ARGYLL AND BUTE COUNCIL              POLICY & RESOURCES COMMITTEE
CLIMATE CHANGE BOARD            8th December 2022     
CLIMATE CHANGE BOARD UPDATE & DE-CARBONISATION TRACKER 
1.0 EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council has been addressing climate change themes for over 7
years through its well established Climate Change Board.  There has been a
notable reduction in the overall carbon emissions generated by the Council in the
past 5 years – reducing by over a third – through its De-Carbonisation Plan.  Whilst
our region is well placed in terms of overall natural assets and relative low number
of carbon emitting sources a great deal of work still needs to be done to achieve
Net Zero obligations by 2030 and 2045 plus become resilient for effects of more
severe weather events and sea level rises in coming years.   
1.2 The purpose of this report is to summarise and highlight some of the main activities
of the Climate Change Board over the previous quarter.   
2.0    RECOMMENDATIONS
2.1 The Policy and Resources Committee are asked to note and consider the updates
contained at Section 5 of the report and the full De-carbonisation Tracker update
contained within Appendix A.

Page 2

ARGYLL AND BUTE COUNCIL              POLICY & RESOURCES COMMITTEE
CLIMATE CHANGE BOARD            8th December 2022     
CLIMATE CHANGE BOARD UPDATE & DE-CARBONISATION TRACKER 
3.0  INTRODUCTION 
3.1 This report highlights recent activity of Climate Change Board. 
4.0    RECOMMENDATIONS 
4.1     The Policy and Resources Committee are asked to note and consider the updates
contained at Section 5 of the report and the full De-carbonisation Tracker update
contained within Appendix A.
5.0      SUMMARY UPDATES OF CLIMATE CHANGE BOARD 
A - Election of Policy Lead for Climate Change & Environment to Climate Change Board 
5.1 Following discussion at August P&R Committee it was agreed that Policy Lead
for Climate Change and Environment, Cllr Ross Moreland, would be elected
to the Climate Change Board (CCB).  Up until this point the Board had been
fully resourced by Officers and staff of our partners. 
5.2 Cllr Moreland joined the October Meeting of CCB which had range of agenda topics
and contributed widely on matters such as Local Heat Energy Efficiency Plans
(LHEES), Waste, Carbon Footprint submissions and Carbon Literacy Training. The
minute from that meeting reflects that both Cllr Moreland & Officers considered the
political presence at CCB was constructive.   
B – Kilmory Biodiversity Project Shortlisted for 3 National Awards 
5.3 A project backed by CCB and previously discussed at Policy & Resources
Committee and delivered earlier in 2022 has now been shortlisted for 3 national
awards.   
5.4 Argyll & Bute Council, ACT and Scottish & Southern Electric Networks (SSEN)
partnered to plant 30ha planting in our Kilmory Estate in Lochgilphead on land
as part of woodland conservation and compensatory planting resulting from
power line upgrades.  The sapling planting commenced in the summer of 2022
and has recently completed.  The planting will help towards meeting the twin
challenges of the climate and biodiversity crisis and establishes an innovative
partnership approach – some other spin off projects are already being
discussed.

Page 3

5.5 The planting is native and contributes to Argyll's rainforest, also known as Atlantic
woodland or Celtic rainforest (which is high value carbon sequestration), is a
unique and rare habitat of ancient and native woodland, open glades,
boulders, rocky cliffs and river gorges.  By planting native species such as
alder, willow, oak, aspen and blackthorn the planting will support local flora
and fauna, creating natural habitats for native species to thrive, supporting
commitments to deliver biodiversity net gain and compensatory planting on all
its major projects 
5.6 The awards the project has recently been shortlisted for are; (1) Scottish
Renewables Green Energy Awards (2) RSPB Nature of Scotland Awards (3) Utility
Week Awards.  Outcomes from these award shortlistings will be known prior to
Christmas.  Both nominations and outcomes will be publicised.   
C – Carbon Literacy Training / Climate Change Training 
5.7 The Council has been rolling out a programme of accredited Carbon Literacy
Training.  The Programme is tailored to both Elected Councillors and also senior
Officers within the Council.  It has been developed and delivered by ACT with
delegates who pass assessment being awarded a nationally recognised Carbon
Literacy Certificate. 
5.8 The Argyll and Bute focussed course is also available free of charge (limited places)
to community groups.  So far around 25 Councillors and Officers have completed
the workshop elements of the course with more cohorts to run in coming months.
The wider the knowledge base of Climate Change the more informed decisions can
be made in relation to the topic.  There is also opportunity to obtain corporate carbon
literate recognition once sufficient numbers of delegates have passed the course.   
5.9 Online Climate Change training for all networked staff (access to a computer) will
also be available in early 2024 as our electronic training system LEON has a
progressed version with assessment that is nearing completion.   
D – HEEPS Warmer Homes – NOW ENERGY EFFICIENT SCOTLAND: AREA BASED
SCHEME (EES:ABS) 
5.10 The Council was awarded a grant by the Scottish Government of £2,011,323
under their Energy Efficient Scotland: Area Based Scheme (EES:ABS) in
July 2022 to facilitate a programme of retrofitting insulation measures in
privately owned and privately rented homes throughout Argyll and Bute.   The
programme runs from 1st July to 30th June each year, and since 1st July 2022
£796,210.57 has been spent on insulation measures to date.  The Energy
Efficiency Team projects that the budget will be spent in full with expectations
that an application will be made to request further funding early in 2023. 
5.11 The programme covers the entire Argyll and Bute area with geography being
no barrier to eligibility for the scheme. 
5.12 In addition the Team has worked with Argyll Community Housing Association
(ACHA) to retrofit insulation on blocks of mixed-tenure flats in Oban and
hopes to work again in partnership with ACHA to replicate this programme for
approximately 150 properties in Cowal, Bute and Tarbert throughout 2023.

