Community Planning Board 
Wednesday, 08 November 2023 
SUPPLEMENTARY AGENDA 
The undernoted reports have been added to the agenda for the meeting of the
Community Planning Board to be held at Council Chambers, Council Office,
High Street, Elgin, IV30 1BX on Wednesday, 08 November 2023 at 14:00. 
BUSINESS 
4a. UK Government Our Long Term Plan for Towns 3 - 10 
Any person attending the meeting who requires access assistance should
contact customer services on 01343 563217 in advance of the meeting. 
Page 1

Page 2

THE MORAY COUNCIL 
Community Planning Board 
SEDERUNT 
Mr Adam Coldwells  (Chair)
Councillor Kathleen Robertson  (Depute Chair)  
Mr George Burgess  (Member)
Mr Murray Ferguson  (Member)
Chief Superintendent Graeme Mackie  (Member)
Mr Grant Moir  (Member)
Mr David Reid  (Member)
Mr Anthony Standing  (Member)
Mrs Susan Webb  (Member)
Ms Caroline Webster  (Member)
Councillor John Divers  (Member)
Councillor Juli Harris  (Member)
Councillor Graham Leadbitter  (Member)
Councillor Bridget Mustard  (Member)
Mr Andrew Anderson  (Member)
Mr Roddy Burns  (Member)
Councillor Tracy Colyer  (Outside Body Appointee)
Councillor Amber Dunbar  (Outside Body Appointee)  
Clerk Name: Lindsey Robinson
Clerk Telephone: 07966 120593
Clerk Email: committee.services@moray.gov.uk 
Page 2

Page 3

REPORT TO: SPECIAL MORAY COUNCIL ON 25 OCTOBER 2023 
SUBJECT: UK GOVERNMENT “OUR LONG-TERM PLAN FOR TOWNS” 
BY:  DEPUTE CHIEF EXECUTIVE (ECONOMY, ENVIRONMENT AND
FINANCE) 
1. REASON FOR REPORT 
1.1 To inform the Council of the announcement on 1 October 2023 that Elgin is
one of 55 towns in the UK to receive £20 million funding towards town centre
regeneration projects from the UK Government and to agree that the Head of
Economic Growth and Development liaises with the UK and Scottish
Governments to progress governance arrangements to establish a Town
Board. 
1.2 This report is submitted to Committee in terms of Section III(A)(2) of the
Council’s Scheme of Administration relating to long-term financial plans. 
2. RECOMMENDATION 
2.1 The Council is asked to: 
(i) note the award of £20 million funding for Elgin from the UK
Government Long-Term Plan for Towns; 
(ii) agree that the Head of Economic Growth and Development liaises
with the other 6 Scottish towns local authorities which have been
awarded funding to share best practice; 
(iii) agree that the Head of Economic Growth and Development
establishes an initial informal group as per para 4.8 and suitable
interim governance structures; 
(iv) agree that the Head of Economic Growth and Development
proposes to the initial group that the Elgin City Centre Masterplan
and Delivery Programme are updated to inform the Long Term
Plan, and if this is supported, delegated authority is granted to
progress that work ahead of formal constitution of the Town
Board; and 
(v) agree a further report be prepared for Council when further details
on the staffing and financial implications surrounding the funding
are available. 
Item 4a.
Page 3

Page 4

3. BACKGROUND 
3.1 The Long –Term Plan for Towns was published on 1 October 2023 and seeks
to invest £1.1billion into 55 towns across the UK, of which 7 are within
Scotland, including Elgin. 
3.2 The Plan recognises that through the Government’s existing programmes and
lessons learned from other countries, the need for longer term funding
certainty, building local partnerships, having a clear plan for delivery, joint
working between central and local Government and involving people and
communities from the outset are key to success and have been embedded in
the Plan. 
3.3   The funding will be focused on the issues that matter most to local people,
including high streets, heritage and regeneration. The funding complements
several projects within the Moray Growth Deal which will invest in Elgin and
town centre regeneration funding secured from a number of external sources
as reported to Economic Development and Infrastructure Services Committee
on 5 September 2023 (paragraph 10 of the minute refers). 
4. PROPOSALS 
4.1 The Long Term Plan requires that each of the 55 towns will have a long term
plan drawn up by a new Towns Board, made up of local community leaders
and employers. Each town will have a £20 million endowment style fund to
invest over the next decade. 
4.2 To support this work, the UK Government will also be establishing a new
Towns Taskforce reporting directly to the Prime Minister, which will support
towns on their Long-Term Plans also making it easier to repurpose empty high
street shops by reforming licensing rules and supporting more housing in town
centres. 
4.3 Each town will be required to; 
• Develop a Long Term Plan to invest in and regenerate their town, based
on the priorities of local people and put to local people for consultation
• Receive £20 million in endowment style funding and support over ten
years to support the Town Plan, to be spent on issues that matter to local
people, including regenerating high streets and securing public safety. This
plan will be put to local people for comment.
• Establish a Town Board to bring together community leaders, employers,
local authorities and the local MP to oversee and deliver the Long-term
Plan. 
4.4 Once structures are in place, capacity funding will be made available from
Spring 2024 to develop Town Plans which should be produced no later than
Summer 2024. From summer 2024 the UK Government will provide the first
year of funding to support the interventions set out in the Long Term Plan
which will be subject to assessment by the Department for Levelling Up,
Housing and Communities 
Page 4

