ARGYLL AND BUTE COUNCIL     POLICY & RESOURCES COMMITTEE
CLIMATE CHANGE BOARD       12TH October 2023 
CLIMATE CHANGE BOARD UPDATE AND DE-CARBONISATION TRACKER 
1.0 EXECUTIVE SUMMARY 
1.1  Argyll and Bute Council has been addressing climate change themes for
over 7 years through its well established Climate Change Board. There
has been a notable reduction in the overall carbon emissions generated
by the Council since annual reporting commenced in 2015/16 - net
reduction of 28.4% - through its Decarbonisation Plan. Whilst our region
is well placed in terms of natural assets and relative low number of
carbon emitting sources, a great deal of work still needs to be done to
achieve Net Zero obligations by 2030 and 2045,  in addition to increasing
resilience to more severe weather events and sea level rises in coming
years. 
1.2  The purpose of this report is to summarise and highlight some of the main  
activities of the Climate Change Board over the previous quarter. 
2.0 RECOMMENDATIONS 
2.1  The Policy and Resources Committee are asked to note and consider
the updates contained at Section 5 of the report and the full
Decarbonisation Tracker update attached at Appendix A.

Page 2

ARGYLL AND BUTE COUNCIL  POLICY & RESOURCES COMMITTEE 
CLIMATE CHANGE BOARD    12TH October 2023 
CLIMATE CHANGE BOARD UPDATE AND DE-CARBONISATION TRACKER 
3.0 INTRODUCTION 
3.1  This report highlights recent activity of the Climate Change Board. 
4.0 RECOMMENDATIONS
4.1  The Policy and Resources Committee are asked to note and consider the 
updates contained at Section 5 of the report and the full Decarbonisation Tracker 
update contained within Appendix A.   
5.0 SUMMARY UPDATES OF CLIMATE CHANGE BOARD 
A – Argyll & Bute Council’s Net Zero Routemap 
5.1  Progress continues towards securing a consultant to undertake the development
of the Council’s Net Zero Routemap. The planned Net Zero Routemap will
supplant the Council’s current Decarbonisation Plan which runs to 2025.
5.2  Council Officers continue to engage with Hub North Scotland to identify and
engage suitable consultants. A productive meeting was held with a consultancy
in July. Discussions between Council Officers, Hub North Scotland and the
consultancy are continuing. 
B – Update on Local Heat and Energy Efficiency Strategy (LHEES)
5.3  The Local Heat and Energy Efficiency Strategies (Scotland) Order 2022 came
into force on 21st May 2022 and sets a legal requirement for local authorities
to produce and publish a Local Heat and Energy Efficiency Strategy (LHEES)
and a Delivery Plan by 31st December 2023.

Page 3

5.4  The LHEES aims to set out a long-term plan to improve buildings’ energy
efficiency and decarbonise the heat source in domestic and non-domestic
buildings within an entire local authority area. The process of LHEES
production is highly technical. It involves the analysis of heat consumption
data across a whole Local Authority geographical area, and the identification
of opportunities to reduce that heat consumption through improvements to
building fabric, or improvements in the efficiency of heating systems,
particularly the utilisation of established heat networks and waste heat.
5.5  The Scottish Government has provided resources to deliver this work. We
have employed an LHEES officer, and engaged consultants through Hub
North Scotland to assist with the highly technical data analysis and mapping
that will be required.
5.6  There has been some delay in the production of the LHEES due to the
scarcity of consultancy support available when all Local Authorities are
requiring the same work at the same time.  It is currently planned to deliver
the LHEES by March 2024 and Scottish Government has been made aware
of this timetable. Officers will continue to update the Council of progress
through the Climate Change Board reporting route. 
C – Update on Energy Efficient Scotland: Area Based Scheme (EES:ABS)
5.7  To the end of the Project Year in June 2023, the Energy Efficient Scotland: Area
Based Scheme spent all of its 2022/23 allocation of £2,011,323 plus an additional
£300,000 which was applied for by the Council and awarded by the Scottish
Government to meet the demands of an increased number of applications.   
5.8 281 homes have been insulated in all areas of Argyll and Bute, contributing to a
reduction in harmful carbon emissions and in turn reducing fuel costs for
householders. The programme covers the entire Argyll and Bute area with
geography being no barrier to eligibility for the scheme.  
5.9  In addition, a joint project between Argyll & Bute Council and Argyll Community
Housing Association embarked on a programme of insulation works on mixed
tenure properties in Tarbert, Bute and Cowal, utilising Scottish Government
funded grants of £722,000, with applications pending to continue this joint project.   
5.10 The Scheme continues to successfully deliver insulation measures throughout
Argyll & Bute in accordance with the Scottish Governments “Fabric First” principle
and had been awarded £1,979,827 to continue the Scheme in 2023/24.
5.11 The Energy Efficiency Team consists of a Project Officer and a Project
Administrator. 
D – Update on Kilmory Solar PV Ground Array System

