ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 16 FEBRUARY 2023
FINANCIAL REPORTS MONITORING PACK – 31 DECEMBER 2022  
1. INTRODUCTION 
1.1 This report provides a summary of the financial monitoring reports as at the end of
December 2022. There are five detailed reports, setting out the position as at 31
December 2022,  which are summarised in this Executive Summary: 
• Revenue Budget Monitoring Report 
• Monitoring of Financial Risks 
• Capital Plan Monitoring Report 
• Treasury Monitoring Report 
• Reserves and Balances 
2. DETAIL 
2.1 Revenue Budget Monitoring Report 
2.1.1 This report provides a summary of the current revenue budget monitoring position to
ensure net expenditure is contained within budget.  It provides corporate and
departmental information with comparisons on a forecast outturn and a year to date
basis. 
2.1.2  There is a forecast underspend of £3.408m as at the end of December 2022.  The
key variances are: 
- £3.666m underspend in central budgets with the largest variances relating to
a one-off treasury gain of £5.398m due to receiving a discount on the early
repayment of PWLB loans and £1.491m recognised in relation to the net
expected funding shortfall from the 2022-23 pay award.  Note that the
£1.491m will be attributed to the relevant services, as opposed to sitting in the
centre as it currently does, when the pay awards are finalized. There are
further numerous other variances within this service area, including
overspends within Elected Members due to the pay award and within utilities
and insurances due to price pressures.  There are underspends from the joint
boards, unfunded pensions and NDR budgets where payments out are lower
than available budget.
- £0.740m overspend due to an under-recovery of income in Piers and
Harbours, an overspend in Waste employee costs due to sickness absence
cover, landfill tax increases and a back-payment for an increased tonnage
rate for Waste Disposal from one of our suppliers. These are partially offset
with additional income in Crematoria, Commercial Waste, Building Control
and Private Water Supply Appraisals plus an underspend in Directorate due
to budget no longer needed.
- £0.597m underspend is due to underspends in employee budgets which are
not included within the Scheme of Devolved School Management, partially

Page 2

offset by an overspend within the Residential School Budget and Home and
Hospital Tuition.
- £0.253m overspend due to a high demand for services and use of agency
staff within Social Work 
- £0.138m over-recovery of Council Tax 
2.1.3  The forecast overspend includes the projected impact of the 2022-23 pay settlement: 
- The Scottish Government agreed to provide an additional £140m of recurring
resource from 2022-23 to support the settlement and a further £120.6m of
capital funding in 2022-23 and 2023-24 which will be baselined as General
Revenue Grant from 2024-25 onwards.  It was agreed at Policy and
Resources on 8 December 2022 that a proportionate share of the funding is
transferred over to the Health and Social Care Partnership (HSCP) and these
budget adjustments have been processed.    
- The Teachers and Chief Officers pay awards are still under negotiation.
- There remains a budget pressure that both the Council and the HSCP will
require to fund.  The estimated gap for the Council is £1.491m and the HSCP
£0.334m.  The Council gap is calculated with the assumption that the
Teachers and Chief Officers pay award is on the same basis as the SJC pay
award so could be subject to change if negotiations result in an increased
amount.  
- The projected impact of £1.491m for the Council has been included in the
forecast outturn reported at 31 December 2022. 
2.1.4 There is a year to date underspend of £6.806m.  More focus is on the forecast
outturn position, hence why sometimes the year to date position is not updated.  The
year to date variances mainly relate to the timing of income and expenditure and
recharging of costs to capital. 
2.1.5 With regard to the ongoing financial impact of COVID-19, there are £8.965m of
reserves committed to manage the impact of the pandemic. The detail behind these
commitments is contained within Appendix 2 of the Reserves and Balances report.   
2.1.6 Total policy savings relevant to 2022-23 financial year amount to £1.560m.  The
table below outlines their progress as at 31 December 2022.   
Category No. of
Options
2022-23
£000
2022-
23
FTE
2023-24
£000
2023-
24
FTE
Future
Years
£000
Future
Years
FTE
Delivered 10 367.0 1.4 375.0 1.4 375.0 1.4
On Track to be Delivered 6 350.0 0.5 353.0 0.5 356.0 0.5
Still to be Implemented 1 0.5 0.0 0.5 0.0 0.5 0.0
Being Developed 0 0.0 0.0 0.0 0.0 0.0 0.0
Potential Shortfall 6 818.2 0.0 937.8 0.0 937.8 0.0
Delayed 1 24.0 0.0 24.0 0.0 24.0 0.0
TOTAL 24 1,559.7 1.9 1,690.3 1.9 1,693.3 1.9

Page 3

2.1.7 For those savings approved prior to February 2022, there are six savings
categorised as having a shortfall and one currently delayed.   
Health and Social Care Partnership (HSCP) – Financial Update 
2.1.8 The forecast outturn position at the end of December is an estimated overspend of
£0.598m for 2022-23 (£0.253m for Social Work and £0.345m for Health).  The Chief
Financial Officer of the IJB is confident that the spend will be brought in line with
budget by the end of the financial year using slippage from growth projects and
anticipated additional funding allocations. 
2.2 Monitoring of Financial Risks 
2.2.1  This report outlines the process and approach developed in carrying out a financial
risks analysis and provides an update on the current assessment of financial risks.   
2.2.2 There are 5 Council wide revenue risks identified for 2022-23 currently amounting to
£2.290m.   
2.2.3 There are currently 41 departmental risks totalling £4.935m.  Of the 41 departmental
risks, one is categorised as almost certain and 4 are categorised as likely.  These
will continue to be monitored and action taken to mitigate or manage these risks.   
2.2.4 The top three risks in terms of the financial impact are noted in the table below. 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Roads and
Infrastructure
Services
Roads
Maintenance -
Bridges, Culverts
& Sea Defences
Extreme localised weather may
result in loss of bridge, culvert, road
or sea defence.
3 750
Roads and
Infrastructure
Services
Roads Materials -
Bitumen
Increased cost of asphalt material
due to price of crude oil rising. 
Discussions emerging from the
industry about possible rationing of
bitumen which, if applied, will
affect our programmes due to
availability
3 400
Roads and
Infrastructure
Services
Winter
Maintenance
Adverse weather conditions which
require greater than budgeted
number of gritting runs.
3 365 
2.2.5 There has been 1 change to the departmental risks since the report as presented to
the Policy and Resources Committee on 8 December 2022.  These are outlined in
paragraph 3.4.1 of the Financial Risks Report.

Page 4

2.3 Capital Plan Monitoring Report 
2.3.1 This report provides a summary of the current capital plan monitoring position. 
Information is provided in terms of monitoring year to date budget, current full year
budget, future years total budget and funding and non-financial in terms of project
performance. 
2.3.2 
2.3.3
At the budget setting meeting on 25 February 2021, the Council agreed to provide a
£2.5m provision for the increase in capital contract costs as a result of COVID-19
and following agreement at the Policy and Resources Committee on 14 October
2021, this, plus a further £0.146m, was added to the capital programme. At the
budget meeting in February 2022 an additional £3.9m was set aside for further
capital contract increases including up to £1.2m for Campbeltown Flood Scheme. 
There are likely to be further financial pressures facing the capital programme that
are not able to be quantified at this stage largely relating to inflationary increases in
the construction industry and supply chain issues. 
2.3.4 Actual net expenditure to date is £19.846m compared to a budget for the year to
date of £19.186m giving rise to an overspend for the year to date of £0.660m
(3.44%).  
2.3.5 The forecast outturn for 2022-23 is a forecast net expenditure of £33.440m
compared to an annual budget of £39.014m giving rise to a forecast underspend for
the year of £5.574m (14.29%). 
2.3.6 The forecast total net projects costs on the capital plan are £180.736m compared to
a total budget for all projects of £180.009m giving rise to a forecast overspend for
the overall capital plan of £0.727m (0.40%).  
2.3.7 In respect of total project performance, there are 162 projects within the capital plan,
140 are complete or on target, 8 are off target and recoverable and 14 projects are
off track.  
2.4 Treasury Monitoring Report 
2.4.1 This report provides information on the current levels and recent transactions in
relation to the capital financing limit, total borrowing, temporary borrowing and long
term borrowing and investments.   
2.4.2 The net movement in external borrowing for the period 1 November 2022 to 31
December 2022 was a decrease of £9.98m. 
2.4.3 Borrowing is below the Capital Financing Requirement for the period to 31
December 2022. This is due to the repayment of long term PWLB borrowing earlier
in the year offset by the need to take temporary borrowing for cash flow purposes. 
2.4.4 The levels of investments were £99.1m at 31 December 2022. The average rate of
return achieved was 2.869% which is below the target SONIA (Sterling Overnight
Index Average) rate for the same period of 3.202%.

Page 5

2.5 Reserves and Balances 
2.5.1 This report summarises the overall level of reserves and balances and monitors the
spending of the earmarked reserves, providing detailed information on the unspent
budget earmarked balances.   
2.5.2 The Council has a total of £394.480m unusable reserves that are not backed with
resources.  They are required purely for accounting purposes. 
2.5.3 At 31 March 2022, the Council had a total of £103.183m of usable reserves.  Of this: 
• £2.682m relates to the Repairs and Renewals Fund
• £4.414m relates to Capital Funds
• £96.087m was held in the General Fund, with £88.990m of this balance
earmarked for specific purposes. 
2.5.4  Of the earmarked balance of £88.990m:
• £43.882m is invested or committed for major initiatives/capital projects
• £10.605m has already been drawn down
• £8.580m is still to be drawn down in 2022-23
• £25.370m is planned to be spent in future years
• £0.553m has been released back to the general fund 
2.5.5 The table below summarises the position of the unallocated General Fund balance
taking into consideration the points noted above.
Heading Detail £000
Unallocated General Fund
as at 31 March 2022
This is the balance that is
unallocated over and above the 2%
contingency, which amounts to
£5.256m
1,841
Budgeted allocation to
General Fund for 2022-23
Budget
Per the Budget Motion at Council on
24 February 2022
2,482
Earmarked Balances no
longer required
Per paragraphs 3.3.3 to 3.3.5 –
amounts previously earmarked that
can be released back to the general
fund
553
Current Forecast Outturn
for 2022-23 as at 31
December 2022
Note, this includes an overspend of
£0.253m against Social Work 
3,408

Page 6

Social Work outturn
adjustment
Per paragraph 3.4.2 - Social Work
hold reserves so would be expected
to cover their overspend
253
Estimated Unallocated
balance as at 31 March
2023 
8,537 
2.5.6  It can be seen that, after taking into consideration the Budget Motion, the current
forecast outturn for 2022-23, the balances no longer required and the expected
adjustment in relation to the Social Work outturn, the Council is forecast to have a
£8.537m surplus over contingency.   
2.6 VIREMENTS OVER £0.200m (Revenue) 
2.6.1 Virement is the process of transferring budget between cost centres, services or
departments or between capital projects.  The Council’s constitution notes that
virements over £0.200m require approval by Council.  This section of the report will
be used to outline revenue virements in the period that require approval.   Capital
virements are included within the capital monitoring report. 
2.6.2 For the periods November and December, there are 3 virements requiring
authorisation: 
- 0.216m reallocation of carers budgets within Social Work
- 0.358m between Roads and Infrastructure and Other Operating Income and
expenditure to correct a coding error in piers and harbours inflation
- 0.417m recognised within Social Work for the increased costs of the pay
award 
3.  RECOMMENDATIONS 
3.1 It is recommended that the Policy and Resources Committee: 
a) Consider the revenue budget monitoring report as at 31 December 2022 
b) Note the financial risks for 2022-23 
c) Note the capital plan monitoring report as at 31 December 2022 and approve the
proposed changes to the capital plan outlined in Appendix 4 of that report. 
d) Note the treasury monitoring report as at 31 December 2022 
e) Consider the reserves and balances report as at 31 December 2022  
f) Recommend to Council that the revenue virements over £0.200m during
November and December 2022 are approved

Page 7

4. IMPLICATIONS 
4.1 Policy – None.
4.2 Financial -  Outlines the revenue and capital monitoring for
2022-23 as at 31 December 2022
4.3 Legal -  None.
4.4 HR -  None.
4.5 Fairer Scotland Duty -   None.
4.5.1 Equalities – protected
characteristics - 
None.
4.5.2 Socio-economic Duty -  None.
4.5.3 Islands -  None.
4.6 Climate Change - None.
4.7 Risk -  Risks are included in financial risks report. 
4.8 Customer Service -  None. 
Kirsty Flanagan
Executive Director /Section 95 Officer
13 January 2023 
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 8

REVENUE BUDGET MONITORING REPORT AS AT 31 DECEMBER 2022 POLICY AND RESOURCES COMMITTEE
16 FEBRUARY 2022 
2022-23 Overall Position:
There is an overall forecast underspend of £3.408m as at the end of December 2022.  Central Budgets are projecting a £3.666m underspend
with the largest variances relating to a treasury gain of £5.398m due to receiving a discount on the early repayment of three PWLB loans
offset by £1.491m recognised in relation to the net expected shortfall in funding from the 2022-23 pay award.  Note that the £1.491m will be
attributed to the relevant services, as opposed to sitting in the centre as it currently does, when the pay awards are finalised.  There are
further numerous offsetting variances, including overspends within Elected Members due to the pay award and within utilities and insurances
due to price pressures and underspends from the Joint Boards, Unfunded Pensions and NDR budgets where payments out are lower than
available budget.  Within Executive Director Kirsty Flanagan, there is a forecast overspend of £0.740m due to an under-recovery of income in
Piers and Harbours, an overspend in Waste employee costs due to sickness absence cover, landfill tax increases and a back-payment for an
increased tonnage rate for Waste Disposal from one of our suppliers. These are partially offset with additional income in Crematoria,
Commercial Waste, Building Control and Private Water Supply Appraisals plus an underspend in Directorate due to budget no longer needed.
Within Social Work, there is a forecast overspend of £0.253m due to a high demand for services and agency staff costs.    Within Executive
Director Douglas Hendry, there is a forecast underspend of £0.597m, this is due to underspends in employee budgets which are not included
within the Scheme of Devolved School Management, partially offset by an overspend within the Residential School Budget and Home and
Hospital Tuition. There is a projected over-recovery of Council tax of £0.138m 
There is a year to date underspend of £6.806m.  The year to date variances within the departments tend to relate to the timing of income and
expenditure and costs to capital not recharged yet. 
Key Highlights as at December 2022:  
• There has been a one-off treasury gain that was achieved in October by repaying some PWLB loans early to take advantage of a
discount in the repayment.  There was a short window of opportunity for these transactions brought about by the volatility at
Westminster which affected the interest rates.
• The expected total shortfall of all pay awards has been built into the projection for December (£1.491m). 
Key Financial Successes:
Performance against budget for 2021-22 was an overall net favourable position of £1.630m underspend after adjusting for year-end
earmarking.  This breaks down as: 
• £0.815m net underspend in relation to Council service departmental expenditure
• £0.432m net overspend in relation to other central costs
• £1.247m over-recovery of Council Tax income.

Page 9

Key Financial Challenges: Proposed Actions to address Financial Challenges:
Ongoing consideration of the financial impact of COVID on the Council’s
revenue position. 
Continue to identify additional costs as a consequence of COVID to
ensure earmarked COVID funds are applied appropriately. 
Achieving a favourable year-end position and achieving savings targets
in light of council wide risks to expenditure. 
Robust monitoring of the financial position and delivery of savings to
ensure budget issues inform the budget monitoring process.
Monitoring Social Work expenditure and more widely the IJB position as
any overspend will transfer back to partner bodies in the first instance.  
Continue to work closely with the CFO of the IJB to ensure that early
indication of any potential adverse financial outturn is known and
corrective action is agreed as appropriate to reduce the risk to the
Council. 
Identifying further savings and delivering services more efficiently with
less resources, as whilst a balanced 2022-23 budget was agreed in
February 2022 there are still budget gaps in future years.
The Council will continue to progress savings options identified in
2021-22 that require further development and seek to identify further
savings through themed reviews and business process reviews.
Maintaining or improving the level of service income recovered, for
example planning, building standards and car parking.  
Actively monitor income recovery and ensure Council fees and
charges policies are regularly reviewed. 
Managing spend in service areas which are demand led and, to some
extent, outwith service control, for example Winter Maintenance. 
Use risk based approach to budget monitoring to focus additional
attention on these areas.
Ongoing requirement to fund unavoidable inflationary increases in areas
like utility costs, fuel, food etc. This is impacted further by the availability
of supply as a result of the COVID-19 pandemic, UK exit from the
European Union, Russia’s invasion of Ukraine and sanctions on Russian
owned entities to name a few influencing factors.
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be reported through the budget monitoring
and preparation processes. 
Cost of living crisis impacting on pay inflation negotiations which could
result in pay awards above what is deemed affordable.
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be reported through the budget monitoring
and preparation processes.

Page 10

Forecast Outturn Position
There is a forecast overspend of £0.499m for 2022-23 as at the end of December 2022
Department
Annual
Budget   
£'000
Forecast
Outturn   
£'000
Current
Forecast
Variance
£'000
Previous
Forecast
Variance
£000
Change
£000 Explanation
Chief Executive's Unit 7,652 7,652 0 0 0
Executive Director (Douglas Hendry) 128,603 128,006 597 597 0
Underspend is due to underspends in employee budgets which are not included
within the Scheme of Devolved School Management, partially offset by an
overspend within the Residential School Budget and Home and Hospital Tuition.
Executive Director (Kirsty Flanagan) 48,922 49,662 (740) (302) (438)
Overspend due to an under-recovery of income in Piers and Harbours, an
overspend in Waste employee costs due to sickness absence cover, landfill tax
increases and a back-payment for an increased tonnage rate for Waste Disposal
from one of our suppliers. These are partially offset with additional income in
Crematoria, Commercial Waste, Building Control and Private Water Supply
Appraisals plus an underspend in Directorate due to budget no longer needed.
Social Work 73,823 74,076 (253) (253) 0 Overspend due to high demand for services and agency staff costs.
Central Budgets 23,709 20,043 3,666 (26) 3,692
There is a large one-off Loans Fund gain due to early repayment of loans
resulting in a discount in the repayment and other smaller underspends against
joint boards, unfunded pensions and NDR budgets where payments out are
lower than available budget.  There are overspends due to the projected
Teachers and Chief Officers pay awards yet to be decided, Elected Members
pay award being higher than the available budget and also from utilities and
insurances due to price pressures. 
Financed By (282,709) (282,847) 138 493 (355) Projected over-recovery of Council tax has been reduced due to recent recovery
levels being lower than expected
Total 0 (3,408) 3,408 509 2,899

Page 11

Further information on the departmental forecast variances is included later on in the report. 
(1,000)
(500)
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
April
May
June
July
August
September
October
November
December
January
February
£ 000
Forecast outturn position for each Department from the start of the financial year
Chief Executive's Unit
Executive Director (Kirsty Flanagan)
Executive Director (Douglas Hendry)
Social Work
Central Budgets
Financed By
Underspend
Overspend

Page 12

Year to Date Position
The year to date position as at the end of December 2022 is an underspend of £6.806m and the main variances are noted below. 
Department
YTD
Actual
£'000
YTD
Budget
£'000
YTD
Variance   
£'000
Explanation
Chief Executive's Unit 6,392 6,391 (1) The YTD overspend can be attributed to profiling issues
Executive Director (Douglas Hendry) 88,063 88,574 511 The YTD underspend position is mainly due to underspends in employee budgets.
The underspends in school and learning centre employee budgets fall within the
Scheme of Devolved School Management in schools which are permitted flexibility
at the end of the year so no forecast variance for this part of the underspend is
required. The remaining variances are mainly profile related and will be refined
through January.
Executive Director (Kirsty Flanagan) 37,757 34,340 (3,417) The YTD overspend is mainly due to income being behind profile in the Roads
Operational Holding Account due to Capital project timing which is difficult to
profile and the under-recovery of income in Piers and Harbours
Social Work 42,538 43,839 1,301 The YTD underspend can be attributed to timings of payments and profiling issues
and demand for purchased Children's Services. This is partially offset by high
demand for services across Adult Services and staffing
pressures, including the use of agency staff, across Homecare and Older People
Residential Units
Central Budgets (67) 8,345 8,412 The YTD underspend can be attributed to timings of payments and profiling issues. 
A large proption of the YTD can be attributed to the one-off Loans Fund gain
resulting from early repayment of loans £5.398m
Funding (186,801) (186,801) 0
Total Net Expenditure (12,118) (5,312) 6,806

Page 13

Further information on the departmental year to date variances is included later on in the report. 
-25%
0%
25%
50%
75%
100%
Chief
Executive's
Unit
Executive
Director
(Kirsty
Flanagan)
Executive
Director
(Douglas
Hendry)
Social W
ork
Central
Budgets
TOTAL
Expenditure to date against the remaining budget for each
Department
YTD Actual Remaining Budget

Page 14

OBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 DECEMBER 2022
YTD
Actual
YTD
Budget
YTD
Variance
Variance Annual Budget Forecast
Outturn
Forecast
Variance
Variance
£'000 £'000 £'000 % £'000 £'000 £'000 %
Departmental Budgets
Chief Executive's Unit 6,392 6,391 (1) (0.0%) 7,652 7,652 0 0.0%
Executive Director (Kirsty Flanagan) 37,757 34,340 (3,417) (10.0%) 48,922 49,662 (740) (1.5%)
Executive Director (Douglas Hendry) 88,063 88,574 511 0.6% 128,603 128,006 597 0.5%
Social Work 42,538 43,839 1,301 3.0% 73,823 74,076 (253) (0.3%)
Total Departmental Budgets 174,750 173,144 (1,606) (0.9%) 259,000 259,396 (396) (0.2%)
Central Budgets
Other Operating Income and Expenditure (1,364) 1,093 2,457 224.8% 2,248 4,202 (1,954) (86.9%)
Joint Boards 940 1,122 182 16.2% 1,496 1,325 171 11.4%
Non-Controllable Costs 357 6,130 5,773 94.2% 19,965 14,516 5,449 27.3%
Total Central Budgets (67) 8,345 8,412 100.8% 23,709 20,043 3,666 15.5%
TOTAL NET EXPENDITURE 174,683 181,489 6,806 3.8% 282,709 279,439 3,270 1.2%
Financed By
Aggregate External Finance (140,228) (140,228) 0 0.0% (219,325) (219,325) 0 0.0%
Local Tax Requirement (46,573) (46,573) 0 0.0% (55,262) (55,400) 138 (0.3%)
Contributions to General Fund 0 0 0 0.0% 2,482 2,482 0 0.0%
Earmarked Reserves 0 0 0 0.0% (10,604) (10,604) 0 0.0%
Total Funding (186,801) (186,801) 0 0.0% (282,709) (282,847) 138 (0.1%)
(Deficit)/Surplus for Period (12,118) (5,312) 6,806 0 (3,408) 3,408
CURRENT PROJECTED FINAL OUTTURNYEAR TO DATE POSITION

Page 15

SUBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 DECEMBER 2022
YTD
Actual
YTD
Budget
YTD
Variance
Variance Annual
Budget
Forecast
Outturn
Forecast
Variance
Variance
£'000 £'000 £'000 % £'000 £'000 £'000 %
Subjective Category
Employee Expenses 122,672 124,395 1,723 1.4% 177,744 179,795 (2,051) (1.2%)
Premises Related Expenditure 12,120 11,660 (460) (4.0%) 16,867 17,365 (498) (3.0%)
Supplies and Services 19,617 18,610 (1,007) (5.4%) 25,061 25,469 (408) (1.6%)
Transport Related Expenditure 10,050 8,957 (1,093) (12.2%) 17,317 17,495 (178) (1.0%)
Third Party Payments 117,938 117,457 (481) (0.4%) 171,200 171,720 (520) (0.3%)
Capital Financing 3,336 0 (3,336) 14,039 14,039 0 0.0%
TOTAL EXPENDITURE 285,733 281,079 (4,654) (1.7%) 422,228 425,883 (3,655) (0.9%)
Income (297,851) (286,391) 11,460 (4.0%) (422,228) (429,291) 7,063 (1.7%)
(Deficit)/Surplus for Period (12,118) (5,312) 6,806 0 (3,408) 3,408
YEAR TO DATE POSITION CURRENT PROJECTED FINAL OUTTURN
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less than budget.

Page 16

CHIEF EXECUTIVE’S UNIT – AS AT 31 DECEMBER 2022 
The department is currently forecasting spend in line with budget. 
The department has a year to date overspend of £0.001m. 
Forecast Outturn Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Chief Executive 959 959 0 0 0
Head of Financial Services 6,693 6,693 0 0 0
Totals 7,652 7,652 0 0 0
Year to Date Position 
0%
25%
50%
75%
100%
Chief Executive Head of Financial Services
Expenditure to date against the remaining budget for each
Service
YTD… Remaining Budget…
Key Financial Successes:
 All savings options have been delivered.  
 The department’s 2021-22 outturn position was an underspend of £0.018m.  This resulted from an overall underspend of £2.013m
offset by earmarking of £1.769m due to auto-carry forwards including unspent grants and COVID-19 funding and £0.226m of unspent
budget earmarkings. 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
To continue to deliver a high quality support service function during a time
of substantial uncertainty and challenge arising from continuing reductions
in funding whilst costs are increasing due to high inflation and service
demand caused by world events including the COVID-19 pandemic and
the conflict in Ukraine.
Ensure the team is operating as efficiently and effectively as
possible to enable continued support to departments with reduced
resources by building resilience through knowledge sharing across
the team and maximising the benefits to the service from the
implementation of the Oracle Fusion Financial Ledger System.

Page 17

Carry out a business process review of the Revenues and Benefits
function to determine if there is scope to deliver the service in a more
cost effective manner. 
Work collaboratively with other services of the Council to identify
opportunities to improve the operational and financial efficiency of
services and to support evidence based decision making.

Page 18

CHIEF EXECUTIVE’S UNIT – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2022 
Service Area YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Chief Executive 266 264 (2) (0.8%) 387 387 0 0.0% Outwith Reporting Criteria
Community Planning
& Development 354 372 18 4.8% 572 572 0 0.0% Outwith Reporting Criteria  
620 636 16 2.5% 959 959 0 0.0%  
Accounting &
Budgeting 1,860 1,866 6 0.3% 2,493 2,493 0 0.0% Outwith Reporting Criteria
Internal Audit & Fraud 213 216 3 1.4% 228 228 0 0.0% Outwith Reporting Criteria
Revenues & Benefits 2,015 2,063 48 2.3% 2,248 2,248 0 0.0% Outwith Reporting Criteria
Scottish Welfare Fund 1,684 1,610 (74) (4.6%) 1,724 1,724 0 0.0%
LACER Fund overspent, correction journal to
be processed due to mis-codings and
earmarked reserves to be drawn down.  
5,772 5,755 (17) (0.3%) 6,693 6,693 0 0.0%    
6,392 6,391 (1) (0.0%) 7,652 7,652 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 19

CHIEF EXECUTIVE’S UNIT – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2022 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 3,907 3,864 (43) (1.1%) 5,482 5,482 0 0.0% Outwith Reporting Criteria
Premises 0 0 0 0.0% 0 0 0 0.0% Outwith Reporting Criteria
Supplies and
Services 310 334 24 7.2% 678 678 0 0.0% Outwith Reporting Criteria
Transport 9 24 15 62.5% 32 32 0 0.0% Underspend on staff travel budgets.
Third Party 15,766 18,448 2,682 14.5% 26,326 26,326 0 0.0%
An underspend of £2.755m on Housing benefits
(offset against income) offset by numerous
accumulating variances coming to an overspend
of £0.073m
Income (13,600) (16,279) (2,679) 16.5% (24,866) (24,866) 0 0.0%
An overspend of £2.750m on Housing Benefits
(offset against third party payments) offset by
numerous accumulating variances coming to an
underspend of £0.071m
Totals 6,392 6,391 (1) (0.0%) 7,652 7,652 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 20

CHIEF EXECUTIVE’S UNIT – RED VARIANCES AS AT 31 DECEMBER 2022
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation      
0 0.0%   
A red variance is a forecast variance which is greater than +/- £50,000.

Page 21

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – AS AT 31 DECEMBER 2022 
The department is currently forecasting an underspend of £0.597m (0.5%) for the year.  This is due to underspends in employee budgets
which are not included within the Scheme of Devolved School Management, partially offset by an overspend within the Residential School
Budget and Home and Hospital Tuition.  
The department has a year to date (YTD) underspend of £0.511m (0.6%). The year to date underspend position is mainly due to underspends
in employee budgets. The underspends in school and learning centre employee budgets fall within the Scheme of Devolved School
Management in schools which are permitted flexibility at the end of the year so no forecast variance for this part of the underspend is required.               
The remaining variances are mainly profile related and will be refined through January.                              
Forecast Outturn Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Executive Director
(Douglas Hendry) 443 443 0 0 0
Head of Commercial
Services 10,258 10,258 0 0 0
Head of Education 98,725 98,128 597 597 0
Head of Legal and
Regulatory Support 19,177 19,177 0 0 0
Totals 128,603 128,006 597 597 0
Year to Date Position 
Key Financial Successes:
The 2021-22 year-end consolidated outturn position was an under spend of £0.223m after adjusting for earmarkings. This was due to the
effective contract management of NPDO and Hub School contracts, including a lower than expected insurance premium as a result of the
annual renegotiation of insurance costs. The costs of COVID were contained and minimised where possible across departments, with staff
0%
25%
50%
75%
100%
Executive Director
(Douglas Hendry)
Head of Commercial
Services
Head of Education Head of Legal and
Regulatory Support
Expenditure to date against the remaining budget for each
Service
YTD… Remaining Budget…

Page 22

from all areas of the service assisting in planning, implementing and delivering a wide range of additional services in schools and communities
and helping businesses through the return from lockdown.
Key Financial Challenges: Proposed Actions to address Financial Challenges:
The ongoing impact of COVID-19 Costs are being contained where possible. 
Impact of numbers/uptake in demand led service areas like catering,
design services and licensing.
Continually refine/develop systems to accurately calculate forecast
outturns and the impact on the future financial outlook.
Manage the impact of the Statutory Guidance supporting Nutritional
Requirements for Food and Drink in Schools (Scotland) Regulations
2020, on the cost of producing school meals and also the uptake.
Monitor and report on the impact on costs and on income as the
year progresses.
Support longer term service re-design project for Catering and Cleaning
services to ensure efficiencies and financial savings are secured for the
Council as well as delivery of free school meals for 1140 hours of Early
Learning and Childcare and the phased universal free school meals
expansion in Primary Schools. 
Effective working with partners and support with implementation of
service delivery method. Continual monitoring and review of
budgets.
Legislative/policy requirements not fully funded by Scottish Government
which may put additional burdens on the Council. For example, the
introduction of free school meal payments for holidays.
Analysis of new obligations and whether they incur additional costs
not met through increased grant.
The Council has a requirement to deliver 1140 hours of Early Learning
and Childcare. The initial funding from Scottish Government was based
on individual implementation plans with funding confirmed up to March
2022. The ring fenced grant has been reduced in 2022-23 and an
exercise is required to ensure that the service can be delivered efficiently
and effectively within this reduced funding allocation.
Robust service costings, financial monitoring and timely reporting
to ensure the service can continue to deliver the service within the
financial resources available. 
Impact of high inflationary uplifts within the NPDO/HUB School contracts. Ensuring continued effective contract management of NPDO/HUB
Schools to minimise the impact of high inflationary uplifts.

Page 23

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2022  
Service Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Executive
Director
(Douglas
Hendry)
Central/Management
Costs 263 270 7 2.6% 443 443 0 0.0% Outwith Reporting Criteria    
263 270 7 2.6% 443 443 0 0.0%  
Head of
Commercial
Services
Catering 369 474 105 22.2% 1,206 1,206 0 0.0%
The YTD underspend is partially
due to the profiling of catering
purchases which will be refined
through January and underspends
on staffing due to vacancies and
delays in recruitment. 
Head of
Commercial
Services
Central/Management
Costs 898 812 (86) (10.6%) 1,104 1,104 0 0.0%
The YTD overspend in Cleaning
and Catering HQ is due to staff
costs - virement for new post to be
processed in January and costs
relating to Our Modern Workspace
project have to be transferred to
the capital budget which will
eliminate the overspend.  The
remainder is due to profiling of
One Council Property income
which will be refined through
January.
Head of
Commercial
Services
CHORD 92 61 (31) (50.8%) 26 26 0 0.0%
The YTD overspend in CHORD is
due to income profiling which will
be refined through January. 
Head of
Commercial
Services
Cleaning 127 186 59 31.7% 524 524 0 0.0%
The YTD underspend is due to
reduced use of bank staff which
will be given up for vacancy
savings in January.
Head of
Commercial
Services
Culture, Heritage,
Recreation & Sport 4,490 4,424 (66) (1.5%) 5,815 5,815 0 0.0%
The YTD overspend is due to
higher than anticipated essential
central repair costs within council
buildings.

