Democracy Spraffa

Agenda Document Pack - Audit Committee - 16/06/2025

Midlothian Council · 16 June 2025
Back to Audit Committee — 16 June 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Notice of Meeting and Agenda 
Audit Committee 
Venue:  Council Chambers/Hybrid, 
Midlothian House, Dalkeith, EH22 1DN 
Date:  Monday, 16 June 2025 
Time:  11:00 
Executive Director : Place 
Contact:
Clerk Name: Democratic Services
Clerk Telephone: 
Clerk Email: democratic.services@midlothian.gov.uk 
Further Information: 
This is a meeting which is open to members of the public.  
Privacy notice: Please note that this meeting may be recorded. The
recording may be publicly available following the meeting. If you would
like to know how Midlothian Council collects, uses and shares your
personal information, please visit our website: www.midlothian.gov.uk 
Page 1 of 396

Page 2

1          Welcome, Introductions and Apologies   
2          Order of Business 
Including notice of new business submitted as urgent for consideration at the
end of the meeting. 
3          Declaration of Interest 
Members should declare any financial and non-financial interests they have in
the items of business for consideration, identifying the relevant agenda item
and the nature of their interest. 
4          Minute of Previous Meeting 
Minute of Audit Committee meeting of 24 February 2025
submitted for approval
5 - 14 
Action Log 15 - 16 
5          Public Reports
5.1 Midlothian Council Transformation:  how councils are redesigning
and delivering more efficient services to achieve planned
outcomes, report by Audit Scotland
17 - 44
5.2 Annual Treasury Management Report 2024/25, report by Chief
Financial Officer and Section 95 Officer
45 - 74
5.3 Unaudited Annual Accounts 2024/25, report by Chief Financial
Officer and Section 95 Officer (report added - see below) 
5.4 Accounts Commission – Local Government Budgets 2025/26,
report by Chief Financial Officer and Section 95 Officer
75 - 114
5.5 Internal Audit Work to May 2025, report by Chief Internal Auditor 115 - 142
5.6 Council Tax Refunds Control Assurance Review, report by Chief
Internal Auditor
143 - 176
5.7 Internal Audit Annual Assurance Report 2024/25, report by Chief
Internal Auditor
177 - 190
5.8 Counter Fraud Annual Report 2024/25, report by Chief Internal
Auditor
191 - 200
5.9 External Quality Assessment of Midlothian Council’s Internal
Audit Service, report by Chief Internal Auditor
201 - 228
Page 2 of 396

Page 3

5.10 Draft Annual Governance Statement 2024/25, report by Chief
Executive
229 - 242
5.11 Risk Management Update – Strategic Risk Profile Quarter 4,
2024-25, report by Chief Officer Place
243 - 290 
6          Private Reports 
No items for discussion 
7          Date of Next Meeting 
The next meeting will be held on Tuesday 30 September 2025.   
Page 3 of 396

Page 4

Page 4 of 396

Page 5

Minute of Meeting 
Audit Committee        
Monday 16 June 2025
Item No 4.1 
Audit Committee 
Date Time Venue
Monday 24 February 2025 11am Council Chambers/Hybrid 
Present:
Councillor McEwan (Chair) Councillor Bowen
Councillor McCall Councillor Milligan
Councillor Smaill (virtual) 
In Attendance:
Councillor Alexander (virtual) 
Councillor Curran (virtual) 
Dr Grace Vickers  Chief Executive
Fiona Robertson Executive Director, Children, Young People
and Partnerships 
David Gladwin Chief Financial Officer and Section 95 Officer
Saty Kaur Chief Officer Corporate Solutions
Derek Oliver Chief Officer Place
Duncan Stainbank Chief Internal Auditor 
Page 5 of 396

Page 6

Alan Turpie Legal and Governance Manager and
Monitoring Officer
Gary Thomson Senior Finance Business Partner
Patricia Fraser Senior Audit Manager, Audit Scotland
Claire Gardiner Audit Director, Audit Scotland
Hannah Forbes Democratic Services Officer
Nicola Thorburn Democratic Services Officer 
1. Welcome and Apologies for Absence 
The Chair welcomed everyone to the meeting of the Audit Committee. 
2. Order of Business 
The order of business was as detailed in the agenda.
3. Declarations of interest 
No declarations of interest were intimated at this stage of the proceedings. 
4. Minute of Previous Meeting
4.1 Minutes of the previous meeting held 25 November 2024 were submitted and
approved as the correct record. Minutes were moved by Councillor Milligan and
seconded by Councillor McCall.
4.2 The Action Log was submitted and noted. 
5.      Public Reports 
Report No. Report Title Submitted by:
5.1 Midlothian Council Annual Audit Plan
2024/25 - Draft Audit Scotland
Outline of report and summary of discussion
The Audit Director presented the draft report highlighting areas of change and focus
in relation to materiality and significant risks.   
The third-year theme for Best Value will be Transformation and will follow on from
the national report which was published in October 2024.  Work has commenced
locally and engagement with key officers is underway. 
Audit Scotland plan to issue their report by 30 September 2025, which is line with
the national target date.   
Page 6 of 396

Page 7

The audit fee of £295,490 for 2024/25 is also detailed within the report, this is a
1.9% increase from prior year which is standard across all bodies audited by Audit
Scotland. 
The Chair thanked the Audit Director for their report and opened for questions.  No
questions were raised. 
The report was moved by Councillor McCall and seconded by Councillor Bowen. 
Decision
The Audit Committee noted the report. 
Report No. Report Title Submitted by:
5.2 Local Government in 
Scotland: Financial Bulletin 2023/24
Audit Scotland
Outline of report and summary of discussion
The Audit Director advised that this report had been included for information.  The
report was compiled by the Audit Scotland Overview Team and is a review of the
published financial statements of 2023/24 and information gathered from Section
95 Officers across Scotland. 
The report shows the challenging financial landscape across local authorities and
the key messages are the reduction of income in-year in both revenue and capital,
increased borrowing and capital expenditure and an acknowledgement of the
dependency on reserves to meet service delivery commitments. 
The Chair thanked the Audit Director for their report and opened for questions.  No
questions were raised. 
The report was moved by Councillor Bowen and seconded by Councillor McCall. 
Decision
The Audit Committee noted the report. 
Report No. Report Title Submitted by:
5.3 Treasury Management and Investment
Strategy 2025/26 & Prudential
Indicators
Chief Financial
Officer and Section 
95 Officer
Outline of report and summary of discussion
The Chief Financial Officer and Section 95 Officer presented the report for decision,
advising that in accordance with the Treasury Management Code of Practice, the
annual Treasury Management & Investment Strategy (TMIS) & Prudential
Indicators report is required to be adequately scrutinised before being referred to
Council for approval. For Midlothian, this role is undertaken by the Audit
Committee, with this report being presented today prior to consideration by Council
Page 7 of 396

Page 8

on 25 February 2025.  The purpose of the report to Council will be to provide an
update on the implementation of the Council’s TMIS 2024/25, and to make
recommendations to facilitate consideration of the 2025/26 Strategy. 
The Chief Financial Officer and Section 95 Officer highlighted one material change
from the existing strategy that will prove to be effective in the delivery of the
Council’s Capital Plan investment plans.  The change asked is to move from a
position of fully cash back Council reserves to a more flexible position allowing
greater internal borrowing thus allowing the deferral of long-term borrowing to a
point in time where interest rates are forecast to reduce.   
The Chief Financial Officer and Section 95 Officer added that the figures in the
report and appendices reflect the approved General Services and Housing
Revenue
Account (HRA) Capital Plans and that further decisions on capital projects will
impact delivery of the strategy. The implications of these will be picked up in the
half-year review. 
The Audit Committee is asked to scrutinise and comment on this report before it is 
presented to Council and to note the following recommendations which are
proposed to be presented to Council on 25 February 2025.  The Chief Financial
Officer and Section 95 Officer will verbally update Council of any changes to the
paper that are agreed in this meeting. 
a) Approve the restriction of the Authorised Limit to the value of the Capital
Financing Requirement at 31 March 2026 (£604.957 million), pending
finalisation of the General Services Capital Plan Prioritisation.   
b) Note that there is no other material changes proposed to the Treasury
Management and Investment Strategy (TMIS) for 2025/26 from the strategy
currently in place, other than: 
(i)  to no longer fully cash back the Council’s useable reserves - instead, to
run down cash balances to support the deferral of borrowing as outlined in
Section 4, to allow the Council to navigate past the current interest rate hump;
and 
(ii) to update the Prudential Indicators (Section 5), to reflect the revised capital
plans. 
c) Note the use of the Asset Life method for the repayment of all loans fund
advances as outlined in Section 6; and 
d) Accordingly approve the Treasury Management and Investment Strategy for
2025/26. 
The Chair thanked the Chief Financial Officer and Section 95 Officer for their report
and opened for questions. 
Elected Members thanked the Chief Financial Officer and Section 95 Officer for
their report and noted that they were sympathetic to moving away from the old
Page 8 of 396

Page 9

policy of cash backing the Council’s reserves and added the importance that Audit
Committee has sight of the expansion of the Council’s debt and the implications. 
The Chief Financial Officer and Section 95 Officer thanked the Elected Members
for their endorsement for the flexibility of internal borrowing and agreed that it
should be monitored closely.  The key point is the relativity of the borrowing and
the borrowing costs which are embedded in the Medium-Term Financial Strategy
(MTFS) for both General Fund reserves and multi-year HRA plans. 
Elected Members noted that there had been some press where international
commentators and professors of economics expressed opinions that the UK
economy is heading downwards and asked if this is something the Council should
be concerned about.  The Chief Financial Officer and Section 95 Officer is aware
of the international concerns but the biggest risk, coming from this perspective, is
that interest rates go up and the impact that will have on the affordability of the
Council’s plan, and how those challenges are managed.  The Senior Finance
Business Partner agreed that the global economy is uncertain, even more so than
in previous years.   
The Chair asked if an emergency were to occur, and it required a high spend, is
there a contingency for this.  The Chief Financial Officer and Section 95 Officer
advised that the Council would not borrow explicitly to fund the costs of an
emergency, the reserves would be used in that capacity.  If there were insufficient
liquid reserves, then Council could borrow to finance a capital expenditure and use
that cash to release some funding. 
The report was moved by Councillor McCall and seconded by Councillor Bowen. 
Decision
The Audit Committee approved the recommendations set out in the report. 
Report No. Report Title Submitted by:
5.4 Internal Audit 
Work to January 2025
Chief Internal
Auditor
Outline of report and summary of discussion
The Chief Internal Auditor presented the report for decision, providing members of
the Audit Committee with details of the recent work carried out by Internal Audit and
the findings and recommended audit actions agreed by management to improve
internal controls and governance arrangements. 
The Audit Committee is asked to: 
a) Consider the Executive Summary of the final Internal Audit assurance report
issued associated with the delivery of the approved Internal Audit Annual Plan
2024/25. 
b) Note the Internal Audit Consultancy and Other Work carried out in accordance
with the approved Internal audit Charter. 
Page 9 of 396

Page 10

c) Acknowledge the assurance provided on internal controls and governance
arrangements in place for the areas covered by this Internal Audit work. 
The Chair thanked the Chief Internal Auditor for their report and opened for
questions.  No questions were submitted. 
The report was moved by Councillor Bowen and seconded by Councillor McCall. 
Decision
The Audit Committee approved the recommendations set out in the report. 
Report No. Report Title Submitted by:
5.5 Internal Audit Mid-Term Performance
Report 2024/25
Chief Internal
Auditor
Outline of report and summary of discussion
The Chief Internal Auditor presented the report for decision, informing the Audit
Committee of the progress Internal Audit has made in the first 10 months of the
year to 31 January 2025, towards completing the Internal Audit Annual Plan
2024/25. It also summarises the statutory obligations for Internal Audit 
and requirements of the Public Sector Internal Audit Standards. 
The Audit Committee is asked to: 
a) Note the progress Internal Audit has made with activity in the Internal Audit
Annual Plan 2024/25 to the end of January 2025. 
b) Confirm that it is satisfied with the performance of the Internal Audit service
provision. 
The Chair thanked the Chief Internal Auditor for their report and opened for
questions.   
Elected Members asked about East Renfrewshire Council auditing Midlothian
Council, and whether this was normal practice and how long this takes.  The Chief
Internal Auditor advised that there is a requirement for Internal Audit function to be
reviewed every 5 years by an external body.  Local Authorities review each other
within a framework that meets the standard requirements.  Midlothian Council have
previously audited Dumfries & Galloway Council, which took approximately 20-30
days.  The alternative is paying an external body however the cost is extensive, so
this is the best value way to complete the review at a very good standard. 
The report was moved by Councillor McCall and seconded by Councillor Bowen. 
Decision
The Audit Committee approved the recommendations set out in the report. 
Page 10 of 396

Page 11

Report No. Report Title Submitted by:
5.6 Internal Audit Charter Chief Internal
Auditor
Outline of report and summary of discussion
The Chief Internal Auditor presented the report for decision, providing the Audit
Committee with the updated Internal Audit Charter, in accordance with Global
Internal Audit Standards (GIAS), for approval that defines the purpose of Internal
Audit and the mandate for Internal Audit within Midlothian Council. The Charter
clarifies the independence, organisational position and reporting relationships of
Internal Audit and outlines the roles and responsibilities of the Audit Committee and
the Chief Audit Executive, who is the Chief Internal Auditor for Midlothian Council
and Midlothian Integration Joint Board (MIJB). 
The Audit Committee is invited to: 
a) Note that the Internal Audit Charter has been fully updated in accordance with
the Chartered Institute of Internal Auditors model charter and in compliance with
Global Internal Audit Standards in application in the UK Public sector from 1 April
2025. 
b) Approve the revised Internal Audit Charter for use from 1 April 2025. 
c) Note that the Internal Audit Charter will be reviewed annually. 
The Chair thanked the Chief Internal Auditor for their report and opened for
questions.  No questions were submitted. 
The report was moved by Councillor Bowen and seconded by Councillor McCall. 
Decision
The Audit Committee approved the recommendations set out in the report. 
Report No. Report Title Submitted by:
5.7 Internal Audit Strategy and Annual Plan
2025/26
Chief Internal
Auditor
Outline of report and summary of discussion
The Chief Internal Auditor presented the report for decision, providing Audit
Committee with the proposed Internal Audit Strategy and Annual Plan 2025/26
which enables the Chief Internal Auditor to prepare annual opinions on the
adequacy of the overall control environment for Midlothian Council, and MIJB. 
The Chair thanked the Chief Internal Auditor for their report and opened for
questions.   
Elected Members queried item 5.3 within the report which states that Midlothian
Council do not fully comply with the GIAS Standard 9.5 Coordination and Reliance
as they do not have a full assurance map and whether this is a serious problem. 
Page 11 of 396

Page 12

The Chief Internal Auditor confirmed that there is not a formal assurance framework
in Midlothian Council and that there are several external bodies that provide
reporting and assurances to Midlothian Council, and that they take cognisance of
the work they are undertaking along with the Internal Audit Plan. 
Elected Members also asked for details on Mosaic, as detailed on page 204.  The
Chief Internal Auditor confirmed that this was an online system that provides case
management within the Social Work Department. 
Elected Members queried School Transport being on the Internal Audit Plan (page
203) and that they were aware of a consultation being carried out and whether there
was a risk of too many different areas working on this.  The Chief Internal Auditor
advised that School Transport had been identified as an area of risk and therefore
must be on the plan.  If it is deemed that the risk has diminished because of work
elsewhere this can be removed from the plan after a further review. 
The report was moved by Councillor McCall and seconded by Councillor Bowen. 
Decision
The Audit Committee approved the recommendations set out in the report. 
Report No. Report Title Submitted by:
5.8 Counter Fraud Annual Plan 2025/26 Chief Internal
Auditor
Outline of report and summary ofiscussion
The Chief Internal Auditor presented the report for decision, providing the Audit
Committee the proposed Counter Fraud Annual Plan 2025/26 to support the 
delivery of the Council’s Counter Fraud Strategy and to demonstrate compliance
with the Council’s Counter Fraud Policy Statement. 
The Audit Committee is invited to approve the Counter Fraud Annual Plan 2025/26 
The Chair thanked the Chief Internal Auditor for their report and opened for
questions.   
Elected Members raised the recent public comment on the overpayment of housing
benefit and asked if Midlothian Council were at risk to be involved as a data provider
in relation to these overpayments.  The Chief Internal Auditor advised that this will
be reviewed as part of the fraud risk assessment however Universal Credit is no
longer paid by the Council.  There is a legacy role in housing benefits which are
reviewed every 2 years in line with the National Fraud Initiative and there are
controls in place.  The Chief Internal Auditor is not aware of any particular risk in
this area, but the risk assessment would highlight these and subsequently
mitigations can be put in place. 
The Chair noted increased use of digital applications and asked how satisfied the
Chief Internal Auditor is that they are dealing with real people and if there are any
personal interactions with applicants. The Chief Internal Auditor advised that as
Page 12 of 396

Page 13

they go through all the business areas dealing with the public online will be an area
of review but there are already controls in place to request evidence where
required.  The Chief Internal Auditor is satisfied with what is in place currently but
noted that cyber fraud will always be an area of risk for ongoing review. 
The report was moved by Councillor McCall and seconded by Councillor Bowen. 
Decision
The Audit Committee approved the recommendations set out in the report. 
Councillor Curran joined the meeting virtually at 11:39am. 
Report No. Report Title Submitted by:
5.9 Audit Committee Recruitment of an
Independent Member
Chief Internal
Auditor
Outline of report and summary of discussion
The Chief Internal Auditor presented the report for decision, highlighting the
proposal to remunerate Independent Members. 
Audit Committee is recommended to
a) Note the contents of the report, informed by the Audit Committee Annual/End of
Term Report 2023/24. 
b) Provide comments on the proposal to remunerate Independent Members to
inform Council’s decision on Tuesday 25 February 2025. 
The Chair thanked the Chief Internal Auditor for their report and opened for
questions.  No questions were submitted. 
The report was moved by Councillor Bowen and seconded by Councillor McCall. 
Decision
The Audit Committee approved the recommendations set out in the report. 
Report No. Report Title Submitted by:
5.10 Strategic Risk Profile Quarter 2&3, 2024
-25
Chief Officer Place 
Outline of report and summary of discussion
The Chief Officer Place presented the report for information, providing the Audit
Committee with an update on the risk responses Midlothian Council has
implemented during Q2 and Q3 2024/25 to respond to the current risk climate,
assurance that Midlothian Council took a proportionate and planned approach to
prepare and respond to the current risk climate and the risk evaluation of current 
strategic risks and opportunities for the Council. 
Page 13 of 396

Page 14

Audit Committee is recommended to note the current risk landscape and
organisational response to the most significant risks in Quarter 2 (Q2) 2024-25 (1st 
Jul to 30th Sep 2024) and in Quarter 3 (Q3) 2024-25 (1st Oct to 31st Dec 2024). 
The Chair thanked the Chief Internal Auditor for their report and opened for
questions.  No questions were submitted. 
Decision
The Audit Committee noted the recommendations in the report. 
6. Private Reports 
No items for discussion. 
7. Date of Next Meeting 
The Chair apologised for the proximity of today's meeting to the meeting of Midlothian
Council. 
The next meeting of the Audit Committee will be held on Monday 16 June 2025 at
11:00, and the next meeting of Midlothian Council following that will be Tuesday 24
June 2024. 
The meeting ended at 11:43am.
Page 14 of 396

Page 15

Audit Committee               
Monday 16 June 2025
Item 4.2
Audit Committee Action Log 
No Date of Meeting Item No and
Title
Action Action Owner Expected
completion date
Comments
1 5.1 Treasury
management 
06/12/2022 Session with members to be
organised with regards to
responsible treasury
management/ethical issues.
Chief Financial
Officer / Section
95 Officer
February 2025 An update will be provided
in the Treasury
Management and
Investment Strategy for
2025/26. 
Reporting on ESG
developments is contained
in annual TMIS and ½
yearly reviews
Recommended for
closure.   
Page 15 of 396

Page 16

No Date of Meeting Item No and
Title
Action Action Owner Expected
completion date
Comments
2 5.5 Risk
Management
Update – Strategic
Risk Profile
Quarter 1 2024/25 
30/09/2024 Review report to determine if
risk scores linked to cost of
living and Care at Home
need to be upgraded.
Chief Officer
Place
Dec 2024 in line
with Q2 risk
reporting.
A combined Q2 and Q3
Strategic Risk Report
submitted to Audit
Committee on 24 February.
Recommended for
closure. 
Page 16 of 396

Page 17

Midlothian Council
Transformation: how councils are redesigning and
delivering more efficient services to achieve planned
outcomes
Prepared by Audit Scotland
June 2025
Audit Committee
Monday 16 June 2025
Item No 5.1
Page 17 of 396

Page 18

Midlothian Council | 2 
Contents 
Key messages 3
Introduction 5
Transformation planning 8
Programme management 12
Partnership working and community engagement 15
Impact of transformation 20
Appendix 23 
Accessibility
You can find out more and read this report using assistive technology on
our website www.audit.scot/accessibility.
Page 18 of 396

Page 19

Key messages | 3 
Key messages 
1 Midlothian Council recognises that transformation is essential to ensure
service delivery remains financially sustainable and has published a
Transformation Blueprint for Midlothian. This strategic plan was approved in
June 2023 and has five clear objectives, including supporting the council in
addressing the £8.9 million funding gap. 
2 The council is focused on delivering a wide range of key transformation
initiatives to progress the Transformation Blueprint. This includes a variety of
digital initiatives being progressed as part of its Digital Transformation
Strategy to create efficiencies in its operations. It is too early to fully
determine the scale of all of the projects being taken forward, and the extent
to which they will contribute towards closing the funding gap. The council
recognises that it is operating in a fiscally challenging environment and now
needs to find a way to accelerate progress on the remaining projects within
the Transformation Blueprint within the resources it has available.  
3 The council has established effective governance arrangements for reporting
progress with delivering transformation to its senior leadership team and
elected members.
4 There are challenges in recruitment and capacity across the public sector
including Midlothian Council. In particular, the council is experiencing
challenges recruiting into procurement and digital, among other service
areas. The council is using its Transformation Fund to help alleviate some of
these pressures, including the establishment of a fixed-term Programme
Management Office. 
5 The council is working well with partners, and has engaged with communities,
the third sector and vulnerable groups to deliver transformation in Midlothian. 
6 From our review of a sample of the council’s integrated impact assessments,
we found it is not always clear how public consultation has influenced plans
and the council does not always clearly document how it intends to mitigate
potential negative impacts identified. 
Page 19 of 396

Page 20

Key messages | 4 
7 The council can demonstrate the impact of previous transformation activity,
including its Equipped for Learning project and No.11 Recovery Hub. It
recognises the need to improve how it reports this to the public. 
Page 20 of 396

Page 21

Introduction | 5 
Introduction 
1.  Transformation is about radically changing how councils operate and
deliver services to achieve planned outcomes in a financially sustainable
way (Transformation in councils, Accounts Commission, October 2024).
The 2023 Local Government Overview (LGO) notes that councils have
never faced such a challenging situation. Service demands have
increased after the Covid-19 pandemic and funding is forecast to reduce in
real terms. 
2.  The Accounts Commission’s Transformation in councils report
recognises that, while work has been ongoing in relation to local
government transformation for decades, a step change is required and the
pace and scale of transformation must increase significantly.
Transformation, through greater collaboration with partners, will be key for
councils to deliver more sustainable service models in challenging
financial climates.
3.  This report sets out how the council is redesigning and delivering more
efficient services to achieve planned outcomes.
4.  The Accounts Commission’s Strategy (2021-26) sets out its priorities to
focus on inequalities, funding, communities and recovery. The Code of
Audit Practice sets out the Best Value work required to report on these
priorities. 
5.  This report covers the thematic aspect of the Best Value audit
requirements. The Commission has directed auditors to report on
transformation and how councils are redesigning and delivering more
efficient services to achieve planned outcomes. In carrying out the work,
auditors have considered the following questions: 
• To what extent does the council have clear plans for transformation
that link to its priorities and support long-term financial
sustainability?
• To what extent do the council’s programme management
arrangements facilitate effective oversight of its transformation
plans?
• To what extent are partners and communities involved in the
development and delivery of the council’s plans for transformation?
Page 21 of 396

Page 22

Introduction | 6 
• To what extent has the council considered the impact of its
transformation activity, including on vulnerable or protected
groups?  
6.  An improvement action plan is included at Appendix 1 of this report.
This sets out audit recommendations in key areas, and the council’s
planned response including responsible officers and dates for
implementation.
7.  The coverage of the work is in line with the expectations for council’s
arrangements for the seven Best Value themes in the Local Government in
Scotland Act 2003, Best Value Statutory Guidance 2020 and we have
considered the Accounts Commission’s transformation principles set out in
Transformation in councils (Exhibit 1). 
Exhibit 1: Transformation principles 
Principle  
Vision
Have a clear vision that sets out the intended end state of any transformation
activity, focused on: 
• delivering large-scale recurring savings or generating income for the
council, contributing to its longer-term financial sustainability
• improving outcomes for citizens in line with council priorities
• taking a whole-system approach to see and realise opportunities both
within councils and more widely
• meeting the needs of the people who use services and reduce inequalities
• focusing on preventative activity, where applicable, to reduce the demand
for services and to make them sustainable in the longer term.
Planning
• Be clear on the scale of the change required and ensure transformation
plans are sufficiently ambitious to credibly respond to the scale of the
challenge.
• Commit staff with appropriate skills, time, and resources to ensure
transformation occurs at the scale and pace required and that there is
enough capacity for the changes to be embedded.
• Be clear about the timescales, costs, outcomes, and anticipated impacts of
transformation projects.
• Show urgency and progress projects at pace without compromising
appropriate governance on projects.
Governance
• Have a clear process for monitoring, evaluating, and reporting progress.
• Put in place effective governance and escalation processes so that the
transformation activities are well managed in their own right, but also able
to be given priority alongside other business-as-usual activities. 
Collaboration  • Develop better working relationships with communities and/or partners to
achieve a sustainable model of service delivery.
Page 22 of 396

Page 23

Introduction | 7 
Source: Accounts Commission
• Actively consider the opportunities offered by regional or national sectoral
collaboration, or by integrating services locally with partners, or by
supporting individuals and communities to achieve desired outcomes in
place of an existing service.
• Learn from good practice across Scotland and beyond.
Innovation 
• Implement new ways of thinking, including innovation, creativity and a
desire, willingness, and action to change and do things in new and different
ways that achieve the outcomes needed.
• Embed the right culture and behaviours to manage change and help
maximise the contribution of all the team.
Page 23 of 396

Page 24

Transformation planning | 8 
Transformation planning 
8.  Midlothian Council needs to ensure it can deliver sustainable services
now and in the future, and difficult decisions will need to be made to
achieve this. The Accounts Commission’s Local government budgets
2024/25 briefing noted that councils’ cumulative funding gap between
2025/26 and 2026/27 is £780 million. This means that, cumulatively,
councils need to identify and deliver recurring measures such as savings
or increased income of five per cent of their overall revenue budget to be
financially sustainable in the short term. 
Findings and evidence relating to the council’s transformation planning
arrangements 
Findings Evidence
The council’s
Transformation Blueprint
provides a clear strategic
plan for transformation
organised around five
themes. The
Transformation Blueprint
aligns with its Medium-
Term Financial Strategy
and the Single Midlothian
Plan. The council’s Digital
Transformation Strategy
and Workforce Strategy are
key enablers of the
Transformation Blueprint. 
Transformation Blueprint
The council agreed its Transformation Blueprint in June 2023,
which recognises the council as the fastest growing local
authority in Scotland. This strategic plan has five clear
objectives, including supporting the council in addressing the
£8.9 million funding gap. Work to support the Transformation
Blueprint is organised around five themes:
• Follow the money
• 21st century workforce
• Workplaces for the future
• Income generation and commercialisation
• Multi-agency transformation.
Each of the themes has an elected member sponsor and are
to be supported by a series of short projects, called sprints, to
be phased over several years. Examples of sprints include:
• Contract management
• Delivering joined-up services in ‘One Stop Shop’ hubs
• Digital transformation
• Estate rationalisation
• Advertising and marketing.
The council has outlined that sprints are intended to be 100-
day collaborative challenges but in reality activity is taking
longer than this.
Page 24 of 396

Page 25

Transformation planning | 9 
Findings Evidence
The Transformation Blueprint aligns with the ambitions set out
within the council’s Single Midlothian Plan and the Medium-
Term Financial Strategy. It is complemented by the council’s
Digital Transformation Strategy 2024-2029, Workforce
Strategy 2024-2029 and supports delivery of the Scottish
Health and Social Care Partnership Strategy and Midlothian’s
HSCP strategy. 
Digital Transformation
Midlothian Council approved its Digital Transformation
Strategy 2024-2029 in November 2024. Digital transformation
supports the council’s vision and is viewed as a key element
of driving change in the council and for the people of
Midlothian. Digital transformation will create efficiencies and
in so doing will assist the council in bridging its budget gap.
Specifically, the council is aiming to make better use of digital
tools, digitise and automate processes, use Artificial
Intelligence and enhance data-led decision making. The
council’s Digital Transformation Strategy 2024-2029 includes
four strategic pillars with activities sitting below these. The
pillars are:
• Automate: For an Efficient, Modern Council
• Reimagine: Transform Service Delivery
• Data: Deeper Insights and Preventative Operations
• Secure and Sustain: Protect and Preserve.
The council is currently progressing 22 key digital projects,
including implementing online payments through the
customer services platform, rollout of Microsoft 365 tools and
upgrading audio visual equipment across the learning estate. 
Creation of a 21st century workforce
One of the key themes within the Transformation Blueprint is
the creation of a 21st century workforce, which includes
workstreams that focus on both digital and human resource.
The council’s Workforce Strategy 2024-29 supports the
delivery of this theme, and demonstrates the council’s
innovation in its approach to addressing workforce and
capacity issues. For example, it has worked with education
providers to develop a programme of entry level
apprenticeships across key professional groups to enable the
council to grow its own workforce. The council has also
introduced staff development conversations which link to
workforce/succession plans.
The council is carrying out
a wide range of key
transformation initiatives to
progress the
Work to deliver the Transformation Blueprint is ongoing.
Current activities include, but are not limited to, reviews of the
large grants programme, council estate and contract
management; improvements to the council’s open revenues
Page 25 of 396

Page 26

Transformation planning | 10 
Findings Evidence
Transformation Blueprint. It
has identified priority
projects for 2025/26 and is
developing project plans to
support these. The council
recognises the fiscally
challenging environment it
is operating in and now
needs to find a way to
accelerate progress further. 
processes; implementation of the digital transformation
strategy; and work to develop the twin-stream collection of
waste and recycling, but as yet there are no projects with
quantified costs and benefits.
At March 2025, 24 projects were being monitored through
Transformation Blueprint progress reporting. Two projects
were complete: phase one of the school holiday programmes
project and phase one of the building maintenance services
contract project. Thirteen projects were at the business case
stage. 
The council identified five priority projects to be prioritised in
2025/26 as part of its Transformation Blueprint. One is
aligned with the workplaces of the future theme and the
others relate to the income generation theme. The projects
being taken forward are:
• A one-stop shop pilot in Gorebridge
• Commercial opportunities at Vogrie Country Park
• Introduction of a RingGo service for on-street parking
• Out of school childcare provision
• Early learning and childcare 52 week provision.
The council is now developing project plans for these and
they are expected to be reported to the Business
Transformation Steering Group in Spring 2025.
The Transformation Blueprint covers the period from 2023-28.
Therefore, the council now needs to find a way to accelerate
progress further within the fiscally challenging environment it
is operating in.
The council projects an
£8.9 million funding gap
between 2025/26 and
2028/29 and is working to
quantify projected savings
from delivering
transformation. 
The Medium-Term Financial Strategy (MTFS) approved in
February 2025 forecasts a funding gap of £8.9 million. As part
of its MTFS, the council intends to use one-off reserves to
help achieve a balanced budget up to 2027/28. The council
has also approved indicative increases in council tax from
2026/27 through to 2028/29.
The council has reported that the delivery of savings through
the Transformation Blueprint is its preferred route to financial
sustainability. At February 2025, it had not identified savings
or income generation for each of the projects to be taken
forward in 2025/26, so these were not included in the 2025/26
budget savings. It is now developing plans for these and it
intends to incorporate expected savings into its MTFS once
developed. It is important that plans are developed at pace in
order to ensure that these contribute to closing its funding
gap and reduce its reliance on one-off reserves to balance
future budgets.
Page 26 of 396

Page 27

Transformation planning | 11 
Recommendation 1
The council should finalise its plans for its identified priority
transformation projects, outlining savings to be achieved, costs and
anticipated financial and non-financial benefits.
Findings Evidence
In February 2023, the council earmarked £2 million from its
General Reserve to invest in projects to support the delivery
of the Transformation Blueprint.  The council reports that this
fund has been critical to the delivery of transformation,
particularly in terms of resourcing. In February 2025, the
council projected that the non-committed balance on this
earmarked fund would be £0.849 million at 31 March 2025.
The council reports that additional approvals in Q4 2024/25
for use of the fund have led to a further decrease in the
remaining balance. The council plans to consider options to
commit further reserves to supporting transformation as part
of the 2024/25 year-end financial reporting process.
Page 27 of 396

Page 28

Programme management | 12 
Programme management 
9.  It is essential that the council has good programme management
arrangements in place to ensure it is making sufficient progress against its
transformation plans. It is important that the council has the structures and
the staffing resource in place to deliver its transformation ambitions. In
addition, the council must ensure that both senior officers and elected
members have appropriate oversight of progress.
Findings and evidence relating to the council’s programme management
arrangements 
Findings Evidence
The council has effective
governance arrangements
in place for reporting
progress to the senior
leadership team and
elected members. It has
developed a
Transformation Blueprint
dashboard to provide an
overview of progress
across projects. This is
supported by detailed
papers on individual
projects.
The council has a Business Transformation Board (BTB) and
a Business Transformation Steering Group (BTSG). The BTB
is an officer-only board attended by senior officers. Its
purpose is to oversee Transformation Blueprint delivery and
to report progress to the Corporate Management Team and
BTSG.
The BTSG is formed of elected members and has cross-party
representation. Its purpose is to:
• scrutinise and approve the transformation work for onward
transmission to the Full Council;
• advise the Business Transformation Board on priorities
and risks; and
• allocate funding from the council’s Transformation Fund.
The council has developed a Transformation Blueprint
dashboard, which is used for reporting progress on the
Transformation Blueprint as whole to the Full Council, the
BTB and the BTSG. This includes:
• RAG statuses for the Transformation Blueprint as a whole
and for individual projects;
• key risks for the Transformation Blueprint as a whole;
• three key milestones since the previous update and for the
next three months;
• more detailed updates for individual projects.
The council is still at the early stages of delivering the
Transformation Blueprint, so for most projects key information
(such as financial savings) is still being developed. Therefore,
Page 28 of 396

Page 29

Programme management | 13 
Findings Evidence
the dashboards only include limited reporting of areas such
as costs, savings, anticipated benefits, and timescales. As
projects progress and more information becomes available,
the council should consider how to incorporate this into its
reporting. 
The Transformation Blueprint dashboards are supplemented
by more detailed papers on individual projects. These include
limited information about timescales, savings, or anticipated
benefits, reflecting the stage that the council is at with the
Transformation Blueprint. A number of papers did include
estimated costs. Overall, the papers reviewed provided
suitable information for senior leadership and elected
members on progress and issues relating to transformation
work.
The council faces
challenges with recruitment
and capacity in some
service areas and reports
that it is working to
address these. It has used
its Transformation Fund to
develop a fixed-term
Project Management Office
to support implementation
of the Transformation
Blueprint. 
As documented in our Best Value report on workforce
innovation, the council faces significant challenges related to
capacity and recruitment in some service areas. In some
cases, these are reflective of wider workforce issues across
local government in Scotland.  In particular, the council is
experiencing challenges recruiting into procurement and
digital, among other service areas.
We identified a number of instances illustrating recruitment
issues: 
• The council was repeatedly unsuccessful in recruiting a
suitably qualified person for transformation work on
developing a more robust approach to supporting children
with complex additional support needs transitioning to adult
services. These capacity issues caused delays in this work. 
• The council informed us that some of its project managers
are contractors owing to difficulties recruiting in-house project
managers, leading to increased costs. 
• The council’s Digital Transformation Strategy 2024-2029
notes difficulties in recruiting owing to a shortage of local
workers and competition from other sectors and local
authorities.
The council has used its Transformation Fund to establish a
Project Management Office (PMO) for a three-year period to
October 2026. 
The PMO, which includes six Project Managers and three
Project Support Officers, is led by the Executive Business
Manager (Transformation), who attends BTB, BTSG and
Midlothian Multi-Agency Transformation Management Group
meetings. The council reports that the Executive Business
Manager (Transformation) regularly reviews resourcing of the
Page 29 of 396

Page 30

Programme management | 14 
Recommendation 2
The council should consider how to incorporate consistent reporting of
costs, savings, anticipated benefits, and timescales into its
Transformation Blueprint dashboard updates as this information
becomes available.
Recommendation 3
The council should consider how it will resource its transformation work
after the current three-year term for its Project Management Office ends.
Findings Evidence
Transformation Blueprint and discusses this in fortnightly
meetings with the Chief Officer Corporate Solutions. 
The council informed us that the PMO has facilitated more
collaborative working, given better oversight across the
council’s transformation activities, and provided a forum for
staff to suggest transformation ideas and get support with
implementing transformation. 
The council has also used the Transformation Fund to create
additional posts in service areas to implement transformation.
However, the council has faced difficulties recruiting for some
of these posts. Moreover, even where recruitment is
successful, some projects require a deep knowledge of the
council, which newly-hired staff need time to develop. To
address this, the council has considered employing support
staff and has recruited consultants to mitigate capacity issues
around transformation work. 
There remains, however, an ongoing risk that recruitment and
capacity issues lead to overreliance on key individuals for the
delivery of transformation. In our Best Value report on
workforce innovation, we reported that there were some
examples of succession planning at the council, but that this
was not being done in a formalised or consistent way. The
council has since approved its revised Workforce Strategy
2024-34. The supporting action plan indicates the council’s
intentions to have succession plans in place for all parts of
the council by April 2026. 
Page 30 of 396

Page 31

Partnership working and community engagement | 15 
Partnership working and
community engagement 
10.  The Best Value in Scotland report noted that councils must now
rethink how they work together, and with local partners and communities,
to provide financially sustainable services. Few councils provide services
jointly or share support services across different councils to a great extent.
The scale and nature of the challenge, as set out in the Transformation in
councils report, means that it is only by working more collaboratively that
councils and their local partners, communities and the third sector will be
able to provide sustainable local services.
Findings and evidence relating to the council’s partnership working and
community engagement arrangements 
Findings Evidence
The council is working well
with partners to deliver
transformation in
Midlothian. 
One of the Transformation Blueprint themes is multi-agency
transformation. Projects being taken forward under this theme
include economic growth and skills; the Midlothian Aligned
Curriculum Offer; estate rationalisation; one stop shops; and
exploring the Safeguarding Through Rapid Intervention
(STRIVE) model. The council has established a board with its
partners, the Multi-Agency Transformation Management
Group (M-MATMG) to deliver whole system change, which is
chaired by the Chief Executive. Partners which are
represented on the M-MATMG include NHS Lothian, Police
Scotland, Scottish Fire and Rescue Service, University of
Edinburgh, Edinburgh College, Scottish Ambulance Service
and East Lothian Council.
As part of the workplaces for the future Transformation
Blueprint theme, the council reported that it will review its
workspaces to seek opportunities to share with partners and
link this with the multi-agency transformation programme. The
Transformation Blueprint is a standing item on the M-MATMG
agenda and estate rationalisation is an area of focus.
The council and its partners operate the No.11 Recovery
Hub, which offers support with mental health, substance
misuse and justice services for adults (Case study 1, page
18).
Page 31 of 396

Page 32

Partnership working and community engagement | 16 
Findings Evidence
The M-MATMG is exploring a multi-agency approach for early
intervention to support vulnerable individuals, known as
STRIVE. The council is working collaboratively with Police
Scotland, the Midlothian/East Lothian Public Protection Unit
and East Lothian Council on the project. 
As part of its work on economic growth and skills, the M-
MATMG visited Highland Council and Aberdeenshire Council
to look at their agendas for developing skills for pathways to
healthcare jobs. It is working with NHS Lothian, Edinburgh
University and Edinburgh College to explore how pathways
can be developed for Midlothian.
The council is working with Vattenfall Heat UK on a joint
venture known as Midlothian Energy Limited (MEL). This will
deliver low-carbon heat through energy captured from the
Millerhill Recycling and Energy Recovery Centre waste plant
to homes, education and retail properties in Midlothian (Case
study 2, page 19). There is a current business plan to extend
the network beyond this.
There is evidence of jointly
funded transformation
activity with partners.
MEL is a joint venture between the council and Vattenfall
Heat UK. The council provided a £1.6 million shareholder
equity injection into MEL to cover business costs of the
company and up to £8.6 million to allow the Shawfair project
to proceed. This is being matched by Vattenfall. MEL has also
benefitted from £7.4 million funding from the Scottish
Government’s Low Carbon Transition Programme.
In December 2023, the council received £2.2 million grant
funding from Zero Waste Scotland’s Recycling Improvement
Fund for the implementation of its twin stream recycling
project. The project aims to introduce a new residential waste
collection system to separate out paper and cardboard from
plastic by February 2026. 
The council is working with partners on Midlothian’s House
Project, which supports care experienced young people aged
16-26 to live independently. The council received Life
Changes Trust Funding to launch the National House Project
framework in Midlothian and has supported 40 care
experienced young people, with 65 per cent now in their own
permanent properties. 
The council engaged with
communities on its savings
options as part of its
2025/26 budget setting. It
has engaged with
communities on certain
projects within the
Transformation Blueprint.
Community engagement is important to Midlothian Council. 
The council ran a budget consultation for its 2025/26 budget
between October and November 2024. As part of this,
respondents were asked to rate the extent to which savings
proposals would negatively impact them, from no impact to
high impact. The consultation incorporated proposals being
considered as part of the Transformation Blueprint, including
Page 32 of 396

Page 33

Partnership working and community engagement | 17 
Findings Evidence
There is evidence of
engagement with the third
sector and vulnerable
communities on specific
projects, some of which
pre-date the
Transformation Blueprint. 
Vogrie Country Park commercialisation, closing Roslin library
and reviewing out of school childcare provision. 
Four out of the five Transformation Blueprint projects which
are now being prioritised for 2025/26 were included in the
consultation and the results for all four showed that the
majority of respondents rated these as having a low or no
negative impact on them. It will be important for the council to
engage with those who are impacted to a greater extent by
the proposals to shape its plans for redesigning services.
The council has been progressing various activities to support
the delivery of its Transformation Blueprint. Not all ongoing
projects require public consultation as some focus on the
council’s internal operations. Examples of community
engagement exercises which have been carried out as part of
the Transformation Blueprint include:
• Client Transport Review – the council is developing an
integrated transport policy as part of its client transport
review.  An online consultation was conducted from February-
March 2025 which aimed to explore ways in which the
transport system could be made more inclusive, fairer and
accessible to users, particularly those with additional support
needs (ASN). Feedback will be incorporated in the draft
policy, where appropriate. The council also presented
information on the new policy to an ASN parent chairs
meeting ahead of the online consultation launch.
• Large Grants Review – the council has established a short-
life working group as part of the review of its large grant
programme. Membership of the group includes representation
from the third sector interface and communities. The scope of
the group includes comparing different grant delivery models
across Scotland, developing options for funding core costs
against the current approach and adoption of and agreed
data/evidence informed approach to allocating funding.
Recommendations for future funding are expected to be
presented to the Full Council in May 2025.
The council also engaged with service users in its
transformation work prior to the Transformation Blueprint. For
example:
• The council provided numerous examples of engagement
with people who use services through the No.11 hub, which
opened in November 2019. For example, within justice
services there is a focus group of community advisors, who
have been part of the justice system (known as Bound) which
are consulted on community justice projects and social
worker recruitment. The justice service has also engaged with
women who use the Spring Service to identify ways to
Page 33 of 396

Page 34

Partnership working and community engagement | 18 
Case study 1
No. 11 Recovery Hub 
The council has worked with NHS Lothian and third sectors partners through the health and
social care partnership to develop the No.11 Recovery Hub. This provides shared care for
recovery and services which focus on early intervention and prevention. Community substance
use and mental health staff, employed by both NHS Lothian and the council, are co-located with
Justice Social Work and third sector partners at the Hub. All services within the No.11 Recovery
Hub work in partnership to provide a person-centred, trauma informed, holistic approach to
improving people’s health and well-being. 
The council and its partners deliver a variety of services through the No.11 Recovery Hub. For
example: 
− Health and social care partners work with third sector partners to identify people who are
at high risk of severe drug-related harm and provide rapid support to the individual for
engagement or re-engagement with holistic care, such as medication assisted treatment
for those who are opiate dependent.
− The Midlothian Young Peoples’ Advice Service (MYPAS) provides support, information
and advice on drugs and alcohol to young people within Midlothian and East Lothian.
− The council worked with a third sector partner to develop and implement a new Mental
Health and Resilience Service for citizens between 18-65 years old. This provides same
day access for individuals experiencing crisis and distress related to their mental health
and wellbeing. 
− The council delivers a bespoke service for women called the Spring Service in partnership
with NHS, Health in Mind, Access to Industry and Woman’s Aid. This provides support to
women who have experience of trauma or who have challenges with substance abuse or
mental health and are at risk of entering the justice system.
The council has provided a range of data on the outputs and outcomes generated through the
No.11 centre which demonstrate its impact. For example, the council reported that 107 people
Findings Evidence
develop the service further, such as sessions addressing
issues around online safety. 
• The council reports that it engages annually with
stakeholders, including pupils, families, staff and senior
leaders on its Equipped for Learning project. This five-year
project (2021-2026) aims to equip learners with digital skills
for learning, life and work. The council has established a
Digital Leader Network of staff from school and early years
settings who influence and shape the planned work. The
council also reports engagement with parent council chairs
and pupil councils. The council is able to demonstrate how
engagement has influenced the project. For example, the
council created communication grids for iPad introductory
materials and the 2025 pupil survey to improve accessibility in
response to feedback received.
Page 34 of 396

Page 35

Partnership working and community engagement | 19 
engaged in ongoing support through MYPAS in Midlothian, of which 47 reported a reduction in
substance use and 11 reported becoming drug-alcohol free. The council also reported that
MYPAS uses a ‘Teen Star’ outcomes measuring tool at initial and final assessments. This
facilitates an assessment of progress across six categories, such as drugs and alcohol,
wellbeing, and safety and security. The council reports that average scores across all
categories improved between initial and final assessments in Midlothian for 2023/24.
The council also has three performance indicators relating to substance use services and
mental health, which it measures quarterly. These monitor mental health bed occupancy and
waiting times for referrals relating to ‘Adults with Incapacity’, drugs and alcohol. The council
reported that during Q1-Q3 24/25:
• Waiting times were below the 12-week target for 100 per cent of ‘Adults with Incapacity’
reports;
• Waiting time targets for drugs and alcohol referrals exceeded the target of treatment
being offered within three weeks in 90 per cent of cases (100 per cent of cases in Q1 and
Q3 and in 98.11 per cent of cases in Q2); and
• The target of maintaining mental health bed occupancy below 100 per cent was met in
Q1, but not in Q2-3 owing to increases in new presentations and existing patients
requiring hospital admission.
Source: Audit Scotland 
Case study 2 
Midlothian Energy Limited (MEL) 
Midlothian Energy Limited is an energy services company which is a joint venture between
Midlothian Council and Vattenfall Heat UK. The company was set up to deliver low carbon
energy projects across Midlothian and supports the council’s 2020 Climate Change Strategy.
Waste heat captured from the Millerhill Recycling and Energy Recovery Centre waste plant will
be supplemented with other waste heat sources and aims to provide low-carbon heat to homes,
education and retail properties in the Midlothian region. The council reports that waste heat
captured and supplied by MEL will be cheaper than alternative low-carbon sources and not
affected by the current wholesale energy cost inflation.
Initially, the project will supply low-carbon heat to around 3,000 homes, education and retail
spaces in Midlothian’s new town, Shawfair. The first connection to a residential property was
achieved in December 2024. The council and Vattenfall are aiming to expand the MEL network
into existing buildings in Midlothian and Edinburgh over the next five years.
MEL is expected to benefit the council’s long-term financial position, while providing both
environmental and community benefits, such as helping to achieve its net zero carbon ambition
by 2030, jobs creation, outreach events for schools and generating local supply chain
opportunities.
Source: Audit Scotland
Page 35 of 396

Page 36

Impact of transformation | 20 
Impact of transformation 
11.  It is important that the council has success measures in place to
demonstrate the impact of its transformational activity on service quality;
outcomes for people who use services, inequalities and/or savings. 
Findings and evidence relating to the impact of the council’s transformation
activity 
Findings Evidence
The council can
demonstrate the impacts of
previous transformation
projects through a variety
of success measures. It
should continue to
establish and monitor
impacts and outcomes for
transformation as work
progresses with the
Transformation Blueprint. 
As part of the audit, we requested case study examples of
successful transformation achieved by the council to date. We
found that for each project, success measures were in place.
Equipped for Learning
The council conducted surveys with pupils, staff and families
to get feedback on the programme. This fed into the
Equipped for Learning Digital Strategy 2024, which set
priorities for the programme going forward. 
Each priority has an ‘Impact Measure Challenge Question’,
i.e. the question to be answered in order to assess whether
the priority has been addressed successfully. For each
question, the council sets out the position it is aiming to reach
and by what date. For example, in feedback staff requested
training and guidelines for fast-moving technological
developments such as AI. In response, the council set a
priority to develop a robust professional learning offer to
equip staff with the digital skills they need, including for AI, by
June 2026.
The council could further strengthen its future priorities for the
project by adding quantifiable success measures where
appropriate.
No.11 Recovery Hub
The council provided a range of data on the outputs and
outcomes generated through the No.11 Recovery Hub.
Examples are provided in Case study 1, page 18.
Midlothian Energy Limited (MEL)
Midlothian Energy Limited is expected to benefit the council’s
long-term financial position, while providing both
environmental and community benefits (Case study 2, page
19). Anticipated benefits in relation to these areas are set out
Page 36 of 396

Page 37

Impact of transformation | 21 
Findings Evidence
in MEL’s Business Plan 2025-29. The Business Plan also
includes financial forecasts for MEL over a 40-year period. 
Ongoing transformation work
The council told us that there are no separate key
performance indicators for the Transformation Blueprint work,
but that projects contribute to improved service delivery which
is reported to elected members through Cabinet and the
Performance, Review and Scrutiny Committee. It said that
Senior Responsible Officers determine reporting at a service
level.
While committee papers set out the rationale for going ahead
with projects, most projects in the Transformation Blueprint do
not have success measures in place at this stage. However,
we identified good practice in this area in the council’s Waste
Services In-Cab transformation project. The council listed
benefits with contextual information, set quantified measures
of success for each benefit, and set out baselines and
measurement frequency. The council also considered what
benefits might be achieved under different scenarios.
In summary, the council should apply a similarly robust
approach to all projects in its Transformation Blueprint as it
moves forward with this work. 
The council recognises that
it should be more
transparent in reporting the
impacts of its
transformation work and is
taking steps to improve
this.
As noted above, the council collects a variety of information
on the impacts of its transformation work. The council
acknowledges that it could do more to publicly report these.
In March 2025, it included ‘good news’ stories around
transformation in its staff newsletter, which is publicly
available on the council’s website. It could supplement this by
publicly reporting progress and impacts of key transformation
projects. This could include both projects still in progress and
those already implemented.
The council has recently developed a Transformation
webpage, which it plans to use to inform the public on
delivery of transformation workstreams against the five
Transformation Blueprint themes as work progresses. 
In the council’s integrated
impact assessments for
transformation proposals,
it is not always clear how
public consultation has
influenced plans, nor what
mitigating actions are in
place to address potential
negative impacts. 
The council published integrated impact assessments (IIAs)
for a number of savings proposals in its MTFS 2025/26 to
2028/29. These documented potential negative impacts on
vulnerable groups. While mitigating actions were generally set
out within these, two of the eleven IIAs did not set out any
mitigating actions for these negative impacts. Three IIAs
concluded that the proposal should not go ahead owing to
potential negative impacts, but these proposals were
approved in the council’s budget setting meeting in February
Page 37 of 396

Page 38

Impact of transformation | 22 
Recommendation 4
The council should clearly report the impact of its transformation activity
to the public.
Recommendation 5
The council should consistently document how it intends to mitigate
potential negative impacts from its transformation proposals within its
integrated impact assessments.
Findings Evidence
2025. The council plans to agree mitigating actions as part of
the development process. 
The IIAs published with the MTFS 2025/26 to 2028/29 also
demonstrate limited public consultation beyond the council’s
budget survey. The council should ensure that this is
documented in IIAs.
The council provided a number of additional IIAs alongside
those published with the MTFS 2025/26 to 2028/29. These
primarily identified neutral or positive impacts. They set out
details of consultation with service users and other
stakeholders, but it is not always clear how this contributed to
proposals.
The council has guidance and training in place around IIAs,
so should make sure that this is adhered to in practice.
Page 38 of 396

Page 39

Appendix | 23 
Appendix
Improvement action plan
Issue/risk Recommendation
Agreed management
action/timing
1. Transformation planning
The council is carrying out a wide
range of activities to progress the
Transformation Blueprint. It has
identified priority projects for
2025/26 and is developing project
plans to support these. The
council recognises the fiscally
challenging environment it is
operating in and now needs to
find a way to accelerate progress
further.
The council should finalise its
plans for its identified priority
transformation projects,
outlining savings to be
achieved, costs and
anticipated financial and non-
financial benefits.
Management response
The Council has reported
that the delivery of
savings through the
Transformation Blueprint
is its preferred route to
financial sustainability.
Transformation projects
are initiated once
approval for funding etc.
is agreed through the
Council’s governance
route. Currently,
transformation projects
such as Waste In-Cab,
Client Transport,
Customers Payments
and Open Revenues
have been approved and
are underway. Plans for
the proposals agreed at
Council in February 2025
are being developed and
when Business Cases
are approved, plans for
delivery will be
developed. Once
expected or identified
savings are known these
will be incorporated into
the MTFS. It is
recognised pace is
required to ensure
transformation
contributes to closing the
Council’s funding gap
and reduce its reliance
on one-off reserves to
balance future budgets.
Page 39 of 396

Page 40

Appendix | 24 
Issue/risk Recommendation
Agreed management
action/timing
Responsible officer
Business Transformation
Board
Business Transformation
Steering Group
Actioned by
December 2025
2. Reporting progress of
transformational activities
The council has effective
governance arrangements in
place for reporting progress to
the senior leadership team and
elected members. It has
developed a Transformation
Blueprint dashboard to provide
an overview of progress across
projects. This is supported by
detailed papers on individual
projects.
The council should consider
how to incorporate consistent
reporting of costs, savings,
anticipated benefits, and
timescales into its
Transformation Blueprint
dashboard updates as this
information becomes
available.
Management response
The Transformation
Blueprint dashboard is a
summary of the individual
transformation
projects/workstreams.
The dashboard is
supported by individual
project documentation
through which spend,
timescales and benefits
are reported through
Project Boards and
relevant Committees.
The dashboard will
continue to report on key
milestones and project
status and incorporate
key anticipated benefits
for each project.
Financial reporting on
overall transformation
spend will be
incorporated from Q1
2025/26. Individual
project spend is
monitored through
Project Boards. Savings
or income generation
identified from the
delivery of projects will
be incorporated in the
MTFS.
Responsible officer
Executive Business
Manager, Transformation
Page 40 of 396

Page 41

Appendix | 25 
Issue/risk Recommendation
Agreed management
action/timing
Business Transformation
Steering Group
Actioned by
December 2025
3. Resources for
transformation
The council faces challenges with
recruitment and capacity in some
service areas and reports that it
is working to address these. It
has used its Transformation Fund
to develop a fixed-term Project
Management Office to support
implementation of the
Transformation Blueprint.
The council should consider
how it will resource its
transformation work after the
current three-year term for its
Project Management Office
ends.
Management response
The future resourcing of
Transformation work and
the Programme
Management Office will
be considered as part of
the Council’s
Transformation Blueprint
and strategic workforce
and organisational
planning. 
Responsible officer
Business Transformation
Steering Group
Midlothian Council
Actioned by
August 2027
4. Reporting the impact of
transformational activity
The council recognises that it
should be more transparent in
reporting the impacts of its
transformation work and is taking
steps to improve this.
The council should clearly
report the impact of its
transformation activity to the
public. 
Management response
Public information is
communicated through
various social media
channels, and a local
community radio
channel. Transformation
work is also shared on
the news pages of the
Council’s website and
media releases to
highlight where
achievements and
milestones have been
reached. There have
been recent social media
releases highlighting the
Council’s key
performance statistics
some of which link to
transformation initiatives.  
Page 41 of 396

Page 42

Appendix | 26 
Issue/risk Recommendation
Agreed management
action/timing
The development of the
Council’s Transformation
web pages will be used
to strengthen public
communications and
highlight progress and
successes to the public.
Responsible officer
Transformation
Programme Management
Office
Actioned by
August 2025
5. Integrated impact
assessments
In the council’s integrated impact
assessments for transformation
proposals, it is not always clear
how public consultation has
influenced plans, nor what
mitigating actions are in place to
address potential negative
impacts. 
The council should
consistently document how it
intends to mitigate potential
negative impacts from its
transformation proposals
within its integrated impact
assessments. 
Management response
The Council ensures the
importance and legal and
moral reasons for
Integrated Impact
Assessments is known to
relevant staff through the
delivery of training.
Training is delivered in
partnership with City of
Edinburgh Council, East
Lothian Council, West
Lothian Council and NHS
Lothian. The training will
be reviewed to ensure it
focuses on mitigating
factors for transformation
proposals.
Responsible officer
Transformation Project
Senior Responsible
Officer
Actioned by
December 2025
Page 42 of 396

Page 43

Midlothian Council
Transformation: how councils are redesigning and
delivering more efficient services to achieve planned
outcomes 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot 
AS.5.0
Page 43 of 396

Page 44

Page 44 of 396

Page 45

2
Audit Committee
Monday 16 June 2025
Item No 5.2   
Annual Treasury Management Report 2024/25 
Report by David Gladwin, Chief Financial Officer & Section 95 Officer 
Report for Decision 
1 Recommendations 
The Audit Committee is invited to consider this report before the final
report is presented to Council.  Committee should note that the
proposed recommendation to Council is that it note the Annual
Treasury Management Report 2024/25. 
2 Purpose of Report/Executive Summary 
The purpose of the report is to inform members of the Audit Committee
of the Treasury Management activity undertaken in 2024/25 and the
year-end position. 
Date: 2 June 2025
Report Contact:
Gary Thomson, Senior Finance Business Partner
gary.thomson@midlothian.gov.uk 
Page 45 of 396

Page 46

3 Background 
The main points arising from treasury activity in 2024/25 were: 
• The pooled internal loans fund rate for General Fund and HRA
was 2.73% in 2024/25, which is again expected to be one of the
lowest when benchmarked against all mainland Authorities in
Scotland; 
• Were the pooled internal loans fund rate to have equated to the
Scottish weighted average of 3.66%, this would have generated
loan charges in 2024/25 of £26.4 million.  The Council’s actual
2024/25 loan charges for General Services and HRA were £22.3
million, representing a cash saving (compared to the Scotland
weighted average) of £4.1 million in 2024/25; 
• Total long term borrowing maturing in the year amounted to
£1.426 million, comprising the following:- 
o £0.057 million of PWLB Annuities of various tenors and
interest rates;
o £0.626 million of PWLB Maturities (original 
o £0.673 million of Annuity and EIP, and £0.070 million of
interest free loans. 
• Total new long term borrowing taken in the year amounted to
£40.000m, this being four £10.000 million loans from PWLB:- 
o 2 x £10.000 million Maturity loans drawn on 20 August
2024 with tenors of 4 and 4.5 years and at interest rates of
4.15% and 4.13% respectively;
o 1 x £10.000 million Maturity loan drawn on 25 November
2024 with a tenor of 5.5 years and at an interest rate of
4.67%;
o 1 x £10.000 million Equal Instalment of Principal (EIP)
loan drawn on 20 December 2024 with a total tenor of 10
years and at an interest rate of 4.49% 
all drawing down loan funding to fund the Council’s 2024/25
capital plans in line with the 2024/25 Treasury Management and
Investment Strategy approved by Council on 27 February 2024; 
• The remainder of the 2024/25 borrowing requirement was
supported by the change in policy to no longer fully cash back
the Council’s useable reserves and to run down cash balances,
to allow the Council to navigate past the current interest rate
plateau; 
• As a result, the Council were under-borrowed by £90.421 million
(19% of the borrowing Capital Financing Requirement (CFR)) at
Page 46 of 396

Page 47

31 March 2025.  This means that the Council has funded the
majority (81%) of its underlying borrowing requirement as at 31
March 2025.  This position is prudent in the current economic
climate (with PWLB rates forecast to drop from their prevailing
rates, across the next 2-3 financial years), as it balances longer-
term interest rate and refinancing risk with short-medium term
budgetary implications; 
• The average rate of interest paid on external debt was 3.14% in
2024/25, up from 3.00% in 2023/24 reflective of the financing of
the Council’s CFR in the current interest rate environment; 
• Only instant access deposits were placed during the year, with
each deposit with an approved counterparty in line with the
Council’s approved creditworthiness process as outlined in the
“Treasury Management and Investment Strategy 2024/25 &
Prudential indicators” (TMSS 24/25) report approved by Council
on 27 February 2024.  The Council’s deposit portfolio at 31
March 2025 is outlined in Table 2 below and in detail in Table 11
in Appendix 1; 
• The average rate of return on deposits was 5.03% in 2024/25
(exceeding the benchmark1 of 4.82% for the twenty first year in
succession) with total interest earned on deposits totalling
£2.438 million and reflecting the approved strategy in the TMSS
24/25; 
• Useable reserves at 31 March 2025 equated to £85.295 million,
with cash balances partly cash backing reserves and partly used
to support the deferral of borrowing as outlined in the TMSS for
2025/26. 
• No debt rescheduling was undertaken during 2024/25. 
A detailed report “Annual Treasury Management Review 2024/25” on the
activity during 2024/25 is attached as Appendix 1. 
The Treasury Portfolio at the start and end of the financial year is shown
in Tables 1 and 2 below. 
1 3 month forward uncompounded SONIA (Sterling Overnight Index Average) which reflects the
weighted average duration of the Council’s portfolio for the year
Page 47 of 396

Page 48

Table 1: Loan Portfolio at 1 April 2024 and 31 March 2025 
Loan Type
Principal
Outstanding
1 Apr 2024
£000’s
Principal
Outstanding
31 Mar 2025
£000’s
Movement 
£000’s
PWLB Annuity 452 395 -57
PWLB Maturity 304,128 333,502 +29,374
PWLB EIP 0 10,0000 +10,000
LOBO 20,000 20,000 0
Other Market Loans 16,221 15,548 -673
Salix Loans 70 0 -70
Total Loans 340,871 379,445 +38,574    
Underlying Borrowing
Requirement
401,845 469,866 +68,021
Over/(Under) Borrowed -60,974 -90,421 -29,447 
Table 2: Deposits at 1 April 2024 and 31 March 2025 
Deposit Type
Principal
Outstanding
1 Apr 2024
£000’s
Principal
Outstanding
31 Mar 2025
£000’s
Movement 
£000’s
Bank Call Accounts 1,518 538 -980
Money Market Funds 25,100 25,946 +846
Bank Fixed Term Deposit Accounts 30,000 0 -30,000
Total Deposits 56,618 26,484 -30,134    
Useable Reserves 84,505 85,295 +1,504 
Throughout 2024/25, all counterparties that the Council placed deposits
with met their obligations in respect of the return of the deposited funds
and interest receivable in full and on the required dates. 
5 Report Implications (Resource, Digital and Risk) 
5.1 Resource 
Treasury Management activity during the year, in accordance with the
approved strategy, has once again been effective in minimising loan
charges through minimising the cost of borrowing and maximising the
return on deposits within the parameters set by the strategy for the year. 
Although benefits from Treasury Management activity continue to accrue
there are no direct financial implications or other resource issues arising
from this report.
Page 48 of 396

Page 49

The loan charges associated with Capital Expenditure and Treasury
Management activity during 2024/25 are reported in the Financial
Monitoring 2024/25 – General Fund Revenue report and HRA 2024/25
Outturn report elsewhere on the Council agenda for 24 June 2025. 
5.2 Digital 
None. 
5.3 Risk 
As the Council follows the requirements of the CIPFA Code of Practice
and the Prudential Code this minimises the risks involved in Treasury
Management activities place.  For those risks that do exist there are
robust and effective controls in place to further mitigate the level of risks.
These include full written Treasury Management Practices, which define
the responsibilities of all staff involved and reflect the provisions of the
Prudential and Treasury Management Codes. 
5.4 Ensuring Equalities (if required a separate IIA must be completed) 
This report does not recommend any change to policy or practice and
therefore does not require an Equalities Impact Assessment. 
5.5 Additional Report Implications 
See Appendix A 
Appendices:- 
Appendix 1: Annual Treasury Management Review 2024/25 
Page 49 of 396

Page 50

APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Not applicable 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
The report does not directly impact on Delivering Best Value. 
A.5 Involving Communities and Other Stakeholders 
Although no external consultation has taken place, cognisance has
been taken of professional advice obtained from Link Asset Services,
the Council’s appointed Treasury Consultants. 
A.6 Impact on Performance and Outcomes 
The strategies adopted are an integral part of the corporate aim to
achieve Best Value as they seek to minimise the cost of borrowing by
exercising prudent debt management and placement of deposits. This
in turn helps to ensure that the Council’s capital expenditure is
sustainable in revenue terms. 
A.7 Adopting a Preventative Approach 
Page 50 of 396

Page 51

Not applicable. 
A.8 Supporting Sustainable Development 
Not applicable. 
Page 51 of 396

Page 52

Appendix 1 
Annual Treasury Management
Review 2024/25
Midlothian Council
June 2025 
Page 52 of 396

Page 53

Contents 
1 The Council’s Capital Expenditure and Financing 2024/25
2 The Council’s overall borrowing need
3 Treasury Position as at 31 March 2025
4 The Strategy for 2024/25
5 The Economy and Interest Rates
6 Borrowing Rates in 2024/25
7 Borrowing Outturn for 2024/25
8 Deposit Rates in 2024/25
9 Deposit Outturn for 2024/25
10 Performance Measurement
11 Conclusion 
Page 53 of 396

Page 54

This Council is required by regulations issued under the Local Government in
Scotland Act 2003 to produce an annual treasury management review of
activities and the actual prudential and treasury indicators for 2024/25. This
report meets the requirements of both the updated CIPFA Code of Practice on
Treasury Management, (the Code), and the updated CIPFA Prudential Code
for Capital Finance in Local Authorities, (the Prudential Code).
During 2024/25 the minimum reporting requirements were that the full Council
should receive the following reports:
• an annual treasury strategy in advance of the year (Council 27
February 2024);
• a mid-year, (minimum), treasury update report (Council 17 December
2024);
• an annual review following the end of the year describing the activity
compared to the strategy, (this report);
The regulatory environment places responsibility on members for the review
and scrutiny of treasury management policy and activities.  This report is,
therefore, important in that respect, as it provides details of the outturn position
for treasury activities and highlights compliance with the Council’s policies
previously approved by members.  
This Council confirms that it has complied with the requirement under the Code
to give prior scrutiny to all of the above treasury management reports by the
Audit Committee before they are reported to the full Council.  
Page 54 of 396

Page 55

1. The Council’s Capital Expenditure and Financing
2024/25
The Council undertakes capital expenditure on long-term assets.  These
activities may either be:
• Financed immediately through the application of capital or revenue
resources (capital receipts, capital grants, revenue contributions etc.), which
has no resultant impact on the Council’s borrowing need; or
• If insufficient financing is available, or a decision is taken not to apply
resources, the capital expenditure will give rise to a borrowing need.
The actual capital expenditure forms one of the required prudential indicators. 
The table below shows the actual capital expenditure and how this was
financed. 
2023/24 2024/25 2024/25
Actual Budget Actual
£000 £000 £000
General Fund
Capital Expenditure 47,656 78,524 48,778
Available Funding 26,903 28,579 19,155
Borrowing Required 20,753 49,945 29,623
HRA
Capital Expenditure 50,412 103,054 53,175
Available Funding 6,724 19,611 9,523
Borrowing Required 43,688 83,443 43,652
General Fund and HRA
Capital Expenditure 98,068 181,578 101,953
Available Funding 33,627 48,190 28,678
Borrowing Required 64,441 133,388 73,275
Table 1: Capital Expenditure + Financing
Page 55 of 396

Page 56

2. The Council’s Overall Borrowing Need
The Council’s underlying need to borrow for capital expenditure is termed the
Capital Financing Requirement (CFR).  This figure is a gauge of the Council’s
indebtedness.  The CFR results from the capital activity of the Council and what
resources have been used to pay for the capital spend.  It represents the
2024/25 unfinanced capital expenditure (see above table), plus prior years’ net
or unfinanced capital expenditure which has not yet been paid for by revenue
or other resources. 
Part of the Council’s treasury activities is to address the funding requirements
for this borrowing need.  Depending on the capital expenditure programme, the
treasury service organises the Council’s cash position to ensure sufficient cash
is available to meet the capital plans and cash flow requirements.  This may be
sourced through borrowing from external bodies (such as the Government,
through the Public Works Loan Board [PWLB] or the money markets), or
utilising temporary cash resources within the Council. 
Reducing the CFR – the Council’s underlying borrowing need (CFR) is not
allowed to rise indefinitely.  Statutory controls are in place to ensure that capital
assets are broadly charged to revenue over the life of the asset.  The Council
is required to make an annual revenue charge, called the Scheduled Debt
Amortisation (or loans repayment), to reduce the CFR.  This is effectively a
repayment of the borrowing need. This differs from the treasury management
arrangements which ensure that cash is available to meet capital commitments. 
External debt can also be borrowed or repaid at any time, but this does not
change the CFR. 
The total CFR can also be reduced by:
• the application of additional capital financing resources (such as unapplied
capital receipts); or 
• charging more than the minimum loan repayment each year through an
additional revenue charge. 
The Council’s CFR for the year is shown below, and represents a key prudential
indicator. 
31-Mar-24 2024/25 31-Mar-25
Actual Budget Actual
£000 £000 £000
Opening balance 346,898£  496,656£  401,845£ 
Add Borrowing Required 64,441£    73,893£    72,862£   
Loans Fund Review Retrospective -£              -£             5,525£     
Less scheduled debt amortisation (9,494)£     (10,760)£  (10,366)£  
Closing balance 401,845£  559,789£  469,866£ 
Table 2: Council's Underlying Borrowing Requirement
CFR:
Page 56 of 396

Page 57

Borrowing activity is constrained by prudential indicators for net borrowing and
the CFR, and by the authorised limit. 
Gross borrowing and the CFR - in order to ensure that borrowing levels are
prudent over the medium term and only for a capital purpose, the Council
should ensure that its gross external borrowing does not, except in the short
term, exceed the total of the capital financing requirement in the preceding year
(2023/24) plus the estimates of any additional capital financing requirement for
the current (2024/25) and next three financial years.  This essentially means
that the Council is not borrowing to support revenue expenditure.  This indicator
allows the Council some flexibility to borrow in advance of its immediate capital
needs in 2024/25.  The table below highlights the Council’s gross borrowing
position against the CFR (excluding PFI schemes).  The Council has complied
with this prudential indicator. 
The authorised limit – this Council has kept within its authorised external
borrowing limit as shown by the table below.  Once this has been set, the
Council does not have the power to borrow above this level. 
The operational boundary – the operational boundary is the expected
borrowing position of the Council during the year.  Periods where the actual
position is either below or over the boundary is acceptable subject to the
authorised limit not being breached. 
31-Mar-24 2024/25 31-Mar-25
Actual Budget Actual
£000 £000 £000
Gross Borrowing 340,871£  509,105£  379,445£ 
CFR 401,845£  559,789£  469,866£ 
Table 3: Council's Gross Borrowing Position
2024/25
Authorised limit - borrowing £   604,957
Operational boundary - borrowing £   604,957
Maximum gross borrowing position £   379,623
Average gross borrowing position £   358,618
Table 4: Gross Borrowing against
Authorised Limit / Operational Boundary
Page 57 of 396

Page 58

3. Treasury Position as at 31 March 2025
The Council’s debt and investment position is organised by the treasury
management service in order to ensure adequate liquidity for revenue and
capital activities, security for investments and to manage risks within all treasury
management activities. Procedures and controls to achieve these objectives
are well established both through Member reporting detailed in the Purpose
section of this report, and through officer activity detailed in the Council’s
Treasury Management Practices.  At the beginning and the end of 2024/25 the
Council‘s treasury (excluding borrowing by PFI and finance leases) position
was as follows: 
31 March
2024
Principal
Rate/
Return
Average
Life
(Yrs)
31 March
2025
Principal
Rate/
Return
Average
Life
(Yrs)
Debt
Fixed Rate Debt
PWLB 304,580£    3.02% 29.40 343,897£    3.16% 25.79
Market 21,291£      3.01% 28.34 20,548£      3.03% 27.68
Total Fixed Rate Debt 325,871£    3.02% 29.33 364,445£    3.15% 25.90
Variable Rate Debt
PWLB -£                  n/a n/a -£                  n/a n/a
Market 15,000£      4.63% 26.71 15,000£      4.63% 25.71
Total Variable Rate Debt 15,000£      4.63% 26.71 15,000£      4.63% 25.71
Total debt/gross borrowing 340,871£   3.09% 29.22 379,445£   3.21% 25.89
CFR 401,845£   469,866£  
Over/(under) borrowing (60,974)£    (90,421)£   
Deposits
Fixed Rate Deposits
In House 30,000£      5.12% 0.83 -£                  n/a n/a
With Managers -£                  n/a n/a -£                  n/a n/a
Total Fixed Rate Deposits 30,000£      5.12% 0.83 -£                  n/a n/a
Variable Rate Deposits
In House 26,618£      5.28% 0.01 26,484£      4.54% 0.01
With Managers -£                  n/a n/a -£                  n/a n/a
Total Variable Rate Deposits 26,618£      5.28% 0.01 26,484£      4.54% 0.01
Total Deposits 56,618£      5.20% 0.45 26,484£      4.54% 0.01
Table 5: Treasury Position
Page 58 of 396

Page 59

The maturity structure of the debt portfolio was as follows: 
The maturity structure of the Council’s deposits was as follows: 
The exposure to fixed and variable interest rates on debt was as follows:- 
£000 % £000 %
Under 12 months 1,426£       0% 0% to 50% 2,263£       1%
12 months to 2 years 1,263£       0% 0% to 50% 11,759£    3%
2 years to 5 years 22,323£    7% 0% to 50% 45,346£    12%
5 years to 10 years 45,106£    14% 0% to 50% 60,095£    16%
10 years to 20 years 32,365£    10% 0% to 50% 22,220£    6%
20 years to 30 years 51,505£    16% 0% to 50% 60,879£    16%
30 years to 40 years 81,883£    25% 0% to 50% 81,883£    22%
40 years to 50 years 100,000£  31% 0% to 50% 90,000£    24%
50 years and above 5,000£       2% 0% to 50% 5,000£       1%
Total 340,871£  106% 379,445£  100%
Table 6: Maturity Structure of Debt Portfolio
31-Mar-24 2024/25 31-Mar-25
Actual Original Limits Actual
%
31-Mar-24 31-Mar-25
£000 £000
Deposit
Under 1 Year 56,618£     26,484£    
Over 1 Year -£                -£               
Total 56,618£     26,484£    
Table 7: Maturity Structure
of Deposit Portfolio
£0 % £0 %
Fixed Interest Rate Exposure £325,871 96% 0% to 100% 364,445£ 96%
Variable Interest Rate Exposure £   15,000 4% 0% to 30% 15,000£   4%
Total 340,871£ 100% 379,445£ 100%
Table 8: Fixed/Variable Interest Rate Exposure of Debt Portfolio
31-Mar-24 2024/25 31-Mar-25
Actual Original Limits Actual
%
Page 59 of 396

Page 60

4. The Strategy for 2024/25 
At the outset of the financial year, the Council were under borrowed by £60.974
million and holding £56.618 million in instant access accounts and fixed term
deposits. 
Interest rate forecasts within the 2024/25 Treasury Management & Investment
Strategy suggested that interest rates were expected to gradually fall
throughout the year and the forthcoming 2 financial years. 
Link Interest Rate forecasts at time of TMIS 2024/25 setting (February 2024) 
MUFG Interest Rate forecasts at end of 2024/25 Financial Year (May 2025,
unchanged from March 2025) 
With interest rates on new borrowing remaining elevated throughout much of
2024/25 at the medium-long end of the curve, borrowing was undertaken at the
short end, in order to navigate past the expected hump in interest rates, and
timed to correlate to dips in Gilt Yields. 
Borrowing undertaken during the 2024/25 financial year amounted to £40.000
million, this comprising 
• 2 x £10.000 million Maturity loans drawn on 20 August 2024 with tenors
of 4 and 4.5 years and at interest rates of 4.15% and 4.13%
respectively;
• 1 x £10.000 million Maturity loan drawn on 25 November 2024 with a
tenor of 5.5 years and at an interest rate of 4.67%;
• 1 x £10.000 million Equal Instalment of Principal (EIP) loan drawn on
20 December 2024 with a total tenor of 10 years and at an interest rate
of 4.49% 
all drawing down loan funding to de-risk the funding of the Council’s 2024/25
capital plans in line with the 2024/25 Treasury Management and Investment
Strategy approved by Council on 27 February 2024; 
MUFG Corporate Markets Interest Rate View 05.02.24
Mar-24 Jun-24 Sep-24 Dec-24 Mar-25 Jun-25 Sep-25 Dec-25 Mar-26 Jun-26 Sep-26 Dec-26 Mar-27
BANK RATE 5.25 5.25 4.75 4.25 3.75 3.25 3.00 3.00 3.00 3.00 3.00 3.00 3.00
3 month ave earnings 5.30 5.30 4.80 4.30 3.80 3.30 3.00 3.00 3.00 3.00 3.00 3.00 3.00
6 month ave earnings 5.20 5.10 4.60 4.10 3.70 3.30 3.10 3.10 3.10 3.10 3.10 3.10 3.10
12 month ave earnings 5.00 4.90 4.40 3.90 3.60 3.20 3.10 3.10 3.10 3.10 3.10 3.20 3.20
5 yr   PWLB 4.50 4.40 4.30 4.20 4.10 4.00 3.80 3.70 3.60 3.60 3.50 3.50 3.50
10 yr PWLB 4.70 4.50 4.40 4.30 4.20 4.10 4.00 3.90 3.80 3.70 3.70 3.70 3.70
25 yr PWLB 5.20 5.10 4.90 4.80 4.60 4.40 4.30 4.20 4.20 4.10 4.10 4.10 4.10
50 yr PWLB 5.00 4.90 4.70 4.60 4.40 4.20 4.10 4.00 4.00 3.90 3.90 3.90 3.90
MUFG Corporate Markets Interest Rate View 28.05.24
Jun-24 Sep-24 Dec-24 Mar-25 Jun-25 Sep-25 Dec-25 Mar-26 Jun-26 Sep-26 Dec-26 Mar-27
BANK RATE 5.25 5.00 4.50 4.00 3.50 3.25 3.25 3.25 3.25 3.00 3.00 3.00
3 month ave earnings 5.30 5.00 4.50 4.00 3.50 3.30 3.30 3.30 3.30 3.00 3.00 3.00
6 month ave earnings 5.30 4.90 4.40 3.90 3.50 3.30 3.30 3.30 3.30 3.10 3.10 3.20
12 month ave earnings 5.10 4.80 4.30 3.80 3.50 3.40 3.40 3.40 3.40 3.20 3.30 3.40
5 yr   PWLB 4.90 4.70 4.50 4.30 4.10 4.00 3.90 3.90 3.90 3.90 3.90 3.80
10 yr PWLB 5.00 4.80 4.60 4.40 4.30 4.10 4.10 4.10 4.00 4.00 4.00 3.90
25 yr PWLB 5.30 5.20 5.00 4.80 4.70 4.50 4.50 4.40 4.40 4.40 4.30 4.30
50 yr PWLB 5.10 5.00 4.80 4.60 4.50 4.30 4.30 4.20 4.20 4.20 4.10 4.10
Page 60 of 396

Page 61

This position is prudent in the current economic climate (with PWLB rates
forecast to drop from their prevailing rates, across the next 2 financial years),
as it balances longer-term interest rate and refinancing risk with short-medium
term budgetary implications. 
At 31 March 2025, the Council was under-borrowed by £90.421 million.  This
means that the majority (81%) of the capital borrowing need, (the Capital
Financing Requirement), is fully funded with loan debt. 
Useable reserves at 31 March 2025 equated to £85.295 million, with cash
balances partly used to support the deferral of borrowing as outlined in the
TMSS for 2025/26.  Deposits at 31 March 2025 equated to £26.484 million.
Page 61 of 396

Page 62

5. The Economy and Interest Rates
UK Economy 
UK inflation has proved somewhat stubborn throughout 2024/25.  Having
started the financial year at 2.3% y/y (April), the CPI measure of inflation briefly
dipped to 1.7% y/y in September before picking up pace again in the latter
months.  The latest data shows CPI rising by 2.8% y/y (February), but there is
a strong likelihood that figure will increase to at least 3.5% by the Autumn of
2025. 
Against that backdrop, and the continued lack of progress in ending the Russian
invasion of Ukraine, as well as the potentially negative implications for global
growth as a consequence of the implementation of US tariff policies by US
President Trump in April 2025, Bank Rate reductions have been limited.  Bank
Rate currently stands at 4.50%, despite the Office for Budget Responsibility
reducing its 2025 GDP forecast for the UK economy to only 1% (previously 2%
in October). 
Moreover, borrowing has becoming increasingly expensive in 2024/25.  Gilt
yields rose significantly in the wake of the Chancellor’s Autumn Statement, and
the loosening of fiscal policy, and have remained elevated ever since, as
dampened growth expectations and the minimal budget contingency (<£10bn)
have stoked market fears that increased levels of borrowing will need to be
funded during 2025. 
The table below provides a snapshot of the conundrum facing central banks:
inflation pressures remain, labour markets are still relatively tight by historical
comparisons, and central banks are also having to react to a fundamental re-
ordering of economic and defence policies by the US administration. 
UK Eurozone US
Bank Rate 4.50% 2.5% 4.25%-4.5%
GDP 0.1%q/q Q4 
(1.1%y/y)
+0.1%q/q Q4
(0.7%y/y)
2.4% Q4
Annualised
Inflation 2.8%y/y (Feb) 2.3%y/y (Feb) 2.8%y/y (Feb)
Unemployment
Rate
4.4% (Jan) 6.2% (Jan) 4.1% (Feb) 
The Bank of England sprung no surprises in their March meeting, leaving Bank
Rate unchanged at 4.50% by a vote of 8-1, but suggesting further reductions
would be gradual.  The Bank of England was always going to continue its cut-
hold-cut-hold pattern by leaving interest rates at 4.50% but, in the opposite of
what happened at the February meeting, the vote was more hawkish than
expected. This suggested that as inflation rises later in the year, the Bank cuts
rates even slower, but the initial impact of President Trump’s tariff policies in
Page 62 of 396

Page 63

April 2025 on the financial markets underpin our view that the Bank will
eventually reduce rates to 3.50%. 
Having said that, the Bank still thinks inflation will rise from 2.8% in February to
3.75% in Q3. And while in February it said “inflation is expected to fall back
thereafter to around the 2% target”, this time it just said it would “fall back
thereafter”. That may be a sign that the Bank is getting a bit more worried about
the “persistence in domestic wages and prices, including from second-round
effects”. Accordingly, although we expect a series of rate cuts over the next
year or so, that does not contradict the Bank taking “a gradual and careful”
approach to cutting rates, but a tepid economy will probably reduce inflation
further ahead and prompt the Bank to cut at regular intervals. 
From a fiscal perspective, the increase in businesses’ national insurance and
national minimum wage costs from April 2025 is likely to prove a headwind,
although in the near-term the Government’s efforts to provide 300,000 new
homes in each year of the current Parliament is likely to ensure building industry
employees are well remunerated, as will the clamp-down on immigration and
the generally high levels of sickness amongst the British workforce.  Currently
wages continue to increase at a rate close to 6% y/y.  The MPC would prefer a
more sustainable level of c. 3.5%. 
As for equity markets, the FTSE 100 has recently fallen back to 7,700 having
hit an all-time intra-day high 8,908 as recently as 3rd March.   The £ has also
endured a topsy-turvy time, hitting a peak of $1.34 before dropping to $1.22 in
January and then reaching $1.27 in early April 2025. 
USA Economy 
Despite the markets willing the Federal Open Market Committee (Fed) to repeat
the rate cut medicine of 2024 (100 basis points in total), the Fed Chair, Jay
Powell, has suggested that the Fed Funds Rate will remain anchored at 4.25%-
4.5% until inflation is under control, and/or the economy looks like it may head
into recession as a consequence of President Trump’s tariff policies. 
Inflation is close to 3.0% and annualised growth for Q4 2024 was 2.4%.  With
unemployment just above 4.0%, and tax cuts in the pipeline, the FOMC is
unlikely to be in a hurry to cut rates, at least for now. 
EZ Economy 
The Eurozone economy has struggled throughout 2024 and is flat lining at
present, although there is the promise of substantial expenditure on German
defence/infrastructure over the coming years, which would see a fiscal
loosening.  France has struggled against a difficult political backdrop, but with
a large budget deficit it is difficult to see any turn-around in economic hopes in
the near-term. 
Page 63 of 396

