ARGYLL AND BUTE COUNCIL      POLICY AND RESOURCES
COMMITTEE 
DEVELOPMENT AND 
ECONOMIC GROWTH          12 OCTOBER 2023 
PLACE BASED INVESTMENT PROGRAMME FUND 2021 – 2024 ALLOCATIONS
AND PROJECT UPDATES 
1.0 EXECUTIVE SUMMARY 
1.1 The 2020 Programme for Government committed to establishing a Place
Based Investment Programme (PBIP), linking and aligning place-based
funding initiatives. Scottish Government confirmed that each Local Authority
would be receiving a share of the PBIP funding over a 5 year period, starting
in 2021/22, to support and advance place-based investment and build on the
strong partnership currently existing through the Regeneration Capital Grant
Fund.   
1.2 The purpose of this report is to provide an update to members on the PBIP
allocation for the years 2021/22, 2022/23 and 2023/24 as well as the
allocations agreed to individual projects and any subsequent changes made
to allocations and an update on progress for each of the projects. 
1.3 The PBIP allocation to Argyll and Bute Council for 2021/22 was £821,000.
The allocation for 2022/23 was £712,000 and for 2023/24 it was £496,000.
There remains a further two years of funding available based on the 2020
Programme of Government 5 year commitment. 
1.4 The PBIP allocation for each year was split across a number of projects
following agreement from members at the relevant Policy and Resources
Committee meetings. The individual project supported via the PBIP are listed
in Table 1 along with the year awarded and the specific PBIP allocations. The
funding for each year had to be committed by the end (31 March) of the
respective financial year it was awarded and evidenced by, at minimum, a
fully let contract or commencement of works in order to avoid having to return
any unspent funds to Scottish Government. This has meant that the projects
not only have had to have the ability to meet the aims of the fund, but also
add value to existing pieces of work and be time critical.

Page 2

1.5 The PBIP funding can only be used for capital regeneration projects, and
projects must aim to:
 link and align to place-based initiatives, and establish a coherent local
framework to implement the Place Principle; 
 support place policy ambitions, such as town centre revitalisation, community-
led regeneration, 20 minute neighbourhoods and Community Wealth Building;  
 ensure that all place-based investments are shaped by the needs and
aspirations of local communities; and,
 accelerate net zero ambitions, wellbeing and inclusive economic
development, tackling inequality and disadvantage, community involvement
and ownership.
1.6 The fund links closely to the ongoing reprioritisation focus of the Economic
Growth service, and associated Economic Strategy and Economic Recovery
Plan. With its ‘place’ focus, the fund also builds on and adds value to the
previous year’s Town Centre Fund investment, as well as previous
regeneration initiatives taken forward by the Council. 
1.7      As part of the annual reporting requirements to Scottish Government for this
fund, the Council has to advise how the funding has been spent across the
categories.   
RECOMMENDATION 
It is recommended that Policy and Resources Committee: 
a) Note the allocation of PBI funding provided in from the period 2021-2024;
b) Note the agreed allocation of the Place Based Investment funding during the
period 2021-2024 to the projects in Table 1; 
c) Approve any amendments to the funding allocation as detailed in paragraph
4.9; 
d) Note the update on each of the individual projects as detailed in Table 1; and 
e) Agree to a delegation of powers to the Executive Director with responsibility
for Development and Economic Growth to allow any subsequent amendment
to approved PBIP grant allocations to ensure that any risk relating to payback
of any grant is minimised. This may involve swapping PBIP allocations with
Crown Estate (CE) allocation of grants against individual projects but would
not affect the projects but simply the grant source.

