Page 1

Argyll and Bute Council  
Development and Economic Growth     
This Supplementary report is a recommended response to the Scottish Government’s
Energy Consents Unit (ECU) consultation on the Section 36 Consultation for Ladyfield
Renewable Energy Park Ltd comprising up to 13 turbines with a maximum height of
180m and ancillary infrastructure, including a Battery Energy Storage System (BESS)
on Land approximately 4.7 km north of Inveraray
_________________________________________________________________________  
Reference No: 24/00053/S36/ECU0003291  
Applicant:       The Scottish Government 
Proposal:  Section 36 Consultation for erection of 13 turbines with a maximum   
height of 180m, and ancillary infrastructure, including a Battery Energy   
Storage System (BESS)
Site Address:   Land Approximately 4.7 km north of Inveraray
________________________________________________________________________   
SUPPLEMENTARY REPORT NO. 1 
1. INTRODUCTION  
1.1 A detailed Report of Handling was prepared for PPSL Committee on the 20th
November 2024 (dated 6th November 2024).  The committee were advised that due
to an outstanding issue regarding Noise, the Energy Consents Unit had agreed to
an extension for submission of a consultation response from Argyll and Bute Council
in respect of this proposal to 19th December 2024.  
1.2 It was recommended that consideration of this proposal be continued until the PPSL
Committee on 18 December 2024 when an updated report would be presented. 
1.3 The Committee agreed to continue consideration of this proposal to their meeting on
18 December 2024. 
1.4 This Supplementary Report provides an update for Members on this Section 36
Consultation.  
2. REPRESENTATION UPDATE  
2.1 Since November PPSL no further representations have been received by the Energy
Consents Unit.  
3. CONSULTATION UPDATE  
3.1 NatureScot - since November PPSL it has been brought to the attention of Officers
that the Energy Consents Unit had not uploaded the most recent consultation
response from NatureScot.  This response was received by the ECU in the 14th May
2024 and simply confirmed that they had no further comments to make on the
application.  Consequently, no change is required to the Officer recommendation in
respect to the advice provided by NatureScot.  
4. NOISE  
4.1 In the Report of Handling it was recommended that the ECU be notified that Argyll
& Bute Council objected to the proposal on the grounds that there were unresolved

Page 2

noise issues, and it was not possible to reach a conclusion on the proposal's
acceptability in that regard at that time.  Furthermore, that if these matters were
resolved Argyll & Council would withdraw its objection.  
4.2 Following November PPSL the Applicant provided further clarification to the points
raised by the Council’s Noise Consultant.   
Applicant (25th November 2024) – in summary, are pleased that the Noise
Consultants report concludes that in general good practice has been adopted, seeks
clarity on a couple of minor matters and recommends that a condition can be used
to control noise from the proposal. 
The report recommends that the day-time noise limits proposed in the EIAR can be
accepted, but that the night-time noise limits should be reduced to a minimum of
38dB instead of 43dB.  Although the 43dB minimum fixed limit is recommended for
night-time periods in ETSU-R-97 (which is still recommended in current Scottish
planning guidance), in this instance the applicant is prepared to accept the proposed
noise limit values. 
On this basis the Applicant accepts the planning condition recommended by the
Council’s Noise Consultant subject to a couple changes to bring the wording more
in line with current good practice.  In particular, the requirement for post-construction
monitoring in the absence of complaints is proposed to be deleted as it does not
accord with the ETSU-R-97 guidelines.    
4.3 The Applicant’s response, which included points of clarification and a revised noise
condition was forwarded to the Council’s Noise Consultant for comment. 
Council’s Noise Consultant (27th November 2024) – advised that they have reviewed
the information provided by the Applicant.  They confirm that the Applicant is correct
– the requirement to monitor within 6 months from the start of operation is not part
of the example condition that they had used as the basis for the included condition. 
They are happy for this to be removed and rely upon the requirement to monitor in
response to reasonable complaint.  Finally, the additional information provided
covers their request. 
4.4 The agreed condition is attached at Appendix 1 of this report.  
5. CONCLUSION & RECOMMENDATION  
5.1 To conclude, all outstanding noise matters have now been addressed, subject to the
agreed condition.  Consequently, it is recommended that the noise objection is
removed and the recommendation is amended as follows. 
(1) Argyll & Bute Council does not object on landscape and visual grounds,
however, recommends the following advice is considered by the Energy
Consents Unit: 
Mitigation - Consideration should be given to the mitigation recommended by the
Council’s Consultant Landscape Architect: 
• There is scope to reduce effects on views from Glen Aray and from Dun na
Cuaiche by removing or substantially reducing the heights of Turbines 11 and
13. This measure would also reduce intrusion from Loch Fyne, particularly in the
Strachur area and would negate adverse impacts (particularly if woodland were

