October 2024
Electricity Infrastructure
Consenting in Scotland
Proposals for reforming the consenting
processes in Scotland under the Electricity
Act 1989
Closing date: 29 November 2024
Appendix 2

Page 2

2
Foreword by Michael Shanks MP
Minister for Energy, UK Government 
Reforming the planning system is an imperative of the UK Government. It is essential that we
have a planning system which can deliver the critical infrastructure that communities need.
This includes the renewable electricity infrastructure required to accelerate towards clean
power by 2030, which will boost the economy, create new jobs, secure our energy future, and
remove barriers to cheaper, cleaner power. To achieve this, the entire UK needs an efficient
planning system that is clear to understand, considers all its stakeholders, and includes local
voices. Our focus in this consultation is on Scotland, where processing consent for an
application can take up to four years. Both the UK and Scottish governments agree this is too
long and that the electricity planning regime requires modernisation to meet the needs of
today’s society. 
The current system is inefficient and unpredictable, providing no certainty on how long consent
will take. For those desperate to bring new energy generating assets onto the grid, it presents
a barrier to attracting investment and delivering yet more clean energy to homes and
businesses. 
The reforms seek to consult communities at an early stage. This is not about making quick
decisions, but instead making considered decisions as efficiently as possible. The energy
transition is one that will be achieved by cooperation, not coercion, which is why I believe that
local communities should be consulted on applications early, influencing them from the outset. 
We are asking everyone to play their part, through building a system that requires applicants,
communities, local authorities, advisory bodies and the Scottish Government to have the right
conversations early. 
These reforms are also not about pushing through inappropriate developments. Our goal is to
process applications in a more efficient manner, ensuring they are accepted or declined based
on a more streamlined and effective system. 
Collaboration is key
We have worked closely with the Scottish Government to develop these reform proposals, and
this has been an exemplar of what can be achieved when two governments work together on
an issue of shared interest.  
Scotland’s renewable electricity industry currently supports more than 42,000 jobs and has an
economic output of over £10bn. We know there is far more potential to unlock with this diverse
and immensely skilled workforce. By removing the unnecessary delays in the planning system,
we can accelerate towards our 2030 ambition and deliver cheaper, cleaner and more secure
energy to thousands of communities and businesses. 
We look forward to hearing your views on these proposals and we hope that, with your input,
we can deliver a reformed process that benefits everyone.

Page 3

3
Foreword by Gillian Martin MSP 
Cabinet Secretary for Net Zero and Energy, Scottish
Government 
Planning and consenting systems across our land and sea are crucial enablers of Scotland's
net zero transition. These systems provide clarity and confidence to support development and
investment, while balancing the needs of communities, nature, and other users of our
environment. It is therefore essential that our systems are robust, timely, and proportionate to
be truly effective.
The energy consenting landscape in Scotland is a complex interplay of reserved and devolved
responsibilities. Applicants, communities, local authorities, advisory bodies, and government all
play vital roles in reaching optimal decisions.
However, as applications have grown more complex and increased in volume, processing
times have extended significantly. Coupled with the projected further increase in application
numbers, it is imperative that we take decisive action to address these challenges.
We welcome this consultation as an opportunity to seek reforms that can both make an
immediate impact, and future-proof our consenting systems, ensuring they remain fit for a
modern Scotland. We appreciate our counterparts in the UK Government for their engagement
and collaborative approach throughout this process.
It is important to acknowledge that there is no single, quick fix to this multifaceted issue. This
consultation outlines potential reforms spanning from the pre-application stage to statutory
appeals. These proposals require action, cooperation, and at times, compromise from all
stakeholders. Our aim is to strike the right balance and work towards a system that serves
everyone effectively.
We are committed to partnering with those at the forefront of the net zero transition. We
eagerly anticipate hearing the views of applicants, communities, local authorities, and advisory
bodies on the proposals outlined herein. Your input is crucial in shaping a planning and
consenting system that can meet Scotland's evolving needs and environmental commitments.

Page 4

4
Introduction
The UK and Scottish governments are committed to accelerating to net zero across the
economy. This will not only restore the UK’s position as a global leader on climate action, but
by boosting homegrown, renewable energy it will reduce our exposure to volatile fossil fuel
markets, protect bill payers, and strengthen our energy independence. Scotland, with its wealth
of renewable resources, will play a critical role in decarbonising the power system, and
accordingly the transition to clean power is expected to bring long-term benefits to Scotland in
terms of jobs and growth. 
The Scottish Government determines applications to construct or install electricity
infrastructure – both generating stations over 50MW (or over 1MW for offshore generating
stations between 0 and 12 nautical miles from shore) and network projects - under the
Electricity Act 1989. This is in alignment with the Scottish Government having responsibility for
land use and the planning system in Scotland. While Scottish Ministers are responsible for
taking decisions under the Electricity Act 1989, the UK Parliament has responsibility for the
legislative framework, as the powers to legislate for “generation, transmission, distribution and
supply of electricity” were reserved in the Scotland Act 1998. 
In England and Wales, ‘nationally significant’ energy infrastructure is consented under the
Planning Act 2008, which was brought in to streamline the consenting process and make it
fairer and more efficient for local communities and applicants. The Electricity Act 1989, as used
in Scotland, has not been modernised in the same way. It can take up to 4 years to consent
large-scale onshore electricity infrastructure projects. This is slow in comparison to consents
under the Planning Act 2008 in England and Wales, and for generating stations permitted
under the Town and Country Planning (Scotland) Act 1997. Delays are caused by inefficient
and outdated features of the Electricity Act 1989. This ultimately results in lengthy timescales
for determination of applications to install essential electricity infrastructure.  This is costly to
consumers, as ‘constraint payments’ to electricity generators, paid when there are insufficient
networks to transport the power produced, were £2bn1 in 2022 and could rise to £8bn per year
(£80 per household per year) across Great Britain in the late 2020s if delays to consenting and
building network infrastructure persist2.
The UK and Scottish governments believe that Scotland’s growing renewable electricity sector
requires a robust, timely and proportionate consenting process which meaningfully involves
communities and relevant planning authorities in decision-making. This is vital if we are to achieve
clean power by 2030 and reach net zero across the whole economy by 2050. The UK and Scottish
governments agree that modernising and removing inefficiencies within the Electricity Act 1989 is
the most pragmatic route to speeding up infrastructure deployment, whilst ensuring applications
of an acceptable standard. This would break down a major barrier to an efficient consenting
process and provide greater certainty of process and timescales for all parties. It is also agreed
that requirements for applicants to seek views from the public, communities and consultees at pre-
application stage should be introduced, to build a fairer consenting system and help applicants
develop better quality applications for consent. 
1 National Grid, 2022. ‘Monthly Balancing Services Summary (MBSS).’
2 Department for Energy Security and Net Zero, 2023. Community benefits for electricity transmission network
infrastructure: Government response.