Page 3

ARGYLL AND BUTE COUNCIL      POLICY AND RESOURCES
COMMITTEE 
DEVELOPMENT AND 
ECONOMIC GROWTH         12 OCTOBER 2023 
PLACE BASED INVESTMENT PROGRAMME FUND 2021-2024 ALLOCATIONS
AND PROJECT UPDATES 
2.0 INTRODUCTION 
2.1 The Scottish Government committed to provide local authorities with funding
from its Place Based Investment Programme on an annual basis for a period
of 5 financial years. To date the Council has received 3 years of PBIP funding
including funding for 2023/24. Although the annual share for Argyll and Bute
has reduced since the initial allocation of £821,000 in 2021/22 to £496,000 in
2023/24, it has enabled the delivery of a number of key projects either by
providing the main funding source or by providing match funding to unlock
larger projects. 
2.2 The purpose of this report is to provide an update to members on the PBIP
allocation for the years 2021/22, 2022/23 and 2023/24 as well as the
allocations agreed to individual projects and any subsequent change that has
had to be made as well as an update on progress of each project. 
2.3      All of the projects approved for PBIP funding are considered to fit strongly
with the PBI criteria, deliver on the Council’s Economic Recovery Strategy,
are time critical, add value to investment that has already been made by the
Council, deliver on our regeneration outcomes for our places, take account of
available officer resources and take account of the relatively tight timeline that
we need to meet to align with the funding. 
2.4      Once members agree the projects and the allocation in respect of the PBIP,
officers continually monitor the projects to ensure compliance with the criteria
and timeframe in order to avoid having to return any uncommitted funds to
Scottish Government . As members will note from the Table 1 it is proposed to
move the PBIP funding originally set aside against Rockfield and use it for the
Tobermory Harbour Wall and Railings Phase 2 project making their overall
PBIP support £200,000 and taking the £100,000 Crown Estate (CE) allocation
against the Tobermory Harbour Wall and Railings project and instead setting
it against Rockfield. The Tobermory project is on site and will meet the PBIP
timeframe. The CE funding is more flexible in regard to delivery timeframe
and will allow Rockfield more time to progress their project without
jeopardising the grant.

Page 4

3.0 RECOMMENDATIONS 
3.1 It is recommended that Policy and Resources Committee:- 
a) Note the allocation of PBI funding provided in from the period 2021-2024;
b) Note the agreed allocation of the Place Based Investment funding during the
period 2021-2024 to the projects in Table 1; 
c) Approve any amendments to the funding allocation as detailed in paragraph
4.9; 
d) Note the update on each of the individual projects as detailed in Table 1; and 
e) Agree to a delegation of powers to the Executive Director with responsibility
for Development and Economic Growth to allow any subsequent amendment
to approved PBIP grant allocations to ensure that any risk relating to payback
of any grant is minimised. This may involve swapping PBIP allocations with
Crown Estate (CE) allocation of grants against individual projects but would
not affect the projects but simply the grant source. 
4.0 DETAIL 
4.1 The 2020 Programme for Government committed to establishing a Place
Based Investment Programme (PBIP), linking and aligning place-based
funding initiatives. Scottish Government confirmed that Local Government
would be receiving a share of the PBIP funding over a 5 year period to
support and advance place-based investment and build on the strong
partnership currently existing through the Regeneration Capital Grant Fund.   
4.2 Argyll and Bute Council’s allocation for year 1 (2021/22) was £821,000, year 2
(2022/23) it was £714,000 and for this financial year (2023/24) it was
£496,000. There remains 2 years of PBIP funding support to be received
based on the Scottish Government’s initial 5 year commitment but as yet
there is no confirmation of figures for the forthcoming years. 
4.3 The main objectives of the PBIP are:  
 to link and align place-based initiatives, and establish a coherent local
framework to implement the Place Principle; 
 to support place policy ambitions such as town centre revitalisation,
community led regeneration, 20 minute neighbourhoods and Community
Wealth Building; 
 to ensure that all place-based investments are shaped by the needs and
aspirations of local communities; and,
 to accelerate our ambitions for net zero, wellbeing and inclusive economic
development, tackling inequality and disadvantage, community involvement
and ownership. 
4.4 The challenge in respect of the funding has always been to identify projects
that meet the place-based criteria, and are able to be delivered within short

