Moray Integration Joint Board 
Thursday, 27 March 2025 
Council Chambers 
NOTICE IS HEREBY GIVEN that a Meeting of the Moray Integration Joint Board,
Council Chambers, Council Office, High Street, Elgin, IV30 1BX on Thursday, 27
March 2025 at 09:30 to consider the business noted below. 
AGENDA 
1. Welcome and Apologies 
2. Declaration of Member's Interests 
3. Minute of meeting of 30 January 2025 5 - 10
4. Action Log of 30 January 2025 11 - 12
5. Minutes - for noting 
5a Minute of meeting Audit Performance and Risk
Committee of 26 September 2024
13 - 18
5b Minute of meeting Clinical and Care Governance
Committee of 28 November 2024
19 - 22
6. Chief Officer Report 23 - 28
7. Revenue Budget and Recovery Plan 2025-26 29 - 94
8. Medium Term Financial Framework 2025-26 - 2029-30 95 - 112
Page 1

Page 2

9. Health and Social Care Moray Strategic Delivery Plan
2025-28
113 - 142
10. Equalities Mainstreaming Progress Report 2021-2024 143 - 162 
Item(s) which the Committee may wish to consider with
the Press and Public excluded   
11. CONFIDENTIAL Care at Home
• 9. Information on terms proposed or to be proposed by or to the
Authority; 
Watching the Meeting
You can watch the webcast live by going to: 
http://www.moray.gov.uk/moray_standard/page_43661.html    
Webcasts are available to view for 1 year following the meeting.  
You can also attend the meeting in person, if you wish to do so,
please come to the High Street entrance door and a member of
staff will be let into the building. 
Page 2

Page 3

MORAY INTEGRATION JOINT BOARD 
SEDERUNT 
Mr Dennis Robertson  (Chair)  
Councillor Peter Bloomfield  (Voting Member)
Councillor Elaine Kirby  (Voting Member)
Councillor Scott Lawrence  (Voting Member)
Mr Derick Murray  (Voting Member)
Mr Sandy Riddell  (Voting Member)
Mr Alex Stephen  (Voting Member)
Councillor Ben Williams  (Voting Member)
Dr Adam Coldwells  (Ex-Officio)
Ms Karen Greaves BEM  (Ex-Officio)
Mr John Mundell  (Ex-Officio)  
Mr Ivan Augustus  (Non-Voting Member)
Professor Duff Bruce  (Non-Voting Member)
Mrs Sheila Brumby  (Non-Voting Member)
Mr Sean Coady  (Non-Voting Member)
Ms Sonya Duncan  (Non-Voting Member)
Ms Jane Ewen  (Non-Voting Member)
Dr Robert Lockhart  (Non-Voting Member)
Mr Jim Lyon  (Non-Voting Member)
Ms Deirdre McIntyre  (Non-Voting Member)
Ms Deborah O'Shea  (Non-Voting Member)
Ms Judith Proctor  (Non-Voting Member)
Ms Elizabeth Robinson  (Non-Voting Member)
Dr Malcolm Simmons  (Non-Voting Member)
Mr Kevin Todd  (Non-Voting Member) 
Clerk Name: Caroline O'Connor
Clerk Telephone: 07779 999296
Clerk Email: committee.services@moray.gov.uk 
Page 3

Page 4

Page 4

Page 5

MINUTE OF MEETING OF THE MORAY INTEGRATION JOINT BOARD 
Thursday, 30 January 2025 
Council Chambers, Council Office, High Street, Elgin, IV30 1BX 
PRESENT 
Mr Ivan Augustus, Councillor Peter Bloomfield, Mrs Sheila Brumby, Mr Sean Coady,
Dr Adam Coldwells, Ms Sonya Duncan, Ms Jane Ewen, Councillor Elaine Kirby,
Councillor Scott Lawrence, Mr Jim Lyon, Ms Deirdre McIntyre, Mr Derick Murray, Ms
Deborah O'Shea, Ms Judith Proctor, Mr Sandy Riddell, Mr Dennis Robertson, Ms
Elizabeth Robinson, Dr Malcolm Simmons, Mr Alex Stephen, Mr Kevin Todd,
Councillor Ben Williams 
APOLOGIES 
Professor Duff Bruce, Dr Robert Lockhart, Mr John Mundell 
IN ATTENDANCE 
Planning, Innovation and Programmes Directorate, NHS Grampian; Programme
Manager (NHS Grampian General Practice Vision Programme); Consultant in
Public Health Medicine/Immunisation Coordinator and Vaccination Planning
Manager, both Public Health, NHS Grampian; Corporate Programme Manager;
Head of Governance, Strategy and Performance and Caroline O'Connor,
Committee Services Officer. 
1.         Chair 
The meeting was chaired by Mr Dennis Robertson.  
2.         Declaration of Member's Interests 
The Board noted there were no declarations of member's interest.  
3.         Minute of meeting of 28 November 2024 
The minute of the meeting of 28 November 2024 was submitted and approved.  
Item 3.
Page 5

Page 6

4.         Action Log of 28 November 2024 
The Action Log of the meeting of 26 November 2024 was discussed and updated
accordingly.  
5.         Minute of Special Meeting of 20 November 2024 
The minute of the Special Meeting of 20 November 2024 was submitted and
approved.  
6.         Minute of meeting Clinical and Care Governance Committee of 29
August 2024 
The Board noted the minute of the meeting of the Clinical and Care Governance
Committee of 27 June 2024.  
7.         Chief Officer Report 
The meeting had before it a report by the Chief Officer informing the Board of the
Chief Officer activities that support the delivery against the Moray Integration Joint
Board's (MIJB's) strategic priorities articulated in the Strategic Plan, and the delivery
against the 9 Health and Wellbeing outcomes. 
During discussion Mr Todd asked for more detail on the positive changes made by
the Discharge to Access Team joining forces with the START team (care at home
enablement team) referenced in paragraph 3.1 in order to provide assurance
discharges are safe.  In response the Chief Officer offered to arrange a development
session on the positive change work being done in relation to discharges with a
further report to come back to the Board. 
Following consideration the Board unanimously agreed:-  
(i) to note the content of the report; 
(ii) that transforming services to meet the aspirations of the MIJB's Strategic Plan
remains a priority; and 
(iii) that the Chief Officer arrange a development session on the positive change
work being done in relation to discharges with a further report to come back to
the Board.  
8.         Revenue Budget Monitoring Quarter 3 for 2024-25 
The meeting had before it a report by the Chief Financial Officer updating the Moray
Integration Joint Board (MIJB) of the current Revenue Budget reporting position as at
31 December 2024 for the MIJB budget.  
Following consideration the Board unanimously agreed to:-  
(i) note the financial position of the Board as at 31 December 2024 is showing an
overspend of £4,841,788 on core services;  
(ii) note the provisional forecast position for 2024/25 of an overspend of £5,889,502
on total budget for core services;  
Page 6

Page 7

(iii) note the progress against the approved savings plan in paragraph 6, and
Appendix 4;  
(iv) note the budget pressures and emerging budget pressure as detailed in
paragraph 7;  
(v) note the revisions to staffing arrangements dealt with under delegated powers
and in accordance with financial regulations within the Council (MC) and NHS
Grampian (NHSG) for the period 1 October to 31 December 2024 as shown in
Appendix 3; and  
(vi) approve Directions for issue as set out at Appendix 5 to NHS Grampian and
Moray Council.  
9.         North East Route Map for Strategic Change 
The meeting had before it a report by the Chief Officer providing a brief overview of
the North East Route Map for Strategic Change.  
Following consideration the meeting unanimously agreed to:- 
(i) provide comment on the Grampian Strategic Change Board terms of reference at
Appendix 1; 
(ii) endorse the establishment of the Grampian Strategic Change Board; 
(iii) endorse the collaborative approach proposed to develop a Route Map for
Strategic Change; and 
(iv) agree that the IJB Chief Officers should actively participate in the development
and implementation of the Route Map for Strategic Change and work
collaboratively with other partners to ensure the success of this crucial
transformation program.  
10.         General Practice Vision and Objectives Update 
The meeting had before it a report by the Programme Manager, GP Vision
Programme updating the Board on the outcomes and recommendations of the NHS
Grampian General Practice (GP) Vision programme and seeking endorsement of the
vision and SMART objectives related to the programme.  
In relation to Demand Measurement through GP Systems referenced at paragraph
4.9, Councillor Kirby asked for more detailed information, specifically how and when it
would be done and whether it would involve patient engagement. In response, the
Programme Manager (NHSG General Practice Vision Programme) advised she
would provide a written answer for Board members.  
Following consideration the Board unanimously agreed:- 
(i) to note the content of the report as an update on current progress on the GP
Vision Programme; and 
(ii) a report be brought back to the Board with a further annual update in spring
2026. 
Page 7

Page 8

11.         Grampian Vaccination and Immunisation Annual Report 2024 
The meeting had before it a report updating the Board with an annual monitoring
report of vaccine preventable disease surveillance data, along with uptake data for
each vaccine delivered within Grampian to provide assurance.  
Following consideration the Board unanimously agreed:-  
(i) to note the findings of the Vaccination and Immunisation Annual Report 2024
attached as Appendix 1; and 
(ii) annual monitoring reporting continues to the Board.  
12.         Charging for Services 
The meeting had before it a report by the Chief Financial Officer asking the Board to
consider the charges for services for the 2025/26 financial year.  
Following consideration the Board unanimously agreed to:-  
(i) adhere to the request of the Moray Council that the MIJB recommend to them,
the charges for the services delivered within the delegated functions; 
(ii) approve the charges set out at Appendix 1 for recommendation to Moray Council
for approval and inclusion into their budget setting processes; and 
(iii) note the recommended charges will be subject to assessment for the socio-
economic impact and reported back to the MIJB where there is significant impact
and no mitigation. 
13.         Children’s Services Plan 2023-2026 - Annual Report for 2023-2024 
The meeting had before it a report by the Interim Chief Social Work Officer presenting
the draft Children's Services Plan 2023-24 Annual Report to the Board.  
Following consideration the Board unanimously agreed to:-  
(i) approve the Children’s Services Plan 2023-2024 Annual report attached as
Appendix 1; and 
(ii) note when both the Community Planning Board and the Moray Integrated Joint
Board have approved the report, a finalised version will be submitted to the
Scottish Government and published on the Community Planning Board website. 
14.         Carefirst Replacement - Update 
The meeting had before it a report by the Interim Head of Service and Chief Social
Work Officer informing the Board of the progress of the replacement Social Work and
Social Care case management system and outline business case.  
Following consideration the Board unanimously agreed to:-  
(i) approve the outline business case at Appendix 1; 
Page 8

Page 9

(ii) note the amended project timescales at Appendix 2; and 
(iii) note approval for funding will be subject of a future report following the outcome
of the tender process and further details are known. 
15.         Getting it Right for Everyone 
The meeting had before it a report by the Deputy Head of Service informing the
Board of progress of the national Getting it Right for Everyone (GIRFE) programme,
the involvement of Health and Social Care Moray (HSCM) as a GIRFE partner, and
the collaborative GIRFE approaches being taken by partners in Grampian.  
Following consideration the Board unanimously agreed to:-  
(i) consider and note the content of the report; 
(ii) endorse the collaborative whole system approach being taken in Moray and by
partners across Grampian; and 
(iii) receive further reports detailing how GIRFE is being embedded in Moray. 
16.         Chair of Moray Integration Joint Board 
The meeting had before it a report by the Standards Officer asking the Board to agree
a temporary change to the arrangements for Chair of the Moray Integration Joint
Board (MIJB), as set out in the Moray Integration Scheme.  
Following consideration the Board unanimously agreed:-  
(i) to a temporary deviation from the Moray Integration Scheme allowing Mr Dennis
Robertson to continue to undertake the role of Chair of the Board until 31 March
2025; and 
(ii) that Councillor Elaine Kirby take on the role of Chair of the Board from 1 April
2025 until 30 September 2025, following which the role of Chair will revert back to
a Health Board Member in line with the Integration Scheme. 
17.         Code of Conduct Update 
The meeting had before it a report by the Standards Officer asking the Board to adopt
the Standards Commission's Model Code of Conduct for Members of Devolved
Bodies replacing the Code of Conduct previously agreed by the Board in June 2016.  
In response to an offer from the Head of Governance, Strategy and Performance to
provide additional training, the Chair stated it would be helpful for refresher training in
terms of the enhanced Code to be scheduled for one of the Board's development
sessions. 
Following consideration the Board unanimously agreed to adopt the Standards
Commission's Model Code of Conduct for Members of Devolved Bodies (Appendix 1)
as the Code of Conduct for the Moray Integration Joint Board.   
Page 9

Page 10

Page 10

Page 11

MEETING OF MORAY INTEGRATION JOINT BOARD 
Thursday 30 January 2025 
ACTION LOG 
ITEM
NO.
TITLE OF
REPORT
ACTION REQUIRED DUE DATE ACTION
BY
UPDATE FOR 27
MARCH 2025
1. Options for Ward
4 Inpatient Unit
for Patients with
Mental Illness
Further development work to be undertaken in
order to prepare a full detailed report which
would be brought back to the Board for
consideration in approximately 3 months. 
Update 28/11/24: Development session to be
scheduled to be held before the strategic
delivery plan progress update comes back to
the Board in 6 months, to provide more details
on progress and engage with members of the
Board. 
TBC 
TBC
SC/KK 
JP
There will be a Grampian
wide mental health
inpatient bed base review
and any
recommendations in
relation to Ward 4 will be
included within this
Item 4.
Page 11

Page 12

ITEM
NO.
TITLE OF
REPORT
ACTION REQUIRED DUE DATE ACTION
BY
UPDATE FOR 27
MARCH 2025
2. Chief Officer
Report 26/09/24
• Interim Chief Officer provide an update
in relation to progress made resulting
from the external inspection of
Children's Services in relation to
children and young people at risk of
harm, through the governance
structures of the MIJB;
• Interim Chief Officer would provide a
report in relation to how the rights and
supported needs of unpaid carers are
met in Moray;
• Interim Chief Officer would arrange a
development day for a demonstration in
relation to Digital Health and Care 
TBC JP Partially Complete / In
Progress
3. Chief Officer
Report 30/01/25
Chief Officer to arrange development session
on the positive change work being done in
relation to discharges, with a further report to
come back to the Board. 
JP 
4. GP Vision and
Objectives
Update
Written answer to be provided to Board
members providing more detailed information
on Demand Measurement through GP Phone
systems, specifically how and when it will be
done and whether there will be patient
engagement. 
AC 
5. Code of Conduct
Update
Refresher training in terms of the enhanced
Code to be scheduled for one of the Board's
development sessions. 
SD/AMcE Timetabled Summer
2025 
Page 12

Page 13

MINUTE OF MEETING OF THE AUDIT, PERFORMANCE AND RISK COMMITTEE 
Thursday, 26 September 2024 
Remote Locations via Connect Remote, 
PRESENT 
Mr Sean Coady, Councillor Scott Lawrence, Mr Derick Murray, Mrs Jeanette
Netherwood, Ms Deborah O'Shea, Ms Judith Proctor, Mr Sandy Riddell 
APOLOGIES 
Ms Deirdre McIntyre, Ms Janette Topp, Councillor Ben Williams 
IN ATTENDANCE 
Interim Chief Officer, Angela Pieri, Engagement Lead and Andrew Wallace, Audit
Manager, both of Grant Thornton, Service Manager (Primary Care Contracts), Carl
Campbell, Service Manager (Education and Social Care), Social Work Service
Manager, Chief Internal Auditor, Chief Financial Officer, Corporate Programme
Manager, Ms L Van Zyl, Service Manager and Mrs L Rowan, Committee Services
Officer as Clerk to the Committee.   
1         Chair 
Mr Sandy Riddell chaired the meeting. 
2         Declaration of Member's Interests 
Mr Riddell stated for transparency that he was Chair of the Mental Welfare
Commission Scotland.  
The Committee noted that there were no other declarations of member's interests.  
3         Minute of meeting of 27 June 2024 
The minute of the meeting of 27 June 2024 was submitted and approved. 
Item 5a
Page 13

Page 14

4         Action Log of Meeting of 27 June 2024 
The Action Log of the meeting of 27 June 2024 was discussed and updated
accordingly.  
5         External Auditors Report to Those Charged with Governance 
The meeting had before it a report by the Chief Financial Officer asking the
Committee to consider the reports to those charged with governance from the Board's
External Auditor for the year ended 31 March 2024.  
The Committee joined the Chair in thanking those involved in providing the External
Auditor's Report and thereafter unanimously agreed to note the reports from the
External Auditor as set out in Appendices 1 and 2 of the report and recommended
them for approval by the Moray Integration Joint Board.  
6         2023-24 Audited Annual Accounts 
The meeting had before it a report by the Chief Financial Officer presenting to the
Committee the Audited Annual Accounts for the year ended 31 March 2024.  
Following consideration, the Committee agreed to note the Audited Annual Accounts
for the financial year 2023/24 and the letter of Representation and recommended
them to the Moray Integration Joint Board for approval. 
7         Quarter 1 (April-June 2024) Performance Report 
Mr Coady, Head of Service joined the meeting during discussion of this item.  
The meeting had before it a report by the Corporate Programme Manager updating
the Committee on performance as at Quarter 1 2024 (April-June).  
During discussion, it was noted that there were several areas where it was
acknowledged that performance is poor, and it was queried whether future reports
could include narrative explaining what measures are being taken to improve
performance in these areas.  
In response, the Interim Chief Officer agreed to include narrative explaining what
measures are being taken to improve performance in areas of poor performance in
future reports.  
During further discussion, the Chair noted that the report stated that there was no
need for an Equality Impact Assessment as there would be no impact on people with
protected characteristics as a result of the report and sought assurance that the
Committee was complying with it's legal responsibilities in relation to equalities and
suggested that this section be expanded in future reports.  
In response, the Interim Chief Officer assured the Committee that the Board is
committed to acknowledging any inequality in minority groups and advised that it was
her intention to refresh equalities training in the near future.  
Following consideration, the Committee unanimously agreed to note: 
Page 14

Page 15

(i) the performance of local indicators for Quarter 1 (April to June 2024) as
presented in the Performance Report at Appendix 1; 
(ii) the analysis of the local indicators that have been highlighted and actions being
undertaken to address performance that is outside of acceptable target ranges as
detailed in Appendix 1 of the report; 
(iii) the performance for 2023/24 against the national indicators, where data is
published, as set out in Appendix 2 of the report; 
(iv) that future performance reports would include narrative explaining what measures
are being taken to improve performance in areas of poor performance; and 
(v) that the Interim Chief Officer intended to refresh equalities training in the near
future. 
8         Quarter 1 Performance Report for Childrens Social Work and Justice
Services 
The meeting had before it a report by the Chief Social Work Officer/Head of Service
informing the Committee on Children and Families and Justice Social Work
performance as at Quarter 1.  
During discussion surrounding the activity that had taken place within Children and
Families and Justice Social Work Section it was queried whether future reports could
include narrative in relation to outcomes resulting from the activity.  
In response, the Service Manager agreed to take this point forward and
include narrative in relation to outcomes resulting from the activity in future
performance reports.  
During further discussion, the Chair again noted that the Equalities paragraph in the
Summary of Implication Section stated that there was no equality impact as a result
of the report when he was aware of some good work that had taken place in this area
and suggested that this section be expanded to reflect this.  
In response, the Service Manager agreed to expand the paragraph in relation to
equalities in future reports.  
Following consideration, the Committee unanimously agreed to note the: 
(i) performance of local indicators for Quarter 1 as presented in the Performance
Report at Appendix 1; and 
(ii) analysis of the local indicators as detailed in Appendix 1 of the report; 
(iii) that future reports would: 
• include narrative in relation to outcomes resulting from the activity in future
performance reports;
• expand the equalities paragraph within the Summary of Implications section
of the report.    
Page 15

Page 16

9         Internal Audit Section - Completed Projects 
The meeting had before it a report by the Chief Internal Auditor providing an update
on audit work completed since the last meeting of the Committee.  
Following consideration, the Committee agreed to note the audit update. 
10         Public Sector Internal Audit Standards - External Quality Assessment of
Internal Audit 
The meeting had before it a report by the Chief Internal Auditor providing the
Committee with details of a recent external quality assessment undertaken of the
Council's Internal Audit Service.  
The Committee joined the Chair in commending all involved in the recent external
quality assessment and thereafter unanimously agreed to note the report and the
Action Plan prepared to address the issues raised in the external quality assessment
of internal audit.  
11         Payment Verification 
The meeting had before it a report by the Head of Service/Depute Chief Officer
providing an update on the review of the Payment Verification (PV) Assurance
Service provided by National Services Scotland (NSS) Practitioner Services Division
(PSD), on behalf of NHS Grampian.  
Following consideration, the Committee unanimously agree to note: 
(i) the arrangements in place in Grampian for the management of the payment
verification process; 
(ii) that the payment verification process has now fully restarted after pausing during
COVID-19; and 
(iii) the actions already taken to address the outstanding issues, with plans for future
action to include an update on progress to this committee in January 2025.  
12         Annual Performance Report 2023-24 
The meeting had before it a report by the Interim Chief Officer presenting the draft
Annual Performance Report 2023/24.  
The Chair thanked the Corporate Programme Manager for circulating the revised
Annual Performance Report for 2023/24 after several typos had been noted following
publication of the agenda.  
Following consideration, the Committee unanimously agreed to: 
(i) note the draft Annual Performance Report 2023/24 at Appendix 1 and
subsequent amendments previously circulated; and 
(ii) recommend to the Moray Integration Joint Board for approval and publication of
the Annual Performance Report 2023/24 by 30 September 2024.   
Page 16

Page 17

13         Internal Audit Section - Update Report [Para 6.2.5] 
The meeting had before it a report by the Chief Internal Auditor providing an update
on the work of the Internal Audit Section.  
Following consideration, the Committee unanimously agreed to note the contents of
the report.  
14         Internal Audit Section - Completed Project - Email Security [Para 6.2.5] 
The meeting had before it a report by the Chief Internal Auditor providing an update
on audit work completed since the last meeting of the Committee.  
Following consideration, the Committee unanimously agreed to note the audit update. 
15         Update on Improvement Plan for Adult Social Care Commissioning
[Para 6.2.2] 
The meeting had before it a report by the Head of Service/Chief Social Work Officer
updating the Committee about progress regarding the Improvement Plan for Adult
Social Care Commissioning.  
Following consideration, the Committee unanimously agreed to note: 
(i) the progress of the Improvement Plan as set out in Appendix 1 of the report; 
(ii) the progress within the report as at the end of July 2024 in relation to the
recommendations detailed in the Improvement Plan; and 
(iii) that the updated report includes details of contract values, timelines, and risks.   
Page 17

Page 18

Page 18

Page 19

MINUTE OF MEETING OF THE CLINICAL AND CARE GOVERNANCE
COMMITTEE 
Thursday, 28 November 2024 
Council Chambers, Council Office, High Street, Elgin, IV30 1BX 
PRESENT 
Mr Ivan Augustus, Councillor Peter Bloomfield, Mrs Sheila Brumby, Mr Sean Coady,
Councillor Scott Lawrence, Dr Robert Lockhart, Mr Jim Lyon, Mr Derick Murray, Ms
Deborah O'Shea, Ms Judith Proctor, Ms Elizabeth Robinson 
APOLOGIES 
Professor Duff Bruce, Ms Helen Chisholm, Dr Malcolm Simmons, Mr Alex Stephen,
Mr Kevin Todd, Ms Janette Topp 
IN ATTENDANCE 
Allied Health Professional, Sector Lead Moray; Corporate Manager; Business
Manger, Mental Health and Drug and Alcohol Services; Consultant Practitioner,
Adult Support and Protection Lead; Integrated Service Manager, Community
Learning Disability Service; Lesley Attridge, Locality Manager and Caroline
O'Connor, Committee Services Officer.  
SUBSTITUTES
Mr Sandy Riddell (for Mr Alex Stephen) 
ALSO IN ATTENDANCE
Councillor Elaine Kirby  
1.         Chair 
The meeting was chaired by Mr Derick Murray.  
2.         Welcome and Apologies 
The Committee joined the Chair in thanking Mr Sandy Riddell for continuing to
substitute for Mr Alex Stephen and welcomed Cllr Kirby to her first meeting of the
Committee.  
Item 5b
Page 19

Page 20

3.         Order of Business 
In terms of Standing Order 2.2, the meeting agreed to vary the order of business as
set down on the Agenda and take Item 7 "Health and Social Care Moray Clinical and
Care Governance Group Escalation Report" after Item 5 "Complaints Report for
Quarter 2 2024-25" followed by Item 6 "Drug Related Deaths in Moray" in order to
allow the Allied Health Professional, Sector Lead Moray to vacate the meeting at the
earliest opportunity.  
4.         Declaration of Member's Interests 
There were no declarations of Member's interests in respect of any item on the
agenda.  
5.         Minutes of meeting of 29 August 2024 
The minutes of the meeting of 29 August 2024 were submitted for approval.  
In respect of Item 9 "Inspection of the Moray Supported Lodgings Project in May
2024", Mr Riddell noted the wording in the third paragraph should read "progressed"
rather than "progress".  
Subject to the amendment above, the Committee agreed the minutes of the meeting. 
6.         Action Log - 29 August 2024 
The Action Log of the meeting of 29 August 2024 was discussed and updated
accordingly.  
7.         Complaints Report for Quarter 2 2024-25 
The meeting had before it a report by the Allied Health Professional - Sector Lead,
Moray informing the Committee of complaints reported and closed during Quarter 2
(1 July 2024 - 30 September 2024).  
Following consideration the Committee unanimously agreed to note the totals,
lessons learned, response times and action taken for complaints completed within the
last quarter.  
8.         Health and Social Care Moray Clinical and Care Governance Group
Escalation Report 
The meeting had before it a report by the Chief Nurse, Moray informing the
Committee of progress and exceptions reported to the Clinical and Care Governance
Group since the last report to Committee in August 2024.  
Following consideration the Committee unanimously agreed to note the contents of
the report.  
9.         Drug Related Deaths in Moray 
The meeting had before it a report by the Business Manager, Mental Health and Drug
and Alcohol Services updating the Committee about drug-related deaths in Moray.  
Page 20

