Notice of Meeting and Agenda 
Midlothian Council 
Venue:  Council Chambers, 
Midlothian House, Dalkeith, EH22 1DN 
Date:  Tuesday, 15 November 2022 
Time:  11:00 
Executive Director : Place 
Contact:
Clerk Name: Democratic Services
Clerk Telephone: 
Clerk Email: democratic.services@midlothian.gov.uk 
Further Information: 
This is a meeting which is open to members of the public.  
Privacy notice: Please note that this meeting may be recorded. The
recording may be publicly available following the meeting. If you would
like to know how Midlothian Council collects, uses and shares your
personal information, please visit our website: www.Midlothian.gov.uk 
Page 1 of 164

Page 2

1          Welcome, Introductions and Apologies   
2          Order of Business 
Including notice of new business submitted as urgent for consideration at the
end of the meeting. 
3          Declaration of Interest   
4          Deputations   
5          Minutes
5.1 MInute Midlothian Council 4 October 2022 5 - 22
5.2 MINUTE Special Midlothian Council for 27 September 2022 23 - 26
5.3 Minute Volume Index - 15 November 2022 27 - 28
5.4 Private Minute Volume Index 15 November 2022 
5.5 Midlothian Council Action Log - 15 November 2022 29 - 32 
6          Questions to the Council Leader 
No items for discussion 
7          Motions 
No items for discussion 
8          Public Reports
8.1 Midlothian Council Strategic Plan 2023 - 2028 Report by Chief
Executive
33 - 52
8.2 Financial Monitoring 2022/23 – General Fund Revenue Report by
Chief Financial Officer (Acting)
53 - 66
8.3 General Services Capital Plan 2022-23 Quarter 2 Monitoring Report
by Chief Financial Officer (Acting)
67 - 80
Page 2 of 164

Page 3

8.4 Housing Revenue Account - Revenue Budget and Capital Plan
2022_23 Report by Chief Finance Officer (Acting)
81 - 88
8.5 Early Learning and Childcare Funding Rate 2022-23 Report by
Executive Director Children, Youing People & Partnership
89 - 98
8.6 Appointment of Representatives to Outside Bodies - Midlothian
Twinning Association– Executive Director Place
99 - 102
8.7 Social Work Annual Report 2021-2022 by Chief Social Work Officer 103 - 106
8.8 Midlothian Strategic Housing Investment Plan 2023_24 to 2027_28
Report by Executive Director Place
107 - 146
8.9 Capacity increase to Replacement Beeslack CHS Report by
Executive Director Childre, Young People & Partnerships
147 - 152
8.10 Proposed Revised schedule of meeting dates January to June 2023
Report by Executive Director Place
153 - 158
8.11 Webcasting Meetings of Council and its Committees Report by
Executive Director Place
159 - 164 
9          Private Reports
9.1 Appointment of Interim Chief Officer Corporate Solutions Report by
Executive Director Place
• 1. Information relating to a particular employee, former employee or
applicant to become an employee of, or a particular office holder, former
office-holder or applicant to become an office-holder under, the authority.
• 7. Information relating to anything done or to be done in respect of any
particular person for the purposes of any of the matters referred to in section
27(1) of the Social Work (Scotland) Act 1968 (providing reports on and
supervision of certain persons). 
9.2 Poltonhall Artificial Pitches Refurbishment and Extension - Budget
Expenditure update Report by Executive Director Place
• 6. Information relating to the financial or business affairs of any particular
person (other than the authority).
• 9. Any terms proposed or to be proposed by or to the authority in the course
of negotiations for a contract for the acquisition or disposal of property or the
supply of goods or services. 
10    Date of Next Meeting 
The next meeting will be held on 13 December 2022 
Page 3 of 164

Page 4

Page 4 of 164

Page 5

Minute of Meeting 
Midlothian Council 
Date Time Venue
4 October 2022 11.00 am Council Chambers, Midlothian
House 
Present: 
Provost McCall (Chair) Depute Provost McManus
Councillor Parry – Council Leader Councillor Cassidy  – Depute Council
Leader
Councillor Curran  Councillor Bowen
Councillor Drummond Councillor Imrie
Councillor McEwan Councillor McKenzie
Councillor Milligan Councillor Pottinger
Councillor Russell Councillor Smaill
Councillor Scott Councillor Winchester
Councillor Virgo 
In attendance: 
Dr Grace Vickers, Chief Executive  Fiona Robertson, Executive Director
Children, Young People & Partnerships
Kevin Anderson, Executive Director
Place
Alan Turpie, Legal and Governance
Manager/Monitoring Officer
Gary Fairley, Chief Officer Corporate
Solutions
Nick Clater, Head of Adult & Social Care
Derek Oliver, Chief Officer Place Fiona Clandillon Head of Development
Saty Kaur, Executive Business
Manager
Lynn Cochrane Communications Team
Leader
David Gladwin Financial Services
Manager
Annette Lang , Strategic Service Re-
Design Manager
Gordon  Pollock, Project Director Zero
Waste Edinburgh and Midlothian
Myra Forsyth Quality and Scrutiny
Manager
Edel Ryan , Senior Manager Protective   
Page 5 of 164

Page 6

2
Marco Reece-Heal Business Analyst Mike Broadway , Democratic Services
Officer
Ross Neill, Democratic Services Team
Leader
Andrew Henderson , Democratic Services
Officer 
1.  Welcome and Apologies for Absence 
The Provost welcomed everyone to the meeting reminding all that it was a public
meeting being webcast live. 
Apologies for absence were intimated on behalf of Councillor Alexander, Morag
Barrow, Mrs Morton & Mrs Lawrie. 
The Provost then asked all to stand and in memory of Her Majesty the Queen’s
Elizabeth II’s passing. 
Councillor Leader Parry offered words of condolence on behalf of Midlothian Council
and best wishes to Charles III and the royal family. She reminded all present of the
visit the late Queen made to Midlothian earlier in her reign. She thanked the people
of Midlothian for all the tributes and council staff for providing opportunities for the
public to note their condolences. 
Councillors Milligan and Virgo also offered condolence to the Royal family. Both
noted that the late Queen was a fantastic public servant whose duty to the country
will be missed. 
The Provost echoed all sentiments by fellow councillors adding her own
condolences. 
2. Order of Business 
The Provost advised the order of business as per the agenda noting 9.2 had been
withdrawn 
3. Declarations of interest 
None 
4. Deputations 
None received. 
5. Minute of Previous Meeting 
No.  :
5.1  MINUTE Midlothian Council for
Approval  23 Aug 2022
Executive Director Place
Questions to Officers
Accepted as a clear and fair record  Page 6 of 164

Page 7

3 
Midlothian Council Minute 23 August 2022
Private Midlothian Council Minute 23 August  2022 
Proposed Councillor Parry
Seconded Councillor Smaill 
Decision
Approved 
Action
All to Note 
No.  :
5.2 & 5.3 Minute Volume Executive Director Place
Questions to Officers
5. 2 Minute Volume Index - 04 October 2022
5.3 PRIVATE Minute Volume Index - 04 October 2022 
All members were satisfied the action log was up to date and in order. 
Both proposed and seconded by 
Councillor Parry
Councillor Milligan 
Decision
All to Note
Action
None 
No.  :
5.4 Action Log Update Executive Director Place
Questions to Officers 
All members were satisfied the action log was up to date and in order. 
Councillor Milligan asked if there would be an update to future Council meetings
concerning the levelling up fund. He requested it focus on areas that ‘Are left
behind’, aimed primarily at areas of Midlothian deemed deprived. 
Mr Anderson responded that this would be presented later in the year and had
been submitted and the Council was awaiting the outcome of that.   
Decision
All to Note
Action
None 
6. Question to the Leader of the Council 
Page 7 of 164

Page 8

4
None 
7. Notices of Motion 
None 
8. Reports 
Report
No.
Report Title Report by:
8.1 MLC Annual Audit Report 2021-22  Report by EY, Chief Officer
Corporate Solutions
Outline of report and summary of discussion 
This report has been prepared in accordance with Terms of Appointment Letter
from Audit Scotland dated 31 May 2016 through which the Accounts Commission
has appointed us as external auditor of Midlothian Council (the Council) for
financial years 2016/17 to 2021/22. As a result of the impact of Covid-19 our
appointment was extended by a further 12 months to include the financial year
2021/22. We undertake our audit in accordance with the Local Government
(Scotland) Act 1973 and our responsibilities as set out within Audit Scotland’s
Code of Audit Practice. This report is for the benefit of the Council and is made
available to the Accounts Commission, the Controller of Audit and Audit Scotland.
This report has not been designed to be of benefit to anyone except the recipients.
In preparing this report we have not taken into account the interests, needs or
circumstances of anyone apart from the recipients, even though we may have
been aware that others might read this report. 
Any party other than the Recipients that obtains access to this report or a copy
(under the Freedom of Information Act 2000, the Freedom of Information
(Scotland) Act 2002, through a Recipient's Publication Scheme or otherwise) and
chooses to rely on this report (or any part of it) does so at its own risk. To the
fullest extent permitted by law, Ernst & Young LLP does not assume any
responsibility and will not accept any liability in respect of this report to any party
other than the Recipients. 
Mr Fairley spoke to the report in the absence of EY representatives he noted it
provides an unqualified opinion. There is no change to the reserve provision,
financial sustainability is highlighted in ‘Red’ due to the current uncertainty. He
added that since last year the financial management has moved from green due to
the current transition period. Best value is currently making good progress. 
Councillor Parry thanked EY for the report and the former independent Chair of the
Audit Committee, she added that a large part of the uncertainty is out with the
Councils control. 
Both Councillor Parry and Smaill suggested that in future the language within the
report be plainer to allow it to be more accessible to the public. Councillor Smaill
also noted a reduction in surplus and asked for this to be explained. 
Mr Fairley responded that there are certain accountant etiquettes that must be
followed and are a requirement of the accountancy code. That said, the summaries
within the report do attempt to simplify the more technical aspects of the report. 
Page 8 of 164

Page 9

5
Councillor Milligan echoed his Colleagues comments stressing that it is important
now in light of the very challenging times that every penny is accounted for. 
P:roposed by Councillor Parry
Seconded by Councillor Smaill   
Decision
None 
Action 
All to Note 
Report
No.
Report Title Report by:
8.2  Midlothian Council Strategic Plan
2022-2027 and associated Medium
Term Financial Strategy  2023-24 to
2027-28
Chief Officer Corporate
Solutions
Outline of report and summary of discussion
Midlothian Council Strategic Plan 2022-2027, A great, green place to grow: where
people and the environment flourish
1. Inclusive, Empowered, Resilient and Safe Communities:
2. All children, young people, adults and communities in Midlothian are supported to be the
best they can be
3. Health and Social Care Transformation
4. Accelerating Inclusive Growth
5. Carbon Neutral by 2030: 
The aim of developing a Medium Term Financial Strategy continues to be that of
providing a multiyear strategy aligned to the development and approval of the
Midlothian Council Strategic Plan 2022-2027, a great, green place to grow: where
people and the environment flourish. It seeks to support the Council in fulfilling its
statutory duty to set a balanced budget and determine Council Tax levels annually. 
In that respect, the final budget for 2023/24 will be updated to reflect the actual
position for Scottish Government grant and Council Tax policy once the Scottish
Government’s budget bill and the associated finance circular are published either
late in 2022 or potentially early 2023.  As updates are brought to Council a
reassessment of pay and inflation provisions will be made taking cognizance of the
Scottish Government Public Sector pay policy and the extent to which this is
reflected in the grant settlement. 
Recommendations – 
Council is asked, on the recommendation of the Business Transformation
Steering Group, to:-
a) Note the draft of the Midlothian Council Strategic Plan 2022-2027, A great,
green place to grow: where people and the environment flourish as set out
in appendix B to this report and endorse moving forward with a period of
communication, engagement and consultation with communities on the draft
strategic plan in the context of the challenging financial outlook;
b) Agree to receive a further report on the outcome of the communication,
engagement and consultation with communities;
c) Note the operational saving measures set out in appendix C; 
Page 9 of 164

Page 10

6
d) Note the adoption a range of additional transformation focused activity as
set out in the report. In doing so agree that additional capacity to progress
these at pace is funded from the set aside business transformation
funds/capital receipts flexibility;
e) Note that a further report will need to be presented to Council to formalise
the compliance requirements set out in Finance Circular 2/2022 in respect
of the use of the capital receipts flexibility;  
f) Note that the work of The Business Transformation Steering Group will
continue to give consideration to further measures necessary to support the
delivery of balanced budgets before any policy measures are presented to
Council;
g) Note that the financial outlook remains challenging for this term of Council
and note the recommendation of the external Auditor that, “as a matter of
urgency, officers and elected members need to work together to develop
and agree the medium-term financial strategy and progress the Council’s
transformation plans”. 
In addition to the recommendations of Business Transformation Steering Group:- 
a) Note the update on Scottish Government grant prospects incorporating the
additional measures, which support the 2022/23 pay negotiations including
additional grant together with the exploration of funding flexibilities.  
b) Note the direct implications arising from the UK Government fiscal event on
23 September 2022 and that an update to the Scottish Governments budget
is expected to follow;
c) Note the potential for a delay in the publication of the draft Scottish
Government budget for 2023/24 and associated grant settlement for
Councils as a consequence of the timing of the UK Autumn Budget
Statement;
d) Note the update on the position with 2022/23 pay claims and future pay
provisions and the associated impact for the period of the Medium Term
Financial Strategy;
e) Delegate to the S95 Officer, in consultation with the Leader of the Council
authority to implement the most appropriate mechanism to utilise the
additional capital grant being provided in 2022/23 and 2023/24 to part fund
increased pay bill costs;
f) Note the update in respect of fiscal flexibilities; 
g) Note that the underlying budget gap for 2022/23 is now projected to be  
£11.730 million and that as a consequence of both the inflationary increase
in costs and cash flat grant settlements the projected budget gap for
2023/24 now stands at £13.4 million rising to a projected £26.2 million by
2027/28;
h) Otherwise note the remainder of the report. 
Dr Vickers introduced the report noting that it followed on from a previous report,
adding it is imperative that all work together to face the challenges, risk &
uncertainty ahead. The report outlines the budget gap 23/24 of approximately £13
million through to 27/28 where it will rise to approximately £26 million. It is
recommended within the report that the new draft 5 year strategy go out for
consultation. Page 10 of 164

Page 11

7 
Drawing attention to Section 9 of the report, Dr Vickers noted it covers the cost
saving measures, and the Capital grant. She noted again the challenges and
complexities contained with the report.
Mr Fairley spoke in depth to report focusing on key areas noting again the financial
challenges and projections. He also noted the work on savings covered by the
Business Transformation Steering Group (BTSG). 
Mr Fairley spoke to Section 5, this covers the Scottish Government Grant
Prospects and noted the mechanism to use the capital grant, and this comes in a
very challenging environment as outlined in the previous report by EY. The
projection includes uncertainty over pay rises and if there is any increase in
Government funding. Work is continuing to fully establish all the implications post
pandemic in partnership with Audit Scotland. The budget gap is described in detail
and predicts future years before any rent increase or any other funding.
Members agreed this is the most challenging of times, the public through
communications need to be encouraged to participate in the consultation. At
present all efficiencies have already been made and services in some areas
reduced. The public must be made aware of Statutory services. No decision made
by Councillors will be made lightly.
There was debate around the wording of certain targets and commitments and
although items such as reduction in child poverty were to be achieved they should
be striven for. 
Councillor Milligan felt the strategic plan for 2022 to 2027 needed to be rewritten
Councillor Parry suggested it return to BTSG 
Councillor Virgo agreed that some of the targets within the plan are aspirational
and not commitments and a re-write was in order.
All groups content for BTSG to review and draft a re-write of the 5 Year strategic
plan. 
Councillor Parry proposed the report and its recommendation with the exception of
1A - the 5 year strategic plan
Councillor McKenzie seconded 
Decision
Agreed 
Action
5 year Strategic Plan passed to BTSG for further work and a re-write 
Report
No.
Report Title Report by:
8.3 National Public Holiday for HM The
Queen’s Funeral Report  
Executive Director
Children, Young People
and Partnerships
Outline of report and summary of discussion
Page 11 of 164

Page 12

8
The Council is asked to approve the recommendation to change the planned
school holiday day of 19 September 2022 to Monday 24 October 2022 and the
Staff Development day scheduled for 24 October 2022 to Tuesday 25 October
2022. 
Recommendation – 
To seek the Council’s approval to re-arrange the pre-existing school holiday
scheduled for 19 September 2022 to Monday 24 October 2022, in light of the
national bank holiday on 19 September to mark the State Funeral of HM Queen
Elizabeth II. 
Ms Robertson spoke to the report noting the Scottish Government is expected to
give consent, it was also in lined with neighbouring local authorities and would
result in one less learning day. 
Councillor Parry proposed
Councillor Virgo seconded 
Decision
Agreed
Action
None 
Report
No.
Report Title Report by:
8.4 Standing Order 19.2 Decision Report  Chief Executive
Outline of report and summary of discussion
The purpose of this report is to advise the Council of the decision taken by the
Chief Executive in consultation with the Leader of the Council in terms of Standing
Order 19.2. 
Recommendation – 
Council is invited to note the terms of this report. 
Dr Vickers introduced the paper drawing attention to key areas for noting. 
Councillor Parry thanked all staff who had to make other provisions on the day
Decision
None
Action
All to Note 
Report
No.
Report Title Report by:
8.5 Midlothian Cares Practical Support
Measures Identified Report
Strategic Service Re-
Design Manager 
Outline of report and summary of discussion
The purpose of this report is to explore the potential mitigating actions Midlothian
Council could take to support local people experiencing additional challenges from
the cost of living crisis.  The report also sets out some immediate recommended
Page 12 of 164

Page 13

9
actions and others for further exploration to enable a fuller assessment of cost,
impact and deliverability. 
The report also contains a communications plan of how we will ensure local people
are made aware of the additional supports available through the Midlothian Carers
Communication Plan, as well as a Calendar of Activity for Challenge Poverty
Week. 
Recommendations – 
• Note the range of time limited crisis mitigation measures outlined in the
report, and
• Note the time limited review timescales for these measures due to rapidly
changing landscape and pressures
• Agree to take forward some immediate measures in advance of winter from
utilisation of £118,013 (22/23) from earmarked Covid funding on the basis
that it supports wellbeing.
• Note the launch of Midlothian Cares Communication Plan including pledges
from Local Businesses and Organisations
• Note and promote the Calendar of Activities for Challenge Poverty Week. 
Ms Lang spoke to the report highlighting the decisions of the Task Force and the
work ongoing by Council Services & partners, she noted it sets out short term and
long term goals for consideration. 
Members thanked all for their contribution of the 3rd sector partners and others who
worked closely with Council services providing assistance for the most vulnerable
in the community. That vulnerable will also need to be regularly re-assessed 
Ms Lang agreed that the projections predict household with incomes of £40k may
begin to be affected by the Cost of Living increases. Therefore the definition will
need to be flexible. 
Councillor Imrie asked if every penny goes to those in need. 
Ms Lang confirmed that it does but partners do incur running costs and 15% is
attribute to those costs which include fuel, Facilities, photocopying etc. This figure
has been benchmarked with other funding. 
Members asked further questions concerning information exchange protocols
between Partners to combat fraud. Also the provision of school meals in particular
children not eating them. 
Ms Lang confirmed that within the limits of General Data Protection Regulation
(GDPR) legislation there is information sharing and regular checks. The Cost of
Living Task Force also has two head teachers present who will provide a briefing
to the group in due course. 
Ms Robertson added that the school uniform provision is out to consultation, it
covered a number of options to reduce costs that would be considered. Food
standard for school meals is set by the Scottish Government and is very strict. 
A monthly audit of how the finds are distributed and spent was requested by
Members. 
Ms Land confirmed that partners already had a reporting template in place  Page 13 of 164

Page 14

10
Councillor Curran suggested that once the results of the School uniform
consultation were back and policy on school uniforms could be drafted. 
Ms Robertson confirmed a report will be presented to Council in due course 
Councillor Parry proposed 
Councillor Scott seconded 
Decision
Agreed
Action
Audit of funding distribution report – Annette Lang 
Report
No.
Report Title Report by:
8.6 Housing Revenue Account – Rent
Setting Strategy 2023-24 - 2025-26
Report 
Executive Director Place
Outline of report and summary of discussion
This report presents rent setting strategy options for future rental charges for
council housing from April 2023, which in turn will support the continuing
investment in the Council’s existing Housing stock and will determine the level of
new build investment beyond the Council’s current social housing programme
commitment.   
Recommendation – 
It is recommended that Council approves the Rent Setting Strategy options for
2023/24 – 2025/26 for consultation. Following approval the options will be subject
to consultation with all Midlothian Council tenants and waiting list applicants during
the Winter 2022 period. The consultation outcomes and a recommended option
will be reported back to Council in February 2023. 
Mr Anderson spoke to the report noting council housing demand will increase, he
also drew member’s attention to the potential rent increase required in 2023 to
2026, adding that there has been a rent freeze for 2 years. 
Councillor McKenzie thank Mr Anderson and his team adding his support for a
public consultation. 
Councillor Curran asked how the Scottish Government decision affect the house
building. 
Mr Anderson replied that there is already an overspend position for the end of the
year. We can however go back to the Scottish Government in light of any rent
freeze anticipate an increase in social housing demand. 
Councillor Smaill suggested that the 4.1% rent increase anticipate should be made
clearer. 
Mr Anderson agreed to incorporate that into the public consultation Page 14 of 164

Page 15

11 
Councillor McKenzie proposed the report
Councillor Curran seconded 
Decision
Agreed
Action
Clearly communicate the anticipated 4.1% rent increase within the Public
Consultation – Mr Anderson 
Report
No.
Report Title Report by:
8.7 Midlothian Council’s Housing
Services Assurance Statement 2022, 
Report
Executive Director Place
Outline of report and summary of discussion
To comply with the Scottish Housing Regulator’s (SHR) Regulatory Framework,
the Council must approve and submit an Annual Assurance Statement (AAS) each
year providing assurance that it is meeting legislative and regulatory standards for
social housing in Scotland.  
This report explains the Regulatory Framework and appends an Assurance
Statement for approval by Council. The AAS confirms the Council fully meets the
SHR required standard and outcomes.  
Following Council approval, the AAS will be published on the SHR and Midlothian
Council’s websites. 
Recommendations –
Council is recommended to approve the Housing Services Annual Assurance
Statement 2022, as attached at Appendix B, for submission to the Scottish
Housing Regulator by 31 October, 2022. 
Mr Anderson introduced the report and detailed key areas within the paper. 
Councillor Curran proposed the Report
Councillor Parry seconded
Decision
Agreed 
Action
None 
12.29 pm Provost announced a short recess 
12.45 pm All returned 
Report
No.
Report Title Report by:
Page 15 of 164

Page 16

12
8.8 Mayfield Town Centre Regeneration
Close-out Report on Community
Led Project
Head of Development
Outline of report and summary of discussion
The purpose of this report is to provide Council with a closing out report on the
Mayfield In It Together (IIT) project following conclusion of the Mayfield Town
Centre Masterplan, as agreed in the October 2019 report to Council. 
Recommendations – 
a) Note the progress made in identifying the community’s aspirations for
improvements at Mayfield Town Centre and the significant achievement of the In It
Together partnership who delivered this project;
b) Note the content of the Masterplan and areas for improvement identified in
the Mayfield Town Centre as a long term ambition by the local community and
partners to deliver; and
c) Note the proposed next steps:
• In It Together will continue to lead on the delivery of the project, taking steps
to resource a development manager to develop a robust business case that
reflects current priorities and context.
• The In It Together group will continue to work with different partners,
including Midlothian Council, setting out clear parameters and expectations
in relation to their roles and responsibilities from the outset.
• Midlothian Council will seek to develop a Place Brief as part of the Strategic
Infrastructure Investment Framework, working with local partners to
establish priorities in the local area. 
Ms Clandillon spoked to the report and the aspects required to finish the current
phase, noting the long term framework is for regeneration of the town centre using
a cluster model. She asked members to acknowledge the significant progress and
achievements made. 
Responding to a question concerning timescale Ms Clandillon said the ambition
and scale is significant, emphasizes is on key areas that would make an impact
but a further year would be required of further project development. 
Members welcomed the paper and thanked all involved for their efforts. 
Councillor Bowen proposed the report
Councillor McKenzie seconded 
Decision
Agreed
Action
None   
Report
No.
Report Title Report by:
8.9 Vogrie Country Park – feasibility
update Report
Head of Development
Outline of report and summary of discussion
A report was requested form elected members on the current status of Vogrie
Country Park and to provide answers to the following: Page 16 of 164