Page 64

With GDP currently below 1% in the Euro-zone, the ECB is likely to continue to
cut rates, although the headline inflation rate is still above 2% (2.3% February
2025).  Currently at 2.5%, a further reduction in the Deposit Rate to at least 2%
is highly likely.  
Page 64 of 396

Page 65

6. Borrowing Rates in 2024/25
PWLB rates are based on gilt (UK Government bonds) yields through HM
Treasury determining a specified margin to add to gilt yields.  The main
influences on gilt yields are Bank Rate, inflation expectations and movements
in US treasury yields. Inflation targeting by the major central banks has been
successful over the last 30 years in lowering inflation and the real equilibrium
rate for central rates has fallen considerably due to the high level of borrowing
by consumers: this means that central banks do not need to raise rates as much
now to have a major impact on consumer spending, inflation, etc. This has
pulled down the overall level of interest rates and bond yields in financial
markets over the last 30 years.  Indeed, in recent years many bond yields up to
10 years in the Eurozone turned negative on expectations that the EU would
struggle to get growth rates and inflation up from low levels. In addition, there
has, at times, been an inversion of bond yields in the US whereby 10-year yields
have fallen below shorter-term yields. In the past, this has been a precursor of
a recession. 
However, since early 2022, yields have risen dramatically in all the major
developed economies, first as economies opened post-Covid; then because of
the inflationary impact of the war in Ukraine in respect of the supply side of
many goods.  In particular, rising cost pressures emanating from shortages of
energy and some food categories have been central to inflation rising rapidly. 
Furthermore, at present the Fed, ECB and Bank of England are all being
challenged by levels of persistent inflation that are exacerbated by tight labour
markets and high wage increases relative to what central banks believe to be
sustainable. 
Gilt yields have been volatile through 2024/25.  Indeed, the low point for the
financial year for many periods was reached in autumn 2024.  Thereafter, and
especially following the Autumn Statement, PWLB Certainty rates have
remained elevated at between c. 5% - 6% with the exception of the slightly
cheaper shorter dates. 
At the close of 31 March 2025, the 1-year PWLB Certainty rate was 4.82%
whilst the 25-year rate was 5.98% and the 50-year rate was 5.67%.   
Regarding PWLB borrowing rates, the various margins attributed to their pricing
are as follows: - 
• PWLB Standard Rate is gilt plus 100 basis points (G+100bps)
• PWLB Certainty Rate is gilt plus 80 basis points (G+80bps)
• HRA Borrowing Rate is gilt plus 40bps (G+40bps) 
There is likely to be a fall in gilt yields and PWLB rates across the whole curve
over the next one to two years as Bank Rate falls and inflation (on the
Consumer Price Index measure) moves lower. 
Page 65 of 396

Page 66

As a general rule, short-dated gilt yields will reflect expected movements in
Bank Rate, whilst medium to long-dated yields are driven primarily by the
inflation outlook. 
The Bank of England is also continuing on a process of Quantitative Tightening. 
The Bank’s original £895bn stock of gilt and corporate bonds will gradually be
sold back into the market over several years (currently c£623bn).  The impact
this policy will have on the market pricing of gilts, while issuance is still markedly
increasing, and very high in historic terms, is an unknown at the time of writing. 
HIGH/LOW/AVERAGE PWLB RATES FOR 2024/25 
3.50%
4.00%
4.50%
5.00%
5.50%
6.00%
6.50%
PWLB Rates 02.04.24 - 31.03.25
1 Year 5 Year 10 Year 25 Year 50 Year 50 year target %
1 Year 5 Year 10 Year 25 Year 50 Year
Low 4.77% 4.31% 4.52% 5.08% 4.88%
Date 26/02/2025 17/09/2024 17/09/2024 17/09/2024 17/09/2024
High 5.61% 5.34% 5.71% 6.18% 5.88%
Date 29/05/2024 13/01/2025 13/01/2025 13/01/2025 09/01/2025
Average 5.14% 4.86% 5.07% 5.56% 5.32%
Spread 0.84% 1.03% 1.19% 1.10% 1.00%
Page 66 of 396

Page 67

7. Borrowing Outturn for 2024/25
New Treasury Borrowing:- 
The following table gives details of new external treasury loans drawn during
the year:- 
Maturing Debt:- 
The following table gives details of treasury debt maturing during the year:- 
Rescheduling:- 
No rescheduling was done during the year. 
Summary of debt transactions:- 
The average interest rate payable on external debt gradually increased during
the year as a result of new external loans drawn at the prevailing PWLB rates,
averaging 3.14% for the 2024/25 financial year (opening rate of 3.09% with
closing rate of 3.21%).  The average life of debt within the loan portfolio dropped
from 29.22 years to 25.89 years. 
Lender Date
Taken
Principal
£000's
Interest
Rate
Fixed/
Variable
Maturity
Date
Term
(Yrs)
PWLB Maturity 20 Aug 2024 £  10,000 4.15% Fixed 22 Aug 2028 4.00
PWLB Maturity 20 Aug 2024 £  10,000 4.13% Fixed 22 Feb 2029 4.50
PWLB Maturity 25 Nov 2024 £  10,000 4.67% Fixed 24 May 2030 5.50
PWLB EIP 20 Dec 2024 £  10,000 4.49% Fixed 20 Dec 2034 10.00
Total £  40,000
Table 9: New Loans Taken in Financial Year 2024/25
Lender Date
Repaid
Principal
£000's
Interest
Rate
Fixed/
Variable
Date
Originally
Taken
Original
Term
(Yrs)
PWLB Annuities Various £          57 7.75%-9.50% Fixed 02 Aug 1968 to
15 May 1972 56-60 years
PWLB Maturity 28 Sep 2024 £        626 8.25% Fixed 28 Sep 1995 29.00
Salix Various £          70 0.00% Fixed Various 7-8 years
Deutsche Pfandbriefbank Various £        357 2.63% Fixed 29 Jun 2017 28.00
Deutsche Pfandbriefbank Various £        316 2.73% Fixed 15 Nov 2018 25.50
Total £     1,426
Table 10: Maturing Debt in Financial Year 2024/25
Page 67 of 396

Page 68

8. Deposit Rates in 2024/25
Investment returns decreased throughout 2024/25, reflective of the Bank of
England base rate cuts during the year. 
Money market funds and instant access bank call accounts were utilised to
manage the Council’s day to day liquidity needs. 
Money market fund / bank account rates started the year at 5.09%-5.29%,
decreasing throughout the year in line with movements in Bank of England
Base Rates, ending the year at 4.34%-4.56%. 
HIGH/LOW/AVERAGE BANK AND SONIA RATES FOR 2024/25 
Investment returns remained robust throughout 2024/25 with Bank Rate
reducing steadily through the course of the financial year (three 0.25% rate
cuts in total), and even at the end of March the yield curve was still relatively
flat, which might be considered unusual as further Bank Rate cuts were
expected in 2025/26. 
4.00
4.25
4.50
4.75
5.00
5.25
5.50
5.75
6.00
Bank Rate vs term SONIA rates % 2.4.24 - 31.03.25
Bank Rate SONIA 1 mth 3 mth 6 mth 12 mth
FINANCIAL YEAR TO QUARTER ENDED 31/03/2025
Bank Rate SONIA 1 mth 3 mth 6 mth 12 mth
High 5.25 5.20 5.21 5.20 5.17 5.08
High Date 02/04/2024 03/05/2024 27/06/2024 17/04/2024 31/05/2024 30/05/2024
Low 4.50 4.45 4.45 4.36 4.28 4.15
Low Date 06/02/2025 12/02/2025 04/03/2025 31/03/2025 31/03/2025 10/02/2025
Average 4.95 4.90 4.88 4.82 4.72 4.54
Spread 0.75 0.75 0.76 0.85 0.89 0.93
Page 68 of 396

Page 69

Bank Rate reductions of 0.25% occurred in August, November and February,
bringing the headline rate down from 5.25% to 4.50%.  Each of the Bank Rate
cuts occurred in the same month as the Bank of England publishes is
Quarterly Monetary Policy Report, therein providing a clarity over the timing of
potential future rate cuts. 
As of early April 2025, market sentiment has been heavily influenced of late
by President Trump’s wide-ranging trade tariffs policy.  Commentators
anticipate a growing risk of a US recession, whilst UK GDP is projected by the
Office for Budget Responsibility to remain tepid, perhaps achieving 1% GDP
growth in 2025/26. 
Looking back to 2024/25, returns in excess of 5% were able to be achieved
for all periods ranging from 1 month to 12 months in the spring of 2024, but by
March 2025 deposit rates were some 0.75% - 1% lower. 
That is not to say that investment choices were straight-forward.  Concerns
over rising inflation after the Autumn Statement in October led to reduced
expectations for Bank Rate to fall.  Indeed, the CPI measure of inflation is
expected to reach c. 3.75% by the autumn of 2025, which could provide for
some presentational issues for a Bank whose primary mandate is to ensure
inflation is close to 2% on a two-to-three-year timeframe.  At the end of March,
only two further rate cuts were priced into the market for 2025 (to fall to 4.00%
by December 2025).  A week later and sentiment has changed dramatically in
the wake of the equity market sell-off to the extent that markets now expect
three Bank Rate reductions between May and December 2025 (Bank Rate to
fall to 3.75% by December 2025). 
Page 69 of 396

Page 70

9. Funds on Deposit Outturn for 2024/25
Deposit Policy:- 
The Council’s policy for placing deposits is governed by Scottish Government
Investment Regulations, and the requirements of the CIPFA Prudential and
Treasury Management Codes, which have been implemented in the annual
investment strategy approved by the Council on 27 February 2024.  This policy
sets out the approach to the considerations when placing deposits, specifically
security, liquidity and then yield (in that order) and sets out the approach for
choosing counterparties based on their credit strength, and for financial
institutions is based on credit ratings provided by the three main credit rating
agencies supplemented by additional market data (such as rating outlooks,
credit default swaps, bank share prices etc.). 
The activity during the year conformed to the approved strategy, and the
Council had no liquidity difficulties.  The position at 31 March 2025 was as
follows:- 
* As at 31 March 2025 by MUFG Clients 
Deposits placed by the Council:- 
The Council maintained an average balance of £48.386 million of instant
access and fixed term deposits, earning an average rate of return of 5.03%. 
The comparable performance indicator2 is 4.82%. 
2 3 month forward uncompounded SONIA (Sterling Overnight Index Average) which reflects the
weighted average duration of the Council’s portfolio for the year 
Counterparty
Principal
Outstanding
31 Mar 2025
£000's
Security
Long/Short
Term Rating
(Colour)
Yield
UK Local
Authority
Investment*
£000's
Bank of Scotland 518                  AA-/F1+
(Orange) 4.34% 162,087        
Royal Bank of Scotland 1                      A+/F1
(Orange) 2.50% 21,221          
Handelsbanken 19                    AA/F1+
(Orange) 4.34% 129,896        
MMF - Aberdeen Liquidity Fund 10,982            AAAmmf
(Yellow) 4.53% 1,118,170    
MMF - Federated 51                    AAAmmf
(Yellow) 4.53% 704,965        
MMF - LGIM 14,913            AAAmmf
(Yellow) 4.56% 548,057        
Total Deposits 26,484           4.54% 2,684,395    
Instant Access Money Market Fund
Instant Access Money Market Fund
Table 11: Breakdown of Deposits by Counterparty at 31 March 2025
Liquidity
Instant Access Call Account
Instant Access Call Account
Instant Access Call Account
Instant Access Money Market Fund
Page 70 of 396

Page 71

10. Performance Measurement
One of the key requirements in the Code is the formal introduction of
performance measurement relating to investments, debt and capital financing
activities. 
Loans Fund Rate 
Combining the interest paid (earned) on external debt (deposits) with charges
for premiums written off and internal interest allowed into an average Loans
Fund Rate, Midlothian’s result of 2.08% for 2023/24 was the 2nd lowest Loans
Fund Rate amongst all mainland authorities in Scotland, as reported previously
to Council. 
The comparative Loans Fund Rate for 2024/25, of 2.73%, is once again
expected to be one of the lowest when benchmarked against all mainland
authorities in Scotland (note that at present, these benchmark figures are not
yet available). 
Deposit Benchmarking 
The Council participates in the Scottish Investment Benchmarking Group set
up by its Treasury Management Consultants, Link.  This service provided by
Link provides benchmarking data to authorities for reporting and monitoring
purposes, by measuring the security, liquidity and yield within an individual
authority portfolio.  Based on the Council’s funds on deposit as at 31 March
2025, the Weighted Average Rate of Return (WARoR) on deposits of 4.54%
against other authorities is shown in the graph below:- 
As can be seen from the above graph, Midlothian is performing in line with the
Link model benchmarks (red to green lines).
Population Returns against Model Returns
Actual WARoR Model WARoR Difference Lower Bound Upper Bound Performance
4.52% 4.65% -0.13% 4.50% 4.80% Inline
Midlothian Council
Midlothian Council
3.00%
3.25%
3.50%
3.75%
4.00%
4.25%
4.50%
4.75%
5.00%
5.25%
5.50%
5.75%
6.00%
4.00% 4.25% 4.50% 4.75% 5.00% 5.25% 5.50% 5.75% 6.00%
Actual WARoR
Model WARoR
Upper Return Lower Return Peer Returns Portfolios within +/- 2%
Benchmarking Group 6 Midlothian Council
Page 71 of 396

Page 72

Debt Performance 
Whilst deposit performance criteria have been well developed and universally
accepted, debt performance indicators continue to be a more problematic area
with the traditional average portfolio rate of interest acting as the main guide. 
In this respect, the relevant figures for Midlothian are incorporated in the table
in Section 3. 
Page 72 of 396

Page 73

11. Conclusion
The Council’s overall cost of borrowing continues to benefit significantly from
the approved strategy and the proactive Treasury Management activity
undertaken. 
The weighted average cost of long term borrowing has risen marginally during
the year, reflective of the borrowing undertaken at prevailing Gilt Yields during
the year.  Tenor of borrowing has been kept short on the market expectation
that the current plateau in Gilt Yields will gradually reduce over the coming 2-3
years. 
A better than average return on deposits has been achieved for the twenty first
consecutive year and Midlothian continues to perform in line with the Link model
benchmarks. 
Overall Midlothian’s Loans Fund Rate of 2.73% for the year is expected to be
one of the lowest when benchmarked against all mainland Authorities in
Scotland.
Page 73 of 396

Page 74

Page 74 of 396

Page 75

Audit Committee
Monday 16 June 2025
Item No 5.4   
Accounts Commission – Local Government Budgets 2025/26 
Report by David Gladwin, Chief Financial Officer and Section 95 Officer 
Report for Information 
1 Recommendation 
1.1 Audit Committee is recommended to:
• Consider the Audit Scotland Report; and
• Note the key messages. 
2 Purpose of Report / Executive Summary 
2.1 The purpose of this report is to provide Audit Committee with a
summary of the Local Government Budgets 2025/26 report which was
published by Audit Scotland in May 2025 and is appended to this
report. 
2.2 Five main messages come from the report covering Scottish
Government funding, rising costs and increasing demand for Councils,
requirements for Councils to find local solutions to budget gaps,
transparency of the presentation of budget information and community
engagement as part of budget processes. 
Date: 29 May 2025 
Report Contact:
David Gladwin: 0131 271 3113
David.gladwin@midlothian.gov.uk 
Page 75 of 396

Page 76

2 
3 Background 
3.1 Audit Scotland is a statutory body established in April 2000, under the
Public Finance and Accountability (Scotland) Act 2000. It provides
services to the Auditor General for Scotland and the Accounts
Commission for Scotland. 
3.2 Audit Scotland has prepared the attached report “Local Government
Budgets 2025/26” for the Auditor General for Scotland. The Auditor
General appoints auditors to Scotland’s central government and NHS
bodies; examines how public bodies spend money; helps them to
manage their finances to the highest standards; and checks whether
they achieve value for money. 
3.3  The report sets out the key messages relating to 2025/26 budget
setting in Councils and looks to challenges ahead and areas of
improvement for Councils to consider. 
Key Messages 
3.4 Scottish Government funding to Councils increased in 2025/26 but
Councils face significant recurring cost pressures from inflation,
customer demand and infrastructure investment costs. Not all cost
increases can be matched by government funding and Councils require
to take local action including savings and increasing Council Tax to
balance budgets 
3.5 Councils continue to make savings to address financial challenges and
have successfully implement recurring measures. However, more is
needed to balance budgets looking forward. 
3.6 Transparency of how budget information is presented is important both
to aid local decision making and to also support effective community
engagement. 
Report Implications 
4.1  Resource 
None. 
4.2 Digital 
None. 
4.3  Risk 
None. 
4.4 Ensuring Equalities 
None. 
4.5 Additional Report Implications (See Appendix A)
Page 76 of 396

Page 77

3
Appendices 
Appendix A – Additional Report Implications
Appendix B – Local Government Budgets 2025/26 
Page 77 of 396

Page 78

4
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Midlothian Council and its Community Planning Partners have made a
commitment to treat the following areas as key priorities under the
Single Midlothian Plan:- 
• Reducing the gap in learning outcomes
• Reducing the gap in health outcomes
• Reducing the gap in economic circumstances 
This report does not directly impact Midlothian Council’s key priorities
but a key message within the Accounts Commission report is that the
way Council’s respond to the financial challenge will inevitably impact
on how they can deliver of key priorities and outcomes. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
A.4 Delivering Best Value
The report does not directly impact on Delivering Best Value. 
A.5 Involving Communities and Other Stakeholders
No consultation was required. 
A.6 Impact on Performance and Outcomes
The decisions taken to balance the budget will have fundamental
implications for service performance and outcomes. The Council’s
Transformation Programme aims to minimise the impact on priority
services. 
Page 78 of 396

Page 79

5
A.7 Adopting a Preventative Approach
The proposals in this report do not directly impact on the adoption of a
preventative approach. 
A.8 Supporting Sustainable Development
There are no sustainability issues arising from this report. 
Page 79 of 396

Page 80

Page 80 of 396

Page 81

Briefing
Local government
budgets 2025/26
Prepared by Audit Scotland
May 2025
Page 81 of 396

Page 82

2Local government budgets 2025/26
Contents
Key facts 3
Key messages 4
Commission expectations 6
Introduction 8
1. Scottish Government funding to councils 10
2. Council budgets 14
3. Consulting with communities 28
Appendix 1. Selected 2025/26 budget
information 31
Appendix 2. Progress since 2024/25 32
Accessibility
You can find out more and read this report using assistive
technology on our website www.audit.scot/accessibility.
Page 82 of 396

Page 83

3Key facts
Key facts
Local government budgets 2025/26:
£15.2 billion funding from the Scottish Government
£18 billion councils’ approved net revenue budgets
£4.7 billion councils’ approved capital budgets
9.6 per cent average council tax increase
£647 million identified revenue budget gap
Actions to bridge the gap:
£275 million increase to council tax
£24 million increase to income (including fees and charges)
£192 million agreed savings (recurring)
£12 million agreed savings (non-recurring)
£1 million unidentified savings
£113 million use of reserves
£30 million other measures (recurring)
30
the number of councils that carried out
budget consultations to inform 2025/26 budget-
setting
31 the number of councils that carried out equality-
impact assessments as part of budget-setting
Page 83 of 396

Page 84

4
Key messages
Key messages
1 Scottish Government funding to local government in 2025/26 is
increasing by six per cent in real terms, to £15.2 billion. However,
local government continues to face recurring pressures in excess
of funding uplifts, such as inflation, annual pay deals and growing
demand for services, and most of the increase will be used to
deliver previously agreed national commitments. Alongside this,
councils are facing additional costs related to the increase in
employer’s National Insurance contribution rates, and investing in
new buildings and assets is increasingly expensive.
2 At a time of constrained public finances and growing demand,
not all cost increases can be met from central government
funding and councils need to take local action to achieve budget
balance over the short and medium term. At the time of setting
their budgets, councils identified a difference of £647 million
between anticipated expenditure and the funding and income
they receive (the ‘budget gap’). Councils are required to set
balanced budgets and have agreed a range of actions to achieve
this and close this gap. This includes all councils raising council
tax rates, by between six and 15.6 per cent, identifying savings,
drawing on reserves and increasing or introducing charges for
accessing some services.
Page 84 of 396

Page 85

Key messages 5
3 Councils continue to make savings across a broad range
of services to address financial challenges and have been
successful in identifying recurring measures that will help to
address underlying pressures. Despite this, councils are still
forecasting that more will need to be done in future years to
achieve financial sustainability given their projected increases in
both costs and level of service demand.
4 Councils’ budget-setting processes vary, partly reflecting
differences in organisational structures and local priorities, and
this makes it difficult to compare information across Scotland.
There remains an underlying issue with the transparency of how
budget information is being presented.
5 Most councils engaged communities in some way to make
decisions on their budgets for 2025/26, but there were variations
in the depth and level of this engagement. By improving the
accessibility and transparency of how they are reporting budget
information, councils can better inform and include their local
communities in making the choices required to address ongoing
financial challenges.
Page 85 of 396

Page 86

6Commission expectations
Commission expectations
We published our first briefing on council budgets last year.
Within this, we acknowledged that variation in how budgets
are presented. We also set out a range of expectations related
to the transparency of council budget papers.
The return of greater freedom in setting council tax rates, with
residents in all areas of Scotland being asked to contribute
more, means that there is greater expectation on the
performance of local services.
With financial pressures forecast to remain, and the continued
need to identify savings and transform services to address
these, it is more important than ever that communities are
actively involved in decision-making.
The decisions taken by councils when setting their budgets
impact us all. Without clear and transparent reporting,
however, it is difficult for elected members and communities
to fully engage and participate in making these decisions.
There has been good progress against most of the
expectations set out in Local government budgets 2024/25
(set out in Appendix 2). However, further improvements 
could be made in the transparency of budget gaps and
associated savings.
In future, we expect to see councils encourage more active
participation in the budget-setting process by ensuring that:
• budget papers and financial monitoring reports provided
to elected members include clear and understandable
headline figures that state the impact of specific budget
decisions on the overall financial position of the council
Page 86 of 396

Page 87

Commission expectations 7
• budgets should link back to the council’s corporate plan to
allow elected members to make spending choices better
informed by, and based upon, the council’s priorities
• fundamental information, such as the forecast budget
gap, is clearly presented as part of the consultation
process with residents
• estimated costings of how specific proposals will
contribute to managing the budget gap are made available
to residents, including the potential contribution of any
proposed increase to council tax and the anticipated
impact on levels of service delivery
• general public consultations are supplemented by targeted
consultations with groups most impacted by changes to
specific services and that consideration is given to how to
encourage participation
• the ongoing impact of budget decisions are fully
assessed, including through Equality Impact
Assessments, to enable elected members to make
informed decisions.
Page 87 of 396

Page 88

8Introduction
Introduction
Purpose and methodology
1. Audit Scotland has prepared this budget briefing on behalf of the
Accounts Commission to summarise key issues arising from our analysis
of the 2025/26 budgets recently agreed by Scotland’s 32 councils.
2. Councils are legally required to set a balanced budget for each upcoming
financial year. This means that a council’s funding and income must cover
their anticipated expenditure. Councils might identify a budget gap as they
are preparing their budgets. This is the difference between their anticipated
expenditure for the year and the funding and income they expect to receive.
Councils will identify and agree actions, including saving measures or using
reserves, to allow them to set a balanced budget.
3. This briefing brings together data from all 32 councils to provide an
indicative national picture of budgets set for 2025/26. It considers how
Scottish councils are addressing the challenges faced in achieving a
balanced budget and long-term financial sustainability. It also considers
how councils have consulted with communities on their budget priorities
including the measures agreed to achieve financial savings.
4. The wide range of approaches councils take to budget-setting and
the level of information, and the way that it is publicly reported, make it
challenging to report a definitive national position. Some of the variation
between councils is likely due to differing budgeting approaches. We
have added caveats to the exhibits where caution is required.
5. The report is part of a series of overview outputs produced for
the Accounts Commission. These reports provide an independent
overview of the financial and operational performance of Scotland’s
local government sector. In the next 12 months, we intend to publish a
spotlight report, highlighting overall and specific service performance,
and then our annual financial bulletin which assesses the financial
performance and position of Scotland’s councils in the most recently
audited financial year.
Methodology
6. Councils completed a data return and submitted these to us in March
and April 2025, shortly after agreeing their 2025/26 budgets. The data
return requested information on councils’ revenue and capital budgets;
the identified budget gaps and bridging actions; fees and charges; and
savings and their anticipated impact.
Page 88 of 396

Page 89

Introduction 9
7. As part of the data return, we asked councils to identify the
assumptions they made when calculating projected revenue budget
gaps over the short term. As expected, these assumptions varied across
the country in relation to general inflation, pay awards and the Scottish
Government finance settlement in future years.
8. When looking at trends, we convert some financial data into real
terms, adjusting it for inflation to make trend information comparable. We
have used the March 2025 deflators published by HM Treasury to adjust
financial information from past or future years into 2025/26 prices.
Page 89 of 396

Page 90

10
1.
1. Scottish Government funding to councils
1. Scottish Government
funding to councils
Initial funding to councils is higher than last year, with
revenue and capital funding both increasing in real terms,
but additional costs and inflationary pressures will remain
challenging to manage.
Scottish Government core funding to local
government is increasing in 2025/26
9. The Scottish Government publishes a draft budget every year, usually
in December, which is subject to parliamentary scrutiny and approval.
The final Scottish Budget, generally agreed in February, is accompanied
by the Local Government Finance settlement, which outlines the funding
each council will receive. The Scottish Government will provide
£15.2 billion to local government in 2025/26 (Exhibit 1).
10. The level of funding allocated to local government is expected to
change throughout the year as additional funding is made available to
councils. For example, the 2024/25 local government budget increased in
real terms to £14.7 billion by the spring Budget revision. It is therefore
likely that the 2025/26 local government budget will change.
Exhibit 1.
Scottish Budget initial government settlement 2023/24 to 2025/26
Scottish Government core funding to local government is increasing in 2025/26.
Cash terms Real terms
2023/24
£ million
2024/25
£ million
2025/26
£ million
2023/24
£ million
2024/25
£ million
2025/26
£ million
Total local government
funding 13,481 13,913 15,177 14,363 14,281 15,177
Total revenue funding 12,652 13,257 14,397 13,480 13,608 14,397
Total capital funding 829 656 780 883 673 780
Note: Real terms funding has been adjusted into 2025/26 prices using March 2025 GDP deflators.
Source: Analysis of Scottish Government Finance Circulars
The Scottish
Government adjusts
its budget during the
year. This generally
takes place during
the annual autumn
and spring Budget
revisions and
includes allocating
additional funding
to, as well as in-year
transfers between,
spending portfolios.
Page 90 of 396

Page 91

1. Scottish Government funding to councils 11
All councils are receiving an annual increase in their
initial revenue funding allocations
11. The finance settlement outlines both the revenue and capital funding
allocations that individual councils receive from the Scottish Government.
Revenue funding can be used to meet day-to-day costs of providing
services including staff costs. The Scottish Government allocated
£14.4 billion of revenue funding to local government in 2025/26, an
annual real terms increase of £789 million (six per cent) (Exhibit 2).
12. This settlement differs from the figures presented in the draft
Scottish Budget published in full in December, due to changes made
to the budget prior to receiving parliamentary approval. All councils are
receiving an increased revenue allocation in 2025/26, in both cash and
real terms.
Exhibit 2.
Scottish Budget 2025/26 local government revenue settlement in real terms
2023/24 to 2025/26
All councils are receiving an increase in their revenue allocation in 2025/26.
3,246m 3,149m 3,114m
827m 270m 272m
9,407m 10,189m 11,012m
General Revenue
Grant
Non-Domestic
rates
Specific Revenue
Grant
2023/24 2024/25 2025/26
Note: Prior years have been adjusted into 2025/26 prices using the March 2025 GDP deflators.
Source: Analysis of Scottish Government Finance Circulars
Page 91 of 396

Page 92

1. Scottish Government funding to councils 12
13. The increase in total revenue funding to councils is driven by an eight
per cent annual real terms increase in the General Revenue Grant
(GRG) to £11 billion. GRG has increased due to additional funding, but
also because the Scottish Government moved previously ring-fenced
funding into the general grant. Similarly, some elements of funding that
were previously transferred from other portfolios during the year have
now been included within initial allocations.
14. An increase in GRG is in-line with the commitments made as part
of the Verity House Agreement to reduce ring-fenced funding. The
Convention of Scottish Local Authorities (COSLA), however, contends
that the increase in GRG does not provide councils with greater
autonomy or discretion when setting their own budgets. This is because
much of the increase is to support previously announced commitments
that have been carried forward into 2025/26 and ‘baselined’ into GRG.
For example, increasing GRG to fund previously agreed pay awards.
15. In 2025/26, the increase in GRG includes baselining of funding
for non-teaching staff pay awards and teacher pension contribution
increases, as well as the following:
• £125 million of Living Wage funding
• £43 million of 2024 pay awards to teachers
• £10 million free personal and nursing care funding.
16. The 2025/26 finance settlement also outlines an additional £152 million
of revenue funding, including £144 million of additional funding to partly
compensate for the increase in employer’s National Insurance contributions.
Prior to this funding being confirmed, COSLA estimated that councils
would need to identify £240 million to meet additional costs related to
directly employed council staff (paragraphs 29–31).
Capital funding is increasing for 2025/26, but it is still
lower than in 2023/24
17. Capital funding is used to buy, maintain or improve assets such
as buildings, general infrastructure and equipment. The Scottish
Government is allocating £779.7 million of capital funding to
local government,1 a 16 per cent increase compared to last year
(Exhibit 3, page 13).
18. Again, the final settlement slightly differs from the figures presented
in the draft Scottish Budget, due primarily to around £60 million of
Specific Capital Grant moving into the General Capital Grant. Twenty-six
councils are receiving less capital funding in 2025/26 than in 2023/24,
The General
Revenue Grant
(GRG) is funding
provided by the
Scottish Government
to councils to help
them finance their
general services. Most
of this grant is typically
not ring-fenced for
specific purposes
and this provides
councils flexibility
to allocate based
on local needs and
priorities. However,
some funding received
by councils through
the GRG is directed
for national policy
initiatives. Though not
formally ring-fenced,
this funding is provided
with the expectation
that it will be spent on
specific services.
The Verity House
Agreement aims to
increase collaboration
on shared priorities
between the Scottish
Government and
councils. It outlines
a shared vision
around tackling
poverty, transitioning
to net zero and
delivering sustainable
public services.
It also includes
commitments on
agreeing a new fiscal
framework and an
accountability and
assurance framework,
aiming to reduce ring-
fenced funding.1 This includes £12.4 million of funding to Strathclyde Partnership for
Transport and £89.5 million of undistributed funding in 2025/26.
Page 92 of 396

Page 93

1. Scottish Government funding to councils 13
and three councils are receiving less funding (in both cash and real terms)
than in 2024/25. In two of these councils, East Lothian and Stirling,
reductions in capital funding have been enough to offset increases in
revenue funding resulting in a real-terms reduction in their total funding.
19. Our Local government budgets 2024/25 briefing explained how
the significant reduction in capital funding between 2023/24 and 2024/25
was largely because of the decision to move general capital to the
general revenue grant to fund prior year local government pay awards
(alongside additional funding also provided for that purpose).
Exhibit 3.
Scottish Budget 2025/26 local government capital settlement in real
terms 2023/24 to 2025/26
Capital funding is increasing in 2025/26 from the previous year but it is lower
compared to 2023/24.
Note: Funding allocation directly to Strathclyde Partnership for Transport is included within Specific
Capital Grants (2025/26: £12.4 million). Prior years have been adjusted into 2025/26 prices using the
March 2025 GDP deflators.
Source: Analysis of Scottish Government Finance Circulars
£735m £644m£549m
£148m
£136m
£124m
2023/24 2024/25 2025/26
General Capital
Grant
Specific Capital
Grant
Page 93 of 396

Page 94

142. Council budgets
2. Council budgets
Councils continue to identify savings, use reserves and review
how they deliver services to manage financial pressures.
Councils’ combined revenue budgets for 2025/26 have
increased from 2024/25
20.Councils’ revenue budgets need to cover the cost of delivering services
each year as well as certain other expenses. Councils need to set a
balanced revenue budget every year.
21.Most of councils’ revenue funding comes from the Scottish Government
with around 61 per cent coming through the General Revenue Grant. The
revenue budget available for the year also includes funding from other
sources, including council tax, other grants, non-domestic rates (NDR,
commonly referred to as business rates) and income raised through fees and
charges:
• £11 billion of funding from the Scottish Government mainly through
the GRG.
• £3 billion of funding from non-domestic rates.
• £3 billion of funding from council tax.
• £1 billion from other income and fees that councils set.
22.In 2025/26, councils reported a combined revenue budget of around
£18 billion, increasing from £16.7 billion in 2024/25 (around seven per
cent). Councils have again reported budget gaps in 2025/26. Where
councils are forecasting that their in-year spending will be greater than their
available income, we refer to this as a budget gap. The budget gap is the
difference between anticipated income (excluding income drawn from
reserves) and expenditure (reduced only for savings approved by elected
members).
23.At the time of setting their 2025/26 budgets, councils identified a
combined revenue budget gap of around £647 million. This represents a
budget gap in the range of 3.4 per cent of councils’ total combined
revenue budgets for 2025/26. Compared to 2024/25, the total budget gap
identified by councils has increased by £52 million. Paragraph 25 sets out
some of the pressures on councils which may account for this increase in
the budget gap.
24.At a council level, budget gaps ranged from £70.3 million in the City of
Edinburgh Council to £4.4 million in Eilean Siar. This represents five
per cent and three per cent of their respective total revenue budgets
(Exhibit 4, page 15 and Exhibit 5, page 16). Appendix 1 sets out further
selected information on individual council budgets for 2025/26 where
available. Page 94 of 396

Page 95

2. Council budgets 15
Exhibit 4.
Council budget gaps 2025/26
0 10 20 30 40 50 60 70 80
Eilean Siar
South Lanarkshire
East Renfrewshire
South Ayrshire
Inverclyde
Moray
Clackmannanshire
Scottish Borders
Dundee City
West Dunbartonshire
Argyll and Bute
Dumfries and Galloway
Stirling
Angus
Midlothian
North Ayrshire
East Ayrshire
East Lothian
Renfrewshire
North Lanarkshire
Aberdeen City
Orkney Islands
West Lothian
Fife
East Dunbartonshire
Perth and Kinross
Falkirk
Highland
Aberdeenshire
Shetland Islands
Glasgow City
City of Edinburgh
£ million
Councils
Note: There are differences in the way councils’ approach and present their budget and identify
budget gaps. This means that direct comparisons should be made with caution.
Source: Council data returns
Page 95 of 396

Page 96

2. Council budgets 16
Exhibit 5.
Budget gaps for 2025/26 as a percentage of their total revenue budget
0 1 2 3 4 5 6 7 8
South Lanarkshire
North Lanarkshire
South Ayrshire
East Renfrewshire
Fife
Dundee City
Glasgow City
Dumfries and Galloway
Scottish Borders
Inverclyde
Renfrewshire
Aberdeen City
Moray
North Ayrshire
Eilean Siar
East Ayrshire
Argyll and Bute
Angus
West Lothian
West Dunbartonshire
Highland
Stirling
Midlothian
City of Edinburgh
East Lothian
Aberdeenshire
Clackmannanshire
Perth and Kinross
East Dunbartonshire
Falkirk
Percentage
Councils
Note: Shetland and Orkney hold significant reserves related to oil, gas and harbour activity. They are
excluded from this chart as they are outliers due to their planned use of available reserves to balance their
budgets. Their budget gaps as a percentage of revenue budget are 20 per cent and 18 per cent respectively.
Source: Council data returns
Page 96 of 396

Page 97

2. Council budgets 17
Councils are continuing to forecast budget gaps over
the short term
25. Councils are anticipating that funding pressures will continue, citing
several key assumptions that inform budgets in the medium term. Where
the information was available:
• most councils report the pressures around annual pay settlements,
with many expecting three per cent increases to 2027/28. This,
alongside higher employer’s National Insurance contributions,
increasing overall workforce costs
• potential increases to employer pension contributions, following
recent reductions in these (paragraph 35)
• a majority of councils also reference general inflationary pressures,
including increasing costs of goods and services, making councils’
operations more expensive
• several councils are also projecting flat cash funding settlements
from the Scottish Government
• potential annual increases to council tax rates with a lack of
consistency on the projected expected increase from individual
councils.
Councils will need to carefully manage these financial pressures to
maintain services whilst still addressing rising costs.
26. Based on 31 councils, the total projected revenue budget gap for
2026/27 is £528 million. The projected revenue gap for 2027/28 is
£496 million, also across these 31 councils. If savings in 2025/26 are
not delivered, or are made through non-recurring means, then there is
potential that these gaps will widen further.
27. The largest cumulative revenue budget gap to 2027/28 is Glasgow
(£116.8 million), followed by Shetland (£106.0 million). When evaluating
the budget gap relative to the proportion of councils’ revenue budgets,
Shetland and Orkney rank as the highest (Exhibit 6, page 18).
28. While elements of these projections are either expected to be
addressed or lessen in impact, councils are currently anticipating a
cumulative revenue budget gap of £997 million over the next two years.
This means that councils will need to increase their income levels,
identify further saving measures or consider how they can continue to
transform how (and what) they deliver to close these projected revenue
budget gaps.
Page 97 of 396

Page 98

2. Council budgets 18
Exhibit 6.
Councils’ projected budget gaps to 2027/28
Councils
Budget gap
for 2026/27
£ million
Budget gap
for 2027/28 
£ million
Cumulative
gap to
2027/28 
£ million
Cumulative gap as
% of 2025/26 net
revenue budget
Shetland Islands 47.7 58.3 106.0 51%
East Dunbartonshire 40.1 43.0 83.1 22%
Orkney Islands 15.0 11.0 26.0 22%
East Lothian 21.0 15.8 36.8 10%
West Dunbartonshire 8.2 8.3 16.5 5%
Eilean Siar 6.7 3.7 10.4 8%
Highland 34.6 27.3 61.9 8%
Clackmannanshire 7.3 4.7 12.0 7%
South Ayrshire 17.5 8.2 25.8 7%
Scottish Borders 13.3 13.5 26.7 7%
Stirling 10.0 10.4 20.4 7%
Aberdeen City 29.0 40.8 40.8 6%
Aberdeenshire 11.1 13.4 24.5 3%
East Ayrshire 13.0 14.0 27.0 6%
Argyll and Bute 9.6 10.3 19.9 6%
Falkirk 20.1 9.0 29.1 6%
West Lothian 16.9 18.1 35.0 6%
Inverclyde 8.1 8.3 16.4 6%
Renfrewshire 15.6 17.9 33.0 6%
Glasgow City 72.9 43.9 116.8 5%
North Lanarkshire 32.3 25.3 57.7 5%
Dumfries and Galloway 10.7 11.9 22.6 5%
Dundee City 8.4 12.2 20.6 4%
Angus 6.0 8.6 14.6 4%
East Renfrewshire 5.0 5.0 10.0 3%
City of Edinburgh 19.9 19.3 39.2 3%
South Lanarkshire 11.7 13.8 25.5 3%
Midlothian 5.4 2.3 7.7 2%
North Ayrshire 3.6 7.4 11.0 2%
Fife 5.1 11.1 16.2 1%
Moray 1.9 1.1 3.0 1%
Total 527.8 495.7 997.3
Note: Perth and Kinross Council did not report any projected budget gaps.
Source: Council data returns
Page 98 of 396

Page 99

2. Council budgets 19
Financial pressures in 2025/26 include increased
costs related to National Insurance contributions
29. The UK Government announced in October 2024 that they would
increase the rate of employers’ National Insurance (NI) contributions,
alongside a reduction in the threshold of when employers would also
start paying the contribution.
30. All councils report facing increased costs from the changes in
NI contributions for employers and in response to this, the Scottish
Government announced £144 million in additional funding (paragraph
16). COSLA, however, estimated the additional cost could be up to
£370 million: £240 million for directly employed staff and £130 million
for indirectly employed staff (£85 million for staff working in Adult Social
Care commissioned services, and up to £46 million for staff across other
commissioned services and ALEOs).
31. Returns submitted to us by councils showed additional costs of
around £235 million within approved 2025/26 budgets, as councils mainly
adjusted budgets to recognise costs associated with direct employees.
Councils need to meet these increased costs, and manage them within
overall revenue budgets, potentially impacting the funding available for
frontline services.
Councils, however, continue to benefit from reduced
pension costs
32. LGPS employer contributions decreased (as a percentage of
employee pay) in 2024/25, with councils using the results of the 2023
triennial pension fund revaluation as an opportunity to reduce
contribution rates. From 2024/25, up until 2026/27, this allows councils to
redirect the notional savings to other project or service areas.
33. The scale of reduction to required employer contributions varies.
They are directly influenced by the funding position for each individual
employer within each fund, considering historic contributions, and can
therefore vary across councils even within the same fund.
34. Councils’ financial plans and budgets for 2025/26 incorporated the
reduction in pension contributions, allowing the reduced costs against
2023/24 rates to be redirected to other areas. Not all councils recognised
this reduction as a saving in 2025/26, as the changes were implemented
during 2024/25, but 12 councils directly referenced savings from reduced
pension contributions when setting their 2025/26 budgets.
35. Reduced pension contribution rates should only be seen as a
temporary source of funding by council, with rates increasing in 2026/27.
The level of reductions range from 13 per cent (for a two-year period)
to one per cent. Councils who reported a 13 per cent reduction in
The triennial
revaluation assesses
the funding position
of each of Scotland’s
11 Local Government
Pension Scheme
(LGPS) Funds, looking
at the investments
held, and the forecast
returns, against the
projected future
liabilities of each. The
results from all LGPS
funds in Scotland
(31 March 2023)
showed a significantly
improved funding
position, compared to
31 March 2020.
Page 99 of 396

Page 100

2. Council budgets 20
contribution rates are the 12 members of Strathclyde Pension Fund. 
They will see their contribution rates rise from 6.5 per cent in 2025/26
to 17.5 per cent in 2026/27. Further increases in future employer
contribution rates across all councils will be subject to the outcome of 
the next triennial revaluation.
Councils are taking various actions to close their
2025/26 budget gaps
36. In order to set a balanced budget, councils must not operate with
a budget gap. There are various tools available to councils to close a
budget gap, either by generating additional income or by reducing their
expenditure, and to balance their budgets (Exhibit 7).
37. Councils should use recurring measures to ensure cost savings take
effect over multiple years, for example by transforming how they deliver
services, by permanently reducing staff numbers or; taking decisions
that will increase their annual income, for example by making changes to
council tax rates (paragraph 45).
Exhibit 7.
Councils’ bridging actions to set their 2025/26 budgets
Councils are taking various actions to close their 2025/26 budget gap.
Source: Council data returns
6
0 50 100 150 200 250 300
Unidentified savings
Agreed savings – non-recurring
Increase to income
Other measures – recurring
Use of reserves
Agreed savings – recurring
Increase to council tax
£ million
113
192
12
275
30
24
0.7
Page 100 of 396

Page 101

2. Council budgets 21
38. They can also identify non-recurring measures that are one-off or
produce only temporary savings, for example delaying certain spending
or temporarily leaving vacant posts unfilled. Relying on non-recurring
measures is unsustainable and is only a temporary plug for a budget gap in
that one year. The gap will need to be met with the same level of recurring
measures such as recurring savings or increases to income in future years
and will not address a cumulative funding gap (paragraph 28).
Councils continue to make savings across a broad
range of services to address financial challenges
39. Most councils have identified service areas where they are expecting
to make savings in 2025/26. Reducing the level of unidentified savings
supports sound financial planning by minimising the need to find
additional budget reduction measures and unplanned reprioritisation of
spending throughout the year.
40. All councils provided information on the service areas where they
are planning financial savings in 2025/26. Councils are planning to deliver
around £210 million of approved savings in 2025/26. Most of these
saving measures are recurring, with only £12.2 million of non-recurring
savings planned. The City of Edinburgh Council is proposing the highest
service-level saving measures in 2025/26, totalling £28.4 million
representing around two per cent of their total 2025/26 revenue budget.
South Ayrshire Council projects the lowest level of service level saving
measures of £0.7 million, around 0.2 per cent of the council’s total
2025/26 total revenue budget.
41. Across all councils, most savings are planned within corporate services,
followed by children’s services. Councils plan to achieve £68 million of
savings within corporate services and £58 million of savings in children’s
services. Actions to tackle climate have the lowest level of saving measures
planned, with £0.4 million of savings planned in 2025/26.
42. Sixteen councils provided information on the services where they
are planning significant reductions, exceeding five per cent of their overall
service budgets. For example, Glasgow City Council is making savings of
around £8 million in its financial services through policy changes, partly in
providing relief to unoccupied non-domestic properties. Generally, councils
provided limited information on their assessment of how these saving
measures will impact on particular groups and communities. Councils
have a responsibility to assess the impact budgetary decisions may have
on groups with protected characteristics and will also have to consider the
impact on their corporate priorities (paragraphs 62 and 63).
43. Councils are introducing new and innovative measures to reduce
costs. For example, Renfrewshire Council’s new digital advisor, Millie,
provides 24/7 assistance to individuals who have routine or transactional
requests. By December 2024, this service answered over 18,000 calls,
Page 101 of 396

Page 102

2. Council budgets 22
of which 36 per cent were resolved, with no staff involvement. East
Ayrshire Council is also progressing its £40 million Early Intervention Fund
which supports projects that reduce dependency on council services.
44. Audit Scotland and appointed auditors are carrying out further work
on transformation activities across all councils as part of the 2024/25
thematic Best Value work. These reports will be published throughout
2025/26, followed by a national report that outlines consistent themes
later in 2027.
All councils chose to increase council tax rates
significantly in 2025/26 
45. Councils had full flexibility over Council Tax decisions in 2025/26. All
councils increased their council tax levels, ranging from a six per cent
increase in South Lanarkshire Council to a 15.6 per cent rise in Falkirk
Council (Exhibit 8, page 23). Exhibit 8 also demonstrates the variation
in the ‘baseline’ of council tax levels for councils. For example, North
Ayrshire council agreed a seven per cent rise in council tax taking their
band D amount to £1,553.77, while North Lanarkshire agreed a higher
increase of ten per cent, with the new band D rating of £1,452.86.
Across councils, band D rates vary by 20 per cent between the highest
and lowest.
46. Council tax only represents a small proportion of a council’s overall
revenue budget, making up around 19 per cent of total council income
across Scotland, with the exact proportion varying across council areas.
On this basis, for example, a ten per cent increase to council tax rates
will not represent an overall ten per cent increase in council budgets; but
only increase available funding by 1.9 per cent. This is often referred to as
the council tax gearing effect.
47. Council tax increases can also disproportionately impact lower income
households, although the Council Tax Reduction Scheme is in place
to support a range of claimants. Analysis shows that councils with the
highest deprivation (Dundee, Glasgow City, Inverclyde, North Ayrshire)
were among those with the lowest council tax increase ranging from
seven per cent to 8.5 per cent (West Dunbartonshire increased their
council tax by 11.5 per cent). With the exception of North Lanarkshire
Council (ten per cent increase), council areas with the highest local
authority housing stock were also among those councils with the lowest
council tax increases (ranging from six per cent to 8.2 per cent).
48. In total, councils expect to receive £284.3 million from the increase
to council tax in 2025/262. The amount of income that individual councils
expect to receive from the increase in council tax is influenced by the
scale of the increase, the size of the council and the nature of the local
housing stock. Expected increases in income range from £1 million in
Comhairle nan Eilean Siar to £31 million in the City of Edinburgh Council.
2 £275 million will be used to bridge the funding gap and the remaining
is additional income. Page 102 of 396

Page 103

2. Council budgets 23
Exhibit 8.
All councils increased their council tax in 2025/26
Councils increased council tax rates significantly in 2025/26.
Councils
Council Tax
increase in
2025/26
%
Council
Tax Band D 
2025/26
£
Band D
Annual
Increase in
2025/26
£
Additional income
from council tax
increase in
2025/26 
(£000)
Aberdeen City 9.85 1,636.3 146.7 13,790
Aberdeenshire 10 1,532.8 139.3 16,922
Angus 11 1,461.5 144.8 6,999
Argyll and Bute 9.9 1,625.6 146.4 6,275
City of Edinburgh 8 1,563.5 115.8 30,997
Clackmannanshire 13 1,594.4 183.4 3,321
Dumfries and Galloway 9 1,454.0 120.1 7,685
Dundee 8 1,605.3 118.9 6,311
East Ayrshire 8 1,606.4 119.0 6,388
East Dunbartonshire 13 1,599.0 183.3 9,440
East Lothian 10 1,579.2 143.6 9,456
East Renfrewshire 8 1,528.4 113.2 5,446
Eilean Siar 8 1,387.6 96.8 1,033
Falkirk 15.6 1,576.8 213.0 12,247
Fife 8.2 1,498.8 113.6 15,908
Glasgow 7.5 1,611.4 112.0 20,250
Highland 7 1,527.1 99.9 10,487
Inverclyde 8.5 1,551.3 121.5 2,975
Midlothian 10 1,666.2 151.5 6,600
Moray 10 1,573.8 143.1 5,516
North Ayrshire 7 1,553.8 101.7 5,008
North Lanarkshire 10 1,452.9 132.1 15,300
Orkney 15 1,574.6 205.4 1,446
Perth and Kinross 9.5 1,537.0 133.3 10,480
Renfrewshire 9.5 1,572.6 136.4 10,606
Scottish Borders 10 1,491.7 135.6 7,654
Shetland Islands 10 1,386.7 126.1 1,147
South Ayrshire 8 1,569.4 116.3 5,921
South Lanarkshire 6 1,378.9 78.1 9,480
Stirling 8.8 1,611.9 130.4 5,329
West Dunbartonshire 11.5 1,559.9 160.9 4,685
West Lothian 8.95 1,515.5 124.5 9,191
Note: Council tax figures have been rounded to one decimal place.
Source: Council data returns and Scottish Government Council Tax DocumentsPage 103 of 396

Page 104

2. Council budgets 24
49. Increasing council tax allows councils to address some immediate
financial pressures, but wider sustainability pressures remain. Some
councils reported that council tax rate increases would have been higher
had they not identified savings in 2025/26.
Councils continue to raise income by charging for
certain local services
50. Councils also generate income from the fees and charges they set
for using certain services. For example, councils may charge households
for the collection of garden waste, although must collect food waste free
of charge. Twenty-four councils provided information on their 2024/25
income from fees and charges. Those councils generated £966 million
from fees and charges in 2024/25, representing around five per cent of
their 2025/26 revenue budgets. Fourteen councils received more income
from fees and charges in 2024/25 compared to initial projections.
51. In total, councils anticipate receiving £1.1 billion from fees and charges
in 2025/26. This represents around six per cent of the combined 2025/26
approved revenue budgets for councils. Glasgow City Council expects
to raise the most from fees and charges in 2025/26, with around
£210.6 million projected to be raised, around ten per cent of their
approved 2025/26 revenue budget.
52. Twenty-five councils provided information on the areas where they
plan to significantly increase fees and charges in 2025/26. For example:
• Income from Glasgow City Council’s Neighbourhood, Regeneration
and Sustainability services is projected to increase by three per cent
to £111 million, driven by the fees and charges in place for 2025/26.
• Midlothian Council are increasing the fees and charges in their
leisure services on average by eight per cent. The council will
now raise £5.9 million in total from fees and charges within leisure
services.
• Falkirk Council is increasing fees and charges within leisure charges
by five per cent for 2025/26. This is projected to contribute to a
combined income of £5.6 million from the fees and charges in
place within leisure services.
53. Thirteen councils are introducing new charges for services in
2025/26. For example:
• North Lanarkshire Council will start charging to collect garden
waste. The council expects this to generate £1.5 million in
additional income.
• South Lanarkshire Council forecasts generating £1.4 million from
issuing garden waste permits.
Page 104 of 396

Page 105

2. Council budgets 25
• Highland Council is introducing charges for tourist visitor experiences.
The councils expect this to raise £0.2 million in additional income.
Councils are also continuing to use reserves to
balance their budgets
54. As set out in the Local government in Scotland: Financial bulletin
2023/24, councils’ continuous use of reserves to balance budget pressures
is not sustainable. Using reserves in one year means future years’ services
are at greater risk if they are directly used to support expenditure but are
not invested to address underlying issues and transform service delivery.
All councils have a reserves policy in place which sets out a minimum
level of uncommitted reserves held. While it is for each council to set their
own reserves policies, and the minimum level of uncommitted reserves
they hold varies, two per cent of their net budgeted revenue expenditure
is commonly regarded as a suitable benchmark.
55. At the end of 2024/25, 25 councils are estimating that they will be
holding £1.8 billion in their General Fund, a usable reserve, with £1.3
billion of this committed. An estimated £0.14 billion has been identified
by councils as formal contingency funding, with a further £0.4 billion of
uncommitted reserves also available for that purpose if required. Combined,
this represents a potential contingency of 2.9 per cent of net revenue
expenditure. Councils approved the use of £0.19 billion of reserves in
2025/26 during budget-setting as a means of balancing budgets.
Borrowing continues to be the primary funding
source for capital projects
56. Councils’ capital budgets are used for key capital projects such as
constructing or upgrading public buildings, such as schools or libraries, or
infrastructure such as roads. Capital projects across the public sector are
now costing more, with the cost of delivering projects estimated to have
been increasing at a greater rate than general inflation for a sustained
period. The total capital budget for all councils in 2025/26 is £4.74 billion.
This is an increase from £4.23 billion in 2024/25 across Scotland,
however eleven councils are reducing their capital budgets.
57. Borrowing is the main source for funding capital projects, and councils
are intending to borrow £3.13 billion in 2025/26, an increase from
2024/25 (£2.67 billion). Exhibit 9 (page 26) shows a breakdown of the
sources of capital finance for 2025/26 and compares them to 2024/25.
Councils are increasing the amount they intend to
spend on building and maintaining social housing
58. Twenty-six councils own and maintain council housing, and all these
councils provided information on how much of their capital budget is
allocated to their Housing Revenue Account (HRA). Councils are
committing a combined £1.5 billion from their capital budgets to the
The Housing
Revenue Account
(HRA) is a ring-fenced
account relating to
local authority housing.
The HRA is intended
to record expenditure
and income on running
a council’s own
housing stock and
closely related services
or facilities, which
are provided primarily
for the benefit of the
council’s own tenants.
The main sources
of income are from
tenants in the form
of rents and service
charges.
Page 105 of 396

Page 106

2. Council budgets 26
HRA in 2025/26, an increase of £186 million from the previous year. All
councils are planning expenditure on new builds in 2025/26:
• Councils expect to spend £656 million from the HRA on new
builds in 2025/26, an increase of £81 million from 2024/25. This
represents the largest area of expenditure within the HRA. East
Renfrewshire Council had the largest expenditure on new builds
in 2024/25, although their 2025/26 forecast expenditure will be
lower than all other councils. The council accelerated its new build
programme during 2024/25, which involved utilising the grant
support available for both 2024/25 and 2025/26. As a consequence,
the council’s new build plan for 2025/26 was reduced. However,
this will be reviewed in light of revised grants available.
Exhibit 9.
Source of capital budgets for 2024/25 and 2025/26
Borrowing continues to be the key funding source for capital projects.
Source: Council data returns
0 50 100 150 200 250 300 350
Borrowing
Government General Capital Grants
Government Specific Capital Grants
Internal revenue funding
Capital receipts
Developer contributions
Other
£ million
2024/25 2025/26
Page 106 of 396

Page 107

2. Council budgets 27
• Refurbishment costs are the second largest area of expenditure
within the HRA, increasing by £142 million from 2024/25 to
2025/26. Councils expect to spend £521 million on refurbishing
housing stock in 2025/26 compared to £379 million in 2024/25.
• Sixteen councils are planning programmes of maintenance work in
2025/26. They are expecting to utilise £289 million of funding for
maintenance, an increase of £78 million from 2024/25.
Social care revenue budgets make up a high
proportion of total revenue budgets for 2025/26
59. Of the £18 billion revenue budget in 2025/26, councils reported
£4 billion related specifically to social care services. This equates to
almost 23 per cent of councils’ total revenue budget. Across councils,
the social care budget ranges between 18 and 30 per cent of councils’
total revenue budget for 2025/26. Most councils provide social care
services through separate integrated joint boards (IJBs), with the
exception of Highland who operate a different model. At the time of
collecting the data, 21 IJBs had agreed their budgets with the remaining
ten to be agreed.
60. The financial pressures and risks experienced by IJBs include reliance
on non-recurring sources of income, such as reserves and one-off
savings, and reserve levels falling below individually agreed minimum
reserve policy levels. These have a strong impact on council budgets and
collaborative working and planning is needed across IJB partners in the
budget-setting process.
61. The Accounts Commission IJB Finance bulletin 2023/24 set out that
the agreement of savings plans and NHS partner funding were the most
common reasons for balanced budgets not being agreed at the start
of the financial year. This misalignment in budget processes, however,
presents a challenge as councils look to identify savings and transform
how they deliver services, given the significant proportion of their
budgets dedicated to providing social care services.
Page 107 of 396

Page 108

283. Consulting with communities
3. Consulting with
communities
As councils continue to make difficult decisions, it is more
important than ever that they involve communities in the
decisions that impact their local services.
Most councils carried out an assessment to
understand the impact budget decisions will have on
different groups
62. Public bodies use Equality Impact Assessments (EIA) to understand
how policies or budgetary decisions affect groups with a protected
characteristic. These assessments identify ways to advance equality
while highlighting potential discrimination. Public bodies must complete
an EIA when introducing new policies or making strategic decisions that
could affect different groups.
63. Councils must consider the impact their budget choices will have
on different groups and communities, especially those with protected
characteristics under the Equality Act 2010. This is even more important
when councils face difficult choices about their budget allocations at
a time of financial pressure. For example, an EIA should highlight the
consequences of a council closing a community centre, particularly for
potential disabled or elderly residents who rely on it for essential local
services.
64. Thirty-one councils completed an EIA as part of their 2025/26 budget
process. Shetland Islands Council carried out an informal assessment
which assessed an EIA as not necessary, as there had been no major
changes to existing policies or practices and limited impact on services
contained within their budget proposals. With financial pressures forecast
to continue (paragraphs 25 and 26) it is increasingly important that
councils continue to assess how the financial decisions they are taking
impact their local populations, including vulnerable or marginalised
communities.
Councils must consult with groups in addressing
financial challenges
65. A March 2025 blog, outlines the Accounts Commission’s
expectation on councils engaging with communities in responding to the
challenging financial environment. Councils should engage with residents
Page 108 of 396

Page 109

3. Consulting with communities 29
to increase their understanding of the challenging financial environment,
the options available to manage these challenges and how council tax
rises can support local services. For example, residents’ expectations on
the quality and provision of local service may grow and councils need to
be able to demonstrate how it is using funds to maintain services and
improve performance.
Most councils consulted with residents on their
2025/26 budgets
66. Thirty councils provided evidence to us of how they engaged with
residents, while identifying saving measures and wider proposals within
their 2025/26 budgets. However, the approaches taken varied.
67. There was variance in the form and level in how councils engaged
with their communities while setting their 2025/26 budgets:
• Some councils held focus groups with residents to discuss budget
proposals whereas others directly consulted with groups that will
be impacted by service-saving measures.
• There was a mixed approach in how councils monitored the
response rate to any consultation exercise. Most councils recorded
consultation responses based on the population of the local
authority area, whereas others based on it on a street survey
response rate.
• Some councils used innovative ways to consult with stakeholders.
For example, Stirling Council ran a dedicated survey for young
people on the impact that proposed reductions to library services
would have on their learning and education. Shetland Islands
Council created animations which were shown in the local cinema
to inform the public on the council’s finances.
• Comhairle nan Eilean Siar’s consultation results did not influence
this year’s budget-setting decision as the measures taken to
achieve the savings required did not impact significantly on service
delivery. They will however feed into the 2026/27 budget-setting
process.
68. Councils provided examples of how their engagement activities
influenced budgetary decisions:
• East Ayrshire Council agreed to various initiatives which were
all raised during the consultation process. This included services
around free school meals, road improvement projects and the
Community Safety Fund.
Page 109 of 396

Page 110

3. Consulting with communities 30
Work remains to make councils’ budgets accessible,
transparent and more easily understood
69. As highlighted in last year’s report, budget-setting processes vary
across councils, partly reflecting differences in organisational structures
and local priorities. By issuing a standardised data return we have looked
to make information as comparable as possible. However, it continues to
be challenging to compare information across the sector.
70. Within individual councils, the way in which budget papers are
presented could also be improved. A lack of transparency in the
presentation of financial and budget information is a recurring theme
across our programme of Best Value audits of individual councils, and
within annual audit reports produced by our appointed auditors.
71. This means that elected members and communities cannot easily
determine the impact of budget decisions nor the overall financial
position of the council, highlighting a need to improve accessibility and
transparency. More transparent reporting of agreed budgets, the budget
gaps they are facing and how they intend to make use of reserves
(including previously agreed actions), councils can inform and better
include their local communities in making the choices still needed to
address ongoing financial challenges.
72. Appendix 2 sets out, at a high level, how councils have progressed
against the expectations related to these issues that we set out in our
Local government budgets 2024/25 briefing published in May 2024.
The Accounts Commission’s forthcoming work will
assess how key council services are performing
73. The Accounts Commission produces a series of overview reports
which provide an independent assessment of the financial and
operational performance of Scotland’s local government sector. This
report follows the Local government in Scotland: Financial bulletin
2023/24, published in January 2025.
74. For the next report in this series, the Accounts Commission will
publish a service spotlight. This new report, due to be published in
October 2025, will provide an overview of council performance as set out
by the Local Government Benchmarking Framework (LGBF) and other
key metrics. For 2025, the spotlight will have a particular focus on culture
and leisure services that councils provide.
Page 110 of 396

Page 111

31Appendix 1. Selected 2025/26 budget information
Appendix 1. Selected 2025/26
budget information
All councils’ 2025/26 revenue budget, budget gaps, approved
savings and other bridging to close budget gap. 
Councils
Revenue budget
2025/26
£ million
Budget gap
2025/26
£ million
Approved
savings 2025/26
£ million
Other bridging
actions 2025/26
£ million
Aberdeen City 665  21.2 4.0  17.1
Aberdeenshire  802  38.5 15.8  22.7
Angus  372  13.6 2.1  11.5
Argyll and Bute  327  11.5 3.0  8.5
City of Edinburgh  1,496  70.3 28.4  41.9
Clackmannanshire  171  10.2 3.8  6.4
Dumfries and Galloway  482  12.8 3.5  9.3
Dundee City  496  11.0 4.9  6.1
East Ayrshire  439  15.1 8.6  6.5
East Dunbartonshire  379  24.0 3.6  20.4
East Lothian  372  17.7 2.3  15.3
East Renfrewshire  350  7.1 1.2  5.8
Eilean Siar  135  4.4 1.4  3.0
Falkirk  488  33.8 10.0  23.8
Fife  1,148  15.6 7.1  8.5
Glasgow City  2,127  49.2 26.2  23.0
Highland  818  34.2 6.6  27.6
Inverclyde  272  7.6 3.1 4.5
Midlothian  321  14.1 2.0  12.1
Moray  294  9.4 7.9 1.5
North Ayrshire  459  14.9 3.6 11.3
North Lanarkshire  1,103  20.9 0.0 20.9
Orkney Islands  119  21.2 0.7  20.5
Perth and Kinross  503  31.1 7.6  23.5
Renfrewshire  589  18.1 6.4  11.7
Scottish Borders  400  10.8 1.9  8.9
Shetland Islands  207  42.2 8.3  33.9
South Ayrshire  377  7.2 0.7  6.5
South Lanarkshire  1,019  5.3 4.7  0.5
Stirling  310  13.0 7.7  5.3
West Dunbartonshire  311  11.4 5.2  6.2
West Lothian  603  22.1 11.9 10.1
Note: How councils present their budgets, and budget gaps, can vary and is often influenced by
specific local arrangements. The information is taken from council budget documents, as supplied to
us by councils. Other bridging actions are set out as part of Exhibit 7 and include increase to income,
increase to council tax and use of reserves. Figures may not exactly sum due to rounding.
Page 111 of 396

Page 112

32Appendix 2. Progress since 2024/25
Appendix 2. Progress since
2024/25
Progress against the expectations in Local Government
Budget Briefing 2024/25.
Councils should: Progress/ status
The Commission expects councils to
present some fundamental information
within publicly available budget papers.
Information we expect to see set out clearly
includes:
• The annual revenue budget, comprising
funding and income, prior to savings and
other ‘bridging’ actions.
• The associated budget gap, prior to
‘bridging’ actions such as savings and
use of reserves.
• The savings plan, clearly setting out
the split between recurring and non-
recurring actions.
• Projected revenue budget gaps, both
annual and cumulative.
• The assumptions used in calculating
projected budget gaps.
Substantial progress
We reviewed around a third of 2025/26 budget
papers to assess progress, and found that ten
of the 11 reviewed provided links or copies of
the required budget documents. 
Of the ten councils providing information
seven met all five of the expectations, with
three councils meeting three or four. The main
area not documented was the split between
recurring and non-recurring savings.
The information from two councils in relation to
one or more of the following areas, could have
been demonstrably clearer:
• The annual revenue budget, comprising
funding and income, prior to savings and
other ‘bridging’ actions.
• The associated budget gap, prior to ‘bridging’
actions such as savings and use of reserves.
• Projected revenue budget gaps, both annual
and cumulative.
Page 112 of 396

Page 113

Briefing
Local government
budgets 2025/26
Audit Scotland 4th Floor 102 West Port Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot
ISBN 978 1 915839 70 1
Page 113 of 396

Page 114

Page 114 of 396

Page 115

Audit Committee
Monday 16 June 2025
Item No 5.5 
Internal Audit Work to May 2025 
Report by Chief Internal Auditor 
Report for Decision 
1 Recommendations 
The Audit Committee is asked to:
a) Consider the Executive Summary of the final Internal Audit assurance report issued
associated with the delivery of the approved Internal Audit Annual Plan 2024/25;
b) Note the Internal Audit Consultancy and Other Work carried out in accordance with the
approved Internal audit Charter; and
c) Acknowledge the assurance provided on internal controls and governance arrangements
in place for the areas covered by this Internal Audit work. 
2 Purpose of Report/Executive Summary 
The purpose of this report is to provide members of the Audit Committee with details of the
recent work carried out by Internal Audit and the findings and recommended audit actions
agreed by Management to improve internal controls and governance arrangements. 
The Internal Audit Annual Plan 2024/25 was approved by the Audit Committee on 18 March
2024. Internal Audit has carried out work associated with the delivery of the plan to meet its
objective of providing an opinion on the efficacy of the Council’s risk management, internal
control and governance. 
An Executive Summary of the final Internal Audit assurance report issued, including audit
objective, findings, good practice and recommendations (where appropriate), and the Chief
Internal Auditor’s independent and objective opinion on the adequacy of the control
environment and governance arrangements within each audit area is shown in Appendix 1. 
The Internal Audit function conforms to the professional standards as set out in Public Sector
Internal Audit Standards (PSIAS) (2017) including the production of this report to
communicate the results of the reviews. 
Date 2 June 2025 
Report Contact:
Duncan Stainbank
duncan.stainbank@midlothian.gov.uk
Page 115 of 396

Page 116

2
3 Progress Report 
3.1 The Internal Audit Annual Plan 2024/25 was approved by the Audit Committee on 18 March
2024. Internal Audit has completed the following work in the period from 1 February 2025 to
31 May 2025 associated with the delivery of the plan to meet its objective of providing an
opinion on the efficacy of the Council’s risk management, internal control and governance. 
3.2 The Internal Audit function conforms to the professional standards as set out in Public Sector
Internal Audit Standards (PSIAS) (2017), including the production of this report to
communicate the results. 
3.3 Internal Audit issued final assurance reports on the following subjects:
• SEEMIS;
• Education Construction Governance;
• IT Asset Management; and
• Revenue Financial Budget Monitoring. 
3.4 An Executive Summary of the final Internal Audit assurance report issued including audit
objective conclusions, key findings, recommendations, areas of good practice, the Chief
Internal Auditor’s independent and objective opinion on the adequacy of the control
environment and governance arrangements within each audit area is shown in Appendix 1. 
3.5 The definitions for Internal Audit assurance categories are as follows: 
Level Definition
Substantial
Assurance
A sound system of governance, risk management and control exists, with internal controls
operating effectively and being consistently applied to support the achievement of objectives in
the area audited. 
Reasonable
Assurance
There is a generally sound system of governance, risk management and control in place. Some
issues, non-compliance or scope for improvement were identified which may put at risk the
achievement of objectives in the area audited. 
Limited
Assurance
Significant gaps, weaknesses or non-compliance were identified. Improvement is required to the
system of governance, risk management and control to effectively manage risks to the
achievement of objectives in the area audited. 
No Assurance Immediate action is required to address fundamental gaps, weaknesses or non-compliance
identified. The system of governance, risk management and control is inadequate to effectively
manage risks to the achievement of objectives in the area audited. 
Internal Audit Consultancy and Other Work 
3.6 Internal Audit staff have been involved in the following for the Council to meet its aims and
objectives, and its roles and responsibilities in accordance with the approved Internal Audit
Charter and Strategy:
a) In its critical friend role provided an independent view and challenge at various forums
including: Capital Plan and Asset Management Board, Chief Officers Risk & Resilience
Group, and the Integrity Group.
b) Learning and development during the research stage of new audit areas for all Internal
Audit team members and through joining audit forums (Computer Audit Sub-group) and
meetings; and
c) Monitored publication of Audit Scotland reports. 
Page 116 of 396

Page 117

3 
Recommendations 
3.7 Recommendations in reports are suggested changes to existing procedures or processes to
improve the controls or to introduce controls where none exist. The grading of each
recommendation reflects the risk assessment of non-implementation, being the product of the
likelihood of the risk materialising and its impact: 
High Recommendations relating to factors fundamental to the success of the control objectives of the
system. The weaknesses may give rise to significant financial loss/misstatement or failure of
business processes. 
Medium Recommendations which will improve the efficiency and effectiveness of the existing controls. 
Low Recommendations concerning minor issues that are not critical, but which may prevent attainment
of best practice and/or operational efficiency. 
Outwith the report, Internal Audit informs operational managers about other matters as part of continuous
improvement. 
3.8 The table below summarises the number of Internal Audit recommendations made during
2024/25:
Recs Rating 2024/25 Number of Recs
High 0
Medium 12
Low 21
Not Graded 0
Sub-total reported this period 33
Previously reported 22
Total 55 
Recommendations agreed with action plan 55
Not agreed; risk accepted 0
Total 55 
4 Report Implications (Resource, Digital, Risk and Equalities) 
4.1 Resource 
Resource implications of implementing Internal Audit recommendations are considered as
part of the audit process to ensure these are reasonable and proportionate to the risks. 
4.2 Digital 
There are no digital implications arising from this report. 
Page 117 of 396

Page 118

4
4.3 Risk 
The PSIAS require Internal Audit to evaluate the effectiveness of the Council’s Risk
Management arrangements and contribute to improvements in the process. At the start of
each audit engagement, to capture potential areas of risk and uncertainty more fully, key
stakeholders have been consulted and risk registers have been considered. During each
audit engagement the management of risk has been tested. 
It is anticipated that improvements in the management and mitigation of risks will arise as a
direct result of Management implementing the Internal Audit recommendations made. If audit
recommendations are not implemented, there is a greater risk of financial loss and/or
reduced operational efficiency and effectiveness, and Management may not be able to
demonstrate improvement in internal control and governance arrangements, and effective
management of risks. 
4.4 Ensuring Equalities 
This report does not relate to a new or revised policy, service or budget change, which
affects people (the public or staff), so an Integrated Impact Assessment (IIA) is not an
applicable consideration. 
The Internal Audit work is carried out in accordance with the appropriate legislation and
professional standards. The latter includes compliance by those within the Internal Audit
function with the Code of Ethics set out in the PSIAS which is appropriate for the profession
of Internal Audit founded as it is on trust placed in its independent and objective assurance
about risk management, internal control and governance. 
4.5 Additional Report Implications (See Appendix A) 
Page 118 of 396

Page 119

5
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Although this report does not relate directly to the key priorities within the Single Midlothian
Plan to which Midlothian Council and its Community Planning Partners have made a
commitment (Reducing the gap in economic circumstances; Reducing the gap in learning
outcomes; Reducing the gap in health outcomes; and Reducing the impact of climate
change), good governance is important to enable Midlothian Council to deliver its key
priorities in support of achieving the Council’s objectives. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working  
Hub and Spoke  
Modern  
Sustainable  
Transformational  
Preventative  
Asset-based  
Continuous Improvement  
One size fits one 
None of the above 
Midlothian Council is committed to creating a great place to grow supported by the 9 drivers
for change. Implementing the 9 drivers for change in practice is applicable to the Council’s
Internal Audit service provision to assist the Council in achieving its objectives. 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you  
Preventative and Sustainable  
Efficient and Modern  
Innovative and Ambitious 
A.4 Delivering Best Value 
The definition of Internal Auditing within the Public Sector Internal Audit Standards (PSIAS) is
“Internal auditing is an independent, objective assurance and consulting activity designed to
add value and improve an organisation’s operations. It helps an organisation accomplish its
objectives by bringing a systematic, disciplined approach to evaluate and improve the
effectiveness of risk management, control and governance processes.” 
Implementation by Management of the actions associated with Internal Audit
recommendations, that are designed to improve internal control and governance
arrangements and management of risks, underpins the Council’s own continuous
improvement arrangements to enhance its effectiveness, thus supporting the delivery of the
Council’s best value duties.
Page 119 of 396

Page 120

6 
A.5 Involving Communities and Other Stakeholders 
The Chief Internal Auditor is accountable to the Audit Committee which, in fulfilling its
governance role, acts as a bridge between the Council and other stakeholders. 
This report has been presented to Senior Management relevant to the areas audited and
have agreed the final Internal Audit assurance reports as set out in the relevant Executive
Summary within Appendix 1. 
A.6 Impact on Performance and Outcomes 
The Findings and Recommendations from Internal Audit work during the year are designed to
assist the Council in improving its performance and outcomes. 
A.7 Adopting a Preventative Approach 
Internal Audit assurance work includes assessments on when a preventative approach can
be adopted. 
A.8 Supporting Sustainable Development 
This report does not relate directly to supporting sustainable development. Good governance
is important to enable Midlothian Council to achieve its objectives. 
Page 120 of 396

Page 121

Appendix 1 Executive Summary: SEEMiS 
Conclusion: Reasonable Assurance
In relation to the management of the SEEMiS system there is a generally sound system of internal control in place including an SLA and
members agreement implemented in 2015; and appropriate processes to review and manage staff and pupil records on the system.  However,
a number of SEEMiS userIDs for employees who no longer work for the Councill had access to SEEMiS and some users who are not
employed by the Council, or are temporary staff, require to be reviewed to ensure their access to the system remains appropriate.  Some user
profiles or SEEMiS accounts for school employees may no longer be required.  A number of Education employees who have access to
SEEMiS have not completed the Council’s mandatory courses. Further clarification is required on the business continuity arrangements for
SEEMiS, guidance is required on the retention of data within the system and an audit trail of user access changes at a school level needs to
be implemented. 
Background
Strathclyde Educational Establishments Management Information System (SEEMiS) is used by all Scottish Councils to support electronic
education administration within Council headquarters and schools. SEEMiS is a Limited Liability Partnership (LLP) made up of all Scottish Local
Authorities, including Midlothian Council, and provides the education management information needs for all Midlothian schools as well as a wide
range of central, administrative and quality improvement functions.  It is used for the maintenance of personal and academic (including SQA)
records for pupils; personal information and work records for staff; and attendance records for pupils and staff.  The system is modular in nature
with the Click & Go module being the primary one.  There is also functionality which records and supports business processes relating to free
school meals, attainment, Education Maintenance Allowances and Clothing Grants.  The responsibility for maintaining the system is split
between the Council and SEEMiS LLP.  The Council is responsible for day-to-day user administration, data input and user access control
whereas SEEMiS LLP is responsible for system security, system developments, issue resolution, backup and performance monitoring.  Within
the Council, the Business Applications Team has oversight of SEEMiS and is responsible for implementing new functionality. Schools are
responsible for managing access within their respective schools. The Children and Young People Partnership (CYPP) Business Support team
assist schools with their statutory returns and liaise with the Business Applications team when required. 
In December 2024, a business case was approved by the Business Transformation Steering Group (BTSG) to implement the Parent’s Portal
module within SEEMiS with a one-off cost of £42,250.   This will improve the way in which schools engage with parents and reduce the amount
of time that staff in schools spend on routine and repetitive tasks that are inefficient and labour intensive.   The delivery of the project will be
phased with an initial roll out to a small number of schools during February and March 2025 with the remaining schools onboarded during April to
June 2025.  Management advised that a Data Protection Impact Assessment (DPIA) will be completed as part of the deliverables for the Parent
Portal project. 
Page 121 of 396

Page 122

Summary of findings & recommendations
The following key findings and recommendations are highlighted which have all been agreed by Management: 
A recommendation has been raised in the Business Continuity audit to ensure that appropriate business continuity plans are in place, reviewed
and updated within services. 
Recommendation Summary
• A number of employees who no longer work for the Council still had access to SEEMiS and there were some users who did not work for the
Council (eg careers advisors) or temporary staff (eg supply teachers) that require review to ensure access is still appropriate.  In addition,
user profiles or SEEMiS accounts for school employees not being used should be disabled.  Leavers identified have been reviewed, access
and user profiles will be reviewed, and schools will be reminded to enter leaving dates for employees if they leave the school by June 2025. 
• There are a number of Education employees who have not completed the Council’s mandatory courses, including GDPR and Introduction to
Information Security.  Management will follow this up with the individuals who have not completed the mandatory courses by 31 March 2025.
• Signed copies of variation agreements needed to be obtained, further clarification was also required on the business continuity arrangements
for SEEMiS and guidance is required on the retention of data within the system. Management has clarified this with SEEMiS and have
obtained signed copies of the variation agreements - Complete. Guidance is still required on the retention of data within the system which will
be clarified by 30 June 2025. 
• An audit trail of requests to update user access is not maintained by schools as it is actioned on verbal instruction from senior management.    
A documented approval process to ensure there is an audit trail of user access changes at a school level will be implemented by 30 June
2025.   
Recommendations Grade  High Medium Low Total
Current Report - 2 3 5
Prior Report (N/A) - - - -
Materiality 
SEEMiS is funded via an annual membership fee. During 2024/25,
Midlothian Council paid £100,611 for the membership fee and 
£13,707 for extra charges based on the number of SMS
messages sent from the system in quarter 1 and 2.   
Page 122 of 396

Page 123

Headlines
Objectives Conclusion Comments
1. Contractual
arrangements have
been established
with the provider to
ensure the
availability, integrity
and confidentiality of
Council information.
Reasonable Members entered into an agreement for the supply of certain Education Management Information
Systems and services by SEEMiS which is noted in the service level agreements (SLAs) and a Members
Agreement with SEEMiS and other partners which has been in place since 2015.  Variations occur in the
service level agreements between SEEMiS and Midlothian Council.  The last variation occurred in 2023. 
There were no signed copies (by SEEMiS) of the variation agreements at the time of review; further
clarification was required on the business continuity arrangements for SEEMiS and guidance is required
on the retention of data within the system.  
2. User procedures,
support and training
are available to
SEEMiS users.
Reasonable  System guidance notes are provided on the SEEMiS website which can be accessed by anyone with a
SEEMiS account.  There are no Council specific guides available on the Council’s intranet however
guidance notes have been produced by the Business Applications Team and sent to schools.  Schools
can also contact the Business Applications Team regarding any queries / issues; and if required this can
be escalated to the SEEMiS helpdesk. 
A number of SEEMiS webinars are held throughout the year but there is a low record of attendance from
employees based in Midlothian Schools (only 13 employees from schools attended sessions between
January to September 2024).  There are no formal training sessions or workshops held for school staff. 
New staff undertake on the job training, and support and training can be requested from the Business
Applications Team.  It was reported that there have been occasions where there was no handover
process in schools when an employee leaves.  Management advised that formal training sessions will
be arranged in May 2025 which will include SEEMiS and other system processes. 
A report dated December 2024 highlighted a number of employees within Education services (including
supply teachers and administration staff) who have not completed the Council’s mandatory courses. 
3. There is effective
user account
management which
ensures only
authorised users
have access.
Limited  A SEEMiS user access form needs to be completed to allow school employees to be set up as a staffing
record.  Each employee has their own user ID, creates their own passwords and a work record is created
detailing the position they are filling at the school (e.g. Teacher, Music Teacher or Support Staff).  Once
the employee is set up on the system, changes can be managed by school system administrators.   An
audit trail of requests to update user access is not maintained by schools as it is actioned on verbal
instruction from senior management.     
The list of SEEMiS users (as at November 2024) was reviewed against the Council’s HR system, (iTrent)
and the data match identified 83 anomalies which required to be updated. 
4. There are
effective data input
and validation
Substantial There are validation controls in the SEEMiS system in the form of mandatory completion fields and drop-
down cells which only allow specific inputs and addresses can be verified on SEEMiS.  SEEMiS data
Page 123 of 396

Page 124

controls and data
interfaces ensure
complete and
accurate transfer of
data.
quality checks are undertaken during the collation of staff and pupil census for the Scottish Government
at the start of each school year. 
There are a significant number of data transfers to/from the Council’s SEEMiS system to third parties
such as the SQA and the Scottish Government.  The data transfer and import to SEEMiS is managed
directly by SEEMiS LLP, with Council staff being responsible for various validation and accuracy checks. 
The files are transferred using secure encryption to and from the file server via the Intranet. 
An education privacy statement was published on the website when GDPR came into force in 2018. A
Data Protection Impact Assessment (DPIA) is a legal requirement for any type of processing to ensure
data protection and privacy are considered at all times; and mitigate any risks to privacy that may arise
from the system changes.  Management advised that a DPIA will be completed as part of the deliverables
for the Parents Portal project. 
5. Regular reports
are produced to
ensure data quality
for the SEEMiS
system and
operational and
statutory reporting is
relevant, accurate
and produced on a
timely basis.
Substantial  Statutory reports which include the staff and pupil census are produced and submitted on a timely basis. 
Regular reports are produced to ensure data quality for the SEEMiS system and an annual check of data
held on students takes place.  Parents/guardians are asked to confirm, in writing, whether key contact
information held is accurate and any updates must be communicated in writing or in person and records
are then updated by office staff.  There are also provisions in place for parents/guardians to request that
schools update records at any time throughout the school year.
Regular reports are produced to monitor pupil’s attendance and bespoke reports are also produced which
allows the school office to run reports as and when required when data needs to be checked.  The
Education Performance team runs reports from SEEMiS and presents the data through the Google
Dashboard which allows schools to check the data on the reports and ensure information reported is
accurate. 
6.  Appropriate
assurances are in
place to ensure that
there are adequate
backup/recovery
procedures in place
and business
continuity plan for
SEEMiS.
Limited   Disaster recovery, backups, and continuity of the system is the responsibility of SEEMiS LLP. 
Schools have their own business continuity arrangements however these are not formally documented
which increases the risk of plans not being accessible if the SEEMiS system is unavailable.  Only 1
school had a draft plan in place, but it was still being developed at the time of the audit.  A
recommendation has been raised in the Business Continuity Audit to ensure that appropriate business
continuity plans are in place, reviewed and updated within services.  
Councils have been briefed by SEEMiS on data centre moves over the pasts few years however, no
formal documentation has been provided to evidence this.  Also, more clarity is required from SEEMiS
with regards to the annual updates undertaken on the Business Continuity Plans and evidence that
SEEMiS have appropriately tested their IT disaster recovery plans.
Page 124 of 396

Page 125

Areas where expected controls are met/good practice 
No. Areas of Positive Assurance
1. As part of the annual staff census, the Council is required to provide information on individual teaching staff to the Scottish Government.
This is checked and signed off on a school-by-school basis to ensure that only current teaching staff are included. 
2. Regular reports are produced to monitor pupil’s attendance and custom reports (eg check number of pupils receiving free school meals)
are also available which enables the school office to run reports as and when required. 
3. SEEMiS can only be accessed through a Midlothian Council PC or laptop connected to the Council network. Access to SEEMiS from
the Council network is through a secure VPN. 
4. A number of user guides and procedures are available to users.  Online system guidance notes are provided by SEEMiS on their website
which can be accessed by anyone with a SEEMiS account.  The Business Applications Team also offers training and support to schools.
5. Statutory reports which include the staff and pupil census are produced and submitted on a timely basis. 
Page 125 of 396

