ARGYLL AND BUTE COUNCIL      POLICY AND RESOURCES COMMITTEE
COMMERCIAL SERVICES                              08 DECEMBER 2022 
OUR MODERN WORKSPACE (OMW) – PLACE DEMONSTRATOR FUNDING FOR
ROTHESAY 
1.0 EXECUTIVE SUMMARY 
1.1. The Scottish Government have sought applications from Local Authorities that
have undertaken Place Based Reviews (PBR) and are in a position this financial
year to implement the outcomes of the review.
1.2. A Place Based Review of Rothesay and Dunoon was undertaken in 2021 jointly
funded by the Council, HSCP and NHS Highland and the outcomes and actions
from that review have been used and act as a foundation for changes we are
implementing through Our Modern Workspace (OMW).
1.3. A bid to this competitive fund was made by the OMW team in August 2022 and
the Scottish Government have now confirmed Argyll and Bute Council’s
application to implement the redesign proposals in Rothesay has been
recommended for a grant award.  This includes both the Victoria St Office and
the Union St Office.  The verbal confirmation is for the total capital costs for
Rothesay to be funded as noted in Appendix 1 It is recognised Argyll and Bute
are one of only a few authorities to have both completed a PBR and progressed
far enough with staff engagement, permissions and strategy to implement
actions this financial year. 
1.4. This level of funding would allow the OMW Project team to accelerate the
Rothesay redesign which was originally part of Phase 2 and subsequently divert
capital resources into other priorities or remove pressures in available budget.
1.5. The Scottish Government have requested that Argyll and Bute Council make a
public commitment to:
 ensure the funds awarded are spent solely on this project
 demonstrate the place context, in discussion with other key partners
 note the additionality this funding can provide – what this funding can
unlock in the context of the wider Place Narrative.
 Confirm the project and Council commitment by 31 March 2023

Page 2

ARGYLL AND BUTE COUNCIL      POLICY AND RESOURCES COMMITTEE
COMMERCIAL SERVICES                              08 DECEMBER 2022 
OUR MODERN WORKSPACE (OMW) – PLACE DEMONSTRATOR FUNDING FOR
ROTHESAY 
2.0 INTRODUCTION 
2.1. The Scottish Government have sought applications from Local Authorities that
have undertaken Place Based Reviews (PBR) and are in a position this financial
year to implement the outcomes of the review.
2.2. A Place Based Review of Rothesay and Dunoon was undertaken in 2021 jointly
funded by the Council, HSCP and NHS Highland and the outcomes and actions
from that review have been used and act as a foundation for changes we are
implementing through Our Modern Workspace (OMW).
2.3. A bid to this competitive fund was made by the OMW team in August 2022 and
the Scottish Government have now verbally confirmed Argyll and Bute Council’s
application to implement the redesign proposals in Rothesay has been
recommended for a grant award.  This includes both the Victoria St Office and
the Union St Office.  The verbal confirmation is for the total capital costs for
Rothesay to be funded as noted in Appendix 1 It is recognised Argyll and Bute
are one of only a few authorities to have both completed a PBR and progressed
far enough with staff engagement, permissions and strategy to implement
actions this financial year. 
2.4. This level of funding would allow the OMW Project team to accelerate the
Rothesay redesign which was originally part of Phase 2 and subsequently divert
own capital resources into other priorities or remove pressures in available
budget.
2.5. The Scottish Government have requested that Argyll and Bute Council make a
public commitment to:
 ensure the funds awarded are spent solely on this project
 demonstrate the place context, in discussion with other key partners
 note the additionality this funding can provide – what this funding can
unlock in the context of the wider Place Narrative.
 Confirm the project and Council commitment by 31 March 2023