Page 17

13 
• How many user groups utilise Vogrie Country Park?
• How much it costs Midlothian Council to run Vogrie Country Park year on
year and what income is generated by the Park?
• What are the locations of the Core Paths around Vogrie?
• What is the estimated time for progressing any emerging investment
strategy? 
Recommendations – 
• Note the findings of the User Survey and the contents of this report;
• Approve the use of £40,000 of Blueprint funding (in addition to the £10,000
previously allocated to Vogrie) to commission a landscape and access
strategy for the site, noting that officers will ensure that the redirection of
Blueprint Grant (£50,000) to fund this has the full written consent of Scottish
Ministers prior to any expenditure being incurred;
• Approve the preparation of an updated Management Plan by Midlothian
Council, which would be resourced internally by Land and Countryside
team.
• Approve the allocation of £200,000 of the 2022/23 Place Based Investment
Fund towards the upgrade of toilet facilities within Vogrie, as an immediate
action in response to the User Survey;
• Support the continued exploration of revenue streams that are
complementary to an overall vision and ambition to utilise the asset of
Vogrie Country Park. 
Ms Clandillon noted that the completed report follows work completed in 2018,
adding a wide range of groups currently use the park and asked members to
consider the long term recommendations to improve the facilities included within
the report. 
Members thanked all who took part in the consultation adding that they would like
to see further ambitious proposals in future. Also members noted that there are
current issues with parking also that more visitors are likely to increase pressure
on the residents of Dewarton adjacent to the park. 
Ms Clandillon confirmed the parking issue has been noted and will be addressed
in the future. 
Councillor Parry moved to accept all recommendations 
Councillor Scott seconded 
Decision
Agreed
Action
None 
Report
No.
Report Title Report by:
8.10 Brexit and COVID-19 – An
Economic Assessment for
Midlothian Council, Report
Chief Officer Place
Page 17 of 164

Page 18

14
Outline of report and summary of discussion
In March 2022, Midlothian Council commissioned Ekosgen to undertake an analysis
of the economic impact of Brexit and the COVID-19 pandemic on Midlothian’s
economy.   
Ekosgen’s report (Appendix B) presents an analysis of challenges, opportunities and
strategic priorities that will enable the Council, along with its strategic partners, to
respond to the impacted economic landscape through a refreshed economic
strategy. 
This report summarises the key findings and the strategic priorities that are
recommended to be taken forward through a new Economic Strategy. 
Recommendations – 
• Note the contents of the Economic Assessment;
• Endorse the ten strategic priorities listed within the Economic Assessment
and summarised in Sections 3.9 to 3.18 of the report;
• Approve the creation of a new Economic Strategy for Midlothian, to be
presented to Council for approval in early 2023. 
Mr Oliver highlighted aspects of the reports analysis on the much changed
circumstances to allow future planning. A further report will be presented in 2023. 
Councillor Imrie pointed out that the report endorses the actions we would need to
take anyway 
Members discussed the issues and factors that affect one area of Midlothian but not
another noting that some business models within the county are more resilient than
others, the changing face of town centres being one example. In general members
welcomed the report and noted the challenging funding situation and how funds are
allocated. 
Mr Oliver responded that Midlothian is made aware of what funding is available and
in certain circumstances have time to present projects making them ready for
submission.  Applications for levelling up and Prosperity funding were still awaiting
a decision. The strategy going forward will include all possible funding options. 
Councillor McKenzie asked if the weaker £ affects the Council? 
Mr Fairley confirmed the Council doesn’t have a huge exposure to financial
fluctuations but simply put, money doesn’t go as far as it did before. 
Councillor Parry moved to accept all recommendations 
Councillor Cassidy seconded
Decision
Agreed
Action
None 
Report
No.
Report Title Report by: Page 18 of 164

Page 19

15
8.11 Short-Terms Let Licensing Policy
for Midlothian Council for
Consideration and Adoption Report  
Chief Officer Place
Outline of report and summary of discussion
The report provides details of the attached Short-term Let Licensing Policy for
Midlothian Council. It provides members with information on the new powers which
have been given to local authorities to regulate short term lets in the form of a
licensing scheme. An appended report details the public consultation which took
place regarding this policy, the responses received and the action taken as a result. 
Recommendation – 
• Note the terms of this report; and
• Adopt the Short-term Lets Licensing Policy for Midlothian Council 
Mr Oliver presented the report to members 
Councillor McKenzie moved to accept the report
Councillor Virgo seconded
Decision
Agreed
Action
All to Note 
Report
No.
Report Title Report by:
8.12 Voluntary Community Asset
Transfer, Report
Executive Director Place
Outline of report and summary of discussion
The purpose of the report is to advise Council that CATs may be achieved by
agreement between the Council and community groups without requiring such
groups to submit a formal application in terms of the Community Empowerment
(Scotland) Act 2015, subject to compliance with the Disposal of Land by Local
Authorities (Scotland) Regulations 2010 and related Scottish Government guidance. 
A similar report was considered by the CAT Committee at its meeting of 24 February
2022 when it was agreed to refer the matter to Council for further consideration. This
report includes revisions which were suggested by the CAT Committee. 
Recommendations – 
(a) Note the terms of this report; and
(b) Approve a revision to the current practice for Community Asset Transfers
(CATs) and allow a voluntary approach to be adopted, where appropriate, as an
alternative to the formal process under the Community Empowerment (Scotland)
Act 2015. 
Mr Anderson spoke to the report in particular Section 3, outlining the existing
process of changing/ varying the scheme. Mr Anderson confirmed that the statutory
process is being used. 
Councillor Parry moved to the report
Councillor Milligan seconded 
Decision Page 19 of 164

Page 20

16
Agreed
Action
None 
Report
No.
Report Title Report by:
8.13 Scottish Government Funding for
Children’s Outdoor Play
Refurbishment of Play Areas,
Report
Chief Officer Place
Outline of report and summary of discussion
The purpose of this report is to advise on the proposed expenditure of £0.097 million
across the council play estate to replace equipment that has either been removed
or requires replacement along with appropriate safety surfacing and where required
an access path to the refurbished play area in accordance with equalities legislation. 
Recommendations – 
• A capital expenditure budget of £0.097 million in the General Services Capital
Plan, to be fully phased in 2022/23 and to be fully financed by£0.097 million of
Scottish Government Capital Grant funding;
• Subject to Council approval, the proposal to install the outdoor play
equipment be progressed. 
Mr Oliver introduced the report and referred to key areas contained within the
document. 
Councillor Cassidy welcomed the report
Councillor Winchester stipulate the paths must be wheelchair accessible 
Councillor Parry moved to accept the report
Councillor Scott seconded 
Decision
Agreed
Action
None 
Report
No.
Report Title Report by:
8.14 Audit Committee – Independent
Chair & Independent Non-Voting
Member Report
Executive Director Place
Outline of report and summary of discussion
The council invited applications to the posts of Independent Chair and Independent
Non-Voting Member of the Audit Committee. The roles are voluntary but expenses
are paid. The appointments are at the council’s discretion and are expected to run
until the council elections in May 2027. 
Recommendation – 
Council is to note that no applications or notes of interest were  received for the
recently advertised roles of the Independent  Chair and Independent Non-Voting
Page 20 of 164

Page 21

17
Member of the Audit Committee and is recommended to consider the alternative
options available to; 
i) re-advertise the roles across an additional range of recruitment sources; or
ii) continue with an elected member chair; or to
iii) Address the matter in the Standing Orders review to potentially combine the
committee remit into another relevant wider scope committee ie. a prospective Audit,
Risk & Performance Review Committee. 
Mr Anderson referred to the report noting the background and the current situation
contained within the paper and that no applications for the position were received. 
Councillor Parry moved recommendation 2
Councillor Cassidy seconded 
Councillor Milligan queried whether a substitute council member could hold the
position full time. 
Mr Turpie responded that the governance could not be changed and that the current
situation is just for the time being.
Decision
Agreed – Recommendation 2 
Action
None 
Report
No.
Report Title Report by:
8.15 Pupil Admissions Policy Update
Report
Executive Director Children,
Young People &
Partnerships
Outline of report and summary of discussion
Following the conclusion of the 2022/23 P1 and S1 intake, the Children, Young
People and Partnerships Business Support Team have been working to review,
update and improve the admissions process.  This report provides the updated
revisions to the admissions policy. The main areas for approval are:
• The inclusion of the explanation around reserved places.
• The process for late placing requests, including those with exceptional
circumstances.
• An explanation of what constitutes exceptional circumstances and how this
is incorporated into the waiting list criteria. 
Recommendation – 
This report seeks Council approval to the revisions made to the Admission to
Primary and Secondary Schools policy 
Ms Robertson introduced the report highlighting key areas including how gratefully
she was for the feedback from Parents and Elected Members. 
Councillor Scott moved to accept the report
Councillor Virgo seconded
Decision
Agreed
Action Page 21 of 164

Page 22

18
None 
Report
No.
Report Title Report by:
8.16 Appointment of Member to
Champion the White Ribbon
Campaign Report 
Executive Director Place
Outline of report and summary of discussion
Midlothian Council has previously committed to the White Ribbon    Campaign
towards Men working to end Violence Against Women.   White Ribbon Day is on
25th November, 2022 which correlates with the start of the 16 Days of Action. A
programme being developed locally    alongside the Violence Against Women and
Girls Officer in the    Midlothian & East Lothian Public Protection Team.   
Recommendation – 
The Council is invited to endorse a ‘champion’ as part of previously agreeing to
support the White Ribbon Campaign initiative and it is recommended that role is
assigned to Councillor Connor McManus to align with his portfolio as Equalities
champion. 
Mr Anderson spoke to the report noting Midlothian Council’s long standing
involvement and contribution. 
Councillor Winchester spoke about how pleased she was that Midlothian Council
was continuing its involvement, she added that although this group focused on
violence toward women al should note there are cases of violence towards men
also. 
Members spoke of their ongoing commitment to this campaign and their unwavering
support. 
Councillor Parry nominated Councillor McManus 
Councillor Curran seconded  
Decision
Councillor McManus Nominated 
Action
None 
The Provost joined Dr Vickers in acknowledging Gary Fairley (Chief Officer
Corporate Solutions) , who was attending his final Midlothian Council meeting, she
wished him well in future endeavours and thank his long services and loyalty , all
members echoed those sentiments. 
Public Council Meeting ended at 13.45 pm 
___________________________________________________________________
Date of Next Meeting Tuesday 15 November 2022 at 11am 
Page 22 of 164

Page 23

Minute of Meeting 
Special Midlothian Council 
Date Time Venue
27 September 2022 09.30 am via MS Teams 
Present: 
Provost McCall (Chair) Depute Provost McManus
Councillor Parry – Council Leader Councillor Cassidy  – Depute Council
Leader
Councillor McEwan Councillor Bowen
Councillor Milligan Councillor McKenzie
Councillor Smaill Councillor Pottinger (Private  Section
Only)
Councillor Scott Councillor Virgo
Councillor Winchester Councillor Curran
Councillor Russell 
In attendance: 
Dr Grace Vickers, Chief Executive  Morag Barrow, Joint Director Health and
Social Care
Kevin Anderson , Executive Director
Place
Alan Turpie, Legal and Governance
Manager/Monitoring Officer
Gary Fairley, Chief Officer Corporate
Solutions
Sinead Urquhart Executive Business
Manager
Marc Bedwell Executive Business
Manager
Nick Clater, Head of Adult & Social Care
David Gladwin Financial Services
Manager
Myra Forsyth Quality and Scrutiny
Manager
Saty Kaur, Executive Business
Manager
Marco Reece-Heel Business Analyst
Ross Neill, Democratic Services Team
Leader
Mike Broadway, Democratic Services
Officer     
Page 23 of 164

Page 24

2 
1.  Welcome and Apologies for Absence 
The Provost welcomed everyone to the meeting reminding all that it was a public
meeting being webcast live. 
Apologies for absence were intimated on behalf of Councillor Alexander and Milligan
also Mrs Lawrie & Mrs Morton Religious Representatives to the Cabinet. 
2. Order of Business 
The Provost advised the order of business as per agenda 
3. Declarations of interest 
None 
4. Deputations 
None received. 
5. Minute of Previous Meeting 
None 
6. Question to the Leader of the Council 
None 
7. Notices of Motion 
None 
8. Reports 
Report
No.
Report Title Report by:
8.1 Hybrid Meetings of Council and its
Committees
Executive Director Place
Outline of report and summary of discussion 
The Cross Party Working Group meeting on 31 August 2022 considered Hybrid
Meetings, combining in person and virtual participants. In discussing the matters
members agreed that they would prefer to return to in-person meetings for certain
Committee meetings, in particular Council meetings, and discussed the possibility
of having the October Council Meeting in person.   
Also discussed was the governance around any decision to have the Council
meeting of 4 October in person/hybrid with advice that this required a decision of
Council, and therefore a Special Council prior to 4 October, 2022.   
Recommendation – 
Page 24 of 164

Page 25

3
Council is advised that the “Short Life Working Group – Hybrid Meetings of Council
and its Committees” recommends to Council that the previous default Remote
Working decision for elected members governance meetings, implemented from
June 2020, is now revised to permit an in-person meeting of Council on 4 October,
2022. 
Mr Anderson introduced the report and outlined the recommendations noting this
followed on from reports to BTSG and the options available as per the cross
working party group. 
Councillor Parry moved the report and its recommendations adding, for the record
her thanks Councillors McEwan and Virgo, thanking all parties concerned with
bring this report to Council. She added this facility could be used by other
organisations. 
Councillor Smaill also thanked the cross party group and its work. He asked if the
expense could capitalised. 
Mr Fairley confirmed the capital expenditure would be paid over a short period of
time from the digital budget so no additional costs, it however would limit future
digital projects. Any revenue costs would come from the revenue account. 
Councillor Curran was happy to support the report. 
Mr Anderson cautioned that Hybrid working would not be in place for Midlothian
Councils meeting on the 4th of October, it would need to be either in person or
virtual 
Councillor Parry suggested this facility would most likely be used for selected
public facing meetings, other meetings would best be served by using the virtual
MS team’s model. 
Councillor Cassidy seconded the report, urging everyone, where possible, to
attend on the 4th October. 
Agreed unanimously 
Decision
Agreed
Action
All to Note 
Public Council Meeting ended at 9.45 am 
The meeting concluded at 9.50 am
___________________________________________________________________
Date of Next Meeting 4 October 2022 
Page 25 of 164

Page 26

Page 26 of 164

Page 27

Midlothian Council Minute Volume 
Presented to the Meeting
of Midlothian Council
on Tuesday, 15 November 2022 
Page 27 of 164

Page 28

1           Minutes of Meetings submitted for Approval 
MINUTE Special  Midlothian Council for Approval  27 September
2022
3 - 6 
MINUTE Midlothian Council for 4 October 2022 7 - 24 
2           Minutes of Meetings submitted for Consideration 
Approved Minutes for Noting, Information and Consideration of
any recommendations contained therein 
Audit Minute of 29 June 2022 25 - 34 
Minute of Cabinet - 06 September 2022 35 - 42 
Local Review Body Minute of Meeting 13 September 2022 43 - 48 
Local Review Body Minute of Special Meeting 26 September 2022 49 - 54 
Performance Review and Scrutiny Minute of Meeting 21 June 2022 55 - 62 
Planning Minute of Meeting of 30 August 2022 63 - 70 
Police Fire and Rescue Board Minute of Meeting 30 May 2022 71 - 78 
PRIVATE Minute of BTSG 5 Sept 2022 
PRIVATE Minute of Special BTSG 22 Sept 2022 
3          Minutes of Meetings submitted for Information 
Minute for Information 
Minutes MIJB of 29 June 2022 Audit & Risk 79 - 84 
MIJB Minutes 25 August 2022 85 - 94 
Minutes of the Special MIJB held on 15 September 2022 95 - 100 
Page 28 of 164

Page 29

Action Log 
No Subject Date Action Action Owner Expected
completion
date
Comments
1 Minute action -
prospective crematorium
development.
16/11/2021 Scope potential suitable sites
for prospective crematorium
development.
Chief Officer
Place
February 2023 Report scheduled for
February 2023 Council.
2 Motion Amendment –
Loanhead  Football
Club
16/11/2021 Update the Sports Needs
Assessment from 2016 and
report to future council
meeting
Head of Adult
Social Care/
Sport & Leisure
Manager 
December 2022 Slight delay in report due
to lack of response from
some clubs. This issue
has been proactively
followed up and
anticipated that report will
be available at the end of
year.
3 Motion - Infrastructure  14/12/2021 Report to Council  Strategic
Investment Framework 
Executive
Director Place
TBC Strategic Infrastructure
Investment Framework 2nd
stage review has
commenced and full
report shall be presented
to Council when
completed and available.
4 Minute Action - CCTV 14/12/2021 To Provide a Report outlining
an expansion of sites for
CCTV
Chief Officer
Place
February  2023 Phase 1 Procurement &
progressed. Phase 2
expansion needs further
consideration with a report
anticipated for February
Midlothian Council 
15 November  2022
Item 5.5 
Page 29 of 164

Page 30

No Subject Date Action Action Owner Expected
completion
date
Comments
2023 Council
5 Minute Action –
Improving Energy
efficiency by tackling
Dampness,
Condensation and
improving ventilation 
15/02/2022 Provide a Report to Council 
Additional Report –
Update on Current Housing
Stock that will not meet
Energy Efficiency Targets
Chief Officer
Place
February 2023 Work progressing.  
EESH2 Report scheduled
for February 2023 Council.
6 Arm’s Length Company
to Manage Industrial
Sites in Midlothian 
28/06/2022 Explore and outline process
for creating an Arm’s length
company 
Head of
Development
December 2022 Report scheduled for
December Council
7 Risk Management
Strategy Report
23/08/2022 Briefing for Councillors Virgo &
McKenzie  Executive
Director Place
30 September
2022
Completed. Meeting
scheduled and further
follow with Chief Officer
Place 
8 Wheelchair Accessible
targets 
23/08/2022 Opportunities that would
increase targets 
Executive
Director Place
November 2022 Completed
Added into the SHIP
report in November 2022
in opportunities for other
developments as they
arise. Also scoped into the
Local Development
Review once commenced. 
Page 30 of 164

Page 31

No Subject Date Action Action Owner Expected
completion
date
Comments
9 Briefing - Trauma
Informed practice
23/08/2022 Members Briefing on Trauma
Practice and Mental Health
First Aid 
Head of Adult
Services
TBC Trauma training will be
arranged when Trauma
Lead is in post
(recruitment currently in
process). Mental Health
Training can be provided
by Health in Mid who can
design bespoke half day
training for elected
members. Confirmation of
date required and then
can be arranged with
Health in Mind.
10 Quality Scoping Report    23/08/2022 On the quality of builds over
the last 10 years comparing
all tendered projects
including with those of HUB
SE
Executive
Director Place
TBC Peer Review of Hub SE
tender process completed.
Separate commission
procured for wider scope
schools review since
commenced.
11 5 year Strategic Plan 04/10/2022 5 year Strategic Plan passed to
BTSG for further work and a re-
write 
Executive
Director Place
November 2022 Completed. Included in
November 2022 Council
Agenda.
12 Midlothian Cares Practical
Support Measures
Identified Report
04/10/2022   Audit of funding distribution
report 
Strategic Service
Re-Design
Manager
November 2022 
Page 31 of 164

Page 32

No Subject Date Action Action Owner Expected
completion
date
Comments
13 Housing Revenue Account
– Rent Setting Strategy
2023-24 - 2025-26
04/10/2022 Clearly communicate the
anticipated 4.1% rent increase
within the Public Consultation 
Executive
Director Place
November 2022 Public consultation
commenced in November
2022 and results report to
Council in February 2023.
15       
Page 32 of 164

Page 33

Midlothian Council
15 November 2022
Item 8.1 
Draft Midlothian Council Strategic Plan 2023 - 2028 
Report by Dr Grace Vickers, Chief Executive 
Report for Decision 
1 Recommendations 
1.1 It is recommended that Council approves the appended Draft
Draft Midlothian Council Strategic Plan 2023 – 2028 for consultation. 
1.2 Following approval the consultation and engagement with Midlothian 
Communities and stakeholders will take place during the Winter 2022
period. The consultation outcomes and recommended options will be
reported back to Council in February 2023. 
2 Purpose of Report 
2.1 This report presents strategic options for future service aims building
on the learning and new ways of working that were adopted during the
pandemic period, and to renew our focus on delivering our key
priorities at the most local level possible. 
2.2      Rooted in the creation of a wellbeing economy, the vision of our new 5
year strategy is committed to reducing inequalities in health outcomes,
learning outcomes and economic circumstances while addressing the
health of our planet. 
Date: 4 November 2022
Report Contact:
Name : Kevin Anderson, Executive Director, Place 
Tel No : 0131 271 3102
kevin.anderson@midlothian.gov.uk 
Page 33 of 164

Page 34

2 
3         Background 
3.1 A wellbeing economy is an economy which puts people and the planet
first. Midlothian aspires to be a socially, economically, and ecologically
sustainable community by 2030. This is particularly critical as we
respond to the ongoing Cost of Living Crisis. 
3.2 Responding to the current cost of living crisis with the available
resources, we aim to provide the right support at the right time to our
communities through our strategic goals; 
3.3 A wellbeing economy where our people and the environment flourish,
as wellbeing economy which puts people and the planet first.
Midlothian aspires to be a socially, economically, and ecologically
sustainable community by 2030. This is particularly critical as we
respond to the ongoing Cost of Living Crisis. 
3.4 Fostering empowered, inclusive, resilient and safe communities. The
principle encourages and enables flexibility to respond to local issues
and circumstances in different places. 
3.5 Supporting individuals and communities to be the best they can be.
This will be achieved through a nurturing, respectful and collaborative
approach that promotes wellbeing, equity, inclusion and lifelong
learning. 
3.6 Transforming health and social care. The Midlothian Health and Social
Care Partnership brings together parts of Midlothian Council and NHS
Lothian to help people in Midlothian live well and get support when they
need it -from care homes to care at home, voluntary organisations to
vaccinations. 
3.7 Accelerating inclusive growth. As Scotland’s fastest growing local
authority area, Midlothian has a number of significant challenges and
many opportunities which lie ahead. It is critical to deliver investment in
community infrastructure, such as housing, the learning estate,
economic investment and green infrastructure, in the right place at the
right time. We will continue to bid for investment opportunities to help
our communities live well, live locally and prosper. 
3.8 The Council declared a climate emergency in December 2019 and
stated its ambition to achieve Net Zero Carbon status by 2030. New
emissions legislation (October 2019) commits the Scottish Government
to achieving Net Zero Carbon status by 2045. This puts into context the
scale of the challenge facing the Council and the transformational
nature of the change required to achieve our 2030 target. 
4 Report Implications (Resource, Digital and Risk) 
4.1 Resource
Page 34 of 164

Page 35

3 
Good governance requires that organisation structures are
kept under review to ensure that they are fit for purpose, that
they are congruent with the priorities set out in the Strategic
Plan and the actions contained in the Council’s Medium Term
Financial Strategy and are designed to support the
achievement of long term financial sustainability.   
4.2 Digital 
There are no current digital implications. 
4.3 Risk 
There are no current risk implications. 
4.4 Ensuring Equalities (if required a separate IIA must be completed) 
An IIA is not required at this time but shall be provided in the post
consultation reporting process. 
4.5 Additional Report Implications (See Appendix A) 
See Appendix A 
Appendices 
Appendix A – Additional Report Implications
Appendix B – Background information/Links 
Page 35 of 164

Page 36

4
APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
We manage all aspects of our business so that customers receive
services that provide continually improving value for the charges they
pay. 
A.5 Involving Communities and Other Stakeholders 
A full consultation will be carried out with Midlothian Communities and
stakeholders. 
A.6 Impact on Performance and Outcomes 
The Draft Strategy options support key objectives to improving and
invest in council services. 
A.7 Adopting a Preventative Approach 
The Draft Strategy aims to reduce inequality, learning, health and
education outcomes. 
A.8 Supporting Sustainable Development 
Page 36 of 164

Page 37

5
The Draft Strategy aims for ecologically and socially sustainable
growth. 
Page 37 of 164

Page 38

6 
APPENDIX B 
Background Papers/Resource Links (insert applicable papers/links) 
Draft Midlothian Council Strategic Plan 2023 - 2028 
Page 38 of 164

Page 39

Midlothian Council
Strategic Plan 2023-2028
A great, green place to grow:
where people and the environment flourish
Page 39 of 164

Page 40

2
The last two years have brought significant and
unprecedented challenge to our communities as we
responded to the COVID-19 pandemic. As we move
into a new post-pandemic world, we are committed to
building on the learning and new ways of working that
were adopted during this period, and renew our focus
on delivering our key priorities at the most local level
possible.
Rooted in the creation of a wellbeing economy, the
vision of  our new 5 year strategy is committed to
reducing inequalities in health outcomes, learning
outcomes and economic circumstances while
addressing the health of our planet.
Introduction
Page 40 of 164