Page 3

to be removed in future) close to Inveraray at Viewpoint 4. It is additionally
recommended that off-site planting should be undertaken to extend screening
along the A819 and mitigate effects on views. 
• The applicant should also consider more ambitious landscape and biodiversity
mitigation and enhancement proposals in line with the aims of NPF4 Policy 3.
The proposed wind farm should form a catalyst to effect quicker and more far-
reaching improvement to uniform and, in places, poorly designed forestry. The
proposed Wind Farm Restocking Plan does not hugely differ from the baseline
Restocking Plan (see Figures 14.4 and 14.7) and more should be done to
improve the angular northern and south-eastern margins of productive forest.
The planting of more extensive native woodlands should form part of the
Biodiversity Enhancement Management Plan (BEMP) and Wind Farm Forest
Plan. Biodiversity and landscape enhancement measures should not be
confined to the site (which is limited by its use as a productive forest) but should
extend outside the site with the aim of better integrating the forest with its
surroundings and improving connectivity for wildlife. 
• The effects of visible aviation lighting are concerning particularly given the
considerable number of applications in Argyll & Bute where turbine lighting is
proposed. While it is accepted that the day-time effects of the proposal would be
of greater significance and would be likely to affect more people, consideration
should be given to future mitigation of the effects of lighting on the dark skies of
Argyll. It is therefore also strongly recommended that an Aircraft Detection
Lighting System should be installed at the earliest opportunity as this would
reduce the duration and impact of night-time lighting. 
(2) Argyll & Bute Council recommends that the recommendations of the Local
Biodiversity Officer are considered by the ECU: 
• Floatation tracks must be used on areas of deeper peat to avoid disturbance.
• While the impact to bats is unlikely to be significant, it would be advisable to
monitor any fatalities that may occur from collision as they are found to forage
within the wind turbine areas.
• the applicant should include a clear plan of proposed fence siting, the type of
marking to be used, the distance from known lek sites, and programme of
monitoring fence for any potential black grouse carcasses. 
(3) Argyll & Bute Council recommends that all conditions recommended by
consultees should be included in any Consent 
Author of Report: Arlene Knox        Date: 2nd December 2024
Reviewing Officer: Sandra Davies       Date: 3rd December 2024 
 
  
Fergus Murray   
Head of Development and Economic Growth

Page 4

APPENDIX 1: NOISE CONDITION 
The rating level of noise immissions from the combined effects of the wind
turbines hereby permitted (including the application of any tonal penalty and
amplitude modulation (AM) penalty), when determined in accordance with the
attached Guidance Notes, shall not exceed the values for the relevant integer
wind speed set out in or derived from Table 1 attached to these conditions and: 
A) The wind farm operator shall continuously log power
production, wind speed and wind direction, all in
accordance with Guidance Note 1(b). This data shall be
retained for a period of not less than 24 months. The wind
farm operator shall provide this information in a format to be
agreed with the Planning Authority within 14 days of receipt
in writing of such a request.
B) Within 21 days from receipt of a written request of the
Planning Authority, following a complaint to it alleging noise
disturbance at a dwelling, the wind farm operator shall, at its
expense, employ an independent consultant and provide a
written protocol to be approved by the Planning Authority.
The protocol shall describe the procedure to assess the
level and character of noise immissions from the wind farm
at the complainant's property in accordance with the
procedures described in the attached Guidance Notes. The
written request from the Planning Authority shall set out as
far as possible the time or meteorological conditions to
which the complaint relates and time or conditions relating
to tonal noise or AM if applicable. Measurements to assess
compliance with the noise limits shall be undertaken in
accordance with the assessment protocol which shall be
approved in writing by the Planning Authority.
C) The assessment of the rating level of noise immissions shall
be undertaken in accordance with an assessment protocol
that shall, prior to the commencement of any
measurements, have been submitted to and approved in
writing by the Planning Authority. The protocol shall include
the proposed measurement location identified in
accordance with the Guidance Notes where measurements
for compliance checking purposes shall be undertaken and
also the range of meteorological and operational conditions
(which shall include the range of wind speeds, wind
directions, power generation and times of day) to determine
the assessment of rating level of noise immissions. The
proposed range of conditions shall include those which
prevailed during times when the complainant alleges
there was disturbance due to noise, having regard to the
written request of the Planning Authority under paragraph
(b), and such others as the independent consultant
considers likely to result in a breach of the noise limits.
D) The wind farm operator shall provide to the Planning
Authority the independent consultant's assessment of the
rating level of noise immissions undertaken in accordance
with the protocol within 2 months of the date of the approval