Page 5

timeframes with our limited staff resources. Projects put forward to members
for the last 3 years needed to be delivered often in a short period of time and
therefore need to be sufficiently well advanced in terms of their development,
straightforward to deliver and/or be ready to start on site, or be able to be
delivered by a third party. 
4.5 Under the PBI allocation for 2021/22 the Council supported a total of 8
projects and prior to the commencement of PBIP funding the Council
supported a total of 28 projects under the previous SG Town Centre Funding
stream.  As a number of those projects being supported through the previous
year’s allocation are ongoing, the key issue has and continues to be the
availability of internal resources to develop and deliver new projects. 
4.6 At their respective meetings of 24th June 2021, 12th August 2021, and 2nd
September 2021, Argyll and Bute Council, the Policy and Resources
Committee and Environment, Development and Infrastructure Committee
agreed to use the 2021/22 PBIP towards 8 projects that support a living well
locally concept, have climate friendly ambitions, and which have stemmed
from the community through design-led consultation activity or through needs
identified by key partner organisations.  Table 1 provides an update in respect
of each of these projects.   
4.7       At the meeting of the Policy and Resources Committee on 16th June 2022
members agreed to allocate £389,514 of the PBIP 22/23 funding to 3 initial
projects. The remaining £322,486 was allocated to a further 4 projects via a
delegated authority process agreed at the August 2022 Policy and Resources
Committee meeting.  All 7 projects are listed in Table 1. 
4.8      On 10 August 2023, members of the Policy and Resources Committee
agreed to allocate the PBIP 23/24 to a total of 8 projects. All 8 projects are
listed in Table 1 however as members will appreciate this decision was only
recently taken and therefore the delivery of these projects is still at a very
early stage. 
4.9  As members will note from the Table 1 it is proposed to move the PBIP
funding originally set aside against Rockfield and use it for the Tobermory
Harbour Wall and Railings Phase 2 project making their overall PBIP support
£200,000 and taking the £100,000 Crown Estate (CE) allocation against the
Tobermory Harbour Wall and Railings project and instead setting it against
Rockfield. The Tobermory project is on site and will meet the PBIP timeframe.
The CE funding is more flexible in regard to delivery timeframe and will allow
Rockfield more time to progress their project without jeopardising the grant. 
5.0 CONCLUSION 
5.1 The relatively tight timescales associated with PBIP funds, combined with the
large number of existing projects being delivered by the Council, make for a
challenging place based investment programme. However there is no doubt that
the PBIP funding has enabled more projects to be delivered that build on

Page 6

investment already in place as well as supporting new investment, and that
support community wealth building and wider economic development of the area. 
6.0 IMPLICATIONS 
6.1 Policy – There is a need to comply with the Scottish Government ‘place’ policies
as outlined in the report and associated guidance for the PBIP Fund. 
6.2 Financial – The Scottish Government expect that any uncommitted funds will
be returned to Scottish Government.    
6.3  Legal – None. 
6.4  HR – Resourced from existing staff. 
6.5  Fairer Scotland Duty:
6.5.1   Equalities - protected characteristics – None.
6.5.2   Socio-economic Duty – The Fund supports local economies through place-
based centre regeneration activity.
6.5.3 Islands – The Fund supports island economies through place-based
regeneration activity and has the potential to align with, and add value to, the
Islands Infrastructure Investment Fund. 
6.6 Risk – In order for each project to progress to delivery stage, a fully let contract
or grant contract must be in place by the end of the financial year (31st March)
the grant is awarded in. The projects are continually monitored to ensure that
funds can be swapped out and reallocated to avoid having to return any
uncommitted funds to Scottish Government. 
6.7  Climate Change – None arising directly from this report.   
6.8  Customer Service - None 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Policy Lead for Strategic Development, Councillor Robin Currie 
September 2023                                                 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Audrey Martin Transformational Projects and Regeneration Manager 
APPENDICES 
Appendix 1 – List of Projects