Page 21

Following consideration the Committee unanimously agreed to note:-  
(i) the drug related death figures for Moray; 
(ii) the ongoing work of the service in relation to the Multi Agency Risk System
(MARS) process; 
(iii) the National Benchmarking report on the implementation of the Medication
Assisted Treatment (MAT) Standards: Scotland 2023/24; 
(iv) the work being done on the Moray residential rehabilitation pathway; and 
(v) the development of a strategic group and lived experience panel to align the
Moray strategy and the National Mission.  
10.         Joint Inspection of Adult Support and Protection - Progress Review
Summary and Findings 
The meeting had before it a report by the Consultant Practitioner, Adult Support and
Protection Lead Officer providing a summary and overview of the findings of the
Moray Joint Inspection of Adult Support and Protection - Progress Review that took
place between August - October 2024.  
The Board joined the Chair in commending the work of the team and partners in
relation to the significant progress highlighted in the Progress Review.   
Following consideration the Committee unanimously agreed to:-  
(i) note the Joint Inspection of Adult Support and Protection - Progress Review
Report; and 
(ii) acknowledge the hard work and commitment demonstrated by the Moray Adult
Protection Committee, Leaders and Front-Line Practitioners throughout the
Partnership in supporting people at risk in the Moray community.  
11.         Adult Support and Protection Multi Agency Improvement Plan 
The meeting had before it a report by the Consultant Practitioner, Adult Support and
Protection Lead Officer updating the Committee on progress against the Adult
Support and Protection Multi-Agency Improvement Plan since the last update
provided in March 2024.  
Following consideration the Committee unanimously agreed to:-  
(i) note the Multi-Agency Improvement Plan and progress to date; and 
(ii) note the systems in place to monitor and progress actions within the plan.  
12.         Learning Disability Services Dynamic Support Register - Update 
The meeting had before it a report by the Integrated Service Manager, Community
Learning Disability Service informing the Committee of the requirements of the
Scottish Government directive relating to the Coming Home Report, and of the
actions and progress made by the Learning Disability Service in response to the
Page 21

Page 22

directive.  Assurance is also given that planning and development continues which
will address future anticipated needs associated to the directive.  
Following consideration the Committee unanimously agreed to:-  
(i) note the requirements of the Scottish Government in relation to the Coming
Home Report and Dynamic Support Register and the actions taken by the
Learning Disability Service to respond to the Scottish Government Directive as
set out in paragraphs 4.1-4.6, and in doing so; 
(ii) continue to support the housing projects that are to be utilised by adults with a
Learning Disability which is integral to meeting the requirements of the register
and which was previously agreed at the Moray Integration Joint Board on 30
March 2023 (para 12 of the minute refers).  
13.         End of Life Care Home Beds 
The meeting had before it a report by the Locality Manager informing the Committee
of the termination of block funded End of Life Beds within Moray.  
Following consideration the Committee unanimously agreed to:-  
(i) homologate the termination of End of Life (EOL) Care Bed block funded
contract from March 2024; and 
(ii) the new EOL Care Bed Provision Strategy; transitioning to a spot-purchase
through the Resource Allocation meeting (RAM) process, ensuring continued
access to EOL care for Moray residents.  
14.         Items for Escalation to MIJB 
The Committee noted there were no items for escalation to the Moray Integration
Joint Board.   
Page 22

Page 23

REPORT TO: MORAY INTEGRATION JOINT BOARD ON 27 MARCH 2025 
SUBJECT:   CHIEF OFFICER REPORT 
BY:  CHIEF OFFICER 
1.   REASON FOR REPORT 
1.1 To inform the Board of the Chief Officer activities that support the delivery
against the Moray Integration Joint Board’s (MIJB’s) strategic priorities
articulated in the Strategic Plan, and the delivery against the 9 Health and
Wellbeing outcomes. 
1.2 Strategic planning needs to maintain a focus on transformational change to
deliver services to our community within the resources we have available.
2024/25 is a very challenging year for delivering within the budget, with our
two funding partners, Moray Council and NHS Grampian, under considerable
financial pressure as well. 
2.   RECOMMENDATION 
2.1 It is recommended that the Board:
i) consider and note the content of the report; and
ii) agree that transforming services to meet the aspirations of the
MIJB’s Strategic Plan remains a priority. 
3. BACKGROUND 
Home First/Discharge without Delay
3.1 The number of patients whose discharge is delayed remains stable. At time of
report, there are 37 delayed discharges and our target remains 26. Work has
continued to ensure that patient flow is optimised, daily meetings continue to
collectively deploy available resource to avoid admissions or ensure a safe
early discharge. The START/Discharge to Assess (D2A) pilot continues to
ensure a collaborative re-enablement approach to complex discharges and a
review of Multi-Disciplinary Team (MDT) working is ongoing. 
3.2     In response to National concern relating to the number of delayed discharges,
a new national collaborative has been developed focusing on Discharge
without Delay (DWD). This collaborative has four work streams:-
Item 6.
Page 23

Page 24

• Frailty at the Front Door
• Planned Date of Discharge and integrated discharge hubs
• Community Hospitals and step-down rehabilitation units
• Discharge to Assess and Home First 
3.3     Moray will be part of the Grampian regional DWD group and be represented
locally, regionally and nationally by designated leads for each of the work
streams. There is also a Moray Programme Manager and a Clinical Lead who
will facilitate this work alongside the leads. This collaborative links to the
national frailty collaborative and the whole system unscheduled care work that
have been underway for some time. 
3.4     Phase one required the completion of a self-assessment tool developed by
NHS Tayside which was submitted to the Grampian group for submission on
the 5 March. Work is underway to complete the needs assessment from the
self-assessment tool and this will form the actions for Moray going forward. 
Vaccination Programme
3.5 The winter vaccination programme continues. The COVID-19 offer ended on
31 January, and Flu vaccine continues to be offered to all those eligible until
31 March.  The Shingles and Pneumococcal vaccination programme are
ongoing along with all other routine vaccination programmes for preschool,
and school aged children. Non routine vaccination continues.   Planning is in
place for other routine programmes including RSV and the Spring Covid-19. 
3.6 Notice has been given to vacate the current Moray Vaccination Centre at
Southfield, Elgin, no later than 23 April 2025. NHS Grampian colleagues are
supporting Health and Social Care Moray (HSCM) to identify a short-term
accommodation solution at pace, in order to maintain vaccine delivery. This is
likely to be a mixed model of delivery, utilising some of the venues that are
already used for pop up clinics, and options are being explored to provide a
hub for fridges, records, vaccine delivery and admin / management staff. A
solution for longer-term delivery is also being considered.  Some local comms
will be worked up in due course to update the local populace about the
changes which will include information briefing sheets to go to councillors,
local groups etc, press releases, social media posts and posters to go out to
local venues. 
Mental Health Bed Base Review
3.7  The Mental Health Bed Base Review group reported to the Mental Health and
Learning Disability Programme Board (MHLDPB) on the 25 February 2025.
The MHLDB considered the outputs of the Bed Base Review alongside seven
proposed priority actions and agreed that the Programme can move to an
implementation phase and that the priority actions can be taken forward.   
3.8 Priority action number six referred to the redesign of mental health inpatient
beds and the development of a community treatment model within Moray. 
3.9 The Mental Health Bed Base Review group will now be tasked with
progressing these priorities through specific work streams. 
3.10 The Moray Mental Health Strategic Group will provide a detailed report to the
MIJB on 29 May 2025. 
Page 24

Page 25

GMED
3.11 The GMED service continues to observe recurring difficulties in staffing shifts
across its centres. Rota cover is impacted by seasonal illness, school holidays
and other unplanned absences.           
3.12 Early in 2024, Chief Officers for Moray, Aberdeen City and Aberdeenshire
health and social care partnerships requested a review of the GMED model.
The review, led by a programme board, aims to enhance the quality, safety
and efficiency of the service while ensuring sustainable workforce levels and
promoting staff wellbeing. 
3.13 The review was completed at the end of January 2025. A programme of
engagement and consultation is being developed as guided by Health
Improvement Scotland and the national Planning with People guidance.
Further details will be shared when the next steps have been formally agreed. 
3.14  Work continues on salaried GP service model via Local Negotiating
Committee where terms and conditions for salaried medical staff are
negotiated in partnership between NHSG, British Medical Association, HR,
Staff and Service representation. 
Review of Social Work Governance & Assurance Arrangements across
Scotland
3.15 The Scottish Government undertook a review on social work governance and
assurance in Scotland between July to December 2024, carried out by the
Care Inspectorate on their behalf. The review sought to address, nationally,
how well social work governance and assurance arrangements support
leaders. The report’s findings shall be considered in the development of our
local social work governance arrangements which are currently under review. 
3.16 The review report is due to be published nationally in March 2025 and from
our regular Link Inspector meeting, as of 4 March 2025, there was no
indication of slippage at this time.  A report on this will come to a future MIJB
or relevant committee.         
4.  KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1 To support the acceleration of the MIJB ambitions set out in the Strategic Plan
the Delivery plan is currently being refreshed to support next steps. 
4.2 The challenge of finance persists and there remains the need to address the
underlying deficit in core services. The development of a Programme
Management Office is in progress to support our financial savings. 
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP)) and Moray Integration Joint Board Strategic Plan
“Partners in Care 2022 – 2032”
Working with our partners to support people so they can cope with, and
where possible, overcome the health and wellbeing challenges they
may face. 
Page 25

Page 26

Ensuring that the right care is provided at the right place at the right time
when people are in need. Ensuring that our systems are as simple and
efficient as possible. 
(b) Policy and Legal
The Chief Officer continues to operate within the appropriate level of
delegated authority, ensuring that the MIJB is sighted on key issues at
the earliest opportunity, and continues to influence and agree the
strategic direction. 
(c) Financial implications
There are no financial implications arising directly from this report. The
Chief Finance Officer continues to report regularly. There is an ongoing
requirement to find efficiencies and to demonstrate best value for money. 
(d) Risk Implications and Mitigation
The risk of not redesigning services will mean that HSCM and the Moray
Portfolio cannot respond adequately to future demands.   
(e) Staffing Implications
Staff remain the organisation’s greatest asset, and engagement with all
sectors must continue to ensure full involvement, which will create the
best solutions to the challenges faced. HSCM staff are facing continued
pressures on a daily basis, and effort into ensuring staff well-being must
continue. 
(f) Property
There are no issues arising directly from this report. 
(g) Equalities/Socio Economic Impact
Any proposed permanent change to service delivery will need to be
impact assessed to ensure that HSCM are not disadvantaging any
section of our community. 
HSCM will continue to work closely with all our partners to ensure that
we contribute to the health and well-being of the community and support
the recovery phase of the Covid-19 pandemic. 
(h) Climate Change and Biodiversity Impacts
Care closer to and at home, delivered by teams working on a locality
basis, will reduce HSCM’s reliance on centralised fixed assets and their
associated use of utilities.  
(i) Directions
There are no directions arising from this report. 
(j) Consultations
The Moray Portfolio Senior Management Team, the Legal Services
Manager and Caroline O’Connor, Committee Services Officer have been
consulted in the drafting of this report.  
Page 26

Page 27

6. CONCLUSION 
6.1 The MIJB are asked to acknowledge the significant efforts of staff,
across in-house providers, externally commissioned services, the
Independent and Third Sector, who are supporting the response to the
recovery, and the drive to create resilience and sustainability through
positive change. 
6.2 The size of the financial challenge facing the MIJB, and also its two
funding partners, means that redesign and transformation is not an
option but a necessity. HSCM’s approach will be to prioritise quality,
safety and good outcomes in all service redesigns. 
Author of Report:  Judith Proctor, Chief Officer, Moray Portfolio
Page 27

Page 28

Page 28

Page 29

REPORT TO: MORAY INTEGRATION JOINT BOARD ON 27 MARCH 2025 
SUBJECT: REVENUE BUDGET AND RECOVERY PLAN 2025/26 
BY:  CHIEF FINANCIAL OFFICER 
1. REASON FOR REPORT 
1.1 To outline the budget allocations to the Moray Integration Joint Board (MIJB)
and to consider the revenue budget for 2025/26, the estimated funding gap and
the charges. 
2. RECOMMENDATION 
2.1 It is recommended that the Board: 
i) notes the funding allocations proposed by NHS Grampian and Moray
Council, detailed at 4.6; 
ii) notes the anticipated budget pressures detailed in 4.10; 
iii) approves the 2025/26 proposed savings plan at 4.24 and detailed in
Appendix 2; 
iv) formally approves the Revenue Budget for 2025/26 as detailed in
Appendix 1, following consideration on risks highlighted in 4.34; and 
v) approves Directions for issue as set out at Appendix 5 to NHS
Grampian and Moray Council. 
3. BACKGROUND 
3.1 On 4 December 2024 following the announcement of the Scottish
Government’s indicative budget for 2025-26 by the Cabinet Secretary for
Finance and the Director of Health Finance and Governance wrote to Health
Board Chief Executives providing details of the funding settlement for Health
Boards. In Parliament on 4 December, the Cabinet Secretary set out that
2025/26 continues to present a challenging fiscal environment across all public
services. He added that it was the intent of the Scottish Government budget to
deliver progress for Scotland. The budget is set out to deliver on those priorities
and on the issues people care about most. It also seeks to lay the foundation
Item 7.
Page 29

Page 30

for Scotland’s future success, putting in place the investment that will help
deliver the public services people need and deserve. 
3.2 The letter outlined that NHS payment uplifts to Integration Authorities for
delegated health functions must deliver an uplift of 3% over the 2024/25 agreed
recurring budgets. 
3.3 In addition and separate to Health Board funding uplifts, the health and social
care portfolio will transfer additional funding of £125 million to Local
Government for Adult services and £25.7 million for children’s services to
support retention by beginning to embed improved pay and conditions for care
workers, with Scottish Government considering that this funding requires local
government to deliver a £12.60 minimum pay settlement for social care workers
in commissioned services, in line with the equivalent commitment being made
in the public sector pay policy.  In addition to this, further additional funding of
£10 million will support the uprating of Free Personal and Nursing Care rates. 
3.4 Scottish Government have stipulated that the funding allocation to Integration
Authorities should be additional and not substitutional to each Council’s
2024/25 recurring budgets for adult social care services and therefore, Local
Authority adult social care budgets for allocation to Integration Authorities
should be £150.7 million greater than 2024/25. 
3.5 The settlement outlined does not make provision for the UK Government’s
increases to employers National Insurance Contributions (NIC). Work is
constructively on going with the Convention of Scottish Local Authorities
(COSLA) to ensure that the UK Government provide the funding necessary to
support public services in Scotland. The latest indication is that there will be a
further £300 million from the UK Government to support the impact of its
decision to raise employer NIC on the public sector. However it is clear that the
impact on Scotland’s public sector, including local government, as well as
commissioned services and third sector organisations which provide statutory
services, could well be in excess of £700 million. 
4. KEY MATTERS RELEVANT TO RECOMMENDATION 
MIJB Budget 
4.1 The MIJB is required to consider its budget in the context of economic
uncertainty in relation to the ongoing increase in the cost of living and high
interest rates. It is fair to say that the impact of these circumstances remains a
challenge and cannot yet be fully assessed. 
4.2 Following the announcement of the Scottish Budget, NHS Grampian and Moray
Council have notified the MIJB Chief Officer and Chief Financial Officer of the
funding allocation for the forthcoming financial year. 
4.3 On 26 February 2025, a meeting of Moray Council agreed its 2025/26 budget
for the forthcoming financial year (para 3 of draft minute refers).  The Local
Government settlement is for one year only, but the budget was set in the
context of longer-term planning. The funding to the Council included £289
million for local priorities / to preserve the settlement in real terms. The Scottish
Government are also providing funding for up to 60% towards the costs of the
increase in employers’ National Insurance Contributions (eNIC) and so apart
Page 30

Page 31

from these funds which are to be passported through to the MIJB, there will be
no further uplift passed on to the MIJB. The paper presented referred to the
Moray share of the additional funding that is required to be passed through from
the Council to the MIJB. This is the Moray share of the reported national
investment in health and social care (adult and children’s services) of £231.5
million and £10 million relating to free nursing and personal care, which equates
to a £2.845 million share for Moray. In addition there is £0.198 million relating to
Children and Young People community mental health services and £0.05 million
for trauma informed training, both of which are directed funding from Scottish
Government. 
4.4 The NHS Grampian budget setting process is based on the principle that
funding allocations to the 3 Grampian IJB’s will be uplifted in line with the
increase in baseline funding agreed through the Scottish Government budget
settlement, with the total to each IJB being made on the National Resource
Allocation Committee (NRAC) share. The draft Scottish Government budget
was announced on 4 December 2024. It provides for a minimum baseline
funding uplift of 3% for 2025/26. The 3% uplift provides MIJB with an increased
funding allocation on the recurring budget of £2.262 million. Formal agreement
of the 2025/26 NHS Grampian financial plan will be sought at its Board on 10
April 2025. 
4.5 The table below summarises the additional funding provided to Integration
Authorities by Scottish Government that is passported through both Moray
Council and NHS Grampian. 
Route Scotland
Wide
Allocation 
Moray IJB
Share  
£m £m
£12.60 – uplift for Adult
Social Care Staff *
Council (full year
effect)
125.0 2.098
£12.60 – uplift for
Children’s Social Care
Staff
Council (full year
effect)
25.7 0.254
Free Personal & Nursing
Care *
Council 10.0 0.197
Directed funding for
caseload reduction in
Children’s social work
Council  0.296
Children and Young
People community
mental health
services (directed
funding)
Council  0.198
Trauma informed training
(directed funding) 
Council  0.050
NHS increase in base
funding by 3%
NHS  2.262
60% funding for the eNIC  Council & NHS  1.392
Total  Additional
Allocation  
6.747 
Page 31

Page 32

MIJB Funding 2025/26
4.6 The MIJB has a responsibility under the Public Bodies (Joint Working)
(Scotland) Act 2014 to set its revenue budget by 31 March each year. The
funding of the MIJB revenue budget in support of the delivery of the Strategic
Plan is delegated from NHS Grampian and Moray Council. The allocated
funding is summarised below: 
£’000
NHS Grampian (recurring 2025/26) 94,724
NHS Grampian – Set Aside Services 15,638
NHS Grampian – 3% increase in base 2,262
NHS Grampian – additional funding for eNIC *** 592
Moray Council – Core ** 85,161
Moray Council Children’s Social Work - Community Mental
Health Services
198
Moray Council Trauma informed training 50
Moray Council – Improvement Grants* 1,060
Moray Council – SG additional funding (share of £160.7M) 2,845
Moray Council – SG additional funding for eNIC *** 800
PARTNER MIJB FUNDING 2025/26 203,330
* Improvement Grants includes £0.707 million which requires to be ring-
fenced as it relates to council house tenants.
** Children’s services includes £3.279 million which required to be ring-fenced
as it relates to the joint Out of Area budget which remains in the Council.
*** Estimated additional grant funding from Scottish Government in respect of
direct costs relating to the implementation of eNIC 
Hosted Services
4.7 Within the scope of services delegated to the MIJB are hosted services.
Budgets for hosted services are primarily based on NRAC. Hosted services are
operated and managed on a Grampian-wide basis. Hosting arrangements mean
that one IJB within the Grampian Health Board area would host the service on
behalf of all 3 IJB’s. Strategic planning for the use of the hosted services is
undertaken by the IJB’s for their respective populations. 
4.8 The 2025/26 budget for Moray’s share of all hosted services is £5.907 million as
detailed below. 
£’000
Hosted by Aberdeen City IJB 
Intermediate Care 990
Sexual Health Services 571  
Hosted by Aberdeenshire IJB 
Marie Curie Nursing 201
Heart Failure Service 70
Continence Service 149
Diabetes MCN including Retinal Screening 246
Chronic Oedema Service 49
HMP Grampian 606
Police Forensic Examiners 381
Page 32

Page 33

Hosted by Moray IJB 
GMED Out of Hours 2,522
Primary Care Contracts 122
TOTAL MORAY HOSTED SERVICES 5,907 
Large Hospital Services (Set Aside)
4.9 Budgets for Large Hospital Services continue to be managed on a day-to-day
basis by the NHS Grampian Acute Sector and Mental Health Service,
however the MIJB has an allocated set aside budget, designed to represent
the consumption of these services by the Moray population. The MIJB has a
responsibility in the joint strategic planning of these services in partnership
with the Acute Sector. 
£’000
General Medicine 7,880
Geriatric Medicine 1,228
Rehabilitation Medicine 100
Respiratory Medicine 252
Palliative Care 32
A & E Inpatient 69
A & E Outpatient 5,172
Learning Disabilities 53
Psychiatry of Old Age 113
General Psychiatry 739  
TOTAL SET ASIDE BUDGET 15,638 
Budget Pressures 
4.10 Budget pressures are a major consideration for the MIJB and are an intrinsic
part of the budget setting process. The additional funding highlighted in the
Scottish Government budget for health and social care is welcomed and will
be required to support expected budget pressures arising for adult and
children’s social care uplift of £12.60 for externally commissioned services
and free personal and nursing care. In previous years, both Moray Council
and NHS Grampian would have supported some elements of inflation through
their budget setting process, taking cognisance of the budget setting protocol
agreed by the MIJB on 14 December 2017 (para 15 of the minute refers).
Given the difficult budget settlement for Local Authorities, there has been no
additional funding aligned to MIJB for adult social care in addition to the
requirement to transfer the share of the additional investment as determined
by Scottish Government. Following the financial pressures facing NHS
Grampian, there is a Scottish Government requirement to increase base
funding for pay and non pay inflation of 3% for the IJB. There is also an
expectation as MIJB continue to re-mobilise and transform, there will be
budget pressures arising in relation to what is described as the recurring
deficit. There will be budget pressures arising during the year that are not yet
known and these will be reported upon once quantified. It is important that any
investment in building capacity is viewed in the context of historical cost
pressures. The identified cost pressures below are based on estimates and
remains an ongoing consideration in the financial planning. The table below
Page 33

Page 34

outlines the anticipated budget pressure the MIJB needs to address in the
forthcoming financial year: 
£’000
BUDGET PRESSURES 
Pay Inflation  2,758
Contractual Inflation & Scottish Living Wage 2,796
Prescribing & Community Pharmacy 1,153
Children in Transition  771
Mental Health complex clients 270
Recurring Deficit 5,988
Hosted services 122
National Care Home Contract (NCHC) uplift 902
Free Personal & Nursing Care (FPNC) uplift 205
Occupational therapy equipment 100
Children with disabilities placement 180
Continuing Care placements 626
Other 41
eNIC pressure 2,505  
TOTAL BUDGET PRESSURES 18,417  
4.11 In March 2024 following agreement at COSLA Leaders, the Scottish
Government wrote to Integration Authorities providing details of the pay uplift
that would apply to staff providing direct care within Adult and Children’s
Social Care in commissioned services. The Scottish Government settlement
for 2025/26 includes funding to support retention and to continue to embed
improved pay and conditions for care workers, requiring local government to
deliver a £12.60 minimum pay settlement for adult and children social care
workers in commissioned services. This will cost in the region of £2.428
million and is included within the budget pressures for the forthcoming year in
the table above. 
4.12 £0.902 million is included as a budget pressure for the NCHC however it is not
yet finalised as Scottish Government and COSLA are still in negotiations
around the increase for 2025/26. This will be partly funded from the additional
funding mentioned above for the £12.60 per hour. The latest proposal
includes an element of increase for the eNIC increases. 
4.13 Budget pressure for FPNC is also to be funded from the Scottish Government
as part of the £10 million additional funding agreed as part of the settlement
for 2025/26. 
4.14 With funding being provided by Scottish Government for some elements listed
above, totalling £6.203 million, which gives a net budget pressure of £12.214
million. 
4.15 Prescribing pressures continue to grow, with a current 5% increase in overall
costs. Details of this budget for 2025/26 is attached at Appendix 3. 
Savings Plan 
4.16 The MIJB strategy sets out the programme of transformation, operation and
improvement. The vision for MIJB Strategy is that “we come together as equal
Page 34

Page 35

and valued partners in care to achieve the best health and wellbeing possible
for everyone in Moray throughout their lives. The 3 themes within the strategy
are:
• Homefirst – developing locality planning approach with the development of
multidisciplinary teams and initiatives including discharge to assess, crises
support, rehabilitation, re-ablement and recovery, housing, adaptations and
technology. Building based to community services.
• Building resilience – developing Making Every Opportunity Count, self
management, prevention, personal responsibility, social prescribing.
• Partners in care- developing care and support planning, support for unpaid
carers, self directed support, realistic medicine, long term conditions,
palliative/end of life, market – shaping strategies.
4.17 Our outcomes continue align with the National Health and Wellbeing
Outcomes (9):
• Lives are healthier
• People live more independently
• Experiences of services are positive
• Quality of life is improved
• Health inequalities are reduced
• Carers are supported
• People are safe
• The workforce continually improves 
4.18 The Moray Joint Strategic Needs Assessment (JSNA) has been refreshed to
analyse the needs of the local population to inform and guide the
commissioning of health, wellbeing and social care services within Moray. The
main goal of the JSNA is to accurately assess the care needs of a local
population in order to improve the physical, mental health and wellbeing of
individuals and communities. 
4.19 MIJB understand that the building blocks of health and wellbeing include:
employment, housing, education and skills, childhood experiences, economic
stability, healthcare, social and community requirements. MIJB also are
working with competing priorities - cost savings, reducing demand on
hospitals, better experiences and outcomes for people who use health and
care services, improved service alignment/integration, developing population
health and prevention at scale, including wellbeing and tackling inequalities. 
4.20 A change in focus for Moray is required to deliver improved care and better
outcomes, ensuring sustainability for the future, rather than to deliver cost
savings only in the short term. The health and care system is often seen as
hospital focused, however an integrated and holistic response is required that
encompasses community assets. This requires a system with increased
generalism and multidisciplinary teamworking, with practitioners able to hold
risk and enable people to live healthily in their communities, with a focus on
prevention and reablement. A community focused health and care system
prioritised to local need and individualised support is most effective where that
support maximises independence. 
Page 35