Page 5

of the protocol by the Local Authority unless otherwise
agreed by the Planning Authority. The assessment shall
include all data collected for the purposes of undertaking
the compliance measurements and analysis, such data to
be provided in a format to be agreed with the Planning
Authority. Certificates of calibration of the equipment shall
be submitted to the Planning Authority with the report.
E) Where a further assessment of the rating level of noise
immissions from the wind farm is required pursuant to
Guidance Note 5 of the attached Guidance Notes, the wind
farm operator shall submit a copy of the further assessment
within 21 days of submission of the independent
consultant's initial assessment unless otherwise agreed by
the Planning Authority. 
Table 1 Daytime and night-time noise limits on combined operational noise
levels due to the consented wind turbines (LA90, dB) 
Standardised
wind speed
v10 m/s
1 2 3 4 5 6 7 8 9 10 11 12
Ladyfield Farm, North Tullich and South Tullich
Daytime
dB LA90
37.2 38.2 39.1 40.1 41.1 42.1 43.2 44.2 45.4 46.5 47.7 48.9
Night-time
dB LA90
38.0 38.4 39.4 40.3 41.2 42.2 43.2 44.2 45.3 46.5 47.7 49.0             
Drimfern            
Daytime
dB LA90
35.0 35.0 35.6 36.7 37.6 38.7 39.8 40.9 42.1 43.2 44.5 45.7
Night-time
dB LA90
38.0 38.0 38.0 38.0 38.0 38.5 39.4 40.4 41.5 42.6 43.8 44.9             
Three Bridges and Linnieghluttain
Daytime
dB LA90
45.1 45.1 45.3 45.8 46.5 47.3 48.2 49.2 50.1 50.9 51.7 52.2
Night-time
dB LA90
45.7 45.7 45.7 46.1 46.7 47.5 48.3 49.2 49.9 50.5 50.8 50.8             
Maam House            
Daytime
dB LA90
40.8 41.6 42.4 43.2 44.1 45.0 45.9 46.8 47.7 48.7 49.7 50.7
Night-time
dB LA90
42.1 42.6 42.9 43.4 43.8 44.3 45.0 45.7 46.6 47.7 49.0 50.6 
Reason: to protect residential amenity.

Page 6

Guidance Notes for Noise Condition
These notes are to be read with and form part of the planning condition on noise.
The measured data is to be split into bins as described below. The rating level
in each bin is the arithmetic sum of the wind farm noise level, any tonal penalty
applied in accordance with Note 3 and any AM penalty applied in accordance
with Note 4. Reference to ETSU-R-97 refers to the publication entitled "The
Assessment and Rating of Noise from Wind Farms" (1997) published by the
Energy Technology Support unit (ETSU) for the Department of Trade and
Industry (DTI). IOAGPG is “A Good Practice Guide to the Application of ETSU-
R-97 for the Assessment and Rating of Wind Turbine Noise” or any update of
that report current at the time of measurement. The IOA Metric is “A Method for
Rating Amplitude Modulation in Wind Turbine Noise” dated 9th August 2016 or
any update of that current at the time of measurement. 
Note 1 – Data Collection
a. Values of the LA90,10-minute noise index should be measured in
accordance with the IOAGPG. Measurements shall be undertaken in such
a manner to enable a tonal penalty to be calculated and to allow an AM
penalty to be calculated for selected periods where a tonal or AM
assessment is required.
b. To enable compliance with the conditions to be evaluated, the wind farm
operator shall continuously log arithmetic mean wind speed in metres per
second (m/s) and arithmetic mean wind direction in degrees from north in
each successive 10-minutes period in a manner to be agreed in writing
with the Planning Authority. The wind speed at turbine hub height shall be
'standardised' to a reference height of 10 metres as described in ETSU-
R- 97 at page 120 using a reference roughness length of 0.05 metres. It
is this standardised 10 metre height wind speed data which are correlated
with the noise measurements determined as valid. The wind farm operator
shall continuously log arithmetic mean nacelle anemometer wind speed,
arithmetic mean nacelle orientation, arithmetic mean wind direction as
measured at the nacelle, arithmetic mean rotor RPM and whether each
wind turbine is running normally during each successive 10-minutes period
for each wind turbine on the wind farm. All 10-minute periods shall
commence on the hour and in 10-minute increments thereafter
synchronised with Universal Time (UT). 
Note 2 – Data Analysis
a. The independent consultant shall identify a sub-set of data having had regard to:-
• the conditions (including time of day and corresponding wind
directions and speeds) at times in which complaints were recorded;
• the nature/description recorded in the complaints if available;
• information contained in the written request from the local planning authority;
• likely propagation effects (downwind conditions or otherwise);
• the results of the tonality/AM analysis where relevant.
In cases where it is possible to identify patterns of clearly different
conditions in which complaints have arisen additional sub-sets may be
considered provided this does not introduce unreasonable complexity in
the analysis and can be justified by the independent consultant.
b. Within each of the sub-set(s) of data identified, data shall be placed into