Page 41

Page 41 of 164

Page 42

4
Strategic goal: a wellbeing economy where our people and the environment flourish
A wellbeing economy is an economy which puts people and the
planet first. Midlothian aspires to be a socially, economically,
and ecologically sustainable community by 2030.  This is
particularly critical as we respond to the ongoing Cost of Living
Crisis.
This strategic goal links with the aim of the United Nations
Sustainable Development Goals to promote prosperity while
protecting the planet (as shown below).
Our key objectives include:
• Responding on the ground to the current cost of living crisis, within the
resources available, we aim toprovide the right support at the right time
through the creation of multi-disciplinary teams located in our new local ‘Live
Well’ hubs. These hubs would be based in a central point within targeted
communities and would help our citizens with the services they need,
whether it be issues relating to food and fuel poverty, housing or wellbeing
support and much more.
v
• Reducing inequality in learning, health and education outcomes.
v
• Adopting a Participatory Budgeting (PB) approach in which citizens decide
howto spend part of the public budget, within the fiscal resources available.
We aim to use PB as a tool for community empowerment and to widen
community participation. Adopting a PB approach will help deliver on the
outcomes in Scotland’s National Performance Frameworkthat 'we live in
communities that are inclusive, empowered, resilient and safe' and 'we tackle
poverty by sharing opportunities, wealth and power more equally’.
• Achieving carbon neutrality by 2030.
v
• Increasing wellbeing and prosperity. In Midlothian this means ecologically and
socially sustainable economic growth, high levels of employment,
championing the need for sustainable public finances, and stability in the
economy, all of which help avoid unforeseen negative impacts on people’s
wellbeing.
Page 42 of 164

Page 43

5
Strategic goal: a wellbeing economy where our people and the environment flourish
Over the next 5 years we aim to:
• Grow our ‘Live Well’ hubs where multi-disciplinary teams
would provide the right support at the right time within the
resources available. These hubs would be based in a central
point within our communities and would help our citizens
with the services they need
• v
• Reduce inequalities in educational outcomes, health
outcomes and economic circumstances
v
• Adopt a Participatory Budgeting (PB) approach in which
citizens decide how to spend part of the public budget within
the fiscal resources available.
V
• Accelerate the implementation of the Climate Change
Strategy
• Support economic growth and resilience by attracting new
investment and enable existing local businesses to survive,
grow and prosper
• Promote our towns, villages and high streets as attractive,
safe, digitally connected and healthy centres for business,
homes, visitors, services and facilities, creating prosperity
with support for regeneration within the fiscal resources
available
v
• Work to equip people with the skills they need to enter, re-
skill and progress in the labour market and meet the
demands of the local economy, with a focus on
apprenticeships and growing our own talent
v
• Work with our businesses to adapt, diversify, develop and
grow and promote local communities and workers to have
fairer jobs, pay and opportunities to train and progress
v
• Encourage people to support our businesses by spending
locally and promoting the Midlothian brand.
Page 43 of 164

Page 44

6
Fostering empowered, inclusive, resilient and safe communities
In line with the Place Principlewe are committed to
delivering services at a local level fostering
communities that are inclusive, empowered,
resilient and safe. Due to the limited resources
available we will need to work differently and
adopting the Place Principle will help promote a
shared understanding of place, taking a more
collaborative approach to a place’s services and
assets to achieve better outcomes for people and
communities.
The principle encourages and enables flexibility to
respond to local issues and circumstances in
different places.  Through the Local by Default driver
for change, we will aim to implement the Hub and
Spoke model for locality based service provision and
‘Live well’ one stop shops – which will bring our
services to communities so that the right support
can be delivered at the right time within the
resources available.
Place is where people, location and resources
combine to create a sense of identity and purpose,
and are at the heart of addressing the needs and
realising the full potential of communities. Places
are shaped by the way resources, services and
assets are directed and used by the people who live
in and invest in them.
A focus on Place will also deliver a more joined-up,
collaborative, and participative approach to
services, land and buildings, across all sectors within
a place, enabling better outcomes for everyone and
increased opportunities for people and communities
to shape their own lives.
Page 44 of 164

Page 45

7
Fostering empowered, inclusive, resilient and safe communities
Over the next 5 years we aim to:
• Modernise our Neighbourhood Services and aim to deliver
sustainably within the resources available
• Deliver the Hub & Spoke model (building and estate
rationalisation) and locality based service delivery including
the ‘one stop shop’ approach
• Empower our communities so that we co-create services
together
• Implement a participatory approach to the identification of
key priorities for Place to ensure that our communities are
inclusive empowered, resilient and safe.
v
v
• Create a comprehensive asset management programme to
include property, roads and fleet, providing more efficient
and responsive services for our communities
• Bid for grants so that we can continue to invest in our green
and open spaces, achieve and maintain green flag awards and
maximise the use of the public realm
• Facilitate modal shift, reducing the use of cars and promoting
more active travel options to, from and around the county
• Develop our own people and their careers in Midlothian
Council
v
v
Page 45 of 164

Page 46

8
Supporting individuals and communities to be the best they can be
Our agreed vision is that:
All children, young people, adults and
communities in Midlothian are supported to
be the best they can be. This will be achieved
through a nurturing, respectful and
collaborative approach that promotes
wellbeing, equity, inclusion and lifelong
learning.
The challenges for Midlothian continue to grow with
the impact of COVID-19 and our recovery out of the
pandemic, the growing and ageing population and
the increasing demand for services that this brings.
Population growth over the next 10 to 15 years will
see Midlothian remain the fastest growing Council in
Scotland. A 0-15 population increase is projected at
20% and 75+ population increase is projected at
100% between 2014 and 2039.
The pace of growth demands additional capacity
within the learning estate to cope with the
projected increase in pupil and pre-school numbers
and the associated children’s, education and
community services to support this growth. As part
of work to address the issue of significant
population growth and demographic changes within
Midlothian, the key drivers of change in delivery of
sustainable and transformational services and
regeneration of our communities must be viewed
holistically.
Page 46 of 164

Page 47

9
Supporting individuals and communities to be the best they can be
Over the next 5 years we aim to:
• Improve children and young people’s attainment, particularly in
literacy and numeracy
• Reduce the attainment gap between the most and least
disadvantaged children and young people
• Improve attainment of children and young people who require
additional learning support, including young carers and looked after
children
• Improve employability skills and sustained positive school leaver
destinations for all young people
• Improve employability skills and opportunities, particularly within
known skill gap areas for adults
• Reduce inequalities in learning, economic circumstances and health
through local and inclusive actions that meet our commitment to The
Promise
• Improve the physical, mental health and wellbeing of children,
prioritising care-experienced and looked-after children
v
v
• Mitigate against the impact of poverty and disadvantage across our
communities
• Improve support to children and young people affected by domestic
abuse, parental alcohol or drug misuse
• Within the resources available, expand early years services and
improve services for children and families to ensure the best start in
life
• Support young carers and give them the help they need
• Continue to promote the responsibilities of the Council as a Corporate
Parent, including its responsibility for the wellbeing of those in its care
• Develop new family services to improve outcomes for children and
families that identifies, understands and responds to need at the
earliest opportunity in line with our approach to Getting It Right for
Every Child
• Place the human rights and needs of every child and young person at
the centre of CYPP service delivery
• Support our children, young people and communities to develop and
engage with activities which reduce carbon emissions and support
climate change
v
Page 47 of 164

Page 48

10
Transforming health and social care
The Midlothian Health and Social Care
Partnership brings together parts of Midlothian
Council and NHS Lothian to help people in
Midlothian live well and get support when they
need it - from care homes to care at home, 
voluntary organisations to vaccinations.
We aim to:
• Improve the quality of health and social care
servicesand achieve the 9 national health and
wellbeing outcomes;
• Change how health and social care is
delivered to better understand and meet the
needs of the increasing number of people with
long term health conditions, with complex
needs and those who need support, working
with people as partners in their health and
social care.
• Provide more support, treatment, and care
for people in their homes, communities, or a
homely settingrather than in hospitals
Page 48 of 164

Page 49

11
Accelerating inclusive growth
As Scotland’s fastest growing local authority
area, Midlothian has a number of significant
challenges and many opportunities which lie
ahead. It is critical to deliver investment in
community infrastructure, such as housing, the
learning estate, economic investment and green
infrastructure, in the right place at the right
time. We will continue to bid for investment
opportunities to help our communities live
well, live locally and prosper.
How we invest in community infrastructure
must also respond to changes in our working
and living patterns so that we can retain the
best practice identified during the COVID-19
pandemic. This will mean  moving from centrally
delivered to local solutions so our communities
can readily access the services they need.
Capital investment is also an opportunity to support our
local economy through job creation and skills
enhancement. This is particularly the case as we move
to ensure that our new and existing property assets
contribute to Midlothian Council’s commitment to being
net zero by 2030. We must ensure investment in our
community infrastructure delivers jobs that benefit
those living locally and supports our transition to a
green economy. Improving our skills landscape and
developing our people to meet the future economic
needs remains a high priority.
As a growing Council, we have the opportunity to
transform parts of Midlothian in a way that reflects how
we live now. Within the fiscal resources available, we
will aim to invest in community infrastructure with a
focus on place-making, reducing inequalities, improving
economic opportunities and improving education and
health and wellbeing outcomes.Page 49 of 164

Page 50

12
Accelerating inclusive growth
Over the next 5 years we aim to:
• Meet local housing need with 25% of new homes built
to be affordable in perpetuity and expand Council
house building.
• Invest in existing Council housing to make them more
energy efficient and affordable to live in for tenants.
• Within the capital resources available, continue to
invest in our learning estate to meet learners’ needs,
raise attainment rates and give our young people a
great start towards rewarding careers.
• Bid for funding to help enhance and regenerate key
town centres in Midlothian
• Ensure capital investment generates employment
opportunities locally and delivers community benefits.
v
v
• Create new Council owned employment space to
support business.
• Bid for funding so that we can invest in local public
transport infrastructure and active travel networks to
make it easier to travel sustainably using available
resources.
• Through the City Deal, deliver transport network
solutions to enhance connectivity across the City
Region.
• Protect and enhance the natural and built heritage of
Midlothian to support our communities’ health and
wellbeing and attract visitors to the area.
v
v
Page 50 of 164

Page 51

13
Being carbon neutral by 2030
The Council declared a climate emergency in
December 2019 and stated its ambition to achieve Net
Zero Carbon status by 2030.
The Covid-19 pandemic necessitated an emergency
response from the Council. It has brought about
substantial organisational change across the Council in
a very short period of time.
The Council's "Route Map" out of Covid-19 identifies
"Digital by Default" as one of its key priorities. It
supports continuing the practice of working from
home (introduced because of the pandemic) and
promotes a carbon neutral approach to the workplace.
New emissions legislation (October 2019) commits the
Scottish Government to achieving Net Zero Carbon
status by 2045. This puts into context the scale of the
challenge facing the Council and the transformational
nature of the change required to achieve our 2030
target.
In light of the climate emergency, the Single
Midlothian Plan has adopted a new sustainable
growth outcome to be an ‘earth friendly’ partnership,
resource aware and committed to working to support
Scotland’s net zero carbon ambition by 2045 (2030 in
Midlothian) and prioritises the following climate
change specific actions:
• a Climate Emergency group in the Midlothian
Community Planning Partnership;
• a Sustainable Growth Agreement (SGA) between
Midlothian Council and SEPA;
• identifying tree coverage on community planning
partners land using appropriate software
Page 51 of 164

Page 52

14
Being carbon neutral by 2030
Over the next 5 years we aim to:
• make the Council's activities net carbon zero by 2030.
• establish a Citizens Assembly and Climate Change Partnership
Group to engage the wider population, business, education and
scientific sectors in the climate change debate.
• raise awareness of the impacts and risks from a changing climate
and facilitate individual and collective action to combat climate
change.
• use green energy to heat and light our estate buildings, making
them as energy efficient as possible.
• take a ‘One Council’ approach to reducing carbon emissions and
putting this objective at the heart of our organisational activities,
processes and decisions.
• encourage people, businesses and communities to work
alongside the Council and make their own climate change
commitment.
• increase our recycling rates and reduce waste.
• lead by example and provide climate change leadership to our
partners, communities and businesses.
• develop our resilience and ability to adapt to the impacts and
risks of a changing climate.
• deliver the fleet replacement programme, expanding our electric
and ultra-low carbon vehicle fleet within available resources.
• adopt the Passivhausbuilding standard and incorporate ‘green’
and ‘blue’ infrastructure as standard design principles for new
developments.
• investigate the feasibility of Zero Carbon Development Zones.
• deliver the Shawfair low carbon community heating system and
investigate options to develop heat networks across the county.
• develop the Midlothian Active Travel network including cross-
boundary connections for longer distance commuting and leisure
routes.
• accelerate organisational change to extend home working and
reduce the need to travel.
• promote a ‘digital by default’ approach to service provision,
reducing paper based activity.
• work closely with the ‘local by default’ programme to embed a
carbon neutral approach to locality working.
Page 52 of 164

Page 53

Midlothian Council 
15th November 2022
Item 8.2 
Financial Monitoring 2022/23 – General Fund Revenue 
Report by David Gladwin, Chief Finance Officer (acting) 
Report for Information 
1 Recommendations 
Council is recommended to: 
a) Note specifically the projected financial position for the General Fund
Reserve in financial year 2022/23 and the associated risks with
projections at this stage in the year;  and otherwise 
b) Note the contents of the report. 
2 Purpose of Report / Executive Summary 
2.1 The purpose of this report is to provide Council with information on
projections of performance against service revenue budgets in 2022/23
and to provide commentary on areas of material variance against
budget. The projected budget performance figures as shown in
appendix 1 result in a net underspend of £1.442 million for the year
which is a £1.667 million improvement on the position at quarter 1
reported to Council on 23rd August. The projected underspend
represents 0.54% of the revised budget.
2.2 The projected General Fund balance at 31st March 2023 is £6.305
million, of which £0.265 million is earmarked for specific use.
2.3 The projection of the General Fund Balance at 31st March 2023 is
predicated on the ongoing financial impact of the Covid-19 Pandemic
continuing to be met from the available funding, whether ring fenced for
specific purposes, or from general funding provided.   
Date:  31 October 2022
Report Contact:
David Gladwin, Chief Finance Officer (acting)
David.Gladwin@midlothian.gov.uk   0131 271 3113 
Page 53 of 164

Page 54

2 
3 Background 
3.1 This report encompasses all performance against revenue budget for
General Fund services including additional costs incurred and
projected lost income as a consequence of the Covid-19 pandemic. 
3.2 The main areas of projected service budget variances projected at
quarter 2 are outlined below. As ever, projections during a financial
year are difficult in many areas and come with a degree of risk. The
implications of economic conditions prevalent during 2022/23 only adds
to this this. 
Projected Overspends
• There remains £1.212 million of Medium Term Financial
Strategy (MTFS) cost reductions to be finalised mainly relating
to Management Reviews across Place (£0.756 million), Sport &
Leisure (£0.166 million) and also including a review of the
Council’s Creative Arts service (£0.290 million). Clearly the
pandemic has impacted on progress with these but they are all
are now at implementation stage. These cost pressures are
partly mitigated by vacancies of £0.675 million held pending
completion of reviews; 
• Council run cafes and the outside catering service have
reopened after a long period of closure. Business is
considerably slower than experienced pre-pandemic and may
not fully recover leading to a projected overspend of £0.233
million. Management are reviewing the offering;
• Insurance costs are projected to be over budget by £0.292
million due to provisions made for new or reopened claims on
the Council. Whilst no individual claim is of particularly high
value the volume of individual claims is higher than is
customary. Council officers and loss adjusters review each claim
with oversight by the Risk and Safety Group;
• Costs of transporting young people to education settings
exceeds budget by £0.089 million. A full review of school and
children’s services transport has been initiated; 
• Costs of vehicle repairs mainly relating to external works
exceeds budget by £0.105 million. A service review is underway
alongside immediate cost containment measures; 
• Customer income from the Trade Waste service is lower than
provided for in the budget. The customer base is contracting and
management are reviewing the implications of this. The
projected overspend is £0.116 million;
• Costs of software and licencing due to increased cyber security
measures and a continued move to cloud-based software gives
rise to a projected overspend of £0.204 million;
• The budget for the year for Council Tax Income is £58.496
million and this includes £1.350 million aligned to continued
Page 54 of 164

Page 55

3 
housing growth in Midlothian. Projections at Q2 show a shortfall
against budget of £0.160 million (0.27%). Whilst household
growth to date does not differ significantly from budget setting
assumptions further forecasting work is necessary alongside a
review of collection rates. Further updates will be provided in
upcoming Medium Term Financial Strategy (MTFS) reports and
also within quarter 3 financial monitoring; 
• Fuel purchase costs for the Council’s fleet are projected to be
£0.151 million in excess of budget. Supply costs increased
considerably in recent months although have now returned close
to budgeted levels.
These are more than offset by favourable movements against budget:
• Significantly higher surplus cashflow than expected linked to the
current spend on Capital Programmes and the continued
increasing interest rate environment has provided opportunity to
generate a significantly higher return on short term deposits in
22/23 than was anticipated when the budget was set. Approved
methodology for allocating Loan Charges between General
Fund and Housing Revenue Account results in the vast majority
of this upside benefitting the General Fund. Current projections,
albeit in a fluctuating market, show an in-year underspend of
£1.141 million;
• Council Officers from Midlothian and the City of Edinburgh
Council (CEC), as part of the joint management and monitoring
arrangements for the waste plant at Millierhill, have been
working through calculations for third party income due. In
2022/23 it is projected that £0.734 million is due to Midlothian.
Work continues to develop understanding of future year
possibilities and an income assessment will be included in the
next MTFS update; 
• The cost of residential and day education placements for
children is £0.340 million lower than budgeted. Investment in
local supports rather than utilising external placements is driving
this position but there remains a risk of expensive external
placements at short notice and out with the Council’s control;
• The cost of family placements for children is projected to
underspend by £0.218 million with a continued push to recruit
foster carers;
• Savings continue to accrue from the avoidance of use of Bed
and Breakfast accommodation for homeless clients. An
underspend of £0.210 million is projected.   
3.3 Relevant senior officers are required to deliver recovery actions at pace
for the service areas that are projecting overspends and accordingly it
is expected that pressure in these areas may reduce over the
remainder of the year once the impact of the recovery action is
validated.
Page 55 of 164

Page 56

4 
Covid Costs
3.4 Covid related funding provided to the Council by the Scottish
Government alongside other funding streams aligned to Covid recovery
were carried forward from 2021/22 to 2022/23. Funding continues to be
applied in year to match costs and lost income with the planning
assumption that the remainder will be applied in 2022/23 or in future
years to mitigate the continued impact of the pandemic and support
increased service costs across Midlothian. 
Inflationary Pressures
3.5 Since the 2022/23 budget was approved there has been a rapid rise in
inflation. This has manifested itself in considerable additional and
unbudgeted costs in some service areas. Most visibly this is seen in
energy prices and contractual inflation embedded in contracts,
particularly for Public Private Partnerships (PPP). Council approved a
supplementary estimate of £1.395 million on 23rd August to fund these.
3.6 Further unbudgeted costs of £0.115m are projected in 22/23 for fuel for
Council operated fleet. Latest projections for energy costs do not
indicate further inflationary costs beyond the available budget mainly
due to forward purchasing and work is ongoing to understand the
impact of food price inflation.
Agreed Savings
3.7 Council on 4th October 2022 approved some operational efficiency
measures totalling £1.227 million in 2023/24 as an early contribution to
delivering a financially balanced MTFS. The following measures are
now implemented in 2022/23 and reflected in the projected outturn
figures in section 3.2 above.
• Leadership Review Corporate Solutions - £0.045m;
• Place – review of temporary accommodation provision -
£0.200m;
• Sport and Leisure
o Premises, Supplies and Services and Third Party
Payments - £0.045m;
o Reduction of Specialist Instructors - £0.035m.
The remaining measures will take a little more time to implement but
will be progressed as quickly as possible.  
Pay + National Insurance
3.8 The 2022/23 pay claims for the SJC bargaining group have now been
concluded and are at implementation stage. The agreed offer
represents:
• For those on the Local Government Living Wage and pay
scale point (SCP) 19 to 24 and undifferentiated 5% or a
£2,000 uplift (calculated on a nominal 36 hour working
week), whichever is larger;
• A 10.2% increase for the lowest paid. For SCP 38 (£24,984)
a 7.7% increase (£1,925) and for SCP 52 (£30,212) a 6.37%
increase (£1,925); and
Page 56 of 164

Page 57

5 
• An undifferentiated 5% or a £1,925 uplift (calculated on a
nominal 36 hour working week), whichever is larger, capped
for those currently earning £60,000 or more at a £3,000 uplift
(based on a 37 hour working week). 
It is estimated that this equates to a 7.23% increase in the Council’s
SJC paybill. 
3.9 An offer of 5% had been made to and rejected by the Scottish
Negotiating Committee of Teachers bargaining group. Discussions are
ongoing. 
Funding
3.10 A pay increase of 2.5% was provided for in the 2022/23 base budget.
The Scottish Government have provided additional funding for 3.73%
of the increased cost:
• £140m revenue funding nationally of which £2.338m will flow
to Midlothian as part of general revenue funding;
• £120.6 million of Capital Funding (Capital Flexibilities) of
which £2.014 million will flow to Midlothian as a capital grant.
A one-off flexibility option to allow capital grant to fund in-
year revenue expenditure has been developed with Scottish
Government and CoSLA officials and is awaiting Scottish
Government Ministerial approval. Until agreement by all
parties is reached (including Audit Scotland) there remains a
risk that the Council will not have adequate revenue funding
in place for the pay award. 
3.11 The remaining 1%, estimated at £1.8 million, links into ongoing national
discussions around funding flexibilities. Detail on options available for
Councils is awaited and the planning assumption is that there will be an
option within that works for all Councils. However, until this is known,
risk remains that the Council will not have an adequate funding solution
and may need to fund this from existing resources. 
3.12 At this point no adverse variation has been reflected in the outturn
projections for pay. 
National Insurance  
3.13 The UK Government reversed the 1.25% Health and Social Care
additional levy on Employers National Insurance rates. This will be
implemented from 6th November 2022 and is projected to reduce the
Council’s total paybill by around £0.400 million in 2022/23. As work is
ongoing to embed the change in detailed workings the projected
underspend for the year is not reflected in section 3.2 of the report but
instead is shown separately in the General Fund Reserve movement in
section 5.   
Building Maintenance Service
3.14 Financial outturn for 2021/22 reported to Council in June showed a
considerable adverse variance of £0.788 million for the Building
Page 57 of 164

Page 58

6 
Maintenance Service. A subsequent discussion took place at Business
Transformation Steering Group at which clear direction was given to
officers to undertake a fundamental service review. Officers are
progressing well with the review.  
3.15 Whilst the value of work invoiced at this point in the financial year has
improved from previous years there remains insufficient quality data on
which to base a robust financial projection. As a consequence there
remains a risk, based on previous experience, of an adverse variance
against budget arising which would add to the reported overspend and
further deplete reserves.
4 Delegation of resources to Midlothian Integration Joint Board
4.1 The approved budget provided for the allocation of £56.438 million to
the Midlothian Integration Joint Board (MIJB) for the provision of
delegated services. Minor technical adjustments to this allocation
during the year to date increase the allocation to £56.710 million.  
4.2 In accordance with the Integration Scheme the MIJB is required to
deliver delegated services within the budget allocations from the
Council and NHS Lothian and where any overspend is projected to put
in place a recovery plan to address that. As a last resort the integration
scheme allows for the MIJB to seek additional financial support from its
partners, either by way of an additional budget allocation or by
“brokerage” (provision of additional resources in a year which are
repaid in the following year).  
4.3 Additional costs incurred by the MIJB in response to the Covid-19
pandemic are expected to continue to be funded by government and
accordingly at this time the expectation is that delegated services will
be delivered within the allocations provided and so no provision has
been made for an additional budget allocation from the Council.
4.4 Financial Monitoring reports covering all of the MIJB activity are 
presented to the Integration Joint Board and are available on the
committee management section of the Council website:- 
Midlothian Integration Joint Board (cmis.uk.com) 
Page 58 of 164

Page 59

7 
5 Projected General Fund Reserve 
5.1 The projected balance on the General Fund as at 31 March 2023 is as
follows: 
£ million £ million
General Fund Reserve at 1 April 2022   32.432   
Planned movements in reserves  
Application of Budgets carried forward from
2021/22 for use in 2022/23  (19.923) 
Funding of Corporate Solution for 2022/23 Budget (5.576) 
Supplementary Estimate for Inflationary Pressures  (1.395) 
Supplementary Estimate for costs of the additional
public holiday  (0.030) 
Other movements 0.026 
(26.898)
Application of Business Transformation Funding to
support service re-design  (1.071)
Projected underspend per appendix 1  1.442
Projected saving from Employers National
Insurance rate cut   0.400
Projected General Fund Balance at 31 March
2023 
6.305 
An element of the General Fund is earmarked for specific purposes
and this is shown below: 
£ million
Projected General Fund Balance at 31 March 2023 6.305
Earmarked for specific purposes 
To support Council Transformation (0.265)
Projected General Reserve at 31 March 2023 6.040 
5.2 The Reserves Strategy approved by Council on 12 February 2019
needs the Council to maintain an adequate level of General Reserve to
provide a contingency for unforeseen or unplanned costs and that in
the financial context at that time approved the adoption of 2% of the
approved budgeted net expenditure (excluding resources delegated to
the IJB) to be considered a minimum. This now equates to £3.818
million. Council also agreed that where projections indicate that should
the 2% minimum General Reserve balance be breached an immediate
recovery plan be implemented to recover the position, failing which, the
next available budget would need to provide for the reinstatement of
reserve position. 
5.3 The projected General Reserve of £6.040 million is above the minimum
set in the Reserves Strategy but will only remain that way if there is no
further adverse performance against budget or any further draw on
reserves. There is also the continued uncertainty over the financial
impact of the pandemic and funding assumptions together with
essential response costs relating to weather conditions during the
winter period. 
Page 59 of 164