Page 5

5
We have identified reforms to modernise the Electricity Act 1989 and remove inefficiencies, whilst
giving communities and statutory consultees meaningful opportunities to influence applications for
consents. These reforms do not make applications for electricity infrastructure consent more or
less likely to be granted. These decisions will continue to be taken by Scottish Ministers on a case-
by-case basis, in consideration of relevant policy frameworks and weighing the impacts, including
cumulative impacts, and the benefits of each development.
The reforms are largely aimed at modernising the consenting regime for onshore electricity
infrastructure, in recognition of the recommendations made by the Electricity Networks
Commissioner in his report to the previous government in August 20233. Building on this, we
believe that the review should extend beyond grid connections onshore, and also consider where
reforms could benefit processes for applications for offshore generating stations. In this
consultation, we have sought to specify where reform will impact consenting for relevant onshore
and offshore projects.  In cases consented under the Electricity Act 1989 where there are common
challenges onshore and offshore, we have proposed a shared solution; in other cases, the reform
proposals are focused onshore where we do not believe a common solution is required.
The proposals cover the entire journey of an application, beginning with pre-application
requirements, and continuing through to the process for challenging consenting decisions
made by Scottish Ministers. These are: 
• Pre-application requirements – in contrast to all other legislative planning regimes in
Great Britain, the Electricity Act 1989 stipulates no pre-application requirements, for
example the requirement to consult in advance of an application being made. This
allows applicants to submit applications for electricity infrastructure consent without
consulting communities or statutory consultees, although some may choose to do so.
Reform proposals include the introduction of requirements for pre-application
consultation, notification and publication of planned applications. Also proposed is the
ability for Scottish Ministers to recover the costs of any pre-application activities, and the
introduction of an ‘Acceptance Stage’ when Scottish Ministers can decline to accept
applications which have not fulfilled pre-application requirements. 
• Applications – statutory consultees including relevant planning authorities, Scottish
National Heritage (now known as NatureScot), the Scottish Environment Protection
Agency and Historic Environment Scotland provide important input to enable effective
scrutiny of applications. However, without timely delivery of each input, supported by the
right skills and capacity, the application timeline can become lengthy. The proposals
provide collaborative approaches to deliver a predictable application timeline facilitated
by the right skills and capacity to provide greater certainty for all parties. Further
measures to support the clarity and timeliness of the process include enabling updates
of the information requirements for applications, and constraints on the timing of
amendments for onshore applications.     
• Public inquiries – under existing arrangements, where a relevant planning authority
objects to an application within statutory timescales, and the objection is not withdrawn
or given effect through modification or conditions, the Scottish Ministers must hold a
public inquiry. This is a formal process, usually involving an examination by way of an
oral hearing and/or inquiry sessions which takes an average of 18 months. The reform 
3 Electricity Networks Commissioner, 2023. Accelerating electricity transmission network deployment: Electricity
Networks Commissioner’s recommendations - GOV.UK (www.gov.uk)

Page 6

6
package, particularly pre-application consultation, aims to reduce the number of
planning authority objections by bringing forward more complete and better formulated
applications, shaped at an earlier stage by input from relevant planning authorities, local
communities and other statutory consultees. Specific reform proposals focus on
retaining the opportunity for relevant planning authorities to object, and handling
objections through a tailored, reporter-led process. 
• Variations – there is no prescribed process to vary consents for network projects
granted under section 37 of the Electricity Act 1989. This causes uncertainty for
generators awaiting connections, is a procedural risk for developers and Ministers, and
has the potential to prevent significant network upgrades going ahead unless a new, full
application is submitted. Reform proposals seek to implement a prescribed process for
varying consents to network projects. There is a further proposal to give the Scottish
Government powers to revoke, suspend or vary consents under specific circumstances. 
• Necessary wayleaves – in contrast to the UK Government, the Scottish Government
cannot charge fees for processing applications for necessary wayleaves (statutory rights
that allow electricity licence holders to install and access their electricity lines and
associated infrastructure on land owned by others). Changes are required to enable the
Scottish Government to process an expected significantly increased volume of
applications in coming years. Reform proposals seek to allow the Scottish Government
to charge the network operator fees at the point of application submission. 
• Statutory appeals and judicial proceedings – in Scotland, there is inconsistency as to
whether consents granted to applications for electricity infrastructure can be challenged
by a judicial review or a statutory right of appeal, depending on whether the consent is
granted for an onshore or offshore project. The time limit for the challenge also varies
and may either be 3 months or 6 weeks. Reform proposals look to align the timescales
to 6 weeks and use a statutory right of appeal process for all onshore and offshore
consenting in Scotland. 
The UK and Scottish governments have worked together closely on the proposals in this
consultation, which sets out current thinking and seeks to gather views and evidence on the
reform proposals. The governments will continue to work together in acting on the consultation
outcome and resulting next steps. Responses to the consultation will inform the steps that
need to be taken next to address these challenges. The intention is for reforms to be
implemented mainly through amendments to the Electricity Act 1989, when Parliamentary time
allows.

Page 7

7
Contents
Foreword by Michael Shanks MP _______________________________________________ 2
Foreword by Gillian Martin MSP ________________________________________________ 3
Introduction ________________________________________________________________ 4
General information __________________________________________________________ 8
Why we are consulting ______________________________________________________ 8
Consultation details ________________________________________________________ 9
How to respond __________________________________________________________ 10
Quality assurance ________________________________________________________ 10
Glossary ________________________________________________________________ 11
The proposals _____________________________________________________________ 13
Pre-application requirements ________________________________________________ 13
Application procedures _____________________________________________________ 19
Application information requirements ________________________________________ 19
Application input from statutory consultees ___________________________________ 21
Amendments to applications ______________________________________________ 23
Public inquiries _________________________________________________________ 24
Variations _______________________________________________________________ 27
Variations of network projects _____________________________________________ 27
Variation of consents without an application __________________________________ 28
Fees for necessary wayleaves _______________________________________________ 30
Statutory appeals and judicial proceedings _____________________________________ 32
Transitional arrangements __________________________________________________ 34
The package of reforms ____________________________________________________ 35
Evidence and analysis _____________________________________________________ 36

Page 8

8 
General information
Why we are consulting
The UK Government believes that Scotland’s growing renewable electricity sector requires a
robust, timely and proportionate consenting process which meaningfully involves communities
and relevant planning authorities in decision-making. The Scottish Government grants consents
to electricity infrastructure – both generating stations over 50MW (1 MW for generating stations
0-12 nautical miles from shore) and network projects - under the Electricity Act 1989. The UK
and Scottish governments agree that modernising and removing inefficiencies within the
Electricity Act 1989, is the best route to speeding up infrastructure deployment, which is vital to
achieving clean power by 2030. It is also agreed that requirements for applicants to involve
communities and statutory consultees through pre-application and application processes should
be strengthened, to build a fairer consenting system and develop better quality applications for
consent. 
This consultation sets out a package of proposals for reform which span the consenting journey.
The purpose of the consultation is to test these proposals with a wide group of stakeholders
ranging from communities hosting infrastructure to applicants for consent. This will help us
understand the impacts proposals will have across stakeholder groups and be used to shape the
development of policy proposals.

Page 9

9 
Consultation details
Issued: 28 October 2024
Respond by: 29 November 2024
Enquiries to: 
Scottish Electricity Consenting Team 
Department for Energy Security and Net Zero
7th Floor
3-8 Whitehall Place
London
SW1A 2AW 
Email: scottishelectricityconsenting@energysecurity.gov.uk 
Consultation reference:  Electricity Infrastructure Consenting in Scotland   
Web link: https://energygovuk.citizenspace.com/energy-infrastructure-planning/electricity-
infrastructure-consenting-in-scotland 
Audiences: 
We are seeking views particularly from stakeholders in the Scottish electricity consenting
process including members of the public local to electricity infrastructure development,
statutory consultees in the consenting process, planning authorities and developers of network
projects and electricity generating stations. 
Territorial extent: Proposed changes are intended to apply to Scotland only.

Page 10

10 
How to respond
Respond online at: https://energygovuk.citizenspace.com/energy-infrastructure-
planning/electricity-infrastructure-consenting-in-scotland  
or
Email to: scottishelectricityconsenting@energysecurity.gov.uk
Write to:
Scottish Electricity Consenting Team 
Department for Energy Security and Net Zero
7th Floor
3-8 Whitehall Place
London
SW1A 2AW 
When responding, please state whether you are responding as an individual or representing
the views of an organisation.
Your response will be most useful if it is framed in direct response to the questions posed,
though further comments and evidence are also welcome.
Confidentiality and data protection: 
Information you provide in response to this consultation, including personal information, may
be disclosed in accordance with UK legislation (the Freedom of Information Act 2000, the Data
Protection Act 2018 and the Environmental Information Regulations 2004). 
If you want the information that you provide to be treated as confidential please tell us, but be
aware that we cannot guarantee confidentiality in all circumstances. An automatic
confidentiality disclaimer generated by your IT system will not be regarded by us as a
confidentiality request.
We will process your personal data in accordance with all applicable data protection laws. See
our privacy policy.
We will summarise all responses and publish this summary on GOV.UK. The summary will
include a list of names or organisations that responded, but not people’s personal names,
addresses or other contact details.
Quality assurance
This consultation has been carried out in accordance with the government’s consultation
principles. If you have any complaints about the way this consultation has been conducted,
please email: bru@energysecurity.gov.uk.

