Council Decarbonisation Plan Tracker

Argyll and Bute Council · 11 May 2023
Back to Policy and Resources Committee — 11 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL                  POLICY & RESOURCES COMMITTEE
CLIMATE CHANGE BOARD                                                                     11th May 2023     
COUNCIL DECARBONISATION PLAN TRACKER 
1.0   EXECUTIVE SUMMARY 
1.1 The Council’s Decarbonisation Plan sets a 3 year framework to continue our
climate journey and routemap to net zero which was approved in December
2021.  Our Council has made a clear commitment to be a net zero organisation
by 2045 and has also declared a climate emergency befitting the importance
and critical nature of the topic.   
1.2 Whilst the main Decarbonisation Plan will be fixed for 3 years the associated
Action Plan (which forms an Appendix of the document) will be continuously
updated and reported to both the Climate Change Board and Policy &
Resources Committee.   
1.3 The latest update can be found at Appendix A.   
2.0  RECOMMENDATIONS
2.1 That the Policy & Resources Committee:
2.1.1 Note and consider the updated De-Carbonisation Tracker. 
3.  IMPLICATIONS
3.1 Policy – This paper content is entirely consistent with climate change
policy and action at local, national and international level.
3.2 Financial – Not specific but many actions will have individual and
cumulative financial implications.  
3.3 Legal – Meeting requirements of Climate Change Scotland Act.  
3.4 HR – None 
3.5 Fairer Scotland Duty 
3.5.1 Equalities – Protected characteristics – None

Page 2

3.5.2 Socio economic Duty – Creating warmer or more efficient
homes that are cheaper to heat is a positive for all.  
3.5.3 Islands – None specific
3.6 Climate change – Direct link to meeting net zero obligations for our
Council.    
3.7 Risk – Not addressing impacts or causes of climate change can lead to
increased cost or censure if targets are not met.  
3.8 Customer Service – Creating warmer or more efficient homes that are
cheaper to heat is a positive for all.  
Douglas Hendry
Executive Director with responsibility for Commercial Services 
Councillor Ross Moreland
Policy Lead Climate Change & Environment 
5th April 2023 
For further information contact: 
Ross McLaughlin
Head of Commercial Services 
The Helensburgh and Lomond Civic Centre
ross.mclaughlin@argyll-bute.gov.uk

Page 3

Appendix A – Climate Change Tracker
ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
W1 –Develop and Implement
Waste Strategy 
(L) Roads and
Amenity
Services,
Community,
commercial
customers
Implementation
of the Waste
Strategy
transitioning to
Landfill ban
compliant
Residual Waste
Recovery
solutions by
2025.
External funding and support
being sought from the Scottish
Government
An options appraisal was
conducted by an external
consultant. This document and
an Officer report was prepared
for ED&I committee in
December. The main focus of
the report was to approach the
Scottish Government (SG) to
request a derogation for the
area covered by the PPP
contract, and to also liaise with
Renewi to progress discussions
around landfill ban compliance
should a derogation not be
given by SG. This engagement
continues by Officers and
elected members.
W2 – Promote the Waste
Hierarchy through community
Education 
(L) Roads and
Amenity
Services
Evidence of
community
Education
Not secured New Web content and
Education materials for
Primary and Secondary Schools
were developed and delivered
to online Education
Environment Summit October
21 and the COP 26 Event on
the 6th November 21.

Page 4

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
W3 – Reduce Council use of
disposable and single use plastics
across all departments and
settings 
(L)
Procurement
and
Commercial
Services, all
Council
Services 
Adoption of new
working
practices and
procurement
No specific funding in place,
research required to impact on
operation costs 
A report on Single Use Plastic
went to the Policy and
Resources Committee on 9
December 2021, and the
following recommendations
were approved:
 Note and consider that
the various Services
that currently purchase
SUP products consider
whether these products
are essential or if there
is a potential
alternative that would
meet the Service
requirements, prior to
orders being placed via
PECOS or contacting
the Procurement,
Commercial and
Contract Management
Team (PCCMT) for a
procurement process
to be carried out.
 Note and consider that
the Sustainable

Page 5

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Procurement Policy will
be updated to reflect
the Climate Change
Board desire to limit
SUP where possible –
wording has been
included in the Annual
Review 2023/2024
version of the
Procurement Strategy
2022/2025 as follows:
“To provide
procurement support
to any strategic
decisions taken by the
Council in relation to
the usage of Single Use
Plastic products and
their recyclability.” 
 Note and consider that
the Commodity
Sourcing Strategy
templates used for
Regulated
Procurements have
been updated to
include a question