Page 5

4.5      Details of the endowment style fund need to be clarified, with the Plan stating
that Towns will receive funding and support of £20M (25% resource, £75%
capital) to provide a range of interventions across the investment themes and
will have ten years to deliver these, providing longer term certainty to deliver
significant improvements in their towns. The 25% “resource” needs is
presumed to be revenue but clarification is required on spending criteria. 
4.6 The Plan states that the UK Government will provide further guidance and
discuss next steps with each of the local authorities. The UK Government will
work with devolved administrations in Scotland and Wales to consider how
best this approach is applied in Scotland and Wales. 
4.7 The Town Boards are expected to comprise a group of local organisations,
including;
• Community partners, such as community groups, faith groups and local
charities, the neighbourhood forum, the local Council for Voluntary
Services
• Local businesses and social enterprises, such as the chair or board
members for the Business Improvement District, key local employers or
investors in the town
• Key cultural, arts, heritage and sporting organisations
• Public sector agencies such as representatives from schools or police
subject to local priorities
• The local MP/MSP (to be clarified) in Scottish towns, relevant local
authorities representatives such as local Councillors. 
4.8      The Plan encourages local authorities to start bringing partners together
which will form part of their Town Boards in advance of this, and to begin to
set out a vision, formulate investment priorities and engage with local
communities. 
4.9      The significant work and engagement already undertaken associated with the
Elgin City Centre Masterplan (ECCMP), Levelling Up Fund (LUF) round 2 bid
and Moray Growth Deal mean that many projects are well positioned to
progress to further engagement and delivery with advanced design work
completed. The current work to complete addressing formal and informal
feedback received on the unsuccessful LUF round 2 bid is transferable and
includes; 
• Establishing governance structures, including partnership agreements
• Baseline information requirements and monitoring and evaluation
framework
• Risk registers
• Revised project costs to reflect inflation
• Phasing plan
• Ensuring a strong, linked package of projects is retained
• Revised economic modelling 
4.10 However, given that the funding is secured, there is an opportunity to revisit
long list projects which weren’t included within the LUF round 2 bid and
consider for inclusion. 
Page 5

Page 6

4.11 Updating the ECCMP and preparing a complementary Delivery Plan is a
resource efficient way to progress, aligning with the work associated with
developing a place based approach in the next local development plan. This
will then provide the opportunity to consult on priority projects which support
the objectives of the Fund. 
5 NEXT STEPS 
5.1 The proposed next steps are; 
• Continue liaison with UK and Scottish Governments to inform governance
and understand funding implications.
• Liaise with the other 6 Scottish towns to share best practice.
• Establish an initial informal group.
• Report to Moray Economic Partnership and the Community Planning
Board on the proposed governance structures and representation on the
Town Board. It is suggested that council representatives for informal
discussions be those appointed to Moray Economic Partnership and the
Council Leader.
• Report to Council by March 2024 with proposed governance structures
and further details on financial and staffing implications.
• Establish Town Board and associated governance structures by April
2024. The Town Board to include representation from business and
community.
• If supported, update the ECCMP and develop a Delivery Plan by end July
2024.
• Recruitment of project management staff to support the Delivery Plan by
September 2024. 
6 SUMMARY OF IMPLICATIONS 
(a) Corporate Plan and 10 Year Plan (Local Outcomes Improvement
Plan (LOIP))
Town Centre regeneration is a key element of economic development
which is a priority in the Corporate Plan. The funding will support
employment, training and skills opportunities with regeneration of the
town centre supporting and enhancing the regional role of Elgin as a
place to live, work and invest. 
A Community Wealth Building Plan will be developed to support the
programme of projects seeking to maximise economic benefit. 
(b) Policy and Legal
The funding will support delivery of the statutory Moray Local
Development Plan 2020 and the ECCMP. 
Subsidy control advice has been taken through development of the LUF
bid and further advice will be required as the programme progresses. 
(c) Financial implications
The details of how the endowment fund will operate are not known at this
time with details awaited from the UK Government.
Page 6