Page 11

11 
Glossary
Consent – permission for the construction, extension or operation of a generating station or
the installation and maintenance of overhead lines, pursuant to sections 36 and 37 of the
Electricity Act 1989. The consent may include conditions. In Scotland consents are granted by
Scottish Ministers. 
Consultation bodies – advisory bodies on EIA developments as defined under the Electricity
Works (EIA) (Scotland) Regulations 2017. These are the planning authority, Scottish Natural
Heritage (now known as NatureScot), the Scottish Environment Protection Agency (SEPA) and
Historic Environment Scotland. They must be consulted on an application for consent for an
EIA development under the Electricity Act 1989. 
Community council – a council established by a local authority under Part 4 of the Local
Government (Scotland) Act 1973. It is a voluntary organisation, run by local residents to act on
behalf of the area. 
Environmental Impact Assessment (EIA) – a tool used to assess the significant effects of a
project or development proposal on the environment. EIAs make sure that project decision
makers think about the likely effects on the environment at the earliest possible time and aim to
avoid, reduce or offset those effects. 
Necessary wayleaves – wayleaves are agreements that permit access to private land for the
placement or upkeep of utilities. When parties cannot agree to a voluntary wayleave through
negotiation or a landowner wants to revoke an existing wayleave, network operators may use a
statutory procedure under paragraph 6 of Schedule 4 of the Electricity Act 1989 to obtain a
‘Necessary Wayleave’. This is granted in Scotland by Scottish Ministers, giving the electricity
licence holder legal authority to install and maintain lines and equipment on private land.
Relevant planning authorities – planning authorities who cover the location that a consent is
located in, usually a local authority, but can also be a district planning authority. For large-scale
network projects there may be several relevant planning authorities.  
Section 36 – the provision of the Electricity Act 1989 which requires consent to be granted for
the construction, extension and operation of generating stations.
Section 36C – the provision of the Electricity Act 1989 which provides that Section 36 consent
relating to a generating station in Scotland may be varied by Scottish Ministers upon
application. 
Section 37 – the provision of the Electricity Act 1989 which requires consent to be granted for
the installation and the keeping installed of overhead lines. 
Statutory consultees – these bodies will be notified in relation to an application for consent
and will have an opportunity to make representations on the application to Scottish Ministers.
These bodies are relevant planning authority,4 and, if the application is for an EIA
development, the consultation bodies (see definition above). NatureScot must also be notified
if all or part of the land to which the application relates is a site of special scientific interest,5 
4 Paragraph 2(1) of Schedule 8 to the Electricity Act 1989. 
5 Regulation 6 of the Electricity (Applications for Consent) Regulations 1990 (reference to the Nature Conservancy
Council to be read as Scottish Natural Heritage/NatureScot).

Page 12

12 
and advice from SEPA must be obtained if a ‘controlled activity’ will be carried on in respect of
a generating station.6 
6 Section 36(5A) of the Electricity Act 1989; controlled activity has the meaning given in the Water Environment
(Controlled Activities) (Scotland) Regulations 2005, and advice in this context is on matters relating to the
protection of the water environment.

Page 13

13 
The proposals
Pre-application requirements 
Background 
There are no pre-application requirements to be met for applications for consent for onshore or
offshore electricity infrastructure under the Electricity Act 1989. 
This means that the Electricity Act 1989 is the only legislative planning regime in Great Britain
without pre-application requirements for large-scale projects. Consents under other planning
regimes require applicants to fulfil certain pre-application requirements, most critically
consultation. Pre-application requirements for applications for nationally significant
infrastructure projects in England and Wales under the Planning Act 2008, and in particular
consultation, are designed to lead to “applications which are better developed and better
understood by the public, and in which the important issues have been articulated and
considered as far as possible in advance of submission…this in turn will allow for shorter and
more efficient examinations.”7 
Currently the Scottish Government asks applicants to voluntarily engage in pre-application
consultation. For onshore projects this is set out in guidance produced by the Scottish
Government’s Energy Consents Unit8. For offshore projects, applicants are encouraged to
carry out pre-application discussions with key stakeholders. The Scottish Government does not
have powers to make these requests mandatory, and 43% of applications for consent for
onshore projects requiring EIAs have been submitted since 2007 with incomplete, insufficient,
or poor-quality information, and frequently without any pre-application consultation. The lack of
pre-application engagement with relevant planning authorities and communities local to
electricity infrastructure, may be linked to their high levels of dissatisfaction with applications
for consent, as evidenced by the fact that since 2007 relevant planning authorities have
objected to 30% of all major applications requiring EIA post-submission. 
The Scottish Government must accept and process all applications, including those with
incomplete information, which can result in a protracted process of gathering all the information
needed from applicants. This contrasts with applications submitted under the Planning Act
2008, which may be declined if they are submitted without adequate information or pre-
application consultation.   
Case for change 
Introduction of pre-application requirements has the capacity to transform the consenting
system under the Electricity Act 1989. While the increased responsibilities for applicants will
require pre-application steps that not all applicants are currently taking, it is expected that the
applications submitted will be more thorough and of a higher quality, meaning their journey
through the consenting process as a whole will be quicker. 
The introduction of a structured pre-application process has the potential to significantly reduce
the number of objections raised by relevant planning authorities, by ensuring sufficient 
7 Ministry of Housing Communities and Local Government, 2015. ‘Planning Act 2008: Guidance on the pre-
application process’
8 Energy Consents Unit, 2022. ‘Good Practice Guidance for Applications under Section 36 and 37 of the Electricity
Act 1989’

Page 14

14 
information is made available to the public, local communities, relevant planning authorities
and statutory consultees at an early stage, when feedback can be properly considered by
developers and influence final proposals before an application is made. 
The absence of pre-application requirements impacts the functionality, fairness and efficiency
of the consenting process, which has a particular effect on:   
• Communities and the public – the current absence of notification or consultation
provisions in the Electricity Act 1989 means the public and local communities might
remain unaware of proposed projects until an application is submitted, missing the
advantages of early engagement. Though communities and the public are consulted
during the application process, this is managed by the Scottish Government through
written submissions, without a chance for direct conversation with the applicants.
This may be less effective since making changes to applications at this juncture can
be complicated and time-consuming for applicants.   
• The Scottish Government – without pre-application consultations, applications can
have omissions that dialogue with the public, local communities, relevant planning
authorities and other statutory consultees could have identified beforehand.
Consequently, many applications are submitted lacking adequate information or with
insufficient environmental information or proposed mitigation. These applications
cannot be rejected by the Scottish Government, limiting their capacity to conduct an
efficient consenting procedure, as they invest substantial time and effort in soliciting
additional details from applicants and handling changes made after the initial
application is submitted or after consent is granted. 
• Applicants – whilst many applicants follow the Scottish Government’s pre-application
guidance and advice, the lack of legal compulsion to do so means there is a variable
approach from applicant to applicant, and this undermines public confidence and
does not provide standardisation. Applicants in the competitive renewables sector
can be less willing to commit sufficient time and resource to pre-application
processes. The resulting shortcoming in applications results in inefficient processing
which impacts their delivery certainty. 
• Relevant planning authorities – relevant planning authorities can play an important
role in the development of applications for onshore developments, through
representing local communities and providing tailored local guidance.  Absence of
pre-application notification and consultation can leave relevant planning authorities
either unaware of applications until they are submitted, or with insufficient
information to meaningfully comment at an early stage on the likely effect of
proposals. They are unable to offer the valuable early advice which can shape
project development in ways that are mutually beneficial to the project and location.   
Pre-application consultation would mean applicants must share information with the public and
engage with local communities, relevant planning authorities, other statutory consultees and
the Scottish Government before starting the application process, facilitating productive
discussions with these groups. Providing notification and preliminary information would give all
parties sufficient time to consider the proposed projects before entering the consultation
period. Early involvement of the local communities and statutory consultees - particularly
relevant planning authorities - in the development of a project, regarding matters from site
appropriateness to specific project design and mitigation, helps ensure that their input is
meaningful and considered before proposals are finalised and submitted, since changes
become more difficult afterward.