Page 6

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
regarding SUP.
Changes in legislation were
brought into force by the
Scottish Government on the
1st June 2022 restricting
single-use plastic cutlery,
plates, straws, drink stirrers
and balloon sticks, expanded
polystyrene food containers
and expanded polystyrene
cups and other beverage
containers, as well as all
products made of oxo-
degradable plastic.  
Some products already
changed and others under
review. 
W4 – Extend and explore pre-
ordering for school food to reduce
food waste 
(L) Commercial
Services and 
Education 
Evidence of
extension of
pre-ordering &
food waste
reduction
Project funded and solution
procured
Project Team currently
implementing this, with full
project end date estimated as
June 2023. 
E1 – Deliver Renewable Sourcing
Strategy 2 
(L) Commercial
Services 
Adoption of
Strategy
RSS2 consultancy work funding
to be confirmed; expectation is
that project implementation
will be through combinations
of prudential borrowing
RSS2 next stage development
work includes specification
development and preparation
of invitation to tender for
specialist consultancy

Page 7

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
(subject to business case
approvals) and/or external
funding. 
support. Current work in
progress; intended to be
market tested during 2023.
E2 – Delivery of Non-domestic
Energy Efficiency Framework
(NDEEF) Projects 
(L) Commercial
Services 
Evidence of
delivery of
projects
Project development work is
funded by combinations of the
Scottish Government and the
procured provider (costs
absorbed within the tender
process). 
Funding for project
implementation will come from
Council approved capital
allocations:
 Climate Change 20/21 -
£500K
 Climate Change 21/22 -
£600K
 Asset Sustainability – 
£175K
NDEEF Energy Performance
Contract was signed on 16 July
2021 (circa £1.2m investment
with 10 year payback). The 
NDEEF mini project list has
been fully delivered with the
exception of three final mini
projects which are currently
being scheduled for
installation. It should be noted
that there has been some
variation to the mini project list
originally intended; mainly on
account of accommodation
reviews and technical risks
identified during detailed site
survey; where originally
identified projects have not
proceeded, alternative projects
have been introduced in their
stead. 
In addition to the above, the
procurement sourcing strategy

Page 8

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
for the next batch of sites,
using designation NDEEF2, is
under way.
E3 – Delivery of additional solar
installations at Council assets 
(L) Commercial
Services 
Evidence of
delivery of
projects
Consultancy work funding to
be confirmed; expectation is
that project implementation
will be through combinations
of prudential borrowing
(subject to business case
approvals) and/or external
funding.
Solar pv Options (initial
feasibility work completed for
circa 9 further sites) – some
opportunities absorbed within
NDEEF (Ref item E2) as project
replacements due to
accommodation reviews etc. A
‘mop up’ of remaining project
prospects intended to be
market tested as a component
within an upcoming solar pv
maintenance contract in 2023.
E4 – Delivery of Water Efficiency
Audits across our Estate 
(L) Commercial
Services 
Evidence of
delivery of
projects
Feasibility work being absorbed
within existing approved
budgets. 
Individual works items are
generally small scale and it is
proposed to utilise existing
approved budgets where
possible.
Significant Council wide asset
verification exercise and
ensuring water use minimised. 
This project is substantially
complete but will continue
further into 2023 when a case
study will be prepared to
demonstrate the range of tasks
undertaken and to convey the
reduction in water
consumption (with carbon
emissions reduction) and costs

Page 9

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
arising from this already
successful project.
E5– Delivery of Energy Efficiency
Scotland Programme 
(L) Housing
Services,
Registered
Social
Landlords 
Evidence of
delivery of
projects
Funding amounts are
determined by localised factors
and is paid as a  proportion of
the Scottish Governments’
Heat In Buildings Strategy 
The Scheme is projected to
spend all of its £2,011,323
budget for 2022/23 plus a
further £300,000 which was
awarded by the Scottish
Government to meet the
demands of an increased
number of applications in
2022/23.   Additionally Argyll &
Bute Council was awarded
£2.23m by the Scottish
Government to complete a
programme of insulation works
in conjunction with Argyll
Community Housing
Association on mixed tenure
properties throughout Argyll &
Bute.   The Scheme continues
to successfully deliver
insulation measures
throughout Argyll & Bute in
accordance with the Scottish
Governments “Fabric First”
principle.