Page 4

5.12 The 50kW Solar PV ground array system is now on line and generating at Kilmory 
Castle with the formal handover ceremony having taken place on Monday 11th 
September.
5.13 A time-lapse camera has recorded the entire project from inception to finish. Aerial 
drone footage has also been organised, and will be shared with the Council once 
finalised. 
E – Update on Communications Team
5.14 The Council’s Communications Team continues to externally promote the
Council’s climate actions, and actions that others can take, to develop the ‘Climate
Friendly Argyll and Bute’ branding.
5.15 The Communications Team has ran a series of posts encouraging people to
adopt small changes called the ‘Green Summer’ campaign. This included
promoting school uniform recycling scheme, plastic free picnics, International
Plastic Free Bag Day, Shop Local, Reduce fast fashion, active travel maps,
National Marine Week and World Conservation Day. 
F – Update on Argyll and the Isles Coast & Countryside Trust (ACT)
5.16 ACT are working in partnership with Argyll and Bute Community Planning
Partnership on the recruitment of a new Climate Change Action Project Manager.
This new role will be hosted by ACT, with the postholder responsible for leading
on delivery of a new regional Argyll and Bute Climate Action Plan. The post was
advertised over the summer, with interviews scheduled for September 2023.
5.17 Additionally, ACT is working with partners to submit a proposal to the Scottish
Government to host a new Argyll Climate Action Hub. 
G – Decarbonisation Tracker
5.18 The Council’s Decarbonisation Plan sets a 3 year framework to continue our
climate journey and routemap to net zero. Our Council has made a clear
commitment to be a net zero organisation by 2045 and has also declared a
climate emergency befitting the importance and critical nature of the topic. Whilst
the main Decarbonisation Plan will be fixed for 3 years, the associated Action Plan
(which forms an Appendix of the document) will be continuously updated and
reported to both the Climate Change Board and Policy & Resources Committee.
The latest update can be found at Appendix A.
5.19 The Decarbonisation Action Plan Tracker is shared publicly on the Council’s
Climate Change webpages. 
6.0  CONCLUSION

Page 5

6.1  This report provides various updates in relation to the Council’s activities in
relation to Climate Change. 
7.0 IMPLICATIONS
7.1 Policy –  Meeting obligations and commitment to Climate Change.
7.2 Financial –  No direct linkage in this paper.
7.3  Legal –  Meeting requirements of the Climate Change (Scotland) Act 
2009, and the Climate Change (Emissions Reduction Targets)     
(Scotland) Act 2019.
7.4  HR -   None
7.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics - None 
6.5.2   Socio-economic Duty - None 
6.5.3  Islands - None
6.6 Climate Change – Direct link updating activities of the Climate Change Board
and projects that will address climate change. 
6.7 Risk - Not addressing impacts or causes of climate change can lead to
increased cost or censure if targets are not met.
6.8  Customer Service - None 
Douglas Hendry, Executive Director with responsibility for Commercial Services

