ARGYLL AND BUTE COUNCIL  MID ARGYLL, KINTYRE AND
ISLANDS AREA COMMITTEE
ROAD AND INFRASTRUCTURE   6 SEPTEMBER 2023
SERVICES
PLAY PARK ENGAGEMENT – UPDATE REPORT
1.0 EXECUTIVE SUMMARY
1.1 In August 2022, the Scottish Government confirmed a full 5 year funding package
to all Scottish Local Authorities from 2020/21 through to 2025/26.  Argyll and Bute
Council will receive a total of £938k for Play Park funding. 
1.2 In December 2022, the Environment, Development and Infrastructure Committee
noted the priority list of play parks in each area, based on inspections and
feedback from Youth Forums.  A copy of this can be found in the following link:- 
Environment, Development and Infrastructure Committee 1 December 2022
1.3 The March 2023 Environment, Development and Infrastructure Committee
agreed a process for further engagement with other groups, including youth
forums and relevant Community Councils. 
1.4 This report outlines the response from the engagement exercise and seeks
agreement for an Area Business Day to take forward how the funding will be spent
in the Mid Argyll, Kintyre and Islands area.   
RECOMMENDATIONS
It is recommended that the MAKI Area Committee:
• Note the breakdown of engagement and consultation responses in each
area with the majority of responses focussing on new/replacement
equipment;
• Agree that officers make arrangements for a Business Day to agree how
the funding will be spent in Mid Argyll, Kintyre and Islands; and
• Agree to progress Tarbert Play Park and supplement the current funding
available with £20k from the Scottish Government Play Park Funding
allocation.

Page 2

ARGYLL AND BUTE COUNCIL  MID ARGYLL, KINTYRE AND
ISLANDS AREA COMMITTEE
ROAD AND INFRASTRUCTURE   6 September 2023
SERVICES
PLAY PARK ENGAGEMENT – UPDATE REPORT
2.0 INTRODUCTION
2.1 This report provides an update to the Play Park engagement responses for the
Mid Argyll Kintyre and Islands Area Committee.
3.0 RECOMMENDATIONS
3.1 It is recommended that the Mid Argyll, Kintyre and Islands Area Committee:
• Note the breakdown of engagement and consultation responses in each
area with the majority of responses focussing on new/replacement
equipment;
• Agree that officers make arrangements for a Business Day to agree how
the funding will be spent in Mid Argyll, Kintyre and Islands; and
• Agree to progress Tarbert Play Park and supplement the current funding
available with £20k from the Scottish Government Play Park Funding
allocation.
4.0  DETAIL
4.1  In August 2022, the Scottish Government confirmed a full 5 year funding package
to all Scottish Local Authorities from 2020/21 through to 2025/26.  Argyll and Bute
Council will receive a total of £938k for Play Park funding. 
4.2 The below table highlights the funding split for each area as well as the number 
of play parks, as per previous Environment, Development and Infrastructure
Committee agreement, the funding was an indicative £33,500 per play park which,
when the engagement process has been fully reviewed, this can be amended by
the local Area Committee.
Area Number of Play
Parks
Funding Total
Helensburgh and
Lomond
11 £368,500

Page 3

Mid Argyll, Kintyre and
the Islands
11 £368,500
Bute and Cowal 5 £167,500
Oban Lorn and the Isles 1 £33,500
TOTAL 28 £938,000
4.3 The March 2023 EDI Committee agreed a process for further engagement with
other groups, including youth forums and relevant Community Councils.
4.4 Area Committee Business days with Elected members took place in 2022. A full
engagement process has since taken place and the online engagement for adults
and youths closed on Friday 14 July 2023 with the following update:- 
• 1054 Adult Responses
• 408 Youth Responses
This was a remarkable return for the play park engagement process and
highlights the depth of feeling play parks have on our communities who are clearly
keen to express their views.
4.5 The responses were broken down as follows:
A Total of 1054 adult responses:
Area New/Replacement
Equipment
Health and Safety Access for ALL
Bute and
Cowal
146 35 64
Helensburgh
and Lomond
226 74 54
Mid Argyll,
Kintyre and
Islands
215 40 37
Oban Lorn
and the Isles
9 3 4
Out of the 1054 adult responses there were a total of 147 which were void either
due to referring to a non-council play park or being unable to assess the correct
location from the comments.
A Total of 408 Youth Responses:
Area New/Replacement
Equipment
Health and Safety Access for ALL
Bute and
Cowal
68 7 5