Page 3

3.0 RECOMMENDATIONS 
Committee are asked to:-
3.1  Note this opportunity to access substantial Scottish Government capital
funding as noted in Appendix 1;
3.2 Agree that the Place Demonstrator Funding will only be used to complete Our
Modern Workspace programme in Rothesay to demonstrate the context of
Place as a direct outcome of the Place Based Review 
3.3 Agree that the Council should accept the opportunity to work with the Scottish
Government and Scottish Futures Trust to accelerate the Rothesay Phase of
the Our Modern Workspace through the Place demonstrator Funding by
committing to their requests:- 
 demonstrate the place context, in discussion with other key partners
 note the additionality this funding can provide – what this funding can
unlock in the context of the wider Place Narrative, and
 Confirm the project and Council commitment by 31 March 2023 
4.0 DETAIL 
4.1. The Place Demonstrator Fund has been established by the Scottish
Government and is part of the Place Based Investment Programme.  The
process for applications was as follows:
 A group has been convened by SG across COSLA, Government,
HIE, SOSE, SFT, STP and DTAS
 A set of criteria for investment and learning have been developed
 The group is identifying a long list of possibilities
 This list then works through conversations with the places to
understand fit and deliverability
 A short list is brought to the group for consideration and agreement
 The recommendations are agreed by the Minster
 Allocation is for the financial year 2022/23  
4.2. Given the Place Based Review undertaken for Dunoon and Rothesay by
HubNorth Scotland in 2021, it was suggested by them that Argyll and Bute
project are considered appropriate to make a submission to the Place
Demonstrator Fund to accelerate the implementation of the redesign of offices in
Rothesay as this met the criteria for the funding.  
4.3. In order to accurately reflect the costs for this part of the project. A review of the
initial cost plan was undertaken to ensure the costs accurately reflected the
current market costs given recent significant inflation increases. These costs are
noted in Appendix 1: NB – Note given that the budget / financial information
contained within this appendix relates to commercially sensitive information as
part of an imminent tender the Appendix is considered as publically restricted.

Page 4

4.4. If the panel do commend the Rothesay project and this funding is made
available it will only be able to be used for the delivery of the redesign of both
Union St and Victoria St offices in Rothesay due to nature and objectives of the
fund.  Copies of the proposed floor plans are attached at Appendix 2.
4.5. This is an opportunity for Argyll and Bute Council to work with the Scottish
Futures Trust and HubNorth Scotland to assist other Local Authorities that are at
the very start of their office rationalisation and co-location programmes to
understand the Place narrative around how they look to better utilise their
assets.
4.6. The Scottish Government have requested that Argyll and Bute Council make a
public commitment to:
 ensure the funds awarded are spent solely on this project
 demonstrate the place context, in discussion with other key partners
 note the additionality this funding can provide – what this funding can
unlock in the context of the wider Place Narrative.
 Confirm the project and Council commitment by 31 March 2023 
4.7 There were a number of outcomes identified in the Place Based Review of
Rothesay and Our Modern Workspace is the first of those to be implemented.  It
is hoped that this funding and subsequent acceleration of these outcomes will
provide a catalyst to the other partners involved in the Place Based Review to
look at implementation of further outcomes identified. 
4.8 The Place Based Review has allowed the review of spaces with other key
partners, one of those are the Scottish Courts Services – who currently have
some occupation of Eaglesham House, Rothesay which will become largely
surplus to requirements following the remodelling exercise as proposed.   
4.9 The remodelling of both Union Street and Victoria Street offices will free up
Eaglesham House for further development opportunities, the OMW team will
work with other Council Services and wider key partners to utilise the building to
best meet the needs of the Island. 
4.10 Further opportunities to utilise the spaces within these buildings to support the
communities on the island are welcome and fundamental to the OMW project. 
5.0 CONCLUSION
5.1 This paper provides an overview of the funding application submitted to the
Scottish Governments Place Demonstrator Fund. 
6.0 IMPLICATIONS
6.1 Policy : SG funding requirement to have a public commitment to the project in
the terms noted within the paper
6.2 Financial : This funding will provide significant investment in Rothesay 
6.3  Legal : None

Page 5

6.4  HR : Funding will support the implementation of the Hybrid and Flexible
Working Policy
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics 
6.5.2   Socio-economic Duty 
6.5.3  Islands 
6.6 Climate Change : the works undertaken will take cognisance of net zero best
practice 
6.7 Risk: without this funding the implementation of the OMW programme in
Rothesay would not be delivered until available budget was identified in
the Capital Plan
6.8  Customer Service : the completion of the works in Victoria St will provide easier
access to Public Services within a High Street location 
Douglas Hendry
Executive Director with responsibility for Commercial Services
Policy Lead Cllr Gary Mulvaney
08 December 2022                                                  
For further information contact: 
Ross McLaughlin, Head of Commercial Services
Shirley Johnstone, Change Manager 
APPENDICES
Appendix 1 – Financial Summary – Publically restricted due to commercial /
contractual nature
Appendix 2 – Proposed Floor Plans for Union St and Victoria St Offices