Page 126

Page 126 of 396

Page 127

Executive Summary: Education Construction Governance
Conclusion: Reasonable Assurance
Reasonable assurance is in place over the majority of the areas detailed in the audit scope.  However, some weaknesses were identified in
governance processes for issue escalation, arrangements for and management of the Project Boards, risk management processes,
management of project documentation, and the processes for monitoring External Project Manager performance.
Background
Following issues with the Beeslack Community High School (BCHS) contract works and Mayfield Learning Community Campus (MLCC) contract
costs, which were projects managed by the same external contractor, a review of the control and governance processes concerning these
projects was requested.  The purpose of the assurance review was to establish if the governance, control, and monitoring processes in relation to
these projects were operating effectively and issues are raised through the Council’s governance processes in a timely manner.  
Summary of findings and recommendations
The following key findings and recommendations are highlighted, which have all been agreed by Management:
• Although not a breach of the procurement process, by only appointing the top project management framework provider for financially
significant, strategic projects, there is a risk that the Council may not achieve best value or appoint an External Project Manager with the best
cultural fit using this approach.  Management will consider this for the future appointment of Project Managers by September 2025.
• The contracts for external project management resource did not formally set out any Midlothian Council specific performance standards,
expectations or governance arrangements above the standard framework conditions.  Appropriate performance standards will be agreed for
future appointments of External Project Managers by September 2025.
• Both the BCHS and MLCC Internal Project Managers were not regularly saving all relevant project documentation on to Midlothian systems. 
Management will ensure that Project Managers follow the relevant service procedures by June 2025.
• The Project Board Terms of Reference (ToR) for BCHS does not adequately set out the roles and responsibilities for members and the quorum
for decisions.  The MLCC ToR does not specify a quorum for decisions, has incomplete sections, and the board meetings for MLCC were
subsumed into other meetings following the summer period.  Management will update the ToRs and ensure board meetings are reinstated for
MLCC by June 2025. 
• Although risk reporting to the Project Boards is in place, there is no reference to the full project risk registers and the Project Boards are not
receiving assurances that the full project risk registers are regularly reviewed.  Management will review and update the risk management
processes for construction projects by June 2025.
Page 127 of 396

Page 128

• It is not documented in the Capital Plan & Asset Management Board Terms of Reference that the Chief Executive and the Leader of the
Council should be informed of any significant issues.  The Terms of Reference for the Capital Plan & Asset Management Board will be updated
by June 2025 to address the identified issues.
Recommendations
Grade 
High Medium Low Total
Current Report - 2 5 -
Prior Report (N/A) - - - -
Materiality – 
From the December 2022 Council report, the Mayfield Learning Community
Campus (MLCC) project has a budget of £46.469m. 
From the June 2023 Council report and minutes, the Replacement Beeslack
Community High School (BCHS) project including Community Facilities has a
budget of £115.811m.
Page 128 of 396

Page 129

Headlines
Objectives Conclusion Comments
1.    The procurement
process for the appointment
of the project management
elements of the Beeslack
High School and the Mayfield
Primary School
Developments was in
accordance with the
Council’s procurement
process and provided
assurance that an
appropriate qualified project
management team were
available and engaged
appropriately for both
projects.
Reasonable
Assurance
The Edinburgh City Council Professional Services Framework was used to procure the multi-
disciplinary external project management services for both projects.  Following this framework, the
Council is permitted to make a direct award to the top framework provider.  Procurement Services
confirmed that the appointed Project Managers were the top framework provider, they had
appropriate experience and suitable terms and conditions were in place.   Although not a breach
of the Council’s procurement process, there is a risk that the Council may not achieve best value
or appoint a Project Manager with the best cultural fit using this approach.   
The call-off order for project management services included the standard scope of services
detailed in the framework and did not set out any Midlothian Council specific performance
standards, expectations, or governance arrangements.  
The Development Team utilises agency workers in a variety of roles including the Internal Project
Manager for MLCC.  Resource has also been procured via a framework contract, for the BCHS
and Penicuik High School Internal Project Manager role.  There is a risk that the use of agency
workers in the same role for long periods of time may result in higher costs for the Council
compared to the cost of an equivalent employee.
2.    Appropriate processes
and resources are available
and operating effectively to
ensure adequate
management of the contracts
for project management on
both developments.
Reasonable
Assurance
Projects are allocated to Internal Project Managers in the Development Team, and they represent
the Council as the main liaison officer, ensuring the Council’s interests are represented through
the input of the Project Board, and that the appointed External Project Manager is delivering the
work required as per the contract.  Appropriately qualified external project management resource
was procured through a valid procurement route, and suitably experienced Internal Project
Managers have been appointed by the Development Team.
The BCHS Project Board ToR does not adequately set out the roles and responsibilities of Board
Members and does not specify the quorum for decisions.  The MLCC board met frequently over
the summer of 2024 however, progress reporting of the MLCC had been subsumed into other
related meetings.  Although the MLCC Project Board ToR adequately sets out the individual board
member roles and responsibilities, the quorum is not defined, and some parts of the ToR are
incomplete.  Weaknesses were identified in the management and reporting of project risks from
the full project risk register and the Internal Project Managers were not regularly updating Council
systems with all relevant project documentation.
Page 129 of 396

Page 130

3.     For the Mayfield Primary
School project an
appropriate, and consistent
methodology had been used
for identifying the budgeted
cost and tender price for the
project and that an
appropriate value
engineering process is in
place to reduce costs to an
appropriate level to allow for
a timely commencement of
the project.
Reasonable
Assurance
An external Quantity Surveyor and Cost Manager was appointed as part of the project.  The
project costs were based on Scottish Futures Trust Learning Estate Investment Programme
metrics and adjusted for inflation using the Building Cost Information Service’s index.  Following
this, abnormal costs were then included to reach the budgeted cost taking into account unique
factors relating to the building and the project.  This audit has only reviewed the process and has
not independently engaged a Quantity Surveyor to review any of the figures reported by the
Project’s Quantity Surveyor and Cost Manager.  The Stage 2 tender report was reviewed, and it
was seen that the majority of sub-contractor returns included a minimum of three quotes indicating
that the contractor’s supply chain was appropriately being assessed for the best available prices.  
For the value engineering process, evidence was provided by the Internal Project Manager of a
reasonable risk-based process being applied involving the contractor, the External Project
Manager and the Project Board members.  
4.    The tender process and
tender evaluation (based on
incorrect scoring) for the
Beeslack Community High
School contract, was
operated in accordance with
Council procurement
processes and that the
oversight of the process was
appropriate from Midlothian
Council officers.
Reasonable
Assurance
The Procurement information saved in the file directory for the original Beeslack Community High
School contract was reviewed and nothing else unusual was noted regarding the tender.  The
Internal Project Manager and the Procurement Team provided oversight over the process;
however, an error was made by the External Project Manager in a response to a contractor query
regarding how the tender evaluation should be scored.  The error was not identified at the time by
Midlothian officers or the Internal Project Manager.  
The Internal Project Manager advised that the tender documentation was not prescriptive enough
in detailing how the evaluation should be scored which allowed the error to occur.  This issue has
been rectified for the new Beeslack Community High School tender and the Penicuik High School
tender, and management have advised that it will be applied for all relevant contracts going
forward.
5.    When significant issues
relating to cost, quality or
timeliness of delivery for
either project had been
identified that there are clear
governance processes in
place and operating to
escalate these issues and
that these processes have
been followed.
Reasonable
Assurance
The Capital Plan & Asset Management Board (CP&AMB) is in place to provide a monitoring and
reporting forum for all of the Council’s capital projects.  5 sub-boards report into the CP&AMB
including the Children & Young People Estate Programme Board which is responsible for
monitoring the progress of the Children & Young People Estate programme and use of resources
as well as provide strategic oversight and technical input into the projects within the programme.  
Minutes from the CP&AMB are reported to the Corporate Management Team and are therefore
made available to the Council’s Chief Executive.  However, the Terms of References for the
Boards do not state when issues should be escalated to the Council’s Chief Executive and Leader
of the Council.
Page 130 of 396

Page 131

Areas where expected controls are met/good practice 
No. Areas of Positive Assurance
1. The Council’s procurement process has been followed for the procurement of project management resource utilising a relevant
Framework Agreement thus ensuring the appointed Project Managers are suitably qualified.
2 Internal Project Managers with the appropriate experience have been appointed to monitor the Council’s External Project Managers
and to manage Midlothian’s construction projects.
3. A consistent methodology was applied for identifying the budgeted costs of MLCC and an appropriate, risk-based process was applied
for the value engineering process.
4. Changes have already been applied to tender documentation to prevent the scoring issue that occurred with the original BCHS tender
from occurring again.
5 The Council has developed reasonable governance processes to allow for monitoring and oversight of capital projects. 
Page 131 of 396

Page 132

Page 132 of 396

Page 133

Executive Summary: IT Asset Management
Conclusion: Limited Assurance
Asset management systems are in place to manage and track IT assets and staff are knowledgeable in how to use their respective systems. 
Weaknesses were identified in the asset reconciliation process to ensure every IT asset recorded on the asset management system reconciles
to the purchases made and the details of the assets have been recorded correctly in the asset management system.  The Council’s contract for
the disposal of IT assets has been inadequately managed and the financial rebate due to the Council has not been received for a number of
years.  It was identified that IT assets were not always returned when employees leave the Council - a leavers process is in place to enable
Digital Services to disable system access but it is the responsibility of service management to ensure IT equipment is returned.  
Background
The purpose of the audit was to review the processes in place to ensure that IT assets are recorded, managed and maintained in an effective
and efficient manner.  Digital Services are responsible for the purchase and management of the Council’s corporate IT assets.  Digital Inclusion &
Learning Technology (DI&LT) are responsible for the purchase and management of Chromebook devices and Ipads primarily used by teaching
staff and pupils in Midlothian’s schools.  Digital Services utilise the Service Now IT Service Management System to support the asset
management processes.  At the time of review, the Service Now asset register had 32,462 assets in circulation (i.e. assets that have not been
classified as retired or missing).  This included 6,441 monitors, 2,961 laptops, 2,613 docking stations 2,431 PC base units, 2,172 telephones and
accessories, 1,732 Netbooks, 1,359 wireless access points and 1,196 interactive screens.  DI&LT use Google Console and Jamf to manage and
track Chromebook and Ipad devices respectively.  At the time of review there were 13,242 Chromebooks and 3,347 Ipads.
Summary of key findings and recommendations
The following findings and recommendations are highlighted, which have all been agreed by Management:
• There is no formal reconciliation process between what has been purchased and what has been uploaded to Service Now resulting in a
number of assets that could not initially be located on the system as part of the audit.  Management will develop an appropriate, independent
reconciliation process to check that all capital purchases have been logged on Service Now and include all relevant information by December
2025.
• Google Console and Jamf hold no reference to the purchase order number or invoice reference number, so it is not possible to reconcile the
systems to the purchases made using the purchase order number.  Management will ensure that the relevant Integra reference for
Chromebooks and Ipads purchased is recorded in the system so the total number in the asset system can be reconciled to purchases made
by September 2025.  
• No payments have been received from the IT asset disposal contractor since November 2018 and the contract is overdue for retendering. 
Management have agreed with the asset disposal contractor that a payment of £40,000 for the disposal of Council assets is due and an
invoice has been raised for this - a new exercise has commenced to tender for a supplier as out of contract by December 2025.  
• Although a leavers process is in place to disable system access, Digital Services rely on service management for the return of equipment.  In
the short term, Digital Services will use information from the iTrent HR and Payroll system to support the leavers and staff movers’ process. 
In the longer term, Digital Services will liaise with relevant management to improve the return rates and explore systems-based solutions to
improve asset management information by December 2025.  
• There is no documented Corporate IT Asset Management Policy, and the written procedures are incomplete and out of date.  Management
will prepare an IT Assets Strategy that sets out how the service addresses the Council’s Corporate IT Asset needs (by June 2026) and IT
asset management written procedures will be updated by December 2025.  Page 133 of 396

Page 134

• There is no formal manager sign-off of disposals prior to collection by the disposal contractor, the reason for disposal is not documented as
part of the disposal process and no notes are added to disposal documentation explaining any differences between the number of assets
submitted for collection and the number the contractor has collected.  Management will implement an authorisation process, mark the reason
for disposal and improve disposal documentation by September 2025. 
Recommendations
Grade 
High Medium Low Total
Current Report - 4 7 11
Prior Report - N/A - - - -
Materiality - 
The Net Book Value of the Council’s tangible IT Assets as at 2023/24 was
£9.21m.
Digital Services’ capital spend in 2023/24 was £567,106 and £535,483 in
2024/25.
DI&LT Equipped for Learning (EFL) capital spend in 2023/24 was £1,274,788
and 1,704,534 in 2024/25 (higher in 2024/25 due to replenishment of
Chromebook devices in the year and upgrade of classroom smart screens). 
Page 134 of 396

Page 135

Headlines
Objectives Conclusion Comments
1.    Clear, accessible,
relevant, and appropriate
policies and procedures are
in place to manage IT
assets effectively.
Reasonable
Assurance
Digital Services use the Service Now system appropriately to support its IT asset management
processes.  Procedures (dated 2018) are in place, but these are out of date and did not cover the asset
disposal process.  There is no documented IT asset management policy, e.g. a document outlining
what the Council’s IT Asset needs are and how they are addressed.  DI&LT have prepared an
appropriate asset management strategy for their assets.
2.   A complete and
accurate asset register is in
place containing all relevant
details of IT hardware
assets and a process is in
place to periodically confirm
the accuracy of the register
and update as required.
Limited
Assurance
IT assets are tagged with a unique asset number and logged on the Service Now system following
delivery.  There is no reconciliation between purchases and Service Now uploads.  The employee
uploading the majority of the asset information to Service Now is also carrying out the majority of the
purchasing activity.  19 invoices for the purchase of IT assets were reviewed and for 6 of these invoices
the assets ordered could not be fully agreed to the Service Now system; management have now
rectified this issue and all of the assets from these invoices have been located.
As part of the Windows upgrade and periodic patching requirements, Digital Services carry out reviews
to trace IT assets and service desk officers update asset details on the Service Now system following
help-desk calls, but periodic asset inspections are not carried out routinely outside of these purposes.  
DI&LT manage some Education IT assets specifically Chromebooks and Ipads; Google Console and
Jamf are used to manage and track these devices respectively.  No reference to the purchase order
numbers or invoice reference numbers were held for the assets recorded in either system, as a result it
is not possible to reconcile the systems to the purchases made using the purchase order number;
during the audit management addressed this issue going forward in Google Console.
3.   Procedures are in place
to ensure that all equipment
is returned to the Council
for reuse or disposal when
staff, workers and service
users (such as school
pupils) no longer require the
equipment and appropriate,
secure asset disposal
arrangements are in place.
Limited
Assurance
51 laptops were identified that appear to be allocated to leavers.  If an employee leaves or moves role,
it is the manager’s responsibility to ensure their team member returns all equipment.  
Digital Services and DI&LT utilise a contractor to securely dispose of IT Assets and are due a rebate for
the disposal of assets as part of the contract.  There has been inadequate management of the disposal
contract in recent years.  No payments have been received by the Council since November 2018.  In
addition, the disposal contract has been due for retendering since March 2023.  A payment of £40,000
for the disposal of Council assets has subsequently been agreed by management with the asset
disposal contractor and an invoice has been raised for this.  
There are no written procedures in place outlining the disposal process for Digital Services or DI&LT.   
Page 135 of 396

Page 136

Objectives Conclusion Comments
4.  Adequate procedures
are in place to ensure that
IT equipment allocated to
council officers and
schools, teaching staff and
pupils is appropriately
recorded to the individual
holding the equipment and
regular reconciliations are
carried out to confirm the
assets to the asset
management system.
Reasonable
Assurance
The Service Now system and Google Console utilise Active Directory to link a user account to all
mobile assets such as Chromebooks or laptops; this ensures that there is a contact to trace all assets
issued.  Microsoft Configuration Manager is used for the patching of Windows devices and further
information on the Council’s Windows assets is available through Qualys, the vulnerability and
configuration management software.  Management have advised that better usage and asset
monitoring information would be available in Service Now if information from Qualys could be
integrated into Service Now using the Cyber Security Asset Management module provided by Qualys,
but there would be a cost for this.  For example, details of asset IP addresses or the most recent user
to login is available in Qualys but has to be manually added for that information to be available in
Service Now.   
5.   Procedures are in place
to record and monitor the
loss / breakage of IT assets
across the Council
(including schools) and
potential fraud is reported
and investigated on a timely
basis.
Reasonable
Assurance
Breakage of Corporate devices appears to be infrequent with only 85 laptops submitted for repair in
2024/25.  IT assets reported as stolen are submitted to the Information Compliance Officer and a data
breach form is prepared.  Thefts of IT assets over the past 3 years are as follows: 2024 – 1 laptop,
2023 – 2 laptops, 2022 – 5 laptops.  Other IT assets are recorded as ‘missing’ by Digital Services each
year in the Service Now system, but these assets are not subsequently reported to the Information
Compliance Officer (2024 – 22 devices, 2023 – 69 devices, 2022 – 36 devices).  The Information
Compliance Officer advised that these ‘missing’ devices, although relatively lower in risk due to device
encryption, are still a potential information breach that should be reported as is currently done for all
lost mobile phones.  Corporate Fraud are not currently informed of IT asset losses.
Reasonable policies and procedures have been developed by DI&LT for Chromebooks and Ipads
issued to schools.  Appropriate asset damage tracking processes have been developed and rolled out
to all schools and appear to be operating well from the sample of 5 schools reviewed.  A form must be
prepared for all school leavers, and this includes collecting their device.  Since the start of EFL, 803
Chromebook devices have not been returned by pupils (this represents approx. 4.2% of the 19,081
Chromebooks purchased since the start of EFL).  
Page 136 of 396

Page 137

Areas where expected controls are met/good practice 
No. Areas of Positive Assurance
1. Appropriate asset management systems are in place to allow the Council to manage and track its IT assets.
2 Services are knowledgeable in how to use their respective systems to support the Council’s asset management processes.
3. Mobile IT assets are issued to a named individual and the details of this are logged in the respective asset management system.
4. Comprehensive policies, procedures and processes have been developed to support the Council’s Equipped for Learning Project and
significant rollout of Chromebooks to pupils including the tracking of asset damage and leavers’ management.
5 The Council’s IT assets are disposed of using a provider that has been assessed as appropriately secure.
6 Asset management information is provided by DI&LT to all schools.
8 Processes are in place and are operating effectively to remove systems access for employees that leave the Council.
9 Data breach procedures have been established for reporting asset thefts. 
Page 137 of 396

Page 138

Page 138 of 396

Page 139

Executive Summary: Revenue Financial Budget Monitoring 
Conclusion: Reasonable Assurance
Revenue budget monitoring processes are in place, regular reports are produced and meetings with budget holders are taking place on a regular
basis. However, material variances within Social Care services are not currently included in Council reports. Financial Directives require updating
and Finance procedures should be documented. 
Background
The Council has responsibility for setting an annual budget and monitoring expenditure and income against budget allocations.  Budget monitoring
is carried out by utilising the financial accounting software system, Integra Centros; and there are a range of other management information
systems which provide data that is utilised by the Finance team and budget holders to evaluate the financial performance of services. The timing
of financial information does not always allow accurate forecasting which creates inaccurate position statements and does not aid management
decisions to address any financial issues in a timely manner. The Finance team have a key role in providing advice and analysis to service areas
throughout the year on the financial impact of decisions made, to help ensure the Council continues to deliver the highest quality of services in
Midlothian.  The Medium-Term Financial Strategy (MTFS) details the general fund revenue statement forecast through to 2028/29 and identifies
additional revenue savings and income required with the objective of achieving a financial-balanced budget. It also demonstrates assumptions
used within budget projections and information from the Scottish Government.  The Council had a General Fund Revenue Budget of approximately
£295 million for the financial year 2024/25.  As part of the budget setting process, Members were presented with a range of savings measures
for consideration which were approved by Council.  The Business Transformation Steering Group (BTSG) consider the necessary actions required
to support the delivery of a balanced MTFS before any policy measures are presented to Council. 
Summary of findings & recommendations
The following key findings and recommendations are highlighted, which have all been agreed by Management:
• The Financial Directions require update to provide appropriate procedural instructions and responsibilities to budget holders; and budget
monitoring procedures within the Finance team should be documented. Management have agreed to update and review the Financial Directives
by December 2025 and have agreed to review good practice and consider establishing budget monitoring procedures within the Finance Team
by December 2025.
• Material variances within Adult Social Care services are not currently included in Council reports. Management have agreed to report the
impact of material variances within Social Care services in Council reports from September 2025.
• There is not an agreed / specific material variance amount above which consideration of reporting to Council should be given.  Management
have agreed to state in the Finance budget monitoring procedures the specific level of material variances which should be considered for
reporting to Council by December 2025.
• The reasons for any income shortfall identified within the formal budget monitoring are not always documented following budget monitoring
meetings. Management have agreed to reinforce this process and include as part of the budget monitoring procedures by December 2025. 
• There is no documentation of the risk assessment completed of each service to indicate the frequency of budget reporting required.
Management advised that there is an ongoing assessment of financial risk and flexing the budget monitoring approach and will implement a
documented register of all service areas and their current risk assessments by December 2025. 
Page 139 of 396

Page 140

• Senior management budget monitoring meetings are held to assist with forecasting and budget monitoring, an action log is not always currently
being documented. The process is currently being reviewed and any new process will ensure that appropriate documentation is maintained by
December 2025.   
Recommendation Summary
Recommendations
Grade 
High Medium Low Total
Current Report  3 7 10
Prior Report  3 4 - 7
Materiality
As reported in February 2025, the projection of the General Fund
balance as at 31 March 2025 was £20.965 million, of which £13.126
million is earmarked for specific use leaving a non-earmarked
General Fund Balance of £7.839 million. 
Page 140 of 396

Page 141

Headlines
Objectives Conclusion Comments
1.  Revenue budgets
are controlled in
accordance with the
Financial Regulations.
Reasonable Financial Regulations are in place and any changes require the approval of Council.  The Financial
Regulations are supported by a series of Financial Directives.  The Financial Regulations were approved
by Council in June 2022 however the Financial Directives are still under review.  There are no documented
budget monitoring and reporting procedures within the Finance team.  
2. Revenue budget
setting is linked to
planning processes
and budgets are
revisited when plans
change. 
Reasonable Budgets are set annually, agreed with budget holders and senior management and are formally approved
by Council. Budget reports are not produced on a period-by-period basis in areas considered to be low
risk, however there is no documented risk assessment detailing the risk rating of all areas.  
3.  Revenue budget
process and
procedures are being
completely
appropriately by
adequately trained
officers. 
Reasonable Informal training is provided to new budget holders however a record is not maintained of the training
provided.  A questionnaire was issued to 55 budget holders (32 responses were received) and the majority
were confident they understand the financial information they are receiving.  Some points raised were that
budget lines can be confusing and refresher training would be useful.  Additional management comments
received stated that the timing of financial information does not allow accurate forecasting which creates
inaccurate position statements and does not aid management decisions to address any financial issues in
a timely manner.
4. Revenue budget
monitoring reporting for
Elected Member; and
senior management
level is adequate. 
Limited Members receive a quarterly financial monitoring report of the general revenue fund however the report
for the first quarter of each financial year is not received until August due to the timing of Council meetings. 
It was reported in February 2025 (end of quarter 3) that there was a projected net overspend of £2.168m
which partly or mainly relates to recurring areas of financial pressure or slower than planned delivery of
savings measures. The report does not highlight variances within the Adult Social Care areas – a verbal
update of the significant overspend was provided to Council during 2024/25 and in formal MIJB reporting
which is signposted as part of the reporting to Council. 
5. Plans are in place for
the monitoring of the
achievement of
identified savings. 
Reasonable As part of the budget setting process, Members approved a range of savings measures.  Half yearly reports
are presented to BTSG providing an update on the delivery of approved savings and this is also included
within reports to Council on a quarterly basis.  In February 2025, a report to Council stated that there
remains £1.34 million of MTFS cost reductions either to be finalised or to be fully implemented and
highlighted that a number of these are taking longer than planned to implement.  Although income and
saving targets within Services are regularly monitored, the reasons for any income shortfall identified within
the formal budget monitoring are not documented following budget monitoring meetings. 
Page 141 of 396

Page 142

Areas where expected controls are met/good practice 
No. Areas of Positive Assurance
1. The Finance team hold regular meetings with budget holders and various budget boards / groups have been set up within Directorates
which focus on monitoring of revenue budgets.  Regular reports on forecast outturn and budget variances are provided to budget
holders, senior management and Members.  Material variances are investigated and discussed at the budget board / group meetings
and actions are tracked on the material variance statements.  In some areas, budget working papers are held on the shared network
drive so that relevant budget holders can access them accordingly. 
2. Budgets are set annually and include assumptions contained therein. Budgets are agreed with budget holders and senior management.
The budget is reviewed and formally approved by Members each year at Council.  
3. From our sample of questionnaire responses from budget holders, the majority of budget holders reported that they were satisfied with
the completeness and accuracy of budget monitoring information provided to them and the Finance team provides effective ongoing
support to budget holders. The Finance team provide one-to-one training for new budget holders. 
4. Cost Centres are established to collect costs and incomes for a specific service area. This information is used to prepare / monitor
budgets. 
Page 142 of 396

Page 143

Audit Committee
Monday 16 June 2025
Item No 5.6 
Council Tax Refunds Control Assurance Review 
Report by Chief Internal Auditor 
Report for Information 
1 Recommendations 
The Audit Committee is asked to note the Council Tax Refunds
Controls Assurance review completed by Internal Audit in June 2025,
as a result of the letter from the Chair of the Accounts Commission to
all Scottish Local Authority Chief Executives on the 10 January 2025.   
2 Purpose of Report/Executive Summary 
Following receipt of a letter from the Chair of the Accounts Commission
the Chief Executive of Midlothian Council requested that Internal Audit
review the areas indicated in the letter against the processes for
payment of Council Tax refunds in Midlothian Council. The Report
concludes that the Council has good procedural controls in place,
however there is evidence that compliance with these controls is not
always being monitored and are not backed by appropriate systems
controls for segregation of duties. Subsequent sample testing identified
no evidence of fraud within the 2024/25 financial year 
Date 4 June 2025 
Report Contact:
Duncan Stainbank 
duncan.stainbank@midlothian.gov.uk  
Page 143 of 396

Page 144

2
3 Background 
3.1 On 10 January 2025, the Chair of the Accounts Commission sent a
letter to all Scottish Local Authority Chief Executives copying the
Directors of Finance (see appendix 1). The letter highlighted the
consideration that had been given to the report from the 2023/24 year
on the significant council tax refund fraud perpetrated against
Aberdeen City Council (see appendix 2). The Commission indicated
that it was important to share the lessons the sector as a whole can
learn from Aberdeen City’s experience. 
3.2 Following receipt of this letter the Chief Executive referred this to
Internal Audit to undertake an exercise to review if the control
weaknesses in place in Aberdeen City Council, as highlighted in the
report, also exist in Midlothian Council. This report provides the
conclusion to this review     
3.3 The review covered the following key areas in relation to Council Tax
Refund Processes:
• Segregation of Duties;
• Systems Controls;
• Reconciliations; 
• Systems Documentation;
• Monitoring; and
• Counter Fraud Arrangements. 
3.4 The report concludes that the Council has good procedural controls in
place, however there is evidence that compliance with these controls is
not always being monitored and are not backed by appropriate systems
controls for segregation of duties. Subsequent sample testing identified
no evidence of fraud within the 2024/25 financial year. Implementation
of the 3 recommendations made will return the controls in this area to a
reasonable state going forward. One recommendation is for the refresh
of the Counter Fraud Policies which was already planned for in
2025/26. 
Page 144 of 396

Page 145

3
4 Report Implications (Resource, Digital, Risk and Equalities) 
4.1 Resource 
Resources to implement the recommendations made in the report have
been identified by service management as appropriate. 
4.2 Digital 
The systems supplier has already been asked to develop the required
solution this as part of an ongoing upgrading project. 
4.3 Risk 
Implementation of the recommendations made in the report will reduce
the risk of fraud within the Council Tax Refunds processes. Further
consideration of the risks highlighted across the Council will further
assist in reducing the Councils risks. 
4.4 Ensuring Equalities 
This report does not relate to a new or revised policy, service or budget
change, which affects people (the public or staff), so an Integrated
Impact Assessment (IIA) is not an applicable consideration. 
4.5 Additional Report Implications (See Appendix A) 
Page 145 of 396

Page 146

4
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Although this report does not relate directly to the key priorities within
the Single Midlothian Plan (Reducing the gap in economic
circumstances; Reducing the gap in learning outcomes; Reducing the
gap in health outcomes; and Reducing the impact of climate change)
Note is made that these key prioities are reflected in the audit plan and
any links will be identified as part of each assurance review planning
process going forward. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working  
Hub and Spoke  
Modern  
Sustainable  
Transformational  
Preventative  
Asset-based  
Continuous Improvement  
One size fits one 
None of the above 
Midlothian Council is committed to creating a great place to grow
supported by the 9 drivers for change. Implementing the 9 drivers for
change in practice is applicable to the Council’s Internal Audit service
provision to assist the Council in achieving its objectives. 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you  
Preventative and Sustainable  
Efficient and Modern  
Innovative and Ambitious 
A.4 Delivering Best Value 
The definition of Internal Auditing within the Public Sector Internal Audit
Standards (PSIAS) is “Internal auditing is an independent, objective
assurance and consulting activity designed to add value and improve
an organisation’s operations. It helps an organisation accomplish its
objectives by bringing a systematic, disciplined approach to evaluate
and improve the effectiveness of risk management, control and
governance processes.” 
Page 146 of 396

Page 147

5
Implementation by Management of the actions associated with these
consulting recommendations, are designed to improve internal control
and governance arrangements and management of risks, underpinning
the Council’s own continuous improvement arrangements to enhance
its effectiveness, thus supporting the delivery of the Council’s best
value duties. 
A.5 Involving Communities and Other Stakeholders 
The Chief Internal Auditor is accountable to the Audit Committee which,
in fulfilling its governance role, acts as a bridge between the Council
and other stakeholders. 
This report was created with consultation from Service and Senior
Management. 
A.6 Impact on Performance and Outcomes 
The Findings and Recommendations from Internal Audit work during
the year are designed to assist the Council in improving its
performance and outcomes. 
A.7 Adopting a Preventative Approach 
Internal Audit assurance work includes assessments on when a
preventative approach can be adopted. 
A.8 Supporting Sustainable Development 
This report does not relate directly to supporting sustainable
development. Good governance is important to enable Midlothian
Council to achieve its objectives. 
Page 147 of 396

Page 148

Page 148 of 396

Page 149

Chief Internal Auditor
Duncan Stainbank 
Auditor: Duncan Stainbank
Assurance Review 
To 
Kevin Anderson, Executive Director Place                                                                     
Saty Kaur, Chief Officer Corporate Solutions 
Jacqui Dougall, Business Service Manager 
David Gladwin, Chief Financial Officer and Section 95 Officer 
On 
Council Tax Refunds Fraud Control Assurance Review 
4th June 2025 
Page 149 of 396

Page 150

Midlothian Council
Internal Audit Assurance Review Council Tax refunds   
1 Background 
1.1 On 10 January 2025, the Chair of the Accounts Commission sent a letter to all Scottish Local Authority Chief Executives copying
the Directors of Finance (see appendix 1). The letter highlighted the consideration that had been given to the report from the
2023/24 year on the significant council tax refund fraud perpetrated against Aberdeen City Council (see appendix 2). The
Commission indicated that it was important to share the lessons the sector as a whole can learn from Aberdeen City’s experience. 
1.2 The letter further indicates that: 
“as finances get tighter and decisions are taken to rationalise back-office functions to protect front line services for our
communities, it is critical that your staff across all functions have and implement effective financial controls, which safeguard
public assets, irrespective of the level of income and expenditure involved.”
“While this particular fraud was complex, weaknesses in the council's internal controls allowed the fraud to continue over a
prolonged period. Controls exist to safeguard both the employees and the employer. In this case, failure to implement controls
and a lack of monitoring enabled an abuse of authority which, when combined with a detailed operational knowledge, provided the
opportunity to withdraw funds inappropriately.”
1.3 The Chief Executive referred this to Internal Audit to undertake an exercise to review if the control weaknesses in place in
Aberdeen City Council, as highlighted in the report, also exist in Midlothian Council.   
2 Findings 
For the key objectives, the following points were noted: 
Segregation Of Duties / System Controls
2.1 The Council Tax team have appropriate procedures in place for making credit balance refunds that would indicate that there is a
requirement for request and authorisation of any credit balance refund to be completed before the refund has been paid.
However, when asked to confirm if the Council Tax system enforces this segregation of duties it was established that this is not
the case.   
2.2 Testing of a sample of 32 credit balance refunds in 2024/25 established that for 3 cases Revenues Officers were able to issue
refunds above their limit (set by the procedures) due to the lack of any system control preventing this action. 
Reconciliations 
2.3 The Finance team complete regular reconciliations of the Council tax system to the financial ledger which cover all payments. 
Page 150 of 396

Page 151

Midlothian Council
Internal Audit Assurance Review Council Tax refunds   
Systems Documentation 
2.4 Appropriate procedures and systems documentation are in place for credit balance refunds. There were 11 refunds where a refund
memo was not created in accordance with the refund procedures and there were 6 refunds when a refund letter was not sent out
confirming the refund made, which would provide assurance that a notification system was in place for refunds. There are some
concerns that improvements are still required to ensure that procedural controls are adhered to particularly as the systems controls
are not in place. 
Monitoring 
2.5 The level of credit balances is reviewed by the Revenues team on an annual basis and the Council currently has circa £200k of
credit balances remaining on council tax accounts. Processes are undertaken to transfer balances to new accounts or refund
balances when details of the council taxpayer are known. However, there is no monitoring of the payment of credit balance
refunds.  This should be put in place particularly to identify transactions that have not followed the appropriate refund procedures
including segregation of duties, and to review payments to duplicate bank details on at least a six-monthly basis. 
Counter Fraud Arrangements 
2.6 The Council has robust counter fraud arrangements which include regular Integrity Group meetings, a whistleblowing policy and
links to report suspected fraud, whistleblowing, bribery and corruption. A substantial number of reports are made and investigated
on an annual basis. There is however a requirement, which was already planned for, to review the Counter Fraud, Bribery and
Corruption policies and the Whistleblowing policy during the 2025/26 financial year. These policies will then be presented to the
Integrity Group for approval and communicated across the Council to further enhance the controls in place to ensure detection of
any issues. 
3 Conclusion 
Based on our review, the Council has good procedural controls in place, however there is evidence that compliance with these controls is not
always being monitored and are not backed by appropriate systems controls for segregation of duties. Subsequent sample testing identified no
evidence of fraud within the 2024/25 financial year. Implementation of the recommendations made will return the controls in this area to a
reasonable state going forward. 
4 Recommendations 
Recommendation 1: The Council tax system supplier should be requested to ensure that the system implements rules for all refund payments
that require 2 individual accounts, including the value escalations in accordance with the procedures, to confirm refund payment details before
payments are made and this should be progressed to full implementation as soon as possible.     
Management Response 
Page 151 of 396

Page 152

Midlothian Council
Internal Audit Assurance Review Council Tax refunds   
The systems supplier has already been asked to develop this as part of an ongoing upgrading project. 
Responsible Officer and Target Date 
Saty Kaur/Jacqui Dougall:  June 2026 
Recommendation 2:  Revenues Management should implement a systems reporting process to identify all refund details on a monthly basis
and review those that have not been completed within the procedures including, but not restricted to, segregation of duties requirements, delivery
of letters and correct bank details being used.     
Management Response 
There are on average, 250 refunds every month (based on the volume for 2024/25). The system supplier has been requested to implement
controls on segregation of duties and values. Once we have had a response as to whether this can be implemented and a timeline for this, then
a monthly reporting process will be designed. It will not be possible to manually check every refund transaction however a review of the
procedure to reflect the system changes will be made and sample testing will follow thereafter. 
Responsible Officer and Target Date 
Saty Kaur/Jacqui Dougall:  June 2026 
Recommendation 3: Midlothian Council Whistleblowing, Fraud and Bribery and Corruption policies should be updated and approved by the
Integrity Group and then communicated effectively across the Council. 
Management Response 
This will be completed in line with the planned expectation. 
Responsible Officer and Target Date 
Duncan Stainbank/Integrity Group, December 2025. 
Page 152 of 396

Page 153

4th Floor
102 West Port
Edinburgh  EH3 9DN
T: 0131 625 1500
E: info@audit-scotland.gov.uk
www.audit-scotland.gov.uk 
To All Chief Executives            10 January 2025 
Copied to: Directors of Finance; External auditors 
Dear Chief Executive, 
You may be aware that, on 12 December, the Accounts Commission considered a report from
the Controller of Audit (under powers in s102 (1) of the Local Government (Scotland) Act 1973)
in relation to a significant council tax refund fraud perpetrated against Aberdeen City Council.
In her remarks to the Commission, the Controller made the point that this case should act as
a “cautionary tale”. In response, the Commission decided that, in addition to publishing
findings (which can be found here), it would be important to share with all Chief Executives,
copying in relevant local government professional networks, the lessons the sector as a whole
can learn from Aberdeen City’s experience. 
As finances get tighter and decisions are taken to rationalise back-office functions to protect
front line services for our communities, it is critical that your staff across all functions have and
implement effective financial controls, which safeguard public assets, irrespective of the level
of income and expenditure involved. 
While this particular fraud was complex, weaknesses in the council's internal controls allowed
the fraud to continue over a prolonged period. Controls exist to safeguard both the employees
and the employer. In this case, failure to implement controls and a lack of monitoring enabled
an abuse of authority which, when combined with a detailed operational knowledge, provided
the opportunity to withdraw funds inappropriately. 
This should serve as a timely reminder for all councils to consider whether the following
fundamental internal controls are operating effectively:   
• segregation of duties: ensuring access to systems are restricted to appropriate
levels (to negate the possibility of individuals processing transactions all the way
through the payments process).  
• reconciliations: ensuring feeder systems are effectively reconciled to other
systems (e.g. general ledger); using third party information (suppliers’ statements)
and reconciling with payment systems.  
• system documentation: system documentation should be maintained which
details key controls to be carried out by staff to prevent fraud or error.  
• monitoring: scrutiny monitoring should be at a level that would allow managers to
identify anomalous payments at an early stage. 
• counter-fraud arrangements: refresh and promote the counter-fraud policy with
staff. 
Page 153 of 396

Page 154

It is your responsibility to ensure that such arrangements are in place to help assure elected
members and the public that risks are being identified and managed effectively. I would
encourage you all to use the annual governance statement as an opportunity to take stock of
the key controls and processes and whether self-assessment procedures are sufficient to
provide elected members and officers with the required assurances. Internal and external
auditors have an important role to play in helping public bodies assess their control
environment and evaluating the effectiveness of controls, but they are not responsible for
identifying all instances of fraud. 
If you have any questions or queries in relation to the report on the Aberdeen City Council case
specifically or on any other aspect of the Commission’s work, please do not hesitate to email
acsupport@audit-scotland.gov.uk 
I look forward to engaging with you during 2025. 
Yours sincerely, 
Jo Armstrong
Chair, Accounts Commission 
Page 154 of 396

Page 155

The 2023/24 audit
of Aberdeen City
Council
Council tax refunds – a significant fraud 
Prepared by the Controller of Audit
January 2025
Page 155 of 396

Page 156

The 2023/24 audit of Aberdeen City Council | 2
Contents
Commission findings 3
Introduction 5
Timeline of key events 7
Council tax – accounts in credit 9
Strengthening the council’s internal controls 14
The council’s response to taxpayers 19
Conclusions 20
Accessibility
You can find out more and read this report using assistive technology on our website www.audit.scot/accessibility.
Page 156 of 396

Page 157

Commission findings | 3
Commission findings
The Accounts Commission accepts the Controller of Audit’s report on a
matter arising from the 2023/24 audit of Aberdeen City Council – a
significant council tax refund fraud perpetrated against the council. The
Commission welcomes that the Controller used her powers to bring this
issue, and the council’s response, to the Commission’s attention. Following
consideration of the report (presented at page 5) at its meeting on
12 December, the Commission has made the findings presented below:
1 The member of staff who identified this fraud should be commended, for
having the confidence to initially raise the issue and to then escalate it when
they remained concerned by the response received. The Commission wishes
to stress the importance of the council keeping its policies, training, and
procedures in relation to counter-fraud and whistleblowing up to date and
communicated to all staff. This will ensure that staff continue to have the
confidence to raise concerns if they suspect something fraudulent may
be happening.
2 The Commission recognises that the council reacted quickly once the
suspected fraud was brought to their attention and has made progress to
recover lost funds. However, this case exposed real weaknesses in internal
controls, allowing the perpetrator’s actions to go unnoticed for 17 years. While
controls and policies were in place, reports were not routinely run or reviewed
and there was no scrutiny by the council to ensure the effectiveness of
controls, something that is of concern to the Commission. 
3 The Commission is pleased to see evidence that the council is taking the
matters highlighted by this fraud seriously, including the segregation of duties
immediately following the issue coming to light, the development of an
improvement plan by the service, and the engagement of internal audit to
further strengthen key controls. However, controls have yet to be embedded
in a way that fully addresses all the issues identified. December 2024 was
identified as a key implementation date for improvement actions, but the
absence of interim milestones makes it difficult to assess progress on the
ground. As a matter of priority, the Commission asks the council’s ‘Task and
Page 157 of 396

Page 158

Commission findings | 4
Finish’ Group to confirm to elected members and management team when
all actions will be complete, given it has now been more than a year since
the perpetrator was charged. 
4 There is an important obligation on Aberdeen City Council to have and to
implement effective financial controls, which safeguard public assets, across
all its functions, irrespective of the level of income and expenditure involved.
Building on this experience, the Commission would urge the council to ensure
that no areas are neglected within their control environment and that the
council’s internal audit function regularly considers areas that might be
perceived as low risk when developing audit plans. Through governance
processes, we expect to see evidence that the council’s management team is
acting upon and applying recommendations from both external and internal
auditors to address potential weaknesses and risks.
5 The Commission expects all councils in Scotland to ensure that fundamental
internal controls are in place and working effectively. Such controls include
appropriate segregation of duties, ensuring systems reconciliations are
carried out, maintenance of system documentation (detailing key controls),
and budget monitoring. All councils should also be self-assessing controls
and processes through their annual governance statement. It is also
important that across all councils, internal and external auditors raise and
discuss any areas of potential concern. 
Page 158 of 396

Page 159

Introduction | 5
Introduction
1. The Code of Audit Practice requires auditors to produce an Annual Audit
Report (AAR) summarising the significant matters arising from their audit
work. For local authorities, auditors address the AAR to elected members
and the Controller of Audit.
2. I have reviewed the 2023/24 AAR for Aberdeen City Council (the
council) from the appointed auditor, Michael Oliphant (Audit Services
Group, Audit Scotland). The auditor’s AAR was considered by the council’s
Audit, Risk and Scrutiny Committee on 27 June 2024. The auditor issued
an unmodified opinion on the council’s 2023/24 annual accounts.
3. The auditor reported on a significant fraud identified by the council in
September 2023. A former employee had diverted fraudulent payments
totalling £1.109 million to his own bank accounts over a period of 17 years.
Having plead guilty to criminal charges of embezzlement, the perpetrator
received a four-year prison sentence at the High Court in Edinburgh in
July 2024.
4. I have decided to use the reporting powers available to me under
s102 (1) of the Local Government (Scotland) Act 1973 to bring this issue,
and the council’s response, to the Commission’s attention.
Background
5. The perpetrator identified council tax accounts with historic credit
balances and used their unsupervised authority to issue council tax
refunds of up to £3,000, to divert refunds to themselves, often on a
weekly basis.
6. There was no major impact on the financial statements during this
period, covering financial years 2006/07 to 2023/24 and the payments did
not represent a material misstatement in any given year. There was no
impact on the council’s budget as the amounts were taken from balances
held by the council on behalf of taxpayers who had made overpayments
on their council tax accounts. Nevertheless, the funds were held for
safekeeping by the council who will need to manage any associated
reputational risk and ensure credit balances are restored. The council has
reached agreement with the perpetrator to recover funds. In addition,
a claim to the council’s insurers is currently under negotiation but is
expected to cover the remainder of the loss.
Page 159 of 396

Page 160

Introduction | 6
7. There were failures in controls within the council that allowed this fraud
to continue over a prolonged period. In particular, a lack of segregation of
duties and monitoring in relation to council tax refunds allowed the
perpetrator to transfer balances between council tax accounts, input
bank account details and process refunds without any further checking
of processing.
Page 160 of 396

Page 161

Timeline of key events | 7
Timeline of key events
Date Event
1 November 2006 –
6 September 2023
Perpetrator processed 655 payments to himself totalling
£1.109 million.
12 September 2023 Staff member identified and investigated an irregular transaction on
a council tax account and raised the entry with the perpetrator.
The perpetrator subsequently repaid the queried amount into the
council tax standing order bank account.
13 September 2023 The perpetrator contacted staff member to discuss irregular
transaction, but staff member was not convinced by the
explanation offered.
14 September 2023 The perpetrator reversed all entries relating to the last
embezzlement transaction.
14 September 2023 Staff member investigated further and raised with Council Tax and
Recovery Manager. Senior revenues staff and the council’s
counter-fraud team advised.
15 September 2023 The perpetrator was suspended (under a precautionary
suspension) and all access to buildings and computer systems was
disabled.
21 September 2023 Counter-fraud team contacted Police Scotland following initial
investigation.
21/22 September 2023 Chief Officer – Finance advised members of the Corporate
Management Team, Internal and External Audit. Director advised
Councillor Malik (Audit, Risk and Scrutiny Committee Convener)
and Councillor McLellan (Finance and Resources Committee
Convener).
September/October
2023
Chief Officer – Finance undertook review of systems and
processes. Improvement plan produced.
26 November 2023 The perpetrator was arrested and charged by Police Scotland.
12 December 2023 A formal disciplinary meeting was held and the accused was
dismissed.
21 December 2023 All elected members advised of the matter and the upcoming court
appearance. 
Page 161 of 396

Page 162

Timeline of key events | 8
Date Event
12 February 2024 Report to Audit, Risk and Scrutiny Committee.
17 April 2024 Follow-up report to full council.
June 2024 The High Court in Edinburgh found perpetrator guilty of
embezzlement of £1.109 million from the council. He was later
jailed for four years.
July-September 2024 Internal Audit requested to review the implementation of the
service’s improvement plan. A review was undertaken and
reported to management in September 2024. 
Page 162 of 396

Page 163

Council tax – accounts in credit | 9
Council tax – accounts in credit
8. The council administers the council tax database which includes
approximately 124,500 properties and raises annual income in excess of
£100 million (Exhibit 1). The database requires to be regularly updated for
changes in taxpayers’ circumstances, such as changes in address or other
household details. The council offers taxpayers a number of payment
options although direct debit is the most popular.
9. Unpaid income is collectable for all prior years and the council pursues
outstanding debts for all years until they are either paid or identified as
uncollectable. Over the last 17 years, approximately £2 billion of council
tax income was administered and collected.
Exhibit 1
Council tax credit balances as a percentage of council tax
Year
Council tax billed
(net of discounts)
£000
Credit balances
at year end
£000
Credits as a
percentage of
council tax billed
2023/24 139,111 366 0.26%
2022/23 130,850 441 0.34%
2021/22 126,185 482 0.38%
2020/21 123,777 454 0.37%
2019/20 120,282 281 0.23%
2018/19 113,871 376 0.33%
Source: Aberdeen City Council audited accounts and council tax reports
10. At 31 March 2024, the cumulative value of accounts in credit covering all council tax years
was £1.2 million. This comprised 6,600 accounts of which 95 per cent had balances less than
£500. Exhibit 1 also gives an indication of the relatively small scale of council tax credit balances
when compared with the amount of council tax billed each year. In general, the balances on
these accounts are less than 0.5 per cent of billing totals. For example, with reference to
financial year 2021/22, council tax billed
Page 163 of 396

Page 164

Council tax – accounts in credit | 10
amounted to £126.185 million while accounts in credit for that financial
year were £482,000 at 31 March 2022.
11. There is no single reason for an account to be overpaid (in credit) but
many will arise from a change in address where the taxpayer has not
provided a forwarding address. When a taxpayer changes address within
the city area, any credit balance is transferred to the new council tax
account. If the move is outwith the city, a refund is required. Prior to 2006,
this was dependent on taxpayers getting in touch to request a refund.
As most amounts are small, this generally did not happen. In 2006, the
council introduced a policy to automatically refund paying bank accounts
for any overpayments which had arisen by direct debit. Exhibit 2 shows
the age of the historical balances held by the council at 31 March 2024
on behalf of taxpayers.
Exhibit 2
Age of credit balances at 31 March 2024
Source: Aberdeen City Council reports
12. Where bank details are not held or an address is not known, the council sends a letter to
the property address to enable a letter to be forwarded should a mail redirection be in place.
There is no time limit for a taxpayer to make contact and seek a refund.
Page 164 of 396

Page 165

Council tax – accounts in credit | 11
Scale of embezzlement
13. A total of 655 payments amounting to £1.109 million and involving an
estimated 5,700 council tax accounts were made to the embezzler’s bank
accounts over a 17-year period between November 2006 and
September 2023.
14. The total value of the accounts in credit at 31 March 2024 was
approximately £1.2 million. Had funds not been withdrawn inappropriately,
the level of balances would be £2.4 million. Exhibit 3 shows the combined
total of the balances on the accounts in credit for recent years with the
amounts embezzled.
Exhibit 3
Cumulative fraud and credit balances
Source: Aberdeen City Council reports
Page 165 of 396

Page 166

Council tax – accounts in credit | 12
15. Exhibit 4 provides details of the fraudulent refunds made including the
total and average values and the number of refunds on an annual basis.
Exhibit 4
Council tax fraudulent payments – number and value by financial year
Year
Value of fraudulent
refunds per year (£) Number of refunds Average Value (£)
2023/24 46,921 16 2,932
2022/23 82,836 29 2,856
2021/22 90,307 31 2,913
2020/21 74,368 26 2,860
2019/20 94,835 36 2,634
2018/19 87,166 33 2,641
2017/18 69,809 26 2,685
2016/17 62,331 25 2,493
2015/16 67,659 31 2,182
2014/15 78,970 38 2,078
2013/14 67,306 38 1,771
2012/13 55,114 40 1,378
2011/12 56,602 46 1,230
2010/11 46,925 57 823
2009/10 32,878 44 747
2008/09 45,499 75 607
2007/08 41,335 53 780
2006/07  8,413 11 765
Total 1,109,274 655
Source: Aberdeen City Council reports
Page 166 of 396

Page 167

Council tax – accounts in credit | 13
16. The perpetrator, as a team leader, had authority to process refunds for
amounts between £500 and £3,000. Accounts in credit are mainly smaller
amounts and therefore the perpetrator needed to collate a number of
balances together in a single council tax account to produce a total
amount in the range he could authorise which were then processed as a
refund to his own bank account.
17. Identification of the embezzlement was the result of an officer routinely
checking arrears recovery reports with the council tax computer system.
Multiple transfers were noticed on an account in credit and not being
satisfied with the explanation received from the perpetrator, as team
leader, the officer referred the matter to a more senior officer.
The perpetrator was promptly suspended thereafter, and investigations
commenced.
Page 167 of 396

Page 168

Strengthening the council’s internal controls | 14
Strengthening the council’s
internal controls
Council tax refunds
18. The perpetrator was a team leader in the council tax team which forms
part of People and Citizens services within the Corporate Services
Directorate. While the service and job titles have been restructured on
several occasions over the years, the individual held this, or similar roles,
within council tax administration since 1988. Key responsibilities included:
• supervising council tax and recovery administration
• ensuring documentation is accurate and issued on time
• contacting customers by means of writing, telephone and visits
• undertaking quality checks on council tax and recovery
administration
• recording performance and producing reports.
19. As part of the team leader role, the individual could authorise refunds
of between £500 and £3,000. There were controls in place (Exhibit 5,
page 15) which required team leaders to involve another team leader in
checking and processing refunds to ensure adequate segregation of
duties. While the procedures existed, there were no checks to ensure they
were adhered to. It was therefore possible for the perpetrator to process
refunds without anyone else being involved. Failure to implement controls
enabled an abuse of authority which when combined with a detailed
knowledge of council tax administration, obtained over many years of
employment, provided the opportunity to withdraw funds inappropriately.
20. Given the number of accounts affected and the number of transfers
between accounts for each fraudulent payment, the perpetrator required a
degree of planning and fore thought to select council tax accounts,
process transfers between accounts and make payments.
Page 168 of 396

Page 169

Strengthening the council’s internal controls | 15
Exhibit 5
Council’s existing controls for processing refunds
Level Processing
Tier 1:
Refunds up to £500
• Council tax team members have the authority to input bank
details and process refunds to customers.
Tier 2:
Refunds between
£500 and £3,000
• Council tax team leaders, to carry out their role, have the
authority and system access to input bank details and process
refunds to customers without any scrutiny.
• Council tax team members pass the refund to a team leader for
checking and processing by the team leader on Capita One
Revenues & Benefits.
• Refunds created by council tax team leaders must be passed
directly to another team leader for checking and processing.
Tier 3:
Refunds over £3,000
• Council Tax and Recovery Manager, to carry out their role, has
the authority and system access to input bank details and
process refunds to customers without any scrutiny.
• Refunds created by council tax team members are passed to
team leaders for checking and the refund is then passed to
Council Tax and Recovery Manager for processing.
• Refunds created by a council tax team leader, are passed
directly to Council Tax and Recovery Manager for checking and
processing by the Council Tax and Recovery Manager.
Source: Aberdeen City Council reports
21. Managing accounts in credit did not feature as a high priority within the
council’s internal control systems. The amounts involved were small and,
initially, any refund depended on a taxpayer seeking a request. In addition,
once automatic direct debit payments were available, it was expected
many overpayment issues would be resolved.
22. Controls were in place in the form of authority limits. There were no
exception reports for this area of work and reports of refunds paid were
not routinely run or reviewed. Had this been the case, the embezzlement
would have been identified much earlier. An average council tax bill is
currently around £2,000 to £3,000 per annum and while an occasional
refund of a whole year’s council tax might arise, several refunds of this
scale every month would have attracted attention.
23. At 31 March 2024, there were only 105 accounts (Exhibit 6, page 16)
with credit balances over £1,000. By comparison, there were 16 fraudulent
refunds in 2023/24 with an average value of £2,932 (Exhibit 4).
Page 169 of 396

Page 170

Strengthening the council’s internal controls | 16
Exhibit 6
Council tax credit balances at 31 March 2024
Year Number %
£0 to £500 6,243 95
£500 to £1,000 245 4
£1,000 to £1,500 49 1
£1,500 to £2,000 27 –
£2,000 to £2,500 12 –
£2,500 plus 17 –
Total 6,593 100
Source: Aberdeen City Council reports
The internal control environment
24. In the public sector, there are recognised fraud risks, including those
relating to tax receipts, welfare benefits, grants and other claims made by
individuals and organisations. Bodies are responsible for implementing
effective systems of internal control, including internal audit, which
safeguard public assets and prevent and detect fraud, error and
irregularities, bribery and corruption.
25. Auditors aim to obtain reasonable assurance about whether the
financial statements as a whole are free from material misstatement,
whether due to fraud or error, and to issue an auditor’s report that includes
their opinion. Reasonable assurance is a high level of assurance but is not
a guarantee that an audit conducted in accordance with ISAs (UK) will
always detect a material misstatement when it exists.
26. Irregularities that result from fraud are inherently more difficult to
detect than irregularities that result from error as fraud may involve
collusion, intentional omissions, misrepresentations, or the override of
internal control. The capability of the audit to detect fraud and other
irregularities depends on factors such as the skilfulness of the perpetrator,
the frequency and extent of manipulation, the degree of collusion involved,
the relative size of individual amounts manipulated, and the seniority of
those individuals involved.
27. As part of the financial statements audit, the external auditor regards
council tax income as a material financial system and considers the key
controls in place. This focuses on the key aspects of the income accounts
including billing (including discounts and exemptions), collection and the
adequacy of the provision for non-collection to ensure that council tax
income is not materially misstated.
Page 170 of 396

Page 171

Strengthening the council’s internal controls | 17
28. When planning audit assignments, internal audit consider:
• the significant risks to the activity’s objectives, resources and
operations and the means by which the potential impact of risk is
kept to an acceptable level
• the adequacy and effectiveness of the activity’s governance, risk
management and control processes compared to a relevant
framework or model.
29. Internal audit routinely undertake audits of council tax administration.
The scope might focus on one aspect of administration or take a wider
view across the service. The last audit which included some consideration
of refunds was a review of council tax billing carried out in 2016. This
included samples of reliefs, payments and refunds. In respect of refunds,
the auditor reported that the sample was correctly calculated, supported
by appropriate documentation, authorised and refund payments had been
made to the correct bank accounts.
Improvements in the council’s internal controls
30. The council was quick to respond once the suspected fraudulent activity
was brought to officers’ attention. Internal counter-fraud officers undertook initial
enquiries before referring the matter to Police Scotland. Disciplinary
proceedings were quickly enacted. This resulted in the individual pleading guilty
to the embezzlement of funds and receiving a prison sentence.
31. The Chief Officer – Finance undertook a review of the systems and
processes operating around accounts in credit and refunds and provided
the Audit, Risk and Scrutiny Committee with an update in February 2024.
Immediate action was taken in October 2023 to strengthen segregation of
duties between processing and approving refunds and inputting bank
details.
32. An improvement plan was prepared by the service covering council tax
refunds and wider banking and supplier payment controls. Ten actions were
identified for which prompt steps were taken to implement five and the
remainder, with one exception due in July 2024, were prioritised for
implementation by December 2024. Given the passage of time since the fraud
was identified, the inclusion of interim milestones would have been helpful to
maintain focus and demonstrate progress.
33. The council’s officer-led risk board monitored progress with the actions
between March and October 2024. This responsibility has now passed to a Task
and Finish Group which has recently been convened to oversee completion of
the actions and provide assurance to the corporate management team.
Membership includes a range of finance, council tax and governance officers.
34. In July 2024, the Chief Officer – Finance sought assurance that key
control weaknesses had been addressed and engaged internal audit to
assess progress with implementation and offer further considerations to
Page 171 of 396

Page 172

Strengthening the council’s internal controls | 18
strengthen the framework. Work has been undertaken to address the
improvement actions identified by the service. In some cases, the
associated controls have yet to be embedded in a way that fully addresses
the issues identified. The chief internal auditor also identified a number of
additional system-wide risks and made further recommendations. 
35. In the chief internal auditor’s view, most actions were therefore only
partially complete with some expected to take longer than the target dates
previously reported by the service. The Task and Finish Group have
recently taken ownership of the improvement plan, including the additional
recommendations, and now need to increase momentum by prioritising
the additional recommendations and allocating clear responsibilities and
timescales for action.
Lessons for others
36. While the fraud was complex, weaknesses in the council's internal
controls facilitated the fraud and meant that it was not detected for some
time. In particular, the council had controls in place but there was no
scrutiny to ensure the effective operation of these controls. All councils
should consider whether the following fundamental internal controls are
operating effectively:
• Segregation of duties: ensuring access to systems are restricted
to appropriate levels (to negate the possibility of individuals
processing transactions all the way through the payments process).
• Reconciliations: ensuring feeder systems are effectively
reconciled to other systems (eg, general ledger); using third-party
information (suppliers’ statements) and reconciling with payment
systems.
• System documentation: system documentation should be
maintained which details key controls to be carried out by staff to
prevent fraud or error.
• Monitoring: scrutiny monitoring should be at a level that would
allow managers to identify anomalous payments at an early stage.
• Counter-fraud arrangements: refresh and promote the counter-
fraud policy with staff.
37. The processes around the annual governance statement also provide
a useful opportunity for councils to take stock of the key controls and
processes in place and whether self-assessment processes are sufficient
to provide elected members and officers with the required assurances.
Page 172 of 396

Page 173

The council’s response to taxpayers | 19
The council’s response to
taxpayers
38. The council is acutely aware that accounts in credit balances belong to
taxpayers and that the funds are held for safekeeping by the council. The
priority for the council has therefore been to make sure that the individual
council tax accounts affected were corrected and credit balances
reinstated.
39. Since February 2024, there has been ongoing work to identify all
accounts affected by the embezzlement. So far, around 1,400 accounts
(25 per cent) have been identified from the estimated 5,700 accounts
affected.
40. At this stage, no attempt has been made to contact taxpayers and no
refunds have been made. There are practical challenges of providing a
refund to taxpayers often years after the event, who had not already been
located at the time.
41. The council intends to try to establish contact with the relevant
taxpayers and where this is not possible, revised procedures for managing
accounts in credit will be applied. When there is no response to follow up
correspondence, a credit balance will be cleared by writing the amount
back in the council tax system. Should a taxpayer ever identify themselves
to the council in the future however, the money remains available for
repayment.
42. Provision was made in the 2023/24 annual accounts for the loss of
funds. The council expects to recover the loss through a combination of
cash from the pension of the perpetrator and a claim on the council’s
insurance.
Page 173 of 396

Page 174

Conclusions | 20
Conclusions
43. There were failures in controls within the council that allowed this fraud
to continue over a prolonged period. In particular, a lack of segregation of
duties and monitoring in relation to council tax refunds allowed the
perpetrator to transfer balances between council tax accounts.
44. Controls exist to safeguard both the employees and the employer.
In this case, failure to implement controls enabled an abuse of authority
which, when combined with a detailed knowledge of council tax
administration, provided the opportunity to withdraw funds inappropriately.
45. In totality, the scale of the fraud was significant. There was no major
impact on the individual financial statements from 2006/07 to 2023/24 and
the payments did not represent a material misstatement in any given year.
46. The amounts were taken from balances held by the council on behalf
of taxpayers who had made overpayments on their council tax accounts.
The council recognises its safeguarding role, and to date, has identified
around 25 per cent of the accounts affected. No attempt has yet been
made to contact taxpayers and make refunds.
47. Once an irregular transaction was identified in September 2023, the
council acted quickly to deal with the individual, the situation and take
corrective action. Key controls such as segregation of duties were
promptly revised and an improvement plan of prioritised actions was
developed. Good progress has also been made with processes to recover
lost funds.
48. Work was undertaken to address the improvement actions identified
by the service but some of the associated controls have yet to be
embedded in a way that fully addresses the issues identified. Management
requested internal audit review progress being made against the
improvement plan and consider controls to further strengthen the
framework around accounts in credit and refunds. A number of additional
system-wide risks were duly identified and further recommendations
were made.
49. In the chief internal auditor’s view, most actions were therefore only
partially complete with some expected to take longer than the target dates
previously reported by the service. The Task and Finish Group have
recently taken ownership of the improvement plan including the additional
recommendations and now need to increase momentum.
Page 174 of 396

Page 175

Conclusions | 21
50. The council generally has a sound system of internal controls in place
but should take the opportunity to undertake a risk assessment of its wider
internal control and counter-fraud arrangements and use the annual
governance statement process to review its self-assessment
arrangements across services.
Page 175 of 396

Page 176

The 2023/24 audit of Aberdeen
City Council
Council tax refunds – a significant fraud
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot
ISBN: 978 1 915839 59 6
AS.5.0
Page 176 of 396

Page 177

Audit Committee
Monday 16 June 2025
Item No 5.7 
Internal Audit Annual Assurance Report 2024/25 
Report by Chief Internal Auditor 
Report for Decision 
1 Recommendations 
The Audit Committee is asked to:
a) Consider the Internal Audit Annual Assurance Report 2024/25 (Appendix 1),
and assurances contained therein; and
b) Provide any commentary thereon, including any further actions required by
Management. 
2 Purpose of Report/Executive Summary 
The purpose of this report is to present to the Audit Committee the Internal
Audit Annual Assurance Report for the year to 31 March 2025 which includes
the Chief Internal Auditor’s independent assurance opinion on the adequacy of
Midlothian Council's overall control environment. 
The Public Sector Internal Audit Standards (PSIAS) require that the chief audit
executive, the Council’s Chief Internal Auditor, provides an annual internal
audit opinion and report on the adequacy and effectiveness of the Council’s
governance, risk management and internal controls to support the preparation
of the Annual Governance Statement. This is in support of the overall
governance arrangements of the Council, as set out in the Local Code of
Corporate Governance. 
To meet the requirements of the PSIAS, the Internal Audit Annual
Assurance Report 2024/25 (Appendix 1) includes the Chief Internal Auditor’s
annual opinion, provides details of the Internal Audit activity and performance
during the year to fulfil its role, and summarises the outcomes of assessments
of the Internal Audit service against the PSIAS. 
Date 1 June 2025 
Report Contact:
Duncan Stainbank
duncan.stainbank@midlothian.gov.uk
Page 177 of 396

Page 178

3 Background 
3.1 The Local Authority Accounts (Scotland) Regulations 2014 that came into
force on 10 October 2014 require a local authority to operate a professional
and objective internal auditing service. This service must be provided in
accordance with recognised standards and practices in relation to internal
auditing. Recognised standards and practices are those set out in the Public
Sector Internal Audit Standards: Applying the IIA International Standards to
the UK Public Sector (PSIAS). The standards require internal audit to have
suitable operational independence from the organisation. 
3.2 The Public Sector Internal Audit Standards (PSIAS) 2017 require that:
“The chief audit executive [MLC’s Chief Internal Auditor] must deliver an
annual internal audit opinion and report that can be used by the organisation
to inform its governance statement. 
The annual internal audit opinion must conclude on the overall adequacy and
effectiveness of the organisation’s framework of governance, risk
management and control.
The annual report must incorporate:
• the opinion;
• a summary of the work that supports the opinion; and
• a statement on conformance with the Public Sector Internal Audit
Standards and the results of the quality assurance and improvement
programme.” 
3.3 The Terms of Reference of the Midlothian Council Audit Committee states:
• The Audit Committee is a key component of Midlothian Council’s
corporate governance. It provides an independent and high-level focus
on the audit, assurance and reporting arrangements that underpin good
governance and financial standards.
• The purpose of the Audit Committee is to provide independent
assurance to Elected Members of the adequacy of the risk
management framework and the internal control environment. It
provides independent review of Midlothian Council’s governance, risk
management and control frameworks, and overseas the financial
reporting and annual governance processes. It oversees Internal and
External Audit, helping to ensure efficient and effective assurance
arrangements are in place. 
4.        Internal Audit Annual Assurance Report 2024/25 
4.1 The Internal Audit Annual Assurance Report 2024/25 (Appendix 1) includes
the Chief Internal Auditor’s independent and objective opinion regarding the
adequacy and effectiveness of internal control within Midlothian Council to fulfil
the statutory role of Internal Audit, provides details of the Internal Audit activity
that supports the opinion and of the performance during the year, and
summarises the outcomes of assessments of the Internal Audit service against
the Public Sector Internal Audit Standards (PSIAS). 
4.2 The Internal Audit Annual Assurance Report 2024/25 provides assurances in
relation to the Council’s corporate governance framework that is a key
component in underpinning delivery of the corporate priorities within the Single
Midlothian Plan and will be used to inform the Annual Governance Statement
2024/25. 
Page 178 of 396

Page 179

5 Report Implications (Resource, Digital, Risk and Equalities) 
5.1 Resource 
The Internal Audit function reports directly to the Chief Executive
(operationally) and the Audit Committee (functionally). The staff resource
during 2024/25 was 3.22 FTE, comprising Chief Internal Auditor (0.5 FTE –
shared with East Lothian Council; Principal Internal Auditor (0.72 FTE), and
Internal Auditor (2.0 FTE). Each member of the Internal Audit team has a
professional internal audit or accountancy qualification, and has suitable
experience, knowledge, skills and competencies (such as the Code of Ethics
set out in PSIAS and the Seven Principles of Public Life) needed to perform
the plan. 
There is a commitment by Midlothian Council to provide resource to the
Midlothian Health and Social Care Integration Joint Board (MIJB) as part of the
Council’s commitment to partnership working. Separate Plans and Reports are
presented to the MIJB Audit and Risk Committee. The audit opinion based on
work undertaken during the year to meet that commitment will be presented in
a separate Annual Assurance Report to the MIJB Audit and Risk Committee
and MIJB to fulfil that role. 
Budget monitoring of the Service is discussed by the Chief Internal Auditor
and the Principal Internal Auditor with the Financial Services Manager on a
quarterly basis to address any budgetary pressures. 
5.2 Digital 
There are no digital implications arising from this report. 
5.3 Risk 
The PSIAS require Internal Audit to evaluate the effectiveness of the Council’s
Risk Management arrangements and contribute to improvements in the
process. The Chief Internal Auditor’s opinion on the systems of internal
control, risk management and governance is set out within section 2 of the
Internal Audit Annual Assurance Report 2024/25 (Appendix 1). 
Internal Audit provides assurance to the Corporate Management Team and
the Audit Committee on the adequacy and effectiveness of internal controls
and governance within the Council, including risk management, and to
highlight good practice and recommend improvements. Key components of
the audit planning process include a clear understanding of the Council’s
functions, associated risks, and range and breadth of audit areas for inclusion
within the Annual Plan. 
It is anticipated that improvements in the management and mitigation of risks
will arise as a direct result of Management implementing the Internal Audit
recommendations made during the year or outstanding from previous years. 
Delivery of the Internal Audit services in conformance with the PSIAS will
enable the Council to meet the requirements of the Local Authority Accounts
(Scotland) Regulations 2014 to consider the findings of assessments as part
of the consideration of the system of internal control required by regulation 5. 
Page 179 of 396

Page 180

5.4 Ensuring Equalities 
This report does not relate to a new or revised policy, service or budget
change, which affects people (the public or employees), so an Integrated
Impact Assessment (IIA) is not an applicable consideration. 
The Internal Audit work is carried out in accordance with the appropriate
legislation and professional standards. This includes compliance by those
within the Internal Audit function with the Code of Ethics, set out in the PSIAS,
and the Seven Principles of Public Life (the Nolan Principles), set out in the
Employees’ Code of Conduct. This is appropriate for the profession of Internal
Audit, founded as it is on the trust placed in its independent and objective
assurance about risk management, internal control and governance. 
5.5 Additional Report Implications (See Appendix A) 
Page 180 of 396

Page 181

APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Although this report does not relate directly to the key priorities within the
Single Midlothian Plan to which Midlothian Council and its Community
Planning Partners have made a commitment (Reducing the gap in learning
outcomes; Reducing the gap in health outcomes; Reducing the gap in
economic circumstances; and Reducing the impact of climate change), by
providing an independent and objective annual assessment of the adequacy
of the entire control environment, Internal Audit supports the Council to
achieve its objectives. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working  
Hub and Spoke  
Modern  
Sustainable  
Transformational  
Preventative  
Asset-based  
Continuous Improvement  
One size fits one 
None of the above 
Midlothian Council is committed to creating a great place to grow supported by
the 9 drivers for change. Implementing the 9 drivers for change in practice is
applicable to the Council’s Internal Audit service provision to assist the Council
in achieving its objectives. 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you  
Preventative and Sustainable  
Efficient and Modern  
Innovative and Ambitious 
A.4 Delivering Best Value 
The definition of Internal Auditing within the Public Sector Internal Audit
Standards (PSIAS) is “Internal auditing is an independent, objective assurance
and consulting activity designed to add value and improve an organisation’s
operations. It helps an organisation accomplish its objectives by bringing a
systematic, disciplined approach to evaluate and improve the effectiveness of
risk management, control and governance processes.” 
Implementation by Management of the actions associated with Internal Audit
recommendations, that are designed to improve internal control and
governance arrangements and management of risks, underpins the Council’s Page 181 of 396

Page 182

own continuous improvement arrangements to enhance its effectiveness, thus
supporting the delivery of the Council’s best value duties. 
A.5 Involving Communities and Other Stakeholders 
Internal Audit’s purpose is to support the Council in its activities designed to
achieve its declared objectives for the benefit of Midlothian’s communities and
other stakeholders. 
The Chief Internal Auditor is accountable to the Audit Committee which, in
fulfilling its governance role, acts as a bridge between the Council and other
stakeholders. 
This report has been presented to the Corporate Management Team to outline
the key messages of assurance and areas of improvement. Senior
Management have been advised to take into account the findings from Internal
Audit work during the year when completing their internal control and
governance assurance statements as part of the annual self-evaluation and
assurance process for the Council’s Annual Governance Statement 2024/25. 
A.6 Impact on Performance and Outcomes 
The Findings and Recommendations from Internal Audit work during the year,
which are designed to maintain and / or enhance internal controls, governance
arrangements and risk management, assists the Council in improving its
performance and outcomes. 
A.7 Adopting a Preventative Approach 
Having robust internal controls, governance arrangements and risk
management in place contributes to safeguarding the Council’s resources for
delivery of services, as part of protecting the public purse. Internal Audit
assurance and consultancy activity is designed to improve operations and
assist the Council in accomplishing its objectives. 
A.8 Supporting Sustainable Development 
This report does not relate directly to supporting sustainable development.
Good governance, including the provision of an Internal Audit service, is
important to enable Midlothian Council to achieve its objectives.  
Page 182 of 396

Page 183

APPENDIX 1
Chief Internal Auditor’s Annual Assurance Report and Opinion 2024/25 for
Midlothian Council
1 Introduction
1.1 It is Management’s responsibility to design and maintain proper risk management,
governance and internal control processes and systems to ensure probity in systems
and operations, including the prevention, detection and resolution of fraud and
irregularities. Management is also responsible for checking that the arrangements and
controls are operating effectively. These are known as the first and second lines which
are not fixed but evolve as the Council changes.
1.2 Internal Audit, as the third line, is an independent appraisal function established for
the review of the internal control system as a service to Midlothian Council. It
objectively examines, evaluates and reports on the adequacy of internal control as a
contribution to the proper, economic, efficient and effective use of resources and the
management of risk.
1.3 The Internal Audit activity adds value to the organisation (and its stakeholders) when
it considers strategies, objectives, and risks; strives to offer ways to enhance
governance, risk management and control processes; and objectively provides
relevant assurance.
1.4 The Objectives of Internal Audit are set out in its Charter:
“Internal Audit’s responsibility is to report to Midlothian Council on its assessment
of the adequacy of the entire control environment, through the Corporate
Management Team (‘senior management’) and the Audit Committee (the ‘board’
for the purposes of Internal Audit activity).
Internal Audit adds value to the organisation (and its stakeholders) by enhancing
governance, risk management and control processes and objectively providing
relevant assurance.
As part of Midlothian Council’s system of corporate governance, Internal Audit’s
purpose is to support the Council in its activities designed to achieve its declared
objectives”
1.5 The Public Sector Internal Audit Standards (PSIAS) (2017) requires that:
“The chief audit executive must deliver an annual internal audit opinion and report
that can be used by the organisation to inform its governance statement.
The annual internal audit opinion must conclude on the overall adequacy and
effectiveness of the organisation’s framework of governance, risk management and
control.
The annual report must incorporate:
• the opinion;
• a summary of the work that supports the opinion; and
• a statement on conformance with the Public Sector Internal Audit Standards and
the results of the quality assurance and improvement programme.”
1.6 This Annual Assurance Report provides the annual internal audit opinion to fulfil the
statutory role of Internal Audit and summarises the work carried out by Internal Audit
during the year to 31 March 2025 that underpins the opinion in accordance with the
Internal Audit Charter, Strategy and Annual Plan 2024/25. The report also states the
outcomes of assessments of the Internal Audit service against the PSIAS.
Page 183 of 396

Page 184

2 Opinion on the systems of Internal Control, Risk Management and Governance
2.1 My opinion is that, based on our reviews, risk assessments and knowledge, the systems
of internal control, risk management and governance are generally adequate. There is
more work to be done with the implementation of Internal Audit recommendations
made in previous years associated with the strategic governance arrangements that
underpin procurement, contract management, and risk management. Internal Audit
Reviews throughout the year have provided reasonable assurance against the majority
of the areas reviewed, however 2 limited assurance reviews have been completed
being Business Continuity and IT Asset Management, with only two High rated
recommendations being raised both in relation to Business Continuity.  Two further
reviews reported limited assurance in at least one area, being: Absence Management 
and Revenue Financial Budget Monitoring. Recommendations made are being
implemented to improve the control environment in these areas. 
2.2 The Council’s Local Code of Corporate Governance, updated and approved by Council
in March 2021, complies with the CIPFA/SOLACE Framework ‘Delivering Good
Governance in Local Government’ (2016). This ensures that this key document
continues to be relevant and complete to reflect the appropriate framework for
effective governance of the Council’s affairs and facilitate the exercise of its functions
to deliver best value.
2.3 The Financial Regulations (approved June 2022), and associated policies, procedures
and guidelines have been reviewed, updated and developed, as appropriate, to reflect
changes arising from organisation structures and systems, and address
recommendations arising from Internal Audit findings. 
2.4 The Internal Audit review of Absence Management September 2024 concluded: 
substantial assurance for policy and procedures. Assurance was limited for the
reporting and monitoring of sickness absence, training of managers and absence
management documentation. Additional training is being put in place for managers to
ensure compliance with the procedures in place and improvements in monitoring and
documents storage are being developed to improve these processes. 
2.5 The Internal Audit review of Risk Management March 2024 concluded:  substantial
assurance in relation to the Council’s Risk Management Policy and application of the
policy at a strategic level.  Assurance was limited over the application of the Risk
Management Policy at the service (operational) level, the provision of training and
guidance, and service level reporting and monitoring arrangements.  In order for
management of risks at the strategic level to be fully effective, service risk registers
should be up-to-date. It was found that processes have not been established to
formally report on risks to DMTs and escalate as required, there is limited risk
management resource in place to support the Council, limited training and guidance is
in place for risk management. It is noted that whilst improvements in training guidance
and processes have been noted during the year and that some services have utilised
consultancy resource, the majority of services do not have updated risk registers at a
service level - progress in this area is not being regularly reported to the Audit
Committee. 
2.6 The Procurement function has continued to have resourcing difficulties throughout the
year, a Procurement Manager is now in place. Work has commenced on updating and
implementing contracts in a number of key areas across the Council. Counter Fraud
and Council transformation blueprint work has identified that there are further savings
that can be made across the Council with the implementation of enhanced purchasing,
procurement and contract management controls.  Resources are being identified
within the Council Transformation blueprint work to improve these processes. 
Page 184 of 396

Page 185

2.7 Further improvements in internal control, risk management and governance have
been agreed by Management, as highlighted in Internal Audit reports and through
recommendations made during the year or outstanding from previous years. It is
important that Management continue to monitor and oversee the implementation of
Internal Audit recommendations on a regular basis to demonstrate continuous
improvement and to address identified risks.
3 Internal Audit Annual Plan 2024/25 Delivery
3.1 The Internal Audit team continue to work from home, facilitated by the use of MS
Teams and access to network drives and business applications. The team attend
Council premises as necessary to obtain information or assurances as required. There
has been no impairment to the independence or objectivity of the Internal Audit
function arising from deployment to non-audit work or from consulting work during
the year.
3.2 The revisions to the Internal Audit Annual Plan 2024/25 were approved by the Audit
Committee. The following Audits have been removed from the 2024/25 Audit Plan in
February 2025:
• Education Additional Support needs was replaced with assurance work on the
Renfrewshire Council Bowles report comparing current practice within the Council
with that external review of Renfrewshire Council. This work was reported to the
September 2024 Audit Committee.      
• School Funds had issues noted in the Attainment Scotland Funding review
reported in November 2024, resulting in further work. More detailed work not
being required until the end of 2025/26;
• Purchase to Pay has been delayed until 2025/26 as a result of systems upgrades,
resource being diverted to the assurance review of Council Tax refunds; 
• Vehicle Maintenance and Fleet management had aspects reviewed in 2024/25,
with a full review to be completed in 2025/26;  and 
• Property assets and property strategy was replaced with Education Construction
Governance (reported to the June 2025 Audit Committee) and will be completed
in 2025/26. 
3.3 A review of Fostering and Adoption is currently ongoing and will be reported to the
September Audit Committee.      
3.4 The range and breadth of Internal Audit work, which amounts to 86% completion of
the revised Internal Audit Plan, performed during the year, which is listed below, is
sufficient to inform the Internal Audit assurance opinion. 
Risk Based Audits & Assurance Exercises
3.5 To provide assurance on the internal controls, risk management and governance
arrangements associated with strategic and operational frameworks in place for the
efficient and effective delivery of objectives, reviews included (date reported to Audit
Committee): 
• Annual Assessment of Internal Controls and Governance (Continuous audit
approach to follow-up on implementation of actions for Areas of Improvement set
out in the Annual Governance Statement 2024/25. Annual evaluation against the
Local Code of Corporate Governance to determine whether the arrangements are
operating as described. Prepare this Annual Assurance Report forming the
statutory opinion on the adequacy of the Council’s arrangements for risk
management, governance and internal control.) – June 2025.
Page 185 of 396

Page 186

• Absence Management (Reviewed the operation of the systems in place for
monitoring of absence to ensure maintenance of staff wellbeing in new working
environments and capacity for service delivery.). –  September 2024.
• Bowles Report – School Capacity Assurance Review (Considered the failings
identified in the Bowles report, together with the associated recommendations
and measured them against the governance, risk and control framework within
Midlothian Council.) – September 2024.
• Midlothian Energy (Reviewed the governance structures, ensure monitoring
regimes are in place and operating to ensure long term delivery of outcomes for
the Council and control over financial and operational risk). –  November 2024.
• Attainment Scotland Funding (Reviewed the governance and internal control
arrangements in place to support the effective utilisation of Attainment Scotland
Funding (Pupil Equity, Strategic Equity and Care Experienced Children and Young
People Funding) in line with local Council procedures and the respective National
Operational Guidance for each type of funding.)  – November 2024.
• Business Continuity (Reviewed the Business Continuity processes in place within
the Council ensuring that they cover all key risks, including cybersecurity incidents,
power/energy losses etc.) – February 2025.
• SEEMIS (Reviewed the control process in place to ensure accurate recording and
use of management information within the SEEMIS System.) – June 2025.
• Education Construction Governance (Established if the governance, control, and
monitoring processes in relation to two significant capital projects were operating
effectively and issues were raised through the Council’s governance processes in a
timely manner when appropriate.) – June 2025.
• IT Asset Management (Reviewed the processes in place to ensure that IT assets are
recorded, managed and maintained in an effective and efficient manner.) June
2025. 
• Revenue Financial Budget Monitoring (Review the processes in place to ensure that
services and service management are effectively monitoring and managing
budgets throughout the financial year and identifying and escalating significant
issues through finance and governance structures on a timely basis.) – June 2025.
• Commercial Lease Reviews – (Complete an audit review of requested Commercial
Lease issues at the request of the Audit Committee.) – March 2024.
• Destination Hillend Water Pipe Delays (Review of the revised project processes
following the Water Pipe Delays for this project.) – June 24 
Consultancy
3.6 In its ‘critical friend’ role, Internal Audit provided an independent view and challenge
at various forums including: Capital Planning and Asset Management Board, Learning
Estate Board, Information Management Group. 
Other Audit Work
3.7 During the year, resources were deployed in undertaking the following other audit
work in support of the Internal Audit function meeting its wider objectives as set out
in the Internal Audit Charter:
• PSIAS External Quality assurance review was completed by East Renfrewshire
Council following a self-assessment and is being reported to the June 2025 Audit
Committee.  
Page 186 of 396

Page 187

• MLC Audit Committee Self-Assessment (Provided assistance to the Chair in
undertaking a self-assessment of the Audit Committee against the CIPFA best
practice guidance leading to a report to the Audit Committee in September 2024).
• MLC Recommendation Follow-Up Reviews (Undertook two reviews. The first
included a sample check of Audit Recommendations which are flagged as closed,
to check that they have been effectively implemented and to ensure that the new
controls had the desired effect on improving internal controls, risk management
and governance; and the second assessed performance against closing Audit
Recommendations by the agreed due date).
• Help Desk Enquiry System (Provided guidance and advice on request to
Management and Staff on internal controls and governance).
• MLC Administration of Audit Scotland Reports (Monitored publication of Audit
Scotland reports and co-ordinated submission by Management of Audit Scotland
Reports to the Audit Committee or other Committee as relevant).
• Risk Management and Integrity Groups (Attended the forums and provided
support in the form of relevant Internal Audit updates and advice to the Groups to
fulfil their roles).
• MLC Boards / Committees (Prepared for and attended Audit Committee meetings
and other Boards/Committees as relevant).
• MLC Audit Planning for 2025/26 (Reviewed and updated the Internal Audit Charter
and Internal Audit Strategy, preparing for the implementation of GIAS. Reviewed
and updated the Audit Universe to develop and consult on the proposed coverage
within the Internal Audit Annual Plan for 2025/26). 
Non MLC Work
3.8 The MLC Internal Audit team has carried out assurance work during the year for the
Midlothian Integration Joint Board (MIJB) based on a plan approved by the MIJB Audit
and Risk Committee in March 2024. An annual assurance report, including audit
opinion on the adequacy of the MIJB’s arrangements for risk management, governance
and control of the delegated resources, has been presented to the MIJB Audit and Risk
Committee. 
4 Public Sector Internal Audit Standards and Quality Assurance & Improvement Plan
4.1 The professional standards as set out in Public Sector Internal Audit Standards (PSIAS)
effective 1 April 2013 (updated 2017) include:
➢ Definition of Internal Auditing;
➢ Code of Ethics;
➢ Attribute Standards (Purpose, Authority and Responsibility; Independence and
Objectivity; Proficiency and Due Professional Care; Quality Assurance and
Improvement Programme);
➢ Performance Standards (Managing the Internal Audit Activity; Nature of Work;
Engagement Planning; Performing the Engagement; Communicating Results;
Monitoring Progress; Communicating the Acceptance of Risks).
4.2 The annual self-assessment 2024/25 of Internal Audit practices against the Standards,
as required by the PSIAS, was carried out in June 2024 taking into account the progress
with implementation of improvement actions arising from the previous year’s self-
assessment, as set out in the Quality Assurance and Improvement Plan (QAIP).This has
been assessed in an external assessment by East Renfrewshire Council which is being
reported to the June 2025 Audit Committee as required on a 5 year basis by PSIAS.  Page 187 of 396