Page 24

Head of
Commercial
Services
Events &
Commercial
Catering
190 71 (119) (167.6%) 138 138 0 0.0%
The YTD overspend is due to an
under recovery of income caused
by the closure of the Civic Centre
Café which has now reopened for
staff only and reduced footfall
within Kilmory Canteen. There is
also an under recovery of income
within Events as a result of the
slow recovery from the pandemic.
Head of
Commercial
Services
Property Portfolio (95) (161) (66) 41.0% (194) (194) 0 0.0%
The YTD overspend is due to
upgrading work within Dunoon
Food Bank and re-instatement
costs for 83-85 East Clyde Street.
Head of
Commercial
Services
Property Services 879 728 (151) (20.7%) 660 660 0 0.0%
The YTD overspend is largely due
to a variance within Renewable
Energy due to a delay in the
receipt of income from renewable
schemes.
Head of
Commercial
Services
Shared Offices 727 777 50 6.4% 979 979 0 0.0%
The YTD underspend is due to the
profiling of the central repairs
budget which will be refined
through January.    
7,677 7,372 (305) (4.1%) 10,258 10,258 0 0.0%  
Head of
Education
Additional Support
for Learning 7,109 7,307 198 2.7% 10,380 10,380 0 0.0%
The YTD underspend is due to
delays in recruitment within Pupil
Support Teachers and Additional
Support Needs Assistants.
Head of
Education
Central/Management
Costs 1,474 1,459 (15) (1.0%) 2,047 2,047 0 0.0% Outwith Reporting Criteria
Head of
Education
Community Learning
& Development 6 5 (1) (20.0%) 1 1 0 0.0%
The YTD overspend is due to the
budget profile and will be refined
through January.
Head of
Education COVID 1,010 706 (304) (43.1%) 1,217 1,217 0 0.0%
The YTD overspend is due to the
budget profile of Covid funding
which will be refined through
January.
Head of
Education
Early Learning &
Childcare 3,039 3,189 150 4.7% 9,118 9,118 0 0.0%
The YTD underspend is due to the
delay in staffing structures being
fully implemented.  There is also
an underspend in healthy snacks
which is profile related and will be
refined through January according
to pupil numbers.

Page 25

Head of
Education Primary Education 25,488 24,831 (657) (2.7%) 35,437 35,437 0 0.0%
The YTD overspend of £657k is
mainly due to the late receipt of
income from the SG for PEF and
the budget profile will be adjusted
to reflect this.  There is also an
overspend within Primary HQ due
to higher than anticipated minor
repairs within schools. 
Head of
Education Pupil Support 1,667 1,638 (29) (1.8%) 2,528 2,831 (303) (12.0%)
There is a YTD overspend of £30k
in Schools Residential Placements
and £5k in Home and Hospital
Tuition, offset by other small YTD
underspends.  It is likely that both
will continue to be a pressure
through 2022/23 and a forecast
projection to reflect this has been
processed. 
Head of
Education
Schools - Central
Services 1,372 1,915 543 28.4% 2,548 2,148 400 15.7%
The YTD underspend is due to
£91k income being received for
STEM projects that requires
profiling. Budget held centrally
following a review of school
formula and profiling within the
SEEMIS budget which will be
refined through January. The
forecast underspend is due to
funding held centrally which has
been freed up following the review
of the teacher staffing formulas
and the annual review of school
entitlements.
Head of
Education
Secondary
Education 24,559 25,261 702 2.8% 35,449 34,949 500 1.4%
The YTD underspend is mainly
due to underspends within
secondary schools staffing
budgets. Under the Scheme of
Devolved School Management
(DSM) schools are permitted
flexibility at yearend, therefore no
forecast variance has been
processed in relation to this. There
are a number of staffing
underspends (that do not fall within
DSM) due to funding held centrally
which has been freed up following
the review of the teacher staffing

Page 26

formulas and the annual review of
school entitlements. A forecast
variance has now been processed
to reflect the expected year end
position. Both above are partially
offset by the late receipt of PEF
funding from the SG and the
budget profile will be refined
through January.    
65,724 66,311 587 0.9% 98,725 98,128 597 0.6%  
Head of Legal &
Regulatory
Support
Central/Management
Costs 175 177 2 1.1% 263 263 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Community Safety 124 97 (27) (27.8%) 177 177 0 0.0%
The YTD overspend is profile
related and will be refined through
January.
Head of Legal &
Regulatory
Support
Elections 234 206 (28) (13.6%) 386 386 0 0.0%
The YTD overspend is due to
budget profiling which will be
refined through January.
Head of Legal &
Regulatory
Support
Governance 492 517 25 4.8% 791 791 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Governance, Risk &
Safety 394 394 0 0.0% 554 554 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Legal Services 367 394 27 6.9% 679 679 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
NPDO and Hub
Schools 11,287 11,467 180 1.6% 14,424 14,424 0 0.0%
The YTD underspend is due to
profiling of Third Party Payments
and the timing of associated
recharge income from Education.
Head of Legal &
Regulatory
Support
Procurement,
Commercial and
Contract
Management
745 802 57 7.1% 1,160 1,160 0 0.0%
The YTD underspend is due to
delays in filling vacancies within
Procurement and Commissioning.
Head of Legal &
Regulatory
Support
Trading Standards &
Advice Services 581 567 (14) (2.5%) 743 743 0 0.0% Outwith Reporting Criteria    
14,399 14,621 222 1.5% 19,177 19,177 0 0.0%      
88,063 88,574 511 0.6% 128,603 128,006 597 0.5%

Page 27

YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 28

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2022
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 67,571 70,127 2,556 3.6% 99,229 98,329 900 0.9%
Non-Education: The YTD overspend of £21k is due to an overspend of £83k within Commercial
Services catering and events offset by an underspend of £62k within Legal and Regulatory due to
delays in recruitment in Procurement and Commissioning.
Education: The YTD underspend of £2.577m is largely due to employee budgets within schools and
learning centres which is higher as pay award has not been agreed yet.  Under the Scheme of
Devolved School Management (DSM) schools are permitted flexibility at yearend, therefore no
forecast variance has been processed in relation to this. There a number of staffing underspends that
do not fall within DSM and a forecast variance has now been processed to reflect year end position.
Premises 5,297 4,857 (440) (9.1%) 7,349 7,349 0 0.0%
Non-Education: The YTD overspend of £76k is largely due to contractor costs for surplus properties.
Education: The YTD overspend of £364k is in part due to demolition costs for Hermitage PS and
other school estate property adaptations not covered by the CRA budgets. Position will be monitored
in relation to potential recovery of insurance monies in respect of Hermitage PS.  
Supplies and
Services 8,613 9,020 407 4.5% 11,988 11,988 0 0.0%
Non-Education: The YTD overspend of £239k is profile related and will be refined through January..
Education: The YTD underspend of £646k is mainly due to the profiling of Pupil Equity Funding
Expenditure Budget Allocations from the Scottish Government and the SEEMIS budget which will all
be refined through January.
Transport 273 232 (41) (17.7%) 353 353 0 0.0%
Non-Education: The YTD overspend of £6k is profile related and will be refined through January.
Education: The YTD overspend of £35k is due to higher than anticipated staff travel costs including
acting posts and additional costs of school to college transport/ASN support.
Third Party 30,200 29,598 (602) (2.0%) 41,021 41,324 (303) (0.7%)
Non-Education: The YTD overspend of £68k is due to budget profiling that requires refining through
January.
Education: The YTD overspend of £534k is largely down to profiling within COVID budgets, 100 day
promise funding and Universal Free School Meal Expansion which will be refined through January.
There is also a YTD overspend within the Schools Residential Budget for which a forecast variance
has been processed.
Income (23,891) (25,260) (1,369) 5.4% (31,337) (31,337) 0 0.0%
Non-Education: The £333k YTD over-recovery is due to NPDO recharges to Education and profiling
within Catering, Cleaning and shared offices.  This is partially offset by YTD under-recovery within
Renewable Energy due to income profiling and accruals.
Education: The £1.701m YTD under-recovery of income is mainly due to late receipt of £1.4m income
from the SG for PEF funding,  the budget profile will be refined through January, and the profiling of
school meal income in Primary and Secondary Schools which will also be refined through January.
Totals 88,063 88,574 511 0.6% 128,603 128,006 597 0.5%

Page 29

YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 30

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – RED VARIANCES AS AT 31 DECEMBER 2022 
Service Area
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Education - Pupil Support 2,433 2,736 (303) (12.5%)
Higher than anticipated demand for placements within
Residential Schools (£268k) and Home and Hospital Tuition
(£35k).
Education - Schools - Central Services 2,521 2,121 400 15.9%
Forecast underspend in employee costs due to funding held
centrally which has been freed up following the review of the
teacher staffing formulas and the annual review of school
staffing entitlements.
Education - Secondary Education 35,364 34,864 500 1.4%
Forecast underspend in employee costs due to funding held
centrally which has been freed up following the review of the
teacher staffing formulas and the annual review of school
entitlements.
A Red variance is a forecast variance which is greater than +/- £50,000.

Page 31

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – AS AT 31 DECEMBER 2022 
The department is currently forecasting an overspend of £0.740m (1.5%) for the year.  This is due to an under-recovery of income in Piers and
Harbours, an overspend in Waste employee costs due to sickness absence cover, landfill tax increases and a back-payment for an increased
tonnage rate for Waste Disposal from one of our suppliers.  These are partially offset with additional income in Crematoria, Commercial
Waste, Building Control and Private Water Supply Appraisals plus an underspend in Directorate due to budget no longer being needed. 
The department has a year to date overspend of £3.417m (10.0%).  This is mainly due to income being behind profile in the Roads
Operational Holding Account due to Capital project timing, which is difficult to profile, and the under-recovery of income in Piers and Harbours.  
Forecast Outturn Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Executive Director (Kirsty
Flanagan) 331 199 132 132 0
Head of Customer Support
Services 8,055 7,995 60 0 60
Head of Development and
Economic Growth 10,151 10,124 27 420 (393)
Head of Roads and
Infrastructure Services 30,385 31,344 (959) (854) (105)
Totals 48,922 49,662 (740) (302) (438) 
Year to Date Position 
Key Financial Successes:
At the end of financial year 2021-22 the department showed an overall underspend of £0.574m after taking into account all earmarkings. The
main underspends were due to the over-recovery of vacancy savings, additional income in Environmental Health from Private Water Supply
Appraisals and additional Planning Fee income which was partially offset by the under-recovery of Building Warrant income. Overall there was
a favourable net position. 
0%
25%
50%
75%
100%
Executive Director
(Kirsty Flanagan)
Head of Customer
Support Services
Head of
Development and
Economic Growth
Head of Roads and
Infrastructure
Services
Expenditure to date against the remaining budget for each
Service
YTD
Actual
£000
Remaining Budget
£000

Page 32

Key Financial Challenges: Proposed Actions to address Financial Challenges:
The impact of COVID-19 Costs are being monitored and contained where possible. 
Department / Service ongoing ability to meet future savings / efficiency
requirements.
Monitoring of trends / expenditure levels / service configuration and
the Service Packages Policy Options savings process.
Dangerous buildings costs as there is no budget for this expenditure and
the council has no control over the demand for the service.   
Building Standards, Legal Services and Financial Services are
working closely to manage debt recovery and to consider other
options to minimise corporate risk exposure.  
Due to the nature of the various components of Waste Management there
are ongoing challenges with:
• The introduction of the Deposit Return Scheme
• Uncertainty with recycling income/ gate fee costs due to the           
volatility of the market
• Challenges in the legislative changes around the disposal of      
Biodegradable Municipal Waste 
To closely monitor all service components of Waste Management
and review the Waste Strategy in conjunction with our contractual
partner Renewi (previously Shanks).
Winter Maintenance costs are difficult to estimate as they are very much
dependant on the weather.  
Close monitoring of Winter Maintenance and reporting of the
financial implications through the budget monitoring process. The
Council agreed the winter policy, setting out the intervention level
and locations to be treated.  The number of treatments is determined
by weather conditions. The current budget provision provides for 58
full equivalent runs. There is a sophisticated weather monitoring
system in place consisting of several weather stations, this is
supported by a forecasting and meteorological service which is
collaboratively procured by West of Scotland local authorities.
Rising cost of materials across the service will result in a reduction in
activity or overspends. Specifically there have been significant increases
in the price of salt and bitumen in recent months.
Costs are monitored regularly and contained as much as possible,
with any unavoidable overspends highlighted as soon as known.

Page 33

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2022
Service
Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Executive
Director
(Kirsty
Flanagan)
Central/Management
Costs 193 168 (25) (14.9%) 331 199 132 39.9%
The YTD overspend is due to
one-off consultancy costs. 
Forecast variance relates to
budget harvested across the
department from previous years
which is no longer needed.    
193 168 (25) (14.9%) 331 199 132 39.9%  
Head of
Customer
Support
Services
Central/Management
Costs 126 120 (6) (5.0%) 164 164 0 0.0% Outwith Reporting Criteria.
Head of
Customer
Support
Services
Communications 170 220 50 22.7% 311 311 0 0.0%
The YTD underspend is due to a
vacancy in the Communications
Team being used to fund agency
staff for the remainder of the
year.
Head of
Customer
Support
Services
Customer Service
Centres 1,144 1,020 (124) (12.2%) 1,379 1,379 0 0.0%
Drawdown from earmarking to be
done in relation to Main/dev
comp software.  Under recovery
of income in print room.
Head of
Customer
Support
Services
HR 1,575 1,508 (67) (4.4%) 2,145 2,085 60 2.8%
Profiling of Income recharges. 
Vacancy Savings needing
realligned.
Head of
Customer
Support
Services
ICT 2,599 2,573 (26) (1.0%) 4,015 4,015 0 0.0% Outwith Reporting Criteria.
Head of
Customer
Support
Services
Registrars 9 6 (3) (50.0%) 41 41 0 0.0% Minor variance relating to income
timing.    
5,623 5,447 (176) (3.2%) 8,055 7,995 60 0.7%  
Head of
Development
& Economic
Growth
Airports 981 930 (51) (5.5%) 1,182 1,182 0 0.0% Petrol stock purchased in
advance of resale.
Head of
Development Building Control (321) (100) 221 (221.0%) (93) (113) 20 (21.5%) Variance due to over-recovery of
Building Warrant income.

Page 34

& Economic
Growth
Forecast variance less than YTD
due to timing and profile of
income budget.
Head of
Development
& Economic
Growth
Central/Management
Costs 403 421 18 4.3% 590 590 0 0.0% Outwith Reporting Criteria.
Head of
Development
& Economic
Growth
Culture & Heritage 141 104 (37) (35.6%) 218 218 0 0.0%
Expenditure for Events and
Festivals - earmarked reserve to
be drawn down to cover.
Head of
Development
& Economic
Growth
Development
Management (448) 122 570 467.2% 264 264 0 0.0%
Additional Planning Fee income
which is planned to be used to
fund additional resources.
Head of
Development
& Economic
Growth
Development Policy 302 302 0 0.0% 428 428 0 0.0% Outwith Reporting Criteria.
Head of
Development
& Economic
Growth
Economic
Development 2,452 2,775 323 11.6% 2,853 2,853 0 0.0%
Income for Islands Infrastructure
Fund and Place Based
Investment received in advance
of payments offset against
outstanding claims for UK
Community Renewal Fund.
Head of
Development
& Economic
Growth
Environmental
Health 873 818 (55) (6.7%) 1,236 1,229 7 0.6%
Delay in Private Water Supply
grant.  Forecast variance relates
to additional income for Water
Supply Appraisals offset with a
reduction in Fish Export income
and additional expenditure for
supplies and services.
Head of
Development
& Economic
Growth
Environmental
Initiatives 105 82 (23) (28.1%) 117 117 0 0.0% Profile of third party payment.
Head of
Development
& Economic
Growth
Housing 3,539 3,399 (140) (4.1%) 3,130 3,130 0 0.0%
HEEPS expenditure incurred in
advance of income being claimed
for which is offset against an
underspend in Private Sector
Housing Grant payments.
Head of
Development
& Economic
Growth
Private Landlords (11) 0 11 0.0% 0 0 0 0.0% Outwith Reporting Criteria.

Page 35

Head of
Development
& Economic
Growth
Transportation Policy 275 159 (116) (73.0%) 226 226 0 0.0%
Expenditure incurred for CWSS
and SUSTRANS prior to grant
being claimed.    
8,291 9,012 721 8.0% 10,151 10,124 27 0.3%  
Head of
Roads &
Infrastructure
Services
Amenity 2,911 2,798 (113) (4.0%) 3,255 3,356 (101) (3.1%)
Forecast variance relates to an
over-recovery of income in
Crematoria offset with
overspends in employee costs,
under-recovery of income in
Parks for Hire of Facilities
income, Pest Control for external
income and Public Convenience
income.
Head of
Roads &
Infrastructure
Services
Car Parking (430) (578) (148) 25.6% (604) (604) 0 0.0%
Under-recovery of DPE income
partially offset with additional
parking income and underspend
in Car Park Maintenance.
Head of
Roads &
Infrastructure
Services
Central/Management
Costs 2,346 2,328 (18) (0.8%) 2,869 2,869 0 0.0% Outwith Reporting Criteria.
Head of
Roads &
Infrastructure
Services
Depots 283 212 (71) (33.5%) (469) (469) 0 0.0% Additional costs for Kilmory
Depot for rationalisation project.
Head of
Roads &
Infrastructure
Services
Fleet & Transport 6,766 6,308 (458) (7.3%) 8,720 8,720 0 0.0%
Overspend due to vehicle repairs
in Fleet, additional staff costs in
Pupil Transport which are
partially offset with an
underspend in Public Transport.
Head of
Roads &
Infrastructure
Services
Infrastructure 572 509 (63) (12.4%) 722 722 0 0.0% Profile of budget out of line with
payments.
Head of
Roads &
Infrastructure
Services
Marine (3,550) (4,105) (555) 13.5% (3,871) (3,432) (439) 11.3% Under-recovery of income in
Piers and Harbours.
Head of
Roads &
Infrastructure
Services
Network & Traffic
Management 164 78 (86) (110.3%) 139 139 0 0.0%
Under-recovery of income for
Traffic Regulation Orders and
New Roads and Street Works
Act.

Page 36

Head of
Roads &
Infrastructure
Services
Road Safety 77 90 13 14.4% 145 145 0 0.0% Minor underspend in supplies
and services.
Head of
Roads &
Infrastructure
Services
Roads & Lighting 6,291 4,009 (2,282) (56.9%) 6,371 6,371 0 0.0%
Delays in recharges to capital
budget resulting in a reduction in
income in the Roads Operational
Holding Account, this should be
rectified as we continue through
the year and the recharges are
processed.
Head of
Roads &
Infrastructure
Services
Waste 8,220 8,064 (156) (1.9%) 13,108 13,527 (419) (3.2%)
Forecast overspend relates to
additional expenditure due to
increased disposal fees, offset
against additional income
received for Commercial Refuse.    
23,650 19,713 (3,937) (20.0%) 30,385 31,344 (959) (3.2%)      
37,757 34,340 (3,417) (10.0%) 48,922 49,662 (740) (1.5%)   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 37

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2022 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 25,933 26,181 248 1.0% 37,163 37,077 86 0.2%
Underspend in Roads Operational Holding Account which will be offset against reduction in income.
Forecast variance relates to savings in transport and staff training offset against additional staffing
costs in Waste to cover sickness absence.
Premises 1,606 1,591 (15) (0.9%) 3,034 3,034 0 0.0% Outwith Reporting Criteria.
Supplies and
Services 8,464 7,368 (1,096) (14.9%) 10,189 10,192 (3) (0.0%)
Material expenditure in the Roads Operational Holding Account higher than the profiled budget due to
high level of capital expenditure, this will be offset with an increase in income as recharges are
processed against capital throughout the year.
Forecast variance relates to small overspend for Environmental Health for Sampling costs.
Transport 9,328 8,190 (1,138) (13.9%) 16,051 16,302 (251) (1.6%) Overspend due to vehicle repairs and additional external leases.  Forecast variance relates to Waste
vehicle repairs and fuel costs.
Third Party 32,175 27,933 (4,242) (15.2%) 39,525 40,127 (602) (1.5%)
Recharges from Roads Operational Holding Account higher than the profiled budget, this will be offset
with an increase in income as recharges are processed.  Various grant payments made in Economic
Development and Housing which are offset against actual income received. 
Forecast variance relates to Waste Disposal payment regarding increased disposal fees and
additional staffing recharges in Amenity and Waste to cover sickness absence.
Capital Financing 0 0 0 0.0% 1,979 1,979 0 0.0% Outwith Reporting Criteria.
Income (39,749) (36,923) 2,826 (7.7%) (59,019) (59,049) 30 (0.1%)
Forecast variance relates to an under-recovery of income in Piers and Harbours offset with an over-
recovery of Commercial Refuse Income in Waste, Water Supply Appraisals and Crematorium income. 
YTD variance also includes a delay in recharges to capital resulting in a reduction in income in the
Roads Operational Holding Account offset against income for Islands Infrastructure Fund and Place
Based Investment received in advance of payments.
Totals 37,757 34,340 (3,417) (10.0%) 48,922 49,662 (740) (1.5%) 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 38

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – RED VARIANCES AS AT 31 DECEMBER 2022
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Directorate 132 0 132 100.0% Unallocated budget saving.
HR 93 33 60 64.5% Reduction in staff training.
Crematoria (496) (581) 85 (17.1%) Additional income in Cardross
Crematorium.
Environmental Health (66) (116) 50 (75.8%) Additional income for Appraisal of
Water Supplies.
Planning (1,181) (1,236) 55 (4.7%) Additional planning fee income.
Waste Collection 34 84 (50) (147.1%) Overspend in vehicle repairs.
Waste Collection 470 551 (81) (17.2%) Overspend in fuel.
Waste Collection (1,692) (2,112) 420 (24.8%) Additional income for Commercial
Refuse.
Waste Disposal 189 523 (334) (176.7%) Additional expenditure for increase
in disposal fees.
Waste Disposal PPP 6,487 6,571 (84) (1.3%) Landfill tax increase due to banding
changes.
Marine (1,656) (1,217) (439) 26.5% Under-recovery of income. 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 39

SOCIAL WORK – AS AT 31 DECEMBER 2022 
The department is currently forecasting an overspend of £0.253m (0.3%) which is mainly due to high demand for services and the use of
agency staff to fill staffing recruitment and retention gaps across Adult Services.   
The department has a year to date underspend of £1.301m (3.0%) which is mainly due to the timing of payments, budget profiling across
services and demand for purchased Children’s Services. This is partially offset by high demand for services across Adult Services and staffing
pressures, including the use of agency staff, across Homecare and Older People Residential Units. 
Forecast Outturn Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Chief Officer Integration 2,790 490 2,300 2,300 0
Head of Strategic Planning
and Performance 455 450 5 5 0
Head of Health and
Community Care 38,003 39,162 (1,159) (1,159) 0
Head of Acute and
Complex Care 17,156 18,866 (1,710) (1,710) 0
Head of Children and
Families 15,419 15,108 311 311 0
Totals 73,823 74,076 (253) (253) 0
Year to Date Position 
0%
25%
50%
75%
100%
Chief Officer
Integration
Head of Adult
Services
Head of Children
and Families
Head of
Strategic
Planning and
Performance
Expenditure to date against the remaining budget
for each Service
YTD… Remaining Budget…
Key Financial Successes: 
Delivered an underspend at the end of 2021/22 after automatic earmarkings and full repayment of £2.759m of debt owed to the Council for
prior year deficits. This should allow for future investment and transformation across Social Work with prior year deficits now fully repaid.

Page 40

Key Financial Challenges: Proposed Actions to address Financial Challenges:
Deliver the outstanding savings total for 2022/23 of £0.425m (as at
December 2022).
Maintain a close working relationship with the HSCP Service
Improvement Team in order to quickly and efficiently identify and
assess options for delivering the outstanding savings.
Development and delivery of future service redesigns which will be
necessary to contain service expenditure within the allocated resource in
the medium to long term.
Support from finance to assist strategic managers to look beyond
the short term to identify and plan the changes which will be needed
to address the expected ongoing budget challenge over the next 3
to 5 years.
Support the HSCP through the recovery from the COVID-19 pandemic.
There have been additional costs and pressures across the HSCP as a
direct result of the partnership’s response to COVID-19. These costs are
captured and reported to the Scottish Government via Mobilisation Plans.
Support from finance to assist the service in capturing details of all
additional costs associated with the response to COVID-19 to
ensure these are included in Scottish Government funding returns. 
Use of agency staff to support service delivery across Social Work, but
particularly in Older People services, due to recruitment and retention
challenges within the service. Year to date spend £1.247m, with a forecast
spend of £1.576m at December 2022.
Close working relationship with the HSCP to support the costing of
a recovery plan to stabilise the service and ensure it is operationally
and financially sustainable.

Page 41

SOCIAL WORK – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2022
Service Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Chief Officer
Integration
Integration
Headquarters 225 282 57 20.2% 449 445 4 0.9%
The YTD position is as a result of
over-recovery of income for a post
recharged to Scottish Government
partially offset by timing of payments
to Health Boards. The forecast
variance is outwith reporting criteria. 
Chief Officer
Integration
Social Work
Central
Support
52 1,126 1,074 95.4% 2,341 45 2,296 98.1%
The YTD variance is due to
underspends on centrally held funds
(£1.432m) and YTD underspends on
central repairs (£21k) combined with
income over-recovery for Covid-19
income loss from charges to clients
and funding for Staff Bonus
Payments (£54k). This is partially
offset by YTD overspend on Covid-
19 expenditure due to timing of
receipt of funding allocations (£273k)
and YTD vacancy savings under-
recovery (£140k). These will both be
rectified in January through budget
profiling and funding allocations. The
forecast underspend reflects
forecast underspends on centrally
held funds (£2.1m) combined with
forecast over-recovery on vacancy
savings (£650k) and additional
Covid-19 funding (£54k). This is
partially offset by a £500k provision
for the unfunded impact of the
2022/23 pay award across Social
Work.    
277 1,408 1,131 115.6% 2,790 490 2,300 99.0%  
Head of
Strategic
Planning &
Performance
Management &
Central Costs 301 313 12 3.8% 431 424 7 1.6%
Outwith reporting criteria.
Head of
Strategic
Service
Development 22 21 (1) (4.8%) 24 26 (2) (8.3%) Outwith reporting criteria.

Page 42

Planning &
Performance    
323 334 11 (0.9%) 455 450 5 (6.7%)  
Head of Health
and Community
Care
Management &
Central Costs 330 400 70 17.5% 489 487 2 0.4%
The YTD position is due to an over-
recovery of income as a result of a
post recharge to Scottish
Government combined with budget
profiling and timing of payments to
third parties.  The forecast variance
is outwith reporting criteria.
Head of Health
and Community
Care
Older People 21,505 22,006 501 2.3% 37,514 38,675 (1,161) (3.1%)
The YTD underspend is a result of
an over-recovery of income in
Homecare, Care Home Placements
and Residential Units and payroll
underspends in the Assessment and
Care Management teams due to
staff vacancies and posts being filled
by NHS staff. This is further
increased by budget profiling/timing
of payments for purchased services
in Older People. This is partially
offset by YTD overspends on
staffing in Homecare and Residential
Units (including spend on agency)
and as a result of demand for Care
Home Placements. The forecast
overspend reflects demand for Care
Home Placements and Homecare as
well the use of Agency staff across
Assessment and Care Management,
Homecare and Residential Units.    
21,835 22,406 571 2.6% 38,003 39,162 (1,159) (3.0%)  
Head of Acute
and Complex
Care
Learning
Disabilities 6,700 5,898 (802) (13.6%) 12,032 13,479 (1,447) (12.0%)
The YTD overspend is due to
demand for services within
Supported Living and Residential
Placements combined with slippage
against budget savings targets
(£261k). This is partially offset by
underspends in the Day Services.
The forecast overspend reflects
higher than budgeted demand for
services in Supported Living (£663k)
and Joint Residential (£527k)
combined with slippage in

Page 43

achievement of budget savings
(£305k). This is partially offset by
forecast underspends on Day
Services. 
Head of Acute
and Complex
Care
Management &
Central Costs 69 90 21 23.3% 126 122 4 3.2%
The YTD position is as a result of
budget profiling and timing of
payments to third parties and on
staff training. The forecast variance
is outwith reporting criteria.
Head of Acute
and Complex
Care
Mental Health 1,280 1,217 (63) (5.2%) 2,343 2,444 (101) (4.3%)
The YTD overspend is due to budget
profiling and timing of income
receipts and payments to other
bodies for purchased services. The
forecast overspend reflects higher
than budgeted demand for services
in Supported Living (£19k) and
Residential Placements (£85k). 
Head of Acute
and Complex
Care
Physical
Disability 1,801 1,765 (36) (2.0%) 2,655 2,821 (166) (6.3%)
Outwith reporting criteria. The
forecast overspend reflects higher
than budgeted demand for services
in Supported Living (£85k) and
Residential Placements (£80k).    
9,850 8,970 (880) 2.5% 17,156 18,866 (1,710) (19.4%)  
Head of
Children &
Families
Child
Protection 2,070 2,183 113 5.2% 3,259 3,228 31 1.0%
The YTD underspend is due budget
profiling and timing of payments to
other bodies and health boards as
well as underspends on staff travel
and subsistence all partially offset by
timing of receipt of income from
other bodies. The forecast variance
is outwith reporting criteria.
Head of
Children &
Families
Children with a
Disability 584 665 81 12.2% 964 966 (2) (0.2%)
The YTD underspend is as a result
of budget profiling and timing of
payments to other bodies.  The
forecast variance is outwith reporting
criteria.
Head of
Children &
Families
Criminal
Justice 40 64 24 37.5% 126 110 16 12.7%
The YTD underspend is as a result
of staff turnover and vacancies
combined with underspends on staff
travel and subsistence as a result. 
The forecast underspend is on
payments to other local authorities
combined with staff travel and

Page 44

subsistence partially offset by a
forecast overspend on payroll costs.
Head of
Children &
Families
Looked After
Children 5,313 5,563 250 4.5% 7,792 7,502 290 3.7%
The YTD underspend is due to
underspends in Fostering and
Adoption due to demand for these
services combined with
underspends on Residential
Placements and over-recovery of
income in Supporting Young People
Leaving Care from the Home Office
for UASC. This is all partially offset
by overspends on staff costs in the
Children's Houses and Hostels. The
forecast underspend reflects
demand for Fostering, Adoption and
Residential Placements as well as
over-recovery of income across
Supporting Young People Leaving
Care for UASC activity from the
Home Office. This is partially offset
by overspends in the Children's
Houses and Hostels on payroll costs
and on service provision at
Castlewood Court. 
Head of
Children &
Families
Management &
Central Costs 2,246 2,246 0 0.0% 3,278 3,302 (24) (0.7%)
Outwith reporting criteria.    
10,253 10,721 468 4.4% 15,419 15,108 311 2.0%  
GRAND
TOTAL   42,538 43,839 1,301 3.0% 73,823 74,076 (253) (0.3%)   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 45