Page 6

Councillor Ross Moreland – Policy Lead Climate Change & Environment 
12 September 2023                                                  
For further information contact:
Ross McLaughlin
Head of Commercial Services
The Helensburgh and Lomond Civic Centre
ross.mclaughlin@argyll-bute.gov.uk 
APPENDICES
Appendix A – Decarbonisation Tracker – October 2023

Page 7

Appendix A – Climate Change Tracker
ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
W1 –Develop and Implement Waste
Strategy 
(L) Roads and
Amenity Services,
Community,
commercial
customers
Implementation of
the Waste Strategy
transitioning to
Landfill ban
compliant Residual
Waste Recovery
solutions by 2025.
External funding and support being
sought from the Scottish Government
An update report was submitted to
ED&I committee in June and
subsequently a meeting was
arranged with the SG Minister to
discuss the derogation following the
options appraisal. SG Officers will
meet with Council Officers in August
to have further discussion as to
whether the derogation would be
accepted as it would require a
change of law. Liaison with Renewi
continues with regard to landfill ban
compliance should a derogation
authorised by the SG.
W2 – Promote the Waste Hierarchy
through community Education 
(L) Roads and
Amenity Services
Evidence of
community
Education
Not secured New Web content and Education
materials for Primary and Secondary
Schools were developed and
delivered to online Education
Environment Summit October 21 and
the COP 26 Event on the 6th
November 21. 
W3 – Reduce Council use of disposable
and single use plastics across all
departments and settings 
(L) Procurement
and Commercial
Services, all
Council Services 
Adoption of new
working practices
and procurement
No specific funding in place, research
required to impact on operation
costs 
A report on Single Use Plastic went to
the Policy and Resources Committee
on 9 December 2021, and the
following recommendations were
approved:
 Note and consider that the
various Services that
currently purchase SUP

Page 8

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
products consider whether
these products are essential
or if there is a potential
alternative that would meet
the Service requirements,
prior to orders being placed
via PECOS or contacting the
Procurement, Commercial
and Contract Management
Team (PCCMT) for a
procurement process to be
carried out.
 Note and consider that the
Sustainable Procurement
Policy will be updated to
reflect the Climate Change
Board desire to limit SUP
where possible –wording
has been included in the
Annual Review 2023/2024
version of the Procurement
Strategy 2022/2025 as
follows: “To provide
procurement support to any
strategic decisions taken by
the Council in relation to the
usage of Single Use Plastic
products and their
recyclability.” 
 Note and consider that the
Commodity Sourcing
Strategy templates used for
Regulated Procurements
have been updated to

Page 9

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
include a question regarding
SUP.
Changes in legislation were brought
into force by the Scottish
Government on the 1st June 2022
restricting single-use plastic cutlery,
plates, straws, drink stirrers and
balloon sticks, expanded polystyrene
food containers and expanded
polystyrene cups and other beverage
containers, as well as all products
made of oxo-degradable plastic.  
Some products already changed and
others under review. 
W4 – Extend and explore pre-ordering for
school food to reduce food waste 
(L) Commercial
Services and 
Education 
Evidence of
extension of pre-
ordering & food
waste reduction
Project funded and solution procured Project Team currently implementing
this, remaining sites due for
implementation August 2023.
E1 – Deliver Renewable Sourcing Strategy
2
(L) Commercial
Services 
Adoption of
Strategy
RSS2 consultancy work funding to be
confirmed; expectation is that project
implementation will be through
combinations of prudential
borrowing (subject to business case
approvals) and/or external funding. 
RSS2 next stage development work
includes specification development
and preparation of invitation to
tender for specialist consultancy
support. Current work in progress;
intended to be market tested
during 2023.
E2 – Delivery of Non-domestic Energy
Efficiency Framework (NDEEF) Projects 
(L) Commercial
Services 
Evidence of delivery
of projects
Project development work is funded
by combinations of the Scottish
Government and the procured
provider (costs absorbed within the
tender process). 
Funding for project implementation
will come from Council approved
capital allocations:
Non Domestic Energy Efficiency Fund
(NDEEF1) Energy Performance
Contract was signed on 16 July 2021
(circa £1.25m investment with 10
year payback). The originally
intended mini project list has been
fully delivered. Following on from the
P&R Committee report in May 2023:
May PR - Climate Change -NDEEF

