Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
AREA  PROJECT/
TIMESCALE FOR
COMPLETION  
RESPONSIBLE
SERVICE
CROWN 
ESTATE FUNDING
ALLOCATION 
FINANCIAL YEAR  STATUS  PROGRESS UPDATE –
NOVEMBER 2022 – AUGUST
2023  
B&C  Dunoon
Community STEM
Hub 
Indicative
timescale is the
end of March
2024 (all funding
will be spent).    
DEG  £250,000 
This is a Rural Growth Deal
project and this funding is
part of a total funding
package of £1.75 million.    
£100,000 – 20/21 
£150,000 – 21/22 
Ongoing  Project progress is as follows: 
 Procurement ITT Stage 1
complete (selection of
appropriate construction
companies to undertake the
works). 
 Procurement ITT Stage 2
(quality and price) issued with
tender returns due early October.    
 On conclusion of the
procurement process the
affordability of repurposing the
Hill Street building to a
Community STEM Hub will be
known. 
 Alternative options
discussed at a workshop
facilitated by Hub North on 26th
June 2023. Lead architects for
the external Design Team
currently looking at the viability of
some of the options proposed if
Hill Street is unaffordable.   
B&C  Dunoon Active
Travel Hub 
DEG  £394,000 (additional £40k
was reallocated from Bute
and Cowal Climate Change
Satellite Pods 
£249,000 – 20/21 
£145,000 – 21/22 
Ongoing  Phase 1 works – exterior tiling
and painting needs to be
undertaken in order to complete
the project. This will be

Page 2

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
NEARING
COMPLETION  
as per P&R report
16/06/22. 
This funding is part of a
funding wider package. 
undertaken in September when
the Phase 2 contractor is off
site.    
Landscaping works – the works
are almost complete. We have
cobbled the entrance to the gate
lodge, built the retaining wall and
completed drainage works.
Tarmacing the road is falling to
the Roads and Amenity team
which will be undertaken in
September. Site works will be
inspected Friday 25th August with
a view to signing off on
completion. 
Phase 2 works – the water
connection is being installed at
present. Electric installation is
complete. The interior walls and
floors have been completed. Final
fixings and fixtures will be
installed with an early October
2023 completion date.   
B&C     Bute Bike
Handover Station 
PROJECT
COMPLETE  
DEG  £10,000  20/21  Complete 1. Allocation drawn down with an
underspend of £219.39. 
B&C  Rothesay
Pontoons 
PROJECT
COMPLETE  
R&I  £293,441 
This funding is part of a
funding wider package.
£191,000 – 20/21 
£102,441 – 21/22 
Complete Previous update states all spent
& project closed. The date of
Completion of the whole of the
works is 19th January 2023. Total
Cost of the Works: £865,381.60

Page 3

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
£151,000 was also
allocated from
19/20. 
B&C  Rothesay Kiddies
Corner 
R&I  £44,000     
Re-allocation of funding
source to Crown Estate.
Moved to CE from PBI. 
21/22  Ongoing Due to legal issues, this has
proven to be a more difficult
process than first anticipated. 
These issues have now been
worked through and final
amendments are being made to
the grant contract and licence to
occupy with the aim to issue
shortly.
B&C  Glenmorag
campervan site 
DEG  £100,000 
P&R 16 February 2023
(Para 3.b) - agreed to
switch allocation of £100k
to £100k CE funding
allocation). Moved to CE
table. 
21/22  Ongoing Tender has been issued and
officers await returns. 
MAKI  Ardrishaig Public
Realm
Improvements 
PROJECT
COMPLETE  
DEG  £250,000 
This funding is part of a
funding wider package.
£50,000 – 20/21 
£200,000 – 21/22 
Complete  Works completed in April 2023
and the project was officially
opened on 19 August 2023
during the community organised
Ardrishaig Gala. The defects
period will run until April 2024. 
MAKI  Tarbert Public
Realm
Improvements 
March 2024 
DEG  £200,000  £4,000 – 20/21 
£196,000 – 21/22 
Ongoing  Awaiting proposals from Tarbert
harbour Authority who are keen
to progress with a project within
the centre of the village.