Page 188

4.3 The 2024/25 External Quality Assessment (EQA) completed under the “EQA Peer
Review Framework” was developed by the Scottish Local Authorities Chief Internal
Auditors Group (SLACIAG). This EQA provided an overall conclusion of ‘Generally
Conforms’ with the assessment of fully conforming with 8 of the standards and
generally conforming with 6 of the standards the following recommendations have
been made and will be progressed during 2025/26. 
Recommendation  Management Response 
When the Audit Charter is next reviewed it
should include:
• An expanded section definitively addressing
the Internal Audit role in combatting fraud,
the role and status of the fraud team,
signposting to the counter fraud and anti-
corruption policies and the arrangements for
fraud to be notified to the relevant
officer/team.
• A definition of the nature of assurance
services
• The roles and responsibilities of statutory
officers in relation to internal audit.
Agreed these will be added when the Audit
Charter is reviewed in March 2026. The current
charter was based on the model charter for the
new GIAS standards as provided by the
Chartered Institute for Internal Audit and will be
updated to include these additional items. 
An appropriate methodology to facilitate and
document service feedback should be
developed and used to inform ongoing service
delivery.
Agreed a document has been developed in
assessing the working papers as part of the
implementation of GIAS and in accordance with
the approved Quality Assurance Plan in place
and will be utilised for audits in the 2025/26
financial year. 
A performance measurement methodology
should be developed to evaluate the internal
audit function’s performance against its
objectives.
Agreed, a review will be undertaken to establish
appropriate KPIs in accordance with the GIAS
guidance and in benchmarking with other Local
Authority audit teams to attempt to find
meaningful targets. These will be set and then
monitored from the next strategy and plan
approval. 
The Audit Strategy and specifically the planning
document for each individual audit should reflect
the annual plan link to the overall strategic
objectives of the Council.
The link to strategy will be included in the
individual audit planning document and reflected
more specifically in the Internal Audit Strategy
prior to its next approval at Audit Committee.   
The Chief Auditor should consider developing an
assurance mapping methodology to provide
clarity around the internal audit planning and
reporting approach
Agreed this was raised with Audit Committee
within the Charter paper in March 2025 and will
be progressed within the resources available a
methodology for developing being in place
during 2025/26. 
The Terms of Reference Document should be
expanded to include any exclusions from the
scope of the work and consideration of the
resources allocated, whilst recognising that the
choice of resources is limited.
Agreed the TOR was updated for GIAS
compliance to include this and will operate for
the 2025/26 audits as current resourcing really
only allows for a choice of one Auditor or the
other one we can record that choice in the TOR. 
The Chief Auditor should discuss the circulation
of audit reports with key stakeholders including
the Audit Committee to ascertain their preferred
format for example whether they want all reports
circulated in full or abridged versions with only
key points highlighted.
Agreed this will be included in the Audit
Committee self-evaluation for reporting to Audit
Committee in September 2025. 
Page 188 of 396

Page 189

4.4 As indicated to the Audit Committee in February 2025, the PSIAS have been replaced
by the Global Internal Audit Standards. A Self-assessment against these standards will
be presented to the Audit committee in March 2026. “EQA Peer Review Framework”
was developed by the Scottish Local Authorities Chief Internal Auditors Group
(SLACIAG) will again be used to complete an External Quality Assessment against these
revised standards in the future. 
Duncan Stainbank Bsc (Hons) CPFA
Chief Internal Auditor
4 June 2025 
Page 189 of 396

Page 190

Page 190 of 396

Page 191

Audit Committee
Monday 16 June 2025
Item No 5.8 
Counter Fraud Annual Report 2024/25 
Report by Chief Internal Auditor 
Report for Decision 
1 Recommendations 
The Audit Committee is asked to:
a) Consider the counter fraud work undertaken during the year to
31 March 2025 in support of the Council’s counter fraud policy
and strategy; and
b) Note the outcomes of the counter fraud activity 2024/25. 
2 Purpose of Report/Executive Summary 
The purpose of the report is to make the Audit Committee aware of the
Council’s counter fraud responsibilities and the activities of the Integrity
Group and Corporate Fraud team in liaison with other services over the
past year as part of the arrangements to tackling fraud at the Council. 
Having robust fraud prevention and investigation arrangements in place
contributes to safeguarding the Council’s resources for delivery of
services, as part of protecting the public purse. The Counter Fraud
Strategy approved by Council on 25 August 2020 includes: a focus on
enhancing fraud prevention and detection to improve Midlothian
Council’s resilience to the risk of fraud, theft, corruption and crime; and
ensure these are embedded preventative practices. 
Assurances about the effectiveness of the Council’s existing systems
and arrangements for tackling fraud can be taken from the outcomes
contained within this report. 
Date 6 May 2025 
Report Contact:
Duncan Stainbank  
duncan.stainbank@midlothian.gov.uk  
Page 191 of 396

Page 192

2
3 Background 
3.1 The size and nature of the Council’s services, as with other large
organisations, puts the Council at risk of loss due to fraud, theft,
corruption and crime.  Having robust fraud prevention and investigation
arrangements in place contributes to safeguarding the Council’s
resources for delivery of services, as part of protecting the public purse. 
3.2 The Council approved a Counter Fraud Policy Statement and Counter
Fraud Strategy in 2020 including: a focus on enhancing fraud
prevention and detection to improve the Council’s resilience to the risk
of fraud, theft, corruption and crime; and ensure these are embedded
preventative practices. 
3.3 The primary responsibility for the prevention, detection and
investigation of fraud rests with management.  The Integrity Group is
an officer forum which has representatives from across the Council’s
Services to support management to fulfil their responsibilities in tackling
fraud, and it is chaired by the Executive Director Place. The purpose of
the Integrity Group is to improve the Council’s resilience to fraud,
corruption, theft and crime (including cybercrime and money
laundering).  It oversees the policy framework, agrees and monitors the
implementation of improvement actions, raises awareness as a method
of prevention, and performs self-assessments against best practice. 
3.4 Part of the Audit Committee’s role is to review the assessment of fraud
risks and potential harm to the Council from fraud and corruption, and
to monitor the counter fraud strategy, actions and resources. 
3.5 Tackling fraud is not a one-off exercise; it is a continuous process
across all parts of the Council because the service delivery processes it
underpins are continuous. Tackling fraud is an integral part of good
governance within the Council and demonstrates effective financial
stewardship and strong public financial management. 
Page 192 of 396

Page 193

3
4 Counter Fraud Activity during 2024/25 
4.1 The Counter Fraud Annual Plan 2024/25, setting out Corporate Fraud
activity at a high level, was approved by the Audit Committee on 18
March 2024.  All elements of the Counter Fraud planned work were
carried out, relating to activity at a high level as follows:
a) Contract Management
b) Corporate Fraud Enquiries
c) National Fraud Initiative
d) Social Housing
e) Council Tax
f) Corporate Fraud Policy Framework
g) Fraud Risk Assessments
h) Fraud Awareness Training
i) Integrity Group 
4.2 As specialist investigators, the Corporate Fraud Officers have
conducted significant and comprehensive work in respect of Contract
Management, liaised with Scotland Excel and Police Scotland as
required, and recommended improvements to reduce risks. Work has
identified areas of control concern in relation to end to end procurement
processes and contract management, within the Council and Scotland
Excel. Improvements are being implemented through improved
Procurement staffing and blueprint work to resolve these control
issues. 
4.3 The Corporate Fraud Team has dealt with 111 enquiries including 32
from the Midlothian Council website page “Report a possible crime,
fraud or similar concern” which is available to employees or the public
for whistleblowing purposes. Fraud Response Group meetings have
been held to share concerns and progress actions with relevant
Management. 
4.4 Midlothian Council continues to participate in the National Fraud
Initiative (NFI) which is a UK wide counter-fraud exercise led by the
Cabinet Office and Audit Scotland. It uses data analytic techniques to
compare information about individuals held by different public bodies,
and on different systems, to identify circumstances (data matches) that
might suggest the existence of fraud or error. The Principal Internal
Auditor acts as the Council’s Key Contact for NFI and the Corporate
Fraud Team has coordinated the submission of the required data sets
from various Council systems and responded to the data matches
received with input from relevant Services across the Council. 
4.5 The Corporate Fraud Team has received referrals from Housing
Officers during the year to investigate potential subletting or
abandonment of Council owned properties; 48 allegations of potential
tenancy fraud were investigated (see 5.2 for outcomes). 
4.6 The Corporate Fraud Team responded to 27 notifications of alleged
fraud associated with Council Tax Discounts and Exemptions during
the year to determine whether these discounts and exemptions are
claimed legitimately, including Council Tax Reduction Scheme (CTRS)
and Single Person Discount (SPD) (see 5.3 for outcomes).
Page 193 of 396

Page 194

4 
4.7 It is important that associated policies, procedures and guidelines
across the Council are regularly reviewed and updated, as appropriate,
to ensure that they keep pace with best practice in relation to fraud and
corruption prevention and detection. 
4.8 The Corporate Fraud Officers are members of the Scottish Local
Authority Investigators Group (SLAIG) and represent Midlothian
Council. They join SLAIG’s quarterly virtual meetings as a forum for
sharing best practice across Councils and the wider public sector, thus
ensuring their knowledge of emerging fraud risks and issues is up to
date. Any insights on fraud risk assessments are shared on a regular
basis with the Integrity Group. The Corporate Fraud Officers liaise
throughout the year with the Internal Audit Team to provide their view
on the potential fraud risk aspects of areas under review. 
4.9 The Integrity Group held 4 meetings during the year 2024/25 to
undertake its functions as set out in its Terms of Reference. The
Integrity Group is chaired by the Executive Director Place and has
representatives from HR, Finance, Legal, IT, Procurement, Internal
Audit and Corporate Fraud.                                                                                                                                                 
5 Outcomes of Counter Fraud Activity 2024/25 
5.1 It has been calculated, using Audit Scotland guidance (where relevant
for nominal values), that as a result of counter fraud activity a total
savings value of £906,713 has been identified during 2024/25. The
types of referrals and the outcomes are summarised in the table in
Appendix 1, with details provided below. 
5.2 As a result of the collaboration between Housing Officers and the
Corporate Fraud Team, 11 of the 48 allegations of potential tenancy
fraud that were investigated resulted in the return of a property to the
Council’s housing stock, which were subsequently made available to
those in genuine need of social housing. For each of the properties
identified, the calculation of savings per property (based on NFI
Estimates Outcomes Methodologies) is £78,300, thus resulting in a
saving of £861,300. However, the key benefit is the ability to provide
more homes to those in genuine need of social housing. 
5.3 11 referrals of internal fraud allegations have been made during the
year - 2 of these have resulted in funds being returned to the Council
totalling £22,450. Recovery of a further £22,963 has been made as a
result of further action on 2 historic cases one of which remains
ongoing. 2 of the investigations undertaken remain in progress through
HR processes. 
5.4 Outcomes of the Council’s participation in the National Fraud Initiative
for 2022/23 resulted in a total saving of £162,387. These outcomes are
detailed in Appendix 2.   
5.5 In conclusion, the Corporate Fraud Team in collaboration with other
Services have been successful in delivering the range of activity set out
in the Counter Fraud Annual Plan 2024/25 to support the Council’s
Page 194 of 396

Page 195

5
objectives. Tackling fraud is an ongoing process as the Council’s
internal and external operating environment changes. 
6 Report Implications (Resource, Digital, Risk and Equalities) 
6.1 Resource 
The Integrity Group will support Management across the Council with
counter fraud management by: overseeing the review of the counter
fraud policy framework in line with best practice; highlighting emerging
fraud and corruption risks, threats, vulnerabilities; agreeing fraud and
corruption mitigation actions; raising awareness of bribery, fraud and
corruption in the Council as a method of prevention. 
The staff resource set out in the Counter Fraud Annual Plan 2024/25
relates to 2 Corporate Fraud Officers, plus some management and
supervision provided by the Principal Internal Auditor and the Chief
Internal Auditor. The Corporate Fraud Officers collaborate with other
managers and employees across the Council to carry out the activity
and support the Integrity Group. 
6.2 Digital 
None. 
6.3 Risk 
The size and nature of the Council’s services puts the Council at risk of
loss due to fraud, theft, corruption and crime. 
The Counter Fraud Policy sets out the roles and responsibilities for the
prevention, detection and investigation of fraud. The Counter Fraud
Strategy provides a shift in approach to focus on enhancing fraud
prevention and detection to improve Midlothian Council’s resilience to
the risk of fraud. Council service fraud risk register creation is now
taking place facilitated by the Counter Fraud team. The steer provided
by the Integrity Group and the work undertaken by the Corporate Fraud
Team during 2024/25 in collaboration with other services is aligned to
the Policy and Strategy. 
6.4 Ensuring Equalities 
An Integrated Impact Assessment (IIA) Form was completed prior to
the presentation of the revised Counter Fraud Policy and Strategy that
were approved by the Council on 25 August 2020. 
6.5 Additional Report Implications (See Appendix A) 
Page 195 of 396

Page 196

6
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Although this report does not relate directly to the key priorities within
the Single Midlothian Plan (Reducing the gap in economic
circumstances; Reducing the gap in learning outcomes; Reducing the
gap in health outcomes; and Reducing the impact of climate change)
by preventing and detecting fraud, additional resources might be
available to support the Council’s objectives. Any loss of funds due to
fraud, theft, corruption or crime might impact on the ability of Midlothian
Council to achieve its key priorities. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working  
Hub and Spoke  
Modern  
Sustainable  
Transformational  
Preventative  
Asset-based  
Continuous Improvement  
One size fits one 
None of the above 
Midlothian Council is committed to creating a great place to grow
supported by the 9 drivers for change. Implementing the 9 drivers for
change in practice is applicable to the Council’s arrangements for
tackling fraud as set out in the Counter Fraud Policy Statement and
Counter Fraud Strategy. The shift to the key drivers for change is an
intrinsic part of the proposed change in approach and culture for the
Council for tackling fraud and corruption. For example:
(a) The formal establishment of an Integrity Group with a Terms of
Reference (approved by the Audit Committee on 22 June 2020)
shifting to more holistic working in multi-disciplinary forums to
tackle fraud in a consistent and collaborative way across the
Council;
(b) A focus on enhancing fraud prevention and detection to improve
Midlothian Council’s resilience to the risk of fraud, theft, corruption,
and crime and ensure these are embedded preventative practices; 
(c) Applying the minimum standard within the CIPFA Code of Practice
on ‘Managing the Risk of Fraud and Corruption (2014)’ for counter
fraud policy, strategy and other practices, and adopting the CIPFA
Counter Fraud Maturity Model as a means of self-assessment
moving forward will enable continuous improvement to be
evaluated, managed and evidenced; and
(d) Use of a blend of toolkits such as fraud risk assessments and e-
learning packages that can be tailored to specific Services. 
Page 196 of 396

Page 197

7
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you  
Preventative and Sustainable  
Efficient and Modern  
Innovative and Ambitious 
A.4 Delivering Best Value 
Having robust fraud prevention and investigation arrangements in place
contributes to safeguarding the Council’s financial resources, for
delivery of services, as part of protecting the public purse. The Counter
Fraud Strategy (August 2020) states the Council will measure progress
against the CIPFA Counter Fraud Maturity Model as a self-assessment
approach to continuous improvement in order to be evaluated,
managed and evidenced to demonstrate best value in the use of
resources. 
A.5 Involving Communities and Other Stakeholders 
Ensuring awareness of the Whistleblowing facility to report areas of
concern is important in the approach to tackling fraud. The facility has
is being utilised by employees, those within communities or other
stakeholders. 
A.6 Impact on Performance and Outcomes 
The primary responsibility for the prevention, detection and
investigation of fraud rests with Management, supported by the
Corporate Fraud team. Internal Audit provides advice and independent
assurance on the effectiveness of processes put in place by
Management. The Findings and Recommendations from Internal Audit
work which are presented to the Audit Committee during the year
assists the Council in maintaining and / or enhancing fraud prevention
and detection controls. 
A.7 Adopting a Preventative Approach 
Having robust fraud prevention and investigation arrangements in place
contributes to safeguarding the Council’s financial resources, for
delivery of services, as part of protecting the public purse. A focus on
enhancing fraud prevention and detection to improve Midlothian
Council’s resilience to the risk of fraud, theft, corruption and crime, and
ensure these are embedded preventative practices are specific
changes associated with the Counter Fraud Strategy. 
A.8 Supporting Sustainable Development 
None.  
Page 197 of 396

Page 198

Appendix 1 – Outcomes from Corporate Fraud Team activity on corporate fraud enquiries in 2024/25 
Type of Referral No. of
Referrals  Web  Phone
Email /
letter
No. with
Potential
Fraud
Detected 
Fraud
Detected
Comments
Corporate Fraud
(Internal) 11 2 4 5 1 £45,413
Full Investigations undertaken in response to referrals from various
sources.
• 1 investigation resulted in full recovery of CLLE rent grant payments
totalling £21,750 which was paid in error and retained without the
knowledge of the organisation. 
• Full recovery of £700 from an ex-employee.
• Recovery of £15,963 in relation to historic School Transport
investigation.
• historic embezzlement case from 3 years ago is with the Scottish
Courts, a guilty plea from one of the accused has been accepted with a
£7k compensation order in favour of Midlothian Council. 
Housing Tenancy
Fraud 48 6 3 39 11 £861,300
48 referrals were received by email directly from Housing Officers.
All 48 referrals were investigated, resulting in the recovery of 11
Council houses.
Value for each property calculated as per Cabinet Office NFI
Estimates Outcomes Methodologies guidance (£78,300 per property
recovered).
Council Tax
Discounts &
Exemptions & 
CTRS / SPD/
DWP Benefits
27 17 2 8  
8 cases referred to the Department for Work and Pensions to
investigate due to benefits in payment
DPA/SOCG
enquiries 10   10   9 enquiries received from Police Scotland.
1 enquiry received from East Lothian Council.
Other  15 7 3 5  
Investigations resulting in referrals being submitted to external
partners and internal services including Education, Blue Badge,
Trading Standards and Economic Development.
Total 111 32 12 67 12 £906,713 
Page 198 of 396

Page 199

9
Appendix 2 – Total outcomes from Midlothian Council’s participation in the National Fraud Initiative 2022/2023 exercise 
Type No of
Matches
22/23
No of
matches
reviewed
Fraud or
Errors
Detected
Outcome
(overpayment)
Estimated
Savings
Total
Savings
Comments
Council Tax (SPD) 35  35 £43,824 £22,078 £65,902
Including 5 cases where CTRS was reduced and 4
cases where Housing Benefit was reduced (see
below for figures).
Housing Benefit 4  4 £57,041 £3,834 £60,875 
Council Tax
Reduction (CTRS) 5  5 £7,330 £977 £8,307 
Small Business
Bonus Scheme
(SBBS- NDR) 
25  2 £13,359 £13,944 £27,303 This data set was reviewed by City of Edinburgh
Council as they hold and administer Midlothian
Council non- domestic rates (NDR) data.
Total savings for
2022/23 NFI
exercise in 2024/25   
£121,554 £40,833 £162,387 
Page 199 of 396

Page 200

Page 200 of 396

Page 201

Audit Committee
Monday 16 June 2025
Item No 5.9 
External Quality Assessment of Midlothian Council’s Internal Audit
Service 
Report by Chief Internal Auditor 
Report for Information 
1 Recommendations 
The Audit Committee is asked to note the External Quality Assessment
of Midlothian Council’s Internal Audit Service recently completed by
Michelle Blair, Chief Auditor East Renfrewshire Council.   
2 Purpose of Report/Executive Summary 
The purpose of the report is to introduce the External Quality
Assessment of Midlothian Council’s Internal Audit Service recently
completed by Michelle Blair, Chief Auditor East Renfrewshire Council
to the Audit Committee for noting. The report is included as Appendix 1   
Date 4 June 2025 
Report Contact:
Duncan Stainbank 
duncan.stainbank@midlothian.gov.uk  
Page 201 of 396

Page 202

2
3 Background 
3.1 Public Sector Internal Audit Standards require an External Quality
Assessment of Internal Audit Services is completed every 5 years. The
last External Quality Assessment of Midlothian Council’s Internal Audit
team was completed by Highland Council in June 2018, delays in
completion of this current review were a one year delay accepted due
to Covid 19; and a further years delay as a  reorganisation of the
schedule of reviews was required as a result of the Shared Service
Arrangement with East Lothian Council as Midlothian Council had been
scheduled to complete the review of East Lothian Council.   
3.2 The Report highlights that Midlothian Council’s Internal Audit Service
‘fully conforms’ with 8 of the PSIAS standards and ‘generally conforms’
with the remaining 6 standards. 7 Low graded recommendations have
been made and accepted by the Chief internal Auditor, 2 of the
recommendations have previously been advised to the Audit
Committee and 3 were already in progress as a result of a full review of
the Internal Audit documentation in advance of the implementation of
Global Internal Audit Standards.   
3.3 I note that the report indicates the ‘extensive experience of the
Principal Auditor’ and the Chief Internal Auditor ‘and Qualified staff
providing a strong team with experience and knowledge to lead the
audit service’. The report also recognises ‘the Council actually having a
really robust anti-fraud strategy and a strong, separate anti-fraud team
linked to and reporting to the Chief Internal Auditor and the work of the
Fraud team is reported to Audit Committee annually with a financial
value attached to the fraud prevention work.’ 
3.4 The next External Quality Assessment (EQA) of the Internal Audit
Service is also scheduled to be completed within the next five years.
This EQA will also be completed under the “EQA Peer Review
Framework” which has been developed by the Scottish Local
Authorities Chief Internal Auditors Group (SLACIAG). The next review
will be against the Global Internal Audit Standards that came into effect
in April 2025 for the UK public sector. These standards for the UK
Public Sector are an evolution from the PSIAS standards and therefore
the recommendations made in this report will be implemented to meet
these standards also. 
Page 202 of 396

Page 203

3
4 Report Implications (Resource, Digital, Risk and Equalities) 
4.1 Resource 
The only resources impacted as Internal Audit resources and have
been appropriately discussed as part of the Assessment closure
meetings. 
4.2 Digital 
There are no digital implications arising from this report. 
4.3 Risk 
The PSIAS require Internal Audit to evaluate the effectiveness of the
Council’s Risk Management arrangements and contribute to
improvements in the process. At the start of each audit engagement, to
capture potential areas of risk and uncertainty more fully, key
stakeholders have been consulted and risk registers have been
considered. During each audit engagement the management of risk
has been tested. 
It is anticipated that improvements in the management and mitigation of
risks will arise as a direct result of Management implementing the
Internal Audit recommendations made. If audit recommendations are
not implemented, there is a greater risk of financial loss and/or reduced
operational efficiency and effectiveness, and Management may not be
able to demonstrate improvement in internal control and governance
arrangements, and effective management of risks. 
4.4 Ensuring Equalities 
This report does not relate to a new or revised policy, service or budget
change, which affects people (the public or staff), so an Integrated
Impact Assessment (IIA) is not an applicable consideration. 
The Internal Audit work is carried out in accordance with the
appropriate legislation and professional standards. The latter includes
compliance by those within the Internal Audit function with the Code of
Ethics set out in the PSIAS which is appropriate for the profession of
Internal Audit founded as it is on trust placed in its independent and
objective assurance about risk management, internal control and
governance. 
4.5 Additional Report Implications (See Appendix A) 
Page 203 of 396

Page 204

4
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Although this report does not relate directly to the key priorities within
the Single Midlothian Plan (Reducing the gap in economic
circumstances; Reducing the gap in learning outcomes; Reducing the
gap in health outcomes; and Reducing the impact of climate change)
Note is made that these key priorities are reflected in the audit plan and
any links will be identified as part of each audit planning process going
forward. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working  
Hub and Spoke  
Modern  
Sustainable  
Transformational  
Preventative  
Asset-based  
Continuous Improvement  
One size fits one 
None of the above 
Midlothian Council is committed to creating a great place to grow
supported by the 9 drivers for change. Implementing the 9 drivers for
change in practice is applicable to the Council’s Internal Audit service
provision to assist the Council in achieving its objectives. 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you  
Preventative and Sustainable  
Efficient and Modern  
Innovative and Ambitious 
A.4 Delivering Best Value 
The definition of Internal Auditing within the Public Sector Internal Audit
Standards (PSIAS) is “Internal auditing is an independent, objective
assurance and consulting activity designed to add value and improve
an organisation’s operations. It helps an organisation accomplish its
objectives by bringing a systematic, disciplined approach to evaluate
and improve the effectiveness of risk management, control and
governance processes.” 
Page 204 of 396

Page 205

5
Implementation by Management of the actions associated with Internal
Audit recommendations, that are designed to improve internal control
and governance arrangements and management of risks, underpins
the Council’s own continuous improvement arrangements to enhance
its effectiveness, thus supporting the delivery of the Council’s best
value duties. 
A.5 Involving Communities and Other Stakeholders 
The Chief Internal Auditor is accountable to the Audit Committee which,
in fulfilling its governance role, acts as a bridge between the Council
and other stakeholders. 
This report was created with input from previous Chairs of the Audit
Committee and various members of Senior Management including the
Chief Executive, the Section 95 Officer and the Monitoring Officer. 
A.6 Impact on Performance and Outcomes 
The Findings and Recommendations from Internal Audit work during
the year are designed to assist the Council in improving its
performance and outcomes. The Performance and Outcomes of the
Internal Audit Service will be improved by the implementation of the
recommendations of this report. 
A.7 Adopting a Preventative Approach 
Internal Audit assurance work includes assessments on when a
preventative approach can be adopted. 
A.8 Supporting Sustainable Development 
This report does not relate directly to supporting sustainable
development. Good governance is important to enable Midlothian
Council to achieve its objectives. 
Page 205 of 396

Page 206

Page 206 of 396

Page 207

2 June 2025 Page 1 
EXTERNAL QUALITY
ASSESSMENT 
OF 
MIDLOTHIAN COUNCIL’S
INTERNAL AUDIT SERVICE 
Report Recipients: 
Grace Vickers, Chief Executive
Alan Turpie, Legal and Governance Manager
David Gladwin, Chief Financial Officer
Duncan Stainbank, Chief Internal Auditor
Cllr Derek Milligan
Cllr Peter Smaill 
Page 207 of 396

Page 208

EXECUTIVE SUMMARY 
2
1.  INTRODUCTION 
1.1 The mandatory Public Sector Internal Audit Standards (PSIAS), published initially in
April 2013 and updated most recently in March 2017, apply to all internal audit service
providers in the UK public sector, whether in-house, provided via a shared service
arrangement or outsourced. To supplement the PSIAS, and provide specific guidance
surrounding its application within a local government setting, the Chartered Institute of
Public Finance and Accountancy (CIPFA) compiled a Local Government Application
Note, which was last updated in 2019. 
1.2 The objectives of the PSIAS are to define the nature of internal auditing within the UK
public sector; set basic principles for carrying out internal audit; establish a framework
for providing internal audit services, which add value to the organisation, leading to
improved organisational processes and operations; establish the basis for the evaluation
of internal audit performance and drive improvement planning. 
1.3 The PSIAS require the Chief Audit Executive (the Shared Chief Internal Auditor in
Midlothian Council) to develop and maintain a quality assurance and improvement
programme (QAIP) that covers all aspects of the internal audit activity.  The QAIP must
include both periodic internal self-assessments and five-yearly external assessments,
carried out by a qualified, independent assessor from outwith the organisation, and
enable evaluation of the internal audit activity’s conformance with the PSIAS, including
the Mission of Internal Audit, Definition of Internal Auditing and Code of Ethics. In
addition, the QAIP should also assess the efficiency and effectiveness of the internal
audit activity and identify opportunities for improvement. 
1.4 To assist its members to meet the five-yearly external assessment requirement, the
Scottish Local Authorities Chief Internal Auditors’ Group (SLACIAG) established a
collaborative system of formal peer reviews.  This approach not only assists with
ensuring that independent assessors, and their teams, have appropriate knowledge and
experience of the local government internal audit environment but also removes the
financial burden from councils, associated with procuring these services externally.  The
allocation of assessors / assessment teams to councils participating in the peer review
process was undertaken autonomously, ensuring that, amongst other governing
principles, local authorities with perceived / known conflicts of interest could not review
one another.  At the outset, assessors were required to formally declare any interests
so that these could be appropriately addressed during the allocation process.  East
Renfrewshire Council was selected to carry out the external assessment in Midlothian
Council.   
1.5 To support the peer review process, SLACIAG developed a comprehensive External
Quality Assessment (EQA) framework, including an EQA Checklist for Assessing
Conformance with the PSIAS and the Local Government Application Note (EQA
Checklist) and a key Stakeholder Questionnaire proforma. The external assessment of
Midlothian Council’s Internal Audit function has been carried out by East Renfrewshire
Council’s Chief Internal Auditor utilising this framework.   
1.6 This report provides a high level summary of requirements for each standard per the
PSIAS and CIPFA Local Government Application Note and sets out the findings,
conclusions and recommendations from the external assessment, which involved
discussions with key members of staff, including the Chief Internal Auditor, review of the
most recent self-assessment carried out utilising the EQA Checklist and consideration
of other relevant supporting documentation / information (Evidence Pack) including
working paper files and completed stakeholder questionnaires. A comprehensive list of
Page 208 of 396

Page 209

EXECUTIVE SUMMARY 
3
supporting documentation / information and completed stakeholder questionnaires
considered as part of the assessment can be found at appendices B and C respectively. 
1.7 Whilst it is acknowledged that PSIAS has been replaced from 1 April 2025 by the
General Internal Audit Standards (GIAS) it is expected that compliance with PSIAS will
still contribute to a good level of compliance with the new standards. 
Page 209 of 396

Page 210

4 
2.  OVERALL CONCLUSION
2.1 The overall conclusion of the external assessment is that Midlothian Council’s Internal
Audit generally conforms with the PSIAS. None of the standards have been assessed
as partially or not conforming with PSIAS, however seven recommendations have been
made to assist the Internal Audit function, all of which are low graded minor
recommendations. A full summary of assessment, per assessment area, can be found
at Appendix A.  A summary of totals is as follows:   
Fully
Conforms     
Generally
Conforms     
Partially
Conforms     
Does Not
Conform   
TOTALS 8 6 0 0 
2.2 The main areas for improvement highlighted in the report are as follows: 
• There should be an expanded section within the Audit Charter defining the role of
internal audit in any fraud related work.
• A performance measurement methodology should be developed to evaluate the
internal audit function’s performance against its objectives.
• An appropriate methodology to facilitate and document service feedback should be
developed. 
• The Audit Strategy, specifically the audits included in the audit plan, could be more
closely linked to the overall strategic objectives of the Council.
• An assurance mapping methodology should be developed
• The terms of reference document should be expanded to include resources and
reflect any limitation in scope.
• Key stakeholders including the audit committee should be consulted on their
preference on the format of audit reports distributed and the form that this should
take. 
2.3 Full details of the assessment recommendations and management responses can be
found in the Action Plan at Appendix D. 
Page 210 of 396

Page 211

5 
3.  SECTION A – MISSION OF INTERNAL AUDIT AND CORE PRINCIPLES 
The PSIAS state that the Mission of Internal Audit articulates what internal audit aspires
to accomplish within an organisation, which is ‘to enhance and protect organisational
value by providing risk-based and objective assurance, advice and insight’.   
Taken as a whole, the Core Principles for the Professional Practice of Internal Auditing,
as set out in the PSIAS, articulate internal audit effectiveness.  For an internal audit
function to be considered effective, all Core Principles should be present and operating
effectively.  Failure to achieve any of the Core Principles would imply that an internal
audit activity was not as effective as it could be in achieving the Mission of Internal Audit. 
3.1 Evidence obtained from assessing conformance with other standards in the PSIAS has
been used, along with specific consideration surrounding the achievement of the Core
Principles, to conclude that the Midlothian Councils Internal Audit function fully
conforms with accomplishing the Mission of Internal Audit as detailed above. 
4. SECTION B – DEFINITION OF INTERNAL AUDITING 
The PSIAS state that internal auditing is an independent, objective assurance and
consulting activity designed to add value and improve an organisation’s operations. It
helps an organisation accomplish its objectives by bringing a systematic, disciplined
approach to evaluate and improve the effectiveness of risk management, control and
governance processes. 
4.1 Evidence obtained from assessing conformance with other standards in the PSIAS has
been used to conclude that Midlothian Councils Internal Audit function fully conforms
with the definition of Internal Auditing as detailed above.  Evidence provided, principally
the Audit Charter and high level approval of this document confirms that the objectives
of the Internal Audit function is to “support the Council in its activities designed to achieve
its objectives.” It does so by supporting the Councils vision, values and priorities,
contributing to the corporate management of risk, ensuring all stakeholders operate
within the law and relevant regulations and that public money is safeguarded, accounted
for and used efficiently and effectively.   
5.  SECTION C – CODE OF ETHICS 
The PSIAS state that the purpose of the Institute of Internal Auditor’s Code of Ethics is
to promote an ethical culture in the profession of internal auditing. A code of ethics is
necessary and appropriate for the profession of internal auditing, founded as it is on the
trust placed in its objective assurance about risk management, control and governance. 
Internal auditors in UK public sector organisations must conform to the Code of Ethics
as set out in the PSIAS. If individual internal auditors have membership of another
professional body then he or she must also comply with the relevant requirements of
that organisation. 
5.1 Evidence obtained from assessing conformance with other standards in the PSIAS, in
particular the Attribute Standards 1000 – Purpose Authority and Responsibility, 1100 –
Independence and Objectivity, 1200 – Proficiency and Due Professional Care and
Professional Standards 2000 – Managing the Internal Audit Activity and 2300 –
Performing the Engagement, has been used to conclude that Midlothian Council’s
Internal Audit function generally conforms with the requirement to comply with the
Code of Ethics given that there are a small number of improvements set out within this
report to further enhance compliance with PSIAS. 
5.2 As part of the assessment carried out there were several areas of Good Practice
identified as below: 
Page 211 of 396

Page 212

6 
5.2.1 Fully qualified experienced staff. The Shared Chief Internal Auditor has extensive
experience and is supported by an equally experienced Principal auditor and qualified
staff – this is a strong team with experience and knowledge to lead the audit service. 
5.2.2 The Audit Manual is a comprehensive and supportive document, clearly laying out each
stage of a potential audit and with easily understandable and helpful appendices and
templates to guide the auditor. 
5.2.3 A fully functioning Fraud Prevention team with close links to the Internal Audit function,
strengthening controls against the risk of fraud. The work of the Fraud team is reported
to Audit Committee annually with a financial value attached to the fraud prevention
work. 
5.2.4 Strong reporting lines and processes, regular reporting to Audit Committee and the
Corporate Management team as appropriate. 
6. SECTION D – ATTRIBUTE STANDARDS 
Attribute Standards apply to organisations and individual internal auditors
providing the internal audit services in a local authority. 
6.1 1000 - Purpose, Authority, and Responsibility 
The PSIAS state that the purpose, authority and responsibility of the internal audit
activity must be formally defined in an Internal Audit Charter, consistent with the Mission
of Internal Audit and the mandatory elements of the International Professional Practices
Framework.  The chief audit executive must periodically review the internal audit charter
and present it to senior management and the board for approval.  The internal audit
charter must also: 
• define the terms ‘board’ and ‘senior management’ for the purposes of internal audit
activity;
• cover the arrangements for appropriate resourcing; 
• define the role of internal audit in any fraud-related work; and 
• describe safeguards to limit impairments of independence or objectivity if internal
audit or the chief audit executive undertakes non-audit activities. 
6.1.1 Midlothian Council’s Internal Audit Charter is periodically reviewed with the most recent
review taking place in February 2025, and being approved by the Audit Committee on
24 February 2025. 
6.1.2 The Audit Charter is well written and comprehensive. However the section around the
role of internal audit in any fraud related work, the arrangements for anti-fraud and anti-
corruption polices, and the reporting of fraud to audit is quite small and not as strong as
it could be. This is placed in sharper focus by the Council actually having a really robust
anti-fraud strategy and a strong, separate anti-fraud team linked to and reporting to the
Chief Internal Auditor. Expanding this section to embed the anti-fraud strategy, the work
of the anti-fraud team and the operational arrangements for fraud reporting within the
Audit Charter would strengthen the position of the work undertaken here. 
6.1.3 In addition, the Audit Charter could be further enhanced by specifically clarifying the
roles of the statutory officers in relation to internal audit and providing a clear definition
of assurance services that are provided. 
Recommendation 1
When the Audit Charter is next reviewed it should include:
Page 212 of 396

Page 213

7 
• An expanded section definitively addressing the Internal Audit role in combatting fraud,
the role and status of the fraud team, signposting to the counter fraud and anti-corruption
policies and the arrangements for fraud to be notified to the relevant officer/team.
• A definition of the nature of assurance services
• The roles and responsibilities of statutory officers in relation to internal audit. 
6.1.4 Having considered the findings above, it has been concluded that the Midlothian
Council’s Internal Audit function generally conforms with Standard 1000 on Purpose,
Authority and Responsibility. 
6.2 1100 - Independence and Objectivity 
The internal audit activity must be independent and internal auditors must be objective
in performing their work.  Various aspects of independence and objectivity are covered
in this standard as well as 1200, including reporting functional lines of the CAE, the
relationship between the CAE and the board and any impairment to individual internal
auditors’ objectivity or independence. Reporting and management arrangements must
be put in place that preserve the CAE’s independence and objectivity, in particular with
regard to the principle that the CAE must be independent of the audited activities. 
6.2.1 The Shared Chief Internal Auditor reports functionally to the Audit Committee and
administratively to the Chief Executive who is a member of the Council’s Senior
Management Team. As a further note, in the Service Level Agreement supporting the
shared service, the Chief Internal Auditor’s performance is managed by the Executive
Director for Council Resources.  The Chief Internal Auditor has direct and unrestricted
access to the Chief Executive and the Chair of the Audit Committee and this has been
confirmed through the completed Stakeholder Questionnaires.  These reporting / access
arrangements are clearly defined in the Internal Audit Charter, as are safeguards to limit
impairment of independence or objectivity.   
6.2.2 In support of organisational independence, the Chief Internal Auditor attends Audit
Committee meetings to present all internal audit reports (including, for example, the
Internal Audit Charter, Annual Report, Internal Audit Plan and reports / executive
summaries from the planned audits) to Elected Members.  The reports are all submitted
in the Chief Internal Auditor’s name.   
6.2.3 The Chief Internal Auditor does not have operational responsibility for the activities
audited and this is implicit in the documents reviewed. It is noted that this is now explicitly
stated in the latest Audit Charter. 
6.2.4 All staff within the Internal Audit function and Fraud Team are required to complete a
register of interests form (or equivalent) on an annual basis to declare any conflicts of
interest.   
6.2.5 Midlothian Council’s Internal Audit function fully conforms with Standard 1100 on
Independence and Objectivity. 
6.3 1200 - Proficiency and Due Professional Care 
The CAE must be professionally qualified, suitably experienced and responsible, in
accordance with the organisation’s human resources processes, for recruiting
appropriate staff.  He or she is responsible for ensuring that up-to-date job descriptions
exist, reflecting roles and responsibilities, and that person specifications define the
required qualifications, competencies, skills, experience and personal attributes. 
The CAE should periodically assess individual auditors’ skills and competencies against
those set out in the relevant job descriptions and person specifications. Any training or
development needs identified should be included in an appropriate ongoing
development programme that is recorded and regularly reviewed and monitored. In
Page 213 of 396

Page 214

8 
addition, all internal auditors have a personal responsibility to undertake a programme
of continuing professional development (CPD) to maintain and develop their
competence. This may be fulfilled through requirements set by professional bodies or
through the organisation’s own appraisal and development programme. Auditors should
maintain a record of such professional training and development activities. 
The internal audit activity should be appropriately resourced to meet its objectives. It
should have appropriate numbers of staff in terms of grades, qualifications, personal
attributes and experience or have access to appropriate resources in order to meet its
objectives and to comply with these standards. The PSIAS states that the CAE must
obtain competent advice and assistance if the activity is unable to perform all or part of
an engagement. 
6.3.1 The Chief Internal Auditor holds a relevant professional qualification, and is suitably
experienced, with over 20 years internal audit experience within a public sector
environment.  The Chief Internal Auditor is a member of SLACIAG  and regularly attends
and contributes to meetings.  In relation to the SLACIAG Computer Audit Sub-Group
(CASG) and the Scottish Local Authority Investigators Group (SLAIG), Midlothian
Council’s Internal Audit function is regularly represented on both. 
6.3.2 There are 3.22 FTE members of staff in the Internal Audit function, including the Chief
Internal Auditor (0.5 FTE), Principal Auditor (0.72 FTE) and 2 FTE Internal Auditors. 
Membership of the Consultative Committee of Accountancy Bodies (CCAB), Chartered
Institute of Management Accountants (CIMA) or the Chartered Institute of Internal
Auditors (CIIA) is noted as a requirement in each of the job descriptions. The Internal
Audit function delivers internal audit services to Midlothian Council.  There are also two
FTE corporate fraud officers both line managed by the Chief Internal Auditor.   
6.3.3 Midlothian Council have a competency framework in place, supported by an Annual
Review and Planning process/meeting. It is clear all staff have received an annual
review and this process is working effectively. 
6.3.4 The Internal Audit function is well represented on a number of corporate groups,
including the Children and Young People Estate Board, Capital Plan Asset Management
Board, Business Transformation Board, Information Management Group, Risk
Management Group and Integrity Group. 
6.3.5 The Chief Internal Auditor, Principal Auditor and Internal Auditors all have specific CPD
requirements to adhere to, relevant to their own membership institutes.  Evidence was
provided that all staff participate actively in fulfilling their CPD requirements.   
6.3.6 The audit manual and associated templates are comprehensive documents to fully
support the exercise of due professional care for planning assurance and consulting
engagements. In terms of the team having the relevant knowledge and skills, there is a
training budget and there are also some courses which are required to be completed
and update annually, for example cyber security.  Computer assisted audit techniques
are utilised by the team and are considered as part of each audit. 
6.3.7 Stakeholder questionnaires confirm that the Chief Internal Auditor demonstrates
sufficient knowledge and experience and that all members of the Internal Audit function
exercise due professional care.   
6.3.8 Midlothian Council’s Internal Audit function fully conforms with standard 1200 on
Proficiency and Due Professional Care. 
6.4 1300 - Quality Assurance and Improvement Programme 
Page 214 of 396

Page 215

9 
The PSIAS state that the Chief Audit Executive must develop and maintain a quality
assurance and improvement programme (QAIP) that covers all aspects of the internal
audit activity. 
The QAIP must include both periodic internal self-assessments and five-yearly external
assessments, carried out by a qualified, independent assessor from outside the
organisation, and enable evaluation of the internal audit activity’s conformance with the
PSIAS, including the Definition of Internal Auditing and Code of Ethics. In addition, the
QAIP should also assess the efficiency and effectiveness of the internal audit activity
and identify opportunities for improvement. 
The public sector requirement in the PSIAS states that results of the QAIP and progress
against any improvement plans must be reported in the annual report. 
6.4.1 Internal audit reports are reviewed by the Chief Internal Auditor or Principal Auditor prior
to issue. Meetings can be arranged with the Principal Auditor to discuss any issues on
a more detailed basis.   
6.4.2 Client feedback is not actively pursued by the Internal Audit function for assignments
carried out within Midlothian Council, however verbal feedback is provided at Corporate
Management Team meetings. The Chief Internal Auditor advised that client surveys are
not used due to the inherent flaws in the process and the size of the Council could lead
to the same officers being asked to repeatedly supply feedback. 
6.4.3 However, the use of survey forms was recommended as part of the action plan flowing
from the previous external PSIAS assessment at Midlothian and a feedback mechanism
was also raised as part of the internal assessment process as reported in the 2023/24
Annual Assurance Report and Opinion, where an improvement action was highlighted
to “Develop appropriate methodology to formally document service feedback.” 
Recommendation 2
An appropriate methodology to facilitate and document service feedback should be
developed and used to inform ongoing service delivery. 
6.4.4 The Mid-Year Performance Report and the Annual Assurance Reports are detailed and
comprehensive around the regulatory framework and PSIAS requirements and reports
on whether an audit is complete, in progress or not started. In the Annual Assurance
report, the percentage of work carried out compared to the Internal Audit Plan is reported
but there are no Key Performance Indicators or Balanced Scorecards produced around
the performance of the Internal Audit Function. 
6.4.5 Whilst the use of performance indicators is not explicitly required in PSIAS, the GIAS
requires the development of objectives to evaluate the internal audit function’s
performance. 
Recommendation 3
A performance measurement methodology should be developed to evaluate the internal
audit function’s performance against its objectives.   
6.4.6 Formal PSIAS Self Assessments are carried out each year, and a corresponding QAIP
is compiled and reported as part of the Annual Assurance Report along with progress
on any actions agreed as part of the previous year’s self assessment. 
6.4.7 Midlothian Council’s Internal Audit Function generally conforms with Standard 1300 on
Quality Assurance and Improvement Programme. 
7. SECTION E – PERFORMANCE STANDARDS
Page 215 of 396

Page 216

10 
Performance Standards describe the nature of the internal audit services being
provided and provide criteria against which the performance of an internal audit
function can be measured. 
7.1 2000 - Managing the Internal Audit Activity 
The chief audit executive must effectively manage the internal audit activity to ensure it
adds value to the organisation.  The internal audit activity is effectively managed when
it achieves the purpose and responsibility included in the internal audit charter, it
conforms with the PSIAS, its individual members conform with the Code of Ethics and
the PSIAS and it considers trends and emerging issues that could impact the
organisation.  The internal audit activity adds value to the organisation and its
stakeholders when it considers strategies, objectives and risks; strives to offer ways to
enhance governance, risk management, and control processes; and objectively
provides relevant assurance. 
7.1.1 An annual Internal Audit Plan is compiled by the Chief Internal Auditor outlining the
planned programme of work to be undertaken. Audit work during the past 5 years was
analysed against the audit universe which had been recently revised to reflect current
strategic and operational management arrangements. The Strategic Risk Profile was
checked also to ensure coverage on key strategic risks and account was also taken of
external audit work and inspection activities to avoid duplication, alongside an annual
evaluation of compliance with the Local Code of Corporate Governance. 
7.1.2 An audit was undertaken in 2023/24 around Midlothian Council’s Risk Management
Framework which concluded there was a substantial level of assurance around the
policy at a strategic level but limited assurance at an operational level. 
7.1.3 The resources in the team has reduced in recent years and it is acknowledged that this
has led to a reduction in the contingency budget and reduces the resilience of the team
in terms of being able to fully complete the Audit Plan. 
7.1.4 Directors and Chief Officers, alongside the Corporate Management Team (CMT) and
the Audit Committee all consider and have input into the Audit Plan before it is approved
by Audit Committee and the CMT. 
7.1.5 Work by the Internal Audit function towards completion of the assignments included in
the Audit Plan is reported to Audit Committee quarterly alongside the salient points from
each audit completed. 
7.1.6 Four out of five stakeholder questionnaire responses believe that the internal audit
function adds value to the Council and that the internal audit plan takes account of the
council’s risk management framework and the Chief Auditors assessment of risk. One
responder in each of these questions considered it only to be partly true.     
7.1.7 Key Priorities within the Single Midlothian Plan and also the Key Drivers for Change are
detailed as an appendix in the cover report for the Internal Audit Strategy and Annual
Plan. Each audit on the plan is linked to the Council Strategic plan objectives as part of
the planning process.  However the Internal Audit Strategy could both be linked more
closely to the organisational objectives and priorities and this linkage reflected in the
individual audit planning document. 
Recommendation 4
The Audit Strategy and specifically the planning document for each individual audit
should reflect the annual plan link to the overall strategic objectives of the Council. 
7.1.8 The audit plan should be developed on a risk basis and should take account of other
sources of assurance.  This should include an assurance mapping exercise and co-
Page 216 of 396

Page 217

11 
ordination of activities with other assurance providers where appropriate.  Whilst there is
some co-ordination with the external auditors and reviews of some external assurance
reports, there is no overall assurance map. 
Recommendation 5
The Chief Auditor should consider developing an assurance mapping methodology to
provide clarity around the internal audit planning and reporting approach. 
7.1.9 Midlothian Council’s Internal Audit function generally conforms with Standard 2000 on
Managing the Internal Audit Activity. 
7.2 2100 - Nature of Work 
The internal audit activity must evaluate and contribute to the improvement of the
organisation’s governance, risk management, and control processes using a systematic,
disciplined, and risk-based approach. Internal audit credibility and value are enhanced
when auditors are proactive and their evaluations offer new insights and consider future
impact. 
More specifically, the internal audit activity must assess and make appropriate
recommendations to improve the organisation’s governance processes, evaluate the
effectiveness and contribute to the improvement of risk management processes and
assist the organisation in maintaining effective controls by evaluating their efficiency and
effectiveness and promoting continuous improvement. 
7.2.1 The Internal Audit function has adequate coverage over governance and risk
management and control.  Stakeholder questionnaires completed for this review
generally agreed that the Internal Audit function adds value to the Council and leads to
improved organisational processes and operations.   Each audit programme for
individual assignments lays out in detail relevant risks and legislation applicable to the
audit, expected internal controls and any other recent reviews that have taken place and
whether there are any fraud risk assessments to consider. 
7.2.2 In particular, adequate arrangements are in place to evaluate the risk of fraud and this
is considered as part of each audit.  Midlothian Council has a separate fraud plan which
is submitted to the Audit Committee annually. 
7.2.3 Each control objective in each audit forms part of a working paper which is the base for
recording all test results and recommendations. The results of each complete audit is
then communicated to all relevant staff as appropriate including the Chief Executive,
Corporate Management Team and Departmental Management team. 
7.2.4 Midlothian Council’s Internal Audit function fully conforms with Standard 2100 on
Nature of Work. 
7.3 2200 - Engagement Planning 
Internal auditors must develop and document a plan for each engagement, including the
engagement’s objectives, scope, timing and resource allocations. The plan must
consider the organisation’s strategies, objectives and risks relevant to the engagement. 
The CIPFA Local Government Application note states that for each engagement, a brief
should be prepared, discussed and agreed with relevant managers. The brief should
establish the objectives, scope and timing for the assignment and its resource and
reporting requirements. Audit work should be undertaken using a risk-based audit
approach. 
7.3.1 As detailed above, each audit assignment has a completed terms of reference which
details the objectives and estimated timing of the audit, however the resources required
giving consideration to knowledge, skills and competencies, whilst reflected in the audit
Page 217 of 396

Page 218

12 
plan should be formally recorded as considered at this stage.  It is noted that the
resources are limited to the small team available.  The scope of the engagement is
detailed but not what is excluded and this section could be expanded to incorporate this. 
This is then linked to a document which sets out the internal control environment
expected, alongside risks and relevant legislation and subsequently to working papers
containing the details and results of testing against the control objectives. The work
carried out for each audit is then reviewed by senior staff before being reported to
management. 
Recommendation 6
The Terms of Reference Document should be expanded to include any exclusions from
the scope of the work and consideration of the resources allocated, whilst recognising
that the choice of resources is limited. 
7.3.2 Midlothian’s Internal Audit function also undertakes audits for the Midlothian Integration
Joint Board which involves regular discussion with neighbouring IJBs and NHS Lothian
Internal Audit. 
7.3.3 There is also an allowance in the Audit Plan to support consulting engagements of which
there were two in 2023/24. Each consultancy engagement has a standard brief prepared
and is then reported using a standard template. 
7.3.4 Midlothian Council’s Internal Audit function generally conforms with Standard 2200 on
Engagement Planning. 
7.4 2300 - Performing the Engagement 
Internal auditors must identify, analyse, evaluate and document sufficient information to
achieve the engagement’s objectives. 
At each stage of the audit, auditors should consider what specific work needs to be
conducted and evidence needs to be gathered to achieve the engagement objectives
and support an independent and objective audit opinion.  Systems should be in place to
ensure that auditors obtain and record, within the working papers, sufficient evidence to
support their conclusions, professional judgements and recommendations.  Working
papers should always be sufficiently complete and detailed to enable an experienced
internal auditor with no previous connection with the audit to ascertain what work was
performed, re-perform it if necessary and support the conclusions reached.  The CAE
should also specify how long all audit documentation should be retained, whether held
on paper or electronically.  All audit work should be subject to an appropriate internal
quality review process. 
Internal auditors must be alert to the possibility of intentional wrongdoing, errors and
omissions, poor value for money, failure to comply with management policy and conflicts
of interest when performing their individual audits. They must also have sufficient
knowledge to identify indicators that fraud or corruption may have been committed. 
7.4.1 The Midlothian Internal Audit Manual is a comprehensive document, a working blue print
to be able to conduct all aspects of an effective Internal Audit assignment. 
7.4.2 In general, there are very effective standard templates to allow a consistent and
methodical approach to be undertaken on audit assignments and for effective peer
review, including templates for meeting structures, engagement emails, Terms of
Reference, audit programmes, audit working papers and reports. 
7.4.3 Working papers are based on a standard template for each objective or expected
control. The background to the objective and the risks involved are detailed in each
working paper, alongside the tests carried out and detailed findings. All related
documents including detailed workings are hyperlinked. 
Page 218 of 396

Page 219

13 
7.4.4 The Internal Audit Team meet weekly to discuss progress and any issues being
encountered. A review of working paper files demonstrated that audit work is
appropriately reviewed at all stages. 
7.4.5 Records management arrangements and consideration of GDPR are fully detailed in the
audit manual.     
7.4.6 Midlothian Council’s Internal Audit function fully conforms with Standard 2300 on
Performing the Engagement. 
7.5 2400 - Communicating Results 
The basic aims of every internal audit report should be to: 
• give an opinion on the risk and controls of the area under review, building up to the
annual opinion on the overall adequacy and effectiveness of the organisation’s
framework of governance, risk management and control;
• prompt management to implement the agreed actions for change leading to
improvement in the control environment and performance; and
• provide a formal record of points arising from the audit and, where appropriate, of
agreements reached with management, together with appropriate timescales. 
Each report should include the scope and purpose of the audit to help the reader to
understand the extent, or limitations, of the assurance(s) provided by the report.  During
the course of the audit, key issues should be brought to the attention of the relevant
manager to enable them to take corrective action and to avoid surprises at the closure
stage.  Before issuing the final report, the internal auditor should normally discuss the
contents with the appropriate levels of management to confirm the factual accuracy, to
seek comments and to confirm the agreed management actions. A draft report is useful
for this purpose.  Recommendations should be prioritised according to risk. The
recommendations and the resultant management action plans should be agreed prior to
the issue of the final report.  Any areas of disagreement between the internal auditor and
management that cannot be resolved by discussion should be recorded in the action
plan and the residual risk highlighted.  Those weaknesses giving rise to significant risks
that are not agreed should be brought to the attention of a more senior level of
management and the board. 
As set out in the PSIAS, the CAE must deliver an annual internal audit opinion and report
that can be used by the organisation to inform its annual governance statement. This
must include the annual internal audit opinion concluding on the overall adequacy and
effectiveness of the organisation’s governance, risk and control framework, a summary
of the audit work from which the opinion is derived (including reliance placed on work by
other assurance bodies); and a statement of conformance with the PSIAS and the
results of the internal audit QAIP. 
7.5.1 Midlothian Internal Audit function has an effective reporting template which allows the
results of the Audit assignment to be clearly communicated to management. A
management summary is followed by the findings from the audit with clear links to the
recommendations section. There is also room for acknowledging good practice. 
7.5.2 The content of the report and its factual accuracy are discussed throughout the
engagement and a standard template is in place for exit meetings where positive
findings are discussed initially before other findings and recommendations. An exit
meeting takes place after every audit and before the draft report is issued. 
7.5.3 Within the overall audit opinion there is a summary included of all reports issued during
the year and the status of recommendations made.  There is a clear link between the
audit work completed during the year and the opinion given.  Management responses
Page 219 of 396

Page 220

14 
are then received for all recommendations with implementation dates and the names of
officers responsible for implementing them. 
7.5.4 Audit reports are all given assurance gradings in line with CIPFA public sector guidance.   
7.5.5 All of the stakeholder questionnaires responses confirmed that internal audit reports are
accurate, objective, clear, concise, constructive, complete and timely.   Two of the
responses indicated that internal audit reports, whether in full or abridged were not
always reported to key stakeholders and audit committee, though it was acknowledged
that they were available on request.     
Recommendation 7
The Chief Auditor should discuss the circulation of audit reports with key stakeholders
including the audit committee to ascertain their preferred format for example whether
they want all reports circulated in full or abridged versions with only key points
highlighted.   
7.5.6 Midlothian Council’s Internal Audit function generally conforms with Standard 2400 on
Communicating Results. 
7.6 2500 - Monitoring Progress 
The PSIAS place responsibility for monitoring progress with the CAE to ensure that
management actions have been effectively implemented or, if not, that senior
management have accepted the risk of not taking action.  The CAE must, therefore,
implement a follow-up process for ensuring the effective implementation of audit results
or ensuring senior management are aware of the consequences of not implementing an
action point and are prepared to accept the risk of such consequences occurring. The
results of this process should be communicated to the board.  The CAE should develop
escalation procedures for cases where agreed actions have not been effectively
implemented by the date agreed. These procedures should ensure that the risks of not
taking action have been understood and accepted at a sufficiently senior management
level. The effective involvement of the board in the follow-up process is critical to
ensuring that it works. The CAE should consider revising the internal audit opinion in
light of findings from the follow-up process.  The findings of follow-up reviews should
inform the planning of future audit work. 
7.6.1 Follow up of audit recommendations is made in two ways, a sample check on a risk
assessed basis of audit actions flagged as closed by management, and an assessment
of performance against audit actions being closed by the due date. 
7.6.2 Progress on audit actions is reported to Audit Committee or to the IJB Audit and Risk
Committee as appropriate through the year. 
7.6.3 Midlothian Council’s Internal Audit function fully conforms with Standard 2500 on
Monitoring Progress. 
7.7 2600 - Communicating the Acceptance of Risks 
When the chief audit executive concludes that management has accepted a level of risk
that may be unacceptable to the organisation, they must discuss the matter with senior
management. If the chief audit executive determines that the matter has not been
resolved, they must communicate the matter to the board. It is not the responsibility of
the chief audit executive to resolve the risk. 
7.7.1 Reports to Audit Committee and CMT are always in the Chief Internal Auditor’s name
and reported directly by them. Allied to this, the Chief Internal Auditor has a monthly
meeting with the Chief Executive and meets the Audit Committee Chair prior to every
Page 220 of 396

Page 221

15 
audit committee. There were no incidents where a recommendation was not agreed by
management and would have required escalation.     
7.7.2 The full scope of the internal audit function and its responsibilities are covered
comprehensively in the annual report, opinion and appendices.   
7.7.3 Midlothian Council’s Internal Audit function fully conforms to the Standard on
Communicating the Acceptance of Risk. 
Michelle Blair 
Chief Auditor
East Renfrewshire Council
2 June 2025
Page 221 of 396

Page 222

16 
APPENDIX A – SUMMARY OF ASSESSMENT 
REF PAGE
No. ASSESSMENT AREA
Fully
Conforms 
Generally
Conforms 
Partially
Conforms 
Does Not
Conform 
Section A  Mission of Internal Audit and Core Principles    
Section B  Definition of Internal Auditing    
Section C  Code of Ethics    
Section D  ATTRIBUTE STANDARDS 
1000  Purpose, Authority and Responsibility    
1100  Independence and Objectivity    
1200  Proficiency and Due Professional Care    
1300  Quality Assurance and Improvement Programme    
Section E  PERFORMANCE STANDARDS 
2000  Managing the internal Audit Activity    
2100  Nature of Work    
2200  Engagement Planning    
2300  Performing the Engagement    
2400  Communicating Results    
2500  Monitoring Progress    
Page 222 of 396

Page 223

17 
2600  Communicating the Acceptance of Risks    
TOTALS 8 6 0 0
Page 223 of 396

Page 224

18 
APPENDIX B – EVIDENCE PACK
• Completed EQA checklist
• Annual Report 2023/24 and 2024/25 and minute
• Organisation Chart
• Internal Audit Charter and minute 
• Follow up cover report and supporting papers  
• Annual Governance Statement 
• Clearance of objectives examples
• Procedures for updating Plan
• Annual plan 2023/2024 and minute
• Progress report examples
• Audit and Scrutiny Committee report and minute
• Details of staff qualifications 
• Confirmation of independence 
• Best Value Report (2023)  
• Employee code of conduct and HR Policies and Procedures
• Examples of audit reports
• Chief Internal Auditor and staff job description
• Confirmation of Attendance at Committee
• Training records  
• Review Points  
• Anti-fraud procedure extract and annual report
• External PSIAS assessment audit committee report (2018)
• Stakeholder questionnaires
• Interview with Auditor 
Page 224 of 396

Page 225

19 
APPENDIX C – STAKEHOLDER QUESTIONNAIRES
Stakeholder questionnaires were completed by the following key members of staff and Elected
Members:
• Grace Vickers (Chief Executive)
• Alan Turpie (Monitoring Officer, Legal and Governance Manager)
• David Gladwin (S95 Officer, Chief Financial Officer)
• Cllr Derek Milligan
• Cllr Peter Smaill
Page 225 of 396

Page 226

20 
APPENDIX D – ACTION PLAN
No.   Para  Recommendation  Management Response 
Responsible Officer
/ Agreed
Completion Date
1 6.1.3
When the Audit Charter is next reviewed it should include:
• An expanded section definitively addressing the Internal
Audit role in combatting fraud, the role and status of the
fraud team, signposting to the counter fraud and anti-
corruption policies and the arrangements for fraud to be
notified to the relevant officer/team.
• A definition of the nature of assurance services
• The roles and responsibilities of statutory officers in
relation to internal audit.
Agreed these will be added when the Audit Charter is reviewed
in March 2026. The current charter was based on the model
charter for the new GIAS standards as provided by the
Chartered Institute for Internal Audit and will be updated to
include these additional items. 
Chief Internal Auditor 
March 2026
2 6.4.3
An appropriate methodology to facilitate and document
service feedback should be developed and used to inform
ongoing service delivery.
Agreed a document has been developed in assessing the
working papers as part of the implementation of GIAS and in
accordance with the approved Quality Assurance Plan in place
and will be utilised for audits in the 2025/26 financial year. 
Chief Internal Auditor 
July 2025
3 6.4.5
A performance measurement methodology should be
developed to evaluate the internal audit function’s
performance against its objectives.
Agreed, a review will be undertaken to establish appropriate
KPI’s in accordance with the GIAS guidance and in
benchmarking with other Local Authority audit teams to
attempt to find meaningful targets. These will be set and then
monitored from the next strategy and plan approval. 
Chief Internal Auditor 
March 2026
4 7.1.7
The Audit Strategy and specifically the planning document
for each individual audit should reflect the annual plan link to
the overall strategic objectives of the Council.
The Link to strategy will be included in the individual audit
planning document and reflected more specifically in the
Internal Audit Strategy prior to its next approval at Audit
Committee.   
Chief Internal Auditor 
March 2026
5 7.1.8
The Chief Auditor should consider developing an assurance
mapping methodology to provide clarity around the internal
audit planning and reporting approach
Agreed this was raised with Audit Committee within the
Charter paper in March 2025 and will be progressed within the
resources available a methodology for developing being in
place during 2025/26. 
Chief Internal Auditor 
March 2026
6 7.3.1
The Terms of Reference Document should be expanded to
include any exclusions from the scope of the work and
consideration of the resources allocated, whilst recognising
that the choice of resources is limited.
Agreed the TOR was updated for GIAs compliance to include
this and will operate for the 2025/26 audits as current
resourcing really only allows for a choice of one Auditor or the
other one we can record that choice in the TOR. 
Chief Internal Auditor 
July 2025
7 7.5.5
The Chief Auditor should discuss the circulation of audit
reports with key stakeholders including the audit committee
to ascertain their preferred format for example whether they
Agreed this will be included in the Audit Committee self-
evaluation for reporting to Audit Committee in September
2025. 
All Audit Committee
members and the
Chief Internal Auditor 
Page 226 of 396

Page 227

21 
want all reports circulated in full or abridged versions with
only key points highlighted.
September 2025 
Critical 
Significant 
Routine 
Page 227 of 396

Page 228

Page 228 of 396

Page 229

Audit Committee
Monday 16 June 2025
Item No 5.10 
Draft Annual Governance Statement 2024/25 
Report by Chief Executive 
Report for Decision 
1 Recommendations 
The Audit Committee is asked to:  
a) Consider the details of the draft Annual Governance Statement
2024/25 at Appendix 1 to ensure it reflects the risk environment
and governance in place to achieve objectives, and acknowledge
the actions identified by Management to improve internal controls
and governance arrangements; and 
b) Approve that it be published in the Council’s Statement of Accounts
2024/25, noting the requirement for the final Annual Governance
Statement to be signed by the Chief Executive and Leader of the
Council at the conclusion of the external audit process. 
2 Purpose of Report/Executive Summary 
The purpose of this report is to propose that the Audit Committee
considers and approves the draft Annual Governance Statement that
will be published in the Council’s Statement of Accounts 2024/25. 
Midlothian Council is responsible for ensuring that its business is
conducted in accordance with the law and proper standards, and that
public money is safeguarded and properly accounted for, and used
economically, efficiently and effectively. 
The Council’s Local Code of Corporate Governance that was approved
by Council on 23 March 2021 was used to assist with the annual
assurance process 2024/25. 
The draft Annual Governance Statement 2024/25, which is appended
to this report as Appendix 1 for consideration, is the output from the
annual assurance process and review against the Local Code. 
Date 2 June 2025 
Report Contact:
Duncan Stainbank
duncan.stainbank@midlothian.gov.uk  
Page 229 of 396

Page 230

2
3 Background 
3.1 Midlothian Council is responsible for ensuring that its business is
conducted in accordance with the law and proper standards, and that
public money is safeguarded and properly accounted for, and used
economically, efficiently and effectively. 
3.2 Fundamentally, Corporate Governance is about openness, integrity
and accountability. It comprises the systems and processes, and
cultures and values by which the authority is directed and controlled
and through which it accounts to, engages with and, where appropriate,
leads its communities. 
4 Annual Assurance Process 2024/25 
4.1 The CIPFA/SOLACE Framework urges local authorities to review the
effectiveness of their existing governance arrangements against their
Local Code and prepare a governance statement and report
compliance on an annual basis. 
4.2 The Audit Committee is integral to overseeing independent and objective
assurance and monitoring improvements in internal control and
governance. Its Terms of Reference includes ‘To review the Annual
Governance Statement prior to approval and consider whether it
properly reflects the risk environment and supporting assurances’. 
4.3 The Internal Audit function undertook an assessment of the Local Code
of Corporate Governance and identified areas of further improvement
to enhance the effectiveness of internal control and governance
arrangements and compliance against the Local Code. 
4.4 Progress with implementation of actions regarding previously identified
improvement areas of governance has also been evaluated.   
4.5 The draft Annual Governance Statement 2024/25 at Appendix 1, in
compliance with the CIPFA/SOLACE Framework, provides details of
the Council’s Governance Framework, the annual Review of
Framework undertaken, Improvement Areas of Governance, and
Overall Opinion. 
4.6 It is the Chief Executive’s opinion that reasonable assurance can be
placed upon the adequacy and effectiveness of Midlothian Council’s
systems of internal control and governance. Although areas for further
improvement have been identified, the annual review demonstrates
sufficient evidence that the Council’s Local Code of Corporate
Governance is operating effectively, and that the Council complies with
that Local Code in most respects to meet its principal objectives.
Systems are in place to regularly review and improve governance
arrangements and the system of internal control. 
4.7 The draft Annual Governance Statement 2024/25 is informed by the
assessment of compliance against the Local Code, written assurance
statements from the Executive Directors, Internal Audit annual opinion
and findings and recommendations, and comments and
Page 230 of 396

Page 231

3
recommendations made by External Auditor and other external scrutiny
bodies and inspection agencies. 
5 Report Implications (Resource, Digital, Risk and Equalities) 
5.1 Resource 
The overall aim of the CIPFA/SOLACE Framework ‘Delivering Good
Governance in Local Government’ (2016), on which Midlothian
Council’s Local Code of Corporate Governance is framed, is to ensure
that:
• resources are directed in accordance with agreed policy and
according to priorities;
• there is sound and inclusive decision making; and
• there is clear accountability for the use of those resources in order
to achieve desired outcomes for service users and communities. 
Core principle of good governance “E. Developing the entity’s capacity,
including the capability of its leadership and the individuals within it” is
included within the CIPFA/SOLACE Framework. Workforce and elected
member development are a key part of the good governance
framework within the Council’s Local Code of Corporate Governance. 
5.2 Digital 
There are no digital implications arising from this report. 
5.3 Risk 
The Local Code of Corporate Governance ensures that internal
controls, risk management and other governance arrangements reflect
the arrangements in place on an evidence-basis. The draft Annual
Governance Statement 2024/25 details areas where additional work
would further enhance the internal control environment or improve risk
management and corporate governance arrangements. 
Core principle of good governance “F. Managing risks and performance
through robust internal control and strong public financial management”
is included within the CIPFA/SOLACE Framework. Midlothian Council’s
Local Code of Corporate Governance sets out evidence of systems,
processes and documentation to demonstrate local compliance with
this core principle of good governance. 
5.4 Ensuring Equalities 
This report does not relate to a new or revised policy, service or budget
change, which affects people (the public or staff), so an Integrated
Impact Assessment (IIA) is not an applicable consideration. 
The application of equalities legislation within practices is set out in
Midlothian Council’s Local Code of Corporate Governance to
demonstrate compliance of core principle of good governance “A.
Behaving with integrity, demonstrating strong commitment to ethical
values, and respecting the rule of law”.
Page 231 of 396

Page 232

4  
5.5 Additional Report Implications (See Appendix A) 
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Good governance is important to enable Midlothian Council to deliver
its key priorities in support of achieving the Council’s objectives as set
out in the Single Midlothian Plan (Reducing the gap in economic
circumstances; Reducing the gap in learning outcomes; Reducing the
gap in health outcomes; and Reducing the impact of climate change). 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working  
Hub and Spoke  
Modern  
Sustainable  
Transformational  
Preventative  
Asset-based  
Continuous Improvement  
One size fits one 
None of the above 
Midlothian Council is committed to creating a great place to grow
supported by the 9 drivers for change. Implementing the 9 drivers for
change in practice is embedded in the Council’s Local Code of
Corporate Governance to assist the Council in achieving its objectives. 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you  
Preventative and Sustainable  
Efficient and Modern  
Innovative and Ambitious 
A.4 Delivering Best Value 
The overall aim of the CIPFA/SOLACE Framework ‘Delivering Good
Governance in Local Government’ (2016), on which Midlothian
Council’s Local Code of Corporate Governance is framed, is to ensure
that: resources are directed in accordance with agreed policy and
according to priorities; there is sound and inclusive decision making;
and there is clear accountability for the use of those resources in order
to achieve desired outcomes for service users and communities. 
Page 232 of 396

Page 233

5
This will enable the Council to fulfil its obligations to provide best value
service delivery to its citizens. 
A.5 Involving Communities and Other Stakeholders 
Core principle of good governance “B. Ensuring openness and
comprehensive stakeholder engagement” is included within the
CIPFA/SOLACE Framework. Midlothian Council’s evidence of systems,
processes and documentation to demonstrate local compliance with
this core principle of good governance is set out in its Local Code of
Corporate Governance. 
The Council’s Corporate Management Team was engaged in the
review and finalisation of the updated Local Code of Corporate
Governance (approved by Council on 23 March 2021), and the update
of the evidence to demonstrate good governance which reflects the
current operating environment. 
A.6 Impact on Performance and Outcomes 
The annual self-assessment and the identification of improvement
actions as evidenced through the draft Annual Governance Statement
2024/25 are designed to enhance the internal control environment, and
risk management and corporate governance arrangements. 
This demonstrates the core principle of good governance “G.
Implementing good practices in transparency, reporting, and audit to
deliver effective accountability” included within the CIPFA/SOLACE
Framework. 
A.7 Adopting a Preventative Approach 
Core principle of good governance “D. Determining the interventions
necessary to optimise the achievement of the intended outcomes” is
included within the CIPFA/SOLACE Framework. Prevention
governance arrangements are a key part of the good governance
framework within the Council’s Local Code of Corporate Governance. 
A.8 Supporting Sustainable Development 
Core principle of good governance “C. Defining outcomes in terms of
sustainable economic, social, and environmental benefits” is included
within the CIPFA/SOLACE Framework. Midlothian Council’s evidence
of systems, processes and documentation to demonstrate local
compliance with this core principle of good governance is set out in its
Local Code of Corporate Governance. 
Page 233 of 396

Page 234

Page 234 of 396

Page 235

Draft Annual Governance Statement 2024/25
Introduction
The Annual Governance Statement explains how the Council has complied with the terms of the
CIPFA/SOLACE Framework (2016) for the year ended 31 March 2025, sets out the Council’s
governance arrangements and systems of internal control, and reports on their effectiveness. The
statement also covers relevant governance matters as they affect those entities included as part of
the Council’s Group Accounts.
Scope of Responsibility 
Midlothian Council is responsible for ensuring that its business is conducted in accordance with the
law and proper standards, and that public money is safeguarded and properly accounted for. The
Council also has a statutory duty of Best Value under the Local Government in Scotland Act 2003 to
make arrangements to secure continuous improvement and performance, while maintaining an
appropriate balance between quality and cost; and in making these arrangements and securing that
balance, to have regard to economy, efficiency and effectiveness.
In discharging this overall responsibility, elected members and senior officers are responsible for
putting in place proper arrangements for the governance of Midlothian Council’s affairs and
facilitating the exercise of its functions in a timely, inclusive, open, honest and accountable manner.
This includes setting the strategic direction, vision, culture and values of the Council, effective
operation of corporate systems, processes and internal controls, engaging with and, where
appropriate, lead communities, monitoring whether strategic objectives have been achieved and
services delivered cost effectively, and ensuring that appropriate arrangements are in place for the
management of risk.
The system can only provide reasonable and not absolute assurance of effectiveness.
Framework for Good Governance
The overall aim of the CIPFA/SOLACE Framework ‘Delivering Good Governance in Local
Government’ (2016) is to ensure that: resources are directed in accordance with agreed policy and
according to priorities; there is sound and inclusive decision making; and there is clear accountability
for the use of those resources in order to achieve desired outcomes for service users and
communities.
The Framework defines the seven core principles of good governance, namely:
A.  Behaving with integrity, demonstrating strong commitment to ethical values, and respecting
the rule of law;
B.  Ensuring openness and comprehensive stakeholder engagement;
C.  Defining outcomes in terms of sustainable economic, social, and environmental benefits;
D.  Determining the interventions necessary to optimise the achievement of the intended
outcomes;
E.  Developing the entity’s capacity, including the capability of its leadership and the individuals
within it;
F.  Managing risks and performance through robust internal control and strong public financial
management; and
G. Implementing good practices in transparency, reporting, and audit to deliver effective
accountability.
The Council’s Local Code of Corporate Governance, which is consistent with the principles and
recommendations of the CIPFA/SOLACE Framework and the supporting guidance notes for Scottish
authorities (November 2016), was approved by Council in March 2021.  
Page 235 of 396

Page 236

The Council’s Governance Framework 
The key elements of the Council’s governance arrangements, as set out in the Council’s Local Code
of Corporate Governance, include:
A. Behaving with integrity, demonstrating strong commitment to ethical values, and respecting rule of law
The roles and responsibilities of elected members and officers and the processes to govern the
conduct of the Council’s business are defined in the Elected Members Code of Conduct, standing
orders and scheme of delegation for officers, scheme of administration, and financial regulations.
Codes of conduct are in place for and define the high ethical values and standards of behaviour
expected from elected members and officers to make sure that public business is conducted with
fairness and integrity.
The Monitoring Officer is responsible for ensuring that agreed procedures are followed and that all
applicable statutes and regulations are complied with. The Standards Committee is responsible for
dealing with matters relating to conduct and ethical standards.
The Council seeks feedback from the public through its complaints and complements procedures for
all of the Council which responds to the outcomes, as appropriate, and reports the results annually.
Professional advice on the discharge of statutory social work duties was provided during the year to
the Council by the Chief Social Work Officer (CSWO). The CSWO promotes values and standards
of professional practice and acts as the 'agency decision maker' taking final decisions on a range of
social work matters including adoption, secure accommodation, guardianship, etc. The CSWO
reports annually on the statutory work undertaken, regulation and inspection, workforce issues and
significant social policy themes.
B. Ensuring openness and comprehensive stakeholder engagement
All meetings of the Council and its Committees are held in public with the exception of items for
discussion that are exempt under the Local Government (Scotland) Act 1973. All Council and
Committee meetings are hybrid and webcast to ensure public access, and recordings can be
accessed from the Council’s website.
Unless confidential, decisions made by Council or other Committees are documented in the public
domain. All decisions are explicit about the criteria, rationale and considerations used. The impact
and consequences of all decisions are clearly set out.
The Council seeks community views on a wide range of issues and undertakes regular consultation
and engagement with citizens and service users, including the public consultation on the Medium
Term Financial Strategy 2025/26 to 2028/29 reported to the December 2024 Council meeting.  
C. Defining outcomes in terms of sustainable economic, social, and environmental benefits
The Council’s vision, strategic objectives and priorities are set out in the Single Midlothian Plan
developed through the Community Planning Partnership (of which the Council is a partner). The
Council’s Medium Term Financial Strategy and Service Plans outline how Midlothian Council will
deliver its contribution to the Single Midlothian Plan. In June 2023 the Council also approved a
Transformation Blueprint 2023-2028 to support the Medium Term Financial Strategy and help bridge
a projected five-year funding gap. Progress against this blueprint is reported to Council on a quarterly
basis along with progress on the Medium Term Financial Strategy which was updated for the period
2025/26 to 2028/29 in October 2024.Progress is also reviewed at 4 weekly BTB’s and reported to
BTSG as a Standing Item.  
Capital investment at a strategic level is structured to consider and balance the combined economic,
social and environmental impact of policies and plans when taking decisions about service provision.
Asset management planning is being developed to support this, although it is recognised that this
process needs to be accelerated to meet the needs of the growing Council area. 
The Council considered the recommendation of the February 2024 Aether Climate Action Support
Report in November 2024 and has instructed a refresh of the Council’s Climate Change Strategy. 
The Council approved the Economic Growth Strategy 2025-30 in November 2024, which has been
reviewed to align with the Scottish Government National Strategy for Economic Transformation
and the Edinburgh and South East Scotland City Region Deal Regional Prosperity Framework. 
The Council supports community empowerment and recognises the importance of building
community capacity and volunteering as a key factor in building stronger, safer, and supportive
communities. 
Page 236 of 396

Page 237

Implications are considered during the decision-making process within the standard report template
covering Resources, Risk, Single Midlothian Plan and Key Priorities, Impact on Performance and
Outcomes, Adopting a Preventative Approach, Involving Communities and Other Stakeholders,
Ensuring Equalities, Supporting Sustainable Development, and IT issues.
D. Determining the interventions necessary to optimise the achievement of the intended outcomes
Decision makers receive detailed information indicating how intended outcomes would be achieved
together with the risks, financial and other implications associated with the proposals, by way of the
compulsory sections of the Committee report template.
In determining how services and other courses of action should be planned and delivered, the
Council is increasingly engaging with internal and external stakeholders. The Council fosters
effective relationships, collaborative working and contractual arrangements with other public, private,
and voluntary organisations in delivering services that meet the needs of the local community
including the achievement of ‘social value’ (community benefits) through service planning and
commissioning.
E. Developing the entity’s capacity, including the capability of its leadership and the individuals within it
The roles of officers are defined in agreed job descriptions. Staff performance is reviewed on an
annual basis in accordance with the relevant appraisal processes in place during the year. In
December 2024, the Council approved the Midlothian Council Workforce Strategy 2024 to 2034
developed using an evidence-based management approach engaging with stakeholders and
employees via an employee survey. 
The Chief Executive is responsible and accountable to the Council for all aspects of management
including promoting sound governance, providing quality information/support to inform decision
making and scrutiny, supporting other statutory officers, and building relationships with all
Councillors.
The Elected Members Induction Programme took place following elections in May 2022 and is
periodically supplemented by training events, seminars and briefings. Members appointed to certain
committees have also received specific training related to the responsibilities on these committees
e.g. licensing, planning, audit.
F. Managing risks and performance through robust internal control & strong public financial management
The Council has overall responsibility for directing and controlling the organisation. The Cabinet is
the principal decision-making committee of the Council. The Performance, Review and Scrutiny
Committee is responsible for reviewing performance against policy objectives and commenting on
decisions and policies and their impact.
The Council updated its Risk Management policy and strategy in August 2022 whose main priorities
are the robust systems of identification, evaluation and control of risks which threaten the Council’s
ability to meet its objectives to deliver services to the public. Internal Audit’s assessment in March
2024 was that assurance is substantial in relation to the Council’s Risk Management Policy and
application of the policy at a strategic level, however significant further progress is required on the
Service level risk management framework. 
The Chief Financial Officer (the Section 95 officer) is responsible for the proper administration of all
aspects of the Council’s financial affairs including ensuring appropriate advice is given to the
Council on all financial matters. 
The Council’s system of internal financial control is based on a framework of financial regulations
(updated in June 2022), regular management information, administrative procedures (including
segregation of duties), management supervision and a system of delegation and accountability.
This remains reliant on the staff within the framework to ensure management supervision and
accountability are diligently enforced. 
The Council has an approved strategy to tackling fraud, theft, corruption and crime, as an integral
part of protecting public finances, safeguarding assets, and delivering services effectively.
A revised Medium Term Financial Strategy continues to be monitored and updated on a regular
basis with the latest 2025/26 to 2028/29 strategy being approved by Council in February 2025. 
Given the significant fiscal challenges which lie ahead, the Council continues to regularly monitor
the Transformation Blueprint workstreams aligned to the Medium Term Financial Strategy. This will
then inform the revised service plans, workforce plans and the long term sustainability of services.
A Balanced budget was set by Council in February 2025 for the 2025/26 financial year by increasing
Page 237 of 396

Page 238

Council tax by 10% and utilisation of £4.1 million of reserves, with indicative increases of Council tax
of, 9%, 8% and 5% in the following 3 financial years and continued utilisation of reserves of
£4.1milllion in the following 2 years the budget gap by 2028/29 becomes £8.9million. Highlighting
the unprecedented financial pressure on the Council and some of the difficult decisions to be made
in relation to both Capital and Revenue Budgets to establish a sustainable financial position. 
The previous Chief Officer Corporate Solutions carried out a self-assessment against the CIPFA FM
code and reported the findings of this to CMT in September 2021 and this was subsequently reported
to Audit Committee in December 2021.  The Chief Officer Corporate Solutions identified six areas
requiring improvement from his review of the CIPFA FM code.  Actions identified included improving
the resourcing of the Procurement team (ongoing), updating the Council’s Financial Regulations and
Directives (complete – approved at June 2022 Council), putting in place a multi-year financial plan
(ongoing – action relevant to two sections of the FM Code), improving the Council’s approach to
lessons learned from completed projects (ongoing), and improving the Council’s risk management
arrangements (ongoing). No further Committee update has been provided within the 2024/25
financial year.   
Revenue and Capital Budget Monitoring reports are presented to the Council on a quarterly basis
for monitoring and control purposes including the annual outturn. The Management Commentary in
the Statement of Accounts provides financial and other performance information regarding the
operation of the Council, its wider achievements and areas for development. The Internal Audit of
Budget Monitoring highlighted that the Council element of the IJB spend, being adult social work
expenditure, needed to be included in the revenue budget monitoring figures and whilst this had
been verbally updated to Council during the 2024/25 financial year, and formally reported to the
Midlothian IJB Board with links provided to this publicly available information within the quarterly
reports, these figures will now be included in the monitoring for the 2025/26 financial year.
On 10 January 2025, the Accounts Commission wrote in a letter to all Chief Executives of Scottish
Local Authorities, copying in Directors of Finance and external auditors highlighting the report of 12
December 2024 relating to a significant council tax fraud perpetrated against Aberdeen City Council.
Highlighting the Chief Executive’s responsibility to ensure arrangements are in place to help assure
elected members and the public that risks are being identified and managed effectively. The letter
encouraged all Chief Executives to use the annual governance statement as an opportunity to take
stock of the key controls and processes and whether self-assessment procedures are sufficient to
provide elected members and officers with the required assurances. A review of the Council Tax
processes within Midlothian Council has been completed and highlighted that in relation to Council
Tax refunds the system did not provide adequate segregation of duties controls and there was not
an appropriate monitoring regime in place. Subsequent sample testing identified no evidence of fraud
within the 2024/25 financial year. Work is now ongoing with the supplier and within the service to
rectify these issues.  
G. Implementing good practices in transparency, reporting, & audit to deliver effective accountability
The independent and objective audit opinion of the Chief Internal Auditor (Chief Audit Executive) is
stated within the Internal Audit Annual Assurance Report 2024/25. This is based on work carried out
by an in-house team, including shared service resources from East Lothian Council for the Chief
Internal Auditor, in conformance with the Public Sector Internal Audit Standards to fulfil statutory
Internal Audit provision.
The Council responds to the findings and recommendations of Internal Audit, External Audit, Scrutiny
and Inspection bodies including associated Action Plans for improvement. The Audit Committee is
integral to overseeing independent and objective assurance and monitoring improvements in internal
control and governance.
Quarterly Performance Reports were presented to Cabinet and the Performance, Review and
Scrutiny Committee for monitoring the achievement of strategic priorities and key performance
indicators.
The Annual Accounts and Report sets out the financial position in accordance with relevant
accounting regulations. 
Review of Adequacy and Effectiveness of the Council’s Governance Framework
An annual review of the adequacy and effectiveness of the Council’s overall governance framework
has been carried out. The output is this Annual Governance Statement which is presented to the
Audit Committee.
Page 238 of 396