Page 36

4.21 The budget setting for 2025/26 includes the continuation of the 2024/25
saving plan, which was initially set over 2 financial years, this gives a total of
£5.556 million that is planned to be achieved in 2025/26. This was not enough
to cover all the budget gap in 2025/26, so ongoing meetings of the Chief
Officer and the Senior Management Team, along with service managers have
taken place, and given savings identified to date, it remains extremely
challenging to identify additional savings to support the 2025/26 budget
setting process. The proposed savings being presented today are provided
following discussion at the recent MIJB Development session on 27 February
2025. Given that each separate decision made when setting the budget may
impact on the lives of people with protected characteristics, the importance of
the cumulative impact on the decisions being taken is recognised, including
the cumulative impact of service changes and unintended consequences on
communities where multiple organisations might have reduced savings.  
4.22 There is still a focus and commitment around identifying further in-year
savings and savings for future years that will be brought back before the MIJB
for approval to ensure future years budgeting is robust. MIJB is acutely aware
of the challenges it faces surrounding both its people and financial resources
which remains a focus within its decision making. Financial and staffing
impacts will be monitored on an individual savings basis and scrutiny will be
provided through the agreed governance structure. The savings have been
RAG-rated (i.e. provided with a Red, Amber, Green risk level) on the basis of
the savings being achieved with particular reference to political environment;
staff and changes in services; capacity; engagement and processes i.e. HR,
procurement etc. With this in mind, 25 are green status, 8 are amber status
and 3 are red status. 
4.23 The table below summarises the progress made by the Health and Social
Care Moray management team in identifying opportunities for
efficiency/savings, which fall under the 3 themes of the MIJB strategy and a
4th heading of savings already implemented. Areas under each theme are
detailed in Appendix 2. Close monitoring of progress will be undertaken via a
range of operational financial governance controls, including the Budget
Savings Oversight Group and will be reported on a quarterly basis during
2025/26. 
Page 36

Page 37

4.24 
Para Ref 2025/26 2026/27  
£ 000’s £ 000’s
Projected Efficiencies/Savings approved
May 2024 
Building resilience 4.25 2,276 261
Home first  4.26 1,445 
Partners in care 4.27 1,635 354
Savings already implemented 4.28 200 
Subtotal Projected Efficiencies  5,556 615
Projected Efficiencies 2025/26   
Building resilience 4.29 350 
Partners in care 4.30 386 
Savings already implemented 4.31 3,175 
Subtotal Projected Efficiencies  3,911 
Total Projected Efficiencies  9,467 615 
4.25 Building resilience covers 11 proposals, predominantly with a RAG status of
green. These proposals cover review and redesign of services: Internal care
at home; Ward 4; GMED (hosted service for Grampian, led by Moray);
relocation/ reduction of lease of buildings and use of pool cars. There are 2
proposals that have a RAG status of red for the review of care and care
purchasing, this is, reviewing all care packages and the use of spot
purchasing. These proposals although challenging will be achievable, a total
of £2.537 million is the expectation over the next 2 financial years, with £2.276
million being achievable in 2025/26. 
4.26 Home first covers 4 proposals; all these proposals have a RAG status of
amber and relate to the review of respite provision; use of proportionate care
model ; the review/redesign of the Learning disability nighttime model of care
delivery and in conjunction with our home first priority to ensure people are
looked after in their own homes as safely as possible and relates to redesign
of community hospitals, to ensure services are fit for purpose. These
proposals although challenging will be achievable, a total of £1.445 million is
the expectation over the next  financial year. 
4.27 Partners in care covers 10 proposals, 7 of which have a RAG status of green
and relate to review of service for day services and adult services; review of
complex and challenging behaviour units; review of step down building based
facilities, prescribing efficiencies, use of digital support and review of contracts
There are 3 proposal that have an amber RAG status which relates to review
of Learning disability service and review of care home bed usage for Learning
disability and the review of the transport contract for children’s and justice
service and adult services. These proposals although challenging will be
achievable, a total of £1.989 million is the expectation over the next 2 financial
years, with £1.635 million being achievable in 2025/26. 
4.28 There are 3 plans that have already been implemented and savings taken in
2025/26. They were for 1 year initially, and have been reviewed for the next
financial year to continue, which relate to no non-essential travel, no non-
essential training and no backfill for secondments. These proposals total £0.2
million all achievable in 2025/26.
Page 37

Page 38

4.29 Building resilience covers 1 proposal which has a green RAG status and
relate to the continuation of the SDS recovery spend to save proposal. This
proposal totals £0.350 million expected to be achieved in 2025/26. 
4.30 Partners in care covers 3 proposals, majority of which have a green RAG
status, these relate to the pharmacy spend to save for medicine reviews in
care homes and a reduction in overtime payments across all. There is 1
amber RAG status relating to the review of the palliative care service in
Moray. These proposals total £0.386 million. 
4.31 Already implemented covers 3 proposals, which are green RAG status that
relates to the continuation of the vacancy factor for NHS services and an
increase for Council services in line with the increase for the pay award, a
refund expected for a contract and a 3.4% cut against a number of services
where there are no other savings proposals which will entail service redesign
but is expected to be achievable during 2025/26.These proposals total £3.175
million. 
Budget Overview
4.32 The MIJB Revenue Budget for 2025/26 is £214.254 million which includes
£14.665 million Set Aside. The detail is provided in Appendix 1 and
summarised below:   
£’000
BUDGET 
Recurring Budget 179,244
Inflationary and Demand Led Pressures 6,021
Recurring Deficit 5,988
Scottish Living Wage (SLW), FPNC & NCHC 3,903
eNIC pressure 2,505
Set Aside  15,638
Additional commitments 544
Use of reserves 
TOTAL BUDGET 213,843  
FUNDED BY 
NHS Grampian Recurring (inc. Set Aside) 110,362
Moray Council (inc. Improvement Grants) 86,222
Scottish Government Additional Funding (£241.5m) 2,549
Children’s & Justice services Additional Funding  544
NHS Grampian 3% Additional Funding 2,262
Reserves balance 45
Scottish Government additional funding for eNIC 1,392
Savings identified  9,467
TOTAL FUNDING 212,843  
BUDGET DEFICIT (1,000)  
FUNDED FROM EARMARKED RESERVES 1,000 
Page 38

Page 39

4.33 Earmarked reserves estimated to be carried forward into 2025/26 are £1.647
million, this included reserves relating to Primary Care Improvement Fund
(PCIF) and Moray Action 15 which will be exhausted by the end of 2024/25.
The balance on the remaining reserves will be reviewed after the 2024/25
year end. 
Financial Risks
4.34 The budget assumptions made within this report carry a degree of financial
risk, meaning that variations that may arise will impact on financial
performance. Acceptance of risk is a necessary part of the budget setting
process. The main risks are summarised: 
• Financial Settlement – the 2025/26 financial settlement is for one year
only and the increased level of funding is required to meet policy
commitments as determined by Scottish Government. There is no
inflationary increase for children’s or adult social care provided by Moray
Council, but for NHS Grampian there is the agreement of a 3% increase
in pay and non pay inflation. Whilst a provision has been made for Local
Authority and NHS Grampian pay increases, the NHS Public Sector Pay
Policy and Local Authority pay award negotiations has not yet been
agreed and there is a risk that this will exceed the provision. Whilst the
benefits of longer-term financial planning are well documented in
assisting the delivery of strategic priorities, at this stage, financial
planning is subject to continuous change and there is a need to adapt to
the changing landscape. 
• The budget pressures identified in paragraph 4.10 are based on
continued discussion and assessment and through monitoring, this
process is reasonably accurate. However, there remains the risk in the
event that inflationary increases and demand driven pressures may
exceed the anticipated cost. There is no provision for increases over and
above the SLW payments for providers. 
• Prescribing costs are a large and volatile part of the MIJB budget with
demographic changes a material contributing factor. Whilst the decisions
to prescribe are made locally, the costs of drugs and agreements to
introduce new drugs are made on a national basis. Provision in the
budget has been made based on analysis undertaken by NHS Grampian
with a range of options provided from Best Case to Best Prediction and
Worst-Case scenario. MIJB are proposing the inclusion of the Best
Prediction scenario with the associated pressure of this option. There is
a risk associated with this option and the IJB will closely monitor this
budget through regular reporting to the IJB throughout financial year
2025/26 and appropriate action taken to mitigate the pressure in year
through continued close working with NHS Grampian, this is being
reviewed not only across Grampian but nationally. 
• Demographic changes - the demographic profile of Moray continues to
show a general rise in population with a specific increase in the age
profile of the population. The associated challenges of providing care for
a rising population where people live with multiple conditions are well
known. These challenges manifest themselves in a financial sense when
we experience issues such as rising numbers for social care packages
Page 39

Page 40

and rising demand for aids, adaptations, and equipment. The increasing
level of complexity of need for some of our clients means that high-cost
care packages may arise during the year for which we have not
budgeted. The same applies to patients who need out of area care and
where a clinical decision has been made that this is in their best
interests. 
• In Primary Care there continues to be a number of continuing challenges
around sustainability of some of our GP Practices with inability to recruit
General Practitioners a common issue. This has necessitated the
Partnership providing support and investment to maintain GP services in
some parts of Moray. We will continue to use the Primary Care
Improvement Fund and other funding streams to support General
Practices and wider Primary Care teams across Moray. 
• The MIJB must also ensure preparedness for the implementation of
national policy and legislation in particular the Health and Care (Staffing)
(Scotland) Act 2019 ensuring safe and appropriate staffing with
implementation from 1 April 2024 and full compliance by March 2025. 
• The savings identified are challenging to achieve fully in the year - the
risk of achieving the savings has been calculated based on the RAG
status, with green assuming will be 90% achieved, amber 80% and red
70% respectively. Using this assumption the savings for 2025/26 could
be £7.961 million, leaving a risk of a potential funding gap, which would
have to be borne by the partners of £1.507 million. All endeavours will be
undertaken to ensure delivery where possible and the Chief Officer and
Chief Financial Officer will continue to work within the tri-partite approach
with finance colleagues in both Moray Council and NHS Grampian. The
implementation of savings also presents an opportunity to redesign
services collaborating with staff and communities. 
4.35  Accounts Commission have released an IJB Finance bulletin 2023/24 on 6
March 2025 which was prepared by Audit Scotland. This summarises the
position for all the IJB’s in Scotland and is attached at Appendix 4. This
provides background information and clarification that the issues facing MIJB
are affecting all IJB’s. One of the key messages from this publication is
around the need to work collaboratively with IJB’s and partners to find ways to
transform services so that they are affordable. 
5.      SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP)) and Moray Integration Joint
Board Strategic Plan 2022 – 2032, ‘Partners in Care’
The approval of a balanced budget for the MIJB is key to the delivery of
health and social care services in Moray in accordance with the Strategic
Plan. 
(b) Policy and Legal
In accordance with the Public Bodies (Joint Working) (Scotland) Act
2014, MIJB is subject to the audit and accounts regulations and
legislation of a body under Section 106 of the Local Government
Page 40

Page 41

(Scotland) Act 1973 and is classified as a local government body for
accounts purposes by the Office for National Statistics. 
(c) Financial implications
The 2025/26 revenue budget (excluding Set Aside) as detailed in
Appendix 1 is £198.205 million. 
The funding allocated to the MIJB by Moray Council and NHS Grampian
and through the Partner bodies from Scottish Government totals
£187.737 million (excluding Set Aside). In addition, the indicative
savings plan for the forthcoming year totals £9.467 million. 
The notional Set Aside budget for Moray’s share of the Large Hospital
Services is currently £14.665 million. The Set Aside budget is provided
by NHS Grampian. 
A balanced budget is presented displaying use of slippage in ear marked
reserves of £1 million, this will need to be funded in 2026/27. 
(d) Risk Implications and Mitigation
The revenue budget for 2025/26 is subject to the following risks: 
• GP Prescribing – represents around 10% of the MIJB core
budget. It is well documented that the Prescribing budget can be
extremely volatile in nature with volume and price increases
potentially leading to substantial adverse variances. 
• Growth and demand in the system, together with service users
with complex care needs are attracting additional financial
challenge. These issues require to be managed within the overall
resource of the MIJB. 
• The need to transform at pace and drive forward opportunities
arising through changes to working practice experienced through
the pandemic. The risk being the ability to capture and embed in a
timely manner. 
• National Care Home Contract for 2025/26 has not yet been
agreed and whilst this will be partly funded from Scottish
Government funding for the £12.60 per hour, this will not fully fund
the increase once agreed. 
• The implications of the cost-of-living crisis and current levels of
inflation, which although are now forecast to decrease continuing
cost increases may mean the provision for inflation may not cover
all the calls upon it. Price inflation may impact on areas where no
provision has been made for inflationary increases and this will
add pressure to budgets. Budget managers will need to control
their expenditure to absorb such pressure if possible and may
have to reduce service levels or identify further savings. 
• This report highlights the anticipated budget pressures at
paragraph 4.10.  It will be necessary to note that budget
Page 41

Page 42

pressures may exceed allocation. This will be closely monitored
and reported accordingly to the MIJB as part of the budget
monitoring reports. 
• With the level of savings required to balance the budget there is a
risk that the budget may not be achieved in line with expectations
for 2025/26. Based on the rag status as in para 4.22, there is a
risk of not achieving the savings in this financial year of £1.507
million, which will require to be borne by the partners of the MIJB. 
(e) Staffing Implications
There are no direct implications in this report. 
(f) Property
None arising directly from this report. 
(g) Equalities/Socio Economic Impact
None arising directly from this report as there is no change to policy. Any
subsequent changes to policy arising from proposals made within this
paper will be considered and Impact assessed as appropriate. 
(h) Climate Change and Biodiversity Impacts
There are no direct climate change and biodiversity implications as there
has been no change to policy. 
(i) Directions
Directions are detailed in para 4.32 above and in Appendix 5. 
(j) Consultations
The Chief Officer, Health and Social Care Moray Senior Management
Team, Operational Management Team, Corporate Manager, Chief
Finance Officer (Moray Council), Deputy Director of Finance NHS
Grampian, the finance teams of both Moray Council and NHS Grampian,
and Caroline O’Connor, Committee Services Officer. 
6. CONCLUSION 
6.1 Legislation requires the MIJB to set its Revenue Budget for the
forthcoming year by 31 March each year. The budget displays a balanced
position. The Section 95 Officer as Chief Financial Officer to the Board
recommends the budget as presented at Appendix 1. 
6.2 Close monitoring of the continuing effects of the increasing demands on
services will be required in order to ensure the MIJB can remain within
the funding allocation provided by NHS Grampian and Moray Council. 
Author of Report: Deborah O’Shea, Chief Financial Officer
Background Papers:  with author
Ref: 
Page 42

Page 43

APPENDIX 1MORAY INTEGRATION JOINT BOARD
JOINT FINANCE REPORT APRIL 2025 -MARCH 2026
Para Approved Annual
Ref Net Budget
£'s
2025-26
Community Hospitals 6,600,692                   
Community Nursing 6,484,911
Learning Disabilities 17,865,037
Mental Health 11,945,985
Addictions 1,221,222
Adult Protection & Health Improvement 265,307
Care Services provided in-house 25,594,449
Older People & PSD Services 25,172,334
Intermediate Care & OT 1,904,400
Care Services provided by External
Contractors 2,203,164
Other Community Services 10,220,408
Admin & Management 1,401,173 
Other Operational Services 1,253,043
Primary Care Prescribing 18,727,506
Primary Care Services 20,020,057
Hosted Services 5,906,873
Out of Area 720,131
Improvement Grants 1,060,200
Childrens Services 19,482,682
Total Moray IJB Core 178,049,572
Other recurring Strategic Funds in the ledger 1,194,806
Total Moray IJB Including Other Strategic
funds in the ledger 179,244,378
Other resources not included in ledger under
core and strategic: 18,960,862
Total Moray IJB (incl. other strategic funds)
and other costs not in ledger 198,205,240
Set Aside Budget 15,638,000
Overall Total Moray IJB 213,843,240
Funded By:
NHS Grampian 113,215,806
Moray Council 90,159,571
Savings identified 9,467,863
Use of ear marked reserves 1,000,000
IJB FUNDING 213,843,240
Item 7.
Page 43

Page 44

Page 44

Page 45

Progress to
MIJB proposed savings APPENDIX 2
100%
Ref Service Brief Description Full year effect £000s  Saving expected
for 2025/26 
Saving confident
to be achieved in
2025/26
Progress towards
Implementation
Planned
Implementation
Date
Implementation
Date Risk Level Risk Description
BUILDING RESILIENCE                             3,409.00                    2,626.00                    2,626.00
1 Internal Care at Home review Review of Internal care at home
including redesign                               122.00                      122.00                      122.00  1/4/2025 Green Timeline
Continuation of 24/5 saving
4 &5 Ward 4 redesign of service Cease locum use - gradual &
implement 2 CESR fellows                          1,044.00                      261.00                      261.00 Jan-26 Green
Recruitment
Taking longer than expected and not
both vacancies at the same time
continuation of 24/5 saving
6,7,8 GMED redesign & health village relocation
Relocation from Health Village,
redesign of clinical & admin
staffing model, Ad astra Ehealth
system
110.00                      110.00                      110.00  Apr 25 Green
Workforce Impact
Parking
Footfall dependent on location
Delayed for 3 months
9 Pool car vs expenses review
Review into all teams transport
and expenses to evalaute best
options                                 
20.00                         20.00                         20.00 0% Apr-25 Green Time and capacity – will be spend to
save in the first instance
10,12 Cessation of leases and relocation Southfield, Strathisla dental
practice                                 63.00                         63.00                         63.00 61% Apr-25 Green none
Lease cessation delayed by a month
14 &15 Review of Care & Care Purchasing spot purchasing & review care
packages                          1,700.00                  1,700.00                  1,700.00 Apr-25 Red
Reviews commenced in Jan 2025 and
this is the continuation of that work
already started
42 *new SDS recovery Review packages to increase
recovery                              350.00                      350.00                      350.00 Apr-25 Green Reviews are not completed timeously
HOME FIRST                             1,445.00                    1,445.00                    1,445.00
16 Respite provision
Review into planned and
emergency respite - change in
model                              
413.00                      413.00                      413.00 0% Apr-25 Amber
Time to implement fully
Care home bed shortage
Care Home Provider monopoly
Competition from other boards
Time heavy paperwork for care homes
17 Proportionate  care Redesign model                               555.00                      555.00                      555.00 0% Apr-25 Amber
Time to fully implement
Needs full EQIA
Service user safety
Internal progressing slower than
expected and external delayed until
next financial year
Item 7.
Page 45

Page 46

18 Night Time Responder (LD) Redesign LD nighttime model of
care delivery                               277.00                      277.00                      277.00 0% Apr-25 Amber
Organisational change
More complex than expected and
delayed from 24/25
20 Community hospital redesign Redesign of inpatient services
supporting Home First                               200.00                      200.00                      200.00 0% Apr-25 Amber
Contentious – public opinion
Reputational damage
Impact on secondary care
Progressing but other pressures on the
budget
PARTNERS IN CARE                             3,459.00                    2,021.00                    2,021.00
23 Commissioning and contracts review Review of all contracts and
redesign of provisions                              350.00                      350.00                      350.00 Apr-25 Green
Time and capacity, reputational
damage
Balance of needs versus costs
Continuation of last years work with
providers
21,24 Day Services review
Review into day services and
provsion, including building based:
co-location options, MRC catering
& infrastructure                              
220.00                      220.00                      220.00 Apr-25 Green
Reputational damage
Impact on Unpaid carers
Downstream impact
Impact on MH of service user
25 Complex & challenging behaviour unit Review Review into Woodview and change
management                               657.00                      159.00                      159.00 Apr-25 Green Organisational change, continuation of
24/5 proposal
26,27 LD review & review of care home bed usage Internal review and redesign,
review care home bed utilitsation                               736.00                      491.00                      491.00 Apr-25 Amber
Any care package savings has
implications for safety. Requires care
home registration change and agreed
costings . Continuation of 24/5 saving
28 Review of step down building based facilities Review into model of care                               118.00                         69.00                         69.00 Apr-25 Green
Lack of step down facility
Impact on acute /secondary care/
primary care
Continuation of 24/5 saving
30,
43*new Prescribing efficiencies
Medication cessatio,switches
within GP services and work with
Care Homes
669.00                      169.00                      169.00 Apr-25 Green
Pan Grampian approach may take tme
to implement
Progressing but other pressures on the
budget
Continuation of 24/5 saving
31 Digital Support efficiencies - NO TEMPLATE
REQUIRED
As part of DHI (Moray Growth Deal
and Analogue To Digital Proposal)                              100.00                      100.00                      100.00 Apr-25 Green Pan Grampian approach may take time
to implement
33 Transport contract
Review fo how we contract for
transport for childrens and adult
services
292.00                      146.00                      146.00 Oct-25 Amber Time and resources
44 *new Reduction in overtime reduce the amount spent on
overtime during the year                              200.00                      200.00                      200.00 Apr-25 Recruitment levels
46 *new Review of palliative care services
Review of provision of palliative
care in Moray to improve
outcomes
117.00                      117.00                      117.00 Apr-25 Amber
Contentious – public opinion
Reputational damage
Impact on secondary care
Page 46

Page 47

ALREADY IMPLEMENTED                             3,376.00                    3,376.00                    3,376.00
38 No non-essential travel (I year) Non essential travel ban (out of
area)                                  30.00                         30.00                         30.00 Apr-25 Green Impact on staff development
38 No non-essential training (I year) Non essential training ban
(conference attendance etc)                                 20.00                         20.00                         20.00 Apr-25 Green Impact on staff development
38 No backfill for secondments (1 year) Maternity leave- case by case
consideration via RMG                               150.00                      150.00                      150.00 Apr-25 Green Displacement of some staff, service
pressures
41 *new Vacancy target NHS & increase on Council in line with
pay award increase Already implemented                           1,135.00                  1,135.00                  1,135.00 Apr-25 Apr-25 Green continuation of previous year
47* new Healthcare system reduced payment Refund due for system                                 20.00                         20.00                         20.00 Apr-25 Green Implemented - refund expected
48* new 3.42% budget cut on other services not included
above
3.42% reduction in expenditure
across a variety of budget
headings
2,021.00                  2,021.00                  2,021.00 75% Mar-24 Mar-24 Green Implemented - Physio wait list
TOTAL                          11,689.00                    9,468.00                    9,468.00
Page 47

Page 48

Page 48

Page 49

APPENDIX 3
Predicted Prescribing Budget Resource Requirements 2025-2026 
Prescribing pressures continue to grow, with a current 5% increase in overall costs. There is a net predicted need for a budget resource of £23,824m, for
2025-26. 
This paper provides information on the predicted prescribing budget resource requirements for 2025-206, alongside key drivers of growth and mitigations
regarding costs. 
Current forecasting indicates that Moray will end the 2024-25 year with a prescribing deficit of -£3,131,000 which will be further affected by identified
factors and estimates for these factors. Historic limited budget uplifts have resulted in significant historic overspends. 
Appendix A highlights a trend of increasing void between actual budget and actual spend.2024-25 spend has not accurately reflected estimates due to
factors such as stabilisation of growth, multiple medicines shortages and price changes. Medicines shortages present unpredictable risk to expenditure
estimates and cannot be mitigated for. 
There has been unprecedented growth in items and costs across all boards in Scotland (Appendix B). This has been further impacted also by the increase
in Acute prescription requests by patients. There are wide ranging factors affecting performance. 
Resource assessment for prescribing has been undertaken for 2025-26. This was done using the approach adopted in previous years, which estimates
growth in volume and spend in the coming year, and also offsets these with generic savings and approved efficiency plans. The key themes and data
presented here are taken from the more comprehensive ‘Health and Social Care Prescribing Budget Supporting Information and Data for 2025/2026’, which
has been scrutinised and approved by the multidisciplinary / cross sector Grampian Area Drug and Therapeutics Committee (GADTC) and NHS Grampian
Primary Care Prescribing Group. 
A breakdown of the components of the Moray requested budget for 2025-26 is provided in Appendix C. 
A growing and ageing population demographic has had an effect on prescribing volumes and subsequent costs as cost per patient rises with age: 
• NRS figures now show that 23% of Moray population are now over age 65 which carries much higher cost per patient (Appendix D). Mitigation is
to offer Primary and continue to offer Secondary prevention and adopt Realistic Medicine approaches to care. 
Item 7.
Page 49

Page 50

Volume growth for 2024-25 was still highly variable due to multiple factors out with our control, including changes in volumes and treatments and
continuing post-Covid variation in operating levels across Primary and Secondary care. In 2024-25 we had unprecedented growth in items and costs
exceeding traditional pre-pandemic rates of growth 
Following Grampian’s increasing trend over time, the number of items and cost trends per financial quarter show an increase, as does the cost per item
(detailed in Appendix E). 
The need for sustainable and environmentally friendly prescribing is a consideration.
The following are the main financial risks:
Scottish Drug Tariff Pricing and Medicine Shortages: Volatility within pricing of several widely used medications means that prices are likely to remain high
in 2025-26. 
There remains scope to ensure that all new medicines are prescribed generically even before generic availability to ensure smooth transition and cost
effectiveness. There is a risk in that the future prices for generic medicines, and associated reimbursement levels set within the Scottish Drug tariff, remain
high and difficult to predict. The Scottish Government sets the Scottish tariff prices. They are committed to rebalancing Community Pharmacy contractor
payments by reducing the emphasis on margin share and moving these payments to within the guaranteed global sum. 
Generic shortages arise from increase in demand, lack of active ingredient, quality control and manufacturing delay, etc. These result in more costly
prescribing e.g. more expensive sometimes unlicensed medication choices, as well as impacting pharmacy admin and clinician time required. 
The global supply chain of medication remaining fragile continues to be a significant sourcing problem for Community Pharmacy within a wide range of
medicines for a variety of conditions. Such shortages can lead to unpredictability in the cost per item during the year. 
The growth in consumption of medicines, strengthened approaches to medication review and associated reductions in polypharmacy. The variations in
volume are partially related to changes in patient behaviours, as well as changes in capacity within Primary Care. Repeat prescribing increase has
continued, and acute prescribing and outpatient/medication requests are variable corresponding to service provision and patient flow. 
In terms of Primary Care rebates, a patient access scheme system provides the NHS in Scotland with post-use discounts on spend on specific medicines
has remained generally stable, but there remains a risk that these rebates may change or be removed.  N.B. these discounts accrue to the individual Health
and Social Care Partnerships (HSCPs) based on spend and so are offset within prescribing expenditure estimates. 
Page 50