Page 7

APPENDIX 1 – LIST OF PROJECTS 
Table 1 
AREA PROJECT/
TIMESCALE FOR
COMPLETION
RESPONSIBLE
SERVICE
PBI
ALLOCATION
YEAR
OF
AWARD
PROGRESS UPDATE –
AUGUST 2023
ALL A&B Wide
Shopfront Scheme
DEG £80,000 21/22 Works complete.
B&C   Rothesay TH –
Tower Street
DEG £100,000 21/22 Works Ongoing. Due for
completion by the end of
2023.
B&C   Dunoon Cycle
Bothy
DEG £70,000 21/22 PBI funded works
complete. Full project is
due for completion in
October 2023.
B&C   Dunoon Burgh Hall
Café Garden
DEG £50,000 21/22 Works complete. 
H&L   Helensburgh Pier Commercial
Services
£163,000 21/22 Works complete. 
H&L   Hermitage Park –
Bothy
DEG £28,000 21/22 Works complete. 
MAKI Bowmore Public
Realm works
R&I £80,000 21/22 Works complete. 
OLI   Gibraltar Street
Public Realm
DEG £250,000 21/22 RIS looking to start
works on-site 18th
September.  
21/22 Total £821,000   
B&C   Re-instate fountain
on Rothesay
Promenade 
R&I   £15,000  22/23 Works complete. 
H&L  Helensburgh Pier  Commercial
Services
£113,000  22/23 Works complete. 
MAKI  Lochgilphead
CARS Priority
Buildings 
DEG  £200,000  22/23 Works commenced on
site 
The funding has been
awarded to two priority
buildings.  The contracts
were both awarded in
2022-23.  Both projects
are currently on
site.  The entire
£200,000 will be paid out
in 2023-24. 
MAKI  Port Ellen Playing
Fields - RCGF
project 
DEG £44,000  22/23 Works ongoing, onsite
construction has
commenced. 
OLI   Rockfield Outdoor
Centre  
DEG £100,000  22/23 Grant contract issued
and accepted. Awaiting
confirmation from

Page 8

Rockfield on the project
timescales. 
Due to the delays, we
are seeking to swap this
PBI funding with the
Crown Estates funding
allocated to Tobermory
Harbour Wall and
Railings.
OLI  Aros Waterfront
Development 
DEG  £140,000  22/23 Works complete 
OLI  Tobermory
Harbour Wall and
Railings, Phase 2 
R&I  £100,000  22/23 Works Ongoing.
Completion due
December 2023 
Tender Value –
£398,255.10 
Date of Award –
07/03/2023 
Total Payment to
Contractor to date –
£174,018.39 
Date and value of
Invoice 1 – 24/07/2023
(£133,191.07) 
Date and value of
invoice 2 – 28/08/2023
(£40,827.32) 
22/23 Total £712,000   
B&C   Dunoon Burgh Hall
Phase 2
DEG £74,500 23/24 Grant contract currently
being prepared for issue
mid-September 2023.
B&C   Dunoon
CARS/LACER
DEG £49,500 23/24 Grant application
documents currently
being prepared.
H&L   Helensburgh
CARS – Shopfront
Scheme
DEG £44,000 23/24 Grant application
documents currently
being prepared.
H&L   Helensburgh
Skatepark
DEG/
Commercial
Services
£80,000 23/24 Discussions ongoing
regarding site of new
skatepark.
MAKI Lochgilphead
CARS – Shopfront
Scheme
DEG £100,000 23/24 Grant application
documents currently
being prepared.
MAKI Campbeltown –
Steel Beam
Project and
LACER Shopfront
Scheme
DEG £38,000 23/24 Grant application
documents currently
being prepared.

Page 9

OLI  RGD – Tobermory
Worker
Accommodation
DEG £50,000 23/24 Tender documents being
prepared.
OLI  Bid4Oban
Shopfront Scheme
and Signage
DEG £60,000 23/24 Grant contract currently
being prepared for issue
mid-September 2023.  
23/24 Total £496,000