SOCIAL WORK – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2022 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 22,870 22,335 (535) (2.4%) 32,419 33,907 (1,488) (4.6%)
Both the YTD overspend and forecast overspend is
due to overspends in Residential Units (both children
and adults)  and across Homecare as a result of use
of bank, agency staff and overtime.
Premises 802 711 (91) (12.8%) 1,140 1,299 (159) (14.0%)
The YTD overspend is as a result of budget profiling
on the refuse collection budgets and overspends on
rental costs.
The forecast overspend is due to rental costs across
the Service and utility costs at the Hostels.
Supplies &
Services 1,393 1,017 (376) (37.0%) 1,000 1,391 (391) (39.1%)
The YTD overspend reflects slippage on the
achievement of budget savings and YTD overspends
on small tools and equipment due to timing of
purchases at the Equipment Store, staff subsistence at
Tigh a Rudha, laundry costs at Ardfenaig and fees in
relation to the transfer of Kintyre Care Centre.  
The forecast overspend is mainly due to forecast
slippage on budget savings (£305k) combined with
overspends on staff subsistence at Tigh a Rudha and
across various other supplies and services at the Adult
Services Residential Units.
Transport 408 475 67 14.1% 631 557 74 11.7%
The YTD underspend is due to various travel
underspends across the service which is to be
expected due to the  changes to travel habits as a
result of Covid-19 and the current level of staffing
vacancies across the service. 
The forecast year end outturn reflects the continued
reduction in travel costs across the service and an
expectation that different ways of working will continue
to reduce future spending on travel.
Third Party 38,634 39,917 1,283 3.2% 62,248 62,034 214 0.3%
The YTD underspend reflects timing of payments
across services and subsequent budget profiling as
well as YTD underspends on unallocated centrally
held funding.
The forecast underspend is as a result of demand for
purchased care services across Fostering and
Adoption as well as underspends on unallocated
centrally held funding. This is partially offset by

Page 46

demand for purchased care services across Adult
Services.
Income (21,569) (20,616) 953 (4.6%) (23,615) (25,112) 1,497 (6.3%)
Both the YTD and forecast over recovery of income is
mainly due to increased income from fees, charges
and recharges.
Totals 42,538 43,839 1,301 3.0% 73,823 74,076 (253) (0.3%)   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 47

SOCIAL WORK – RED VARIANCES AS AT 31 DECEMBER 2022
Service Area
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Social Work Central Support 2,341 45 2,296 98.1%
The forecast underspend reflects forecast underspends on centrally held funds (£2.1m)
combined with forecast over-recovery on vacancy savings (£650k) and additional Covid-
19 funding (£54k). This is partially offset by a £500k provision for the unfunded impact of
the 2022/23 pay award across Social Work.
Looked After Children 7,792 7,502 290 3.7%
The forecast underspend reflects demand for Fostering, Adoption and Residential
Placements as well as over-recovery of income across Supporting Young People
Leaving Care for UASC activity from the Home Office. This is partially offset by
overspends in the Children's Houses and Hostels on payroll costs and on service
provision at Castlewood Court. 
Older People 37,514 38,675 (1,161) (3.1%)
The forecast overspend reflects demand for Care Home Placements and Homecare as
well the use of Agency staff across Assessment and Care Management, Homecare and
Residential Units.
Physical Disability 2,655 2,821 (166) (6.3%) The forecast overspend reflects higher than budgeted demand for services in Supported
Living (£85k) and Residential Placements (£80k).
Learning Disability 12,032 13,479 (1,447) (12.0%)
The forecast overspend reflects higher than budgeted demand for services in Supported
Living (£663k) and Joint Residential (£527k) combined with slippage in achievement of
budget savings (£305k). This is partially offset by forecast underspends on Day
Services. 
Mental Health 2,343 2,444 (101) (4.3%) The forecast overspend reflects higher than budgeted demand for services in Supported
Living (£19k) and Residential Placements (£85k). 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 48

MONITORING OF SAVINGS – AS AT 31 DECEMBER 2022
New policy savings were identified for the three year period 2022-23 to 2024-25 and these were agreed by Council in February 2022.  Council
agreed to policy savings of £0.280m in 2022-23 rising to £0.286m by 2024-25. 
The position of historical policy saving options is as follows:
- 2021/22 – those not delivered or that have further increase in value in 2022-23 onwards total £0.732m
- 2020/21 – those not delivered total £0.050m
- 2019/20 – all delivered
- 2018/19 - those not delivered total £0.498m
The 2022-23 savings have been removed from departmental budgets, however, it is important to monitor whether the saving has actually been
delivered to ensure that costs are not continuing resulting in an overspend by the end of the year.  It is also important to ensure that any
preparatory work required to deliver savings in future years is on track. 
There are six savings categorised as having a potential shortfall and one currently delayed as summarised below: 
Saving Saving
Agreed
Status Detail Shortfall/
Delayed
Value
TB07 – Depots  Feb-18 Potential Shortfall -
there is a risk that
the original saving
will not be achieved
in full.  
Create one main depot in key areas to reduce costs – it has
become apparent that the operating costs of the single
redeveloped site in each town will increase, reducing the
anticipated saving.  Work ongoing on a depot consolidation
scheme in Lochgilphead and work is progressing to outline
various funding options for discussion. A project is also
underway for Bowmore.
£107,500
TB13b Roads and
Amenity Services
charging (non-statutory
services)
Feb-18 Potential Shortfall -
there is a risk that
the original saving
will not be achieved
in full.  
The original proposal was to introduce charges for providing
lighting design and increase charges by 20% for road
construction consents, skips, scaffolds, hoarding, permits and
licences. Whilst some additional income has been generated
through third party works, opportunities are expected to be
limited over the foreseeable future due to staff shortages and
other competing demands.
£100,000

Page 49

TB12b Stadiums Feb-18 Potential Shortfall -
there is a risk that
the original saving
will not be achieved
in full.  
Discussions had stalled with partners in the Oban and Lorn
area with regard to Mossfield stadium to create a sports Hub,
attract external funding to improve facilities and therefore attract
additional events to the arena.  The users group has now
reconvened and will be reporting to the steering group. It should
be noted there is generally a downturn in usage of pitches
partly due to more clubs booking all weather pitches at high
schools and the loss of a well established club disbanding
which will result in the loss of income. The Mossfield Sport
Group have highlighted that certain clubs along with the Shinty
Associations have expressed concerns with regards to the
condition of the Pavilion and changing facilities and this is likely
to impact on income.  East King Street bookings have reduced
due to the condition of the changing facilities and clubs having
to play their fixtures elsewhere.
£30,000
DEG05 – Building
Standards
Feb-20 Potential Shortfall -
there is a risk that
the original saving
will not be achieved
in full.  
Building market has slowed due to the increase in cost and
availability of some materials.  Reservations that the type of
applications we receive may not realise sufficient additional
income using the BCIS guide. 
£50,000
TB09 – Public
Conveniences
Feb-18 Delayed - The full
saving will not be
achieved in line with
the original
estimated timescale.  
Tender returns for the PC charging infrastructure were
significantly over budget. Additional funding has now been
confirmed via the Coastal Communities Fund which will allow
us to deliver the full scheme of 16 PCs. This was confirmed in
mid-December which will allow us to let the contract and
proceed. This saving will not be achieved this financial year but
we would expect at this stage infrastructure to be in place for
the start of 23/24 financial year and for the saving to be
achieved thereafter.
£24,000
TB17 - Office
Rationalisation and
Income Generation
Feb-18 Potential Shortfall -
there is a risk that
the original saving
will not be achieved
in full.  
Analysis of both PROP01 and TB17 has shown that there has
been a number of offices that were identified for closure,
leasing or sale that are no longer closing, therefore the full
saving will not be realised.
£69,000
PROP01 - Office
Rationalisation
Feb-21 Potential Shortfall -
there is a risk that
the original saving
The rationalisation programme has been delayed due to the
volume of information required to determine the number of
office spaces required for continued service delivery. Analysis
£213,000

Page 50

will not be achieved
in full.     
of both PROP01 and TB17 has shown that there were a
number of offices that were identified for closure, leasing or
sale that are no longer closing, therefore the full saving will not
be realised. Whilst the Our Modern Workspace project is
progressing, it is unlikely that overall utilities savings can be
achieved given the current pricing and inflationary increases
and a change in third party demand for disposals due to
economic conditions is likely to impact on NDR savings. 
All policy saving options previously agreed are noted in the table below for information.

Page 51

2022-23 2022-23
£000 FTE
Chief Executive's Unit
FS02 Feb-22 Financial
Services
Reduction of vacant 0.4FTE Local Tax
Assistant role
10.0 0.40 Delivered
Executive Director Douglas Hendry
PROP01 Feb-21 Commercial
Services
Rationalisation of the Council's property
estate over a three year programme to
identify properties which can either be
disposed of or used to generate
commercial income
294.20 4.0 Potential Shortfall
TB17 Feb-18 Commercial
Services
Identify opportunities for office
rationalisation and raising income
121.50 0.0 Potential Shortfall
CS01 Feb-22 Commercial
Services
Climate Change & Resource Efficiency 63.0 0.00 On Track to be Delivered
CS03 Feb-22 Commercial
Services
Stretch Targets for One Council Income &
Events
20.0 0.00 On Track to be Delivered
ED5 Feb-21 Education Review and reduce Clerical Support
Entitlement using updated school rolls.
121.00 5.7 Delivered
ED01 Feb-22 Education Removal of Community Learning
Development Manager Post
66.5 1.00 Delivered
Executive Director Kirsty Flanagan
CSS03 Feb-22 Customer
Support
Services
Restructure of CSP/Registration Team at
Helensburgh Civic Centre
19.0 0.50 Delivered
DEG01 Feb-22 Development
and Economic
Growth
Crown Estate Administration Contribution
to Project Delivery
101.0 0.00 On Track to be Delivered
DEG05(a) Feb-20 Development
and Economic
Growth
Raise additional fees by adopting the
current Building Cost Information Service
(BCIS) guide for the cost of building work.
Regular service users have been
informed of this change.
50.00 0.0 Potential Shortfall
DEG02 Feb-21 Development
and Economic
Growth
Reduction to overtime budget in the
provision of fire cover at the airports for
weather delayed flights.  Arrangements
are in place that staff no longer remain at
the airport and there is a cut-off period.
22.00 0.0 Delivered
DEG07 Feb-21 Development
and Economic
Growth
Additional income through fees and
charges for s64 Non-Material Amendment
Submissions, non e-planning application
submissions and property history
searches
20.00 0.0 Delivered
DEG10 Feb-21 Development
and Economic
Growth
Maximise income through additional
private water supplies income from risk
assessments of supplies  and introducing
a new charge for the provision of shellfish
movement documents
17.50 0.0 Delivered
TB07 Feb-18 Roads and
Infrastructure
Services
Create one main depot in key areas to
reduce costs
172.50 0.0 Potential Shortfall
TB13b Feb-18 Roads and
Infrastructure
Services
Roads & Amenity Services charging (non-
statutory services)
150.00 0.00 Potential Shortfall
R&I17 Feb-21 Roads and
Infrastructure
Services
Public transport fare scale increase 76.00 0.0 On Track to be Delivered
R&I03 Feb-21 Roads and
Infrastructure
Services
Administrative support - rationalise across
service
50.00 2.0 Delivered
R&I05 Feb-21 Roads and
Infrastructure
Services
Design service fees - bringing in line with
industry standards and reduce cost of
consultancy. Two posts created as a
spend to save
50.00 -2.0 On Track to be Delivered
R&I09 Feb-21 Roads and
Infrastructure
Services
Road inspections find and fix -  reduce
reactive work by proactivity. Moving to AI
technology as technology develops
40.00 1.0 On Track to be Delivered
TB12b Feb-18 Roads and
Infrastructure
Services
Review charges for stadiums to enable
improvement work
30.00 0.0 Potential Shortfall
R&I04 Feb-21 Roads and
Infrastructure
Fees and charges - commercial waste,
TTROs, permits/licenses. Access to debt           
25.00 -1.0 Delivered
Status of ImplementationTemplate
Ref
Saving
Agreed
Service Savings Option

Page 52

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE 
16 FEBRUARY 2023
FINANCIAL RISKS ANALYSIS 2022-23  
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to provide a summary of the key financial risks
facing the Council.   
1.2  A number of Council wide risks, both revenue and capital have been identified
along with risks for each department and service of the Council.  For each
departmental risk the financial impact has been quantified and the likelihood
assessed based on the standard risk matrix. 
1.3 There are 5 Council wide revenue risks identified for 2022-23 currently amounting
to £2.290m. 
1.4 There are currently 41 departmental risks totalling £4.935m.  Of the 41
departmental risks, one is categorised as almost certain and 4 are categorised as
likely.   
1.5 The financial risks are monitored routinely and actions put in place to continue to
mitigate the risks.

Page 53

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE 
16 FEBRUARY 2023
FINANCIAL RISKS ANALYSIS 2022-23  
2. INTRODUCTION 
2.1 This report outlines the process and approach developed in carrying out a
financial risks analysis and provides a note of the current assessment of financial
risks for 2022-23. 
3 DETAIL 
3.1 Introduction 
3.1.1 The Council is currently in a period of significant financial challenge.  In
developing its budget to address both restricted resources and cost and demand
pressures there are a number of financial risks the Council needs to consider and
manage. 
3.1.2 There are a number of risks that affect the income or expenditure across the
whole council and these have been identified.  Financial risks have been
considered by each department and service of the Council.   
3.1.3 For each risk, the financial impact has been quantified and the likelihood
assessed based on the standard risk matrix as follows: 
1 – Remote
2 – Unlikely
3 – Possible
4 – Likely
5 – Almost Certain 
3.1.4 The Argyll and Bute Integrated Joint Board (IJB) with responsibility for Social
Work and a range of Health services was established and came into effect on 1
April 2016.  The IJB is responsible for financial and strategic oversight of these
services.  It is the responsibility of the IJB to consider the individual financial risks
associated with Integration Services and they are therefore not contained within
this report.  A Council wide risk has been included in respect of the IJB being
unable to deliver the social care service within the budget allocated. 
3.2 Council Wide Risks 
Revenue  
3.2.1 Utility costs remain a volatile area and it is difficult to accurately predict how the
prices could vary.  The outturn in respect of utilities for 2021-22 was an
underspend of £0.310m which was partly due to fixed price contracts that had

Page 54

been secured which have now expired. With the volatility of utilities pricing it is
very difficult to predict the impact going forward but a financial risk based on a
20% variation in utility costs amounts to £0.706m. 
3.2.2 The estimated level of council tax income is based on current and forecast Band
D equivalents and non-payment rates.  This reflects our most recent experience in
terms of the council tax base and likely collection rates.  A 1% variation in council
tax income amounts to approximately £0.553m. 
3.2.3 At the budget meeting on 24 February 2022, the Council agreed 6 new policy
savings options that would deliver savings over the period 2022-23 to 2024-25. 
The savings to be delivered in 2022-23 amount to £0.280m.  Whilst the Council
have a good track record in delivering savings, a 10% shortfall on this savings
target would amount to £0.028m.    
3.2.4 In respect of the Health and Social Care Partnership, it is the responsibility of the
Chief Officer and Chief Financial Officer to manage the HSCP financial position. 
If an overspend is forecast, a budget recovery plan will be prepared and
submitted to the IJB, the Council and NHS Highland.  Where recovery plans are
unsuccessful and an overspend occurs at the financial year end, and the HSCP
has insufficient reserves to meet the overspend, then the partners will be required
to make additional payments to the HSCP.  Whilst any additional payments by the
Council and NHS Highland will be deducted from future years funding, there is still
a financial risk that the Council may have to pay out additional monies in year.  As
at 31 December 2022, the net HSCP outturn in 2022-23 is estimated to be a
£598m overspend (£0.253m from Social Work and £345m from Health). 
3.2.5 There is an ongoing requirement to fund unavoidable inflationary cost increases in
areas like fuel, food etc. This has been predominantly caused by the lack of
availability of supply of labour and materials as a result of the COVID-19
pandemic, the UK exit from the European Union, Russia’s invasion of Ukraine and
sanctions on Russian owned entities.  The Bank of England are currently
forecasting that inflation will continue to rise until around Quarter 1 of 2023 where
after they forecast that it will start to fall.  We will continue to closely monitor the
situation and update our financial forecasts using the best information available to
us. 
3.2.6  The Council wide risks are noted within the table below.   
Description Likelihood Assessed
Financial Impact
£000
Energy costs increase by 20% greater
than anticipated
3 706
1% variation in Council Tax Income 2 553
10% shortfall on Savings Options 2 28
IJB refer to Council for additional
funding to deliver social work services
3 253
1% variation of General Inflation Risk  4 750
Total  2,290

Page 55

Capital 
3.2.7 The finance settlement announcement on 20 December 2021 provided details of
the Local Government funding for 2022-23 and there is therefore certainty as to
what our funding is in respect of General Capital Grant and the specific capital
grants already distributed. 
3.2.8  The capital plan for 2022-23 includes an estimate of £1.387m in respect of capital
receipts.   This is based on an assessment provided by the Special Projects Team
in January 2022.  A 10% variation equates to £0.139m and this would require to
be managed across the capital programme.   
3.2.9 
3.2.10 
3.2.11
General feedback from Scotland Excel and the Project Managers indicates that
price increases and uncertainty are being experienced as well as disruptions to
the supply chain and longer lead times, particularly in relation to the construction
sector and material availability. This can be attributed to a number of factors such
as the COVID-19 pandemic, UK exit from the European Union, Russia’s invasion
of Ukraine and sanctions on Russian owned entities, to name a few. 
The increased rate of inflation impacts costs such as energy prices, labour,
packaging and transport. These all have an effect on the overall contract price
and make it extremely challenging to manage expenditure and the availability of
supply. 
While it has been possible to estimate the impact of these pressures on some
projects, and therefore include those projections within the capital monitoring
report, for others it has been more difficult and an overspend has not been
forecast at this stage but there are likely to be further significant financial impacts
not yet reported within the following projects: 
- Rothesay Pavilion
- Harbour Investment Programme
- Helensburgh Waterfront Development
- Universal Free School Meals 
3.2.12 For those liabilities/risks to the capital programme that were known at the start of
2022-23 it was agreed at the budget meeting in February 2022 to use amounts
from the Unallocated General Fund, the 2021-22 Revenue Surplus, COVID-19
specific funding and additional borrowing to mitigate these risks.

Page 56

3.3  Departmental/Service Risks 
3.3.1 The detail of each departmental financial risk is included within Appendix 1.  The
following table provides a summary of the number of risks within each department
and likelihood category with the financial impact. 
Department 1 - Remote 2 - Unlikely 3 - Possible 4 - Likely 5 - Almost
Certain Total
No £000 No £000 No £000 No £000 No £000 No £000
Chief Executive's
Unit 1 125 0 0 2 115 0 0 1 345 4 585
Executive Director
Douglas Hendry 2 20 7 545 9 870 4 380 0 0 22 1,815
Executive Director
Kirsty Flanagan 3 160 3 240 9 2,135 0 0 0 0 15 2,535
Total 6 305 10 785 20 3,120 4 380 1 345 41 4,935 
3.3.2 The current top three risks in terms of the financial impact are noted in the table
below. 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Roads and
Infrastructure
Services
Roads Maintenance -
Bridges, Culverts &
Sea Defences
Extreme localised weather may
result in loss of bridge, culvert, road
or sea defence.
3 750
Roads and
Infrastructure
Services
Roads Materials -
Bitumen
Increased cost of asphalt material
due to price of crude oil rising. 
Discussions emerging from the
industry about possible rationing of
bitumen which, if applied, will affect
our programmes due to availability
3 400
Roads and
Infrastructure
Services
Winter Maintenance Adverse weather conditions which
require greater than budgeted
number of gritting runs.
3 365 
3.3.3 The risks which are almost certain and likely are noted below:

Page 57

SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD
FINANCIAL
IMPACT
£000
Commercial
Services
Catering Costs
– Changes to
Food and Drink
in Schools
Standards
The Scottish Government reviewed the
regulations that govern the food and
drinks currently provided in schools. The
proposed changes  were published in June
2019 and were implemented from Easter
2021.  The revised standards focus on
reducing sugar, reducing red and red
processed meat and increasing fibre. Thus
far, there has been an increase in costs
and a reduction in demand for school
meals. 
4 150
Commercial
Services
Catering
Purchases
Increased supplier charges.  This estimate
does not include the additional risk to food
cost and uptake from the changes to food
and drink standards in schools.
4 100
Legal and
Regulatory
Support
Contract RPI
for NPDO and
Hub Schools
Increase in RPI would result in higher
costs.
4 100
Legal and
Regulatory
Support
Licensing Reduced numbers of licensing applications
leading to reduced income.
4 30 
3.4 Changes to Financial Risks since last report 
3.4.1 There has been 1 change to the departmental risks since the financial risks report
was presented to the Policy and Resources Committee on 8 December 2022, as
follows: 
- The risk in relation to council tax collection has had the financial impact
reduced from £0.500m to £0.345m due to a recent improvement in
summonsed debt recovery by the sheriff officer.    
3.5 Monitoring of Financial Risks 
3.5.1 Financial risks will be reviewed and monitored on a two monthly basis and will be
included in the pack of financial reports submitted to Policy and Resources
Committee.

Page 58

3.6 Potential Future Risks 
3.6.1 At the Policy and Resource meeting on 13th October 2022, it was discussed that
the Dunbartonshire and Argyll and Bute Valuation Joint Board would be
publishing new NDR rates for 2023-24 to 2025-26 at the end of November.  There
is a risk of increased NDR costs across the Council’s buildings and schools in
2023-24 year onwards due to an increase in rateable value on the NDR roll.  The
government has announced a transitional relief scheme and the Council will
consider its position in respect of appealing any increases to the valuation of its
land and heritages. 
3.6.2 Within Customer Support Services, there is a risk in relation to the cost of
additional bandwidth required to deliver the Education Digital Strategy due to a
more digitalised learning curriculum.  It is uncertain when this risk will arise.   
4 CONCLUSION 
4.1 This report summarises the key financial risks facing the Council.  There are a
number of Council wide risks and 41 departmental risks identified; one is
categorised as almost certain and 4 are categorised as likely.  The financial risks
are monitored routinely and actions put in place to continue to mitigate the risks.   
5 IMPLICATIONS 
5.1 Policy - None.
5.2 Financial -  The financial value of each risk is included within the
appendix.   
5.3 Legal -  None.
5.4 HR -  None.
5.5 Fairer Scotland Duty - None.
5.5.1 Equalities – protected
characteristics - 
None.
5.5.2 Socio-economic Duty -  None.
5.5.3 Islands -  None.
5.6 Climate Change - None.
5.7 Risk -  Financial risks are detailed within the appendix.
5.8 Customer Service -  None. 
Kirsty Flanagan
Executive Director/Section 95 Officer
13 January 2023 
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney 
APPENDICES
Appendix 1 – Detail of Department/Service financial risks 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 59

APPENDIX 1
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 DECEMBER 2022
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
Chief Executive's
Unit
Financial Services Council Tax Debt Collection
Recovery
Recovery of debt becomes more difficult to
pursue in the current economic climate.  This is
in relation to historical debt that has
accumulated over many years therefore any
adverse collection rates will impact on the year
end debt provision as opposed to the in-year
financial position, hence no forecast variance has
been reported within the current year.
Robust monitoring of arrangements with
debt collection agency and performance
against target collection rates.
5 500 5 345
Chief Executive's
Unit
Financial Services Housing Benefit Subsidy Loss of Housing Benefit Subsidy due to exceeding
LA error threshold.
Processes in place for handling of claims
accurately and efficiently.
1 125 1 125
Chief Executive's
Unit
Financial Services Sundry Debt Recovery Recovery of debt becomes more difficult to
pursue in the current economic climate. 
Robust monitoring of arrangements with
debt collection agency. Joint working with
Legal Services to assist services with the
recovery of aged debt.
3 85 3 85
Chief Executive's
Unit
Financial Services Non-Domestic Rates Relief Risk of demand changing due to legislative
changes outwith our control or new charitable
businesses. 
Outwith direct management control. 3 30 3 30
Executive Director
Douglas Hendry
Commercial Services Property - Central Repairs Increased demands on central repairs as a result
of the decrease in capital funding available and
increases in supplier/contractor charges.
Joint strategy with procurement colleagues
to reduce potential impact of
supplier/contractor charges.  Close
monitoring of central repairs budgets and
commitments and instructing only
essential repairs.
3 300 3 300
Executive Director
Douglas Hendry
Commercial Services Catering Costs – Changes to
Food and Drink in Schools
Standards
The Scottish Government reviewed the
regulations that govern the food and drinks
currently provided in schools. The proposed
changes  were published in June 2019 and were
implemented from Easter 2021.  The revised
standards focus on reducing sugar, reducing red
and red processed meat and increasing fibre.
Thus far, there has been an increase in costs and
a reduction in demand for school meals.
There is a need to work with Education
colleagues to ensure the maximum uptake
of school meals in secondary schools is
achieved.  This is very challenging given the
reduction in secondary school meal uptake
due to COVID.
4 150 4 150
Executive Director
Douglas Hendry
Commercial Services Catering Costs - Provision of
Meals to Early Years Children
The Children and Young People (Scotland) Act
places duties on Councils to provide meals in an
Early Years setting to entitled children where
sessions span over lunch time.  The total
quantum of funding of £1.2m may not be
sufficient to fund the additional costs depending
on uptake and the additional costs to support the
meal provision in partner provider settings.
Joint strategy with Education colleagues to
implement requirements and closely
monitor financial implications.  Costs likely
to be contained within overall early years
funding allocation.
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Catering Purchases Increased supplier charges.  This estimate does
not include the additional risk to food cost and
uptake from the changes to food and drink
standards in schools.
Joint strategy with procurement colleagues
to reduce potential impact.  Control food
wastage/portion controls.
4 100 4 100
As at 31 October 2022 As at 31 December 2022

Page 60

APPENDIX 1
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 DECEMBER 2022
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
As at 31 October 2022 As at 31 December 2022
Executive Director
Douglas Hendry
Commercial Services Catering - Implementation of
Universal Free School Meals in
Primary Schools
The Scottish Government may not give the local
authority adequate funds to support the policy
Catering Manager sits on National
Operational Delivery Group
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Surplus Properties Ongoing market difficulties lead to increased
numbers of surplus properties, there are residual
running costs associated with surplus properties.
One Council property team now in place. 3 50 3 50
Executive Director
Douglas Hendry
Commercial Services Leisure Service Level
Agreements
Increase in RPI resulting in requests for
additional funding.
Monitoring annual alteration to contract
RPI rate and mitigation through financial
forecasting and review of existing budget.
2 25 2 25
Executive Director
Douglas Hendry
Commercial Services Rental Income from Properties Due to current economic climate there may be
reduced ability to recover rental income from
leased properties or place suitable tenants in
properties as leases come to an end.
Management of leasehold properties by
Estates team, any issues with debt
recovery being dealt with in line with
Council debt recovery policy.
2 20 2 20
Executive Director
Douglas Hendry
Education Central Repairs Increased demands on budget as a result of
increase in statutory and emergency repairs and
increases in supplier/contractor charges.
Regular liaison with Property Services re
prioritisation and commitment of in-year
spend.
2 100 2 100
Executive Director
Douglas Hendry
Education ASN Support Demand for ASN support continues to increase,
resulting in an additional resource requirement.
The effect of COVID-19 has further increased
demand on this service.
Scottish Government has given additional
funding for "additional support needs
priority for learning" and this has been
built into the budget, this will help reduce
the demand risk 
3 100 3 100
Executive Director
Douglas Hendry
Education Pre-Five Units - retention of
partner providers
Failure in the commissioning or retention of pre-
five partner provider units to deliver 1140 hours
would result in an increased pressure on the
Council to deliver the service.
Annual financial appraisal; Support
network; Short-term cash injections.
3 100 3 100
Executive Director
Douglas Hendry
Education Legislative Requirements -
Children and Young People
(Scotland) Act - ELC 1140
hours
The Council has been required to deliver 1140
hours of Early Learning and Childcare since
August 2021.  The Scottish Government has
committed to funding this and the Council has
altered the implementation plan to align it to the
Scottish Government funding profile.  A risk
remains that actual costs of delivery exceed the
Government Grant in any given year.  For
example, if child numbers are higher than
estimated, this may require additional staffing
which has not been built into the staffing model
funded by Scottish Government.
Continuous monitoring and review of the
implementation plan, usage and resources.
3 100 3 100

Page 61

APPENDIX 1
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 DECEMBER 2022
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
As at 31 October 2022 As at 31 December 2022
Executive Director
Douglas Hendry
Education Legislative Requirements -
Education (Scotland) Act
Education (Scotland) Act 2000 was enacted
March 2016.  This places additional requirements
on Councils to carry out assessments of the need
for the provision of Gaelic Medium Primary
Education (GMPE) and the duty to support and
promote Gaelic Education. May lead to
additional staffing requirements.
Monitoring developments of the
implementation of the Act and statutory
guidance produced and adhered too.
3 50 3 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Hub DBDA/DBFM Schools  -
Litigation
Increased risk of the requirement to litigate to
conclude final capital contract payments due.
Monitoring claims and mitigation through
robust challenge of any additional claims.
2 150 2 150
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Contract RPI for NPDO and
Hub Schools
Increase in RPI would result in higher costs. Monitoring annual alteration to contract
RPI rate and mitigation through financial
forecasting and review of existing budget.
4 100 4 100
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO - Reduction in insurance
savings within NPDO Schools
Increase in insurance costs as a result of Covid-
19 and flood claims.
Monitoring annual alteration to contract
insurance rate and mitigation through
financial forecasting and review of existing
budget.
3 75 3 75
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Legal Services - Litigation Increased number of litigation cases. Ensure Legal Services are gateway to
access all legal advice and that advice is
sought at earliest opportunity.
3 50 3 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO/Hub DBFM contract
management efficiencies
Reduction in ability to generate contract
management efficiencies.
Monitoring annual efficiencies generated
and mitigation through robust contract
management and application of contract
specifications/requirements.
2 50 2 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Elections More than 1 by-election required outwith
standard election cycle.
Outwith direct management control. 3 45 3 45
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Licensing Reduced numbers of licensing applications
leading to reduced income.
Monitoring of trends and reporting the
financial impact in the budget monitoring.
4 30 4 30
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Children's Panel Increased number of referrals increasing costs
through increases in the running costs.
Maximise the use of council
facilities/resources for panel session in the
first instance.
1 10 1 10
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Legal Services Failure to minimise Council wide use of external
legal advice.
Ensure legal services are gateway to access
all legal advice.
1 10 1 10
Executive Director
Kirsty Flanagan
Customer Support Services Software Licences Potential risk of being under licensed for
software which will be identified via software
audits which would incur additional costs.
ICT security and compliance officer in post
and duties include review of systems to
ensure fully licenced. 
2 100 2 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Environmental Health- export
certificates
Downturn in requests for export certificates as a
result of UK withdrawal from EU, changes to
international trading agreements or business
economy. Reduction in demand creates a budget
pressure on environmental health budget.
Monitor income and resources required for
export health certificates/attestations
required to support the export market.
Continue with food safety regulation
activities associated and support at 3rd
country audits.  Pursue debt rigorously
with key customers through seeking
regular payments.
2 130 2 130

Page 62

APPENDIX 1
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 DECEMBER 2022
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
As at 31 October 2022 As at 31 December 2022
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Dangerous Buildings
interventions
Building Standards having to deal with an
increasing level of dangerous building work
which has significant financial implications for
Council.
Monitor activity and seek to recover costs
from the owner.
3 100 3 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning fees reduced by
Scottish Government
Scottish Government reducing planning fees due
to poor performance by the Planning Authority. 
Details of national Planning Performance Co-
ordinator and Fee Reform still awaited.
Maintain high levels of performance as
articulated by performance markers
detailed in Planning Performance
Framework annual report.
1 100 1 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning fee shortfalls Due to downturn in economic / building activity,
in particular renewable energy development and
other major developments could lead to planning
fee income shortfalls leading to revenue budget
pressures.
Current income levels are looking more
positive, however, we are dependent on
some high value applications coming in
which if don't materialise, will impact the
overall position.  Will continue to monitor
Development Management income and
expenditure tightly and investigate further
income generation streams.
1 50 1 50
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Building Warrant fee shortfalls Due to loss of commercial income and downturn
in economic / building activity, building warrant
fee income shortfalls leading to revenue budget
pressures.
Continue to monitor Building Standards
income and expenditure tightly and
investigate further income generation
streams. 
3 100 3 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Homelessness Temporary
Accommodation Income
Unpredictable number of Homeless applications.
Inability to recover rent.  Increase costs of
property maintenance and tenancy change over.
Provision of Housing Options information
and advice service to minimise number of
applicants proceeding to full homeless
application.  Implementation of Rapid
Rehousing Plan.
3 50 3 50
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Animal Health Carrying out livestock seizure to protect welfare
of the animals
Monitor activity and seek to recover costs
from the disposal of the animals.
1 10 1 10
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Airfields and Air Services -
usage
The PSO for the existing air service to Coll and
Colonsay operating from Connel Airport is due
for renewal in October 2023.  Possibility that this
will create a budget pressure for a new contract
to be established to serve the needs of the island
communities.
Tenders have been received and are
currently at the evaluation process with
Procurement.  Once this process is
complete, a more definitive position will be
known.
2 10 2 10
Executive Director
Kirsty Flanagan
Roads and Infrastructure
Services
Roads Maintenance - Bridges,
Culverts & Sea Defences
Extreme localised weather may result in loss of
bridge, culvert, road or sea defence.
The recent storm damage to Bute Sea Wall is
likely to cost in excess of £1m to repair so the
value on this risk has been updated for 22-23 in
recognition of the potential costs associated with
this risk
Routine inspections to deal with potential
weak areas - based on a stitch in time
repair regime.
3 750 3 750