Page 60

8 
5.4 Similarly there is an expectation that there will be a recovery in the
service overspends projected at quarter 2. The impact of this recovery
action will be reflected in future projections when they are validated. 
6 Report Implications (Resource, Digital and Risk) 
6.1 Resource
The projected performance against budget set out in this report
presents the initial projections for the year. Work continues across the
council to reduce overspends and to progress at pace delivery of
approved savings. 
Whilst this report deals with financial issues there are no financial
implications arising directly from it. 
6.2 Digital 
Increased reliance and investment in digital solutions and digital first
solutions will be a key element of future plans. 
6.3 Risk
Section 95 of the Local Government (Scotland) Act 1973 requires all
Local Authorities in Scotland to have adequate systems and controls
in place to ensure the proper administration of their financial affairs. 
The assessment of performance against budgets by services is
underpinned by comprehensive financial management and budgetary
control arrangements. These arrangements are central to the
mitigation of financial risk. 
Ensuring that adequate systems and controls are in place reduces the
risk of significant variances arising, and where they do arise they help
to ensure that they are identified and reported on and that appropriate
and robust remedial action is taken. The primary purpose of this report
is to provide an assessment of projected performance against budget
for the full year based on activity in the second quarter of the year.
The material variances detailed in the report highlight that the financial
management and budgetary control arrangements require continual
review and enhancement if financial risk is to be effectively mitigated
during the year. 
At this point in the financial year there is a heightened risk that actual
costs and income level may vary across the remainder of the financial
year. The projected financial position could also deteriorate if local or
national restrictions were to be reintroduced. In additional the risk of
adverse weather has the potential to create pressure on service
budgets over the remainder of the year 
There are a some areas where effective forecasting of spend against
budget is hindered due to incomplete service information which in
previous years has resulted in previously unreported or significantly
adjusted variances at the financial year end. Financial Management
Page 60 of 164

Page 61

9 
CMT continues to consider these areas and supports actions to
address the underlying issues and mitigate the risk associated with
them.   
The financial projections are predicated on new burdens, including
those arising from the Government’s 100 day commitments to be fully
funded. The position with outstanding pay awards and the potential for
unfunded costs arising presents a significant risk to the Council’s
financial position not only for the current financial year but for future
years. 
The Council recognises the potential for compensation claims deriving
from Scottish Government’s Limitation (Childhood Abuse) (Scotland)
Act 2017 which removes the three year time limit on claims of child
abuse. Some claims will be historic and relate to Lothian Regional
Council, Midlothian District Council or their predecessors and some
will date post reorganisation and relate to Midlothian Council, and so
presents a risk that would further reduce reserves from those currently
projected.  Further financial obligations may also arise as the
implications associate with the The United Nations Convention on the
Rights of the Child (Incorporation) (Scotland) Bill, which has yet to
secure Royal Assent , are more fully understood. 
6.4 Ensuring Equalities 
As changes to existing plans are developed the assessment of the
impact of these proposals in relation to their impact on equalities and
human rights will be carried out. This will help to ensure wherever
possible that there are no negative impacts on equality groups or
potential for infringement of individuals’ human rights from the any of
the proposals. 
6.5 Additional Report Implications 
See Appendix A 
Appendices 
Page 61 of 164

Page 62

10 
APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
The existing financial plans support the delivery of the key priorities in
the single Midlothian Plan. As the impact on the Council of the
pandemic and recovery continues to unfold over the financial year any
changes in the availability and allocation of resources will need to be
considered in parallel to the actions proposed to continue to delivery
key priorities. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
The report does not directly impact on Delivering Best Value. 
A.5 Involving Communities and Other Stakeholders 
The development of the Medium Term Financial Strategy reflected a
community consultation exercise carried out in 2019 which has also
helped shape the drafting of the “Midlothian Promise” and the early
development of the Council’s Longer Term Financial Strategy.   
In addition there is continues engagement with the recognised Trade
Unions on the financial position. 
Page 62 of 164

Page 63

11 
A.6 Impact on Performance and Outcomes 
The Financial Strategy facilitates decision on how Council allocates
and uses its available resources and as such has fundamental
implications for service performance and outcomes. The financial
consequences of the pandemic will impact on the availability and
allocation of resources in pursuit of key outcomes as set out in the
Single Midlothian Plan for both the immediate and longer term and
therefore the ability of the Council to continue to deliver services in a
financial sustainable manner. 
A.7 Adopting a Preventative Approach 
Maintaining the effectiveness of the Financial Strategy will support the
prioritisation of resources to support prevention. 
A.8 Supporting Sustainable Development 
There are no direct sustainability issues arising from this report and we
will work to mitigate as far as feasible any sustainability issues which
arise as a consequence of any of the changes to existing plans. 
Appendix 1 financial tables 
Page 63 of 164

Page 64

Page 64 of 164

Page 65

MIDLOTHIAN COUNCIL
Appendix 1
GENERAL FUND 2022/23
Performance against budget
Revised Budget Revised Budget Revised Budget (Underspend)
Function Approved Budget Expenditure Income Net Outturn / Overspend
£ £ £
Management and Members 1,965,977 2,002,202 0 2,002,202 2,015,202 13,000
Place
Corporate Solutions 22,081,954 47,172,648 (24,528,180) 22,644,468 22,751,468 107,000
Place 35,963,912 52,878,285 (13,534,276) 39,344,009 39,098,009 (246,000)
Central Costs 1,860,593 4,998,061 4,998,061 5,290,061 292,000
People and Partnerships
Midlothian Integration Joint Board 56,437,641 65,231,665 (8,521,628) 56,710,037 56,710,037 0
Non-Delegated Services - Sport and Leisure, Community Safety and
Welfare Rights 1,995,738 7,453,717 (5,056,125) 2,397,592 2,548,592 151,000
Childrens Services, Partnerships and Communities 20,138,997 23,282,413 (438,567) 22,843,847 22,199,847 (644,000)
Education 108,920,147 136,039,764 (16,661,463) 119,378,301 119,244,301 (134,000)
Lothian Valuation Joint Board 581,659 581,659 0 581,659 581,659 0
Non Distributable Costs 898,936 898,936 0 898,936 898,936 0
GENERAL FUND SERVICES NET EXPENDITURE 250,845,553 340,539,350 (68,740,238) 271,799,112 271,338,112 (461,000)
Loan Charges 2,763,485 2,763,485 2,763,485 1,622,485 (1,141,000)
NDR Discretionary Relief 70,300 70,300 70,300 70,300 0
Investment Income (110,736) 0 (110,736) (110,736) (110,736) 0
Allocations to HRA, Capital Account etc. (5,331,603) (5,331,603) (5,331,603) (5,331,603) 0
248,237,000 338,041,532 (68,850,974) 269,190,558 267,588,558 (1,602,000)
less Funding:
Scottish Government Grant (184,165,000) 0 (184,583,500) 184,583,500 184,583,500 0
Council Tax (58,496,000) 0 (58,496,000) 58,496,000 58,336,000 160,000
Utilisation of Reserves 5,576,000 338,041,532 (311,930,474) 26,111,058 24,669,058 (1,442,000)
Page 65 of 164

Page 66

Page 66 of 164

Page 67

Midlothian Council
15 November 2022 
Item 8.3  
General Services Capital Plan
2022/23 Quarter 2 Monitoring 
Report by David Gladwin, Chief Finance Officer (Acting) 
Report for Decision 
1 Recommendations 
It is recommended that the Council:- 
1. Approve addition of the project budgets set out in Section 3.1; and
2. Note the forecast outturn for expenditure (after reflecting
rephased project budgets), funding and borrowing, as outlined in
Section 4. 
2. Purpose of Report 
The purpose of this report is to provide Council with:- 
• An update of the General Services Capital Plan incorporating
information on additions to the Capital Plan for approval (Section
3); and
• Information on the projected performance against budget for
2022/23 (Section 4); also to
• Update on the Capital Fund (Section 5). 
Date 03 November 2022
Report Contact:
Gary Thomson, Senior Finance Business Partner
gary.thomson@midlothian.gov.uk 0131 271 3230  
Page 67 of 164

Page 68

2
3 Update of General Services Capital Plan 
3.1 New projects presented for endorsement in the Plan 
The following additions are being presented for inclusion in the General
Services Capital Plan and represent technical adjustments reflecting the
award of external funding:- 
• Midlothian Energy Limited: Heat Offtake Facility: Capital expenditure
budget of £1.040 million, to be fully phased in 2022/23 and fully funded by
prudential borrowing, for the Council’s contribution to the installation of a
Heat Interface Station at the Millerhill Energy from Waste Facility. 
Approved by Council on 4 October 2022;
• Play Park Renewal 2022/23: Capital expenditure budget of £0.097
million, to be fully phased in 2022/23 and fully funded by Play Park
Renewal Capital Grant funding from Scottish Government, for the
replacement of existing equipment in play areas across the county. 
Approved by Council on 4 October 2022.
• Vogrie Country Park Toilets: Capital expenditure budget of £0.200
million, to be fully phased in 2022/23 and fully funded by Place Based
Investment Fund Capital Grant Funding from Scottish Government, for the
upgrade of toilet facilities in the Country Park.  Approved by Council on 4
October 2022;
• Nature Restoration Fund: Capital expenditure budget of £0.103 million,
to be fully phased in 2022/23 and funded by £0.103 million of Nature
Restoration Fund Capital Grant from Scottish Government, for the
restoration and improvement for biodiversity of ponds at Vogrie Country
Park and Valleyfield, Penicuik; and the creation of a new biodiversity pond
at the Penicuik-Dalkeith former railway active travel route at Rosewell. 
Approved by Capital Plan & Asset Management Board on 13 September
2022;
• Hearse House, Penicuik: Capital expenditure budget of £0.142 million, to
be fully phased in 2022/23 and fully funded by Place Based Investment
Fund Capital Grant Funding from Scottish Government, for the repair and
restoration of the Hearse House in Penicuik. Approved by Capital Plan &
Asset Management Board on 25 October 2022;
• Heritage Trail, Penicuik: Capital expenditure budget of £0.045 million, to
be fully phased in 2022/23 and funded by £0.030 million of Place Based
Investment Fund Capital Grant Funding from Scottish Government and
£0.015 million of prudential borrowing from the three local Member’s
Environmental Capital Budgets, for the creation of a heritage trail for
Penicuik Town Centre. Approved by Capital Plan & Asset Management
Board on 25 October 2022;
• Millerhill Pavilion Demolition: Capital expenditure budget of £0.023
million, fully phased in 2022/23 and to be funded from prudential
borrowing.  Approved by Capital Plan & Asset Management Board on 25
October 2022;  
Page 68 of 164

Page 69

3
4 2022/23 Projection against budget 
4.1 2022/23 Budget 
After accounting for the following:- 
• Rephasing of budgets from 2021/22 to 2022/23 as reported to Council at
Quarter 1 on 23 August 2022;
• Including the new projects and adjustments to project budgets as outlined
in Section 3. 
The capital plan expenditure budget for 2022/23 is £57.175 million,
funding budget was £31.571 million and in-year borrowing of £25.604
million. 
4.2 Rephasing 
Project expenditure budgets have been rephased based on the latest
information available from Project managers and Service Leads as noted
in Table 1 below. 
Table 1: Rephasing of project expenditure budgets 
Project Description of rephasing of budget Previous
2022/23
Budget
£000’s
Revised
2022/23
Budget
£000’s
2022/23
Budget
Rephasing
£000’s
CHILDREN, YOUNG PEOPLE & ESTATES PROGRAMME BOARD
Easthouses
Primary School
Programme is being revised and so initial
construction works that were anticipated for the
later part of 2022/23 have now been rephased to
early 2023/24
2,418 645 -1,773
King’s Park
Primary Schools
Extension &
Refurbnishment
Awaiting outcome of LEIP Phase III bid to
determine way forward, either new build or
extension
600 200 -400
St. David’s Primary
School Extension
Roll projections showing extension works
currently not required for August 
225 0 -225
Mauricewood
Primary School
Work to progress detailed outline business case
is progressing
200 70 -130
Rosewell Primary
School
Awaiting outcome of LEIP Phase III bid to
determine way forward, either new build or
extension
250 0 -250
Newtongrange
refurb & expansion
to 2-stream
Pupils will be required to decant in order for
works to be carried out; this requires Easthouses
PS to be open (scheduled for 2024/25) to
accommodate Newtongrange PS decant
645 0 -645
Bonnyrigg Primary
– modular unit
Roll projections show this is currently not
required for August 2023 with capacity need to
be reviewed
562 0 -562
Lasswade High –
Toilets and
Changing
Facilities
Toilets are complete other than end of year
defects.  Changing room proposals need
reviewed with any works now to be carried out in
2023/24
453 50 -403
Page 69 of 164

Page 70

4
Lasswade High –
ASU
Linked to completion of move of Mount Esk
nursery to Hawthornden Primary – anticipated
completion now 2025
1,333 0 -1,333
Woodburn Primary
School
Project programme revised 1,500 828 -672
Early Years Capital
Grants Scheme
Projects with external partners now complete 30 343 +313 
Project Description of rephasing of budget Previous
2022/23
Budget
£000’s
Revised
2022/23
Budget
£000’s
2022/23
Budget
Rephasing
£000’s
ASSET MANAGEMENT PROGRAMME BOARD
Digital Services
Asset Management
Plan
Current forecasts of expenditure prior to refresh
of Digital Asset Management Plan targeted for
Quarter 3
3,735 1,508 -2,227
Street Lighting &
Traffic Signal
Upgrades
Rephasing due to delays in procurement process
with expiring capital works contractor framework
and new contractor being appointed
1,210 1,100 -110
Footway &
Footpath Asset
Management
Programme
Reprioritisation of work and internal resources to
the Accelerated Roads Residential Streets
programme
889 500 -389
Temple Ground
Stabilisation
Reprioritisation of work and internal resources to
the Accelerated Roads Residential Streets
programme along.  Detailed design schemes will
be prepared in due course for these essential
work to ensure the long term integrity of these
sections of the public road network
309 0 -309
B6372 Arniston
Bank Stabilisation
Reprioritisation of work and internal resources to
the Accelerated Roads Residential Streets
programme
593 0 -593
Property Sport &
Leisure – Various
Rephased to 2023/24 prior to business case
regarding need being brought forward
406 0 -406 
TRANSPORT, ENERGY & INFRASTRUCTURE PROGRAMME BOARD
A701 & A701 Relief
Road
Rephasing based on revised project programme
and awaiting outcome of Levelling Up Fund
application
1,532 1,423 -109
Cycling, Walking &
Safer Routes
Surfacing works to Rosewell to Auchendinny
Cycleway will be undertaken and complete by
June 2023
596 398 -198  
Page 70 of 164

Page 71

5
Project Description of rephasing of budget Previous
2022/23
Budget
£000’s
Revised
2022/23
Budget
£000’s
2022/23
Budget
Rephasing
£000’s
REGENERATION & DEVELOPMENT PROGRAMME BOARD
Destination Hillend The project is undergoing work to refresh the
business case to control the capital costs and to
market test the product incomes to ensure an
economically viable project.  A members briefing
is scheduled on the project.
8,035 2,210 -5,825 
OTHER
Highbank
Intermediate Care
Reprovisioning
Construction work on Extra Care building will
commence in late 2022/23 ahead of
commencement of work on Intermediate and Day
Care buildings in early 2023/24
1,553 500 -1,053
CCTV Network Fixed cameras currently out to tender, expected
conclusion in early 2023 calendar year, with
installation in early 2023/24
472 73 -399
Free School Meal
Provision
Roll out of remainder of provision when free
school meals for Primary 6 and 7’s are
implemented by Scottish Government
324 162 -162
Others Rephasing of other projects 3,416 3,347 -69
Total  31,286 13,357 -17,929 
This results in a rephased capital expenditure budget for 2022/23 of
£39.246 million as shown in detail in Appendix 1. 
In line with this, the expected level of funding available to finance the
plan has also been rephased and now totals £26.641 million. 
This results in an in-year borrowing requirement of £12.605 million. 
The projected performance against budget for 2022/23 is shown in table
2 below:- 
Table 2: General Services Capital Plan Projected Performance
against Budget 2022/23 – as at Quarter 2 
Item 2022/23 Actual 2022/23 2022/23 2022/23
Rephased To Projected Variance Carry
Forecwar Budget 11.09.21 Outturn 
£000’s
Forward
£000’s
£000’s
£000’s £000’s £000’s 
Expenditure 39,246 5,761 39,006 -240 -17,929
Funding 26,641 5,443 26,660 +19 -4,930
Borrowing
Required
12,605 318 12,346 -259 -12,999 
4.3 Expenditure 
Expenditure to 11 September 2022 is £5.761 million and at this point
project managers and service leads are indicating a forecast expenditure
outturn of £39.006 million, a projected net underspend of £0.240 million
against the revised budget of £39.246 million. Page 71 of 164

Page 72

6 
The net variation of £0.240 million relates to the following:- 
• North Middleton Bridge: Project complete with outturn £0.025 million
less than budget.
• Poltonthall Pitch: Overspend of £0.143 million against £0.582 million
budget (see report elsewhere on today’s agenda);
• Penicuik Pitch: Underspend of £0.070 million against £0.309 million
budget.  Underspend due to project completing without requiring use of
contingency.
• Strathesk Primary School: 1 class extension works no longer
required.  Saving in indicative project budget of £0.305 million
• Saltersgate School: now complete with £0.015 million overspend
against budget, offset by £0.019 million external grant funding (see
Section 4.4). 
Expenditure incurred to 11 September 2021 across all projects in the
General Services Capital Plan amounts to £5.761 million, equating to
15% of the projected total expenditure budget for 2022/23. 
Given the substantive expenditure currently estimated to be committed
in the second half of the year combined with material supply and
inflationary pressures, all Project Managers and Service Leads are
carrying out a full review of project plans and expenditure profiles and
the outcome of this will be reflected in the Q3 report to Council in
February 2023. 
4.4 Funding 
The funding available to finance the Capital Plan in 2022/23 is expected
to total £26.660 million, £0.019 million higher than the rephased budget,
reflecting £0.019 million of external grant funding available for the
Saltersgate School project 
Funding of £5.443 million has been received to 11 September 2022. 
4.5 Borrowing 
Based on the forecast expenditure and funding levels as noted above,
the revised estimate of the level of borrowing required for 2022/23 is
forecast to be £12.346 million.  The impact on the Council’s borrowing
costs is reflected in the Financial Monitoring 2022/23 General Fund
Revenue report elsewhere on today’s agenda. 
5. Capital Fund 
The Capital Fund at the start of the 2022/23 financial year was £22.178
million.  £7.694 million of this is committed to fund the City Deal, with a
further £12.061 million committed to support capital investment including
the utilisation of £3.000 million in 2022/23. 
Page 72 of 164

Page 73

7
The forecast non-committed capital fund balance at 31 March 2023 is
£1.888 million, as shown in the table below. 
Item Amount
£000’s
Balance at 01 April 2022 22,178
Committed to fund City Deal Project -7,694
Committed to support Capital Investment -12,061
Developer Contributions earmarked for specific purposes -535
Non-committed balance at 31 March 2023 1,888 
6. Report Implications 
6.1 Resource 
The borrowing required to finance the planned investment in 2022/23 is
currently £12.346 million and is reflected in the Financial Monitoring
2022/23 General Fund Revenue report elsewhere on today’s agenda. 
6.2 Digital 
There are no Digital Services implications arising from this report. 
6.3 Risk 
The construction materials supply chain has already been subject to
unprecedented disruption and inflation pressures through a combination
of the Coronavirus (COVID-19) Pandemic, the conflict in the Ukraine and
the UK leaving the European Union.  The Construction Leadership
Council (CLC) continues to report shortages of construction materials
and forecasts this disruption to continue for the foreseeable future. 
Ongoing engagement with suppliers confirms that materials shortages,
longer lead times and steep price increases are highly likely to continue
to impact the supply chain. 
Factors contributing to pricing increases include contractors no longer
being able to absorb strong upward pressure from input costs, rising
demand, logistics problems and materials and labour shortages.  In
particular, materials prices are likely to be an ongoing concern due to
worldwide supply issues; and this is being reflected in recent tender
returns.  Tendering contractors are making specific reference to time
periods for the supply of labour and materials, a recent change in diesel
rules, the current conflict in Ukraine and potential shortages of materials
from China and elsewhere. 
Specific areas of major increases include groundworks, steel (structural
and steel product), metal cladding, timber, insulation and fire protection. 
This potentially exacerbates the inherent risk in the Capital Plan that
projects will cost more than estimated thus resulting in additional
borrowing, or will be subject to significant delay. 
The construction industry in Scotland and the UK is currently
experiencing unprecedented adverse market conditions, which is leading Page 73 of 164

Page 74

8
to significant rises in tender prices for a wide range of materials. There is
evidence that inflation of between 10% and 15% beyond BCIS
predictions is affecting projects and whilst measures such as value
engineering and contract award review are partially mitigating cost
increase there is a risk that the capital budgets provided for delivery of
the project in the plan will need to be increased with a resultant impact
on the funding strategy. The situation is currently being monitored and
reviewed and an update will be provided to Council when the value of
the impact has been determined. 
Strengthened financial monitoring & governance procedures have been
approved by CP&AMB, which will ensure that significant variations can
be captured and reported to Programme Boards and CP&AMB so that
remedial action can be taken to mitigate the risks. 
In developing the strategy and taking cognisance of the longer term
affordability gap it is clear that a number of potential projects which are
currently included will only be able to be progressed if they can be
delivered on a spend to save basis (i.e. where income or cost savings
more than offset the cost of funding the investment) or where they can
be delivered on a cost neutral basis or through alternative funding
mechanisms. 
The Capital Plan includes a provision for the return of contingencies of
£5.793 million over the period 2022/23 to 2025/26, equating to 2.5% of
all project expenditure.  The risk is that projects throughout the plan are
unable to deliver this which could be in part due to factors outwith the
Council’s control.  Capital Plan & Asset Management Board will review
the level of return of contingencies against the £5.793 million provision
on an ongoing basis to ensure that projects can, where possible, deliver
against this provision and that the provision continues to be appropriate 
6.4 Ensuring Equalities 
There are no equalities issues arising directly from this report. 
6.5 Additional Report Implications 
See Appendix A.  
Page 74 of 164

Page 75

9
Appendix A: Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Not applicable. 
A.2 Key Drivers for Change 
A.3 Key Delivery Streams 
Themes addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
The report does not directly impact on Delivering Best Value. 
A.5 Involving Communities and Other Stakeholders 
No external consultation has taken place on this report. 
A.6 Impact on Performance and Outcome 
There are no issues arising directly from this report. 
A.7 Adopting a Preventative Approach 
Not applicable. 
A.8 Supporting Sustainable Development 
Not applicable. 
Page 75 of 164

