Democracy Spraffa

Tarbert and Lochgilphead Regeneration Fund - Projects Update

Argyll and Bute Council · 7 June 2023
Back to Mid Argyll, Kintyre & the Islands Area Committee — 7 June 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  MID ARGYLL, KINTYRE AND THE      
ISLANDS AREA COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
7 JUNE 2023 
TARBERT AND LOCHGILPHEAD REGENERATION FUND – PROJECTS UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the 6 projects which Mid Argyll, Kintyre and
the Islands Area Committee agreed on 6 September 2017 focusing on those
projects which have not previously been reported to committee as complete.  
1.2 The Ardrishaig North Public Realm project completed on schedule and details of
the works are shown in Appendices 1 and 2. The works included changes to
the south car park as a result of recommendations of the pre-construction road
safety audit. Following concerns raised, a post-completion road safety audit is to
be undertaken. 
1.3 The only outstanding project is the Gleaner phase 2 site in Ardrishaig.
Discussions are ongoing in relation to this site. 
RECOMMENDATIONS 
Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to: 
1. Note the progress made with the projects as detailed within the report

Page 2

ARGYLL AND BUTE COUNCIL  MID ARGYLL, KINTYRE AND THE      
ISLANDS AREA COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
7 JUNE 2023 
TARBERT AND LOCHGILPHEAD REGENERATION FUND – PROJECTS UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update on the 6 projects which Mid Argyll, Kintyre and
the Islands Area Committee agreed on 6 September 2017 (ratified by Policy and
Resources Committee) should form the Tarbert and Lochgilphead Regeneration
Fund and proceed to full business case. The projects include:  
Project
Ref.
Project  Status
T02 Barmore Road (A83)/Garvel Road junction
improvement
Complete
T11 Tarbert Harbour facilities Complete
LA10 Lochgilphead Front Green Complete
LA11 Argyll Street Complete
LA13 Ardrishaig North Public Realm Improvements Complete
LA17  Gleaner Oil Site  Phase 1
complete, phase 2
ongoing 
The report below provides an update on the recently completed and remaining
ongoing projects. 
3.0 RECOMMENDATIONS 
3.1 Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to: 
1. Note the progress made with the projects as detailed within the report. 
4.0 DETAIL 
Ardrishaig North Public Realm (LA13) 
4.1 As advised in our previous report, works were commenced by P1 Solutions Ltd
on 29 August 2022 and they were certified as completed on 24 April 2023. The
works completed are shown on the drawing at Appendix 1 and include:

Page 3

 A new lochside viewing area with additional seating and art work;
 Alterations to the north car park including an expansion of disabled parking;
 New artwork on the canal embankment;
 Reconfiguring of the memorial garden to include new seating areas, picnic
benches and a path;
 Improved accessibility for the Argyll Sea Kayak Trail making it easier for
kayakers to go between Loch Fyne and the Crinan Canal; 
A series of before and after photos are included at Appendix 2. 
4.2 The works included changes to the circulation of the south car park, this was
recommended during the pre-construction road safety audit to ensure that, when
in use the relocated bus layby didn’t obscure visibility to the north. Following
concerns raised since works have been completed a post-construction road
safety audit has now been instructed. 
Ardrishaig Gleaner Site (LA17) 
4.3 This project is being delivered by Scottish Canals with a grant being provided
through the Tarbert and Lochgilphead Regeneration Fund. Phase 1 of the
Gleaner Site, the Egg Shed, was completed in 2019. 
4.4 Discussions are ongoing between the Head of Development and Economic
Growth, senior members of Scottish Canals and a private investor as to a potential
development in relation to Phase 2 of the site. It is anticipated that further clarity
on whether this proposal is progressing will be known over the summer/autumn
time. 
5.0 CONCLUSION 
5.1 With the exception of the grant for the phase 2 of the Gleaner site all projects
shortlisted for funding through the Tarbert and Lochgilphead Regeneration Fund,
including all projects to be delivered by the Council, have been successfully
completed. We are in the process of finalising costs for the completed projects
and following this expect to be able to report upon the financial aspects of the
project as well as the outputs delivered. Should any underspend remain once the
agreed six projects have been completed this will be reported to Committee so
that arrangements can be agreed as to how this should be allocated. 
6.0 IMPLICATIONS 
6.1 Policy 
The projects will support the overarching objective and long term
outcomes of the Council’s Corporate Plan, Argyll and Bute Outcome
Improvement Plan, the Local Development Plan, the Economic Strategy.
It will deliver the Tarbert and Lochgilphead Regeneration Fund. 
6.2 Financial

Page 4

A total of £3 million is allocated through the Tarbert and Lochgilphead
Regeneration Fund, external funding has also been secured.
Expenditure at April 2023 is £3,131,461.27. 
6.3  Legal 
Working with procurement colleagues in regard to management of
contracts and tendering process. Leases, licences and memorandums of
understanding with third party progressed by the legal team where
necessary. 
6.4  HR 
Support required from colleagues across the Council particularly Roads
and Infrastructure Services who are the asset owners for the Lochgilphead
Front Green and Ardrishaig North. 
6.5  Fairer Scotland Duty: 
6.5.1 Equalities - protected characteristics   
Equalities and Socio Economic Impact Assessments have been carried
out. 
6.5.2 Socio-economic Duty  
See above 
6.5.3 Islands 
No impacts anticipated. 
6.6. Climate Change 
Construction works undertaken as a result of the Tarbert Lochgilphead
Regeneration Fund will result in carbon emissions although it is
anticipated that these will be restricted to the construction period. Works
at Lochgilphead Front Green raise the ground level of part of the green
and may offer a form of climate change adaptation. 
6.7 Risk  
As projects are completed the number of risks is reducing however for the
remaining ongoing project these include those associated with external
funding, public perception, etc. Project Risk Registers have been
maintained. 
6.8  Customer Service   
None at this time 
Kirsty Flanagan – Executive Director with responsibility for Development and  
Economic Growth 
Policy lead – Robin Currie

Page 5

29 May 2023 
Appendix 1 – Ardrishaig North Public Realm Landscape Plan
Appendix 2 – Ardrishaig North Public Realm Photographs 
For further information contact: 
Anna Watkiss, Senior Development Officer, Development and Economic Growth, Tel.
01546 604344

Page 6

Appendix 1 – Ardrishaig North Public Realm Landscape Plan

Page 7

APPENDIX 2 – Ardrishaig North Public Realm Photographs 
Before After

Page 8

Before After

Page 9

Before After