Page 63

APPENDIX 1
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 DECEMBER 2022
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
As at 31 October 2022 As at 31 December 2022
Executive Director
Kirsty Flanagan
Roads and Infrastructure
Services
Residual Waste H&L and Tiree There is a potential increase to tipping fees and
haulage costs for H&L residual waste.  The
Council’s supplier Barr Environmental (contract
to end of 2023) lost a tribunal relating to the
underpayment of landfill tax, which may have led
to the Council having to source alternatives at a
higher cost.    Barr appealed the decision which
was heard in the Spring and they won the case
which should have reduced or eliminated this
financial risk.  However, the Scottish
Government laid an Amendment Order on Friday
1 July 2022 which came into force at 1700 on 1
July which indicates that Landfill tax will be due
on materials previously not chargeable and we
have now received notification of an increase in
the cost which officers are currently assessing
Officers currently assessing the potential
impact on the Council.
Executive Director
Kirsty Flanagan
Roads and Infrastructure
Services
Roads Materials - Bitumen Increased cost of asphalt material due to price of
crude oil rising.  Discussions emerging from the
industry about possible rationing of bitumen
which, if applied, will affect our programmes due
to availability
Increased costs are currently being
managed but with further increases likely,
this is being closely monitored by
managers to evaluate the impact.
3 400 3 400
Executive Director
Kirsty Flanagan
Roads and Infrastructure
Services
Winter Maintenance Adverse weather conditions which require
greater than budgeted number of gritting runs.
Monitor weather conditions and apply
gritting policy to minimise costs.
3 365 3 365
Executive Director
Kirsty Flanagan
Roads and Infrastructure
Services
Roads Maintenance - Roads
Network
Adverse weather conditions result in
deterioration of the road network necessitating
greater spend on repair of defects.
Manage maintenance budgets to ensure
that spend is prioritised to deal with safety
defects.
3 230 3 230
Executive Director
Kirsty Flanagan
Roads and Infrastructure
Services
Street Lighting Age of lighting stock requires greater
maintenance as health and safety becomes a
consideration.
Manage maintenance budgets to ensure
that spend is prioritised to deal with safety
defects.
3 100 3 100
Executive Director
Kirsty Flanagan
Roads and Infrastructure
Services
Ferry Services - income Changes to ferry services resulting in reduced
passenger income.
Closely monitor passenger number
information coming from CalMac to
identify any emerging trends with reducing
passenger numbers.
3 40 3 40
41 5,090 41 4,935

Page 64

ARGYLL  AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY & RESOURCES COMMITTEE
16 FEBRUARY 2023
CAPITAL BUDGET MONITORING REPORT – 31 DECEMBER 2022
1.0 EXECUTIVE SUMMARY
1.1 This report provides an update on the position of the capital budget as at 31
December 2022. The report provides information on the financial position in
respect of the capital plan and also the performance in terms of delivery of
capital plan projects. 
1.2 Financial Position:
 Current Year to Date – actual net expenditure to date is £19,846k
compared to a budget for the year to date of £19,186k giving rise to an
overspend for the year to date of £660k (3.44%).
 Forecast Outturn for 2022-23 – forecast net expenditure for the full
financial year is £33,440k compared to an annual budget of £39,014k
giving rise to a forecast underspend for the year of 5,574k (14.29%).
 Total Capital Plan – forecast total net project costs on the total capital
plan are £180,736k compared to a total budget for all projects of
£180,009k giving rise to a forecast overspend for the overall capital plan
of £727k (0.40%).
1.3 Project Delivery:
 Asset Sustainability – Out of 94 projects there are 81 projects (86%) on
track, 3 projects (3%) off track but recoverable and 10 projects off track
(11%).
 Service Development - Out of 41 projects there are 37 projects (90%) on
track, 3 projects (7.5%) off track but recoverable and 1 project (2.5%) off
track.
 Strategic Change – Out of 27 projects there are 22 projects (81%) on
track, 2 projects (7.5%) are off track but recoverable and 3 projects (11.5%)
off track.
1.4
1.5
The Capital Programme is funded by various income streams as detailed in
Appendix 5. 
Originally the Council was projecting £1,387k of capital receipts this financial
year. However, to date only £170k has been received and it is unlikely that the
original projection of £1,387k will be met. The Estates team are currently in the
process of updating their asset sale projections as part of the budget setting
process and this is likely to result in a lower level of anticipated capital receipts
over the life of the programme.

Page 65

ARGYLL  AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY & RESOURCES COMMITTEE
16 FEBRUARY 2023
CAPITAL BUDGET MONITORING REPORT – 31 DECEMBER 2022
2.0 INTRODUCTION
2.1
2.2
2.3
2.4
2.5
This report provides an update on the position of the capital budget as at 31
December 2022. The report provides information on the financial position in
respect of the capital plan and also the performance in terms of delivery of capital
plan projects. 
Following the decision at Policy and Resources Committee on 9 December 2021,
the Rothesay Pavilion project is on pause whilst potential funding options are being
considered. The financial information included within this report therefore excludes
amounts relating to Rothesay Pavilion.  
A £1m cost pressure was identified during 2021-22 in relation to repairs to the
A884 Ardbeg Sea Wall, where severe storm damage resulted in failure of the sea
wall on Bute. Emergency works were carried out and a permanent solution is
currently being developed. Additional funding of £1m was allocated for this
purpose at the Council meeting on 24 February 2022 however there remains a risk
that costs will exceed this. It was agreed at Environment, Development and
Infrastructure Committee on 2 June 2022 that the Chair would approach the
Scottish Government with a view to securing additional resources to support the
scheme.
Project Managers were asked to identify specific Covid-19 impacts on the capital
programme. At the budget meeting on 25 February 2021, the Council agreed to
provide £2.5m of funding and following agreement at the Policy and Resources
Committee on 14 October 2021, this, plus a further £0.146m, was added to the
capital programme.
Furthermore, at the budget meeting on 24 February 2022, an additional £3.9m was
set aside for future capital contract increases. This includes up to £1.2m for
Campbeltown Flood Scheme, the final costs of which are estimated to be
£15.215m. The Scottish Government will fund 80% of scheme costs with the
Council expected to contribute an estimated £3.043m.
The impact of the pandemic along with the UK exit from the European Union, the
Russian invasion of Ukraine and sanctions on Russian owned entities has seen
significant price increases as well as disruptions to the supply chain and longer
lead in times. The increased rate of inflation impacts costs such as energy prices,
labour, packaging and transport. These all have an effect on the overall contract
price and make it extremely challenging to manage expenditure and the availability
of supply.
As a result of this it should be noted that there are likely to be other significant
financial impacts which are not quantifiable at this stage, as follows: 
 Rothesay Pavilion – project currently paused due to increased costs as a
result of the main contractor being placed into administration in March 2020.
 Harbour Investment Programme – likely to be contractual cost increases in
future years (expected to be funded from increased fees and charges).

Page 66

4.0 CURRENT YEAR TO DATE FINANCIAL POSITION 
4.1 
4.2
Overall Position 
Actual net expenditure to date is £19,846k compared to a budget for the year to
date of £19,183k giving rise to an overspend for the year to date of £660k (3.44%). 
Project/Department Position 
The table below shows the year to date net expenditure against the year to date
budget by project type and service: 
Project Type:
Year to
Date
Budget    
£'000
Year to
Date
Actual    
£'000
Variance       
£'000
Asset Sustainability 11,339 11,380 (41)
Service Development 2,674 2,698 (24)
Strategic Change 5,173 5,768 (595)
Total  19,186 19,846 (660)
Service:      
ICT 647 647 0
Education 3,742 3,724 18
Live Argyll 171 175 (4)
Health & Social Care Partnership 152 155 (3)
Shared Offices 123 137 (14)
Roads & Infrastructure 9,494 9,559 (65)
Development & Economic Growth 1,386 1,383 3
CHORD 3,471 4,066 (595)
Total 19,186 19,846 (660) 
Material variances are explained in Appendix 1 and there are a number of small
variances contributing to the year to date overspend. 
 Helensburgh Waterfront Development – commercial negotiations are
ongoing with the main contractor to determine the financial impact.  
 Universal Free School Meals – delayed roll out to P6 and P7 and uncertain
capital funding levels available from Scottish Government (delay not
mentioned as part of Resource Spending Review). 
 Other general construction inflationary increases.
3.0 RECOMMENDATIONS 
3.1 Note the contents of this report and the financial summaries as detailed in
Appendix 8 and approve the proposed changes to the capital plan detailed in
Appendix 4.

Page 67

5.0  FORECAST OUTTURN 2022-23 
5.1  Overall Position 
Forecast net expenditure for the full financial year is £33,440k compared to an annual
budget of £39,014k giving rise to a forecast underspend for the year of £5,574k  
(14.29%). 
5.2 Project/Department Position 
The table below shows the forecast expenditure and budget for the year by project
type and service. 
Project Type:
Annual
Budget            
£'000
Forecast
Outturn        
£'000 
Forecast
Variance 
COVID-19
Related       
£'000
Forecast
Variance 
Non
COVID-19
Related       
£'000
Forecast
Variance         
£'000
Asset Sustainability 21,558 18,128 0 3,430 3,430
Service Development 4,626 4,704 0 (78) (78)
Strategic Change 12,830 10,608 0 2,222 2,222
Total  39,014 33,440 0 5,574 5,574
Service:          
ICT 1,243 1,243 0 0 0
Education 6,336 6,348 0 (12) (12)
Live Argyll 580 566 0 14 14
Health & Social Care
Partnership 613 638 0 (25) (25)
Shared Offices 4,240 2,256 0 1,984 1,984
Roads & Infrastructure 19,481 16,308 0 3,173 3,173
Development &
Economic Growth 2,602 2,602 0 0 0
CHORD 3,919 3,479 0 440 440
Total 39,014 33,440 0 5,574 5,574 
Material variances are explained in Appendix 2 and there are a number of smaller
variances contributing to the forecast underspend.

Page 68

6.0 TOTAL PROJECT COSTS
6.1 Overall Position
Forecast total net project costs on the total capital plan are £180,736k compared to
a total budget for all projects of £180,009k giving rise to a forecast overspend for
the overall capital plan of £727k (0.40%). 
6.2 Project/Department Position
The table below shows the forecast expenditure and budget for the total capital
plan by project type and service. 
Project Type:
Capital
Plan
Budget
£'000
Forecast
Project
Costs
£'000
Capital
Plan
Variance
COVID-19
Related
£'000
Capital
Plan
Variance
Non
COVID-
19
Related
£'000
Total
Capital
Plan
Variance
£'000
Asset Sustainability 52,093 52,100 0 (7) (7)
Service Development 19,261 19,339 0 (78) (78)
Strategic Change 108,655 109,297 0 (642) (642)
Total 180,009 180,736 0 (727) (727)
Service:
ICT 5,007 5,007 0 0 0
Education 42,072 42,084 0 (12) (12)
Live Argyll 3,368 3,374 0 (6) (6)
Health & Social Care
Partnership 4,222 4,232 0 (10) (10)
Shared Offices 21,507 21,514 0 (7) (7)
Roads & Infrastructure 54,711 54,777 0 (66) (66)
Development &
Economic Growth 5,284 5,284 0 0 0
CHORD 43,838 44,464 0 (626) (626)
Total 180,009 180,736 0 (727) (727)
Material variances are explained in Appendix 3 and there are a number of
smaller variances leading to the forecast overspend.

Page 69

7.0  TOTAL PROJECT PERFORMANCE 
7.1 Overall Position 
There are 162 projects within the Capital Plan, 140 are Complete or On Target, 8
are Off Target and Recoverable and 14 are Off Track.
7.2  Project Position 
The table below shows the Performance Status of the Projects in the Capital Plan. 
Project Type:
Complete/
On Target
Off Target/
Recoverable
Off
Target/
Problem Total
Asset Sustainability 81 3 10 94
Service Development 37 3 1 41
Strategic Change 22 2 3 27
Total 140 8 14 162
Service:        
ICT 6 0 1 7
Education 29 1 0 30
Live Argyll 27 1 0 28
Health & Social Care
Partnership 18 1 0 19
Shared Offices 18 0 4 22
Roads & Infrastructure 25 3 7 35
Development & Economic
Growth 15 1 0 16
CHORD 2 1 2 5
Total 140 8 14 162

Page 70

7.3  Chart of Performance Status 
The graph provides a view of the Performance Status of the Projects included  in
the Capital Plan: 
0
10
20
30
40
50
60
70
80
90
100
Asset Sustainability Service Development Strategic Change
Number
Off Target/
Problem
Off Target/
Recoverable
Complete/ On
Target

Page 71

8.0 OFF TRACK PROJECTS 
8.1  The Off Track projects are noted in the table below and variance reports are
included in Appendix 6. 
Project Type Project What is Off
Track?
Explanation
Major Projects Helensburgh
Waterfront
Development 
Current Year
and total
project
expenditure
Overspend due to
multiple global issues
as well as delays in
connection to mains
electricity supply
which led to
temporary power
supplies to maintain
the timeliness of the
program.  Elements
relating to COVID-19
currently being
projected and will be
updated for next
update.
Asset
Sustainability 
Bowmore Area Office Current year
expenditure
Budget slipped due to
timescale delays.
Slippage from 22-23
to 23-24.
Asset
Sustainability
Burnett Building Current year
expenditure
Budget slipped due to
timescale delays.
Slippage from 22-23
to 23-24.
Asset
Sustainability
Kilmory Castle Current year
expenditure
Budget slipped due to
timescale delays.
Slippage from 22-23
to 23-24.
Asset
Sustainability 
Our Modern
Workspace
Current year
expenditure
Budget slipped due to
timescale delays.
Slippage from 22-23
to 23-24.

Page 72

Asset
Sustainability
Flood Prevention Current year
expenditure
Project timescales for
construction has
caused slippages into
23-24 following the
studies provided by
consultant.
Asset
Sustainability
Costal Change
Adaptation
Current year
expenditure
Budget slipped due to
timescale delays.
Slippage from 22-23
to 23-24.
Asset
Sustainability
Bute Sea Wall
Repairs
Current year
expenditure
Slippage from 22-23
to 23-24 due to
timescale delays.
Construction contract
to be progressed in
2023/24.
Asset
Sustainability
Helensburgh Flood
Mitigation
Current year
expenditure
Tender abandoned
due to high costs
received. Slipped
budget into 23-24 to
allow project to be
retendered.
Asset
Sustainability
Bridge Strengthening  Current year
expenditure
Acceleration from 23-
24 to 22-23.
Reversed a portion of
the November
slippage to cover CY
costs which were still
to clear the ledger.
Asset
Sustainability
Local Bridge
Maintenance Fund
Current year
expenditure
Project delayed to
allow appropriate
studies to be
undertaken in
advance of
construction. Slippage
from 22-23 to 23-24.

Page 73

9.0
9.1
Service
Development
Oban Depot
Development Project
Current year
expenditure
and total
project
expenditure
Project is overspent in
22-23 and total
project lifetime.
Strategic
Change
Campbeltown Flood
Scheme
Current year
expenditure
Slippage from 22-23
to 23-24 due to
change in contractor
cash flow predictions.
CHORD Kilmory Business
Park Phase 2AA
Current year
expenditure
Delays in planning
application has
caused slippage from
22-23 to 23-24. Works
anticipated to start at
the end of FQ2 23-24
STRATEGIC CHANGE PROJECTS
Appendix 7 gives detailed information in respect of the Strategic Change
Projects within the Capital Plan. The appendix gives details of the forecast cost
of each project against the approved budget, the start and anticipated
completion date of the project and an assessment of the risks of the project and,
if these are not green, gives an explanation of the problem.
10.0
10.1
CHANGES TO CAPITAL PLAN
The table below shows proposed changes to the Capital Plan at summary level
which include slippages, accelerations and virements. Explanations relating to
the specific projects involved can be seen in Appendix 4.
The updated capital plan incorporating these proposed changes can be found in
Appendix 9.

Page 74

Department
Prev.
Agreed
Changes
2022-23
2022-
23
2023-
24
2024-
25
Future
Years
Total
Capital
Plan
£’000 £’000 £’000 £’000 £’000 £’000
Asset
Sustainability (4,486) (3,437) 3,437 0 0 0
Service
Development (874) 0 0 0 0 0
Strategic Change (32,024) (2,864) 2,864 0 0 0
Total (37,384) (6,301) 6,301 0 0 0
Service:
ICT (275) 0 0 0 0 0
Education 239 0 0 0 0 0
Live Argyll (655) (20) 20 0 0 0
Health & Social
Care Partnership (1,494) 15 (15) 0 0 0
Shared Offices 43 (1,991) 1,991 0 0 0
Roads &
Infrastructure (35,686) (3,239) 3,239 0 0 0
Development &
Economic Growth (718) 0 0 0 0 0
Major Projects 1,162 (1,066) 1,066 0 0 0
Total (37,384) (6,301) 6,301 0 0 0 
11.0   FUNDING 
11.1 
11.2
12.0
12.1
12.2
12.3
The Capital Programme is funded by various income streams as detailed in
Appendix 5. Additional funding of £96,000 has been drawn down from
Earmarked Reserves to fund the Lochgilphead Primary School Demolition.
Originally the Council was projecting £1,387k of capital receipts this financial
year. However, to date only £170k has been received and it is unlikely that the
original projection of £1,387k will be met. The Estates team are currently in the
process of updating their asset sale projections as part of the budget setting
process and this is likely to result in a lower level of anticipated capital receipts
over the life of the programme. 
IMPLICATIONS
Policy – Monitors progress against the capital plan. 
Financial – Monitors funding and commitments of the capital plan.
Legal – Available funding may not address all Statutory and Regulatory
requirements in relation to Health and Safety.

Page 75

12.4
12.5
12.6
12.7
12.8
HR – Available funding may have an impact on the sustainability of the Property
Design Team and Infrastructure Design Team. 
Fairer Scotland Duty – None. 
12.5.1     Equalities – protected characteristics – None.
12.5.2     Socio-economic Duty – None. 
12.5.3     Islands – None. 
Climate Change – The Council is committed to addressing climate change via
projects within the capital plan. 
Risk – There are risks around increasing capital contract costs and the level and
timing of capital receipts. 
Customer Service – None.
Kirsty Flanagan 
Executive Director / Section 95 Officer
13 January 2023
Policy Lead for Finance and Commercial Services – Councillor Gary
Mulvaney
APPENDICES
- Appendix 1 – Year To Date finance variance explanations
- Appendix 2 – Forecast Outturn variance explanations
- Appendix 3 – Total Project finance variance explanations
- Appendix 4 – Changes to Capital Plan and Financial Impact
- Appendix 5 – Capital Funding
- Appendix 6  - Off Track project variance reports
- Appendix 7 - Cumulative spend, completion dates and risks relating
to significant capital projects.
- Appendix 8 - Financial Summary – Overall
- Financial Summary – Executive Director Kirsty Flanagan
- Financial Summary – Executive Director Douglas Hendry
- Appendix 9 - Updated/Revised Capital Plan
For further information contact: Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 76

APPENDIX 1 – Year to Date Financial Variance Explanations
Listed below are the projects where the variance is +/- £50k.
Project
YTD
Budget
£’000
YTD
Actual
£’000
(Over)/
Under
Variance       
£’000
Explanation
Helensburgh Waterfront Development 3,078 3,704 (626) Overspend on project, details provided in Variance report.
Oban Depot Development Project 76 17 (59)
Overspend on project due to additional requests made by the service for the
project. These additional works are to be funded from revenue, the transfer
is still to take place.
Other variances under £50k              25 Total value of non-material variances less than +/-£50k
Total   (660)

Page 77

APPENDIX 2 – Outturn Variance Explanations
Listed below are the projects where the current year variance is +/- £50k. 
Project 
Annual
Budget
£’000
Outturn
£’000 
(Over)/ Under
Forecast
Variance
COVID-19
Related         
£’000
(Over)/ Under
Forecast
Variance Non
COVID-19
Related         
£’000
Total
(Over)/
Under
Forecast
Variance         
£’000
Explanation
Helensburgh Waterfront
Development  3,078 3,704  0 (626) (626) Overspend on project, details provided in Variance
report.
Oban Depot Development 17 76  0 (59) (59)
Overspend on project due to additional requests
made by the service for the project. These
additional works are to be funded from revenue,
the transfer is still to take place.
Burnett Building 110 0  0 110 110 Budget slipped due to timescale delays.
Kilmory Castle 1,368 2  0 1,366 1,366 Budget slipped due to timescale delays.
Flood Prevention 349 10  0 349 349
Project timescales for construction has caused
slippages into 23-24 following the studies
provided by consultant.
Bridge Strengthening  156 215  0 (59) (59) Partial reversal of November slippage to cover
costs which were still to come through.

Page 78

Campbeltown Flood Scheme 5,756 3,958 0 1,798 1,798 Slippage due to change in contractor cash flow
predictions.
Helensburgh Flood Mitigation 332 4 0 328 328 Delays in tender process has caused slippage
into 23-24
Local Bridge Maintenance
Fund 712 475 0 237 237 Project delayed to allow appropriate studies to
be undertaken in advance of construction.
Bute Sea Wall Repairs 575 148 0 427 427 Project timescale delays has caused budget to
slip to 23-24
Bowmore Area Office 76 0 0 76 76 Project timescale delays has caused budget to
slip to 23-24
Kilmory Business Park Phase
2AA 1,120 54 0 1,066 1,066
Project timescale delays has caused budget to
slip to 23-24
Coastal Change Adaptation 159 0 0 159 159
Project timescale delays has caused budget to
slip to 23-24
Our Modern Workspace 549 110 0 439 439 Project timescale delays has caused budget to
slip to 23-24
Other variances under £50k  0 (37) (37) Total value of non-material variances less than +/-
£50k.
Total 0 5,574 5,574

Page 79

APPENDIX 3 – Total Project Finance Variances
Listed below are the projects where the total project variance is +/- £50k.
Project
Capital
Plan
Budget
£’000
Forecast
Project
Costs
£’000
(Over)/ Under
Forecast
Variance
COVID-19
Related     
£’000
(Over)/ Under
Forecast
Variance Non
COVID-19
Related     
£’000
Total (Over)/
Under
Forecast
Variance   
£’000
Explanation
Helensburgh Waterfront
Development  22,740 23,366 0 (626) (626) Overspend on project, details provided in Variance
Report
Oban Depot Development 2,117 2,176 0 (59) (59) Overspend on project due to additional requests
made by the service for the project. These additional
works are to be funded from revenue, the transfer is
still to take place.
Other variances under £50k (42) (42) Total value of non-material variances less than +/-
£50k. Project Managers are working to reduce these
small individual overspends by identifying
underspends elsewhere within the capital plan.
Total (727) (727)

Page 80

APPENDIX 4 – Changes to Capital Plan and Financial Impact
OVERALL COST CHANGES
Project
2022-
23
£’000
2023-
24
£’000
2024-
25
£’000
Future
Years
£’000
Total
Capital Plan
£’000
Recommendation Explanation
Total Cost Changes 0 0 0 0 0
SLIPPAGES AND ACCELERATIONS
Project 2022-23
£’000
2023-24
£’000
2024-25
£’000
Future
Years
£’000
2022-23
Slippage
Related to
COVID-19
£’000
2022-23
Slippage
Related
to Non
COVID-
19
£’000
Total
2022-23
£’000
Recommendation Explanation
Kilmory Business
Park Phase 2AA (1,066) 1,066 0 0 0 (1,066) (1,066)
Slip budget into
future years.
Budget slipped to 23-24 due to
timescales and project
capacity
Flood Prevention (349) 349 0 0 0 (349) (349)
Slip budget into
future years.
Project slipped to 23-24 due to
timescales and project
capacity 
Coastal Change
Adaption (159) 159 0 0 0 (159) (159) Slip budget into
future years. Project slipped to 23-24 due to
no valid tender bidders.
Bute Sea Wall
Repairs (427) 427 0 0 0 (427) (427) Slip budget into
future years. Project timescale delays has
caused budget to slip to 23-24
Helensburgh Flood
Mitigation (328) 328 0 0 0 (328) (328) Slip budget into
future years. Project timescale delays has
caused budget to slip to 23-24
Local Bridge
Maintenance Fund (237) 237 0 0 0 (237) (237)
Slip budget into
future years. Project timescale delays has
caused budget to slip to 23-24
Campbeltown Flood
Scheme (1,798) 1,798 0 0 0 (1,798) (1,798)
Slip budget into
future years. Project timescale delays has
caused budget to slip to 23-24
Bridge
Strengthening 59 (59) 0 0 0 59 59
Accelerate from
2023-24 Reverse part of slippage
processed in previous report to

Page 81

cover costs still to be
processed.
Greenwood/Woodla
nds 15 (15) 0 0 0 15 15
Accelerate from
2023-24 Accelerate from 23-24 to cover
forecasted expenditure. 
Bowmore Area
Office (76) 76 0 0 0 (76) (76)
Slip budget into
2023-24 Project timescale delays has
caused budget to slip to 23-24
Burnett Building (110) 110 0 0 0 (110) (110)
Slip budget into
2023-24 Project timescale delays has
caused budget to slip to 23-24
Our Modern
Workspace (439) 439 0 0 0 (439) (439)
Slip budget into
2023-24
Project timescale delays has
caused budget to slip to 23-24
Kilmory Castle (1,366) 1,366 0 0 0 (1,366) (1,366)
Slip budget into
2023-24
Project timescale delays has
caused budget to slip to 23-24
Victora Hall,
Campbeltown (20) 20 0 0 0 (20) (20)
Slip budget into
2023-24 Project timescale delays has
caused budget to slip to 23-24
Total Slippages
and Accelerations
(6,301) 6,301 0 0 0 (6,301) (6,301)
Net Impact of
Changes
(6,301) 6,301 0 0 0 (6,301) (6,301)

Page 82

CAPITAL PROGRAMME FUNDING Appendix 5
Estimated
Capital
Funding
Carry
Forwards
from 21-22
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 21-22
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 21-22
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
General Capital Grant 9,569 0 0 0 9,569 9,569 0 0 157 9,726 9,569 0 0 235 9,804
Transfer to Revenue for Private Sector Housing Grant (PSHG) -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033
Capital Receipts 1,387 0 0 0 1,387 1,095 0 0 0 1,095 0 0 0 0 0
Flooding Allocation 155 0 0 0 155 155 0 0 0 155 155 0 0 0 155
Ring Fenced Capital Grant 4,656 2,722 0 268 7,646 0 5,728 0 0 5,728 0 0 0 0 0
Restricted Funding 1,486 609 -210 2,876 4,761 1,150 0 210 0 1,360 0 0 0 0 0
Funded by Reserves 3,145 4,388 -1,256 1,385 7,662 36 172 -75 0 133 0 0 1,331 0 1,331
Additional Funding from Revenue 0 0 0 12 12 0 0 0 25 25 0 0 0 0 0
Insurance 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Harbour Investment Programme 31,180 2,484 -28,038 0 5,626 16,900 0 5,335 0 22,235 31,600 0 -4,575 0 27,025
Prudential Borrowing 15,528 3,352 -17,241 -350 1,289 5,006 -1,429 17,241 -25 20,793 27 0 0 0 27
Loans Fund Review 0 4,025 0 0 4,025 0 0 0 0 0 0 0 0 0 0
COVID Funding 1,640 2,167 0 0 3,807 0 0 0 0 0 0 0 0 0 0
67,713 19,747 -46,745 4,191 44,906 32,878 4,471 22,711 157 60,217 40,318 0 -3,244 235 37,309
BREAKDOWN OF ADDITIONAL FUNDING
Additional Funding 2022-23 2023-24 Reported
C'town Museum LA income 40 Live Argyll Jun-22
H&L/Rosneath Cycleways 140 Jun-22
Nature Restoration Fund 238 Jun-22
Rothesay Pontoons 315 Grant Funding Jun-22
Ardrishaig North 280 Grant Funding Jun-22
Lismore Ferry 7 External Income Jun-22
Lochgilphead PS Demolition 11 Reserves Jun-22
Fleet Management 499 Reserves Jul-22
Roads Reconstruction 958 STTS Jul-22
Gartrecfk Landfill 640 Reserves Aug-22
Lochgilphead Primary School Demolition 143 Reserves Sep-22
Lochgilphead Depot 37 Revenue Funding Oct-22
Kilmory Business Park 979 Grant Funding Oct-22
Helensburgh Waterfront Development 183 Grant Funding Nov-22
Lochgilphead PS Demolition 96 Reserves Dec-22
Tobermory Car Park -375 Grant Funding Dec-22
Total 4,191 0
2022-23
SPT
Scottish Government
2024-252023-24
Source

Page 83

OFF TRACK PROJECT Appendix 6
Project Name:
Bridge Strengthening & Replacement Programme
and
Local Bridge Maintenance Fund
Project Manager: Elsa Simoes Risk:  Low
Initial Start Date:  2000 Proposed End Date:  Ongoing
How was this project initially funded?
Block Allocation
Please detail any additional funding.  
Local Bridge Maintenance Fund – Scottish Government Funding
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Jan 23:
(BSRP: £59k pulled forward from 23/24 to 22/23 – reversed a portion of November slippage to cover CY costs)
LBMF: £237k slipped from 22/23 to 23/24 
Dec 22:
BSRP: £1,297k slipped from 22/23 to 23/24
LBMF: £525k slipped from 22/23 to 23/2
What has caused the issue outlined above?
Jan 22:
Due to departmental workload, construction contracts for a number of projects have been moved from 2022/23 to 2023/24:
 00019-41 A815-230 Cothouse Bridge – LBMF
 00019-38 B840-140 Ardchonnell Bridge - LBMF
 00019-43 B842-150 Whitestone Bridge - LBMF
Capital Monitoring Report updated accordingly.
Dec 22:
Infrastructure Design successfully secured £5.45m funding from Scottish Government’s Local Bridge Maintenance Fund to deliver strengthening & replacement schemes not able to be funded in the short term through the
existing capital Bridge Strengthening & Replacement Programme due to the large estimated costs.
Following the award of a number of Services Contracts to progress studies for the four replacement schemes and five strengthening schemes under LBMF, the programme for delivery of the schemes has been revised
with a clear timeline for delivery developed.
Capital Monitoring Report updated accordingly.
What action will be taken to rectify this issue?
Jan 23:
Budgets will be slipped into 23-24 accordingly.
Dec 22:
Budgets will be slipped into 23-24 accordingly.
What are the implications of the action proposed?
Jan 23:
None – projects on track to be delivered.
Dec 22:
None – projects on track to be delivered.