Page 10

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
 Climate Change 20/21 -
£500K
 Climate Change 21/22 -
£600K
 Asset Sustainability –  £175K
Progress update.pdf (argyll-
bute.gov.uk), four final mini projects,
which were added as contract
variations, remained to be
implemented. Tarbert School LED
lighting was installed in the 2023
school summer recess; Kilmory
Nursery solar pv is underway and
scheduled to be complete in
September 2023; the intended low
carbon heating solution and pv
installation at Cardross PS have been
intentionally delayed whilst we try to
access a recently launched funding
scheme: Phase 3c Public Sector
Decarbonisation Scheme | Salix
Finance. 
In addition to the above, the
procurement sourcing strategy for
the next batch of sites, using
designation NDEEF2, is under way.
E3 – Delivery of additional solar
installations at Council assets 
(L) Commercial
Services 
Evidence of delivery
of projects
Consultancy work funding to be
confirmed; expectation is that project
implementation will be through
combinations of prudential
borrowing (subject to business case
approvals) and/or external funding.
Best solar pv opportunities are being
delivered within NDEEF (Ref item E2)
and advantage is also being taken to
install solar pv solutions within the
asset sustainability capital
programme where possible  e.g. as a
component of roof upgrades.
The potential for a large solar pv
ground array at the Kilmory Estate is
currently being limited due to electric
grid constraints – engagement with

Page 11

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
SSEN is ongoing to try to identify
solutions. 
E4 – Delivery of Water Efficiency Audits
across our Estate 
(L) Commercial
Services 
Evidence of delivery
of projects
Works items are generally small scale
and are being funded through
existing approved budgets where
possible; otherwise costs will be met
from savings generated.
Significant Council wide asset
verification exercise and ensuring
water use minimised. 
The asset verification element of this
project is substantially complete and
substantial savings have been
identified and recovered. A case
study is being prepared to
demonstrate the range of tasks
undertaken and to convey the scale
of savings made and refunds
received. The final stage of work
involves an exercise to reduce water
consumption (with carbon emissions
reduction) over a number of sites and
is underway.
E5– Delivery of Energy Efficiency Scotland
Programme 
(L) Housing
Services,
Registered Social
Landlords 
Evidence of delivery
of projects
Funding amounts are determined by
localised factors and is paid as a 
proportion of the Scottish
Governments’ Heat In Buildings
Strategy 
To the end of the Project Year in June
2023, the Scheme spent all of its
2022/23 allocation of £2,011,323
plus an additional £300,000 which
was applied for by the Council and
awarded by the Scottish Government
to meet the demands of an increased
number of applications.   281 homes
were insulated in all areas of Argyll
and Bute, contributing to a reduction
in harmful carbon emissions and in
turn reducing fuel costs for
householders.   In addition, a joint
project between Argyll & Bute
Council and Argyll Community

Page 12

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Housing Association embarked on a
programme of insulation works on
mixed tenure properties in Tarbert,
Bute and Cowal, utilising Scottish
Government funded grants of
£722,000, with applications pending
to continue this joint project.   The
Scheme continues to successfully
deliver insulation measures
throughout Argyll & Bute in
accordance with the Scottish
Governments “Fabric First” principle
and had been awarded £1,979,827 to
continue the Scheme in 2023/24. 
E6 – Complete LED streetlight
replacement programme 
(L) Roads and
Infrastructure
Services
Evidence of delivery
of projects
Fully funded through prudential
borrowing
Contractors have now commenced
works  in the Lorn Area to progress
the last installation phase of the
project and have a programme of
approx. 4-6 weeks to install 1100 new
LED luminaires. 860 have now been
installed and delivery of some
additional luminaires is awaited
before contractor completes in the
Lorn area.  All works in the Oban area
should be complete by the end of
May 2023.The Council has 14442
streetlights in total so carbon
emissions have already been greatly
reduced by the LED Upgrade Project.
2021/22 figures were CO2 totals 738
tonnes, this has been reducing year
on year, back in 2015/16 figures were
CO2 Totals 3140 tonnes.