Page 10

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
E6 – Complete LED streetlight
replacement programme 
(L) Roads and
Infrastructure
Services
Evidence of
delivery of
projects
Fully funded through
prudential borrowing
Contractors have now
commenced works  in the Lorn
Area to progress the last
installation phase of the
project and have a programme
of approx. 4-6 weeks to install
1100 new LED luminaires. 860
have now been installed and
delivery of some additional
luminaires is awaited before
contractor completes in the
Lorn area.  All works in the
Oban area should be complete
by the end of May 2023.The
Council has 14442 streetlights
in total so carbon emissions
have already been greatly
reduced by the LED Upgrade
Project.
2021/22 figures were CO2
totals 738 tonnes, this has
been reducing year on year,
back in 2015/16 figures were
CO2 Totals 3140 tonnes.
2022/23 emissions are forecast
to be reduced by approx. 10 –
15% on the 2021/22 figures.

Page 11

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
E7 – Continue support of ABRA
and review Renewable Energy
Strategy annually 
(L) Economic
Development
Evidence of
delivery of
projects 
Officer resource to support
currently funded
Work to support ABRA
ongoing.  Current ongoing
project by SSE Networks for
renewal of powerlines
between Inveraray and
Crossaig.    Work commenced
on outline business case for
progressing Islay Energy
System work through the Rural
Growth Deal.  Islay was
selected as one of the Carbon
Neutral Islands being
progressed by the Scottish
Government , work is ongoing. 
E8 – Continue support for offshore
development of renewables 
(L) Economic
Development
Evidence of
delivery of
projects
(expected late
2020s/early
2030s)
Officer resource to support
currently funded
Scottish Power Renewables are
progressing the Islay site
(Machair Wind) project with
consultation events held during
2022.  An announcement on
the Crown Estate Scotland
Innovation and Targeted Oil
and Gas (INTOG) leasing has
been made and a site off Islay
identified.

Page 12

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
T1 – Develop a Fleet Replacement
Strategy supportive of fuel
efficient, electric and hybrid
vehicles 
(L) Roads and
Infrastructure
Services
Adoption of
Strategy
Part for current financial year The Strategy is complete, final
review will take place to ensure
the 2025 legislative changes
are included.  The council have
introduced hybrid and electric
vehicles to the Fleet. The
council operates 14% of its
Fleet with the new technology.
T2 – Develop a vehicle routing
system that will reduce road miles
for operations 
(L) Roads and
Infrastructure
Services
Evidence of
delivery of
projects
Part for current financial year  The Council went to tender
earlier this year for route
optimisation and had a number
of bidders. Officers have gone
through the selection process
and a preferred bidder has
been chosen and their bid is
within the budget available. 
They recently provided a
demonstration of their system
which was well received by our
tender evaluation panel.  
Arrangements are being made
with colleagues in
Procurement and IT to finalise
the necessary due diligence
then we will look to award the
contract.

Page 13

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
T3 – Develop an electric vehicle
infrastructure strategy 
(L) Roads and
Infrastructure
Services
Evidence of
delivery of
projects 
Part for current financial year 
The development of the EV
network is funded by external
grant monies from Transport
Scotland, and the costs of
developing the strategy in
terms of staff time are covered
via existing budgets
Ultimately the cost recovery
model 
Work on the strategy
document is now effectively
complete and we have a long
list of sites which will be
recommended to Committee
for formal adoption as well as
ancillary parts of the strategy
around maintenance,
procurement etc. A
comprehensive year-end
report will go to EDI in
December summarising the
current position. The next key
stage is securing enough
external funding and/or
agreeing a delivery model –
self delivery supported by
business case, concession
model or leasing sites, or a
mixture of the three. A high
level analysis of possible
delivery options will also be
contained in the year end
report. 
T4 – Support Digital by Default
theme Service Review & Recovery
Plan to reduce need to travel
All Council
Departments
Evidence of
delivery of
projects
Part for current financial year Council is adopting ‘Our
Modern Workspace’
programme and  Digital First