Page 84

OFF TRACK PROJECT Appendix 6
Project Name:
Bute Seawall Repairs
Project Manager: Elsa Simoes Risk:  Low
Initial Start Date:  Dec 2021 Proposed End Date:  Ongoing
How was this project initially funded?
Block Allocation
Please detail any additional funding.
N/A
Previously Reported Committee and Date:
N/A
Next Reported Committee and Date:
N/A
Why is the project classified as off target?
Jan 23:
£427k slipped from 22/23 to 23/24
Dec 22:
£175k slipped from 22/23 to 23/24
What has caused the issue outlined above?
Jan 23:
Temporary Works with GeoRope still ongoing.
Permanent Works still under surveys, consultation and design stage.
Construction contract to be progressed in 2023/24
Capital Monitoring Report updated accordingly.
Dec 22:
Temporary Works with GeoRope ongoing.
Permanent Works still under surveys, consultation and design stage.
£175k moved to next FY to allow tender to be progressed into 2023/24 (rather than only 2022/23)
Capital Monitoring Report updated accordingly.
What action will be taken to rectify this issue?
Jan 23:
Budgets will be slipped into 23-24 accordingly.
Dec 22:
Budgets will be slipped into 23-24 accordingly.
What are the implications of the action proposed?
Jan 23:
None – project on track to be delivered.
Dec 22:
None – project on track to be delivered.

Page 85

OFF TRACK PROJECT Appendix 6
Project Name:  Campbeltown Flood Scheme Project Manager: Jamie Salmon Risk:  Low
Initial Start Date:  June 2016 Proposed End Date:  Mar 2026
How was this project initially funded?  Scottish Government Grant 80%/Council Contribution 20% Please detail any additional funding.
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Move £1.798m (of £5.756m) from FY22/23 to FY 23/24
What has caused the issue outlined above?
Jan 23
Move £1.798m (of £5.756m) from FY22/23 to FY 23/24
Full update of future years forecasts – Total Project Forecast and Budget remain the same
 Contractor submitted updated Cashflow prediction considering full programming of works phases.
 Following reprogramming of works costs for Public Utility works moved from FY22/23 to FY23/24.
 Still awaiting Consultant’s cashflow predictions which shall allow further refining of project cashflow.
 Capital Monitoring Report updated accordingly.
Dec 22
Move £3,342m (of £9.098m) from FY22/23 to FY 23/24:
 Later award of Construction Contract than programmed.
 Phasing of works confirmed by Contractor which allows development of associated cashflow prediction.
 Construction commenced on site and Contractor submitted Cashflow prediction.
 Capital Monitoring Report updated accordingly.
What action will be taken to rectify this issue?
Jan 23
Move £1.798m  from FY22/23 to FY 23/24:
 Budget will be slipped into 23-24 accordingly.
 Full update of future years forecasts – Total Project Forecast and Budget remain the same
 Slip / Pull forward accordingly
Dec 22
Move £3,342m (of £9.098m) from FY22/23 to FY 23/24:
 Budget will be slipped into 23-24 accordingly.
What are the implications of the action proposed?
Jan 23
Move £1.798m (of £5.756m) from FY22/23 to FY 23/24 & Full update of future years forecasts – Total Project Forecast and Budget remain the same
 None – project on track to be delivered as per outline business case.
Dec 22
Move £3,342m (of £9.098m) from FY22/23 to FY 23/24:
 None – project on track to be delivered as per outline business case.

Page 86

OFF TRACK PROJECT Appendix 6
Project Name:
Flood Prevention 0100
Project Manager: Elsa Simoes Risk:  Low
Initial Start Date:  2020/21 Proposed End Date:  Ongoing
How was this project initially funded?
Block Allocation
Please detail any additional funding.
N/A
Previously Reported Committee and Date:
N/A
Next Reported Committee and Date:
N/A
Why is the project classified as off target?
Jan 23:
£349k slipped from 22/23 to 23/24
Dec 22:
£115k slipped from 22/23 to 23/24
What has caused the issue outlined above?
Jan 23:
£349k moved to next FY for Ettrickdale, Tigh Dearg Road, Lochavullin, Rothesay FPS construction following ongoing studies by Consultant (rather than construction in 2022/23).
Capital Monitoring Report updated accordingly.
Dec 22:
£115k moved to next FY for Ettrickdale construction following ongoing studies by Consultant (rather than construction in 2022/23).
Capital Monitoring Report updated accordingly.
What action will be taken to rectify this issue?
Jan 23:
Budgets will be slipped into 23-24 accordingly.
Dec 22:
Budgets will be slipped into 23-24 accordingly.
What are the implications of the action proposed?
Jan 23:
None – project on track to be delivered.
Dec 22:
None – project on track to be delivered.

Page 87

OFF TRACK PROJECT Appendix 6
Project Name:
Helensburgh Flood Mitigation
Project Manager: Elsa Simoes Risk:  Low
Initial Start Date:  2018/19 Proposed End Date:  Ongoing
How was this project initially funded?
Block Allocation
Please detail any additional funding.
N/A
Previously Reported Committee and Date:
N/A
Next Reported Committee and Date:
N/A
Why is the project classified as off target?
Jan 23:
£328k slipped from 22/23 to 23/24
Dec 22:
£100k slipped from 22/23 to 23/24
What has caused the issue outlined above?
Jan 23:
Tender for works abandoned due to high costs received. To be retendered in 23-24.
£328k moved to next FY to allow scheme to be retendered. 
Capital Monitoring Report updated accordingly.
Dec 22:
Tender for works abandoned due to high costs received. To be retendered in 22-23.
£100k moved to next FY to allow scheme to be retendered 
Capital Monitoring Report updated accordingly.
What action will be taken to rectify this issue?
Jan 23:
Budgets will be slipped into 23-24 accordingly.
Dec 22:
Budgets will be slipped into 23-24 accordingly.
What are the implications of the action proposed?
Jan 23:
None – project on track to be delivered.
Dec 22:
None – project on track to be delivered.

Page 88

OFF TRACK PROJECT Appendix 6
Project Name:  Kilmory Business Park – Phase 2AA: Essential
Infrastructure Works
Project Manager:  John Gordon Risk: Low
Initial Start Date:  1 April 2021 Proposed End Date:  September 2024
How was this project initially funded?
Argyll & Bute Council (Crown Estates) £   150,000
Highlands & Islands Enterprise £   150,000
M&K MacLeod Ltd £   850,000
Scottish Government (RCGF) £   650,000
Total £1,800,000
Please detail any additional funding.
Scottish Government (RCGF) £   179,000
Total £1,979,000
Previously Reported Committee and Date:
Policy & Resources Committee 8-Dec-22 (as part of the Capital Budget
Monitoring pack)
Next Reported Committee and Date: 
Policy & Resources Committee Feb-23
Why is the project classified as off target?
Capital Budget Allocation for FY22/23 is £1,102,000, based on the original programme forecast for the implementation of the works commencing in September
2022. The revised forecast expenditure for FY22/23 is circa £36,000.
£1,066,000 of capital to be carried forward into FY23/24.
What has caused the issue outlined above?
M&K Macleod submitted formal Planning Application in April 2022, however due to wider issues with the availability of Planning Authority resources, and the
volume of applications that they were dealing with, the formal Decision was not published until 21 December 2022. M&K Macleod have been unable to
progress other statutory consents, and therefore the technical design solution for the works, until the Planning Application was decided. The focus through FQ4
FY22/23 will be on progressing statutory consents with Transport Scotland, Argyll & Bute Council (RAS) and Scottish Water to enable implementation of the
physical works in FY23/24, currently estimated as having a start date at the end of FQ2 FY23/24.
What action will be taken to rectify this issue?
Programme has had to be revised with major expenditure not now expected until FQ2/FQ3 in FY23/24. Approximately £1.066million will need to be
carried forward from FY22/23 to FY23/24.

Page 89

What are the implications of the action proposed?
A&BC will need to slip Crown Estate Funding of £150,000 from FY22/23 to FY23/24.
The RCGF Funding of £829,000 was paid to A&BC in FQ1 of FY22/23 and, therefore some £739,000 may need to be carried over into FY23/24
The Highlands and Islands Funding of £150,000 has yet to be claimed by A&BC therefore there are no implications in respect of this funding
We are awaiting revised programme from M&K MacLeod Limited, along with cashflow profile following on from publication of Planning Decision, and
subsequent agreements with the other statutory bodies, which should be available for the beginning of FY23/24

Page 90

OFF TRACK PROJECT Appendix 6
Project Name:  Burnett Building Structural Alterations Project Manager:  Rhona Mitchell Risk:
Initial Start Date:  2021 Proposed End Date:  TBC
How was this project initially funded?  Capital Please detail any additional funding.  n/a
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Works complete – Account still open and not finalised
What has caused the issue outlined above?
Structural Works (£120k) –The proposal to appoint a multi-disciplinary team through Lot 11 of the Edinburgh Framework failed therefore another
route will need to be developed to outsource the design of this project. The Failed Procurement Report (FPR) was signed off on 2 August 2022.
This project also includes internal work associated with Our Modern Workspace so this along with the proposed structural works will be delayed.
No further progress on this project at this stage.
What action will be taken to rectify this issue?
Further dialogue to progress in conjunction with OMW works.
What are the implications of the action proposed?
Works to recommence on completion of OMW works.

Page 91

OFF TRACK PROJECT Appendix 6
Project Name:  Bowmore Area Office Project Manager:  Rhona Mitchell Risk:
Initial Start Date:  not yet progressed Proposed End Date:  March 23/24 if works instructed to proceed
How was this project initially funded?  Capital Please detail any additional funding.  n/a
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Works have not progressed initially as a consequence of COVID, exact details of entrance not agreed, OWM works
What has caused the issue outlined above?
Discussion around if the building is to remain open given uncertainty of the development of Kilarrow and the office rationalisation/OMW works currently
progressing
What action will be taken to rectify this issue?
Works can progress if necessary – further guidance required
What are the implications of the action proposed?
Progressing may result in abortive works or value spent on an asset due to be removed from Council portfolio.

Page 92

OFF TRACK PROJECT Appendix 6
Project Name:  Kilmory castle, Lochgilphead Project Manager:  Rhona Mitchell Risk:
Initial Start Date:  not yet progressed Proposed End Date:  March 23/24 if works instructed to proceed
How was this project initially funded?  Capital Please detail any additional funding.  n/a
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Works have not progressed initially as a consequence of COVID, OWM works
What has caused the issue outlined above?
Discussion around revised design of building given the development of the office rationalisation/OMW programme currently progressing but still to define the
use of the Castle office areas
What action will be taken to rectify this issue?
Works can progress once new design layouts are agreed in conjunction with OMW
What are the implications of the action proposed?
Progressing may result in abortive works or value spent on an asset due to be removed from Council portfolio.

Page 93

OFF TRACK PROJECT Appendix 6
Project Name:  Helensburgh Waterfront Development Project Manager:  Andrew Collins Risk:  Med
Initial Start Date: Construction Phase commenced 31 August 2020 Proposed End Date: Practical Completion of Section 2 of the Construction Phase
is on programme for mid February 2023
How was this project initially funded? 
Prudential Borrowing - £16.255 million
S75 Funding - £0.195 million
Capital Receipt (Retail Development) - £1.000 million
Please detail any additional funding:
UKG LIBOR Funding - £5.000 million
SportScotland - £0.100 million
Place Based Investment - £0.163 million
Live Argyll (FF&E) - £0.344 million 
Place Based Investment - £0.090 million
Crown Estates Funding - £0.093 million
Previously Reported Committee and Date:
Helensburgh & Lomond Area Committee – 20 September 2022
Next Reported Committee and Date:
TBC – subject to conclusion of commercial claim negotiations as between
Contractor and Employer
Why is the project classified as off target?
Reporting an overspend against approved budget.
What has caused the issue outlined above?
A combination of factors including: delays in achieving permanent connection to mains electrical supply, which required the provision of temporary power
supplies and heating to maintain overall contract programme; conformance by the Contractor with the Scottish Government COVID Regulations pertaining to
construction sites; impact of a number of external international/global factors e.g. COVID-19, BREXIT, Russian Invasion of Ukraine on the availability and cost
of essential construction sector materials, resources, plant and equipment.
What action will be taken to rectify this issue?
We are currently awaiting the formal assessment of the Contractors contractual claim by our appointed Cost Consultants, which will enable us to undertake and
conclude the commercial negotiations with them as to the final contract sum. Additionally we are assessing all commercial/legal options to address issues of
underperformance on the delivery of services etc., and which have had a detrimental impact upon the project costs e.g. the delay in achieving the permanent
connection to the mains electrical supply

Page 94

What are the implications of the action proposed?
We have previously reported to Committees of the Council that, whilst the value of the Construction Contract, at Award Stage was £19,971,918.51, given the
global health pandemic and other economic impacts which have emerged since the Contract Award, the Anticipated Final Cost for the Contract and therefore
the project was likely to increase. We are working with the Contractor, Heron Bros Ltd, to ensure that any claims for Extensions of Time, and/or Loss and
Expense, are properly and fully substantiated and assessed in accordance with the requirements of the Contract. This work stream is on-going and its’ outcome
will be reported to the relevant committees of the Council in due course.  It is therefore likely that we may require to secure additional budget support, and
which could include funds from the COVID specific additional funding that the Council has been in receipt of.

Page 95

OFF TRACK PROJECT Appendix 6
Project Name:  Oban Depot Development Project Project Manager: Mark Calder Risk: Low
Initial Start Date:  August 2019 Proposed End Date:  TBC
How was this project initially funded?
Insurance Claim - £1.681 million
Please detail any additional funding.  
Prudential Borrowing - £0.42 million
Block Allocation - £0.032 million
Capital Receipt (Appin Depot – anticipated) £0.150 million
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Reporting an overspend against approved budget.
What has caused the issue outlined above?
Additional works were requested by the operations team which exceeded the original building refurbishment contract. These works were agreed on the basis
that they would be absorbed by the service. Some costs are attributed to Electric Vehicle charger installations which will be claimed against an external fund.
What action will be taken to rectify this issue?
Funding for the additional works will be transferred from the service to the Oban Depot Development Project for the additional works, as agreed.
What are the implications of the action proposed?
Transfer of funding from the service to the Oban Depot Development Project for the additional works requested will eliminate the overspend.

Page 96

Strategic Change Projects - Cumulative Spend, Start/Finish Dates and Project Risks APPENDIX 7
Strategic Change Projects
Prior Years
Spend
£'000
Current Year
Forecast
£'000
Total Project
Forecast
£'000
Total Project
Budget
£'000
Project Start
Date
Estimated
Completion
Date
Project
Risks
Identified Explanation
Helensburgh Waterfront Development 1,387 3,704 23,366 22,740 01/04/2017 31/03/2024 Red Current overspend being investigated by Project Manager with Contractor.
Campbeltown Flood Scheme 181 3,958 15,215 15,215 01/08/2016 31/03/2023 Red Contractor's updated programming of work moved Public Utility works from 22/23 to 23/24
CHORD Oban 7,129 651 7,905 7,905 27/10/2016 31/03/2022 Amber Issues with contract close out impacting on timescales.
TIF - Halfway House Roundabout 0 47 640 640 tbc tbc Amber Scope of project still to be determined - budget to be reprofiled.
Harbour Investment Programme 1,802 5,626 91,292 91,292 01/04/2017 31/03/2028 Green Budget slipped into future years.
Dunoon Primary 7,170 304 10,869 10,869 18/12/2014 30/04/2020 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Kirn Primary School 9,878 99 10,119 10,119 24/04/2014 31/10/2017 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Replacement of Oban High 2,496 136 3,250 3,250 24/04/2014 31/01/2019 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Street Lighting LED Replacement 2,700 791 3,900 3,900 01/08/2016 31/12/2022 Green Tender for final package of works still to be awarded.
Helensburgh Office Rationalisation 11,500 310 11,838 11,838 25/04/2013 31/12/2022 Green Project subject to legal dispute.
CHORD Dunoon 12,238 55 12,522 12,522 03/02/2012 09/03/2018 Green
Main contract complete and retentions paid. Landscaping and remediation works ongoing but
issues with water ingress may require works in 22-23.
Kilmory Business Park Phase 2AA 0 54 1,129 1,129 01/02/2022 01/09/2023 Green Development Agreement still to be concluded.
Carbon Management Business Cases 201 60 261 261 01/02/2014 31/12/2022 Green Budget to be reprofiled pending development of new projects.
Carbon Management - Group Heating Conversion Project 1,938 10 1,948 1,948 01/02/2016 31/12/2022 Green Complete.
Carbon Management - Non Education 14 21 50 50 01/04/2015 31/12/2022 Green Projects being determined.
NPDO Schools Solar PV Panel Installations 761 183 944 944 26/06/2014 31/12/2022 Green Budget to be reprofiled pending development of new projects.
Non NPDO Schools Solar PV Panel Installations 400 88 488 488 20/03/2014 31/12/2022 Green Budget to be reprofiled pending development of new projects.
Carbon Management Capital Property Works 2016/17 19 20 39 39 01/02/2016 31/12/2022 Green Budget to be reprofiled pending development of new projects.
Oil to Gas Heating Conversions 182 5 187 187 01/02/2012 31/12/2022 Green Budget to be reprofiled pending development of new projects.
Dunoon Pier OBC 2,844 0 2,844 2,844 03/02/2012 26/02/2016 Green Project complete.
Campbeltown Office Rationalisation 595 1 596 596 01/02/2015 31/03/2019 Green Complete.
TIF - Oban Airport Business Park 447 101 590 590 22/01/2015 31/12/2022 Green
Campbeltown Schools Redevelopment 1,649 76 2,130 2,130 16/02/2012 30/11/2018 Green Physically complete - negotiations with contractor delaying payment of financial sums outstanding.
CHORD - Helensburgh 6,483 28 6,557 6,557 29/09/2011 30/04/2015 Green Main contract complete. Art project originally proposed for 21-22 now slipped into 22-23.
TIF - North Pier Extension 214 0 214 214 06/12/2017 06/12/2021 Green Complete.
TIF - Lorn/Kirk Road 1,959 1 2,170 2,170 22/01/2015 31/03/2021 Green Complete.
Carbon Management Fuel Conversions 107 0 107 107 01/02/2014 31/03/2019 Green Complete.
Kilmory Biomass  Carbon Management 956 0 956 956 20/09/2012 31/03/2019 Green Complete.
Clean Energy 0 567 745 729 tbc tbc Green
Clean Energy 2022-23 0 500 500 500 tbc tbc Green
Strategic Change Total 75,250 17,396 213,371 212,729
Project Risk Classifications:
Green - Risks can be managed and are viewed as stable or reducing.
Amber - Risks are increasing but are still manageable.
Red - Risks are increasing or have increased to such an extent they may affect delivery of the project.
Capital Expenditure Dates Risks

Page 97

ARGYLL AND BUTE COUNCIL - CAPITAL PLAN MONITORING REPORT - OVERALL COUNCIL
FINANCIAL SUMMARY - NET EXPENDITURE
Current Financial Year To Date
Budget Actual
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Executive Director Douglas Hendry 2,770 2,811 (41) 8,150 6,161 1,989 19,258 19,265 (7)
Executive Director Kirsty Flanagan 8,914 8,914 0 15,423 13,982 1,441 34,850 34,850 0
Asset Sustainability Total 11,684 11,725 (41) 23,573 20,143 3,430 54,108 54,115 (7)
Service Development Projects
Executive Director Douglas Hendry 948 948 0 1,255 1,267 (12) 15,157 15,169 (12)
Executive Director Kirsty Flanagan 1,795 1,860 (65) 6,417 6,483 (66) 33,010 33,076 (66)
Service Development Total 2,743 2,808 (65) 7,672 7,750 (78) 48,167 48,245 (78)
Strategic Change Projects
Campbeltown Schools Redevelopment 38 38 0 76 76 0 2,130 2,130 0
Dunoon Primary 257 257 0 304 304 0 10,869 10,869 0
Replacement of Oban High 100 100 0 136 136 0 3,250 3,250 0
Kirn Primary School 65 65 0 99 99 0 10,119 10,119 0
Carbon Management - Non Education 0 0 0 21 21 0 50 50 0
Carbon Management Business Cases 0 0 0 60 60 0 261 261 0
NPDO Schools Solar PV Panel Installations 0 0 0 183 183 0 944 944 0
Non NPDO Schools Solar PV Panel Installations 0 0 0 88 88 0 488 488 0
Carbon Management Fuel Conversions 0 0 0 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 0 0 0 20 20 0 39 39 0
Carbon Management - Group Heating Conversion Project 0 0 0 10 10 0 1,948 1,948 0
Kilmory Biomass  Carbon Management 0 0 0 0 0 0 956 956 0
Oil to Gas Heating Conversions 0 0 0 5 5 0 187 187 0
Campbeltown Office Rationalisation 0 0 0 1 1 0 596 596 0
Helensburgh Office Rationalisation 10 10 0 310 310 0 11,838 11,838 0
Clean Energy 0 0 0 551 567 (16) 729 745 (16)
Clean Energy 2022-23 0 0 0 500 500 0 500 500 0
Campbeltown Flood Scheme 1,130 1,130 0 5,756 3,958 1,798 15,215 15,215 0
Street Lighting LED Replacement 101 101 0 791 791 0 3,900 3,900 0
Harbour Investment Programme 294 294 0 5,626 5,626 0 91,292 91,292 0
TIF - Lorn/Kirk Road 0 0 0 1 1 0 2,170 2,170 0
TIF - North Pier Extension 0 0 0 0 0 0 214 214 0
TIF - Oban Airport Business Park 0 0 0 101 101 0 590 590 0
TIF - Halfway House Roundabout 1 1 0 47 47 0 640 640 0
CHORD - Helensburgh 0 0 0 28 28 0 6,557 6,557 0
CHORD Dunoon 15 17 (2) 55 55 0 12,522 12,522 0
CHORD Oban 16 16 0 651 651 0 7,905 7,905 0
Helensburgh Waterfront Development 3,078 3,704 (626) 3,078 3,704 (626) 22,740 23,366 (626)
HWD - FFE (Funded by LA) 344 306 38 344 344 0 350 350 0
Kilmory Business Park Phase 2AA 18 18 0 1,120 54 1,066 1,129 1,129 0
Dunoon Pier OBC 0 0 0 0 0 0 2,844 2,844 0
Strategic Change Total 5,467 6,057 (590) 19,962 17,740 2,222 213,079 213,721 (642)
Total Expenditure 19,894 20,590 (696) 51,207 45,633 5,574 315,354 316,081 (727)
INCOME
Asset Sustainability
Executive Director Douglas Hendry 0 0 0 0 0 0 0 0 0
Executive Director Kirsty Flanagan (345) (345) 0 (2,015) (2,015) 0 (2,015) (2,015) 0
Asset Sustainability Total (345) (345) 0 (2,015) (2,015) 0 (2,015) (2,015) 0
Service Development Projects
Executive Director Douglas Hendry 0 (38) 38 0 0 0 (7,771) (7,771) 0
Executive Director Kirsty Flanagan (69) (72) 3 (3,046) (3,046) 0 (21,135) (21,135) 0
Service Development Total (69) (110) 41 (3,046) (3,046) 0 (28,906) (28,906) 0
Strategic Change Projects
Helensburgh Office Rationalisation 0 0 0 0 0 0 (349) (349) 0
Dunoon Primary 0 0 0 0 0 0 (137) (137) 0
Campbeltown Flood 0 0 0 0 0 0 (270) (270) 0
Harbour PB (294) (294) 0 (5,626) (5,626) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road 0 0 0 (149) (149) 0 (2,167) (2,167) 0
H'burgh CHORD Public Realm Imprv 0 0 0 0 0 0 (570) (570) 0
Helensburgh Waterfront Development 0 0 0 (378) (378) 0 (6,676) (6,676) 0
HWD - FFE (Funded by LA) 0 5 (5) 0 0 0 (350) (350) 0
Kilmory Business Park Phase 2AA 0 0 0 (979) (979) 0 (979) (979) 0
CHORD - Dunoon Waterfront 0 0 0 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 0 0 0 (1,624) (1,624) 0
Strategic Change Total (294) (289) (5) (7,132) (7,132) 0 (104,424) (104,424) 0
Total Income (708) (744) 36 (12,193) (12,193) 0 (135,345) (135,345) 0
Net Total 19,186 19,846 (660) 39,014 33,440 5,574 180,009 180,736 (727)
Appendix 8
Full Year This Financial Year Total Project Costs
31 December 2022

Page 98

MONITORING REPORT
Current Financial Year To Date
Budget Actual
(Over)/Under
Variance Budget
Year End
Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Flood Prevention 4 4 0 359 10 349 1,084 1,084 0
Coastal Protection 0 0 0 15 15 0 200 200 0
Coastal Change Adaptation 0 0 0 159 0 159 159 159 0
Bute Sea Wall Repairs 59 59 0 575 148 427 750 750 0
Helensburgh Flood Mitigation 0 0 0 332 4 328 432 432 0
Bridge Strengthening 209 209 0 156 215 (59) 2,049 2,049 0
Local Bridge Maintenance Fund 150 150 0 712 475 237 5,447 5,447 0
Roads Reconstruction 6,663 6,663 0 8,679 8,679 0 16,294 16,294 0
Roads Reconstruction - Helensburgh CHORD 0 0 0 0 0 0 47 47 0
Roads Reconstruction - Oban CHORD 0 0 0 3 3 0 3 3 0
Helensburgh CHORD - Signage etc 0 0 0 0 0 0 10 10 0
Lighting 0 0 0 140 140 0 1,040 1,040 0
Environmental Projects 0 0 0 734 734 0 934 934 0
Play Park Refurbishment 0 0 0 0 0 0 938 938 0
Public Convenience Upgrades 0 0 0 82 82 0 82 82 0
Footway Improvements 162 162 0 269 269 0 269 269 0
Glengorm - Capping 0 0 0 82 82 0 82 82 0
Glengorm - Cell and Transfer Station (PB) 1,102 1,102 0 1,200 1,200 0 1,200 1,200 0
EV Quick Chargers 0 0 0 93 93 0 93 93 0
Tobermory Car Park 74 74 0 576 576 0 576 576 0
Active Travel 0 0 0 370 370 0 500 500 0
Bin Replacement Programme 0 0 0 100 100 0 100 100 0
Server Sustainability 4 4 0 187 187 0 251 251 0
PC Replacement 466 466 0 522 522 0 522 522 0
Telecomms Network 21 21 0 78 78 0 98 98 0
Computer Network Security 0 0 0 0 0 0 0 0 0
MS Exchange & Doc Sharing 0 0 0 0 0 0 0 0 0
Corporate GIS Portal Rollout 0 0 0 0 0 0 0 0 0
Block Allocation - ICT 0 0 0 0 0 0 1,690 1,690 0
Asset Sustainability Total 8,914 8,914 0 15,423 13,982 1,441 34,850 34,850 0
Service Development Projects
Preliminary design for  Regional Transport projects 0 0 0 16 16 0 221 221 0
Campbeltown Old Quay 0 0 0 43 43 0 1,424 1,424 0
Fleet Management - Prudential Borrowing 0 0 0 1,187 1,187 0 4,861 4,861 0
Fleet Management 174 174 0 499 499 0 3,358 3,358 0
Lismore Ferry 13 19 (6) 13 19 (6) 666 672 (6)
Oban Depot Development Project 17 76 (59) 17 76 (59) 2,117 2,176 (59)
Lochgilphead Depot Rationalisation 0 0 0 8 8 0 37 37 0
Jackson's Quarry Refurbishment 0 0 0 0 0 0 285 285 0
Witchburn Road Demolition 0 0 0 (1) 0 (1) 157 158 (1)
Safe Streets, Walking and Cycling (CWSS) 0 0 0 544 544 0 2,878 2,878 0
SPT - bus infrastructure 0 0 0 0 0 0 1,405 1,405 0
Cycleways - H&L (FSPT) 3 3 0 240 240 0 3,112 3,112 0
Helensburgh Public Realm - Arts Strategy Fund 0 0 0 51 51 0 53 53 0
Town Centre Funds 768 768 0 1,054 1,054 0 3,876 3,876 0
Dunoon Cycle Bothy 215 215 0 266 266 0 279 279 0
Dunoon STEM Hub 30 30 0 603 603 0 608 608 0
Ardrishaig North Active Travel 396 396 0 712 712 0 880 880 0
Nature Restoration Fund 0 0 0 346 346 0 346 346 0
Gibraltar Street Public Realm Improvements 23 23 0 248 248 0 250 250 0
Hermitage Park 0 0 0 69 69 0 3,314 3,314 0
West Coast UAV Innovation Logistics and Training Hub 0 0 0 0 0 0 0 0 0
Applications Projects 156 156 0 502 502 0 2,883 2,883 0
Service Development Total 1,795 1,860 (65) 6,417 6,483 (66) 33,010 33,076 (66)
Strategic Change Projects
Campbeltown Flood Scheme 1,130 1,130 0 5,756 3,958 1,798 15,215 15,215 0
Street Lighting LED Replacement 101 101 0 791 791 0 3,900 3,900 0
Harbour Investment Programme 294 294 0 5,626 5,626 0 91,292 91,292 0
TIF - Lorn/Kirk Road 0 0 0 1 1 0 2,170 2,170 0
TIF - North Pier Extension 0 0 0 0 0 0 214 214 0
TIF - Oban Airport Business Park 0 0 0 101 101 0 590 590 0
TIF - Halfway House Roundabout 1 1 0 47 47 0 640 640 0
Strategic Change Total 1,526 1,526 0 12,322 10,524 1,798 114,021 114,021 0
Total Expenditure 12,235 12,300 (65) 34,162 30,989 3,173 181,881 181,947 (66)
INCOME
Asset Sustainability
EV Quick Chargers 0 0 0 (97) (97) 0 (97) (97) 0
Roads Reconstruction (345) (345) 0 (958) (958) 0 (958) (958) 0
Glengorm Capping/New Cell - Prudential Borrowing 0 0 0 (560) (560) 0 (560) (560) 0
Tobermory Car Park 0 0 0 (400) (400) 0 (400) (400) 0
Play Park Renewal 0 0 0 0 0 0 0 0 0
Sale of Plant and Machinery 0 0 0 0 0 0 0 0 0
Sale of Vehicles 0 0 0 0 0 0 0 0 0
Asset Sustainability Total (345) (345) 0 (2,015) (2,015) 0 (2,015) (2,015) 0
Service Development Projects
Applications Projects 0 0 0 (46) (46) 0 (437) (437) 0
Safe Streets, Walking and Cycling 0 (3) 3 (550) (550) 0 (2,483) (2,483) 0
SPfT 0 0 0 0 0 0 (1,243) (1,243) 0
Cycleways - H&L (FSPT) 0 0 0 (240) (240) 0 (3,212) (3,212) 0
Town Centre Funds 0 0 0 (382) (382) 0 (1,794) (1,794) 0
Dunoon STEM Hub 0 0 0 (100) (100) 0 (608) (608) 0
Ardrishaig North Active Travel (50) (50) 0 (50) (50) 0 (50) (50) 0
Dunoon Cycle Bothy 0 0 0 (209) (209) 0 (279) (279) 0
Gibraltar Street Public Realm Improvements 0 0 0 0 0 0 (250) (250) 0
Hermitage Park 0 0 0 0 0 0 (3,245) (3,245) 0
Fleet Management - PB 0 0 0 (1,187) (1,187) 0 (4,861) (4,861) 0
Fleet Management (8) (8) 0 0 0 0 0 0 0
Lochgilphead Depot Rationalisation 0 0 0 (1) (1) 0 (1) (1) 0
Millpark Depot Demolition Insurance 0 0 0 0 0 0 (53) (53) 0
Oban Depot - Mill Park Insurance Claim 0 0 0 0 0 0 (1,681) (1,681) 0
Oban Depot - Appin Depot Sale 0 0 0 (150) (150) 0 (150) (150) 0
Lismore Ferry (11) (11) 0 (131) (131) 0 (631) (631) 0
Witchburn Road Demolition 0 0 0 0 0 0 (157) (157) 0
Service Development Total (69) (72) 3 (3,046) (3,046) 0 (21,135) (21,135) 0
Strategic Change Projects
Campbeltown Flood 0 0 0 0 0 0 (270) (270) 0
Harbour PB (294) (294) 0 (5,626) (5,626) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road 0 0 0 (149) (149) 0 (2,167) (2,167) 0
Strategic Change Total (294) (294) 0 (5,775) (5,775) 0 (93,729) (93,729) 0
Total Income (708) (711) 3 (10,836) (10,836) 0 (116,879) (116,879) 0
Net Departmental Total 11,527 11,589 (62) 23,326 20,153 3,173 65,002 65,068 (66)
31 December 2022
Full Year This Financial Year Total Project Costs
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR KIRSTY FLANAGAN
Appendix 8