Page 76

10 
Background Papers:
Appendix 1 –General Services Capital Plan 2022/23 Quarter 2 Monitoring 
Page 76 of 164

Page 77

Appendix 1: General Services Capital Plan 2022/23 Quarter 2 Monitoring 
Rephased
2022/23 2022/23 2022/23 2022/23 2022/23
GENERAL SERVICES CAPITAL PLAN Budget Actual Forecast Variance Carry
Q2 Monitoring Q2 to P6 Outturn Q2 Q2 Forward Q2
£000's £000's £000's £000's £000's
CHILDREN, YOUNG PEOPLE & ESTATES PROGRAMME BOARD
Education - Primary
Woodburn Primary 16 class & activity hall extensi 828 164 828 - 672
Easthouses Primary School 645 (7) 645 - 1,773
Kings Park PS upgrade to existing building 200 200 - 400
St Davids Primary - 4 class & EY extension - - - 225
Mauricewood Refurbishment 70 70 - 130
Rosewell Primary School - extend to 2 stream - - - 250
Hopefield Farm Primary 2 (HS12) - - - -
Newtongrange refurb & expansion to 2 stream - - - 645
Strathesk Primary one class extension 305 - (305) (91)
Mayfield School Campus replace & extend 15 15 - -
Bonnyrigg Primary - Modular Unit - - - 562
Burnbrae Primary - Conversion of ASN to GP Sp 82 82 - -
Tynewater Primary School 10 10 - -
Education - Primary - Projects near completion
Paradykes Primary Replacement 144 0 144 - -
St. Mary’s RC & Early Burnbrae Primary Schools 140 140 - -
New Danderhall Primary hub 277 113 277 - -
Sacred Heart Primary School Extension 415 266 415 - -
Education - Secondary
Beeslack CHS Replacement 1,054 655 1,054 - -
Lasswade High - Toilets & Changing to 1,600 pu 50 1 50 - 403
Education - ASN
Hawthornden Primary - ASN Unit 492 103 492 - -
Lasswade High - ASU - - - 1,333
ASN Provision - Social Complex Needs 250 250 - -
Saltersgate Alterations Phase III - Playground Im 149 191 191 42 -
Saltersgate Phase IV - Internal Alterations 28 2 2 (27) -
Education - Early Years
Mount Esk Nursery School Replacement @ Haw - - - -
King's Park Primary School 55 22 55 - -
Rosewell Primary School New Build - - - -
Roslin Primary School 364 364 - -
Capital grants to partner providers 343 343 343 - -
Gorebridge Primary School - - - -
Catering kitchens - - - -
Hawthorn Children & Families Centre Alteration 164 7 164 - -
Mauricewood Primary School 247 109 247 - -
Vogrie Outdoor Early Learning Centre 81 81 - -
Other Outdoor Spaces 67 19 67 - -
Settings' kitchens - - - -
Newtongrange Primary School - - - -
Lasswade Primary School - - - -
Woodburn Primary School - - - -
Rosewell Primary School Alteration - - - -
Mount Esk Nursery School - 15 - - -
Tynewater Primary School - - - -
Bilston Primary School - - - -
Moorfoot Primary School - - - -
Loanhead Primary School - - - -
Cuiken Primary School - - - -
St Andrew's Primary School - - - -
Remaining Balance - - - -
Education _ General
Learning Estate Strategy: Development Budget 1,222 265 1,222 - -
Modular Units - Session 2017/18 107 - 107 - -
Burnbrae Primary School External Works 73 - 73 - -
New Learning Estate Furniture & IT Equipment - - - -
TOTAL - CHILDREN, YOUNG PEOPLE & ESTA 7,876 2,266 7,587 (289) 6,302
Page 77 of 164

Page 78

12 
Rephased
2022/23 2022/23 2022/23 2022/23 2022/23
GENERAL SERVICES CAPITAL PLAN Budget Actual Forecast Variance Carry
Q2 Monitoring Q2 to P6 Outturn Q2 Q2 Forward Q2
£000's £000's £000's £000's £000's
ASSET MANAGEMENT PROGRAMME BOARD
Digital
Business Applications 8 35 8 - -
DS Corporate Solutions 142 34 142 - 474
Front Office - Hardware, Software  & Services 302 171 302 - (481)
Back Office - Hardware, Software & Services 176 (31) 176 - 1,208
Network, Software & Services 526 34 526 - 52
Schools - Hardware, Software  & Services 362 204 362 - 974
Digital: Equipped for Learning 776 136 776 - -
Roads & Street Lighting
Street Lighting and Traffic Signal Upgrades - New 1,100 209 1,100 - 110
Footway & Footpath Asset Management Plan - N 500 58 500 - 389
Roads Asset Management Plan - New 1,733 1,733 - -
Accelerated Roads Residential Streets 2,950 449 2,950 - -
Roads Asset Management Plan - Temple Ground - - - 309
Roads Asset Management Plan - B6372 Arniston - - - 593
Fleet
Vehicle & Plant Replacement Programme 2,066 506 2,066 - -
Property
Property Upgrades 1,283 119 1,283 - -
Open Spaces / Play Areas
Ironmills Park Steps 7 7 - -
Outdoor Play Equipment - Rosewell 46 46 - -
Outdoor Play Equipment - Gorebridge 1 1 - -
Roslin Wheeled Sports Facility 59 59 - -
Mauricewood Road Bus Shelter 4 4 - -
Millerhill Park Circular Path & Bicycle Pump Track 89 89 - -
Welfare Park, Newtongrange 98 98 - -
Pump Track, North Middleton 76 76 - -
Play Park Renewal 2021/22 98 98 - -
Play Park Renewal 2022/23 97 97 - -
Nature Restoration Fund 2021/22 41 4 41 - -
Nature Restoration Fund 2022/23 103 103 - -
Birkenside Grass Pitch Drainage 12 12 - -
Open Spaces - Midlothian Wide Play Areas 169 169 - 169
Contaminated Land 186 31 186 - -
Sport & Lesiure Equipment
Property - Poltonhall Astro & Training Area Resu 384 475 527 143 -
Property - Penicuik Astro Resurfacing 76 6 (70) -
Dalkeith Thistle - Pavilion Upgrade 6 6 - -
Loanhead Memorial Park Pitch 4 4 - -
Flotterstone Car Park Infrastructure & Charging 16 16 - -
Property - King's Park Tennis Courts Resurfacing - - - 82
Property - Penicuik Centre Flooring, Cardio & Eq - - - 178
Property - Lasswade Centre Flooring - - - 97
Property - Gorebridge Leisure Centre - - - 48
Property - Loanhead Centre - - - 2
TOTAL - ASSET MANAGEMENT PROGRAMME 13,498 2,435 13,571 73 4,203
TRANSPORT, ENERGY & INFRASTRUCTURE PROGRAMME BOARD
Transport
A701 & A702 Relief Road City Deal Project 1,423 66 1,423 - 109
A7 Urbanisation 106 106 - -
Orbital Bus Route 302 302 - -
Cycling, Walking & Safer Streets Projects 398 - 398 - 198
Midlothian Energy Limited - Heat Offtake Facility 1,040 1,040 - -
TOTAL - TRANSPORT, ENERGY & INFRASTRU 3,269 66 3,269 - 308
REGENERATION & DEVELOPMENT PROGRAMME BOARD
Regeneration
Place Based Investment Fund 2021/22 649 43 649 - -
Place Based Investment Fund 2022/23+ 534 534 - -
Development
Stobhill Depot Upgrade 568 568 - -
Destination Hillend 2,210 180 2,210 - 5,825
Shawfair Town Centre Land Purchase 5,165 106 5,165 - -
Dalkeith Town Centre
Newtongrange Library
TOTAL - REGENERATION & DEVELOPMENT P 9,126 329 9,126 - 5,825
Page 78 of 164

Page 79

13 
Rephased
2022/23 2022/23 2022/23 2022/23 2022/23
GENERAL SERVICES CAPITAL PLAN Budget Actual Forecast Variance Carry
Q2 Monitoring Q2 to P6 Outturn Q2 Q2 Forward Q2
£000's £000's £000's £000's £000's
OTHER (PROGRAMME BOARD NOT YET DEFINED)
PLACE
Digital
Newbattle Centre of Excelllence 258 9 258 - -
Civica Automation 47 47 - -
CCity Deal - Digital - - - -
Transport
North Middleton Bridge 62 36 37 (25) -
PrNew recycling facility - Penicuik - - - -
Food Waste Rural Routes 132 132 - -
LEZ Electric Vehicles & Charging Points 48 1 48 - -
Rosewell Road Toucan Crossing 50 50 - -
Property/Development
Midlothian & Fairfield House Shower Upgrades 5 5 - -
32-38 Buccleuch Street Ground Floor Redevelop 346 137 346 - -
Hardengreen One and Two 3,107 0 3,107 - -
Public Sector Housing Grants 198 96 198 - -
Borders Rail - Economic Development Projects 125 125 - -
Gorebridge Connected - - - -
Penicuik THI 132 132 - -
Mayfield Town Centre Regeneration 4 4 - -
CCTV Network 73 73 - 399
Town Centre Regeneration Fund 2019/20 0 11 0 - -
Town Centre Regeneration Fund 2020/21 91 17 91 - -
Purchase to Pay 2 2 - -
EWiM - Buccleuch House Ground Floor 33 33 - -
Millerhill Pavilion 23 23 - -
PEOPLE & PARTNERSHIPS
Education
CO2 Monitors for Schools / Ventilation 21/22 Pha 93 92 93 - -
Free School Meal Provision 162 162 - 162
Children's Services
Residential House for 5-12 year olds 210 39 210 - -
Communities & Partnerships
Members Environmental Improvements 233 166 233 - -
Participatory Budgets - - - -
Adult Social Care
Assistive Technology 176 13 176 - -
Homecare 55 55 - -
Highbank Intermediate Care Reprovisioning 500 (33) 500 - 1,053
General Fund Share of Extra Care Housing 297 79 297 - -
Sport & Leisure
Property - Shawfair Leisure/Library Provision - - - -
TOTAL NOT ALLOCATED TO PROGRAMME B 6,462 664 6,437 (25) 1,614
COST OF SALES
- - - -
TOTAL COST OF SALES - - - - -
SUBTOTAL - PRE RETURN OF CONTINGENCIE 40,231 5,761 39,991 (240) 17,929
Provision for Return of Contingencies (985) (985) - -
GENERAL SERVICES CAPITAL PLAN TOTAL 39,246 5,761 39,006 (240) 17,929
Page 79 of 164

Page 80

Page 80 of 164

Page 81

Midlothian Council
15 November 2022
Item No 8.4   
Housing Revenue Account
Revenue Budget and Capital Plan 2022/23 
Report by David Gladwin, Chief Finance Officer (Acting). 
Report for Decision 
1 Recommendations 
Council is recommended to:
• Note the contents of this report;
• Approve the reallocation of the £10 million earmarked capital
budget for Retrofit Fire Safety Sprinkler Systems to the New
Social Housing Phase 3-4 project as covered in section 3.1
below;
• Approve the release of a further £0.020m from the HRA
Reserve to support the developing strategy for Dalkeith Town
Centre. 
2 Purpose of Report/Executive Summary 
The purpose of this report is to provide Council with a summary of
expenditure and income to 26th September 2022 for the Capital Plan
and a projected outturn for both the Housing Revenue Account (HRA)
and Capital Plan for 2022/23.    
The summarised financial performance for 2022/23 is:
• Capital Investment in the year totalling £53.842 million; 
• A net underspend of £0.171 million on the Revenue Account;
• A projected HRA general reserve at 31st March 2023 of £32.264
million. 
Date 26th October 2022 
Report Contact: 
Name Lisa Young Tel No 0131-271-3111
lisa.young@midlothian.gov.uk 
Page 81 of 164

Page 82

2 
3 Background 
3.1 Capital Plan 2022/23 
The Capital Plan Budget has been revised to reflect the current profile
of spend as shown in appendix C.  Capital investment in the year is
projected to be £53.842 million and there are currently no material
variances to be reported.   
The construction industry in Scotland and the UK is currently
experiencing unprecedented adverse market conditions, which is
leading to significant rises in tender prices for a wide range of
materials. There is evidence that inflation of between 10% and 15%
beyond BCIS predictions is affecting projects and whilst measures
such as value engineering are partially mitigating cost increase there
is a risk that the capital budgets provided for delivery of the New
Social Housing project will need to be increased with a resultant
impact on the funding strategy. Spend in 2022/23 is largely
determined by contracts awarded prior to the acceleration of market
influences thus the principal risk at this stage relates to future financial
years. 
Currently there is an approved budget of £156.258 million allocated to
Phase 3 and 4 of the New Social Housing project phased over
2019/20 to 2026/27. Due to the factors mentioned above the current
projected overall project cost is £18 million more than budgeted. To
address this, two sites, where there is current uncertainty to their
progression, will now be included as part of phase 5 thus reducing
overall projected cost by approximately £8 million. 
The approved Environmental improvements budget includes an
allocation of £10 million for fire safety sprinkler systems which was
earmarked as a precaution should Scottish Ministers require that the
Council retrofit fire safety sprinkler systems to our social housing stock
in response to the Grenfell Tower incident.  The Ministerial Group on
Fire & Building Regulations has since announced that there is not a
requirement to carry out these works and it is therefore recommended
to reallocate this budget to the New Social Housing Phase 3 and 4
project to address the remaining £10 million projected cost over-run
therefore bringing the current approved capital plan back within
budget. 
3.2 Revenue Account 2022/23 
Dalkeith Town Centre Masterplan and Outline Business Case
Council on 14th December 2021 approved the utilisation of £0.060m
from the General Fund Reserve and £0.020m from the Housing
Revenue Account Reserve to fund work needed to update the
masterplan and strengthen the economic, financial and commercial
case.
Page 82 of 164

Page 83

3 
Work has been progressing well and a final report will be presented to
Members early in 2023. Additional consultant input to support
attendance at meetings and consultation events not originally scoped
for and also to work through some additional analysis is anticipated to
cost a further £0.020m to that already approved. The nature of this
additional work relates to possible housing options in Dalkeith Town
Centre and as such is properly chargeable to the Housing Revenue
Account. Members are asked to approve an additional release of
£0.020m from the HRA Reserve to support this. 
The overrspend reported to Council on 23rd August 2022 was £0.294
million. Projected spend at quarter 2 for 2022/23 has decreased by
£0.465 million principally due to reduced borrowing costs aligned to
lower forecast in-year capital expenditure. Projections now show an
underspend of £0.171 million against budget, as shown in appendix D. 
The HRA general reserve balance is projected to be £32.264 million at
31st March 2023 and is committed to finance existing investment plans
through to 2037/38. 
3     Report Implications 
3.1  Resource
There are no direct resource implications arising from this report. 
3.2  Digital
There are no direct digital implications arising from this report. 
3.3 Risk
The principal risks are around the issue of affordability, ensuring that
the investment in new build and the existing stock can be made
without having to impose unacceptable increases on weekly rents.
This is mitigated by the adoption of a long term financial strategy and
modelling which demonstrates that existing investment commitments
are sustainable. 
There is also the risk of capital spend being lower than projected due
to delays on projects, particularly in the current climate , this could
result in lower debt charges causing the Housing Revenue Account
Reserve balance to increase more than projected. 
3.4 Ensuring Equalities
There are no equality issues arising directly from this report. 
3.5 Additional Resource Implications
See Appendix A. 
Appendices Page 83 of 164

Page 84

4
Appendix A – Additional Resource Implications
Appendix B – Background Information
Appendix C - Capital Plan 2022/23
Appendix D – Revenue Account 2022/23 
Page 84 of 164

Page 85

5 
APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Not applicable 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
The report does not directly impact on Delivering Best Value. 
A.5 Involving Communities and Other Stakeholders 
The report does not directly relate to involving communities. 
A.6 Impact on Performance and Outcomes 
The report does not directly impact on Midlothian Council’s
performance and outcomes. 
A.7 Adopting a Preventative Approach 
The report does not directly relate to adopting a preventative approach. 
A.8 Supporting Sustainable Development 
The report does not directly relate to supporting sustainable
development. 
Page 85 of 164

Page 86

6 
APPENDIX B 
Background Papers/Resource Links 
HRA Capital Plan and Revenue Budget enclosed 
Page 86 of 164

Page 87

MIDLOTHIAN COUNCIL Appendix C
HOUSING REVENUE ACCOUNT CAPITAL PLAN 2022/23
Revised
Budget
2022/23
Actuals to
Date
Projected
Outturn
Variation
(Under)/Over
£'000 £'000 £'000 £'000
FUNDING
Grants
- Incentivising New Build 7,742 0 7,742 0
- Buy Backs Funding 880 250 880 0
Council Tax on Second Homes 96 0 96 0
Borrowing Requirement 45,124 14,999 45,124 0
TOTAL AVAILABLE FUNDING 53,842 15,249 53,842 0
APPROVED EXPENDITURE £'000 £'000 £'001 £'000
New Build Houses Phase 2, Phase 3 & Phase 4 41,034 11,773 41,034 0
Buy Backs 3,300 1,459 3,300 0
Aids & Adaptations 454 151 454 0
Environmental Improvements 1,000 0 1,000 0
BDHS Meters 1,300 0 1,300 0
Homelessness - Temporary Accommodation Provision 415 299 415 0
Scottish Housing Quality Standard 0
-Upgrade Central Heating Systems 1,673 410 1,673 0
-SHQS Repairs 4,666 1,157 4,666 0
TOTAL EXPENDITURE 53,842 15,249 53,842 0
Page 87 of 164

Page 88

MIDLOTHIAN COUNCIL Appendix D
HOUSING REVENUE ACCOUNT 2022/23  
Revised Projected Variation
Budget Outturn (Under)/Over
Average No of Houses 7,451               7,370              (81)
£000's £000's £000's
Repairs and Maintenance
General Repairs 6,356 6,712 356
Decant/Compensation 63 53 (10)
Grounds Maintenance 801 833 32
7,220 7,598 378
Administration and Management 5,332 5,332 0
Loan Charges 13,790 12,212 (1,578)
Other Expenses 2,702 2,985 283
TOTAL EXPENDITURE 29,044 28,127 (917)
Rents
Houses 31,950 31,143 807
Garages 617 617 0
Others 486 547 (61)
TOTAL RENTS 33,053 32,307 746
NET EXPENDITURE/(INCOME) (4,009) (4,180) (171)
Movement in HRA Reserve
Opening HRA Reserve (28,084)
Enhancement during 2022/23 as above (4,180)
Reserve Earmarked to fund capital investment plans (32,264)
Page 88 of 164

Page 89

1
Midlothian Council
15 November 2022
Early Learning and Childcare Funding Rate 2022-23
Report by Fiona Robertson Executive Director Children, Young People and
Partnerships
Report for Decision
1 Recommendations
Council is recommended to:
a. Maintain the current 2 year old rate of £6.90, whilst increasing the 3-5 year old rate
from £5.71 to £6.42 for both funded providers and childminders delivering Early
Learning and Childcare (ELC).
b. Backdate the increase in 3-5s rate to August 2022.
c. Give delegated authority to the Executive Director (Children, Young People and
Partnerships) to write to the Scottish Government (SG), on behalf of Council, to
seek clarity on future funding and assurance that the SG will provide the necessary
funds to allow Midlothian to pay funded providers a sustainable rate.
d. Review the funding rates for 2023/24 once the funding allocation from the Scottish
Government is confirmed.
2 Purpose of Report/Executive Summary
Following the Council Briefing on 14 November 2022, this report seeks a decision to
maintain the current rate paid to partner providers for 2 year olds, whilst applying an
increase to the 3-5 year old funding rate from August 2022 for the 2022/23 financial
year, which can be funded from existing carry-forward.  With the Scottish
Government’s (SG) funding methodology for ELC for 2023/24 onwards unavailable
and the 2022/23 funding gap estimated to be circa £11.084m, it is recommended that
the future rate be determined once the SG’s funding settlement is known.
Report Contact:
Fiona Robertson Fiona.Robertson@midlothian.gov.uk
Item 8.5
Page 89 of 164

Page 90

2 
3 Background 
3.1 When to increase the rate
In 2022 Ipsos MORI carried out a survey of the cost to provider settings and
childminders of delivering early learning and childcare. The funding rate discussed
below has been calculated on the basis of coming into effect from August 2022.  It has
been extrapolated from the results of the survey using inflation estimates since March
2022, as the survey was carried out before the cost of living crisis became as apparent
and inflation, and hence wage pressures, escalated. 
3.2 Whether to have separate rate for settings and childminders
Midlothian currently pays the same funding rate to settings and childminders (CM). 
With the very direct relationship between the funding rate and childminders’ incomes,
allied to the small number of funded ELC hours currently delivered by CM, continuing
to pay childminders the same rate as settings would not incur significant additional
expenditure for the council.  An increase in the funding rate may lead to an increase in
the number of active childminders, broadening the choice and flexibility of ELC
available to parents. 
3.3 What to increase the rate(s) to
Following the inflationary adjustment to the costs established by the survey and an
allowance for Return on Investment (ROI), a new sustainable rate for 3-5 year olds has
been calculated1.     
The Care Inspectorate staff to child ratio for 2 year olds is 1:5, whereas for 3-5 year
olds it is 1:8.  This means that 2 year olds require 60% more staff than 3-5 year olds,
and staffing constitutes nearly three quarters of providers’ operating costs. To account
for this, Midlothian currently applies a 21% adjustment to the 3-5s rate. This is
significantly higher than Edinburgh City (7%) and Scottish Borders (5%).  Therefore, it
is recommended to increase the 3-5s rate £6.42, while holding the 2s rate at current
levels (£6.90).  This would make both rates comparable to those approved at
Edinburgh City.  Applying this increases from August 2022 to March 2023 will incur an
additional funding requirement of circa £411k in financial year 2022/23.      
Current  Proposed % diff
2 year olds £6.90 £6.90 -
3-5 year olds £5.71 £6.42 12.40%
Total additional cost (Aug 22 - Mar 23)     £411,118 
1 Methodology was discussed in the Council briefing on 14 November and provided in Appendix A.
Page 90 of 164

Page 91

3 
3.4 Benchmarking
The table below presents the local benchmarking comparisons.  The rates presented
by Edinburgh City Council (from August 2022) and Scottish Borders Council (SBC,
backdated to August 2021) do not include meals.  If we add 40p onto these figures (as
an assumption) then it is clear that the Midlothian proposal is almost identical to
Edinburgh City and less than SBC and West Lothian (from August 2020) for 3-5 year
olds.  This table also provides the proportion of ELC places delivered by funded
providers in these neighbouring authorities.  We are aligned with the proportion of
funded providers for Edinburgh City and SBC, who have both increased their rate. 
3.5 Funding
The Scottish Government provides ring-fenced funding for the implementation of the
expansion from 600 to 1140 hours of funded ELC, initially increasing year on year until
full implementation from August 2021. The rest of the cost of the Early Years’ Service
is met by the allocation of funds from the Revenue Support Grant from Scottish
Government and the council’s other funding sources. The multi-year funding for 1140
hours is presented below, showing a £1.7m reduction in ring fenced revenue funding
from 21-22 to 22-23. 
2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Multi-year
Ring fenced
funding
£1.475m £6.942m £11.725m £13.125m £11.411m TBC 
The 26 May 2022 letter (see Appendices) from Alison Cumming, Director of ELC at the
Scottish Government to local authorities advised; 
“2022-23 represents an interim year for ELC funding. The ELC Specific Revenue Grant
will remain ring-fenced in the next financial year while we work together to agree the
annual quantum for 2023-24 onwards, taking into account changing costs and
population figures.” 
“Councils will work with partners, on the basis of the available evidence and within the
funding envelope available for ELC, to uplift rates for 2022-23 to ensure that they reflect
the costs of delivery (including inflationary increases), provide scope for reinvestment
(reflecting a measure of profit in a private sector setting or surplus in a third sector
organisation) and enable delivery of the Real Living Wage commitment. The level of
change in rates in 2022-23 will reflect evidence about local needs and circumstances,
and will be determined through robust and transparent processes that are supported
by local engagement. Rates must be affordable for local authorities within their overall
ELC budget.” 
LA 2s 3-5s Notes Proportion
Midlothian
(current) 6.90 5.71 Includes meals top-up 37%
Midlothian
(proposed) 6.90 6.42 Includes meals top-up 37%
Edinburgh 6.48 6.03 Plus £3.10 per meal 41.3% (NDNA)
Borders 6.55 6.21 Does not include meals 37% (NDNA)
West Lothian 6.80 6.80 Settings, includes meals 9.5% April 2020
West Lothian 6.30 6.30 Childminders, includes meals 0.6% April 2020
Page 91 of 164

Page 92

4 
The additional funding requirement for an increase in the sustainable rate for financial
year 2022/23, will be met by the early years carry forward.   
3.6 Future years
The use of the carry-forward noted above is a one-off and not recurring position. The
May 2022 letter also confirms that the Scottish Government intends to adopt a new
funding methodology for ELC for 2023/24 onwards.  However, we do not have details
of what this method will be or whether it will result in an increase or decrease to the
funding allocated to Midlothian. 
With the increase to the real Living Wage announced in September 2022, and
circumstances that are unknown, such as details of the proposal to cap gas and
electricity costs to businesses, the continued impact of the war in Ukraine, and the final
budget position of the UK Government, the proposed rate will need to be reviewed for
the 2023/24 budget.  However, with uncertainties around the funding methodology and
the allocated budget to Midlothian, it would be prudent to determine the future rate
once these uncertainties are resolved. 
To support the future budgeting activity, we recommend that delegated authority is
given to the Executive Director (Children, Young People and Partnerships) to write to
the Scottish Government, on behalf of the council, to seek clarity on future funding and
assurance that the SG will provide the necessary funds to allow Midlothian to pay
funded providers a sustainable rate.   
As an overview, any review of the rate must be sustainable for authorities in terms of
the budgets available and will have to take account of the following considerations:
 The rate does not have a detrimental effect on the local authority’s ability to
continue to pay for the service in the long-term.
 The wider package of ‘in-kind benefits’, which are separate to the sustainable rate,
available to the funded provider as part of their contract with the local authority.
 The rate does not need to be cross-subsidised by parents and carers through
charges for non-funded hours. 
3.7 Risks
The information provided in this paper recognises that while we must calculate a
sustainable rate for our funded providers, the application of that rate must be affordable
for the authority.  With budget shortfalls and funding uncertainty, it is necessary to
consider the implications associated with increasing and not increasing the rate. 
Risks if the rate IS increased:
 Irrespective of the rate chosen, there will be an increased cost to the authority.
 While an increase may be funded by underspend in the short-term, there are
significant unknowns about the Scottish Government’s future funding methodology
and allocation.  This may lead to an even larger funding gap.
 Other local authorities have reported using their reserves to fund the sustainable
rate increases.  This is not financially sustainable practice. 
Page 92 of 164