Page 51

Sustained and increased pressures within GP practices and requirement of Pharmacotherapy teams to deliver Pharmacotherapy Memorandum of
Understanding (MOU) work has reduced time availability for medicines management cost efficiency work by Pharmacists and GPs. 
National/international research, change to evidence based guidance or change to government policy. Many new medicines and new indications/licensing
change for existing medications, from new protocols, are likely to have a significant clinical and subsequent financial impact e.g. Rimegepant in
management and prevention of Migraine,  and Attention Deficit Hyperactivity Disorder (ADHD ) treatment in adults.  Appendix F highlights examples of
medicines predicted to cause significant cost impact in Grampian. The list is not exhaustive and difficult to predict so will continue to be monitored. 
Changes in delivery of local services and patient pathways, have the potential to affect medicine use e.g. transfer of prescribing from secondary care to
primary care has a financial impact. 
Extended hospital procedure waiting lists also requires extended prescribing time and increased prescribing costs while patients are on the waiting list. 
Summary of Risk Mitigation 
Patent Expiry
On expiry of a drug patent, increasing competition can drive down market prices where there are alternative manufacturers’ competition. This relies on
manufacturers to manufacture the newly off patent medicine. On patent expiry there is also opportunity to review the preparation prescribed and change to
generic or more cost effective drug. 
Prescribing Cost Efficiencies and Cost Avoidance
There is an urgent need and opportunity to deliver several cost efficiencies. An actionable tracker (in line with Grampian Primary Care Prescribing Group)
holds some appropriate cost efficiency work for the pharmacy team to complete. Moray Pharmacotherapy staff annotate work when completed. This work
has been challenging in terms of workforce capacity and workload pressures. 
Spend to Save Initiative
Following a brief intervention in 2023-24 Considerable cost savings work has now been undertaken in 2024-25 under a Moray Pharmacy Spend to Save
Prescribing Cost Effectiveness Strategy. This involved some GP practice Clinician collaboration as well as seconded Specialised Pharmacy Technician
input to drive progress. Recent program of cost efficiency work from June 2024 to end Feb 2025 has provided annualised prescribing savings of £648,242. 
The work involved visits to GP practices and also some secondary care discussions and managed interventions via dedicated focused work. Prescribing
reports were utilised. As well as therapeutic switches, prescribing of non-formulary and low clinical value items was scrutinised and discussions were had
Page 51

Page 52

with GPs, practice clinicians and patients. From discussions with prescribing staff within practice and secondary care indirect savings were achieved by
changing prescribing processes. Reducing over ordering and medicines wastage also helped maximise prescribing cost efficiency. 
A Grampian primary care prescribing efficiencies agreement was also put in place for GPs with the aim of medication review interventions involving drug
therapeutic switches and generic switches. There were 3 levels of work stream and GPs suitably actioned some level 3 aspects.   Medicines management
team have provided guidance and support for prescribers re delivery of cost efficient prescribing in GP practices which has been a huge benefit to our
intervention also.  A Grampian Primary Care Prescribing group workbook has been developed which details information to guide efficiency, generic,
preferred brand switches and a stop list with or without alternative re low clinical value prescribing. 
Scriptswitch
This is a communication tool providing electronic advice messages to the prescriber. We continually review these messages to ensure that Scriptswitch
underpins and delivers many cost saving initiatives. This can be in the form of a targeted therapeutic drug switch, reducing waste by dose optimising, as
well as safety alerts. In 12 months, Moray generates approximately £85,000 savings via Scriptswitch, as well as adding influences prescribing for future. 
Generic Savings Work
On our actionable tracker, we include work from the Practice Generic Savings Quarterly Report, and all teams are given details on medications not
prescribed generically and the costs involved, although admittedly this is less than previous impact. The teams are requested to review and annotate
changes made. 
Extraordinary Prescribing Report
Moray Pharmacotherapy Team Management check reports and request copies of prescriptions in order to identify where pricing and reimbursement
overpayments may require to be claimed. This can be from specials medications or normal prescribing. Time capacity more recently prevents us collating
much of this work, however as an example in 2022, we claimed back £23,545 via pricing recovery. 
Tighter Control of Specials Items
Automatic authorisation of specials items of £100 or less has been removed to allow more scrutiny of the specials prescribing and payments. 
Medicine Care and Review – Serial Prescribing
Use of this serial prescription service, and now also in care homes, has the potential to reduce wastage as prescriptions are issued at correct intervals,
which prevents any unnecessary stock piling. 
The Grampian Formulary
Page 52

Page 53

A Grampian Formulary tool is installed in all Moray GP Practices to steer the appropriate cost-effective prescribing choices. There remains opportunity to
identify and amend non formulary prescribing.  
Page 53

Page 54

Appendix A – Moray Budget Predictions, Budget Allocation and Actual Spend  
Page 54

Page 55

Appendix B – NHS Grampian vs Other Health Boards
Figure 1 – Items Trends, NHS Scotland Mainland Health Boards 
Page 55

Page 56

Figure 2 – Cost Trends, NHS Scotland Mainland Health Boards 
Page 56

Page 57

Appendix C – Moray Health and Social Care Partnership:
Summary and Budget Estimates
Tables A and B: Estimates for Prescribing
Table A: Growth, Expenditure and Savings – Primary Care Prescribing
Factor Low estimate  Medium
estimate
High estimate 
£000’s £000’s £000’s 
Level of  Level
of 
Level
of 
Add over accrual impact 
from 2024/25 129  129  129 
Demographic impact 0  0  0 
Volume estimate
movement 661  770  881 
Price impact from
2024/25 39  39  39 
Price impact further
movement 0  231  346 
ScriptSwitch allocation
and communications  44  44  44 
Discount income -12  -16  -18 
New Medicines affecting
Primary care 0  0  0 
Existing Medicines
affecting Primary Care 544  543  544 
Scottish Tarriff discount %
reduction  0  0  0 
Further Prescribing
Efficiencies  0  0  0 
Total Movements 1404  1740  1965 
Page 57

Page 58

Table B: Overall Moray HSCP Suggested Primary Care Prescribing
Budget Requirement 2025/26
Factor Low Estimate Medium
Estimate
High estimate 
£000’s £000’s £000’s
Full year Budget 2024/25 18728  18728  18728 
Predicted Year End Out-
turn 2024-25 21859  21859  21859 
Total Movements 1404  1740  1965 
Suggested Total budget 
2025/26 23263  23599  23824 
% increase on 2024/25
budget 24.2  26.0  27.2 
% increase on predicted 
2024/25 expenditure 6.4  8.0  9.0 
Table C: Moray HSCP Suggested Primary Care Core HSCP Service
Requirements 2025/26
Full year
budget
2025/26
£000’s
Estimated
Out-Turn
2025/26
£000’s
Suggested
Budget
2025/26
£000’s
Uplift on
2025/26
Budget
%
Uplift on
2025/26
Out-turn
%
264 323 363 37.3% 12.3% 
Table D: Hosted Services Impact by IJB
Hosted Sector 
2025/26
Total uplift
£000’s
Moray IJB
impact 2025/26
£000’s
Moray IJB %
shares
City Sexual Health -17 -3 18
City Intermediate Care 46 2 4
Moray GMED 66 12 18
Shire HMP Grampian* 634 112 18
Shire Police Custody 0 0 18
Total 730 122 
*Under review pending investigation into HepC medicine recharges.
Page 58

Page 59

Appendix D – Population Calculations
Rationale for Financial Updates Associated for Population Changes 
The age profile of each HSCP is different, this will result
in different needs and therefore different prescribing
patterns. 
Aberdeenshire and Moray have a greater proportion of
their population aged 65 and over. 
The age structure of council areas, mid-2023, can be
seen to the right. 
Page 59

Page 60

Table 1 – Moray Estimated Costs based on Population Predictions using Cost per Patient per Age Band 
Page 60

Page 61

Appendix E – Items and Cost Performance Trends
Figure 1 – Number of Items Prescribed in General Practice (GP10, GP10N, GP10P (practice pharmacist) & GP10A) 
Page 61

Page 62

Figure 2 – Cost of Items Prescribed in General Practice (GP10, GP10N, GP10P (practice pharmacist) and GP10A) 
Page 62

Page 63

Appendix F – Primary Care Growth of Medicines Predictions (existing and new medicines)
Page 63

Page 64

Page 64

Page 65

Page 65

Page 66

Page 66

Page 67

Page 67

Page 68

Page 68

Page 69

Page 69

Page 70

Page 70

Page 71

Page 71

Page 72

Page 72

Page 73

Page 73

Page 74

Page 74

Page 75

Integration Joint
Boards
Finance bulletin 2023/24
Prepared by Audit Scotland
March 2025
APPENDIX 4Item 7.
Page 75

Page 76

Integration Joint Boards | 2
Contents
Key messages 3
Introduction 5
Context 6
Financial performance 7
Accessibility
You can find out more and read this report using assistive technology on
our website www.audit.scot/accessibility
Page 76

Page 77

Key messages | 3 
Key messages 
1 Integration Joint Boards’ (IJBs) finances continue to be precarious. IJBs
2023/24 funding has increased in real terms compared to 2022/23 but there is
a concerning picture of continued overspending, depletion of reserves and
required savings being met through one-off rather than recurring savings. 
2 The majority of IJBs reported a deficit on the cost of providing services
requiring unplanned use of reserves and additional contributions from partner
bodies:
• Total reserves held by IJBs have reduced by 40 per cent in 2023/24.
Contingency reserves have almost halved, limiting IJBs ability to address
future deficits. Nine IJBs now do not hold any contingency reserves
reducing their financial flexibility and increasing the risk to their financial
sustainability.
• NHS boards and councils face significant financial challenges themselves
and IJBs cannot continue to rely on their partners being able to find
additional money to support them during the year. IJBs need to agree
budgets that are realistic and transparent and to have strategies in place to
manage in-year risks.
3 The majority of the total planned savings were achieved, but a substantial
proportion were achieved on a one-off basis meaning these non-recurring
savings need to be carried forward and covered each year to balance future
budgets.
4 The financial position is set to worsen with a projected funding gap of £457
million in 2024/25. The budget process needs collaboration with partners and
candid conversations with communities about the impact of the savings
needed to set a balanced budget. The budgets and proposed savings need to
be realistic and achievable. 
5 A continued high turnover of chief officers and chief finance officers adds to
the risks around effective strategic planning and decision-making.
Page 77

Page 78

Key messages | 4 
6 IJBs need to be working collaboratively with each other and with their NHS
and council partners to find ways to transform services so that they are
affordable. Investment in prevention and early intervention is needed to help
slow the ever-increasing demand for services, the cost of more complex care
and, improve the experience and outcomes for people.  
Page 78

Page 79

Introduction | 5
Introduction
1. Integration Joint Boards (IJBs) are responsible for the governance,
planning and resourcing of social care, primary and community healthcare
and unscheduled hospital care for adults in their local area. The Public
Bodies (Joint Working) (Scotland) Act 2014 (the Act) requires the 32
Scottish councils and 14 territorial NHS boards to work together in
partnerships to integrate how social care and community healthcare
services are provided. IJBs were created as part of the Act. More
information about the role of IJBs is set out in a short video available on
our website What are Integration Joint Boards?
2. On behalf of the Accounts Commission, Audit Scotland has undertaken
an analysis of the IJB annual accounts for 2023/24 and the annual audit
reports produced by local auditors. The data and analysis is published on
the Audit Scotland website as an interactive online tool – The IJB Finance
bulletin 2023/24.
3. The interactive online tool allows users to explore the financial
performance of their local IJB, as well as compare individual IJBs. We
anticipate this will be a useful resource for IJBs, their stakeholders and
members of the public. It includes data on the funding and income and
reserves position, outturn budget position, savings performance and
financial outlook. The tool also includes local and national contextual data
from the 2022 census that illustrates the increasing population pressures
nationally and the significant variation across Scotland. Accompanying
guidance on how to use the online tool is also available on the Audit
Scotland website.
4. This document provides a summary of the national level messages from
the online Finance bulletin.
5. Our findings are based on the 2023/24 annual accounts for 29 IJBs (27
audited and two unaudited), 2023/24 annual audit reports, as well as IJB
budget documentation. The accounts for East Dunbartonshire IJB were
unavailable at the time of publication.
6. We have published the Finance bulletin as early as possible to help
inform budget-setting discussions. Further information will be added to the
data tool as it becomes available. By Autumn 2025, it will also include
performance and outcome data.
Page 79

Page 80

Context | 6
Context
Demographic shifts are driving an increase in the demand and
complexity of health and care needs
7. The pressures on Scotland's social care and healthcare services are
escalating, with higher demand, workforce difficulties, and financial strains,
further aggravated by inflationary cost pressures.
8. Scotland’s wide-ranging population density also presents different
logistical and workforce challenges, along with associated cost pressures,
to providing services.
9. The 2022 Census sets out how the underlying factors impacting on the
demand for social care and healthcare services have changed since 2011.
2022 Census data Movement since 2011
census/range
Population 5.4 million 2.7% increase
Proportion of population aged over 65 20% Increasing from 17%
Population density (residents per km2) 70 Varying from 9 (Eilean Siar)
to 3,555 (Glasgow)
Percentage of people who reported
having bad or very bad health 7% 27% increase
Percentage of people with a long-term
illness, disease or condition 21% Increasing from 19%
Percentage of population that provide
unpaid care 12% 28% increase
Source: Scotland’s Census 2022
10. These societal changes result in an increased resource demand for
social care and healthcare services and impact on the financial
sustainability of these services as we set out later in this report.
Page 80

Page 81

Financial performance | 7
Financial performance
The financial health of IJBs continues to weaken and there are
indications of more challenging times ahead
IJB funding has increased in real terms compared to
2022/23 
11. IJBs receive their funding as annually agreed contributions from their
council and NHS board partners. Funding is largely received to cover in-
year expenditure on providing services but can also be received for
specific services and national initiatives to be funded in future years. The
funding split between NHS and council partners remains around 70 per
cent from NHS boards and 30 per cent from councils.
12. There has been a four per cent real-terms increase in IJB funding
between 2022/23 to 2023/24 (Exhibit 1).
Exhibit 1
IJB Funding and income 2020/21 – 2023/24
Funding increased by four per cent in real terms in the past year
Note: * Position/movement excluding East Dunbartonshire IJB as accounts are unavailable.
Source: Audited accounts
£10,577 £10,792 £9,996
£11,841
£507 £960
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
11,000
12,000
2020/21 2021/22 2022/23 2023/24*
£ million
Partner contributions Covid-19 funding
Page 81

Page 82

Financial performance | 8
The majority of IJBs reported a deficit on the cost of
providing services requiring additional contributions from
partner bodies and the unplanned use of reserves
13. Twenty-four IJBs reported a deficit on the cost of providing services
with the majority (18) reporting a deficit between zero and three per cent
(Exhibit 2, page 9).
14. Of the 24 IJBs reporting an operating deficit, 11 received additional
contributions from partner bodies to cover the year end overspend and 16
made an unplanned drawdown from reserves. A number of IJBs will have
received additional partner contributions during the year that will not be
captured by this analysis. These additional in-year contributions can arise
for a variety of reasons, including specific one-off cost pressures not
anticipated during budget-setting.
15. Five IJBs reported an operational surplus, down from 19 in 2022/23.
Reasons reported for surplus’ included delays in the launch of some
transformation and improvement projects and challenges in health and
social care recruitment.
16. Recruitment and retention issues facing the sector persist, but the
related savings from holding vacancies, that contributed to the majority of
operational surpluses in 2022/23, are being outstripped by inflationary cost
pressures and, reflecting the workforce pressures, a higher spend on
agency/locum/bank staff. Other financial pressures driving the increase in
the costs of providing services include increasing demand for services,
prescribing costs and pay inflation.
Page 82

Page 83

Financial performance | 9
Exhibit 2
Operational surplus/deficit as a proportion of the 2023/24 net cost of service
The majority of IJBs reported a deficit on the cost of providing services in 2023/24 requiring
additional contributions from partner bodies and the unplanned use of reserves.
Note: * Comparable data for 2022/23 was not available for these IJBs. ** East Dunbartonshire
IJB accounts unavailable.
Source:  Audited accounts, auditor returns
The majority of the total planned savings were achieved,
but a substantial proportion was achieved only on a one-off
basis
17. There was a 154 per cent increase in the savings target between
2022/23 and 2023/24, increasing to £214 million. Overall, IJBs achieved
79 per cent of their planned savings targets in 2023/24. This was down
-10% -5% 0% 5% 10%
Shetland
Orkney*
Dumfries & Galloway*
Falkirk
Eilean Siar
Midlothian
Aberdeen
East Renfrewshire
Fife
Aberdeenshire
Scottish Borders
East Ayrshire
Perth and Kinross
North Ayrshire
Moray
East Lothian
Glasgow
Dundee
Clackmannanshire & Stirling
Edinburgh*
West Dunbartonshire
Inverclyde
West Lothian
Renfrewshire
East Dunbartonshire**
Argyll & Bute
South Lanarkshire
Angus
North Lanarkshire
South Ayrshire
2022/23
2023/24
Page 83

Page 84

Financial performance | 10
from 84 per cent in 2022/23. Only seven IJBs achieved all of their savings
target with three IJBs achieving less than half their target (Exhibit 3, page
11).
18. Fifty-seven per cent of savings were achieved on a recurring basis
with the remaining 43 per cent being achieved on a non-recurring basis.
The non-recurring savings will be carried forward to be found again in
future years.
Page 84

Page 85

Financial performance | 11
Exhibit 3
2023/24 Savings performance
79 per cent of total planned savings were achieved in 2023/24, compared to 84 per cent in
2022/23.
Note: * In the absence of the 2023/24 East Dunbartonshire IJB accounts, the 2022/23 Net Cost
of Service was used.
Source: 2023/24 Audited accounts, auditor returns
0.0% 1.0% 2.0% 3.0% 4.0% 5.0%
North Lanarkshire
Angus
Inverclyde
Perth and Kinross
Renfrewshire
Clackmannanshire & Stirling
South Ayrshire
Orkney
Scottish Borders
East Ayrshire
East Dunbartonshire*
Glasgow
North Ayrshire
Moray
East Renfrewshire
Fife
Dundee
Shetland
Aberdeen
West Lothian
Argyll & Bute
Edinburgh
West Dunbartonshire
Eilean Siar
Falkirk
Dumfries & Galloway
Savings target as a proportion of the net cost of service
Savings achieved Savings target + target amount
£23.2m
£1.4m
£13.5m
£7.9m
£20.7m
£8.9m
£6.6m
£9.4m
£2.0m
£5.1m
£21.4m
£7.1m
£4.1m
£5.0m
£21.5m
£3.9m
£5.2m
£2.5m
£2.4m
£2.4m
£2.5m
£3.3m
£4.4m
£1.3m
£0.9m
£2.7m
85%
59%
146%
71%
106%
83%
97%
79%
57%
100%
53%
39%
66%
94%
100%
64%
61%
100%
85%
31%
95%
85%
75%
100%
100%
57%
100%
Page 85

Page 86

Financial performance | 12
19. IJBs achieved 79 per cent of their planned savings target in 2023/24.
Over two-fifths of this were achieved on a non-recurring basis. This means
that these savings will be carried forward to be found again in future years.
Identifying and achieving savings every year on a recurring basis, and
moving away from relying on one-off savings, is essential for IJBs to
maintain financial sustainability.
Total reserves held by IJBs have reduced by 40 per cent in
2023/24. 
20. By the end of 2023/24, IJBs reported a reduction in their total level of
reserves, decreasing by 36 per cent between 2022/23 and 2023/24 (40
per cent real-terms reduction). Part of the reduction relates to the use of
ringfenced reserves to support Scottish Government national policy
objectives (Exhibit 4).
Exhibit 4
Total reserves by year
Total reserves held by IJBs have reduced by 40 per cent in real terms in 2023/24.
Note: * 2023/24 position/movement excludes the East Dunbartonshire IJB position.
Source: Audited accounts 
£-
£200.00
£400.00
£600.00
£800.00
£1,000.00
£1,200.00
£1,400.00
2020/21 2021/22 2022/23 2023/24
Millions
Ringfenced/Earmarked reserves Contingency reserves Covid reserves
Page 86

Page 87

Financial performance | 13
Contingency reserves have almost halved, limiting IJBs
ability to address future deficits
21. Contingency reserves have almost halved (49 per cent real-terms
reduction) and now represent 0.8 per cent of the total Net Cost of Services
(down from 1.6 per cent). These are reserves that are held but have not
been earmarked for a specific purpose and are often used to mitigate the
financial impact of unforeseen circumstances (Exhibit 5).
Exhibit 5
2023/24 year end IJB reserves as a proportion of the net cost of services
Over half of all IJBs had contingency reserve levels of less than one per cent of net cost of
services.
Source: Audited and unaudited accounts
0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0%
Aberdeenshire
Midlothian
Fife
East Lothian
Shetland
Edinburgh
East Renfrewshire
Moray
Perth and Kinross
North Ayrshire
Dumfries & Galloway
Aberdeen
West Lothian
East Ayrshire
Clackmannanshire & Stirling
Scottish Borders
Argyll & Bute
Dundee
Glasgow
Orkney
South Lanarkshire
South Ayrshire
Renfrewshire
Falkirk
West Dunbartonshire
North Lanarkshire
Angus
Inverclyde
Eilean Siar
Ringfenced/Earmarked reserves Contingency reserves
Page 87

Page 88

Financial performance | 14
22. One IJB (Aberdeenshire) utilised all their reserves in year, meaning
that any future overspend position would require additional funding from
partner bodies.
23. Four IJBs utilised all their contingency reserve in year, bringing the
total number of IJBs without any contingency reserves, at the end of
2023/24, to nine.
Financial sustainability risks have been identified by
auditors in the vast majority of IJBs
24. The majority of auditors raised financial sustainability risks as part of
their annual audits of IJBs. The risks identified included the reliance on
non-recurring sources of income, such as reserves and one-off savings, to
meet overspends.
2023/24 Audit
Financial management risks identified* 22%
Financial sustainability risks identified* 96%
Medium-term financial plan in place** 90%
Accounts presented within agreed timetable** 83%
Unmodified opinion* 100%
IJBs reporting turnover in senior officer roles (CO/CFO)** 57%
IJBs who agreed their 2024/25 budget prior to the start of the financial year** 87%
Note: * Based on 27 IJBs, where Annual Audit Reports were available. ** Based on all IJBs.
Turnover figures include IJBs with interim Chief Officers (CO)/Chief Finance Officers (CFO) in
place.
Source: Annual Audit Reports, IJB budget papers, Medium-term financial plans
25. Other financial sustainability risks highlighted by auditors included:
• Reserves level falling below minimum required as per their
individual reserves policies. In one case, the general reserve has
been depleted in full.
• Undeveloped/underdeveloped plans for the achievement of
recurring savings to allow IJBs to reach a balanced financial
position.
Page 88

Page 89

Financial performance | 15
• Additional contributions being required from IJB partners to meet
cost pressure.
• Inability to reduce reliance on agency and locum staff due to
ongoing recruitment challenges.
26. Financial management risks identified included:
• Inaccurate information provided or not presented in line with
regulations.
• Insufficient detail provided to allow the reader to fully assess the
board’s overall performance.
• Financial forecasting requiring more accuracy.
• Requirement to enhance the reporting to provide greater clarity
regarding the underlying IJB budget and performance against the
budget during the year.
Instability of leadership continues to be a challenge for
IJBs
27. Over half of IJBs reported a change of Chief Officer or Chief Finance
Officer in 2023/24. We previously reported that half of IJBs reported a
change in senior leadership across 2021/22 and 2022/23.
28. The leadership and strategic vision of senior officers is crucial in the
strategic planning and decision making required to drive much needed
transformation change. Instability in leadership teams has the potential to
disrupt strategic planning and the leadership capacity to bring about the
fundamental change required to address the growing scale of challenges
facing IJBs.
The projected financial position is set to worsen
29. 2024/25 budget-setting revealed that the projected funding gap for
IJBs has increased again to £457 million (£357 million for 2023/24)
(Exhibit 6, page 16).
30. For 2024/25, 16 of the 30 IJBs agreed a balanced budget before the
start of the financial year. Delays in the agreement of savings plans and
NHS partner funding were the most common reasons for balanced
budgets not being agreed at the start of the financial year.
Page 89

Page 90

Financial performance | 16
Exhibit 6
IJB funding gaps as a proportion of 2023/24 net cost of services
IJB annual accounts and budget papers identify a 28 per cent increase in the overall projected
funding gap between 2023/24 and 2024/25.
Note: * In the absence of the 2023/24 East Dunbartonshire IJB accounts, the 2022/23 Net Cost
of Service was used. 
Source: IJB budget papers, auditor returns
Reliance on non-recurring sources of income is not
sustainable
31. At the time of the 2024/25 budget-setting, nine per cent of the
projected funding gap was planned to be bridged using non-recurring
reserves (Exhibit 7, page 17).
0% 2% 4% 6% 8% 10% 12%
Scottish Borders
South Ayrshire
Angus
West Lothian
North Ayrshire
Perth and Kinross
Argyll & Bute
East Dunbartonshire*
West Dunbartonshire
Orkney
East Lothian
Fife
Falkirk
Moray
Eilean Siar
2024/25 gap as proportion of Net Cost of Service
2023/24 gap as proportion of Net Cost of Service
Page 90

Page 91

Financial performance | 17
32. A proportion of the funding gap did not have planned savings agreed
against it at the time of budget-setting. These unidentified savings made
up 13 per cent of the total projected funding gap and were the result of 12
IJBs starting the 2023/24 financial year with an unbalanced budget.
Exhibit 7
2024/25 IJB funding gap planed action
The use of non-recurring reserves makes up nine per cent of plans to bridge the funding gap.
Source: IJB budget papers, auditor returns
33. The proposed savings contain both recurring and non-recurring
savings. The reliance on non-recurring sources of income to fund recurring
budget pressures is unsustainable in the medium to long term. The
identification and delivery of recurring savings and a reduced reliance on
drawing from reserves to fund revenue expenditure will be key to ensuring
long-term financial sustainability.
Agreed savings
76%
Use of
reserves
9%
Other
2%
Remaining
gap
13%
Agreed savings
Use of reserves
Other
Remaining gap
Page 91

Page 92

Integration Joint Boards
Finance bulletin 2023/24
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit.scot
www.audit.scot
ISBN 978 1 915839 65 7
AS.5.0
Page 92