Page 99

MONITORING REPORT
Budget Actual Variance Budget Forecast Variance Budget Forecast Variance
£000s £000s £000s £000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability
Education 2,334 2,354 (20) 4,520 4,520 0 11,000 11,000 0
Live Argyll 171 175 (4) 559 545 14 2,073 2,079 (6)
Health and Social Care Partnership 152 155 (3) 559 584 (25) 2,922 2,932 (10)
Shared Offices 113 127 (14) 2,512 512 2,000 3,263 3,254 9
Asset Sustainability Total 2,770 2,811 (41) 8,150 6,161 1,989 19,258 19,265 (7)
Service Development Projects
Ardrishaig Primary Pre 5 Unit 0 0 0 0 0 0 2 2 0
Bowmore Primary School - Pre 5 Unit 0 0 0 0 0 0 149 149 0
Clyde Cottage - 600 hour provision 0 0 0 23 23 0 579 579 0
Craignish Primary School - Pre 5 Extension 0 0 0 0 0 0 400 400 0
Iona Primary School - Pre 5 Unit 0 0 0 0 0 0 490 490 0
Islay High and Rosneath Primary School Pitches 0 0 0 (12) 0 (12) 707 719 (12)
Lochgoilhead Primary School - Pre 5 Unit 0 0 0 0 0 0 391 391 0
Park Primary Extension/Pre Fives Unit 0 0 0 0 0 0 341 341 0
Sandbank Gaelic Pre Five Unit 0 0 0 0 0 0 491 491 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 0 0 0 120 120 0
Early Learning and Childcare 0 0 0 0 0 0 850 850 0
Early Learning and Childcare - 1140 Hours 945 945 0 1,036 1,036 0 7,751 7,751 0
CO2 Monitoring - Covid Mitigation in Schools 3 3 0 116 116 0 192 192 0
Early Learning and Childcare - 1140 Hours - CFCR 0 0 0 0 0 0 111 111 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 38 38 0 38 38 0
Riverside Leisure Centre Refurbishment 0 0 0 0 0 0 1,245 1,245 0
Dunclutha Childrens Home 0 0 0 54 54 0 1,300 1,300 0
Service Development Total 948 948 0 1,255 1,267 (12) 15,157 15,169 (12)
Strategic Change Projects
Campbeltown Schools Redevelopment 38 38 0 76 76 0 2,130 2,130 0
Dunoon Primary 257 257 0 304 304 0 10,869 10,869 0
Replacement of Oban High 100 100 0 136 136 0 3,250 3,250 0
Kirn Primary School 65 65 0 99 99 0 10,119 10,119 0
Carbon Management - Non Education 0 0 0 21 21 0 50 50 0
Carbon Management Business Cases 0 0 0 60 60 0 261 261 0
NPDO Schools Solar PV Panel Installations 0 0 0 183 183 0 944 944 0
Non NPDO Schools Solar PV Panel Installations 0 0 0 88 88 0 488 488 0
Carbon Management Fuel Conversions 0 0 0 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 0 0 0 20 20 0 39 39 0
Carbon Management - Group Heating Conversion Project 0 0 0 10 10 0 1,948 1,948 0
Kilmory Biomass  Carbon Management 0 0 0 0 0 0 956 956 0
Oil to Gas Heating Conversions 0 0 0 5 5 0 187 187 0
Campbeltown Office Rationalisation 0 0 0 1 1 0 596 596 0
Helensburgh Office Rationalisation 10 10 0 310 310 0 11,838 11,838 0
Clean Energy 0 0 0 551 567 (16) 729 745 (16)
Clean Energy 2022-23 0 0 0 500 500 0 500 500 0
CHORD Oban 16 16 0 651 651 0 7,905 7,905 0
CHORD - Helensburgh 0 0 0 28 28 0 6,557 6,557 0
CHORD Dunoon 15 17 (2) 55 55 0 12,522 12,522 0
Helensburgh Waterfront Deveopment 3,078 3,704 (626) 3,078 3,704 (626) 22,740 23,366 (626)
HWD - FFE (Funded by LA) 344 306 38 344 344 0 350 350 0
Kilmory Business Park Phase 2AA 18 18 0 1,120 54 1,066 1,129 1,129 0
Dunoon Pier OBC 0 0 0 0 0 0 2,844 2,844 0
Strategic Change Total 3,941 4,531 (590) 7,640 7,216 424 99,058 99,700 (642)
Total Expenditure 7,659 8,290 (631) 17,045 14,644 2,401 133,473 134,134 (661)
INCOME
Asset Sustainability
Education 0 0 0 0 0 0 0 0 0
Live Argyll 0 0 0 0 0 0 0 0 0
Asset Sustainability Total 0 0 0 0 0 0 0 0 0
Service Development Projects
Sandbank Gaelic Pre Five Unit 0 0 0 0 0 0 (485) (485) 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 0 0 0 (30) (30) 0
Early Learning and Childcare 0 0 0 0 0 0 (918) (918) 0
Early Years 1140 Hours 0 0 0 0 0 0 (6,300) (6,300) 0
CO2 Monitoring - Covid Mitigation in Schools 0 (38) 38 0 0 0 0 0 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 0 0 0 (38) (38) 0
Service Development Total 0 (38) 38 0 0 0 (7,771) (7,771) 0
Strategic Change
Helensburgh Office Rationalisation 0 0 0 0 0 0 (349) (349) 0
Dunoon Primary School 0 0 0 0 0 0 (137) (137) 0
H'burgh CHORD Public Realm Imprv 0 0 0 0 0 0 (570) (570) 0
Helensburgh Waterfront Development 0 0 0 (378) (378) 0 (6,676) (6,676) 0
HWD - FFE (Funded by LA) 0 5 (5) 0 0 0 (350) (350) 0
CHORD - Dunoon Waterfront 0 0 0 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 0 0 0 (1,624) (1,624) 0
Kilmory Business Park Phase 2AA 0 0 0 (979) (979) 0 (979) (979) 0
Strategic Change Total 0 5 (5) (1,357) (1,357) 0 (10,695) (10,695) 0
Total Income 0 (33) 33 (1,357) (1,357) 0 (18,466) (18,466) 0
Net Departmental Total 7,659 8,257 (598) 15,688 13,287 2,401 115,007 115,668 (661)
31 December 2022
Total Project CostsFull Year This Financial YearCurrent Financial Year To Date
Appendix 8
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR DOUGLAS HENDRY

Page 100

CAPITAL PLAN 2022-23 APPENDIX 9
Overall Summary
Service
Previous Years
£000's
2022-23
£000s
2023-24
£000s
2024-25
£000s
2025-26
£000s
2026-27
£000s
Total
£000s
Education 36,575 6,336 4,843 2,226 0 0 49,980
Shared Offices 16,687 2,249 2,492 428 0 0 21,856
ICT 2,126 1,289 1,258 771 0 0 5,444
RIS 21,002 25,352 46,349 33,028 30,091 0 155,822
DEG 15,435 4,282 898 0 0 0 20,615
HSCP 1,246 628 1,920 428 0 0 4,222
Live Argyll 1,274 560 1,106 428 0 0 3,368
CHORD 48,486 4,210 1,351 0 0 0 54,047
Overall Total 142,831 44,906 60,217 37,309 30,091 0 315,354

Page 101

CAPITAL PLAN 2022-23 APPENDIX 9
Education
Category Service Project
Previous
Years
£000's
2022-23         
£000s
2023-24         
£000s
2024-25         
£000s
2025-26         
£000s
2026-27         
£000s
Total
£000s
Asset Sustainability Education Asbestos Control/Removal Works 0 7 0 0 0 0 7
Block Allocation - Education 0 12 4,231 2,226 0 0 6,469
Digital Inclusion 20-21 0 9 0 0 0 0 9
Free School Meals 0 14 0 0 0 0 14
Homeless Houses - Housing Quality Standard 0 1 0 0 0 0 1
Internal Refurbishment Budget 0 7 0 0 0 0 7
Lochgilphead Primary School Demolition 0 246 0 0 0 0 246
Pre-5's/Nurseries 0 1 0 0 0 0 1
Primary Schools 0 3,354 23 0 0 0 3,377
School Houses - Housing Quality Standard 0 26 0 0 0 0 26
Secondary Schools 0 843 0 0 0 0 843
Asset Sustainability Total 0 4,520 4,254 2,226 0 0 11,000
Service Development Education Ardrishaig Primar School - Pre Five Extension 2 0 0 0 0 0 2
Bowmore Primary School - Gaelic Medium Grant 0 38 0 0 0 0 38
Bowmore Primary School - Pre Five Unit 149 0 0 0 0 0 149
Bunessan Primary School - Gaelic Medium Improvements 120 0 0 0 0 0 120
Clyde Cottage - 600 hours provision 556 23 0 0 0 0 579
CO2 Monitoring - Covid Mitigation in Schools 76 116 0 0 0 0 192
Craignish Primary School - Pre Five Extension (600 hours funding) 400 0 0 0 0 0 400
Early Learning and Childcare 850 0 0 0 0 0 850
Early Learning and Childcare - 1140 Hours 6,696 1,036 19 0 0 0 7,751
Early Learning and Childcare - 1140 Hours - CFCR 111 0 0 0 0 0 111
Iona Primary School - Pre Five Unit (600 hours funding) 490 0 0 0 0 0 490
Islay High & Rosneath PS Pitches 719 -12 0 0 0 0 707
Lochgoilhead Primary School - Pre Five Unit (600 hours funding) 391 0 0 0 0 0 391
Park Primary Extension and Pre Fives Unit 341 0 0 0 0 0 341
Sandbank Gaelic Pre Five Unit 491 0 0 0 0 0 491
Service Development Total 11,392 1,201 19 0 0 0 12,612
Strategic Change Education Campbeltown Schools Redevelopment 2,054 76 0 0 0 0 2,130
Dunoon Primary School 10,365 304 200 0 0 0 10,869
Kirn Primary School 10,020 99 0 0 0 0 10,119
Replacement of Oban High School 2,744 136 370 0 0 0 3,250
Strategic Change Total 25,183 615 570 0 0 0 26,368
Overall Total 36,575 6,336 4,843 2,226 0 0 49,980

Page 102

CAPITAL PLAN 2022-23 APPENDIX 9
Shared Office
Category Service Project
Previous
Years
£000's
2022-23
£000s
2023-24
£000s
2024-25
£000s
2025-26
£000s
2026-27
£000s
Total
£000s
Asset Sustainability Shared Offices Argyll House, Dunoon 0 12 0 0 0 0 12
Asbestos Capital Property Works 0 51 0 0 0 0 51
Block Allocation 0 0 193 398 0 0 591
Bowmore Area Office 0 0 76 0 0 0 76
Burnett Building 0 0 110 0 0 0 110
Capital Property Works 0 38 0 0 0 0 38
Fire Risk Assessment Works 0 14 0 0 0 0 14
Helensburgh and Lomond Civic Centre - Emergency Heating Pipework 0 43 0 0 0 0 43
Hill Street Dunoon Rewire 0 33 0 0 0 0 33
Kilmory Castle 0 2 1,409 0 0 0 1,411
Legionella Control Works 0 215 0 0 0 0 215
Manse Brae District Office 0 1 0 0 0 0 1
Manse Brae Roads Office 0 2 0 0 0 0 2
Our Modern Workspace 0 110 526 30 0 0 666
Asset Sustainability Total 0 521 2,314 428 0 0 3,263
Strategic Change Shared Offices Campbeltown Office Rationalisation 595 1 0 0 0 0 596
Carbon Management - Group Heating Conversion Project (Prudential Borrowing)1,938 10 0 0 0 0 1,948
Carbon Management Business Cases (FPB) 201 60 0 0 0 0 261
Carbon Management Capital Property Works 16/17 19 20 0 0 0 0 39
Carbon Management Fuel Conversions (FPB) 107 0 0 0 0 0 107
Cleaner Energy 0 551 178 0 0 0 729
Cleaner Energy 2022-23 0 500 0 0 0 0 500
Helensburgh Office Rationalisation  (FPB,REC) 11,528 310 0 0 0 0 11,838
Kilmory Biomass Project OBC (FPB,REV) 956 0 0 0 0 0 956
Non-NPDO Schools PV Panel Installations 400 88 0 0 0 0 488
NPDO Schools Solar PV Panel Installations 761 183 0 0 0 0 944
Oil to Gas Heating Conversions (FPB) 182 5 0 0 0 0 187
Strategic Change Total 16,687 1,728 178 0 0 0 18,593
Overall Total 16,687 2,249 2,492 428 0 0 21,856

Page 103

CAPITAL PLAN 2022-23 APPENDIX 9
Major Projects
Category Service Project
Previous
Years
£000's
2022-23         
£000s
2023-24         
£000s
2024-25         
£000s
2025-26         
£000s
2026-27         
£000s
Total
£000s
Strategic Change CHORD CHORD - Dunoon 12,467 55 0 0 0 0 12,522
CHORD - Helensburgh -Public Realm Imprv 6,529 28 0 0 0 0 6,557
CHORD - Oban 7,254 651 0 0 0 0 7,905
Helensburgh Waterfront Development 19,377 3,078 285 0 0 0 22,740
HWD - FFE 6 344 0 0 0 0 350
Kilmory Business Park Phase 2AA 9 54 1,066 0 0 0 1,129
OBC for Dunoon Pier 2,844 0 0 0 0 0 2,844
Strategic Change Total 48,486 4,210 1,351 0 0 0 54,047
Overall Total 48,486 4,210 1,351 0 0 0 54,047

Page 104

CAPITAL PLAN 2022-23 APPENDIX 9
ICT
Category Service Project
Previous
Years
£000's
2022-23
£000s
2023-24
£000s
2024-25
£000s
2025-26
£000s
2026-27
£000s
Total
£000s
Asset Sustainability ICT Block Allocation - ICT 0 0 919 771 0 0 1,690
PC Replacement 0 522 0 0 0 0 522
Server Sustainability 0 187 64 0 0 0 251
Telecomms Network 0 78 20 0 0 0 98
Asset Sustainability Total 0 787 1,003 771 0 0 2,561
Service Development ICT Applications Projects 2,126 502 255 0 0 0 2,883
Service Development Total 2,126 502 255 0 0 0 2,883
Overall Total 2,126 1,289 1,258 771 0 0 5,444

Page 105

CAPITAL PLAN 2022-23 APPENDIX 9
Roads and Infrastructure Services
Category Service Project
Previous
Years
£000's
2022-23
£000s
2023-24
£000s
2024-25
£000s
2025-26
£000s
2026-27
£000s
Total
£000s
Asset Sustainability RIS Bin Replacement Programme 0 100 0 0 0 0 100
Bridge Strengthening 0 215 1,484 350 0 0 2,049
Bute Sea Wall Repairs 0 148 602 0 0 0 750
Coastal Change Adaptation 0 0 159 0 0 0 159
Coastal Protection 0 15 85 100 0 0 200
Environmental Projects 0 734 100 100 0 0 934
EV Quick Chargers 0 93 0 0 0 0 93
Flood Prevention 0 10 769 305 0 0 1,084
Footway Improvements 0 269 0 0 0 0 269
Glengorm - Capping 0 82 0 0 0 0 82
Glengorm - Cell and Transfer Station (PB) 0 1,200 0 0 0 0 1,200
Helensburgh CHORD - Signage etc 0 0 10 0 0 0 10
Helensburgh Flood Mitigation 0 4 428 0 0 0 432
Investment in Active Travel 0 370 130 0 0 0 500
Lighting 0 140 750 150 0 0 1,040
Local Bridge Maintenance Fund 0 475 4,972 0 0 0 5,447
Play Park Renewal 0 0 312 235 391 0 938
Public Convenience Upgrades 0 82 0 0 0 0 82
Roads Reconstruction 0 8,679 4,203 3,412 0 0 16,294
Roads Reconstruction - Helensburgh CHORD 0 0 47 0 0 0 47
Roads Reconstruction - Oban CHORD 0 3 0 0 0 0 3
Tobermory Car Park 0 576 0 0 0 0 576
Asset Sustainability Total 0 13,195 14,051 4,652 391 0 32,289
Service Development RIS Campbeltown Old Quay 1,381 43 0 0 0 0 1,424
Fleet Management 2,859 499 0 0 0 0 3,358
Fleet Management - Prudential Borrowing 2,674 1,187 1,000 0 0 0 4,861
Jackson's Quarry Refurbishment 285 0 0 0 0 0 285
Lismore Ferry Replacement 618 13 15 20 0 0 666
Lochgilphead Depot Rationalisation 29 8 0 0 0 0 37
Oban Depot Development 2,100 17 0 0 0 0 2,117
Preliminary design for  Regional Transport projects (tif) 205 16 0 0 0 0 221
Witchburn Road Demolition 158 -1 0 0 0 0 157
Service Development Total 10,309 1,782 1,015 20 0 0 13,126
Strategic Change RIS Campbeltown Flood Scheme 878 3,958 9,048 1,331 0 0 15,215
Harbour Investment Programme PB 6,706 5,626 22,235 27,025 29,700 0 91,292
Street Lighting LED Replacement 3,109 791 0 0 0 0 3,900
Strategic Change Total 10,693 10,375 31,283 28,356 29,700 0 110,407
Overall Total 21,002 25,352 46,349 33,028 30,091 0 155,822

Page 106

CAPITAL PLAN 2022-23 APPENDIX 9
Development and Economic Growth
Category Service Project
Previous
Years
£000's
2022-23
£000s
2023-24
£000s
2024-25
£000s
2025-26
£000s
2026-27
£000s
Total
£000s
Service Development DEG Ardrishaig North Active Travel 0 712 168 0 0 0 880
Cycleways - H&L (FSPT) 2,722 240 150 0 0 0 3,112
Dunoon Cycle Bothy 13 266 0 0 0 0 279
Dunoon STEM Hub 5 603 0 0 0 0 608
Gibraltar Street Public Realm Improvements 2 248 0 0 0 0 250
Helensburgh Public Realm - Arts Strategy Fund 2 51 0 0 0 0 53
Hermitage Park 3,245 69 0 0 0 0 3,314
Nature Restoration Fund 0 346 0 0 0 0 346
Safe Streets, Walking and Cycling (CWSS) 2,334 544 0 0 0 0 2,878
SPT - bus infrastructure 1,405 0 0 0 0 0 1,405
Town Centre Funds 2,792 1,054 30 0 0 0 3,876
West Coast UAV Innovation Logistics and Training Hub 0 0 0 0 0 0 0
Service Development Total 12,520 4,133 348 0 0 0 17,001
Strategic Change DEG 01 TIF - Lorn/Kirk Road 2,169 1 0 0 0 0 2,170
05 TIF - North Pier Extension 214 0 0 0 0 0 214
09 TIF - Oban Airport Business Park 489 101 0 0 0 0 590
TIF - Halfway House Roundabout 43 47 550 0 0 0 640
Strategic Change Total 2,915 149 550 0 0 0 3,614
Overall Total 15,435 4,282 898 0 0 0 20,615

Page 107

CAPITAL PLAN 2022-23 APPENDIX 9
Health & Social Care Partnership
Category Service Project
Previous
Years
£000's
2022-23
£000s
2023-24
£000s
2024-25
£000s
2025-26
£000s
2026-27
£000s
Total
£000s
Asset Sustainability HSCP Ardfenaig 0 43 87 0 0 0 130
Block Allocation 0 0 577 428 0 0 1,005
Capital Property Works 0 0 96 0 0 0 96
Digitalising telecare 0 0 100 0 0 0 100
Dunoon Hostel 0 33 0 0 0 0 33
Eadar Glinn 0 0 196 0 0 0 196
East King Street Childrens Hospital 0 90 0 0 0 0 90
Glencruitten Hostel 0 115 0 0 0 0 115
Gortonvogie 0 0 80 0 0 0 80
Greenwood/Woodlands 0 105 119 0 0 0 224
Rothesay Community Education Centre 0 0 0 0 0 0 0
Shellach View 0 65 0 0 0 0 65
Struan Lodge Boiler 0 42 222 0 0 0 264
Thomson Home Rothesay 0 0 125 0 0 0 125
Tigh An Rudha HFE 0 80 302 0 0 0 382
Tobermory Top Flat 0 0 0 0 0 0 0
Asset Sustainability Total 0 574 1,920 428 0 0 2,922
Service Development HSCP Dunclutha Childrens Home 1,246 54 0 0 0 0 1,300
Service Development Total 1,246 54 0 0 0 0 1,300
Overall Total 1,246 628 1,920 428 0 0 4,222

Page 108

CAPITAL PLAN 2022-23 APPENDIX 9
Live Argyll
Category Service Project
Previous
Years
£000's
2022-23
£000s
2023-24
£000s
2024-25
£000s
2025-26
£000s
2026-27
£000s
Total
£000s
Asset Sustainability Live Argyll Aqualibrium 0 56 0 0 0 0 56
Campbeltown Museum - Burnet Bldg 0 0 38 0 0 0 38
Capital Property Works 0 0 976 428 0 0 1,404
Inveraray CARS 0 21 0 0 0 0 21
Kintyre Community Education Centre - Lift Shaft Refurbishment 0 30 0 0 0 0 30
Lochgilphead Library Relocation 0 52 0 0 0 0 52
Riverside Leisure Centre - Cladding Upgrade 0 1 45 0 0 0 46
Riverside Leisure Centre - Spa Pool Upgrade 0 80 0 0 0 0 80
Rothesay Swimming Pool 0 0 27 0 0 0 27
The Moat Centre - Gym Store 0 35 0 0 0 0 35
Victoria Halls, Helensburgh 0 80 20 0 0 0 100
Asset Sustainability Total 0 539 1,106 428 0 0 2,073
Service Development Live Argyll Riverside Leisure Centre Refurbishment 1,245 0 0 0 0 0 1,245
Service Development Total 1,245 0 0 0 0 0 1,245
Strategic Change Live Argyll Carbon Management 29 21 0 0 0 0 50
Strategic Change Total 29 21 0 0 0 0 50
Overall Total 1,274 560 1,106 428 0 0 3,368

Page 109

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 16 FEBRUARY 2023
TREASURY MANAGEMENT MONITORING REPORT – 31 DECEMBER 2022
1. EXECUTIVE SUMMARY
1.1. This report sets out the Council’s treasury management position for the period 1
November 2022 to 31 December 2022 and includes information on:
• Overall borrowing position
• Borrowing activity
• Investment activity
• Economic background
• Interest rate forecast
• Prudential Indicators
1.2. Borrowing is below the Capital Financing Requirement for the period to 31 December
2022. This is due to the repayment of long term PWLB borrowing earlier in the year
offset by the need to take temporary borrowing for cash flow purposes.
1.3. The net movement in external borrowing in the period 1 November 2022 to 31
December 2022 was a decrease of £9.98m.
1.4. The levels of investments were £99.1m at 31 December 2022. The rate of return
achieved was 2.869% which is below the target SONIA rate which was 3.202%.

Page 110

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 16 FEBRUARY 2023 
TREASURY MANAGEMENT MONITORING REPORT – 31 DECEMBER 2022 
2. INTRODUCTION 
2.1. This report sets out the Council’s treasury management position for the period 1
November 2022 to 31 December 2022 and includes information on: 
• Overall borrowing position
• Borrowing activity
• Investment activity
• Economic background
• Interest rate forecast
• Prudential Indicators 
3. DETAIL
Overall Borrowing Position 
3.1. The table below details the estimated capital financing requirement (CFR) and
compares this with the estimated level of external debt at 31 March 2022. The CFR
represents the underlying need for the Council to borrow to fund its fixed assets and
accumulated capital expenditure. 
Forecast Forecast Forecast
2022/23 2023/24 2024/25
£000 £000 £000
CFR at 1 April 309,092 305,839 337,480
Net Capital Expenditure 6,915 43,028 27,052
Less Loans Fund Principal Repayments (5,353) (5,507) (5,788)
Less: NPDO Repayment (4,815) (5,880) (6,038)
Estimated CFR 31 March 305,839 337,480 352,706
Less Funded by NPDO (116,681) (117,064) (112,184)
Estimated Net CFR 31 March 189,158 220,416 240,522
Estimated External Borrowing at 31 March 142,158 172,154 202,135
Gap 47,000 48,262 38,387

Page 111

3.2. Borrowing is below the Capital Financing Requirement for the period to 31 December
2022. This is due to the repayment of long term PWLB borrowing earlier in the year
offset by the need to take temporary borrowing for cash flow purposes.  The gap that
the Council is under borrowed by is due to the decision to repay long term debt and
potentially not take any new borrowing due to high borrowing rates at present
3.3. The Council’s Treasury Management Strategy states that any decision to borrow in
advance will be within forward approved Capital Financing Requirement estimates.
3.4. The Council’s estimated net capital financing requirement at 31 December 2022 is
£189.2m. The table below shows how this has been financed. £144.1m is funded by
loans and there are substantial internal balances of £144.1m of which £99.1m are
currently invested, leaving a net internal balance of £45m.
3.5. During the period from 1 November to 31 December 2022, £20.001m of loans were
repaid and new borrowing of £10.025m was taken. This was mainly made up of the
repayment of long temporary borrowing of £20m, partly funded by new temporary
borrowing of £10m.  The balance relates to the renewal of local bonds and some new
temporary borrowing, the analysis of the movement in borrowing is shown in the table
below:
Actual
£000
(20,001)
10,025
Net Movement in External Borrowing (9,976)
External Loans Repaid 1st November 2022 to 31st
December 2022
Borrowing undertaken  1st November 2022 to 31st
December 2022
3.6. The table below summarises the movement in the level and rate of temporary
borrowing at the start and end of the period.
Position at
31/10/22
Position at
31/12/22
£000 £000
Loans 154,069 144,094
Net Internal Balances 18,360 45,064
Total CFR 172,429 189,158
£000 % Rate
Temp borrowing at 31st October 2022 20,515 1.26%
Temp borrowing at 31st Decemberr 2022 10,515 2.57%

Page 112

Investment Activity
3.7. The average rate of return achieved in the Council’s investments to 31 December
2022 was 2.869% compared to the Sterling Overnight Index Average (SONIA) rate for
the same period of 3.202%. The Council rate of return is less than SONIA due to the rapid rise in
interest rates in 2022 which increased SONIA faster than the Council was able to redeem its
investments at lower rates.  At 31 October 2022 the Council had £99.1m of short term
investments at an average rate of 2.869%. The table below details the counterparties
that the investments were placed with, the maturity date, the interest rate and the credit
rating applicable for each counterparty.
Counterparty Maturity Amount £000 Interest Rate Rating  S&P
Clydesdale Bank Instant 6,921 3.40% Short Term A-2, Long Term A-
First Abu Dhabi bank 20/01/2023 5,000 1.00% Short Term A-1+, Long Term AA-
National Bank of Kuwait 11/04/2023 7,500 2.08% Short Term A-1, Long Term A
First Abu Dhabi bank 10/05/2023 5,000 2.11% Short Term A-1+, Long Term AA-
Close Bros 31/02/2023 2,500 2.00% Short Term A-1, Long Term A+
AL Ryan Bank 02/02/2023 5,000 2.45% Short Term A-1, Long Term A+
First Abu Dhabi bank 10/08/2023 5,000 3.12% Short Term A-1+, Long Term AA-
Australia and New Zealand Banking Group 23/02/2023 5,000 3.01% Short Term A-1+, Long Term AA-
Australia and New Zealand Banking Group 06/10/2023 5,000 4.99% Short Term A-1+, Long Term AA-
Toronto Dominion Bank 13/10/2023 5,000 5.25% Short Term A-1+, Long Term AA-
Cheshire West & Chester Council 12/01/2023 2,500 0.90% AA
Cambridgeshire County Council 22/07/2024 5,000 1.00% AA
Slough Borough Council 26/05/2023 5,000 2.10% AA
Slough Borough Council 29/06/2023 5,000 2.10% AA
Thurrock Borough Council 31/07/2023 5,000 3.00% AA
Thurrock Borough Council 19/09/2023 5,000 3.50% AA
Spelthorn Borough Council 03/04/2023 5,000 3.00% AA
London Borough of Croydon 10/10/2024 5,000 4.10% AA
Barnsley Metropolitian Borough Council 20/02/2023 5,000 3.60% AA
Money Market Fund - BNP Paribas Call 4,700 3.50% AAA
Total 99,121
3.8. All investments and deposits are in accordance with the Council’s approved list of
counterparties and within the limits and parameters defined in the Treasury
Management Practices. The counterparty list is constructed based on assessments
by leading credit reference agencies adjusted for additional market information
available in respect of counterparties.
Economic and Interest Rate Forecasts
3.9. The latest economic background is shown in Appendix 1 with the interest rate forecast
in Appendix 2.
Prudential Indicators
3.10. The prudential indicators for 2022-23 are attached in Appendix 3.

Page 113

4. CONCLUSION
4.1 In the period from 1 November 2022 to 31 December 2022, the Council’s borrowing
decreased by £9.98m and is currently below the Capital Financing Requirement.
There are substantial internal balances, of which £99.1m is currently invested. The
investment returns were 2.869% which is below the target of 3.202%.
5. IMPLICATIONS
5.1 Policy –  None.
5.2  Financial –   Complies with Annual Treasury Strategy.
5.3 Legal –  None.
5.4 HR –   None.
5.5 Fairer Duty Scotland – None.
5.5.1 Equalities – protected characteristics –  None.
5.5.2 Socio-economic Duty – None.
5.5.3 Islands –  None.
5.6 Climate Change –  None.
5.7 Risk –  None.
5.8 Customer Service – None.
Kirsty Flanagan
Executive Director/Section 95 Officer
13 January 2023
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney
Appendix 1 – Economic Background
Appendix 2 – Interest Rate Forecast
Appendix 3 – Prudential Indicators
For further information contact: Anne Blue, Head of Financial Services
anne.blue@argyll-bure.gov.uk

Page 114

Appendix 1 – Economics Update (at 31-12-22)
This section has been provided by Link Asset Services and therefore includes their views
and opinions of future trends and events.
• The third quarter of 2022/23 saw:
- A 0.5% m/m rise in GDP in October, mostly driven by the reversal of bank holiday effects;
- Signs of economic activity losing momentum as households increased their savings;
- CPI inflation fall to 10.7% in November after peaking at 11.1% in October;
- A small loosening in the labour market which pushed the unemployment rate up to 3.7% in
October;
- Interest rates rise by 125bps over Q4 2022, taking Bank Rate to 3.50%;
- Reduced volatility in UK financial markets but a waning in global risk appetite.
• GDP fell by 0.3% q/q in Q3 2022 (ending 30th September), which probably marked the start of the
UK recession. About half of that decline was the effects of the extra bank holiday in September for
the Queen’s funeral. The unwinding of those bank holiday effects meant that GDP rebounded in
October and explained at least 0.3 percentage points (ppts) of the 0.5% m/m rise. Accordingly, if
GDP were to avoid falls of more than 0.2% m/m in November and December, then GDP over Q4
as a whole could avoid a contraction, which would prevent a recession in 2022.
• However, at 49.0 in December, the flash composite activity PMI stayed below the “boom-bust” level
of 50 and pointed to a small 0.1% q/q contraction in GDP in Q4. Consumer confidence was -42 in
December and stayed close to its record low of -49 in September. Strike action could be another
small drag and may mean that GDP is 0.0% to 0.5% lower than otherwise in December. GDP is
projected to contract marginally in Q4 by around 0.1% q/q.
• Meanwhile, the 0.4% m/m fall in retail sales volumes in November only reversed some of the 0.9%
m/m rise in October. That left sales volumes 4.5% below their level at the start of the year. Indeed,
the rise in the household saving rate from 6.7% in Q2 to 9.0% in Q3 implied that higher interest
rates are encouraging households to save more. And a larger-than-usual £6.2bn rise in cash in
household bank accounts in October may imply households have started to increase their
precautionary savings.
• There were signs that the labour market was loosening gradually going into the final quarter of 2022.
Although employment in the three months to October rose by 27,000, the fall in the composite PMI
employment balance in December took it into contractionary territory and suggests that labour
demand will cool. Meanwhile, labour supply improved as inactivity fell by 76,000 in the three months
to October. That helped drive a rise in the unemployment rate from 3.6% in September to 3.7% in
October. The number of job vacancies in November fell for the sixth consecutive month and were
18% below their peak in May.
• Crucially, though, wage growth remained resilient. Average earnings growth, excluding bonuses,
grew by 0.7% m/m in October, above the 2022 monthly average of 0.5% m/m. That drove the 3myy
rate up to 6.2%, well above the rates of 3-3.5% consistent with inflation at its 2% target. Wage
growth is likely to slow gradually in the coming months as the labour market loosens further but if
extensive strike action is successful in achieving large pay increases, then wage growth could be a
bit stronger for longer.
• CPI inflation peaked in October at a 41-year high of 11.1% and fell to 10.7% in November. Goods
price inflation, which is driven largely by global factors, has peaked. The sharp rises in energy prices
in 2022 mean that energy price inflation will fall sharply in 2023. Meanwhile, the large fall in
agricultural prices since May means that food price inflation should start to decline soon. What’s
more, upward pressure on goods price inflation from global supply shortages is fading quickly.