Page 239

The review was further informed by assurances from: assessment of compliance against the Local
Code; written assurance statements from the Executive Directors; Internal Audit annual opinion,
findings and recommendations; and comments and recommendations made by External Auditor and
other external scrutiny bodies and inspection agencies.
Improvement Areas of Governance
The collective review activity outlined above has identified the following areas where improvement
in governance arrangements can continue to be made to enhance compliance with the Council’s
Local Code of Corporate Governance and to demonstrate Best Value: 
1) The previous Chief Officer Corporate Solutions carried out a self-assessment against the CIPFA
FM code and reported the findings of this to CMT in September 2021 and this was subsequently
reported to Audit Committee in December 2021. One of the actions identified was putting in
place a multi-year financial plan. The Council subsequently approved a 2023-2028 Strategic
Blueprint in June 2023, aligned to the Medium Term Financial Strategy. The Medium Term
Financial Strategy 2025/26 to 2028/29 approved in October 2024 highlighted that the budget
gap for 2025/26 incorporating planned use of service concession retrospection and a 5%
Council Tax increase was projected to £9.4million rising to £20.6million by 2028/29. A Balanced
budget was set by Council in February 2025 for the 2025/26 financial year by increasing Council
tax by 10% and utilisation of £4.1 million of reserves, with indicative increases of Council tax of,
9%, 8% and 5% in the following 3 financial years and continued utilisation of reserves of
£4.1milllion in the following 2 years the budget gap by 2028/29 becomes £8.9million. Working
towards that sustainable position has been significant during the year, however further ongoing
work is required and there were also 15 risks noted to this strategy that could impact on the
current position, including the MIJB finances with management highlighting that the level of
financial resource available to both partners is not reflective of the current level of demand to
maintain services on a sustainable basis. Work will continue during 2025/26 towards a
sustainable financial position over a multiyear period. 
2) The Procurement Service continues to face recruitment challenges and despite multiple
recruitment attempts was unable to secure a permanent Procurement Manager for 2024/25. A
permanent Procurement Manager was appointed at the end April 2025, and the work plan is
being developed for improvements to the service for the 2025/26 reporting year. Issues arising
from the reduced team capacity are the off contract spend, and non-contracted spend within the
organisation, chief officers are continuing to report impacts to the delivery of services. Expired
contracts and off contract spend is being managed through regular review at Budget Boards to
ensure that the risk is managed, and the appropriate remedial action is being taken, with
oversight from the Executive Director and Chief Officers. In addition, commissioning and
contract management are both focused areas of the Transformation Blueprint. 
3) Capital plan affordability continues to be worked through as part of the Capital Plan prioritisation
exercise, which was considered by Council in February 2025, alongside approval of new
projects to the General Services Capital Plan and noting the expenditure and funding levels
shown in the GSCP for 2024/25 to 2028/29 prior to reaching a financially sustainable outcome.
Within that paper, it is noted that in developing the strategy and taking cognisance of the longer
term affordability gap, it is clear that a number of potential projects which are currently included
will only be able to be progressed if they can be delivered on a spend to save basis or where
they can be delivered on a cost neutral basis or through alternative funding mechanisms. Whilst
approval for fully funded learning estates projects has been progressed, delays in decision to
critical projects may result in breaches of capacity to provide education provision across the
Council area. The condition of certain schools is deteriorating, and significant investment is
required in order to ensure all schools meet at least condition B standard. Changes to the
leadership and management of the learning estate delivery programme are being worked
through. It is also noted that there is ongoing development of the Council’s asset management
across fleet, property and infrastructure to manage and invest in the portfolios effectively. 
4) During the year there has been insufficient recording and reporting by services on service level
risk registers and business continuity plans. There is a requirement to ensure that there is a one
system approach to aligning business continuity planning across NHS and Midlothian Council
including cybersecurity planning to ensure all critical services can be maintained at times of
incidents. Training is being delivered to staff within services in relation to risk management and
there has been involvement of contracted resource in the Children, Young People and
Partnerships directorate. Outstanding Internal Audit recommendations to report to Audit
Page 239 of 396

Page 240

Committee on the delivery of service risk registers and the review of business continuity
resourcing, and completion of plans should result in an improvement in the control environment.
5) Deficiencies in the control environment for Council Tax within systems controls and monitoring
of refunds are being resolved in conjunction with the systems supplier and ongoing monitoring
will be implemented. The Counter Fraud team are intending to establish a risk assessment
process for the Council to identify areas of risk and work with services for them to implement
appropriate mitigations across the Council, specifically on the risk of fraud. 
Prior Year Improvement Areas of Governance Implemented 
The 2023/24 Annual Governance Statement for Midlothian Council contained the following areas of
improvement all of which have been taken forward: 
1) It was highlighted that the Council over the next 5 years required an approved multi-year financial
plan key to developing the Council on a sustainable basis. The Medium Term Financial Strategy
2025/26 to 2028/29 approved in October 2024 highlighted that the budget gap for 2025/26
incorporating planned use of service concession retrospection and a 5% Council Tax increase
was projected to £9.4million rising to £20.6million by 2028/29. A Balanced budget was set by
Council in February 2025 for the 2025/26 financial year by increasing Council tax by 10% and
utilisation of £4.1 million of reserves, with indicative increases of Council tax of, 9%, 8% and 5%
in the following 3 financial years and continued utilisation of reserves of £4.1milllion in the
following 2 years the budget gap by 2028/29 becomes £8.9million. Working towards that
sustainable position has been significant during the year, however further ongoing work is
required and there were also 15 risks noted to this strategy that could impact on the current
position. 
2) Improvements in Procurement Service Capacity have been enacted within the 2024/25 financial
year, however obtaining and maintaining resources within the Procurement team remains a
workforce challenge.  A solution is currently in place however services have highlighted that the
procurement workload has increased, and a planned approach will now need to be implemented
over a significant period of time, which will require support across the Council. 
3) Capital plan affordability continues to be worked through as part of the Capital Plan prioritisation
exercise, which was considered by Council in February 2025, alongside approval of new projects
to the General Services Capital Plan and noting the expenditure and funding levels shown in the
GSCP for 2024/25 to 2028/29 prior to reaching a financially sustainable outcome. Within that
paper it is noted that the in developing the strategy and taking cognisance of the longer term
affordability gap, it is clear that a number of potential projects which are currently included will
only be able to be progressed if they can be delivered on a spend to save basis or where they
can be delivered on a cost neutral basis or through alternative funding mechanisms. A Capital
plan prioritisation paper with options for consideration was also considered at the February 2025
Council and further work will be required to deliver a long-term sustainable solution.  
4) In December 2024, the Council approved the Midlothian Council Workforce Strategy 2024 to
2034 developed using an evidence-based management approach engaging with stakeholders
and employees via an employee survey. Additional resources were deployed during 2024/25 to
improve the Council’s position in relation to Council Tax and Housing Benefit processing and
within the compliance environment to meet statutory reporting responsibilities, work is ongoing
to provide long term sustainable staffing in this area. The Council is currently subject to a Level
2 intervention from the Scottish Information Commissioner (SIC) in respect of its response rates
for Freedom of Information requests. An action plan has been created and being delivered to
improve the current position, with regular reporting to the Corporate Management Team (CMT).
The Chief Officer Corporate Solutions, the Legal and Governance Manager and the Lead
Performance and Improvement Officer (Place) meet the SIC on a monthly basis to monitor and
evaluate progress on the improvement plan. Feedback from the SIC is that significant sustained
improvement is demonstrated, and it is expected that the intervention will be removed Summer
2025. 
Conclusion and Opinion on Assurance 
The conclusion from the review activity completed and subject to the successful progression of the
areas for improvement highlighted above, our opinion is that reasonable assurance given financial
constraints can be placed upon the adequacy and effectiveness of Midlothian Council’s systems of
Page 240 of 396

Page 241

governance, risk management and internal control. Although areas for further improvement have
been identified, the annual review demonstrates sufficient evidence that the Council’s Local Code of
Corporate Governance is operating effectively and that the Council complies with that Local Code in
most respects to meet its principal objectives. Systems are in place to regularly review and improve
governance arrangements and the system of internal control. 
_______________________ ______________________ 
Dr Grace Vickers Kelly Parry
Chief Executive Leader of the Council
** September 2025 ** September 2025
Page 241 of 396

Page 242

Page 242 of 396

Page 243

Audit Committee
Monday 16 June 2025
Item 5.11 
Risk Management Update – Strategic Risk Profile Quarter 4, 2024-25 
Report by Derek Oliver, Chief Officer Place 
Report for Information 
1 Recommendations 
Audit Committee is recommended to: 
• Note the current risk landscape and organisational response to
the most significant risks in Quarter 4, 2024-25 (1st Jan to 31st
March 2025). 
2 Purpose of Report/Executive Summary 
The purpose of this report is to provide Audit Committee with: 
• An update on the risk responses Midlothian Council has
implemented during Q4 2024/25 to respond to the current risk
climate
• Assurance that Midlothian Council took a proportionate and
planned approach to prepare and respond to the current risk
climate
• The risk evaluation of current strategic risks and opportunities
for the Council 
31st May 2025 
Report Contact:
Derek Oliver, Chief Officer Place
Derek.Oliver@midlothian.gov.uk 
Page 243 of 396

Page 244

2 
3 Q4 Risk Management Overview 
3.1 Midlothian Council has delivered a wide range of services to the people
of Midlothian throughout Quarter 4, 2024-25. 
3.2 The Council continues to manage and review risks recorded within the
Strategic Risk Profile. The work required to maintain the necessary
corporate oversight over the broader strategic landscape continues
through the Risk and Resilience Chief Officer Group and Corporate
Management Team (CMT). 
3.3 Audit Committee should note that there were no new risks added from
the previous Quarter however, as per the request from Audit
Committee, the Strategic Opportunities section was revised to include
Strategic Projects.  The Projects included have a Red category across
their respective Risk Evaluation. Updates on actions taken are included
in the full strategic risk profile (Appendix B). 
3.4 Strategic Risk Profile (SRP) 
The SRP is split into three sections:
• Strategic issues
• Strategic risks
• Opportunities 
3.5 STRATEGIC ISSUES - SUMMARY 
Strategic issues Likelihood Impact Score Evaluation 
Q4 Q3
The Change Programme 5 5 25 Critical Critical
Financial Sustainability 5 5 25 Critical Critical 
3.6 The Change Programme 
The Change Programme remains evaluated at Critical. The financial
challenges of the forecasted budget gap pose a significant challenge
for benefits realisation. Council agreed to a Transformation Blueprint in
June 2023 which is a 5-year transformation plan. 
3.7 Financial Sustainability 
The scale of the financial challenge continues to be reported to the
Business Transformation Steering Group and Council. 
Page 244 of 396

Page 245

3 
3.8 STRATEGIC RISKS – SUMMARY 
Strategic Risks Likelihood Impact Score Evaluation
Q4 24-25  Q3 24-25
Climate Change 5 5 25 Critical  Critical
Financial Sustainability in
future years 5 5 25 Critical  Critical
The Long-Term Change
Programme 5 5 25 Critical  Critical
Legal and Regulatory
compliance 5 5 25 Critical  Critical
UK decision to leave the EU 4 5 20 High  High
Scottish Child Abuse Inquiry 4 4 16 High  High
Growing Council 4 4 16 High  High
Cost of Living Crisis 3 5 15 Medium  Medium
Asset Management 3 5 15 Medium  Medium
Cyber Security 3 5 15 Medium  Medium
Health and Safety 3 5 15 Medium  Medium
Care at Home 3 4 12 Medium  Medium
Employee performance 3 4 12 Medium  Medium
Emergency planning and
business continuity 3 4 12 Medium  Medium
Governance and Standards 2 4 8 Low  Low
Internal control environment 2 3 6 Low  Low
Corporate policies and
strategies 2 3 6 Low  Low 
3.9     STRATEGIC RISKS – RATED CRITICAL/HIGH 
3.10 Climate Change 
Councillors were presented with a briefing on the Climate Action Plan
in Q2 24-25 as committed to through the Transformation Blueprint. 
With a report presented to October Council, Councillors approved,
given the challenges (particularly financial), the realignment of the
target deadline of 2030 for net zero emissions from the Midlothian
Council estate to 2045.   
.
Page 245 of 396

Page 246

4 
In light of this, a refresh of the Council’s Climate Change Strategy,
approved by Council in August 2020, is progressing. 
3.11 Financial Sustainability in future years 
The scale of the financial challenge continues to be reported to
Business Transformation Steering Group and Council. 
3.12 The Long-Term Change Programme
The Change Programme has remained at Critical for the last 2 years.
The financial challenges of the underlying budget gap pose a
significant challenge. Council agreed to a Transformation Blueprint in
June 2023 which is a 5-year transformation plan. 
3.13 Legal and Regulatory compliance
Significant resourcing pressures have impacted on risk evaluation. 
Work is ongoing with the Scottish Information Commissioner and
National Records of Scotland to develop and deliver improvement
plans. 
3.14 UK decision to leave the EU 
The rate of inflation is impacting on the cost-of-living crisis for
Midlothian residents and posing significant risk to a number of Council
Capital Programme work streams. This was reported to the Business
Transformation Steering Group (BTSG) and also through progress
reports on programmes to Council.  A new Economic Strategy was
approved by Council in October.  This risk evaluation remains High. 
3.15 Scottish Child Abuse Inquiry (SCAI)
The SCAI risk evaluation remains High as the Inquiry continues. 
3.16 Growing Council
The risk evaluation remains High in Q4 2024-25. This is in response to
the current financial challenge as described above and the increased
pressure the Council faces with growth. Some current examples of this
include:
• Inflationary impact on the delivery of the capital programme
• Cost of living crisis 
• Pressure on the care sector as people are living longer and
require more care provision
• General population growth places additional demand on
infrastructure such as GPs, schools, waste services etc.
Page 246 of 396

Page 247

5 
3.17 Work is ongoing to review the Learning Estate Strategy and a
reprioritisation of the Capital Programme.  
3.18 STRATEGIC OPPORTUNITIES 
3.19 Capital Projects - Housing
Projects impacted with 26% reduction in Affordable Housing Supply
Programme grant to Midlothian and continued high build costs.  Phase
5 housing programme has been reviewed to ensure affordability within
the Housing Revenue Account, allowing for reduced levels of grant. 
Projects highlighted with specific Red Risk Evaluation(s) and detailed
within the SRP are Edmonstone Road, Shawfair and Newton Church
Road, Danderhall, with the latter having now commenced. 
3.20 Capital Projects – Transport, Net Zero & Infrastructure
Cost of delivering enabling infrastructure projects has risen, resulting in
significant funding gap emerging and impacting on progress of A701
Relief Road, Sustainable Transport Corridor and Straiton Junction
Improvements, which are detailed within the SRP. 
3.21 Capital Projects – Children, Young People & Partnerships Estates
Programme: Primary
Five specific projects identified within the SRP:
1. Mayfield/St Lukes PS New Build: Programme delayed for project
revision. 
2. Mauricewood PS Extension & Refurbishment: Rising roll and
catchment review requires investment in school to address capacity
and suitability. Limited budget available.  
3. Bilston PS Extension: Rising roll and catchment review requires
investment in school to address capacity and suitability. Limited
budget available.  Design team appointed to develop investment in
school that aligns with budget available from Developer
Contributions.
4. Relocation of Mount Esk Nursery/Hawthornden Extension: Rising
roll and catchment review requires investment in school to address
capacity and suitability. Limited budget available.  Design team
appointed to develop investment in school that aligns with budget
available from Developer Contributions. 
3.22 Capital Projects – Children, Young People & Partnerships Estates
Programme: Secondary 
Three specific projects identified within the SRP:
1. Beeslack HS Replacement:  Site acquisition being progressed.  
2. Shawfair All Through: Site acquisition complete. School location
fixed with design team. Remediation programme being revised.
Seeking to make efficiencies in remediation programme.
Page 247 of 396

Page 248

6 
3. Penicuik HS New Build: LEIP target for delivery is December 2026,
however programme for occupation is July 2027. Cost reports
tracking higher and risks identified in refurbishment works.   SFT
advising if additional LEIP funding available. 
3.23 Capital Projects – Regeneration 
Three specific projects identified within the SRP:
1. Vogrie Changing Places.
2. Destination Hillend: Alpine Coaster delivered with access and
parking infrastructure. Project absorbed risk and contingency.  Next
Phase to be recast. Interim works on water supply and drainage
required.
3. Hopefield Industrial Estate: Updated financial model required.
4. Dalkeith Asset Rationalisation Programme: Budget approved by
Council. 
3.24 City Region Deal 
Edinburgh and South East Scotland City Region Deal - bid for funding
to Scottish and UK Governments to accelerate economic growth
through investment in infrastructure/ housing/ skills and innovation was
agreed by Council in June 2018.  Projects continue to be progressed
with realisation of regional enhancements and connectivity. 
4 Report Implications (Resource, Digital and Risk) 
4.1 Resource 
There are no direct resource implications indicated in this report,
although individual risks have associated resource implications. 
4.2 Digital 
None 
4.3 Risk 
The risks reported in this report are understood with the Council able to
demonstrate the current risk controls and actions being taken in
response to these.
The report provides an overview of the significant risks faced by the
Council during Quarter 4 2024-25 and should act to provide assurance
that Midlothian Council took a proportionate and planned approach to
prepare and respond to each of these risks. 
4.4 Ensuring Equalities (if required a separate IIA must be completed) 
There are no direct equalities issues arising from this report. 
4.5 Additional Report Implications (See Appendix A)
Page 248 of 396

Page 249

7 
See Appendix A 
Appendices 
Appendix A – Additional Report Implications
Appendix B – Strategic Risk Profile 
Page 249 of 396

Page 250

8 
APPENDIX A – Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
This report provides an overview of the Strategic Risk Profile of
Midlothian Council at a defined point in time. The issues, risks and
opportunities affecting or supporting delivery of the council priorities are
set out within the Strategic Risk Profile. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
None of the above 
A.4 Delivering Best Value 
The Council’s commitment to best value and securing continuous
improvement can best be delivered when decisions are made against a
backdrop of understanding the risks and opportunities before an
organisation. This report seeks to provide assurance that the current
risk environment is understood and that Midlothian Council is taking
appropriate action in response to those identified risks. 
A.5 Involving Communities and Other Stakeholders 
This Strategic Risk Profile report has been compiled with input from a
range of internal key stakeholders. 
Page 250 of 396

Page 251

9 
A.6 Impact on Performance and Outcomes 
This report seeks to provide an overview of the challenging risk
environment within which the Council is operating at this time. Being in
a risk aware position helps to inform current and future decision
making, with the intention of enhancing decision making and the
associated performance and outcomes which flow from well informed
decision making. 
A.7 Adopting a Preventative Approach 
The Risk Management approach being taken by the Council is founded
on a preventative approach to managing risks, where appropriate and
more generally to decision making with far greater risk awareness. 
A.8 Supporting Sustainable Development 
Senior Managers must ensure the sustainability of the Council, which
entails identifying, understanding and managing Strategic and Service
level risks and opportunities.
Page 251 of 396

Page 252

Page 252 of 396

Page 253

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
STRATEGIC RISK PROFILE, Q4 January-March 2025 
SRP STRATEGIC RISK PROFILE 
SRP This risk register captures the main strategic issues, risks and opportunities that are corporate in nature. It identifies the nature of the risks, measures required to control the risks and their evaluation. It also
details what further actions are required to reduce the likelihood and impacts of those risks to more acceptable and manageable levels with timescales. 
Strategic Issues 
SRP.IR.02 The Change Programme 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.IR.
02
Risk cause
The pace of transformation strands of
activity, reporting to the Business
Transformation Board, does not secure
service transformation, delivery of
outcomes or benefit realisation. 
Risk event
Delayed progress or non-achievement of
outcomes and benefits. 
Risk effect 
Slow or delayed financial benefits arising
from service redesign, requiring the
adoption of recovery plans or requiring
short term service reductions which impact
on the Council’s ability to deliver against
its priorities. 
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
1. Transformation Blueprint agreed at Council June 2023 which is a 5-
year transformation plan. Revised governance for transformation agreed
and revised Terms of Reference in place for the Business Transformation
Board to oversee progress on change programme. 
2. Regular reporting to Council setting out scale of financial challenge
ahead with recurring expenditure for current service delivery projected to
exceed recurring income. 
3. Cross Party Business Transformation Steering Group are given
updates on the progress of the Transformation programme. 4. Financial
monitoring reports and work of the Corporate Management Team
evidence continued financial sustainability, in so far as services are
delivered within the overall budget in year.  
5 5 
Page 253 of 396

Page 254

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SPR.R
A-02.08 Transformation Blueprint 2023-28 delivery
Q4 24/25: As Q3 24/25 
Q3 24/25: As Q2 24/25.
Q2 24/25: Progress with sprints is reported to BTB at every meeting via the
dashboard and also in detailed reports at some points. BTSG are provided with
an updated dashboard every cycle and receive focused reports on individual
sprints and also funding requests to release BT funds to support project work.
Q1 24/25: As Q4 23/24. 
Q4 23/24: Work on sprints continues with some reporting to BTSG in the run
up to June Council with the majority of others scheduled for August. BTB is now
meeting fortnightly to encourage and closely monitor progress. To support
monitoring of progress a dashboard has been developed and this is shared with
CMT and BTSG as a standing item. 
Chief *Executive;
Chief Officer
*Place; Chief
Officer Corporate
Solutions; Chief
Finance Officer; 
30-Jun-2028  20%
SRP.R
A.02.03
Develop Medium Term Financial Strategy
with greater oversight, clearer
responsibility and accountability.
Q4 24/25: MTFS projections to 2028/29 were presented to Council in February
2025 as part of setting the 2025/26 budget and accompanying Council Tax
levels. A further update will be provided to Council during Q1 of 25/26. 
Q3 24/25: An update on the MTFS was presented to Council in December along
with outcomes from the public consultation. Detailed analysis of emerging
national budget positions for 2025/26 was presented and discussed at the
Business Transformation Group. 
Q2 24/25: Further update on the MTFS was presented to Council in October
and a public consultation was launched on 9th October running to 20th
November. 
Q1 24/25: An update on the MTFS was presented to Council in June 2024. This
identifies immediate actions required, in addition to those in the Transformation
Blueprint, to bridge the gap between recurring expenditure and recurring
income and to allow the setting of a balanced budget for 2025/26.   
Q4 23/24: An update on the MTFS with refreshed projections and a clear plan
to address financial sustainability will be presented to Council in June 2024. 
Chief *Executive;
Chief Finance
Officer;
30-June-2024  100% 
Page 254 of 396

Page 255

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.IR.07 Financial Sustainability 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.IR.
07
Risk cause
Scottish Government Grant settlements
fall short of the resources needed to
sustain core services. Core funding falling
short of inflation pressures, pay awards
and demographic pressures arising from
an Increasing ageing population of over
75’s. 
Increasing population of 0-15 age group
and at a time when there are rising
customer expectations. 
Risk event
Transformation activity and the flexibility
available to Councils as part of the grant
settlement does not address future years
projected budget gaps. 
Risk effect Inadequate government
funding makes securing balanced budgets
challenging. This in turn erodes the
Council’s ability to deliver services to the
community and potentially means that
resources available fall short of those the
Council assess as required to meet its
statutory obligations. Whilst transformation
activity can help reshape services and
ensure best value in the delivery of
services it is not a solution to continued
erosion of core funding. 
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
1. There is an approved Capital Strategy and Reserves Strategy in place.
The Capital Strategy is being updated in the context of ongoing and
significant infrastructure pressures. 
2. There is an approved budget for 2024/25. Services are delivered
within the totality of that budget. 
3. Enhanced monitoring arrangements have been agreed for service
areas that are regularly showing overspends. 
4. Directorates have budget boards in place to monitor and agree actions
for those items which are identified as needing specific attention or
present a risk to the financial position of services. 
5. Strategic Boards in place and BTB focus and attention on driving
transformation to support future year’s financial sustainability. 
6. Working through COSLA to influence government spending decisions
to influence Scottish Government’s budget allocation to Councils. 
7. Capital Plan and Asset Management Board will scrutinise and
challenge slippage on capital programmes recognising that slippage can
have an adverse impact on financial sustainability and also the delivery
on assets required to support capital growth. 
8. Chief Executive continues to emphasise the need for effective financial
control and underlined the benefit to the organisation of such an
approach.  
9. Scottish Governments May 2022 Resource Spending Review provided
planning parameters for term of parliament, albeit these are challenging
and present a real terms reduction in grant funding of circa 7% over the
period. 
10. Report to Council February 2024 sets out scale of financial challenge
ahead with recurring expenditure for current service delivery projected to
exceed recurring income. Updated MTFS projections presented in June
2024 with a further update presented in February 2025.
11. Cross Party Business Transformation Steering Group engaged in
consideration of measures to secure balanced budgets alongside the
development of a Strategic Plan to support decisions about what
services, beyond those which are statutory can be provided.  
5 5 
Page 255 of 396

Page 256

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SPR.R
A-02.09 Transformation Blueprint 2023 to 2028
Q4 24/25: Refer to SRP.RA-02.08 
Q3 24/25: Refer to SRP.RA-02.08 
Q2 24/25: Refer to SRP.RA-02.08 
Q1 24/25: As Q4 23/24. 
Q4 23/24: Work on sprints continues with some reporting to BTSG in the run
up to June Council with the majority of others scheduled for August. BTB is now
meeting fortnightly to encourage and closely monitor progress. To support
monitoring of progress a dashboard has been developed and this is shared with
CMT and BTSG as a standing item. 
Chief *Executive;
Chief Finance
Officer; 
30-Jun-2024  20%
SRP.R
A.02.03
Develop Medium Term Financial Strategy
with greater oversight, clearer
responsibility and accountability.
Q4 24/25: Refer to SRP.RA-02.03 
Q3 24/25: Refer to SPR.RA-02.03 
Q2 24/25: Refer to SPR.RA-02.03 
Q1 24/25: An update on the MTFS was presented to Council in June 2024. This
identifies immediate actions required, in addition to those in the Transformation
Blueprint, to bridge the gap between recurring expenditure and recurring
income and to allow the setting of a balanced budget for 2025/26. 
Q4 23/24: An update on the MTFS with refreshed projections and a clear plan
to address financial sustainability will be presented to Council in June 2024. 
Chief *Executive;
Chief Finance
Officer; 
30-June-2024  100%
SRP.R
A-02.10 Capital Plan Prioritisation
Q4 24/25: Council in February received an update on Capital Plan Prioritisation
work and made a decision on an updated Learning Estate Strategy. The extent
and affordability of work flowing from building condition surveys is being
assessed and will be concluded and reported to Elected Members early in
2025/26.
Q3 24/25: Work continues on Capital Plan Prioritisation
Q2 24/25: Work continues on Capital Plan prioritisation
Q1 24/25: Work continues on Capital Plan prioritisation 
Chief Finance
Officer; Executive
Director – Place;
Executive Director
- Education
31-Oct-2024  0% 
SRP.IR.11 National Care Service
Page 256 of 396

Page 257

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.IR.
11
Risk cause
In August 2022 the Scottish Government
launched a 12-week consultation on the
way in which social care is delivered in
Scotland. The consultation followed
recommendations made in the
Independent Review of Adult Social care.
The independent analysis of responses
was published in February 2022. On 20
June 2022 the Scottish Parliament
published the National Care Service
(NCS) Bill which will provide the
foundation for the NCS. 
Risk event
The Bill is currently in Stage 1 of the
process. The most significant part of the
legislation which poses the most risk is the
intention to transfer social care
responsibility from local authorities to a
new, national service. 
Risk effect 
The details of the logistics of any transfer
are not yet provided within the Bill. It is not
clear the extent to which powers will be
removed from local authorities or what the
provision or delivery of services will or will
not be. At this stage, the risk effect is
anticipated to be significant financial
impact to local authorities and IJBs, as
well as the potential for impacts on
staffing, transfer of property and facilities
and the reshaping of the delivery of care. 
It should be noted that the initial impact on
the Council is staff time to contribute to the
ongoing discussions and understanding of
the impact of the Bill.  
Head of *Adult
and Social Care;
Chief *Executive;
Director *Health
and Social Care;
Executive
Director *Place;
Chief Officer
Young People
and Partnerships
As of 14 November 2024, a pause has been placed on the delivery of
NCS legislation by the Scottish Government. 
NOTE: As of Jan 2025, the National Care Service proposal is now
not proceeding.
N/A N/A N/A               
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
Page 257 of 396

Page 258

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.R
A.11.1 Officer Working Group 
Q3 24/25: Scottish Government announced in January 2025 that they will not
be proceeding with the National Care Service. 
Q2 24/25: As of 14 November 2024, the Scottish Government has paused
legislation on the creation of a NCS. 
Q1 24/25: The Bill is at Stage 2 
Q4 23/24: The Bill is at Stage 2. 
Chief *Executive;  31-Dec-2024  100% 
Strategic Risks 
SRP.RR.01 Financial Sustainability in Future Years 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.01
Risk cause:
Scottish Government Grant settlements
fall short of the resources needed to
sustain core services. Core funding falling
short of inflation pressures, pay awards
and demographic pressures arising from
an Increasing ageing population of over
75’s. 
Increasing population of 0-15 age group
and at a time when there are rising
customer expectations. 
Policy decisions by UK & Scottish
Governments which are not fully funded. 
Changes to the responsibilities of Local
Government and the funding implication
that arise from that, particularly in respect
of the creation of a National Care Service. 
Future year pay award settlements. 
Risk event: 
Real terms reduction in core grant
settlements. 
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
1. Development of Strategic Plan, Transformation Blueprint and MTFS
projections which come together to provide a framework to effect change
and to move the Council to a position of financial sustainability. 
2. Maintaining a level of reserves to deal with unforeseen or one-off cost
pressures. 
3. Capital and Reserves Strategies in place. The Capital Strategy is
being updated in the context of ongoing and significant infrastructure
pressures. 
4. Working through COSLA to influence government spending decisions
to influence Scottish Government’s budget allocation to Councils. 
5. Implement a lobbying strategy with government to recognise the
unique position Midlothian Council is in. 
6. Best Value Audit report actions. 
7. Strategic Boards in place to drive transformation in line with the
Transformation Blueprint. 
8. Dedicating capacity to understand impact of NCS Bill, but limited
details mean this is challenging and many unanswered questions (refer
to specific risk on NCS for further detail).  
5 5 
Page 258 of 396

Page 259

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Policies decisions at Government level not
fully funded to Council's. 
Implementation of a National Care Service
and impact on grant settlements. 
Securing the extent of change required in
order to deliver financial sustainability and
a change program that recognises the size
of the challenge. 
Cost pressures exceeding budget
estimates. 
Risk to not achieving financial
sustainability is a failure to deliver cost
reductions / service change embedded in
the blueprint and also supplementing the
blueprint.   
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.RA
.02.03
Develop Medium Term Financial Strategy
with greater oversight, clearer
responsibility and accountability.
Q4 24/25: Refer to SRP.RA-02.03 
Q3 24/25: Refer to SRP.RA-02.03 
Q2 24/25: Refer to SRP.RA-02.03 
Q1 24/25: An update on the MTFS was presented to Council in June 2024. This
identifies immediate actions required, in addition to those in the Transformation
Blueprint, to bridge the gap between recurring expenditure and recurring
income and to allow the setting of a balanced budget for 2025/26. 
Q4 23/24: An update on the MTFS with refreshed projections and a clear plan
to address financial sustainability will be presented to Council in June 2024. 
Chief *Executive;
Chief Finance
Officer; 
30-June-2024  100%
SRP.RA
.02.04 Transformation Blueprint 2023 to 2028
Q4 24/25: Refer to SRP.RA-02.08 
Q3 24/25: Refer to SRP.RA-02.08 
Q2 24/25: Refer to SRP.RA-02.08 
Q1 24/25: As Q4 23/24. 
Q4 23/24: Work on sprints continues with some reporting to BTSG in the run
up to June Council with the majority of others scheduled for August. BTB is now
Chief *Executive;
Chief Finance
Officer; 
30-Jun-2028  20%
Page 259 of 396

Page 260

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
meeting fortnightly to encourage and closely monitor progress. To support
monitoring of progress a dashboard has been developed and this is shared with
CMT and BTSG as a standing item. 
SRP.RA
.02.06 Capital Plan prioritisation
Q4 24/25: Council in February received an update on Capital Plan Prioritisation
work and made a decision on an updated Learning Estate Strategy. The extent
and affordability of work flowing from building condition surveys is being
assessed and will be concluded and reported to Elected Members early in
2025/26. 
Q3 24/25: Work continues on Capital Plan Prioritisation 
Q2 24/25: Work continues on Capital Plan prioritisation 
Q1 24/25: Work continues on Capital Plan prioritisation 
Q4 23/24: Work continues on Capital Plan prioritisation.   
Head of
*Development;
Executive Director
*Place; Chief
Finance Officer; 
31-Oct-2024  0%  
SRP.RR.02 The Long-Term Change Programme 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.02
Risk cause:
A MTFS that does not address the
projected budget shortfall or contextual
factors relating to the Midlothian area. 
Reduced resources 
Leadership fit for the future. 
Lack of clarity or clear compelling vision
for the future 
Delay or shortfall in securing savings 
Lack of or not securing transformational
change in service provision 
Risk event:
Delayed progress in applying various
strands of the Change Programme
including Delivering Excellence
Framework 
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
1. Development of Strategic Plan, Transformation Blueprint and MTFS
projections which come together to provide a framework to effect change
and to move the Council to a position of financial sustainability. 
2. Leadership from all Elected Members, Executive Team and Senior
Leadership Group. 
3. Appropriate governance in place across the BTB Strategic Boards 
4. Resilience planning. 
5. Capacity to deliver change. 
6. Dedicating capacity to understand impact of NCS Bill, but limited
details mean this is challenging and many unanswered questions (refer
to  specific risk for NCS Billl).
7. High level priority is given to blueprint work.    
5 5 
Page 260 of 396

Page 261

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Slow benefits realisation and budget
savings. Cuts in service provision rather
than service transformation 
Risk effect:
Objectives of change not actually met or
progress too slow. Adverse impact on
services Slow or delayed
proposals/savings arising from service
redesign. Potentially further eroding
reserves or requiring short term service
reductions which impact on Council's
ability to deliver against its priorities. Staff
morale negatively affected, Government
step-in short term savings instead of
transformation                  
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.02.03
Develop Medium Term Financial Strategy
with greater oversight, clearer
responsibility and accountability.
Q4 24/25: Refer to SPR.RA-02.03 
Q3 24/25: Refer to SPR.RA-02.03 
Q2 24/25: Refer to SPR.RA-02.03 
Q1 24/25: An update on the MTFS was presented to Council in June 2024. This
identifies immediate actions required, in addition to those in the Transformation
Blueprint, to bridge the gap between recurring expenditure and recurring
income and to allow the setting of a balanced budget for 2025/26. 
Q4 23/24: An update on the MTFS with refreshed projections and a clear plan
to address financial sustainability will be presented to Council in June 2024. 
Chief *Executive;
Chief Finance
Officer;
30-June-2024  100%
SRP.R
A.02.04 Transformation Blueprint 2023 to 2028
Q4 24/25: Refer to SRP.RA-02.08 
Q3 24/25: Refer to SRP.RA-02.08 
Q2 24/25: Refer to SRP.RA-02.08 
Q1 24/25: As Q4 23/24 
Q4 23/24: Work on sprints continues with some reporting to BTSG in the run
up to June Council with the majority of others scheduled for August. BTB is now
Chief *Executive;
Chief Finance
Officer; 
30-Jun-2028  20%
Page 261 of 396

Page 262

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
meeting fortnightly to encourage and closely monitor progress. To support
monitoring of progress a dashboard has been developed and this is shared with
CMT and BTSG as a standing item. 
SRP.RR.03 Legal and Regulatory Compliance 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.03
Risk cause
Current or new legislation applying to
Midlothian Council.
Lack of capacity to resource statutory
obligations around GDPR, data protection,
records management, information
requests and statutory regulatory
functions. 
Risk event
Council and or Services not identifying all
applicable legislation impacting Council
activities and Service requirements. 
Risk effect
Council failing to meet its statutory
obligations resulting in a potential negative
impact for service users or employees.
Reputational impact of not meeting
statutory obligations.  
Head of *Adult
and Social Care;
Legal *and
Governance
Manager; Chief
Operating Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
1. Executive Directors, Chief Officer(s) and Head(s) of Service
responsible for identifying applicable legislation and propose Council or
Service responses to CMT and Cabinet/Council as required. 
2. Annual Assurance Statement. 
3. Internal Audit testing of internal controls as part of risk-based audit
plan. 
4. External Audit. 
5. Range of external inspection. 
6. BTSG oversight of new legislation 
7. Central repository of applicable legislation.  
5 5 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.03.02 Rights of the Child Bill
Q4 23/24: Bill now adopted. Policy to be presented to Council May/June 2024. 
Q4 Council wide group established and developing a plan that ensures we are all
aware and adhering to UNCRC. 
Executive Director
– People  31-Dec-2024  0%
SRP.R
A.03.03 National Care Service
Q3 24/25: Scottish Government announced in January 2025 that they will not
be proceeding with the National Care Service.  Chief *Executive;  31-Dec-2024  0%
Page 262 of 396

Page 263

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Q2 24/25: As of 14 November 2024, the Scottish Government has paused
legislation on the creation of a NCS. 
Q1 24/25: The Bill is at Stage 2.
Q4 23/24: Q4 National Care Service is at stage 2 and we await decisions
around what next.
SRP.R
A.03.05
Review of Standing Orders, Scheme of
Administration and Scheme of Delegation
Q4 24/25: Standing Orders and Scheme of Administration updated and
approved at Feb 2025 Council 
Q4 23/24: Workplan presented and agreed by SOWG in April 2024. Some
changes to SOs and Scheme of Administration presented and approved by
Council in May 2024 (this is technically Q1 2024/25 update). 
Legal &
Governance
Manager;
Executive Director
*Place; Chief
Officer Corporate
Solutions;
28 Feb 2027   40%
SRP.R
A.03.07
Review of policy and creation of a policy
register
Q4 24/25: Policy list presented to CMT May 2025 for CMT to review and
feedback
Q4 23/24: Work to develop policy register ongoing. 
Chief Officer
Corporate
Solutions
31-Dec-2025  40%
NEW Compliance with statutory duties
Q4 24/25 : Resourcing proposal for a new Compliance Team being agreed  by
Corporate Management Team. Funding to be identified through existing
Corporate Solutions budgets with implementation on a phased basis.  Now
proceeding to final stages of Managing Change process
Q1 24/25: Records Management Officer in post and reviewing the Records
Management Plan, Corporate Retention Policy and Schedule and supporting the
development of retention framework for M365 rollout.  
Q4 23/24: Work is ongoing with the Scottish Information Commissioner and
National Records of Scotland to develop and deliver improvement plans.
Ongoing recruitment for Records Manager. Rationale report for resourcing in
development. Significant resourcing pressures contribute to the increase in
scoring for Q4.
Chief Officer
Corporate
Solutions, Legal
and Governance
Manager 
31-Dec-2025  10%    
SRP.RR.04 Employee performance 
Page 263 of 396

Page 264

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.04
Risk cause
Employees not suitably trained/developed
for the roles required of them. 
Limited availability of qualified
practitioners in certain sectors. 
Change program not informed by all key
stakeholders. 
Ageing work force. 
Employees unclear on expected
behaviours. 
Employees constrained to innovate as a
result of management practice. 
Employee productivity rate below the
required level because of ineffective use
of the People Policies particularly
Maximising Attendance. 
Salaries in some functional areas lower
compared to other LA’s resulting in
recruitment issues particularly with trying
to recruit experienced staff. 
Risk event
Employees not engaged/consulted as part
of organisational transformation. 
Experienced employees leaving the
organisation. 
Inability to recruit suitably qualified /
trained staff to fill vacancies negatively
impacting on remaining workforce. 
Unacceptable behaviours demonstrated
by employees. 
Stated organisational culture not
consistently reinforced by managers. 
Poor employee performance will stifle
transformational change. 
Risk effect
Difficulties recruiting the right staff. 
Challenges retaining quality staff. 
Low skill levels. 
Low morale, especially during change. 
High absence rates, loss of experience in
service areas. 
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
HR Strategic
Lead; Chief
Officer Young
People and
Partnerships
Over-riding risk control measure = Focus on having the right people,
here, healthy, performing, behaving and well led via effective utilisation of
the workforce strategy and accompanying action plan. 
Approval of the Council’s Workforce Strategy 2024-2034 which
focuses on the thematic areas below:  
Attendance / Wellbeing
1. Continuing implementation of the Wellness@Midlothian agenda. 
2. Creation of an Employee Health and Wellbeing Strategy and
supporting policy. 
3. Maintaining the Healthy Working Lives Gold Award. 
4. Proactive use of Occupational Health, Midlothian Physiotherapy,
Employee Assistance Programme and the Workplace Chaplaincy
Service. 
5. Change of EAP supplier to ensure provision of best possible service. 
6. Development of progressive People Policies. 
7. Roll-out of mental health training for staff and managers. 
Performance
1. Service-level workforce plans. 
2. Structured, robust, well established ‘Making Performance Matter’
Framework where expected standards of behaviour and Council values
are re-enforced. 
3. Continued re-enforcement of all People Policies involving various
communication methods. 
4. Development of a suite of management information to ensure Service
Managers are informed e.g., turnover, absence levels/reasons etc. 
Organisational Change
1. Policy for Organisational Change includes strong emphasis on early
engagement of employees. 
2. Redeployment Procedure to ensure maximum chance of successful
redeployment. 
Conduct
1. Resolution Policy encourages early intervention of workplace issues. 
2. Professional standards and values build into the induction process and
management development programme. 
Communication
1. A range of initiatives to keep staff informed of change (Chief
Executive’s weekly email, Connect, All staff emails, tailored team
briefings etc.  
3 4 
Page 264 of 396

Page 265

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
‘A Great Place to Grow’ our values
including respect, collaboration, pride and
ownership not realised, potentially
resulting in missing the opportunity to
capitalise on the abilities, experience and
ideas of team members. Poor employee
performance will Exacerbate the financial
challenge. 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.RA
.02.04
Development and Delivery of the Council’s
Workforce Strategy 2024-34 including
analysis of future workforce requirements,
gap analysis and gap closing strategies,
and performance measures and target
setting.
Q4 24/25: Council approved the Workforce Strategy 2024-2034 in December
2024. Work progressing on the delivery of the first three years through an
agreed action plan. Acting HR Strategic Lead appointed. Two interim posts from
BTB funding are being progressed for Talent and Reward. 
Q1 24/25: Workforce Strategy in development and expected to be presented
to December Council with Action Plan for approval. Audit Scotland external audit
on workforce and digital to be presented to Audit Committee September 2024. 
Q4 23/24: Ongoing work nationally to review workforce planning which
Midlothian is contributing to. Best Value focus this year is on workforce planning
– awaiting outcome of external audit to identify improvement plan for 24/25. 
Chief Officer
Corporate
Solutions 
31 Dec 2027   25%
NEW
Recruitment challenges in Procurement
Service leading to contract management
pressures and backlog in procurement
exercises
Q4 24/25: Procurement Manager appointed to start on 1 June 2025. Chief
Officer Corporate Solutions to implement an improvement plan and revised work
plan for the service and develop business case for appropriate resourcing.
Chief Officer
Corporate
Solutions  31 Dec 2025  10%          
SRP.RR.07 Care at Home 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
Page 265 of 396

Page 266

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.R
R.07
Risk cause
Internal and External providers of Care at
Home services unable to meet service and
quality requirements as a result of a lack
of capacity. 
Risk event
Capacity of Community Support
outstripped by demand. 
Risk effect
There is a risk that patients will have their
discharge delayed because there is
insufficient community supports to enable
timely discharge leading to deterioration in
their health, beds being blocked and
elective operations potentially being
cancelled.  
Head of *Adult
and Social Care;
Director *Health
and Social Care
1. Care at Home winter assurance plan and business continuity plan
complete 
2. Development of Care at Home Service Improvement action plan near
completion 
3. External commissioning complete and ongoing contract monitoring in
place 
4. External provider audits complete 
5. Re-established Multi-Agency Quality in Care at Home quarterly review
meetings jointly with East Lothian 
6. Weekly provider meetings in place 
7. Additional locum team members and contracts with agency staff in
place 
8. Daily discharge meeting with Multidisciplinary and Multi-agency team
planning to plan and coordinate discharge to ensure care at hone support
in place  
3 4 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.07.01
Independent review of adult and social
care 
Q3 24/25: Scottish Government announced in January 2025 that they will not
be proceeding with the National Care Service. 
Q2 24/25: The Scottish Government has initiated a pause on the development
of the NCS. 
Q1 23/24: Pause remains in place.
Head of *Adult
and Social Care;
Chief *Executive; 
31-Jan-2024  100%         
SRP.RR.08 Asset Management – buildings, vehicles,  roads and Digital assets/networks 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
Page 266 of 396

Page 267

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.R
R.08 
Risk cause
Many of the assets the Council own by
their nature are in a position of ongoing
deterioration through their normal use,
e.g., roads - normal wear and tear,
streetlights and vehicles & buildings used
to deliver services. 
Risk event
Many assets will deteriorate under normal
conditions although buildings, roads and
streetlights as an example can be
damaged during more extreme weather
events or as a result of a lack of
maintenance. 
Risk effect
In the case of Roads Services there is a
real risk of increased potholes and
insurance claims, reduced skid resistance
leading to higher accident potential and
building up of higher costs in the future. In
respect of vehicles, increased
breakdowns, service failures, greater
maintenance inevitable, higher short-term
hire costs. In terms of property, health and
safety issues arise, failure to meet current
standards and higher running costs. There
is also the risk of two-tier accommodation,
some high quality, some low. 
Head of *Adult
and Social Care;
Head of
*Development;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
1. There is provision in place within the capital plan for investment in the
asset base. 
2. Asset register 
3. Condition Survey 
4. Understanding of future asset needs 
5. Asset Strategy: 
. Roads 
. Land 
. Fleet 
. Digital Service Network 
. Digital Service hardware 
6. Capital programme - investment in estate. 
7. Ongoing monitoring of properties by: Maintenance Surveyors,
Facilities Management and Property Users. 
8. Established Capital Plan and Asset Management Board and dedicated
Asset Management Board 
9. Establishment of 7 thematic Estate Safety and Management Groups
chaired by Chief Officer Place 10. Building Accessibility Strategy  
3 5 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.08.02
Plan for appropriate investment in capital
works and remedial maintenance over the
lifespan of each property asset.
Q3 24/25:  Condition Surveys of Learning Estate (excl PPP) has concluded.  Q4
presentation to Elected Members.  Backlog repairs continue. 
Q1 24/25: Condition Surveys continue, with Learning Estate (excl PPP)
expected to be concluded by end December 2024 to inform capital investment
proposal.
Chief Officer
*Place;  30-Apr-2025  33%
Page 267 of 396

Page 268

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Q4 23/24: Backlog maintenance repairs being undertaken across the estate on
a prioritised basis. 
SRP.R
A.08.05 Learning Estate Strategy
Q3 24/25 Learning Estate Strategy Update paper due to go February Council,
this includes a progress report on status of all approved and ‘approved in
principle’ projects. Edge analytics have also completed their validation of the
School Roll Projections. 
Q4 23/24: All Priority 1 and 2 projects are progressing. In terms of all of the
capacity breaches that were detailed in Priority 2 of the LES, investment was
made to provide a solution. 
Head of
*Development;  30-Apr-2025  50%
SRP.R
A.08.06 Asset Management systems Q4 23/24: Identified for implementation through Transformation Blueprint and
The Change Programme.  
Chief Officer
*Place;  31-Mar-2025  0%  
SRP.RR.09 Emergency Planning and Business Continuity Management 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.09
Risk cause
The Council not preparing or timeously
reviewing Emergency Plans and testing
arrangements to respond to Civil
Contingencies Incidents 
Risk event
There are a wide range of potential events
the Council may be expected to respond
to e.g., Severe weather incident,
Pandemic, Utility disruption etc. 
Risk effect
Censure through non-compliance with the
Civil Contingencies Act Not adequately
recovering from the loss of major
accommodation (e.g., secondary school,
main offices), computer systems and staff
Not able to respond to a major emergency
in the community Fatal Accident Inquiries  
Head of *Adult
and Social Care;
Head of
*Development;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
David Robertson;
Chief Officer
Young People
and Partnerships
1. Civil Contingencies Risk Register used to highlight key risks and
record response, 
- Council’s plans developed and maintained in response to identified
risks, 
- Risk and Resilience Group support development, peer review and roll
out of plans. 
2. Establishment based incident response plans in place and maintained
locally. 
3. Emergency response plan setting out general approach to respond to
a major emergency in-line with key partner organisations. 
4. As part of the Council’s Emergency response the importance of
recording decisions made and information available at the time is
highlighted as this would be scrutinised in the event of an FAI. 
05 – Care for People Group: Afghan, Ukrainian and UASC support
programmes  
3 4 
Page 268 of 396

Page 269

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.09.02 Development of Emergency Plans
Q4 24/25: The service review for the Health, Safety and Resilience Team
Service, which includes Contingency Planning, requires to progress to
implementation stage. 
Ongoing challenges continue, preventing notable progress.  Plans and 
Procedures updated this quarter:  
Emergency Contacts Directory (reflecting staff changes)    
Business Continuity Planning: 
The Internal Audit Team conducted an audit of Business Continuity (BC) across
the organisation.  There were specific recommendations for the Health, Safety
and Resilience Team.  Some of these actions were already in progress prior to
the Audit, following a series of activities raising awareness of Business
Continuity in 2024.  In summary, these are to: 
• Revise the Corporate BC Policy (in progress)
• Revise the word BC template for completion by services 
• Explore the viability of rolling out a BC software system.  The main
factors for consideration are: 
• The current system now has a limited lifespan so an alternative would
need to be sourced 
• Resourcing of a system – cost and staffing resource 
• Provide training for nominated BC leads (nominations to be done by
services).  This is to include an e-learning module 
• Establish a forum for BC leads to share good practice and ensure
consistency of approach 
• Establish a system to monitor service compliance with BC
requirements. 
Practical demonstration of Business Continuity tested in recent storm Éowyn 
(Jan 25).
There are target dates associated with the Audit recommendations. The report
does note that to meet the recommendations, additional resource may be
required - as identified by the service review.  As at the end of this Q4 24/25
reporting period, the outcome of the service review is still waited.  Furthermore,
one of the team members will be reducing hours by 20% from May 2025. 
Other Plans/Procedures: 
As well as the need to focus on the outcome of the BC Audit, generic
“emergency planning” activities require to be undertaken as resources permit,
Chief Officer
*Place; Senior
Manager
Protective
Services; David
Robertson
30 September
2025   75%
Page 269 of 396

Page 270

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
including reviewing and updating existing procedures. Work is also ongoing
regarding learning from Storm Éowyn.  As well as considering our own
procedures, liaison is taking place with neighbouring local authorities and
Scottish Power Energy Networks to better understand their responsibilities
towards customers and to improve communications across the piece.  The
results of these discussions will be reflected in documentation in due course. 
CONTEST/Prevent: 
Support is offered to the CONTEST and Prevent SPOC on an ongoing basis.  This
includes attending relevant briefing sessions, multi-agency CONTEST Groups
(internal and external) and training events as applicable. 
Assistance has also been given this quarter in the preparation of Midlothian
Council’s submission to the Prevent Assurance process carried out by the Home
Office. 
Ongoing monitoring and circulation of information on Martyn’s Law (Terrorism
(Protection of Premises) Bill).  
Collaborated with Business Services (Operational Support) to have updated
Prevent and Action Counters Terrorism (ACT) modules available on our e-
learning platform. These are both national products. Next steps were discussed
at the January CONTEST meeting and are to be introduced in Q1 of 25/26.   
Q3 24/25: The service review for the Health, Safety and Resilience Team
Service, which includes Contingency Planning, has not yet concluded.  This
means ongoing challenges continue, preventing notable progress. 
Plans and Procedures updated this quarter:  
• Midlothian Council Severe Weather Plan 
• Emergency Contacts Directory (reflecting staff changes) 
• Support to the Executive PA Place with the Festive Period Service
Arrangements document. 
Plan updates/procedures in progress:  
• Midlothian Council Emergency Plan (generic). This document outlines
internal emergency management arrangements and multi-agency
partnership relationships.  
• Operation UNICORN (and associated arrangements). Scottish
Government have advised that national planning arrangements are
underway and where relevant to Midlothian, will be incorporated in the
Midlothian Council guidance document.    
• Corporate Business Continuity (BC) Plan has been drafted.  
Multi-agency Exercises, Training, Presentations, Work streams:  
Page 270 of 396

Page 271

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
• Participated in a Cyber Security training exercise organised by Digital
Services in liaison with an external partner. This is a further example of
collaborative working with Digital Services in order to improve Business
Continuity Planning across the organisation.
• Supporting School Business Managers in the development of their
School Incident Plans, in collaboration with Police Scotland colleagues.   
Q2 24/25: Service review for the Health, Safety and Resilience Team Service,
which includes Contingency Planning, is still in progress. 
Plans/plan updates include: 
• Midlothian Pipelines Emergency Plan (required under the Pipelines
Safety Regulations 1996).   
• Emergency Contacts Directory (reflecting staff changes) 
• Provision of Business Continuity guidance notes to service managers. 
Plan updates/procedures in progress:  
• Midlothian Council Emergency Plan (generic). This document outlines
internal emergency management arrangements and multi-agency
partnership relationships. 
• Operation UNICORN (and associated arrangements). Scottish
Government have advised that national planning arrangements are
underway, and we will tie in with those. Meantime, we have the basics
in place, based on previous experience. 
• Corporate Business Continuity (BC) Plan. An update to the Corporate
Business Continuity Policy was provided to Corporate Management
Team members in Q4 23/24. However, learning from a Cyber Security
event facilitated by Scottish Government in June 2024 and September
2024 and the experiences of other organisations will be incorporated
into an expanded document, which will also link in with the work being
done by Digital Services on the technical response to a cyber-attack.   
• Draft action plan in relation to the revised Prevent Duty Guidance to
measure our compliance.  (In support of the Prevent SPOC.)
• Support to the Executive PA Place with the Festive Period Service
Arrangements document. 
Multi-agency Exercises, Training, Presentations, Work streams:
• Debrief for the multi-agency Exercise Puma (Torness related exercise)
held in June 2024. 
• Supporting School Business Managers in the development of their
School Incident Plans, in collaboration with Police Scotland colleagues. 
Page 271 of 396

Page 272

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
• Familiarisation training exercise using Airwave handsets (held by Police
Scotland for partner use in emergencies).  These short sessions are
organised by the Scottish resilience community on a regular basis
throughout the year. 
• A number of national presentations relating to Prevent (extremism) 
Q1 24/25: Exercise (simulated cyber attack) took place at the Leadership
Forum June 2024 with the session facilitated by Scottish Government and LRP
Colleagues. The session was designed to remind services managers of the
importance of having , maintaining and exercising their Business Continuity
Planning arrangements.   
Plans/plan updates include: 
• Midlothian Council generic Emergency Plan. This document outlines
internal emergency management arrangements and multi-agency
partnership relationships. 
• Operation UNICORN (and associated arrangements).  Scottish
Government have advised that national planning arrangements are
underway.  Meantime, we have the basics in place, based on previous
experience. 
• Corporate Business Continuity (BC) Plan. An update to the Corporate
Business Continuity Policy was provided to Corporate Management
Team members in Q4 23/24.  However, learning from a Cyber Security
event facilitated by Scottish Government in June 2024 and the
experiences of other organisations will now be incorporated into an
expanded document, which will also link in with the work being done by
Digital Services on the technical response to a cyber attack.   
Multi-agency Exercises, Training, Presentations, Work streams:
Team Members also participated in the following where appropriate to their
areas of work, invitations were extended to colleagues in other services and
partners: 
• Planning for and participation in a Torness related exercise in June
2024. 
• Lothian and Borders Local Resilience Partnership non-routine inputs
including Met Office Extreme Heat Awareness 
Q4 23/24: Work on flooding across the county and its risks has commenced,
with a report to Council scheduled for post-recess.  CMT desktop exercise
undertaken. 
SRP.R
A.09.03 Business Continuity Software System 
Chief Officer
*Place; Senior
Manager
31-Dec-2025   25%
Page 272 of 396

Page 273

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Q4 24/25: Consideration currently being given to the option of using
Teams/Sharepoint as a solution/replacement for existing software, the contract
for which ends in Dec 2025. 
Q3 24/25: Any new system requires resource to roll out across the
organisation. 
Q1 24/25: The Health, Safety & Resilience Service review is progressing and
has identified staffing shortages to meet obligations. 
Q4 23/24: Report in early draft, to be completed once Health, Safety &
Resilience service review completed (SRPO.RA.09.02).  BCPs in the event of
power outage to be incorporated. 
Protective
Services; David
Robertson   
SRP.RR.10 Governance and Standards in Public Life 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.10
Risk cause
Code of conduct for Members and
employees’ actions falling short of
International Standards. 
Risk event
Failure in openness, accountability, clarity. 
Risk effect Service, partnerships and
project outcomes not achieved. Non-
compliance with conduct standards and
reduction in standards in public life.  
Legal *and
Governance
Manager; Chief
*Executive; Chief
Officer *Place;
Executive
Director *Place;
Chief Officer
Corporate
Solutions
01 Annual Assurance Statement. 
02 Standing Orders 
03 Scheme of Administration 
04 Scheme of Delegation 
05 Elected Member Code of Conduct 
06 Induction programme for new members and ongoing learning and
development programme 
07 Employee Code of Conduct  
2 4 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.RA
.03.05
Review of Standing Orders, Scheme of
Administration and Scheme of Delegation
Q4 24/25: Standing Orders and Scheme of Administration updated and
approved at Feb 2025 Council. 
Legal *and
Governance
Manager; Chief
28 Feb 2027  20%
Page 273 of 396

Page 274

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Q1 24/25: Workplan presented and agreed by SOWG in April 2024. Some
changes to SOs and Scheme of Administration presented and approved by
Council in May 2024. 
Officer Corporate
Solutions; 
SRP.RA
.10.03
Review of the employee onboarding and
induction programme
Q4 24/25: Work ongoing to finalise the refreshed induction programme and
onboarding process 
Q3 2023/24: CMT agreed to a refresh of the staff induction programme which
include a compliance section. It is anticipated that the new programme will be
fully completed by end Dec 2024, with a phasing of improvement actions being
delivered throughout 2024.  
HR Strategic Lead 31-Dec-2025  5%  
SRP.RR.11 Corporate Policies and Strategies 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.11
Risk cause
Policies may not match the aspirations of
the Council's Strategic priorities or cultural
perspective. 
Risk event
Policies not monitored may become out of
date. 
Policies not reviewed to ensure alignment
with strategic priorities. 
Risk effect Policies not monitored could
result in non-compliance with legislation
Policies not aligned to strategic priorities
will inhibit rather than support
implementation of strategic priorities.  
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
1. Single Midlothian Plan providing overarching direction 
2. Service plans aligned to Single Midlothian Plan. 
3. Leadership team to ensure correct approaches are adopted to get the
right results. 
4. Strategic housing investment plan, submitted to Scottish Government. 
5. Capital Strategy 
6. Integrated Joint Board (IJB) Plan 
7. IJB Strategic needs assessment 8. Midlothian Local Development Plan
2017 – the Council’s corporate spatial strategy.  
2 3 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
Page 274 of 396

Page 275

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.RA
.02.04 Transformation Blueprint 2023 to 2028
Q4 24/25: Refer to SRP.RA-02.08 
Q3 24/25: Refer to SRP.RA-02.08 
Q2 24/25: Refer to SRP.RA-02.08 
Q1 24/25: As Q4 23/24. 
Q4 23/24: Work on sprints continues with some reporting to BTSG in the run
up to June Council with the majority of others scheduled for August. BTB is now
meeting fortnightly to encourage and closely monitor progress. To support
monitoring of progress a dashboard has been developed and this is shared with
CMT and BTSG as a standing item. 
Chief *Executive;
Chief Finance
Officer; 
30-Jun-2028  20%
SRP.RA
.03.07
Review of policy and creation of a policy
register
Q4 24/25: Policy list presented to CMT May 2025 for CMT to review and
feedback 
Q4 23/24: Work to develop policy register ongoing. 
Chief Officer
Corporate
Solutions
31-Dec-2025  10%
SRP.RA
.11.05 Antisocial Behaviour Policy
Q1 24/25: Member Briefing on Housing and Antisocial Behaviour to be
prepared and presented during Q2, with report to Council to follow. 
Q4 23/24: Midlothian Community Action Team SLA 2024-25 contains tackling
ASB as a strategic objective. 
Chief Officer
*Place;  31-Dec-2024  0%        
SRP.RR.12 Internal Control Environment 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.12
Risk cause
Work procedures/process inadvertently
create the capacity for fraud and waste to
occur. 
Internal Controls requiring more time,
effort or cost than the risk being managed. 
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
1. Services have been prompted to consider fraud and waste within
Service Risk Registers. 
2. Risk Management Guide provides direction on the need to balance
time, effort and cost against benefit of risk controls. 
3. Internal Audit examine internal control arrangements based largely on
the risk registers. 
2 3 
Page 275 of 396

Page 276

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Mangers failing to follow procedures and
keep systems updated with accurate
information. 
Risk event
Persons exploiting opportunities to commit
fraud. 
Waste and errors 
Changing risk landscape associated with
remote working solutions. 
Risk effect
Waste and loss 
Risks over managed with risk controls
costing more than the potential loss being
managed. Increased opportunity for fraud
or financial loss has direct impact on
management information. Has adverse
effect on service performance.  
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships
4. Corporate Fraud team in place who assist managers to undertake
fraud risk assessments in their areas (focused on priority areas) and
provide advice and guidance on fraud related matters. Active
participation in the National Fraud Initiative to investigate matches. 5.
Whistleblowing Policy and Counter Fraud Policy in place (subject to
review) with whistleblowing channels available to report concerns
(anonymously if required). 
6. Internal and external assurance. Annual Governance Statement which
involves obtaining assurance from Management over controls in their
Service. 
7. E-learning for staff to complete mandatory training for fraud
awareness. 
8. Regular updates to Audit committee on progress with
recommendations made by Internal Audit. 
9. Remind staff to declare secondary employment/outside interests and
gifts & hospitality 
10. Induction for all new employees (with service exceptions), including
legal, HR, procurement, health and safety. Control at entry to
organisation. 
11. The Integrity Group continues to meet to improve the Council’s
resilience to fraud, corruption, theft and crime (including cybercrime),
maintaining proper risk management, governance and internal control
processes and systems to ensure probity in systems and operations, and
mitigation of risks, including the prevention, detection and resolution of
fraud and irregularities. Management is also responsible for checking that
the arrangements and controls are operating effectively and obtaining
assurances from internal compliance, risk, inspection, quality, and control
functions.   
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.12.04
Review of Serious Organised Crime
(SOC) group
Q3 24/25: Draft Strategy devised.  Regulatory safeguards/actions progressing
through Licensing. 
Q1 24/25: Initial meeting with Police is planned to discuss strategy. 
Q4 23/24: Chief Officer Place on national SOC working groups and utilising
forums to inform strategy. 
Chief Officer
*Place; Health,
Safety &
Resilience
Manager
31-Mar-2025  50%  
Page 276 of 396

Page 277

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.RR.13 Climate Change 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.13
Risk cause
Council Services not adequately engaged,
resourced or directed to fulfil the
requirements of the Climate Change Act. 
Risk event
Council Services not responding to the
Climate Change Act with sufficient pace. 
Risk effect Council failing to meet its
obligation under the Climate Change
(Scotland) Act 2009 and incurring the
associated reputational damage.  
Chief *Executive;
Executive
Directors and
Chief Officers.
1. Statutory requirement to report on compliance with climate change
duties. 
2. Council Carbon Management Plan 
3. Approval of a Corporate Climate Change Strategy and action plan 
4. CPP Board for Climate Change to bring strategic focus and oversight
of plans and progress. 
5. Resilience Seminars  
5 5 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.RA
.13.04
Delivery of the BTB Board Carbon Neutral
by 2030
Q3 24/25:  Council approved realignment of Net Zero target from 2030 to
2045. 
Q2 24/25: Member Briefing delivered. 
Q1 24/25: Member Briefing on Climate Action Plan being prepared for
presentation in Q2/3. 
Q4 23/24: Climate Action Plan finalised and will be presented to Council in
2024/25. 
Planning,
Sustainable
Growth and
Investment
*Manager; Chief
Officer *Place; 
31-Mar-2030  0%
SRP.RA
.13.05
Development of the Strategic Plan 2023-
27
Q3 24/25:  Council approved realignment of Net Zero target from 2030 to
2045.  Climate Action Strategy refresh to follow. 
Q4 23/24: Climate Action Plan finalised and will be presented to Council in
2024/25. 
Planning,
Sustainable
Growth and
Investment
*Manager; Chief
Officer *Place; 
31-Mar-2025  90%  
Page 277 of 396

Page 278

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.RR.14.1 Scottish Child Abuse Inquiry 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.14.1
Risk Cause: Midlothian Council and its
legacy organisations, predating the
creation of Midlothian Council in 1996,
have been involved in the provision of
care of children going back to living
memory. During this time there is the
likelihood that the care children received
fell below standards of care now in place.
There is the further potential that some
people in the care of Midlothian Council
and its legacy organisations were subject
to abuse by those who were employed to
care for them. 
Risk Event: The Scottish Government
began an Inquiry into cases of Child
Abuse occurring prior to 17 December
2014, the intention of this enquiry is to
identify historic case of abuse which have
to date gone unreported. 
The most recent Section 21 notice around
the Foster Care Case Study is a
significant piece of work. The request for
information from 1930 to date is very
challenging given the volume of files that
require to be read and analysed. 
Risk Effect: If the inquiry finds historic
cases of abuse in Midlothian this could
damage the reputation of the Council and
could place doubt in the eyes of the public
as to the safety of these currently in care.
There is significant scope for a substantial
financial impact arising from claims of
historic abuse. Some existing employees
may be affected by the inquiry and
subsequent claims of abuse. 
We have requested an extension for Parts
B, C & D of the last Section 21 to April
2020, which has been granted. To date
there has been no evidence from the
Chief *Executive;
Chief *Social
Work Officer 
The Council initially set up an Inquiry Project Team, however this is no
longer required as we have an experienced worker overseeing all
requests for the Scottish Child Abuse Inquiry Team. 
Work is ongoing and we have the additional tasks of supporting and
responding to enquiries from the redress team. 
The Inquiry Team have established a Project Plan covering: 
1. Residential establishments, List D Schools and Foster Carers:
identifying Children’s homes, Foster Carers and any List D Schools in
Midlothian over the last 100 years and researching historic records. 
2. Record Audit: reviewing the Council’s existing paper and electronic
recordkeeping systems to identify relevant records and map them to
residential establishments. This also includes, where possible, noting the
Council’s historic recordkeeping policies, such as retention schedules. 
3. Cataloguing/Indexing: checking and updating existing recordkeeping
systems for accuracy and consistency, enabling effective information
retrieval when requested by the Inquiry. 
The Project Team have established a Project Plan covering: 
4. Ascertaining the succession and insurance position in relation to
potential historic child abuse claims. 
5. Ascertaining and agreeing Midlothian Council’s legal position/
approach in dealing with the potential historic child abuse claims. 
6. Identifying the need for guidance, protocol, templates etc. should/if any
claims be made against the council. 
7. Consideration to identifying if additional staffing will be required as
expected deluge of FOI’s SARs in 2018 from solicitors of potential
claimants. 
8. Project team is in place with project plan with a range of identified
actions which are being progressed. Monthly meetings to progress
project plan. 9. The SCAI Social Worker is very competent and
experienced in this area of work and provides quarterly updates on their
findings from the file read. This is a real strength within this area of work.
The CSWO and Principal Solicitor meet regularly with the social worker
to discuss findings from the file read. 
4 4 
Page 278 of 396

Page 279

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
extensive file read to suggest there has
been systemic abuse within our foster
care system. 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.14.03
Foster Care and Residential Care File
Review
Q3 24/25: Phase 10 is now in progress with investigation of residential care
homes run by local authorities. We will comply with all s21 requests. 
Q4 23/24: Foster care enquiry completed. 
Childrens Services
Management
Team; Chief
*Social Work
Officer;  Chief
Officer Young
People and
Partnerships
31-Mar-2024  100%  
SRP.RR.16 Growing Council 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.16
Risk cause
Population growth in Midlothian over the
next 10 to 15 years will see Midlothian
become the fastest growing Council in
Scotland. 
Between 2014 and 2039, ages 0-15yrs,
population is projected to increase by 20%
and for ages 75+ population projected to
increase by 100%. 
Risk event 
Failure to resource and plan for these
rises will significantly impact the Councils
ability to fulfil its statutory obligations in
relation to these groups. 
Risk effect Inadequate capacity within the
school estate to cope with the projected
increase in pupil numbers. In sufficient
provision to support an aging population
Head of *Adult
and Social Care;
Chief *Executive;
Executive
Director *Place;
Fiona
*Robertson;
Chief Officer
Young People
and Partnerships
1. Local development plan and supplementary guidance on developer
contributions. 
2. Services planning future service provision on the basis of anticipated
service demands 
3. The change programme 
4. Learning Estate Strategy 
5. Capital Plan Prioritisation 
6. Strategic Housing Investment Strategy 
7. Rent Review Strategy 
8. Joint needs assessment used to develop - IJB Strategic Plan 
9. Capital Plan and Asset Management Board will scrutinise and
challenge slippage on capital programmes recognising that slippage can
have an adverse impact on financial sustainability and also the delivery
on assets required to support capital growth. 10. City Deal provides the
opportunity to support inclusive growth.  
4 4 
Page 279 of 396

Page 280

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
placing costly inefficiencies on other parts
of the care sector. General population
increase placing additional demand on
infrastructure including GP services.
Increased pressure on infrastructure,
services e.g., waste collection and growth
of road network as new development
roads are adopted. 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.RA
.02.06 Capital Plan prioritisation
Q4 24/25: Council in February received an update on Capital Plan Prioritisation
work and made a decision on an updated Learning Estate Strategy. The extent
and affordability of work flowing from building condition surveys is being
assessed and will be concluded and reported to Elected Members early in
2025/26. 
Q3 24/25: Work continues on Capital Plan prioritisation. 
Q2 24/25: Work continues on Capital Plan prioritisation. 
Q1 24/25: Work continues on Capital Plan prioritisation. 
Q4 23/24: Work continues on Capital Plan prioritisation.   
Head of
*Development;
Executive Director
*Place; Chief
Finance Officer; 
31-Oct-2024  75%  
SRP.RR.17 UK Decision to leave the EU 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.17
Risk cause
UK vote to leave the European Union 
Risk event
UK leaving the European Union 
Risk effect The impacts associated with
the UK's decision to leave the UK have yet
to be realised and will only become clear
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
1. Risk and Resilience Group 
2. Taking a risk management approach to identifying and assessing
anticipated impacts 
3. Working with a range of national and local bodies to inform preparatory
arrangements. 
4. EU Settlement scheme promoted on Council Internet to support those
living and working in Midlothian to access the Home Office scheme.  
4 5 
Page 280 of 396

Page 281

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
once the final terms of the UK's departure
are finalised. There are some direct
potential impacts such as an end to EU
funding of Council co-ordinated projects
and indirect impacts on industries
undertaken within the geographical area
which have relied on EU funding, such as
agriculture. There are wider potential
implications arising from uncertainty
regarding the resident status of EU
nationals, post any exit agreement, and
the availability of workers from outside the
UK accessing the job market here in the
future. These factors have the potential to
impact on the availability of the right
people with the right skills being available
to help grow the economy here in
Midlothian. One area this could affect the
Council could be in the delivery of future
building projects within Midlothian which
could curtail further economic growth.  
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
Young People
and Partnerships                
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.17.01 Refresh of Economic Strategy
Q3 24/25: Council approved new Midlothian Strategy for Inclusive Economic
Growth 2025-2030. 
Q2 24/25: Member Briefing delivered on Midlothian Strategy for Inclusive
Economic Growth, with report prepared for Council in November. 
Q1 24/25: Member Briefing scheduled for 3rd October 2024. 
Chief Officer
*Place; 30-Jun-2024  100%  
SRP.RR.19 Health & Safety 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.19
Risk cause
Failing to identify and rectify non-
compliance with Health and Safety
regulations. 
Head of *Adult
and Social Care;
Chief Operating
Officer
1. Health Safety and Wellbeing Strategy & Service Plan 
2. Suite of Health and Safety Management Arrangements developed
setting out council response to statutory obligations 
3 5 
Page 281 of 396

Page 282

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Risk event
Employees required to undertake tasks
they are not competent to. 
Statutorily driven health and safety
protective arrangements for service users
and employees not implemented correctly. 
Non-compliance with policy and procedure 
Not undertaking audits and inspections to
confirm adherence to policy and legislative
requirements. 
Risk effect 
Serious injury of ill health impact on
employees and or service users. 
Negative impact on outcomes for
customers/service users. 
Service users and employees exposed to
hazards where statutory requirements
exist. 
Statutory health and safety - duty of care
over services users and employees not
met. Criminal prosecution of the Corporate
body and or individuals through Corporate
Homicide (Corporate Manslaughter)
Significant financial penalties from
Criminal Prosecution.  
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
David Robertson;
Chief Officer
Young People
and Partnerships
3. Comprehensive range of Health & Safety Management & Assessment
based development opportunities for line managers 
4. Use of Health & Safety Management Information System (SPHERA) to
enhance information transfer and organisational efficiency 
5. Comprehensive training programme in place to support those with
responsibility for managing health and safety. 
6. Use of comprehensive audit programme to confirm the application of
agreed management Arrangements and Council Policy. 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
NEW 
Health, Safety & Resilience Service
Review 
Q4 24/25: Position unchanged from Q3 The service review for the Health,
Safety and Resilience Team Service requires to progress to implementation
stage. 
Q3 24/25: Service review completed, pending action. 
Q2 24/25: Service Review progressing and developing (completed Sept 2024). 
Q1 24/25: The Health, Safety & Resilience Service review is progressing and
has identified staffing shortages to meet obligations. The report will be
submitted in Q2 for consideration. 
Q4 23/24: Service review in progress.
Chief Officer
*Place; Senior
Manager
Protective
Services; David
Robertson
31/10/2025  100%
Page 282 of 396

Page 283

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.R
A.19.01
Delivery of Health, Safety and Wellbeing
Service Plan 
Q4 24/25: Position unchanged from Q2. Awaiting outcome before service plan
for 25/26 can be fully drafted. 
Q3 24/25: Position unchanged from Q2. 
Q2 24/25: Awaiting outcome of service review before reviewing service plan. 
Q1 24/25: Implementation of the Protective Services Health, Safety &
Resilience Service Plan continues. The plan will be reviewed at conclusion of the
service review. 
Chief Officer
*Place; Senior
Manager
Protective
Services; David
Robertson
31-Mar-2025  50%
SRP.R
A.19.07
H&S fire safety audit across all Council
estate 
Q4 24/25: New Fire Safety Adviser now recruited. To begin work on 28th April
2025. Meanwhile, require contractor backfill to help deal with fire risk
assessment backlog. 
Q3 24/25: Departure of Fire Safety Adviser in Nov 2024 has adversely affected
implementation of audit programme and reactive responses. Another member of
staff is temporarily dealing with priority work until a replacement is recruited.   
Q2 25/25: As Q1 24/25. 
Q1 24/25: Fire Risk Assessments/Audits progressing. A number of Zurich
Insurance audits have also taken place. 
Q4 23/24: Fire Risk Assessments/Audits are currently priority. 
Chief Officer
*Place; Senior
Manager
Protective
Services; David
Robertson
31-Mar-2026  33%  
SRP.RR.21 Cyber Security 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.21
Risk Cause
Malicious attempts to damage, disrupt or
gain unauthorised access to Council
computer systems, networks or devices. 
Risk Event
The cyber threat is severe and advancing
quickly.The Council is at significant risk of
Head of *Adult
and Social Care;
Cyber Security
Information
Governance and
*Compliance
Manager; Head
of *Development;
1. Implementation of and compliance with the Scottish Government
Cyber Resiliency Public Sector Action Plan 
2. Cyber Essentials Plus Certification 
3. Public Sector Network Certification 
4. Regular Audits and Inspections
5. Appropriate technical and organisational measures deployed to reduce
the likelihood and impact of an attack 
6. Having adequate skills and knowledge in the organisation 
3 5 
Page 283 of 396

Page 284

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
cyber-attack from Ransomware Phishing
Emails, Advanced Persistent Threats
(APT) and Distributed Denial of Service
Attacks (DDOS) attacks. Hacking and
Social Engineering. 
Risk Effect
Access to Council systems by cyber
criminals and foreign intelligence agencies
for financial, commercial or information
gathering reasons. This could lead to
significant financial losses, data
compromise and subsequent regulatory
sanction if our technical and organisational
measures are deemed insufficient. Severe
business disruption including the almost
total loss of critical IT systems and
networks leading to significant service
delivery challenges.  
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
David Robertson;
Chief Officer
Young People
and Partnerships
7. Implementing Scottish Government Cyber Security Action Plan
8. Adoption of the NCSC (National Cyber Security Centre) Active Cyber
Defence programme  
9. Technology upgrades
10. Incident Response plans and exercises                
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.21.1
Appropriate Technical and Organisational
Measures 
Q4 24/25 
1. Delivered a week-long cyber security awareness campaign (24
February – 2 March), using email, posters, intranet news, social media,
and updates from the Chief Executive  
2. Secured a £7,000 grant from the Scottish Government to support cyber
security training for Digital Services staff  
3. Provided support for the 2025 Audit Scotland audit, focusing on key
financial systems and cyber security controls  
4. Successfully defended the organisation against multiple cyber attacks  
5. Provided security oversight for the onboarding of new applications and
technical services   
Q3 24/25 - Action/mitigation includes: -
1. Quorum cyber security tabletop exercise completed 
2. Successfully defended the organisation from several cyber incidents
3. Provided significant Information Governance and Security advice for
the continued deployment of M365 and Google Workspace
4. Audit on business continuity
5. Ran successful phishing exercises
Cyber Security
Information
Governance and
*Compliance
Manager; Chief
*Digital Officer;
31-Mar-2025  75%
Page 284 of 396

Page 285

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Q1 24/25 - Action/mitigation includes: -
1. Achieved Cyber Essentials Plus Certification
2. Achieved PSN Certification from the Cabinet Office
3. Organised and facilitated a leadership forum exercise on cyber
resilience
4. Successfully responded to 15 significant cyber security events
5. Provided significant Information Governance and Security advice for
the continued deployment of M365 and Google Workspace 
Q4 23/24: Ongoing review of cyber incident response plans. Information
Governance and Security processes for M365 deployment ongoing and a number
of milestones achieved to progress further rollout of applications within M365
environment. Leadership Forum tabletop session scheduled June 2024. 
SRP.RR.22 Cost of Living Crisis 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.R
R.22
Risk cause
The UK is currently facing an
unprecedented storm of increasing prices,
bills and tax. The 40-year high inflation
rate of 9% is the main driver of the cost of
living crisis which has outstripped wage
and benefit increases. 
Risk event
Rapid ongoing rise of energy prices as
well as food and drink prices. 
Risk effect The impact on households is
already being noted with 87% of adults in
the UK reported an increase in their cost
of living in April 2022 (Office for National
Statistics; Francis-Devine et al, 2022). The
price rises will impact low-income
households the hardest as a larger
proportion of their bills are on energy and
Chief *Executive;
Director *Health
and Social Care;
Executive
Director *Place
1. Council Cost of Living Task Force to oversee the Council’s response
to the crisis 
2. Allocation of LACER funding to support those most affected 
3. Strategic Evaluation Partner appointed to create poverty profile 
4. Community Planning Partnership has established a Midlothian
Strategic Poverty Prevention Group co-chaired by Council Leader and
Director of Public Health 
5. New Child Poverty chair and lead appointed (Executive Director
Children, Young People and Partnerships) 
6. Child Poverty self-evaluation underway with Improvement Service  
3 5 
Page 285 of 396

Page 286

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
food. The Resolution Foundation
estimates an extra 1.3 million people will
fall into absolute poverty in 2023, including
500,000 children. 
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.R
A.22.1 Cost of Living Task Force Q1 23/24: Meetings continuing.   Chief *Executive;  31-Mar-2024  100%
SRP.R
A.22.2 LACER funding
Q2 22/23: Identification of 15 trusted partners to distribute funding in
communities for food and fuel, wash and dry provision and support to establish
reheatable food initiatives.  
Lifelong Learning
and Employability;  31-Mar-2023  100% 
Page 286 of 396

Page 287

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Strategic Opportunities 
SRP.OP.08 Capital Projects - Housing 
Risk
Code Risk Identification Managed by Risk Commentary Risk Evaluation
SRP.O
P.08
Cost of delivering Affordable Housing
Supply Programme has risen at faster rate
than available grant to Midlothian and
continued high build costs will affect ability
to deliver housing programme. 
Projects progressing, with Timeline,
Budget, Risk and Resource categorised
as parameters on a RAG status, with any
Red classifications identified and reported.   
Executive
Director *Place;
Head of
Development
1. Edmonstone Road, Shawfair – Timeline, Budget and Risk impacted
with Stewart Milne entering administration.  Midlothian Council now in
contract with Dundas Building and will be on site in May 2025.
3. Newton Church Road, Danderhall – Start on site delayed due to
commercial negotiation with Ogilvie. On site March 2025. 
Phase 5 housing programme has been reviewed to ensure affordability
within the Housing Revenue Account. Grant level now restored to
2023/24 level with core RPA £10.534m and additional grant uplift from
£40m of £1.062m, which is to be used for acquisitions to address
temporary accommodation pressures. 
Timeline Budget Risk Resource
R A A G
R A A G
SRP.OP.09 Capital Projects – Transport, Net Zero & Infrastructure 
Risk
Code Risk Identification Managed by Risk Commentary Risk Evaluation
SRP.O
P.09
Cost of delivering enabling infrastructure
projects has risen, resulting in significant
funding gap emerging. 
Projects progressing, with Timeline,
Budget, Risk and Resource categorised
as parameters on a RAG status, with any
Red classifications identified and reported.  
Executive
Director *Place;
Head of
Development  
1. A701 Relief Road
2. A701 Sustainable Trasport Corridor
3. A701 Straiton Junction Improvements 
For all highlighted projects, estimated cost significantly exceeds budget
available to deliver project. 
For all highlighted projects, addressing requirement for investment in
A701 corridor in phases with prioritisation applied. Bush Loan Junction
progressing ahead of remaining programme fully funded by ESESCRD
funding. 
Timeline Budget Risk Resource
A R R G
A R R G
A R R G     
Page 287 of 396

Page 288

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
SRP.OP.10 Capital Projects – Children, Young People & Partnerships Estates Programme: Primary 
Risk
Code Risk Identification Managed by Risk Commentary Risk Evaluation
SRP.O
P.10
Projects progressing, with Timeline,
Budget, Risk and Resource categorised
as parameters on a RAG status, with any
Red classifications identified and reported.  
Executive
Director *Place;
Executive
Director CYPP;
Head of
Development  
1. Mayfield/St Lukes PS New Build: Programme delayed for project
revision. Mayfield School pupils were decanted to the new
Easthouses PS in December. Budget gap has lowered due to
intensive cost reduction exercise.
2. Mauricewood PS Extension & Refurbishment: Rising roll and
catchment review requires investment in school to address capacity
and suitability. Limited budget available.  Funding insufficient as
some contributions were withdrawn for pay for costs of previous
extension.
3. Bilston PS Extension: Rising roll and catchment review requires
investment in school to address capacity and suitability. Limited
budget available.  Design team appointed to develop investment in
school that aligns with budget available from Developer
Contributions. 
4. Relocation of Mount Esk Nursery / Hawthorden Extension: Rising
roll and catchment review requires investment in school to address
capacity and suitability. Limited budget available.  Design team
appointed to develop investment in school that aligns with budget
available from Developer Contributions. Stage 2 design and costs
complete. 
Timeline Budget Risk Resource
R R R A
R R R A
A A A A
A A A A   
SRP.OP.09 Capital Projects – Children, Young People & Partnerships Estates Programme: Secondary 
Risk
Code Risk Identification Managed by Risk Commentary Risk Evaluation
SRP.O
P.09
Projects progressing, with Timeline,
Budget, Risk and Resource categorised
as parameters on a RAG status, with any
Red classifications identified and reported.  
Executive
Director *Place;
Executive
Director CYPP;
Head of
Development  
1. Beeslack HS Replacement: Site acquisition being progressed.
Planning consent now in place. . Preferred contractor appointed
under two stage process.
2. Shawfair All Through: Site acquisition complete. School location
fixed with design team. Remediation programme underway by
Shawfair LLP. Shawfair All Thorugh Campus budget approved at
Council. 
3. Penicuik HS New Build: LEIP target for delivery is Dec 2026,
however programme for occupation is July 2027. Cost reports
tracking higher and risks identified in refurbishment works.  SFT 
Timeline Budget Risk Resource
A A A G
R A A A
A A A G
Page 288 of 396