Page 14

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
approach as services change
and evolve post pandemic.  
T5 – Develop new active travel
plans for Council buildings and our
towns 
(L) Economic
Development
Evidence of
delivery of
projects
£2.9M external funding
secured development and
delivery of Active Travel in
22/23 financial year.
No active travel funding is
provided by Council.  
External competitive challenge
funds are time consuming to
secure and projects have to be
shaped to fit with external
funders’ aspirations and
requirements by the 1.7FTE
staff in the Strategic
Transportation Team.
However, at present these are
the only available source(s) of
potential funding to deliver
active travel improvements.
The purpose of active travel is
to make it as easy as possible
and help to encourage
individuals, businesses and
visitors to choose to walk,
wheel or cycle for local
journeys.  Increasing activity
and reducing sedentary
behaviour has significant
health benefits and can
increase accessibility to
essential services, education,
employment, retail and
leisure.  Walking and cycling
are lower cost travel modes
and, if they are a viable option,
can help households reduce
their reliance on private cars,
particularly multiple car
households.
No Council funding is currently
expended on Active Travel
work, with all costs, including
internal staff costs (1.7FTE),
having to be funded via

Page 15

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
successfully securing external
challenge funds. As all active
travel work is currently reliant
on securing external funding,
therefore the projects which
are progressed are those which
can successfully secure
external challenge funding. 
Argyll and Bute Active Travel
Strategy: Officers are working
to develop an Argyll and Bute
Active Travel Strategy and
present it for Council by
summer 2024.  The Active
Travel Strategy would provide
the overarching context for the
Council to support and
promote active travel across
the Council area. Having an
adopted and current Active
Travel Strategy is increasingly
becoming a pre-requirement
to access Scottish Government
derived active travel funding. 
Active Travel Delivery Plan:

Page 16

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Following approval of Active
Travel Strategy, an Active
Travel Delivery Plan will be
developed to create a
prioritised list of active travel
projects for the whole of Argyll
and Bute. 
Active Travel Projects: The
majority of external funding
available is provided by the
Scottish Government via a
number of third sector
organisation who are paid to
administer these funds.  The
focus for Scottish Government
Active Travel funding is to
develop and deliver
infrastructure projects and
associated behaviour
change.  As such, the focus for
the very limited staff capacity
in the Active Travel Team has
been to develop and deliver
infrastructure projects across
Argyll and Bute with a focus on
our main towns and locations

Page 17

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
with strong community
support. 
Active Travel Plans for Towns:
There are Active Travel Plans in
place for the main towns in
Argyll and Bute, albeit some
are now quite historic.  The
town Active Travel Plans focus
on identifying potential active
travel route networks for key
towns.  These provide a
framework for the
development of new active
travel routes, which will enable
and encourage residents,
businesses and visitors to
choose to travel more
actively.  No funding is
currently secured to enable the
Active Travel Plans for towns to
be updated. 
Council Staff Travel Plan: At
present it is not proposed to
progress with development of
a Council Staff Travel Plan.  This

Page 18

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
is due to (a) requirement to
make best use of limited
internal staff capacity; and, (b)
the ongoing uncertainty of
longer-term staff profiles and
bases.  Staff Travel Plans focus
on measures to make it easier
and preferable for staff to
choose to walk, cycle, use
public transport or car share to
commute to work or for work
journeys, or use economical
pool vehicles for work
journeys.   A travel plan should
encourage staff to choose the
most economical and least
environmentally damaging
travel mode.  Engagement will
be required with services
which manage staff in buildings
and/or council buildings as this
is essential to creating
deliverable and effective travel
plans for staff.  This includes
Estates, HR, SMT and building
users.  It is recommended that
work on the Council Staff

Page 19

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Travel Plan is commenced after
a decision has been made on
future staff working patterns
and office rationalisation as
these will have a significant
impact on the Council Staff and
their travel.  There is currently
no funding secured to enable
this work to be progressed.   
PA1 – Review Council Flooding &
Coastal Protection Policy 
(L) Roads and
Infrastructure
Services
Review of policy No specific funding in place,
research required to impact on
operation costs
Reviews are in process. 
PA2 – Review Council Sustainable
Procurement Policy 
(L)
Procurement 
Review of policy  No specific funding in place,
research required to impact on
operation costs
This policy is reviewed on an
annual basis. 
OFF1 – Develop opportunities for
Carbon Offsetting with ACT and
partners 
(L) Climate
Change Board,
ACT and
partners
Delivery of
projects 
Limited funding via ACT for
existing projects
SSEN compensatory planting –
Phase 1 complete, Phase 2
underway with planting at
Kilmory and Dunbeg, which
will complete the LT40
compensatory planting
obligation SSEN allocated to
ACT.  ACT is working with SSEN
to pilot a Biodiversity Net Gain
project in Cowal which would

