ARGYLL AND BUTE COUNCIL     POLICY AND RESOURCES COMMITTEE                                                                           
DEVELOPMENT AND ECONOMIC GROWTH                   8 DECEMBER 2022 
CONSERVATION AREA REGENERATION SCHEME (CARS) PROJECT 
3-17 COLCHESTER SQUARE, LOCHGILPHEAD 
1.0 EXECUTIVE SUMMARY 
1.1 The Lochgilphead Conservation Area Regeneration Scheme (CARS) is a grant
programme focussing on the regeneration of historical buildings as well as
traditional skills training and community engagement. Lochgilphead CARS is
jointly funded by Historic Environment Scotland and Argyll and Bute Council.
1.2 Argyll and Bute Council has recognised a need for greater economic
development and regeneration activities within Lochgilphead particularly the
town centre. 
1.3 3-17 Colchester Square (see Appendix 1) is one of four priority buildings for
Lochgilphead CARS and comprises of two ground floor commercial units and
two first floor residential flats. The aim is to bring the building back to a good
level of repair, safeguarding the future of 2 businesses and 2 residential units.
1.4 The Lochgilphead CARS Officer and Housing Improvement Officer have been
working with this property since 2021.  The project development phase has
been completed and a report has been submitted to the Mid-Argyll, Kintyre and
the Islands Area Committee meeting on 7th December 2022, requesting
approval to award CARS grant funding of £241,808.68.  The grant figure was
based on the last available cost plan.  At the time of writing the first draft report,
the project was fully funded. 
1.5 Following the submission of the first draft report to MAKI Area Committee in
early November, the construction tender process was concluded on 21st
November 2022.  Due to inflation, including the increasing cost of building
materials, the original projected costs have escalated by £42,642.24. 
1.6      The private owners of the building have agreed to contribute another £2,000 
(£500 per unit).  This leaves a shortfall of £40,642.24.  There is capacity within 
the Private Sector Housing Grant (PSHG) budget for 2022/23, and providing the

Page 2

gap funding to facilitate this project aligns with the key aims of the PSHG to 
extend the life of capital assets. 
RECOMMENDATIONS 
It is recommended that the Policy and Resources Committee consider and
approve the utilisation of the Private Sector Housing Grant (PSHG) to award an
additional £40,642.24 grant to the 3-17 Colchester Square, Lochgilphead CARS
project, thus providing essential gap funding to facilitate the restoration of this
building.

Page 3

ARGYLL AND BUTE COUNCIL     POLICY AND RESOURCES COMMITTEE                                                                           
DEVELOPMENT AND ECONOMIC GROWTH                   8 DECEMBER 2022 
CONSERVATION AREA REGENERATION SCHEME (CARS) PROJECT – 3-17
COLCHESTER SQUARE, LOCHGILPHEAD 
2.0 INTRODUCTION 
2.1 This report outlines the gap funding that exists in the second priority building of
the Lochgilphead Conservation Area Regeneration Scheme (CARS).  The
CARS is jointly funded by Historic Environment Scotland and Argyll and Bute
Council. The report requests utilisation of an additional £40,642.24 grant funding
from the PSHG to cover that gap and facilitate this key project.   
3.0 RECOMMENDATIONS 
3.1 It is recommended that the Policy and Resources Committee consider and
approve the utilisation of the Private Sector Housing Grant (PSHG) to award an
additional £40,642.24 grant to the 3-17 Colchester Square, Lochgilphead CARS
project, thus providing essential gap funding to facilitate the restoration of this
building. 
4.0 DETAIL 
4.1 3-17 Colchester Square is a two-storey terrace building occupying a key location
in Lochgilphead town centre (see Appendix 1). It acts as a gateway building not
only for Colchester Square but for the progression of Argyll Street beyond which
is the primary commercial/shopping street in Lochgilphead.  It is one of four
Lochgilphead CARS priority buildings and comprises of two ground floor
commercial units and two first floor flats.   
4.2 The private owners formed an Owners Association to manage the repair and
future maintenance of the property.  They appointed a conservation
accredited Design Team to develop and manage the building repair project on
their behalf.