Page 7

separate 1 m/s wide wind speed bins. 
Note 3 – Tonal Penalty
a. Where, in accordance with the protocol, the noise contains or is likely to
contain a tonal component, a tonal audibility shall be calculated for each
ten-minute period using the following procedure.
b. For each 10-minute period for which a tonal assessment is required this
shall be performed on noise immissions during 2-minutes of each 10-
minute period. The 2-minute periods should be spaced at 10-minute
intervals provided that uninterrupted uncorrupted data are available ("the
standard procedure").
c. For each of the 2-minute samples the tone level above audibility shall be
calculated by comparison with the audibility criterion given in Section 2.1
on pages 104 -109 of ETSU-R-97. Samples for which the tones were below
the audibility criterion or no tone was identified, a value of zero audibility
shall be substituted. Where data for a ten-minute period are corrupted,
that period shall be removed from the tonal analysis.
d. The tone level above audibility for each ten-minute period shall be placed
in the appropriate data sub-set and wind speed bin. 
Note 4 – AM Penalty
a. Where, in accordance with the protocol, the noise contains or is likely to
contain AM, an AM penalty shall be calculated for each ten-minute period
using the following procedure.
b. For each 10-minute interval for which an AM assessment is required this
shall be performed in accordance with The IOA Metric. The value of AM
for each ten-minute period shall be converted to a penalty in decibels in
accordance with the graph below and the penalty shall be placed in the
appropriate data sub-set and wind speed bin. Where a penalty is zero it
should be placed in the bin in the same way. 
Note 5 – Calculation of Rating Level
a. The LA90 sound pressure level for each data sub-set and wind speed bin
is the arithmetic mean of all the 10 minute sound pressure levels within

Page 8

1
that data sub-set and wind speed bin except where data has been
excluded for reasons which should be clearly identified by the independent
consultant. The tonal penalty for each bin is the arithmetic mean of the
separate 10-minute tonal audibility levels in the bin converted to a penalty
in accordance with Fig 17 on page 104 of ETSU-R-97. The AM penalty for
each bin is the arithmetic mean of the AM penalties in the bin. The
assessment level in each bin is the arithmetic sum of the bin LA90, and
the larger of the AM or tonal penalty should be applied.
b. If the assessment level in every bin lies at or below the values set out in
the Table(s) attached to the conditions then no further action is necessary.
In the event that the assessment level is above the limit(s) set out in the
Tables attached to the noise conditions in any bin, the independent
consultant shall undertake a further assessment of the rating level to
correct for background noise so that the rating level relates to wind turbine
noise immission only. Correction for background noise need only be
undertaken for those wind speed bins where the assessment level is
above the limit.
c. The wind farm operator shall ensure that all the wind turbines in the
development are turned off for such periods as the independent consultant
requires to undertake the further assessment. The further assessment
shall be undertaken in accordance with the following steps:-
i. Repeating the steps in Note 1, with the wind farm switched off, and
determining the background noise (L3) in each bin as required in the
protocol. At the discretion of the consultant and provided there is no
reason to believe background noise would vary with wind direction,
background noise in bins where there is insufficient data can be
assumed to be the same as that in other bins at the same wind
speed.
ii. The wind farm noise (L1) in each bin shall then be calculated as
follows where L2 is the measured level with turbines running but
without the addition of any tonal nor AM penalty:
L  = 10 log10L2 /10  −10L3 /10 
iii. The rating level shall be calculated by adding the tonal and AM
penalties to the derived wind farm noise L1 in that bin.
iv. If the rating level after adjustment for background noise contribution
and adjustment for tonal and AM penalties in every bin lies at or
below the values set out in the Tables attached to the condition at
all wind speeds then no further action is necessary. If the rating level
at any integer wind speed exceeds the values set out in the Table(s)
attached to the condition then the development fails to comply with
the planning condition in the circumstances represented by that bin.