Page 115

• Domestic inflation pressures also eased in Q4. The 0.2% m/m rise in core CPI inflation in November
was the smallest monthly gain since August 2020 and drove a fall in core CPI inflation from 6.5% in
October to 6.3% in November. Services CPI inflation was stable at 6.3% in November despite the
resilience of wage growth. And the easing of price expectations in the Bank of England’s Decision
Maker Panel survey in November suggests that inflation may become less persistent.
• The Chancellor’s Autumn Statement on 17th November succeeded in restoring the government’s
fiscal credibility in the eyes of the financial markets without deepening the recession. The total fiscal
consolidation package of £54.9bn (1.8% of GDP) in 2027/28 made the outlook for fiscal policy much
tighter than at the beginning of Q4. The package was heavily backloaded, with net handouts of
£3.8bn (0.15% of GDP) in 2023/24 and £0.3bn (0.01% of GDP) in 2024/25, and most of the
tightening kicking in after 2024/25. The largest fiscal support was the extension of the Energy Price
Guarantee for another 12 months, until April 2024, although at a higher price cap of £3,000 from
April 2023 rather than £2,500. At the same time, Chancellor Hunt loosened the fiscal rules by
requiring debt as a percentage of GDP to be falling in five years’ time, rather than three. The Office
of Budget Responsibility (OBR) estimated that the Chancellor will meet this new rule with a slim
£9.2bn (0.3% of GDP) to spare.
• With fiscal policy now doing much less to fan domestic inflation pressures, we think Bank Rate will
peak at 4.50%, or at least close to that figure. Despite stepping up the pace of policy tightening to
a 75-basis point (bps) rate hike in November, taking Bank Rate from 2.25% to 3.00%, the MPC’s
communication was dovish. The MPC pushed back heavily against market rate expectations, which
at the time were for Bank Rate to peak at 5.25%. The Bank’s new forecasts predicted a deeper and
longer recession than the analyst consensus, of eight quarters and with a peak-to-trough fall in real
GDP of 2.9%.
• The Bank sounded dovish again in December when it slowed the pace of tightening with a 50bps
rate rise, from 3.00% to 3.50%. Two members, Dhingra and Tenreyro, voted to leave rates
unchanged, judging that the current level of Bank Rate was sufficient to bring inflation back to target.
That said, the rest of the MPC appeared to suggest that further rate hikes would be necessary. We
expect that the majority of the MPC will need to see stronger signs that activity is slowing, the labour
market is loosening, and wage growth is slowing before stopping rate rises. As such, we expect that
the MPC will deliver three further rate hikes in February, March and May, taking Bank Rate to a
peak of 4.50% but with the pace of increase reducing to 25bps in March and May.
• Gilt yields have fallen sharply since their highs following the “mini-budget” on 23rd September as
government fiscal credibility has been largely restored with the resignation of Truss-Kwarteng and
the fiscal consolidation package announced at the Autumn Statement on 17th November. Indeed,
the 10-year yield fell from a peak of 4.55% to about 3.60% now, while the 30-year yield fell from
5.10% to 3.90%. Admittedly, yields rose by around 50bps in December, partially on the back of a
global rise in yields. But if we are right in thinking Bank Rate will fall back in 2024 and 2025 then gilt
yields will probably fall over the next two years, with the 10-year yield slipping from around 3.60%
now to 3.30% by the end of 2023 and to 2.80% by the end of 2024.
• Lower volatility in gilt markets in Q4 meant that the Bank of England was able to stop its purchases
of long-term gilts for financial stability reasons as planned on 14th October. It was also able to begin
active gilt sales in November, albeit with a focus on shorter dated gilts. So far quantitative tightening
has had little influence on short-term money markets. But as it is still an experiment, the risk of a
widespread tightening in financial conditions remains.
• The restoration of fiscal credibility boosted the pound and the FTSE 100 early in Q4. While much of
the benefit passed in the first half of Q4, sterling continued to rally against a softer dollar. Our
colleagues at Capital Economics do not think that the global recession is fully priced into markets,
and so expect a further fall in risk appetite to boost safe haven demand for the dollar and weigh on
the pound. They are expecting the pound to fall from $1.19 now to $1.10 in mid-2023, before
climbing to $1.15 by the end of 2023 as the prospect of lower interest rates and a recovery in global
economic growth buoys equity prices.

Page 116

• Through December, the rally in the FTSE 100 petered out as investors have become increasingly
concerned by the prospect of a global recession. However, the relatively dovish tone of the Bank of
England, compared to the Federal Reserve and the ECB meant that UK equities held up better than
other developed market indices. Indeed, at 7,452 at the December month end, the FTSE 100 is only
marginally below its peak of 7,568 on 5th December, while the S&P 500 is around 4% lower over
the same period. Nevertheless, there is a great deal of uncertainty as to which direction markets
will move in 2023 and at what pace.  Continued volatility is anticipated.
MPC meetings 3rd November and 15th December 2022
• On 3rd November, the Bank of England’s Monetary Policy Committee (MPC) increased Bank Rate
by 75 basis points to 3.00%, and on 15th December moved rates up a further 50 basis points to
3.50%.  The later increase reflected a split vote – six members voting for a 50 basis points increase,
one for 75 basis points and two for none.
• Nonetheless, the UK government appears more settled now, with Rishi Sunak as Prime Minister,
and Jeremy Hunt as Chancellor.   Having said that, a multitude of strikes across several public
services and the continued cost-of-living squeeze is going to make for a difficult backdrop to
maintain fiscal rectitude without pushing the economy into anything worse than a mild recession.
• Of course, what happens outside of the UK is also critical to movement in gilt yields.  The US FOMC
has led with increases of 425 basis points in 2022 and is expected to increase rates further in 2023.
Similarly, the ECB has also started to tighten monetary policy, albeit from an ultra-low starting point,
as have all the major central banks apart from Japan (although the BoJ has “tightened” its policy
by widening the accepted yield levels for 10yr JGBs, from 0.25% to 0.5% on 20th December).
Arguably, though, it is US monetary policies that are having the greatest impact on global bond
markets.
• What happens in Ukraine will also impact the global economy, but particularly in Europe.  The
search for alternative providers of energy, other than Russia, will take both time and effort.  The
weather will also play a large part in how high energy prices stay and for how long.

Page 117

Appendix 2 – updated Interest Rate Forecast (19-12-22)
The Council has appointed Link Group as its treasury advisors and part of their service is to assist the
Council to formulate a view on interest rates. The PWLB rate forecasts below are based on the Certainty
Rate (the standard rate minus 20 bps) which has been accessible to most authorities since 1st
November 2012. 
The latest forecast, made on 19th December, sets out a view that both short and long-dated interest
rates will be elevated for some little while, as the Bank of England seeks to squeeze inflation out of the
economy, whilst the government is also providing a limited package of fiscal loosening to try and protect
households and businesses from the ravages of ultra-high wholesale gas and electricity prices.  PWLB
rates reflect a less elevated yield curve than prevailed under the Truss/Kwarteng government, and the
17th of November Autumn Statement made clear the government’s priority is the establishment and
maintenance of fiscal rectitude.  In addition, the MPC has tightened short-term interest rates with a view
to trying to slow the economy sufficiently to keep the secondary effects of inflation – as measured by
wage rises – under control.  
Our current and previous PWLB rate forecasts below are based on the Certainty Rate. 
Link Group Interest Rate View 08.11.22
Dec-22 Mar-23 Jun-23 Sep-23 Dec-23 Mar-24 Jun-24 Sep-24 Dec-24 Mar-25 Jun-25 Sep-25 Dec-25
BANK RATE 3.50 4.25 4.50 4.50 4.50 4.00 3.75 3.50 3.25 3.00 2.75 2.50 2.50
3 month ave earnings 3.60 4.30 4.50 4.50 4.50 4.00 3.80 3.30 3.00 3.00 2.80 2.50 2.50
6 month ave earnings 4.20 4.50 4.60 4.50 4.20 4.10 3.90 3.40 3.10 3.00 2.90 2.60 2.60
12 month ave earnings 4.70 4.70 4.70 4.50 4.30 4.20 4.00 3.50 3.20 3.10 3.00 2.70 2.70
5 yr   PWLB 4.30 4.30 4.20 4.10 4.00 3.90 3.80 3.60 3.50 3.40 3.30 3.20 3.10
10 yr PWLB 4.50 4.50 4.40 4.30 4.20 4.00 3.90 3.70 3.60 3.50 3.40 3.30 3.20
25 yr PWLB 4.70 4.70 4.60 4.50 4.40 4.30 4.10 4.00 3.90 3.70 3.60 3.50 3.50
50 yr PWLB 4.30 4.40 4.30 4.20 4.10 4.00 3.80 3.70 3.60 3.40 3.30 3.20 3.20

Page 118

A SUMMARY OVERVIEW OF THE FUTURE PATH OF BANK RATE
• Our central forecast for interest rates was most recently updated on 19th December and reflected
a view that the MPC would be keen to further demonstrate its anti-inflation credentials by
delivering a succession of rate increases.  This has happened but the Government’s policy of
emphasising fiscal rectitude will probably mean Bank Rate will not need to increase to further
than 4.5%. 
• Further down the road, we anticipate the Bank of England will be keen to loosen monetary policy
when the worst of the inflationary pressures are behind us – but that timing will be one of fine
judgment: cut too soon, and inflationary pressures may well build up further; cut too late and any
downturn or recession may be prolonged. 
• The CPI measure of inflation looks to have peaked at 11.1% in Q4 2022 (currently 10.7%). 
Despite the cost-of-living squeeze that is still taking shape, the Bank will want to see evidence
that wages are not spiralling upwards in what is evidently a very tight labour market. 
• Regarding the plan to sell £10bn of gilts back into the market each quarter (Quantitative
Tightening), this has started and will focus on the short, medium and longer end of the curve in
equal measure now that the short-lived effects of the Truss/Kwarteng unfunded dash for growth
policy are firmly in the rear-view mirror. 
• In the upcoming months, our forecasts will be guided not only by economic data releases and
clarifications from the MPC over its monetary policies and the Government over its fiscal policies,
but the on-going conflict between Russia and Ukraine.  (More recently, the heightened tensions
between China/Taiwan/US also have the potential to have a wider and negative economic
impact.) 
• On the positive side, consumers are still estimated to be sitting on over £160bn of excess
savings left over from the pandemic so that will cushion some of the impact of the above
challenges.   However, most of those are held by more affluent people whereas lower income
families already spend nearly all their income on essentials such as food, energy and
rent/mortgage payments. 
PWLB RATES
• The yield curve movements have become less volatile of late and PWLB 5 to 50 years Certainty
Rates are, generally, in the range of 4.10% to 4.80%.   
• We view the markets as having built in, already, nearly all the effects on gilt yields of the likely
increases in Bank Rate and the elevated inflation outlook. 
The balance of risks to the UK economy: -
• The overall balance of risks to economic growth in the UK is to the downside. 
Downside risks to current forecasts for UK gilt yields and PWLB rates include: - 
• Labour and supply shortages prove more enduring and disruptive and depress economic activity
(accepting that in the near-term this is also an upside risk to inflation and, thus, rising gilt yields). 
• The Bank of England acts too quickly, or too far, over the next year to raise Bank Rate and causes
UK economic growth, and increases in inflation, to be weaker than we currently anticipate. 
• UK / EU trade arrangements – if there was a major impact on trade flows and financial services due
to complications or lack of co-operation in sorting out significant remaining issues.

Page 119

• Geopolitical risks, for example in Ukraine/Russia, China/Taiwan/US, Iran, North Korea and Middle
Eastern countries, which could lead to increasing safe-haven flows. 
Upside risks to current forecasts for UK gilt yields and PWLB rates: -
• The Bank of England is too slow in its pace and strength of increases in Bank Rate and, therefore,
allows inflationary pressures to build up too strongly and for a longer period within the UK economy,
which then necessitates Bank Rate staying higher for longer than we currently project or even
necessitates a further series of increases in Bank Rate. 
• The Government acts too quickly to cut taxes and/or increases expenditure in light of the cost-of-
living squeeze. 
• The pound weakens because of a lack of confidence in the UK Government’s fiscal policies,
resulting in investors pricing in a risk premium for holding UK sovereign debt. 
• Longer term US treasury yields rise strongly and pull gilt yields up higher than currently forecast. 
• Projected gilt issuance, inclusive of natural maturities and QT, could be too much for the markets
to comfortably digest without higher yields consequently.

Page 120

Appendix 3 – Prudential Indicators 
PRUDENTIAL INDICATOR 2022-23 2022-23 2023-24 2024-25
(1).  EXTRACT FROM BUDGET
Forecast
Outturn
Original
Estimate
Forecast
Outturn
Forecast
Outturn
Capital Expenditure £'000 £'000 £'000 £'000
Non - HRA 6,915 51,699 43,028 27,052
TOTAL 6,915 51,699 43,028 27,052
Ratio of financing costs to net revenue stream
Non - HRA 2.70% 2.70% 4.56% 4.57%
Net borrowing requirement
brought forward 1 April * 309,092 292,303 305,839 337,480
carried forward 31 March * 305,839 333,145 337,480 352,706
in year borrowing requirement (3,253) 40,842 31,641 15,226
In year Capital Financing Requirement
Non - HRA (3,253) 40,842 31,641 15,226
TOTAL (3,253) 40,842 31,641 15,226
Capital Financing Requirement as at 31 March    
Non - HRA 305,839 333,145 337,480 352,706
TOTAL 305,839 333,145 337,480 352,706

Page 121

PRUDENTIAL INDICATOR 2022-23 2023-24 2024-25
(2).  TREASURY MANAGEMENT PRUDENTIAL
INDICATORS
£'M £'M £'M    
Authorised limit for external debt -        
borrowing 228 252 272    
other long term liabilities 120 121 116     
TOTAL 348 373 388    
Operational boundary for external debt -         
borrowing 223 247 267     
other long term liabilities 117 118 113     
TOTAL 340 365 380    
Upper limit for fixed interest rate exposure   
Principal re fixed rate borrowing  190% 190% 190%    
Upper limit for variable rate exposure   
Principal re variable rate borrowing  60% 60% 60%    
Upper limit for total principal sums invested for over 364
days
£20m £20m £20m     
(per maturity date)   
Maturity structure of new fixed rate
borrowing during 2022/23
upper
limit   
lower
limit 
under 12 months  30%    0% 
12 months and within 24 months 30%    0% 
24 months and within 5 years 30%    0% 
5 years and within 10 years 40%    0% 
10 years and above 100%    0%

Page 122

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 16 FEBRUARY 2023
RESERVES AND BALANCES – UPDATE AS AT 31 DECEMBER 2022 
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to advise Members of the overall level of
reserves held by the Council as well as providing detail on the monitoring of the
earmarked balances held within the General Fund. 
1.2 The Council has a total of £394.480m unusable reserves that are not backed with
resources.  They are required purely for accounting purposes. 
1.3 At 31 March 2022 the Council had a total of £103.183m of usable reserves.  Of
this:
• £2.682m relates to the Repairs and Renewals Fund
• £4.414m relates to Capital Funds
• £96.087m was held in the General Fund, with £88.990m of this balance
earmarked for specific purposes.
1.4 Of the earmarked balance of £88.990m: 
• £43.882m is invested or committed for major initiatives/capital projects
• £10.605m has already been drawn down
• £8.580m is still to be drawn down in 2022-23
• £25.370m is planned to be spent in future years
• £0.553m has been released back to the general fund 
Appendix 1 provides further information on the unspent budget earmarkings and
Appendix 2 provides further information on the COVID earmarkings. 
1.5 The Council’s General Fund contingency level is set at 2% of net expenditure for
2022-23 which equates to £5.256m.  At the beginning of the financial year there
was £1.398m of unallocated General Fund Balance (over and above contingency). 
At the Council meeting on 24 February 2022 it was agreed that the budgeted
revenue surplus of £2.482m would be transferred into the general fund. After taking
this into consideration alongside the current forecast outturn for 2022-23, the
balances no longer required and the expected adjustment in relation to the Social
Work outturn, the Council is estimated to have a £8.537m surplus over
contingency.

Page 123

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 16 FEBRUARY 2023
RESERVES AND BALANCES - UPDATE AS AT 31 DECEMBER 2022 
2. INTRODUCTION 
2.1 This report outlines current balances on the Council’s reserves, both usable and
unusable. It also provides detail on the monitoring of the earmarked balances
within the General Fund.   
3. DETAIL 
3.1 Types of Reserves 
3.1.1 Usable Reserves - Councils have powers to establish certain resource backed
reserves which can be used to fund expenditure.  The powers of councils to
establish reserves are laid out in Schedule 3 of the Local Government
(Scotland) Act 1975.  These allow councils to establish a Renewal and Repairs
Fund, Insurance Fund and Capital Fund. Councils can also establish a Useable
Capital Receipts Reserve.  The Council must also maintain a General Fund and
can earmark balances for specific purposes within the General Fund. 
3.1.2 Unusable Reserves – Councils are also required to establish certain reserves
that are not backed by resources. They are required purely for accounting
purposes and do not represent resources available for councils to utilise. The
Pensions Reserve, Revaluation Reserve, Capital Adjustment Account, Financial
Instruments Adjustment Account and Accumulated Absences Account are
examples of unusable reserves. 
3.2 Reserve Balances at 31 March 2022 
3.2.1 The balances on each type of reserve at 31 March 2022 are set out in the two
tables below, per the Audited Accounts for 2021-22. 
Unusable Reserves £000
Revaluation Reserve 157,645
Capital Adjustment Account 241,327
Financial Instruments Adjustment Account (2,198)
Pensions Reserve 4,634
Accumulated Absences Account (6,928)
Total Unusable Reserves 394,480 
Usable Reserves £000
Repairs and Renewals Fund 2,682
Capital Fund and Usable Capital Receipts Reserve 4,414                                                                                                                
General Fund  96,087
Total Usable Reserves  103,183
Total Reserves  497,663

Page 124

3.2.2 The Revaluation Reserve represents the unrealised gains in the valuation of
fixed assets. The Capital Adjustment Account represents the difference
between depreciation based on proper accounting practice and statutory
charges for financing capital expenditure. The Financial Instruments Adjustment
Account represents the difference between gains and losses on borrowing and
statutory capital financing charges. The Pensions Reserve represents the
difference between pension costs based on proper accounting practice and
payments made for pension costs. The Accumulated Absences Account
represents the costed difference between holiday pay entitlement and actual
holidays taken at 31 March. 
3.2.3 The Repairs and Renewals Fund was established to support funding of renewal
and replacement of school equipment.  Schools can only draw on the Repairs
and Renewals Fund to the extent they have previously paid into the Fund and
contributions must be contained within schools devolved budgets. 
3.2.4 The Capital Fund was established to receive all capital receipts generated by
the Council and can be used to support the capital plan or meet the principal
repayments on loan charges. The Council decides as part of the budget
process each year how it wishes to draw funding from the Capital Fund. 
3.2.5 The Usable Capital Receipts Reserve relates to the accumulated unspent
capital receipts from sale of council houses prior to transfer of the housing
stock. The reserve forms part of the Council’s Strategic Housing Fund and can
only be used for investment in social housing. The reserve will be used in
accordance with the approach to investing in housing agreed by the Council in
August 2012. 
3.3 General Fund 
3.3.1 The General Fund balance at 31 March 2022 can be analysed as follows: 
Balance
31/03/22
£000
Balance on General Fund as at 31 March 2021 78,245
Increase to General Fund balance at end of 2021-22 17,842
Earmarked Balances (88,990)
Contingency allowance at 2% of net expenditure (5,256)
Unallocated balance as at 31 March 2022 1,841 
3.3.2 The General Fund includes balances that the Council has agreed to earmark for
specific purposes. Some of these earmarked balances will be spent during the
current financial year and some of them will be held over and spent in later
years. The table below shows the balance at 31 March 2022, the amounts that
are currently invested or set aside for major initiatives, the amount already
spent and planned to be spent in the current year, the amount to be spent in
future years and any sums no longer required to be earmarked. Appendix 1
provides further details on the breakdown of unspent budget earmarkings.

Page 125

Officers have reviewed and updated the spending profiles. Appendix 2 provides
further details on the breakdown of COVID reserves.   
3.3.3 Investment in Affordable Housing £0.100m – this earmarked balance provides
cash backed reserves for the loans to registered social landlords.  It is
estimated that as at 31 March 2023, the balance on the remaining loans will be
£3.200m, therefore £0.100m can be released back to the general fund.   
3.3.4 Due to there being no planned expenditure, an earmarking for capital
expenditure on a leased property of £0.025m has been released back to the
general fund.

Page 126

3.3.5 In 2020-21 and 2021-22, the Council received allocations for the administration
of Business Support Grants which currently sit within the COVID-19 earmarked
reserves. There is a balance remaining of £0.411m is no longer required for this
purpose and is being released to the General Fund. 
3.3.6  The last of the redundancy payments in relation to the Kintyre Recycling
unspent budget earmarking have been drawn down so remaining balance of
£0.017m can be released back to the general fund. 
3.4 Unallocated General Fund Balance 
3.4.1 
3.4.2
The Council’s General Fund contingency is set at 2% of net expenditure for
2022-23 and amounts to £5.256m.  At the beginning of the financial year there
was £1.841m of unallocated General Fund Balance (over and above
contingency).   After taking into consideration the budgeted allocation to the
General Fund agreed by Council on 24 February 22 and the current forecast
outturn position for 2022-23, the Council is forecast to have a £8.511m surplus
over contingency. 
The revenue budget position as at 31 December 2022 was estimated to be
£3.408m underspent, however, this is subject to change, particularly as the last
three months of the financial year are the time of winter maintenance and the
level of expenditure is difficult to predict. Note that this underspend is largely as
a result of the treasury gain of £5.398m due to receiving a discount on the early
repayment of three PWLB loans offset by £1.491m recognised for the net
expected shortfall in funding from the 2022-23 pay award plus other forecast
variances within the Departments netting to a £0.499m overspend. 
3.4.3 The Current Forecast Outturn at December includes an overspend against the
Social Work service of £0.253m.  The Chief Financial Officer of the IJB is
confident that the spend will be brought in line with budget by the end of the
financial year using slippage from growth projects and anticipated additional
funding allocations.  As Social Work began to accumulate reserves at 31 March
2022 therefore it is expected that any residual overspend that materialises
would be covered from those reserves and the General Fund of the Council
would not be impacted.    
3.4.4  The table below summarises the position of the unallocated General Fund
balance taking into consideration the points noted above. 
Heading Detail £000
Unallocated General Fund
as at 31 March 2022
This is the balance that is
unallocated over and above the 2%
contingency, which amounts to
£5.256m
1,841
Budgeted allocation to
General Fund for 2022-23
Budget
Per the Budget Motion at Council on
24 February 2022
2,482
Earmarked Balances no
longer required
Per paragraphs 3.3.3 to 3.3.6 –
amounts previously earmarked that
553

Page 127

can be released back to the general
fund
Current Forecast Outturn
for 2022-23 as at 31
December 2022
Per paragraph 3.4.2. Note, this
includes an overspend of £0.253m
against Social Work.
3,408
Social Work outturn
adjustment
Per paragraph 3.4.3 - Social Work
hold reserves so would be expected
to cover the overspend
253
Estimated Unallocated
balance as at 31 March
2023 
8,537 
3.5 Loans Fund Review 
3.5.1 At the Council meeting on 27 February 2020, it was agreed that the one-off re-
profiling gain of £20.561m generated by the loans fund review should be used
partly to create a provision for the increasing principal repayments over the next
10 years (£7.649m) with the remainder of the gain (£12.912m) used to fund the
known liabilities/cost pressures. The table below shows what has been drawn
down against the one-off gain and the remaining balance. 
Agreed
Allocation
Transferred
to
Earmarked
Reserves / 
20-21 / 21-22
Budget
Transferred
to
Earmarked
Reserves /
22-23
Budget
Balance
Remaining 
£000 £000 £000 £000
Provision for the increasing
principal repayments 7,649   7,649
Provision to Support
Organisational Change 500 (500)  0
Estimated Cost of 2020-21
redundancies that are part of
budget savings proposals
600 (600)  0
Future Redundancies
Provision 1,500 (1,500)  0
Spend to Save Route
Optimisation 100 (100)  0
Funding Gap in Capital
Programme 2,619   2,619
Capital Programme
Intolerable Red Risks 574 (574)  0
Campbeltown Flood
Prevention Scheme 1,406  (1,406) 0
Significant Strategic Change
Projects  5,013 (2,856)  2,157
2020-21 Revenue Budget
Contribution  600 (600)  0 
20,561 (6,730) (1,406) 12,425

Page 128

4. CONCLUSION 
4.1 The report outlines the overall reserves and balances for the Council covering
the purpose and level of each reserve.  It also provides detail as to expenditure
against earmarked balances held within the General Fund.   
4.2 As at 31 December 2022 the estimated unallocated General Fund, after taking
into consideration the budget motion, the current forecast outturn for 2022-23,
the balances no longer required, a one-off gain from the Loans Fund and the
expected adjustment in relation to the Social Work outturn, the Council is
estimated to have a £8.537m surplus over contingency. 
5. IMPLICATIONS 
5.1 Policy - Earmarked funds and funds set aside for delivery of
Single Outcome Agreement are available to support
Council Policy.
5.2 Financial -  Outlines the balances held with the Council’s usable
and unusable reserves.     
5.3 Legal -  None.
5.4 HR -  None.
5.5 Fairer Scotland Duty- None.
5.5.1 Equalities – protected
characteristics - 
None.
5.5.2 Socio-economic Duty -  None.
5.5.3 Islands -  None.
5.6 Climate Change - None.
5.7 Risk -  A contingency of £5.256m (equivalent to 2% of net
expenditure) has been set aside as part of the
general fund.  This has been subject to a risk
assessment. 
5.8 Customer Service -  None. 
Kirsty Flanagan
Executive Director/Section 95 Officer 
10 February 2023 
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney 
APPENDICES
Appendix 1 – Earmarked Reserves breakdown of unspent budget
Appendix 2 – Earmarked Reserves breakdown of COVID earmarkings 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 129

APPENDIX 1
Earmarked Reserves - Unspent Budget
As at 31 December 2022
Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
001 Chief Executive's
Unit
Community
Planning
Communities and
Partnership Team
8,855 0 8,855 8,855 0 The funds have originated from externally sourced income due to an employee being
seconded to the Scottish Community Development Centre (SCDC).  The funds will be used
to support the team in relation to meeting its priorities of Building Back Better
(Communities), Climate Change and the review of the Argyll and Bute Outcome
Improvement Plan.
8,855 0 0
002 Chief Executive's
Unit
Community
Planning
Gaelic Development 8,235 8,235 8,235 0 To fund Gaelic specific work and project work of the Community Planning Partnership
including the development of the new 10 year Outcome Improvement Plan
8,235 0 0
003 Chief Executive's
Unit
Financial Services Financial Systems 114,000 80,252 33,748 33,748 0 To fund the completion of the implementation of the Oracle Fusion Financial
Management System, a software update for cash receipting to ensure card payments can
still be taken and the procurement and implementation of a new system to manage the
requirements of the IFRS16 Leases accounting standard.
114,000 0 0
004 Chief Executive's
Unit
Financial Services Accounting and
Budgeting Team
Resilience
95,000 64,336 30,664 0 30,664 To fund the implementation of a new staffing structure in 2022/23 as agreed at ELT on 12
April 2022.  This will provide funding to cover the additional staffing costs in 2022/23 and
the training costs over the period 2022/23 to 2026/27
64,336 16,664 14,000
005 Chief Executive's
Unit
Financial Services CIPFA 32,530 3,565 28,965 2,000 26,965 CIPFA Training - To fund the professional training costs for staff undertaking the CIPFA
professional accountancy qualification.
5,565 6,000 20,965
006 Chief Executive's
Unit
Financial Services Scottish Government
Funding - Welfare
Reform/Discretionary
Housing Payments
(agreed at Council
February 2014)
18,595 18,595 0 18,595 The Council was allocated additional funding of £550k from the Scottish Government late
in 2013-14. This money was allocated to support the Community Learning and
Development Team to provide courses to support Universal Credit claimants 2019/2020
to support the recruitment of casual tutors and the purchase and upgrade of laptops. The
monies were not utilised however it will now be required to top up the Scottish Welfare
Fund and DHP monies for 2023/24 earmarking ref 008 and 012 as it is likely that given the
current cost of living crisis that more people will be in need of support through these
funds
0 18,595 0
007 Executive Director
(Douglas Hendry)
Across Services /
Education
Digital Projects
(Supply Staff Booking
System)
35,000 9,900 25,100 0 25,100 To deliver a number of Digital Service Transformation Projects, specifically in Education
and Customer Support Services, but also to reserve a further amount to support priority
digital transformation projects identified in Departmental ICT programmes, that have not
yet started due to resource constraints.  The specific projects include: Supply Staff
Booking System £0.035m, Skype for Business (for Education) £0.030m, Enhancing
Curriculum Choice and Equity of Provision £0.080m, Digital Customer Engagement
Developments £0.073m, Replacement of Learning Management System £0.030m,
Increase in Schools Bandwidth £0.063m and a general provision still to be allocated
£0.189m
9,900 9,900 15,200
008 Executive Director
(Douglas Hendry)
Commercial
Services
Rothesay Pavilion
Charity
750,000 750,000 90,000 660,000 Agreed at Council meeting February 2020, £750k additional revenue support subject to
conditions which seek to minimise the risk to the Council as far as is reasonably
practicable including requirement for adequate business and financial management and
regular reporting by RPC.
90,000 660,000 0
009 Executive Director
(Douglas Hendry)
Commercial
Services
Demolition of former
Lochgilphead Primary
and Rothesay
Secondary School
320,000 320,000 105,000 215,000 To fund the demolition of the former Lochgilphead Primary School and former Rothesay
Academy (subject to the removal of the listing).
105,000 215,000 0
010 Executive Director
(Douglas Hendry)
Commercial
Services
Rothesay Pavilion
Essential repairs
306,400 306,400 0 306,400 Essential repairs to deal with potential health and safety risks and to avoid further
deterioration.  Budget provision was approved by the Policy and Resources Committee on
21 August 2014. 
0 0 306,400
011 Executive Director
(Douglas Hendry)
Commercial
Services
Estates - NDR
Revaluation Appeals
84,688 84,688 0 84,688 The Council agreed to make provision to meet the cost of appealing Non Domestic Rates
(NDR) revaluations which were imposed from 1st April 2017. The remaining funds were
carried forward to the 2023 revaluation cycle however a recent change in position by the
Scottish Government may restrict the appeals which can be made. This is still under
discussion and Gerald Eve Surveyors have been appointed as specialist advisers on this
matter. In the event that appeals are limited there may be an opportunity to utilise
Gerald Eve for more general valuation advice subject to Procurement approval.
0 84,688 0