Page 4

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
MAKI  Kilmory Industrial
Estate Phase 2  
Subject to
achieving the
necessary
statutory
approvals and
concluding the
various legal
agreements, M&K
McLeod Ltd
(MKML) forecast
that physical
works could
commence
October 2023 and
run through until
November 2024 
Commercial
Services
£150,000 
This funding is part of a
funding wider package. 
21/22  Ongoing   Planning Application
Approved in Feb-23 
 MKML progressing
statutory utility applications for
connections/diversions following
planning approval 
 MKML progressing
statutory approvals from
Transport Scotland and ABC
Roads 
 WoSAS have approved
Written Investigation Statement
for on-site archaeology, which
will commence w/c 7 –Aug-23 
 Legal Agreements
reaching conclusion
MAKI  Argyll and the Isles
Countryside Trust
(ACT) 
Eco Hub 
March 2024  
DEG  £50,000  20/21  Ongoing  The Eco hub is on site.  Retention
of £5k still remains to be drawn
down pending submission of
building warrant and obtaining
completion certificate. 
MAKI Port Ellen Public
Realm
DEG £6,000  21/22  Ongoing Works ongoing, onsite
construction has commenced. 
MAKI  Jura Community
Gigabit
Programme 
DEG  £50,000  21/22  Ongoing  After further discussions with our
Roads Department, it was
established that due to the fragile
nature of the network along the
route from Ardfernal to
Knockrome, a series of poles to

Page 5

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
accommodate the fibre would be
required. This required significant
survey work to be undertaken. 
The application for the installation
of 28 new poles was approved. 
Over 50% of the project is
complete, however Open Reach
have raised concerns that take up
is lower than anticipated, the
financial viability of this project
was subject to residents pledging
their vouchers (85% required)
these vouchers can only be
redeemed once a service has
been received. It is still being
established whether the low take-
up of the new service is down to
affordability or premises being
tied into existing contracts. 
MAKI  War memorial
upgrade,
Campbeltown 
R&I £20,000  22/23  Ongoing   Report received from Craig Frew
Building Conservation which
highlights works required. 
Quotes are currently being
sought to carry out these works,
however, extra funding may be
required to complete these.   
Cleaning works will be
undertaken in
September/October 2023.

Page 6

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
MAKI  Campbeltown
Community Action
Plan 
September 2024 
DEG  £50,000  20/21  Ongoing  Two proposals have been
received. A grant agreement is
being prepared for South Kintyre
Development Trust in relation to a
food growing project. Further
information is awaited from
Campbeltown Community
Council in relation to a proposal
for upgrades to the jubilee/trench
path. 
MAKI  Colonsay Roads 
PROJECT
COMPLETE 
R&I  £200,000  22/23 Complete Works are complete. 
Loop road surface dressed with
overlays and strengthening to
localised areas adjacent to the
ferry port.  
MAKI     Bowmore Hall,
Islay    
Phase 1 – End of
2023
DEG     £225,000  22/23  Ongoing Works are ongoing. The
remaining grant will be drawdown
by the end of 2023. Drawdown
figure to date is £171,775.
MAKI     Jura Passenger
Ferry
Infrastructure 
R&I  £100,000  22/23 Ongoing Background: 
This to provide safe foot
passenger access to any smaller
vessel brought in to cover for
repair or breakdown of the main
Jura Ferry. Presently having to
use a vertical ladder for access. 
Survey work completed and
tender is being prepared for a
design / build or premade
pontoon structure with gangway.