Page 4

5.13 The Energy Efficiency Team consists of a Project Officer and a Project
Administrator. 
E – De-carbonisation Tracker 
5.14 The De-carbonisation Plan sets a 3 year framework to continue our climate
journey and routemap to net zero.  Our Council has made a clear commitment
to be a net zero organisation by 2045 and has also declared a climate emergency
befitting the importance and critical nature of the topic.   Whilst the main
decarbonisation plan will be fixed for 3 years the associated Action Plan (which
forms an Appendix of the document) will be continuously updated and reported
to both the Climate Change Board and Policy & Resources Committee.  The
latest update can be found at Appendix A.   
6.0  CONCLUSION 
6.1 This report provides various updates in relation to the Council’s activities in
relation to Climate Change.   
7.0  IMPLICATIONS
7.1 Policy – Meeting obligations and commitment to Climate Change.
7.2 Financial – No direct linkage in this paper.  
7.3 Legal – Meeting requirements of climate change Scotland act.  
7.4 HR – None 
7.5 Fairer Scotland Duty 
7.5.1 Equalities – Protected characteristics – None
7.5.2 Socio economic Duty – None
7.5.3 Islands – None
7.6 Climate change – Direct link updating activities of CCB and projects that will
address climate change.  
7.7 Risk – Not addressing impacts or causes of climate change can lead to
increased cost or censure if targets are not met.  
7.8 Customer Service – None.
Douglas Hendry, Executive Director with responsibility for Commercial Services
Councillor Ross Moreland – Policy Lead Climate Change & Environment 
13 November 2022

Page 5

For further information contact: 
Ross McLaughlin
Head of Commercial Services 
The Helensburgh and Lomond Civic Centre
ross.mclaughlin@argyll-bute.gov.uk 
Appendix 
Appendix A – Climate Change Tracker – December 2022

Page 6

Appendix A – Climate Change Tracker – December 2022 
ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
W1 –Develop and Implement
Waste Strategy 
(L) Roads and
Amenity
Services,
Community,
commercial
customers
Implementation
of the Waste
Strategy
transitioning to
Landfill ban
compliant
Residual Waste
Recovery
solutions by
2025.
External funding and support
being sought from the Scottish
Government
A recently procured options
appraisal is now complete. The
options appraisal determines
the approach required by the
Council to move towards the
landfill ban in 2025
incorporating the Waste PPP
contract.  An Officer report is
available and will be discussed
at the ED&I committee in
December 2022.
W2 – Promote the Waste
Hierarchy through community
Education 
(L) Roads and
Amenity
Services
Evidence of
community
Education
Not secured New Web content and
Education materials for
Primary and Secondary Schools
were developed and delivered
to online Education
Environment Summit October
21 and the COP 26 Event on
the 6th November 21. 
W3 – Reduce Council use of
disposable and single use plastics
across all departments and
settings 
(L)
Procurement
and
Commercial
Services, all
Council
Services 
Adoption of new
working
practices and
procurement
No specific funding in place,
research required to impact on
operation costs 
A report on Single Use Plastic
went to the Policy and
Resources Committee on 9
December 2021, and the
following recommendations
were approved:
 Note and consider that