Page 13

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
2022/23 emissions are forecast to be
reduced by approx. 10 – 15% on the
2021/22 figures. 
E7 – Continue support of ABRA and
review Renewable Energy Strategy
annually 
(L) Economic
Development
Evidence of delivery
of projects 
Officer resource to support currently
funded
Work to support ABRA ongoing.  A
meeting was held in May 23 and
focused on the Cruachan expansion
and Machair offshore wind projects. 
Current ongoing project by SSE
Networks for renewal of powerlines
between Inveraray and Crossaig as
well as more minor works. 
Work ongoing on outline business
case for Islay Energy System work
through the Rural Growth Deal.  Islay
is one of the Carbon Neutral Islands
being progressed by the Scottish
Government, work is ongoing.
E8 – Continue support for offshore
development of renewables 
(L) Economic
Development
Evidence of delivery
of projects
(expected late
2020s/early 2030s)
Officer resource to support currently
funded
Scottish Power Renewables are
progressing the Islay site (Machair
Wind) project , expected to seek
consent during the mid2020s. ABC
and HIE supported supply chain
development events in relation to the
project during June. 
The Crown Estate Scotland
Innovation and Targeted Oil and Gas
(INTOG) leasing has identified a site
off Islay for a 100MW innovation
project.
T1 – Develop a Fleet Replacement
Strategy supportive of fuel efficient,
electric and hybrid vehicles 
(L) Roads and
Infrastructure
Services
Adoption of
Strategy
Part for current financial year The Fleet Replacement Strategy is
complete but is subject to on-going
change in line with legislative
changes as it is an operational
document.

Page 14

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
T2 – Develop a vehicle routing system
that will reduce road miles for operations 
(L) Roads and
Infrastructure
Services
Evidence of delivery
of projects
Part for current financial year  A progress update on the route
optimisation project went to the
Environment, Development and
Infrastructure committee in June and
is available here: https://www.argyll-
bute.gov.uk/moderngov/documents/
s195722/ROUTE%20OPTIMISATION%
20UPDATE.pdf 
The main headlines are that a
contract has been awarded and a
project plan is in place which we are
working through, We are at the key
stage now of checking the
information uploaded into the
system on existing routes to ensure
the foundation data is solid before
we look to model new options from
there. The data requires some
manual manipulation to pick up on
local nuances like road end
collections but largely checks out.
We are now moving to looking at
different routing options available
through the system – the project
plan is still on track to have option
available to consider by the end of
the year. In advance of this we’ll look
to arrange a member seminar to
demonstrate the system. 
T3 – Develop an electric vehicle
infrastructure strategy 
(L) Roads and
Infrastructure
Services
Evidence of delivery
of projects 
Part for current financial year  Work on the strategy document is
now effectively complete and we
have a long list of sites which will be