Page 7

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
MAKI     Kilmartin Overflow
Carpark 
DEG  £50,000  22/23  Ongoing Draft contract to be
issued.  Awaiting confirmation of
funding package and planning
permission outcome.  Planning
permission withdrawn due to
access concerns.  Discussions
ongoing regarding resubmission. 
OLI  Tobermory
Cemetery 
PROJECT
COMPLETE
R&I £400,000  21/22 Complete P&R 16 February 2023 (Para
3.1.b) - agreed to use the 400k
allocation for the Tobermory  car
park and staycation facilities to
instead deliver the cemetery
extension at Kilmory. 
The Cemetery extension has now
been completed and we are
finalising the snagging and
payments. This can now be
marked complete. 
OLI  Kerrera Road 
PROJECT
COMPLETE
DEG   £200,000  20/21 Complete   Works are complete. 
OLI    Feasibility study
and specification
work for pier
infrastructure at
Ellenabeich and
Easdale which
would support the
ongoing provision
of the council ferry
service 
R&I   £100,000  22/23 Ongoing   Terms Of Reference produced
and work is being carried out by
Caledonian Economics.

Page 8

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
OLI     Island Airport
Resilience (part of
the unsuccessful
Islands
Infrastructure bid). 
Provision of CCTV
at both Coll and
Colonsay Airport &
Provision of a
small fire training
rig on each island 
March 2024 
DEG   £100,000  22/23 Ongoing On target with spend 
Training rigs and CCTV for
airports – out to tender.
OLI  Tobermory
Harbour Wall and
Railings, Phase 2 
December 2023
R&I £100,000 
This funding is part of a
funding wider package.
22/23  Ongoing Works Ongoing. 
Tender Value – £398,255.10 
Date of Award – 07/03/2023 
Total Payment to Contractor to
date – £174,018.39 
It is proposed to move this
allocation over to Place Based
Investment funding and replace
this with The Rockfield Centre
due to the wider flexibility of
Crown Estate funding.
H&L  Helensburgh 5-7
Clyde Street
Refurbishment 
Timescale for
completion
DEG  £350,000  20/21 Ongoing  Some progress has been made in
securing involvement of ACHA in
developing a permanent solution.
Property also added to Councils
SHIP which will access additional
funding. Final costings being

Page 9

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
cannot yet be
confirmed as
there are still
ongoing issues
to resolved I the
project but likely
to be 2024 
discussed to identify financial
viability of the project and
whether sufficient funding is
available. ACHA have made
application to Scottish
Government for additional grant
funding.  
H&L  Arrochar Car
Parking 
Timescale cannot
be confirmed as
yet, as there is an
issue with land
ownership. 
R&I  £250,000      20/21 Ongoing  Currently confirming land
ownership permission before this
can progress. This is still with
Legal trying to get ownership
transferred to the Council.
H&L     Helensburgh
Masonry Pier      
PROJECT
COMPLETE
Commercial
Services 
£69,224 
This funding is part of a
funding wider package. 
21/22 Complete  Works are complete.
ALL     Charging
Mechanisms in
high footfall public
conveniences. 
TBC
R&I   £200,000  22/23 Ongoing Following confirmation of the
Crown Estate funding of
£200,000 in addition to the
£100,000 council funding the
contract was awarded for all 16
sites.    
Regrettably the contractor has
not been able to mobilise at the
pace we would have liked. We
are continuing to engage with
them to move things along and
expect a programme to be
submitted for approval shortly.

Page 10

Appendix 1 - PROGRESS OF PROJECTS   
TABLE 1 
ALL     Cemetery
maintenance and
roads access fund
to be delegated
£75,000 to each
Area Committee to
agree the best
options for the
Fund. This may
include un-adopted
roads and officers
would need to
seek agreement
from landowners –
this would be a
temporary
diversion of the
Council’s policy to
only upgrade and
maintain adopted
roads until the fund
is fully spent.     
R&I   £300,000  22/23 Ongoing A number of sunken lairs have
been re-levelled with the majority
of the works across the four
administrative areas, as agreed
through Area Committees, on
track to be delivered during the
winter months when the demands
on the grounds team are
reduced. 
Agreement being drawn up for
works to be undertaken in the
winter for Brackley cemetery to
allow improvements to be made
to the access road. 
ALL Contingency DEG £14,441  22/23 Ongoing Agreed at P&R on 13 October
2022 that the unallocated funds
of £75,939 would be used as
contingency.  £61,498 of this has
been reallocated.
ALL Funding for Project
Officers
DEG £101,000  22/23 Ongoing Agreed at P&R on 17 February
2022.  
TOTAL £4,627,106