Page 15

15 
This is intended to produce better formulated applications which are more likely to find local
community and relevant planning authority support and attract fewer objections post-
submission. To ensure pre-application requirements are met, the Scottish Government would
also need the ability to reject applications which have not met requirements. In addition,
notifying the Scottish Government in advance of making an application would facilitate better
workforce planning. Conducting consultations means that later adjustments to applications will
be less likely, resulting in a quicker, more efficient consenting process. 
The Scottish Government anticipates that the introduction of pre-application requirements
would necessitate the provision of new services they would need to supply, in order to assist
prospective applicants to meet requirements. These would include but are not limited to
offering introductory meetings with applicants, convening of meetings between applicants and
public bodies with an interest in the application, and validation of pre-application information.
To offer these services the Scottish Government needs to be able to recover costs through the
charging of fees. 
Proposed changes
The introduction of pre-application requirements for applications for consent, and for
applications to vary certain existing consents. This would be achieved through implementing a
clear set of statutory requirements for applicants, through amendments to the Electricity Act
1989. 
The pre-application requirements are based on those in the Planning Act 2008 (sections 42-
49) and the Town and Country Planning (Scotland) Act 1997 (sections 34-35C). Pre-
application requirements would apply to all onshore applications for electricity generating
stations and for network projects that require an EIA. Some pre-application requirements would
apply to offshore applications – these are specified in the below proposals. 
The intended outcomes are: 
• To enable key information about a project to be shared with the public, relevant planning
authority, local communities, other statutory consultees and the Scottish Government to
give them an opportunity to have meaningful and influential dialogue with applicants at
an early stage of project development as part of the pre-application consultation
process. 
• To speed the consenting process by improving the quality of applications for consent for
electricity infrastructure and where possible resolving issues before submission. 
• To enable the Scottish Government to verify if applicants have met the requirements
and to reject applications which have failed to do so.     
• To enable the Scottish Government to recover the cost of carrying out any pre-
application activity.
The proposals for pre-application requirements are as follows: 
A duty to notify the Scottish Government 
• The applicant must notify the Scottish Government, and where appropriate the Marine
Licensing Authority, of the intention to undertake the duties set out below and provide a

Page 16

16 
list of proposed bodies to be consulted. This must include relevant statutory consultees
and any public body which the developer considers is likely to be interested in the
application. This would apply to onshore and offshore applications for consent.  
A duty to publicise
The applicant must publish: 
A public notice – containing a brief description of the proposed development for which
an application for consent or variation is proposed to be made and its location, details of
how and within what time period preliminary information may be inspected or obtained,
an explanation of how and by what date any person can comment on the information,
and a statement clarifying that these comments are not representations to the Scottish
Government and that there will be an opportunity to make these once the application is
submitted. This would apply to onshore and offshore applications for consent under the
Electricity Act 1989.  
The applicant must send to the Scottish Government and make available to the public, in
accordance with the notice: 
A Preliminary Information Report – a description of the project, containing all information
reasonably required for local communities and statutory consultees to develop an
informed view of the likely effects of the development. The information required will be a
concise description of the proposed project, a description of the land or place to which it
relates and a location and outline site plan, and brief details of any environmental
considerations made up until the point of publication/consultation.  The Scottish
Government may prescribe in more detail the preliminary information required. This
would apply to onshore and offshore applications for consent under the Electricity Act
1989.
A duty to consult: 
• The applicant should undertake a consultation which includes relevant planning
authorities (for onshore applications) within or adjoining the land where the application is
located, the marine licensing authority (for offshore projects), community councils as
agreed in any Statement of Community Consultation, and the list of proposed bodies
agreed with the Scottish Government following notification. This would apply to onshore
and offshore applications for consent under the Electricity Act 1989. 
• A Statement of Community Consultation - to be sent to the Scottish Government and
any relevant planning authority, together with the Preliminary Information Report, prior
to the proposed public and community council consultation. The statement should set
out how the public and community councils will be notified of and consulted on
preliminary information, how they will be able to submit views to the prospective
applicant on the information, and how these comments will be considered in formulating
the final application. This must provide details of at least two public consultation events
as well as a website, and an email and postal address for public comments to be
lodged. The Statement of Community Consultation and the Preliminary Information
Report must then be made available for public view. This would apply to onshore
consents under the Electricity Act 1989 only and sections of offshore consents under
the Electricity Act 1989 that are on land.

Page 17

17 
The relevant planning authority will have the opportunity to make comments to the
Scottish Government on the Statement of Community Consultation and the Preliminary
Information Report and Scottish Ministers will within 21 days notify the prospective
applicant of any changes required. 
• Community consultation - the applicant should hold two engagement events for
members of the public where they can examine preliminary information, engage with the
applicants and make comments on the proposals. It should be clear to the public at
these events how their views may be provided, how they will be considered by the
applicant, and how they will be reflected in any final application submitted to the Scottish
Government. This would apply to onshore consents under the Electricity Act 1989 only
and sections of offshore consents under the Electricity Act 1989 that are on land.   
• Additional requirements for network projects – due to the way in which complex
overhead line applications are planned, some of which cover many kilometres, we
would welcome views on whether a single consultation stage is appropriate or whether
some flexibility is needed in certain circumstances that may necessitate a multistage
consultation process with the public, local communities and statutory consultees.  This
is to ensure that key issues are picked up during the pre-application process, while at
the same time not imposing a disproportionate burden on developers. 
• A Pre-application Consultation Report - the applicant must submit this with the eventual
application under the Electricity Act. This report would set out how pre-application
consultation has been undertaken in accordance with the above requirements, how
views have been gathered and considered at each stage, and the prospective
applicant’s consideration of the views raised during the pre-application consultation
process, demonstrating regard to relevant responses. 
Acceptance stage
Directly after an application is submitted to the Scottish Government, the ‘Acceptance Stage’
would begin. This would precede the ‘Application Stage’ and is based on the ‘Acceptance of
Applications’ detailed in section 55 of the Planning Act 2008. During this stage: 
• The Scottish Government would analyse the Pre-Application Consultation Report and
decide if the pre-application consultation meets statutory requirements. If it does not
meet requirements, the Scottish Government can reject the application. 
• The relevant planning authority would be able to raise an objection to the Scottish
Government if it considers the pre-application consultation has been insufficient for
consultees to fully consider or make representations on the application. 
Pre-application fees
To facilitate the support of applicants in fulfilling pre-application requirements, the Scottish
Government proposes to charge fees to applicants. Supporting applicants might include
functions such as offering introductory meetings to applicants, convening meetings between
applicants and public bodies which have an interest in the development, and validation of pre-
application information. Fees would be based on the principle of full cost recovery, in