Page 4

4.3 A grant approval recommendation report has been submitted to the Mid Argyll,
Kintyre and the Islands Area Committee meeting for consideration on 7th
December 2022 requesting approval to award CARS grant funding of
£241,808.68, based on a total projected cost of £291,988.68. At the time of
writing that first draft report the project was fully funded as follows: 
4.4 Following the submission of the first draft MAKI report, the construction tender
process was concluded on 21st November 2022.  Due to inflation, including the 
increasing cost of building materials, the total project costs have escalated by 
£42,642.24 to £334,630.92.  The initial increase in cost was higher but the 
Design Team carried out a savings exercise, removing a number of items.  The 
remaining scope of works covers all essential items including partial re-slate of 
roof, full leadwork replacement, lime harling to chimney stacks, new stone copes 
to chimney stacks, removal of small chimney stack to north gable and the
replacement of gutters in cast iron.  All works are in line with HES’s advisory
standards of repair. 
4.4       Following discussions, the building owners have agreed to contribute an 
additional £2,000 (£500 per unit). This takes the total contribution from the 
building owners to £20,000. 
4.6  The proposal to this Committee is to utilize additional grant funding from the
PSHG to fill the outstanding £40,642.24 gap. PSHG should be spent on capital
projects such as; adding value to an asset, extending the life of an asset, or
acquiring a new asset. The proposed works described in this paper meet the
finance parameters for PSHG spend.  Although this is a larger grant level than
usual for PSHG it will fall within the available PSHG budget remaining for this
financial year, and will facilitate the completion of this key project within the
Lochgilphead CARS scheme. 
5.0 CONCLUSION 
5.1 The additional funds proposed would help to carry out extensive repairs to the
fabric of the building, helping to safeguard 2 businesses and 2 homes.  This
project will build on the investment to date in Lochgilphead town centre and
encourage other building owners to maintain and repair their properties. 
Lochgilphead CARS (Funding from HES and Council)    £241,808.68
Private Sector Housing Grant (4 standard grants)    £32,180.00
Private owners contribution       £18,000.00
Total project cost       £291,988.68

Page 5

6.0 IMPLICATIONS
6.1 Policy - The Outcome Improvement Plan, Economic Strategy and Local
Development Plan support town centre regeneration and a diverse and
thriving economy. 
6.2 Financial The proposed use of PSHG grant funding falls within the criteria for
use of PSHG and will appropriately utilise capital budget available for  this
financial year. 
6.3  Legal – Grant contracts will be provided to third parties. 
6.4  HR - A dedicated project officer has been recruited for the duration of the
Lochgilphead CARS project. Staff salaries are included within the project
budget. 
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics - None 
6.5.2   Socio-economic Duty - None 
6.5.3  Islands – None 
6.6 Climate Change – Extremes of weather caused by climate change will
continue to put buildings under pressure. These projects help property owners
undertake large scale maintenance projects under the supervision of
conservation accredited architects which ensures they are future proofed
against climate change, using traditional building materials.    
6.7 Risk - That grant schemes are undersubscribed or that projects run over time
or budget. These risks will be carefully monitored and mitigation measures
introduced on a case by case basis. 
6.8  Customer Service - The council is responsible for administering the CARS
grants on behalf of HES and for ensuring due diligence in the performance of
its duties. 
Kirst Flanagan Executive Director with responsibility for Development and
Economic Growth 
Councillor Liz McCabe, Policy Lead for Islands and Business Development 
Councillor Robin Currie, Policy Lead for Economy and Rural Growth 
24th November 2022 
For further information contact: 
James Lafferty, Lochgilphead CARS Project Officer 
james.lafferty@argyll-bute.gov.uk

Page 6

Douglas Whyte, Area Team Leader
douglas.whyte@argyll-bute.gov.uk 
APPENDICES
Appendix 1: Photograph showing the front elevation of 3-17 Colchester Square,
Lochgilphead

Page 7

APPENDIX 1: PHOTOGRAPH SHOWING THE FRONT ELEVATION OF 3-17
COLCHESTER SQUARE, LOCHGILPHEAD.