Page 289

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
advising if additional LEIP funding available to address abnormal
costs. Contractor, Morrison Construction appointed Jan’25.  
SRP.OP.09 Capital Projects – Regeneration 
Risk
Code Risk Identification Managed by Risk Commentary Risk Evaluation
SRP.O
P.10
Projects progressing, with Timeline,
Budget, Risk and Resource categorised
as parameters on a RAG status, with any
Red classifications identified and reported.  
Executive
Director *Place;
Head of
Development  
1. Vogrie Changing Places: issues with contractor and obtaining
buliding warrant, however due to go on site this summer.
2. Destination Hillend: Alpine Coaster delivered with access and
parking infrastructure and Coaster now open. Project absorbed risk
and contingency.  Next Phase to be recast.
3. Hopefield Industrial Estate: Updated financial model required. Cost
plan for upgrade to infrastructure being developed
4. Dalkeith Asset Rationalisation Programme: Decant of staff to
Fairfield House underway and planning application for works to
Midlothian House to be submitted in June 2025 following public
consultation . 
Timeline Budget Risk Resource
R A R A
R R R A
R A A G
A G A G  
SRP.OP.04 City Deal 
Risk
Code Risk Identification Managed by Risk Control Measures Likelihood Impact Risk Evaluation
SRP.O
P.04
South East Scotland Region City Deal - a
bid for funding to Scottish and UK
Governments to accelerate economic
growth through investment in
infrastructure/ housing/ skills and
innovation. 200 Council Houses linked to
the City Deal. 
Head of *Adult
and Social Care;
Chief Operating
Officer
*Education; Chief
*Executive;
Director *Health
and Social Care;
Chief Officer
*Place; Executive
Director *Place;
Chief Officer
Corporate
Solutions; Chief
Finance Officer;
Chief Officer
1. Maintain strong Midlothian involvement through the City Deal
governance structure. 
2. Midlothian City Deal Key Officer (Internal) Group. 
3. Securing best arrangements for Midlothian through close liaison with
partners and conclusion of business cases.  
4 5 
Page 289 of 396

Page 290

STRATEGIC RISK PROFILE, Q4 Jan-Mar 2025 v1.2 
Young People
and Partnerships                
Related
Action
Code
Related Action Related action latest note Managed By Due Date Status
SRP.O
P.04.02
Realisation of outcomes of respective
workstreams Q1 24/25: Work continues on the relevant programmes.   Executive Director
*Place 31-Mar-2025  10% 
Page 290 of 396

Page 291

Audit Committee
Monday 16 June 2025
Item No 5.3 
Unaudited Annual Accounts 2024/25 
Report by David Gladwin, Chief Financial Officer and Section 95 Officer 
Report for Information 
1 Recommendation 
1.1 In accordance with The Local Authority Accounts (Scotland)
Regulations 2014 set out in section 3.2 of this report and specifically
sections 8 (9) and 8 (10), Audit Committee are asked to consider the
unaudited annual accounts for 2024/25. 
2 Purpose of Report / Executive Summary 
2.1 The purpose of this report is to outline material changes in the value of
net assets as at 31st March 2025 and to facilitate Audit Committee
consideration of the Council’s unaudited annual accounts for 2024/25. 
2.2 At the time of writing this report a final review of the document is
ongoing. 
Date: 12 June 2025 
Report Contact:
David Gladwin: 0131 271 3113
David.gladwin@midlothian.gov.uk 
Page 291 of 396

Page 292

2 
3 Background 
3.1 The unaudited annual accounts for 2024/25 are in the final stages of
preparation with work on track to complete the document in advance of
the statutory deadline of 30th June. A draft copy of the accounts will be
issued to Committee members in advance of the meeting and will
published online once signed after Audit Committee consideration. 
3.2 The Local Authority Accounts (Scotland) Regulations 2014 sets out the
requirements in respect of preparation, submission and scrutiny of
unaudited accounts as follows, paragraphs 9 and 10 set out the
requirements for Audit Committee to consider the unaudited annual
accounts by 31st August 2025. 
Published Accounts and Audit
8.—(1) A local authority must ensure that its Annual Accounts are prepared in
accordance with these Regulations and, so far as compatible with these  Regulations,
in accordance with proper accounting practices.
(2) The Annual Accounts must include, in addition to the financial statements required
by proper accounting practices, the following statements, which are to be prepared in
accordance with proper accounting practices and recognised guidance—
(a) a management commentary;
(b) a statement of responsibilities;
(c) an annual governance statement;
(d) either—
(i) a remuneration report in the style set out in the Schedule to these
Regulations, or
(ii) a statement that no remuneration report has been prepared
because no persons have received remuneration that requires to be
included in such a report.
(3) The Annual Accounts must also include such of the following statements and
disclosures as are relevant to the functions of the local authority—
(a) a housing revenue account;
(b) a non-domestic rate account;
(c) a council tax account;
(d) any other statement relating to statutory funds which is required by any
statutory provision.
(4) The remuneration report referred to in paragraph (2)(d)(i) must contain the
information set out in the Schedule to these Regulations.
(5) The proper officer must ensure that—
(a) the statement of responsibilities required by paragraph (2)(b) accurately
reflects the proper officer’s responsibilities; and
(b) the financial statements give a true and fair view of the financial position
of the local authority and its group at the end of the financial year and the
transactions of the local authority and its group for that year.
(6) Once the proper officer is satisfied as to the matters set out in paragraph (5), the
proper officer must certify these matters by signing and dating the statement of
responsibilities and the balance sheets contained within the Annual Accounts and
then submit the Annual Accounts to the auditor.
(7) The Annual Accounts must be submitted to the auditor no later than 30th June
immediately following the financial year to which the Annual Accounts relate.
(8) The local authority must publish a copy of the Annual Accounts submitted to the
auditor, clearly identified as an unaudited version, on a website of the authority from
the date they are submitted until the date on which the audited Annual Accounts are
published in accordance with regulation 11.
(9) A local authority or a committee of that authority whose remit includes audit or
governance functions must meet to consider the unaudited Annual Accounts as
submitted to the auditor.
(10) The meeting referred to in paragraph (9) must be held no later than 31st August
immediately following the financial year to which the Annual Accounts relate. 
Page 292 of 396

Page 293

3
3.3  As required by paragraph 6 and 7 of the regulations the unaudited
annual accounts will be signed by the Chief Financial Officer on or
before the 30th June 2025 and immediately submitted to Audit
Scotland, the Council’s appointed external auditors. 
3.4 The regulations also provides for public inspection and this will run from
30th June 2025 to 21st July 2025. 
3.5 Separately, on the Council agenda for 24th June 2025, are the year-
end financial monitoring reports which provide commentary on the in-
year spend against budget and reserves positions for the following
account areas:
• Financial Monitoring 2024/25 General Fund Revenue;
• Housing Revenue Account Revenue and Capital Plan Final Outturn
2024/25;
• General Services Capital Plan Outturn 2024/25. 
3.6 The Annual Treasury Management Report 2024/25 is on the Audit
Committee agenda today and will subsequently be reported to Council. 
4 Financial Statements Presentation 
4.1 There continues to be refinements to the format and presentation of the
annual accounts as part of a continuous improvement approach. 
4.2 There is one significant change to the accounting code for 2024/25 that
impacts materially on the Council’s accounts. The accounting
requirements of International Financial Reporting Standard (IFRS) 16
(Leases) has been reflected in the Council’s Accounts. At this stage
figures in the draft accounts are provisional whilst we await final figures
from MUFG Corporate Markets who have been commissioned by the
Council to undertake a detailed assessment of scope, provide the
appropriate accounting entries and support with Audit work in this area. 
4.3 IFRS16 requires recognition of assets and liabilities for almost all
leases with assessment of eligibility centred around control of an
identified asset for a period of time. Previously the costs of many of
these arrangements may have simply been revenue expenses. 
5 Long Term Assets 
5.1 The total value of Long-Term Assets increased during the year by £30
million reflecting further investment in the asset base and changes to
the value of the Council’s asset base. 
5.2 For the School estate the Council’s valuation methodology applies
published Scottish Futures Trust (SFT) metrics intrinsic in the Learning
Estate Investment Programme (LEIP) alongside evidence on the cost
of school builds in Midlothian in recent years. 
5.3 Valuation methodology for the Council Housing stock was an area
raised during the 2023/24 audit resulting in a recommendation that
management consider the use of a rent yield adjustment in the
valuations of council dwellings. Further work has been done in this area
Page 293 of 396

Page 294

4
but at this stage the valuation basis remains consistent with 2023/24
and previous years. To progress this issue to conclusion requires
further engagement with Audit Scotland and this will take place during
the audit process. As a consequence, a revised valuation methodology
and consequently an adjustment to the reported value of Housing
Stock may need to be reflected in the draft audited accounts.   
5.4 In 2020/21 the Council amended the valuation basis for its
shareholding in Lothian Buses Ltd to exclude any impact from the
volatility of IAS 19 Pension valuation methodology. This basis of
valuation remains in 2024/25. Excluding pension valuations, Lothian
Buses Ltd accounts to 31st December 2024 show an increase in net
assets of £8.929 million. 
5.5 The Council have a 5.47% shareholding in Lothian Buses Ltd valued in
the accounts at £6.082 million. This is an increase of £0.489 million
from that in the 2023/24 accounts. 
5.6 Council approved a capped level of investment in Midlothian Energy
Limited of £8.6 million to support work on the initial Shawfair project.
During 2024/25 there was further drawdown of £4.589 million taking the
total to the maximum approved value. 
Lothian Pension Fund Valuation 
5.7 The requirement of International Accounting Standard (IAS) 19 –
Employee Benefits requires an annual actuarial valuation for
accounting purposes of the council’s share of Lothian Pension Fund.
There can be significant volatility between annual valuations. 
5.8 The draft accounts in front of Audit Committee today the incorporates
results based on actual figures for 2024/25. They show a net asset for
the Council’s share of Lothian Pension Fund of £273.943 million. This
is an increase of £87.414 million on the value at 31st March 2024. 
5.9 The accounting standard imposes a limit on the maximum amount of
surplus which can be recognised on an employer’s balance sheet and
this limit depends on factors unique to each employer. The limitation on
valuation is based on the remaining future working lifetime of active
staff and the present value of accruing service cost less value of cash
contributions. 
5.10 Application of this methodology results in the derecognition of all the
pension asset. However, the accounting standard requires inclusion of
the liability in relation to the present value of unfunded obligations. At
the 31st March this is £6.433 million being a £1.179 million reduction on
the figure as at 31st March 2024.   
5.11 Funding of pension obligations is determined by a full triennial valuation
and the 2023 triennial valuation showed an increase in the overall
funding position to 158% of assets relative to liabilities. In response the
contribution rate that the Council pay for employee members of Lothian
Page 294 of 396

Page 295

5
Pension Fund reduced from 22.2% in 23/24 to 17.6% for 2024/25 to
2026/27. The next triennial revaluation is in 2026. 
6 Current Assets 
6.1 At 31st March 2024, the combined value of short-term investments and
cash and cash equivalents shown in the Balance Sheet was £57.522
million. The position at 31st March 2025 of £26.948 million reflects an
increased under borrowed position of £90 million which is in line with
approved Treasury Strategy related to interest prospects for longer
term Public Works Loans Board borrowing.   
7 Long term Liabilities 
7.1 As the Council’s Public Private Partnership (PPP) and similar contracts
move a year closer to expiry there is reduction of £2.6 million in the
outstanding long-term liability. 
7.2 Despite maintaining the Treasury Strategy of delaying longer term
borrowing whilst interest rates remain high it was appropriate towards
the end of the financial year to take some shorter dated long-term
borrowing to the value of £40 million. 
8 Audit and Consideration of audited Accounts 
8.1 Audit Scotland are well underway with the initial phase of the 2024/25
audit. Plans for the substantive phase of the audit over the summer
months are in place with a clearance meeting expected during
September 2025. 
8.2 Thereafter, the audited annual accounts are scheduled to be presented
to Audit Committee on Tuesday 30th September 2025 together with the
Audit Scotland annual audit report which will also go on to Council in
October. 
8.3 The Local Authority Accounts (Scotland) Regulations 2014 also set out
the requirements for completion, approval and signing of the audited
accounts as follows. 
Consideration and Signing of Audited Annual Accounts
10.—(1) A local authority, or a committee of that authority whose remit includes audit or
governance functions, must—
(a) meet to consider the audited Annual Accounts; and
(b) aim to approve those accounts for signature as described in this regulation no
later than 30th September immediately following the financial year to which the
accounts relate.
(2) That local authority or committee must consider whether the Annual Accounts should be
signed, having regard to any report made on those accounts and any advice given by the
proper officer or the auditor.
(3) Immediately following the approval of the Annual Accounts for signature, the statements
which form part of those accounts are to be signed and dated as follows—
(a) the management commentary by the proper officer, the Chief Executive and the
Leader of the Council;
(b) the statement of responsibilities by the Leader of the Council and the proper
officer, who must also certify the matters referred to in paragraphs (5) and (6)
respectively;
Page 295 of 396

Page 296

6
(c) the annual governance statement by the Chief Executive and the Leader of the
Council;
(d) the remuneration report by the Chief Executive and the Leader of the Council; and
(e) the balance sheets by the proper officer, to authorise publication of the financial
statements.
(4) Where a local authority does not have a Chief Executive or a Leader of the Council, the
statements that paragraph (3) requires that person to sign are to be signed by such other
person as it nominates for that purpose.
(5) The person who signs the statement of responsibilities as Leader of the Council must
certify that the Annual Accounts have been approved for signature by, or on behalf of, the
authority.
(6) The proper officer must certify that the financial statements give a true and fair view of the
financial position of the local authority and its group at the end of the financial year and the
transactions of the local authority and its group for that year.
(7) Following the signature of the Annual Accounts, the proper officer must provide the Annual
Accounts, including the signed statements, to the auditor.
(8) Any further report provided by the auditor following the signature of the Annual Accounts
which relates to those accounts must be considered by the local authority or a committee of
that authority whose remit includes audit or governance functions. 
9 Report Implications 
9.1  Resource
Whilst this report deals with financial issues there are no financial
implications arising directly from it. 
9.2 Digital
There are no IT implications arising from this report. 
9.3  Risk
Section 95 of the Local Government (Scotland) Act 1973 requires all
Local Authorities in Scotland to have adequate systems and controls in
place to ensure the proper administration of their financial affairs. The
Council’s Standing Orders and Financial Regulations detail the
responsibilities of members and officers in relation to the conduct of the
Council’s financial affairs. 
9.4 Ensuring Equalities
There are no equality implications arising directly from this report. 
9.5 Additional Report Implications (See Appendix A) 
Appendices 
Appendix A – Additional Report Implications 
Page 296 of 396

Page 297

7
APPENDIX A – Additional Report Implications 
A.1 Key Priorities within the Single Midlothian Plan 
Midlothian Council and its Community Planning Partners have made a
commitment to treat the following areas as key priorities under the
Single Midlothian Plan:- 
• Reducing the gap in learning outcomes
• Reducing the gap in health outcomes
• Reducing the gap in economic circumstances 
This report does not directly impact Midlothian Council’s key priorities
but a key message within the Accounts Commission report is that the
way Council’s respond to the financial challenge will inevitably impact
on how they can deliver of key priorities and outcomes. 
A.2 Key Drivers for Change 
Key drivers addressed in this report: 
Holistic Working 
Hub and Spoke 
Modern 
Sustainable 
Transformational 
Preventative 
Asset-based 
Continuous Improvement 
One size fits one 
None of the above 
A.3 Key Delivery Streams 
Key delivery streams addressed in this report: 
One Council Working with you, for you 
Preventative and Sustainable 
Efficient and Modern 
Innovative and Ambitious 
A.4 Delivering Best Value
The report does not directly impact on Delivering Best Value. 
A.5 Involving Communities and Other Stakeholders
No consultation was required. 
A.6 Impact on Performance and Outcomes
The decisions taken to balance the budget will have fundamental
implications for service performance and outcomes. The Council’s
Transformation Programme aims to minimise the impact on priority
services. 
Page 297 of 396

Page 298

8
A.7 Adopting a Preventative Approach
The proposals in this report do not directly impact on the adoption of a
preventative approach. 
A.8 Supporting Sustainable Development
There are no sustainability issues arising from this report. 
Page 298 of 396

Page 299

2024/25
www.midlothian.gov.uk
Midlothian Council 
Midlothian Council      
Unaudited Annual Accounts
Page 299 of 396

Page 300

WWW.MIDLOTHIAN.GOV.UK 
1 Table of Contents
Table of Contents 
TABLE OF CONTENTS .................................................................................................................... 0
MANAGEMENT COMMENTARY ...................................................................................................... 3
ABOUT MIDLOTHIAN COUNCIL ............................................................................................................... 3
KEY PRIORITIES AND OBJECTIVES ............................................................................................................ 4
KEY ACHIEVEMENTS AND HIGHLIGHTS FOR 2024/25 ................................................................................... 5
FINANCIAL PERFORMANCE FOR 2024/25 ................................................................................................. 5
RISKS AND UNCERTAINTIES FACING THE COUNCIL ..................................................................................... 12
LOOKING AHEAD .............................................................................................................................. 13
CONCLUSION .................................................................................................................................. 14
ACKNOWLEDGEMENTS ....................................................................................................................... 15
STATEMENT OF RESPONSIBILITIES .............................................................................................. 16
ANNUAL GOVERNANCE STATEMENT ........................................................................................... 17
REMUNERATION REPORT ........................................................................................................... 24
REMUNERATION OF COUNCILLORS ........................................................................................................ 24
REMUNERATION OF EMPLOYEES............................................................................................................ 25
PENSION BENEFITS ........................................................................................................................... 26
REMUNERATION OF OTHER EMPLOYEES BY PAY BANDS ............................................................................... 28
EXIT PACKAGES ................................................................................................................................ 28
TRADE UNION FACILITY ...................................................................................................................... 29
INDEPENDENT AUDITOR’S REPORT ............................................................................................. 30
EXPENDITURE AND FUNDING ANALYSIS ..................................................................................... 31
PRINCIPAL FINANCIAL STATEMENTS ........................................................................................... 32
GROUP AND COUNCIL COMPREHENSIVE INCOME AND EXPENDITURE STATEMENT .............................................. 33
GROUP AND COUNCIL MOVEMENT IN RESERVES STATEMENT ....................................................................... 34
GROUP AND COUNCIL BALANCE SHEET .................................................................................................. 35
GROUP AND COUNCIL CASH FLOW STATEMENT ........................................................................................ 36
NOTES TO THE ACCOUNTS ......................................................................................................... 37
1. ACCOUNTING POLICIES ........................................................................................................... 37
2. ACCOUNTING STANDARDS ISSUED, NOT YET ADOPTED .................................................................... 51
3. CRITICAL JUDGEMENTS IN APPLYING ACCOUNTING POLICIES ............................................................. 51
4. FUTURE ASSUMPTIONS AND ESTIMATION UNCERTAINTIES ................................................................. 51
5. EVENTS AFTER THE REPORTING PERIOD ........................................................................................ 54
6. NOTE TO THE EXPENDITURE AND FUNDING ANALYSIS ....................................................................... 55
7. ADJUSTMENTS BETWEEN ACCOUNTING BASIS AND FUNDING BASIS UNDER REGULATIONS ......................... 56
8. MOVEMENT IN EARMARKED RESERVES ......................................................................................... 58
9. OTHER OPERATING INCOME AND EXPENDITURE .............................................................................. 58
10. FINANCING AND INVESTMENT INCOME AND EXPENDITURE ................................................................. 58
11. TAXATION AND NON-SPECIFIC GRANT INCOME AND EXPENDITURE ...................................................... 58
12. GRANT INCOME ..................................................................................................................... 59
13. EXPENDITURE AND INCOME ANALYSED BY NATURE .......................................................................... 60
14. PROPERTY, PLANT AND EQUIPMENT............................................................................................. 61
15. INFRASTRUCTURE ASSETS ......................................................................................................... 64
Page 300 of 396

Page 301

WWW.MIDLOTHIAN.GOV.UK 
2 Table of Contents
16. HERITAGE ASSETS ................................................................................................................... 64
17. INTANGIBLE ASSETS ................................................................................................................ 64
18. LONG-TERM DEBTORS ............................................................................................................. 65
19. FINANCIAL INSTRUMENTS ......................................................................................................... 65
20. NATURE AND EXTENT OF RISKS ARISING FROM FINANCIAL INSTRUMENTS ............................................... 69
21. ASSETS HELD FOR SALE ........................................................................................................... 72
22. INVENTORIES ......................................................................................................................... 72
23. DEBTORS ............................................................................................................................. 72
24. CASH AND CASH EQUIVALENTS .................................................................................................. 73
25. CREDITORS ........................................................................................................................... 73
26. PROVISIONS .......................................................................................................................... 73
27. GRANTS RECEIVED IN ADVANCE ................................................................................................. 73
28. USABLE RESERVES .................................................................................................................. 74
29. UNUSABLE RESERVES .............................................................................................................. 74
30. EXTERNAL AUDIT COSTS ........................................................................................................... 76
31. RELATED PARTIES ................................................................................................................... 76
32. CAPITAL EXPENDITURE AND CAPITAL FINANCING ............................................................................ 78
33. LEASES ................................................................................................................................ 78
34. PUBLIC PRIVATE PARTNERSHIP (PPP) AND SIMILAR CONTRACTS ......................................................... 79
35. PENSION SCHEMES ACCOUNTED FOR AS DEFINED BENEFIT CONTRIBUTION SCHEMES ............................. 82
36. DEFINED BENEFIT PENSION SCHEMES ......................................................................................... 83
37. CONTINGENT LIABILITIES .......................................................................................................... 87
38. TRUSTS AND BEQUESTS ............................................................................................................ 87
39. NOTES TO THE GROUP ACCOUNTS .............................................................................................. 87
SUPPLEMENTARY STATEMENTS .................................................................................................. 89
HOUSING REVENUE ACCOUNT ............................................................................................................. 89
NOTES TO THE HOUSING REVENUE ACCOUNT .......................................................................................... 90
COUNCIL TAX INCOME ACCOUNT.......................................................................................................... 91
NON-DOMESTIC RATE ACCOUNT .......................................................................................................... 93
GLOSSARY OF TERMS ................................................................................................................. 94 
Page 301 of 396

Page 302

WWW.MIDLOTHIAN.GOV.UK 
3 Management Commentary
Management Commentary
The Management Commentary is intended to assist users in understanding the objectives and strategy of
the Council and provide a review of its business and financial performance for the year. It also outlines the
principal risks and uncertainties which are likely to affect the future development and performance of the
Council.
The Annual Accounts present the financial position and performance of the Council, demonstrating the
stewardship of funds that support the Council’s vision and key priorities. The format and content of the
Annual Accounts are prepared in accordance with the Code of Practice on Local Authority Accounting in
the United Kingdom.
About Midlothian Council
Midlothian Council is located south of Edinburgh centred on the main towns of Penicuik, Dalkeith,
Bonnyrigg and Lasswade. One of the smaller local authority areas, but also one of the fastest growing, it
has emerged as a world centre for the Bioscience industry. Midlothian population has grown by 16.1%
between the census 2011 and 2022. Projections show a continued increase by a further 9.1% to 2043. Key
facts about Midlothian are: 
MidlothianEmployees
5,357
Population
96,527
(Census 2022)
Primary
Schools 33
Secondary
Schools 6
Elected
Members 18
(SNP 8, Lab 7,
Con 3)
Page 302 of 396

Page 303

WWW.MIDLOTHIAN.GOV.UK 
4 Management Commentary
Council Service Structure 
Key Priorities and Objectives
Midlothian Council’s key priorities and objectives are set out in in The Single Midlothian Plan (SMP). The
priorities are delivered through the Community Planning Partnership (CPP), which sets out how we
collaborate with communities and partners to deliver our vision for Midlothian to be a “Great Green Place
to Grow.” 
The Single Midlothian Plan has identified its three main outcomes for the next four years:
• Individuals and communities to have improved health and skills for learning, life and work;
• No child or household should be living in poverty;
• Significant progress to be made towards net carbon emissions by 2045.
These form the common and strategic guidance for the Council and its partners to encourage plans and
measures to be developed to work towards enabling individuals and communities being able to lead
healthier, safer and greener lives by 2030.
The Community Planning Partnership is led by the Community Planning Board, on which a number of
organisations sit and work together to achieve key actions towards seven thematic priorities across the
four years, with a more focused approach in reducing poverty and collaborating with communities to
increase wealth, reflecting the wellbeing and circular economy principles using a place based model.
Dr Grace Vickers
Chief Executive
PEOPLE AND
PARTNERSHIPS
Fiona Robertson
Executive Director
Children, Young People
and Parnerships
Chief Education Officer
Rebecca Hooten
Chief Officer Children's
Services, Partnerships and
Commuinities
Michelle Strong
Chief Education Operating
Officer
Morag Barrow
Joint Health and Social
Care
Chief Officer IJB
Nick Clater
Head of Adult Social Care
Chief Social Work Officer
Grace Cowan
Head of Primary Care and
Older People
PLACE
Kevin Anderson
Executive Director Place
Saty Kaur
Chief Officer
Corporate Solutions
Derek Oliver
Chief Officer Place
Fiona Clandillion
Head of
Development
FINANCE
David Gladwin
Chief Financial Officer
Section 95 Officer
Page 303 of 396

Page 304

WWW.MIDLOTHIAN.GOV.UK 
5 Management Commentary 
The annual Balanced Scorecard measures progress towards these outcomes and is used to show ongoing
improvements and reflect the ongoing challenges within Midlothian. The full detail behind the performance
indicators measured by the Balanced Scorecard for 2024/25 can be found on the Council’s website
Midlothian Council/Performance and spending.
Key Achievements and Highlights for 2024/25 
Achievement Commentary
Completion of
Woodburn Primary
School Extension
The £11.4 million extension and refurbishment project was completed during October
2024, six weeks ahead of schedule. The new 2,262 m2 extension and refurbishment
increases pupil capacity from a three-stream to a four-stream entry and is available for
the community to use.
Official Opening of
the Alpine Coaster
The Alpine Coster was officially opened to the public in September 2024. The coaster is
the only one in Scotland and the longest in the UK. The Alpine Coaster is part of the
ambitious Destination Hillend project – a national tourist attraction, with total visitor
numbers expected to rise, bringing in much needed additional revenue to the Council.
Official Opening of
New Easthouses
Primary School 
The new primary school, which was delivered on time and on budget, was opened in
August 2024.
Official Opening of
Midlothian Energy
Ltd (MEL)
The project is part of a partnership between Midlothian Council and Vattenfall to deliver
low carbon energy projects across the region. The first project is to supply low carbon
heat to new homes in Midlothian through the MEL heat network that is planned to expand
into existing buildings and other areas in Midlothian and north into Edinburgh.
Provision of
Affordable Housing
The Council’s Strategic Housing Investment Programme (SHIP) was submitted to the
Scottish Government in October 2024. To address the need for affordable housing the
SHIP details potential sites for 2,082 new affordable homes to be built during 2024 to
2030. During 2024/25 100 new Council houses were completed, this brings the total
completed to 1,755 over the past eighteen years, net of demolitions and disposals. In
addition, seven properties were purchased during the year to add to the overall housing
stock. 
Financial Performance for 2024/25
Financial information is part of the Council’s Performance Management Framework with the General Fund
and Housing Revenue Account (HRA) financial performance regularly reported to Council. This section
Page 304 of 396

Page 305

WWW.MIDLOTHIAN.GOV.UK 
6 Management Commentary
summarises our financial performance for 2024/25. Full details of the Council's financial performance
were reported to Council on 24 June 2025 and is available on the Council's website.
Usable Reserves
The Council holds funds in a number of Usable Reserves for various purposes. Details of the balances and
prior year comparatives are shown in the table below, more detail can be found in the Movement in
Reserves Statement on page 34. 
Usable Reserve  Purpose
2024/25
£000
2023/24
£000
General Fund Reserve – Non-earmarked  Funds held as a general contingency 6,408  9,318 
General Fund Reserve  - Earmarked Funds held for specific purposes (note 8) 25,621 37,021
Housing Revenue Account Funds held for investment in the Council’s
housing stock  31,910  33,182
Capital Fund Funds set aside for major capital
developments or asset purchases  17,600  17,242
Repairs and Renewals Fund Funds held for specific types of repairs and
maintenance work  3,756  4,113 
General Fund Performance
The General Fund is a statutory fund into which all the receipts of the Council are required to be paid and
out of which all liabilities of the Council are to be met, except to the extent the statutory rules provide
otherwise. Government grants, council tax income, fees and charges, non-domestic rates income (subject
to pooling arrangements) and interest/returns on investments provide resources to the General Fund. The
General Fund is split between non-earmarked balances (the level of funding available to the Council to
manage financial risks and unplanned expenditure) and balances that are earmarked for specific purposes
(note 8).
Actual outturns against budget for each of the Council’s General Fund Service areas are as follows: 
General Fund Revenue Outturn 2024/25   
Service Area
Revised
Budget
£000
Net
Expenditure
£000
(Under)/
Overspend
£000
Management and Members 2,684 2,464 (220)
Place:   
Corporate Solutions 25,009 26,469 1,460
Place 46,267 47,842 1,575
Central Costs 24 378 354
People and Partnerships:   
Midlothian Integration Joint Board 69,072 69,072 0
Adult Health and Social Care (Non-delegated) 719 707 (12)
Children’s Services, Partnerships and Communities 19,318 19,118 (200)
Education 149,246 150,600 1,354
Lothian Valuation Joint Board 582 613 31
Non-distributable Costs 992 923 (69)
Net Expenditure 313,913 318,186 4,273
Loan Charges 5,460 4,140 (1,320)
Non-domestic Discretionary Relief  70 77 7
Investment Income (111) (51) 60
Allocations to Housing Revenue Account  (5,537) (5,587) (50)
Total Expenditure 313,795 316,765 2,970
Less Funding:   
Scottish Government Grant (229,789) (229,964) (175)
Council Tax (64,686) (64,170) 516
Service Concessions – in-year adjustment (2,796) (2,796) 0
Utilisation of Reserves 16,524 19,835 3,311 
Page 305 of 396

Page 306

WWW.MIDLOTHIAN.GOV.UK 
7 Management Commentary
The most significant areas (greater than £0.500 million) contributing to variances against budget in the
Council service areas were in relation to:
• The cost of transporting school pupils to school exceeded budget by £1.677 million;
• The level of maternity cover required in schools and deployment of temporary resources in areas
of the council where permanent recruitment of staff has been challenging resulted in an
overspend pf £0.987 million;
• A reduction in housing benefit subsidy received from the Department of Work and Pensions of
£0.537 million. This relates to an ongoing appeal relating to error testing in a previous financial
year;
• Council Tax Income was £0.516 million lower than budged due to household growth being slower
than anticipated, a significant increase in the number of households eligible for single person
discount and a slight increase in bad debt provision;
• Additional costs in relation to the extension of the bulky items disposal contract and legislative
changes in relation to treatment and haulage of air pollution contaminants have increased costs
of waste disposal by £0.529 million;
• The cost of maintaining ageing vehicles, higher than anticipated volumes of externally contracted
repairs and subsequent external fleet hire to support service continuity during periods of vehicle
downtime resulted in an overspend for fleet of £0.573 million.
Offset by:-
• A reduction in loan charges of £1.320 million due to deferral of borrowing to later years, a reduction
of £36 million in the borrowing requirement for 2024/25 and higher than forecast surplus cash
providing opportunity to generate deposit income. These all relate to timing of planned capital
expenditure. 
Full details of all other variances affecting the final outturn position can be found in the 24 June Council
report Midlothian Council > Meetings.
Midlothian Council provide Midlothian Integration Joint Board (MIJB) an annual sum for services managed
by Midlothian Health and Social Care Partnership. This sum is adjusted in-year in accordance with the
integration scheme. In 2024/25 MIJB spend exceeded budget by £8.888. Of this, £4.883 million related to
Adult Social Care services and in accordance with the Integration Scheme, required a further allocation
from the Council to MIJB to fund this. Detailed commentary on the financial performance of the Midlothian
Integration Joint Board is contained in their annual accounts.
Summary Position
The Council approved a reserves strategy in February 2019 setting the minimum level of uncommitted
reserve of two percent of net expenditure (excluding resources delegated to Midlothian Integration Joint
Board), which now equates to £4.9 million. In 2024/25 there was a decrease of £19.835 million in the
General Fund Reserve, as shown in the table below:
Movement in General Fund Reserve £000
2024/25 performance against budget 3,311
Planned utilisation of reserves 22,836
Supplementary Estimate for MIJB 4,883
Budget carried forward for use in future years (11,195)
Total Movement 19,835 
Page 306 of 396

Page 307

WWW.MIDLOTHIAN.GOV.UK 
8 Management Commentary
Housing Revenue Account
The Council has a statutory obligation to maintain a revenue account for its housing provision in
accordance with the Housing (Scotland) Act 1987. The Housing Revenue Account records all income and
expenditure relating to the Council's own housing stock. Rents paid by tenants’ funds the revenue
expenditure on housing management, repairs and maintenance and in part financing capital expenditure.
The table below provides analysis of financial performance for 2024/25: 
Housing Revenue Account Outturn 2024/25
Revised
Budget
£000
Net
Expenditure
£000
(Under)/
Overspend
£000
Expenditure:   
Repairs and Maintenance 9,157 12,775 3,618
Administration and Management 5,537 5,587 50
Loan Charges 16,568 15,532 (1,036)
Other Expenses 2,979 3,760 781
Total Expenditure 34,241 37,654 3,413
Income:   
Council House Rents (35,299) (35,516) (217)
Other Rents and Recharges (866) (866) 0
Total Income (36,165) (36,382) (217)
Utilisation of Reserves (1,924) 1,272 3,196 
Overall, the Housing Revenue Account showed an overspend of £3.196 million at the year-end mainly due
to:
• High value repairs, particularly in relation to essential damp, roofing works and electrical
insulation contributed to an overspend in repairs to the housing stock of £3.618 million;
• An increase in levels of outstanding debt and write-offs of historic debt resulted in an overspend 
of £0.607 million;
Offset by:-
• The timing of delivery of HRA capital plan projects allowed lower than expected loan charges of
£1.036 million.
The closing balance on the Housing Revenue Account reserve is £31.910 million which is committed to
fund the Council’s ambitious capital investment plan, currently running to 2039/40. The capital plan
includes provision to build additional housing stock and continue to  improve and upgrade its existing
stock, particularly through Scottish Quality Housing Standard (SHQS) and Energy Efficiency Standard for
Social Housing (EESSH) works. The majority of this plan is funded through prudential borrowing with costs
of borrowing met from rental income and planned utilisation of the Housing Revenue Account reserve,
which is projected to reduce to approximately £2 million by the end of the plan.
Reconciliation of General Fund and Housing Revenue Account Monitoring to the EFA
The table below provides a reconciliation to assist users of the accounts to navigate from the Midlothian
Council Budget Monitoring position reported in the previous section to the first column in the Expenditure
and Funding Analysis (EFA) on page 31. The EFA provides the link between the Final Outturn reports and
the figure in the Comprehensive Income and Expenditure Statement (CIES) by removing the various
statutory adjustments required under generally accepted accounting practices. 
Page 307 of 396

Page 308

WWW.MIDLOTHIAN.GOV.UK 
9 Management Commentary
Final Outturn to EFA Reconciliation   
Service Area 
Final
Outturn
£000
Internal
Reporting
Adjustments
£000
Figure
Reported
in EFA
£000
Management and Members 2,464 (469) 1,995
Place:   
Corporate Solutions 26,469 (67) 26,402
Place 47,842 (10,306) 37,536
Central Costs 378 (69) 309
People and Partnerships:   
Midlothian Integration Joint Board 69,072 (41) 69,031
Adult Health and Social Care (Non-delegated) 707 (1) 706
Children’s Services, Partnerships and Communities 19,118 (26) 19,092
Education 150,600 (11,157) 139,443
Lothian Valuation Joint Boards 613 0 613
Non-distributable Costs 923 0 923
Add Back:   
Housing Revenue Account 0 (14,668) (14,668)
Net Expenditure 318,186 (36,804) 281,382
Loan Charges 4,140 26,613 30,753
Non-domestic Discretionary Relief  77 (77) 0
Investment Income (51) 0 (51)
Allocations to Housing Revenue Account  (5,587) 5,587 0
Service Concessions (2,796) 0 (2,796)
Scottish Government Grant (229,964) 77 (229,887)
Council Tax (64,170) 5,876 (58,294)
Total Funding and Other Expenditure (298,351) 38,076 (260,275)
Utilisation of Reserves 19,835 1,272 21,107 
Internal Reporting Adjustments     
HRA (1)  PPP and
Leases (2) 
Council
Tax
Reduction
(3)  Other(4)  Total 
Service Area £000 £000 £000 £000 £000
Management and Members (87) 0 0 (382) (469)
Place:     
Corporate Solutions (2,593) 0 (5,876) 8,402 (67)
Place (2,560) 320 0 (8,066) (10,306)
Central Costs 0 0 0 (69) (69)
People and Partnerships:     
Midlothian Integration Joint Board 0 (41) 0 0 (41)
Adult Health and Social Care (Non-delegated)    (1) (1)
Children’s Services, Partnerships and Communities 0 (8) 0 (18) (26)
Education 0 (10,368) 0 (789) (11,157)
Lothian Valuation Joint Boards 0 0 0 0 0
Non-distributable Costs 0 0 0 0 0
Add Back:     
Housing Revenue Account (14,608) (60) 0 0 (14,668)
Net Expenditure (19,848) (10,157) (5,876) (923) (36,804)
Loan Charges 15,533 10,157 0 923 26,613
Non-domestic Discretionary Relief  0 0 0 (77) (77)
Investment Income 0 0 0 0 0
Allocations to Housing Revenue Account  5,587 0 0 0 5,587
Service Concessions 0 0 0 0 0
Scottish Government Grant 0 0 0 77 77
Council Tax 0 0 5,876 0 5,876
Total Funding and Other Expenditure 21,120 10,157 5,876 923 38,076
Utilisation of Reserves 1,272 0 0 0 1,272
1. As part of the financial monitoring process the Council reports on the Housing Revenue Account separately from the
General Fund, this adjustment adds back the Housing Revenue Account to reflect the structure reported in the Expenditure
and Funding Analysis.
2. The Council has a number of Public Private Partnership (PPP) and  lease arrangements  which fall under IFRS 16.
Accounting regulations require to be treated as finance leases. This is a statutory adjustment which is not required for
internal reporting purposes.
Page 308 of 396

Page 309

WWW.MIDLOTHIAN.GOV.UK 
10 Management Commentary
3. For the purpose of the annual accounts the cost of  the Council Tax Reduction Scheme is offset against the Council Tax
Income received, whereas this is reported against the service area as part of the internal reporting process.
4. Various other presentational adjustments.
Capital Expenditure 2024/25
Capital expenditure is the money spent by the Council for buying, upgrading or improving assets such as
buildings and roads. The difference between capital and revenue expenditure is that the Council receives
the benefit from capital expenditure over a period exceeding one year. In 2024/25 the final budget for
General Services capital investment was £49.270 million (2023/24 £47.509 million), which was underspent
by £0.236 million. The table below identifies actual capital spend during the financial year for key projects
classes:
2023/24
Revised
Budget
2023/24
Actual
Spend 
2024/25
Revised
Budget
2024/25
Actual
Spend
£000 £000 General Fund Capital Spend £000 £000
26,047 26,241 School Estate 17,532 17,218
2,007 2,007 Roads, Pavements and Street Lighting 6,971 6,971
6,263 6,263 Regeneration and Development 15,078 15,078
5,137 5,137 Fleet Replacement and Upgrades 2,401 2,401
2,824 2,824 Digital Assets 2,560 2,560
2,358 2,340 Transport, Energy and Infrastructure 2,361 2,346
599 599 Centralised Property Upgrades 872 872
2,274 2,245 Other Capital Projects 1,495 1,588
47,509 47,656 Total  49,270 49,034 
The table below demonstrates the breakdown of the Housing Revenue Account Capital Spend for 2024/25:
2023/24
Revised
Budget
2023/24
Actual
Spend 
2024/25
Revised
Budget
2024/25
Actual
Spend
£000 £000 Housing Capital Spend £000 £000
39,215 39,215 New Social Housing and Market Purchases 42,247 42,247
8,570 8,570 Scottish Housing Quality Standard (SHQS) Works 7,739 7,739
1,267 1,267 Energy Efficiency Standard for Social Housing (EESSH 2) 2,724 2,724
1,396 1,360 Other Housing Capital Projects 625 464
50,448 50,412 Total  53,335 53,174 
A combination of government grants, external funding contributions from third parties, capital receipts,
Section 75 developer contributions and prudential borrowing funded this expenditure. Note 32 in the
accounts provides a full analysis of capital expenditure and the financing required.
Treasury Management and Investment
The Council is able to regulate its own capital spending limits within a prudential framework recommended
by the Chartered Institute of Public Finance and Accountancy (CIPFA) and endorsed by Scottish
Government, provided it operates within a series of indicators. The Council’s capital expenditure is a key
driver of treasury management activity, and these indicators are relevant for the purposes of establishing
an integrated treasury management strategy, which demonstrates that the Council’s capital investment
plans are affordable, prudent and sustainable. 
Page 309 of 396

Page 310

WWW.MIDLOTHIAN.GOV.UK 
11 Management Commentary
Financial Indicator 2023/24 2024/25 Commentary 
Capital financing requirement (excluding PPP
and similar contracts)  £401.845m  £469.866m
Reflects the Council’s underlying need to
borrow to finance capital expenditure
incurred historically by the Council that has
yet to be financed. 
Authorised debt limit  £534.105m  £604.957m
This is calculated in line with the requirements
of the Prudential Code for Capital Finance in
Local Authorities and  represents the
maximum amount that the Council may
borrow and is set at a level that reflects capital
expenditure but includes headroom to allow
for unusual cash movements. 
Actual external borrowing  £340.871m  £379.445m
The actual external debt and long-term
liabilities position of the Council. This figure
should never exceed the Councils authorised
debt limit (see indicator above). 
Under/(over) borrowed  £60.974m  £90.421m
This demonstrates that the Council’s capital
borrowing requirement has not been fully
funded by loan debt and is using cash from
working capital to support capital
programmes whilst interest rates on long-
term fixed rate borrowing are high. 
General Fund ratio of finance costs to net
revenue stream  0.60%  1.63%
This is a measure of how affordable the
Council’s capital plans are. It takes actual
finance costs as a % of net revenue.
HRA ratio of finance costs to net revenue
stream  40.24%  42.81%  As above. 
External Loans Fund Interest Rate  3.00%  3.14%  Average rate of interest paid on external debt. 
Internal Loans Fund Interest Rate  2.08%  2.73%
This combines the interest paid by the Council
on money borrowed, with the interest earned
by the Council on money invested, along with
other charges to arrive at  a weighted average
‘loans fund rate’ figure for the Council. 
The borrowing strategy is prepared in accordance with the Code of Practice on Treasury Management in
Local Authorities. The majority of the Council’s borrowing comes from Public Works Loan Board (PWLB).
Note 19 and 20 of the accounts provides further information on the Council's borrowing.
Balance Sheet
The table below summarises the Council’s Balance Sheet as at 31 March 2025. The Balance Sheet brings
together assets and liabilities, year-end balances, money owed to and by the Council and reserves. More
information on the Balance Sheet is provided on page 35. 
31 March 25
£000
31 March 24
£000
Change
£000
Long-term Assets 1,255,439 1,225,660 29,779
Current Assets 51,776 98,298 (46,522)
Current Liabilities (106,110) (96,872) (9,238)
Long-term Liabilities (467,126) (432,401) (34,725)
Net Assets 733,979 794,685 (60,706) 
The main areas of movement in the net assets of the Council relate to the following areas:-
Long-term Assets
Long-term Assets have decreased in value by £29.779 million. This is  primarily due to continued
investment in new assets across the Council and increase in the value of our existing assets which have
been revalued as part of our five-year rolling revaluation programme. Further details of these movements
can be found in Notes 14-17 of the annual accounts. 
Page 310 of 396

Page 311

WWW.MIDLOTHIAN.GOV.UK 
12 Management Commentary
Current Assets
A reduction in short-term and liquid deposits within current assets to £0.070 million, reflecting an
increased level of internal borrowing in line with the Council's treasury strategy.
Long-term Liabilities- Long-term Borrowing
Increase in the Council’s longer term borrowing of £37.725 million.
Long-term Liabilities- Pension Obligation
The impact of the Local Government Pension Scheme and Scottish Teachers Superannuation Scheme on
the Council’s accounts have been disclosed in Notes 34 and 35 to the accounts. As at 31 March 2025, the
Council’s share of Lothian Pension Fund shows a net pension asset of £273.943 million (2023/24 Pension
Asset £186.529 million). However, under the International Financial Reporting Interpretations Committee
Standard 14 – The Limit of a Defined Benefit Asset (IFRIC 14) the actuary has calculated the net present
value of future contributions of £913.931 million exceeds the value of the future service costs of £658.215
million, a negative contribution. As a result of this calculation, IFRIC 14 advises that no defined benefit
plan asset should be recognised in the Council’s Balance Sheet and there is no requirement to recognise
the £255.716 million difference as a liability, however the Council is required to reflect the liability in
relation to present value of unfunded obligations of £6.433 million and this figure is contained in the
Balance Sheet.
Formal actuarial valuations are conducted every three years, where each employer’s assets and liabilities
are calculated on a detailed basis, using individual member data, for cash contribution setting purposes.
The most recent formal valuation was March 2023 with the subsequent results based on a roll forward from
the formal valuation. The movements in the pension valuation is due to a combination of applying the
actuals pension increase order of 1.7% to the benefits, an increase in the discount rate of 1% and changes
in demographic assumptions by the actuary.
Risks and Uncertainties Facing the Council 
Like all local authorities Midlothian Council is facing a period of unprecedented change and financial
challenge with many factors affecting the need to adapt as an organisation. These pressures and demand
for Council services are only likely to increase as it reacts to future challenges which have been
exacerbated by the recent pandemic and growing cost of living crisis. Some of the challenges the Council
face include:
Risk and Uncertainty Commentary
Continued Demographic
Pressures
Continued demographic pressures particularly around looked after children,
people with learning disabilities, elderly care, school age pupils and the
significant population growth in Midlothian. Increasing financial hardship is
also expected due to pressures on household budgets. These pressures
continue to present a considerable challenge to the Council in both financing
them and transforming services to improve ways of managing some of the
service delivery to respond to these pressures. 
Delays in the supply chain
caused by local or global
market shortages
World events continue to contribute to a supply chain volatility leading to the
Council facing higher prices and shortages of key resources, particularly in the
construction and care sectors. This has resulted in longer lead times and
increased development costs in maintaining existing and constructing new
capital assets. The Council continues to monitor the impact of this on delivery
of its front-line services and its capital programmes.
Climate Change The Council recognises that climate change is an urgent issue and has
committed to significantly reduce carbon emissions by 2045. This will require
significant investment and resource to achieve this.
Financial Pressures Pay, general inflationary pressures and available Scottish Government Grant
funding are critical areas of modelling given their overall significance and
uncertainty. For 2024/25, and again for 2025/26, the Scottish Government
published a one-year budget and grant settlement. Pressure on the public
Page 311 of 396

Page 312

WWW.MIDLOTHIAN.GOV.UK 
13 Management Commentary
purse remains acute and indications are that grant support to Councils will
remain at, or close to, a cash flat level for at least the next few years. This
represents a challenging outlook for local government with a potential real
term reduction in grant income at a time when costs and service demands
continue to rise, particularly in Midlothian as the fastest growing Council.
There are a number of factors which will continue to influence the actual level
of grant support the Council might expect. Among these will be a range of
economic factors which will impact on the resources Scottish Government
has at its disposal, whether from the UK Government block grant or through
tax revenues directly controlled by Scottish Government. Scottish
Government priorities and policies relating to taxation and spending will also
be a key factor. 
Whilst an assessment of economic factors can be made at this time, based on various sets of published
information the impact of Scottish Government’s tax and spending priorities will only become apparent
when the Scottish Government’s 2026/27 budget is published later in 2025  and whilst the Council set a
balanced budget for 2025/26, which included a council tax increase of 10%, in the context of potentially
reduced real terms external funding and exponential growth in demand for services, the Council faces a
considerable challenge to ensure its future expenditure plans are financially sustainable.
How the Council Manages Risk 
Action Commentary
Service Risk Registers The service Risk Registers contain operational risks and are managed by each
Service Management Team. The Risk Management Group provides further
scrutiny of service risks and significant risks are added to the corporate risk
register.
The Corporate Risk Register The Corporate Risk Register managed by the Corporate Management Team
provides assurance through scrutiny and challenge and ensures that the
significant risks facing the Council have been identified and effective
treatment actions are implemented. The Corporate Risk Register is then
submitted to Audit Committee for approval which provides effective scrutiny
and challenge as part of the Council’s corporate governance arrangements.
Development of a Medium-term
Financial Strategy (MTFS)
The Council’s Medium-term financial outlook highlights significant funding
pressure that the Council may face over the next few years. On 25 February
2025 Council agreed a Medium-term Financial Strategy 2025/26-
2029/30, which sets out budget projections for this period and shows a
projected budget gap of £8.9 million by 2028/29. 
The MTFS set out cost projections for pay and price inflation, debt charges and
the impact of demographic changes together with projections of income. As a
framework to address the financial challenge, Council approved a
Transformation Blueprint which contains five main strategic themes of
Following the Money, 21st Century Workforce, Commercialisation and Income
Generation, Workplaces of the Future and Multi-Agency Transformation.
Within each theme sits a number of individual projects phased over the next
two financial years. Council will also continue to explore any options to
increase external funding including ongoing discussion with the Scottish
Government on funding fast growing Councils. 
Looking Ahead
Economic performance has a significant impact on the availability of funding and demand for public
services. The February 2025 the Bank of England monetary report states that whilst progress towards
achieving the 2% cpi inflation target remains consistent, there are still significant uncertainties around the
current and prospective balance of demand and supply in the economy, therefore the Monetary Policy
Page 312 of 396

Page 313

WWW.MIDLOTHIAN.GOV.UK 
14 Management Commentary
Committee is maintaining its focus on the persistence of inflationary pressures in the medium term to
ensure sustainability of this target. 
In addition, Midlothian Council also faces additional pressure being the fastest growing local authority in
Scotland, resulting in greater demand for services with future funding for Local Government likely to
remain constrained. The Council’s Capital Plan remains under pressure but contains further major
investment in the following areas over the coming years:
Capital Expenditure Commentary
School Infrastructure • Wide-ranging school building, extension and refurbishment programme
including a major project at Penicuik High School;
• A new 3-18 school at Shawfair;
• Replacement Schools for:
o Beeslack Community High School;
o Mayfield Primary School Campus.
Provision of Care Services A new care facility in Bonnyrigg which will provide accommodation for those in
need of high quality care.
Carriageway and Footway
Infrastructure
• Continuing investment in improved roads, footpaths and lighting across
Midlothian;
• As part of the Edinburgh and South East Scotland City Region Deal major
investment is also planned in the new A701 Relief Road and A702 link
which will support planned investment in new research and technology
facilities at Easter Bush.
Social Housing A continuation of the new build housing programme and upgrading of existing
housing, particularly with regard to energy efficiency measures to work
towards the Councils carbon neutral target. 
The Council has recognised the need for a strategic step change in the form of the Medium-Term Financial
Plan together with resource allocation measures that will enable the Council to balance revenue budgets
for each financial year.
The Council continues to regularly monitor its financial position and provide full financial updates to the
Corporate Management Team and elected members as appropriate, including options on addressing any
new budgetary and spending pressures. This may include further use of reserves, reallocation of
committed reserves, changes to capital spend, or other cost savings. Management is continuing to engage
with the Scottish Government on providing sustainable funding going forward.
The Council will continue to assess the potential impact of the external risks and challenges facing the
Council, including the possible financial and economic impacts. From a financial perspective, the
potential impact on future Scottish Government grant funding levels, and from an economic perspective,
the potential lack of skilled resource and the impact on the local economy.
In delivering services, it is important to recognise that people are our most important asset. Our people
have the potential to have a positive impact every day and can deliver life-changing impacts for our
communities. Therefore, to maximise that positive impact, it is imperative that we work as One Council by
removing any institutional barriers; and eliminate silo working to enable the organisation to implement
simple solutions which make a big difference. This means placing our citizens and communities at the
centre of our daily work; growing our own talent and empowering our staff and thereby enabling Midlothian
to fulfil its potential as a ‘Green Great Place to Grow.’
Conclusion
Budget constraints and increasing cost pressures are putting Scotland’s councils’ finances under a severe
strain. COSLA have continued to highlight that funding in the Local Government Finance Settlement falls
short of the amount required to protect local services. Adding to the challenge of constrained funding,
Midlothian Council continues to face the ongoing impacts of a global pandemic as well as long-standing
and growing demographic pressures and the impact of pressured household budgets thus placing
Page 313 of 396

Page 314

WWW.MIDLOTHIAN.GOV.UK 
15 Management Commentary
increasing pressures on Council resources and demand for its services. Despite these pressures, the
Council continues to make significant improvements across a range of service areas and is investing in its
asset base to provide essential infrastructure to support the growing population. It is important to
appreciate these improvements. 
We have concluded the year with financial challenge ahead but with a focus on meeting the challenges
identified in the Medium-Term Financial Strategy and the Transformation Blueprint to ensure the Council
maintains longer-term financial sustainability.
Acknowledgements
We would like to acknowledge the tremendous effort undertaken in producing the Annual Accounts and
express our thanks to colleagues throughout the Council for the significant dedication and commitment
shown throughout the year in financial matters. 
_____________________  _____________________  _____________________
David Gladwin   Dr Grace Vickers  Councillor Kelly Parry                  
Chief Financial Officer  Chief Executive   Leader of the Council
and Section 95 Officer   
Page 314 of 396

Page 315

WWW.MIDLOTHIAN.GOV.UK 
16 Statement of Responsibilities 
Statement of Responsibilities
The Council’s Responsibilities
The Council is required to:
• Make arrangements for the proper administration of its financial affairs and to secure that one of its
officers has the responsibility for the administration of those affairs. In this Council, that officer is the
Chief Financial Officer;
• Manage its affairs to secure economic, efficient and effective use of resources and safeguard its
assets.
I certify that the Annual Accounts have been approved for signature by, or on behalf of, the authority. 
___________________________
Councillor Kelly Parry
Leader of the Council 
The Chief Financial Officer Responsibilities
The Chief Financial Officer is responsible for the preparation of the Council’s Annual Accounts in
accordance with proper practices as required by legislation and as set out in the CIPFA/LASAAC Code of
Practice on Local Authority Accounting in the United Kingdom (the code).
In preparing these Annual Accounts, the Chief Financial Officer has:
• Selected suitable accounting policies and then applied them consistently;
• Made judgements and estimates that were reasonable and prudent;
• Complied with the local authority code;
• Kept proper accounting records, which were up to date;
• Taken reasonable steps for the prevention and detection of fraud and other irregularities.
I certify that the financial statements present a true and fair view of the financial position of the Council
(and its group) at the reporting date and the transactions of the Council (and its group) for the year ended
31 March 2025. 
___________________________
David Gladwin
Chief Financial Officer 
Page 315 of 396

Page 316

WWW.MIDLOTHIAN.GOV.UK 
17 Annual Governance Statement
Annual Governance Statement 
Introduction
The Annual Governance Statement explains how the Council has complied with the terms of the
CIPFA/SOLACE Framework (2016) for the year ended 31 March 2025, sets out the Council’s governance
arrangements and systems of internal control, and reports on their effectiveness. The statement also
covers relevant governance matters as they affect those entities included as part of the Council’s Group
Accounts.
Scope of Responsibility 
Midlothian Council is responsible for ensuring that its business is conducted in accordance with the law
and proper standards, and that public money is safeguarded and properly accounted for. The Council also
has a statutory duty of Best Value under the Local Government in Scotland Act 2003 to make arrangements
to secure continuous improvement and performance, while maintaining an appropriate balance between
quality and cost; and in making these arrangements and securing that balance, to have regard to economy,
efficiency and effectiveness.
In discharging this overall responsibility, elected members and senior officers are responsible for putting
in place proper arrangements for the governance of Midlothian Council’s affairs and facilitating the
exercise of its functions in a timely, inclusive, open, honest and accountable manner. This includes setting
the strategic direction, vision, culture and values of the Council, effective operation of corporate systems,
processes and internal controls, engaging with and, where appropriate, lead communities, monitoring
whether strategic objectives have been achieved and services delivered cost effectively, and ensuring that
appropriate arrangements are in place for the management of risk.
The system can only provide reasonable and not absolute assurance of effectiveness.
Framework for Good Governance
The overall aim of the CIPFA/SOLACE Framework ‘Delivering Good Governance in Local Government’
(2016) is to ensure that: resources are directed in accordance with agreed policy and according to
priorities; there is sound and inclusive decision making; and there is clear accountability for the use of
those resources in order to achieve desired outcomes for service users and communities.
The Framework defines the seven core principles of good governance, namely:
A.  Behaving with integrity, demonstrating strong commitment to ethical values, and respecting the rule
of law;
B.  Ensuring openness and comprehensive stakeholder engagement;
C.  Defining outcomes in terms of sustainable economic, social, and environmental benefits;
D.  Determining the interventions necessary to optimise the achievement of the intended outcomes;
E.  Developing the entity’s capacity, including the capability of its leadership and the individuals within
it;
F.  Managing risks and performance through robust internal control and strong public financial
management; and
G.  Implementing good practices in transparency, reporting, and audit to deliver effective
accountability.
The Council’s Local Code of Corporate Governance, which is consistent with the principles and
recommendations of the CIPFA/SOLACE Framework and the supporting guidance notes for Scottish
authorities (November 2016), and was approved by Council in March 2021.  
Page 316 of 396

Page 317

WWW.MIDLOTHIAN.GOV.UK 
18 Annual Governance Statement
The Council’s Governance Framework 
The key elements of the Council’s governance arrangements, as set out in the Council’s Local Code of
Corporate Governance, include:
A. Behaving with integrity, demonstrating strong commitment to ethical values, and respecting rule of law
The roles and responsibilities of elected members and officers and the processes to govern the conduct
of the Council’s business are defined in the Elected Members Code of Conduct, standing orders and
scheme of delegation for officers, scheme of administration, and financial regulations.
Codes of conduct are in place for and define the high ethical values and standards of behaviour expected
from elected members and officers to make sure that public business is conducted with fairness and
integrity.
The Monitoring Officer is responsible for ensuring that agreed procedures are followed and that all
applicable statutes and regulations are complied with. The Standards Committee is responsible for
dealing with matters relating to conduct and ethical standards.
The Council seeks feedback from the public through its complaints and complements procedures for all
of the Council which responds to the outcomes, as appropriate, and reports the results annually.
Professional advice on the discharge of statutory social work duties was provided during the year to the
Council by the Chief Officer Children’s Services, Partnerships and Communities (Chief Social Work
Officer). The CSWO promotes values and standards of professional practice and acts as the 'agency
decision maker' taking final decisions on a range of social work matters including adoption, secure
accommodation, guardianship, etc. The CSWO reports annually on the statutory work undertaken,
regulation and inspection, workforce issues and significant social policy themes.
B. Ensuring openness and comprehensive stakeholder engagement
All meetings of the Council and its Committees are held in public with the exception of items for discussion
that are exempt under the Local Government (Scotland) Act 1973. All Council and Committee meetings
are hybrid and webcast to ensure public access, and recordings can be accessed from the Council’s
website.
Unless confidential, decisions made by Council or other Committees are documented in the public
domain. All decisions are explicit about the criteria, rationale and considerations used. The impact and
consequences of all decisions are clearly set out.
The Council seeks community views on a wide range of issues and undertakes regular consultation and
engagement with citizens and service users, including the public consultation on the Medium Term
Financial Strategy 2025/26 to 2028/29 reported to the December 2024 Council meeting.  
C. Defining outcomes in terms of sustainable economic, social, and environmental benefits
The Council’s vision, strategic objectives and priorities are set out in the Single Midlothian Plan developed
through the Community Planning Partnership (of which the Council is a partner). The Council’s Medium
Term Financial Strategy and Service Plans outline how Midlothian Council will deliver its contribution to
the Single Midlothian Plan. In June 2023 the Council also approved a Transformation Blueprint 2023-2028
to support the Medium Term Financial Strategy and help bridge a projected five-year funding gap. Progress
against this blueprint is reported to Council on a quarterly basis along with progress on the Medium Term
Financial Strategy which was updated for the period 2025/26 to 2028/29 in October 2024.Progress is also
reviewed at 4 weekly BTB’s and reported to BTSG as a Standing Item.  
Capital investment at a strategic level is structured to consider and balance the combined economic,
social and environmental impact of policies and plans when taking decisions about service provision.
Asset management planning is being developed to support this, although it is recognised that this process
needs to be accelerated to meet the needs of the growing council area. 
Page 317 of 396

Page 318

WWW.MIDLOTHIAN.GOV.UK 
19 Annual Governance Statement
The Council considered the recommendation of the February 2024 Aether Climate Action Support Report
in November 2024 and has instructed a refresh of the Councils Climate Change Strategy. 
The Council approved the Economic Growth Strategy 2025-30 in November 2024, which has been
reviewed to align with the Scottish Government National Strategy for Economic Transformation and the
Edinburgh and South East Scotland City Region Deal Regional Prosperity Framework.
The Council supports community empowerment and recognises the importance of building community
capacity and volunteering as a key factor in building stronger, safer, and supportive communities. 
Implications are considered during the decision-making process within the standard report template
covering Resources, Risk, Single Midlothian Plan and Key Priorities, Impact on Performance and
Outcomes, Adopting a Preventative Approach, Involving Communities and Other Stakeholders, Ensuring
Equalities, Supporting Sustainable Development, and IT issues.
D. Determining the interventions necessary to optimise the achievement of the intended outcomes
Decision makers receive detailed information indicating how intended outcomes would be achieved
together with the risks, financial and other implications associated with the proposals, by way of the
compulsory sections of the Committee report template.
In determining how services and other courses of action should be planned and delivered the Council is
increasingly engaging with internal and external stakeholders. The Council fosters effective relationships,
collaborative working and contractual arrangements with other public, private, and voluntary
organisations in delivering services that meet the needs of the local community including the achievement
of ‘social value’ (community benefits) through service planning and commissioning.
E. Developing the entity’s capacity, including the capability of its leadership and the individuals within it
The roles of officers are defined in agreed job descriptions. Staff performance is reviewed on an annual
basis in accordance with the relevant appraisal processes in place during the year. In December 2024 the
Council approved the Midlothian Council Workforce Strategy 2024 to 2034 developed using an evidence-
based management approach engaging with stakeholders and employees via an employee survey. 
The Chief Executive is responsible and accountable to the Council for all aspects of management including
promoting sound governance, providing quality information/support to inform decision making and
scrutiny, supporting other statutory officers, and building relationships with all Councillors.
The Elected Members Induction Programme took place following elections in May 2022 and is periodically
supplemented by training events, seminars and briefings. Members appointed to certain committees have
also received specific training related to the responsibilities on these committees e.g. licensing, planning,
audit.
F. Managing risks and performance through robust internal control & strong public financial management
The Council has overall responsibility for directing and controlling the organisation. The Cabinet is the
principal decision-making committee of the Council. The Performance, Review and Scrutiny Committee
is responsible for reviewing performance against policy objectives and commenting on decisions and
policies and their impact.
The Council updated its Risk Management policy and strategy in August 2022 whose main priorities are
the robust systems of identification, evaluation and control of risks which threaten the Council’s ability
to meet its objectives to deliver services to the public. Internal Audit’s assessment in March 2024 was
that assurance is substantial in relation to the Council’s Risk Management Policy and application of the
policy at a strategic level, however significant further progress is required on the Service level risk
management framework. 
Page 318 of 396

Page 319

WWW.MIDLOTHIAN.GOV.UK 
20 Annual Governance Statement
The Chief Financial Officer (the Section 95 officer) is responsible for the proper administration of all
aspects of the Council’s financial affairs including ensuring appropriate advice is given to the Council on
all financial matters. 
The Council’s system of internal financial control is based on a framework of financial regulations
(updated in June 2022), regular management information, administrative procedures (including
segregation of duties), management supervision and a system of delegation and accountability. This
remains reliant on the staff within the framework to ensure management supervision and accountability
are diligently enforced. 
The Council has an approved strategy to tackling fraud, theft, corruption and crime, as an integral part of
protecting public finances, safeguarding assets, and delivering services effectively.
A revised Medium Term Financial Strategy continues to be monitored and updated on a regular basis with
the latest 2025/26 to 2028/29 strategy being approved by Council in February 2025 Given the significant
fiscal challenges which lie ahead, the Council continues to regularly monitor the Transformation
Blueprint workstreams aligned to the Medium Term Financial Strategy. This will then inform the revised
service plans, workforce plans and the long term sustainability of services. A Balanced budget was set by
Council in February 2025 for the 2025/26 financial year by increasing Council tax by 10% and utilisation of
£4.1 million of reserves, with indicative increases of Council tax of, 9%, 8% and 5% in the following 3
financial years and continued utilisation of reserve of £4.1milllion in the following 2 years the budget gap
by 2028/29 becomes £8.9million. Highlighting the unprecedented financial pressure on the Council and
some of the difficult decisions to be made in relation to both Capital and Revenue Budgets to establish a
sustainable financial position.
The previous Chief Officer Corporate Solutions carried out a self-assessment against the CIPFA FM code
and reported the findings of this to CMT in September 2021 and this was subsequently reported to Audit
Committee in December 2021.  The Chief Officer Corporate Solutions identified six areas requiring
improvement from his review of the CIPFA FM code.  Actions identified included improving the resourcing
of the Procurement team (Ongoing), updating the Council’s Financial Regulations and Directives
(Complete – approved at June 2022 Council), putting in place a multi-year financial plan (Ongoing – action
relevant to two sections of the FM Code), improving the Council’s approach to lessons learned from
completed projects (Ongoing), and improving the Council’s risk management arrangements (Ongoing). No
further Committee update has been provided within the 2024/25 financial year.   
Revenue and Capital Budget Monitoring reports are presented to the Council on a quarterly basis for
monitoring and control purposes including the annual outturn. The Management Commentary in the
Statement of Accounts provides financial and other performance information regarding the operation of
the Council, its wider achievements and areas for development. The Internal Audit of Budget Monitoring
highlighted that the Council element of the IJB spend, being adult social work expenditure needed to be
included in the revenue budget monitoring figures and whilst this had been verbally updated to Council
during the 2024/25 financial year, and formally reported to the Midlothian IJB Board with links provided to
this publicly available information within the quarterly reports, these figures will now be included in the
monitoring for the 2025/26 financial year.
On the 10 January 2025 the Accounts Commission wrote in a letter to all Chief Executives of Scottish Local
Authorities, copying in Directors of Finance and external auditors highlighting the report of the 12
December 2024 relating to a significant council tax fraud perpetrated against Aberdeen City Council.
Highlighting the Chief Executives responsibility to ensure arrangements are in place to help assure elected
members and the public that risks are being identified and managed effectively. The letter encouraged all
Chief Executives to use the annual governance statement as an opportunity to take stock of the key
controls and processes and whether self-assessment procedures are sufficient to provide elected
members and officers with the required assurances. A review of the Council Tax processes within
Midlothian Council has been completed and highlighted that in relation to Council Tax refunds the system
did not provide adequate segregation of duties controls and there was not an appropriate monitoring
Page 319 of 396

Page 320

WWW.MIDLOTHIAN.GOV.UK 
21 Annual Governance Statement
regime in place. Subsequent sample testing identified no evidence of fraud within the 2024/25 financial
year. Work is now ongoing with the supplier and within the service to rectify these issues.  
G. Implementing good practices in transparency, reporting, & audit to deliver effective accountability
The independent and objective audit opinion of the Chief Internal Auditor (Chief Audit Executive) is stated
within the Internal Audit Annual Assurance Report 2024/25. This is based on work carried out by an in-
house team, including shared services resources from East Lothian Council for the Chief Internal Auditor,
in conformance with the Public Sector Internal Audit Standards to fulfil statutory Internal Audit provision.
The Council responds to the findings and recommendations of Internal Audit, External Audit, Scrutiny and
Inspection bodies including associated Action Plans for improvement. The Audit Committee is integral to
overseeing independent and objective assurance and monitoring improvements in internal control and
governance.
Quarterly Performance Reports were presented to Cabinet and the Performance, Review and Scrutiny
Committee for monitoring the achievement of strategic priorities and key performance indicators.
The Annual Accounts and Report sets out the financial position in accordance with relevant accounting
regulations.
Review of Adequacy and Effectiveness of the Council’s Governance Framework
An annual review of the adequacy and effectiveness of the Council’s overall governance framework has
been carried out. The output is this Annual Governance Statement which is presented to the Audit
Committee.
The review was further informed by assurances from: assessment of compliance against the Local Code;
written assurance statements from the Executive Directors; Internal Audit annual opinion, findings and
recommendations; External Audit, and comments and recommendations made by External Auditor and
other external scrutiny bodies and inspection agencies.
Improvement Areas of Governance
The collective review activity outlined above has identified the following areas where improvement in
governance arrangements can continue to be made to enhance compliance with the Council’s Local Code
of Corporate Governance and to demonstrate Best Value:
1) The previous Chief Officer Corporate Solutions carried out a self-assessment against the CIPFA FM
code and reported the findings of this to CMT in September 2021 and this was subsequently reported
to Audit Committee in December 2021. One of the actions identified was putting in place a multi-year
financial plan. The Council’s subsequently approved a 2023-2028 Strategic Blueprint in June 2023,
aligned to the Medium Term Financial Strategy. The Medium Term Financial Strategy 2025/26 to
2028/29 approved in October 2024 highlighted that the budget gap for 2025/26 incorporating planned
use of service concession retrospection and a 5% Council Tax increase was projected to £9.4million
rising to £20.6million by 2028/29. A Balanced budget was set by Council in February 2025 for the
2025/26 financial year by increasing Council tax by 10% and utilisation of £4.1 million of reserves,
with indicative increases of Council tax of, 9%, 8% and 5% in the following 3 financial years and
continued utilisation of reserve of £4.1milllion in the following 2 years the budget gap by 2028/29
becomes £8.9million. Working towards that sustainable position has been significant during the year,
however further ongoing work is required and there were also 15 risks noted to this strategy that could
impact on the current position, including the MIJB finances with management highlighting that the
level of financial resource available to both partners is nor reflective of the current level of demand to
maintain services on a sustainable basis. Work will continue during 2025/26 towards a sustainable
financial position over a multiyear period. 
2) The Procurement Service continues to face recruitment challenges and despite multiple recruitment
attempts was unable to secure a permanent Procurement Manager for 2024/25. A permanent
Procurement Manager was appointed at the end April 2025, and the work plan is being developed for
improvements to the service for the 2025/26 reporting year. Issues arising from the reduced team
Page 320 of 396

Page 321

WWW.MIDLOTHIAN.GOV.UK 
22 Annual Governance Statement
capacity are the off contract spend, and maverick spend within the organisation, chief officers are
now reporting impacts to the delivery of services from this lack of resource. Expired contracts and off
contract spend is being managed through regular review at Budget Boards to ensure that the risk is
managed, and the appropriate remedial action is being taken, with oversight from the Executive
Director and Chief Officers. In addition, commissioning and contract management are both focused
areas of the Transformation Blueprint. 
3) Capital plan affordability continues to be worked through as part of the Capital Plan prioritisation
exercise, which was considered by Council in February 2025, alongside approval of new projects to
the General Services Capital Plan and noting the expenditure and funding levels shown in the GSCP
for 2024/25 to 2028/29 prior to reaching a financially sustainable outcome. Within that paper it is
noted that in developing the strategy and taking cognisance of the longer term affordability gap it is
clear that a number of potential projects which are currently included will only be able to be
progressed if they can be delivered on a spend to save basis or where they can be delivered on a cost
neutral basis or through alternative funding mechanisms. Whilst approval for fully funded learning
estates projects has been progressed, delays in decision to critical projects may result in breaches of
capacity to provide education provision across the council area. The condition of certain schools is
deteriorating, and significant investment is required in order to ensure all schools meet at least
condition B standard. Changes to the leadership and management of the learning estate delivery
programme are being worked through. It is also noted that there is ongoing development of the
Council’s asset management across fleet, property and infrastructure to manage and invest in the
portfolios effectively. 
4) During the year there has been insufficient recording and reporting by services on service level risk
registers and business continuity plans. There is a requirement to ensure that there is a one system
approach to aligning business continuity planning across NHS and Midlothian Council including
cybersecurity planning to ensure all critical services can be maintained at times of incidents. Training
is being delivered to staff within services in relation to risk management and there has been
involvement of contracted resource in the Children, Young People and Partnerships directorate.
Outstanding Internal Audit recommendations to report to Audit Committee on the delivery of service
risk registers and the review of business continuity resourcing, and completion of plans should result
in an improvement in the control environment.
5) Deficiencies in the control environment for Council Tax within systems controls and monitoring of
refunds are being resolved in conjunction with the systems supplier and that ongoing monitoring will
be implemented. The Counter Fraud team are intending to establish a risk assessment process for
the Council to identify areas of risk and work with services for them to implement appropriate
mitigations across the Council, specifically on the risk of fraud. 
Prior Year Improvement Areas of Governance Implemented 
The 2023/24 Annual Governance Statement for Midlothian Council contained the following areas of
improvement all of which have been taken forward: 
1) It was highlighted that the Council over the next 5 years required an approved multi-year financial plan
key to developing the Council on a sustainable basis. The Medium Term Financial Strategy 2025/26 to
2028/29 approved in October 2024 highlighted that the budget gap for 2025/26 incorporating planned
use of service concession retrospection and a 5% Council Tax increase was projected to £9.4million
rising to £20.6million by 2028/29. A Balanced budget was set by Council in February 2025 for the
2025/26 financial year by increasing Council tax by 10% and utilisation of £4.1 million of reserves, with
indicative increases of Council tax of, 9%, 8% and 5% in the following 3 financial years and continued
utilisation of reserve of £4.1milllion in the following 2 years the budget gap by 2028/29 becomes
£8.9million. Working towards that sustainable position has been significant during the year, however
further ongoing work is required and there were also 15 risks noted to this strategy that could impact
on the current position. 
2) Improvements in Procurement Service Capacity have been enacted within the 2024/25 financial year,
however obtaining and maintaining resources within the procurement team remains a workforce
challenge.  A solution is currently in place however services have highlighted that the procurement
Page 321 of 396

Page 322

WWW.MIDLOTHIAN.GOV.UK 
23 Annual Governance Statement
workload has increased, and a planned approach will now need to be implemented over a significant
period of time to reestablish an appropriate control framework, which will require support across the
Council. 
3) Capital plan affordability continues to be worked through as part of the Capital Plan prioritisation
exercise, which was considered by Council in February 2025, alongside approval of new projects to
the General Services Capital Plan and noting the expenditure and funding levels shown in the GSCP
for 2024/25 to 2028/29 prior to reaching a financially sustainable outcome. Within that paper it is noted
that the In developing the strategy and taking cognisance of the longer term affordability gap it is clear
that a number of potential projects which are currently included will only be able to be progressed if
they can be delivered on a spend to save basis or where they can be delivered on a cost neutral basis
or through alternative funding mechanisms. A Capital plan prioritisation paper with options for
consideration was also considered at the February 2025 and further work will be required to deliver a
long-term sustainable solution.  
4) In December 2024 the Council approved the Midlothian Council Workforce Strategy 2024 to 2034
developed using an evidence-based management approach engaging with stakeholders and
employees via an employee survey. Additional resources were deployed during 2024/25 to improve
the Council’s position in relation to Council Tax and Housing Benefit processing and within the
compliance environment to meet statutory reporting responsibilities, work is ongoing to provide long
term sustainable staffing in this area. The Council is currently subject to a Level 2 intervention from
the Scottish Information Commissioner (SIC) in respect of its response rates for Freedom of
Information requests. An action plan has been created and being delivered to improve the current
position, with regular reporting to the Corporate Management Team (CMT). The Chief Officer
Corporate Solutions, the Legal and Governance Manager and the Lead Performance and Improvement
Officer (Place) meet the SIC on a monthly basis to monitor and evaluate progress on the improvement
plan. Feedback from the SIC is that significant sustained improvement is demonstrated, and it is
expected that the intervention will be removed Summer 2025.
Conclusion and Opinion on Assurance 
The conclusion from the review activity completed and subject to the successful progression of the areas
for improvement highlighted above, our opinion is that reasonable assurance given financial constraints
can be placed upon the adequacy and effectiveness of Midlothian Council’s systems of governance, risk
management and internal control. Although areas for further improvement have been identified, the
annual review demonstrates sufficient evidence that the Council’s Local Code of Corporate Governance
is operating effectively and that the Council complies with that Local Code in most respects to meet its
principal objectives. Systems are in place to regularly review and improve governance arrangements and
the system of internal control. 
_______________________ ______________________ 
Dr Grace Vickers Kelly Parry
Chief Executive Leader of the Council 
Page 322 of 396

Page 323

WWW.MIDLOTHIAN.GOV.UK 
24 Remuneration Report
Remuneration Report
The Local Authority Accounts (Scotland) Regulations 2014 require local authorities in Scotland to prepare
a Remuneration Report as part of the annual statutory accounts.
The following report details Midlothian Council’s remuneration policy for its senior councillors and senior
employees, providing full details of the remuneration and pension benefits they receive. This report also
provides information on the number of employees whose annual remuneration was £50,000 or more as
well as summary information in relation to employees’ exit packages agreed during the year.
Information disclosed in the tables in this report is subject to audit by Audit Scotland, who report on
whether the information has been properly prepared in accordance with the Local Authority Accounts
(Scotland) Regulations 2014 (with the exception of the table in note 4.4). All other sections of the
Remuneration Report, including the table in respect of Trade Union Facility Time, are read and considered
to identify any material inconsistencies with the financial statements.
Remuneration of Councillors
The remuneration of Councillors is regulated by the Local Governance (Scotland) Act 2004 (Remuneration)
Regulations 2007 (SSI No 2007/183) as amended. The Regulations provide for the grading of councillors for
the purposes of remuneration arrangements, as Leader of the Council, Provost, Senior Councillors or
Councillors. The Leader of the Council and the Provost cannot be the same person for the purposes of
payment of remuneration. A Senior Councillor is a Councillor who holds a significant position of
responsibility within the Council’s political structure.
The Regulations permit the Council to remunerate one Leader of the Council and one Provost. For 2024/25
the Regulations set the salary for the Leader of Midlothian Council £35,580 (2023/24 £33,503) and the
salary for the Provost was set at £26,686 (2023/24 £25,128), the maximum level.
The Regulations also set out the remuneration that may be paid to Senior Councillors and total number of
Senior Councillors the Council may have. The maximum yearly amount that may be paid to a Senior
Councillor is 75% of the total yearly amount payable to the Leader of the Council. For 2024/25, the
maximum salary which could be paid to a Senior Councillor was £26,686 (2023/24 £25,128) with the
maximum number of Senior Councillors set at eight (excluding the Provost and the Leader). The total
remuneration for Senior Councillors (excluding the Provost and the Leader) should not exceed £192,128
(2023/24 £180,905). The Council is able to exercise local flexibility in the determination of the precise
number of Senior Councillors and their salary within these maximum limits.
The Regulations also permit the Council to pay contributions or other payments as required to the Local
Government Pension Scheme in respect of those Councillors who elect to become Councillor Members of
the pension scheme.
In addition to the Senior Councillors of the Council, the regulations also set out the remuneration payable
to Councillors with the responsibility of a Convener or a Vice-Convener of a Joint Board. The Regulations
require the remuneration and any pension contributions, if a member of the Local Government Pension
Scheme, to be paid by the Council of which the Convener and Vice-Convener is a member. The Council is
reimbursed by the Joint Board for any additional remuneration paid to a member from being a Convener or
Vice-Convener of a Joint Board.
Details of the Remuneration of Council Leader, Provost and Senior Councillors are shown in the table
below: 
Page 323 of 396

Page 324

WWW.MIDLOTHIAN.GOV.UK 
25 Remuneration Report 
Councillor Name and Responsibility 
Salary
2024/25 
Expenses
2024/25 
Total
Remuneration
2024/25
Total
Remuneration
2023/24
Senior Councillor (Apr 24-Mar 25)    
K Parry: Council Leader £35,580 £0 £35,580 £33,526
D McCall: Provost £26,686 £447 £27,133 £25,256
D Virgo: Group Leader £24,016 £38 £24,054 £22,759
D Alexander: Cabinet Member £24,016 £77 £24,093 £22,792
C McManus: Cabinet Member £24,016 £36 £24,052 £22,724
E Scott: Cabinet Member £24,016 £0 £24,016 £22,719
S McKenzie: Cabinet Member £24,016 £0 £24,016 £22,614
D Milligan: Group Leader £24,016 £58 £24,074 £22,952
R Imrie: Chair of Planning Committee £24,016 £1,327 £25,343 £22,824
C Cassidy: Depute Leader and Group Leader £24,016 £0 £24,016 £22,646
Total £254,394 £1,983 £256,377 £240,812 
The total remuneration of all the Council’s elected members (including Senior Councillors above) and
including all business expenses for 2024/25 was £0.428 Million (2023/24 £0.402 million). Detailed figures
for these costs are available on the Council’s website, members' remuneration details for 2024/25.
Remuneration of Employees
The salary of senior employees is set by reference to national arrangements. The Scottish Joint Committee
(SJC) for Local Authority Services sets the salaries for the Chief Executives of Scottish Local Authorities.
The salaries of the Executive Directors, Chief Officers and Heads of Service are all now based on a fixed
percentage of the Chief Executives salary.
The salaries of all other employees are set by reference to:
• Teaching staff – The Scottish Negotiating Committee for Teachers (SNCT);
• Other staff – The Scottish Joint Committee (SJC).
The table below details the remuneration paid to Senior Employees (as defined in the regulations) of the
Council during the financial year: 
Senior Employee Name and Responsibility
Total Salary, Fees
and Allowances
2024/25
Total
Remuneration
2023/24
Full Year (Apr 24-Mar 25)  
G Vickers: Chief Executive £137,928 £133,135
G Vickers: Returning Officer £545 £0
M Barrow: Joint Director: Health and Social Care (1) £59,048 £55,822
K Anderson: Executive Director: Place £120,542 £116,353
F Robertson: Executive Director: Children, Young People and Communities £120,542 £116,353
D Gladwin: Chief Financial Officer (S95 Officer) £101,890 £95,000
A Turpie: Legal Services Manager (Monitoring Officer) £81,834 £76,661
Part-Year  
J Tranent: Chief Officer: Children’s Services, Partnerships and Communities (Chief
Social Work Officer) (2)  £60,925  £98,349
N Clater: Head of Adult Social Care (Chief Social Work Officer) (2)  £101,890 N/A
Total £785,144 £691,673
Notes:
1. Post joint funded with NHS Lothian , full time equivalent £118,095,
2. N Clater assumed Chief Social Work Officer role Nov 2024. He replaces J Tranent, who retired from post 29
October 2024 (full time equivalent £101,890). 
Subsidiary Entities
None of our subsidiaries have remunerated employees.
Page 324 of 396

Page 325

WWW.MIDLOTHIAN.GOV.UK 
26 Remuneration Report
Pension Benefits
Pension benefits for Councillors and local government employees are provided through the Local
Government Pension Scheme (LGPS), which is administered by the Lothian Pension Fund. From 1 April
2015, this became a career average salary pension scheme, although it was a final salary scheme until that
date. This means that pension benefits are based on an average of the pay over the number of years that a
person has been a member of the scheme.
From 1 April 2009, a five-tier contribution system is in place with contributions from scheme members
based on how much pay falls into each tier. This is designed to give more equality between costs and
benefits of scheme membership. Part-time workers contribution rates are worked out on the whole time
pay rate for the job, with actual contributions paid on actual pay earned.
The tiers and contribution rates are as follows: 
Pensionable Pay 2024/25
Contribution
Rate
On earnings up to and including £27,000 5.5%
On earnings above £27,001 and up to £33,000 7.25%
On earnings above £33,001 and up to £45,300 8.5%
On earnings above £45,301 and up to £60,400 9.5%
On earnings of £60,401 and above 12% 
There is no automatic lump sum on retirement. Pension scheme members may opt to commute pension
for a lump sum payment up to the limits set by the Finance Act 2004. The rate and basis at which employees
accrue their pension benefits has changed over time, this is shown in the table below: 
Pension Benefit  
Time Period Accrual Basis Accrual Rate Lump Sum Basis 
From 1 April 2015
Career Average 1/49th Pensionable pay
each year  n/a 
From 1 April 2009 to 31 March 2015  Final Salary
1/60th Pensionable pay
each year  n/a 
Prior to April 2009  Final Salary 
1/80th Pensionable pay
each year
3/80th Final pensionable
salary and years of
pensionable service 
The value of accrued benefits has been calculated on the basis of the age at which the person will become
first entitled to receive a pension on retirement without reduction on account of its payment at that age,
without exercising any option to commute pension entitlement into a lump sum, and without any
adjustment for the effects of future inflation.
The pension entitlements for Senior Councillors for the year to 31 March 2025 are shown in the tables
below, together with the contribution made by the Council to each Senior Councillor’s pension during the
year. 
Page 325 of 396