Page 18

18 
accordance with UK Government and Scottish Government policy for pre application
functions.9 
Consultation questions 
1. Do you agree with the proposal for pre-application requirements for onshore
applications? Why do you agree/not agree? How might it impact you and/or your
organisation?   
2. Do you agree with the proposal for pre-application requirements for offshore generating
stations? Why do you agree/not agree? How might it impact you and/or your
organisation? 
3. Do you agree that pre-application requirements should apply to all onshore applications
for electricity generating stations, and for network projects that require an EIA? Why do
you agree/not agree? How might it impact you and/or your organisation?   
4. Do you agree that a multistage consultation process may be appropriate for some
network projects? Why do you agree/not agree? How might it impact you and/or your
organisation?   
5. Do you agree with the proposal for an ‘Acceptance Stage’ for applications? How long do
you think an acceptance stage should be (in weeks)? Why do you agree/not agree?
How might it impact you and/or your organisation? 
6. Do you agree that the Scottish Government should be able to charge fees for pre-
application functions? Why do you agree/not agree? How might it impact you and/or
your organisation?   
7. Do you agree that our proposals for pre-application requirements will increase the
speed of the end-to-end project planning process overall? Why do you agree/not agree? 
9 Scottish Government, 2024. ‘Scottish Public Finance Manual’

Page 19

19 
Application procedures
Application information requirements
Background
To examine applications the Scottish Government requires the applicant to supply certain
information about the project. Currently, the application must describe the land or place to
which the application relates, through reference to a map.
For network projects, the application must also include: 
• the length of the proposed line 
• its nominal voltage 
• whether necessary wayleaves have been agreed with the owners and occupiers of the
land, proposed to be crossed by the line 
• any supplementary information requested by the Scottish Government 
The Scottish Government has guidance asking applicants to submit further information such as
a detailed map showing the land where the proposed development would be built or the
electric line(s) installed including detailed infrastructure, access routes etc and a planning
statement. The Scottish Government has powers to ask for additional information for
applications for consent for network projects, but not for generating stations. This means
supplying this information for applications for generating stations is not mandatory, with the
exception of additional information requested under EIA regulations. 
The Scottish Government would like to set out more detailed application requirements when
submitting an application and make their inclusion in submission of the application a condition
of the application being accepted.
Requirements would vary depending on the nature, scale and location of a proposal. 
Case for change 
According to the Scottish Government, nearly 43% of applications for onshore generating
stations needing EIAs have been submitted since 2007 with substandard or inadequate
information. This hampers the efficiency of the consenting process by consuming the Scottish
Government’s time and resources to gather additional details from applicants, resulting in
delays for the processing of these applications and all other applications. 
Proposed changes
To expand the information that applicants must supply in consent applications. This would be
established through amendments to the Electricity Act 1989 and would apply to all network and
generation applications made to the Scottish Government, for onshore and offshore
applications. The Scottish Government would not be obliged to process the application until the
required information is supplied.                              
The information requirements would be prescribed in more detail in regulations and would vary
depending on whether the development was onshore or offshore, whether it was EIA
development or not, and whether it was a generating station or an overhead line.

Page 20

20
The information requirements may include the following. This list is for illustration and is not
exhaustive. Applicants will not be required to submit information twice if it is required to meet
existing requirements (such as EIA requirements):
• A detailed plan showing the location of all infrastructure
• A statement setting out pre-application engagement with interested parties and how
their input has been reflected in the application
• A statement on the alternative approaches considered
• A statement of benefits and needs
• A statement of all components of the proposal requiring consent
The intended outcome is to ensure an efficient applications process by guaranteeing that the
Scottish Government is provided with all necessary information to commence processing of
applications. 
Consultation questions
1. Do you agree with the proposal for increased information requirements in
applications? Why do you agree/not agree? How might it impact you and/or your
organisation?
2. Do you agree with the proposal to set out detailed information requirements in
regulations? Why do you agree/not agree? How might it impact you and/or your
organisation?

Page 21

21 
Application input from statutory consultees
Background  
After an application for consent for electricity infrastructure is submitted to the Scottish
Government, the Scottish Government will, in most cases, run a consultation which invites
responses. This includes: (a) consulting the relevant planning authority (and, where relevant to
the particular application, NatureScot and/or SEPA); and (b) consulting the consultation bodies
set out in the Electricity Works (EIA) (Scotland) Regulations 2017 (‘EIA regulations’), section 2,
and any other public body which the Scottish Government considers is likely to be concerned
by the proposed development.
The Scottish Government must consider all representations made under the above processes
before determining an application. This input is important as it enables effective scrutiny of the
application. It allows the relevant planning authority to consider and raise the planning
implications of the application for its area and brings in specialist advice from expert bodies on
matters such as the effective management of protected sites. The statutory consultees
understandably wish to consider their input carefully. However, without timely delivery of each
input, the timeline for applications can become lengthy. This is a particular challenge for
onshore applications, and the proposal is to focus reform on onshore applications. 
Under the requirements of the Electricity Act 1989 and the Electricity (Applications for Consent)
Regulations 1990, the relevant planning authority must notify the Scottish Government of any
objection by it to the application within 4 months (in the case of a section 36 application) or
within 2 months (in the case of a section 37 application). The consultation bodies under the
EIA regulations will be invited to send representations to the Scottish Ministers, following
sharing of its EIA report by the developer. The consultation bodies are relevant planning
authorities, NatureScot, SEPA and Historic Environment Scotland. The Scottish Government
must have access to expertise to examine an EIA report, and expertise is in great part
provided by the consultation bodies in their consideration of environmental information and
subsequent responses. Lengthy response times significantly delay decision-making and create
uncertainty.   
Case for change 
The key components for a successful process are a predictable application timeline facilitated
by the right skills and capacity. All parties benefit from clear expectations on the timeline for
applications, which enable workflow planning for Scottish Government and the statutory
consultees and give applicants scope to create realistic project plans for all phases of work,
including activities after consenting decisions are made. The input from statutory consultees,
along with the Scottish Government’s preparation of a report to Scottish Ministers, are
important components of the timeline.
As the volume and complexity of applications increases, it is understood that statutory
consultees’ capacity to respond to consultation requests from the Scottish Government in a
timely way will rely on a level of skills and resources, which is not readily available.
Additionally, internal planning authority consultation and schemes of delegation, which require
decisions to be taken by planning committees on whether to object, require forward planning
and alignment of planning officer and internal department resource, and with committee
schedules.
Scottish Government’s recent ‘Investment in Planning’ consultation sought views from
stakeholders on proposals to ensure that the planning system is better equipped to deal with
current and future challenges. The ‘Verity House Agreement’ and the ‘New Deal for Business’

Page 22

22 
have set out how the Scottish Government intends to work collaboratively with local authorities
and others to deliver a just transition to net zero.
As a result, measures such as establishing Scotland’s first Planning Hub have already been
committed by Scottish Government to assist in addressing these issues. However, the Scottish
Government is keen to understand what further support mechanisms and practical measures
could be explored, within a collaborative framework between the Scottish Government and
statutory consultees, to reduce the time needed for the statutory consultees to provide
consultation responses.
The reform process launched by this consultation creates an opportunity to re-set the
expectations on the bodies providing essential support to the application process, taking
account of their views, suggestions and their specific circumstances.
Proposed changes
Alongside the recent commitments made by the Scottish Government to provide greater
support for statutory consultees, possible measures which could also be taken to provide
greater clarity for application timelines include:
1. Establishing a forum including the Energy Consents Unit and the statutory consultees to
consider the common reasons for and patterns of delay and work together on agreed solutions;
2. Developing a framework for delivering the application process for all statutory consultees,
agreed on a collaborative basis with the Energy Consents Unit; 
3. Providing additional specialist support to facilitate the statutory consultees’ ability to respond
to the Scottish Government’s consultations, to manage highly technical matters relating
specifically to electricity infrastructure; 
4. Enabling Scottish Government to set time limits for each stage of the application process,
including for the Scottish Government’s determination, and the contribution needed from each
of the bodies, with the scope for these time limits to be extended by Scottish Government for
the most complex applications.
Consultation questions
1. What are the reforms that would be most impactful in enabling your organisation to
provide timely input on section 36 and section 37 applications?
2. What are the advantages and drawbacks of the options set out under Proposed
Changes? How might your organisation benefit from the proposed forum and
framework?
3. What specialist or additional support could the Scottish Government’s Energy
Consents Unit provide to facilitate the statutory consultees’ ability to respond?
4. Would new time limits help your organisation to prioritise its resources to provide the
necessary input to the application process?