Page 7

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
the various Services
that currently purchase
SUP products consider
whether these products
are essential or if there
is a potential
alternative that would
meet the Service
requirements, prior to
orders being placed via
PECOS or contacting
the Procurement,
Commercial and
Contract Management
Team (PCCMT) for a
procurement process
to be carried out.
 Note and consider that
the Sustainable
Procurement Policy will
be updated to reflect
the Climate Change
Board desire to limit
SUP where possible –
proposed wording has
been included in the
current draft version
for 2022/23, and will be
updated as follows in

Page 8

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
the final version: “To
provide procurement
support to any strategic
decisions taken by the
Council in relation to
the usage of Single Use
Plastic products and
their recyclability.” 
 Note and consider that
the Commodity
Sourcing Strategy
templates used for
Regulated
Procurements be
updated to include a
question regarding SUP
Changes in legislation were
brought into force by the
Scottish Government on the
1st June 2022 restricting
single-use plastic cutlery,
plates, straws, drink stirrers
and balloon sticks, expanded
polystyrene food containers
and expanded polystyrene
cups and other beverage
containers, as well as all
products made of oxo-
degradable plastic.

Page 9

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Some products already
changed and others under
review. 
W4 – Extend and explore pre-
ordering for school food to reduce
food waste 
(L) Commercial
Services and 
Education 
Evidence of
extension of
pre-ordering &
food waste
reduction
Project funded and solution
procured
Project Team currently
implementing this, with full
project end date estimated as
March 2023. 
E1 – Deliver Renewable Sourcing
Strategy 2 
(L) Commercial
Services 
Adoption of
Strategy
RSS2 consultancy work funding
to be confirmed; expectation is
that project implementation
will be through combinations
of prudential borrowing
(subject to business case
approvals) and/or external
funding. 
RSS2 next stage development
work includes specification
development and preparation
of invitation to tender for
specialist consultancy
support. Current work in
progress; intended to be
market tested later in
financial year 2022/2023.
Whilst this larger
procurement exercise is
conducted, a Quick Quote
was developed in conjunction
with Procurement colleagues
to secure consultancy
support to assist with
immediate renewable
consultancy requirements
(including development of
items E2 and E3). This interim
contract has now expired but

Page 10

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
existing commissioned work-
streams will be concluded.
E2 – Delivery of Non-domestic
Energy Efficiency Framework
(NDEEF) Projects 
(L) Commercial
Services 
Evidence of
delivery of
projects
Project development work is
funded by combinations of the
Scottish Government and the
procured provider (costs
absorbed within the tender
process). 
Funding for project
implementation will come from
Council approved capital
allocations:
 Climate Change 20/21 -
£500K
 Climate Change 21/22 -
£600K
 Asset Sustainability –
circa £100K
NDEEF Energy Performance
Contract was signed on 16 July
2021 (circa £1.2m investment
with 10 year payback). The
original NDEEF mini project list
has either been installed or
deleted by variation.
Outstanding works are now
effectively those mini projects
introduced to the overall
project to replace deletions. 
Outstanding items are now
limited to a couple of solar pv
installations (including Kilmory
Castle ground array which
requires planning approval and
Blackhill Depot roof) and a full
site solution for Cardross PS
(including heating as a
mandated item and roof
mounted, solar pv).  Timelines
for this balance of works are
currently being agreed (all
expected within financial year
2022/2023)  The following
renewable solutions are
being/have been delivered

Page 11

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
within the NDEEF package to
augment existing solutions:
Solar PV: Kilmory Gardens,
Cardross PS, Blackhill Depot,
Rothesay Pool, GWIT Centre,
Lochgilphead RC, Kintyre
House. 
Air Source Heat Pump: Manse
Brae Roads Office,
Lochgilphead CEC, Strachur
Primary School, Lochgilphead
RC, Arrochar Primary School. 
In addition to the above, the
procurement sourcing strategy
for the next batch of sites,
using designation NDEEF2, is
under way.
E3 – Delivery of additional solar
installations at Council assets 
(L) Commercial
Services 
Evidence of
delivery of
projects
Consultancy work funding to
be confirmed; expectation is
that project implementation
will be through combinations
of prudential borrowing
(subject to business case
approvals) and/or external
funding.
Solar pv Options (initial
feasibility work completed for
circa 9 further sites) – some
opportunities absorbed within
NDEEF (Ref item E2) as project
replacements due to
accommodation reviews. A
‘mop up’ of remaining project
prospects intended to be
market tested as a component
within an upcoming solar pv