Page 7

Project Management costs will be paid from the 25% revenue within the
£20 million allocation. Capacity funding will be released in April to help
progress the Town Centre Plan, the amount is not yet known. 
Projects are likely to result in increased maintenance costs as previously
reported and it is important that projects are designed from the outset to
minimise ongoing costs to the Council. 
Update of the ECCMP and Delivery Plan if supported will be progressed
within existing resources. 
(d) Risk Implications
There are a number of risks and opportunities including; 
• A risk that the benefits of the £20M are not fully realised or evaluated
officers have held workshops to establish Monitoring and Evaluation
and benefits realisation plans associated with the LUF projects and
these can be updated and adapted to support the Delivery Plan.
• A risk that projects are not shovel ready, however, as noted above,
strong partnerships and design work has been progressed for a
number of projects.
• A risk regarding inflation and construction costs, which has been and
will continue to be reflected in updated cost for projects including
high optimism bias levels.
• A risk that the public are not engaged in the project- this will be
managed through a strong and active Communications and
Engagement Plan. The local press have been very supportive and
active on town centre regeneration projects and a partnership
approach to communications and engagement will be key to keeping
everyone informed and engaged as projects progress. 
(e) Staffing Implications
Most of the work carried out to address LUF feedback has been carried
out in house by officers within Strategic Planning and Development,
Transportation and Consultancy with external expert economic
consultancy support. 
Officers within Strategic Planning and Development, Transportation and
Consultancy will continue to progress and deliver projects as part of their
duties in delivering the Moray Local Development Plan 2020, the
ECCMP, Active Travel Strategy, Elgin Transport Strategy, Surface Water
Management Plan.
Page 7

Page 8

It is proposed that in discussion with the initial advisory group, the
ECCMP is updated and a Delivery Plan prepared for engagement. This
will be done within existing staff resources as it aligns with the place
based approach required for the new local development plan which is
being prepared. Any aspirational plans outwith those previously
articulated through levelling up, growth deal  and ECCMP may require
additional staffing resource and would need to be funded through the
capacity funding within the grant. 
However, it is likely that there will be a requirement for the following
additional staffing resource for the delivery phase of the project, as well
as external legal support; 
• A dedicated programme/ project manager to co-ordinate the project to be
employed in house and a part time project officer, reporting to the Strategic
Planning and Development Manager
• A Project Manager (engineer) to lead on transportation projects, reporting
to the Senior Engineer (Transportation)
• Potentially additional part time staff in communications, finance,
procurement and audit which will need further clarification. 
(f) Property
Council property and the public realm within the town centre may be
eligible for support through this funding although clearly the focus of the
funding is much wider. 
(g) Equalities/Socio Economic Impact
The funding aims to support town centre regeneration and address
economic disadvantage and in doing so, provide safer, more inclusive
and accessible places. 
An Equalities/ Socio Economic Impact Assessment will be undertaken on
the updated Elgin City Centre Masterplan and Delivery Plan. 
(h) Climate Change and Biodiversity Impacts
The proposals support delivery of the ECCMP which include objectives
intended to reduce carbon, by re-using vacant and derelict premises,
promoting active travel, greening town centres and through new
initiatives including investigating a potential heat network. 
There is an opportunity to link funding from the Nature Restoration Fund
with delivery of town centre project in future years. 
(i) Consultations
The Depute Chief Executive (Economy, Environment and Finance), the
the Head of Economic Growth and Development, the Legal Services
Manager, the Head of Financial Services, the Democratic Services
Manager, the Principal Climate Change Officer, the Consultancy
Manager, the Senior Engineer (Transportation), the Senior
Communications Officer and the Equalities Officer have been consulted
and comments received have been incorporated into the report. 
Page 8

Page 9

5. CONCLUSION 
5.1 The UK Government has published “Our Long- Term Plan for Towns”
which includes Elgin as one of 55 towns in the UK to receive £20M
funding towards issues that matter most to local people, including high
streets, heritage and regeneration and public safety and security. 
5.2 The Plan requires the Council to set up a Town Board and prepare a
Town Plan to deliver the £20M. The ECCMP and work to develop the LUF
round 2 bid and address subsequent feedback would provide a strong
platform for progressing the governance arrangements required. 
5.3 This report proposes that officers liaise with the UK and Scottish
Governments over arrangements and begin to establish an initial
advisory group and governance arrangements, then update the ECCMP
and Delivery Programme. 
Author of Report: Gary Templeton, Strategic Planning and Development Manager