Page 23

23 
Amendments to applications
Background
An amendment refers to a modification requested by the applicant during the processing of an
application. Substantial changes that would alter the project significantly are not permitted,
necessitating the submission of a new application. Allowed amendments require a consultation
even if one has already been conducted for the original application. The Scottish Government
must review any amendments requested at any stage of the consenting process. 
Case for change
All stakeholders agree on the importance of being able to amend applications. However, the
Scottish Government wishes to restrict the point in the application timeline when amendments
can be requested. This is because making amendments at late stages of application
processing leads to significant duplication of the Scottish Government’s work, which depletes
resources and slows the entire consenting system. Limiting the time within which applicants
can apply for amendments would therefore enable better resource use and speed the entire
consenting system. This has been a particular issue for onshore applications.
Proposed changes
To restrict the point in the application timeline when an applicant can request an amendment.
The Scottish Government would set out a point in the application process at which no further
substantive amendment to an application may be made. The point at which no further
amendment may be made would be set on a case-by-case basis and communicated to the
applicant following submission of the application.
This proposal would apply to all network and generation applications made to the Scottish
Government for onshore projects and be achieved through amendments to the Electricity Act
1989. It would not apply to offshore projects. 
The outcome sought is not to discourage amendments, but to ensure they are submitted in a
timely manner, to avoid duplication and therefore depletion of the Scottish Government’s
resource. 
Consultation questions
1. Do you agree with implementing a limit for amendments to applications? Why do you
agree/not agree? How might it impact you/your organisation? 
2. Do you agree the limit should be determined by Scottish Ministers on a case-by-case
basis? Why do you agree/not agree? How might it impact you/your organisation?

Page 24

24 
Public inquiries
Background
Under the Electricity Act 1989, the relevant planning authority is consulted on applications for
network projects or generating stations. The relevant planning authority must respond to this
consultation within two months for network projects and four months for generating stations. If
during this time period the relevant planning authority objects to the application and the
application is not withdrawn, then Scottish Ministers must cause a public inquiry to be
held10.Typically, a reporter from the Scottish Government’s Planning and Environmental
Appeals Division is appointed to hold the public inquiry and to report back to Ministers with
recommendations on whether or not the application should be granted.
There are only limited provisions for the conduct of such public inquiries. Therefore, the
Scottish Government adopted a code of good practice11 for handling these public inquiries.
The procedure to be followed at inquiry is a matter for the discretion of the reporter, the
objective being to conduct proceedings in a fair, transparent and efficient manner. In each case
the reporter considers whether the issues raised in objections, representations or comments
from consultees can be dealt with on the basis of written submissions or a hearing, restricting
the topics to be addressed at an inquiry session to those that require cross-examination or
otherwise require to be dealt with by that form of procedure. This form of hybrid procedure will
be adopted if the reporter considers that this would be the most efficient way of conducting the
inquiry and where parties agree to this approach.
A public inquiry session is the most formal of the choice of procedures available. Each witness
must give its evidence in advance in the form of a precognition. Each witness is cross-
examined by the opposing party. Legal representation is not essential, but is common,
especially for applicants and statutory consultees. 
Public inquiries are very common, with 30% of all large-scale onshore applications requiring
EIA since 2007 going to public inquiry. The full public inquiry process, from appointment of the
reporter to the submission of the report to Scottish Ministers, currently takes an average of 18
months. This is a substantial addition to application timelines and creates significant
uncertainty for applicants.
In England and Wales, the Planning Act 2008 creates several opportunities for relevant
planning authorities to give their advice and views on applications for nationally significant
infrastructure projects, and ensures they are integral to the examination procedure. A separate
inquiry is not required if the relevant planning authority does not support the application, as the
intention of the Planning Act 2008 is to resolve all planning issues within a single process. The
Planning Act 2008 does however have an ‘Acceptance Stage’ when the relevant planning
authority may advise the consenting authority on whether the pre-application requirements
have been met. 
Case for change
The wider reform package, particularly pre-application procedures and the ‘Acceptance Stage’,
are intended to bring forward better formulated applications which have been shaped by and 
10 A public inquiry is not required where the Scottish Ministers propose to grant the application subject to
modifications or conditions that will give effect to the relevant planning authority’s objection.
11 Scottish Government, Planning and Environmental Appeals Division. ‘Code of Practice for Handling Inquiries
under Section 62 and Schedule 8 to the Electricity Act 1989.’

Page 25

25 
will have a better chance of enjoying the support of relevant planning authorities and
communities, meaning there should be less cause for the triggering of public inquiries. 
However, the UK and Scottish governments consider it important that relevant planning
authorities and communities continue to have statutory opportunities to challenge and
influence applications made under section 36 and section 37 of the Electricity Act 1989, and
that their views on those applications are engaged with and acted on constructively and
efficiently.
The use of the term ‘public inquiry’ implies the adoption of the formal public inquiry sessions as
described above. However, there are alternate methods of examination, such as written
submissions or hearings guided by a reporter, which can be just as effective in informing the
report to Ministers. Moreover, anecdotal evidence, for example feedback to the Planning &
Environmental Appeals Division of the Scottish Government from some of its stakeholders,
suggests that members of the public and community representatives can sometimes feel that a
formal public inquiry session is intimidating, complex, time-consuming and (if, for example,
they feel the need for legal representation) costly. These same potential drawbacks can also
apply to applicants and statutory consultees, particularly the relevant planning authority. 
The UK and Scottish governments still consider that inquiry sessions can be a useful tool. This
is most likely to be the case where there is a dispute on complex or technical matters, where
essential facts are in dispute, or where there is a conflict of professional opinion or evidence
and, in these cases, where the reporter would find it helpful for the evidence to be tested by
cross examination. However, their view is that the legislation should more explicitly allow the
reporter to make an informed decision about the procedures to be adopted on a case-by-case
basis. 
Proposed changes 
The following proposal would apply to all onshore applications for consent but not offshore
applications. 
Relevant planning authorities will be encouraged to engage fully with the pre-application
consultation outlined in the Pre-application requirements chapter, and to advise against
acceptance during the ‘Acceptance Stage’ if they consider that applicants have not fulfilled
their requirements around consultation. The intended outcome is to surface any matters for
discussion before applications are accepted.   
It is proposed that the Electricity Act 1989 be amended so that, where the relevant planning
authority submits an objection to an application within the prescribed period, which is not
withdrawn, the Scottish Ministers must appoint a person to make an examination into that
application and to report to them on the result of that examination. The legislation would
provide that the procedures to be adopted for that examination would be at the discretion of the
appointed person. That person may decide that the evidence available to them at the time of
appointment is sufficient, and that no further procedures are required. If that person determines
that further procedures are required, they may specify a site inspection, further written
submissions, hearing sessions, public inquiry sessions, or a combination of these. This
proposed process is based on the procedures followed under the Town and Country Planning
(Scotland) Act 1997 and which is provided for in the Town and Country Planning (Appeals)
(Scotland) Regulations 2013.
Although the choice of procedures would remain a matter for the reporter to determine, the
views of the applicant, the relevant planning authority and other interested parties may assist
the reporter in deciding what procedures would be appropriate. Therefore, it is proposed that

Page 26

26 
the legislation would provide for interested parties to express a view on what further
procedures, if any, they consider to be necessary. The reporter would take these into account
but would not be bound by them. The reporter would have the option of holding a pre-
examination meeting to discuss the procedures which may be adopted to inform the reporter’s
final decision in respect of these. This decision will be communicated to the interested parties.
The reporter will also communicate a target timescale for any procedure(s) selected up to the
final report. Following the reporter’s examination, whether or not this involves any further
procedure, they would then submit their report of that examination to the Scottish Ministers.
Where the relevant planning authority does object, the intention is to examine applications in
an efficient, proportionate and constructive manner, with the approach tailored to the case
being considered. The intention is that applications will continue to be subject to an appropriate
level of scrutiny, but without unnecessarily adversarial or protracted processes.  
Consultation questions
1. What is you or your organisation’s experience of public inquiries? What are the
advantages? What are the disadvantages? 
2. Do you agree with the proposed ‘examination’ process suggested? Why do you
agree/not agree? How might it impact you/your organisation?