Page 93

5 
Risks if the rate is NOT increased:
 Neighbouring authorities with the same proportion of funded providers have
increased their rates.  Not doing so will lead to reputational damage and potential
scrutiny from the SG.
 Funded providers are required to pay the real Living Wage.  If they do not have
the financial support to do so, they may have to withdraw from partnership as they
will not meet the National Standard.
 Analysis has shown that costs are increasing for our funded providers; not
supporting our partners may lead to a loss of local businesses and associated
employment, direct and indirect.
 The local authority does not currently have the physical capacity or infrastructure
to be able to mitigate against the risk of losing our partner providers.
 If we lose some of our funded providers, there will be cost implications associated
with increasing and transforming our learning estate to create a suitable early
year’s environment.
 Losing funded providers will impact upon the council’s ability to provide parents
with choice, flexibility and affordability for funded ELC, three of the four tenets of
1140 hours.  
Page 93 of 164

Page 94

6 
4 Report Implications (Resource, Digital and Risk) 
4.1 Resource 
If Council decides to approve an increase in the funding rate for 3-5 year olds, the
additional funding requirement of circa £411k for financial year 2022/23 will be met by
the early years carry forward, although it is important to note that this is a one-off and
not recurring position. Budgets for future years will be set taking account of the revised
rate. 
4.2.1 Digital 
There are no digital implications arising from this report. 
4.2.2 Risk 
There are two interconnected risks addressed by this report. The council has a
legislative duty to provide ELC places to eligible children. If the ELC funding rate to
funded providers is set too low, providers may be unsustainable and capacity will
reduce, thereby the council’s ability to meet its duty will be at risk. The council may
either fail to meet this duty or will incur additional costs while seeking to provide
substitute places through other routes. This risk must be balanced against the
budgetary pressure upon the council.  While the authority has an obligation to provide
a sustainable rate to the funded providers, it needs to be affordable. As stated by the
Scottish Government ‘the rate does not have a detrimental effect on the local
authority’s ability to continue to pay for the service in the long-term’. 
4.3 Ensuring Equalities (if required a separate IIA must be completed) 
An Integrated Impact Assessment was carried out on the potential impact of setting
rates that are not sustainable to either providers or to the council. It identified that
setting the rate(s) too high would negatively impact upon other services provided by
the council, though which groups might be affected would be determined by how the
budget was balanced. Setting the rate(s) too low would disproportionately negatively
impact young people and children, women (particularly female single parents and the
predominantly female workforce in the ELC sector), people with a disability and those
vulnerable to falling into poverty. A reduction in settings and flexibility may increase
travel distances for parents and carers, potentially increasing CO2 and particulate
emissions. 
4.4 Additional Report Implications (See Appendix A) 
See Appendix B 
Page 94 of 164

Page 95

7 
APPENDIX A – Sustainable Rate Methodology 
On behalf of local authorities, CoSLA commissioned IPSOS MORI to conduct a survey
of the costs incurred by funded providers to deliver childcare. The survey was carried
out in February and March 2022. The data produced was at Regional Improvement
Collaborative (RIC) level. Midlothian is a member of the South East Improvement
Collaborative (SEIC), along with East Lothian, Edinburgh, Fife and Scottish Borders
councils. 
The Scottish Government states in the guidance for setting sustainable rates that: 
Local authorities must act transparently, regardless of the process chosen, and make
available details of the process. 
The current rate was an estimate calculated by SG in 2018 for the rate in 2020, using
data collected through an IPSOS MORI survey carried out in 2016.  There have been
significant unforeseeable events causing upward pressures on salaries, utilities etc.
(pandemic, labour market competition, Russia’s invasion of Ukraine and the cost of
living crisis) since that time. The 2022 IPSOS MORI survey shows that costs are now
above Midlothian’s current funding rate. 
The SG estimate of the hourly rate for 2020 did not include payment for meals. As a
result, Midlothian added a 40 pence per hour top-up to the hourly rate to cover meals.
The 2022 IPSOS MORI cost data includes the costs associated with providing meals,
therefore, the sustainable rate calculated from it includes meals. 
Angus Council provided a detailed breakdown of how it calculated its sustainable rate,
extrapolating the IPSOS MORI survey data using publically available statistical
information on increases in costs and applying a factor to account for the different staff-
to-child ratios between three to five year olds and two year olds. For almost all cost
elements it used the mean costs found by the survey rather than median or a
percentile. It then applied an 8% Return on Investment (ROI) (discussed later).   
The Angus method has been applied to the SEIC data provided to Midlothian by IPSOS
MORI. In order to make these costs reflect current economic conditions, we made the
following adjustments: 
Cost adjustment Adjusted
by
Proportion
of costs
Staff costs aligned to real Living Wage (rLW) April 2022 rLW  72%
Utilities Ofgem  2%
Other costs, where appropriate CPIH 26%
TOTAL  100% 
Following the inflationary adjustment to the costs, an 8% Return on Investment (ROI)
rate is applied to produce a new sustainable rate for 3-5s.   
Page 95 of 164

Page 96

8 
Return on Investment 
The cost per hour used to calculate the sustainable rate proposed was the mean
(average) cost figure found by the IPSOS MORI survey.  This means around half of
providers will experience higher costs that the mean funding rate calculated from the
survey2. Clearly, therefore, if the council were to set the sustainable rate at this cost
per hour half of the providers would either need to charge parents more for unfunded
hours in order to meet the funding shortfall, or could be unsustainable and ultimately
close. This could have a significant impact upon children and families and the council’s
ability to meet its legislative duty.
Providers do not operate solely to break even however, an ROI rate of 8% has been
applied to the cost per hour. As stated in the IPSOS MORI paper “private companies
are unlikely to continue to operate if they are not generating a profit in addition to their
costs, although actual/desired profit margins will vary widely”. This is also
acknowledged by SG in the guidance: 
“Ensuring a sustainable rate in the current economic climate is challenging. For private
and third sector providers, this means an adequate return on investment and being
able to recruit and retain staff. For local authorities, it means that the service reflects
high quality ELC provision and affordability.” 
Due to the variability of costs discussed above, only providers with costs matching the
mean figure will have an 8% ROI rate if the sustainable rate is set as proposed.  Around
half of providers will be above this figure and around half will have a lower rate, with
some potentially making a loss.  As well as the mean cost figures, the IPSOS MORI
survey provided 80th percentile cost figures. The 80th percentile is where the cost per
hour of delivering childcare at 80% of providers will be less than this figure and they
will make, to a greater or lesser degree, a profit, and at 20% it costs more and they will
make a loss.   
2 Assuming that the providers who completed the survey are representative of all providers
Page 96 of 164

Page 97

9 
APPENDIX B – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
• Individuals and communities have improved health and learning outcomes
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
This report has been considered from a Best Value perspective, to maintain a
sustainable position for our providers and support quality provision of ELC in line with
the National Standard, enabling the council to meet its statutory duty and delivering
flexibility and choice to parents and carers. 
A.5 Involving Communities and Other Stakeholders 
The development of this rate has been driven by the needs of our community, and will
be delivered in partnership with funded providers.  
Page 97 of 164

Page 98

10 
A.6 Impact on Performance and Outcomes 
The sustainable rate is required to ensure that the authority has the capacity and
resource to effectively delivery 1140 hours to our children, meeting the council’s
statutory duty. 
A.7 Adopting a Preventative Approach 
Providing a rate that is sustainable is, by its very nature, preventative. The provision of
high quality ELC for eligible children is also preventative in terms of supporting the
development of children, improving attainment and learning outcomes. 
A.8 Supporting Sustainable Development 
Not applicable. 
Page 98 of 164

Page 99

Midlothian Council
Tuesday 15 November 2022 
Appointment of Members in Accordance with the Scheme of
Administration – Midlothian Twinning Association 
Report by Kevin Anderson, Executive Director Place 
Report for Decision 
1 Recommendation
The Council is invited to consider the appointment of an additional
named member to the Midlothian Twinning Association Committee. 
2 Purpose of Report/Executive Summary 
In accordance with Standing Order 4.1 (x) consideration requires to be
given by Council to the appointment of representatives to Joint
Committees, Outside Bodies and other partnership working. 
Date:  25 October 2022
Report Contact:  Kevin Anderson, Executive Director Place
Email:  Kevin.Anderson@midlothian.gov.uk 
Page 99 of 164

Page 100

2
3 Main report          
Midlothian Twinning Association is an outside organisation consisting of            
volunteers with an interest in establishing and maintaining links in            
Europe. 
The former Midlothian District Council had twinning arrangements in            
place with Kreis Heinsberg in Germany and Komarom- Esztergom in            
Hungary. Dalkeith in Midlothian has been twinned with the town of            
Jarnac in Charente, France since 1960 with other towns/villages            
twinned with towns in France. Twinning has continued following the            
formation of Midlothian Council in 1996 
At its meeting of 24 May 2022, Council approved the appointment of               
Councillor Debbie McCall, Provost; Councillor Peter Smaill and            
Councillor Margo Russell to the Midlothian Twinning Association. 
Four places are available to the Council on the Midlothian Twinning                                            
Association and following an approach by office-bearers of the            
Association this report requests Council to consider the appointment of 
a named additional member for the available remaining place. 
4. Report Implications (Resource, Digital and Risk)
4.1 Resource
None
4.2 Digital 
There are no digital implications related to this report.
4.3 Risk
In accordance with Standing Order 4.1(x), this report invites the Council
to appoint Members to Joint Committees and Outside Bodies etc.          
There are no risk implications arising directly from this report.
4.4 Ensuring Equalities 
An equalities impact assessment has not been required in connection
with this report as there are no equality implications arising directly
from this report.
4.5 Additional Report Implications 
See Appendix A 
Page 100 of 164

Page 101

3
Appendix A - Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Not applicable 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
There are no direct implications related to this report. 
A.5 Involving Communities and Other Stakeholders 
The report does not directly relate to involving communities. 
A.6 Impact on Performance and Outcomes   
Not applicable 
A.7 Adopting a Preventative Approach 
Not applicable 
A.8 Supporting a Sustainable Development 
Not applicable
Page 101 of 164

Page 102

Page 102 of 164

Page 103

Midlothian Council
15 November 2022
Item 8.7 
Chief Social Work Officer – Annual Report 2021-2022 
Report by Joan Tranent, Chief Social Work Officer 
Report for Decision 
1 Recommendations
Council is asked to: 
• Note the Chief Social Work Officer’s Annual Report for 2021-22 
• Agree the Chief Social Work Officer should place a copy of the
annual report on the Council website. 
2 Purpose of Report/Executive Summary
This report provides Council and the IJB with the annual report of the
Chief Social Work Officer (CSWO). The shortened report provides both
Council and the IJB with a high level overview of key issues and
challenges as a result of Covid-19. 
Date:  October 2022
Report Contact: Joan Tranent
Joan.tranent@midlothian.gov.uk 
Page 103 of 164

Page 104

2 
3 Background
The requirement that every local authority should have a professionally
qualified Chief Social Work Officer is contained within Section 3 of the
Social Work (Scotland) Act 1968. The particular qualifications are set
down in regulations. This is one of a number of officers, roles or duties
with which local authorities have to comply. In Midlothian Council the
role of Chief Social Work Officer is held by the Chief Officer Children’s
Service, Partnerships and Communities
The annual reports of all CSWO’s are submitted to the Office of the
Chief Social Work Advisor at the Scottish Government in order that a
national overview report can be produced. 
This year’s report offers a high level overview of some of the great work
undertaken despite the continued challenges that social work and social
care staff faced as Covid-19 remained a very live and current issue.  
It was very much a shared endeavour by all staff across the council and
the health and social care partnership including our 3rd sector partners
that prioritising the safety and health and wellbeing of those who were
most in need within our communities was our number one priority.   
4 Report Implications (Resource, Digital and Risk)
This report does not make recommendations, which entail the allocation
of resources. 
4.1 Resource
None 
4.2 Digital 
None 
4.3 Risk
CSWO’s have well-developed arrangements in place to assess and
manage risk both within social work services and in inter-agency
contexts. This has been particularly prevalent during the ongoing Covid-
19 pandemic where as CSWO with a children and families background I
have had to liaise with colleagues in health and social care to support
the roll out of robust governance and oversight around high risk areas
such as care at home and residential care homes settings. Having
positive professional working relationships with a clear understanding of
each other’s roles has reduced any potential risk. 
4.4 Ensuring Equalities (if required a separate IIA must be completed)
This report does not recommend any change to policy or practice and
therefore does not require an Equalities Impact Assessment. 
Page 104 of 164

Page 105

3
4.4 Additional Report Implications 
See Appendix A 
APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan
This report focuses on the delivery of statutory functions rather than
strategic development of social work services. There are, however,
clear links to business transformation and partnership arrangements in
so much as the integrity of the CSWO has been safeguarded and
designed into organisational change. 
A.2 Key Drivers for Change
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value
The report highlights the involvement efforts taken across all areas of
social work and social care to deliver best practice. 
A.5 Involving Communities and Other Stakeholders
The report highlights good practice where the involvement of users of
services have been sought in the development of services. 
A.6 Impact on Performance and Outcomes
The report highlights performance levels across the services and how a
commitment to improve outcomes. 
Page 105 of 164

Page 106

4
A.7 Adopting a Preventative Approach
It has been critical to adopt a preventative approach across our
services and this report highlights these areas of work. 
A.8 Supporting Sustainable Development
Not applicable 
Appendix B – Chief Social Work Officer Annual Report (2021-22) 
Page 106 of 164

Page 107

Midlothian Council   
15 November 2022
Item 8.8 
Midlothian Strategic Housing Investment Plan 2023/24 - 2027/28 
Report by Kevin Anderson, Executive Director - Place 
Report for Decision 
1 Recommendations 
Council is recommended to approve the appended Strategic Housing
Investment Plan (SHIP) 2023/24-2027/28, which has been submitted to
the Scottish Government on 28 October, 2022 in order to meet the
required dateline, with the proviso this is subject to approval by
Council. 
2 Purpose of Report/Executive Summary 
This report summarises the key points set out in Midlothian’s Strategic
Housing Investment Plan (SHIP) 2023-28, which details the priorities
for investment in new affordable housing in Midlothian. 
Date: 14 October 2022 
Report Contact: Fiona Clandillon, Head of Development
email: fiona.clandillon@midlothian.gov.uk 
Page 107 of 164

Page 108

2 
3 Background/Main Body of Report 
3.1 The Scottish Government requires all local authorities to prepare a
SHIP that identifies the main strategic investment priorities for
affordable housing over a 5 year period. This important document is
required on an annual basis as the Scottish Government requires detail
on the Affordable Housing Supply Programme in each regional area
towards meeting the national target of supporting the development of
110,000 new affordable homes. The SHIP sets out Midlothian Council’s
approach to promoting affordable housing investment and meeting
housing supply targets identified in the Strategic Development Plan for
Edinburgh and South East Scotland.
3.2 The delivery of more affordable housing remains a high priority for
Midlothian Council, which is undertaking a development programme of
1,000 new council houses. 
3.3 While the SHIP sets out a recent increase in the number of lettings, in
part as a result of the Midlothian Council’s most recent new build
programme, it also records an 8% increase in the number of
households on the waiting list. Despite significant levels of investment
in new housing, there is still a shortage against the demand for
affordable housing in Midlothian with 4,237 households now on the
Council’s Housing List.
3.4 Midlothian Council has 11 projects named in the SHIP which are not
yet on site. Partner Registered Social Landlords (RSLs) have an
additional 21 projects listed in the SHIP. Finally, there are a further 8
projects where the lack of an affordable housing provider has not been
confirmed. It is anticipated that these will be delivered by Midlothian
Council. However, due to a lack of certainty surrounding local authority
rent increases at this time, due to existing Scottish Government
legislation in the response to the Cost of Living Crisis, it is not certain
that these sites can be funded through the Housing Revenue Account.
Until a rent setting strategy is agreed, the means to deliver these sites
must therefore remain unconfirmed. 
3.5 A total of £127.520 million of Scottish Government grant funding would
be required by the Council and RSLs to deliver the identified units over
the next 5 years. This is an increase of £22.612 million from the
previous Strategic Housing Investment Plan.
3.6 Due to the uncertain future of the rent setting strategy, the number of
confirmed Midlothian Council new build properties to be built over the
course of the SHIP has reduced from 1,413 (in 2022/23 – 2026/27) to
1,007. This is in contrast to the number of planned RSL new build
properties which have increased from 832 to 1,144. 
4 Report Implications (Resource, Digital and Risk) 
4.1 Resource 
It is anticipated that the Scottish Government will part-fund these
homes through grant provided via the Affordable Housing Supply
Programme. Grant levels were uplifted in 2022 by approximately 32%,
Page 108 of 164

Page 109

3
however this uplift was outpaced by increases in inflation associated
with the rising cost of materials and labour. Those elements not funded
by grant are funded through the Housing Revenue Account, where
delivered by Midlothian Council, or through affordable housing RSL
partners. 
As outlined in the SHIP, any projects not currently funded through
existing commitments cannot be delivered by Midlothian Council, as
there are insufficient reserves in the Housing Revenue Account. This
will need to be resolved prior to funding projects not currently in the
committed programme. Rent consultation commences in
Autumn/Winter 2022 and the results will be presented to Council in
February 2023. This will determine the funding to be earmarked for the
future delivery of the Midlothian Council new build programme. 
It should be noted that the Scottish Government may extend the rent
freeze currently in force or impose a cap on rent increases. 
4.2 Digital 
NA 
4.3 Risk 
If the Council does not support the development of new affordable
housing, the level of housing need will increase with negative
consequences for Midlothian’s communities. 
4.4 Ensuring Equalities (if required a separate IIA must be completed) 
Equality is central to all housing and housing services delivery. An
Integrated Impact Assessment (IIA) has been undertaken on the Local
Housing Strategy 2021-26 to ensure that the needs of local
communities have been fully considered. The SHIP reflects identified
needs and draws on findings from the IIA when considering the
implications flowing from the translation of strategic aims into housing
policies. 
4.5 Additional Report Implications (See Appendix A) 
See Appendix A 
Appendices 
Appendix A – Additional Report Implications
Appendix B – Background information/Links 
Page 109 of 164

Page 110

4
APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
This Strategy aligns with Midlothian’s Single Midlothian Plan and with
corporate priorities. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
x   Sustainable 
Transformational
x    Preventative
x    Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
x   Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
N/A 
A.5 Involving Communities and Other Stakeholders 
Extensive consultation was carried out for the LHS involving the input
of key stakeholders, including local organisations such as housing
associations and private landlords as well as the wider community. 
During consultation, it was widely recognised that investment in
affordable housing a key priority. All developing Housing Associations
have discussed their development plans with Council Officers. Private
sector developers were also given the opportunity to discuss their
future development plans with Council Officers. 
A.6 Impact on Performance and Outcomes 
The SHIP supports the following Local Housing Strategy (LHS)
Outcomes, these are: 
• Households have improved housing options across all tenures. 
Page 110 of 164

Page 111

5
• Homeless households and those threatened with homelessness
are able to access support and advice services and all
unintentionally homeless households will be able to access settled
accommodation. 
• The condition of housing across all tenures is improved. 
• The needs of households with particular needs will be addressed
and all households will have equal access to housing and housing
services. 
• Housing in all tenures will be more energy efficient and fewer
households will live in or be at risk of fuel poverty. 
A.7 Adopting a Preventative Approach 
Setting out a programme for development in the SHIP enables the           
investment of affordable housing to be carried out in a balanced             
approach in order that any investment takes into account the needs of             
the community.  This includes those with particular needs such as extra             
care housing for older people, wheelchair housing or those Complex             
Physical or Learning Disabilities where provision of suitable housing             
would require less resourcing in comparison to traditional models of             
care. 
A.8 Supporting Sustainable Development 
An SEA Pre Screening was undertaken in respect of the Strategy,
following this it is expected that a full screening will not be required.  In
addition, good practice in relation to energy efficiency and sustainability
is highlighted in the document. 
Page 111 of 164

Page 112

6 
APPENDIX B 
Background Papers/Resource Links 
Midlothian Strategic Housing Investment Plan 2023/24 - 2027/28 
Page 112 of 164

Page 113

Midlothian Council 
Strategic Housing Investment Plan
2023/24 - 2027/28 
Page 113 of 164

Page 114

2 
Front page photographs
Top: Completed homes by Midlothian Council, Bonnyrigg
Bottom: Completed homes by Taylor Wimpey for Melville Housing at Pentland Green, Bilston 
Page 114 of 164

Page 115

3 
Table of Contents   
1. Introduction and Strategic Links                     p.4                                     
2. Profile of Midlothian                                        p.5                                                   
3. Partnership Working                                       p11 
4. Investment Priorities & Resources                 p.14                                    
5. Housing Infrastructure Fund                           p.23 
6. Conclusion                                                      p.24                                                 
Appendix 1                 
Page 115 of 164

Page 116

4 
1 Introduction and Strategic Links 
In March 2021, the Scottish Government published its first long-term housing strategy
‘Housing to 2040’ which set an ambition to deliver a further 110,000 affordable homes
by 2032, with at least 70% of these for social rent.  Meeting this target is ambitious
and will require increased investment by the Scottish Government, Local Authorities
and Registered Social Landlords and a step change in the pace of housebuilding in
order that it is achieved. The delivery of more affordable housing remains a high
priority for Midlothian Council which is undertaking a development programme of 1,000
new council houses in Midlothian. 
The purpose of Midlothian’s Strategic Housing Investment Plan (SHIP) is to set out
strategic investment priorities for affordable housing over a 5 year period to achieve
the outcomes set out in the Local Housing Strategy (LHS). The SHIP priorities are
clearly aligned with the LHS Outcomes Action Plan 2021-2026 which can be accessed
here:
Housing strategy and performance | Midlothian Local Housing Strategy 2021-2026 
The strategic housing priorities of the SHIP are aligned and consistent with the
priorities and outcomes within the Rapid Rehousing Transition Plan and the annual
updates to the document. The latest Rapid Rehousing Transition Plan can be found
here:
Rapid Rehousing Transition Plans | Rapid Rehousing Transition Plan 2022/23 - 2023/24
(midlothian.gov.uk) 
The SHIP is the key document for identifying strategic housing projects towards
meeting the Government’s 110,000 affordable housing target. This document is
updated annually to present up to date information on affordable housing investment
plans. 
The SHIP provides an opportunity for the Council to: 
• Set out investment priorities for affordable housing and identifies how these will
be delivered
• Identify the resources required to deliver these priorities
• Involve key partners in the delivery of new affordable housing. 
The SHIP will continue to inform the allocation of resources from the Scottish
Government’s Affordable Housing Investment Programme, which primarily supports
the delivery of affordable housing via the Council and Registered Social Landlords. In
addition, other funding streams that support investment in affordable housing have
also been evaluated.
Local Child Poverty Action Report
The latest report, published in 2022, notes that 24% of children in Midlothian are living
in poverty. A target has been set to reduce this level to fewer than 10% of children
living in relative poverty by 2030. A key driver for reducing the level of poverty is
reducing the cost of living for families. The Strategic Housing Investment Plan will
support this by increasing the total number of affordable homes in Midlothian. For
many households this will result in significantly reduced rental payments and an
improved quality of life, for example, by alleviating overcrowding in a household and
Page 116 of 164

Page 117

5 
providing a home which costs less to heat. The SHIP is aligned with the strategic
housing priorities of the Midlothian Local Child Poverty Action Report. Key progress
delivered as a result of the SHIP for low income families will be captured within the
Local Child Poverty Action Report 2023. 
2 Profile of Midlothian 
Housing Market Areas (HMAs) 
Midlothian is situated within the Edinburgh and South East of Scotland City Region
area and is therefore influenced by the wider region in terms of where households
choose to live and work. The table below shows the two HMAs along with their
corresponding towns and villages, while the map shows the geographical spread of
the HMAs. The Midlothian West (A) HMA is denoted in purple while the Midlothian
East (B) HMA is denoted in blue colour. 
Table 2.1: Main Settlements in Housing Sub Market Areas
Midlothian West (A)  Penicuik, Loanhead, Bilston, Roslin, Straiton,
Auchendinny 
Midlothian East (B)  Dalkeith, Bonnyrigg, Gorebridge, Rosewell, Mayfield,
Easthouses, Pathhead, Newtongrange,
Danderhall/Shawfair 
Figure 2.1: Map showing Midlothian Housing Sub Market Areas 
Page 117 of 164