Page 326

WWW.MIDLOTHIAN.GOV.UK 
27 Remuneration Report
Senior Councillors In-Year Pension Contributions 
Councillor Name and Responsibility
Year to 31 Mar
2025
Year to 31 Mar
2024
Senior Councillor (Apr 24-Mar 25)  
K Parry: Council Leader  £6,262 £7,438
D McCall: Provost £4,696 £5,578
D Virgo: Group Leader £4,227 £5,020
C McManus: Cabinet Member  £4,227 £5,036
E Scott: Cabinet Member  £4,227 £5,020
S McKenzie: Cabinet Member £4,227 £5,020
R Imrie: Chair of Planning Committee  (1) £0 £3,347
C Cassidy: Depute Leader and Group Leader £4,227 £5,020
Total £32,093 £41,479
1. Member now out of scheme due to scheme regulations.
Senior Councillors Accrued Pension Benefits  
Pension at 31
March 2025 
Lump Sum at 31
March 2025 
Pension Difference
from 31 March 2024
Lump Sum
Difference from
31 March 2024
Senior Councillor £000 £000 £000 £000
K Parry 5 0 1 0
D McCall 4 0 1 0
D Virgo 1 0 0 0
C McManus 1 0 1 0
E Scott 1 0 1 0
S McKenzie 2 0 1 0
C Cassidy 4 0 1 0
Total 18 0 6 0 
The pension entitlements for Senior Employees for the year to 31 March 2025 are shown in the tables
below, together with the contribution made by the Council to each Senior Employees (as defined in the
regulations) pension during the year.
Senior Employees In-Year Pension Contributions 
Senior Employee Name and Responsibility
Year to 31 Mar
2025
Year to 31 Mar
2024
Full Year (Apr 24-Mar 25)  
G Vickers: Chief Executive £24,371 £29,556
K Anderson: Executive Director: Place £21,215 £25,830
F Robertson: Executive Director: Children, Young People and Communities £21,215 £25,830
D Gladwin: Chief Financial Officer (S95 Officer) £17,933 £21,210
M Barrow: Joint Director: Health and Social Care (2) £12,241 £0
A Turpie: Legal Services Manager (Monitoring Officer) £14,403 £17,019
Part-Year  
J Tranent: Chief Officer: Children’s Services, Partnerships and Communities (Chief
Social Work Officer) (1)  £10,316  £21,834
N Clater: Head of Adult Social Care (Chief Social Work Officer) (1)  £17,933 N/A
Total £139,627 £141,279
1. N Clater assumed Chief Social Work Officer role Nov 2024. He replaces J Tranent, who retired from post 29 October 2024 (full
time equivalent £17,933). 
2. Member rejoined the pension scheme during 2024_25. Post joint-funded with NHS Lothian,  Full time equivalent £24,481. 
Page 326 of 396

Page 327

WWW.MIDLOTHIAN.GOV.UK 
28 Remuneration Report 
Senior Employees Accrued Pension Benefits  
Pension at 31
March 2025 
Lump Sum at 31
March 2025 
Pension Difference
from 31 March 2024
Lump Sum
Difference from
31 March 2024
Senior Councillor £000 £000 £000 £000
G Vickers 26 0 4 0
K Anderson 75 119 5 4
F Robertson 20 0 4 0
D Gladwin 50 63 6 4
M Barrow 30 82 n/a n/a
J Tranent 45 49 2 1
A Turpie 47 68 5 4
N Clater 43 0 n/a n/a
Total 336 381 26 13 
All senior employees (as defined in the regulations), except M Barrow, shown in the tables above are
members of the Local Government Pension Scheme. M Barrow is employed by NHS Lothian and is a
member of the NHS pension scheme. The pension figures shown relate to the benefits accrued as a
consequence of total local government service, not solely on the current appointment.
Remuneration of Other Employees by Pay Bands
The Regulations require the Remuneration Report to provide information on the number of persons whose
remuneration was £50,000 or above, this information is detailed in bands of £5,000 in the table below:
Total
Employees
2023/24  Remuneration Band
Non-teaching
Employees
2024/25
Teaching
Employees
2024/25
Total
Employees
2024/25
80 £50,000-£54,999 56 431 487
107 £55,000-£59,999 26 112 138
63 £60,000-£64,999 16 48 64
60 £65,000-£69,999 15 62 77
47 £70,000-£74,999 11 35 46
20 £75,000-£79,999 5 34 39
5 £80,000-£84,999 3 10 13
4 £85,000-£89,999 1 6 7
2 £90,000-£94,999 1 2 3
7 £95,000-£99,999 0 2 2
0 £100,000-£104,999 6 0 6
0 £105,000-£109,999 0 1 1
2 £110,000-£114,999 0 0 0
2 £115,000-£119,999 0 2 2
0 £120,000-£124,999 2 0 2
1 £130,000-£134,999 0 0 0
0 £135,000-£139,999 1 0 1
400 Total 143 745 888 
Exit Packages
Termination benefits are amounts payable because of a decision by the Council to terminate an officer’s
employment before the normal retirement date or an officer’s decision to accept voluntary redundancy.
They are charged on an accruals basis to Services in the Comprehensive Income and Expenditure
Statement when the Council is demonstrably committed to either terminating the employment of an
officer or making an offer to encourage voluntary redundancy. The Council is only demonstrably
committed to a termination when it has a detailed formal plan for the termination and it is without realistic
possibility of withdrawal.
Page 327 of 396

Page 328

WWW.MIDLOTHIAN.GOV.UK 
29 Remuneration Report
Where termination benefits involve the enhancement of pensions, statutory provisions require the General
Fund balance to be charged with the amount payable by the Council to the pension fund or pensioner in
the year, not the amount calculated according to the relevant accounting standards. In the Movement in
Reserves Statement, appropriations are required to and from the Pensions Reserve to remove the notional
debits and credits for pension enhancement termination benefits and to replace them with debits for the
cash paid to the pension fund and the pensioners and any such amounts payable but unpaid at the year-
end.
Details of the cost incurred by the Council for voluntary redundancy packages in 2024/25 was as follows.
Total
Employees
2023/24
Total Cost
2023/24
£000  Remuneration Band
Total
Employees
2023/24
Total Cost
2023/24
£000
0 0 £10,000-£19,999 3 49
0 0 £20,000 + 3 149
0 0 Total 6 198 
Trade Union Facility
The Council is now required to publish details of Trade Union facility time incurred during the year. Further
information is published on the Council’s website: Trade union facility time | Midlothian Council
For the reporting year 2024/25, the equivalent of 5.6 FTE employees (across fourteen individuals) of paid
time facility was made available. The proportion of their working hours spent on facility time is as follows:
Percentage of Time Number of Employees
1%-50% 12
51%-99% 1
100% 1 
The percentage of the total pay bill spent on facility time (calculated as total cost of facility time ÷ total pay
bill) is:
Total cost of facility time £244,013
Total pay bill £202,526,725
100% 0.12% 
Time spend on paid Trade Union activities as a percentage of total paid facility time: 10,519 hours = 100%. 
___________________________   ___________________________
Councillor Kelly Parry     Dr Grace Vickers
Leader of the Council    Chief Executive 
Page 328 of 396

Page 329

WWW.MIDLOTHIAN.GOV.UK 
30 Independent Auditor’s Report
Independent Auditor’s Report
Independent Auditor’s Report to the members of Midlothian Council and the Accounts Commission
Under arrangements approved by the Commission for Local Authority Accounts in Scotland, the auditor
with responsibility for the audit of the annual accounts of Midlothian Council for the year-end 31 March
2025 is:
Claire Gardiner
Audit Director
Audit Scotland
4th Floor
102 West Port
Edinburgh
EH3 9DN
The certified Annual Accounts will be presented to Audit Committee for approval on completion of the
audit. 
Page 329 of 396

Page 330

WWW.MIDLOTHIAN.GOV.UK 
31 Expenditure and Funding Analysis
Expenditure and Funding Analysis
The Expenditure and Funding Analysis shows how annual expenditure is used and funded from resources
(government grants, rents, council tax and business rates) by the Council in comparison with those
resources consumed or earned by the Council in accordance with generally accepted accounting
practices. It also shows how this expenditure is allocated for decision making purposes between the
Council’s services. Income and expenditure accounted for under generally accepted accounting practices
are presented more fully in the Comprehensive Income and Expenditure Statement. 
2023/24    2024/25 
Net
expenditure
charged to
the General
Fund and
HRA
Balances 
Adjustments
(see note 6) 
Net
expenditure
in the CIES 
Net
expenditure
charged to
the General
Fund and
HRA
Balances 
Adjustments
(see note 6) 
Net
expenditure
in the CIES
£000 £000 £000 Service £000 £000 £000
1,889 (11) 1,878 Management & Members 1,995 20 2,015 
18,635  76  18,711
Children’s Services,
Partnerships &
Communities  19,092  426  19,518
121,038 22,228 143,266 Education 139,443 29,999 169,442 
615  566  1,181
Adult Health & Social
Care  (Non-Delegated)  706  10  716 
57,416  2,827  60,243
Midlothian Integrated
Joint Board  69,031  725  69,756
46,091 10,150 56,241 Place 37,536 8,281 45,817
11,424 1,013 12,437 Corporate Solutions 26,402 1,498 27,900 
(14,717)  55,597  40,880
Housing Revenue
Account  (14,668)  63,328  48,660
562 0 562 Joint Boards 613 0 613
313 74 387 Central Costs 309 69 378
808 (23) 785 Non-distributable Costs 923 0 923
244,074 92,497 336,571 Net Cost of Services 281,382 104,356 385,738 
(236,000)  (53,655)  (289,655)
Other income and
expenditure  (259,918)  (48,984)  (308,902)
8,074 38,842 46,916 (Surplus) or Deficit 21,464 55,372 76,836       
(87,569)  
Opening General Fund &
HRA Balance  (85,046)   
8,074  
Less/plus (Surplus) or
Deficit on General Fund &
HRA Balance in year  21,464   
(25)  
Transfers to/from other
Statutory Reserves  (357)   
(79,520)  
Closing General Fund
and HRA Balance at 31
March*  (63,939)  
*For a split of this balance between the General Fund and HRA – see Movement in Reserves Statement 
Page 330 of 396

Page 331

WWW.MIDLOTHIAN.GOV.UK 
32 Principal Financial Statements
Principal Financial Statements
The annual accounts summarise the Council’s transactions for the year, its year-end position at 31 March
2025 and its cash flows. The annual accounts are prepared in accordance  with the Code of Practice on
Local Authority Accounting in the United Kingdom 2024/25 (the Code), which is based on International
Financial Reporting Standards (IFRSs). Every effort has been made to use plain language; where technical
terms are unavoidable, they have been explained in the Glossary.
The four principal statements and their relationships are explained in more detail below:
• Comprehensive Income and Expenditure Statement – this shows the accounting cost in the
year of providing services in accordance with generally accepted accounting practices, rather
than the amount to be funded from taxation (or rents). Councils raise taxation (and rents) to cover
expenditure in accordance with statutory requirements; this may be different from the accounting
cost. The taxation position is shown in both the Expenditure and Funding Analysis and the
Movement in Reserves Statement.
• Movement in Reserves Statement – this shows the movement from the start of the year to the
end on the different reserves held by the Council, analysed into ‘usable reserves’ (i.e. those that
can be applied to fund expenditure or reduce local taxation) and other ‘unusable reserves.’  The
statement shows how the movements in the year of the Council’s reserves are broken down
between gains and losses incurred in accordance with generally accepted accounting practices
and the statutory adjustments required to return to the amounts chargeable to council tax (or
rents) for the year. The net increase/decrease line shows the statutory General Fund balance and
Housing Revenue Account (HRA) balance movements in the year following those adjustments.
• Balance Sheet – this shows the value as at the Balance Sheet date of the assets and liabilities
recognised by the Council. The net assets of the Council (assets less liabilities) are matched by
the reserves held by the Council. Reserves are reported in two categories. The first category of
reserves are usable reserves, i.e. those reserves  that the authority may use to provide services,
subject to the need to maintain a prudent level of reserves and any statutory limitations on their
use. The second category of reserves is those that the Council is not able to use to provide
services. This category of reserves includes reserves that hold unrealised gains and losses (for
example the revaluation reserve), where amounts would only become available to provide
services if the assets are sold; and reserves that hold timing differences shown in the Movement
in Reserves Statement line  ‘adjustments between accounting basis and funding basis under
regulations.’
• Cash Flow Statement – this shows the changes in cash and cash equivalents of the Council
during the reporting period. The statement shows how the Council generates and uses cash and
cash equivalents by classifying cash flows as operating, investing and financing activities. The
amount of net cash flows arising from operating activities is a key indicator of the extent to which
the operations of the Council are funded by way of taxation and grant income or from the recipients
of the services provided by the Council. Investing activities represent the extent to which cash
outflows have been made for resources which are intended to contribute to the Council’s future
service delivery. Cash flows arising from financing activities are useful in predicting claims on
future cash flows by providers of capital (i.e. borrowing) to the Council. 
Page 331 of 396

Page 332

WWW.MIDLOTHIAN.GOV.UK 
33 Principal Financial Statements
Group and Council Comprehensive Income and Expenditure Statement   
2023/24     2024/25 
Gross
Expenditure 
Gross
Income 
Net
Expenditure
or (Income 
Group Net
Expenditure   
Gross
Expenditure 
Gross
Income 
Net
Expenditure
or (Income) 
Group Net
Expenditure
£000 £000 £000 £000 Service £000 £000 £000 £000
1,878 0 1,878 1,878 Management and Members 2,173 (158) 2,015 2,015
20,490 (1,779) 18,711 18,711 Children’s Services, Partnerships and Communities 22,054 (2,536) 19,518 19,518
163,851 (20,585) 143,266 143,266 Education 180,739 (11,297) 169,442 169,442
1,598 (417) 1,181 1,181 Adult Health and Social Care (Non-Delegated) 1,021 (305) 716 716
150,812 (90,569) 60,243 60,243 Midlothian Integration Joint Board 164,132 (94,376) 69,756 69,756
106,713 (50,472) 56,241 56,241 Place 95,009 (49,192) 45,817 45,817
36,415 (23,978) 12,437 12,437 Corporate Solutions 46,226 (18,326) 27,900 27,900
72,840 (31,960) 40,880 40,880 Housing Revenue Account 85,166 (36,506) 48,660 48,660
562 0 562 562 Lothian Valuation Joint Board 613 0 613 613
387 0 387 387 Central Costs 378 0 378 378
785 0 785 782 Non-Distributable Costs 923 0 923 855
556,331 (219,760) 336,571 336,568 Cost of Services 598,434 (212,696) 385,738 385,670   
0 6,244
Associates and Joint Ventures accounted for on an Equity
Basis (Note 39)    0  98  
(70) (70) Other Operating (Income) or Expenditure (Note 9)    45 45   
31  31
Financing and Investment Income and Expenditure (Note 10)   
7,466  7,466   
(289,616)  (289,616)
Taxation and Non-specific Grant Income and Expenditure
(Note 11)    (316,413)  (316,413)  
46,916 53,157 (Surplus) or Deficit on Provision of Services (Note 13)   76,836 76,866   
(15,560)  (15,560)
Surplus or Deficit on Revaluation of Property, Plant and
Equipment Assets    (20,025)  (20,025)   
165  165
Surplus or deficit on Financial Assets Measured at Fair Value
through Other Comprehensive Income    (488)  (488)   
11,373  11,373  Remeasurement of the Net Defined Benefit Liability/(Asset)    4,896  4,896  
2,705 4,198 Other (Gains)/Losses   (513) (544)  
(1,317) 176 Other Comprehensive (Income) and Expenditure   (16,132) (16,163)  
45,599 53,333 Total Comprehensive (Income) and Expenditure   60,706 60,705
Page 332 of 396

Page 333

WWW.MIDLOTHIAN.GOV.UK 
34 Principal Financial Statements
Group and Council Movement in Reserves Statement 
General Fund
Housing
Revenue
Account
Capital Fund
Repairs &
Renewals
Fund
Total Usable
Reserves
Unusable
Reserves
Total Council
Reserves
Councils
Share of
Reserves of
Associates,
Subsidiaries &
Joint Ventures
Total Group
Reserves
Current Year £000 £000 £000 £000 £000 £000 £000 £000 £000
Balance at 31 March 2024 (46,338) (33,182) (17,242) (4,113) (100,875) (693,810) (794,685) 910 (793,775)
Opening Balance Adjustment (5,526) 0 0 0 (5,526) 5,526 0 0 0
Revised Balance at 31 March 2024 (51,864) (33,182) (17,242) (4,113) (106,401) (688,284) (794,685) 910 (793,775)
Movement in  Reserves during 2024/25         
Total comprehensive income and expenditure 18,878 57,958 (358) 0 76,478 (15,772) 60,706 (1) 60,705
Adjustments between accounting basis and funding basis
under regulations (Note 7)  4,110  (56,686)  0  0  (52,576)  52,576  0  0  0
Adjustment to the statutory repayment of debt for service
concession arrangements – permitted flexibility  (2,796)  0  0  0  (2,796)  2,796  0  0  0
Transfers to/(from) other statutory reserves (357) 0 0 357 0 0 0 0 0
(Increase)/Decrease in Year 19,835 1,272 (358) 357 21,106 39,600 60,706 (1) 60,705
Balance at 31 March 2025 Carried Forward (32,029) (31,910) (17,600) (3,756) (85,295) (648,684) (733,979) 909 (733,070) 
General Fund
Housing
Revenue
Account
Capital Fund
Repairs &
Renewals
Fund
Total Usable
Reserves
Unusable
Reserves
Total Council
Reserves
Councils
Share of
Reserves of
Associates,
Subsidiaries &
Joint Ventures
Total Group
Reserves
Comparative Year £000 £000 £000 £000 £000 £000 £000 £000 £000
Balance at 31 March 2023 (34,963) (32,143) (20,107) (4,138) (91,351) (748,933) (840,284) (6,948) (847,232)
Opening Balance Adjustment (20,463) 0 0 0 (20,463) 20,463 0 124 124
Revised Balance at 31 March 2023 (55,426) (32,143) (20,107) (4,138) (111,814) (728,470) (840,284) (6,824) (847,108)
Movement in  Reserves during 2023/24         
Total comprehensive income and expenditure (1,295) 48,211 2,865 0 49,781 (4,182) 45,599 7,734 53,333
Adjustments between accounting basis and funding basis
under regulations (Note 7)  15,087  (51,321)  0  0  (36,234)  36,234  0  0  0
Adjustment to the statutory repayment of debt for service
concession arrangements – permitted flexibility  (2,608)  0  0  0  (2,608)  2,608  0  0  0
Transfers to/(from) other statutory reserves (2,096) 2,071 0 25 0 0 0 0 0
(Increase)/Decrease in Year 9,088 (1,039) 2,865 25 10,939 34,660 45,599 7,734 53,333
Balance at 31 March 2024 Carried Forward (46,338) (33,182) (17,242) (4,113) (100,875) (693,810) (794,685) 910 (793,775)
Page 333 of 396

Page 334

WWW.MIDLOTHIAN.GOV.UK 
35 Principal Financial Statements
Group and Council Balance Sheet
31 Mar 24 31 Mar 24  31 Mar 25 31 Mar 25 
Midlothian
Council  Group 
Midlothian
Council  Group 
£000 £000  £000 £000 Notes
1,170,980 1,170,980 Property, Plant and Equipment 1,181,730 1,181,730 14
38,423 38,423 Infrastructure Assets 52,394 52,394 15
456 456 Heritage Assets 507 507 16
104 104 Intangible Assets 448 448 17
4,171 4,113 Long-term Debtors 3,756 3,756 18/19
11,526 5,916 Long-term Investments 16,604 6,404 19
0 4,589 Share of Net Assets of Associates and Joint Ventures 0 9,111 39
1,225,660 1,224,581 Long-term Assets 1,255,439 1,254,350 
30,017 30,017 Short-term Deposits 70 70 19
1,690 1,690 Assets Held for Sale 810 810 21
972 972 Inventories 985 985 22
38,114 38,175 Short-term Debtors 23,033 23,098 19/23
27,505 27,505 Cash and Cash Equivalents 26,878 26,878 24
98,298 98,359 Current Assets 51,776 51,841 
(3,797) (3,797) Short-term Borrowing (5,015) (5,015) 19
(50,960) (50,852) Short-term Creditors (54,035) (53,920) 19/25
(1,294) (1,294) Provisions (1,005) (1,005) 26
(40,821) (40,821) Grants Received in Advance (46,055) (46,055) 27
(96,872) (96,764) Current Liabilities (106,110) (105,995) 
(339,971) (339,971) Long-term Borrowing (377,696) (377,696) 19  
Other Long-term Liabilities   
(84,818) (84,818) • PPP Contracts (81,615) (81,615) 19/34
0 0 • Leases (1,382) (1,382) 33
(7,612) (7,612) • Pension Liability (6,433) (6,433) 35/36
(432,401) (432,401) Long-term Liabilities (467,126) (467,126) 
794,685 793,775 Net Assets 733,979 733,070 
100,875 100,079 Usable Reserves 85,295 84,480 28
693,810 693,696 Unusable Reserves 648,684 648,590 29
794,685 793,775 Total Reserves 733,979 733,070 
The unaudited accounts were authorised for issue on 16 June 2025.
I certify that the Balance Sheet presents a true and fair view of the financial position of the Council and its
Group at 31 March 2025, and its income and expenditure for the year ended 31 March 2025. 
_____________________
David Gladwin
Chief Financial Officer 
Page 334 of 396

Page 335

WWW.MIDLOTHIAN.GOV.UK 
36 Principal Financial Statements
Group and Council Cash Flow Statement
2023/24 2023/24  2024/25 2024/25
Midlothian
Council  Group 
Midlothian
Council  Group
£000 £000  £000 £000
(46,916) (53,157) Net surplus/(deficit) on the provision of services  (76,838) (76,868)     
Operating Activities    
Adjustments to the surplus or deficit on the provision of
services for non-cash movements:  
50,206 50,206 Depreciation 26,949 26,949
44,230 44,230 Impairment and downward valuations 73,333 73,333
124 124 Amortisation 50 50
2,223 2,285 (Increase)/decrease in debtors 15,029 15,091
(10,416) (10,524) Increase/(decrease) in creditors 2,763 2,655
51 51 (Increase)/decrease in inventories (12) (12)
(11,561) (11,561) Movement in pension liability (6,073) (6,073)
179 179 Carrying amounts of non-current assets sold or derecognised 573 573 
55  6,342
Other non-cash items charged to the net surplus or deficit on the
provision of services  (289)  (213)
75,091 81,332 Total Non-cash Movements 112,323 112,353  
Adjustments to the surplus or deficit on the provision of
services for investing and financing activities:  
132,000 132,000 Proceeds from short and long-term deposits 30,000 30,000 
(249)  (249)
Proceeds from sale of property, plant and equipment and
intangible assets  (528)  (528) 
(33,554)  (33,554)
Any other items for which the cash effects are investing or
financing cash flows  (28,231)  (28,231)
98,197 98,197 Total Investing and Financing Activities 1,241 1,241
173,288 179,529 Net Cash Flows from Operating Activities 113,564 113,594     
Investing Activities  
(95,601) (95,601) Purchase of property, plant and equipment and intangible assets (99,792) (99,792)
(142,000) (142,000) Purchase of short and long-term deposits (4,590) (4,590)
0 0 Other payments for investing activities 0 0 
249  249
Proceeds from sale of property, plant and equipment and
intangible assets  528
528
27,322 27,322 Other receipts from investing activities 30,645 30,645
(210,030) (210,030) Net Cash Flows from Investing Activities (73,209) (73,209)     
Financing Activities  
20,000 20,000 Cash receipts from short and long-term borrowing 40,000 40,000 
(3,769)  (3,769)
Cash payments for the reduction of the outstanding liabilities
relating to finance leases and on balance sheet PPP contracts  155  155
160 160 Other receipts from financing activities (2,874) (2,874)
(882) (882) Repayments of short and long-term borrowing (1,425) (1,425)
15,509 15,509 Net Cash Flows from Financing Activities 35,856 35,856     
(68,149) (68,149) Net Increase/(Decrease) in Cash and Cash Equivalents (627) (627)
95,654 95,654 Cash and Cash Equivalents at 1 April 27,505 27,505
27,505 27,505 Cash and Cash Equivalents at 31 March (Note 24) 26,878 26,878     
The cash flow for operating activities include the following
items:    
Interest Paid and Received  
4,415 4,415 Interest Received 2,386 2,386
(16,244) (16,244) Interest Paid (20,066) (20,066)
175 175 Dividend Received 0 0 
Page 335 of 396

Page 336

WWW.MIDLOTHIAN.GOV.UK 
37 Notes to the Accounts
Notes to the Accounts
The notes to the accounts provide further information about the basis of preparation of the Annual
Accounts, the specific accounting policies used and where the materiality is such that further disclosure
is merited.
The Council’s Annual Accounts for 2024/25 have been prepared on a going concern basis. The concept of
a going concern assumes that the Council’s functions and services will continue in operational existence
for the foreseeable future. The provisions in respect of going concern reporting requirements reflect the
economic and statutory environment in which local authorities operate. These provisions confirm that, as
authorities cannot be created or dissolved without statutory prescription, they must prepare their annual
accounts on a going concern basis of accounting. In accordance with the CIPFA Code of Local Government
Accounting (2024/25), the Council is required to prepare its annual accounts on a going concern basis
unless informed by the relevant national body of the intention for dissolution without transfer of services
or function to another entity. The accounts are prepared on the assumption that the Council will continue
in operational existence for the foreseeable future.
1. Accounting Policies
i. General principles
The statement of accounts summarise the Council’s transactions for the 2024/25 financial year and its
position for the year-end of 31 March 2025. The Council is required to prepare an annual statement of
accounts by the Local Authority Accounts (Scotland) Regulations 2014, which Section 12 of the Local
Government Scotland Act 2003 require to be prepared in accordance with proper accounting practices.
These practices under Section 21 of the 2003 Act primarily comprise the Code of Practice on Local
Authority Accounting in the United Kingdom 2024/25, supported by International Financial Reporting
Standards (IFRS) and the statutory guidance issued under section 12 of the 2003 Act.
The accounting convention adopted in the statement of accounts is principally historical cost, modified by
the revaluation of certain categories of non-current assets and financial instruments.
ii. Accruals of income and expenditure
Activity is accounted for in the year that it takes place, not simply when cash payments are made or
received. In particular:
• Revenue from contracts with service recipients, whether for services or the provision of goods, is
recognised when (or as) the goods or services are transferred to the service recipient in
accordance with the performance obligations of the contract.
• Supplies are recorded as expenditure when they are consumed – where these is a gap between
the date supplies are received and their consumption, they are carried as inventories on the
Balance Sheet.
• Expenses in relation to services received (including services provided by employees) are recorded
as expenditure when the services are received rather than when payments are made.
• Interest receivable on deposits and payable on borrowings is accounted for respectively as
income and expenditure on the basis of the effective interest rate for the relevant financial
instrument rather than the cash flows fixed or determined by the contract.
• Where revenue and expenditure have been recognised but cash has not been received or paid, a
debtor or creditor for the relevant amount is recorded in the Balance Sheet. Where debts may not
be settled, the balance of debtors is written down and a charge made to revenue for the income
that might not be collected.
Page 336 of 396

Page 337

WWW.MIDLOTHIAN.GOV.UK 
38 Notes to the Accounts
iii. Cash and cash equivalents
Cash is represented by cash in hand and deposits with financial institutions repayable without penalty on
notice of not more than 24 hours. Cash equivalents are highly liquid deposits that mature in no more than
three months or less from the date of acquisition and that are readily convertible to known amounts of
cash with insignificant risk of change in value.
In the Cash Flow Statement, cash and cash equivalents are shown net of bank overdrafts that are
repayable on demand and form an integral part of the Council’s cash management.
iv. Prior period adjustments, changes in accounting policies, estimates and errors
Prior period adjustments may arise as a result of a change in accounting policies or to correct a material
error. Changes in accounting estimates are accounted for prospectively, i.e. in the current and future years
affected by the change and do not give rise to a prior year adjustment.
Changes in accounting policies are only made when required by proper accounting practices or the change
provides more reliable or relevant information about the effect of transactions, other events and
conditions on the Council’s financial position or financial performance. Where a change is made, it is
applied retrospectively (unless stated otherwise) by adjusting opening balances and comparative
amounts for the prior period as if the new policy had always been applied.
Material errors discovered in prior period figures are corrected retrospectively by amending opening
balances and comparative amounts for the prior period.
v. Charges to revenue for non-current assets
Services and support services are charged an accounting estimate of the cost of holding non-current
assets during the year. This comprises:
• Depreciation attributable to the assets used by the relevant service;
• Revaluation and impairment losses on assets used by the service where there are no accumulated
gains in the revaluation reserve against which the losses can be written off;
• Amortisation of intangible assets attributable to the service.
The Council is not required to raise council tax to fund depreciation, revaluation and impairment losses or
amortisation. However, it is required to make an annual contribution from revenue towards the reduction
in its overall borrowing requirement, equal to an amount calculated on a prudent basis determined by the
Council in accordance with the statutory Repayment of Loans Fund Advances. This is known as the Loans
Fund Principal Repayment. Depreciation, revaluation and impairment losses, and amortisation are
therefore replaced by the Loans Fund Principal Repayments in the General Fund balance by way of an
adjusting transaction with the Capital Adjustment Account in the Movement in Reserves Statement for the
difference between the two.
vi. Employee Benefits
Benefits payable during employment
Short-term employee benefits are those due to be settled wholly within 12 months of the year-end. They
include such benefits as wages and salaries, paid annual leave, paid sick leave and overtime for current
employees. They are recognised as an expense for services in the year in which employees render service
to the Council. An accrual is made for the cost of holiday entitlements earned by employees but not taken
before the year-end that employees can carry forward into the next financial year. The accrual is made at
the wages and salary rates applicable in the following accounting year. The accrual is charged to surplus
or deficit on the provision of services, but then reversed out through the Movement in Reserves Statement
to the accumulated absences account so that holiday entitlements are charged to revenue in the financial
year in which the holiday absence occurs.
Page 337 of 396

Page 338

WWW.MIDLOTHIAN.GOV.UK 
39 Notes to the Accounts
Termination benefits
Termination benefits are amounts payable as a result of a decision by the Council to terminate an officer’s
employment before normal retirement date or an officer’s decision to accept voluntary redundancy in
exchange for those benefits and are charged on an accruals basis to the appropriate service segment when
the Council is demonstrably committed to the termination of the employment of an officer or group of
officers or making an offer to encourage voluntary severance.  
Where termination benefits involve the enhancement of pensions, statutory provisions require the General
Fund balance to be charged with the amount payable by the Council to the pension fund or pensioner in
the year, not the amount calculated according to the relevant accounting standards. In the Movement in
Reserves Statement, appropriations are required to and from the pensions reserve to remove the notional
debits and credits for pension enhancement termination benefits and replace them with debits for the
cash paid to the pension fund and pensioners and any such amounts payable but unpaid at the year-end.
Post-employment benefits
Employees of the Council are members of two separate pension schemes:
• The Teachers’ pension scheme, administered by the Scottish Government;
• The Local Government Pensions Scheme, administered by the City of Edinburgh Council on behalf
of Lothian Pension Fund.
Both schemes provide defined benefits to members (retirement lump sums and pensions), earned as
employees worked for the Council.
However, the arrangements for the teachers’ scheme mean that liabilities for these benefits cannot
ordinarily be identified specifically to the Council. The scheme is therefore accounted for as if it were a
defined contribution scheme and no liability for future payments of benefits is recognised in the Balance
Sheet. The education services line in the Comprehensive Income and Expenditure Statement is charged
with the employer’s contributions payable to the Teachers’ Pensions in the year.
The Local Government Pension Scheme
The Local Government Pension Scheme is accounted for as a defined benefits scheme:
• The liabilities of the Lothian Pension Fund attributable to the Council are included in the Balance
Sheet on an actuarial basis using the projected unit method – i.e. an assessment of the future
payments that will be made in relation to retirement benefits earned to date by employees, based
on assumptions about mortality rates, employee turnover rates, etc. and projected earnings for
current employees.
• Liabilities are discounted to their value at current prices, using a discount rate as advised by the
actuary, Hymans Roberson LLP.
• The assets of Lothian Pension Fund attributable to the Council are included in the Balance Sheet
at their fair value:
o Quoted securities – current bid price;
o Unquoted securities – professional estimate;
o Unitised securities – current bid price;
o Property – market value.
The change in the net pension’s liability is analysed into the following components:
• Service cost comprising:
Page 338 of 396

Page 339

WWW.MIDLOTHIAN.GOV.UK 
40 Notes to the Accounts
– Current service cost - the increase in liabilities as a result of years of service earned this
year – allocated in the Comprehensive Income and Expenditure Statement to the services
for which the employees worked;
– Past service cost - the increase in liabilities as a result of a scheme amendment or
curtailment whose effect relates to years of service earned in earlier years – debited to the
surplus or deficit on the provision of services in the Comprehensive Income and
Expenditure Statement as part of Non-Distributed Costs;
– Net interest on the net defined liability (asset), i.e. net interest expense for the
Council - the change during the period in the net defined liability (asset) that arises from
the passage of time charged to the financing and investment income and expenditure line
of the Comprehensive Income and Expenditure Statement – this is calculated by applying
the discount rate used to measure the defined benefit obligation at the beginning of the
period to the net defined benefit liability (asset) at the beginning of the period, taking into
account any changes in the net defined benefit liability (asset) during the period as a result
of contribution and benefit payments.
• Re-measurements comprising:
– The return on plan assets – excluding amounts included in net interest on the net defined
benefit liability (asset) – charged to the pensions reserve as other comprehensive income
and expenditure;
– Actuarial gains and losses – changes in the net pensions liability that arise because
events have not coincided with assumptions made at the last actuarial valuation or
because the actuaries have updated their assumptions – charged to the pensions reserve
as other comprehensive income and expenditure;
– Contributions paid to the Lothian Pension Fund – cash paid as employer’s
contributions to the pension fund in settlement of liabilities; not accounted for as an
expense.
In relation to retirement benefits, statutory provisions require the General Fund balance to be charged with
the amount payable by the Council to the pension fund or directly to pensioners in the year, not the amount
calculated according to the relevant accounting standards. In the Movement in Reserves Statement, this
means that there are transfers to and from the pensions reserve to remove the notional debits and credits
for retirement benefits and replace them with debits for the cash paid to the pension fund and pensioners
and any such amounts payable but unpaid at the year-end. The negative balance that arises on the
pensions reserve thereby measures the beneficial impact to the General Fund of being required to account
for retirement benefits on the basis of cash flows rather than as benefits earned by employees.
Pension Net Asset Restriction Calculation
The actuary has calculated the Council’s IAS 19 defined benefit surplus for 2024/25 to be £273.943 million
as detailed in Note 35 to the accounts. IAS 19 states that when an entity has a surplus in the defined benefit
plan it should measure the net defined benefit of the asset as the lower of:
• The surplus in the defined benefit plan, and
• The asset ceiling, which the actuary has calculated as the present value of any economic benefits
available in the form of reductions in future contributions to the plan. 
For IFRIC 14 purposes, the actuary has calculated the net present value of the future contributions which
exceeds the value of the future service costs resulting in a negative contribution. As a result of this
calculation IFRIC 14 advises that no defined benefit plan asset should be recognised on the Council’s
Balance Sheet and there is no requirement to recognise the difference as a liability, however, is required
to reflect the liability in relation to present value of any unfunded obligations.
Page 339 of 396

Page 340

WWW.MIDLOTHIAN.GOV.UK 
41 Notes to the Accounts
Discretionary benefits
The Council also has restricted powers to make discretionary awards of retirement benefits in the event of
early retirements. Any liabilities estimated to arise as a result of an award to any member of staff (including
teachers) are accrued in the year of the decision to make the award and accounted for using the same
policies as are applied to the Local Government Pension Scheme.
vii. Employee Benefits
Events after the Balance Sheet reporting period are those events, both favourable and unfavourable, that
occur between the Balance Sheet date and the date when the statement of accounts is authorised for
issue. Two types of events can be identified:
• Those that provide evidence of conditions that existed at the end of the reporting period – the
statement of accounts is adjusted to reflect such events;
• Those that are indicative of conditions that arose after the reporting period – the statement of
accounts is not adjusted to reflect such events, but where such a category of events would have
a material effect, disclosure is made in the notes of the nature of the events and their estimated
financial effect.
Events taking place after the date of authorisation for issue are not reflected in the statement of accounts.
viii. Financial instruments
Financial Liabilities
Financial liabilities are recognised on the Balance Sheet when the Council becomes a party to the
contractual provisions of a financial instrument and are initially measured at fair value and are carried at
their amortised cost. Annual charges to the financing and investment income and expenditure line in the
Comprehensive Income and Expenditure Statement (CIES) for interest payable are based on the carrying
amount of the liability, multiplied by the effective rate of interest for the instrument. The effective interest
rate is the rate that exactly discounts estimated future cash payments over the life of the instrument to the
amount at which it was originally recognised.
For most of the borrowings that the Council has, this means that the amount presented in the Balance
Sheet is the outstanding principal repayable (plus accrued interest); and interest charged to the CIES is the
amount payable for the year according to the loan agreement.
Where premiums and discounts have been charged to the CIES, regulations allow the impact on the
General Fund or Housing Revenue Account balances to be spread over future years. The Council has a
policy of spreading the gain or loss over the term that was remaining on the loan against which the premium
was payable or discount receivable when it was repaid. The reconciliation of amounts charged to the CIES
to the net charge required against the General Fund balance is managed by a transfer to or from the
financial instruments adjustment account in the Movement in Reserves Statement.
Financial Assets
Financial assets are classified based on a classification and measurement approach that reflects the
business model for holding the financial assets and their cash flow characteristics. The Council holds
financial assets measured at:
• Amortised cost; and
• Fair value through other comprehensive income (FVOCI).
The Council’s business model is to hold investments to collect contractual cash flows. Financial assets
are therefore classified at amortised cost, except for those whose contractual payments are not solely
payment of principal and interest (i.e. where the cash flows do not take the form of a basic debt
instrument).
Page 340 of 396

Page 341

WWW.MIDLOTHIAN.GOV.UK 
42 Notes to the Accounts
Financial Assets Measured at Amortised Cost
Financial assets measured at amortised cost are recognised on the Balance Sheet when the Council
becomes party to the contractual provisions of a financial instrument and are initially measured at fair
value. They are subsequently measured at their amortised cost. Annual credits to the financing and
investment income and expenditure line in the CIES for interest receivable are based on the carrying
amount of the asset multiplied by the effective rate of interest for the instrument. For most of the financial
assets held by the Council, this means that the amount presented in the Balance Sheet is the outstanding
principal receivable (plus accrued interest), and interest credited to the CIES is the amount receivable for
the year in the loan agreement.
Any gains and losses that arise on de-recognition of a financial asset are credited or debited to the
financing and investment income and expenditure line in the CIES.
Expected Credit Loss Model
The Council recognises expected credit losses on all of its financial assets held at amortised cost (or
where relevant FVOCI), either on a   12-month or lifetime basis. The expected credit loss model also
applies to lease receivables and contract assets. Only lifetime losses are recognised for trade
receivables (debtors) held by the Council.
Impairment losses are calculated to reflect the expectation that the future cash flows might not take
place because the borrower could default on their obligations. Credit risk plays a crucial part in
assessing losses. Where risk has increased significantly since an instrument was initially recognised,
losses are assessed on a lifetime basis. Where risk has not increased significantly or remains low,
losses are assessed on the basis of 12-month expected losses.
Financial Assets Measured at Fair Value through Other Comprehensive Income (FVOCI)
Financial assets that are measured at FVOCI are recognised on the Balance Sheet when the Council
becomes a party to the contractual provisions of a financial instrument and are initially measured and
carried at fair value. Fair value gains and losses are recognised as they arise in other comprehensive
income.
Fair Value Measurement of Financial Assets
Fair value of an asset is the price that would be received to sell an asset in an orderly transaction between
market participants at the measurement date. The fair value measurements of the Council’s financial
assets are based on the following techniques:
• Instruments with quoted market prices – the market price;
• Other instruments with fixed determinable payments – discounted cash flow analysis.
The inputs to the measurement techniques are categorised in accordance with the following three levels:
• Level 1 inputs – quoted prices (unadjusted) in active markets for identical assets that the Council
can access at the measurement date;
• Level 2 inputs – inputs other than quoted prices included in Level 1 that are observable for the
asset, either directly or indirectly; 
• Level 3 inputs – unobservable inputs for the asset.
Any gains and losses that arise on de-recognition of the asset are credited or debited to the financing and
investment income and expenditure line in the Comprehensive Income and Expenditure Statement.
The Council designates that investments held for strategic purposes be classified as being measured as
FVOCI. Any gains and losses on these investments will be held in the Financial Instruments Revaluation
Reserve.
Page 341 of 396

Page 342

WWW.MIDLOTHIAN.GOV.UK 
43 Notes to the Accounts
Where assets are identified as impaired because of a likelihood arising from a past event that payments
due under the contract will not be made (fixed or determinable payments) or fair value falls below cost, the
asset it written down and a charge made to the Financing and Investment Income and Expenditure line in
the CIES. If the asset has fixed or determinable payments, the impairment loss is measured as the
difference between the carrying amount and the present value of the revised future cash flows discounted
at the asset’s original effective interest rate. Otherwise the impairment loss is measured as any shortfall
of fair value against the acquisition cost of the instrument (net of any principal repayment and
amortisation).
ix. Government grants and contributions
Whether paid on account, by instalments or in arrears, government grants and third party contributions
and donations are recognised  as due to the Council when there is reasonable assurance that:
• The Council will comply with the conditions attached to the payments; and
• The grants or contributions will be received.
Amounts recognised as due to the Council are not credited to the Comprehensive Income and Expenditure
Statement until conditions attached to the grant or contribution have been satisfied. Conditions are
stipulations that specify that the future economic benefits or service potential embodied in the asset in
the form of the grant or contribution are required to be consumed by the recipient as specified, or future
economic benefits or service potential must be returned to the transferor.
Monies advanced as grants and contributions for which conditions have not been satisfied are carried in
the Balance Sheet as creditors. When conditions are satisfied, the grant or contribution is credited to the
relevant service line (attributable revenue grants and contributions) or taxation and non-specific grant
income and expenditure (non-ring-fenced revenue grants and all capital grants) in the Comprehensive
Income and Expenditure Statement.
Where capital grants are credited to the Comprehensive Income and Expenditure Statement, they are
reversed out of the General Fund Balance in the Movement in Reserves Statement. Where the grant has
yet to be used to finance capital expenditure, it is posted to the capital grants received in advance. Where
it has been applied, it is posted to the Capital Adjustment Account once they have been applied to fund
capital expenditure.
x. Heritage assets
A heritage asset is defined as a tangible asset with historical, artistic, scientific, technological, geophysical
or environmental qualities that is held and maintained principally for its contribution to knowledge and
culture.
Heritage assets are valued at insurance replacement value where available, otherwise assets are held at
depreciated historic cost since the cost of obtaining a valuation would outweigh the benefits to users of
the accounts.
xi. Intangible assets
Expenditure on non-monetary assets that do not have physical substance but are controlled by the Council
as result of past events (i.e. software licences) is capitalised when it is expected that future economic
benefits or service potential will flow from the intangible asset to the Council.
Intangible assets are measured initially at cost. Amounts are only revalued where the fair value of assets
held by the Council can be determined by reference to an active market. In practice, no intangible asset
held by the Council meets this criterion, and they are therefore carried at amortised cost. The depreciable
amount of an intangible asset is amortised over its useful life to the relevant service(s) line in the
Comprehensive Income and Expenditure Statement. An asset is tested for impairment whenever there is
Page 342 of 396

Page 343

WWW.MIDLOTHIAN.GOV.UK 
44 Notes to the Accounts
an indication that the asset might be impaired – any losses recognised are posted to the relevant service
line(s) in the Comprehensive Income and Expenditure Statement.
xii. Interests in companies and other entities
The Council has an interest in companies and other entities that have the nature of subsidiaries,
associates and jointly controlled entities. In the Council’s own single entity accounts these interests are
recorded as the share of net assets.
xiii. Inventories
Inventories are included in the Balance Sheet at the lower of cost and net realisable value. The cost of
inventories is assigned using the First in First out (FIFO) costing formula.
xiv. Leases
The Council as lessee
The Council classifies contracts a leases based on their substance. Contracts and parts of contracts,
including those described as contracts for services, are analysed to determine whether they convey the
right to control the use of an identified asset, through the rights both to obtain substantially all the
economic benefits or service potential from that asset and to direct its use. The Code expands the scope
of IFRS 16 Leases to include arrangements with nil consideration, peppercorn or nominal payments.
Initial Measurement
Leases are recognised as right-of-use assets with a corresponding liability at the date from which the
leased asset is available for use (or IAS 16 transition date, if later). The leases are typically for fixed periods
in excess of one year but may have extension options.
The Council recognises lease liabilities measured at the present value of lease payments, discounting by
applying the Council’s incremental borrowing rate wherever the interest rate implicit in the lease cannot
be determined. Lease payments included in the measurement of the lease liability include:
• Fixed payments, including in-substance fixed payments;
• Variable lease payments that depend on an index or rate, initially measured using the prevailing
index or rate as at the adoption date;
• Amounts expected to be payable under a residual value guarantee;
• The exercise price under a purchase option that the Council is reasonably certain to exercise;
• Lease payments in an optional renewal period if the Council is reasonably certain to exercise an
extension option;
• Penalties for early termination of a lease, unless the Council is reasonably certain not to terminate
early.
The right-of-use asset is measured at the amount of the lease liability, adjusted for any prepayments made,
plus any direct costs incurred to dismantle and remove the underlying asset or restore the  underlying asset
on the site on which it is located, less any lease incentives received. However, for peppercorn, nominal
payments or nil consideration leases, the asset is measured at fair value.
Subsequent Measurement
The right-of-use asset is subsequently measured using the fair value model.  The Council considers the
cost model to be a reasonable proxy except for:
• Assets held under non-commercial leases;
• Leases where rent reviews do not necessarily reflect market conditions;
Page 343 of 396

Page 344

WWW.MIDLOTHIAN.GOV.UK 
45 Notes to the Accounts
• Leases with terms of more than five years that do not have any provision for rent reviews;
• Leases where rent reviews will be at periods of more than five years.
For theses leases, the asset is carried as a revalued amount. In these financial statements, right-of-use
assets held under index-linked leases have been adjusted for changes in the relevant index, while assets
held under peppercorn nil consideration leases have been valued using market prices or rentals for
equivalent land and properties.
The right-of-use asset is depreciated straight-line over the shorter period of the remaining lease term and
useful life of the underlying asset as at the date of adoption.
The lease liability is subsequently measured at amortised cost, using the effective interest method. The
liability is remeasured when:
• There is a change in future lease payments arising from a change in index or rate;
• There is a change in the group’s estimate of the amount expected to be payable under a residual
value guarantee;
• The Council changes its assessment of whether it will exercise a purchase, extension or
termination option, or;
• There is a revised in-substance fixed lease payment.
When such remeasurement occurs, a corresponding adjustment is made to the carrying amount of the
right-of-use asset, with any further adjustment required from remeasurement being recorded in the
income statement. 
Low Value and Short Lease Exemption
As permitted by the code, the Council excludes leases:
• For low-value items that cost less than £10,000 when new, provided they are not highly
dependent on or integrated with other items, and;
• With a term shorter than twelve months (comprising the non-cancellable period plus any
extension options that the authority is reasonably certain to exercise and any termination options
that the authority is reasonably certain not to exercise).
Lease Expenditure
Expenditure in the Comprehensive Income and Expenditure Statement includes interest, straight-line
depreciation, any asset impairments and changes in variable lease payments not included in the
measurement of the liability during the period in which the triggering event occurred. Lease payments less
than twelve months are expensed.
Depreciation and impairments are not charged against council tax, as the cost of non-current assets is
fully provided for under separate arrangements for capital financing. Amounts are therefore appropriated
to the Capital Adjustment Account from the General Fund balance in the Movement in Reserves
Statement. 
The Council as lessor
Midlothian Council currently has no finance leases where the Council is the lessor.
xv. Allocation of Support Services
Support services will not be recharged although the costs of services provided by the Council will be
charged to separate accounts such as the Housing Revenue Account. The costs of support and other
services will be allocated in government returns as required.
Page 344 of 396

Page 345

WWW.MIDLOTHIAN.GOV.UK 
46 Notes to the Accounts
xvi. Property, Plant and Equipment
Assets that have physical substance and are held for use in the production or supply of goods or services,
for rental to others or for administrative purposes, and that are expected to be used during more than one
financial year are classified as Property, Plant and Equipment.
Recognition
Expenditure on the acquisition, creation or enhancement of Property, Plant and Equipment is capitalised
on an accruals basis, provided it is probable that the future economic benefits or service potential
associated with the item will flow to the Council and the cost of the item can be measured reliably.
Expenditure that maintains but does not add to an asset’s potential to deliver future economic benefits or
service potential (i.e. repairs and maintenance) is charged as an expense when it is incurred.
Measurement
Assets are initially measured at cost, comprising:
• The purchase price;
• Any costs attributable to bringing the asset to the location and condition necessary for it to be
capable of operating in the manner intended by management.
The Council does not capitalise borrowing costs incurred whilst assets are under construction.
The cost of assets acquired other than by purchase is deemed to be its fair value, unless the acquisition
does not have commercial substance (i.e. it will not lead to a variation in the cash flows of the Council). In
the latter case, where an asset is acquired via an exchange, the cost of the acquisition is the carrying
amount of the asset given up by the Council.
Assets are carried in the balance sheet using the following measurement bases:
• Community assets – depreciated historical cost;
• Assets under construction – historical cost;
• Dwellings - current value, determined using the basis of existing use value for social housing
(EUV-SH). Gross valuations are reduced by applying the discount factor which is designed to
reflect that houses are only available for social use. Any new build housing and newly purchased
houses are valued at historic cost;
• Vehicles, Plant and Equipment – depreciated historical cost;
• Surplus Assets – fair value based on open market value;
• Other land and buildings – current value, determined as the amount that would be paid for the
asset in its existing use (existing use value – EUV).
Where there is no market-based evidence of current value because of the specialist nature of an asset,
depreciated replacement cost (DRC) is used as an estimate of current value.
Where non-property assets that have short useful lives or low values (or both), depreciated historical cost
basis is used as a proxy for current value.
Assets included in the Balance Sheet at current value are revalued as a minimum every five years to ensure
their carrying amount is not materially different from their current value at year-end. As part of the
Council’s plan for revaluation, a move has been made to revalue all items in a specific category in the same
year, if one of the assets in the category has been revalued. Increases in valuations are matched by credits
to the Revaluation Reserve to recognise any unrealised gains. Exceptionally, gains might be credited to the
surplus or deficit on the provision of services where they arise from the reversal of a loss previously charged
to the service.
Page 345 of 396

Page 346

WWW.MIDLOTHIAN.GOV.UK 
47 Notes to the Accounts
Where decreases in value are identified, they are accounted for by:
• Where there is a balance of revaluation gains for the asset in the Revaluation Reserve, the carrying
amount of the asset is written down against that balance (up to the amount of the accumulated
gains);
• Where there is no balance in the Revaluation Reserve or an insufficient balance, the carrying
amount of the asset is written down against the relevant service line(s) in the Comprehensive
Income and Expenditure Statement (CIES).
The Revaluation Reserve contains revaluation gains recognised since 1 April 2007 only, the date of its
formal implementation. Gains arising before that date have been consolidated into the Capital Adjustment
Account.
Impairment
Assets are assessed at each year-end to establish whether there is any indication that an asset may be
impaired. Where indications exist and any possible differences are estimated to be material, the
recoverable amount of the asset is estimated and, where this is less than the carrying amount of the asset,
an impairment loss is recognised for the shortfall.
Where impairment losses are identified, they are accounted for by:
• Where there is a balance of revaluation gains for the asset in the Revaluation Reserve, the carrying
amount of the asset is written down against that balance (up to the amount of the accumulated
gains);
• Where there is no balance in the Revaluation Reserve or an insufficient balance the carrying
amount of the asset is written down against the relevant service line(s) in the CIES.
Where an impairment loss is subsequently reversed, the reversal is credited to the Revaluation Reserve or
the relevant service line(s) in the CIES, up to the amount of the original loss, adjusted for depreciation that
would have been charged if the loss had not been recognised.
Depreciation
Depreciation is provided for on all Property, Plant and Equipment assets by the systematic allocation of
their depreciable amounts over their useful lives. An exception is made for assets without a determinable
finite useful life (i.e. freehold land and certain Community Assets) and assets that are not yet available for
use (i.e. assets under construction).
Depreciation is calculated on the following bases:
• Dwellings and other buildings – straight-line allocation over the useful life of the property as
estimated by the valuer;
• Vehicles, plant and equipment – straight-line allocation over the useful life of the assets in
Balance Sheet, as advised by a suitably qualified officer).
Where an item of Property, Plant and Equipment asset has major components whose cost is significant in
relation to the total cost of the item, the components are depreciated separately. Council policy is to only
consider any asset with a gross book value of £1.5 million or above. The assessment of which components
of these assets require to be recognised and depreciated separately is based on the cost of each of
component. Significance is determined by comparing the cost of components against the overall cost of
the asset. This threshold is set at 15% or more of the overall cost of the asset.
Revaluation gains are also depreciated, with an amount equal to the difference between current value
depreciation charged on assets and the depreciation that would have been chargeable based on their
historical cost being transferred each year from the Revaluation Reserve to the Capital Adjustment
Account.
Page 346 of 396

Page 347

WWW.MIDLOTHIAN.GOV.UK 
48 Notes to the Accounts
Disposals of non-current assets held for sale
When it becomes probable that the carrying amount of the asset will be recovered principally through a
sale transaction rather than through its continuing use, it is reclassified as an Asset Held for Sale. The asset
is revalued immediately before reclassification and then carried at the lower of this amount and fair value
less costs to sell. Where there is a subsequent decrease to fair value less costs to sell, the loss is posted
to the other operating expenditure Line in the CIES. Gains in fair value are recognised only up to the amount
of any previously recognised losses in the Surplus or Deficit on the Provision of Services. Depreciation is
not charged on Assets Held for Sale.
If assets no longer meet the criteria to be classified as Assets Held for Sale, they are reclassified back to
non-current assets and valued at the lower of their carrying amount before they were classified as Held for
Sale; adjusted for depreciation, amortisation or revaluations that would have been recognised had they
not been classified as Held for Sale, and their recoverable amount at the date of the decision not to sell.  
Assets that are to be abandoned or scrapped are not reclassified as Assets Held for Sale.
When an asset is disposed of or decommissioned, the carrying amount of the asset in the Balance Sheet
(whether Property, Plant and Equipment or Assets Held for Sale) is written off to the Other Operating
Expenditure Line in the CIES as part of the gain or loss on disposal. Receipts from disposals (if any) are
credited to the same line in the CIES also as part of the gain or loss on disposal (i.e. netted off against the
carrying value of the asset at the time of disposal). Any revaluation gains accumulated for the asset in the
Revaluation Reserve are transferred to the Capital Adjustment Account.
Amounts received for a disposal in excess of £10,000 are categorised as capital receipts. The balance of
receipts is credited to the Capital Fund and can then only be used for new capital investment or to defray
debt. Receipts are appropriated to the Reserve from the General Fund Balance in the Movement in
Reserves Statement.
The written-off value of disposals is not a charge against Council Tax, as the cost of non-current assets is
fully provided for under separate arrangements for capital financing. Amounts are appropriated to the
Capital Adjustment Account from the General Fund Balance in the Movement in Reserves Statement.
xvii. Infrastructure Assets
More information on the accounting for and disclosure around infrastructure assets held by the Council
can be found at note 15.
xviii. Public Private Partnership (PPP) and Similar Contracts
PPP and similar contracts are agreements to receive services, where the responsibility for making available
the property, plant and equipment needed to provide the services passes to the contractor. As the Council
is deemed to control the services that are provided under its schemes, and where ownership of the
property, plant and equipment will pass to the Council at the end of the contracts for no additional charge,
the Council carries the assets used under the contracts on its Balance Sheet as part of Property, Plant and
Equipment.
The original recognition of these assets at fair value (based on the cost to purchase the property, plant and
equipment) was balanced by the recognition of a liability for amounts due to the scheme operator to pay
for the capital investment.
Non-current assets recognised on the Balance Sheet are re-valued and depreciated in the same way as
property, plant and equipment owned by the Council.
The amounts payable to operators each year are analysed into five elements:
• Fair value of the services received during the year – debited to the relevant service in the
Comprehensive Income and Expenditure Statement (CIES);
Page 347 of 396

Page 348

WWW.MIDLOTHIAN.GOV.UK 
49 Notes to the Accounts
• Finance Cost – an interest charge on the outstanding Balance Sheet liability, debited to the
Financing and Investment Income and Expenditure line in the CIES,  the interest charges are as
follows:
o Dalkeith Schools  - 9.69%;
o Midlothian Primary Schools - 7.29%;
o Newbattle Community Campus - 5.06%;
o Residual Waste Treatment Plant, Millerhill – 18.84%; 
• Contingent rent – increases in the amount to be paid for the property arising during the contract,
debited to the Financing and Investment Income and Expenditure line in the CIES;
• Payment towards liability – applied to write down the Balance Sheet liability towards the PPP
operator (the profile of write-downs is calculated using the same principles as for a finance lease);
• Service charge and lifecycle replacement costs – proportion of the amounts payable is posted
to the Balance Sheet as a prepayment and then recognised as additions to Property, Plant and
Equipment when the relevant works are eventually carried out.
xix. Provisions, Contingent Liabilities and Contingent Assets
Provisions
Provisions are made where an event has taken place that gives the Council a legal or constructive
obligation that probably requires settlement by a transfer of economic benefits or service potential, and a
reliable estimate can be made of the amount of the obligation. For instance, the Council may be involved
in a court case that could eventually result in the making of a settlement or the payment of compensation.
Provisions are charged as an expense to the appropriate service line in the Comprehensive Income and
Expenditure Statement in the year that the Council becomes aware of the obligation, and are measured at
the best estimate at the balance sheet date of the expenditure required to settle the obligation, taking into
account relevant risks and uncertainties.
When payments are eventually made, they are charged to the provision carried in the balance sheet.
Estimated settlements are reviewed at the end of each financial year – where it becomes less than
probable that a transfer of economic benefits will now be required (or a lower settlement than anticipated
is made), the provision is reversed and credited back to the relevant service.
Where some or all of the payment required to settle a provision is expected to be recovered from another
party (i.e. from an insurance claim), this is only recognised as income for the relevant service if it is virtually
certain that reimbursement will be received if the Council settles the obligation.
Contingent Liabilities
A contingent liability arises where an event has taken place that gives the Council a possible obligation,
whose existence will only be confirmed by the occurrence or otherwise of uncertain future events not
wholly within control of the Council. Contingent liabilities also arise in circumstances where a provision
would otherwise be made but either it is not definite that an outflow of resources will be required, or the
amount of the obligation cannot be measured reliably.
Contingent liabilities are not recognised in the balance sheet but disclosed in a note to the accounts.
Contingent Assets
A contingent asset arises where an event has taken place that gives the Council a possible asset whose
existence will only be confirmed by the occurrence or otherwise of uncertain future events not wholly
within the control of the Council.
Page 348 of 396

Page 349

WWW.MIDLOTHIAN.GOV.UK 
50 Notes to the Accounts
Contingent assets are not recognised in the balance sheet but disclosed in a note to the accounts where
it is probable that there will be an inflow of economic benefits or service potential.
xx. Reserves
Reserves are created by transferring amounts out of the General Fund Balance. When Expenditure to be
financed from a reserve is incurred, it is charged to the appropriate service in that year to score against the
Surplus or Deficit on the Provision of Services in the Comprehensive Income and Expenditure Statement.
The reserve is then transferred back into the General Fund Balance in the Movement in Reserves Statement
so that there is no net charge against Council Tax for the expenditure.
Certain reserves are kept to manage the accounting processes for non-current assets, financial
instruments and retirement and employee benefits and do not represent usable resources for the Council
– these reserves are explained in the relevant policies.
xxi. Revenue Expenditure Funded from Capital Under Statute (Refcus)
Expenditure incurred during the year that may be capitalised under statutory provisions but that does not
result in the creation of a non-current asset is charged as expenditure to the relevant service line in the
Comprehensive Income and Expenditure Statement in the year. Where the Council has determined to
meet the cost of this expenditure from existing capital resources or by borrowing, a transfer in the
Movement in Reserves Statement from the General Fund Balance to the Capital Adjustment Account then
reverses out the amounts charged so there is no impact on the level of council tax.
xxii. VAT
VAT payable is included as an expense only to the extent that it is not recoverable from HMRC. VAT
receivable is excluded from income.
xxiii. Fair Value Measurement of Non-financial Assets
The Council measures some of its non-financial assets, such as Surplus Assets and some of its financial
instruments at fair value at each reporting date. Fair value is the price that would be received to sell an
asset in an orderly transaction between market participants at the measurement date. The fair value
measurement assumes the transaction to sell the asset takes place either:
• In the principal market for the asset; or
• In the absence of a principal market, in the most advantageous market for the asset.
The Council measures the fair value of an asset using the assumptions that market participants would use
when pricing the asset, assuming the market participants act in their economic best interest.
When measuring the fair value of a non-financial asset, the Council takes into account a market
participant’s ability to generate economic benefits by using the asset in its highest and best use or by
selling it to another market participant that would use the asset in its highest and best use. 
The Council uses valuation techniques that are appropriate in the circumstances and for which sufficient
data is available, maximising the use of relevant observable inputs and minimising the use of unobservable
inputs.
Inputs to the valuation techniques in respect of assets and liabilities for which Fair Value is measured or
disclosed in the Council’s financial statements are categorised within the fair value hierarchy, as follows:
• Level 1 inputs – quoted prices (unadjusted) in active markets for identical assets that the Council
can access at the measurement date;
• Level 2 inputs – inputs other than quoted prices included within Level 1 that are observable for
the asset, either directly or indirectly;
• Level 3 inputs – unobservable inputs for the asset.
Page 349 of 396

Page 350

WWW.MIDLOTHIAN.GOV.UK 
51 Notes to the Accounts
2. Accounting Standards Issued, Not Yet Adopted
The code requires disclosure of information relating to the impact of an accounting change that will be
required by a new standard that has been issued but not yet adopted. This applies to the adoption of the
following new or amended standards within the 2025/26 code.
• The changes to the measurement of non-investment assets with the 2025/26 code include
adaptations and interpretations of IAS 16 Property, Plant and Equipment and IAS 38 Intangible
Assets. These include setting out three revaluation processes for operational property, plant and
equipment, requiring indexation for tangible non-investment assets and a requirement to value
intangible assets using the historical cost approach.
The changes will be effective from 1 April 2025 and none are expected to have a material impact on the
Council’s financial statements.
3. Critical Judgements in Applying Accounting Policies
In applying the accounting policies set out in Note 1, the Council has to make certain judgements about
complex transactions or those involving uncertainty about future events (see Note 4). The accounting
policies considered and critical judgements made in the annual accounts are:
• Uncertainty over future funding - There is a high degree of uncertainty around future levels of
funding for local government, which may significantly impact the Council’s ability to maintain its
property, plant and equipment. The council has determined that this uncertainty is not yet
sufficient to provide an indication that the assets of the council might be impaired as a result of a
reduction in funding and subsequent required changes to investment and capital strategies
• Public-Private Partnerships (PPP) and similar type contracts - The Council has entered into PPP
and similar type contracts for the provision of educational buildings and waste facilities as
detailed in Note 33. For each of these contracts the Council has considered the tests under IFRIC
12 and concluded the following:
The Council is deemed to control the services provided under the scheme and ownership of
schools will pass to the Council at the end of the contract. The educational buildings are therefore
all recognised as Property, Plant and Equipment on the Council’s Balance Sheet.
The Council is deemed to control 20% of the services provided under the Design, Build, Finance
and Maintain (DBFM) for the Residual Waste Treatment Plant (80% controlled by Edinburgh
Council) and is therefore recognised as Property, Plant and Equipment on the Council’s Balance
Sheet. Having considered the ownership transfers as outlined in Note 33 the Council is not
deemed to control the Millerhill Food Waste Treatment Plant and has therefore concluded this is
a service concession.
The Council has therefore recognised assets in relation to PPP and similar type contracts on the
council’s balance sheet at a net book value of £197.405 million, with a corresponding liability in
relation to future payments to be made under the scheme of £85.790 million.
• Associates -  The Valuation Joint Board is included within the group accounts under the wider
definition of an “associate” although the council holds less than 20% of voting rights that is
normally presumed to confer significant influence. This is in view of the funding arrangements in
place whereby the Council provides £0.613 million annually, and as such is considered to hold
significant influence. Details of the impact on the Group accounts is provided in Note 39.
4. Future Assumptions and Estimation Uncertainties
The Annual Accounts contain estimated figures that are based on assumptions made by the Council about
the future or events that are otherwise uncertain. Estimates are made taking into account historical
Page 350 of 396

Page 351

WWW.MIDLOTHIAN.GOV.UK 
52 Notes to the Accounts
experience, current trends and other relevant factors. The assumptions and other sources of estimation
uncertainty disclosed below relate to the estimates that require the Council’s most difficult, subjective or
complex judgements. As the number of variables and assumptions affecting the possible future resolution
of the uncertainties increases, those judgements become more subjective and complex. As a result,
balances cannot be determined with certainty and actual results could be materially different from the
assumptions and estimates.
The items in the Council’s Balance Sheet as at 31 March 2025 for which there is significant risk of material
adjustment in the forthcoming year are as follows:
Property, Plant and Equipment
Uncertainties
The valuation of the Council’s property, plant and equipment which are subject to revaluation are subject
to significant estimation due to several factors, including ongoing changes to estimates around the costs
of replacing existing assets, the market value fluctuation of comparable assets used for valuation, the
current condition and future maintenance costs of assets, changes to regulatory standards and the
remaining useful economic lives of the assets. Given the material nature of the Council’s assets, there is
a high likelihood that changes in these estimates will result in material changes in the valuation of assets
on the balance sheet. The total value of the Council’s assets at 31 March 2025 is outlined and broken down
by asset category at note 14.
2024/25 Valuations
In 2024/25, revaluations were undertaken for the following assets:
31 March - Housing stock, parks & open spaces, garages & garage sites, several schools and depots.
The housing assets were revalued on a EUV-SH basis and totalled £462.478 million, the parks &
open spaces were revalued on a DRC basis and totalled  £28.850 million, garages & garage sites
were revalued  on a DRC basis and totalled £3.195 million, the schools were revalued on a DRC
basis and totalled  £231.449 million and the depots were valued on  a  DRC basis and totalled
£30.591 million, with a valuation movement of (£82.455 million) for housing, (£0.325 million) for
parks & open spaces, (£0.766 million) for garages & garage sites and  (£3.959 million) for the schools
, £5.280 million for the depots (from previous valuation (15.12%) for housing, (1.11%) for  parks &
open spaces, (19.33%) for garages & garage sites, (1.68%) for the schools, 21.99% for the depots). 
The changes in valuation in assets in 2024/25, compared to 2023/24, represent updated information
around the assets since the most recent full valuation, in particular the cost of replacing assets
based on indices for schools, the changes in adjustments for social rent discounts for housing
stock, updating housing market information, and updated information on the indices used to value
parks & open spaces.
Ongoing assessment of asset valuation
In addition to formal valuations of property, plant and equipment on a rolling basis over a five year
period, the Council assesses all assets to ensure there are no material changes that should drive
an earlier valuation, to ensure that, in line with the CIPFA code, assets are revalued with sufficient
regularity to ensure that the carrying amount does not differ materially from that which would be
determined using the current value at the end of the reporting period. The council’s Corporate
Estates Manager has determined in his professional opinion that, at 31 March 2025, no asset
categories were subject to early revaluation. The council has also continued to assess the valuation
of its asset base after the financial year end to ensure new information does not indicate a change
in valuation at the balance sheet date.
Assets are depreciated over useful lives that are dependent on several assumptions including the
level of repairs and maintenance that will be incurred in relation to individual assets.
Page 351 of 396

Page 352

WWW.MIDLOTHIAN.GOV.UK 
53 Notes to the Accounts
Effect if Actual Result Differ from Assumptions
The net book value of all council property, plant and equipment subject to revaluation through the 5 year
revaluation cycle is £1.084.111 billion. Assets revalued in 2024/25 totalled £97.934 million before
revaluation. 
The impact of a 5% change in valuation of these would be £6.483 million, either resulting in an increase or
decrease in the Council’s revaluation reserve or an additional impairment charge. There would be no
impact on the Council’s general fund. 
Given the wide ranging nature of the assets under revaluation, as well as the differing and overlapping
estimates involved in the valuations, it is not possible for management to provide an expected range of
estimate outcomes going forward. However, given the experience in past years and materiality of the asset
values, it is expected that these balances will continue to be subject to change as estimates are updated
annually.
If the useful life of the asset is reduced, depreciation increases and the carrying amount of the asset falls.
It is estimated that the annual depreciation charge would increase by £7.196 million for every year that
useful lives had to be reduced.
Pension Obligation
Uncertainties
Estimation of the net obligation to pay pensions depends on several complex judgements relating to the
discount rate used, the rate at which salaries are projected to increase, changes in retirement ages,
mortality rates and expected returns on pension fund assets. A firm of consulting actuaries is engaged to
provide the council with expert advice about the assumptions to be applied.
The actuarial inputs into the pension obligation valuation are subject to annual review, and have a
significant impact on the potential valuation. Historically it is common for small changes in the discount
rate, salary assumption rate and pension rate to have material impacts on the year-end valuations on a
year to year basis. 
More information on the key assumptions used in the actuarial valuation of the estimates is available in
note 35 to the accounts, including information on the key assumptions, risks, sensitivities and restrictions
on the amount on the balance sheet arising from IFRIC 14. An update is also included in this note on the
latest development around several equalisation adjustments to pension obligation which have occurred
in LGPS and may continue to materially impact the valuation of the Council’s obligation going forward.
Effect if Actual Result Differ from Assumptions
The effects of the net pension obligation of changes in individual assumptions can be measured. For
instance, it is estimated that a one year increase in life expectancy would approximately increase the
Employers Defined Benefit Obligation by around 3-5%. 
However the assumptions interact in complex ways. During 2023/24 the Council’s actuary advised that
the net pension obligation had increased by £81,339 million because of estimates being corrected as a
result of updating of the financial assumptions.
Arrears
Uncertainties
As at 31 March the Council has Council Tax and Non-Domestic Rates debt due of £46.943 million.
Management reviewed this balance at 31 March and determined that an allowance for doubtful debts,
detailed in Note 23, of £46.826 million was appropriate based upon historical assessment of
recoverability/review of individual balances and correspondence with third parties at year-end. However,
it is recognised that in the current economic climate and taking into account the impact of Covid-19 there
Page 352 of 396

Page 353

WWW.MIDLOTHIAN.GOV.UK 
54 Notes to the Accounts
is increased uncertainty around the recoverability of debtor balances. Management has continued to
review all material outstanding balances at the year-end subsequent to 31 March, and has not determined
any further allowance is required based on recovery to date.
Effect if Actual Result Differ from Assumptions
If collection rates were to deteriorate then this will result in an increase in the provision required i.e., 1%
would require an increase of £0.468 million, 3% an increase of £1.405 million and 5% an increase of £2.341
million.
5. Events after the Reporting Period
The Unaudited Accounts were authorised for issue on 16 June 2025 by the Chief Financial Officer. Events
taking place after these dates are not reflected in the annual financial statements or notes. Where events
taking place before these dates provided information about conditions existing at 31 March 2025, the
figures in the financial statements and notes have been adjusted in all material respects to reflect the
impact of this information. 
Page 353 of 396

Page 354

WWW.MIDLOTHIAN.GOV.UK 
55 Notes to the Accounts
6. Note to the Expenditure and Funding Analysis 
Adjustments between funding and accounting basis    
Adjustments from General Fund to arrive at the
Comprehensive Income and Expenditure Statement
amounts
Adjustments
for Capital
Purposes
Net Change
for Pension
Adjustments 
Other
Adjustments 
Total
Adjustments 
£000 £000 £000 £000
Current Year 2024/25    
Management and Members 0 17 3 20
Children’s Services, Partnerships and Communities 299 129 (2) 426
Education 26,662 2,159 1,178 29,999
Adult Health and Social Care (Non-Delegated) 0 0 10 10
Midlothian Integrated Joint Board 470 315 (60) 725
Place 7,726 550 5 8,281
Corporate Solutions 1,866 (383) 15 1,498
Housing Revenue Account 63,309 19 0 63,328
Joint Boards 0 0 0 0
Central Costs 69 0 0 69
Non-distributable Costs 0 0 0 0
Net Cost of Services 100,401 2,806 1,149 104,356
Other expenditure from the Expenditure and Funding Analysis (42,887) (8,880) (13) (51,780)
Adjustments between funding and accounting basis 57,514 (6,074) 1,136 52,576
Application of Service Concessions 0 0 2,796 2,796
Difference between the General Fund surplus or deficit
and Comprehensive Income and Expenditure surplus or
deficit on provision of services  57,514  (6,074)  3,932  55,372     
Comparative Year 2023/24    
Management and Members 0 (10) (1) (11)
Children’s Services, Partnerships and Communities 199 (74) (49) 76
Education 22,654 (1,017) 591 22,228
Adult Health and Social Care (Non-Delegated) 713 0 (147) 566
Midlothian Integrated Joint Board 3,155 (206) (122) 2,827
Place 10,267 (331) 214 10,150
Corporate Solutions 1,964 (881) (70) 1,013
Housing Revenue Account 55,608 (11) 0 55,597
Joint Boards 0 0 0 0
Central Costs 74 0 0 74
Non-distributable Costs 0 0 (23) (23)
Net Cost of Services 94,634 (2,530) 393 92,497
Other expenditure from the Expenditure and Funding Analysis (47,211) (9,031) (21) (56,263)
Adjustments between funding and accounting basis 47,423 (11,561) 372 36,234
Application of Service Concessions 0 0 2,608 2,608
Difference between the General Fund surplus or deficit
and Comprehensive Income and Expenditure surplus or
deficit on provision of services  47,423  (11,561)  2,980  38,842 
Adjustments for Capital Purposes
This column adds in depreciation and impairment and revaluation gains and losses in the services line,
and for:
• Other operating expenditure – adjusts for capital disposals with a transfer of income and
disposal of assets and the amounts written off for those assets.
• Financing and investment income and expenditure – the statutory changes for capital financing
i.e. loans fund repayments and other revenue contributions are deducted from other income and
expenditure as these are not chargeable under generally accepted accounting practices.
• Taxation and non-specific grant income and expenditure – Capital grants are adjusted for
income not chargeable under generally accepted accounting practices. Revenue grants are
adjusted from those receivable in the year to those receivable without conditions or for which
Page 354 of 396

Page 355

WWW.MIDLOTHIAN.GOV.UK 
56 Notes to the Accounts
conditions were satisfied throughout the year. The taxation and non-specific grant income and
expenditure line is credited with capital grants receivable in the year without conditions or for
which conditions were satisfied in the year.
Net Change for Pensions Adjustments
Net change for the removal of pension contributions and the addition of IAS 19 Employee Benefits pension
related expenditure and income.
• For services – this represents the removal of the employer pension contributions made by the
Council as allowed by statute and the replacement with the current service costs and past service
costs.
• For financing and investment income and expenditure – the net interest on the defined benefit
liability is charged to the Comprehensive Income and Expenditure Statement.
Other Adjustments
Other adjustments between amounts debited/credited to the Comprehensive Income and Expenditure
Statement and the amounts payable/receivable to be recognised under statute.
• For services – the amount by which officer remuneration charged to the Comprehensive Income
and Expenditure Statement on an accruals basis is different from the remuneration chargeable in
the year in accordance with statutory requirements.
• For financing and investment income and expenditure – this is the effective interest adjustment
on the Council’s Lender Option/Borrower Option (LOBO) debt.
7. Adjustments between Accounting Basis and Funding Basis under
regulations
This note details the adjustments that are made to the total comprehensive income and expenditure
recognised by the Council in the year in accordance with proper accounting practice to arrive at the
resources that are specified by statutory provisions as being available to the Council to meet future capital
and revenue expenditure. The following sets out a description of the reserves that the adjustments are
made against.
General Fund Balance
The General Fund is the statutory fund into which all the receipts of the Council are required to be paid and
out of which all liabilities of the Council are to be met, except to the extent that statutory rules might
provide otherwise. These rules can also specify the financial year in which liabilities and payments should
impact on the General Fund balance, which is not necessarily in accordance with proper accounting
practice. The General Fund balance therefore summarises the resources that the Council is statutorily
empowered to spend on its services or on capital investment (or the deficit of resources that the Council
is required to recover) at the end of the financial year.
Housing Revenue Account Balance
The HRA balance reflects the statutory obligation to maintain a revenue account for local authority council
housing provision in accordance with Part VI of the Local Government and Housing Act 1989. It contains
the balance of income and expenditure as defined by the 1989 Act that is available to fund future
expenditure in connection with the Council’s landlord function or (where in deficit) that is required to be
recovered from tenants in future years.
Capital Fund and Repairs and Renewals Fund
The Capital Fund and the Repairs and Renewals Fund are reserves to hold funds for major capital
developments and specific types of repairs and maintenance work, respectively.  Whilst these funds are
Page 355 of 396

Page 356

WWW.MIDLOTHIAN.GOV.UK 
57 Notes to the Accounts
classed as useable reserves, they are not subject to adjustments between the funding and accounting
basis.
Adjustments between Funding & Accounting Basis 
Current Year 2024/25
General
Fund
Reserve
£000
Housing
Revenue
Account
£000
Total
Usable
Reserves 
£000
Total
Unusable
Reserves 
£000
Adjustments to Revenue Resources    
Amounts by which income and expenditure included in the
Comprehensive Income and Expenditure Statement are
different from revenue for the year calculated in accordance
with statutory requirements:    
• Pensions Costs (transferred to/from pensions reserve) 6,043 31 6,074 (6,074)
• Financial Instruments (transferred to the Financial
Instruments Adjustment Account)  12  0  12  (12)
• Holiday Pay (transferred to the Accumulated Absence
Account)  (1,149)  0  (1,149)  1,149
• Reversal of entries included in the surplus or deficit on the
provision of services in relation to capital expenditure (these
items are charged to the Capital Adjustment Account)  (36,682)  (63,764)  (100,446)  100,446
Total adjustments to Revenue Resources (31,776) (63,733) (95,509) 95,509
Adjustments between Revenue and Capital Resources    
Statutory provision for the repayment of debt  (transfer from the
Capital Adjustment Account)  7,655  7,047  14,702  (14,702)
Total adjustments between revenue and capital resources 7,655 7,047 14,702 (14,702)
Adjustments to Capital Resources    
Application of capital grants to finance capital expenditure 28,231 0 28,231 (28,231)
Total Adjustments to Capital Resources 28,231 0 28,231 (28,231)
Total adjustments between accounting and funding basis 4,110 (56,686) (52,576) 52,576
Application of Service Concessions (2,796) 0 (2,796) 2,796
Total Adjustments 1,314 (56,686) (55,372) 55,372 
Comparative Year 2023/24
General
Fund
Reserve
£000
Housing
Revenue
Account
£000
Total
Usable
Reserves 
£000
Total
Unusable
Reserves 
£000
Adjustments to Revenue Resources    
Amounts by which income and expenditure included in the
Comprehensive Income and Expenditure Statement are
different from revenue for the year calculated in accordance
with statutory requirements:    
• Pensions Costs (transferred to/from pensions reserve) 11,495 66 11,561 (11,561)
• Financial Instruments (transferred to the Financial
Instruments Adjustment Account)  22  0  22  (22)
• Holiday Pay (transferred to the Accumulated Absence
Account)  (393)  0  (393)  393
• Reversal of entries included in the surplus or deficit on the
provision of services in relation to capital expenditure (these
items are charged to the Capital Adjustment Account)  (38,558)  (55,608)  (94,166)  94,166
Total adjustments to Revenue Resources (27,434) (55,542) (82,976) 82,976
Adjustments between Revenue and Capital Resources    
Statutory provision for the repayment of debt  (transfer from the
Capital Adjustment Account)  8,967  4,221  13,188  (13,188)
Total adjustments between revenue and capital resources 8,967 4,221 13,188 (13,188)
Adjustments to Capital Resources    
Application of capital grants to finance capital expenditure 33,554 0 33,554 (33,554)
Total Adjustments to Capital Resources 33,554 0 33,554 (33,554)
Total adjustments between accounting and funding basis 15,087 (51,321) (36,234) 36,234
Application of Service Concessions (2,608) 0 (2,608) 2,608
Total Adjustments 12,479 (51,321) (38,842) 38,842 
Page 356 of 396

Page 357

WWW.MIDLOTHIAN.GOV.UK 
58 Notes to the Accounts
8. Movement in Earmarked Reserves
This note sets out the amounts set aside from the General Fund in earmarked reserves to provide financing
for future expenditure plans and the amounts posted back from earmarked reserves to meet general fund
expenditure in 2024/25. 
Balance
at 1
April
2023 
Transfers
out
2023/24 
Transfers
in
2023/24
Balance
at 31
March
2024 
Transfers
out
2024/25 
Transfers
in
2024/25
Balance
at 31
March
2025 
£000 £000 £000 £000 £000 £000 £000
Scheme of Devolved Budget
Management carry forwards  (16,012)  16,012  (15,335)  (15,335)  15,335  (11,035)  (11,035) 
Loans Fund Review      0  3,373  (5,525)  (2,152)
Transformation Blueprint (1,069) 433 (2,000) (2,636) 1,132 0 (1,504)
Set aside to balance budget (1,166) 1,166 (2,680) (2,680) 2,680 (163) (163)
Total Earmarked Reserves (18,247) 17,611 (20,015) (20,651) 22,520 (16,723) (14,854)
Vat claim not yet settled (6,839) 6,839 0 0 0 0 0
Service Concessions 0 4,093 (20,463) (16,370) 5,603 0 (10,767)
Non-earmarked reserves (9,877) 0 560 (9,317) 2,909 0 (6,408)
Total General Fund Balance (34,963) 28,543 (39,919) (46,338) 31,032 (16,723) (32,029) 
9. Other Operating Income and Expenditure 
2023/24  2024/25
£000 Other Operating Income and Expenditure £000
(70) (Gains)/Losses on disposal of non-current assets 45
(70) Total 45 
10. Financing and Investment Income and Expenditure 
2023/24  2024/25
£000 Financing Investment Income and Expenditure £000
16,244 Interest payable and similar charges 21,470
(9,031) Net interest on the net defined benefit liability/(asset) (8,880)
(7,182) Interest receivable and similar income (5,124)
31 Total 7,466 
11. Taxation and Non-specific Grant Income and Expenditure 
2023/24  2024/25
£000 Taxation and Non-specific Grant Income and Expenditure £000
(57,306) Council tax income (58,294)
(35,136) Non-domestic rates income (34,867)
(163,620) Non-ringfenced government grants (195,021)
(33,554) Capital grants and contributions (note 12) (28,231)
(289,616) Total (316,413) 
Page 357 of 396

Page 358

WWW.MIDLOTHIAN.GOV.UK 
59 Notes to the Accounts
12. Grant Income
The Council credited the following grants, contributions and donations to the Comprehensive Income and
Expenditure Statement in 2024/25. 
2023/24  2024/25
£000 Grant Income £000 
Credited to Taxation and Non-specific Grant Income and
Expenditure 
(7,453) General Capital Grant (7,708)
(6,135) Affordable Housing Supply Programme (8,470)
(10,167) Developer Contributions (2,592)
(3,918) General Capital Grant – Early Years Childcare (2,517)
(2,060) Capital Fund Contribution 0
(2,686) Other Scottish Government Grants (5,357)
(501) Net-Zero Funding (818)
(184) Other Capital Grants and Contributions (769)
(33,554) Total (28,231) 
Credited to Services 
(16,786) Housing Benefit Subsidy (17,065)
(11,569) Early Years Expansion Grant 0
(6,913) LCITP Low Carbon Heating 0
(2,696) Unitary Charge Funding (2,677)
(2,424) Pupil Equity Funding (2,436)
(374) Unaccompanied Asylum Seeking Children (463)
(1,663) Community Justice Grant (1,390)
(1,079) Energy Efficient Scotland (498)
(627) McMillan Funding for Improving Cancer Journey (461)
(929) UK Shared Prosperity Fund (2,717)
(608) Child Protection Grant (715)
(457) Ukrainian Programme (937)
(497) Scottish Government Attainment Programme (618)
(526) Penicuik Townscape Heritage Project (527)
(2,759) Other Grants Received (2,723)
(49,907) Total (33,227) 
Page 358 of 396