Page 15

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
The development of the EV network
is funded by external grant monies
from Transport Scotland, and the
costs of developing the strategy in
terms of staff time are covered via
existing budgets
Ultimately the cost recovery model 
recommended to Committee for
formal adoption as well as ancillary
parts of the strategy around
maintenance, procurement etc. A
comprehensive year-end report will
go to EDI in December summarising
the current position. The next key
stage is securing enough external
funding and/or agreeing a delivery
model – self delivery supported by
business case, concession model or
leasing sites, or a mixture of the
three. A high level analysis of possible
delivery options will also be
contained in the year end report. 
T4 – Support Digital by Default theme
Service Review & Recovery Plan to reduce
need to travel
All Council
Departments
Evidence of delivery
of projects
Part for current financial year Council is adopting ‘Our Modern
Workspace’ programme and  Digital
First approach as services change and
evolve post pandemic.  
T5 – Develop new active travel plans for
Council buildings and our towns 
(L) Economic
Development
Evidence of delivery
of projects
No active travel funding is provided
by Council.   
External competitive challenge funds
are time consuming to secure and
projects have to be shaped to fit with
external funders’ aspirations and
requirements by the 1.7FTE Active
Travel staff in the Strategic
Transportation Team. However, at
present these are the only available
source(s) of potential funding to
deliver active travel improvements. 
2022/23 Progress
The purpose of active travel is to
make it as easy as possible and help
to encourage individuals, businesses
and visitors to choose to walk, wheel
or cycle for local journeys.  Increasing
activity and reducing sedentary
behaviour has significant health
benefits and can increase accessibility
to essential services, education,
employment, retail and
leisure.  Walking and cycling are
lower cost travel modes and, if they
are a viable option, can help
households reduce their reliance on

Page 16

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
The 1.7FTE Active Travel Team
secured £3.03M external challenge
funding in 22/23 for development
and delivery of 32 active travel
projects across Argyll and Bute,
requiring 22 separate competitive
challenge funding applications to 8
separate funds. 
Projects funded via the active travel
team within Strategic Transportation
in 2022/23 included:
 First two sections of high-quality
segregated cycleway in Argyll and
Bute constructed at Helensburgh
Waterfront and Ralston Road,
Campbeltown in 2022/23.
 Significant upgrade to path
network in Castle Gardens,
Dunoon.
 New cycle and scooter storage and
access at Castlehill School,
Campbeltown.
 New cycle parking at the
community owned Port Ellen
Playing Fields Community
Development, Islay.
 Funded Cycling UK to run the
Dunoon Cycle Bothy
 Funded ACT to upcycle 65 bikes to
return to the local Mid-Argyll
Community and to assist children
private cars, particularly multiple car
households.
No Council funding is currently
expended on Active Travel work, with
all costs, including internal staff costs
(1.7FTE), having to be funded via
successfully securing external
challenge funds. As all active travel
work is currently reliant on securing
external funding, therefore the
projects which are progressed are
those which can successfully secure
external challenge funding. 
Argyll and Bute Active Travel Strategy:
Officers are working to develop an
Argyll and Bute Active Travel Strategy
and present it for Council by summer
2024.  The Active Travel Strategy
would provide the overarching
context for the Council to support
and promote active travel across the
Council area. Having an adopted and
current Active Travel Strategy is
increasingly becoming a pre-
requirement to access Scottish
Government derived active travel
funding. 
Active Travel Delivery Plan:
Following approval of Active Travel
Strategy, an Active Travel Delivery
Plan will be developed to create a