Page 118

6 
The Housing Market Areas are the core development areas in Midlothian which
concentrates new development in Midlothian on: 
• The A701 Corridor; 
• The A7/A68/ Borders Rail Corridor; and 
• Shawfair   
Most of the affordable housing units to be delivered are in the Midlothian East area,
largely due to the population, and therefore housing need, being greater in this housing
market area. The Danderhall/Shawfair area will see a significant level of new
development with an allocation of land for around 4,000 houses, employment land, a
town centre including a supermarket and school provision. The initial new sites for
development have been completed with further sites under construction. 
Housing Tenure in Midlothian
The most common housing tenure in Midlothian is owner occupied housing (67%)
followed by social rented housing by the council or housing association (24%). In
addition private rented homes comprise 9% of the housing stock.1 
Social Housing Demand
An analysis of social housing in Midlothian shows: 
• In the mainstream stock (ie. excluding temporary accommodation) there are 6,806
Council homes in Midlothian. The majority of stock is 2 bed (3,728 units), followed
by 3 bed (1,863 units). There are fewer 1 bed homes (892 units) and 4 bed and
larger homes (323 units).
• There are currently 3,416 RSL properties in Midlothian. Table 2.2 below, shows
how many properties each landlord has.  
• One and two bedroom properties are most in demand from the Housing List; 19%
of applicants are waiting for one bed homes and 64% of applicants are waiting for
two bed homes. Only 16% of Housing List applicants require 3 and 4 bed homes. 
Table 2.2: Number of Registered Social Landlord (RSL) properties in Midlothian2
Registered Social Landlord (RSL) Number of
properties
Melville Housing Association 2010
Castle Rock Edinvar Housing Association 1075
Bield Housing Association 116
Dunedin Canmore Housing Association 98
Trust Housing Association 35
Viewpoint Housing Association 34
Blackwood Housing Association 23
Link Housing Association 20
Ark Housing Association 5 
1 Scottish House Condition Survey: Local Authority Analysis 2017-2019 - gov.scot
(www.gov.scot)
2 Scottish Housing Regulator October 2022
Page 118 of 164

Page 119

7 
Chart 2.1 below, shows the number of council lets in recent years.  It shows that
between 2015/16 and 2021/22 allocations have increased by 58% due to changes to
the Housing Allocation Policy and the number of new build completions in these years.
It is expected than the annual number of lets will increase significantly in future years
as a result of the new build programme. 
Chart 2.1: Midlothian Council Lettings 
Chart 2.2 shows that the number of households on Midlothian Council waiting lists
increased by 8% between 2021 and 2022. The ‘Choice’ waiting list was removed in
2020 which resulted in a sharp reduction in waiting list numbers rather than a lessening
of demand for social housing which is evident in the number of households currently
waiting for housing. The Choice List applicants did not have any housing or medical
needs but a preference to move home, with other housing options available to facilitate
that choice. 
0
50
100
150
200
250
300
350
400
450
500
2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22
No. of Midlothian Council lets
Page 119 of 164

Page 120

8 
Chart 2.2: Number of Households on Midlothian Council Housing List 2018 –
2022 
Chart 2.3 below shows the number of homeless applications received by Midlothian
Council since 2015/16. It clearly shows a sharp reduction in the number of applications
since 2017/18 (18%) as a result of actions contained within the Rapid Rehousing
Transition Plan (see p14 for more details). 
Chart 2.3: Number of Homeless Applications per year 
3400
3600
3800
4000
4200
4400
4600
4800
2018 2019 2020 2021 2022
No. of households on Midlothian Council waiting lists
0
100
200
300
400
500
600
2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22
No. of Homeless Applications
Page 120 of 164

Page 121

9 
Affordable Housing Development in Midlothian
Table 2.3 shows the level of investment in new affordable homes in Midlothian since
2006 (when the Council began building new homes again). It shows that 1,238 council
homes have been provided, and a total of 1,739 council and RSL affordable units have
been built overall. It should be noted that these figures report completions by calendar
year up to June 2022 and don’t include open market purchases or shared equity
purchases which have been recorded seperately. 
Table 2.3: New Affordable Housing in Midlothian since 20063
Year of completion No. of completed
Council units
No. of completed RSL
units (Social Rent and
Mid Market Rent)
2006 0 19
2007 28 12
2008 172 42
2009 237 10
2010 88 20
2011 160 33
2012 170 121
2013 76 6
2014 0 20
2015 48 0
2016 41 28
2017 87 0
2018 0 103
2019 10 39
2020 31 0
2021 90 48
Total 1238 501 
3 Housing statistics quarterly update: new housebuilding and affordable housing supply -
gov.scot (www.gov.scot)
Page 121 of 164

Page 122

10 
Open Market Purchases
Midlothian Council has an Open Market Purchase Scheme whereby ex-council
properties are purchased and returned to housing stock. Midlothian Council receives
funding towards each Open Market Purchase from the Scottish Government. Table
2.4 below details the number of Open Market Purchases carried out in recent years. 
Table 2.4: Number of Open Market Purchases4
Financial year No. of Open Market Purchases
2017/18 7
2018/19 13
2019/20 42
2020/21 14
2021/22 22 
Open Market Shared Equity
A number of Midlothian residents have been able to purchase affordable homes using
the Scottish Government’s Open Market Shared Equity Scheme (OMSE) whereby
purchasers pay for the biggest share of a property and the Scottish Government hold
the remaining share under a shared equity agreement. Table 2.5 below shows the
number of successful home purchases in Midlothian using the Open Market Shared
Equity Scheme (and predecessor schemes which operated similarly). 
Table 2.5: No. of OMSE home purchases in Midlothian5
Financial Year No. of OMSE home purchases
2006/07 45
2007/08 62
2008/09 8
2009/10 41
2010/11 28
2011/12 3
2012/13 13
2013/14 42
2014/15 53
2015/16 93
2016/17 126
2017/18 104
2018/19 72
2019/20 16
2020/21 13
2021/22 15
Total 734 
4 Midlothian Council Housing Strategy and Performance statistics
5 Scottish Government More Homes Division
Page 122 of 164

Page 123

11 
3 Partnership Working 
Partnership working is crucial to the delivery of high quality housing and housing
related services across all tenures in Midlothian. As part of the development of this
SHIP, Council Officers have engaged and consulted with all delivery partners on their
proposals and priority projects. 
In order to identify suitable investment priorities council officers have worked with the
Scottish Government, Housing Associations, tenants groups, private developers and
colleagues in the planning, finance, estates and construction teams to determine the
level of housing need in the region, the level of demand for different tenures of
affordable housing and the mix of suitable house sizes and types in order to agree a
five year programme of development, informed by the current housing needs and
demand assessment (HoNDA) and the drafted National Planning Framework 4
(NPF4). 
The development priorities in the SHIP will be monitored through a number of ways
including by:
• Monitoring and reviewing of the actions in the Local Housing Strategy
• Annual assessment of the Council’s Housing Supply Targets
• Annual assessment of RSLs’ housing delivery
• Monitoring of housing need and demand.
• Reports and returns submitted to the Scottish Government 
Health and Social Care
Housing providers in Midlothian work collaboratively with health and social care
colleagues to ensure that housing provision in Midlothian can better meet the needs
of households who may require specialist housing provision to be able to live
independently. The types of outcomes that this will facilitate include: 
• Increased specialist housing provision as a result of improved understanding of
the future needs of the population, such as developing extra care housing which
provides an alternative to living in a care home for some people.
• Identification of the level of need for, and funding of, adaptations to ensure that
people living in private sector housing and council housing are able to continue
to live independently.
• Improving the health outcomes for homeless households, many of whom
currently have poorer levels of physical health and mental health than the
general population.
• Taking action to improve the energy efficiency of housing and reducing fuel
poverty which would lessen the risk to a household’s health and wellbeing. 
Page 123 of 164

Page 124

12 
More information is contained in the Midlothian Health and Social Care Partnership
Strategic Plan 2022-2025, available here:
What we do Information - Midlothian Health and Social Care Partnership 
Local Housing Strategy 2021-2026
The purpose of Midlothian’s Strategic Housing Investment Plan (SHIP) is to set out
strategic investment priorities for affordable housing over a 5 year period to achieve
the outcomes set out in the Local Housing Strategy (LHS). Extensive consultation work
was carried out in the preparation of the LHS and therefore to set the outcomes within
the document. Stakeholders included:
• Tenants     
• Waiting list applicants
• Residents
• Registered Tenants Organisations
• Resident and Tenants Groups
• Midlothian Tenants Panel
• Registered Social Landlords
• Shelter Scotland
• Home Energy Scotland
• Changeworks 
Consultation methods included:
• Social media
• Surveymonkey
• Microsoft Teams virtual consultation meetings
• Zoom virtual consultation meetings 
Initially stakeholders were provided with some background information on Local
Housing Strategies and the broad areas to be examined and discussed. These areas
were revisited throughout the development of the strategy at different points
throughout the engagement process. Stakeholders were provided with the draft
document for the final consultation process along with key challenges to prioritise for
the duration of the Local Housing Strategy and thus for the Strategic Housing
Investment Plan. 
Edinburgh and South East Scotland City Region Deal
The Edinburgh and South East Scotland City Region comprises the six local
authorities of City of Edinburgh, Fife, East Lothian, Midlothian, Scottish Borders and
West Lothian. Officers from these Councils collaborate with the UK and Scottish
Governments respectively to deliver a transformational and inclusive city deal for the
region which will attract investment of up to £1.1 Billion over 15 years. This includes
investment and collaboration on housing. Housing is included within the City Region
Deal as it is recognised as being an area of pressure but also an opportunity for
accelerated economic growth while reducing social exclusion. 
All Councils in the South East of Scotland face the same pressures in addressing
housing need with the recent housing need and demand assessment for the region
Page 124 of 164

Page 125

13 
estimating at least 67,000 new homes are required by 2030, with the majority of need
being for households who cannot buy or rent at market prices. 
Key housing investment areas in Midlothian that are being supported through the City
Region Deal include:
• Supporting a 10 year affordable housing programme across the region with
Scottish Government grant funding.
• Supporting local authority borrowing and share financing risk of infrastructure
delivery for key development sites.
• Provision of a £50 Million housing infrastructure fund of predominantly private
sector loans to be spent on projects that will unlock housing in strategic
development sites across the region.
• Collaborating to develop innovative approaches to increasing the use of offsite
construction methods.
• The potential to establish a council-owned regional housing company to deliver
mid-market and private rented sector housing. 
Edinburgh & South East Scotland Housing Demonstrator Programme
To take forward the opportunity to increase the use of offsite construction methods,
the Edinburgh & South East Scotland Housing Demonstrator Programme seeks to
create a programme of housing that will be delivered to standardised typologies and
performance standards with the use of offsite construction processes for a pipeline of
sites across the city region. 
Midlothian Council undertook a review of its garage and lock up sites as a potential
source of future housing sites. From this review, and a wider look at land in Council
ownership that had potential for housing development, a number of sites were put
forward for further assessment as part of the feasibility stage of the Housing
Demonstrator Programme. 
The approximately capacity of the Midlothian sites is 40 homes, within an overall
regional pipeline that to date comprises approximately 320 homes. Midlothian Council
intends to enter into a Memorandum of Understanding to embed collaborative working
in advance of each City Deal local authority procuring feasibility work to their
Demonstrator sites to a common specification with the same design team. Table 3.1
contains details of the proposed Housing Demonstrator sites in Midlothian. 
Table 3.1: Proposed Housing Demonstrator sites in Midlothian
Site name Location Approx No. of
homes
Build type 
Eastfield Drive Penicuik 8 Houses/Cottage Flats
Eskvale Drive Penicuik 6 Houses/Cottage Flats
Lomond Vale Penicuik 4 Houses/Cottage Flats
Lyne Terrace Penicuik 8 Houses/Cottage Flats 
Blackcot Road Mayfield 6 Houses/Cottage Flats
Page 125 of 164

Page 126

14 
Stone Place Mayfield 8 Houses/Cottage Flats
At this stage, these sites will be assessed for suitability for housing development
before they form a confirmed part of the affordable housing supply programme. A
catalogue of agreed housing design typologies has been developed, which will deliver
a certain performance standard, aiming to achieve net zero. However, these
typologies are not designed to deliver homes to a passivhaus standard, which should
be noted. Discussions are ongoing regarding how we could achieve an energy
performance as close to passivhaus standard as possible using off site manufacture 
Alternatives approaches for the future use of other garage or lock up sites which are
currently underused will also be taken forward. This will include options such as
demolition, sale or re-use for other purposes. 
Midlothian’s Rapid Rehousing Transition Plan
The vision for Midlothian Council’s Rapid Rehousing Transition Plan is that by 2024: 
“An increased number of homeless households will obtain permanent
accommodation, no homeless household will be accommodated in bed and breakfast
accommodation, and the average time taken for the Council to complete its homeless
duty will have halved from 105 to 52 weeks.” 
The Plan has five key outcomes to reach by 2024:
Outcome 1: Increasing the supply of affordable housing in Midlothian.
Outcome 2: Revise Midlothian Council’s Housing Allocation Policy to address the
backlog of homeless households already in temporary accommodation, and reduce
the time taken to house homeless households in the future.
Outcome 3: Seek alternative models of temporary accommodation to reduce the need
for bed and breakfast accommodation.
Outcome 4: Ensure homeless households are supported to access a wide range of
housing options, including the private rented sector.
Outcome 5: Develop a ‘housing first’ approach in Midlothian to house homeless
households with complex needs. 
The investment plans outlined in the SHIP are key to the objective of increasing the
supply of affordable housing. The Scottish Government is supporting Midlothian
Council to implement specific actions within the Rapid Rehousing Transition Plan and
between 2018/19 and 2021/22 allocated £643,000 to support this work. Further
funding is expected in future years to continue to support the implementation of this
Plan. 
Town Centre Regeneration
The Town Centre First Principle was agreed by the Scottish Government and the
Convention of Scottish Local Authorities in July 2014 and asked that government, local
authorities, the wider public sector, businesses and communities put the health of town
centres at the heart of decision making. It seeks to deliver the best local outcomes,
align policies and target available resources to prioritise town centre sites,
Page 126 of 164

Page 127

15 
encouraging vibrancy, equality and diversity. Town Centre Regeneration requires a
collaborative approach which strengthens the long-term plan for each town centre.
Work is underway by Midlothian Council and partner organisations to regenerate
Dalkeith6 and Newtongrange7 town centres to provide more and better housing,
become 20 minute neighbourhoods and realise greener buildings and town centres (in
order to become net zero by 2030). 
4 Investment Priorities and Resources
In order for the SHIP to deliver strategic investment priorities for affordable housing in
Midlothian, the Council has engaged with RSLs and relevant delivery partners in
setting out Midlothian’s investment priorities for affordable housing. To ensure that
available resources are prioritised in delivering affordable housing, each project is
scored against a set of criteria: Housing Need; Land Availability; Ability to Start on
Site; Constraints; Equalities Needs and Environmental Impact, as shown in the tables
below. In total, a project can be awarded a maximum score of 30 points and a score
less than 18 indicates a ‘low priority project’, 18-22, ‘a medium priority project’ and
over  22, a ‘high priority project’. 
Table 4.1: Project Prioritisation Scoring
Criteria Explanation Score
Area Housing Need Housing need rankings are based on a waiting list
demand study. 1 would indicate no housing need
in an area, whilst 5 indicates the highest level of
need. 
1-5
Land Availability Sites ranked most highly are those owned by the
Council or RSL. Also ranked highly are sites with
Planning Permission in place
1-5
Ability to Start on Site A site with a high score indicates that the work
could start on site once funding was approved.
1-5
Constraints Issues such as Section 75 requirements that have
yet to be resolved would be given a lower score.
1-5
Equalities Needs All sites will score at least a good rating (3) due to
Housing for Varying Needs.  Additional points
would be awarded for particular needs housing,
mixed tenure development e.g. shared equity.
1-5
Environmental Impact All sites which have been allocated through the
Midlothian Local Plan would not be considered as
having a negative environmental impact. Use of
renewable technology and building on Brownfield
sites would score more points.
1-5 
6 Have your say: Dalkeith Town Centre Regeneration | Creating a fresh vision for Dalkeith
town centre | Midlothian Council
7 Newtongrange and Stobhill and Lady Victoria | Masterplans | Midlothian Council
Page 127 of 164

Page 128

16 
Table 4.2: Area Project Prioritisation Score
Rank Area Points
1 Bonnyrigg/Lasswade/Poltonhall 
Loanhead, Newtongrange, Danderhall/Shawfair 
Small Settlements including Pathhead, Roslin, Rosewell,
Bilston
5
2 Dalkeith, Penicuik 4
3 Gorebridge, Mayfield/Easthouses 3 
It should be noted that some projects may have scored less not because they are of
less strategic importance to the Council or RSLs but due to circumstances which
prevent construction works from commencing on site (e.g. need for infrastructure
works or demolition). In terms of the area ranking for housing need, there are no areas
in Midlothian with a low level of housing need so areas judged to have lower levels of
housing need are those where there has already been significant investment in new
affordable housing in recent years. 
The sections below show both Council and RSL housing development priorities over
the next 5 years. It should be noted that sites indicated are subject to change as some
sites have not yet been approved by the developing organisation, received planning
permission or land ownership has not been secured. There is also potential for
additional sites to be developed within the 5 year period. More detail on each site is
shown in Appendix 1. 
Council Development Priorities
The table below sets out the priorities for proposed Council projects over the next 5
years. Key notes:
• 21 development projects are proposed by Midlothian Council over the next 5 years.
• Projects which are currently onsite do not need to be prioritised as they are already
in the process of being built
• 6 of the remaining 11 projects are considered high priority while 5 are medium
priorities. There are no projects judged to have a low priority.  
• Most projects with the highest priority scores are highlighted for commencement in
the short term whilst those with medium priorities are planned for the later years of
the SHIP period.
• One of the developments is for Open Market Purchases whereby Midlothian
Council purchases ex local authority properties from the open market which are
then returned to general stock. 
Page 128 of 164

Page 129

17 
Table 4.3: Council Housing Development Priorities 
RSL Development Priorities
The table below sets out the priorities for proposed RSL projects over the next 5 years.
Key notes:
• 35 development projects are proposed by RSLs over the next 5 years.
• Some of these projects contain several phases of development, each having its
own prioritisation and SHIP entry
• Projects which are currently onsite do not need to be prioritised as they are in the
process of being built
• 8 of the remaining 21 projects are high priority while 13 scored as medium priority.
No projects scored with a low priority. 
• 5 RSLs have indicated their plans to develop during this period including:
- Castle Rock Edinvar (17 projects)
- Dunedin Canmore Housing Association (9 projects)
- Melville Housing Association (7 projects)
- Viewpoint Housing Association (1 project)
- Ark Housing Association (1 project). 
Page 129 of 164

Page 130

Table 4.4: RSL Housing Development Priorities 
Page 130 of 164

Page 131

• There are a further 8 projects where the affordable housing provider has not yet
been confirmed due to a lack of certainty surrounding local authority rent increases
and therefore the ability to fund new build affordable housing beyond those which
are already budgeted for. Table 4.5 illustrates that 3 of these sites are high priority
whereas the remaining 5 are medium priority developments. 
Table 4.5: TBC Housing Development Priorities 
Addressing Potential Development Constraints 
Midlothian Council and developing partners are confident that the SHIP can be
delivered given the actions and initiatives undertaken to date by the Council and its
strategic partners to source suitable sites for development. However, a number of
challenges need to be addressed by the Council and its partners in order that an
accelerated pace of development can be achieved 
Risks and constraints to development vary depending on the circumstances of each
site and the developing landlord. These potential risks and constraints are: 
• Obtaining required Planning Approval. 
• Rising inflation and the cost of materials and labour
Page 131 of 164

Page 132

2 
• The emerging number of s75 sites without a confirmed affordable housing provider.
The lack of certainty surrounding rent increases has resulted in an inability to
confirm longer term housing projects.
• A diminishing number of Midlothian Council owned sites mean that many future
sites will be controlled by a third party.
• Building and Procurement Constraints. 
• Environmental and design issues.
• The commencement of affordable housing policy sites are dependent on
developers’ timescales and the economic conditions of the housing market. 
• Unknown site ground conditions. 
• The rural nature of some areas in Midlothian can mean that development is
constrained in these areas, particularly in relation to available land for housing and
the requirements for additional infrastructure prior to development commencement   
Scottish Government Affordable Housing Supply Funding Required 
The Strategic Housing Investment Plan details potential sites for 2,594 new affordable
homes to be built between 2023/24 and 2027/28, of which:
• House types: 2,251 are general needs homes and 343 are specialist provision
homes.
• Built form: 2,514 will be new build housing and 80 will be ‘off the shelf purchases’.
• Tenure type: 1,007 homes will be council housing and 788 will be social rented
housing by an RSL, 14 will be Low Cost Home Ownership – Shared Equity housing
by an RSL and 356 will be Mid-Market Rent housing provided by an RSL (MMR).
The remaining 429 homes do not have a confirmed social housing provider. 
• This reflects the fact that the affordable housing tenure with the highest demand is
social rented housing. 
• 1,958 units are expected to receive additional funding due to them meeting the
‘greener homes’ standard – this number is likely to increase as renewable
technology becomes more commonplace in new housing designs.
• 432 units will be developed in sub-area A (Midlothian West) 
• 2,042 units are to be developed in sub-area B (Midlothian East). 
A total of £127.520 million of Scottish Government grant funding is required by the
Council and RSLs to deliver the identified units over the next 5 years:
• The year which requires the most grant funding is 2023/24, with a requirement of
£32.057 Million. 
• 1,007 of the units will be new Council housing requiring £28.069 million grant
funding.  Monies already claimed from the Scottish Government have not been
included in these sums.
• 1158 of the units will be RSL housing requiring £74.362 million Government
funding. 
• 429 of the units with no confirmed affordable housing provider will require £24.340
million grant funding.
• The current uncertainty regarding affordable housing rent increases have resulted
in a large number of units with no confirmed housing provider. Once the situation
has become clearer both the Council and RSLs will ensure that future development
plans do not result in rents that are unaffordable to low income households.  
• The required level of grant funding to deliver this number of units greatly exceeds
the stated level of funding available. Council Officers will continue to discuss
Page 132 of 164

Page 133

3 
resource requirements with the Scottish Government to ensure that projects
receive appropriate levels of grant funding. In previous years Midlothian has been
able to claim significantly increased resources in response to the number of
projects being taken forward. 
• Most units to be built will be smaller sized properties, which reflects the Local
Housing Strategy target that at least 70% of all new affordable housing units will
be 1 and 2 bedroom properties in order to address the need for smaller properties
from Housing List applicants. 
Disposal of Council Assets and Land 
The Council is required by law to ensure it achieves best value in disposing of any
asset, including land. The Council acknowledges that Best Value does not always
mean highest price but can be linked to a range of wider benefits. Provision of
affordable housing is a good example of where the Council has sold land and assets
to RSLs at a price lower than market value while still achieving the required Best Value.
There are also opportunities to undertake developments in partnership with other
RSLs. 
Commuted Sums 
In some circumstances the Council may consider accepting commuted sums as
opposed to the delivery of affordable housing units on some sites. In 2021/22 a total
of £78,762 was received in developer contributions for affordable housing. This was
used to support Midlothian’s New Council Housing Programme. 
Second Homes and Empty Homes Council Tax Funding 
Under the Council Tax (Discount for Unoccupied Dwellings) (Scotland) Regulations
2005, Midlothian Council reduced the amount of discount for long term empty
dwellings and second homes from 50% to 10%, with the extra revenue used to support
affordable housing. A total of £398,000 was raised between 2016/17 and 2021/22
which is being used to support Midlothian’s New Build Council Housing Programme. 
Empty Homes
Midlothian Council does not have a dedicated ‘Empty Homes Officer’. Home owners
of empty properties are advised to contact the Housing Strategy and Performance
Team for advice on how to bring their homes back into use. Midlothian Council also
advocates use of the Scottish Empty Homes Partnership and Empty Homes Advice
Service which look at different options and the support available including the Empty
Homes Loan Fund (EHLF). Under the Local Government Finance (Unoccupied
Properties etc.) (Scotland) Act 2012, Midlothian Council reduced the amount of
discount for long-term empty dwellings and second homes from 50% to 10%, with the
extra revenue used to support affordable housing. 
Gypsy Traveller Accommodation
Improving the lives of Gypsy/Traveller communities is a significant human-rights
commitment for Midlothian Council and is crucial if we are to tackle deep-rooted
inequalities and deliver a fairer society. Improving the lives of Gypsy/Travellers 2019-
2021 is the Scottish Government’s action plan to improve the lives of Gypsy/Travellers
by ensuring they:
Page 133 of 164