Page 12

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
maintenance contract later in
financial year 2022/2023.
E4 – Delivery of Water Efficiency
Audits across our Estate 
(L) Commercial
Services 
Evidence of
delivery of
projects
Feasibility work being absorbed
within existing approved
budgets. 
Individual works items are
generally small scale and it is
proposed to utilise existing
approved budgets where
possible.
Significant Council wide asset
verification exercise and
ensuring water use minimised. 
This project will continue into
early 2023 when a case study
will be prepared to
demonstrate the range of tasks
being undertaken and to
convey the reduction in water
consumption (with carbon
emissions reduction) and costs
arising from this already
successful project. 
E5– Delivery of Energy Efficiency
Scotland Programme 
(L) Housing
Services,
Registered
Social
Landlords 
Evidence of
delivery of
projects
Funding amounts are
determined by localised factors
and is paid as a  proportion of
the Scottish Governments’
Heat In Buildings Strategy 
Works which required
Contractors to enter
households were delayed by
continued Covid-19 restrictions
but were able to be replaced
by external measures ensuring
the programme continued. The
Scottish Government have
confirmed an award of
£2,011,323for the
2022/23Area Based Scheme.

Page 13

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
E6 – Complete LED streetlight
replacement programme 
(L) Roads and
Infrastructure
Services
Evidence of
delivery of
projects
Fully funded through
prudential borrowing
Contractors have now
commenced works  in the Lorn
Area to progress the last
installation phase of the
project and have a programme
of approx. 4-6 weeks to install
1100 new LED luminaires. The
Council has 14442 streetlights
in total so carbon emissions
have already been greatly
reduced by the LED Upgrade
Project.
2021/22 figures were CO2
totals 738 tonnes, this has
been reducing year on year,
back in 2015/16 figures were
CO2 Totals 3140 tonnes.
2022/23 emissions are forecast
to be reduced by approx. 10 –
15% on the 2021/22 figures. 
E7 – Continue support of ABRA
and review Renewable Energy
Strategy annually 
(L) Economic
Development
Evidence of
delivery of
projects 
Officer resource to support
currently funded
Work to support ABRA
ongoing.  Current ongoing
project by SSE Networks for
renewal of powerlines
between Inveraray and
Crossaig.  Ongoing discussions
with both transmission and
distribution teams.  Work
commenced on outline

Page 14

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
business case for progressing
Islay Energy System work
through the Rural Growth Deal. 
Islay announced as one of the
Carbon Neutral Islands being
progressed by the Scottish
Government which is expected
to complement this work. 
E8 – Continue support for offshore
development of renewables 
(L) Economic
Development
Evidence of
delivery of
projects
(expected late
2020s/early
2030s)
Officer resource to support
currently funded
Scottish Power Renewables
have secured an option on the
Islay site (Machair Wind)
through the Scotwind Leasing
Process. Consultation
commenced by SPR.
The Crown Estate Scotland
launched Innovation and
Targeted Oil and Gas (INTOG)
leasing in August 2022 which
could allow seabed rights for
small scale (less than 100MW)
innovation projects. 
T1 – Develop a Fleet Replacement
Strategy supportive of fuel
efficient, electric and hybrid
vehicles 
(L) Roads and
Infrastructure
Services
Adoption of
Strategy
Part for current financial year The Strategy is complete, final
review will take place to ensure
the 2025 legislative changes
are included.  The council have
introduced hybrid and electric
vehicles to the Fleet. The

Page 15

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
council operates 14% of its
Fleet with the new technology.
T2 – Develop a vehicle routing
system that will reduce road miles
for operations 
(L) Roads and
Infrastructure
Services
Evidence of
delivery of
projects
Part for current financial year  The Council went to tender
earlier this year for route
optimisation and had a number
of bidders. Officers have gone
through the selection process
and a preferred bidder has
been chosen and their bid is
within the budget available. 
They recently provided a
demonstration of their system
which was well received by our
tender evaluation panel.  
Arrangements are being made
with colleagues in
Procurement and IT to finalise
the necessary due diligence
then we will look to award the
contract.
T3 – Develop an electric vehicle
infrastructure strategy 
(L) Roads and
Infrastructure
Services
Evidence of
delivery of
projects 
Part for current financial year 
The development of the EV
network is funded by external
grant monies from Transport
Scotland, and the costs of
developing the strategy in
terms of staff time are covered
via existing budgets
Work on the strategy
document is now effectively
complete and we have a long
list of sites which will be
recommended to Committee
for formal adoption as well as
ancillary parts of the strategy
around maintenance,
procurement etc. A