Page 93

APPENDIX 5 
MORAY INTEGRATION JOINT BOARD 
DIRECTION 
Issued under Sections 26-28 of the Public Bodies (Joint Working)
(Scotland) Act 2014 
1. Title of Direction and Reference
Number
MIJB 2025.26 Budget
20240327GHB/MC14
2. Date Direction issued by the Moray
Integration Joint Board
27.03.2025
3. Effective date of the Direction 01.04.2025
4. Direction to: NHS Grampian  and Moray Council 
5. Does the Direction
supersede/update a previous
Direction?  If yes, include the
reference number(s) of previous
Direction
No new budget for 2025/26 
6. Functions covered by Direction All functions listed in Annex 1, Part
1 of the Moray Health and Social
Care Integration Scheme and all
functions listed in Annex 2, Part 1 of
the Moray Health and Social Care
Integration Scheme. 
7. Direction Narrative  Directed to deliver for the Board, the
services noted below in pursuance
of the functions noted below and
within the associated budget noted
below
8. Budget Allocation by MIJB to deliver
on the Direction
Moray Council associated budget -
£96.5 million, of which £0.6 million is
ring fenced for Housing Revenue
Account aids and adaptations and
£3.3 for Children Services &
Criminal Justice OOA ring fenced
shared budget. 
NHS Grampian associated budget - 
£82.8 million, of which £5.9 million
relates to Moray’s share for services
Item 7.
Page 93

Page 94

to be hosted and £18.7 million
relates to primary care prescribing. 
An additional £15.6 million is set
aside for large hospital services . 
All details contained in APPENDIX 1
to the report
9. Desired Outcomes The direction is intended to reflect
the budget position for 2025/26 
10. Performance monitoring
arrangements and review
Directions will be reviewed by the
Audit Performance & Risk
Committee on a six monthly basis
for assurance.  Any concerns should
be escalated at the first available
opportunity to the MIJB. 
An annual report of all current
Directions will be presented to the
MIJB 
Page 94

Page 95

REPORT TO: MORAY INTEGRATION JOINT BOARD ON 27 MARCH 2025 
SUBJECT: MEDIUM TERM FINANCIAL FRAMEWORK 2025/26 – 2029/30 
BY:  CHIEF FINANCIAL OFFICER 
1. REASON FOR REPORT 
1.1 The Board is asked to approve the updated Medium Term Financial Framework
2025/26 to 2029/30. 
2. RECOMMENDATION 
2.1 It is recommended the Board: 
i) consider and approve the updated Medium Term Financial
Framework as set out below and at Appendix 1; and 
ii) agree that a review of the Framework be carried out on an annual
basis. 
3. BACKGROUND 
3.1 The current Medium Term Financial Framework covers the period 2023/24 to
2027/28 and was presented to the Board on 30 March 2023 (para 7 of the
minute refers). 
3.2 Scottish Government stipulated that the funding allocation to Integration
Authorities should be additional and not substitutional to each Council’s
2024/25 recurring budgets for social care services and therefore, Local
Authority social care budgets for allocation to Integration Authorities should be
£115 million greater than 2024/25 recurring budgets. 
3.3 The Audit Scotland annual audit report, presented to the Board on 26
September 2024 (para 11 of the minute refers) as part of the report for those
charged with governance made a recommendation that the Board’s medium-
term financial plan should be reviewed as it is considered out of date, alongside
the suite of supporting documents that support the Strategic Plan.  The latest
Strategic Plan was approved by the Board on 24 November 2022 (para 14 of
the minute refers) for the delegation of Childrens Services and Criminal Justice. 
Item 8.
Page 95

Page 96

3.4 In October 2018, the Scottish Government published it’s medium term financial
framework for health and social care (Scottish Government Medium Term
Health and Social Care Financial Framework).  This framework outlined the
future shape of demand and expenditure for health and social care services
and included cost and demand projections from work undertaken by the
Institute of Fiscal Studies which outlines that UK expenditure on healthcare
would require to increase by an average of 3.3% per annum over the next 15
years to maintain NHS levels at 2018 levels.  The report also set out that
spending on social care services would require to increase by 3.9% per annum
to meet the needs of an increasingly elderly population and an increasing
number of younger adults living with disabilities. The Scottish Government
updated its medium term financial framework in May 2022,  Scotland’s Fiscal
Outlook: The Scottish Government’s Medium-Term Financial Strategy, then
again in May 2023, Scotland's Fiscal Outlook: The Scottish Government's
Medium-Term Financial Strategy 
3.5 The Medium Term Health and Social Care Financial Framework was updated
in March 2022, due to the recognition that there have been significant
developments since the original Framework was published in October 2018,
most notably the ongoing impact and future implications of the Covid-19
pandemic.   
4. KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1 The current Medium Term Financial Framework covers the period 2023/24 –
2027/28 and is overdue for review.  A commitment was made to ensure a
revised framework would be before the Board on 31 March 2025.   
4.2 The Joint Strategic Needs Assessment (JSNA) was updated and presented to
the Board on 26 September 2024 (para 14 of the minute refers). The main goal
of the JSNA is to accurately assess the care needs of local in order to improve
the physical and mental wellbeing of individuals and communities. This
information will be used to inform the reviews of the Strategic Plan. The latest
Strategic plan was approved by Board on 24 November 2022 (para 14 of the
minute refers) and the Strategic Delivery Plan is a separate item on this
agenda. 
4.2 The review of the MIJB Medium Term Financial Framework takes account of
information currently available, however it is recognised that assumptions and
applied methodology will be subject of ongoing review and refinement as
additional information becomes available (notably the updated Scottish
Government Medium Term Health and Social Care Financial Framework) and
information relating to the National Care Service / Independent Review of Adult
Social Care.  Given the current uncertainty, it is therefore considered necessary
to review the medium term financial framework on an annual basis.  The
updated Medium Term Financial Framework is included at Appendix 1. 
4.3 There is a summary of the key information contained within the report relating
to financial information and the table on page 7 details the budget pressures
estimated to be required for the next 5 financial years, with assumptions
detailed in the paragraphs after the table. 
Page 96

Page 97

4.4 There are 2 tables on page 8, which shows the funding forecast for the next 5
years, this is based on flat cash settlement from the Council and a 3% increase
on base funding each year for NHS Grampian. The key table is the one that
gives the summary position and the level of savings required for the MIJB to
achieve. 
Summary Position 2025/26 2026/27 2027/28 2028/29 2029/30 
£000’s £000’s £000’s £000’s £000’s      
Estimated Budget
Requirement
204,375 212,158 215,950 220,268 224,715      
Total Funding 203,375 207,390 211,525 215,784 220,170        
Use of ear marked reserves 1,000          
Budget Surplus/(Deficit) - (4,768) (4,425) (4,484) (4,545) 
4.5 The predicted rise in costs over the term of this framework is £18.222 million,
which will require significant transformation to achieve financial balance. 
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP)) and Moray Integration Joint
Board Strategic Plan 2022 – 2032, ‘Partners in Care’
The approval of a balanced budget for the MIJB is key to the delivery of
health and social care services in Moray in accordance with the Strategic
Plan. 
(b) Policy and Legal
In accordance with the Public Bodies (Joint Working) (Scotland) Act
2014, MIJB is subject to the audit and accounts regulations and
legislation of a body under Section 106 of the Local Government
(Scotland) Act 1973 and is classified as a local government body for
accounts purposes by the Office for National Statistics. 
(c) Financial implications
Financial implications are contained throughout the report. 
(d) Risk Implications and Mitigation
The revenue budget for 2025/26 onwards is subject to the following
risks: 
• GP Prescribing – represents around 13% of the MIJB core
budget.  It is well documented that the Prescribing budget can be
extremely volatile in nature with volume and price increases
potentially leading to substantial adverse variances.   
• Growth and demand in the system, together with service users
with complex care needs are attracting additional financial
challenge.  These issues require to be managed within the overall
resource of the MIJB.
Page 97

Page 98

• The need to transform at pace and drive forward opportunities
arising through changes to working practice experienced through
the pandemic.  The risk being the ability to capture and embed in
a timely manner. 
• The implications of the cost of living crisis and current levels of
inflation, which are still forecast to rise may mean the provision for
inflation may not cover all the calls upon it.  Price inflation may
impact on areas where no provision has been made for
inflationary increases and this will add pressure to budgets.
Budget managers will need to control their expenditure to absorb
such pressure if possible and may have to reduce service levels
or identify further savings 
(e) Staffing Implications
There are no direct implications in this report . 
(f) Property
None arising directly from this report 
(g) Equalities/Socio Economic Impact
None arising directly from this report as there is no change to policy. 
Any subsequent changes to policy arising from proposals made within
this paper will be considered appropriately. 
(h) Climate Change and Biodiversity Impacts
There are no direct climate change and biodiversity implications as there
has been no change to policy. 
(i) Directions
None arising directly from this report. 
(j) Consultations
Consultations have taken place with the Senior Management Team, the
finance teams of both Moray Council and NHS Grampian, Caroline
O’Connor, Committee Services Officer and the Corporate Manager. 
6. CONCLUSION 
6.1 The Medium Term Financial Framework for 2025/26 to 2029/30 is
presented at Appendix 1. 
6.2 There will be close monitoring and review of the Medium Term Financial
Framework on an annual basis. 
Author of Report: Deborah O’Shea, Chief Financial Officer
Background Papers:  with author
Ref: 
Page 98

Page 99

APPENDIX 1 
MEDIUM TERM
FINANCIAL FRAMEWORK 
2025/26 – 2029/30 
MORAY
INTEGRATION
JOINT BOARD   
Item 8.
Page 99

Page 100

Table of Contents
Introduction ........................................................................................... 2
Context .................................................................................................. 3
Purpose ................................................................................................. 4
Influencing Factors ............................................................................... 5
Demographics .......................................................................................................................... 5
Costs ........................................................................................................................................ 7
Funding .................................................................................................................................... 8
Risk and Sensitivity Analysis ................................................................................................... 10
Legislative & Policy Changes ................................................................................................... 11
Demand ................................................................................................................................. 12
Risk ........................................................................................................................................ 12
Page 100

Page 101

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page
10 1 
Introduction 
Moray Integration Joint Board (MIJB) has been operating since April 2016 following
the introduction of new legislation - the Public Bodies (Joint Working) (Scotland) Act
2014. The legislation was developed with the aim of reshaping the health and care
system in Scotland to ensure sustainability of good quality services through a time of
change where demand continues to grow, our population is ageing and our budgets
are reducing. It changed the way in which health and social care services were
planned and delivered by introducing a single integrated system in creating Integration
Authorities. The MIJB is funded through allocations made by NHS Grampian and
Moray Council. 
MIJB has set out its approach for transforming the health and care system over the
long term in its Strategic Plan 2022-32 and has defined its priorities for the next ten
years through its Transformation Plan.  The Strategic Plan is underpinned by three
Strategic Outcomes 
This Medium Term Financial Framework (MTFF) is designed to assist the MIJB from
a planning perspective based on the totality of its financial resource across health and
social care in meeting the needs of the people of Moray. It will support the delivery of
the Strategic Plan within the context of the significant financial challenge being faced
and the continuing pressure being driven by growing demand and complexity, higher
costs and increasing expectations.
BUILDING RESILIENCE – Taking greater responsibility for our health and wellbeing
HOMEFIRST – Being supported at home or in a homely setting as far as possible
PARTNERS IN CARE – Making choices and taking control over decisions
Page 101

Page 102

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page
10 2 
Context 
There are 31 Integration Authorities established between 14 health boards and 32
councils across Scotland. 30 of the Integration Authorities are separate legal entities
and operate through a body corporate (Integration Joint Boards) and one area
operates a Lead Agency model. 
Scottish Government has been clear in that health and social care integration remains
a key priority. From the outset of integration, the aim has been to shift the balance of
care from large hospital settings into community based care. 
In May 2024, the Institute for Financial Studie1s reported in 2019 that UK spending on
healthcare would require to increase in real terms by an average of 3.3% per year over
the next 15 years in order to maintain NHS provision at current levels. However, latest
plans imply average growth of 2.7% per year between 2019/20 and 2024/25. The
Office for Budget Responsibility (OBR) estimate that health spending will have to rise
further to meet demographic and cost pressures 
There are numerous measures being used to monitor the local and national progress
of Integration. The Scottish Government’s Ministerial Strategic Group for Health and
Community Care have identified six priority areas against which progress against
integration is being measured: 
• Acute Unplanned Bed Days 
• Emergency Admissions 
• A&E Attendances 
• Delayed Discharge Bed Days 
• End of Life Spent at Home or in the Community 
• Balance of Care percentage of population in a Community or Institutional
Setting 
1The past and future of UK health spending | Institute for Fiscal Studies 
Page 102

Page 103

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page
10 3 
Purpose 
MIJB is focussed on improving the health and wellbeing of the people in Moray. It
seeks to reduce health inequalities and drive transformational change through
innovative approaches. 
Medium term financial planning is an essential part of the strategic planning process
that supports the MIJB to develop plans which consider the financial climate and
broader economic impacts. A robust medium term financial framework will provide
transparency and support informed decision making. 
Inherent within the MTFF is a significant degree of uncertainty. Scottish Government
funding settlements to our funding partners, Moray Council and NHS Grampian are
currently on a one year only basis and have a direct impact on the funding to the MIJB.
The MTFF sets out anticipated cost pressures and future funding projections based
on planning assumptions and advice from our funding partners. This is an evolving
model and it will be essential to refine and update at regular intervals. This review of
the framework follows the updated Strategic Plan and the full delegation of Children’s
Services from 1 April 2024. 
Given the level of uncertainty and potential for variability, it is essential that the MIJB
plans for a range of potential outcomes, ensuring sufficient flexibility to manage in a
sustainable manner over the course of this plan. 
The MTFF Framework seeks to support the understanding surrounding the broader
climate within which the MIJB will operate in over the medium term. There are wide-
ranging factors which encompass the complexity that impacts on the financial
pressures of the MIJB. 
The main objectives of the MTFF are: 
• To look to the longer term to help plan sustainable services, estimating the level
of resources required to operate these services and deliver on the MIJB’s
strategic ambition. 
• To estimate the level of increasing demand on services and provide a single
document to communicate the financial context to all stakeholders and support
partnership working. 
• The MTFF includes a five-year budget forecast that will be reviewed annually
to ensure our strategic priorities remain the focus in a challenging financial
climate.
Page 103

Page 104

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page
10 4 
Influencing Factors 
Demographics 
Moray’s population has grown significantly in the past 20 years from 87,000 in 2001 to
an 93,400 in 2022; an increase of 7.4%. However, the population growth in Moray is
slowing and it is projected that against the 2022 baseline, Moray will be one of the 14
councils in Scotland who will have had a population decline by 2028. Between 2022
and 2028 the age group +75 is projected to see the largest percentage increase at
32.4%. The largest percentage decrease is projected to be in the 0 to 15 years age
group (table 1 below). Given the most significant population growth is projected to
occur amongst older adults, this will have a significant impact on demand for our
services and creates a challenging environment in which to operate whilst transforming
our services and delivering on national and local priorities. The table 2 below illustrates
the % change across the main population groups by 2028.12
However, the 2024 census
data will provide a more accurate reflection of the current population in Moray and
once published will enable more accurate projections to be calculated. The census
data are expected to be available in May 2025.3
.
2  https://www.scotlandscensus.gov.uk/documents/scotlands-census-2022-rounded-population-estimates-data/ 
3 https://www.scotlandscensus.gov.uk/census-blog/looking-ahead-to-census-releases-in-2024/ 
DEMOGRAPHICS COSTS FUNDING POLICY DEMAND RISKS
Page 104

Page 105

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 10 
Table 1: Moray Population by Age Group – Comparison Between 2022 Estimate and
2028 Projection (NRS data) 
Table 2: Percentage Change in Projected Population for Moray, by Age Group, (NRS
data) 
This MTFF has been updated following the revised Strategic Plan; allowing our local
systems to develop plans within the overall, agreed financial position and alongside
service and workforce considerations. 
Page 105

Page 106

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 10 
During 2024/25, the Joint Strategic Needs Assessment (JSNA) was produced to inform
and support the production of the Strategic Plan for 2024 and beyond. The SNA was
developed through a short-life working group comprising of representatives from Health
and Social Care Moray, The Moray Council, the Moray Health and Wellbeing Forum,
NHS Information Services Division Scotland, and NHS Grampian. The SNA focused
on the collation and analysis of data from a range of sources to inform the identification
of priorities, and subsequent decision-making regarding service provision. It also
contributes to longer term planning undertaken by the Moray Community Planning
Partnership and the updating of the Moray Local Outcomes Improvement Plan
(LOIP).There are seven relevant areas for Moray. 
The SNA highlighted seven areas to be considered: 
• Population demographics – these are the basis of the JSNA and includes
population projections, which is an increasingly ageing population in Moray along
with a reducing birth rate. Deprivation in Scotland, where Moray is showing a low
level of deprivation but child poverty is rising faster than Scotland as a whole. 
• Social, clinical and behaviour risk factors – there are a number of risk factors
which are known to influence health, societal, behavioural and clinical. These risk
factors are strongly influenced by the environments we live in and the commodities
that we are able to access.Clinical risk factors may be associated with an increased
risk of certain diseases or death. 
• Population health – the diseases, illnesses and risk factors faced by the
population of Moray, with a purpose to not only understand future services but what
can be done to prevent, treat or support in different ways. 
• Secondary care services – increasing hospital admissions, including emergency
admissions, preventable admissions, unintentional injuries and falls and delayed
discharges in Moray. 
• Social care – long stay residents supported in care homes is increasing and above
the Scottish average as well as demand for care at home support. Most common
client type for care at homes services in Moray are elderly and frail individuals. 
• Finance and workforce – Staff headcount has increased within Health &
Socal Care Moray, however, the workforce is becoming older, with increases
in retirement and part time working. Increasing funding gap for Health & Social
care since 2024/25 onwards . 
• Different ways of working – looking at partnerships with people and other
transformations to meet the outcomes of people. 
Page 106

Page 107

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 10 
In response to the SNA, the MIJB Strategic Plan was developed and set the direction
and approach to prevention in addressing what is required in order to build resilience
in individuals and communities to be able to maximise their health and wellbeing
potential whilst ensuring services are available and fit for purpose when required. 
Costs 
There is a predicted rise in costs over the term of this framework of over £18 million.
The key elements are in relation to pay and price inflation and the increasing number
of complex care packages and the pressures on the prescribing budget. 
Budget Pressures 2025/26 2026/27 2027/28 2028/29 2029/30 
£000’s £000’s £000’s £000’s £000’s
Pay 2,758 2,841 2,926 3,014 3,105
Non pay inflation  960 843 855 880 907
SG investment ie RLW, FPNC      3,084      2,088      2,150 2,215 2,280
Learning Disability – High Cost 1,076 700 700 700 700
Transitioning Children 771 800 800 800 800
Prescribing 1,153 1,000 1,000 1,000 1,000
Other 666 126 130        134        138
Recurring Deficit 5,988    
eNIC pressure 2,505          
Total Budget Pressures 18,961 8,398 8,561 8,743 8,931 
Assumptions embedded within Budget Pressures: 
Pay – 3%, in each year for both Council and NHS staffing. Funding will be provided
for the health staff increase with the assumption is that this will continue to be the
case. 
Non pay inflation –3% in each of the following years for non pay external purchasing
but includes £141,000 one off expenditure for 2025/26. 
Scottish Government investments – this relates to the Real Living wage increase for adult
and Children’s social care, National Care Home Contract and the Free Personal and Nursing
Care, for 2025/26 includes increases of 5% and 6.7% but is assumed it will reduce to 3% in
each of the following years Funding is received towards the majority of this pressure. 
High Cost Individuals – there are significant packages expected in 2025/26 but
beyond then we will need to consider different care models in order to ensure we can
manage the related budget pressure 
Transitioning Children – work has been on going to deal with the expected increase for
clients coming into the service. There is expected to be a constant increase over the
next few financial years, for which the service is monitoring and reviewing to ensure
the budget pressures can be managed.
Page 107

Page 108

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 10 
Prescribing – pressure continues on this budget for the foreseeable future, due to
increase in both demand and prices. 
eNIC pressure – relates to the UK Government’s increases to employers National
Insurance Contributions (eNIC). This pressure includes both directly employed staff
and commissioned provider contracts. Funding is expected to provide 60% of the
directly employed pressure with the balance having to be met by the IJB’s. 
Funding 
The two main sources of funding for the MIJB are provided by NHS Grampian and
Moray Council. In recent years, additional investment for health and social care has
been provided by the Scottish Government and this is passported through either the
local authority or the health board. Any future funding will be impacted by the
respective financial planning processes of both organisations and the funding
settlements they receive. The MTFF makes assumptions regarding future funding
contributions from both Partners based on information which is currently available.
Outlined below is the potential funding that will be provided over the term of this plan. 
Funding Forecast 2025/26 2026/27 2027/28 2028/29 2029/30 
£000’s £000’s £000’s £000’s £000’s
NHS Grampian Recurring 94,724 97,578 99,908 102,308 104,780
NHS Grampian Uplift (3%) 2,262 2,330 2,400 2,472 2,546
NHS Grampian eNIC 592    
Moray Council Recurring 86,221 90,159 91,844 93,579 95,366
Moray Council eNIC 800    
Additional SG investment 3,138 1,685 1,735 1,787 1,840
Set Aside 15,638 15,638 15,638 15,638 15,638      
Total Funding Estimated 203,375 207,390 211,525 215,784 220,170 
*assumes budget protocol principles are reinstated 
Summary Position 2025/26 2026/27 2027/28 2028/29 2029/30 
£000’s £000’s £000’s £000’s £000’s      
Estimated Budget
Requirement
204,375 212,158 215,950 220,268 224,715      
Total Funding 203,375 207,390 211,525 215,784 220,170        
Use of ear marked reserves 1,000          
Budget Surplus/(Deficit) - (4,768) (4,425) (4,484) (4,545) 
Page 108

Page 109

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 10 
The summary position tabled above highlights that the MIJB will be required to
continue to closely observe the financial constraints within which it is operating. Future
funding assumes a level of savings will be achieved each year, together with
transformational redesign that we know we need to make in order to provide affordable
sustainable services within the resources available. It assumes that the existing
financial pressure will be addressed through savings alongside the need to transform
the way we provide services across our whole system in an innovative way. With this in
mind and assuming this can be achieved over the short-term, there still remains a
deficit that will require to be addressed, again reinforcing the need to review this
framework on a regular basis, updating it with the most current information available
and creating a focus on the period ahead. 
Risk and Sensitivity Analysis 
The MTFF is a financial model based on the best available planning assumptions at
the time and accordingly, has related risks associated with it. The main risks
associated with this framework are:
• Impact of MIJB decisions on Partner bodies and Vice-versa
• Failure to identify a future budget pressure
• Under estimation of the cost pressures
• Under estimation of demand pressures
• Public expectation of delivered services
• Over /under estimated impact of local and national factors
• Failure to accurately forecast income sources 
It is important that the MIJB is aware of these risks in determining its appetite to risk
as it considers its Strategic Plan. The MIJB recognises strategic risks through its Risk
Register. This is used to ensure that significant risks are identified and mitigating
actions are effective in reducing these risks to an acceptable level.
Sensitivity Analysis is used to test the major assumptions being made and what the
implications would be, should those assumptions change. The Financial Projections
outlined in this framework are based on what is determined to be a medium case
scenario for future funding. In addition to the funding element, there are risks aligned
to other assumptions made in the framework around future budget pressures for the
MIJB. It is important that the MIJB regularly reviews this framework.
Page 109

Page 110

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 11 
Legislative & Policy Changes 
Integration Authorities are operating within a complex and changing environment
where national issues are likely to have an impact on the services provided and how
we deliver them locally. This environment has changed significantly following the
Covid 19 pandemic and the ongoing effect of public health and the economic impact. 
Some of the recent legislative changes impacting on integration authorities are: 
• Free Personal Care for the Under 65’s – the Scottish Government has committed
to the extension of Free Personal Care to those under the age of 65 who require it,
regardless of condition. This became effective from 1 April 2019. This represents a
significant change to how personal care is funded and is likely, over time to increase
demand for personal care across Scotland.
• Carers Act (Scotland) Act 2016 – This legislation came in to effect on 1 April 2018
and is designed to support the health and wellbeing of carers by supporting
sustainability. It places a duty on Local Authorities to provide support for carers, based
on the carer’ identified needs which meet local eligibility criteria.
• Scottish Living Wage – there is a continued commitment from Scottish Government
to support the payment of the Scottish Living Wage to improve people’s lives and help
build a fairer society. Scottish Government has continued to provide funding to support
this commitment. For the 2025/26 financial year, the uplift is set to increase to a
minimum of £12.60 per hour.
• Delayed Discharge – a Scottish Government priority to reduce the number of people
who are delayed from being discharged from hospital. Work is on going on a whole
system approach to reduce this.  
• National Care Service – the recommendations arising from the Independent
Review of Adult Social Care which concluded in January 2021 are likely to have a
major impact on how Integration Authorities are governed and how services are
delivered. Confirmation and further detail are awaited 
Page 110

Page 111

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 12 
Demand 
The recovery from  the impact of the Covid 19 pandemic continues to create increased
pressure and demand on our health and social care system. The full extent of this
impact remains unknown but we are acutely aware of the current impact on the citizens
of Moray in respect of the level of unmet need we are experiencing in both assessment
and delivery of care. We understand that in order to address increasing demand it will
require the whole health and social care system to work together to redesign to create
truly transformational services. The landscape is constantly changing as we progress
through the recovery stage. We must ensure we have robust plans in order to maintain
delivery of our strategic aims whilst being mindful of the flexibility that will be required
as we continue to understand the broader impacts that we face as we recover and
remobilise following the pandemic. 
Risk 
We are experiencing challenging economic conditions. The effects of the global
economy in turn is impacting on the Moray population through taxation, inflation and
level of earnings. The broader impact is on the funding being made available to
support public spending. Scotland’s funding is largely dependent on funding being
received from the UK Government. The most recent ‘State of the Economy’ report4
from Scotland’s Chief Economic Advisor was published in May 2024 and highlighted
the following:
• Scotland’s GDP grew in the three months to February 2024 by 0.4% in
February, and is likely that the economy will show growth in the first
quarter of 2024, confirming that the Scottish economy has avoided a
recession; 
• Scotland’s labour market continues to be robust, with the unemployment
rate falling to 4% and the number of payrolled employees remaining close
to its series high.  Earnings also continue to grow faster that inflation, with
annual earnings growth of 6.3% in March, 3.1% faster than inflation;
• Economic growth is expected to strengthen across 2024 and 2025, as lower
inflaction supports real earnings growth, with interest rates also expected to
fall with will support a pick-uo in consumption. Howeverm the path for
inflation, earnings and interest rates remain uncertain and will be an
important determinant of the economic outlook.
4 https://www.gov.scot/publications/scottish-economic-bulletin-2024/
Page 111