Page 134

4 
• have safe and culturally appropriate places to live and travel
• understand their rights and have positive experiences of accessing services
• have support to maximise incomes, increase employment opportunities, and
improve the standard of living
• feel safe, respected and valued members of Scotland’s diverse population
• have a seat at the table, are listened to, and have a say in decisions that affect
their lives.
The work within the Improving the lives of Gypsy/Travellers 2019-2021 action plan has
been extended for 18 months with an end date of October 2022.
The Strategic Housing Investment Plan 2023/24-2027/28 acknowledges the aims and
objectives of ‘Improving the lives of Gypsy/Travellers 2019-21. The Gypsy/Traveller
site managed by East Lothian Council on behalf of East and Midlothian Councils
closed in June 2021 following extensive vandalism. East Lothian and Midlothian
Councils are now in the process of determining future accommodation options for the
site and for Gypsy/Travellers in the greater communities. It is important to note that
site lease break provisions are of immediate consideration to both the landlord and
lease holders. 
Wheelchair Accessible Housing Targets
In August 2022 Midlothian Council set wheelchair accessible housing targets for the
five year period between 2022/23 – 2026/27. The targets cover both social and market
housing and have been set following consultation with Midlothian residents, RSL
partners, the Health and Social Care Partnership and Planning Officers. The targets
state that 20 wheelchair accessible homes will be built per annum with 10 in the social
sector and 10 in the private sector, while other available opportunities shall also be
maximised. More information is contained in the Wheelchair Accessible Housing
Target Report 2022/23 – 2026/27, available here:
Housing strategy and performance | Wheelchair Accessible Housing Targets 2022/23 -
2026/27 (midlothian.gov.uk) 
Non-Traditional Financial Models of Development 
The use of innovative financial models is being encouraged in Midlothian to accelerate
the development of new affordable housing. Innovative approaches to development
often do not require traditional grant funding and will therefore increase the total
number of new affordable homes that can be built. Table 4.5 shows the proposed
locations for these additional units. 
In 2018, Places for People were successful in securing Scottish Government loan
funding of £47.5 Million for their proposal to deliver 1,000 mid-market rented homes in
Scotland. The development of these homes, which will be let by Castle Rock Edinvar
Housing Association, will also receive funding from investors to secure capital for the
development of 1,000 homes. 
In addition, LAR Housing Trust is an established affordable housing provider set-up to
create permanent below market rent options for households that would otherwise be
Page 134 of 164

Page 135

5 
at risk of financial hardship. LAR is financed using loan funding from the Scottish
Government and therefore does not require any direct subsidy and so will not be
seeking any grant allocations from local authorities. 
Table 4.5 New Homes Planned using Non-Traditional Finance Models 2023/24 –
2027/28
Location Developer Number of
additional
new homes 
Estimated
Date of
Completion
Wester Cowden, Dalkeith LAR 25 2025/26
Fordel Village LAR 24 2025/26 
It is important to note that the site at Fordel Village was purchased on the open market
and the 24 units planned by LAR are not part of the site’s affordable housing
requirement. As per the purchase arrangement, 12 affordable housing units (which
are eligible to pay section 758 costs) are still required to be provided on the remainder
of the site by another provider. 
5 Housing Infrastructure Fund 
The Scottish Government’s Housing Infrastructure Fund (HIF) is aimed at supporting
housing development through loans and grants with priority being given to those
projects, which will deliver affordable housing. As part of the Scottish Government’s
“Housing to 2040 Strategy” Scottish Ministers have approved the continuation of the
Housing Infrastructure Fund (HIF) in the current Parliamentary period. The fund
comprises two main elements: 
• Infrastructure loans available to non-public sector organisations
• Infrastructure grant available to local authorities and Registered Social
Landlords (RSLs) to support affordable housing delivery. 
Eligible works for HIF could include on site and off site elements. Works will include
physical infrastructure generally required to start a project, such as roads, sewers,
SUDS ponds, decontamination, flood remediation and demolition work. Where a
Section 75 obligation requires it, certain off-site infrastructure will also be eligible. The
fund does not support the provision of community infrastructure required as a
consequence of new housing development, for example, funding for schools. 
As part of developing the SHIP, Midlothian Council will work with partners to identify
and prioritise those sites which are of strategic importance and cannot proceed or have
stalled due to the extent and costs/financing of infrastructure works involved, and with
HIF’s support, unlock these sites for the delivery of housing9. The Council will work 
8 A Section 75 agreement, sometimes known as a planning obligation, is a contract entered into
between a landowner and the local Council, as part of the planning application process. The
agreement may restrict use of the land and/ or regulate activities on the land being developed.
9 https://www.gov.scot/policies/more-homes/housing-infrastructure-fund/
Page 135 of 164

Page 136

6 
with partners in examining the identified projects to ensure that such projects are
eligible for the fund10.   
Further information on the Housing Infrastructure Fund can be found here:
Housing Infrastructure Fund : guidance for applications - gov.scot (www.gov.scot)
6 Conclusion 
The Midlothian Strategic Housing Investment Plan 2023/24 – 2027/28 identifies the
priorities for the development of affordable housing and where development will be
undertaken over the next 5 years. It identifies sites which can deliver 2,594 units during
the next 5 years to meet the increasing level of housing need in Midlothian. This will
not only ensure best value in the use of resources but also ensure the delivery of the
right mix of houses in the most pressured areas. 
If you have any comments or queries on the content of this document, please contact
the Housing Planning & Performance Section at Midlothian Council for more
information. 
Development
Midlothian Council
Midlothian House
40-46 Buccleuch Street
Dalkeith
EH22 1DN
housing.enquiries@midlothian.gov.uk
Telephone: 07808 903454 
Equality Impact Assessment (EIA) and Strategic Environmental Assessment
Midlothian Council is committed to ensuring equality of opportunity and combating
discrimination through a series of equal opportunities and anti-discriminatory policies.
The Council has embedded equalities principles into strategic planning as well as
service delivery. Housing policies and services are regularly monitored, reviewed and
reported on to ensure that they comply with equalities requirements. 
Midlothian Council carried out an Equality Impact Assessment to ensure that the
Strategic Housing Investment Plan takes the needs of all equality strands into account.
The assessment found no evidence that any direct discrimination will arise from any
part of the strategy. The SHIP is also subject to pre-screening as part of Strategic
Environmental Assessment requirements.
10 https://www.gov.scot/publications/housing-infrastructure-fund-guidance-for-applications/
Page 136 of 164

Page 137

Appendix 1: SHIP Project Tables 
Page 137 of 164

Page 138

Table 1 - AFFORDABLE HOUSING SUPPLY PROGRAMME 2023/24-2027/28 
Page 138 of 164

Page 139

Page 139 of 164

Page 140

Page 140 of 164

Page 141

Page 141 of 164

Page 142

Page 142 of 164

Page 143

Page 143 of 164

Page 144

Table 2 - AFFORDABLE HOUSING PROJECTS FUNDED OR SUPPORTED BY SOURCES OTHER THAN THE RPA/TMDF BUDGET 
Table 3 - COUNCIL TAX ON SECOND AND EMPTY HOMES 
Page 144 of 164

Page 145

Table 4 - DEVELOPER CONTRIBUTIONS 
Page 145 of 164

Page 146

Page 146 of 164

Page 147

Midlothian Council
15 November 2022                 
Item 8.9 
Capacity increase to Replacement Beeslack CHS 
Report by Fiona Robertson, Director, Children, Young People & Partnerships 
Report for Decision 
1 Recommendations  
1. The Council is recommended to approve the increase in capacity for the
Replacement Beeslack Community High School from 1200 pupils to 1600 pupils. 
2 Purpose of Report/Executive Summary 
2.1 At full Council 28th June 2022, updated Heads of Terms were approved, with regards
to securing the site, for the Replacement Beeslack CHS. If the replacement school is
built to the current proposal of a 1200 capacity school our roll projections show that a
further extension would be required within two years of the school opening. The
current design of the 1200 pupil capacity school includes core accommodation - such
as gym halls, dining and all social spaces - to accommodate 1600 pupils. A full
business case with detailed financial costs will be brought back to December Council. 
2.2 Approval is now being sought to increase the indicated capacity of the new school
building from 1200 pupils to 1600 pupils 
Date: 20 October 2022 
Report Contact:
Marc Bedwell, Executive Business Manager, Children, Young People & Partnerships   
marc.bedwell@midlothian.gov.uk 
Page 147 of 164

Page 148

3 Background 
3.1  Midlothian Council successfully secured funding from the Scottish Government
Learning Estate Investment Programme (LEIP) for the Replacement Beeslack CHS.
LEIP projects were anticipated to be completed by 2024 but due to the impact of the
pandemic Scottish Government (SG) has granted some flexibility on this completion
date. To ensure the SG funding remains secure this project needs to be fully funded,
agreed and commenced as soon as is practically possible. It is intended to bring a
further report covering the financial costs to Council in December 2022. 
3.2 As stated in the Council report of 28 June 2022, approval was given for the provision
of a new high school for an increased roll of 1200 pupils, with future provision to 1600
pupils, in a location more central to a revised catchment area (subject to a Statutory
Consultation exercise).   
3.3 School roll projections were updated recently and indicate that a capacity of 1200
would be insufficient to accommodate all pupils from the catchment area proposed
initially. It is prudent to only project to a maximum of 6 years and the latest housing
completions from the Housing Land Audit inform our projections. Projections beyond
this timeframe become less accurate and more volatile. 
3.4 Several roll projection scenarios were explored and the breakdown of these can be
seen in the figures below. The proposed Replacement Beeslack is scheduled to open
in 2026 (shown in blue), any school capacity breaches are indicated in red. 
Please note, Glencorse PS closed in 2021 however children from the catchment area
can choose to attend either Mauricewood PS or Roslin PS and have been factored
into the projections below. 
Figure 1 displays the projected school rolls for each secondary school with the
following primary school catchment areas:  
• Beeslack CHS – Bilston, Roslin and Paradykes PS
• Lasswade HS - Bonnyrigg, Burnbrae, Hawthornden, Lasswade, Loanhead,
Rosewell PS
• Penicuik HS - Cornbank, Cuiken, Mauricewood, Strathesk PS 
Capacity 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
Beeslack 860 817 874 947 982 1046 1131
Lasswade 1600 1612 1654 1685 1670 1652 1624
Penicuik 945 656 679 679 774 837 911
Figure 1 Projected school rolls based on the inclusion of Paradykes PS to Beeslack CHS and
Mauricewood PS to Penicuik HS 
Figure 2 displays the projected school rolls for each secondary school with the
following primary school catchment areas:  
• Beeslack CHS – Bilston, Roslin, Loanhead and Paradykes PS
• Lasswade HS - Bonnyrigg, Burnbrae, Hawthornden, Lasswade, Rosewell PS
• Penicuik HS - Cornbank, Cuiken, Mauricewood, Strathesk PS 
Page 148 of 164

Page 149

Capacity 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
Beeslack
860
Replacement
1200 817 874 947 1027 1134 1256
Lasswade 1600 1612 1654 1685 1642 1596 1545
Penicuik 945 656 679 679 774 837 911
Figure 2 Projected school rolls based on the inclusion of Loanhead and Paradykes PS 
to Beeslack CHS and Mauricewood PS to Penicuik HS 
Figure 3 displays the projected school rolls for each secondary school with the
following primary school catchment areas:  
• Beeslack CHS – Bilston, Loanhead and Paradykes PS
• Lasswade HS - Bonnyrigg, Burnbrae, Hawthornden, Lasswade, Rosewell PS
• Penicuik HS - Cornbank, Cuiken, Mauricewood, Roslin, Strathesk PS 
Capacity 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
Beeslack 860 817 874 947 954 963 989
Lasswade 1600 1612 1654 1685 1642 1596 1545
Penicuik 945 656 679 679 829 964 1109
Figure 3 Projected school rolls based on the inclusion of Loanhead and Paradykes PS to
Beeslack CHS and Mauricewood, Roslin PS Penicuik HS 
3.5 As shown in the scenarios above, the rationale for building the replacement Beeslack
to a 1600 pupil capacity to include the primary school catchments of Bilston, Roslin,
Loanhead and Paradykes will ensure that there is sufficient capacity for the future. In
addition, other secondary schools are not projected to breach their stated capacity
because of the increased size of the replacement Beeslack CHS. If Loanhead PS is
included in the new catchment area this will reduce and stabilise the Lasswade HS
roll, this school has experienced accommodation pressures for a number of years. 
3.6 If the replacement school is built to the current proposal of a 1200 capacity school our
roll projections show that a further extension would be required within two years of
the school opening. The current design of the 1200 pupil capacity school includes
core accommodation - such as gym halls, dining and all social spaces - to
accommodate 1600 pupils. The only significant increase in floor area and costs will
relate to the provision of additional classroom bases. If the school capacity is not
increased and the school does breach it is likely that any appropriate community
space will have to be utilised for school pupils as is currently the case at Lasswade
CHS.   A full business case with detailed financial costs will be brought back to
December Council. 
3.7 A school extension within a two year time frame would not only be costly, but also
cause disruption to pupils, staff and the school community. The replacement
Beeslack CHS is being designed to Midlothian Council’s Net Zero Policy and we are
advised that extending onto a building of a passivhaus specification would also be
extremely challenging. 
Page 149 of 164

Page 150

3.8 The proposal to create a 1600 pupil capacity Beeslack CHS will also alleviate
ongoing capacity pressures at Lasswade High School. Due to site constraints the
ability to extend Lasswade HS is problematic and would lead to a loss of community
facilities such as sports pitches. The increase in capacity to 1600 pupils will also
factor into Local Development Plan 2 with any potential housing development sites
contributing towards education provision in the area. 
3.9 If the increase in capacity is approved, a statutory school consultation will be
undertaken with the proposal to move both Loanhead and Paradykes PS into the
Beeslack CHS catchment area and Mauricewood to the Penicuik HS catchment area. 
3.10 It is worth noting that any further delay to the existing project will have a detrimental
affect on the existing Beeslack CHS, and plans to provide temporary additional
capacity will be required. Further delays may also risk SG LEIP funding. 
4  Report Implications (Resource, Digital and Risk) 
4.1 Resource 
The proposed increase in capacity will lead to an increased project cost. The
current plan of the 1200 pupil capacity school includes core accommodation -
such as gym halls, dining and all social spaces - to accommodate 1600 pupils. 
4.2  Digital 
None 
4.3  Risk 
If the proposed increase to a 1600 pupil capacity school is not approved, a new
extension at the replacement Beeslack CHS is likely to be required within a few
years of opening. Lasswade HS will also continue to breach capacity. 
Page 150 of 164

Page 151

APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan
Not applicable 
A.2 Key Drivers for Change
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value
The implementation of the recommendation of this report will enhance best
value in the delivery of Council services. 
A.5 Involving Communities and Other Stakeholders 
A statutory consultation will take place to engage with communities and other
stakeholders. 
A.6 Impact on Performance and Outcomes
The report does not directly impact on Midlothian Council’s performance and
outcomes  
A.7 Adopting a Preventative Approach
Not applicable 
A.8 Supporting Sustainable Development
Not applicable 
Page 151 of 164

Page 152

APPENDIX B Background Papers/Resource Links (if applicable) 
Page 152 of 164

Page 153

Midlothian Council
15 November 2022
Item 8.10 
Proposed Revised Schedule of Meeting Dates for January – June 2023 
Report by Executive Director Place 
Report for Decision 
1 Recommendation 
To Approve the Revised Schedule of Meeting Dates for January – June 2023
as detailed in Appendix B. 
2 Purpose of Report/Executive Summary 
At the meeting of Council on 24 May 2022 it was proposed that a short life
working group review the schedule of dates. 
The schedule of dates have been reviewed by Democratic Services taking
into consideration school holidays and this revised proposed schedule is now
presented to Council for consideration. 
Date:  25 October 2022
Report Contact:
Ross Neill, Democratic Services Team Leader 
ross.neill@midlothian.gov.uk   
Page 153 of 164

Page 154

2 
3 Background 
3.1 The Council currently operates on a six weekly cycle of meetings with breaks
incorporated for the summer recess, Christmas/New Year and wherever
possible school holidays. 
3.2 The proposed reviewed schedule of meetings for January – June 2022 is shown
at Appendix B. 
3.3  Members are aware that a review of the Council’s Governance arrangements
is pending and should there be any change as a result of this work a further
report would be brought forward to Council. 
3.4 Members are also reminded that the facility also exists under Standing Orders
for special meetings to be called as and when required. 
4 Report Implications (Resource, Digital and Risk) 
4.1 Resource 
None 
4.2 Digital 
None 
4.3 Risk 
The availability of the schedule of meeting dates contributes to the mitigation
of risk by: 
• facilitating forward planning for meetings; 
• contributing to the governance framework which allows the Council to
conduct its business; and 
• providing a timetable to which officers can work to ensure that reports are
submitted timeously. 
4.4 Ensuring Equalities (if required a separate IIA must be completed) 
This report does not recommend any change to policy or practice and
therefore does not require an Equalities Impact Assessment. 
4.5 Additional Report Implications 
See Appendix A 
Page 154 of 164

Page 155

3 
Appendices 
Appendix A – Additional Report Implications
Appendix B – Proposed Revised Schedule of Meeting Dates January – June
2023  
Page 155 of 164

Page 156

4 
APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan
Not applicable 
A.2 Key Drivers for Change
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value
The report does not directly impact on Delivering Best Value but the absence
of a schedule of meetings may result in delays in the ability to carry out proper
scrutiny. 
A.5 Involving Communities and Other Stakeholders
The report does not directly relate to involving communities 
A.6 Impact on Performance and Outcomes
The absence of a schedule of meetings may impact on Midlothian Council’s
performance and outcomes 
A.7 Adopting a Preventative Approach
Not applicable 
A.8 Supporting Sustainable Development
Not applicable 
Page 156 of 164

Page 157

5 
APPENDIX B 
Proposed Schedule of Meetings Dates for January - June 2023
January 2023  
Tuesday 10 10.00 General Purposes
Tuesday 10 13.00 Planning
Thursday 12 14.00 Midlothian Integration Joint Board Development Workshop
Tuesday 17 11.00 Cabinet  
Monday 23 10.00 Local Review Body Site Visits
Monday 23 13.00 Local Review Body
Tuesday 24  11.00 Audit Committee
Monday 30  11.00 Business Transformation Steering Group
Tuesday 31 11.00 Performance, Review and Scrutiny Committee
Tuesday 31 14.30 JCG   
February 2023  
Monday 6  11.00 Police Fire and Rescue Board
Tuesday 7 10.00 General Purposes
Thursday 9 14.00 Midlothian Integration Joint Board
School Holidays 13 – 17  February 2023
Monday 20 10.00 Planning Site Visits
Tuesday 21 11.00 Midlothian Council
Monday 27 10.00 Planning Site Visits
Tuesday 28  10.00 Cabinet
Tuesday 28 13.00 Planning   
March 2023  
Thursday 2 14.00 Midlothian Integration Joint Board Audit & Risk Committee
Monday 6 10.00 Local Review Body Site Visits
Monday 6  13.00 Local Review Body
Tuesday 7 11.00 Audit Committee
Monday 13 11.00 Business Transformation Steering Group
Tuesday 14 11.00 Performance, Review and Scrutiny Committee
Tuesday 14 14.30 JCG
Thursday 16 14.00 Special Midlothian Integration Joint Board
Tuesday 21 11.00 Midlothian Council
Tuesday 28 10.00  General Purposes
Tuesday 28 13.00  Planning   
Page 157 of 164

Page 158

6 
April 2023
School Holidays 3 – 14 April 2023
Thursday 13 14.00 Midlothian Integration Joint Board
Monday 17 10.00 Local Review Site Visits
Monday 17 13.00 Local Review Body
Tuesday 18 11.00 Cabinet
Monday 24 11.00 Business Transformation Steering Group
Tuesday 25 11.00  Audit Committee   
May 2023  
Tuesday 2 11.00  Performance Review and Scrutiny Committee
Tuesday 2 14.30 JCG
Tuesday 9 11.00 Midlothian Council
Thursday 11 14.00 Midlothian Integration Joint Board Development Workshop
Monday 15 11.00 Police Fire and Rescue Board
Tuesday 16 10.00 General Purposes Committee
Tuesday 16 13.00 Planning Committee
Monday 22  10.00 Local Review Body Site Visits
Monday 22 13.00 Local Review Body
Tuesday 30 11.00 Cabinet   
June 2023  
Thursday 1 14.00 Midlothian Integration Joint Board Audit & Risk Committee
Monday 5 11.00 Business Transformation Steering Group   
Tuesday 13  10.00 General Purposes Committee
Tuesday 13 13.00 Planning Committee
Thursday 15 14.00 Midlothian Integration Joint Board
Monday 19 10.00 Local Review Body Site Visits
Monday 19 13.00 Local Review Body
Tuesday 20 11.00 Performance Review and Scrutiny
Tuesday 20 14.30 JCG
Monday 26 11.00 Audit Committee
Tuesday 27 11.00 Midlothian Council   
July 2023  SUMMER RECESS  29 June – 16 August 2023
Note: Dates of meetings of Midlothian Integration Joint Board (MIJB) and the
MIJB Audit and Risk Committee are included for information and completeness
however these are not set by the Council 
Page 158 of 164

Page 159

Midlothian Council 
15 November 2022                    
Item 8.11 
Webcasting Meetings of Council and its Committees 
Report by Kevin Anderson, Executive Director - Place 
Report for Decision 
1 Recommendation 
Council is requested to consider the range of its public governance meetings
which are broadcast and live streamed, and to direct officers to implement one
of the three options as set out in this report. 
2 Purpose of Report/Executive Summary 
Special Council held on 27 September 2022 decided to proceed with an in-
person Council meeting of 4 October 2022 and thereafter the range of public
governance meetings for Council, Cabinet and its established Committees.
For this schedule of meetings, these have been live streamed or recorded for
available broadcast to members of the public. Council are asked to consider
the current arrangements and determine what the interim broadcasting
approach should be whilst awaiting the implementation of a technical solution
for hybrid meetings, anticipated by March 2023. 
Date: 28 October 2022 
Report Contact: 
Name: Kevin Anderson, Executive Director - Place  
Tel No: 0131 271 3102
kevin.anderson@midlothian.gov.uk 
Page 159 of 164

Page 160

2
3 Background 
At its Special Council meeting on 27 September 2022, Council agreed
to reconvene Council, Cabinet and established Committees in-person.
Up until this point, from June 2020, meetings of Council and its
Committees were held virtually using the MS Teams platform due to
the impact of the Covid-19 pandemic.
3.1 Prior to the pandemic, some in-person meetings held in the Council
chamber were webcast and/or recorded to allow the public to watch live
or view after the meeting (Council and Planning). The number of
meetings webcast was limited due to the arrangements with the
webcasting supplier, which meant that to webcast all meetings would
have exceeded the number of streaming hours included in the contract.
3.2 During the pandemic, when meetings were held via MS Teams, the
majority of the meetings were also live video broadcast to members of
the public. 
Current arrangements for consideration
3.3 Following Council’s decision on 27 September 2022 to return to in-
person meetings for all Council, Cabinet and established Committees,
all meetings have been webcast from the Council chamber. This is a
change from pre-COVID arrangements as the contract with the
webcasting supplier has been renegotiated and there is now increased
streaming hours capacity.
3.4 Council are asked to consider whether this revised arrangement should
continue, or if some meetings should not be webcast. Options are set
out below.
Option 1: to continue with the current arrangements in that all in-
person governance meetings should be webcast:
• Council
• Cabinet
• Performance, Review and Scrutiny Committee
• Planning Committee
• Audit Committee
• General Purposes Committee
• Local Review Body
Option 2: to revert to the previous arrangements pre-pandemic:
• Council
• Planning
Option 3: to discount both options 1 and 2 and propose a list of
meetings that should be webcast. 
Page 160 of 164

Page 161

3
3.5 It should be noted that any decision above does not apply to Integration
Joint Board meetings who have their own arrangements nor the
Midlothian Police and Fire & Rescue Board.
3.6 The above options are interim measures. Council on 4 October 2022
has endorsed the implementation of hybrid meetings. This was on the
basis that the implementation costs associated with the revised
proposed technical solution were significantly less than those reported
to Council earlier in the calendar year. However it was noted at that
meeting that implementation may take until March 2023 subject to
availability of supplies for installation. 
4 Report Implications (Resource, Digital, Risk and Equalities) 
4.1 Resource 
There are no additional resource requirements as the contract allows
for increased webcasting hours. 
4.2 Digital 
There are no additional digital requirements as the technical solution is
available and in use. 
4.3 Risk 
There is a risk that the Council does not meet its obligations for public
access where meetings are not broadcast or made available to the
public.   
4.4 Ensuring Equalities 
Equality implications continue to be assessed as part of the hybrid
implementation and any mitigations necessary would be carried out as
part of the detailed work to design the implementation of the systems
layout.   
4.5 Additional Report Implications 
See Appendix A 
Page 161 of 164

Page 162

4
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan
The route map through and out of the crisis approved in June 2020
outlines the phases of service recovery and transformation which
underpin delivery of the Single Midlothian Plan. 
A.2 Key Drivers for Change
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value
The report aims to deliver best value. 
A.5 Involving Communities and Other Stakeholders
The focus to date has been on identifying a technical solution including
consultation with other Councils. No wider consultation has been
undertaken.
A.6 Impact on Performance and Outcomes
The arrangements for meetings of Council and its Committees
facilitates the governance to determine outcomes and policies and also
the scrutiny of performance and the delivery of outcomes. 
A.7 Adopting a Preventative Approach
The report considers the facilitation of meetings of Council and its
Committees the business of which encompasses the adoption of
preventative approaches. 
A.8 Supporting Sustainable Development
New systems can be assessed to consider energy management and
utility consumption alongside consideration of the wider building
ownership implications. 
Page 162 of 164

Page 163

5
Background papers: 
1. Council on 14 December 2021 Hybrid Meetings of Council and its
Committees
2. Council on 24 May 2022, Hybrid Meetings of Council and its Committee 
Page 163 of 164