Page 27

27 
Variations
Variations of network projects  
Background
A variation is a change to a consent that may be requested by the consent holder after consent
is granted. It must not fundamentally change the terms of the original consent, as this requires
a completely new application. Variations are a common occurrence in consenting for large-
scale infrastructure, as they are long-term projects during which conditions and technology
often change. 
Under the Electricity Act 1989, the Scottish Government is authorised to approve changes to
generation projects but lacks a clear prescribed process to do so for network projects. This
reflects the era in which the legislation was written, when large-scale network projects
necessitating variations were much less common. Due to the lack of a prescribed process and
the uncertainty this causes, the Scottish Government prefers not to process variations for
network projects. 
Case for change
In 2023, the duration for consenting network projects in Scotland was an average of 28 months
for projects where an EIA was required. Since the Scottish Government does not process
variations to existing consents, applicants needing changes face a choice between starting a
new application process, which substantially lengthens their project timeframe, or continuing
with less-than-ideal designs that affect their delivery capability. 
Such restrictions hinder the Scottish Government's capacity to maintain an effective consenting
system, as resources must be diverted to re-processing applications instead of being efficiently
managed through variation approvals.  
Proposed changes
To give the Scottish Government a clear statutory process under which variations to network
projects may be granted. This would be achieved by mirroring existing variation provisions for
generating station consents (in s36C of the Electricity Act 1989) and giving the Scottish
Government the power to prescribe a process for varying network projects in regulations. 
The intended outcome is to increase the efficiency of consenting for both applicants and the
Scottish Government. 
Consultation questions
1. Do you agree with the proposal to prescribe a clear statutory process under which
variations to network projects may be granted? Why do you agree/not agree? How
might it impact you/your organisation?

Page 28

28 
Variation of consents without an application 
Background
Given the extended duration of infrastructure projects, sometimes conditions evolve which
might include environmental factors or new scientific insights. Additionally, over time certain
consent conditions may become obsolete or an unnecessary barrier to development. There are
also situations where errors have been made in the consents that may require correction. In
these circumstances it is useful for the Scottish Government to be able to alter consents,
without the need for applicants to submit variation requests.
The Scottish Government currently has this power for consents granted outside the Electricity
Act 1989 framework, under section 30 of the Marine (Scotland) Act 2010, section 72 of the
Marine and Coastal Access Act 2009 and section 68 of the Town and Country Planning
(Scotland) Act 1997. 
Case for change
As consents are in place for the operational life of a generating station or network project,
variations may be required to ensure they do not become outdated and the infrastructure can
adapt to future changes. This may include adaptation to environmental changes or to changes
in knowledge or technology. 
Currently, due to the inability to modify, suspend or revoke consents when errors in consents
are found, an applicant must apply for a section 36 consent variation and go through the full
variation process, including payment of a fee. Examples include minor editorial errors by the
regulator, or minor project description errors or omissions by an applicant. Where the error
does not relate to a material matter, the Scottish Government wishes to expedite a correction
without the need for full process and payment of a full fee.
While the Scottish Government may currently vary a section 37 consent after it is granted, this
is not possible within the time period set out in the consent, and therefore within that period
variations – for example to correct errors – cannot be made. It is therefore proposed that the
changes set out below should apply to both section 36 and section 37 consents.
Enabling the Scottish Government to modify, suspend or revoke consents would ensure
delivery of electricity infrastructure that is sustainable over the long-term
This would be similar to the circumstances under which variations are made in other regimes
as mentioned above, for example to the conditions in section 30 of the Marine (Scotland) Act
2010 and section 72 of the Marine and Coastal Access Act 2009.
Proposed changes
To give the Scottish Government the ability to modify, suspend or revoke consents for network
projects or generating stations both onshore and offshore under the Electricity Act 1989
without an application, where: 
• There has been a change in environmental circumstances or relevant technological
changes 
• It is necessary to correct errors in consents 
The consent holder would have the opportunity to make representations on the proposed
variation, suspension or revocation and the Scottish Government would take any

Page 29

29 
representations from the consent holder into account before making a final decision. The
proposed changes would be achieved through amendments to the Electricity Act 1989. 
Consultation questions
1. Do you agree with the proposal to give the Scottish Government the ability to
vary, suspend or revoke consents, without an application having been made in
the circumstances set out above? Why do you agree/not agree? How might it
impact you or your organisation?   
2. Do you believe there should be any other reasons the Scottish Government
should be able to vary, suspend or revoke consents? What reasons are these?

Page 30

30 
Fees for necessary wayleaves
Background
Operators of electricity networks do not typically own the land network infrastructure is built on.
They therefore often need to enter private land to set up, service, or upgrade network
infrastructure. This necessitates an appropriate arrangement with the landowner, including
appropriate compensation. Wayleaves are agreements that permit access to private land for
the placement or upkeep of utilities. Generally, these permissions are pursued through
voluntary negotiations between network operators and the landowners or their representatives.
When parties cannot agree through negotiation or a landowner wants to revoke an existing
wayleave, network operators may use a statutory procedure under paragraph 6 of Schedule 4
of the Electricity Act 1989 to obtain a ‘Necessary Wayleave’. This grants the electricity license
holders legal authority to install and maintain lines and equipment on private land, with rights
including access for upkeep and equipment management. In Scotland, the Scottish
Government can approve these applications, often spanning a 40-year term. Compensation for
the landowner is agreed separately. The Scottish Government's Energy Consents Unit and the
Planning and Environmental Appeals Division are responsible for processing applications for
necessary wayleaves.
Case for change
With Scotland’s network infrastructure poised for expansion to achieve net zero targets and to
connect existing generation projects to the national grid, the next few years will likely see a
surge in necessary wayleave applications to the Scottish Government.  
The Scottish Government does not currently charge a fee for processing necessary wayleaves
applications or have the power to do so. This is atypical - in England and Wales an application
fee of £236.50, plus a day rate of £1000 in England and £742 in Wales for travel and
subsistence costs for the inspector’s work on the application, are charged for necessary
wayleave applications.12 The Scottish Government also charges fees to process applications
for electricity infrastructure consents.13
The number of necessary wayleaves applications is expected to significantly increase in the
next few years. In recent years the Scottish Government has received around 40 applications
for necessary wayleaves each year. However, Transmission Operators advise that over 1000
such applications could be made in 2025 alone. This kind of rise in application numbers is
likely to result in increasing financial and staffing pressures, which will create additional
burdens on already constrained services. If staffing cannot be increased to deal with this influx,
timescales for processing applications will increase, delaying the building of network projects.
Charging fees would be used to directly resource the processing of this service. This would
bring it into line with standard UK Government and Scottish Government policy, that where
public sector organisations charge for services, the charges normally pass on the full cost of
providing those services.14 
12 The Electricity (Necessary Wayleaves and Felling and Lopping of Trees) (Charges) (England and Wales)
Regulations 2013. The Electricity (Necessary Wayleaves and Felling and Lopping of Trees) (Charges) (England
and Wales) (Amendment) Regulations 2017.
13 The Electricity (Applications for Consent and Variation of Consent) (Fees) (Scotland) Regulations 2019.
14 UK Government, 2023. ‘Managing Public Money’. Scottish Government, 2024. ‘Scottish Public Finance Manual’