Page 112

Draft Medium Term Financial Framework 2022/23 - 2026/27
Page 13 
The MIJB is facing new risks which may impact on its budget over the next few
years:
• Significant financial pressures – the funding challenges are not only
affecting the IJB’s but also both of the partners are under significant
pressure too;
• Health Debt – we are acutely aware of what is being described as the health
debt, resulting from services which were paused during the pandemic and in
some instances have not fully resumed.
• National Care Service – this will have a major impact on services and how
they are delivered in the coming years, the full extent of which is still
uncertain. 
It is important that the MIJB understands its appetite to risk to enable effective
management and mitigation of the inherent risks.
Page 112

Page 113

REPORT TO:    MORAY INTEGRATION JOINT BOARD ON 27 MARCH 2025 
SUBJECT: HEALTH AND SOCIAL CARE MORAY STRATEGIC DELIVERY
PLAN 2025-2028 
BY:  CORPORATE PROGRAMME MANAGER 
1. REASON FOR REPORT 
1.1 To ask the Moray Integration Joint Board (MIJB) to review the progress and
agree the approach to finalise the Delivery Plan that supports meeting the aims
and objectives of the Moray Integration Joint Board Strategy. 
2. RECOMMENDATION 
2.1 It is recommended that the Board:- 
i) consider the progress in development of Health and Social Care
Moray’s Delivery Plan (2025-2028), attached as Appendix 1; and 
ii) instruct that the finalised Delivery Plan be presented to the Board
in May 2025. 
3. BACKGROUND 
3.1 The Public Bodies (Joint Working) (Scotland) Act 2014 places a duty on
Integrated Authorities to develop a Strategic Plan for delegated functions under
their direction. As reported to the Board on 24 November 2022 (paragraph 13
of the minute refers), the revised strategic plan ‘Partners in Care 2022-2032’
was approved to allow for the Strategic Delivery Plan (SDP) to be developed. 
3.2 At the meeting of the Board on 29 June 2023 (para 10 of the minute refers) the
priorities for the strategic plan were agreed as follows: 
• Transformation priority 1 - Supported self-management
• Transformation priority 2 - Long term condition management
• Transformation priority 3 - Care in place
• Transformation priority 4 - Smarter Homes / Smarter Communities 
• Transformation priority 5 - Mental wellbeing 
• Improvement priority 1 – Primary Care Improvement Plan
• Improvement priority 2 – Frailty Pathway 
3.3 The Strategic Delivery Plan 2023 to 2026 was agreed by the Board on 28
September 2023 (para 12 of the minute refers) and set out how the Strategy
will be delivered, highlighting the key improvements and transformational
change which will be required. 
Item 9.
Page 113

Page 114

4. KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1 The past two years have seen significant changes in the financial landscape for
Health and Social Care Partnerships (HSCP), Local Authorities and the
National Health Service.  The challenges of an aging population and increasing
multi-morbidity are placing growing pressure on maintaining existing services
along with increasing demands for care in a period of financial constraints.  In
addition, there have been significant changes in the Senior Management Team
(SMT) with the appointments of a new Chief Officer, Chief Financial Officer and
Interim Head of Service/Chief Social Work Officer.  The Joint Strategic Needs
Assessment was also reviewed and approved by the Board on 26 September
2024 (para 14 of the minute refers). Given all these changes, it was felt
appropriate to review and reset the SDP, whilst retaining the key areas of focus
previously agreed. 
4.2 The content of the draft Delivery Plan reflects the work necessary to meet
national objectives, shared objectives in collaboration with Health and Social
Care Moray’s (HSCM) partners, Moray Council and NHS Grampian and with
Aberdeen City and Aberdeenshire HSCPs and with redesigns of models of
service delivery to improve outcomes and efficiency.  An example of this will be
the work that will progress in collaboration with our partners through the
Grampian Strategic Change Board (established in November 2024) that will
develop and implement the NHS Grampian’s Route Map for Strategic Change
in collaboration with IJBs to create a future sustainable health and care system.   
4.3 Consultation has taken place with the Senior Management and Operational
Management Team to build on progress already made and to confirm the
priority work streams for the next three years of the Strategic Plan to 2028.
Following the development of the draft Plan, there has been consultation with
the MIJB at the development session in February and discussion at the
Strategic Planning and Commissioning Group (SPCG) on 4 March 2025 and
comments received have been addressed. 
4.4 The draft SDP (Appendix 1) provides an overview of the agreed priority work
streams and actions for HSCM. The Plan requires to be flexible and responsive
ensuring the complex range of work streams are prioritised and progressed
within meaningful timescales and within capacity and resources available. 
Given the recent requirement to review budgets and identify additional savings
for 2025/26, it would be prudent to provide managers with a further opportunity
to consult on the draft SDP, prior to finalisation, to ensure resources are
available and timescales are achievable.  A focussed session with service
managers will be held at the end of April, where the draft SDP will be
considered alongside the proposed performance framework, with a final draft
presented to the Board in May 2025.   
4.5 Regular monitoring of progress of the SDP will be undertaken by SMT and
SPCG, with a summary report to the Board every 6 months.  The performance
reporting framework is being refreshed and will set the governance
arrangements for reporting on key performance indicators related to achieving
aims set out in the delivery plan to Audit, Performance and Risk Committee. 
4.6 The SDP provides that overarching assurance of how projects that are agreed
will also support the delivery of both the HSCP’s Medium Term Financial
Page 114

Page 115

Strategy and the Workforce Plan. The project documentation also
encompasses the work toward delivery of the Equality Outcomes set by the
partnership as well as capturing links other plans and strategies as relevant.
This provides a cohesive and co-ordinated approach to the delivery of the
current Strategic Plan. 
4. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP)) and Moray Integration Joint
Board Strategic Plan “Partners in Care 2022 – 2032”
The SDP underpins the named plans and supports achieving better
outcomes for citizens in Moray. 
(b) Policy and Legal
The implementation and publication of the delivery plan will ensure that
the MIJB complies with legal requirements. 
(c) Financial implications
Pivotal to the effective delivery on the actions in the strategic delivery
plan are the financial resources available to MIJB. To assist with the
planning process, a Medium Term Financial Framework supports the
delivery of the strategic plan to aid decision making. This is scrutinised
regularly by Senior Management and reported quarterly to MIJB.  The
Budget Savings Oversight Group will regularly monitor the progress of
projects regarding delivery of budget savings to ensure anticipated
savings are achieved. 
(d) Risk Implications and Mitigation
Risks to achieving the deliverables in the plan will be highlighted through
the Strategic Risk Register and monitored by the Audit Performance and
Risk Committee. The immediate risk to successfully delivering the Plan
could be defined as Intensification – trying to do more with the same
(e.g. financial resources, workforce availability). To mitigate against this,
the MIJB agreed the 3 year transformation priorities and improvement
projects in 2023; to offer a clear focus for HSCM staff and these priorities
are incorporated in this iteration of the SDP. Each service/team will have
or will develop service plans that encompass their responsibilities
contained in the SDP. This supports good governance, risk and issue
escalation if required. 
(e) Staffing Implications
With any changes in ways and models of working, there may be
implications for staff in how they go about their work and how supported
they are within a pressured and changing environment. Staff side,
Unions and Human Resources will be working alongside SMT in
delivering change, observing the associated policy and procedures of the
Council and NHS. The SDP will be delivered using existing staffing. That
said, as a saving target has been agreed though vacancy management,
the MIJB must be cognisant of the health and wellbeing of the workforce
as they continue to deliver and transform in a resource constraint
environment.   
Page 115

Page 116

(f) Property
The Moray Infrastructure Board offers oversight and scrutiny to service
delivery, linking into the assets management arrangements for NHS
Grampian and Morays Council. Service specific infrastructure and
property issues will be detailed in service plans and risks raised through
the Infrastructure board and Strategic Risk register is appropriate. 
(g) Equalities/Socio Economic Impact
An Equality Impact Assessment (including assessment against Fairer
Scotland Duty) was undertaken in line with statutory obligations.  This
has been reviewed and there were no changes identified.  The EIA was
included as part of the submission for the Strategy on 29 November
2022 and are available publicly on HSCM website.  As projects progress,
they will undertake Integrated Impact Assessments that will be reported
and published as necessary. 
(h) Climate Change and Biodiversity Impacts
There are no direct impacts arising from the recommendations of this
report.
Climate change impacts are considered and incorporated into project
documentation and business plans as we work towards reducing carbon
footprint and delivering on net zero emissions targets. 
(i) Directions
No direction requires to be issued to Moray Council or NHS Grampian as
a result of this report. 
(j) Consultations
Consultations have been undertaken with Senior Management Team,
Operational Management Team and Caroline O’Connor, Committee
Services Officer, Moray Council, and comments have been incorporated
in this report. 
5. CONCLUSION 
5.1 The SDP is a key document for the Partnership which, when approved,
will set out the agreed priorities to be delivered over the next three years,
within the capacity and resources available, and progress will be
monitored on a regular basis and reported in the Annual Performance
Report. 
Author of Report: Jeanette Netherwood, Corporate Programme Manager 
Background Papers:  20250130 North East Route Map for Strategic Change Report
and Appendix 
20230928 Strategic Delivery Plan 2023-26 and Appendix 
20230629 Strategic Transformation Plan Report  
20221124 Strategic Plan 2022-2032 Report and Appendix 
Page 116

Page 117

APPENDIX 1
Page | 1 
|  1  
Health & Social Care  Moray  
Strategic Delivery Plan   202 5   -   2028  
Item 9.
Page 117

Page 118

APPENDIX 1
Page | 2 
Contents
1 Introduction .......................................................................................................................................................................................3
2  Moray Health & Social Care Partnership .......................................................................................................................................4
2.1 Joint Strategic Needs Assessment .........................................................................................................................................4
2.2 Establishing Sustainable Models of Care ...............................................................................................................................6
2.3 Relationships and Collaboration ............................................................................................................................................7
3  Key Enablers ....................................................................................................................................................................................8
4  Performance and Governance .........................................................................................................................................................8
5  Strategic Delivery Plan .....................................................................................................................................................................9 
Building Resilience ………………………………………………………………………………………………………………………………………………………….10 - 15 
Home First ………………………………………………………………………………………………………………………………………………………..16 - 18 
Partners in Care …………………………………………………………………………………………………………………………………………………19 - 24 
Strategic Leadership, Planning and Performance …………………………………………………………………………………………………….25 - 27 
Page 118

Page 119

APPENDIX 1
Page | 3 
1 Introduction 
This Strategic Delivery Plan should be read alongside the Moray Health and Social Care Partnership (HSCM) Strategic
Plan which was agreed by the Moray Integration Board (MIJB) in November 2022. This delivery plan sets out the
programme of transformational
and improvement work underway to enable the HSCM to meet its strategic priorities. The Strategic Plan itself is also
supported by the HSCM’s Workforce Plan, Medium Term Financial Strategy and Commissioning and Procurement
Plan. The work of the HSCM also supports, in part, the delivery of Moray Council’s Plan and NHS Grampian’s Plan for
the Future. 
Our key focus continues to be progressing the integration agenda by increasing access to community-based health
and social care services, shifting the balance of care from hospital to more homely settings, and supporting our most
vulnerable citizens. Whilst setting out our vision, which remains “We come together as equal & valued partners in
care to achieve the best health & wellbeing possible for everyone in Moray throughout their lives”. We continue
to deliver on our three strategic themes by setting clear strategic objectives which can lead us to improving outcomes
over the next ten years.      
BUILDING RESILIENCE                   
HOME FIRST            
PARTNERS IN CARE 
Page 119

Page 120

APPENDIX 1
Page | 4 
2 Moray Health & Social Care Partnership 
Many of the pressures and challenges being faced within Moray are reflected across Scotland.  The joint strategic
needs assessment was updated as part of refreshing and continuingly informing the development of the delivery plan. 
There is a changing dynamic over the last 20 years where the population is becoming healthier and living longer but
we appreciate that an increasing number of people experience the burden of long-term medical conditions. Moray is a
large rural area where the average life expectancy is above the Scottish average. However, due to socio-economic
factors and population spread, there are different rates of life expectancy and healthy life expectancy across Moray.    
2.1 Joint Strategic Needs Assessment
The revised Joint Strategic Needs Assessment was approved by MIJB on 26 September 2024.  The key aspects identified in the
assessment for Health and Social Care Needs in Moray identify the specific challenges and pressures on the health and care
system within Moray, and are set out below:-
Ageing Population 
Moray is projected to have an increasingly ageing population structure. Between 2023 and 2038 it is projected that the number of 5-
17 year-olds in Moray will decline by 19% (-11% for Scotland). Conversely, those aged 85 and over will increase by 63% in Moray
and 47% in Scotland.
Above average limiting long term illnesses 
Approximately 40% of Moray residents live with limiting long term illnesses, above the Scottish average of 36%.    Moray has a
higher prevalence for all diseases when compared to Scotland as a whole, the only exception being COPD.
The prevalence of Dementia 
Within the Moray population has increased from 4.9 per 1,000 population in 2017/18 to 5.6 in 2022/23.  
The prevalence of Depression
In both Moray and Scotland has risen between 2017/18 and 2022/23.
Page 120

Page 121

APPENDIX 1
Page | 5 
Above average smokers  
In the 2018-2022 aggregate time period, 18% of Moray adults aged 16 years and over were smokers, above the Scottish average
of 13%.
A&E attendances at Dr Gray’s Hospital 
There were 28,402 attendances in 2022/23, an 11.2% increase on the previous financial year and reaching a value above pre-
pandemic levels (in contrast to Aberdeen Royal Infirmary).   High intensity use is greatest in areas of deprivation, and across all age
groups it is associated with issues such as homelessness, being out of work, mental health conditions, drug and alcohol problems,
criminality, and loneliness and social isolation.
Care Homes 
Moray has higher rates of 65-84 year olds than Scotland
Care at Home
A decrease in the number of people supported with care at home provided/funded by Moray Health and Social Care Partnership for
the fourth consecutive year.   Moray’s Care at Home Service recipients have high levels of A&E attendances as a rate per 1,000 at
189.6 (Jan-Mar 2023) compared to 155.6 for Scotland.
Access to GPs
52% report they cannot get a GP appointment within 3 days.
Cancer Screening 
GPs in Moray report that they are seeing and referring more people with cancer symptoms, but less cancer is being diagnosed and
it is being diagnosed later.  This is a concern as there will be increasing 'unfound' cancers, and later diagnosis means less will be
treatable.
Inequalities 
Clear inequalities are present: females in the most deprived areas of Moray have a 3% lower life expectancy than Moray as a
whole; males in the most deprived areas have a 5% lower life expectancy than Moray as a whole. 
Page 121

Page 122

APPENDIX 1
Page | 6 
Fuel Poverty
32% of Moray residents faced fuel poverty, far higher than the overall Scottish figure of 24% over the same period.  Extreme
fuel poverty in Moray (2017-2019) was estimated to be 19%, higher than Scotland’s 12% over the same period.  Cost of
Living - almost 40% of Moray households (39%) describe themselves as experiencing problems with meeting housing
payments, which ranges from 42% in Buckie to 33% in Speyside. 15% of Moray households describe themselves as having
financial difficulties now, in comparison to 4% pre COVID. One in five households in Keith were currently experiencing
financial difficulties (20%). 
Increasing child poverty
24.1% children (4,228 individuals) were in poverty in 2021/22 in Moray, a rise in percentage from 20.8% in 2014/15 (3896
individuals).
Food insecurity has increased in Moray: in the 2018-2022 period 8% of residents were worried that they would run out of
food, up from 7% in 2017-2021, and 6% in 2016-2019
Veterans - There are two large military bases in Moray: RAF Lossiemouth and Kinloss Barracks, which employ around 4000
people at present.  We also need to consider the health needs of veterans of the armed forces; where the population often
differs in structure to the non-veteran population; usually older and more males than females.
Unsuitable housing 
The Moray HDNA 2022 estimated 2,160 households across Moray (which equates to 5% of the total households in Moray of
43,995) require to move to alternative housing to address housing unsuitability. 
Delayed Discharges
On average, 39 beds were occupied by delayed discharges each day in Moray in the 2022/23 financial year. This is a 34.5%
increase on the 2021/22 value of 29 beds. 
2.2 Establishing Sustainable Models of Care
As a partnership, we are cognisant of the financial constraints we, and our partners, are working within.  The existing
available budget does not meet the demand for services being delivered at the current rate, and in order to be sustainable
Page 122

Page 123

APPENDIX 1
Page | 7 
we will have to make difficult choices and continue with designing services through transformational change where the
person receiving the service remains at the heart of the conversation. The future of Health and Social Care delivery very
much depends on the decisions that will require to be made, as the option to remain as we are is not viable.  
Therefore, there is a strengthened focus on prevention and early intervention to promote good, positive physical and
mental health and wellbeing for all people across all ages and client groups. We know 70 to 80% of people with long term
health conditions could manage their conditions themselves with support from informal health systems, and a number of
identified projects will seek to explore the options to maximise every opportunity for informal supports.    
We must continue to work with our communities as we move forward, placing communities at the heart of public health
can reduce health inequalities, engage those most at risk of poor health, empower individual and communities, and build
resilience. That also involves supporting people to enable them to be responsible for their own health, and to work with
health and care professionals to manage existing conditions.   
HSCM is responsible for almost 1,795 staff members employed by NHS Grampian or Moray Council. Not only do we
recognise the tremendous amount of effort and work undertaken each day in Moray to support people in our communities,
but we also recognise the role of ‘communities’ themselves, in supporting the most vulnerable and providing resilience. 
We have to change, we have to deliver differently, we have to focus on what we can support, what we ask people to do and how we
ask communities support us. 
2.3 Relationships and Collaboration
Our partner organisations, Moray Council and NHS Grampian are facing similar financial challenges along with our
neighbouring Health and Social Care partnerships in Aberdeen City and Aberdeenshire.  There is agreement that we need
to work together to ensure we maximise every opportunity whilst minimising any negative impact of change across our
whole health and social care systems.  We are committed to sharing best practice and learning from each other and a
Grampian Health and Care Strategic Change Board was established in November 2024.  As the Board develops it will be
responsible for developing and implementing the NHS Grampian’s Route Map for Strategic Change in collaboration
with Integration Joint Boards (IJB), which will be a key document outlining our shared strategic priorities for the future of
Page 123

Page 124

APPENDIX 1
Page | 8 
health and care across the North East, coupled with the practical steps required to create a sustainable health and care
system. 
3  Key Enablers
The delivery of the strategic plan is underpinned by key workstreams shown under the theme of Strategic Leadership, Planning
and Performance.  This workstream encompasses the development and implementation of strategies that will set the culture and
standards for HSCM in relation to Finance, Communications, Workforce, Performance and Quality Assurance, Commissioning,
Infrastructure, Digital Health Care and Governance.  These elements combined will form the basis and structure for the delivery of
the specific priorities outlined under the Strategic Objectives and our strategic themes of Building Resilience, Home First and
Partners in Care. 
4  Performance and Governance 
The Strategic Planning and Commissioning Group (SCPG) has responsibility for oversight of the development work
streams arising from the HSCM’s Strategic Delivery Plan and will consider options appraisals and key project
documentation as progress is made.  HSCM Senior Management Team will lead the implementation of the delivery plan
and the definition of SMART objectives, against which progress will be measured.  
Progress of the actions within this delivery plan will be overseen and scrutinised by the Senior Management team and Strategic
Planning and Commissioning group and will be reported to the MIJB on a six monthly basis. An annual review process will provide
the opportunity for the MIJB to review both the progress of the projects during the previous year as well as the focus for the
forthcoming year. In developing this approach, we aim to remain cognisant of prioritising areas of change and transformation that
will enable the delivery of our strategic priorities in an environment which very much requires a flexible approach 
Page 124

Page 125

APPENDIX 1
Page | 9 
The performance reporting framework is being revised and will be implemented for reporting in 2025. To provide
assurance and oversight a high-level summary of performance against the outcomes of the Strategic Delivery Plan will be
reported to the Audit, Performance and Risk (APR) Committee on a quarterly basis.  
Outcomes to be achieved will be set against each project, along with key milestones for delivery, and the performance
indicators that will provide assurance that the required changes and improvements are taking place. 
The Strategic Delivery Plan will be closely aligned with the HSCM Medium Term Finance Strategy (MTFS) and Workforce
Plan, as the three main levers through which we will deliver the HSCM Strategic Plan.   
5  Strategic Delivery Plan 
As previously described, this Strategic Delivery Plan sits within a wide and complex planning and policy environment
where the HSCM plays a critical role in working collaboratively with partners to deliver on whole system priorities and work
streams, including supporting delivery of the NHS Grampian Plan for the Future and Moray Council Plan. It is therefore not
exhaustive of all areas of HSCM activity where we are a key partner, for example: in delivery of the Moray Children’s
Services Plan to improve the wellbeing of children and young people in line with the GIRFEC (Getting It Right For Every
Child) philosophy; in the initiative Discharge Without Delays, to develop improve the integrated model across the whole-
system for frail older people accessing hospitals; and in developments around population health initiatives to support
prevention and early intervention for all.  
The plan below reflects the key actions being driven by HSCM over the next three years. The Strategic Delivery Plan will
remain a live document to ensure we can be agile and responsive to new or emerging priorities whilst ensuring a focus on
delivery of the HSCM’s own strategic priorities. 
This Strategic Delivery plan provides high level information about each action, links to strategic objective and strategic
themes including a key summary and the priority tasks that will be undertaken. Some of the projects identified will go
beyond the duration of this Strategic Delivery Plan due to their nature and complexity. 
Page 125

Page 126

APPENDIX 1
Page | 10 
STRATEGIC THEME - BUILDING RESILIENCE            
YEARS   
Objective 1: We focus on prevention and tackling inequality           
Key Heading Description Lead 1 2 3 Timescale Outcomes  
1 Early Intervention and
Prevention
We aim to provide support to the citizens
aimed at improving outcomes and
preventing escalating need or risk              
1.1 Community Appointment
Days (CAD)     
Test out Community Appointment Days in
three areas of Moray, focussing on areas
of inequality/accessibility, utilising learning
to adapt ways of working to become more
inequalities sensitive.  To help people to
self-manage their own conditions
Health
Improvement
Team Leader
X     Mar-26 Three events held, learning
synthesised and
recommendations for future
approaches agreed.  
1.2 LD Health Checks Annual Health Checks for People 16+ with
Learning Disabilities
LD Service
Manager    
X Mar-26 Evaluation completed and
learning shared  
1.3 Social Prescribing To scale up the current test of change and
deliver a social prescribing model across
all Moray localities
Health
Improvement
Team Leader    
X Mar-26 reducing in targeted service
waiting lists  
2 Poverty Strategy    To work with partners to raise awareness
and to work to reduce the impact of
poverty on people’s health and wellbeing in
Moray              
2.1 Contribute to development
of Moray wide poverty
Strategy and Action Plan  
Localities
Manager (West)
X     Jun-25 Moray-wide strategy and action
plan in place to tackle poverty,
and in progress by March 2025  
2.2 Implement HSCM actions
of Moray Wide Poverty
Action Plan  
Senior
Management
Team
X     April
2025 to
March
2026
To be determined from the actions
Page 126

Page 127

APPENDIX 1
Page | 11 
2.3 Implement actions from the
Children’s Plan
Child Poverty - 
- Implement actions from the Children
Services Plan 
- Establish a Child Poverty Data Set
Service Manager
C&F
X     Jun-25 Actions implemented
Child Poverty Dataset in place  
2.4 Raising awareness of the
Impact of Poverty on health
Develop and deliver training to front line
staff and decision makers in order to raise
awareness & understanding of impact of
poverty on health and ability to access
health services/comply with treatment
HI Team Leader X X   Sep-26 Increased number of frontline staff
trained & confident in speaking
about poverty/referring on for
appropriate support  
OBJECTIVE 2:  We nurture and are part of communities that care for
each other                
Key Heading Description Lead 1 2 3 Timescale Outcomes  
3 Supporting Unpaid
Carers   
Continue to work collaboratively with
partners to achieve a support network and
deliver high level services to ensure unpaid
carers are supported to meet their own
individual needs and the needs of the
person they care for              
3.1 Review mechanism for
assessment of support
provided to unpaid carers,
to meet statutory
requirements in Carers
(Scotland) Act 2016 
Implement revised
mechanism  
Unpaid Carers
Strategy Group
X X   Nov-24 Revised mechanism identified,
consulted on and approved for
adoption. 
Revised mechanism implemented
across all teams.  
3.2 Implement actions outlined
in the Unpaid Carers
delivery plan  
Unpaid Carers
Strategy Group  
X   Mar-26 Increased awareness of unpaid
carers with professionals across
health and social care and within
the community.
Page 127

Page 128

APPENDIX 1
Page | 12 
3.3 Produce and plan
implementation of the
Unpaid Carers Strategy for
2027-2030  
Unpaid Carers
Strategy Group    
X Mar-27 Published strategy 
implementation plan actioned  
4 Primary Care
Sustainability
Aiming for sustainable General Practices
across Grampian that enables people to
stay well in their communities through the
prevention and treatment of ill health
through the VISION aims and objectives
(Hosted Services)              
4.1 Lead and Deliver the
VISION objectives for GPs
across Moray
Focus on 5 areas 2025/26: 
Data
Digital
Multi-Disciplinary Team
Models of contract
Premises
Primary Care
Development
Manager  
X X   Mar-26 Delivery of the VISION objectives
on time and within budget.  
4.2 GP Sustainability Delivering the contract within the available
funds
Reviewing the directives within the MOU
Primary Care
Development
Manager  /Clinic
al Leads
X     Jun-25 Programmes of work are
evaluated as “well“ by the PCIP
board by June 2025  
4.3 Deliver the Primary Care
Improvement Plan
Delivery of the MOU and develop
opportunities for flexibility in the contract
Primary Care
Development
Manager
/Clinical Leads
X X X ongoing Improvement plan implemented  
5 Mental Health Services Intact the Moray Good Mental Health for
All Strategy (2016-2026) and the
underpinning Mental Health Delivery Plan            
Page 128