Page 359

WWW.MIDLOTHIAN.GOV.UK 
60 Notes to the Accounts
13. Expenditure and Income Analysed by Nature
The Group and Council’s expenditure and income, which includes adjustments between the funding and
accounting basis, is analysed as follows:
2023/24  2024/25
£000 Expenditure and income analysed by nature £000 
Expenditure 
192,380 Employee expenses 207,799
260,356 Other service expenses 281,419
94,560 Depreciation, amortisation and impairment 100,332
16,244 Interest payments 21,470
(70) Gain/(Loss) on disposal on non-current assets 45
6,241 Share of operating results of associates and joint ventures 30
569,711 Total Expenditure 611,095 
Income 
(97,665) Fees, charges and service income (99,881)
(7,182) Interest and investment income (5,124)
(57,306) Income from council tax (93,161)
(354,401) Government grants and contributions (336,063)
(516,554) Total Income (534,229)
53,157 (Surplus) or deficit on the provision of services 76,866 
Page 359 of 396

Page 360

WWW.MIDLOTHIAN.GOV.UK 
61 Notes to the Accounts
14. Property, Plant and Equipment
Movements on Balance 
Movements in 2024/25
Council
Dwellings
Buildings
Land
Vehicles, Plant
and Equipment
Community
Assets
Assets Under
Construction
Surplus Assets
Total property,
plant &
Equipment 
Service
Concession 
Assets*
Cost of Valuation £000 £000 £000 £000 £000 £000 £000 £000  £000
Balance at 1 April 2024 518,018 573,575 17,297 54,508 8,868 73,297 952 1,246,515  195,300
Additions 12,830 1,911 28 10,734 374 66,331 0 92,208  0
Revaluation increases/(decreases) recognised in the Revaluation Reserve (9,292) 2,630 2,216 0 (1,007) 0 (3,137) (8,590)  4,980
Revaluation increases/(decreases) recognised in the Surplus/Deficit on the Provision of
Services
(73,926) (2,792) 29 (42) 435 0 411 (75,885)  (522)
De-recognition – Disposals (269) 0 (5) (1,528) (24) 0 0 (1,826)  0
Reclassification of Assets 24,835 35,135 97 2,979 0 (70,704) 2,793 (4,865)  0
Other Movements* 114 1,279 0 502 0 0 0 1,895  0
Balance at 31 March 2025 472,310 611,738 19,662 67,153 8,646 68,924 1,019 1,249,452  199,758
Accumulated Depreciation and Impairment          
Balance at 1 April 2024 (22,961) (16,355) 0 (36,165) (54) 0 0 (75,535)  (3,197)
Depreciation Charge (12,199) (30,472) 0 (4,624) (23) 0 (4) (47,322)  (3,154)
Depreciation written out to the Revaluation Reserve 11,318 15,493 0 0 70 0 0 26,881  666
Depreciation written out to the Surplus/Deficit on the Provision of Services 22,986 3,559 0 0 1 0 0 26,546  3,331
De-recognition – Disposals 269 0 0 1,439 0 0 0 1,708  0
Reclassification of Assets 23 (23) 0 0 0 0 0 0  0
Balance at 31 March 2025 (564) (27,798) 0 (39,350) (6) 0 (4) (67,722)  (2,354)
Net Book Value          
At 31 March 2025 471,746 583,940 19,662 27,803 8,640 68,924 1,015 1,181,730  197,404
At 31 March 2024 495,057 557,220 17,297 18,343 8,814 73,297 952 1,170,980  192,103
*Service concession assets included in ‘land and buildings ‘total. Adoption of right-of-use assets, under IFRS 16, are included in the other movements line of the note. 
Page 360 of 396

Page 361

WWW.MIDLOTHIAN.GOV.UK 
62 Notes to the Accounts 
Movements in 2023/24
Council
Dwellings
Buildings
Land
Vehicles, Plant
and Equipment
Community
Assets
Assets Under
Construction
Surplus Assets
Total property,
plant &
Equipment 
Service
Concession 
Assets*
Cost of Valuation £000 £000 £000 £000 £000 £000 £000 £000  £000
Balance at 1 April 2023 512,802 576,158 17,380 49,490 8,832 50,386 827 1,215,878  198,022
Additions 20,495 3,822 0 6,253 138 59,977 0 90,685  2
Revaluation increases/(decreases) recognised in the Revaluation Reserve (5,105) (8,449) 58 0 (102) 0 0 (13,598)  (2,724)
Revaluation increases/(decreases) recognised in the Surplus/Deficit on the Provision of
Services  (43,868)  (767)  (1)  0  0  0  0  (44,636)   0
De-recognition – Disposals (251) (100) (12) (1,235) 0 0 0 (1,598)  0
Reclassification of Assets 33,942 2,911 (128) 0 0 (37,066) 125 (216)  0
Balance at 31 March 2024 518,018 573,575 17,297 54,508 8,868 73,297 952 1,246,515  195,300
Accumulated Depreciation and Impairment          
Balance at 1 April 2023 (11,472) (15,802) 0 (32,576) (56) 0 0 (59,906)  (2,397)
Depreciation Charge (11,740) (29,730) 0 (4,757) (21) 0 0 (46,248)  (3,161)
Depreciation written out to the Revaluation Reserve 0 28,765 0 0 23 0 0 28,788  2,361
Depreciation written out to the Surplus/Deficit on the Provision of Services 0 412 0 0 0 0 0 412  0
De-recognition – Disposals 251 0 0 1,168 0 0 0 1,419  0
Balance at 31 March 2024 (22,961) (16,355) 0 (36,165) (54) 0 0 (75,535)  (3,197)
Net Book Value          
At 31 March 2024 495,057 557,220 17,297 18,343 8,814 73,297 952 1,170,980  192,103
At 31 March 2023 501,333 560,356 17,380 16,914 8,776 50,386 827 1,155,972  195,625
*Service concession assets included in ‘land and buildings ‘total 
Page 361 of 396

Page 362

WWW.MIDLOTHIAN.GOV.UK 
63 Notes to the Accounts
Depreciation
The following useful lives are used in the calculation of depreciation for the categories of assets, except
where the useful like is known to be different from these as a consequence of a Council decision:
• Council Dwellings – 40 to 60 years;
• Buildings – 10 to 60 years;
• Vehicles, Plant and Equipment – 5 to 10 years.
Capital Commitments
At 31 March 2025, the Council has entered into a number of contracts for the construction or enhancement
of property, plant and equipment in 2024/25. The major commitments are : 
Original
Contractual
Commitment 
Outstanding at
31 March 25
Capital Commitments £000 £000
Housing Revenue Account (HRA)  
Phase 3-5 New Social Housing – Site 32/34 Newbyres Crescent 17,532 8,868
Phase 3-5 New Social Housing – Site 130 Morris Road (Newbattle HS) 25,038 7,748
Phase 3-5 New Social Housing – Danderhall AA2/AA3 (Bellway) 7,383 1,546
Phase 3-5 New Social Housing – Dalhousie Mains  9,715 910
Phase 3-5 New Social Housing – Roslin Expansion Site 8,237 2,555
Phase 3-5 New Social Housing – Conifer Road 15,147 227
Phase 3-5 New Social Housing – Newmills Road 19,600 144
Phase 3-5 New Social Housing – Newton Church Road 7,039 7,039
Energy Efficiency in Social Housing 2,590 993   
General Fund  
Destination Hillend 7,820 596
Easthouses Primary School 19,801 355
Woodburn Primary School 11,596 121
Other General Fund capital commitments 105 15   
Joint-funded Project  
Phase 3-5 New Social Housing – Site 114 23,940 11,113
Total Contractual Commitment 175,543 42,230 
Revaluations 
Valuations of the above categories of assets are undertaken by independent expert valuers engaged by the
Council over a five-year rolling programme by Chartered Surveyors of the Council’s Estates department,
in accordance with the Statement of Asset Valuation Practice and Guidance Notes of the Royal Institution
of Chartered Surveyors. 
In 2024/25 valuations were undertaken for categories Housing stock, parks & open spaces, garages &
garage sites. Several schools and depots were also revalued. The majority of asset valuations were based
on either a depreciated replacement cost (DRC) basis or market value and resulted in a net downwards
revaluation of assets of £28.266 million.
In addition to formal valuations of property, plant and equipment on a rolling basis over a five year period,
the Council assesses all assets to ensure there are no material changes that should drive an earlier
valuation, to ensure that, in line with the CIPFA code, assets are revalued with sufficient regularity to
ensure that the carrying amount does not differ materially from that which would be determined using the
current value at the end of the reporting period. The Council has continued to assess the valuation of its
asset base subsequent to the financial year end as summarised in note 4 to these financial statements.
Page 362 of 396

Page 363

WWW.MIDLOTHIAN.GOV.UK 
64 Notes to the Accounts
15. Infrastructure Assets
The Council’s infrastructure assets have been recorded on the Balance Sheet at depreciated historic cost.
A useful life of 15 years is applied to these assets and used in the calculation of the annual depreciation
charge, based on the Council’s assessment of the average useful economic life of these assets, with the
exception of where the useful life is known to be different from this amount as a consequence of a Council
decision. 
On 29 August 2022, the Scottish Government confirmed in Local Government Finance Circular 09/2022
that it has provided a temporary statutory override to the accounting and disclosure requirements related
to infrastructure assets in local government financial statements, whilst more permanent updates are
developed within the CIPFA/LASAAC Code of Practice for Local Authority Accounting (“the Code”). The
allowed changes are applicable for the 2021/22 financial year through to the 31 March 2025 financial year.
The Council has applied both statutory overrides for infrastructure assets:
• Statutory Override 1: For accounting periods commencing from 1 April 2021 until 31 March 2025 a
local authority is not required to report the gross cost and accumulated depreciation for
infrastructure assets.
• Statutory Override 2: For accounting periods commencing from 1 April 2010 until 31 March 2025
the carrying amount to be derecognised in respect of a replaced part of an infrastructure asset is
to be taken to be and accounted for as zero. No subsequent adjustment shall be made to the
carrying amount of the asset with respect to that part.
2023/24
£000  Infrastructure Assets
2024/25
£000
34,819 Balance at 1 April  38,423
(3,956) Depreciation (2,222)
7,560 Additions 9,279
0 Reclassification of Assets and other movements 6,914
38,423 Balance at 31 March 52,394 
16. Heritage Assets
The Council’s chains and badges of office are the main heritage assets and have been included in the
Balance Sheet at reinstatement cost, obtained from the Council’s insurer.
2023/24
£000  Heritage Assets
2024/25
£000
458 Balance at 1 April  456
(2) Depreciation (3)
0 Additions 1
0 Revaluations and restatements 53
456 Balance at 31 March 507 
17. Intangible Assets
The Council accounts for its software as intangible assets, to the extent that the software is not an integral
part of a particular IT system and accounted for as part of the hardware item Property, Plant and
Equipment. The intangible assets include software licences, warranties and internally generated assets. 
The movement on Intangible Asset balances during the year is as follows: 
Page 363 of 396

Page 364

WWW.MIDLOTHIAN.GOV.UK 
65 Notes to the Accounts
2023/24
£000  Intangible Assets
2024/25
£000 
Balance at 1 April  
2,946 Gross carrying amounts 2,972
(2,744) Accumulated amortisation (2,868)
202 Net carrying amount at start of year 104
26 Additions – Purchases 498
(124) Amortisation for the period (50)
104 Net carrying amount at end of year 448   
Comprising 
2,972 Gross carrying amounts 3,366
(2,868) Accumulated amortisation (2,918)
104 Net carrying amount at end of year 448 
18. Long-term Debtors 
2023/24
£000  Long-term Debtors
2024/25
£000
4,113 Prepayment to PPP contractor 3,756
58 Pacific Shelf 0
4,171 Total 3,756 
19. Financial Instruments
Categories of Financial Instruments
The following categories of financial instruments are carried in the Balance Sheet.
Financial Assets 
31 Mar
2024    
31 Mar
2025 
Long-
term  Current  Total  
Long-
term  Current  Total
£000 £000 £000 Financial Assets Category £000 £000 £000
0 30,017 30,017 Short/long-term deposits (below) Amortised Cost 0 70 70
0 22,878 22,878 Debtors (note 23) Amortised Cost 0 19,158 19,158 
11,526  0  11,526  Long-term investments (below)
Fair value through
other
comprehensive
income  16,604  0  16,604
11,526 52,895 64,421 Total Financial Assets  16,604 19,228 35,832 
0 15,236  15,236
Debtors not defined as financial
instruments   0  3,875  3,875
11,526 68,131 79,657 Total  16,604 23,103 39,707 
Page 364 of 396

Page 365

WWW.MIDLOTHIAN.GOV.UK 
66 Notes to the Accounts
The short and long-term deposits on the balance sheet comprises: 
31 Mar
2024   
31 Mar
2025 
Long-
term  Current  Total 
Long-
term  Current  Total
£000 £000 £000 Deposits £000 £000 £000
0 30,017 30,017 Commercial banks/building societies 0 70 70
0 30,017 30,017 Total  0 70 70 
Financial Liabilities 
31 Mar
2024    
31 Mar
2025 
Long-
term  Current  Total  
Long-
term  Current  Total
£000 £000 £000 Financial Liabilities Category £000 £000 £000
339,971 3,797 343,768 Borrowings (below) Amortised Cost 377,696 5,015 382,711
73,347 3,352 76,699 PPP Liability  (note 33) Amortised Cost 70,722 3,602 74,324 
11,471  568  12,039
PPP Donated Asset Liability (note
33)  Amortised Cost  10,893  573  11,466
0 0 0 IFRS 16 – Leases  Amortised Cost 1,382 352 1,734
0 33,331 33,331 Creditors (note 25) Amortised Cost 0 24,398 24,398
424,789 41,048 465,837 Total   460,693 33,940 494,633 
0 17,629  17,629
Creditors not defined as financial
instruments   0  29,637  29,637
424,789 58,677 483,466 Total   460,693 63,577 524,270 
The Council’s borrowing is presented in the Balance Sheet as the outstanding principal repayable (plus
accrued interest) and interest charged to the Comprehensive Income and Expenditure Statement is the
amount payable for the year according to the loan agreement. Borrowing is classed as either a long-term
liability, repayable after twelve months or longer, or a current liability if it is repayable within twelve months.
The external borrowing as shown in the Balance Sheet comprises: 
31 Mar
2024   
31 Mar
2025 
Long-
term  Current  Total 
Long-
term  Current  Total
£000 £000 £000 Borrowing £000 £000 £000
303,897 2,630 306,527 Public Works Loan Board (PWLB) Loans 342,316 3,911 346,227
20,526 286 20,812 Lender Option/Borrower Option (LOBO) Loans 20,514 289 20,803 
15,548  881  16,429
Loans from commercial banks and other local
authorities  14,866  815  15,681
339,971 3,797 343,768 Total 377,696 5,015 382,711 
Loans Fund Deferral of Repayments
Loans Fund Principal repayments were deferred in 2022/23 under the Local Government Finance Circular
5/2022 provisions. The term over which deferred repayments will be repaid are in line with the provisions
of the circular, as follows:-
Deferred Principal Repayments – Loans Fund £000
Within 1 year 241
Within 2 to 5 years 770
Within 6 to 10 years 602
Within 11 to 15 years 317
Within 16 to 20 years 207
Total 2,137 
Page 365 of 396

Page 366

WWW.MIDLOTHIAN.GOV.UK 
67 Notes to the Accounts
Investments Designated at Fair Value through Other Comprehensive Income
Fair value of equity instruments designated at Fair Value through Other Comprehensive Income include
the following: 
31 Mar
2024
£000  Long-term Assets
Input Level in
Fair Value
Hierarchy (see
note 1 viii) 
31 Mar
2025
£000
5,594 Equity Shareholding in Lothian Buses Level 2 6,082
324 Subordinated Debt Subscription in Newbattle DBFMCo Level 3 322
5,610 Midlothian Energy Shareholding Level 3 10,200
11,528 Total  16,604 
Lothian Buses Plc
Midlothian Council holds a 5.5% shareholding in Lothian Buses plc, a company incorporated in January
1986 under the terms of the Transport Act 1985 to operate buses in the City of Edinburgh and its
surrounding area.
The valuation basis for the Council’s shareholding (350,000 £1 ordinary shares) is calculated as net share
of equity attributable to equity holders, in line with the published results for the year ended 31 December
2024. The IAS 19 Pension Asset/Liability has now been removed from calculations due to its volatility, as
demonstrated in the on-year movement in the transfer to/from reserves figure in the table below. Note 37
provides more detail on the potential guarantee liability associated with investment.
Year to 31 Dec 23  Year to 31 Dec 24
£000 Lothian Buses £000 
Profit/Loss: 
16,760 Profit/(Loss) before taxation  5,774
(2,178) Taxation (2,470)
14,582 Profit/(Loss) after Tax 3,304 
Other relevant Financial Information: 
183,508 Revenue 197,749
3,200 Ordinary Dividend 0
25,841 Transfer to/(from) reserves (9,819)
102,266 Equity attributable to equity holders (excluding IAS 19 Pension Asset/Liability) 111,195 
Newbattle DBFMCo
In 2017/18, the Council subscribed £0.333 million of subordinated debt in Newbattle DBFMco Limited, a
company set up specifically to deliver the Council’s Schools Newbattle Community Campus project.
Whilst the investment is sellable in the secondary market, the valuation basis for the Council’s
shareholding (nominal value of loan stock £0.333 million) is calculated based on the subscription value as
there is no equivalent market data to estimate resale value.
The principal on this investment will be repaid fully over the 25-year project life. Interest will be paid
biannually at 10.5% coupon based on the average principal outstanding over the relevant 6-month period.
Midlothian Energy Ltd
In 2021/22, the Council entered into a 50:50 joint venture with Vattenfall Heat UK to create Midlothian
Energy Limited, a company set up specifically to generate, distribute and supply energy within Midlothian.
The carrying value of the Council investment in Midlothian Energy Limited represents the funds invested in
2022. The published results for Midlothian Energy Limited for the year ended 31 December 2024 are
summarised below. 
Page 366 of 396

Page 367

WWW.MIDLOTHIAN.GOV.UK 
68 Notes to the Accounts
Year to 31 Dec 23  Year to 31 Dec 24
£000 Midlothian Energy Ltd £000 
Profit/Loss: 
48 Profit/(Loss) before taxation  (347)
(41) Taxation 1
7 Profit/(Loss) after Tax (346) 
Other relevant Financial Information: 
11,220 Shares issued during the period 20,400
(2,758) Accumulated Losses (3,104)
8,462 Total Equity 17,296 
Income, Expenses, Gains and Losses  
2023/24  2024/25
Income, Expenses, Gains and Losses Surplus or
deficit on
the
provision of
services
£000 
Other
comprehensive
income and
expenditure
£000
Surplus or
deficit on
the
provision of
services
£000 
Other
comprehensive
income and
expenditure
£000
Net gains/losses on:    
• Investments in equity instruments designated at
fair value through other comprehensive income  0  (165)   488
Total net gains/(losses) 0 (165)  488     
Interest revenue:    
• Financial assets measured at amortised cost 4,590 0 2,438 0
Total Interest Revenue 4,590 0 2,438 0     
Interest Expense 9,752 0 11,460 
Fee Expense:    
• Financial assets or financial liabilities that are not
at fair value through profit and loss  167  0  153  0
Total Fee Expense 167 0 153 0 
Fair Value of Financial Assets and Liabilities
Except for the financial assets carried at fair value through other comprehensive income, all other financial
liabilities and financial assets held by the Council are carried in the Balance Sheet at amortised cost. The
fair values calculated for these instruments are as follows: 
31 Mar 2024   31 Mar 2025
Carrying
Amount
£000 
Fair Value
£000 
`
Financial Liabilities
Carrying
Amount
£000 
Fair Value
£000
306,526 209,199 PWLB Loans (Level 2) 346,227 231,469 
20,812  18,666
Lender Option/Borrower Option (LOBO)
Loans (Level 2)
20,803 16,818 
16,430  13,469
Loans from commercial lenders and
other local authorities (Level 2)
15,681 12,226
33,331 33,331 Creditors 24,398 24,398
0 0 IFRS 16 – Lease Liabilities 1,734 1,734
76,699 76,699 PPP Finance Lease Liability  74,324 74,324
12,039 12,039 PPP Donated Asset Account Liability 11,466 11,466
465,837 363,403 Total  494,633 372,435 
The fair value for borrowings have been arrived at using a discounted cash flow analysis, with the most
significant inputs being the discount rate. 
The fair value of borrowing is lower than the carrying amount because the Council’s portfolio of loans
includes a number of loans where the interest rate payable is lower than the prevailing rates at the balance
Page 367 of 396

Page 368

WWW.MIDLOTHIAN.GOV.UK 
69 Notes to the Accounts
sheet date. The commitment to pay interest below current market rates reduces the amount the Council
would have to pay if the lender requested or agreed to early repayment of the loans. 
31 Mar 2024   31 Mar 2025
Carrying
Amount
£000 
Fair Value
£000 
`
Financial Assets
Carrying
Amount
£000 
Fair Value
£000
30,017 30,017 Short/long-term Deposits 70 70
22,878 22,878 Debtors 19,158 19,158
52,895 52,895 Total  19,228 19,228 
Short-term debtors and creditors are carried at cost as this is a fair approximation of their value.
The fair value for financial liabilities and financial assets that are not measured at fair value can be
assessed by calculating the present value of the cash flows that will take place over the remaining term of
the instruments, using the following assumptions:
Financial Assets Financial Liabilities
- The valuation of fixed term deposits (maturity deposits) is
made by comparison of the fixed term deposit with a
comparable deposit with the same/similar lender for the
remaining period of the deposit.
- No early repayment is recognised.
- The fair value of receivables is taken to be the invoiced or
billed amount.
- Estimated ranges of interest rates at 31 March 2025 for
loans payable based on new lending rates for equivalent
loans at that date. 
- The fair value of payables is taken to be the invoiced or
billed amount. 
20. Nature and Extent of Risks arising from Financial Instruments
The Council’s activities expose it to a variety of financial risks including:
• Credit risk – the possibility that other parties might fail to pay amounts due to the Council;
• Liquidity risk – the possibility that the Council might not have funds available to meet its
commitments to make payments;
• Market risk – the possibility that financial loss might arise for the Council as a result of the
changes in such measures as interest rates and stock market movements.
The Council has fully adopted CIPFA’s Code of Treasury Management in the Public Services Code of
Practice and set treasury management indicators to control key financial instrument risks in accordance
with CIPFA’s Prudential Code.
The Council’s management of treasury risks actively works to minimise the Council’s exposure to the
unpredictability of financial markets and to protect the financial resources available to fund services.
Credit Risk
Credit risk arises from deposits with banks and financial institutions, as well as credit exposures to the
Council’s customers. 
The risk is minimised through the Council’s Treasury Management Strategy, which is set annually and is
monitored throughout the year. The strategy sets out the limits on both duration and maximum levels of
deposits. The lower an institution’s creditworthiness the lower the maximum duration and level of deposit
will be. These Counterparties are chosen, by officers, using credit data supplied by the Council’s treasury
advisers (based on data from the three main credit rating agencies, overlaid by:
• Credit watches and credit outlooks from credit rating agencies;
• Credit Default Swap (CDS) spreads to give early warning of likely changes in credit ratings;
Page 368 of 396

Page 369

WWW.MIDLOTHIAN.GOV.UK 
70 Notes to the Accounts
• Sovereign ratings to select counterparties from only the most creditworthy countries.
It is the policy of the Council to place deposits only with a limited number of banks and building societies
whose credit rating is independently assessed as sufficiently secure by the Council’s treasury advisers and
to restrict lending to a prudent maximum amount for each institution. The Council also has a policy of
limiting deposits to £15 million per institution, other than for UK Nationalised and Part-Nationalised
institutions where the maximum is extended to £30 million. No credit limits were exceeded during the
financial year.
The expected credit loss for the Council’s financial assets held at amortised cost has been calculated to
be £0.001 million (2023/24 £0.010 million). The Council deems this immaterial and therefore has not
included any impact of this with the Comprehensive Income and Expenditure Statement (CIES).
The expected credit loss for the Council’s financial assets held at FVOCI is expected to be zero, calculated
on the following basis:
• Lothian Buses Shareholding – There was no dividend received during 2024/25, 2023/24 was the
first dividend received since 2019; it was previously estimated that dividend would not be received
until 2026;
• Subordinated Debt Investment in Newbattle DBFM Co SPV – Whilst there is no directly
observable indicators which would allow an expected credit loss for this investment to be
accurately calculated, there are no indications of adverse performance with the DBFM Co or any
indications that future scheduled lifecycle maintenance will not be able to take place or senior
and/or subordinated debt will not be able to be repaid. The Council will continue to review the
performance of the SPC on an annual basis;
• Midlothian Energy Ltd – Whilst there is no directly observable indicators which would allow an
expected credit loss for this investment to be accurately calculated, there are no indications of
adverse performance. The Council will continue to review the performance of the company on an
annual basis.
An age analysis of cash and cash equivalents and short-term deposits is shown in the table below:
2023/24 
£000  Financial Assets
2024/25 
£000
27,505 Less than three months 27,018
10,006 Between three and six months 0
20,011 Between six months and one year  0
0 More than one year 0
57,522 Total  27,018
Liquidity Risk
The Council manages its liquidity position through the approval of treasury investment strategy reports and
through a comprehensive cash flow management system as required by CIPFA Code of Practice. This
seeks to ensure that cash is available as needed.
If unexpected movements happen, the Council has ready access to borrowings from the money markets
and the Public Works Loan Board. There is no significant risk that it will be unable to raise finance to meet
its commitments under financial instruments. Instead the risk is that the Council will be bound to replenish
a significant proportion of its borrowings at a time of unfavourable interest rates. The Council sets limits
on the proportion of its fixed rate borrowing during specified periods. The strategy is that loan maturities
are spread across financial years to mitigate refinancing risk, through a combination of careful planning of
new loans taken out and (where it is economic to do so) making early repayments. The maturity analysis of
financial liabilities is as follows: 
Page 369 of 396

Page 370

WWW.MIDLOTHIAN.GOV.UK 
71 Notes to the Accounts 
2023/24
£000  Financial Liabilities
2024/25
£000
3,797 Less than one year 5,015
1,275 Between one and two years 11,771
22,362 Between two and five years 45,387
60,177 Between five and ten years 60,177
42,582 Between ten and twenty years 22,447
41,681 Between twenty and thirty years 61,031
81,887 Between thirty and forty years 81,883
100,000 Between forty and fifty years  90,000
5,000 More than fifty years 5,000
343,768 Total  382,711 
All trade and other payables are due to be paid in less than one year.
Market Risk
Interest Rate Risk
The Council is exposed to interest rate risk in terms of its exposure to interest rate movements on its
borrowings and investments. Movements in interest rates have a complex impact on the Council. For
instance, a rise in interest rates would have the following effects:
The current interest rate risk for the Council is summarised below:
• Borrowings at variable rates - the interest charged to the surplus or deficit on the provision of
services will rise;
• Borrowings at fixed rates – the fair value of the liabilities will fall;
• Deposits at variable rates - the interest income credited to the surplus or deficit on the provision
of services will rise;
• Deposits at fixed rates - the fair value of the assets will fall.
Borrowings are not carried at fair value, so normal gains and losses on fixed rate borrowings would not
impact on the surplus or deficit on the provision of services of other comprehensive income and
expenditure. However, changes in interest payable and receivable on variable rate borrowings and
deposits will be posted to the surplus or deficit on the provision of services and affect the General Fund
balance. 
The Council has a number of strategies for managing interest rate risk. The Council’s policy is to aim to
keep a maximum of 30% of its borrowings in variable rate loans. During periods of falling interest rates, and
where economic circumstances make it favourable, fixed rate loans will be repaid early to limit exposure
to losses.
The treasury management team has an active strategy for assessing interest rate exposure that feeds into
the setting of the annual budget and which is used to update the budget quarterly during the year. This
allows any adverse changes to be accommodated. The analysis will also advise whether new borrowing
taken out is fixed or variable.
According to this assessment strategy, at 31 March 2025, if interest rates had been 1% higher with all other
variables held constant, the financial effect would be: 
Page 370 of 396

Page 371

WWW.MIDLOTHIAN.GOV.UK 
72 Notes to the Accounts
2023/24
£000 
2024/25
£000 
Impact on taxpayer and rent payer: 
0 Increase in interest payable  on variable rate borrowings 0
1,047 Increase in interest receivable on variable rate instruments 485
1,047 Impact on Surplus/Deficit on the Provision of Services 
Other presentational changes: 
(28,791)
Decrease in fair value of fixed rate borrowing liabilities (no impact on the
Surplus/Deficit on the Provision of Services or Other Comprehensive
Income and Expenditure) 
(29,001) 
The impact of a 1% fall in interest rates would be as above but with the movements being reversed.
Price Risk
There is no price risk associated with the Council’s available for sale investments specified in Note 19 of
the Financial Statements.
Foreign Exchange Risk
The Council has no financial assets or liabilities denominated in foreign currencies and thus has no
exposure to loss arising from movements in exchange rates.
21. Assets Held For Sale 
2023/24
£000  Assets Held for Sale
2024/25
£000
1,080 Balance at 1 April  1,690
216 Assets newly qualified as held for sale 0
394 Revaluations and restatements (425)
0 Assets sold (455)
1,690 Balance at 31 March 810 
22. Inventories 
2023/24
£000  Inventories
2024/25
£000
1,023 Balance at 1 April  972
973 Purchases 1,027
(1,024) Recognised as an expense in the year (1,014)
972 Balance at 31 March 985 
23. Debtors 
2023/24
£000  Current Debtors
2024/25
£000
7,096 Central Government Bodies 11,909
5,293 Other Public Sector Bodies 2,227 
Other entities and individuals (net of impairment for bad debts*): 
12,777 • Council Tax and Non-domestic rates 117
3,608 • Rents 3,659
9,340 • Other debtors 5,121
38,114 Total  23,033 
Page 371 of 396

Page 372

WWW.MIDLOTHIAN.GOV.UK 
73 Notes to the Accounts
* For impairment, significant individual balances are considered before a collective impairment of all
remaining debtors based on their age profile. Impairment is applied to all outstanding debt at the balance
sheet date for Council Tax and Non-Domestic Rates of £46.826 million (2023/24 £44.466 million) and Rents
of £4.100 million (2023/24 £3.380 million). For sundry debtors, all debts that are over six months past their
payment date impairment will be applied of £0.843 million (2023/24 £2.689 million), of which £1.765
million relates to housing benefit overpayments (2023/24 £1,761 million).
24. Cash and Cash Equivalents
The balance of cash and cash equivalents is made up of the following elements:
2023/24
£000  Cash and Cash Equivalents
2024/25
£000
441 Cash held by the Council 478
26,793 Short-term Deposits 26,414
271 Bank current accounts (14)
27,505 Total  26,878 
25. Creditors 
2023/24
£000  Creditors
2024/25
£000
311 Central government bodies 71
2,199 Other public sector bodies 2,592
48,450 Other entities and individuals 50,799
50,960 Total  54,035 
26. Provisions 
Uninsured
Losses (1)  Total 
£000 £000
Balance at 1 April 2024 1,294 1,294
New provisions made during the year 760 760
Increase/(decrease) to existing insurance provisions during the year 122 122
Amounts used during the year (1,171) (1,171)
Balance at 31 March 2025 1,005 1,005 
Notes:
1. This relates to potential uninsured losses arising from insurance claims made against the Council.
27. Grants Received in Advance
The Council has received a number of grants and contributions that have yet to be recognised as income
as they have conditions attached to them that will require the monies to be returned to the grantor. The
balances at year-end are as follows:
2023/24
£000  Grants Received in Advance
2024/25
£000
44,731 Balance at 1 April  40,821 
New capital grants received , conditions of use not yet met: 
366 Scottish Government Place Based Investment Fund 30
8,327 Section 75 contributions from private developers 11,248
25 Other grants received in advance 0
8,718 Balance at 31 March 11,278
(12,628) Amounts released to CIES, conditions of use met (6,044)
40,821 Balance at 31 March 46,055
Page 372 of 396

Page 373

WWW.MIDLOTHIAN.GOV.UK 
74 Notes to the Accounts
28. Usable Reserves
Movements in the Council’s usable reserves are detailed in the Movement in Reserves Statement.
29. Unusable Reserves 
2023/24  2024/25
£000 Unusable Reserves £000
(319,859) Revaluation Reserve (319,151)
(5,243) Financial Instruments Revaluation Reserve (5,732)
(386,625) Capital Adjustment Account (341,521)
1,310 Financial Instruments Adjustment Account 1,143
7,612 Pensions Reserve 6,433
8,995 Accumulated Absences Account 10,144
(693,810) Total  (648,684) 
Revaluation Reserve
The Revaluation Reserve contains the gains made by the Council arising from increases in the value of its
Property, Plant and Equipment and Intangible Assets. The balance is reduced when assets with
accumulated gains are:
• Revalued downwards or impaired and the gains are lost;
• Used in the provision of services and the gains are consumed through depreciation; or
• Disposed of and the gains are realised.
The reserve contains only revaluation gains accumulated since 1st April 2007, the date the reserve was
created. Accumulated gains arising before that date are consolidated into the balance on the Capital
Adjustment Account.
2023/24  2024/25
£000 Revaluation Reserve £000
(325,527) Balance at 1 April (319,859)   
(16,939) (Surplus) or deficit on revaluation of non-current assets not posted to the
surplus or deficit on the provision of services 
(22,748)
22,502 Difference between fair value depreciation and historical cost
depreciation
23,276   
Amounts written off to the Capital Adjustment Account 
105 Accumulated (gains)/losses on assets sold or scrapped  180
105 Amount written off to the Capital Adjustment Account 180
(319,859) Balance at 31 March (319,151) 
Financial Instruments Revaluation Reserve
The Financial Instruments Revaluation Reserve contains the gains made(319,151) by the Council arising
from increases in the value of its investments that at measured at fair value through other comprehensive
income. The balance is reduced when investments with accumulated gains are:
• Revalued downwards and the gains are lost;
• Disposed of and the gains are realised.
2023/24  2024/25
£000 Financial Instruments Revaluation Reserve £000
(5,408) Balance at 1 April (5,243)
163 (Upward)/Downward Revaluation of Investments (489)
(5,243) Balance at 31 March (5,732) 
Page 373 of 396

Page 374

WWW.MIDLOTHIAN.GOV.UK 
75 Notes to the Accounts
Capital Adjustment Account
The Capital Adjustment Account absorbs the timing differences arising from the different arrangements
for accounting for the consumption of non-current assets and for financing the acquisition, construction
or enhancement of those assets under statutory provisions. The account is debited with the cost of
acquisition, construction or subsequent costs such as depreciation, impairment losses and amortisations
are charged to the Comprehensive Income and Expenditure Statement. The account is credited with the
amounts set aside by the Council as finance for the costs of acquisition, construction and subsequent
expenditure.
The account contains revaluation gains accumulated on property, plant and equipment before the 1st April
2007, the date that the Revaluation Reserve was created to hold such gains.
Note 7 provides further details of transactions posted to the account, apart from those involving the
revaluation reserve.
2023/24   2024/25
£000 Capital Adjustment Account £000 £000
(435,891) Balance at 1 April  (386,625)
20,463 Opening Balance adjustment – Service concessions  5,526
(415,428) Revised Opening Balance  (381,099) 
Reversal of items relating to capital expenditure debited or credited to
the Comprehensive Income and Expenditure Statement (CIES):  
27,704 • Charges for depreciation and impairment on non-current assets 26,949 
45,580 • Revaluation movements on property, plant and equipment 52,666 
124 • Amortisation of intangible assets 50 
74 • Revenue expenditure funded from capital under statute 69 
179
• Amounts of non-current assets written off on disposal or sale as part
of the gain/loss on disposal to the CIES
573 
73,661   80,307
(105) Adjusting amounts written out of the Revaluation Reserve  (180) 
73,556
Net written out amount of the cost of non-current assets consumed
in the year 
80,127 
Capital financing applied in the year:  
(249) Use of capital receipts to finance new capital expenditure (528) 
(33,554)
Capital grants and contributions credited to the CIES that have been
applied to capital financing  (28,231) 
(11,116)
Statutory provision for the financing of capital investment charged
against the General Fund and HRA balances  (14,701) 
2,608 Application of Service concessions 2,796 
(1,822) Use of Capital Fund reserve to finance Capital Expenditure 528 
(44,133)   (40,136)
(620) Other movements  (413)
(386,625) Balance at 31 March  (341,521) 
Financial Instruments Adjustment Account
The Financial Instruments Adjustment Account absorbs the timing differences arising from the different
arrangements for accounting for income and expenses relating to certain financial instruments and for
bearing losses or benefiting from gains per statutory provisions.
2023/24  2024/25
£000 Financial Instruments Adjustment Account £000
1,491 Balance at 1 April 1,310
(159) Premiums incurred in the year  (155)
(22) Amount by which finance costs charged to the CIES are different from finance
costs chargeable in year in accordance with statutory requirements (12)
1,310 Balance at 31 March 1,143 
Page 374 of 396

Page 375

WWW.MIDLOTHIAN.GOV.UK 
76 Notes to the Accounts
Pensions Reserve
The Pension Reserve absorbs the timing differences arising from the different arrangements for accounting
for post-employment benefits and for funding benefits in accordance with statutory provisions. The
Council accounts for post-employment benefits in the Comprehensive Income and Expenditure
Statement (CIES)  as the benefits earned by employees accruing years of service, updating the liabilities
recognised to reflect inflation, changing assumptions and investment returns on any resources set aside
to meet the costs. However, statutory arrangements require benefits earned to be financed as the Council
makes employers contributions to pension funds or eventually pays any pensions for which it is directly
responsible. The pension reserve mirrors the net pension asset/liability, as detailed in Note 35. 
2023/24  2024/25
£000 Pensions Reserve £000
7,800 Balance at 1 April 7,612 
(182,768)
Re-measurements of the net defined benefit
liability/(asset)  (189,245) 
8,453
Reversal of items relating to net changes for
retirement benefits charged to Surplus or Deficit on
the Provision of Services in the CIES  11,042
(20,014) Employers’ pension contributions  (17,117)
194,141 Restriction Adjustment under IFRIC 14 194,141
7,612 Balance at 31 March 6,433 
Accumulated Absences Account
The Accumulated Absences Account absorbs the differences that would otherwise arise on the General
Fund Balance from accruing for compensated absences earned but not taken in the year, e.g. annual leave
entitlement carried forward at 31 March. Statutory arrangements require that the impact on the General
Fund Balance is neutralised by transfers to or from the account.
2023/24   2024/25
£000 Accumulated Absences Account £000 £000
8,602 Balance at 1 April  8,995
(8,602) Settlement or cancellation of accrual made at the end of the preceding year (8,995) 
8,995 Amounts accrued at the end of the current year 10,144 
393
Amount by which officer remuneration charged to the CIES on an accruals basis is
different from remuneration chargeable in the year in accordance with statutory
requirements    1,149
8,995 Balance at 31 March  10,144 
30. External Audit Costs
The estimated fee payable by the Council to Audit Scotland in respect of the work conducted for external
audit services is £0.295 million (2023/24 £0.290) million). Where further additional work is required, fees
will be agreed with management and reported to the Audit Committee.
31. Related Parties
The Council is required to disclose material transactions with related parties - bodies or individuals that
have the potential to control or influence the Council, or to be controlled or influenced by the Council.
Disclosure of these transactions allows readers to assess the extent to which the Council might have been
constrained in its ability to operate independently or might have secured the ability to limit another party’s
ability to bargain freely with the Council. 
The Scottish Government
The Scottish Government has significant influence over the general operations of the Council – it is
responsible for providing the statutory framework within which the Council operates, provides much of its
Page 375 of 396

Page 376

WWW.MIDLOTHIAN.GOV.UK 
77 Notes to the Accounts
funding in the form of grants, and prescribes the terms of many of the transactions that the Council has
with other parties (such as Council Tax bills and Housing Benefits). Further information is contained with
Note 11 Taxation and Non-specific Grant Income and Note 12 Grant Income in the Annual Accounts.
Elected Members
Elected members of the Council have direct control over the Council’s financial and operating policies.
The total of members’ allowances paid in 2024/25 is shown in the Remuneration Report.
Members’ Register of Interests can be viewed on the Council’s website. A review of these interests has
been conducted. Related party interests for which transactions exist in 2024/25 were declared by nine
members:
• With voluntary bodies or charitable organisations that received funding totalling an estimated
value of £0.216 million;
• With businesses or other organisations that have contracted for goods and services with the
Council to the estimated value of £0.738 million.
In addition to the above many members have relationships or hold positions with other public bodies and
voluntary organisations with which the Council does not have a financially material relationship but with
which the Council has a financial or influential relationship.
Officers
There are no related party transactions with officers of the Council.
Other Public Bodies
The Council has a number of joint working arrangements with other local authorities. In 2024/25 payments
of £1.521 million were made to other local authorities and income of £0.710 million was received from
other local authorities.
Midlothian Integration Joint Board
The Council works in partnership with NHS Lothian, providing a range of Health and Social Care services
across Midlothian. NHS Lothian transferred £4.903 million of resource transfer funding to the Council in
2024/25 in respect of activities delegated to the Midlothian Integration Joint Board, as well as an additional
£4.816 million in relation to Social Care Fund, £1.324 million from the Integrated Care Fund. The funding
supports various Adult Social Care services, both purchased and in-house.
NHS Lothian employs the Joint Director of Health and Social Care. Midlothian Council is recharged for 50%
of the cost of this post. Details are included in the Remuneration Report.
The Council delegated resources totalling £69.072 million to the Midlothian Integration Joint Board in
2024/25. These resources were allocated to the Council for the provision of Adult Social Care services.
NHS Lothian also delegated financial resources to the Board. The Board provides the strategic direction in
relation to the delivery of Health and Adult Social Care Services in Midlothian. The Council provides
assistance in kind in terms of Board staff (Chief Officer) and administrative support for the operation of the
Board. In addition no charge is made for central support functions provided over and above the resources
delegated which relate specifically to Adult Social Care. As at 31 March 2025 the Council held £0.007
million on behalf of the Board.
Other Entities Controlled or Significantly Influenced by the Council
During the year, the Council entered into material transactions with the Lothian Valuation Board. This
amounted to £0.613 million (2023/24 £0.562 million). There was no balance due to or from the Lothian
Valuation Board as at 31 March 2025.
Page 376 of 396

Page 377

WWW.MIDLOTHIAN.GOV.UK 
78 Notes to the Accounts
Midlothian Energy Limited was set up in 2021/22 as a 50:50 joint venture with Vattenfall Heat UK to
generate, distribute and supply energy. The company has been consolidated into the Group Accounts and
details of all other entities in which the Council has significant interest are explained in the Group Accounts
in Note 39.
32. Capital Expenditure and Capital Financing
The total amount of capital expenditure incurred in the year is shown in the table below (including the value
of assets acquired under finance leases and PPP contracts), together with the resources that have been
used to finance them.
2023/24  2024/25
£000 Capital Expenditure and Capital Financing £000
431,462 Opening Capital Financing Requirement 505,516
20,463 Opening Balance Adjustment – Service concessions 0
451,925 Revised Opening Capital Financing Requirement 505,516 
Capital Investment: 
20,495 Council Dwellings 12,830
3,3820 Buildings 1,911
0 Land 28
6,253 Vehicles, Plant & Equipment 10,734
138 Community Assets 374
59,977 Assets under Construction 66,331
7,560 Infrastructure Assets 9,279
0 Heritage Assets 1
26 Intangible Assets 395
74 Revenue Expenditure funded by Capital Under Statute 69
2 Public, Private Partnership (PPP) 0
98,345 Total Capital Investment 101,952 
Sources of Finance: 
(60) Capital Receipts (175)
2,608 Application of Service Concessions 2,796
(2,000) Capital Fund Applied 0
(31,494) Government Grants and Other Contributions (28,056)
(400) Donated asset (573)
(13,408) Loans fund and PPP Finance lease repayments (14,122)
0 Closing Balance Adjustment – IFRS 16 PPP Finance Lease Remeasurement 338
(44,754) Total Sources of Finance (39,792)
53,591 Increase/(decrease) in Capital Financing Requirement 62,160
505,516 Closing Capital Financing Requirement 567,676 
The 2023/24 closing capital financing requirement has changed from the figure presented in 2023/24
audited accounts due to a 2023/24 audit adjustment of £0.489 million for a capital accrual against assets
under construction not being reflected in this note in the 2023/24 audited accounts.
33. Leases
The Council’s lease contracts comprise leases of operational land and buildings, plant and equipment
and motor vehicles. Most are individually immaterial, however material leases include:
• The lease for Millerhill Food Waste Plant, more detail behind this lease can be found in Note 34.
Right-of-use assets
This table shows the change in the value of right-of-use assets held under leases by the Council. 
Page 377 of 396

Page 378

WWW.MIDLOTHIAN.GOV.UK 
79 Notes to the Accounts
2023/24
£000  Right of Use Assets
2024/25
£000
0 Balance at 1 April  1,859
0 Depreciation (371)
0 Additions 0
0 Reclassification of Assets and other movements 1,267
0 Balance at 31 March 2,755
Transactions under leases
The Council incurred the following expenses and cash flows in relation to leases.
2023/24
£000  Lease Transactions
2024/25
£000 
Comprehensive income and expenditure statement 
0 Interest expense on lease liabilities 118
0 Expense relating to short-term leases 229
0 Expense relating to low value items 335 
Cash flow statement 
0 Minimum lease payment 418
Maturity analysis of lease liabilities
The lease liabilities are due to be settled over the following time bands (measured at the undiscounted
amounts of expected cash payments).  
2023/24
£000  Maturity Analysis
2024/25
£000
0 Less than one year ( Short-term creditors) 352
0 One to five years (Long-term liabilities) 498
0 More than five years (Long-term liabilities) 884
0 Total Undiscounted Liabilities 1,734 
34. Public Private Partnership (PPP) and Similar Contracts
The Council has entered into five such contracts:
Dalkeith Schools Campus
This is a 30-year PPP contract with Dalkeith SPV Ltd for the provision and facilities management of the
Campus. When the agreement ends in 2034 the Campus facilities will transfer to the Council with a
guaranteed maintenance - free life of five years. The contractor does not have any right of renewal on
contract expiry. Termination of contract is either at contract end date or following the issue of a contractor
default notice of voluntary termination with one contract months’ notice.
Midlothian Schools Ltd
This is a PPP contract for the provision and facilities management of Stobhill, Gorebridge, Tynewater,
Moorfoot, Loanhead and St Margaret’s, Lawfield and Strathesk Primary Schools. When the agreement
ends in 2037 the facilities will transfer to the Council in a usable condition as defined by the contract. The
contractor does not have any right of renewal on contract expiry. Termination of contract is either at
contract end date or following the issue of a contractor default notice of voluntary termination with six
months’ notice.
Newbattle Community Campus
This is a 25-year Not for Profit Distributing Model (NPDM) contract with hubCo for the provision and
lifecycle maintenance of the Campus. The facility opened in the financial year 2018/19 on 25th May 2018.
Page 378 of 396

Page 379

WWW.MIDLOTHIAN.GOV.UK 
80 Notes to the Accounts
When the agreement ends in 2043 the facilities will transfer to the Council in a useable condition as defined
by the contract. The contractor does not have any right of renewal on contract expiry. Termination of
contract is either at contract end date or following the issue of a contractor default notice of voluntary
termination with variable notice periods as defined in the contract.
Food Waste Treatment Plant, Millerhill
This is a 20- year Design, Build, Finance and Maintain (DBFM) contract which was jointly procured between
Midlothian and the City of Edinburgh Council. At the end of the concession period in 2036 the asset will not
revert back to the partner Councils and will remain under the full control of the DBFO operator, who has
the option to continue to operate the asset from year 20 through to year 40, paying the market rent for the
lease of the land over this period. At the end of the 40th year, the asset will be decommissioned and the
decommissioned site transferred back to the ownership of the Councils. Termination of contract is either
at contract end date or following the issue of a contractor default notice or voluntary termination with 40
days’ notice. As this is a non-service concession contract the liability for the contract is included within
Note 33 Leases. 
Residual Waste Treatment Plant, Millerhill
This is a 25- year DBFM contract which was jointly procured between Midlothian and the City of Edinburgh
Council. At 1 April 2020, the contract was in the commissioning phase, with full service commencement
achieved on 17 April 2019. The asset will be fully maintained throughout the life of the contract in
accordance with the Partner Council’s requirements and will be inspected 18 months prior to the end of
the contract (contract end date 6 May 2044) to ensure that it has been maintained. The asset will then be
handed back to the Partner Councils in a condition that is commensurate with such maintenance. The
contractor does not have any right of renewal on contract expiry. Termination of contract is either at
contract end date or following the issue of a contractor default notice, the issue of a Partner Council
Default notice, or voluntary termination by the Partner Councils with variable notice periods as defined in
the contract.
Property, Plant and Equipment
The assets used to provide the services at the Dalkeith Schools Community Campus, the Primary Schools,
the Newbattle Community Campus and the Millerhill Residual Waste Plant are recognised in the Council’s
Balance Sheet under the Property, Plant and Equipment category in Note 14.
Payments
The council makes an agreed payment each year that is increased annually by inflation and can be reduced
if the contractor fails to meet availability and performance standards in any year but which is otherwise
fixed.
There is also a donated asset account associated with the financing of the Millerhill Residual Waste asset.
The recognition of donated asset income is on a flat line basis over the 25 years of the contract.
Payments remaining to be made under these contracts at 31 March 2025 are as follows:  
Liability  Interest
Service
Charge  Total
Dalkeith Schools Campus £000 £000 £000 £000
Within 1 Year 1,333 1,720 2,432 5,485
Within 2 to 5 Years 6,836 5,371 9,727 21,934
Within 6 to 10 Years 8,587 2,119 8,591 19,297
Total Remaining Contract 16,756 9,210 20,750 46,716 
Page 379 of 396

Page 380

WWW.MIDLOTHIAN.GOV.UK 
81 Notes to the Accounts  
Liability  Interest
Service
Charge  Total
Midlothian Primary Schools  £000 £000 £000 £000
Within 1 Year 1,230 1,737 2,759  5,726
Within 2 to 5 Years 5,891 5,984 11,742 23,617
Within 6 to 10 Years 10,126 4,718 16,406 31,250
Within 11 to 15 Years 6,836 881 9,057 16,774
Total Remaining Contract 24,083 13,320 39,964 77,367 
Liability  Interest
Service
Charge  Total
Newbattle Community Campus £000 £000 £000 £000
Within 1 Year 984 1,426 166 2,576
Within 2 to 5 Years 4,461 5,179 707 10,347
Within 6 to 10 Years 6,968 5,081 988 13,037
Within 11 to 15 Years 8,918  3,132 1,118 13,168
Within 16 to 20 Years 7,290 725 779 8,794
Total Remaining Contract 28,621 15,543 3,758 47,922 
Donated
Asset  Liability  Interest
Service
Charge  Total
Millerhill Residual Waste £000 £000 £000 £000 £000
Within 1 Year 573 55 914 1,342 2,884
Within 2 to 5 Years 2,292 204 3,559 5,786 11,841
Within 6 to 10 Years 2,867 638 4,110 7,937 15,552
Within 11 to 15 Years 2,867 1,443 3,204 8,972 16,486
Within 16 to 20 Years 2,867 2,524 1,201 8,217 14,809
Total Remaining Contract 11,466 4,864 12,988 32,254 61,572 
Although the payments made to the contractor are described as unitary payments, they have been
calculated to compensate the contractor for the fair value of the services they provide, the capital
expenditure incurred and interest payable while the capital expenditure remains to be reimbursed. The
liability outstanding to be paid to the contractors for capital expenditure incurred is as follows:  
2023/24    2024/25 
Liability
Donated
Asset  Total   Liability
Donated
Asset  Total
£000 £000 £000 Liabilities £000 £000 £000
79,819 12,613 92,432 Balance Outstanding at 1 April 76,699 12,039 88,738
(3,120) 0 (3,120) Payments during the year (3,602) 0 (3,602)
0 (574) (574) Other Movements 1,227 (573) 654
76,699 12,039 88,738 Balance at 31 March 74,324 11,466 85,790 
2023/24
£000  Included in the Balance Sheet
2024/25
£000
3,920 Current (Short-term Creditors) 4,175
84,818 Non-Current (Other Long-term Liability) 81,615
88,738 Balance at 31 March 85,790 
Page 380 of 396

Page 381

WWW.MIDLOTHIAN.GOV.UK 
82 Notes to the Accounts
Service Concession Arrangements (SCA’s)
Midlothian Council has adopted the revised accounting arrangements under Local Government Finance
Circular 10/2022 – Finance Leases and Service Concession Arrangements. 
The current repayment charges for each SCA have been compared against an annuity repayment profile
based on the estimated useful asset lives. The calculation of the repayment charges of each SCAs or Public
Private Partnership (PPP) scheme using the asset life annuity basis is compared to the current charges
which are made over the contract period and summarised as follows: 
Year
Current
Repayment
£000
Revised
Repayment
£000
Total
(reduction)/Cost
£000 
NPV  
£000
Pre 2023/24 23,783 3,320 (20,463) (20,463)
2023/24 3,120 512 (2,608) (2,520)
Yrs 2 to 5 14,973 2,486 (12,487) (11,045)
Yrs 6 to 10 26,182 4,441 (21,741) (16,443)
Yrs 11 to 25 35,541 30,466 (5,075) (5,387)
Yrs 26 to 40 0  43,663 43,663 14,375
Yrs 41+ 0  18,711 18,711 4,250
Total Saving 103,599 103,599 0 (37,233) 
The total cumulative statutory adjustment up to the 31st March 2023 which would result from changing
the calculation of the repayment of debt liability on the four SCAs using a 60-year, 50-year and a 26-year
annuity period respectively is £20.463m. This is a one off in year reduction, compared to the current
schedule of repayments. In the financial years up to the expiry date of each contract date(s) there would
be further reductions. In the remaining years following the end of the SCAs,  the rescheduled debt
repayments continue until the debt liability has been extinguished.
Over the full life of the SCAs the total repayment for the debt liability remains the same. However, when a
Net Present Value (NPV) is applied the reprofiled charges would result in a total reduction in NPV terms of
£37.233m.
35. Pension Schemes Accounted for as Defined Benefit Contribution Schemes
Teachers employed by the Council are members of this Scottish Teachers Superannuation scheme,
administered by the Scottish Government. The Scheme provides teachers with specified benefits upon
their retirement, and the Council contributes towards the costs by making contributions based on a
percentage of members’ pensionable salaries.
The scheme is technically a defined benefit scheme. However, the scheme is unfunded and the Scottish
Government uses a notional fund as the basis for calculating the employers’ contribution rate by local
authorities. The Council is not able to identify its share of underlying financial position and performance of
the scheme with sufficient reliability for accounting purposes. For the purposes of this Statement of
Accounts, it is therefore accounted for on the same basis as a defined contribution scheme.
In 2024/25 the Council paid £15.202 million (2023/24 £12.439 million) to the Scottish Government in
respect of teachers’ pension costs. The rate of contribution was 26% for 2024/25 (2023/24 23%).
The Council is responsible for the costs of any additional benefits awarded upon early retirement outside
the terms of the teachers’ scheme. These costs are accounted for on defined benefit basis (detailed in
note 35).
The Council is not liable to the scheme for any other entities’ obligations under the plan.
Page 381 of 396

Page 382

WWW.MIDLOTHIAN.GOV.UK 
83 Notes to the Accounts
36. Defined Benefit Pension Schemes
As part of the terms and conditions of employment and its officers, the Council makes contributions
towards the cost of post-employment benefits. Although these benefits will not actually be payable until
employees retire, the Council has a commitment to make the payments (for those benefits) and to disclose
at the time that employees earn their future entitlement.
The Council participates in the Local Government Pension (Scotland) Scheme. Employees other than
teachers are eligible to join this scheme. The scheme is administered by City of Edinburgh Council through
Lothian Pension Fund. This is a funded defined benefit final salary scheme, meaning the Council and
employees pay contributions into a fund, calculated at a level intended to balance the pension’s liabilities
with the investment assets.
The principal risks to the Council of the scheme are the longevity assumptions, statutory changes to the
scheme, and structural changes to the scheme (i.e. large-scale withdrawals from the scheme), changes
to inflation, bond yields and the performance of equity investments held by the scheme. These are
mitigated to a certain extent by the statutory requirements to charge the General Fund and Housing
Revenue Account the amounts required by statute as described in the accounting policies note.
Transactions Relating to Post-Employment Benefits
The cost of retirement benefits in the reported cost of services is recognised when they are earned by
employees, rather than when the benefits are eventually paid as pensions. However, the charge that is
required to be made against council tax is based on cash payable in the year, so the real cost of post-
employment/retirement benefits is reversed out of the General Fund and Housing Revenue Account via
the Movement in Reserves Statement.
The following transactions have been made in the Comprehensive Income and Expenditure Statement and
the General Fund balance via the Movement in Reserves Statement during the year.
2023/24  2024/25
£000 Comprehensive Income and Expenditure Statement (CIES) £000 
Cost of services: 
Service Cost Comprising: 
17,484 • Current service cost 19,766
0 • Past service cost (including curtailments) 156 
Financing and Investment Income and Expenditure: 
(9,031) • Net interest (income)/expense (8,880) 
8,453
Total Post-employment Benefit Charged to the Surplus or Deficit on the
Provision of Services  11,042 
Other Post Employment Benefit charged to the Other Comprehensive Income &
Expenditure Statement: 
Re-measurement of the Net Defined Benefit Asset Comprising: 
(9,603) • Return on plan assets 15,001
(19,560) • Actuarial (gains)/losses arising on changes in financial assumptions (89,635)
(11,007) • Actuarial (gains)/losses arising on changes in  demographic assumptions (911) 
(2,122)
• Actuarial (gains)/losses arising on changes in the effect of limiting a net
defined benefit asset to the asset ceiling  86,235
53,665 • Other re-measurement experiences (5,794) 
11,373
Total post-employment benefits charged to the Other Comprehensive Income
& Expenditure Statement  4,896
19,826 Total post-employment benefits charged to the CIES 15,938 
2023/24
£000  Movement in Reserves Statement
2024/25
£000 
(8,453)
Reversal of net charges made to the surplus or deficit for the provision of services
for post-employment benefits in accordance with the code  (11,042)
20,014 Employers Contributions payable to the scheme 17,117
11,561 Total Charged to the Movement in Reserves 6,075
Page 382 of 396

Page 383

WWW.MIDLOTHIAN.GOV.UK 
84 Notes to the Accounts
Pension Assets and Liabilities Recognised in the Balance Sheet
Net Asset Restriction
The actuary has calculated the Council’s IAS 19 defined benefit surplus for 2024/25 to be £273.943 million
(2023/24 £186.529 million) as detailed in the tables below. IAS 19 states that when an entity has a surplus
in the defined benefit plan it should measure the net defined benefit of the asset as the lower of:
• The surplus in the defined benefit plan, and
• The asset ceiling has been calculated by the actuary as the present value of any economic benefits
available.  Reductions in future contributions to the plan was used as the basis to determine the
amount of the economic benefit as Midlothian Council has no unconditional right to a refund from
the Fund and therefore there is no economic benefit available as a refund. 
For IFRIC 14 purposes, the actuary has calculated the net present value of the future contributions of
£913.931 million exceeds the value of the future service costs of £658.215 million, a negative contribution
of £255.716 million. As a result of this calculation IFRIC 14 advises that no defined benefit plan asset
should be recognised in the Council’s Balance Sheet and there is no requirement to recognise the
difference as a liability, however, is required to reflect the liability in relation to present value of unfunded
obligations of £6.433 million.
The amount included in the Balance Sheet arising from the Council’s obligation in respect of its defined
benefit plans is as follows:
2023/24  2024/25
£000 Pensions Assets and Liabilities Recognised in the Balance Sheet £000
(550,295) Present value of the defined benefit obligation (486,187)
736,824 Fair value of Plan Assets 760,130
186,529 Net (liability)/asset arising from defined benefit obligation 273,943
(194,141) Restriction Adjustment under IFRIC 14 (280,376)
(7,612) Revised Net (liability)/asset arising from defined benefit obligation (6,433) 
2023/24
£000
Reconciliation of the present value of the scheme liabilities (defined
benefit obligation)
2024/25
£000
510,236 Opening Balance at 1 April 550,295
17,484 Current service cost 19,766
24,316 Interest Cost 26,531
5,105 Contributions by Scheme Participants 5,419 
Re-measurement (gains)/losses 
(19,560) • Changes in financial assumptions (89,635)
(11,007) • Changes in demographic assumptions (911)
45,063 • Other (5,794)
0 Past service cost (including curtailments) 156
(751) Estimated Unfunded Benefits Paid (751)
(20,591) Estimated Benefits Paid (18,889)
550,295 Closing Balance at 31 March 486,187 
Page 383 of 396

Page 384

WWW.MIDLOTHIAN.GOV.UK 
85 Notes to the Accounts 
2023/24   2024/25
£000 Reconciliation of the movements in the fair value of scheme assets £000
698,699 Opening fair value of scheme assets 736,824
33,347 Interest Income 35,411 
Re-measurement gains/(losses): 
9,603 • Return on assets excluding amounts included in net interest (15,001)
(8,602) • Other 0
19,263 Contributions from Employer 16,366
5,105 Contributions from employees into the scheme 5,419
(20,591) Benefits Paid (18,889)
751 Contributions in respect of Unfunded Benefits 751
(751) Unfunded Benefits Paid (751)
736,824 Closing Balance at 31 March 760,130 
Local Government legislation provides that Local Authorities have an obligation to meet their share of the
expenditure of the Joint Boards of which they are constituent members. At 31 March 2025, the liability for
Pensions sits at £1.275 million (2023/24 £1.082 million). As a consequence the Council has additional
assets arising from the pension surplus of the Lothian Valuation Joint Board.
Basis for Estimating Assets and Liabilities Recognised
Liabilities have been assessed on an actuarial basis using the projected unit credit method, an estimate of
the pensions that will be payable in future years are dependent on assumptions about mortality rates,
salary levels etc. 
The Local Government Pension Scheme liabilities have been estimated by Hymans Robertson LLP, an
independent firm of actuaries and estimates for the pension fund are based on the latest full valuation of
the scheme as at 31 March 2025.
The significant assumptions used by the actuary have been:
2023/24 Mortality Assumptions 2024/25 
Longevity at 65 for Current Pensioners: 
20.1 - Men (Years) 20
23 - Women (Years) 23 
Longevity at 65 for Future Pensioners: 
20.9 - Men (Years) 20.8
24.6 - Women (Years) 24.5 
Financial Assumptions 
2.8% Rate of Inflation/increase in pensions 2.8%
3.5% Rate of increase in salaries 3.5%
4.8% Rate for discounting scheme liabilities 5.8%
6.1% Actual Rate of Investment Returns 2.8% 
The estimation of the defined benefit obligations is sensitive to the actuarial assumptions set out in the
table above. The sensitivity analysis below have been determined based on possible changes of the
assumptions occurring at the end of the reporting period and assumes for each change that the
assumption analysed changes while all the other assumptions remain constant. The estimations in the
sensitivity analysis have followed the accounting policies for the scheme, i.e. on an actuarial basis using
the projected unit credit method. The methods and types of assumptions used in preparing the sensitivity
analysis below did not change from those used in the previous period.
Page 384 of 396

Page 385

WWW.MIDLOTHIAN.GOV.UK 
86 Notes to the Accounts 
Pension Sensitivities at 31 March 25
Approximate %
increase to the
Employer
Obligation
Approximate
monetary
amount 
£000
0.1% decrease Real Discount Rate 2% 8,454
1 year increase in member life expectancy 4% 19,447
0.1% increase in the Salary Increase Rate 0% 494
0.1 % increase in the Pension Increase Rate (CPI) 2% 8,188 
Local Government Pension Schemes Comprised 
2023/24     2023/24 
Fair Value
of Scheme
Assets 
Percentage
of Total
Assets 
Quoted
prices in
active
markets
Quoted
prices
not  in
active
markets
Total  Fair
Value of
Scheme
Assets 
Percentage
of Total
Assets
£000  Pension Fund Assets £000 £000 £000 
27,363 4% Cash and Cash Equivalents 26,070 0 26,070 3%  
Equity Instruments:    
87,027 12%   Consumer 96,319 0 96,319 13%
101,191 14%   Manufacturing 91,509 0 91,509 12%
40,028 5%   Energy and Utilities 42,516 0 42,516 6%
43,382 6%   Financial Institutions 42,441 0 42,441 6%
47,614 6%   Health and Care 48,054 0 48,054 6%
36,530 5%   Information Technology 23,498 17 23,515 3%
45,196 6%   Other 51,223 0 51,223 7%
400,968 54% Sub-total Equity 395,560 17 395,577 53%  
Bonds:    
11,893 2%   Corporate  0 0 0 0%
99,052 13% Government 132,552 0 132,552 17%
12,757 2%   Other 12,478 0 12,478 2%
123,702 17% Sub-total bonds 145,030 0 145,030 19%  
Property:    
37,652 5%   UK  0 28,588 28,588 4%
2,501 0%   Overseas 0 0 0 0%
40,153 5% Sub-total Property 0 28,588 28,588 4%  
Investment Trusts and Unit Trusts:    
0 0%   Equities 1,322 0 1,322 0%
8,165 1%   Commodities 0 0 0 0%
18,742 3%   Bonds 11,085 13,005 24,090 3%
111,081 15%   Infrastructure 0 2,944 2,944 0%
0 0%   Other 6,300 0 6300 1%
137,988 19% Sub-total Trusts 18,707 15,949 34,656 4%
6,767 1% Private Equity (all) 1,168 128,895 130,063 17% 
(117)  0%
Derivatives: Forward Foreign
Exchange Contracts  146  0  146  0%
736,824 100% Total Assets 586,681 173,449 760,130 100% 
Impact on Council Cash Flows
The objectives of the scheme are to keep employers’ contributions at as constant a rate as possible. The
fund has agreed a strategy with the scheme’s actuary to achieve a funding level of 100% of the overall
liabilities of the fund in the longer term. Funding levels are monitored on an annual basis. The next triennial
valuation will be performed at 31 March 2026, with results being published by 31 March 2027 and will
impact contribution rates from 1 April 2027. The Council anticipates to pay £16.256 million in contributions
to the scheme to 31 March 2026.
The weighted average duration of the defined benefit obligation scheme members is 17 years for 2024/25
(17 years 2023/24).
Page 385 of 396

Page 386

WWW.MIDLOTHIAN.GOV.UK 
87 Notes to the Accounts
37. Contingent Liabilities
The assimilation of the stand-alone Lothian Buses Pension Fund into the general Lothian Pension Fund
required all four Council shareholders in Lothian Buses Limited to enter into a deed of guarantee and
function as guarantors for Lothian Buses Limited contributions to the general fund. Previously, whilst there
was no formal guarantee in place for the stand alone Lothian Buses Fund, in the event of a default then the
City of Edinburgh Council (as administering authority) would have looked to the four Council shareholders
to make good any liability.
38. Trusts and Bequests
There are some 15 active trusts, bequest and community funds of varying size managed by the Council,
each of which has specific objectives and conditions. None of the funds are currently registered charities.
The main funds are:
2023/24
£000  Trusts, Bequests, Common Good and Community Funds
2024/25
£000
8 Dalkeith Common Good Fund 8
2 Penicuik Common Good Fund 2
52 Community Mining Funds 55
108 Other Funds 115
170 Total 180 
A total £0.115 million (2022/23 £0.108 million) has been committed to be spent from these funds.
The funds do not represent assets of the Council and are included in the Balance Sheet as creditors except
the Community Mining Funds that are held in separate bank accounts.
39. Notes to the Group Accounts
The Code of Practice on Local Council Accounting in the United Kingdom 2024/25 (The Code) applies to
Local Authorities or similar bodies defined in section 106 of the Local Government (Scotland) Act 1973 e.g.
statutory bodies such as Integration Joint Boards and Valuation Boards. Authorities are required to prepare
a full set of group accounts in addition to their own Council’s accounts where they have a material interest
in such entities. The Group Accounts of Midlothian Council are prepared in accordance with the
accounting policies of the Council with the additions and exceptions shown below. The Group Accounts
consolidate the results of the Council with other entities. These organisations are entirely independent of
the Council under law and for taxation.
Valuation of Property, Plant and Equipment
The basis of valuation across the combining entities is in accordance with the Code and there are no
material inconsistencies with the policies adopted by Midlothian Council. The Integration Joint Board has
no Property, Plant or Equipment.
Depreciation
The basis of valuation across the combining entities is in accordance with the Code and there are no
material inconsistences with the policies adopted by Midlothian Council.
Goodwill
The Council has acquired its share of the net assets of its associates for  nil consideration and no goodwill
has been included in the Group Balance Sheet.
Basis of Consolidation
Subsidiaries are consolidated on a line-by-line basis. All other entities are accounted for under the
accounting conventions of the “acquisition basis” using the equity method – the Council’s share of the
Page 386 of 396

Page 387

WWW.MIDLOTHIAN.GOV.UK 
88 Notes to the Accounts
entities results and its share of other gains and losses (recognised in the Group CIES). With the exception
of Midlothian Energy Ltd, whose reporting date is 31 December, all entities have the same reporting date
as the Council.
Restrictions of the Transfer of Funds
The Council’s share of the reserves of its associate and joint ventures is unusable i.e. it cannot be used to
fund the Council’s services to reduce taxation. Further details for each entity are as follows: 
Entity 
Percentage
Share in
Entity
Share
of
Assets
£000 
Share of
Liabilities
£000
Net
Share of
Assets
£000 
Share of
Revenues
£000 
Share of
(Profit)/Loss
£000
Subsidiaries:      
Trusts, Bequests,
Common Good and
Community Funds
100 
180  (180)  0  (10)  (10)
Pacific Shelf 826 Ltd* 100 0 0 0 0 (58)  
180 (180) 0 (10) (68)
Associates:      
Lothian Valuation Joint
Board  9  341  (353)  (12)  (1,758)  (1)       
Joint Ventures:      
Midlothian Integration
Joint Board  50  474  0  474  (102,045)  (75)
Midlothian Energy Ltd 50 16,338 (7,689) 8,649 174 174
Total Joint Ventures &
Associates   17,153  (8,042)  9,111  (103,629)  98
Total for Group  17,333 (8,222) 9,111 (103,639) 30
*Pacific shelf was dissolved during 2024/25
The information above agrees to the group accounts after the elimination of inter-company transactions.
Combining Entities
The following table provided further details about the entities incorporated into the Council’s Group
Accounts:
Group Entities Nature of Body Accounts Available From
Subsidiaries:  
Trusts, Bequests,
Common Good and
Community Funds
To award grants across Midlothian. Midlothian Council, Midlothian
House, Buccleuch Street,
Dalkeith
Associates:  
Lothian Joint
Valuation Board
Maintains the electoral, council tax and non-domestic rates registers for
the Edinburgh, Midlothian, West Lothian and East Lothian Councils.
The Treasurer, Lothian Joint
Valuation Board, Edinburgh
Council, Waverly Court,
Edinburgh
Joint Ventures:  
Midlothian
Integration Joint
Board
Its purpose is to improve the well-being of families, our communities and
of people who use health and social care services. The Integration
Scheme determines when the Council will have shared responsibility for
additional funding with NHS Lothian and is linked to demographic shifts
and demand volumes linked to service delivery.
Midlothian Council, Midlothian
House, Buccleuch Street,
Dalkeith
Midlothian Energy
Limited
Energy generation, distribution and supply. Midlothian Council, Midlothian
House, Buccleuch Street,
Dalkeith 
Non-material Interests in Other Entities
In addition to the organisations outlined above, the Council also has an interest in Seemis Group LLP who
provide Scottish Local Authorities with an Education Management System. Midlothian have a 1.90%
interest in Seemis.
Page 387 of 396

Page 388

WWW.MIDLOTHIAN.GOV.UK 
89 Supplementary Statements
Supplementary Statements
Housing Revenue Account
The HRA Income and Expenditure Statement shows the economic cost in the year of providing housing
services in accordance with generally accepted accounting practices, rather than the amount to be funded
from rents and government grants. The Council charge rents to cover expenditure in accordance with the
legislative framework; this may be different from the accounting cost. The increase or decrease in the year,
on the basis which rents are raised, is shown in the movement on the Housing Revenue Account
Statement.
2023/24   2024/25
£000 HRA Income and Expenditure Statement £000 £000 
Expenditure:  
8,739 Repairs and Maintenance 12,062 
5,427 Supervision and Management 5,259 
55,608 Depreciation, impairment and revaluation non-current assets 63,310 
670 Movement in the allowance for bad debtors 720 
0 Void rent and council tax* 1,432 
2,396 Other Expenditure 2,384 
72,840 Total Expenditure  85,167 
Income:  
(31,372) Dwelling Rents (35,575) 
(342) Non-dwelling Rents (704) 
(155) Service Charge Income (159) 
(91) Other Income (69) 
(31,960) Total Income  (36,507) 
40,880
Net Expenditure or (Income) of HRA services as included in the
Comprehensive Income and Expenditure Statement   48,660
332 HRA Share of Corporate and Democratic Core  348
41,212 Net (Income)/expenditure for HRA Services  49,008 
HRA share of the operating income and expenditure included in the whole
authority Comprehensive Income and Expenditure Statement:  
0 (Gain) or Loss on sale of HRA non-current assets 455 
8,588 Interest payable and similar charges 10,398 
(1,534) Interest and investment income (1,853) 
(55) Net interest on the net defined liability benefit liability (asset) (50) 
6,999   8,950
48,211 (Surplus)/Deficit for the year on HRA Services  57,958
*Netted off against rent in 2023/24
Movement in the Housing Revenue Account
2023/24   2024/25
£000 Movement on the HRA Statement £000 £000
(32,143) Balance on the HRA at the end of the previous reporting period  (33,182) 
48,211 (Surplus) or deficit for the year on the HRA Income and Expenditure Statement   57,958 
Adjustments between accounting basis and funding basis under statute:  
(55,608) Depreciation, impairment and revaluation non-current assets (63,309) 
0 Gain or (Loss) on sale of HRA non-current assets (455) 
4,221 Loans Fund Principal 7,047 
66 Net charges made for retirement benefits in accordance with IAS 19 31 
(51,321) Total Adjustments between accounting basis and funding basis under statute 
(56,686)
2,071 Transfer to General Fund Reserve  0
(1,039) (Increase) or Decrease in year on the HRA  1,272
(33,182) Balance on the HRA at the end of the current reporting period  (31,910) 
Page 388 of 396

Page 389

WWW.MIDLOTHIAN.GOV.UK 
90 Supplementary Statements
Notes to the Housing Revenue Account 
Housing Stock
The number of council dwellings for the year can be analysed as follows:
2023/24 Housing Stock 2024/25
1,083 1 Bedroom 1,132
4,128 2 Bedroom 4,149
1,975 3 Bedroom 2,006
332 4 Bedroom 336
11 5/6 Bedroom 11
7,529 Total Housing Stock at 31 March  7,634 
This represents an increase in the year of 105 units (2023/24 258), which is represented in the table below:
2023/24 Increase/(decrease) in Housing Stock 2024/25
233 New Build Completions 100
27 Open Market Purchases 7
(2) Re-purposed units for temporary accommodation (2)
0 Demolition/Disposal 0
258 Net increase in Housing Stock at 31 March  105 
Other Information
2023/24  2024/25
£000 Other Information* £000
6,979 Total Rent Arrears 7,755
3,380 Bad Debt Provision 4,100
*void rent now shown as an expense within the main HRA Income and Expenditure Statement. 
Page 389 of 396

Page 390

WWW.MIDLOTHIAN.GOV.UK 
91 Supplementary Statements
Council Tax Income Account
The Council Tax Income Account (Scotland) shows the gross income raised from Council Taxes levied and
deductions made under statute. The resultant net income is transferred to the Comprehensive Income and
Expenditure Statement of the Council.
Local Authorities raise taxes from its residents through Council Tax, which is based on property values.
Each dwelling in a local Council area is placed into one of eight valuation bands, A to H. The Council
declares a tax for Band D properties and all other properties are charged a proportion of this, lower valued
properties (Bands A to C) pay less; higher valued properties (Bands D to F) pay more.
2023/24  2024/25
£000 Council Tax Income Account £000
72,406 Gross Council Tax levied and Contributions in Lieu 73,857 
Less: 
(5,671)   Council Tax Reduction Scheme (5,876)
(6,942)   Other Discounts and Reductions (7,219)
(2,443)   Write-off of Uncollectable Debts and Allowances for impairment (2,487)
(44)   Prior year adjustments 19
57,306 Net Council Tax Income transferred to General Fund 58,294 
Midlothian Council Tax Charge and Properties by Band
2023/24  2023/24  2024/25  2024/25
Property
Numbers
£ per
Property  Band
Property
Numbers
£ per
Property
1 842 A - Disabled 1 842
603 1,010 A 598 1,010
8,532 1,178 B 8,516 1,178
8,741 1,346 C 8,699 1,346
5,231 1,515 D 5,253 1,515
5,056 1,990 E 5,135 1,990
4,397 2,461 F 4,498 2,461
2,896 2,966 G 3,009 2,966
178 3,711 H 180 3,711
35,635   35,889 
Page 390 of 396

Page 391

WWW.MIDLOTHIAN.GOV.UK 
92 Supplementary Statements
Calculation of Council Tax Base (shown as numbers of properties)
2024/25 A
(Disabled)
A B C D E F G H Total No of
Properties
Number of Properties 0 988 12,834 11,352 6,108 5,804 4,801 3,159 189 45,235
Properties subject to Empty Homes Premium 0 5 57 58 34 24 17 17 4 216
Properties subject to Disabled Relief 2 36 43 (49) 12 5 (12) (34) (3) 0
Less:            
Exempt Properties 0 68 506 296 109 195 71 29 6 1,280  
Properties Entitled to 25% Discounts 0 147 1,497 989 472 342 167 82 4 3,700  
Properties Entitled to 50% Discounts 0 0 4 5 3 3 2 2 0 19  
Properties Entitled to Other Discounts 0 7 20 15 5 3 7 3 1 61  
Reduction in Tax Base due to Council Tax Reduction 1 209 2,391 1,357 312 155 60 17 0 4,502
Total Equivalent Properties  1 598 8,516 8,699 5,253 5,135 4,499 3,009 179 35,889
Ratio to Band D 0.56 0.67 0.78 0.89 1 1.31 1.63 1.96 2.45 
Band D Equivalent Properties 0 399 6,624 7,732 5,253 6,746 7,310 5,893 440 40,397
Contributions in Lieu - Band D Equivalents          230
Sub-total          40,627
Less Bad Debt Provision at 3.75%          (1,642)
Total Council Tax Base          38,985 
2023/24 A
(Disabled)
A B C D E F G H Total No of
Properties
Band D Equivalent Properties 0 402 6,636 7,770 5,231 6,643 7,145 5,671 437 39,935
Contributions in Lieu - Band D Equivalents          199
Sub-total          40,134
Less Bad Debt Provision at 3.75%          (1,613)
Total Council Tax Base          38,521 
Page 391 of 396

Page 392

WWW.MIDLOTHIAN.GOV.UK 
93 Supplementary Statements
Non-domestic Rate Account
The Non-domestic Rate Account (Scotland) is a statement that reflects the statutory obligation for billing
authorities to maintain a separate non-domestic rate account. The statement shows the gross income
from the rates and deductions made under statute. The net income is paid to the Scottish Government as
a contribution to the national non-domestic rate pool.
2023/24  2024/25
£000 Non-Domestic Rate Income Account £000
47,637 Gross Council Tax levied and Contributions in Lieu 49,794 
Less: 
(10,790)   Reliefs and other deductions (10,398)
(938)   Write-off of Uncollectable Debts and Allowances for impairment (1,066)
35,909 Net Non-Domestic Rates Income 38,330
(711) Prior year adjustments (2,260)
0 Non-domestic rates income retained by the council (BRIS) 0
35,198 Contribution to Non-Domestic Rate Pool 36,070 
Allocated: 
35,954 Contribution to non-domestic rate pool 36,212
(756) Council Rate Income - non-pool (142)
35,198  36,070
35,215 Amount distributed to Midlothian Council from non-domestic rate pool 34,944 
The Business Rate Incentivisation Scheme (BRIS) permits the Council to retain 50 percent share of the
Non-domestic rates income, which exceeds the income target set by Scottish Government.
Net Rateable Value Calculation
Occupiers of non-domestic property pay rate based on the valuation of the property within the valuation
roll for Midlothian. The NNDR poundage is determined by the Scottish Government and was 49.8p (2023/24
49.8p) per £, where the rateable value was less than £51,000 (2023/24 £51,000), 54.5p where the rateable
value is between £51,000 and £100,000 (2023/24 51.1p between £51,000 and £100,000,) and 55.9p per £
where the rateable value exceeded £100,000 (2023/24 52.4p greater than £100,000).
2023/24 2023/24  2024/25 2024/25
Numbers £000 Analysis of Rateable Values and Number of Premises Numbers £000
1,831 49,831 Shops, Offices and Other Commercial Subjects 1,836 49,835
973 19,913 Industrial and Freight Transport 960 19,560
304 23,379 Miscellaneous (Schools, etc.) 302 23,320
3,108 93,123 Total 3,098 92,715 
Page 392 of 396

Page 393

WWW.MIDLOTHIAN.GOV.UK 
94 Glossary of Terms
Glossary of Terms
While much of the terminology used in this report is intended to be self-explanatory, the following
additional definitions and interpretation of terms may be of assistance.
Actuarial Gains and Losses (Pension)
For a defined benefit scheme, the changes in actuarial deficits or surpluses that arise because events have
not coincided with the actuarial assumptions made for the last valuation (experience gains and losses) or
the actuarial assumptions have changed.
Amortisation
Amortisation is the cost of reducing the value of an intangible asset over its useful economic life. A charge
is made against services for the value of the assets they have used during the year.
Assets
An asset is any item that has value including cash, investments, properties, vehicles, etc. Assets are
classified as current, which will be consumed within the current year, or non-current, which will be used
to provide services over more than one year.
Associate
An entity other than a subsidiary or joint venture in which the reporting Council has a participating interest
and over whose operating and financial policies, the reporting Council is able to exercise significant
influence.
Capital Expenditure
This is expenditure incurred in creating, acquiring or improving assets where the expenditure is normally
financed by borrowing with repayment over a period of years, or by using the income from the sale of
existing assets.
Capital Financed from Current Revenue
This heading covers the costs of creating, acquiring or improving assets where the expenditure is charged
directly to the Revenue Account.
Corporate and Democratic Core
Corporate and Democratic Core costs include the costs of policymaking and all other Councillor based
activities together with costs that relate to the general running of the Council. The Best Value Accounting
Code of Practice stipulates that such costs are to be excluded from the “total cost” relating to service
activity.
Community Assets
Long-term assets that have no determinable useful economic life and are held in perpetuity by the Council,
including parks and open spaces.
Creditors
Creditors are a kind of liability. They represent payments owed by the Council to another person or
organisation for past events.
Debtors
Debtors are a kind of asset. They represent payments owed to the Council by another person or
organisation for past events. 
Page 393 of 396

Page 394

WWW.MIDLOTHIAN.GOV.UK 
95 Glossary of Terms
Defined Benefit Pension Scheme
A Defined Benefit Pension Scheme is a scheme where the benefits due to participants are predetermined
based on earnings, length of service and age and are not directly dependant on the contributions paid or
investment returns realised.
Depreciation
Depreciation is the measure of the cost of wearing out, consuming or reducing the useful life of the
Council’s assets. A charge is made against services for the value of the assets they have used during the
year.
Entity
A body corporate, partnership, trust, unincorporated association, or statutory body that is delivering a
service, or carrying on a trade or business, with or without a view to profit. It should have a separate legal
personality and is legally required to prepare its own single-entity accounts.
Fair Value
The fair value of an asset or liability is the price at which it could be exchanged or settled in an arm’s length
transaction between two willing, knowledgeable parties.
Financial Instrument
A financial instrument is any contract, which gives rise to a financial asset or liability or an equity
instrument in another entity, this includes cash, debtors, creditors, loans, borrowings and shares in other
companies.
Infrastructure Assets
Non-current assets that cannot be transferred or sold, including roads, bridges and footpaths.
Inventories
Inventories are raw materials or goods which have been purchased but which have not yet been consumed
in the delivery of Council services.
Liabilities
A liability represents a payment owed to another person or organisation including loans, outstanding
invoices, provisions, contributions owed to third parties, etc. Short-term liabilities are due to be paid within
the current year. Long-term liabilities are amounts that will not be paid until a later year.
Non-Distributable Costs
Non Distributable Costs represent costs that cannot be allocated to specific services and again, under the
Best Value Accounting Code of Practice, are excluded from the total cost relating to service activity.
Examples of Non Distributable Costs are charges for added pension years and early retirement.
Other Costs
This heading covers items of expenditure that cannot be accommodated in any of the other categories.
Provisions
A provision is a kind of liability. Where a payment for a liability is certain or highly likely to occur but the
exact amount and timing is not known, an amount must be put aside to meet the estimated future costs.
Revaluation / Impairment
Revaluations and impairments are adjustments to the value of an asset, either positively or negatively, to
align the carrying value of an asset to an independent assessment of the asset’s fair value.
Page 394 of 396

Page 395

WWW.MIDLOTHIAN.GOV.UK 
96 Glossary of Terms
Revenue Expenditure
Revenue expenditure includes the day-to-day costs of providing services including salaries and wages,
property costs, transport costs, supplies, and services. It also includes the costs of the repayment of loans
used to finance capital expenditure. 
Page 395 of 396

Page 396

Page 396 of 396