Page 31

31 
Proposed changes
To introduce a fee for necessary wayleave applications in Scotland. The proposed fee would
be paid by the network operator at the point of application submission. The fee would be based
on the average cost to process a necessary wayleaves application, including administration
and reporters’ (equivalent to an inspector in England and Wales) costs. 
The intention behind this change would be to recoup the full cost of processing applications to
better resource the system and maintain a fast and high-quality service.
Consultation questions 
1. Do you agree with the principle of introducing a fee for the Scottish Government to
process necessary wayleaves applications? Why do you agree/not agree? How might it
impact you or your organisation?   
2. Do you agree that the fee amount should be based on the principle of full cost
recovery, in accordance with Managing Public Money and the Scottish Public Finance
Manual? Why do you agree/not agree?15 How might it impact you or your organisation? 
15 As above

Page 32

32 
Statutory appeals and judicial proceedings 
Background
Scottish Ministers’ decisions on consenting applications for electricity infrastructure, can be
challenged by an ‘aggrieved person’. The process by which consenting decisions under the
Electricity Act 1989 in Scotland are challenged is not uniform; it may involve either a judicial
review or a statutory appeal. 
Consenting decisions for offshore electricity infrastructure in “relevant waters”16 can be
challenged through a statutory appeal. This must be initiated within 6 weeks of the consent
being granted. It is made by application to the Inner House of the Court of Session and can be
made on the grounds set out in section 36D of the Electricity Act 1989. 
Consenting decisions for onshore electricity infrastructure in Scotland can be challenged via
judicial review. This must be initiated within 3 months of consent being granted under the
general judicial review procedure set out in section 27A of the Court of Session Act 1988. It is
made by application to the Outer House of the Court of Session, and outcomes can be
appealed in the Inner House of the Court of Session. 
Section 36 and 37 consents in England and Wales may be challenged via judicial review
however this rarely occurs as large-scale electricity infrastructure is consented to under the
Planning Act 2008. Under the Planning Act 2008 decisions may be challenged by judicial
review, which must be initiated within 6 weeks. 
Case for change
Creating a unified system would make it simpler for individuals to launch challenges which
could help to reduce overall timescales. Where a challenge is brought, any work on the
electricity infrastructure tends to be paused until the outcome of the challenge is known which
creates development and investment delays. With criteria for bringing a challenge set out in
legislation this makes the grounds for challenge clear. A shorter period for bringing a challenge
would reduce the time of uncertainty that a challenge will be brought, and the consequences
for a project being paused or commenced at risk. 
Available data shows that, where challenges were brought against section 36 consents for
onshore wind in Scotland using the Judicial Review process, the majority were lodged after 90
days. The current 3-month time limit for initiating a challenge delays the development of
infrastructure. A 6-week timescale and statutory appeal is allowed for challenging planning
appeal decisions in the Inner House of the Court of Session in Scotland under Section 239 of
the Town and Country Planning (Scotland) Act 1997. There have been 30 such challenges
since 2020 and all have been lodged within 6 weeks. 
A 6-week period for challenging consenting decisions under the Electricity Act 1989 in
Scotland would allow for sufficient time to initiate a challenge and would not disproportionately
delay infrastructure development. Additionally, by taking challenges directly to the Inner House
of the Court of Session, decisions on outcomes would be final except for those appealed
through the UK Supreme Court. 
16 Section 36D(6) Electricity Act 1989, defined as waters in or adjacent to Great Britain which are between the
mean low water mark and the seaward limits of the territorial sea; and waters in the area designated by the
Renewable Energy Zone (Designation of Area) (Scottish Ministers) Order 2005 as the area in which the Scottish
Ministers are to have functions.

Page 33

33 
Proposed changes
To create a unified and more efficient system for challenging consents made under the
Electricity Act 1989 in Scotland. This would be achieved by making the statutory right of appeal
the legal mechanism for challenges to be brought in Scotland for onshore consenting. This
would simplify the process by aligning onshore consents with offshore consents under the
Electricity Act 1989. This could be achieved through legislation by extending section 36D of the
Electricity Act 1989 to apply to all onshore consenting decisions in Scotland made under
sections 36, 36C and 37. This would require consequential amendments to the Town and
Country Planning (Scotland) Act 1997 so that deemed planning permission under sections
57(2) and (2ZA) Town and Country Planning (Scotland) Act 1997, would be subject to the
same appeal process. 
Consultation questions
1. Do you agree that a statutory appeal rather than a judicial review process should be
used for challenging the onshore electricity consenting decisions of Scottish Ministers?
Why do you agree/not agree? How might it impact you or your organisation?   
2. Do you agree there should be a time limit of 6 weeks for initiating a challenge to a
consenting decision of Scottish Ministers for onshore electricity infrastructure? Why do
you agree/not agree? How might it impact you or your organisation?

Page 34

34 
Transitional arrangements
Once any changes to the Electricity Act 1989 are implemented through legislation, applications
for electricity consent will need to be consented under the new system. 
Proposed changes
All applications submitted to the Scottish Government after the new provisions come into force
and applications already being processed by the Scottish Government will be consented to
under the new system. This would apply from the stage in the consenting process that the
application has already reached and would not be retrospective. For example, applications
which have been submitted before the new system comes into effect would not be required to
fulfil pre-application requirements but would be subject to limits on requesting amendments. 
Consultation questions 
1. Do you agree with the above proposal for transitional arrangements? Why do you
agree/not agree? What impact would this have on you/your organisation?

Page 35

35 
The package of reforms 
Consultation questions 
1. Having read the consultation, do you agree with the reforms as a package? Why do
you agree/not agree? What impact would they have on you/your organisation? 
2. What steps could we take to ensure the project planning process (including the pre-
application stage) can be completed as fast as possible?

Page 36

36 
Evidence and analysis
An options assessment has been developed and published alongside the consultation. The
options assessment outlines the rationale for intervention and identifies the monetised and
non-monetised impacts. For more detail and the assumptions used in the analysis, please refer
to the options assessment. The following questions seek to gather additional evidence to
inform future analysis and should be considered in reference to the options assessment. 
Consultation questions
1) Do you agree with the rationale for intervention? Are there any points we have missed?  
2) Familiarisation:
a) How long do you think it would take your business to familiarise with the changes to the
legislation and how much of an impact on your pre-development costs do you expect
this to have (either a saving or an increased cost)?
b) How many people in your business need to review the legislation?
3) Impact: 
a) Do you agree with the impacts that have been identified? 
i) If not, please explain why with supporting evidence.  
ii) If you think there are other impacts that have not been identified, please set out the
additional impacts with supporting evidence.   
b) Can you provide further data and evidence to: 
i) Support a detailed assessment of each of the impacts?  
ii) Establish whether this policy is likely to reduce delays to transmission network build,
renewables or storage projects, and if so how long by?  
iii) Establish whether there are any groups you expect would be uniquely impacted by
these proposals, such as small and micro businesses or people with protected
characteristics? If yes, which groups do you expect would be uniquely impacted?
Please provide supporting evidence.

Page 37

37 
This consultation is available from: https://www.gov.uk/government/consultations/electricity-
infrastructure-consenting-in-scotland  
If you need a version of this document in a more accessible format, please email
alt.formats@energysecurity.gov.uk. Please tell us what format you need. It will help us if you
say what assistive technology you use.