Page 129

APPENDIX 1
Page | 13 
5.1 Mental Health - Early
intervention, prevention
and self-management 
Move towards a preventative, population
health model which promotes and sustains
good mental health and wellbeing.
Mental Health
Services
Manager /
Health
Improvement
Team Leaders /
Mental Health
Strategic Lead
X X   Mar-26 We have developed social
connections, tackled isolation,
built resilience, strengthened use
of community assets.
We have improved responses to
people in distress - both from
services and the wider community  
5.2 Mental Health Quality
Standard 1: Access
People in Moray have equitable and non-
discriminatory access to effective and
relevant support for their mental health,
within appropriate timescales.
Mental Health
Services
Manager
Child Health
Commissioner
Strategic Lead
Mental Health
X X   Oct-26 People can access the person-
centred support they require. 
5.3 Mental Health Quality
Standard 2: Assessment
People with mental health conditions,
including those with co-existing health
conditions, experience improved quality
and length of life, free from stigma and
discrimination 
Strategic Lead
Mental Health
Service Manager
- Mental health
X     Mar-26 a Moray Dementia Plan is develop
in line with Grampian Dementia
Strategy  
5.4 Mental Health Quality
Standard 3
Moving between and out of services Strategic Lead
Mental Health
Service Manager
- Mental health
X     Mar-26 Co-produced written care plans
for transitions between services
are in place  
5.5 Mental Health Quality
Standard 4: Workforce
The mental health and wellbeing workforce
is diverse, skilled, supported and
sustainable, trauma & inequality informed 
Strategic Lead
Mental Health
Service Manager
- Mental health
X     Mar-26 Workforce plan for Mental Health
Services in Moray in place  
5.6 Mental Health Quality
Standard 5
Governance & accountability Strategic Lead
Mental Health
X     Dec-25 Self-assessment against Core
Mental Health Quality Standards
completed  
6 Promoting third sector
and community services
to enable people to
manage their own
physical, social and
mental well-being 
Our communities and third sector partners
provide a vital and valuable contribution to
the levels of prevention, support and
resilience that can be provided in and
across Moray.  This is an area we need to
grow, encourage and nurture in order to
meet increasing demand for low level
needs appropriately.          
increase number of people being
supported by third sector partners
Page 129

Page 130

APPENDIX 1
Page | 14 
6.1 Build the infrastructure and
capacity in the community
to support people to self-
manage
Invite third sectors representation in design
of services and contracts, where there is
an opportunity for working differently.
All Service
managers /
Commissioning
X     Mar-26 Third Sector representation in all
appropriate service redesign or
contract reviews  
6.2 Collaborative Working Increase resilience, sustainability and
growth of third and community led groups
across Moray
Community
Wellbeing
Development
Team
X X   Jun-26 Increase in number of community
led groups supporting wellbeing in
Moray
Groups have increased resilience
and are equipped to continue
delivering services
Increase and improve offer of
services available in communities
across Moray, to support
wellbeing, resilience and
enablement.  
6.3 Partnership Working (a) SET group - review current delivery of
seated exercise classes across Moray
Community
Wellbeing
Development
Team
X X   Jun-26 Sustainability and growth of
groups across Moray 
Increase in capacity of classes for
older people to support their
physical and mental wellbeing  
6.4 Partnership Working (b) Increase partnership working and
opportunities in Moray
Community
Wellbeing
Development
Team
X     Mar-26 New nature and outdoor outings
provided to support mental health
for older people  
6.5 Community Growth Development of Be Active Live Long
(B.A.L.L) groups forum
Community
Wellbeing
Development
Team
X X   Sep-26 An overarching Forum to support
and connect all BALL groups
across Moray is established 
Increase ability to apply and
attract funding to support groups 
Increase in membership numbers 
New BALL groups established in
areas where need identified
Page 130

Page 131

APPENDIX 1
Page | 15 
7 Children Service plan
2023-2026
Plan aims to embed Corporate Parenting
and implement the foundations of The
Promise for Children, Young People and
families of Moray)
Head of Service
/ CSWO            
7.1 Delivery of the 6
improvement priorities
- Improving Outcomes for looked after and
care experienced young people
- Tackling child poverty
- Supporting children and families who
experience challenges due to
disability/neurodiversity
- Keeping children safe
- Improving emotional and mental
wellbeing
- Strengthening family support
Head of Service
/ CSWO
X X     delivery of the actions 
improvements in Key performance
measures identified  
8 Provision of a
Sustainable Locality
Model
Rooted in the principles of proximity,
accessibility, and community engagement,
the locality model seeks to enhance the
responsiveness, effectiveness, and
relevance. of health and social care
provision by decentralising services and
fostering strong partnerships at the
neighbourhood level.              
8.1 To have an updated
Locality Plan in place for
each Moray Locality
Development, monitoring and evaluation of
Locality Plans
Deputy Head of
Service
X     Sep-25 Locality Plan in place  
8.2 Further development of
Locality MDTs and Virtual
wards in community
settings.
Confirmation and implementation of
sustainable model for multi-disciplinary
working across all localities
Deputy Head of
Service
X X   Sep-26 MDT embedded in all localities  
8.3 Development of Locality
Dashboards which align
with Moray wide
performance dashboard
Establish framework of performance
monitoring within localities
Deputy Head of
Service
X     Sep-25 Locality Dashboard established
Page 131

Page 132

APPENDIX 1
Page | 16 
8.4 Involvement of community
members, third sector
members and locality
practitioners in monitoring
the effectiveness of local
service delivery.
Involvement of community members, third
sector members and locality practitioners
in engagement activity and monitoring the
effectiveness of local service delivery.
Deputy Head of
Service
X X   Jun-26 Communities involved in
monitoring effectiveness of local
service delivery   
STRATEGIC THEME - HOME FIRST        
OBJECTIVE 3:  We work together to give you the right care in the right place at the right time      
Key Heading Description Lead 1 2 3 Timescale Outcomes  
9 Discharge Without Delay
(DWD)
Discharge without Delay (DWD) is a
whole-system programme for frail older
people currently accessing Scottish
hospitals, pulling best practice, individual
services and pathways into an integrated
model that strives to deliver
Comprehensive Geriatric Assessment
(CGA) in the timeliest manner, while
ensuring no negative impact from hospital
induced harm or dependency to the
person.          
1. Reduce acute geriatric length of
stay (LOS) by >20% by December
2026 
2. Reduce community hospital/
step-down LOS to 20% by
December 2026
3. Reduce total respective HSCP
delayed discharges by >20% by
December 2026 
4. Less 25% of delayed
discharges are in acute hospitals
by December 2025 
5. Aim acute hospital geriatric
service and community hospital
occupancy to 90% by December
2026  
9.1 Discharge to Assess
(D2A)/HomeFirst
To discharge people home in a timely
manner to minimise hospital induced
dependency. With services providing a
responsive community home care support
to enable discharge without delay.  
tbc X     Dec-25 Reduction in delayed discharges
Page 132

Page 133

APPENDIX 1
Page | 17 
9.2 Community Hospital and
Step Down Rehabilitation
Units
Facilities should be staffed and
empowered to take frail people required
rehabilitation and more prolonged periods
of assessment, ideally from frailty units and
discharge back to communities via agreed
PDD process, both without delay. 
Professional
lead OT / Team
Manager
(Independent
Living)
X X   Dec-26 “To be” status designed and
action plan developed and
approved 
Changes identified in plan are
implemented 
Reduction in length of stay 
Avoidance of unnecessary
admissions :-
Reduction in unnecessary
admissions from Emergency
Department, AMAU and CDU 
Number (& %) of people re-abled
through the D2A/START process
within 12 week target  
9.3 Frailty at Front Door Acute hospitals should deliver early
comprehensive geriatric assessment
(CGA) in specialist acute frailty units from
point of acute admission. 
tbc X     Mar-26 Pathways completed and
communicated 
increase assessments for support
(inc care) undertaken in the home  
9.4 Planned Date of Discharge
(PDD) process and
Integrated Discharge
Teams
Acute hospitals should aspire to single
point of referral for complex discharges
with the process of discharge planning via
MDT proactive advanced discharge date
setting. 
Lead Nurse X X   Dec-26 Increase in % (and number) of
compliant PDD (target to be
defined)  
10 Promotion of Self
Directed Support (SDS)
Options
Increase the promotion and use of SDS
Options (from baseline) to meet individual
needs. 
Increasing choice and control of individual
needs and how their support and care
needs are delivered.          
Quarterly Audits of use of SDS
options (establish baseline)  
10.1 Develop SDS Framework
for options 1, 2 & 3
providers  
SDS Officer /
Procurement
Officer MC,
Provider
Services
Manager
X     Dec-25 Framework for providers
established for SDS options to
promote choice and control driven
by individual preference opposed
to market availability.  Social work
processes and assessment align
with the principles of SDS
Page 133

Page 134

APPENDIX 1
Page | 18 
10.2 Self-evaluation against
national SDS framework of
standards to inform future
requirements to improve
performance and delivery  
SDS Steering
Group
X     Aug-25 Utilising the self-evaluation,
identified areas of improvement
can be identified and a robust
implementation can be developed
to improve practise and peoples
lived experience of accessing
SDS.  Internal process will align
with the national vision for SDS. 
Social work process and
assessment align with the
principles of SDS. 
Commissioning activity aligns with
the principles of SDS.  
10.3 Continue promotion of
independent support and
advise for SDS options  
SDS Steering
Group
X X X Mar-28 Individuals have access to
independent support and advice
enabling them to make informed
decisions around the four options
of SDS.  Individuals have access
to independent SDS Advocacy to
support with accessing SDS.  
OBJECTIVE 4: We help build communities where people are safe                
11 Managing frailty in the
community 
Within the proactive care model, develop a
test of change to integrate community and
acute frailty teams, utilising the e-frailty tool
to proactively identify and case manage
frail patients in order to prevent
deterioration and hospital attendance          
All GP practices have all patients
identified as being frail are
entered into e-frailty system
People tracked by efrailty
changes and plans put into place
via proactive care function (
tracking and short term
intervention and monitoring back
to health and social care baseline)
Reduction in
presentations/readmission rate of
frail patients  
11.1 Identification and
assessment of frailty within
primary care over 65s
E-frailty tool is rolled out across all GP
practices
GP Strategic
Lead / Moray
Frailty Lead
X X   Jun-27 % of MEOC conversations taken
place within community 
12 Public Protection Implementing the Public Protection plan              
12.1   info to be provided            
Page 134

Page 135

APPENDIX 1
Page | 19 
STRATEGIC THEME - PARTNERS IN CARE     
OBJECTIVE 5:  We are an ambitious and effective partnership                
Key Heading Description Lead 1 2 3 Timescale Outcomes  
13 Redesigning Models of
Care
summary description required              
13.1 AHP transformation and
redesign
Support in the community is consolidated tbc X X   Sep-26 Model of provision embedded  
13.2 Community Hospital
Redesign  
Review and redesign model for community
hospitals using research undertaken in
Moray, and learning from other areas. 
Engaging with stakeholders to consider
options and ultimately establish the model
for Moray
Head of Service X X X Dec-27 Model for community hospitals in
Moray agreed  
13.3 Moving with Dignity
(Proportionate Care )
Following pilot scheme, completion of
evaluation and wider implementation and
training plan to reduce requirement of care
hours for those meeting criteria.  
Head of Service X X   Jun-26 implementation plan completed 
reduction in care hours required
for those meeting criteria  
13.4 GMED - redesign Through the redesign, the service will find
the balance between financial pressure,
clinical governance and patient safety, staff
governance with a focus on prevention 
Service Manager
- GMED
X     Dec-26 Model of service delivery agreed
and implemented  
14 Care at Home Strategic review and redesign of the care
at home service to create options and
capacity within a sustainable model that
will meet future needs
Service Manager
- Provider
Services            
14.1 Strategic Review and
redesign of care at home
service  
Service Manager
- Provider
Services 
X
Sept-25  Redesigned model of care agreed
with plan for implementation 
Page 135

Page 136

APPENDIX 1
Page | 20 
14.2 Adoption of "Moving with
Dignity" protocol across
HSCM services and
partner providers
Implement protocols, train workforce and
embed provision of Proportionate Care for
those people for whom it is appropriate 
Service Manager
- Provider
Services 
X
Mar-26 Increase efficiency by releasing
care hours required for those who
are able to utilise equipment.  
15 Review and Redesign of
Adults Day Care
services
A full redesign and modernisation of Adult
day services which will see individuals
being able to access day support which is
person centred and meets their agreed
outcomes and aspiration. Where
appropriate day service will be provided
within their own local communities
Service Manager
- Provider
Services
X     Mar-26 Redesign model agreed and
implemented 
Transportation policy revised and
adopted  
16 Suitable Housing -
Strategic oversight of
accommodation
requirements 
In collaboration with partners in developing
the Local Housing Strategy (SHIP), work
with people and their families in
establishing tenancies in appropriate
accommodation to prevent inappropriate
long-term placement and breakdown of
care.
Service Manager
Learning
Disabilities /
Localities
Manager Elgin            
16.1 Learning Disability long
term sustainable
accommodation
In collaboration with partners supporting
people with learning disabilities and their
families in establishing tenancies in new
supported accommodation. 
Continuation of LD Housing Projects in
collaboration with partners to develop
sustainable accommodation provision
within Moray
Service Manager X X X ongoing Reduction in the out of area
placements and associated costs 
Increase in the number of people
with learning disabilities
establishing tenancies 
16.2 Older People - provision
of sustainable supported
accommodation
Local Housing Strategy Priority 3 
Partnership working maximises housing
role in improving health and wellbeing 
Define model for mixed groups for extra
care
Local Housing
Strategy
Steering Group
X     Aug-25 Requirement defined for
incorporating into the Local
Housing Strategy
Page 136

Page 137

APPENDIX 1
Page | 21 
16.3 Mental health - provision
of sustainable,
appropriate supported
accommodation
Assessment of need within Moray and
development of plan to address need
Local Housing
Strategy
Steering Group
X X   Sep-26 Plan for provision of supported
accommodation 
17 Review Approaches for
Social Work practice and
process 
Review of approach and associated
policies and guidance used across all
teams to ensure consistency and equity of
service provision.
Head of
Services and
Chief Social
Work Officer
X     Jun-26 Develop agreed pathways and
process (inc SOP) for
Assessment and Review (Care at
Home, Care homes and other
pathways from assessment
process) 
Reduce waiting times for
individuals requiring assessment
and ensure where possible people
are not dependent on formal care
and support 
Reduction in unmet needs 
agreed single assessment and
review pathways/ processes
across both community and
hospital  
18 GIRFE Getting it Right For Everyone (GIRFE) will
take a multi-agency approach to health
and social care support and services from
young adulthood to end of life. 
18.1 To embed the GIRFE
toolkit and principles into
the planning and delivery
of services.
The promotion of GIRFE to key Moray
stakeholder groups 
GIRFE lead
officer
X X   Mar-26 GIRFE principles embedded in
service delivery  
19 Support for long term
conditions   
Support people with long term conditions
to stay well and independent for as long as
possible through a variety of tools and
models.              
19.1 Heart of Moray - Making it
easier to improve our
health and wellbeing.
- Diabetes
Using research from DHI and working with
partners to develop new range of services
to help people improve their diet and
lifestyle.  Initial focus to work with people
aged 40 and under who have type 2
diabetes
Lead Dietician X X   Sep-26 Improvement in health of
participants in the programme
Page 137

Page 138

APPENDIX 1
Page | 22 
19.2 Consolidation of palliative
cancer services
Consolidation of palliative cancer services
through engagement with stakeholders
Chief Nurse X     Dec-25 Sustainable model of care in
place
Support available to those who
need it  
19.3 Pharmacological Reviews Working in collaboration with GP practices
to seek opportunities to make therapeutic
and generic switches from high cost and
high volume areas and overall to support
cost effective prescribing culture
Lead Pharmacist
Primary Care
X     Mar-26 Reduction in cost of medications
prescribed  
19.4 Establishment of a Moray
Dementia Strategy and
Moray Dementia Pathway
in line with Grampian and
National dementia delivery
plans.
Establishment of a Moray Dementia
Strategy and Moray Dementia Pathway in
line with Grampian and National dementia
delivery plans.
Mental Health
Services
Manager
X     Sep-25 Moray Dementia pathway in place  
19.5 Embed promotion of
technology enabled care
(TEC) options within
assessment process to
increase use and impact of
TEC, supporting self-
management (i.e. to
support management of
longer-term conditions)
Embed promotion of technology enabled
care (TEC) options within assessment
process to increase use and impact of
TEC, supporting self-management (i.e. to
support management of longer-term
conditions)
Digital Health
Lead
X X X Mar-28 Increase in use of TEC to support
people to live independently  
20 Moray Growth Deal Working with DHI as part of the Moray
Growth Deal to design the sustainable
services for the future that enable people
to live as independently as possible for as
long as possible.  (Community
Connections, Personal Data Store, Smart
Housing) 
Increase ratio of those supported
at home with technology enabled
care rather than in person care 
Impact of demographic growth on
care at home provision - manage
demographic growth via hybrid
approaches to care as opposed to
in person care  
20.1 LL1 Supported Self-
Management
Improving the health and wellbeing of local
people with friendly new uses of local
community spaces. https://heartof.co.uk/ 
DHI /  X     Mar-26 Increase number onboarding and
engaging with supports  
20.2 LL2 Long-term Condition
Co-management
Development of a community occupational
therapy digital pathway.
DHI /  X     Mar-26 Pathway in place
Increase in people using TEC
Page 138

Page 139

APPENDIX 1
Page | 23 
20.3 LL3 Care in Place Development of a Personal Data Store and
the Community Connections Moray digital
platform
DHI / Deputy
Head of Service
X X   Jun-25 Community connections available
on Webpage  
20.4 LL 4 Smart Housing/Smart
Communities 
Development of a digital platform for smart
housing and monitoring community patient
health within a residential setting. 
DHI /  X     Mar-26 Digital platform defined  
20.5 LL 5 Mental Wellbeing Development of Mental Health Pathway
within the Community Connections Moray
digital platform
DHI /  X     Mar-26 Mental Health pathway in place  
Page 139

Page 140

APPENDIX 1
Page | 24 
Strategic Leadership, Planning and Performance      
E
N
A
B
L
E
R
S
E1 Digital Health and Care To improve the care and wellbeing of
people in Moray by making best use of
digital technologies in the design and
delivery of services 
Ensuring we utilise modern technologies,
systems and tools that assist and empower
our workforce to deliver high quality
services
Digital Health
Project Board
X X X   Localisation of the National Digital
Health and Care Strategy 2021.  
E1.1 Develop Strategy for
TEC
Developing and implementing a strategic
approach and framework for TEC support,
based on evidence, to provide sustainable
options through collaboration with DHI
Project Board
A2D / DHI /
Team manager
(OT)
X     Mar-26 Model of support is in place and
shared widely  
E1.2 Implementation of the
Analogue to Digital
Implementation Plan  
Senior Project
Officer
X     Dec-25 All existing analogue customers
transferred to digital equipment by
December 2025  
E1.3 New Social Work and
Social Care
Information
Management System
Procure and Implement a new Information
Management system  for Social Work and
Social Care with the scope to develop and
integrated information management
system across wider services providing
support to individuals and families
CSWO / Senior
Project Officer
X X   Mar-27 Procurement completed and
tender awarded. 
System implemented 
services migrated and operational
Page 140

Page 141

APPENDIX 1
Page | 25 
E1.4 Solution for Care at
Home scheduling 
Business Case, procurement and
implementation of staff scheduling system
for Care at home
CSWO / Senior
Project Officer
X     Aug-25 System implemented and
operational  
E1.5 Incorporating new
technologies
Work in collaboration with partners to
explore the opportunities of Artificial
intelligence for performance of routine
tasks to achieve efficiencies
Digital lead X     Mar-26 Implementation of use of artificial
intelligence in various functions to
release capacity for other tasks.  
E2 Strategic
Commissioning 
Develop the strategic framework and
governance to involve all stakeholders in
being partners in provision of care and
support in communities
SMT / Strategic
Planning and
Commissioning
Group
X X   Mar-27 Strategic Framework and
governance approved and
implemented  
E3 Communications Develop and embed a strategy to inform
and engage with all stakeholders and to
include management of expectations
Corporate
Manager / SMT
X     Sep-25 Communications Strategy
approved  
E4 Workforce Ensuring we have a Workforce that is agile
and motivated to meet the challenges
presented and that is sustainable and safe
with a focus on staff wellbeing. 
Our volunteers provide a vital and valuable
contribution to the levels of support that
can be provided to our communities.  This
is an area we need to grow in order to
meet needs appropriately.
SMT       Sep-25 Annual Report (via NHSG) 
Workforce plan implemented 
Increase in Volunteer numbers
and roles  
E5 Infrastructure Working with partners, review of
occupancy and use of premises to seek
opportunities for rationalisation or
collaboration with partners to secure
sustainable and efficient use of buildings
and premises
Infrastructure
Board
X X X ongoing Sustainable model for vaccination
delivery
Accommodation assessed as
suitable for service delivery  
E6 Performance  and
Quality Assurance &
Improvement
Frameworks
Develop framework to further support
informed decision making
Deputy head of
service 
X X   Dec-26 Performance framework updated
and implemented
Quality Assurance Framework
embedded
Page 141

Page 142

APPENDIX 1
Page | 26 
E7 Governance SDS Framework
Review of specific policies
Implementation of learning from audits and
inspections
SMT X X X To March
2027
Policy and protocol are updated
and implemented 
Positive inspection and audit
reports received  
E8 Finance Recovery Plan, Mid Term Financial Plan Chief Finance
Officer
X X X ongoing Budget savings plan approved
and delivered 
Page 142

Page 143

REPORT TO: MORAY INTEGRATION JOINT BOARD ON 27 MARCH 2025 
SUBJECT: EQUALITIES MAINSTREAMING PROGRESS REPORT 2021-2024 
BY:  CORPORATE MANAGER AND PUBLIC HEALTH CONSULTANT 
1. REASON FOR REPORT 
1.1 To seek approval of the Draft Moray Integration Joint Board (MIJB) Equality
Mainstreaming Progress Report 2021-2024. 
1.2 To inform the Board of the intention to present the Final Report to the Board on
29 May 2025. 
1.3 To inform the Board of the intention to present the Equalities and
Mainstreaming and Outcomes for 2025-2029 to the Board on 29 May 2025. 
2. RECOMMENDATION 
2.1 It is recommended that the Board: - 
i) consider and approve the Draft MIJB Equality Mainstreaming
Progress report 2021-24 (Appendix 1) for publication by April 2025; 
ii) request the further development of the report, with a Final version to
be presented to the Board on 29 May 2025 for publication May 2025;
and 
iii) request that the Final MIJB Equality Mainstreaming Report 2021-24
includes proposed equality outcomes for the period 2025-2029,
aligned with the strategic priorities outlined in Moray Integration
Joint Board Strategic Plan “Partners in Care 2022 – 2032”. 
3. BACKGROUND 
The Public Sector Equality Duty 
3.1 The Public Sector Equality Duty, laid out in the Equality Act 2010 (the Act),
came into force in Scotland in April 2011.  This equality duty is often referred to
as the “general duty” and it requires public authorities to have “due regard” to
the need to: 
Item 10.
Page 143

Page 144

•  Eliminate unlawful discrimination, harassment and victimisation and other
conduct that is prohibited by the Act; 
•  Advance equality of opportunity between people who share a relevant
protected characteristic and those who do not; and, 
•  Foster good relations between people who share a protected characteristic
and those who do not. 
3.2 The general duty covers the following protected characteristics: age; disability;
sex; gender reassignment; pregnancy and maternity; sexual orientation;
marriage and civil partnership; religion, belief, or lack of religion/belief; and
race. 
Equalities Outcomes
3.3 Integration Joint Boards were added to the list of public authorities subject to
the requirements of the Act in 2015 and were required to publish Equality and
Mainstreaming Outcomes plans by the end of April 2016. 
3.4 The first MIJB Equality Outcomes and Mainstreaming Equalities Framework
was published in April 2016 following approval by the Board on 28 April 2016
(para 7 of the minute refers). The Equality Outcomes contained within the
framework were subject to consultation, including representation from people
who have protected characteristics, and were intended to contribute to the
strategic priorities and shifts identified within the Strategic Commissioning Plan. 
A report on progress was submitted to the Board on 26 April 2018 advising
further work was required (para 8 of the minute refers) with a final report agreed
by the Board on 28 June 2018 (para 11 of the minute refers). 
3.5 In the 2018 report it was identified that the wording of the outcomes was too
specific to facilitate reporting of the progress made across the wider service. It
was agreed that revised outcomes should be developed in tandem with the
development of the new Strategic Plan and presented for consideration prior to
March 2019. There were delays in the compilation and approval of the Strategic
Plan and Transformation Plan which impacted on the ability to progress the
revision of equality outcomes prior to the Coronavirus Pandemic. 
3.6 The Pandemic impacted on all aspects of work for Health and Social Care
Services and will continue to do so with regard to the health debt that has
accrued, some of which is known but most of which is currently unquantified
and some is not yet known. 
3.7 There is a requirement to review Equality and Mainstreaming Outcomes at
least every four years; meaning the first substantive review in Moray was due
by 1 April 2020. A short life working group was established early 2021 to rework
the outcomes and provide a basis for reporting performance and demonstrating
implementation across the whole of Health and Social Care services, whilst
ensuring alignment to the Strategic Plan. 
3.8 The Board approved the revised MIJB set of equality outcomes and the specific
focuses at its meeting on 29 April 2021 (para 5 of the minute refers). 
Equality Mainstreaming Progress Report 2021-24
3.9 The Equality Act 2010 (Specific Duties) (Scotland) Regulations 2012 (the
Regulations) impose “specific duties” on Scottish public authorities to publish a
Page 144