Page 4

Helensburgh
and Lomond
101 7 4 (Plus 2 don’t
know)
Mid Argyll,
Kintyre and
Islands
129 5 8 (plus 1 Don’t
Know)
Oban Lorn
and the Isles
1 0 0
Out of the 408 young person responses there were a total of 70 which were void
either due to referring to a non-council play park or being unable to assess the
correct location from the comments.
A note of the responses to the engagement priorities from the Mid Argyll, Kintyre
and Islands community is attached at Appendix 1 of this report.
4.6 At the request of the Council Leader, further engagement has been carried out
and South Islay Development have been identified as carrying out work to the
Port Ellen Play Park, they are keen to work with the Council to improve the play
park as a partnership approach to benefit the local community.
4.7 Tarbert Play Park is currently in the process of being upgraded, the equipment
was previously removed for safety concerns and whilst there is funding of
approximately £80k within current resources, it was the opinion of officers that this
could be supplemented by the Scottish Government Play Park funding. As such
officers delayed the works until the play park engagement work was completed
and the returns reviewed.  In light of the feedback from the public in Tarbert, it is
the view of officers’ that works to this park are taken forward, on the basis that
there is £80k of budget available.  The new play park will have a resin based
surface and it is proposed to include a net swing and wheelchair accessible
roundabout, however this is likely to increase costs beyond the £80k available by
approximately £20k. 
4.8  The Council now requires to consider what equipment is needed for each play
park.  It is proposed that Area Business Days are arranged with Ward Members
and officers will bring forward proposals which will be based on the feedback
from the consultation.   
4.9 The costings of equipment only:-
• Swings - £6500 + VAT
• Spring Seesaw - £2750 + VAT
• Climbing Net - £11,250.00 + VAT
• Wheel Chair Accessible Roundabout - £5000-£12000 +VAT
The funding for the Mid Argyll Kintyre and Islands area to cover its 11 play parks
is £368,500.

Page 5

4.10  The timeline for play parks is noted as follows:- 
ACTION TIMESCALE
Engagement with Community Councils and
Education Department 
Commenced March-May 2023
Engagement with Disability Forums Expected to commence
Autumn/Winter 2023
Area Business Days to agree how funding
will be spent 
Autumn (prior to Area Committee
Meetings in December 2023) 
Area Committee to formally agree the
funding for each play park 
December 2023
Procurement process (which will last 8 – 12
weeks) 
Expected to commence early 2024
Installations Expected to commence Spring 2024
(dependent on procurement process
as above) 
5.0 CONCLUSION
5.1 The Scottish Government has allocated a total of £938k for Play Park funding to
Argyll and Bute Council for investment in play park equipment through to 2025/26
from the Capital Allocation for Renewal of Play Parks Fund. 
5.2 Officers will make the necessary arrangements for a Mid Argyll, Kintyre and
Islands Area Committee Business Day to take place, which will allow officers to
report to the December Area Committee to formally agree the funding for each
play park in the area.  
6.0 IMPLICATIONS
6.1 Policy – This project will be delivered within the Procurement tendering process
however, as we have had two unsuccessful processes already as well as a
direct award failure members should note that this may well delay matters and
officers.
6.2 Financial – funded from grant funding from Scottish Government.
6.3 Legal – None known.
6.4 HR – None known.
6.5 Fairer Scotland Duty: None known

Page 6

6.5.1   Equalities - protected characteristics – engagement will take place with
appropriate groups, including the disability forum, to provide a positive impact
on our young people.
6.5.2   Socio-economic Duty – None known.
6.5.3 Islands – elements of renewal on all play parks, which therefore will not
adversely affect islands.
6.6. Climate Change – we will endeavour to minimise carbon footprint of this project.
6.7  Risk – Failure to deliver within the allotted Scottish Government timescales may
result in losing the budget allocated.
6.8  Customer Service – the intention of this funding is to provide better facilities for
our customers.
Executive Director with responsibility for Road and Infrastructure Services,
Kirsty Flanagan
Policy Lead for Climate Change and Environment, Councillor Ross Moreland
August 2023
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
Hugh.ONeill@argyll-bute.gov.uk 
APPENDICES:
Appendix 1 – Breakdown of community responses to consultation 
Appendix 2 – Breakdown of indicative costs for equipment and fitting

Page 7

APPENDIX 1: BREAKDOWN OF COMMUNITY RESPONSES TO
CONSULTATION 
Play Park
Name/Location
Responses for
priority being
Renew/Replace 
Responses for
priority being
Health and Safety 
Responses for
priority being
Access for ALL 
Young Adult Young Adult Young Adult
Ardrishaig  13 29 1 5 0 6
Ardrishaig
KGV 
4 14 1 2 0 3
Bay View Port
Ellen 
11 10 0 5 2 4
Bengullion
Skate Park
1 2 1 1 1 1
Jocks Boat,
Campbeltown 
8 25 0 9 0 3
Hillside  18 20 1 2 2 5
Stewarton  7 12 0 5 0 1
Kinloch Park  6 8 0 0 0 0
Lochend  13 6 1 3 1 2
Meadows  16 35 0 5 1 7
Tarbert  32 54 0 3 1 4
(Plus 1
Don’t
Know)
Total: 129 215 5 40 8 37

Page 8

APPENDIX 2: INDICATIVE COSTS FOR PLAY EQUIPMENT
1. CUSTOM Ship £18,800.00 plus installation £3,125.00
2. Featured Springer between £500 to £630.00 plus Installation £294.00
3. Spring Seesaw £2,250.00 plus Installation £514.00
4. Climbing Net £11,250.00 plus Installation £3,372.00
5. Frame £4,360.00 plus Installation £698.00
6. Spinner Bowl £680.00 plus Installation £231.00
7. Swing Frame, £5,040.00 plus Installation £1,452.00
8. Flexus stand up swing, £3,120.00 plus Installation £514.00
9. Ground Preparation £54,966.62
• Site Set up
• Excavate area and remove spoil off site,
• Supply & install kerb edging,
• Supply & lay cultivated turf
• Supply & sow seed
• Safer Surfacing WETPOUR
• Heras site security fencing
• Removal of packaging and Waste
10. Equipment Delivery Charge £4,181.20
11. Total Excl. VAT £115,477.82
12. Total Inclusive of VAT = £138,573.38