Page 17

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
of refugees in Oban to have
opportunity to cycle.
 Funded ACT to deliver Carbon
Literacy training to over 30 people.
 Creation of new Smartphone Apps
for Tobermory and Bowmore
(adding to the existing popular
apps for Campbeltown, Dunoon,
Helensburgh, Oban and Rothesay)
 Printed Active Travel Map
Helensburgh
 Design work progressed for
ambitious walking and cycling
projects including:
- Dunoon, Town Centre to Hunters
Quay Active Travel route.
- Helensburgh: Helensburgh –
Cardross – Dumbarton Cyclepath
and Helensburgh – Garelochhead
Cycleway.
- Islay, Bowmore to Bridgend Path
(with Islay Community Access
Group).
- Jura, Craighouse to Corran Sands
Active Travel Improvements.
- Lochgilphead: Front Green to
Crinan Canal and Town Centre to
Joint Campus Active Travel
Routes.
- Rothesay, Town Centre to Joint
Campus Active Travel
Improvements.
- Oban, Oban to Ganavan Sands
Active Travel Improvements and
prioritised list of active travel projects
for the whole of Argyll and Bute. 
Active Travel Projects: The majority of
external funding available is provided
by the Scottish Government via a
number of third sector organisations
who are paid to administer these
funds.  The focus for Scottish
Government Active Travel funding is
to develop and deliver infrastructure
projects and associated behaviour
change.  As such, the focus for the
very limited staff capacity in the
Active Travel Team has been to
develop and deliver infrastructure
projects across Argyll and Bute with a
focus on our main towns and
locations with strong community
support. 
Active Travel Plans for Towns: There
are Active Travel Plans in place for
the main towns in Argyll and Bute,
albeit some are now quite
historic.  The town Active Travel Plans
focus on identifying potential active
travel route networks for key
towns.  These provide a framework
for the development of new active
travel routes, which will enable and
encourage residents, businesses and
visitors to choose to travel more
actively.  No funding is currently

Page 18

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Community engagement to
identify desire for future active
travel improvements in Oban.
secured to enable the Active Travel
Plans for towns to be updated. 
Council Staff Travel Plan: At present it
is not proposed to progress with
development of a Council Staff Travel
Plan.  This is due to (a) requirement
to make best use of limited internal
staff capacity; and, (b) the ongoing
uncertainty of longer-term staff
profiles and bases.  Staff Travel Plans
focus on measures to make it easier
and preferable for staff to choose to
walk, cycle, use public transport or
car share to commute to work or for
work journeys, or use economical
pool vehicles for work journeys.   A
travel plan should encourage staff to
choose the most economical and
least environmentally damaging
travel mode.  Engagement will be
required with services which manage
staff in buildings and/or council
buildings as this is essential to
creating deliverable and effective
travel plans for staff.  This includes
Estates, HR, SMT and building
users.  It is recommended that work
on the Council Staff Travel Plan is
commenced after a decision has
been made on future staff working
patterns and office rationalisation as
these will have a significant impact on
the Council Staff and their

Page 19

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
travel.  There is currently no funding
secured to enable this work to be
progressed.   
PA1 – Review Council Flooding & Coastal
Protection Policy 
(L) Roads and
Infrastructure
Services
Review of policy No specific funding in place, research
required to impact on operation
costs
Reviews are in process. 
PA2 – Review Council Sustainable
Procurement Policy 
(L) Procurement  Review of policy  No specific funding in place, research
required to impact on operation
costs
This policy is reviewed on an annual
basis. 
OFF1 – Develop opportunities for Carbon
Offsetting with ACT and partners 
(L) Climate
Change Board,
ACT and partners
Delivery of projects  Limited funding via ACT for existing
projects
SSEN compensatory planting – Phase
1 and 2 complete at Kilmory with
additional planting of a new
community woodland to take place
Dunbeg. 
ACT are currently undertaking
habitat surveys in the Glenan Wood
area in Cowal for a biodiversity net
gain project supported by SSEN.  This
project would see 50 hectares of
Rainforest cleared of invasive
rhododendrons. Funding for full
delivery tbc.   
ACT have entered agreement with
Mastercard’s Priceless Planet
Coalition to plant 100,000 native
trees in Argyll. over the coming 5
years.  Sites are confirmed and legal
agreements being finalised. This
planting will offer opportunities for
carbon credits for landowners.

