantation
Dalhousie Burn Plantation
W
orkings
dis
W
eirs
Track
Track
Young Bog W
ood
Track
Track
0
120
240
metres
Copyright Reserved
c
DRAW
N
BY
CHECKED
BY
CLIENT
PROJECT
DRAW
ING
TITLE A1
ED13814-001
-
1:2,000
17.05.2024
AB
SCALE
DATE
APPROVED
BY
DRG
No.
DRG
SIZE
REV
SUIT. CODE
Upper Dalhousie Sand Quarry
Restoration Masterplan
Tillicoultry Quarries
N:\ED\ED13814
- DALHOUSIE
QUARRY
EXTENSION\03
- DESIGN\AUTOCAD\ED13814-001
RESTORATION
M
ASTERPLAN.DW
G
Reproduced from
Ordnance Survey Maps
Ó
Crown Copyright All Rights Reserved
Licence No. 0100031673
APP'D
CHK'D
REVISION
DETAILS
DATE
DRAW
N
KEY
Existing quarry
W
oodland
Trees
Hedgerows
Core Paths
Existing features
Other Paths
Informal paths identified by the local community
W
oodland
Hedgerow
trees
Hedgerows
Species rich grassland field margins
Proposed features
Agricultural grassland
W
ater feature
Informal path to provide link between
existing paths
Grassland
W
etland margins to water feature
Proposed extension to quarry
W
oodland edge/scrub
W
et woodland
Page 111 of 112

Page 112

Page 112 of 112