Page 20

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
see 50 hectares of Rainforest
cleared of invasive
rhododendrons.   
ACT have entered agreement
with Mastercard’s Priceless
Planet Coalition to plant
100,000 native trees in Argyll.
over the coming 5 years.  Sites
confirmed. This planting will
offer opportunities for carbon
credits for landowners. 
ACT are working in partnership
with the Community Planning
Partnership and will be hosting
a Climate Change Officer. 
Funding for initial phase of
work secured. 
ACT undertaking peatland
restoration on Islay, Jura and
extending into mainland Argyll,
supported by ScotGov’s
Peatland Action and Esmee
Fairbairn Foundation.  In
addition to the 2 Islay based

Page 21

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
jobs, we will be offering a 1-
year trainee position in 2024. 
ACTNow project officer has
delivered Carbon Literacy
Training to A&BC Elected
Members and Senior Council
Officers.  Now working on a
carbon literacy initiative for
schools and youth groups.  Also
delivering Bikes Back to the
Community with the support of
Smarter Choices, Smarter
Places funding.  ACT has
recently taken ownership of
two electric bikes available for
groups and businesses to trial. 
A successful bid to the
Community Led Local
Development Fund resourced 
engagement materials and
communications plan to launch
a regional natural capital
strategy.  Initial project
concluded,  Stakeholder

Page 22

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
workshop to progress
scheduled May 2023. 
ACT received development
funding from the Nature
Restoration Fund to survey
invasive rhododendron within
Rainforest zones in Knapdale. 
Currently working with
landowners.  Full bid for rhodo
clearance will be submitted
July 2023. 
ACT leading a consortium of
Alliance for Scotland’s
Rainforest partners to submit a
bid to Facility for Investment
Ready Nature in Scotland – to
facilitate private finance
investment into habitat
restoration.
COMM1- Develop and deliver
Communications Plan to support
Decarbonisation Plan 
(L) Climate
Change Board
and
Communicatio
ns Team
Delivery of
Communications
Plan
Part of Communications
Support 
External communications
We continue to promote
actions the council is taking,
and actions that others can
take, to develop climate-

Page 23

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
friendly Argyll and Bute. For
example:
 Promoting Scottish.
 Cost of living support –
warm spaces.
 Gigha Primary School
Green Flag award.
 £5.58 million secured
to deliver energy
efficiency savings.
 Pupils from Appletree
Nursery and Gigha and
Rosneath Primary
Schools won Keep
Scotland Beautiful
Pocket Garden
Competition.
 Supporting
Communities Fund.
 Advertised job vacancy
to develop Local Heat
and Energy Strategy.
 Progress updates about
Campbeltown Flood
Protection Scheme.

Page 24

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
 Lochgilphead to Crinan
Active Travel Route.
 Promotion of school
uniform recycling
scheme.
 Christmas recycling tips
– how to dispose of
your tree responsibly,
re-use wrapping paper
and how to recycle
Christmas cards etc.
 Promotion of HEEPS.
 Ongoing recycling
reminders.
 Working in partnership
with Argyll Community
Housing Association -
ACHA Group, 406
households across
Argyll and Bute set to
benefit from new
energy efficiency
measures.

Page 25

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
COMM2 - Engage with community
and partners and deliver Climate
Change Directory for our region 
(L) Community
Planning and
Development
Team
Delivery of
engagement
map 
In place until end of financial
year
The CPP Climate Change
signposting page is  live 
https://www.argyll-
bute.gov.uk/cpp-climate-
change   with further entries
added as they are received. 
The dedicated Climate Change
funding opportunities search,
available through the
signposting page, is conducted
and an updated document
produced on a regular basis.
The Community Planning team
provides input and support to
the Climate Change Working
Group which feeds back to the
Community Planning
Partnership Management
Committee.
Through community
engagement data collated over
the past 3 years, Climate
Change was selected as a
priority theme to be included
within the consultation to help
inform discussions on the new

Page 26

ACTION LEAD (L)
AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
10-year Argyll and Bute
Outcomes Improvement Plan. 
COMM3 - Monitor the delivery of
actions in the Climate Change
Action Plan and review in 2024
(L) Climate
Change Board 
Review of this
plan by
December 2024 
Monitored through Tracker to
be submitted quarterly to
Policy & Resources Committee. 
Completed – next review Dec
2024