Page 130

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
012 Executive Director
(Douglas Hendry)
Commercial
Services
Site Investigation
Works
21,013 21,013 21,013 0 For Site Investigation works in relation to Tweeddale Street Car Park and Oban Airport
Business Park, exploring commercial opportunities to develop the sites and raise revenue
income for Argyll and Bute Council. HUB North were instructed to procure contractors to
undertake the site investigations these are now complete. The remainder of the budget is
intended to be utilised for other site investigation and pre-development works to further
develop commercial opportunities across the council area.
21,013 0 0
013 Executive Director
(Douglas Hendry)
Commercial
Services
Catering and Cleaning
Restructure Costs
17,000 17,000 0 0 0 To support the catering and cleaning team restructure 17,000 0 0
014 Executive Director
(Douglas Hendry)
Education Education
Transformation Fund
187,526 40,852 146,674 0 146,674 At the Council meeting on 27 February 2020, it was agreed to input £400k into Education
Digital Learning.  The additional funds have been spent in 20/21, 21/22 and 22/23 as part
of the ongoing transformation work in the Education service, focussing on digital and
virtual learning technology and the development of learning clusters.  This will continue
into 2023/24.
40,852 146,674 0
015 Executive Director
(Douglas Hendry)
Education Education Learning
Estate Condition
Surveys
77,440 46,853 30,587 30,587 0 To fund the delivery of School Core Facts (SCF) compliant Condition Surveys for prioritised
School Buildings.
77,440 0 0
016 Executive Director
(Douglas Hendry)
Education Skype for Business for
Education / Digital
Projects (Skype for
Business)
10,000 10,000 10,000 0 To fund the initial capital costs for the implementation of Skype for Business for
Education.  This will bring the Education service in line with other council departments
and will improve staff collaboration and modernise school telephony to deliver the 
service more efficiently and cost effectively.
A balance has been released back to the general fund because the rollout project is
almost complete with only £0.01m expected spend in 22/23.
10,000 0 0
017 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Education Purchasing
Officers
210,000 210,000 0 210,000 The earmarked funds will be used to fund an education purchasing team within the
Procurement Service for two years.  The team will embed good procurement practice,
train headteachers on current procurement process requirements, develop spend plans
that evidence best value.
0 105,000 105,000
018 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
NDR - One off
contribution to 22/23
Budget
200,000 200,000 0 0 0 To fund one off operational saving CS04 agreed for the 2022/23 budget. 200,000 0 0
019 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
NPDO Schools
Contract
166,000 166,000 0 0 0 To fund one off operational saving LRS01 agreed for the 2022/23 budget 166,000 0 0
020 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Transformation
Agenda QIO
100,259 74,274 25,985 0 25,985 Ongoing funding for the QIO post to lead the implementation of the service
transformation programme. The QIO will assist the Executive Director to deliver the
Council’s transformation agenda by developing, analysing and monitoring initiatives and
projects which deliver the vision, values and strategic objectives of the Council.
74,274 25,985 0
021 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Digital Projects:
Hybrid Council
meetings
55,000 55,000 30,000 25,000 Per paper agreed at SMT October 2021 - allocation from Digital Projects (General
Provision to be allocated).  To fund the costs of livestreaming of Council meetings. 
30,000 25,000 0
022 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Councillor IT
Equipment
65,000 65,000 25,000 40,000 To meet the cost of provision of IT equipment for all new Elected Members as a result of
the Local Government Election in May 2022.
25,000 25,000 15,000
023 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Debt Counselling &
Welfare Rights
27,025 27,025 5,573 21,452 To meet the cost of a Debt Counselling and Welfare Rights Management System. 5,573 5,965 15,487
024 Executive Director
(Douglas Hendry)
Legal and
Regulatory
Services
Community Safety
Partnership
16,000 16,000 0 16,000 To earmark the Community Safety Partnership funding received for 2021/22 to be used
for Community Safety Partnership purposes. These monies will be spent on future
Community Safety requirements – most likely to be additional CCTV spend as required -
Likely to be amalgamated with 076 in future.
0 16,000 0
025 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Microsoft 365 300,000 300,000 0 300,000 To be added to existing earmarked reserves to meet increasing MS365 licensing costs
from 2022/23 onwards
0 0 300,000
026 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Growing our Own and
Modern Apprentices
109,150 109,150 95,790 13,360 Funding earmarked to support trainee development and modern apprenticeship
opportunities based on priority workforce risk areas. These areas have been identified
and proposals developed. £95,790 to be spent in 22/23 and £13,360 to be spent in 23/24
to fund a graduate trainee and 3 apprentices to deliver trainee development and modern
apprenticeship opportunities
95,790 13,360 0

Page 131

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
027 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Security Operations
Centre Subscription
76,455 76,455 0 76,455 There is a requirement to pay for a 3-year subscription at £60,000 per annum with a cost
pressure being added to the ICT revenue budget to cover the costs from year 4 onwards. 
There is unallocated funding of £103,545 from the earmarking (172) created at 2020/21
year end for 'Digital Projects' combined with this earmarking to cover these costs for 3
years.
16,455 60,000
028 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Learning and
Development
36,508 36,508 36,508 0 In order to maximise the opportunities and efficiencies of digital learning, this funding will
be used to support the extension of digital learning in order to deliver the Digital Learning
Strategy, which was approved in FQ4 20/21.
36,508 0 0
029 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Implementation of
Gaelic Language Plan
30,000 30,000 0 30,000 Agreed at Council Meeting February 2021.  Provision of funding for delivery and
implementation of the council’s Gaelic Language Plan in recognition of the contribution
that Gaelic makes to economic growth and to the tourism sector, and to enable delivery
of key activities within the plan which currently receive no revenue funding.
0 30,000 0
030 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Establishing HR
Service Centre
30,000 30,000 18,000 12,000 To facilitate the implementation of technical efficiency improvements and new processes 18,000 12,000 0
031 Executive Director
(Kirsty Flanagan)
Customer
Support Services
Business
Development Training
27,601 27,601 1,000 26,601 This budget is funding ongoing leadership development, coaching, action learning sets
and commissioned training including Priority Management.
1,000 26,601 0
032 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Oban TIF (Tax
Incremental
Financing)
709,700 709,700 60,000 649,700 Will be used to fund the TIF Programme office for a further 3 years as well as the
programme office for Rural Growth Deal beyond the funding that was agreed at Council
for this in February 2021.
60,000 116,000 533,700
033 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Strategic Events &
Festivals
115,764 115,764 35,000 80,764 At the Council meeting on 25 February 21, a decision was taken to agree £90k funding for
Events and Festivals for 22/23, in order that the application process can commence
during 21/22 and that this agreed figure be augmented by any underspend remaining
from the 20/21 financial year.  At 24 February 22, decision made to agree £90k for 23/24,
in order that the application process can commence during 22/23 and that this agreed
figure be augmented by any underspend remaining from the 21/22 financial year
35,000 80,764 0
034 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Island Post 50,461 50,461 0 50,461 To fund a temporary post at LGE11 to assist with the National Islands Plan
Implementation Route Map 2020-2025.
0 50,461 0
035 Executive Director
(Kirsty Flanagan)
Development
and Economic
Growth
Royal National Mod 40,000 40,000 20,000 20,000 One off funding allocation for the Royal National Mod agreed as part of the budget
setting process for 2019/20. Grant contract issued. Proposed payment of £20k per annum
starting 2020/21  (2023/24 final payment of £20k)
20,000 20,000 0
036 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Waste Variation
Monies
1,492,997 1,492,997 0 1,492,997 This would be used to fund/part-fund various waste infrastructure projects that will
support the council’s compliance with the 2025 ban on the Landfill of Biodegradable
Municipal Waste, including the development of landfill cell construction works at
Gartbreck.  £640k for Capital works on Gartbreck completed in 2022/23, reserve will be
drawn down for this in 2023/24.
0 1,066,000 426,997
037 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Climate Change 500,000 500,000 500,000 0 At the Council meeting on 27 February 20, it was agreed to input £500k budget to
mitigate the impacts of weather related damage and climate change with specific
emphasis on gully cleaning and drainage improvements.  Spend has been delayed due to
COVID and the intention is to spend the funds on 2 Gully Motors plus staff over next 2
years. Vehicles have been received and budget will be drawn down to cover their cost.
The remaining budget will be used towards running the vehicles.
500,000 0
038 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
3G pitches / Tarbert
Sports Pitches
427,286 44,660 382,626 5,340 377,286 In November 2018, the Council agreed to a maintenance funding package to be
progressed for a number of 3G pitches including Tarbert. This funding will provide an
estimated 6.5 years’ worth of ongoing maintenance up to 2025-26.  Final drawn down for
22/23 will be done closer to year end once final costs are confimed.
50,000 90,000 287,286
039 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Green Transport
Initiatives
400,000 400,000 260,000 140,000 At the Council meeting on 27 February 20, it was agreed to input £400k in Green
transport, investment in footway and cycle path maintenance supporting the healthy
wellbeing and green agenda.  Spend has been delayed due to COVID and this will be taken
forward in 23/24. £260k Footways Reconstruction programme now spent and will be
drawn down against capital programme during 23/24. £140k Ardrishaig North Project will
be soent in 22/23 and drawn down in 23/24.
260,000 140,000 0
040 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Waste Strategy 363,000 56,070 306,930 49,211 257,719 To fund/part-fund various waste projects that will support the council's compliance with
the 2025 ban on the Landfill of Biodegradable Municipal Waste.  Final draw down in
22/23  for Welfare Units at Waste Disposal sites on Mull and Tiree and Shed
Improvements on Tiree once final invoices are received.
105,281 129,000 128,719
041 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Waste Management 256,753 10,040 246,713 19,960 226,753 Will be used towards long term waste management strategy/model, including but not
limited to scoping work for the creating of a waste transfer station at Helensburgh. 
Consultancy fees and ground investigation works in 22/23 to be drawn down once final
invoice is received.
30,000 135,000 91,753

Page 132

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
042 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Replacement Signage
and Bins
135,366 135,366 135,366 0 Replacing key road signage. This will help to reduce future budget pressures for
replacement of signs and would also help to enhance the streetscape and general
appearance of the area.  The bulk of Road signs have been delivered and installation is
now in progress and will be completed during 2022/23.
135,366 0 0
043 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Kintyre Recycling
Redundancy Costs
36,000 19,588 16,412 0 0 0 To fund redundancy costs associated with Kintyre Recycling. 19,588 0 0
044 Executive Director
(Kirsty Flanagan)
Roads &
Infrastructure
Amenity Services
introduction of
management
information system
28,099 28,099 0 28,099 Delay with introduction of amenity time recording system due to increased costs. 
Discussions ongoing to find alternative cheaper solution.
0 28,099 0
045 Non Departmental Non
Departmental
Underwriting
development of
Rothesay Pavilion
1,000,000 1,000,000 0 1,000,000 Funding to meet additional costs identified as necessary for the refurbishment of
Rothesay Pavilion.
0 0 1,000,000
046 Non Departmental Non
Departmental
Loans Fund 385,279 385,279 0 385,279 At the Council Budget meeting on 24 February 2022, Saving FS01, a Loans Fund
Management/Operational saving for 22/23 budget of £0.500m was agreed with at least
£0.200m to come from underspends in 21/22.  The underspend position for 21/22 is
£0.385m and this earmarking is being released as a saving to help bridge the 2023/24
budget gap.
0 385,279 0
047 Non Departmental Non
Departmental
Utilities 283,000 283,000 283,000 0 To contribute towards the expected adverse impact on the 2022/23 budget of utility
costs inflation as per Budget Pack. Funding will be drawndown by the end of March 2023.
283,000 0 0
048 Non Departmental Non
Departmental
Digital Projects
(General Provision to
be allocated)
103,545 103,545 60,000 43,545 It has been agreed to use the balance of this earmarking towards the Security Operations
Centre Subscription unspent budget request - per Appendix 2.1  This sum plus earmarked
reserve (85) combine to £180k and will cover the subscription for 3 years 22/23 / 23/24 /
24-25
60,000 43,545 0
049 Non Departmental Non
Departmental
Community Resilience
Fund
76,447 76,447 0 76,447 Fund established in 2012/13 to be spent over more than one year. Fund reduced at the
Council meeting on 11 February 2016
0 0 76,447
050 Non Departmental
/ Chief Executive's
Unit
Across Services /
Chief Executive's
Unit
Information
Management
(Balance of Funding)
209,844 209,844 0 209,844 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k, document management and workflow system for
Planning, Building Standards and Environmental Health £77k and a balance of funding to
explore information management solutions in a strategic and coherent way £209k
0 0 209,844
051 Non Departmental
/ Executive
Director (Douglas
Hendry)
Across Services /
Commercial
Services
Information
Management (Estates
Survey Work)
12,697 12,697 0 12,697 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k, document management and workflow system for
Planning, Building Standards and Environmental Health £77k and a balance of funding to
explore information management solutions in a strategic and coherent way £209k
0 12,697 0
052 Non Departmental
/ Executive
Director (Douglas
Hendry)
Across Services /
Legal and
Regulatory
Services
Information
Management
(Digitalisation of Title
Deeds)
92,000 92,000 0 92,000 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k (delay on spending due to COVID-19), document
management and workflow system for Planning, Building Standards and Environmental
Health £77k and a balance of funding to explore information management solutions in a
strategic and coherent way £209k
0 92,000 0
053 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Customer
Support Services
Digital Projects (Digital
Customer
Engagement Projects)
73,000 73,000 73,000 0
To deliver a number of Digital Service Transformation Projects, specifically Customer
Engagement.  These include £25.5k for an upgrade to contact centre systems (Converse),
£9.7k for a voice chatbot pilot, £15k for Alexa smartspeaker services, £22.8k for Proactive
Notification Service (Eloqua).   All of these have been implemented in 2022/23 and will be
drawn down in January.
73,000 0 0
054 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Customer
Support Services
Digital Projects
(Increase in Schools
Bandwidth)
63,455 63,455 0 63,455 To deliver a number of Digital Service Transformation Projects, specifically in Education
and Customer Support Services, but also to reserve a further amount to support priority
digital transformation projects identified in Departmental ICT programmes, that have not
yet started due to resource constraints.  The specific projects include: Supply Staff
Booking System £0.035m, Skype for Business (for Education) £0.030m, Enhancing
Curriculum Choice and Equity of Provision £0.080m, Digital Customer Engagement
Developments £0.073m, Replacement of Learning Management System £0.030m,
Increase in Schools Bandwidth £0.063m and a general provision still to be allocated
£0.189m
0 63,455 0

Page 133

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawn down in
22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to
be Spent in
2023-24
Amount
Planned to be
Spent from
2023-24
onwards
055 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Customer
Support Services
Digital Projects
(Replacement
Learning
Management System)
11,470 11,470 11,470 0 To deliver a number of Digital Service Transformation Projects, specifically in Education
and Customer Support Services, but also to reserve a further amount to support priority
digital transformation projects identified in Departmental ICT programmes, that have not
yet started due to resource constraints.  The specific projects include: Supply Staff
Booking System £0.035m, Skype for Business (for Education) £0.030m, Enhancing
Curriculum Choice and Equity of Provision £0.080m, Digital Customer Engagement
Developments £0.073m, Replacement of Learning Management System £0.030m,
Increase in Schools Bandwidth £0.063m and a general provision still to be allocated
£0.189m
11,470 0 0
056 Non Departmental
/ Executive
Director (Kirsty
Flanagan)
Across Services /
Development
and Economic
Growth
Information
Management
(Document
Management and
Workflow for
Planning, Building
Standards and
Environmental
Health)
57,491 36,314 21,177 0 21,177 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of change as
outlined in the BV Review.  The planned initiatives include: Estates Survey work £122k,
Digitalisation of Title Deeds £92k, document management and workflow system for
Planning, Building Standards and Environmental Health £77k and a balance of funding to
explore information management solutions in a strategic and coherent way £209k
36,314 21,177 0
10,458,934 869,704 16,412 0 9,572,818 2,033,656 7,539,162 2,903,360 3,932,364 3,606,798

Page 134

APPENDIX 2
COVID
As at 31 December 2022
Ref Department Service Description Opening
Balance
Budget
Drawdown
Released
back to
General
Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawndown
in 22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent from
2023-24
onwards
001 Chief Executive's
Unit
Community
Planning
Community
Planning - temp
post to support
communities
55,000 55,000 55,000 0 As agreed at Policy & Resources committee on 9 December 2021, allocation of
£0.055m to a post to support the economic and social recovery together with
the building back stronger themes.
55,000 0 0
002 Chief Executive's
Unit
Community
Planning
COVID-19 - Test
and Protect
Support
44,047 0 44,047 44,047 0 Funding provided in relation to the Local Self-Isolation Assistance Service.  The
Community Planning and Development Team will work with community groups
to support their community response and resiliency to Test and Protect and
the longer term impacts of COVID-19 on local community organisations.
44,047 0 0
003 Chief Executive's
Unit
Financial
Services
LACER Fund 797,720 797,720 0 0 0 The Council meeting on 28 April 2022, it was agreed that Local Authority Covid
Economic Recovery (LACER) Funding is to be used to distribute Scotland Loves
Local cards to CTR recipients. This will take place in June 2022 giving Economic
Development time to encourage the Co-op to sign up to accept the cards.
Actual spend on this fund is £841,317, the overspent balance will be funded
from a combination of the Recovery and Renewal Fund (£36,713 as agreed at
P+R Committee in December 2022)and Benefits earmarking 008 (£6,884).
797,720 0 0
004 Chief Executive's
Unit
Financial
Services
Housing Benefits
Private
231,027 231,027 84,884 146,143 Specific funding allocation for Housng Benefit including DHP. Funds will be
used to continue to support vulnerable people initially financially affected by
the COVID-19 outbreak but now facing the cost of living crisis to sustain their
tenancies.  There is a projected overspend of £133,000 in SWF fund for 22/23
and it is expected that this pressure will continue into 23/24. £55,000 will be
taken from earmarking ref 012 and £78,000 from this earmarking to cover the
projected SWF overspend inn 22/23. In addition £6,884 of funds will be used to
offset the overspend on the Scotland Loves Local Cards in the LACER fund
(earmarking ref 007). The reminaing £109,430 will be used to support
DHP/SWF spend in 23/24.
84,884 146,143 0
005 Chief Executive's
Unit
Financial
Services
Flexible Food Fund 510,573 224,164 286,409 92,792 193,617 Financial Insecurity funding from Scottish Government routed into the Argyll
and Bute Flexible Food and Fuel Fund (ABFFFF) is aimed at tackling financial
insecurity for adults and families across Argyll and Bute.  Working in
partnership with the Community Food Forum, Bute Advice Centre and
ALIenergy, households with low incomes and no access to cash savings can
apply for immediate financial support.  The Fund helps support daily living
expenses.   In the period from 10 January 2021 to 30 November 2022  client
gain in extra benefits income for families was £2.25 million with 1,550 families
had been supported. The project has been extended to 31 March 2025 with
funding coming from the UK Shared Propsperity Fund and this earmarking to
support it. It is proposed that underspends from the Flexible Funding for
Supporting People at tier 4 COVID wil be used to support this project over the
next two years to cover a funding gap of £50,000. The Scottish Government
have provided this funding and have endorsed this award winning project
promoting it as part of the solution to end the need for foodbanks nationally.
316,956 108,000 85,617

Page 135

Ref Department Service Description Opening
Balance
Budget
Drawdown
Released
back to
General
Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawndown
in 22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent from
2023-24
onwards
006 Chief Executive's
Unit
Financial
Services
Flexible Funding for
Supporting People
while at Tier 4
COVID
167,983 65,537 102,446 37,446 65,000 Funding from SG to strengthen local authority responses to meet emerging
needs and support people in their communities struggling with the restrictions
and guidance at all protection levels re COVID, particularly those at risk
through health and social inequalities. This support could cover the same types
of support.  In June 2021 the Council agreed to support 20 projects led by a
range of Council officers, officers from the HSCP and members of the third
sector to deliver wide ranging support across our region. Projects will come to
a conclusion on 31 March 2023 with the exception of one HSCP project which
will spend its remaining £15,000 in 23/24. Projected underspend is £65,000 in
total. A report will be presented to ELT after yeared givign them a full update
on the use of the funds and recomending that the remaining balance of
£50,000 be transferred to the earmarked reserve suppoting the Argyll and Bute
Flexcible Food and Fuel Fund through to 31 March 2025 (earmaking ref 009).
SG has indicated that they support this project and the use of funds.
102,983 65,000 0
007 Chief Executive's
Unit
Financial
Services
Self Isolated
Support Grant
16,000 16,000 1,000 15,000 Unspent admin funding for processing Self isolation Support Grants. Only
£1,000 required in 2022/2023. Scheme now closed, balance of funding should
be added to the Scottish Welfare Fund earmarking ref 012 to support
vulnerable customers affected by the Cost of Living Crisis with Crisis Grants
1,000 15,000 0
008 Chief Executive's
Unit
Financial
Services
Test and Protect
Extension
9,929 9,929 9,929 0 Funding provided in relation to the Local Self-Isolation Assistance Service.  This
has been used to support the recruitment of 0.5FTE LGE6 temp post to assist
with call volumes in the Scottish Welfare Fund team in 2022/23 - reserve will
be drwndown by year end.
9,929 0 0
009 Executive
Director (Douglas
Hendry)
Education Logistics Funding -
Safe Opening of
Schools
940,605 98,089 842,516 108,911 733,605 Scottish Government funding to ensure the safe opening and operation of
schools. Includes transport, PPE, cleaning, ventilation and expansion of estate.
It is likely that any unused balances would have to be returned to the Scottish
Government.
207,000 733,605 0
010 Executive
Director (Douglas
Hendry)
Education Additional
Teaching/Support
in Schools/Digital
Devices/Family
Home Learning
Support Fund -
£45m Grant
488,310 488,310 0 0 0 Continuation of funding for additional staffing, teachers, support staff,
additional devices for pupils and additional family /home learning
programmes.
488,310 0 0
011 Executive
Director (Douglas
Hendry)
Education COVID 19 -
Education
Recovery -
Additional Staff in
School and ELC
settings
373,346 373,346 0 0 0 To employ a variety of school staff to meet the needs of children and young
people in their local areas and ensure that levels of teaching and support staff
in schools can be maintained.  Funding will also be used to support the
transition from ELC to primary school.
373,346 0 0
012 Executive
Director (Douglas
Hendry)
Education Education to
Support Young
People
321,816 178,310 143,506 0 143,506 As agreed at the Council Meeting on 25 February 2021 with an original
allocation of £0.600m.  Agrees to fund a package of measures to boost the
wellbeing and build back the resilience of young people, in particular those
most vulnerable, following the Covid-19 pandemic, including counselling and
increased provision of childcare for children under three. Notes that the
Scottish Government is yet to confirm details of funding for similar initiatives
and, should our investment in children’s wellbeing qualify for this funding, the
balance will be re-allocated to the Recovery and Renewal Fund. 
178,310 87,307 56,199
013 Executive
Director (Douglas
Hendry)
Education Recruitment of
Additional
Teachers and
Support Staff in
Schools
136,715 136,715 0 0 0 Fund additional teachers and support staff. 136,715 0 0

Page 136

Ref Department Service Description Opening
Balance
Budget
Drawdown
Released
back to
General
Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawndown
in 22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent from
2023-24
onwards
014 Executive
Director (Douglas
Hendry)
Education EDU - Community
Mental Health and
Wellbeing Support
to Children and
Young People -
Pandemic Funding
49,756 49,756 0 0 0 Scottish Government/COSLA Initiative to support the work under the Children
and Young People's Mental Health and Wellbeing Programme grant split in
2020/21 with £183,750 of the fund utilised by local collaborative partnerships
for supporting children, families and carers through the pandemic.  The
Scottish Government has agreed for the balance to be spent in 2022/23.
49,756 0 0
015 Executive
Director (Douglas
Hendry)
Legal and
Regulatory
Services
Welfare Rights
Support
172,000 172,000 38,954 133,046 As agreed at the Council Meeting on 25 February 2021 - an allocation of
£0.172m.  As part of our focus on Improving Opportunities for People and
Communities, agrees to provide additional resources to proactively support
people experiencing poverty and hardship, by investing in two additional
Welfare Rights support staff for two years.
38,954 77,908 55,138
016 Executive
Director (Douglas
Hendry)
Legal and
Regulatory
Services
LACER Funding -
Advice Services
130,000 130,000 0 0 0 Local Authority COVID Economic Recovery (LACER) Funding for Welfare Rights -
ALI Energy, Bute Advice, Citizens Advice
130,000 0 0
017 Executive
Director (Kirsty
Flanagan)
Customer
Support
Services
Self Isolated
Support / Self
Isolated Support
Grant (HR)
115,000 115,000 115,000 0
These were monies that were provided by Scotgov to fund additional overtime
and resources for Shielding/Caring for People and Test and Protect activities,
however efficient delivery practices in A&B meant that this was not required in
2020/21 or 2021/22.
The funds are being used for a number of Customer Service and Business
efficiency related projects including £68,000 will be used to fund a system and
consultancy of RPA (robotic process automation) and application development.
£49,750 will be drawn down in January. The remaining training and
consultancy will hopefully be completed this year. £42,500 has been allocated
to a full corporate website upgrade and renewal using specialist web
resources. £30k of this will be drawn down in January and the rest on website
launch in February. The remaining £4.5k is for the remaining milestones on the
Digital Reception Project and will be drawn down in March.
115,000 0 0
018 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
Staycation and
Marketing Argyll
and Bute
592,013 156,342 435,671 135,671 300,000 As agreed at the Council Meeting on 25 February 2021 with an original
allocation of £0.800m.   This will include provision of additional waste disposal
facilities and other facilities that will be informed by the Motorhome and
Informal Camping Survey.
292,013 300,000 0
019 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
Tackling Digital
Exclusion Top-Up
Fund
250,000 250,000 40,000 210,000 As agreed at the Council Meeting on 25 February 2021.  Establishes the
Tackling Digital Exclusion Top Up Fund to support communities and in some
cases individuals that are missing out on national programmes due to logistics
and economies of scale.  While vouchers are available from the UK and Scottish
Governments in some cases these do not cover the full cost of infrastructure
builds. £40k anticipated  spend by 31 March 2023.
40,000 210,000 0
020 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
LACER Funding
(Small Business
Development
Grant)
200,000 69,413 130,587 130,587 0 Local Authority COVID Economic Recovery Fund grant.  This funding will
provide funding of between £500 and £5,000 to help existing micro and small
businesses to improve their resilience or growth via projects to implement
green initiatives, implement digital development, implement marketing
improvements and improve efficiency/innovation.  Fully committed and all
payment should be made and draw down processed prior to 31 March 2023.
200,000 0 0
021 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
LACER Funding
(Sector Support
Grant)
150,000 17,100 132,900 57,900 75,000 Local Authority COVID Economic Recovery Fund grant.  This will provide
funding, either part of the small  business development grant or standalone, to
help micros and small business to implement projects that contribute to the
sector as well as benefitting the business, for example: Tourism and hospitality,
food and drink or retail.  With option to provide additional business support to
hard hit areas including Bute and Kintyre where unemployment remains higher
than average - support via specialist advice, locally tailored grants to meet local
priorities and targeted marketing activity.
75,000 75,000 0

Page 137

Ref Department Service Description Opening
Balance
Budget
Drawdown
Released
back to
General
Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawndown
in 22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent from
2023-24
onwards
022 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
LACER Funding
(New Enterprise
Support Grant)
120,000 45,000 75,000 65,000 10,000 Local Authority COVID Economic Recovery Fund grant.  This funding would
provide £3,000 grants to help new businesses start up and establish.  Fund fully
committed, although there might be slight delay in getting all payments made
and some may come out of 23-24.
110,000 10,000 0
023 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
Staycation
Investment per
budget pack
February 22
100,000 100,000 0 100,000 As agreed at Council on 24 February 2022, Staycation investment £0.100m. 
Augments the 2021/22 £0.5m staycation initiative with an additional
investment of £100k, including support for community groups and partners in
the provision of facilities which can support increasing staycation visitor
numbers during the 2022/23 and 2023/24 seasons.
0 100,000 0
024 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
Economic
Development -
temp post to
support economic
recovery
55,000 55,000 0 55,000 As agreed at Policy & Resources committee on 9 December 2021, allocation of
£0.055m to a post to support the economic and social recovery together with
the building back stronger themes.
0 55,000 0
025 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
EH Covid Posts 41,145 41,145 41,145 0 Funding for 2 posts for 2 years.  Recruitment unscuccessful, agency staff have
been used instead.  Draw down will be processed once final costs known at
end of year.
41,145 0 0
026 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
LACER Funding
(Shop Local)
40,000 40,000 15,000 25,000 Local Authority COVID Economic Recovery Fund grant.  This funding would
provide funding to continue the Shop Local scheme into 2022/23 and 2023/24,
buying additional cards and allow the cards to gather momentum and support
local businesses.
15,000 25,000 0
027 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
Tenant Hardship
Fund
30,000 30,000 0 0 0 Grant received from Scottish Government to support tenants suffering
hardship due to COVID-19.  Claims have been made and Housing are in the
process of paying these out and all claims will be settled during 2022/23.
30,000 0 0
028 Executive
Director (Kirsty
Flanagan)
Development
and Economic
Growth
LACER Funding
(Gypsy Travellers)
10,000 10,000 5,500 4,500 Local Authority COVID Economic Recovery Fund grant.  This funding would pay
for MECOPP (Minority Ethnic Carers of People Project) to engage with the
Gypsy Travellers community on the important subject of the cost of living
increases, fuel poverty and the impact of factors such as their remote rural
locations and the facilities available to them for everyday living  have on their
livelihoods.  Claim for 22/23 awaited from ACHA, earmarking will be drawn
down once received and paid.
5,500 4,500 0
029 Non
Departmental
Across
Departments
COVID Cost
Pressures Beyond
2021/22
370,000 77,000 293,000 293,000 0 As agreed at the Council Meeting on 25 February 2021 (£2.5m)  with the value
reduced to £0.370m based on more up to date projections at year end
2021/22.  Allocation of COVID funding to projected 22/23 Revenue Cost
Pressures
370,000 0 0
030 Non
Departmental
Non
Departmental
Recovery and
Renewal Fund
1,547,000 1,547,000 186,713 1,360,287 As agreed at Council on 24 February 2022, Recovery and Renewal Fund
£1.547m.  This is provision for future recovery, regeneration and renewal, as
well as any future pressures which may arise following the Covid-19 pandemic
through a dedicated Recovery and Renewal Fund.  Proposals for use of this
fund to be brought forward by officers to the Policy and Resources Committee.
To include in the first instance options for maximising Argyll and Bute’s
potential as a green, connected staycation destination of choice, requesting
that officers bring to the Environment, Development and Infrastructure
Committee a report on use of external funding sources and other opportunities
for improving the electric vehicle charging network.
186,713 1,360,287 0
031 Non
Departmental
Non
Departmental
Unallocated Admin
Support Grant
411,285 411,285 0 0 0 Funding to support the delivery of the Business Grants to local businesses,
partially used during 20/21 and 21/22. The unused balance to be returned to
the General Fund in 2022/23.
0 0 0
032 Non
Departmental
Non
Departmental
Capital pressure 257,000 257,000 0 257,000 Pressure identified on the 20/21 COSLA COVID costs spreadsheets - requires to
be earmarked to be drawn down when required against the Capital Plan
0 257,000 0
033 Non
Departmental
Non
Departmental
Levelling up Fund
bids per P&R
February 22
150,000 150,000 150,000 0 As agreed at Policy & Resources committee on 17 February 2022, an allocation
of  up to £0.150m to support Levelling Up Fund bids
150,000 0 0

Page 138

Ref Department Service Description Opening
Balance
Budget
Drawdown
Released
back to
General
Fund
New
earmarking
during 22-23
Remaining
Balance
Still to be
drawndown
in 22-23
Planned to
spend in
future years
Plans for Use Amount
Planned to be
Spent in 2022-
23
Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent from
2023-24
onwards
034 Non
Departmental
Non
Departmental
CHARTS per budget
pack February 22
75,000 50,000 25,000 25,000 0 As agreed at Council on 24 February 2022, investment in CHARTS £0.075m.  To
support the organisation in delivering targeted support, in communities, to the
culture, arts and heritage sector as part of its plans to contribute to overall
economic recovery.
75,000 0 0
035 Non
Departmental
Non
Departmental
CHARTS 7,000 7,000 0 0 0 As agreed at the Council Meeting on 25 February 2021.  Allocation of COVID
funding to CHARTS £0.067m, with the balance of £0.007m carried into
2022/23.  The allocation was to ensure that Argyll and Bute’s culture, heritage
and arts sector can make a contribution to our overall recovery and renewal.
7,000 0 0
8,965,270 2,993,802 411,285 0 5,560,183 1,733,479 3,826,704 4,727,281 3,629,750 196,954