Page 16

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Ultimately the cost recovery
model 
comprehensive year-end
report will go to EDI in
December summarising the
current position. The next key
stage is securing enough
external funding and/or
agreeing a delivery model –
self delivery supported by
business case, concession
model or leasing sites, or a
mixture of the three. A high
level analysis of possible
delivery options will also be
contained in the year-end
report. 
T4 – Support Digital by Default
theme Service Review & Recovery
Plan to reduce need to travel
All Council
Departments
Evidence of
delivery of
projects
Part for current financial year Council is adopting ‘Our
Modern Workspace’
programme and Digital First
approach as services change
and evolve post pandemic.  
T5 – Develop new active travel
plans for Council buildings and our
towns 
(L) Economic
Development
Evidence of
delivery of
projects
£2.9M external funding
secured development and
delivery of Active Travel in
current financial year.
No active travel funding is
provided by Council.  
External competitive challenge
funds are time consuming to
secure and projects have to be
The purpose of active travel is
to make it as easy as possible
and help to encourage
individuals, businesses and
visitors to choose to walk,
wheel or cycle for local
journeys.  Increasing activity
and reducing sedentary
behaviour has significant

Page 17

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
shaped to fit with external
funders’ aspirations and
requirements. However, at
present these are the only
available source(s) of potential
funding to deliver active travel
improvements.
health benefits and can
increase accessibility to
essential services, education,
employment, retail and
leisure.  Walking and cycling
are lower cost travel modes
and, if they are a viable option,
can help households reduce
their reliance on private cars,
particularly multiple car
households.
No Council funding is currently
expended on genuine Active
Travel work, with all costs,
including internal staff costs
(1.7FTE), having to be funded
via successfully securing
external challenge funds. As all
active travel work is currently
reliant on securing external
funding, therefore the projects
which are progressed are those
which can successfully secure
external challenge funding. 
Argyll and Bute Active Travel
Strategy: It is recommended
the Committee instruct
Officers to develop an Argyll
and Bute Active Travel Strategy

Page 18

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
and present it to full Council
for approval within 18 months
of Committee instruction.  The
Active Travel Strategy would
provide the overarching
context for the Council to
support and promote active
travel across the Council area.
Having an adopted and current
Active Travel Strategy is
increasingly becoming a pre-
requirement to access Scottish
Government derived active
travel funding. 
Active Travel Projects: The
majority of external funding
available is provided by the
Scottish Government via a
number of third sector
organisation who are paid to
administer these funds.  The
focus for Scottish Government
Active Travel funding is to
develop and deliver
infrastructure projects and
associated behaviour
change.  As such, the focus for
the very limited staff capacity
in the Active Travel Team has

Page 19

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
been to develop and deliver
infrastructure projects across
Argyll and Bute with a focus on
our main towns and locations
with strong community
support. 
Active Travel Plans for Towns:
There are Active Travel Plans in
place for the main towns in
Argyll and Bute, albeit some
are now quite historic.  The
town Active Travel Plans focus
on identifying potential active
travel route networks for key
towns.  These provide a
framework for the
development of new active
travel routes, which will enable
and encourage residents,
businesses and visitors to
choose to travel more
actively.  No funding is
currently secured to enable the
Active Travel Plans for towns to
be updated. 
Council Staff Travel Plan: At
present it is not proposed to
progress with development of

Page 20

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
a Council Staff Travel Plan.  This
is due to (a) requirement to
make best use of limited
internal staff capacity; and, (b)
the ongoing uncertainty of
longer-term staff profiles and
bases.  Staff Travel Plans focus
on measures to make it easier
and preferable for staff to
choose to walk, cycle, use
public transport or car share to
commute to work or for work
journeys, or use economical
pool vehicles for work
journeys.   A travel plan should
encourage staff to choose the
most economical and least
environmentally damaging
travel mode.  Engagement will
be required with services
which manage staff in buildings
and/or council buildings as this
is essential to creating
deliverable and effective travel
plans for staff.  This includes
Estates, HR, SMT and building
users.  It is recommended that
work on the Council Staff
Travel Plan is commenced after
a decision has been made on