Page 20

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
ACT are working in partnership with
the Community Planning Partnership
and will be hosting a Climate Change
Officer.  Post has been advertised
and interviews will take place in
September ’23.  
Also working with partners to submit
a proposal to host an Argyll Climate
Action Hub (SSCAN ScotGov project). 
ACT undertaking peatland
restoration on Islay, Jura and
extending into mainland Argyll,
supported by ScotGov’s Peatland
Action and Esmee Fairbairn
Foundation.  In addition to the 2 Islay
based jobs, we will be offering a 1-
year trainee position in 2024. 
Carbon Literacy Training – ACTNow
continuing to offer this service.  A
number of Councillors have indicated
that they would like to undertake the
training – funding tbc.  A&BC Climate
Change Officer working with ACT and
Climate Change Board to discuss
progressing towards being a Silver
Accredited Carbon Literate
Organisation. 
ACT delivering Bikes Back to the
Community with the support of

Page 21

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Smarter Choices, Smarter Places
funding.  
ACT has two electric bikes available
for groups and businesses and
Councillors/Council officers to trial. 
ACT has applied to Nature
Restoration Fund which if awarded
would achieve landscape scale
rhododendron clearance in Knapdale. 
Outcome of bid due end Sept ‘23. 
ACT has led a bid on behalf of
Alliance for Scotland’s Rainforest to
the Facility for Investment Ready
Nature in Scotland – to facilitate
private finance investment into
habitat restoration.  Outcome due
September ’23. 
ACT has submitted Expression of
Interest for asset transfer or lease of
land adjacent to Kilmory Castle to
establish a Woodland Enterprise Hub. 
With A&BC for consideration. 
ACT working with DRAX to develop
STEM subjects outdoor learning
programme.  Also working with new
groups at MAKI Pups nursery site to
encourage new groups to enjoy
outdoor activities and learning.

Page 22

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
COMM1- Develop and deliver
Communications Plan to support
Decarbonisation Plan 
(L) Climate Change
Board and
Communications
Team
Delivery of
Communications
Plan
Part of Communications Support  External communications
We continue to promote actions the
council is taking, and actions that
others can take, to develop climate-
friendly Argyll and Bute. For example:
 Promoting easier recycling
on Coll and Tiree
 HMPA SG consultation
response 
 Council calls for ban on
single use disposable vapes
 Council and ATC nomination
for Planning Awards for
Argyll rainforest project
 Council achieves bronze
carbon literate award
 Council calls for clarity on
deposit return scheme 
 Promotion of home
efficiency projects –
insulated over 160
households to date
 Landfill ban – request
meeting with SG Minister
 Food waste service
campaign to encourage
more Helensburgh and
Lomond residents to use
their caddies – ‘Bucket Load
of Good’
 Promotion of ongoing
Campbeltown Flood
Prevention Scheme
 Free active travel apps

Page 23

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
 Hermitage Park green flag
status
 Funding for additional EV
charging points
 Increased funding
announcement for Energy
Efficiency Scheme 
 Green Summer campaign –
series of posts encouraging
people to adopt small
changes 
- School uniform recycling
scheme
- Plastic free picnics
- International plastic
free bag day
- Shop Local
- Reduce fast fashion
- Active travel maps
- National Marine Week
- World Conservation Day
 New Campbeltown cycle
path
 Dunoon active travel route
consultation
 Helensburgh active travel
route consultation 
 Supporting Communities
Fund.
 Highlighted Corporate Plan
including climate action
 Built environment Planning
Awards

Page 24

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
COMM2 - Engage with community and
partners and deliver Climate Change
Directory for our region 
(L) Community
Planning and
Development
Team
Delivery of
engagement map 
In place until end of financial year The CPP Climate Change signposting
page is  live 
https://www.argyll-bute.gov.uk/cpp-
climate-change   with further entries
added as they are received. 
The dedicated Climate Change
funding opportunities search,
available through the signposting
page, is conducted and an updated
document produced on a regular
basis. 
The Community Planning team
established the CPP Climate Change
Working Group which has developed
a collaborative funding package and
work to deliver a Climate Change
Plan for the area. (see update on ACT
and partners within this report)
COMM3 - Monitor the delivery of actions
in the Climate Change Action Plan and
review in 2024
(L) Climate Change
Board 
Review of this plan
by December 2024 
Monitored through Tracker to be
submitted quarterly to Policy &
Resources Committee. 
Completed – next review Dec 2024