Page 145

set of Equality Outcomes and a report showing progress being made in
mainstreaming equality at intervals of not more than two years. 
3.10 A progress report was submitted to the Board in April 2018 and following
additional work, was approved at the Board meeting on 26 June 2018 (para 11
of the draft Minute refers).  The next report was due to be submitted in April
2020, but this was delayed due to the priority of responding to the pandemic. 
3.11 The Board approved the Equality Mainstreaming Progress Report 2019-2021 at
its meeting on 29 April 2021 (para 5 of the minute refers). 
3.12 Health and Social Care Moray (HSCM) did not publish a progress report
against the outcomes in 2023.  The Corporate Manager has discussed this with
The European Human Rights Commission (EHRC) Office who have accepted
HSCM’s position based on its commitment to do so as soon as possible. 
3.13 The Regulations specify that Equality Mainstreaming Progress Reports must be
clearly identifiable and accessible to the public.  Following approval, the report
will be: 
• Designed to meet accessibility standards
• Published on the HSCM website
• Made available in alternative formats upon request
• Copies made available to relevant groups and organisations representing
people with protected characteristics. 
3.14 This approach ensures compliance with Equality and Human Rights
Commission recommendations for accessible public information. 
4. KEY MATTERS RELEVANT TO RECOMMENDATION 
4.1 This report has been developed under the governance of the Strategic Planning
and Commissioning Group (SPCG) with the implementation support from
HSCM. 
4.2 The SPCG will be responsible for monitoring and reviewing the equality
outcomes, to ensure alignment with the priorities outlined in the Moray
Integration Joint Board Strategic Plan “Partners in Care 2022 – 2032”. 
4.3 A comprehensive progress update on the Equality Outcomes implementation
will be presented to the Board by April 2027, marking the midpoint of the 2025-
2029 outcomes period. 
5. SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes
Improvement Plan (LOIP)) and Moray Integration Joint
Board Strategic Plan “Partners in Care 2022 – 2032”
This report forms part of the governance arrangements of MIJB Strategic
Plan. 
(b) Policy and Legal
It is recognised that the MIJB is directly subject to the Public Sector
Equality Duty and therefore continues to address equalities matters
Page 145

Page 146

through integration arrangements to ensure compliance with the Equality
Act 2010 (specific duties) (Scotland) Regulations 2012.   
(c) Financial implications
None arising directly from this report. 
(d) Risk Implications and Mitigation
Failure to comply with the commitments of the Public Sector Equality
Duty would result in services delegated to the MIJB not meeting the
needs of people who share protected characteristics, leading to poorer
outcomes and a widening inequality gap. 
(e) Staffing Implications
None arising directly from this report. 
(f) Property
None arising directly from this report. 
(g) Equalities/Socio Economic Impact
None arising directly from this report. 
(h) Climate Change and Biodiversity Impacts
None arising directly from this report. 
(i) Directions
None arising directly from this report. 
(j) Consultations
Consultations have been undertaken with Service Managers
(Operational Management Team), HSCM Senior Management Team 
6. CONCLUSION 
6.1 This draft report demonstrates progress against the Equalities Outcomes
and set in 2021 and outlines mainstreaming achievements to date. 
6.2 A final version of the report will be presented to the Board in May 2025 for
approval. 
6.3 The Final MIJB Equality Mainstreaming Report 2021-24 will include
proposed equality outcomes for the period 2025-2029 for approval by
MIJB, ensuring continued aligned with the strategic priorities outlined in
MIJB Strategic Plan “Partners in Care 2022 – 2032”. 
Author of Report: Sonya Duncan, Interim Corporate Manager
Elizabeth Robinson, Public Health Consultant
Isla Whyte, Corporate Business Support Manager
Background Papers: with authors
Ref: 
Page 146

Page 147

APPENDIX 1
1
MORAY INTEGRATION JOINT BOARD  
Equality Mainstreaming & Outcomes Draft Report 2021-2024                
This report provides an overview of progress made in achieving Moray
Integration Joint Board’s equality outcomes over the last three years. It
identifies areas for improvement and priorities for the next four years in
relation to equalities mainstreaming. The report is compliant with the Equality
Act 2010, supplementary regulations and guidance issued by the Equality and
Human Rights Commission. 
Item 10.
Page 147

Page 148

APPENDIX 1
2
1. Introduction  
2. Background 
3. The Equality Act and Fairer Scotland Duty 
4. Moray in the context of Equalities 
5. Joint Strategic Needs Assessment 
6. Mainstreaming 
• Leadership
• Board Structure and Staff 
• Getting it Right for Everyone (GIRFE) 
• IIAs 
7. Equality Outcomes set out in 2019-2021 report and progress report 
• Review of Equality Outcomes
➢ Moray Community Appointment Day
➢ Day Opportunities Team
➢ Engagement Equality Groups
➢ Carers Strategy – Engagement/Feedback
➢ Making Recovery Ream (MRR) Partnership
➢ New Scots
➢ Moray Mental Health Strategic Group 
• Working with Our Partners
➢ Frailty
➢ Links to Partners Plans 
• Horizon Scanning
➢ Self-Directed Support (SDS)
➢ The Human Rights Bill
➢ Asylum Seekers Health Needs Assessment  
8. Priorities for 2025-2029 
Appendix 1 – To follow.   
Page 148

Page 149

APPENDIX 1
3
1. Introduction 
The Moray Integration Joint Board (MIJB), as a public body, is responsible for the
planning and oversight of health and social care services across Moray. These
services are deleted to the MIJB by our partners, NHS Grampian, and Moray
Council. They are delivered by the Moray Health and Social Care Partnership
(HSCM). 
The Equality Act 2010 requires MIJB to:
• Write a report which explains what it will do as part of its day to day working to
ensure people are treated fairly and (Mainstreaming)
• Public equality outcomes every 4 years. 
2. Background 
MIJB’s strategic plan ‘Partners in Care, 2022-2032’ is the IJB’s third plan, and sets
out MIJB’s strategic vision and priorities, and sets out how we will use our integrated
resources to deliver outcomes for the citizens of Moray. The vision for MIJB is:
‘We come together as equal and valued partners in care to achieve the best health
and wellbeing possible for everyone in Moray throughout their lives.’ 
The 3 Strategic Themes: 
Building Resilience: Taking greater responsibility for our
health and wellbeing
Home First: Being supported at home or in a homely
setting as far as possible
Partners in Care: Making choices and taking control over
decisions affecting our care and support 
3. The Equality Act and Fairer Scotland Duty 
The Equality Act 2010 states that MIJB must:
• Write a report that explains what it will do as part of its day to day working to
make sure that people are treated fairly and;
• Publish equality outcomes every 4 years
• Consider how their decisions affect different groups of people
• Ensure equality is part of all planning and decision-making
• Work to remove barriers that might stop people accessing services
• Involve local communities and people with lived experience in their planning 
Page 149

Page 150

APPENDIX 1
4
Section 149 of The Equality Act 2010 imposes as duty on ‘public authorities and
bodies’ to make sure all people are treated fairly. The three requirements of the
general duty are:
• Eliminate discrimination, harassment, victimisation, and any other conduct
that is prohibited by the Act.
• Advance equality of opportunity between persons who share a relevant
protected characteristic and persons who do not share it
• Foster good relations between persons who share a relevant protected
characteristic and persons who do not share it. 
There are nine protected characteristics listed in the Act: 
• Age
• Disability
• Sex
• Gender reassignment
• Pregnancy and maternity
• Sexual orientation
• Marriage and civil partnership
• Religion and belief or lack of religion/belief
• Race 
The MIJB should also foster good relations between people from different protected
characteristic groups. This will allow us all to recognise and understand the needs of
different people. 
The Fairer Scotland Duty, which is part of the Equality Act, requires public bodies to
consider how they can reduce inequalities caused by social and economic
disadvantage when making decisions. People living in poverty or difficult social
circumstances often experience poorer health and wellbeing outcomes.    
Page 150

Page 151

APPENDIX 1
5
4. Moray in the context of Equalities 
5. Joint Strategic Needs Assessment 
Following the last Joint Strategic Needs Assessment being written in 2018, a revised
version was developed during 2024. The Needs Assessment attempts to provide a
profile of the health of the Moray population, including the building blocks of health –
housing, income, environment – which most significantly influence health. It then
goes on to consider which diseases and illnesses pose the greatest threat to
population health and well-being.  This information is designed to help the Health
and Social Care Partnership to consider how to use limited resources for maximum
benefit, planning interventions and delivering services to enhance prevention,
improve disease outcomes, and reduce health inequalities.  
The following areas are highlighted from amongst the wealth of intelligence
compiled.  
Page 151

Page 152

APPENDIX 1
6
  
1. There are continuing inequalities in health status across Moray, with an
evident association between level of poverty and deprivation (including cost of
living, poor housing, transport, employment) and ill health and death.   
2. Lives are being cut short through suicide, drug and alcohol related deaths,
conditions which are significantly affected by deprivation. In 2022, admissions
for alcohol-related conditions were almost 4 times higher among those living
in the most deprived areas in Moray as compared to the least deprived.  
3. The population is predicted to continue ageing, with a growing proportion
represented by adults over the age of sixty-five, and growing numbers of
adults aged over eighty, with implications for increasing ill health.   
4. Significant demand for health and social care services arise from sometimes
preventable chronic disease, and a growing proportion of the population is
experiencing more than one condition (“multi-morbidity”).   
5. There is significant death and poor health due to often modifiable behaviours,
such as lack of exercise, smoking, alcohol and drug use.   
6. A small number of individuals, with higher numbers coming from more
deprived areas, require significant amounts of healthcare spending. This
warrants further detailed analysis.   
However, we recognise that there are gaps, for example, around the specific needs
of people with learning disabilities, people who experience gender based violence,
people who use services intensively and ethnicity data which is poorly recorded; it is
recommended that further work takes place to understand the needs and views of
particularly vulnerable populations in more depth.  There are also limitations in the
data; for example, service activity only tells us about those who use services and not
about those who need services but are not able to access them. As such, the data
used in this report must be interpreted with caution and used in conjunction with
qualitative data from Moray residents and workforce. 
6. Mainstreaming 
Mainstreaming quality for MIJB means that it considers equality in everything they
do. Equality consideration is embedded in all aspects of how the IJB and HSCM
works, from strategic planning to service delivery. The goal is to make equality and
fairness a natural part of the IJB’s culture, rather than something that is considered
as an add-on. An example of this would be the budget planning; the IJB analyses
how funding decisions might affect groups from those listed in the protected
characteristics and those facing economic challenges. 
Page 152

Page 153

APPENDIX 1
7
Leadership
MIJB Structure and Staff
The Scottish Government outlines who the members of the Moray Integration Joint
Board should be. Membership of the MIJB includes citizens with experience of using
health and care services alongside local councillors, NHS Board members, staff from
the Health and Social Care Partnership and a representative from voluntary
organisations. 
The board meets monthly. It alternates between formal meetings where decisions
are made (those are web-cast and are accessible by the public), they are also
recorded and available online for 6 months, and informal development sessions
where the board have more in-depth discussions on specific issues and topics e.g.
finance, strategy, current issues.
Deputations can be made to the formal meetings by spokesperson of any
organisation or group. All MIJB papers are available on the Council website. The
MIJB has 2 sub-committees; Audit, Performance and Risk and Clinical and Care
Governance.
The MIJB has only two staff, the Chief Officer and the Chief Finance Officer and so
is not required to publish gender pay gap information nor statements on equal pay. 
The MIJB continues to work alongside its partners, to ensure the Moray Health and
Social Care Partnership benefits from a diverse workforce, which reflects the
residents of Moray and promotes fairness. Reports from Moray Council and NHS
Grampian are available online, detailing further information in relation to the
workforce. 
Page 153

Page 154

APPENDIX 1
8
Getting It Right for Everyone (GIRFE)
Moray Health and Social Care Partnership has committed to being a pathfinder for
GIRFE. This involves co-designing the approach with Scottish Government. GIRFE
represents a multi-agency approach to health and social care support and services
spanning from young adulthood to end of life care. It will establish the future practice
model for health and social care professionals in HSCM, and influence the design
and delivery of services, ensuring people's needs are met appropriately.
GIRFE aims to provide a more personalised pathway to access help and support
when needed. It places individuals at the centre of all decision-making affecting
them, with a meaningful and consistent approach regardless of the support required
at any life stage.
Moray Health and Social Care Partnership are currently embedding the GIRFE
toolkit and principles into the planning and delivery of services.
Why do an Integrated Impact Assessment (IIA)
• Legal requirement and ensures we are adhering to the Equality Act 2010 and
addressing impacts on protected characteristics
• Increase collaboration with communities and partners who have experience of
working with groups who have protected characteristics
• Individuals with lived experience of inequality and exclusion will have the
opportunity to share their views, concerns and suggestions for improvements
• Improve understanding and build relationships between individuals and groups
who share protected characteristics and those who do not
• Develop better policies, procedures, strategies, and practices, based on evidence 
An equality impact assessment can identify the anticipated likely effects of a policy,
procedure, strategy, or practice. The impacts should be reviewed and this may
require the Equality Impact Assessment to be updated. 
7. Equality Outcomes set out in 2019-2021 report and progress report
Review of Equality Outcomes
What we said: A key priority will be to continue the review work completed to date
incorporating the potential health and social care debt impacts and consequences of
Covid to ensure that key focus is directed to the greatest need. We will consult more
widely with communities to ensure they reflect their desired outcomes and to further
develop the reporting of data against the measures identified. This information will be
reported to the Strategic Planning and Commissioning Group (SPCG) which will
have oversight and be able to provide clear recommendations in relation to how
Equality Issues are supported, governed, monitored and driven forward. SPCG will
Page 154

Page 155

APPENDIX 1
9
also explore how our commissioning activity, both internal and external, can better
support the delivery of equality outcomes. 
Examples of what we have been doing: 
Moray Community Appointment Day
With a focus on addressing the lengthy post covid waiting times, HSCM organised
an event to support people who were waiting for treatment. The event focused on
supporting people with joint, bone and muscle problems. Over 120 people attended
the event and were supported by a mix of physiotherapists, podiatrists, occupational
therapists, nutrition and dietetic specialists in Moray Sports Centre in Elgin. The
event was also supported by charities and community groups who also attended to
advise people of how they can also provide support, with issues such as mental
health, cost of living, arthritis, home energy cost and general fitness. A video link to
the event is available here. 
Day Opportunities Team
The COVID-19 pandemic necessitated the closure of building-based day services,
which created an opportunity for service transformation. Following extensive
engagement with people who access services, we identified a clear need for person-
centred, flexible support options.
In response, our Self-Directed Support (SDS) Enablers collaborated closely with the
Social Work team to develop individualised support plans focused on meaningful
outcomes. This approach successfully supported approximately 100 carers and care
recipients during this challenging period. Our methodology centred on improved
communication, relationship building, and working with unpaid carers to envision and
achieve what constitutes 'a good life' for them.  The team take a person centred,
strength and asset-based approach that is community led supporting individuals to
reconnect with their own communities wherever possible.
Following a successful pilot program, the Moray Integration Joint Board (MIJB)
approved the permanent implementation of this approach in June 2022. To meet
growing demand, we three additional SDS Enablers were recruited, completing the
team establishment by October 2022.
The positive impact of this transformation is reflected in feedback from service users,
including: 'I can't believe how much you have done for D, which has really benefitted
her mental health and wellbeing.'"
Page 155

Page 156

APPENDIX 1
10 
Engagement with Equality Groups
What we said: We recognize that people with protected characteristics must help
shape our equality goals - this is both a legal requirement and essential for effective
outcomes. Though COVID-19 limited our engagement efforts, we are forming a
dedicated working group to Priorities identified in Equalities and Mainstreaming
Report 2019/21 address this gap. This group will improve how we connect with
diverse communities, making it easier for everyone to participate in developing and
reviewing our services. We are committed to ensuring all voices are heard as we
move forward
Examples of what we have been doing: 
Carers Strategy – Engagement/Feedback 
Engagement sessions were held with unpaid carers in January 2021, during the
COVID-19 pandemic to explore what a meaningful break would like for them, this
feedback was collated and incorporated into wider engagement sessions with unpaid
carers when developing the Moray Carers Strategy Recognised, Valued, Supported
(2023-2026)  The wider engagement sessions took place as focus groups in August
2021, with an on-line survey launched on 1st October 2021 and remained open for a
four week period.  There was a total of 181 responses to the survey, with 85% of
those responding identifying as female, and 15% who identified as male.  Almost half
of those who responded were providing care for more than 50 hours per week. 
Carers reported having “time for me” and “having a few hours to myself- a whole day
would be bliss” would support them to look after their own health and wellbeing. 
Carers responded that having “time out for myself to pursue hobbies whilst my
partner was cared for in my absence” would support them to have a life alongside
their caring role as “the relentless nature of caring is relentless”.  Carers responded
saying being able to “catch up on sleep” and having “a day out of the house relaxing”
is what a meaningful break would look like for them. 
Page 156

Page 157

APPENDIX 1
11 
Making Recovery Ream (MRR) Partnership 
HSCM recognises the value and added benefit that lived and living experience
brings to ongoing service improvements and developments.  Collaborative and co-
productive working relationships have been established for some time in Moray via
the MRR Partnership.  MRR was established in 2014/15 to take a co-produced
approach to the delivery of the local mental health and wellbeing strategy.  The
group is designed to be a meaningful and mutual balance of lived experience and
professional expertise. The partnership meets in accessible spaces both off-line and
online and takes a strengths-based approach underpinned by CHIME values. 
CHIME is an evidence-based framework for recovery. The partnership has a
commitment to share skills, knowledge and resources in a mutually supportive way
(recognising that we may have different levels of resource, but we are all assets).
HSCM also work closely with a local social enterprise, The Moray Wellbeing Hub,
who lead on a ‘Collective Voice’ initiative to gather, collate and feedback the views of
members of the public with lived and living experience of mental health challenges. 
This has been instrumental in many ways, from establishing lived experience peers
delivering support on our inpatient mental health ward to informing and shaping
commissioned contracts for mental health support recently procured in late 2024. 
The Moray Wellbeing Hub facilitate peer support and training events all over Moray
and have an ’always on’ listening ear.  They have also undertaken specific pieces of
work when funded to do so for example from the Drug and Alcohol Partnership. 
During recent commissioning and procurement work HSCM and lived experience
representative co-produced the service specification that went out to market. 
Thereafter community members with lived and living experience participated on the
evaluation panel to score the submissions received therefore ultimately influencing
the successful awards of contract. 
New Scots  
In Moray there have been 19 asylum seeking young people via the National Transfer
Scheme. There is now a care-based language approach used, where Moray has
adopted the term ‘New Scots’ rather than ‘Unaccompanied Asylum Seeking Children’
(UASC). 
On arrival in Moray, New Scots are supported by the Throughcare & Aftercare Team
as Looked After Children and are offered accommodation in either dual occupancy
housing or Supported Lodgings, depending on their assessed needs. 
To date, 12 New Scots have been granted asylum and have been supported in
making longer-term plans. For example, two young people have moved to their own
tenancies in Moray and one young person started a course at Dundee College.
Other young people have relocated to other areas in the United Kingdom including
Glasgow and London. This has been in order to relocate closer to members of their
community. 
Page 157

Page 158

APPENDIX 1
12 
Moray Mental Health Strategic Group
The Moray Mental Health Strategic Group, established in 2024 has delivered the
following outcomes: 
Created a comprehensive Moray mental health service delivery plan with clearly
defined development priorities, developed with direct input from people accessing
services and operational staff. 
Established a multi-service governance framework that monitors, evaluates and
reports on mental health service delivery across Moray, bringing together third sector
and public sector services. 
Developed early intervention, prevention and self-management resources and
protocols.
Implemented a structured approach to mental health service improvement organised
around five quality standards:
1. Mental Health Quality Standard 1: Access
2. Mental Health Quality Standard 2: Assessment, Care Planning, Treatment &
Support
3. Mental Health Quality Standard 3: Moving between and out of services
4. Mental Health Quality Standard 4: Workforce
5. Mental Health Quality Standard 5: Governance & accountability
Created a regular reporting system with six-monthly progress updates to the MIJB.
Achieved integration of perspectives across sectors, establishing a whole-system
approach to mental health service delivery in Moray. 
Page 158

Page 159

APPENDIX 1
13 
Working with our Partners 
What we said: We will work closely with our partners across the public sector to meet
our equality duties, particularly in areas like employment practices and procurement.
We will continue collaborating with Integrate Grampian to better understand our
diverse population's needs and coordinate our equality efforts throughout the region. 
Examples of what we have been doing: 
Frailty 
Over the past 18 months, Health and Social Care Moray participated in the National
Frailty Collaborative, facilitated by Health Improvement Scotland. This collaboration
resulted in Moray establishing a Frailty Action Plan aligned with broader Grampian
initiatives. The key outcomes from this work include:
• To create the conditions for a whole system approach to frailty within Health
and Social Care Moray encompassing community initiatives to promote aging
well, early identification within Primary Care, the assessment of frailty at the
front door, and a range of related interventions and responses.
• The early identification of frailty in both primary and secondary care settings.
• A proactive integrated planning and case management approach to ensure
optimal outcomes for the individual.
• Active engagement with the public, health and social care staff and third
sector/community groups to promote healthy ageing practices.
• Collaboration with the Digital Health Institute to maximise the potential for
digital innovation; from a prevention and early intervention approach, through
to condition monitoring and self-management.
• Integration of Moray’s frailty initiatives with the broader NHS Grampian Frailty
Network, creating a cohesive regional approach. 
A Moray Frailty Delivery Group, with an associated delivery plan, continues to
progress the work developed through the national collaborative. The group works
closely with leads in Aberdeen City and Aberdeen Shire through the work of the
Grampian Frailty Group. 
Links to partners plans: 
Moray Council Equalities page - Equalities - Public Sector Duties - Moray Council 
NHS Anchors Grampian Plan - https://www.nhsgrampian.org/about-
us/planforthefuture/what-we-intend-to-do/places/anchor/ 
NHS G Race Equality Scheme
https://www.nhsgrampian.org/globalassets/foidocument/foi-public-documents1---all-
documents/mainstreaming-report-april-2021-march-2023-as-at-12th-april-2023.pdf   
Page 159

Page 160

APPENDIX 1
14 
Horizon Scanning
What we said:  Future Planning
We are improving how we spot potential inequalities across our system. By
identifying early signs of change in our communities, especially for vulnerable
groups, we can take timely action and access available resources. The Independent
Review of Adult Social Care in Scotland will significantly influence our approach as
we implement its key recommendations.
Service Development
The recently approved Self-Directed Support standards will help us expand
understanding of SDS options and focus on personal outcomes through our 3
Conversations model. We are also reviewing the Moray Carer Strategy to support
the growing number of unpaid carers needed for our aging population and those with
long-term conditions. Additionally, we are monitoring how new legislation, including
Human Rights in Scots Law, will impact our services.
Examples of what we have been doing:
Self-Directed Support (SDS)
The SDS Framework of Standards (2024) support the implementation of SDS in line
with the statutory guidance which accompanies the Social Care (Self-Directed
Support) (Scotland) Act 2013.  The current 12 standards with accompanying practice
statements and core components are designed to align with the statutory guidance
to support the necessary system changes to assist with the implementation of the
SDS principles, improve practice and provide consistency for individuals in receipt of
care and support.  Through the completion of a self-evaluation as a benchmark for
embedding practice against the 12 standards, good practice can be embedded.
The re-establishment of the SDS Steering group will provide the necessary
governance and oversight, in embedding the SDS principles in line with the national
SDS Framework of Standards.
The Human Rights Bill
The Human Rights Bill for Scotland is currently in development but has faced some
delays. The Scottish Government has committed to introducing this legislation to
incorporate:
1. The International Covenant on Economic, Social and Cultural Rights
(ICESCR)
2. The Convention on the Elimination of All Forms of Discrimination against
Women (CEDAW)
3. The Convention on the Elimination of Racial Discrimination (CERD)
4. The Convention on the Rights of Persons with Disabilities (CRPD)
Page 160

Page 161

APPENDIX 1
15 
The bill remains in development and at the time of writing this report, has not yet
been formally introduced to Parliament
Asylum Seekers Health Needs Assessment
HSCM also participated in an exercise to understand the health needs of asylum
seekers across Grampian.
These recommendations arising from the needs assessment seek to ensure that
asylum seekers receive the right care, at the right time, in the right place. 
1. Information sharing 
A process of data sharing to understand the composition of the asylum seeker
population has been established. This process must be adapted to fit the changing
landscape of support for asylum seekers, including the withdrawal of the Aberdeen
City health care navigator team. We need to acknowledge that the recommendations
following this one will not succeed unless this data sharing is continued. 
2. Enabling access 
Both in terms of language and systems, asylum seekers need assistance and
support to navigate the health care system. This assistance would ideally take the
form of consistent team, allowing asylum seekers to build trusting relationships with
a single point of contact. The value of less tangible support (such as assistance with
transport and route planning) provided by those who assist with navigation cannot be
overestimated. Language support will require different parts of the health care
system to provide information to asylum seekers in an accessible format. There
needs to be recognition that an accessible format might require information to be
provided in a language other than English, and may need to be verbal or recorded to
avoid assumptions of literacy. 
3. Health improvement 
We need to recognise that asylum seekers are entitled to the same health care
provided to UK citizens living in Scotland. As such, there is an impetus to identify
and remove barriers to engagement in relevant screening programmes, and other
services that manage long-term conditions and risk factors, including dental and
mental health care. 
4. Protecting health 
In order to protect individual and population health, asylum seekers will need support
to engage with care that protects health, including screening for relevant
communicable diseases (TB, blood borne viruses) and vaccination to prevent
disease. We need to ensure we can demonstrate people in the asylum seeker
population have been given the opportunity to consent to care that protects health, or
that they have had the chance to make a truly informed choice and have refused to
consent to such care. This might rely on the utilisation of existing, or development of
Page 161

Page 162

APPENDIX 1
16 
new datasets and data collection procedures. Such datasets could be informed by a
retrospective analysis of the asylum seeker population to establish which asylum
seekers have already had TB screening, for example. Making this recommendation
operational will require objectives to be specific, measurable, achievable, relevant
and time-bound. 
5. Learning lessons 
The lessons learnt from working with the asylum seeker population may be
applicable to other vulnerable groups with complex needs across the health care
system. Learning could be disseminated across the system to improve the care
offered to these groups and prevent duplication of efforts to reach vulnerable people
with complex needs. 
APPENDIX 1 - TO BE ADDED IN FINAL REPORT