Page 21

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
future staff working patterns
and office rationalisation as
these will have a significant
impact on the Council Staff and
their travel.  There is currently
no funding secured to enable
this work to be progressed.   
PA1 – Review Council Flooding &
Coastal Protection Policy 
(L) Roads and
Infrastructure
Services
Review of policy No specific funding in place,
research required to impact on
operation costs
Reviews are in process. 
PA2 – Review Council Sustainable
Procurement Policy 
(L)
Procurement 
Review of policy  No specific funding in place,
research required to impact on
operation costs
This policy is reviewed on an
annual basis. 
OFF1 – Develop opportunities for
Carbon Offsetting with ACT and
partners 
(L) Climate
Change Board,
ACT and
partners
Delivery of
projects 
Limited funding via ACT for
existing projects
SSEN compensatory planting –
Phase 1 complete, Phase 2
scheduled with further
planting planned at Dunbeg
under the agreement.   This
partnership project between
ACT – Argyll and Bute Council
and SSEN has been shortlisted
for three national awards, to
be announced Nov/Dec ’22. 
ACT have entered agreement
with Mastercard’s Priceless
Planet Coalition to plant

Page 22

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
100,000 native trees in Argyll
over the coming 5 years.  Sites
currently being agreed. There
are carbon credit
opportunities for site owners. 
ACT are working with CPPs
Climate Change Working
Group to secure funding for a
2-year Climate Change Officer
hosted within ACT. 
ACT have secured support
from ScotGov’s Peatland
Action and Esmee Fairbairn
Foundation to continue
peatland restoration on Islay,
Jura and activity extend into
Kintyre.  CANN project now
concluded – major outputs 2
Conservation Action Plans for
protected sites produced, and
586 hectares of peat restored
to favourable status, and
invasive non-native plants
removed from a further 687 ha
of peatland. 
ACTNow project officer has
delivered Carbon Literacy

Page 23

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Training to A&BC Elected
Members and Senior Council
Officers. 
ACT has a submitted bid to the
Community Led Local
Development Fund to procure
community engagement
resources to support a regional
natural capital strategy. 
ACT working with NatureScot,
Forest and Land Scotland and
private landowners in Knapdale
area to improve and extend
Rainforest in Knapdale area. 
Development bid has been
submitted to Nature
Restoration fund. 
COMM1- Develop and deliver
Communications Plan to support
Decarbonisation Plan 
(L) Climate
Change Board
and
Communicatio
ns Team
Delivery of
Communications
Plan
Part of Communications
Support 
External communications
We continue to promote
actions the council is taking,
and actions that others can
take, to develop climate-
friendly Argyll and Bute. For
example:
 Promoting Scottish
Climate Week

Page 24

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
- Islay one of six
Scottish islands to
become fully
carbon neutral by
2040
- Carbon literacy
training programme
- Council has reduced
heating oil
consumption by
70%
- Port Ellen Primary
project on impact of
clothes waste on
planet
 Street lighting works to
reduce carbon
emissions
 Promotion of Climate
Change Officer vacancy  
 Council cut carbon
emissions for fourth
year in a row
 Cost of living support –
business growth and
climate friendly
communities to benefit
from £4.5M investment
plan

Page 25

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
 Cascade article to
promote Scottish
Climate Week to staff
 Native woodland
project -
Council/ACT/SSEN
nominated for 3
national awards
 Active travel – footpath
improvement works 
 Eco flag awards for
schools
 Hermitage Park
awarded green flag
status
 Promotion of Home
Energy Efficiency
Project (HEEPS)
 Cascade article to
promote energy saving
tips 
COMM2 - Engage with community
and partners and deliver Climate
Change Directory for our region 
(L) Community
Planning and
Development
Team
Delivery of
engagement
map 
In place until end of financial
year
Web page is active and live 
https://www.argyll-
bute.gov.uk/cpp-climate-
change   with climate change
funding search updated every
two months.

Page 26

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Community Groups and
initiatives mapped and
promoted on website. Input
to, support for and reporting
back from the Community
Planning Partnership Climate
Change Group.
Regular update of webpage
directory.  Ongoing dialogue
with Community Planning
Partnership.
2 x Meetings have taken place
with Argyll and Bute Branch of
National Farmers Union (NFU)
and workshop currently being
scoped out to explore Climate
Change opportunists across
the Agricultural and Land Use
Sector.  Headline topics likely
to include: - Sustainable
Upland Farming, Planting for
Carbon Sequestration, Dairy
Industry and Suckling Beef.  
COMM3 - Monitor the delivery of
actions in the Climate Change
Action Plan and review in 2024
(L) Climate
Change Board 
Review of this
plan by
December 2024 
Monitored through Tracker to
be submitted quarterly to
Policy & Resources Committee. 
Completed – next review Dec
2024